QUARTERLY REPORTFor the Third Quarter of the Year 2014
Period : July 2014 to September 2014
PT.PERENTJANAOJAJAin subconsultancy with e Yongma Engineering Co. Ltd and i'PT. EpadasconPer~ata Engineering ConsultantCTCOffice: JI.Ciniru VII No. 25, Kebayoran Baru, Jakarta Selatan, 12180
Phone /Fax: (021) 7229823
Direktur Jenderal Bina MargaInspektorat Jenderal, Kementrian PUDirektur Transportasi - BappenasDirektur Pengelolaan Kas Negara (PKN), Kementrian KeuanganDirektur Bina Program, DitJen Bina MargaDirektur Bina Teknik, Dit.Jen Bina MargaDirektur Bina PelaksanaanWilayah I, DJBMBiro Perencanaan & KLN, Kementrian PUKasubdit Kawasan Strategis dan Andalan, Kementrian Dalam NegeriKasubdit Pembiayaan dan Kerjasama Luar Negeri, Dit. Bipran, DJBMKasubdit Wilayah I B, Direktorat Bina PelaksanaWilayah I, DJBMKasubditWilayah I C, Direktorat Bina PelaksanaWilayah I, DJBMKasubdit Wilayah I 0, Direktorat Bina PelaksanaWilayah I, DJBMKepala SNVT Pembinaan Administrasi dan Pelaksanaan Pengendalian PHLNTheWorld Bank Task Team LeaderPT. Perentjana DjajaYongma Engineering Co, LtdPT. Epadascon Permata Engineering ConsultantFile
Cc:1.2.3.4.5.6.7.8.9.10.11.12.13.14.15.16.17.18.19.
Should you have any comment or additional information that need to be incorporated in the Report, pleasefeel free to get in touch with us.
This report is reproduced and submitted in twenty (20) copies for distribution to all concerned authorities.
In compliance with Item No.3 (List of Documents To Be Delivered) of our Consultancy Contract, we submitherewith the Quarterly Progress Report covering the 3rd Quarter of the Year 2014 (July, August, andSeptember).
: Quarterly Progress Report for the 3rdQuarter of the Year 2014Subject
: Ir. Agusta E. Sinulingga, M.TOfficer in Charge PMUWINRIP
Attention
Directorate General of Highways, MPWJI. Patimura 20 Kebayoran BaruJakarta SelatanIndonesia
Jakarta, October 7, 2014: 03_1OICTAlO/Q-3.2014No
MINISTRY OF PUBLIC WORKSDIRECTORATE GENERAL OF HIGHWAYS
DIRECTORATE OF PLANNINGCore Team Consultant for
Western Indonesia National Roads Improvement Project (WIN RIP)IBRD Loan No. 8043-ID
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 1
1 Executive Summary
1.1 Current Implementation Situation
1.1.1 Civil Works
Implementation of the WINRIP Project is scheduled to be implemented intothree (3) Annual Work Programs (AWP’s).
AWP-1 original implementation begun with the pre-construction activities(procurement) in mid 2011 and the actual work implementation started in mid2012.
AWP-2 consist of three (3) implementation stages. The 1st stage is thepreparation of Tender Documents (construction drawings, bid documents,special specs and other related documents) by Design Supervision Consultant(DSC) and Project Preparation Consultant (PPC), 2nd stage is the procurementof Works (Prequalifications, Post Qualifications and Tendering) either thruInternational Competitive Bidding or National Competitive Bidding and the 3rd
stage is the actual implementation of the Works. AWP-2 was originallyscheduled to start in mid 2013 and to be implemented at the beginning of Year2014.
AWP-3 implementation stages are of the same sequence with that of AWP-2.The only difference is that AWP-3 is originally scheduled to take-off beginningthe 1st month of the Year 2013 and to be implemented in the 1st month of theYear 2015.
But to due some unavoidable circumstances, the original schedules incurreddelays. Actual implementation status are shown in Table 1.
Table 1
AWP No. ofPackages
Implementation Statusas of September 30, 2014
AWP-1 4 4 Nos. Under construction
AWP-2 9
1 No. Bids submitted and opened. Bid Evaluation Report (BER) on-goingpreparation.
2 Nos. Currently under tendering period until Oct. 3, 20141 No. BID preparation (Post Qualification) NCB4 Nos. DED under final review prior to submission to World Bank for NOL1 No. Replacement road, still to be determined.
AWP-3 81 No. Bid Evaluation Report (BER) completed. Final review by DGH.2 Nos. BID preparation (Post Qualification)ICB and NCB4 Nos. DED1 Nos. Replacement roads, still to be determined
TOTAL 21
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 2
For contract packages under AWP-2 and AWP-3 which have a combined totalof 17 sub-projects (Packages), a consolidated updated status ending on the3rd Quarter of the Year 2014 are presented in Table 2.
1.1.2 Consultancy Services
TA Consultant PlannedMobilization
ContractSigned
ActualMobilization
CTC Jul 2012 5 Nov 2012 12 Nov 2012
DSC Jul 2012 11 Jun 2013 19 Jun 2013
Capacity Building forDisaster Risks Reduction
Still to beprocured
Capacity Building forEnvironmental Management
Still to beprocured
Capacity Building for RoadSafety
Still to beprocured
1.1.3 Goods
At the end of this reporting quarter, no goods were procured.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 3
Table 2
Brief Summary as of the 3rd Quarter of Year 2014
DEDTechnical
DesignReview
Road SafetyAudit
Status Doc Requirement Status Doc Requirement StatusBudget
AllocationStatus
Est'd.Start
Duration(Months)
1 Krui - Bha Completed Completed CompletedSPPL & AMDAL
(No.1 & 17)
SPPL OK P2JN 2010 &AMDAL Subdit TLKJOK 2012 . WB NOL
issues on 20 Nov 2013
1.LARAP2.Lap.Mon LARAP
1.NOL WB 4 Jan 132.NOL WB
Satker PJNProp 98% Completed Jan-14 21.00 A
Padang Saw ah - Sp. Ampat
Including Air Gadang Bridge
3 Manggopoh - Padang Saw ah Completed Completed Completed SPPLOK P2JN 2010.(No
need NOL WB forSPPL/UKL&UPL)
1.LARAP 2.Monit.LARAP Report
1.NOL WB 13 Dec 122.Pending
compensationpayment for theremaining 3 PAP
APBD Propinsi 99% Completed Jan-14 24.00 A
4 Ipuh - Bantal Completed Completed Completed SPPL & UKL&UPL
SPPL OK P2JN 2010 &UKL/UPL presentationon Balai III on 27 Aug
14.
1.LARAP 2.Monit.LARAP Report
1.NOL WB 10 Dec 122.Completed
Satker PJNPropinsi
100% Completed Jan-14 24.00 A
5 Sp. Rampa - Poriaha Completed Completed Completed UKL/UPLOK Balai 1 2011. (No
need NOL WB forSPPL/UKL&UPL)
1.SLARAP2.LARAP monit
Report
1.Nol WB 10 Dec 122.relocation 1 kioskaffected project w ill
be done paralelconstruction
Satker PJNPropinsi
NotApplicable.
No LoudAcquisition
Bids opened onSept. 22, 2014
Des-14 18.00 I
6 Ps. Pedati - Kerkap Completed Completed Completed UKL/UPLOK TLKJ 2011. NOLWB issued on 20 Nov
2013
1.SLARAP2.LARAP monit
Report
1.NOL WB 20 Nov2013
2. Target of LarapImplementation is Sep
2014
Satker PJNPropinsi
Compensation paymentin process
Not Yet Started Dec-14 15.00 J
7 Indrapura - Tapan Completed Completed Completed AMDALOK TLKJ , 20 Feb
2014. NOL WB issueson 8 Aug 2014
SLARAP Target Sept 2014 APBD PropinsiTarget Mon:
Oct 2014 Not Yet Started Jan-15 21.00 G
8 Bts. Kota Pariaman - Manggopoh Completed Completed Completed AMDALOK TLKJ 2013 . NOL
WB issued on 14 April2014
LARAP NOL WB Aug 12 2014 APBD PropinsiTarget Mon:
Oct 2014 Not Yet Started Feb-15 24.00 G
9 Rantau Tijang - Kota Agung UKL/UPLOK TLKJ 2011. NOLWB issued on 20 Nov
2013LARAP
Being prepared byConsultant
recuirement (Balai 3)
Satker PJNPropinsi Not Yet Started Jun-15 21.00 L
10 Sp. Empat - Sp. Air Balam Completed Completed Completed AMDALOK TLKJ 2013 . NOL
WB issued on 14 April2014
LARAP NOL WB Aug 12 2014 APBD Propinsi Target Mon:Oct 2014
Not Yet Started Feb-14 24.00 G
11 Bantal - Mukomuko Completed Completed Completed AMDALOK TLKJ 2014. NOLWB issues on 8 Aug
2014
1.LARAP2.LARAP monit
Report
1.Nol WB :20 Nov2013
2.Target Sep 2014
Satker PJNPropinsi 10% On Going Dec-14 24.00 I
12 Kambang - Indrapura Completed Completed Completed AMDALOK TLKJ 2014 .NOLWB issues on 8 Aug
2014SLARAP Target Sep 2014 APBD Propinsi Staking Out Not Yet Started Feb-15 24.00 G
13 Sp. Rukis - Tj.Kemuning Completed Completed Completed UKL/UPLOK P2JN 2011. (No
need NOL WB forSPPL/UKL&UPL)
1.LARAP2.LARAP monit
Report
1.NOL WB:20 Nov2013
2.Target Dec 2014
Satker PJNPropinsi
Compensation paymentin process
On Going Dec-14 24.00 I
14 Painan - Kambang On Going AMDALOK TLKJ 2014 .NOLWB issues on 8 Aug
2014SLARAP
Consultantrecuirement (Balai 2) APBD Propinsi Staking Out Not Yet Started Mar-15 21.00 B
15 Sibolga - Bts.Tap Sel Completed Completed Completed UKL/UPLOK Balai 1 2011. (No
need NOL WB forSPPL/UKL&UPL)
1.LARAP2.LARAP monit
Report
1.NOL WB:5Feb 20142.Target Dec 2014
Satker PJNPropinsi Inventory Not Yet Started Feb-15 30.00 J
Seblat - Ipuh including
Air Lalang & Air Guntung Bridge
18 Mukomuko - Bts.Sumbar UKL/UPLOK TLKJ 2011. (No
need NOL WB forSPPL/UKL&UPL)
SLARAPBeing prepared by
Consultantrecuirement (Balai 3)
Satker PJNPropinsi Not Yet Started May -15 18.00 L
19 Lais - Bintuan Completed Completed Completed UKL/UPLOK TLKJ 2011.(Noneed NOL WB forSPPL/UKL&UPL)
1.LARAP2.LARAP monit
Report
1.Nol WB :20 Nov2013
2.Target August 2014
Satker PJNPropinsi
Compensation paymentin process
Not Yet Started Dec-14 10.00 J
20 Lubuk Alung - Sicincin On Going UKL/UPLOK TLKJ 2011.(Noneed NOL WB forSPPL/UKL&UPL)
SLARAPRevision byConsultant
recuirement (Balai 2)
Satker PJNPropinsi Staking Out Not Yet Started Feb-15 18.00 B
21 Lubuk Alung - Kurajati On Going UKL/UPLOK TLKJ 2011. (No
need NOL WB forSPPL/UKL&UPL)
SLARAPRevision byConsultant
recuirement (Balai 2)
Satker PJNPropinsi Staking Out Not Yet Started Feb-15 18.00 B
Remarks :A On going Construction = 3 Packages in 1 study AMDAL (West Sumatera Prov ince)B Detailed Engineering Design Under Preparation by DSC
C Technical Design Rev iew by CTC = 2 Packages in 1 study AMDAL (Bengkulu Prov ince)D Under Rev iew by Directorate of Technical AffairsE Final Detailed Engineering Design by DSCF Under Review by BALAIG Design revision by BALAI II (Padang) in line w ith Internal memo (Nota Dinas) No.130/ND/BL/2014 dated September 19, 2014H World Bank review for issuance of NOLI Currently on Tendering stageJ Under Bid PreparationK Bid Evaluation Report (BER) f inalized by POKJAL Propose to be replaced
Completed
21.00Mar-15Not Yet StartedStaking OutSatker PJNPropinsi
Satker PJNPropinsi
OK TLKJ 2014 . NOLWB issues on 8 Aug
2014On Going AMDAL
Completed AMDAL (No.1&17)
1.NOL WB: 20 Nov2014
2.Target Dec 2014
1.LARAP2.LARAP monit
Report
K
C
AWP-3Inventory
Bids opened onAugust. 15, 2014
Oct-14 24.00OK TLKJ 2011. NOLWB issued on 20 Nov
2013
1.LARAP2.LARAP monit
Report
1.NOL WB: 16 Sep2014
2.Target Dec 2014
16 On Going On Going
17 Sp.Gunung Kemala - Pg.Tampak Completed
AWP-2
Remarks
ContractImplementation Plan
Loan Package Name
2 Completed Completed CompletedSPPL&UKL/ UPL
Bridge
OK P2JN 2010 (Noneed NOL WB forSPPL/UKL&UPL)
Environmental Social Land Acquisition
24.00 A
Group Pack.No.
ProcurementStatus
AWP-1
1.LARAP 2.Monit.LARAP Report
1.NOL WB 13 Dec 122.Pending
Compensation for theremaining 21 PAP and
24 new PAP
APBD Propinsi 80% Completed Jan-14
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 4
1.2 Current Status of Loan
At the end of this quarter ( September 2014) some USD 6.681 million of theUSD 112.37 million forcasted expenditures representing 2.67 % of theavailable loan had been disbursed. Disbursement is considerably behindschedule by 42.28% of the forecast expenditures, while 44.28% of the timehas already elapsed with the main reason for the delay being the long periodwaiting for the implementation of the remaining civil works contracts andslow progress of the four (4) on going construction packages.
Total disbursements during this Quarter amounted to USD 0.691 millionrepresenting the payments for “Statement of Work Accomplished’ (MC) tocivil works Contractor and CTC and DSC Invoices. Details of theDisbursements and Expenditures Status are presented in Appendix 1.
A more detailed and updated status of the loan are fully described andpresented in the Seventh (7th) Quarterly Financial Report covering the 3rd
Quarter (July, August, September) of the Year 2014 which will be submittedseparately.
1.3 Current Problems and Action Required
Program Activity Responsibility
AWP-1
4 Nos. Under construction stage.Staking out and repair and restoration ofdeteriorated existing pavements, roadwayexcavation, embankment formation, spreadingof granular pavement for roadway widening,structural works, construction of stone masonryside ditches, stockpiling of raw material,production of crush aggregates and other minorworks.
ContractorDSCCivil Works ProjectManager
AWP-2 & AWP-3
2 Nos. Bid Evaluation Report (BER) forsubmission to World Bank.
2 Nos. Bids to be opened on October 3, 2014.3 Nos. Bids preparation (Post Qualification)
NCB and ICB4 Nos. Detailed design under final revision by
BALAI II4 Nos. On-going detailed engineering design2 Nos. Proposed replacement roads still
subject to economic evaluation
Procurement committeeCivil Works Project Manager
Sub Directorate ofEnvironment & Road Safety,DTA - DGHDSC
Capacity Buildingfor Disaster RisksReduction
Terms of Reference
On-going preparation
Sub-Directorate ofEnvironment & Road Safety -DTA - DGH
Capacity Buildingfor EnvironmentalManagement
Terms of Reference
On-going preparation
Sub-Directorate ofEnvironment & Road Safety,DTA - DGH
Capacity Buildingfor Road Safety
Terms of Reference
On-going preparation
Sub-Directorate ofEnvironment & Road Safety,DTA - DGH
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 5
2 General
2.1 Reporting Requirements
Quarterly Progress Reports: This is the Third (3rd) Quarterly Progress Reportas required and stipulated in CTC’s consultancy contract and the Loan Agreement.Prior to the production of this report, Monthly Progress Reports have beenprepared and have dealt with all aspects of the works. This report attempts tobring the situation up to date by covering overall progress up to the end ofThird (3rd) Quarter of the Year 2014.
Financial Monitoring Reports: These have been prepared for each quartersince the beginning of 2013 with the first Report, issued in May 2013,covering the period January – March 2013. Since that date quarterly reportshave been prepared and submitted regularly.
Report Period Covered Date IssuedFinancial Monitoring Report No. 1 January 2013 – March 2013 15 May 2013Financial Monitoring Report No. 2 April 2013 – June 2013 15 August 2013Financial Monitoring Report No. 3 July 2013 – September 2013 15 November 2013Financial Monitoring Report No. 4 October 2013 – December 2013 15 February 2014Financial Monitoring Report No. 5 January 2014 – March 2014 15 May 2014Financial Monitoring Report No. 6 April 2014 – June 2014 15 August 2014Financial Monitoring Report No. 6 July 2014 – September 2014 Under Preparation
CTC Monthly Progress Reports: These report have been prepared coveringeach full month since January 2013. Subsequent reports have been submittedon a regular monthly basis.
2.2 Loan StatusThe agreed allocation of loan funds from the original loan agreement togetherwith the % disbursed to the end of the quarter date (September 30, 2014) ispresented in Table 3
Table 3
Category Description Loan RestructuringAmount US$
Total Disbursementfor the 3rd Quarter
PreviousDisbursement
Total Disbursed byWB to End September
2014 in US$% Disbursed
1 Part 1
Betterment and CapacityExpansion of National Roads.
220,400,000.00 417,693.83 4,029,275.62 4,446,969.45 2.02
2 Part 2
Implementation Support
16,000,000.00 273,082.70 1,574,976.48 1,848,059.18 11.55
3 Part 3
Road Sector InstitutionalDevelopment
1,000,000.00 0,00 0 0 0
4 Part 4
Contingency for Disaster RiskResponse
0 0 0 0
Unallocated 12,600,000.00 0,00 0 0 0
LN 8043 DA-A(Ending Balance SA) 386,275.82 386,275.82 0
Original LoanAmount 250,000,000.00 690,776,53 5,990,527.92 6,681,304.45 2.67
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 6
1.454.35 4.35
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Month
% C
ompl
ete
Actual Expenditure USD6.68 mil (2.67 %)
WINRIP ACTUAL PROGRESS UP TO SEPTEMBER 2014 AND FORECAST UP TO DECEMBER 2017
ACTUAL September 2014
Forecast September 2014Forecast Expenditure USD
112.37 mil (44.95%)
Deviation = 42.28%
2.3 Financial Management
S-Curve for Financial Progress
A report at the end of the quarter (September 30, 2014) is presented in Appendix 2
2.4 Project Cost Monitoring
A detailed summary of the project cost monitoring in tabular format is presentedas Appendix 3 at the end of this report
2.5 Bank Mission
There was no World Bank review mission and site visit during this quarter.However, a regular monthly meetings were held to update the “Agreed Key Actionsand Plans” that were taken up during the last Bank Mission on April 28 – May 19,2014.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 7
Shown in Table 4 are the update “Agreed Key Action and Plans”.
Table 4
Status as of September 2014No. Action By Whom Status and Target dates
1 Project reviews DGH andBank October 2014
2 ToR for Capacity Enhancement onDisaster Risk Mitigation
PMU andCTC /
TLKJ is reviewing the new draft TOR and willsend it to Bank in early October 2014.
