r- jljv .i.r, › work › 07 › 40161772.pdf · the east parcel was leased by the nebraska...
TRANSCRIPT
'O'
r- JLJV .i.r,:
SUPERFUND PRELIMINARY SUE CLOSE OUT REPORTfor the
LONG-TERM REMEDIAL ACTIONat the
CLEBURN STREET WELL SUPERFUND SITE
GRAND ISLAND, NEBRASKA
PREPARED BY:
U.S. ENVIRONMENTAL PROTECTION AGENCY
REGION VH
KANSAS CITY, KANSAS
AUGUST 2004
40161772
SUPERFUND RECORDS
1.0 INTRODUCTION
This Preliminary Close Out Report documents that the U.S. Environmental Protection
Agency (EPA) completed construction activities at Operable Units (OUs) 1 through 5 at the
Cleburn Street Well Superfund Site in accordance with the Close Out Procedures for National
Priorities List Sites guidance, Office of Solid Waste and Emergency Response Directive 9320.2-
09A-P, January 2000. EPA and the Nebraska Department of Environmental Quality (NDEQ)
conducted a final inspection of the facilities at OUS on June 30, 2004 and determined that the
responsible party - Union Pacific Railroad (UPRR) - has substantially constructed the remedy for
OUS in accordance with the remedial design plans and specifications. After certification that a
small number of minor items had been addressed, the EPA issued a construction completed letter
on August 9, 2004. This is the last OU to be constructed. This constitutes a construction
complete for the site.
The remediation facilities for OU1 and OU2 were completed in August 1998 and were
constructed per the March 9, 1998 approved contract documents developed by EPA (Start-
up/Semi-annual Performance Report, Cleburn Street Site Operable Units 1 & 2, Revision 1,
Sverdrup Environmental, Inc., September 15, 1999). The pre-final inspection for OU1 and OU2
was performed on November 3, 1998 by EPA. A punch list of deficient and outstanding items
was prepared and the items were corrected by the remediation contractor (Interim remedial Action
Report, Cleburn Street Site Operable Units 1 & 2, Revision J, Sverdrup Environmental Inc.,
December 28, 1999).
The remediation activities for OU3 and OU4 were completed with installation ofgroundwater monitoring wells between March 31, 1998 and April 7, 1998. According to theMarch 23, 1999 Final Remedial Action Report for OU3 and OU4 (Sverdrup Environmental, Inc.,
1998) the monitoring wells were installed in accordance with the project planning documents. No
major instances of deviation or non-compliance were noted.
2.0 SUMMARY OF SITE CONDITIONS
2.1 Background Information
The Cleburn Street Well Superfund Site is located in Grand Island, Hall County, Nebraska
and is located approximately two miles north of the Wood River and approximately seven miles
1
northeast of the Platte River. The Cleburn Street Well site encompasses approximately 144 city
blocks in the downtown area and is surrounded by a variety of light industries, commercial
businesses, and residential dwellings. The Site consists of a former municipal water supply well,the Cleburn Street Well, and surrounding groundwater and soils containing volatile organic
compounds (VOCs), primarily tetrachloroethylene (PCE). Results of the remedial investigation
(RI) (Sverdrup Environmental, Inc.,1993) indicated there were four separate source areas
including three dry cleaning facilities and a former solvents distribution facility.
The Cleburn Street Well Superfund site consists of five operable units. OU1 consists of
the subsurface soil at the One Hour Martinizing facility; OU2 consists of the groundwater at the
One Hour Martinizing facility; OU3 consists of the Liberty Cleaners; OU4 consists of the Ideal
Cleaners; and OU5 consists of the former Nebraska Solvent Company facilities. The Nebraska
Solvent Company facilities were located on property owned by the UPRR. One Hour Martinizing
and Nebraska Solvents Company are no longer in business.
The Cleburn Street OU1 and OU2 facilities are located at the southwest corner of 4th Street
and Eddy Street. Cleburn Street OU 3 and OU4, the Liberty Cleaners and the Ideal Cleaners, are
located at the northwest corner of 8th Street and Eddy Street and the southeast corner of 1st Street
and Cedar Street, respectively. Cleburn Street OU5 is located at an area generally bounded by
North Front and South Front Streets from Lincoln Street northwesterly for approximately eight
hundred and fifty feet.
