project planning - مصرosp.mans.edu.eg/elbeltagi/cb517p ch1.pdf · project planning activity...
TRANSCRIPT
1
Project PlanningProject Planning
29/09/2016 Emad Elbeltagi 2
Project PlanningProject PlanningPlanning in General : SWOT analysisPlanning in General : SWOT analysis
S: StrengthsW: WeaknessesO: OpportunitiesT: Threats
S: StrengthsW: WeaknessesO: OpportunitiesT: Threats
Objectives should be: SMARTObjectives should be: SMARTS: SpecificM: MeasurableA: AchievableR: RealisticT: Timely
S: SpecificM: MeasurableA: AchievableR: RealisticT: Timely
2
29/09/2016 Emad Elbeltagi 3
Project PlanningProject PlanningCharacteristics of a good planCharacteristics of a good plan
Based on clearly definite and practical objectives Simple Flexible Easy to control Provide proper standards
Exploit existing resources, etc.
Based on clearly definite and practical objectives Simple Flexible Easy to control Provide proper standards
Exploit existing resources, etc.
29/09/2016 Emad Elbeltagi 4
Project PlanningProject PlanningPlanning Inputs and OutputsPlanning Inputs and Outputs
Contract informationDrawings
SpecificationsAvailable resources
Bills of quantitiesSite reports
Organizational dataConstruction methods
ActivitiesRelationships among activitiesMethod statementResponsibilityReporting levelsProject network diagramActivities durationActivities cost
INPUTS OUTPUTS
PLANNING
3
29/09/2016 Emad Elbeltagi 5
Project PlanningProject PlanningPlanning Major stepsPlanning Major steps
Determination of Project Activities (WHAT)
Establishment of Logic; Relationships and overlap (How)
Presentation (Table, Network, Chart, …)
Estimate Activities’ Duration and Cost (When)
Determination of Project Activities (WHAT)
Establishment of Logic; Relationships and overlap (How)
Presentation (Table, Network, Chart, …)
Estimate Activities’ Duration and Cost (When)
29/09/2016 Emad Elbeltagi 6
Project PlanningProject PlanningWork Breakdown Structure (WBS)Work Breakdown Structure (WBS)
The WBS is a hierarchical structure which is designed to logically sub-divide all the work-elements of the project into smaller elements.
The WBS is a hierarchical structure which is designed to logically sub-divide all the work-elements of the project into smaller elements.
House
Civil Plumping Electrical
Foundations Walls/Roof
Piping
H/C Water
Wiring Finishing
4
29/09/2016 Emad Elbeltagi 7
Project PlanningProject PlanningWork Breakdown Structure (Why)Work Breakdown Structure (Why)
Prepare project plan Identifying Activities Scheduling Identifying cost & schedule at various levels of
details Time & cost control Identifying individual or departmental responsibilities
Prepare project plan Identifying Activities Scheduling Identifying cost & schedule at various levels of
details Time & cost control Identifying individual or departmental responsibilities
29/09/2016 Emad Elbeltagi 8
Project PlanningProject PlanningWBS & Organizational Breakdown Structure (OBS) WBS & Organizational Breakdown Structure (OBS)
Project
Area 1 Area 3
Beams Columns Slabs
Formwork Reinforcement Concreting
OBS (Responsibility & reporting)
Area 2 ……
……
……
Project manager
WBS (Work elements)
Subcontractor A
General contractor
Subcontractor B
Civil superinte
ndent
Mechanical
superintendent
Electrical superinte
ndent
Formwork foreman
Rebar foreman
Concrete foreman
Control account
5
29/09/2016 Emad Elbeltagi 9
Project PlanningProject PlanningWBS Coding WBS Coding
Each work package or activity in a WBS is given a unique code that is used in project planning and control Identifying Activities
Each work package or activity in a WBS is given a unique code that is used in project planning and control Identifying Activities
29/09/2016 Emad Elbeltagi 10
Project PlanningProject PlanningProject ActivitiesProject Activities
Project is divided into segments of work called activities
Activity: Time-consuming single work element
Guidelines for project breakdown: by: area of
responsibility, structural element, category of work, etc.
Level of details depends on: planning stage, size of the
project, complexity of the work, etc.
Project is divided into segments of work called activities
Activity: Time-consuming single work element
Guidelines for project breakdown: by: area of
responsibility, structural element, category of work, etc.
