re4294871 rail station rail capacity project no · proposed funding (in $000s) 2016 - 2017 2017 -...
TRANSCRIPT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
RE4294871
District:
County:
RAIL CAPACITY PROJECT
SFRTA FROM HIALEAH MARKET TRI- RAIL STATION
TO MIC
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 02,400 0 2,400
0 0 0 0 0 02,400 2,400TotalPLANNING AND DESIGN
DS 0 0 0 0 01,800 0 1,800
0 0 0 0 0 01,800 1,800TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
GMR 9,295 0 0 0 00 0 9,295
LF 0 352 0 0 00 0 352
TRIP 0 352 0 0 00 0 352
9,295 704 0 0 0 00 9,999TotalCAPITAL
$14,199Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $31,200429487Item Number:
RESPONSIBLE AGENCY: So. Florida Regional Transportation Authority
Section A1 - Page 1 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLORIDA RAIL ENTERPRISE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
RE4294872
District:
County:
PURCHASE RAIL RIGHT OF WAY
SFRTA FROM HIALEAH MARKET TRI- RAIL STATION
TO MIC
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
GMR 5,705 0 0 0 00 0 5,705
LF 0 5,648 0 0 00 0 5,648
TRIP 0 5,648 0 0 00 0 5,648
5,705 11,296 0 0 0 00 17,001TotalRIGHT OF WAY
$17,001Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $31,200429487Item Number:
RESPONSIBLE AGENCY: So. Florida Regional Transportation Authority
$15,000 $12,000 $0 $0 $0$4,200 $0 $31,200Yearly Totals
5 Year TIP Total $27,000FLORIDA RAIL ENTERPRISE
Section A1 - Page 2 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLORIDA RAIL ENTERPRISE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP2539181
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
DISTRCTWIDE AVIATION ADMINISTRATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 80 80 0 0 01,199 0 1,359
80 80 0 0 0 01,199 1,359TotalADMINISTRATION
$1,359Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,359253918Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP2543871
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
DISTRCTWIDE AVIATION GRANT MANAGEMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 30 30 0 0 0342 0 402
30 30 0 0 0 0342 402TotalOPERATIONS
$402Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $402254387Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 3 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4232902
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT CONCOURSE H INTERNALIZATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0204 0 204
DPTO 0 1,950 4,001 0 2,5005,441 0 13,892
DS 0 0 0 0 01,783 0 1,783
LF 0 1,950 4,001 0 2,5007,428 0 15,879
0 3,900 8,002 0 5,000 014,856 31,758TotalCAPITAL
$31,758Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $40,542423290Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4232903
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT GATE D1 AND D2 A 380 GATE MODIFICATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,500 0 2,500
Section A1 - Page 4 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4232903
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT GATE D1 AND D2 A 380 GATE MODIFICATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,500 0 2,500
0 0 0 0 0 05,000 5,000TotalCAPITAL
$5,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $40,542423290Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4232904
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT TERMINAL F GATE IMPRVMNTS F4, F6 & F8
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,892 0 1,892
Section A1 - Page 5 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4232904
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT TERMINAL F GATE IMPRVMNTS F4, F6 & F8
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,892 0 1,892
0 0 0 0 0 03,784 3,784TotalCAPITAL
$3,784Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $40,542423290Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4277561
District:
County:
AVIATION SECURITY PROJECT
HOMESTEAD GENERAL X-51 SECURITY PROJECT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 459 0 0765 0 1,224
Section A1 - Page 6 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4277561
District:
County:
AVIATION SECURITY PROJECT
HOMESTEAD GENERAL X-51 SECURITY PROJECT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 153 0 0153 0 306
0 0 612 0 0 0918 1,530TotalCAPITAL
$1,530Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,530427756Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4277581
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT CONCOURSE E SATELLITE IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 06,928 0 6,928
DPTO 8,655 0 0 0 05,649 0 14,304
DS 0 0 0 0 051 0 51
Section A1 - Page 7 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4277581
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT CONCOURSE E SATELLITE IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 8,655 0 0 0 012,628 0 21,283
17,310 0 0 0 0 025,256 42,566TotalCAPITAL
$42,566Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $42,566427758Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4292671
District:
County:
AVIATION CAPACITY PROJECT
MIAMI HOMESTEAD GENERAL RUNWAY 18/36 CONNECTOR REHABILITATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 277 0 0 0 00 0 277
LF 69 0 0 0 00 0 69
346 0 0 0 0 00 346TotalCAPITAL
$346Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $346429267Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 8 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4292711
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT PERIMETER ROAD WIDENING & REALIGNMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 800 0 0 0 00 0 800
GMR 0 5,536 5,000 0 00 0 10,536
LF 800 5,536 5,000 0 00 0 11,336
1,600 11,072 10,000 0 0 00 22,672TotalCAPITAL
$22,672Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,673429271Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4292721
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT UPGRADE TERMINAL PLB TO 400 H2
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0850 0 850
DPTO 0 1,000 0 0 02,897 0 3,897
Section A1 - Page 9 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4292721
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT UPGRADE TERMINAL PLB TO 400 H2
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 1,000 0 0 03,747 0 4,747
0 2,000 0 0 0 07,494 9,494TotalCAPITAL
$9,494Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,494429272Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4295311
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT TERMINAL ROOF DRAINS, REROOFING AND SCUPPERS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0163 0 163
DPTO 2,000 6,164 0 0 1,0007,008 0 16,172
Section A1 - Page 10 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4295311
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT TERMINAL ROOF DRAINS, REROOFING AND SCUPPERS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 2,000 6,164 0 0 1,0007,171 0 16,335
4,000 12,328 0 0 2,000 014,342 32,670TotalCAPITAL
