(prs of river amravati)...(prs of river amravati) page 1 of 8 national mission for clean ganga...

108
(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb 20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UTCompliance Status 1 Ensure 100% treatment of sewage at least insitu remediation 31.03.2020 Presently there is no any proposal for insitu remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 31.03.2020 PRH & RDD was informed to submit the action plan for the sewage generated from the villages Limbet, Hirapor, Sangpur, Pardi, Piprod, and Dadhal for 1.36 MLD discharge 2 Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 31.03.2021 3 Chief Secretaries may set up appropriate monitoring mechanism at State level Specifying accountability of nodal authorities not below the Secretary Level Chief Secretaries may have an accountable person attached in their office for this purpose. Monitoring at State level must take place 22.01.2020 22.01.2020 Fortnightly commencing 21.12.2019 Quarterly RRC meeting held at GPCB, Gandhinagar to review the progress & minutes of the same (having progress status) is regularly submitted to CPCB Reviews of all NGT matters are taken frequently under chairmanship of Hon’ble CS (Last meeting was conducted on 24/12/2019) in matter of O.A. No.:606/2018 4 Progress report may be furnished by the States/UTs to Secretary, Ministry of Jal Shakti Member Secretary, CPCB Monthly (preferably before 20 th of every month) Noted & Complied 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting sources including drains contributing to river pollution and action as per NGT order on insitu treatment Identification of polluting sources including drains contributing to river pollution is already completed and submitted in the PRS action plan. Insitu treatment:Pl. refer point no:1

Upload: others

Post on 09-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAmravati)

Page 1 of 8 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently  there  is no any proposal  for  in‐situ  remediation.    However,  as  per  the suggestion  given  by  Assessment  team during  meeting  held  on  04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached  by  UDD/GUDM/Concerned for technical support in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  PRH &  RDD was  informed  to  submit  the action plan for the sewage generated from the  villages  Limbet,  Hirapor,  Sangpur, Pardi, Piprod,   and Dadhal  for   1.36 MLD discharge   

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020 Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the  progress  & 

minutes  of  the  same  (having  progress 

status) is regularly submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently under chairmanship of Hon’ble CS  (Last  meeting  was  conducted  on 24/12/2019)  in  matter  of  O.A.    No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & Complied 

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources including  drains  contributing  to  river pollution  is  already  completed  and submitted in the PRS action plan.  In‐situ treatment:‐ Pl. refer point no:‐1    

Page 2: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAmravati)

Page 2 of 8 

 

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure: ‐‐ Gap analysis: 1.36 MLD (from the Villages) Proposed : ‐‐  Completion Timeline : ‐‐ PRH &  RDD was  informed  to  submit  the action plan for the sewage generated from the  villages  Limbet,  Hirapor,  Sangpur, Pardi, Piprod,   and Dadhal  for   1.36 MLD discharge 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  There  is  no  Industries  in  the  vicinity  of River Amravati  and  there  is  no  discharge of industrial effluent in to Amravati river 

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  Data not available Letter issued to concern authorities 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – I 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There are total 321 # of HCUs (Health Care Units)  located  in  the  Ankleshwar  taluka, treatment  &  disposal  of  Bio  Medical Waste of which is being taken care of by a common  facility  M/s,  Globe  Bio  Care located in GIDC Ankleshwar. Industrial Waste:‐ 

In  the  State,  all  hazardous  waste generating  units  are  consented  with  the authorization  under  Haz.  Waste Management  Rules,  amended  time  to time &  they  are  disposing  their waste  to TSDF/CHWIF/registered  recycler  under Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the 

Page 3: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAmravati)

Page 3 of 8 

 

recently  framed  draft  bill  titled “Conservation, Protection, Regulation and Management of Ground Water  in Gujarat State”  in the meeting held on 04/02/2020 at  GPCB  with  PRS  Assessment  Team nominated by Ministry of Jal Shakti which is  in  process  and within  3 months  to  be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date is attached as Annexure – II (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed during the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of  Jal Shakti about  proposal  sent  by  them  to  CAMPA for  funding of  around Rs. 5  crore  for  the development  of  Biodiversity  Park.  Team suggested  tying  up  with  AMC  as  they already  have  some  plan  to  develop Biodiversity park at Khari under NRCP.  

 

 

 

 

      

 

Page 4: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAmravati)

Page 4 of 8 

 

Annexure –I (Amravati) 

Progress/Status Report of the River/PRS water quality Monitoring (Feb‐2020):‐ 

Sr.no.  Location ID   Name of Location  Parameter 

DO (mg/l)  pH  BOD (mg/l)  COD 

(mg/l) 

Total coliform 

(MPN/ 100ml) 

Fecal coliform 

(MPN/100 ml) 

1  43527  At village Dadhal  6.77  7.82  1.01  8  130  49 

 

Progress /Status Report for Ground water quality monitoring pertaining to PRS River (Feb‐2020):‐ 

 

Location ID  

Name of Location  Parameter 

pH  BOD 

(mg/l) 

COD 

(mg/l) 

Cu  mg/l 

T.Cr. mg/l 

H.Cr. mg/l 

Fe mg/l  Pb  mg/l 

Mn  mg/l 

Ni mg/l 

Zn  mg/l 

50637  Jitali Water works  7.13  0.34  5  0.058  BDL  BDL  0.094  BDL  ‐‐‐  0.050  0.027 

Page 5: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAmravati)

Page 5 of 8 

 

Drain details with flow: 

Sr. 

No 

Location   Name of Inletting River/Drain  Discharge *(Cusec) 

Max  Min 

1  Limbet Gram 

Panchayat‐ Ta. 

Jhagadia 

 

Domestic w/w drain pipe line 

outlet  in to River Amravati  

0.1878  0.1 

2  HiraporGram 

Panchayat‐ Ta. 

Valia 

 

Domestic w/w drain pipe line 

outlet in to River Amravati  

0.2120  0.1  

3  Sangpur Gram 

Panchayat‐ Ta. 

Ankleshwar 

 

Domestic w/w drain pipe line 

outlet  in to River Amravati  

0.2884  0.2  

4  Pardi 

(Pardi‐Piplod 

Group Gram 

Panchayat)‐ Ta. 

Ankleshwar 

Domestic w/w drain pipe line 

outlet  of Pardi  in to River 

Amravati  

0.0633  0.03 

5  Piprod 

(Pardi‐Piplod 

Group Gram 

Panchayat)‐ Ta. 

Ankleshwar 

Domestic w/w drain pipe line 

outlet  of Piprod  in to River 

Amravati  

0.0656  0.03 

6  Avadar Gram 

Panchayat‐ Ta. 

Ankleshwar 

Domestic w/w drain pipe line 

outlet  in to River Amravati  

0.1440  0.1 

7.  Dadhal Gram 

Panchayat‐ Ta. 

Ankleshwar 

Domestic w/w drain pipe line 

outlet in to River Amravati  

0.3991  0.4 

 

 

 

 

Page 6: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAmravati)

Page 6 of 8 

 

 

Annexure‐II 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

Sr.No  River name  Details/Status 

1  Amravati  Data/details will be furnished soon 

 

Annexure‐III 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

Stretch/river  Existing 

plantation/vegetation 

cover details 

Proposed plan to 

cover remaining 

gap along river 

/river stretch 

Time limit  Remarks 

Amravati (Dadhal  

to Ankleshwar)  

8.00 Km  

1200 trees Target submitted by APCCF for all the Rivers of 

Gujarat is as per attached details in Annexure‐A 

Source:‐ Social Forestry Wing, Aranya Bhavan, Gandhinagar 

 

 

 

 

 

 

 

 

 

Page 7: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAmravati)

Page 7 of 8 

 

Annexure‐A 

 

Page 8: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAmravati)

Page 8 of 8 

 

 

Page 9: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 1 of 10 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for February ‐ 2020 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sr. No. 

Activity to be monitored  Timeline  Submission of Progress by States/UT‐Compliance Status 

1  Ensure  100%  treatment    of  sewage  at least in‐situ remediation 

31.03.2020  Presently  there  is  no  any  proposal  for  in‐situ remediation.   However,  as  per  the  suggestion given by Assessment team during meeting held on  04/02/2020, NEERI, UP Govt.,  Punjab Gov. etc  may  be  approached  by UDD/GUDM/Concerned  for  technical  support in the matter 

  Commencement  of  setting  up  of  STPS and connecting all  the drains and other sources of generation of  sewage  to  the STPs must be ensured 

31.03.2020  Vapi Namdha (14 MLD) – Dec –2020 Vapi Chandor (29.53 MLD) ‐ May‐2021 Vapi Notified  Area  Authority  (5 MLD)  –  Sep  ‐2021 

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021  STPs:‐ Vapi Namdha (14 MLD) – Dec –2020 Vapi Chandor (29.53 MLD) ‐ May‐2021 Vapi Notified  Area  Authority  (5 MLD)  –  Sep  ‐2021 CETPs:‐ CETP  Vapi  (VGEL)  ‐  Expansion  55  to  70 MLD. Dec‐2019  (Timeline  already  due,  EC  awaited however, CETP is meeting with the norms) 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020 Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar to review the progress & minutes 

of the same (having progress status) is regularly 

submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently  under  chairmanship  of  Hon’ble  CS (Last meeting was conducted on 24/12/2019) in matter of O.A.  No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & Complied  

Page 10: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 2 of 10 

 

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources  including drains contributing  to river pollution  is already completed  and  submitted  in  the  PRS  action plan.  In‐situ treatment:‐ Pl. refer point no:‐1    

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure:  ‐‐‐ Gap analysis: 20.5 MLD Proposed : 48.53 MLD Completion Timeline: December 2021  Proposed Plan with Present Status:‐ Vapi Namdha (14 MLD) ‐ Work in Progress. 25 % completed.  Expected to complete by Sep –2020 Vapi Chandor  (29.53 MLD)  ‐  Land proposal  at revenue  level.  Tender  invited.  Expected  to complete by May‐2021 Vapi Notified Area Authority (5 MLD)  ‐ Design to be  finalized. Expected  to complete by Sep  ‐2021 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  GIDC  Vapi  Estate  located  at  Bank  of  River Damanganga.  519  Nos.  of  units  having discharge  into CETP Vapi  (55 MLD). At present CETP meeting with the norms. Existing CETP/ETP:‐ 

CETP  VGEL‐55 MLD 

M/s.  GHCL,  Sarigam‐2.5  MLD. Meeting with the Norms 

Proposed  Expansion  with  Status:‐VGEL  ‐ Proposed Expansion 55 to 70 MLD. EC awaited. VGEL proposed to complete their up gradation up  to March  –  2020.  Time  line  is  already  due but CETP at present meeting with norms. 

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  5 (iv) Status is attached as Annexure – I 

Page 11: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 3 of 10 

 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – II 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There  are  total  717  #  of  HCUs  (Health  Care Units),  treatment  &  disposal  of  Bio  Medical Waste  of  which  is  being  taken  care  of  by  a 

common  facility  M/s  En‐Cler  Biomedical Waste Treatment Pvt. Ltd located in Surat Industrial Waste:‐ 

In  the  State,  all  hazardous  waste  generating units  are  consented  with  the  authorization under  Haz.  Waste  Management  Rules, amended  time  to  time  &  they  are  disposing their waste  to TSDF/CHWIF/registered  recycler under  Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the  recently framed  draft  bill  titled  “Conservation, Protection,  Regulation  and  Management  of Ground Water  in Gujarat State”  in the meeting held  on  04/02/2020  at  GPCB  with  PRS Assessment Team nominated by Ministry of Jal Shakti which  is  in process and within 3 months to be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by  Irrigation  Dept.  as  on  date  is  attached  as Annexure – III (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details  w.r.t  point  no.  5  (xii)  given  by  Forest Dept.  /PCCF/ACCF/Concerned  as  on  date  is attached as Annexure – IV 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed  during  the  meeting  held  on 04/02/2020  at  GPCB  with  PRS  Assessment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around  Rs.  5  crore  for  the  development  of Biodiversity Park. Team suggested tying up with AMC  as  they  already  have  some  plan  to develop Biodiversity park at Khari under NRCP.  

