project appraisal report - african development bank · appendix i. comparative socio-economic...
TRANSCRIPT
AFRICAN DEVELOPMENT FUND
PROJECT : ECCAS Institutional Capacity Building Support
(PARCI-ECCAS)
MULTINATIONAL: Economic Community of Central African States
(ECCAS)
PROJECT APPRAISAL REPORT September 2012
Appraisal Team
Sector Director: Mr. Isaac Lobe Ndoumbe, Director, OSGE
Regional Director: Mrs. M. KANGA, Director, ORCE
Sector Manager: Mr. J-L. BERNASCONI, Manager, OSGE.1
Team Leader: Mr. A. AMOUMOUN, Principal Governance Expert, OSGE.2
TABLE OF CONTENTS
I. Strategic Thrust and Rationale .......................................................................................... 1
1.1 Project Linkages with the Regional Integration Strategy and Objectives ................... 1
1.2 Rationale for Bank’s Involvement .............................................................................. 2
1.3 Aid Coordination ......................................................................................................... 3
II – Project Description .............................................................................................................. 4
2.1 Project Components .................................................................................................... 4
2.2 Technical Solutions Retained and Other Alternatives Explored ................................. 6
2.3 Project Type ............................................................................................................... 6
2.4 Project Cost and Financing Arrangements .................................................................. 6
2.5 Project Target Area and Beneficiaries......................................................................... 8
2.6 Participatory Process for Project Identification, Design and Implementation ............ 8
2.7 Consideration of Bank Group Experience and Lessons Learnt Reflected in Project Design .. 9
2.8 Key Performance Indicators ........................................................................................ 9
III – Project Feasibility ............................................................................................................ 10
3.1 Economic and Financial Performance ....................................................................... 10
3.2 Environmental and Social Impact ............................................................................. 10
IV – Implementation ................................................................................................................ 12
4.1 Implementation Arrangements ................................................................................. 12
4.2 Monitoring ................................................................................................................. 13
4.3 Governance ................................................................................................................ 13
4.4 Sustainability ............................................................................................................. 14
4.5 Risk Management ...................................................................................................... 15
4.6 Knowledge Development .......................................................................................... 15
V – Legal Framework .............................................................................................................. 16
5.1 Legal Instrument........................................................................................................ 16
5.2 Conditions Associated with Fund Intervention ......................................................... 16
5.3 Compliance with Bank policies ................................................................................. 16
VI – Recommendation ............................................................................................................. 16
Appendix I. Comparative Socio-Economic Indicators of ECCAS
Appendix II. Table of the Bank Group’s Portfolio of Multinational Operations in Central Africa as
at 30 June 2012 (in UA million)
Appendix III Major Related Projects Financed by the Bank and Other Development Partners of
ECCAS
Appendix IV. Map of the Project Area
i
LIST OF TECHNICAL ANNEXES
ANNEX A: DEVELOPMENT AGENDA, SECTOR OVERVIEW AND DONOR SUPPORT
A1 Development Agenda A2 Sector Overview A3 Donor Support
ANNEX B: SUPPORTING ANALYSIS OF THE KEY ARGUMENTS OF THE REPORT
B1 Main Lessons B2 Detailed Project Costs B3 Implementation Arrangements (details) B4 Financial Management and Disbursement Arrangements (details)
Financial Management Arrangements (details)
B5 Procurement Arrangements (details) B6 Audit Arrangements (details) B7 Environmental and Social Analysis B9 Project Preparation and Supervision
ANNEX C: OTHER TECHNICAL ANNEXES
C1 Detailed Description of Project Components C2 List of Financing Criteria for RPGs
LIST OF TABLES
No. Title Page 1.1 Support of Technical and Financial Partners for ECCAS Capacity-Building
(in CFA.F million) 4
2.1 Project Components 5
2.2 Alternative Solutions Considered and Reasons for their Rejection 6
2.3 Estimated Costs by Component 7
2.4 Project Costs by Expenditure Category 7
2.5 Sources of Financing 7
2.6 Expenditure Schedule by Expenditure Category 8
2.7 Expenditure Schedule by Component 8
4.1 Monitoring Stages/Feedback Loop 13
4.2 Risks and Mitigation Measures 15
ii
Currency Equivalents
September 2012
UA = CFA.F 791.668
UA = EUR 1.20689
UA = USD 1.52202
Fiscal Year
1 January – 31 December
Weights and Measures
1 metric tonne = 2204 pounds
1 kilogramme (kg) = 2,200
1 metre (m) = 3.28 feet
1 millimetre (mm) = 0.03937 inches
1 kilometre (km) = 0.62 miles
1 hectare (ha) = 2.471 acres
iii
Acronyms and Abbreviations
ACBF African Ccapacity Building Foundation
ADF African Development Fund AMU Arab Maghreb Union AU African Union CAADP Comprehensive Africa Agriculture Development Programme CEMAC Central African Economic and Monetary Community CEN-SAD Community of Sahel-Saharan States
CET Common External Tariff CIC Community Integration Contribution
CIDA Canadian International Development Agency
COBAC Banking Commission of Central Africa COMESA Common Market for East and Southern Africa
COMIFAC Central African Forestry Commission COPAX Council for Peace and Security in Central Africa DIPEM Department in charge of Physical, Economic and Monetary Integration
ECA Economic Commission for Africa ECCAS Economic Community of Central African States ECOWAS Economic Community of West African States EU European Union FCD Community Cooperation and Development Fund
FOMAC Central African Multinational Force
FTA Free Trade Area GDP Gross Domestic Product IGAD Intergovernmental Authority on Development
ITC International Trade Center
MARAC Central African Early Warning System MIP Minimum Integration Programme NEPAD New Partnership for Africa’s Development NEPAD-IPPFF NEPAD Infrastructure Project Preparation Facility
PACT II Programme for Building African Capacity for Trade PAP Priority Action Programme PAPS Support Programme for Peace and Security in Central Africa PARCI-ECCAS ECCAS Institutional Capacity-Building Support Project of ECCAS
(PARCI-ECCAS) PDCT-AC Central African Consensual Transport Master Plan PIDA Programme for Infrastructure Development in Africa PIU Project Implementation Unit PSC Project Steering Committee
REC Regional Economic Community REG Republic of Equatorial Guinea REP Regional Economic Programme RIS Regional Integration Strategy RISP Regional Integration Strategy Paper SADC Southern African Development Community
STP Sao Tome and Principe UDE Equatorial Customs Union UDEAC Central African Customs and Economic Union UNDP United Nations Development Programme UNECA United Nations Economic Commission for Africa
US United States
iv
Project Information Sheet
Client Information
DONEE : Economic Community of Central African States
(ECCAS)
EXECUTING AGENCY : ECCAS General Secretariat
Financing Plan
Source Amount (UA
million) Instrument
ADF (regional RPG budget)
7.00
Grant
ECCAS 1.23 Counterpart Funds
TOTAL COST 8.23
Key Financing Information on ADF Grant
Grant Currency
UA
Interest* Type NA
Interest Rate Spread* NA
Service Charge* NA
Other Charges* NA
Tenor NA
Grace period NA
FRR, NPV (baseline scenario) NA
ERR (baseline scenario) NA
*if applicable
Timeframe – Main Milestones (expected)
Concept Note Approval August 2012
Appraisal September 2012
Regional Team October 2012
Project Approval December 2012
Effectiveness January 2012
First Disbursement March 2013
Last Disbursement December 2016
Completion March 2017
v
Project Summary
Project
Overview The ECCAS Institutional Capacity Building Support Project (PARCI-CEEAC) falls within the framework of
the Bank’s Regional Integration Strategy Paper (RISP, 2011-2015) for Central Africa, the main pillars of
which is focused on capacity-building for the Central African Economic Community (ECCAS). Its objective is
to promote regional integration in Central Africa by building ECCAS’ institutional, human and operational
capacity to implement regional programmes and the harmonization of sector policies. It aims to enhance
performance in the preparation and implementation of regional infrastructure programmes by building
institutional capacity. It also contributes to the improvement of intra-regional trade by supporting the
streamlining ECCAS and CEMAC sector policy initiatives. The project cost is UA 8.23 million, jointly
financed by the ADF (UA 7 million) and ECCAS (UA 1.23 million). It will be implemented over a four-year
period from 2013 to 2016.
Beneficiaries The project’s main direct beneficiaries are the ECCAS General Secretariat of ECCAS, the CEMAC
Commission and the Technical Secretariat of the Central Africa-REC Rationalization Committee that will
participate in studies and in other activities planned under the rationalization and harmonization of regional
policies and standards.
Consultations were held with stakeholders during project preparation. The participatory process will be
maintained during project implementation using an implementation framework involving all beneficiary
structures. Ownership of the planned institutional reforms will be ensured through ECCAS’ participatory
decision-making process involving all Member-States.
Needs
assessment The project will ensure the continuation of ECCAS capacity-building activities which are necessary for the
efficient implementation of regional infrastructure programmes and the harmonization of sector policies.
Indeed, ECCAS is faced with several institutional, human, organizational and financial constraints that
undermine the efficiency, impact and visibility of its action. It will also ensure the concrete implementation of
the ECCAS and CEMAC activities rationalization process of which the Bank is a key partner.