$32,670Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $32,670429531Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4295332
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT TAXIWAY T REHABILITATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 500100 0 600
LF 0 0 0 0 500100 0 600
0 0 0 0 1,000 0200 1,200TotalCAPITAL
Section A1 - Page 11 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
$1,200Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,400429533Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4295333
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT TAXIWAY S REHABILITATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 500100 0 600
LF 0 0 0 0 500100 0 600
0 0 0 0 1,000 0200 1,200TotalCAPITAL
$1,200Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,400429533Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4295342
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT E AND F TAXIWAY AND APRON REHAB
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 25 00 0 25
Section A1 - Page 12 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4295342
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT E AND F TAXIWAY AND APRON REHAB
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 25 00 0 25
0 0 0 50 0 00 50TotalCAPITAL
$50Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $50429534Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4311271
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI HOMESTEAD GENERAL RUNWAY 18/36 PAVEMENT REHABILITATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 377 0 0 0 00 0 377
Section A1 - Page 13 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4311271
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI HOMESTEAD GENERAL RUNWAY 18/36 PAVEMENT REHABILITATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 377 0 0 0 00 0 377
754 0 0 0 0 00 754TotalCAPITAL
$754Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $754431127Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4333711
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT TERMINAL WIDE CC E - H LIGHTNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 270 0 0 00 0 270
DPTO 0 2,500 0 0 00 0 2,500
DS 0 155 0 0 00 0 155
Section A1 - Page 14 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4333711
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT TERMINAL WIDE CC E - H LIGHTNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 2,500 0 0 00 0 2,500
LF 0 425 0 0 00 0 425
0 5,850 0 0 0 00 5,850TotalCAPITAL
$5,850Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,850433371Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4353791
District:
County:
AVIATION REVENUE/OPERATIONAL
MIAMI EXECUTIVE AIRPORT TAXIWAY REHABILITATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 1,001 0 00 0 1,001
LF 0 0 1,001 0 00 0 1,001
0 0 2,002 0 0 00 2,002TotalCAPITAL
$2,002Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,002435379Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 15 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4367741
District:
County:
AVIATION CAPACITY PROJECT
MIAMI OPA LOCKA EXECUTIVE AIRPORT INTERNAL PERIMETER ROAD SYSTEM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 2,000 00 0 2,000
LF 0 0 0 400 00 0 400
0 0 0 2,400 0 00 2,400TotalCAPITAL
$2,400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,400436774Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4367761
District:
County:
AVIATION SECURITY PROJECT
MIAMI INT'L AIRPORT NEW CENTRAL TERMINAL H THRU F
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 1,000 00 0 1,000
LF 0 0 0 1,000 00 0 1,000
0 0 0 2,000 0 00 2,000TotalCAPITAL
$2,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,000436776Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 16 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4367781
District:
County:
AVIATION CAPACITY PROJECT
MIAMI EXECUTIVE AIRPORT INTERNAL PERIMETER ROAD SYSTEM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 2,000 00 0 2,000
LF 0 0 0 400 00 0 400
0 0 0 2,400 0 00 2,400TotalCAPITAL
$2,400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,400436778Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4367791
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT CONCOURSE F APRON AND UTILITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 1,000 00 0 1,000
LF 0 0 0 1,000 00 0 1,000
0 0 0 2,000 0 00 2,000TotalCAPITAL
$2,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,000436779Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 17 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4367861
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT CONCOURSE H APRON & UTILITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 1,000 00 0 1,000
LF 0 0 0 1,000 00 0 1,000
0 0 0 2,000 0 00 2,000TotalCAPITAL
$2,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,000436786Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4386121
District:
County:
AVIATION CAPACITY PROJECT
DADE-COLLIER AIRPORT POWER DISTRIBUTION & AIRFIELD LIGHT FEEDER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 38 0 0 00 0 38
DPTO 0 167 0 0 00 0 167
Section A1 - Page 18 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4386121
District:
County:
AVIATION CAPACITY PROJECT
DADE-COLLIER AIRPORT POWER DISTRIBUTION & AIRFIELD LIGHT FEEDER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 51 0 0 00 0 51
0 256 0 0 0 00 256TotalCAPITAL
$256Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $256438612Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4386141
District:
County:
AVIATION PRESERVATION PROJECT
OPA LOCKA EXECUTIVE AIRPORT ENGINE RUN UP PAD
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 400 0 0 0 00 0 400
LF 350 0 0 0 00 0 350
Section A1 - Page 19 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4386141
District:
County:
AVIATION PRESERVATION PROJECT
OPA LOCKA EXECUTIVE AIRPORT ENGINE RUN UP PAD
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
SED 1,000 0 0 0 00 0 1,000
1,750 0 0 0 0 00 1,750TotalCAPITAL
$1,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,750438614Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4386161
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT CONCOURSE D TO E FACADE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 597 975 0 00 0 1,572
DPTO 0 3,500 0 0 2,7500 0 6,250
LF 0 4,097 975 0 2,7500 0 7,822
Section A1 - Page 20 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4386161
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT CONCOURSE D TO E FACADE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 8,194 1,950 0 5,500 00 15,644TotalCAPITAL
$15,644Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,644438616Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4386181
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT TERMINAL E THRU F CONNECTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 7,540 0 00 0 7,540
LF 0 0 7,540 0 00 0 7,540
0 0 15,080 0 0 00 15,080TotalCAPITAL
