providing ugd system to connect 300 kld stp, … · electronics city industrial township authority...

68
ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, PHASE - 1 VOLUME – I DETAILED PROJECT REPORT JANUARY - 2016 E I Technologies Pvt. Ltd., ISO 9001:2008 CERTIFIED - TUV NORD #1149, 26 th Main, Jayanagar 4 th “T” Block, Bangalore – 560041. Ph.: +91 (80) 40914714 ● Fax: +91 (80) 26650912 www.eitech.in[email protected]

Upload: doankhuong

Post on 09-Apr-2018

237 views

Category:

Documents


13 download

TRANSCRIPT

Page 1: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY

7(P), ELCIA Complex, Electronics City, Bangalore – 560 100

PROVIDING UGD SYSTEM TO CONNECT

300 KLD STP, PHASE - 1

VOLUME – I

DETAILED PROJECT REPORT

JANUARY - 2016

E I Technologies Pvt. Ltd., ISO 9001:2008 CERTIFIED - TUV NORD #1149, 26

th Main, Jayanagar 4

th “T” Block, Bangalore – 560041.

Ph.: +91 (80) 40914714 ● Fax: +91 (80) 26650912

www.eitech.in●[email protected]

Page 2: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd.

Document Control Title: ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY

Subject: DETAILED PROJECT REPORT

Type: REPORT

Classification: CLIENT USE

Control: CLIENT

Copyright: E I TECHNOLOGIES PVT. LTD., BANGALORE

Digital filename: EIT-1210X-WRE-DPR-A001-R0

Document No.: EIT-1210X-WRE-DPR-A001-R0

References:

Rev. Description Issue Date Author Checked Approved

00 Document created

15/10/2015 BS SN NR

01 After Discussions

03/12/2015 BS SN NR

02 After Discussions

27/01/2016 BS SN NR

Page 3: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd.

Contents Chapter 1 Introduction .............................................................................................................. 1

1.1 Project Background .............................................................................................................. 1

1.2 Objective of the Assignment ................................................................................................. 1

1.3 Client’s Representative ........................................................................................................ 1

1.4 Consultant ............................................................................................................................ 2

1.5 Purpose of the Report .......................................................................................................... 2

1.6 Document Organisation........................................................................................................ 2

Chapter 2 Scope of the Work .................................................................................................... 3

2.1 General ................................................................................................................................ 3

2.2 Detailed Activities ................................................................................................................. 3

2.3 Drawings and Estimates ....................................................................................................... 4

2.3.1 List of Drawings .............................................................................................................. 4

2.3.2 Estimates ........................................................................................................................ 5

2.4 Deliverables ......................................................................................................................... 5

Chapter 3 Project Service Area ................................................................................................ 6

3.1 Project Service Area ............................................................................................................ 6

3.2 Location of Proposed Project Area ....................................................................................... 6

3.3 Accessibilitys ........................................................................................................................ 8

3.4 Administrative Boundary ...................................................................................................... 8

3.5 Geographical location........................................................................................................... 8

3.6 Climatic Condition ................................................................................................................ 8

3.6.1 General ........................................................................................................................... 8

3.6.2 Rainfall ............................................................................................................................ 8

3.6.3 Temperature ................................................................................................................... 9

3.6.4 Humidity .......................................................................................................................... 9

3.6.5 Cloudiness ...................................................................................................................... 9

3.7 Topography .......................................................................................................................... 9

3.8 Geomorphology and Soil types ............................................................................................ 9

Chapter 4 Approach and Methodology .................................................................................. 10

4.1 Approach ............................................................................................................................ 10

4.2 Methodology ....................................................................................................................... 11

Chapter 5 Designs ................................................................................................................... 12

5.1 General .............................................................................................................................. 12

Page 4: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd.

5.2 Design Factors ................................................................................................................... 12

5.3 Minimum Size of Circular Sewers ...................................................................................... 12

5.4 Shape and Size of Sewers ................................................................................................. 13

5.5 Ductile Iron pipes ............................................................................................................... 13

5.6 Flow in Circular Sewers ...................................................................................................... 13

5.7 Profile of Sewer System ..................................................................................................... 14

5.8 Manhole Chamber .............................................................................................................. 14

5.9 Sewer Distribution Network ................................................................................................ 15

5.9.1 Network Design ............................................................................................................ 15

5.10 Estimation .......................................................................................................................... 15

5.11 Existing Storm Water Drains .............................................................................................. 16

Chapter 6 Abstract and Detailed Cost Estimates .................................................................. 19

6.1 Cost Estimate ..................................................................................................................... 19

Chapter 7 Recommendations ................................................................................................. 21

7.1 Introduction ........................................................................................................................ 21

7.2 Pipe Material for Distribution System ................................................................................. 21

7.3 Method of Distribution system ............................................................................................ 21

7.4 Findings and Recommendations ........................................................................................ 21

Page 5: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd.

List of Figures

Figure 3.1: Index showing the proposed project Location ......................................................................... 7

Figure 4.1: Design Administrative Process ..............................................................................................10

Figure 5.1: Existing storm water drain along the Branch line 2 of 2 ........................................................16

Figure 5.2: Existing storm water drain along the Branch 2 of 2 near BESCOM .......................................16

Figure 5.3: Existing storm water drain along the Branch 2 of 2 near PRADOT ........................................17

Figure 5.4: Existing storm water drain along the Branch 2 of 2 on Canara Bank Road ...........................17

Figure 5.5: Existing storm water drain along the Main Line 2 ..................................................................17

Figure 5.6: Existing storm water drain along the Main Line 2 opposite KSSIDC Block ............................17

Figure 5.7: Existing storm water drain along the Main Line 2 opposite Paramount .................................18

Figure 5.8: Existing storm water drain along the Trunk line .....................................................................18

Figure 5.9: Existing storm water drain along the trunk line 2 ...................................................................18

Figure 5.10: Existing storm water drain along the Trunk line near ITI land ..............................................18

Page 6: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd.

List of Tables

Table 5.1: Details of Diameters of manholes ...........................................................................................14

Table 5.2: List of Manhole chamber .........................................................................................................14

Table 5.3: Details of Sewer Network ........................................................................................................15

Table 6.1: Abstract Cost Estimate for the Scheme ..................................................................................19

Page 7: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd.

Abbreviations

BOQ Bill Of Quantities

CPHEEO Central Public Health and Environmental Engineering Organization

DI Ductile Iron pipes

ft Feet

GAD General Arrangement Drawing

IS Indian Standards

IT Information Technology

kms Kilometers

MLD Kilo Liters per Day

lpcd Litres per capita per day

lps Liter per second

m Meters

m/s Meters per second

MLD Million Liters per Day

PMC Project Management Consultancy

PWD Public Works Departments

QA Quality Assurance

QC Quality Control

RCC Reinforced Cement Concrete

RL Reduced level

ROU Right of Use

SOI Survey of India

Sq. kms. Square Kilometers

SR Schedule of Rates

TOR Terms of Reference

WRD Water Resources Department

Page 8: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 1

Chapter 1 Introduction

1.1 Project Background

Electronics City has been developed as a major hub for setting up state of the art enterprises more so in

the field of Information Technology by various entrepreneurs. The said area boasts of several leading

national and international organizations that have set up their facilities within it.

Electronics City Industrial Township Authority (ELCITA) is the nodal agency responsible for looking

after the welfare of the companies who have put up their enterprises in the Electronic City. ELICTA

would like to ensure that the entire Electronics City comprising of various phases shall function as a

smart city providing world class facility in terms of communication, transportation network, pedestrian

movement, pollution free environment, state of the art drainage network, etc.

It is a fact that Electronics City contributes a higher share of GDP making the capital of Karnataka,

Bangalore, as the hub for IT development (Silicon Valley). As a result, the number of industries and

the end-users within the Electronics city has increased and, the pace of development need to match with

the safety aspects and infrastructure facilities provided should meet the need of the end-users. With

this in background, ELCITA is planning to address all the issues.

ELCITA further wants to ensure that the Electronics City in Bangalore to be the first smart industrial

zone, which can be a role model for several other industrial zones, developed across the nation.

1.2 Objective of the Assignment

The objective of the present assignment is to prepare a Techno-economically viable detailed project

report for UGD scheme of Electronics City Industrial Township Authority (ELCITA).

1.3 Client’s Representative

The client for the project is Electronics City Industrial Township Authority (ELCITA), having

registered office at the following address:

ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY (ELCITA),

7(P), ELCIA Complex,

Electronics City - 560 100

Page 9: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 2

1.4 Consultant

E I Technologies Pvt. Ltd. Bangalore, have been entrusted with the work to prepare the detailed

project report for the Sewer network system.

1.5 Purpose of the Report

The purpose of the project is to collect sewage from the Industries and also septic tanks of the

various buildings through a network of lateral pipe lines and their after connecting to the 300 KLD

STP through a network of Trunk/Mains/Branch lines within the Electronics City Industrial Township

Authority (ELCITA) selected blocks, Bangalore.

1.6 Document Organisation

This Detailed Project report is organized as follows:

VOLUME – I – GENERAL REPORT

Chapter 1 – Introduction

Chapter 2 – Scope of the Work

Chapter 3 – Project Service Area

Chapter 4 – Approach and Methodology

Chapter 5 – Designs

Chapter 6 – Abstract and Detailed Cost Estimates

Chapter 7 – Recommendations

Page 10: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 3

Chapter 2 Scope of the Work

2.1 General

The scope of works for the Proposal of UGD scheme of Electronics City Industrial Township

Authority (ELCITA) includes collection of data, reconnaissance survey, study of alternates and Detailed

Survey of the alignment of proposed sewer network pipeline and preparation of detailed report

containing source identification, preliminary designs and cost estimates.

2.2 Detailed Activities

The detailed activities carried out to meet the Terms of Reference (TOR) of the project are:

1. Detailed interaction with M/s. Electronics City Industrial Township Authority, in order to

collect all the existing data and information available about the total number of industries

within Electronic City Cluster 1, their location including their present location of the chamber

to which the sewage from their industry is being connected.

2. Carrying out detailed reconnaissance survey of the entire Electronic City Cluster 1 project

site including identification of alt the industries, their sewage disposal chamber and up-dating

the map.

3. Planning of network of collector link and trunk sewer lines from all the industries located in

Electronic City Cluster 1, lead the sewage up to Sewage Treatment Plant.

4. Establishing detailed control and plans-metric points and height control along the network of

sewer line planned at coordinating junction.

5. Transferring the proposed collected link and the trunk sewer lines from the plant to the ground

and ensuring that the proposed line planned will have a dedicated corridor free from existing

utility lines.

6. Carrying out detailed alignment survey using State of the Art digital equipment along the

proposed sewer network lines in order 'o capture the data and information such as, the

location of the existing chambers in individual industrial area, road network, existing utilities

(which are visible), names of the industries and also staking center lines at every turning point,

etc., As a part of the alignment survey, levels will be taken at every 20 meters center to center

and also at turning point including the crossing points of roads, utilities, etc.

