rail safety summary report - parliament of nsw...technical failures 7 local...
TRANSCRIPT
Contributing Factors in NSW Rail Incidents 2004 – 2013 i
RAIL SAFETY SUMMARY REPORT
CONTRIBUTING FACTORS IN NSW RAIL INCIDENTS
2004 – 2013
RAIL SAFETY SUMMARY REPORT
CONTRIBUTING FACTORS IN NSW RAIL INCIDENTS
2004 – 2013
Released under the provisions of Section 45C (2) of the Transport Administration Act 1988
Investigation Reference 04679
Published by: The Office of Transport Safety Investigations
Postal address: PO Box A2616, Sydney South, NSW 1235
Office location: Level 17, 201 Elizabeth Street, Sydney NSW 2000
Telephone: 02 9322 9200
Accident and incident notification: 1800 677 766
Facsimile: 02 9322 9299
E-mail: [email protected]
Internet: www.otsi.nsw.gov.au
This Report is Copyright©. In the interests of enhancing the value of the information
contained in this Report, its contents may be copied, downloaded, displayed, printed,
reproduced and distributed, but only in unaltered form (and retaining this notice). However,
copyright in material contained in this Report which has been obtained by the Office of
Transport Safety Investigations from other agencies, private individuals or organisations,
belongs to those agencies, individuals or organisations. Where use of their material is
sought, a direct approach will need to be made to the owning agencies, individuals or
organisations.
Subject to the provisions of the Copyright Act 1968, no other use may be made of the
material in this Report unless permission of the Office of Transport Safety Investigations has
been obtained.
THE OFFICE OF TRANSPORT SAFETY INVESTIGATIONS
The Office of Transport Safety Investigations (OTSI) is an independent NSW agency whose purpose is to improve transport safety through the investigation of accidents and incidents in the rail, bus and ferry industries. OTSI investigations are independent of regulatory, operator or other external entities. Established on 1 January 2004 by the Transport Administration Act 1988, and confirmed by amending legislation as an independent statutory office on 1 July 2005, OTSI is responsible for determining the causes and contributing factors of accidents and to make recommendations for the implementation of remedial safety action to prevent recurrence. Importantly, however, OTSI does not confine itself to the consideration of just those matters that caused or contributed to a particular accident; it also seeks to identify any transport safety matters which, if left unaddressed, might contribute to other accidents. This OTSI rail safety summary report was initiated in accordance with the provisions of the Transport Administration Act 1988.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 i
TABLE OF CONTENTS
TABLE OF FIGURES iii
Abstract 1
Introduction 2
Contributing Factors Framework 2
Occurrence categories 3
Analysis of contributing factors from OTSI rail reports 5
Individual/team actions 6
Technical failures 7
Local conditions/organisational factors 8
Local conditions 10
Organisation factors 15
Investigation report summaries and contributing factors 20
1. Baan Baa - Level Crossing Collision - 4 May 2004 21
2. Port Botany - Shunting Fatality - 1 July 2004 23
3. Bethungra - Derailment - 22 December 2004 25
4. Lapstone/Wauchope - Derailment – 1 & 7 March 2005 27
5. Old Burren - Derailment - 6 April 2005 29
6. Grawlin Plains - Level Crossing Collision - 31 May 2005 31
7. Bloomfield- Opposing movement - 20 August 2005 33
8. Steel sleepers – Systemic report -2005 36
9. Conoble- Derailment - 16 October 2005 38
10. Lidcombe - Derailment – 4 November 2005 40
11. Ariah Park – Shunting fatality – 15 April 2006 42
12. Baan Baa – Ballast wagon fatality – 22 May 2006 45
13. Town Hall Tunnel - Self harm fatality - 30 August 2006 47
14. North Strathfield – Opposing movement – 2 September 2006 49
15. Thirroul – SPAD and derailment – 11 September 2006 51
16. Nyngan – Derailment – 1 October 2006 53
17. Sandgate – Track work injury – 7 November 2006 55
18. Leeton – Derailment – 11 January 2007 57
19. Euabalong West – Derailment – 14 January 2007 60
20. Connemarra – Derailment – 8 February 2007 62
21. Singleton – Track worker fatalities – 16 July 2007 64
22. Breeza – Derailment – 8 January 2008 67
23. Homebush – SPAD and Derailment – 7 January 2009 69
24. Unanderra – SPAD and Derailment – 24 January 2009 71
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 ii
25. Peak Hill – Derailment – 8 February 2009 74
26. Goobang – SPAD and collision – 10 May 2009 77
27. Temora – Runaway wagon – 28 July 2009 79
28. Glenlee – Safeworking breach – 28 October 2009 81
29. Darling Park – Monorail collision – 27 February 2010 83
30. Whittingham – Derailment – 13 March 2010 85
31. Strathfield – Near strike of maintenance staff – 1 April 2010 87
32. Woy Woy – Unsecured container gate – 11 April 2010 90
33. Kogarah – Track worker fatality – 13 April 2010 92
34. Wee Waa – Level crossing collision – 1 September 2010 96
35. Bankstown – Near miss with track workers – 29 October 2010 98
36. Unanderra – Uncontrolled movement – 2 February 2011 100
37. Zig Zag – Collision between a train and a Hi-rail – 1 April 2011 102
38. Enfield yard – Runaway rolling stock – 3 May 2011 105
39. Woy Woy – Level crossing collision – 2 Sep 2011 107
40. Clifton – Broken axle derailment – 23 Nov 2011 109
41. Unanderra – Safeworking incident – 12 Dec 2011 111
42. Gunnedah – SPAD and opposing movement – 7 March 2012 113
43. Nundah – Level crossing collision – 7 May 2012 115
44. Bengalla – Ballast train collision – 18 May 2012 117
45. Summit Tank – Safeworking incident – 17 July 2012 120
46. Boggabri – Coal train derailment – 28 Nov 2012 122
47. Gulgong – Wagon structural failure – 5 Dec 2012 124
48. Rennie – Derailment – 3 January 2013 126
49. Moree – Level crossing collision – 21 May 2013 128
50. East Maitland – Safeworking incident – 27 November 2013 130
51. Moss Vale – Safeworking incident – 21 December 2013 132
Appendix A: Contributing factors framework overview 134
Appendix B: Contributing factors framework analysis 135
Appendix C: OTSI rail investigation reports with keywords 138
Appendix D: Incident notification and classification 142
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 iii
TABLE OF FIGURES
Figure 1: Reason’s model of organisational accidents 3
Figure 2: OTSI investigations classified using OC-G1 4
Figure 3: Main contributing factors groups 5
Figure 4: Individual/team action findings grouped by person type 6
Figure 5: Technical failure findings grouped by component area 7
Figure 6: Local conditions and organisational factors 8
Figure 7: Knowledge, skills and experience type findings 10
Figure 8: Task demands type findings 11
Figure 9: Personal factors type findings 12
Figure 10: Physical environment type findings 13
Figure 11: Social environment type findings 14
Figure 12: Organisational management type findings 15
Figure 13: Equipment, plant and infrastructure type findings 16
Figure 14: Procedure type findings 17
Figure 15: People management type findings 18
Figure 16: Training and assessment type findings 19
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 1
Abstract The aim of this report is to record in summary form the results of the classification and
analysis of the findings from Office of Transport Safety Investigations rail safety
investigations.
All the findings from the 51 rail safety investigations undertaken in the 10 year period from
2004 to 2013 were examined. The contributing factors were then identified and coded in
accordance with a Contributing Factors Framework based on Professor James Reason’s
Model of Organisational Accidents. Of the total of 346 findings, 277 (80%) were classified in
the contributing factors group of organisational factors/local conditions. Individual/ team
actions contributed on 49 occasions and technical failures on 20 occasions. The findings
are further classified within each main contributing factors group. The results are presented
in graphical form together with examples from the investigations.
The report contains a brief overview of each investigation accompanied by general
occurrence information. All related findings are tabulated along with their contributing factors
framework details.
No specific recommendations are made in this report. However, rail industry stakeholders
would benefit from using the contributing factors framework as a method to analyse findings
from investigation reports. This would facilitate comparison of contributing factors as a
means to better understand frequently occurring issues and possible industry-wide trends.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 2
Introduction This report records the results from the analysis and classification of the findings from Office
of Transport Safety Investigations (OTSI) rail safety investigations.
The classification system used is the Contributing Factors Framework (CFF), an overview of
which is included in Appendix A. The Rail Safety Regulators Panel published the CFF to
assist interested parties in classifying the key findings of rail safety investigations. The CFF
was developed by a working group comprised of representatives from Australian safety
regulators, the rail industry, and independent rail safety investigation agencies. Work on the
framework began in 2005 and the first version was published in February 2009. OTSI has
applied the framework to its rail investigation findings progressively since its introduction.
The aim of the framework is to:
provide a structured and consistent framework to code the systemic contributors to
incidents and accidents
facilitate the analysis of aggregate data to identify patterns and trends in safety
issues
assist in making informed decisions on safety issues and enhance continual
improvement practices.1
Contributing Factors Framework The CFF is based on the Professor James Reason Model of Organisational Accidents2
which has been widely adopted across the rail industry and other safety critical industries.
This adapted model is illustrated in Figure 1.
This model starts with the organisational factors such as strategic decisions and
organisational processes. The processes are influenced by the corporate culture of the
business. These processes transfer throughout the organisation and give rise to task and
environmental conditions that are likely to lead to violations and errors by individuals/teams
in the workplace, or to technical failures.
1 Rail Safety Regulators Panel (2011): Contributing Factors Framework Manual, Version 2, p.8. 2 Ibid., p.16.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 3
Figure 1: Reason’s model of organisational accidents
The CFF coding process occurs after the formal investigation is concluded. The coding is
then entered into a database for analysis and identification of systemic safety trends. A
summary of the CFF applied to OTSI investigations is included in Appendix B.
The trends that have emerged from OTSI rail safety investigations are evident from the data
presented in the first section of this report. The second section of this report provides a brief
background summary for each investigation along with occurrence details. All related
findings are then tabulated along with the results of the CFF analysis.
A list of OTSI rail safety investigations along with relevant CFF keywords is included in
Appendix C. A full version of each investigation report is available on the OTSI website at
otsi.nsw.gov.au
Occurrence categories Every OTSI rail safety investigation report was classified according to the Occurrence
Classification Guideline (OC-G1) (see Figure 2). Derailment was the most frequent
investigation type. There were 20 derailment investigations, 11 collisions between rail
vehicles, eight safeworking incidents, six level crossing collisions, and three signals passed
at danger (SPADS). Two SPADs involved the driver completely missing the signal, while the
other was a driver misjudgement.
Organisation
Management systems,
decisions & organisational
processes
Local Conditions
Workplace -Task /
Environment
Error and violation
producing conditions
Individual / Teams
Errors & violations
Occurrence
Latent failure pathway
Direct failure
pathway
Social, Political, Regulatory & Economic environment…
Technical failures
Contributing factors
Investigation pathway
Organisation
Management systems,
decisions & organisational
processes
Local Conditions
Workplace -Task /
Environment
Error and violation
producing conditions
Individual / Teams
Errors & violations
Occurrence
Latent failure pathway
Direct failure
pathway
Social, Political, Regulatory & Economic environment…
Technical failures
Contributing factors
Investigation pathwayInvestigation pathway
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 4
Figure 2: OTSI investigations classified using OC-G1
The complete list of OC-G1 occurrence categories and related OTSI investigations is
contained in Appendix D. The number of OTSI’s investigations represents only a small
sample of the large number of reported accidents and safety-related rail incidents. The
number and categories of investigations should not be taken in any way to be proportionally
representative of the total of reported incidents.
20
11
86
31 1 1
0
5
10
15
20
25
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 5
Analysis of contributing factors from OTSI rail reports During the period from 2004-2013 there were 345 findings recorded in the 51 OTSI
investigations. There were 49 findings made about individual or team actions, 20 findings
made about technical failures, and 276 findings made about organisational factors or local
conditions (see Figure 3). ‘The evidence from a large number of accident inquiries indicates
that bad events are more often the result of error-prone situations and error-prone activities
than they are of error-prone people.’3
Figure 3: Main contributing factors groups
Most of the findings were classified in the organisational factors/local conditions category.
Not all reports made findings about individual’s actions and only a small proportion of
findings were about technical failures. These groupings of individual/team actions, technical
failures, and organisational factors/local conditions are further analysed in the following
sections of this report.
3 Reason, J. (1997). Managing the risks of organizational accidents, Ashgate, p.129.
Individual / team actions,
49Technical Failures, 20
Organisational Factors/Local conditions, 276
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 6
Individual/team actions
The individuals identified in the findings area of the individual/team action area were from the
following groups: infrastructure maintainers, light passenger vehicle drivers, network
controllers, rolling stock maintainers, terminal staff and train crew (see Figure 4). Station
staff, heavy freight vehicle drivers or emergency services staff were not identified in any
report.
Figure 4: Individual/team action findings grouped by person type
Of the train crew identified seven were passenger train drivers, seven were freight train
drivers, two were track machine operators and one was a guard.
The six light passenger vehicle drivers identified in the findings were all car drivers involved
in incidents at level crossings.
Infrastructure maintainers, 14
Light passenger vehicle driver,
6
Network controller, 8
Rollingstock maintainer, 1
Terminal staff, 3
Train crew, 17
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 7
Technical failures The technical failure components identified in the findings came from the following groups:
infrastructure, rolling stock, and signalling and communications equipment (see Figure 5).
Figure 5: Technical failure findings grouped by component area
The condition of the track was identified as a contributing factor in all 12 instances of
infrastructure failure. The origin of the failure was maintenance related in the majority of
cases.
Bogies, braking systems, car bodies, and a train detection system were the component
areas found to have contributed to rolling stock failures. A train detection system failure
occurred in the monorail accident where the anti-collision emergency stop system on the
monorail did not function as designed.
The signalling and communication failure resulted from a CCTV camera being sighted such
that its field of vision was partially obscured by a platform structure.
Infrastructure, 12
Rollingstock, 7
Signalling & communication equipment, 1
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 8
Local conditions/organisational factors
The analysis of organisational factors/local conditions found that organisational factor
findings were made most often. The 276 findings were split between 102 local conditions
and 174 organisational factors (see Figure 6).
Figure 6: Local conditions and organisational factors
‘Local conditions can be considered conditions present in the local workplace or environment
in which the individual/team action or a technical failure occurs.’4 They are grouped under
the following headings:
knowledge, skills and experience
personal factors
physical environment
social environment
task demands.
‘Organisation factors are those factors in the management system, decision-making at the
senior level and policy settings that guide the activities of the organisation.’5 They can
4 Contributing Factors Framework Manual, Version 2, p.22. 5 Ibid., p.22.
Local Conditions, 102
Organisational factors, 174
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 9
sometimes be identified in organisations other than the one directly responsible for the
occurrence.
Organisational factors are grouped as:
organisational management
equipment, plant and infrastructure
people management
procedures
training and assessment
external organisational influences.
These factors may be within the organisation’s internal or external environment.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 10
Local conditions
The most frequently identified local conditions findings were in the knowledge, skills and
experience area. These included persons having trouble with normal operational tasks, lack
of communication skills, inadequate task experience, poor abnormal/ emergency skills and
deficient teamwork skills (see Figure 7).
Figure 7: Knowledge, skills and experience type findings
Examples of knowledge, skills and experience findings can be found in the following
investigations:
An abnormal/emergency skills finding was made in the 2005 Bloomfield opposing
movement investigation. Neither train crew operated the emergency function on the
radio system to report the incident because, having avoided a collision, they did not
consider that they had been involved in an emergency.
In the 2010 Kogarah investigation recordings revealed that voice communications
from train control were informal and not in accordance with network rules and
procedures.
The 2012 Gulgong investigation found that a defective welded joint completed during
a normal operational task was not detected during inspections. This contributed to a
structural failure in a wagon.
19
11
7
5
2
0
2
4
6
8
10
12
14
16
18
20
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 11
The next most common category was in the area of task demands (see Figure 8). The most
significant factor in this area was distraction. Other factors identified were high workload,
being under time pressure and familiarity with the task.
Figure 8: Task demands type findings
Examples of task demand findings can be found in the following investigations:
The 2006 Ariah Park investigation found that the shunter may have been distracted
by the presence of spectators in close proximity as he attempted to couple the tender
and the carriage.
At Singleton in 2007 a high level of task familiarity was found to have lessened the
workers’ appreciation of the risks associated with their task. This accident resulted in
two fatalities when the workers were struck by a train.
A high workload was found to have contributed to the 2009 Glenlee near miss when
a driver returning from a train inspection was almost struck by an oncoming train on
the adjacent track. The workload of network controllers was high prior to and at the
time of the incident.
A near miss at Bankstown in 2010 occurred because a protection officer did not see
workers enter the danger zone as he was distracted by using his mobile phone.
In 2010 at Strathfield a work team was under time pressure to perform a task. They
had insufficient time to complete a full safety assessment and work plan in addition to
all other necessary preparatory tasks. As a consequence, they were nearly struck by
a passing train.
12
4
3
1
0
2
4
6
8
10
12
14
Distraction Time pressure High workload Familarity
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 12
There were 16 findings made in the area of personal factors. These included problems with
fatigue/alertness, motivation/attitude, preoccupation, stress/anxiety and health (see Figure
9).
Figure 9: Personal factors type findings
Examples of personal factor findings can be found in the following investigations:
The 2005 Lidcombe derailment investigation found that the driver was affected by
fatigue as he had not slept well the night before his shift.
The investigation into the fatalities at Singleton in 2007 found that both workers had
worked seven shifts over the preceding seven days. Consequently, both workers
were probably suffering from a degree of fatigue.
The 2009 Peak Hill derailment investigation found that the co-driver was
incapacitated through illness. Therefore, he was unable to perform his duties of
maintaining a lookout and relaying trackside infrastructure information to the driver.
Similarly, the 2009 Unanderra SPAD and derailment investigation found that the
guard was feeling stressed and unwell which affected his decision-making ability at a
critical time.
8
4
2
1 1
0
1
2
3
4
5
6
7
8
9
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 13
The physical environment was found to be a contributing factor on 15 occasions. The
following factors were identified: lighting/visibility, noise, temperature/humidity, and weather
related factors. There was one finding where an unstable surface contributed to the incident
(see Figure 10).
Figure 10: Physical environment type findings
Examples of physical environment findings can be found in the following investigations:
A noise-related finding was made in the 2006 Sandgate investigation into a track
worker injury. The track worker’s ability to hear the approaching excavator would
have been affected by the noise associated with the cutting and welding tasks he
was performing, as well as the operation of trains on the adjacent lines.
An unstable surface contributed to a fatality at Baan Baa in 2006. Stepping onto a
loosely-packed, rough, sloping ballast shoulder from a ballast machine increased the
risk of an accident.
The 2012 Bengalla ballast train collision investigation found that the lights were not
illuminated on a stationary track machine. Because it was a dark night, the pilot on
the propelling train did not see the track machine until just before his train collided
with it.
8
2 2 2
1
0
1
2
3
4
5
6
7
8
9
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 14
The social environment was found to be a contributing factor on seven occasions. Norms
and values and peer pressure were the two areas identified (see Figure 11).
Figure 11: Social environment type findings
Examples of social environment findings can be found in the following investigations:
The investigation into a collision on the Zig Zag Railway in 2011 found there was an
accepted practice of qualified workers authorising rail traffic movements without
reference to the train controller. On the day of the incident a guard authorised a hi-rail
movement resulting in it subsequently colliding with a train.
The 2012 Gunnedah SPAD and opposing movement investigation found that the co-
driver was under training, was relatively inexperienced and an authority gradient
existed between him and the driver. This contributed to him not taking more positive
action when the driver did not comply with procedures in stopping the train before the
signal.
5
2
0
1
2
3
4
5
6
Norms and values Peer pressure
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 15
Organisation factors
The most frequently identified organisational factor findings were in the organisational
management area (see Figure 12).
Figure 12: Organisational management type findings
Examples of organisational management findings can be found in the following
investigations:
A monitoring, review and validation finding was made in the 2008 Breeza derailment
investigation. The rail was not adequately constrained against the forces on it due to
ineffective anchoring. The task of replacing anchors following track work several
months prior to the derailment had not been completed when the incident occurred.
23
21
10
6
43 3 3
2 10
5
10
15
20
25
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 16
The investigation into the uncontrolled movement of a train at Unanderra in 2011
found that the modifications made to the brake pipe of a particular class of wagons
did not meet engineering requirements.
The next most common category was in the area of equipment, plant and infrastructure (see
Figure13).
Figure 13: Equipment, plant and infrastructure type findings
Examples of equipment, plant and infrastructure findings can be found in the following
investigations:
The investigation into a railway crossing accident at Nundah in 2012 found the
crossing did not fully meet the requirements of Australian Standards. There was no
visible stop line accompanying the stop sign.
A safeworking incident occurred at Moss Vale in 2013. It was found that there were
no designated locations where train crew could conduct axle bearing inspections
after an axle alert was triggered by a trackside detector.
15
12
6
4
3
21 1
0
2
4
6
8
10
12
14
16
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 17
In many incidents it was found that problems with procedures contributed to the incident
occurring. There were 31 findings associated with procedures. These included problems with
the accuracy or clarity of procedures, absent procedures, and one instance where the
procedure was not available or accessible (see Figure14).
Figure 14: Procedure type findings
Examples of procedure findings can be found in the following investigations:
Inspection standards for unit train maintenance not emphasising the examination of
the axle barrel contributed to a derailment at Clifton in 2011.
An investigation into a derailment at Rennie in 2013 found there was not a standard
or guideline to assist track managers in responding to unfavourable individual track
geometry measurements.
In 2013 there was a safeworking incident at Unanderra where the investigation found
that the train crew did not have access to procedures to check how protection should
be requested and implemented.
17
13
10
5
10
15
20
Accuracy / clarity Absent procedure Availability / accessibility
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 18
There were 10 findings associated with people management (see Figure15).
Figure 15: People management type findings
Examples of people management findings can be found in the following investigations:
A train driver involved in an opposing movement at North Strathfield in 2006 had
been rostered for nine consecutive days. The area controller had been rostered for
eight consecutive days. These rostering arrangements were found to have
contributed to the driver missing a signal.
At Whittingham in 2010 the supervisor did not adequately supervise a worker to
ensure the route was correctly set after the points were set and clipped. As a result a
freight train derailed on the points.
A specified welding process which made the weld technically difficult for the welder
during manufacture was found to have contributed to the structural failure of a wagon
at Gulgong in 2012.
5
2 21
0
1
2
3
4
5
6
Job / task design Rostering /scheduling Supervision Fitness for duty monitoring
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 19
There was also a total of 11 findings associated with training and assessment (see
Figure16).
Figure 16: Training and assessment type findings
Examples of training and assessment findings can be found in the following investigations:
At Kogarah in 2010 workers were caught on the track with a train approaching and
no safe place readily accessible. During their induction and worksite protection
training there was insufficient coverage of the emergency safety precautions to be
taken in such circumstances.
An investigation into a safeworking incident at East Maitland in 2013 found that the
on-job training provided to the protection officer was inadequate. Although the on-job
workbook was signed off to confirm that he had demonstrated knowledge in a wide
range of tasks and procedures, the reality was different.
The final category is external organisational influences. It had the least number of findings of
any category. Within this category one finding was made concerning regulatory activities and
one finding was made about industry standards.
These examples of external organisational influence findings can be found in the following
investigations:
The investigation into a derailment at Bethungra in2004 found that the NSW rail
regulator did not have sufficient visibility of the condition of the track and related
infrastructure.
The investigation into the uncontrolled movement of a train at Unanderra in 2011 found that there was no industry standard defining what constituted single and dual pipe wagons. Such a standard would be expected to cover various engineering aspects such as the purpose, application, flow rates and timing in reference to charge rates.
5
2 2 2
0
1
2
3
4
5
6
Initial training Competency assessment
Currency tracking Ongoing training
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 20
Investigation report summaries and contributing factors
The following section contains a brief summary of each incident and the findings made for
each investigation. The occurrence details are also provided with information on the number
of injuries and fatalities, the event description and type of operation (passenger, freight or
track maintenance) included in the details is the OC-G1 categorisation.
Occurrence details (Example shown below)
Event description: Passenger train collision with car at level crossing
Type of operation: Passenger
Fatalities 1 Injuries: 4
Occurrence Classification Level crossing occurrence Collision with road vehicle
At crossing with passive warning devices: Stop signs
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 21
1. Baan Baa - Level Crossing Collision - 4 May 2004
At 5.10pm a passenger service, carrying 33 passengers and three crew members, collided
with a motor vehicle, with the driver as the sole occupant on the Baranbah Street Level
Crossing at Baan Baa. Baan Baa is located between Boggabri and Narrabri in the Northwest
Plains region of NSW. Following the collision, the leading carriage of the two carriage consist
derailed and came to rest on its right side across the tracks approximately 420 metres
beyond the crossing. The rear carriage remained upright.
As a result of the collision the driver of the car, who
was a local resident, was fatally injured; four train
passengers were hospitalised and a number of
persons, both passengers and train crew, were treated
on site for shock and minor injuries; the car was
destroyed and there was considerable damage to the
train and track. The rail line was closed for three days
to effect repairs.
The investigation established that the accident was a consequence of the car being
positioned within the crossing’s danger zone. The investigation could not establish whether
this was an unintentional or intentional act.
The investigation also established that the respective mechanical conditions of the car and
train did not contribute in any way to the accident. It also established that the train driver
operated the train within specified limits and that he
responded appropriately when it became apparent that a
collision was in prospect.
Whilst emergency services responded efficiently and
effectively to the accident, the evacuation of passengers
and crew from the train was complicated by a number of
the train’s design features. As a consequence of this investigation OTSI made a number of
recommendations to RailCorp, the Australian Rail Track Corporation (ARTC) and the
Independent Transport Safety and Reliability Regulator (ITSRR).
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 22
Occurrence details
Event description: Passenger train collision with car at level crossing
Type of operation: Passenger
Fatalities 1 Injuries: 4
Occurrence Classification Level crossing occurrence Collision with road vehicle
At crossing with passive warning devices: Stop signs
Individual actions
Findings Person type Activity type Error/Violation
type
OTSI found that the collision at the level crossing was the
consequence of a failure of the driver of the motor vehicle
to observe NSW traffic rules 121 and 123. OTSI was
unable to determine whether this failure was the
consequence of an unintended act (an error), or an
intended act (a violation).
Light passenger
vehicle driver
Monitoring and
checking
Unknown
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
There were limited defences to warn drivers of motor
vehicles on their approach to the level crossing, or to assist
them to remain clear of the rail line when necessary.
Equipment, plant
& infrastructure
Infrastructure
design
Road
environment
Design features on the Xplorer, under certain
circumstances, inhibit emergency egress.
Equipment, plant
& infrastructure
Functionality Rolling stock
construction
Additional safety equipment is required aboard services
operated by RailCorp.
Equipment, plant
& infrastructure
Availability Rolling stock
construction
Emergency services were inhibited by a lack of specific
knowledge in relation to emergency access points and
power shut-down.
Knowledge, skills
& experience
Emergency
operations
knowledge & skills
Emergency
management
RailCorp’s imposition of blanket speed restrictions
throughout most of regional NSW has reduced the
prospect, and consequences, of collisions at level
crossings.
Organisational
management
Policy On-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 23
2. Port Botany - Shunting Fatality - 1 July 2004
At 1.50pm on 1 July 2004, a shunter was fatally injured whilst involved in shunting
operations at the Port Botany rail yard. The employee, a qualified train driver, is believed to
have fallen from the decking of a flat top container wagon through a gap in the wagon’s floor
during a shunting movement. Following this fall he was run over by the train’s wheels.
The Driver of the train (T250) involved in the shunting
operation went in search of the shunter, as he had failed
to respond to a planned radio communication. The
shunter was subsequently located across the track by
the driver. There were no eyewitnesses to the accident.
The investigation established that the accident was a
consequence of the shunter being on top of the wagon’s
decking, without the means of a physical restraint, whilst the wagon was in motion. The
design of the wagon featured a smooth skeletal decking which did not incorporate any form
of protection against the risk of falling onto the track.
Based on the information obtained during the investigation
and forensic reports, it was concluded that the shunter
probably lost his footing because of either a jolting
movement, a slip or as a consequence of a momentary
loss of concentration, whilst standing on top of an un-
walled and only partially decked wagon during shunting. It
was found that the company’s risk assessment did not
consider in detail the operational activities of a shunter and the likely risks arising from those
activities. There were no Operator Specific Procedures which covered the company’s
accepted practices for riding on wagon side steps or end steps. Also, the company was
unable to stop the practice of riding on the top of un-walled wagons where they had had prior
knowledge that such a practice had occurred previously within the railway yard environment.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 24
Occurrence details Event description: Shunter killed after falling from flat top container wagon
Type of operation: Freight
Fatalities 1 Injuries: nil
Occurrence Classification Collision Yard collision
With a person not on a level crossing
Individual actions
Findings Person type Activity type Error/Violation
type
The positioning of the Shunter on top of the wagon’s
decking, without the means of a physical restraint, whilst
the wagon was in motion.
