    1/59

    Its happening nowQueens Quay Revitalization

    Central Waterfront Update Meeting: June 6, 2012

  • 7/31/2019 Queens Quay Revitalization Plan

    2/59

    Beginning the transformation of Queens Quay from

    austere and uninviting

    BEFORE

  • 7/31/2019 Queens Quay Revitalization Plan

    3/59

    into a truly great and vibrant waterfront street

    AFTER

  • 7/31/2019 Queens Quay Revitalization Plan

    4/59

    BEFORE

    From a place to move through

  • 7/31/2019 Queens Quay Revitalization Plan

    5/59

    AFTER

    into a great place to be

  • 7/31/2019 Queens Quay Revitalization Plan

    6/59

    June 2006: Central Waterfront Design Competition

  • 7/31/2019 Queens Quay Revitalization Plan

    7/59Summer 2006: Quay to the City Pilot Project

  • 7/31/2019 Queens Quay Revitalization Plan

    8/59

    April 2010: Full Approval for Environmental Assessment

  • 7/31/2019 Queens Quay Revitalization Plan

    9/59

    Fall 2010 Summer 2011: Detailed Design for Queens Quay

  • 7/31/2019 Queens Quay Revitalization Plan

    10/59

    November 2011 June 2012: Planning for Construction

  • 7/31/2019 Queens Quay Revitalization Plan

    11/59

    Its happening nowQueens Quay Vision

    http://sp/sites/cwf/03/Marcom/Queens%20Quay/New%20renderings%20MAY%202012/04.jpg
  • 7/31/2019 Queens Quay Revitalization Plan

    12/59

    Design and Construction Team

    Design Team

    Lead Designer: West 8 + DTAH

    Civil/Municipal Engineer: ARUP

    Structural Engineering: Halsall

    Bus/Traffic Management: BA Group

    Utility Coordination/Design: DPM Energy

    Electrical: TSL Consulting & Design Group

    Environmental and Geotechnical: LVM Franz/Golder Associates

    Cost Estimating: AW Hooker Associates Ltd.

    Urban Forestry: James Urban and AssociatesIrrigation: Smart Watering Systems

    Construction Team

    Construction Manager: Eastern Construction Company Ltd.

    Toronto Hydro Constr. Contractor: Powerline Plus Ltd.Bell Canada Constr. Contractor: Aecon

  • 7/31/2019 Queens Quay Revitalization Plan

    13/59

    Design Elements for Queens Quay

    4. Roadway

    1. Southside Promenade

    2. Martin Goodman Trail

    5. Northside sidewalk

    3. TTC Streetcar Corridor

  • 7/31/2019 Queens Quay Revitalization Plan

    14/59

    Design Elements for Queens Quay

    1. Southside Promenade

  • 7/31/2019 Queens Quay Revitalization Plan

    15/59

    New Pedestrian Promenade: Generous granite mosaic

  • 7/31/2019 Queens Quay Revitalization Plan

    16/59

    Design Elements for Queens Quay

    2. Martin Goodman Trail

  • 7/31/2019 Queens Quay Revitalization Plan

    17/59

    New Martin Goodman Trail: Connecting east and west and framedby double row of trees