Level of details depends on: planning stage, size of the
project, complexity of the work, etc.
6
29/09/2016 Emad Elbeltagi 11
Project PlanningProject PlanningProject ActivitiesProject ActivitiesTypes of construction activities:
Production: taken directly from drawings and/or
specifications
Management (Approvals, site establishment, …etc).
Procurement (equipment delivery, material
procurement)
Types of construction activities:
Production: taken directly from drawings and/or
specifications
Management (Approvals, site establishment, …etc).
Procurement (equipment delivery, material
procurement)
29/09/2016 Emad Elbeltagi 12
Project PlanningProject PlanningProject ActivitiesProject Activities
Example (Double Span Bridge):
Precast beams
Deck slab
Road base left Road base right
Hand rail
7
Code Description
10 Set-up site -
14 Procure RFT -
16 Procure P.C. Beams -
20 Excavate left abutment -
30 Excavate right abutment -
40 Excavate central pier -
50 Foundation left abutment -
60 Foundation right abutment -
70 Foundation central pier -
80 Construct left abutment -
90 Construct right abutment -
100 Construct central pier -
110 Erect left P.C. Beams -
120 Erect right P.C. Beams -
140 Fill left embankment -
150 Fill right embankment -
155 Construct deck slab -
160 Left road base -
170 Right road base -
180 Road surface -
190 Bridge railing -
200 Clear site -
29/09/2016 Emad Elbeltagi 14
Project PlanningProject PlanningActivities RelationshipsActivities Relationships The order in which project activities are to be performed
Which activity(ies) must be completed before an activity
can start
Which activity(ies) can not start until activity completion
Which activity(ies) have no logical relations
Logic constraints: Physical, and Resources
The order in which project activities are to be performed
Which activity(ies) must be completed before an activity
can start
Which activity(ies) can not start until activity completion
Which activity(ies) have no logical relations
Logic constraints: Physical, and Resources
8
29/09/2016 Emad Elbeltagi 15
Project PlanningProject PlanningPredecessorsPredecessors
Controls the start or finish of another activity Controls the start or finish of another activity
SuccessorsSuccessors Depends on the start or finish of another activity Depends on the start or finish of another activity
Predecessor to Act. B
Successor to Act. B
29/09/2016 Emad Elbeltagi 16
Project PlanningProject PlanningType of Activities RelationshipsType of Activities Relationships
Four Types:Finish to Start (FS) Finish to Finish (FF)Start to Start (SS) Start to Finish (SF)
FS FF
SS SF
9
29/09/2016 Emad Elbeltagi 17
Project PlanningProject PlanningType of Activities RelationshipsType of Activities Relationships
Finish-StartWhen A finishes, then B can startDefault Relationship
AFirst Activity
BSecond Activity
29/09/2016 Emad Elbeltagi 18
Project PlanningProject PlanningType of Activities RelationshipsType of Activities Relationships
Start-StartWhen A starts, then B can start
AFirst Activity
BSecond Activity
10
29/09/2016 Emad Elbeltagi 19
Project PlanningProject PlanningType of Activities RelationshipsType of Activities Relationships
Finish-FinishWhen A finishes, then B can finish
AFirst Activity
BSecond Activity
29/09/2016 Emad Elbeltagi 20
Project PlanningProject PlanningType of Activities RelationshipsType of Activities Relationships
Start-FinishWhen A starts, then B can finish
AFirst Activity
BSecond Activity
11
29/09/2016 Emad Elbeltagi 21
Project PlanningProject PlanningOverlapsOverlapshow much a particular activity must be completed before a succeeding activity may start Used for activities not using the same type of resources With a value less than the duration of the preceding activity
+ve overlap (-ve lag) -ve overlap (+ve lag)
Code Description Predecessors
10 Set-up site ---
14 Procure RFT ---
16 Procure P.C. Beams ---
20 Excavate left abutment 10
30 Excavate right abutment 10