Page 12: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 4 of 10 

 

 

Annexure‐I 

5 (iv ) Status of Solid Waste Management & Details of Processing Facilities (From Notified Area Authority) 

Types of 

Waste/ 

Characteri

stic of 

waste 

Generated 

Quantity/day 

Collection/  

Storage facility 

with capacity 

Disposal/ 

Treatment facility 

with capacity along 

with location 

Total Gap with 

generation & existing 

treatment facilities if 

any 

Proposed action plan 

/facility to cover gap 

Time 

limit 

Remarks/ 

Present 

Status 

Domestic  8.50 MT  @3 Lakh MT 

 

Total Area – 

3.8 Hectare  

Composting Method 

‐ 5.50 MT/Day  

At Survey/Plot No. 

4804 to 4807, GIDC 

Vapi   (Near TSDF 

Site, GIDC Vapi) 

Gap of 3.00 MT/Day  

 

The Tender for 

Collection, Sorting and 

Recovery of waste and 

set up material 

recovery facility under 

DBFOOM model as per 

Rules, Norms and 

regulation of SWM 

Rules – 2016 

Capacity:‐ 15 MT/Day 

June ‐ 

2019 

Expected to 

complete by 

June‐2020 

Total  8.50 TPD    5.5 TPD  3 TPD  ‐‐  ‐‐  ‐‐ 

 

(From Nagarpalika Vapi) 

 

Types of Waste/ 

Characteristic of 

waste 

Generated 

Quantity/ 

day 

Collection/  

Storage facility 

with capacity 

Disposal/ 

Treatment facility 

with capacity along 

with location 

Total Gap with 

generation & existing 

treatment facilities if 

any 

Proposed action 

plan /facility to 

cover gap 

Time 

limit 

Present Status

Page 13: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 5 of 10 

 

 

 

 

Domestic  50 MT/D   

Capacity: 4 – 5 

Lakh MT. 

 

Total Area: 

31472 Sq. 

Meter.  

 

Vermi Compost – 3 

MT/Day,  

Organic Fertilizers ‐  

100 Kg/Day, 

Material Recovery 

Facility – 12 MT/Day 

At Village Namdha 

Survey No. 113 to 

116.  

Total Gap is 34.9 

TPD. 

Tendering for 

solid waste 

management for  

100 TPD with O 

and M for  9 years 

has been done 

and same has 

been floated in 

new paper on 

18/1/2019 

 

Dec‐ 

2019 

At  present Vapi  has Vermi Compost  –  3 MT/Day, Organic Fertilizer  – 100  Kg/Day, Material Recovery Facility  –  12 MT/Day hence Now  for  34.9 MT/Day  Gap Nagarpalika has  work tender  is  on agreement stage.  Vapi Nagarpalika has  proposed to  work completion upto  July  – 2021.   

Total  50 TPD    15.1 TPD  34.9  TPD  ‐‐  ‐‐  ‐‐ 

Page 14: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 6 of 10 

 

Annexure‐II 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  Progress/Status Report of the River/PRS water quality Monitoring: February ‐ 2020 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

05/02/

2020 

GIDC Vapi Weir  6.90  8.23  0.60  4.00  41.00  210 

Zari Causeway Kachigam  5.10  7.17  2.40  20.00  1600  >1600 

Village Namdha  4.80s  7.28  2.30  32.00  1600  >1600 

   

Progress/Status Report of the River/PRS ground water quality Monitoring: February ‐ 2020 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

05/02/

2020 

Borewell at Jilla Panchyat 

School, Kanta Faliya, 

Village Namdha 

6.90  8.05  0.60  7.00  <2  <2 

Drain details with flow: 

Sr.No.  Location/Name of 

Drain 

Name of Inletting River/Drain  Discharge (MLD) 

Max.  Min. 

1  Zari Causeway 

Kachigaon Bridge, 

Daman (UT) 

Kalkada Khadi (Domestic 

outfall from Vapi Nagarpalika 

Area) 

20 MLD  18 MLD 

2 Near GIDC Weir, Vapi 

Domestic outfall from Village 

Chanod Area 

0.5 

MLD 

0.3 

MLD 

Page 15: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 7 of 10 

 

Annexure‐III Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

Sr.No  River name  Details/Status 

1  Damanganga  Details mentioned as below 

 

 

Page 16: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 8 of 10 

 

Annexure‐IV 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

Stretch/river  Existing 

plantation/vegetation cover 

details 

Proposed plan to 

cover remaining 

gap along river 

/river stretch 

Time 

limit 

Remarks

Damanganga  

(kachigaon to Vapi)  8 ha. Plantation 

Target submitted by APCCF for all the Rivers of Gujarat 

is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 17: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 9 of 10 

 

Annexure‐A 

 

 

Page 18: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverDamanganga)

Page 10 of 10 

 

 

Page 19: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 1 of 9 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for February ‐ 2020 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sr. No. 

Activity to be monitored  Timeline  Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently  there  is no any proposal  for  in‐situ  remediation.    However,  as  per  the suggestion  given  by  Assessment  team during  meeting  held  on  04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached  by  UDD/GUDM/Concerned for technical support in the matter.  

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  Gunjan  STP  proposed  by  Vapi  Notified Area Authority (10 MLD):‐ ‐ 2020. PRH &  RDD was  informed  to  submit  the action plan for the sewage generated from the  village  Chhiri,  Chharwada,  Salvav  & Balitha (18 MLD) 

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020    Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the  progress  & 

minutes  of  the  same  (having  progress 

status) is regularly submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently under chairmanship of Hon’ble CS  (Last  meeting  was  conducted  on 24/12/2019)  in  matter  of  O.A.    No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted &  Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources including  drains  contributing  to  river pollution  is  already  completed  and submitted in the PRS action plan In‐situ treatment:‐ Pl. refer point no:‐1    

Page 20: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 2 of 9 

 

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure:  ‐‐‐ Gap analysis: 26 MLD Proposed : 10 MLD  Completion Timeline: 2020  Proposed Plan and Present Status:‐ 

I. Gunjan  (10  MLD)  proposed  by Vapi  notified  area  authority  to treat the 8 MLD sewage generated from Gunjan, Notified Area.  Time line‐2020 (Land  Issue:‐  Insufficient land). 

II. PRH  &  RDD  was  informed  to submit  the  action  plan  for  the sewage generated from the village Chhiri,  Chharwada,  Salvav  & Balitha (18 MLD) 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  No  any  industrial  effluent  is  being discharge into the stretch of River Kolak  

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  5 (iv) Status is attached as Annexure – I 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – II 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There are total 717 # of HCUs (Health Care Units),  treatment  &  disposal  of  Bio Medical  Waste  of  which  is  being  taken 

care of by a common  facility M/s En‐Cler Biomedical Waste  Treatment  Pvt.  Ltd located in Surat Industrial Waste:‐ 

In  the  State,  all  hazardous  waste generating  units  are  consented  with  the authorization  under  Haz.  Waste 

Page 21: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 3 of 9 

 

Management  Rules,  amended  time  to time &  they  are  disposing  their waste  to TSDF/CHWIF/registered  recycler  under Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the recently  framed  draft  bill  titled “Conservation, Protection, Regulation and Management of Ground Water  in Gujarat State”  in the meeting held on 04/02/2020 at  GPCB  with  PRS  Assessment  Team nominated by Ministry of Jal Shakti which is  in  process  and within  3 months  to  be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5  (viii),  (ix),  (x),  (xi) given  by  Irrigation  Dept.  as  on  date  is attached as Annexure – III (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details  w.r.t  point  no.  5  (xii)  given  by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed during the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of  Jal Shakti about  proposal  sent  by  them  to  CAMPA for  funding of around Rs. 5 Crore  for  the development  of  Biodiversity  Park.  Team suggested  tying  up  with  AMC  as  they already  have  some  plan  to  develop Biodiversity park at Khari under NRCP.  

 

 

Page 22: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 4 of 9 

 

Annexure‐I 

5 (iv ) Status of Solid Waste Management & Details of Processing Facilities  (From Notified Area Authority) 

Types of Waste/ 

Characteristic of 

waste 

Generated 

Quantity/day 

Collection/  

Storage facility 

with capacity 

Disposal/Treatment 

facility with capacity 

along with location 

Total Gap with 

generation & existing 

treatment facilities if 

any 

Proposed action plan /facility to 

cover gap 

Time limit Remarks/Present 

Status as on 

submitted in MPR 

of Jan‐20 

Domestic  8.50 MT  @3 Lakh MT

 

Total Area –  

3.8 Hectare 

Composting Method 

‐ 5.50 MT/Day  

At Survey/Plot No. 

4804 to 4807, GIDC 

Vapi   (Near TSDF 

Site, GIDC Vapi) 

At present @5.50 

MT/day waste is 

converted through 

composting process. 

For the Gap of 3.00 

MT/Day the  

 

The Tender for Collection, 

Sorting and Recovery of waste 

and set up material recovery 

facility under DBFOOM model 

as per Rules, Norms and 

regulation of SWM Rules – 2016 

Capacity: 15 MT/Day 

June ‐

2019 

Expected to 

complete by 

June‐2020 

Total  8.50 MT    5.5 TPD 3.0 TPD 15 TPD ‐‐ ‐‐

 

 

 

 

 

 

 

Page 23: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 5 of 9 

 

Annexure‐II 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  Progress/Status Report of the River/PRS water quality Monitoring (February ‐ 2020): 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

03/02/

2020 

River Kolak at N H No. 8, 

Morai 6.80  8.17  0.80  4.00  170.00  430.00 

River Kolak at Pataliya 

Bridge 5.90  8.07  1.80  23.00  1600  >1600 

   

Progress/Status Report of the River/PRS ground water quality Monitoring (February ‐ 2020): 

BOREWELL OF KOTASHWAR MAHADEV TEMPLE VATTAR Samp ID & Dt   ALK  CHL  BOD  COD  DOX  COL  FCO  TCO  SS  FLU   NIT   NTR   pH   SUP   T.H   TDS  TMP  

275682 ‐ 03/02/2020  144.00  146.00  2.40  7.00 4.20 2.50 <2  <2  10.00 0.23 0.04  0.62  8.27  23.00 165.00 388.00 24.00 

 

Drain details with flow: 

Sr. No.  Location/Name of 

Drain 

Name of Inletting 

River/Drain 

Discharge (MLD) 

Max.  Min. 

1  Morai, Vapi  Bill Khadi 26 MLD 10 MLD

Page 24: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 6 of 9 

 

Annexure‐III 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

Sr. No  River name  Details/Status 

1  Kolak  Details as per below 

 

 

 

Page 25: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 7 of 9 

 

Annexure‐IV 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

Stretch/river  Existing 

plantation/vegetation cover 

details  

Proposed plan to 

cover remaining 

gap along river 

/river stretch  

Time limit  Remarks

Kolak(kikarla to 

salvav)  Nil  

Target submitted by APCCF for all the Rivers of Gujarat 

is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 26: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 8 of 9 

 

Annexure‐A 

 

 

Page 27: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKolak)

Page 9 of 9 

 

 

Page 28: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMahi)

Page 1 of 7 

   

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No. 

Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently  there  is  no  any  proposal  for  in‐situ remediation.    However,  as  per  the  suggestion given by Assessment  team during meeting held on  04/02/2020,  NEERI,  UP  Govt.,  Punjab  Gov. etc  may  be  approached  by UDD/GUDM/Concerned  for  technical support  in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  There  is no any domestic discharge/outlet  in  to this stretch 

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020     22.01.2020 Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the progress & minutes 

of the same (having progress status)  is regularly 

submitted to CPCB 

Reviews of all NGT matters are taken frequently under chairmanship of Hon’ble CS (Last meeting was conducted on 24/12/2019) in matter of O.A.  No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources  including drains  contributing  to  river  pollution  is  already completed and submitted in the PRS action plan. In‐situ treatment:‐ Pl. refer point no:‐1    

Page 29: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMahi)

Page 2 of 7 

   

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure: ‐‐‐  Gap analysis:‐‐‐ Proposed : ‐‐‐  Completion Timeline : ‐‐‐ There  is no any domestic discharge/outlet  in  to this stretch 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  There  is  no  any  industrial  or  domestic discharge/outlet in River Mahi in this stretch. 

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  There is no Nagarpalika area in this stretch of River. 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – I As per the CPCB report (Sep‐18) based on results 

of 2016 & 2017, also Mahi not been  fall  in any 

priority with  <3 mg/L BOD  and  information  for 

the same is already submitted to CPCB.

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There  are  total  105  #  of  HCUs  (Health  Care Units) located in the Thasra Taluka All  are  members  of  either  M/s.  Samvedana BMW  Incinerator  or M/s.  Pollucare  Biomedical Management Pvt. Ltd. Industrial Waste:‐ 

In  the  State,  all  hazardous  waste  generating units  are  consented  with  the  authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered  recycler  under  Rule‐9/Co‐processing  and  as  per  consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the  recently framed  draft  bill  titled  “Conservation, Protection,  Regulation  and  Management  of Ground Water  in Gujarat State”  in  the meeting held  on  04/02/2020  at  GPCB  with  PRS Assessment Team nominated by Ministry of  Jal Shakti which  is  in process and within 3 months to be submitted to the Assembly 

Page 30: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMahi)

Page 3 of 7 

   

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5  (viii),  (ix),  (x),  (xi) given by  Irrigation  Dept.  as  on  date  is  attached  as Annexure – II (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details  w.r.t  point  no.  5  (xii)  given  by  Forest Dept.  /PCCF/ACCF/Concerned  as  on  date  is attached as Annexure – III 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed  during  the  meeting  held  on 04/02/2020 at GPCB with PRS Assessment Team nominated  by  Ministry  of  Jal  Shakti  about proposal sent by them to CAMPA for funding of around  Rs.  5  crore  for  the  development  of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP. 

 

 

 

 

 

 

 

 

 

Page 31: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMahi)

Page 4 of 7 

   

Annexure‐ I 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  

Latest water quality of polluted river 

Month  Location  DO 

(mg/l) 

pH  BOD 

(mg/l) 

COD 

(mg/l) 

Fecal 

Coliform 

(MPN/100 

ml) 

Total 

coliform 

(MPN/100 

ml) 

Feb 2020  River Mahi at 

Sevalia 

7.8  8.24  0.55  4  12  49 

Annexure‐II 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

Sr.No  River name  Details/Status 

1  Mahi  1. Environmental flow: 300 cusecs 2.Detail of Good lrrigation Practices and Flood Plain Management Zone: Detail given below 

 

Page 32: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMahi)

Page 5 of 7 

   

Annexure‐III 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

Stretch/river  Existing  plantation/vegetation 

cover details  

Proposed  plan  to 

cover  remaining 

gap  along  river 

/river stretch  

Time 

limit 

Remarks 

Mahi, Shedhi  

8,32,000  Plants  were  planted 

along the Mahi, Shedhi and Other 

river  in the areas available under 

the  Vanmahotsav  and  other 

Schemes  of  the  forest 

Department  with  the  co‐

operation of local People.  

Target submitted by APCCF for all the Rivers of Gujarat is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 33: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMahi)

Page 6 of 7 

   

Annexure‐A 

 

Page 34: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMahi)

Page 7 of 7 

   

 

Page 35: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 1 of 9 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently there is no any proposal for in‐situ remediation.    However,  as  per  the suggestion given by Assessment team during meeting  held  on  04/02/2020,  NEERI,  UP Govt., Punjab Gov.  etc may be  approached by  UDD/GUDM/Concerned  for  technical support in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  Kheda STP (5.2 MLD) ‐ Feb‐2021 Underground  drainage  Project  for  Nadiad Nagarpalika  ‐ Feb‐2021 

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021  Kheda  STP  (5.2 MLD) GWSSB‐  Expected to be commissioned by Feb‐2021 

Underground  drainage  Project  for Nadiad Nagarpalika ‐ Feb‐2021  

ETP:‐ Mafatlal Industries Limited Upgradation – RRC asked  to submit  the proposal  of  modification  for  ZLD  to achieve River discharge norms. Unit has submitted  letter  dated  20/01/2020 regarding  permission  of  Nadiad Nagarpalika  to  continue  discharge  of treated  wastewater  to  inlet  of  STP  via drainage line.  

CETP Nadiad ‐ Dec‐2020 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020 Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the  progress  & 

minutes  of  the  same  (having  progress 

status) is regularly submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently  under  chairmanship  of  Hon’ble CS  (Last  meeting  was  conducted  on 24/12/2019)  in  matter  of  O.A.    No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted &  Complied.  

Page 36: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 2 of 9 

 

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources  including drains  contributing  to  river  pollution  is already completed and submitted in the PRS action plan.  In‐situ treatment:‐ Pl. refer point no:‐1    

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing  infrastructure:  52  MLD  (Spare capacity):‐  Gap analysis: 8.2 MLD Proposed : 5.2 MLD  Completion Timeline : Feb‐2021 Proposed Plan and Present Status:‐ 

I. Kheda  STP  (5.2  mld):‐  Feb‐2021 Primary  line  out  work  in  progress. Work  order  issued.  DILR demarcation to be done.  

II. Underground drainage Project ‐  Feb‐2021 Nadiad  Nagarpalika  has  STP  of adequate  capacity.  Underground drainage  Project  Phase  I  is completed.  Work  order  is  issued dated  17/01/2020  by  GUDC  for Underground  drainage  Project Phase II under AMRUT.  

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  No of Industries:‐ GIDC Nadiad has 21 no. of 

industries ( 13 discharging units having 

captive ETP while rest 8 are zero discharge) 

M/s. Mafatlal Industries Limited  (5 MLD):‐ 

ETP Upgradation – RRC asked to submit the 

proposal of modification for ZLD to achieve 

River discharge norms 

Proposed CETP & Status:‐ 

CETP Nadiad 0.5 MLD .Timeline:‐ Dec‐2020 

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  5 (iv) Status is attached as Annexure – I 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – II 

Page 37: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 3 of 9 

 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  

There are  total 232 # of HCUs  (Health Care 

Units)  located  in  the  Nadiad  and  Kheda 

taluka,  treatment & disposal of Bio Medical 

Waste of which  is being  taken  care of by a 

common  facility  M/s.  Samvedana  BMW 

Incinerator  or  M/s.  Pollucare  Biomedical 

Management Pvt. Ltd. 

Industrial Waste:‐ 

In the State, all hazardous waste generating 

units  are  consented with  the  authorization 

under  Haz.  Waste  Management  Rules, 

amended time to time & they are disposing 

their  waste  to  TSDF/CHWIF/registered 

recycler under Rule‐9/Co‐processing  and  as 

per consented conditions 

(vii)        Ground water regulation    GWRDC has given details about the recently 

framed  draft  bill  titled  “Conservation, 

Protection, Regulation  and Management  of 

Ground  Water  in  Gujarat  State”  in  the 

meeting  held  on  04/02/2020  at GPCB with 

PRS  Assessment  Team  nominated  by 

Ministry of Jal Shakti which is in process and 

within  3  months  to  be  submitted  to  the 

Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date is attached as Annexure – III (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed  during  the meeting  held  on 04/02/2020  at  GPCB  with  PRS  Assessment Team  nominated  by  Ministry  of  Jal  Shakti about proposal sent by  them  to CAMPA  for funding  of  around  Rs.  5  crore  for  the development  of  Biodiversity  Park.  Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.  

Page 38: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 4 of 9 

 

Annexure‐ I 

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:  

Types of 

Waste/ 

Characteristic 

of waste 

Generated 

Quantity/ day 

Collection/ 

Storage facility 

with capacity 

Disposal/ 

Treatment facility 

with capacity along 

with location 

Total Gap 

with 

generation & 

existing 

treatment 

facilities if 

any 

Proposed 

action plan 

/facility to 

cover gap 

Time 

limit 

Respons

ible 

agency 

Present Status 

Domestic  85 TPD  70 TPD 45 Ton 

MRF 

15 Ton Pit 

composting 

25 TPD  25 Tone 

Wastage will be 

treat by on site 

waste 

composting 

machines 

Year 

Nadiad 

Nagar 

palika 

SLF  site  ‐Proposed  to  be carried  out  in cluster  level  by concerned authority.  Present  status  of SLF ‐ Nil Identification  of land – 6 months  Design  and construction  –  6 months Commissioning of 

SLF – 1 year 

(31/03/2022) 

Domestic (Dry 

Waste + 

Wet Waste) 

6 TPD  6 TPD Iyavapura dumping 

Site At‐Kheda 

Not scientifically 

developed 

6 TPD Action Plan 

Under Planning 

31‐

4‐

2019

Kheda 

Nagar 

palika 

Total  91 TPD  76 TPD 31 TPD  ‐‐ ‐‐ ‐‐

Page 39: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 5 of 9 

 

Annexure‐II 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  

Latest water quality of polluted river 

Month  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

Feb 2020  River Shedhi at 

Kheda Matar Bridge 

5.6  7.76  2.7  21  120  350 

At Nadiad ‐

Mahemdabad 

Bridge 

5.2  7.66  0.96  12  96  240 

Latest ground water quality in the catchment of polluted River Shedhi 

Month  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

Oct 2019 (Half 

yearly) 

Borewell Nadiad 

GIDC Water Works 

Not Applicable  7.53  0.48  4  <2  <2 

 

Drain details with flow: 

Sr.No.  Location  Name of Inletting 

River/Drain 

Discharge (MLD) 

Max.  Min. 

1  Nadiad  Natural Drain  34  28 

2  Kheda  Natural drain  0.020  0.010 

Page 40: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 6 of 9 

 

Annexure‐III 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

 

Sr.No  River name  Details/Status 

1  Shedhi  Environmental Flow:‐ River is not a perennial river Detail of good irrigation practices:‐ Detail attached below Details on flood plain management zone:‐ Detail attached below 

 

 

 

 

 

 

Page 41: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 7 of 9 

 

Annexure‐IV 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

Stretch/river  Existing 

plantation/vegetation  cover 

details  

Proposed plan  to  cover 

remaining  gap  along 

river /river stretch  

Time 

limit 

Remarks 

Mahi, Shedhi  

8,32,000 Plants were planted 

along  the  Mahi,  Shedhi  and 

Other  river  in  the  areas 

available  under  the 

Vanmahotsav  and  other 

Schemes  of  the  forest 

Department  with  the  co‐

operation of local People.  

