project name: premier diamonds 88/3,3/6,6 kv s/s project id: ne-rfm-1107-2772 presented by: charles...
TRANSCRIPT
Project Name:Project Name:Premier Diamonds 88/3,3/6,6 kV S/S Premier Diamonds 88/3,3/6,6 kV S/S
Project ID:Project ID:NE-RFM-1NE-RFM-1107-2772107-2772
Presented by: Charles Cudjoe
Date: >>>TEF Date<<<
Technical Evaluation ForumTechnical Evaluation ForumTemplate Identifier 240-60811165 1
Document Identifier XXX-XXXXXXX X
Authorisation Date 05 March 2013
23-04-19 2Rev. 1Rev. 1
Eskom ValuesEskom Values
Zero Harm Integrity Innovation Sinobuntu Customer Satisfaction Excellence
23-04-19 4Rev. 1Rev. 1
1. Decision Required1. Decision Required
The TEF is hereby requested to approve the technical content of the preliminary designs for the following project/job.
The TEF is also hereby requested to support the submission of the following project/job to the IC for financial approval.
Project Name
Job ID Job Name Scope of Work - Summary Total Cost
NE-RFM-1107-2772
Premier Diamonds 88/3,3/6,6 kV S/S
Substation refurbishment. Install new transformers
Grand Total Project Cost
23-04-19 6Rev. 1Rev. 1
3. Problem Statement3. Problem Statement
Provide what triggered the project: Substation is approximately 48 years old. The substation configuration is non-standard with no metering on the
Eskom side. Earthing on Isolators/Structures are missing posing a danger to
operators. All operating labels are not to standard. Large oil volume breakers and old isolators are redundant. No spares
available. The 88 kV VT`s are oil type and leaking. Substation fence is beyond repair Flooding and soil build up in sub yard Trfr DP values are low & some are PCB contaminated Block house still housing 3,3kV busbars (Safety concern)
23-04-19 19Rev. 1Rev. 1
5. Project Schedule5. Project Schedule
Provide information on the causes of any delays of the project. State if there are other dependencies such as Environmental, Land
Acquisition, etc.
Existing Project Schedule
TEFBQDRADHOERACommissioningFRA
19
23-04-19 20Rev. 1Rev. 1
6. Load Forecast6. Load Forecast
Title
0
1
2
3
4
5
6
7
8
9
10
2010 2011 2012 2013
Lo
ad [
MV
A]
Fdr A Fdr B Fdr C 185X Cu
Double Click to edit.
23-04-19 21Rev. 1Rev. 1
6. Load Forecast6. Load Forecast
Annual Maximum Demand Forecast
32
33
34
35
36
37
38
39
2012 2013 2014 2015 2016 2017 2018 2019 2020
Lo
ad
[M
VA
]
Total Outgoing Feeders
23-04-19 22Rev. 1Rev. 1
7. Geographical Location7. Geographical Location
Mark where the project is taking place.
Show places others can use to orientate themselves such as major roads, cities
and substations.
Show the scale.
23-04-19 23Rev. 1Rev. 1
7. Geographical Location7. Geographical Location
NDP Area Bynes
Engineering Area Pretoria
Technical Services Area Pretoria FSC
Customer Services Area Pretoria
Field Services Area CullinanTSC
23-04-19 24Rev. 1Rev. 1
8. SHIM – Stakeholders Invited, Register, 8. SHIM – Stakeholders Invited, Register, Comments & Minutes Comments & Minutes
24
The recorded minutes of the Stakeholders Input Meeting, and the actual comments of all Stakeholders must be captured at the Stakeholder
Input meeting, scanned and included in the TEF presentation.