Bank’s Added-
Value
This operation comes at the right time to help address challenges that require bold responses at the strategic,
institutional and operational levels, in order to help Central Africa to catch up with other parts of the continent
in terms of regional integration. Indeed, the Bank, more than any other partner, is engaged in supporting RECs
to implement the integration process in accordance with its mandate.
Knowledge
Management
Implementation of this project will lead to the development of several types of knowledge, including the
capacity to analyze and adapt the institutional framework of RECs, the development of a statistical tool for
monitoring the implementation of regional infrastructure, and harmonization of the trade policies of ECCAS
and CEMAC which are two communities in the same region with different levels of liberalization for their
respective domestic markets. The technical assistance provided for under the project will promote the transfer
of knowledge to the institution through the deployment of counterpart experts. Lessons learnt from project
implementation will be disseminated through validation and dissemination of the studies produced. The
knowledge and lessons learned will be disseminated within the Bank.
vi
Results-based Logical Framework
Country and Project Name : Multinational ECCAS - Institutional Capacity Building Support Project (PARCI-ECCAS) Project Goal : Promote regional integration in Central Africa by building ECCAS’ institutional, human
and operational capacity to implement regional programmes and harmonization of sector
policies.
RESULTS CHAIN PERFORMANCE INDICATORS
MEANS OF
VERIFICATION RISKS/ MITIGATION MEASURES Indicator (including CSIs) Baseline
Situation Target
IMP
AC
T
Consolidation of economic growth
in the Central African region Economic growth rate of the ECCAS area 4.5% in 2011 5.3% in 2020 ECCAS, UNECA
and ADB reports
OU
TC
OM
ES Outcome 1: Implementation of
regional projects/programmes is
better coordinated and more
efficient
Disbursement rate of projects/programmes
coordinated by the ECCAS General
Secretariat 5% in 2010 30% in 2016 ECCAS reports
Regional CPPR
Risk 1. Low level of ownership by member States as reflected in the
delays in CIC payments and
difficulties in holding summits
Mitigation Measure 1. The revival of
national coordination teams for the harmonization of RECs and the
facilitation of intra-regional trade will
enable ECCAS to increase its visibility substantially in other to
arouse the greater interest among the Highest Authorities in Member
States. Risk 2. The weakness of national
structures responsible for regional
integration undermines the smooth conduct of projects.
Mitigation Measure 2. The future establishment of National NEPAD
Coordination teams in each State,
coupled with the support provided under this
project will help to facilitate intra-
regional trade and increase the presence of the General Secretariat.
Risk 3. Bottlenecks in the decision-making process could delay revision
of the legal framework and the
implementation of necessary reforms.
Mitigation Measure 3. Joint action
by donors, very close and coordinated monitoring of the project by
headquarters as well as technical
assistance provided by the Bank through other projects could help to
speed up the process of reviewing
ECCAS texts. Besides, the effective functioning of the Steering
Committee on the Rationalization of
RECs in Central Africa (COPIL/REC-CA) and the creation of
the CEMAC-ECCAS Joint
Committee will facilitate the
execution of actions planned under
the harmonization of regional
integration policies and instruments.
Risk 4. The weakness of the fiduciary
framework cannot guarantee the transparency or rational use of
financial resources
Outcome 2: Intra-regional trade
strengthened. Share of intra-community trade in the
region's total trade 1 % in 2010 2.5% in 2016 ADB statistics
(ESTA)
Component I: Supporting improvement of the institutional framework and monitoring/evaluation of regional infrastructure development
projects/programmes
OU
TP
UT
S
Output 1.1: The legal and
institutional framework of the GS
is strengthened
Output 1.2: The operational and
financial management mechanism
of the General Secretariat is
strengthened
1.1.1 The texts (Treaty, IR, SR and FR) are
revised.
1.2.1 Establishment of a RB strategic
framework
Outdated
fundamental
texts
Non-existent
Texts revised in
2015
RB strategic
framework
adopted in 2016
Adoption
instruments/decision
s
ECCAS Report
Adoption
instrument/decisions
Output 1.3: The infrastructure
projects in the PIDA Priority
Action Plan are in an advanced
stage of preparation
1.3.1 Level of preparation of the 12 PIDA-
PAP projects Stage S1
(identification
phase)
The 12 projects
of PIDA-PAP are
in the S2 level of
preparation
(feasibility
studies done)
including at least
4 projects in the
S4 stage
(implemented) in
2016
Regional PIDA
monitoring reports
Output 1.4: The statistics unit of
ECCAS is operational and the
infrastructure and trade databases
are available
1.4.1 Regional statistical development
strategy
1.4.2 Regional infrastructure database
1.4.2 External trade database
Non-existent
Almost non-
existent
Almost non-
existent
Strategy available
in 2014
Regional
infrastructure
database
available before
the end of 2015
External trade
database
available before
the end of 2015
ECCAS Report
ECCAS Report
Component II: Supporting the harmonization of regional integration policies and instruments Output 2.1: Harmonization of the
CET of CEMAC/ECCAS and of
the common customs code are at an
advanced level of implementation
2.1.1 Level of harmonization of the CET of
CEMAC/ECCAS
2.1.2 ECCAS/CEMAC customs codes
harmonized
2.1.3 A permanent CEMAC/ECCAS
coordination, exchange and validation
mechanism for the harmonized monitoring
of regional policies and programmes
Harmonization
underway
Customs codes
not harmonized
in 2011
Non-existent
CET harmonized
at the end of 2015
Common customs
code adopted in
2016
Harmonized
monitoring
mechanism
established in
2014
ECCAS and ADB
reports
Output 2.2: The COPIL TS is
operational
Capacity for steering the CEMAC
and ECCAS rationalization process
is strengthened
2.2.1 The organizational framework of the
ST is established and operational
2.2.2 Number of COPIL TS staff trained
including the number of COPIL TS women
trained
Embryonic in
2012
Low-skilled
experts
Organizational
framework of ST
COPIL
established in
2014;
16 COPIL TS
experts trained,
including at least
4 women, for
2014-16.
ECCAS and ADB
reports
vii
Output 2.3: ECCAS has greater
visibility.
Output 2.4: The focal points, the
NSA are sensitized to integration
issues.
Output 2.5: Greater ownership by
member-states
2.3.1 A communication plan with the 10
member states is prepared and validated.
2.4.1 : Number of stakeholders trained
including the percentage of women trained
2.5.1 The mechanism for monitoring and
acceleration of CIC collection is established
No plan
Low
Outstanding
CIC payments
in 2011
Communication
plan adopted
200 persons 40% of women
30% decline from
2011 to 2015
ECCAS and ADB
reports
Mitigation Measure 4: The Bank’s
procedures will be used. The
technical assistance provided under
this project to review the texts,
mechanisms as well as the
programmatic and financial
management processes will help to
strengthen the financial management
system.
KE
Y A
CT
IVIT
IES
COMPONENTS RESOURCES Component I: Supporting the improvement of the institutional framework and of the monitoring/evaluation of
regional infrastructure development programmes - Technical assistance, equipment and training
Component II: Supporting the harmonization of regional integration policies and instruments - Technical assistance, equipment and training
Component III: Project management Technical assistance, operational management manuals, equipment and training
ADF loan:
Indicative Cost in UA
million Component I 4.50
Component II 2.96
Project
Management 0.77
Total 8.23
viii
Project Implementation Schedule
Years
Activities / Months N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Prior to Start-Up
Board Presentation
Grant Effectiveness
Appointment of Coordinator
Formation of PT
Preparation of Procedures Manual
Project Launching Mission
Equipment and Supplies
Bidding for Office Automation and IT
Equipment.
Procurement of Software
Bidding for Other Equipment
Delivery of Goods and Start-Up
Consultants
Preparation of BDs and SLs
Issue of Invitations to Bid, Bid Analysis and
Award of Contracts,
Consulting Services
Tech. Assist. Legal Unit
Tech Assist. DISC
Tech. Assistance. DIPEM
Tech. Assist. COPIL
Tech. Assist. PBARH
Regional Consultants
Recruitment of Counterparts
Training and Other Items
Training
Operating Expenditure
Mid-Term Review
Monitoring-Evaluation 0 0
Tech. Coordination Committee Meetings
PSC Meeting io
n
Audit
Annual Audit of Accounts
Final Audit of Accounts
2012 2013 2014 2015 2016
1
BANK GROUP MANAGEMENT REPORT AND RECOMMENDATION TO THE BOARD OF DIRECTORS
CONCERNING A PROPOSAL TO AWARD A GRANT TO ECCAS FOR THE INSTITUTIONAL CAPACITY
BUILDING SUPPORT PROJECT OF ECCAS (PARCI-ECCAS)
Management submits this report and recommendations on a proposal to award a grant of UA 7 million
to the General Secretariat of the Economic Community of Central African States (ECCAS) to finance
the Institutional Capacity Building Support Project of ECCAS (PARCI-ECCAS).
