project management c53pm

29
1 Project Management C53PM Session 8 Russell Taylor Lecturer in Computing & Business Studies E-mail: [email protected]

Upload: cleo

Post on 22-Jan-2016

32 views

Category:

Documents


0 download

DESCRIPTION

Session 8 Russell Taylor Lecturer in Computing & Business Studies E-mail: [email protected]. Project Management C53PM. Session 8. Project Monitoring & Control Chapter 8 Earned Value Analysis Exam question. Summary - Session 8. Difference between monitoring and control - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Project  Management  C53PM

1

Project Management C53PM

Session 8

Russell TaylorLecturer in Computing & Business Studies

E-mail: [email protected]

Page 2: Project  Management  C53PM

Business Department 2

Session 8

• Project Monitoring & Control– Chapter 8

• Earned Value Analysis– Exam question

Page 3: Project  Management  C53PM

Business Department 3

Summary - Session 8

• Difference between monitoring and control

• Discussed processes for change management

• Considered appropriate project control systems

• Discussed two different methods of project control

– Milestone & EVA

• Identified three most important variables to measure in project control

– ACWP, BCWP & BCWS

• Explained EVA spreadsheet

Page 4: Project  Management  C53PM

Business Department 4

Major Budgeting Processes

1. Resource Planning– People, Equipment, Materials, Overheads

2. Cost Estimating– Developing approximate cost for each

resource

3. Cost Budgeting– Relating cost estimates to schedule

– Producing time-phased cost & cash-flow predictions

4. Cost Control– Controlling cost in relation to project schedule

Page 5: Project  Management  C53PM

Business Department 5

Project Monitoring & Control

• Monitoring– Comparison of actual costs & schedule with planned cost & schedule.

• Control– Setting control limits– Deviation outside limits– Corrective action

• Effectiveness of project control systems– Response time– Traceability

Page 6: Project  Management  C53PM

Business Department 6

Project Monitoring & Control Systems

• What control measures to select

• What data to collect to estimate the current value of each control measure

• How to collect the data

• What analysis to perform on data collected to detect deviations

• Who needs it, in what format and how often

Page 7: Project  Management  C53PM

Business Department 7

Project monitoring & control Areas

• Critical tasks not started or finished on time– Schedule

• Non-critical tasks becoming critical– Schedule

• Milestones / key dates missed– Schedule

• Price changes, cost over-runs, cash flows– Costs

Page 8: Project  Management  C53PM

Business Department 8

Project monitoring & control Areas

• Long supply lead times – Resources, Schedule

• Resource availability problems– Resources, Schedule, Costs,

• Insufficient technical information – Resources, Schedule, Costs,

• Changes in project scope– Performance, Resources, Schedule, Costs,

Page 9: Project  Management  C53PM

Business Department 9

Typical types of change

• Scope creep

• Increase level of effort

• Quality creep

• New technologies or tools

• Personnel changes

• Schedule improvement

• Client discretion

Page 10: Project  Management  C53PM

Business Department 10

Change Management

1. Identify the change

2. Analyse the effects of change

3. Develop a response strategy

4. Communicate the strategy and gain endorsement for the change

5. Revise the work plan and monitor the effects of change

Page 11: Project  Management  C53PM

Business Department 11

Cost Control

• Two methods– Milestone Monitoring

– Earned Value Analysis

• Exam Question

Page 12: Project  Management  C53PM

Business Department 12

Milestone Monitoring

• A milestone is a key event in a project– Clear and well defined (Concrete)– Related to deliverables in the Gantt chart

• Milestones mark progress– Either achieved or not achieved – Have a target completion date– Have a budgeted cost

• Milestone monitoring– Simple & effective method– Plotted Deliverables on graph

Page 13: Project  Management  C53PM

Business Department 13

Figure 8.1: Milestone monitoring

0

50

100

150

200

250

0 10 20 30 40 50 60

Week No.

Cos

t/£ Planned budget

Actual cost

1.10 1.15 1.201.25 1.30 1.35

1.401.45 1.50

1.55 1.60

1.651.70

Milestone Monitoring

Page 14: Project  Management  C53PM

Business Department 14

Example

0

50

100

150

200

250

0 10 20 30 40Week No.

Co

st/£

Planned budget

Actual cost

1.10 1.15 1.201.25 1.30 1.35

1.401.45 1.50

1.55 1.60

Page 15: Project  Management  C53PM

Business Department 15

Earned Value Analysis (EVA)

• Earned Value Analysis (EVA)– also called Cost/Schedule Control System (C/SCS)

– or Baseline Performance Measurement (BPM)

– or Integrated Baseline Review (IBR)

• Comparison of the value actual work completed (earned value) against planned progress & actual expenditure of each activity

• Time-phased plan

Page 16: Project  Management  C53PM

Business Department 16

Earned Value Analysis (EVA)

• Actual cost of work performed (ACWP)– Actual costs incurred & recorded

– Progress reports

• Budget costs of work scheduled (BCWS)– The value of the work scheduled to be

accomplished at a given period in time.

