quarterly social monitoring report - asian development · pdf filequarterly social monitoring...
TRANSCRIPT
Quarterly Social Monitoring Report
This report has been submitted to ADB by the Borrower and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB.
Project Number: LN2612/EI7303 January to March 2014
PHI: Visayas Base-load Power Development Project
Prepared by
KEPCO SPC Power Corporation
Cebu City, Philippines
2 x 100 MW CEBU POWER PLANT
2014.04
Site Office
Quarterly Social Monitoring Report
(January–March 2014)
2
Social Monitoring Report January – March 2014
Table of Contents
I. Introduction/Background 3 II. Land Acquisition and Involuntary Resettlement – Naga Land 3
III. Land Acquisition and Involuntary Resettlement – 138 kV T/L Project 5 IV. Social Development Plan and Corporate Social Responsibilities Program 6 V. Attachments:
Attachment 1 2014 Approved Budget for SDP and CSR Program
Attachment 2 Table of Status of ROW Cases in T/L
Project (as of April 21, 2014)
Attachment 2 Table and Photos of Implemented SDP and CSR Projects (January–March 2014)
3
Social Monitoring Report January – March 2014
I. INTRODUCTION/BACKGROUND A. Brief Project Description KEPCO SPC Power Corporation (KSPC) undertook the construction of a 2 x 100 megawatts (MW) CFBC power plant in Barangay Colon, City of Naga, Cebu. The project is standing in a 10-hectare land that is leased for 25 years from National Power Corporation (NPC). The project involves 2 resettlement issues: a) in the leased property called Naga Land; and b) along the Transmission Line (T/L) Project. Prior to construction period, resettlement of some informal settlers families just outside the lease land have been carried out as a joint effort by Barangay Colon, the then Municipal Government of Naga, NPC and KSPC. Out of 22 families, 17 families have accepted financial assistance provided and voluntarily moved their houses in the same vicinity outside the plant’s perimeter fence. Five families claim to have legal titles and during the construction phase remain to be partially encroaching in the leased land. NPC filed a civil case for recovery of possession of the areas occupied by these 5 families. Meanwhile, a social analysis conducted by Transco, now National Grid Corporation of the Philippines (NGCP), concluded that the proposed 138 KV T/L Project requires land acquisition and resettlement. The 0.90–kilometer transmission line from KSPC’s Cebu Power Plant Project to the New Naga Substation will affect 11 landowners, 1 tenant, 13 structures owners and 10 relocatee-households.
II. LAND ACQUISITION AND INVOLUNTARY RESETTLEMENT – NAGA LAND
A. Progress on Case Filed in Court vs. 5 Illegal Dwellers within Naga Land
4
Social Monitoring Report January – March 2014
The Court already resolved the case filed by NPC vs. the five (5) Illegal Dwellers within Naga Land. Two of the defendants did not file answers to the complaint while the three others already entered into a Compromise Agreement with National Power Corporation (NPC). The Court approved the Compromise Agreement and resolved the issue on the two (2) other defendants, who were earlier declared in default for not filing an answer to the complaint.
B. Progress on living condition of 17 Resettlement Families The families living in the Resettlement Area are already insulated from direct contact with the land reclaimed using coal ash after the completion of the concreting project. They are prioritized in the different community outreach projects under the Social Development Plan and Corporate Social Responsibilities (SDP and CSR) Program that KSPC implements every year. KSPC is sending a doctor to six (6) barangays nearest to the power plant, including the host Barangay Colon, for a weekly free health check-up as well as donating basic medicines to augment the supplies provided by the local government. Last March 7, forty (40) women from Barangay Colon completed the Hair Styling and Beauty Care Training conducted by KSPC through the Alternative Learning System (ALS) Program of the Department of Education (DepEd), the Technical Education and Skills Development Authority (TESDA) and local government units (LGUs). They are the fourth batch of completers under KSPC’s Skills Development Training Program aimed to equip the residents
5
Social Monitoring Report January – March 2014
of the community with skills that can provide them livelihood and employment opportunities. KSPC has also been donating medical equipment and upgrading the facilities of the barangay health centers and the public schools to help improve the services they provide. This school year, the budget for Scholarship Program was doubled in order to widen the coverage of the free education of its existing four (4) beneficiaries and be able to help additional poor but deserving public high school graduates in its host communities. A new program to address the problem of malnutrition among school children will also be implemented, as well as assistance for the Persons with Disability (PWDs) residents of the barangay. Meanwhile, as committed to the LGU partners, KSPC will continue the quarterly consultation meetings with the three nearest barangays of Colon, North Poblacion and Tangke to update the communities of the different activities of the power plant, as well as get feedback and recommendations from the nearby residents. Attached is KSPC’s approved 2014 budget for its SDP and CSR Program with significant increase compared to last year’s budget. Additional budget for donation and financial assistance is being provided for the other needs solicited by the host communities and the stakeholders. Please see Attachment 1
III. LAND ACQUISITION AND INVOLUNTARY RESETTLEMENT – 138 kV T/L PROJECT A. Progress on the remaining ROW Issues Please see NGCP report on the latest Status of ROW Cases as of April 21, 2014 in Attachment 2.