I. Strategic Thrust and Rationale
1.1 Project Linkages with the Regional Integration Strategy and Objectives
1.1.1 The African Union (AU) Integration Strategy derives from the Abuja Treaty to create the
African Economic Community (AEC) that has been in force since May 1994. The AEC is
implemented through the eight regional communities1 (RECs) which include ECCAS, created in 1983
and comprising 10 member states2, six3 of which are members of the Central African Economic and
Monetary Community (CEMAC), established in 1994. The 2009-2016 Minimum Integration
Programme (MIP) is the AU’s general strategic framework for implementation of regional and
continental integration by the RECs. PARCI-ECCAS is consistent with these AU strategic guidelines
and in line with the strategic vision framework (Vision 2025) of ECCAS, adopted in 2007 "and whose
main objective is to transform the region into a haven of peace, solidarity and balanced development".
This Vision is also consistent with CEMAC’s Regional Economic Programme (REP) for 2010-2015,
whose objective is to build a competitive regional environment in order to attract substantial private
investments to growth sectors.
As concerns the Bank, it should be noted that regional integration is enshrined in its Charter and has
been part of its mandate since its creation in 1963. Its intervention in multinational operations is
defined under its Regional Integration Strategy (RIS) 2009-2012 whose second pillar seeks to "build
institutional capacity including trade facilitation, with a view to promoting regional integration and
trade in Africa". PARCI-ECCAS falls under Pillar II of the Bank’s Regional Integration Strategy in
Central Africa (RISP 2011-2015), which seeks to "build the institutional and human capacities of
RECs" with a view to ensuring (i) greater ownership of regional infrastructure programmes; and (ii)
advanced rationalization of their action especially in the harmonization of regional integration policies
and instruments. This is in line with the Bank’s 2013-2022 Long-term Strategy (LTS) which makes
regional integration the driver for promoting sustainable and inclusive growth in Africa by releasing the
potential generated by economies that are more integrated through infrastructure and regional trade.
1 SADC, ECCAS, ECOWAS, AMU, CEN-SAD, COMESA, IGAD and EAC. 2 Angola, Burundi, Cameroon, Central African Republic (CAR), Congo, Democratic Republic of Congo (DRC), Gabon, Equatorial Guinea (REG), Sao
Tome and Principe (STP) and Chad 3 Cameroon, CAR, Congo, Gabon, REG and Chad
2
1.2. Rationale for Bank’s Involvement
1.2.1 Limited infrastructure is the main constraint to more robust growth in Central Africa. The AU,
in partnership with the ECA, the Bank and the NEPAD Planning and Coordination Agency, designed a
Programme for Infrastructure Development in Africa (PIDA). This continent-wide initiative, which
relies on regional projects and programmes, will help to address the infrastructure shortage which
hampers Africa’s competitiveness on the world market. ECCAS is recognized as the REC that should
coordinate NEPAD and the Priority Action Plan of PIDA (PAP-PIDA) in Central Africa. Regional
infrastructure development is one of the two pillars of RISP. RISP highlighted the weak institutional
and human capacities of ECCAS and CEMAC, especially in the design of regional programmes as well
as the harmonization and dissemination of community standards. These constraints are evident, inter
alia, in: (i) the limited cooperation between the two institutions that affects the implementation of the
regional integration agenda; and (ii) the lack of harmonization of standards which hampers the free
flow and facilitation of transport. Furthermore, ECCAS which is recognized as the REC responsible for
coordinating NEPAD and PIDA_PAP in Central Africa, faces several institutional, human,
organizational and financial constraints that include: (i) outdated fundamental texts that are not adapted
to the current missions of the institution and to modern management; (ii) shortage of human resources
and the lack of a performance-based human resource management system; (iii) the lack of budget and
investment management following a results-based programmatic approach; and (iv) poor coordination
between headquarters and member-states. It also faces the problem of irregular payment of the
Community Integration Contribution (CIC) by certain member states.4 These structural constraints
negatively affect the efficiency, impact and visibility of its action.
1.2.2 Besides, Central Africa’s integration agenda considerably lags behind that of other RECs
(ECOWAS, COMESA, etc.). The opening of the Free Trade Area (FTA), scheduled for 2004, is still
not effective. Limited ownership of regional market instruments by national and community
administrations is reflected, inter alia, in the limited intra-regional trade within both CEMAC and
ECCAS (1% of total trade). It has also been noted that tariff and non-tariff barriers continue to hamper
trade in the region. CEMAC and ECCAS treaties and conventions contain, in their related protocols,
provisions defining community policies on trade and laying down the rules, instruments and mechanisms
of trade cooperation. Yet one of the specificities of market systems is that they are mutually exclusive
whenever their parameters are not coordinated. Without harmonization, selection of one of the regimes
will systematically exclude the instruments of ECCAS' FTA or ECCAS' Customs Union. Maintenance of
a dual trade policy (even partially) by CEMAC and ECCAS deprives economic operators and national
governments of visibility. Harmonizing standards is a prerequisite to the optimization of the Central
African market. That is why ECCAS and CEMAC currently lay emphasis on rationalization, pursuant to
the decision of the 13th Conference of ECCAS Heads of State, held in October 2007, inviting the two
RECs to "set up a Steering Committee comprising the AU, ECA and the ADB to prepare a roadmap,
defining the actions for harmonization of the integration policies and instruments of both Communities,
in order to end up with a single REC in the Central African region".5 However, the Technical Secretariat
of COPIL, which has been set up, has very limited institutional capacity and lacks the resources to prepare
the rationalization roadmap.
4 However, it should be noted that there are encouraging prospects with the decision of the Conference of Heads of State held in January 2012,
requesting the General Secretariat to apply the sanctions provided under the Treaty for non-payment of contributions. 5 13th Conference of ECCAS Heads of State and Government, Brazzaville, October 2007.
3
1.2.3 Why the Bank Group has to intervene: In accordance with AU guidelines, the Bank
contributes to the implementation of the integration strategy in Central Africa through ECCAS. Hence,
the current operation is justified for three main reasons. First of all, there is need to continue with and
complete the capacity-building actions initiated under completed or on-going Bank operations (cf.
Appendix II). It should be recalled that the first institutional support project started in 2006, at the time
when ECCAS was emerging from a long period of lethargy characterized by institutional instability,
very limited ownership by member-states and staff demobilisation due to irregular payment of salaries.
Although the results were satisfactory on the whole, the diagnosis6 conducted under PAI-SG,
confirmed by the conclusions of the EU’s 4-pillar audit,7 reveals enormous capacity-building needs that
have not yet been addressed, especially as regards review of the legal framework, monitoring of sector
policies and results-based management. Secondly, the Bank is a key partner of ECCAS as regards
capacity-building and rationalization of Central Africa’s RECs. Indeed, the project will make it
possible to continue with harmonization activities piloted by COPIL/REC, whose TORs were prepared
with joint financing from the Bank and Sub-regional Office for Central Africa of the UN Economic
Commission for Africa (ECA/SRO-CA) in 2011, focusing on the 12 priority areas of rationalization.
Lastly, this project will help to create conditions conducive to the implementation of the two RISP
pillars,8 mainly by building capacity for the implementation of regional infrastructure development
programmes featured in the PIDA-PAP. It will also make it possible to build ECCAS capacity for more
effective monitoring-evaluation of integration programmes and the harmonization of sector policies.
The analysis that led to classification of the project as a regional public good, in accordance with the
criteria for prioritizing regional operations, is presented in Annex C2 of the technical annexes. Indeed,
given its multinational character (spanning two RECs and 10 countries) and the effects of positive
externalities on other communities, the project constitutes a regional public good whose benefits will
ultimately be shared by a great number of countries.
1.3. Aid Coordination
1.3.1 Technical Annex A3 provides details of TFP regional integration operations in Central Africa.
TFP coordination in both regional organizations remains limited. There is no operational structure for
coordinating and monitoring donor operations. Nevertheless, periodic meetings between donors enable
them to exchange ideas and share information with a view to coordinating and rationalizing their
operations. Participation in the project's steering committee by TFPs (EU, ECA) involved in
institutional capacity-building will enable ECCAS to strengthen the coordination and harmonization of
its support. Furthermore, project support to the setting up of a results-based programmatic management
framework within the GS, will in the long run provide ECCAS with a tool for integrated resource
programming and, consequently, an aid coordination instrument.
6 Institutional and Operational Diagnosis Report of ECCAS, 2008 7 Accounting, Audit, Procurements and Control 8 References: ADF/BD/WP/2009/153/Rev.1
4
Table 1.1: Support of Technical and Financial Partners for ECCAS Capacity-Building (in CFA.F million) Projects ADF ACBF Status Institutional support to the General Secretariat of ECCAS (PAI-SG) 2 135 Completed in 2010 Capacity-building for the ECCAS General Secretariat (RENFOR) 1 150 Completed in 2009 Capacity-building for Central African Members of Parliament (REPAC) 750 On-going 2007-
2010 Aid Coordination Level Existence of thematic working groups No Existence of a global sector program No ADB’s role in aid coordination None
II. Project Description
2.1 Project Components
2.1.1 The project’s overall objective is to promote regional integration in Central Africa by building
ECCAS’ institutional, human and operational capacity to implement regional programmes and
harmonizing sector policies.
