project design document (pdd) - cdm loan schemecdmloanscheme.org/sites/default/files/pdd-3_2.pdf ·...
TRANSCRIPT
UNFCCC/CCNUCC
CDM – Executive Board Page 1
PROJECT DESIGN DOCUMENT FORM
FOR CDM PROJECT ACTIVITIES (F-CDM-PDD)
Version 04.1
PROJECT DESIGN DOCUMENT (PDD)
Title of the project activity Renewable Wind Energy by Fortune Five
Hydel Projects (P) Limited
Version number of the PDD 02
Completion date of the PDD 15/10/2012
Project participant(s) Fortune Five Hydel Projects Private Limited
Host Party(ies) India
Sectoral scope and selected methodology(ies) Sectoral Scope: 01 Energy industries
(renewable - / non-renewable sources)
Methodology: ACM0002 – Version 12.3.0 -
Consolidated baseline methodology for grid-
connected electricity generation from
renewable Sources
Estimated amount of annual average GHG
emission reductions
179,474 t CO2 e
UNFCCC/CCNUCC
CDM – Executive Board Page 2
SECTION A. Description of project activity
A.1. Purpose and general description of project activity
>>
Fortune Five Hydel Projects Private Limited (Fortune Five) has planned to establish a 100.8MW Wind
Farm near Basavana Bagewadi Town & Taluka, Bijapur District in Karnataka State, India. The wind
farm consists 63 Nos. 1.6MW Wind Turbine Generators (WTGs). The installation of WTGs are spread
over in the villages Ingaleshwar, Rabinal, Dindvar, Karabantanal, Salvadgi in Basavana Bagewadi
Taluka. The project activity is expected to generate about 200,090 MWh of power annually at a PLF of
22.66% and would reduce approximately 179,474 tCO2 / annum of GHG emissions. The power generated
from the project activity would be exported to Southern grid.
The project activity has identified the land required for the project and acquiring the same is expected to
be completed by September 2012. Executed contract with GE India Industrial Private Limited on
05/01/2012 for supply, installation and commissioning services of Wind Turbine Generators of 1.6 MW
each. Achieved financial closure during December, 2011. The commissioning of WTGs is expected to be
between 01/01/2013 and 30/06/2013.
The purpose of the project activity is generation of clean energy by tapping wind velocity, which would
be exported to the Southern grid of India. Since the project activity does not consume any fossil fuels it
contributes to reduction of greenhouse gases emissions, which would have otherwise been generated by
the operation of grid-connected power plants and by addition of new generation sources.
The electricity generated at 690V by each wind turbine would be stepped up by Unit Transformer to 33
kV voltage level and would be transmitted to wind farm pooling substation through a net work of 33 kV
transmission lines. At the wind farm pooling substation, the power would be further stepped to 220 kV
level and transmitted through 220 kV double circuit lines connected to Karnataka Power Transmission
Corporation Limited’s substation at Basavana Bagewadi, which is located at about 12 km from the wind
farm.
The technology employed in wind power generation is conversion of kinetic energy of wind into
mechanical energy by using wind turbine and subsequently into electrical energy.
No power generation facility existed at the project site prior to the start of implementation of the project
activity.
The scenario existing prior to the start of implementation of the project activity is same as baseline
scenario identified for the project activity as described under Sec.B.4.
The project activity contributes to the following sustainable development indicators:
Social well being
The project activity provides direct and indirect job opportunities to the local population during erection.
The project helps to reduce demand-supply gap in electricity in the state. The project leads to rural
upliftment and infrastructure development in the areas around the project such as improving the
condition of roads connecting to the project site.
Economic well being
The investment on the project activity would ensure economic development of the local people.
UNFCCC/CCNUCC
CDM – Executive Board Page 3
The project activity provides business opportunity to the local stakeholders such as suppliers,
manufacturers, contractors etc.
The project proponent desires to spend 2% of the revenue from sale of Carbon Credits towards local area
development.
Environmental well being
The Project activity would utilize wind velocity for generating and supplying power to the grid which is
dominated by power generated using fossil fuels such as coal, lignite and gas etc and hence it will result
in reduction of GHG emissions and contributes to preserving and improving the environment.
Technological well being:
The project activity is environmentally safe that paves the way for increased interest in wind energy in the
country and this in turn would push the investment into research for creating better wind turbines.
As evident from the foregoing, the project activity would contribute to the sustainable development of
the host country.
A.2. Location of project activity
A.2.1. Host Party(ies)
>>
India
A.2.2. Region/State/Province etc.
>>
Karnataka State
A.2.3. City/Town/Community etc.
>>
Taluka: Basavana Bagewadi
Village : Ingaleshwar, Rabinal, Dindvar, Karabantanal and Salvadgi Villages
District : Bijapur
A.2.4. Physical/Geographical location
>>
The project activity is located near Basavana Bagewadi Town & Taluka of Bijapur District in Karnataka
State. The site is approachable by NH -13 from Bijapur on the way to Mulgund. The nearest Airport to
the project site is located at a distance of 230 Km at Hubli and nearest Railway Station is located at a
distance of 45.Km at Bijapur.
The geographical co-ordinates of the project activity is in the range of:
Latitude : 16 30’0”N – 16 41’42”N
Longitude : 76 0’0”E – 76 7’22”E
Physical location of the project site is shown below.
UNFCCC/CCNUCC
CDM – Executive Board Page 4
Maps depicting project location
UNFCCC/CCNUCC
CDM – Executive Board Page 5
A.3. Technologies and/or measures
>>
The technology adopted in the wind power generation is conversion of kinetic energy into mechanical
energy and then converted into electrical energy by the generators. In this process there would be no
greenhouse gas emissions or burning of any fossil fuels. Thus, electricity would be generated through
sustainable means without causing any negative impact on the environment. Therefore, the technology is
environmentally safe and sound.
No power generation facility existed at the project site prior to the start of implementation of the project
activity.
The project activity is installation of a new grid-connected renewable power plant and hence as per the
methodology ACM0002 Version 12.3.0, the baseline scenario is “Electricity delivered to the grid by the
project activity would have otherwise been generated by the operation of grid-connected power plants
and by the addition of new generation sources”.
No technology transfer is envisaged for the project activity.
The technical specifications of the WTGs selected for the project activity are given below.
Item Particulars
Make GE
Model 1.6 xle
Rating 1600 kW
Rotor Diameter 82.5 m
Hub height 80 m
Number of blades 3
Swept area 5346 m2
Orientation Upwind
Speed Regulation Pitch Control
Type of Generator Doubly Fed Induction (DFM)
Voltage 690 V
Frequency 50 Hz
Cut-in-wind speed 3.5 m / s
Rated wind speed 11.5 m / s
Cut-out wind speed 25 m / s
Design Life1 20 years
1 Fact Sheet – 1.6 – 82.5 Wind Turbine : http://www.ge-
energy.com/content/multimedia/_files/downloads/GEA18112B_1.6-82.5%20Wind%20Turbine_r1.pdf
UNFCCC/CCNUCC
CDM – Executive Board Page 6
A.4. Parties and project participants
Party involved
(host) indicates a host Party
Private and/or public
entity(ies) project participants
(as applicable)
Indicate if the Party involved
wishes to be considered as
project participant (Yes/No)
Party A (host)
India
Private entity A
Fortune Five Hydel Projects
Private Limited
No
A.5. Public funding of project activity
>>
The project activity does not involve any public funding from Annex-1 countries.