$15,080Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,080438618Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 21 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4386191
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT CONCOURSE E TO H TICKET COUNTER IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 5,000 0 00 0 5,000
LF 0 0 5,000 0 00 0 5,000
0 0 10,000 0 0 00 10,000TotalCAPITAL
$10,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,000438619Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388061
District:
County:
AVIATION CAPACITY PROJECT
MIAMI OPA LOCKA EXECUTIVE AIRPORT BLAST FENCE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 2100 0 210
LF 0 0 0 0 420 0 42
0 0 0 0 252 00 252TotalCAPITAL
$252Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $252438806Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 22 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388071
District:
County:
AVIATION CAPACITY PROJECT
MIAMI OPA LOCKA EXECUTIVE APT US CUSTOMS & BORDER PATROL FIS FACILITY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 5000 0 500
LF 0 0 0 0 1000 0 100
0 0 0 0 600 00 600TotalCAPITAL
$600Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $600438807Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388081
District:
County:
AVIATION SAFETY PROJECT
MIAMI OPA LOCKA EXECUTIVE APT UPGRADE 9R/27L TO NON-PRECISION RUNWAY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 3000 0 300
LF 0 0 0 0 600 0 60
0 0 0 0 360 00 360TotalCAPITAL
$360Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $360438808Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 23 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388091
District:
County:
AVIATION SAFETY PROJECT
MIAMI OPA LOCKA EXECUTIVE APT NEW PARALLEL TAXIWAY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 7000 0 700
LF 0 0 0 0 1400 0 140
0 0 0 0 840 00 840TotalCAPITAL
$840Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $840438809Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388101
District:
County:
AVIATION CAPACITY PROJECT
MIAMI HOMESTEAD GENERAL X51 WIDEN BLDG 6 PARKING LOT - ROADWAY ACCESS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 7500 0 750
LF 0 0 0 0 1500 0 150
0 0 0 0 900 00 900TotalCAPITAL
$900Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $900438810Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 24 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388111
District:
County:
AVIATION REVENUE/OPERATIONAL
MIAMI HOMESTEAD GENERAL X51 PAVE SW 280TH STREET
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 1500 0 150
LF 0 0 0 0 300 0 30
0 0 0 0 180 00 180TotalCAPITAL
$180Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $180438811Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388121
District:
County:
AVIATION SAFETY PROJECT
MIAMI EXECUTIVE AIRPORT FIRE STATION ADDITION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 1500 0 150
LF 0 0 0 0 300 0 30
0 0 0 0 180 00 180TotalCAPITAL
$180Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $180438812Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 25 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388131
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L APT NW BLDG 871 THROUGH 896 APRON & DRAINAGE IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 5000 0 500
LF 0 0 0 0 5000 0 500
0 0 0 0 1,000 00 1,000TotalCAPITAL
$1,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,000438813Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388141
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT SATELLITE E PAVEMENT REHABILITATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 1,0000 0 1,000
LF 0 0 0 0 1,0000 0 1,000
0 0 0 0 2,000 00 2,000TotalCAPITAL
$2,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,000438814Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 26 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388151
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT RELAMPING AIRFIELD LIGHTS WITH LED
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 5000 0 500
LF 0 0 0 0 5000 0 500
0 0 0 0 1,000 00 1,000TotalCAPITAL
$1,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,000438815Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388161
District:
County:
AVIATION SECURITY PROJECT
MIAMI INT'L FIRE PROTECTION UPGRADE OF SECURITY CCTV/COMMUNICATION RMS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 5000 0 500
LF 0 0 0 0 5000 0 500
0 0 0 0 1,000 00 1,000TotalCAPITAL
$1,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,000438816Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 27 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388181
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L APT CLOSURE OF PERIMETER ROAD ALONG FUEL FARM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 720 0 72
DPTO 0 0 0 0 4810 0 481
LF 0 0 0 0 5530 0 553
0 0 0 0 1,106 00 1,106TotalCAPITAL
$1,106Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,106438818Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388191
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT TAXI MANAGEMENT SYSTEM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 5000 0 500
Section A1 - Page 28 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388191
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT TAXI MANAGEMENT SYSTEM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 5000 0 500
0 0 0 0 1,000 00 1,000TotalCAPITAL
$1,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,000438819Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388201
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT LOWER CC E INT'L/DOMESTIC BUS STATION RENOVATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 5000 0 500
Section A1 - Page 29 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388201
District:
County:
AVIATION PRESERVATION PROJECT
MIAMI INT'L AIRPORT LOWER CC E INT'L/DOMESTIC BUS STATION RENOVATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 5000 0 500
0 0 0 0 1,000 00 1,000TotalCAPITAL
$1,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,000438820Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 30 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
AP4388211
District:
County:
AVIATION CAPACITY PROJECT
MIAMI INT'L AIRPORT & GA ENVIRONMENTAL COMPLIANCE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 5000 0 500
LF 0 0 0 0 5000 0 500
0 0 0 0 1,000 00 1,000TotalCAPITAL
$1,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,000438821Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
$25,870 $43,710 $47,646 $10,850 $26,918$73,591 $0 $228,585Yearly Totals
5 Year TIP Total $154,994FLP: AVIATION
Section A1 - Page 31 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: AVIATION
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4310772
District:
County:
PARK AND RIDE LOTS
MDT - SR 836 EXPRESS PARK AND RIDE LOT AT SW 8 ST AND SW 147 AVE
AT SW 8 ST AND SW 147 AVE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
transit signal priority and park and rides.
