rajasthan solarpark development company limited · testing, commissioning & execution of civil...

77
1 RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED (A Government of Rajasthan Undertaking) CIN NO. U40102RJ2011SGC036861 Reg. Office: E-166, Yudhisthir Marg, C-Scheme, Jaipur-302001 Tel: 2225859, 2229341 email: [email protected] No. RSDCL/Solar Park/ TN-03 (2019-20)/D-spl 1 Date 16.03.2020 Sub: Corrigendum/Amendment/ Clarification No.1 in tender documents of TN-03 (2019- 20) for the reference of interested bidders. Certain Corrigendum/Amendment/ Clarification in tender documents of TN-03 (2019-20) as per attached documents & drawings is hereby issued for the reference of interested bidders. The bidders may go through these documents before completing and uploading their tenders. Attachment: As above. --sd-- Director (Technical) RSDCL, Jaipur

Upload: others

Post on 22-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

1

RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED (A Government of Rajasthan Undertaking)

CIN NO. U40102RJ2011SGC036861

Reg. Office: E-166, Yudhisthir Marg, C-Scheme, Jaipur-302001

Tel: 2225859, 2229341 email: [email protected]

No. RSDCL/Solar Park/ TN-03 (2019-20)/D-spl 1 Date 16.03.2020

Sub: Corrigendum/Amendment/ Clarification No.1 in tender documents of TN-03 (2019-

20) for the reference of interested bidders. Certain Corrigendum/Amendment/ Clarification in tender documents of TN-03 (2019-20) as per attached documents & drawings is hereby issued for the reference of interested bidders. The bidders may go through these documents before completing and uploading their tenders. Attachment: As above. --sd--

Director (Technical) RSDCL, Jaipur

Page 2: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Angelique International Ltd.,

NOIDA.

Ref: Your e-mail dated 04.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

1

Clause Ref. Description Bidder’s Query RSDCL’s Comments

Part-I

Instructions To

Bidders

41.0 Security

Guarantee

In order to secure/assure due fulfillment of the contract, the

successful bidder, to whom the

contract is awarded shall be required to furnish within a period of

15 (Fifteen) days from the

a) date of issue of the order(s) security bank guarantee equivalent

to 2% (two percent) of the total contract value………….

As per general practice being

followed in Indian tenders, only

Performance guarantee of 10% is

required.

Kindly waive off the security

guarantee of 2 %.

As per tender Specifications.

Part-I

Instructions To

Bidders

2.6 Other

Disqualification

Criteria:

(ii) record of poor performance such as incompletion of projects

awarded in past/ inordinate delays in completing the contract

earlier awarded by RSDCL or litigation history or blacklisting etc.

We understand, criteria under this

clause are in reference to RSDCL

contracts only.

But you have to submit Information

regarding any current litigation in

which the bidder isinvolved, the

parties concerned and disputed

amount involved, as per clause No.

2.5(c)of ITB, Vol-I.

If there is no current litigation, then

your declaration in this regard is

required.

Part-I

Instructions To

Bidders

2.6 Other

Disqualification

Criteria:

34.7.3 The payment terms for various components of Supply and

Services shall be as under:

(A) Ex-Works Price Component for Main Equipment

(ii) Progressive Payment

(b) Further 20% (Twenty percent) payment of ex-works value will

be paid after submission of verification/certification by engineer

that equipment/ material has been erected.

In order to have a positive cash-flow

for successful implementation of the

project, we request you to please pay

20% payment (linked with erection)

along with 60% payment which is

due upon receipt of material at site.

As per tender Specifications.

Part-III

Special Conditions

Of Contract

10.0 Time

Schedule

For the purpose of Clause No. 17.0 of ITB, the schedule for

completion of supply of material/ equipment, successful erection,

testing, commissioning & execution of Civil Works of allfour

220/33kV Park Pooling Sub-stations and their handing over to

RSDCL, complete in all respect as per specification of entire work

shall be 15 (Fifteen) months from the date of issue of detailed

purchase/work order(s). The completion period is inclusive of

monsoon period also.

Please amend the Completion period

from 15 months to 18 months.

As per tender Specifications.

Page 3: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

23.0 Bid Security

(EMD)

ii. Bid Security (Rs. 4,83,80,000): DD/Banker‟s Cheque/BG as under:

a) 20% amount of prescribed Bid Security by DD/Banker‟s cheque in favour of MD, RSDCL, Jaipur payable at Jaipur.

b) 80% amount of prescribed Bid Security by furnishing Bank

Guarantee (in original) on the Rajasthan State Non Judicial Stamp

Paper of Rs. 100/- (or as per Govt. norms) purchased in the name

of executant‟s Bank, duly authenticated either by a first class Magistrate or Notary Public or directly confirmed by the issuing

Bankers & shall be valid for at least 180 days with the grace

period of 90 days (Bid Bank Guarantee format is enclosed at

Annexure-VIII, Vol-I).

or

The bidder may furnish the entire amount of Bid Security by

DD/Banker‟s Cheque

Please reduce the Bid Security to 1%

of the estimated contract value in the

form of Bank Guarantee.

As per tender Specifications.

Page 4: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s BGR Energy Systems Ltd.,

Chennai.

Ref: Your e-mail dated 06.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

2

Clause Ref. Description Bidder’s Query RSDCL’s Comments

2.1 of SCC 2.0 BID GUARANTEE (EMD)

b) Rs. 96,76,000 only (Rupees Ninety Six Lakhs Seventy Six Thousand only)

shall be furnished through Demand Draft/Banker‟s Cheque drawn in favour of MD, RSDCL, Jaipur or deposited in cash.

c) Rs. 3,87,04,000 only (Rupees Three Crore Eighty Seven Lakhs Four

Thousand only) shall be furnished in the form of Bank Guarantee, initially

valid for a period of 180 days with a grace period of 90 (ninety) days for

which proforma has been enclosed at Annexure-VIII, Volume-I.

We request you to consider 100%

of Bid Guarantee (EMD) amount

i.e. Rs.4,83,80,000/- (Rupees Four

Crore Eighty Three Lakhs Eighty

Thousand only) shall be

acceptable in the form of bank

Guarantee instead of 20% DD and

80% BG .

Kindly confirm.

As per tender

Specifications.

Funding Please confirm the funding

agency of this project.

Self

1.13 of

Specification

for Design,

Manufacturing

and

Testing/Commi

ssioning of

80/100 mva,

220/33 kv

power

transformer

1.13.1 The bidders are required to offer the Transformers having “No Load‟ & “Load‟ losses not exceeding the following values, without any positive

tolerance:

No Load Loss : 38 kW

Load Loss : 250 kW

1.13.3 The bidders are requested to indicate whether the figures given for

guaranteed losses in schedule of guaranteed technical particulars are with or

without such tolerances. If tolerances are applicable, the limits for the same

should be indicated. In the absence of any intimation to this effect, the figures

for “No Load‟ & “Load‟ losses (including Auxiliary losses) will be increased by the following tolerances provided in the Indian standards:

Total losses : 10%

Component losses : 15%..…….

Clause no. 1.13.1 and 1.13.3 are

contradictory. Kindly confirm

whether the offered transformers

are with or without tolerance.

Bidder may quote lower

losses than the prescribed

limit (clause 1:13:1).

If bidder doesn‟t prescribe

any tolerance limit in

tender than limit as

prescribed (10% and 15%,

as per clause 1:13:3) will be

considered.

If any bidder quotes less

than the prescribed limit

then for evaluation purpose,

the capitalization is

required.

1.13.1 The bidders are required to offer the Transformers having “No Load‟ & “Load‟ losses not exceeding the following values, without any positive tolerance:

No Load Loss : 38 kW

Load Loss : 250 kW

As per clause no. 1.13.1, the

losses are already stipulated in the

tender and bidders quoting more

than the stipulated losses will be

rejected.

Page 5: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

The bidders quoting losses more than the values prescribed above in GTP

shall be rejected.

No benefit shall be allowed to the bidders quoting losses less than the above

prescribed values.

1.13.5: For the purpose of comparison of tenders, the quoted prices shall be

capitalized for the “No Load‟ losses and “Load‟ losses in two windings (HV+LV) including Auxiliary losses at the same rate as given at clause No.

1.13.2 forthe penalty/recovery, on the basis of max. guaranteed losses figures

including tolerance, if any. The Auxiliary losses shall be the losses for two

groups of cooler fans. Losses for standby arrangement will not be accounted for

penalty/capitalization purpose

Whereas clause No.1.13.5

indicates capitalization is

applicable for the purpose of

comparison of tenders

Kindly confirm that bidder should

quote losses specified as per

clause no 1.13.1. Also please

confirm capitalization of losses is

not applicable for comparison of

tenders

Page 6: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Sterling & Wilson Pvt. Lid.,

Kolkata.

Ref: Your e-mail dated 06.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

3

Clause Ref Description Bidder’s Query RSDCL’s Comments

General

Scope

Present scope involves the work inside Plot

boundary as per SLD. We assume that 220KV

incoming side conductor upto dead end tower

including line side insulator are not under present

scope. Please confirm.

Yes

General

Stringing Insulator

Single & Double, both stringing

insulator are mentioned in the tender

documents

We are considering double tension insulator &

single suspension insulator for 220KV & 33KV

voltage. Please confirm.

As per tender Specifications.

General

Soil Resistivity

Please provide us the soil resistivity of the 4 nos

substation site for estimation of earthing quantity.

Report is enclosed herewith

SECTION-I, ClNo. 2 Busbar

arrangement, Page 5

No of conductor for 33KV

Aux Bus

4. 33kV Auxiliary Bus: Single Tarantula

conductor.

As per specification 33KV aux bus is single

Tarantula but as per tender drawings it is twin

Tarantula. Please confirm which one to be followed

for present scope.

Single Tarantula

General

Soil Investigation Report

Please provide us the soil investigation report. Report is enclosed herewith

ITB 2.1(i) Experience The bidder must have successfully

erected, tested and commissioned at

least 1 No. of 220kV or above voltage

class Grid sub-station or switchyards on

turn-key basis within the last

sevenyears, immediately preceding the

date of Technical bid openingby

supplying at least major

material/equipments i.e. Transformer,

circuit breakers, switchyard structures,

CTs, PTs, CVTs, LAs, Isolators, Control

& Relay panels. The bidder should have

also executed the associated Civil works

We Understand that the bidder must have

successfully erected, tested and commissioned at

least 1 No. of 220kV or above voltage class AIS

Grid sub-station or switchyards on turn-key basis

within the last seven years, immediately preceding

the date of Technical bid opening by supplying at

least major material/equipments i.e. Transformer

with Similar rating (i.e. 220/33 KV, 100MVA),

circuit breakers, switchyard structures, CTs, PTs,

CVTs, LAs, Isolators, Control & Relay panels. The

bidder should have also executed the associated

Civil works of these sub stations/ switchyards to

qualify for the Package. Please confirm.

As per tender Specifications.

Page 7: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

of these sub stations/ switchyards to

qualify for the Package.

General

Drawings

Please arrange to provide the drawings like

Boundary Wall, Store Shed, Fencing, Gate for

recent projects.

Enclosed.

Civil

Drawings

The minimum required heights(if any) for

dormitory and control room, then confirm the same

since it is not available in tender document.

As per Standards

Civil

Drawings

Please arrange to provide the Standard drawings of

Transformer Foundation, Cable Trenches, Oil Pits,

Underground Tanks, Road Cross Sections etc.

Enclosed.

Road thickness shall be 550mm

which will include

Quarry rubbish/murrum -300mm.

PCC (1:4:8)- 100mm

CC (1:1.5:3)- 150mm

Civil Please arrange to provide the dimensions of security

room (Guard hut).

Enclosed.

General

Taxes & Duties

Whether the Cess will be applicable on total

Contract or on Labour portion only. Please confirm.

As per prevailing Tax provisions

ITB 1.1, 35

Work Contract

Please confirm whether the work will be treated as

work contract or Divisible contract.

As per tender Specifications.

GCC 29.1

TRAINING OF OWNER'S

PERSONNEL

If desired by RSDCL, the contractor

shall undertake…................The details of the Nos. of persons to be trained,

period of training, nature of training etc.

shall be as mutually agreed.

Please confirm the name of product for which

training is required. Also, please confirm the

number of persons to be trained and period of

training.

As per conditions of tender

Specifications.

Page 8: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Shyama Power,

Gurugram.

Ref: Your e-mail dated 11.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

4

Query RSDCL’sReply

We shall submit the Manufacturer's Authorization form on award ofcontract.

Kindly confirm.

Request you to please clarify the amount of stamp paper For Bank Guarantee As per Rajasthan Govt. norms.

Request you to please provide drawing the structure These are standard structures and drawings will be provided at the time of

work execution.

We presume that only following documents will be submitting as hard or physical

1. Bid Security (EMD)

2. Copy receipt of tender fee

3. Copy receipt of processing fee

4. Power of attorney of authorize person.

Rest of documents will be submitting through online.

Kindly Confirm

Following items in original are to be submitted in physical form in Envelope

upto due date and time in the office of Director (Fin.), E-166, Yudhishthir

Marg,C-Scheme, RSDCL, Jaipur:

1. Tender cost in the form of DD/ BC.

2. Bid Security as prescribed in tender specification.

3. RISL processing Fee in the form of DD/ BC

4. Joint Venture Agreement & Power of Attorney for Joint Venture

Request you to please provide the water level at site. Water table>40 meters

Request you to please extend the tender date atleast 10-15 days more No

Page 9: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Amara Raja Power Systems Ltd.,

Hyderabad.

Ref: Your e-mail dated 11.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

5

Clause Ref. Description Bidder’s clarification/ proposed amendment RSDCL’s Comments

IFB, Note -2

Bid Security (Rs. 4,83,80,000): DD/Banker‟s Cheque/BG as under:

a) 20% amount of prescribed Bid Security by

DD/Banker‟s cheque in favour of MD, RSDCL, Jaipur payable at Jaipur.

b) 80% amount of prescribed Bid Security by

furnishing Bank Guarantee (in original) on the

Rajasthan State Non Judicial Stamp Paper of Rs.

100/- (or as per Govt. norms) purchased in the

name of executant‟s Bank, duly authenticated either by a first class Magistrate or Notary Public

or directly confirmed by the issuing Bankers &

shall be valid for atleast 180 days with the grace

period of 90 days (Bid Bank Guarantee format is

enclosed at Annexure-VIII, Vol-I).

Bid Security (Rs. 4,83,80,000): DD/Banker‟s Cheque/BG as under:

100% amount of prescribed Bid Security by

DD/Banker‟s cheque in favour of MD, RSDCL, Jaipur

payable at Jaipur.

OR

100% amount of prescribed Bid Security by furnishing

Bank Guarantee on the Non Judicial Stamp Paper of Rs.

100/- (or as per Govt. norms) purchased in the name of

executant‟s Bank, duly authenticated either by a first

class Magistrate or Notary Public or directly confirmed

by the issuing Bankers & shall be valid for atleast 180

days with the grace period of 90 days (Bid Bank

Guarantee format is enclosed at Annexure-VIII, Vol-I).

As per tender Specifications.

SPECIAL

CONDITIONS

OF

CONTRACT -

8

PRICE ADJUSTMENT DUE TO PRICE

VARIATION: Not applicable

The Prices for the following items, quoted by the

Bidder shall be VARIABLE in accordance with the

relevant IEEMA/CACMAI Price Variation Formula

and Indices.

Equipment / Materials:

1) Power Transformers

2) C&R Panels, SAS

3) Conductors & Ground Wires.

4) Lightning Arresters.

5) Transformer Oil.

6) Tower Parts, equipment mounting/ Station

Structures.

7) Control Cables.

The prices will be firm.

Page 10: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

8) HT/EHT Cables

9) Conductor Hardware.

10) Battery & Battery Chargers.

11) Instrument Transformers.

12) Insulators

13) Transmission line Towers & Access

14) Circuit Breakers.

34.7 TERMS

OF

PAYMENT

34.7.3 (A) Ex-Works Price Component for Main

Equipment

(i) Interest Bearing Advance (Optional*): Ten

percent (10%) of the Ex- works price of the

main equipment/materials shall be paid as an

advance

34.7.6 ERECTION AND CIVIL WORKS

PRICE COMPONENT:

Interest Bearing Advance (Optional**): Ten

percent (10%) of the total contract price for

service viz. ETC and its associated civil works

component including supervision of erection

charges shall be paid as initial advance

34.7.3 (A) Ex-Works Price Component for Main

Equipment

(i) Interest Free Advance (Optional*): Ten percent

(10%) of the Ex- works price of the main equipment

/materials shall be paid as an advance

34.7.6 ERECTION AND CIVIL WORKS PRICE

COMPONENT:

Interest Free Advance (Optional**): Ten percent

(10%) of the total contract price for service viz. ETC

and its associated civil works component including

supervision of erection charges shall be paid as initial

advance

As per tender Specifications.

10.0 TIME

SCHEDULE

For the purpose of Clause No. 17.0 of ITB, the

schedule for completion of supply of material/

equipment, successful erection, testing,

commissioning & execution of Civil Works of all

four 220/33kV Park Pooling Sub-stations and

their handing over to RSDCL, complete in all

respect as per specification of entire work shall

be 15 (Fifteen) months from the date of issue

of detailed purchase/work order(s). The

completion period is inclusive of monsoon period

also.

For the purpose of Clause No. 17.0 of ITB, the schedule

for completion of supply of material/ equipment,

successful erection, testing, commissioning & execution

of Civil Works of all four 220/33kV Park Pooling Sub-

stations and their handing over to RSDCL, complete in

all respect as per specification of entire work shall be 18

(Eighteen) months from the date of issue of detailed

purchase/work order(s).

As per tender Specifications.

Bid price

schedule Bid Price Schedule_Sl.No-4.0 _ Bus bar material

We are not envisaged line side string insulator as well

as string hardware for 220KV & 33KV line feeders.

Please confirm the bidder understanding is correct.

Yes

Bid price

schedule

Bid Price Schedule Wave Trap Unit Structure

_Sl.No-1.12

We presume the Wavetrap unit structure weight is equal

to three single units of PIS Unit weight. _Please

confirm the bidder understanding is correct.

Wave trap will be pedestal type, to be

mounted on structure.

Bid price

schedule

Bid Price Schedule Structure Unit weights

_Sl.No-1.16 & 1.17

We have taken the XYZ (Y-without stub) and XY unit

weights are addition of individual X, Y and Z unit

weights, which were given in the specification. Please

As per tender specification and BoQs.

Page 11: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

confirm the bidder understanding is correct.