Terminal staff Operating
equipment
Violation
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional
area
The design of the wagon, which featured a skeletal and
smooth decking and which did not incorporate any form of
protection against the danger of falling onto the track.
Equipment, plant &
infrastructure
Functionality Rolling stock
construction
The company’s risk assessment and risk management
process did not consider in detail the operational activities
of a shunter and the likely risks arising from those
activities.
Organisational
Management
Risk Management Off-train
operations
The limitations of the company’s approach to training,
competency assessment and supervision, noting the
absence of Operator Specific Procedures that defined
accepted practices for riding on wagon sides and the
supporting training documentation designed to instruct a
shunter in these practices.
Procedures Absent procedure Off-train
operations
The design of side and end steps of some freight wagon
types do not facilitate a safe/ergonomic riding position and
may have encouraged the use of alternate, and unsafe,
riding positions.
Equipment, plant &
infrastructure
Functionality Off-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 25
3. Bethungra - Derailment - 22 December 2004
At 8.05pm on 22 December 2004 freight service 4VM9, operated by Freight Australia
Limited, derailed whilst descending the grade at Bethungra, on the main south line. 4VM9
consisted of four locomotives and 11 loaded bulk cement wagons and was en route from
Berrima to Melbourne. All 11 wagons from the train and 288 metres of track were severely
damaged as a result of the incident. There were no reported injuries.
The investigation found 4VM9 derailed when it traversed
an area of misaligned and unstable track. The
derailment occurred where the rail had been stressed for
a considerable period of time and that track resurfacing
work 16 days prior to the derailment would have
exacerbated this stress. The initiation of emergency
braking, at a speed 6km/h in excess of the posted speed
limit, when the misalignment first became apparent, would have imparted additional stress to
the track. However, the magnitude of this stress would not have been significant had the
track been stable and properly aligned.
Two of the primary defences designed to prevent such occurrences, track inspections and
track maintenance, failed over time. A third defence of managing an area with known
deficiencies through the imposition of speed limits was not employed.
There were clear indications available to the NSW Rail
Infrastructure Corporation (RIC), and subsequently the
Australian Rail Track Corporation (ARTC), to suggest
track instability in the area where the derailment occurred,
but that these indicators were either unnoticed or not
acted upon. Track inspection records for the previous 12
months implied that there were few problems within the
section in which the derailment occurred. However, inspections of a relatively small area
within the section by the Office of Transport Safety Investigations, revealed that there were
significant defects and that these were not a recent phenomena, suggesting that previous
inspections had been less than thorough.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 26
Occurrence details Event description: A main line derailment of a freight train
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure mechanism Failure origin
4VM9 derailed when it traversed an area of misaligned
and unstable track.
Infrastructure - Track Deformation Maintenance
Local Condition/Organisational factor
Findings Local
Condition/Organisa
tional factor
Keywords Functional area
The initiation of emergency braking, at a speed 6km/h in
excess of the posted speed limit, when the misalignment
first became apparent, would have imparted additional
stress to the track. However, the magnitude of this stress
would not have been significant had the track been stable
and properly aligned.
Knowledge, skills
& experience
Abnormal/emergency
operations
knowledge & skills
On-train
operations
Two of the primary defences designed to prevent such
occurrences, track inspections and track maintenance, failed
over time, and a third defence, of managing an area with
known deficiencies through the imposition of speed limits,
was not employed.
Organisational
Management
Risk Management Infrastructure
construction and
maintenance
There were clear indications available to RIC, and
subsequently ARTC, to suggest track instability in the area
where the derailment occurred, but that these indicators
were either unnoticed or not actioned.
Organisational
Management
Risk Management Infrastructure
construction and
maintenance
Track inspection records for the previous 12 months,
compiled by RIC and ARTC, implied that there were few
problems within the section in which the derailment
occurred. However, OTSI’s inspections of a relatively small
area within the section revealed that there were significant
defects and that these were not a recent phenomena,
suggesting that both RIC’s and ARTC’s inspections had
been less than thorough.
Organisational
Management
Monitoring, review
and validation
Infrastructure
construction and
maintenance
The transition of assets, records and systems from RIC to
ARTC was problematic and that ARTC did not enjoy good
visibility of the condition of the asset at the time of handover
of responsibility, or indeed at the time of the derailment.
Organisational
Management
Interface
management
Infrastructure
construction and
maintenance
ITSRR does not have sufficient visibility of the condition of
the track and related infrastructure in NSW and that, whilst it
can and does undertake a range of actions to gain such
visibility, the onus for providing ITSRR with such visibility
should largely rest with those responsible for its operation.
External
organisational
influences
Regulatory
activities
Infrastructure
construction and
maintenance
The derailment occurred where the rail had been stressed
for a considerable period of time and that track resurfacing
work 16 days prior to the derailment would have
exacerbated these stresses.
Organisational
Management
Monitoring, review
and validation
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 27
4. Lapstone/Wauchope - Derailment – 1 & 7 March 2005
On 1 March 2005, at approximately 1:55pm, Pacific National coal service CB76 suffered a
screwed journal after a Packaged Unit Bearing (PUB) failed. As a result of this mechanical
failure, a wagon derailed but remained upright and attached to CB76. The wagon travelled
4.28km in this state and in the process caused significant track damage between Glenbrook
and Lapstone. It also caused ballast to be dislodged from a rail bridge over the Great
Western Highway, shattering the windscreen of a car below. Another incident occurred at
approximately 11:15am, on 7 March 2005, when Pacific National freight service 1WB3 also
suffered a screwed journal when a Packaged Unit Bearing failed. One wagon derailed,
approximately 11km North of Wauchope, but remained upright and attached to 1WB3. As a
consequence, approximately 3km of track and a rail bridge were damaged.
The investigation found that both derailments were
caused by the failure of PUBs. There was nothing to
suggest, in either instance, that the PUBs had been
inadequately maintained or that there were problems
elsewhere on the bogies. Nor were the wagons
overloaded. Both PUBs were virtually destroyed and
there was no conclusive evidence to indicate what
initiated their failure. There were some limited indications to suggest that both bearings
might have been penetrated by moisture or some other foreign material. Pacific National
suspects that in the case of CB76, this may have occurred while the wagon was being
pressure-cleaned. However, this possibility and Pacific National’s premise could not be
confirmed.
Pacific National had appropriate policies in place to
minimise the likelihood of PUBs failing and continued to
refine its policies and practices to further reduce the
related risks. ARTC and RailCorp have plans to expand
and upgrade the range of monitoring and detection
systems throughout the rail network in NSW which would l
contribute to enhancing the safety of rail operations.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 28
Occurrence details Event description: A main line derailment of freight train as a result of a screwed journal
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
Failure of packaged unit bearings. Rolling stock - Bogies Fracture Unknown
Local Condition/Organisational factor
Findings Local Condition/Organisational
factor
Keywords Functional area
nil nil nil nil
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 29
5. Old Burren - Derailment - 6 April 2005
At approximately 5.45pm a fully loaded wheat train operated by Pacific National Limited,
designated as wheat service 5424, derailed on a Class 5 single grain line North West of
Narrabri. As a result of the derailment, which occurred at a location known as Old Burren in
the section of track between Merrywinebone and Burren Junction, six of 37 wheat hopper
wagons came off the rails and were damaged, 87 metres of track was damaged and 17
tonnes of wheat was lost. Neither crew members from the train were physically injured in the
derailment.
The journey from Merrywinebone was uneventful until
5424 exited a curve where the crew recalled noting a
small kick in the rails to their front. The driver was not
concerned about the misalignment; indeed, he indicated
that such occurrences were not uncommon and did not
consider it necessary to adjust the train’s speed of
28km/h, which was below the speed limit of 30km/h.
However, he did maintain observation of the rest of 5424 in his rear vision mirrors.
Both crew members recall that their locomotive wobbled slightly as it passed over the kick.
The driver observed the train ride over the kick and then noticed the leading wagons begin to
rock from side to side, progressively more violently. He immediately shut off the throttle and
applied the emergency brakes. As the train came to a stand, the driver recalls seeing and
feeling some of the wagons kick out sideways off the track before 5424 came to rest.
It was noted that the driver saw the misalignment and had
sufficient time to reduce train speed. However, he elected
not to do so, on the basis of his experience and the fact
that such track conditions were not uncommon to him.
However, it is possible that if the driver had reduced the
train’s speed, the misalignment may have been safely
negotiated. The investigation found 5424 derailed when
misaligned and unstable track spread under load. The condition of the track was not a recent
phenomenon and could be attributed to progressive and un-remediated degradation.
Inspection, defect recording and maintenance systems in the region were less than
sufficiently robust or integrated to provide adequate managerial oversight of the asset and its
condition.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 30
Occurrence details Event description: A main line derailment of freight train
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The train derailed when a misaligned and unstable
track spread under load.
Infrastructure - Track Deformation Maintenance
Local Condition/Organisational factor
Findings Local
Condition/Organisation
al factor
Keywords Functional area
The condition of the track was not a recent
phenomenon and could be attributed to progressive
and unremediated degradation.
Organisational
management
Business
planning and
asset/ resource
management
Infrastructure
construction and
maintenance
Inspection, defect recording and maintenance
systems in the region were less than sufficiently
robust or integrated to provide adequate managerial
oversight of the asset and its condition.
Organisational
management
Monitoring,
review and
validation
Infrastructure
construction and
maintenance
There is continued utilisation of Class 5 lines that do
not meet the required standards under the provisions
of a waiver system that was introduced by RIC,
embraced by ARTC, but which was never
countenanced by the ITSRR and which expired on 1
October 2004.
Organisational
management
Risk/change
management
Infrastructure
construction and
maintenance
Adherence to track engineering standards appears to
have assumed less significance and risk management
appears to have been increasingly devolved to a local
level. Such practises might be acceptable were they
informed by a detailed understanding of track
conditions and deliberate decision-making.
Organisational
management
Risk/change
management
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 31
6. Grawlin Plains - Level Crossing Collision - 31 May 2005
At approximately 3.00pm a single locomotive operated by the Australian Railway Group
collided with a Toyota Landcruiser towing a trailer on a level crossing at Grawlin Plains,
approximately 10 km South of Forbes in the Central West Region of NSW.
The driver of the Landcruiser, a local farmer, was
fatally injured in the collision and his vehicle was
destroyed. The locomotive remained on the track and
came to a stand approximately 350m past the point of
impact. The locomotive suffered minor damage to the
front headstock region and various side-mounted
components. The track infrastructure was not damaged
but debris was scattered over 350m of the track. While there were no injuries to the crew of
the locomotive, both members were treated for shock.
The major safety issues identified in this report relate to
the actions of the driver of the motor vehicle; the
immediate response of the Locomotive’s crew; passive
level crossing safety; train communications and
emergency response. The investigation established that
the collision was caused by the failure of the driver of the
Landcruiser to commence braking in sufficient time for
him to stop and give way to the Locomotive, as was required by Australian Road Rule 121.
The speed at which the driver of the Landcruiser approached the level crossing was not
consistent with a prior intention to stop at the crossing. The driver’s chances of survival were
further diminished because he was not wearing a seat belt at the time of the accident and
that the seat belt he should have been wearing was defective.
Other findings were that the road signage on the approaches to, and at, the level crossing
did not conform to the minimum requirements prescribed by Australian Standard
1742.7:1993, Manual of Uniform Traffic Control Devices, Part 7: Railway Crossings. Also
road users approaching the level crossing from the East had their visibility of trains
approaching from the South obstructed by the presence of trees, vegetation and a wheat
silo.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 32
Occurrence details
Event description: Passenger train collision with car at level crossing
Type of operation: Freight
Fatalities 1 Injuries: nil
Occurrence Classification Level crossing occurrence Collision with road vehicle
At crossing with passive warning devices: Stop signs
Individual actions
Findings Person type Activity type Error/Violation
type
The collision was caused by the failure of the driver of the
Landcruiser to commence braking in sufficient time for him
to stop and give way to the Locomotive, as was required
by Australian Road Rule 121.
Light passenger
vehicle driver
Monitoring and
checking
Unknown
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
There were limited defences to warn drivers of motor
vehicles on their approach to the level crossing, or to assist
them to remain clear of the rail line when necessary.
Equipment, plant
& infrastructure
Signage Road
environment
Design features on the Xplorer, under certain
circumstances, inhibit emergency egress.
Equipment, plant &
infrastructure
Functionality Rolling stock
construction
Additional safety equipment is required aboard services
operated by RailCorp.
Equipment, plant
& infrastructure
Availability Rolling stock
construction
Emergency Services were inhibited by a lack of specific
knowledge in relation to emergency access points and
power shut-down.
Knowledge, skills &
experience
Emergency
operations
knowledge & skills
Emergency
management
RailCorp’s imposition of blanket speed restrictions
throughout most of regional NSW has reduced the
prospect, and consequences, of collisions at level
crossings.
Organisational
management
Policy On-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 33
7. Bloomfield- Opposing movement - 20 August 2005
At approximately 11.27am two Pacific National Limited coal trains, designated DS184 and
DS233 respectively, were routed into the same section of track from opposing directions.
The opposing movement occurred when DS233 exited one of four sets of parallel lines at
Thornton in the Hunter Valley Region of NSW, under controlled signalling arrangements, and
entered the single line track leading into the Bloomfield Colliery. As it approached the
Thornton staff hut where it was required to stop and where its crew was required to
communicate with the Train Controller, DS233 was confronted by DS184 which was awaiting
a final clearance to depart the Colliery. The driver of DS233 was able to bring his train to a
stand approximately 64 metres from DS184 and all but one service was able to be diverted
around DS233, the rear of which remained on one of the main lines. There was no damage
or injuries as a result of the incident.
The opposing movement occurred when the Train
Controller at the Broadmeadow Hunter Train Control
Centre (HTCC) authorised the movement of DS233
into the Bloomfield Colliery Branch Line, having
overlooked the fact that DS184 was awaiting a
clearance to exit the same track. This oversight was
caused by the fact that the Broadmeadow HTCC Train
Controller was pre-occupied with the requirement to
reschedule train movements elsewhere, due to a points failure at Whittingham,
approximately 50km North West of Thornton. In addition, because DS184 was not standing
on circuited track, neither the Broadmeadow HTCC Train Controller nor the Area Controller
at Maitland Signal Box had the benefit of having the train’s position illuminated on their track
indication panels.
Operations on the Bloomfield Colliery line were unusual in
that it was the only location on the network where a single
line Staff and Ticket section leads into and out of a
balloon loop. The investigation established that the
opposing movement would not have occurred had the
driver of DS184 communicated with the train controller
and advised him that he could not move as scheduled
because he did not have a signal to proceed. However, he was not obliged to do so; delayed
departures from the Bloomfield Colliery line were not unusual and drivers were not always
given an explanation for the delays or a revised departure time.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 34
Occurrence details
Event description: Opposing movement by two freight trains
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Safeworking rule/procedure
breach
Token based system rule procedure breach
Individual actions – Network Controller
Findings Person type Activity type Error/Violation type
The opposing movement occurred when the Train
Controller at the Broadmeadow Hunter Train Control
Centre (HTCC) authorised the movement of DS233 into
the Bloomfield Colliery Branch Line, having overlooked the
fact that DS184 was awaiting a clearance to exit the same
track.
Network
controller
Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
This oversight was caused by the fact that the
Broadmeadow HTCC Train Controller was pre-occupied
with the requirement to reschedule train movements
elsewhere, due to a points failure at Whittingham,
approximately 50kms North West of Thornton.
Task Demands High workload Off-train operations
In addition, because DS184 was not standing on circuited
track, neither the Broadmeadow HTCC Train Controller nor
the Area Controller at Maitland Signal Box (MSB) had the
benefit of having the train’s position illuminated on their
track indication panels.
Equipment, plant &
infrastructure
Absent equipment,
plant &
infrastructure
Off-train operations
Operations on the Bloomfield Colliery line are unusual in
that it is the only location on the network where a single
line Staff and Ticket section leads into and out of a balloon
loop. The frequency of train movements on the line is also
irregular.
Knowledge, skills
& experience
Abnormal/
emergency
operations
knowledge & skills
Off-train operations
These factors increased the potential for error and were
compounded by the fact that DS184 and DS233 were
operating at a point where two different systems of
safeworking each with its own procedures, intersected.
Procedures Accuracy/clarity Off-train
operations
Having lost visibility of DS184 after it left Thornton staff hut,
there were no additional procedures or prompts that might
have reminded the Area Controller at MSB that the train
was still on the Bloomfield Colliery line.
Procedures Absent procedure Off-train
operations
ARTC’s Network Rules and Procedures is the capstone
reference for train operations in territory controlled by
ARTC. These rules are supplemented by Local Appendix
Unit 217 (LAU 217) and General Order 8-2001 which
contain local and specific orders for safeworking at
Thornton. However, there were subtle differences between
these safeworking procedures which, in conjunction with
the uniqueness of the track layout at Thornton and the
Knowledge, skills &
experience
Task experience Off-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 35
relative infrequency of operations there, resulted in
different levels of understanding between some Drivers,
Area Controllers and Train Controllers in relation to their
obligations to communicate in certain circumstances.
The communications between all of the involved parties
did not conform to the requirements contained in ARTC’s
Network Rules and Procedures.
Knowledge, skills &
experience
Task experience Off-train
operations
Individual actions – Train Crew
Findings Person type Activity type Error/Violation type
The opposing movement would not have occurred had the
Driver of DS184 communicated with the Train Controller
(HTCC) and advised him that he could not move as
scheduled because he did not have a signal to proceed.
Train Crew Communicating Error
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
However, he was not obliged to do so; delayed departures
from the Bloomfield Colliery line are not unusual and
Drivers are not always given an explanation for the delays
or a revised departure time. Over time, and in the absence
of clear instructions in relation to the requirement to
communicate in such circumstances, some Drivers have
become conditioned to waiting for a proceed signal.
Procedures Accuracy/clarity Off-train
operations
Neither train crew operated the emergency function on the
Countrynet radio system to report the incident because,
having avoided a collision, they did not consider that they
had been involved in an emergency. However, part of
DS233 was still on the main line and an opportunity to
divert a following train was lost. Subsequently, however, all
other following trains were effectively diverted.
Knowledge, skills
& experience
Abnormal/
emergency
operations
knowledge &
skills
On-train
operations
The communications between all of the involved parties
did not conform to the requirements contained in ARTC’s
Network Rules and Procedures.
Knowledge, skills
& experience
Task experience On-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 36
8. Steel sleepers – Systemic report -2005
When the OTSI was established in 2004 it took over an investigation into a derailment at
Rocky Ponds in November 2002. This derailment had been caused by track misalignment.
One of the recommendations of the report was for OTSI to conduct a supplementary
investigation into the introduction and performance of steel sleepers in the NSW Rail
Network The systemic investigation found that in 1996 the decision was made to install steel
sleepers on the Main South line in a random installation pattern as a part of the Partial Re-
Sleepering program. This decision was made jointly at senior management level in the NSW
railway organisations of Rail Access Corporation (RAC) and Rail Services Australia (RSA).
The decision to continue with their installation was made against the advice of the
Engineering Standards Group and in contradiction of the manufacturer’s recommendation.
The Engineering Standards and Manufacturer’s advice
recommended that a heavier sleeper section be used
together with a different installation process. There was
no corporate standard in place covering the installation
within either organisation. There was also no track
stiffness design verification conducted to provide an
assurance that random steel sleepers would be
compatible when interspersed with timber sleepers. A standards waiver was not issued
before installation took place on Class 1 Main line track.
The decision to introduce steel sleepers on Class 1 Main line track revolved around two key
issues: the impending timber sleeper supply problem and the cost benefits to be gained from
the use of steel sleepers. The forecast supply problem with timber sleepers initiated a
number of studies into the alternatives regarding sleeper type and installation pattern. These
studies identified savings associated with the use of steel sleepers and decisions were made
based on these savings. The investigation found the creation of RAC and RSA in 1996 made
for an environment where changes to the infrastructure
could be carried out under processes that differed from
the previously vertically integrated State Rail. Changes to
business processes could be made more readily in the
newly formed organisations, especially where there had
been major organisational changes and loss of
personnel.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 37
Occurrence details Event description: A systemic investigation into the installation of steel sleepers in NSW. When the OTSI was
established in 2004 it took over an investigation into a derailment at Rocky Ponds in November
2002. This derailment had been caused by track misalignment. One of the recommendations of
the report was for: ’The Office of Transport Safety Investigation to conduct a supplementary
investigation into the introduction and performance of steel sleepers in the NSW Rail Network.
This investigation would seek to identify the basis on which steel sleepers where introduced into
the network and whether their introduction has increased the likelihood of track structure failures
to any significant extent.’
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The installation of steel sleepers on Class 1 main line in
1996 (Main West) and later in 1997 (Main South)
contravened the sleeper standard at that time.
Infrastructure - Track Other Installation/co
mmissioning
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
No immediate standards waivers were obtained to allow
installation of steel sleepers on Class 1 Main lines. A waiver
to the standard allowing for the change was ultimately
obtained some 18 months following the introduction.
Organisational
management
Risk/change
management
Infrastructure
construction and
maintenance
Installation procedure and pattern recommendations gained
from steel sleeper trials on the Main West Class 1 and Class
2 lines were not followed in the installation on the Main
South.
Organisational
management
Risk/change
management
Infrastructure
construction and
maintenance
No prior engineering trials were conducted on Class 1 Main
lines covering the modified installation process and patterns
employed on the Main South Class 1 line.
Organisational
management
Risk/change
management
Infrastructure
construction and
maintenance
Financial provision for the tamping of steel sleepers as they
were installed on the Class 1 Main South was inadequate in
the planning and the implementation stages.
Organisational
management
Business planning
& asset/ resource
management
Infrastructure
construction and
maintenance
The RAC Asset Management approach at the time of
installation was to proceed with the installation unless there
was engineering proof that steel sleepers were unsafe.
Organisational
management
Policy Infrastructure
construction and
maintenance
Controls over the identification of which timber sleepers
were to be removed were inadequate in the initial stages of
changeover.
Organisational
management
Information
management
Infrastructure
construction and
maintenance
The filling and compaction of steel sleeper ballast pods was
not consistently achieved due to the problems associated
with the revised installation process required by the
Maintainer.
Organisational
management
Contractor/
interface
management
Infrastructure
construction and
maintenance
The inherent difficulties of identifying substandard
installation immediately following the installation process
meant that a measurement of quality could not be easily
associated with the installation.
Organisational
management
Contractor/
interface
management
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 38
9. Conoble- Derailment - 16 October 2005
At approximately 7:54am a Pacific National (PN) freight train, designated 7SP5, derailed one
unladen flat wagon in the vicinity of the township of Conoble in the Western Region of NSW.
After travelling a further 34.8km the wagon re-railed itself in the vicinity of the township of
Ivanhoe. The train driver was not aware of what had happened, but stopped the train some
133km later because he did not feel that it was as responsive as it should be. He found that
a brake pipe isolating cock, located between the 30th and 31st wagon, was in the up
(closed) position and that there was extensive damage to the rear wheel-set of the 30th
wagon in the consist.
The derailment of the rear wheel set of the rear bogies
of wagon RQKY 02034E was due to excessive lateral
movement of the bogie, known as hunting. The
constant contact side bearer components of the bogie
should have countered the tendency to hunt but they
had been fitted with incorrect resilient blocks when the
wagon underwent a major service less than four
months prior to the derailment. The fitting of the incorrect type of resilient blocks, RB 35
instead of RB 27, was attributable to human error. Three factors contributed to the error: the
maintenance crew were fitting RB 35 type blocks to other types of wagons during the
previous week; both types of blocks were the same colour and shape; and block storage
arrangements at the maintenance facility were inadequate for effective stock management.
The investigation found no evidence of train handling or
track condition having contributed to the derailment.
However, PN had been critical of the standard of the track
and its effect on ride quality between Parkes and Broken
Hill for some years, though the results of testing
conducted before and after the derailment have proven
inconclusive and remained contested between PN and
ARTC. The problem could be attributed to a system that focuses on measuring a variety of
parameters related to track geometry rather than the impact the combined effect of those
parameters might have on ride quality.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 39
Occurrence details Event description: A main line derailment of freight train.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The derailment of the rear wheel set of the rear bogies of
wagon RQKY 02034E occurred because the wagon was
‘hunting’. This was the result of the inability of the rear
bogie components to prevent or control excessive lateral
movement of the bogie.
Rolling stock- Bogie Wear Installation/
commissioning
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
The wagon’s Constant Contact Side Bearer’s were fitted
with incorrect resilient blocks when it underwent a major
service less than four months prior to the derailment. The
blocks wore very quickly to a state where they were not
providing effective dampening of the forces acting on the
wagon.
Equipment, plant &
infrastructure
Availability Rolling stock
construction and
maintenance
The fitting of the incorrect type of blocks, RB 35 instead of
RB 27, was attributable to human error. Three factors
contributed to the error: the maintenance crew were fitting
RB 35 type blocks to other types of wagons during the
previous week; both types of blocks are the same colour
and shape; and block storage arrangements at the facility
were inadequate for effective stock management.
Equipment, plant &
infrastructure
Availability Rolling stock
construction and
maintenance
PN’s train marshalling requirements were ambiguous
especially in their guidance to marshall lightly loaded
wagons to the rear, where possible. 7SP5 left the terminal
where its consist was formed with four empty wagons
which were very close to the front of the consist. Wagon
RQKY 02034E was arguably towards the rear but could
have been positioned closer to the rear in Sydney.
Whether or not the positioning of the wagon contributed to
the derailment cannot be determined but, at least, there is
scope for more definitive guidance on train marshalling.
Procedures Clarity Off-train
operation
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 40
10. Lidcombe - Derailment – 4 November 2005
At approximately 12:07am 4BM7, a Brisbane to Melbourne freight service, passed Signal ST
419GL at Stop without authority whilst traversing the Lidcombe Goods Loop and derailed at
a set of catch-points identified as No.717. The catch-points were deliberately positioned
beyond Signal ST 419GL to derail any train that passed the signal at Stop without authority,
to mitigate the risk of collision with trains on the nearby main line.
4BM7 consisted of two locomotives and 34 container
wagons and was operated by Interail Australia Pty Ltd,
a subsidiary of Queensland Rail. The leading
locomotive derailed all wheels before becoming
embedded in the ballast and resting against a small
safety wall on top of an eight metre-high embankment.
The second locomotive derailed all wheels on the
leading bogie but remained upright. There were no injuries resulting from the derailment.
The derailment occurred when the driver of 4BM7 failed to
respond to a Stop indication at Signal ST 419GL and ran
through a set of catch-points which performed as they
were designed to, by deliberately derailing the train to
prevent both unauthorised entry onto the main line and
the inherent hazard that such unauthorised entry would
pose to authorised main line traffic.
Other findings were that the driver had only been at the controls of 4BM7 for approximately
10 minutes and was still adjusting to the train’s handling. In addition, he had not slept well
following his previous shift. These factors, and the prospect of proceeding on holidays the
next day, may also have affected the driver’s attentiveness. No.717 catch-points functioned
as intended. However, the placement of the catch-points did not conform to RailCorp’s
design standards.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 41
Occurrence details
Event description: SPAD and derailment of freight train.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Individual actions
Findings Person type Activity type Error/Violation type
The derailment occurred when the driver of 4BM7 failed to
respond to a Stop indication at Signal ST 419GL and ran
through a set of catch-points which performed as they
were designed to, by deliberately derailing the train to
prevent both unauthorised entry onto the main line and the
inherent hazard that such unauthorised entry would pose
to authorised main line traffic.
Train crew Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
Notwithstanding an indication from the preceding Signal
ST 422S, which indicated that he should proceed with
caution, the driver admitted to being complacent during his
approach to Signal ST 419GL because it was his
expectation that the Signal would be displaying a proceed,
or ‘calling on’, indication. This expectation was based on
his previous experiences at the Signal where he claims he
had never previously been required to stop.
Personal factors Motivation/
attitude
On-train operations
A large peppercorn tree on the Western side of the track
restricted the driver’s visibility until he was approximately
93 metres from Signal ST 419GL. However, had the driver
maintained proper control of 4BM7 in accordance with the
previous signal indication, he would have had sufficient
time and distance, albeit with a small margin for error, to
bring 4BM7 to a stand prior to Signal ST 419GL.