Target  submitted  by  APCCF  for  all  the  Rivers  of 

Gujarat is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 42: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 8 of 9 

 

Annexure‐A 

 

Page 43: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverShedhi)

Page 9 of 9 

 

 

Page 44: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 1 of 17 

 

National Mission for Clean Ganga 

Format for Submission of Monthly Progress Report by States/UTs for Feb‐2020 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently  there  is no any proposal  for  in‐situ  remediation.    However,  as  per  the suggestion  given  by  Assessment  team during  meeting  held  on  04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached  by  UDD/GUDM/Concerned for technical support in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  Signapore  (155  MLD)  –  Expansion.  Dec‐2020 Gavier (53 MLD) – Expansion. March‐2021 Bhatar  (162  MLD)  –  Expansion.  March‐2021 Bhesan (100 MLD) – Expansion. June‐ 2020STPs under Tapi Suddhikaran Yojana (Total 37 STPs by SUDA and GWSSB) –Feb‐22  to Dec‐22 

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020    Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the  progress  & 

minutes  of  the  same  (having  progress 

status) is regularly submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently under chairmanship of Hon’ble CS  (Last  meeting  was  conducted  on 24/12/2019)  in  matter  of  O.A.    No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per 

     Identification  of  polluting  sources including  drains  contributing  to  river pollution  is  already  completed  and submitted in the PRS action plan.. 

Page 45: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 2 of 17 

 

NGT  order  on  insitu treatment 

In‐situ treatment:‐ Pl. refer point no:‐1    

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure:  470 MLD Gap analysis: 370.15 MLD Proposed : 564.99 MLD  Completion Timeline: December 2022  Proposed STPs and present status:‐ 

Signapore (155 MLD) – Upgradation & expansion.50% completed. Work in Progress. Expected to complete by Dec‐2020 

Gavier  (53  MLD)  ‐  Network  is under  process.  Expected  to complete by March‐2021 

Bhatar  (162  MLD)  –  Expansion. 50%  completed.Work  in Progress. Expected  to  complete  by March‐2021 

Bhesan  (100  MLD)‐  Expansion. 80% completed. Work in Progress. Expected  to  complete  by  June‐ 2020 

STPs  under  Tapi  Suddhikaran Yojana (Total 37 STPs by SUDA and GWSSB) – Proposed. Tender to be invited  subject  to  land possession issues.  Expected  to  complete  by Feb‐22  to  Dec‐22  (Please  refer Annexure V for details).  

In  last  video  conference meeting, CS  has  intimated  to  concerned dept. to resolve the issues 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  No Industrial wastewater discharge into this river stretch  

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with 

  5 (iv) Status is attached as Annexure – I 

Page 46: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 3 of 17 

 

completion timeline 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – II 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There  are  total  3683  #  of  HCUs  (Health Care  Units),  treatment  &  disposal  of  Bio Medical  Waste  of  which  is  being  taken care  of  by  a  common  facility M/s, Globe 

Bio Care and En‐Cler Biomedical Waste Treatment Pvt. Ltd located in Surat Industrial Waste:‐ 

In  the  State,  all  hazardous  waste generating  units  are  consented  with  the authorization  under  Haz.  Waste Management  Rules,  amended  time  to time &  they  are  disposing  their waste  to TSDF/CHWIF/registered  recycler  under Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the recently  framed  draft  bill  titled “Conservation, Protection, Regulation and Management of Ground Water  in Gujarat State”  in the meeting held on 04/02/2020 at  GPCB  with  PRS  Assessment  Team nominated by Ministry of Jal Shakti which is  in  process  and within  3 months  to  be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5  (viii),  (ix),  (x),  (xi) given  by  Irrigation  Dept.  as  on  date  is attached as Annexure – III (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details  w.r.t  point  no.  5  (xii)  given  by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed during the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of  Jal Shakti about  proposal  sent  by  them  to  CAMPA 

Page 47: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 4 of 17 

 

for  funding of  around Rs. 5  crore  for  the development  of  Biodiversity  Park.  Team suggested  tying  up  with  AMC  as  they already  have  some  plan  to  develop Biodiversity park at Khari under NRCP.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 48: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 5 of 17 

 

Annexure‐I 

5 (iv ) Status of Solid Waste Management & Details of Processing Facilities 

 Types of Waste/ Characteristic of

waste

Generated Quantity/day

Collection/Storage facility with capacity

Disposal/Treatment facility with capacity along with location

Total Gap with generation &

existing treatment facilities if any

Proposed action plan /facility to cover gap

Time limit Remarks/Present Status

Wet waste  800 TPD  100%  collection  and 

transportation facility is 

in place 

50 TPD bio methanation 

at APMC market 

700  TPD  composting  at 

Khajod Disposal site 

10  TPD  decentralized 

plants  for  onsite 

treatment 

40 TPD

 

SMC  has  formulated 

policy  of  Decentralized 

waste  processing  facility 

i.e.  OWC,  50  to  100% 

subsidy  is being provided 

for such kind of Facility. 

7  nos  of  10  TPD 

decentralized  processing 

plants  have  been 

planned. 

12 month Surat  Municipal 

Corporation  has 

municipal  waste 

disposal  site  at 

Khajod  which  is  in 

operation  

Dry Waste 

 

 

Plastic waste 

 

 

C&D waste 

 

Textile ‐ cloth 

cutting  waste 

(Chindi waste) 

500 TPD 

 

 

100 TPD 

 

 

300 TPD 

 

 

100 TPD 

 

100%  collection  and 

transportation facility is 

in place 

500  TPD  RDF  unit  at Khajod disposal site 

20  TPD  Plastic 

treatment  unit  at 

Bhatar 

300 TPD C&D treatment 

unit at Kosad 

100 TPD  Plant is under tendering 

stage at SMC level. 

80 TPD

 

 

SMC  has  planned  to 

expand  the  processing 

capacity  in  next  12‐18 

months 

 

12 ‐18

months 

Total 1800 TPD 1680 TPD 120 TPD -- -- --

 

Page 49: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 6 of 17 

 

 

Annexure‐II 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  Progress/Status Report of the River/PRS water quality Monitoring: 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

03‐02‐2020  Kathor, N.H. 8  7.26  7.8  0.86  8  11  53 

03‐02‐2020  Varachha Bridge  7.03  7.98  0.89  9  9  51 

05‐02‐2020  ONGC Bridge  6.28  7.79  1.7  24  11  77 

03‐02‐2020  Rander  7.13  7.7  0.99  12  9  83 

05‐02‐2020  Swamivivekanand 

Bridge 6.72  7.7  1.48  22  9  63 

05‐02‐2020  Sardar Bridge  6.49  7.68  1.62  24  11  51 

05‐02‐2020  Umara Temple  6.41  7.01  1.58  ‐‐  9  83 

   

Progress/Status Report of the River/PRS ground water quality Monitoring: 

Name of Location Date BOD DOX FCO FLU MAG NH3 pH SS SUP T.H TCO TDS TKN TMP

BORE WELL OF KADOD, TA.MANDVI

Oct-2019 0.88 4.19 8 0.18 34.1 0.28 7.55 8 34 250 36 710 2.8 28

BORE WELL OF SHREE SAI ASHA PETROL PUMP(IOC),BHATHA

Oct-2019 0.98 2.9 9 0.28 55.94 0.56 7.98 6 13 410 41 546 2.24 28

 

Page 50: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 7 of 17 

 

 

Drain details with flow: 

Sr.No.  Location/Name of Drain  Discharge (MLD) 

Average 

  Outside SUDA ‐ L 

1  Koliwad  0.12 

2  Rataniya   0.09 

3  Tarsada  0.47 

4  Village near Tarsada   2.44 

5  Mori  0.07 

6  Bhamaiya   0.08 

7  Vaghechha   0.16 

8  Timba   0.40 

9  Machhi  0.10 

10  Dhatva   0.20 

11  Dungra  0.45 

12  Kholeshwar  0.21 

  SUDA‐L 

13  Kamrej  6.58 

14  Kholwad  4.58 

15  Vav  14.37 

16  Laskana  4.75 

17  Koli Bharthana   3.84 

18  Valak Creek  43.24 

19  Varachha Creek  51.72 

20  Jat Bharthana  5.19 

21  Pasodara  4.09 

22  Sevni  4.98 

  SMC‐L 

23  Kotar‐7  75 

24  Kotar‐9  5 

25  Makkai Bridge   9 

26  Sardar Bridge   11 

27  Umra Drain  7 

28  Dimple Row House   5 

29  Rundh Jakatnaka  2 

  Outside SUDA – R 

30  Mandvi   22.28 

Page 51: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 8 of 17 

 

31  Gamtalav Bujrang   0.23 

32  Ushkhed khurd  0.07 

33  Puna gam   0.26 

34  Unn ‐kosadi   0.21 

35  Nandpore   1.23 

36  Kharoli  1.07 

37  Kevadiya ‐ Vadod  0.20 

38  Bodhan  0.88 

39  Nogama  1.30 

40  Karjan  0.46 

41  Virpore  0.20 

42  Limodara  0.67 

43  Dhoran Pardi  12.31 

44  Khanjroli  0.14 

45  Ghala   0.66 

  SUDA – R 

46  Kathor   13.56 

47  Bharthana  17.29 

  SMC – R 

48  Swaminarayan Temple   7.5 

49  Pal Jakatnaka   12.5 

50  Pal‐Halpativas  15 

Page 52: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 9 of 17 

 

Annexure‐III 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

Sr.No  River name  Details/Status 

1  Tapi  Details mentioned as below 

 

 

Page 53: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 10 of 17 

 

 

 

Annexure‐IV 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

The details received from  Social Forestry wing, Aranya Bhavan, Gandhinagar are as under 

Stretch/river  Existing 

plantation/vegetation 

cover details 

Proposed plan to 

cover remaining gap 

along river/river 

stretch 

Time limit  Remarks 

Tapi  5,10,035 sq.mt  1,50,000 sq.mt  24 

months 

at Katargam Water Works 

Tapi  River  

(khadod to surat)  

 

2350  trees  (Source:‐ 

Social  Forestry  wing, 

Aranya Bhavan) 

Target submitted by APCCF for all the Rivers of Gujarat 

is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

Page 54: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 11 of 17 

 

Annexure‐A 

 

Page 55: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 12 of 17 

 

 

Page 56: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 13 of 17 

 

Annexure‐V 

Break up of STPs proposed in Tapi Suddhikaran Yojana 

River   Proposed (P) STPs, capacity  

Present Status (%)  

Timeline given in RAP 

Expected time line  

Remarks  

Tapi  Bharthana SPS 1 at TPS‐83 (22.7 mld) SUDA   

Tender to be invited subject to land possession (0%)  

February‐2022   

February‐2022   

Land is finalised, Detail engineering is started but possession is yet to be received. SUDA give consent letter to collectorate to submit 10 % cost of land for advance possession vide letter dtd 23/12/2019  

  Kamrej‐ Dungra 

(0.67 mld) SUDA  

Tender to be 

invited subject 

to land 

possession 

Februar

y‐2022  

February

‐2022*  

Other parcel of  land  to be neemed  in  lieu 

of GAUCHAR land by GoG. Proposal is sent 

by  Collectorate  to  revenue  department, 

GoG  on 14/10/2019  

  Kamrej‐ 

Kholeshwar (0.33 

mld) SUDA  

Tender to be 

invited subject 

to land 

possession 

Februar

y‐2022 

February

‐2022* 

Land  is  finalised,  Detail  engineering  is 

started  but  possession  is  yet  to  be 

received.  Hon.  Collector  shri  Instructed 

mamlatdar    to  check  land  is  whether 

GAUCHAR  or  GOVERNMENT  on 

25/11/2019.  

  Kamrej‐ Kamrej 1 

(18.5 mld) SUDA  

Detail 

Engineering 

stated.  