23-04-19 25Rev. 1Rev. 1
8. SHIM – Stakeholders Invited, Register, 8. SHIM – Stakeholders Invited, Register, Comments & Minutes Comments & Minutes
NAME DEPARTMENT TELEPHONE
1 Kumarin Govender QOS (Plant) 012 421 4754
2 Vernon Lewis GOU (COW) #3308
3 Frans Kirsten Plant 083 787 2677
4 Martin Rafedile NS Planning 083 704 9376
5 Lethebe Mswazi CPM - Telecontrol 083 488 4766
6 M Beukman CPD COW #3308
7 TV Mahlangu CPMD Metering 082 077 2067
8 Larissa Wesi CPD – QS 011 721 2843
9 Levy Masenya PED – Menlyn 073 560 6666
10 Shaun Hards or Vincent Dreyer
Actom P & C-Control Plant 083 600 3277 or082 377 8030
11 Jorrie Jordaan Cullinan Field Services 082 375 3841
12 Charles Cudjoe NED 012 484 5044
13 Neels J v Vuuren Petra 082 803 0302
25
23-04-19 26Rev. 1Rev. 1
8. SHIM – Stakeholders Invited, Register, 8. SHIM – Stakeholders Invited, Register, Comments & Minutes Comments & Minutes
Planning • New fault studies have been done for the NDP
Plant• 3,3kV b/bars to be removed.• Building will remain. • HV cables will be sealed off
Control
• investigate the metering. • Telecontrol (D20 RTU) needs Optic Fibre communication link to
Byness to work for communication to SCADA
Customer Services • Quote the customer for 1 additional transformer
26
23-04-19 27Rev. 1Rev. 1
9. Design Alternatives Considered9. Design Alternatives Considered
Option Description Technical Viable (Yes/No) Financial Analysis
Option 1 – Give a brief description. It should be the CRA scope of work.
Yes/No – Give evidence Cost implication
Option 2 – Give a brief description. It should be the options where there is additional work as per stakeholders inputs.
Yes/No – Give evidence Cost implication
Etc.
Please indicate the preferred one
23-04-19 28Rev. 1Rev. 1
9. Design Alternatives Considered9. Design Alternatives Considered
Option Description Technical Viable (Yes/No) Financial Analysis
Option 1 – Replace all 5MVA trf’s with 4 X 10MVA units.
Yes Cost implication
Option 2– Replace all 5MVA trf’s with 2 X 20MVA units. Upgrade the 3.3kV to 6.6kV
Yes Cost implication
Option 2 is the preferred one
23-04-19 29Rev. 1Rev. 1
10. Network Performance – Historical and 10. Network Performance – Historical and ExistingExisting
23-04-19 32Rev. 1Rev. 1
12. Existing Substation General 12. Existing Substation General ArrangementArrangement
32
23-04-19 33Rev. 1Rev. 1
12. Proposed Substation General 12. Proposed Substation General Arrangement cont.Arrangement cont.
23-04-19 34Rev. 1Rev. 1
13. Existing Network Diagram13. Existing Network Diagram
Bynes 132kV & Esselen 88kV network
Bynes 88kVBynes 132kV
23-04-19 36Rev. 1Rev. 1
14. Control Plant Scope of Work14. Control Plant Scope of WorkExisting Equipment
Proposed installation or replacement
Reason for new installation or replacement
AC/DC 220VDC Panel 110VDC Panel with an ACO built-in
Old scheme and conversion to 110VDC
DC System 220VDC battery bank with FCP17 lead-acid cells, housed in a separate battery room
110VDC battery bank with NiCAD cells
Standardised on 110VDC. Battery room will be converted into an extension of the current control room
88kV Metering No 88kV Stats Panel 1x Stats Panel New installation
6.6kV Metering 2x Tariff Panels(Non-standard)
2x Tariff Panels Existing panels not to standard and not sufficient to cover metering requirements
88/6.6kV Transformer(Trfs 5 & 6)
Old phase 1 schemes 2x 4TM7100 schemes Old schemes to be upgraded
23-04-19 37Rev. 1Rev. 1
14. Control Plant Scope of Work Cont.14. Control Plant Scope of Work Cont.
Existing Equipment
Proposed installation or replacement
Reason for new installation or replacement
88/6.6kV Transformer(Trfs 1 & 2)
Non existent 2x 4TM7100 schemes New installation
88kV BusZone Older phase 1 schemes 1x 4BZ5800 scheme Old schemes to be upgraded
88kV Feeders Older phase 1 schemes 3x 4FZD3920 protection scheme
Old schemes to be upgraded
Tele-control Non existent 1X D20 RTU 1X BME1X Fibre Patch Panel
New installation
23-04-19 39Rev. 1Rev. 1
15. Power Plant Scope of Work15. Power Plant Scope of Work
Give a description of the work to be done: Specify new equipment, its size and quantity. Specify equipment to be decommissioned. Specify changes in network configuration. Separate the work that is covered by the customer from the work to be
done by Eskom.