TLKJ will prepare and submit to the Bank therequest for manifestation of interest by earlyOctober 2014.
TLKJ will also prepare and submit to the Bankthe request for proposals by the end of October2014.
3 Complete and send to the BankUKL & UPL for package 4 CTC
Under process environmental permit from theBupati Muko-muko.
The environmental permit of UKL/UPL Package4 will be submitted to Bank on first week ofOctober 2014.
4Submit LARAP documents forpackages 7, 8, 10 and 12 for Bankreview
DGH 8, 10 - NOL given on August 12, 2014. 7, 12 submitted on September 29.
5 Submit to the Bank the LARAPmonitoring report for package 2 PMU Will be submitted in Oct. 2014.
6Submit to the Bank the LARAPmonitoring reports for packages 6,11 and 19
PMU Will be submitted in Oct. 2014.
7Submit to the Bank the LARAPmonitoring report for packages 13and 15
PMU Will be submitted in November 2014.
8Submit to the Bank the LARAP forpackages 14, 20 and 21 PMU Will be submitted in October 2014.
9 Submit to the Bank the LARAPmonitoring report for package 17 PMU Will be submitted on Oct. 2014.
10Finalize NCB standard biddingdocument (SBD) for full e-procurement
MPW(Bintek,PMU,Pusdata, andBapekon)and Bank
The Bank cannot agree on three final requestsby Bapekon. Bapekon staff will seek theagreement of their Director to desist from theserequests by October 7, 2014. If no agreementcan be reached in the week of October 6, theBank will have to ask the director general ofDGH/Bappenas for assistance to avoid furtherdelays in project implementation.
As soon as the NCB standard bidding documentis approved, DGH can move ahead with thebidding process of packages 6 and 9 withouthaving to submit the specific documents to theBank for no-objection since these are subject toprior review (however, we are pleased to have alook at the technical aspects of these documentsto make sure they are consistent).
11 Bidding of Package 17 PMU
Bid opening took place on August 15, 2014. Sixbidders submitted their bids.
Submit the BER in the week of October 6.Please note that the Bank needs to receive allBERs within one month of bid opening sincenew rules in terms of bid security extension willmake it much harder for the Bank to accept bidsecurity extension requests.
12 Bidding of package 5 PMU
Bid Opening Record forwarded to Bank onSeptember 23, 2014.
Bid Evaluation Report for the Bank’s prior reviewby October 23.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 8
13 Bidding of packages 11 and 13 PMU
NOL to the bidding document of the twopackages issued on August 6, 2014. DGHreceived a complained related to the PQ.
The invitation to bid was issued August 14, 2014. The PMU will send to the Bank by October 6,
2114 a copy of bid documents and a statementthat DGH has not received any furthercomplainant, so the Bank can close thecomplaint in our system.
The Bid opening for package 13 took place onOctober 3 and DGH will submit BER to the Bankby November 3.
14Submit the bidding document ofpackage 15 (ICB) to the Bank forNOL
PMU If the SBD for NCB E-Procurement is agreed, the
Bank will consider going for full ICB E-Procurement for package 15 as a pilot.
15 The auditing report of the 2012 and2013 financial statements
PMU andBank
The PMU needs to report back to the Bank onhow they have implemented therecommendations of the auditors by the end ofNovember.
16 Submit to the Bank the revisedPMM, including the web application PMU
The revised PMM, including the supplement withthe procedures to activate component 4 of theloan agreement, will be submitted on October17, 2014.
17Finalize ToR for technical andfinancial audit and submit proposalto DFAT for funding
DGH (teamleader forEINRIP) andBank
The Bank will finalize the TOR in the end ofOctober 2014.
DGH and EINRIP will meet in the beginning ofOctober to discuss the details regarding the auditof the four ongoing packages through their TFACconsultants.
18
Make sure that adequate budgetsfor LARAP implementation areallocated in 2015 for packages allpackages, especially packages 14,16, 20, 21, 12 and 7
DGH
DGH will checked to Local Government of WestSumatera and Balai III for #16 and for all otherpackage for which they do not have yet thisinformation and report back to the Bank byOctober 10.
19 LARAPs for packages #2 PadangSawah – Simpang Empat DGH
NOL for additional LARAP issued on Submittedto Bank on July 21, 2014.
On August 18, 204 Bank sent a reminder to thePMU to complete the LARAP implementationprocess and submit documentary evidence.
The TL of DSC reported a change of design ofthe slope protection. Bank will follow up on theimpact on LARAP in a meeting planned for mid-October.
20 LARAPs for packages #3Manggopoh - Padang Sawah PMU
On August 18, 2014 the Bank sent a reminderletter to PMU to complete LARAPimplementation process and submitdocumentary evidence. Bank will follow up onthe impact on LARAP in a meeting planned formid-October.
21
Engineering design andreview/approval of slope protectiondesign completion and thenomination of the chief inspectorfor package 4
DSC The PMU will send to the Bank a copy of thesedesigns for information by the end of October.
22 PMU to submit draft DED and EEof package # 7, 8, 10, and 12 PMU
Bina Marga decided to redesign these fourpackages based on 2011 standard.
The PMU will send to WB the revised designsand OE on November 17, 2014.
23 PMU to submit draft DED and EEof package # 14, 16, 20, and 21
PMU The PMU will send draft DED and OE to WB onNovember 30, 2014.
24 DSC additional staffs PMU andDSC
The TL of DSC informed the Bank team thatDSC is finalizing the contract addendum #1 foradditional staff, asking for one highwayinspector, one surveyor, and one laboratorytechnician for each work package and, for thecentral office, one highway engineer, one bridgeengineer, one quality engineer, one social and
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 9
environmental specialist, and one QAT operator. To expedite the process, the Bank team
suggested that PMU and DSC to submit arequest letter for some staffs who are urgentlyneeded (e.g. bridge engineer package #2,supervision engineer, and environmentalspecialist), rather than waiting for the completeaddendum.
DSC will submit the request to the PMU in thesecond week of October.
25 Submission of IFR PMU The PMU will submit the IFR for the period Julyto September by November 15.
26 Approving of field engineering forpackage 1 to 4 DSC/DGH Month of October.
27Submission of environmentalmanagement plan for packages 2and 3
CTC/DGH By October 15.
28Submission of environmentalmanagement plan for packages 1and 4
CTC/DGH By October 30.
29
Status reports to be sent to theenvironmental agency, whichapproved the environmentaldocuments.
CTC/DGH Submission of status reports at regular intervals
as per local law. Please copy the Bank on thesubmission of these reports.
30
Replacement packages forpackage No. 9 Rantau Tijang –Kota Agung and package No. 18Mukomuko – Batas Sumbar (Biha– Bengkunat and Sibolga –Sorkam)
CTC/DGH
If DGH wants to try to include them in thisproject, design works need to start immediatelysince no new bidding processes can be startedafter March 31, 2015 (otherwise worksimplementation will go beyond the closing date).However, before starting the design works underthe project, DGH needs to confirm that they willfinance the works with ABPN budget in case thetechnical and economic evaluation is notsatisfactory or the bidding for civil works cannotstart 31before March 31, 2015. In addition, DGHneeds to provide the Bank with the technical andeconomic evaluation for the new sections by theend of November at the latest (the Bank isavailable to meet at your convenience to discussthe scope of this evaluation).
31
Meeting to review the status ofwork package readiness, includingLARAP implementation andrespective budgets, andpreparation of time schedule forpackages to be ready to bid byMarch 31, 2015
PMU andWB
Bank and PMU to meet in the third week ofOctober.
2.6 Project Steering Committee Meeting
No Steering Committee meeting during this quarter.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 10
3 Project Management and Implementation
3.1 Procurement Status
(A) Civil Works
Civil Works are now being implemented in Annual Work Programs (AWP)which have been numbered AWP-1, AWP-2, and AWP-3.
All four (4) AWP-1 contract packages were signed by the end of 2013 with actualwork commencement on January 2014.
During the Third (3rd) Quarter of Year 2014, three (3) contract packages forAWP-2 and one (1) contract package under AWP-3 are under finalprocurement proceedings. Under AWP-2, bids for one (1) sub-project wereopened and Bid Evaluation Report is currently under preparation, while two (2)sub-projects are presently on tendering period with bids scheduled to be openedon October 3, 2014. Bid Evaluation Report (BER) for one (1) sub-project underAWP-3 had been completed by POKJA and forwarded to DGH for final review.
Presented in Appendix 4 is the current status of procurement management.
(B) Services
The Core Team (CTC), Design & Supervision Consultant (DSC), and the othersCapacity Building Consultancy status are discussed in Section 3.4. The othersconsultancy packages are as follows :
1) Capacity Building for Disaster Risks Reduction2) Capacity Building for Environmental Management3) Capacity Building for Road Safety
Finalization of the TOR draft for the above 3 consultancy Packages are beingprepared by Sub Directorate of Environment & Road Safety - Directorat ofTechnical Affair – DGH.
3.2 Implementation Status – Civil Works
AWP-1 PackagesAll four (4) contract packages scheduled under AWP-1 are currently underconstruction by different Contractors. Commencement of Works for all the four (4)packages commenced on the 2nd week January 2014.
All the 4 Contractors substantially completed their mobilization and construction ofBase Camps in all packages have been completed. Other activities done duringthis quarter were staking out and repair and restoration of deteriorated existingpavements, roadway excavation, embankment formation, spreading of granularpavement for roadway widening, structural works construction of stone masonryside ditches, stockpiling of raw material, production of crush aggregates and otherminor works. Table 5 presents the current work progress of the four (4) contractpackages.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 11
Table 5
ProgramContractPackage
#Contractor Name of
Road
TargetProgressSchedule
EndingSeptember
2014
ActualProgress
Accomplished
SlippageContract
Time (Cal.days)
Commencement of Works
Target Date ofcompletion
Timeelapsed
(Cal. Days)
PercentTime
Elapsed
AWP-1
1
JayaKonstruksiManggalaPratama Tbk
Biha - Krui 33.99% 8.60% -30.39% 640 Jan, 8, 2014 Oct, 9, 2015 265 41.41%
2
JayaKonstruksiManggalaPratama Tbk
PadangSawah –Sp.Empatincl.AirGadangBrd
27.88% 22.55% -5.33% 730 Jan, 6, 2014 Jan, 5, 2016 267 36.58%
3
JayaKonstruksiManggalaPratama Tbk
Manggopoh –PadangSawah
21.53% 12.43% -9.10% 730 Jan, 6, 2014 Jan, 5, 2016 267 36.58%
4
PT. WaskitaKarya andPT. MulyaTurangga(JO)
Ipuh -Bantal 21.72 3.73% -16.35% 730 Jan, 10, 2014 Jan, 9, 2016 263 36.03%
At the end of this reporting quarter of Year 2014, all the four (4) contract packageswere still lagging behind schedule. The situation remains the same as in previousmonth as three (3) of the contract packages continue to follow a downward trend ofdelayed schedules, while the other one (1) Package No.2 showed signs ofimprovement to catch up with the schedule.
With more than 35% contract time for each of the four (4) contract packages haveelapsed, the Contractors will have hard time to deliver the Works on the targetdates of completion, unless a realistic action plans or “catch-up Schedules” will bestrictly implemented.
Packages No. 1 : Biha – Krui
At the end of this quarter, there was no substantial work accomplished to reduceprevious month slippage of -25.60%, instead the behind works further slipped to –30.39%.
The major work items which brought down the slippage to highly alarming situationare the drainage works (17.39%) and granular and asphalt pavements (15.22%)which accounted for a total of 32.61% cummulative target schedule for the end ofthis month. In contrast, the Contractor was able to accomplished only 2.40% totalfor both of the two (2) major work items.
As the action plan proposed in the 1st Show Cause meeting was not successful inoffsetting the huge negative slippage a 2nd Show Cause meeting was held inJakarta on September 19, 2014.
It was agreed that a Test Case of the first 2 weeks shall attain at least minimum of2.53% shall be executed by the Contractor, starting from September 22, 2014 –October 6, 2014.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 12
Unless a successful results of the Test Case is attained and realistic workableaction plan and catch up schedule is implemented by the Contractor, the workdelays will keep on accumulating.
A more detailed status of this Package is presented in ANNEX P-I ExecutiveSummary Report.
Packages No. 2 : Padang Sawah – Sp. Empat (Including Air Gadang Bridge)
As the quarter ended, there were signs of positive improvement as the Contractorwas able to reduce the slippage from -6.78% the previous month to -5.33% thismonth.
Based on the last four (4) months performance with respect to work progress, thetrend shows that the negative slippage is gradually reduced as months passed by.
ANNEX P-2 Executive Summary Report present a more detailed status of theContract Package.
Package No. 3 : Manggopoh – Padang Sawah
Although the current slippage of -9.10% end of the quarter, is still manageable atthe moment, the delayed works are also leading to a downward trend from -7.26%the previous month. Reason for this delay is the minimal work accomplished on thegeneral and drainage items and asphalt pavement which is still yet to be started.
Work activities shall be closely supervised and monitored in order that the delayedworks could be reduced or attain an ahead of schedule progress in the comingmonth.
A more detailed status of the project progress are shown in ANNEX P-3 “ExecutiveSummary Report”.
Package No. 4 : Ipuh – Bantal
The current status of this contract package is similar with that of Package No. 1wherein the negative slippage of -14.36% incurred last month further slipped downto -16.35% as of end of this reporting month.
The actual progress of only 3.73% since the project started nine (9) months ago isof much concern than the slippage. Simply looking at the percentage of workaccomplished, it seems that the project is not moving forward.
Due to the alarming situation concerning the progress of works a Show Causemeeting to tackle the current problems was held in Bengkulu last September 17,2014.
A Test Case of 30 days period from September 18, 2014 to October 18, 2014 with8.753% work accomplishment will be executed by the Contractor.
Shown in ANNEX P-4 “Executive Summary Report” are the current problem andactions to be taken to attain substantial progress in order to catch-up with theschedule.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 13
For contract packages under AWP-2 and AWP-3 which have a combined total of17 Packages, a brief summary of the actual activities and status as of this reportingperiod are presented in Table 1.1, page 6 of this Report.
AWP-2 & AWP-3 PackagesDuring this quarter, four (4) sub-project were under bidding process. Bid Openingfor two (2) packages were conducted while opening for the other two (2)packages is are scheduled on October 3, 2014.
As of end of this report period, the procurement status of the four (4) contractpackages are shown in Table 6.
Table 6
No. Package Name PackNo. Status
AWP-2
1 Sp. Rampa - Poriaha 5 Bid Evaluation Report (BER) on-going finalization.
2 Bantal - Mukomuko 11On tendering period Bidsscheduled to be opened onOctober 3, 2014.
3 Sp. Rukis - Tnj.Kemuning 13On tendering period Bidsscheduled to be opened onOctober 3, 2014.
AWP-3
4 Sp.Gn.Kemala - Pg.Tampak 17 Bid Evaluation Report (BER)submitted to DGH.
The status of the remaining packages are shown in Table 7
Table 7
No. Package Name Pack.No.
Status Type ofProcure.
Procure.
Prepr.
ReviewDED/R
SADED NCB ICB
AWP-21 Psr. Pedati - Kerkap 6 √ C C * -2 Indrapura - Tapan 7 √ C * -
3Bts. Pariaman -Manggopoh 8 √ C - *
4 Rantau Kijang - KotaAgung 9 - - - - -
5 Sp. Empat - Sp. AirBalam 10 √ C - *
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 14
No. Package Name Pack.No.
Status Type ofProcure.
Procure.
Prepr.
ReviewDED/R
SADED NCB ICB
6 Kembang - Indrapura 12 √ C - *AWP-3
7 Painan - Kambang 14 √ *8 Sibolga - Bts Tapsel 15 √ C C - *9 Seblat - Ipuh 16 √ √ *
10 Mukomuko - Bts. Sumbarumbar
18 - - - - -11 Lais - Bintunan 19 √ C C * -12 Lubuk Alung - Sicincin 20 √ *13 Lubuk Alung - Kuraitaji 21 √ *
TOTAL : 3 4 4 9 4
Notes :Packages No. 9 and 18 are proposedto be deleted and to be replaced bytwo (2) road links located in Biha-Bengkunat, Lampung Province andSorkam-Sibolga, North SumateraProvince.
3.3 Variation Order DetailsThere are still no Variation Order submitted by either the DSC Consultant or theContractors of the four (4) civil works contract of the on-going contract packages.It is expected that as a result of the finalization of field engineering by therespective Contractors of each package will result in additive cost variations.
However, in anticipation of future claims for varied works by the Contractors, arevised costs of additional 10% to the Estimated Cost for each contract packagewas prepared and submitted to PMU to cover any Variation Orders that may ariseduring the implementation of the Works.
3.4 Consultancy ServicesTechnical Assistance for Core Team Consultant (CTC) to Support the ProjectManagement Unit.
Lead Consultant: PT. Perentjana Djaja
CTC Contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 Nov 2012between the Ministry of Public Works , Directorate of Planning, DGH and PT.Perentjana Djaja, Yongma Engineering Co. Ltd, PT. Epadascon PermataEngineering Consultant, JV and the work commenced on 12 November 2012.
Amendment No.1 to this contract dated 25 October 2013 was signed toaccommodate the increase in staffing requirements with the following increase incost.
Amendment No. 2 is still to be officially approved. Proposed amendment to theOriginal Contract and Amendment No. 1 are additional man-months forprofessional and technical staff for international and local, replacement of foreignand local consultants and modification to various reimbursables to match with the
Legend : C – Completed√ – On Going
* – Procurement Type
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 15
actual requirements. Presented in Table 8 is the current status of CTC contract.
Table 8
Description USD IDR
Original Contract 1,276,700 21,415,400,000
10% VAT 127,670 2,141,540,000
Total Original Contract 1,404,370 23,556,940,000
Amendment No.1 1,315,925 22,426,175,000
10% VAT 131,592 2,242,617,500
Total Amendment No. 1 1,447,517 24,668,792,500
Variance Against Original Contract +3,07% +4,72%
Amendment No. 2 * 1,371,925 *22,458,676,500
10% VAT *137,192 *2,245,867,650
Total Amendment No. 2 *1,509,117 *24,704,544,150
Variance Against Original Contract *+7,46% *+4,87%
* Tentative until Amendment No. 2 is officially approved
Technical Assistance for Design & Supervision Consultant (DSC)
Lead Consultant: Renardet S.A
DSC Contract No. KU.03.01/PPK-PR/WINRIP/Bx/01/VI/2013 was signed on 11Jun 2013 between the Ministry of Public Works, Head of Regional Office forNational Roads Implementation, DGH and Renardet S.A. PT Cipta Strada, PT.Daya Creasi Mitrayasa, PT. Seecons and PT. Yodya Karya (Persero) JointVenture and mobilized on 19 June 2013. Table 9 shows the current status of DSCcontract.
Table 9
Description USD IDROriginal Contract (exc. VAT) 820,600,00 51,818,705,000
VAT 10% (GOI Portion) 82,060,00 5,181,870,500
Total 902,660,00 57,000,575,500
Technical Assistance for Capacity Building for Disaster Risks Reduction
Lead Consultant : Still to be Procured
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 16
World Bank sent the results of their informal review to Teknik Lingkungan danKeselamatan Jalan (TLKJ) on the Draft Final Terms of Reference. TLKJ is currentlyfinalizing the TOR based on Bank’s informal review and expected to be resubmittedto the Bank by the 1st week of October 2014.
