progress on petroleum exploration and development in uganda at the oil development, environmental...

26
PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION ON OIL AND GAS (CSCO) STAKEHOLDER CIVIL SOCIETY COALITION ON OIL AND GAS (CSCO) STAKEHOLDER DIALOGUE DIALOGUE HOTEL AFRICANA KAMPALA, 14 HOTEL AFRICANA KAMPALA, 14 TH TH February 2014 February 2014 MINISTRY OF ENERGY AND MINERAL DEVELOPMENT THE REPUBLIC OF U GANDA 0 ,1,675 <2 )( 1 (5 *<$ 1' 0 ,1 (5$ /' (9( /2 30 (1 7 7+(5(38%/,&2)8* $1'$

Upload: kaiden-christman

Post on 31-Mar-2015

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA

at theat the

OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS;OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS;CIVIL SOCIETY COALITION ON OIL AND GAS (CSCO) STAKEHOLDER DIALOGUECIVIL SOCIETY COALITION ON OIL AND GAS (CSCO) STAKEHOLDER DIALOGUE

HOTEL AFRICANA KAMPALA, 14HOTEL AFRICANA KAMPALA, 14THTH February 2014 February 2014

MINISTRY OF ENERGY AND MINERAL DEVELOPMENT0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '

0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

Page 2: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

PRESENTATION OUTLINE

1. Introduction: Current Status

2. Legal and Regulatory Framework

3. Infrastructure Development

4. National Participation

5. Way forward

6. Challenges

7. Concluding Remarks

2

Page 3: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

STATUS OF THE OIL AND GAS SECTORSTATUS OF THE OIL AND GAS SECTOR

3

RESOURCE BASERESOURCE BASE

• 21 oil and/or gas discoveries made in the Albertine Graben

• 18 discoveries taken forward for appraisal

• Appraisal for 10 of the discoveries completed, and applications for production license submitted

• One Production Licence (Kingfisher) approved during September 2013

• Appraisal of the remaining 8 discoveries still ongoing and is expected to be completed by end of 2014

LAKE VICTORIA

Lake Edward

Lake George

River Kafu

Lake Wamala

UGANDA

TANZANIA

RWANDA

SUDAN

DEMOCRATIC REPUBLIC OF CONGO

0 50 km

N

32 0 E 31 0 E 30 0 E

3 0 N

2 0 N

1 0 N

0 0

1 0 S

LEGEND

Rift Sediments

Exploration Area Boundary

Oil Discovery

Oil and Gas Discovery

Gas Discovery

2 0 N

1 0 N

2 0 N

1 0 N

32 0 E 31 0 E 30 0 E

32 0 E 31 0 E 30 0 E

LAKE VICTORIA

Lake Edward

Lake George

River Kafu

Lake Wamala

UGANDA

TANZANIA

RWANDA

SUDAN

DEMOCRATIC REPUBLIC OF CONGO

0 50 km

N

32 0 E 31 0 E 30 0 E

3 0 N

2 0 N

1 0 N

0 0

1 0 S

LEGEND

Rift Sediments

Exploration Area Boundary

Oil Discovery

Oil and Gas Discovery

Gas Discovery

2 0 N

1 0 N

2 0 N

1 0 N

32 0 E 31 0 E 30 0 E

32 0 E 31 0 E 30 0 E

Kingfisher

NgassaMputaNziziWaraga

KasameneWaihrindiNsogaNgegeKigogoleNgara

JobiRiiNgiriMpyoGunyaJobi-EastLyec

Discoveries in the Albertine Graben (Source: PEPD)

Page 4: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

STATUS OF THE OIL AND GAS SECTORSTATUS OF THE OIL AND GAS SECTOR

4

Appraisal Areas in the Albertine Graben (Source: PEPD)

TOTAL E&P Uganda B.V•Has submitted application for one Production license – Ngiri Discovery•Appraisal of six discoveries in EA1 & 1A

Tullow Uganda Operations Pty Ltd

•Has submitted application for Production License for eight discoveries in EA2

•Appraising one discovery in EA2

CNOOC Uganda Ltd•Production License for the Kingfisher Field approved.

