project - mydocsmydocs.dot.ga.gov/info/designbuild/shared documents/0010925...project as it relates...
TRANSCRIPT
Project #:
Pavement Design Package Submittal Checklist
PI #:
County:
Project Manager Office:
Project Manager:
Designer's Office/Company:
Design Phase Leader:Date Package Submitted:
MGMT Let Date: Expected Construction Length (months):
Brief Project Description (examples: widen and reconstruct 2 to 4-lane, interchange reconstruction):
Note: A more detailed pavement project description will be attached. This description will be focused on the project as it relates to the pavement designs being proposed.
Please check all items below that are attached before submitting your package to your Project Manager. (Note 1) Include this checklist in your pavement design package submittal. NOTE 1: GDOT Design Phase Leaders (DPL) submit their packages to the State Roadway Design Engineer (SRDE) or designee instead of their Project Manager. 1) Construction Plan Sheets (11” x 17” is acceptable if legible)
CoverTypical Sections Staging Typical Sections (Note 2)
Traffic Diagrams (Note 3)
Note 2: Staging typicals are required when temporary pavement sections are proposed.
Note 3: Include GDOT Office of Planning review and approval correspondence for traffic diagrams prepared by consultants.
2) Reports and Summaries (Note 4)
Soil Survey Summary (Note 5)Pavement Evaluation SummaryPavement Type Selection ReportGDOT's VE Study Implementation Correspondence
Note 4: Include GDOT Office of Materials and Research review and approval correspondence for reports and summaries prepared by consultants. Note 5: One package will include a copy of the complete Soil Survey including sample test data. The remaining copies only require the Soil Survey Summary.
3) Quality Assurance (QA) - (required for Consultant DPL submittals)
SRDE QA Review SheetsConsultant DPL QA Review Responses
4) Design Analysis
Full Depth Rigid PavementOverlay Rigid PavementFull Depth Flexible PavementOverlay Flexible Pavement
Number of Designs -Number of Designs -Number of Designs -Number of Designs -
Mgmt Let Date:
PI No: Project No: Submitted by:
County: SR: Date Received:
OPD PM: WFTK: CST Funding:
1
2015/2035
N/A
Traffic Diagrams1. Only include the "Build" ADT and DHV traffic diagrams. The "No Build" and the existing year traffic diagrams are notneeded in the pavement design package.2. Based on the Management Let Date and an assumed construction length of two years; the initial and final design yearshould be 2017/2037, respectively.
Pavement Design Package Submittal Checklist1. A Pavement Design Package Submittal Checklist that is available on the GDOT ROADS website needs to be included in thepackages sent to the Committee.2. As stated on the checklist; include all plan sheets as half size sheets.
Pavement Design1. The Consultant Design Phase Leader needs to sign the "Recommended By" line on all of the pavement designs.2. On the Riverside Dr. full depth pavement design, the lanes in each direction needs to be changed to one.3. Even though 5 inches of 25mm SP is allowed by Sec. 400 Shelf Special Provision, the Office of Materials has requested thatthe Pavement Design Committee not approve designs using this due to possible construction issues.4. The underdesign percentage for the Riverside Dr. full depth pavement design is not within the required underdesign valueof 0 - 5% for roadways with curb and gutter. Also, the roundabout traffic data and LDF should be used; if it is higher.5. The overlay pavement design for Riverside Dr. is incorrect. There is no Pavement Evaluation Summary that details theexisting pavement structure. As noted on the design remarks; the plans that the existing pavement information was gatheredfrom need to be included in the pavement package.6. The existing pavement structure shown for the overlay pavement design seems to be unrealistic. There is only 2 inchesof existing asphalt. Also, clarify if the Pavement Evaluation Summary is pending.7. On the Riverside Dr. overlay pavement design the form should show 2 lanes in one direction and the LDF should be modified.8. Since there is no Soil Survey Report available yet; typical county values should be used for the soil support value and regionalfactors. Also, clarify if a Soil Survey Report will be done for this project.9. On the Riverside Dr. overlay pavement design; according to the typical sections, there is no reason why a thicker pavement structure cannot be provided that will ensure the underdesign value is within or close to the 0 - 5% required range.10. The ramps should not be constructed with CRCP as the design analysis reflects. Use JPCP to construct the ramps; whichthe typical sections and the project description show.11. Separate ramp designs can be proposed if desired to possibly save on the construction material costs; since each ramp hasdifferent traffic data.
Typical Sections1. Use the full pay item description for all of the pavement layers.2. Include the Class B Base and Pavement Widening Detail.3. Extend the 19mm Superpave interlayer 2 ft. beyond the vertical edge of the concrete paving.4. Milling is shown on the overlay design but is not shown on the overlay typical sections; E.g. Riverside Dr. typical Section.5. The Riverside Dr. mainline and roundabout typical sections show different thicknesses for the 25mm layer (Label C).
Cover Sheet1. Show the begin/end location for the Ramp A - D construction.
GDOT Office of Roadway Design QA Review By:
Pavement Design Package Quality Assurance Review Sheet 11/15/2015
0010925 0010925 IPD
Fulton N/A 5/5/2014
Marlo Clowers $2,080,800.00
Full Depth Concrete: 1 Overlay Asphalt: Full Depth Asphalt: 1
Overlay Concrete: N/A Traffic Data: Pavement Eval Summary: Not Included
VE Study Immplementation:
N/A Soil Survey: Pavement Type Selection: 3/11/2010
g:\tra\gdot i-285\riverside\rdy\pavement design\riverside supporting docs\04_consultant_qa_responses.docx Page:
1/3
Subject:
Riverside Drive Roundabouts Pavement Design Package Quality Assurance Review Consultant Responses PI No. 0010925
From:
Ryan Graves
Date: ARCADIS Project No.:
May 16, 2014 GADT0201.0141
Traffic Diagrams 1. Only include the "Build" ADT and DHV traffic diagrams. The "No Build" and the existing year traffic diagrams are
not needed in the pavement design package. ARCADIS Response: Only “Build” ADT and DHV traffic diagrams will be included with the
pavement design submittal. 2. Based on the Management Let Date and an assumed construction length of two years; the initial and final design
year should be 2017/2037, respectively. ARCADIS Response: The Riverside Drive Roundabout project is being advanced as a
design-build project and the project schedule has been accelerated. The interchange is expected to open to traffic in 2015.
Pavement Design Package Submittal Checklist 1. A Pavement Design Package Submittal Checklist that is available on the GDOT ROADS website needs to be
included in the packages sent to the Committee. ARCADIS Response: The current Pavement Design Package Submittal Checklist, from the
GDOT R.O.A.D.S. website, will be included with the pavement design submitted to the Pavement Design Committee.
2. As stated on the checklist; include all plan sheets as half size sheets. ARCADIS Response: Construction Plan sheets will be included with the Pavement Design
Submittal.
ARCADIS U.S., Inc.