2.1.2 The project’s specific objectives are to: (i) build the institutional capacity of the General
Secretariat to ensure better implementation of regional programmes and greater ownership of the
regional integration agenda; and (ii) support the implementation of the rationalization process for
Central Africa’s RECs with a view to harmonizing their integration policies and instruments and
facilitating intra-regional trade. The project has three components: (i) Supporting the improvement of
the institutional framework and monitoring/evaluation of regional infrastructure development
programmes; (ii) Supporting the harmonization of regional integration policies and instruments; and
(iii) Project management and coordination. Implementing these components which are
complementarity, contributes to the achievement of the project objective. Indeed, improvement of the
organizational and operational capacities of the ECCAS General Secretariat will enable the institution
to strengthen its role of coordinating regional programmes and driving Central Africa’s integration
agenda through synergy of action with CEMAC in the area of harmonization of community policies
and standards. A summary of project components and activities is presented below:
5
Table 2.1: Project Components Components Total cost
(UA
Million)
Description of Components
1. Supporting the
improvement of the
institutional framework
and of the
monitoring/evaluation
of regional
infrastructure
development
programmes
4.50
1.1 Institutional and organizational capacity-building for the GS of ECCAS
Support to the Legal Unit and revision of texts;
Capacity-building for DISC (including support for implementation of the
gender policy)
Support for the implementation of results-based programmatic management
1.2 Building the implementation and monitoring capacity of infrastructure
projects
Support to the Surface Transport Service (roads, rail, ports)
Support to the Water and Air Transport Service
Support to the Energy Unit
Support to the Information and Communication Technology (ICT) Service
1.3 Strengthening of the regional statistics system
Support to the development of regional external trade statistics
Strengthening of the infrastructure statistics system
Establishment of a statistical and economic analysis system
Support to the preparation of a Regional Statistical Development Strategy
2. Supporting the
harmonization of
regional integration
policies and instruments
2.96
2.1 Implementation of the ECCAS/CEMAC Rationalization Programme
Studies on the harmonization of ECCAS and CEMAC trade policies
Operationalization of the ECCAS/CEMAC Joint Committee on nomenclature,
tariffs and legislation
Preparation and follow-up of the Annual Forum on Rationalization of the
RECs in CA
Validation, publishing and dissemination of the Regional Customs Code
Rationalization Communication Plan and the ECCAS/CEMAC exchange and
consultative mechanism
2.2. Institutional support to the COPIL Technical Secretariat
Logistical support
Technical assistance for the operationalization of COPIL TS
Human resources capacity-building
Operational support
2.3 Strengthening of cooperation between the GS of ECCAS, member-states and
the Institutions
Support to the preparation and implementation of the Communication Plan Study of the organizational framework and establishment of mechanisms to
speed up collection of the Community Integration Contribution (CICI) from member
states
Awareness-raising programme for non-state actors (CSOs and private sector)
in the States
3. Management and
coordination 0.77 3.1 Management
3.2 Audit
6
2.1.3 Technical Annex B2 provides the detailed costs of project activities by component.
Furthermore, Technical Annex C1 gives a detailed description of project activities, indicating for each
sub-component: (i) the context and challenges to be addressed; (ii) the actions implemented by the
project; and (iii) expected results.
2.2 Technical Solutions Retained and Other Alternatives Explored
2.2.1 Although the causes of ECCAS’ human and financial resource constraints certainly stem from
inadequate management mechanisms, they are also structural. To address these difficulties, institutional
reforms are necessary. At the same time, the institution badly needs capacity-building to be able to
implement its integration agenda in the priority domains such as infrastructure development,
harmonization of sector policies and regional trade facilitation. Hence, the approach adopted by the
project entails tackling structural problems by reviewing the institutional framework (revision of the
fundamental texts, establishment of a strategic framework and a results-based medium- and long-term
action plan) and providing technical assistance that can build the institution’s existing capacity so that
it can implement its work programme in key areas (infrastructure, trade, statistics, programming).
Table 2.2: Alternative Solutions Considered and Reasons for their Rejection Alternative Solutions Brief Description Reasons for Rejection Establishment of a young
professionals programme To address the shortage of human resources
at the GS of ECCAS, there were plans to
set up a young professionals programme
Solution not sustainable without an adequate human
resource management policy
Include, within project, support
to certain specialized entities
(COMIFAC, COBAC)9.
Under RISP, there are plans to build the
institutional capacities of ECCAS, CEMAC
and COMIFAC
The project targets the rationalization of CEMAC and
ECCAS. Including other entities could create the risk of
dissipation of Bank intervention without tangible
results. Key support could be envisaged directly for
these entities at the proper time.
2.3 Project Type
2.3.1 PARCI-ECCAS is an institutional support project which, through its regional dimension and
its objectives, contributes to the promotion of a Regional Public Good. Indeed, it fulfils the conditions
defined in the Strategic and Operational Framework for Regional Operations (2008) as well as the
seven eligibility criteria for Regional Public Goods (cf. Annex C2). The choice of an operation in the
form of institutional support is justified by the nature of the planned activities (technical assistance,
studies, training) which, furthermore, will be implemented in several institutions. Through institutional
support, the Bank also hopes to strengthen synergies with the support of other TFPs involved in the
capacity-building of structures responsible for implementing the institutional reforms targeted by this
project.
2.4 Project Cost and Financing Arrangements
2.4.1 The total project cost, including customs duties and taxes, is estimated at UA 8.23 million (or
approximately CFA.F 6.62 billion at the exchange rate of September 2012), comprising UA 5.04
million in foreign exchange (61.24%) and UA 3.19 million in local currency (38.76%). The costs
include a 2% provision for physical contingencies and a 3% provision for price escalation per year for
expenditure in both foreign exchange and local currency. A detailed table of costs is presented in
Technical Annex B2 of this report. The table below provides a summary of total project costs by
component.
9 Banking Commission of Central Africa
7
Table 2.3: Estimated Costs by Component
COMPONENTS USD thousands Total Cost in UA thousand % F.E.
F.E. L.C. Total F.E. L.C. Total 1. Supporting the improvement of the institutional framework and monitoring/evaluation of regional infrastructure development
programmes Institutional and organizational capacity-building for the GS 1 010.5 644.6 1 655.0 663.9 423.5 1 087.4 61.06%
Building the implementation and monitoring capacity of infrastructure projects 2 217.1 740.8 2 957.9 1 456.7 486.7 1 943.4 74.96%
Strengthening of the regional statistics system 1 351.2 556.8 1 908.0 887.8 365.8 1 253.6 70.82%
Baseline cost Component I 4 578.8 1 942.1 6 520.9 3 008.4 1 276.0 4 284.4 70.22%
2. Supporting the harmonization of regional integration policies and instruments Implementation of the ECCAS/CEMAC Rationalization Programme 1 274.2 1 601.0 2 875.2 837.2 1 051.9 1 889.1 44.32%
Institutional support to the COPIL Technical Secretariat 544.5 88.2 632.7 357.7 57.9 415.7 86.06%
Strengthening of coordination between ECCAS, member States
and other institutions 559.6 224.4 784.0 367.7 147.4 515.1 71.38%
Baseline cost Component 2 2 378.3 1 913.6 4 291.9 1 562.6 1 257.3 2 819.9 55.41%
3. Management and Coordination Project Management 239.4 765.8 1 005.1 157.3 503.1 660.4 23.8%
Audit 105.0 0.0 105.0 69.0 0.0 69.0 100.0%
Baseline cost Component 3 344.4 765.8 1 110.1 226.3 503.1 729.4 31.02%
TOTAL BASE COST 7 301.4 4 621.5 11 922.9 4 797.2 3 036.4 7 833.6 61.24%
Physical Contingencies 146.0 92.4 238.5 95.9 60.7 156.7 61.24%
Price escalation 223.4 141.4 364.8 146.8 92.9 239.7 61.24%
TOTAL PROJECT COST 7 670.9 4 855.3 12 526.2 5 040.0 3 190.0 8 230.0 61.24%
NB: The exchange rates used are indicated in the introduction to this report (page (i)).
2.4.2 Table 2.4 presents estimated project costs by expenditure category, while Table 2.5 presents
an analysis of sources of financing and Tables 2.6 and 2.7 provide the expenditure schedule by
expenditure category and by component.
Table 2.4: Project Cost by Expenditure Category, (in UA thousand) EXPENDITURE CATEGORIES F.E. L.C. Total % F.E.
GOODS 199.6 0.0 199.6 100.00%
SERVICES 4187.5 2278.6 6466.1 64.76%
OPERATION 410.0 757.9 1167.9 35.11%
TOTAL BASE COST 4 797.2 3036.4 7833.7 61.24%
Physical Contingencies 95.9 60.7 156.7 61.24%
Inflation 146.8 92.9 239.7 61.24%
TOTAL COMPONENT COST 5 040.0 3 190.1 8 230.0 61.24%
Table 2.5: Sources of Financing [amounts in UA million]
Category/Sources of Financing ADF ECCAS Total UA
million % UA
million % UA
million 1. Supporting the improvement of the institutional framework and of the
monitoring/evaluation of regional infrastructure development
programmes 3.94 87% 0.57 13% 4.50
1. Supporting the harmonization of regional integration policies and instruments 2.53 85% 0.43 15% 2.96
3. Project management 0.53 70% 0.23 30% 0.77
Total 7.00 85% 1.23 15% 8.23
2.4.3 The project will be co-financed by an ADF grant of UA 7 million (85% of the total cost) and
by ECCAS counterpart contribution of UA 1.23 million, or 15% of the project cost. The counterpart
funds will earmarked for procurement of equipment and operational expenses.
