project implemetation plan meghalaya community led ... · gimgreen india mission, one of the eight...

59
PROJECT IMPLEMETATION PLAN Meghalaya Community Led Landscape Management Project (CLLMP) With assistance from the World Bank Planning Department Government of Meghalaya The World Bank New Delhi October 2017

Upload: others

Post on 09-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

PROJECT IMPLEMETATION PLAN

Meghalaya Community Led Landscape Management Project

(CLLMP)

With assistance from the World Bank

Planning Department

Government of Meghalaya

The World Bank

New Delhi

October 2017hp

Hewlett-Packard

[Pick the date]

Page 2: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

TABLE OF CONTENTS

CONTACT DETAILS ......................................................................................................................... ii ABBREVIATIONS AND ACRONYMS ........................................................................................... iii 1. STRATEGIC CONTEXT FOR THE PROJECT......................................................................... 1

1.1. Country Economic Context ...................................................................................................... 1 1.2. Meghalaya Economic Context ................................................................................................. 2 1.3. Natural Resource Context ........................................................................................................ 2

1.4. Climate Change Vulnerability Context .................................................................................... 3 1.5. Institutional Context - Administrative Set-up and Traditional Institutions.............................. 6 1.6. Community Contest - Ownership and Management of Natural Resources .............................. 8

1.6.1. Land ................................................................................................................................... 8

1.6.2 Forests ................................................................................................................................. 8 1.6.3 Water ................................................................................................................................... 9

1.7. Developmental Context – Synergy of CLLMP with other programmes ................................ 10 2. Project Framework ..................................................................................................................... 14

2.1. Proposed Developmental Goal of the CLLM-Project ............................................................ 14 2.2. Higher level objectives ........................................................................................................... 14 2.3. Project Period ......................................................................................................................... 14

2.4. Project Area ............................................................................................................................ 14

2.5. Target Village Selection Criteria and Process (Milestones) under the Project ...................... 17 2.6. Project benefits. ...................................................................................................................... 18

3. Project Components ................................................................................................................... 19

3.1 Project cycle ........................................................................................................................... 19 3.2 Project Components ............................................................................................................... 20

3.2.1. Component 1: Strengthening Knowledge and Capacity for NRM ................................. 20 3.2.1.1. Component 1A: Promotion of traditional knowledge, grass-root innovations and

communication .................................................................................................................................... 21

3.2.1.2 Component 1B: Training and Capacity Building .................................................................... 21

3.2.1.3 Component 1C: Promotion of CLLMP Principles through Catalytic Fund ............................ 22

3.2.1.4 Component 1D: Research and Development ........................................................................... 22

3.2.1.5 Component 1E: Monitoring learning and reporting ................................................................ 22

3.2.1.6 Costing of Component 1 .......................................................................................................... 23

3.2.2 Component2: Community-led Landscape Planning and Implementation ...................... 26 3.2.2.1 Sub-Component 2A: Preparation of CNRM Plans .................................................................. 26

3.2.2.2 Sub Component 2B(i) CNRM Plan Implementation ............................................................... 27

3.2.2.3 Sub Component 2B(ii) CNRM Implementation Support ........................................................ 28

3.2.2.4 Costing of Component 2 ......................................................................................................... 30

3.2.2.5 Steps in CNRM plan approval and release of funds for investments ..................................... 32

3.2.3 Component 3: Project Management and Governance – Institutional Structure ................ 33 3.2.3.1 State Level ............................................................................................................................... 33

3.2.3.2 District & Block Level ............................................................................................................ 34

3.2.3.3 Village level ............................................................................................................................. 35

3.2.3.4 Costing of Component 3 .......................................................................................................... 37

Page 3: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

i

3.2.4 Summary of CLLM – Project Costing (INR) ................................................................... 38

3.2.5 Summary of CLLM-Project Costing (USD) ..................................................................... 39 4. Financial and Procurement Management ................................................................................... 40

4.1 Financial Management ........................................................................................................... 40 4.1.1 Main assumptions ............................................................................................................ 40 4.1.2 Project Component Financing and Financial Management ............................................. 40

4.1.3 Financial Management ..................................................................................................... 40 4.2 Procurement Management...................................................................................................... 46 4.2 Financial and Technical Safeguards and Reporting ................................................................. 50 5.1 Economic analysis .................................................................................................................. 51

FIGURES

Figure 1 Climate change glimpses ....................................................................................................... 4 Figure 2 Administrative Map of Meghalaya ........................................................................................ 7

Figure 3 Synergy of CLLMP with IBDLP......................................................................................... 12 Figure 4 Area in high priority zone .................................................................................................... 15

Figure 5 Area in very high priority zone............................................................................................ 16 Figure 6 Project Components ............................................................................................................. 20

Figure 7 Organogram State Project Management Unit ...................................................................... 34 Figure 8 Organogram of District Project Management Unit ............................................................. 35

Figure 9 Organogram of Block Project Management Unit ................................................................ 35

Page 4: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

ii

CONTACT DETAILS

Mr. S M Sahai, IFS

Project Director - CLLMP (Additional Principal Chief Conservator of Forests)

Meghalaya Basin Development Authority

Government of Meghalaya

Upper Nongrim Hills, Cooperative Society Complex

Behind Bethany Hospital

Shillong

Email: [email protected]

Mobile: 9436999107

Page 5: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

iii

ABBREVIATIONS AND ACRONYMS

ACA Additional Central Assistance

ADC Autonomous District Council

BADP Boarder Area Development Programme

BUS Business as Usual Scenario

BRGF Backward Grant Fund

BPL Below Poverty Line

BSA Benefit Sharing Agreements

CAMPA Compensatory Afforestation Fund Management and Planning Authority

CAT Catchment Area Treatment

CBO Community Based Organisation

CC Climate Change

CCA Climate Change Adaptation

CDD Community Driven Development

CEM Chief Executive Member

CLLMP Community Led Land Scape Management Project/ Programme

CSS Centrally Sponsored Scheme

CNRMP Community Natural Resource Management Plan

C&RD Community and Rural Development Department, Govt. of Meghalaya

DBDU District Basin Development Units

EKH East Khasi Hills

EGH East Garo Hills

EJH East Jaintia Hills District

FD Forest Department

GHADC Garo Hills Autonomous District Council

GIM Green India Mission, one of the eight missions of the NAPCC

GIS Geographic Information System

GoM Government of Meghalaya

GoI Government of India

Govt. Government

IBDLP Integrated Basin Development and Livelihood Programme

IGA Income Generating Activities

IVCS Integrated Village Cooperative Society

JFM Joint Forest Management

JHADC Jaintia Hills Autonomous District Council

JWMC Joint Watershed Management Committee

KHADC Khasi Hills Autonomous District Council

MBDA Meghalaya Basin Development Authority

MBMA Meghalaya Basin Management Agency

MDC Members of District Councils

MGNREGS Mahatma Gandhi National Rural Employment Guarantee Scheme

MIE Meghalaya Institute of Entrepreneurship

MIG Meghalaya Institute of Governance

MINR Meghalaya Institute of Natural Resources

MoDoNER Ministry of Development of North Eastern Region

MoEFCC Ministry of Environment Forest and Climate Change

MoRD Ministry of Rural Development, Government of India

MSRLS Meghalaya State Rural Livelihood Society

Page 6: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

iv

NABARD National Bank for Agriculture and Rural Development

NAP National Afforestation Programme

NAPCC National Action Plan on Climate Change

NEHU North Eastern Hill University

NERCORMP The North Eastern Region Community Resource Management Project

NGO Non-governmental Organisation

NMSHE National Mission on Sustaining Himalayan Eco-systems

NREGA National Rural Employment Guarantee Act

NRLM National Rural Livelihood Mission

NRM Natural Resource Management

NTFP Non Timber Forest Products

PD Project Director

PDO Project Development Objective

PES Payment for Environmental Services

PIA Project Implementing Agency

PMU Project Management Unit

PRA Participatory Rural Appraisal

RB Ri-Bhoi District

RFR Recognition of Forest Rights

RKVY Rastriya KrishiVikasYojana

Rs. Indian Rupees

SAPCC State Action Plan on Climate Change of HP

SHG Self Help Group

SGH South Garo Hills District

SPMU State Project Management Unit

SMR Small Multipurpose Reservoirs

SWGH South West Garo Hills District

SWKH South West Khasi Hills

S&WCD Department of Soil and Water Conservation

UPNRM Umbrella Programme for Natural Resource Management

WGH West Garo Hills District

WJH West Jaintia Hills District

WKH West Khasi Hills District

Page 7: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

1 | P a g e

1. STRATEGIC CONTEXT FOR THE PROJECT

1.1.Country Economic Context

India (macro-economic condition): India‟s economic growth this fiscal (2016-17) is expected

to be 6.5%1 and the projected economic growth for 2017-18 is between 6.75% and 7.5% .

International Monetary Fund (IMF) has projected rate of 6.6% in 2016-17 and 7.2% in 2017-

18. The farm sector is expected to grow at 4.1% this fiscal, up from 1.2% last year and

Industrial Sector growth rate is expected to be 5.2% this fiscal, from 7.4% of last fiscal. India

introduced structural reform of uniform system of Goods and Services Taxes from July 2017

and it demonetized higher denomination note in November 2016 which is expected to affect

growth rate by 0.25-0.5%, but will have long-term benefits. As of January 15, 2017,

aggregate sowing of the two major Rabi crops; Wheat and Pulses exceeded last year‟s

planting by 7.1% and 10.7%, respectively. GDP growth expected to be in the 6¾ to 7½%

range in FY2018. India is expected to remain one of the fastest growing economies in the

world.

The Central government is committed to achieve its fiscal deficit target of 3.5% of GDP

2017. The current account deficit declined to about 0.3% of GDP in the first half of FY2017.

Foreign exchange reserves are at comfortable levels, having risen from around US$350

billion at end-January 2016 to US$360 billion at end-December 2016. The trade deficit

declined by 23.5% in April-December 2016 compared to corresponding period in previous

year. Government debt to GDP in 2016 was 68.5%, down from 69.1% in 2015.

India‟s growth continues to be impressive but sustainability depends on judicious

management of the country‟s natural resources. The country still faces development

challenges with the largest number of poor in the world. Primary sector (agriculture, fishing

and forestry) contributes only 13.9 percent to the GDP but for a large share of population it is

the principal source of livelihood. About 29 percent of The most significant process of

degradation is water erosion (loss of soil cover mainly due to rainfall and surface runoff

water) at 10.98%, followed by vegetation degradation (mainly as deforestation) at 8.91% and

wind erosion (denotes the spread of sand by various processes) at 5.55%.The most significant

process of degradation is water erosion (loss of soil cover mainly due to rainfall and surface

runoff water) at 10.98%, followed by vegetation degradation (mainly as deforestation) at

8.91% and wind erosion (denotes the spread of sand by various processes) at 5.55%.nearly

India‟s land is undergoing degradation mainly due to soil erosion and loss of vegetation and

topsoil. Addressing such land degradation is essential to raise agricultural productivity and

incomes. Groundwater, which is the source for nearly 80 percent of the water for irrigation

and drinking in rural areas, is overexploited, and is already unsustainable in about 30 percent

of the blocks.

1Economic survey of the Government of India

Page 8: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

2 | P a g e

1.2.Meghalaya Economic Context

Meghalaya is located in the Northeast of India. The state shares its border on the north and

east with Assam and on the south and west with Bangladesh. Between 2004-05 and 2015-16,

Gross State Domestic Product (GSDP) expanded at a compound annual growth rate (CAGR)

of 9.74 per cent to US$ 4.17 billion whereas the Net State Domestic Product (NSDP)

expanded at a CAGR of 9.17 per cent to US$ 3.41 billion. At a CAGR of 16.13 per cent, the

secondary sector was the fastest growing among the three sectors during 2004-05 to 2015-16.

Growth has been driven by construction, electricity, gas & water supply. Location and

economic parameter are given in Annex 2.

1.3.Natural Resource Context

Agriculture: Agriculture is the main source of income of the people of Meghalaya that

employs 70% of the population in the State and contributes 22% to the State GDP.US$ 54.66

million was proposed for the improvement of the agriculture sector of the state under the 12th

Five Year Plan (2012-2017). Net sown area in the State is 218892 ha. Shifting cultivation

is a prominent traditional agricultural land use associated with the social framework of the

tribal communities in Meghalaya specially is Garo Hills. Agriculture is heavily dependent on

monsoon. Much of the area available for crop is dedicated to paddy which is dependent on

rainfall. Other food grain crops grown in the State are wheat, maize, other cereals, pulses

(cowpea, pea, lentil, arhar, black gram, rajma etc.), oilseeds (castor, sesame, rapeseed,

soyabean, sunflower. Garo hills are the food basket of the State.