2410 Paces Ferry Road
Suite 400
Atlanta
Georgia 30339
Tel 770.431.8666
Fax 770.435.2666
www.arcadis-us.com
TRANSPORTATION
Contact:
Ryan Graves
Phone:
770.431.8666
Email:
g:\tra\gdot i-285\riverside\rdy\pavement design\riverside supporting docs\04_consultant_qa_responses.docx Page:
2/3
Pavement Design 1. The Consultant Design Phase Leader needs to sign the "Recommended By" line on all of the pavement designs.
ARCADIS Response: The Consultant Design Phase Leader will sign “Recommended By” line on all pavement designs.
2. On the Riverside Dr. full depth pavement design, the lanes in each direction needs to be changed to one. ARCADIS Response: The number of lanes in each direction will be changed to one for the
Riverside Drive Full depth pavement design. 3. Even though 5 inches of 25mm SP is allowed by Sec. 400 Shelf Special Provision, the Office of Materials has
requested that the Pavement Design Committee not approve designs using this due to possible construction issues.
ARCADIS Response: A depth of 7 inches for 25mm superpave will be used instead of 5 inches on all flexible pavement designs.
4. The underdesign percentage for the Riverside Dr. full depth pavement design is not within the required underdesign value of 0 - 5% for roadways with curb and gutter. Also, the roundabout traffic data and LDF should be used; if it is higher.
ARCADIS Response: The Riverside Drive pavement design will be adjusted to be within the required underdesign percentage range of 0-5%. Due to the addition of right turn lanes to all the roundabout approaches traffic in a single lane will not be greater than the traffic volume shown for Riverside Drive, which will be used for the full depth pavement design on Riverside Drive.
5. The overlay pavement design for Riverside Dr. is incorrect. There is no Pavement Evaluation Summary that details the existing pavement structure. As noted on the design remarks; the plans that the existing pavement information was gathered from need to be included in the pavement package.
ARCADIS Response: In response to comments by the State Pavement Engineer, a pavement evaluation was not completed and as-built plans were used to determine existing pavement sections. The existing plans will be included in the Pavement Design Package.
6. The existing pavement structure shown for the overlay pavement design seems to be unrealistic. There is only 2 inches of existing asphalt. Also, clarify if the Pavement Evaluation Summary is pending.
ARCADIS Response: A pavement evaluation is not proposed for the project. As-built plans were used to determine the existing pavement section of Riverside Drive. These plans indicate that Riverside Drive was constructed with only 2 inches of asphalt. The pertinent existing plan sheets will be included with the Pavement Design Package.
7. On the Riverside Dr. overlay pavement design the form should show 2 lanes in one direction and the LDF should be modified.
ARCADIS Response: Riverside Drive will only have two lanes in one direction on the approaches to the interchange, where right turn lanes will be added. The travel lanes leaving the interchange will remain just a single lane. For this reason the LDF for the overlay section was kept as 1 lane. Proposed construction plan sheets will be included in the Pavement Design Package so that the lane configurations of the proposed construction are clearer.
8. Since there is no Soil Survey Report available yet; typical county values should be used for the soil support value and regional factors. Also, clarify if a Soil Survey Report will be done for this project.
ARCADIS Response: Typical county values for soil support values and regional factors were used when preparing the pavement evaluations.
g:\tra\gdot i-285\riverside\rdy\pavement design\riverside supporting docs\04_consultant_qa_responses.docx Page:
3/3
9. On the Riverside Dr. overlay pavement design; according to the typical sections, there is no reason why a thicker pavement structure cannot be provided that will ensure the underdesign value is within or close to the 0 - 5% required range.
ARCADIS Response: A pavement design on Riverside Drive that would provide and underdesign value within the 0-5%required range would require 5.5 inches of 19mm leveling. While the project does propose replacing curb & gutter along the entire length of the project it is crucial to minimize grade changes along much of the project corridor as this would increase impacts to adjacent parcel. This is especially critical in the area adjacent to the historically eligible resource in the southwestern quadrant of the interchange.
10. The ramps should not be constructed with CRCP as the design analysis reflects. Use JPCP to construct the ramps; which the typical sections and the project description show.
ARCADIS Response: The ramp pavement design will be updated to show JPCP 11. Separate ramp designs can be proposed if desired to possibly save on the construction material costs; since
each ramp has different traffic data. ARCADIS Response: For simplicity, only one pavement design will be proposed for the ramps
at this time. The design-build team may propose alternate pavement sections for the ramps.
Typical Sections 1. Use the full pay item description for all of the pavement layers.
ARCADIS Response: Full pay item descriptions will be used on the typical sections. 2. Include the Class B Base and Pavement Widening Detail.
ARCADIS Response: The Class B Base and Pavement Widening Detail will be included with the project typical sections.
3. Extend the 19mm Superpave interlayer 2 ft. beyond the vertical edge of the concrete paving. ARCADIS Response: The 19mm Superpave interlayer will be extended 2 feet beyond the
vertical edge of the concrete paving. 4. Milling is shown on the overlay design but is not shown on the overlay typical sections; E.g. Riverside Dr.
typical Section. ARCADIS Response: Milling will be shown on the Riverside Drive overlay typical section
5. The Riverside Dr. mainline and roundabout typical sections show different thicknesses for the 25mm layer (Label C). ARCADIS Response: The thickness of the 25mm pavement layer will be revised to be
consistent between the Riverside Drive typical section and the roundabout typical section. Cover Sheet
1. Show the begin/end location for the Ramp A - D construction. ARCADIS Response: Limit of construction labels will be added to the cover sheet for all
ramps.
P.I. 0010925, Fulton County, Riverside Drive at I-285 Interchange Improvements
Detailed Project Description: The proposed Design-Build project is located on Riverside Drive at the
interchange with I-285 in Fulton County Georgia and is within the city limits of Sandy Springs. The
project consists of safety improvements to the existing interchange which will convert the two existing
signalized intersections at each ramp terminal with roundabouts.
The current roadway configuration of Riverside Drive consists of one, twelve foot lane in both directions
and traffic signals at the ramp termini. There are no turn lanes at the intersections with the I-285
entrance ramps, resulting in turning vehicles blocking the through movements. The existing bridge only
provides for two lanes of traffic, one northbound and one southbound. The eastbound and westbound I-
285 off ramps each consists of a single, sixteen foot lane. There are no existing sidewalks approaching
the bridge, however there are existing sidewalks on the bridge itself. The existing right-of-way along
Riverside Drive varies from 50 to 100 feet.
The proposed Design-Build project will convert the signalized intersections at the ramp termini to single
lane roundabouts, one at each intersection. Each approach to the roundabout will be widened to two
lanes with one lane entering the roundabout and the other serving as a right turn lane. Sidewalks will
be added to both sides of the roadway along Riverside Driveway within the limits of the project. The
project is approximately 0.5 mile length.
The project will also include routine rehabilitation of the existing bridge. This work includes
replacement of the joints at bent 2 and abutments 1 and 5. All construction joints will be resealed and
the bridge deck will be sealed with a two-part polymer overlay. Concrete spalling will be repaired on
bents 3 & 4 and abutment 5.
Proposed Pavement DescriptionThe full depth flexible pavement section for Riverside Drive will consist of 12” GAB base layer, 5” 25mmsuperpave intermediate layer, and top layer of 2” 19mm superpave, 1.5” 12mm superpave. This willproduce a SN of 5.10, and the required SN is 5.70 resulting in a 10.52% underdesign.
