quality control (qc) for

902
QUALITY CONTROL FOR ASPHALT RUBBER BINDERS AND MIXES by R. Gary Hicks Professor Emeritus Department of Civil Engineering Oregon State University and Jon A. Epps Professor Emeritus Department of Civil Engineering University of Nevada – Reno prepared for Rubber Pavements Association 1801 S Jentilly Lane, Suite A-2 Tempe, Arizona 85281 June 9, 2000

Upload: others

Post on 03-Feb-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: QUALITY CONTROL (QC) FOR

QUALITY CONTROL FOR ASPHALT RUBBER BINDERS AND MIXES

by

R. Gary Hicks Professor Emeritus

Department of Civil Engineering Oregon State University

and

Jon A. Epps

Professor Emeritus Department of Civil Engineering

University of Nevada – Reno

prepared for

Rubber Pavements Association 1801 S Jentilly Lane, Suite A-2

Tempe, Arizona 85281

June 9, 2000

Page 2: QUALITY CONTROL (QC) FOR

ABSTRACT As the use of asphalt rubber binders in hot mix asphalt (HMA) and chip seals gains wider acceptance, it becomes imperative that the quality control testing programs become formalized and uniform throughout the industry. Even one failure attributed to the asphalt rubber binder can set the industry back substantially.

Asphalt rubber (AR) binder is designed to meet a given agency specification and the results of the design are generally furnished to the agency. AR is presently controlled in the field using viscosity tests, unlike other binders which are certified by the supplier. This report summarizes the current practices used for quality control (QC) and quality assurance (QA) of asphalt rubber binders and mixes. Suggestions for improvements to the existing process have been identified. The report is intended to provide guidelines for new and/or existing producers of asphalt rubber binders to produce more uniform binders and to identify those factors which need to be closely monitored.

KEY WORDS asphalt cement, crumb rubber modifier, asphalt rubber, binder properties, quality control, quality assurance

i

Page 3: QUALITY CONTROL (QC) FOR

ACKNOWLEDGMENTS

This study is a cooperative industry-sponsored study which has been reviewed by agency and industry personnel. The authors are grateful to the critical review provided by the following people: Mark Belshe FNF Construction Sam Huddleston Law Engineering and Environmental Services George Way Arizona DOT K.C. Evans Texas DOT Maghsoud Tahmoressi PaveTex Engineering and Testing Inc. The report was typed by Peggy Blair of the Engineering Research Office, Oregon State University.

DISCLAIMER This document is disseminated under the sponsorship of the Rubber Pavements Association (RPA) in the interest of information exchange. The contents of this report reflect the views of the authors who are solely responsible for the facts and the accuracy of the material presented. The contents do not necessarily reflect the official views of the foundation.

ii

Page 4: QUALITY CONTROL (QC) FOR

TABLE OF CONTENTS

Page

1.0 Introduction .................................................................................................................... 1

1.1 Background............................................................................................................ 1

1.2 Objectives .............................................................................................................. 2

1.3 Study Approach ..................................................................................................... 2

2.0 Quality Control Procedures for AR Binder Ingredients .................................................... 3

2.1 Virgin Asphalt........................................................................................................ 3

2.1.1 Sampling and Testing of the Asphalt......................................................... 3 2.1.2 Sources of Asphalt Used............................................................................ 3 2.1.3 Agency Testing .......................................................................................... 7

2.2 Crumb Rubber Modifier (CRM)............................................................................ 7

2.2.1 Sampling and Testing the CRM................................................................. 7 2.2.2 Agency Testing ........................................................................................ 11

2.3 Discussion............................................................................................................ 11

3.0 Binder Design .................................................................................................................. 12

3.1 General Design Considerations............................................................................ 12

3.1.1. Pumping Consistency for Placement ....................................................... 12 3.1.2. High In-Use Temperature Stiffness ......................................................... 12 3.1.3 Moderate Temperature Consistency ........................................................ 13 3.1.4 Elastic Characteristics.............................................................................. 13 3.1.5 Elongation Properties............................................................................... 13 3.1.6 Low Temperature Stiffness or Fracture Characteristics .......................... 14 3.2 Factors Which Influence AR Properties .............................................................. 14

3.2.1 Asphalt Cement........................................................................................ 14 3.2.2 Crumb Rubber Modifier .......................................................................... 15 3.2.3 Contaminants ........................................................................................... 16 3.2.4 Mixing Conditions ................................................................................... 16 3.2.5 Time and Temperature............................................................................. 16 3.2.6 Extender Oil Additives ............................................................................ 17

iii

Page 5: QUALITY CONTROL (QC) FOR

3.3 Binder Design Process Currently in Use ............................................................. 17

3.4 Discussion............................................................................................................ 23

4.0 QC Procedures for AR Binders and Mixes...................................................................... 24

4.1 Current Procedures Used for AR Binders............................................................ 24

4.2 Ranking of Important Binder Factors .................................................................. 26

4.3 Important Factors for Mixes ................................................................................ 29

4.4 QC Tests for AR Mixtures................................................................................... 29

4.5 Discussion............................................................................................................ 29

5.0 Recommendations for Industry Standards for QC/QA.................................................... 32

5.1 Quality Control .................................................................................................... 32

5.2 Quality Assurance................................................................................................ 34

6.0 Implementation Plan ........................................................................................................ 35

6.1 Quality Control Procedures for AR Producers .................................................... 35

6.2 Quality Control/Quality Assurance Specifications for Public Agencies ............. 35

7.0 References .................................................................................................................. 36

Appendices

A Interview Survey Forms for RPA User and Producer Members

B List of Interviewees

C Results of Interviews – User Members

D Results of Survey – Producer Members

iv

Page 6: QUALITY CONTROL (QC) FOR

LIST OF TABLES

Table Page

2.1 QC/QA Procedures for Virgin Asphalt................................................................................4

2.2 QC/QA Procedures for Crumb Rubber Modifier.................................................................8

3.1 Procedures Used to Design AR Binders and Relate AR Binder Properties to Performance .......................................................................................................................18

3.2 Typical Design Profile of Type I Asphalt-Rubber Binder.................................................20

3.3 Typical Design Profile of f Type II Asphalt-Rubber Binder .............................................21

4.1 QC/QA Procedures Used in Production of AR Binders ....................................................25

4.2 Ranking of Important Factors – AR Binders .....................................................................28

4.3 Important AR Mix Performance Factors ...........................................................................30

5.1 Recommended QC Guidelines for Ingredients ..................................................................33

5.2 Recommended QC Guidelines for AR Binder...................................................................33

5.3 Recommended QC Guidelines for AR Mixtures ...............................................................33

v

Page 7: QUALITY CONTROL (QC) FOR

LIST OF FIGURES

Figure Page

2.1 Typical Certificate of Compliance – Paramount .................................................................5

2.2 Typical Certificate of Compliance – Navajo Western.........................................................6

2.3 Typical Certificate of Compliance – PolyTek Southwest....................................................9

2.4 Typical Certificate of Compliance – BAS.........................................................................10

4.1 Statistical Summary of AR Binder Properties ...................................................................27

vi

Page 8: QUALITY CONTROL (QC) FOR

1.0 INTRODUCTION

1.1 Background As the use of asphalt rubber binders in hot mix asphalt (HMA) and chip seals (CS) gains wider acceptance, it becomes imperative that the quality control testing programs become formalized and uniform throughout the industry. Even one failure attributed to the asphalt rubber binder can impact the industry greatly. There is no guarantee that current procedures will result in consistent binders as time and temperature of reaction can easily affect the properties of the binder produced. Furthermore, the base asphalt and the crumb rubber modifier (CRM), and their uniformity can also produce binders with varying properties. To monitor the quality of the asphalt rubber binders, the asphalt rubber industry uses several tests to evaluate the asphalt rubber binders including (Chehovits, 1993):

1) Viscosity, 2) Cone penetration, 3) Resilience, and 4) Softening point

Descriptions of these tests can be found in ASTM D-3407. These tests have been used since the 1970s to evaluate the properties of asphalt rubber binders (Chehovits, 1993; Epps, 1994). Questions which need to be addressed in this study include the following:

1) Do these tests ensure that the properties of the asphalt rubber binder on the pavement will be consistent and result in good performance?

2) Does time and temperature after measuring these properties vary such that there can

be vast differences in binder properties? 3) Asphalt source can impact the reaction between the base asphalt and crumb rubber

modifier. What steps are needed to ensure a more uniform source (or stream) of asphalt?

4) CRM source and uniformity can also affect the properties of the AR binder. What

steps are needed to ensure a more uniform stream of CRM? 5) What is the optimum frequency of testing needed to ensure a uniform product?

1

Page 9: QUALITY CONTROL (QC) FOR

1.2 Objectives The objectives of this study are two-fold, as follows:

1) Document the current procedures used by industry to control the quality of the asphalt rubber binder

2) Develop an industry standard (or guideline) to ensure that the asphalt rubber

properties are consistent from batch to batch and from contractor to contractor. 1.3 Study Approach Several steps should be taken to develop better and more uniform quality control procedures for asphalt rubber binders. As a minimum, the following should be undertaken:

1) Collect existing QC procedures for asphalt rubber binders through interviews with selected producers (Appendix A contains the survey instruments used to collect the necessary information for the study; Appendix B includes a list of those surveyed),

2) Summarize the information collected during the survey (see Appendices C and D), 3) Identify shortcomings of the QC procedures currently in use, and 4) Identify new or improved QC procedures which are needed to ensure uniform and

quality binders, including the identification of the AR properties which most influence pavement performance.

The end result of this study would be an industry-wide plan to ensure that AR binders are of high quality and uniform.

2

Page 10: QUALITY CONTROL (QC) FOR

2.0 QUALITY CONTROL PROCEDURES FOR AR BINDER INGREDIENTS

Both asphalt and/or CRM source can effect the properties of the resulting asphalt rubber (AR) binder. This section of the report summarizes the current procedures used to monitor the uniformity of the ingredients used in producing AR binders. 2.1 Virgin Asphalt A number of questions were asked of the AR binder producers regarding the QC/QA procedures they use for the virgin asphalt. The responses are provided in Table 2.1. Following is a brief discussion of the responses. 2.1.1 Sampling and Testing of the Asphalt Most asphalt rubber producers or blenders sample from the asphalt supplier’s transport when unloaded at the hot mix asphalt contractor’s production facility. Some asphalt rubber producers sample the base asphalt from the hot mix asphalt contractor’s storage tank. If the base asphalt is sampled and then subjected to additional heating, the properties could easily be altered due to the added heat. Most of the asphalt rubber producers take a 1 gallon sample of base asphalt daily for themselves and the agency. The temperature and the time of sampling varies even within a state, but the temperatures are higher in California than in other states (see Table 2.1). All of the AR binder producers rely on the supplier certification sheet to define the properties of the base asphalt. Typical certification sheets for Arizona and California are given in Figures 2.1 and 2.2. 2.1.2 Sources of Asphalt Used Most asphalt rubber producers generally use a base asphalt binder from one to three asphalt suppliers per year. Some use only one supplier of base asphalt. Most asphalt binders can be used to successfully produce AR. Some base asphalts will require higher contents of CRM to meet the AR binder specifications. Only a few asphalt binder sources have been found to not react with the CRM. These sources seem to be widely known among the producers of AR binders.

3

Page 11: QUALITY CONTROL (QC) FOR

Table 2.1. QC/QA Procedures for Virgin Asphalt

Arizona California Others

Question FNF ISSMeadow Valley FNF Granite Silvia MAI WSS All States Cox Paving

a) Where do you sample the asphalt?

From transport truck

From transport truck

From transport truck

From transport truck

From transport truck

From transport truck

From transport truck

From producer’s heated tank

From producer’s heated tank

From transport truck and/or producer’s tank

b) How often do you • sample the asphalt? • test the asphalt?

Daily

As needed

Daily

Daily

Daily

As needed

Daily

Each load

Daily

Weekly

Weekly

Weekly

c) What is the asphalt temperature (°F) at time of sampling? • average • min • max

350 335 400

290 320

315 300 330

385 375 410

400 375 415

380 350 425

400 385 425

410 390 425

300 275 325

385 360 410

d) What tests are used for QC? None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

e) How many sources of asphalt do you use/season?

1-3 1-3 > 3 1-3 > 3 1-3 1 1 1-3 1-3

f) Are you able to use all sources?

No No Yes Yes Yes Yes Yes No Yes No

g) Do you use asphalt supplier test results in lieu of your own for QC?

Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

h) Do you use public agency test results in lieu of your own for QA?

Yes Yes, only if there are problems

Yes, only if there are problems

Yes Yes Yes Yes No No No

4

Page 12: QUALITY CONTROL (QC) FOR

PRODUCT: RUBBER-ASPHALT BASE STOCK Purchaser ____________________ CODE No: 625 Destination ____________________ DATE: June 21, 1999 Transporter ____________________ TANK: Tk 20002 Truck or Railcar No ____________________ Bill of Lading No ____________________ Contract No ____________________ Purchase Order No ____________________ Meets Specifications: ASTM D3381, Table 3; AASHTO M226, Table 3; PBA-1; PBA-1a; Caltrans

92-102; Section 203-1.2 of 1997 “Greenbook” _________________________________________________________________________________

CERTIFICATE OF COMPLIANCE _________________________________________________________________________________ TESTS ASTM No ASHTO No SPEC RESULTS Tests on Residue from Rolling

Thin-Film Oven Test: D2872 T240 Viscosity, 60°C (140°F), Poise D2171 T202 3000-5000 4140

Viscosity, 135°C (275°F), cSt D2170 T201 275 min 416 Penetration, 25°C, 100g, 5s D5 T49 25 min 39 % of Original Penetration D5 T49 45 min 66 Ductility, 25°C, 5cm/min, cm D113 T51 75 min 100+ Loss on Heating, wt % D2872 T240 - - .20 Penetration, 4°C, 200g, 60s D5 T49 - - 12 Absolute Viscosity Ratio, 60°C

RTFO Vis./Original Vis. D2171 T202 4.0 max 2.4 Tests on Original Asphalt:

Penetration, 25°C, 100g, 5s D5 T49 - - 59 Flash Point, C.O.C., °F D92 T48 450 min 30 Solubility in

Trichloroethylene % D2042 T44 99.0 min 99.9 Viscosity, 60°C (140°F), Poise D2171 T202 - - 1730 Viscosity, 135°C (275°F), cSt D2170 T201 - - 279 Specific Gravity, 77/77°F D70 T228 - - 1.023 Specific Gravity, 60/60°F D70 T228 - - 1.024 API Gravity, 60°F D70 T228 - - 6.7

_________________________________________________________________________________

We hereby certify that the above sample was tested according to the applicable ASTM and AASHTO standards and that it complies with all specifications. Data Compiled By: _______________________ Released by: ____________________________ Shift Chemist Shift Team Leader

Figure 2.1. Typical Certificate of Compliance – Paramount

5

Page 13: QUALITY CONTROL (QC) FOR

Figure 2.2. Typical Certificate of Compliance – Navajo Western

6

Page 14: QUALITY CONTROL (QC) FOR

2.1.3 Agency Testing The AR binder producers generally provide samples of the virgin asphalt to the public agency for specification QA testing. The agency test results are generally provided to the AR binder producers anywhere from a few days to several weeks after receipt of the sample. If the binder is out of specification, penalties can be imposed. For the protection of the AR producer, it is always wise to document the time and location where the sample was taken. Some producers will retain samples of the virgin asphalt for up to one year. 2.2 Crumb Rubber Modifier (CRM) Several questions were asked of the AR producers regarding the QC/QA process used for the CRM. The responses are provided in Table 2.2. A brief discussion of all responses is given below. 2.2.1 Sampling and Testing the CRM Most of the producers do not sample the CRM unless there is a problem. They rely on the CRM supplier’s certification. Typical testing frequencies used by CRM suppliers are as follows: Property Frequency

• Sieve analysis from every 4000 lbs to twice a day • Chemical composition every 500,000 lbs

(e.g. carbon black, natural rubber content, ash content, and % hydrocarbon

However, there have been problems reported in California with respect to gradation recently. It is not clear whether this is due to sampling techniques or production methods. Regardless, a good sampling technique for the public agency is still needed. None of the AR binder producers routinely test the CRM. Only one AR producer reported having any tests performed when they change CRM suppliers. All of the AR producers rely on the certification of the CRM supplier. Samples of certification sheets from selected CRM suppliers are given in Figures 2.3 and 2.4.