SECTION B. Application of selected approved baseline and monitoring methodology
B.1. Reference of methodology
>>
Title: Consolidated baseline methodology for grid-connected electricity generation from renewable
Sources
Ref : ACM0002 – Version 12.3.0
Tools used: 1) Tool for the demonstration and assessment of additionality (Version 06.0.0)
2) Tool to calculate the emission factor for an electricity system (Version 02.2.1)
B.2. Applicability of methodology
>>
In the methodology ACM0002 Version 12.3.0, applicability criteria for various projects are mentioned.
Applicable conditions for the present activity and fulfillment of the same are mentioned below.
Applicability criteria Project activity
This methodology is applicable to grid-connected
renewable power generation project activities that
(a) install a new power plant at a site where no
renewable power plant was operated prior to the
implementation of the project activity (greenfield
plant); (b) involve a capacity addition; (c) involve
a retrofit of (an) existing plant(s); or (d) involve a
replacement of (an) existing plant(s).
The project activity is installation of new Wind
power plant for generation of power utilizing wind
velocity and the generated power will be exported
to Southern grid. No renewable power plant was
installed and operated at the proposed project
location prior to the implementation of the project
activity.
The project activity is the installation, capacity
addition, retrofit or replacement of a power
plant/unit of one of the following types: hydro
power plant/unit (either with a run-of-river
reservoir or an accumulation reservoir), wind
power plant/unit, geothermal power plant/unit,
solar
power plant/unit, wave power plant/unit or tidal
power plant/unit
The project activity is installation of new Wind
power projects.
UNFCCC/CCNUCC
CDM – Executive Board Page 7
In the case of capacity additions, retrofits or
replacements (except for capacity addition projects
for which the electricity generation of the existing
power plant(s) or unit(s) is not affected): the
existing plant started commercial operation prior to
the start of a minimum historical reference period
of five years, used for the calculation of baseline
emissions and defined in the baseline emission
section, and no capacity addition or retrofit of the
plant has been undertaken between the start of this
minimum historical reference period and the
implementation of the project activity;
Not applicable. The project activity is installation
of new Wind power projects.
In case of hydro power plants, one of the following
conditions must apply:
a) The project activity is implemented in an
existing single or multiple reservoirs, with no
change in the volume of any of reservoirs; or
b) The project activity is implemented in an
existing single or multiple reservoirs, where the
volume of any of reservoirs is increased and the
power density of each reservoir, as per definitions
given in the Project
Emissions section, is greater than 4 W/m2 after the
implementation of the project activity; or
c) The project activity results in new single or
multiple reservoirs and the power density of each
reservoir, as per definitions given in the Project
Emissions section, is greater than 4 W/m2
after the
implementation of the project activity
Not applicable. The project activity is installation
of new Wind power projects.
In case of hydro power plants using multiple
reservoirs where the power density of any of the
reservoirs is lower than 4 W/m2 all the following
conditions must apply:
• The power density calculated for the entire
project activity using equation 5 is greater than 4
W/m2;
• All reservoirs and hydro power plants are located
at the same river and where are designed
together to function as an integrated project that
collectively constitutes the generation capacity of
the combined power plant;
• The Water flow between the multiple reservoirs
is not used by any other hydropower unit which is
not a
part of the project activity;
• The total installed capacity of the power units,
which are driven using water from the reservoirs
with a power density lower than 4 W/m2, is lower
than 15MW;
Not applicable. The project activity is installation
of new Wind power projects.
UNFCCC/CCNUCC
CDM – Executive Board Page 8
• The total installed capacity of the power units,
which are driven using water from reservoirs with
a
power density lower than 4 W/m2, is less than 10%
of the total installed capacity of the project
activity from multiple reservoirs.
The methodology is not applicable to the
following:
• Project activities that involve switching from
fossil fuels to renewable energy sources at the
site of the project activity, since in this case the
baseline may be the continued use of fossil
fuels at the site;
• Biomass fired power plants;
• A hydro power plant that results in the creation of
a new single reservoir or in the increase
in an existing single reservoir where the power
density of the power plant reservoir is less
than 4 W/m2.
The project activity is a new wind power project. It
does not involve switching from fossil fuels to
renewable energy sources and also not fall under
the category of biomass fired power plant and
hydro power plant. Hence, the methodology is
applicable to the project activity.
Applicability Conditions of Tools referred by
the Methodology
“Tool to calculate the emission factor for an
electricity system” Version 02.2.1
This tool may be applied to estimate the OM, BM
and/or CM when calculating baseline emissions for
a project activity that substitutes grid electricity,
i.e. where a project activity supplies electricity to a
grid or a project activity that results in savings of
electricity that would have been provided by the
grid (e.g. demand-side energy efficiency
projects).In case of CDM projects the tool is not
applicable if the project electricity system is
located partially or totally in an Annex I country.
The project activity is a Wind Farm which
generates and supplies the electricity to grid and
hence this tool is applicable to the project activity
to estimate OM, BM and CM for calculating
baseline emissions.
The project activity is located in Karnakata State,
India and does not fall under Annex I country and
hence this tool is applicable to the project activity.
“Tool for the demonstration and assessment of
additionality” Version 06.0.0”
Use of this tool is mandatory to demonstrate
additionality of the project as per methodology
ACM0002 Version 12.3.0
“Combined tool to identify the baseline scenario
and demonstrate additionality”
This tool is only applicable to methodologies for
which the potential alternative scenarios to the
proposed project activity available to project
participants cannot be implemented in parallel to
the proposed project activity.
The project activity is installation of Greenfield
facility which supplies electricity generated to grid
and the methodology ACM0002 Version 12.3.0
applied for this project activity prescribed baseline
scenario. Further as per Paragraph 115 of VVS
(Version 2.0) “where the baseline scenario is
prescribed in the approved methodology, no further
analysis is required”. Hence, use of this tool is not
necessary.
UNFCCC/CCNUCC
CDM – Executive Board Page 9
“Tool to calculate project or leakage CO2 emissions
from fossil fuel combustion”
This tool can be used in cases where CO2 emissions
from fossil fuel combustion are calculated based on
the quantity of fuel combusted and its properties.
The project activity is a Wind Farm which
generates electricity utilizing wind velocity and it
does not involve combustion of fossil fuels. Hence
use of this tool is not required.
The project meets the criteria mentioned in the methodology ACM0002, Version 12.3.0 and hence
justifies the selection of approved consolidated baseline methodology for this project activity.
B.3. Project boundary
As per the methodology ACM 0002 Version 12.3.0, the spatial extent of the project boundary includes
the project power plant and all power plants connected physically to the electricity system that the CDM
project power plant is connected to. Accordingly, the project boundary encompasses the physical and
geographical site of the Wind farm till the power evacuation system. As per the CO2 baseline database
published by Central Electricity Authority (CEA) there are two Indian grid system viz., 1) integrated
Northern, Eastern, Western and North-Eastern (NEWNE) and 2) Southern grid. Since the project activity
falls under Southern grid, all the power plants connected to Southern grid are also forms part of project
boundary.
