project rehabilitation report of hagaribomanahalli pick up dam
TRANSCRIPT
Project Rehabilitation Report of H B Halli Dam
i | P a g e
Project Rehabilitation Report of
Hagaribomanahalli Pick Up Dam
Karnataka Water Resources Department Doc. No.: CDSO_DSR_PRR_ KA06MH0087_KaWRD_v1.0
June 2020
Central Water Commission
Ministry of Jal Shakti
Department of Water Resources,
River Development & Ganga Rejuvenation
Government of India
Project Rehabilitation Report of H B Halli Dam
ii | P a g e
Quality Control:
Version Date Writers/Contributors Checked by
1 23/06/2020
Hemant Joshi (HJ) Dr. Hadush S Hagos (HSH) Pankaj Kumar Awasthi (PKA) Anil Kumar Verma (AKV)
Rajiv Kumar Sawarn
Issued/Copied to:
I/C Date Name Organization
Issued 25/06/2020 Shri. Pramod Narayan Central Water Commission
Project Rehabilitation Report of H B Halli Dam
iii | P a g e
Abbreviations
DRIP Dam Rehabilitation & Improvement Project
CWC Central Water Commission
CPMU Central Project Management Unit
CSV Construction Site Visit
SPMU State Project Management Unit
IA Implementation Agency
PIC Project Identification Code
DSRP Dam Safety Review Panel
PST Project Screening Template
DFR Design Flood Review
MSL Mean Sea Level
FRL Full Reservoir Level
MWL Maximum Water Level
TBL Top Bund Level (Top Level of Dam)
MDDL Maximum Draw Down Level
LSL Lowest Sill Level
DSL Dead Storage Level
U/S Upstream
D/S Downstream
El. Elevation
L/B Left Bank
R/B Right Bank
PMF Probable Maximum Flood
SPF Standard Project Flood
CD Works Cross Drainage Works
VRB Village Road Bridge
WBM Water Bound Macadam
NDT Non Destructive Testing
DHARMA Dam Health And Rehabilitation Monitoring Application
O & M Operation and Maintenance
EAP Emergency Action Plan
Project Rehabilitation Report of H B Halli Dam
iv | P a g e
ESMF Environmental and Social Management Framework
E & S specialists Environmental and Social Specialists
HM Works Hydro-Mechanical Works
EM Works Electro-Mechanical Works
SCADA Supervisory Control and Data Acquisition System
DG Set Diesel Generator Set
MW Mega Watt
MU Million units
Ha Hectare
MCM Million Cubic Metre
Deg. Degree
Min. Minute
Sec. Second
CM Construction management
QC Quality control
m meter
m3 Cubic meter
m3/sec Cubic meter per second
Km2 Square kilometre
Mcm Million cubic meter
TNWRD Tamil Nadu Water Resource Department
TANGEDCO Tamil Nadu Generation and Distribution Corporation
KWRD Kerala Water Resource Department
KSEB Kerala State Electricity Board
MPWRD Madhya Pradesh Water Resource Department
UJVNL Uttarakhand Jal Vidyut Nigam Limited
DVC Damodar Valley Corporation
Project Rehabilitation Report of H B Halli Dam
v | P a g e
DRIP Component Wise Project Cost
KaWRD Initial/Revised Projects & Cost
BACKGROUND
In April 2012, the Central Water Commission
(CWC) with assistance from the World Bank,
embarked upon a six year Dam
Rehabilitation and Improvement Project
(DRIP) at a preliminarily estimated initial cost
of Rs.2100 Crore targeting rehabilitation and
improvement of about 250 dams initially of
six, later of nine implementing agencies -
namely: MPWRD, OWRD, TNWRD,
TANGEDCO, KWRD, KSEB, KaWRD,
UJVNL and DVC.
In June 2018, the project was extended by
two years, until June 2020. The current
revised cost for DRIP is Rs.3466 Crore out of which Rs. 2920.5 Crore is allocated for
Component 1 (Rehabilitation and Improvement of Dams and Associated Appurtenances),
Rs.232.5 Crore for Component 2 (Dam Safety Institutional Strengthening), and Rs.313 Crore
for Component 3 (Project Management). Appropriate assistance is also provided under
DRIP to develop O & M Manuals and Emergency Action Plans (EAP) for these dams. The
project also promotes new technologies and improves institutional capacities for dam safety
evaluation and implementation at the Central and State levels as well as in some identified
premier academic and research institutes in the country. The actual total number of dams
under DRIP stands at 223.
The Implementing Agencies for DRIP are the Water Resources Departments and State
Electricity Boards in the participating States and Damodar Valley Corporation (DVC) with
Central Water Commission at Central Level. State Implementing Agencies are responsible
for implementation of works of dams under their charge. Co-ordination and management of
such works within a State rests with the
concerned State Project Management
Unit (SPMU). Overall project oversight
and coordination is carried out by Central
Project Management Unit (CPMU) headed
by the Project Director with assistance of
an Engineering and Management
Consultant.
Karnataka Water Resource Department
(KaWRD) joined DRIP in August 2014
with initial number of dams totalling 31.
Later, KaWRD dropped 9 dams and
continuing in DRIP with 22 dams.
Preliminarily estimated initial DRIP project
cost for KaWRD was Rs.276.1 Crore and
the revised actual current project cost is
Rs.581.2 Crore.