•Development in Progress

STATUS OF UPSTREAM ACTIVITIESSTATUS OF UPSTREAM ACTIVITIES

Page 5: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

1 1 1 1

5 4

13

7

11 12

18

23

1

2

22

5

2

0

5

10

15

20

25

30

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Nu

mb

er

of

We

lls

YEAR

DRILLING SUCCESS TREND IN THE ALBERTINE GRABEN

Discovery Dry hole

STATUS OF THE OIL AND GAS SECTOR5

Drilling success trend (Source : PEPD)

• 115 exploration and appraisal wells drilled in the Albertine Graben to date

• 101 wells encountered hydrocarbons

• Drilling success rate of over 85%

• 36 exploration wells and 79 appraisal wells

• 28 wells have been flow tested

• Crude blend between 230 – 330 API with very low sulphur and is waxy

1.2 EXPLORATORY AND APPRAISAL DRILLING1.2 EXPLORATORY AND APPRAISAL DRILLING

87%

13% Success

Failure

Page 6: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

0.0

500.0

1000.0

1500.0

2000.0

2500.0

1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

3.0 3.2 3.5 7.6 12.6 27.7 47.7 59.7105.7

231.8

509.7

775.6

1,074.1

1,393.6

1,728.4

2,478.4

INV

ES

TM

EN

T (

Mil

lio

n U

S$

)

YEAR

INVESTMENT TREND IN THE OIL AND GAS SECTOR

Annual Investment Cummulative Investment

STATUS OF THE OIL AND GAS SECTORSTATUS OF THE OIL AND GAS SECTOR

6

Drilling success trend (Source : PEPD)

UPSTREAM CAPITAL INVESTMENTSUPSTREAM CAPITAL INVESTMENTS

Investment by industry in seismic surveys, exploratory and appraisal drilling is projected at over US$2.5billion by the end of 2013

Sharp increase in investment after first commercial discovery

This investment has been important in progressing the country’s oil and gas sector

Expected to increase significantly during development, production, refinery development and attendant pipelines development

1st Commercial Discovery

Page 7: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

7

1.5 ONGOING PROMOTION EFFORTS1.5 ONGOING PROMOTION EFFORTS

1. STATUS OF THE OIL AND GAS SECTOR

Participating in and presenting papers at International fora such as at AAPG, SEG, Africa Upstream and EAPCE’13.

Preparing to undertake a multi-client (non-exclusive) seismic survey over unlicensed areas

Commencing analysis of other sedimentary basins in the country.

Undertaking assessment of the oil and gas resources for all discoveries and compilation of country resource report.

Page 8: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

© Petroleum Exploration and Production Department, Uganda8

2. THE LEGAL AND REGULATORY FRAMEWORK2. THE LEGAL AND REGULATORY FRAMEWORK

The National Oil and Gas Policy (2008)

Available on: www.petroleum.go.ug

NATIONAL OIL AND GAS POLICY

PETROLEUM LEGISLATIONS

PETROLEUM REGULATIONS PSA

POLICY

LAWS

• The Petroleum (Exploration, Development and Production) Act, 2013 - Enacted in April 2013

• Petroleum (Refining, Conversion, Storage and Transportation) Act, 2013 – Enacted in July 2013

• Formulation of a Bill for the management of petroleum revenues (The Public Finance Bill) on going and the Bill is currently in Parliament

• Other relevant statutes and guidelines such as Environment , Wildlife, Water, Income Tax, land

• Petroleum (Exploration and production) (Conduct of Exploration Operations) Regulations, 1993

• New Petroleum Regulations expected by June 2014 to address aspects of Exploration, Development, Production, HSE, NC and Midstream among others

REGULATIONS

Page 9: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

9

2.2 Other Practical Tools used to Regulate the Petroleum Upstream 2.2 Other Practical Tools used to Regulate the Petroleum Upstream SectorSector

•Assessment of Technical Submissions: Review of Field Development Plans; Well proposals, drilling programs, seismic survey plans, among others.

•Monitoring of Costs of Petroleum Operations and Review of Work Programs and Budgets.

•Monitoring Field Activities on a full time basis and holding regular operational meeting between Government and the licensed companies.

•Monitoring Compliance of the Licensees; to the Laws, Regulations, PSAs and other regulatory instruments through a License Management System.

•Documenting and categorising the country’s petroleum resources.

•Management of Petroleum Data.

Guidelines to support these tools have and continued to be developed.

OTHER REGULATORY TOOLS USED

Page 10: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

10

Refinery Distribution in Africa (Source: CITAC)

Uganda’s petroleum products consumption during 2012 was 27,000 bbl/day

Regional consumption is about 200,000 bbl/day with a growth rate of 7%.

Region has only one refinery with a capacity of 70,000 bbl/day but has been operating at half capacity.

Reduced security of supply and high import bill of about 1 billion USD annually.

The EAC strategy for development of regional refineries was adopted by Partner States in 2008. It recommended a refinery should be developed in Uganda.

3.1 Refinery Development

3. PLANS FOR INFRASTRUCTURE DEVELOPMENT

Page 11: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

Feasibility study for the development of a green field refinery in Uganda confirmed that developing a refinery in Uganda was profitable.

Government procured a Transaction Advisor (Taylor DeJongh from USA) to support structuring of the refinery development and source a lead investor.