Horticulture: The geo-climatic conditions of Meghalaya offer an excellent scope for

growing of different types of horticultural crops including fruits, vegetables, spices,

plantation crops, medicinal and aromatic plants of high economic values. Important fruit

crops of Meghalaya are Pineapple, Citrus, and Banana. Meghalaya is also known for its high

quality vegetables as the agro-climatic conditions favour cultivation of vegetables though out

the year. Many varieties of spices are grown in Meghalaya viz., turmeric, ginger etc.

World‟s best quality turmeric is grown in Meghalaya. Other spices are black pepper, bay

leaf. All above mentioned economic activities are dependent on natural resources. However

the natural resources are under extreme state of degradation which underlines the importance

of landscape approach with community participation for sustainable management of these

resources.

Forests: It is often quoted that the state - with about 77 per cent of its total geographical area

under forest cover - is a forest-surplus region, but the

quality of the forest has deteriorated, and dense forests

with canopy closure of 40 per cent or more have been

degraded into open forests or scrublands. With the change

climatic conditions native broadleaved species are

disappearing and various exotic invasive (pines) species,

that do not support much of biodiversity, are encroaching

on the patches so created. Substantial forest area (88.15%)

is under the unclassed category, and is owned by private

Page 9: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

3 | P a g e

individuals, clans, village councils, district councils and other traditional community

institutions.

Forest fires: A large area of forests and grasslands in the state is destroyed by fire every year.

Forest fire create heavy smog that is harmful to human and animal life. Forest fires most

certainly destroy the understory vegetation and in many cases also standing full-size trees.

Trees damaged from forest fires are more susceptible to bark beetle attacks, especially in

adverse weather conditions. The destruction of vegetative cover leads to surface runoff and

soil erosion especially in the steeper topography. Run off also carries suspended soil

particles, dissolved inorganic nutrients, and other materials into adjacent streams and lakes

adversely affecting water quality and destroying fish habitats.

Resource degradation: Heavy biotic pressure, shifting cultivation, mining and other

anthropogenic activities have lead to fragmentation, destruction and degradation of forests

and irreversible changes in landscapes. There forest lands are deficient in nutrients and have

poor regeneration carrying capacity. Many species have become extinct due to fragmentation

and degradation of habitats. Deforestation also resulted into loss of soil cover and siltation of

fish habitats, decrease in primary productivity of natural and agro-ecosystems, loss of habitats

and disappearance of native species, invasion of exotic weeds etc. Deforestation and the

resultant loss of soil especially in the hill areas are leading to increased siltation of rivers and

streams. The deep pools that are the favoured habitats of many species are rapidly becoming

shallow and choked with silt, leading to a decline in habitat. At the same time, swamps,

marshes, and other wetlands are increasingly being reclaimed for urban and agricultural

expansion.

Loss of bio-diversity: Forests have faced extreme loss of biodiversity in last decade. Many

of the endemic species have become extinct or are endangered. Major causes of loss of bio-

diversity are deforestation, habitat destruction, fragmentation of natural forests into isolated

patches due to mining, shifting cultivation, encroachment, forest fires, illegal extraction of

forest production and other anthropogenic pressures and land use changes. The depletion rate

of forest cover accelerated since 1985. This has reduced species richness, reduced population

size of endemic species and increased number of threatened species

1.4.Climate Change Vulnerability Context

Climate change vulnerability: Climate of Meghalaya is dependent on the south-west

monsoons2 which bring torrential rains and flash floods in many part of the State specially in

the low altitude areas bordering Assam and Bangladesh which cause heavy damage to the

crops. In the case of Meghalaya, the 5 districts are moderate to highly vulnerable. These

districts include: West Khasi Hills, South Garo Hills, Ri- Bhoi, East Garo Hills and West

Garo Hills. The moderate to low vulnerability districts are East Khasi Hills and Jaintia Hills.

None of the districts scores “very low” on the current overall vulnerability scale.

2http://megplanning.gov.in/MSDR/agriculture_allied_sectors.pdf

Page 10: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

4 | P a g e

Meghalaya with spots of wettest place on the earth faces extreme scarcity of water in

winter season. Most parts of the State face 5-10% probability of moderate and severe

drought intensity and floods. According to a study done by Indian Institute of Science most

of the districts in Meghalaya are expected to receive much less monsoon precipitation during

the short term period but the water yield in short term is expected to increase by 10-40%.

This may be attributed to the increase in intensity of rainfall events and the reduction in the

number of these rain events. Thus in the short term water yield may increase but the water

scarcity may also increase due to increased rainfall intensity and runoff. Increase in evapo-

transpiration under both short and long term scenarios is projected for majority of the

districts, even up to about 50%.

Impact of climate change: Extreme precipitation events (heavy rainstorm, cloud burst)

cause widespread landslides and soil erosion. The response of hydrologic systems, erosion

processes and sedimentation in the river basins could alter significantly due to climate

change. Occurrenceofextremelyintensecloudburstsofunprecedentedintensityinthe western

Meghalaya hills in 2004 produced devastating flash floods causing hundreds of deaths.

Floods in the northern part of West Garo Hills adjoining Assam cause tremendous loss to

crops, infrastructure, economy, livelihoods and lives of the people. About 815,000 ha in

Meghalaya gets affected due to flooding, which might increase in the next few decades in-

terms of intensity, frequency, erosion potential, environmental damage, social disruption and

economic costs. Some of the glimpses of impact of climate change are given below:

Figure 1 Climate change glimpses

Page 11: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

5 | P a g e

Impact of CC on springs: 79% of population living in villages depends on springs as main

source of water for household and irrigation purposes. Climate change has resulted into

reduction in water discharge or drying of 54% of 6000+ springs in Meghalaya. Impaired

springs have caused widespread water stress in the rural landscape, adversely affecting

agriculture, livestock and other allied livelihood activities of the people and causing hardship

and drudgery. Despite heavy rainfall, many areas are water-stressed due to increase in

demand-supply gap leading to a surge in the use of ground water. Further, ground water data

shows that the depletion rate between pre and post

monsoon period is about 40 to 80% depending on the

landscape. Besides the combined effect of

anthropogenic activities and climate change reduced

the “sponge action” of the land and consequently

limited percolation of the rainwater. Thus hydrological

imbalance is experienced in some of the watersheds,

besides the issues of soil erosion, siltation, soil and

water pollution. It has been estimated that less than10-

15%

oftherainwaterisabletopercolatedownthroughdeforested

slopestorechargethesprings while rest flows down causing floods and landslides.

Impact of CC on agriculture/ horticulture and animal husbandry: The State is deficit in

food production. Rain fed agriculture is highly vulnerable to climate variability and changes

as frequent drought and flood conditions adversely affecting livelihoods, water supply and

food production. The sector is constrained by high rainfall variability, weather shift and

projection of water stress during the cropping season resulting in decline of grain yield. Low

net ground water availability, traditional subsistence based agriculture practices, shifting

(jhum) cultivations, lack of irrigational facility along with large number of small and

marginal land holding makes the agriculture of Meghalaya vulnerable to climate change.

Animal husbandry sector also faces scarcity of feed, fodder and water for animals

especially during draughts. Climate change has led to problems in feeding and reproductive

management of animals and higher incidence of parasitic infections in animals is reported.

There is steep decline in grasslands due to water stress which has resulted into increased

biotic pressure in forest areas. Non availability of sufficient nutrition for cattle leads to

malnutrition and vitamin deficiency related diseases in cattle.

Addressing above concerns though the project: The project aims at reversing this rate of

deforestation and loss of soil fertility through afforestation, natural regeneration, soil and

water conservation measures, soil productivity enhancement measures and introduction of

climate resilient agriculture. These measures are expected to improve resilience of natural

resource dependent communities and reduce their vulnerability to climate change.

Page 12: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

6 | P a g e

1.5.Institutional Context - Administrative Set-up and Traditional Institutions

The people of Meghalaya have their own traditional socio-political system where self-

governing institution follow their own customary laws, traditions and practices to govern

their land, forests and water resources without any constitutional powers. Their decisions are

respected by the people.

Non-

trad

itio

onal

inst

ituti

on

Government of Meghalaya

Legislature – MLA and council of ministers

Executive Adminstration- District administration (11 districts) and block admonistration

(45 blocks)

Khasi Hill Autonomous District

Council

Jaintia Hills Autonomous

District Council

Garo Hills

Autonomous District

Council

Tra

dit

ional

inst

ituti

ons

3 tier structure 3 tier structure 1 tier structure

The administrative arrangement of the Government consist of revenue districts, Autonomous

District Councils and traditional institutions. The State is divided into 11 revenue districts3

recently carved out of original 7 districts, 45 CD blocks and 6026 villages.

Khasi State (Hima)

Siyem

Dorbar Shnong (Village Council)

Rangbah Shnong

Dorbar Shnonmg

Rangbah Shnong

Dorbar Reid (Council of group

of villages)Bakhrawas/ Lyngdoh//

Basan/ Myntri

Jaintia State (Ka Ri ki Khadar Doloi)

Raja

Chanong (Village)

Waheh Chnong (Headman)

Chanong (Village)Rangbah Shnong

Elaka (Region)

Doloi / Basan

Village level joint assembly of elders

King Nokma

Page 13: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

7 | P a g e

Figure 2 Administrative Map of Meghalaya

The legislative, executive and judicial functions and local administration of the State are

vested in three elected Autonomous District Councils set up under the provisions of the Sixth

Schedule to the Constitution of India viz.,

The Khasi Hills Autonomous District Council:- East Khasi Hills, West Khasi

Hills, South West Khasi Hills and Ri- Bhoi Districts fall under their jurisdiction. Its

headquarters is at Shillong.

The Garo Hills Autonomous District Council:- North Garo Hills, East Garo Hills,

West Garo Hills, South West Garo Hills and South Garo Hills Districts fall under their

jurisdiction. Its headquarters is at Tura.

The Jaintia Hills Autonomous District Council:- East Jaintia Hills and West

Jaintia Hills District fall under their jurisdiction. Its headquarters is at Jowai.

The District Councils are constituted by Members representing District Council

Constituencies. These Members of District Councils (MDC) are elected by adult franchise.

The leader of the party which gets maximum representation in the District Council is

appointed by the Governor of Meghalaya as the Chief Executive Member (C.E.M.). On the

advice of the C.E.M., some members are appointed by the Governor as Executive Members

who along with the C.E.M. constitute the Executive Committee of the District Council and

exercise their executive powers. The ADCs have executive as well as judiciary powers in

relation to land disputes and social conflicts including regulation of the traditional

institutions, namely, Syiem, Hima and village headman etc.. Details discussion on ADC is

given later discourse non-traditional institutions.

Page 14: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

8 | P a g e

1.6. Community Contest - Ownership and Management of Natural Resources

1.6.1. Land

The pattern of land ownership plays an important role in land use and agricultural

development and planning as the basic concept of land ownership and tenure deals with the

interrelated network of rights, duties, privileges, immunities and capacity to have and hold

land for certain uses by individuals and groups within a society. Meghalaya is chiefly a

matrilineal society where the system of inheritance is through the female member of the

household.

Garo Hills: In the Garo Hills, land is subject to the ordinary laws of inheritance, and really

belongs to the wife of the nokma or traditional village chief or headman of a Garo village. All

the inhabitants of a village are entitled to cultivate whatever land they require, and may

cultivate wherever they choose within the traditional village boundary. Village boundaries are

recognised traditionally but without records.

Jaintia Hills: Land in the Jaintia Hills is basically classified into two types, namely, Hali

land and High land. The Hali lands are the permanently cultivated land terraced wet rice land

and were of two kinds: the difference being in the method of irrigation; one where water was

brought from the streams and the other which depended on rainfall for water. The Hali lands

comprise of the Raj land (property of king), Service land (land granted for use only for

providing services to raja), Village Puja land, Private land (can be transferred, mortgaged and

sold or otherwise, at the will of the owners) and Patta land (District Council land given on

lease to individuals). The High lands, on the other hand, are all lands not under hali or

permanent terraced cultivation. High lands were divided into two: private lands held like hali

private lands and unclaimed lands or government wastelands. The high lands, being in private

possession, can be bought, sold, mortgaged and inherited at the will of the owners.

Khasi Hills: In the Khasi Hills, landed property is classified under two main heads --– Ri

Raid (community/ clan land for use of people) and Ri Kynti (private heritable and

transferable land).

1.6.2Forests

Forest ownership: The forest in Meghalaya is managed by the State Forest Department, the

Autonomous District Councils and by the community. Less than 5% of the forest land is

controlled by the State Forest Department. The rest are under the direct or indirect control of

the Khasi Hills, Jaintia Hills and Garo Hills Autonomous District Councils‟ or the

communities. About 88 per cent of the forests are under the control of the communities.

Most of the forest lands are also under the direct control of private individuals. There are

three kinds of forests under the jurisdiction of the District Councils:

Unclassed state forests, which are under the direct control of district councils;

Clan/community forests and

Private forests.