Februar

y‐2022 

February

‐2022*  

Land Possession received , 

  Kamrej‐ Valak 

creek (43.24 mld) 

SUDA  

Work in 

Progress  

Decemb

er‐2021 

Decemb

er‐

2021*  

Land Possession received  

  Kamrej‐ Vav‐ 1 

(16.09 mld) SUDA  

Tender to be 

invited subject 

to land 

possession 

Februar

y‐2022 

February

‐2022* 

Land  is  already NEEM  for  “Smashangruh” 

Hon. Collector shri will visit site  

  Kamrej‐ Laskana 

(5.17 mld) SUDA  

Tender to be 

invited subject 

to land 

possession 

Februar

y‐2022 

February

‐2022*  

Other parcel of  land  to be neemed  in  lieu 

of GAUCHAR land by GoG. Proposal is sent 

by  Collectorate  to  revenue  department, 

GoG on 14/10/2019  

  Kamrej  – 

Kolibharthana 

(4.3 mld) SUDA  

Tender  to  be 

invited  subject 

to  land 

possession 

Februar

y‐2022 

February

‐2022*  

Other parcel of  land  to be neemed  in  lieu 

of GAUCHAR land by GoG. Proposal is sent 

by  Collectorate  to  revenue  department, 

GoG on 14/10/2019  

Page 57: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 14 of 17 

 

  Kamrej‐ Varachha 

Creek (51.72 mld) 

SUDA  

Work    in 

Progress  

Decemb

er‐2021 

Decemb

er‐

2021* 

Land Possession received  

  Kamrej‐  Pasodara 

(4.15 mld) SUDA  

Tender  to  be 

invited  subject 

to  land 

possession 

Februar

y‐2022 

February

‐2022*  

Other parcel of  land  to be neemed  in  lieu 

of GAUCHAR land by GoG. Proposal is sent 

by  Collectorate  to  revenue  department, 

GoG on 14/10/2019  

  Kamrej‐  Karjan  (1 

mld) SUDA  

Tender  to  be 

invited  subject 

to  land 

possession 

Februar

y‐2022 

February

‐2022*  

Other parcel of  land  to be neemed  in  lieu 

of GAUCHAR land by GoG. Proposal is sent 

by  Collectorate  to  revenue  department, 

GoGon 25/10/2019 

  Kamrej‐  Dhoran 

Creek  (1.18  mld) 

SUDA  

Tender  to  be 

invited  subject 

to  land 

possession 

Februar

y‐2022 

February

‐2022* 

SUDA  put  up  proposal  to  Irrigation 

Department  

  Kamrej‐  Dhoran 

Pardi‐2 (12.5 mld) 

SUDA  

Tender  to  be 

invited  subject 

to  land 

possession 

Februar

y‐2022  

February

‐2022* 

Other parcel of  land  to be neemed  in  lieu 

of GAUCHAR land by GoG. Proposal is sent 

by  Collectorate  to  revenue  department, 

GoG on 14/10/2019  

  Kamrej‐ Kathor (16 mld) SUDA  

Tender  to  be 

invited  subject 

to  land 

possession 

Februar

y‐2022 

February

‐2022* 

Land  is  finalised,  Detail  engineering  is 

started but possession is yet to be received 

from DDO shri.  

  Kamrej‐ 

JatBharthana 

(5.22 mld) GWSSB  

DPR under 

approval  

February‐2022 

 

February‐2022 

Land acquisition proposal is with Revenue Department dtd.14/10/2019. Compliance asked from Collector Surat dated.24/12/20219 

  Kamrej‐ Ghala 

(1.4 mld)  GWSSB  

  Kamrej‐  Datva 

(0.34 mld) GWSSB  

February‐2022 

February‐2022 

Land acquisition proposal is with Revenue Department dtd.25/10/2019. Compliance asked from Collector Surat dated.24/12/20219  

  Kamrej‐  Sevni 

(5.18 mld) GWSSB 

December‐2022 

Decemb

er‐2022 

Land acquisition proposal is with Revenue Department dtd. 14/10/2019. Compliance asked from Collector Surat dated. 24/12/20219  

  Mandvi‐  Koliwad 

Rataniya  (0.41 

mld) GWSSB  

DPR  under 

preparation  

Decemb

er‐2022 

Decemb

er‐2022  

Land acquisition proposal is with Collector, Surat  

Page 58: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 15 of 17 

 

  Mandvi‐  Khanjroli 

(0.21 mld) GWSSB  

DPR under 

approval  

Decemb

er‐2022 

Decemb

er‐2022  

Land acquisition proposal is with Collector,Surat  

  Bardoli‐  Mori (0.15 mld) GWSSB  

Decemb

er‐2022 

Decemb

er‐2022  

Land acquisition proposal is with Collector, 

Surat Land is not Available as per 

requirement. So Land acquisition proposal 

is  sent to Mamlatdar for scrutiny as on 

dt.25/11/2019  

  Mandvi‐  Unn Kosadi  (0.29 mld) GWSSB  

DPR  under 

preparation  

 

December‐2022 

 

December‐2022 

 

Land acquisition proposal is with Collector, Surat  

  Mandvi‐  Patna 

Creek(0.35  mld) 

GWSSB  

DPR  under 

preparation 

December‐2022 

 

December‐2022 

 

Land acquisition proposal is with Collector, Surat  

  Mandvi‐  Tarsada 

(0.82 mld) GWSSB  

DPR  under 

approval  

 

December‐2022 

 

December‐2022 

 

Land acquisition proposal is with Collector, Surat  

  Bardoli  –  Kadod 

Creek  (3.5  mld) 

GWSSB  

DPR  under 

preparation  

 

December‐2022 

 

December‐2022 

 

Land acquisition proposal is with Collector, Surat  

  Bardoli‐ 

Bhamaiya  (0.17 

mld) GWSSB  

DPR  under 

approval  

 

December‐2022 

 

December‐2022 

 

Land acquisition proposal is with Collector, Surat  

  Bardoli‐ 

Vaghecha  (0.28 

mld) GWSSB  

December‐2022 

 

December‐2022 

 

Land acquisition proposal is with Collector, Surat  

  Kamrej‐  Timba 

(0.75 mld) GWSSB  

December‐2022 

 

December‐2022 

 

Land acquisition proposal is with Collector, Surat  

  Kamrej‐  Maachi 

(0.16 mld) GWSSB  

December‐2022 

 

December‐2022 

 

Land acquisition proposal is with Collector, Surat  

  Mandvi‐  Mandvi 

(25 mld) GWSSB  

DPR  under 

preparation  

Decemb

er‐2022 

Decemb

er‐2022  

Land available  

Page 59: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 16 of 17 

 

  Mandvi‐  Puna 

Gam  (0.36  mld) 

GWSSB  

Decemb

er‐2022 

Decemb

er‐2022  

Land acquisition proposal is with Collector, 

Surat  

Scrutiny  is necessary  for  Site  situation  for 

land allocation in favour of Panchayat  

  Mandvi‐ 

Kamlapore  Creek 

(1.9 mld) GWSSB  

Decemb

er‐2022 

Decemb

er‐2022  

Land acquisition proposal is with Collector, 

Surat 

  Mandvi‐  Vareli 

Kudashi  (2  mld) 

GWSSB  

Decemb

er‐2022 

Decemb

er‐2022  

Land acquisition proposal is with Collector, 

Surat 

  Mandvi‐  Bodhan 

Creek  (2.2  mld) 

GWSSB  

Decemb

er‐2022 

Decemb

er‐2022  

Land acquisition proposal is with Collector, 

Surat 

  Mandvi‐  Uskhed 

Khurd  (0.11  mld) 

GWSSB  

Decemb

er‐2022 

Decemb

er‐2022  

Common land for both STPs. Land acquisition proposal is with Collector, Surat 

  Mandvi‐ 

Gamtalav Bujrang 

(0.34 mld) GWSSB  

Decemb

er‐2022 

Decemb

er‐2022  

  Mandvi‐  Bodhan 

Village  (1.3  mld) 

GWSSB  

Decemb

er‐2022 

Decemb

er‐2022  

Proposal under preparation  

* Timeline given as per DPR sanctioned by NRCP. 

Note:‐  

A meeting   was held under  the  chairmanship of  The Chief  Secretary, Gujarat  for policy  level decisions  of  Pollution  Abatement  And  Conservation  Of  River  Tapi  At  85  Km  Stretch  From Kakarapar Barrage To ONGC Bridge, Surat Project at Chief Secretary’s office  dated 24/01/2020 in which following matters were brought forward: 

• Operation and Maintenance shall be done by GWSSB for a specific duration of 7 years and funds 

arrangement for the same shall be done by Panchayat Department  

•  After  completion  of  Project  as  Deposit  works,  project  has  to  be  handed  over  to  Gram 

Panchayat.   

• Non Core items like River Front Garden Development, Vermi‐Compost, River Quality Monitoring 

System etc. shall not be implemented by GWSSB in Rural Areas of Surat.SMC/SUDA shall decide 

implementation of the same.  

• Mandvi  STP  tender  is  included  in  SJMMSVY  and Administrative Approval  is  accorded  for  the 

same. The same is also included in above project.  

• Secretary (Water Supply) and Chairman, GWSSB informed the estimated project cost varies with 

respect to the original sanctioned cost by NRCD.  

Page 60: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverTapi)

Page 17 of 17 

 

• For 17 villages, DPR cost was RS 115 crore (without O&M). Now revised cost : Capital cost‐99.65 

Cr & 7 yr O&M cost ‐71.79 Cr . Total cost ‐ Rs 171 crore (with 7 year O&M)  

• Presently  only  sewage  interception  and  treatment  are  considered  for  villages  near  creek.  It 

won’t be technically feasible to collect sewage from open drains as storm water and other solid 

waste may also enter in creek.  

•  Each  creek  receives  sewage  from more  than  5  villages  so  26 more  villages will  have  to  be 

planned with complete UGD system and STP with 7 years O&M.  

• Thus  tentative  project  cost  for  additional  villages may  be  around Rs.146  crore  .Total  revised 

tentative project cost may be around Rs.320 crore 

Page 61: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAnas)

Page 1 of 8 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently  there  is no any proposal  for  in‐situ  remediation.    However,  as  per  the suggestion  given  by  Assessment  team during  meeting  held  on  04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached  by  UDD/GUDM/Concerned for technical support in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  I. 13.70  MLD  of  STP  of  Dahod Nagarpalika – Apr ‐2020 

II. 4.60  MLD  of  STP  of  Zalod Nagarpalika – Oct‐2020 

  2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020 Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the  progress  & 

minutes  of  the  same  (having  progress 

status) is regularly submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently under chairmanship of Hon’ble CS  (Last  meeting  was  conducted  on 24/12/2019)  in  matter  of  O.A.    No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources including  drains  contributing  to  river pollution  is  already  completed  and submitted in the PRS action plan.  In‐situ treatment:‐ Pl. refer point no:‐1    

Page 62: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAnas)

Page 2 of 8 

 

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure: ‐‐‐ Gap analysis: 12 MLD Proposed : 18.3 MLD  Completion Timeline : April‐Oct, 2020 Proposed STPs and present status:‐  

I. 13.70  MLD  of  STP  (Dahod Nagarpalika):‐  60%  completed.  Expected  to  be completed in April ‐2020 

II. 4.60  MLD  of  STP  (Zalod Nagarpalika):‐ 30%  completed.  Expected  to  be completed in Oct ‐2020 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  No Industrial effluent discharge in the identified stretch of River Anas 

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  5 (iv) Status is attached as Annexure – I  

 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – II 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There are total 364 # of HCUs (Health Care Units)  located  in  the  Dahod  and  Zalod Taluka:‐    Bio‐medical  waste  of  HCUs  in Dahod  and  Zalod  Taluka  is  disposed  at Common Bio‐medical waste management facility  namely  Samvedana  Biomedical waste  Incinerator  facility, Plot No. 217/1, Chandrapura  Industrial  Estate, Halol Dist. Panchmahals. Industrial Waste:‐ In  the  State,  all  hazardous  waste generating  units  are  consented  with  the authorization  under  Haz.  Waste 

Page 63: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAnas)

Page 3 of 8 

 

Management  Rules,  amended  time  to time &  they  are  disposing  their waste  to TSDF/CHWIF/registered  recycler  under Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the recently  framed  draft  bill  titled “Conservation, Protection, Regulation and Management of Ground Water  in Gujarat State”  in the meeting held on 04/02/2020 at  GPCB  with  PRS  Assessment  Team nominated by Ministry of Jal Shakti which is  in  process  and within  3 months  to  be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5  (viii),  (ix),  (x),  (xi) given  by  Irrigation  Dept.  as  on  date  is attached as Annexure – III (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details  w.r.t  point  no.  5  (xii)  given  by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed during the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of  Jal Shakti about  proposal  sent  by  them  to  CAMPA for  funding of  around Rs. 5  crore  for  the development  of  Biodiversity  Park.  Team suggested  tying  up  with  AMC  as  they already  have  some  plan  to  develop Biodiversity park at Khari under NRCP.  