40 Excavate central pier 10
50 Foundation left abutment 14, 20
60 Foundation right abutment 14, 30
70 Foundation central pier 14, 40
80 Construct left abutment 50
90 Construct right abutment 60
100 Construct central pier 70
110 Erect left P.C. Beams 16, 80, 100
120 Erect right P.C. Beams 16, 90, 100
140 Fill left embankment 80
150 Fill right embankment 90
155 Construct deck slab 110, 120
160 Left road base 140
170 Right road base 150
180 Road surface 155, 160, 170
190 Bridge railing 155
200 Clear site 180, 190
12
29/09/2016 Emad Elbeltagi 23
Project PlanningProject PlanningOverlapsOverlapsExample
Consider the construction of the following sequential activities of
a bridge consists of 19 bays
Pile manufacturing with duration 2.5 wks/pier
Pile driving with duration 1.5 wks/pier
Pile cap with duration 2.0 wks/pier
Pier shaft with duration 2.5 wks/pier
Determine the appropriate overlap between activities
Example
Consider the construction of the following sequential activities of
a bridge consists of 19 bays
Pile manufacturing with duration 2.5 wks/pier
Pile driving with duration 1.5 wks/pier
Pile cap with duration 2.0 wks/pier
Pier shaft with duration 2.5 wks/pier
Determine the appropriate overlap between activities
29/09/2016 Emad Elbeltagi 24
Project PlanningProject PlanningRelationships Considering Resource ConstraintsRelationships Considering Resource Constraints
Activity descriptionPredecessors (unconstrained
resources)
Predecessors (constrained resources)
A1B1C1
A2B2C2
A3B3C3
Excavate unit 1Concreting unit 1Brickwork unit 1
Excavate unit 2Concreting unit 2Brickwork unit 2
Excavate unit 3Concreting unit 3Brickwork unit 3
-A1B1
-A2B2
-A3B3
-A1B1
A1B1, A2C1, B2
A2B2, A3C2, B3
13
29/09/2016 Emad Elbeltagi 25
Project PlanningProject PlanningProject networks: AOAProject networks: AOA
Two Types: Activity-On-Arrow; AOA (Arrow Networks). Activity-On-Node; AON (Precedence Networks):AOA Activity represented as arrows with start and finish nodes called Events
i jActivity A
j > i
29/09/2016 Emad Elbeltagi 26
Project PlanningProject PlanningProject networks: AOAProject networks: AOA
5 A 10 15BB depends on A
5 A 10 15C
5
BC depends on A and B
5 A 10 15C
15B B depends on A
C depends on A
15D
15C C depends on A and B
D depends on A and B
5B 10
5 A
14
29/09/2016 Emad Elbeltagi 27
Project PlanningProject PlanningProject networks: AOAProject networks: AOA
Dummy activity Activity with zero duration and no resources to adjust the network
Incorrect representation
20C5
A15
10
B
C depends on A and B; D depends on B only
25
D
Correct representation
5A
20 25C
1510B 30D
Dummy
15A5
B
5 15A
10
BDummy
29/09/2016 Emad Elbeltagi 28
Project PlanningProject PlanningProject networks: AONProject networks: AON
AOA Activity represented as nodes
10A
Activity number
Activity name
15
29/09/2016 Emad Elbeltagi 29
Project PlanningProject PlanningProject networks: AONProject networks: AON
B depends on A10A
20B
C depends on A and BD depends on C
30C
10A
20B
40D
B depends on AC depends on BD depends on B
10A
20B
40D
30C
29/09/2016 Emad Elbeltagi 30
Project PlanningProject PlanningProject networks: ExampleProject networks: Example
Activity Predecessors
ABCDEFG
--
A, BCCD
D, E
16
29/09/2016 Emad Elbeltagi 31
Project PlanningProject PlanningProject networks: Example (AOA)Project networks: Example (AOA)
29/09/2016 Emad Elbeltagi 32
Project PlanningProject PlanningProject networks: Example (AON)Project networks: Example (AON)
EFG
Finish
CD
D, EF, G
SS(C)+1 = 4SS(D)+1 = 4Highest of [SS(D), SS(E)] = 5Highest of [SS(F), SS(G)] = 5
Calculate the Sequence step
Start - SS(Start) = 1A - SS(Start) +1 = 2B - SS(Start) +1 = 2C A, B Highest of [SS(B), SS(A)] = 3D C SS(C) +1 = 4
Activity Predecessor Sequence step (SS)
17
29/09/2016 Emad Elbeltagi 33
Project PlanningProject PlanningProject networks: Example (AON)Project networks: Example (AON)
Sequence step 1 2 3 4 5 6
29/09/2016 Emad Elbeltagi 34
Project PlanningProject PlanningActivity Duration & Direct CostActivity Duration & Direct Cost