• Budget cost of work performed (BCWP)– Earned Value (EV)

– Budgeted value of work completed to date

Page 17: Project  Management  C53PM

Business Department 17

BCWS & BCWP

Actual progress 70%

• Budget costs of work scheduled:BCWS = £1000,000 x 60% = £600,000

• Budget costs of work Performed: BCWP = £1000,000 x 70% = £700,000

Total Activity Budget = £1000,000

0 10 weeks6

Scheduled progress 60%

Page 18: Project  Management  C53PM

Business Department 18

Scheduled Variance

• Schedule variance (SV)– Indicates the difference between work content

performed and work content scheduled – Monitory units– Difference between BCWP and BCWS

• SV = BCWP – BCWS= £700,000 - £600,000= +£100,000

• Project ahead of schedule by £100,000 (1week)

Page 19: Project  Management  C53PM

Business Department 19

ACWP

Actual progress 70%

• Budget costs of work scheduled:BCWS = £1000,000 x 60% = £600,000

• Budget costs of work Performed: BCWP = £1000,000 x 70% = £700,000

Total Activity Budget = £1000,000

0 10 weeks6

Scheduled progress 60%ACWP = £750,000

Page 20: Project  Management  C53PM

Business Department 20

Cost Variance

• Cost variance (CV)– Identifies deviations in costs on work content

actually performed – Difference between BCWP and ACWP

• CV = BCWP – ACWP= £700,000 - £750,000= -£50,000

• Project has a cost overrun of £50,000

Page 21: Project  Management  C53PM

Business Department 21

CV & SV

Actual progress 70%

• SV = + £100,000• CV = - £50,000

Total Activity Budget = £1000,000

0 10 weeks6

Scheduled progress 60%ACWP = £750,000

Page 22: Project  Management  C53PM

Business Department 22

Performance Indices

• Schedule Variance (SV) & Cost Variance (CV) – Absolute measures in monitory units

• Schedule Performance Index (SPI)

• Cost Performance Index (CPI)

Page 23: Project  Management  C53PM

Business Department 23

Schedule Performance Index (SPI)

• SPI value = 1 indicates activity is on schedule

• SPI value >1 indicates activity ahead of schedule

• SPI value <1 indicates schedule overrun

SPI =BCWPBCWS

SPI =£700,000£600,000

= +1.16

• SPI defined as the ratio between BCWP & BCWS

Page 24: Project  Management  C53PM

Business Department 24

Cost Performance Index (CPI)

• CPI value = 1 indicates activity is on budget• CPI value > 1 indicates better than planned

cost performance• CPI value <1 indicates cost overrun

CPI =BCWPACWP

CPI =£700,000£750,000

= 0.93

• CPI defined as the ratio between BCWP & ACWP

Page 25: Project  Management  C53PM

Business Department 25

Earned Value Analysis

Actual progress 70%

• SV = + £100,000• CV = - £50,000• SPI = 1.16• CPI = 0.93

Total Activity Budget = £1000,000

0 10 weeks6

Scheduled progress 60%ACWP = £750,000

Page 26: Project  Management  C53PM

Business Department 26

Cost Estimate at Completion (EAC)

• Budget at Completion (BAC)– BAC = BCWS at completion = £1000,000

• Estimate at Completion (EAC)

EAC =BACCPI =

£1000,0000.93

= £1075,268

EAC = ACWP + (BAC – BCWP)

EAC = £750,000 + (£1000,000 - £700,000) = £1050,000

Page 27: Project  Management  C53PM

Business Department 27

Variance at Completion (EAC)

• Variance at Completion (VAC)– VAC = BAC - EAC

– VAC = £1000,000 - £1075,286

= -(£75,286)– VAC = £1000,000 - £1050,000

= -(£50,000)

Page 28: Project  Management  C53PM

Business Department 28

Schedule at completion

• Schedule at Completion (SAC)

• Project will have a cost overrun of £75,286, but will finish 1.4 weeks ahead of scheduled

SAC =Original estimated duration

SPI

=10 weeks

1.16= 8.62 weeks

Page 29: Project  Management  C53PM

Business Department 29

Summary - Session 8

• Difference between monitoring and control

• Discussed processes for change management

• Considered appropriate project control systems

• Discussed two different methods of project control

– Milestone & EVA

• Identified three most important variables to measure in project control

– ACWP, BCWP & BCWS

• Explained EVA spreadsheet