Page 15: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

9 | P a g e

The control of the District Councils on the second and third categories of forests is limited

only to the collection of royalty on the timber exported by the owners; outside their own area

of trade. There are also types of lands which are declared as forest lands according to the

United Khasi - Jaintia Hills Autonomous District (Management and Control of Forest) Act,

1958. They include the following:

Protected forest: are forests declared protected by the District Council for the growth

of trees for the benefit of local inhabitants.

Green blocks: These forests belong to an individual family or clan or joint clans and

grow on Raid lands and are protected for aesthetic beauty and water supply of the

urban areas.

Reserve forests: are forests declared so by the executive committees of the District

Councils. In these forests human settlement and felling of trees or cutting of

branches are prohibited. Such forests are under the control of the State Forest

Department.

Unclassed forests: are mostly private forests over which local self-government has

some control. They are mostly on the hill slopes and are used by local inhabitants for

jhum cultivation. They are „unclassed‟ simply because these forests, before the

commencement of the Constitution of India, they are under the direction and control

of the government. They also include any other forests not classified in any of the

above.

Majority of the forests are both owned and managed by the people or communities; the

exception being that under the Sixth Schedule, they are under the regulatory authority of the

District Councils. Various types of community owned forests are: Sacred Forests (Law

Kyntang), Village Supply Forests (Law Shnong), Village Restricted Forest (Law Adong),

Law Raid (forests belonging to a group of villages), Private Forests - Law Ri-Sumar (private

forest on community land), and Law Ri-Kynti (private forest on private land), Cemetery

Forests (Law Lum Jingtep), Champe (managed by Nokma in Garo hills), Wa. Grin are

bamboo reserves managed by Nokma, Clan Forests (Law Kur).

Management of community owned forests: Communities with their traditional knowledge

have been managing forests in Meghalaya with their cultural and economic activities

designed to ensure their sustainable management and utilisation. Traditional institutions have

played a critical role in sustainable management of forests. However, with breaking up and

weakening of traditional institutions and recent threat of climate change this knowledge is

getting sidelined. So there is need to not just strengthen the traditional institutions but also

support traditional knowledge with scientific knowledge and management practices to create

new avenues for bio-diversity conservation, enhanced ecosystem services, forest productivity

and adaptation to climate change.

1.6.3 Water

Custodianship of water: There is a dichotomy between amount of rain and availability of

water in the state of Meghalaya. The state receives between 2,000 mm-12,000 mm of rain for

Page 16: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

10 | P a g e

6-8 months, leaving the dry months with lots of water scarcity problems. The river system of

Meghalaya comprises mainly of rivers draining to the Brahmaputra basin in the north and the

Meghna Basin in the South. There is no defined custodian of water resources in the state. It

does not have any specific law defining ownership and rights over water resources. Rights are

derived from customary beliefs and practices which in turn are supported by several

legislations. Rights over water in rivers and lakes are exercised by the community/clans and

individuals according to the customary laws and beliefs, a bit of which derives its genesis

from the land tenure system. This freedom to use land in any manner they deem suitable has

affected the lakes and rivers.

State and ADC ownership: The Constitution of India provides that the natural resources are

property of the nation and that the property rights in all rivers, streams, other natural

watercourses and canals vest with the state. However, Meghalaya is a Sixth Scheduled state

and the autonomous district councils have some power to legislate on water for agricultural

purposes. It can also make laws with respect to the use of any canal or watercourse for

agriculture4.

Community management: Under customary law in the state no specific water related

institutions exists. Rather, water related matters have always been considered part of the

associated land use interests and are generally handled through the village Dorbar.

Traditionally, the user of land had the use of water on that land. Streams, rivers, etc. under

customary law are considered to be common property. Spring and streams are the principal

source of water in south Meghalaya. Villagers pay ample regard to these water sources. They

use this water for drinking and make efforts to keep them clean and unpolluted. As such, they

do not permit their cattle at the places from which they collect drinking water; do not allow

anyone to throw garbage in its source. In villages where government supplies water are

inadequate or absent, water from these community forests play an important role in their

daily requirements. Ponds and wells are made at most water sources where in some villages

a signboard is put up having cautionary notes on how to use the water. Some community

forests act as a source for government water supply.

1.7. Developmental Context – Synergy of CLLMP with other programmes

The State has substantial experience in implementing Sate and Centrally Sponsored

Programmes. It has currently implementing IFAD funded Megha-LAMP project in 18

blocks. Details of various development programme implemented by the Government of

Meghalaya in last two decades are summarized in Annex 4.

As discussed in section 1.3 and 1.4 Meghalaya‟s population is heavily dependent on natural

resources (forest, land water) for their sustenance which are under various stages of

degradation. While most of the springs in Meghalaya have either dried or experienced

decrease in discharge, there are high incidence of forest fragmentation, loss of bio-diversity,

flash floods, reduction in productivity in agriculture, horticulture and livestock sectors

4The Indian Law Institute – Legal Issues in the management of water with special reference to the

state of Meghalaya.

Page 17: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

11 | P a g e

threatening livelihood, food and water security of the people of Meghalaya. Impending

threats of degradation of natural resources due to climate change or anthropogenic activities

clearly underlines a community based integrated approach to tackle the problems in a

sustainable manner as most of the natural resources are owned by communities (refer section

1.6). Taking a serious note on the status of natural resources, Government of Meghalaya

launched its Integrated Basin Development Programme (IBDLP) as its flagship programme

in 2012.

Integrated basin Development and Livelihood Programme (IBDLP) is a citizen-centric and

demand driven programme that emphasizes on self-reliance and entrepreneurship based on

development of social, intellectual (skills) and natural capital through community

participation as the pathway to its vision for sustainable eco-systems development. It is

systematic approach for inclusive growth through universal access, universal opportunity and

universal coverage centred around good governance, convergence, institutional

strengthening, capacity building, knowledge management, communications and financial

inclusion. Innovation, optimisation and sustainability run across all aspects of IBDLP.

Thus the programme ensures “universality to partners” catalysing people‟s aspirations to

participate through fair and transparent policies rather than through a “targeted beneficiary

approach” which may lead to exclusion or marginalisation. This flagship programme has two

major investment areas:

i) Natural resource management through landscape approach (CLLM –Programme);

ii) Livelihood and market access through agri-value chain promotion and

development of market infrastructure (Megha-LAM Progamme).

Thus IBDPL as a programme has two sub-programmes viz. CLLM-Programme to cater to

needs of community based NRM through land scape approach; and Megha-LAM Programme

to address issues of livelihood and market access. Each of these programmes are supported

and partially financed by the IFAD (on-going Megha-LAM Project) and the World Bank

(proposed CLLM-Project).

Megha-LAMP (Programme) has three major components viz.

1. NRM based livelihood and food and water security

2. Livelihood support through i) enterprise development ii) integrated production and

marketing clusters iii) livestock development iv) marketing infrastructure and market

roads v) rural finance and

3. Knowledge Services for information on core areas of NRM and livelihood

development including technology testing and action research; communication and

information dissemination to stakeholders on NRM and livelihood.

Page 18: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

12 | P a g e

Figure 3 Synergy of CLLMP with IBDLP

CLLM-Programme, on the other hand, aims at strengthening communities and traditional

institution to manage their natural resources such as soil, springs and other water sources,

forest and biodiversity, agriculture and horticulture through landscape approach. This

program is designed to strengthen community participation in planning and implementation

of landscape based activities; improved project management skills and building knowledge

and capacity etc.

Village based integrated planning and governance is common feature of both CLLM-

Programme and Megha-LAMP.

In order to catalyse, design, evolve and standardise State-wide investment policies and

practices two smaller projects one for each sub-programme were designed. CLLM-Project,

financed by the World Bank, is expected to serve into universal CLLM-Programme while

Megha-LAMP (Project) serve universal Megha-LAM Programme thus providing universal

access and opportunity to the people of Meghalaya. Both the programmes and their respective

projects complement and supplement each other.

Programme CLLM-Programme Megha-LAM Programme

Coverage Across the State (universal) Across the State (universal)

Project for

demonstrating

and evolving

programme

principles

CLLM Project financed by World

Bank (proposed)

Megha-LAM Project financed

by IFAD (on-going)

Programme

supported by

respective

project-specific

activities in

limited

Preparation and implementation of

village based Community NRM

Plans with landscape approach in 400

villages

Preparation and implementation

of livelihood plans (IVDPs) in

1350 villages for

1. NRM based livelihood and

food and water security

2. Livelihood support through

Page 19: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

13 | P a g e

geographies i) enterprise development

ii) integrated production and

marketing clusters

iii) livestock development

Project activities

with universal

coverage

supported by

respective

projects

1. Strengthening capacity building of

communities, traditional

institutions and other stakeholders

for landscape management

2. Knowledge management and

communication services for

landscape management

iv) marketing infrastructure and

market roads

v) rural finance

3. Knowledge Services for

livelihood

Source of finance

for replication of

project

investment

activities in

geographies

beyond project

areas

State and Centrally Sponsored

Schemes mainly NRM component of

MGNREGS

National Infrastructure

Development Assistance

(NIDA) and RIDF from

NABARD for market access and

infrastructure / roads

State and Centrally sponsored

schemes

Thus both Megha-LAM Project and CLLM-Project feed into and are later expected to merge

with wider Megha-LAM Programme and CLLM-Programme under IBDLP. Universal

coverage, equal access and equal opportunities for development for the people of Meghalaya

is quintessence of IBDLP irrespective of the source of funds. IFAD and World Bank funding

have been introduced to bring in best practices that can be replicated beyond the geographies

covered under these projects.

Page 20: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

14 | P a g e

2. Project Framework

2.1.Proposed Developmental Goal of the CLLM-Project

To strengthen community-led natural resources management with landscape approach in the

State of Meghalaya.

2.2.Higher level objectives

Sustainable Management of natural resource for economic growth: to manage and

conserve the natural resources, especially forests, soil and water sources, in a manner that

support accelerated economic growth and well-being of every community in Meghalaya

Institutional development: institutionalize and demonstrate a model for government

support to community-led management of natural resources that could be replicated in

other parts of India where communities have the legal rights over the resources.

Promotion of Country Partnership Strategy of WB and GoI : The proposed operation

under the project is also consistent with the World Bank India Country Partnership

Strategy (CPS) for 2013-17 which focuses on Transformation and Inclusion by

supporting community-led interventions to restore and sustainably manage forests, land

and water resources and biodiversity, on which 80 percent of the population depends, and

by enhancing the involvement of the World Bank in a low-income state of India which is

committed to reforms.

Alignment with SCD: The proposed project is also aligned with India‟s emerging

Systematic Country Diagnostic (SCD) which stresses the importance of a resource-

efficient and inclusive growth path. Meghalaya is in the North-East, a financially

excluded region in the country with lower per capita income than the national average,

low HDI and a large population of scheduled tribes. In addition to supporting

community-led natural resource management in the state, the proposed project will have a

positive impact in terms of improving the availability and reliability of water sources for

drinking and economic purposes through various interventions in soil and water

conservation. Furthermore, the proposed project is well aligned with the WBG Forest

Action Plan and its focus area of Sustainable Forestry. In particular, it will contribute to

the goals of the Climate Action Plan by optimizing the potential of natural forests to

provide monetary and non-monetary benefits, participatory management and

rehabilitation of degraded lands.

2.3.Project Period

Project will be implemented over a period of five years.

2.4.Project Area

As discussed earlier, natural resources viz., forests, bio-diversity, water sources and soils in

Meghalaya are in high state of degradation due to anthropogenic and climatic factors.

Therefore, it is logical to include area for treatment that have acute water shortage, high

degradation of forests and soils with high incidence of poverty of resource dependent

communities. In 2012 the North East Space Application Centre (NESAC) conducted

watershed based vulnerability analysis of all 35 watershed and 179 sub watersheds of

Meghalaya and classified landscapes as (i) most critical (very high priority), (ii) moderately

Page 21: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

15 | P a g e

critical (high priority), and (iii) low priority areas based on vegetation index, slope and soil

brightness index.

Very high

vulnerable to

soil erosion

High vulnerable to

soil erosion

Moderately

vulnerable to soil

erosion

Low or very

low priority

watersheds

Area in sq. km 1427.31 8891.86 10993

No. of sub-

watersheds

30 29 77 43

Figure 4 Area in high priority zone

Page 22: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

16 | P a g e

Figure 5 Area in very high priority zone

However, The NESAC classification of critical landscapes is over 5 years old and it is possible that

number of villages under critical and very critical category may have increased over the years.

Therefore, ground truthing of such villages will have to be undertaken before such villages are taken

up for intervention under Component 2 of CLLM-Project.