7

Page 15: QUALITY CONTROL (QC) FOR

Table 2.2. QC/QA Procedures for Crumb Rubber Modifier

Arizona California Other

Question FNF ISSMeadow Valley FNF Granite Silvia MAI WSS All States Cox Paving

a) Where do you sample the CRM?

Do not sample normally

From the bag or hopper

Do not sample

Do not sample normally

Do not sample

From the bag or hopper

Do not sample normally

From the hopper

From the bag

From the hopper

b) How often do you sample the CRM?

As needed As needed or if a new supplier

Do not sample

As Needed Only if there is a problem

Every truck load

Only if there is a problem

Weekly When received

Daily

c) Do you perform any QC tests?

No Yes (gradation, metal, fabric moisture)

No No No No No No Yes, gradation

No

d) Do you use CRM supplier tests in lieu of your own for QC?

Yes, rely on certification

Yes, rely on certification

Yes, rely on certification

Yes Yes, rely on certification

Yes, rely on certification

Yes Yes Yes Yes

e) Do you use public agency test results in lieu of your own for QA?

Yes Yes, but varies greatly with agency

Yes Yes Yes Yes, and it has resulted in penalties

Yes No No No

8

Page 16: QUALITY CONTROL (QC) FOR

Figure 2.3. Typical Certificate of Compliance – PolyTek Southwest

9

Page 17: QUALITY CONTROL (QC) FOR

Figure 2.4. Typical Certificate of Compliance – BAS

10

Page 18: QUALITY CONTROL (QC) FOR

2.2.2 Agency Testing All AR binder producers rely on the agency tests for QA. In California this has resulted in penalties due to gradation. However, it has been suggested that the out of specification material is due more to sampling methods used than to variation in the product. This still needs to be confirmed. 2.3 Discussion The asphalt rubber producers currently rely almost entirely on the QC tests performed by suppliers of virgin asphalt and CRM. They do little or no QA tests on the products used to produce AR binders. Consideration should be given to the development of a QA plan which would include, as a minimum, the factors given below:

1) types of tests, 2) sampling procedures, 3) frequency of testing, 4) control limits, 5) acceptance limits, 6) pay adjustments, 7) referee testing, 8) retained samples, and 9) coping with non-specification materials.

11

Page 19: QUALITY CONTROL (QC) FOR

3.0 BINDER DESIGN

3.1 General Design Considerations Binder design involves an evaluation of the components of AR (asphalt cement, CRM, and additive) to determine:

1) the properties of the blend reacted over a range of time and temperature, 2) the stability of the blend over time, and 3) the proper proportions of the components to achieve the desired properties.

It must be emphasized that the physical properties of AR binders are substantially different from virgin asphalt cements. For any application that an AR blend will be used, there are several general characteristics of the blend that should be considered for the application. Several types of tests have been used to evaluate these characteristics as discussed in the following sections. 3.1.1 Pumping Consistency for Placement Pumping consistency at typical placement temperatures (250-400°F) can be monitored using rotational type viscometers such as a Haake hand-held, portable viscometer1 or a Brookfield viscometer (ASTM D2669). While these tests are being performed, it is important to ensure that the rotating probes are conditioned to the test temperature and that readings are taken at specific intervals because of a tendency with some AR blends for viscosity readings to reduce due to rubber particle migration away from the probe while it is rotating. The viscosity range at placement temperatures for AR blends is mainly affected by the rubber type, content, and degree of rubber swelling, and can vary from 100 to 20,000 centipoise for various applications. 3.1.2 High In-Use Temperature Stiffness Stiffness can be measured at typical high-range pavement surface temperatures of 120-170°F by several different testing procedures. The Ring and Ball Softening Point (ASTM D36) procedure provides an indication of relative stiffness of materials. A high softening point temperature indicates materials that are more resistant to softening at high temperatures. Ring and Ball Softening Points for AR binders will vary from approximately 110°F to 180°F. Results are mainly influenced by asphalt grade, rubber type and content, and degree of reaction. ________________________ 1No ASTM standard exists for the Haake Viscometer. It should be correlated to a Brookfield at 350°F ± 5°F over a range of values from 1.5 to 4.5 Pa-s.

12

Page 20: QUALITY CONTROL (QC) FOR

Asphalt and CRM blends have also been tested using the Dynamic Shear Rheometer (DSR) to determine characteristics over a wide temperature range. The DSR procedure is used to specify asphalt stiffness at high pavement surface temperatures in the Strategic Highway Research Program’s asphalt cement specification. This procedure has been adapted for use with AR, using the cup and plate test configuration, but its use is still under evaluation. 3.1.3 Moderate Temperature Consistency (77°F) Moderate temperature consistency (77°F) can be evaluated using the standard ASTM D5 penetration test or by using the cone penetration test as specified in ASTM D5329. The standard D5 test with the needle is most appropriate for finer rubber particles (minus 20 mesh) while the cone penetration test is more appropriate with larger rubber particles (10 mesh). Testing has shown that results for the two types of penetration tests (needle using 100 grams for 5 seconds, and cone using 150 grams for 5 seconds) typically agree within approximately 10 percent for tests at 77°F. The addition of CRM to asphalt cement decreases the penetration at 77°F. Typical penetration results range from approximately 30 for high CRM content materials with stiff asphalts to 150 for lower CRM content materials with soft asphalts. 3.1.4 Elastic Characteristics The elastic characteristics of asphalt and CRM blends can be evaluated using the ASTM D5329 resilience procedure. This procedure indicates the percentage of rebound of the material at 77°F under a 75 gram load after the material is compressed. Typical results for asphalt cement vary from approximately 0 to 5 percent for AC-20 or 30 grades to approximately 50 percent for AC-5. Addition of CRM to asphalt increases resilience up to approximately a value of 40 to 50 percent above the original asphalt result for high CRM contents. 3.1.5 Elongation Properties The elongation properties of AR have been evaluated using the standard ASTM D113 ductility procedure; however, many feel this test is not a reliable measure of ductile properties due to the particle interference of the CRM within the reduced area of the test specimen. Available results indicate the addition of CRM to asphalt tends to reduce ductility at 77°F, but may increase ductility at low temperatures (Huddleston, 2000). Results at 77°F for higher rubber content blends can vary between approximately 10 and 40 centimeters depending on the CRM type, asphalt physical and chemical characteristics, and degree of reaction. The ductility test can also be performed at lower temperatures to provide an indication of elongation properties at low temperatures.

13

Page 21: QUALITY CONTROL (QC) FOR

3.1.6 Low Temperature Stiffness or Fracture Characteristics Low temperature stiffness or fracture characteristics can be measured using several different types of procedures. Types of procedures that can be used include: 1) needle or cone penetration at low temperatures of 32 or 39.2°F (ASTM D5 or D5329), 2) ductility at 39.2°F (ASTM D113), 3) flexibility at a specific low temperature using the ASTM C711 flexibility procedure, or, with modifications, 4) the SHRP bending beam procedure, or 5) the Fraas brittle point procedure. CRM additions to asphalt cement can offer some improvements in low temperature properties. The major manner of improving low temperature properties, however, is to use softer grades of asphalt that offer improved low temperature properties, and then to add CRM to increase the high temperature stiffness to the desired level. 3.2 Factors Which Influence Asphalt Rubber Properties The interaction that occurs between asphalt cement and CRM and the physical properties which result have been shown through many research studies to be dependent on a variety of factors including: 1) asphalt cement physical and chemical properties, 2) CRM physical and chemical properties, 3) reaction time and temperature, 4) mixing conditions, and 5) use of additives. When developing an AR blend for a specific use, the effect of each of these factors needs to be considered to assure that an appropriately functioning material is produced. 3.2.1 Asphalt Cement The physical properties of the asphalt cement influence the properties of AR blends. The stiffness, temperature susceptibility and aging characteristics of the asphalt will affect the high temperature and low temperature performance of the blend. Typical grades of asphalt that are used with CRM for various applications and climate ranges are shown below:

Climate AC Grade AR Grade PG Grade

Cold AC-5 AR-2000 PG 52-28

Moderate AC-10 AR-4000 PG 58-22

Hot AC-20 AR-8000 PG 64-16

Use of stiffer asphalts will produce AR materials that have greater high temperature stiffness than obtained with softer asphalts. However, stiffer asphalts will produce AR materials that are harder at lower temperatures than those AR binders made with softer asphalts. Chemical properties of the asphalt cement can also influence the characteristics of the AR by affecting reaction of the rubber. Asphalts that have lower levels of components which are absorbed by the rubber can tend to produce AR materials with lower viscosities and lesser degrees of modification of properties.

14

Page 22: QUALITY CONTROL (QC) FOR

3.2.2 Crumb Rubber Modifier (CRM) Many of the characteristics of the CRM can influence properties of AR. Previous research has reported on the effects of rubber quantity in the blend and particle size distribution. Additional effects include: 1) CRM surface area, 2) grinding process, 3) CRM chemical composition, and 4) contaminants such as water, fiber, mineral, or metal. Each is discussed below.

1) CRM Quantities. The amount of CRM added to the asphalt will influence blend properties with higher amounts providing greater changes in properties. Generally speaking, as the rubber content increases: 1) the viscosity of the material at 350°F increases, 2) the resilience increases, 3) the softening point increases, and 4) the cone penetration at 77°F decreases.

2) CRM Particle Size Distribution (Gradation). The particle size distribution of the

CRM has previously been shown to influence the physical properties of asphalt and CRM blends. Generally, small differences in the particle sizes do not affect blend properties significantly, but large differences in CRM size can produce larger differences. Finer sized CRM materials will generally experience quicker swelling due to their increased surface area and will produce higher viscosities than CRM with larger particle sizes. Additionally, very small particle size CRM will tend to more quickly experience viscosity reduction with storage due to its quicker and more thorough swelling and subsequent depolymerization.

3) CRM Surface Area. Surface area of the CRM can influence physical properties. In

some ways, this is similar to gradation; however, surface area differences can exist even for CRM with similar gradations.

4) CRM Grinding Process. The CRM production process may influence the physical

shape and surface area characteristics of the rubber particles. Additionally, ambient temperature size reduction results in rough shredded particles surfaces, while cryogenic size reduction results in smoother glassy surfaces.

5) CRM Chemical Composition. Tires are composed of several different types of

rubber compounds. The major variations are in the synthetic rubber content, natural rubber content, total rubber hydrocarbon content, and acetone extractables. Ash and carbon black contents are typically similar for different tire rubber compounds. The major CRM compositional effect on AR physical properties is the total rubber hydrocarbon content of the rubber with additional effects from the natural rubber content. When using CRM, it is important to comprehend that tire rubber is typically composed only of about one-half of actual rubber polymer that will swell in the asphalt. The other major ingredients (carbon black, ash, oil) do not swell when added to hot asphalt cement binder. Therefore, the effective rubber hydrocarbon content (the AR rubber content times the rubber hydrocarbon content of the rubber) becomes a factor that should be considered during the AR design process. Additionally, it is important to note that adjustments of the chemical composition made to CRM by

15

Page 23: QUALITY CONTROL (QC) FOR

blending with additional CRM with a different composition may not produce the same results in AR blends as an unblended CRM with the same composition.

3.2.3 Contaminants Various types of contaminants may be present in CRM. Typical contaminants are moisture, tire cord and belt fiber, particulate minerals, and fine metal particles. The effect of moisture in CRM is to cause foaming and swelling of the asphalt when moist CRM is added to the hot asphalt. Foaming causes a volume expansion of the blend just after the CRM is added to the asphalt that can cause production or storage vessels to overflow. Moisture contents of CRM can simply be determined by loss of heating procedures that dry the rubber particles at 230°F until a constant weight is achieved. The presence of even small amounts of moisture in the CRM can cause foaming to occur. Experience has shown that moisture amounts over 1 percent by weight can cause excessive foaming. The amount of foaming which can be tolerated is somewhat dependent on the production equipment, process, and rate of CRM addition. It is suggested that moisture contents be kept at less than 0.75 percent by weight of CRM to minimize foaming. 3.2.4 Mixing Conditions The intensity of mixing during the interaction time period can influence AR properties. Differences in mixing and shearing intensity can vary from low speed agitation that gently keeps the rubber particles in suspension to high speed shearing that can mechanically break down the rubber particles. With low speed agitation, the asphalt contents are simply absorbed as the rubber particles swell with little dispersion of the rubber polymer into the asphalt. During high intensity mixing, the rubber particles swell and soften due to asphalt absorption, and the high energy mixing tends to shear off the softened rubber outer surfaces and produces a dispersed rubber component in the asphalt phase of the material. 3.2.5 Time and Temperature The reaction process of rubber particles in asphalt cement is both time and temperature dependent. Higher temperatures result in quicker reaction and may result in greater amounts of swelling. These effects have been well documented in the literature. Typical temperatures that are used with AR materials range from 325 to 400°F. AR materials made with tire derived CRM generally maintain their physical properties for at least 24 hours at temperatures of up to 350°F. At higher temperatures (375 to 400°F), the CRM can begin to depolymerize within three to six hours to such an extent that physical properties are affected.

16

Page 24: QUALITY CONTROL (QC) FOR

3.2.6 Extender Oil Additives Various extender oil additives can be added to AR materials to modify the properties of the blend. Extender oil addition tends to soften the asphalt and decrease low temperature stiffness of the blend. Depending on the chemical characteristics of the asphalt, certain extender oil types may be preferentially absorbed by the CRM. Generally, aromatic or napthenic oils are preferred. 3.3 Binder Design Process Currently in Use The physical properties of an AR mixture depend on the physical and chemical properties of the materials used, the reaction between these materials, and the interaction conditions. Therefore, to obtain desired properties, appropriate materials and interaction conditions which will produce desired properties need to be identified. Specific items which should be addressed are: 1) asphalt cement source and grade, 2) CRM source and gradation, 3) CRM content, 4) interaction conditions of time, temperature, and mixing intensity, and 5) the need for additives, if required. Table 3.1 summarizes the general binder design procedures currently used by the AR producers. The binder design is generally established at a target viscosity for field testing. If the viscosity fluctuates greatly, an additional test for resilience might be warranted to insure the desirable properties are achieved. The concept of a “design profile” (Huddleston, 1999) is a useful tool to aid in determining the frequency of tests in the field. Examples of typical “design profiles” are given in Tables 3.2 and 3.3 for a type I and II AR binder.

Since the characteristics of AR vary depending on heating time and temperature, it is important that the characteristics of the blend be evaluated over a range of heating times and temperatures and mixing intensities that the material will be exposed to during the usage period. In general, it is recommended that the physical characteristics of AR be evaluated using the planned mixture temperature and mixing intensity, and at short, medium and long interaction time periods which would be appropriate for the specific application.