Page 11: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 4

7. Generation of strip map showing all the details including the alignment sheet showing the plan

and profile.

8. Detailed design in order to optimize the diameter of the sewer lines including selection of

suitable material, based on the cost, economics and also considering the life span of the

project.

9. Detailed design for all the appurtenant structures such as chambers, man-holes, etc., as per

CPHEEO manual / guidelines.

10. Preparation of engineering alignment sheet with all the design para meters including the cross

section drawings at all the crossing locations.

11. Preparation of detailed Bill of Quantities including the cost estimate based on the rates

available from the published schedule of fates, which is in vogue.

12. Preparation of comprehensive detailed project report and submission of the same in duplicate

both hard and soft copy.

2.3 Drawings and Estimates

2.3.1 List of Drawings

No. Name of Drawing Drawing No.

1. Index Map of Electronic City, Bangalore. EIT-1210X-WRE-IND-A001

2. Schematic Diagram Showing UGD Network Drawing for Existing Industries, Cluster 2 & 3, Electronic City, Bangalore.

EIT-1210X-WRE-SCD-A002

3. Plan Showing UGD Network Drawing for Existing Industries, Cluster 2 & 3, Electronic City, Bangalore

EIT-1210X-WRE-PLN-A003

4. Longitudinal Section for Proposed Sewer Line - Trunk Line.

EIT-1210X-WRE-LS-A004

5. Longitudinal Section For Proposed Sewer Line - Main Line-01.

EIT-1210X-WRE-LS-A005

6. Longitudinal Section For Proposed Sewer Line - Main Line-02.

EIT-1210X-WRE-LS-A006

7. Longitudinal Section For Proposed Sewer Line - Main Line-03, Main Line-07 & Main Line-12.

EIT-1210X-WRE-LS-A007

8. Longitudinal Section For Proposed Sewer Line - Branch-2/2.

EIT-1210X-WRE-LS-A008

9. Standard Details of Manhole chamber. EIT-1210X-WRE-STR-A009

10. Typical Cross Section showing the proposed DI Pipein the existing Storm Water Drain

EIT-1210X-WRE-TCS-A010

11. Typical Pipe joint showing the DI pipe and HDPE pipe Connection

EIT-1210X-WRE-TCS-A011

Page 12: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 5

2.3.2 Estimates

Cost estimates are based on the Schedule of Rates of KUWS & DB for the year 2014 – 2015. Rates

for items which are not available in the schedule of rates, realistic market rates have been considered.

2.4 Deliverables

Detailed project report on planning, designs, cost estimates for review and approval in duplicate.

Final Detailed project report based on comments with firm recommendation on techno

economically viable proposal in 2 sets of hard copies 2 sets of soft copies in the form of CDs.

Page 13: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 6

Chapter 3

Project Service Area

The Consultant has studied various alternatives for identifying the source by studying the merits and

demerits were undertaken and the most feasible and sustainable route was finalized.

The findings and observations on various aspects of the project by the Consultant are enumerated in

this chapter.

3.1 Project Service Area

Electronics City has been developed as a major hub for setting up state of the art enterprises more so in

the field of Information Technology by various entrepreneurs. The said area boasts of several leading

national and international organizations that have set up their facilities within it.

Electronics City Industrial Township Authority (ELCITA) is the nodal agency responsible for looking after

the welfare of the companies who have put up their enterprises in the Electronic City. ELICTA would like

to ensure that the entire Electronics City comprising of various phases shall function as a smart city

providing world class facility in terms of communication, transportation network, pedestrian movement,

pollution free environment, state of the art drainage network, etc.

The proposed Project service area is located in Electronic city of Anekal taluks of Bangalore urban

district.

3.2 Location of Proposed Project Area

The location of the proposed scheme is shown in Figure 3.1

Page 14: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 7

Figure 3.1: Index showing the proposed project Location

Page 15: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 8

3.3 Accessibilitys

The proposed Project Area is situated in the Bangalore Urban district. The proposed project covers parts of

Electronic city of Anekal Taluk.

Nearest Airport is at Devanahally, Bangalore and is at a distance of 39 Km.

Nearest bus station is Kempegowda Bus Station and is at a distance of 22.1 Km.

Nearest Railway station is Bangalore city railway station and is at a distance of 22.8 Km.

Nearest sea port is Mangalore and is at a distance of 384.7 Km through NH48.

3.4 Administrative Boundary

The proposed Project area is located in Electronic city of Anekal taluks of Bangalore urban district.

3.5 Geographical location

The geographic location of Project area lies at 12° 51´ 14´´ North Latitude and 77° 39´ 49´´ East Longitude.

3.6 Climatic Condition

3.6.1 General

The climate of the district is agreeable and moderate throughout the year. Though March, April and May

are regarded as summer months, during this period the maximum day temperature stays around 36°c and

the night temperature however around 19°c. Average rainfall is 974.5 mm; Bangalore has a handful of

freshwater lakes and water tanks, the largest of which are Madivala tank, Hebbal Lake, Ulsoor Lake,

Yediyur Lake and Sankey Tank.

The city stands positioned at 12.97° N 77.56° E. The district receives normal average rainfall of 974.5 mm.

Bangalore district borders with Kolar and Chikkaballapur in the northeast, Tumkur in the northwest, Mandya

and Ramanagaram in the southeast and Mysore. While the soils of Bangalore consist of red laterite and

red, fine loamy to clayey soils.

3.6.2 Rainfall

The average annual rainfall of the district is 974.5 mm. Bangalore in the middle receives lower rainfall in

June and July when the South West monsoons break over the western regions (Kodagu) than later in the

season showing a historical bimodal pattern. The city stands positioned at 12.97° N 77.56° E. The district

receives normal average rainfall of 974.5 mm. Bangalore district borders with Kolar and Chikkaballapur in

Page 16: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 9

the northeast, Tumkur in the northwest, Mandya and Ramanagaram in the southeast and Mysore. While

the soils of Bangalore consist of red laterite and red, fine loamy to clayey soils.

3.6.3 Temperature

The climate of the district is agreeable and cool throughout the year. Though March, April and May are

regarded as summer months, during this period the maximum day temperature stays around 36°c and the

night temperature however around 19°c.

3.6.4 Humidity

The region on the whole enjoys a dry climate. The months from December to May are the driest. The

average relative humidity in the afternoons is 65% and as low as 45% in individual days. Even during the

Monsoon months, the average humidity is appreciably below the saturation level.

3.6.5 Cloudiness

Skies are generally clear or lightly clouded during the months of December to March. Cloudiness begins to

increase progressively from April and during monsoon months the skies are heavily clouded on most of the

days.

3.7 Topography

Groundwater occurs in silty to sandy layers of the alluvial sediments. The Peninsular Gneissic Complex

(PGC) is the most dominant rock unit in the area and includes granites, gneisses and migmatites, while the

soils of Bangalore consist of red laterite and red, fine loamy to clayey soils.

3.8 Geomorphology and Soil types

The rock types prevalent in the district belong to the Saugar, Charnokite and Peninsular Gneissic Complex

(PGC) groups. The PGC is the dominant group of rocks and covers two-thirds of the area and includes

granites, gneissis and migmatites. The soils in Bangalore vary from red laterite to clayey soils.

Page 17: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 10

Chapter 4 Approach and Methodology

4.1 Approach

The Consultant has adopted an approach based on the project terms of reference. The preliminary

activities undertaken by the Consultant is to study the specifics of the project, mobilize its resources in

respective fields, to carry out the related activities within the shortest possible time, propose a credible

work plan and execute the plan within agreed time frame. The Consultant’s design approach specific to the

present assignment is illustrated in Figure 4.1

Design Administrative

Process

Planning, Scheduling &

Development of QAP

Designs

Review & UpdateNoClient

Approval

Yes

Collection of data

from Client

Study of sources

Preliminary

Reconnaissance of

sources

Submission

Waste Water/ Sewage

Requirement

Source

Preparation of Final

Detailed Project Report

QC

Gravity and Pumping

Distribution Network

Reports

Preparation of Detailed

Project Report

Figure 4.1: Design Administrative Process

Page 18: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 11

4.2 Methodology

In order to ensure that all project activities are completed as per schedule and terms of reference, it is

necessary to follow a proper methodology. The methodology adopted by the Consultant for this project is

as follows:

Data Collection from Client

Engineering Designs for Sewer Distribution Network

Preparation of Detailed Cost Estimates

Preparation of Report

Page 19: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 12

Chapter 5 Designs

5.1 General

The sewer network design usually involves using the survey data and design period factors, total

containment of sanitary wastes and maximum exclusion of infiltration and inflow to determine the size of

the pipe and location of the man holes. The pipe material selected for the pipeline is DI because it is

relatively cheap, easily available in most parts of the state and is very easy to repair. The following

sections will discuss the method adopted to design the Sewer Network.

5.2 Design Factors

The following factors are considered in the design of sanitary sewers distribution network.

Peak sewage flows from residential, commercial, institutional, and industrial sources;

Groundwater infiltration and exfiltration;

Topography and depth of excavation;

Treatment plant location;

Soils conditions;

Pumping requirements;

Maintenance, including manpower and budget;

Existing sewers;

Existing and future surface improvements;

Controlling service connection elevations

5.3 Minimum Size of Circular Sewers

The minimum diameter may be adopted as 200 mm for cities having present/ base year population of

over 1 lakh. However, depending on growth potential in certain areas even 150 mm diameter can also

be considered. However, in towns having present/ base year population of less than 1 lakh, the

minimum diameter of 150 mm shall be adopted.

In the case of hilly locations, the minimum diameter of 150 mm shall be adopted. The house sewer

connection pipe to public sewer shall be (a) minimum 100 mm or higher based on the number of

houses / flats connected and (b) subject to the receiving public sewer being of higher diameter.

Page 20: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 13

5.4 Shape and Size of Sewers

In general, circular sewer sections are ideal from load bearing point of view in public roads and as the

hydraulic properties are better for varying flows.

In the current design 200 mm pipe diameter is considered.

5.5 Ductile Iron pipes

Ductile iron pipe is a pipe made of ductile iron commonly used for potable water transmission, and

wastewater sewer applications . it has become the most preferred pipe material for water supply and

pressure sewerage applications around the world. has a chemical composition which is very similar to

cast iron, it is considered superior due to its spheroidal micro-structure which has vast advantages such

as higher pressure bearing ability, impact resistance, corrosion resistance etc.

The standard diameters of pipes and flanges followed in this standard are as follows:

80, 100, 125, 150, 200, 250, 300, 350, 400, 450, 500, 600, 700, 750, 800, 900, 1000, 1 100,1 200,

1 400, 1 600, 1 800 and 2 000 mm.