Power plants
connected to grid
Project Boundary
33 / 220 kV pooling Sub-
station at Ingaleshwar
63 WTGs
Consumers
220/110/33/11kV Sub-
station at Basavana
Bagewadi
CM
Metering
MM
MM
CM
UNFCCC/CCNUCC
CDM – Executive Board Page 10
Source GHGs Included? Justification/Explanation B
ase
lin
e sc
ena
rio
Source 1
CO2 emissions from
electricity generation
in fossil fuel fired
power plants that are
displaced due to the
project activity
CO2 Included Main emission source
CH4 No Minor emission source
N2O No Minor emission source
Source 2 CO2
CH4 - Nil -
N2O
Pro
ject
scen
ari
o
Source 1
Electricity generation
by installing wind
turbine generators
CO2 No Not applicable since no
emissions occur from project
operation
CH4 No Not applicable since no
emissions occur from project
operation
N2O No Not applicable since no
emissions occur from project
operation
Source 2 CO2
CH4 - Nil -
N2O
B.4. Establishment and description of baseline scenario
>>
According to the approved consolidated methodology ACM0002, version 12.3.0, baseline scenario for
the installation of a new grid-connected renewable power plant is as under:
“Electricity delivered to the grid by the project activity would have otherwise been generated by the
operation of grid-connected power plants and by the addition of new generation sources, as reflected in
the combined margin (CM) calculations described in the Tool to calculate the emission factor for an
electricity system”.
As the proposed project activity is new renewable grid-connected power plant, the applicable baseline
scenario for this project is the electricity delivered to the grid by the project activity which would have,
otherwise, been generated by the operation of grid-connected power plants and by addition of new
generation sources, as reflected in the combined margin (CM) calculations.
B.5. Demonstration of additionality
>>
Additionality of the project activity is demonstrated using the Methodological tool “Demonstration and
assessment of additionality” Version 06.0.0 as specified by the approved methodology ACM0002
Version 12.3.0 as described below: context
Step 1. Identification of alternatives to the project activity consistent with current laws and
regulations
The methodology ACM 0002 Version 12.3.0 states that if the project activity is the installation of a new
grid-connected renewable power plant/unit, the baseline scenario will be grid connected power plant.
Paragraph 115 of VVS (Version 2.0) states that “where the baseline scenario is prescribed in the
UNFCCC/CCNUCC
CDM – Executive Board Page 11
approved methodology, no further analysis is required.” Hence, no further analysis on the alternatives is
necessary.
As the project activity is installation of a new grid connected renewable power plant, no further analysis
on the alternatives is necessary basing on the above referred clause(s).
Step 2. Investment analysis
Sub-step 2.a.: Determine appropriate analysis method
The tool for additionality provides the following three options for investment analysis.
Option – I : Simple cost analysis
Option - II : Investment comparison analysis
Option – III : Benchmark analysis
Option - I: Simple cost analysis is not applicable to the project activity as the CDM revenues are not the
only means of income.
Option - II: Since the alternative to the project activity is the import of electricity from the grid,
investment comparison analysis is not appropriate for the project
Option - III: The Benchmark analysis is considered appropriate for the project activity as the alternative
to the project is supply of electricity from a grid and the choice of the project proponent is to invest or
not to invest in the project activity. Therefore, the selection of benchmark analysis is in conformity with
the guidance 19 of Annex 5 of EB 62.
Sub-step 2b: Option III - Benchmark analysis
Since the project is funded by a mix of debt and equity, post tax project IRR is considered as an
appropriate financial indicator as the financial indicator accounts for both the cost of debt and return on
equity. The project proponent seeks to demonstrate the addtionality of the project through Project IRR.
The IRR so computed is compared with a benchmark indicator to assess the financial attractiveness of
the project.
As per the guidance note issued by CDM EB at its 62nd
meeting (Annex 5, item 12, selection and
validation of appropriate benchmarks) “In case where benchmark approach is used the applied
benchmark shall be appropriate to the type of IRR calculated. Local commercial lending rates or
weighted average cost of capital (WACC) are appropriate benchmarks for a project IRR”. Accordingly,
Weighted Average Cost of Capital (WACC) has been worked out, the details of which are furnished
below:
Weighted average cost of capital (WACC) is calculated as weighted average cost of equity and cost of
debt as illustrated below:
WACC = E/V * Re + D/V * Rd * ( 1- Tc)
Where:
Re = cost of equity
Rd = cost of debt
E = Equity
D = Debt
V = E + D
UNFCCC/CCNUCC
CDM – Executive Board Page 12
E/V = percentage of financing that is equity
D/V = percentage of financing that is debt
Tc = Corporate tax rate
Cost of Equity (Re) :
The real cost of equity of 11.75% as provided in Appendix to the EB 62 Annex 5 “Guidelines on the
Assessment of Investment Analysis” for India applicable to the Group I project categories (Energy
Industries) is considered. Further as per the said guidelines, the cost of equity (Real term value) has been
converted to the nominal value by adding inflation rate of 6%2 (RBI projected rate).
Cost of Debt (Rd) :
Cost of debt is defined as the rate at which lender’s agree to lend money to a project. The additionality
tool and the guidance to investment analysis clarify that the benchmark for a project with more than one
potential developer should not be based on project specific parameters but should represent the standard
in the market. Accordingly, the bank prime lending rate prevailing at the time of investment decision
(November, 2011) has been considered as the cost of debt. The prime lending rate available at the time of
investment was 14.75%3; it has been considered as the cost of debt. Interest costs are tax deductible;
therefore, in order to arrive at the post tax cost of debt, the cost of debt is multiplied with the factor, (1-
applicable marginal tax rate i.e., 20.01%).
As per the Detailed Project Report the debt equity (E/V and D/V) ratio is 70:30. The envisaged Equity
(E) is Rs.1952.89 million and Debt (D) is Rs.4556.75 million.
Based on the above, the WACC works out to 13.58%. The selected benchmark is in conformity with
guidance 12 and 13 of Annex 5, EB 62. The WACC calculation is provided in the IRR analysis
worksheet.
Sub-step 2.c.: Calculation and comparison of financial indicators
The IRR analysis is prepared based on detailed project report available at the time of investment
decision. While computing the IRR all the benefits and fiscal concessions available to the project have
been taken into account.
Assumptions underlying Financial Indicators
Parameters Value Source for input Values
Project cost (Rs.in million) 6509.64 Detailed Project Report /Offer from
Equipment supplier and contract executed
with GE India Industrial private limited.
Means of Finance (Rs.in million):
-Equity (30%)
-Term Loan (70%)
1952.89
4556.75
Detailed Project Report
Annual Gross Energy (MWh) 200090 Detailed Project Report Plant load Factor (%) 22.66 Detailed Project Report and Report on
Energy Estimation prepared by CECL a
third party engineering company
2 http://rbi.org.in/scripts/PublicationsView.aspx?id=14335 – Sec.3
3 http://www.statebankofindia.com/user.htm
UNFCCC/CCNUCC
CDM – Executive Board Page 13
Derating after 10 years (%) 5 Detailed Project Report
Tariff (Rs./kWh) 3.70 Detailed Project Report / KERC order-
December, 2009
Operation & Maintenance
- % of Capital cost
- % of escalation per annum
1.3
5
Detailed Project Report
Generation based incentive (GBI) (in
Rs.) per unit of electricity fed into the
grid with a cap of Rs.62 Lakhs/MW
0.50 Operational guidelines for
implementation of “Generation Based
Incentive” for grid connected wind power
projects issued by Indian Renewable
Energy Development Agency Ltd.,
(IREDA) in line with the Scheme for
implementation of GBI issued by
Ministry of New and Renewable Energy
(MNRE) dt. 17.12.2009.
