PROGRESS REPORT (1st Week March 2015)
PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
Outstanding Work (In Progress)
Section Activity Percentage
ManPower
Pre-Successor Activity
Successor Activity Remark
Building Architectural Works
Brickwall-in-Position 97% FF-Sprinkler Pump
Bricklayering->Plastering
Level Lower Ground- 85%
Plastering Work 89% Level Lower Ground- 40%Ceiling Works 22% Framing Works - 50%M&E Works Piping & Conduiting Works
- Cold+Hot Water & Plumbing Works- Fire Fighting Services- Electrical Services- ELV Services- HVAC ServicesCabling & Wiring Works- Cold+Hot Water & Plumbing Works- Fire Fighting Services- Electrical Services- ELV Services- HVAC Services
Floor FinishesWall FinishesExternal Plastering +Internal Plastering
Left Side- 100%Front- 100%Back-95%Right- 95%
16+15
Bricklayer Internal Left room ,3019,3020,4017
Ceiling frame Third Floor- 3017,3018,3021Fourth floor -left ac storage room 4007Request for information
1. Advice from id designer on the finishing near
PROGRESS REPORT (1st Week March 2015)
PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
window
Skim Coat 6 Two days render Demonstration on supplier 22-23/1/2015Ideal Thickness: 5-7mm Bad weather caused delay
Electric Wiring 2nd Floor
12/27 room completed3rd floorMain cabling on corridorInstall busbar ground floor
6 Main progress still on typical roomBusduct TPN already install for riser staircase 3. #Ensure the electrical room out of water.Request for information
1. Any isolator for submersible pump and standby pump for sump pit_lower ground ?
ELV 3rd floor typical room
4 Request for information1. Need of cctv installation along fencing?2.
Housekeeping / Demobilization
3 Excavation on Retaining Wall, New Store Room (12mx16m)
Banyan start to remove their rebar wastage by 26/1/2015.Expect Manager briefing on Site preparation on receiving scheduled incoming material and setting out site storage with protected security {URGENT}Expect sub-contractor start housekeeping on all wastage.
Plumbing 2 Internal Plumbing 4th Floor
Hydrostatic test will redo again after ID finalized.Request for information
1. Insufficient detail on laundry room =source of hot water? Need water heater? = the cw and hw pipe are concealed or exposed?
PROGRESS REPORT (1st Week March 2015)
PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
2. Request catalogue for all plumbing fixture etc.
Dewatering on Basement
1 Wall plastering, Crack repair
New kerb on preventing water entering lift entrance lower groundImproving external drainage to prevent inflow water into building*Mud Flow on entrance after storm rain 16/1/2015
Lift Core Repairing crack Lift installation *Structural Repair claimed insufficient thickness of reinforced concrete (1inch) on the edge lead to dampness on the lift core.*They reported waterstop failure on Passenger lift along the certain perimeter of lift core.
Water tightness on internal Building
Sealing some windows with plywood+silicon (Location: Lift motor Room, lift lobby, switchboard room), Lift Installation, Switchboard Room
Some rooms were flooded due to incoming of heavily rain through window opening.Q: Necessary to temporarily seal some windows?High risk zone: Busbar riser, render storage, ac storage room, lift
Crack Sprinkler Tank Pending Structural Repair for investigation reportFencing 7 Bricklayering Main activities on retaining wallMain Drainage Pending arrival of precast drain (estimation 3 weeks)aircond 2 ID Drawing Drainage problem (sitting lounge)Window subframe 4 Bricklayering
5017 on toilet5017, 4014, 3021,3022, sitting lounge toilet (1025, 2024, 3023, 4018, 5018)
Rectification on 5 windows due to wrong positioning (>1 inch).Inspection on squareness of window and alignment will be completed on Thursday 29/1/2015.
Handrail roof garden 2 Start marking and Plastering on rc wall for handrail (24-1-2015)
Wrapping protection on Handrail completed.
Plastering on Hose Reel Room
15% Plastering->Wall Painting -> Hose Reel Piping -> Hose Reel Drum (critical on 5th floor)
Plastering on fire hose reel compartment 1st / 4 /5 floor completed.Expectation on completing plastering on Wed 28/1/2015
PROGRESS REPORT (1st Week March 2015)
PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
Internal plastering 5th floor
Floor screeding
Sealing gap on fixed glass near meeting room
40% Ceiling frame
Screeding on pump room
Bricklayering->Plastering
Hacking the problematic wall due to plumbing pipe on cafeteria.Cement Skim Coat RC PlinthLintel /stiffener on 3021/3022
Remove loading bay
Bricklayering on 4th floor corridor in replace hitching waterproofing
Housekeeping wastage
Toilet screeding and wall plasteringPainting Rendering ->
Mock Up Sample
-After CNY-For ground floor, current external wall (without rendering) is ideal for painting(commented by TBS Tang).
Mark level on flooring (GF-meeting Room)Concreting on toilet floor 3011
Discrepancy between old and new drawing
Additional beam or lintel support for FG 15/16/17/18
Seek CHT Consultant advice, EOT drawing
Request for information1. Dimension on fg 15/16/17/18 from EOT2. Structural design on lintel for fg 15/16/17/18
from CHT consultantCoring 5th floor Soil PipeAnd sitting lounge
Request for information1. Latest id drawing
Ceiling Gypsum Board on first floor
Final ID Drawing, M&E Inspection, M&E
Checklist completed and will be distributed to contractor.
PROGRESS REPORT (1st Week March 2015)
PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
As built drawingOpening for exhaust fan for switch board room + toilet Roof Garden + lift motor room
Request for information1. Enquiry model of exhaust fan.2. Need of any subframe for the exhaust fan.
Inspection on Staircase 2
Staircase work report will completed 28/1/2015 WEDNESDAY.
Hacking parapet wall Roof Garden
Pending final EOT design
Ceiling Evenness Basement
Planned mock up painting on ceiling lower ground for review the finishing work_cement skim coat on Monday 26/1/2015. Check the work of cement skim coat.
Screeding on AC Room each floor
External Plastering
Screeding RC ledge first floor + fourth floor
Outstanding report- welding report (ff), crack report (structural repair), water tightness building report, render defect report, cement sand screed report, staircase report, outstanding work.