Since the WB assistance is limited, the Government of Meghalaya will utilize it to establish and

demonstrate best practices for planning and implementation of landscape management approach

through actual investments in land, water, soil and forests development activities in few villages so

that those practices can be replicated in the entire State as part of CLLM-Programme. It would be

reasonable to take up landscape management activities in around 400 villages. Keeping in view the

principle of providing equal opportunity to all villages through self-selection process, all villages that

are finally identified as falling under critical and very critical landscapes will have equal opportunity

to submit their Expression of Interest for participating under CLLM-Project. First 400 villages that

demonstrate their preparedness to implement CLLM-Project through achieving set milestones will

receive investment funds for CNRM plan preparation and implementation under the project. All

remaining villages in the State will receive financial assistance from GoM from State and Centrally

sponsored schemes under CLLM-Programme for implementing CNRM plans as and when they are

able to achieve set milestones for receiving that assistance.

Page 23: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

17 | P a g e

2.5.Target Village Selection Criteria and Process (Milestones) under the Project

Step 1 Sensitisation and Awareness Generation: All villages will be sensitized on IBDLP

and CLLMP approaches and further screening requirement/ milestones for CLLM-

Programme by block level officials /demonstrators. These officials will organise series of

village level meetings, where all households in a village will participate, to discuss issue of

natural resource degradation that affect them and how they can jointly manage them. In these

meetings, CLLM-Programme and its community operational manual along with a draft

citizens charter will also be introduced to the villagers. Theecitizens charter would be a joint

undertaking by the community to conserve and sustainably manage their natural resources.

Villages will ne guided and encouraged to constitute their village NRM Committee and its

executive committee and open their bank account as per the Community Operations Manual.

Basic eligibility criteria under CLLM-Project: While all villages will be eligible to

participate in the CLLM-Programme of the Government of Meghalaya, the World Bank

assistance will be used for planning and implementation of Community NRM Plans

(Component 2 of the Project) in limited villages (400 Nos.) in critical and very critical

landscapes only. The Government of Meghalaya will use GIS tools and ground truthing to

villages that have high incidence of poverty amongst resource dependent communities, acute

water shortage and high degradation of forests and soil resources.

Step 2: Submission of Expression of Interest: The villages (or cluster of villages) will

submit their expression of interest at block unit, for inclusion under the project/programme

through an agreed template (draft template will be provided in the Community Operations

Manual).

Step 3: Screening of Expression of Interest

The expression of interest by each village (or cluster of villages) will be screened at block

level using the following major and optional criteria:

Major criteria

One female (head of the family) and one male Member of each household sign Citizens

Green Charter

Bank account for Village CNRM committee is opened.

Availability of undisputed land for CLLMP

Percentage performance under various State and Centrally sponsored schemes,

particularly MGNREs (this will be an “ranking criteria” to shortlist villages if there are

more number of applicants)

Optional criteria

Village NRM committee is established and Executive Committee for project planning

and implementation is appointed

Land dispute, if any, is resolved or excluded from prospective development

Traditional knowledge holders on NRM are identified

Community nursery is established

6-8 youth are selected for undergoing training on various aspects of land-scape

management (GIS and geospatial tools, CNRM plan preparation, accounting and book

keeping, social and environmental safeguards, social audit, community mobilisation etc.)

Page 24: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

18 | P a g e

Note: Representation for regional balance (village will be selected in proportion to the

number of villages in critical landscape in each of Garo, Khasi and Jaintia regions)

First set (400) of villages that submit their valid expression of interest for inclusion under

CLLM-Project after having satisfied above criteria will receive financial and technical

assistance for project planning and implementation once their EoI is accepted as per the

guidelines developed for the same.

On evaluation of EoI the District Screening Committee and District Project Management Unit

will decide source of finance for any village (WB assistance / other sources under CLLM-

Programme). All those villages who submit their valid expression of interest and which are

not covered under CLLM-Project will be covered under CLLM-Programme in a phased

manner. This design will not only ensure competition for willing and active participation

amongst villages to be covered under the project/programme but will also ensure timely and

adequate absorption of project/programme funds.

2.6.Project benefits.

1. The project will ensure increased availability of water, biological resource and soil

productivity which will impact the around 55500 ha. of land in 400 villages under

different activities as summarised below

Particulars Benefitted

area (ha.)

Remarks

Agriculture land –Kharif 8278 20-30% increase in crop production

Agriculture land – Rabi 5466 20-30% increase in crop production

Horticulture 4830 10% of better culturable wasteland used for

horticulture

Agro-forestry 5217 30% of culturable wasteland used for agro-

forestry

Forestry 12585 50% of highly degraded forest area

developed as dense forests through

reforestation and natural regeneration

Soil and water

conservation measures

22632 Mainly in culturable wastelands and

degraded forest areas. Only area not treated

under any of the previous schemes will be

undertaken for development

Mining affected area

treatment

600 Rough estimate

Treated area under the

project

31510

Average area per village 78.78

Page 25: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

19 | P a g e

3. Project Components

3.1 Project cycle

The project and programme will be implemented in the following sequence

Step Activity Responsibility Component

1 Establishment of SPMU, DPMUs, BPMUs MBMA CLLM-Programme

and Project

1 Identification of critical and very critical

landscapes

SPMU CLLM-Project

2 Sensitisation and awareness on IBDP and

CLLMP

Discussion of NRM Issues and draft Green

Citizens‟ Charter and Community Operations

Manual with the villages

DPMU and

BPMU

CLLM-Programme

and Project

3 Formation of Village NRM Committees and

Executive Committees

Opening of bank account

Identification of youth for training and capacity

building

Village CLLM-Programme

and Project

4 Submission of Expression of Interest for

participation in CLLM-Project/ Programme

Village NRM

– Executive

Committee

CLLM-Programme

and Project

5 Screening on EoIs from villages By DPMU and

recommendati

on made to

SPMU

CLLM-Programme

and Project

6 Training and capacity building, awareness,

critical consultancies, research and development,

and knowledge management

SPMU with

DPMU

Comp-1

7 Release of funds for plan preparation for villages

who have under gone training

DPMU Comp-2

8 Procurement of services of village service

providers (trained under component 1)

Requisition for expert assistance from block

level and district level experts

Plan preparation

Village NRM

Committee

Comp-2

9 Submission of plan Village

Committee to

DPMU

through

BPMU

Comp-2

10 Review and approval of plan DPMU Comp-2

11 Plan approval and signing of MoU between

DPMU and village committee

DPMU Comp-2

12 Implementation training SPMU and

DPMU

Comp-2

13 Release of funds for plan implements in tranches SPMU to

Village NRM

Comp-2

Page 26: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

20 | P a g e

Committee

14 Procurement of labour and material

Requisition for expert assistance from block

level and district level experts

Village NRM

Committee

Comp-2

15 Plan implementation Village NTM

Committee

Comp-2

3.2 Project Components

Figure 6 Project Components

In order to achieve project goal and higher level objectives the project has been designed to

have three components viz

1. Strengthening knowledge and capacity of stakeholders

2. Planning and implementation of Community Natural Resource Plans

3. Project Management

3.2.1. Component 1: Strengthening Knowledge and Capacity for NRM This component will be implemented in the entire State through World Bank Assistance.

Continuous development, assimilation, analysis and dissemination of knowledge and skills

related to landscape management is important for project implementation. This component

has following sub-components:

1. Promotion of traditional knowledge, grass-root innovations and communication

2. Strengthencommunities through training and capacity building

3. Promotion of landscape management principles through Catalytic Funds

4. Research and development

5. Monitoring, learning and reporting

GIS and Geo-spatial

application(Component 1)

Strengthening

Knowledge and

Capacity for NRM -

Knowledge

Centres and

Communication

(Component 1A)

PMU Technical

and Management

Support

(Component 3)

Monitoring and

Evaluation

(Component 1)

Training and Capacity

building of Stakeholders

(Component 1B)

Preparation of Community

NRM Plans (Component 2)

Plan implementation

(Component 2)

Page 27: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

21 | P a g e

3.2.1.1. Component 1A: Promotion of traditional knowledge, grass-root innovations and

communication

i) Participatory documentation and exchange of traditional knowledge: This will

involve:

Community consultation will be held by MBMA/ MBDA at the State level

and Regional level through seminars and workshops. It may include

identification of opportunities for promoting unique NRM practices (e.g.

Living Root Bridges, bamboo-based drip irrigation etc.) in Meghalaya;

learning from IVDPs and resource maps developed through PRA under

other projects and community driven initiatives; review of existing

institutions for their potential contribution to landscape management and in

development of plans for convergence of various schemes and resource at

the disposal of these institutions.

Development of KM strategy

Development of e-platform for dynamic sharing of landscape related

knowledge with the community under IBDLP and development of

knowledge networks.

Development of website for CLEM-Programme

ii) Promoting grassroots innovation:

Expression of interest will be invited from individual, village institutions,

community representatives and State / national level institutions /

organisation for innovations in sustainable natural resource management

and their products and services. Most potential innovative ideas will be

provided further grants to seek IPR, popularise and if possible

commercialise their innovation. The grant will cover cost of applied

research, testing, application and replication

iii) The project will also assist in preparation of strategy paper and action plan for

development of future centre of excellence in knowledge management, innovation

and communications.

3.2.1.2Component 1B: Training and Capacity Building

i) MBMA will closely work with Meghalaya Institute of Natural Resource

Management, Institute of Governance, Department of Science and Technology,

State Institute of Rural Development (SIRD), Forest Training Institute (FTI –

Tura) and Conservation Training Institute of the Soil and Water Conservation

Department (CTI) to impart training to various stakeholder of the project. If

required other State and National training institutes can also be roped in.

ii) A consulting agency will be involved to validate training need assessment of

various stakeholders done during initial consultation at the time of project

preparation. Following training needs were identified during initial consultation

with various stakeholder:

Sensitisation and introduction to the log Frame of the project,

Development of NRM plans including PRA tools, resource mapping,

vulnerability analysis, integrated village development planning, climate

change and its impact, water security planning and management, land

conservation and management planning, forest management planning,

project governance and conflict resolution, spring-shed development,

restoration of mined areas, soil productivity enhancement, fire protection

and disaster risk management, knowledge management tools, village level

maintenance of books of accounts,

Page 28: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

22 | P a g e

Project governance and conflict resolution

Use of GIS and geospatial technology in planning

Training on implementation on environmental and social safeguards in

project,

Soft skills and leadership development program for youth and women on

institutional dev. (communication and personality) development,

community ownership and collective action, motivation and positive attitude

for achieving goals, development of civic sense in youth etc.

iii) Development of training infrastructure: In order to optimise on training

infrastructure at block level Bharat Nirman Rajiv Gandhi Seva Kendra

(BNRGSK) or existing Enterprise Facilitation Centres will be equipped with

training infrastructure

iv) Publication and training material: Various project related publications, videos,

radio programmes, case studies, information kits etc in English and local

languages will be financed under the project. Preparation of training material

for technical and soft skills required for project implementation will also be

undertaken. The Community Implementation Manual will be developed.

v) National and international exposure visits for stakeholders will be conducted

3.2.1.3 Component 1C: Promotion of CLLMP Principles through Catalytic Fund

Village not covered under the CLLM-Project for investment under Component 2 will be

supported by the State Government under CLLM-Programme. A catalytic fund will be

established to fill any gaps that are required for adoption of CLLMP principles in non-project

villages. This could include improvement of designs, systems, procedures in various

activities related to sustainable management of natural resources, adoption of social and

environmental framework, procurement and financial management, monitoring and

evaluation or acquisition of special equipment so support CLLMP principals and approach or

any other activity as deemed fit by the State Project Management Unit.

3.2.1.4 Component 1D: Research and Development

Following activities will be financed under this sub-component

Institutional development study for IBDLP

Baseline survey/study for the project

Drivers of deforestation and natural resource degradation

Rehabilitation of population displaced due of mines

Further research, as required, on gaps in community conservation practices and

knowledge as identified during community consultation workshop

3.2.1.5 Component 1E: Monitoring learning and reporting

A State-wide MIS based performance tracking system is an important management tool that

will be used to track implementation progress and other aspects of the IBDLP including

CLLM-Project at select intervals. MIS structure, indicators and information flow will be

designed along with defining the information requirement from institutions/stakeholders.

MBMA will design and establish MIS infrastructure for CLLMP that can be scaled up to cater

to other requirements of IBDLP. It has also been suggested that since multiple other state

government and central government schemes are being digitalized, provisions be made for

linkages between this MIS platform and such other platforms for the sake of data

rationalization and information sharing. This MIS system will also help villagers, traditional

leaders, farmers, Government officials, project team members, facilitating NGOs to

understand their roles and responsibilities to manage their natural resources more efficiently.

Page 29: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

23 | P a g e

3.2.1.6 Costing of Component 1

Page 30: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

24 | P a g e

Page 31: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

25 | P a g e

Page 32: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

26 | P a g e

3.2.2 Component2: Community-led Landscape Planning and Implementation

3.2.2.1 Sub-Component 2A: Preparation of CNRM Plans

Community Operations Manual provides detailed guidance on preparation of landscape plans.