Administrative expenses (Rs.in million)
Annual escalation (%)
6
5
Detailed Project Report
Interest on Term Loans (%) 13 Term Loan sanction letter Loan Repayment period (Years) 12 Detailed Project Report Moratorium period 1 Detailed Project Report Income Tax - MAT 2011-12 (%) 20.01 Indian Income Tax Act 1961
http://incometaxindiapr.gov.in/incometaxi
ndiacr/contents/forms2010/pamphets/CO
MPANIES_2013_14.htm
Income Tax – Regular 2011-12 (%) 32.45 Indian Income Tax Act 1961 http://incometaxindiapr.gov.in/incometaxi
ndiacr/contents/forms2010/pamphets/CO
MPANIES_2013_14.htm Life time of the project activity 20 years Detailed Project Report
The PLF is based on the “Report on Energy Estimation prepared by Consolidated Energy
Consultants Limited (CECL), Bhopal a third party engineering consultant for wind energy and
therefore conforms to Annex11, EB 48. The financial indicator has been calculated for 20 years which is
the operating life of the project based on the DPR, and hence represents “expert opinion”, which
conforms to Annex 15, EB 50.
Based on the above assumptions, the project IRR works out to 7.25% in contrast to the benchmark return
of 13.58% chosen to compare project IRR. Therefore, the project is not a business-as-usual scenario and
hence additional. This conclusion has been tested by subjecting critical parameters to reasonable
variations.
Sub-step 2.d.: Sensitivity Analysis
The “tool for the demonstration and assessment of additionality” requires that a sensitivity analysis is
conducted to check weather the financial attractiveness is robust to reasonable variations in the critical
assumptions. The Guidance on the Assessment of Investment Analysis issued by the EB in its 62nd
Meeting requires subjecting those variables which constitute more than 20% of project cost or total
project revenue to sensitivity analysis and considering a +/- 10% variations in the selected variables.
Accordingly, the variables viz., generation, tariff, project cost and O&M are selected for sensitivity
analysis.
UNFCCC/CCNUCC
CDM – Executive Board Page 14
The results of the sensitivity analysis for the IRR are furnished below:
Sensitivity Analysis
Variation % -10% 0% 10%
PLF 5.56% 7.25% 8.87%
Project cost 9.11% 7.25% 5.65%
Tariff 5.66% 7.25% 8.77%
O & M Cost 7.51% 7.25% 6.98%
Bench Mark 13.58%
With CDM 9.51%
The sensitivity analysis proves that the project is unlikely to be financially viable even under the most
optimistic conditions of generation (PLF) going up by 10% or project cost going down by 10% or tariff goes
up by 10% or O & M cost going down by 10%. In either case, the project IRR remains at 8.87%, 9.11%,
8.77% and 7.51% respectively in contrast to the benchmark return of 13.58%. This proves that the project
activity is not a business-as-usual scenario. The project IRR in the baseline scenario improves to 9.60%
considering revenue from CDM in contrast to the benchmark return of 13.58%. Hence, the project requires
CDM benefits to make it financially attractive.
The Project will become non-additional only if the PLF goes up by 41.60% or the project cost drops down by
28.40% or tariff goes up by 44.70%. Even if the O&M cost reduce by 100% the IRR of the project activity
does not reach the benchmark. All these scenarios are not possible as explained below:
There is no possibility of PLF reaching 31.95% (increase in PLF by 9.43% from the considered PLF of
22.66%). Karnataka Electricity Regulatory Commission (KERC) in its tariff order dt.11th Dec 2009 has
approved a PLF of 26.5% for determination of tariff. The IRR works out to 9.96% considering the PLF of
26.5% as approved by KERC, which is still below the benchmark of 13.58%.
As regards the project cost, the cost is firmed up at Rs.6110 million as against the estimated cost of Rs.6509.64
million in the DPR. The reduction in the project cost is 6.5% and there is no scope for further reduction in the
project cost as the same is firmed up.
As per KERC Order dt.11th
December 2009, the tariff is fixed at Rs.3.70 per kWh without any escalation for
the first 10 years from the date of signing of the PPA. Any assumption on tariff applicable from 11th year
onwards is highly uncertain today and do not provide a reliable basis for investment decisions. Hence the tariff
applicable at the time of investment decision is considered for 11th year to 20
th year.
O & M Costs includes salaries and wages, repairs and maintenance and various other expenses required for the
operation as well as maintenance of the plant and hence there is no possibility of decrease in O & M charges.
The sensitivity analysis proves that the project is unlikely to be financially attractive even under the most
optimistic conditions.
UNFCCC/CCNUCC
CDM – Executive Board Page 15
Outcome of Step 2: The sensitivity analysis proves that the project is not financially attractive without
CDM support. With the CDM support the project IRR improves to 9.51%. Therefore, CDM benefits are
imperative for the project to alleviate the financial barrier.
Step 3 Barrier analysis
As the sensitivity analysis under Step 2 demonstrated that the proposed CDM project activity is unlikely
to be the financially attractive, step 3 is skipped.
Step 4 Common practice Analysis
Sub-step 4a. Analyze other activities similar to the proposed project activity
Common practice analysis has been conducted as per the procedure laid down in Additionality Tool
(version 06.0.0). As required by the Additionality Tool, the entire country has been defined as the
geographical area for the purpose of common practice analysis.
Step 1:
The applicable output range of the designed capacity of the project (± 50% of the capacity) is 50.4 MW
(50% of installed capacity) to 151.2 MW (150%) of installed capacity). All the data required for the
common practice analysis have been sourced from CEA - CO2 Baseline Database (version 07) and the
data of wind power projects as available in the Directory-India Wind Power 2011 published by
Consolidated Energy Consultants Limited (CECL), Bhopal has been used.
The registered CDM/VCS projects (2 hydro projects consisting of 7 units, 2 thermal power plants and 6
wind projects which are falling within +/-50% range) have been excluded in the analysis.
There are no projects which have commissioned after the start date of the project activity.
With regard to biomass power / solar power projects there is no complete data available for all the states
in India, to include in the analysis. However, based on the information available in few state nodal
agency websites, the biomass/solar projects already commissioned are having an installed capacity of
below 25MW and these will not fall under +/- 50% of the output range of the capacity of the project
activity.
The following weblinks of state nodal agencies presented list of commissioned biomass / solar power
projects. It is observed from these sources that the maximum capacity of each biomass / solar power
projects already implemented is below 25MW.
Biomass Power Projects:
http://www.nedcap.gov.in/Biomass_Energy.aspx?ID=31
http://www.kredltest.in/Bioreport.aspx
http://hareda.gov.in/?model=pages&nid=155
http://www.mahaurja.com/PDF/Biomass_Proj_StatusC.pdf
Solar Power Projects:
UNFCCC/CCNUCC
CDM – Executive Board Page 16
http://nedcap.gov.in/Solar_Energy.aspx?ID=70
http://kredltest.in/Solargridreport.aspx
http://hareda.gov.in/?model=pages&nid=155
http://www.teda.in/
(It is appearing in the home page that the achievement with respect to Solar Power upto 31.03.2012 is
10MW)
Step 2:
Total number of projects (Nall) which have commenced commercial operation before the start date of the
project activity and which are falls within +/- 50% of the output capacity of the project activity are 482,
the details of which are furnished below:
Sector Total (Nos.)