8
Table 2.6: Expenditure Schedule by Expenditure Category, [in UA thousand]
EXPENDITURE CATEGORIES 2013 2014 2015 2016 Total
GOODS 124.2 78.7 3.5 3.5 209.7
SERVICES 2 050.0 2 763.0 1 478.4 501.9 6 793.3
OPERATION 186.2 487.9 321.5 231.4 1 227.0
TOTAL 2 360.3 3 329.6 1 803.3 736.7 8 230.0
Table 2.7: Expenditure schedule by component (in UA thousand)
COMPONENTS 2013 2014 2015 2016 Total
1. Supporting the improvement of the institutional framework and of the
monitoring/evaluation of regional infrastructure development
programmes 1 012.9 2 146.2 1 140.5 201.6 4 501.2
1. Supporting the harmonization of regional integration policies and instruments 1 109.1 988.2 495.5 369.8 2 962.6
3. Project management 238.4 195.1 167.4 165.3 766.3
TOTAL COST 2 360.3 3 329.6 1 803.3 736.7
8 2
3
0
.
0
2.5 Project Target Area and Beneficiaries
2.5.1 The project area comprises the territory of ECCAS member-states. Indeed, the activities of
PARCI-ECCAS will concern the services of the General Secretariat, but also the Technical Secretariat
of COPIL-CER-AC, the CEMAC Commission in Bangui (CAR), the Regional Coordinations of
NEPAD, ECCAS focal points in the countries, customs services and the Ministries in charge of trade
and regional integration in the 10 ECCAS member states.
2.5.2 The main direct beneficiaries of the Project are: (i) the GS of ECCAS; (ii) COPIL TS; (iii) the
CEMAC Commission that will be involved in studies and other rationalization activities to be
conducted under the second component of the project. The indirect beneficiaries of the project are the
people of these countries, women, youths, the private sector and especially SMEs and the informal
sector that will operate within a more favourable statutory framework of regional trade and certainly
benefit from basic infrastructure. Indeed, businesses could benefit from the growth opportunities in
intra-community trade that ensue from the trade rationalization and facilitation activities supported by
the project through unified approval procedures, a harmonized regional customs code and more
efficient market information systems.
2.6 Participatory Process for Project Identification, Design and Implementation
2.6.1 During project identification, a consultative process was established through exchanges
between the ADB, the relevant ECCAS departments and donors. These consultations continued during
preparation and appraisal missions to ensure greater ownership of the project. The project appraisal
mission held discussions with the TS of COPIL-CER-AC in Yaoundé and the CEMAC Commission in
Bangui. Similarly, the ECA contributed to project design through review of the concept note and
discussions that the project team held with BSR-CEA in Yaoundé at appraisal. The participatory
process will be maintained during project implementation through the steering committee (including
civil society) and internal mechanisms for consultations with States. The project supports the revision
9
of ECCAS fundamental texts that will be adopted in accordance with the applicable decision-making
process of ECCAS (after review by the Internal Committee of the GS, the Member-States Committee
of Experts, Council of Ministers, Conference of Heads of State). The project will also support
communication and awareness-raising actions directed at member-states in order to ensure greater
ownership of integration objectives in the countries. The project contributes to building the capacity of
the department in charge of infrastructure (DIPEM), and social and trans-border migration issues have
been factored into the design of regional infrastructure projects.
2.7 Consideration of Bank Group Experience and Lessons Learnt Reflected in Project
Design
2.7.1 Annex B1 in the technical annexes analyses the main lessons learnt from previous projects.
The completion report10 of PAI-SG shows that the project has achieved generally satisfactory results
with a score of 3 out of 4. Despite its implementation delays, the project has led to, inter alia, the
conduct of an institutional and operational diagnostic study of ECCAS and the adoption of a new
organization chart, the definition and implementation of priority programme activities in the areas of
NEPAD and statistics, an update of the accounting for FY 2008-2009 as well as the procurement of
equipment. The abovementioned diagnostic study as well as the study on Audit 4 pillars conducted by
European Union in 2010 clearly demonstrated that revision of ECCAS fundamental texts (Treaty, Staff
Regulations, Internal Rules and Financial Rules) was indispensable in order to ensure the effective
operationalization of the new organization chart as well as the adoption of a governance system that is
consistent with international accounting standards and results-based management.
2.7.2 The main lesson learnt from the project is the need to factor into the Bank’s future operations,
the fact that ECCAS has weak project implementation capacity due to its inadequate human resources.
Furthermore, in 2010 NEPAD’s Infrastructure Project Preparation Facility (IPPF) spent USD 1,098,000
to finance an institutional support project for the implementation and monitoring of the Central African
Consensual Transport Master Plan (PDCT-AC) by ECCAS. This project, which is being completed
(46% disbursement rate), contributes to the implementation actions of PIDA’s Priority Action Plan in
Central Africa. Lastly, the lessons learnt from review of the Bank’s portfolio of multinational
operations, conducted in 2010, highlighted the need to: (i) continue with efforts to build RECs’
capacities to improve programme implementation and design sustainable resource mobilization
mechanisms; (ii) strengthen coordination with other TFPs by focusing on joint financing; (iii) focus on
selectivity to generate a greater impact in the development of the region; and (iv) pursue and step up
dialogue with countries to ensure greater ownership of multinational projects. The lessons learnt from
the previous operation and from portfolio review were factored into project design. Indeed, a selective
approach was used to choose capacity-building actions for RECs, supported by participatory dialogue
with all stakeholders that will continue during implementation. Furthermore, discussions with other
TFPs led to better targeting of operations in order to avoid duplication and overlap.
2.8 Key Performance Indicators
2.8.1 The project’s key performance indicators are presented in the logical framework on Page viii.
The main expected achievements and outcomes of the project are:
10 References ADF/BD/IF/2011/124
10
Box 1: Key Performance Indicators Impact indicator
The economic growth rate of the CEMAC area rises from 4.5% in 2011 to 5.3% in 2020.
Impact indicators
The implementation rate of regional projects coordinated by the GS of ECCAS rises from 5% in 2010 to 30% in 2016.
The share of intra-community trade in total regional trade increases from 1% in 2010 to 2.5% in 2016.
Output indicators :
The texts (Treaty, IR, SR and FR) are revised in 2015
The GS of ECCAS has a Results-based Strategic Management Plan in 2016.
The 12 projects of the PIDA-PAP are in the S2 level of preparation (feasibility studies done) including at least 4
projects in the S4 stage (implemented) in 2016. CEMAC and ECCAS end up with one harmonized CET at the end of 2015. CEMAC and ECCAS use a single harmonized Regional Customs Code from 2016.
16 COPIL TS experts, including at least 4 women, are trained during the 2014-2015 period.
CIC payments arrears decline by 30% from 2011 to 2015.
III. Project Feasibility
3.1 Economic and Financial Performance
3.1.1 Since this is an institutional support project, economic and financial analyses do not apply.
However, it should be noted that due to the building of internal managerial capacity, the project could
contribute to better resource management by ECCAS and more judicious use of such resources.
3.2 Environmental and Social Impact
Environment
3.2.1 The project has no direct negative environmental impact since its activities are limited to
training, technical assistance, studies and the procurement of logistical resources including small-sized
office automation and IT equipment. Indeed, the project was classified under category 3 in accordance
with Bank Guidelines. Nevertheless, sub-component 1.2 of this project helps to build the capacity of
the department in charge of infrastructure (DIPEM). The environmental component is taken into
account in the preparation and implementation of various regional infrastructure projects. The Bank,
through the Congo Basin Ecosystems Conservation Support Programme (PACEBCo), supports
conservation of the second largest tropical forest in the world after the Amazon. This programme
should provide the answers to the steady degradation of this forest and climate change. The programme
duration is 5 years from March 2009 and its total cost is estimated at UA 37.28 million, with an ADF
grant financing of UA 32 million. In conclusion, through capacity-building, this project complements
the various forms of support provided by the Bank in response to environmental degradation and
climate change.
Climate Change
3.2.2 Project activities, focused on human and institutional capacity-building, have no negative
impact on the environment or on the climate change process. Nevertheless, the Bank, through the
Congo Basin Ecosystems Conservation Support Programme (PACEBCo) supports regional initiatives
to combat climate change.
