The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date: Friday 2 September 2016 The Project Construction of a two level 116 bed hospital. Current Status Works carried out this week: Lay main water service line to hospital and excavate and lay main sewer drain. Formwork construction to building three, third floor suspended slab; building four, second floor suspended slab; and building five, second floor suspended slab. Scaffold erection to level three of building four and level two of building five. Construction of columns to building three, level two to level three. Concrete pour of building one, level four suspended slab. On site subcontractors: C & V Concreters carrying out concrete pours to building one, level four suspended slab; and building three columns, level two to three. Project Plumbing averaging 10 men a day carrying out works to: 1. Main water services lines; 2. Excavate and lay main sewer drain. NT Scaffold Erecting scaffold to buildings four and five. NT Proform Pty Ltd Averaging 45 men a day on site. Carrying out formwork construction to building three, level three; building four, level two; and building five, level two suspended slabs; and building three, levels two to three columns. Rob O’Keefe Pty Ltd Averaging 15 men a day on site. Carrying out blockwork to buildings one and two. Man hours worked on site for the week 15 August 2016 to 19 August 2016 were 6480. This week there was a total of 19 Indigenous employees working on the site.

Upload: others

Post on 27-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

Project Status Report

Date: Friday 2 September 2016

The Project

Construction of a two level 116 bed hospital.

Current Status

Works carried out this week:

Lay main water service line to hospital and excavate and lay main sewer drain.

Formwork construction to building three, third floor suspended slab; building four, second floor suspended slab; and building five, second floor suspended slab.

Scaffold erection to level three of building four and level two of building five.

Construction of columns to building three, level two to level three.

Concrete pour of building one, level four suspended slab.

On site subcontractors:

C & V Concreters carrying out concrete pours to building one, level four suspended slab; and building three columns, level two to three.

Project Plumbing averaging 10 men a day carrying out works to:

1. Main water services lines;

2. Excavate and lay main sewer drain.

NT Scaffold – Erecting scaffold to buildings four and five.

NT Proform Pty Ltd – Averaging 45 men a day on site. Carrying out formwork construction to building three, level three; building four, level two; and building five, level two suspended slabs; and building three, levels two to three columns.

Rob O’Keefe Pty Ltd – Averaging 15 men a day on site. Carrying out blockwork to buildings one and two.

Man hours worked on site for the week 15 August 2016 to 19 August 2016 were 6480.

This week there was a total of 19 Indigenous employees working on the site.

Page 2: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

OHS Incidents: Nil.

Environmental Controls:

Spray seal to manage dust control.

Head works road construction progressing and monitored.

Fire break maintenance and management implemented, managed and inspected

weekly throughout dry season.

Works for the forthcoming week:

Formwork erection for building three, level three suspended slab; building four, level two suspended slab; and building five, level two suspended slab. Building four, levels two to three columns.

Concrete pour of building four, level two suspended slab.

Blockwork construction to buildings one and two.

Scaffold erection to buildings four and five, level three.

Excavation of main sewer drain, pipe laying and backfilling.

Future Trade Packages pending award:

Metal roofing.

Nurse call and security system.

Page 3: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

Current trade packages awarded to local firms:

Bulk excavation & site clearing Allan King & Sons

Boundary fencing & gates Totem Fencing P/L

Footings & columns C & V Concrete P/L

Site survey & set out works Bennett & Bennett P/L

Quantity surveying services QS Services P/L

Early works hydraulic services Project Plumbing P/L

Tower crane High Rise & Rigging P/L

Reinforcement supply One Steel Darwin P/L

Site surveillance camera Intech NT

Genset fuel supply Mini Tankers P/L

Formwork NT Pro Form P/L

Concrete supply HB Concrete Darwin P/L

Concrete place C & V Concreters NT P/L

Reinforcement fix Reo Fast NT P/L

Concrete pumping Darwin Concrete Pumping P/L

Early works electrical Nilsen NT

Site accommodation NT Link P/L

Rubbish removal VEOLIA Environmental Darwin

Civil early works - stormwater Allan King & Sons P/L

Traffic control Core Staff NT P/L

Scaffold NT Scaffold

Site amenities cleaning &

consumable

Corestaff NT & Shemrock

Chemicals

Structural steel roofing MMC P/L

Block work supply HB Blocks & Pavers

Lifts Otis Lifts Darwin

Block laying (Early works) Rob O’Keeffe P/L

Electrical Services Nilson NT

Fire Walls Intract Australia

Fire Protection, Wet & Dry Control Fire Services P/L

Mechanical Services Airducter

Hydraulic Services Project Plumbing

Page 4: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

LAYING OF MAIN SEWER DRAIN.

EXCAVATION FOR MAIN SEWER DRAIN.

Page 5: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

CONTINUED ROCK EXCAVATION FOR MAIN SEWER DRAIN.

PLACED & TIED REO BAR TO BUILDING 1, LEVEL 4 SUSPENDED SLAB.

Page 6: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

POURING OF CONCRETE TO BUILDING 1, LEVEL 4 SUSPENDED SLAB.

CONCRETE POUR COMPLETION TO BUILDING 1, LEVEL 4 SUSPENDED SLAB.

Page 7: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

FORMWORK CONSTRUCTION TO BUILDING 3, LEVEL 3 SUSPENDED SLAB.

FORMWORK CONSTRUCTION TO BUILDING 4 SUSPENDED SLAB (MATERNITY WARD).

Page 8: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

PLACED & TIED REO BAR TO BUILDING 4 SUSPENDED SLAB (MATERNITY WARD) WITH LINK BRIDGE IN THE BACKGROUND TO BUILDING 3 (WARD 4 SURGICAL)

CONSTRUCTION OF BASE FOR MATERIAL HOIST ERECTION.

Page 9: Project Status Report · 2017-09-29 · The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments Project Status Report Date:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory

Governments

BUILDING REFERENCE MAP.