  • 7/31/2019 Queens Quay Revitalization Plan

    18/59

  • 7/31/2019 Queens Quay Revitalization Plan

    19/59

    TTC: New streetcar right-of-way with expanded platforms

    and amenities

  • 7/31/2019 Queens Quay Revitalization Plan

    20/59

    Design Elements for Queens Quay

    4. Roadway

  • 7/31/2019 Queens Quay Revitalization Plan

    21/59

    Roadway: New Two-lane, twoway road with expanded turning lanes

    and laybys and improved signalization

  • 7/31/2019 Queens Quay Revitalization Plan

    22/59

    INSERT Northside sidewalk elements Page

    Design Elements for Queens Quay

    5. Northside sidewalk

  • 7/31/2019 Queens Quay Revitalization Plan

    23/59

    North Side Beautification: Granite curbs/sidewalk pavers and tree-

    planting

  • 7/31/2019 Queens Quay Revitalization Plan

    24/59

    Completely upgraded utilities and municipal services

    Storm sewer installation Watermain installation

  • 7/31/2019 Queens Quay Revitalization Plan

    25/59

    Improvement to Public and Private Space - Northside

    BEFORE

  • 7/31/2019 Queens Quay Revitalization Plan

    26/59

    Improvement to Public and Private Space - Northside

    AFTER

  • 7/31/2019 Queens Quay Revitalization Plan

    27/59

    NOW

    Improvement to Public and Private Space - Southside

  • 7/31/2019 Queens Quay Revitalization Plan

    28/59

    AFTER

    Improvement to Public and Private Space - Southside

  • 7/31/2019 Queens Quay Revitalization Plan

    29/59

    Interim Martin Goodman Trail Connection

    Existing: Looking East at Pier 27

  • 7/31/2019 Queens Quay Revitalization Plan

    30/59

    Martin Goodman Trail Connection

    Looking East at Pier 27

  • 7/31/2019 Queens Quay Revitalization Plan

    31/59

    Interim Martin Goodman Trail Connection

    Existing: Looking East at Redpath

  • 7/31/2019 Queens Quay Revitalization Plan

    32/59

    Interim Martin Goodman Trail Connection

    Looking East at Redpath

  • 7/31/2019 Queens Quay Revitalization Plan

    33/59

    Its happening nowHow construction will unfold

  • 7/31/2019 Queens Quay Revitalization Plan

    34/59

    Queens Quay Central Waterfront

    Yo Yo Ma Lane Bay Street

    Interim MGT Connection

    Bay Street Jarvis Street

    EBF Queens Quay

    Jarvis Street - Parliament

  • 7/31/2019 Queens Quay Revitalization Plan

    35/59

    Coordinated Construction

    Transit infrastructure and most of the utilities and municipal services beneath

    Queens Quay require major upgrades and/or expansion now

    The TTC tracks have reached the end of their service life

    Toronto Hydro is replacing aging electrical infrastructure

    Bell will building new infrastructure and run new fibre optic cable

    The aging sanitary line will be rebuilt and relocated

    Storm sewer and water main upgrades

    These projects would have happened in the near future with or without the

    revitalization of Queens Quay

    We are coordinating these upgrades with our work to avoid the need for more

    disruptive construction in the near future

    Construction is about more than rebuilding the surface of the roadway

  • 7/31/2019 Queens Quay Revitalization Plan

    36/59

    Coordinated Construction

    Streamlined Schedule Overlapping approach allows different construction

    programs to run simultaneously.

    Moratorium After Construction Complete Avoids the need for more construction

    on Queens Quay in the near future.

    Cost Effective Streamlined schedule means crews are not required to stop work

    and remobilize.