DPTO 874 0 0 0 00 0 874
DS 24 0 0 0 00 0 24
LF 898 0 0 0 00 0 898
1,796 0 0 0 0 00 1,796TotalCAPITAL
$1,796Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,723431077Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 32 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: INTERMODAL
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4371431
District:
County:
TRANSIT CENTER WITH PARK AND RIDE LOT
Dolphin Station at HEFT and NW 12th St Dolphin Station Intermodal Terminal
Miami Lakes Terminal
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-43
SIS or Non-SIS: No
PHASE :
Extra Description:
Project requires a CDMP amendment prior to construction.
DDR 0 0 5,000 0 0300 0 5,300
LF 0 0 5,000 0 00 0 5,000
0 0 10,000 0 0 0300 10,300TotalCAPITAL
$10,300Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,300437143Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
$1,796 $0 $10,000 $0 $0$300 $0 $12,096Yearly Totals
5 Year TIP Total $11,796FLP: INTERMODAL
Section A1 - Page 33 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: INTERMODAL
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA2496431
District:
County:
INTERMODAL HUB CAPACITY
MIAMI INTERMODAL CTR (MIC) MANAGEMENT CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 170 170 170 170 17021,934 0 22,784
DIH 0 0 0 0 0895 0 895
DS 0 0 0 0 022,384 0 22,384
LF 0 0 0 0 02,273 0 2,273
170 170 170 170 170 047,486 48,336TotalPLANNING AND DESIGN
BNCA 0 0 0 0 0291 0 291
BNDS 0 0 0 0 01,155 0 1,155
DS 0 0 0 0 0112 0 112
0 0 0 0 0 01,558 1,558TotalRIGHT OF WAY
$49,894Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $52,884249643Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 34 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA2496432
District:
County:
INTERMODAL HUB CAPACITY
MIAMI INTERMODAL CTR (MIC) LEGAL CONSULTANT FOR RENTAL CAR FACILITY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,990 0 2,990
0 0 0 0 0 02,990 2,990TotalPLANNING AND DESIGN
$2,990Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $52,884249643Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA2516846
District:
County:
INTERMODAL HUB CAPACITY
GOLDEN GLADES MULTI- MODAL TERMINAL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 033 0 33
DIS 0 0 0 0 0118 0 118
DS 0 0 0 0 015 0 15
GMR 0 0 0 0 01,415 0 1,415
SU 500 0 0 0 00 0 500
500 0 0 0 0 01,581 2,081TotalPLANNING AND DESIGN
Section A1 - Page 35 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA2516846
District:
County:
INTERMODAL HUB CAPACITY
GOLDEN GLADES MULTI- MODAL TERMINAL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 888 0 0 00 0 888
SU 0 28,210 0 0 00 0 28,210
TRIP 0 12,149 0 0 00 0 12,149
TRWR 0 6,234 0 0 00 0 6,234
0 47,481 0 0 0 00 47,481TotalDESIGN/BUILD
SU 0 0 0 0 2000 0 200
TRIP 0 0 0 0 2000 0 200
0 0 0 0 400 00 400TotalALTERNATIVE CONTRACTING INCENTIVES
$49,962Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $51,951251684Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 36 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4068001
District:
County:
INTERMODAL HUB CAPACITY
MIAMI INTERMODAL CTR (MIC) MIC CORE ROW (PRIORITY 3 ROW)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
BNCA 0 0 0 0 014 0 14
BNCA 0 0 0 0 0420 0 420
BNDS 0 0 0 0 0187 0 187
BNDS 0 0 0 0 08,168 0 8,168
DDR 0 0 0 0 067 0 67
DDR 0 0 0 0 0698 0 698
DDR 0 0 0 0 06,221 0 6,221
DIH 0 0 0 0 0141 0 141
DIRS 0 0 0 0 0364 0 364
DIRS 0 0 0 0 06,896 0 6,896
DS 0 0 0 0 0371 0 371
DS 0 0 0 0 0167 0 167
DS 345 0 0 0 0997 0 1,342
SA 0 0 0 0 015 0 15
TIFI 0 0 0 0 07,604 0 7,604
TIFI 0 0 0 0 0100,718 0 100,718
345 0 0 0 0 0133,048 133,393TotalRIGHT OF WAY
Section A1 - Page 37 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
$133,393Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $415,651406800Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4068002
District:
County:
INTERMODAL HUB CAPACITY
MIAMI INTERMODAL CTR (MIC) MIC CENTRAL STATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 018,048 0 18,048
GMR 0 0 0 0 09,509 0 9,509
SU 0 0 0 0 020,000 0 20,000
0 0 0 0 0 047,557 47,557Total
DDR 0 0 0 0 03,455 0 3,455
DIH 0 0 0 0 0321 0 321
DPTO 0 0 0 0 0185 0 185
DS 0 0 0 0 04,068 0 4,068
LF 0 0 0 0 0598 0 598
TIFI 0 0 0 0 03,210 0 3,210
0 0 0 0 0 011,837 11,837TotalPLANNING AND DESIGN
BNDS 0 0 0 0 02 0 2
DDR 300 0 0 0 06,657 0 6,957
DDR 0 0 0 0 0895 0 895
DI 2,600 0 0 0 02,600 0 5,200
DIRS 0 0 0 0 0411 0 411
Section A1 - Page 38 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4068002
District:
County:
INTERMODAL HUB CAPACITY
MIAMI INTERMODAL CTR (MIC) MIC CENTRAL STATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 0201 0 201
LF 0 0 0 0 0147 0 147
LF 0 0 0 0 0100 0 100
TRIP 0 0 0 0 0500 0 500
2,900 0 0 0 0 011,513 14,413TotalRIGHT OF WAY
DDR 0 0 0 0 05,210 0 5,210
DDR 0 0 0 0 03,859 0 3,859
DDR 0 0 0 0 05,287 0 5,287
DDR 0 0 0 0 03,572 0 3,572
DIH 0 0 0 0 0801 0 801
DS 0 0 0 0 01,000 0 1,000
DSB4 0 0 0 0 0435 0 435
LF 0 0 0 0 03,053 0 3,053
LF 0 0 0 0 0822 0 822
LF 0 0 0 0 05,337 0 5,337
SIB1 0 0 0 0 037,814 0 37,814
SIBG 0 0 0 0 07,186 0 7,186
SU 0 0 0 0 019,089 0 19,089
Section A1 - Page 39 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4068002
District:
County:
INTERMODAL HUB CAPACITY
MIAMI INTERMODAL CTR (MIC) MIC CENTRAL STATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
SU 0 0 0 0 017,318 0 17,318
TIFI 0 0 0 0 013,290 0 13,290
TRIP 0 0 0 0 07,595 0 7,595
TRIP 0 0 0 0 0403 0 403
TRIP 0 0 0 0 0122 0 122
0 0 0 0 0 0132,193 132,193TotalCONSTRUCTION
TIFI 0 0 0 0 0950 0 950
0 0 0 0 0 0950 950TotalCAPITAL
$206,950Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $415,651406800Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 40 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4068004
District:
County:
PUBLIC TRANSPORTATION STATION
MIAMI INTERMODAL CTR (MIC) TRI-RAIL RELOCATION /TEMPORARY STATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0891 0 891
0 0 0 0 0 0891 891Total
0 0 0 0 0977 0 977
0 0 0 0 0 0977 977TotalRAILROAD & UTILITIES
0 0 0 0 0555 0 555
0 0 0 0 015 0 15
0 0 0 0 0876 0 876
0 0 0 0 0 01,446 1,446TotalCONSTRUCTION
$3,314Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $415,651406800Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 41 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4068005