11
Gender
3.2.3 The vision that defines ECCAS’ gender policy is that of a community in which men and
women enjoy equal rights, develop their skills and thus contribute as equal partners to the building of a
fair and prosperous society for all and the sustainable development of Central Africa. The
establishment, within the ECCAS General Secretariat, of an adequate institutional framework endowed
with the requisite authority as well as human and material resources is necessary to achieve gender
policy objectives. Within this framework, the project supports capacity-building for the Department of
Social and Cultural Integration (DISC) responsible for preparing and implementing ECCAS's gender
policy. Supported activities relate to: (i) the preparation of the gender policy action plan; (ii) training on
gender issues in regional infrastructure projects; and (iii) support to validation workshops of the Gender
Action Plan. The training and sensitization component of the project will affect 40% of women. The
project also supports measures that ensure efficient implementation of regional infrastructure projects
to generate jobs especially for women and women’s groups. Ultimately, women and youths who are
mainly involved in trade will see their incomes rise owing to increased marketing of agricultural and
artisanal products in the ECCAS area after the institution of the free trade area and the application of a
single customs code. In summary, project actions tend to improve the living conditions and well-being
of women and youths.
Social
3.2.4 The project covers 10 countries of the ECCAS area with an estimated total population of 137
million inhabitants. On average, poverty affects 63% of the population. The retained actions will lead
to more efficient coordination in the implementation of PIDA action plan projects and, ultimately, the
implementation of regional infrastructure projects (which will strengthen intra-regional trade and the
supply of public services). The implementation rate of regional projects coordinated by the GS of
ECCAS will rise from 5% in 2010 to 30% in 2016. Meanwhile, the harmonization of policies and trade
policy instruments (free trade area, common customs code) will reinforce intra-community trade and
generate an increase in customs revenue in the countries of the area. The share of intra-community
trade in total regional trade is expected to rise from 1% in 2010 to 2.5% in 2016. This will help raise
the living standards of the people.
3.2.5 In the longer-term, nationals of ECCAS member countries (including those considered to be
fragile States), women, youths, private sector will certainly benefit from inclusive growth generated by
the development of basic infrastructure and an environment which is more conducive to business,
thanks to the harmonization of trade policies at the regional level. Indeed, project activities will help to
generate employment including for women and youths. The beneficiary population is estimated at
approximately 27 million (20% of the population in countries of the ECCAS area). This operation will
contribute to the achievement of certain MDGs in particular combatting poverty by improving the
living conditions of the people and creating jobs. Ultimately, the benefits will be shared by a large
number of countries within the ECCAS area and in other regions, through the positive externalities of
successful integration.
Involuntary Resettlement
3.2.6 The project will not lead to displacement of communities.
12
IV. Implementation
4.1 Implementation Arrangements
4.1.1 Institutional arrangements: The institutional framework of project management is described in
detail in Annex B3 of the technical annexes in this report. According to the terms of the Paris
Declaration on the harmonization and alignment of project management on national systems, the
project implementation organ is the ECCAS General Secretariat. A Project Team (PT) will be
established within the GS that will comprise a coordinator, an accountant and support staff. The
Coordinator will be an expert from ECCAS with experience in project management. He will be
seconded for the duration of the project and placed under the direct responsibility of the GS. The PT
will be reinforced with technical assistance recruited on a competitive basis with ADF resources and
comprising: a procurements expert, a monitoring/evaluation expert, a training expert and an
administrative and financial officer (AFO). These experts will also be responsible for training their
counterparts, who will be experts designated by the PBARH (procurements, financial management,
monitoring-evaluation, human resource management) Department.
4.1.2 A Project Steering Committee (PSC) will be set up to serve as a consultative and monitoring
body for the project and to strengthen coordination. It will comprise representatives from the ECCAS
General Secretariat, the CEMAC Commission, the Technical Secretariat of COPIL, UNECA and a
regional civil society organization in Central Africa. It will be chaired by the ECCAS Secretary
General or his representative. The PSC shall meet twice a year and whenever necessary to ensure
consultation between stakeholders and project monitoring.
4.1.3 Procurements: All goods, works and services financed by the ADF shall be procured in
accordance with the Bank’s relevant rules and procedures on procurement (May 2008 edition, revised
in July 2012), or where necessary, the Bank’s rules and procedures for the recruitment of consultants
(May 2008 edition, revised in July 2012), using the Bank’s standard bidding documents. The project
team, placed under the supervision of the Secretary General, shall be responsible for procurements and
will be reinforced with one procurement expert familiar with the procurement procedures of the ADF
or of other TFPs. A draft procurement plan will be prepared by the Project Team and submitted to the
ADF for review and approval prior to the signing of the Grant Agreement. Details of the project’s
procurement arrangements are presented in Technical Annex B5 of this report.
4.1.4 Disbursement: The ADF grant will be disbursed according to the Bank’s applicable
procedures. The direct payment, repayment and special account methods will be used to finance
activities. A special account will be opened in a commercial bank and used to finance operating
expenses and staff allowances. Goods, services and audit fees will be defrayed by direct payment.
Replenishment of the special account shall be subject to justification of 50% of the last advance and
100% of previous advances. Proof of the opening of the special account will be a condition precedent
to first disbursement.
4.1.5 Financial Management and Audit: The overall project financial management risk was deemed
to be "high" and should be brought down to "substantial" with the satisfactory application of mitigation
measures (reference Technical Annex B4). The PT will be responsible for the financial, administrative
and accounting management of the project. The fiduciary team will be led by the AFO. It shall keep the
accounting ledgers of project activities and ensure that annual financial statements are produced on a
timely basis and in accordance with the accounting principles of OHADA (Organization for the
13
Harmonization of Business Law in Africa) – SYSCOHADA. The ECCAS General Secretariat will
prepare a work programme and an annual activity budget which should be submitted to the Bank,
together with annual progress reports and financial statements. It will ensure that the project's
administrative, financial and accounting procedures manual to be approved by the Bank, is prepared
and approved not later than three months after loan effectiveness (and prior to any disbursements). The
accounting software procured by ECCAS will be configured for project needs and the accountant will
be trained to use it. The annual audit of project accounts will be conducted by an approved independent
accounting firm. ECCAS must submit the audit report for project accounts not later than six months
after the end of each fiscal year.
4.2 Monitoring
4.2.1 The project’s physical implementation is expected to cover a period of 48 months, from
January 2013 to December 2016. This schedule is deemed reasonable, given the scope of activities to
be implemented and the average implementation deadlines for multinational operations. Furthermore,
the use of project funds to recruit a procurements expert and a monitoring/evaluation expert should
make it possible to reduce procurement deadlines and ensure appropriate monitoring of the
implementation of project components. The procurement of monitoring-evaluation software and the
training of project staff are also planned. A monitoring/evaluation system will be established, including
easily quantifiable performance indicators, collection of baseline situation data as well as measurement
of project progress towards attainment of intermediate targets and impacts.
4.2.2 The Project Team will be responsible for monitoring project implementation using logical
framework indicators. As soon as the Grant Agreement becomes effective, a launching mission will be
organized to train PT officials in Bank procedures. Supervision missions involving Bank offices in
Gabon, Cameroon and CAR will be organized at least twice a year. Quarterly progress and annual
reports will also be prepared and transmitted to the Bank. The key indicative monitoring stages are
presented in the table below:
Table 4.1: Monitoring Stages/Feedback Loop Schedule Stages Monitoring Activities/Feedback Loop
Dec. -12 Grant approval by the Board Notification to the ECCAS General Secretariat Jan-13 Grant effectiveness Signature of grant agreement
Jan-13 GPN and SPN UN Development Business; national and regional newspapers
March -13 Fulfilment of conditions precedent to 1
st
disbursement Proof of fulfilment of conditions submitted to the Bank
March -13 Launching of project Training of PT; Launching of first activities, preparation of
work programme.
2013-2016 Implementation of activities Quarterly and annual progress reports / audit reports
Feb-15 Mid-term Review Mid-term review reports Dec. -16 Last disbursement Closing audit reports
March 17 Project Completion Completion report
4.3 Governance
4.3.1 The risks faced by the project management team relate to procurement decisions, the use of
project assets and the selection of persons for training abroad or capacity-building. These risks will be
mitigated by preparing a detailed procurement plan, establishing sound processes for contractors as
well as rigorous selection of participants and applying the Bank’s standard rules and guidelines. More
14
advanced training will be provided to project staff members to ensure that they are fully informed on
the requirements and regulations. Compliance with these control mechanisms will be reviewed during
supervision missions.
4.3.2 As concerns financial management of the project, the executing organ shall keep separate
accounts for the project using software of international repute. This will make it possible to keep cost
accounting and produce reports that show expenditure by component, category and financing source.
Project accounts will be audited annually by a firm recruited for that purpose. The financial statements
and audit reports will be submitted to the ADF within six months following the close of the accounting
period.
4.4 Sustainability
4.4.1 Project implementation will make it possible to enhance the institutional efficiency of the
General Secretariat. The result will be a significant improvement in the design and monitoring of
regional infrastructure development programmes, which is one of the major components of the
integration agenda, given its expected impact on the circulation of goods and persons and on the quality
and cost of communications. The project will also make it possible to factor into these programmes, the
key concerns of member-state governments in the area of capacity-building for all stakeholders
involved in monitoring/evaluation (enhanced regional statistics system) and the harmonization of
policies. Furthermore, emphasis will be laid on the harmonization of CEMAC and ECCAS actions with
a view to increasing cooperation and synergies between these two institutions in order to reach the
common goal of creating a Central African common market as a prelude to the continental common
market; a target set for 2020 by the AU in MIP. Attainment of project results will consequently have an
obvious impact on improving the visibility of ECCAS among the peoples and authorities in Member
States, which could translate into a strong attachment to the reaffirmed political will to implement the
integration agenda in Central Africa.
