Project Location: El Chaguite, Yoro District, Honduras
Northeastern University’s Student Chapter
1Project: El Chaguite Water System
Project: El Chaguite Water System 2
Project: El Chaguite Water System 3
Project: El Chaguite Water System 4
Guides
Project: El Chaguite Water System 5
El Tecuan
Project: El Chaguite Water System 6
Los Planes
Project: El Chaguite Water System 7
Project Schedule
Project: El Chaguite Water System 8
Dates of Travel Purpose Description
December 2007 Los Planes Implementation & El Chaguite Assessment
Complete Transmission Main in Los Planes, Visit El Chaguite
April – May 2008 El Chaguite Assess. Water Quality, Hydraulic Investigations, Existing System Inspections, Topographic Survey, Health Survey
December 14- December 29, 2008
El Chaguite Phase 1 Implementation
Construct Transmission Main/ Begin Distribution System
April – May 2010(proposed)
El Chaguite Phase 2 Implementation
Storage Tank/ Finish Distribution System
El Chaguite Existing System
9Project: El Chaguite Water System
Existing Conditions
Project: El Chaguite Water System 10
• Sufficient, clean water source• Limited service• Unusable distribution system• Damaged main line• Diverse topography• Hurricane damage• Fire damage
11Project: El Chaguite Water System
Current and Future Conditions
Project: El Chaguite Water System 12
Chaguite now: Chaguite in 25 years:
60 homes 87 homes
333 people 483 people
68 students 99 students
Conditions now: Conditions in 25 years
Total Average Available Flow (GPD)
22,349Total Average Available Flow (GPD)
22,349
Total Average Demand for People (GPD)
8,797Total Average Demand for People (GPD)
12,755
Total Average Demand for Irrigation (GPD)
3,000Total Average Demand for Irrigation (GPD)
4,350
Total Demand (GPD) 11,797 Total Demand (GPD) 17,105
Design Details
• Feasibility
• Transmission Main
• Distribution Network
• Float Valve Tank
• Sustainability
Project: El Chaguite Water System 13
El ChaguitePopulation: 333 people
Project: El Chaguite Water System 14
Overall Feasibility
Project: El Chaguite Water System 15
• Water Source : 15.52 gpm (22,348 gallons/day)
• 25 year projected demand: 12,755 gpd
+4,350 gpd (Irrigation use)
17,105 gpd• Diurnal Demand Cycle
• Conclusion: Feasible with water storage tank
Design Process
Project: El Chaguite Water System 16
• Excel water flow model• WaterGEMS flow model• Multi-phase implementation
• Phase 1 (COMPLETE)– Construct Transmission Main– Instruct villagers on
construction of distribution system
– Build break pressure tank (float-valve tank)
• Phase 2– Water storage tank– Inspect village-constructed
distribution system
Transmission Main
Project: El Chaguite Water System 17
SourceProposed Tank Site
Existing Tank Site
Transmission Main
Project: El Chaguite Water System 18
Float Valve Tank
Project: El Chaguite Water System 19
Alternatives Considered
Project: El Chaguite Water System 20
North Water Storage Tank East Water Storage Tank
Distribution System Model
Project: El Chaguite Water System 21
El Chaguite
Project: El Chaguite Water System 22
Transmission Main
Project: El Chaguite Water System 23
Trench Detail
Project: El Chaguite Water System 24
Trench Examples
Project: El Chaguite Water System 25
Tank Design
Trip Schedule
Project: El Chaguite Water System 27
Jun-11Fly to San Pedro SulaGet Supplies Order MaterialsVisit Rigo
Jun-12Buy GroceriesOrder Rest of SuppliesResearch Pumps for Carrizalito Project
Jun-13Drive To RosarioMeet with Village and Present DesignLay out Tank Site
Jun-14Dig Tank SiteTransport Bricks, Cement, Rebar, etc.
Jun-15 Train Villagers our process for concreteJun-16 Layout casting of FoundationJun-17 Cast Foundation
Jun-18Inspect Distribution System - Day 1Install Services - Day 1
Jun-19Start Walls of TankInspect Distribution System - Day 2Install Services - Day 2
Jun-20Visit Los PlanesVisit El Tecuan
Jun-21Survey CarrizalitoTake a trip to Yoro
Jun-22Cut GI pipe for tankVisit El Rosario School
Jun-23 Visit El Chaguite SchoolJun-24 Final Meeting With El ChaguiteJun-25 Drive to San Pedro SulaJun-26 Fly back to Boston
Budget
Project: El Chaguite Water System 28
El Chaguite Phase 2 Estimated Budget
Travel
Airfare $ 4,800
Exit Fees $ 210
Truck Rental $ 1,300
Gas $ 120
GroundHotel $ 300
Food $ 600
Labor
Guides $ 240
Laundress $ 100
Cooks $ 240
Materials
PVC Fittings/Valves $ 180
GI Pipes & Fittings $ 281
Tools $ 164
Tank Materials $ 1,365
Contingency $ 928
Total $ 10,827
Building Materials
Project: El Chaguite Water System 29
Sustainability• Extra materials supplied for maintenance and replacement.
• Locals will be educated on water conservation and proper system maintenance.
• Water Board willcollect usage tax to fund future repairs.
• Simple design and construction
Project: El Chaguite Water System 30
Community Ownership & Education
Project: El Chaguite Water System 31
• What kind of help will the community be providing?– Labor (digging trench, laying pipe, mixing cement, transporting
materials).– We will coordinate a schedule of construction with El Chaguite’s
Water Board.
• Who will own the project once it’s completed? – El Chaguite will own the water system upon completion of the
project. The El Chaguite Water Board will manage the communally used infrastructure.
Community Ownership & Education
Project: El Chaguite Water System 32
• Who will be overseeing maintenance once the team leaves and how will repairs be paid for?– El Chaguite’s Water Board will be overseeing the maintenance
of the system. We will leave extra materials with the villagers to take care of any immediate necessary repairs. Hopefully, with improved health, the villagers will be able to establish community funds and pay for repairs further in the future.
• What education will be provided to the community?– The community will be educated on the maintenance of the
system, and we also plan to provide information about health and sanitation. In order for this to be a successful effort we will be working with the community Water Board and local organizations to ensure that the people understand the situation and are well informed about health and sanitation issues.
Project Lead Sign-Off
Project: El Chaguite Water System 33
• I, Daniel P. Saulnier, P.E., as the Professional Mentor of this project, have reviewed the technical and logistical contents of this project, and approve of the proposed design. I will also comply with TAC recommended changes and make suggested changes before traveling on the implementation trip.
• Daniel P. Saulnier October 8, 2008 [signed]
Questions?
Project: El Chaguite Water System 34
Thank you for your attention. This slide
concludes our formal presentation.