The existing overlay flexible pavement section for Riverside Drive will consist of existing 6” GAB baselayer, an existing 5” cement stabilized graded aggregate, an existing 1.5” asphalt concrete intermediatelayer, and a proposed top layer of 2” 19mm superpave, 1.5” 12mm superpave. This will produce a SN of3.39, and the required SN is 5.70 resulting in a 40.52% underdesign.
The full depth rigid pavement section for the interstate ramps will consist of 10” GAB base layer, 3” of19mm superpave intermediate layer, and top layer of 9” plain concrete pavement. This will result in apavement that is 14.24% understressed and 16.60% overdesigned.
01-
PROJECT LOCATION
MILES
DATE
FEDERAL AID PROJECT
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
PLANS COMPLETED - -
REVISIONS
FEDERAL ROUTE # N/A
STATE ROUTE # N/A
P.I. NO. 0010925 FULTON COUNTY
COSTING PLANS OF PROPOSED
NET LENGTH OF EXCEPTIONS
GROSS LENGTH OF PROJECT
NET LENGTH OF ROADWAY
NET LENGTH OF BRIDGES
NET LENGTH OF PROJECT
LENGTH OF PROJECT
SUBMITTED BY:
RECOMMENDED FOR
SUBMISSION BY:
TRAFFIC A.D.T.:
TRAFFIC A.D.T.:
TRAFFIC D.H.V.:
DIRECTIONAL DIST:
SPEED DESIGN:
24 HR.TRUCKS %:
% TRUCKS:
DESIGN DATA:
INTERCHANGE IMPROVEMENTSRIVERSIDE DRIVE AT I-285
LOCATION SKETCH
DESIGNED IN ENGLISH UNITS.
PROJECT DESIGNATION: EXEMPT
CHIEF ENGINEER
STATE DESIGN ENGINEER
DESIGN
19,350 (2015)
21,580 (2035)
1745 (2035)
8.5%
8%
35 MPH
01-001SUBSECTIONS 102.04, 102.05, AND 104.03 OF THE SPECIFICATIONS.
OF TRANSPORTATION IN ANY WAY. THE ATTENTION OF BIDDER IS SPECIFICALLY DIRECTED TO
SAME ARE SHOWN AS INFORMATION ONLY, ARE NOT GUARANTEED, AND DO NOT BIND THE DEPARTMENT
FIELD INVESTIGATIONS AND ARE BELIEVED TO BE INDICATIVE OF ACTUAL CONDITIONS. HOWEVER, THE
INDICATED THEREBY, WHETHER BY DRAWINGS OR NOTES, OR IN ANY OTHER MANNER, ARE BASED UPON
THE DATA, TOGETHER WITH ALL OTHER INFORMATION SHOWN ON THESE PLANS OR IN ANYWAY
THE DEPARTMENT OF TRANSPORTATION.
STATE HIGHWAY DEPARTMENT OF GEORGIA, AND SHALL BE DEEMED TO MEAN
DEPARTMENT ", OR " DEPARTMENT " WHEN THE CONTEXT THEREOF MEANS THE
HIGHWAY DEPARTMENT ", GEORGIA STATE HIGHWAY DEPARTMENT ", " HIGHWAY
WITH THIS DOCUMENT, TO " STATE HIGHWAY DEPARTMENT OF GEORGIA ", "STATE
DOCUMENTS, DRAWINGS, OR PHOTOGRAPHS USED, OR TO BE USED IN CONNECTION
ALL REFERENCES IN THIS DOCUMENT, WHICH INCLUDES ALL PAPERS, WRITINGS,
NOTE :
APPROVAL DATE:
LOCATION & DESIGN
URBAN MINOR ARTERIAL
FUNCTIONAL CLASS:
56% IN CONG. DIST. 6
44% IN CONG. DIST. NO. 11 &
FULTON COUNTY AND IS
THIS PROJECT IS 100% IN
OF 1988.
AMERICAN VERTICAL DATUM (NAVD)
1983)/94 WEST ZONE, AND THE NORTH
COORDINATE SYSTEM OF 1984 (NAD
USING THE HORIZONTAL GEORGIA
THIS PROJECT HAS BEEN PREPARED
COUNTY No. 121
0010925
Project No.
FULTON COUNTY, GA
LAND DISTRICT 17
LAND LOTS 133, 166
PROJECT IS LOCATED IN
0.239
0.000
0.239
0.190
0.049
PLANS PREPARED BY:
UNDER THE SUPERVISION OF:
SHAMIR POUDEL, P.E.
0.50/0.50 (N.B./S.B.)
400 800
SCALE IN FEET
0 200
TS AT
E
OG
FE
O
RGIA
17
76
CONSTIT
UTI
ON
JU
STI
CE
OM
DER
ATIO
NDO
M
WIS
5/16/2014
USER:rgraves
GPLOT-V8
gplotborder-V8i-PO.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_01-001.dgn
GRWCOV
SHEET NO.PROJECT NUMBER
TOTAL SHEETSSTATE
GA
CONCOV
DRAWING No.
I-285
TO ATLANTA
E 2223772.7112
N 1423985.9348
RIVERSIDE DRIVE
STA 104+32.67
BEGIN PROJECT
E 2223782.9738
N 1425245.9152
RIVERSIDE DRIVE
STA 116+92.69
END PROJECT
SANDY SPRINGS
TO
LL 166
LL 133
100+00
105+00
110+00
115+00
120+00
RIVERSIDE DR.
RA
MP
A
RA
MP
B
RA
MP
C
RA
MP
D
E 2223777.7135N 1424600.0920
STA 110+73.23PROJECT MIDPOINT
RAMP ’A’
STA 26+39.33
LIMIT OF CONSTRUCTION
RAMP ’B’
STA 63+55.47
LIMIT OF CONSTRUCTION
RAMP ’C’
STA 2+81.03
LIMIT OF CONSTRUCTION
RAMP ’D’
STA 45+33.68
LIMIT OF CONSTRUCTION
RA
MP B
RIVERSIDE DRIVE
RA
MP C
RIVERSIDE DRIVE
RA
MP B
RAMP A
RA
MP
A
RA
MP C
RA
MP
D
RA
MP
D
COL
DSTRE
AM C
OURT
RIVERSIDE DRIVE
GDOT DETAIL RA-1LANDSCAPING AS PER
DO NOT DISTURB SIGN
STA 111+12.64
END EX. BRIDGE
STA 108+51.79
BEGIN EX. BRIDGE
GDOT DETAIL RA-1LANDSCAPING AS PER
DE
NTE
NTI
ON STR
UCT
URE
POTE
NTI
AL ST
OR
MW
ATER
GR
ADE T
O
DR
AI
NP
AVE
ME
NT
RE
MO
VE E
X.
TYP.CONC. ISLAND
6" RAISED
ISLAND TYP.6" RAISED CONC.