District:
County:
INTERMODAL HUB CAPACITY
MIAMI INTERMODAL CTR (MIC) CORE/RCF MIA MOVER STATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04,132 0 4,132
0 0 0 0 0 04,132 4,132Total
0 0 0 0 032 0 32
0 0 0 0 0 032 32TotalPLANNING AND DESIGN
0 0 0 0 04,132 0 4,132
0 0 0 0 0888 0 888
0 0 0 0 0 05,020 5,020TotalCONSTRUCTION
$9,184Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $415,651406800Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 42 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4068006
District:
County:
INTERMODAL HUB CAPACITY
MIAMI INTERMODAL CTR (MIC) MIC/MIA STATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 011,243 0 11,243
0 0 0 0 0 011,243 11,243Total
0 0 0 0 03,881 0 3,881
0 0 0 0 030,885 0 30,885
0 0 0 0 011,243 0 11,243
0 0 0 0 0 046,009 46,009TotalCONSTRUCTION
$57,252Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $415,651406800Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 43 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4083232
District:
County:
FUNDING ACTION
MIAMI INTERMODAL CTR (MIC) FDOT/DISTRICT 6 LOAN REPAYMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 18,500 9,750 1,750 1,750 1,750113,400 9,750 156,650
LF 0 0 0 0 07,415 0 7,415
LFNE 16,116 16,854 1,847 0 060,182 0 94,999
34,616 26,604 3,597 1,750 1,750 9,750180,997 259,064TotalADMINISTRATION
$259,064Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $276,171408323Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4083241
District:
County:
FUNDING ACTION
MIAMI INTERMODAL CTR (MIC) RENTAL CAR FACILITY (RCF) TIFIA LOAN REPAYM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LFNE 19,397 19,824 19,762 19,851 19,94272,105 102,211 273,092
19,397 19,824 19,762 19,851 19,942 102,21172,105 273,092TotalADMINISTRATION
$273,092Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $273,092408324Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 44 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4280114
District:
County:
INTERMODAL HUB CAPACITY
MDT - NW 27TH AVENUE ENHANCED BUS SERVICE BUS TERMINAL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,595 0 1,595
0 0 0 0 01,586 0 1,586
0 0 0 0 0 03,181 3,181TotalCAPITAL
$3,181Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,826428011Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4353811
District:
County:
INTERMODAL HUB CAPACITY
MDT - PALMETTO INTERMODAL TERMINAL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 2,091 0 00 0 2,091
DPTO 0 0 235 386 00 0 621
DS 0 0 395 0 00 0 395
Section A1 - Page 45 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4353811
District:
County:
INTERMODAL HUB CAPACITY
MDT - PALMETTO INTERMODAL TERMINAL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 1,338 95 00 0 1,433
0 0 4,059 481 0 00 4,540TotalCAPITAL
$4,540Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,540435381Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4379501
District:
County:
PTO STUDIES
DISTRICT INTERMODAL LOGISTIC CENTER (ILC) DEVELOPMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 20 0 00 0 20
Section A1 - Page 46 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4379501
District:
County:
PTO STUDIES
DISTRICT INTERMODAL LOGISTIC CENTER (ILC) DEVELOPMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 300 0 00 0 300
0 0 320 0 0 00 320TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$320Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $320437950Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 47 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4388421
District:
County:
PTO STUDIES
PORTMIAMI TUNNEL FREIGHT MOBILITY EVALUATION STUDY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
HPP 1,440 0 0 0 00 0 1,440
SA 250 0 0 0 00 0 250
1,690 0 0 0 0 00 1,690TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,690Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,690438842Item Number:
RESPONSIBLE AGENCY: FDOT
$59,618 $94,079 $27,908 $22,252 $22,262$716,746 $111,961 $1,054,826Yearly Totals
5 Year TIP Total $226,119FLP: MULTIMODAL FACILITY
Section A1 - Page 48 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: MULTIMODAL FACILITY
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TR2544391
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
D/W INTERMODAL/RAIL ADMINISTRATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 70 70 0 0 01,087 0 1,227
70 70 0 0 0 01,087 1,227TotalADMINISTRATION
$1,227Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,227254439Item Number:
RESPONSIBLE AGENCY: So. Florida Regional Transportation Authority
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TR2544411
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
D/W INTERMODAL/RAIL GRANTS MANAGEMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 85 85 0 0 01,123 0 1,293
85 85 0 0 0 01,123 1,293TotalOPERATIONS
$1,293Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,293254441Item Number:
RESPONSIBLE AGENCY: So. Florida Regional Transportation Authority
Section A1 - Page 49 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: RAIL
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TR4335111
District:
County:
RAIL CAPACITY PROJECT
NE 203 ST & NE 215 ST INTERSECTION IMPROVMTS BTWN US-1 & W DIXIE HWY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 029 0 29
0 0 0 0 0 029 29TotalPLANNING AND DESIGN
0 0 0 0 02,526 0 2,526
0 0 0 0 0 02,526 2,526TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,555Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $28,550433511Item Number:
RESPONSIBLE AGENCY: So. Florida Regional Transportation Authority
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TR4335112
District:
County:
RAIL CAPACITY PROJECT
NE 203 STREET INTERSECTION IMPROVEMENTS BETWN SR 5/US-1 & W DIXIE HWY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 200 0 0 0 010 0 210
DIS 0 0 0 0 02,100 0 2,100
GMR 3,530 0 0 0 00 0 3,530
Section A1 - Page 50 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: RAIL
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TR4335112
District:
County:
RAIL CAPACITY PROJECT
NE 203 STREET INTERSECTION IMPROVEMENTS BETWN SR 5/US-1 & W DIXIE HWY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