Planning time unit (hours, days, weeks, months)
Establish method statement (method of construction)
Specify number of resources, and hence output
Duration = Quantity of work / No. of Res. x Res. Output
Planning time unit (hours, days, weeks, months)
Establish method statement (method of construction)
Specify number of resources, and hence output
Duration = Quantity of work / No. of Res. x Res. Output
18
29/09/2016 Emad Elbeltagi 35
Project PlanningProject PlanningActivity Duration & Direct CostActivity Duration & Direct Cost
Productivity data
Man-hours/ unitMhrs/unit
Daily productionUnits/day
How long it takes form one labor to finish one unit
Applies to any crew formation
How long it takes form one labor to finish one unit
Applies to any crew formation
How many units can be done in one time unit
Applies to a given crew
How many units can be done in one time unit
Applies to a given crew
Productivity can be estimated:
From published data ( الموسوعة الھندسیة(
Previous records of a company
Productivity can be estimated:
From published data ( الموسوعة الھندسیة(
Previous records of a company
29/09/2016 Emad Elbeltagi 36
Project PlanningProject PlanningActivity Duration & Direct CostActivity Duration & Direct CostExampleWhat is the duration to install 6000 square feet of walls shuttering if:
Crew of 2 carpenters is used, output of 200 square feet/day Productivity is measured as 0.008 man-hour/square feet. Number
of carpenters =3, and number of working hours/day = 8 hours
ExampleWhat is the duration to install 6000 square feet of walls shuttering if:
Crew of 2 carpenters is used, output of 200 square feet/day Productivity is measured as 0.008 man-hour/square feet. Number
of carpenters =3, and number of working hours/day = 8 hours
a. Duration = 6000 / 200 = 3 daysa. Duration = 6000 / 200 = 3 days
b. Total man-hours needed = 6000 x 0.008 = 48 man-hours (if one man used)
Duration = 48 / 8 = 6 days (if one man used)Duration using 3 men = 6 / 3 = 2 days
b. Total man-hours needed = 6000 x 0.008 = 48 man-hours (if one man used)
Duration = 48 / 8 = 6 days (if one man used)Duration using 3 men = 6 / 3 = 2 days
19
29/09/2016 Emad Elbeltagi 37
Project PlanningProject PlanningActivity Duration & Direct CostActivity Duration & Direct CostExample (balanced mix of resources)A wall involves 660 m3 concrete, 50 tone of steel, and 790 m2 of formwork.
- A 6 man concrete crew can place 16 m3 of concrete/day.- A steel-fixer and assistant can fix 0.5 ton of reinforcement/day.- A carpenter and assistant can fix and remove 16 m2 of shuttering/day
Example (balanced mix of resources)A wall involves 660 m3 concrete, 50 tone of steel, and 790 m2 of formwork.
- A 6 man concrete crew can place 16 m3 of concrete/day.- A steel-fixer and assistant can fix 0.5 ton of reinforcement/day.- A carpenter and assistant can fix and remove 16 m2 of shuttering/day
- using one steel-fixer: duration = 50 / 0.5 = 100 days- using one carpenter: duration = 790 / 16 = 49.4 days- using one concreting crew: duration = 660 / 16 = 41.25 days.2 steel-fixer crews, one carpenter crew, and cone concreting crew.
duration = 50 / 0.5 x 2 = 50 days
- using one steel-fixer: duration = 50 / 0.5 = 100 days- using one carpenter: duration = 790 / 16 = 49.4 days- using one concreting crew: duration = 660 / 16 = 41.25 days.2 steel-fixer crews, one carpenter crew, and cone concreting crew.
duration = 50 / 0.5 x 2 = 50 days
29/09/2016 Emad Elbeltagi 38
Project PlanningProject PlanningActivity Duration & Direct CostActivity Duration & Direct CostActivity direct cost:
Duration, resources, and cost are interrelated elements
Direct cost comprises: labor, material, equipment, and/or
subcontractors
Unit cost = total cost / quantity
Activity direct cost:
Duration, resources, and cost are interrelated elements
Direct cost comprises: labor, material, equipment, and/or
subcontractors
Unit cost = total cost / quantity