Project Costing Tool
EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM
![Page 2: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/2.jpg)
Project Costing Tool - EUROnu 2
Agenda
Main objectives
Tool functionalities
Further improvements
EUROnu setup planning
03-June-2010
![Page 3: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/3.jpg)
Project Costing Tool - EUROnu 3
Main objectives
Centralize costing data
Standardize calculation methods
Collaborative tool (web application)
Compare the various EUROnu configurations
03-June-2010
![Page 4: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/4.jpg)
Project Costing Tool - EUROnu 4
Tool functionalities
Project Breakdown Structure
Estimates on PBS nodes
Calculations
Reports
03-June-2010
![Page 5: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/5.jpg)
Project Costing Tool - EUROnu 5
PBS Edition
03-June-2010
Basic operations
PBS selection according your access rights PBS Status : Active, Frozen or Test
![Page 6: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/6.jpg)
Project Costing Tool - EUROnu 6
PBS: Tree Structure with 6 levels
03-June-2010
Level 0 - Project
Level 1 - Beam and Services
Level 2 - Domain
Level 3 - Sub-Domain
Level 4 - System
Level 5 - Component
Level 6 – Sub-component
![Page 7: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/7.jpg)
Project Costing Tool - EUROnu 7
PBS: node edition – UI interface
03-June-2010
Create
Delete
Re-order
![Page 8: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/8.jpg)
Project Costing Tool - EUROnu 8
PBS: node edition – Excel file
03-June-2010
Initial setup
Large modifications
No user interface to directly upload data
![Page 9: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/9.jpg)
Project Costing Tool - EUROnu 9
PBS: node properties
•Name
•Date of estimate
•Technical uncertainty
•Document link (EDMS, CERN system)
Common
•Multiplicity
•Industrial index
•Technical responsible and expert
•Expected offers
Level specific
03-June-2010
![Page 10: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/10.jpg)
Project Costing Tool - EUROnu 10
Estimates on PBS node (1/2)
03-June-2010
3 phases : Industrialisation and tendering, Procurement, Reception
Start date and duration
•Proportional Cost
Manpower
•Fixed Cost
•Proportional Cost
•Currency
Material
![Page 11: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/11.jpg)
Project Costing Tool - EUROnu 11
Total cost of a PBS node
Cost at the current date
Multiplicity applied to
Proportional Estimates
One Reference Currency
Exchange rate at the estimate date
Escalation factors
03-June-2010
Current version:•Material costs calculated in CHF•Manpower costs calculated in Men Years
![Page 12: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/12.jpg)
Project Costing Tool - EUROnu 12
Escalation factors – CLIC exampleMachine and Construction indexes
03-June-2010
![Page 13: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/13.jpg)
Project Costing Tool - EUROnu 13
The total cost Cp (t)of an item p of the PBS
Cp(t) = Sum { ni [e∙ i (t)/ ei (ti)] r∙ i (ti) X∙ i (ti)}
i the types of the items composing p
ni the multiplicity of the item i if proportional estimate
ri the exchange rate at the estimate date
Xi the estimate amount of the item i
ei the escalation factor of the item i
t the calculation date
ti the estimate date of the item i
03-June-2010
![Page 14: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/14.jpg)
Project Costing Tool - EUROnu 14
Estimation extractions (1/2)Calculation feature from the PBS view
03-June-2010
![Page 15: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/15.jpg)
Project Costing Tool - EUROnu 15
Estimation extractions (2/2)
•Filters and dimensions
•Excel Export
Crosstab report
03-June-2010
![Page 16: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/16.jpg)
Project Costing Tool - EUROnu 16
Uncertainties – CLIC example
Technical uncertainty Price uncertainty Total uncertainty
03-June-2010
sindustry
0.5/expected offers
stotal
r.m.s of sdesign and sindustry
sdesign
Known technology 0.1
Extrapolation from known technology
0.2
Requires R&D 0.3
![Page 17: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/17.jpg)
Project Costing Tool - EUROnu 17
Further improvements
EUROnu projects
PBS content configuration
(levels, fields,...)
Calculation methods
Compare different configs/scenarios
Costing Knowledge Base (parameterized?)
03-June-2010
![Page 18: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/18.jpg)
Project Costing Tool - EUROnu 18
Work process• Analytical• Scaling
Define / Update PBS
Work on estimates
Enter data in the tool and
produce reports
Freeze a version
03-June-2010
![Page 19: Project Costing Tool EUROnu Annual Meeting – 3rd June 2010 Jurgen De Jonghe / Benoît Daudin – CERN, GS-AIS-PM](https://reader036.vdocument.in/reader036/viewer/2022062407/56649d0a5503460f949dc15d/html5/thumbnails/19.jpg)
Project Costing Tool - EUROnu 19
EUROnu setup planning
PBS definition in an Excel file
• Easier to start with• Faster for large amount of data• Template will be sent to Work Packages second week of June
User and access rights – based on CERN Nice account – June
Access to the application from July
Contact: [email protected] responsible for collecting data and for loading them
03-June-2010