Bid price

schedule

Bid Price Schedule_Sl.No-2.01 to 2.28 TOOLS

& TACKLES

We are not envisaged Maintenance equipment & spare

parts for the main equipments like Power transformer,

Reactor, CB, CT, CVT, Panels and SAS equipment etc.

Please confirm.

As per tender specification.

Bid price

schedule

Bid Price Schedule_Sl.No-2.01 and 2.03 to 3.12

:Maintenance equipment & spare parts

We are not envisaged TOOLS & TACKLES for the

main equipments like Power transformer, Reactor etc.

Please confirm.

As per tender specification.

Bid price

schedule 220KV CT/CVT Junction Boxes

220KV CT/CVT Junction Boxes are not given in the

Bid price schedule. Please provide

As per tender specification.

SLD 220KV Metering Instrument transformers Please furnish the Technical specification of 220KV

Metering CT's & CVT's

As per tender specification.

SLD Deviation of 220KV Double earth switch

quantity

As per SLD shows 220KV double earth switch quantity

for all four pooling substations is 42 however BPS

schedule shows the qty-36. Please clarify.

As per tender specification and BoQs.

Structural

layout plan 220KV Marshalling kiosk- quantity

As per Bid price schedule quantity has shown 38 nos

however structural layout plan quantity has shown 34

no's. Please clarify.

As per tender specification and BoQs.

Bid price

schedule ABT Meters

ABT meters 's are not given in the given BPS schedule

.Please provide

ABT Meters are not in the scope of

supply.

Bid price

schedule

Deviation of Wave trap along with structures

quantity

As per Bid price schedule Wave trap equipment

quantity: 24 but wavetrap structure supply qty-28.

Please clarify.

As per tender specification and BoQs.

Earthing Earthing Calculation

Kindly provide the soil resistivity report for

calculation and estimation of earthing material for our

reference .

Report is enclosed.

Lighting Clarification of Street lights Street lights can be eliminated if the lux level is

achieved using switch yard lighting

As per tender specification and site

requirement.

General Drawings required Please provide the structural foundation drawings for any one of 220/33KV substation.

Enclosed.

General Drawings required Please provide the cable trench section drawing. Enclosed.

General Electrical layout Plan for PSS-1,2,3,4

We understand lightening protection & Illumination of

proposed Pooling station of 220kV & 33kV switchyard

are to be achieved through gantry mounted GI shielded

wire and lighting fixtures. However LM's are not

envisaged for both the application's _ Please confirm

the bidder understanding is correct.

Lightening protection- through gantry

mounted GI shielded wire.

Illumination- on yard structures and

GI poles.

PLCC Transmission Line Details

Request to clarify whether all the 220kV Lines from 4

PSS will be connected to 765kV Bhadla SS. If any

LILO of existing Lines is present , request to provide

the same to consider shifting of PLCC equipment

All works will be new only.

Page 12: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Tech Spec,

Section-I,

Clause 2.0,

S.No(6), Page

129 of 607

and Page 484

of 607, Clause

4, S.No (7)

Creepage Distance :6125mm and Minimum

creepage distance of the Insulator for moderately

polluted atmosphere (total)3800 mm.

Request to Clarify the creepage distance to be

considered for 220kV and 33kV

Creepage distance shall be as under:

1. For 220kV- 6125 mm

2. For 33kV- 900 mm

Tech Spec,

Section-I,

Clause 3.0,

S.No(m), Page

130 of 607

and Page 484

of 607, Clause

4, S.No (7)

Degree of Pollution

Degree of Pollution is mentioned as "Heavy" in climatic

conditions but as Moderate in technical specification of

Disc Insulators. Kindly Clarify.

As per site conditions.

General Unit weights for HG Fuse structures Request to kindly provide the weight of 33KV and

11KV HG Fuse structure unit weights.

As per standard norms.

General General Please specify the Cantilever strength on 33KV Post

Insulators

As per relevant IS.

Page 13: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Proteus Enterprise Pvt. Ltd.,

Ahmedabad.

Ref: Your e-mail dated 11.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

6

Clause Ref. Description Clarification sought RSDCL’s clarification/comments

Invitation of Bid

Note: 2.(ii)

Bid Security (Rs. 4,83,80,000): DD/Banker‟s

Cheque/BG as under:

a) 20% amount of prescribed Bid Security by

DD/Banker‟ s cheque in favour of MD,RSDCL, Jaipur payable at Jaipur.

b) 80% amount of prescribed Bid Security by

furnishing Bank Guarantee (in original) on

the Rajasthan State Non Judicial Stamp Paper of

Rs. 100/- (or as per Govt. norms) purchased in

the name of executant‟ s Bank, duly

authenticated either by a first class Magistrate or

Notary Public or directly confirmed by the

issuing Bankers & shall be

valid for atleast 180 days with the grace period

of 90 days (Bid Bank Guarantee format is

enclosed at Annexure-VIII, Vol-I).

or

The bidder may furnish the entire amount of Bid

Security by DD/Banker‟s Cheque.

Bid Security (Rs. 4,83,80,000): BG as under:

100% amount of prescribed Bid Security by furnishing

Bank Guarantee (inoriginal) on the Rajasthan State

Non Judicial Stamp Paper of Rs. 100/- (or asper Govt.

norms)purchased in the name of executant‟s Bank,

dulyauthenticated either by a first classMagistrate or

Notary Public or directly confirmed by the issuing

Bankers &shall be valid for atleast 180 days with the

grace period of 90 days (Bid Bank Guarantee format is

enclosed at Annexure-VIII, Vol-I).

Also provide us the RSDCL Bank Details for issuing

the Bank Guarantee.

And when the RSDCL are returned the bid

security.

Bid Security will be as per tender

Specifications only.

RSDCL Bank Details are as under:

Bank: Oriental

bank of Commerce

Branch: RSAMB, Jaipur

Account No.: 11331131000550

IFSC code: ORBC0101133

GENERAL Tender Estimated Cost We understand that, the given ECV of tender are

inclusive of all taxes and duties.

Please confirm.

Bidder has to quote the price

inclusive of all taxes and duties but

exclusive of GST.

GENERAL Entry Tax and Other Local Taxes Please provide us the percentage of entry tax and other

Local taxes. The entry tax are credit in GST set off. Plz

confirm.

As per tender Specification.

GENERAL Drawings Please provide us all Structure & Equipment FND

drawings, Electrical Section Drawings of TBC & BC

bay.

All structures are standard structures

generally used in the GSSs. Some

standard drawings are enclosed. For

electrical section drawings please go

through the specification.

BoQ 1. 1.12

Wave trap

Structure & 11.08

As per the Given BoQ qty. of wave trap and wave trap

structure are mismatch. Plz correct the same.

As per BoQ.

Page 14: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Wave Trap

GENERAL Please provide us the LOT Qty. of BOQ items breakup. Quantity to be assessed by bidder as

per standard norms and site

requirements.

Technical

Specification

Annexure-II(A)

Approved Vendor List We are proposed another vender list, the vendors are

approval in other Power sector utility. Plz incorporate

the same. (herewith we attached vendor list)

Please follow the approved vendors

list given in the specification.

BoQ 1. 11.08

Wave trap

Equipment

As per the Given BoQ description of wave trap and

Specification of wave trap is mismatch with BOQ

description. Kindly confirm the same.

As per BoQ.

BoQ 1. 4.08, 4.09

,4.10,4.11 & 4.12

Conductor

&Earthwire

Technical Specification is not available for Earth wire

& Conductor. Plz. Give the same.

Please refer relevant Standards.

BoQ 1. 3.17

LTDB

Technical Specification is not available. Plz. Give the

same.

The details will be provided at the

time of work execution.

Technical

Specification

Section-II BoQ 1.

2.01 Power

Transformer

1.13: GUARANTEES:

1.13.1: The bidders are required to offer the

Transformers having „No Load‟ & „Load‟ losses

not exceeding the following values, without any

positive tolerance:

(i) No load losses at rated voltage, normal ratio

& rated freq. : 38 kW.

(ii) Load losses at rated current, normal ratio,

rated freq. & : 250 kW.

75 deg. C including auxiliary loss.

The bidders quoting losses more than the values

prescribed above in GTP shall be rejected. No

benefit shall be allowed to the bidders quoting

losses less than the above prescribed values.

However, as per following clause capitalization

shall be applicable for subject enquiry :

1.13.5: For the purpose of comparison of

tenders,

the quoted prices shall be capitalized for the

„No

Load‟ losses and „Load‟ losses in two windings

(HV+LV) including Auxiliary losses at the same

rate

Kindly confirm whether subject we should be quoted

with fixed losses or Capitalization shall be considered.

In case of capitalization, also explain its application, as

it is stated that there shall be rejection for high losses

and no benefit for low losses.

Bidder may quote lower losses than

the prescribed limit (clause 1:13:1).

If bidder doesn‟t prescribe any

tolerance limit in tender than limit as

prescribed (10% and 15%, as per

clause 1:13:3) will be considered.

If any bidder quotes less than the

prescribed limit then for evaluation

purpose, the capitalization is

required.

Page 15: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

as given at clause No. 1.13.2 for the

penalty/recovery, on the basis of max.

guaranteed

losses figures including tolerance, if any. The

Auxiliary losses shall be the losses for two

groups of cooler fans. Losses for standby

arrangement will not be accounted for

penalty/capitalization

purpose.

ITB Cl. 40.0

CONTRACT

PERFORMANCE

GUARANTEE

and

Cl. 41.0

SECURITY

GUARANTEE

CONTRACT PERFORMANCE GUARANTEE

and

SECURITY GUARANTEE

As per the given clause successful bidder submit the

Contract Performance Guarantee of 10% of total

contract value, so why submit the 2% of Security

Guarantee of total contract value.

Plz modifying the clause. As per the standard biding

process.

As per tender Specifications.

GCC Cl. 24.0 CHANGE OF QUANTITY: Plz provide us the percentage of (+/-) for the Quantity. As per specification.

GENERAL Plz. Provide us the Pooling Sub-stations A, B, C & D

Co-ordinates. As per the given co-ordinates are

location only.

GENERAL Material Inspection We understand that the supply of all Electrical items

Inspected by RSDCL. Plz Confirm.

If any third part to be depute for Inspection, like

NABL, RITES, BIS….etc. Plz Clarify.

RSDCL as well as other also.

Technical St. Transformer For 33/0.4 KV, 250 KVA transformer- OEM having

type test reports of BIS Level-2 instead of BIS Level 3.

Plz confirm whether Level-2 type test report are

acceptable or not.

For 11/0.4KV, 100 KVA Transformer- As per the

technical specification offer transformer of BIS Level-

1 is obsoleted and is no longer manufactured, So we

offer BIS Level-2. Plz clarify.

Impulse Test of 100KVA BIS Level-2 Transformer is

conducted at B.I.L 75 KVp instead of 95 KVp. Plz

Confirm.

As per tender Specifications.

Equipment of better technical

parameters may be accepted.

Page 16: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Blue Star Ltd.,

Mumbai.

Ref: Your e-mail dated 11.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

7

Item / Description Doc Ref. No / Page

no.

Remarks by Blue Star Ltd. Clarification from RSDCL

Last date of Deposit of Cost

of Tender Specification,

Processing Fee, Bid Security

including BG in original, in

physical form

Sl. No. II Important

Dates in NIT

We presume that only these documents mentioned under SL. no II of

NIT are to be submitted in Hard copy. Soft copies of rest all

documents (Cover 2 ) as mentioned under Cl. No 18 Documents

Comprising the Bid to be uploaded on website. Please Confirm.

Following items in original are to be

submitted in physical form in

Envelope upto due date and time in the

office of Director (Fin.), E-166,

Yudhishthir Marg,C-Scheme, RSDCL,

Jaipur:

1. Tender cost in the form of DD/ BC.

2. Bid Security as prescribed in tender

specification.

3. RISL processing Fee in the form of

DD/ BC

4. Joint Venture Agreement & Power

of Attorney for Joint Venture.

Confirmation of GTP Cl. No 10

Documents

Comprising of Bid

to be uploaded to e-

proc Portal - NIT

As concluded during the pre-bid conference, we shall submit a

declaration stating that all equipments /materials supplied shall be as

per tender specification and confirming to Guaranteed technical

parameters. Detailed GTP, Type test reports, Manufacturer's

Authorization etc. shall be submitted in the event of order and not as

part of bid. Please confirm.

Yes.

However, Loss figures of

Transformers and Reactor are to be

indicated in the Technical bid.

Estimated Value of project

as mentioned in Portal is

INR 241 Cr

e-procurement

portal

We presume that the Estimated value of project i.e. INR 241 Cr is

excluding GST since the prices being asked by bidders are also

excluding GST. please confirm

Bidder has to quote the price inclusive

of all taxes and duties but exclusive of

GST.

Bid Security Sl. No 2, (Note) NIT 1. We have noted that 20% of the Bid security need to be deposited

in DD/Banker's cheque. Please review and accept 100% of Bid

Security in the form of Bank Guarantee.

2. Tender specification is having specific requirement of submission

of EMD in Bank guarantee executed in Rajasthan state Non Judicial

stamp paper. Please review and allow bidders to submit the Bank

guarantee executed in Non Judicial stamp paper of any state.

As per tender Specification.

Page 17: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Pre-Dispatch inspection of

Equipment/Materials

Sl. No 11, NIT Kindly provide the list of major materials /equipment for which

Factory inspection test / Pre-dispatch inspection test shall be carried

out so that we can estimate the Traveling, and lodging cost for such

materials

All the material shall be supplied after

due inspection.

Qualifying Requirement of

Bidder : Technical Criteria

Cl. No 2.1 The technical PQ criteria asks bidders experience of 220 kV or

above class Grid S/s with Supply, Installation Testing and

commissioning of Major Equipment such as Transformer, circuit

breakers, switch yard structures, CTs, PTs, CVTs, LAs, Isolators,

Control & Relay panels. We wish to highlight the fact that many of

the SEBs / power utilities have standard practice of awarding the

construction of Substation work with Power transformers as a Free

issue item, eventually the scope related Power transformer is

Erection testing and comissioning only. We request you to review

the technical criteria of qualification and consider the Substation

construction experience with supply of all other major equipment

and ETC of Power transformer

As per tender Specification.

The quoted prices shall be

„FIRM‟ only. Cl. No 16 ITB Please review the subject tender clause and allow for variable prices

as per IEEMA indices applicable for entire contract

As per tender Specification.

Award of Contract Cl. No 35 ITB, page

23 of 607

Confirm whether the contract prices shall be inclusive of GST or

excluding GST?

Further also explain the modality of GST transaction, since the

bidder's prices are being quoted excluding GST.

Bidder has to quote the price exclusive

of GST.

The Modality of GST transaction shall

be as per applicable provisions of

CGST Act and rules thereon.

Taking over of Pooling

substations

Cl. No 31. Terms

ofPayment, Part - II

GCC, Page 42/607.

In case upon the completion of Pooling Substation, If solarpark is

still under construction and 33 kV Line feeders not available at

Substation level, the substation to be charged from 220 kV line and

entire substation deemed to be commissioned. Please confirm

As per tender specifications.

Payment of Taxes and

Duties

Cl. No 34.7. Terms

ofPayment, Part - II

GCC, Page 45/607.

Tender specification is not clarifying regarding the payment of GST

for the bills submitted during progressive payment of Supply and

installation portions (i.e. 60%/70% of Supply payment and

80%/90% of Installation Testing and commissioning & Civil

payment). We assume that 100% taxes and duties shall be

reimbursed along with above progressive payments Please confirm.

Tender Specification is already clear

about payment mechanism of

progressive payment and there will be

no bifurcation for taxes and duties.

The rate of progressive payment

which is given in tender shall be

applicable for payment of taxes as

well.

Page 18: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Handholding charges : 100%

payment of Handholding

charges shall be released

after the successful

completion of 12 months

period from the date of

taking over certificate and

issue of certificate by the

incharge of Pooling Sub-

station (s) regarding

satisfactory performance of

handholding.

Cl. No 34.7.5 Terms

ofPayment, Part - II

GCC, Page 47/607.

We request you please review the payment terms for handholding

charges and kindly consider its payment towards Monthly running

bills instead of yearly payment.

As per tender Specification.

Water supply at proposed

project sites

Cl. No 14.3

WATER Part IV

ECC page no 74 of

607

1. Please confirm the status of availability of water at all 4 PSS

locations. 2. What is the prevailing rates if the same is provided by

RSDCL.3. Establishment of tube well/Water pipeline is not included

in BOQ. Hence, incase if the source of water supply is established

by contractor at PSS same should be reimbursed at actuals.

The Contractor shall make his own

arrangements for power, water and

other facilitiesnecessary for the

construction/erection of Pooling Sub-

stations at his own cost.

Geo technical Investigation,

Soil resistivity Test,

Contour Survey

Annexure 12,

Volume III Civil

Works

1. Please provide the Geo technical Investigation Reports (Soil

report) for design and estimation of civil works also provide contour

drawing with indication of area to be developed with mentioning the

levels both NGL and FGL.

2. Referring to Earth mat layout design drawings in page no 603 of

607, we presume that the quantity of Earth Electrodes /Raisers/MS

Rounds are to be considered as per drawing provided for tender

purpose only.

If the design of earthing grid is in bidder‟s scope, please provide

substation wise soil resistivity report.

Soil Report and contour map of the

area are enclosed.

Details of Boundary Wall Sl. No 11. Volume 3

Specification of

Civil works

Please provide the drawing of Boundary wall along with the details

of Stone masonary, Brick work etc.

Kindly refer the clause no. 11 of Civil

section (Volume III) of Tender

Specification.

33 kV Feeder

interconnection at

Substations

Tender drawings (

PDF Pg. No.602)

Section drawings

1. Since the substations are Park Pooling Substation, the 33 kV

Feeders marked should be Incomers instead of O/G as in Drawing.

Please confirm whether the understanding is correct.

2. We presume that the scope of cables and LAs for 33 kV Line

feeders are not included in subject tender. Please confirm.

3. Please confirm the size of the Outdoor Kiosks (NTPCScope) as

mentioned in the Tender layout.

1. No matter.

2. Yes.

3. CT/PT set for measurement of

energy input on each 33kv Feeder

shall not be in the scope of bidder.

Page 19: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Inspection path Tender drawings

(PDF Pg. No. 602)

Section drawings

Kindly confirm the 3M wide inspection path/road within the 220KV

Switch yard shall be suitable for vehicle movement or not. If yes,

then please refer to the enclosed Sectional details as prepared (viz.

220KV Section AA, BB, CC, DD & EE) and confirm suitability.