 

 

 

 

 

 

Page 64: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAnas)

Page 4 of 8 

 

Annexure‐ I 

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:  

Types of Waste/ 

Characteristic of 

waste 

Generated 

Quantity/ 

Day 

(MT/Day) 

Collection/ 

Storage facility 

with capacity 

Disposal/ 

Treatment 

facility with 

capacity along 

with location 

Total Gap with 

generation & 

existing treatment

facilities if any 

Proposed action plan /

facility to cover gap 

Time 

limit 

Remarks 

Municipal Solid 

Waste (Dahod) 

50  

 

Collection  

System and 

Dumping site  

provided 

‐‐  At present there is 

no solid waste 

treatment facility.

50  MT/Day 

 

MSW Processing Facility 

of 60 MT/day capacity is 

proposed at S.No. 

315/P, Vill. Pushari 

Project Cost of Rs. 52.76 

Crore with Capex and 

Opex for five years. 

Feb 2020 

(as submitted 

by 

Municipality)

Proposed project of 

Solid Waste 

processing is at 

Tender Process 

Stage. 

MRF   & Processing 

facility made 

operational  at 

Dahod  Nagarpalika 

Municipal Solid 

Waste (Zhalod) 

10  

 

Collection system 

and Dumping Site 

provided.  

‐‐  At present there is 

no solid waste 

treatment facility.

10  MT/Day 

 

 

MSW Processing Facility 

of 1000 kg/hr (about 20 

MT/day) is proposed 

with Project cost of Rs. 

1.91 Crores at S.No. 

784/1.  At 

Vill.Kakradungra,  

 

August 2020

(as submitted 

by 

Municipality)

Proposed project of 

Solid Waste 

processing is at DPR 

Stage. 

MRF facility made 

operational at Jhalod 

Nagarpalika 

Total  60   ‐‐  ‐‐    80 MT/day  ‐‐  ‐‐ 

Page 65: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAnas)

Page 5 of 8 

 

Annexure‐II 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  Progress/Status Report of the River/PRS water quality Monitoring (Feb – 2020): 

Sampling Point  Type BOD  COD DO  FCO pH  TCO  TDS 

 RIVER ANAS AT LIMADI (ZALOD) ‐ KUSHALGADH ROAD, VILL. CHAKALIYA, DIST. DAHOD. 

ROU  0.65  4  6.8  12  8.3  50  294 

 

Progress /Status Report for Ground water quality monitoring pertaining to PRS River (Feb – 2020): 

Sampling Point  Type  BOD  COD DO  FCO pH  TCO  TDS 

HAND PUMP OPP. M/S STAR REDIATOR, CHAKALIYA ROAD, GIDC, DAHOD, DIST. DAHOD 

ROU  0.52  4  2.2  <2  7.9  <2  882 

WELL AT HINDU DHARAMASHALA, STATION ROAD, DAHOD 

ROU  0.55  4  1.3  <2  8.5  <2  484 

 

Drain details with flow: 

Sr.No.  Location  Name of 

Inletting 

River/Drain 

Discharge (MLD) 

Max.  Min. 

1  Mandavav Bridge, 

Mandavav ‐ 

Dhamarada Road, 

Dahod. 

River Khan  ‐‐  ‐‐ 

2  Kharasana Bridge, 

Zalod – 

Thunthikankachiya 

Road, Dist. Dahod. 

(Zalod) 

River 

Machhananala

‐‐  ‐‐ 

 

 

 

Page 66: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAnas)

Page 6 of 8 

 

Annexure‐III 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

 

Sr.No  River name  Details/Status 

1  Anas  Data/details will be furnished soon 

 

Annexure‐IV 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

Stretch/river  Existing plantation/vegetation 

cover details 

Proposed plan to cover 

remaining gap along river 

/river stretch 

Time 

limit 

Remarks 

Anas  

Existing vegetation covered by 

Propopis juliflora & caparis 

aphylla, other shrubs.  

Target submitted by APCCF for all the Rivers of 

Gujarat is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

Page 67: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAnas)

Page 7 of 8 

 

Annexure‐A 

 

Page 68: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverAnas)

Page 8 of 8 

 

 

Page 69: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverBaleshwarKhadi)

Page 1 of 8 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently  there  is  no  any  proposal  for  in‐situ remediation.    However,  as  per  the  suggestion given by Assessment  team during meeting held on  04/02/2020,  NEERI,  UP  Govt.,  Punjab  Gov. etc  may  be  approached  by UDD/GUDM/Concerned  for  technical support  in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  PRH & RDD was  informed  to  submit  the action plan for the sewage generated from the villages (Baleshwar, Samrod & nearby) (9 MLD) 

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021  PRH & RDD was  informed to submit the action  plan  for  the  sewage  generated from  the villages  (Baleshwar, Samrod & nearby) 

Up gradation of GETPL‐2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020     22.01.2020 Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the progress & minutes 

of the same (having progress status)  is regularly 

submitted to CPCB 

Reviews of all NGT matters are taken frequently under chairmanship of Hon’ble CS (Last meeting was conducted on 24/12/2019) in matter of O.A.  No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources  including drains  contributing  to  river  pollution  is  already completed and submitted in the PRS action plan. In‐situ treatment:‐ Pl. refer point no:‐1    

Page 70: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverBaleshwarKhadi)

Page 2 of 8 

 

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure: ‐‐‐ Gap analysis: 9 MLD Proposed : ‐‐‐  Completion Timeline : ‐‐‐ PRH & RDD was  informed  to  submit  the action plan for the sewage generated from the villages (Baleshwar, Samrod & nearby‐9 MLD) 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  No. of industries: ‐ Industrial Estate Gujarat Eco Textile  Park  and  Industries  located  near Palsana  village  with  total  80  Nos.  of industries.  All  the  industries  are  CETP  members  having primary ETP facility.  Existing CETPs:‐  There are two CETPs namely‐ Gujarat Eco Textile Park  Ltd  (GETPL),  Palsana  and  New  Palsana Industrial  Co‐op  Society  Ltd,  Palsana  having GPCB  permission  for  final  discharge  of  treated effluent Surat 105 MLD   

Proposed CETP Modification/Upgradation:‐  Gujarat Eco Textile Park Ltd,‐GETPL, Palsana (60 

MLD)  ‐  has  obtained  CTE  Amendment  for zero  liquid  discharge  as  the  treated  water shall be recycled to member units. They will propose  new  installation  of  Sedimentation tank,  casket  cooling  system,  Disk  flotation, ultrafiltration and RO plant  for upgradation and  recycle  of  treated  waste  water  to member units.  Present Status‐  Land  levelling &  Compound wall  / Gabion wall under  Progress.  Expected  to  be    completed  by 2021 

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  Letter  has  been  issued  to  Panchayat,  Rural Housing  &  Rural  Development  Department  by GPCB,  Head  office‐Gandhinagar  to  submit  the action plan of solid waste management  

Page 71: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverBaleshwarKhadi)

Page 3 of 8 

 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – I 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There are total 45 # of HCUs (Health Care Units), treatment &  disposal  of  Bio Medical Waste  of which  is  being  taken  care  of  by  a  common facility M/s, Globe Bio Care located in Surat Industrial Waste:‐ 

In  the  State,  all  hazardous  waste  generating units  are  consented  with  the  authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered  recycler  under  Rule‐9/Co‐processing  and  as  per  consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the  recently framed  draft  bill  titled  “Conservation, Protection,  Regulation  and  Management  of Ground Water  in Gujarat State”  in  the meeting held  on  04/02/2020  at  GPCB  with  PRS Assessment Team nominated by Ministry of  Jal Shakti which  is  in process and within 3 months to be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date is attached as Annexure – II (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed  during  the  meeting  held  on 04/02/2020 at GPCB with PRS Assessment Team nominated  by  Ministry  of  Jal  Shakti  about proposal sent by them to CAMPA for funding of around  Rs.  5  crore  for  the  development  of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.  

 

Page 72: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverBaleshwarKhadi)

Page 4 of 8 

 

Annexure‐I 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river Progress/Status Report of the River/PRS water quality Monitoring (Feb ‐2020): 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

06‐02‐2020  Baleshwar Khadi  7.12  7.99  0.72  16  11  53 

Progress/Status Report of the River/PRS ground water quality Monitoring : 

Location:‐ BOREWELL AT LUCKY FILLING STATION PALASANA 

Date  ALK  BOD  BOR  CHL  CND  COD   COL   DOX  FCO   MAG  NH3  NIT  NTR  pH  PHO  POT  SOD  SS  SUP  T.H  TCO  TDS  TKN  TMP 

03/10/2019  180  0.99  0.04  122  1394  11  5  3.42  9  36.48  0.56  0.059  0.095  7.45  0.015  2.22  97.59  4  23  250  63  832  3.08  28 

Location:‐ BOREWELL AT PRIMARY HEALTH CENTER(PHC) 

Date  ALK  BOD  BOR  CHL  CND  COD   COL   DOX  FCO   FLU  MAG  NH3  NIT  NTR  pH  PHO  POT  SOD  SS  SUP  T.H  TCO  TDS  TKN 

03/10/2019  610  0.92  0.04  283  2119  10  5  3.64  6  0.15  38.91  0.28  0.036  0.13  7.75  0.014  2.05  134.69  8  42  340  21  1268  2.24 

 

Drain details with flow: 

Sr.No.   Name of Drain/Location Discharged

Max Min

1  Bagumara‐Gangadhara 0.3 MLD 0.1 MLD

2  Baleshwar‐Samrod 114 MLD 50 MLD

Page 73: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverBaleshwarKhadi)

Page 5 of 8 

 

Annexure‐II 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

Sr.No  River name  Details/Status 

1  Baleshwar Khadi  Details mentioned as below 

 

 

 

 

 

 

 

 

Page 74: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverBaleshwarKhadi)

Page 6 of 8 

 

Annexure‐III 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

The details received from  Social Forestry wing, Aranya Bhavan, Gandhinagar are as under 

Stretch/river  Existing 

plantation/vegetation cover 

details 

Proposed plan to 

cover remaining 

gap along river 

/river stretch 

Time limit  Remarks 

Baleshwar Kahdi 

(Pandesara to  

kapletha) 

1430 trees Target submitted by APCCF for all the Rivers of Gujarat 

is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 75: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverBaleshwarKhadi)

Page 7 of 8 

 

Annexure‐A 

 

Page 76: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverBaleshwarKhadi)

Page 8 of 8 

 

 

Page 77: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 1 of 9 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently  there  is no any proposal  for  in‐situ  remediation.    However,  as  per  the suggestion  given  by  Assessment  team during  meeting  held  on  04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached  by  UDD/GUDM/Concerned for technical support in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  PRH &  RDD was  informed  to  submit  the action plan for the sewage generated from the villages Sahol & Kim having discharge 10 MLD  2  Timeline for completing all steps of 

action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020 Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the  progress  & 

minutes  of  the  same  (having  progress 

status) is regularly submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently under chairmanship of Hon’ble CS  (Last  meeting  was  conducted  on 24/12/2019)  in  matter  of  O.A.    No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources including  drains  contributing  to  river pollution  is  already  completed  and submitted in the PRS action plan.  In‐situ treatment:‐ Pl. refer point no:‐1    

Page 78: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 2 of 9 

 

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure: ‐‐ Gap analysis: 10 MLD Proposed : ‐‐  Completion Timeline : ‐‐ PRH &  RDD was  informed  to  submit  the action plan for the sewage generated from the villages (Sahol & Kim‐10 MLD) 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  No Industrial wastewater discharge into this river stretch  

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  Letter is issued from ACS, F & ED, GoG to PRH & RDD, GoG for proper discharge & disposal  of  sewage  /solid  waste  &  its management.   