DI pipes rate are based on the pig Iron (Si. 2% - 2.5%) with WPI of 141. K 7 Class DI pipes conforming

to IS 8329:2000 with latest amendments and conveying to work site, rolling, lowering into trenches,

laying true to line, level and perfect linking at joints are used for Distribution network.

5.6 Flow in Circular Sewers

If the velocity and depth of flow is the same for the length of a conduit, it is termed steady flow and as

otherwise, it is non-steady flow. The hydraulic analysis of sewers is simplified by assuming steady flow

conditions though the actual flow conditions are different during morning peak flows and varying flows in

other parts of the 24 hours.

In the design of sanitary sewers, an attempt shall be made to obtain adequate scouring velocities at the

average or at least at the maximum flow at the beginning of the design period. The flow velocity in the

sewers shall be such that the suspended materials in sewage are not silted up; i.e., the velocity shall be

such as to cause automatic self-cleansing effect. The generation of such a minimum self-cleansing

velocity in the sewer, at least once a day is important, because if depositions are takes place and is not

removed, it will obstruct free flow, causing further deposition and finally leading to the complete blocking

of the sewer.

Page 21: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 14

The smooth interior surface of a sewer pipe gets scoured due to continuous abrasion caused by the

suspended solids present in sewage. It is, therefore, necessary to limit the maximum velocity in the

sewer pipe. This limiting or non-scouring velocity will mainly depend upon the material of the sewer.

Thus the sewers are designed on the assumption that although silting might occur at minimum flow, it

would be flushed out during peak flows. Erosion of sewers is caused by sand and other gritty material in

the sewer and by excessive velocity.

5.7 Profile of Sewer System

The vertical profile is drawn from the survey notes for each sewer line. All longitudinal sections are

indicated with reference to the same datum line. The vertical scale of the longitudinal sections are

usually magnified ten times the horizontal scale. The profile shows ground surface, tentative manhole

chamber locations, size and material of pipe, ground and invert levels and extent of concrete protection,

etc. At each manhole chamber the surface elevation, the elevation of sewer invert entering and leaving

the manhole chamber are listed.

5.8 Manhole Chamber

A manhole chamber is an opening by which a man may enter a sewer for inspection, cleaning and other

maintenance and fitted with a removable cover to with stand traffic loads in sewers. Having designed the

sewer system, the manhole chambers are identified where ever required based on the ground profile to

accommodate the sub mersible pumps for pumping the sewage into the UGD system provided along the

walls of the storm water drains. The diameters of circular manholes for stated depths of sewers are in

Table 5.1 and List of Manhole chamber whever is required is listed in Table 5.2.

Table 5.1: Details of Diameters of manholes

No Range of Depths (m) Internal Diameter (m)

1. above 1.65 m and up to 2.30 m 1.70 m

Note: 1.75 m diameter manhole chambers are considered in the current design and estimate

Table 5.2: List of Manhole chamber

No Dimensions Manhole No. Location

1. 1.75 m Dia X 2.0 m Depth MH - 95 At Main line – 01 connecting to Trunk

Line @ MH - 13

2. 1.75 m Dia X 2.0 m Depth MH - 45 At Main line – 02 connecting to Trunk

Line @ MH - 13

3. 1.75 m Dia X 2.0 m Depth MH - 122 At Branch 2/ 2 connecting to Connecting

to Main line - 02 @ MH - 60

Page 22: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 15

No Dimensions Manhole No. Location

4. 1.75 m Dia X 2.0 m Depth MH - 73 At Main line – 07 connecting to Trunk

Line @ MH - 09

5. 1.75 m Dia X 2.0 m Depth MH - 107 At Main line – 12 connecting to

Connecting to Trunk Line @ MH - 31

6. 1.75 m Dia X 2.0 m Depth MH - 41 At Trunk line connecting to Connecting to

300 KLD STP

5.9 Sewer Distribution Network

5.9.1 Network Design

Considering the above design parameters Sewer network consisting of trunk line, mains, branches and

laterals has been designed. Manhole chambers are constructed wherever required to pump the sewage

into the UGD pipe line by providing 1 working and 1 standby submersible pumps in the manholes. The

sewer network is planned along the walls of the existing storm water drains 0.3 m below the top of storm

water drain.The detail of the Sewer network system is as follows.

Table 5.3: Details of Sewer Network

No Description Material Class Length (m) Diameter of pipe

(mm)

1. Trunk Line DI K 7 1561.00 200

2. Main Line DI K 7 1744.00 200

3. Branch Line DI K 7 1072.00 200

4. Laterals DI K 7 138.00 200

Refer Annexure 1 to Annexure 5 for Economic analysis, Calculations of Discharge capacity for UGD

Electronic city, Various Manhole chambers are constructed wherever required to pump the sewage into

the UGD pipe line, design of Pumping machinery, typical hydraulic calculations and for manhole

locations on Trunk Line, Main lines, Branch lines and laterals of sewer distribution network system.

5.10 Estimation

Following provisions are made in the estimate of distribution network

Earthwork Excavation for pipeline trenches and Manholes, soil profile considered in all soils

mixed with boulders of 30 cm. size and exclusive of disintegrated rock, 60 % of the depth of

cut, For disintegrated rock, soft rock, soft shale and medium hard rock 20 % of the total depth

of cut and hard rock by chiseling is 20 % of Total depth of cut.

Supplying, Laying, Jointing, Testing & Commissioning of DI Pipes on both sides of the road

along the alignment.

Reinstatement of the existing roads wherever cutting is there.

Page 23: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 16

Construction of Manhole chambers for accommodating the submersible pumps.

A provision of Rs. 247.00 Lakhs as per the SOR 2014-15 of KUWS&DB is made in the estimate for

“Providing, laying, jointing, testing and commissioning of Sewer Network system using DI pipe, K7 class

and Manhole chambers for accommodating the submersible pumps”.

Refer Annexure 6 for Estimates.

5.11 Existing Storm Water Drains

The Sewer Network is planned along the walls of the existing storm water drains 0.3 m below the top of

storm water drain.The detail of the existing storm water drains are shown as below in Figure 5.1 to

Figure 5.10.

Figure 5.1: Existing storm water drain along the Branch line 2 of 2

Figure 5.2: Existing storm water drain along the Branch 2 of 2 near BESCOM

Page 24: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 17

Figure 5.3: Existing storm water drain along the Branch 2 of 2 near PRADOT

Figure 5.4: Existing storm water drain along the Branch 2 of 2 on Canara Bank Road

Figure 5.5: Existing storm water drain along the Main Line 2 Figure 5.6: Existing storm water drain along the Main Line 2

opposite KSSIDC Block

Page 25: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 18

Figure 5.7: Existing storm water drain along the Main Line 2 opposite Paramount

Figure 5.8: Existing storm water drain along the Trunk line

Figure 5.9: Existing storm water drain along the trunk line 2 Figure 5.10: Existing storm water drain along the Trunk line

near ITI land

Page 26: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 19

Chapter 6 Abstract and Detailed Cost Estimates

6.1 Cost Estimate

6.1.1 Capital cost for implementation of scheme

Capital cost of scheme for Sewer Network with DI pipe material is amounting to Rs. 247.00 Lakhs. The

cost estimates are based on schedule of rates SOR of KUWS & DB for the year 2014 – 15. For items

where market rates are considered, such rates are obtained from various vendors to arrive at a

reasonably correct cost: An abstract giving the details of various items considered for arriving at the total

project cost is indicated hereunder (Refer Table 6.1). Detailed cost estimates are enclosed in

Annexure – 6.

Table 6.1: Abstract Cost Estimate for the Scheme

No. Description Amount (Rs.)

Part - A

1 Earthwork Excavation for Trial Pits and Manholes. 42,847/-

2 Refilling Excavated Earth Quantity for Trial pits and Manholes. 12,720/-

3 Reinstatement of the existing Roads including Cutting and Filling. 1,70,989/-

4 Providing casurinapole three tier barricading as protection while excavating and sand, murram/ Gravel bedding for pipeline. 20,352/-

5 Supplying, installing, testing and commissioning of DI pipes with SS Clamps. 18,94,880/-

6 Supplying, lowering, laying, jointing, testing and commissioning of Ductile Iron pipes.

6.1 For Trunk Line (Left and Right side of the road along the alignment). 45,41,928/-

6.2 For Main Lines (Left and Right side of the road along the alignment).

50,75,332/-

6.3 For Branches (Left and Right side of the road along the alignment). 32,29,082/-

6.4 For Lateral Lines (Left and Right side of the road along the alignment). 4,04,345/-

7 Supplying Ductile Iron pipes Specials and fittings. 28,93,230/-

8 Providing and constructing of Manhole chambers of 1.75 m Dia x 2.0 m Depth for accomodating the submersible pumps. 4,07,505/-

9

Design manufacture, supply, erection, trail running, performance test and commissioning of Wastewater Non Clogging Submersible Pumps at Manhole Chambers for Pumping the Sewage.

42,77,148/-

10 Supplying, laying, jointing, testing and commissioning of Non Return Valves.

2,48,590/-

11 Others including dismantling, Removing debris. Etc., 2,50,000/-

Sub Total - Part A 2,34,58,094/-

Page 27: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 20

No. Description Amount (Rs.)

Part - B

12 Utility shifting/ Relocation @ 5 % 11,72,905/-

Sub Total - Part B 11,72,905/-

Total = Part (A+B) 2,46,30,999/-

Rounding off 69,001/-

Grand Total 2,47,00,000/-

2.47 Crores Rupees Two Crore Forty Seven Lakh(s) Only

Page 28: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 21

Chapter 7 Recommendations

7.1 Introduction

Electronics City Industrial Township Authority (ELCITA) is the nodal agency responsible for looking after

the welfare of the companies who have put up their enterprises in the Electronic City. ELICTA would like

to ensure that the entire Electronics City comprising of various phases shall function as a smart city

providing world class facility in terms of communication, transportation network, pedestrian movement,

pollution free environment, state of the art drainage network, etc.

The purpose of the project assignment is to collect waste water from the septic tanks of the various

buildings through a network of pipe lines to the proposed 300 KLD STP in the Electronics City

Industrial Township Authority (ELCITA), Bangalore.

7.2 Pipe Material for Distribution System

It is proposed to use DI pipes for sewer distribution network system along the existing storm water

drains.

7.3 Method of Distribution system

It is proposed to adopt gravity and pumping based sewer distribution network system with brick masonry

manhole chambers for accommodating the submersible pumps wherever required.

7.4 Findings and Recommendations

Electronics City Industrial Township Authority (ELCITA) has established 300 KLD STP.

The STP will get the sewage from various industries through a network of Trunk lines/ Main

Lines/ Branches/ Laterals.

The entire network is designed to cater for 300 KLD capacity such that future demand can be

met without further augmentation.

