ADM 217 PROJECT MANAGEMENT
ACKNOWLEDGEMENT
COLLEGE MCS 1
ADM 217 PROJECT MANAGEMENT
1.0 Acknowledgement
Bissmillahirrahmanirrahim.
Alhamdulillah. Thanks to Allah SWT, that with His willing gives us the opportunity to complete
this Final Assignment. This assignment was prepared for Computer Principles subject.
First and foremost, we would like to express our deepest thanks to our beloved lecturer and also
as guidance, Miss Faradila for the valuable guidance and advices. We also would like to thank
her for showing us some good example that related to the assignment.
Besides that, our deepest thanks and appreciation our parents, family, special mate of us, and
others for their cooperation, encouragement, constructive suggestion and full of support for the
assignment completion, from the beginning till the end. Also thanks to all of classmate, DITM
Group 4 and everyone, that has been contributed by supporting our work and helps us during the
assignment progress till it is fully completed.
Last but not least, our thanks to MCS College, for great facilities and accommodations that have
been provided. Without helps of the particular that mentioned above, we could face many
difficulties while doing this assignment.
COLLEGE MCS 2
ADM 217 PROJECT MANAGEMENT
INTRODUCTION
COLLEGE MCS 3
ADM 217 PROJECT MANAGEMENT
2.0 Introduction about company
Event Management Sdn Bhd
Company Name : EVENT MANAGEMENT SDN. BHD.
Address : An Event Management Sdn Bhd
No. 3, Jalan 14/53
46100 Petaling Jaya
Selangor Darul Ehsan, Malaysia
Fax. No. : 03-5353 3535
Website Address : http://www.an-event.com/
Email Address : [email protected]
COLLEGE MCS 4
ADM 217 PROJECT MANAGEMENT
2.1 Company Background
An Event Management Sdn Bhd was formed in July 1999 in Kuala Lumpur, Malaysia, with the
goal of organizing memorable events and help clients to effectively promote their messages.
With more than 10 years of collective working experience in the events, media, and advertising
industries, we set to design and organize events for our clients that help them achieve their
targets best.
An Event Management Sdn Bhd is a leading company in Malaysia, organizing quality, unique
and cost-effective events. With the constant introduction of new trends, the integrated events
solutions we provide, and the ability to operate in Malaysia and in many other countries, we
strive to provide our clients with the best service they can expect.
Our company has been given hired by the well known automotive company, Yamaha to conduct
motorcycle exhibition, to launch their new motorcycle Yamaha 135LC. With our experience in
the management event in few years, we sure can do our best to accomplish this task.
COLLEGE MCS 5
ADM 217 PROJECT MANAGEMENT
2.2 Project Title
My project is launching Yamaha 135LC Extreme Spirit
COLLEGE MCS 6
ADM 217 PROJECT MANAGEMENT
2.3 Project Venue
CONCORDE HOTEL SHAH ALAM
3 Jalan Tengku Ampuan Zabedah C9/C, 40100 Shah Alam, Selangor Darul Ehsan, Malaysia
We choose this place because that place is suitable and have many facilities, lower cost, and easy to get there.
COLLEGE MCS 7
ADM 217 PROJECT MANAGEMENT
2.3.1 How To Get There
COLLEGE MCS 8
ADM 217 PROJECT MANAGEMENT
2.4 Project Date
December 21rd, 2010
We have chosen this date for this event because it is holiday time
2.5 Project Cost
Our cost for this event is RM 50,000,that include :
Management hotel
Rental accommodation
Activities management
Set of eating and drinking
PA System
VIP and VVIP
Present
2.6 Objectives of this event
To introduce latest Yamaha product to market
To attract costumer
To increase the usage of Yamaha product
To support international Automotive
Give our customer know the new news about company
COLLEGE MCS 9
ADM 217 PROJECT MANAGEMENT
CONTENT
COLLEGE MCS 10
ADM 217 PROJECT MANAGEMENT
3.0 CONTENTS
3.1 Project Name Description
This report should briefly describe the whole project.