Physical
environment
Visibility Infrastructure,
construction and
maintenance
Knowledge, skills &
experience
Normal
operations
knowledge &
skills
The driver had only been at the controls of 4BM7 for
approximately 10 minutes and was still adjusting to the
train’s handling. In addition, he had not slept well following
his previous shift. These factors, and the prospect of
proceeding on holidays the next day, may also have
affected the driver’s attentiveness.
Personal factors Fatigue/
alertness
On-train operations
RailCorp has a maintenance program to check on matters
that might impact on the operation or visibility of signals,
but this program failed to detect what was an obvious and
long-standing obstruction, caused by a large peppercorn
tree on the Western side of the track, 93 metres from
Signal ST 419GL.
Organisational
management
Information
management
Infrastructure,
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 42
11. Ariah Park – Shunting fatality – 15 April 2006
A heritage passenger steam train operated by Lachlan
Valley Railway Society Cooperative Ltd was
participating in an event to celebrate the centenary of
the opening of the rail line between Temora and Ariah.
The train consisted of a 32 Class steam locomotive,
No. 3237, its tender and five passenger carriages. For
the journey from Temora to Ariah Park, it was designated SS83 and configured with the
tender of the locomotive leading. It arrived at Ariah Park at 10:30am with approximately 160
passengers who disembarked at the platform and moved on foot to the site of a
commemorative ceremony adjacent to the Coolamon Street level crossing. The locomotive
and tender were detached from the carriages and moved
around the rail loop to take up a position near the level
crossing for the ceremony.
On completion of the ceremony at about 11:40am, the
locomotive and tender had to be reversed towards the
Ariah Park platform to be re-coupled with the carriages for
the return journey to Temora as heritage service SS84. The train’s Guard directed this
reversing movement with hand signals and was responsible for connecting the couplings
between the locomotive’s tender and the leading passenger carriage.
To engage the hook and link of the coupling mechanism, the Guard stepped into the gap
between the tender and the carriage on two occasions; initially to align the coupling link and
subsequently to place the carriage’s coupling link over the tender’s coupling hook. At
approximately 11:52am, as the Guard attempted to effect the coupling manoeuvre, he was
crushed between the tender and the carriage. The Guard received immediate emergency
treatment at the site of the incident and was then transported by ambulance to Temora
Hospital where he died shortly afterward from the injuries he had sustained.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 43
Occurrence details
Event description: A shunter was killed when he was crushed between carriages.
Type of operation: Freight
Fatalities 1 Injuries: nil
Occurrence Classification Collision Running line collision
With a person not on a level crossing
Individual actions
Findings Person type Activity type Error/Violation
type
The accident occurred when the Guard placed himself in
an unsafe position between a moving tender and a
stationary carriage in order to manually couple the two
pieces of rolling stock.
Train crew Operating
equipment
Error
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
The Guard had worked 18 shifts over the preceding 20
days and had been involved in preparation of the train well
into the evening before, and in the early morning on the
day of, the accident. It is likely, therefore, that the Guard
was affected by fatigue.
Personal factors Fatigue/
alertness
Off-train
operations
He may also have been distracted by the presence of
spectators in very close proximity to him as he attempted
to couple the tender and the carriage.
Task demands Distraction Off-train
operations
The Guard was an experienced rail safety worker but his
primary experience lay in signalling, and LVRS could not
provide evidence to show that he had formally qualified as
a shunter or that he had the competence to carry out
manual coupling tasks.
Organisational
management
Risk/ change
management
Off-train
operations
When the Guard stepped between the tender and the first
carriage, he lost contact with the Driver of the locomotive
because he did not employ another crew member to
repeat his hand signals to the Driver, as was required by
Lachlan Valley Operating Procedure (LVOP) 16.
Knowledge, skills
and experience
Normal
operations
knowledge and
skills
Off-train
operations
LVRS did not anticipate and manage a range of risks that
were associated with their operations on the day of the
accident, and their wider operations more generally.
Organisational
management
Risk/ change
management
Off-train
operations
LVRS was failing to employ its SMS and as such, was in
breach of the terms of its accreditation.
Organisational
management
Monitoring,
review and
validation
Off-train
operations
Video footage taken immediately prior to the incident
showed the Guard and Chairman of LVRS riding on a
ladder on the end of the locomotive’s tender which
contravened a prohibition notice, 02346/1 – 04/001105,
issued by ITSRR on 7 July 2004.
Organisational
management
Competence of
senior
personnel
Off-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 44
Documentation provided by LVRS confirmed that the
Driver was fully qualified to operate SS84 but similar
records could not be produced to substantiate the
qualifications of the remainder of the crew.
Organisational
management
Information
management
On-train
operations
The certificates of competency issued to the Fireman,
Supernumerary Fireman and LVRS’s Trainer/Assessor
had expired.
Training and
assessment
Competency
assessment
On-train
operations
The Supernumerary Fireman should have been required to
submit to an updated health assessment before returning
to crew duties following a serious injury, but this
requirement had not been complied with.
People management Fitness for duty
monitoring
On-train
operations
LVRS had established procedures for propelling, shunting
and coupling operations, including LVOP 10 (Propelling
Movements) and LVOP 16 (Screw Couplings & Transition
Links). However, its operating procedures had not been
amended to reflect the requirements of a prohibition notice,
issued by ITSRR in July 2004, in relation to riding on
moving . Nor had LVOPs been amended to reflect
requirements identified during successive audits by the
Regulator.
Organisational
management
Monitoring,
review and
validation
Off-train
operations
The decision to operate SS84 with a carriage that did not
have buffers and to attach it to the locomotive’s tender,
had risks that were not appreciated on the day. It was also
inconsistent with LVOP 16 which required crews to
“Ensure that vehicles with buffers are only coupled to other
vehicles fitted with buffers or diaphragms”.
Organisational
management
Risk/ change
management
Off-train
operations
LVRS did not have a proper understanding of its risks and
did not have an effective risk management framework in
place.
Organisational
management
Risk/ change
management
On-train
operations
ARTC’s policy on secondary employment “External
Employment (Policy Number HR06-004)” and the rostering
processes which underpin its management of fatigue,
warrant internal review.
Organisational
management
Policy Off-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 45
12. Baan Baa – Ballast wagon fatality – 22 May 2006
At approximately 9:00am a track worker employed by the Rail Infrastructure Corporation and
seconded to the Australian Rail Track Corporation was fatally injured while participating in
ballasting operations approximately 3km South of Baan Baa. The ballast train (5M23) was
crewed by two Southern & Silverton Railway Pty Ltd drivers and consisted of three
locomotives and 22 ballast wagons, with a plough van at the rear.
The fatally injured worker had
been one of a team of three track
workers who were controlling the
distribution of ballast. A fourth
worker operated the plough at the
rear of the train, reducing the
height of the ballast where
necessary so that it was no higher than the rails. A fifth worker supervised the operation from
the leading locomotive, while a sixth drove a support vehicle along the fire trail beside the
track.
In order to maintain continuity of ballast distribution, the
three track workers each rode at the front or rear of a
loaded wagon to operate the ballast hopper door controls,
alighting when the ballast in that wagon was depleted,
and re-joining the train at a loaded wagon by means of
the steps providing access to the walkway below the
hopper door controls. The ballasting operation
commenced at approximately 7:54am and was underway when at about 9:00am one of the
three ballast wagon operators saw a colleague lying on the ballast shoulder. He alerted the
rest of the crew and when they attended to the worker lying on the ballast, he was found to
have a major head injury and to be deceased.
The track worker died as a result of severe head injuries that were sustained by falling onto
the ballast shoulder and being struck by a ballast hopper side door of a passing wagon. No-
one witnessed the track worker’s fall so it could not be positively determined whether he fell
while getting off a moving ballast wagon, or while moving beside the track.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 46
Occurrence details
Event description: A ballast worker was killed when he fell onto the ballast.
Type of operation: Track maintenance
Fatalities 1 Injuries: nil
Occurrence Classification Collision Yard collision
With a person not on a level crossing
Individual actions
Findings Person type Activity type Error/Violation type
The track worker died as a result of severe head injuries that
were sustained by falling onto the ballast shoulder and being
struck by a ballast hopper side door of a passing wagon.
Infrastructure
maintainer
Operating
equipment
Error
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
Stepping down from a moving rail vehicle is inherently
dangerous and the danger is increased when stepping onto
a loosely-packed, rough, sloping ballast shoulder and these
were the prevailing conditions at the scene of the accident.
Physical
environment
Other –
unstable
surface
Infrastructure
construction and
maintenance
At the time of the accident the ballast train was moving at a
speed averaging between 9 and 10 km/h, significantly faster
than the 4 to 6 km/h at which ballast is usually laid and this
would have heightened the risks associated with movement
onto and off the ballast wagons and movement on the
ballast.
Task demands Time pressure Infrastructure
construction and
maintenance
The track workers sought to slow the train down but the
radio that was normally available to them had been
reallocated due to failure of the radio used by the plough
operator. This meant that their request could not be
communicated directly to, and therefore acted upon
immediately by, the driver.
Equipment, plant
and infrastructure
Absent
equipment
Infrastructure
construction and
maintenance
Both the Work Method Statement and the Pre-Work Brief
identified the dangers associated with the operation and
classified the related risk as being “medium” in nature. The
documents failed to identify any means other than the
exercise of care, to reduce the risk. In this regard the activity
planning was deficient.
Procedures Accuracy/
adequacy
Infrastructure
construction and
maintenance
The work plan specified a significantly greater amount of
work than could be performed in the available time. As a
consequence, the track workers were placed under pressure
and therefore exposed to increased risk.
Procedures Accuracy/
adequacy
Infrastructure
construction and
maintenance
The work plan contained no contingency provisions to be
implemented in the event that communications equipment
became unserviceable and there was no hand-held or other
radio as a back-up to ensure continuity of radio
communication in the event of an equipment malfunction.
Procedures Absent
procedure
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 47
13. Town Hall Tunnel - Self harm fatality - 30 August 2006
At approximately 4:25pm on Wednesday 30 August 2006, a 43 year old woman was struck
and killed by CityRail passenger service 10-F in an underground section of the Eastern
Suburbs Railway (ESR) between Town Hall and Central Railway Stations, approximately
238 metres North of Platform 25 at Central. The woman’s entrance into the tunnel was
unauthorised and evidence acquired after the incident indicates that she was intent on
committing suicide.
The Police and Emergency Services were notified and
upon entering the tunnel system were escorted to the
scene of the incident where they found the deceased
woman beneath the third carriage of the train. A
decision was made to evacuate the passengers
through the front of the train utilising the emergency
door in the train driver’s cab. It was initially estimated
that up to 1000 passengers were evacuated from the
train and escorted through the tunnel and onto Platform 25 at Central Station. During the
course of the evacuation, Ambulance officers were called to attend to a passenger who
suffered an anxiety attack.
The evacuation was completed at approximately 5:40pm
and the train was moved at 6:51pm, after which Police
completed their examination of the scene. The
investigation revealed that the woman entered the tunnel
via stairs leading from the platform to the track surface at
the Northern end of Platform 25 at Central Station. The
defences against unauthorised entry into the tunnel
system from Platform 25 consisted of signage at the tunnel portals, which was clearly visible,
indicating that public access to the tunnel system was prohibited, and a CCTV network to
monitor public movement on the platform. However, the CCTV camera best placed to
capture movement in the tunnel had its field of vision obscured by a platform structure.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 48
Occurrence details Event description: A passenger died after being struck by a train.
Type of operation: Passenger
Fatalities 1 Injuries: nil
Occurrence Classification Suspected suicide Struck by train
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The CCTV network is limited as a defence against
unauthorised entry into the tunnel system from
Platform 25 because the camera best placed to
capture movement into the tunnel had its field of vision
obscured by a platform structure.
Signalling and
Communications item:
Control interface
equipment
Other Installation/com
missioning
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 49
14. North Strathfield – Opposing movement – 2 September 2006
At approximately 1:08am an empty CityRail service 67-R passed Signal ST 164 at stop
without authority on the Down Relief line at North Strathfield and continued onto the single,
bi-directional Goods line between North Strathfield and Homebush, as the points were set
for this route. At the same time, Pacific National’s freight service 5YN2 was travelling on the
same Goods line between Flemington and Homebush, but in the opposite direction. 67-R
and 5YN2 were proceeding towards each other on the same line.
The Area Controller at Strathfield Signal Box witnessed
the evolving opposing movement on his indication
board and attempted to contact the Drivers of 67-R and
5YN2 by radio to direct them to stop their trains
immediately. The Driver of 5YN2 responded by
stopping his train as directed. However, the Area
Controller was unable to establish radio contact with
the Driver of 67-R because the Driver had entered the wrong train designation, or run
number, when he logged into the radio network. In the meantime, a number of other Area
Controllers stood on the balcony of the Strathfield Signal Box and tried to attract the
attention of the Driver of 67-R in an attempt to warn him of
the impending danger. In the face of what was an
imminent and significant emergency, other members in
the Strathfield Signal Box reacted quickly by making radio
calls to support the Area Controller and attempting to
warn the Driver of 67-R by using flags and hand lamps.
The Driver was unaware of these attempts to contact him
but eventually realised that he was on the wrong line and bought his train to a stand adjacent
to the Strathfield Signal Box and some 194 metres from the stationary 5YN2.
The opposing movement was a consequence of an error by the Driver of 67-R who either did
not see, or did not respond to, Signal ST 164 and passed the signal when it was at stop. As
a result, 67-R deviated from the intended route and proceeded onto on the same track as,
and travelling towards, 5YN2.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 50
Occurrence details
Event description: There was an opposing movement between a passenger train 67-R and freight train 5YN2
when 67-R passed signal ST164 at stop.
Type of operation: Passenger
Fatalities nil Injuries: nil
Occurrence Classification Signal Passed at Danger Completely missed while running
Individual actions
Findings Person type Activity type Error/Violation type
The Driver of 67-R who either did not see, or did not
respond to, Signal ST 164 and passed the signal when it
was at stop. As a result, 67-R deviated from the intended
route and proceeded onto on the same track as, and
travelling towards, 5YN2.
Train crew Monitoring and
checking
Error
Other Area Controllers stated that they would have set the
route in such a way that would have required the Driver to
have waited longer at Signal ST 168R but then given him a
clear run through Signal ST 164 and on to Strathfield.
Such a setting would also have provided an increased
safety margin.
Network controller Preparation
and planning
Error
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
Signal ST 164 is sited in a manner and location that meets
the required technical parameters; as such it should have
been readily apparent. However, as a ‘ground dwarf
signal’, it is lower than other signals in the immediate area
and may have been overlooked by the Driver in favour of
two Main Line signals in advance of it which were showing
proceed indications.
Equipment, plant
and infrastructure
Infrastructure
design
Infrastructure
construction and
maintenance
The Driver of 67-R had worked for nine consecutive days
and was due to proceed on rest days at the end of their
shift. There was an increased likelihood of him making an
error.
People
management
Rostering/
scheduling
On-train operations
The Area Controller had worked for eight consecutive days
and was due to proceed on rest days at the end of his
shift. There was an increased likelihood of him making an
error.
People
management
Rostering/
scheduling
Off-train operations
There was no record within RailCorp of Signal ST 164
having previously been passed at danger. Even so, Signal
ST 164 is not fitted with any form of mechanical protection,
such as a train stop or catch points, to mitigate the
consequences of a SPAD.
Equipment, plant
and infrastructure
Absent
equipment,
plant &
infrastructure
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 51
15. Thirroul – SPAD and derailment – 11 September 2006
At 5:32am the leading car on CityRail’s passenger service 312A operated by RailCorp
derailed at catchpoints in the vicinity of No.3 Platform at Thirroul after failing to stop at Signal
WG 568D. On approach to the signal the train did not respond to normal braking techniques
forcing the driver to apply his emergency brakes approximately 20 metres prior to the signal.
The train consisted of an eight-car Tangara set and
was carrying approximately 30 passengers who were
safely disembarked under the direction of the guard.
There were no injuries and only minor damage to the
train and track. The prevailing weather conditions were
wet and blustery. Speed, signalling anomalies, driver
fatigue and wheel and rail defects were able to be
readily excluded as contributory factors. Importantly, brake failure was eliminated at the
beginning of the investigation as a result of on-site testing undertaken by RailCorp
engineers. The investigation then focussed on track conditions and the braking process.
Severe weather conditions prevailing at the time were
found to be responsible for the formation of an emulsion
consisting of rust, moisture and salt building up on the rail
which had not been used for some 58 hours. This resulted
in a particularly slippery rail surface and consequent
reduced braking effectiveness. Historically, there had
been a number of similar situations of Tangaras
encountering stopping difficulties in wet and inclement
conditions at Thirroul and in the wider South Coast region. Further, having disc brakes, the
Tangara contributed less to rail head conditioning during normal operation than did trains
with brake shoes that help to remove contamination from the wheel tread.
In this instance, braking effectiveness was reduced to such a degree that significantly
greater stopping distances were needed than was usual. This should have been apparent to
the driver from an experience of minor wheel slip under similar conditions earlier in the trip.
However, insufficient allowance was made for the obvious reduction in braking effectiveness.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 52
Occurrence details
Event description: The leading car on CityRail’s passenger service derailed at catch-points at Thirroul after
failing to stop at Signal WG 568D.
Type of operation: Passenger
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Individual actions
Findings Person type Activity type Error/Violation type
The derailment occurred because passenger service 312A
proceeded past Signal WG 568D, which was at Stop, and
ran through a set of catch-points which performed in the
manner for which they were designed. The Driver sought
to comply with the signal by bringing his train to a stand but
it failed to respond because an emulsion formed by rust,
moisture and salt on top of the rails impeded the transfer of
braking effort.
Train crew Operating
equipment
Error
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
Actuation of the WSP module earlier in the trip was
followed by a more cautious braking technique by the
Driver for a short period, but this same degree of caution
was not in evidence on the approach to Thirroul.
Knowledge, skills
and experience
Abnormal/
emergency
operations
knowledge and
skills
On-train operations
The braking performance of all trains is downgraded by
wet conditions and this has contributed to a number of
SPADs, and instances of overshooting platforms and
colliding at dead-ends. A disproportionate number of these
have been on the South Coast, especially at Thirroul. It is
probable that this is due to the particularly slippery rail
conditions resulting from the moist, salty environment on
rails that may carry no traffic for extended periods.
Physical
environment
Weather-
related factors
On-train operations
The No. 3 Platform had not been used for 58 hours prior to
the derailment. If this had been in excess of 72 hours the
track may have been conditioned using a train operating
specifically for the purpose. However, the severity of the
weather conditions would have promoted oxidation of the
rail at a faster rate than normal. Tangaras are fitted with
disc brakes which make them less effective in conditioning
rail in the course of normal operation than trains fitted with
treaded brakes, and as a consequence the rearward
carriages would have had little benefit from conditioning by
the leading carriages.
Equipment plant
and infrastructure
Functionality On-train operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 53
16. Nyngan – Derailment – 1 October 2006
At 5:46am the trailing locomotive and 14 wagons within Pacific National Limited’s ore
container service 4835 derailed four kilometres South-East of a locality known as Miowera,
on a Class 3 freight line, between Nevertire and Nyngan in the Central West region of NSW.
These rail vehicles and 22 containers suffered varying degrees of damage. Fortunately,
there were no injuries.
4835 departed Nevertire at 5:15am for Nyngan. The
crew recalled the journey from Nevertire towards
Nyngan as being uneventful until shortly after passing
the 604 kilometre post when they felt the train jerk and
shudder. The Driver then observed, in the rear view
mirror on his side of the locomotive’s cabin, dust
emanating from underneath the train and noticed that
the brake air pressure gauge was indicating a loss of brake pipe pressure. His view to the
rear was then obscured by a large dust cloud. These signs typically indicate that some
portion of a train has derailed and the Driver therefore applied the train’s emergency brakes.
The Assistant Driver, who was seated on the opposite
side of the cabin, also recalled the jerk and watching the
second and third wagon disappear from sight in his mirror
before the dust also obscured his view
Event recordings captured on the two Hasler tapes
removed from 4835 indicated that the train had been
travelling at 78km/h at the time of the incident. This speed was under the posted speed limit
of 80km/h for the immediate area. The recordings also showed that 4835 had been operated
in accordance with ARTC’s Network Rules and Procedures and within posted track speed
limits up until the loss of brake pipe pressure at 5:46am, after which it came to a stand.
4835 derailed because the track over which it was travelling was in a poorly maintained
condition. The derailment at 604.120km occurred when a poorly-supported rail joint snapped
under the pressure of the weight of 4835’s approach. When this joint snapped, the exposed
rail end was struck by the wheels of 4835’s leading locomotive. Approximately 6m of rail
subsequently shattered and as a consequence, the trailing locomotive and 14 wagons
derailed.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 54
Occurrence details
Event description: A freight train derailment on a running line.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
4835 derailed because the track over which it was
travelling was in a poorly maintained condition. The
derailment at 604.120km occurred when a poorly-
supported rail joint snapped under the pressure of the
weight of 4835’s approach. When this joint snapped, the
exposed rail end was struck by the wheels of 4835’s
leading locomotive. Approximately 6m of rail subsequently
shattered and as a consequence, the trailing locomotive
and 14 wagons derailed. The rail-end became exposed
when the fishplates that had been used to join two lengths
of rail broke. Metallurgical testing established that this
breakage was associated with fatigue fractures that had
developed in the fishplates over time because of
inadequate support underneath the rail joint.
Infrastructure -
Track
Fracture Maintenance
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
The limitations in the condition of the track were readily
apparent but were not detected in successive track
inspections. This meant that ARTC lacked visibility of
issues that should have informed its maintenance and
track management priorities.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
ARTC has established standards, processes and an
‘‘Exceedent Control System” to identify and manage the
risks associated with track defects and/or failures.
However, these standards and processes were not
properly applied within the Nevertire-Nyngan rail section
and as a consequence ARTC lacked visibility of, and did
not act to address, defects that should have been readily
apparent.
Organisational
management
Risk/
change
management
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 55
17. Sandgate – Track work injury – 7 November 2006
At approximately 1:10pm a 24 year-old male track worker was preparing to weld a newly-laid
section of rail in an area where new track was being commissioned when he was struck by a
reversing Hi-rail excavator operated on behalf of John Holland Rail. The track worker was
severely injured, requiring hospitalisation and emergency surgery.
The welder and the excavator driver were engaged in
separate tasks associated with the construction of an
additional flyover to provide improved rail traffic flow at
Sandgate near Newcastle NSW. The excavator
operator was filling the shoulders of newly-laid track
with ballast and the welder was one of a crew of four
engaged in cutting the rail in preparation for welding
track panels together.
The welding crew completed three welds without incident and were working on their fourth
when the excavator approached. Although the welding crew was aware that an excavator
was operating in the general area, they were unaware of
its close proximity to them. The operator of the excavator
was being assisted by a spotter but neither saw the
welding crew and only became aware of its presence
when other workers nearby shouted to alert them to the
fact that the excavator had struck one of the welders.
One of the excavator’s wheels subsequently ran over the welder’s left arm forcing it into a
25mm gap which the welder had cut in preparation for joining the rail. Although his arm was
severely crushed in the process, had this gap not existed, the welder’s arm would most likely
have been severed.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 56
Occurrence details
Event description: A track worker was injured when he was struck by a reversing excavator.
Type of operation: Track maintenance
Fatalities nil Injuries: 1
Occurrence Classification Collision Yard collision
With a person not on a level crossing
Individual actions
Findings Person type Activity type Error/Violation type
The accident occurred because the welder and excavator
operator were oblivious to each other’s presence on the
track.
Infrastructure
maintainer
Operating
equipment
Error
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
The welder’s ability to see the approaching excavator was
further restricted by the safety goggles he was required to
wear, which limit peripheral vision.
Physical
environment
Visibility Infrastructure
construction and
maintenance
The welder’s ability to hear the approaching excavator
would have been affected by the noise associated with the
cutting and welding tasks he was performing, and the
operation of trains on the adjacent lines.
Physical
environment
Noise Infrastructure
construction and
maintenance
The nature of the task in which the excavator operator was
engaged required him to focus in the opposite direction to
that which the excavator was travelling this rendered the
excavator’s rear vision mirror ineffective.
Physical
environment
Visibility Infrastructure
construction and
maintenance
The excavator operator was being assisted by a ‘spotter’
but the spotter’s attention was focussed on protecting rail
traffic on an adjacent track, not on workers around the
excavator.
Task demands Distraction Infrastructure
construction and
maintenance
The excavator was fitted with a warning beacon but it was
ineffective because it was inoperable.
Equipment, plant
& infrastructure
Functionality Infrastructure
construction and
maintenance
The risks associated with the day’s tasking had been
identified but the controls that had been specified to
mitigate them were imprecise and therefore inadequate.
Organisational
management
Risk/ change
management
Infrastructure
construction and
maintenance
WorkCover NSW’s Code of Practice for Moving Plant on
Construction Sites, 2004 identifies that where heavy
machinery cannot be separated, particular controls need to
be in place. Had such defences been in place, the
excavator and welders would not have been permitted to
operate in close proximity to each other.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
The excavator operator was late for work and
consequently did not attend the safety briefing. However,
even if he had, the safety controls that were identified
during the briefing were imprecise and therefore
inadequate.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 57
18. Leeton – Derailment – 11 January 2007
At 5:30pm ten container wagons on Pacific National’s freight service 5CM3 derailed
approximately 3km North West of Leeton in the Riverina region of NSW. The train consisted
of three locomotives and 27 container wagons conveying 69 shipping containers, and was
en route from Griffith to Melbourne.
The derailment occurred on a straight section of track
as the train was slowing in preparation for a temporary
speed restriction just beyond the Griffith Road level
crossing. The 17th and 19th to 27th wagons derailed
and the train came to rest blocking the level crossing.
Police, Roads and Traffic Authority and Leeton Shire
Council personnel attended and directed road traffic to
an alternative crossing. Fortunately, the crew was not injured and there were no other
persons involved in the derailment.
The ten derailed wagons, three shipping containers on one of the wagons which overturned,
220m of track and the road surface at the level crossing sustained varying degrees of
damage. The NSW Rural Fire Service responded to a
small grass fire caused by the derailment.
The investigation found that the derailment was caused
by a lateral misalignment of the track at 615.987km. The
two main track-related factors contributing to the lateral
misalignment were found to be excessive compressive
forces in the rail, and failure of the track structure to contain the compressive forces. In
addition, it was found that, although the Australian Rail Track Corporation (ARTC) had
appropriate processes in place to monitor and measure the condition of the track, errors and
omissions in the records meant that an accurate depiction of the track condition was not
being recorded. This was particularly the case in regard to the annual welded track stability
analysis (WTSA) which did not detect any problems warranting other than routine
programmed maintenance. As the primary tool for detecting the potential for misalignments,
the WTSA had some limitations in that there were some conditions which it did not analyse.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 58
Occurrence details
Event description: A freight train derailed due to a track misalignment.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On Running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The derailment of PN freight service 5CM3 was caused by
a misalignment in the track at 615.987km as it was being
traversed by the train. The misalignment was of such
magnitude that travelling below the allowed speed could
not negotiate the reverse curves with a radius of
approximately 60m resulting from the misalignment.
Infrastructure -
Track
Deformation Maintenance
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
The investigation could not determine the specific cause of
the misalignment. However, it was most likely due to
structural weaknesses in the track that were not detected
during programmed track condition monitoring and that
may have been contributed to by mistakes made in the
welding process during the conversion of the track from
JWR to CWR.
Organisational
management
Risk/Change
management
Infrastructure
construction and
maintenance
The track structure lacked the structural rigidity to constrain
the forces acting on it, particularly the buckling forces
arising from the very hot prevailing conditions. Specifically:
• a disproportionate number of loose fastenings in the
predominately timber sleepers transferred the buckling
forces to the intermittently placed steel sleepers; and
• the steel sleepers did not contain a sufficient quantity of
compact ballast to provide the critical mass essential to
resist lateral movement.
Organisational
management
Risk/Change
management
Infrastructure
construction and
maintenance
Although ARTC had appropriate processes in place to
monitor and measure the condition of the track, errors and
omissions in the records meant that a true and accurate
indication of the situation was not being represented. This
was particularly the case with regard to the WTSA
completed on the basis of data collected in 2006 which did
not detect any problems warranting other than routine
programmed maintenance.
Knowledge, skills
and experience
Normal
operations
knowledge and
skills
Infrastructure
construction and
maintenance
The welding returns recording the welding work on the line,
including a portion of track within 100m of the derailment,
were not filled out in the manner intended and were not
signed-off appropriately. As a consequence, it remains
impossible to determine whether or not the track was
correctly adjusted in the welding process.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 59
ARTC has an established maintenance and defects
management system to identify and manage the risks
associated with track defects and failures which rely on
accurate measurement and recording by maintenance
staff and sub-contractors. However, the accuracy of some
assessments is being affected through reliance on
inaccurate or incomplete information on inspection sheets
and unverified records of track maintenance undertaken
apparently without adequate supervision, monitoring or
auditing.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
Despite a specific recommendation made in a previous
OTSI Investigation Report, no specific standards or
instructions have been produced to cover the ongoing
inspection of ballast levels or compaction in steel sleeper
pods.