4.4.2 The technical assistance to be provided and the training of experts from beneficiary
institutions will enhance the prospect of sustaining project impact. Besides, the sustainability of project
impact remains largely dependent on reform of the fundamental texts governing the functioning of the
General Secretariat; aimed at developing skills mainly through the creation of a legal and regulatory
framework as well as planning and management tools that enhance the efficiency of institution experts
in the exercise of their duties. Ultimately, the reform will result in the establishment of strategic
planning, a medium-term budgetary framework and staff regulations that lay emphasis on performance-
based career management, skills and training and continuous retraining of staff that will promote the
stability of experts. Similarly, the project envisages recruiting junior experts, with ECCAS counterpart
funds, who will be counterparts trained by technical assistance financed by the ADF grant. This activity
will enable the various structures to have the minimum capacity to define, implement and monitor
sector policies, thereby become an important factor of sustainability. Lastly, as concerns recurrent costs
generated by the project, it should be noted that equipment purchases only account for 3% of the total
project budget. The maintenance costs for this equipment, approximately UA 0.031 million per year (or
0.35% of ECCAS revenue), could easily be borne by the Institution.
15
4.5 Risk Management
4.5.1 The table below presents a summary of residual risks (other than those related to governance
and sustainability) as well as mitigation measures.
Table 4.2: Risks and Mitigation Measures Risks Level Mitigation Measures 1. Low level of ownership by member
States as reflected in the delays in the
payment of the CIC and difficulties in
holding summits
High The revival of national coordination teams for the
harmonization of RECs and the facilitation of intra-regional
trade, will enable to ECCAS to increase its visibility
substantially in other to arouse the greatest possible interest
among the highest ranking authorities in member States. 2. The weakness of national structures
responsible for regional integration
undermines the smooth conduct of
projects.
High The future creation of the National Coordinations of NEPAD
and support scheduled under this project should facilitate intra-
regional trade and increase the presence and visibility of the
GS. 3. Bottlenecks in the decision-making
process could delay revision of the legal
framework and the implementation of
necessary reforms.
High Close monitoring of the project as well as the technical
assistance and high-level dialogue provided by the Bank during
ECCAS summits could speed up the process of reviewing
ECCAS texts. 4. Weak fiduciary framework High The Bank’s procedures will be used. The technical assistance
provided under the project will help to strengthen the financial
management system.
4.5.2 The above analysis shows that the project presents relatively high risk levels. Nevertheless, the
achievements of ECCAS and the regional context argue in favour of Bank support to the project, given
the significant results expected in terms of institutional efficiency and ownership by member countries
through this operation and on-going NEPAD projects and considering the Bank’s commitment to
support the development of RECs within the framework of its mandate and its regional integration
strategy.
4.6 Knowledge Development
4.6.1 Implementation of this project will lead to the development of several types of knowledge,
including: (i) capacities to analyses and adapt the legal framework of a REC to an institutional
framework that is more compliant with international standards of administrative and financial
governance; (ii) the use of statistics to monitor the construction of regional infrastructure in an
environment characterized by endemically weak national systems; (iii) the definition of a harmonized
trade policy between CEMAC and ECCAS, two RECs whose respective domestic markets are at
different stages of liberalization; (iv) preparation of strategic plans and the introduction of results-based
programmatic management in an organization with a pyramidal structure and a high concentration of
decision-making powers at the top. Practices will be disseminated within the two RECs and Member
States through validation and dissemination of the studies conducted, the use of developed software,
procedures manuals and training sessions that will be organized under the project. This knowledge will
be acquired through processes involving production of the following reports: reports of technical
assistants, activity reports prepared by the executing agency, supervision reports and the project
completion report. These reports will also be disseminated within the Bank.
16
V. Legal Framework
5.1 Legal Instrument
A Grant agreement will be signed between the ADF and the Economic Community of Central African
States (ECCAS) on the ADF resources, for a maximum amount of 7 million UA.
5.2 Conditions Associated with Fund Intervention
o Grant effectiveness conditions:
Grant effectiveness shall be subject to the signature of the Grant Agreement between the Bank, the
ADF and the ECCAS General Secretariat.
o Conditions precedent to first disbursement
In addition to effectiveness of the Grant Agreement, the first disbursement of grant resources shall be
subject to fulfilment by the Donee of the following specific conditions to the satisfaction of the Fund:
(i) Provide evidence of the opening of a special account in foreign exchange in the name of
the project in a bank acceptable to the Fund, to receive grant resources (§ 4.1.4);
(ii) Provide evidence of the appointment of a Project Coordinator whose qualifications and
experience shall have been previously approved by the Fund (§ 4.1.1);
(iii) Provide evidence of the preparation of a manual of administrative, financial and
accounting procedures for the project which shall have been previously approved by the
Fund (§ 4.1.5); and
(iv) Provide evidence of the recruitment of an administrative and financial manager for the
project whose qualifications and experience shall have been considered satisfactory by
the Fund (§ 4.1.5).
5.3 Compliance with Bank Policies
This project complies with all the Bank’s applicable policies.
VI. Recommendation
Management recommends that the Board of Directors approve a proposed grant of UA 7.00 million to
the Economic Community of Central African States (ECCAS) to finance the Institutional Capacity
Building Support Project of ECCAS (PARCI-ECCAS) subject to the conditions stipulated in this
report.
1
Appendix I: Comparative socio-economic indicators of ECCAS
Year
Central
African
Republic
Africa
Develo-
ping
Countries
Develo-
ped
Countries
Basic Indicators
Area ( '000 Km²) 2011 623 30 323 80 976 54 658Total Population (millions) 2011 4,5 1 044,3 5 733,7 1 240,4Urban Population (% of Total) 2011 39,2 40,4 45,5 75,4Population Density (per Km²) 2011 7,2 36,1 59,9 36,5GNI per Capita (US $) 2010 470 1 549 3 304 38 657Labor Force Participation - Total (%) 2011 69,5 74,7 65,0 60,4Labor Force Participation - Female (%) 2011 46,7 42,5 49,2 50,2Gender -Related Dev elopment Index Value 2007 0,354 0,502 0,694 0,911Human Dev elop. Index (Rank among 187 countries) 2011 179 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population) 2008 62,8 40,0 22,4 ...
Demographic Indicators
Population Grow th Rate - Total (%) 2011 1,9 2,3 1,3 0,4Population Grow th Rate - Urban (%) 2011 2,6 3,4 2,3 0,7Population < 15 y ears (%) 2011 40,1 40,4 28,7 16,5Population >= 65 y ears (%) 2011 4,0 3,4 5,9 16,2Dependency Ratio (%) 2011 78,9 78,1 53,0 48,6Sex Ratio (per 100 female) 2011 97,1 99,5 103,4 94,6Female Population 15-49 y ears (% of total population) 2011 24,4 24,4 26,2 23,6Life Ex pectancy at Birth - Total (y ears) 2011 48,4 57,7 77,7 67,0Life Ex pectancy at Birth - Female (y ears) 2011 50,0 58,9 68,9 81,1Crude Birth Rate (per 1,000) 2011 34,7 34,5 21,1 11,4Crude Death Rate (per 1,000) 2011 16,0 11,1 7,8 10,1Infant Mortality Rate (per 1,000) 2011 98,6 76,0 44,7 5,4Child Mortality Rate (per 1,000) 2011 160,4 119,5 67,8 7,8Total Fertility Rate (per w oman) 2011 4,5 4,4 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 890,0 530,7 230,0 13,7Women Using Contraception (%) 2007-09 19,0 28,6 61,2 72,4
Health & Nutrition Indicators
Phy sicians (per 100,000 people) 2007-09 8,0 57,8 112,0 276,2Nurses (per 100,000 people)* 2007-09 41,0 134,7 186,8 708,2Births attended by Trained Health Personnel (%) 2009 43,7 53,7 65,3 ...Access to Safe Water (% of Population) 2010 67,0 65,7 86,3 99,5Access to Health Serv ices (% of Population) 2007-09 ... 65,2 80,0 100,0Access to Sanitation (% of Population) 2010 34,0 39,8 56,1 99,9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2009 4,7 4,3 0,9 0,3Incidence of Tuberculosis (per 100,000) 2010 319,0 241,9 150,0 14,0Child Immunization Against Tuberculosis (%) 2010 74,0 85,5 95,4 ...Child Immunization Against Measles (%) 2010 62,0 78,5 84,3 93,4Underw eight Children (% of children under 5 y ears) 2007-09 21,8 30,9 17,9 ...Daily Calorie Supply per Capita 2007 1 986 2 462 2 675 3 285Public Ex penditure on Health (as % of GDP) 2009 1,6 2,4 2,9 7,4
Education Indicators
Gross Enrolment Ratio (%)
Primary School - Total 2011 94,1 101,4 107,8 101,4 Primary School - Female 2011 79,2 97,6 105,6 101,3 Secondary School - Total 2011 18,0 47,5 64,0 100,2 Secondary School - Female 2011 12,8 44,3 62,6 99,8Primary School Female Teaching Staff (% of Total) 2010 14,3 44,3 60,7 81,7Adult literacy Rate - Total (%) 2010 56,0 67,0 80,3 98,4Adult literacy Rate - Male (%) 2010 69,3 75,8 86,0 98,7Adult literacy Rate - Female (%) 2010 43,2 58,3 74,9 98,1Percentage of GDP Spent on Education 2010 1,2 4,6 4,1 5,1
Environmental Indicators
Land Use (Arable Land as % of Total Land Area) 2009 3,1 7,6 10,7 10,8Annual Rate of Deforestation (%) 2007-09 0,1 0,6 0,4 -0,2Forest (as % of Total Land Area) 2010 36,3 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,1 1,1 2,9 12,5
Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :
UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.