23-04-19 40Rev. 1Rev. 1
15. Power Plant Scope of Work15. Power Plant Scope of Work
HV SideReplace all (8) 5MVA trfr`s(double banked units) with (2) single 20MVA unitsReplace 88kV VT`s on BusbarReplace WOD`s switches with 132kV Breakers on Tfr1-4Replace all Isolators including bus sections with new double break 132kV unitsReplace 88kV busbar Conductor to standard Bull conductorInstall new 132kv bkr on 88kV Zonderwater incoming line with Stats metering.Move all line surge arrestors to busbar side of line isolatorReplace all surge arrestors on Trfr`s 88/6,6/3,3 kVReplace all 88kV incoming cables with overhead lines
MV SideInstall new 3,3 kV (6,6kV) feeder cable supportsInstall new 11kV Isolators on 3,3kV side for isolation between Eskom and CustomerInstall new 11kV transformer kiosk breakers and Vt`s for protection and metering on 3,3kV side Construct MV transformer bay according 2/ET-15108
23-04-19 41Rev. 1Rev. 1
15. Power Plant Scope of Work cont.15. Power Plant Scope of Work cont.
Civil & other WorkCivil & other Work
Build a bund wall around all Transformer plinthsInstall an oil holding damBuild a retaining wall to prevent floodingReplace bolted connections with crimp connections.Test earth mat and repair if necessaryReplace all equipment labels.Replace yard overhead screening wire to Hare conductorInstall yard lights
Replace fence with steel welded galvanised fence enclosing control room Replace the roof of the control room Supply 9 sets of 10kA earth/applicator sticks with lock-up box (2-Et/14904) Repair Control room and install Desk(2-ET/14904) All indoor bus bars, isolators, panels are to be removed. New trfr panels move to
control room
23-04-19 42Rev. 1Rev. 1
16. Site/Route/Township Plan16. Site/Route/Township Plan
42
ZETA
POTCH DS
NEW SUB
OPTION1
Route directly to Potch DS
Lines and Cables: Provide geographical layout of the route showing other mapping details such as roads, erven, rivers, wetlands, contours, etc.
Substations: Provide geographical layout of the substation site showing other mapping details such as roads, access, private properties, rivers, wetlands, contours, etc.
Developer and Electrification: Provide the development layout with respect to existing network.
23-04-19 44Rev. 1Rev. 1
17. Materials Selection17. Materials Selection
Description
General Conductor
VoltageFuture Fault Level Maximum
LoadSize
Conductor RatingBurn Off
3 Phase 1 Phase Normal Emergency
HV Incomer
HV Busbar
Trfr HV Side
Trfr MV Side
MV Busbar
DescriptionBreaker Isolator Current Transformer VT SA
Cont. 3sec Cont. 3sec Cont. 3sec Voltage Voltage
HV Incomer
HV B/C or B/S
Trfr HV Side
Trfr MV Side
MV B/C or B/S
MV Feeders
The purpose of this slide is to compare load
and fault level requirements to material
selection.
23-04-19 45Rev. 1Rev. 1
17. Materials Selection17. Materials Selection
Description
General Conductor
VoltageFuture Fault Level Maximum
Load (A)Size
Conductor Rating Burn Off (s)3 Phase 1 Phase Normal (A) Emergency (A)
HV Incomer
88kV
Bear
HV Busbar 1350 Bull 1350 1680
Trfr HV Side 131.2 Centipede 833 A 1340A
Trfr MV Side6.6kV
1750 Twin Bull 2700 3360
MV Busbar - - - -
DescriptionBreaker Isolator Current Transformer VT SA
Cont. 3sec Cont. 3sec Cont. 3sec Voltage Voltage
HV Incomer 3150 40kA 2500 40kA 2500 40kA - 88kV
HV B/C or B/S - - 2500 40kA - - 88kV -
Trfr HV Side 3150 40kA 2500 40kA 2500 40kA - 88kV
Trfr MV Side 2500 25kA 2500 25kA - - 3.3 / 6.6kV 3.3 / 6.6kV
MV B/C or B/S - - 2500 25kA - - - -
MV Feeders 2500 25kA 2500 25kA - - - 3.3 / 6.6kV
Note: A cable will go out from the s/s to the customer’s common point of connection
23-04-19 46Rev. 1Rev. 1
18. DRA Decommission Input Sheet18. DRA Decommission Input Sheet
Use ‘Print Screen’ to copy this table.