Technical Assistance for Capacity Building for Environmental Management
Lead Consultant : Still to be Procured
Draft Terms of Reference still to be prepared.
Technical Assistance for Capacity Building for Road Safety
Lead Consultant : Still to be Procured
Draft Terms of Reference still to be prepared.
Procurement Plan for consulting services is presented in Appendix 5
3.5 Implementation of the Anti-Corruption Action Plan
Community Representative Officers (CRO)
CROs have been appointed for AWP-1 packages and those appointed for theAWP-1 packages attended the bid opening meetings in Packages 1 and 4 andPackages 2 and 3 in Palembang and Padang, respectively. All CROs areuniversity staff members as prioritized in the PMM and have had extensivetraining sessions.
Likewise, appointed CRO’s for Package Nos. 17 and 5. attended the pre-bidmeetings, site visits and bid openings in Bengkulu and Medan
To date or as of end of this 3rd Quarter of the Year 2014, a total of sixteen (16)have been appointed to discharge their duties as independent observers during theprocurement activities.
A complete list of CROs appointed with corresponding credentials as of end ofSeptember 2014 can be found in Appendix 6.
Appendix 7 shows their activities since the inception of the Project.
Third Party Monitors (TPM)
During this Quarter there was no appointment of Third Party Monitors, however,in the 1st Quarter at this Year, Third Party Monitors have been appointed tomonitor the progress of the Works for Packages 1, 2, 3 and 4. To date a totaltwelve (12) appointments have been approved.
List of appointed TPM with their respective occupations and professionalaffiliations are shown in Appendix 8, while Appendix 9 shows the past topresent activities/progress of the TPM.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 17
Complaint Handling System (CHS)
The WINRIP website has been online, and available for reporting all aspects ofthe Anti-Corruption A c t i o n Plan including the registering of complaints by thegeneral public. The website can be accessed at the URL addresshttp://www.winrip-ibrd.com.
The CHS application has completed. The application was put in sub-domain ofWINRIP website since February 2014 and in August 2014 socialization wereconducted in Padang, Lampung and Bengkulu. To access it, click on the sub-domain URL address http://chs.winrip-ibrd.com. Appendix 10 and Appendix 11show the Work Plan on CHS System and Work Activities onPublication/Disclosures.
3.6 Implementation of the Environmental Management Plan and LARAPA project category is assigned to each package as either Category A, B or Cdepending on the likely degree of influence on environmental issues with a briefexplanation as follows:
Category A project is one which will have a significant negative impact on theenvironment and may have an influence on areas outside the actual project area.A project classified as such requires an AMDAL (ANDAL, RKL/RPL) study.
Category B project is one which affects the people or the environment to someextent but with a smaller impact than a Category A. The required environmentalanalysis is a UKL/UPL study only.
Category C project has minimal effect on the people or environment and anenvironmental analysis is not required. SPPL are used to handle any minorproblem which may arise.
All the twenty one (21) packages require environmental impact investigations.There are a total of fourty one (41) studies required, twenty (20) for environmentalimpact investigations and twenty one (21) for social studies.
The twenty (20) environmental studies need the approval of the EnvironmentalAgency (BLH) with five (5) of the studies (AMDAL/EIA) to be approved by WorldBank (WB).
While the twenty one (21) social studies (SLARAP and LARAP) require theapproval of World Bank prior to implementation.
As of end of this quarter reporting period (September 2014), nineteen (19)environmental impact studies has been approved by BLH, while all of the five (5)studies that requires World Bank approval, Bank already issued No ObjectionLetter (NOL). The remaining one (1) environmental impact studies (UKL-UPL) for
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 18
Packages No. 4 (Ipuh-Bantal) is currently under processing of environmentalpermit from the Bupati Kabupaten Muko-muko.For the social studies , twelve (12)of the twenty one (21) studies were already given No Objection Letter from theWorld Bank (WB).
Appendix 12 details the list of Environmental Safeguard and Appendix 13describes the Environmental Management Plan (EMP) Compliance up to the endof this Quarter (June 2014).
Presented below Table 10 in a tabulated format is the current status of theenvironmental and social studies.
Table 10
WorksProgram
No ofPackages
No of Investigations Approval by Remarks
BLH World Bank
AWP-1 4 11
AMDAL x 1
UKL&UPL x 2
SPPL x 4
Full LARAP x 4 1 (AMDAL) 1UKL&UPL4 (SPPL)
1 EIA, NOLIssued by WB
4
Full LARAP
Approved – NOL issuedby WB (LARAP andAMDAL paket 1&17),except for SPPL.
UKL-UPL for PackageNo.4 processing ofenvironmental permit isbeing prepared byBupati Kab. Muko-muko
AWP-2 9 17
AMDAL Study x 4
UKL&UPL x 4
Simple LARAP x 1
Full LARAP x 8
4 UKL&UPL
4 AMDAL
1 SimpleLARAP;
3 Full LARAP
4 EIA, NOLIssued by WB
1 (one) Study AMDALfor three packages.Packages No.7, 12 and14 /packages on AWP2&AWP3.
1 (one) Study AMDALfor two packages.Packages No.11 & 16./packages on AWP2&AWP3.
AWP-3 8 13
Full LARAP x 4
Simple LARAP x 4
AMDAL Study x1= Paket No.1AWP 1
UKL/UPL x 5
AMDAL OK =paket No.1&
17 AWP15 UKL&UPL
EIA same withPackage 1
1 SimpleLARAP;
3 Full LARAP
Approved – NOL issuedby WB include AMDALexcept for UKL/UPL
Total 21 41 Env=20,Soc=21 19 12
Note: UKL & UPL do not need a NOL from WB, and SPPL not necessary to submit to the WB.
Status of monitoring of environmental mitigation are shown in Appendix 14 andAppendix 15 covers the status of overall land acquisition.
2014 Quarterly Progress Report 3rd Quarter : July-August-September
Western Indonesia National Roads Improvement Project 19
4 Workshops & Training
During this quarter (July, August and September 2014) two (2) trainings were conductedin Bengkulu. The two (2) training are “Training on Work Plan for EnvironmentalManagement and Monitoring or Rencana Kerja Pengelolaan dan PemantauanLingkungan (RKPPL)” and “Training on Third Party Monitoring (TPM)”.
Aside from the two (2) training that were delivered, socialization workshop for the ProjectManagement Manual (PMM) was carried out in Padang.
Presented in Appendix 16 is the Summary of Workshop and Trainings since the projectstarted up to end of this quarter.
Table Of Contents
1 Executive Summary...................................................................................................... 1
1.1 Current Implementation Situation........................................................................ 1
1.1.1 Civil Works............................................................................................... 1
1.1.2 Consultancy Services…………………………………………………………..2
1.1.3 Goods...................................................................................................... 2
1.2 Current Status of Loan ....................................................................................... 4
1.3 Current Problems and Action Required.............................................................. 4
2 General........................................................................................................................ 5
2.1 Reporting Requirements .................................................................................... 5
2.2 Loan Status ....................................................................................................... 5
2.3 Financial Management ....................................................................................... 6
2.4 Project Cost Monitoring ...................................................................................... 6
2.5 Bank Mission ...................................................................................................... 6
2.6 Project Steering Committee Meeting .................................................................. 9
3 Project Management and Implementation ..................................................................10
3.1 Procurement Status...........................................................................................10
3.2 Implementation Status – Civil Works.................................................................10
3.3 Variation Order Details.......................................................................................14
3.4 Consultancy Services ........................................................................................14
3.5 Implementation of the Anti-Corruption Act ion Plan .........................................16
3.6 Implementation of the Environmental Management Plan ....................................17
4 Workshops & Training ................................................................................................19
ANNEXES
Annex P-1 : Package No. 1
Annex P-2 : Package No. 2
Annex P-3 : Package No. 3
Annex P-4 : Package No. 4
ANNEX P-1
MONTH :
Package No. Time Elapsed (Days) 229
Name Time Elapsed (%) 35.78%
Project Manager Scheduled Progress (%) 31.58 Contractor PT JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 5.98 Supervision Consultant Balance (%) -25.60 Commencement Date Progress This Month (%) 1.19 Take Over Date Time for Complation (Days) 640 Addendum-1 Status date Contract Amount Rp. Accumulative Rp. 10.46% Contract Amount Add-1 (+ PPN) *) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month MonthI G e n e r a l 8.25 2.35 0.01 2.36 2.04II D r a i n a g e 34.19 0.22 0.13 0.35 14.65III Earthworks 3.95 0.84 0.41 1.25 2.72
IV Pavement Widening &Shoulders
1.47 - - - -
V Granular Pavement 9.22 0.53 0.41 0.94 7.09VI Asphalt Pavement 40.14 - - - 3.82VII S t r u c t u r e s 1.09 0.57 0.20 0.77 0.86
VIII Reinstatement &Minor Works
1.20 0.09 0.03 0.12 0.15
IX Day Work 0.14 - - - 0.05
X Routine MaintenanceWorks
0.36 0.18 0.01 0.19 0.20
TOTAL 100.00 4.79 1.20 5.99 31.58
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 220.22 0.87 1.69 5.62 11.11 18.06 24.50 31.58 38.99 46.36 53.25 60.68 67.46 74.81 80.69 83.98 87.62 91.27 93.71 96.16 98.75 100.000.10 0.58 0.79 1.59 2.93 3.71 4.79 5.98
(0.12) (0.29) (0.90) (4.03) (8.18) (14.35) (19.71) (25.60)
Scheduled Progress Original (%) Actual Progress (%) Balance (%)
Div Description
PHYSICAL PROGRESS MONITORING TABLE2014 2015 Year
Month The month of time for complation
- Late of Field Engineering Decision - DSC and Contractor to discuss with PPK regarding the finalization of the Field Engineering.
PHYSICAL WORK PROGRESS BY CATEGORY
134,909,211,000.00
DISBURSEMENT *)
14,106,688,650.003-Jul-14
- The Contractor has not started works as per the - The contractor have to started the main work approved schedule such as drainage works
RENARDET S.A JV - Insufficient manpower, equipment and financial - The contractor have to add manpower aspecialy
SUPARJONO, ST,MT
AMO
UN
T
8-Jan-14 resources to undertake the needed acceleration for drainage work9-Oct-15 of works.
EXECUTIVE SUMMARY REPORTAug-14
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
01
TIM
E August 25, 2014
BIHA - KRUI MAJOR PROBLEMS ACTION TO BE TAKEN
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #01
Schedule
Actual
ANEXES EXECUTIVE SUMMARY REPORT edit 9 Sep 2014_8C4693 ExSum P-1
ANNEX P-2
MONTH :
Package No. Time Elapsed (Days) 231 Name Time Elapsed (%) 31.64% Project Manager Scheduled Progress (%) 20.63 Contractor PT JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 13.85 Supervision Consultant Balance (%) -6.78 Commencement Date Progress This Month (%) 4.17 Take Over Date Time for Complation (Days) 730 Addendum-1 Status date Contract Amount Rp. Accumulative Rp. 10.21% Contract Amount Add-1 (+ PPN) *) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 10.46 1.59 2.15 3.74 4.89II D r a i n a g e 3.53 1.58 0.80 2.37 3.39III Earthworks 4.44 1.10 0.21 1.32 2.32
IV Pavement Widening &Shoulders
2.26 0.47 0.48 0.95 -
V Granular Pavement 10.49 0.29 0.34 0.63 3.53VI Asphalt Pavement 52.09 - - - 1.33VII S t r u c t u r e s 14.35 3.47 0.14 3.61 4.71
VIII Reinstatement & MinorWorks
1.65 0.88 0.04 0.92 0.10
IX Day Work 0.12 - - - 0.04
X Routine MaintenanceWorks
0.62 0.31 0.01 0.32 0.32
TOTAL 100.00 9.69 4.17 13.85 20.63
Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Schedl Progress Original (%) 0.45 0.90 2.20 3.45 7.17 13.58 17.48 20.63 27.88 33.56 38.81 44.72 50.52 56.13 62.58 69.25 73.65 79.35 82.91 85.94 90.59 93.85 97.89 100.00 Actual Progress (%) - 0.13 1.02 2.19 4.11 5.96 9.69 13.85 Balance (%) (0.45) (0.77) (1.17) (1.26) (3.07) (7.62) (7.80) (6.78)
2014 2015
- Late of Field Engineering Decision - DSC and Contractor to discuss with PPK
- Contractor has insufficient manpower and finan- - The contractor have to add manpower aspecialy cial resource to excecute the available works for drainage work - Delayed land acquisition of Air Gadang Bridge - DSC ask partial land acquisition plan to PPK approach - Delayed of additional land acquisition - PPK should coordinate with respective agency - Delayed relocation of existing electrical pole - PPK should give notification to the utility company
197,936,699,000.00 regarding the finalization of the Field Engineering.
August 25, 2014PADANG SAWAH-SIMPANG EMPAT MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORTAug-14
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
The month of time for complation
DISBURSEMENT *)14-Jul-14
20,211,284,785
02
TIM
EAM
OU
NT
RENARDET S.A JV6-Jan-145-Jan-16
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
PHYSICAL PROGRESS MONITORING TABLE
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #02
Schedule
Actual
ANEXES EXECUTIVE SUMMARY REPORT edit 9 Sep 2014_8C4693 ExSum P-2
ANNEX P-3
MONTH :
Package No. Time Elapsed (Days) 231
Name Time Elapsed (%) 31.64% Project Manager Scheduled Progress (%) 14.27 Contractor PT JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 7.01 Supervision Consultant Balance (%) -7.26 Commencement Date Progress This Month (%) 1.31 Take Over Date Time for Complation (Days) 730 Addendum-1 Status date - Delayed relocation of existing electrical pole - PPK should give notification to the utility company Contract Amount Rp. Accumulative Rp. 11.20% - Late of Field Engineering Decision - DSC and Contractor to discuss with PPK Contract Amount Add-1 (+ PPN) *) Include advance payment regarding the finalization of the Field Engineering.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 10.21 1.35 0.01 1.36 3.40II D r a i n a g e 13.17 1.10 0.07 1.17 6.17III Earthworks 3.04 2.51 0.08 2.59 1.29
IV Pavement Widening &Shoulders
2.45 - - - -
V Granular Pavement 11.27 0.80 0.07 0.87 1.77VI Asphalt Pavement 55.81 - - - 0.50VII S t r u c t u r e s 0.80 0.36 0.14 0.50 0.57
VIII Reinstatement & MinorWorks
2.27 0.56 0.44 1.00 0.12
IX Day Work 0.22 0.03 0.00 0.03 0.07
X Routine MaintenanceWorks
0.76 0.38 0.01 0.39 0.38
TOTAL 100.00 7.08 0.83 7.91 14.27
Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Schedl Progress Original (%) 0.26 1.00 1.67 2.45 4.78 7.45 10.70 14.27 21.53 30.10 36.95 44.01 51.62 58.67 65.63 73.03 79.97 87.04 91.61 93.19 94.30 95.76 97.82 100.00 Actual Progress (%) 0.24 0.48 2.07 2.43 2.87 5.45 5.70 7.01 Balance (%) (0.02) (0.52) 0.40 (0.02) (1.91) (2.00) (5.00) (7.26)
PHYSICAL PROGRESS MONITORING TABLE
143,688,963,000.00
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
RENARDET S.A JV - Delayed decision of the design of concrete pile - DSC and Contractor has discussed with PPK regar-
DISBURSEMENT *)
6-Jan-14 retaining wall ding the finalization of the design and the5-Jan-16 method of construction of precast retaining wall.
cial resource to excecute the available works for drainage work
EXECUTIVE SUMMARY REPORTAug-14
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
2014 2015
30-Jun-1416,091,601,613.00
03
TIM
E August 25, 2014
MANGGOPOH - PADANG SAWAH MAJOR PROBLEMS ACTION TO BE TAKEN
- Delayed of additional land acquisition - PPK should coordinate with respective agency
AMO
UN
T - Contractor has insufficient manpower and finan- - The contractor have to add manpower aspecialy
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #03
Schedule
Actual
ANEXES EXECUTIVE SUMMARY REPORT edit 9 Sep 2014_8C4693 ExSum P-3
ANNEX P-4
MONTH :
Package No. Time Elapsed (Days) 227
Name Time Elapsed (%) 31.10%
Project Manager Scheduled Progress (%) 15.81 Contractor PT WASKITA KARYA - PT DAYA JO Actual Overall Progress (%) 1.45 Supervision Consultant Balance (%) -14.36 Commencement Date Progress This Month (%) 0.58 Take Over Date Time for Complation (Days) 730 Addendum-1 Status date Contract Amount Rp. Accumulative Rp. 9.30% Contract Amount Add-1 (+ PPN) *) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 7.59 0.56 0.01 0.56 0.59II D r a i n a g e 12.26 - 0.03 0.03 4.68III Earthworks 3.58 0.03 - 0.03 0.77
IV Pavement Widening &Shoulders
3.39 - - - -
V Granular Pavement 18.07 0.21 0.56 0.77 4.92VI Asphalt Pavement 49.27 - - - 3.27VII S t r u c t u r e s 2.55 - - - 1.16
VIII Reinstatement & MinorWorks
2.95 0.06 - 0.06 0.30
IX Day Work 0.14 - - - 0.06
X Routine MaintenanceWorks
0.20 0.01 0.00 0.01 0.08
TOTAL 100.00 0.87 0.59 1.46 15.81
Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Schedl Progress Original (%) 0.11 0.32 0.75 1.14 6.57 10.29 12.85 15.81 21.72 25.43 32.76 40.88 47.93 55.61 63.45 70.19 77.04 81.55 84.79 90.84 94.62 97.05 98.80 100.00 Actual Progress (%) - 0.18 0.40 0.53 0.56 0.78 0.87 1.45 Balance (%) (0.11) (0.14) (0.35) (0.61) (6.01) (9.51) (11.98) (14.36)
PHYSICAL PROGRESS MONITORING TABLE
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
- Late of Field Engineering Decision - DSC and Contractor to discuss with PPK
186,936,750,000.00 regarding the finalization of the Field Engineering.
DISBURSEMENT *)23-May-14
17,385,117,750.00
- The contractor have to add manpower aspecialy10-Jan-14 resources to undertake the needed acceleration for drainage work9-Jan-16 of works.