Communities, with the help of project facilitating teams (subject matter specialists) at block

level and village level service providers will prepare plans which will allow communities to

(i) optimize synergies between programs and funding streams; (ii) plan holistically rather than

be program/ scheme-driven to meet targets; and, (iii) take a leadership role for the

management of natural resources under their stewardship.

Plan preparation in a village will be preceded by community mobilization; formation of

Village NRM Committee and selection of an executive committee within the village to

coordinate and manage the process on behalf of the village; submission of expression of

interest by the village for participating in CLLM Project/ Programme; training and capacity

building of village service providers and members of the executive committee. The process

will be further enhanced with communities receiving support in the use of latest geo-spatial

tools for planning and monitoring. During development of these plans communities will

identify the leading causes of degradation of natural resources in their area and agree on

actions to address those and capitalize on new opportunities and on trade-offs.

Following principles will be adhered to during planning process under CLLM-Project and

Programme.

1. Best management practices: Best management practices will be adopted right from the

planning state itself. These will related to informed and consented decisions making by

the stakeholders; prior removal of bottlenecks, respect for shared natural resources;

equitable access to natural resource; sustainability of investment with provision for future

maintenance of assets beyond the project period; constructive channelizing power of

youth; dignity of labour and shared responsibility; self-reliance through training and

capacity building, knowledge management and optimal use of technology.

2. Project facilitationat village and block levels: CNRM Plans will be developed with the

help of project facilitating teams (subject matter demonstrators) at block level; technical

experts nominated from the district offices; and village service providers5 at the village

level. Each village can use services of village-based youth who have been trained in

various aspects of CNRM planning and implementations such as forests management,

water & soil conservation, maintenance of accounts, environmental safeguards and social

safeguards and gender etc. Project villages will also have a GIS community assistant for

data compilation and management.

These service providers will be trained by SIRD, Forest Training Institute, Conservation

Training Institute of Soil and Water Conservation Department, MINRM, MIG and

Knowledge Services Division of MBDA etc. on various aspects of CNRM plan

preparation and implementation.

It is envisages that shorts term technical experts on various aspects of plan preparation

and implementation can also be engaged from the market. The DC office will prepare a

panel of experts on calling the expression of interest and engage on an average 300

5Also called as green volunteers under IBDLP

Page 33: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

27 | P a g e

person days / per year of ST experts at the block level to assist the block facilitation

teams in project planning, execution and supervision.

3. Application of environmental and social safe-guards: For EMF there are 3 levels of

screening (i) eligibility screening, (ii) regulatory requirements screening and (iii)

Screening/Identification of environmental impacts based on which the community will

identify any risks, impacts or permits needed, and adopt the appropriate mitigation

measures and cost them so the C NRM plan is compliant with the provisions of the

EMF.CLLM-Programme will adopt and follow the procedures in the project social and

environmental management framework and will ensure that following list of activities are

avoided with CLLMP funding:

Activities that are in violation of existing laws and policies GoI, GoM.

Purchase of land;

Construction of dam (existing or new) of 10 m height or more.

Use banned pesticides, agrochemicals in WHO classes IA, IB and II.

Activities that would adversely affect religious or cultural sites and historical assets.

No individual to be excluded to participate in the proposed interventions based on any

criteria (social, economic, gender, land ownership etc.);

Activities that lead to alteration, conversion, deforestation or degradation of natural

forests or natural habitats.

Activities on lands under dispute

Financing of elections or election campaigns

4. Components of village CNRM plans: Community Operations Manual (COM) of the

project will outline processes of community consultation and development of CNRM

Plans. COM will specifically define “bottom-up” participatory planning processes viz.,

Participatory Rural Appraisal (PRA) and Participatory Rural Investment Planning (PRIP)

3.2.2.2 Sub Component 2B(i) CNRM Plan Implementation

Plan preparation and implementation in each village will take 4 years i.e. 1 year for plan

preparation and 2 years for plan implementation and 1 year for consolidation. 60% of the

investment cost will be incurred in the 1st year of implementation and 40% in the 2nd

year of

implementation. Tentative phasing of different set of villages for Plan Preparation (PP),

Plan Implementation (PI) and Plan Consolidation (PC) will be as under.

Months 1-6 7-12 13-18

19-24 25-30 31-36 37-42 43-48 49-54 55-60

Villages

100 PP PI PC

150 PP PI PC

150 PP PI PC

Actual implementation of plans will be in a phased manner, agreed through an MoU between

the Village NRM Committee and respective District Project Management Units.

Communities will first implement agreed first phase activities in their plan and graduate to

the next phase of financing if implementation meets agreed criteria. This approach is meant

to incentivize performance based access to funds by the communities. Criteria for assessing

successful implementation will be agreed in the MoU itself. Actual interventions needed

will be decided by the community in their respective CNRM Plans will relate to Soil and

water conservation measures; soil health improvement and productivity

Page 34: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

28 | P a g e

enhancement measures; spring-shed development and water management plans; nursery and

agro forestry and community forestry; optimisation of shifting cultivation; rehabilitation of

areas affected by mining etc.

Average Village cost for Component 2B(i) (Rs. in Lakh)

3.2.2.3 Sub Component 2B(ii) CNRM Implementation Support

1. Implementation of Social and Environmental framework: Implementation of

social and environmental management framework including setting up of grievance

redressal mechanism, training and consultation of social and environmental issues e,

external evaluation of status of implementation etc.

2. Use of GIS and geospatial technology: It provides a platform where all data/

information products relating to development, governance, project design, planning,

monitoring etc. can be tagged with geospatial identifiers and represented in

Geographic Information Systems. This will also include development and

maintenance of community level outreach network through establishment of village

level kiosks and building capacity of different stakeholder to use the technology and

its infrastructure.

3. Monitoring and Evaluation: Monitoring and Evaluation (M&E) is a very important

aspect of any project to ensure smooth and efficient implementation through tracking

and documentation of results, processes and experiences. Monitoring is checking

progress against plans. The data acquired through monitoring is used for evaluation.

M&E will consist of in-house monitoring, external evaluation and reporting:

In-house output and outcome monitoring: This will ensure that the targets and

milestones set are achieved in the stipulated timeline. Various types of monitoring

systems will be adopted:

Progress monitoring visits by project staff and desk monitoring: This will be

undertaken on a regular basis to ascertain achievement of physical targets for

project activities and outputs as set out in Annual Work Plans and Budgets and

provide course corrections. This activity will be undertaken by the SPMU team

and will be based on reports generated and MIS.

Self-monitoring by community institutions: Given the focus on sustainability of

community institutions, the need for applying a mechanism for continuous

(concurrent) tracking of organizational growth and performance of these

community institutions is emphasised. Therefore, it is proposed to design and

implement a Participatory Monitoring and Evaluation (PME) framework in the

inception phase to delineate approaches and pathways towards development of a

Spring development 1.75

1

Composting 1

Other components of NRM Plan 17.8

External experts hired by village CNRM Committee 2.5

Green Service Providers from village 11.52

35.57Total

Nursery

Page 35: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

29 | P a g e

community-based contextual, evolutionary/adaptive M&E system for the Project.

The framework can be developed by the M&E team. The PME could be

implemented by village institutions and uploaded in the project MIS using tablets/

mobiles. A simplified mobile based technology feedback system can be used at

community level to capture and feed data into the Management Information

System of the PMU. PMU will also establish a too-free number for reporting of

concurrent monitoring by the community and for grievance management.

Financial and Procurement Monitoring: A Financial and Procurement

Monitoring and Supervision system shall be installed. For that purpose, a

“Financial Monitoring Guideline” and Procurement Manual outlining

procurement procedures under the projectshall be prepared during the inception

phase of the project. The expenditures will be audited by in-house concurrent

auditor annually with regard to the correctness of the procedures, amounts and

documents by a professional Auditing Company and the audit reports shall be sent

to World Bank.

External evaluation: Based on reports from various studies, monitoring mechanisms

and MIS, half yearly and annual progress reports will be compiled and submitted for

review. Any issues of concern/red flags and suggestions for course correction will be

included in these reports.

Mid-term Assessment Study – this would be undertaken mid way through the

project to ascertain the progress achieved and any mid-course corrections which

need to be introduced. It would include indicators to measure progress towards log

frame goals and objectives.

End-Term Assessment Study – this will be undertaken at the end of the project

period (around the time of project completion) and will assess the achievement of

the project during the tenure.

Reporting: MBMA shall report to the WB semi-annually on the progress of the

project (progress report), including on the fulfilment of implementation agreements

and on all developments of all other important general conditions. The content and

form of report shall be determined by the WB and agreed in the Separate Agreement.

In addition, MBMA shall report on all circumstances that might jeopardise the

achievement of the overall objective, the project purpose and the results. The first

report of the state of affairs shall be submitted within three months after launch of the

project. Subsequent reports must be submitted to the WB not later than 6 weeks after

the end of the period under review. At the time of physical completion of the Project,

MBMA shall submit a final report on the measures carried out

Page 36: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

30 | P a g e

3.2.2.4 Costing of Component 2

Average Village cost for Component 2B(i)

2A.(i) CNRM PLAN PREPARATION Rs. Lakh

Unit Lakh/Unit Year 1 Year 2 Year 3 Year 4 Year 5 Total

100 150 150 400.00

a) Plan preparation cost @ Rs.30000 per plan (Rs. Lakh) 0.3 30.00 45.00 45.00 120.00 Grant

b) Sensitisation of CNRM Committees (1 day) 1015 Trg norm 7.08 7.08 14.16 Grant

c) 5 Day Training of selected CNRM Committees (7 members) 400 Trg norm 46.38 69.56 69.56 185.50 Grant

83.45 121.64 114.56 0.00 0.00 319.66

2B(i) CNRM IMPLEMENTATION

35.57

100 150 150 400

100 150 150 400

a) 1st Cost of plan implementation @ 60% of outlay 2134.20 3201.30 3201.30 8536.80 Grant

b) 2nd year of plan implementation @ 40% of outlay 1422.80 2134.20 2134.20 5691.20 Grant

c) Cluster development fund (common investment between villages) 500.00 750.00 750.00 2000.00 Grant

d) Social Audit 400 0.045 18.00 18.90 19.85 20.84 21.88 99.46 Grant

Sub 18.00 2153.10 5143.95 6106.34 2906.08 16327.46

No. of villages

Treatment cost per village (Rs. Lakh)

Ist year of plan implementation (No. of villages)

2nd year of plan implementation (No. of villages

Particulars

Sub Total

Spring development 1.75

1

Composting 1

Other components of NRM Plan 17.8

External experts hired by village CNRM Committee 2.5

Green Service Providers from village 11.52

35.57Total

Nursery

Page 37: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

31 | P a g e

2B(ii) CNRM IMPLEMENTATION SUPPORT

a) Implemenation of E&SMF LS 65.00 68.25 71.66 75.25 79.01 359.17 CS

b) GIS and Geo Spatial Equipment 737.24 737.24 Goods

c) GIS and Geo Spatial Consultancy 178.80 187.74 197.13 206.98 217.33 987.98 CS

d) GIS operating expenses 12.00 12.60 13.23 13.89 14.59 66.31 IOS

e) Project Equipment (Software and hardware) 1099.20 1099.20 Goods

f) Monitoring and Evaluation 20.00 21.00 77.18 23.15 85.09 226.41 CS

2112.24 289.59 359.19 319.27 396.01 3476.30

2213.69 2564.33 5617.70 6425.61 3302.09 20123.43

844.89 115.84 143.68 127.71 158.40 1390.52

0.61 73.21 174.89 207.62 98.81 555.13

1368.18 2375.29 5299.13 6090.29 3044.88 18177.77

20123.43

GoM Contribution 2A(i) 0.00% 0.00 0.00 0.00 0.00 0.00 0.00

2B(i) 0.00% 0.00 0.00 0.00 0.00 0.00 0.00

2B(ii) 40.00% 844.89 115.84 143.68 127.71 158.40 1390.52

Community contribution 2A(i) 0.00% 0.00 0.00 0.00 0.00 0.00 0.00

2B(i) 3.40% 0.61 73.21 174.89 207.62 98.81 555.13

2B(ii) 0.00% 0.00 0.00 0.00 0.00 0.00 0.00

World Bank 2A(i) 100.00% 83.45 121.64 114.56 0.00 0.00 319.66

2B(i) 96.60% 17.39 2079.89 4969.05 5898.72 2807.27 15772.33

2B(ii) 60.00% 1267.34 173.75 215.52 191.56 237.61 2085.78

Total 2213.69 2564.33 5617.70 6425.61 3302.09 20123.43

Grand Total

GoM Contribution

Community Contribution

World Bank contribution

Details in Annex

Sub total

Details in Annex

Details in Annex

Details in Annex

Details in Annex

Page 38: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

32 | P a g e

3.2.2.5 Steps in CNRM plan approval and release of funds for investments

Village level

(i) Each Village CNRM Committee shall prepare its CNRM Plan with the assistance of

the cluster facilitation staff / technical staff at the block level and also by using

expertise of the traditional knowledge holder.