3,730 0 0 0 0 02,110 5,840TotalPLANNING AND DESIGN
DDR 0 3,777 0 0 00 0 3,777
DDR 0 0 0 0 030 0 30
DIH 38 20 0 0 00 0 58
DS 0 400 2,100 0 00 0 2,500
GMR 13,790 0 0 0 00 0 13,790
13,828 4,197 2,100 0 0 030 20,155TotalRIGHT OF WAY
$25,995Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $28,550433511Item Number:
RESPONSIBLE AGENCY: So. Florida Regional Transportation Authority
$17,713 $4,352 $2,100 $0 $0$6,905 $0 $31,070Yearly Totals
5 Year TIP Total $24,165FLP: RAIL
Section A1 - Page 51 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: RAIL
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
SP2544571
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
DISTRICTWIDE SEAPORTS ADMINISTRATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 50 50 0 0 0482 0 582
50 50 0 0 0 0482 582TotalADMINISTRATION
$582Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $582254457Item Number:
RESPONSIBLE AGENCY: Miami-Dade Seaport Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
SP4311261
District:
County:
SEAPORT CAPACITY PROJECT
PORT OF MIAMI, PORT OF MIAMI (POM) POST PANAMAX CRANES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIS 443 6,000 0 0 00 0 6,443
DPTO 931 0 0 0 00 0 931
GMR 0 0 10,000 0 05,000 0 15,000
LF 1,374 6,000 10,000 0 08,935 0 26,309
PORB 0 0 0 0 02,880 0 2,880
Section A1 - Page 52 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: SEAPORT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
SP4311261
District:
County:
SEAPORT CAPACITY PROJECT
PORT OF MIAMI, PORT OF MIAMI (POM) POST PANAMAX CRANES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
PORT 0 0 0 0 01,055 0 1,055
2,748 12,000 20,000 0 0 017,870 52,618TotalCAPITAL
$52,618Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $52,618431126Item Number:
RESPONSIBLE AGENCY: Miami-Dade Seaport Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
SP4333631
District:
County:
SEAPORT CAPACITY PROJECT
PORT OF MIAMI CRUISE TERMINAL IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 2,750 0 0 0 04,000 0 6,750
POED 0 0 0 0 04,000 0 4,000
Section A1 - Page 53 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: SEAPORT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
SP4333631
District:
County:
SEAPORT CAPACITY PROJECT
PORT OF MIAMI CRUISE TERMINAL IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
PORT 2,750 0 0 0 00 0 2,750
5,500 0 0 0 0 08,000 13,500TotalCAPITAL
$13,500Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,500433363Item Number:
RESPONSIBLE AGENCY: Miami-Dade Seaport Department
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
SP4380291
District:
County:
SEAPORT CAPACITY PROJECT
PORT OF MIAMI PASSENGER BOARDING BRIDGES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 2,3000 0 2,300
LF 0 0 0 0 2,3000 0 2,300
Section A1 - Page 54 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: SEAPORT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
SP4380291
District:
County:
SEAPORT CAPACITY PROJECT
PORT OF MIAMI PASSENGER BOARDING BRIDGES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 4,600 00 4,600TotalCAPITAL
$4,600Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,600438029Item Number:
RESPONSIBLE AGENCY: Miami-Dade Seaport Department
$8,298 $12,050 $20,000 $0 $4,600$26,352 $0 $71,300Yearly Totals
5 Year TIP Total $44,948FLP: SEAPORT
Section A1 - Page 55 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: SEAPORT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4162223
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FL VANPOOL - FTA 5307 & STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
LRTP Ref: 5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 1,710 1,710 0 0 03,420 0 6,840
LF 337 337 0 0 0674 0 1,348
2,047 2,047 0 0 0 04,094 8,188TotalCAPITAL
$8,188Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $27,090Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4179172
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT-S MIA DADE BSWY ROUTES OPERATING ASSISTNC
FROM DADELAND TO FL CITY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
LRTP Ref: C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 189 189 0 0 0715 0 1,093
DPTO 0 0 0 0 03,952 0 3,952
189 189 0 0 0 04,667 5,045TotalOPERATIONS
$5,045Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $27,090Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 56 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329341
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - 95 EXPRESS DADE/BROWARD CIVIC CENTER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
LRTP Ref: C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 268 00 0 268
TOBD 0 0 400 400 02,922 0 3,722
0 0 400 668 0 02,922 3,990TotalOPERATIONS
$3,990Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $27,090Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389501
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - SOUTH MIAMI DADE BUSWAY ROUTES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
LRTP Ref:
0
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 4670 0 467
0 0 0 0 467 00 467TotalOPERATIONS
$467Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $27,090Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 57 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389701
District:
County:
PURCHASE VEHICLES/EQUIPMENT
MDT - SR 836 EXPRESS BUS SERVICE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
SIS or Non-SIS: No
PHASE :
Extra Description:
CIGP 0 0 0 4,700 00 0 4,700
LF 0 0 0 4,700 00 0 4,700
0 0 0 9,400 0 00 9,400TotalCAPITAL
$9,400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $27,090Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA2538911
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
DISTRICTWIDE TRANSIT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 30 30 0 0 0214 0 274
30 30 0 0 0 0214 274TotalOPERATIONS
$274Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $274253891Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 58 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA2538921
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
DISTRICTWIDE TRANSIT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 50 50 0 0 01,100 0 1,200