The entire network of sewage network is planned along the existing storm water drains using

Ductile Iron pipes (DI) material and K7 class the flow will be by gravity and pumping.

Indivisual Units connections to the UGD network is not considere in the Design & Estimation.

Page 29: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Client :Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City

DETAILED PROJECT REPORT

Consultant: Consultant: E I Technologies Pvt Ltd., Page 22

Manhole chambers has been proposed wherever required of 1.75 m diameter and 2.0 m depth

for accommodating 1 working + 1 standby submersible pumps as per the design/ site

requirement.

Considering the project has to be developed in an urban area with restricted right of way a

provision for Restoration/ Relocation of Utilities/ Dismantling and Restoration of

Structures/ Disposal of excavated material etc. have been made in the cost estimate.

The total cost of the distribution network consisting of Trunk lines/ Main lines/ Branches

/ Laterals and Manhole chambers with submersible pumps is amounting to Rs. 247.00 Lakhs

as per the schedule of rates SOR of KUWS & DB for the year 2014 – 15.

Page 30: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

From To

1 General Abstract 23 23

2 Annexure - 1 Economic analysis 24 24

3 Annexure - 2 Discharge capacity for UGD Electronic city 25 25

4 Annexure - 3 List of Manholes 26 26

5 Annexure - 4 Design of Pumping Machinery 27 32

6 Annexure - 5 Typical Hydraulic Design 33 33

7 Annexure - 6 Detailed Estimates for Sewer Distribution Network 34 53

PagesDescriptionNo.

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

DISCHARGE CAPACITY FOR STORAGE TANK

UGD SYSTEM PHASE-1

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd.

Page 31: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

GENERAL ABSTRACT

Page 32: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No. Description Amount (Rs.)

1 Earthwork Excavation for Trial Pits and Manholes. 42,847/-

2 Refilling Excavated Earth Quantity for Trial pits and Manholes. 1,866/-

3 Reinstatement of the existing Roads including Cutting and Filling. 1,70,989/-

4Providing casurinapole three tier barricading as protection while

excavating and sand, murram/ Gravel bedding for pipeline.20,352/-

5Supplying, installing, testing and commissioning of DI pipes with SS

Clamps. 18,94,880/-

6Supplying, lowering, laying, jointing, testing and commissioning of Ductile

Iron pipes.

6.1 For Trunk Line (Left and Right side of the road along the alignment). 45,41,928/-

6.2 For Main Lines (Left and Right side of the road along the alignment). 50,75,332/-

6.3For Branches (Left and Right side of the road along the alignment).

32,29,082/-

6.4 For Lateral Lines (Left and Right side of the road along the alignment). 4,04,345/-

7 Supplying Ductile Iron pipes Specials and fittings. 28,93,230/-

8Providing and constructing of Manhole chambers of 1.75 m Dia x 2.0 m

Depth for accomodating the submersible pumps. 4,07,505/-

9

Design manufacture, supply, erection, trail running, performance test and

commissioning of Wastewater Non Clogging Submersible Pumps at

Manhole Chambers for Pumping the Sewage.

42,77,148/-

10Supplying, laying, jointing, testing and commissioning of Non Return

Valves. 2,48,590/-

11 Others including dismantling, Removing debris. Etc., 2,50,000/-

Sub Total - Part A 2,34,58,094/-

12 Utility shifting/ Relocation @ 5 % 11,72,905/-

11,72,905/-

2,46,30,999/-

69,001/-

2,47,00,000/-

2.47 CroresRupees Two Crore Forty Seven Lakh(s) Only

UGD SYSTEM PHASE-1ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

Sub Total - Part B

Total = Part (A+B)

Rounding off

Grand Total

Part - A

Part - B

GENARAL ABSTRACT

Consultant: E I Technologies Pvt. Ltd. Page 23

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Page 33: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

ANNEXURE - 1

ECONOMIC ANALYSIS

Page 34: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Length (m)Rate in

Rs. Ps.

Amount

in Rs.Length (m)

Rate in

Rs. Ps.

Amount

in Rs.Length (m)

Rate in

Rs. Ps.

Amount

in Rs.Length (m)

Rate in

Rs. Ps.

Amount

in Rs.

Trunk line 1560.60 1429.00 22,30,669 /- 1561.00 1813.00 28,30,093 /- 1561.00 1455.00 22,71,255 /- 1561.00 1719.00 26,83,359 /-

Main line-1 726.30 1429.00 10,37,454 /- 726.00 1813.00 13,16,238 /- 726.00 1455.00 10,56,330 /- 726.00 1719.00 12,47,994 /-

Main line-2 760.70 1429.00 10,87,469 /- 761.00 1813.00 13,79,693 /- 761.00 1455.00 11,07,255 /- 761.00 1719.00 13,08,159 /-

Branch-2/2 1109.30 1429.00 15,84,761 /- 1109.00 1813.00 20,10,617 /- 1109.00 1455.00 16,13,595 /- 1109.00 1719.00 19,06,371 /-

Laterals-1 35.00 1429.00 50,015 /- 35.00 1813.00 63,455 /- 35.00 1455.00 50,925 /- 35.00 1719.00 60,165 /-

Laterals-4 103.90 1429.00 1,48,616 /- 104.00 1813.00 1,88,552 /- 104.00 1455.00 1,51,320 /- 104.00 1719.00 1,78,776 /-

Main line-7 108.20 1429.00 1,54,332 /- 108.00 1813.00 1,95,804 /- 108.00 1455.00 1,57,140 /- 108.00 1719.00 1,85,652 /-

Main line-12 148.00 1429.00 2,11,492 /- 148.00 1813.00 2,68,324 /- 148.00 1455.00 2,15,340 /- 148.00 1719.00 2,54,412 /-

4552.00 Total 65,04,808 /- 4552.00 Total 82,52,776 /- 4552.00 Total 66,23,160 /- 4552.00 Total 78,24,888 /-

Annexure - 01

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

200 mm Internal Dia pipe for the

UGD network for the Electronic

City in the existing storm water

drains along the wall of it.

DI PIPE K - 7 CLASS DI PIPE K - 9 CLASSHDPE Grade - PE- 80 PN 8 rates

conforming to IS 4984:1995

HDPE Grade - PE- 80 PN 6 rates

conforming to IS 4984:1995

ECONOMIC ANALYSIS

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 24

Page 35: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

ANNEXURE - 2

DISCHARGE CAPACITY

Page 36: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No.Retention Time

in Minutes

Retention Time

in Seconds

Discharge

in Cumecs

Volume

in m/sec

Depth

in m

Area

in Sq.m

Diameter of

Storage Tank in m Dimensions

Amount

in Rs.

1 10 600 0.008 4.67 2 2.33 1.75 1.75 Dia x 2.0 m 37,428 /-

2 15 900 0.008 7.00 2 3.50 2.25 2.25 Dia x 2.0 m 61,870 /-

3 30 1800 0.008 14.00 2 7.00 3.00 3.00 Dia x 2.0 m 1,09,992 /-

4 60 3600 0.008 28.00 2 14.00 4.25 4.25 Dia x 2.0 m 2,20,747 /-

1 10 600 0.040 24.05 2 12.03 4.00 4.00 Dia x 2.0 m 1,95,541 /-

2 15 900 0.040 36.08 2 18.04 5.00 5.00 Dia x 2.0 m 3,05,532 /-

3 30 1800 0.040 72.16 2 36.08 7.00 7.00 Dia x 2.0 m 5,98,843 /-

4 60 3600 0.040 144.32 2 72.16 9.75 9.75 Dia x 2.0 m 11,61,786 /-

1 10 600 0.014 8.58 2 4.29 2.50 2.50 Dia x 2.0 m 76,383 /-

2 15 900 0.014 12.88 2 6.44 3.00 3.00 Dia x 2.0 m 1,09,992 /-

3 30 1800 0.014 25.75 2 12.88 4.25 4.25 Dia x 2.0 m 2,20,747 /-

4 60 3600 0.014 51.50 2 25.75 5.75 5.75 Dia x 2.0 m 4,04,066 /-

1 10 600 0.011 6.56 2 3.28 2.25 2.25 Dia x 2.0 m 61,870 /-

2 15 900 0.011 9.83 2 4.92 2.75 2.75 Dia x 2.0 m 92,423 /-

3 30 1800 0.011 19.67 2 9.83 3.75 3.75 Dia x 2.0 m 1,71,862 /-

4 60 3600 0.011 39.33 2 19.67 5.25 5.25 Dia x 2.0 m 3,36,849 /-

Annexure - 2

Location of Collection Sump near MH 1 to pump the waste water to Trunk Line connecting Main Line - 01, Main Line - 02,

Branch 2/2, Lateral 2 and Lateral 4 upto the 300 KLD proposed STP)

Location of Collection Sump near MH 81 to collect the Wastewater from Main Line - 01 and to pump the wastewater to the Trunk Line

Location of Collection Sump near MH 145 to collect the Wastewater from Branch 2/2 and to pump the wastewater to the Main Line - 02 and then to Trunk Line

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

DISCHARGE CAPACITY FOR STORAGE TANK

Location of Collection Sump near MH 45 to collect the Wastewater from Main Line - 02 and to pump the wastewater to the Trunk Line

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 25

Page 37: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

ANNEXURE - 3

LIST OF MANHOLES

Page 38: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Annexure - 3

No.Chainage

in mManhole No. Main line Remarks

1 568.298 MH - 95 Main line - 01 Connecting to Trunk Line @ MH - 13

2 416.276 MH - 122 Branch 2/ 2 Connecting to Main line - 02 @ MH - 60

3 0.00 MH - 73 Main line - 07 Connecting to Trunk Line @ MH - 09

4 0.00 MH - 107 Main line - 12 Connecting to Trunk Line @ MH - 31

5 1414.63 MH - 41 Trunk line Connecting to 300 KLD STP

6 0.00 MH - 45 Main line - 02 Connecting to Trunk Line @ MH - 13

Details for Construction of Manhole

UGD SYSTEM PHASE-1

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 26

Page 39: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

ANNEXURE - 4

DESIGN OF PUMPING MACHINERY

Page 40: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

HEAD CALCULATIONS

Total friction loss + Other losses = 10.0 m

Required Discharge = 0.008 Cumecs

Design Discharge = 0.008 Cumecs

No of pumps = 1 Working+1 Standby

Discharge per pump = 0.008/1=0.008 Cumecs = 28.800 Cum/Hr

Type of pump = Submersible pump

Pump efficiency = 70 %

28.80 x 10.00

367.20 x 0.70

= 1.12 KW

= 2.50 KW

= 3.62 KW

= 95%

3.81 KW

Total = 3.81 KW

Motor rating with 10% overload = 4.23 KW

Total = 4.23 KW

Say = 10.00 KW

= 13.40 HP

Say = 15.00 HP

POWER REQUIREMENT

= 1 x 11.19 KW each motor =

TOTAL

Add 1 KW Aux power

Considering 0.9 Power factor =

Add 25 % for starting power =

Total =

Say =

Annexure - 4

3.39 KVA

16.94 KVA

20.00 KVA

20.00 KVA

It is proposed to provide 1 working + 1 standby of 20.00 KVA power Transformer with