Refinery to be developed on a Private – Public Partnership (PPP) basis RFQ issued in October 2013 and six firms and/or consortia have been shortlisted. The

Ministry issued a detailed RFP during January 2014 to the six bidders:• Consortium led by China Petroleum Pipeline Bureau• MARUBENI Corporation (Japan);• Consortium led by PETROFAC (UK/UAE);• Consortium led by RT – Global Resources (Russia);• Consortium led by SK Energy (Korea); and• Consortium led by VITOL (Switzerland).

Lead investor to be procured by June 2014 and the first phase of the refinery (30k bopd) expected in 2017/18.

11

Medium-large refineryRefinery Development; Progress

PLANS FOR INFRASTRUCTURE DEVELOPMENT (2)

Page 12: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

Processes of acquiring land in Kabaale, Buseruka Subcounty, Hoima for refinery development is on-going;

Survey of the land was undertaken by the Ministry of Lands, Housing and Urban Devt.

Sensitisation of affected communities and undertaking a Resettlement Action Plan in 2012

RAP approved and implementation commenced in July 2013 with verification, disclosure of compensation values, livelihood improvement and financial management training and identification of resettlement areas.

Payment of compensation packages commenced in December 2013 and will be concluded in the first half of 2014 as sensitisation continues

Environment baseline survey has been completed12

Medium-large refineryRefinery Development; Land Acquisition

PLANS FOR INFRASTRUCTURE DEVELOPMENT

Page 13: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

13PLANS FOR INFRASTRUCTURE DEVELOPMENT

REFINERY DEVELOPMENT MILESTONES

Feasibility Study

Land Acquisition

Environmental Baseline Survey

Identification of Lead Investor

FEED & EIA

EPC

Commissioning Phase-1

2011 2012 2013 2014 2015 2016 2017 2018

FID Commissioning Phase-1

Feasibility Study

2010 - 2011

2012 - 2013

2013

2014

2014 - 2015

2015 - 2017

2017 - 2018

2012 - 2014

Page 14: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

Kingfisher

NgassaMputaWaraga

KasameneNsogaKigogoleWaihrindi

JobiRiiNgiri

BASIN WIDE DEVELOPMENTBASIN WIDE DEVELOPMENT

14

PLANS FOR INFRASTRUCTURE DEVELOPMENT

Page 15: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

A study to evaluate development of pipelines and storage facilities for crude oil and gas in Uganda has been concluded; Two routes; Northern and Southern to a central hub/refinery

Plans are underway to develop a 205km refined products pipeline from the Refinery to Buloba, west of Kampala where a terminal is planned.

Roads, water, electricity and other infrastructure in the Albertine Graben are being upgraded.

15

REFINERY

Refinery

Refined products pipeline

PLANS FOR INFRASTRUCTURE DEVELOPMENT

PIPELINES AND TRANSPORTATION FACILITIES

Page 16: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

1. Crude Transportation Pipeline to refinery

The study to evaluate development of pipelines and storage facilities was completed in 2012;

Two routes (Northern and Southern) to a central hub/Refinery were identified

i. Northern route: 97km, 16-inch and, ii. Southern route: 46km, 12.5 inch

Cost of pipelines estimated at $185M

PIPELINE DEVELOPMENT

16

PLANS FOR INFRASTRUCTURE DEVELOPMENT

Page 17: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

17

2. Crude Export Pipeline

Three possible routes were evaluated

i. Northern route to Lamu Port in Kenya, 1380km long

ii. Central route to Mombasa, 1300km long

iii. Southern route to Dar es Salam, 1950km long

The actual sizing of pipeline and detailed routing to be completed with a view of regional infrastructure development once commercialization plans are finalized

PLANS FOR INFRASTRUCTURE DEVELOPMENT

Page 18: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

18

Government strongly encourages National Participation as one of the optimum ways to ensure sustainable development through:

• Partnering with the Ugandan investors,

• Use of local goods and services and

• Contribution to development of skills and expertise through employment and training in line with the industry quality and safety standards.

This is important because sustainable development ultimately requires that a country’s citizens are part and parcel of the development process.

NATIONAL PARTICIPATION

Page 19: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

Strategies to ensure National ParticipationStrategies to ensure National Participation

1. Regulation of inflow of expatriates; expatriate workers must acquire work permits.

2. Requirement to develop Nationalisation Plans for expatriate positions

3. Approval of organisation structures for oil companies

4. Streamlining the procurement procedures for oil companies

5. Production Sharing Agreements (PSAs) provide for State Participation in the range of 15% to 20%

6. Several aspects of national participation have been included in the new petroleum legislation.

7. Capacity Building and Skills Development

8. Ministry is developing a National Content Policy19

NATIONAL PARTICIPATION

Page 20: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

20

NATIONAL ENTREPRENEURSNATIONAL ENTREPRENEURS National Entrepreneurs are actively involved in provision of services in the sector in the following areas;

1.Civil Works and Engineering,

2.Medical Services,

3.Clearing and Forwarding,

4.Environment Services (Consultancy and Waste Handling).