PA
VE
D
DIT
CH
PA
VE
D
DIT
CH
PA
VE
D
DIT
CH
PA
VE
D
DIT
CH
Smyrna
1
14
12
1
12
Brokhaven
22
7
N.R.A.RIV 4
421
CHAT
ATLUSNAS
AFB
120Lp
2
2
2
2
2
2
NAT’L. CEMMARIETTA
2
3
2
2
1
3
1
COBB
DOBBINS
10
17
1
6
11
3
Chamblee
2
SpringsSandy
Doraville
78,278
280
236
9
120
41
140
400
TEAD1 ST
TPBL5 ST
LL166
LL133
LL166
LL133
LL166
LL133
APPROX LOCATION L.L.L.
APPROX LOCATION L.L.L.
APPROX LOCATION L.L.L.
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
14
13
19
21
74
75
69
65
44
42
43
38
16
17
20
39
73
32
33
12725
13203
68
Profile Grade
2% 2%
12’-0"
Travel Lane Travel Lane
12’-0"
2:1
MAX
2:1 MAX
2% 2%2:
1 MAX
2:1 MAX
5’-0"2’-6"
Sidewalk
Shoulder
5’-0"
Sidewalk
2’-6"
CL
GADOTLOWNDES
0’-0" to 12’-0"
Turn Lane
Varies
2’-0"
10’-0"
Shoulder
10’-0"
2’-0"
0’-0" to 12’-0"
Turn Lane
Varies
Travel Lane Travel Lane
& S.E. Pivot Point
Profile Grade
or S.E.
2%
12’-0" to 16’-0" 0’-0" to 12’-0"
Varies Varies
2’-6"
6.25%
10’-0"
3’-0"
9’-0"
NOT TO SCALE
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-V8i-PO-utilities-25.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_TYP.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
OFFICE:
TYPICAL SECTIONS
05-001
PI No. 0010925
8:44:00 PM
GPLN
STATE
GA
6/20/2011
LB
2:1 MAX
GADOTLOWNDES
Existing Shoulder
6’-0"
ShoulderPaved
Existing
Travel Lane Travel Lane
& S.E. Pivot Point
Profile Grade
or S.E.
2%
0’-0" to 12’-0" 12’-0" to 16’-0"
Varies Varies
2’-6"
6.25%
10’-0"
LB
2:1 MAX
Varies
Widening
0’-0" to 8’-0"
Existing Pavement
16’-0"
GADOTLOWNDES
Exist. Concrete V-Gutter
Exist. Conc. Curb & Gutter
Exist. Type T Guardrail
Exist. Pavement Varies
20’-0" to 24’-0"
I-285 EASTBOUND EXIT RAMP
TYPICAL SECTION
I-285 WESTBOUND EXIT RAMP
TYPICAL SECTION
FOR DESIGN-BUILD
COSTING PLANS
G
D
C
B
A
6" 6"
OUTSIDE OF INTERCHANGE
RIVERSIDE DRIVE
TYPICAL SECTION
E
AF
D
C
B
AF
J
I
G
J
I
G
6"
2% 2%
Existing Pavement
16’-0"
Varies
Widening
0’-0" to 8’-0"
K K
Exist. Concrete Pavement
Exist. Concrete Pavement
Exist. Asphalt Pavement
C
A
B
D
REQUIRED PAVEMENT
E
F
G
H
I
J
K
GP 2 ONLY, INCL BITUM MATL & H LIME
165 LB/SY RECYCLED ASPH CONC 12.5 MM SUPERPAVE,
GP 1 OR 2,INCL BITUM MATL & H LIME
220 LB/SY RECYCLED ASPH CONC 19 MM SUPERPAVE,
GP 1 OR 2, INCL BITUM MATL & H LIME
RECYCLED ASPH CONC 25 MM SUPERPAVE, 770 LB/SY
GR AGGR BASE CRS, INCL MATL12"
& H LIME, AS REQUIRED
RECYCLED ASPH CONC LEVELING, INCL BITUM MATL
CONC SIDEWALK, 4 IN
CONC CURB AND GUTTER, 8 IN X 30 IN, TYPE 2
CONC CURB AND GUTTER, 8 IN X 30 IN, TYPE 7
PLAIN PC CONC PVMT, CL 3 CONC, 9 INCH THK
GP 1 OR 2, INCL BITUM MATL & H LIME
330 LB/SY RECYCLED ASPH CONC 19 MM SUPERPAVE,
10" GR AGGR BASE CRS, INCL MATL
2’
6"
2’
L MILL ASPH CONC PVMT, VARIABLE DEPTH L
2%2%
LC
1’-0"5’-0" 14’-0" 14’-0" 5’-0"
1’-0"SidewalkSidewalk
Profile Grade
NOT TO SCALE
2’-6"
2%
5’-0"
Sidewalk
2’-0"
Shoulder
10’-0"
LC
Landscaping
Central Island
Central Island
4% to 6:1
4:1 MAX
Plain PC Concrete
Graded Aggregate Base
Concrete Header Curb,
4 inch, Type 9
Concrete Header Curb,
6 inch, Type 7
Center of Roundabout
1% to 2%
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-V8i-PO-utilities-25.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_TYP.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
OFFICE:
TYPICAL SECTIONS
05-002
PI No. 0010925
8:45:05 PM
GPLN
STATE
GA
6/20/2011
Circulatory Roadway
18’-0"Varies
Truck Apron
Exist. Travel LaneExist. Travel Lane
& S.E. Pivot Point
Profile Grade
or S.E.
2%
2’-6"
6.25%
10’-0"
LB
2:1 MAX
GADOTLOWNDES
0’-0" to 16’-0"
Varies
Exist. Pavement
0’-0" to 18’-0"
Varies
Prop. Pavement
16’-0" to 18’-0"
Varies
Travel Lane 10’-0"
2%
2’-6"
7’-6" to 25’-3"16’-3" to 34’-0"
42’-0"
I-285 ENTRANCE RAMPS
TYPICAL SECTION
RIVERSIDE DRIVE BRIDGE OVER I-285
TYPICAL SECTION
RIVERSIDE DRIVE ROUNDABOUT
TYPICAL SECTION
FOR DESIGN-BUILD
COSTING PLANS
C
A
B
D
REQUIRED PAVEMENT
E
F
G
H
I
J
I
G
6"
K
D
C
B
A
6"
G
(SEE GDOT CONSTR. DETAIL RA-2)
J
K
K
Exist. Concrete Pavement
GP 2 ONLY, INCL BITUM MATL & H LIME
165 LB/SY RECYCLED ASPH CONC 12.5 MM SUPERPAVE,
GP 1 OR 2,INCL BITUM MATL & H LIME
220 LB/SY RECYCLED ASPH CONC 19 MM SUPERPAVE,
GP 1 OR 2, INCL BITUM MATL & H LIME
RECYCLED ASPH CONC 25 MM SUPERPAVE, 770 LB/SY
GR AGGR BASE CRS, INCL MATL12"
& H LIME, AS REQUIRED
RECYCLED ASPH CONC LEVELING, INCL BITUM MATL
CONC SIDEWALK, 4 IN
CONC CURB AND GUTTER, 8 IN X 30 IN, TYPE 2
CONC CURB AND GUTTER, 8 IN X 30 IN, TYPE 7
PLAIN PC CONC PVMT, CL 3 CONC, 9 INCH THK
GP 1 OR 2, INCL BITUM MATL & H LIME
330 LB/SY RECYCLED ASPH CONC 25 MM SUPERPAVE,
10" GR AGGR BASE CRS, INCL MATL
CLASS "B" CONCRETE
SURFACE COURSE
WIDTH
EXCAV.
