project status report · 2017-09-29 · the palmerston regional hospital project is jointly funded...
TRANSCRIPT
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
Project Status Report
Date: Friday 2 September 2016
The Project
Construction of a two level 116 bed hospital.
Current Status
Works carried out this week:
Lay main water service line to hospital and excavate and lay main sewer drain.
Formwork construction to building three, third floor suspended slab; building four, second floor suspended slab; and building five, second floor suspended slab.
Scaffold erection to level three of building four and level two of building five.
Construction of columns to building three, level two to level three.
Concrete pour of building one, level four suspended slab.
On site subcontractors:
C & V Concreters carrying out concrete pours to building one, level four suspended slab; and building three columns, level two to three.
Project Plumbing averaging 10 men a day carrying out works to:
1. Main water services lines;
2. Excavate and lay main sewer drain.
NT Scaffold – Erecting scaffold to buildings four and five.
NT Proform Pty Ltd – Averaging 45 men a day on site. Carrying out formwork construction to building three, level three; building four, level two; and building five, level two suspended slabs; and building three, levels two to three columns.
Rob O’Keefe Pty Ltd – Averaging 15 men a day on site. Carrying out blockwork to buildings one and two.
Man hours worked on site for the week 15 August 2016 to 19 August 2016 were 6480.
This week there was a total of 19 Indigenous employees working on the site.
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
OHS Incidents: Nil.
Environmental Controls:
Spray seal to manage dust control.
Head works road construction progressing and monitored.
Fire break maintenance and management implemented, managed and inspected
weekly throughout dry season.
Works for the forthcoming week:
Formwork erection for building three, level three suspended slab; building four, level two suspended slab; and building five, level two suspended slab. Building four, levels two to three columns.
Concrete pour of building four, level two suspended slab.
Blockwork construction to buildings one and two.
Scaffold erection to buildings four and five, level three.
Excavation of main sewer drain, pipe laying and backfilling.
Future Trade Packages pending award:
Metal roofing.
Nurse call and security system.
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
Current trade packages awarded to local firms:
Bulk excavation & site clearing Allan King & Sons
Boundary fencing & gates Totem Fencing P/L
Footings & columns C & V Concrete P/L
Site survey & set out works Bennett & Bennett P/L
Quantity surveying services QS Services P/L
Early works hydraulic services Project Plumbing P/L
Tower crane High Rise & Rigging P/L
Reinforcement supply One Steel Darwin P/L
Site surveillance camera Intech NT
Genset fuel supply Mini Tankers P/L
Formwork NT Pro Form P/L
Concrete supply HB Concrete Darwin P/L
Concrete place C & V Concreters NT P/L
Reinforcement fix Reo Fast NT P/L
Concrete pumping Darwin Concrete Pumping P/L
Early works electrical Nilsen NT
Site accommodation NT Link P/L
Rubbish removal VEOLIA Environmental Darwin
Civil early works - stormwater Allan King & Sons P/L
Traffic control Core Staff NT P/L
Scaffold NT Scaffold
Site amenities cleaning &
consumable
Corestaff NT & Shemrock
Chemicals
Structural steel roofing MMC P/L
Block work supply HB Blocks & Pavers
Lifts Otis Lifts Darwin
Block laying (Early works) Rob O’Keeffe P/L
Electrical Services Nilson NT
Fire Walls Intract Australia
Fire Protection, Wet & Dry Control Fire Services P/L
Mechanical Services Airducter
Hydraulic Services Project Plumbing
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
LAYING OF MAIN SEWER DRAIN.
EXCAVATION FOR MAIN SEWER DRAIN.
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
CONTINUED ROCK EXCAVATION FOR MAIN SEWER DRAIN.
PLACED & TIED REO BAR TO BUILDING 1, LEVEL 4 SUSPENDED SLAB.
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
POURING OF CONCRETE TO BUILDING 1, LEVEL 4 SUSPENDED SLAB.
CONCRETE POUR COMPLETION TO BUILDING 1, LEVEL 4 SUSPENDED SLAB.
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
FORMWORK CONSTRUCTION TO BUILDING 3, LEVEL 3 SUSPENDED SLAB.
FORMWORK CONSTRUCTION TO BUILDING 4 SUSPENDED SLAB (MATERNITY WARD).
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
PLACED & TIED REO BAR TO BUILDING 4 SUSPENDED SLAB (MATERNITY WARD) WITH LINK BRIDGE IN THE BACKGROUND TO BUILDING 3 (WARD 4 SURGICAL)
CONSTRUCTION OF BASE FOR MATERIAL HOIST ERECTION.
The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory
Governments
BUILDING REFERENCE MAP.