Project Rehabilitation Report of H B Halli Dam
vi | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
vii | P a g e
Table of Contents
Abbreviations .......................................................................................................... iii 1. EXECUTIVE SUMMARY .................................................................................. 1 2. PROJECT DETAILS ......................................................................................... 2
2.1 Project Description .......................................................................................................... 2
2.2 Project Location ............................................................................................................... 2
2.3 Project Benefits ................................................................................................................ 2
2.4 Dam and Reservoir Features (Before rehabilitation under DRIP) ............................... 3
2.5 Any Emergency Spillway, Fuse Plug etc. ...................................................................... 4
2.6 Details of previous dam incidents if any ....................................................................... 4
2.7 PST Details ....................................................................................................................... 4
2.8 DSRP, CPMU and World Bank Recommendations and Compliance ......................... 5
2.9 Scope of Rehabilitation Works as per PST ................................................................. 10
2.10 Drawings ......................................................................................................................... 11
3. DAM VISITS (PST STAGE) ............................................................................ 17 3.1 Dam Inspections ............................................................................................................ 17
3.2 Summary of observations made by CPMU ................................................................. 17
4. DESIGN FLOOD REVIEW (DFR) ................................................................... 17 4.1 DFR Outcome ................................................................................................................. 17
4.2 Brief Summary of Review.............................................................................................. 17
4.3 Recommendations ......................................................................................................... 17
5. REHABILITATION WORKS CARRIED OUT ................................................. 17 5.1 Summary of Investigations ........................................................................................... 17
5.2 Main Dam Works ............................................................................................................ 18
5.3 Basic facilities ................................................................................................................ 18
6. INSTRUMENTATION ..................................................................................... 19 6.1 List of existing instruments installed in dam and their condition ............................ 19
6.2 Details of new instruments installed ........................................................................... 19
6.3 CPMU Recommendations ............................................................................................. 19
7. PROCUREMENT OF WORKS ....................................................................... 20 7.1 Package wise details ..................................................................................................... 20
7.2 Details of Bidding process............................................................................................ 21
7.3 Reason for Variation, if any .......................................................................................... 21
7.4 Litigation / Arbitration, If Any ....................................................................................... 21
8. THIRD PARTY CONSTRUCTION SUPERVISION VISITS BY CPMU ........... 21 8.1 Summary of Visits undertaken ..................................................................................... 21
8.2 Summary of Third-party Material Testing .................................................................... 21
8.3 Summary of Major Recommendations ........................................................................ 21
8.4 Summary of Compliance by SPMU (As Received from Dam Authorties) ................ 25
8.5 Summary of any Special Visits made by CWC/World Bank/Expert Committee ...... 25
Project Rehabilitation Report of H B Halli Dam
viii | P a g e
8.6 Summary of Technical Assistance provided by CPMU ............................................. 25
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) 26 9.1 Basic Details ................................................................................................................... 26
9.2 Summary of Observations ............................................................................................ 26
9.3 Details of ESMF/EIA study (if any) ............................................................................... 26
10. OTHER NON-STRUCTURAL INTERVENTIONS ........................................... 26 10.1 Basic Details ................................................................................................................... 26
10.2 Summary of Observations ............................................................................................ 26
11. PENDING REHABILITATION WORKS .......................................................... 27 11.1 Details of pending works .............................................................................................. 27
11.2 Further course of action................................................................................................ 27
LIST OF FIGURES
Figure 2-1: Google Map of H.B.Halli Dam ........................................................................................ 11
Figure 2-2: Water Catchment Map of H.B.Halli Dam ....................................................................... 12
Figure 2-3: Layout Map of H.B.Halli Dam ......................................................................................... 13
Figure 2-4: Plan and Cross Section of Spillway …….…………………………………………............14
Figure 2-5: Longitudinal Section and Top View Plan of Dam ......................................................... 15
Figure 2-6: Cross-section of Earth Dam ........................................................................................... 16
LIST OF ANNEXURES
12. REFERENCES ............................................................................................... 27
Annex A: PST Approval Letter .............................................................................. 29 Annex B: Drawings issued for Rehabilitation measures .................................... 35 Annex C: Completion Certificate ........................................................................ 101
Annex D: Photographs Before and After Rehabilitation Works ....................... 105 Annex E: DBA and Inundation Maps .................................................................. 116
Project Rehabilitation Report of H B Halli Dam
1 | P a g e
1. EXECUTIVE SUMMARY
This Project Rehabilitation Report (PRR) is for HB Halli Pick up dam which is one of
the 22 dams under DRIP in Karnataka. The Dam Safety Review Panel (DSRP)
inspected the dam on 22nd September 2015 and recommended both structural &
non-structural measures to be taken up by the dam authorities.
The original design flood was 2650.43 cumec and the revised design flood (SPF)
under DRIP worked out to be 6721 cumec, which is more than twice of the original
design flood. Flood routing study carried out by CPMU as part of the dam break
analysis (DBA) shows that the existing spillway is not adequate, and the dam will be
overtopped for the revised design flood. Accordingly, structural, and non-structural
measures are necessary for ensuring dam safety.
DSRP main recommendations included improvement to earthen dam d/s slope
eroded sections; repair of rock toe and u/s slope revetment; removal of silt/debris
accumulated on spillway chute & repair to damaged part; dewatering and desilting of
the stilling basin; treatment of spillway body and joints to stop leakage and water jet;
repair of spillway glacis with high strength concrete; renovation of spillway gates,
hoist bridge and parapet wall; and RCC lining to approach channels of RBC and
LBC. Non-structural measures included review of design flood & check adequacy of
spillway, reservoir siltation surveys; dam stability analysis; preparation of EAP and
O&M manual.
Following DSRP recommendations, rehabilitation works carried out under DRIP
included:
Improvements to Earthen Dam and Rough Stone Revetment
Construction of Surface Drains on Earthen Bund of D/s slope
Grouting Treatment to Spillway gate No.10 and 5.of U/s and D/s,
Providing Painting to crest gates., hoist bridge and parapet wall
Construction of longitudinal open drain, rock toe and improvements to existing
close drains.
Dewatering the stilling basin and improvements to eroded / damaged draft
channel by providing and laying in-situ vibrated M-60 grade silica fume based
fibre reinforced cement concrete.
Providing Poly Ironite Ceramic Cementitious pointing to U/s piers, RBC and
LBC head sluices.
Providing cementitious treatment to D/s piers and training walls,
Improvements to intake canals of LBC and RBC.
Providing Turfing on downstream of the earthen dam.
The rehabilitation works were executed under a single package with a total
completion cost of Rs. 518.7 Lakhs. A variation of 47.39 Lakhs (supplemental
agreement minus saving) was registered due to change in scope of Works.
CPMU carried out dam break analysis and prepared inundation maps, which were
used by the SPMU to prepare Emergency Action Plan (EAP). The Emergency Action
Plan (EAP) prepared by SPMU was reviewed by CPMU and published.
SPMU also prepared O&M Manual as per guidelines published by Central Water
Commission, January 2018. The same was reviewed by CPMU and published.
Project Rehabilitation Report of H B Halli Dam
2 | P a g e
2. PROJECT DETAILS
The HB Halli Pick Up dam is located across Chikkahagari River near Malvi village of
Hagaribommanahalli taluk of Bellary district in Karnataka state. It was completed in
the year 1971. The water catchment area at the dam site is 2346.54 Km2.
The dam is having left and right earthen dam with central masonry/concrete ogee
spillway. The left bank earthen dam is 341.40m long and the right bank earthen dam
1143.60 long. The spillway dam is 121.90 m long with 10 nos. of vertical lift gates
having discharge capacity of 2,650.43 cumec. The TBL, FRL, original MWL and
Spillway Crest level are at EL 527.9 m, 525.78 m, 525.78 m, and 519.68 m,
respectively. The gross storage capacity at the FRL of 525.78 m is 56.64 MCM.
2.1 Project Description
Sl. No.
Item Details
a. Project Identification Code (PIC) KA06MH0087
b. Project Name Hagaribommanahalli Pick Up Dam
c. River Basin Krishina
d. Sub River Basin Chikkahagari
e. River/Stream Chikkahagari
f. Catchment area (km2) 2346.54sq.km
g. Year of commencement of project 1959
h. Year of completion of project 1971
2.2 Project Location
Sl. No.