Procedures Absent
procedures
Infrastructure
construction and
maintenance
The use of the hi-rail (visual) inspections to detect track
abnormalities was largely ineffective as it was not expected
that the high speed “heat patrol” would detect the deficient
track conditions that led to the eventual misalignment. The
emptiness of the steel sleeper pods and the lack of
evidence of proper adjustment should have been detected
by earlier walking inspections but were not.
Task demands Time pressure Infrastructure
construction and
maintenance
The extent of trackwork in the vicinity of the derailment
location (and level crossing) and the length of time it might
have affected the line could have been well in excess of
what is catered for in the WTSA. It may be prudent,
therefore, to give such a combination of circumstances
special consideration in the WTSA process.
Procedures Accuracy/
clarity
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 60
19. Euabalong West – Derailment – 14 January 2007
At 2:53pm a Pacific National Super-Freighter service 6BA6 derailed at high speed in the
Euabalong West – Matakana section.
6BA6 consisted of two NR class locomotives and 26
container wagons conveying 63 containers and was en
route from Brisbane to Adelaide when it derailed
approximately 4kms West of Euabalong West, in
Central Western NSW. The 15th and subsequent
wagons derailed resulting in substantial damage to the
track, wagons and their cargo. Fortunately, the crew
were not injured and there were no other persons involved in the derailment.
A hazardous materials (Hazmat) team from the NSW Fire Brigade responded to the site
because hazardous materials spilled from several containers following the derailment.
The investigation found that instability and misalignment
of the track structure at 623.452kms caused the 15th and
subsequent wagons of 6BA6 to derail. The instability of
the track was attributable to a lack of structural rigidity
resulting from non-conformance with ARTC Engineering
Standards. There was no evidence to indicate that the
way in which 6BA6 was marshalled, loaded or handled contributed to its derailment.
ARTC had technical standards which, if applied correctly, should have identified a variety of
track-related defects and their potential impact. However, because the related inspection,
maintenance and documentation requirements were not undertaken effectively, those
responsible for analysing the condition of the track and determining maintenance priorities
worked with information that was erroneous in some instances and incomplete in others. As
a consequence, they did not comprehend the extent to which the track in the area in which
the derailment occurred had become compromised.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 61
Occurrence details
Event description: A freight train derailed due to track instability.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure mechanism Failure origin
Instability and misalignment of the track structure at
623.452kms caused the 15th and subsequent wagons of
6BA6 to derail.
Infrastructure - Track Deformation Maintenance
The instability of the track was attributable to a lack of
structural rigidity resulting from non-conformance with
ARTC Engineering Standards as evidenced by the
following:
a. poor condition of timber sleepers,
b. ineffective timber sleeper fastenings,
c. poor rail anchorages,
d. inconsistent ballast depth and compaction,
e. non-conforming placement pattern of the steel sleepers,
f. minor additions of rail in the welding processes.
Infrastructure - Track Deformation Maintenance
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
Despite predicted high air temperatures on the day, no
additional track patrols, as required by ARTC Standard
TMP 17, were scheduled.
Organisational
management
Monitoring, review
& validation
Infrastructure
construction and
maintenance
Although ARTC has established standards, track
maintenance records indicated the following:
a. that track maintenance staff were entering little or
incomplete information on inspection sheets despite its
maintenance system being reliant on such information to
accurately monitor the state of the track;
b. accuracy was not maintained during rail welding
processes, and c. the WTSAs conducted in 2005 and 2006
were flawed due to the lack of accurate information
regarding the state of the track.
Personal factors Motivation/
attitude
Infrastructure
construction and
maintenance
Despite a specific recommendation being made in the
OTSI “Steel Sleeper Introduction on NSW Class 1 Mainline
Track” that “field inspection guidance be provided”, there
were no specific standards or instructions for the ongoing
inspection of ballast levels or compaction in steel sleeper
pods.
Procedures Absent procedures Infrastructure
construction and
maintenance
The ARTC internal audit and compliance program was
deficient as it did not include any audits which visually
inspected or sampled the condition of the main line in the
Orange to Broken Hill Corridor.
Organisational
management
Monitoring, review
& validation
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 62
20. Connemarra – Derailment – 8 February 2007
At approximately 3:00pm 16 wagons of Pacific National’s empty grain service 9529 derailed
in the rail section between Binnaway and Werris Creek at a locality known as Connemarra in
North Western NSW. The train parted during the derailment when four derailed wagons
concertinaed across the track. The other derailed wagons remained in a generally upright
position.
The train consisted of four locomotives and 47 empty
grain wagons, and was travelling from Nowra to Werris
Creek via Dubbo with the intention of then proceeding
to load grain at silos located between Gunnedah and
Moree. The incident resulted in damage to 845 metres
of track, and varying degrees of damage to 16 grain
wagons. Fortunately no-one was injured.
In its investigation of the incident, OTSI found that the train was being operated at a speed
permitted for its type and for the track speed limit in force at the time. The drivers were not
aware of any problems with the track, and there were no visible signs of
track misalignment as they approached the derailment point.
The drivers were sensitive to the effect of high temperatures on safe
operating speed and, due to the hot conditions, had enquired whether a
temporary speed restriction, known as a WOLO, had been implemented
for the sections they were to enter. As the temperature was
approximately 1°C below that at which a WOLO restriction would have been imposed, no
such restriction was in place. OTSI investigators found that the track had misaligned due to
stresses caused by the elevated temperature and the movement of the train, as the train
passed over an unstable section of curved track.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 63
Occurrence details
Event description: A freight train derailed due to track instability.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure Findings Failed component Failure
mechanism
Failure origin
The derailment occurred because the track on which the
train was operating misaligned beneath the train.
Infrastructure - Track Deformation Maintenance
Local Condition/Organisational factor Findings Local
Condition/Organisati
onal factor
Keywords Functional area
The condition of the track was such that it was unable to resist
the combination of thermal stresses due to the heat of the
day, and the dynamic loading due to the passage of the train.
Physical environment Temperature/
humidity
Infrastructure
construction and
maintenance
Had the track been in sound condition, it would have been
capable of maintaining its alignment as the train passed.
However, its ability to do so was compromised by poor
sleeper distribution and alignment, and ineffective rail
fastening.
Knowledge, skills
and experience
Normal
operations
knowledge and
skills
Infrastructure
construction and
maintenance
Although the track had been subject to all inspections required
by ARTC’s maintenance standards in the year prior to the
derailment and the specified maintenance and monitoring was
being performed, the track was found to have the following
faults: the distribution of timber and steel sleepers was
irregular, sleeper spacing was uneven with frequent examples
of skewed sleepers, many dog spikes were ineffective, there
were examples of out-of-place and missing anchors, and
there were a number of Category 3 rail twists and rails out of
level.
Knowledge, skills
and experience
Normal
operations
knowledge and
skills
Infrastructure
construction and
maintenance
Despite the fact that ARTC specifically states that the ability of
a train to operate at the posted speed over a track with
Category 3 exceedents depends on the condition of the , thus
transferring the decision on safe operating speed to the train
operator, the operator is not informed of the existence of
these faults.
Organisational
management
Communication
and consultation
process
Infrastructure
construction and
maintenance
Had the air temperature been one degree Celsius higher, a
WOLO would have been declared and the train would have
been limited to a speed of 50km/h rather than the posted
speed of 75km/h. It is inappropriate that no speed restriction
at all was deemed to be necessary.
Procedures Absent
procedures
Infrastructure
construction and
maintenance
On the evidence of this derailment and others that have
occurred under similar conditions, ARTC’s track inspection
and maintenance strategies are not fully effective in
preventing track misalignments and derailments during
periods of high temperature.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 64
21. Singleton – Track worker fatalities – 16 July 2007
At approximately 5:48am a signal electrician and his assistant were struck and fatally injured
by Pacific National’s coal service HV161 at No.56A points approximately 445m South of
Singleton railway station. The two rail maintenance workers had been called-out to attend to
the points which had malfunctioned earlier in the morning.
OTSI’s analysis of recorded conversations between the
Electrician and the Network Controller in charge of train
movements through Singleton, together with signal
records, revealed that the two rail maintenance
workers were working under a method of worksite
protection known as NAR (No Authority Required).
Under this arrangement, one of them was required to
keep a lookout for approaching trains at all times.
At 5:44:09am, the Driver of Pacific National’s South-bound coal service HV388 observed
two workers on an adjacent line near the No.56 points and sounded the horn to alert them to
his train’s presence. The Driver indicated that he was
slowing his train at the time, in anticipation of having to
stop at a signal ahead, and that one of the two workers
acknowledged HV388’s presence. At 5:46:22am, the
Driver of PN’s Northbound coal service HV161
extinguished his train’s headlight after seeing HV388
ahead, as he was obliged to do under ARTC’s Network
Rules. HV388 continued to slow but the signal indications ahead of HV161 were such that its
Driver was able to continue to operate his train at its maximum permitted speed of 80km/h
and at 5:47:22am the two trains commenced to pass each other. Approximately 39 seconds
later, and while the two trains were still in the process of passing each other, the Driver of
HV161 was confronted with what appeared to be two workers in the danger zone
immediately in front of his train. In what he described as being an instant later, HV161 struck
and fatally injured the two rail maintenance workers.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 65
Occurrence details
Event description: Two rail maintenance workers were struck by a freight train and killed.
Type of operation: Freight
Fatalities 2 Injuries: nil
Occurrence Classification Collision Running line collision
With a person not on a level crossing
Individual actions
Findings Person type Activity type Error/Violation type
The two rail maintenance workers were working under a
method of worksite protection known as NAR and this
required that one of them kept a lookout at all times. In the
instant before HV161 struck the two rail maintenance
workers, the Driver saw one of them crouching or kneeling
at the No.56A points while the other was standing with his
back towards the train and appeared to be pointing a torch
onto the track. Since neither of the workers was keeping a
lookout at this time, neither of them saw the approaching
HV161 and did not appreciate the need to move to a safe
place.
Infrastructure
maintainer
Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
The NAR method of worksite protection employed does
not oblige those who employ it to communicate their
intentions to others. In this instance, the Electrician did
advise the Network Controller of his intentions but the
Network Controller was not obliged to, and did not, inform
the Drivers of HV161 and HV388 that there were
maintenance workers on the track near Singleton station.
While the Driver of HV388 ultimately saw the two
maintenance workers, the Driver of HV161 had no
forewarning of their presence and by the time he saw
them, he did not have time to warn them of his train’s
presence.
Procedures Accuracy/
adequacy
Infrastructure
construction and
maintenance
Visual and audible cues that might have alerted the two
workers to HV161’s approach were diminished because
HV161 was operating with its headlight extinguished and
the noise generated by the passing of HV388 on an
adjacent line masked the sound of HV161’s approach.
Physical
environment
Lighting/visibility Infrastructure
construction and
maintenance Physical
environment
Noise
The two rail maintenance workers had worked within the
danger zone at night on many occasions and the
Electrician was very familiar with the location in which he
and his colleague were working. It is possible that these
high levels of familiarity lessened the workers’ appreciation
of the risks associated with their task.
Task demands Other- familiarity Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 66
The Electrician was rostered on-call to respond to events
in Whittingham-Muswellbrook-Dartbrook-Gulgong area on
the morning of 16 July 2007. However, the Electrician’s
Assistant was not on-call and would therefore not have
anticipated being called-out in the early hours of the
morning. In addition, both workers had worked seven shifts
over the preceding seven days. It is therefore probable that
both workers were suffering from a degree of fatigue and
that this may also have affected their appreciation of the
risks associated with their task.
Personal factors Fatigue/alertness Infrastructure
construction and
maintenance
ARTC Network Rule ANWT 300 (Planning Work in the Rail
Corridor) specifies that all work within the rail corridor must
be preceded by a safety assessment by a qualified
Protection Officer and that the protection arrangements
that are to be in force while the work is undertaken must be
recorded. Both of the rail maintenance workers were
qualified Protection Officers but it is clear from recorded
conversations that the Electrician was acting in this
capacity at the time of the accident. However, OTSI could
not find any record of the protection arrangements and
therefore had no way of determining whether the work was
preceded by a safety assessment.
Procedures Absent
procedures
Infrastructure
construction and
maintenance
ARTC’s Network Rule ANGE 204 (Network
Communications), and a related Network Procedure,
ANPR 721 (Spoken and Written Communication), requires
a structured approach to the transmission and receipt of
information and obliges those who are communicating to
reach a complete and shared understanding of those
matters under discussion. The Network Controller and the
Electrician conversed on three occasions during the
morning of 16 July 2007 but their communication did not
conform to ARTC’s requirements. While their manner of
communication did not contribute directly to the
circumstances that led to the accident, had the Electrician
and the Network Controller observed the required
communication protocols and communicated in a more
structured way, aspects such as the proximity of HV161
and HV388 and the instructions to clear signals would
have to have been repeated by the Electrician and
Network Controller respectively and greater significance
might have been attached to both of these elements of
safety critical information.
Knowledge,
skills and
experience
Communication
skills
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 67
22. Breeza – Derailment – 8 January 2008
At approximately 4:33pm Pacific National Limited coal service BO552 derailed in the vicinity
of Breeza approximately 16km North West of Werris Creek in NSW. BO552 consisted of two
locomotives and 42 loaded coal wagons. The train was a regular coal service which had
been loaded earlier that day at Boggabri and was en route to Port Waratah. The train crew
reported that 19 wagons had derailed, commencing at the 10th wagon in the consist and
leaving the remaining 14 on the track. The crew were uninjured and able to inform and
update response teams of the situation.
The derailment coincided with a number of track
misalignments which were occurring around the same
time in other sections of the line. Just minutes prior to
the derailment the driver of a passenger train reported
the effects of several minor misalignments some 25km
and 36km along the track to the North West. The
derailment of BO552 was determined to be a
consequence of a misalignment caused by the effect of hot weather on a poorly maintained
section of track. The weather conditions on the day were described by the crew as very hot,
with the nearest monitoring stations at Tamworth and Gunnedah recording temperatures of
between 36°C and 37°C.
A partial re-sleepering program was completed in the previous September but a number of
anchors were not refitted to timber sleepers. A rail adjustment was completed five and a half
weeks prior to the derailment in response to an analysis
which showed considerable stability loss in the vicinity
through creep. The extent of the compensating
adjustment appears to have been much less than
indicated as necessary by creep measurements. Thus,
the heat related stresses on the day of the derailment
were in addition to residual stresses, due to insufficient
rail adjustment, which were inadequately restrained due to ineffective track stability.
In late 2008, the entire track between Gunnedah and Werris Creek was re-sleepered with
concrete sleepers, which upon follow-up inspection in January 2009 appeared to have
remedied the problems which were present in the section at the time of the derailment.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 68
Occurrence details
Event description: A freight train derailed due to track instability.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The derailment was caused by a misalignment in the track
as it was traversed by the train. The misalignment was due
to the inability of the track infrastructure to constrain the
compressive stresses in the rails resulting from long term
uncontrolled rail creep.
Infrastructure - Track Deformation Maintenance
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
The rail was not adequately constrained against the
forces on it due to ineffective anchoring. Replacement of
anchors following track work several months prior to the
derailment was not completed.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
Rail adjustment to address identified excessive rail
creep carried out five and a half weeks prior was
unsatisfactory in that less than a third of the excess steel
determined by measurement as part of a WTSA was
removed from a point within 80m of the site of the
derailment.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
The additional compressive stresses on the rails due to
hot conditions could not be constrained due to the
inadequacy of the anchoring of the track.
Equipment, plant and
infrastructure
Functionality Infrastructure
construction and
maintenance
Network Control was alerted to track buckles in the
vicinity by an earlier passenger service and, although it
was only minutes prior to the derailment, there is no
evidence that a warning had been or was about to be
broadcast to other rail traffic.
Knowledge, skills
and experience
Communication
skills
Infrastructure
construction and
maintenance
The maintenance regime in place for the detection and
rectification of substandard track conditions allowed for
the poor condition of the track to exist despite regular
inspections.
Organisational
management
Monitoring,
review &
validation
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 69
23. Homebush – SPAD and Derailment – 7 January 2009
At 4:43pm at Homebush, a CityRail eight-car Tangara passenger service passed Signal
ST265L at stop without authority (SPAD) and derailed on the catch-points. No injuries
resulted directly from the derailment or subsequent detrainment of passengers. A minor
injury was reported by a young man using crutches who sustained a suspected sprained
wrist while climbing the stairs to exit the platform adjacent to the derailed train.
The CityRail train, designated as 37-K, consisted of an
eight-car Tangara Electric Multiple Unit train and was
carrying an unknown number of passengers. It was
proceeding Westbound at Homebush Station where it
was scheduled to stop. As the Driver was travelling
alongside Homebush Platform he misinterpreted which
signal applied to his line and accelerated with the
intention of proceeding through to the next station.
As the train passed the end of the platform its brakes were activated by the train stop. To
prevent the train from continuing onto the adjacent line and potentially colliding with another
train, a set of catch-points were positioned to derail the
train into a safe area. As a result of the catch-points
performing their intended function, the leading car of 37-K
derailed all wheels and the leading bogie of the second
car also derailed, while the remaining six cars remained
on the track. 37-K came to a stand 41 metres past the
catch-points with the leading three cars and part of the fourth car beyond the platform and
the remaining four cars adjacent to the platform.
The investigation found that the SPAD and subsequent derailment was a consequence of an
error by the Driver who misinterpreted which signal applied to his line. The Driver was
relatively inexperienced and it is probable that his driving and situational awareness were
adversely affected by fatigue brought on by insufficient quality rest and sleep. It was also
found that the position of the two signals, ST265L and S261S, increased the probability of a
driver misinterpreting which signal applied to the line.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 70
Occurrence details
Event description: A passenger train passed a signal at stop and derailed on the catch-points.
Type of operation: Passenger
Fatalities nil Injuries: 1
Occurrence Classification Derailment On running line
Individual actions
Findings Person type Activity type Error/Violation
type
The derailment was the result of the standard operation
of catch-points in response to Signal ST265L being
passed at danger by service 37-K. The driver of 37-K
responded in error to Signal ST261S on an adjacent line
which displayed a proceed indication instead of Signal
ST265L which governed his line and was at stop.
Train Crew Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional
area
The Driver was relatively inexperienced which may have
led to a misinterpretation of which signal applied to his
track.
Knowledge, skills
and experience
Task experience On-train
operations
It is likely that the Driver was not sufficiently rested to
enable him to effectively perform his duties.
Personal factors Fatigue/alertness On-train
operations
Signal ST265L is sited in a manner and location that
meets the required technical parameters. Yet the
position of the two signals, ST265L and ST261S,
increased the probability of a driver misinterpreting
which signal applied to which line.
Equipment, plant and
infrastructure
Infrastructure
design
Infrastructure
construction
and
maintenance
The train stop and catch-points associated with Signal
ST 265L operated correctly but their location in the track
layout still resulted in the derailed 37-K stopping foul of
the Down Suburban line.
Equipment, plant and
infrastructure
Infrastructure
design
Infrastructure
construction
and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 71
24. Unanderra – SPAD and Derailment – 24 January 2009
At approximately 2:35am CityRail four-car Tangara passenger service K496 departed from
Unanderra Station towards Signal WG1010 which was at stop. A loud noise from a
passenger disturbance in the vestibule behind the Driver momentarily distracted him and, as
a result, he allowed the train to pass Signal WG1010 at stop without authority (SPAD).
The train then encountered the two safety defences
associated with Signal WG 1010. The first, a train stop,
automatically triggered the application of the train’s
emergency brakes as it passed the signal thus
reducing its speed and so mitigating the consequences
of the SPAD. The second defence, catch-points,
derailed the train into a safe area away from the
adjacent line and so a potential collision with an opposing freight service, which was
approaching on the Down Illawarra line, was prevented. The leading two cars of K496
derailed all wheels and the leading bogie of the third car also derailed, while the remaining
car remained on the track.
No injuries were sustained by the crew or passengers. The damage caused by the
derailment was limited to the bogies and bodywork of the two front passenger cars and to
the infrastructure associated with the catch-points.
The investigation found that the SPAD and
subsequent derailment was a consequence of the
Driver’s inattentiveness resulting in his not responding
to the stop signal which applied to his line. The
Driver’s error can be attributed to one or, most likely,
a combination of the following: the distraction of the passenger disturbance behind him, a
loss of situational awareness due to fatigue brought on by insufficient quality rest and sleep,
and the Guard not working from his assigned position. This was the fifth recorded SPAD at
Unanderra since 2003. A SPAD in 2003 was investigated by OTSI resulting in a
recommendation that a human factors review be undertaken in relation to signals and the
predictive information they convey. The recommendation was subsequently not
implemented.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 72
Occurrence details
Event description: A passenger train passed a signal at stop and derailed on the catch-points.
Type of operation: Passenger
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Individual actions
Findings Person type Activity type Error/Violation
type
Service K496 passed Signal WG1010 when it was
showing a stop indication (SPAD). It then derailed on the
catch-points which were set open in accordance with the
Signal’s stop indication. The SPAD of Signal WG1010 was
the consequence of human error on the part of the train
Driver.
Train Crew Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional
area
Contrary to procedural requirements, but on the grounds of
feeling stressed and unwell, the Guard was riding in the
driver’s cab with the Driver’s approval. This meant that he
took his cue to proceed from Signal WG1016, the next
signal in advance from the platform, instead of the Guard’s
Indicator which was linked to Signal WG1010.
Personal factors Stress/anxiety On-train
operations
Although the Driver of K496 was qualified for the route, it
was likely that he was subconsciously expecting the route
beyond the Unanderra platform to be set for the train to
continue past Signal WG1010 as it had been in his
experience on all previous occasions. He departed the
platform on the Guard’s bell indication, passed Signal
WG1016, but then did not respond to Signal WG1010,
which was at stop, until the associated train stop had
triggered the application of the train’s emergency brakes.
Personal factors Preoccupation On-train
operations
Signal WG1010 may also have been obscured for part of
the time due to the position of the driver’s blind and
trackside infrastructure.
Equipment, plant
and infrastructure
Infrastructure
design
On-train
operations
It is likely that fatigue played a part in the Driver losing
concentration and situational awareness. He was not
sufficiently rested to enable him to effectively perform his
duties due to a lack of quality sleep, lingering effects of the
flu and sub-optimal sleep environment because of hot
weather.
Personal factors Fatigue/alertness On-train
operations
Immediately prior to the derailment he had allowed himself
to be distracted by a noisy passenger disturbance behind
his cab. The Guard was likewise distracted.
Task demands Distractions On-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 73
Neither the Guard nor Driver are recorded as having
received formal instruction related to self-assessing fitness
for work in their induction training but they would have at
least undergone awareness sessions subsequently.
However, the current RailCorp training information and
Fatigue Management Policy contain little detail on how to
optimise the sleep environment or how to objectively
assess one’s own fitness for duty.
Training and
assessment
Ongoing training On-train
operations
This is the fifth recorded SPAD at Unanderra since 2003.
The 2003 SPAD was investigated by OTSI resulting in a
recommendation that a human factors review be
undertaken in relation to signals and the predictive
information they convey. The recommendation was
subsequently not implemented. In February 2009, in
response to the incident subject of this investigation, a
“Human Factors SPAD Hazard Checklist” was used to
conduct a sighting test for Signal WG1010 which revealed
five infrastructure issues that could have an impact on
driver performance.
Organisational
management
Risk/change
management
On-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 74
25. Peak Hill – Derailment – 8 February 2009
At approximately 5:23pm El Zorro grain service 8996 derailed nine grain wagons
approximately 7km North of Peak Hill in the Western region of NSW. The train consisted of
four locomotives and 38 loaded grain wagons. The train was en route from Nyngan to Port
Kembla at the time of the derailment. There were no injuries to the crew but there was
extensive damage to 370m of track infrastructure and the nine wagons.
The investigation determined that the derailment was
caused by the train travelling at excessive speed. At
the point of derailment, the train was travelling at
63km/h through an area on which a 40km/h speed limit
had been imposed. The speed restriction had been
imposed due to the condition of the track and had been
appropriately promulgated. However, the relevant
documentation applicable to the locations of all speed restrictions had been left in the last
trailing locomotive of the consist following a prior run-around movement at Narromine.
Initially the Driver had slowed to 23km/h for the speed restriction, but then prematurely
accelerated believing he had cleared the restricted section and that the clearance sign,
which would signify the end of the restriction, was
missing. The Driver allowed the train to exceed the
speed restriction for some 8.5km up to the point of
derailment. The speedometer on the locomotive was
not working and the driver had been relying on his
experience to judge the speed of the train. The Co-
Driver was not in a position to undertake his normal
duties to assist the Driver as he had been indisposed due to illness throughout the journey.
There was a slight misalignment near the derailment site. But, more significantly, the train
had just traversed a small wooden underbridge where the train was felt to sway to one side.
This was found to be due to gaps between the bridge girders and their supports.
At the time of the derailment, a program of upgrading the section of track was underway
involving re-sleepering and ballast renewal. This program had been in progress at various
locations in the area where the derailment occurred for the past two years. Nevertheless,
there was an inherent weakness in the structural integrity and rigidity of the track where the
derailment occurred.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 75
Occurrence details
Event description: A freight train derailed due to track instability.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The track could not constrain the forces on it at the point of
derailment as it was in a less than optimum condition.
Infrastructure -
Track
Deformation Maintenance
Individual actions Findings Person type Activity type Error/Violation
type
The derailment of nine wagons of grain service 8996 at
Kilometrage 505.400 was caused by excessive speed in
that the train was travelling at 23km/h above the speed
assessed as safe for the condition of the track in that
section.
Train Crew Operating
equipment
Error
The overloading of wagons by up to 9.15% placed
additional stress on the track.
Terminal staff Monitoring and
checking
Unknown
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
Although correctly promulgated and signposted speed
restrictions were in place, the driver increased speed some
13km before the end of a speed limited section, believing
the Clearance Sign to be missing.
Personal factors Motivation/
attitude
On-train
operations
On departing Narromine, the driver relied on his
experience to estimate the speed of the train because the
speedometer of locomotive EL54 was not working.
Continuing to operate the train without the benefit of a
speedometer was contrary to Network Rule ANTR 410
which required him to re-marshal at the “first suitable
location” of which there were three between Narromine
and the derailment site.
Equipment, plant
and infrastructure
Functionality On-train
operations
The driver did not utilise the digital speedometer in the
diagnostic information display panel at the rear of the cabin
to check the train’s speed.
Personal factors Motivation/
attitude
On-train
operations
During the “run-around” manoeuvre at Narromine, the
speed restriction notice applicable at the time, and issued
to the train, was not transferred to EL54 by the co-driver
when the lead locomotives changed over.
Knowledge, skills
and experience
Teamwork skills On-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 76
The co-driver was incapacitated through illness and unable
to perform his duties in relation to maintaining a lookout
and relaying trackside infrastructure information to the
driver.
Personal factors Health-related
condition
On-train
operations
The track could not constrain the forces due to: deflection
in a wooden underbridge which allowed excessive vertical
movement causing the train to sway when passing over it;
a slight misalignment at the point of derailment;
weaknesses in the track anchorage because of loose
fastenings; poor ballast condition, and inadequate tamping
associated with an incomplete steel sleeper replacement
program.
Organisational
management
Contractor/
interface
management
Infrastructure
construction and
maintenance
To a lesser extent the effects of very hot weather over a
protracted period placed additional stress on the track.
Physical
environment
Temperature/
Humidity
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 77
26. Goobang – SPAD and collision – 10 May 2009
On the morning of Sunday 10 May 2009, Track Australia was transferring two track
machines from Dubbo to Cootamundra via Parkes on behalf of the Australian Rail Track
Corporation (ARTC). The machines were operating in convoy with a ballast regulator leading
and a tamping machine following. Both track machines were crewed by personnel from
Track Australia and the convoy was running as train number 8M71.
At approximately 10:00am the ballast regulator closed
on signal GJ144 on the approach to Goobang Junction
near Parkes. Signal GJ144 was displaying a stop
indication. While trying to stop his machine at the
signal, the ballast regulator operator checked through
the rear window of the machine and assessed that the
trailing tamping machine was not going to stop in time
to avoid a collision. He then made the decision to speed up and pass the signal at stop
(SPAD). However, the tamping machine collided with the ballast regulator approximately
20m prior to the signal. The tamping machine stopped short of the signal but the ballast
regulator came to a stand approximately 60m beyond the signal. No crew members were
injured and both machines suffered only superficial damage.