Mixing intensity for lab design operations should be correlated with the actual production unit and usage equipment characteristics. Several types of mixing conditions can be used to attempt to simulate actual conditions. One method consists of simply performing the reaction in a one-gallon, round, open-top can that is placed in a forced-draft oven to maintain the desired temperature. Agitation can consist of intermittent stirring with a spatula or glass rod at specified intervals (typically 30 minutes) during the interaction period. This procedure simulates low speed mixing with gentle agitation with minimal shearing of the rubber particles. Another procedure consists of using an oil-jacketed, removable-can type melter specified in ASTM D-5167. This device can uniformly control the temperature of the mixture through indirectly heated oil while constantly stirring at 30 rpm. This procedure provides a higher degree and continuous agitation of the mixture during the interaction period and simulates typical crack and joint sealing and other typical field mixing operations.

17

Page 25: QUALITY CONTROL (QC) FOR

Table 3.1a. Procedures Used to Design AR Binders and Relate AR Binder Properties to Performance (Arizona)

Producers Private Laboratories

Question FNF ISS Meadow Valley Law Engineering Western

Technologies Speedie & Associates

a) Do you perform a binder design? Yes, use private laboratory

Yes, use private laboratory

Yes, use private laboratory

Yes Yes Yes

b) What procedures are used? Experience and lab protocol

Experience and lab protocol

Experience and lab protocol

Experience and lab protocol

Experience Experience plus lab protocol

c) What tests are used in the binder design? • Viscosity • Resilience • Softening point • Cone (or needle) penetration • Other

X X X X

Ductility

X X X X

X X X X

X X X X

X X X X

X X X X

Ductility, retained penetration and resilience

d) How often is a binder design performed? Generally every project

Every project Every time there is a change in oil or CRM

Every project normally; the exception would be when one binder is used on small jobs within short time frame

Every project or whenever the asphalt or CRM source is changed for small projects

Every project or whenever asphalt type or CRM source is changed

e) Is the binder design performed by • an accredited lab? • a certified tech?

Yes Yes

Yes Yes

Yes Yes

Yes (ARML) Yes (NICET)

Yes (ARML) Yes (NICET)

Yes Yes

f) Does the binder design require the use of an extender oil?

No No No No (AZ)Yes (CA)

Yes (AZ) Depends on project spec

g) Does the binder design result in good performance?

Yes Yes Yes Yes Yes, 90% of time

h) How are binder properties correlated with field performance?

Occasional field survey

Database on field projects

No problems to date Only respond to problems

Occasional field surveys

i) Is a new binder design procedure needed?

No No No Yes, always room for improvement

No Yes, standardization of material specific test method

18

18

Page 26: QUALITY CONTROL (QC) FOR

Table 3.1b. Procedures Used to Design AR Binders and Relate AR Binder Properties to Performance (Other Agencies)

California Producers Texas New England Question Granite Silvia MAI WSS Cox Paving All States

a) Do you perform a binder design? Yes, use private lab when required; otherwise do the design in-house

Yes, use private lab

Yes, use private lab

Yes, use private lab

Yes, use private lab

Yes, do the design in-house

b) What procedures are used? Laboratory testing protocol

Experience plus lab protocol

Experience Laboratory testing protocol

Experience plus lab protocol

Laboratory testing protocol

c) What tests are used in the binder design? • Viscosity • Resilience • Softening point • Cone (or needle) penetration • Other

X X X X

X X X X

X X X X

X X X X

X X X X

X X X X

d) How often is a binder design performed? Before every project

Whenever asphalt source is changed

Whenever asphalt source is changed

Every project Every project Whenever asphalt source is changed

e) Is the binder design performed by • an accredited lab? • a certified tech?

Depends on whether done by private lab; Granite lab is not accredited

Yes Yes

Yes Yes

Yes

Yes Yes

Done in-house, no certification

f) Does the binder design require the use of an extender oil?

Yes (CA) No (AZ)

Yes Yes Yes No No

g) Does the binder design result in good performance?

Yes Yes Yes Yes Yes (90%) Yes (90%)

h) How are binder properties correlated with field performance?

Occasional field survey and/or response to problems

Occasional field survey; problems only on a few projects

Annual field surveys of all jobs

Occasional field surveys

Annual field survey + respond to problems

Occasional field survey

i) Is a new binder design procedure needed?

No No No No No No

19

19

Page 27: QUALITY CONTROL (QC) FOR

Table 3.2. Typical Design Profile of Type I Asphalt-Rubber Binder [21.2% Polytek Southwest WRF-14 Crumb Rubber (Queen Creek, Arizona), by Weight of Asphalt Cement (Navajo Western Asphalt PG 64-16)], Law Engineering and Environmental Services, Phoenix, AZ

a) Properties of AR Binder

Minutes of Reaction Test Performed 60 90 240 360 1440

Specified Limits

Viscosity, Haake at 177°C, Pa-s 2.8 2.8 2.6 2.3 2.1 1.5-4.0

Resilience at 25°C, % Rebound (ASTM D5329)

31 31 30 30 Minimum

Ring & Ball Softening Point, °F (ASTM D36)

146.5 146.0 146.5 144.0 140.0 135 Minimum

Needle Penetration at 4°C, 200 g, 60 sec., 1/10 mm (ASTM D5)

21 22 26 10 Minimum

Note: The asphalt-rubber mixture was held overnight at 135°C and heated back to 177°C for the final 24-hour reaction period.

b) Rubber Gradation, Percent Passing (ARIZ 714)

Sieve Size Result Specified Limits

No. 8 100 No. 10 100 100 No. 16 86 65-100 No. 30 29 20-100 No. 50 10 0-45

No. 200 0.0 0-5

20

Page 28: QUALITY CONTROL (QC) FOR

Table 3.3. Typical Design Profile of Type II Asphalt-Rubber Binder [21.9% CRM, Type B ADOT Crumb Rubber (Rancho Dominguez, California), by Weight of Asphalt Cement (Chevron Asphalt PG 58-22)], Law Engineering and Environmental Services, Phoenix, AZ

a) Properties of AR Binder

Minutes of Reaction Test Performed 60 90 240 360 1440

Specified Limits

Viscosity, Haake at 350°F, cP 3600 3200 3400 3400 2900 1500-4000

Resilience at 77°F, % Rebound (ASTM D5329)

43 41 38 25 Minimum

Ring & Ball Softening Point, °F (ASTM D36)

157.5 154.5 155.0 154.5 150.0 130 Minimum

Needle Penetration at 39.2°F, 200 g, 60 sec., 1/10 mm (ASTM D5)

24 24 27 15 Minimum

Note: The asphalt-rubber mixture was held overnight at 275°F and heated back to 350°F for the final 24-hour reaction period.

b) Rubber Gradation, Percent Passing (ARIZ 714)

Sieve Size Result Specified Limits

No. 8 100 No. 10 100 100 No. 16 99 65-100 No. 30 68 20-100 No. 50 18 0-45

No. 200 0.7 0-5

21

Page 29: QUALITY CONTROL (QC) FOR

The last procedure consists of using a research device that is termed a “Torque Fork.” This device consists of an adjustable speed electric motor that stirs the asphalt and CRM blend at a constant speed. The device can monitor the electrical current level required to maintain the desired stirring speed as the viscosity of the mixture increases. This type of device has been used with stirrer speeds of 500 to 750 rpm. The mixing vessel size has been approximately 3000 milliliter (0.8 gallons) with sample weights of 1000 grams. The Torque Fork, when operated at speeds of 500 to 750 rpm, imparts a high degree of mixing intensity to the mixture. Tests which are performed during the design process should be selected to provide an indication of required characteristics of the AR blend. When specifications for the specific application are available, testing required by the specification should be performed as a minimum. For any AR material the testing program for the specific use should be designed to provide the suppliers and users with the following information:

1) Placement temperature viscosity 2) High in-use temperature stiffness or consistency 3) Moderate in-use temperature consistency 4) Elastic characteristics 5) Elongation properties 6) Low in-use temperature consistency 7) Variation of properties over typical heating times encountered during use

Once a design blend of asphalt, CRM and additives is verified for the application, along with defined mixing and production times, temperatures and mixing process, the design process may be complete. For some applications such as chip seals and hot mixes, additional performance testing may be required to verify the appropriateness of the designed binder for the application or to determine if additives for improved adhesion are necessary.

The completed design for an AR binder should consist of the following documentation as a minimum:

1) Asphalt source, grade, and specification test results 2) Rubber source, type and specification test results 3) Additive identification, if required 4) Percentage blend (by weight) for each ingredient 5) Mixing temperature and times considered during the design

22

Page 30: QUALITY CONTROL (QC) FOR

6) Mixing system used during the design 7) Test results for the designed blend at the various mixing times considered in

accordance with the desired blend specification requirements 8) Additional tests and results used to verify performance in the final application, if

required It is important to realize that since asphalt cement and rubber specifications do not

currently address all the factors related to the reaction process and blend characteristics (such as chemical composition, surface area, etc.), that whenever the source of any of the design ingredients change, or there is a change in the composition or properties of the specified asphalt or rubber, that the design should be reverified. This concept is similar to that of hot-mixed, asphalt concrete mix designs in which new designs are required when using different sources of asphalt or aggregate which meet the same specifications due to variations which can occur for materials within the specification limits. 3.4 Discussion A wide variety of physical properties can be achieved by adding CRM to asphalt cement. Different applications of AR materials require different physical properties, and therefore differing formulations. Factors which must be considered when specifying and designing an AR material for a specific use include:

• Climate conditions and temperature ranges the material will be subjected to • Ranges of viscosity at placement temperature which are appropriate for the

production equipment • Constraints on CRM particle size for the intended use • The desired performance level of the AR material in the specific application Even though a wide variety of performance levels can be achieved by using CRM, there

are limits. Performance characteristics of increased high temperature stiffness and reduced low temperature stiffness are achieved by using asphalt cement bases which have appropriate low temperature properties for the intended use, and then adding CRM of the appropriate type and quantity to yield required high temperature and elastic characteristics. The maximum amount of CRM which can be added (and thus the degree of modification of high temperature properties) is dependent on the maximum application temperature viscosity that can be used.

23

Page 31: QUALITY CONTROL (QC) FOR

4.0 QC PROCEDURES FOR AR BINDERS AND MIXES

Producers were surveyed with regard to the quality control procedures they employ for AR binders as well as mixes. This chapter discusses the procedures used as well as a ranking of the factors to be controlled which are considered most important. It also discusses the need for QA by the agencies. 4.1 Current Procedures Used for AR Binders Table 4.1 summarizes the questions dealing with QC of the AR binders. Each of the responses are discussed in more detail below:

1) Sampling Location. Most producers sample from the blending/holding tanks or from the feedline from the holding tank to the mixing unit.

2) Sampling and Use Time. As discussed earlier, time of reaction can greatly affect the

binder properties. Since there is variation in the sampling time (due in part to differences in specifications), one would expect the AR properties could vary from producer to producer. However, as long as the AR is within the specification, the resulting product should produce a quality pavement.

On the other hand, there is also some variation in the reaction time before the

product is used, varying from as little as 45 to 360 minutes. This large range in time could easily have a major impact on binder properties. AR producers need to assure user agencies that the variation in time of reaction before use will not adversely affect the properties of the binder.

3) Reaction and Storage Temperature. As discussed under binder design, these

factors can also greatly affect binder properties. With a temperature range from a low of 325° to 400°F, it is possible the binder will meet specifications at the time of the test in the field, but could fall out of specification if held for longer periods. The binder design must be conducted over the range of temperatures expected in the field and over a range of time periods. Reaction time generally begins when all the rubber is completely introduced in the mixing unit.

4) Frequency of Sampling. Most producers sample every batch while some still

sample daily. For work with public agencies, sampling every batch is recommended. 5) QC Tests Performed. Most producers use the Haake viscometer to check the

consistency of the AR binder. However, there is no consistency in the temperature used to test the product or the allowable temperature range for performing the test. Since the properties of asphalt cement and AR are highly temperature susceptible, tighter controls on the temperatures used to run the viscosity tests are needed.

24

Page 32: QUALITY CONTROL (QC) FOR

Table 4.1. QC/QA Procedures Used in Production of AR Binders

Arizona Producers California Producers Other Producers

Question FNF ISSMeadow Valley FNF Granite Silvia MAI WSS Cox Paving All States

a) Where is the AR binder sampled?

Blending tank Blending tank Blending tank Blending tank Hold tank Feed line from holding tank

Blending tank Hold tank Blending tank,hold tank, and/or feedline

Hold tank

b) When is the AR binder sampled and used (min)? • Sampled

(min-avg-max) • Used

(min-avg-max)

50-60-70

60-90-120

40-60-80

60-90-120

60-75-90

60-90-180

30-45-60

45-??-120

45-??

45-??-180

45-??-120

60-??-240

45-??-50

50-??-180

45-??-60

30-??-90

90-??-360

30-60-90

c) What is the reaction and

storage temperature (°F)? (min-avg-max)

325-350-370 325-350-375 325-350-375 370-380-400 375-385-400 375-385-400 375-400-425 375-390-400 350-360-380 350-375-400

d) What is the frequency of QC sampling?

Every batch Every batch Every batch Every batch Every batch Every batch Every batch Daily Every batch Daily

e) What QC tests are performed?1

Haake viscosity @ 350 ± 5°F

Haake viscosity @ 350 ± 20°F

Haake viscosity @ 350 ± 10°F

Haake viscosity @ 375 ± 5°F

Haake viscosity @ 375 ± 1°F

Haake viscosity @ 375 ± 5°F

Haake viscosity @ 400 ± 20°F

Haake viscosity @ 390 ± 10°F

Haake viscosity @ 350 ± ??°F

Haake viscosity @ 375 ± 10°F

f) What QA tests are performed?

Spec tests performed by ADOT

Spec tests, only if needed

Spec tests, only if needed

Viscosity(local agency) and DSR (Caltrans)

Viscosity (local agency) and DSR (Caltrans)

Viscosity (local agency) and DSR (Caltrans)

Viscosity Viscosity None

g) What is the frequency of QA sampling?

Per batch 2 per day As needed Per batch Daily Varies with agency

Per batch Daily Daily Not applicable

h) Where are the QA samples taken?

Same as for QC

Same as for QC

Same as for QC

Same as for QC

Same as for QC

Same as for QC

Same as for QC

Same as for QC

Same as for QC

Not applicable

i) Are statistical summaries showing variations in AR properties available?

No Yes No No Yes No No No No No

1Varies because of agency’s specification (AZ = 350 °F, CA = 375°F, TX = 350°F, MS = 375°F)

25

Page 33: QUALITY CONTROL (QC) FOR

6) QA Tests Performed. Even though samples are taken for the agency (or owner), QA tests are not always run. The extent of testing varies with the agency.

7) Frequency of QA Sampling. Samples are taken by the producer for the owner

agency as often as every batch and in some cases not at all. It would be useful for the industry to establish quality procedures for the agency to ensure disputes over binder quality do not develop.

8) Statistical Summaries of AR Properties. Only a few of the producers have a data

base showing variations of properties over time (Fig. 4.1). It is essential this sort of information be collected and maintained in a database.