Item Details
a. State Karnataka
b. District Bellary
c. Earthquake Zone II
d. Survey of India Map Ref No’s 57 A/4
e. Nearest City Hagaribommanahalli
f. Nearest Airport JIndal airport, Toranagallu.
g. Nearest Railhead Ghanagapur
h. Name of Immediate U/S Project Bhadra Project
i. Name of Immediate D/S Project Tungabhadra Project
j. Latitude in Deg., Min, Sec. (North) 14º59’52”
k. Longitude in Deg., Min, Sec. (East) 76º11’22”
2.3 Project Benefits
Sl. No. Item Details
a. Type of Project Irrigation
Project Rehabilitation Report of H B Halli Dam
3 | P a g e
Sl. No. Item Details
b. Gross Command Area (Ha) 4735
c. Culturable Command Area (Ha) 4037
d. Annual Irrigation Potential (Ha) 2965
e. Hydropower –
Installed Capacity (MW) Nil
f. Hydropower –
Firm Power (MW) Nil
g. Hydropower –
Average Annual Generation (MU) Nil
h. Domestic/Municipal/Industrial Water –
Annual Quantum (MCM) Nil
i. Domestic/Municipal/Industrial Water –
Area and Population Benefitted Nil
j. Flood Protection –
Flood Protected Area (Ha) Nil
k. Flood Protection –
Details of Area Benefitted Nil
l. Details of Tourism/Recreational Facilities Nil
2.4 Dam and Reservoir Features (Before rehabilitation under DRIP)
Sl. No.
Item Details
a. Full Reservoir Level (m) 525.78
b. Original Maximum Water Level (m) 525.78
c. Gross Reservoir Storage Capacity at FRL (519.60m) (Mm
3 )
56.64
d. Live Storage Capacity (Mm3 ) 49.56
e. Revised Live Storage Capacity, if any
(Mm3 )
-
f. Date of bathymetric survey, if any -
g. Dam Type Composite - Left and Right bank earthen dam with Central masonry/concrete spillway
h.
Length of Dam at Top (m)
i) Total length of the main dam
ii) Length of embankment dam
iii) Length of masonry/concrete dam
1606.90
1485
121.90
i. Number and length of dykes (No. & m) --
j. Top of dam (El. in m.) 527.9
k. Top Level of Upstream Parapet Wall of main dam (El. in m.)
NA
Project Rehabilitation Report of H B Halli Dam
4 | P a g e
Sl. No.
Item Details
l.
Height of Dam (m)
i) Embankment dam – above river bed level (up to dam top without camber)
ii) Concrete/Masonry dam – above deepest foundation level (up to dam top)
15.56
16.06
m Top width of main dam (m) 3.65
n. Spillway details
i) Location Middle (CH 990.60m to 1112.50 m)
ii) Type of spillway Ogee, chute spillway with vertical lift gates
iii) Length of spillway (m) 121.90
iv) Spillway crest level (m) 519.68
v) Type of Gate Vertical Lift Gates
vi) Number and size of gates (no. and
m. x m.) 10, 9.15 X 6.10
vii) Number and thickness of piers (no.
and m. x m.) 9, NA
o.
Outlet/Sluice details
i) In Embankment dam
Number
Size (Width (m). x Height (m).)
Location
Invert level El. (m)
Discharging capacity (m3/s)
ii) In Concrete/Masonry dam
Number
Size (m. x m.)
Location
Invert level El. (m)
Discharging capacity (m3/s)
2 (LBC and RBC)
1.20 x 1.20 and 1.20 x 1.20
Chainage 853 m and Chainage1935 m
519.38 and 519.38
2.12 and 2.46
Nil
Note: All elevations are above MSL
2.5 Any Emergency Spillway, Fuse Plug etc.
Nil
2.6 Details of previous dam incidents if any
Nil
2.7 PST Details
Sl.
No. Item Date/Cost Remarks
a. PST first received from SPMU December 2015
b. Proposed PST Cost (INR in Lakhs) 471.00
Project Rehabilitation Report of H B Halli Dam
5 | P a g e
c. First review by CPMU 22.04.2016
d. Final review by CPMU 22.04.2016
e. World Bank Approval 12.05.2016 E- mail dated 12.05.2016
f. Approved PST Cost (INR in Lakhs) 471.00
2.8 DSRP, CPMU and World Bank Recommendations and Compliance
2.8.1 DSRP Recommendations and Compliance (As Received from Dam Authorities)
Sl. No
Review and Recommendations of DSRT
Compliance by the project
authorities.
FLOOD HYDROLOGY, ADEQUACY OF SPILLWAY CAPACITY, RESERVOIR,OPERATION DURINGFLOODS AND RESERVOIR SEDIMENTATION
1.
Verify the adequacy of the Spillway capacity
provided to deal with SPF which is already
determined subject to approval by CWC, New
Delhi and the existing free board for the dam
based on “Saville”s method and take
corrective measures accordingly.
The work of Conducting study under
action plan for implementation of
National water policy 2002 and
technical preparedness for DDSA-2002.
has been entrusted to WAPCOS, New
Delhi vide work order No. 2097 dated.8-
12-2014 and the same is included in
the study.
2.
Carryout Hydrographic surveys (IBS) of the
reservoir periodically for determination of
extent of reservoir sedimentation in dead and
live storage portions to assess extent of loss
of storage and consequent reduction in the
annual benefits to help formulate schemes for
minimization of rate of sedimentation such as
adoption of watershed management
techniques like contour
bonding, provision of gully traps, anti-soil erosion measures, etc.
------------Do------------
3
The reservoir operation schedules should be
developed and updated for the existing
capacity of the reservoir after siltation
adopting the procedure outlined in IS 7323 –
1994 or its latest
version.
------------Do------------
4.
It is necessary to carry out surveys of river
valley on the downstream of the dam and
mark contours of different elevations to
enable to demarcate the flood zoning
suggested below.
------------Do------------
5.
The Department should prepare necessary
inundation maps of the downstream valley
showing flood contours of different intensities
duly demarcating “Prohibited Zone”,
“Restricted Zone” and “Caution Zone” to avert
possible hazards to life and property
during release of floods over the spillway.
------------Do------------
6.
The Department should prepare Emergency
Action Plan including suitable communication
system of flood forewarning to the habitants
living downstream of the dam within the zone
------------Do------------
Project Rehabilitation Report of H B Halli Dam
6 | P a g e
Sl. No
Review and Recommendations of DSRT
Compliance by the project
authorities.
prohibited
for dwelling.
7.
Determine Economic life of the reservoir by
assessing loss of revenue by reduction in the
annual benefits owing to sedimentation
periodically.