The investigation revealed that the collective knowledge and experience of the crew
members on the route being travelled was confined to that gained travelling in the opposite
direction as passengers on the machines a week earlier.
This lack of route knowledge was determined to be a
major contributing factor to the incident. The ballast
regulator operator was relying on location signs as his
primary navigational aid. Despite being qualified in signal
recognition, he did not respond to a landmark sign 869m
prior to the signal, and did not react to the signal until he was approximately 40m from it
although its presence was clearly visible for well in excess of that distance
Since there were no voice recorders on the track machines, there remains uncertainty as to
why a radio warning about signal GJ144, claimed to have been sent by the ballast regulator
operator, was not received by the tamping machine crew.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 78
Occurrence details
Event description: Two track machines collided with each other.
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Collision Running line collision
Between trains
Individual actions
Findings Person type Activity type Error/Violation
type
The operator of the lead track machine of 8M71 made a
conscious decision to pass signal GJ144 when it was at
stop. He did so in the belief that this would serve to avoid a
rear-end collision involving his ballast regulator and the
following tamping machine. However, the separation
between the machines was not sufficient to avoid a minor
collision as the ballast regulator accelerated away.
Train Crew Operating
equipment
Error
Local Condition/Organisational factor
Findings Local
Condition/Organisation
al factor
Keywords Functional area
The route knowledge of the crew members was limited to
travelling the route in the opposite direction as passengers
on the machines a week earlier. Not having a pilot driver or
being in possession of any documentation that would
assist their navigation, they relied on location signs. The
crews did not respond to a landmark sign well in advance
of the signal though it should have triggered the same
response as a location sign.
Knowledge, skills
and experience
Task experience On-train
operations
The ballast regulator operator’s signal recognition skills
were inadequate for the task on which he was required to
exercise them.
Knowledge, skills
and experience
Normal
operations
knowledge and
skills
On-train
operations
The PO was distracted at the time of passing the landmark
sign, the significance of which he would have been
expected to recognise.
Task demands Distractions On-train
operations
The Pre-Work Brief form which recorded the hazards and
safety controls, did not address any specific risks
associated with travelling in convoy or through relatively
unknown territory.
Procedures Accuracy/clarity On-train
operations
The tamping machine crew denied receiving a warning via
radio claimed to have been sent by the ballast regulator
operator when he realised he was about to SPAD. It is also
noted that non-discreet UHF radio channels were relied
upon for communications between machines despite GRN
radios being available.
Equipment, plant
and infrastructure
Functionality On-train
operations
The separation between the machines was less than that
required to be safe at the speed at which the tamping
machine was travelling.
Knowledge, skills
and experience
Normal
operations
knowledge and
skills
On-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 79
27. Temora – Runaway wagon – 28 July 2009
At approximately 3:05am empty grain wagon CQGY 540S, owned by Chicago Freight Car
Leasing Australia (CFCLA) and leased by El Zorro Transport (EZT), ran away from the
Temora Wheat Sub-Terminal during a shunting operation to detach it from a train. The
wagon was being detached for stowage and subsequent transfer to Junee for scheduled
maintenance requirements and because of defects identified during a previous safety
inspection.
The wagon ran for a total of 7.8 kilometres before
coming to a stand near the locality of Sproules Lagoon.
During this time, it demolished a temporary buffer stop,
struck an uncommissioned derailer and damaged a set
of points, all of which were associated with an
Australian Rail Track Corporation (ARTC) track
infrastructure rationalisation program. The wagon
traversed seven level crossings on the main line recording an average speed of 44.5km/h
between the active level crossings at Junee Road and Victoria Street in Temora.
Fortunately, there were no persons injured or vehicles struck during the runaway.
The investigation found that, while the crew followed correct procedure when detaching the
wagon, it ran away because the handbrake was not fully applied due to the brake chain
becoming jammed behind the guide bracket of the gear
assembly. The chain jammed because of the ineffective design
of the guide bracket installed to cater for the horizontal mounting
of the AAR IP93-type geared handbrake wheel assembly.
Despite the damage from chains jamming being regularly
repaired by maintainers, the problem was not communicated to
the wagon owner or operators. There was also excessive travel
within the handbrake system attributable to lack of adjustment during maintenance.
The only defence in place against a runaway on to the main line was a temporary buffer stop
which proved to be insufficiently robust to stop the wagon. It was constructed using a light
duty standard in the absence of any available heavy duty standard that would have been
appropriate to the situation at Temora.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 80
Occurrence details
Event description: Freight wagon runaway.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Runaway
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The wagon ran away because the handbrake was not fully
applied due to the chain becoming jammed behind the
guide bracket of the gear assembly.
Rolling stock – Braking
system
Mechanical
discontinuity
Design
Local Condition/Organisational factor
Findings Local
Condition/Organisation
al factor
Keywords Functional
area
The poor design of the guide bracket installed to cater for
the horizontal mounting of the AAR IP93-type geared
handbrake wheel assembly permitted the chain to become
jammed in the gear drive mechanism. This meant the
handbrake was not fully applied when the wagon was
detached even though it appeared to be.
Equipment, plant and
infrastructure
Functionality Off-train
operations
There was excessive travel within the handbrake system
caused by the lack of adjustment during maintenance.
Knowledge, skills and
experience
Normal
operations
knowledge and
skills
Off-train
operations
The temporary buffer stop fitted at 486.950kms was
insufficiently robust to stop the runaway wagon. The buffer
stop was installed using ARTC’s Engineering Standard
TDS 16 even though this is only meant to serve “light duty”
applications. Additionally, the clamping arrangement used
was not in accordance with TDS 16, thereby further
weakening the structure.
Equipment, plant and
infrastructure
Functionality Infrastructure
construction
and
maintenance
No additional defences, such as a portable derailer, were
placed on the line to mitigate against runaway rail vehicles
and protect the integrity of the network once the No. 1
Siding was connected to the main line.
Equipment, plant and
infrastructure
Absent
equipment,
plant and
infrastructure
Infrastructure
construction
and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 81
28. Glenlee – Safeworking breach – 28 October 2009
At 1:44pm Pacific National (PN) freight train 3BM4 almost struck the Co-driver of another PN
freight train, 2XW4, who was returning to his locomotive after conducting an axle bearing
inspection. The Co-driver believed there would be no trains running on the adjacent ‘Down
Main’ line after communicating with a Network Controller at the Network Control Centre
South at Junee (NCCS).
The Network Controller had earlier made a request to
the Co-driver of 2XW4 that the train be stopped so an
inspection could be carried out on one of the train’s
axle bearings in response to a hot box detector alert
received at NCCS. From the brief communication with
the Network Controller, the Co-driver thought that both
the Up Main line and the Down Main line had blocking
facilities applied. However, he did not confirm that the Down Main line was safe to access
before conducting the on-track inspection as required under Network Rules.
Having found nothing wrong from the inspection, the Co-driver was returning to his
locomotive along the ‘Down Main’ line when he received a radio call from the Driver warning
of an approaching train. At the same time, the Co-driver
sensed the approaching train from “humming” on the track
and moved quickly to a safe place between the ‘Up Main’
and ‘Down Main’ line.
The incident occurred at the operational interface between Australian Rail Track Corporation
(ARTC) and RailCorp territory. At the location 2XW4 came to a stand, the signals to the rear
on the Up Main line are controlled by ARTC and the signals on the adjacent Down Main line
are operated by RailCorp under ARTC’s control. The Network Controller was a trainee
undertaking on-job training. This was the first occasion on which he had had to request a
train driver stop and undertake an axle bearing inspection in response to a hot box detector
alert. Procedures to deal with hot box detector alerts were not covered in his off-job training
and, at the critical time, his supervising Network Controller was distracted by a personal
telephone call. Additionally, there were no specific procedures for the application of blocking
facilities at operational interfaces.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 82
Occurrence details
Event description: Safeworking breach lead to near miss of a person conducting a track inspection.
Type of operation: Off-train operations
Fatalities nil Injuries: nil
Occurrence Classification Safeworking breach Other procedure/rule breach
Individual actions
Findings Person type Activity type Error/Violation
type
The reason 3BM4 entered the section and almost struck the
Co-driver of 2XW4 was that no blocking facility was
requested to be placed on the Down Main line to prevent a
train from entering into that section.
Train Crew Communicating Error
Network
controller
Communicating Error
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
Contrary to Network Rules, the Co-driver of 2XW4 did not
confirm that the Down Main line was safe to access, either
by calling the Campbelltown Signal Box or confirming the
protection arrangements with the Network Controller at
Junee before he exited the train. The Co-driver made the
assumption that the protection arrangements put in place
provided protection from traffic in both directions.
Knowledge, skills
and experience
Task experience Off-train
operations
The Network Controller was a trainee undertaking on-job
training under supervision. This was the first occasion on
which he had had to request a train driver to stop and
undertake an axle bearing inspection in response to a hot
box detector alert.
Procedures to deal with hot box detector alerts were not
covered in his off-job training. Additionally, he was not
familiar with the area around the operational interface.
Knowledge, skills
and experience
Task experience Off-train
operations
Training and
assessment
Initial training Off-train
operations
The supervising Network Controller was distracted by an
incoming personal telephone call at this operationally critical
time so, in effect, the trainee was acting unsupervised.
Task demands Distractions Off-train
operations
The communication between the Network Controller and the
Co-driver was poor. It was brief and lacking detail, in
particular, there was no feedback or clarification about the
protection arrangements which needed to be applied to the
‘Down Main’ line if the axle bearing inspection was to take
place.
Knowledge, skills
and experience
Communications
skills
Off-train
operations
The workload of both the trainee and supervising Network
Controllers was high prior to and at the time of the incident.
They had worked continuously since beginning their shift at
7:00am and had received a high number of calls mainly
associated with train delay problems throughout the
morning. Neither had any scheduled rest or meal breaks
during the shift and there were no allocated personnel in the
Control Centre to act as reliefs for meal breaks or in the
case of a need to take unscheduled breaks.
Task demands High workload Off-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 83
29. Darling Park – Monorail collision – 27 February 2010
At about 4:00pm a Veolia Transport Sydney Metro monorail (Monorail 1) carrying 15
passengers collided with the rear of a stationary monorail (Monorail 4) at Darling Park
Station, Darling Harbour, Sydney. Monorail 4 had 45 passengers on board and was
experiencing door problems which caused it to stand at the Darling Park Station for longer
than normal. It had just completed loading passengers and the doors on five carriages were
still in the open position when it was hit from behind by Monorail 1 which at the time of
impact was estimated to be travelling at 6m/s (22km/h). Four passengers from Monorail 1
sustained minor injuries and three were transported to hospital for treatment. No one on
Monorail 4 was injured.
Each monorail was fitted with an Anti-Collision
Emergency Stop (ACES) system which was interfaced
to the main Programmable Logic Controller (PLC). This
control system acted as a backup when the monorail
was being operated in manual mode. An alarm was
activated inside the driver’s cab when it detected
another monorail 150m ahead and a different alarm
and the emergency brakes were activated when the separation closed to 100m. On this
occasion the alarms and emergency brakes activated correctly but did not stop the monorail
before it struck the stationary monorail in Darling Park Station.
The investigation established that Monorail 1 was travelling above the speed profile as it
approached the station and that the Driver did not react quickly enough to brake the
monorail when the first of two alarms sounded, warning
him of the presence of another monorail 150m ahead.
The Driver had about five seconds after the first alarm
sounded during which time he should have applied the
brakes before the emergency brakes activated. In this five
second interval, the Driver received a two-way radio call
from Train Control warning him of the stationary monorail ahead. It is likely that this call
distracted him sufficiently to degrade his braking reaction time. The speed profile for the
section of track where the alarm activated was 8.5m/s and testing showed that the most
likely scenario was that Monorail 1 was travelling at around 9.5m/s in that section.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 84
Occurrence details
Event description: Collision by one monorail train into the rear of a stationary monorail train
Type of operation: On-train operations
Fatalities nil Injuries: 4
Occurrence Classification Collision Running line
Between trains
Individual actions
Findings Person type Activity type Error/Violation
type
The investigation established that Monorail 1 was travelling
above the speed profile at the time of the collision and that
the Driver did not react quickly enough to brake the
monorail when the first of two alarms sounded, warning
him of the presence of another monorail 150m ahead.
Train Crew
Monitoring and
Checking
Error
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The Anti-Collision Emergency Stop (ACES) system on
Monorail 1 should have prevented the collision but it did
not do so. While the ACES system activated the
emergency brakes, they did not stop the monorail before it
entered Darling Park Station because the design of the
braking system and the ACES distance settings made no
allowance for monorails being driven above the speed
profile of 8.5m/s.
Rolling stock-
Train Detection
System
Software/
firmware
anomaly
Design
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
The Driver of Monorail 1 was likely to have been distracted
at a critical time on approach to Darling Park Station by
one or more events, including a conversation with the
Relief Driver at the time the first proximity alarm activated,
and by a radio call from the Controller before the second
proximity alarm.
Task demands Distractions On-train
operations
The view to Darling Park Station was obscured by tree
foliage which prevented the driver from having a clear view
to the station entrance, and the stationary Monorail 4
therein, until he was 40m from it.
Physical
environment
Lighting/
visibility
On-train
operations
The design of the braking system and the ACES distance
settings made no allowance for monorails being driven
above the speed profile of 8.5m/s.
Equipment, plant
and infrastructure
Functionality On-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 85
30. Whittingham – Derailment – 13 March 2010
At approximately 9:48am Pacific National empty grain service 2531, travelling from Berrima
Junction to Werris Creek, derailed as it traversed No.203 points at Whittingham, near
Singleton in the Hunter Valley Region of NSW. At the time, an altered method of
Safeworking was being used to control train movements through Whittingham because of
civil and signal renewal works associated with the Maitland to Whittingham Third Track
Project. This method, CAN Block Working, required the points at Whittingham to be operated
manually.
The events leading to the derailment commenced at
8:10am when a team, consisting of a daywork
supervisor and two qualified workers, was directed by
Network Control to manually set 203 points in the
normal position for a proposed main line train
movement. The turnout was made up of three
elements: facing points, a swingnose and a catch point.
When setting 203 points, the qualified workers did not start from the furthermost end as
required by ARTC Network Procedure ANPR 743 Manually Operating Handthrow Electric
Points. This resulted in the swingnose being left set in the reverse position. Further, despite
it being a requirement in the procedure, the qualified workers did not check the route after
setting the points despite having sufficient time to do so. Consequently, service 2531 struck
the swingnose which had been left set in the wrong position and derailed. It was travelling at
55km/h at the time.
Both locomotives and the eight leading wagons were severely damaged, as well as 110
metres of track including 203 points and various items of signalling equipment.
Approximately 6,000 litres of diesel fuel was also spilt.
The driver received a bruised shoulder and was
transported to Singleton Base Hospital. The assistant
driver attended hospital later as a precautionary measure.
The investigation found that the derailment was the result
of a lack of process and validation by the qualified
workers when setting and clipping the points.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 86
Occurrence details
Event description: A freight train derailed when a set of points were incorrectly set.
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Individual actions
Findings Person type Activity type Error/Violation
type
The derailment of 2531 was a consequence of 203B
swingnose being left set in the reverse position when 203
points were set and clipped for the passage of the train.
This resulted in the wheels on the down rail of the Down
Main line being directed towards the inner (gauge) side of
the up rail of the Up Branch line and off the rail head.
Infrastructure
maintainer
Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
Despite sufficient time being available, neither the qualified
workers nor the Supervisor ensured the route was
correctly set for 2531 after the points were set and clipped,
and before giving an assurance to Network Control to that
effect, in accordance with Network Procedure ANPR 743.
People management Supervision Infrastructure ,
construction and
maintenance
Despite being in possession of competency certification for
Engineering Hand Signallers Level 2, evidence suggests
the qualified workers were not adequately assessed, if at
all, in the competency of manually operating handthrown
electric points before being recertified.
Training and
assessment
Competency
assessment
Infrastructure ,
construction and
maintenance
The risk assessment conducted for the Singleton
Extension Yard Limits and CAN Block Working was
detailed and well documented. However, the controls for
which the Hunter 8 Alliance was responsible were not fully
implemented by its Rail Safety Manager or recorded on the
Worksite Protection Plan and Pre-work Briefing forms by
the Protection Officer. As a result, the supervisors were not
fully informed about the controls that had been determined
as applicable to the assessed risks at their Whittingham
site.
Organisational
management
Information
management
Infrastructure ,
construction and
maintenance
There were no formal or effective contractual
arrangements entered into covering the workers engaged
by the Hunter 8 Alliance to implement the CAN Block
Working, other than a verbal agreement to honour fee for
service invoices.
Organisational
management
Contractor/
interface
management
Infrastructure ,
construction and
maintenance
No adequate verification was made of the competencies or
the currency of the qualifications of engaged workers prior
to their commencing work.
Training and
assessment
Currency
tracking
Infrastructure ,
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 87
31. Strathfield – Near strike of maintenance staff – 1 April 2010
Shortly after 5:00am the Driver of N804 CityRail Gosford to Sydney Terminal interurban
service reported to the Area Controller at Strathfield Signal Control Centre that his train had
nearly struck four members of a signal maintenance team working at 538A points on
approach to Platform 1 at Strathfield Station. The Team had been called by the Area
Controller to attend 538A points which had failed.
The Team arrived at the site shortly after 4:50am
where the Protection Officer determined they could
inspect the points using Network Rule NWT 310 No
Authority Required (NAR) as the method of worksite
protection. Although NAR requires at least one
member of the Team to maintain a lookout to warn of
approaching rail traffic, no member of the Team was
formally nominated as the lookout. The task was assumed by a member of the Team who
became the least involved in the maintenance work at the points. NAR does not require any
warning be given to train crews of the presence of rail safety workers on or near the track.
As N804 approached 538A points, the Driver saw the four workers standing in the middle of
the track with their backs to the train. He immediately applied the emergency brake and
sounded the horn. At this point, the train was within 50m
of the points and had decelerated to 39km/h. In response
to the horn blast, the workers moved very quickly in a
disorganised fashion to clear off the track. Expecting it
was likely the train would strike one or more of the
workers, the Driver ducked underneath the dashboard
and waited for the train to come to a stand, which it did at
the points. Here, the Driver recognised the workers as signal maintenance crew and abused
them for their actions. He then reported the incident to the Area Controller at Strathfield.
The near strike was the direct result of the signal maintenance team workers choosing to
remain in the danger zone after the initial warning of the approaching train. Subsequently,
none of them became alert to the presence of the train until its horn was sounded by the
Driver.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 88
Occurrence details
Event description: Near strike of maintenance staff.
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Safeworking rule or
procedure breach
Track work procedure breach
Individual actions
Findings Person type Activity type Error/Violation
type
The near strike occurred when the signal maintenance
team, working under the NAR method of worksite
protection, did not clear the danger zone as soon as the
positioned warning light was automatically extinguished by
the approach of train N804. At the time the warning light
extinguished, the train was 29 seconds (at track speed)
from their location.
Infrastructure
maintainer
Monitoring and
checking
Violation
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
Despite the warning of the train approaching, the Team
engaged in “at risk behaviour” by remaining on track and
instructing the Lookout to warn them when he saw the
train. Contrary to Network Procedures, the Lookout did not
continue to perform his role and the Team did not clear the
track until the Driver of N804 noticed them and blew his
horn.
Social
environment
Peer pressure Infrastructure ,
construction and
maintenance
The Team was on track approximately 15 minutes after
call-out which indicated that they had insufficient time to
complete a full safety assessment and work plan in
addition to all other necessary preparatory tasks. This is
also indicated by the lack of detail on the Worksite
Protection Plan and Pre-work Briefing forms prepared for
the task. Although other higher and safer forms of worksite
protection or train diversions were available, it appears
NAR was chosen by the Protection Officer as the worksite
protection method as it was the most expedient and least
time consuming method to implement.
Task demands Time pressure Infrastructure ,
construction and
maintenance
Of the methods available, NAR provides the least amount
of protection and relies entirely on the lookout’s vigilance,
notwithstanding the fact that in this case he had the
assistance of the warning light. It is reasonable to expect
that a thorough, conscientious safety assessment at the
site should have led to a decision to implement a higher
form of worksite protection and, importantly, one which
would have provided for separation of trains and workers,
as well as informing train crews of the presence of workers
on and about the track.
Organisational
management
Risk/change
management
Infrastructure ,
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 89
Reinstatement of the Protection Officer and Lookout to full
safeworking duties was not in accordance with the
Network Rules and Network Procedures Certification
Standard. The decisions made to reinstate them on the
day of the incident appear to have been based on
operational imperatives rather than safety requirements.
People
management
Job/task design Infrastructure ,
construction and
maintenance
NAR has been the subject of scrutiny over a number of
years but near strikes continue to occur within worksites
using it as the method of protection. The 2005 RailCorp
Worksite Protection Project recommended some changes
to the management and conduct of NAR but not all of its
recommendations have yet been implemented.
Organisational
management
Risk/change
management
Infrastructure ,
construction and
maintenance
There had been serviceability problems with the 538A
points over the 10 months since their replacement but the
routine maintenance system had not provided timely
detection and rectification of these problems. Points failure
attributed to lubrication wash away indicates a possible
underlying problem or combination of problems with the
lubricant being used, its application or the points
themselves.
Equipment, Plant
and infrastructure
Functionality Infrastructure ,
construction and
maintenance
Communications between the Protection Officer and Area
Controller were conversational and informal rather than
operationally formal according to prevailing communication
protocols.
Knowledge skills
and experience
Communication
skills
Infrastructure ,
construction and
maintenance
Management supervision of worksite protection through
on-site monitoring of work-on-track activity and auditing of
worksite planning and briefing documentation does not
appear to be as regular and rigorous as it ought to be.
Such activity is a legislative requirement and the need for it
has been highlighted on several occasions including in
RailCorp’s Worksite Protection Project and by the
Regulator.
Organisational
management
Risk/change
management
Infrastructure ,
construction and
maintenance
The unilateral issue of Standard Operating Instruction’s by
both ARTC and RailCorp to amend the network rules,
procedures and operating instructions associated with
NAR was not in accordance with the provisions of Part 5 of
the Rail Safety (General) Regulation 2008.
Organisational
management
Risk/change
management
Infrastructure ,
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 90
32. Woy Woy – Unsecured container gate – 11 April 2010
At approximately 11:45am Pacific National freight service 7MB4 was travelling through Woy
Woy Station when an unsecured gate on container BSCF215 became detached after hitting
the fencing at the Sydney end of Platform 1 and then striking another fence on the end of
Platform 2. The gate skidded across the platform for approximately 20 metres before
smashing a seating bay glass windbreak panel and coming to rest on the platform. The
dislodged gate narrowly missed striking members of the public waiting on the platform but,
despite a number of people being showered with broken glass, only one person suffered
minor injuries.
The investigation found that the second gate (of four)
on the right side of container BSCF215 detached from
the collapsible container as it struck the platform
fencing because its locking pins had dislodged from
their retaining lugs and it was not adequately restrained
from swinging laterally out of gauge. Two transport
agencies were involved in transporting the container
from where it was loaded to the Melbourne Freight Terminal (MFT) where it was transferred
onto a railway wagon. At no stage was it identified that the side gates of the container were
not secured in accordance with the performance standards recommended in the National
Transport Commission’s Load Restraint Guide – Second Edition 2004.
Subsequently, a pre-departure train examination did not detect that the gates on the
container were not secured in accordance with Pacific National’s Freight Loading Manual.
Checking on the integrity of the loading after departure
relied on a series of roll-by inspections which have
inherent limitations on their effectiveness. However, a
swinging gate was detected and rectified as a result of
one of the roll-by inspections en route but further roll-by
inspections did not detect either the loss of two other gates or anomalies with the securing of
the gates until after the incident. Pacific National’s own investigation into the incident
identified the relevant hazards and proposed 16 wide-ranging safety actions to be taken to
prevent the recurrence of similar incidents, and assigned responsibility and time frames for
implementation.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 91
Occurrence details
Event description: An unsecured container gate strikes infrastructure of a train station.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Collision Running line
With infrastructure
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The second gate on the right side of container BSCF 215
detached from the container as it struck platform fencing
on Woy Woy Station because its locking pins had
dislodged from their retaining lugs and it was not
adequately restrained from swinging laterally out of gauge.
Rolling stock – Car
body
Mechanical
discontinuity
Operation
Local Condition/Organisational factor
Findings Local
Condition/Organisation
al factor
Keywords Functional area
Between the time of loading of the container in Reppers
Transport yard at Stawell on 26 March and departure of
the train from MFT on 10 April, the loaded container
passed through the hands of several road and rail freight
agencies. At no stage was it identified that the side gates
of the container were not secured in accordance with the
requirements of the Load Restraint Guide and PN’s Freight
Loading Manual.
Knowledge, skills
and experience
Normal
operations
knowledge
and skills
Off-train operations
Following clearance by train examiners at MFT, checking
on the integrity of the loading relied on a series of roll-by
inspections which have inherent limitations on their
effectiveness.
Knowledge, skills
and experience
Normal
operations
knowledge
and skills
Off-train operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 92
33. Kogarah – Track worker fatality – 13 April 2010
At approximately 1:08am a CityRail inter-urban passenger service C488, en route from
Kiama to Central Station, struck and fatally injured a track worker at Kogarah Station as he
attempted to get clear of the track by climbing up on to Platform 1. The worker was part of a
team employed by Swetha International Pty Ltd which was contracted by RailCorp to remove
rubbish from tracks. The other four members of the team scattered from the path of the train
and avoided injury.
The Protection Officer for the team obtained approval
to use Controlled Signal Blocking (CSB) as the method
of work site protection at Kogarah. However, a number
of safety critical requirements of Network Rules and
Procedures were omitted in the process of
implementing the CSB. In particular, checks and cross-
checks between the Area Controller and the Protection
Officer were not completed on the two key CSB safety measures, that is, ensuring the
section was clear of all rail traffic and that the required blocking facilities had been applied on
the protecting signal/s. The Area Controller had not applied blocking facilities when he told
the Protection Officer that the blocks were on and the Protection Officer did not seek
confirmation that CSB had been fully implemented before commencing work.
The investigation found that the track worker was struck because the Area Controller did not
identify that the train was already in the section approaching Kogarah and past the
protecting signals before he applied blocking facilities. When the Area
Controller became aware of the situation, he asked the Station’s
Customer Service Attendant to initiate a warning over the Station’s
public address system, rather than using the more expedient means of
the MetroNet Train Radio system to bring trains to an emergency stop.
The Area Controller had only just returned from a lengthy period of
leave, most of which was sick leave. Although he returned to full duties without restrictions,
there was sufficient evidence from the circumstances which had necessitated the sick leave,
together with his previous medical history, to indicate that it would have been prudent to
have required clearance through a triggered health assessment before allowing him to
resume full duties, in accordance with the National Standard for Health Assessment of Rail
Safety Workers.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 93
Occurrence details
Event description: Track worker killed after being struck by passenger train.
Type of operation: Track maintenance
Fatalities 1 Injuries: nil
Occurrence Classification Collision Running line collision
With person not on a level crossing
Individual actions
Findings Person type Activity type Error/Violation
type
The track worker was struck and fatally injured because the
Area Controller did not identify that passenger service C488
had departed Hurstville and was in the section heading
towards Kogarah. When he authorised Controlled Signal
Blocking (CSB) for the protection of the rubbish removal
worksite alongside Platform 1 at Kogarah Station, C488 had
already passed protecting signal SM 914 and the driver had
not been informed of the presence of workers on the track at
Kogarah. In particular, checks and cross-checks were not
completed to ensure the section was clear of rail traffic and
the required blocking facilities had been applied.
Network controller Monitoring and
checking
Error
Instead of using the MetroNet Train Radio system available
to immediately alert trains that workers were on or about the
track, the Area Controller telephoned the Customer Service
Attendant at Kogarah Station and asked for an
announcement to be made over the Station public address
system to alert the track workers to the danger of the
oncoming train. This process took up valuable seconds and
resulted in insufficient time for the track workers to
comprehend the situation and then react to the warning.
The Area Controller had not applied blocking facilities when
he told the Protection Officer blocks were on.
Network controller Communicating Violation
Although the Protection Officer’s intentions and plan for the
worksite protection were sound, his planning, briefing and
documenting procedures lacked rigour in that they were not
fully completed and were conducted off site, en route to the
team’s initial work location at Beverly Hills.
Infrastructure
maintainer
Preparation and
planning
Violation
The Protection Officer did not seek confirmation that CSB
had been fully implemented as he assumed there would be
no more rail traffic and that the Area Controller knew what to
do as he had implemented CSB for him twice a little earlier
that evening without incident.