1. Why did you do this project?
a) Scope Our companies want give the best rating about motor to public
Focus to teenagers that like the new brand motor
To public that want save they petrol used
b) Objective To introduce latest Yamaha product to market
To attract costumer
To increase the usage of Yamaha product
c) Goals To increase people to use the Yamaha 135LC motor model
To make people understand the benefit use Yamaha Motor
COLLEGE MCS 11
ADM 217 PROJECT MANAGEMENT
2. What did you produce?
a) Service or product For this project, we use service to promote client new product to people.
b) Documentation / User Manual for use the product or service On this project, our client just listening from us about what kind of service we
use to promote their product and they suggest to us other alternatives. We use:
Banner Pamphlet Poster Media & Electronic
3. Was the project a success or not?a) Project status (success or not)
Yes, this project was successful
b) Give the reason why project status success or not. This project was successful because, all our team in this project give they best
service and support to make this project success and we also had sponsor that also support us.
COLLEGE MCS 12
ADM 217 PROJECT MANAGEMENT
4. What project management tools did you use, and did they help?
The project management we use in this project is Microsoft Project Gantt Chart, its
easy to use and better to manage our plan to make this event is up to date and success.
We also use other Microsoft tools like:
Microsoft Word 2007
Microsoft Excel 2007
Microsoft Power Point 2007
5. What went right on the project? The went right is the project has successful done on the date and and all plan is
working
6. What went wrong on the project? This project required many people to manage its and make all plan is working on
date.
Each of project member have to do more than one task to complete this event
7. What did you learn by working on this project? Our team project learn how to manage some project and cooperate with each other
We know, learn and improve our skill to use Gantt Chart Project 2007
We learn and know how to plan and manage some project
COLLEGE MCS 13
ADM 217 PROJECT MANAGEMENT
Schedule:
ACTIVITY START DATE END DATE DURATION(DAYS)
Make project team 4/10/2010 4/10/2010 1
Identify the event
launching
5/10/2010 6/10/2010
2
Specified event time 7/10/2010 8/10/2010 2
Survey the venue 11/10/2010 14/10/2010 4
Identify the budget 20/10/2010 21/10/2010 2
Booking venue 25/10/2010 26/10/2010 2
Planning to invite
sponsor and VIP
27/10/2010 29/10/2010
3
Plan the contest and
quiz
1/11/2010 2/11/2010
2
Discuss the schedule 3/11/2010 4/11/2010 2
Booking invitation
card, banner.
5/11/2010 8/10/2010
4
Promote the event 9/11/2010 12/11/2010 4
Discuss transportation 15/11/2010 15/11/2010 1
Identify hotel
accommodations
16/11/2010 17/11/2010
2
Plan the gift and
souvenir
18/11/2010 19/11/2010
2
Planning the tentative
program
22/11/2010 25/11/2010
4
Meet the hotel management
26/11/2010 26/11/2010 1
Preparation the event 6/12/2010 17/12/2010 12
Launching day 21/12/2010 21/12/2010 1
Sent report 28/12/2010 28/12/2010 1
COLLEGE MCS 14
ADM 217 PROJECT MANAGEMENT
3.2 Scope Statement
Prepared by: Norharyani Binti Mohd Solehudin.
Project Title: Yamaha 135LC Extreme SpiritDate: 21/12/2010
Project Justification:Our company an Event Management SDN BHD will be fully responbility to do motor show for
Yamaha to promote their new motorcycle. This event theme is Yamaha 135LC Extreme
Spirit,we choice it because its suitable with the new Yamaha motorcycle product.
Product Characteristics and Requirements:
Decoration place, food and stage.
Promotion.
Requirement material for motor show.
Media
Summary of Project Deliverables:
Project management-related deliverables:Business case, charter, team contract, scope statement, WBS, schedule, cost baseline, status
reports, final project presentation, final project report, lessons-learned report, and any other
documents required to manage the project.
Product-related deliverables:Research reports, design documents, software code, hardware, etc.
1. Microsoft Word
2. Microsoft Project
3. Microsoft Power Point
4. Microsoft Publisher
Project Success Criteria:With the good planning and strategies to do this event,we believe can do the best work and good
quality for our client.
COLLEGE MCS 15
ADM 217 PROJECT MANAGEMENT
3.3 Project Charter
Project Title : Yamaha 135LC Extreme Spirit
Project Start Date : 2010 Projected Finish Date : 21 DECEMBER 2010
Budget Information : RM 50, 000
Project Manager : Juladi Bin Murkim.