AREA
0.0 < WIDTHS < 5.0
6" MIN.
NO SCALE
Item Code 500-9999 - Cu. Yds.
CLASS "B" CONCRETE BASE OR PAVEMENT WIDENING
In excavated areas greater than 5’-0" in width, the Contractor shall
place base and paving as specified on the typical section.
In excavated areas between the existing paving and new curb and gutter
that are 5’-0" or less in width, Class "B" concrete shall be placed in lieu
of the base and paving specified by the typical section. Payment will be
made under "Class B Concrete Base and Pavement Widening".
CLASS "B" CONCRETE BASE OR WIDENING DETAIL
See plans for details of curb and gutter construction.2’
L MILL ASPH CONC PVMT, VARIABLE DEPTH
Department of Transportation State of Georgia
___________________________________________________________________
INTERDEPARTMENT CORRESPONDENCE
FILE Fulton County OFFICE Planning P.I. # 0010925
DATE November 14, 2013
FROM Cynthia L. VanDyke, State Transportation Planning Administrator TO Darryl D. VanMeter, State Innovative Program Delivery Engineer Attention: Marlo Clowers, P.E.
SUBJECT Design Traffic Review for I-285 RAMPS @ CR 209/RIVERSIDE DRIVE.
We have reviewed the consultant’s Design Traffic data for the above project. The Design Traffic is approved.
If you have any questions concerning this information, please contact Rhonda Niles at (404) 631-1924.
CLV/RFN
13-001
MAINLINE PLANEASEMENT FOR CONSTR
EASEMENT FOR CONSTR OF SLOPES
EASEMENT FOR CONSTR OF DRIVES
CONSTRUCTION LIMITS
& MAINTENANCE OF SLOPES
C F
REQUIRED R/W LINE
PROPERTY AND EXISTING R/W LINE PL
LIMIT OF ACCESS
BEGIN LIMIT OF ACCESS............BLA
END LIMIT OF ACCESS..............ELA
REQ’D R/W & LIMIT OF ACCESS
20
SCALE IN FEET
0 40 80
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-V8i-PO.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_13-001.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
OFFICE:
8:18:26 PM
GPLN
STATE
GA
12/14/2012
SEE
DR
AWI
NG
No. 13-002
MAT
CH LI
NE ST
A 109+50
SEE DRAWING No
. 14-002
MATCH LINE S
TA 61+50
SEE DRAWING No. 14-001
MATCH LINE STA 29+00
COUNTY: FULTON
PROJECT: PI 0010925FOR DESIGN-BUILD
COSTING PLANS INNOVATIVE DELIVERY
PI 0010925
ORANGE BARRIER FENCE
LINE AND INSTALL
EXISTING RIGHT-OF-WAY
UP TO 5 FEET BEYOND
PRUNE AMERICAN HOLLY
104+00
105+00
106+00
107+00
108+00
109+00
29+00
30+00
WALL #1
WALL #2
CONSTRUCTION CL
CONSTRUCTION CL
P.C.
60+9
1.18
P.C. 29+37.70
P.T. 29+96.51
P.I. 29+68.15
RIVERSIDE DRIVE
STA 104+46.45
BEGIN CONSTRUCTION
10’+/-
14’+/-
27.35’
+60.91
TAPER 8:1
R=60’
R=800’
R=80’
R=100’
R=500’
R=270’
10.00’
+33.27
R=100’
18’
16’
16’
18.5’
11.54’ RT
STA 107+37.22
18’
8’
12’
12’
GRADE TO DRAINPAVEMENTREMOVE EX.
E= 4.91
R= 92.00
L= 58.81
T= 30.45
E= 2223695.02
N= 1424320.84
PI Sta= 29+68.15
Curve# 1
CUR
VE #1
17.7
1’+28.
67
6.36’
16.18’
16.36’
18.36’
15.65’
25.89’
111’R
486’R
518’R
289’R
218’R
98’R
200’R
ORANGE BARRIER FENCE
CURVE #2
E= 11.04
R= 800.00
L= 264.29
T= 133.36
E= 2223970.12
N= 1424348.05
PI Sta= 62+24.54
Curve# 2
108R
WALL
SOUND
REPLACE
100R
RIVERSIDE DRIVE
RA
MP B
RAMP A
200R
500R
STA 60+00.00 RAMP ’B’
RIVERSIDE DRIVE=
STA 106+84.11
INTERSECTION
STA 30+75.76 RAMP ’A’
STA 106+92.32 RIVERSIDE DRIVE=
INTERSECTION
RIVERSIDE DRIVE
STA 104+32.67
BEGIN PROJECT
STA 108+51.79
BEGIN EX. BRIDGE
GDOT DETAIL RA-1LANDSCAPING AS PER
TYP.CONC. ISLAND
6" RAISED
100R
501R
IN
V=1012.63’
TO
P=1015.63’
IN
LE
T
15"RCP
INV=1044.19’
TOP=1047.39’
CB
TOP OF SILT
INV=1045.90’
TOP=1047.40’
CB
IN
V=1040.94’
IN
V=100
5.20’
TO
P=100
8.50’
DI
IN
V=1004.98
RCP
15"
12"CMP
12"CMP
IN
V=101
4.06’
IN
V=1011.10’
FR
OM
PL
AN
S
BU
RI
ED
JB
DRIV
EW
AY
AS
PH
AL
T
PA
VE
D
DRIV
EW
AY
ASP
HA
LT P
AV
ED
ASPHALT PAVING
PARKING
ASPHALT PAVED
PARKING
ASPHALT PAVED
ASPHALT PAVING
DRIV
EW
AY
ASP
HALT P
AVE
D
CONC.
PA
VE
D
DIT
CH
15
DP
C
F/L 1004.98’
12 DPM
F/L ’1011.10’
12 DPM F/
L ’1
014.
06’
18
DP
C
F/L 1040.94’
Location
CD
#
Co
ntrol
Re-
Shot
#
Co
ntrol
Re-
Sh
ot
#
L
ocatio
n
CD
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Locati
on
CD
#
L
ocation
CD
#
Control
Re-
Shot
#
Control
Re-
Shot
#
C
ontrol
Re-
Shot
#
Locati
on
CD
#
Co
ntrol
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
C
ontrol
Re-
Shot
#
Location
CD
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Sh
ot
#
Co
ntrol
Re-
Sh
ot
#
Location
CD
#
Co
ntrol
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Sh
ot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Contr
ol
Re-
Sh
ot
#
L
ocati
on
CD
#
Location
CD
#
Control
Re-
Shot
#
Locatio
n
CD
#
26.64
STA +32.67
38.41
STA +32.67
60.00
STA +50.00
-23.38
STA +35.00
-35.00
STA +35.00
-35.00
STA +59.92
40.33
STA +78.06
37.28
STA +59.75
26.71
STA +69.07
-55.00
STA +60.33
-70.00
STA +95.65
112.69
STA +95.77
-90.40
STA +96.08
-111.95
STA +38.29
-77.27
STA +55.99
-81.72
STA +64.72
-142.37
STA +10.83
-92.20
STA +85.25 -125.57
STA +10.61NEED FAIR OAKS MANOR S/D
NO DEED FOUND
N/F
E. FRANK TIMMERMAN
N/FJANE L.NATIONS
L. DEAN NATIONS &
N/F
UNITED PRESBYTERIAN CHURCH, U.S.A.