A Record of Decision (ROD) was prepared in April 1996, that addressed only the three dry
cleaning source areas (OU1-4). A ROD was prepared in September 2001 that addressed theformer solvents distribution facility (OU5).
The OU5 site consists of the west parcel and the east parcel. The west parcel was leased
by the Nebraska Solvent Company from 1936 to 1973 for above ground tank storage and
distribution of organic solvents, including PCE, for industrial use, primarily in the dry cleaning
industry. Prior to 1973, bulk petroleum storage tanks, which stored other solvent cleaning
materials, were located at the west parcel. The west parcel occupies an area approximately 75 feet
by 175 feet just south of the Thompson Company grocery distribution facility and is leased by
Toba, Inc., of Grand Island. The parcel is currently unoccupied and is composed of soil fill with
no asphalt or concrete paving.
The east parcel was leased by the Nebraska Solvent Company until 1973 for warehousing,
handling, truck loading and other activities associated with cleaning solvents distribution, mostly
in drums. The east parcel occupies an area approximately 100 feet by 125 feet. It is currently
leased by the City of Grand Island's Street Department. It now consists of a maintenance office
building, a small sign shop and paved maintenance yard.
PCE was first detected in the drinking water wells of Grand Island, Nebraska in April
1984, by the Nebraska Department of Health (NDOH). In 1986, NDOH found low levels of PCE
in the Lincoln Street Well, which is located in the immediate area of OU5. In March 1986, the
NDOH detected PCE at a concentration of 21.9 micrograms per liter (ug/L) in the Cleburn Street
Well. The NDOH re-sampled the well in April 1986, following a citizen's complaint of poor taste
and odor in the municipal drinking water, and confirmed the presence of PCE at a concentration
of 26.9 ug/L. The Cleburn Street Well was subsequently closed for drinking water purposes. The
Lincoln street well was plugged and abandoned in 1999.
In September 1988, the EPA conducted a soil-gas survey over a large area of downtown
Grand Island and discovered that PCE existed in the soils at the Cleburn Street Well Site. Based
on the findings of the soil gas survey and previous sampling events, the Cleburn Street Well Site
was proposed for the National Priorities List on July 29, 1991. Listing of the Cleburn Street Well
Site was finalized on October 14, 1992.
A remedial investigation of the site was initiated by EPA in September 1991. Phase I field
sampling activities occurred in May/June 1992 and Phase n activities in November 1992. The RI
Report, including a Baseline Risk Assessment, was prepared and submitted to EPA in May 1993(Sverdrup Environmental, Inc., 1993). Phase in field sampling activities occurred in April 1993,to delineate the extent of contamination detected in the previous phases, with an emphasis on the
former One Hour Martinizing source area (OU1 and OU2). Phase I and Phase n of the RI
included a partial characterization of the Nebraska Solvents facility area (OU5).
The UPRR, under EPA oversight via an Administrative Order of Consent, completed the"Remedial Investigation Site Characterization Summary Report, Former Nebraska Solvent Site -
OU5, Cleburn Street Well Superfund Site, Grand Island, Nebraska" (TheroRetec, 1999) in July
1998. The RI confirmed and defined the source, magnitude, and locations of the contamination in
both the soil and groundwater at OU5. A feasibility study (FS) was completed in 2000. In
addition to the RI and FS, UPRR also completed a pilot study in the west parcel to substantiate the
effectiveness of a soil vapor extraction (SVE) system to remove contamination from the soil.
The geology is consistent across the site and is comprised of silty sands to a depth of
approximately 90 feet below ground. This zone comprises the single aquifer (water-bearing) unit
in the vicinity of the site and serves as the source of municipal drinking water for the residents ofGrand Island. Depth to groundwater averages between 18-22 feet below ground surface. Depth to
the clay aquitard unit was encountered between 87 feet and 94 feet below ground surface.
Groundwater flow in the vicinity of the site is in a northeasterly direction.
Chemical analysis of soil samples collected from soil borings and monitoring well borings
indicated the presence of PCE, trichloroethylene (TCE), and compounds commonly associated as
potential degradation products of PCE, including 1,2-dichloroethylene (DCE) and 1,1,1-
trichloroethane, at each of the operable units. Other compounds commonly associated as potential
minor degradation products, 1,1-dichloroethylene, and 1,1,2-trichloroethane were also detected.