Project Objectives :
To introduce latest Yamaha product to market
To attract costumer
To increase the usage of Yamaha product
To support international Automotive
Give our customer know the new news about company
Approach:
…………………………..(JULADI BIN MURKIM)
PROJECT MANAGER
COLLEGE MCS 16
ADM 217 PROJECT MANAGEMENT
Roles and responsibilities
Name Position Role Contact No.
JULADI BIN
MURKIM
PROJECT
MANAGER
Leader for project and event, ensure the program run successfully.
019-8735264
NOOR NADIATUL
HUSNA BINTI
MOHD HALIL
ASSISTANT
PROJECT
MANAGER
Help the leader for project, and deal with any problem 013-2369571
NORHARYANI
BINTI MOHD
SOLEHUDIN
FINANCIAL
MANAGER
Manage account and
budget for the event 012-9256105
MUHD AMIRUL
BIN AHMAD
SAKRANI
PROTOCOL
BUREAU
Service and booking
place 017-6547238
MUHSIN BIN
BAHARUDIN
PROMOTION
BUREAU
Survey and give
present
012-6732821
MUHD ASYRAF LOGISTIC BUREAU
Furniture for event,
manage food and
equipments
016-3482489
MUHD YAZID OPERATIONAL
MANAGER
Prepared agenda and
letters 014-2358910
Sign-off : (Signature of all above stakeholders. Can sign by their names in table above.)
Comments : (Handwritten or typed comments from above stakeholders, if applicable.)
COLLEGE MCS 17
Assistant Project ManagerNoor Nadiatul Husna Binti
Mohd Halil
Project ManagerJuladi Bin Murkim
Protocol BureauMuhd Amirul Bin Ahmad
Sakrani
Financial ManagerNorharyani Binti Mohd
Solehudin Sakrani
Promotion BureauMuhsin Bin Baharudin
Logistic BureauMuhd Asyraf
MUHD ASYRAF
Operational ManagerMuhd Yazid
ADM 217 PROJECT MANAGEMENT
3.4 Organizational Chart
Yamaha 135LC Extreme Spirit
COLLEGE MCS 18
ADM 217 PROJECT MANAGEMENT
Prepared by: Noor Nadiatul Husna Binti Mohd Halil
(Assistant Project Manager)
3.5 Team contract
Project Name : Yamaha 135 LC Extreme Spirit
Project Team Members Names and Sign-off:
No. Name Sign-off on Team Contract1 Juladi bin Murkim
2 Noor Nadiatul Husna Bt Mohd Halil
3 Norharyani Bt Mohd Solehudin
4 Muhd Amirul Bin Ahmad Sakrani
5 Muhsin Bin Baharudin
6 Muhd Yazid
7 Muhd Asyraf
Code of Conduct: As a project team, we will:
We hope so that this project runs successfully. We hope so that this project did not happene any experiance
Participation: We will:
Arrive on time and end on time
Pay attention. Everyone has the responsibilities
Communication: We will:
We hope so that can interact nicely with the team work.
Be frank, honest & sincere.
COLLEGE MCS 19
ADM 217 PROJECT MANAGEMENT
Problem Solving: We will:
Attach to the topic at hand
The team speaks with one voice after the decision is made
3.6 Kickoff Meeting
Yamaha 135LC Extreme SpiritMeeting 1
06 September , 2010
Meeting Objective :
Define the vision, mission, goal, and objective. Create community members.
Members present : Positions : Juladi Bin Murkim Project Manager
Noor Nadiatul Husna Bt Mohd Halil Assistant manager
Norharyani Bt Mohd Solehudin Financial Manager
Muhd Amirul Bin Ahmad Sakrani Protocol Bureau
Muhsin Bin Baharudin Promotion Bureau
Muhd Asyraf Logistic Bureau
Muhd Yazid Operational Manager
Agenda: Introduction of attendees.
