prof. maria cristina tavares b.sc. ricardo borgesieee 2011 electrical power and energy conference...
TRANSCRIPT
IEEE 2011 Electrical Power and Energy Conference
Prof. Maria Cristina Tavares B.Sc. Ricardo Borges
1
BRAZIL
IEEE 2011 Electrical Power and Energy Conference
Introduc)on
2
With the constant increase on Brazilian electric energy consumption, it arises the need for more energy generation
High hydroelectric potencials (more than 100 GW) where identified on the Brazilian North Region
Large hydroelectric complexes will be built in this region
Distances for energy transmission from these generation plants to load centers (South-Southeastern Region and Northeastern Region) are around 2500 km
IEEE 2011 Electrical Power and Energy Conference
IEEE 2011 Electrical Power and Energy Conference
Introduc)on
4
IEEE 2011 Electrical Power and Energy Conference
Introduc)on
5
IEEE 2011 Electrical Power and Energy Conference
Basics Caracteris)cs of a HWL Transmission Line or AC-‐Link
6
Voltage gain at no-load
No need of reactive compensation
Low cost line
IEEE 2011 Electrical Power and Energy Conference
Compara)ve Cost Analysis
7
IEEE 2011 Electrical Power and Energy Conference
Future Largest Hydroelectric Plants
8
27 GW will be installed => 23 hydro plants with capacity > 1 GW
IEEE 2011 Electrical Power and Energy Conference
Voltage along the Line
9
Several power flows
IEEE 2011 Electrical Power and Energy Conference
Test Transmission System
10
To give some support a real test was proposed.
A set of existing 500 kV similar transmission lines was identified, forming a 2600 km test long line.
This test is described and analyzed in a companion paper.
IEEE 2011 Electrical Power and Energy Conference
Line Parameters – 60 Hz
Sequence Resistance (Ω/km)
Inductance (mH/km)
Capacitance (µF/km)
Zero 0.38705 1.31743 3.7779
Positive/Negative 0.00832 0.17442 9.7008
800 kV line
8 conductors/phase
Positive sequence surge impedance 134.2 Ω
Νatural power is 4.8 GW
Line with 2600 km long
IEEE 2011 Electrical Power and Energy Conference
Small Loads Connec)on
As the AC-Link has a high natural power it can stand small power extractions through its length without an important compromise of its operation.
Consumption estimative = 40 MW on a 100,000 inhabitants city.
Studies were carried out for 50 MW block extractions through the line (important amount of power for the region where the line is going to pass).
IEEE 2011 Electrical Power and Energy Conference
Small Loads Connec)on
Line was considered to be in steady-state:
Voltages on sending and receiving ends were maintained within 0.95 pu and 1.05 pu.
Power was injected, with unitary power factor, on the sending end of the line
IEEE 2011 Electrical Power and Energy Conference
Connec)on of Different Loads on Different Points along the Line
Load connected near the sending end
Load connected in the line center (worst case)
IEEE 2011 Electrical Power and Energy Conference
Line TransmiJng Different Amounts of Power
The line is not going operate at full load the whole year
50 MW is an important amount of power for the region where the line is going to cross
Based on that, some cases were simulated with 50 MW drain, with the line transmitting different amounts of power
IEEE 2011 Electrical Power and Energy Conference
Line TransmiJng Different Amounts of Power
Load connected 256 km away from the line sending
end
Load connected 684 km away from the line sending
end
IEEE 2011 Electrical Power and Energy Conference
Load connected 1344 km away from the line sending
end
Load connected 1772 km away from the line sending
end
Line TransmiJng Different Amounts of Power
IEEE 2011 Electrical Power and Energy Conference
Conclusions