Infrastructure
maintainer
Communicating Violation
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
Initially, the four workers cleaning the track attempted to
climb onto Platform 1 as there were no safe places for them
along the Platform. Three of the workers abandoned that
Training and
assessment
Initial training Infrastructure ,
construction and
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 94
course of action and moved to the adjacent (live) track.
Evidence indicated that during induction and worksite
protection training, there was insufficient coverage of the
emergency safety precautions to be taken by workers if they
are caught on the track with a train approaching and no safe
place readily accessible.
maintenance
Although the Area Controller was experienced and held the
necessary current competencies, he had only recently
returned from a lengthy period of mainly sick leave
associated with health issues that had been ongoing
intermittently for some years. Even though he had returned
to work unrestricted, he had concerns about his fitness for
duty which had been shared with his Manager while on
leave. He considered calling in sick on the night of the
incident but was concerned about the ramifications of taking
more sick leave. There were sufficient ‘triggers’ in the Area
Controller’s circumstances to indicate that a new health
assessment should have been conducted to determine his
ability to perform his job safely, prior to returning to full
duties.
Organisational
management
Information
management
Off-train
operations
It is likely that the combined effects of a lengthy period of
irregular shifts, reduced sleep, working during the circadian
low and pre-existing health issues adversely affected the
Area Controller’s work performance.
Personal factors Fatigue/alertness Off-train
operations
Staff working in the Sydenham Signal Complex were not
provided with permanent full-time supervision, with
management generally only in location from 5:00am to
1:00pm on weekdays, depending on operational
imperatives, although network operations superintendents
could be called in on an as required basis. There were
conflicting reports as to whether immediate support or
supervision was available to the Area Controller or other
staff after the incident.
People
management
Supervision Off-train
operations
Accounting for attendance was voluntary for staff and the
taking of breaks during shifts occurred on an ad hoc basis.
Despite clear and repeated promulgation of policy, it is
apparent that personal electronic equipment was being used
for non-work related purposes by staff while on duty.
Task demands Distraction Off-train
operations
Although the MetroNet Train Radio provided the ability to
broadcast an emergency ‘STOP’ message, as well as a
direct call to the train, the Area Controller was not confident
in using it or in its capabilities. Nonetheless, RailCorp
considers that the training of Area Controllers in MetroNet
functionality is adequate and frequent enough. However, a
number of area controllers asserted they had never
undertaken a ‘Stop ALL Stop’ drill. Training drills in such a
seldom-required emergency procedure should be conducted
regularly so as to maintain the highest level of competency.
Training and
assessment
Ongoing training Off-train
operations
The recorded voice communications were informal and
conversational and not in accordance with Network Rules
and Procedures, particularly in relation to the handling of
safety critical information. This was despite RailCorp
publishing information bulletins emphasising the importance
to safety of effective communications and the ITSR targeting
communication protocols in its audit and inspection
Knowledge, skills
and experience
Communication
skills
Off-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 95
programs.
RailCorp had been conducting regular compliance audits of
recorded communications but these were not random, there
being a tendency for them to be done on the same day in a
particular time frame during a non-peak period and did not
specifically target communications between area controllers
and protection officers. Few non-compliances were identified
and, as they were classified as minor, they were actioned
informally and no record of the action kept.
Organisational
management
Monitoring,
review and
validation
Off-train
operations
Immediately after the incident, RailCorp made a subtle
change to the CSB Rule and Procedure using an
emergency change provision in the Rail Safety (General)
Regulation 2008. It was found that there was not a universal
knowledge of the change within RailCorp and that
understanding of the original rule varied among those
charged with applying it.
Organisational
management
Information
management
Off-train
operations
A warning light system, which relies on a lookout
maintaining active observation, was in place at Kogarah due
to restricted sighting on the track approach from the South. It
was not utilised as the Protection Officer considered CSB
had been successfully implemented and that any possible
threat was assessed as coming from the opposite direction
(albeit on the adjacent track). Additionally, there were no
backup mechanisms to alert persons in the vicinity that the
lights had in fact extinguished. However, while the purpose
of warning lights is included in the Network Rules and
Procedures, they do not reinforce the requirements for
workers to act when warning lights extinguish. Warning
lights are not shown on older diagrams and network maps.
Procedures Accuracy/Clarity Off-train
operations
The procedures used to place signals back to stop in
emergencies were not current or clearly understood by
users. Further, recent system hardware and software
modifications were not clearly delineated to or understood
by users. For example, the Area Controller was unaware
that the Signal Emergency Control Button on the adjacent
panel had the ability to set automatic signals on his panel to
Stop between Hurstville and Kogarah.
Procedures Accuracy/Clarity Off-train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 96
34. Wee Waa – Level crossing collision – 1 September 2010
At approximately 7:40am two Pacific National locomotives, operating as train D551, struck a
road motor vehicle (RMV) on a private level crossing located in the Narrabri West to Wee
Waa section approximately four kilometres east of the township of Wee Waa. As a result, the
driver of the RMV, a 32 year old resident from Wee Waa, suffered fatal injuries. No crew
members of D551 were injured but they were treated for shock.
The crew stated that D551 was travelling at the
maximum permitted track speed of 80km/h on
approach to the level crossing, and this was verified in
the analysis of the event recorder tape from the leading
locomotive. At a point approximately 400m prior to the
crossing, they sounded the train whistle (horn) in
accordance with ARTC Network Rule ANTR 408 Using
Train Whistles. At a point approximately 100 metres from the crossing the Driver again
sounded the whistle observing that, at this time, the crossing was clear. However, almost
immediately after, the Assistant Driver observed a white RMV appear ‘travelling from right to
left at moderate speed’ and alerted the Driver. The Driver immediately made an emergency
brake application. They then felt and heard the locomotive strike the RMV. D551 came to a
stand some 632m beyond the crossing.
D551 impacted the RMV on the passenger side in the area of the rear pillar of the cabin and
tray section. The RMV was then propelled in an arc-like trajectory from the crossing and
spun approximately 180°. It came to rest on the parallel
access road at a point some 32m from the crossing and
14.4m from the track.
The primary cause of the collision was the driver of the
RMV not stopping and giving way to the approaching train
as is required by Australian Road Rules 121 and 123.
OTSI was not able to establish why the driver of the RMV failed to stop.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 97
Occurrence details
Event description: Passenger train collision with car at level crossing
Type of operation: Freight
Fatalities 1 Injuries: nil
Occurrence Classification Level crossing occurrence Collision with road vehicle
At crossing with passive warning devices: Stop signs
Individual actions
Findings Person type Activity type Error/Violation type
The collision was caused by the failure of the driver of the
Road Motor Vehicle to stop and give way to the
Locomotive, as was required by Australian Road Rule 121
and 123.
Light passenger
vehicle driver
Monitoring and
checking
Error
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 98
35. Bankstown – Near miss with track workers – 29 October 2010
At 12:55am the driver of an empty CityRail train travelling through Bankstown towards
Sydenham reported having sounded the train’s whistle and applied emergency braking due
to the presence of rail workers on the track ahead. The train stopped approximately 60
metres away from the workers, who by then had moved to a safe place beside the track.
The four workers, under the supervision of a Protection
Officer, were removing litter from the rail corridor.
Controlled Signal Blocking had been determined as the
appropriate method of worksite protection to be
employed at Bankstown.
After finishing work on the Down track beside Platform
2, the workers crossed to a safe place at the end of the platform and adjacent to the Up track
where a train was standing at Platform 1. While they
waited for this train to depart, the Protection Officer, who
had been delayed by the need to photograph the
condition of the Down track after cleaning, caught up with
his team. When the train departed, the four workers
moved onto the track and commenced litter removal, in
the belief that their Protection Officer had arranged the
planned worksite protection.
Meanwhile, the Protection Officer, walking along the platform near his team of workers, was
having difficulty contacting the Area Controller at Sydenham by mobile phone to arrange for
the protection on the Down track to be lifted and for protection to be provided on the Up
track. While the workers were on the track and the Protection Officer was seeking mobile
phone connection, the CityRail train approached the Station in the Up direction. On seeing
the workers on the track in front of him, the driver sounded the train’s whistle and
immediately applied emergency braking, stopping short of the workers’ location. On hearing
the whistle the workers moved quickly to the nominated Safe Place, while simultaneously the
Protection Officer turned to warn the workers.
The near miss occurred because, when the track workers commenced work on a live section
of track without any form of worksite protection, their Protection Officer did not ensure their
immediate movement to a Safe Place.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 99
Occurrence details
Event description: Near miss with track workers.
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Safeworking rule or
procedure breach
Track work procedure/rule breach
Individual actions Findings Person type Activity type Error/Violation type
The near miss occurred because when the track workers
commenced work on a live section of track without any
form of worksite protection.
Infrastructure
maintainers
Communicating Error
The Protection Officer did not ensure their immediate
movement to a Safe Place.
Infrastructure
maintainers
Monitoring and
checking
Error
Local Condition/Organisational factor Findings Local
Condition/Organi
sational factor
Keywords Functional area
The Protection Officer was distracted by the need to
communicate with the Area Controller to fulfil the CSB
protection that had been provided for the then completed
work on the Down track, and by the need to take “before
and after” photographs of the corridor as part of the Station
Corridor Cleaning contract. As a consequence he did not
fulfil his primary task which was to provide a safe working
environment for his team.
Task demand Distraction Infrastructure ,
construction and
maintenance
The Protection Officer’s attempts to contact the Area
Controller to fulfil CSB arrangements on the Down track
and to arrange for CSB on the Up track were delayed by
his inability to find a location with an adequate mobile
phone service.
Equipment, plant
and infrastructure
Reliability Infrastructure ,
construction and
maintenance
The track workers proceeded onto the track to commence
work without first checking whether protection had been
established.
Task demands Time pressure Infrastructure ,
construction and
maintenance
The manner of spoken communication between the
Protection Officer and the track workers lacked precision
and clarity, resulting in misinterpretation.
Knowledge skills
and experience
Communication
skills
Infrastructure ,
construction and
maintenance
The Protection Officer’s discussion of protection methods
with the Area Controller was ambiguous, leaving the Area
Controller to understand that work on the Up track at
Bankstown was to be performed under NAR.
Knowledge skills
and experience
Communication
skills
Infrastructure ,
construction and
maintenance
The preparation of Worksite Protection Plans and conduct
of Pre-work Briefings using forms partly copied from earlier
jobs and finalised on the way to the worksite provided the
benefits of time saving and consistency. However, this can
make it easy to overlook unanticipated issues specific to a
worksite at a particular time, and can also result in a lack of
precision with no clear understanding by team members as
to the specific measures to be used.
Procedures Clarity Infrastructure ,
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 100
36. Unanderra – Uncontrolled movement – 2 February 2011
At approximately 6.38am a loaded El Zorro Transport Pty Ltd grain service 3996, en route
from West Wyalong to Port Kembla, passed signal WG 1014 at danger before coming to a
stand 527 metres beyond the signal which is located on the Northern side of Unanderra
Station. The driver had not been able to control the speed of the train towards the end of its
descent of the steeply sloping Illawarra Mountain. No injuries resulted from the incident and
there was no damage occasioned to any or infrastructure.
The investigation found that the train became
uncontrolled during its descent because the manner in
which it was driven did not provide for effective braking.
Initial braking effort was too light, but then was
progressively increased until a full brake application
was achieved using the brake valve handle-off position
rather than the full service or emergency position. At a
critical point in the sequence of events, braking became unbalanced when the dynamic
brake was disengaged and then re-engaged. In addition, on a number of occasions
throughout the journey, the train was allowed to travel well in excess of the designated
speed of 25 km/h for single pipe trains as well as the posted speed of 30 km/h.
Although it did not contribute directly to the uncontrolled movement, there was a difference
between the type of braking system actually fitted to the train and the system that was listed
in the Train Operating Conditions (TOC) manuals. The
WGBY class of wagon making up the consist of the train
was fitted with a dual pipe braking system. However, this
was not documented or recognised as such during the
certifying process on their introduction into service or
during subsequent operations. Consequently, they were
listed in the RailCorp and Australian Rail Track Corporation (ARTC) Train Operating
Conditions (TOC) manuals as ‘single pipe’ wagons.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 101
Occurrence details
Event description: Uncontrolled movement.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Signal passed at danger Completely missed by driver
Individual actions Findings Person type Activity type Error/Violation type
El Zorro grain service 3996 became uncontrolled during its
descent of the Illawarra Mountain because the train was not
managed in accordance with good practice. The result was a
loss of the necessary braking effort to be able to maintain full
control of the movement.
Train crew Operating
equipment
Error
Local Condition/Organisational factor Findings Local
Condition/Organi
sational factor
Keywords Functional area
Up to the time of the incident, El Zorro had no documented
policies or procedures for the control of trains descending the
Illawarra Mountain. Instead, drivers were instructed to use the
network manager’s TOC manuals.
Procedures Absent
procedures
On train operations
Despite being issued with TOC waivers from both RailCorp
and ARTC which classified the WGBY wagons as single pipe
wagons, El Zorro operated the grain train services under dual
pipe conditions from the time of introduction of the wagons into
service. This anomaly was not identified by either RailCorp or
ARTC.
Organisational
management
Monitoring,
review and
validation
On train operations
The co-driver was unable to establish contact with the
Wollongong Signal Box to alert the signaller to the
uncontrolled movement until after the train came to a stand.
He chose to use a mobile telephone in preference to the
CountryNet radio emergency function.
Equipment, plant
and infrastructure
Functionality On train operations
ARTC’s TOC manual had not been updated since 2004 and
there were 592 waivers awaiting insertion in the manual.
Some information in the Local Appendix Units was also not
current.
Organisational
management
Information
management
Rolling stock
construction and
maintenance
The modification to the WGBY wagon involving the addition of
a connection from the main reservoir pipe to the wagon’s
auxiliary reservoir was not subjected to feed or flow rate tests
and does not meet RailCorp’s or ARTC’s engineering
requirements.
Organisational
management
Risk/ change
management
Rolling stock
construction and
maintenance
The modification to the WGBY wagon involving the addition of
a connection from the main reservoir pipe to the wagon’s
auxiliary reservoir was not subjected to feed or flow rate tests
and does not meet RailCorp’s or ARTC’s engineering
requirements.
Organisational
management
Risk/ change
management
Rolling stock
construction and
maintenance
Currently in Australia, there is no standard defining what
constitutes single and dual pipe wagons, including the various
engineering aspects such as the purpose, application, flow
rates and timing in reference to charge rates.
External
organisational
influences
Industry
standards or
guidance
Rolling stock
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 102
37. Zig Zag – Collision between a train and a Hi-rail – 1 April 2011
At 1:30pm a Zig Zag Railway maintenance vehicle (the Hi-Rail), collided with a two-car Rail
Motor on the No 1 Viaduct, Top Road, between Clarence and Top Points stations. The Hi-
Rail, with a Driver and Passenger on board, was freewheeling down the hill in reverse in the
section from Clarence towards Top Points. The Rail Motor, operated by a Driver, was
travelling without passengers in the opposite direction from Top Points.
The Rail Motor Driver saw the approaching vehicle and
applied the brakes. However, the two persons onboard
the Hi-Rail, facing the opposite direction, did not see
the Rail Motor before the collision. The force of the
collision compacted the body of the Hi-Rail such that
neither cab door would open. The two occupants of the
Hi-Rail were injured in the collision and were assisted
out of the Hi-Rail and onto the Rail Motor by the Rail Motor Driver who was uninjured. The
force of the collision caused a minor misalignment of the track.
The investigation established that the collision resulted from the Driver of the Rail Motor and
the Driver of the Hi-Rail not being aware that they were travelling towards each other on the
same track in the Top Points-Clarence section. This lack
of situational awareness resulted from procedural errors.
The Rail Motor Driver departed Top Points without
communicating his intention to his Guard or the Hi-Rail
crew, and the Rail Motor Guard exceeded his authority by
authorising the Hi-Rail to leave a worksite and proceed to
Top Points.
A number of other factors were found to have contributed to the collision, particularly a lack
of radio communications and operational safeworking errors. Other safety issues identified
during the investigation included delayed notification of the accident; poor maintenance of
Train Register Books; passengers travelling in the Rail Motor driver’s cab; Rail Motor
Driver’s fatigue; and excess speed of the Hi-Rail.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 103
Occurrence details
Event description: Collision between passenger train and hi-rail vehicle.
Type of operation: Passenger and track maintenance
Fatalities nil Injuries: 2
Occurrence Classification Collision Running line collision
Between trains
Individual actions
Findings Person type Activity type Error/Violation
type
The collision occurred because the Driver of the Rail Motor
and the Driver of the Hi-Rail were unaware that they were
travelling towards each other on the same track in the same
section and, in the case of the Rail Motor Driver, when he
saw the approaching Hi-Rail, was unable to take any
emergency action which would have been effective in
preventing the Hi-Rail from colliding with the Rail Motor.
Train crew Operating equipment Error
The Driver of the Hi-Rail was unable to take any emergency
action to prevent the collision because he was travelling
backwards down the track and neither he nor his Passenger
was maintaining an effective lookout.
Train crew Operating equipment Error
The Rail Motor Guard exceeded his authority by authorising
the Hi-Rail to leave the RTA worksite and proceed to Top
Points.
Train crew Operating equipment Error
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional
area
The Rail Motor Driver departed Top Points without
communicating his intention to his Guard or the Hi-Rail
crew.
Knowledge,
skills and
experience
Communication skills On train
operations
The Hi-Rail was travelling above the posted speed
restriction of 10km/h on the No.1 Viaduct.
Knowledge,
skills and
experience
Normal operations
knowledge & skills
On train
operations
The Rail Motor Driver’s performance may have been
degraded by fatigue.
Personal factors Fatigue/alertness On train
operations
The Rail Motor Driver left Top Points without any radio
communication at his end of the Rail Motor and no other
means of communicating with other staff. Consequently,
he did not hear the Hi-Rail Driver request and get approval
from the Guard to travel to Top Points.
Equipment, plant
& infrastructure
Absent equipment,
plant & infrastructure
On train
operations
Both the Driver and Guard of the Rail Motor had made an
error on a previous trip when they failed to check they had
the Staff when they departed Top Points.
Knowledge,
skills and
experience
Teamwork skills On train
operations
The Rail Motor Driver, acting in his capacity as Operations
Manager, authorised both the Rail Motor and Hi-Rail to
depart Clarence with the Staff unsecured at the other end
of the section.
Knowledge,
skills and
experience
Normal operations
knowledge & skills
On train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 104
The management of operations was concentrated in the
hands of one person on the day of the collision. The Rail
Motor Driver was also acting as the Train Controller as well
as holding the position of Operations Manager.
Organisational
management
Competence of
senior personnel
On train
operations
There was an accepted practice of qualified workers
authorising rail traffic movements without reference to the
train controller.
Social
environment
Norms and values On train
operations
It was accepted practice for both Staffs being kept in the
Lithgow end of the Rail Motor. This increased the
probability that the required check, that the correct Staff
was at hand, was not done if the Rail Motor was driven
from the Clarence end.
Social
environment
Norms and values On train
operations
The procedure relating to the collection of Staffs from
Signal Boxes was ambiguous.
Procedures Accuracy/clarity On train
operations
The Rail Motor Driver allowed two passengers to ride in
the front cab on a journey from Top Points to Clarence.
This may have distracted him and, to a lesser extent, the
Guard from checking if they had the Staff before departing.
Task demands Distraction On train
operations
There was no rule about passengers travelling in the cab
of the Rail Motor.
Procedures Absent procedures On train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 105
38. Enfield yard – Runaway rolling stock – 3 May 2011
At approximately 12:45pm a Pacific National Terminal Operator was changing brake blocks
on a rake of 28 loaded aggregate wagons stabled in North Road No.1 in Enfield Yard. When
he released the air pressure in the braking system on a wagon in the centre of the rake in
order to change a brake block, the remaining brakes applied to the rake did not hold the rake
on the prevailing grade and it began to run away.
The Terminal Operator’s attempt to stop the rake by
applying hand brakes on two wagons as they passed
was not successful. The rake ran away through the
yard and entered South Road No.1 colliding with
another stabled rake consisting of 15 empty fuel tanker
wagons and three flat bed wagons (located at the
opposite end). The combined rakes continued, with two
of the tankers derailing and slewing across the track, carrying away two shunting signals and
an overhead wiring portal stanchion. The two rakes came to rest approximately 460 metres
from the point of collision with the derailed tankers foul of the Up and Down Main lines. The
rake of aggregate wagons ran away for a total of 1085 metres.
The investigation established that too few handbrakes had been applied to the rake in order
to hold it on the prevailing grade. Pacific National’s maintenance regime and training of
terminal operators was not adequate for the effective
maintenance of brakes on rolling stock that did not have
slack adjusters. Also, Pacific National did not comply with
the Safety Interface Plan and Management Agreement
with RailCorp in regard to controlling the risk of runaways.
Further, Pacific National did not comply with its own
procedures for risk assessments to test the efficacy of its
minimum requirement for handbrake application at Enfield Yard. The investigation identified
a number of safety issues for improvement including Pacific National’s non-conformance
with its own procedures for undertaking risk assessments, and gaps in training and
procedures in relation to brake maintenance.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 106
Occurrence details
Event description: Runaway .
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment Running line collision
Individual actions
Findings Person type Activity type Error/Violation
type
The immediate cause of the incident was that, during
maintenance activities, the air brakes were released on
wagon NPZH35652C and the rake ran away due to the
rake’s remaining brakes being insufficient to hold it stationary
on the prevailing grade.
Terminal staff Operating
equipment
Error
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional
area
Pacific National did not comply with the requirements of
the Safety Interface Plan with RailCorp; viz., it did not
comply with the requirements to “ensure that is not left
unattended unless appropriately stabled and protected in
accordance with RailCorp Network Rules and
Procedures”.
Organisational
management
Communication
and consultation
process
Off train
operations
Pacific National did not comply with the requirements of
the Management Plan with RailCorp which specified that
the requirements of the TOC Manual were to be met. The
TOC Manual specified that nine wagons should have had
handbrakes applied on this train.
Organisational
management
Communication
and consultation
process
Off train
operations
Pacific National had not carried out any risk assessments
to test the efficacy of its minimum requirement for
handbrake application at Enfield Yard as required by its
own procedures and the Safety Interface Plan.
Organisational
management
Risk
management
Off train
operations
There were no procedures specific to the maintenance
activity of changing brake blocks especially on wagons that
were not fitted with slack adjusters.
Procedures Absent procedures Off train
operations
No training been provided to Terminal Operators in regard
to the adjustment of brakes on without slack adjusters.
Training and
assessment
Initial training Off train
operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 107
39. Woy Woy – Level crossing collision – 2 Sep 2011
At approximately 6.17pm CityRail’s Sydney to Wyong interurban passenger service 289G,
carrying approximately 200 passengers, struck a stationary, unoccupied road motor vehicle
(RMV) on the Down Main line at the Rawson Road level crossing at Woy Woy on the Central
Coast of NSW. The RMV had become stuck on the line after its driver became disoriented
and turned onto the line from the crossing while trying to locate a street running parallel to
the line.
The driver of the RMV had been unable to move the
RMV after it became stuck despite the assistance of a
number of passers-by who saw him attempting to move
it off the line. However, shortly after they commenced
attempting to assist the driver, the automatic protection
equipment at the level crossing activated, indicating an
approaching train. The driver, and those assisting,
immediately moved off the tracks out of the path of trains.
The driver of 289G was unable to stop before striking the RMV which, after impact, became
wedged underneath the train and was pushed for approximately 300 metres along the track
but without derailing the train.
While no persons were reported injured in the incident, a
number of safety issues were identified during the course
of the investigation. These included: an inadequate
obstruction deflection system on passenger used on
interurban routes to prevent larger obstructions from
becoming wedged underneath and potentially derailing the train; information overload from
signage at the crossing; the lack of road markings inside the rail corridor defining the
roadway; and the lack of emergency contact information provided at level crossings.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 108
Occurrence details
Event description: Passenger train collision with car at level crossing.
Type of operation: Passenger
Fatalities nil Injuries: nil
Occurrence Classification Level crossing occurrence Collision with road vehicle
Occurrence category At crossing with active warning devices
Individual actions
Findings Person type Activity type Error/Violation
type
The collision occurred as a result of the driver of the RMV
becoming disoriented at Rawson Road level crossing, driving
his vehicle onto the railway line and then not being able to
remove the vehicle from the line to a safe location.
Light passenger
vehicle driver
Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional
area
The number and variety of signage positioned in the
vicinity of the crossing created information overload.
Task demands High workload Road
environment
There were no road markings providing a clear delineation
of the roadway inside the rail corridor at the crossing.
Equipment, plant
and infrastructure
Signage Road
environment
OSCAR EMU sets incorporate lifeguards to clear small
obstacles or debris from the path of the train wheels,
designed in accordance with Section 16 of (British)
RailTrack Railway Group Standard GM/RT 2100.
However, neither the OSCAR sets nor other EMU
passenger operating on interurban routes incorporate
additional protection to deflect more substantial obstacles
such as provided for in Section 12 of the Standard.
Equipment, plant
and infrastructure
Absent
equipment
Rolling stock
construction
and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 109
40. Clifton – Broken axle derailment – 23 Nov 2011
At approximately 11.56pm a Pacific National coal service MC92 derailed eight wagons at
Clifton. MC92, a 45-wagon train with single locomotives at its front and rear, was fully loaded
with coal and was travelling South from the Metropolitan Colliery at Helensburgh to Inner
Harbour at Port Kembla where it was to be unloaded. The leading locomotive had just
passed Clifton level crossing when an emergency application of the train’s brakes occurred
automatically and it came to a stand. The rear of the train was still inside the Coalcliff tunnel.
The Driver on the leading locomotive notified the
RailCorp Signal Complex at Wollongong that his train
was stopped. He then sent his Co-driver back to
inspect the train and locate whatever had caused the
brakes to apply automatically. The Co-driver found that
the train had derailed North of the level crossing and
used his two-way radio to alert the Driver. At 12.08am
the Driver notified the RailCorp Signal Complex at Wollongong that the train had derailed.
The investigation revealed that the barrel of the No.3 axle of the eighth position wagon had
broken and parted, causing both wheels to derail. As a result, seven wagons following this
wagon derailed. The two locomotives and all other
wagons remained on the track. Although there were no
injuries as a result of the derailment, approximately 470
metres of damaged track needed to be replaced.
The investigation established that the break in the axle
was attributable to the propagation of metal fatigue at the
site of the fracture. The fatigue fracture was initiated some time prior to the final complete
failure of the axle at the derailment site but, due to damage sustained in the derailment, the
initiator of the fracture could not be determined.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 110
Occurrence details
Event description: Freight train derailment due to broken axle on wagon.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On a running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The derailment of MC92 was a consequence of the barrel of
the No. 3 axle of the eighth wagon breaking. This breakage
caused the wheelset to derail which subsequently resulted in
eight wagons fully or partially derailing. The axle broke due
to the initiation and propagation of metal fatigue at the site of
the fracture. The fatigue fracture was initiated some time
prior to the final complete failure of the axle at the derailment
site but, due to consequential damage around the axle
circumference, a determination could not be made about the
initiator for this fatigue failure.
Rolling stock- Bogies Fracture Unknown
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
The axle, which was about 50% fractured at the time of the
incident, finally failed while being subjected to normal
cyclic loading.
Equipment, plant
and infrastructure
Functionality Rolling stock
construction and
maintenance
The current inspection standards for Unit Train
Maintenance do not emphasise the examination of the axle
barrel.
Procedures Accuracy/
adequacy
Rolling stock
construction and
maintenance
The two or three year interval (depending on kilometres
travelled) between the non-destructive testing of axles may
exceed the time taken from the initiation of a stress raiser
to the ultimate failure of an axle.
Procedures Accuracy/
adequacy
Rolling stock
construction and
maintenance
The train crew on the trailing locomotive were inside the
cab of their locomotive which was stationary inside the
Coalcliff Tunnel, with no effective means of
communication. The Coalcliff Tunnel is a known black spot
for communications.
Equipment, plant
and infrastructure
Absent
equipment
Rolling stock
construction and
maintenance
There is potential for wagons to be overloaded as there is
no measurement of the weight of the wagons at the
loading terminal, or along the track, until the unloading
facility at Inner Harbour Port Kembla.
Procedures Accuracy/
adequacy
Freight handling
The shutdown button and the control/engine switches in
the trailing locomotive of MC92 were ineffective in shutting
down the engine following the derailment.
Equipment, plant
and infrastructure
Control input
devices design
Rolling stock
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 111
41. Unanderra – Safeworking incident – 12 Dec 2011
At about 12:45am a Pacific National freight train 3930 was stationary at Unanderra Station
when the driver was contacted by the area controller in the Wollongong Signalling Complex
with a request to inspect the condition of one of his wagons. To carry out this inspection, the
driver requested Controlled Signal Blocking (CSB) so that he could access the danger zone
of the track adjacent to his train. The intended effect of the CSB was to exclude rail traffic
from the portion of track in which he would be working. The area controller granted the
request and the driver left the cab of his locomotive and climbed down onto the track.