11 KV/0.433 KV Transformer Centre or 20.00 KVA Diesel Generator.

In put to Motor in KW

No. of working pump 11.20 KW

11.20 KW

1.00 KW

13.56 KVA

Bowl output =

Bearing losses

Total

Motor Efficiency

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

DESIGN OF PUMPING MACHINERY FOR MAIN - 01 @ MH - 95

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 27

Page 41: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

HEAD CALCULATIONS

Total friction loss + Other losses = 10.0 m

Required Discharge = 0.040 Cumecs

Design Discharge = 0.040 Cumecs

No of pumps = 1 Working+1 Standby

Discharge per pump = 0.040/1=0.040 Cumecs = 144.000 Cum/Hr

Type of pump = Submersible pump

Pump efficiency = 70 %

144.00 x 10.000

367.20 x 0.7

= 5.60 KW

= 2.50 KW

= 8.10 KW

= 95%

8.53 KW

Total = 8.53 KW

Motor rating with 10% overload = 9.48 KW

Total = 9.48 KW

Say = 10.00 KW

= 13.40 HP

Say = 15.00 HP

POWER REQUIREMENT

= 1 x 11.19 KW each motor =

TOTAL

Add 1 KW Aux power

Considering 0.9 Power factor =

Add 25 % for starting power =

Total =

Say =

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

DESIGN OF PUMPING MACHINERY FOR MAIN - 02 @ MH - 45

It is proposed to provide 1 working + 1 standby of 20.00 KVA power Transformer with

11 KV/0.433 KV Transformer Centre or 20.00 KVA Diesel Generator.

3.39 KVA

Total

20.00 KVA

Motor Efficiency

In put to Motor in KW

16.94 KVA

1.00 KW

13.56 KVA

11.20 KW

Bowl output =

20.00 KVA

Bearing losses

No. of working pump

11.20 KW

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 28

Page 42: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

HEAD CALCULATIONS

Total friction loss + Other losses = 5.0 m

Required Discharge = 0.014 Cumecs

Design Discharge = 0.014 Cumecs

No of pumps = 1 Working+1 Standby

Discharge per pump = 0.014/1=0.014 Cumecs = 50.400 Cum/Hr

Type of pump = Submersible pump

Pump efficiency = 70 %

50.40 x 5.000

367.20 x 0.7

= 0.98 KW

= 2.50 KW

= 3.48 KW

= 95%

3.66 KW

Total = 3.66 KW

Motor rating with 10% overload = 4.07 KW

Total = 4.07 KW

Say = 10.00 KW

= 13.40 HP

Say = 15.00 HP

POWER REQUIREMENT

= 1 x 11.19 KW each motor =

TOTAL

Add 1 KW Aux power

Considering 0.9 Power factor =

Add 25 % for starting power =

Total =

Say =

3.39 KVA

16.94 KVA

20.00 KVA

20.00 KVA

It is proposed to provide 1 working + 1 standby of 20.00 KVA power Transformer with

11 KV/0.433 KV Transformer Centre or 20.00 KVA Diesel Generator.

In put to Motor in KW

No. of working pump 11.20 KW

11.20 KW

1.00 KW

13.56 KVA

Bowl output =

Bearing losses

Total

Motor Efficiency

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

DESIGN OF PUMPING MACHINERY FOR BRANCH LINE @ MH - 122

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 29

Page 43: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

HEAD CALCULATIONS

Total friction loss + Other losses = 10.0 m

Required Discharge = 0.006 Cumecs

Design Discharge = 0.006 Cumecs

No of pumps = 1 Working+1 Standby

Discharge per pump = 0.006/1=0.006 Cumecs = 21.600 Cum/Hr

Type of pump = Submersible pump

Pump efficiency = 70 %

21.60 x 10.000

367.20 x 0.7

= 0.84 KW

= 2.50 KW

= 3.34 KW

= 95%

3.52 KW

Total = 3.52 KW

Motor rating with 10% overload = 3.91 KW

Total = 3.91 KW

Say = 10.00 KW

= 13.40 HP

Say = 15.00 HP

POWER REQUIREMENT

= 1 x 11.19 KW each motor =

TOTAL

Add 1 KW Aux power

Considering 0.9 Power factor =

Add 25 % for starting power =

Total =

Say =

3.39 KVA

16.94 KVA

20.00 KVA

20.00 KVA

It is proposed to provide 1 working + 1 standby of 20.00 KVA power Transformer with

11 KV/0.433 KV Transformer Centre or 20.00 KVA Diesel Generator.

In put to Motor in KW

No. of working pump 11.20 KW

11.20 KW

1.00 KW

13.56 KVA

Bowl output =

Bearing losses

Total

Motor Efficiency

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

DESIGN OF PUMPING MACHINERY FOR MAIN - 07 @ MH - 73

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 30

Page 44: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

HEAD CALCULATIONS

Total friction loss + Other losses = 10.0 m

Required Discharge = 0.004 Cumecs

Design Discharge = 0.004 Cumecs

No of pumps = 1 Working+1 Standby

Discharge per pump = 0.004/1=0.004 Cumecs = 14.400 Cum/Hr

Type of pump = Submersible pump

Pump efficiency = 70 %

14.40 x 10.000

367.20 x 0.7

= 0.56 KW

= 2.50 KW

= 3.06 KW

= 95%

3.22 KW

Total = 3.22 KW

Motor rating with 10% overload = 3.58 KW

Total = 3.58 KW

Say = 10.00 KW

= 13.40 HP

Say = 15.00 HP

POWER REQUIREMENT

= 1 x 11.19 KW each motor =

TOTAL

Add 1 KW Aux power

Considering 0.9 Power factor =

Add 25 % for starting power =

Total =

Say =

3.39 KVA

16.94 KVA

20.00 KVA

20.00 KVA

It is proposed to provide 1 working + 1 standby of 20.00 KVA power Transformer with

11 KV/0.433 KV Transformer Centre or 20.00 KVA Diesel Generator.

In put to Motor in KW

No. of working pump 11.20 KW

11.20 KW

1.00 KW

13.56 KVA

Bowl output =

Bearing losses

Total

Motor Efficiency

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

DESIGN OF PUMPING MACHINERY FOR MAIN - 12 @ MH - 107

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 31

Page 45: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

HEAD CALCULATIONS

Total friction loss + Other losses = 5.0 m

Required Discharge = 0.011 Cumecs

Design Discharge = 0.011 Cumecs

No of pumps = 1 Working+1 Standby

Discharge per pump = 0.011/1=0.011 Cumecs = 39.600 Cum/Hr

Type of pump = Submersible pump

Pump efficiency = 70 %

39.60 x 5.000

367.20 x 0.7

= 0.77 KW

= 2.50 KW

= 3.27 KW

= 95%

3.44 KW

Total = 3.44 KW

Motor rating with 10% overload = 3.82 KW

Total = 3.82 KW

Say = 10.00 KW

= 13.40 HP

Say = 15.00 HP

POWER REQUIREMENT

= 1 x 11.19 KW each motor =

TOTAL

Add 1 KW Aux power

Considering 0.9 Power factor =

Add 25 % for starting power =

Total =

Say =

3.39 KVA

16.94 KVA

20.00 KVA

20.00 KVA

It is proposed to provide 1 working + 1 standby of 20.00 KVA power Transformer with

11 KV/0.433 KV Transformer Centre or 20.00 KVA Diesel Generator.

In put to Motor in KW

No. of working pump 11.20 KW

11.20 KW

1.00 KW

13.56 KVA

Bowl output =

Bearing losses

Total

Motor Efficiency

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

DESIGN OF PUMPING MACHINERY FOR TRUNK LINE @ MH - 41

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 32

Page 46: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

ANNEXURE - 5

DESIGN OF SEWER DISTRIBUTION NETWORK

Page 47: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

Discharge Requirement

Peak Discharge = 0.040 Cumecs

Velocity in the Hunagunda branch line shall be less than 2 m/s

0.200 m

x d2 =

4

Hence Actual Velocity (m/s),

0.0400.031

It is proposed to install 1 row of 0.20 meter diameter of Main line 02 for 760.56 m

Head Loss in the Reach (Friction loss in Main line 02)

Considered 'C' value, C=130 adopted for MS pipes as per CPHEEO Manual

10.67 L Q 10.67 x (760.6) x (0.040)

C D130 x 0.20

H f1=

6.446 m

Length of Hunagunda branch line (L) = 760.564 m.

H f1 = =

6.446 m

Frictional losses (H f1) =

V = Q/A = = 1.273 m/s

Which is less than 2.0 m/s, Hence OK

Say 0.20 m

Area of

Flow = 3.14 x (0.20 x 0.20)

= 0.031 m²4

Design of Main line 02

Peak Discharge (Q) = 0.040 Cumecs

Design Discharge(Q)= 0.040 Cumecs

Annexure - 5

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

Typical Hydraulic Design

Diameter of pipe proposed (d) =

It is proposed to adopt 200 mm inner Diameter, MS pipe for Main line 02 of length 760.6 m

1.852 4.87 1.852 4.87

1.852 1.852

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 33

Page 48: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

ANNEXURE - 6

DETAILED ESTIMATES FOR SEWER DISTRIBUTION NETWORK

Page 49: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT QUANTITYRATE IN

RS. PS.

AMOUNT IN

RS.

1 2 3 4 5 6

1 Earth work excavation for pipeline trenches

(except building works) including depositing on

bank with all lead including shoring, strutting,

barricading, danger lighting and using sight rails

and boning rods at every 100 meters, wherever

necessary as directed in the following strata.

cum

(SR Item No.1, page 5 of KUWS & DB, for 2014 -

15)

1.(a) Earth work excavation for Manholes

1.75 m diameter. 2.0 m deep 56.81 142.040 8,070 /-

1.(b) In disintegrated rock, soft rock, soft shale and

medium hard rock comprising of Lime stone, sand

stone, hard shale, schist, fissured rock without

resorting to blasting.

cum

1.75 m diameter. 2.0 m deep 18.94 332.840 6,304 /-

1.(c) In hard rock by chiseling cum

1.75 m diameter. 2.0 m deep 18.94 1337.720 25,337 /-

1.(d) Earth work excavation for trial pits in all kinds of

strata and for all depthscum 15.00 209.040 3,136 /-

Considering 1 trial pit over 25 m

2 Refilling pipeline trenches and foundation with

selected available earth from trench and

foundation including watering, consolidation in

layers of 15 cms., thick including disposing off the

surplus earth with all lead and lifts.

cum

(SR Item No.2, page 15 of KUWS & DB, for 2014 -

15)

For Trial Pit & Manholes 44.00 42.400 1,866 /-

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1ABSTRACT ESTIMATE

Annexure - 6

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 34

Page 50: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT QUANTITYRATE IN

RS. PS.