Hydro 243
Wind 0
Thermal / Nuclear 239
Total 482
Nall - All plants of capacities ranging from 50.4MW to 151.2 MW
Step 3:
The hydro and thermal power plants are identified as “technology different” projects since in both cases
the energy source / fuel, access to technology, financial flows, promotional & regulation policies are
different.
Hence, projects which apply technology different from that of the project activity (Ndiff ) as explained
above are also 482 as per the plants identified in Step 2 above. The details of which are furnished below:
Ndiff - Plants operating with different technologies
Sector Total (Nos.)
Hydro 243
Wind 0
Thermal / Nuclear 239
Total 482
.
Step 4:
The plants using technology similar to the technology used in the project activity in all plants that deliver
same output or capacity as the project activity =
UNFCCC/CCNUCC
CDM – Executive Board Page 17
F = 1 – Ndiff/Nall = 1 – (482/482) = 0 &
Nall – Ndiff = 482 – 482 = 0
As per the Additionality Tool the project activity is a “common practice” if both the following conditions
are fulfilled:
(a) the factor F is greater than 0.2, and
(b) Nall - Ndiff is greater than 3
Since both conditions are not fulfilled, it is concluded that the project activity is not a common practice
in the country.
The soft copy of Common Practice analysis is furnished to DOE for verification.
Serious consideration of CDM
As per the guidelines on the demonstration and assessment of prior consideration of the CDM, Annex 13 of
EB 62, the project activities with a starting date on or after 02 August 2008 must inform a Host Party
DNA and the UNFCCC secretariat in writing of the commencement of the project activity and of their
intention to seek CDM status. Such notification must be made within six months of the project activity
start date and shall contain the precise geographical location and a brief description of the proposed
project activity, using the standardized form F-CDM-Prior Consideration.
The PP has signed an agreement with the WTG supplier on 05/01/2012, which is the start date of the
project as per Glossary of CDM terms. The project proponent has submitted the “Prior Consideration of
the CDM Form” duly filled and signed to the Secretariat, UNFCCC and to the Indian DNA on
28/11/2011 and the same is notified at the UNFCCC website. Since the PP has intimated both UNFCCC
and DNA within 6 months from the start date of the project, the requirements of paragraph 2 of Annex
13, EB 62 is fulfilled.
B.6. Emission reductions
B.6.1. Explanation of methodological choices
>>
Application of baseline methodology
According to the “Tool to calculate the emission factor for an electricity system” Version 02.2.1, the
baseline emissions are the amount of electricity produced times the grid emission factor which is the
Combined Margin (CM), calculated as the simple average of the Operating Margin (OM) emission factor
and the Build Margin (BM) emission factor. The emission factor of the grid for the ex-ante approach is
calculated in the following way:
In accordance with the "Tool to calculate the emission factor for an electricity system, Version 02.2.1”
the grid emission factor is calculated as per the following procedure:
Step 1. Identify the relevant electricity systems
Step 2. Choose whether to include off-grid power plants in the project electricity system
Step 3. Select a method to determine operating margin (OM)
Step 4. Calculate the operating margin emission factor according to the selected method
Step 5. Calculate the build margin (BM) emission factor
UNFCCC/CCNUCC
CDM – Executive Board Page 18
Step 6. Calculate the combined margin (CM) emission factor Step 1 – Identify the relevant electric power system
The CEA of the host country has published a delineation of the project electricity system and connected
electricity systems. According to data published by the CEA of India the project activity falls under
Southern Grid.
Step 2 - Choose whether to include off-grid power plants in the project electricity system (optional).
Project participants may choose between the following two options to calculate the operating margin and
build margin emission factor:
Option I: Only grid power plants are included in the calculation.
Option II: Both grid power plants and off-grid power plants are included in the calculation.
Following the calculations of the CEA , and the statistical data available, Option I is chosen
Step 3 – Select a method to determine the operating margin (OM)
The approved methodological tool recommends the use of one of the following for the calculation of the
operating margin emission factor (EF grid,OM,y):
a) Simple OM, or
b) Simple adjusted OM; or
c) Dispatch data analysis OM; or
d) Average OM.
According to the methodological tool the Simple OM can be used if low-cost/must-run resources
constitute less than 50% of total grid generation in: 1) Average of the five most recent years 2) Based on
long-term averages for hydroelectricity production.
As per “CO2 Baseline Database” Version 7.0 the average share of low-cost /must-run resources (for the
five most recent years 2006-07 to 2010-11) of the Southern grid is amounting to 24% which is less than 50%
of the grid generation and hence Simple OM method is used to determine operating margin.
The data vintage option selected is the ex-ante approach, where a 3 year generation weighted average
OM is calculated. The most recent three year data published by CEA on the emission factor of Southern
region is considered.
Step 4 – Calculate the operating margin emission factor according to the selected method.
The Simple OM is calculated as the generation-weighted average CO2 emissions per unit net electricity
generation (tCO2/MWh) of all generating power plants serving the system, not including low-cost / must-
run power plants / units using the CO2 Baseline database of the Southern Grid. The calculation is
furnished below: Table 1: Operating Margin
Most recent three years 2008-09 2009-10 2010-11
Net Generation (Southern) in MWh 121,471,250 134,716,872 137,387,256
UNFCCC/CCNUCC
CDM – Executive Board Page 19
Operating Margin* (OM) in tCO2 e/
MWh
0.97292 0.94150 0.94188
Recent three year weighted average
Simple Operating Margin (tCO2/MWh)
0.95133
* including imports
Source: CO2 Baseline Data base, Version 7.0, January, 2012
(http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm)
Step 5 – Calculate the build margin (BM) emission factor
As per the methodological tool, the project participants can choose one of the following two options for
calculating build margin:
Option 1: For the first crediting period, calculate the build margin emission factor ex ante based on the
most recent information available on units already built for sample group m at the time of CDM-PDD
submission to the DOE for validation. For the second crediting period, the build margin emission factor
should be updated based on the most recent information available on units already built at the time of
submission of the request for renewal of the crediting period to the DOE. For the third crediting period,
the build margin emission factor calculated for the second crediting period should be used. This option
does not require monitoring the emission factor during the crediting period.
Option 2: For the first crediting period, the build margin emission factor shall be updated annually, ex
post, including those units built up to the year of registration of the project activity or, if information up
to the year of registration is not yet available, including those units built up to the latest year for which
information is available. For the second crediting period, the build margin emissions factor shall be
calculated ex ante, as described in Option 1 above. For the third crediting period, the build margin
emission factor calculated for the second crediting period should be used.
Option 1 is considered and the Build Margin (BM) for the most recent year published in CO2 Baseline
Database, Version 7.0 available at the time of PDD development is furnished below:
Build Margin (BM) 0.73389 tCO2 e/ MWh
Source: CO2 Baseline Data base, Version 7.0, January, 2012
(http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm)
Step 6 – Calculate the Combined margin emission factor
As per the methodological tool, the calculation of the combined margin (CM) emissions factor
(EFgrid,CM,y) is based on one of the following methods:
(a) Weighted Average CM; or
(b) Simplified CM
The simplified CM method (option b) can only be used if:
UNFCCC/CCNUCC
CDM – Executive Board Page 20
• The project activity is located in a Least Developed Country (LDC) or in a country with less than 10
registered projects at the starting date of validation; and
• The data requirements for the application of step 5 above cannot be met.