4.2 Ranking of Important Binder Factors Each producer was surveyed as to the importance of factors such as

1) asphalt source and grade, 2) CRM source and gradation, 3) CRM content, 4) blending and agitation method, 5) time/temperature of reaction, 6) binder design, and 7) additives

on the properties of the binder. The results are given in Table 4.2. As expected, different producers ranked the importance of the factors differently. However, when all scores are combined, the following ranking emerges:

26

Page 34: QUALITY CONTROL (QC) FOR

7.05.03.01.01.0

0

50

100

��������������������������������������������

����������������������������������������������������������������������������������������

Time—$

Visc

osity

SpecLimits

Individual test point

27

Figure 4.1. Statistical Summary of AR Binder Properties

Page 35: QUALITY CONTROL (QC) FOR

Table 4.2. Ranking of Important Factors – AR Binders

Arizona Producers California Producers Other Producers

Question FNF ISSMeadow Valley FNF Granite Silvia MAI WSS

Cox Paving

All States Total

Important binder properties* • Asphalt source and grade 1 3 3 1 2 1 1 1 1 3 17 • CRM source and gradation 3 2 3 3 2 2 1 1 2 2 21 • CRM content 2 3 3 2 2 1 1 2 2 1 19 • Blending and agitation

method/equipment 4 1 1 4 1 2 1 2 1 2 18

• Time/temperature of reaction 1 1 2 1 1 1 1 1 2 3 14 • Binder design 4 1 1 4 2 1 1 1 2 1 18 • Additives (extender oils) 5 5 Not used 5 2 2 1 3 5 5 33

*1 = most important 5 = least important

28

Page 36: QUALITY CONTROL (QC) FOR

Factor Total Score Order of Importance

Asphalt Source and Grade 17 2

CRM Source and Grade 21 6

CRM Content 19 5

Blending and Agitation Method 18 3

Time/Temperature of Reaction 14 1

Binder Design 18 3

Additives 33 7 4.3 Important Factors for Mixes AR binders are just one of many factors that can affect the performance of the mix or the pavement. Table 4.3 summarizes the individual rankings of the producers surveyed with regard to the importance of other factors (aggregates, mix design, construction procedures, QC/QA, and structural design). As can be seen, most factors are considered important and should be considered. 4.4 QC Tests for AR Mixtures Based on the survey, most contractors control the following items when producing AR mixes:

1) aggregate gradation, 2) binder content, 3) volumetrics (field mix – lab compacted), and 4) in-place air voids.

Control of these factors are important to ensuring a quality job. 4.5 Discussion Quality control in binder production is very important. As indicated, there are significant differences in the QC processes used by the various producers. The next chapter provides recommendations for industry standards to ensure a consistent product between producers within a given state.

29

Page 37: QUALITY CONTROL (QC) FOR

Table 4.3. Important AR Mix Performance Factors

Arizona Producers California Producers Other Producers

Question FNF ISSMeadow Valley FNF Granite Silvia MAI WSS

Cox Paving

All States

Important AR mixture performance factors* • AR binder 2 1 3 2 2 1 1 1 1• Aggregates 2 1 1 2 2 1 1 2 1• Mix design 3 1 2 3 2 1 1 1 1• Construction procedures including weather

during construction 1 1 4 1 1 1 1 1 1

• QC/QA 3 1 4 3 2 1 1 3 2• Structural design including existing surface

condition 4 1 4 4 1 1 1

Not applicable, only do chip seal work

4 2

*1 = most important 5 = least important

30

Page 38: QUALITY CONTROL (QC) FOR

Also, the binder is but only one of the factors which must be controlled if the AR mix is to perform in the field. Placement of a quality binder does not guarantee the pavement containing the binder will perform. Guidelines for use of AR mixes need to be established. This will also be discussed in the next chapter.

31

Page 39: QUALITY CONTROL (QC) FOR

5.0 RECOMMENDATIONS FOR INDUSTRY STANDARDS FOR QC/QA

As indicated in the prior chapters, there are considerable variations in the QC/QA procedures used. Some of this is due to the variations in the specifications used by the different agencies; others are simply because there is no industry standard for QC. This chapter presents a first attempt at an industry standard. Most of the recommendations are simply based on achieving the best practice currently available. Incremental improvements in processes need to continue as new and/or better techniques become available. 5.1 Quality Control Based on the survey of producers and the authors experience with specifications, the following QC guidelines are recommended.

1) AR Binder Ingredients. Table 5.1 summarizes the QC recommendations for the virgin asphalt and the CRM. As indicated, samples are taken frequently but not always tested unless there is a dispute with the supplier. AR binder producers need to assure themselves that all the ingredients are the ones ordered. Certifications for all ingredients are required (e.g., PP-26 or equivalent).

It should be noted that the existing tests used to characterize AR are not the

same as those used by the rest of the asphalt industry (e.g., performance tests evolving in the Superpave effort). The AR industry needs also to evaluate these tests for QC as the next generation of binder specifications will likely require the Superpave type of binder tests.

2) AR Binder. Considerable variation currently exists in sampling/testing frequency as

well as test temperature. Binders should be tested at the specification temperature and the variation in test temperature should conform as closely as possible with ASTM requirements (± 0.2°F). Initial recommendations are provided in Table 5.2.

Pre-job testing (binder design) can be utilized to establish the standard to

which field testing can be compared. It is recommended that the binder design yield a viscosity in the mid-range of the specification and that rubber content is adjusted in the field to maintain this number. The design profile concept presented in Tables 3.2 and 3.3 is a good tool to use to suggest an appropriate test frequency for monitoring the project. The AR producers may want to initiate a small field study to evaluate cost effective ways of controlling field temperatures (e.g., quart vs. gallon, oil bath, small high temperatures over) and to establish a reasonable field temperature control range (e.g., ± 1°F, ± 5°F).

3) AR Mixture. Table 5.3 provides the recommended tests which should be performed

on the AR mix. At present not all of these properties are being monitored.

32

Page 40: QUALITY CONTROL (QC) FOR

Table 5.1. Recommended QC Guidelines for Ingredients

Ingredient Sampling Frequency Tests to Perform

Recommended Testing

Frequency Comments

Asphalt cement Every truck load

• Viscosity Every truck load

Certification must be provided

CRM Every shipment

• Gradation • Chemical composition

4000 lbs 250 tons

Certification must be provided

Table 5.2. Recommended QC Guidelines for AR Binder

Property Sampling Frequency

Testing Frequency Test Temperature Comments

Haake viscosity Every batch Every batch Spec ± 5°F Must use calibrated device Resilience Every batch As needed ASTM spec Test performed in certified

lab Cone penetrometer Every batch As needed ASTM spec Test performed in certified

lab Softening point Every batch As needed ASTM spec Test performed in certified

lab

Table 5.3. Recommended QC Guidelines for AR Mixtures

Property Sampling Frequency Testing Frequency Comments

Aggregate • absorption, crushed

faces, abrasion As part of mix design process

As needed Sample taken for mix design

• gradation, sand equivalent, PI

500 to 4000 tons 500 to 4000 tons Sample taken from cold feed

AR binder content 500 to 4000 tons 500 to 4000 tons Using ignition oven or nuclear gauge

CRM content in binder 500 to 4000 tons 500 to 4000 tons Monitoring rubber input Volumetric properties (voids, HMA)

500 to 4000 tons 500 to 4000 tons Using Marshall or gyratory compactor

33

Page 41: QUALITY CONTROL (QC) FOR

For all QC processes, summaries showing variations in the property being monitored should be developed. This information will provide assurance to the contractor and owner agency that the product is within specifications and will result in a quality product. 5.2 Quality Assurance The level of quality assurance testing will vary from owner to owner and whether the work is for a public agency or private owner. All owners should be encouraged to develop a QA program for their own protection. The types of tests would include those used for QC, only the frequency of testing need be altered.

34

Page 42: QUALITY CONTROL (QC) FOR

6.0 IMPLEMENTATION PLAN

This section of the report provides recommendations for implementing the findings of this study. Suggestions for both RPA user members and for public agencies are provided. 6.1 Quality Control Procedures for AR Producers The recommendations and processes presented in Chapter 5.0 need to be evaluated by each producer during the 2000 construction season. Constructive feedback on the processes is critical to ensuring incremental improvement in providing quality products. An important consideration is for the AR producers to begin to establish control charts documenting variations in AR properties (e.g., viscosity and resilience) over time (see Fig. 4.1). Variations in properties of the AR binder can easily affect the performance of the AR mix. All producers need to receive training on binder design and the importance of quality control programs. One way to accomplish this is for RPA to establish a training facility where producers’ crews can be trained periodically (e.g., every year). The training program could be monitored by the Technical Advisory Board of RPA to ensure all critical aspects are covered. It is also imperative that all testing be performed by certified technicians in an accredited laboratory. 6.2 Quality Control/Quality Assurance Specifications for Public Agencies All producers must work with the owner agencies to establish acceptable specifications for AR binders and mixtures containing these binders. Training of the owner agencies on the importance of binder design and QC/QA is also needed.

35

Page 43: QUALITY CONTROL (QC) FOR

7.0 REFERENCES

Asphalt Rubber Producers Group, Proceedings, National Seminar on Asphalt-Rubber, Kansas City, MO, October 1989.

Baker, Tim, “Production of Crumb Rubber Modifier Material – Session 3,” Working Notes,

FHWA Crumb Rubber Modifier Workshops, FHWA-SA-93-011, Federal Highway Administration, 1993.

Chamberlin, William P., “Performance-Related Specifications for Highway Construction and

Rehabilitation,” NCHRP Synthesis 212, Transportation Research Board, 1998. Chehovits, J.G., “Binder Design Procedures – Session 9,” Working Notes, FHWA Crumb

Rubber Modifier Workshops, FHWA-SA-93-011, Federal Highway Administration, 1993. Chehovits, J.G. and R.G. Hicks, “Mix Design Procedures – Session 10,” Working Notes, FHWA

Crumb Rubber Modifier Workshops, FHWA-SA-93-011, Federal Highway Administration, 1993.

Epps, Jon A., “Uses of Recycled Rubber Tires in Highways,” NCHRP Synthesis 198,

Transportation Research Board, 1994. Epps, Jon A. and Bob M. Gallaway, “Workshop Summary,” Proceedings, First Asphalt-Rubber

User-Producer Workshop, Scottsdale, AZ, May 1980. Federal Highway Administration, “Crumb Rubber Modifier Workshop Notes: Design

Procedures and Construction Practices,” FHWA-SA-93-011, 1993. Heitzman, M., “State of the Practice – Design and Construction of Asphalt Paving Materials with

Crumb Rubber Modifier,” FHWA-SA-92-202, Federal Highway Administration, May 1992.

Hicks, R.G., James R. Lundy, Rita B. Leahy, Doug Hanson, and Jon A. Epps, “Crumb Rubber

Modifiers (CRM) in Asphalt Pavements: Summary of Practices in Arizona, California and Florida,” FHWA-SA-95-056, Federal Highway Administration, September 1995.

Huddleston, Sam W., “Asphalt Rubber Binder Presentation,” Phoenix, AZ, 1999. Huddleston, Sam W., personal communication, March 2000. Hughes, C.S., Ronald Cominsky and E. Dakatz, “Quality Initiatives,” prepared for AAPT, 1999. LaGrone, B.D., “Rubber Used in Asphalt Rubber Applications,” Proceedings, National Seminar

on Asphalt Rubber, San Antonio, TX, October 1981.

36

Page 44: QUALITY CONTROL (QC) FOR

McDonald, C.H., “Recollections of Early Asphalt-Rubber History,” Proceedings, National Seminar on Asphalt-Rubber, San Antonio, TX, October 1981.

National Center for Asphalt Technology, “Construction Guidelines for Crumb Rubber Modified

Hot Mix Asphalt,” Contract No. DTFH61-94-C-0035, Federal Highway Administration, 1998.

Oliver, J.W.H., “Modification of Paving Asphalts by Digestion with Scrap Rubber,”

Transportation Research Record 821, Transportation Research Board, 1981. Schofield, Larry A., “The History, Development and Performance of Asphalt Rubber at ADOT,”

Report No. AZ-SP-8982, Arizona Department of Transportation, December 1999.

37

Page 45: QUALITY CONTROL (QC) FOR

APPENDIX A Interview Survey Forms for

RPA User and Producer Members

Page 46: QUALITY CONTROL (QC) FOR

8-20-99 INTERVIEW FORM

Quality AR Products – User Members

Company Interviewed ________________________ Phone ________________________

Name ____________________________________ Fax ________________________ E-Mail ____________________________________ Date ________________________ Purpose The purpose of this interview is to: 1) document the current procedures used by industry to control the quality of the asphalt

rubber binder, and

2) develop an industry standard to insure that the asphalt rubber binder properties are consistent from batch to batch and from contractor to contractor.

Questions 1) Asphalt Source

Asphalt source can impact the reaction between the asphalt and the crumb rubber. This question deals with the sampling of the neat asphalt to insure its properties are uniform and consistent.

a) Where do you sample the neat asphalt?

From asphalt supplier transport

From producer’s heated tank prior to blending with CRM

____________________________________

b) How often do you sample and test the asphalt?

Daily

Weekly

________________________

A-1

Page 47: QUALITY CONTROL (QC) FOR

c) What is the temperature of the asphalt used in AR production at the time of sampling?

____________°F Max ____________°F Mean ____________°F Min

d) What tests are used for quality control of the neat asphalt?

Viscosity @ _____________°F

Agency spec tests

________________________

e) How many sources of asphalt do you use in any construction season?

1

1-3

> 3

f) Are you able to use all asphalt sources to produce a quality AR product?

Yes

No If no, what sources do not work for AR? _____________________________________ ______________________________________________________________________ ______________________________________________________________________

A-2

Page 48: QUALITY CONTROL (QC) FOR

g) Do you use asphalt supplier test results in lieu of your own for QC?

Yes

No If yes,

What is the location of sampling? ____________________________________ •

What is the frequency of sampling? __________________________________

What tests are performed? __________________________________________

What is the timing and availability of test results? _______________________

h) Do you use public agency test results in lieu of your own for QA?

Yes

No If yes,

What is the location of sampling? ____________________________________

What is the frequency of sampling? __________________________________

What tests are performed? __________________________________________

What is the timing and availability of test results? _______________________

2) Crumb Rubber Modifier (CRM)

What is done by your organization to insure the CRM is uniform and consistent?

a) Where do you sample the CRM?

From the bag

From the hopper just prior to entering the blending unit

_________________________________________

A-3

Page 49: QUALITY CONTROL (QC) FOR

b) How often do you sample the CRM?

Daily

Weekly

________________________

c) Do you perform any QC tasks on the CRM?

Yes

No If yes, what tests are performed?

Gradation

Chemical analysis

Metal or fabric content

________________________

d) Do you use CRM supplier test results in lieu of your own for QC?

Yes

No If yes,

What is the location of sampling? ____________________________________ •

What is the frequency of sampling? __________________________________

What tests are performed? __________________________________________

What is the timing and availability of test results? _______________________

A-4

Page 50: QUALITY CONTROL (QC) FOR

e) Do you use public agency test results in lieu of your own for QA?

Yes

No If yes,

What is the location of sampling? ____________________________________ •

What is the frequency of sampling? __________________________________

What tests are performed? __________________________________________

What is the timing and availability of test results? _______________________

3) AR Binder Design

Asphalt rubber properties are primarily a function of the asphalt, the CRM, and the time and temperature of reaction. These questions are designed to determine the procedures used to insure the neat asphalt and CRM will produce an acceptable product.

a) Do you perform a binder design?

Yes

No If yes, who performs the design?

Contractor

Private laboratory

Public agency

________________________

A-5

Page 51: QUALITY CONTROL (QC) FOR

b) What procedures are employed to design the AR binder?

Experience

Laboratory testing protocol

________________________

c) What tests are used in the binder design?

Viscosity

Resilience

Softening point

Cone (or needle) penetration

DSR

________________________

d) How often do you perform a binder design?

Every project

Whenever the asphalt source is changed

________________________

e) Is the binder design performed by

accredited laboratory (type of certification = ______________________)

certified technician (type of certification = ______________________)

________________________

A-6

Page 52: QUALITY CONTROL (QC) FOR

f) Does the binder design require the addition of an additive (e.g., extender oil)?

Yes

No If yes, what are the typical percentages of each ingredient in the AR binder? _____________ Asphalt cement _____________ CRM _____________ Additive (e.g., ________________)

g) Does the binder design procedure used result in good field performance?