(ii) Village CNRM Plans will have annual plans and 6 monthly milestones for release of

funds.

(iii) Village CNRM plans will be endorsed by the head of traditional institutions at the

village level (headman) and sent to BPMU for onward submission to DPMU

Block level

(i) BPMU will conduct a quality assessment of the Village CNRM Plan.

(ii) BPMU will prepare a consolidated statement of all village CNRM plans received by it

(iii) BPMU can suggest/ make qualitative improvements in the plans in consultation with

the VPMU Executive Committee before sending it to DPMU

(iv) BPMU will also prepare their block –sub plans

(v) Consolidated block plan will be sent by BPMU to respective DPMU along with

village CNRM plans and recommendations thereon.

District level

(i) DPMU will constitute a committee to review, appraise and approve village CNRM

plans. The village plans, if not found to be in order, can be returned by DPMU to

VPMU for improvement and amendments.

(ii) The DPMU will prepare the District Plans which will be aggregation of a) All village

CNRM plans b) Block sub-plans c) and District sub-plan.

Page 39: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

33 | P a g e

State level

3.2.2 The SPMU will prepare State annual Plans with aggregation of the district plans and

state sub-plan.

(iii) The Sate CLLMP Plans will be approved by the State Project Steering Committee

based on the recommendation of the Project Operations and Finance sub-committees.

B. Fund flow for plans

Based on the approved yearly plans of each village, DPMU will provide annual budget

and six monthly funds to each VPMU.

Based on the approved yearly plans of each BPMU, the DPMU will provide annual

budget and yearly funds to DPMU.

Based on the approved annual plan of each DPMU, the SPMU will provide budget and

annual funds for DPMU sub-plans, BPMU sub-plans and Village CNRM plans.

DPMU will release project funds directly to VPMU on six monthly basis for project

operations (Component 2) based on their annual plan and six monthly progress report or

completion report whichever is earlier.

C. Revision of plan by VPMU

If required, each VPMU can review and revise their CNRM plan whenever required and

get the revised plan approved by the DPMU. DPMU can consider such plans on merit

depending on budget availability, technical feasibility, financial viability, economic and

environmental relevance and social acceptability.

These revised plans will further get incorporated in the plans of BPMU, DPMU and

SPMU.

3.2.3 Component 3: Project Management and Governance – Institutional Structure

The implementation arrangements of the project will constitute of the governance and

management structure of the project from state to the village level. The implementation

arrangements will also cover the details regarding financial management, disbursement and

procurement.

3.2.3.1 State Level

The overall management and coordination will be the responsibility of the Meghalaya Basin

Management Agency (MBMA), an existing Section 8 Company under Companies Act, 2013

floated by Government of Meghalaya to undertake EAPs. The CLLM-project will be

controlled and supervised by the Board of Directors of MBMA. The Board of Directors

comprises of the Chief Secretary of GoM (Chairman), CEO – MBMA, Retd IAS, Dy CEO –

MBMA, Principal Secretary Finance. The Board of Directors of MBMA meet on a quarterly

basis to approve and review the work plans and budget. It accesses the physical and financial

progress of the project and provides corrective measures. Further, it will review and

recommend policy measures to the GoM to ensure sustainability of the project/programme.

Moreover, it will assess and facilitate convergence across different line departments and

stakeholders at the state level.

State Project Management Unit (SPMU): As already mentioned, Meghalaya Basin

Management Agency (MBMA) is the nodal agency for management and implementation of

the project activities. The day-to-day executive control of the Project is with the State Project

Page 40: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

34 | P a g e

Director, who heads the State Project Management Unit (SPMU). The core personnel of the

SPMU are 2 Additional Project Directors for Garo Hills and Jaintia/Khasi Hills; 5 Deputy

Project Directors for activities related to Soil, Water, Forest, Community and Rural

Development and Administration. DPD Administration will also responsible for Finance and

Procurement; and 5 Managers (Environment Management, Social Safeguard and

Management, Monitoring and Evaluation, Knowledge Management, Training and Capacity

Building, Administration). Each of these managers will be supported by subordinate staff as

given in the figure below:

Figure 7Organogram State Project Management Unit

The staff depicted in blue colour will be hired from the market and remaining staff will be

deputed from various line departments of the Government of Meghalaya. The SPMU will

undertake overall planning and implementation of the project. It will be responsible for

reviewing and finalizing fund flow mechanisms, procurement management, reporting and

monitoring, policy advocacy and awareness generation. It will prepare guidelines and

technical manual for programme activities, including the community operational manual.

Moreover, it will provide infrastructural and institutional support to district, block and village

level units.

3.2.3.2 District & Block Level

The project operations at the district level will be governed by the District Project Steering

Committee, headed by the Deputy Commissioner (Chairperson). The members will be the

Officers from the Line Departments in the Districts as well as the Blocks, DPM (Operations)

and DPM (Admin) will be the Member Secretary, there will be two independent members

who will be invited by the Chairman as per the need. The Committee will convene quarterly

meetings to guide, supervise and monitor the progress of the project. In addition, the

committee will review and approve CNRM Plans submitted by block units.

District Project Management Unit (DPMU):

Day-to-day operation and administration of the project will be carried out by two District

Project Managers viz., DPM (operations) and DPM (administration). DPM (operations) will

Page 41: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

35 | P a g e

be supported by a Manager and DPM (administration) will be supported by an Assistant

Manager. The DPMU will draw upon technical government officers from respective line

departments (Soil and Water, Forest, C&RD) Additional staff will be hired for Environment,

Social and Knowledge Management, Procurement, Finance and M&E. In addition to district

level planning and coordination, DPMU will also conduct training needs assessment and

facilitate training and capacity building activities at the district, block and village level

through resource institutions.

Figure 8 Organogram of District Project Management Unit

Block Project Management Unit (BPMU): At the block level, the existing Enterprise

Facilitation Centre (EFC) and government officers will support Village Natural Resource

Management Committee (VNRMC) to plan and implement CNRM plans. The government

officials will be from the Department of Soil and Water Conservation, Water Resource

Department, Forest Department and C&RD Department etc. The Block Development Officer

will be overall responsible for the project at this level.

Figure 9 Organogram of Block Project Management Unit

3.2.3.3 Village level

Since the project is community-driven, village is considered the primary unit of planning and

implementation of CLLM-Project. VNRMC will comprise of one male and one female

member of each house hold. They will appoint an executive committee to undertake day-

today operation and this executive committee members may be elected from Self Help

Groups, Women Groups, Youth etc.. One person from the line department will be available

District GIS

Coordinator

DPM -Admin (1) DPM -Operations (1)

Asst. Mgr. (1) Manager - Operations (1)

Prog. Associate - Proc & Fin (1) Asst Mgr. - Soil (1)

Asst Manager -M&E (1) Asst Mgr. - Water (1)

Asst Mgr. - Forests (1)

Asst Mgr. - C&RD (1)

Asst Mgr. - Environ (1)

.

DPM - District Project Manager Asst Mgr. - Social (1)

KM - Knowledge Management

C&RD- Community and Rural Development Asst. Mgr. - KM (1)

Dis

tric

t P

roje

ct S

teer

ing

Co

mm

itte

e

Deputy Comissioner

Page 42: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

36 | P a g e

from the Block to facilitate the activities. The number of members in Executive Committee

will be 5-7 persons. The VNRMC will be overall responsible for preparation and

implementation of plans and management of project fund, procurement and supervising, etc.

Page 43: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

37 | P a g e

3.2.3.4 Costing of Component 3

Details in Annex 1

World Bank 60.0%

Government of Meghalaya 40%

Year 1 Year 2 Year 3 Year 4 Year 5 Total

3A Human Resource

a) State Project Management Unit 253.80 266.49 279.81 293.81 308.50 1402.41

b) District Project Management Unit 256.20 269.01 282.46 296.58 311.41 1415.67

Total cost of human resource 510.00 535.50 562.28 590.39 619.91 2818.07

3B Administrative expenses

a) State Project Management Unit 76.09 79.89 83.89 88.08 92.48 420.43

b) District Project Management Unit 184.153 193.36 203.028 213.18 223.839 1017.56

c) Block Project Management Unit 120 126 132.3 138.915 145.861 663.08

Total of administrative expenses 380.24 399.25 419.21 440.18 462.18 2101.07

890.24 934.75 981.49 1030.56 1082.09 4919.14

534.14 560.85 588.89 618.34 649.26 2951.48

356.10 373.90 392.60 412.23 432.84 1967.66

TOTAL OF COMPONENT 3

Particulars

World Bank Contribution

Government of Meghalaya

Page 44: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

38 | P a g e

3.2.4 Summary of CLLM – Project Costing (INR) (Note: Contribution of GoM under Component 1 and 2 = 38.5%)

Page 45: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

39 | P a g e

3.2.5 Summary of CLLM-Project Costing (USD)

Page 46: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

40 | P a g e

4. Financial and Procurement Management

4.1 Financial Management

4.1.1 Main assumptions a. Project life : The project life is 5 years, starting from fiscal 2017-18 and it is expected to

be completed by fiscal 2022-23.

b. Physical and price contingencies : As all project interventions are on a project mode,

no specific physical contingencies have been applied. Price contingencies will be applied

on various items and activities once the same is finalized.

c. Inflation rate: As per the data from Ministry of Statistics and Programme

Implementation (MOSPI), India, the inflation rate as on September 2016, inflation rate is

5%.

d. Exchange rates : The initial exchange rate for the analysis has been set at Indian Rupees

(INR) 65 to one USD, the rate prevailing at the time of plan preparation (October 2017).

Exchange rates during implementation phase and the foreign exchange rates forecasts for

the Project costs estimates, and conversions from current INR values into USD are to be

calculated using current exchange rate (INR/USD). Both foreign and local inflation rates

are compounded at mid-year.

4.1.2 Project Component Financing and Financial Management Project will have three components viz.,

1. Strengthening knowledge and capacity of communities for improved NRM

2. Planning and investments

2A Landscape Planning for Sustainable Natural Resource Management

2B Investment in NRM activities

3. Project Management

The proposed financiers for the CLLM-Project are the World Bank, the Government of Meghalaya,

and community. The World Bank will finance about USD 48 million about 80% of total project costs,

the government counterpart funding will be about USD 10.68million, and the community contribution

will be USD 1.32 million, mostly in the form of labour. The Government of Meghalaya will commit

USD 12 Million (USD 16.68 Million GoM contribution and USD 1.32 Million Community

contribution) as counterpart funding through convergence and State‟s resources under the CLLM-

Project

GoM will attempt to leverage funds from various central and state sponsored schemes for

CLLM-Programme to achieve the programme outlay of USD 200 million (including World

Bank finance) by replicating lessons learnt and following systems / procedure and good

practices under CLLM-Project. It is clarified that financial outlay of CLLM-Programme

(excluding CLLM-Project) is beyond the scope of commitment for counterpart funding made

by the GoM under CLLM-Project.

4.1.3 Financial Management

1. The project will be implemented by Meghalaya Basin Management Agency

(MBMA), a section 8 „not-for-profit Company‟6 incorporated in the Indian Companies Act

6 Incorporated in 2012

Page 47: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

41 | P a g e

2013 to develop integrated basin development plans and take measures for their

implementation in GoM. The institution functions through formal Board of Directors headed

by Chairman at the rank of Chief Secretary GoM and supported by Directors (Senior

Bureaucrats of GoM). MBMA is presently implementing a donor funded program of IFAD.

2. Under the administration of Project Director, a State level Project Management Unit

(SPMU) and District level Project Management Unit (DPMU) has been established in

MBMA. The SPMU will have the overall responsibility of maintaining the financial

management system of the project and ensuring that these functions are carried out in

accordance with the project‟s legal agreements. These activities will include (a) adequate

annual budgetary provision and effective utilization; (b) sufficient and timely flow of funds

for project activities, including for community-led program; (c) maintenance of adequate and

competent financial management staff; (d) appropriate accounting of project expenditures; (e)

oversight on project funds spent by Village NRM Council (VPMU) per MoU/Performance

Agreement; (f) control over assets created under the project; (g) preparation and timely

submission of interim financial reports; and (h) timely submission of audit reports and project

financial statements to the World Bank. The following arrangements will govern the Project‟s

financial management:

Budget and Counterpart financing: The World Bank funds (not exceeding 80% of project

cost) will be provided to GoI under IBRD loan terms and it will be released by Government

of India (GoI) to Government of Meghalaya (GoM) as per agreed financing norms between

Centre and the State (i.e. 90% as Grant and 10% as Loan). The GoM will provide 100%

funding (Central and State share) for the Project in the yearly State budget at the beginning of

each financial year based on the budget estimates (AWP) provided by MBMA. It is proposed

that a revolving advance is received from the Funding Agency. This means that first an

advance is given by the funding agency and as it is utilised on submission of the claims to

CAAA the advance amount is restored back. In both the above cases, after submission of the

claim to CAAA, the amount is credited by the Funding Agency to the Designated Account

maintained by GOI. GOI on receipt of the said amount transfers the same to State

Government which in turn transfers the same under Sanction Order to the agency

implementing it. In the sanction order the source and purpose of funds is mentioned. State

share for the entire year will be transferred at the beginning of the year as per the provisions

made in the State Budget book.