Background of project
Review of project-related document (i.e. business case, project request, contract)
Discussion of project organizational structure
Discussion of project scope, time, and cost goals
Discussion of other important topics
List of action items from meeting
No Action Item Assigned To Due Date1 Assigned the task to all community
membersNoor Nadiatul Husna bt Mohd Halil 6/9/2010
COLLEGE MCS 20
ADM 217 PROJECT MANAGEMENT
2 Survey event place Muhd Amirul Bin Ahmad Sakrani 13/9/2010
3 Confirm place event Muhd Amirul Bin Ahmad Sakrani 14/9/2010
3.6 Kickoff Meeting
Yamaha 135LC Extreme Spirit
Meeting 215 September , 2010
Meeting Objective :
Define the vision, mission, goal, and objective.
Chosen the project crew contract.
Members present : Positions : Juladi Bin Murkim Project Manager
Noor Nadiatul Husna Bt Mohd Halil Assistant manager
Norharyani Bt Mohd Solehudin Financial Manager
Muhd Amirul Bin Ahmad Sakrani Protocol Bureau
Muhsin Bin Baharudin Promotion Bureau
Muhd Asyraf Logistic Bureau
Muhd Yazid Operational Manager
Agenda: Introduction of attendees. Background of project Review of project-related document (i.e. business case, project request, contract) Discussion of project organizational structure Discussion of project scope, time, and cost goals Discussion of other important topics List of action items from meeting
No Action Item Assigned To Due Date
COLLEGE MCS 21
ADM 217 PROJECT MANAGEMENT
1 Give task to all community members Noor nadiatu Husnan Bin Mohd Halil
2/10/2010
2 Invite all VIP Juladi Bin Murkim 4/10/20103 Booking place for event Muhd Amirul Bin
Ahmad Sakrani15/9/2010
3.7 Weekly Status Report (1)
Date:
Sept 06th –10nd , 2010 & Sept 13th – 17th, 2010
Project Name:
YAMAHA 135 LC EXTREME SPIRIT
Team Member Name: Juladi Bin Murkim Project Manager Noor Nadiatul Husna Bt Mohd Halil Assistant manager Norharyani Bt Mohd Solehudin Financial Manager Muhd Amirul Bin Ahmad Sakrani Protocol Bureau Muhsin Bin Baharudin Promotion Bureau Muhd Asyraf Logistic Bureau
Muhd Yazid Operational Manager
Work Completed This Week: Looking for a date of event Identify the budget Conformation the place
Work Completed Next Week:
Received the budget from the sponsor Make a meeting for discus the budget with the sponsor Make plan the activity for the event.
What’s going well and why:
After discuss, all accept And end the meeting
What’s not going well and why:
Nothing
Suggestions/Issues:
COLLEGE MCS 22
ADM 217 PROJECT MANAGEMENT
Do the first preparation for the event.
Project changes: Nothing
3.7 Weekly Status Report (2)
Date:
Nov 01th – 05nd , 2010 & Nov 08th – 12th, 2010
Project Name:
YAMAHA 135 LC EXTREME SPIRIT
Team Member Name: Juladi Bin Murkim Project Manager Noor Nadiatul Husna Bt Mohd Halil Assistant manager Norharyani Bt Mohd Solehudin Financial Manager Muhd Amirul Bin Ahmad Sakrani Protocol Bureau Muhsin Bin Baharudin Promotion Bureau Muhd Asyraf Logistic Bureau Muhd Yazid Operational Manager
Work Completed This Week:
Discuss with sponsor and VIP
Discuss the schedule
Work Completed Next Week: Booking invitions
Make a meeting for make a team work for this event
Promote event
What’s going well and why:
After discuss, all accept
And end the meeting
What’s not going well and why:
COLLEGE MCS 23
ADM 217 PROJECT MANAGEMENT
Nothing
Suggestions/Issues: Nothing
Project changes: Nothing
3.8 Monthly Progress Report
Date: November 17h, 2010
a. Accomplishments for Month of October: Already complete survey the place for the event that will be held. Make a budget calculate the item we need for the event
b. Plans for Month of October Plan the gift and souvenir Planning the tentative program
c. Issues: This project in running successfully
d. Project Changes : No changes
e. Action taken: Done
Date: December 19st , 2010
a. Accomplishments for Month of December : We do the final presentation for this project
b. Plans for Month of December : Ensure this project run smoothly before that ceremony
c. Issues:
COLLEGE MCS 24
ADM 217 PROJECT MANAGEMENT
All the work is in successfully progress
d. Project Changes : Nothing changes
e. Action taken: Done
3.9 Milestone reports
Prepared by: Noor Nadiatul Husna Bt Mohd Halil Date: 28 September 2010
Milestone Date Status Responsible Issues / Comments
InitiatingMake project team 4/10/2010 Juladi DONE
Identify the event launching 5/10/2010 Nadia DONE
Specified event time 7/10/2010 Nadia DONE
Survey the venue 18/10/2010 Haryani DONE
PlanningIdentify the budget 20/10/2010 Haryani DONE
Booking venue 25/10/2010 Haryani DONE
Planning to invite sponsor
and VIP
27/10/2010 Yazid DONE
Plan the contest and quiz 1/11/2010 Mirul DONE
Discuss the schedule 3/11/2010 Nadia DONE
ExecutingBooking invitation card,
banner.