Also, even if the inspection path is not intended for vehicle

movement, the above equipment level bus shall be of IPS Tube.

Please confirm.

All roads shall be suitable for vehicle

movement.

33 kV Aux. Bus Tender drawings (

PDF Pg. No. 602)

Section drawings

33KV Sectional Drawings as shown has the Aux.Bus configured by

Twin Tarantula Conductor but in the TS the same has been

mentioned as Single Tarantula Conductor. Please confirm the actual

requirement.

Single Tarantula Conductor

220 kV Spare Bay Structures Tender drawings (

PDF Pg. No.600)

Structural Layout

Plan for PSS-2&3

For 220KV Spare Bay at PSS-2&3 ( right hand side ), 3Nos Beam

Type AB2 to be considered for stringing of main Bus -1 & 2 and

Aux.Bus, which is not labeled in the said layout drawing. Please

confirm its requirement.

As per tender Specification.

Structures/Beams with Nuts,

Bolts & Washers etc.

Complete.

Sl. No. 1.12, 1.13,

1.17 Supply part

BOQ 1

Please provide the weight of these structures (Bifurcation of weight

of structure, Nut and Bolts and Washers).

As per Standards.

Details of Cable Trenches :

Type Ax, A, C, D.

Sl.No 28 to 31,

BOQ 3 Civil Part

Please provide the cross section drawings of these type of trenches

so as to estimate the cost according to depth and width of each type

of cable trench.

Drawing enclosed.

PLCC Equipment with

associated equipment &

accessories

Sl. No 11 of BOQ 1

& 2 Supply part and

Installation part

We presume that the transmission line contractor shall terminate the

220 kV Lines at respective gantries in substation. Kindly Confirm.

Yes.

33Kv CT/PT Junction Box Sl. No 2.16 Tender

BOQ, Schedule A

Quantity of Junction box which is 24 nos is not matching with the

total quantity of 33 kV CT/PT. please confirm the quantity

As per tender Specification.

30 KV Lightning Arrester Sl. No 2.17 Tender

BOQ, Schedule A

Looking at the quantity of 30 KV LAs we presume that supply and

installation of LAs for 33 kV Line Feeders are excluded from subject

project scope. Please confirm.

Supply of 33 kV LAs of 33 kV lines

shall be in the scope of project

developer.

33 KV Marshaling Kiosk Sl. No 2.18 Tender

BOQ, Schedule A

33kV side Marshaling Kiosk's quantity as per the scheme provided

should be be 78 Nos in place of 48 Nos in total. Please confirm.

As per tender Specification.

Equipment Level Bus Sl. No. 4.08, 4.09 &

4.10 Schedule A

Tender BOQ

Can we use IPS Tube in place of AAC/ACSR in Equipment Level to

avoid sag for maintaining necessary ground clearance. Please

confirm.

As per tender Specification.

Page 20: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Land Acquisition Status General 1. The co-ordinates of proposed PSS locations as provided in tender

are:

PPS-1 27o 32‟ 36.68” N 72o 14‟ 30.52” E

PPS-2 27o 34‟ 10.15” N 72o 13‟ 10.70” E

PPS-3 27o 35‟ 15.41” N 72o 13‟ 53.23” E

PPS-4 27o 36‟ 1.16” N 72o 14‟ 23.65” E. Please confirm whether the land of the proposed Substation project

sites under this package are already occupied by RSDCL and ready

for construction.

Yes, the land of the proposed

Substation project sites under this

package is already acquired by

RSDCL.

Land Acquisition Status General We understand that after award of the contract, incumbent free land

will be handed over by RSDCL to the successful bidder for

construction of substations.

Yes, off course.

Land Acquisition Status General Please confirm that the scope of necessary approvals from Forest

Department, Highway Authorities, Pollution board and other

statutory authorities if required during construction of the project,

shall be excluded from the scope of the bidder.

All clearance shall be in the scope of

bidder.

Mandatory Spare and

Recommended Spares

General 1. Mandatory spares are not asked in BOQ 1 Supply schedule as well

as in Equipment Specific specifications. We presume that bidders

dont have to include the prices of spares in their quoted price. please

confirm.

2. Incase if the rates of spares are to be quoted, request RSDCL to

provide the equipment wise list of spares along with Quantity so that

all bidders are through and in parity with RSDCL Requirement.

As per tender Specification.

Process for registering New

Makes for approval

General 1. We request you to kindly allow the bidders to source the

Equipment / Materials from Reputed makes other than the list of

approved makes provided with tender specification, who shall meet

the Manufacturers qualification criteria as per Tender.

Equipment / Materials from such reputed makes shall be supplied

only after taking prior approval from RSDCL.

As per tender Specification.

Drawings General Requesting for following drawings since same are not provided in

Tender specifications

1. Contour Map

2. Boundary Wall

3. Equipment Foundations, Structure Foundations

4. Internal Road and Approach road Drawings.

Enclosed.

Page 21: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Technical Specifications

required

BoQ 1 Supply

Schedule

1. Sl. No. 2.29 33 kV HG Fuse.

2. Sl. No 2.30 11 kV HG Fuse

3. Sl. No. 3.17 Lighting Distribution Board

4. Sl. No. 3.18 Outdoor AC Distribution Box:(i) For 220kV Bays: 1

I/C 100A & 12 O/G 16A

5. Sl. No. 3.19 Outdoor AC Distribution Box:(ii) For 33kV Bays: 2

I/C 100A & 24 O/G 16A

6. Bus Bar Materials - Clamps and connectors and Hardware

accessories

7. AL-59 conductor, ACSR Panther Conductor, AAC Tarantula

conductor

8. Sl. No. 6 LT Power Cable (Aluminum)

9. Sl. No 11.05 48 V, 50/100 Amp, SMPS based battery charger

with N+1 configuration suitable for VRLA maintenance free

batteries.

10. Sl. No 11.07 48 V DCDB

Conductors specification enclosed.

Other material shall be supplied as per

standards.

Page 22: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s L&T Contruction,

Chennai.

Ref: Your e-mail dated 11.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

8

Clause Ref. Bidder’s Query RSDCL’s Comments

Vol. I

IFB 2.ii

Bid Security clause is mentioned as 80% in BG form & 20% in DD form or

bidder may furnish entire Bid Security in DD Form/Banker's Cheque.

We request to amend the clause to submit the Bid Security in BG form for the

complete value, which is generally accepted by all Central/State utilities. Kindly

consider our request.

As per tender specification.

Annexure VIII Please confirm that Bid security in form of BG shall be printed on non-judicial

Stamp Paper of Rajasthan Government of worth INR 100.00. Please confirm.

As per the applicable norms of Rajasthan Stamp

Authority.

General Kindly share the existing soil strata reports as Civil items are lumpsum basis &

to assess the soil condition on principle basis

Soil report enclosed.

General Kindly provide the Bank details, IFSC Code etc of RSDCL for availaing Bank

Guarantee

RSDCL Bank Details are as under:

Bank: Oriental bank of Commerce

Branch: RSAMB, Jaipur

Account No.: 11331131000550

IFSC code: ORBC0101133

General Kindly confirm the both BG Mode (Normal & SFMS) is acceptable by RSDCL Both modes are acceptable.

GCC 34.7.3

Annexure II

Advance BG shall be valid upto 90 days beyond Schedule commissioning/TOC

Date.

We request to kindly consider the BG Liquidation plan on pro-rata

basis/advance adjustment on every quarter.

As per the tender specification.

GCC 34.7.3 In case, the Contractor opts for this interest bearing advance, the same shall be

paid to the Contractor on fulfillment of above conditions and an interest on

monthly outstanding amount will be charged at the rate of 9.5 % per annum.

We request to amend the clause for interest rate as equal to SBILR which is

followed by PGCIL & other utilities. Kindly confirm

It will remain same as per the tender specification.

GCC 13 The contract shall be considered as having come into force from the date of the

Notification of Award unless otherwise provided in the Notification of Award.

We request you to consider the effective date as only from the date of complete

handing over of encumbrance free land to the Successful bidder/Contractor.

It will remain same as per the tender specification

Page 23: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

GCC 13 We request M/s. RSDCL to provide the four corners of location of the land and

coordinates of the proposed substation locations.

Coordinates of all four pooling stations are available

in tender document.

ITB 15.6 We understand that 1% BOCW cess shall be applicable only on the Civil &

Installation works. Please confirm.

It will be deducted as per the applicable norms of

Rajasthan State and BOCW Cess Act.

GCC 20 We presume that the amount of aggregate liability of the bidder to PGCIL shall

be 100% of the contract price. Kindly confirm

As per the tender specification.

GCC 33 Price Variation "Firm" for all items.

We request to consider Price variation for major items like Transformer,

Reactor, Cables, Structures, Civil concrete, and Reinforcement & Installation

items. Kindly confirm

It will remain same as per the tender specification.

SCC 11.0 Quantity variation is applicable to any extent on individual items.

Kindly restrict the limit of Quantity Variation for this contract and which is

followed in PGCIL as 15% limit or kindly provide the modality for variation of

more than proposed percentage.

It will remain same as per the tender specification.

General Kindly provide the details & status of Incoming lines/outgoing Lines for the

Substations (PPS -1,2,3& 4)

Already given in Tender Specification.

Vol. II

Annexure II A

List of Apprved Vendors as per RVPN for Major SS Equipments

We request M/s RSDCL that to consider PGCIL/State utilities approved vendors

for supplying the major equipments. Kindly confirm

As per tender specification.

Vol. II

General

Kindly clarify the scope limit between EPC contract for Park pooling SS &

Solar Contract (Interface, if any)

The scope shall be as per tender specification.

Bid price schedule

sl.no. 2.16

As per referred item, 24Nos. 33kV CT/PT junction boxes are mentioned.

However, as per sl.no. 2.14, 2.15 & 2.21, the quantity of 33kV single phase CT

is 204Nos. (96+138) & 33kV single phase PT is 72 Nos. Accordingly, CT

Junction Box - 68 Nos& PT Junction Box - 24 Nos are required. Kindly check

& confirm the requirement.

As per BOQ.

Bid price schedule sl.no.

2.17

As per referred item, 36 Nos. of 30kV Lightning Arrester are mentioned.

However, as per SLD of PSS-1, 2, 3 & 4, 30kV LA is required for all

transformer incomer bays & station transformer bays. Accordingly each PSS

will have 12# of 30kV LA & hence total, 48 # of 30kV LA's are required.

Kindly check & confirm.

As per BOQ.

Bid price schedule sl.no.6 i) As per referred item, only two power cable sizes i.e., 3.5 core x 300 sq.mm &

3.5 core x 35 sq.mm are mentioned. Please check and include other cable sizes if

required.

ii) And also, there is no detailed specification for LT Power cables in the tender

document. Kindly check & furnish the same by including the type of insulation,

inner & outer sheath and armour.

Power cables shall be only of two types as mentioned

in the specifications.

Page 24: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Bid price schedule sl.no.

3.15

As per referred item, it is mentioned that 220V DCDB (with 2 Nos. I/C & auto

change over facility) shall be provided. We understand that that each

distribution board shall be provided with 2 incomer (1 each from battery and

charger). Please confirm.

As per tender specifications.

Bid price schedule sl.no.

4.01 & 4.02

As per referred item, it is mentioned that

i) Single tension hardware for AL-59 Eq. wt. zebra (bolted type)

ii) Single / Double tension hardware for AL - 59 Eq. wt. zebra (bolted type)

However, In Section-I, clause no.2.0, II, AL-59 conductor (Moose equivalent)

is mentioned.

As there is a discrepancy in the above mentioned clauses, Kindly confirm the

requirement.

Please refer the BOQ.

Bid price schedule sl.no.

3.18 & 3.19

Kindly clarify the purpose of Outdoor AC distribution box given for 220kV &

33kV bays & provide the detailed specification for the same.

It is as per site requirement.

Bid price schedule sl.no.

11.06

As per referred clause, the rating of 48V battery is mentioned 360/600AH.

Please clarify the rating to be supplied under this package i.e. 360AH or 600AH.

Further, if 600AH is required, please furnish technical specification for the same

as in the tender documents specification is available only for 360AH.

The rating of 48V battery will be 360 AH.

Bid price schedule

sl.no. 2.01

As per referred clause, 5% spare oil shall be provided for each 220/33kV,

100MVA Power transformer. However, in Section-II, transformer specification,

clause no. 1.18.3, the quantity of spare oil shall be 10%. As both the clauses are

contradicting, please confirm the actual spare requirement.

5% spare oil shall be supplied for each 220/33kV,

100MVA Power transformers and reactors.

Bid price schedule

Line item for 220kV CT/PT Junction box is not appearing in the bid price

schedule. Please check & include the same in the revised the bid price schedule.

As per tender Specification.

Vol. II Section I Pg No:5,

Cl.2.0, System Short

circuit current

Please specify the short circuit duration for both 220kV & 33kV system.

As per tender Specification.

Volume - II, Section-II,

CRP specification Pg

No:52, cl.no. 9.5.7.1 &

9.5.7.2

We understand the following from the referred clause & BPS line item No. 11 &

12:

a) For remote end tripping of each line the Main Protection-1 shall be through

FOTE whereas the Main Protection-2 shall be through PLCC.

b) Speech & Data shall be through PLCC & FOTE

Please confirm.

As per tender Specification.

Volume - II, Section-I,

scope Pg No:133, cl.no.

15, Annexure-I, Sl.no. 11

As per the referred clause, 4 sets of PLCC equipment shall be supplied at the

remote end stations. As there are 10No. 220kV lines (in 4 substations together),

please clarify the availability of remote end PLCC for the balance lines. If the

PLCC at remote end is already existing, please furnish the make & model

number of the existing PLCC.

As per tender Specification.

Volume - II, Section-I,

scope Pg No:133, cl.no.

15, Annexure-I, Sl.no. 11

As per the referred clause, we understand that 4sets of PLCC equipment shall be

supplied at the remote end stations. We presume that the existing 48V DCDB

shall have adequate spare feeders for extending DC supply to the PLCC panels.

Further the power cables from the existing DCDB to the PLCC panels shall be

All required material for completion of substations

shall be in the scope of bidder only.

Page 25: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

in other's scope. Please confirm whether Bidder's understanding is in order.

Volume - II, Section-I,

scope Pg No:133, cl.no.

15, Annexure-I, Sl.no. 12

As per the referred clause, we understand that 4sets of FOTE equipment shall be

supplied at the remote end stations. We presume that the existing 48V DCDD

shall have adequate spare feeders for extending DC supply to the FOTE panels.

Further the power cables from the existing DCDB to the FOTE panels shall be

in other's scope. Please confirm whether Bidder's understanding is in order.

All required material for completion of substations

shall be in the scope of bidder only.

Volume - II, Section-I,

scope Pg No:133, cl.no.

15, Annexure-I, Sl.no. 12

The number of teleprotection cards as given in the BPS for the respective

pooling stations & remote end stations are not matching with the number of

220kV lines. Please check and confirm.

As per tender Specification.

Volume - II, Section-I,

scope Pg No:133, cl.no.

15, Annexure-I, Sl.no. 11

& 12

As per referred clause, PLCC & FOTE shall be provided at remote end

substation. Hence, please provide the distance between proposed Nokh Park

substation to each remote end substation.

The distance between pooling stations shall vary

from 1.8 Km to 6.5 Km

Volume - II, Section-II,

CRP specification

Pg No:27, cl.no.

5.2

As per referred clause, it is stated that combined bay protection and control unit

shall not be acceptable.

However, as per item no.13, Page no,70, BCPU shall be provided for 33kV twin

feeder. In this regard, we understand that combined BCPU is not acceptable

only for 220kV system. Please confirm.

Yes.

Volume - II, Section-II,

CRP specification

Annexure-V2-P3-

S1-1, Item No. 7

As per referred clause,

i) Bay protection unit - 1 No.

ii) Bay protection unit (Main Protection as per cl.no.9.4) (Main-II) -1No.

iii) Back up protection i.e. directional overcurrent & earth fault protection as per

cl.no. 9.4.4 of specification -1 set shall be provided for reactor protection.

However, under cl.no. 9.4, only specification for transformer protection is

mentioned. Kindly check & provide the Protection requirements for reactor bay.

As per tender Specification.

Volume - II, Section-II,

CRP specification

Annexure-V2-P3-

S1-1, Item No. 12

As per referred clause, peripheral unit &central unit shall be provided for 9 Bays

+ 1 future bay. This is not matching with the number of bays as shown in the

Single Line diagram. Further, there are no future bays shown in the SLD &

layout drawing. Hence we understand that bay units shall be provided only for

present bays under this package.

As per tender Specification.

Volume - II, Section-II,

CRP specification

Annexure-V2-P3-S1-1,

Item No. 12

(applicable for all stations)

Since all control & relay panels are located in the control building, We propose

centralized busbar protection. Please confirm acceptance.

As per tender Specification.

Volume - II, Section-II,

CRP specification

Annexure-V2-P3-

S1-1, Item No. B

As per referred clause, accuracy class of Multifunction meter shall be 0.5.

However, as per bid price schedule, sl.no.2.09, accuracy of CT shall be 0.2. As

there is a mismatch in the accuracy class, please check & confirm the accuracy

required for both CT & Meters.

As per tender Specification.

Volume - II, Section-II,

CRP specification

As per referred clause, In 220kV system, accuracy class of energy meter shall be

0.2s for Transformer & Line feeder bay and accuracy class of energy meter

As per tender Specification.

Page 26: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Annexure-V2-P3-

S1-1, Item No. B

shall be 0.5S for buscoupler bay. However, as per bid price schedule,

sl.no.2.09, accuracy of CT is given as 0.2. As there are mismatches in the

accuracy class, please check & confirm the accuracy required for both CT &

Meters.

Volume - II, Section-II,

CRP specification

Annexure-V2-P3-

S1-1, Item No. 13

As per referred clause, In 33kV system, accuracy class of energy meter shall be

0.2s for Transformer & Line feeder bay and accuracy class of energy meter

shall be 0.5S for buscoupler bay. As there is a mismatch in the accuracy class,

please check & confirm the accuracy required for both CT & Meters.

As per tender Specification.

Volume - II, Section-II,

CRP specification

Annexure-V2-P3-

S1-1, Item No. B

As it is a SAS based system, we do not envisage separate control panels with

mimic, switches & alarms. Only BCU based relay panels shall be provided for

control & protection. Please confirm.

As per tender Specification.

Volume - II, Section-II,

CRP specification

clause no.

9.7.3.2.xv

As per referred clause, built in LBB protection for each feeder shall be provided.

However, Annexure-V2-P3-S1-1, configuration of C&R Panels, separate LBB

Protection for each feeder is required. Please confirm the actual requirement.