23-04-19 47Rev. 1Rev. 1
18. DRA Decommission Input Sheet18. DRA Decommission Input Sheet
Details of Assets to be decommissioned Job Number:Project Name: Premier Diamonds 88/6,6/3,3 kV sub
Disposal
1 2 x 5MVA Trfrs N/A 2 #VALUE! Zero To TSG Witbank X2 8 x 88kV Isolators N/A 1 #VALUE! Zero Scrap 4,800 X3 1 x 88kV breakers N/A 1 #VALUE! Zero Scrap 1,200 X4 15x 88kv Ct`s N/A 1 #VALUE! Zero Scrap 9,000 X5 6 x 88kV Vt`s N/A 1 #VALUE! Zero Scrap 1,800 X6 3x Nulec reclosers N/A 2 #VALUE! Zero to Plant slab X7 X8 X9 X10 X11 X12 X13 X14 X15 X16 X17181920
-R -R 16,800.00R
ASSET REGISTER
PROFIT/LOSS RELATED TO DECOMMISSIONING OF ASSETS
Net Book Value (NBV) 0Less: MATERIAL Returned to Store (RTS) 0Less: SCRAP SALES (SS) 16,800Sub Total (NBV - (RTS+SS)) -16,800
Plus: LABOUR 0Plus: CONTRACTS 0Plus: TRANSPORT 0Plus: GENERAL EXPENSES 0Plus: ENVIRONMENTAL REHAB 0Cost to Dismantle 0
(PROFIT)/LOSS (R16,800)
TOTAL VALUE DECOMMISSIONING (R16,800) (Labour+Transport+Gen Exp+Enviro Rehab)-(RTS+SS)
Net Book Value as onItem
TOTAL
RightsBuild &
FacMachinery &
Plant
TYPE OF ASSETMaterials Return
to storeScrap Sales
LandDescription
Asset Register No.
Scrap (1) or Transfer (2)
Ratio (%) Partial decom
Use ‘Print Screen’ to copy this table.
WRONG FORMAT!
23-04-19 48Rev. 1Rev. 1
19. Project Costing Detail19. Project Costing Detail
Cost Component DRA JOB 1 DRA…N TOTAL DRAEngineering Costs (E) R 10,000,000 10,000,000.00R 10,000,000.00R Materials (M) R 1 1.00R 1.00R Internal Construction (C) External Contracts (E) R 298,248 298,248.00R 298,248.00R Commissioning (T)Overheads R 19,907 19,906.55R 19,906.55R IDC -R -R Land and Rights (L) R 1,240 1,240.00R 1,240.00R Total Project Cost R 10,319,396 10,319,395.55R 10,319,395.55R Approved CRA Amount R 2,000,000 2,000,000.00R 2,000,000.00R Contingency R 32,407 32,407.00R 32,407.00R Long Lead Material R 2,000 2,000.00R 2,000.00R
PROVIDE HIGH LEVEL SCOPE FOR EACH JOB
23-04-19 49Rev. 1Rev. 1
20. Customer Capital Contribution 20. Customer Capital Contribution CalculationsCalculations
Provide the breakdown of customer capital contribution calculations. Provide the basis in which percentage contribution is based upon.
Engineering Costs (E) R 10,000,000 2,000,000 R 8,000,000Materials (M) R 1 R 1Internal Construction (C) External Contracts (E) R 298,248 100,000 R 198,248Commissioning (T)Overheads R 19,907 R 19,907IDCLand and Rights (L) R 1,240 R 1,240Total Project Cost R 10,319,396 2,100,000 R 8,219,396Approved CRA Amount R 2,000,000Contingency R 32,407 R 32,407Long Lead Material R 2,000 R 2,000
Customer Contribution
Eskom ContributionDRACost Component
49
STATE N/A IF NOT REQUIRED
23-04-19 50Rev. 1Rev. 1
21. Financial Analysis/PEM21. Financial Analysis/PEM
Provide FEM Assumptions FEM is required for all projects
that are: For strengthening and
refurbishment. For direct customer and the
customer is not paying the full project cost.
For electrification and the DOE is not paying the full project cost.
Even FEM’s with negative NPV need to be presented.