5/11/2010 Nadia DONE
Promote the event 9/11/2010 Yazid DONE
Discuss transportation 15/11/2010 Muhsin DONE
Identify hotel 16/11/2010 Juladi DONE
COLLEGE MCS 25
ADM 217 PROJECT MANAGEMENT
accommodations
ControllingPrepare the gift and souvenir 18/11/2010 Juladi DONE
Planning the Tentative
Program
22/11/2010 Nadia DONE
Meet the hotel management 26/11/2010 Juladi DONE
ClosingPreparation the event 6/12/2010
MuhsinDONE
Launching day 21/12/2010 Juladi DONE
Sent report 28/12/2010 Nadia DONE
3.10 Work Breakdown Structure (WBS)
Prepared by: Juladi Bin Murkim Date: 22 December 2010
1.0 Initiating
1.1 Kick of Meeting
1.2 Choose Place
1.3 Request a booking for the place
2.0 Planning
2.1 Planning an event agenda
2.2 Prepare a budget
2.3 Find a sponsor
3.0 Executing
3.1 Design a layout
COLLEGE MCS 26
ADM 217 PROJECT MANAGEMENT
3.2 Choose sponsor
3.3 Choose a theme
3.4 Confirmed a budget
4.0 Controlling
4.1 See a layout design a stage
4.2 Make sure accommodation don’t have problem
4.3 Control change and update instruction
5.0 Closing
5.1 Prepare final work about project
5.2 Prepare for presentation
5.3 Project complete
3.11 Prioritized Risks
Prepared by: Norharyani Bt Mohd Solehudin Date: 22 December 2010
Ranking Potential Risk
1 Difficult to find the sponsor.
2 The employee don’t have a team-worker in finished the task.
3 Artist late come to the concert because traffic jams.
4 The public came to the event not achieved the target.
5 System down because suddenly don’t have electric “black out”
COLLEGE MCS 27
ADM 217 PROJECT MANAGEMENT
CONCLUSION
COLLEGE MCS 28
ADM 217 PROJECT MANAGEMENT
4.0 CONCLUSION
4.1 Lessons Learned Report
Prepared by: Norharyani Bt Mohd Solehudin Date: 22/12/2010Project Name: Yamaha 135LC Extreme SpiritProject Sponsor: YamahaProject Manager: Juladi Bin MurkimProject Dates: 24/12/2010Final Budget: RM 50.000
1. Did the project meet scope, time, and cost goals?
Yes,this project meet our scope,time, and cost. With this event,our company has give the best
rating about motor to public, many teenagers has come to this event. This project run smoothly
and successfully
2. What was the success criteria listed in the project scope statement?
This project catches on which encourages from people present
COLLEGE MCS 29
ADM 217 PROJECT MANAGEMENT
3. Reflect on whether or not you met the project success criteria?
In this project, our company has been developing a development that has primary responbility for providing leadership to accomplish the project objectives. Our project has meet the project success criteria.
4. In terms of managing the project, what were the main lessons your team learned?
All team member must do their work and cooperate with each other
5. Describe one example of what went right on this project.The went right is the project has successful done on the schedule and and all plan is
working perfectly.