While he was in the danger zone, the driver was
notified by his co-driver that no CSB protection was in
place and he subsequently observed the lights of an
approaching train. Although he could not determine on
which track this train was proceeding, he prudently
moved to the closest safe place between two wagons
of his train. As it transpired, the approaching train was
travelling on the track on the opposite side of the platform to PN 3930 and posed no actual
threat to the driver’s safety.
The investigation identified a lack of adherence to communications protocols and the specific
procedures, including information exchange protocols, contained in RailCorp’s CSB Rules
and Procedures that were in force at the time. Protecting
train crew using CSB was identified as a task seldom
undertaken by either the area controller or the train driver.
The Report highlights the extent to which ineffective
communications continue to constitute one of the
significant contributing factors in the causation of
safeworking incidents reported to OTSI. Additionally, differences in the rules and procedures
applied by the various network owners within NSW continue to exist.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 112
Occurrence details
Event description: Safeworking breach with driver on track.
Type of operation: Passenger
Fatalities nil Injuries: nil
Occurrence Classification Safeworking Rule or
procedure breach
Track work procedure/rule breach
Individual actions
Findings Person type Activity type Error/Violation
type
The investigation established that the incident occurred
because the communications protocols and the specific
procedures, including information exchange protocols,
contained in RailCorp’s CSB Rules and Procedures that
were in force at the time, were not adhered to.
Network controller Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
Verbal communication did not conform to the requirements
of RailCorp Network Rule NGE204 Network
communication, Network Procedure NPR721 Spoken and
written communication or the requirements of the CSB
(now ASB) rules and procedures.
Knowledge, skills
and experience
Communication
skills
Off-train
operation
Evidence suggests that the AC may have relied on an
earlier learned routine to provide practical protection to the
driver trainer on the Down Illawarra Main line which did not
conform to the letter of the prevailing Network Rules and
Procedures. He was unable to clarify what ‘protection’ had
been requested by the train crew, and which he had
authorised, when challenged by the train controller.
Knowledge, skills
and experience
Normal
operations
knowledge and
skills
Off-train
operation
The AC’s knowledge of the CSB rules and procedures was
incomplete, and he lacked familiarity with applying it,
particularly in relation to the infrequently performed task of
protecting train crews.
Knowledge, skills
and experience
Normal
operations
knowledge and
skills
Off-train
operation
The train crew did not have access to reference
documents to check how CSB (an infrequent task for them
also) should be requested and implemented. Additionally,
they did not have access to the worksite protection plan
form (NRF 015A).
Procedures Availability/
accessibility
Off-train
operation
Pacific National was unaware that their train crews were
required to use Form NRF 015A (or NRF 015B for lookout
working) and had therefore taken no steps to provide the
forms, or training in their use, to train crews.
Organisational
management
Information
management
Off-train
operation
The AC conferred with the 2nd person about the safety
arrangements without reference to the driver trainer who
was the Protection Officer.
Knowledge, skills
and experience
Communication
skills
Off-train
operation
This lack of consultation was exacerbated by the fact that
the driver trainer’s handheld WB radio was unserviceable
when he was outside the locomotive’s cab.
Equipment, plant
and infrastructure
Absent
equipment
Off-train
operation
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 113
42. Gunnedah – SPAD and opposing movement – 7 March 2012
At 10.27pm a Pacific National grain train 5424N passed signal GH26 on the outskirts of
Gunnedah while it was showing a red Stop indication. The second person alerted the driver
to the incident and the driver responded by applying the brakes. The train then trailed
through a set of points before coming to a stand. Concurrently, Pacific National coal train
WH191 was proceeding in the opposite direction from a passing loop onto the single Main
line and so was on a collision course. On becoming aware of 5424N coming towards him,
the driver of WH191 immediately brought his train to a stand. The trains stopped 715 m
apart with 5424N 870 m beyond signal GH26. The crew of 5424N did not detect the
presence of WH191 until after both had stopped.
The network controller attempted to make an
emergency broadcast call over the CountryNet radio
when he became aware of 5424N passing signal
GH26. However, the call failed primarily due to the
network controller’s lack of understanding of the radio
system’s characteristic delay when placing this type of
call. The Australian Rail Track Corporation
subsequently produced an information and instructional document on the subject and
distributed it to its network controllers.
The investigation focused on the actions of the train crews before and during the incident
and the communications failures immediately after it. Also considered was the design and
layout of the signalling infrastructure and crew fitness for
duty.
The reason the driver of 5424N did not respond to the
signal indication is likely to have been his misreading of
two consecutive stop signals as a single signal causing
him to misinterpret where he should stop.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 114
Occurrence details
Event description: SPAD and opposing movement by two freight trains
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Signal Passed at Danger Completely missed by driver
Individual actions Findings Person type Activity type Error/Violation type
The SPAD and opposing movement resulted from train
5424N being driven through signal GH26 at Stop without
authority then proceeding to trail through 55A points. This
brought the train into a conflicting movement with train
WH191 approaching with authority from the opposite
direction on the single line.
Train crew Monitoring and
checking
Error
On becoming aware of the SPAD, the Network Controller
did not attempt to contact 5424N directly via CountryNet,
instead first trying to contact WH191 then making a
‘broadcast call’, neither of which was successful.
Network
controller
Communicating Error
Local Condition/Organisational factor Findings Local
Condition/Organi
sational factor
Keywords Functional area
When viewed from a distance, signal GH22 appears directly
above signal GH26. The main head and marker lights of
each signal merge to appear to be one light. This produces
the effect that signals GH26 and GH22 look like one signal
(main head and marker) as two red lights can be observed
one almost above the other, even though they are two
separate signals 2.1 km apart. The driver is likely to have
observed the two signals as being one and formed the
opinion that the signal was GH22 where, from past
experience, he might expect to have to stop.
Physical
environment
Lighting/
visibility
On-train operation
It is likely that the visual distortion was caused by the design
of the signal lights that now use LED technology which, in
low ambient light, make the smaller marker light appear to
be of similar size and intensity to the larger main head. The
two separate signals appeared to the driver to be one and,
despite the calls from the second person, influenced the
driver’s mental model of where he was authorised to
proceed.
Equipment, plant
and
infrastructure
Infrastructure
design
On-train operation
The second person was under training and was relatively
inexperienced; an authority gradient existed between him
and the driver. This contributed to the second person not
taking more positive action when the driver of 5424N did not
comply with PN’s procedure requiring him to reduce speed
to 15 km/h 200 m from the signal and stop 50 m before it.
Social
environment
Peer pressure On-train operation
Defence against human error at the site relied entirely on the
crew of 5424N observing and obeying the indication of
colour light signals. Installation of an automatic train
management system on the network will provide additional
defences in the future.
Equipment, plant
and
infrastructure
Absent plant On-train operation
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 115
43. Nundah – Level crossing collision – 7 May 2012
At 9.11am on Friday 4 May 2012 an unladen coal train travelling north-west on the Main
North line collided with a utility on a railway crossing on Middle Falbrook Road, Glennies
Creek, at a rail location known as Nundah. The driver of the utility was fatally injured in the
collision.
The train, operated by QR National Limited, was less
than 100 metres from the crossing and travelling at 71
km/h when the crew saw the utility approaching the
crossing from their right at a moderate speed and then
continuing onto the crossing without appearing to slow.
The train struck the left side door of the utility, dragging
the vehicle for 70 metres and finally stopping under emergency braking about 400 metres
past the point of impact, with the utility on the right hand side of the train on the adjacent
track. A laden Pacific National coal train travelling in the opposite direction had been
standing for some minutes with its headlight extinguished approximately 800 metres from the
crossing on the adjacent track, and its crew immediately secured their train and hurried up
the track to lend assistance.
The railway crossing was passively protected by stop signs and associated roadside signs
and road markings, except for a stop line on the road immediately before the crossing. The
driver’s vision of trains approaching from the south-east
was limited by the presence of a work compound to his
left. However, the stop sign before the crossing was
visible for a distance of at least 85 metres.
The reason the utility was driven onto the crossing without
stopping is unknown. However, it is possible that the driver was distracted by the busy visual
environment as he approached the crossing and that the driver’s view of the train
approaching from his left was compromised by the presence of the work compound and
fences in his line of sight.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 116
Occurrence details
Event description: Level crossing collision between road motor vehicle and freight train.
Type of operation: Freight
Fatalities 1 Injuries: nil
Occurrence Classification Level crossing occurrence: Collision with road vehicle
At crossing with passive warning devices: Stop signs
Individual actions
Findings Person type Activity type Error/Violation type
The driver of the utility drove past the stop sign without
stopping and continued onto the crossing into the path of
the approaching train which was unable to stop in time to
avoid collision.
Light passenger
vehicle driver
Monitoring and
checking
Unknown
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
The driver was distracted by the number of signs and other
roadside furniture, by the presence of the Upper Hunter
Valley Alliance compound and by the poor condition of the
road, and paid insufficient attention to the relatively
inconspicuous crossing.
Task demands
Distractions
Road environment
The driver’s view of the approaching train was obscured by
the presence of the compound fencing.
Physical
environment
Lighting/visibility Road environment
The railway crossing did not fully meet the requirements of
Australian Standard 1742.7—2007 as there was no visible
stop line accompanying the stop sign. Furthermore, the
position of the stop sign, although meeting the
requirements of the standard, was such that, if used as the
only guide for the correct stopping position, afforded the
driver an obstructed view to the left.
Equipment, plant
and
infrastructure
Signage Road environment
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 117
44. Bengalla – Ballast train collision – 18 May 2012
At approximately 5.15am the leading wagon of Australian Rail Track Corporation (ARTC)
ballast train 6M21 was derailed after colliding with an unmanned ballast regulating machine
within a worksite in the Bengalla to Mangoola section on the Ulan line. The regulator was
stationary, having run out of fuel. Four workers who were riding on the train underwent
precautionary examination at Muswellbrook Hospital and were treated for minor bruising.
Although the regulator was pushed approximately 50 metres by the train, the rolling stock
suffered comparatively minor damage.
At the time of the collision the train was being propelled
under the direction of a Pilot standing on the rear
platform of the leading wagon. The Pilot had been
made aware of the disabled regulator by the qualified
worker acting in the capacity of Protection Officer of a
resurfacing team responsible for it. However, he had
not been given, nor had he sought, details of the machine’s exact location and believed it
was standing approximately three kilometres beyond the intended drop point for the ballast.
The Pilot did not see the regulator until just before the train collided with it.
The collision of ballast train 6M21 with the disabled ballast regulating machine, and the
subsequent derailment of the leading wagon, was found to be attributable to ineffective
communication between safety critical staff about the
location of the disabled ballast regulator.
Overreliance was placed on the direction lights on the
regulator to indicate its stationary presence and provide
sufficient warning of an obstruction on the track, but these
lights were reported to not be illuminated when the ballast
train was approaching. Also contributing to the incident was the fact that no warning devices
were placed on the track in accordance with ARTC’s Network Rule ANTR 416 Disabled
Trains when the regulator ran out of fuel.
The investigation also found shortfalls in a number of supervisory, management and
protection practices employed by the work groups.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 118
Occurrence details
Event description: Collision between two ballast trains.
Type of operation: Track maintenance
Fatalities nil Injuries: 4
Occurrence Classification Collision Yard collision
Between trains
Individual actions
Findings Person type Activity type Error/Violation type
The collision of ballast train 6M21 with the disabled ballast
regulating machine, and the subsequent derailment of the
leading wagon, is attributable to ineffective communication
between safety critical staff about the location of the
disabled ballast regulator.
Infrastructure
maintainers
Communicating Error
No protection was placed on the track in accordance with
ARTC Network Rule ANTR 416 Disabled Trains when the
regulator ran out of fuel.
Infrastructure
maintainers
Preparation and
planning
Error
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
Overreliance was placed on the direction lights on the
regulator to indicate its stationary presence and provide
sufficient warning of an obstruction on the track, and these
lights were reported not to be illuminated when the ballast
train was approaching.
Physical
environment
Lighting/visibility On-train operations
Despite being informed that the regulator had run out of
fuel, the Traffic Officer/PO and the PO did not consider the
vehicle to be disabled in accordance with the definition
contained within the Glossary of the ARTC Network Rules
and Procedures. In the absence of any controlling rules or
procedures for disabled vehicles in worksites, adequate
vehicle separation and protection was not provided.
Further, there was an understanding by the Traffic
Officer/PO that, because the regulator had run out of fuel
within a worksite, it did not require protection in
accordance with ARTC Network Rules ANTR 400 and
ANTR 416.
Procedures Absent
procedure
Infrastructure
construction and
maintenance
The LS Rail Worksite Supervisor did not consider the risks
and consequences of the regulator becoming disabled in
the section away from fuel access points despite being
informed that it was low on fuel at the commencement of
the shift.
People
management
Job/task design Infrastructure
construction and
maintenance
The Traffic Officer/PO and the PO did not review or
undertake another risk assessment despite the changes in
risk when the regulator became disabled.
People
management
Job/task design Infrastructure
construction and
maintenance
The PO did not review or undertake another risk
assessment when the plough van was removed from the
ballast train.
People
management
Job/task design Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 119
The track tamper and regulator were effectively operating
as a worksite within a worksite. However, this was not
recorded on any worksite documentation; nor were the LS
Rail team signing onto the pre-work briefing forms at the
main site office.
Social
environment
Norms and
values
Infrastructure
construction and
maintenance
The Pilot did not direct the movement of the train in
accordance with ARTC Network Rule ANTR 424 and
SWMS TRA-027. Further, he was unaware of the speed
requirements in SWMS TRA-027 because he had not
been trained in ARTC’s Ballast Train Unloading
Awareness Training package and a copy of the SWMS
was not available on site.
Training and
assessment
Initial training Infrastructure
construction and
maintenance
No instructions or procedures had been developed for
lengthy propelling movements.
Procedures Absent
procedures
Infrastructure
construction and
maintenance
Environmental conditions and inadequate personal
protective equipment influenced the position taken by the
Pilot when directing the train.
Physical
environment
Weather-related
factors
Infrastructure
construction and
maintenance
Communications used at the worksite were not clear and
concise and, particularly post-incident, did not comply with
ARTC Network Rule ANGE 204, Network Procedure
ANPR 721 and the ARTC Incident Management Manual
TA44.
Knowledge,
skills and
experience
Communication
skills
Infrastructure
construction and
maintenance
The LS Rail pre-work briefing forms were photocopies
which were not uniquely numbered and did not follow
document control procedures. There was no reference to
any SWMSs on the forms and there were no hazards or
controls identified for disabled rail vehicles inside the
worksite. Further, the hazards and controls that were listed
were the same for both day and night shifts.
Procedures Clarity Infrastructure
construction and
maintenance
The pre-work briefing form compiled by the Protection
Officer at the main site office was deficient as it made no
reference to any SWMSs; nor were any of these
documents available at the worksite. Further, the hazards
of disabled rail vehicles, partially or unevenly loaded
wagons, propelling movement speeds between worksites
and communications failure between the Pilot and
locomotive crew were not identified and recorded on the
form; nor was the fact that another worksite was effectively
operating within the worksite.
Procedures Clarity Infrastructure
construction and
maintenance
The regulator was not carrying any emergency equipment
as listed in Section 9 of the TOC Manual and there was no
designated secure storage space on the vehicle.
Equipment, plant
and
infrastructure
Absent
equipment
On-train operations
The wagon upon which the ballasting team was riding was
not fitted with an emergency valve to apply the brakes on
the train. Because of this, the Pilot had to alert the
locomotive crew by radio to stop the train when the
regulator came into view.
Equipment, plant
and
infrastructure
Absent
equipment
On-train operations
There were no apparent defects on the lighting system of
the regulator. However, at least two possibilities existed
within the system for the lights to cease working without
intervention of the operator, neither of which was
recognised by the operator.
Equipment, plant
and
infrastructure
Functionality On-train operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 120
45. Summit Tank – Safeworking incident – 17 July 2012
Shortly after 2.00pm three workers commenced an inspection of a rail viaduct located in the
section between Summit Tank and Dombarton on the Unanderra to Moss Vale Branch line.
This was one of several site inspections which had been organised and supervised by an
Australian Rail Track Corporation (ARTC) structures manager to allow two contractors to
familiarise themselves with site conditions so that they could quote on the works required to
effect repairs to various bridges, viaducts and other rail structures. When it was necessary
during the site inspections, the Structures Manager also performed the duties of Protection
Officer.
During the inspection of the viaduct, the contractors
became concerned about the apparent structural
damage to the first pier at the Country end of the
viaduct and explained their need to examine the
damage from track level. Shortly afterwards, they
walked up onto the viaduct and along the walkway
immediately beside the track for approximately 10m until they were directly above the
damaged pier. The ARTC structures manager followed the two contractors up onto the
walkway.
At approximately 1448, Port Kembla-bound Pacific National bulk freight service 2928N
approached the viaduct from the Country end while the three workers were on the viaduct
directly ahead of it. When the train driver saw them on the
viaduct, he immediately blew the horn and applied the
brakes. On becoming aware of the train, the three
workers turned and, seeing the train approaching,
immediately moved quickly towards the Country end of
the viaduct (towards the oncoming train). All three men
were able to step to safety clear of the end of the viaduct
with the train approximately 5m from them. No one was injured in the incident.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 121
Occurrence details
Event description: Near miss with track maintenance workers on viaduct.
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Safeworking Rule or
procedure breach
Track work procedure/rule breach
Individual actions
Findings Person type Activity type Error/Violation type
The Protection Officer was required to combine the
primary responsibilities of his Structures Manager position
and those of protection officer while supervising the
viaduct engineering inspection. As inspecting the structure
from other than below the deck was not anticipated, no
worksite protection planning was undertaken. When the
circumstances changed and the group needed to move
onto the viaduct and into the danger zone, the Protection
Officer made no worksite protection arrangements.
Infrastructure
maintainers
Preparation
and planning
Error
Local Condition/Organisational factor
Findings Local
Condition/Organi
sational factor
Keywords Functional area
All three members of the group appear to have been
focused on the inspection of the viaduct pier and oblivious
to the potential danger of their situation.
Task demands Distractions Infrastructure
construction and
maintenance
The Protection Officer felt there were times where there
was an unreasonable degree of pressure on him to
manage contractors, which he found particularly difficult,
while having to concurrently perform non-core functions
such as those of protection officer and project manager.
He felt this was the case on the day of the incident.
Social
environment
Norms and
values
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 122
46. Boggabri – Coal train derailment – 28 Nov 2012
At approximately 2.13pm a Pacific National coal service NB942 derailed the last six wagons
on the Coxs Creek Bridge near the township of Boggabri. NB942 consisted of 71 loaded coal
wagons which were being hauled by three locomotives at the front of the train. The train was
travelling from Narrabri Coal to Port Waratah near Newcastle where it was to be unloaded.
The majority of the train had passed over the Coxs
Creek Bridge when it experienced an automatic
emergency application of the train’s brakes. Upon
investigation, the crew found the last six wagons had
derailed, with five of the six toppling off the bridge and
spilling their payload. The last (sixth) of the derailed
wagons remained in a precarious upright position on the bridge. There were no personnel
injured as a result of the derailment. All of the derailed wagons were damaged beyond
economical repair. The bridge was extensively damaged with 130 metres of track destroyed
as a result of the incident. The line was reopened to rail traffic on 20 December 2012
following major partial reconstruction of the bridge.
The wagons derailed due to a lateral misalignment which formed under one or more of the
last six vehicles in the consist of train NB942.
The lateral misalignment resulted from track not being
able to contain a build up of excessive compressive
forces in the rail primarily due to: errors being made
completing track stability calculations, creep in the rails
not being controlled, the track infrastructure being in
generally poor and variable condition, inappropriate lifting
of a speed restriction, and the track leading up to the bridge not being maintained to the
applicable engineering standards.
The bridge was repaired and normal traffic resumed within a month of the derailment. The
Australian Rail Track Corporation (ARTC) subsequently completed a planned project to
significantly upgrade and strengthen the track between Gunnedah and Turrawan (near
Narrabri).
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 123
Occurrence details
Event description: Derailment of a freight train.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
Pacific National coal service NB942 derailed as a buckle
formed in the track under it as it traversed the track in the
vicinity of kilometrage 513.002. The buckle resulted from
track not being able to contain a build-up of excessive
compressive forces in the rail.
Infrastructure Track Deformation Maintenance
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
Incorrect calculation of track stability which masked a
significant deficiency that would have alerted track
maintainers to a situation requiring ‘immediate attention or
evasive action’.
Knowledge, skills
and experience
Normal
operations
knowledge
and skills
Infrastructure
construction and
maintenance
With the exception of one incorrect adjustment, creep was
allowed to remain uncontrolled.
Organisation
management
Monitoring,
review and
validation
Infrastructure
construction and
maintenance
With the exception of the bridge, the track infrastructure
was in generally poor and variable condition.
Organisation
management
Monitoring,
review and
validation
Infrastructure
construction and
maintenance
The track leading up to the bridge abutment not being
managed as a bunching point.
Organisation
management
Monitoring,
review and
validation
Infrastructure
construction and
maintenance
The lifting of a speed restriction in association with spot
tamping of the track nearby.
Knowledge, skills
and experience
Normal
operations
knowledge
and skills
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 124
47. Gulgong – Wagon structural failure – 5 Dec 2012
At 3.25am at Gulgong in NSW a train crew conducting a roll by inspection noticed that a
wagon had sagged in the middle and was almost dragging on the ground. The wagon was
one of a fleet of 100 skeletal type container wagons belonging to QUBE Logistics (Rail) Pty
Ltd, all of which had entered service within the previous 12 months.
The immediate cause of the wagon sagging was the
failure of a weld that ran transversely across the centre
of the underside of the wagon’s main structural beam.
The bending forces applied to the welded joint then
transferred to the side members (sills) which gradually
split, from the location of the failed welded joint,
upwards to the top member of the beam.
A second wagon on the same train was found to have welding defects in the same joint as
the failed wagon. Both welds were performed by the same welder on consecutive days.
Inspections during manufacture, including ultrasonic
testing in the case of the joint that failed, did not identify
any defects, nor did visual inspections carried out during
routine maintenance after the wagons entered service.
The investigation found that the wagon manufacturer,
located in the United States of America, used a welded joint that may not have complied with
relevant Australian Standards. Also, the manufacturer did not provide accurate instructions
for performing the weld to its welding personnel; did not have complete records in relation to
welder experience and qualifications; and did not detect flaws present in the failed wagon, or
some other wagons, through testing or inspection during the manufacturing process.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 125
Occurrence details
Event description: Wagon structural failure.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Rolling stock irregularity Other irregularity - wagon
Individual actions Findings Person type Activity type Error/Violation
type
The welding of the joint had not been performed
proficiently. The weld had not penetrated through to or
fused with the backing bar and the weld lacked side fusion
with the steel plates.
Rolling stock maintainer Operating
equipment
Error
Technical failure
Findings Failed component Failure
mechanism
Failure origin
The structural failure of container wagon SQDY 00060G
was due to the failure of the welded joint in the centre of
the bottom member of the wagon’s spine.
Rolling stock – Car-
body
Fracture Manufacture
Local Condition/Organisational factor
Findings Local
Condition/Organisati
onal factor
Keywords Functional area
The welding process specified by ARI had not been
modified for the thicker plate used and the gap between
the plates had not been increased commensurate with the
increased thickness of plate. This made the weld
technically difficult for the welder.
People management Job/task
design
Rolling stock
construction and
maintenance
The defective welded joint had not been detected during
inspections, including Ultrasonic Testing, carried out as
part of the manufacturing process.
Knowledge, skills
and experience
Normal
operations
Rolling stock
construction and
maintenance
The defective welded joint was not detected during routine
maintenance inspections after the wagon had entered
service.
Knowledge, skills
and experience
Normal
operations
Rolling stock
construction and
maintenance
The joint was of a square butt welded configuration. This
type of joint is technically more difficult to perform than a
‘V’ type joint.
Equipment, plant
and infrastructure
Other -
design
Rolling stock
construction and
maintenance
The design of the wagon placed a transverse welded joint
in the centre of the bottom member of the central spine. As
this is within a region of relatively high stress, it is not
considered to be an optimum location for such a joint
Equipment, plant
and infrastructure
Other -
design
Rolling stock
construction and
maintenance
ARI was unable to provide records to demonstrate that all
the welders who performed the welds were ‘qualified’ or
otherwise proficient in the execution of this particular weld.
Organisation
management
Information
management
Rolling stock
construction and
maintenance
The standard of the final product was poor as evidenced
by flame cut plate edges, poor weld finish, undercut welds
and gaps present between plate and backing bar.
Knowledge, skills
and experience
Normal
operations
Rolling stock
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 126
48. Rennie – Derailment – 3 January 2013
On 3 January 2013, El Zorro loaded grain service 5CM7 derailed 10 of its 40 wagons just
south of the township of Rennie while en route from Oaklands in southern New South Wales
to Melbourne via Benalla in Victoria. All 10 derailed wagons were extensively damaged and
approximately 260 metres of track infrastructure was destroyed. No injuries were reported as
a result of the derailment and none of the contents from the derailed wagons was spilt.
The investigation found that the train derailed when it
traversed a buckle in the track. The buckle was due to
the build-up of excessive compressive stress resulting
from rail creep which was exacerbated by high
temperatures on the day of the incident and the week
leading up to it.
There was evidence that rail creep had persisted over a number of years, that track
geometry was progressively deteriorating, and that sleepers and fasteners were becoming
life-expired. Despite a number of indicators that the track
was deteriorating, preventative maintenance had not been
initiated. Additionally, there was no extant document
providing guidance as to how to respond to a situation
where a combination of track parameters on this line had
reached a limit that must not be exceeded.
As had been the case in previous investigations, difficulties were encountered in obtaining
downloads from locomotive data loggers.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 127
Occurrence details
Event description: Freight train derailment.
Type of operation: Freight
Fatalities nil Injuries: nil
Occurrence Classification Derailment On running line
Technical failure
Findings Failed component Failure
mechanism
Failure origin
El Zorro grain service 5CM7 derailed when the train
traversed a buckle in the track at 289.852 km. The track
buckle was likely to have been caused primarily by rail
creep that had accumulated in the last three years,
producing excessive compressive (or buckling) stress
during periods of high temperature. The ability of the track
structure to resist buckling had been progressively
diminished by: deteriorating track geometry as measured
by the Track Condition Index (TCI); and poor sleepers with
loose fastenings not holding the rail to the sleepers,
thereby compromising the rigidity of the track structure.
Infrastructure
Track
Deformation Maintenance
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
ARTC does not have a standard or guideline to assist track
managers in responding to an unfavourable aggregate of
individual track geometry measurements, as expressed by
the TCI.
Procedures Absent
procedure
Infrastructure
construction and
maintenance
In the absence of mandatory detailed inspection of factors
that govern track stability on Light Weight Lines, ARTC’s
governance and performance monitoring arrangements did
not provide a level of oversight of track stability
management sufficient to detect and correct the sort of
deficiencies that were discovered to exist during this
investigation.
Organisational
management
Information
management
Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 128
49. Moree – Level crossing collision – 21 May 2013
At 7.20am on Tuesday 21 May 2013, track measuring and recording train NK81 travelling
north from Narrabri towards Moree collided with the rear left corner of a utility travelling west
across a railway crossing on Tapscott Road, known locally as Dunavant’s Crossing. The
driver of the utility was uninjured in the collision and drove from the scene after speaking to
the train crew.
The train, operated by Pacific National for the
Australian Rail Track Corporation, consisted of three
specially equipped carriages instrumented to record a
range of track geometry parameters. It was hauled by
PN locomotives 48138 and 48104, and was travelling
at approximately 96 km/h. The railway crossing was
passively protected by stop signs and associated roadside signs.
The driver of the utility stopped at the stop sign on the eastern side of the crossing before
proceeding across the crossing into the path of the approaching train. Although he believes
he did look out for trains, he could not explain why he did
not see the train. The most likely explanation is that it was
a case of inattentional blindness, the phenomenon of ‘look
but did not see’.
There were no matters directly associated with the
incident that warranted a recommendation to any party
involved. However, in the course of the investigation, it was noted that the required interface
agreement for the crossing had not been finalised between the Moree Plains Shire Council
and the Australian Rail Track Corporation.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 129
Occurrence details
Event description: Level crossing collision between road motor vehicle and freight train.
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Level crossing occurrence Collision with road vehicle
At crossing with passive warning devices: Stop signs
Individual actions
Findings Person type Activity type Error/Violation
type
The collision occurred as a result of the utility driver, after
stopping at the crossing, proceeding across without first
giving way to the approaching train.
