PVNAVIGATOR, LLC Milliken Landfill Site Solar Project EPC RFP Site Visit, Photo Report WEST COAST 1 Pointe Drive, Suite 320 Brea, CA 92821 714.388.1800 www.PVNavigator.com www.SafetyMoment.org GULF COAST 15990 N. Barkers Landing Rd., Suite 325 Houston, TX 77079 713.468.5004 NORTHEAST 334 East 9 th Street New York, NY 10002 646.370.4588 January 14, 2016 12KV interconnect switchgear (Preliminary SWGR DIMS = 13’Wx3’D) Last SCE 12KV Overhead Pole PVN Proposed Layout of Solar Panel Array

Upload: robert-fritz

Post on 14-Apr-2017

107 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

PVNAVIGATOR, LLC

Milliken Landfill Site Solar ProjectEPC RFP Site Visit, Photo Report

WEST COAST1 Pointe Drive, Suite 320Brea, CA 92821714.388.1800

www.PVNavigator.comwww.SafetyMoment.org

GULF COAST15990 N. Barkers Landing Rd., Suite 325Houston, TX 77079713.468.5004

NORTHEAST334 East 9th StreetNew York, NY 10002646.370.4588

January 14, 2016

12KV interconnect switchgear (Preliminary SWGR DIMS = 13’Wx3’D)

Last SCE 12KV Overhead Pole

PVN Proposed Layout of Solar Panel Array

Page 2: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

2

PVNavigator, LLC is Poised to Start Construction on a 3MW PV Solar Installation on the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor. This Deck Describes the RFP Job Walk.

Sout

h M

illik

en A

venu

e

Mission Boulevard

Sout

h H

aven

Ave

nue

12KV interconnect switchgear (Preliminary SWGR DIMS = 13’Wx3’D)

Last SCE 12KV Overhead Pole

PVN Proposed Layout of Solar Panel Array

Page 3: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

3

On January 12, 2016, PVNavigator, LLC (PVN) and the County of San Bernardino Hosted a Site Visit for Potential Bidders to the Milliken Landfill PV Solar EPC RFP.

Page 4: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

4

Over 30 Individuals Representing 22 Firms Participated.

Page 5: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

5

PVN’s Robert Potter Briefed All Parties with a Safety Moment and a SOW Presentation Before Entering the Site.

Page 6: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

6

Bidders at the SCE Interconnect Location.

Page 7: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

7

With the PV Facility Going to be Located on the Landfill’s Top Deck, PVN Answered Questions Such as Landfill OM&M Procedures, and Gas Well Headers & Lines Protection.

Page 8: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

8

Potential Bidders Review the Milliken Landfill’s Top Deck…The Main Location for the PV Racks.

Page 9: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

9

Potential Bidders Discussed Any Potential Maintenance Costs that Should be Included in their Proposals.

Page 10: PVN_milliken-site-job-walk-photo-report-2016-01-12_v3 (3)

10

PVN’s Robert Potter, Rajeev Sane, and Robert Fritz Closed the Site Visit with a Debriefing and a Q&A Session.