------------Do------------
8.
Install infra-red based automatic digital water
level recorder and provide necessary access
to the same from top of dam to observe and
record the water levels in the reservoir
correctly and maintain the records which are
very important to evaluate the performance
of dam and carry out reservoir operations.
Action will be accordingly.
GEOLOGY OF DAM SITE AND FOUNDATION TREATMENT
1.
As verified from the details the masonry dam
and spillway structures are constructed on
stable rock formations and necessary
foundation treatment have been carried out at
the time of construction. As such there are no
specific remedial measures considered
necessary for the spillway dam at present
from the geological point of view. However
the treatment provided to the
foundation of the right bank earth dam in the gorge portion where sandy strata is met with for considerable depth is found to be inadequate and needs further treatment to be evolved after carrying out sub-surface investigations and consultations with ground water hydrologists as mentioned in Para 2.5.1.3 below. Further treatment to arrest foundation seepage should be provided Accordingly and its efficacy monitored periodically.
The work is being carried out in
consultation with CWPRS, Pune.
2.
It is suggested to continue to measure,
monitor and record the seepage with
reference to the reservoir level and maintain
records and also plot the data in graphical
form before and after
foundation treatment recommended at item 1 above.
Noted and action is taken on the matter
3.
The dam site is located in the seismic zone –
II and is prone to earthquakes. Necessary
steps may be taken to strengthen the dam
sections under seismic conditions if stability
analysis so warrants.
The work of Conducting study under
action plan for implementation of
National water policy 2002 and
technical preparedness for DDSA-2002.
has been entrusted to WAPCOS, New
Delhi vide work order No. 2097 dated.8-
12-2014 and the same is
included in the study.
STRUCTURAL STABILITY ANALYSIS OF DAM
Earthen dam
Project Rehabilitation Report of H B Halli Dam
7 | P a g e
Sl. No
Review and Recommendations of DSRT
Compliance by the project
authorities.
1.
Check the adequacy of the earthen dam
sections provided, by carrying out stability
analysis for different conditions of loadings
including seismic loadings stipulated in IS
1893: 2002 and other relevant IS codes, by
adopting seismic coefficients applicable to the
dam site as per the revised seismic map of
the country by contacting CWC / GSI and
check the stability of the dam.
The work of Conducting study under
action plan for implementation of
National water policy 2002 and
technical preparedness for DDSA-2002.
has been entrusted to WAPCOS, New
Delhi vide work order No. 2097 dated.8-
12-2014 and the same is
included in the study.
2.
The downstream embankment appeared to be
steep which needs to be checked with the
design profile and any deficiency should be
made good.
Action will be taken accordingly
3.
The rain cuts and gullies formed on the
downstream slope of both right bank and left
bank earthen dams should be repaired and
necessary turfing should be provided on the
downstream slope to
prevent rain cuts and gives stability to earthen dam.
Completed under DRIP work
4.
The provision or otherwise of the rock toe at the downstream toe
should be checked and initiate necessary action if not provided.
Completed under DRIP work
5.
Reasons for providing concrete mat at the
junction of the spillway with earthen
embankment on the left flank between Ch.
975 m (Ch32) and Ch. 990 m (Ch. 32.50)
where transverse crack was seen during the
inspection of DSRP in 2003 should be
investigated.
Noted and action will be taken on the matter.
6.
Investigate the cause of transverse crack
developed at Ch. 36.50 which extends to the
full width of the concrete mat by opening a pit
near the top edge on the downstream side
and by extracting undisturbed samples at
about 2-3 m depth and tests conducted to
evaluate the consolidation characteristics such
as compression index, co-efficient of
consolidation, Atterberg limits and in-situ
density etc.
Noted and action will be taken on the
matter.
7. Verify the provision or otherwise of the rock toe up to Ch. 42 of
Completed under DRIP work.
right bank earth dam. The reasons for
terminating the rock toe in the right bank
earthen dam on the right side sluice should
be verified and provided accordingly if not
provided.
Completed under DRIP work.
Project Rehabilitation Report of H B Halli Dam
8 | P a g e
Sl. No
Review and Recommendations of DSRT
Compliance by the project
authorities.
8.
Initiate necessary action to revive the
Piezometers which have become dis-
functional now under the consultation and
guidance of CWPRS. The terminal building
should also be repaired with necessary
appurtenances to measure the pore pressures
and maintain the records which are important
for evaluating the performance of earthen
dam sections.
Action will be taken on the matter.
9.
Install few electrical piezometers at the
following locations in the deepest portion of
earth dam, in the downstream casing zone
above cross drains upstream of rock toe at
Ch. 1200 m, Ch. 1240 m, Ch. 1300 m, Ch.
1350 m and monitor pore pressures at
different reservoir levels.
Action will be taken on the matter.
10.
Install open ended stand pipes immediately
below the rock toe at the above chainage and
another row of pipes about 60 m below the
upper row and monitor water levels in the
stand pipes at
different reservoir levels periodically
Action will be taken on the matter.
Spillway, Draft channel and Stilling Basin
11.
The condition of spill way chute channel
should be inspected by the project engineers
after clearing silt/debris accumulated over it
and any erosion damages that have occurred should be repaired.
Completed under DRIP work
12.
Trees and vegetation grown at few places on
the water face of the training walls
constructed on both ends of draft channel
should be uprooted to ensure safety of walls.
Trees and vegetation grown at few places are cleared.
13.
The stilling basin provided at the end of the
chute which was under water should be
dewatered and inspection done periodically to
examine the condition of the basin under dry
condition and any erosion damages that have
occurred should be repaired for smooth
functioning.
Dewatering work is completed under DRIP work and the inspection is done periodically under dry condition.
14.
Reasons for appearance of water jets in the
spillway body wall above the crest level of the
spill way in bay No 10 should be investigated
and suitable treatment initiated.
Completed the work of arresting seepage under DRIP work.
15.
Reasons for sprouting of water at concrete
joints at RL 523 m to 525 m at gate No 10, in
the center of the span and 2.00 m below the
crest should be investigated and suitable
treatment initiated.
Completed the work of arresting seepage under DRIP work.
16.
All the scours developed in the downstream
glacis shall be repaired with high grade
concrete adopting procedure outlines in
Item 18 of Para 2.5.6 above.
Completed the work of arresting seepage under DRIP work.
Project Rehabilitation Report of H B Halli Dam
9 | P a g e
Sl. No
Review and Recommendations of DSRT
Compliance by the project
authorities.
17.
Check the adequacy of the sections provided
for over flow sections by carrying out stability
analysis for different conditions of loadings
including seismic loadings stipulated in IS
1893: 2002 and other relevant IS codes, by
adopting seismic coefficients applicable to the
dam site as per the revised seismic map of
the country by contacting CWC / GSI and
check the stability of the dam.
