  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    1/13

    SRCPD 1September 2010

    Use this area for cover image

    (Maximum height 6.5cm & width 8cm)

    Permit to Work LEANInitiatives

    September 2010

    Lee Boon Sin

    Cham Chi Shyung

    Lim Ee Hock

    Chua Eu Chieh

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    2/13

    Permit to Work flow Overview

    2

    ApplicationAuthorizatio

    n

    Fire

    permit

    Permit

    Issuance

    Job

    ExecutionClosur

    e

    Cold Work

    Low hazardous job Clearance only

    Hot

    work

    Area of focus for

    this time

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    3/13

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    4/13

    SRCPD 4September 2010

    1. Permits Authorization

    Applicants will submit all planned work permits at least one weekahead (D-7 days). To place them in dedicated slots from Monday to

    Friday, depending on which day they intend to start work.

    Applicants will level-out- the work load of long-lead time jobs (ie.

    Job to be executed longer than d + 7 days)E&SB work permits take priority with dedicated slot.

    No other changes to process; ie. AGSI to sign off work permits daily

    and ensure JHA is also sign/check by Operation

    After proper Authorization is completed, ASC to put the permits in the

    relevant slots

    Approved Permits

    Rejected permits

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    5/13

    SRCPD 5September 2010

    Permits Authorization

    Issue of Acting positions

    Acting SC to cross sign on the other complexes

    Permit applicants to discuss work scope with Plant Managers (FHI

    authorization if require)

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    6/13

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    7/13

    SRCPD 7September 2010

    2. Operation Preparation (D 1)

    Applicant to submit permits for next days job to Plant Managers

    before 1600hrs daily.

    No change to process: Plant Managers will continue providing

    Shift Instructions to shift team to prepare for next day work

    execution (e.g. switching pumps & isolation)

    After approval by Plant Manager, permit will be put in Next days

    permit slotfor night shift team to prepare.

    Night Shift ASCs to pick up permits in next day permit slot and

    prepare accordingly

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    8/13

    SRCPD 8September 2010

    Operation Preparation (D 1)

    If unable to prepare equipment for various reasons ((e.g. passingvalves, single pump), ASC to capture reason in ASC log and place

    red sticker on permits, and put it back in Next Day Permit slot for

    Applicant to collect.

    Applicant will return the next morning to pick up his

    issued/rejected permit

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    9/13

    9

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    10/13

    SRCPD 10September 2010

    3. Permit Issuance stage and job execution

    Permits issuance to start work: begin at 0830 hrs

    (after operation SH, SoSO and STM)

    Possibility of limiting issuance time from 0830 0900hrs, to

    enable gas testing to proceed without interruptions

    Possibility of not issuing jobs that was meant to start in the

    afternoon

    In house contractor normal working hours shifted to 0830hrs

    1730hrs

    For LOTO isolation, PTW issuer to radio electrical person

    (Channel 8)

    Electrical will stand-by from 0830hrs onwards at BRM

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    11/13

    SRCPD 11September 2010

    Permit Issuance stage and job execution

    In the event that work cannot be carried out, filler job (clearancepermit) to be applied.

    Shift Team Meeting for afternoon to start at 1600 hrs instead of

    1630hrs

    Permits sign off around 1630 hrs onwards

    Question from the floor:

    How can ASC effectively conduct a Shift Team Meeting without first issuing permitsto Applicants?

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    12/13

    SRCPD 12September 2010

    Shift

    Handover0730 hrs

    Start of

    ShiftOrientation

    Shift Team

    Meeting

    0745 hrs

    0830 hrs

    ASC issue workpermits

    ASC

    ASC continue

    to issue work

    permits & gas

    test

    0845

    hrs

    TIME M&CC PTW

    Current Practice

  • 7/28/2019 PTW LEAN Initiatives_22 Sept

    13/13

    SRCPD 13September 2010

    Shift

    Handover0730 hrs

    Start of

    Shift

    Orientation

    Shift Team

    Meeting

    0745 hrs

    0800 hrs

    ASC issue work

    permits & gas

    test

    0830 hrs

    TIME M&CC PTW

    Proposed Timing 1 October onwards