Note : n.a. : Not Applicable ; … : Data Not Available.
COMPARATIVE SOCIO-ECONOMIC INDICATORS
Central African Republic
June 2012
0
20
40
60
80
100
120
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
Infant Mortality Rate( Per 1000 )
Central African Republic Africa
0
200
400
600
800
1000
1200
1400
1600
1800
20
02
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
GNI Per Capita US $
Central African Republic
0,0
0,5
1,0
1,5
2,0
2,5
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
Population Growth Rate (%)
Central African Republic
Africa
111213141516171
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
Life Expectancy at Birth (years)
Central African Republic
Africa
Appendix II: Table of the Bank Group’s Portfolio of Multinational Operations in Central Africa as of 30 June
2012 (in UA million)
Sector/Dpt Project Name Approval
Date
Closing
Date
ADB
Amount
ADF Amount TOTAL
ADB+ADF
Amount
Disbursement
Disbursemen
t rate.
AverageAge
WATER AND SANITATION
AWTF ECCAS REGIONAL WATER SUPPLY 09/02/2009 12/30/2013 0.00 1 173 439.24 1 173 439.24 566 204.95 48% 2.8
ENERGY
ONEC STUDY ON INGA AND RELATED
CONNECTIONS
04/30/2008 12/31/2008 0.00 9 510 000.00 9 510 000.00 4 965 433.67 52% 4.1
ONEC NELSAP INTERCONNECTION PROJECT-DRC 12/31/2014 0.00 27 620 000.00 27 620 000.00 66 797.70 0% 3.6
0.00 37 130 000.00 37 130 000.00 5 032 231.37 14% 3.8
TRANSPORT
OITC.1 COSCAP PROGRAMME IN WCA (CAPACITY
BUILDING)
04/27/2005 12/31/2012 0.00 4 600 000.00 4 600 000.00 1 769 160.00 38% 7.2
OITC.1 CAR- TRANSPORT FACILITATION 07/05/2007 12/31/2011 0.00 27 800 000.00 27 800 000.00 20 986 069.90 75% 5.0
OITC.1 CEMAC – TRANSPORT FACILITATION 07/05/2007 12/31/2011 0.00 14 000 000.00 14 000 000.00 1 289 587.21 9% 5.0
OITC.1 CAMEROON – TRANSPORT FACILITATION 07/05/2007 12/31/2011 0.00 48 000 000.00 48 000 000.00 32 852 323.76 68% 5.0
OITC.1 CHAD – TRANSPORT FACILITATION 07/05/2007 12/31/2011 0.00 19 000 000.00 19 000 000.00 13 153 484.58 69% 5.0
OITC.1 BAMENDA-MAMFE-EKOK-MFUM-ABAKALIKI
ROAD-
03/31/2009 12/31/2015 0.00 204 800
000.00
204 800
000.00
58 096 650.48 28% 3.7
OITC.1 CAMEROON/GONGO: KETTA-DJOUM ROAD 09/25/2009 12/31/2018 0.00 121 170
000.00
121 170
000.00
15 826 065.70 13% 2.8
OITC.1 STUDY ON KINSHASA- BRAZZAVILLE
BRIDGE
12/03/2008 0.00 5 000 000.00 5 000 000.00 1 526 320.47 31% 3.5
ONRI CENTRAL AFRICA BACKBONE CEMAC 12/08/2008 12/31/2011 308 849.51 0.00 308 849.51 262 522.08 85% 3.4
308 849.51 444 370
000.00
444 678
849.51
145 762
184.18
33% 4.5
PRIVATE SECTOR
OPSM3 RASCOM TELECOMMUNICATION SATELLITE 07/24/2007 07/01/2010 33 018
992.52
0.00 33 018 992.52 27 483 792.96 83% 5.0
AGRICULTURE
OSAN4 LAKE TANGANYIKA DEVELOPMENT
PROJECT (DRC)
11/17/2004 07/31/2012 0.00 11 750 000.00 11 750 000.00 4 358 337.43 37% 7.6
OSAN2 COTTON SECTOR SUPPORT PROJECT -CHAD 11/29/2006 12/31/2013 0.00 5 000 000.00 5 000 000.00 1 337 883.72 27% 5.6
- 2 -
OSAN4 LAKE CHAD BASIN SUSTAINABLE
DEVELOPMENT
12/11/2008 12/31/2015 0.00 30 000 000.00 30 000 000.00 3 297 248.97 11% 3.5
OSAN4 CONGO BASIN – ECOSYSTEMS
CONSERVATION
11/03/2009 12/31/2014 0.00 32 000 000.00 32 000 000.00 5 246 830.13 16% 3.3
0.00 78 750 000.00 78 750 000.00 14 240 300.25 18% 5.0
SOCIAL
OSHD3 LAKE CHAD BASIN INITIATIVE SUPPORT 10/26/2005 12/31/2011 0.00 10 000 000.00 10 000 000.00 7 284 720.96 73% 6.6
OSHD3 APOC (PHASE III) 07/15/2008 11/30/2013 0.00 15 000 000.00 15 000 000.00 12 599 917.40 84% 4.0
0.00 25 000 000.00 25 000 000.00 19 884 638.36 80%
OVERALL
SITUATION
33 327
842.03
586 423
439.24
619 751
281.27
212 969
352.07
34% 4.3
Appendix III: Major Related Projects Financed by the Bank and Other
Development Partners of ECCAS
Areas/Projects
Source of
Financing Approval
date Date of
signature Effectiveness Closing
date
Approved
amount (in
CFA.F
million) Peace, Security and Stability Sector
Peace Consolidation Mission in the Central African Republic France/EU 09/11/09 09/11/09 12/07/08 01/12/13 25 072
Peace Facility 4 (PF) EU, 10th EDF 17/12/10 01/05/11 31/12/13 3 501
Peace and security support II (PAPS II) EU, 10th EDF 02/12/10 17/12/10 17/12/10 30/06/15 7 819
Infrastructure sector (Transport & ICTs) 13 682
Institutional and operational support to ECCAS for monitoring of PDCT-AC implementation FPPI_NEPAD 27/09/10 06/10/10 06/10/10 30/11/13 494
Railroad bridge and extension of the Kinshasa-Ilebo railway ADB 00/01/00 03/12/08 13/05/09 31/12/12 3 630
Study on the Doussala-Dolisie road and transport facilitation on the Libreville-Brazzaville corridor
ADB/FPPI-NEPAD RIP 18/04/10 19/04/10 23/05/11 31/07/13 1 371
Study on the Ouesso – Bangui – Ndjamena Road and Waterways
Transport on the Congo, Oubangue and Sangha Rivers ADB/ADF 29/04/11 29/04/11 31/12/14 6 324
Ouesso-Sangmélima Road
expenditure related to ECCAS coordination ADB/ADF 11/01/10 11/01/10 31/12/15 1 863
Energy and Water Sector
Project for the implementation of Central Africa’s Regional Water
Policy ADB/AWF &
NEPAD-IPPF 02/09/09 04/02/10 04/02/10 31/12/13 1 257
Environment Sector
Congo Basin Ecosystems Conservation Support Program
(PACEBCo) ADB/ADF 01/02/09 03/04/09 03/04/09 22 400
Conservation and Development of Fragile Ecosystems of Central Africa (ECOFAC V) EU, 10th EDF 24/11/10 17/12/10 17/12/10 16/12/14 19 679
Support System for the Advanced Timber Processing Sector in the
Five Congo Basin Countries CFC 15/10/10 564
Agricultural and Rural Development Sector
Comprehensive Africa Agriculture Development Programme
(CAADP) WB_SF 27/10/10 22/11/10 01/10/10 31/12/13 2 000
Support Project for Phytosanitary Capacity-Building in the Five
Member States of ECCAS and CEMAC FAO 01/06/11 08/06/11 01/07/11 01/01/13 223
Livestock for Livelihoods Project (L4LP) AU-IBAR 01/02/11 01/02/11 01/07/11 31/07/13 14
Project "Participation of African Nations in Meetings of Health
and Phytosanitary Standard-Setting Organisations EU, AU-IBAR 115
Trade and Customs Sector
PACT II ITC Support to the private sector CDE
Multisector
Capacity-building for Central African Members of Parliament
(REPAC) ACBF 18/12/07 18/12/07 18/12/07 30/06/12 750