50 50 0 0 0 01,100 1,200TotalOPERATIONS
$1,200Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,200253892Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA2538971
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
DISTRICTWIDE TRANSIT MOTION SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 50 50 0 0 0588 0 688
50 50 0 0 0 0588 688TotalOPERATIONS
$688Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $688253897Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 59 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA2539081
District:
County:
PUBLIC TRANS IN-HOUSE SUPPORT
DISTRICTWIDE TRANSIT SPECIAL PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 80 80 0 0 01,282 0 1,442
80 80 0 0 0 01,282 1,442TotalADMINISTRATION
$1,442Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,442253908Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4051331
District:
County:
FIXED GUIDEWAY IMPROVEMENTS
MIAMI-DADE TRANSIT AGENCY (GUIDEWAY BRIDGE INSPECTION)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 06,750 0 6,750
0 0 0 0 06,750 0 6,750
0 0 0 0 0188 0 188
0 0 0 0 0 013,688 13,688TotalCAPITAL
$13,688Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,563405133Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 60 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4051332
District:
County:
FIXED GUIDEWAY IMPROVEMENTS
MIAMI-DADE TRANSIT (GUIDEWAY BRIDGE INSPECTION)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,500 0 3,500
0 0 0 0 03,500 0 3,500
0 0 0 0 0875 0 875
0 0 0 0 0 07,875 7,875TotalCAPITAL
$7,875Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,563405133Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4051333
District:
County:
FIXED GUIDEWAY IMPROVEMENTS
MDT - FTA SEC 5307 METRORAIL & METROMOVER GUIDEWAY BRIDGE INSPECTNS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,000 0 3,000
0 0 0 0 03,000 0 3,000
Section A1 - Page 61 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4051333
District:
County:
FIXED GUIDEWAY IMPROVEMENTS
MDT - FTA SEC 5307 METRORAIL & METROMOVER GUIDEWAY BRIDGE INSPECTNS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0750 0 750
0 0 0 0 0 06,750 6,750TotalCAPITAL
$6,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,563405133Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4051334
District:
County:
FIXED GUIDEWAY IMPROVEMENTS
MDT - FTA SEC 5307 METRORAIL & METROMOVER GUIDEWAY BRIDGE INSPECTNS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTAT 1,000 1,000 1,000 1,000 01,000 0 5,000
LF 250 250 250 250 0250 0 1,250
Section A1 - Page 62 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4051334
District:
County:
FIXED GUIDEWAY IMPROVEMENTS
MDT - FTA SEC 5307 METRORAIL & METROMOVER GUIDEWAY BRIDGE INSPECTNS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
SU 1,000 1,000 1,000 1,000 01,000 0 5,000
2,250 2,250 2,250 2,250 0 02,250 11,250TotalCAPITAL
$11,250Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,563405133Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4162222
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FL VANPOOL - FTA 5307 & STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04,830 0 4,830
0 0 0 0 01,046 0 1,046
0 0 0 0 0 05,876 5,876TotalCAPITAL
Section A1 - Page 63 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
$5,876Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,876416222Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4179171
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDTA/S MIA DADE BSWY ROUTES OPERATING ASSISTNC
FROM DADELAND TO FL CITY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,735 0 2,735
0 0 0 0 0 02,735 2,735TotalOPERATIONS
$2,735Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,850417917Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4179173
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT-S MIA DADE BSWY ROUTES OPERATING ASSISTNC
FROM DADELAND TO FL CITY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 153 0 0 0 00 0 153
Section A1 - Page 64 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4179173
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT-S MIA DADE BSWY ROUTES OPERATING ASSISTNC
FROM DADELAND TO FL CITY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 847 1,000 0 115 00 0 1,962
1,000 1,000 0 115 0 00 2,115TotalOPERATIONS
$2,115Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,850417917Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4180511
District:
County:
COMMUTER TRANS. ASSISTANCE
MDTA - DADE-MONROE EXPRESS FROM FLORIDA CITY TO MARATHON (MM 50)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,220 0 1,220
0 0 0 0 01,220 0 1,220
0 0 0 0 0 02,440 2,440TotalOPERATIONS
Section A1 - Page 65 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
$2,440Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,732418051Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4180513
District:
County:
COMMUTER TRANS. ASSISTANCE
MDT - DADE/MONROE EXPRESS BUS ROUTE
FROM FL CITY TO MARATHON (MM 50)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 546 0 515 527 9040 0 2,492
DS 1,279 875 0 0 00 0 2,154
LF 1,825 875 515 527 9040 0 4,646
3,650 1,750 1,030 1,054 1,808 00 9,292TotalOPERATIONS
$9,292Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,732418051Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 66 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204521
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE COUNTY - TMI SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,681 0 1,681
0 0 0 0 0 01,681 1,681TotalPLANNING
$1,681Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,890420452Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204522
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE COUNTY - TDM OUTREACH
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 354 408 0 0 0447 0 1,209
SU 0 0 500 500 00 0 1,000
354 408 500 500 0 0447 2,209TotalPLANNING
$2,209Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,890420452Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 67 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204601
District:
County:
PARK AND RIDE LOTS
MDTA - QUAIL ROOST DRIVE AT SOUTH MIAMI-DADE BUSWAY/PARK & RIDE LOT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,879 0 2,879