The criteria of simplified CM is not applicable to the project activity, therefore Option (a) is chosen for
calculation of Combined Margin (CM) emission factor.
The combined margin emission factor is calculated as the average of the OM and BM emission factors,
i.e. the defaults weights for OM and BM are each weighted at 50%. The resulting Combined Margin is
fixed ex ante for the duration of the crediting period:
Where:
EFgrid, BM, y – Build margin CO2 emission factor in year y (tCO2/MWh)
EFgrid, OM, y – Operating margin CO2 emission factor in year y (tCO2/MWh)
WOM – Weighting of operating margin emissions factor(%)
WBM – Weighting of build margin emissions factor(%)
EFgrid,CM,y = 0.95133 x 75% + 0.73389 x 25% = 0.89697 tCO2 / MWh
The calculated value has been fixed ex-ante for the entire crediting period.
The procedure for calculating the project emissions, baseline emissions, leakage emissions and emission
reductions are furnished below:
Project Emissions:
As per ACM0002 Version 12.3.0, PE,y = 0 for renewable power generation project activities.
Baseline Emissions
The baseline emissions in year y are calculated as:
BEy = EGPJ,y ⋅ EFgrid,CM,y
Where:
BEy = Baseline emissions in year y (tCO2)
EGPJ,y = Quantity of net electricity generation that is produced and fed into the grid as a result
of the implementation of the CDM project activity in year y (MWh)
EFgrid,CM,y = Combined margin CO2 emission factor for grid connected power generation in year y
calculated using the latest version of the “Tool to calculate the emission factor for an
electricity system” (tCO2/MWh)
Calculation of EGPJ,y
The calculation of EGPJ,y is different for (a) greenfield plants, (b) retrofits and replacements, and (c)
capacity additions.
The project is a Greenfield renewable energy power plant since as the project activity is the installation of a
new grid-connected renewable power plant/unit at a site where no renewable power plant was operated prior to
the implementation of the project activity, then:
UNFCCC/CCNUCC
CDM – Executive Board Page 21
EGPJ,y = EGfacility,y
Where:
EGPJ,y = Quantity of net electricity generation that is produced and fed into the grid as a result
of the implementation of the CDM project activity in year y (MWh/yr)
EGfacility,y = Quantity of net electricity generation supplied by the project plant/unit to the grid in
year y (MWh/yr)
Leakage
According to the ACM0002 Version 12.3.0 methodology, no leakage emissions are considered.
Emission reductions
Emission reductions are calculated as follows:
ERy = BEy − PEy
Where:
ERy = Emission reductions in year y (t CO2e/yr)
BEy = Baseline emissions in year y (t CO2/yr)
PEy = Project emissions in year y (t CO2e/yr)
B.6.2. Data and parameters fixed ex ante
(Copy this table for each piece of data and parameter.)
Data / Parameter EFgrid,CM,y
Unit t CO2/MWh
Description Combined margin CO2 emission factor of the project electricity system
in year y
Source of data CO2 Baseline Database, Version 7.0 published by Central Electricity
Authority (CEA) http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm
Value(s) applied 0.89697
Choice of data
or
Measurement methods
and procedures
In order to facilitate adoption of authentic baseline emissions data and
also to ensure uniformity in the calculations of CO2 emission reductions
by CDM project developers, Central Electricity Authority (CEA),
Government of India, Ministry of Power has compiled a database
containing the necessary data on CO2 emissions for all grid-connected
power stations in India.
Calculated as a weighted average of Operating Margin and Build Margin
emission factors as per the “Tool to calculate the emission factor for an
electricity system”.
Purpose of data Calculation of baseline emissions
Additional comment This value is fixed for the first crediting period.
UNFCCC/CCNUCC
CDM – Executive Board Page 22
Data / Parameter EF grid, OM, y
Unit t CO2/MWh
Description Operating Margin CO2 Emission Factor for the project electricity system
in year y (Southern Grid)
Source of data CO2 Baseline Database, Version 7.0 published by Central Electricity
Authority (CEA) http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm
Value(s) applied 0.95133
Choice of data
or
Measurement methods
and procedures
In order to facilitate adoption of authentic baseline emissions data and
also to ensure uniformity in the calculations of CO2 emission reductions
by CDM project developers, Central Electricity Authority (CEA),
Government of India, Ministry of Power has compiled a database
containing the necessary data on CO2 emissions for all grid-connected
power stations in India.
Most recent 3 years (2008-09, 2009-10, 2010-11) net generation and
Operating Margin (OM) emission factor values of Southern region have
been used from the CO2Baseline Database published by Central
Electricity Authority, Government of India, as available at the time of the
PDD submission.
Purpose of data Calculation of baseline emissions
Additional comment This value is fixed for the first crediting period.
UNFCCC/CCNUCC
CDM – Executive Board Page 23
Data / Parameter EF grid, BM, y
Unit t CO2/MWh
Description Build Margin CO2 Emission Factor for the project electricity system in
year y (Southern Grid)
Source of data CO2 Baseline Database, Version 7.0 published by Central Electricity
Authority (CEA) http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm
Value(s) applied 0.73389
Choice of data
or
Measurement methods
and procedures
In order to facilitate adoption of authentic baseline emissions data and
also to ensure uniformity in the calculations of CO2 emission reductions
by CDM project developers, Central Electricity Authority (CEA),
Government of India, Ministry of Power has compiled a database
containing the necessary data on CO2 emissions for all grid-connected
power stations in India.
The Build Margin emission factor data (for the year 2010-11) from CO2
Baseline Database published by Central Electricity Authority,
Government of India has been used as available at the time of the PDD
submission.
Purpose of data Calculation of baseline emissions
Additional comment This value is fixed for the first crediting period. For the second crediting
period, the build margin emission factor will be updated based on the
most recent information available on units already built at the time of
submission of the request for renewal of the crediting period to the DOE.
B.6.3. Ex ante calculation of emission reductions
>>
Baseline emissions calculated as explained in section B.6.1 above are summarised as below.
BEy = EGPJ,y ⋅ EFgrid,CM,y
BEy = 200,090 MWh * 0.89697 tCO2/MWh
BEy = 179,474.38 tCO2 or say 179,474 tCO2
Project emissions
The project activity is a renewable power generation project and hence PEy = 0.
Leakage:
As described in part B.6.1, the leakage of the Project is 0 tCO2e.
Ly = 0
Emission reductions
Emission reductions from the project activity are estimated as the difference between baseline emissions,
project emissions and leakage.
ERy = BEy - PEy
ERy = 179,474 - 0 = 179,474 tCO2e
UNFCCC/CCNUCC
CDM – Executive Board Page 24
B.6.4. Summary of ex ante estimates of emission reductions
It is expected that the Project will generate GHG emission reductions of about 179,474 tCO2e annually
over the crediting period.