As per tender Specification.

Volume - II, Section-II,

Power transformer

specification GTP

Please confirm the type of Power transformer i.e. Constant percentage

impedence or Constant ohmic impedence type.

Impedance type.

Volume - II, Section-II,

Power transformer

specification

As there is no requirement of online DGA, Fiber optic temperature sensing unit,

Digital RTCC, Automatic Voltage regulating relay (AVR) mentioned in

Specification/ Bid price schedule, we are not envisaging these items in our scope

of supply. Please confirm.

As per tender Specification.

Volume - II, Section-II,

Power transformer

specification cl.no.

1.26.4 & 1.33.1

As per referred clause, Type test & short circuit test report of 220kV transformer

shall not be older than 7 years. We understand that if Valid type test reports are

submitted then the repetition of type tests on the first unit of transformer as

mentioned in clause No. 1.26.4 is not required. Please confirm.

As per tender Specification.

Volume - II, Section-II,

25MVAR reactor

specification cl.no.

5.2.3

As per referred clause, Type test report shall be carried out on first unit of shunt

reactor. We propose that if Valid type test reports are submitted then the

repetition of type tests as mentioned in cl.no. 5.2.3 is not required. Please

confirm.

As per tender Specification.

Volume - II, Section-II,

Power transformer

specification cl.no.

1.23.6

As per referred clause, For 220kV bushing, condenser oil filled type (OIP) shall

be provided. However, in annexure-3, Page 143 given in reactor specification,

RIP Bushing for transformer application is mentioned. We presume that the

above mentioned application is typographic error and OIP bushing shall be

followed for 220kV Bushing of 220/33kV Power transformer. Please confirm.

As per tender Specification.

Volume - II, Section-II,

Reactor specification

cl.no. 3.4.1

As per referred clasue, un-used uninhibited insulating oil shall be provided for

25MVAr bus reactor. However, for 100MVA Power transformer, type of oil is

not mentioned. We presume the same shall also be uninhibited type similar to

reactor. Please confirm.

As per tender Specification.

Volume - II, Section-II, As per referred clause, it is mentioned that reports for the type test & short It shall be of same rating.

Page 27: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Power transformer

specification cl.no.

1.26.4

circuit test conducted on the equipment similar to those proposed transformer to

be supplied. We understand that 'similar' shall refer to the test reports of same or

higher rating (voltage & capacity) transformers. Please confirm.

Volume - II, Section-II,

Power transformer

specification cl.no.

1.26.4.b

As per referred clause, it is mentioned that in case of short circuit test report for

transformer is not available, then bidder may submit data to prove the thermal &

dynamic ability of its transformer to withstand short circuit. We propose to

prove the thermal & dynamic withstand capability of the offered transformers

through calculations only. Please confirm acceptance.

As per tender Specification.

Volume - II, Section-II,

CT & PT specification

Kindly provide the following details for 36kV PT :

i) Type of 36kV PT design (i.e., Live / Dead Tank)

ii) Type of Insulator

Live Tank

Porcelain

Volume - II, Section-II,

245kV CVT specification

cl.no. 5.5

Kindly specify the winding material to be considered for 245kV CVT (i.e.

Copper or Aluminium).

Copper

Volume - II, Section-II,

Outdoor Insulators (2 x

24kV) cl.no. 4

Kindly specify the cantilever strength to be adopted for 33kV Bus post

insulators.

As per relevant IS.

Volume - II, Section-II,

AC & DC LT switchgear

specification

Kindly provide the following details :

i) Tentative AC / DC SLD

ii) As there is no future feeders, we are not envisaging AC & DC feeders for

future bays.

iii) short circuit level & its duration for LT AC & DC boards.

As per standards.

Volume - II, Section-II,

250kVA, 33/0.415kV

station transformer

specification

The losses as mentioned in the specification for distribution transformers are not

in line with the revised loss figures issued in Gazette vide Amended notification

to (IS-1180) dated 16-Dec-2016. In this regard, please clarify whether the losses

as per the above notification are to be followed or the losses shall be followed as

per specification.

Losses mentioned in the Specification or of better

figures shall be accepted.

Volume - II, Section-II,

Technical specification for

Ball & Socket type 11kV

45kN,70kN & 120kN Disc

insulators

We propose Polymer type long rod insulators for 220kV & 33kV tension &

suspension strings in place of disc insulators. Please confirm acceptance.

As per tender Specification.

General Kindly furnish Plot boundary with all corner co-ordinates for Nokh solar park

220/33kV PPS-1, 2, 3 & 4.

Co-ordinates for PPS-1, 2, 3 & 4 are provided in the

Specification.

Single Line diagram for

Nokh solar park 220/33kV

PPS-1 ,2, 3 & 4

Kindly provide following for 220kV & 33kV system for pooling stations-1, 2, 3

& 4.

i) Main busbar current rating

ii) Main busbar short circuit duration

As per tender Specification and relevant standards.

Electrical Layout plan for

Nokh solar park 220/33kV

PPS-1 ,2, 3 & 4

As there are certain discrepancies in the room dimensions between the overall

layout & control building layout, we presume that the dimensions as per control

building layout (Drg. No. RSDCL/MCL/C39A/GSS-I/007) shall be followed for

Yes.

Page 28: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

& Control room ground

floor plan for GSS-1

control building. Please confirm.

Electrical Layout plan for

Nokh solar park 220/33kV

PPS-1 ,2, 3 & 4

& Control room ground

floor plan for GSS-1

In the layout drawing a Note stating "33kV CT-PT & LAs for 33kV feeders in

outdoor kisoks are in NTPC scope" is indicated. We understand that Line side

CT & PT (for tariff purpose) & LA for each feeder are in NTPC scope. The CT

required for bay metering & protection is in the scope of this package. Please

confirm.

Yes.

Electrical Layou Section-

33kV Feeder bay (typical)

In the section view, 33kV CT for bay protection and kiosk with 33kV CT, PT &

LA (NTPC scope) are not shown. We request RSDCL to provide a revised

section incorporating all the bay equipment.

ELP provide in the Specification.

Electrical Layout plan for

Nokh solar park 220/33kV

PPS-1 ,2, 3 & 4

Kindly furnish the dimensions of the following facilities:

i) Parking area

ii) Garden

iii) Store shed

iv) Meter room

iv) Guard Hut

v) U/G Water tank

As per Specification.

Structural Layout plan for

Nokh solar park 220/33kV

PPS-1 ,2, 3 & 4

In the structural layout plan, C-type, D-type & Ax-type cable trenches are

shown. Please provide the cross-section view for each of these trench types.

Enclosed.

Section-III

Work of Laying of

substation earthing

Annexure-A sl.no. v.a

As per referred clause, it is mentioned that earthing conductor in outdoor areas

shall be buried at least 600mm below finished ground level. However, in Page

no. 382, B. Earthing procedure, it is mentioned that the Laying of Earth Mesh of

MS rod shall be at a depth of 800mm. As both the clauses are contradicting with

each other, please confirm the actual requirement.

As per Specification and site requirement.

Volume - II, Section-II,

220V & 48V Battery

specification cl.no. 3.0

As per referred clause, Back up duration for 220V & 48V battery shall be

provided for 8, 24 or 48 hours. Normally it is 3 hours as followed by major

utilities like PGCIL. Please check and clarify the actual back up duration to

check the adequacy

As per Specification.

Volume - II, Section-II,

Control cable

For LT Power and control cables please specify whether any Fire retarding

properties are required. If required, please confirm whether FR (or) FRLS type

is required.

As per Specification.

Volume - II, Section-II,

Power transformer

specification cl.no. 1.13.1

As per the referred clause, the following loss figures are mentioned for

transformer:

No load loss - 38kW (Max)

Load Loss - 250kW (Max)

However, as per CEA guidelines ref.no. CEA/PSE& TD/218/3056-4028, dated

01.03.19, Losses for 100MVA, 220/33kV Power transformer shall be as

follows:

No load loss - 43kW (Max)

Load Loss - 245kW (Max)

As per Specification.

Page 29: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Auxiliary loss - 5kW(Max)

We request RSDCL to follow the transformer losses as per CEA guidelines &

issue suitable amendments.

Volume - II, Section-II,

Power transformer

specification cl.no. 1.13.1

As per the referred clause, the following loss figures are mentioned for

transformer:

No load loss - 38kW (Max)

Load Loss - 250kW (Max)

However, Auxiliary loss is not mentioned in specification for Power

transformer. Kindly provide the same.

As per Specification.

Volume - II, Section-II,

Reactor specification

cl.no. 2.7

As per referred clause, loss capitalization for 25MVAR reactor is indicated.

However, there is no maximum losses mentioned in reactor specification. But

for transformer, maximum losses are mentioned. Please clarify the following

w.r.t transformer & reactor:

a) Whether loss capitalization is required for transformer & reactor?

b) If required, please provide the loss capitalization figures for transformer also

c) If not required, please provide the maximum loss values for reactor

As per Specification.

Volume - II, Section-II,

Reactor specification

cl.no. 3.3.7

As per referred clause, fiber optic sensors shall be embedded in each phase of

the winding located at hottest spot of 25MVAR reactor. In this regard, we are

not envisaging any FO sensors for Power transformer as there is no requirment

for the same in Power transformer specification. Please confirm. If required for

transformer, please furnish detailed specification for the same.

As per Specification.

Volume - II, Section-II,

Reactor specification

cl.no. 3.3.7

As per referred clause, fiber optic sensors shall be embedded in each phase of

the winding located at hottest spot of 25MVAR reactor. In this regard, please

clarify/furnish the following:

a) Requirement of Fiber optic temperature monitoring system.

b) Number of sensors to be embedded in each reactor

c) Technical specification for Fiber optic temperature sensing system

As per Specification.

Part-II, General conditions

of contract cl.no. 34.7.8

As per referred clause,it is mentioned that the type test certificates should not be

older than 7 years as on the date of Technical bid opening for which the date of

conducting of test shall be considered. However no separate type test charges

shall be paid to the bidders.

However, the reactor specification does not calls for submission of test reports.

As per cl. no. 5.2.3 of reactor specification, type test shall be carried out on first

shunt reactor. Please check and clarify whether type tests need to be repeated for

reactor or only type test reports are sufficient.

No separate type test charges shall be paid to the

bidders.

Type test reports are required to be submitted for

reactors and type tests shall be carried out on first

shunt reactor as per specification.

Volume-II, Section-III

Work of Laying of

substation earthing

Annexure-A sl.no.6

As per referred clause, it is mentioned that each riser to the structures be bolted

by two bolts to the structure leg. In this regard, we propose welded connections

for structure earthing as followed by all major state and central utilities. Please

confirm acceptance.

It may be discussed at the time of work execution.

Volume-II, Section-III

Work of stringing of bus

As per referred clause, it is mentioned that 45/70kN disc insulators shall be used

for 33kV suspension string. In the Bid price schedule there is no line item

As per BoQ.

Page 30: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

bar and earth wire and

jumpering sl.no. I.c

Table

available for 45kN disc insulators. Hence we understand that 70kN shall be

followed for 33kV suspension string insulators. Please confirm.

Volume-II, Section-I,

Annexure-II(A) sl.no. 11

As per referred clause, the approved relay makes are ABB/ SIEMENS/

AREVA/ GE. But as per Section-II (Tehnical specification for 220kV & 33kV

control & protection panels), ANNEXURE –V2-P3-S1-1, in the approved make

and model of relays, ABB, Siemens, GE, Schneider, SEL, Sifang and ERL are

also mentioned. Hence, we presume that Bidder can choose from the makes

indicated in the Section-II, technical specification. Please confirm.

As per Specification.

Volume - I

Bid price schedule sl.no.

4.07

In the referred line item of BPS, 70/90kN disc insulators are mentioned. But in

specification, Volume-2, Section-III, sl.no.I.c, 90kN insulators are not specified.

Please check and confirm the application for the same.

Bidder may also use 90KN disc insulator against

70KN.

Section-II

800A LT Switchgear

Panel specification sl.no.

1.2

As per referred clause, the configuration of LT switchgear shall be as follows:

i) Incomer circuit shall be with one 800 ACB

ii) Outgoing circuit of fuse switch unit 200 Amps

However, in Bid price schedule sl.no. 3.16, 2# of 800A Incomer, 1#

Buscoupler, 2# Outgoing 400A, 6#Outgoing 32A are mentioned. As there are discrepancies in the above mentioned clauses, we presume that the

configuration as per Bid price schedule shall be followed. Please confirm.

As per BoQ.

Section-I

Scope sl.no. 2.0

As per Section-II, Outdoor Insulator specification, Page No.201, sl.no. 4.1,

minimum creepage distance of each 24kV insulator unit shall be 430mm. As

33kV BPI shall be provided with 2Nos. 24kV insulator stacks the total creepage

distance will be 860mm only.

But the Creepage Distance of 33kV system is 900mm (i.e. 25mm/kV).

Please check and confirm the creepage distance of each 24kV insulator.

Creepage distance for 33 kV insulator shall be

900mm and the same shall be followed for 24kV

insulator unit.

Control building layout

(Drg. No.

RSDCL/MCL/C39A/GSS-

I/007)

In the referred layout, LT switchgear room is not shown. In this regard, we

presume Bidder can modify the layout to accommodate the necessary facilities

without changing the overall dimensions of the building. Please confirm.

LT switchgear panel shall be provided in control

room.

Volume III, Section Civil,

Page no: 11& Schedule

BOQ-3(Civil part) Cl. No.

6

As per referred clause, The approach road is in scope of bidder.

However in technical specification the approach road type, length, width &

Detail specification not speicifed.

kindly provide the above details for approach road in order to estimate the

quantum of work. also include the separate item for the same in price schedule.

All the roads shall be of 3m and 4m wide.

Volume III, Section Civil,

Page no: 11 Cl. No: 5,

Point (9)

As per referred clause, It is mentioned that, "Invert of the drainage system shall

be decided in such a way that the water can easily be discharged above in High

flood level(HGL) outside substation boundary at suitable location upto a

maximum 50M beyond boundary wall of substation or actual whichever occurs

earlier and approved by Owner". Since the drain item is paid as LOT item.

Please furnish the HFL, to estimate the drain quantity.

The drainage system shall be developed in the

substation premises as per site location along the

outer road of switchyard.

Volume III, Section Civil, In technical specification it is not mentioned that, Drain shall be provided on One side of outer road of switchyard.

Page 31: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Page no: 11 Cl. No. 5 both side of road (or) one side of road.

We propose to provide the drain on one side of substation road. Please confirm.

Price schedule, Schedule –

3 Sl.no : 2

Based on price schedule, the site levelling is in bidders scope.

We trust that, the site levelling is to be done for the entire area with in plot

boundary.

please confirm.

Yes.

Price schedule, Schedule -

3 Sl. no : 2

Please provide the proposed FGL Level of Each SS since this item is mentioned

as Lot basis in Price schedule

FGL is generally maintained about 100mm to

150mm above the level of approach road.

Volume III, Section Civil,

Page no: 24 & Schedule

BOQ-3(Civil part)

18.8

In technical specification & price schedule, the RCC Grade is mentioned as

M20.

We propose to use RCC M25 instead of RCC M20, to optimize the design

requirement.

Please clarify.

As per specifications.

Price schedule, Schedule -

3 Sl.no : 2

As per referred clause, it is mentioed that "Site preparation including cutting,

filling of earth and leveling, dressing of complete substation area as per the

contour maps, enclosed with volume- III".

However in tender document (volume III) the same is not enclosed.

please provide the same.

Enclosed.

Price schedule, Schedule -

3 Sl.no : 43

As per referred clause, it is mentioed that "Construction of store shed as per

drawing attached with the specification".

However in tender document the drawing of store shed is not attached.

kindly provide the same. Inorder to estimate the quantum of work.

Enclosed.

Volume III, Section Civil

cl.no : 10

As per referred clause, it is mentioed that "A security room (Guard hut) shall be

constructed at the entrance of each GSS. The minimum dimension of the room

and associated toilet and pantry etc. is given on the drawing.".

However in tender document the drawing of security room is not attached.

kindly provide the same in order to estimate the quantum of work.

Enclosed.

Electrical layout plan -

NOKH SOLAR PARK

220/33KV PSS 1,2,3 & 4

As per referred layout, the meter room is shown near the LT trafo. However in

price schedule and technical specification there is no item for meter room.

Please include the same if required.

Item already in BoQ.

General Please confirm the requirement of fire detection system for control room

building. If required please include the same in Price schedule and provide the

specification.

Not required.

General We presume that there is no requirement of water based fire protection system

for sub station. Please confirm.

Yes.

Page 32: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Bajaj Electricals Ltd.,

Mumbai.

Ref: Your e-mail dated 11.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

9

Clause Ref. Bidder’s query/comment RSDCL’s Comments

General As per pre-bid meeting discussion, kindly provide Plot and orientation of

proposed substations to calculate land development cost.

Bidder may refer ELP.

General

As per pre-bid meeting discussion, kindly provide FGL criteria of proposed

substations to calculate land development cost.

FGL is generally maintained about 100mm to 150mm

above the level of approach road.

General

As per pre-bid meeting discussion, kindly provide Design (various loading)

& Drawings of structure in proposed substations for foundation design.

Enclosed.

"Price schedule sec-3,

Item no. 28,29,30,31"

As per pre-bid meeting discussion, kindly provide specification or drawing

of the trench types mentioned in the price schedule as Type Ax, A, C, D.

Enclosed.

General

As per pre-bid meeting discussion. kindly confirm construction of drainage

is as per design.

The drainage system shall be developed in the substation

premises as per site location along the outer road of

switchyard.

Civil Works Tech Spec-

7.1, sl.no. 4

Pg no.12

As per pre-bid meeting discussion. We are considering foundation plinth

400mm and 1000mm for building foundation (As per technical

specification) above FGL. Kindly confirm

Yes.

Civil Works Tech Spec-

v7.1, sl.no. 5

As per pre-bid meeting discussion. We are considering 150mm thick Lean

concrete M7.5(1:4:8) below foundation as per technical specification.

Kindly confirm

Yes.

Civil Works Tech Spec-

v7.1, sl.no. 5

As per pre-bid meeting discussion. We understand that 300mm thick quarry

rubbish/murrum under the underground structures, foundations and cable

trenches is only required if black cotton soil is identified during soil

investigation. Please confirm.

300mm thick quarry rubbish/murrum are required due to

loose soil.

Civil Works Tech Spec-

v7.1, s.no. 5

Please provide the level above the FGL of Internal substation road and

approach road.

FGL is generally maintained about 100mm to 150mm

above the level of approach road. Level of Internal road

shall be at the level of switchyard foundation.