100% of the time

> 90% of the time

> 80% of the time

________________________

h) How do you correlate the binder lab properties with the binder performance you see in the field?

Annual field surveys

Occasional field survey

Response to problems only

________________________

A-7

Page 53: QUALITY CONTROL (QC) FOR

i) Is a new binder design test or procedure needed?

Yes

No If yes, what do you recommend? ___________________________________________ ______________________________________________________________________

4) AR Binder Information The time and temperature of reaction plus other factors determine the properties of the asphalt rubber. These questions are designed to determine the procedures used to control the AR production. a) Where do you sample the AR blend?

Blending tank

Hold tank (reaction vessel)

Feed line from holding tank and hot mix plant mixing chamber

________________________

b) When do you sample after rubber addition and when do you mix the AR binder with the aggregate?

Sample: Mix:

Average _____________ min. Average _____________ min. Range _____________ min. Range _____________ min.

c) What is the normal temperature of reaction and storage?

Average _________________°F Range _________________°F

A-8

Page 54: QUALITY CONTROL (QC) FOR

d) What is the normal frequency of QC sampling and testing used by your organization for quality control?

Per batch

Daily

Per job

________________________

e) What QC tests are performed on the AR binder?

viscosity @ _____°F ± ______°F

________________________

________________________

f) What QA tests are performed by the owner on the AR binder?

Viscosity

DSR

________________________

g) What is the frequency of the QA tests?

Daily

Per job

________________________

A-9

Page 55: QUALITY CONTROL (QC) FOR

h) Where are the QA samples taken?

Hold tank

________________________ i) Do you have statistical summaries showing variations in AR properties for recent jobs?

Yes

No If yes, please provide copies of this data.

5) Summary a) In your opinion, what factors are the most important to insure a quality AR binder?

(1 = most important, 5 = least important) 1 2 3 4 5 Asphalt source and grade __|______|______|______|______|__ CRM source and gradation __|______|______|______|______|__ CRM content __|______|______|______|______|__ Blending and agitation method/equipment __|______|______|______|______|__ Time/temperature of reaction __|______|______|______|______|__ Binder design __|______|______|______|______|__ Additives __|______|______|______|______|__

A-10

Page 56: QUALITY CONTROL (QC) FOR

b) As an experienced contractor, what other factors must be controlled to insure a quality hot mix product? (1 = most important, 5 = least important)

1 2 3 4 5 AR binder __|______|______|______|______|__ Aggregates __|______|______|______|______|__ Mix design __|______|______|______|______|__ Construction procedures __|______|______|______|______|__ Weather conditions during construction __|______|______|______|______|__ QC/QA __|______|______|______|______|__ Structural design (existing surface condition) __|______|______|______|______|__

c) What tests are routinely used to evaluate the properties of resulting AR mixtures?

Aggregate gradation

Binder content

Volumetrics (field mix–lab compacted)

Strength test

In-place air voids (field mix-field compacted)

d) Please provide (or send) a current specification for AR binders and AR mixes used in your operating area to

R.G. Hicks Professor Emeritus Department of Civil, Construction, and Environmental Engineering 202 Apperson Hall Oregon State University 97331-2302 Phone: 541-737-5318 Fax: 541-737-3052 Internet: R.G. [email protected]

A-11

Page 57: QUALITY CONTROL (QC) FOR

SURVEY FORM ON QUALITY CONTROL PROCEDURES

FOR RPA PRODUCER MEMBERS

1) What tests do you perform to control the quality of the crumb rubber?

Gradation

Moisture Content

Fiber Content

Metal Content

Chemical Composition

__________________________________________

__________________________________________

2) How frequently (e.g. per ton) do you perform each of the tests?

Test Frequency Gradation Moisture Content Fiber Content Metal Content Chemical Composition

3) Who performs the tests?

Tester Property In-House Other

Gradation Moisture Content Fiber Content Metals Content Chemical Composition

A-12

Page 58: QUALITY CONTROL (QC) FOR

4) What tests are run to establish chemical composition?

_____________________________________________

_____________________________________________

_____________________________________________

_____________________________________________

5) What reports are provided to AR producers and what is the frequency of the report?

Test Frequency Gradation Moisture Content

6) Do you think the current QC procedures assure a uniform and consistent product?

Yes No

If no, what other QC steps do you think are needed?

___________________________________________________________________________

___________________________________________________________________________

___________________________________________________________________________

___________________________________________________________________________

Please return by Feb 18, 2000 to:

R.G. Hicks Department of Civil, Construction, and Environmental Engineering

Oregon State University 202 Apperson Hall

Corvallis, OR 97331-2302 Fax: 541-737-3052

Phone: 541-737-5318 E-mail: [email protected]

A-13

Page 59: QUALITY CONTROL (QC) FOR

APPENDIX B List of Interviewees

Page 60: QUALITY CONTROL (QC) FOR

RPA USER MEMBERS

All States Asphalt Paul Montenegro 260 Doyle Ave. Providence, RI 02906 Phone: 401-351-9556 Fax: 508-7890-2545 Web: www.allstatesasphalt.com

Cox Paving Co., Inc. Sidney Cox Box 519 Blanco, TX 78606 Phone: 830-833-4547 Fax: 830-833-4136 MP: 512-658-9102

FNF Construction, Inc. Mark Belshe, A-R Manager 115 S 48th St Tempe, AZ 85281 Phone: 480-784-2910 Fax: 480-921-8720 E-Mail: [email protected] Web: www.fnfinc.com

Granite Construction, Inc. Mark Chalfa 38000 Monroe St Indio, CA 92203 Phone: 760-775-7500 Fax: 760-775-8229 E-Mail: [email protected] Web: www.graniteconstruction.com

International Surfacing Systems Andy Zappettini, VP 6751 W Galveston Chandler, AZ 85226 Phone: 480-268-0874 Fax: 480-961-0766 Web: www.slurry.com

Manhole Adjusting, Inc. Cliff Ashcroft, Marketing Manager 2300 Greenwood Ave Monterey Park, CA 91754 Phone: 323-725-1387 Fax: 323-725-7620 E-Mail: [email protected]

Meadow Valley Corporation Sam Grasmick P O Box 6072 Phoenix, AZ 85082-0726 Phone: 602-437-5400 Fax: 602-437-1681 E-Mail: [email protected] Web: www.meadowvalley.com

Silvia Construction, Inc. Wayne Silvia, President 9007 Center Ave Rancho Cucamonga, CA 91729 Phone: 909-949-1127 Fax: 909-481-8122

Western States Surfacing, Inc. Gregory Reed, President P O Box 4770 Modesto, CA 95352 Phone: 209-525-9065 Fax: 209-525-9062 E-Mail: [email protected] Web: www.chipseal.com

B-1

Page 61: QUALITY CONTROL (QC) FOR

RPA PRODUCER MEMBERS Atlos Rubber, Inc. 1522 Fishburn Ave Los Angeles, CA 90063 Phone: 323-266-4570 Fax: 323-267-4312 E-mail: [email protected]

BAS Recycling, Inc. 1400 North H St San Bernardino, CA 92405 Phone: 909-383-7050 Fax: 909-383-7055 E-mail: [email protected]

Bay Area Tire Recyling 2200 Sacramento St, Suite 1106 San Francisco, CA 94115-2309 Phone: 415-931-3381 Fax: 415-929-8123 E-Mail: [email protected]

CR3 of Indiana 2501 Mt Pleasant Blvd Muncie, IN 47302 Phone: 888-783-7859 Fax: 765-286-5404 E-mail: [email protected]

CRM Co., LLC 15800 S Avalon Blvd Rancho Dominguez, CA 90220 Phone: 760-396-9936 Fax: 310-538-2227 E-mail: [email protected]

First Nation Recovery, Inc. P O Box 297 Mecca, CA 92254 Phone: 760-396-9936 Fax: 760-396-0215 E-mail: [email protected]

Gibson Recycling, Inc. P O Box 1208 Atlanta, TX 75551 Phone: 903-796-8640 Fax: 903-796-0115

PolyTek Rubber & Recycling, Inc. 6245 N 24th Parkway, #202 Phoenix, AZ 85016 Phone: 602-840-2266 Fax: 602-840-8717 E-mail: [email protected] Web: www.polytekrubber.com

Recovery Technologies, Inc. KTI, Inc. 7000 Blvd East Guttenberg, NJ 07093 Phone: 201-854-7777 Fax: 201-854-1771 Web: www.recoverytechnologies.com

B-2

Page 62: QUALITY CONTROL (QC) FOR

RPA ASSOCIATE MEMBERS LAW Engineering & Environmental Svcs Sam Huddleston 4634 S 36th Place Phoenix, AZ 85040 Phone: 602-437-0250 Fax: 602-437-3675 E-Mail: [email protected]

Speedie & Associates Donald Cornelison, P.E. 11029 N 24th St #805 Phoenix, AZ 85029 Phone: 602-997-6391 Fax: 602-943-5508 E-Mail: [email protected]

Western Technologies, Inc. Phillip Feliz, Principal 3737 E Broadway Rd Phoenix, AZ 85040 Phone: 602-437-3737 Fax: 602-470-1341 E-Mail: [email protected]

B-3

Page 63: QUALITY CONTROL (QC) FOR

APPENDIX C Results of Interviews – User Members

Page 64: QUALITY CONTROL (QC) FOR

PREFACE

The survey form in Appendix A was sent to all AR producers. Responses were received

from all. The authors wish to acknowledge the cooperation received from the producers. Each

producer is encouraged to review the information produced for accuracy.

C-1

Page 65: QUALITY CONTROL (QC) FOR

Table C.1. QC/QA Procedures for Virgin Asphalt

Arizona California Others

Question FNF ISSMeadow Valley FNF Granite Silvia MAI WSS All States Cox Paving

a) Where do you sample the asphalt?

From transport truck

From transport truck

From transport truck

From transport truck

From transport truck

From transport truck

From transport truck

From producer’s heated tank

From producer’s heated tank

From transport truck and/or producer’s tank

b) How often do you • sample the asphalt? • test the asphalt?

Daily

As needed

Daily

Daily

Daily

As needed

Daily

Each load

Daily

Weekly

Weekly

Weekly

c) What is the asphalt temperature (°F) at time of sampling? • average • min • max

350 335 400

290 320

315 300 330

385 375 410

400 375 415

380 350 425

400 385 425

410 390 425

300 275 325

385 360 410

d) What tests are used for QC? None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

None, rely on certification

e) How many sources of asphalt do you use/season?

1-3 1-3 > 3 1-3 > 3 1-3 1 1 1-3 1-3

f) Are you able to use all sources?

No No Yes Yes Yes Yes Yes No Yes No

g) Do you use asphalt supplier test results in lieu of your own for QC?

Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

h) Do you use public agency test results in lieu of your own for QA?

Yes Yes, only if there are problems

Yes, only if there are problems

Yes Yes Yes Yes No No No

C-2

Page 66: QUALITY CONTROL (QC) FOR

Table C.2. QC/QA Procedures for Crumb Rubber Modifier

Arizona California Other

Question FNF ISSMeadow Valley FNF Granite Silvia MAI WSS All States Cox Paving

a) Where do you sample the CRM?

Do not sample normally

From the bag or hopper

Do not sample

Do not sample normally

Do not sample

From the bag or hopper

Do not sample normally

From the hopper

From the bag

From the hopper

b) How often do you sample the CRM?

As needed As needed or if a new supplier

Do not sample

As Needed Only if there is a problem

Every truck load

Only if there is a problem

Weekly When received

Daily

c) Do you perform any QC tests?

No Yes (gradation, metal, fabric moisture)

No No No No No No Yes, gradation

No

d) Do you use CRM supplier tests in lieu of your own for QC?

Yes, rely on certification

Yes, rely on certification

Yes, rely on certification

Yes Yes, rely on certification

Yes, rely on certification

Yes Yes Yes Yes

e) Do you use public agency test results in lieu of your own for QA?

Yes Yes, but varies greatly with agency

Yes Yes Yes Yes, and it has resulted in penalties

Yes No No No

C-3

Page 67: QUALITY CONTROL (QC) FOR

Table C.3a. Procedures Used to Design AR Binders and Relate AR Binder Properties to Performance (Arizona)

Producers Private Laboratories

Question FNF ISS Meadow Valley Law Engineering Western

Technologies Speedie & Associates

a) Do you perform a binder design? Yes, use private laboratory

Yes, use private laboratory

Yes, use private laboratory

Yes Yes Yes

b) What procedures are used? Experience and lab protocol

Experience and lab protocol

Experience and lab protocol

Experience and lab protocol

Experience Experience plus lab protocol

c) What tests are used in the binder design? • Viscosity • Resilience • Softening point • Cone (or needle) penetration • Other

X X X X

Ductility

X X X X

X X X X

X X X X

X X X X

X X X X

Ductility, retained penetration and resilience

d) How often is a binder design performed? Generally every project

Every project Every time there is a change in oil or CRM

Every project normally; the exception would be when one binder is used on small jobs within short time frame

Every project or whenever the asphalt or CRM source is cì¥Á�Y� �����¿����������

��ß\���bjbjóWóW������������������ ���`���‘=��‘=��ÍW������¸�����

C-4

Page 68: QUALITY CONTROL (QC) FOR
Page 69: QUALITY CONTROL (QC) FOR
Page 70: QUALITY CONTROL (QC) FOR
Page 71: QUALITY CONTROL (QC) FOR
Page 72: QUALITY CONTROL (QC) FOR
Page 73: QUALITY CONTROL (QC) FOR
Page 74: QUALITY CONTROL (QC) FOR
Page 75: QUALITY CONTROL (QC) FOR
Page 76: QUALITY CONTROL (QC) FOR
Page 77: QUALITY CONTROL (QC) FOR
Page 78: QUALITY CONTROL (QC) FOR
Page 79: QUALITY CONTROL (QC) FOR
Page 80: QUALITY CONTROL (QC) FOR
Page 81: QUALITY CONTROL (QC) FOR
Page 82: QUALITY CONTROL (QC) FOR
Page 83: QUALITY CONTROL (QC) FOR
Page 84: QUALITY CONTROL (QC) FOR
Page 85: QUALITY CONTROL (QC) FOR
Page 86: QUALITY CONTROL (QC) FOR
Page 87: QUALITY CONTROL (QC) FOR
Page 88: QUALITY CONTROL (QC) FOR
Page 89: QUALITY CONTROL (QC) FOR
Page 90: QUALITY CONTROL (QC) FOR
Page 91: QUALITY CONTROL (QC) FOR
Page 92: QUALITY CONTROL (QC) FOR
Page 93: QUALITY CONTROL (QC) FOR
Page 94: QUALITY CONTROL (QC) FOR
Page 95: QUALITY CONTROL (QC) FOR
Page 96: QUALITY CONTROL (QC) FOR
Page 97: QUALITY CONTROL (QC) FOR
Page 98: QUALITY CONTROL (QC) FOR
Page 99: QUALITY CONTROL (QC) FOR
Page 100: QUALITY CONTROL (QC) FOR
Page 101: QUALITY CONTROL (QC) FOR
Page 102: QUALITY CONTROL (QC) FOR
Page 103: QUALITY CONTROL (QC) FOR
Page 104: QUALITY CONTROL (QC) FOR
Page 105: QUALITY CONTROL (QC) FOR
Page 106: QUALITY CONTROL (QC) FOR
Page 107: QUALITY CONTROL (QC) FOR
Page 108: QUALITY CONTROL (QC) FOR
Page 109: QUALITY CONTROL (QC) FOR
Page 110: QUALITY CONTROL (QC) FOR
Page 111: QUALITY CONTROL (QC) FOR
Page 112: QUALITY CONTROL (QC) FOR
Page 113: QUALITY CONTROL (QC) FOR
Page 114: QUALITY CONTROL (QC) FOR
Page 115: QUALITY CONTROL (QC) FOR
Page 116: QUALITY CONTROL (QC) FOR
Page 117: QUALITY CONTROL (QC) FOR
Page 118: QUALITY CONTROL (QC) FOR
Page 119: QUALITY CONTROL (QC) FOR
Page 120: QUALITY CONTROL (QC) FOR
Page 121: QUALITY CONTROL (QC) FOR
Page 122: QUALITY CONTROL (QC) FOR
Page 123: QUALITY CONTROL (QC) FOR
Page 124: QUALITY CONTROL (QC) FOR
Page 125: QUALITY CONTROL (QC) FOR
Page 126: QUALITY CONTROL (QC) FOR
Page 127: QUALITY CONTROL (QC) FOR
Page 128: QUALITY CONTROL (QC) FOR
Page 129: QUALITY CONTROL (QC) FOR
Page 130: QUALITY CONTROL (QC) FOR
Page 131: QUALITY CONTROL (QC) FOR
Page 132: QUALITY CONTROL (QC) FOR