AMOUNT IN

RS.

1 2 3 4 5 6

3 Cutting road surface for pipeline trenches and

disposing off the excavatde stuff with all lead and

lift as directed including barricading, danger

lighting etc., in the following clasifications.

Cum

(SR Item No.4, page 15 of KUWS & DB, for 2014 -

15)

1) Cutting Macadam Road 96 227.90 21,879 /-

2) Cutting Asphalt Road 96 417.64 40,094 /-

3) Cutting Cement Concrete Road 96 840.58 80,696 /-

4 KSRRB M500-41. Providing and laying 25 mm

thick mastic asphalt wearing course with paving

grade bitumen @ 5.82 kg/sqmt meeting the

requirements given in table 500-29, prepared by

using master cooker and laid to required level and

slope after cleaning the surface, including

providing antiskid surface with bitumen procoated

finegrained hard stone chipping of 13.2 mm

nominal size at the rate of 0.005 cum per 10 sqm

and at an approximate spacing of 10 cm center to

center in both directions, pressed into surface

when the temperature of surface is not less than

1000C, protruding 1 mm to 4 mm over mastic

surface all complete as per MRTH clause No 515

complete as per specifications.

Sqm

(SR Item No.21.47, page 163 of PW, P & IWTD,

for 2014 -15)48.00 550.00 26,400 /-

5 KSRRB M500-48. Providing and applying slow

setting bitumen emulsion @ 0.75 kg/sqm for

sealing cracks less than 3 mm wide or incipient

fretting or disintegration in an existing bituminous

surfacing complete as per specifications. MORTH

Specification No.518

Cum

(SR Item No.21.53, page 164 of PW, P & IWTD,

for 2014 -15)48.00 40.00 1,920 /-

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 35

Page 51: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT QUANTITYRATE IN

RS. PS.

AMOUNT IN

RS.

1 2 3 4 5 6

6 Providing erecting and removing casurinapole

three tier Barricading using poles of 7.50 to 10

cms. Dia and 1.5 height above ground fixed

vertically at intervals of 2.0 to 2.50 mtrs. C/C and

horizontally at 0.5 mtrs, above ground level for

minimum depth of 0.30 mtr nd tied with coir rope

firmly including cost and conveyances of all

materials, labour, lead and lift charges and

complete. ( for three tier barrricading )

m

(SR Item No.37.1.2, page 252 of PW, P & IWTD,

for 2014 -15)300.00 67.84 20,352 /-

7 Supplying, installing, testing and commissioning

of Clamps on DI pipes including cost of all

materials, machinery, labour, etc., complete with

all leads and lifts.

Nos

(Market Rate ) 36440.00 52.00 18,94,880 /-

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 36

Page 52: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT QUANTITYRATE IN

RS. PS.

AMOUNT IN

RS.

1 2 3 4 5 6

8 Supplying Ductile Iron pipes conforming to IS

8329:2000 with latest amendments and

conveying to work site, rolling, lowering into

trenches, laying true to line, level and perfect

linking at joints, testing and commissioning,

including loading and unloading at both

destination and cuts of pipes wherever necessary

including jointing of DI pipes and specials

(excluding cost of specials) with rubber gaskets

including cleaning the socket and spigot ends

with soap solution and applying soft soap to the

spigot and soocket ends before insertion of

rubber gaskets, jacking and fixing in perfect

conditions including cost of soap solution, soft

soap, waste ect. and giving necessary hydraulic

test to the required pressure as per ISS with all

lead and lift including cost of materials (contractor

will make his own arrangements for procuring

water for testing).

Note: DI pipes rate are based on the pig Iron (Si.

2% - 2.5%) with WPI of 141.1 as on July 2013.

m

(SR Item No.5.1, page 31 of KUWS & DB, for

2014 -15)

Right side of the raod along the Alignment

200 mm Dia

Trunk line 1561.00 1455.00 22,71,255 /-

Main line-1 727.00 1455.00 10,57,785 /-

Main line-2 761.00 1455.00 11,07,255 /-

Branch-2/2 1110.00 1455.00 16,15,050 /-

Laterals-1 35.00 1455.00 50,925 /-

Laterals-4 104.00 1455.00 1,51,320 /-

Main line-7 109.00 1455.00 1,58,595 /-

Main line-12 148.00 1455.00 2,15,340 /-

Left side of the raod along the Alignment

200 mm Dia

Trunk line 1560.60 1455.00 22,70,673 /-

Main line-1 726.30 1455.00 10,56,767 /-

Main line-2 760.70 1455.00 11,06,819 /-

Branch-2/2 1109.30 1455.00 16,14,032 /-

Laterals-1 35.00 1455.00 50,925 /-

Laterals-4 103.90 1455.00 1,51,175 /-

Main line-7 108.20 1455.00 1,57,431 /-

Main line-12 148.00 1455.00 2,15,340 /-

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 37

Page 53: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT QUANTITYRATE IN

RS. PS.

AMOUNT IN

RS.

1 2 3 4 5 6

9 Supplying Ductile Iron pipes Specials and fittings

etc., conforming to IS 8329:2000 with latest

amendments and conveying to work site, rolling,

lowering into trenches, laying true to line, level

and perfect linking at joints, testing and

commissioning, including loading and unloading

at both destination and complete with all leads

and lifts.

Nos

(Market rate inclusive of all taxes)

Right side of the road along the Alignment

200 mm Dia Specials and fittings 770.00 1891.00 14,56,070 /-

Left side of the road along the Alignment

200 mm Dia Specials and fittings 760.00 1891.00 14,37,160 /-

10 Providing and constructing of Manhole chambers

conical in shape at top with CC 1:3:6 foundation

using 40 mm and down size graded metal of

approved quality aand with an offset of 0.15 mtr.

Alround the chamber and brick masonry in CM

1:3 proportion 12mm thick inside and outside

except for the conical surface outside wher the

thickness of plaster shall be 20 mm thick, with 1

to 6 slope in the concrete towards the central

drain, finished smooth and fixing of pipes in CC

1:2:4 with graded metal of 20 mm and down size

including supplying and fixing SFRC manhole

frame and cover confirming to IS 12592(part-1):

1988 & IS 12592 (Part-II):1991 with latest

amendments in CC 1:2:4, supplying and fixing of

plastic foot steps staggered at 30 cms apart as

directed, watering, curing, barricading, danger

lighting, pouring tar over M.H. frame and cover,

cost of tar, shoring, strutting, dewatering,

engraving with all lead and lift for various

diameters and depths noted below.

No's

(SR Item No.3, page 177 of KUWS & DB, for

2014 -15)

(a) -do- with table moulded bricks of approved

quality and Heavy duty SFRC manhole frame and

cover for 1.80 Mtr. Dia.

For 2.0 Mtr. Depth 6.00 36651.62 2,19,910 /-

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 38

Page 54: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT QUANTITYRATE IN

RS. PS.

AMOUNT IN

RS.

1 2 3 4 5 6

(b) -do- with table moulded bricks of approved

quality and Heavy duty SFRC manhole frame and

cover for 1.80 Mtr. Dia.

For 2.0 Mtr. Depth 6.00 31265.76 1,87,595 /-

11 Design manufacture, supply, erection, trail

running, performance test and commissioning of

Wastewater Non Clogging Submersible Pump of

approved make with all other standard

accessories and safety devices etc., complete as

per specifications, terms and conditions of

contract.

HP

Voltage : 415 V +/- 10%

Frequency : 50 Hz +/- 5%

(As per market rate inclusive of all taxes)

For Main 01 @ MH 95 30.00 23761.92 7,12,858 /-

For Main 02 @ MH - 45 30.00 23761.92 7,12,858 /-

For Branch line @ MH - 122 30.00 23761.92 7,12,858 /-

For Main 07 @ MH - 73 30.00 23761.92 7,12,858 /-

For Main 12 @ MH - 107 30.00 23761.92 7,12,858 /-

For Trunk line @ MH - 41 30.00 23761.92 7,12,858 /-

12 Supplying valves of board approved make

confirming to relevant ISS with latest

amendments as detailed below of following

diameter and types and conveying to work site,

loading, unloading, stacking etc., complete with

all lead and lift. The rate is inclusive of cost of

Bolts and Nuts. Cast steel double flanged dual

plate Check valve Class 300 conforming to API : Set

(SR Item No.9(10), page 63 of Karnataka Urban

Water Supply and drainage board, Bangalore, for

2014 - 15)For 200 mm dia Non Return Valves 12.00 20715.76 2,48,590 /-

13 Dismantling plastering and removing the debris

with a lead up to 200 m.LS 2,50,000 /-

Lump sum

Total = 2,34,58,094 /-

Rupees Two Crore Thirty Four Lakh(s) Fifty Eight Thousand Ninety Four Only

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 39

Page 55: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT No L B D QUANTITY

1 2 3 4 5 6 7 8

1 Earth work excavation for pipeline trenches

(except building works) including depositing

on bank with all lead including shoring,

strutting, barricading, danger lighting and

using sight rails and boning rods at every 100

meters, wherever necessary as directed in the

following strata.

cum

(SR Item No.1, page 5 of KUWS & DB, for

2014 -15)

1.(a) Earth work excavation for Manholes

1.75 m diameter. 2.0 m deep 6 7.89 ─ 2 56.81

Total 56.81

Say 57.00

1.(b) In disintegrated rock, soft rock, soft shale and

medium hard rock comprising of Lime stone,

sand stone, hard shale, schist, fissured rock

without resorting to blasting.

cum

1.75 m diameter. 2.0 m deep 6 2 18.936

Total 18.94

Say 19.00

1.(c) In hard rock by chiseling cum

1.75 m diameter. 2.0 m deep 6 2 18.936

Total 18.94

Say 19.00

1.(d) Earth work excavation for trial pits in all kinds

of strata and for all depths

Considering 1 trial pit over 25 m 6 1 1 2.5 15.000

Total 15.00

Say 15.00

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITYUGD SYSTEM PHASE-1

DETAILED ESTIMATE

7.89

7.89

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 40

Page 56: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT No L B D QUANTITY

1 2 3 4 5 6 7 8

2 Refilling pipeline trenches and foundation with

selected available earth from trench and

foundation including watering, consolidation in

layers of 15 cms., thick including disposing off

the surplus earth with all lead and lifts.

cum

(SR Item No.2, page 15 of KUWS & DB, for

2014 -15)

For Trial Pit 6 1 1 2.5 15.000

Taking 30% refilling for Manholes 1 28.405

Total 43.405Say 44.00

3 Cutting road surface for pipeline trenches and

disposing off the excavatde stuff with all lead

and lift as directed including barricading,

danger lighting etc., in the following

clasifications.