Price schedule schedule-

C, Item no. 5,6,7

As per Pre-Bid meeting, we are considering given 4 meter wide road as Yes.

Page 33: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

approach road and internal road. It also include earth filling. Kindly confirm

General Please confirm that the drainage if required outside proposed substation

area alongside approach road will be paid seperately.

The drainage system shall be developed in the substation

premises as per site location along the outer road of

switchyard.

General Please clarify the requirement of firewall between the transformers. If

required, please include the separate line item in the price schedule for the

same.

Not required.

Civil Works Tech Spec-

sl.no. 10

As per pre-bid meeting discussion, kindly provide drawing of security hut,

store shed and other standard drawings.

Enclosed.

Civil Works Tech Spec-

sl.no. 11

The thickness requirement for brickwork is mentioned 350mm in the

technical specification whereas generally 230mm is provided. Please

confirm that 230mm thickness of brickwork can be used for the boundary

wall.

As per specification.

Bid Price Schedule In BOQ, Sr.No-2.03 & 2.04, The Rated short circuit Current for 220 kV

SF6 Breaker & Isolator is mentioned as 40 KA for 3 Sec. But In Sr.No-2.09

, The Rated short circuit Current for 220 kV CT is mentioned as 40 KA for

1 Sec Current Transformer.

Kindly Clarify

As per specification.

Bid Price Schedule 20 No. of 33kV CT Junctions boxes and 6 No. of 33kV PT Junction Boxes

are Required for Per PSS.

But in BOQ, Sr.No- 2.16, 6 No. of 33kV CT/PT Junction boxes are

Provided per PSS

Kindly Clarify

As per BoQ.

Bid Price Schedule Junction Boxes for 33kV CT & PT are Provided in Price Schedule but for

220kV CT & CVT Junction boxes are not provided in Price Schedule

Kindly Add in Price Schedule

As per BoQ.

Bid Price Schedule In BOQ, Sr.No-2.22, 14 No.sof 33kV Isolators without Earth Blade

(2500A,31.5kA for 1 Second) are given Per PSS. But as per SLD, 12 No.s

of Isolators without Earth Blade are Required Per PSS.

Kindly clarify.

As per BoQ.

Technical Specification In Technical Specification of Page No-129 ,CL No-2 and Point No-II, It is

mentioned that 33kV Auxillary Bus Bar Arrangement shall be on Single

Tarantulla conductor but in sectional layout of Page no-602, for 33kV

Auxiliary Bus Bar Arrangement shall be on Twin Tarantulla condcutor.

Kindly confirm

Auxillary Bus Bar shall be of Single Tarantulla.

Bid Price Schedule&

Technical Specification

We understand that 33kV Outgoing Arrangement is not in our scope.

Kindly Clarify

Scope of work shall be as per specification.

Page 34: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Technical Specification In SLD , It is mentioned that 33kV CT-PT are in NTPC Scope but in

Electrical Layout, 33kV CT-PT Set & LA's for 12No.s 33kV Feeders in

Outdoor kisoks are mentioned in NTPC Scope.

Kindly Clarify the scope

Scope of work shall be as per specification.

Technical Specification Kindly Provide Technical Specification of conductor as required for this

tender.

Conductor specification enclosed.

Bid Price Schedule Quantity of PLCC & FOTE Equipments are mentioned for PGCIL 765kV

Bhadla II GSS.

Kinldy elobrate the scope of work involved for PGCIL 765kV Bhadla II

GSS

As per BoQ.

Bid Price Schedule In BOQ, Sr.No-1.12 , 8 No.s of Wave Trap Structure are Provided. But in

BOQ, Sr.No-11.08, 4 Nos of Wave Trap are Provided.

Kindly Clarify

As per BoQ.

Bid Price Schedule In BOQ Sr. No-4 (4.01 to 4.03) Hardware is mentioned as Zebra Equivalent

Weight where as Conductor is of AL-59 Equivalent Moose Kindly clarify.

Conductor is AL-59 Moose Equivalent and Equivalent

Weight Zebra

Bid Price Schedule In BOQ Sr. No-4 (4.04 to 4.05) Hardware is mentioned as Suitable Twin

Tarantulla conductor Where as in section -III 33KV Auxillary bus is of

Single Tarantulla. Kindly confirm if hardware suitable for Single Tarantulla

Conductor have to be considerd in Same Boq Item.

As per Bus arrangements.

Bid Price Schedule In BOQ Sr. No-11 (11.08) Wave trap Specification is of 0.5mH/1600A

Where as in technical Specifcation it is provided as 0.5mH/1250/2000A.

Kindly clarify the requirement

As per BoQ.

Layout/ EKD For 33KV Type of Structure Details not provided in Layout Drawing/

Section Drawing. Kindly provide.

Please refer ELP.

Technical Specification Technical Specifications of AL-59 Equivalnet Moose Conductor and

Tarantulla Conductor Specifications not provided in Technical

Specification.

Enclosed.

Earthing Kindly provide Soil Resisvity details of all 4 Substations Enclosed.

Volume I part 1

ITB Cls.no 15. 2

All taxes & other levies except GST in respect of the transactions between

the owner and the contractor under the contract.

As informed in Pre-Bid meeting, client will pay 100% GST at actual after

submission of invoice. Kindly confirm

As per Govt. provisions.

Volume I part 1

ITB Cls.no 2.1 (i)

As per pre-bid meeting discussion, contractor's can provide undertaking if

they want to introduce new vender who is meeting technical/qualifications

criteria of tender documents. Same can accept. Kindly confirm

Bidder has to meet the qualifying requirement as per the

specification.

Volume I part 1

SCC Cls.no 35.3 & 35.4

As per mentioned clause and confirmed in pre-bid meeting , contract will

award to only single contractor not to multiple contractors as mentioned in

said clause. kindly accept

As per specification.

General As confirmed in pre-bid meeting, we can charge the substation with 220KV

side for commissioning and taken over purpose. If solar energy is not ready

at the time of commissioning. Kindly accept.

We may charge substation from 220KV side for

commissioning purpose.

Page 35: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Volume I part 1

ITB Cls.no 23.3

As per mentioned clause, Bid Security (EMD) need to submit in form of

DD &BG. Kindly accept total EMD value in BG only.

It will remain same as per the tender specification.

Volume I part 1

ITB Cls.no 23.3

As per mentioned clause, EMD BG on the Rajasthan State Non Judicial

Stamp Paper of Rs.100/- (or as per GoR rules).

Kindly provide the exact value or else the GoRrules(document).

As per the applicable norms of Rajasthan Stamp Authority.

Volume I part 1

ITB Cls.no 23.3

To generate the BG, we required some more details as per recent changes in

banking sector to issue any BG. Following details required.

1. Bank name

2. Account number

3. IFSC code

RSDCL Bank Details are as under:

Bank: Oriental

bank of Commerce

Branch: RSAMB, Jaipur

Account No.: 11331131000550

IFSC code: ORBC0101133

Volume I part 1

ITB Cls.no 23.3 Kindly provide details of preferred bankers for bank guarantee.

Scheduled Banks of RBI.

Volume I part 1

ITB Cls.no 23.6

As per mentioned clause, it is mentioned bid security of the successful

bidder will discharge after execution of Contract Agreement and furnishing

of Security & Performance Guarantees. Kindly provide exact duration.

As per tender specifications.

Volume I Part 3

SCC Cls.no 11

As per metioned clause, owner indicated quantity may vary upto any

extent without any change in unit price. In pre-bid meeting, same was

discussed to make some limitation/capping of 5% of the total contract

value. Kindly confirm.

As per tender specifications.

Volume I Part 3

SCC Cls.no 11

As per mentioned clause, we understand this variation of quantity by owner

should be in contract period only. (15 months) kindly confirm.

Contract including variation, if any has to be completed

within the period mentioned in the specification.

Volume 1 Part 3

SCC

As per mentioned clause, contractor has to place 3 expert engineers in each

PPS who can handle initial operations and shall run the substation along

with RSDCL.

We presume scope is not including any periodic preventive maintenance

and security of those PPS. if such scope is included, given information is

not sufficient.

Kindly elaborate exact scope.

The scope shall be as per specification.

Volume 1 Part 2

GCC Cls.no 29.1

As per mentioned clause. If desired by RSDCL, the contractor shall

undertake to train free of cost. For the period and the nature of training for

the individual personnel shall be agreed upon mutually between the

contractor and the owner.

We presume that 4 no of engineers from RSDCL can be trained for 2 days

each for major equipments, kindly confirm. Otherwise it is difficult to

estimate.

As per specification.

Volume I part 1

ITB Cls.no 15.8

As per mentioned clause, All contracts/ contractors with the Govt. shall

require Registration of workers under the Building & other Construction

Workers (Regulation of Employment & Conditions of

Service) Act, 1996 and extension of benefit to such workers under the Act.

It will be deducted as per the applicable norms of Rajasthan

State and BOCW Cess Act.

Page 36: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Deductions of cess at source will be made as per provisions of the said

Act, in force from time to time.

From the above we understand that 1% will deduct from service portion of

the contract. kindly confirm

Volume I part 1

ITB Cls.no 38.1

As per mentioned clause, it is mentioned that signing of contract agreement

on Rajasthan State Non- judicial stamp paper of appropriate worth as per

stamp duty applicable in Govt. of Rajasthan along with copy of the order.

Value of those stamp papers is not clear and also as per past records it is

much expensive. so, kindly allow signing of contract agreement/documents

on stamp papers from other states/contractor location.

As per Rajasthan Govt. norms.

General

kindly provide details of limitation of liability & Arbitration clause.

As per arbitration rules.

Payment of lot item we presumed, that progressive payments for LOT items will be paid after

submission of detail BOQ. Kindly confirm

Yes.

Page 37: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s K. Ramachandra Rao Transmission & Projects Pvt. Ltd.,

Hyderabad.

Ref: Your e-mail dated 12.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

10

Clause Ref. Bidder’s query/ comment RSDCL’s Comments

Note – 2

Page No 2

Kindly notify the value of Non Judicial stamp papers which are to be purchased from

Rajasthan State for execution of a Bid Bond of INR 3,87,04,000/-

As per the applicable norms of Rajasthan Stamp

Authority.

2.1- Part –I

Instructions to

Bidders

Most of the EHV Turnkey Substation projects invited and executed by leading Utilities/

PGCIL have Contractual Provisions of Free Issue of Power Transformers and accordingly

bidder‟s experience of having Erected, Tested and Commissioning of Power Transformers besides undertaking Design, Supply ,Erection, Testing & Commissioning major

material/Equipments i.e. circuit breakers, switchyard structures, CTs, PTs, CVTs, LAs,

Isolators, Control & Relay panels including associated Civil Works would be considered as

part of meeting Qualification requirements.

As per specification.

As discussed and mutually agreed in principal during the pre bid meeting the Bidder‟s would need to furnish an Undertaking on a Non Judicial Stamp Paper of Rs 300/- that the Offered

substation equipment shall fully comply with RSPDCL Technical requirements & the

selected Vendors should have made supplies to PGCIL/ NTPC within stupid little time

frame.

In view of this UNDERTAKING there will not be any additional need for furnishing

separate Manufacturing Authorisation from individual substation equipment manufacturers.

Kind confirm.

As per specification. However, RSDCL may

accept the material from approved vendors of

PGCIL subject to furnishing of documentary

evidence in this respect and approved by RSDCL.

15.8 ROYALTY

Kindly clarify the details of Royalty payments to be made to Department of Mines at bidding

stage so that these are factored in the offered pricing.

It is applicable during execution of contract.

17.5 – Time

Schedule

Since the Package bidding requirement is on FIRM PRICE BASIS , deferment of Project

completion Schedule beyond the proposed schedule would entitle Project Executing

Contractor claim price variation AT THE SAME PENALTY RATES AS STIPULATED

vide Clause 14.0 DELAY IN DELIVERY/ COMPLETION. Pl confirm.

Price will be FIRM only.

39 Common for

all type of Bank

Guarantees

Keeping in view the large estimated value of the package, we request you to accept Separate

BGs for

(i) Supply (ii) Erection and (iii) Civil contracts. Kindly confirm.

As per specification.

Part – II-

GCC14.0

DELAY IN

DELIVERY/

COMPLETION

RSPDCL as a Project Developer has rights to impose Penalty in the event of delays in project

completion. However, we seek explicit time lines on the part of RSPDCL thereby ensuring

minimum loss of cycle time for overall project execution:-

Granting approval of Engineering drawings/ GTP-Maximum within 7 days of its submission.

Organizing inspections maximum within 7 days of inspection call and empowering

inspecting officer to accord Dispatch Instructions immediately upon successful completion of

inspection activities at the place of inspection if found all tests passed.

As mentioned in the specification.

Page 38: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

34.3 Due date

for payment

Kindly define specific timelines for the release of payments in the overall interest of project's

quick completion within the stipulated time frame.

(i) Process of bills/Material Receipt at Site - within 3 days of its receipt of materials.

(ii) Release of payments from CPC -Maximum within 10 days from the date of its receipt at

Accounts.

As mentioned in the specification.

We further request you to provide the following;

1 Kindly provide Technical Specifications for Nitrogen Injection Fire Protection system 100

MVA transformer & for 25MVAR reactor.

It will be as per Manufacturer of transformer and

reactor.

2 Technical specification for the 220kv & 33kv CT/PT Junction Boxes required. As per standard.

3 Technical specifications of Street Lighting Poles required. As per standard.

4 Soil Resistivity report of all Four Propose substations is required if available. This is required

to design and arrive at the quantity of earthing material as it is a LOT item

Enclosed.

5 Kindly provide Soil Bearing capacity, Water table / Bore log / Contour drawing / FGL / GPS

coordinates of all 4 substations as these are required to design the Civil foundations of

Control Room & Road, Drain etc., if available. These are required to design foundation for

structures, PTR plinth, control room and other foundations.

Soil report and Contour map enclosed.

6 GTP formats of the Substation Equipments are missing. Kindly provide if available. Technical parameters of all major equipments are

given in the specification. Bidder has to furnish a

confirmation regarding supply of various

equipment/ material as per technical particulars

mentioned in the specification.

Page 39: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Shyam Steel Industries Ltd.,

Kolkata.

Ref: Your e-mail dated 11.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

11

Query RSDCL’s Comments

In your given make list, name of many vendors are appeared either they are closed or not

working presently. We are requesting for acceptance of vendors for this package who are

already approved in others state utilities or PGCIL. Reactors make should be same make

of Transformer. Please confirm.

Approved vendors shall be as per specification. However, RSDCL may

accept the material from approved vendors of PGCIL subject to

furnishing of documentary evidence in this respect and approved by

RSDCL. Reactors makes may be same as of Transformer.

You have asked Value of Performance Guaranty – 1) Security Bank Guarantee -2%

valid up contract completion period ie, 15 months. And Performance Bank Guarantee-

10% till 12 months beyond actual date of taking over. ie, would be valid up to 27 months.

Please clarify.

As per specification.

In the Transformer specifications Voll-II (technical specification) clause no 1.40, you

have mentioned that “ Overall Guarantee period of Transformer & Reactor are 30 months from the date of commissioning or 36 months from the date of supply at site whichever is

earlier. For others items you have asked for 12 months from the date of commissioning or

18 months from the date of Supply whichever is earlier. Please clarify modus of

documents which are to be furnished.

Performance Bank Guarantee for relevant periods is to be furnished.

Detailed Technical Specification for Nitrogen Injection Base Fire Protection system for

100MVA Transformer and 25MVAR Reactors are required.

It will be as per Manufacturer of transformer and reactor.

Technical Specification for 220KV & 33KV CT/PT Junction Boxes are required. As per standard.

Technical Specification of Street Lighting Poles are required. As per standard.

Please arrange to give us Soil Resistivity data of all 4 proposed substations area. Soil report enclosed.

Please arrange to send us Soil Bearing Capacity, water table/bore log,/ contour

drawings/FGL/ GPS co-ordinate of all four substations etc. These are required to design

the civil parts like, foundations/control room/road /drain etc.

Soil report and Contour map enclosed. Coordinates are available in

specification.

ITB Cl. No XIV)-Confirmation of GTP–Please clarify if we have to furnish GTP of

Equipment. If so, please provide the Format of GTP (Only the GTP of Reactor is

available in Technical Specification).

Technical parameters of all major equipments are given in the

specification. Bidder has to furnish a confirmation regarding supply of

various equipment/ material as per technical particulars mentioned in the

specification.

Request for consideration of price variation clauses as per IEEMA instead of firm price

contract as asked.

As per specification.

Request for time extension further 3 weeks for submission of competitive bids after duly

site visits etc.

No, it will as per specification.

Page 40: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Montecarlo Ltd.,

Jaipur.

Ref: Your email dated 12.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

12

Clause No. Brief Description mentioned in the Document Clarification Sought by MONTECARLO RSDCL’s Comments

Power

Transformer 1.13:

GUARANTEES:

1.13.1: The bidders are required to offer the Transformers

having „No Load‟ & „Load‟ losses not exceeding the following values, without any positive tolerance:

(i) No load losses at rated voltage, normal ratio & rated

freq.:38 kW.

(ii) Load losses at rated current, normal ratio, rated freq.

&:250 kW.

75 deg. C including auxiliary loss.

The bidders quoting losses more than the values prescribed

above in GTP shall be rejected. No benefit shall be allowed

to the bidders quoting losses less than the above prescribed

values.

1.13.5: For the purpose of comparison of tenders, the quoted

prices shall be capitalized for the „No Load‟ losses and „Load‟ losses in two windings (HV+LV) including Auxiliary losses at the same rate as given at clause No. 1.13.2 for the

penalty/recovery, on the basis of max. guaranteed losses

figures including tolerance, if any. The Auxiliary losses shall

be the losses for two groups of cooler fans. Losses for

standby arrangement will not be accounted for

penalty/capitalization purpose.

However, as per following clause

capitalization shall be applicable for subject

enquiry :

Please note above clauses are contradictory.

Kindly confirm whether subject enquiry should

be quoted with fixed losses or Capitalization

shall be considered. In case of capitalization,

also explain its application, as it is stated that

there shall be rejection for high losses and no

benefit for low losses.

Bidder may quote lower losses

than the prescribed limit (clause

1:13:1).

If bidder doesn‟t prescribe any

tolerance limit in tender than limit

as prescribed (10% and 15%, as

per clause 1:13:3) will be

considered.

If any bidder quotes less than the

prescribed limit then for

evaluation purpose, the

capitalization is required.