The budget utilization will be monitored by finance department of GoM and any additional

demand for the budget during the financial year will be met through a provision by way of

supplementary demand in the month of September. GoM has opened a separate budget head

for the project in the State budget and a budget provision has been made to finance project

activities of FY 2017-18.

3. Fund Flow (GoM to MBMA): MBMA will open a separate bank account for the project.

MBMA will receive sanction order from GoM after the annual budget is approved by GoM to

draw funds from the budget into the project bank account. The payments will be made by

MBMA for the following key project activities: (i) Release of grant funds to Village CNRM

Committee under component 2 of the project as per terms and conditions stipulated in the

MoU/Performance Agreement between MBMA and participating Village CNRM

Committees; and (ii) Goods, Consulting, Non-Consulting, Training and program management

costs under component 1 and 3 of the project. The interest earned by MBMA shall be

managed as per norms of GoM.

Page 48: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

42 | P a g e

4. Fund Flow and financial monitoring for Community led activities: The DPMU and

participating Village CNRM Committees will open a separate bank account to receive funds

under the project. Annual Work Plan (AWP) will be prepared by Village CNRM Committee

with the support of DPMU which will be approved by a District Committee headed by the

Deputy Commissioner of the District.. The Block Project Managements (BPMU), District

Project Management Units (DPMU) and SPMU will also prepare their supplementary

budgets for managing, supporting and supervision CLLMP which will be approved by the

immediate higher level. The funds will be transferred from MBMA bank account into the

bank account of DPMU which in turn will transfer the funds to participating Village CNRM

Committees and BPMUs. The withdrawal of funds will be made by Village CNRM

Committee for the activities specified in the MoU/Performance agreement. There would be a

proper segregation of duties on the financial management functions relating to procurement,

payment and accounting among the elected members of Village CNRM Committee. Village

CNRM Committee will maintain cash book/register and supporting documents for the

payment made from the bank account. Such financial records will be kept for subsequent

audit and verification. VPMU will submit utilization certificate within one month from end of

each half year ending September 30 and March 31 to DPMU which will be endorsed by

Deputy Commissioner and subsequently be forwarded to MBMA. The monitoring on end use

of funds and compliance with the terms and conditions of the MoU/ Performance Agreement

will continue to be undertaken by MBMA with the support of DPMU on an ongoing basis. A

community implementation manual is being developed which will govern the operating

procedures on use and monitoring of grant funds.

5. Finance staff and training: The finance wing of MBMA is presently headed by OSD

finance and supported by accounting professionals specifically recruited by MBMA for IFAD

project. It has been agreed with MBMA that requisite finance staff will be hired at SPMU

and DPMU to manage accounting and financial reporting functions of the Project. Provision

for staff costs have been made in the Project budget. Sufficient training will be provided to

the finance staff on financial management, World Bank disbursement policies and procedures

and use of client connection website.

6. Accounting: MBMA has beenmaintaining books of accounts in a computerized

accounting system since April 2016 and it has a financial management manual to guide the

staff on accounting and internal control principles. The accounting system will be used for

the project and chart of accounts will be appropriately developed to classify project

expenditures based on project components/major activities.

7. Financial reporting: The reporting framework for the Project will consist of an Interim

Financial Report (IFR). The format of IFR is attached to the Disbursement Letter. It will

provide information on the sources and uses of funds according to disbursement categories

and project components (component 1, 2 and 3). The IFR will be prepared by MBMA from

its underlying accounting records, ledger accounts and expenditure statements generated from

the accounting system. The IFR will be submitted by MBMA to World Bank through

Controller of Aid, Accounts and Audit (CAAA) within 45 days from the end of each calendar

semester. To maintain cash flow of the project, MBMA is allowed to submit out of turn IFRs

as and when substantial expenditures are incurred under the project. The IFR will form the

basis of disbursement from World Bank to GoI and GoM.

Page 49: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

43 | P a g e

8. Expenditure Eligible for Disbursement

Component Eligible Expenditure Conditions for Eligibility of World Bank Disbursement

Component 2 of the

Project

Funds to VPMU will be released in two

tranches. MBMA will release funds to

DPMU which in turn will transfer the

funds to VPMUs for community led

activities. The funds transferred by

DPMU to VPMUs will be reported in

the IFR as eligible expenditure.

Monitoring the end use of funds and

compliance with the terms and

conditions of the MoU/ Performance

Agreement will be undertaken by

MBMA with the support of DPMU on an

ongoing basis.

First Tranche: MoU/Performance Agreement defining terms and

conditions of community led activities will be signed between MBMA and

each participating VPMU to govern the use of funds. The project activities

undertaken shall be distinct, identifiable and results are measurable.

Subsequent Tranche: It will be paid upon fulfilment of conditions and

payment schedule specified in the MoU/Performance Agreement verified

by MBMA with the support of DPMU.

FM aspects to be considered:

(i) DPMU and VPMU will open separate bank account to receive

funds under the project.

(ii) Annual Work Plan (AWP) will be prepared by VPMU with the

support of DPMU which will be approved by Deputy

Commissioner of the District and subsequently by MBMA.

DPMU and Deputy Commissioner at the Districts will ensure

that activities included in the AWP do not include any activities

that is presently financed or will be financed during the project

period from any other Centre and State level scheme.

(iii) MBMA will transfer the funds directly from its bank account

into the bank account of DPMU which in turn will transfer the

funds into the Bank account of VPMU.

(iv) Proper segregation of duties (i.e. procurement, payment and

accounting) among the elected members of VPMU.

(v) Payment will be made by VPMU only for the activities specified

Page 50: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

44 | P a g e

Component Eligible Expenditure Conditions for Eligibility of World Bank Disbursement

in AWP.

(vi) VPMU will maintain cash book/register and supporting

documents to record financial transactions. Such records will be

kept for audit and verification.

(vii) Utilization certificate on the use of funds will be submitted by

VPMU to DPMU every six months which will be forwarded to

MBMA.

(viii) MBMA will record names of DPMUs in its accounting system

under respective account codes pre-defined for the Project.

(ix) MBMA will maintain disbursement records for each

disbursement made to VPMU through DPMU and UCs received

from VPMU.

(x) MBMA will provide a complete list of DPMU and VPMU

which have availed Grants under the project in the IFR.

Component

1 and 3 of

the Project

Expenditure incurred and paid on

activities relating to procurement

of Goods, Training, and

Consulting/Non-Consulting and

program management costs.

Expenditure should be duly approved as per MBMA delegation of

authority, evidenced by supporting documentation, be incurred for

the Project, and should be recorded in the Accounting System under

account codes pre-defined for the Project. The expenses should not

have been claimed from any other sources.

Page 51: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

45 | P a g e

9. Internal Audit. MBMA will hire full time audit officers in SPMU to carry out internal

audit of the Project. Adequate provision for the staff costs has been made in the Project

budget. The internal audit will focus mainly on (i) quality of maintenance of financial records

at VPMUs; (ii) payment, financial reporting and procurement functions at VPMUs; and, (iii)

disbursement and reconciliation functions at SPMU, DPMU and VPMUs for the community

led activities. The selection of VPMUs will be carried in such a manner that all VPMUs are

covered for internal audit during the lifetime of the project. The audit reports along with the

corrective actions taken by the project to address control weaknesses will be shared with the

World Bank.

10. External audit. The statutory audit of MBMA as per the India Companies Act is

presently conducted by an external audit firm appointed by the Comptroller and Auditor

General of India (CAG). To obtain fiduciary assurance for this project, it has been agreed

with MBMA that entity audit will also cover project transactions and a separate schedule

reporting financial activities of the project will be provided along with entity audit report and

financial statements. The entity audit report will be shared with the World Bank within nine

months from the end of each fiscal year.

Implementing

Agency

Audit Report Auditor Due Date

MBMA Entity Audit report

(providing financial

information on use of

project funds as a

separate schedule).

Private

Auditor

December 31

of each year

11. Retroactive financing: Payments made by MBMA during the one-year period prior to

the signing of legal agreements for contracts awarded following World Bank procurement

procedures will be eligible for retroactive financing. The limit for retroactive financing is

USD……. million. The MBMA will submit a separate interim financial report to claim such

expenditures.

12. Public disclosure. Annual audit reports and project financial statements will be disclosed

by MBMA on its official website.

13. Supervision plan: The financial management risk of the Project is ‘Substantial’, given

the innovative nature of project design, providing Grants to communities for implementation

of activities and the fact this is the first World Bank-financed project to be directly

implemented by the state government. The assessments indicate that MBMA require

extensive support on Bank‟s financial management and disbursement processes/procedures.

To support project implementation, essential FM capacity is provided through preparation of

community operations manual, training/capacity building to VPMU and by contracting

professionals for project accounting and internal audit. A computerized accounting system

will be used by MBMA for project accounting and timely submission of financial reports.

The oversight arrangements of internal and external audits will provide reasonable assurance

on use of project funds. During the first year of project implementation, the Bank will

undertake semi-annual implementation support missions, including field visits to ensure that

agreed financial management arrangements are understood and appropriately followed by

MBMA. As implementation progresses; financial and audit reports will be reviewed. The

financial management arrangements proposed under this Project are considered to be

Page 52: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

46 | P a g e

adequate to account for and report on project expenditures, and satisfy the fiduciary

requirements of OP/BP 10.00.

14. Designated Account: Government of Meghalaya will maintain a Designated Account for

CLLMP. The MoF, GoI is responsible for foreign exchange risks and repayment of the

principal and interest on the loan to World Bank.

4.2 Procurement Management

a. General Procurement Objectives and Procedures

The objectives of procurement under the Project are to procure the

material/goods/services/works of the specified quality, at the most competitive prices

achieving value for money, in a fair, just and transparent manner; ensuring transparency, fair

and equitable treatment of bidders and consultants, promoting competition and enhancing

efficiency and economy in the procurement process; and ensuring highest standards of

transparency, accountability and probity in the public procurement process and enhancing

public confidence in public procurement.

Procurement for the Meghalaya CLLM-Project will be carried out in accordance with the

Bank‟s Procurement Regulations for Borrowers for Goods, Works, Non-Consulting and

Consulting Services dated July 1, 2016 and applicable to Investment Project Financing [IPF]

here in after referred to as „Regulations‟, and the provisions stipulated in the Legal

Agreements. The project will be subject to the Bank‟s Anticorruption Guidelines, dated July

1, 2016. The project will use the Bank‟s online tool STEP [Systematic Tracking of

Exchanges in Procurement] for procurement planning and implementation.

b. Specific Procurement Objectives

To achieve the PDO together with Value for Money [VfM], Transparency and Integrity

Ensuring timely and efficient availability of material/goods/works/non-consulting

services and consultants, and training, in line with the Procurement Plan [or the updated

Procurement Plan] within budget and on time, and in compliance with the Procurement

Regulation for IPF Borrowers of the World Bank

Effective contract management

Effective and efficient handling of procurement-related complaints

Disclosure of procurement information

c. Procurement Responsibility The project will be implemented by MBMA. The project envisages both centralized and

decentralized procurement which will primarily be carried out at 3 levels, namely, the State

[SPMU/MBMA] level, District [DPMU]level and Communityor Village [VNRMC] level;

and will cover procurement of goods, need based consultancy services for studies and

technical services, non-consulting services and minor civil works to be implemented in a

demand-driven manner by the communities.No procurement will be carried out at Block

level. Procurement for block offices will be undertaken by their respective districts.Materials

and labour,and village level service providers who will prepare CNRM plans will be procured

by the community organisations -VNRMC[Traditional Institutions/Executive Committee of

Village Council]in line with their approved CNRMP and following community procurement

Page 53: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

47 | P a g e

procedures as outlined in the Community Operations Manual [COM] applicable to the

project.