Table C.3b. Procedures Used to Design AR Binders and Relate AR Binder Properties to Performance (Other Agencies)

C-5

Page 133: QUALITY CONTROL (QC) FOR
Page 134: QUALITY CONTROL (QC) FOR
Page 135: QUALITY CONTROL (QC) FOR
Page 136: QUALITY CONTROL (QC) FOR
Page 137: QUALITY CONTROL (QC) FOR
Page 138: QUALITY CONTROL (QC) FOR
Page 139: QUALITY CONTROL (QC) FOR
Page 140: QUALITY CONTROL (QC) FOR
Page 141: QUALITY CONTROL (QC) FOR
Page 142: QUALITY CONTROL (QC) FOR
Page 143: QUALITY CONTROL (QC) FOR
Page 144: QUALITY CONTROL (QC) FOR
Page 145: QUALITY CONTROL (QC) FOR
Page 146: QUALITY CONTROL (QC) FOR
Page 147: QUALITY CONTROL (QC) FOR
Page 148: QUALITY CONTROL (QC) FOR
Page 149: QUALITY CONTROL (QC) FOR
Page 150: QUALITY CONTROL (QC) FOR
Page 151: QUALITY CONTROL (QC) FOR
Page 152: QUALITY CONTROL (QC) FOR
Page 153: QUALITY CONTROL (QC) FOR
Page 154: QUALITY CONTROL (QC) FOR
Page 155: QUALITY CONTROL (QC) FOR
Page 156: QUALITY CONTROL (QC) FOR
Page 157: QUALITY CONTROL (QC) FOR
Page 158: QUALITY CONTROL (QC) FOR
Page 159: QUALITY CONTROL (QC) FOR
Page 160: QUALITY CONTROL (QC) FOR
Page 161: QUALITY CONTROL (QC) FOR
Page 162: QUALITY CONTROL (QC) FOR
Page 163: QUALITY CONTROL (QC) FOR
Page 164: QUALITY CONTROL (QC) FOR
Page 165: QUALITY CONTROL (QC) FOR
Page 166: QUALITY CONTROL (QC) FOR
Page 167: QUALITY CONTROL (QC) FOR
Page 168: QUALITY CONTROL (QC) FOR
Page 169: QUALITY CONTROL (QC) FOR
Page 170: QUALITY CONTROL (QC) FOR
Page 171: QUALITY CONTROL (QC) FOR
Page 172: QUALITY CONTROL (QC) FOR
Page 173: QUALITY CONTROL (QC) FOR
Page 174: QUALITY CONTROL (QC) FOR
Page 175: QUALITY CONTROL (QC) FOR
Page 176: QUALITY CONTROL (QC) FOR
Page 177: QUALITY CONTROL (QC) FOR
Page 178: QUALITY CONTROL (QC) FOR
Page 179: QUALITY CONTROL (QC) FOR
Page 180: QUALITY CONTROL (QC) FOR
Page 181: QUALITY CONTROL (QC) FOR
Page 182: QUALITY CONTROL (QC) FOR
Page 183: QUALITY CONTROL (QC) FOR
Page 184: QUALITY CONTROL (QC) FOR
Page 185: QUALITY CONTROL (QC) FOR
Page 186: QUALITY CONTROL (QC) FOR
Page 187: QUALITY CONTROL (QC) FOR
Page 188: QUALITY CONTROL (QC) FOR
Page 189: QUALITY CONTROL (QC) FOR
Page 190: QUALITY CONTROL (QC) FOR
Page 191: QUALITY CONTROL (QC) FOR
Page 192: QUALITY CONTROL (QC) FOR
Page 193: QUALITY CONTROL (QC) FOR
Page 194: QUALITY CONTROL (QC) FOR
Page 195: QUALITY CONTROL (QC) FOR
Page 196: QUALITY CONTROL (QC) FOR
Page 197: QUALITY CONTROL (QC) FOR
Page 198: QUALITY CONTROL (QC) FOR
Page 199: QUALITY CONTROL (QC) FOR
Page 200: QUALITY CONTROL (QC) FOR
Page 201: QUALITY CONTROL (QC) FOR
Page 202: QUALITY CONTROL (QC) FOR
Page 203: QUALITY CONTROL (QC) FOR
Page 204: QUALITY CONTROL (QC) FOR
Page 205: QUALITY CONTROL (QC) FOR
Page 206: QUALITY CONTROL (QC) FOR
Page 207: QUALITY CONTROL (QC) FOR
Page 208: QUALITY CONTROL (QC) FOR
Page 209: QUALITY CONTROL (QC) FOR
Page 210: QUALITY CONTROL (QC) FOR
Page 211: QUALITY CONTROL (QC) FOR
Page 212: QUALITY CONTROL (QC) FOR
Page 213: QUALITY CONTROL (QC) FOR
Page 214: QUALITY CONTROL (QC) FOR
Page 215: QUALITY CONTROL (QC) FOR
Page 216: QUALITY CONTROL (QC) FOR
Page 217: QUALITY CONTROL (QC) FOR
Page 218: QUALITY CONTROL (QC) FOR
Page 219: QUALITY CONTROL (QC) FOR
Page 220: QUALITY CONTROL (QC) FOR
Page 221: QUALITY CONTROL (QC) FOR
Page 222: QUALITY CONTROL (QC) FOR
Page 223: QUALITY CONTROL (QC) FOR
Page 224: QUALITY CONTROL (QC) FOR
Page 225: QUALITY CONTROL (QC) FOR
Page 226: QUALITY CONTROL (QC) FOR
Page 227: QUALITY CONTROL (QC) FOR
Page 228: QUALITY CONTROL (QC) FOR
Page 229: QUALITY CONTROL (QC) FOR
Page 230: QUALITY CONTROL (QC) FOR
Page 231: QUALITY CONTROL (QC) FOR
Page 232: QUALITY CONTROL (QC) FOR
Page 233: QUALITY CONTROL (QC) FOR
Page 234: QUALITY CONTROL (QC) FOR
Page 235: QUALITY CONTROL (QC) FOR
Page 236: QUALITY CONTROL (QC) FOR
Page 237: QUALITY CONTROL (QC) FOR
Page 238: QUALITY CONTROL (QC) FOR
Page 239: QUALITY CONTROL (QC) FOR
Page 240: QUALITY CONTROL (QC) FOR
Page 241: QUALITY CONTROL (QC) FOR
Page 242: QUALITY CONTROL (QC) FOR
Page 243: QUALITY CONTROL (QC) FOR
Page 244: QUALITY CONTROL (QC) FOR
Page 245: QUALITY CONTROL (QC) FOR
Page 246: QUALITY CONTROL (QC) FOR
Page 247: QUALITY CONTROL (QC) FOR
Page 248: QUALITY CONTROL (QC) FOR
Page 249: QUALITY CONTROL (QC) FOR
Page 250: QUALITY CONTROL (QC) FOR
Page 251: QUALITY CONTROL (QC) FOR
Page 252: QUALITY CONTROL (QC) FOR
Page 253: QUALITY CONTROL (QC) FOR
Page 254: QUALITY CONTROL (QC) FOR
Page 255: QUALITY CONTROL (QC) FOR
Page 256: QUALITY CONTROL (QC) FOR
Page 257: QUALITY CONTROL (QC) FOR
Page 258: QUALITY CONTROL (QC) FOR
Page 259: QUALITY CONTROL (QC) FOR
Page 260: QUALITY CONTROL (QC) FOR
Page 261: QUALITY CONTROL (QC) FOR
Page 262: QUALITY CONTROL (QC) FOR
Page 263: QUALITY CONTROL (QC) FOR
Page 264: QUALITY CONTROL (QC) FOR
Page 265: QUALITY CONTROL (QC) FOR
Page 266: QUALITY CONTROL (QC) FOR
Page 267: QUALITY CONTROL (QC) FOR
Page 268: QUALITY CONTROL (QC) FOR
Page 269: QUALITY CONTROL (QC) FOR
Page 270: QUALITY CONTROL (QC) FOR
Page 271: QUALITY CONTROL (QC) FOR
Page 272: QUALITY CONTROL (QC) FOR
Page 273: QUALITY CONTROL (QC) FOR
Page 274: QUALITY CONTROL (QC) FOR

Table C.4. QC/QA Procedures Used in Production of AR Binders

C-6

Page 275: QUALITY CONTROL (QC) FOR
Page 276: QUALITY CONTROL (QC) FOR
Page 277: QUALITY CONTROL (QC) FOR
Page 278: QUALITY CONTROL (QC) FOR
Page 279: QUALITY CONTROL (QC) FOR
Page 280: QUALITY CONTROL (QC) FOR
Page 281: QUALITY CONTROL (QC) FOR
Page 282: QUALITY CONTROL (QC) FOR
Page 283: QUALITY CONTROL (QC) FOR
Page 284: QUALITY CONTROL (QC) FOR
Page 285: QUALITY CONTROL (QC) FOR
Page 286: QUALITY CONTROL (QC) FOR
Page 287: QUALITY CONTROL (QC) FOR
Page 288: QUALITY CONTROL (QC) FOR
Page 289: QUALITY CONTROL (QC) FOR
Page 290: QUALITY CONTROL (QC) FOR
Page 291: QUALITY CONTROL (QC) FOR
Page 292: QUALITY CONTROL (QC) FOR
Page 293: QUALITY CONTROL (QC) FOR
Page 294: QUALITY CONTROL (QC) FOR
Page 295: QUALITY CONTROL (QC) FOR
Page 296: QUALITY CONTROL (QC) FOR
Page 297: QUALITY CONTROL (QC) FOR
Page 298: QUALITY CONTROL (QC) FOR
Page 299: QUALITY CONTROL (QC) FOR
Page 300: QUALITY CONTROL (QC) FOR
Page 301: QUALITY CONTROL (QC) FOR
Page 302: QUALITY CONTROL (QC) FOR
Page 303: QUALITY CONTROL (QC) FOR
Page 304: QUALITY CONTROL (QC) FOR
Page 305: QUALITY CONTROL (QC) FOR
Page 306: QUALITY CONTROL (QC) FOR
Page 307: QUALITY CONTROL (QC) FOR
Page 308: QUALITY CONTROL (QC) FOR
Page 309: QUALITY CONTROL (QC) FOR
Page 310: QUALITY CONTROL (QC) FOR
Page 311: QUALITY CONTROL (QC) FOR
Page 312: QUALITY CONTROL (QC) FOR
Page 313: QUALITY CONTROL (QC) FOR
Page 314: QUALITY CONTROL (QC) FOR
Page 315: QUALITY CONTROL (QC) FOR
Page 316: QUALITY CONTROL (QC) FOR
Page 317: QUALITY CONTROL (QC) FOR
Page 318: QUALITY CONTROL (QC) FOR
Page 319: QUALITY CONTROL (QC) FOR
Page 320: QUALITY CONTROL (QC) FOR
Page 321: QUALITY CONTROL (QC) FOR
Page 322: QUALITY CONTROL (QC) FOR
Page 323: QUALITY CONTROL (QC) FOR
Page 324: QUALITY CONTROL (QC) FOR
Page 325: QUALITY CONTROL (QC) FOR
Page 326: QUALITY CONTROL (QC) FOR
Page 327: QUALITY CONTROL (QC) FOR
Page 328: QUALITY CONTROL (QC) FOR
Page 329: QUALITY CONTROL (QC) FOR
Page 330: QUALITY CONTROL (QC) FOR
Page 331: QUALITY CONTROL (QC) FOR
Page 332: QUALITY CONTROL (QC) FOR
Page 333: QUALITY CONTROL (QC) FOR
Page 334: QUALITY CONTROL (QC) FOR
Page 335: QUALITY CONTROL (QC) FOR
Page 336: QUALITY CONTROL (QC) FOR
Page 337: QUALITY CONTROL (QC) FOR
Page 338: QUALITY CONTROL (QC) FOR
Page 339: QUALITY CONTROL (QC) FOR
Page 340: QUALITY CONTROL (QC) FOR
Page 341: QUALITY CONTROL (QC) FOR
Page 342: QUALITY CONTROL (QC) FOR
Page 343: QUALITY CONTROL (QC) FOR
Page 344: QUALITY CONTROL (QC) FOR
Page 345: QUALITY CONTROL (QC) FOR
Page 346: QUALITY CONTROL (QC) FOR
Page 347: QUALITY CONTROL (QC) FOR
Page 348: QUALITY CONTROL (QC) FOR
Page 349: QUALITY CONTROL (QC) FOR
Page 350: QUALITY CONTROL (QC) FOR
Page 351: QUALITY CONTROL (QC) FOR
Page 352: QUALITY CONTROL (QC) FOR
Page 353: QUALITY CONTROL (QC) FOR
Page 354: QUALITY CONTROL (QC) FOR
Page 355: QUALITY CONTROL (QC) FOR
Page 356: QUALITY CONTROL (QC) FOR
Page 357: QUALITY CONTROL (QC) FOR
Page 358: QUALITY CONTROL (QC) FOR
Page 359: QUALITY CONTROL (QC) FOR
Page 360: QUALITY CONTROL (QC) FOR
Page 361: QUALITY CONTROL (QC) FOR
Page 362: QUALITY CONTROL (QC) FOR
Page 363: QUALITY CONTROL (QC) FOR
Page 364: QUALITY CONTROL (QC) FOR
Page 365: QUALITY CONTROL (QC) FOR
Page 366: QUALITY CONTROL (QC) FOR
Page 367: QUALITY CONTROL (QC) FOR
Page 368: QUALITY CONTROL (QC) FOR
Page 369: QUALITY CONTROL (QC) FOR
Page 370: QUALITY CONTROL (QC) FOR
Page 371: QUALITY CONTROL (QC) FOR
Page 372: QUALITY CONTROL (QC) FOR
Page 373: QUALITY CONTROL (QC) FOR
Page 374: QUALITY CONTROL (QC) FOR
Page 375: QUALITY CONTROL (QC) FOR
Page 376: QUALITY CONTROL (QC) FOR
Page 377: QUALITY CONTROL (QC) FOR
Page 378: QUALITY CONTROL (QC) FOR
Page 379: QUALITY CONTROL (QC) FOR
Page 380: QUALITY CONTROL (QC) FOR
Page 381: QUALITY CONTROL (QC) FOR
Page 382: QUALITY CONTROL (QC) FOR
Page 383: QUALITY CONTROL (QC) FOR
Page 384: QUALITY CONTROL (QC) FOR
Page 385: QUALITY CONTROL (QC) FOR
Page 386: QUALITY CONTROL (QC) FOR
Page 387: QUALITY CONTROL (QC) FOR
Page 388: QUALITY CONTROL (QC) FOR
Page 389: QUALITY CONTROL (QC) FOR
Page 390: QUALITY CONTROL (QC) FOR
Page 391: QUALITY CONTROL (QC) FOR
Page 392: QUALITY CONTROL (QC) FOR
Page 393: QUALITY CONTROL (QC) FOR
Page 394: QUALITY CONTROL (QC) FOR
Page 395: QUALITY CONTROL (QC) FOR
Page 396: QUALITY CONTROL (QC) FOR
Page 397: QUALITY CONTROL (QC) FOR
Page 398: QUALITY CONTROL (QC) FOR
Page 399: QUALITY CONTROL (QC) FOR
Page 400: QUALITY CONTROL (QC) FOR
Page 401: QUALITY CONTROL (QC) FOR
Page 402: QUALITY CONTROL (QC) FOR
Page 403: QUALITY CONTROL (QC) FOR
Page 404: QUALITY CONTROL (QC) FOR
Page 405: QUALITY CONTROL (QC) FOR
Page 406: QUALITY CONTROL (QC) FOR
Page 407: QUALITY CONTROL (QC) FOR
Page 408: QUALITY CONTROL (QC) FOR
Page 409: QUALITY CONTROL (QC) FOR
Page 410: QUALITY CONTROL (QC) FOR
Page 411: QUALITY CONTROL (QC) FOR
Page 412: QUALITY CONTROL (QC) FOR
Page 413: QUALITY CONTROL (QC) FOR
Page 414: QUALITY CONTROL (QC) FOR
Page 415: QUALITY CONTROL (QC) FOR
Page 416: QUALITY CONTROL (QC) FOR
Page 417: QUALITY CONTROL (QC) FOR
Page 418: QUALITY CONTROL (QC) FOR
Page 419: QUALITY CONTROL (QC) FOR
Page 420: QUALITY CONTROL (QC) FOR
Page 421: QUALITY CONTROL (QC) FOR
Page 422: QUALITY CONTROL (QC) FOR
Page 423: QUALITY CONTROL (QC) FOR
Page 424: QUALITY CONTROL (QC) FOR
Page 425: QUALITY CONTROL (QC) FOR
Page 426: QUALITY CONTROL (QC) FOR
Page 427: QUALITY CONTROL (QC) FOR
Page 428: QUALITY CONTROL (QC) FOR
Page 429: QUALITY CONTROL (QC) FOR
Page 430: QUALITY CONTROL (QC) FOR
Page 431: QUALITY CONTROL (QC) FOR
Page 432: QUALITY CONTROL (QC) FOR
Page 433: QUALITY CONTROL (QC) FOR
Page 434: QUALITY CONTROL (QC) FOR
Page 435: QUALITY CONTROL (QC) FOR
Page 436: QUALITY CONTROL (QC) FOR
Page 437: QUALITY CONTROL (QC) FOR
Page 438: QUALITY CONTROL (QC) FOR
Page 439: QUALITY CONTROL (QC) FOR
Page 440: QUALITY CONTROL (QC) FOR
Page 441: QUALITY CONTROL (QC) FOR
Page 442: QUALITY CONTROL (QC) FOR
Page 443: QUALITY CONTROL (QC) FOR
Page 444: QUALITY CONTROL (QC) FOR
Page 445: QUALITY CONTROL (QC) FOR
Page 446: QUALITY CONTROL (QC) FOR
Page 447: QUALITY CONTROL (QC) FOR
Page 448: QUALITY CONTROL (QC) FOR
Page 449: QUALITY CONTROL (QC) FOR
Page 450: QUALITY CONTROL (QC) FOR
Page 451: QUALITY CONTROL (QC) FOR
Page 452: QUALITY CONTROL (QC) FOR
Page 453: QUALITY CONTROL (QC) FOR
Page 454: QUALITY CONTROL (QC) FOR
Page 455: QUALITY CONTROL (QC) FOR
Page 456: QUALITY CONTROL (QC) FOR
Page 457: QUALITY CONTROL (QC) FOR