CONTROL &

RELAY PANEL

1. Please provide us the detailed specification

for Control & Relay Panel as Section-II

provided only shows the Type of CRP to be

considered. Details of protection requirement

are missing from the document.

2. Kindly provide the Protection SLD.

3. What will be the requirement of PMU for

220KV Line connected to the Grid side.

4. What will be the protection requirement for

Line feeder.

As per specification.

For short lines, RSDCL will

prefer to provide differential

Page 41: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Clause No. Brief Description mentioned in the Document Clarification Sought by MONTECARLO RSDCL’s Comments

Is it a distance protection or differential

protection?

5. Each PSS-1,2,3,4 has two 220kV Line

feeders, are both of these lines connected to the

Grid side?

6. Is there any requirement of Solar SCADA +

PPC Controller as well?

7. Is PQ meter required to be considered in

220KV Line feeders?

protection.

Details of feeders are available in

ELP. However, a copy of

internal/external lines map is

enclosed.

BOQ

In Supply BOQ (Sr no. 1.08, 1.12, & 1.14 to 1.18) Structure

& Equipment Quantities are mismatched with their

foundation Quantities which are mentioned in Civil BOQ. Kindly Correct & upload revised BOQ.

As per BoQ.

Page 42: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Gupta Power Infrastructure Ltd.,

Kolkata.

Ref: Your e-mail dated 12.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

13

Query RSDCL’s Comments

Drawings & BOM is required for all equipment structure & equipment foundations as

same are not provided in tender documents.

BOM is available in specification. Drawings enclosed.

Drawings & dimensions of Dormitory building (item no. 51, BOQ 3) is required as same

is not given in tender documents.

Drawing available in specification. Ceiling height of Dormitory building

shall be 3300mm from FFL.

Contour map is required ( item no. 2, BOQ 3) Enclosed.

Layout & section drawings of Drainage system is required ( item no. 4, BOQ 3) The drainage system shall be developed in the substation premises as per

site location along the outer road of switchyard.

In tender documents you have mentioned that “Bank Guarantee of EMD will be on the Rajasthan State Non Judicial Stamp Paper of Rs. 100/- (or as per Govt. norms)”, Request you to clarify the amount of stamp paper required for Bank guarantee.

As per the applicable norms of Rajasthan State Govt.

In tender documents you have mentioned that 20% value of bid security will be paid

through DD/Banker‟s cheque. We request you to consider 100% Bank Guarantee against

bid security.

It will remain same as per tender specification.

In Price BOQ 1, S. No. 2.12, items S. No. 2.26, items S. No. 4.01 to S. No. 9.02, S.No.

12.11 are given in “Lot”. Request you to provide quantity break up of these items. Quantity break up of items will be provided at the time of work

execution.

Due to various holidays on Holi festival & various bank holiday & financial year closing

there is a very less working window; all of our vendors are demanding some more time to

submit their quotations. We request you to extend bid submission date at least 15-20 days

enable us to submit a most competitive bid.

No, it will be as per specification.

Page 43: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Transrail Lighting Ltd.,

Nagpur.

Ref: Your e-mail dated 12.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

14

Query RSDCL’s Comments

We need structure Drawing of Switchyard items mentioned in BOQ Sr.no. 1.01 to

1.19 and 2.01 to 2.30.

These are standard structures generally used in EHV substations.

We also need foundation Drawing of Switchyard equipment, Tower etc. Enclosed.

SBC report for proposed substation area Soil report enclosed.

Kindly confirm which documents we need to submit in hard copy/physical form &

also in online mode

As mentioned in the specification.

Kindly confirm Beneficiary Bank Details (i.e., Name of the Bank, Account Number,

Branch IFSC Code and Bank Address) for issuing EMD BG through SFMS platform

RSDCL Bank Details are as under:

Bank: Oriental

bank of Commerce

Branch: RSAMB, Jaipur

Account No.: 11331131000550

IFSC code: ORBC0101133

Page 44: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Kalpataru Power transmission Ltd.,

NOIDA.

Ref: Your e-mail dated 12.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

15

Clause reference Query RSDCL’s comments

General Kindly provide the X/R ratio of the system. It shall be provided at the time of work

execution.

As per Tender

Documents

Earthing:

i) Kindly provide tentative value of resistivity for estimating the earthing material quantity.

Enclosed.

As per Tender

Documents

Jack Bus & Dropper Conductor:

Line Side Condutor Name & Type: Kindly confirm the type of conductor entered in the

substation from TL side to consider the type of clamps and connectors suitable for them

accordingly in each substation

Hence,kindly Furnish conductors arrangement details for the scope Substations

As per specification.

As per Tender

Documents

Electrical Equipments: Cl. No.15 & Sl. No2.17 of TS: 30kV LA quantity mentioned are not

suffiecient to accommodate no. of Lines & Transformer Bays shown in the SLD. Please

clarify.

As per BoQ.

As per Tender

Documents

Cable Trench:

i) Kindly provide a typical standard Indoor and Outdoor Cable trench drawings for our

reference for the new substation.

ii) We under stand that Cable tray laying is not required in the outdoor trench. Kinldy confirm

our understanding else please furnish typical standard Cable Trays drawing to be laid in

different type of Trenches for our reference.

Enclosed.

As per Tender

Documents

Control & Power Cabling: Kindly Confirm the below Points:

i) Isolator, CT & CVT cabling will be provided in PVC pipe. There will not be any provision

of RCC trench. PVC pipes will be

ii) Power & Control cables in switchyard shall be laid on cable support angles only.

iii) Kinldy furnish standard Control & Power Cable termination Philosophy (if any).

Cabling will be in the trenches. Laying of

cables will be as per specification.

As per Tender

Documents, As per

Cl. 9, Specific

Requirement

sl.no.(m),

ACDB & DCDB Switchgears :

i) Referring "TECHNICAL SPECIFICATION FOR 220V DC CONTROL AND

DISTRIBUTION BOARDS", we understand that DC supply shall be looped from One

protection Panel to another Protection Panel rather than dedicated DC feeder coonection to

each Protection panel. Kindly Confirm our understanding to freeze the no. of DCDB Feeders.

ii) Kindly furnish a Typical Standard LT SLD for our reference to review the load list

indicating the practice of client .

iii) We are not considering feeders for future bays.

As per specification.

Page 45: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

As per Tender

Documents

Firefighting System: –

From TS we understand that there is no provision of online gas monitoring system for

Transformer and 25MVAr Reactor. Kinldy confirm our understanding.

As per specification.

As per Tender

Documents

Illumination System: –

i) In TS there is no provision/quantity/type of Lighting Distribution Boards e.g. Main Lighting

DB & Emergency Lighting LDB.

Kindly furnish a Typical Standard Lighting SLD for our reference and to finalise the vendor.

ii) We have assumed that there won't be any work of solar lights in our scope. Kindly confirm.

As per specification.

As per Tender

Documents

Remote end PLCC/FOTE Aux. system requirement:

ii) We have excluded, if any, remote end PLCC/FOTE equipment power & control cabling.

As per specification.

As per Tender

Documents

CRP & SAS and Busbar Protection: Refering Cl. No.9.5, Type of 33kV Line protection i.e.

Main-I is not clear. Please specifiy clearly.

Type of 33kV Line protection is given in

the specification.

As per Tender

Documents

cl.No.15, page no.

137 of 607

The quantities provided in excel BOQ does not match with the qunatities provided in

Annexure of Clause no. 15, page no. 137 of Tender documents. We understand that we need to

follow excel BOQ.

As per BoQ.

Please refer cl. No.

15.8 of Tender

Documents

As per refered clause, we need to pay royalty to the Department of Mines, GoR. Kindly

confirm the percentage of royalty.

As per Govt. norms.

As per Tender

Documents

We need to submit EMD (BG) on Rs. 100 Stamp Paper of Rajasthan. Please confirm As per Govt. of Rajasthan Stamp Duty

rules.

Technical

Specification

We request to please provide the standrad structure and foundation drawing of substation for

reference purpose of BOQ estimation

Enclosed.

Hindrance

Register

Hindrance register shall be maintained by us at site which shall include the delays due to force

majures, natural calmaities etc. and extension/compensation shall be provided to us for the

same

Project has to be completed in the given

time period.

Galvanizing

Thickness

We understand that as per civil structural Technical specification provided with tender

documents 610 gm/m2 galvanization is required for the steel structure conforming IS-4759

As per IS and standard provisions.

Soil Report and

Soil Resistivity

Please provide, if possible complete soil physical and chemical properties report along with

soil resistivity report for estimation purpose only

Soil report enclosed.

Design/Estimation

of Foundation

Please provide contour plan if available of subject site and please confirm the FGL for

estimation purpose only

Contour map enclosed.

Boundary Wall

Design

Considering the technical specification and guidelines for civil work provided with tender

documents for design and construction of Boundary wall, We presume that there is no

requirement of Brickwork below plinth level for filling area, Please confirm

Yes.

Water Drainage

system

We presume that there is no requirement of Drain along Boundary Wall and only drain will be

required for collection of storm water for switchyard area only, open brick drain will be

constructed by successful Bidder, Please confirm our understanding

The drainage system shall be developed in

the substation premises as per site location

along the outer road of switchyard.

Page 46: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Stelmec Ltd.,

Mimbai.

Ref: Your e-mail dated 12.03..2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

16

Reference

Clause

Description Query raised by Stelmec Ltd, Mumbai Response by RSDCL

Tender Document

Section Civil-3.0

Site will be handed over in

“AS IS WHERE IS” condition.

We understand that with the description that Soil Investigation & Contour

levels are in Bidder's scope. However, we presumed that hassle free land

will be handed over to the bidder.

Yes.

GENERAL

Water for construction works

& Drinking Purpose

It is bidder's responsibility. However, we understand that Supply of water,

wherever available with the RSDCL, may be made available for the

construction purposes at the prevailing rates and the same shall be given

at an agreed single point at the site. Please confirm.

The Contractor shall make his

own arrangements for power,

water and other facilities

necessary for the

construction/erection of

Pooling Sub-stations at his own

cost.

GENERAL Electricity & Power supply

for construction works

It is bidder's responsibility. However, we understand that bidder's can get

the same by applying to local DISCOM (VVNL). RSDCL good office will

help to get continuous construction power at an early stage. Also, the

expenses for obtaining the connection and payment towards consumption

of electricity as per billing by the DISCOM (VVVNL) shall be born by

bidder. Please confirm.

Site Visit

GENERAL

Construction of Approach

road

It is bidder's responsibility. However, we understand that requirement is

for construction purpose only & the same is temporary approach road. If

"Pakka road" after charging is required shall be paid extra as actual. Please

confirm.

As mentioned in the

specification.

Tender Document

Section Civil-3.0

Site shall be graded to the

levels as per the FGL

(finished grade level) which

includes clearing the site area

free of bushes, trees including

removal of roots.

Please furnish the proposed Finished Ground level. FGL is generally maintained

about 100mm to 150mm above

the level of approach road.

Top of Switchyard

Foundations & Building

Plinths w.r.t to FGL

Section Civil-3.0,

Top of switchyard

foundations plinths and

building plinths shall be

minimum 400 mm and

1000mm above finished

ground level respectively.

We propose Switchyard foundations Top is 300mm in place of 400mm &

Building Plinth is 750mm in place of 1000mm w.r.t FGL level. Please

accept our proposal.

As per specification.

GENERAL

Grade of RCC &

Reinforcement steel

We understand as per Tender spec, Grade of Cement is OPC -43, Mini.

Grade of RCC is M20 & Grade of Reinforcement steel is Fe-415.

As per specification.

Page 47: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Grade of Lean concrete

(PCC) & Thickness

We understand with the tender specification that Grade of Lean Concrete

(PCC) is M7.5 & thickness is 150mm. Please confirm.

As per specification.

Thickness of Compacted

Layer i.e. Morrum/Rubbish

under lean concrete

We understand with the tender specification that Minimum 300mm thick

compacted layer of quarry rubbish/morrum shall be provided under lean

concrete. Please confirm.

As per specification.

Usage of PPC Cement and

Fly ash bricks

Please provide the confirmation on usage of PPC grade cement for work

below ground level & Fly as bricks.

As per specification.

Brick/Block Masonry have

mini. Compressive strength is

35kg/cm2

We proposed RSDCL to allow Fly ash Bricks or AAC blocks or Concrete

blocks along with Burnt clay Bricks, as there might be a shortage of Burnt

Clay bricks at this premises and work may get delayed. It is advisable to

have 2-3 options so that work shall not be hampered. Kindly Accept our

proposal.

As per specification.

Quantity variation We request to provide us the details on the maximum allowable quantity

variation in percentage.

As per specification.

The grade of Rail Section to

be used for Transformer

We presumed that the rails shall be of prime quality 52 kg/m medium

manganese steel as per Indian Railway specification T-12-96 (880 Grade)

and its subsequent revision. Please confirm.

As per specification.

Civil Price Bid-BOQ-3,

Sr No-15

Construction of Foundation of

PIS Type Structure

We understand Construction of PIS Type Structure Means BPI Structure.

Please confirm

PIS type structure.

Civil Price Bid-BOQ-3,

Sr No-27 to 30

Ferro Cement Cover Please brief in detail regarding Ferro cement cover and furnish the mini.

Thickness of cover slab.

Drawing enclosed.

Civil Price Bid-BOQ-3,

Sr No-27 to 30

Construction of Type Ax,

Type A, Type -C, Type-D

Cable Trenches

Please furnish mini. Clear dimension of Trench or GA of each type

Trench with mini. required details

Drawing enclosed.

GENERAL

Bore well for water supply We understand that bore well for water supply is not in Bidder's scope.

Please confirm.

The Contractor shall make his

own arrangements for power,

water and other facilities

necessary for the

construction/erection of

Pooling Sub-stations at his own

cost.

Power during charging We understand that Power during charging is not in Bidder's scope. Please

confirm

General Permanent water supply We understand that permanent water supply after charging/handing over is

Owner's responsibility. Please confirm

Civil Price Bid-BOQ-3,

Sr No-45

Construction of

Security/Guard Hut at Main

Gate

Please furnish the mini. Built up area for Security/Guard Hut or furnish

the Arch Plan.

Drawing enclosed.

Page 48: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Stelmec Ltd.,

Mimbai.

Ref: Your e-mail dated 12.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

17

Clause No. Description as per Specifications /BOQ KEI

Submission/Queries

RSDCL’s Comments

SCC 10.0 Time

Schedule

For the purpose of Clause No. 17.0 of ITB, the schedule for completion of

supply of material/ equipment, successful erection, testing, commissioning

& execution of Civil Works of all four 220/33kV Park Pooling Sub-stations

and their handing over to RSDCL, complete in all respect as per

specification of entire work shall be 15 (Fifteen) months from the date of

issue of detailed purchase/work order(s). The completion period is inclusive

of monsoon period also.

The contractor will immediately mobilize its resources for development of

shop, sketches and proto assembly of structures (if required), selection of

vendors for other works, material/ equipments, placing orders on them and

opening of site offices etc. accordingly.

As the Sub-Station Sites

is located in the remote

location so we hereby

request you to ammend

the Completion Period

to 24 Months after

handing over of sites for

smooth and timely

completion of the

project.

No, it will be as per specification.

SCC 7.10 Terms

of Payment

7.1 The payments for the material/ equipment or erection work shall be

made as under only after execution of the Contract Agreement (CA) and

furnishing of Security Bank Guarantee of 2% of total contract value (valid

upto 90 days from the date of handing over of all the Pooling Sub- stations

after commissioning), Performance Bank Guarantee of 10% of total

contract value (valid upto one year from the date of handing over of all the

Pooling Sub-stations) and Project Implementation Schedule (L-2 Network)

and its approval as per the following relevant clauses.

All payments shall be made in accordance to Clause 34.3 of GCC from the

date of submission of duly verified bills & completion of all contractual

formalities as per requirement of contract.

We would like to submit

that Performance Bank

Guarantee of 10% of the

total contract value is a

normal practice of all

the utlilites in India. We

hereby request to

ammendent/remove the

clause of submission of

Security Bank guarantee

of 2% of the Total

Contract Value.

It will remain same as per tender

specifications.

Plot Size Plot Size Please provide us with

the details of Sub-

Station for further

Designing and preparing

competitive Bid.

As per ELP.

Page 49: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Soil

Invertigation

Report

Soil Investigation Report Please provide the soil

Investigation report of

all Sub-Station as it is

not available in the

tender documents.

Soil Report enclosed.

Approved

Vendor List

Approved Vendor List Please provide us with

the Approved Vendor

List for all

Equipments/Material.

As per specification.

Reactor Losses Reactor Losses of reactor is not

available in the tender

documents, please

provide us with the

same.

Bidder has to quote the losses of the reactor

and to be enclosed with the technical part of

its bid.

Foundation

Drawing

Foundation Drawing Please provide us with

the foundation drawing

of Sub-Stations as it is

not available in the

tender documents.

Enclosed.

Page 50: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s GE T&D India Ltd.,

Jaipur.

Ref: Your email dated 12.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

18

Query RSDCL’s Comments

With reference to the subjected NIT we are in process of reviewing the tender document and preparation of Pre-bid Queries

on the same.

Request you to please allow us time till 18th

of March to submit of queries.

No, it will be as per tender

Specifications.

Page 51: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Suncity Enterprises Ltd.,

Jaipur.

Ref: Your letter dated 06.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

19

Clause Ref. Description Bidder’s clarification/ proposed amendment RSDCL’s Comments

PQR Clause

No. 2.4 (A) &

(B)

As per PQR Clause No. 2.4 (A) & (B) both

partners individually meet the qualification

criteria.

Both partners meet the qualification combined As per tender Specifications.

Page 52: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Ashoka Buildcon Ltd.,

Nashik.

Ref: Your letter dated 29.02.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

20

Clause Ref. Description Bidder’s clarification/ proposed amendment RSDCL’s Comments

2.1 Technical

Criteria: For

Pooling Sub-

station work:

Experience:

Para 2 Page

No. 7

The aforesaid sub-stations or switchyards must

have at least two Nos. circuit breaker bays of

220kV class or above, out of which at least one

bay should be for controlling of a power

Transformer. Also, one sub-station or switchyard

must be in satisfactory operation for at least a

period of one year as on the date of Technical bid opening on turnkey basis within last seven

years immediately preceding the date of

Technical bid opening. A circuit breaker bay shall

mean the bay having at least one circuit breaker,

2 dis-connectors and 3 Nos. single phase CTs.