Cum

(SR Item No.4, page 15 of KUWS & DB, for

2014 -15)

1) Cutting Macadam Road 6 10.00 0.800 2.000 96.000

2) Cutting Asphalt Road 6 10.00 0.800 2.000 96.000

3) Cutting Cement Concrete Road 6 10.00 0.800 2.000 96.000

Total 288.000

Say 288.00

4 KSRRB M500-41. Providing and laying 25 mm

thick mastic asphalt wearing course with

paving grade bitumen @ 5.82 kg/sqmt

meeting the requirements given in table 500-

29, prepared by using master cooker and laid

to required level and slope after cleaning the

surface, including providing antiskid surface

with bitumen procoated finegrained hard stone

chipping of 13.2 mm nominal size at the rate

of 0.005 cum per 10 sqm and at an

approximate spacing of 10 cm center to center

in both directions, pressed into surface when

the temperature of surface is not less than

1000C, protruding 1 mm to 4 mm over mastic

surface all complete as per MRTH clause No

515 complete as per specifications.

Sqm

(SR Item No.21.47, page 163 of PW, P &

IWTD, for 2014 -15)6 10.00 0.800 48.000

Total 48.000

Say 48.00

0.3*94.682

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 41

Page 57: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT No L B D QUANTITY

1 2 3 4 5 6 7 8

5 KSRRB M500-48. Providing and applying

slow setting bitumen emulsion @ 0.75 kg/sqm

for sealing cracks less than 3 mm wide or

incipient fretting or disintegration in an existing

bituminous surfacing complete as per

specifications. MORTH Specification No.518

Cum

(SR Item No.21.53, page 164 of PW, P &

IWTD, for 2014 -15)6 10.00 0.800 48.000

Total 48.000Say 48.00

6 Providing erecting and removing casurinapole

three tier Barricading using poles of 7.50 to 10

cms. Dia and 1.5 height above ground fixed

vertically at intervals of 2.0 to 2.50 mtrs. C/C

and horizontally at 0.5 mtrs, above ground

level for minimum depth of 0.30 mtr nd tied

with coir rope firmly including cost and

conveyances of all materials, labour, lead and

lift charges and complete. ( for three tier

barrricading )

m

(SR Item No.37.1.2, page 252 of PW, P &

IWTD, for 2014 -15)2 150.00 300.000

Total 300.000

Say 300.00

7 Supplying, installing, testing and

commissioning of Clamps on DI pipes

including cost of all materials, machinery,

labour, etc., complete with all leads and lifts.

Nos

(Market Rate )

Right side of the raod along the UGD pipe

Alignment @ 250 m C/C spacing1 18220.00 18220.000

Left side of the raod along the UGD pipe

Alignment @ 250 m C/C spacing1 18220.00 18220.000

Total 36440.000

Say 36440.00

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 42

Page 58: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT No L B D QUANTITY

1 2 3 4 5 6 7 8

8 Supplying Ductile Iron pipes conforming to IS

8329:2000 with latest amendments and

conveying to work site, rolling, lowering into

trenches, laying true to line, level and perfect

linking at joints, testing and commissioning,

including loading and unloading at both

destination and cuts of pipes wherever

necessary including jointing of DI pipes and

specials (excluding cost of specials) with

rubber gaskets including cleaning the socket

and spigot ends with soap solution and

applying soft soap to the spigot and soocket

ends before insertion of rubber gaskets,

jacking and fixing in perfect conditions

including cost of soap solution, soft soap,

waste ect. and giving necessary hydraulic test

to the required pressure as per ISS with all

lead and lift including cost of materials

(contractor will make his own arrangements

for procuring water for testing).

Note: DI pipes rate are based on the pig Iron

(Si. 2% - 2.5%) with WPI of 141.1 as on July

2013.

m

(SR Item No.5.1, page 31 of KUWS & DB, for

2014 -15)

Right side of the raod along the Alignment

200 mm Dia

Trunk line 1560.60 1561.00

Main line-1 726.30 727.00

Main line-2 760.70 761.00

Branch-2/2 1109.30 1110.00

Laterals-1 35.00 35.00

Laterals-4 103.90 104.00

Main line-7 108.20 109.00

Main line-12 148.00 148.00

Total 4555.000

Say 4555.00

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 43

Page 59: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT No L B D QUANTITY

1 2 3 4 5 6 7 8

Left side of the raod along the Alignment

200 mm Dia

Trunk line 1560.60 1561.00

Main line-1 726.30 727.00

Main line-2 760.70 761.00

Branch-2/2 1109.30 1110.00

Laterals-1 35.00 35.00

Laterals-4 103.90 104.00

Main line-7 108.20 109.00

Main line-12 148.00 148.00

Total 4555.000Say 4555.00

9 Supplying Ductile Iron pipes Specials and

fittings etc., conforming to IS 8329:2000 with

latest amendments and conveying to work

site, rolling, lowering into trenches, laying true

to line, level and perfect linking at joints,

testing and commissioning, including loading

and unloading at both destination and

complete with all leads and lifts.

No

(Market rate inclusive of all taxes)

Right side of the road along the Alignment

200 mm Dia Specials and fittings 770.00

Total length/ 6 + No. of Manholes

Total length 4555/ 6 = 770

Left side of the road along the Alignment

200 mm Dia Specials and fittings 760.00

Total length/ 6

Total length 4555/ 6 = 760

770.00

760.00

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 44

Page 60: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT No L B D QUANTITY

1 2 3 4 5 6 7 8

10 Providing and constructing of Manhole

chambers conical in shape at top with CC

1:3:6 foundation using 40 mm and down size

graded metal of approved quality and with an

offset of 0.15 mtr. All-round the chamber and

brick masonry in CM 1:3 proportion 12mm

thick inside and outside except for the conical

surface outside where the thickness of plaster

shall be 20 mm thick, with 1 to 6 slope in the

concrete towards the central drain, finished

smooth and fixing of pipes in CC 1:2:4 with

graded metal of 20 mm and down size

including supplying and fixing SFRC manhole

frame and cover confirming to IS 12592(part-

1): 1988 & IS 12592 (Part-II): 1991 with latest

amendments in CC 1:2:4, supplying and fixing

of plastic footsteps staggered at 30 cms apart

as directed, watering, curing, barricading,

danger lighting, pouring tar over M.H. frame

and cover, cost of tar, shoring, strutting,

dewatering, engraving with all lead and lift for

various diameters and depths noted below.

No’s

(SR Item No.3, page 177 of KUWS & DB, for

2014 -15)

10.1 (a) -do- with table molded bricks of approved

quality and Heavy duty SFRC manhole frame

and cover for 1.20 Mtr. Diameter.

For 2.0 Mtr. Depth 6 6.00

Total 6.00

Say 6.00

10.2 (b) -do- with table molded bricks of approved

quality and Heavy duty SFRC manhole frame

and cover for 1.50 Mtr. Dia.For 2.0 Mtr. Depth 6.0 6.00

Total 6.00

Say 6.00

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 45

Page 61: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT No L B D QUANTITY

1 2 3 4 5 6 7 8

11 Design manufacture, supply, erection, trail

running, performance test and commissioning

of Wastewater Non Clogging Submersible

Pump of approved make with all other

standard accessories and safety devices etc.,

complete as per specifications, terms and

conditions of contract.

HP

(As per market rate inclusive of all taxes)

Voltage : 415 V +/- 10%

Frequency : 50 Hz +/- 5%

For Main 01 @ MH 95

Duty point head =10.00 m

Duty point discharge =0.008 cumecs

Motor rating 11.19 KW (15.00 HP) x

2(1 Working + 1 Standby)30.00

For Main 02 @ MH - 45

Duty point head =20.00 m

Duty point discharge =0.040 cumecs

Motor rating 11.19 KW (15.00 HP) x

2(1 Working + 1 Standby)30.00

For Branch line @ MH - 122

Duty point head =5.00 m

Duty point discharge =0.014 cumecs

Motor rating 11.19 KW (15.00 HP) x

2(1 Working + 1 Standby)30.00

For Main 07 @ MH - 73

Duty point head =10.00 m

Duty point discharge =0.006 cumecs

Motor rating 11.19 KW (15.00 HP) x

2(1 Working + 1 Standby)30.00

For Main 12 @ MH - 107

Duty point head =10.00 m

Duty point discharge =0.004 cumecs

Motor rating 11.19 KW (15.00 HP) x

2(1 Working + 1 Standby)30.00

2*15

2*15

2*15

2*15

2*15

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 46

Page 62: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

No DESCRIPTION OF WORK UNIT No L B D QUANTITY

1 2 3 4 5 6 7 8

For Trunk line @ MH - 41

Duty point head =5.00 m

Duty point discharge =0.011 cumecs

Motor rating 11.19 KW (15.00 HP) x

2(1 Working + 1 Standby)30.00

12 Supplying valves of board approved make

confirming to relevant ISS with latest

amendments as detailed below of following

diameter and types and conveying to work

site, loading, unloading, stacking etc.,

complete with all lead and lift. The rate is

inclusive of cost of Bolts and Nuts. Cast steel

double flanged dual plate Check valve Class

300 conforming to API : 594.

Set

(SR Item No.9(10), page 63 of Karnataka

Urban Water Supply and drainage board,

Bangalore, for 2014 - 15)

For 200 mm dia Non Return Valves 12.0 12.00

13 Dismantling plastering and removing the

debris with a lead up to 200 m.LS

2*15

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 47

Page 63: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

(SR Item No.1, page 5 of KUWS & DB, for 2014 -15)

-do- In all soils mixed with boulders of 30 cms.size and exclusive of disintegrated rock.

= Rs 134.00 / cum

= Rs 8.04 / Cum

Total Amount = Rs 142.04/ Cum

(Approved for Rupees One Hundred Forty Two And Paise Four Only)

= Rs 314.00 / Cum

= Rs 18.84 / Cum

Total Amount = Rs 332.84/ Cum

(Approved for Rupees Three Hundred Thirty Two And Paise Eighty Four Only)

Item No - 1.(g)

Earth work excavation for trial pits in all kinds of strata and for all depths

= Rs 134.00 / Cum

= Rs 8.04 / Cum

= Rs 67.00 / Cum

Total Amount = Rs 209.04/ Cum

(Approved for Rupees Two Hundred Nine And Paise Four Only)

(SR Item No.2, page 15 of KUWS & DB, for 2014 -15)

= Rs 40.00 / Cum

= Rs 2.40 / Cum

Total Amount = Rs 42.40/ Cum

(Approved for Rupees Forty Two And Paise Forty Only)

Area Weightage, 6%

Area Weightage, 6%

Area Weightage, 6%

Adhok Weightage 50%

0 to 2 Mtr depth

Area Weightage, 6%

RATE ANALYSIS

Item no. 1

Earth work excavation for pipeline trenches (except building works) including depositing on bank with all lead

including shoring, strutting, barricading, danger lighting and using sight rails and boning rods at every 100

meters, wherever necessary as directed in the following strata.