THE PRESBYTERY OF ST. ANDREW
N/F
REQ’D
R/W
RE
Q’D
R/
W
1
3
4
2
REQ’D R/W
KC1001
KC1002
KC1003
KC2001
KC2002
KC3001
KC3002
KC3003
KC3004
KC4001
KC4002
KC4003
KC4004 KC4005
KC4006
KC4007
LL166
LL133APPROX LOCATION L.L.L.
RIVERSIDE DRIVE
STA 104+32.67
BEGIN R/W ACQUISITION
PL
PL
SEE SHEET
SEE SHEET
SEE SHEET$RW04$
$RW04$
$RW04$
$RW05$SEE SHEET
14
13
19
21
32
33
EXIST R/
W
& L/
A
EXIST
R/
W
& L/
A
GARRISON HOUSEESA - HISTORICAL BOUNDARY
MAINLINE PLAN
13-002
EASEMENT FOR CONSTR
EASEMENT FOR CONSTR OF SLOPES
EASEMENT FOR CONSTR OF DRIVES
CONSTRUCTION LIMITS
& MAINTENANCE OF SLOPES
C F
REQUIRED R/W LINE
PROPERTY AND EXISTING R/W LINE PL
LIMIT OF ACCESS
BEGIN LIMIT OF ACCESS............BLA
END LIMIT OF ACCESS..............ELA
REQ’D R/W & LIMIT OF ACCESS
20
SCALE IN FEET
0 40 80
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-v8i-PO.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_13-002.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
OFFICE:
8:25:03 PM
GPLN
STATE
GA
12/14/2012
SEE
DR
AWI
NG
No. 13-001
MAT
CH LI
NE 109+50
SEE
DR
AWI
NG
No. 13-003
MAT
CH LI
NE 114+50
SEE DRAWING No. 14-004
MATCH LINE 41+50
SEE DRAWING No.
14-003
MATCH LINE 3+0
0
FOR DESIGN-BUILD
COSTING PLANS
COUNTY: FULTON
PROJECT: PI 0010925
INNOVATIVE DELIVERY
PI 0010925
110+00
111+00
112+00
113+00
114+00
WALL #3
WALL #4
41+00
3+00
RIVERSIDE DRIVE
RA
MP C
CO
NSTR
UCTI
ON CL
CO
NSTR
UCTI
ON CL
CONSTRUCTION CL
PT 3+9
6.81
PI 3+3
9.10
R=300’
R=800’
R=60’
R=100’
R=100’
R=150’
R=230’
R=75’
R=600’
R=100’
24.00’
+91.17
12’
12’
18’
18’
STA 112+25.00
18.5’
18’
18’
17’
E= 2.80
R= 600.00
L= 115.79
T= 58.07
E= 2223659.38
N= 1424775.36
PI Sta= 3+39.10
Curve# 3
CUR
VE #3
20.72’
18.94’
25.28’
16.77’
16.68’
14.23’
250’R
98’R
101’R
801’R
98’R
318’R
CUR
VE #3
WALL
SOUND
REPLACE
STA 40+00.00 RAMP ’D’
STA 112+41.94 RIVERSIDE DRIVE=
INTERSECTION
STA 4+67.17 RAMP ’C’
STA 112+67.51 RIVERSIDE DRIVE=
INTERSECTION
RA
MP
D
GDOT DETAIL RA-1LANDSCAPING AS PER
DO NOT DISTURB SIGN
STA 111+12.64
END EX. BRIDGE
ISLAND TYP.6" RAISED CONC.
24"RCP
15"RCP
24"RCP
15"
RC
P
15"RCP
INV=1021.57’
TOP=1024.77’
CB
INV=1020.52’
TOP=1024.92’
CB
IN
V=1016.71
TO
P=1020.41’
CB
15"CMP
INV=1003.07’
18"
RCP
INV=1001.88’
IN
V=
10
06.
79
TO
P=
101
6.
39’
DI
30"RCP
15"
RC
P
IN
V=1017.05’
BU
RI
ED
JB
METAL PLATE
NOT ACCESSABLE
TOP=991.45
DI
ASPHALT PAVING
DRIV
EW
AY
AS
PH
AL
T
PL
AN
S
TA
KE
N
FR
OM
DI
18
DP
C
F/L 1001.88’
15 DPMF/L
’1003
.07’
L
ocatio
n
CD
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
15
DPC
F/L 1017.05’
C
ontr
ol
Re-
Sh
ot
#
L
ocati
on
CD
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
L
ocati
on
CD
#
C
ontr
ol
Re-
Shot
#
L
ocation
CD
#
C
ontr
ol
Re-
Shot
#
C
ontr
ol
Re-
Sh
ot
#
L
ocatio
n
CD
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
L
ocatio
n
CD
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
C
ontr
ol
Re-
Sh
ot
#
DCB
C
ontr
ol
Re-
Shot
#
C
ontr
ol
Re-
Shot
#
L
ocation
CD
#
C
ontr
ol
Re-
Shot
#
-105.00
STA +99.42
-76.35
STA +83.74
-76.35
STA +02.26
88.06
STA +22.74
-115.76
STA +94.18
-105.00
STA +07.64
-161.85
STA +75.37
46.04
STA +20.49
-105.00
STA +50.00
SANDRA K. CAMPBELL
N/F
RICHARD D. KLINE
N/F
REQ’D R/W
5
7
KC5001
KC7001
KC7002
KC7003
KC7004
LL166
LL133APPROX LOCATION L.L.L.