Year Baseline emissions
(t CO2e)
Project
emissions
(t CO2e)
Leakage
(t CO2e)
Emission
reductions
(t CO2e)
01/06/2013 to 31/05/2014 179,474 0 0 179,474
01/06/2014 to 31/05/2015 179,474 0 0 179,474
01/06/2015 to 31/05/2016 179,474 0 0 179,474
01/06/2016 to 31/05/2017 179,474 0 0 179,474
01/06/2017 to 31/05/2018 179,474 0 0 179,474
01/06/2018 to 31/05/2019 179,474 0 0 179,474
01/06/2019 to 31/05/2020 179,474 0 0 179,474
Total 1,256,318 0 0 1,256,318
Total number of crediting
years
7 years
Annual
average over the crediting
period
179,474 0 0 179,474
B.7. Monitoring plan
B.7.1. Data and parameters to be monitored
(Copy this table for each piece of data and parameter.)
UNFCCC/CCNUCC
CDM – Executive Board Page 25
Data / Parameter EGimport,y
Unit MWh
Description Grid electricity import by the project activity during the year, y
Source of data Monthly statement of joint meter readings issued by the state utility
Value(s) applied 0
Measurement methods
and procedures
Measurement : Tri-vector energy meter installed at receiving station
will be used for measurement of electricity import
Data Type : Measured
Recording : Monthly
Archiving Policy: Paper & Electronic
Accuracy : 0.2s class
The meter reading will be recorded jointly by the representatives of project
proponent and the state utility
Monitoring frequency Continuous
QA/QC procedures The energy meter will be sealed and will be in the custody of state utility.
Measurement results will be cross checked with records of electricity sold
(invoices / receipts).
The energy meters will be calibrated as per PPA
Purpose of data Calculation of baseline emissions
Additional comment The data monitored would be kept in electronic form and hard copy format
for 2 years after the end of crediting period or the last issuance of CERs for
this project activity, whichever occurs later.
Data / Parameter EGexport,y
Unit MWh
Description Electricity exported to the grid by the project activity during the year, y
Source of data Monthly statement of joint meter readings issued by the state utility
Value(s) applied 200,090
Measurement methods
and procedures
Measurement : Tri-vector energy meter installed at receiving station
will be used for measurement of electricity export
Data Type : Measured
Recording : Monthly
Archiving Policy: Paper & Electronic
Accuracy : 0.2s class
The meter reading will be recorded jointly by the representatives of project
proponent and the state utility
Monitoring frequency Continuous
QA/QC procedures The energy meter will be sealed and will be in the custody of state utility.
Measurement results will be cross checked with records of electricity sold
(invoices / receipts).
The energy meters will be calibrated as per PPA
Purpose of data Calculation of baseline emissions
Additional comment The data monitored would be kept in electronic form and hard copy format
for 2 years after the end of crediting period or the last issuance of CERs for
UNFCCC/CCNUCC
CDM – Executive Board Page 26
this project activity, whichever occurs later.
Data / Parameter EGfacility,y
Unit MWh
Description Quantity of net electricity generation supplied by the project activity to the
grid in year y
Source of data Monthly statement of joint meter readings issued by the state utility
Value(s) applied 200,090
Measurement methods
and procedures
The net electricity supplied to the grid will be calculated based on
measured values of electricity export and electricity import.
Monitoring frequency Continuous
QA/QC procedures The net electricity supplied to the grid will be cross checked with the
records of sold electricity.
Purpose of data Calculation of baseline emissions
Additional comment The data monitored would be kept in electronic form and hard copy format
for 2 years after the end of crediting period or the last issuance of CERs for
this project activity, whichever occurs later.
B.7.2. Sampling plan
>>
No sampling approach required for the parameters monitored in section B.7.1.
B.7.3. Other elements of monitoring plan
>>
A CDM project team would be constituted for monitoring of all the parameters described under
Sec.B.7.1. The team will be trained on CDM concept and monitoring plan. The team will be responsible
for data collection and archiving. This team will meet periodically to review CDM project activity, check
the data recorded in the log books and joint meter readings. In case of any irregularity observed, it shall
be informed to the concerned person for necessary action. On monthly basis, these reports shall be
forwarded to the management for their information.
Management Structure for monitoring emission reductions :
Designation Responsibilities
General Manager Conducting internal audits to check the accuracy of monthly electricity generated.
Plant Manager Verify the log books and other records maintained by shift incharge for its
correctness.
Recording of EGexport,y and EGimport,y jointly with the representative of State utility
for the purpose of issue of joint meter readings by the state utility.
All the data monitored under the monitoring plan would be kept in electronic form
and hard copy format for 2 years after the end of crediting period or the last
issuance of CERs for this project activity, whichever occurs later
Shift Incharge Maintain the daily log books for EGexport,y and EGimport,y
UNFCCC/CCNUCC
CDM – Executive Board Page 27
SECTION C. Duration and crediting period
C.1. Duration of project activity
C.1.1. Start date of project activity
>>
05/01/2012 (Contract for the purchase of equipment executed with GE India Industrial Private Limited)
C.1.2. Expected operational lifetime of project activity
>>
20 years (Source: GE Face Sheet – 1.6-82.5 Wind Turbine : http://www.ge-
energy.com/content/multimedia/_files/downloads/GEA18112B_1.6-82.5%20Wind%20Turbine_r1.pdf )
C.2. Crediting period of project activity
C.2.1. Type of crediting period
>> Renewable (first crediting period)
C.2.2. Start date of crediting period
>>
01/06/2013 or from the date of registration whichever occurs later
C.2.3. Length of crediting period
7 y-0m
SECTION D. Environmental impacts
D.1. Analysis of environmental impacts
>>
Since the project activity is electricity generation by installation of wind turbine generators, it does not
cause any negative impacts on the environment or socio-economic situation in the region and does not
require any environmental impact analysis.
D.2. Environmental impact assessment
>>
The project activity does not fall under the purview of Environmental Impact Assessment notification
S.O. 1533, dated 14th September 20064 (which is amended vide Notification S.O.1737(E) dt.11th
October, 2007, S.O.3067(E) dated 1st December, 2009, S.O.695(E) dt.6th April, 2011 and S.O.156(E)
dt.25th January, 2012) issued by Ministry of Environment and Forests (MoEF), Government of India
(GOI) and hence the project activity is exempted from environmental clearances. Since the project
activity is electricity generation by installation of wind turbine generators, it does not cause any negative
impacts on the environment or socio-economic situation in the region and does not require any
environmental impact analysis.
SECTION E. Local stakeholder consultation
E.1. Solicitation of comments from local stakeholders
>>
The project participant had invited local stakeholders for a meeting by way of affixing a notification at
Grampanchayat office on 12/01/2012 by giving week days time for submission of their suggestions /
comments on the project activity and conducted stakeholders meeting at Hotel Vimochan, Basavana
Bagewadi Taluka, Bijapur District, Karnataka on 20/01/2012 at 11.30 a.m. The meeting was attended by
local populace including Committee members. The representative of the project participant had
explained to the members attended, about the project activity and its contribution to protect the
environment from GHG emissions. Except suggestion to establish more number of wind projects and
4 http://envfor.nic.in/legis/eia/so1533.pdf
UNFCCC/CCNUCC
CDM – Executive Board Page 28
expression of their happiness on the economic benefit they got in selling their lands for the project
activity, there is no comment from stakeholders. The notice inviting stakeholders and the minutes of the
stakeholder meeting are furnished to the DOE for verification.
