progress status at pour 5,6 locations

11
Progress Status at Podium LB 6,7 & UB 5 Locations Status as on 24 th Nov’15

Upload: krmchari

Post on 30-Jan-2016

225 views

Category:

Documents


0 download

DESCRIPTION

Progress Status a

TRANSCRIPT

Page 1: Progress Status at Pour 5,6 Locations

Progress Status at Podium LB 6,7 & UB 5 Locations

Status as on 24th Nov’15

Page 2: Progress Status at Pour 5,6 Locations

30% staging works yet to be done at pour 5 UB location.

Page 3: Progress Status at Pour 5,6 Locations

Retaining wall (Dependent activity ) not yet casted at pour 5 UB location

Page 4: Progress Status at Pour 5,6 Locations

40% shuttering works yet to be done at pour 5 UB location.

Page 5: Progress Status at Pour 5,6 Locations

Staircase columns not yet casted at pour 5 location.

Page 6: Progress Status at Pour 5,6 Locations

20% shuttering work yet to be done at pour 6 location.

Page 7: Progress Status at Pour 5,6 Locations

No manpower been deployed for reinforcement works at Pour 6 location.

Page 8: Progress Status at Pour 5,6 Locations

Beam B34 bottom not yet initiated at pour 6 location.

Page 9: Progress Status at Pour 5,6 Locations

Rain water tank bottom slab not yet casted at pour 6 location.

Page 10: Progress Status at Pour 5,6 Locations

16 columns yet to be casted at pour 7 location .

Page 11: Progress Status at Pour 5,6 Locations

Casting of starters not been initiated at pour 7 locations