6. Describe one example of what went wrong on this project.This project require many workers to make it succesfull. The media also take over the event by
over reacting
7. What will you do differently on the next project based on your experience working on this project?
We will make our next project more better and more succesfull
4.2 Advantages of This Event
These advantages are:
We have success manage the event without big error
With this event, we have successfully promoting the Yamaha product to public.
Automotive industry will have opportunity to increase revenue.
4.3 Disadvantages of This Event
COLLEGE MCS 30
ADM 217 PROJECT MANAGEMENT
These disadvantages are:
Some people come just to enjoy with the motor show
Lot of garbage around event place
Traffic jam happen because lots of people come
4.4 Suggestion Improving Future Event
Encourage the local automotive to improve their product
Using new features and technology to make event more interesting and power
Make more activities and show in event make people interested to come to event.
APPENDICES
COLLEGE MCS 31
ADM 217 PROJECT MANAGEMENT
5.1 Gantt Chart
COLLEGE MCS 32
ADM 217 PROJECT MANAGEMENT
5.2 Network Diagram
COLLEGE MCS 33
ADM 217 PROJECT MANAGEMENT
COLLEGE MCS 34
ADM 217 PROJECT MANAGEMENT
5.3 Report (Cost and Resources)
SOURCE EXPECTED BUDGET
RESOURCE
Yamaha RM 50 000
TOTAL RM 50 000
OUTLOWS
PA System RM 2 000
Staging and prop production RM 6 000
Light producing production RM 2 000
Catering
Hotel cost RM 5 000
Food cost RM 5 000
Promoting and marketing
Invitation RM 5 000
Advertising RM 5 000
Sourvenir
VVIP RM 5 000
VIP RM 5 000
Security and safety
Fire marshall RM 10 000
TOTAL RM 50 000
COLLEGE MCS 35
ADM 217 PROJECT MANAGEMENT
5.4 Resource Sheet
COLLEGE MCS 36
ADM 217 PROJECT MANAGEMENT
5.5 Relevant Documents
Letters of Apply Sponsor.
An Event Management Sdn BhdNo. 3, Jalan 14/5346100 Petaling JayaSelangor Darul Ehsan, Malaysia
Digi Berhad (Company No. 167469-A) Menara Digi, No.82, Jalan Raja Muda Abdul Aziz, 50300 Kuala Lumpur, Malaysia. 22 nd October 2010
Dear Sir/Madam,
Apply for Sponsorship
I would like to ask some contribution from you for our event. The main objective of this concert is for the purpose of charity besides launching Search new comeback album. The name of the event is “YAMAHA 135LC EXTREME SPIRIT”.
2. Below are the details of this program:
Date: 21st December 2010
Time: 8:30 a.m - 05:00 p.m
Venue: Concorde Hotel Shah Alam
COLLEGE MCS 37
ADM 217 PROJECT MANAGEMENT
3. For your information, our program will be held on half days I hope you will interest to contribute to our program and become one of sponsors for this program.
I hope to hear from you soon. Thank you for your co-operation.
Yours faithfully,
…………………………
(Juladi Bin Murkim)
Project Manager
COLLEGE MCS 38
ADM 217 PROJECT MANAGEMENT
Letters of Inquiry.
An Event Management Sdn BhdNo. 3, Jalan 14/5346100 Petaling JayaSelangor Darul Ehsan, Malaysia
Manager,Concorde Hotel Shah Alam
3 Jalan Tengku Ampuan Zabedah C9/C, 40100 Shah Alam, Selangor Darul Ehsan, Malaysia 22 nd October 2010
Rent for Concorde Hotel Shah Alam
I would like to rent the Concorde Hotel Shah Alam around one day at 21st December 2010.
2. For your information, our company wants to make a charity concert. We want use this place from 8.30 a.m until 05.00p.m.
Thanks for your co-operation and we very appreciate it.
Yours faithfully,
…………………….
(Juladi Bin Murkim)
Project Manager
COLLEGE MCS 39
ADM 217 PROJECT MANAGEMENT
REFERENCES
\
COLLEGE MCS 40
ADM 217 PROJECT MANAGEMENT
6.0 Reference
6.1 Book/ Magazines
Galaxy.
Manga.
Ha!
Maskulin.
Remaja.