The aforesaid sub-stations or switchyards must have at

least two Nos. circuit breaker bays of 220kV class or

above, out of which at least one bay should be for

controlling of a power Transformer. Also, one sub-

station or switchyard must be in satisfactory

operation as on the date of Technical bid opening on turnkey basis within last seven years immediately

preceding the date of Technical bid opening. A circuit

breaker bay shall mean the bay having at least one

circuit breaker, 2 dis-connectors and 3 Nos. single

phase CTs.

No, it will be as per tender

Specifications.

Page 53: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

M/s Kailash Devbuild (India) Pvt. Ltd.,

Jabalpur.

Ref: Your letter dated 12.03.2020.

Replies against the queries pertaining to the tender document [TN 03(2019-20)].

21

Query RSDCL’s Comments

Bid Security – The section 2(ii) of note to invitation of bids required bid security of Rs.

4,83,80,000/- of this 20% is required to be submitted in cash. This is contrary to prevailing

practice in other transmission utilities and will result in blockage of funds and difficulties in

cash flow.

We would request you to amend this and allow the entire bid security to be submitted in

form of bank guarantee in line with what is being assured for elsewhere.

As per tender Specifications.

Payment – During the course of pre-bid it was mentioned that payment would be released

within 30 days. Given the short completion period this will entail delays in execution and

difficulties in cash flow. We would request you to consider making payment within 7 days

as per terms of payment.

As per tender Specifications.

Entry Tax and Other Local Taxies- Please provide us the percentage of entry tax and other

Local taxes. The entry tax is credit in GST set off. Please confirm.

As per applicable provisions.

Drawings- Please provide us all Structure & Equipment FND drawings, Electrical Section

Drawings of TBC & BC bay.

Drawings enclosed.

Technical Specification Annexure-II(A)- Approved Vendor List-We are proposed another

vender list, the vendors are approval in other Power sector utility. Please incorporate the

same.

Approved vendors shall be as per specification. However, RSDCL

may accept the material from approved vendors of PGCIL subject to

furnishing of documentary evidence in this respect and approved by

RSDCL.

ITB Cl. 40.0 CONTRACT PERFORMANCE GUARANTEE and Cl. 41.0 SECURITY

GUARANTEE-CONTRACT PERFORMANCE GUARANTEE and SECURITY

GUARANTEE- As per the given clause successful bidder submit the Contract Performance

Guarantee of 10% of total contract value, so why submit the 2% of Security Guarantee of

total contract value. Please modify the clause. As per the standard bidding process.

As per tender Specifications.

Page 54: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Besides the above it shall be ensured by the successful bidder that:

1. Creepage distance for 220kV system/ equipment shall be 6125 mm.

2. Creepage distance for 33kV system/ equipment shall be 900 mm.

3. Creepage distance for tension string shall be 6125 mm.

4. Battery room shall have acid proof tiles and exhaust fan.

Max. daily average ambient air temperature and Max. yearly average ambient air temperature shall be 45 and 35 degree centigrade respectively.

Page 55: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

TBM 7 ON STONE RL- 185.923X = 227236.469 Y = 3055584.554

TBM 9 ON WT RL- 172.746X = 225683.156 Y = 3054026.383

TBM 11 ON WT RL- 171.835X = 223794.552 Y = 3055401.714

TBM 10 ON STON RL- 172.856X = 224958.709 Y = 3055448.345

K.RASTA

B.T

. R

OA

DB

.T. R

OA

D

B.T

. R

OA

D

K. RASTA

K. RASTA

K. RASTA

K. R

ASTA

K. RASTA

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

TBM.ON KM STON RL- 188.667

TBM.NO.2 RL- 186.334

TBM.NO.1 ON KM STON RL- 183.929

TBM.NO.4 ON WT RL- 185.934

TBM.NO.3 ON BUILDING RL- 186.996 X = 228315.1515 Y = 3057344.0893

HUT

X = 226729.3050 Y = 3057440.0214

X = 228324.0645 Y = 3056432.9357

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

X = 227141.0670 Y = 3056370.1767

X = 227326.7875 Y = 3055973.2368

K.R

AS

TA

K.R

AS

TA

K.RASTA

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

TBM.ON KM STON RL- 184.193

TBM.ON KM STON RL- 184.193

WB

M.R

OA

D

X = 228359.7630 Y = 3054298.6963

X = 228884.1305 Y = 3055390.2483

TBM 8 ON KM STONE RL- 183.420X = 227797.007 Y = 3055100.972

TBM 3 ON WT RL- 172.207X = 226096.970 Y = 3051626.680

GODAWARI GREEN ENERGY LTD

SOLAR PLANT

SCHOOL

POLICE STATION

KABRISTHAN

VETERINARY HOSPITAL

MOTHERSA SCHOOL

HOSPITAL

TO

TA

LR

IYA

TO BO

DAN

A

TO DHELERI

TO D

HELE

RI

TO SAN

WAR

A GAO

N

MAINER

MAINER

MAINER

MAINER

MAINER

CA

NA

L

CAN

AL

CA

NA

L

CA

NA

L

CA

NA

L

CA

NA

L

CAN

AL

TBM 12 ON CULVERT RL- 177.474X = 224587.702 Y = 3051621.137

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.ROAD

B.T.R

OAD

B.T.ROAD

W.B

.M. R

OAD

W.B.M. R

OAD

W.B.M. R

OAD

W.B.M. R

OAD

W.B.M. R

OAD

W.B

.M. R

OAD

KATC

HA R

ASTA

KATCHA RASTA

KATC

HA R

ASTA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

KATCHA R

ASTA

W.B.M. R

OAD

W.B.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

B.T

. RO

AD

B.T

. RO

AD

B.T. R

OAD

B.T

. RO

AD

B.T

. RO

AD

B.T

. RO

AD

B.T

. RO

AD

B.T

. RO

AD

B.T

. RO

AD

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

C.C.ROAD

C.C.ROAD

C.C.ROADC.C.ROAD

C.C.ROAD

C.C

.RO

AD

C.C

.RO

AD

C.C

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KATCHA RASTA

KATCHA R

ASTA

KATCHA R

ASTA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

W.B.M

. ROAD

KATCHA RASTA

KATCHA RASTA

KA

TC

HA

RA

STA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

KATCHA R

ASTA

KATCHA R

ASTA

KATCHA R

ASTA

KATCHA R

ASTA

KATCHA R

ASTA

KATCHA RASTA

KATCHA RASTA

B.T. ROAD

B.T

. RO

AD

B.T

. RO

AD

B.T

. RO

AD

B.T. R

OAD

B.T. R

OAD

B.T. R

OAD

B.T

. RO

AD

B.T

. RO

AD

B.T

. RO

AD

B.T

. RO

AD

B.T

. R

OA

D

B.T

. R

OA

D

KATC

HA R

ASTA

KATC

HA R

ASTA

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OA

D

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B

.M. R

OAD

W.B.M. ROAD

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KATC

HA R

ASTA

KATC

HA R

ASTA

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

B.T

. R

OA

D

B.T

. R

OA

D

WBM.R

OAD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T

.RO

AD

B.T.R

OAD

B.T

.RO

AD

B.T.R

OAD

B.T.R

OAD

B.T.R

OAD

B.T

.RO

AD

B.T

.RO

AD

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

STA

KA

TC

HA

RA

STA

KATCHA RASTA

KATCHA RASTA

KATCHA RASTA

KATC

HA R

ASTA

KATC

HA R

ASTA

KATC

HA R

ASTA

KATC

HA R

ASTA

KATCHA RASTA

KATC

HA R

ASTA

KATC

HA R

ASTA

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

DW

BM

.RO

AD

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

D

WB

M.R

OA

D

W.B

.M.

RO

AD

W

.B.M

. R

OA

D

W.B

.M.

RO

AD

W

.B.M

. R

OA

D

W.B

.M.

RO

AD

W

.B.M

. R

OA

D

W.B.M. ROAD

W.B.M. ROAD

GSS 33/11 KV

DHANI

NOKH VILLAGE

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

KATC

HA R

ASTA

KATCHA RASTA

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

CH

TBM.ON-5 WT RL- 184.591 X = 228972.2540 Y = 3055774.8695

KA

TC

HA

RA

ST

A

KA

TC

HA

RA

ST

A

TBM 14 ON STONE RL- 179.698 X = 230863.728 Y = 3053720.245

TO

ME

GH

WA

LO

KI D

HA

NI

TO D

ADU K

A G

AO

N

TO BEETHE K

A GAON

TO B

EETH

E K

A G

AO

N

X = 223860.8895 Y = 3056151.5113

X = 223676.8604 Y = 3050859.0471

X = 226013.4064 Y = 3049332.4358

X = 226760.7067 Y = 3047787.7522

X = 228840.6983Y = 3049815.4065

X = 227351.8863 Y = 3052723.3141

X = 232510.0979 Y = 3053681.1548

X = 231049.6996Y = 3056724.3672

X = 226844.0629Y = 3057262.0815

X = 227753.3509Y = 3055236.5140

TO B

ODANA

TO NEWA

TO D

HELE

RI

TO

TH

AK

AR

BA

TO

ME

GH

WA

LO

KI D

HA

NI

TO B

EETHE K

A GAO

N

TO D

HELE

RI

PLOT - 2AAREA- 73.35 Hec.

PR

OP

OS

ED

SH

IFT

ED

GO

DA

WA

RI T

RA

NS

MIS

SIO

N L

INE

CA

NA

L

GODAWARI PLANT

TO

TA

LR

IYA

NOKH VILLAGE

TO BEETHE K

A GAON

SHIFTED GODAWARI

TRANSMISSION LINE

TO B

ODANA

PLOT - 1AAREA-210.14 Hec.

PLOT - 1BAREA-143.58 Hec.

PLOT - 1CAREA-114.88 Hec.

PLOT - 2AAREA- 73.35 Hec.

PLOT - 2BAREA-367.03 Hec.

PLOT - 3BAREA-122.38 Hec.

CA

NA

L

CA

NA

L

GODAWARI PLANT

TO BO

DAN

A

SHIFTED GODAWARI

TRANSMISSION LINE

CANNAL

RAW WATER RESERVOIR ANDTREATMENT PLANT

AREA-

5.00 Hec.

ROAD B- 7.5 M WIDE NEW

ROAD

ROAD A- NEW R

OAD

7.5

M W

IDE R

OAD

7.5 M WIDE ROAD

PLOT - 3AAREA-350.96 Hec.

P.P.S.( 3 )

+DOREMITORY

P.P.S.( 2 )

+DOREMITORY

P.P.S.( 1 )

+DOREMITORYP.P.S.(1)

4.5 Hec.

PLOT - 4CAREA- 60.23 Hec.

PLOT - 4DAREA- 62.80 Hec.

PLOT - 2CAREA-48.62 Hec.

X =

223849.3

069

Y =

3055343.1

035

PLOT - 4FAREA- 19.43 Hec.

P.P.S.(3)

4.5 Hec.

P.P.S.(2)

5.2 Hec.

PLOT - 4AAREA- 72.53 Hec.

PLOT - 4BAREA- 46.37 Hec.

P.P.S.( 4 )

+DOREMITORY

P.P.S.(4)

4.5 Hec.

PLOT - 4EAREA- 100.95 Hec.

X = 228387.4838

Y = 3053722.6070

X = 227544.5613Y = 3055775.0213

X = 227603.4810Y = 3055685.2561

SCALE :-

CONTRACTOR :-

CLIENT :-

PROJECT:-

TITLE:-

DRG No.

SCALE :-

DRAWN BY : RECOM. BY : CHECKED BY : APPROVED BY :

TREE

TELEPHONE POLE/T.B.

ELECTRIC POLE/E.B.

HOUSE/BLDS/STRUCTURE

TRANSFORMER

L.T.POLE

ESR

L E G E N D

WELL & WATER TANK

HAND PUMP

LAMP POST/ROAD LIGHT

BORING

SCHEME BOUNDARY

AIR VALE

KHASRA LINE

HT LINE

N

Ew

S

REVISED SURVEY CONTOUR PLAN

PDCOR

CANAL

W.B.M. ROAD

B.T. ROAD

KATCHA RASTA

FENSING

CULVERT

KM STONE

RSDCL

FIELD BOUNDARY

NOKH SOLAR PARK PROJECT

PPS 1- 4.5 Hec. PPS 2- 5.20 Hec.

PPS 3 - 4.5 Hec. PPS 4 - 4.5 Hec.

Water storage- 5.00 Hec.

PLOT - 1

AREA- 468.60 Hec.

PLOT - 2AREA- 489.00 Hec.

PLOT - 3AREA- 473.35 Hec.

PLOT - 4

AREA- 362.31 Hec.

Page 56: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,
Page 57: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,
Page 58: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Foandac'ipn Sqdton Boundarg Notl*.^_u"

ot

l600n|'fl

loon

6oonnnq

;!

''l

tlsorw

F6L

5 00n4vl

6 O -O$'r :

o <3 d) (|! I €! s fl S r.S + *3 + tr & !3 {! e\ {\ 1,,! ,iti} 11 i:

K ?50MM

-)t

Bv i e k fi o sooeyf (s"p* v "efx'reAt*€J(f

R.q: c(,, ry : 3) M-z&

tevo{

€lo.a.e lfiasoaat4r

Flb d 6mv*d

d*ved

$arc r4aJanaV

n*7,5

Vtttt QLt?trf, *u&&i#*'/v

Page 59: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

iN .,.so

{1'*f"x !" fit'.

;oa(\le

+ t(); !Fop'

I

II

Nl*)\4

Htplz,

F

F"

H

eIr,loFzrt,?

2\

o\a

Ntso l+

oc

-cs

3E(r(e

F{l-< I

l=lthltblF- l:lr' IFnlioll\ i,li urtoqlzo,bni

1t-'-

iriYiRI

i--lXifi-

Er\

trsdtr*i\,FVr6$3l3B'x

h

e--F9t^TEYB;J^R

iq

'l)

3g

.}Foo+lB

ee

sl'xol:n Ap'F'>$nsll

:b

a

It

J-rl^$ict:rC|i,

€I

lg*{

ico

I0J{c*B

h

(1

cIfq

3on(

$

=o\o

I

I

I

I

l-{l-(i\lr,LtlrLtnr)HTp

Eor!

b"fY

vr

*.1

Nl"rtEf\

Hl-t\ll-lloIlP:lf" I

iniinll-t t

icIizs

t?\6

El4DtsS

hi, t,

f.F{,ief;'cg arr

il,?rr{

.S"eIit

"C-ts

3,3

a h:!^

aBt= PId; Fs

i$T$ 8s*q

,tl 6

vlo+€Jg.:b:sh013

;I

a\,&St4n|s,*, s

oife

\,1

.i

) a^

^ro' c6

i" o n

! otli" o'l',, b4

fo,

5$

I:ss

Page 60: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,
Page 61: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,
Page 62: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,
Page 63: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,
Page 64: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,
Page 65: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,
Page 66: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Geotechnical Assessment of the Site

The objectives of Geotechnical Survey were to assess soil profile of the site as well as

to find out electrical resistivity of the soil. Geotechnical investigation includes surface

& subsurface exploration, soil sampling, and laboratory analysis. Geotechnical

investigations have substantial importance in assessing requirement of foundation to be

laid down preventing human and material damage due to the earthquakes, foundation

cracks, and other catastrophes.

Soil resistivity is a measure of soil resistance to the flow of electricity. It is a critical

factor in design of the grounding system in an electrical substation, or for lightning

conductors. To attain the desired objectives, earlier there were 100 boreholes/trial

pits were drilled to assess the soil profile while 25 pits were drilled to assess electrical

resistivity of the soil. Subsequently, few more boreholes/trial pits were drilled to

assess the soil profile and electrical resistivity of the soil. In all, total of 142

boreholes/trial pits were drilled to assess the soil profile while 30 pits were drilled to

assess electrical resistivity of the soil. .

a. Borehole Investigation:

i) For geotechnical investigation work, auger boring used as per IS 1892-1979 clause

3.6.1.

ii) Drilling bore holes of size 100 mm/Nx size using auger boring up to refusal,

collecting necessary disturbed/undisturbed soil samples wherever strata changes.

iii) Standard penetration test was conducted in the bore holes at regular intervals of

1.5 m or at every change of strata, whichever is earlier as per IS 2131-1981.

iv) Disturbed and undisturbed samples were collected at different depths/wherever

strata changes as per IS 1892-1979.

v) Disturbed samples recovered were sealed in polythene labelled and sent to the

laboratory for laboratory test.

b. Standard Penetration Test:

Standard Penetration Test (SPT) was conducted as per IS: 2131 – 1981. SPT split spoon

sampler of standard dimensions was driven into the soil from the borehole bottom

using 63.5 kg hammer falling from 75 cm height. The SPT weight was mechanically

lifted to the specified height and allowed to fall freely on the anvil with the use of cat-

head winch with one to one and half turn of the drum. Blow counts for the penetration

of every 15 cm were recorded and the N is reported as the blow counts for 30 cm

penetration of the sampler leaving the first 15 cm penetration as seating drive.

Page 67: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

When the number of blows exceeded 50 to penetrate the first or second 15 cm length

of the sampler, the SPT N is regarded as more than 100 as described in IS : 2131 - 1981.

The test is terminated in such case and a record of penetration of the sampler under

50 blows or more is made. SPT refusal is recorded when there is no penetration of the

sampler at any stage and also when a rebound of the sounding system is recorded. The

N values are appended in bore log sheet.

c. Trial Pits:

Fifty one Trial pits were excavated at various locations GPS coordinates as shown in the

coordinates tables Trial pits were excavated up to 4.0m depth from EGL. The soil

samples were collected and brought to laboratory for testing.

d. Laboratory Testing:

The following laboratory tests are carried out on soil samples collected at site as

applicable:

i) Grain size analysis

ii) Liquid limit, plastic limit and plasticity index

iii) Angle of repose and cohesion

iv) Sp. gravity

v) Bulk/dry density

vi) Natural moisture content

vii) Standard compaction test

viii) California bearing ratio (unsoaked & soaked)

ix) Chemical analysis of soil (PH, chloride, sulphate)

The test results of boreholes, trial pits, and chemical analysis of soil samples collected

at site are appended in below tables.

e. Findings of Soil Profile:

Soil properties in all 76 boreholes/trial pits is almost the same but in BH No. 1 to 5,

7,8,14,15,44,49 & 50 refusal strata met at 0.75 m depth and soil classified as sand with

gravel from EGL to 0.75 m depth. In this bore holes soil is non plastic and cohesion

less. In all bore holes % of silt & clay varied from 7 to 21 percent and gravels varied

from 13 to 29 percent and remaining part is sand. In BH No. 6, 9 to 13, 16 to 25, 29 to

31, 36, 38 to 41, 45 to 48 and 51 to 76 refusal strata met at 1.5 m, 3.0 m and 4.5 m

depth. Here Soil strata varied from medium to very dense 0.75 to 4.5 m. This soil is

also non plastic and cohesion less. In BH No. 26 to 28, 32 to 35, 37,42,43 soil strata

loose at 0.75 m medium from 1.5 to 3.0 m, dense at 4.5 m, and very dense below 4.5

Page 68: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

m and BH no. 52 to 76 soil strata medium up to 1.5 m and dense below 1.5 to 4.5 m.

over all soil is classified in all Seventy six bore holes is sand. We have also conducted

Sixty six one trial pits from EGL to 3.0 m and one of trial pit is 4.0 m. soil strata of trial

pits is the same as bore holes and soil strata classified here also is sand. Some points

have been neglected because of transported dunes sand with height from 5 to 15 m.