Light passenger
vehicle driver
Monitoring and
checking
Error
Local Condition/Organisational factor
Findings Local
Condition/Organis
ational factor
Keywords Functional area
It is possible that the utility driver either did not look in the
direction of the train or, due to inattentional blindness,
looked but failed to see the train.
Personal factors
Pre-occupation
Road
environment
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 130
50. East Maitland – Safeworking incident – 27 November 2013
At about 2.15pm on 27 November 2013, a group of five rail safety workers was engaged in
manually removing rubbish and surplus materials from a track near East Maitland station.
They were exposed to the danger of being hit by a train when the Protection Officer’s view of
an approaching train was obscured by a train passing on the adjacent track. The Protection
Officer (PO) had not anticipated such an eventuality in planning the worksite protection.
When the PO (acting as a lookout) saw the
approaching train, he gave warning using a handheld
air horn. The workers responded and were able to
move to a safe place just before the approaching train
reached their location. The PO had recently been
assessed and certified as competent by the Centre for
Excellence in Rail Training which used documentation provided by the Australian Rail Track
Corporation (ARTC) for the on-the-job training component. The safeworking incident
occurred on his second day of work following certification.
The investigation identified deficiencies in the process used by training providers to establish
current competency in vocational rail safety functions. Leighton Contractors Pty Limited, who
were undertaking the work under contract to the ARTC,
had recognised this and introduced a process to satisfy
themselves that all safeworking personnel, whether direct
employees or contractors, were suitably qualified and
experienced to carry out the tasks to which they were
assigned. However, the PO’s employer, Momentum Rail,
had no such process, instead relying on the fact that personnel had been issued with
certificates of competency as evidenced by their rail safety worker’s competency cards.
Leighton Contractors were unaware of this and accepted the PO to be in charge of the
worksite. In response to the incident, Leighton Contactors tightened their procedures to
ensure that supplied contractor personnel met their standards.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 131
Occurrence details
Event description: Near miss with workers.
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Safeworking Rule or
procedure breach
Track work procedure/rule breach
Individual actions Findings Person type Activity type Error/Violation type
The Momentum Rail PO had not previously experienced a
loss of sighting distance due to the passage of rail traffic
on an adjacent track and had not taken it into account
when planning his worksite protection.
Infrastructure
maintainers
Preparation
and planning
Error
The Leighton’s’ site supervisor, a protection officer with 39
years experience, did not question the work method,
specifically continuing to work while the Up train passed.
Infrastructure
maintainers
Monitoring and
checking
Error
Local Condition/Organisational factor Findings Local
Condition/Organi
sational factor
Keywords Functional area
The training and assessment leading to the issue of the
PO’s certification had not identified this gap in his
experience and therefore his competence.
Training and
assessment
Currency
tracking
Infrastructure
construction and
maintenance
Leightons made an assumption that their supplier,
Momentum Rail, had a system in place to ensure that the
PO provided for the job was suitably qualified, experienced
and competent, beyond being the holder of an appropriate
certificate of competency, to undertake the required tasks
at the worksite.
Organisational
management
Contractor
management
Infrastructure
construction and
maintenance
The request from Leightons for the supply of a PO at the
same location on 14 and 15 November had included the
following passage: “It is important that the candidate has
knowledge of the area as tight track curvature and high
track speeds exist”. This requirement was not reiterated in
the request for the supply of a PO for 26 to 28 November.
Organisational
management
Contractor
management
Infrastructure
construction and
maintenance
The planned work was not reviewed during one of
Leighton’s weekly safeworking meetings and so the
opportunity to review the method of work and stipulate
minimum safeworking requirements was lost.
Organisational
management
Risk and/or
change
management
Infrastructure
construction and
maintenance
The on-job training provided to the PO was inadequate.
Although the PO’s on-job workbook was signed off to
confirm that the PO had demonstrated knowledge in a
wide range of tasks and procedures, the reality was
different.
Training and
assessment
Initial training Infrastructure
construction and
maintenance
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 132
51. Moss Vale – Safeworking incident – 21 December 2013
At approximately 10.14pm on 21 December 2013 near Moss Vale station, passenger service
ST21 travelling on the Down Main line passed stationary Pacific National freight service
6AB6 on the Up Main line. This alerted the crew of 6AB6 to the fact that worksite protection
had not been in place for the co-driver while he was investigating the report of a warm axle
on one of the train’s wagons.
The protection was sought by the driver of 6AB6 and
was understood to have been implemented by the
network controller located at the Australian Rail Track
Corporation’s Network Control Centre South at Junee.
However, when the network controller was about to
implement protection arrangements, he was distracted
by a personal phone call which resulted in him moving away from his control panel. During
his absence, he was not relieved at the panel and, on return, took no further action to
implement the worksite protection.
Even though controlled signal blocking was not implemented, the network controller told the
crew that it had. In addition to the distraction, the investigation found that the network
controller’s performance may have been fatigue-impaired. He had been working for 9 hours
of a 10 hour shift without a scheduled break. It was normal practice in the control centre not
to have scheduled breaks.
The investigation also identified inadequacies in the use of verbal communication protocols,
post-incident drug and alcohol testing and the train driver’s adherence to procedures in the
implementation of controlled signal blocking.
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 133
Occurrence details
Event description: Near miss with workers.
Type of operation: Track maintenance
Fatalities nil Injuries: nil
Occurrence Classification Safeworking Rule or procedure breach Track work procedure/rule breach
Individual actions Findings Person type Activity type Error/Violation type
The network controller working the Main South ‘A’ Panel in
the Network Control Centre South at Junee did not apply
controlled signal blocking to the Down Main line as
requested by the driver of 6AB6.
Network controller Operating
Equipment
Error
The driver of 6AB6 did not confirm that there were no trains
already in the section; he did not confirm the signal numbers
and there was no read back when he requested controlled
signal blocking as required by the Network Rules and
Procedures.
Train crew Communicating Error
Local Condition/Organisational factor Findings Local
Condition/Organisati
onal factor
Keywords Functional area
The network controller was distracted by a personal phone
call and then a visit by a family member at the Network
Control Centre South at a critical time during the application
of controlled signal blocking. There was no relief staff
provided to cover his absence from the panel.
Task demands Distraction Off-train operations
It is likely that the performance of the network controller may
have been degraded due to fatigue-impairment. This
likelihood was due to the length of time on task and the lack
of any scheduled rest breaks.
Personal factors Fatigue Off-train operations
Communication between the Control Centre and the train
crew lacked the use of standard terms required by the
network procedures. In general, transmissions were informal
and conversational rather than operationally formal
according to prevailing communications protocols.
Social environment Norms and
values
Off-train operations
The requirements for Drug and Alcohol testing were not
followed in that the network controller was not drug tested
following the incident and the train crew were not tested for
the presence of drugs and alcohol.
Organisational
management
Compliance Off-train operations
The initial incident report by ARTC did not include critical
information about the safeworking incident.
Organisational
management
Compliance Off-train operations
The recertification process of the network controller did not
include any reference to controlled signal blocking.
Organisational
management
Compliance Off-train operations
The network controller started his shift at 0700 on 22
December 2013 after a short turnaround time since he
finished his last shift the previous evening at 2300.
Organisational
management
Business
planning
Off-train operations
There are no designated locations where train crew are able
to conduct axle bearing inspections after an axle alert is
triggered by a trackside detector.
Equipment, plant and
infrastructure
Absent
infrastructure
Off-train operations
OTSI Rail Safety Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 134
Appendix A: Contributing factors framework overview
Individual/team actions Person Type Activity Type Error/violation type
Infrastructure maintainers Preparation and planning Error
Network Controllers Operating equipment Violation
Rolling stock maintainers Communicating Unknown error/violation
Train crew Monitoring and checking
Station crew Handover/takeover
Terminal staff Other activity type
Light Passenger vehicle drivers
Heavy freight vehicle drivers
Emergency service staff
Technical failure mechanism Failed Component Failure Mechanism Failure origin
Rolling stock – bogies, braking, car-body,
coupler/drawgear, load restraint, on board traction
system, on board train protection system. Other.
Corrosion Design
Infrastructure – bridge, building, drain/flood
mitigation, lineside rolling stock fault detection
system, overhead power system, road-rail interface,
switches crossings, track, track protection device,
track support, tunnels, other.
Deformation Manufacture
Signalling and communications – communication
systems, control interface equipment, interlocking
system, traffic control, train detection system,
wayside signalling equipment, other.
Electrical Installation
Other – other vehicles Fracture Operation
Mechanical Maintenance
Software/firmware Decommissioning
Wear Unknown failure origin
Other failure mechanism
Unknown failure mechanism
Local conditions and organisational factors Local Conditions Organisational Factors Functional Area
Personal factors Procedures Freight handling
Knowledge, skills and experience Training and assessment Infrastructure construction &
maintenance
Task demands Equipment, plant and
infrastructure
Off-train operations
Physical Environment People management On-train operations
Social environment Organisational management Passenger management
External organisational
influences
Rolling stock construction &
maintenance
Road environment
Emergency Management
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 135
Appendix B: Contributing factors framework analysis
Individual/team action
Person
Activity Error/violation No. Report ID number
Infrastructure maintainer Communicating Error 3 33,35,44
Infrastructure maintainer Monitoring and checking Error 4 21,30,35,50
Infrastructure maintainer Monitoring and checking Violation 1 31
Infrastructure maintainer Operating equipment Error 2 12,17
Infrastructure maintainer Preparation and planning Error 4 33,44,45,50
Light passenger vehicle driver Monitoring and checking Error 3 34,39,49
Light passenger vehicle driver Monitoring and checking Unknown 3 1,6,43
Network controller Communicating Error 3 28,33,42
Network controller Monitoring and checking Error 3 7,33,41
Network controller Operating Equipment Error 1 51
Network controller Preparation and planning Error 1 14
Rolling stock maintainers Operating equipment Error 1 47
Terminal staff Monitoring and checking Unknown 1 25
Terminal staff Operating equipment Error 1 38
Terminal staff Operating equipment Violation 1 2
Train crew Communicating Error 3 7,28,51
Train crew Monitoring and checking Error 6 10,14,23,24,29,42
Train crew Operating equipment Error 8 11,15,25,26,36,37
Technical failure
Component
Mechanism Origin No. Report ID number
Infrastructure - Track Deformation Maintenance 10 3,5,18,19,20,22,25,46,
48
Infrastructure - Track Fracture Maintenance 1 16
Infrastructure - Track Other Installation/
commissioning
1 8
Rolling stock - Bogies Fracture Unknown 2 4,40
Rolling stock - Bogies Wear Installation/
commissioning
1 9
Rolling stock – Braking system Mechanical discontinuity Design 1 27
Rolling stock – Car body Mechanical discontinuity Operation 1 32
Rolling stock –Car-body Fracture Manufacture 1 47
Rolling stock- Train Detection
System
Software/
firmware anomaly
Design 1 29
Signalling and Communications
item: Control interface equipment
Other Installation/
commissioning
1 13
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 136
Local Condition/Organisational
Factor
Keywords No. Report ID number
Equipment, plant & infrastructure Absent equipment, plant & infrastructure 12 7,12,14,27,37,39,40,41,
42, 44,51
Equipment, plant & infrastructure Availability 4 1,6,9
Equipment, plant & infrastructure Control input devices design 1 40
Equipment, plant & infrastructure Functionality 15 1,2,6,15,17,22,25,26,27
,29,31,36,40,44
Equipment, plant & infrastructure Infrastructure design 6 1,14,23,24,42
Equipment, plant & infrastructure Other - design 2 47
Equipment, plant & infrastructure Reliability 1 35
Equipment, plant & infrastructure Signage 3 6,39,43
External organisational influences Industry standards or guidance 1 36
External organisational influences Regulatory activities 1 3
Knowledge, skills & experience Abnormal/emergency operations knowledge &
skills
5 1,3,6,7,15
Knowledge, skills & experience Communication skills 11 21,22,28,31,33,35,37,4
1,44
Knowledge, skills & experience Normal operations knowledge & skills 19 10,11,18,20,26,27,32,3
7,41,46,47
Knowledge, skills & experience Task experience 7 7,23,26,28
Knowledge, skills & experience Teamwork skills 2 25,37
Organisational management Business planning and asset/ resource
management
3 5,8,51
Organisational management Competence of senior personnel 2 11,37
Organisational management Communication and consultation process 3 20,38
Organisational management Compliance 3 51
Organisational management Contractor/ interface management 6 8,25,30,50
Organisational management Interface management 1 3
Organisational management Information management 10 8,10,11,30,33,36,41,47,
48
Organisational management Monitoring, review and validation 21 3,5,11,16,17,18,19,20,2
2,33,36, 46
Organisational management Policy 4 1,6,8,11
Organisational management Risk and/or change management 23 2,3,5,8,11,16,17,18,24,
31,36,38,50
People management Fitness for duty monitoring 1 11
People management Job/task design 5 31,44,47
People management Rostering/ scheduling 2 14
People management Supervision 2 30,33
Personal factors Fatigue/alertness 8 10,11,
21,23,24,33,37,51
Personal factors Health-related condition 1 25
Personal factors Motivation/attitude 4 10,19,25
Personal factors Preoccupation 2 24,49
Personal factors Stress/anxiety 1 24
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 137
Physical environment Lighting/visibility 8 10,17,21,29,42,43,44
Physical environment Noise 2 17,21
Physical environment Other –Unstable surface 1 12
Physical environment Temperature/
Humidity
2 20,25
Physical environment Weather-related factors 2 15,44
Procedures Absent procedure 13 2,7,12,18,19,20,21,36,3
7,38,44,48
Procedures Accuracy/clarity 17 7,9,12,18,21,26,33,35,3
7,40,44
Procedures Availability/
accessibility
1 41
Social environment Norms and values 5 37,44,45,51
Social environment Peer pressure 2 31,42
Task demands Distraction 12 11,17,24,26,28,29,33,3
5,37,43,45,51
Task demands High workload 3 7,28,39
Task demands Other- familiarity 1 21
Task demands Time pressure 4 12,18,31,35
Training and assessment Competency assessment 2 11,30
Training and assessment Currency tracking 2 30,50
Training and assessment Initial training 5 28,33,38,44,50
Training and assessment Ongoing training 2 24,33
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 138
Appendix C: OTSI rail investigation reports with keywords
No. Date Location Event Keywords
1 4/05/04 Baan Baa Passenger train collision with
car at level crossing
Collision; Emergency operations
knowledge & skills; Equipment
availability; Equipment functionality;
Fatality; Infrastructure design; Level
Crossing; Policy
2 1/07/04 Port Botany Shunter killed after falling from
flat top container wagon
Absent procedure; Collision, Equipment
functionality; Fatality; Risk Management
3 22/12/04 Bethungra Derailment of a freight train Abnormal/emergency operations
knowledge & skills; Deformation;
Derailment; Maintenance; Interface
management; Monitoring, review and
validation; Regulatory activities; Risk
Management; Track
4 1-7/03/05
Wauchope &
Lapstone
Derailment of freight trains Axle; Derailment; Fracture; Screwed
journal
5 6/04/05 Old Burren Derailment of a freight train Business planning and asset/ resource
management; Deformation; Derailment;
Maintenance; Monitoring, review and
validation; Risk/change management;
Track
6 31/05/05 Grawlin Plains Freight train collision with car at
level crossing
Emergency operations knowledge &
skills; Equipment Availability; Equipment
Functionality; Fatality; Level Crossing;
Policy; Signage
7 20/08/05 Bloomfield Opposing movement between
two freight trains
Abnormal/emergency operations
knowledge & skills; Absent equipment,
plant & infrastructure; Absent procedure;
High workload; Opposing movement;
Procedure Accuracy/clarity; Task
experience
8 2005 NSW A systemic investigation into
the installation of steel sleepers
Business planning & asset/ resource
management; Contractor/ interface
management; Derailment; Information
management; Installation; Policy;
Risk/change management; Track
9 16/10/05 Conoble Derailment of a freight train Bogie; Derailment; Equipment Availability;
Installation; Procedure – Clarity; Wear
10 4/11/05 Lidcombe SPAD and derailment of a
freight train
Catchpoints; Derailment;
Fatigue/alertness; Information
management; Motivation/ attitude; Normal
operations knowledge & skills; SPAD;
Visibility
11 15/04/06 Ariah Park Shunter killed crushed between
rolling stock
Collision; Competency assessment;
Competence of senior personnel;
Distraction; Fatality ; Fatigue/ alertness;
Fitness for duty monitoring; Information
management; Monitoring, review and
validation; Normal operations knowledge
and skill; Policy; Risk/ change
management
12 22/05/06 Baan Baa Track worker killed after falling Absent equipment; Absent procedure;
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 139
from ballast wagon Procedure Accuracy/adequacy; Fatality;
Time pressure
13 30/08/06 Central to
Town Hall
tunnel
Self harm fatality in rail tunnel Fatality; Suspected suicide
14 2/09/06 North
Strathfield
SPAD and opposing movement Absent equipment, plant & infrastructure;
Infrastructure design; Opposing
movement; Rostering/ scheduling; SPAD
15 6/09/06 Thirroul SPAD and derailment of a
passenger train
Abnormal/emergency operations
knowledge and skills; Catchpoints;
Derailment; Functionality; SPAD
Weather-related factors
16 1/10/06 Nyngan Derailment of a freight train Derailment; Fracture; Maintenance;
Monitoring, review & validation; Risk
change management; Track
17 7/11/06 Sandgate Track work injury Collision; Equipment Functionality; High
Workload; Monitoring, review & validation;
Noise; Risk/ change management
18 11/0107 Leeton Derailment of a freight train Absent procedures; Deformation;
Derailment; Maintenance; Monitoring,
review & validation; Normal operations
knowledge and skills; Procedures
accuracy/clarity; Risk/ change
management; Time pressure; Track
19 14/01/07 Euabalong
west
Derailment of a freight train Absent procedures; Deformation;
Derailment; Maintenance; Monitoring,
review & validation; Motivation/attitude;
Track
20 8/0207 Connemarra Derailment of a freight train Absent procedures; Communication and
consultation process; Deformation;
Derailment; Maintenance; Monitoring,
review & validation; Normal operations
knowledge and skills;
Temperature/humidity; Track
21 16/07/07 Singleton Track worker fatalities Absent procedures; Communication ;
Collision; Familiarity; Fatigue/alertness;
Fatality; Lighting/visibility; Noise
Procedures Accuracy
22 29/0108 Breeza Derailment of a freight train Communication; Derailment; Deformation;
Maintenance; Monitoring, review &
validation; Equipment Functionality; Track
23 7/109 Homebush SPAD and derailment of a
passenger train
Catchpoints; Derailment; SPAD;
Fatigue/alertness; Infrastructure design;
Task experience
24 24/01/09 Unanderra SPAD and derailment of a
passenger train
Catchpoints; Derailment; SPAD;
Distractions; Fatigue/alertness;
Infrastructure design; Preoccupation;
Ongoing training; Stress/anxiety
25 8/0209 Peak Hill Derailment of a freight train Derailment; Track; Deformation;
Maintenance; Contractor/ interface
management; Equipment Functionality;
Health-related condition;
Motivation/attitude; Teamwork skills
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 140
26 10/0509 Goobang SPAD and collision Collision; Distractions; Equipment
Functionality Normal operations
knowledge and skill; Procedures
Accuracy/clarity; Task experience; SPAD
27 28/07/09 Temora Runaway wagon Absent equipment, Equipment
Functionality; Normal operations
knowledge and skills; Plant and
infrastructure; Runaway
28 28/10/09 Glenlee Near miss with train crew Communications skills; Distractions; High
workload; Initial training; Task experience;
Safeworking
29 27/02/10 Darling Park Collision between two Monorail
trains
Collision; Communications skills; Design;
Distractions; Equipment Functionality
Lighting/ visibility; Software/firmware
anomaly ; Train Detection System
30 13/03/10 Whittingham Derailment of a freight train Contractor/ interface management ;
Derailment; Points; Information
management; Supervision; Training
Competency assessment; Training
Currency tracking
31 1/04/10 Strathfield Near miss with maintenance
staff
Communication skills; Equipment
Functionality Job/task design; Peer
pressure; Risk/change management;
Safeworking; Time pressure
32 11/04/10 Woy Woy Container gate detached Collision, Normal operations knowledge
and skills
33 13/04/10 Kogarah Track worker killed after being
struck by passenger train
Collision; Fatality; Communication skills;
Distraction; Fatigue/alertness; Information
management; Monitoring, review and
validation; Ongoing training; Procedures
Accuracy/Clarity; Supervision; Training
Initial training
34 1/09/10 Wee Waa Level Crossing Collision Fatality; Level Crossing
35 29/10/10 Bankstown Near miss with track workers Communication skills; Distraction;
Equipment Reliability; Procedures Clarity;
Safeworking; Time pressure
36 7/02/11 Unanderra Uncontrolled movement Absent procedures; Equipment
Functionality; Industry standards or
guidance ; Information management;
Monitoring review and validation; Risk
change management; SPAD,
37 1/04/11 Zig Zag railway Collision between a train and a
track vehicle
Absent equipment, Collision; plant &
infrastructure; Competence of senior
personnel; Communication skills;
Fatigue/alertness ; Normal operations
knowledge & skills; Teamwork skills
38 3 /05/11 Enfield yard Runaway Absent procedures; Communication and
consultation process, Derailment, Initial
training; Risk management; Runaway
39 2/09/11 Woy Woy Level crossing collision
passenger train and car
Absent equipment; High workload; Level
Crossing; Signage
40 23/11/11 Clifton Derailment of a freight train Absent equipment; Axle; Bogie; Control
input devices design; Derailment;
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 141
Functionality equipment ; Fracture;
Procedures Accuracy/adequacy
41 12/12/11 Unanderra Safeworking incident Absent equipment; Communication skills;
Information management ; Normal
operations knowledge and skills;
Procedures Availability/ Accessibility;
Safeworking
42 7/03/12 Gunnedah SPAD and opposing movement Absent plant; Infrastructure design;
Lighting/visibility; Opposing movement ;
Peer pressure; SPAD
43 4/05/12 Nundah Level crossing collision Fatality; Level Crossing; Distractions;
Lighting/visibility; Signage
44 18/05/12 Bengalla Ballast train collision Absent equipment ; Absent procedure;
Collision; Communication skills ;
Equipment Functionality; Initial training ;
Job/task design; Lighting/visibility; Norms
and values; Procedures Clarity; Weather-
related factors
45 17/07/12 Summit Tank Safeworking incident Distractions; Norms and values;
Safeworking
46 28/11/12 Boggabri Derailment of a freight train Deformation; Derailment; Maintenance;
Monitoring, review and validation; Normal
operations; Track
47 5/12/12 Gulgong Wagon structural failure Job/task design; Equipment design;
Information management; Normal
operations; Rolling stock
48 3 /01/13 Rennie Derailment of a freight train Absent procedure; Deformation;
Derailment; Maintenance; Information
management; Track
49 21/05/13 Moree Level crossing collision Level Crossing; Pre-occupation
50 27/11/13 East Maitland Safeworking incident Contractor management; Initial training;
Risk and/or change management;
Safeworking; Training Currency tracking
51 21/12/13 Moss Vale Safeworking incident Absent infrastructure; Business planning;
Compliance; Distraction; Fatigue; Norms
and values; Safeworking
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 142
Appendix D: Incident notification and classification
Incident Notification
The Rail Safety National Law requires notifiable occurrences to be reported. A notifiable
occurrence means an accident or incident associated with railway operation that has, or
could have, caused significant property damage, serious injury, death or that is, or is of a
class that is, prescribed by the national regulations to be a notifiable occurrence or class of
notifiable occurrence.
Incident Classification
Each notifiable occurrence can be classified according to the Office of National Rail Safety
Regulator Guideline: Classifying Notifiable Occurrences – Occurrence Classification–
Guideline (OC-G1) (ONRSR, 2012).
This was done for each of the OTSI rail investigations from 2004-2013 and the top event6
classification is listed below.
OC-G1 Occurrence Categories CATEGORY SUB-CATEGORY OTSI INVESTIGATION
Derailment 1.1 Running line 3. Bethungra 2004
4. Lapstone & Wauchope 2004
5. Old Burren 2005
8. Steel Sleepers 2005
9. Conoble 2005
10. Lidcombe 2005
15. Thirroul 2006
16. Nyngan 2006
18. Leeton 2007
19. Eubalong West 2007
20. Connemarra 2007
22. Breeza 2008
23. Homebush 2009
24. Unanderra 2009
25. Peak Hill 2009
30. Whittingham 2010
40. Clifton 2011
46. Boggabri 2012
48. Rennie 2013
1.2 Yard derailment 38. Enfield 2011
6 The top event is the event with the greatest adverse outcome. It is independent of the sequence
of events.
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 143
Collision 2.1 Running line collision 11. Ariah Park 2006
21. Singleton 2007
26. Goobang 2009
29. Darling Park 2010
32. Woy Woy 2010
33. Kogarah 2010
37. Zig Zag 2011
2.2 Yard collision 2. Port Botany 2004
17. Sandgate 2006
12. Baan Baa 2006
44. Bengalla 2012
Level crossing occurrence 3.1 Collision with road vehicle 1. Baan Baa 2004
6.Grawlin Plains 2005
34. Wee Waa 2010
39. Woy Woy 2011
43. Nundah 2012
49. Moree 2013
3.2 Collision with person
3.3 Level crossing equipment failure
3.4 Level crossing equipment damage
3.5 Near miss with road vehicle
3.6 Near miss with person
3.7 Other level crossing occurrence
Signal passed at danger 4.1 Driver misjudged 36. Unanderra 2011
4.2 Completely missed while running 14. North Strathfield 2006
42. Gunnedah 2012
4.3 Starting against signal
4.4 Signal restored as train approached
4.5 Other signal passed at danger
Proceed authority exceeded 5.1 Driver misjudged
5.2 Completely missed while running
5.3 Other proceed authority exceeded
Signalling and other proceed authority
systems irregularity
6.1 Wayside systems signal irregularity
6.2 In-cab signalling systems
irregularity
6.3 Token based systems irregularity
6.4 Communications based train
authority systems irregularity
6.5 Other Signalling and other proceed
authority systems irregularity
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 144
Slip, trip or fall 7.1 To/from train
7.2 Between platform and train
7.3 On train
7.4 On track
7.5 On platform/concourse
7.6 On/from escalator/lift
7.7 On/from stairs/ramps
7.8 From structure
7.9 Caught in train doors
7.10 Other slip trip fall
Load irregularity 8.1 Door open
8.2 Out of gauge
8.3 Load shift
8.4 Uneven distribution of load
8.5 Loose load fastening
8.6 Other load irregularity
Dangerous goods 9.1 On train
9.2 Off train
Safeworking rule or procedure breach 10.1 Wayside signalling system
procedure/rule breach
10.2 In-cab signalling system
procedure/rule breach
10.3 Token based system
procedure/rule breach
7. Bloomfield 2005
10.4 Communication based system
procedure/rule breach
10.5 Track work procedure/rule breach 28. Glenlee 2009
31. Strathfield 2010
35. Bankstown 2010
41. Unanderra 2011
45. Summit Tank 2012
50. East Maitland 2013
51. Moss Vale 2013
10.6 Work scheduling
practice/procedure/rule breach
10.7 Other safeworking rule or
procedure breach
OTSI Rail Summary Report
Contributing Factors in NSW Rail Incidents 2004 – 2013 145
Track and civil infrastructure
irregularity
11.1 Broken rail
11.2 Misaligned track
11.3 Spread track
11.4 Points irregularity
11.5 Track obstruction
11.6 Civil infrastructure irregularity
11.7 Bridge strike
11.8 Other track infrastructure
irregularity
Rolling stock irregularity 12.1 Train parting
12.2 Wheel/axle failure
12.3 Defective bearing
12.4 Faulty passenger door
12.5 Braking system
12.6 Other rolling stock irregularity 47. Gulgong 2012
Electrical infrastructure irregularity 13.1 Overhead traction supply
13.2 Other electrical irregularity
Fire 14.1 Fire on train
14.2 Lineside fire
14.3 Station/terminal fire
Explosion 15
Suspected suicide or attempted
suicide
16.1 Suspected suicide 13. Town Hall tunnel 2006
16.2 Attempted suicide
Alcohol or drugs irregularity 17
Train warning enforcement systems
irregularity
18.1 Warning systems irregularity
18.2 Enforcement systems irregularity
Communication systems failure 19
Railway network security 20.1 Railway trespass
20.2 Alleged assault
20.3 Terrorism/sabotage
20.4 Vandalism
20.5 Theft
20.6 Other railway network security
Runaway 21 27. Temora 2009