PCE is the primary contaminant of concern and was detected at all of the source areas.
The highest concentration of PCE (9,200,000 micrograms per kilogram {ug/kg}) was detected in
a soil sample collected from the former One Hour Martinizing source area (OU1). Soil samples
collected from the Liberty and Ideal Cleaners source areas (OU3 and OU4) contained PCE
concentrations up to 110 ug/kg and 270 ug/kg, respectively. Soils from the surface to a depth of
20 feet in the west parcel of OU5 contained PCE concentrations ranging from 3,900,000 to
840,000 ug/kg. Likewise, over the same depths, TCE ranged from 39,000 to 2,900 ug/kg and cis-
DCE 23,000 to 2,700 ug/kg. In the east parcel of OU5, over the same depths from in soil, PCE
concentrations were found to range from 420 to 81 ug/kg, TCE from 440 to 28 ug/kg, and cis-
DCE from 110 to 38 ug/kg.
PCE was detected at concentrations exceeding the maximum contaminant level (MCL) ingroundwater samples collected from each of the operable units. The highest concentration of PCE
(170,000 ug/L) was detected in the groundwater sample collected from OU2 source area.
Compounds commonly associated with the natural degradation of PCE in the environment such as
TCE, 1,2-DCE and 1,1,1 -trichloroethane were also detected in the groundwater samples from
OU2 at maximum concentrations of 410 ug/L, 85 ug/L, and 540 ug/L, respectively. Groundwater
at Liberty Cleaners (OU3) and Ideal Cleaners (OU4) was contaminated to a lesser degree than
OU2. The highest PCE concentrations detected at OU3 and OU4 were 65 ug/L and 95 ug/L,
respectively.
PCE was found in the groundwater at OU5 at concentrations of up to 5,000 ug/L in the
west parcel and 1,600 ug/L in the east parcel. TCE was detected in the groundwater at
concentrations of up to 76 ug/L in the west parcel and 100 ug/L in the east parcel. Cis-DCE was
detected in the groundwater at concentrations of up to 11,000 ug/L in the west parcel and 390
ug/L in the east parcel.
2.2 Remedial Construction Activities
A ROD for OU1, OU2, OU3, and OU4 was issued in June 1996. The selected remedy for
the One Hour Martinizing source area (OU1 and OU2) included:
• Monitoring of groundwater, discharge of treated water and air emissions;
• Institutional controls to restrict groundwater use;
• Extraction of subsurface contaminants using soil vapor extraction;
• Treatment of extracted soil vapors by carbon adsorption;• Extraction of groundwater containing contaminants above MCLs for 20 years; and
• Treatment of extracted groundwater by onsite air stripping for 20 years.
The selected remedy for the Liberty Cleaners (OU3) and Ideal Cleaners (OU4) included:
• Construction of groundwater monitoring wells;
• Groundwater monitoring for 10 years (natural attenuation);
• Institutional controls to restrict groundwater use; and
• Soil vapor extraction and treatment as a contingency.
The EPA issued a ROD for the Nebraska Solvents source area (OU5) on September 10,2001. The selected remedy included:
• Construction of a SVE system and air sparging system;
• Groundwater monitoring;
• LNAPL removal from the groundwater by bailing; and
• Institutional controls in the form of deed restrictions to prohibit groundwater use
and improper subsurface construction on the UPRR properties.
Health based performance standards specified in the ROD for the One Hour Martinizing,
Liberty Cleaners, and Ideal Cleaners include attainment of MCLs for the primary contaminants of
concern in the groundwater. Health based performance standards specified in the ROD for the
soil and groundwater at the Nebraska Solvents source area include:
Constituent
1,1,1 - Trichloroethane
1,1 - Dichloroethene
1,2,4 - Trimethylbenzene
1,3,5 - Trimethylbenzene
Benzene
Cis-1,2 - Dichloroethene
Ethylbenzene
Methylene chloride
Tetrachloroethene
Toluene
Trans- 1 ,2-dichloroethene
Trichloroethene
Vinyl chloride
Xylenes
Soil (mg/kg)
28.1
0.0006
11.1
6.9
0.2
3.2
43.2
0.37
0.656
75.5
3.6
0.17
0.12
None
Groundwater (ug/L)
210
0.1
None
None
5
70
700
12.1
5
1,000
100
5
2
10,000
2.2.1 Operable Units 1 and 2
The remedial design for OU1 and OU2 was completed and approved by EPA in
September 1997 (Sverdrup Environmental, Inc., 1993). The design for OU1 included plans and
specifications for the installation of a SVE and treatment system utilizing an existing SVE process
skid with carbon canisters. The design for OU2 included plans and specifications for the
demolition and reconstruction of a portion of the existing building foundation, construction of a
pre-engineered building, and installation of a 100 gallon per minute groundwater extraction and
treatment system. A vendor-supplied air stripping unit was utilized for OU2.