EXECUTIVE SUMMARY REPORTAug-14
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
2014 2015
04
TIM
E August 25, 2014
IPUH - BANTAL MAJOR PROBLEMS ACTION TO BE TAKEN
AMO
UN
T - The Contractor has not started works as per the - The contractor have to started the main work approved schedule such as drainage works
RENARDET S.A JV - Insufficient manpower, equipment and financial
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #04
Schedule
Actual
ANEXES EXECUTIVE SUMMARY REPORT edit 9 Sep 2014_8C4693 ExSum P-4
APPENDICES
Appendix 1 : Disbursement and Expenditures Status
Appendix 2 : Report At The End of The Quarter (September 30, 2014)
Appendix 3 : Detailed Summary of the Project Cost Monitoring
Appendix 4 : Procurement Management of Civil Works
Appendix 5 : Procurement Plan for Consulting Services
Appendix 6 : List of Names of Community Representative Observers (CRO)
Appendix 7 : Anti Corruption Action Plan (ACAP)
Activity Progress of Community Representative Observers (CRO)
Appendix 8 : List of Appointed Third Party Monitors (TPM)
Appendix 9 : Progress of Third Party Monitoring (TPM) Activities
Appendix 10 : Complaints Handling Mechanism System (CHS)
Appendix 11 : Work Activities On Publication/Disclosure
Appendix 12 : Environmental Safeguards
Appendix 13 : Environmental Management Plan (EMP) Compliance
Appendix 14 : Status of Monitoring of Environmental Mitigation
Appendix 15 : Overall Land Acquisition Status as of September 30, 2014
Appendix 16 : Summary of Workshops and Trainings In 2012 and 2014
APPENDIX 1
Disbursement and Expenditures Status
Appendix - 1 in USD
Detail of Loan Expenditures RemainingCategory Allocation Disbursement Current Cumulative Loan
Quarter to date Allocation1 2 3 4 5 6 7 8 = 3 - 6 9 = 8 *0,7
1 Civil Works under part 1 of the project 220,400,000.00 4,446,969.45 417,693.83 4,446,969.45 53,374,582.50 215,953,030.55
01. Krui - Biha 11,757,337.74 100,033.47 873,532.10 10,883,805.64 7,618,663.9502. Padang Sawah - Sp.Empat/Inc Air Gadang Brgd 17,250,183.32 317,660.36 1,452,525.53 15,797,657.79 11,058,360.4503. Manggopoh - Padang Sawah 12,522,493.13 0.00 977,967.24 11,544,525.89 8,081,168.1204. Ipuh - Bantal 16,291,537.76 0.00 1,142,944.58 15,148,593.18 10,604,015.2317. Sp.Gng Kemala - Pugung Tampak05. Simpang Rampa - Poriaha11. Bantal - Mukomuko13. Sp Rukis - Tj Kemuning06. Ps. Pedati - Kerkap19. Lais - Bintunan15. Sibolga - Batas Tapsel08. Bts.Kota Pariaman - Manggopoh10. Simpang Empat - Sp.Air Balam07. Indrapura - Tapan12. Kambang - Indrapura14. Painan - Kambang16. Seblat - Ipuh, Inc Air Lalang/Guntung Brgd20. Lubuk Alung - Sicincin21. Lubuk Alung - Kuraitaji18. Mukomuko - Batas Sumbar **09. Rantau Tijang - Kota Agung **
2Goods, Non Consulting Services, ConsultingServices and Incremental Operating Cost underpart 2 of the project
16,000,000.00 1,848,059.18 0.00 1,848,059.18 14,151,940.82 14,151,940.82
3Goods, Non Consulting Services, ConsultingServices and Incremental Operating Cost underpart 3 of the project
1,000,000.00 0.00 0.00 0.00 0.00 1,000,000.00
4Goods, Non Consulting Services, ConsultingServices and Incremental Operating Cost underpart 4 of the project
0.00 0.00 0.00 0.00 0.00 0.00
5 Unallocated 12,600,000.00 0.00 0.00 0.00 0.00 12,600,000.00
250,000,000.00 6,295,028.63 417,693.83 6,295,028.63 67,526,523.32 243,704,971.37
Note : Ending Balance Special Account Status September 2014 USD 386,275.82
Western Indonesia National Roads Improvement ProjectDisbursement and Expenditures Status
For the Quarter ending September 30, 2014IBRD Loan No. 8043 - ID
LoanCat
Remaining Amountof Contract
Expenditures not yetreplenish
APPENDIX 2
Report At The End of The Quarter
(September 30, 2014)
Appendix 2Western Indonesia National Roads Improvement ProjectProject Report Format - 2Report for the quarter ended on 30-09-14
Particulars ( Amount in US $ )
Bank Fund disbursed till date I 6,681,304.45Total Project Uses till date II 8,372,695.63World Bank Share @ 70% for CW III 4,446,969.45World Bank Share @ 100% for TA IV 1,744,022.99World Bank Share @ 100% for IOC V 104,036.19Ending Balance Special Account VI 386,275.82Funds Undisbursed to date VII 243,318,695.55
Forecast for Project payments for the next 6 months VIII 8,590,242.53World Bank Share @ 70% for CW IX 6,013,169.77World Bank Share @ 100% for TA X 633,755.59World Bank Share @ 100% for IOC XI 135,000.00Fund Undisbursed for next 6 month 236,536,770.19Net Funds required from the Bank 6,781,925.36
Forecast for DIPA from GOI for the 6 months XII 1,808,317.17
Mar-14
APPENDIX 3
Detailed Summary of the Project Cost Monitoring
Disbursement Contract Procurement Contract Supplier/ Nationality Contract Contract Amount Payment realization Code Cat. Category Description Method /ii Number /iii Contractor Currency Value Invoiced No. SP2D/WA Date of SP2D Amount(Rp) Amount (US$) (Rp.) (US$) Comp.
No Description to date1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1. CIVIL WORKS
1 CIVIL WORKS ICB Krui - Biha PT. JAYA KONSTRUKSI INDONESIA IDR 134,909,211,000.00 27-Dec-13 3,102,911,853.00 131,806,299,147.00
01-26/04-WINRIP-WP1/CE/A/8043/11-13 MANGGALA PRATAMA 2-Jan-14 9,443,644,770.00 122,362,654,377.00
Tanggal 14 November 2013 20-Jun-14 385,839,103.00 121,976,815,274.00
3-Jul-14 1,174,292,924.00 120,802,522,350.00
14,106,688,650.00 120,802,522,350.002 CIVIL WORKS ICB Padang Sawah - Sp.Empat PT. JAYA KONSTRUKSI INDONESIA IDR 197,936,699,000.00 30-Dec-13 4,552,544,077.00 193,384,154,923.00
Including Air Gadang Bridge MANGGALA PRATAMA 2-Jan-14 13,855,568,930.00 179,528,585,993.00
39-06/02-WINRIP-WP1/CE/A/8043-ID/12-13 23-Jun-14 577,715,230.00 178,950,870,763.00
14-Jul-14 1,225,456,548.00 177,725,414,215.00
10-Sep-14 662,017,142.00 177,063,397,073.00
Tanggal 06 December 2013 30-Sep-14 2,521,001,709.00 174,542,395,364.00
23,394,303,636.00 174,542,395,364.003 CIVIL WORKS ICB Manggopoh - Padang Sawah PT. JAYA KONSTRUKSI INDONESIA IDR 143,688,963,000.00 30-Dec-13 3,304,846,149.00 140,384,116,851.00
40-06/03-WINRIP-WP1/CE/A/8043-ID/12-13 MANGGALA PRATAMA 2-Jan-14 10,058,227,410.00 130,325,889,441.00
Tanggal 06 December 2013 12-Jun-14 874,188,600.00 129,451,700,841.00
30-Jun-14 1,854,339,454.00 127,597,361,387.00
16,091,601,613.00 127,597,361,387.004 CIVIL WORKS ICB Ipuh - Bantal PT. WASKITA KARYA - DAYA INDONESIA IDR 186,936,750,000.00 16-Dec-13 4,299,545,250.00 182,637,204,750.00
01-26/04-WINRIP-WP1/CE/A/8043/11-13 MULIA TURANGGA JO 23-May-14 13,085,572,500.00 169,551,632,250.00
Tanggal 14 November 2013 SARI, Jo
17,385,117,750.00 169,551,632,250.00
NOTES:
VAT for Loan portion is not collected/i: This Report provides procurement information for the project from inception to the latest reporting date./ii: Each method in Procurement Guidelines should be shown separately
ICB : International Competitive BiddingNCB : National Competitive BiddingNS : National ShopingDC : Direct Contracting
040667I
092390I
079428I
004/04-WINRIP/26
003/03-WINRIP/06
004/03-WINRIP/06
254931Y
040668I
002/02-WINRIP/06
079428I
003/02-WINRIP/06
004/02-WINRIP/06
Western Indonesia National Roads Improvement ProjectContract Expenditure Report Goods and Works)
for the quarter ended September 30, 2014IBRD Loan 8043 - ID
592,493,911,351.00
Remaining amount Of Contr. Note
590770D
T O T A L CIVIL WORKS 663,471,623,000.00 70,977,711,649.00
001/01-WINRIP/17
415066J
002/01-WINRIP/17
Form 3 - A
APPENDIX 4
Procurement Management of Civil Works
APPENDIX 4
Submission Notification
Sub - Project of ofIDR (x10⁶) Application Qualification Original Addendum
AWP - 1
1 10-17/01-WINRIP-WP1/CE/A/8043-ID/11-13 Krui - BihaLampung Province.
CapacityExpansion 163,534.85 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 PT. Jaya Konstruksi
Manggala Pratama, Tbk. 25-Nov-13 Civil Work ICB 134,909.21 70.00
2 39-06/02-WINRIP-WP1/CE/A/8043-ID/12-13Padang Sawah - Sp.Empat (incl. AirGadang Bridge), West SumateraProvince.
CapacityExpansion 228,772.24 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 PT. Jaya Konstruksi
Manggala Pratama, Tbk. 06-Dec-13 Civil Work ICB 197,936.70 70.00
3 40-06/03-WINRIP-WP1/CE/A/8043-ID/12-13 Manggopoh - Padang Sawah, WestSumatera Province
CapacityExpansion 167,678.40 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 PT. Jaya Konstruksi
Manggala Pratama, Tbk. 06-Dec-13 Civil Work ICB 143,688.96 70.00
4 01-26/04-WINRIP-WP1/CE/A/8043-ID/11-13 Ipuh - Bantal, Bengkulu Province CapacityExpansion 247,105.24 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 PT. Waskita Karya - PT.
Daya Mulia Turangga, J.O. 14-Nov-13 Civil Work ICB 186,936.75 70.00
AWP - 2
5 Simpang Rampa - Poriaha, NorthSumatera Province.
CapacityExpansion 152,870.49 07-Nov-13 22-Jul-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 9-Jun-14 15-Jul-14 22-Jul-14 18-Jul-14 22-Jul-14 11-Aug-14 22-Sep-14 Civil Work ICB 70.00
6 Ps. Pedati - Kerkap, BengkuluProvince
CapacityExpansion 92,127.40 21-Nov-13 Civil Work NCB 70.00
7 Indrapura - Tapan, West SumateraProvince
CapacityExpansion 280,123.02 Civil Work NCB 70.00
8 Bts.Kota Pariaman - Manggopoh,West Sumatera Province
CapacityExpansion 603,016.70 Civil Work ICB 70.00
9
Rantau Tijang - Kota Agung,Lampung Province(proposed change to Biha -Bengkunat, Lampung Province)
CapacityExpansion 149,831.00 Civil Work NCB 70.00
10 Simpang Empat - Sp.Air Balam,West Sumatera Province
CapacityExpansion 819,755.25 Civil Work ICB 70.00
11
Bantal - Mukomuko, BengkuluProvince(proposed change to Sibolga -Sorkam, North Sumatera Province)
CapacityExpansion 246,499.55 07-Nov-13 06-Aug-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 16-Jun-14 25-Jun-14 11-Jul-14 21-Jul-14 6-Aug-14 22-Aug-14 3-Oct-14 Civil Work ICB 70.00
12 Kambang - Indrapura, WestSumatera Province
CapacityExpansion 773,942.44 Civil Work ICB 70.00
13 Sp Rukis - Tj Kemuning, BengkuluProvince.
CapacityExpansion 316,304.67 07-Nov-13 06-Aug-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 16-Jun-14 25-Jun-14 11-Jul-14 21-Jul-14 6-Aug-14 22-Aug-14 3-Oct-14 Civil Work ICB 70.00
AWP - 3
14 Painan - Kambang, West SumateraProvince
CapacityExpansion 118,993.00 Civil Work NCB 70.00
15 Sibolga - Batas Tapsel, NorthSumatera Province
CapacityExpansion 376,479.38 30-Dec-13 28-Feb-14 Civil Work ICB 70.00
16Seblat - Ipuh, (incl. Air Lalang & AirGuntung Bridge), BengkuluProvince
CapacityExpansion 110,237.00 Civil Work NCB 70.00
17 Sp.Gng Kemala - Pugung Tampak,Lampung Province
CapacityExpansion 255,269.25 30-Sep-13 10-Oct-13 30-Sep-13 10-Oct-13 11-Nov-13 30-Dec-13 28-Feb-14 13-Jun-14 25-Jun-14 19-Dec-14 7-Jan-14 4-Jul-14 15-Aug-14 29-Sep-14 Civil Work ICB 70.00
18 Mukomuko - Batas Sumbar,Bengkulu Province
CapacityExpansion 69,233.00 Civil Work NCB 70.00
19 Lais - Bintunan, Bengkulu Province CapacityExpansion 35,886.28 21-Nov-13 Civil Work NCB 70.00
20 Lubuk Alung - Sicincin, WestSumatera Province Betterment 54,557.00 Civil Work NCB 70.00
21 Lubuk Alung - Kuraitaji, WestSumatera Province
CapacityExpansion 65,788.00 Civil Work NCB 70.00
WESTERN INDONESIA NATIONAL ROAD IMPROVEMENT PROJECTPROCUREMENT MANAGEMENT FOR CIVIL WORK
PackageNo. Type of Work
Estimated CostEE (Incl. VAT)
Design PQ Document Invitation forPre-
qualification
Evalt.QualificationReport Category
ContractProcurement Method
Contract Price (IDR 106)including Tax
World BankFinancingRatio (%)
ContractorContractSignature
DateSubmissionDate WB NOL
Contract No.WB NOL
Date
Bidding Document Invitationfor Bids
Date
BidOpening
Date
Bid Evaluation Report
SubmissionDate NOL Date Submission
DateWB NOL
DateSubmission
DateSubmissio
n DateWB NOL
Date
APPENDIX 5
Procurement Plan for Consulting Services
APPENDIX 5
Procurement Plan of Implementation Support and Road Sector Institutional DevelopmentWestern Indonesia National Roads Improvement Project (WINRIP)Name of Executing Agency: Directorate General of Highways , Ministry of Public Works. STATUS Sept 30, 2014
Ref.No. Contract Description Project Cost (US$) Procurement
Method
Review byBank
(Prior/Post)Schedule Preparation
of Draft REOI
EOIadvertised in
MPWWebsite
SubmissionRFP to WB WB NOL to RFP Opening of
Financial Proposal
FinalEvaluationReport
ContractSign
Service Startdate
Period(Month) Consultant Remarks
Allocated Contract Actual Submission WB NOL Submission WB NOL Submission Submission WB NOL
2 Implementation Support
Schedule 14-Nov-10 05-Dec-10 23-Jan-11 12-Feb-11 12-Mar-11 02-Apr-11 23-Apr-12 04-Jun-12 22-Jul-12 05-Aug-12 12-Aug-12 15-Sep-12 29-Sep-12 22-Oct-12 12-Nov-12
Actual 26-Nov-10 7-Jun-11 30-Jan-12 7-Mar-12 9-Dec-11 6-Mar-12 20-Mar-14 30-Apr-12 14-Jun-12 29-Jun-12 27-Aug-12 3-Sep-12 21-Sep-12 12-Oct-12 5-Nov-12 16-Nov-12 40
Schedule 11-Dec-11 08-Jan-12 27-Feb-12 26-Mar-12 07-May-12 28-May-12 08-Oct-12 22-Oct-12 05-Nov-12 12-Nov-12 19-Nov-12 26-Nov-12 01-Apr-13 18-Apr-13 02-May-13
Actual 26-Nov-10 7-Jun-11 4/2/2012 10-Aug-12 20-Jan-12 23-May-12 31-Aug-14 23-Oct-12 20-Dec-12 21-Feb-13 5-Mar-13 13-Mar-13 25-Mar-13 19-Apr-13 11-Jun-13 25-Jun-13 42
3 Road Sector Institutional Development (DGH)
Capacity Building for DGH Environment/Risk Mitigation and Road Safety Unit(developing roadmap, norm, standard, procedure,criteria for disaster risk management in road sector, riskanalysis and standad implementation)Peningkatan Kapabilitas Penanggulangan Bencana,Ditjen Bina Marga. Schedule 04-Oct-14 11-Oct-14 11-Oct-14 25-Oct-14 22-Nov-14 06-Dec-14 20-Dec-14 17-Jan-15 07-Feb-15 21-Feb-15 07-Mar-15 14-Mar-15 28-Mar-15 11-Apr-15 25-Apr-15 09-May-15 18 30-Oct-16
Capacity Building for Disaster Risk Reduction in DGH Actual
Note: Part 3: The packages based on proposed by DTA (Sub-Dit. Of Environmental and Road Safety). TOR of packages had been submitted by DTA (Sub-Dit. Of Environmental and Road Safety) directly to Bank. TOR still revised based on bank review.
PT. PerentjanaDjaja, YongmaEng. Co. Ltd
and PT.Epadascon
PermataRenardet S.A.,PT. Cipta
Strada, PT.Daya Creasi
Mitrayasa, PT.
T O T A L
1,000,000
a. 1,000,000 QCBS Prior
bDesign and Supervision Consultant (DesignAWP-2 & 3 and Construction Supervision of CivilWorks Project)
10,000,000 6,070,722 QCBS
aCore Team Consultant (Project Management,Technical Assistant, Enviromental & Social Aspectand Road safety Audit)
5,000,000 3,497,984 QCBS
Date ofReceipt ofProposals
Prior
Evaluation and Short List Technical EvaluationReport Negotiation & Draft Contract
Prior
Theissuance
RFP to theshortlisted
firms
APPENDIX 6
List of Names of Community Representative Observers(CRO)
No.
Pac
kage
Pack
age
Sele
ctio
n Da
te
Trai
ning
Dat
e
Loca
tion
Tele
phon
e
Emai
l
Date
of B
id O
peni
ng
No
Obj
ectio
n Le
tter
from
Wor
ld B
ank
Anno
unce
men
t of B
id W
inne
r
1. Ir. Lukman MuizziJl. Poltek Grya Mitra A-5 RT07/RW 02, Bukit Lama,Palembang
Lecturer of MuhammadiyahPalembang University
2. Ir. WahidinPerum Politeknik NegeriSriwijaya
Lecturer of Politeknik NegeriSriwijaya
1. Ir. Masril Syukur, M.ScJl. Handayani I No. 11,Steba, Padang
Head Admission of ProcurementConstruction Committee ofAndalas University
2. Darwizal Daoed, MTKomplek Pelangi Indah BlokC4/4, Kuranji, Padang
Lecturer of Andalas University
1. Ir. Jafril Tanjung,MT.,DR.,Eng
Jl. Banuaran Gg. MesjidRaya No. 47, Padang
Lecturer of Andalas University
2. Prof. Dr. Ir. Zaidir,MSKomp. Cendana Perak KopiBlok A-9, Padang
Head of Procurement ServicesUnit of Andalas University
1. Sartika Nisumanti,ST.,MT
Jl. Anggrek Raya No. 629,Palembang
Lecturer of Indo Global MandiriUniversity
2. Ir. ZainuddinMuchtar,MT
Jl. Putri Kembang Dadar No.110, B. Sibuntang,Palembang
Lecturer of Politeknik NegeriSriwijaya
1. Ir. Yohanes MartonoHadi, MT
Jl. Bungur No. 3/4 Blok TC1, Way Halim Permai,Tanjung Karang, BandarLampung
Lecturer of Lampung University
2. Ofik Taufik Purwadi,ST.,MT
Jl. Z.A. Pagar Alam No. 26,Bandar Lampung
Lecturer of Lampung University
May23,
2013
CRO
's Ad
dres
s
CRO's Contact
CRO
's O
ccup
atio
n
CRO Selection and Training
Appendix 6. List of Names of Community Representative Observers (CRO)
May17,
2013
BBPJN III Office, Jl. H. M.Noerdin Pandji No. 78
Palembang
July18,
20131 Lampung 01 Krui - Biha
Date
of I
nvita
tion
to B
id
CRO'sInvolvement
in Bidding
ReportsRelated to
CRO'sActivity
No
Prov
ince
Nam
e of
Sel
ecte
d CR
O
PackageObserved
May 23,2013
May 27,2013
BBPJN II Office, Jl. JatiNo. 109 Padang
May20,
2013
July18,
2013
3West
Sumatera03
Manggopoh -Pd. Sawah
May 27,2013
May 27,2013
BBPJN II Office, Jl. JatiNo. 109 Padang
2West
Sumatera02
Pd. Sawah -Simp. Empat
May 27,2013
Sept 18,2013
Sept 18,2013
Sept 18,2013
Nov 12,2013
Nov 26,2013
Nov 26,2013
Oct 28,2013
July 17,2014
Satker PJN II Office, Jl.Wolter Mongonsidi No.220 B, Bandar Lampung
5 Lampung 17
Sp. GunungKemala -PugungTampak
July 17,2014
Sept 18,2013
May 23,2013
BBPJN III Office, Jl. H. M.Noerdin Pandji No. 78
Palembang
May20,
2013
July18,2013
May17,2013
July18,2013
4 Bengkulu 04 Ipuh - BantalMay 23,
2013
Aug15,
2014
No.