Work could not be carried out there either by tripod or power shovel. Keeping this in

view, recommended safe bearing capacity as per shear criteria from 3.0 m to 6.0 m

depth as per IS 12070 with zero core recovery is 20 T/m².

Table Error! No text of specified style in document.-1: Safe Bearing Capacity Minimum of Fifty One Boreholes

Depth Meter

Safe Bearing Capacity Recommended

Safe Bearing Capacity T/m²

Shear

Criteria T/m²

25 mm settlement criteria

0.75 7.95 12.37 7.50

1.5 19.98 22.97 15.00

3.0 23.49 38.56 20.00

4.5 37.76 48.74 20.00

6.0 62.16 63.39 20.00

Soil properties up to 6.0 m depth are almost same in all seventy six bore holes. Soil

containing 6 to 24 % clay and silt is classified as sand. Soil is non-plastic and cohesion

less up to 6.0 m depth in all fifty one bore holes. Rock was not encountered at

different level of depth in seventy six bore holes. Keeping this in view recommended

safe bearing capacity as per general shear criteria at 6.0 m depth as per IS 12070 with

zero core recovery is 20 T/m².

Table Error! No text of specified style in document.-2: Safe Bearing Capacity Minimum of Fifty One TP Boreholes

Depth Meter

Safe Bearing Capacity Recommended

Safe Bearing Capacity t/m² General Shear Criteria t/m²

1.0 28.05 20.00

2.0 43.79 20.00

3.0 59.45 20.00

4.0 82.16 20.00

Soil strata were very hard so Excavation was not possible below 3.0 m by power shovel.

Page 69: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

f. Electrical Resistivity Test:

Electrical resistivity test was conducted as per IS 7808: 1987 at thirty (30) locations by

Wenner four pin electrode configurations. The testing equipment passes a small, low

frequency AC current, of known value, through the ground via two current electrodes

(C1 and C2), and measures the potential difference between two additional voltage

electrodes (P1 and P2) at intermediate points.

The test is conducted by driving the four electrodes into the ground approximately

100mm to 200mm deep, in a line, such that the electrodes are symmetrical and equally

spaced. The soil resistivity measurements were recorded from the meter when the

readings stabilized in North-South direction and East-West direction. The depth of

influence on the test result was approximately 1/3 of the distance between C1 and C2.

Tests were conducted in two directions, and at different electrode spacing to provide

results applicable to a range of depths. This procedure may be standardized by taking a

set of reading at approximate pin spacing of 80, 165,320, 480 cm.

From the values obtained at field, the Qresistivity of the soil is calculated as follows:

Soil Resistivity (Ω) = 2π. A. R Where π = 3.142,

R = measured resistance between voltage electrodes, A = electrode spacing

C1 --- P1 --- P2 --- C2

A

A

A

Range of soil Resistivity (Ohm-m) Soil Classification

Less than 25 Severely corrosive

25-50 Moderately corrosive

50-100 Mildly corrosive

Above 100 Very mild corrosive

g. Findings of Electrical Resistivity of the Soil:

ERT Test Pit

Mean Resistivity Ω m

Soil Strata Soil Classification

1 74.19 Sand with gravel Mildly corrosive

2 82.40 Sand with gravel Mildly corrosive

3 80.48 Sand with gravel Mildly corrosive

Page 70: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

ERT Test Pit

Mean Resistivity Ω m

Soil Strata Soil Classification

4 80.53 Sand with gravel Very mild corrosive

5 170.06 Sand with gravel Very mild corrosive

6 184.86 Sand with gravel Very mild corrosive

7 178.78 Sand with gravel Very mild corrosive

8 131.76 Sand with gravel Very mild corrosive

9 169.28 Sand with gravel Very mild corrosive

10 149.63 Sand with gravel Very mild corrosive

11 98.19 Sand with gravel Mildly corrosive

12 83.88 Sand with gravel Mildly corrosive

13 75.19 Sand with gravel Mildly corrosive

14 77.38 Sand with gravel Mildly corrosive

15 71.96 Sand with gravel Mildly corrosive

16 71.38 Sand with gravel Mildly corrosive

17 45.06 Sand with gravel Moderately corrosive

18 46.89 Sand with gravel Moderately corrosive

19 39.64 Sand with gravel Moderately corrosive

20 43.25 Sand with gravel Moderately corrosive

21 58.84 Sand with gravel Mildly corrosive

22 49.63 Sand with gravel Mildly corrosive

23 58.56 Sand with gravel Mildly corrosive

24 58.37 Sand with gravel Mildly corrosive

25 59.33 Sand with gravel Mildly corrosive

Page 71: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

ERT Test Pit

Mean Resistivity Ω m

Soil Strata Soil Classification

26 57.00 Sand with gravel Mildly corrosive

27 59.25 Sand with gravel Mildly corrosive

28 55.56 Sand with gravel Mildly corrosive

29 62.25 Sand with gravel Mildly corrosive

30 54.00 Sand with gravel Mildly corrosive

From the above table it is observed that at most of the places the soil is mildly

corrosive and the soils’ resistivity varies from 39.64 Ohm meters to 184.86 Ohm

meters.

Nokh Solar Park falls under Seismic Zone – III which is considered as moderate risk zone

(MSK scale VII). It simply means if earthquake occurs it will be of 5.0 - 5.9 magnitudes

on rector scale.

Water table at Nokh and neaby area is quite deep (more than 40 meters) and

underground water is available in limited quantity. The water available is saline which

is neither potable nor useful in module washing. Its extraction is not advisable since

the levels of the aquifers will be affected resulting in drying of the soil.

The site is least prone to any potential geological hazard like landslide, flooding &

erosion, subsidence, primary ground rupture, strong ground motion & liquefaction etc.

Bearing capacity of the soil is suggested as 20 T/m2. Foundations for PV mounting

structure will require depth of approx 5 – 6 feet.

The site has undulation. Earthwork will require for levelling the undulations which can

be done easily as the soil is sandy desert. This will be done by the Developers.

Page 72: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

1

RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED (A Government of Rajasthan Undertaking)

CIN NO. U40102RJ2011SGC036861

Reg. Office: E-166, Yudhisthir Marg, C-Scheme, Jaipur-302001

Tel: 2225859, 2229341 email: [email protected]

No. RSDCL/Solar Park/ TN-03 (2019-20)/D-spl 2 Date 16.03.2020

Sub: Corrigendum No.2 in tender documents of TN-03 (2019-20) for the reference of

interested bidders. Corrigendum No. 2 is hereby issued for providing of technical specification of conductors to the bidders under TN-03 (2019-20) as per attached document. The bidders may go through the document before completing and uploading their tenders. Attachment: As above. --sd--

Director (Technical) RSDCL, Jaipur

Page 73: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

AL-59 (MOOSE EQUIVALENT) CONDUCTOR:

The AL-59 (Moose Equivalent) 61/3.50 mm conductor shall comply in all respects except

herein otherwise stated with the Standard SS-4240813 & SS-4240814 with latest amendments, if any.

The material shall be new and of best quality & workmanship. The AL-59 (Moose Equivalent) 61/3.50 mm conductor shall be suitable for being installed directly in air on 220KV kV D/C and S/C transmission lines. It shall therefore, be suitable for satisfactory operation under the tropical climatic conditions mentioned in this specification. The climatic conditions are also prone to wide variations in ambient conditions. Heavy lightening may also occur during June to October Months.

PRINCIPAL PARAMETERS: Technical Specification for AL-59 conductor (Moose equivalent, Al-Mag-Si) is as under: ------------------------------------------------------------------------------------------------------------ S. No. Particulars AL-59 conductor (Moose equivalent)

------------------------------------------------------------------------------------------------------------ 1. Standard SS-4240813 & SS-4240814 2. No. of strands and nominal diameter in mm: Aluminium: 61/3.50

1. Diameter of Strand (in sq.mm): Nominal 3.50 Maximum 3.53 Minimum 3.47

4. Total sectional area (in Sq. mm) 587 5. Approximate overall diameter (in mm) 31.50 6. Approximate total mass (Kg/Km) 1618 7. DC resistance at 20 Degree C, 0.05070 whole conductor (Max. in Ohms/Km)

8. Approximate calculated breaking load (KN) 141.12 9. Lay ratio: (i) First layer Max. - 17 Min. - 10 (ii) Second layer Max. - 16 Min. – 10 (iii) Third layer Max. - 15 Min. – 10 (iv) Fourth layer Max. - 14 Min. – 10 10. Final Modulus of Elasticity 68000 MPA 11. Co-efficient of linear expansion/Deg. C. 23.0 x 10-6

12. Max. Continuous current rating at 95 1204 A Deg. C. (corresponding to Ambient Temp 40 Deg. C.) 13. Temp. rise for the above 55 Deg. C. 55 Deg. C. 13. Standard Length (Meters): 1500 + 5% Physical Constants of Materials

The AL-59 should be as per SS-4240814 & IS-9997 and their latest amendments. The material offered shall be of the best quality and workmanship. The AL-59 shall have accurate chemical composition of Alloy so as to offer excellent corrosion resistance, better strength to weight ratio and improved conductivity. The solution treatment shall be done in a very sophisticated and advanced technology furnace with automatic quenching system.

Page 74: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

Resistivity:

The resistivity of AL-59 depends upon its purity and its physical condition. However, as per the

specified value of purity in this specification, the maximum value permitted is 0.02930 ohm Sq. mm/ mtr at 20 Deg. C and this value shall be used for calculation of the maximum permissible value of resistance. This value may be checked from the measured value of the resistance.

Materials (As per SS-42 40814 & IS-9997)

Aluminium alloy: The aluminium alloy wire shall be an aluminium alloy meeting the mechanical strength and resistance of the wire properties as mentioned in the GTP.

Freedom from Defects

The wires shall be smooth & free from all imperfections such as spills, splits, slag inclusion, die marks, scratches, fittings, blow-holes, projections, looseness, overlapping of strands, chipping of aluminium layers etc. and all such other defects which may hamper the mechanical &

electrical properties of the conductor as also the installation of the conductor at the site etc. Special care should be taken to keep away dirt, grit etc. during stranding.

Joints in Wires

Aluminium Wires: No joints shall be permitted in the Aluminium wires in the outermost layer of AL-59 (Moose Equivalent) conductor. However, joints shall be permitted in the aluminium wires in the inner layers of the AL-59 conductor but tensile strength of joint wire should be at least 90% of the value required for an un joint wire but no two such joints shall be less than 15 meter apart in the complete stranded conductor. Such joints shall be made by cold pressure butt-welding.

Stranding

The wires used in the construction of AL-59 conductor shall before stranding and after

stranding shall satisfy all the relevant requirements as per the standards indicated or any other standards with due justification. The lay ratio of the different layers shall be within the limits given in Table above.

Standard Length

The standard length of the conductor shall be 1500 meter. A tolerance of +/-5% on the standard length shall be permitted. All lengths outside this limit of tolerance shall be treated as random lengths.

Random lengths will be accepted provided no length is less than 70% of the standard length specified and the total quantity of such random lengths shall not be more than 5% of the total quantity ordered.

Inspection: No material shall be dispatched from its point of manufacture before it has been satisfactorily inspected, tested by RSDCL’s nominated inspector(s) and necessary dispatch instructions are issued in writing, except for the cases where waiver of Inspection is granted by competent authority of RSDCL. Any dispatches before the issue of Dispatch Instructions in writing will be liable for rejection and non acceptance by the consignee. The acceptance of any quantity of material shall in no way relieve the Contractor of any of his responsibilities for meeting all requirements of the specification and shall not prevent subsequent rejection, if such material is later found to be defective. At least 5% of the total number of drums subject to minimum of two in any lot put up for inspection shall be selected at random to ascertain the length of conductor by following method:

Page 75: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

"At the works of the manufacturer of the conductor, the conductor shall be transferred from one drum to another, at the same time, measuring its length with the help of a graduated pulley & Cyclometer. The difference in the average length thus obtained and as declared by the Supplier/

Contractor in the packing list shall be applied to all the drums, if the conductor is found short during checking." The sample cut off from any numbers of drums for carrying out any type of tests will be to the supplier’s/Contractor’s account. Marking on drum Each drum shall have the following information stenciled on it in indelible ink along with other essential data:

(a) Contract/Award letter / order number (b) Name and address of consignee (c) Manufacturer's name and address (d) Drum Number (e) Size of conductor (f) Length of conductor in meters (g) Gross weight of drum with conductor (h) Weight of empty drum with lagging (i) Arrow marking for unwinding.

Sag and Tension charts: The successful bidder shall be required to submit three copies of stringing charts showing initial & final sags and tensions for various temperatures & spans. One set of chart should be in ink drawn on tracing cloth.

1. Tarantulla conductor:

For 220kV GSS system, ACSR ZEBRA & AAC Tarantulla (Twin) shall be used. The

specification of AAC Tarantulla`is as under:-

S.No. Item Tarantulla

1. Type AAC

2. BIS to which material shall conform / comply IS:398 (Pt-V)

3. Resistance at 20 deg. ohms/km 0.0367

4. Approx. Current carrying capacity at 75 deg. C with peak ambient temp. of 50 deg. C and without solar heating, Amp.

1169

5. No. of wires

a) Aluminium 37/5.23mm

b) Steel size --

485mm2

6. Diameter of wire (mm)

a) Aluminium 5.23

b) Steel size --

7. Dia of conductor mm 36.61

8. Sectional area mm2 Total 778

Aluminium 778

9. Weight of conductor kg / km 2197

10. Breaking load of conductor 123

1.2 Workmanship 1.2.1 The finished conductor shall be smooth, compact, uniform and free from all

imperfections including spills, die marks, scratches, abrasions, scuff marks, kinks (protrusion of wires), dents, press marks, cut marks, wire cross over, over riding looseness (wire being dislocated by finger/ hand pressure and/ or unusual

Page 76: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

bangle noise on tapping), material inclusions, white rust powder formation or black spots (on account of reaction with trapped rain water etc.) dirt, gril etc.

1.2.2 All the aluminium strands shall be smooth, uniform and free from all

imperfections, such as spills and splits, diemarks, scratches, abrasions and kinks after drawing.

1.3 Stranding 1.3.1 The wires used in manufacture of a stranded conductor shall before stranding,

satisfy all requirement of IS: 398 (Part I & V) or any other authorative standard as modified by this specification. For steel-reinforced aluminium conductors the lay ratio of the direct layers shall be within the limits given below:-

1.3.2 In all construction, the successive layers shall have opposite directions of lay, the outer-most layer being right handed. The wires in each layer shall be evenly and closely stranded.

1.3.3 In conductors having multiple layers of aluminium wires the lay ratio of any aluminium layer shall not be greater than the lay ratio of the aluminium layer immediately beneath its.

1.3.4 Lay Ratio: As per IS: 398 (Part I, II & V). 1.4 Joints in Wires

Aluminium Wires No joint shall, be permitted in the individual wires in the outermost layer of the finished

conductor. However, joints in the 12 wire and 18 wire inner layers of the conductor shall be allowed but these joints shall be made by cold pressure butt welding and shall be such that no such joints are within 15 meters of each other in the complete stranded

conductor. 1.5 Materials 1.5.1 Aluminium The aluminium strands shall be hard drawn from electrolytic aluminium rods having

purity not less than 99.5% and a copper content not exceeding 0.04%. 1.5.2 Zinc The zinc used for galvanising shall be electrolytic High Grade Zinc of 99.95% purity. It

shall conform to and satisfy all the requirements of IS: 209-1979 1.6 Standard Length

The Conductor shall be supplied in standard length of 1500 / 1800 meters as required. No joint shall be allowed within a single span of stringing.

1.7 Tests: 1.71 The following type, acceptance & routine tests and tests during manufacturing shall be

carried out on the conductor. 1.7.2 Type tests The following type tests shall be conducted on samples of conductor.

a) UTS test on stranded conductor The number of samples shall be

Page 77: RAJASTHAN SOLARPARK DEVELOPMENT COMPANY LIMITED · testing, commissioning & execution of Civil Works of allfour 220/33kV Park Pooling Sub-stations and their handing over to RSDCL,

mutually agreed between Contractor and Purchaser

b) Corona extinction voltage test (dry)

As per IS/IEC

c) Radio interference voltage test (dry)

As per IS/IEC

d) DC resistance test on stranded conductor

As per IS/IEC

1.7.3 Acceptance Tests (As applicable):

a) Visual check for joints, scratches etc. and lengths of conductor

As per IS/IEC

b) Dimensional check on steel and aluminium strands

As per IS/IEC

c) Check for lay ratios of various layers

As per IS/IEC

d) Galvanising test on steel strands As per IS/IEC e) Torsion and Elongation test on

steel strands As per IS/IEC

f) Breaking load test on steel and aluminium strands

As per IS/IEC

g) Wrap test on steel and aluminium strands

IS: 398 (Part V) 1982 clauses 12.5.2, 12.7 & 12.8

h) DC resistance test on aluminium strands

---do--

i) UTS test on welded joint of aluminium strands

As per IS/IEC

Note: All the above tests except test mentioned at (i) shall be carried out on aluminium and

steel strands after stranding only.

1.7.4 Routine Tests a) Check to ensure that the joints are as per specification. b) Check that there are no cuts, fins etc. on the strands c) All acceptance test as mentioned in clause 2.7.3 above to be carried out on each coil. 1.7.5 Test During Manufacture (As applicable):

a) Chemical analysis of zinc used for galvanising

As per IS/IEC

b) Chemical analysis of aluminium used making aluminium strands

As per IS/IEC

c) Chemical analysis of steel used for making steel strands

As per IS/IEC

1.7.6 Sample Batch for Type Testing The Contractor shall offer material for selection of samples for type testing, only after

getting quality assurance plans approved from Purchaser. The sample shall be manufactured strictly in accordance with the Quality Assurance Plan approved by Purchaser.