5.Security,

6.Catering and Camp Management

7.Freight Forwarders/Courier services

8.Rig Services( Movement and Mud logging)

9. Office Facilities and Equipment

10.Equipment lifting services

11.Engineering services

12.Communications and ICT

NATIONAL PARTICIPATION

Page 21: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

21

EMPLOYMENT BY OIL COMPANIESEMPLOYMENT BY OIL COMPANIES • Licensed companies in the country are employing an increasing number of Ugandans

• Tullow employed a total of 203 people in 2013, out of which 80% are Ugandans

• CNOOC plans to employee 115 people in 2014 out of which 70% are Ugandans

• Total employs over 500 people out of which 80% are Ugandans

• These numbers are expected to increase as more Ugandans acquire skills in the oil and gas sector.

Hundreds of semi-skilled and unskilled workers are employed from the local communities during operations

NATIONAL PARTICIPATION

Page 22: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

0 ,1 ,675 <2 ) ( 1 ( 5 * <$1 '0 ,1 ( 5 $/ ' ( 9( / 2 30 ( 1 7

THE REPUBLIC OF U GANDA 0 ,1 ,675 <2 ) ( 1 ( 5 * <$ 1'

0 ,1 ( 5 $ / ' ( 9( / 2 30 ( 1 7

7+( 5( 38%/ ,&2) 8* $1' $

22

INTERNATIONAL OIL SERVICES COMPANIESINTERNATIONAL OIL SERVICES COMPANIES

Some of the world’s largest oil service companies are now resident and have opened up bases and yards in the country;

Schlumberger; US$79.57 billion

Halliburton; US$24.64 billion

Baker Hughes; US$16.74 billion

Weatherford; US$8.91 billion

These service companies are also providing training and employment opportunities to Ugandans

NATIONAL PARTICIPATION

Page 23: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

Newly recruited workers undergoing survey training by BGP personnel in preparation for the 3D data acquisition

Employment

Majority of these jobs will be through indirect employment.

Employment curve for the oil and gas industry is such that employment increases during the development stage where a lot of infrastructure is put in place.

Acquisition of certified vocational skills is therefore important as these stage will require artisanal and technical skills.

As the activities progress towards actual production, more highly skilled labour is required and high technology utilized, with less man-hours.

Emphasis for communities therefore is to focus on employment but also service provision.

Causal labour sourced from the local community and provide opportunity to build skills

23

5. COMMUNITY PARTICIPATION

Hundreds of semi-skilled and unskilled workers are employed from the local communities during operations

Page 24: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

Development of regulations to support the new upstream and midstream Acts; to be in place during 2014.

Preparations for Licensing through competitive bidding rounds starting with areas with good data coverage is going on

The Ministry will undertake speculative surveys in the unlicensed areas to inform the fiscal terms.

Establishment of the Petroleum Authority and National Oil Company await appointment of the board by the President. The board will be approved by Parliament.

National Content Policy to be developed through a consultative process. Procurement of a lead investor for the refinery to be concluded in the first half of

2014. Development of a National Strategic Plan for Pipelines development has commenced. Development of an implementation plan for the Strategic Environment Assessment

will follow its adoption by Cabinet. Continue with implementation of the communication strategy for the oil and gas

sector Implementation of the Monitoring and Evaluation Framework for the NOGP

24

Medium-large refinery

6. WAY FORWARD

Page 25: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

7. CONCLUDING REMARKS25

Uganda’s oil and gas sector is taking shape, the regulatory for the upstream sector has been finalized, institutional framework is being put in place to manage the resources and the infrastructure to support the development is being built.

Taking forward the sector will require joint and harmonized efforts on the part of the respective stakeholders.

The Ministry of Energy ad Mineral Development recognizes and appreciates the support by other Government Institutions, Oil Companies, Development partners, Civil Society and other stakeholders in the implementation of the different aspects of the National Oil and Gas Policy for Uganda.

Page 26: PROGRESS ON PETROLEUM EXPLORATION AND DEVELOPMENT IN UGANDA at the OIL DEVELOPMENT, ENVIRONMENTAL CONSERVATION AND LIVELIHOODS; CIVIL SOCIETY COALITION

For Further information:

Permanent Secretary, Ministry of Energy and Mineral Development

Email: [email protected]@energy.go.ug [email protected]/ [email protected] www.petroleum.go.ug