The Procurement Cell will be housed within the SPMU of the MBMA, and will be headed by

the DeputyProject Director [Administration] reporting to two Additional Project Directors,

one each for East [Khasi and Jaintia Hills] and West [Garo Hills], who in turn will report to

the Project Director, SPMU.The Procurement Cell will comprise of a Manager [Procurement]

hired from the market and with prior experience in Bank‟s procurement proceduresand a

Multi-tasking Assistant. It will be responsible for day-to-day procurement functions

[procurement planning and monitoring, coordination with decentralized procuring entities at

various levels and with technical cells, reporting and coordinating with the Bank, responsible

for implementation of procurement risk mitigation plan, procurement capacity building under

the Project, etc.]. The Deputy Project Director [Administration] will be responsible for

providing guidance and direction to the Procurement Cell and ensuring that all procurement

under the project is carried out as per agreed procedures applicable to the project.

d. Procurement Capacity The staff in MBMA identified to handle procurement under the project have received training

in procurement procedures in Bank financed projects, and in using STEP. Additionally, the

project is supported by a Manager [Procurement]who is well versedin Bank procurement

procedures.MBMA, with Bank support as needed, will ensure that all staff handling

procurement at all levels are adequately trained in Bank procurement procedures. Contract

management training will also be provided by MBMA with Bank support, upon project

implementation.

e. Procurement Manual Procurement Manual of CLLMP will be prepared. It is intended to guide all entities

involved in procurement and community institutions to understand the procedures to be

followed for procurement under the Project. In addition, a separate and simplified

procurement chapter of the Community Operations Manual would also be prepared for

effective and efficient procurement at the community level, in line with the principles of

community procurement. Value thresholds for community will be mentioned in the CLLMP

Procurement Manual.

f. Community Operations Manual The Procurement Section of the Community Operations Manual prepared by MBMA and

updated from time to time will describe the roles and responsibilities, and procurement

arrangements under the CLLM-Project, and serve as a guide and tool for procurement

functionaries for procurement implementation and contract management under the Project.

g. E-procurement using Portal hosted by NIC

Use of e-Procurement using the NIC Portal will be appropriately introduced in line with GO

FEG.25/2014 dated February 7, 2014 issued by the Finance Department of the Government

of Meghalaya, to bring in greater transparency in the procurement process, as and when the

project and field staff receives training and become comfortable with the system.

h. Procurement Complaint Handling Mechanism

Page 54: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

48 | P a g e

A procurement complaint handling mechanism to address any procurement related

complaints received by the project, will be developed and implemented by the SPMU

[MBMA] to the satisfaction of the Bank. Upon receipt of complaints, immediate action

would be initiated to acknowledge the complaint and to redress it within a reasonable

timeframe. All complaints will be addressed at levels higher than the level at which the

procurement process was undertaken or the decision was taken. Any complaint received will

also be forwarded to the Bank for information, and the Bank would be kept informed after the

complaint is redressed.

i. Procurement Limits, Thresholds and Review Arrangements

The project is to be implemented by MBMA, districts, block and village level authorities.

However, no procurement will be carried out at Block level. Procurement for block offices

will be undertaken by their respective districts.The procurement thresholds and review

arrangements will be followed as below:

Procurement Approaches and Methods Thresholds [US$ equivalent]

Open International [Goods, IT and non-

consulting services]

>3 Million

Open National [Goods, IT and Non-consulting

Services]

> 100,000 and up to 3 Million

National Request For Quotation [Goods/Works] Up to 100,000

Open International [Works] > 40 Million

Open National [Works] > 100,000 and up to 40 Million

Direct Selection No threshold.

For Goods/Works/Non Consulting

Services : As per paragraphs 6.8-6.10 of

Regulation.

For Consultants: As per paragraphs 7.13-

7.15 of Regulation.

Framework Agreement For Goods/Works/Non Consulting

Services : As per paragraphs 6.57-6.59 of

Regulation.

For Consultants : As per paragraph 7.33

of Regulation.

Shortlist of National Consultants Up to 800,000

All major procurement which is not covered under shopping [RFQ] method will be

centralized at SPMU [MBMA] level and follow the prior and post review arrangement of the

Bank as mentioned in below table. The Districts will be procuring the routine goods and

equipment within the value thresholds up-to INR 32.50 Lakhs [about USD 50,000 at 1USD =

65 INR] at their level, and any procurement above this threshold and below the Bank‟s prior

review threshold will be prior reviewed by MBMA at state level.

Review Arrangements by the Bank

Page 55: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

49 | P a g e

Procurement Category Review Thresholds [US$ equivalent]

Works Above US $10 million

Goods and Non-Consulting Services: Above US $2 million

Consultancy services [Firms] Above US $1 million

Consultancy Services [Individual Consultants] Above US $0.3 million

All other contracts which are not covered under prior review by the Bank will be subject to

post review during implementation support missions and/or special post review missions,

including missions by consultants hired by the Bank.Even in post review cases, the inputs of

Bank on Technical Specifications/TORs will be obtained by the Project.

Review Arrangements by MBMA SPMU will establish internal prior review thresholds that will be reflected in the Procurement

Manual for the Project and the Procurement chapter of the Community Operations Manual

prepared by MBMA. Additionally, the terms of reference for internal auditors [Individual

Consultants] hired by the SPMU for conducting the financial audit will include adequate

requirement to cover review of compliance of agreed procurement procedures during project

implementation. The TOR for procurement audit by MBMA will be cleared by the Bank.

j. Record Keeping

All records pertaining to award of tenders/selection of consultants, including tender

notification/advertisement, register pertaining to sale and receipt of bids, bid/proposal

opening minutes, bid/technical and financial evaluation reports and all correspondence

pertaining to bid evaluation, communication sent to/with the Bank in the process, bid

securities, and approval of invitation/evaluation of bids/proposals would be maintained and

kept for post review by the Project.

k. Disclosure of Procurement Plan The project will use the Bank‟s online procurement planning, tracking and monitoring tool,

Systematic Tracking of Exchanges in Procurement. The Procurement Plan and it‟s updates,

as approvedby the Bank in STEP will be disclosed on the Bank‟s external website, the project

website and shared with District and sub-district level implementing agencies.

l. Disclosure of Procurement Information

The following documents shall be disclosed on the Project website: [i] procurement

plan and updates, [ii] Specific Procurement Notice for procurement of goods, non-

consulting services and works for opencompetitive procurement [iii] Request for

Expressions of Interest for selection/hiring of consulting services, [iv]list of contracts

awarded, [v] shortlist of consultants.

For all prior review procurement, following details shall be sent to the Bank through

STEP for publishing in the UNDB and World Bank external website: [i] Procurement

Notices for procurement of goods, non-consulting services and works using

international/nationalopen market approach [ii] request for Expressions of Interest for

consulting services (iii)contract award details of all procurement of goods and works

using international/nationalopen competitive procurement, [iv] contract award details of

all consultancy services and [v] list of contracts/purchase orders placed following

Page 56: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

50 | P a g e

Direct Selection or CQS procedures on a quarterly basis. In addition, implementing

agency will also publish on its website any information required under the provisions of

“suomotu” disclosure as specified by India‟s Right to Information Act.

4.2 Financial and Technical Safeguards and Reporting

The financial and procurement aspect of the Project will be included in the following

technical, fiduciary and safeguards documents:-

1) Determination of fund flow system to various communities involved in the project

2) Depending on the sub-components, plan of action for movement of funds and

procurement of goods

3) Procurement plan involving community participation and community procurement

4) Financial Manual on the practical recording of the transactions of the project

5) Form and format of annual and quarterly work plan, budget and procurement plans

6) Introduction of computerized system of accounting and reporting

7) Procurement Manuals for procurement transactions, Community Operations Manual

and others for various community participation.

The safeguard contained in above documents will be adhered to ensure efficient financial and

procurement and risk management.

Evaluation of the documents and actual work done at specified time intervals, milestones and

recasting will be followed to implement and achieve the above. The Evaluation and

monitoring will be done jointly with the M&E Team. Supervision of the activities undertaken

in terms of financial progress made or to be done has to be done both through accounting

software and internal control measures like real time reporting.

Page 57: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

51 | P a g e

5.1 Economic analysis Data and prices: For the economic analysis, economic prices have been calculated using

standard conversion factors for exported agricultural commodities and imported inputs in

order to correct distortions due to taxation, public subsidies and other market imperfections.

For non-exported / imported traded commodities local prices have been taken. The

economic cost of labour has been assumed to be equal to minimum wage rate approved by

the Government of Meghalaya at Rs. 189 for unskilled labour at which the labour is also

available for all government sponsored schemes which accounts for opportunity cost of

unemployment.

As most of the commodities produced in Meghalaya are consumed within the country

average national prices for last five years have been taken to overcome any distortion due to

subsidies available to NE states. For calculation of ENPV the discount rate of 6% as

recommended by the World Bank7 is used which is also average rate of growth of GDP in

India.

Economic cost. Beneficiaries‟ contributions are considered and any grant for landscape

based activities such as forestry, agriculture, water management are deducted. The non-

recurring investment cost in the project is 82.62% of the investment cost in component 1 and

2 i.e. USD 49.57 Million. Non-recurring investment in horticulture and forestry to be made

by the beneficiary from their own sources will be USD 1.32 Million. Recurrent investment in

on component 3 of the project will be USD 7.57 million. The phasing of the project cost is

assumed according to the COSTAB, between year one and five.

Economic benefits: The economic benefits including in the project economic analysis are:

(i) economic benefits related to improving crop productivity by 10%. (ii) Improved cropping

intensity by 120% due to improved water regime against the current state average of 105.1%

and national average of 135% cropping intensity. The horticulture productivity is also

estimate to increase by 10%. This is captured by the incremental net benefits of crop models

calculated in the financial analysis but valued at economic cost. (iii) Economic benefits from

conversion of 15% open forests in villages with 10% crown density to 40% crown density;

and (iv) economic benefits related to conversion of 20% of culturalable wasteland in villages

into agro-forestry and 10% culturable wasteland into horticulture with improved package of

agronomic practices. For estimating benefits from forestry very conservative approach is

adopted with incremental bio-mass of 6 MT/ha/year where as studies conducted by North

Eastern Hill University have estimated production of 260 MT over a period of 10 years in Sal

forests i.e. average productivity of 26 MT/ ha/year.

Economic benefits stemming from project’s GHG mitigation and carbon sequestration

potential: The GHG emission mitigation potential and carbon sequestration potential for a

range of project activities was calculated as 6611853tonnes of tCO2e. with the tool Ex-Ante

Carbon-balance Tool (EX-ACT) The resulting net carbon balance is 6,176,942 tonnes of

tCO2e over 20 years, implying that the project constitutes a sizeable carbon sink, in particular

as a consequence of introducing agro-forestry and forest plantations on currently degraded

land. A recent World Bank guideline suggests to value carbon emission in the economic

analysis at a shadow price of carbon, or social cost of carbon (SCC), which presents the

marginal damage cost of carbon emission. This value will be used for sensitivity analysis.

7 Technical Note on Discounting Costs and Benefits in Economic Analysis of World Bank Projects (World Bank, 2015)

Page 58: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

52 | P a g e

For the base scenario a conservative approach is used, considering that not all these avoided

damages accrue as benefit to the country, and a social value reflecting an approximate market

value of US$5 per tCO2e emission is used.8 The annual value of the net carbon balanced will

be valued from year 3 onwards.

Economic benefits stemming from soil and water conservation measures: To reduce soil

erosion and conservation of in-situ water various measures are proposed. Meghalaya is

prone to very heavy intensity rains. Mausengram and Cherapunji get highest rainfall in the

world. Heavy rainfall results in high soil erosion, leaching of nutrients and loss of agriculture

productivity. Measure for soil and water conservation will help in avoiding such economic

and environmental losses.

Time period: The economic analysis was conducted over a 10-year period reflecting the full

lifetime of most of the costs and benefits. Only the benefits stemming from forestry

production could occur over a longer period of time since forest trees can remain productive

up to 50.

Results and sensitivity analysis

Results: Based on the above assumptions, the economic analysis of the project yield an

Economic NPV (ENPV) of benefits of US$29.47 million and an Economic Internal Rate of

Return of 26.42percent. The results may be underestimates as several potential project

benefits have not been quantified. These relate in particular to environmental benefits related

to conservation, maintained biodiversity, ecological functions and related values of

maintained forest resources and improved watershed management, increased on-site

productivity due to improved soil conditions, decreased variability and vulnerability due to

adverse weather events in agricultural production, increased availability and production of

forest and agro-forestry products, increased food security and nutrition benefits and reduced

maintenance cost and restoration cost due to reduced sedimentation of manmade water

bodies.

Sensitivity analysis (Table below) demonstrates that the results are robust against changes to

key variables.

Change in

project cost

Change in project

benefit

ENPV @ 6%

discounting (UDS.

Million

EIRR

(USD

Million)

0 0 29.47 26.42%

+5% 0 24.69 21.53%

+10% 0 22.16 19.32%

+5% -5% 20.08 19.10%

+10% -10% 14.37 14.69%

Page 59: PROJECT IMPLEMETATION PLAN Meghalaya Community Led ... · GIMGreen India Mission, one of the eight missions of the NAPCC ... GoI Government of India Govt. Government IBDLP Integrated

53 | P a g e