 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – I 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There are total 30 # of HCUs (Health Care Units),  treatment  &  disposal  of  Bio Medical  Waste  of  which  is  being  taken care  of  by  a  common  facility M/s, Globe Bio Care located in Surat Industrial Waste:‐ 

In  the  State,  all  hazardous  waste generating  units  are  consented  with  the authorization  under  Haz.  Waste Management  Rules,  amended  time  to time &  they  are  disposing  their waste  to TSDF/CHWIF/registered  recycler  under Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the recently  framed  draft  bill  titled “Conservation, Protection, Regulation and Management of Ground Water  in Gujarat State”  in the meeting held on 04/02/2020 

Page 79: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 3 of 9 

 

at  GPCB  with  PRS  Assessment  Team nominated by Ministry of Jal Shakti which is  in  process  and within  3 months  to  be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date is attached as Annexure – II (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed during the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of  Jal Shakti about  proposal  sent  by  them  to  CAMPA for  funding of  around Rs. 5  crore  for  the development  of  Biodiversity  Park.  Team suggested  tying  up  with  AMC  as  they already  have  some  plan  to  develop Biodiversity park at Khari under NRCP.  

 

 

 

 

 

 

Page 80: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 4 of 9 

 

 

Annexure‐I 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  Progress/Status Report of the River/PRS water quality Monitoring (Feb ‐2020): 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

03‐02‐2020  Sahol Bridge  7.07  7.41  1.09  11  9  63 

 

Progress/Status Report of the River/PRS ground water quality Monitoring: 

Location:‐ BOREWELL AT GARG TEX‐O FEB PVT.LTD OLPAD 

Date  %NA  ALK  BOD  CAL   COD   COL   DOX  FLU  MAG  NH3  NIT  NTR  pH  PHO  POT  SOD  SS  SUP  T.H  TCO  TDS  TKN  TMP  TUR 

     01/10/2019  44.29  470  0.86  108.2  10  5  3.22  0.12  36.48  0.56  0.031  0.16  7.29  0.019  2.3  154.7  12  61  420  53  6746  3.92  28  2 

 

Location:‐ BOREWELL AT PIRAMAL GLASS 

Date  ALK  BOD  BOR  CHL  CND  COL   DOX  FCO   FLU  MAG  NH3  NIT  NTR  pH  PHO  POT  SOD  SS  SUP  T.H  TCO  TDS  TKN  TMP  TUR 

     01/10/2019  430  0.86  0.04  290  3840  5  4.21  9  0.15  58.37  0.28  0.2  0.15  7.24  0.016  2.23  160.7  4  55  420  33  2228  3.64  28  2 

 

Location:‐ BOREWELL AT NEELAM FIBER KIM IND AREA PLOT‐202 

Date  ALK  BOD  BOR  CHL  CND  COL   DOX  FCO   FLU  MAG  NH3  NIT  NTR  pH  PHO  POT  SOD  SS  SUP  T.H  TCO  TDS  TKN  TMP  TUR 

     01/10/2019  490  1.02  0.04  280  3403  5  3.76  6  26.75  0.56  0.03  0.13  7.79  0.015  2.05  111.64  4  40  300  41  2012  3.36  28  2 

 

Page 81: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 5 of 9 

 

Drain details with flow: 

Sr.No.   Location/ 

Name of Drain 

Name  of  Inletting 

River/Drain 

Discharge 

Max  Min 

1  Kim to Sahol  Village Kim drain  10 MLD  2 MLD 

Page 82: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 6 of 9 

 

Annexure‐II 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

 

Sr.No  River name  Details/Status 

1  Kim  Details mentioned as below 

 

 

 

 

 

 

 

Page 83: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 7 of 9 

 

Annexure‐III 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

The details received from  Social Forestry wing, Aranya Bhavan, Gandhinagar are as under 

Stretch/river   Existing 

plantation/vegetation cover 

details  

Proposed plan to 

cover remaining gap 

along river/river 

stretch  

Time limit  Remarks 

Kim  (Sahol  Bridge  to 

Hansol)  370 trees 

Target submitted by APCCF for all the Rivers of Gujarat is as 

per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 84: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 8 of 9 

 

Annexure‐A 

 

Page 85: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverKim)

Page 9 of 9 

 

 

Page 86: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMeshwo)

Page 1 of 7 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  There  is no  sewage discharge    in Meshvo river  in    the  stretch  of  Meshvo  at Shamalaji 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  No STP  is  required as  there  is no  sewage discharge  in  the  stretch  of  Meshvo  at Shamalaji. 

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020 Fortnightly commencing 21.12.2019 

Regular  monitoring  is  carried  out  & 

samples are collected periodically. 

 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted and Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     There  are  no  polluting  sources  in  the stretch  of  Meshvo  at  Shamalaji.  The polluted  stretch  is  required  to be deleted from  the  list of polluted river stretches  in the state    

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  No  sewage  is  discharged    in  to  polluted river stretch 

Page 87: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMeshwo)

Page 2 of 7 

 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  There is no Industrial wastewater discharge into this river stretch  

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  NA 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – I 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There are total 970 # of HCUs (Health Care 

Units)  located  in  the  Himmatnagar, 

treatment  &  disposal  of  Bio  Medical 

Waste of which is being taken care of by a 

common  facility Ecoli waste management 

pvt.  Ltd  (unit‐2)  located  at  Plot  no‐

98,99,100  Sabar  industrial  park,  opp. 

Asopalav  Hotel,  Himmatnagar‐  Shamlaji 

road, Asal, Ta. Bhiloda, Dist. Aravalli. 

Industrial Waste:‐ 

In  the  State,  all  hazardous  waste generating  units  are  consented  with  the authorization  under  Haz.  Waste Management  Rules,  amended  time  to time &  they  are  disposing  their waste  to TSDF/CHWIF/registered  recycler  under Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the recently  framed  draft  bill  titled “Conservation, Protection, Regulation and Management of Ground Water  in Gujarat State”  in the meeting held on 04/02/2020 at  GPCB  with  PRS  Assessment  Team nominated by Ministry of Jal Shakti which 

Page 88: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMeshwo)

Page 3 of 7 

 

is  in  process  and within  3 months  to  be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date is attached as Annexure – II (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed during the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of  Jal Shakti about  proposal  sent  by  them  to  CAMPA for  funding of  around Rs. 5  crore  for  the development  of  Biodiversity  Park.  Team suggested  tying  up  with  AMC  as  they already  have  some  plan  to  develop Biodiversity park at Khari under NRCP. 

 

 

 

 

 

 

 

Page 89: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMeshwo)

Page 4 of 7 

 

 

Annexure‐ I 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  Progress/Status Report of the River/PRS water quality Monitoring: 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

Feb‐20  River Meshvo  

D/s at Shamlaji 7.89  7.18  1.09  10  9.1  58 

 

Progress/Status Report of the ground water quality Monitoring: 

Date  Location  pH  BOD (mg/l)  COD (mg/l)  TDS (mg/l) 

Feb‐20  Borewell from Shamlaji 

Dharamshala 7.20  0.59  6  1060 

 

Annexure‐II 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date 

Sr.No  River name  Details/Status 

1  Meshwo  Data/details will be furnished soon 

Page 90: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMeshwo)

Page 5 of 7 

 

Annexure‐III 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

Stretch/river Existingplantation/vegetationcoverdetails

Proposedplantocoverremaininggapalongriver/riverstretch

Timelimit Remarks

Meshvo  

River bank of  

River Shamlaji  

Sparse Natural Vegetation of 

Propopis juliflora &  other 

shrubs  and climbers  

Target  submitted  by  APCCF  for  all  the  Rivers  of Gujarat is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 91: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMeshwo)

Page 6 of 7 

 

Annexure‐A 

 

Page 92: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMeshwo)

Page 7 of 7 

 

 

Page 93: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 1 of 9 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently  there  is no any proposal  for  in‐situ  remediation.    However,  as  per  the suggestion  given  by  Assessment  team during  meeting  held  on  04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached  by  UDD/GUDM/Concerned for technical support in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  STP  of  4  MLD  (2+2  MLD)  proposed  by Sachin Notified Area Authority –2020  

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020      22.01.2020 Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the  progress  & 

minutes  of  the  same  (having  progress 

status) is regularly submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently under chairmanship of Hon’ble CS  (Last  meeting  was  conducted  on 24/12/2019)  in  matter  of  O.A.    No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & to be Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources including  drains  contributing  to  river pollution  is  already  completed  and submitted in the PRS action plan.  In‐situ treatment:‐ Pl. refer point no:‐1    

Page 94: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 2 of 9 

 

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  Existing infrastructure: ‐‐ Gap analysis: 1.6 MLD Proposed : 04 MLD  Completion Timeline : 2020 Proposed STP:‐  STP of 4    (2+2) MLD capacity  is proposed by  Sachin Notified Area Authority. DTR  is ready. Allotment of land is under approval in GIDC.  

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  No Industrial wastewater discharge into this river stretch  

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  5 (iv) Status is attached as Annexure – I 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – II 

(vi)        Preventing  dumping  of waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There are total 30 # of HCUs (Health Care Units),  treatment  &  disposal  of  Bio Medical  Waste  of  which  is  being  taken care  of  by  a  common  facility M/s, Globe Bio Care located in Surat Industrial Waste:‐ 

In  the  State, Hazardous waste  generating units are consented with the authorization under  Haz.  Waste  Management  Rules, amended  time  to  time  &  they  are disposing  their  waste  to TSDF/CHWIF/registered  recycler  under Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the recently  framed  draft  bill  titled “Conservation, Protection, Regulation and 

Page 95: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 3 of 9 

 

Management of Ground Water  in Gujarat State”  in the meeting held on 04/02/2020 at  GPCB  with  PRS  Assessment  Team nominated by Ministry of Jal Shakti which is  in  process  and within  3 months  to  be submitted to the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date is attached as Annexure – III (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB  informed during the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of  Jal Shakti about  proposal  sent  by  them  to  CAMPA for  funding of  around Rs. 5  crore  for  the development  of  Biodiversity  Park.  Team suggested  tying  up  with  AMC  as  they already  have  some  plan  to  develop Biodiversity park at Khari under NRCP.  