The EPA's contractor prepared a bid package that included plans and specifications for the
remedial action at OU1 and OU2. The procurement was advertised and the remedial action
contractor was selected. Construction began in March 1998, and was completed in August 1998.
The SVE system and groundwater extraction system were constructed per the March 9, 1998
conformed contract documents. EPA completed a pre-final inspection of the facilities on
November 3, 1999. Remaining activities at the OU1 and OU2 sites include continued operation
of the SVE system and the groundwater extraction and treatment facilities.
The NDEQ is responsible for operation and maintenance of the OU1 SVE. The SVE
system has not been operated since late September 2002. The NDEQ installed soil borings at
OU1 during the spring of 2004 to determine if the soils met the remediation goals and is planning
to restart the system in the near future.
The EPA has operated the OU2 groundwater extraction and treatment system since July
2000. VOC concentrations, including PCE and TCE, in the OU2 groundwater monitoring wells,
extraction wells, and Cleburn Street Well, which is not currently being used for drinking water
purposes, continue to exceed MCLs.
2.2.2 Operable Units 3 and 4
Two additional groundwater monitoring wells were constructed at both OU3 and OU4.
There were two existing groundwater monitoring wells at each operable unit. The installation and
development of the wells was performed during the period from March 31 to April 7, 1998.
Monitoring wells 1C and ID were installed at OU3 and monitoring wells 4C and 4D were
installed at OU4. Monitoring well 1C is approximately 28 feet deep and screened from 13.5 feet
below ground surface (bgs) to the bottom of the well. Monitoring well ID is approximately 88
feet deep and screened from 78 feet bgs to the bottom. Monitoring well 4C is approximately 32.5
feet deep and screened from 17.5 feet bgs to the bottom of the well. Monitoring well 4D is
approximately 95 feet deep and screened from 85 feet bgs to the bottom of the well.
The EPA's contractor sampled the four wells at each of the operable units for VOCs on a
quarterly basis from April 1998 through July 1999. Responsibility for sampling of these wells has
been transferred to the NDEQ. The University of Nebraska at Kearney, under a cooperative
agreement with NDEQ, sampled the monitoring wells for VOCs on a semi-annual basis through
October 2002.
The PCE concentrations at OU3 decreased from a maximum of 77 ug/L in March 2000 to
concentrations between 15 ug/L in MW-1A and 26 ug/L in MW-1C during the October 2002
sampling event. PCE concentrations at OU4 steadily decreased from 13 ug/L in March 2000 to
less than 2 ug/L (detection limit) in October 2002. From September 2001 through October 2002,
all of the VOCs in groundwater samples at OU4 have been below MCLs.
2.2.3 Operable Unit 5
The UPRR managed the design and construction of the soil and groundwater treatment
facilities at OU5. The soil remedy, construction of a SVE system, was managed in two phases.
Phase 1 of the SVE system was constructed as part of a SVE treatability study and consisted oftwo extraction wells, piping, an air compressor, a vacuum blower, an oil / water separator,
activated carbon filter, coalescing / particulate filter, and a blower building. The extraction wells
were installed in June 1999 and the remaining Phase 1 facilities were constructed in November
1999. Phase 2 consisted of the addition of five new SVE wells (four in the west parcel and one in
the east parcel), the associated piping, sixteen [16] air sparging wells, a temporary building, an air
compressor, a thermal oxidizer [short term], two [2] granulated activated carbon filters [long
term], control and gaging network, and the associated hardware. The remedial design for the
remainder of the SVE system in the east and west parcels and the air sparging system was
submitted in July 2003 and was approved by EPA in January 2004. UPRR's consultant prepared
a bid package that included plans and specifications for the remedial action. A remedial action
contractor was selected and began construction in April 2004. Construction, including meshing of
the two phases of the remedial action at OU5, was completed in June 2004. The EPA conducted
site visits during April 13 and 14, 2004; May 5 and 6, 2004; May 17, 2004; May 18 and 19, 2004;
and June 3, 2004 to observe the installation of the SVE system and the air sparging system ({four
reports} Black & Veatch, 2004).