6
Social Monitoring Report January – March 2014
IV. SOCIAL DEVELOPMENT PLAN
A. Progress on Implementation of Livelihood and
Community Development Programs for People Relocated from Naga Land and Project T/L
In fulfilling its commitment to uplift the lives of the residents of its host communities, KSPC continuously gives priority to the implementation of various programs and projects that are focused on health, education, environment and livelihood. Please see Attachment 2 (Implemented Community Relations Projects/Programs from January– March 2014).
V. PROBLEMS AND FUTURE WORK PLAN
So far, no major problem has been encountered. All SDP and CSR activities are being carried out in coordination with the host communities and stakeholders from the planning stage up to actual implementation.
ATTACHMENT 2 NEW NAGA SUBSTATION & ASSOCIATED TRANSMISSION LINE PROJECT
Status of Expropriation Cases as of 21 April 2014
Case Title
Case
No./Court Date Filed
Presiding
Judge
Defendants’ Counsel
Handling
Lawyer
WOP
Remarks
D. KSPC Associate Lines –
4 cases
1 NGCP vs. Hrs. of Eugenio
dela Corte, namely: Eliseo
A. dela Corte, et.al.
CEB-36004
RTC 5
Cebu City
6-Oct-09 Judge
Castillo
(Pairing
Judge)
Atty. Michael
Yu
√ Documentation for the settlement of the case is being
processed. The copy of the Deed of Absolute Sale was
already sent to the defendants for their review and
signature.
2 NGCP vs. Hrs. of Corazon
Ceniza
CEB-36361
RTC 12
Cebu City
9-Feb-2010 Estella
Singco
Atty.
Capanas
Defendants have been paid of the compensation.
Follow-up is being with Atty. Labrado (counsel for
defendants) for the tax clearance certificate re payment
of estate taxes to complete the transfer of ownership.
15 NGCP vs. Amador
Anastacio
CEB-36326
RTC 14
Cebu City
29-Jan-
2010
Raphael
Yrastorza
ditto √ Prese tatio of defe da ts’ evide ce o the just compensation is ongoing.
16 NGCP vs. AmparoAlforque
and Hrs. of Sergio
Alforque
CEB-36003
RTC 58
Cebu City
6-Oct-09 LynaAdvient
o
Atty. Rio
Bilocura
ditto √ We are still waiting for notice from the Court for the
next hearing schedule. (Note: Hearing on civil cases are
deferred after the earthquake last 15 November 2013.
The Palace of Justice is unsafe for occupancy and the
courts are set to transfer to another location.)
Defe da ts’ proposal for settle ent is being evaluated.
ATTACHMENT 3
Implemented Community Relations Projects and Programs (January–March 2014)
Date Beneficiary/ies Project Name Amount
1 Jan-March 2014 Barangays Colon, Tuyan,
Inayagan, North Poblacion, Tangke and Naalad
Doctor’s Weekly Free Health
Check-Up 144,000.00
2 08-Jan 2014 Uling National High School and Langtad Elementary
School
Financial Support for the City
of Naga’s Contingent to the Sinulog 2014
50,000.00
3 14 Jan. 2014 Barangay Colon Resident
Condolence Money to
Indigent Resident
5,000.00
4 20 Jan. 2014 Barangays Colon and North
Poblacion
Financial Assistance for the
Barangays’ Participation to the 2014 Sinulog sa Naga
10,000.00
5 21 Jan. 2014 Department of Education –
City of Naga
Financial Assistance for the
City of Naga’s Athletes to the Central Visayas Regional
Athletics Meet
23,605.00
6 05 Feb. 2014 Brgy. North Poblacion
Financial Assistance for the
Barangay Youth’s Basketball Tournament
20,000.00
7 11 Feb. – 7 March
2014
Women Sector of Barangay
Colon
Hair Dressing and Beauty
Care Skills Training Program 102,000.00
8 05 March 2014 Barangays Colon, North
Poblacion and Tangke Day Care Centers
Support for the Graduation
Ceremonies 15,000.00
9 06 March 2014
Barangay Health Workers
and Nutrition Scholars
Support for Seminar and
Induction of Officers
14,140.00
10 12 March 2014
NPC-Colon Elementary
School
Incentives to Honor and
Graduating Students 45,000.00
11 19 March 2014 Barangay Tangke
Donation of Concreting
Materials for Barangay Road
Paving Project
14,100.00
12 24 March 2014 Bureau of Fire Protection
Donation of Safety Shoes to
Firemen 54,900.00
13 25 March 2014
Barangay North Poblacion
Chapel & Barangay Colon
Senior Citizens
Donation of Plastic Chairs 22,745.50