The work of Conducting study under
action plan for implementation of
National water policy 2002 and
technical preparedness for DDSA-2002.
has been entrusted to WAPCOS, New
Delhi vide work order No. 2097 dated.8-
12-2014 and the same is included in
the study.
Irrigation sluices
18.
The exact location of water jets appearing in the wall of the staining of right bank sluice well should be identified and repaired by suitable treatment
Completed under DRIP work
19.
The sluice structures should be properly barricaded all-round and
at top to prevent hoists and its accessories
from unauthorized tampering.
Completed under DRIP work
20.
The foot bridges provided for accessing the control structure of left and right bank sluices should be strengthened suitably with provision of protective railings on either sides.
Completed under DRIP work
21. Trash racks should be provided on the upstream of sluice vents to prevent entry of floating objects and blocking the sluice vent.
Completed under DRIP work
22.
The silted approach channel of left bank
sluice vent should be cleared. To avoid the
possibility of accumulation of silt in future
construction of a masonry approach channel
and provision of trash racks should be taken
up.
Completed under DRIP work
MAINTENANCE AND PERFORMANCE OF SPILLWAY GATES, OUTLET SLUICE GATES AND HOISTS
1.
The standby generator should be kept
functional to enable operation of the gates
even in the event of power shutdowns.
Yes ,noted
2.
Gate operations and maintenance should be
done as per the maintenance manual
supplied by the suppliers of the gates and
hoists and also as laid down in IS 7718 –
1991 and also detailed guidelines with check
list for inspection and maintenance of
Spillway Gates brought out by Water
Resource Department, Government of
Karnataka.
Action will be taken accordingly
3 The gates and hoisting mechanism should be
maintained periodically by painting, oiling, greasing, etc.,
Painting, oiling and greasing completed under DRIP work.
4 The electrical problem in Gate No. 7 should be
attended immediately. Completed under DRIP work
2.8.2 CPMU/World Bank Recommendations and Compliance
Nil
Project Rehabilitation Report of H B Halli Dam
10 | P a g e
2.9 Scope of Rehabilitation Works as per PST
Remedial Measures (Structural)
Providing Grouting and pointing to U/S side piers, RBC & LBC head sluice walls.
Providing pointing to D/s, piers, training walls.
Dewatering the Stilling basin and improvements to eroded/damaged portion of
stilling basins and draft chute channel.
Providing R CC lining to approach channels of RBC and LBC of.
Construction of longitudinal Open drain, rock toe and improvements to existing
close drains of earthen embankment.
Providing Turfing to D/s Earthen Embankment.
Providing painting, oiling ,gracing to crest gate and head sluice assembly,
painting to hoist bridge and
Parapet wall, replacement of warns out rubber seals.
Providing Barricading, Re- construction of Foot bridges, supplying and fixing
Trash racks to LBC and RBC head sluices.
Supplying and fixing Entrance and exit gates, WELCOME boards, and security.
Non-structural Measures
Dam Instrumentation L.S
Supplying and fixing infra-red based automatic digital water level recorder LS.
Basic Facilities Enhancement
Supplying and fixing of new panel board, and improvements to electrical system.
Providing electrification to earthen dam.
Providing CCTV cameras.
Providing FIRE extinguisher arrangements.
Providing Bolero Vehicle.
Project Rehabilitation Report of H B Halli Dam
11 | P a g e
2.10 Drawings
Figure 2-1: Google Map of H.B. Halli Dam
Project Rehabilitation Report of H B Halli Dam
12 | P a g e
Figure 2-2: Water Catchment Area Map of H.B. Halli Dam
Project Rehabilitation Report of H B Halli Dam
13 | P a g e
Figure 2-3: Layout Plan of H.B. Halli Dam
Project Rehabilitation Report of H B Halli Dam
14 | P a g e
Figure 2-4: Plan and Cross Section of Spillway
Project Rehabilitation Report of H B Halli Dam
15 | P a g e
Figure 2-5: Longitudinal Section and Top View Plan of Dam
Project Rehabilitation Report of H B Halli Dam
16 | P a g e
Figure 2-6: Cross-section of Earth Dam
Project Rehabilitation Report of H B Halli Dam
17 | P a g e
3. DAM VISITS (PST STAGE)
3.1 Dam Inspections
Sl. No.
Item Date of visit Remarks
a. Dam Safety Review Panel (DSRP) 22.09.2015
b. Site Visit made by CPMU experts --
3.2 Summary of observations made by CPMU
Nil.
4. DESIGN FLOOD REVIEW (DFR)
4.1 DFR Outcome
Sl. No.
Item Original
Value
Revised
Value Remarks
a. Inflow Design Flood (m3/s) 2650.47 6721 SPF
b. Spillway Capacity / Routed Outflow (m
3/s)
-- 5423*
c. Maximum Water Level (m) 525.78 528.59* TBL = 527.91
*Based on flood routing carried out by CPMU as part of DBA analysis.
4.2 Brief Summary of Review
The original design flood was 2650.43 cumec and the revised design flood (SPF) under DRIP
worked out to be 6721 cumec, which is more than twice of the original design flood. Flood
routing study carried out by CPMU as part of the dam break analysis (DBA) shows that the
existing spillway is not adequate, and the dam will be overtopped for the revised design flood.
Accordingly, structural, and non-structural measures are necessary for ensuring dam safety.
4.3 Recommendations
Structural measures – To be further examined by SPMU.
Non-structural measures – EAP.
5. REHABILITATION WORKS CARRIED OUT
5.1 Summary of Investigations
Sl. No.
Item Details Remarks
a. Geo-Physical Investigations
Nil
b. Geo-Technical Investigations
Nil
Project Rehabilitation Report of H B Halli Dam
18 | P a g e
5.2 Main Dam Works
Sl. No.
Item Details Remarks
a. Works from hydrological angle Review of design flood and flood routing
Design flood Completed but Flood Routing
Not Completed
b. Resetting of disturbed upstream pitching (rip-rap)
Improvements to Earthen Dam and Rough Stone Revetment
Completed
c. Repairs to d/s toe drains, provision of V-Notches for seepage measurements
Construction of Surface Drains on Earthen Bund of D/s slope
Completed
d. Work on Downstream of Embankment
Repairs / provision of d/s rock toe.
Provision for d/s turfing
Completed
e. Repair of Spillway (from seepage control and stability angle)
Grouting Treatment to Concrete dam
Providing cementatious pointing to D/s piers and training walls,
Dewatering the stilling basin and improvements to eroded / damaged draft channel by providing and laying in-situ vibrated M-60 grade silica fume-based fibre reinforced cement concrete
Completed
f. Repair of Outlet Structure (from seepage control and stability angle)
Improvements to intake canals of LBC and RBC
Providing Poly Ironite Ceremic Cementatious pointing to U/s piers, RBC and LBC head sluices.