    Benefits of working in a coordinated manner

  • 7/31/2019 Queens Quay Revitalization Plan

    37/59

  • 7/31/2019 Queens Quay Revitalization Plan

    38/59

  • 7/31/2019 Queens Quay Revitalization Plan

    39/59

  • 7/31/2019 Queens Quay Revitalization Plan

    40/59

  • 7/31/2019 Queens Quay Revitalization Plan

    41/59

  • 7/31/2019 Queens Quay Revitalization Plan

    42/59

  • 7/31/2019 Queens Quay Revitalization Plan

    43/59

  • 7/31/2019 Queens Quay Revitalization Plan

    44/59

  • 7/31/2019 Queens Quay Revitalization Plan

    45/59

  • 7/31/2019 Queens Quay Revitalization Plan

    46/59

  • 7/31/2019 Queens Quay Revitalization Plan

    47/59

    What to Expect

    Accessing Queens Quay During Construction

    Queens Quay will be safe andfunctional

    Access will be maintained to all

    businesses and residences at all

    times

    The waterfront is Open For

    Business during construction

    Cars, transit and pedestrian traffic

    will always be able to access

    Queens Quay

  • 7/31/2019 Queens Quay Revitalization Plan

    48/59

    What to Expect

    Types of Construction Impacts

    Temporary fences around all

    construction areas to maintainpedestrian and vehicular safety

    Construction noise as permitted by the

    City of Toronto between 7am and 7pm

    while work is occurring

    Possible dust and debris during workhours

    Possible brief interruptions to

    telephone, power or water when

    connections are being switched over

    (notice to be provided)

    Short-term occasional night work when

    TTC installs track

  • 7/31/2019 Queens Quay Revitalization Plan

    49/59

    What to Expect

    PEDESTRIANS: Temporary

    gangplanks to ensure continuous

    pedestrian access to all buildings

    and stores during sidewalk

    reconstruction

    MOTORISTS: Temporary one-way

    traffic operations alternating

    between the north and south side

    of the TTC tracks to avoidconstruction areas

    Changes in How the Street Operates During Construction

  • 7/31/2019 Queens Quay Revitalization Plan

    50/59

    What to Expect

    TRANSIT: Temporary TTC bus service

    running westbound on Queens Quayand eastbound on Lake Shore while

    the streetcar line is rebuilt in the first

    stage of work.

    CYCLISTS: Building the Martin

    Goodman Trail is a key goal for thisproject as there are currently no

    bicycle lanes along Queens Quay in

    the Central Waterfront. Cyclists

    should use caution when traveling

    along Queens Quay during

    construction or consider usinganother alternative route.

    Changes in How the Street Operates During Construction cont

  • 7/31/2019 Queens Quay Revitalization Plan

    51/59

  • 7/31/2019 Queens Quay Revitalization Plan

    52/59

  • 7/31/2019 Queens Quay Revitalization Plan

    53/59

  • 7/31/2019 Queens Quay Revitalization Plan

    54/59

    Its happening nowLearn more

    d/ k

  • 7/31/2019 Queens Quay Revitalization Plan

    55/59

    QUEENS QUAYOPEN HOUSE

    Drop-in and review proposedconstruction plans and timelines.

    Look for your home or business andtalkto us about what to expect.

    When:Saturday, June 9, 2012

    Where: Waterpark Place Lobby20 Bay St.

    Time: 10am - 2pm

    Stay Connected/Ask Questions

    Construction Information

    d/ k i

  • 7/31/2019 Queens Quay Revitalization Plan

    56/59

    Construction Information

    Waterfront Torontos website

    www.waterfrontoronto.ca will be the

    main hub for information: Weekly construction notices

    subscribe online

    Construction schedule

    Detailed construction

    information

    Live webcams Contact information

    Stay Connected/Ask Questions

    S C d/A k Q i

    http://www.waterfrontoronto.ca/http://www.waterfrontoronto.ca/
  • 7/31/2019 Queens Quay Revitalization Plan

    57/59

    Construction Information

    Construction Liaison Committee

    Forum for residents and businesses to

    discuss construction issues. Group meets regularly to discuss

    construction schedule, issues and

    impacts

    Residents: every condo is represented

    on the CLC

    Businesses: The Waterfront BIA andother businesses are represented

    Contact your rep if you have an issue

    to raise (www.waterfrontoronto.ca)

    Stay Connected/Ask Questions

    St C t d/A k Q ti

  • 7/31/2019 Queens Quay Revitalization Plan

    58/59

    Construction Information

    Questions/Issues:

    Email: [email protected]

    Call: Waterfront Toronto Queens Quay info line is 416.214.9990

    For urgent construction issues call:

    Eastern construction: Robert Pasut, Community Liaison Officer

    (416) 505-3073

    Stay Connected/Ask Questions

  • 7/31/2019 Queens Quay Revitalization Plan

    59/59

    Questions