PROGRESS REPORT (1 st Week March 2015) PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu Outstanding Work (In Progress) Section Activity Percen tage Man Power Pre- Successor Activity Successor Activity Remark Building Architectu ral Works Brickwall-in- Position 97% FF-Sprinkler Pump Bricklayering ->Plastering Level Lower Ground- 85% Plastering Work 89% Level Lower Ground- 40% Ceiling Works 22% Framing Works - 50% M&E Works Piping & Conduiting Works - Cold+Hot Water & Plumbing Works - Fire Fighting Services - Electrical Services - ELV Services - HVAC Services Cabling & Wiring Works - Cold+Hot Water & Plumbing Works - Fire Fighting Services - Electrical Services - ELV Services - HVAC Services Floor Finishes Wall Finishes External Plastering + Internal Plastering Left Side- 100% Front- 100% 16 +15 Bricklayer Internal Left room ,3019,3020,4017

Upload: rachel-ingram

Post on 17-Jul-2016

13 views

Category:

Documents


4 download

DESCRIPTION

soho

TRANSCRIPT

PROGRESS REPORT (1st Week March 2015)

PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu

Outstanding Work (In Progress)

Section Activity Percentage

ManPower

Pre-Successor Activity

Successor Activity Remark

Building Architectural Works

Brickwall-in-Position 97% FF-Sprinkler Pump

Bricklayering->Plastering

Level Lower Ground- 85%

Plastering Work 89% Level Lower Ground- 40%Ceiling Works 22% Framing Works - 50%M&E Works Piping & Conduiting Works

- Cold+Hot Water & Plumbing Works- Fire Fighting Services- Electrical Services- ELV Services- HVAC ServicesCabling & Wiring Works- Cold+Hot Water & Plumbing Works- Fire Fighting Services- Electrical Services- ELV Services- HVAC Services

Floor FinishesWall FinishesExternal Plastering +Internal Plastering

Left Side- 100%Front- 100%Back-95%Right- 95%

16+15

Bricklayer Internal Left room ,3019,3020,4017

Ceiling frame Third Floor- 3017,3018,3021Fourth floor -left ac storage room 4007Request for information

1. Advice from id designer on the finishing near

PROGRESS REPORT (1st Week March 2015)

PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu

window

Skim Coat 6 Two days render Demonstration on supplier 22-23/1/2015Ideal Thickness: 5-7mm Bad weather caused delay

Electric Wiring 2nd Floor

12/27 room completed3rd floorMain cabling on corridorInstall busbar ground floor

6 Main progress still on typical roomBusduct TPN already install for riser staircase 3. #Ensure the electrical room out of water.Request for information

1. Any isolator for submersible pump and standby pump for sump pit_lower ground ?

ELV 3rd floor typical room

4 Request for information1. Need of cctv installation along fencing?2.

Housekeeping / Demobilization

3 Excavation on Retaining Wall, New Store Room (12mx16m)

Banyan start to remove their rebar wastage by 26/1/2015.Expect Manager briefing on Site preparation on receiving scheduled incoming material and setting out site storage with protected security {URGENT}Expect sub-contractor start housekeeping on all wastage.

Plumbing 2 Internal Plumbing 4th Floor

Hydrostatic test will redo again after ID finalized.Request for information

1. Insufficient detail on laundry room =source of hot water? Need water heater? = the cw and hw pipe are concealed or exposed?

PROGRESS REPORT (1st Week March 2015)

PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu

2. Request catalogue for all plumbing fixture etc.

Dewatering on Basement

1 Wall plastering, Crack repair

New kerb on preventing water entering lift entrance lower groundImproving external drainage to prevent inflow water into building*Mud Flow on entrance after storm rain 16/1/2015

Lift Core Repairing crack Lift installation *Structural Repair claimed insufficient thickness of reinforced concrete (1inch) on the edge lead to dampness on the lift core.*They reported waterstop failure on Passenger lift along the certain perimeter of lift core.

Water tightness on internal Building

Sealing some windows with plywood+silicon (Location: Lift motor Room, lift lobby, switchboard room), Lift Installation, Switchboard Room

Some rooms were flooded due to incoming of heavily rain through window opening.Q: Necessary to temporarily seal some windows?High risk zone: Busbar riser, render storage, ac storage room, lift

Crack Sprinkler Tank Pending Structural Repair for investigation reportFencing 7 Bricklayering Main activities on retaining wallMain Drainage Pending arrival of precast drain (estimation 3 weeks)aircond 2 ID Drawing Drainage problem (sitting lounge)Window subframe 4 Bricklayering

5017 on toilet5017, 4014, 3021,3022, sitting lounge toilet (1025, 2024, 3023, 4018, 5018)

Rectification on 5 windows due to wrong positioning (>1 inch).Inspection on squareness of window and alignment will be completed on Thursday 29/1/2015.

Handrail roof garden 2 Start marking and Plastering on rc wall for handrail (24-1-2015)

Wrapping protection on Handrail completed.

Plastering on Hose Reel Room

15% Plastering->Wall Painting -> Hose Reel Piping -> Hose Reel Drum (critical on 5th floor)

Plastering on fire hose reel compartment 1st / 4 /5 floor completed.Expectation on completing plastering on Wed 28/1/2015

PROGRESS REPORT (1st Week March 2015)

PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu

Internal plastering 5th floor

Floor screeding

Sealing gap on fixed glass near meeting room

40% Ceiling frame

Screeding on pump room

Bricklayering->Plastering

Hacking the problematic wall due to plumbing pipe on cafeteria.Cement Skim Coat RC PlinthLintel /stiffener on 3021/3022

Remove loading bay

Bricklayering on 4th floor corridor in replace hitching waterproofing

Housekeeping wastage

Toilet screeding and wall plasteringPainting Rendering ->

Mock Up Sample

-After CNY-For ground floor, current external wall (without rendering) is ideal for painting(commented by TBS Tang).

Mark level on flooring (GF-meeting Room)Concreting on toilet floor 3011

Discrepancy between old and new drawing

Additional beam or lintel support for FG 15/16/17/18

Seek CHT Consultant advice, EOT drawing

Request for information1. Dimension on fg 15/16/17/18 from EOT2. Structural design on lintel for fg 15/16/17/18

from CHT consultantCoring 5th floor Soil PipeAnd sitting lounge

Request for information1. Latest id drawing

Ceiling Gypsum Board on first floor

Final ID Drawing, M&E Inspection, M&E

Checklist completed and will be distributed to contractor.

PROGRESS REPORT (1st Week March 2015)

PROJECT: Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu

As built drawingOpening for exhaust fan for switch board room + toilet Roof Garden + lift motor room

Request for information1. Enquiry model of exhaust fan.2. Need of any subframe for the exhaust fan.

Inspection on Staircase 2

Staircase work report will completed 28/1/2015 WEDNESDAY.

Hacking parapet wall Roof Garden

Pending final EOT design

Ceiling Evenness Basement

Planned mock up painting on ceiling lower ground for review the finishing work_cement skim coat on Monday 26/1/2015. Check the work of cement skim coat.

Screeding on AC Room each floor

External Plastering

Screeding RC ledge first floor + fourth floor

Outstanding report- welding report (ff), crack report (structural repair), water tightness building report, render defect report, cement sand screed report, staircase report, outstanding work.