A final inspection of the SVE system and the air sparging system was performed on
June 30, 2004. The EPA determined that the SVE system and the air sparging systems had been
constructed substantially in accordance with the plans and specifications and a three (3) itempunch list was developed and submitted to the UPRR for action. Participants who performed the
final inspection included Dr. Brian Zurbucken of NDEQ; David Sanders of Black & Veatch; Mike
Mason of the Forrester Group; Cliff Hillin of Geotechnical Services, Inc.; and Glenn Curtis and
John Cook of the EPA. Because the construction was so near complete, it was decided that an on-
site final inspection was not required. In place of that inspection it was decided by EPA that a
letter from the UPRR, certifying that all three of the punch list items had been properly addressed,
would suffice for the on-site final inspection of the facilities. In an August 9, 2004 letter to
UPRR, the EPA accepted the construction of the SVE system and the air sparging system.
3.0 DEMONSTRATION OF CLEAN-UP ACTIVITY QA/QC
At OU1 and OU2, EPA developed a Construction Quality Assurance Plan (CQAP) dated
September 16, 1997, as part of the Final Remedial Design Report for OU1 and OU2 (Sverdrup
Environmental, Inc., 1997). The CQAP addressed both the SVE system and the air stripping
system. The EPA provided oversight during construction of the facilities (Sverdrup
Environmental, Inc., 1997). All construction appeared to have been completed in accordance with
the ROD. The approved plans and specifications and any minor variations were approved by the
EPA.
The EPA installed groundwater monitoring wells MW-1C and MW-1D at OU3 and MW-
4C and MW-4D at OU4. According to the March 23, 1999, Final Remedial Action Report for
OU3 and OU4 (Sverdrup Environmental, 1999), compliance with the project planning documents
was achieved. No major instances of deviation or non-compliance were noted.
UPRR's consultant submitted a CQAP as part of the final design documents for both the
SVE system and the air sparging system at OU5. UPRR's consultant also provided oversight
during the construction of the facilities. The CQAP was used throughout the construction
activities. Site QA/QC audits were provided by UPRR's consultant. In addition, oversight visits
were conducted on four [4] occasions during April through June of 2004 to observe the progress
of the work and trip oversight reports ({four reports} Black & Veatch, 2004) were filed. All
construction appeared to have been completed in accordance with the ROD and the approved
plans and specifications. Accordingly, the work was approved by the EPA.
4.0 ACTIVITIES AND SCHEDULE FOR SITE COMPLETION
Pre-final and final inspections were completed for the SVE system and the groundwater
extraction and treatment facilities at OU1 and OU2. The NDEQ is responsible for the operation
and maintenance of the OU1 SVE. The SVE system has not operated since September 2002. The
NDEQ installed soil borings at the OU1 site during the spring of 2004 to determine if the soils
met the remediation goals.
The EPA has performed operation and maintenance of the facilities at OU2 since July
2000 and performs quarterly monitoring of the groundwater monitoring wells, the influent to the
air stripping unit, and the effluent from the air stripping unit ({multiple reports} Black & Veatch,
2002 - 2004). Quarterly monitoring reports have been submitted to the EPA through April 2004
and are scheduled to continue through June 2005 when EPA's current contract ends. A new
contract to continue this effort will be instituted at that time.
A pre-fmal inspection was performed for both the SVE system and the air sparging system
at OU5. The EPA, in a letter dated August 8, 2004, accepted as complete the construction of the
SVE system and the air sparging system at OU5.
The following activities and associated schedule are estimated for the life of the project.
ACTIVITY
NDEQ will continue to sample the SVE and air sparging
wells at OU1
EPA will continue to sample the groundwater monitoringwells, and the influent and effluent from the air stripping
unit at OU2.