0 to 2 Mtr depth

-do- In disintegrated rock, soft rock, soft shale and medium hard rock comprising of Lime stone, sand stone,

hard shale, schiest, fissured rock without resorting to blasting.

0 to 2 Mtr depth

Item no. 2

Refilling pipeline trenches and foundation with selected available earth from trench and foundation including

watering, consolidation in layers of 15 cms., thick including disposing off the surplus earth with all lead and

lifts.

Basic Rate

ELECTRONIC CITY INDUSTRIAL TOWNSHIP AUTHORITY

UGD SYSTEM PHASE-1

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 48

Page 64: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

(SR Item No.4, page 15 of KUWS & DB, for 2014 -15)

(Note.4, page 17 of KUWS & DB, for 2014 -15)

= Rs 215.00 / Cum

= Rs 12.90 / Cum

Total Amount = Rs 227.90/ cum

(Approved for Rupees Two Hundred Twenty Seven And Paise Ninety Only)

= Rs 394.00 / Cum

= Rs 23.64 / Cum

Total Amount = Rs 417.64/ Cum

(Approved for Rupees Four Hundred Seventeen And Paise Sixty Four Only)

= Rs 793.00 / Cum

= Rs 47.58 / Cum

Total Amount = Rs 840.58/ Cum

(Approved for Rupees Eight Hundred Forty And Paise Fifty Eight Only)

(SR Item No.21.47, page 163 of PW, P & IWTD, for 2014 -15)

= Rs 550.00/ Sqm

Total Amount = Rs 550.00/ Sqm

(Approved for Rupees Five Hundred Fifty Only)

Item no. 3

Cutting road surface for pipeline trenches and disposing off the excavatde stuff with all lead and lift as

directed including barricading, danger lighting etc., in the following clasifications.

Excavation for water supply pipe line trenches will be governed by the following condition. In case of S & S,

tyton or other types of pipes whereever required for lead joints, mechanical joints, etc., extra payment will be

made for caulking pits or collar pits at the same rate for excavation of pipe trenches. The condition is also

applicable for ppelines laid for U.G.D works.

1) Cutting Macadam Road

Area Weightage, 6%

2) Cutting Asphalt Road

Area Weightage, 6%

3) Cutting Cement Concrete Road

Area Weightage, 6%

Item no. 4

KSRRB M500-41. Providing and laying 25 mm thick mastic asphalt wearing course with paving grade

bitumen @ 5.82 kg/sqmt meeting the requirements given in table 500-29, prepared by using master cooker

and laid to required level and slope after cleaning the surface, including providing antiskid surface with

bitumen procoated finegrained hard stone chipping of 13.2 mm nominal size at the rate of 0.005 cum per 10

sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when

the temperature of surface is not less than 1000C, protruding 1 mm to 4 mm over mastic surface all complete

as per MRTH clause No 515 complete as per specifications.

Basic Rate

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 49

Page 65: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

(SR Item No.21.53, page 164 of PW, P & IWTD, for 2014 -15)=

Total Amount = Rs 40.00/ Cum

(Approved for Rupees Forty Only)

(SR Item No.37.1.2, page 252 of PW, P & IWTD, for 2014 -15)

Basic Rate =

= Rs 3.84/ m

Total Amount = Rs 67.84/ m

(Approved for Rupees Sixty Seven And Paise Eighty Four Only)

(Market Rate )= Rs 50.00 / Each= Rs 2.00 / Each

Total Amount = Rs 52.00 / Each

(Approved for Rupees Fifty Two Only)

Rs 64.00/ m

Area Weightage, 4%

Item no. 7

Supplying, installing, testing and commissioning of Clamps on DI pipes including cost of all materials,

machinery, labour, etc., complete with all leads and lifts.

Item no. 6

Area Weightage, 6%

Basic Rate

Item no. 6

Providing erecting and removing casurinapole three tier Barricading using poles of 7.50 to 10 cms. Dia

and 1.5 height above ground fixed vertically at intervals of 2.0 to 2.50 mtrs. C/C and horizontally at 0.5 mtrs,

above ground level for minimum depth of 0.30 mtr nd tied with coir rope firmly including cost and

conveyances of all materials, labour, lead and lift charges and complete. ( for three tier barrricading )

Basic Rate Rs 40.00 / Cum

Item no. 5

KSRRB M500-48. Providing and applying slow setting bitumen emulsion @ 0.75 kg/sqm for sealing cracks

less than 3 mm wide or incipient fretting or disintegration in an existing bituminous surfacing complete as per

specifications. MORTH Specification No.518

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 50

Page 66: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

(SR Item No.5.1, page 31 of KUWS & DB, for 2014 -15)

K - 7 Class

= Rs 1455.00 / Rmt

Total = Rs 1455.00/ Rmt

(Approved for Rupees One Thousand Four Hundred Fifty Five Only)

(Market rate inclusive of all taxes)

= Rs 1891.00 / Rmt

(Approved for Rupees One Thousand Eight Hundred Ninety One Only)

Supplying Ductile Iron pipes conforming to IS 8329:2000 with latest amendments and conveying to work

site, rolling, lowering into trenches, laying true to line, level and perfect linking at joints, testing and

commissioning, including loading and unloading at both destination and cuts of pipes wherever necessary

including jointing of DI pipes and specials (excluding cost of specials) with rubber gaskets including cleaning

the socket and spigot ends with soap solution and applying soft soap to the spigot and soocket ends before

insertion of rubber gaskets, jacking and fixing in perfect conditions including cost of soap solution, soft soap,

waste ect. and giving necessary hydraulic test to the required pressure as per ISS with all lead and lift

including cost of materials (contractor will make his own arrangements for procuring water for testing).

Note: DI pipes rate are based on the pig Iron (Si. 2% - 2.5%) with WPI of 141.1 as on July 2013.

Item no. 8

200 mm Dia

Item no. 9

200 mm Dia

Supplying Ductile Iron pipes Specials and fittings etc., conforming to IS 8329:2000 with latest

amendments and conveying to work site, rolling, lowering into trenches, laying true to line, level and perfect

linking at joints, testing and commissioning, including loading and unloading at both destination and complete

with all leads and lifts.

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 51

Page 67: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

(SR Item No.3, page 177 of KUWS & DB, for 2014 -15)

= Rs 32346.00/ No.

= Rs 1686.00/ No.

= Rs 545.00/ No.

Total = Rs 34577.00/ No.

= Rs 2074.62/ No.

Total = Rs 36651.62/ No.

(Approved for Rupees Thirty Six Thousand Six Hundred Fifty One And Paise Sixty Two Only)

= Rs 27265.00/ No.

= Rs 1686.00/ No.

= Rs 545.00/ No.

Total = Rs 29496.00/ No.

= Rs 1769.76/ No.

Total = Rs 31265.76/ No.

(Approved for Rupees Thirty One Thousand Two Hundred Sixty Five And Paise Seventy Six Only)

For 2.0 Mtr. Depth

Manhole Frame & Cover

Plastic foot Steps

(b) -do- with table moulded bricks of approved quality and Heavy duty SFRC manhole frame and cover for

1.80 Mtr. Dia.

(a) -do- with table moulded bricks of approved quality and Heavy duty SFRC manhole frame and cover for

1.80 Mtr. Dia.

Providing and constructing of Manhole chambers conical in shape at top with CC 1:3:6 foundation using 40

mm and down size graded metal of approved quality aand with an offset of 0.15 mtr. Alround the chamber

and brick masonry in CM 1:3 proportion 12mm thick inside and outside except for the conical surface outside

wher the thickness of plaster shall be 20 mm thick, with 1 to 6 slope in the concrete towards the central drain,

finished smooth and fixing of pipes in CC 1:2:4 with graded metal of 20 mm and down size including

supplying and fixing SFRC manhole frame and cover confirming to IS 12592(part-1): 1988 & IS 12592 (Part-

II):1991 with latest amendments in CC 1:2:4, supplying and fixing of plastic foot steps staggered at 30 cms

apart as directed, watering, curing, barricading, danger lighting, pouring tar over M.H. frame and cover, cost

of tar, shoring, strutting, dewatering, engraving with all lead and lift for various diameters and depths noted

below.

Item no. 10

Add 6% Area Weightage

For 2.0 Mtr. Depth

Manhole Frame & Cover

Plastic foot Steps

Add 6% Area Weightage

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 52

Page 68: PROVIDING UGD SYSTEM TO CONNECT 300 KLD STP, … · ELECTRONICS CITY INDUSTRIAL TOWNSHIP AUTHORITY 7(P), ELCIA Complex, Electronics City, Bangalore – 560 100 PROVIDING UGD SYSTEM

(Market rate inclusive of all taxes)

= Rs 20000.00/ HPCST @ 2 % Rs 400.00/ HP

Total Rs 20400.00/ HP

Transportation @ 2 % Rs 408.00/ HP

Total Rs 20808.00/ HP

Erection & Commissioning @ 10 % Rs 2040.00/ HP

Total Rs 22848.00/ HP

Rs 913.92/ HP

Rs 23761.92/ HP

Total = Rs 23761.92/ HP

200mm diameter check valve with accessories

= Rs 19919.00/Set

= Rs 796.76/ Set

Total = Rs 20715.76/Set

Lump sum

=

Total Amount = Rs 250000.00 /

(Approved for Rupees Two Lakh(s) Fifty Thousand Only)

Item no. 13

Supplying valves of board approved make confirming to relevant ISS with latest amendments as detailed

below of following diameter and types and conveying to work site, loading, unloading, stacking etc., complete

with all lead and lift. The rate is inclusive of cost of Bolts and Nuts. Cast steel double flanged dual plate

Check valve Class 300 conforming to API : 594.

(SR Item No.9(10), page 63 of Karnataka Urban Water Supply and drainage board, Bangalore, for 2014 - 15)

Basic Rate

Add 4% of composite tax

(Approved for Rupees Twenty Thousand Seven Hundred Fifteen And Paise Seventy Six Only)

(Approved for Rupees Twenty Three Thousand Seven Hundred Sixty One And Paise Ninety Two Only)

Item no. 11

Design manufacture, supply, erection, trail running, performance test and commissioning of Wastewater Non

Clogging Submersible Pump of approved make with all other standard accessories and safety devices etc.,

complete as per specifications, terms and conditions of contract.

Base Rate for pump and motor

Add 4% of composite tax

Rate per HP

Dismantling, Plastering and Removing the debris with a lead upto 200 m.

Basic Rate

Item no. 12

Rs 250000.00 /

Client: Electronic City Industrial Township Authority UGD System Phase-1 at Electronic City DETAILED PROJECT REPORT

Consultant: E I Technologies Pvt. Ltd. Page 53