Completed
g. Hydro-mechanical works
i) Main spillway gates & hoists
Providing Painting to Radial Crest Gates, Stop Log Gates and Overhauling and Maintenance of Radial Crest Gates, Stop Log Gates and Gantry crane
Completed
ii) Outlet gates & hoists Restoration of RBC Sluice Gate
Completed
h. Other miscellaneous works d/s of embankment dam
Providing and Fixing Ladder to Crest Gates on Dis Side including Hand Railing and to Catwalk, Drain Holes, Platform, Trash Rack for
Completed
5.3 Basic facilities
S/N Item Details Remarks
a. Roads Construction of MSS Road
on Dam Bund Top Completed
Project Rehabilitation Report of H B Halli Dam
19 | P a g e
6. INSTRUMENTATION
6.1 List of existing instruments installed in dam and their condition
V notch is fixed at gorge portion on the right-side d/s of earthen embankment and it is in good
condition. Automatic water level recorder (gauge reading instrument) is yet to be installed.
6.2 Details of new instruments installed
Nil
6.3 CPMU Recommendations
Nil
Project Rehabilitation Report of H B Halli Dam
20 | P a g e
7. PROCUREMENT OF WORKS
7.1 Package wise details
Work Package No.
Name of Works
Estimated Cost
(INR in Lakhs)
Procurement
Method
Invitation for bids / NIT Issue
date
Pre-Bid Meeting
date
Bid Opening
date
Contract Agreement
No.
Contract Agreement
date
Contractor’s Name &
Address
Scheduled
Duration (Months)
Scheduled Completio
n date
Actual Date of
Completion
Contract / Award
Value (INR in Lakhs)
Completion Cost (INR in Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1
Rehabilitation and Improvement to
Hagaribommanahalli Pick Up dam
under World bank aided DRIP programme.
401.00 NCB 01.12.16 13.12.16 20.12.16 32/2016-17 25.03.17
Sri. S.NarayanaReddy, Class –
I Contractor,Na
gasamudra road,
Chennaraya Patna, Hasan
Dist
12 24.03.18 17.01.19 471.32 518.71
Total 471.32 518.71
Project Rehabilitation Report of H B Halli Dam
21 | P a g e
7.2 Details of Bidding process
As per details in the above table.
7.3 Reason for Variation, if any
SPMU reported an overall variation of 47.39 Lakhs (supplemental agreement minus
saving) due to change in scope of Works during construction.
7.4 Litigation / Arbitration, If Any
No litigation.
8. THIRD PARTY CONSTRUCTION SUPERVISION VISITS BY
CPMU
8.1 Summary of Visits undertaken
Sl. No. Date of visit Transmittal details of CSV Report
a. 29-8-2017 5106/10-10-2017
b. 8-12-2017 5424/ 09-01-2018
c. 1-2-2018 5702/28-03-2018
d. 24-5-2018 6185/06-08-2018
8.2 Summary of Third-party Material Testing
Nil.
8.3 Summary of Major Recommendations
1st Construction Site Visit Report
Observations:
Undulations observed on the downstream slope of the embankment between
chainage Ch. 1320.00 m to 1450.00 m. needs to be rectified before taking up
turfing.
The downstream slope of earthen embankment between Ch. 1400 m & 1500 m
(Gorge portion) slopes gradually for about 25 m length (Along profile) and
suddenly it has become steeper. This change in grade needs to be level
surveyed to ensure the embankment meets design lines and grades. This
condition was pointed out by the DSRT during their inspection of the dam
There is no provision in the contract for a longitudinal drain on the crest of the
dam and runoff will freely flow over the dam and expose the embankment to
erosion. In addition, the new chute drains being constructed have no lead-in
channel to for collecting runoff and do not extend to the toe drain to allow safe
flow of runoff any runoff. This neglected item in the agreement needs to be
taken up as soon as possible to ensure the efficacy of the embankment and
chute drains works being carried out.
Recommendations:
DSRP recommended to check the adequacy of the earthen dam section
provided by carrying out stability analysis for different loading condition. It
Project Rehabilitation Report of H B Halli Dam
22 | P a g e
stated that the work has been entrusted to WAPCOS. CPMU recommends that
the actual sections existing at the site may be surveyed and stability analysis
shall be carried out as the 2.44-meter-wide berm at EL 519.1-meter as
indicated in the construction drawing is not visible at site.
DSRP noticed that the D/s slope appears to be too steep which needs to be
checked with design profile and deficiency should be made good.
2nd Construction Site Visit Report
Observations:
The spillway bridge slab is in a dilapidated condition as the reinforcement has
exposed at bottom of beams of bridge at many locations. Reinforcements are
exposed at centre and at support of the beam vulnerable for failure if further
disintegration of concrete continues. Immediate corrective measures to repair
the same is needed for safety of the bridge.
The construction drawing of earthen embankment depicts a berm of 8-ft. width
at EL 1703.00-ft. at downstream slope. But at site it is not visible. CPMU
recommends a geodetic survey of the actual profile tied to local benchmarks be
taken up for the record. CPMU recommends a stability analysis of the existing
section of the earthen embankment be conducted to document existing
conditions.
Water jetting and seepage observed at the toe of the spillway glacis of Bay No.
10. Remedial measures for arresting foundation uplift pressures is to be taken
up. (Remedial measure to be taken is brought in “other observations and
remarks” below).
Recommendations
DSRP recommended to check the adequacy of the earthen dam section
provided by carrying out stability analysis for different loading condition. It
stated that the work has been entrusted to WAPCOS. CPMU recommends that
the actual sections existing at the site may be surveyed and stability analysis
shall be carried out as the berm at EL 1703’ as indicated in the construction
drawing is not visible at site.
DSRP noticed that the D/s slope appears to be steep which needs to be
checked with design profile and deficiency should be made good.
3rd Construction Site Visit Report
Observations:
Undulations observed on the downstream slope of the embankment; during
turfing operations, these undulations can be corrected using suitable,
turfing/seeding soils and compacted by tamping. Watering of seed and or turf
should be by light sprinkling daily for 7 days or until seeding sprouts.
The downstream slope of earthen embankment between Ch. 1400 m & 1500 m
(maximum section) slopes gradually for about 25 m length (Along profile) and
suddenly it has become steeper. This change in grade needs to be level
surveyed to ensure the embankment meets design lines and grades; this is a
pending deficiency that requires immediate attention to bring physical progress
forward.
Downstream kerbing has been taken up to direct runoff into chute drains; this
will require proper camber on the new crest road to redirect runoff into the new
chute drains.
