Commercial & Utility Solar Installation Sequence
July 2012
![Page 2: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/2.jpg)
Topics
• Technology • Site Analysis • Engineering • Construction Process • Commissioning & Testing • Operations and Maintenance
2
![Page 3: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/3.jpg)
Module Types
3
Monocrystalline (19 - 20% Efficiency) Polycrystalline (14 - 16% Efficiency) Thin Film (10 – 15 % Efficiency)
![Page 4: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/4.jpg)
Site Analysis
4
• Roof Survey Detailed measurements for accurate as-built
conditions. Survey existing infrastructure and environment
for potential layout and shading impacts
• Electrical Survey – Detailed, visual inspection of existing gear
for interconnection design. – Survey existing site plan for ground-level
equipment locations.
• Structural Survey – Verify that as-built conditions for roof framing
and decking complies with plans. – Identify any potential loading concerns for
array and construction logistics
![Page 5: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/5.jpg)
Energy Modeling
5
Calculating kWh of energy generated per kWp installed.
![Page 6: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/6.jpg)
Engineering & Permitting
6
• Construction Drawings Convey the engineered design to the building
department and the construction teams
![Page 7: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/7.jpg)
Construction
7
• Mobilization Equipment and material staging Safety and personnel facilities
![Page 8: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/8.jpg)
Construction
8
• Structural Assembly Roof anchorage or ballast placement Penetration sealing and weatherproofing
![Page 9: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/9.jpg)
Construction
9
• Mechanical Installation Racking assembly and layout Array placement and roof protection
![Page 10: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/10.jpg)
Construction
10
• Rooftop Electrical Array wiring and conduit routing Ancillary equipment mounting
![Page 11: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/11.jpg)
11
• Interconnection Utility AC Disconnect and Monitoring Coupling to existing gear
Construction
![Page 12: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/12.jpg)
12
Commissioning
• Electrical and mechanical inspection. • Curve Tracing – PV performance
benchmark
![Page 13: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/13.jpg)
13
• Annual system maintenance and cleaning • Advanced diagnostics and
troubleshooting
Operations and Maintenance
![Page 14: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/14.jpg)
About Blue Oak Energy
Projects in operation:
~350 MW Work in progress:
200+ MW PV Systems Designed:
453
Closely held entrepreneurial company with a solid and passionate management team since 2003
Relationship oriented we deliver for our customers and grow from repeat business
Downstream focused we only engineer, construct and maintain PV systems
Scale driven commercial & utility segments fuel our growth
Multi-disciplined we are licensed in-house in Electrical, Mechanical, and Civil Engineering. We are also licensed C-10 and L-11 electrical contractors.
![Page 15: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/15.jpg)
15
Our Mission
Our Vision
Our Values
We will design, build and maintain solar energy systems to last a lifetime.
We expect solar energy will be cost competitive with brown power by 2015 in 75% of the US.
Culture. Teamwork. Perspective.
![Page 16: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/16.jpg)
Services
16
Segments
![Page 17: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/17.jpg)
Our Timeline
17
![Page 18: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/18.jpg)
18
It started here….
![Page 19: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/19.jpg)
19
We built 22 retail sites across 7 states
![Page 20: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/20.jpg)
We Designed the Long Island Solar Farm
![Page 21: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/21.jpg)
21
Then we did 100MW across 25 sites
![Page 22: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/22.jpg)
In 2011, we designed a PG&E Solar Farm
![Page 23: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/23.jpg)
In 2007-2011, we designed 20 Wal-Marts.
![Page 24: Project sequence 07.26.12](https://reader035.vdocument.in/reader035/viewer/2022062710/5596f5d01a28ab534b8b4873/html5/thumbnails/24.jpg)