EXIST R/W
SEE SHEET
SEE SHEET
$RW03$,$RW06$,$RW08$
$RW03$,$RW07$,$RW08$
KC5002
74
43
38
12725E
XIST R/
W
& L/
A
EXIST R/
W
& L/
A
MAINLINE PLAN
13-003
EASEMENT FOR CONSTR
EASEMENT FOR CONSTR OF SLOPES
EASEMENT FOR CONSTR OF DRIVES
CONSTRUCTION LIMITS
& MAINTENANCE OF SLOPES
C F
REQUIRED R/W LINE
PROPERTY AND EXISTING R/W LINE PL
LIMIT OF ACCESS
BEGIN LIMIT OF ACCESS............BLA
END LIMIT OF ACCESS..............ELA
REQ’D R/W & LIMIT OF ACCESS
20
SCALE IN FEET
0 40 80
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-v8i-PO.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_13-003.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
OFFICE:
8:31:37 PM
GPLN
STATE
GA
12/14/2012
SEE
DR
AWI
NG
No. 13-002
MAT
CH LI
NE 104+50
FOR DESIGN-BUILD
COSTING PLANS
COUNTY: FULTON
PROJECT: PI 0010925
PI 0010925
INNOVATIVE DELIVERY
LAND LOT LINE
APPROX. LOCATION
36"RCP
INV=974.83’
TOP=978.16’
DI
36"RCP
18"
RC
P
18"
RCP
IN
V=965.42
IN
V=959.61
60"
RC
PINV=977.39’
ASPHALT PAVING
ASPHALT PAVING
ASPHALT PAVING
DRIVEWAY
ASPHALT
AS
PH
AL
T
PA
VIN
G
60
DP
C
F/L 959.61’
ATT
RN
AME
DP
M
F/L ’965.42’
60
DP
C
F/L 965.48’
36
DP
C
F/L 977.39’
Contr
ol
Re-
Shot
#
Location
CD
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Location
CD
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Location
CD
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Location
CD
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Locati
on
CD
#
Control
Re-
Shot
#
Co
ntrol
Re-
Shot
#
Control
Re-
Shot
#
Location
CD
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Control
Re-
Shot
#
Location
CD
#
-105.00
STA +50.00
-55.00
STA +00.00
-55.00
STA +23.70
-55.00
STA +00.00
-34.55
STA +20.00
115+00
116+00
117+00
118+00
119+00
120+00
DEMETRA ABDALLA
MICHAEL J ABDALLA &
N/F
RAJ BHOLE
N/F
PHILOMINA FASAE
KYODE FASAE &
N/F
CONNIE LYNN TAHAMTAN
AMIR A. TAHAMTAN &
N/F
6
1120
5 112
04
11
282
TE
AD1
ST
TE
AD1
TP
BL5
ST
10
14.34
1014.27
1016.57
7
KC5002
KC5003
KC5004
KC6001
KC6002
SANDRA K. CAMPBELL
N/F
LL166
LL133APPROX LOCATION L.L.L.
RIVERSIDE DRIVE
STA 116+20.00
END R/W ACQUISITION
EXIST R/W
EXIST R/W
EXIST
R/
W
EXIST
R/
W
EXIST R/W
EXIST R/W
EXIST R/W
PL
PL
PL
SEE SHEET
SEE SHEET
5
RICHARD D. KLINE
N/F
SEE SHEET
$RW02$,$RW06$,$RW08$
$RW08$
$RW02$,$RW07$,$RW08$
75
69
65
44
42
13203
68
CONSTRUCTION CL
12.00’
+89.27 12’+/-
12’+/-
24.00’
+23.38
RIVERSIDE DRIVE
STA 116+13.13
END CONSTRUCTION
R=35’
81+00
12’+/-
+48.04
12’+/-
+48.04
HE
AR
DS CREE
K
HE
AR
DS CREE
K
ESA - 25’ STREAM BUFFER
ESA - 25’ STREAM BUFFER
HEARDS CREEKUNNAMED TRIBUTARY TO
CROSSROAD PLAN
14-001
EASEMENT FOR CONSTR
EASEMENT FOR CONSTR OF SLOPES
EASEMENT FOR CONSTR OF DRIVES
CONSTRUCTION LIMITS
& MAINTENANCE OF SLOPES
C F
REQUIRED R/W LINE
PROPERTY AND EXISTING R/W LINE PL
LIMIT OF ACCESS
BEGIN LIMIT OF ACCESS............BLA
END LIMIT OF ACCESS..............ELA
REQ’D R/W & LIMIT OF ACCESS
20
SCALE IN FEET
0 40 80
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-v8i-PO.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_14-001.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
Design File and Plot Substitution information
OFFICE:
8:35:57 PM
GPLN
STATE
GA
12/14/2012
SEE
DR
AWI
NG
No. 13-001
MAT
CH LI
NE 29+00
FOR DESIGN-BUILD
COSTING PLANS
COUNTY: FULTON
PROJECT: PI 0010925
PI 0010925
INNOVATIVE DELIVERY
INV=1015.21’TOP=1018.41’DI
18"RCP
INV=1005.37’
18"RCP
18"RCP
INV=1005.20’TOP=1008.50’DI
INV=1004.
98
RC
P15"
2’ WIDE PAVED DITCH
2’ WIDE PAVED DITCH
PAVED DITCH
PAVED DITCH
15 DPC
F/L 1004.98’
Location
CD
#
Control R
e-Shot
# Cont
rol Re-Sho
t
# Cont
rol Re-Sho
t
# Cont
rol Re-Sho
t
# Cont
rol Re-Sho
t
# Loca
tion CD
# Cont
rol Re-Sho
t
# Cont
rol Re-Sho
t
# Cont
rol Re-Sho
t
#
DDI
TOP 1018.41’
INV. IN 1015.21’
INV. IN 1018.41-IN2’INV. IN 1018.41-IN3’INV. IN 1018.41-IN4’INV. OUT 1018.41-OUT’
Control R
e-Shot
# Loca
tion CD
# Cont
rol Re-Sho
t
# Cont
rol Re-Sho
t
# Cont
rol Re-Sho
t
#
Control R
e-Shot
# Loca
tion CD
# Cont
rol Re-Sho
t
#
Location
CD
# Cont
rol Re-Sho
t
# Cont
rol Re-Sho
t
#
3
E. FRANK TIMMERMAN
N/FJANE L.NATIONS
L. DEAN NATIONS &
N/F
2
PL
PL
PL
SEE SHEET
$RW01$,$RW08$ SEE SHEET
$RW01$,$RW08$
1617 20
EXIST R/W & L/A
24+00
25+00
26+00
27+00
28+00
29+00
CONSTRUCTION CL
8.00’+04.72
16.00’
+59.81
V-GUTTER
TIE TO EXIST.
WALL
SOUND
REPLACE
RAMP ’A’
BEGIN C&G LT
STA 26+39.33
LIMIT OF CONSTRUCTION
BUFFERESA - 25’ STREAM
HEARDS CREEKUNNAMED TRIBUTARY TO
CROSSROAD PLAN
14-002
EASEMENT FOR CONSTR
EASEMENT FOR CONSTR OF SLOPES
EASEMENT FOR CONSTR OF DRIVES
CONSTRUCTION LIMITS
& MAINTENANCE OF SLOPES
C F
REQUIRED R/W LINE
PROPERTY AND EXISTING R/W LINE PL
LIMIT OF ACCESS
BEGIN LIMIT OF ACCESS............BLA
END LIMIT OF ACCESS..............ELA
REQ’D R/W & LIMIT OF ACCESS
20
SCALE IN FEET
0 40 80
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-v8i-PO.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_14-002.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
Design File and Plot Substitution information
OFFICE:
8:37:06 PM
GPLN
STATE
GA
12/14/2012
SEE
DR
AWI
NG
No. 13-001
MATC
H LI
NE 61+50
FOR DESIGN-BUILD
COSTING PLANS
COUNTY: FULTON
PROJECT: PI 0010925
INNOVATIVE DELIVERY
24"
RC
P
INV=1012.63’
TOP=1015.63’
INLET
15"
RC
P
INV=1024.41’
36"
RC
P
INV=1024.66’
15"RCP
IVNERT=1026.21’
INV=1024.74’
TOP=1028.49’
DI
FULL OF DIRT
TOP=1040.52’
DI
15"RCP
INV=1027.80’
TOP=1032.30’
DI
INV=1025.75’
FROM PLANS
BURIED
JB
PARKING
ASPHALT PAVED
CO
NC
RE
TE
FL
UM
E
PAVED DITCH
END NOT
FOUND
FROM PLANS
15"
CMP
36 DPCF/L 1024.41’
15 DPC
F/L 10
24.66’
15 DPC
F/L 1025.75’
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Location CD #
Control Re-Shot
#
Control Re-Shot
#
Location CD #
Location CD #
Location CD #
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Control Re-Shot
#
Location CD #
4
UNITED PRESBYTERIAN CHURCH, U.S.A.