Recommendations
Project Rehabilitation Report of H B Halli Dam
23 | P a g e
DSRP recommended to check the adequacy of the earthen dam section
provided by carrying out stability analysis for different loading condition. It
stated that the work has been entrusted to WAPCOS. CPMU recommends that
the actual sections existing at the site may be surveyed and stability analysis
shall be carried out as the 2.44-meter-wide berm at EL 519.1-meter as
indicated in the design drawings is not visible at site (pending).
DSRP noticed that the D/s slope appears to be too steep which needs to be
checked with design profile and deficiency should be made good (pending).
4th Construction Site Visit Report
Observations:
Undulations are still observed on the downstream slope of the embankment;
during turfing operations, these undulations to be corrected using suitable,
turfing/seeding soils and compacted by tamping. Watering of seed and or turf
should be by light sprinkling daily until seeding is well-rooted.
The downstream slope of earthen embankment between Ch. 1400 m & 1500 m
(maximum section) slopes gradually for about 25 m length (Along profile) and
suddenly it has become steeper. This change in grade needs to be level
surveyed to ensure the embankment meets design lines and grades; this is a
pending deficiency that requires attention to bring physical progress
successfully forward.
Downstream kerbing has been taken up to direct runoff into chute drains; this
requires proper camber on the new crest road to redirect runoff into the new
chute drains. Though the outfall openings are adequate, the quality of the work
is poor with evidence of inadequate formation of the kerb footing and placement
of the shutters; concrete has run out of the bottom of the shuttering.
Previous Observations and Compliance:
Sl. No.
Observation / Deficiency Remarks
1 Cross drains are stopped short of revetment at Toe (Fig-14)
Must be extended to toe revetment to avoid erosion of earthen embankment between toe revetment & edge of the cross drain
2
Cross drains are provided at D/s slope for 400-m length of earthen dam at 20-m C/c out of 1600-m length. (right Flank only)
To avoid flow of water on entire length of D/s slope and causing erosion formation of rain cuts it is recommended to provide cross drains for remaining length of earthen embankment provided availability of funds.
3 Longitudinal drain at top of earthen crest or kerb towards D/s edge is not provided (Fig-19)
A small 150-mm-high kerb wall has been constructed tying in all the old stone guard posts.
4
The berm of 8’feet (2.44-m) as shown in the drawing of earthen dam section in downstream slope is not visible at site (Fig-20)
Requires geodetic survey taking 30-meter sections of the earthen embankment for input in to a stability analysis for different loading conditions. Embankment soil engineering properties also need to be determined details to be intimated to CPMU
5 Reinforcement exposed at bottom of beam of spillway bridge (Fig-23 to 29)
The bridge concrete has disintegrated at number of locations and reinforcing has got exposed considerably. (see photos) Further
Project Rehabilitation Report of H B Halli Dam
24 | P a g e
Sl. No.
Observation / Deficiency Remarks
disintegration may endanger safety of the structure. Therefore, remedial measures to strengthen the beams is to be taken up in consultation with IISc. or CWPRS.
6
There was no water in the reservoir and the hence disturbance of revetment at heel could be noticed between Ch. 1310 m & 1650 m, 1290 m & 1230 m
Concrete cut off wall at the heel may be required to support the revetment at the heel to avoid dislodging of some of the stones during reservoir filling.
7 Housekeeping needs improvement
Construction debris and general clean-up of the downstream slopes, upstream areas around the spillway sections and the crest road is required.
8 Shuttering and alignment of downstream kerb poor
Kerb walls require adjustment of alignment. Leakages on the d/s side of the kerb wall is seen at ground level.
9 Turfing of the d/s slope was taken up by seeding only.
Seeding on the downstream face is not adequately taking root. Additional resources for re-seeding and sprinkling of the downstream slope must be intensified to ensure the grasses take root before heavy rains and high potential for erosion rills to form.
10 Vegetation management is poor
Additional resources are necessary to maintain the dam needs to be taken up. Shrubs and grasses on the upstream slope are obscuring inspections of the slopes during high flood events. Shrubs also create long roots that invade the embankment and open potential seepage paths.
11 Livestock on embankment Fencing of the embankment is necessary to minimize erosion of the downstream slopes.
12
Soil used for downstream slope is clumpy and has accumulated at near the downstream toe. BOQ Quantities are not measured in-situ but be delivery only.
CPMU recommends that measurement of suitable soil be measured in place. All soil delivered to the site must be sieved before casting on embankment. Depths of soil must be constantly measured to ensure uniformity before seeding and compacting.
13 The crest road is undulated and full of ruts.
CPMU recommends that re-grading and installation of the sealed road to be installed meets all design lines and grades and is correctly cambered for drainage to the d/s side of the embankment.
14 Downstream piers raking & pointing has missing mortar
Contractor to re-rake lower sections of the piers where mortar is missing and or cracked and repoint with non-shrink, UV resistant cementitious mortars
Project Rehabilitation Report of H B Halli Dam
25 | P a g e
8.4 Summary of Compliance by SPMU (As Received from Dam Authorties)
The CPMU observed that spillway bridge slab is in dilapidated condition as the
reinforcement is exposed along the bottom of the beams at many locations.
Reinforcements are also exposed at centre supports of the beam the beams exposed to
possible failure if further disintegration continues. immediate corrective measures to
repair the beams necessary for the safety of the bridge. The SPMU has taken up the
Repair work to the exposed beams of the spill way bridge under EFI of Drip work.
The design drawing of earthen embankment depicts a berm of 2.44-meters width at EL
519,1-meters at downstream slope. But at the site, this bench it is not visible. CPMU
recommends a level survey of the actual profile tied into approved benchmarks for control
be conducted for input into a stability analysis of the existing section. The geodic survey
will be conducted in consultation with KERS, Mysore for the actual profile of the earthen
embankment.
Undulations observed on the downstream slope of the embankment between chainage
Ch. i320.00 m to 1450.00 m. needs to be rectified before taking up turfing.
Undulations have been rectified before taking up Turfing.
The CPMU observed that the downstream slope of earthen embankment between ch.
1400 m & is 0.00 m (Gorge portion) slopes gradually for about 25 m length (Along profile)
and suddenly it has before steeper. The change in grid needs to be level surveyed to
ensure the embankment meets design lines and grades. This condition; was pointed out
by the DSRT during their inspection of the dam. In this regard, Level survey will be
conducted in consultation with the KERS, Mysore to ensure that the embankment meets
design lines and grades.
CPMU observes that there is no provision in the contract for a longitudinal drain on the
crest of the dam and runoff will free TV flow over the dam and expose the embankment to
erosion. In addition, the new chute drains beino constructed have no lead-in channel to
for collecting runoff and do not extend to the toe drain to allow saf6 flow of runoff any
runoff. This neglected item in the agreement needs to be taken up as soon as possible to
ensure the efficacy of the embankment and chute drains works being carried out. SPMU
in this regard, constructed Kerb wall / Parapet wall on both left and right side of the
earthen embankment to flow runoff water freely from the top of the dam through chute
drains. Kerb walls are constructed for the entire length of the embankment and chute
drains are extended up to the bottom toe. These works are carried out under EFI of DRIP
work.