NDEQ will continue to sample monitoring groundwater
wells at OU3 and OU4
UPRR will perform performance monitoring of the influent
and exhaust from the SVE air treatment facilities at OU5.
UPRR will perform monitoring of the in-situ vapor
monitoring points and SVE wells at OU5.
UPRR will perform ambient air sampling at the site forVOCs at OU5.
UPRR will sample total flow from the knockout tank atOU5.
UPRR will sample groundwater monitoring wells at OU5.
EPA will review data from the SVE system and the air
sparging system at OU5 to determine if confirmation
sampling of soil may proceed at OU5 and whether eitherthe SVE systems or groundwater systems may be shut
down.
SCHEDULE
Quarterly
Quarterly
Quarterly
Weekly until the system is shut
down
Quarterly until the system is shut
down
Quarterly until the system is shutdown
Weekly until the system is shutdown
Quarterly
Ongoing
10
EPA will review data from the SVE system and the air
stripping units at OU1 and OU2, the groundwater
monitoring wells at OU2 to determine if the remedial
action at OU1 and OU2 are completed.
EPA will review data from the groundwater monitoring
wells to determine that the remedial action at OU3 and
OU4 are completed.
UPRR notifies EPA and NDEQ that the remedial action
work is completed at OU5.
EPA and NDEQ conduct an inspection at OU5 in response
to the RA completion notification.
EPA produces and signs final close-out report for OU5.
EPA performed the first 5-year review.
EPA will perform the second 5-year review .
Ongoing
Ongoing
Tentatively July 2005
Tentatively August 2005
Tentatively September 2005
September 2003
September 2008
The schedule listed above is based upon the assumption that the SVE system and the air
sparging system as designed for OU5 will achieve the soil and groundwater cleanup goals within a
one [1 yr.] year period after construction is completed. It is possible that the SVE and air sparging
systems could take longer to reach the cleanup goals. In that event, the systems will continue to
operate or EPA, NDEQ, and UPRR will discuss the options required to modify the remedy, as
needed, to achieve the remedial action objectives as expeditiously as practicable.
5.0 SUMMARY OF REMEDIATION COSTS
The costs associated with the remediation of the Cleburn Street Well Site are shown
below.
CATEGORY
Total Capital Costs of SVE and AirStripping Systems at OU1
Annual O&M costs of SVE and AirStripping Systems for OU1
Total Capital Costs of groundwaterpumping and monitoring at OU2
COST ESTIMATE ($)
$74,478'
$87,848'
$370,072'
ACTUAL COST
$69,6833
$82,0627
$364,2493
11
Annual O&M costs of groundwater
pumping and monitoring OU2
Total Capital Costs of OU3 and OU4
Annual O&M costs for OU3 and OU4
Total Capital Costs of SVE and Air
Sparging Systems for OU5
Annual O&M Costs of SVE and Air
Sparging Systems for OU5
$150,0743
$101,600'
$38,464'
$421,2542
$218,8382
$89,9685
$85,072"
$12,1057
$431,9506
Not yet available
1 Source: June 1996 Record of Decision.2 Source: September 2001 Record of Decision.3 Source: Interim Remedial Action Report, Cleburn Street Site, Operable Units 1 & 2; December 28, 1999.4 Source: Final Remedial Action Report, Cleburn Street Site, Operable units 3 & 4, March 23, 1999.5 Source: B&V RAC Invoices 2000 - 2004 (Average report cost for last four [4 yrs.] years).6 Source: UPRR Internal Construction Analysis 2004.7 Source: Cooperative Agreement Between NDEQ and University of Nebraska - Kearney 12-15-99
VI. FIVE- YEAR REVIEW
Section 121 (c) of the Comprehensive Environmental Response, Compensation, and
Liability Act (CERCLA), as amended, and Section 300.430(f)(4)(ii) of the National Contingency
Plan (NCP) require that periodic reviews (at least once every five years) be conducted for sites
where hazardous substances, pollutants, or contaminants remain at the site above levels that allow
for unlimited use or unrestricted exposure following the completion of all remedial actions for thesite. This type of five-year review is referred to as a statutory review.
The first five year review for the Cleburn Street Well was completed on September 30,
2003. The second five year review will be due in September 2008.
Cecil
Director
Superfund Division
Date
12