Pac
kage
Pack
age
Sele
ctio
n Da
te
Trai
ning
Dat
e
Loca
tion
Tele
phon
e
Emai
l
Date
of B
id O
peni
ng
No
Obj
ectio
n Le
tter
from
Wor
ld B
ank
Anno
unce
men
t of B
id W
inne
r
CRO
's Ad
dres
s
CRO's Contact
CRO
's O
ccup
atio
n
CRO Selection and Training
Date
of I
nvita
tion
to B
id
CRO'sInvolvement
in Bidding
ReportsRelated to
CRO'sActivity
No
Prov
ince
Nam
e of
Sel
ecte
d CR
O
PackageObserved
1. Medis SejahteraSurbakti, ST., MT
Jl. Perpustakaan No. 1,University of NorthSumatera. 081396565879
Lecturer of University of NorthSumatera
2. Josep Admika Ginting,ST
Jl. Industri No. 75, TanjungMorawa. 0811638886
Trainer
1. Hesti Aulia SariJl. Mahakam Raya No. 27Rt. 9 Rw. 3, Kota Bengkulu. 085266724618
Assisstant of Lecturer of BengkuluUniversity
2. Rendesti Nofy Yelizar
Jl. R.A. Kartini Rt. 7 No. 01,Bengkulu Utara. 081373447043
Assisstant of Lecturer of BengkuluUniversity
1. Hot Maria Angelina
Jl. Beo No. 60 Rt. 05 Rw. 02,Perumnas Lingkar Barat,Bengkulu.
Assisstant of Lecturer of BengkuluUniversity
2. Muhammad Fauzi, ST.,MT
Rt. 14 Rw. 3, PematangGubernur, MuaraBangkahulu, Bengkulu.
Lecturer of BengkuluUniversity
Satker PJN I Bengkulu, Jl.Ir. Rustandi Sugianto Km.
12+225, Pulau Baai,Bengkulu
Sept 1,2014
Sept 1,2014
Aug 20,2014
BBPJN I Office, Jl. SaktiLubis No. 1, Medan
7 Bengkulu 11Bantal -
Mukomuko
6Sumatera
Utara05
Sp. Rampa -Poriaha
Aug 20,2014
Sept22,
2014
Oct 3,2014
Aug 22,2014
Sept 1,2014
Satker PJN I Bengkulu, Jl.Ir. Rustandi Sugianto Km.
12+225, Pulau Baai,Bengkulu
Aug 22,2014
Oct 3,2014
8 Bengkulu 13Sp. Rukis -
TanjungKemuning
Sept 1,2014
No ProvinceNo.
PackagePackage Name of Selected CRO Occupation
1. Ir. Lukman Muizzi Lecturer of Muhammadiyah Palembang University
2. Ir. Wahidin Lecturer of Politeknik Negeri Sriwijaya
1. Ir. Masril Syukur, M.Sc Head Admission of Procurement Construction Committee of Andalas University
2. Darwizal Daoed, MT.,DR.,Eng Lecturer of Andalas University
1. Ir. Jafril Tanjung,MT.,DR.Eng Lecturer of Andalas University
2. Prof. Dr. Zaidir, MS Head of Procurement Services Unit of Andalas University
1. Sartika Nisumanti, ST.,MT Lecturer of Indo Global Mandiri University
2. Ir. Zainuddin Muchtar, MT Lecturer of Politeknik Negeri Sriwijaya
1. Ir. Yohanes Martono Hadi, MT Lecturer of Lampung University
2. Ofik Taufik Purwadi, ST.,MT Lecturer of Lampung University
1. Medis Sejahtera Surbakti, ST., MT Lecturer of University of North Sumatera
2. Josep Admika Ginting, ST Trainer
1. Hesti Aulia Sari Assisstant of Lecturer of Bengkulu University
2. Rendesti Nofy Yelizar Assisstant of Lecturer of Bengkulu University
1. Hot Maria Angelina Assisstant of Lecturer of Bengkulu University
2. Muhammad Fauzi, ST., MT Lecturer of Bengkulu University
4 Bengkulu 04 Ipuh - Bantal
3 West Sumatera 03Manggopoh - Pd.
Sawah
2 West Sumatera 02Pd. Sawah - Simp.
Empat
1 Lampung 01 Krui - Biha
5 Lampung 17Sp. Gunung Kemala -
Pugung Tampak
6 Sumatera Utara 05Sp. Rampa -
Poriaha
8 Bengkulu 13Sp. Rukis - Tanjung
Kemuning
7 Bengkulu 11 Bantal - Mukomuko
No Province No.Package
Package SelectionDate
TrainingDate
Location Remarks
5 Lampung 17
SP. GunungKemala -PugungTampak
July 17, 2014July 17,
2014Satker PJN II Office, Jl. Wolter Mongonsidi No. 220 B, Bandar
LampungAttended by 2 candidates from Lampung University, 1 candidate be the Primary CRO and anotherbe the Secondary CRO. CRO Training was held directly after the selection process.
6 NorthSumatera
05Sp. Rampa -
PoriahaAug 20,
2014Aug 20,
2014BBPJN I Office, Jl. Sakti Lubis No. 1, Medan
Attended by 2 candidates, one from University of North Sumatera and another from EngineeringLearning and Training Center (ELTC). The Primary CRO is the one from University of NorthSumatera, and the Secondary CRO is the one from ELTC. CRO Training was held directly after theselection process.
7 Bengkulu 11Bantal -
MukomukoSept 1, 2014
Sept 1,2014
Attended by 4 candidates from Bengkulu University. For Package number 11, a Primary CRO and aSecondary CRO selected from Bengkulu University. CRO Training was held directly after theselection process.
8 Bengkulu 13Sp. Rukis -Tanjung
KemuningSept 1, 2014
Sept 1,2014
Attended by 4 candidates from Bengkulu University. For Package number 13, a Primary CRO and aSecondary CRO selected from Bengkulu University. CRO Training was held directly after theselection process.
Satker PJN I Bengkulu, Jl. Ir. Rustandi Sugianto Km. 12+225,Pulau Baai, Bengkulu
4 Bengkulu 04
1 Lampung 01
2West
Sumatera02
May 23,2013
May 23,2013
May 27,2013
May 23,2013
Krui - Biha
Pd. Sawah -Simp. Empat
Ipuh - Bantal BBPJN III Office, Jl. H. M. Noerdin Pandji No. 78 Palembang
Attended by 6 candidates, 2 candidates from Politeknik Negeri Sriwijaya, 1 candidate fromMuhammadiyah Palembang University, 2 candidates from Indo Global Mandiri PalembangUniversity, and 1 candidate from Palembang University. For Package number 01, a Primary CROselected from Muhammadiyah Palembang University and a Secondary CRO selected from PoliteknikNegeri Sriwijaya. CRO Training was held directly after the selection process.
Attended by 4 candidates from Andalas University. For Package number 02, a Primary CRO and aSecondary CRO selected from Andalas University. CRO Training was held directly after the selectionprocess.
Attended by 4 candidates from Andalas University. For Package number 03, a Primary CRO and aSecondary CRO selected from Andalas University. CRO Training was held directly after the selectionprocess.
Attended by 6 candidates, 2 candidates from Politeknik Negeri Sriwijaya, 1 candidate fromMuhammadiyah Palembang University, 2 candidates from Indo Global Mandiri PalembangUniversity, and 1 candidate from Palembang University. For Package number 04, a Primary CROselected from Indo Global Mandiri University and a Secondary CRO selected from Politeknik NegeriSriwijaya. CRO Training was held directly after the selection process.
BBPJN III Office, Jl. H. M. Noerdin Pandji No. 78 Palembang
BBPJN II Office, Jl. Jati No. 109 Padang
May 23,2013
May 27,2013
3West
Sumatera03
Manggopoh - Pd.Sawah
Date ofBid
Opening
AnnouncementDate of Bid
Winner
1 Lampung 01 Krui - BihaMay 17,
2013July 18,
2013Nov 12, 2013
1. Attending Pre-Bid Meeting on June 10, 2013, and Site Visit on June 13, 2013.2. Attending Bid Opening on July 18, 2013.
2 West Sumatera 02Pd. Sawah -Simp. Empat
May 20,2013
July 18,2013
Nov 26, 20131. Attending Pre-Bid Meeting on June 10, 2013, and Site Visit on June 11, 2013.2. Attending Bid Opening on July 18, 2013.
3 West Sumatera 03Manggopoh -
Pd. SawahMay 20,
2013July 18,
2013Nov 26, 2013
1. Attending Pre-Bid Meeting on June 10, 2013, and Site Visit on June 11, 2013.2. Attending Bid Opening on July 18, 2013.
4 Bengkulu 04 Ipuh - BantalMay 17,
2013July 18,
2013Oct 28, 2013
1. Attending Pre-Bid Meeting on June 10, 2013, and Site Visit on June 13, 2013.2. Attending Bid Opening on July 18, 2013.
5 Lampung 17SP. Gunung
Kemala -Pugung Tampak
Aug 15,2014
1. Attending Pre-Bid Meeting on July 18, 2014, and Site Visit on July 19, 2014.2. Attending Bid Opening on August 15, 2014.
6 North Sumatera 05Sp. Rampa -
PoriahaSept 22,
20141. Attending Pre-Bid Meeting on August 21, 2014, and Site Visit on August 22, 2014.2. Attending Bid Opening on Sepetmber 22, 2014.
7 Bengkulu 11Bantal -
MukomukoOct 3, 2014
1. Attending Pre-Bid Meeting on September 8, 2014, and Site Visit on September 9, 2014.2. Will be attending Bid Opening on October 3, 2014.
8 Bengkulu 13Sp. Rukis -Tanjung
KemuningOct 3, 2014
1. Attending Pre-Bid Meeting on September 8, 2014, and Site Visit on September 9, 2014.2. Will be attending Bid Opening on October 3, 2014.
Reports of CRO Activity
CRO's Involvement in theBidding ProcessNo Province
No.Package
PackageDate of
Invitationto Bid
APPENDIX 7
Anti Corruption Action Plan (ACAP)
Activity Progress of Community Representative Observers(CRO)
Monthly Progress Report September 2014
Western Indonesia National Roads Improvement Project
Appendix 7 ACAP Activity ProgressActivities Progress of Community Representative Observers (CROs)
from January 2013 – September 2014 and the Works Plan
No Subject of Activities Date of Finish/completed
1. Orientation and studied of WINRIP documents and Development of Works Plan January 2013
2 Prepared of Workshop of Procurement Document Evaluation. February 2013
3. Conducted Workshop of Procurement Document Evaluation for POKJA, Satker/PPK,Balai BBPJN and PMU.
Febr. 28, 2013 –March 01, 2013
4. Provided of Term of Reference (TOR) of the CRO's Selection and Guidelines for CRO’sSelection
March 1, 2013
5. Provided the Materials (Slide Presentation/Power-point) of General Explanationsabout WINRIP and the CRO’s selection and
March 8, 2013
6. Provided Training Materials for CROs. March 8, 2013
7. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director ofPlanning as Chairman of PMU to Head of BBPJN II & III, about the Selection ofCROs/WPM, + TOR and Guidelines Document
March 11, 2013
8 Preparation of Socialization on CROs selection in BBPJN II Padang for package 02Padang Sawah – Simpang Empat and package 03 Manggopoh - Padang Sawah, andSocialization on CROs selection in BBPJN III Palembang for package 01 Krui – Biha andpackage 04 Ipuh – Bantal.
March 31, 2013
9. Socialization on CROs selection in BBPJN II Padang for package 02 Padang Sawah –Simpang Empat and package 03 Manggopoh - Padang Sawah
April 9, 2013
10 Socialization on CROs selection in BBPJN III Palembang for package 01 Krui – Biha andpackage 04 Ipuh – Bantal.
April 11, 2013
11. Sent the Invitation letter from Head of BBPJN III to Rector of Universities /Head ofColleges in Palembang, about selection of the CROs for package 01. Krui – Biha (Prov.Lampung) and package 04. Ipuh – Bantal (Prov. Bengkulu).
May 17, 2013
12. Sent the Invitation letter from Head of BBPJN II to Rector of Universities /Head ofColleges in Padang, about selection of the CROs for package 02. Padang Sawah –Simpang Empat and package 03. Manggopoh - Padang Sawah (Prov. Sumatera Barat).
May 20, 2013
13. Selection of CROs for Packages Krui – Biha Province Lampung and Ipuh – BantalProvince Bengkulu, and training for selected CROs in BBPJN III Palembang
May 23, 2013
14. Selection of WPM/CROs for Packages Manggopoh – Padang Sawah and Padang Sawah– Simpang Empat, and training for selected CROs in BBPJN II Padang
May 27, 2013
15. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director ofPlanning as Chairman of PMU to Head of BBPJN II & III, about the Selection ofCROs/WPM, + TOR and Guidelines Document
May 28, 2013
16. Guiding the Balai Besar Pelaksanaan Jalan Nasional (Balai) II Padang to compose theApplication Letter for Approval of selected CROs for Package 03. Manggopoh – PadangSawah, package 02. Padang Sawah – Simpang Empat, and Balai III Palembang forPackage 01. Krui – Biha Province Lampung and Package 04. Ipuh – Bantal ProvinceBengkulu.
May 29, 2013
17. Compiling summary of the results of Selection the Community RepresentativeObservers (CROs)/ Wakil Pengamat dari Masyarakat (WPM) and the Training activitiesfor selected CROs for four Packages AWP-1
June 1 - 9, 2013
Monthly Progress Report September 2014
Western Indonesia National Roads Improvement Project
No Subject of Activities Date of Finish/completed
18. Assist PMU to prepare the Approval letter of selected CROs for four AWP-1 Packages,and prepare of the Decree on Establishment the CROs of AWP-1 WINRIP from Directorof Planning DGH, as the Chairman of PMU.
June 1 - 9, 2013
19. Monitor and observation the Pre-Bid Meeting and Site Visit activities of ProcurementProcess that held by the Procurement Committee, in BBPJN II and III, on 10 June 2013by CROs in implementing their tasks on the
June 10 - 16,2013
20. Evaluate of the CROs observation on Pre-Bid Meeting and Site Visit activities June 17 - 23,2013
21. Examine the report of CROs on the monitoring and observation of Pre-Bid Meetingand Site Visit at the packages of Annual Works Program - 1 (AWP-1) WINRIP.
Modify the template of monitoring the report of the CROs, to be more focused andmore systematically
June 24 - 30,2013
22. Monitor /Observe of Bids Submission and Bids Opening for four packages AWP-1 byCommunity Representative Observers (CROs) for Package 01, 02, 03, and 04
July 18, 2013
23. Monitoring and examined of the CRO’s Report on the monitoring and observation ofBid Submission and Bid Opening activities for four packages of Annual Works Program- 1 (AWP-1) WINRIP, which have been carried out on July 18, 2013
August, 2013
24 Preparation on the Socialization of CROs selection to the Procurement Committee(POKJA) of Sumatera Utara province, for package Simpang Rampa – Poriaha andpackage Sibolga – Batas Tapanuli Selatan
October 2013
25 Monitored /Observed of Procurement progress on Commencement of Bid Winnersfor four packages AWP-1 (Package 01, 02, 03, and 04) and informed to relatedCommunity Representative Observers (CROs).
November 2013
26 Carried out the dissemination of CROs selection to the Procurement Committee(POKJA) of Sumatera Utara province, for package Simpang Rampa – Poriaha. in Balai(BBPJN) I Medan and in Project Management (Satker) Office.
November 19 –20, 2013
27 Carried out the CROs selection for package 17: Simpang Gunung Kemala – PugungTampak in Lampung..
July 17, 2014
28 The CRO of package 17, Mr. Ir. Yohanes Martono Hadi, MT was attended the Pre-BidMeeting.
July 18, 2014
29 The CRO of package 17, Mr. Ir. Yohanes Martono Hadi, MT was attended the BidOpenin Meeting.
August 15, 2014
30 Carried out the CROs selection for package 05: Simpang Rampa – Poriaha in NorthSumatera province.
August 20, 2014
31 The CROs of package 05, Mr. Medis Sejahtera Surbakti ST, MT, was attended the Pre-Bid Meeting.
August 21, 2014
32 Carried out the CROs selection for package 11: Bantal – Mukomuko, and package 13:Simpang Rukis – Tanjung Kemuning in Bengkulu province.