E.2. Summary of comments received
>>
No comments from the stakeholders attended to the meeting instead they expressed their happiness for
the PP’s decision to establish wind power projects in their location as it creates earning sources. The
Minutes of the stakeholder meeting is furnished to the DOE for verification.
E.3. Report on consideration of comments received
>>
No comments received; hence no report is applicable
SECTION F. Approval and authorization
>>
The letter of approval dt.11/10/2012 obtained from Indian DNA i.e., Ministry of Environment & Forests,
Government of India is provided to DOE for verification. .
- - - - -
UNFCCC/CCNUCC
CDM – Executive Board Page 29
Appendix 1: Contact information of project participants
Organization name Fortune Five Hydel Projects Private Limited
Street/P.O. Box # 1071, Road No.44, Jubilee Hills,
Building --
City Hyderabad
State/Region Andhra Pradesh
Postcode 500 033
Country India
Telephone +91- 40 40301000
Fax +91-40 40301101
E-mail [email protected]
Website www.fortunefiveprojects.com
Contact person
Title AVP
Salutation Mr.
Last name Mandapati
Middle name --
First name Tirumala Raju
Department --
Mobile +91 9959552323
Direct fax +91-40 40301101
Direct tel. +91- 40 40301000
Personal e-mail [email protected]
UNFCCC/CCNUCC
CDM – Executive Board Page 30
Appendix 2: Affirmation regarding public funding
The project does not propose to receive any public funding from the Official Development Assistance
(ODA) or other funds provided by any Annex I countries.
UNFCCC/CCNUCC
CDM – Executive Board Page 31
Appendix 3: Applicability of selected methodology
Applicability of the methodology ACM 0002 Version 12.3.0 for the project activity is described under
Section B.2
UNFCCC/CCNUCC
CDM – Executive Board Page 32
Appendix 4: Further background information on ex ante calculation of emission reductions
The information on ex ante calculation of emissions reductions is provided under Section B.6.1 and
B.6.3.
UNFCCC/CCNUCC
CDM – Executive Board Page 33
Appendix 5: Further background information on monitoring plan
As detailed in Section B.7.1., all the parameters would be monitored using calibrated meters. The project
would employ latest microprocessor based high accuracy monitoring and control equipment that would
measure, record, report, monitor and control various key parameters like electricity generated by the
project, electricity imported from the grid and net electricity exported to the grid. Necessary check
meters would be installed along with main meter for cross verification. These meters would be calibrated
and sealed as described under Sec.B.7.1 for each parameter.
Metering and Communication
The electricity generated at 690 kV by each wind turbine would be stepped up by Unit Transformer to 33
kV voltage level and would be transmitted to wind farm pooling substation through a net work of 33 kV
transmission lines. At the wind farm pooling substation, the power would be further stepped to 220 kV
level and transmitted through 220 kV double circuit lines connected to Karnataka Power Transmission
Corporation Limited’s substation at Basavana Bagewadi, which is located at about 12 km from the wind
farm.
Metering
One set of Main and Check energy meters will be installed at 33/220 kV pooling substation. The
electricity generation measured and recorded at these meters will be used for cross checking with the data
recorded at KPTCL Substation as and when required.
One set of dedicated Main and Check energy meters will be installed at KPTCL substation located at
Basavana Bagewadi. These meters will be used for metering the net electricity supplied to the grid by the
project activity. The electricity supplied to the grid recorded by these meters will be used for monthly
billing. These meters measure both (a) electricity exported by the Project to the Grid and (b) electricity
imported by the Project from the Grid. The energy meters installed for measuring electricity export and
electricity import will be of 0.2s accuracy class.
Meter Readings
The meter readings of electricity import and electricity export measured with energy meters installed at
KPTCL’s substation will be recorded jointly by the representatives of the project proponent and the state
utility every month on a particular day. The state utility will issue a statement of joint meter readings
consisting of electricity exported, electricity imported and net electricity supplied by the project to the
grid.
Meter Test Checking and calibration
All the main and check meters would be tested and calibrated as per power purchase agreement.
If during any testing and calibration, a Main meter is found to be within permissible limit of error and the
corresponding Check Meter is found to be beyond such limit of error, the Monthly Bill shall be as per the
reading of the Main Meter. The corresponding Check Meter shall be replaced forthwith with the spare
tested Meter and the defective Check Meter shall be repaired and calibrated by the Testing Laboratory or
replaced by a new and tested Check Meter.
UNFCCC/CCNUCC
CDM – Executive Board Page 34
If during any testing and calibration, a Main Meter is found to be beyond permissible limit of error but
the corresponding Check Meter is found to be within limit of error, the Monthly Bill shall, for that Month
and till the date and time of the repair and calibration or replacement of the defective Main Meter, be as
per the reading of the Check Meter. The corresponding Main Meter shall be replaced forthwith with a
spare tested and calibrated Meter, and the defective Main Meter shall be repaired and calibrated by the
Testing Laboratory or replaced by a new and tested Main Meter.
If during any testing and calibration, a Main Meter and the corresponding Check Meter are both found to
be beyond permissible limit of error, both the Meters or at least the Main Meter shall be replaced
forthwith with a spare tested calibrated Meter. At this time for the purpose of calculating electricity
generation, 99% of metered gross electricity generation will be considered from the time the defect or
failure of meter found till replacement of new/tested meters or repair, calibration and reinstallation of the
old meters.
PARAMETERS REQUIRING MONITORING
Electricity imported from the grid, electricity exported to the grid and net electricity generation supplied
by the project to the grid would be monitored under this monitoring protocol.
As per Indian DNA statute the project proponent is committed to spend 2% of CERs revenue every year
for Sustainable Development including society/community development at the project activity location.
This contribution will be utilised for development of basic infrastructure facilities like roads, lighting,
water supply etc. The developments will be verified with the documentary evidence of payments made
for the respective works.
Procedure for Record Management and Achieving
Log books will be maintained for each of the monitoring parameter described under Sec.B.7.1. All the
data monitored under the monitoring plan would be kept in electronic form and hard copy format for 2
years after the end of crediting period or the last issuance of CERs for this project activity, whichever
occurs later. The monitored data would be presented to the verification agency or DOE to whom
verification of emission reductions is assigned.
Internal audits of CDM project compliance
CDM audits shall be carried out for every six months by the internal auditing team to check the
correctness of procedures and data monitored. Report on internal audits done, faults found and corrective
action taken shall be maintained and kept for review of board of directors.
UNFCCC/CCNUCC
CDM – Executive Board Page 35
Appendix 6: Summary of post registration changes
Not applicable as the project is yet to achieve registration status
UNFCCC/CCNUCC
CDM – Executive Board Page 36
History of the document
Version Date Nature of revision
04.1 11 April 2012 Editorial revision to change version 02 line in history box from Annex 06 to Annex 06b.
04.0 EB 66 13 March 2012
Revision required to ensure consistency with the “Guidelines for completing the project design document form for CDM project activities” (EB 66, Annex 8).
03 EB 25, Annex 15 26 July 2006
02 EB 14, Annex 06b 14 June 2004
01 EB 05, Paragraph 12 03 August 2002
Initial adoption.
Decision Class: Regulatory
Document Type: Form
Business Function: Registration