Table C.5. Ranking of Important Factors – AR Binders and Mixes

C-7

Page 458: QUALITY CONTROL (QC) FOR
Page 459: QUALITY CONTROL (QC) FOR
Page 460: QUALITY CONTROL (QC) FOR
Page 461: QUALITY CONTROL (QC) FOR
Page 462: QUALITY CONTROL (QC) FOR
Page 463: QUALITY CONTROL (QC) FOR
Page 464: QUALITY CONTROL (QC) FOR
Page 465: QUALITY CONTROL (QC) FOR
Page 466: QUALITY CONTROL (QC) FOR
Page 467: QUALITY CONTROL (QC) FOR
Page 468: QUALITY CONTROL (QC) FOR
Page 469: QUALITY CONTROL (QC) FOR
Page 470: QUALITY CONTROL (QC) FOR
Page 471: QUALITY CONTROL (QC) FOR
Page 472: QUALITY CONTROL (QC) FOR
Page 473: QUALITY CONTROL (QC) FOR
Page 474: QUALITY CONTROL (QC) FOR
Page 475: QUALITY CONTROL (QC) FOR
Page 476: QUALITY CONTROL (QC) FOR
Page 477: QUALITY CONTROL (QC) FOR
Page 478: QUALITY CONTROL (QC) FOR
Page 479: QUALITY CONTROL (QC) FOR
Page 480: QUALITY CONTROL (QC) FOR
Page 481: QUALITY CONTROL (QC) FOR
Page 482: QUALITY CONTROL (QC) FOR
Page 483: QUALITY CONTROL (QC) FOR
Page 484: QUALITY CONTROL (QC) FOR
Page 485: QUALITY CONTROL (QC) FOR
Page 486: QUALITY CONTROL (QC) FOR
Page 487: QUALITY CONTROL (QC) FOR
Page 488: QUALITY CONTROL (QC) FOR
Page 489: QUALITY CONTROL (QC) FOR
Page 490: QUALITY CONTROL (QC) FOR
Page 491: QUALITY CONTROL (QC) FOR
Page 492: QUALITY CONTROL (QC) FOR
Page 493: QUALITY CONTROL (QC) FOR
Page 494: QUALITY CONTROL (QC) FOR
Page 495: QUALITY CONTROL (QC) FOR
Page 496: QUALITY CONTROL (QC) FOR
Page 497: QUALITY CONTROL (QC) FOR
Page 498: QUALITY CONTROL (QC) FOR
Page 499: QUALITY CONTROL (QC) FOR
Page 500: QUALITY CONTROL (QC) FOR
Page 501: QUALITY CONTROL (QC) FOR
Page 502: QUALITY CONTROL (QC) FOR
Page 503: QUALITY CONTROL (QC) FOR
Page 504: QUALITY CONTROL (QC) FOR
Page 505: QUALITY CONTROL (QC) FOR
Page 506: QUALITY CONTROL (QC) FOR
Page 507: QUALITY CONTROL (QC) FOR
Page 508: QUALITY CONTROL (QC) FOR
Page 509: QUALITY CONTROL (QC) FOR
Page 510: QUALITY CONTROL (QC) FOR
Page 511: QUALITY CONTROL (QC) FOR
Page 512: QUALITY CONTROL (QC) FOR
Page 513: QUALITY CONTROL (QC) FOR
Page 514: QUALITY CONTROL (QC) FOR
Page 515: QUALITY CONTROL (QC) FOR
Page 516: QUALITY CONTROL (QC) FOR
Page 517: QUALITY CONTROL (QC) FOR
Page 518: QUALITY CONTROL (QC) FOR
Page 519: QUALITY CONTROL (QC) FOR
Page 520: QUALITY CONTROL (QC) FOR
Page 521: QUALITY CONTROL (QC) FOR
Page 522: QUALITY CONTROL (QC) FOR
Page 523: QUALITY CONTROL (QC) FOR
Page 524: QUALITY CONTROL (QC) FOR
Page 525: QUALITY CONTROL (QC) FOR
Page 526: QUALITY CONTROL (QC) FOR
Page 527: QUALITY CONTROL (QC) FOR
Page 528: QUALITY CONTROL (QC) FOR
Page 529: QUALITY CONTROL (QC) FOR
Page 530: QUALITY CONTROL (QC) FOR
Page 531: QUALITY CONTROL (QC) FOR
Page 532: QUALITY CONTROL (QC) FOR
Page 533: QUALITY CONTROL (QC) FOR
Page 534: QUALITY CONTROL (QC) FOR
Page 535: QUALITY CONTROL (QC) FOR
Page 536: QUALITY CONTROL (QC) FOR
Page 537: QUALITY CONTROL (QC) FOR
Page 538: QUALITY CONTROL (QC) FOR
Page 539: QUALITY CONTROL (QC) FOR
Page 540: QUALITY CONTROL (QC) FOR
Page 541: QUALITY CONTROL (QC) FOR
Page 542: QUALITY CONTROL (QC) FOR
Page 543: QUALITY CONTROL (QC) FOR
Page 544: QUALITY CONTROL (QC) FOR
Page 545: QUALITY CONTROL (QC) FOR
Page 546: QUALITY CONTROL (QC) FOR
Page 547: QUALITY CONTROL (QC) FOR
Page 548: QUALITY CONTROL (QC) FOR
Page 549: QUALITY CONTROL (QC) FOR
Page 550: QUALITY CONTROL (QC) FOR
Page 551: QUALITY CONTROL (QC) FOR
Page 552: QUALITY CONTROL (QC) FOR
Page 553: QUALITY CONTROL (QC) FOR
Page 554: QUALITY CONTROL (QC) FOR
Page 555: QUALITY CONTROL (QC) FOR
Page 556: QUALITY CONTROL (QC) FOR
Page 557: QUALITY CONTROL (QC) FOR
Page 558: QUALITY CONTROL (QC) FOR
Page 559: QUALITY CONTROL (QC) FOR
Page 560: QUALITY CONTROL (QC) FOR
Page 561: QUALITY CONTROL (QC) FOR
Page 562: QUALITY CONTROL (QC) FOR
Page 563: QUALITY CONTROL (QC) FOR
Page 564: QUALITY CONTROL (QC) FOR
Page 565: QUALITY CONTROL (QC) FOR
Page 566: QUALITY CONTROL (QC) FOR
Page 567: QUALITY CONTROL (QC) FOR
Page 568: QUALITY CONTROL (QC) FOR
Page 569: QUALITY CONTROL (QC) FOR
Page 570: QUALITY CONTROL (QC) FOR
Page 571: QUALITY CONTROL (QC) FOR
Page 572: QUALITY CONTROL (QC) FOR
Page 573: QUALITY CONTROL (QC) FOR
Page 574: QUALITY CONTROL (QC) FOR
Page 575: QUALITY CONTROL (QC) FOR
Page 576: QUALITY CONTROL (QC) FOR
Page 577: QUALITY CONTROL (QC) FOR
Page 578: QUALITY CONTROL (QC) FOR
Page 579: QUALITY CONTROL (QC) FOR
Page 580: QUALITY CONTROL (QC) FOR
Page 581: QUALITY CONTROL (QC) FOR
Page 582: QUALITY CONTROL (QC) FOR
Page 583: QUALITY CONTROL (QC) FOR
Page 584: QUALITY CONTROL (QC) FOR
Page 585: QUALITY CONTROL (QC) FOR
Page 586: QUALITY CONTROL (QC) FOR
Page 587: QUALITY CONTROL (QC) FOR
Page 588: QUALITY CONTROL (QC) FOR
Page 589: QUALITY CONTROL (QC) FOR
Page 590: QUALITY CONTROL (QC) FOR
Page 591: QUALITY CONTROL (QC) FOR
Page 592: QUALITY CONTROL (QC) FOR
Page 593: QUALITY CONTROL (QC) FOR
Page 594: QUALITY CONTROL (QC) FOR
Page 595: QUALITY CONTROL (QC) FOR
Page 596: QUALITY CONTROL (QC) FOR
Page 597: QUALITY CONTROL (QC) FOR
Page 598: QUALITY CONTROL (QC) FOR
Page 599: QUALITY CONTROL (QC) FOR
Page 600: QUALITY CONTROL (QC) FOR
Page 601: QUALITY CONTROL (QC) FOR
Page 602: QUALITY CONTROL (QC) FOR
Page 603: QUALITY CONTROL (QC) FOR
Page 604: QUALITY CONTROL (QC) FOR
Page 605: QUALITY CONTROL (QC) FOR
Page 606: QUALITY CONTROL (QC) FOR
Page 607: QUALITY CONTROL (QC) FOR
Page 608: QUALITY CONTROL (QC) FOR
Page 609: QUALITY CONTROL (QC) FOR
Page 610: QUALITY CONTROL (QC) FOR
Page 611: QUALITY CONTROL (QC) FOR
Page 612: QUALITY CONTROL (QC) FOR
Page 613: QUALITY CONTROL (QC) FOR
Page 614: QUALITY CONTROL (QC) FOR
Page 615: QUALITY CONTROL (QC) FOR
Page 616: QUALITY CONTROL (QC) FOR
Page 617: QUALITY CONTROL (QC) FOR
Page 618: QUALITY CONTROL (QC) FOR
Page 619: QUALITY CONTROL (QC) FOR
Page 620: QUALITY CONTROL (QC) FOR
Page 621: QUALITY CONTROL (QC) FOR
Page 622: QUALITY CONTROL (QC) FOR
Page 623: QUALITY CONTROL (QC) FOR
Page 624: QUALITY CONTROL (QC) FOR
Page 625: QUALITY CONTROL (QC) FOR
Page 626: QUALITY CONTROL (QC) FOR
Page 627: QUALITY CONTROL (QC) FOR
Page 628: QUALITY CONTROL (QC) FOR
Page 629: QUALITY CONTROL (QC) FOR
Page 630: QUALITY CONTROL (QC) FOR
Page 631: QUALITY CONTROL (QC) FOR
Page 632: QUALITY CONTROL (QC) FOR
Page 633: QUALITY CONTROL (QC) FOR
Page 634: QUALITY CONTROL (QC) FOR
Page 635: QUALITY CONTROL (QC) FOR
Page 636: QUALITY CONTROL (QC) FOR
Page 637: QUALITY CONTROL (QC) FOR
Page 638: QUALITY CONTROL (QC) FOR
Page 639: QUALITY CONTROL (QC) FOR
Page 640: QUALITY CONTROL (QC) FOR
Page 641: QUALITY CONTROL (QC) FOR
Page 642: QUALITY CONTROL (QC) FOR
Page 643: QUALITY CONTROL (QC) FOR
Page 644: QUALITY CONTROL (QC) FOR
Page 645: QUALITY CONTROL (QC) FOR
Page 646: QUALITY CONTROL (QC) FOR
Page 647: QUALITY CONTROL (QC) FOR
Page 648: QUALITY CONTROL (QC) FOR
Page 649: QUALITY CONTROL (QC) FOR
Page 650: QUALITY CONTROL (QC) FOR
Page 651: QUALITY CONTROL (QC) FOR
Page 652: QUALITY CONTROL (QC) FOR
Page 653: QUALITY CONTROL (QC) FOR
Page 654: QUALITY CONTROL (QC) FOR
Page 655: QUALITY CONTROL (QC) FOR
Page 656: QUALITY CONTROL (QC) FOR
Page 657: QUALITY CONTROL (QC) FOR
Page 658: QUALITY CONTROL (QC) FOR
Page 659: QUALITY CONTROL (QC) FOR
Page 660: QUALITY CONTROL (QC) FOR
Page 661: QUALITY CONTROL (QC) FOR
Page 662: QUALITY CONTROL (QC) FOR
Page 663: QUALITY CONTROL (QC) FOR
Page 664: QUALITY CONTROL (QC) FOR
Page 665: QUALITY CONTROL (QC) FOR
Page 666: QUALITY CONTROL (QC) FOR
Page 667: QUALITY CONTROL (QC) FOR
Page 668: QUALITY CONTROL (QC) FOR
Page 669: QUALITY CONTROL (QC) FOR
Page 670: QUALITY CONTROL (QC) FOR
Page 671: QUALITY CONTROL (QC) FOR
Page 672: QUALITY CONTROL (QC) FOR
Page 673: QUALITY CONTROL (QC) FOR
Page 674: QUALITY CONTROL (QC) FOR
Page 675: QUALITY CONTROL (QC) FOR
Page 676: QUALITY CONTROL (QC) FOR
Page 677: QUALITY CONTROL (QC) FOR
Page 678: QUALITY CONTROL (QC) FOR
Page 679: QUALITY CONTROL (QC) FOR
Page 680: QUALITY CONTROL (QC) FOR
Page 681: QUALITY CONTROL (QC) FOR
Page 682: QUALITY CONTROL (QC) FOR
Page 683: QUALITY CONTROL (QC) FOR
Page 684: QUALITY CONTROL (QC) FOR
Page 685: QUALITY CONTROL (QC) FOR
Page 686: QUALITY CONTROL (QC) FOR
Page 687: QUALITY CONTROL (QC) FOR
Page 688: QUALITY CONTROL (QC) FOR
Page 689: QUALITY CONTROL (QC) FOR
Page 690: QUALITY CONTROL (QC) FOR
Page 691: QUALITY CONTROL (QC) FOR
Page 692: QUALITY CONTROL (QC) FOR
Page 693: QUALITY CONTROL (QC) FOR
Page 694: QUALITY CONTROL (QC) FOR
Page 695: QUALITY CONTROL (QC) FOR
Page 696: QUALITY CONTROL (QC) FOR
Page 697: QUALITY CONTROL (QC) FOR
Page 698: QUALITY CONTROL (QC) FOR
Page 699: QUALITY CONTROL (QC) FOR
Page 700: QUALITY CONTROL (QC) FOR
Page 701: QUALITY CONTROL (QC) FOR
Page 702: QUALITY CONTROL (QC) FOR
Page 703: QUALITY CONTROL (QC) FOR
Page 704: QUALITY CONTROL (QC) FOR
Page 705: QUALITY CONTROL (QC) FOR
Page 706: QUALITY CONTROL (QC) FOR
Page 707: QUALITY CONTROL (QC) FOR
Page 708: QUALITY CONTROL (QC) FOR
Page 709: QUALITY CONTROL (QC) FOR
Page 710: QUALITY CONTROL (QC) FOR
Page 711: QUALITY CONTROL (QC) FOR
Page 712: QUALITY CONTROL (QC) FOR
Page 713: QUALITY CONTROL (QC) FOR
Page 714: QUALITY CONTROL (QC) FOR
Page 715: QUALITY CONTROL (QC) FOR
Page 716: QUALITY CONTROL (QC) FOR
Page 717: QUALITY CONTROL (QC) FOR
Page 718: QUALITY CONTROL (QC) FOR
Page 719: QUALITY CONTROL (QC) FOR
Page 720: QUALITY CONTROL (QC) FOR
Page 721: QUALITY CONTROL (QC) FOR
Page 722: QUALITY CONTROL (QC) FOR
Page 723: QUALITY CONTROL (QC) FOR
Page 724: QUALITY CONTROL (QC) FOR
Page 725: QUALITY CONTROL (QC) FOR
Page 726: QUALITY CONTROL (QC) FOR
Page 727: QUALITY CONTROL (QC) FOR
Page 728: QUALITY CONTROL (QC) FOR
Page 729: QUALITY CONTROL (QC) FOR
Page 730: QUALITY CONTROL (QC) FOR
Page 731: QUALITY CONTROL (QC) FOR
Page 732: QUALITY CONTROL (QC) FOR
Page 733: QUALITY CONTROL (QC) FOR
Page 734: QUALITY CONTROL (QC) FOR
Page 735: QUALITY CONTROL (QC) FOR
Page 736: QUALITY CONTROL (QC) FOR
Page 737: QUALITY CONTROL (QC) FOR
Page 738: QUALITY CONTROL (QC) FOR
Page 739: QUALITY CONTROL (QC) FOR
Page 740: QUALITY CONTROL (QC) FOR
Page 741: QUALITY CONTROL (QC) FOR
Page 742: QUALITY CONTROL (QC) FOR
Page 743: QUALITY CONTROL (QC) FOR