THE PRESBYTERY OF ST. ANDREW
N/F
SEE SHEET
$RW01$,$RW08$
EXIST R/W & L/A
EXIST R/W & L/A
CONSTRUCTION CL
P.I. 62+24.54
P.T. 63+55.47
62+00
63+00
64+00
64+29
16’+/-
RAMP ’D’
END C&G RT
STA 45+33.68
LIMIT OF CONSTRUCTION
RAMP ’B’
END C&G
STA 63+55.47
LIMIT OF CONSTRCUTION
E= 11.04
R= 800.00
L= 264.29
T= 133.36
E= 2223970.12
N= 1424348.05
PI Sta= 62+24.54
Curve# 2
CURVE #2
CROSSROAD PLAN
14-003
EASEMENT FOR CONSTR
EASEMENT FOR CONSTR OF SLOPES
EASEMENT FOR CONSTR OF DRIVES
CONSTRUCTION LIMITS
& MAINTENANCE OF SLOPES
C F
REQUIRED R/W LINE
PROPERTY AND EXISTING R/W LINE PL
LIMIT OF ACCESS
BEGIN LIMIT OF ACCESS............BLA
END LIMIT OF ACCESS..............ELA
REQ’D R/W & LIMIT OF ACCESS
20
SCALE IN FEET
0 40 80
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-v8i-PO.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_14-003.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
Design File and Plot Substitution information
OFFICE:
8:38:42 PM
GPLN
STATE
GA
12/14/2012
SEE
DR
AWI
NG
No. 13-002
MAT
CH LI
NE 3+00
FOR DESIGN-BUILD
COSTING PLANS
COUNTY: FULTON
PROJECT: PI 0010925
PI 0010925
INNOVATIVE DELIVERY
18"RCP
15"RCP
15"RCP15"RCP
INV=1001.70’TOP=1005.20’DI
INV=996.12’
TOP=999.68’
CB
FULL OF DIRT
IN END OF FLUME
DI
15"
RCP
FROM PLANS
BURIED JB
POSSIBLE JB
15"RCP
PAVED DITCH
PAVED DITCH
Control Re-Shot #
Control Re-Shot #
Control Re-Shot #
Control Re-Shot #
Control Re-Shot #
Control Re-Shot #
Location CD #
Control Re-Shot #
Location CD #
15 DPCF/L 1001.70’
Location CD #
Control Re-Shot #
Control Re-Shot #
Control Re-Shot #
DDITOP 1005.20’INV. IN 1001.70’INV. IN 1005.20-IN2’
INV. IN 1005.20-IN3’
INV. IN 1005.20-IN4’
INV. OUT 1005.20-OUT’
Control Re-Shot #
Control Re-Shot #
Location CD #
Control Re-Shot #
Location CD #
Control Re-Shot #
Control Re-Shot #
Control Re-Shot #
Location CD #
Control Re-Shot #
Control Re-Shot #
RICHARD D. KLINE
N/F
5
PL
SEE SHEET
$RW02$,$RW03$,$RW08$
39 EXIST R/W & L/A
0+00
1+00
2+00
3+00
CONSTRUCTION CL
0+00
PI 0+00.00
PC 2+81.03
16’+/-
CURVE #3
RAMP’C’
STA 2+81.03
LIMIT OF CONSTRUCTION
14-004
CROSSROAD PLANEASEMENT FOR CONSTR
EASEMENT FOR CONSTR OF SLOPES
EASEMENT FOR CONSTR OF DRIVES
CONSTRUCTION LIMITS
& MAINTENANCE OF SLOPES
C F
REQUIRED R/W LINE
PROPERTY AND EXISTING R/W LINE PL
LIMIT OF ACCESS
BEGIN LIMIT OF ACCESS............BLA
END LIMIT OF ACCESS..............ELA
REQ’D R/W & LIMIT OF ACCESS
20
SCALE IN FEET
0 40 80
REVISION DATES
DRAWING No.
DEPARTMENT OF TRANSPORTATIONSTATE OF GEORGIA
5/15/2014
USER:rgraves
GPLOT-V8
gplotborder-v8i-PO.tbl
G:\TRA\GDOT I-285\Riverside\RDY\DGN\0010925_14-004.dgn SHEET NO.PROJECT NUMBER
TOTAL SHEETS
Design File and Plot Substitution information
OFFICE:
8:39:54 PM
GPLN
STATE
GA
12/14/2012
SEE
DR
AWI
NG
No. 13-002
MAT
CH LI
NE 41+50
FOR DESIGN-BUILD
COSTING PLANS
COUNTY: FULTON
PROJECT: PI 0010925
PI 0010925
INNOVATIVE DELIVERY
INV=1006.
79TOP=10
16.39’
DI
INV=1024.
74’TOP=1028.
49’DI
INV=1009.51
36"
RC
P
INV=1018.88’
TOP=1021.98’
DI
15"RCP
INV=1019.71
INV=1033.89’
TOP=1037.69’
DI
15"
CMP
15"
DP
M
F/L ’1019.71’
Locat
ion CD
#
Contr
ol Re-
Shot
#
Contr
ol Re-
Shot
#
Locat
ion CD
#
Locat
ion CD
#
Contr
ol Re-
Shot
#
Contr
ol Re-
Shot
#
Contr
ol Re-
Shot
#
Contr
ol Re-
Shot
#
Locat
ion CD
#
Contr
ol Re-
Shot
#
Locat
ion CD
#
Contr
ol Re-
Shot
#
Contr
ol Re-
Shot
#
SANDRA K. CAMPBELL
N/F
7 PL
SEE SHEET
$RW02$,$RW03$,$RW08$
73
EXIST R/W & L/A
42+00
43+00
44+00
45+00
46+00
45+00
42+00
43+00
44+00
45+00
46+00
PI 46+00.54
CONSTRUCTION CL
REPLACE SOUND WALL OARNGE BARRIER FENCE
8.00’
+33.69
16.00’
+65.53
RAMP ’D’
END C&G RT
STA 45+33.68
LIMIT OF CONSTRUCTION
INTER
MITTE
NT STRE
AM #1
ESA - 25’ STREAM BUFFER