Sept. 1, 2014
33 The CROs of package 11, Ms. Hesti Aulia Sari, ST was attended the Pre-Bid Meeting. Sept. 8, 2014
34 The CROs of package 13, Ms. Hot Maria Angelina, ST was attended the Pre-BidMeeting.
Sept. 8, 2014
35 The CROs of package 05, Mr. Medis Sejahtera Surbakti ST, MT, was attended the BidOpening Meeting.
Sept. 22, 2014
Monthly Progress Report September 2014
Western Indonesia National Roads Improvement Project
Works Plan for the next steps of CROs subject activities
No Subject of Activities Datelines Plan /Actual condition
1. Assist PMU to prepare the Decree on Establishment the CRO by Director of PlanningDGH, as the Chairman of PMU for package 17: Simpang Gunung Kemala – PugungTampak, package 05: Simpang Rampa – Poriaha, Package 11: Bantal – Mukomuko,and package 13: Simpang Rukis – Tanjung Kemuning
October 2014
APPENDIX 8
List of Appointed Third Party Monitors (TPM)
I II III I II III IV V VI VII VIII I II III Final
1. Dr. Ir. Hery RiyantoJl. Duku D2 No. 9, Kel.Beringin Raya, Kemiling-Bandar Lampung
08127218266 [email protected] of BandarLampungUniversity
2. Ir. Sugito, MTJl. Sukardihamdani, Palapa5A No. 29A, BandarLampung
08218143644 [email protected] of BandarLampungUniversity
3. Ir. Juniardi, MTJl. U. Surapati Gg.Mataram No. 1, BandarLampung
085225168058 [email protected]
Head Departmentof Civil Engineeringof Bandar LampungUniversity
1. Syaiful Amri,SST., MTJl. Andalas Gg. Sarga IndahNo. 43, Padang
Lecturer ofPoliteknik NegeriPadang
2. Ir. Syaifullah Ali,MTKomp. Pelangi Indah B5/5Korong Gadang, Kuranji
Lecturer ofPoliteknik NegeriPadang
3. Ir. Riswandi, M.SIJl. Lubuk Bayu No. 1Kurao, Pagang Nanggalo,Padang
Lecturer ofPoliteknik NegeriPadang
1. Ir.M. Nursyaifi Yulius,MTJl. Gadih Rantih Ujung No.20 B, Padang
08126608128 [email protected] of BungHatta University
2. Alzahri, ST.,MTKomp. Polamas Blok W5,Alai Parak Kopi, Padang
08126721639 [email protected] of BungHatta University
3. Ir. Heldi, M.ScParak Jigarang No. 1/3 RT03/05 Kuanji, Padang
Lecturer of BungHatta University
1. Muhammad Fauzi,ST.,MTRT 014/RW 003, PematangGubernur-MuaraBangkahulu, Bengkulu
Lecturer ofBengkuluUniversity
2. Hardiansyah, ST.,MTRT01/RW 004 SumurDewa-Slebar, Bengkulu
Lecturer ofBengkuluUniversity
3. Agung Febrianto,STRT 02/RW 003, DwiTunggal - Curup Utara,Bengkulu
Lecturer staff ofBengkuluUniversity
Reports Related toTPM's ActivityNo
Prov
ince
No.
Pac
kage
Pack
age
Nam
e of
Sel
ecte
dTP
M
Sele
ctio
n Da
te
Trai
ning
Dat
e
Satker PJN I Office,Jl. Ir. Rustandi
Sugianto Km 12+225,Pulau Baai-Bengkulu
Site Visit Coordination Meeting
Loca
tion
TPM
's Ad
dres
s
Tele
phon
e
Emai
l
Satker PJN I Office,Jl. Khatib Sulaiman
No. 9, Padang
TPM
's O
ccup
atio
n TPM Involvement
Pd. Sawah -Simp. Empat
March 7,2014
July 7-8,2014
3West
Sumatera03
Manggopoh - Pd.Sawah
March 7,2014
June 18-19,2014
4 Bengkulu 04 Ipuh - BantalMarch 10,
2014
Appendix 8. List of Names of Third Party Monitoring (TPM)
Package Observed TPM Selection and TrainingTPM Contact
June 18-19,2014
Satker PJN I, Jl.Khatib Sulaiman No.
9, Padang
1 Lampung 01 Krui - BihaMarch 5,
2014June 5-6,
2014
Satker PJN II Office,Jl. W. R. Mongonsidi
No. 220 B, BandarLampung
2West
Sumatera02
No ProvinceNo.
PackagePackage Name of Selected TPM Occupation
1. Dr. Ir. Hery Riyanto Lecturer of Bandar Lampung University
2. Ir. Sugito, MT Lecturer of Bandar Lampung University
3. Ir. Juniardi, MT Head Department of Civil Engineering of Bandar Lampung University
1. Syaiful Amri,SST., MT Lecturer of Politeknik Negeri Padang
2. Ir. Syaifullah Ali,MT Lecturer of Politeknik Negeri Padang
3. Ir. Riswandi, M.SI Lecturer of Politeknik Negeri Padang
1. Ir.M. Nursyaifi Yulius,MT Lecturer of Bung Hatta University
2. Alzahri, ST.,MT Lecturer of Bung Hatta University
3. Ir. Heldi, M.Sc Lecturer of Bung Hatta University
1. Muhammad Fauzi,ST.,MT Lecturer of Bengkulu University
2. Hardiansyah, ST.,MT Lecturer of Bengkulu University
3. Agung Febrianto,ST Lecturer staff of Bengkulu University
3 West Sumatera 03Manggopoh - Pd.
Sawah
4 Bengkulu 04 Ipuh - Bantal
2 West Sumatera 02Pd. Sawah - Simp.
Empat
1 Lampung 01 Krui - Biha
No ProvinceNo.
PackagePackage
SelectionDate
LocationTraining
DateLocation Remarks
1 Lampung 01 Krui - BihaMarch 5,2014
Satker PJN II Office, Jl. W. R.Mongonsidi No. 220 B, BandarLampung
June 5-6,2014
Satker PJN II Office, Jl. W. R. Mongonsidi No. 220B, Bandar Lampung
4 Bengkulu 04 Ipuh - BantalMarch 10,2014
Satker PJN I Office, Jl. Ir. RustandiSugianto Km 12+225, Pulau Baai-Bengkulu
July 7-8,2014
Satker PJN I Office, Jl. Ir. Rustandi Sugianto Km12+225, Pulau Baai-Bengkulu
June 18-19,2014
BBPJN II Office, Jl. Jati No. 109 Padang
3
Satker PJN I Office, Jl. KhatibSulaiman No. 9 Padang
2West
Sumatera02
Pd. Sawah -Simp. Empat March 7,
2014WestSumatera
03Manggopoh -
Pd. Sawah
I II III I II III IV V VI VII VIII I II III Final
1. Dr. Ir. Hery Riyanto
2. Ir. Sugito, MT
3. Ir. Juniardi, MT
1. Syaiful Amri,SST., MT
2. Ir. Syaifullah Ali,MT
3. Ir. Riswandi, M.SI
1. Ir.M. Nursyaifi Yulius,MT
2. Alzahri, ST.,MT
3. Ir. Heldi, M.Sc
1. Muhammad Fauzi,ST.,MT
2. Hardiansyah, ST.,MT
3. Agung Febrianto,ST
No.Package
Package Coordination Meeting
4 Bengkulu 04 Ipuh - Bantal
3West
Sumatera03
Manggopoh -Pd. Sawah
2West
Sumatera02
Pd. Sawah -Simp. Empat
Site Visit
1 Lampung 01 Krui - Biha
TPM Involvement
Reports of TPMActivityName of Selected TPMNo Province
APPENDIX 9
Progress of Third Party Monitoring (TPM) Activities
Monthly Progress Report September 2014
Western Indonesia National Roads Improvement Project
Appendix 9The Progress of Third Party Monitoring (TPM) Activities
January 2013 – September 2014 and Works Plan for Next Steps
No Subject of Activities Target Completed
1. Preparation the initial draft of ToR of selection the TPM Dec, 2013 Dec, 2013
2. Providing the TPM selection guidelines. Dec, 2013 Dec, 2013
3. Providing the Training Materials for the TPM Dec, 2013 Dec, 2013
4.Preparing the official letter from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection ofTPM.
Jan, 2014 Jan. 24, 2014
5. Preparing the official letter from the Director of Planning asChairman of PMU to Universities, about the Selection of TPM. Jan., 2014 Jan 29, 2014
Preparing the official letter from the Official in Charge/KetuaPelaksana Harian PMU to Satker/PPK, about the Selection of TPM Jan, 2014 Jan 13, 2014
5.Preparing the official letter from the Official in Charge/KetuaPelaksana Harian PMU to Universities and Satker/PPK, about theSocialization of TPM Selection for Package 01, 02, & 03
Feb. 2014 Feb. 07, 2014Feb. 13, 2014
6. Socialization of the TPM selection for package 01: Krui - Biha. Feb. 2014 Febr. 14, 2014
7. Socialization of the TPM selection for package 02: Padang Sawah –Simpang Empat and package 03: Manggopoh – Simpang Empat Feb. 2014 Febr. 18, 2014
8.Preparing the official letter from the Director of Planning asChairman of PMU to University of Bengkulu, about the Selection ofTPM for package 04: Ipuh - Bantal.
Jan, 2014 Febr. 19, 2014
9. Help the PMU on formulating the TPM Evaluation Team March 2014 Febr. 25, 2014
10. Implementation of selection of the TPM for four AWP-1 packages byTPM Evaluation Team March 2014 March 10, 2014
11. Delivery of the Preparatory Training for elected TPM for package 01:Krui – Biha in Lampung June 2014 June 5 - 6, 2014
12.Delivery of the Preparatory Training for elected TPM for package 02:Padang Sawah – Simpang Empat, and package 03: Mangopoh –Padang Sawah in West Sumatera
June 2014 June 17-18, 2014
13. Delivery of the Preparatory Training for elected TPM for package 04:Ipuh – Bantal in Bengkulu July 2014 July 7 – 8, 2014
14 Approval process of elected TPM July 2014 July 7 – 8, 2014
15Signing of the Decree on Establishment the TPM of AWP-1 WINRIP(Packages 01, 03, and 04) by Director of Planning DGH, as theChairman of PMU.
August 2014 Sept. 1, 2014
16 Signing letter of Employment Agreement and mobilization of TPM October 2014
APPENDIX 10
Complaints Handling Mechanism System (CHS)
Western Indonesia National Roads Improvement Project
Appendix 10
Works Plan on Complaints Handling Mechanism System (CHS) Activities.
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
1 Review of Minister Decree of Public Works No. 323/2005 concerning theprocedures of Handling input from communities on the environment of theMinistry of Public Works.
April 18, 2013
2 Preparation of Complaints Register and the complaints address (developing of website of WINRIP) and provided ACAP to inputting data in the web site.
Completed on themiddle of Feb. 2014.
3 Preparation of Complaint Handling Procedure (already available on the WINRIPwebsite with the URL address http://chs.winrip-ibrd.com).
April 2014
4 The completion of the Initial investigation of a complaint Procedure, and theprocedure for the investigation of Complaints, as well as the conclusion ofinvestigation (already available on the WINRIP website with the URL addresshttp://chs.winrip-ibrd.com).
April 2014
5 The establishment of the settlement Commission Handling the Complaint underthe Inspectorate General of the Ministry of Public Works (Executing Agency)
May, 2014
6 Preparation of the device for Executing Agency such as: Proceduresannouncement of penalties, procedures for the annual Survey, Procedure AnnualIndependent Review, the process of Auctions
May, 2014
7 The development of a code of conduct and actions for Implementing Institutions/Implementing Agency (Bidders, Suppliers, contractors and Consultants)
May, 2014
8 Support the PMU in the Management and Monitoring of the implementationpolicy in handling public complaints
May, 2014
9 We conducted to socialization of the CHS (Complaint Handling System) applicationin the TPM (Third Party Monitoring) training for the ACAP activities. Thesocialization process is conducted at 3 times in Bandar Lampung, Padang andBengkulu. To follow up this socialization activities, the BBPJN 1 and 2 are requiredto disseminate that information to the public. The BBPJN 1 and 2 can take thistraining modules as a dissemination materials to the public.
June-July, 2014
10 We also did a presentation of public complaints mechanism using the CHSapplication at the socialization of PMM WINRIP revision 1 in Padang.
September, 2014
APPENDIX 11
Work Activities On Publication/Disclosure
Appendix 11
Works Activities on Publication / Disclosure Activities
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
1 Conducted Workshop of Procurement Document Evaluation for POKJA,Satker/PPK, Balai BBPJN and PMU
February 28, 2013– March 01, 2013
2 Conducted Workshop of World Bank Guidelines of Procurement forWINRIP to the POKJA, Satker/PPK, Balai BBPJN and PMU
April 24 – 25, 2013
3 Review training materials on Project Management Manual (PMM),especially CHAPTER XI of the anti-Corruption Action Plan (ACAP)
First updating April 29, 2013
4 The second Review of training materials on Project Management Manual(PMM), Chapter I - XII
Second updating onDecember 18, 2013
5 The third Review of training materials on Project Management Manual(PMM), Chapter I - XII
third updating onApril, 2014
6. Preparing Method Transparency to the Public, and Improvement theprocedures to the Public Disclosure through information media (website).
Establishment of InformationSystem (MIS) was finish on
March 2014
7. The updating of Project Management Manual (PMM), Chapter 3, 9, 11, and13, has been held in Bogor June 2014
8 Delivery of the Preparatory Training for elected TPM for AWP-a packages:01, 02, and 03 June 2014
9 Delivery of the Preparatory Training for elected TPM for AWP-a packages:04
July 2014
10 The implementation of Dissemination/training of the PMM toStakeholders
September 10 - 11 2014
11 Delivery of PMM Training for PPK, contractors and Supervision Consultants(DSC)
PMM for Project Executorsafter the Work Order to the
Contractors
12 Delivering the training programs will inline of project implementationprogress.
Depend on projectimplementation progress
13Monitoring of the implementation of the methods and proceduresdisclosure and transparency of information to the public in each packetsthat has begun construction
2014
APPENDIX 12
Environmental Safeguards
Length Width
(Km) (m) Result ProjectCategory Comments Environmental Agency World Bank
AWP - 1
1 Krui - Bha Lampung 25 7 CapacityExpansion
SPPL &AMDAL (some
doc withpackage No.1)
C*) andA*)
Air pollution, trafficcongestion, steepsopes,slopes,sopt soil andrivers and beach, abrasion
YES(Recommended 2010)
AMDAL YES on 20November 2013 andSPPL Not Required
YES(Not completed a waiting
drawing from the contractor)
Padang Sawah - Sp Empat 40.9 7 CapacityExpansion
C*) andB*)
YES(Recommended 2010) Not Required Not Yet
Including Air Gadang Bridge 100 m 7 Replacement
3 Manggopoh - Padang Sawah Sumatera Barat 32 7 CapacityExpansion
SPPL
C*)one link,sensitive areas/resident,public,facilities, squater,market,sopt soil and rivers
YES(Recommended 2010) Not Required Not Required
4 Ipuh- Bantal Bengkulu 42.4 7 CapacityExpansion
SPPL &UKL&UPL
C*) andB*)
Geometric, traffic congestion,steep sopes,slopes,sopt soil andrivers
SPPL YES(Recommended 2010 &
2013) dan UKL&UPLUKL?UPL under process
environmental license by theBupati Muko-Muko (98%)
Not Required Not Yet
AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg. Tampak Lampung 36.8 6 CapacityExpansion
AMDAL (some docwith package No.1) A*)
sensitive areas/resident, landacquisition, steepsopes,slopes,sopt soil and riversand beach, abrasion
YES(Recommended 2012)
AMDAL YES NOLWB issued on 20November 2013
Not Yet
5 Sp. Rampa - Poriaha Sumatera Utara 9.7 6 CapacityExpansion UKL&UPL B*)
slope stability, water quality, Runoff, bridges acces, continuedtraffic access & quarry problem
YES(Recommended 2011) Not Required Not Yet
11 Bantal - Mukomuko Bengkulu 50.1 6 CapacityExpansion AMDAL A*)
Sensitive areas, social issues,market on the street, geometric,waste managemnt, continuedtraffic access, etc
YES(Recommended 2014)
AMDAL YES NOLWB issued 8
Aug 2014Not Yet
13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 CapacityExpansion UKL&UPL B*)
one link,sensitive/steepsopes,slopes,sopt soil and rivers,squater on the street, resident,productive land
YES(Recommended 2011) Not Required Not Yet
6 Ps Pedati - Kerkap Bengkulu 20.9 7 CapacityExpansion UKL&UPL B*)
Comersil areas, trafficcongestion, market on the street,air pollution & noise
YES(Recommended 2011) Not Required Not Yet
No. Package Loan Package Name PROVINSI
ENVIRONMENTAL SAFEGUARDS FOR WINRIP
As of September 2014
APPENDIX No; 12
Intergration of EnvironmentalMitigation Into The Design
2 Sumatera Barat
TypeEnvironmental and Social Screening Report Approval
SPPL&UKL/UPL
Bridge
one link,sensitive areas/resident,public,facilities, squater,market,sopt soil and rivers
Length Width
(Km) (m) Result ProjectCategory Comments Environmental Agency World Bank
No. Package Loan Package Name PROVINSI Intergration of EnvironmentalMitigation Into The DesignType
Environmental and Social Screening Report Approval
19 Lais- Bintunan Bengkulu 10.8 7 CapacityExpansion UKL&UPL B*)
one link,sensitive/air pollution,traffic congestion, squater on thestreet, etc
YES(Recommended 2011) Not Required Not Yet
15 Sibolga - Bts Tap Sel Sumatera Utara 36 7 CapacityExpansion UKL&UPL B*) resident, comersil areas, market
(pasar tumpah) geometric etcYES
(Recommended 2011) Not Required Not Yet
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 46.8 7 CapacityExpansion AMDAL A*)
Comersil areas, market, publicfacilities, Air pollution, trafficcongestion, market on street,sopt soil and rivers
YES(Recommended 2013)
AMDAL YES NOLWB issued 14
April 2014Not Yet
10 Sp Empat - Sp Air Balam Sumatera Barat 61.7 7 CapacityExpansion AMDAL A*)
Sensitive forest areas, socialissues, slope stability, waterquality, waste managemnt, bridgetraffic access & quarry problem
YES(Recommended 2013)
AMDAL YES NOLWB issued 14
April 2014Not Yet
7 Indrapura - Tapan Sumatera Barat 19.5 7 CapacityExpansion AMDAL A*)
Sensitive forest areas, socialissues, slope stability, waterquality, waste management, airpollution, squater on ROW etc
YES(Recommended 2014)
AMDAL YES NOLWB issued 8
Aug 2014Not Yet
12 Kambang - Indrapura Sumatera Barat 55.2 7 CapacityExpansion AMDAL A*)
Resident, productive land,Catcment areas,rivers, slopestability, squater on the street,land acquisition.