 

 

 

 

 

 

 

Page 96: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 4 of 9 

 

Annexure‐I 

5 (iv ) Status of Solid Waste Management & Details of Processing Facilities 

 Type of waste/ 

Characteristic 

of waste  

Generated 

quantity/ 

day  

Collection/ 

Storage facility with 

capacity  

Disposal/Treatment 

facility with capacity 

along with location  

Total Gap 

with 

generation 

&existing 

treatment 

facilities if 

any  

Proposed 

action 

plan/facility 

to cover gap  

Time 

limit  

Present Status 

Solid waste  10    Authorized 

Agencies/end 

users/recyclers 

10  DPR is under 

processes 

Year 

2020 

Sachin  Notified Area  Authority has  requested for  land allotment required  for municipal  solid waste  disposal site development  in their  Head Office.  After receiving necessary approval  they will proceed  for further development. 

Total  10      10       

 

Page 97: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 5 of 9 

 

Annexure‐II 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  Progress/Status Report of the River/PRS water quality Monitoring: 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

06‐02‐2020  River Mindhola  5.79  7.13  8  118  11  83 

 

Progress/Status Report of the River/PRS ground water quality Monitoring: 

Location: ‐ BOREWELL AT SACHIN GIDC (SIEL) 

Date  %NA  ALK  BOD  CAL   CHL  CND  COD   COL   DOX   FDS  FLU   MAG  NAA  NH3  NTR  pH  PHO  POT  SOD  SS  SUP  T.H  TCO  TDS  TKN  TMP  TUR 

04/10/19  43.2  350  1.18  268.5  272  8331  14  5  3.27  571  0.22  167.8  5.6  0.84  0.12  7.65  0.02  5  478.5  4  35  1360  47  1952  3.64  28  3 

Location: ‐ BOREWELL AT NR COMMON HAZ WASTE DSPO.SITE(GEPIL) 

Date  %NA  ALK  BOD  CAL   CHL  CND  COD   COL   DOX   FDS  FLU   MAG  NH3  NTR  pH  PHO  POT  SOD  SS  SUP  T.H  TCO  TDS  TKN  TMP  TUR 

04/10/19  48.64  310  0.92  268.54  280  3522  19  5  3.31  691  0.3  92.42  0.84  0.07  7.62  0.021  5.01  460.22  4  40  1050  53  2012  2.52  28  2 

Location : ‐ OPEN WELL AT GABHENI OPP: PANCHYAT OFFICE 

Date  %NA  ALK  BOD  CAL   CHL  CND  COD   COL   DOX   FDS  FLU   MAG  NH3  NTR  pH  PHO  POT  SOD  SS  SUP  T.H  TCO  TDS  TKN  TMP  TUR 

04/10/19  47.8  240  0.74  44.09  126  1644  10  5  6.59  316  0.12  17.02  0.56  0.084  7.76  0.013  2.12  76.95  4  41  180  41  928  1.96  28  3 

 

Page 98: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 6 of 9 

 

Drain details with flow: 

Sr.No.   Location   Name of Inletting River/Drain  Discharged    

Max  Min 

1  Sachin Notified area  Kapletha village drain meeting River Mindhola 

     1.6 MLD        0.5 MLD 

Note:‐ Entire Baleshwar Khadi is meeting to River Mindhola at village Samrod as major drain. Polluted River action plan of Baleshwar Khadi is prepared and submitted separately. 

 Annexure‐III 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

Sr.No  River name  Details/Status 

1  Mindhola  Details mentioned as below 

 

Page 99: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 7 of 9 

 

Annexure‐IV 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

The details received from  Social Forestry wing, Aranya Bhavan, Gandhinagar are as under 

Stretch/river   Existing 

plantation/vegetation 

cover details  

Proposed plan to cover 

remaining gap along 

river/river stretch  

Time limit   Remarks  

Mindhola  

(Along  

sachin) 

1250 trees 

Target submitted by APCCF for all the Rivers of Gujarat is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 100: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 8 of 9 

 

Annexure‐A 

 

Page 101: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverMindhola)

Page 9 of 9 

 

 

Page 102: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverNarmada)

Page 1 of 7 

 

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb‐20 

(Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) 

Sl.No.  Activity to be monitored  Timeline   Submission of Progress by States/UT‐Compliance Status 

1  Ensure 100% treatment  of sewage at least in‐situ remediation 

31.03.2020  Presently there  is no any proposal for  in‐situ  remediation.    However,  as  per  the suggestion  given  by  Assessment  team during  meeting  held  on  04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached  by  UDD/GUDM/Concerned for technical support in the matter 

  Commencement of setting up of STPS and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 

31.03.2020  There  is  no  discharge  of  domestic wastewater  from  any  Municipal Corporation  (city)  or  Municipality (town) in this river stretch. 

2  Timeline for completing all steps of action plans including completion of setting up of STPs and their commissioning 

31.03.2021 

3  Chief Secretaries may set up appropriate monitoring mechanism at State level 

Specifying accountability of nodal authorities not below the Secretary Level 

Chief Secretaries may have an accountable person attached in their office for this purpose. 

Monitoring at State level must take place 

22.01.2020     22.01.2020  Fortnightly commencing 21.12.2019 

Quarterly  RRC  meeting  held  at  GPCB, 

Gandhinagar  to  review  the  progress  & 

minutes  of  the  same  (having  progress 

status) is regularly submitted to CPCB 

Reviews  of  all  NGT  matters  are  taken frequently  under  chairmanship  of Hon’ble CS  (Last meeting was conducted on  24/12/2019)  in matter  of O.A.   No.:‐ 606/2018 

4  Progress report may be furnished by the States/UTs to 

Secretary, Ministry of Jal Shakti 

Member Secretary, CPCB 

Monthly (preferably before 20th of every month) 

Noted & Complied  

5  Progress Report may be comprised of details along with completion timelines on: 

(i)        Identification  of  polluting sources  including  drains contributing  to  river pollution  and  action  as  per NGT  order  on  insitu treatment 

     Identification  of  polluting  sources including  drains  contributing  to  river pollution  is  already  completed  and submitted in the PRS action plan.  In‐situ treatment:‐ Pl. refer point no:‐1    

Page 103: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverNarmada)

Page 2 of 7 

 

(ii)      Status of STPs, I&D and sewerage networks Details  of  existing infrastructure,  gap  analysis, proposed  along  with completion timeline 

  There  is  no  discharge  of  domestic wastewater  from  any  Municipal Corporation  (city) or Municipality  (town) in this river stretch. 

(iii)        Status of CETPs Details of existing CETP and ETP  infrastructure,  gap analysis,  proposed  along with  completion  timeline, no.  of  industries  and complying status 

  No Industrial wastewater discharge into this river stretch  

(iv)         Status of Solid Waste Management & Details of Processing Facilities Details  of  existing infrastructure,  gap  analysis,  proposed  along  with completion timeline 

  5 (iv) Status is attached as Annexure – I 

(v)        Latest  water  quality  of polluted river, its tributaries, drains with  flow details and ground water quality  in  the catchment of polluted river 

  5 (v) Status is attached as Annexure – II As per the CPCB report (Sep‐18) based on 

results  of  2016  &  2017,  Narmada  not 

been fall in any priority with <3 mg/L BOD 

and  information  for  the  same  is  already 

submitted to CPCB. (vi)        Preventing  dumping  of 

waste  and  scientific  waste management  including  bio‐medical  wastes,  plastic wastes  and  decentralizing waste  processing,  including waste  generated  from hotels, ashrams etc. 

  Bio‐Medical Waste:‐  There are total 61 # of HCUs (Health Care Units)  located  in  the Ankleshwar  taluka, treatment  &  disposal  of  Bio  Medical Waste of which  is being taken care of by a  common  facility M/s,  Globe  Bio  Care located in GIDC Ankleshwar Industrial Waste:‐ 

In  the  State,  all  Hazardous  waste generating units  are  consented with  the authorization  under  Haz.  Waste Management  Rules,  amended  time  to time &  they are disposing  their waste  to TSDF/CHWIF/registered  recycler  under Rule‐9/Co‐processing  and  as  per consented conditions 

(vii)        Ground water regulation    GWRDC  has  given  details  about  the recently  framed  draft  bill  titled “Conservation,  Protection,  Regulation and  Management  of  Ground  Water  in 

Page 104: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverNarmada)

Page 3 of 7 

 

Gujarat  State”  in  the  meeting  held  on 04/02/2020  at  GPCB  with  PRS Assessment Team nominated by Ministry of  Jal  Shakti  which  is  in  process  and within 3 months  to be  submitted  to  the Assembly 

(viii) Adopting  good  irrigation practices 

  Details w.r.t point no. 5 (viii), (ix), (x), (xi) given  by  Irrigation  Dept.  as  on  date  is attached as Annexure – III (ix)         Protection  and 

management  of  Flood  Plain Zones (FPZ) 

 

(x)        Rain water harvesting   

(xi)        Maintaining  minimum environmental flow of river 

 

(xii)        Plantation  on  both  sides  of the river 

  Details  w.r.t  point  no.  5  (xii)  given  by Forest  Dept.  /PCCF/ACCF/Concerned  as on date is attached as Annexure – IV 

(xiii)       Setting up biodiversity parks   on  flood  plains  by  removing encroachment 

  GBB informed during the meeting held on 04/02/2020  at  GPCB  with  PRS Assessment Team nominated by Ministry of Jal Shakti about proposal sent by them to  CAMPA  for  funding  of  around  Rs.  5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as  they  already  have  some  plan  to develop Biodiversity park  at Khari under NRCP.  

 

 

 

 

 

 

 

Page 105: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverNarmada)

Page 4 of 7 

 

Annexure‐ I 

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:  

Types of 

Waste/ 

Characteristic 

of waste 

Generated 

Quantity/day 

Collection/

Storage facility 

with capacity 

Disposal/ Treatment 

facility with capacity 

along with location 

Total Gap with 

generation & 

existing treatment 

facilities if any 

Proposed action plan 

/facility to cover gap 

Present Status

MSW waste  95 MT/d  No proper 

collection & 

storage  

Disposed off at village 

Mandva‐bhuzarg site on 

open land without fencing 

or any other measures. 

95 MT/d  The Nagarpalika has 

proposed facility for waste 

to energy. This project is 

proposed at plot no. DP 97 

& DP 98/1, Saykha GIDC, 

Vill: Saykha, Tal: Vagra, 

Dist: Bharuch 

Physical progress is so far not started 

 

 

Annexure‐II 

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river  Progress/Status Report of the River/PRS water quality Monitoring: 

Date  Location  DO (mg/l)  pH  BOD (mg/l)  COD (mg/l)  Fecal Coliform 

(MPN/100 ml) 

Total coliform 

(MPN/100 ml) 

Feb‐20  NTPC Zanor  7.66  7.92  0.78  7  26  68 

Zadeshwar  7.58  8.15  0.81  8  140  320 

Garudeshwar  7.03  8.18  0.61  7  22  49 

Page 106: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverNarmada)

Page 5 of 7 

 

Annexure‐III 

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date  

Sr.No  River name  Details/Status 

1  Narmada  Data/details will be furnished soon 

 

Annexure‐IV 

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date 

Stretch/river  Existing 

plantation/vegetation 

cover details  

Proposed plan to 

cover remaining gap 

along river /river 

stretch  

Time 

limit 

Remarks 

Narmada River South side  

(Asha to mulad village) 

56.44 Km  

12500 trees 

Target  submitted  by  APCCF  for  all  the  Rivers  of Gujarat is as per attached details in Annexure‐A 

 

 

 

 

 

 

 

 

 

 

 

Page 107: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverNarmada)

Page 6 of 7 

 

Annexure‐A 

 

Page 108: (PRS of River Amravati)...(PRS of River Amravati) Page 1 of 8 National Mission for Clean Ganga Monthly Progress Report of Gujarat State for Feb ‐20 (Hon’ble NGT in the matter of

(PRSofRiverNarmada)

Page 7 of 7