RAILROAD COMMISSION OF TEXAS

PSA Wells, Allocation Wells and Stacked LateralsPermitting and Completion

Lorenzo Garza & Joe Stasulli

Page 2: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

2

Presentation Overview

• How to qualify for Stacked Lateral status

• Requirements for PSA and Allocation wells

• Filing completions for these types of applications

Page 3: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

3

Page 4: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

Stacked Laterals- how to qualify

•2 or more horizontal drainhole wells within lease/pooled unit in the correlative interval.•Horizontal drainholes are drilled from different surface locations.• The first well drilled establishes the parameters that the subsequent wells will be tested against.

Make sure your field rules allow for Stacked Laterals and if so what well spacing is required.

4

Page 5: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

Stacked Laterals- how to qualify cont.

•Each surface location must be permitted separately and assigned its own API number.

•Plat must clearly show all wellbores attempting to qualify for Stacked Lateral status.

•To be considered a “regular location” each well must comply to any minimum lease or between well spacing rules

5

Page 6: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

Stacked Laterals why all the fuss?

• For each well that qualifies as a Stacked Lateral well your overall well count will not increase when the RRC tests your lease for density exceptions.

•Remember that the wells must be completed in the same regulatory field to qualify as a stacked lateral.

6

Page 7: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

Stacked Laterals potential problem?

•If your well, when completed, does not remain within the established parameters of the “record well” then you will be required to amend the permit to reflect its new status and count this well against your total well count. If you exceed density then an exception to SWR 38 will be needed.

7

Page 8: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

8

Page 9: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

9

Page 10: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

PRODUCTION SHARING AGREEMENTSSupporting Documentation:

•Authorization letter to include % of participation•PSA-12 form showing acreage to be assigned to proposed well•Plat showing the external boundary of all tracts contributing acreage to the proposed well•Well allocation worksheet

10

Page 11: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– AdvancedPRODUCTION SHARING AGREEMENTSSupporting Documentation:Authorization letter•Contractual right to develop all proposed tracts

•To be approved administratively minimum of 65% of mineral and working interest owners must be signed to agreement

•If less than 65% sign-up then request to set up application for hearing

11

Page 12: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

PSA/ALLOCATION AUTHORITY LETTER

12

Page 13: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

PRODUCTION SHARING AGREEMENTSSupporting Documentation:PSA-12 and Plat•PSA-12 form filled out showing all tracts and acreage involved

•Plat that shows the entire boundary of all contributing tracts

•All supporting lease/unit line calls should be to exterior boundary of the contributing tracts

•Any un-leased tracts within contributing tracts should be identified

13

Page 14: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

14

Page 15: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Online Filing - Advanced

15

Page 16: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

PRODUCTION SHARING AGREEMENTSSupporting Documentation:Acreage allocation work sheet•Breakdown of activity for each contributing lease/pooled unit

•If any contributing lease/pooled unit is over assigned then a statement as to how the deficiency will be resolved

•If SWR 38 density exception is required then application must follow procedures set forth in the rule

16

Page 17: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

W-1 ACREAGE ALLOCATION WORK SHEET

17

Page 18: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

18

Page 19: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

19

Page 20: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

What is the difference between a “PSA” well and an “Allocation” well?

1. On tracts that you have a valid lease in place an “Allocation”well permit will allow you to get a drilling permit application without the qualifier that you have to provide for a “PSA” wellthat 65% of both mineral and working interest owners havesigned an agreement as to how production proceeds will be divided.

2. What it doesn’t allow you to do is incorporate tracts into your“Allocation” unit that the wellbore does not traverse.

20

Page 21: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

PSA or ALLOCATION WELLSSWR Exceptions: Lease line•Allocation well application will always require an exception•PSA application will require an exception if there is less than 100% participation

Between Well•Normal notification procedures will be followed

Density Exception•Unless specified in the field rules normal notification and data requirements will be followed

21

Page 22: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– AdvancedPSA or ALLOCATION WELLS -Example

22

TRACT B

TRACT A

Page 23: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– AdvancedPSA or ALLOCATION WELLS -Example

23

Page 24: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– AdvancedPSA or ALLOCATION WELLS -Example

24

Page 25: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– AdvancedPSA or ALLOCATION WELLS -Example

25

Page 26: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– AdvancedPSA or ALLOCATION WELLS -Example

26

Page 27: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– AdvancedPSA or ALLOCATION WELLS -Example

27

Page 28: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– AdvancedPSA or ALLOCATION WELLS -Example

28

Page 29: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

Would you like to make your life a little easier and help decrease the processing time of both your drilling permits and completions?

29

Page 30: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

30

Page 31: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Contact InformationFor further questions concerning Drilling

Permits please contact:

Lorenzo GarzaPhone: 512-463-2184

Email: [email protected]

Valerie AtkinsPhone: 512-463-6979

Email: [email protected] 31

Page 32: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

32

Now Presenting Mr. Joe Stasulli

Page 33: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Railroad Commission of Texas

Operator Procedures for PSA and Allocation Wells

33

Page 34: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

34

Completion Report (G1/W2) must include:

• (SA) does NOT need to be included in the lease name.

• Sharing Agreement information must be referenced in the G1/W2 remarks.

• Detailed Sharing Agreement information must be attached to the completion packet.

Page 35: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

35

Page 36: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

36

Page 37: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

37

Page 38: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

38

Page 39: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Railroad Commission of Texas

Operator Procedures for Stacked Laterals

39

Page 40: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

40

• The first well of a stacked lateral is set up and processed in the same manner as any regular producing well. SL is NOT required to be part of the lease name.

• All the standard information should be filed for this well, drilling permit, completion, and associated forms.

Page 41: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

41

Page 42: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

42

• Any additional lateral wells (2nd, 3rd, 4th) must have an approved drilling permit and completions filed.

• The letters SL (Stacked Lateral) should be included in the well number if feasible.

• The drilling permit (W-1) and completion (G-1/W-2) remarks should reference that this is a stacked lateral and report all Railroad Commission identification numbers associated with all wells that are part of the stacked lateral. Use the drilling permit numbers if an RRC ID has not been assigned.

Page 43: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

43

Page 44: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

44

Page 45: RAILROAD COMMISSION OF TEXAS PSA Wells, Allocation Wells and Stacked Laterals Permitting and Completion Lorenzo Garza & Joe Stasulli

Drilling Permits and Well Compliance– Advanced

45