YES(Recommended 2014)
AMDAL YES NOLWB issued 8
Aug 2014Not Yet
14 Painan -Kambang Sumatera Barat 31.5 7 CapacityExpansion AMDAL A*)
Sensitive forest areas, socialissues, slope stability, waterquality, waste managemnt,continued traffic access & quarryproblem
YES(Recommended 2014)
AMDAL YES NOLWB issued 8
Aug 2014Not Yet
Seblat - Ipuh including 34.5 6 CapacityExpansion AMDAL A*) Not Yet
Air Lalang & Air Guntung Bridge 64 m 6 Twin bridges
20 Lubuk Alung - Sicincin Sumatera Barat 14.6 7 CapacityExpansion UKL&UPL B*)
sensitive areas/resident, landacquisition, steepsopes,slopes,sopt soil and rivers
YES(Recommended 2011) Not Required Not Yet
21 Lubuk Alung -Kurataji Sumatera Barat 16.8 7 CapacityExpansion UKL&UPL B*) one link,sensitive/steep
sopes,slopes,sopt soil and riversYES
(Recommended 2011) Not Required Not Yet
18 Mukomuko - Bts. Sumbar (rencanadiganti dengan Seblat - Ketahun) Bengkulu 25.8 6 Capacity
Expansion UKL&UPL B*)one link,sensitive/steepsopes,slopes,sopt soil and riversand abrasion on the Beach
YES(Recommended 2010) Not Required Not Yet
9 Rantau Tijang - Kota Agung (rencanadiganti dengan Tais - Betungan) Lampung 42 7 Capacity
Expansion UKL&UPL B*)
Sensitive areas, resident, airpollution, traffic congestion, steepsopes,slopes,sopt soil and riversand beach, abrasion
YES(Recommended 2012) Not Required Not Yet
AMDAL YES NOLWB issued 8
Aug 2014
sensitive areas/steepsopes,slopes,sopt soil and riversand beach, abrasion
YES(Recommended 2014)16 Bengkulu
APPENDIX 13
Environmental Management Plan (EMP) Compliance
APPENDIX 13
No. Package Loan Package Name PROVINSI Contractor Road SafetyMeasurement
Awareness &Readiness to EMP
DocumentsAvailability Camp Cleanliness Labour Camp Disposal of Waste
(Sludges)Handling of
BitumenPollution Control
Measures Vehicle Management Disposal ofWastewater
Total ScoreObtained Rangking (%) Level Remarks
AWP - 1
1 Krui - Bha Lampung PT.JACON x x 3 x x x x x x x x x
Padang Sawah - Sp Empat PT.JACON x x 2 x x x x x x x x x
Including Air Gadang Bridge
3 Manggopoh - Padang Sawah Sumatera Barat PT.JACON x x 2 x x x x x x x x x
4 Ipuh- Bantal Bengkulu Waskita Karya KSODMT x x 1 x x x x x x x x x
AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg. Tampak Lampung
5 Sp. Rampa - Poriaha Sumatera Utara
11 Bantal - Mukomuko Bengkulu
13 Sp Rukis - Tj Kemuning Bengkulu
6 Ps Pedati - Kerkap Bengkulu
19 Lais- Bintunan Bengkulu
15 Sibolga - Bts Tap Sel Sumatera Utara
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat
10 Sp Empat - Sp Air Balam Sumatera Barat
7 Indrapura - Tapan Sumatera Barat
12 Kambang - Indrapura Sumatera Barat
14 Painan -Kambang Sumatera Barat
Seblat - Ipuh including
Air Lalang & Air Guntung Bridge
20 Lubuk Alung - Sicincin Sumatera Barat
21 Lubuk Alung -Kurataji Sumatera Barat
18 Mukomuko - Bts. Sumbar (rencanadiganti dengan Seblat - Ketahun) Bengkulu
9 Rantau Tijang - Kota Agung (rencanadiganti dengan Tais - Betungan) Lampung
EMP Compliance on WINRIP (Up to 30 September, 2014)
Contractor Performance on EMP
16 Bengkulu
2 Sumatera Barat
APPENDIX 14
Status of Monitoring of Environmental Mitigation
Civil Work
APPENDIX No.14
Status as of September 2014
Length Width
(Km) (m)
AWP - 1
1 Krui - Bha Lampung 25 7 x x x x x _ _ _ _
The DSC conducted monitoring on package No.1: Krui-Biha from January to May 2014, Monitoring form on January to March 2014 no refer to CTC form, while form for April and May 2014 already use CTC form but notcompleted with Road and contract status,date, time, wether,location, then the contractor safeguard documents availability. The answer in the monitoring form on April and May 2014 is same (copy paste), should be the DSCmonitor relevant with civil work is being done by the contractor on April to May 2014. the base camp and quarry not yet operation on April to May 2014 so the row of base camp and quarry aspec is necessary no tick/no answerthen the DSC not comments for constrains when the contractor not implement the environmental mitigation for the activities, for example: Traffic aspec (traffic acident) and vegetation (loss of endemic trees and faunadisturbance. The DSC not conducted monitoring on environmental management by the contractor for package No1 on Aug to September 2014, CTC not receive yet the environmental monitoring report from DSC for Aug to Sep2014..
Padang Sawah - Sp Empat 40.9 7
Including Air Gadang Bridge 100 m 7 _ _ _ _ _ _ _ _ _
3 Manggopoh - Padang Sawah Sumatera Barat 32 7 _ _ _ _ _ _ _ _ _ The DSC not conducted monitoring on environmental management by the contractor for Aug to September 2014 and CTC not receive yet the environmental monitoring report from DSC for Aug to Sep 2014..
4 Ipuh- Bantal Bengkulu 42.4 7 _ _ _ _ _ _ _ _ _ The DSC not conducted monitoring on environmental management by the contractor for Aug to September 2014 and CTC not receive yet the environmental monitoring report from DSC for Aug to Sep 2014..
AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg.Tampak Lampung 36.8 6 Construction not yet started
5 Sp. Rampa - Poriaha Sumatera Utara 9.7 6 Construction not yet started
11 Bantal - Mukomuko Bengkulu 50.1 6 Construction not yet started
13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 Construction not yet started
6 Ps Pedati - Kerkap Bengkulu 20.9 7 Construction not yet started
19 Lais- Bintunan Bengkulu 10.8 7 Construction not yet started
15 Sibolga - Bts Tap Sel Sumatera Utara 36 7 Construction not yet started
8 Bts. Kota Pariaman -Manggopoh Sumatera Barat 46.8 7 Construction not yet started
10 Sp Empat - Sp Air Balam Sumatera Barat 61.7 7 Construction not yet started
PAKET WINRIP, IBRD LOAN NO. 8043-ID STATUS DAN JADWAL PELAKSANAAN
No. Package Loan Package Name PROVINSI Oct Nov RemarksJan DecFeb Mar Apr May Jun Jul Aug Sep
STATUS OF MONITORING OF ENVIRONMENTAL MITIGATION ON WINRIP YEAR 2014
The DSC not conducted monitoring on environmental management by the contractor for Aug to September 2014and CTC not receive yet the environmental monitoring report from DSC for Aug to Sep 2014..2 Sumatera Barat
Appendix 14_8B39B8
Length Width
(Km) (m)No. Package Loan Package Name PROVINSI Oct Nov RemarksJan DecFeb Mar Apr May Jun Jul Aug Sep
7 Indrapura - Tapan Sumatera Barat 19.5 7 Construction not yet started
12 Kambang - Indrapura Sumatera Barat 55.2 7 Construction not yet started
14 Painan -Kambang Sumatera Barat 31.5 7 Construction not yet started
Seblat - Ipuh including 34.5 6 Construction not yet started
Air Lalang & Air Guntung Bridge 64 m 6 Construction not yet started
20 Lubuk Alung - Sicincin Sumatera Barat 14.6 7 Construction not yet started
21 Lubuk Alung -Kurataji Sumatera Barat 16.8 7 Construction not yet started
18 Mukomuko - Bts. Sumbar (willreplace to others link in NorthSumatera)
Bengkulu 25.8 6 Construction not yet started
9 Rantau Tijang - Kota Agung(will replace to others link inNorth Sumatera)
Lampung 42 7 Construction not yet started
Notes : = Readiness 1 (DED telah tersedia dan DSC belum terkontrak sehingga pengkajian/review dilaksanakan oleh CTC).= Readiness 2 (DED telah tersedia dan DSC telah terkontrak sehingga pengkajian/review dilaksanakan oleh DSC).= Kondisi ruas jalan saat ini baik sehingga penanganan konstruksi diusulkan untuk ruas yang lain.
16 Bengkulu
Appendix 14_8B39B8
Civil Work
Length WidthIndicative Cost(PAD Apr 2011)
(excl. VAT)
OE/EE(Incl. VAT) DED
(Km) (m) (Rp Juta) (Rp Juta)1.Kegiatan2.Posisi3.Target
Dokumen1.Kegiatan2.Posisi3.Target
Dokumen1.Kegiatan2.Posisi3.Target
AlokasiDana
1.Kegiatan2.Posisi3.Target
Tandatangankontrak
SPMK Duration(months)
TOTAL(Rp. juta)
PHLN(Rp. juta)
PDP(Rp. juta)
TOTAL(Rp. juta)
PHLN(Rp. juta)
PDP(Rp. juta)
AWP - 1 71,608.68 49,053.86 22,554.82 116,037.22 34,727.83 81,309.39
1 Krui - Bha Lampung 25 7 148,668.00 163,534.86
DED SiapPPC WINRIP
Nov, 2010
SPPL A. OK P2JN2010 B.Persiapan trainingRKPPL pdKontraktor. CTarget. Des 2013
A. LARAPB. Lap. MonLARAP
A. NOL WB04Jan2013B. NOL WB18Apr2013
APBN, SatkerPJN II
Lampung
1.Pembayaran2. Sisa pekerj.renovasi 1 (satu)Mesjid3. Saat pelaks.Konstruksi
1.Bidding2.TT Kontrak 25November 20133.Kontrak Nov 13
Percepatan NOLDisbursementuntuk pencairanuang muka
14-Nov-13 06-Dec-13 21.00 13,796.13 9,336.09 4,460.04 24,904.57 11,019.57 13,885.00
ICB/Pre
Padang Sawah - Sp Empat 40.9 7
Including Air Gadang Bridge 100 m 7
3 Manggopoh - Padang Sawah SumateraBarat 32 7 152,434.90 209,171.00
DED SiapPPC WINRIP
Nov, 2010
SPPL A. OK P2JN2010B. Persiapan trainingRKPPL pdKontraktor.C Target. Des 2013
A. LARAPB. Lap. MonLARAP
A. NOL WB04Jan2013B. NOL WB18Apr2013
APBD Prop.Sumbar,Dinas PU
1.Pembayaran2. Sisa 16 WTP3.Sebelum kontrak
1.Bidding2.Rencana TTKontrak 05Desember 20133.Kontrak Nov 13
Percepatan NOLDisbursementuntuk pencairanuang muka
14-Nov-13 06-Dec-13 24.00 15,243.49 10,670.44 4,573.05 21,197.16 2,904.97 18,292.19
ICB/Pre
4 Ipuh- Bantal Bengkulu 42.4 7 226,275.10 253,698.61
DED SiapPPC WINRIP
Nov, 2010
SPPL A. OK P2JN2010B. Persiapan trainingRKPPL pdKontraktor.C Target. Des 2013
A. LARAPB. Lap. MonLARAP
A. NOL WB10/12/2012B. Prosespengump datapelaksanaanpembayaran
APBN, SatkerPJN I
Bengkulu
1.Pembayaran2. Data info drSatker 19 dari 199WTP telah dibyr.3.Sebelum kontrak
1.Bidding2.TT Kontrak 14November 20133.Kontrak Nov 13
Percepatan NOLDisbursementuntuk pencairanuang muka
14-Nov-13 06-Dec-13 24.00 21,449.06 14,530.01 6,919.05 29,725.59 5,480.21 24,245.38
ICB/Pre
AWP - 2 dan AWP - 3 118,058.92 78,615.41 39,443.51 126,237.45 67,480.04 58,757.41
17 Sp.Gunung Kemala - Pg. Tampak Lampung 36.8 6 104,238.00 255,269.30
DED SiapPPC WINRIP
Nov, 2010
AMDAL A. OK TLKJ 2012B. PenyusunanDesign integrasi isulingkungan.C Target. Des 2013
A. LARAPB. Lap. MonLARAP
A. NOL WB 16Sep 2013B. -PersiapanimplementasiLARAP
APBN, SatkerPJN IILampung
1. Koordinasi dgnPemda utkpembentukan TimApraisal2. PersiapanPengukuran3. November 2013
1. Proses prakualifikasi2. PengumumanPQ 11 Nov 20133. Pemasukan PQtgl 30 Des 2013
MonitoringLARAP, SBD
Jul-14 Aug-14 24.00 12,566.53 9,439.39 3,127.14 13,946.90 6,946.90 7,000.00
ICB/Pre
5 Sp. Rampa - Poriaha SumateraUtara 9.7 6 55,126.60 152,870.49
PersetujuanSubdit T JalanBintek T Jalan 17 Okt 2013
UKL/UPL A. OK BBPJN 2011B. PenyusunanDesign integrasi isulingkungan.C Target. Des 2013
A. SimpleLARAPB. Lap. MonLARAP
A. NOL WB 16Sep 2013B. -PersiapanimplementasiLARAP
APBN, SatkerPJN II Sumut
Pemindahanbangunan 1 kiospremium (1 WTP)paralel Pek.Fisik
1. Proses NOLDED & PQ Doku-men2. Persiapan PQ,NOL 18/113. PQ Des 2012
Perbaikan EEsesuai reviewBank, SBD,Monitoring LARAP
Jul-14 Aug-14 18.00 8,659.00 5,284.00 3,375.00 11,915.99 3,647.00 8,268.99
ICB/Pre
11 Bantal - Mukomuko Bengkulu 50.1 6 157,820.00 246,499.55
PersetujuanSubdit T JalanBintek T Jalan 11 Okt 2013
AMDAL Proses IzinLingkungan dariGubernur (98%)
LARAP A. Dok LARAPsiap.B. PengirimanDok.ke WB.C. Nol WB akhirNov 2013
APBN, SatkerPJN I
Bengkulu
1. Proses NOLLARAP2. Persiapansosialisasi3. Maret 2014
1. Proses NOLDED & PQ Doku-men2. Persiapan PQ,NOL 18/113. PQ Des 2012
Perbaikan EEsesuai reviewBank, SBD,Monitoring LARAP
Jul-14 Aug-14 24.00 9,881.14 6,120.00 3,761.14 13,721.11 9,251.91 4,469.20
ICB/Pre
13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 225,481.50 316,304.67
PersetujuanSubdit T JalanBintek T Jalan 11 Okt 2013
UKL/UPL A. OK P2JN 2011B. PenyusunanDesign integrasi isulingkungan.C Target. Des 2013
LARAP A. Dok LARAP.B. PengirimanDok.ke WB.C. Nol WB akhirNov 2013
APBN, SatkerPJN I
Bengkulu
1. Proses NOLLARAP2. Persiapansosialisasi3. Maret 2014
1. Proses NOLDED & PQ Doku-men2. Persiapan PQ,NOL 18/113. PQ Des 2012
Perbaikan EEsesuai reviewBank, SBD,Monitoring LARAP
Jul-14 Aug-14 21.00 15,116.99 9,529.00 5,587.99 18,234.41 13,284.74 4,949.67
ICB/Pre
6 Ps Pedati - Kerkap Bengkulu 20.9 7 72,018.80 88,541.26
PersetujuanSubdit T JalanBintek T Jalan 11 Okt 2013
UKL/UPL A. OK TLKJ 2011B. PenyusunanDesign integrasi isulingkungan.C Target. Des 2013
A. LARAPB. Lap. MonLARAP
A. Dok LARAP.B. PengirimanDok.ke WB.C. Nol WB akhirNov 2013
APBN, SatkerPJN I
Bengkulu
1. Proses NOLLARAP2. Persiapansosialisasi3. Maret 2014
1. Finalisasi NCB2. Revisi sesuaireview Bank3. 15 Des 2013
Perbaikan EEsesuai reviewBank, SBD,Monitoring LARAP
Mar-14 Apr-14 15.00 6,697.74 4,537.18 2,160.56 10,937.19 7,480.29 3,456.90
NCB/Post
19 Lais- Bintunan Bengkulu 10.8 7 37,558.00 33,515.22
PersetujuanSubdit T JalanBintek T Jalan 11 Okt 2013
UKL/UPL A. OK TLKJ 2011B. PenyusunanDesign integrasi isulingkungan.C Target. Des 2013
LARAP A. Dok LARAP.B. PengirimanDok.ke WB.C. Nol WB akhirNov 2013
APBN, SatkerPJN I
Bengkulu
1. Proses NOLLARAP2. Persiapansosialisasi3. Maret 2014
1. Finalisasi NCB2. Revisi sesuaireview Bank3. 15 Des 2013
Perbaikan EEsesuai reviewBank, SBD,MonitoringLARAP, AlokasiDIPA 2014
Mar-14 Apr-14 10.00 - - - - - -
NCB/Post
15 Sibolga - Bts Tap Sel SumateraUtara 36 7 129,228.00 272,551.18
Final RevisingConsultant P2Jn
UKL/UPL A. OK BBPJN I 2011B. PenyusunanDesign integrasi isulingkungan.C Target. Des 2013
A. LARAPB. Lap. MonLARAP
A. NOL WB 28Oct 2013 B.-PersiapanpenyusunandokumenMonitoringLARAP
APBN, SatkerPJN II Sumut
1. Persiapanpembentukan TimApraisal2. Persiapanpengukuran3. Koordinasidengan PemdaTapteng
1. Finalisasi DEDdg CTC & Bintek2. Menunggu hasifinal DED3. 15 Des 2013
Cost increase,160 Bilion, ReviewDED, Dok.LARAP,PembebasanLahan, SBD
May-14 Jun-14 30.00 6,000.00 4,000.00 2,000.00 15,154.73 7,354.73 7,800.00
ICB/Post
8 Bts. Kota Pariaman - Manggopoh SumateraBarat 46.8 7 183,268.80 161,963.37
Revisi II DED &EEPenyampaianrevisi oleh DSC10Nop2013.Proses final-isasiDED (DSC,CTC, Bintek)
AMDAL A. OK BBPJN II2013B. PenyusunanDesign integrasi isulingkungan.C Target. jan 2014
LARAP A. Revisi LARAPoleh P2JN sesuaiReview CTCB. -
APBD Prop.Sumbar,Dinas PU
PembebasanPemda Tk.I 15
Mei 2014
1. DokumenLelang oleh DSC
(ICB/Post)
DED, DokLARAP,PembebasanLahan, SBD
Apr-14 May-14 24.00 17,043.99 11,545.93 5,498.06 11,819.91 6,321.85 5,498.06
ICB/Post
10 Sp Empat - Sp Air Balam SumateraBarat 61.7 7 241,617.20 252,629.98
Revisi II DED &EEPenyampaianrevisi oleh DSC10Nop2013.Proses final-isasiDED (DSC,CTC, Bintek)
AMDAL A. OK BBPJN II2013B. PenyusunanDesign integrasi isulingkungan.C Target. jan 2014
LARAP A. Revisi LARAPoleh P2JN sesuaiReview CTCB. -
APBD Prop.Sumbar,Dinas PU
PembebasanPemda Tk.I 15
Mei 2014
1. DokumenLelang oleh DSC
(ICB/Post)
DED, DokLARAP,PembebasanLahan, DokLelang
Apr-14 May-14 24.00 21,970.40 15,221.88 6,748.52 11,782.39 4,533.87 7,248.52
ICB/Post
7 Indrapura - Tapan SumateraBarat 19.5 7 96,921.00 184,714.97
Revisi II DED &EEPenyampaianrevisi oleh DSC10Nop2013.Proses final-isasi
AMDAL Proses IzinLingkungan dariGubernur (98%)
SLARAP A. Revisi LARAPoleh Balai II PdgB. -
APBD Prop.Sumbar,Dinas PU
PembebasanPemda Tk.I 15
Mei 2014
1. DokumenLelang oleh DSC
(NCB/Post)
DED, DokLARAP,PembebasanLahan, SBD
May-14 Jun-14 21.00 8,632.68 6,106.02 2,526.66 3,600.65 693.02 2,907.63
NCB/Post
12 Kambang - Indrapura SumateraBarat 55.2 7 171,948.00 316,306.66
Revisi II DED &EEPenyampaianrevisi oleh DSC10Nop2013.Proses final-isasi
AMDAL Proses IzinLingkungan dariGubernur (98%)
LARAP A. Revisi LARAPoleh Balai II PdgB. -
APBD Prop.Sumbar,Dinas PU
PembebasanPemda Tk.I 15
Mei 2014
1. DokumenLelang oleh DSC
(ICB/Post)
DED, DokLARAP,PembebasanLahan, SBD
Apr-14 May-14 24.00 11,490.44 6,832.00 4,658.44 9,124.16 3,965.72 5,158.44
ICB/Post
14 Painan -Kambang SumateraBarat 31.5 7 118,993.00
PenyelesaianDED oleh DSCOct 15, 2013
AMDAL Proses IzinLingkungan dariGubernur (98%)
SLARAP A. Revisi LARAPoleh Balai II PdgB. -
APBD Prop.Sumbar,Dinas PU
PembebasanPemda Tk.I 1
Juli 2014
Revisi Dok PQ &Dok Lelang
DED, DokLARAP,PembebasanLahan
Jan-15 Feb-15 21.00 - - - - - -
NCB/Post
Seblat - Ipuh including 34.5 6
Air Lalang & Air Guntung Bridge 64 m 6
20 Lubuk Alung - Sicincin SumateraBarat 14.6 7 54,557.00
PenyelesaianDED oleh DSCOct 15, 2013
UKL/UPL A. OK TLKJ 2011B. PenyusunanDesign integrasi isulingkungan.C Target. jan 2014
SLARAP A. Revisi LARAPoleh Balai II PdgB. -
APBD Prop.Sumbar,Dinas PU
PembebasanPemda Tk.I 1
Pebr. 2014
Penyiapan Dok.Lelang NCB
DED, DokLARAP,PembebasanLahan
Jan-15 Feb-15 18.00 - - - - - -
NCB/Post
21 Lubuk Alung -Kurataji SumateraBarat 16.8 7 65,788.00
PenyelesaianDED oleh DSCOct 15, 2013
UKL/UPL A. OK TLKJ 2011B. PenyusunanDesign integrasi isulingkungan.C Target. jan 2014
SLARAP A. Revisi LARAPoleh Balai II PdgB. -
APBD Prop.Sumbar,Dinas PU
PembebasanPemda Tk.I 1
Pebr. 2014
Penyiapan Dok.Lelang NCB
DED, DokLARAP,PembebasanLahan
Jan-15 Feb-15 18.00 - - - - - -
NCB/Post
18 Mukomuko - Bts. Sumbar(rencana diganti dengan Seblat- Ketahun)
Bengkulu 25.8 6 69,233.00
PenyelesaianDED oleh DSC
UKL/UPL OK TLKJ 2011(Usulan screeningdokumen lingkung-an utk paket peng-ganti)
SLARAP A. PenyusunanLARAPB. -
Satker PJN IBengkulu
0% Penyiapan Dok.Lelang NCB
Review DED, DokLARAP,PembebasanLahan
Jan-15 Feb-15 18.00 - - - - - -
NCB/Post
9 Rantau Tijang - Kota Agung(rencana diganti dengan Tais -Betungan)
Lampung 42 7 149,831.50
PenyelesaianDED oleh DSC
UKL/UPL OK TLKJ 2011(Usulan screeningdokumen lingkung-an utk paket peng-ganti)
LARAP A. LARAP belumdisusunB. -
Satker PJN IILampung
0% Revisi Dok PQ &Dok Lelang
Review DED,Dok. LARAP,PembebasanLahan
Jan-15 Feb-15 21.00 - - - - - -
NCB/Post
2,776,633.60 189,667.60 127,669.27 61,998.33 242,274.67 102,207.87 140,066.80
Notes : = Readiness 1 (DED telah tersedia dan DSC belum terkontrak sehingga pengkajian/review dilaksanakan oleh CTC).