APPENDIX D Results of Survey – Producer Members

Page 744: QUALITY CONTROL (QC) FOR

D-1

PREFACE

The survey form in Appendix D was sent to all CRM producers. Responses received are

included in this appendix. It is unfortunate that not all producers contributed information to this

report. Each producer who provided information is encouraged to check it for accuracy.

Page 745: QUALITY CONTROL (QC) FOR

D-2

1) What tests do you perform to control the quality of the crumb rubber?

Page 746: QUALITY CONTROL (QC) FOR

D-3

Page 747: QUALITY CONTROL (QC) FOR

D-4

Page 748: QUALITY CONTROL (QC) FOR

D-5

Page 749: QUALITY CONTROL (QC) FOR

D-6

Page 750: QUALITY CONTROL (QC) FOR

D-7

Page 751: QUALITY CONTROL (QC) FOR

D-8

Page 752: QUALITY CONTROL (QC) FOR

D-9

Page 753: QUALITY CONTROL (QC) FOR

D-10

Page 754: QUALITY CONTROL (QC) FOR

D-11

Page 755: QUALITY CONTROL (QC) FOR

D-12

Page 756: QUALITY CONTROL (QC) FOR

D-13

Page 757: QUALITY CONTROL (QC) FOR

D-14

Page 758: QUALITY CONTROL (QC) FOR

D-15

Page 759: QUALITY CONTROL (QC) FOR

D-16

Page 760: QUALITY CONTROL (QC) FOR

D-17

Page 761: QUALITY CONTROL (QC) FOR

D-18

Page 762: QUALITY CONTROL (QC) FOR

D-19

Page 763: QUALITY CONTROL (QC) FOR

D-20

Page 764: QUALITY CONTROL (QC) FOR

D-21

Page 765: QUALITY CONTROL (QC) FOR

D-22

Page 766: QUALITY CONTROL (QC) FOR

D-23

Page 767: QUALITY CONTROL (QC) FOR

D-24

Page 768: QUALITY CONTROL (QC) FOR

D-25

Page 769: QUALITY CONTROL (QC) FOR

D-26

Page 770: QUALITY CONTROL (QC) FOR

D-27

Page 771: QUALITY CONTROL (QC) FOR

D-28

Page 772: QUALITY CONTROL (QC) FOR

D-29

Page 773: QUALITY CONTROL (QC) FOR

D-30

Page 774: QUALITY CONTROL (QC) FOR

D-31

Page 775: QUALITY CONTROL (QC) FOR

D-32

Page 776: QUALITY CONTROL (QC) FOR

D-33

Page 777: QUALITY CONTROL (QC) FOR

D-34

2) How frequently are the tests performed?

Page 778: QUALITY CONTROL (QC) FOR

D-35

Page 779: QUALITY CONTROL (QC) FOR

D-36

Page 780: QUALITY CONTROL (QC) FOR

D-37

Page 781: QUALITY CONTROL (QC) FOR

D-38

Page 782: QUALITY CONTROL (QC) FOR

D-39

Page 783: QUALITY CONTROL (QC) FOR

D-40

Page 784: QUALITY CONTROL (QC) FOR

D-41

Page 785: QUALITY CONTROL (QC) FOR

D-42

Page 786: QUALITY CONTROL (QC) FOR

D-43

Page 787: QUALITY CONTROL (QC) FOR

D-44

Page 788: QUALITY CONTROL (QC) FOR

D-45

Page 789: QUALITY CONTROL (QC) FOR

D-46

Page 790: QUALITY CONTROL (QC) FOR

D-47

Page 791: QUALITY CONTROL (QC) FOR

D-48

Page 792: QUALITY CONTROL (QC) FOR

D-49

Page 793: QUALITY CONTROL (QC) FOR

D-50

Page 794: QUALITY CONTROL (QC) FOR

D-51

Page 795: QUALITY CONTROL (QC) FOR

D-52

Page 796: QUALITY CONTROL (QC) FOR

D-53

Page 797: QUALITY CONTROL (QC) FOR

D-54

Page 798: QUALITY CONTROL (QC) FOR

D-55

Page 799: QUALITY CONTROL (QC) FOR

D-56

Page 800: QUALITY CONTROL (QC) FOR

D-57

Page 801: QUALITY CONTROL (QC) FOR

D-58

Page 802: QUALITY CONTROL (QC) FOR

D-59

Page 803: QUALITY CONTROL (QC) FOR

D-60

Page 804: QUALITY CONTROL (QC) FOR

D-61

Page 805: QUALITY CONTROL (QC) FOR

D-62

Page 806: QUALITY CONTROL (QC) FOR

D-63

Page 807: QUALITY CONTROL (QC) FOR

D-64

Page 808: QUALITY CONTROL (QC) FOR

D-65

3) Who performs the tests?

Page 809: QUALITY CONTROL (QC) FOR

D-66

Page 810: QUALITY CONTROL (QC) FOR

D-67

Page 811: QUALITY CONTROL (QC) FOR

D-68

Page 812: QUALITY CONTROL (QC) FOR

D-69

Page 813: QUALITY CONTROL (QC) FOR

D-70

Page 814: QUALITY CONTROL (QC) FOR

D-71

Page 815: QUALITY CONTROL (QC) FOR

D-72

Page 816: QUALITY CONTROL (QC) FOR

D-73

Page 817: QUALITY CONTROL (QC) FOR

D-74

Page 818: QUALITY CONTROL (QC) FOR

D-75

Page 819: QUALITY CONTROL (QC) FOR

D-76

Page 820: QUALITY CONTROL (QC) FOR

D-77

Page 821: QUALITY CONTROL (QC) FOR

D-78

Page 822: QUALITY CONTROL (QC) FOR

D-79

Page 823: QUALITY CONTROL (QC) FOR

D-80

Page 824: QUALITY CONTROL (QC) FOR

D-81

Page 825: QUALITY CONTROL (QC) FOR

D-82

Page 826: QUALITY CONTROL (QC) FOR

D-83

Page 827: QUALITY CONTROL (QC) FOR

D-84

Page 828: QUALITY CONTROL (QC) FOR

D-85

Page 829: QUALITY CONTROL (QC) FOR

D-86

Page 830: QUALITY CONTROL (QC) FOR

D-87

Page 831: QUALITY CONTROL (QC) FOR

D-88

Page 832: QUALITY CONTROL (QC) FOR

D-89

Page 833: QUALITY CONTROL (QC) FOR

D-90

Page 834: QUALITY CONTROL (QC) FOR

D-91

Page 835: QUALITY CONTROL (QC) FOR

D-92

Page 836: QUALITY CONTROL (QC) FOR

D-93

Page 837: QUALITY CONTROL (QC) FOR

D-94

Page 838: QUALITY CONTROL (QC) FOR

D-95

Page 839: QUALITY CONTROL (QC) FOR

D-96

Page 840: QUALITY CONTROL (QC) FOR

D-97

4) What tests are run to establish chemical composition?

Page 841: QUALITY CONTROL (QC) FOR

D-98

Page 842: QUALITY CONTROL (QC) FOR

D-99

Page 843: QUALITY CONTROL (QC) FOR

D-100

Page 844: QUALITY CONTROL (QC) FOR

D-101

Page 845: QUALITY CONTROL (QC) FOR

D-102

Page 846: QUALITY CONTROL (QC) FOR

D-103

Page 847: QUALITY CONTROL (QC) FOR

D-104

Page 848: QUALITY CONTROL (QC) FOR

D-105

Page 849: QUALITY CONTROL (QC) FOR

D-106

Page 850: QUALITY CONTROL (QC) FOR

D-107

Page 851: QUALITY CONTROL (QC) FOR

D-108

Page 852: QUALITY CONTROL (QC) FOR

D-109

Page 853: QUALITY CONTROL (QC) FOR

D-110

Page 854: QUALITY CONTROL (QC) FOR

D-111

Page 855: QUALITY CONTROL (QC) FOR

D-112

Page 856: QUALITY CONTROL (QC) FOR

D-113

Page 857: QUALITY CONTROL (QC) FOR

D-114

Page 858: QUALITY CONTROL (QC) FOR

D-115

Page 859: QUALITY CONTROL (QC) FOR

D-116

Page 860: QUALITY CONTROL (QC) FOR

D-117

Page 861: QUALITY CONTROL (QC) FOR

D-118

Page 862: QUALITY CONTROL (QC) FOR

D-119

Page 863: QUALITY CONTROL (QC) FOR

D-120

Page 864: QUALITY CONTROL (QC) FOR

D-121

Page 865: QUALITY CONTROL (QC) FOR

D-122

Page 866: QUALITY CONTROL (QC) FOR

D-123

Page 867: QUALITY CONTROL (QC) FOR

D-124

Page 868: QUALITY CONTROL (QC) FOR

D-125

Page 869: QUALITY CONTROL (QC) FOR

D-126

Page 870: QUALITY CONTROL (QC) FOR

D-127

Page 871: QUALITY CONTROL (QC) FOR

D-128

5) What reports are provided to AR users and what are the frequency of the reports?

Page 872: QUALITY CONTROL (QC) FOR

D-129

Page 873: QUALITY CONTROL (QC) FOR

D-130

Page 874: QUALITY CONTROL (QC) FOR

D-131

Page 875: QUALITY CONTROL (QC) FOR

D-132

Page 876: QUALITY CONTROL (QC) FOR

D-133

Page 877: QUALITY CONTROL (QC) FOR

D-134

Page 878: QUALITY CONTROL (QC) FOR

D-135

Page 879: QUALITY CONTROL (QC) FOR

D-136

Page 880: QUALITY CONTROL (QC) FOR

D-137

Page 881: QUALITY CONTROL (QC) FOR

D-138

Page 882: QUALITY CONTROL (QC) FOR

D-139

Page 883: QUALITY CONTROL (QC) FOR

D-140

Page 884: QUALITY CONTROL (QC) FOR

D-141

Page 885: QUALITY CONTROL (QC) FOR

D-142

Page 886: QUALITY CONTROL (QC) FOR

D-143

Page 887: QUALITY CONTROL (QC) FOR

D-144

Page 888: QUALITY CONTROL (QC) FOR

D-145

Page 889: QUALITY CONTROL (QC) FOR

D-146

Page 890: QUALITY CONTROL (QC) FOR

D-147

Page 891: QUALITY CONTROL (QC) FOR

D-148

Page 892: QUALITY CONTROL (QC) FOR

D-149

Page 893: QUALITY CONTROL (QC) FOR

D-150

Page 894: QUALITY CONTROL (QC) FOR

D-151

Page 895: QUALITY CONTROL (QC) FOR

D-152

Page 896: QUALITY CONTROL (QC) FOR

D-153

Page 897: QUALITY CONTROL (QC) FOR

D-154

Page 898: QUALITY CONTROL (QC) FOR

D-155

Page 899: QUALITY CONTROL (QC) FOR

D-156

Page 900: QUALITY CONTROL (QC) FOR

D-157

Page 901: QUALITY CONTROL (QC) FOR

D-158

Page 902: QUALITY CONTROL (QC) FOR

D-159

6) Do you believe the current QC procedures assure a uniform and consistent product? Atlos Yes BAS Yes PolyTek Yes