CPMU observed Water jet and seepage at the toe of the spillway glacis of Bay No.10.
Remedial measures for arresting foundation uplift pressures is to be taken up. Cement
grouting work is done by the agency on upstream and downstream of the spill way
portions of gate No.10 and 5 of Hagaribommanahalli pick up dam. Holes are drilled for a
depth of 3’ @ 1m c/c. Upstream side spill way portion is opened by excavation for a depth
of 6 feet and honey comb and open joint portions are closed by plastering and pointing
and it is observed that leakage has been completely arrested on the spillway portions of
gate 10 and 5.
8.5 Summary of any Special Visits made by CWC/World Bank/Expert
Committee
Nil
8.6 Summary of Technical Assistance provided by CPMU
Review of PST. Review of design flood.
Provided technical guidance on maintaining quality of works as per design, contract agreement technical specification and best engineering practices.
Carry out dam break analysis and prepare inundation maps.
Review O&M manual.
Project Rehabilitation Report of H B Halli Dam
26 | P a g e
Review of EAP.
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT
FRAMEWORK (ESMF)
9.1 Basic Details
Sl. No.
Item Yes / No Remarks
a. ESMF Issue Identified in PST Yes
b. Mitigation Measures Proposed Yes
c. Any Rehabilitation and Resettlement involved No
d. Site Visit Date of CPMU E&S Specialists -
e. Site Visit Report of CPMU E&S Specialists -
9.2 Summary of Observations
ESMF management during implementation was generally satisfactory but PPE was
sometimes unused during construction.
9.3 Details of ESMF/EIA study (if any)
Nil.
10. OTHER NON-STRUCTURAL INTERVENTIONS
10.1 Basic Details
Sl. No.
Item Yes / No Remarks
a
Emergency Action Plan (EAP)
(i) EAP Available at Site
(ii) EAP Prepared under DRIP
(iii) EAP Published
(iv) Stake holder consultations
Yes
Yes
Yes
No
DBA carried out and inundation maps prepared by CPMU. Based on this the SPMU prepared EAP which was reviewed by CPMU and Published.
b. O&M Manual availability Yes O&M manual prepared as per DRIP guideline, reviewed by CPMU, and published.
c. Inflow Forecasting No
d. DHARMA Implementation Yes In progress. most data uploaded.
e. Siren No To be procured.
10.2 Summary of Observations
Nil
Project Rehabilitation Report of H B Halli Dam
27 | P a g e
11. PENDING REHABILITATION WORKS
11.1 Details of pending works
i. Stakeholder meeting for EAP.
ii. Completion of data entry in DHARMA.
iii. Flood routing study, planning structural and non-structural measures to
accommodate the revised design flood.
11.2 Further course of action
All pending actions stated above should be completed before closing of DRIP
Project.
12. REFERENCES
i. PST
ii. DSRP report
iii. Construction site visit report.
iv. Information received from SPMU from time to time
v. Completion Certificate.
vi. World Bank approval
vii. Compliance letters from SPMU.
viii. Inundation report and maps.
ix. O&M manual
Project Rehabilitation Report of H B Halli Dam
28 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
29 | P a g e
Annex A: PST Approval Letter
Project Rehabilitation Report of H B Halli Dam
30 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
31 | P a g e
Project Rehabilitation Report of H B Halli Dam
32 | P a g e
Project Rehabilitation Report of H B Halli Dam
33 | P a g e
Project Rehabilitation Report of H B Halli Dam
34 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
35 | P a g e
Annex B: Drawings issued for
Rehabilitation measures
Project Rehabilitation Report of H B Halli Dam
36 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
37 | P a g e
Project Rehabilitation Report of H B Halli Dam
38 | P a g e
Project Rehabilitation Report of H B Halli Dam
39 | P a g e
Project Rehabilitation Report of H B Halli Dam
100 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
101 | P a g e
Annex C: Completion Certificate
Project Rehabilitation Report of H B Halli Dam
102 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
103 | P a g e
Project Rehabilitation Report of H B Halli Dam
104 | P a g e
Project Rehabilitation Report of H B Halli Dam
105 | P a g e
Annex D: Photographs Before and
After Rehabilitation Works
Project Rehabilitation Report of H B Halli Dam
106 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
107 | P a g e
Pointing to Downstream of Spillway Piers
Before
During Construction
Project Rehabilitation Report of H B Halli Dam
108 | P a g e
After
Erosion/Damaged Portion of Draft Chute channel
Before
Project Rehabilitation Report of H B Halli Dam
109 | P a g e
Erosion/Damaged Portion of Draft Chute channel
After
Water jet & Seepage arrested at spillway gate No10 by grouting
Before
After
Project Rehabilitation Report of H B Halli Dam
110 | P a g e
Foot Bridge to Sluice
Before
After
Project Rehabilitation Report of H B Halli Dam
111 | P a g e
Downstream Kerb Wall/Parapet Wall
After
Painting of Vertical Gates
Project Rehabilitation Report of H B Halli Dam
112 | P a g e
De-Silting of Stilling Basin
Turfing on Downstream
Project Rehabilitation Report of H B Halli Dam
113 | P a g e
Painting to Dam top Parapet Wall
Upstream Rip-Rap
Project Rehabilitation Report of H B Halli Dam
114 | P a g e
Construction of Chute Drains on Downstream
Laying of M60 grade fume based silica concrete after working
Project Rehabilitation Report of H B Halli Dam
115 | P a g e
Painting to Piers supporting gate hoisting structure & hoist bridge
View of stilling basin after dewatering and deslilting
Project Rehabilitation Report of H B Halli Dam
116 | P a g e
Annex E: DBA and Inundation Maps
Project Rehabilitation Report of H B Halli Dam
100 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of H B Halli Dam
101 | P a g e
Project Rehabilitation Report of H B Halli Dam
102 | P a g e
Project Rehabilitation Report of H B Halli Dam
103 | P a g e
Project Rehabilitation Report of H B Halli Dam
104 | P a g e
Project Rehabilitation Report of H B Halli Dam
105 | P a g e
Project Rehabilitation Report of H B Halli Dam
106 | P a g e
Project Rehabilitation Report of H B Halli Dam
107 | P a g e
Project Rehabilitation Report of H B Halli Dam
108 | P a g e
Project Rehabilitation Report of H B Halli Dam
109 | P a g e
Project Rehabilitation Report of H B Halli Dam
110 | P a g e
Project Rehabilitation Report of H B Halli Dam
100 | P a g e