23-04-19 51Rev. 1Rev. 1
22. Risk and Mitigation Strategy22. Risk and Mitigation Strategy
51
Risk Impact on Project Mitigation Strategy ImpactUnder-estimation of integration/interface effort of SAP with third party systems
Project Schedule
Project Cost
Project Quality
Provide adequate contingency for integration
High
Organisation may not be prepared to accept newly implemented solution
Realisation of Benefits Strong change management and training required.
Medium
Inability to achieve standardisation (This is largely an effect of improper, ineffective change management)
Realisation of Benefits Limit exceptions in process design. Effective socialisation of new processes across the organisation
Low
• Indicate if the mitigation is an allocation of funds in the contingency to cater for the uncertainty factor
• Is this amount also in the financial budget for the year
• If applicable reduce or increase the number of risks
23-04-19 52Rev. 1Rev. 1
23. Long Lead Materials – Primary Plant23. Long Lead Materials – Primary Plant
Lead Time (Mths) Quantity Amount ( Rands ) %
3 2000 1,236,380R 80.1%
PMB 3 3 287,793R 18.6%
Poles 3 16 12,000R 0.8%
Hare conductor 3 1214 8,304R 0.5%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
1,544,477R 100.0%Total Long Lead Time Material Approved
LONG LEAD TIME MATERIAL REQUIRED
Item Description
22kV 185mm sq 3c XLPE copper cable
23-04-19 53Rev. 1Rev. 1
23. Long Lead Materials – Control Plant23. Long Lead Materials – Control Plant
Lead Time (Mths) Quantity Amount ( Rands ) %
3 2000 1,236,380R 80.1%
PMB 3 3 287,793R 18.6%
Poles 3 16 12,000R 0.8%
Hare conductor 3 1214 8,304R 0.5%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
1,544,477R 100.0%Total Long Lead Time Material Approved
LONG LEAD TIME MATERIAL REQUIRED
Item Description
22kV 185mm sq 3c XLPE copper cable
23-04-19 54Rev. 1Rev. 1
24. Sequence of Construction Events24. Sequence of Construction Events
Discuss how will the project be constructed: Highlight the need for backfeeding / switching off the busbar. Highlight the number of outages and the number of customers that will
be affected as well as type of customers. Contingency plans during construction. Is there a need for mobile transformers, rhino units, RMU, voltage
regulators, live line, etc. “A picture is worth a 1,000 words”
23-04-19 55Rev. 1Rev. 1
24. Sequence of Construction Events24. Sequence of Construction Events
One 88/6.6kV transformer will be kept alive at a time while the other trfr bay is normalized
The 3.3kV side will be switched off and normalized while the 6.6kV is alive (Customer will provide the 6.6/3.3 kV transformers)
Repair the earth mat and fence and construct the dam Normalize transformer bays 1 and 3 Restring the b/b and normalize the feederbays
23-04-19 56Rev. 1Rev. 1
25. Impact on SAIDI During Construction25. Impact on SAIDI During Construction
56
Use the KPI impact calculator to determine the impact on SAIDI during
construction.
23-04-19 66Rev. 1Rev. 1
27. Other Technical Requirements27. Other Technical Requirements
Substations (See Substation Technical Requirements Template) HV Lines (See HV Lines Technical Requirements Template) HV Cables (See HV Cables Technical Requirements Template) Distribution: Overhead Lines (See Dx O/L Technical Requirements
Template) Distribution: Underground Cables (See Dx U/C Technical
Requirements Template) Electrification (See Electrification Technical Requirements
Template)
Delete all that is not to your project including the red text!>>>Add the applicable Technical Requirement Slides Beyond This Slide<<<
23-04-19 67Rev. 1Rev. 1
Annexure/Additional Information
Transformer Make
PCB
MVA Rating
Year of Manufacture
Serial No DP Value
1A Asea Y
1B Brush R
2A Asea G
2B Desta G
3A Asea Y
3B Brush R
4A Ferranti N
4B Brush Y
5 Alstom G
6 Alstom G
5MVA
5MVA
5MVA
5MVA
5MVA
5MVA
5MVA
5MVA
20MVA
20MVA
1966
1990
1966
1997
1966
1988
1988
20091
06/60176
20083
T2316
20093
51451
138523
51452
28928
28930
500 DP value degrade by +- 30 per year
550
340
490
910
490
310
410
750
420Note:
If unit reach DP of <200 extensive paper degradation took place and reactor is at serious risk of failure