= Readiness 2 (DED telah tersedia dan DSC telah terkontrak sehingga pengkajian/review dilaksanakan oleh DSC).
= Kondisi ruas jalan saat ini baik sehingga penanganan konstruksi diusulkan untuk ruas yang lain.
PAKET WINRIP, IBRD LOAN NO. 8043-ID STATUS DAN JADWAL PELAKSANAAN
STATUS : 03 Desember 2013
No.Pkt Loan Package Name PROVINSI
LINGKUNGAN SOSIAL PEMBEBASANLAHAN
ProcurementStatus
1.Kegiatan2.Posisi3.Target
Masalah danSolusi
Implementation PlanWP1/WP2/WP3
Rev. DIPA TA. 2013(versi penghematan) Indikatif DIPA TA. 2014
ProcurementMethod
2013
Q4
2014 2015 2016
Q1 Q2 Q3 Q4
2017
Q2 Q3 Q2 Q1 Q2
2 SumateraBarat 207,390.20 293,185.00
DED SiapPPC WINRIP
Nov, 2010
SPPL&UKL/UPLBridge
A. OK P2JN2010B. Persiapan train-ing RKPPL pd Kon-traktor.C Target. Des 2013
Q3
14,517.31A. LARAPB. Lap. MonLARAP
A. NOL WB13Jan13B. NOL WB19Jul13
APBD Prop.Sumbar,Dinas PU
1.Pembayaran2. Sisa 21 WTP3.Sebelum kontrak
1.Bidding2.Rencana TTKontrak 05Desember 20133.Kontrak Nov 13
Percepatan NOLDisbursementuntuk pencairanuang muka
14-Nov-13 06-Dec-13 24.00 21,120.00
16 Bengkulu 110,237.00
PenyelesaianDED oleh DSC
Dec 2013
21.00AMDAL Proses IzinLingkungan dariGubernur (98%)
SLARAP A. Dok LARAP.B. PengirimanDok.ke WB.C. Nol WB akhirNov 2013
APBN, SatkerPJN I
Bengkulu
1. Proses NOLLARAP
2. Persiapansosialisasi
3. Maret 2014
Revisi Dok PQ &Dok Lelang
DED, DokLARAP,PembebasanLahan
6,602.68 40,209.90 15,323.08 24,886.82
ICB/Pre
Jan-15 Feb-15
NCB/Post
- - - 6,000.00 4,000.00 2,000.00
Appendix 14_8B39B8
APPENDIX 15
Overall Land Acquisition Status as of 30 September, 2014
(Km) (m) Total Household Year of LandAcquisition Total Land (m2)
Total Building(m2)
Total Trees Total Area (m2) Rp/m2 Total Area (m2) Rp/m2 Total Rp/m2
AWP - 1
1 Krui - Bha Lampung 25 7 Widening 2805 2011 28,763 882 653 2012 2805 28,763 50,000 882 500,000 653 50,000
Padang Sawah - Sp Empat 40.9 7 Widening 430 2011 Not LA 2110 873 2012 430 Not LA
Including Air Gadang Bridge 100 m 7 New 2011 2,426 72 2012 10 1,492 50,000 410 700,000 72 60,000
3 Manggopoh - Padang Sawah Sumatera Barat 32 7 Widening 1338 2011 Not LA 668 5324 2012 1338 Not LA 668 700,000 5324 60,000
4 Ipuh- Bantal Bengkulu 42.4 7 Widening 227 2011 Not LA 238 58 2013 227 Not LA 238 250,000 58 50,000
AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg. Tampak Lampung 36.8 6 Widening 1885 2013 194278 4557 4267
5 Sp. Rampa - Poriaha Sumatera Utara 9.7 6 Widening 1 25
11 Bantal - Mukomuko Bengkulu 50.1 6 Widening 209 2013 2500 820 36
13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 Widening 2564 2013 88852 6001 2059
6 Ps Pedati - Kerkap Bengkulu 20.9 7 Widening 582 2013 3625 4399
19 Lais- Bintunan Bengkulu 10.8 7 Widening 378 2013 9504 1380 379
15 Sibolga - Bts Tap Sel Sumatera Utara 36 7 Widening 1448 2013 45831 4391 385
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 46.8 7 Widening 1282 2014 Not LA 17123 7863
10 Sp Empat - Sp Air Balam Sumatera Barat 61.7 7 Widening 1514 2014 Not LA 23061 4369
7 Indrapura - Tapan Sumatera Barat 19.5 7 Widening 1193 2014 Not LA 13414 3290
12 Kambang - Indrapura Sumatera Barat 55.2 7 Widening 2678 2014 Not LA 19201 3225
14 Painan -Kambang Sumatera Barat 31.5 7 Widening NA
Seblat - Ipuh including 34.5 6 Widening 104 2013 755 33
Air Lalang & Air Guntung Bridge 64 m 6 New
20 Lubuk Alung - Sicincin Sumatera Barat 14.6 7 Widening NA
21 Lubuk Alung -Kurataji Sumatera Barat 16.8 7 Widening NA
18 Mukomuko - Bts. Sumbar (rencanadiganti dengan Seblat - Ketahun) Bengkulu 25.8 6 Widening NA
9 Rantau Tijang - Kota Agung (rencanadiganti dengan Tais - Betungan) Lampung 42 7 Widening NA
Land AcquistionTrees
Appendix No. 15A. Western Indonesia National Roads Improvement Projet Summary of Land Acquisition for WINRIP Packages Base on LARAP
Compensation
Household
Land BuildingType
Length Width
Year
16 Bengkulu
PackageNumber Package PROVINCE
2 Sumatera Barat
AWP - 1
1 Krui - Bha Lampung 28,763 28,763 - 100.0
Padang Sawah - Sp Empat Not LA
Including Air Gadang Bridge 2,426 1,492 934 61.5
3 Manggopoh - Padang Sawah Sumatera Barat Not LA
4 Ipuh- Bantal Bengkulu Not LA
AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg. Tampak Lampung 194,278 0 194,278 0
5 Sp. Rampa - Poriaha Sumatera Utara Not LA 0
11 Bantal - Mukomuko Bengkulu 2,500 848 1,652 33.9
13 Sp Rukis - Tj Kemuning Bengkulu 88,852 0 88,852 0
6 Ps Pedati - Kerkap Bengkulu 3,625 0 3,625 0
19 Lais- Bintunan Bengkulu 9,505 0 9,505 0
15 Sibolga - Bts Tap Sel Sumatera Utara 45,831 0 45,831 0
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat Not LA
10 Sp Empat - Sp Air Balam Sumatera Barat Not LA
7 Indrapura - Tapan Sumatera Barat Not LA
12 Kambang - Indrapura Sumatera Barat Not LA
14 Painan -Kambang Sumatera Barat NA
Seblat - Ipuh including 4,124 0 4,124 0
Air Lalang & Air Guntung Bridge
20 Lubuk Alung - Sicincin Sumatera Barat NA
21 Lubuk Alung -Kurataji Sumatera Barat NA
18 Mukomuko - Bts. Sumbar (rencanadiganti dengan Seblat - Ketahun) Bengkulu NA
9 Rantau Tijang - Kota Agung(rencana diganti dengan Tais -Betungan)
Lampung NA
Appendix No 15. Western Indonesia National Roads Improvement Projet Overall Land Acquisition Status as per 30 September 2014
Total Area to be Acquiredthrough LA Act (under
process)
Progress(%)
2 Sumatera Barat
16 Bengkulu
Total Area to beAcquired (m2) Total Acquired (M2)Package Number Package Province
APPENDIX 16
Summary of Workshops and Trainings In 2013 and 2014
Appendix 16
Summary of Trainings and Workshops of WINRIP in 2012 – 2014
No Activity Date Location Purposes
1 ProcurementTraining
Nov. 1 – 2, 2012 Hotel Grand SerelaJl. Martadinata No. 56Bandung.+62 22 4240328
The training of all project managers and procurementcommittees in the procurement procedures requiredto be used under WINRIP is crucial. This trainingprogram is on the critical path for procurement, asindicated in the Project Implementation Schedulereviewed in section 4.1 Project Implementation Plan(PIP), and it will need to be prepared and delivered assoon as possible to ensure that procurement of WP 1contractors is not delayed.
2 Workshop onProcurementProcess andBidding DocumentEvaluation
Feb. 27, 2013ToMarch 1, 2013
Swissbel hotelJl. Kemang Raya No. 7,Jakarta SelatanPhn: +62 21 7198000Fac: +62 21 719088
The purpose of this workshop is to provide training onthe procurement process and evaluation of tenderdocuments for each member of the ProcurementCommittee and Satker/PPK (Management Unit /Official Commitment Making of the WINRIP project.The purpose (output) of this workshop is theavailability of the Procurement Committee membersand Satker/PPK (Management Unit / OfficialCommitment Making of the WINRIP project becompetent in carrying out the the procurementprocess, while its outcome is achieving a smooth theprocurement process of WINRIP meet to therequirements and in accordance with applicable lawsand regulations.Subject Matters of Workshop are:
- Standard Bid Documents (SBD)- Bid Requirements and Regulations- Bid Evaluation Reports (BER)- Owner Estimate (OE)
3 Workshop onWorld BankProcurementGuidelines forWINRIP
April 24–25, 2013 Hotel Grand Hatika, Jl.Kemuning No. 16ATanjung Pandan,Belitung Barat 33411,Phn: +62 719-22889,Fac: +62 719-23800.
The purpose of this workshop is to provide a sharedunderstanding of the procurement of constructionservices process for every member of theProcurement Committee, Official of Management Unit(Satker) and Official Commitment Making (PPK) ofthe WINRIP project, relevant officials from theDirectorate of Implementation of Region I, relevantofficials from BBPJN I, II, and III, Project ManagementUnit, and of the Core Team Consultants.The purpose (Output) of this workshop is theavailability of members of Procurement Committeeand officials of related Work Unit to the WINRIPproject be competent in carrying out the procurementprocess in accordance with the guidelines of theWorld Bank.While its outcome is to achieving a smooth of thebidding process of WINRIP, meet to the requirements,and in accordance with the rules / regulations.
4 PreparatoryTraining for theCommunityRepresentativeObservers (CROs)
Package 01:Krui – Biha.May 23, 2013 Balai Besar Pelaksanaan
Jalan Nasional (BBPJN)III Palembang.Jl. Nurdin Panji No 78,KM. 7, Palembang
The purpose of the debriefing training of CROs is sothat they be able to know about the highlights ofWINRIP Project, the scope of duties of the CROs, andthus they can carry out their duties in monitoring theprocurement process undertaken by the ProcurementCommitteePackage 04:
Ipuh – Bantal.May 23, 2013
No Activity Date Location Purposes
Package 02:Padang. Sawah –Simpang. Empat.May 27, 2013
Balai Besar PelaksanaanJalan Nasional (BBPJN)II Padang.Jl. Jati No 109, Padang
Package 03:Manggopoh –Padang. SawahMay 27, 2013
5 PreparatoryTraining for theThird PartyMonitoring (TPM)
Package 01:Krui – Biha.June 5-6, 2014
PPK 08 Office.Jl. Wolter Monginsidi No.220 B Bandar Lampung.
The Objectives of this training is to provide the basicinformation necessary to support the implementationof the project, so that the TPM personnel canimplement monitoring in accordance with theprovisions and procedures prescribed. Completed thetraining, the participants are expected to:- Explaining about ACAP and its implementation;- Describe the scope of monitoring by the TPM;- Describe the monitoring of the construction works;- Describe how to monitor the implementation of
Work Plan for Environmental Management andMonitoring.
- Describe provisions on reporting and financialaccountability is necessary.
The main target group is the TPM team members, aswell as of other elements related to the constructionproject, namely Satker/PIU Implementation ofNational Road; PPK related package; DSCConsultant (Field Supervision Team); National RoadImplementation Agency (Balai BBPJN) ), and
Package 02:Padang. Sawah –Simpang. Empat.June 17-18, 2014
BBPJN II Office.Jl. Jati No. 109 PadangPackage 03:
Manggopoh –Padang. SawahJune 17-18, 2014
Package 04:Ipuh – Bantal.July 7-8, 2014
Satker PJN I OfficeJl. Ir. Rustandi SugiantoKM 12+225 Pulau BaayBengkulu
6 Training on ActionPlan forEnvironmentalManagement andMonitoring /Rencana Kerjapengelolaan danPemantauanLingkungan(RKPPL)
Package 01:Krui – Biha.June 5, 2014
PPK 08 Office.Jl. Wolter Monginsidi No.220 B Bandar Lampung.
Training on Action Plans of EnvironmentalManagement and Monitoring is intended to providethe basic information necessary to support theimplementation of the project, so that all rules andprocedures related to environmental managementcan be complied with and implemented in accordancewith the terms and conditions applicable.Finished the training the participants are expected to:- Describe the impact of road works on the
environmental aspects in the implementation ofroad and bridge construction;
- Explain the benefits and contents of the ActionPlans of the Environmental Management andMonitoring;
- Describe the monitoring of environmentalmanagement efforts to reduce / prevent thenegative impact of work activities on theimplementation of the construction work.
The main target group is the the Contractors, TPMteam members, as well as of other elements relatedto the construction project, namely Satker / PIUImplementation of National Road; PPK relatedpackage; DSC Consultant (Field Supervision Team);National Road Implementation Agency (Balai BBPJN
Package 02:Padang. Sawah –Simpang. Empat.June 17, 2014
BBPJN II Office.Jl. Jati No. 109 Padang
Package 03:Manggopoh –Padang. SawahJune 17, 2014
Package 04:Ipuh – Bantal.July 7, 2014
Satker PJN I OfficeJl. Ir. Rustandi SugiantoKM 12+225 Pulau BaayBengkulu
No Activity Date Location Purposes
7 PreparatoryTraining for theThird PartyMonitoring (TPM)
BengkuluJuly 7 – 8, 2014
Satker PJN I Bengkulu,Jln. Ir. Rustandi SugiantoKm 12 + 225 Pulau Baai,Bengkulu.
The Objectives of this training is to provide the basicinformation necessary to support the implementationof the project, so that the TPM personnel canimplement monitoring in accordance with theprovisions and procedures prescribed. Completed thetraining, the participants are expected to:- Explaining about ACAP and its implementation;- Describe the scope of monitoring by the TPM;- Describe the monitoring of the construction works;- Describe how to monitor the implementation of
Work Plan for Environmental Management andMonitoring.
- Describe provisions on reporting and financialaccountability is necessary.
The main target group is the TPM team members, aswell as of other elements related to the constructionproject, namely Satker/PIU Implementation ofNational Road; PPK related package; DSCConsultant (Field Supervision Team); National RoadImplementation Agency (Balai BBPJN) ), and
8 Training on ActionPlan forEnvironmentalManagement andMonitoring /Rencana Kerjapengelolaan danPemantauanLingkungan(RKPPL)
BengkuluJuly 7 – 8, 2014
Satker PJN I Bengkulu,Jln. Ir. Rustandi SugiantoKm 12 + 225 Pulau Baai,Bengkulu.
Training on Action Plans of EnvironmentalManagement and Monitoring is intended to providethe basic information necessary to support theimplementation of the project, so that all rules andprocedures related to environmental managementcan be complied with and implemented in accordancewith the terms and conditions applicable.Finished the training the participants are expected to:- Describe the impact of road works on the
environmental aspects in the implementation ofroad and bridge construction;
- Explain the benefits and contents of the ActionPlans of the Environmental Management andMonitoring;
- Describe the monitoring of environmentalmanagement efforts to reduce / prevent thenegative impact of work activities on theimplementation of the construction work.
The main target group is the the Contractors, TPMteam members, as well as of other elements relatedto the construction project, namely Satker / PIUImplementation of National Road; PPK relatedpackage; DSC Consultant (Field Supervision Team);National Road Implementation Agency (Balai BBPJN
9 ProjectManagementManual (PMM)SocializationWorkshop
September10 – 11, 2014
The Premier BaskoHotel, Jl. Prof. Dr. HamkaNo. 2A, Padang.
The training aims to socialize/disseminate the ProjectManagement Manual (PMM) to those who areinvolved in the project implementation of the WINRIPIt will introduce provisions in the PMM to all elementsthat are responsible for the implementation ofWINRIP, in order to carry out their duties complyingwith the need to be properly and fully observed duringproject implementation.
.