0 0 0 0 02,879 0 2,879
0 0 0 0 0720 0 720
0 0 0 0 0 06,478 6,478TotalCAPITAL
$6,478Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,478420460Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204622
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDTA - I-95 EXPRESS DOWNTOWN MIA ALONG I95 TO SHERIDAN ST & BROWRD BLV
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 013,845 0 13,845
Section A1 - Page 68 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204622
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDTA - I-95 EXPRESS DOWNTOWN MIA ALONG I95 TO SHERIDAN ST & BROWRD BLV
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,461 0 3,461
0 0 0 0 0 017,306 17,306TotalCAPITAL
$17,306Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,405420462Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 69 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204623
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE I-95 EXPRESS CALL CENTER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0359 0 359
0 0 0 0 0 0359 359TotalPLANNING
$359Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,405420462Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204624
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE I-95 EXPRESS CALL CENTER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0664 0 664
0 0 0 0 0 0664 664TotalPLANNING
$664Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,405420462Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 70 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204627
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE I-95 EXPRESS CALL CENTER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 072 0 72
0 0 0 0 0 072 72TotalPLANNING
$72Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,405420462Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204628
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE I-95 EXPRESS CALL CENTER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 201 201 201 201 0200 0 1,004
201 201 201 201 0 0200 1,004TotalPLANNING
$1,004Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,405420462Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 71 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4222391
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE COUNTY - OPERATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,553 0 3,553
0 0 0 0 0 03,553 3,553TotalPLANNING
$3,553Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,892422239Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4222392
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE COUNTY - OPERATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 58 0 0 00 0 58
DPTO 875 717 513 526 526875 0 4,032
875 775 513 526 526 0875 4,090TotalPLANNING
$4,090Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,892422239Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 72 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4222393
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE COUNTY - OPERATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
CM 36 36 24 24 0127 0 247
SA 0 0 0 0 02 0 2
36 36 24 24 0 0129 249TotalPLANNING
$249Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,892422239Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4222421
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE COUNTY - MARKETING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,843 0 3,843
0 0 0 0 0 03,843 3,843TotalPLANNING
$3,843Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,143422242Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 73 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4222422
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA COMMUTER SERVICES IN MIAMI-DADE COUNTY - MARKETING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SU 850 850 850 850 0900 0 4,300
850 850 850 850 0 0900 4,300TotalPLANNING
$4,300Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,143422242Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4225291
District:
County:
TRANSIT SERVICE DEMONSTRATION
MDT-KENDALL DRIVE ENHANCED BUS SERVICE FRM DADELAND N TO SW 167 AVE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0599 0 599
0 0 0 0 0599 0 599
0 0 0 0 0 01,198 1,198TotalOPERATIONS
$1,198Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,748422529Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 74 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4225292
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT-KENDALL CRUISER FROM DADELAND NORTH STN TO SW 162 AVENUE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 550 550 0 0 00 0 1,100
DPTO 0 0 0 550 01,900 0 2,450
550 550 0 550 0 01,900 3,550TotalOPERATIONS
$3,550Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,748422529Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4280115
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - NW 27TH AVENUE CORRIDOR ROBUST BUS STATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 2,363 00 0 2,363
DPTO 0 0 0 1,282 00 0 1,282
0 0 0 3,645 0 00 3,645TotalCAPITAL
$3,645Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,826428011Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 75 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4289751
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 020,440 0 20,440
0 0 0 0 020,440 0 20,440
0 0 0 0 0 040,880 40,880TotalOPERATIONS
$40,880Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $82,484428975Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4289752
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0475 0 475
0 0 0 0 0475 0 475
0 0 0 0 0 0950 950TotalOPERATIONS
$950Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $82,484428975Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 76 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4289753
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 11,260 0 0 0 00 0 11,260
DPTO 8,592 0 0 0 00 0 8,592
LF 19,852 0 0 0 00 0 19,852
39,704 0 0 0 0 00 39,704TotalOPERATIONS
$39,704Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $82,484428975Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4289754
District:
County:
COMMUTER TRANS. ASSISTANCE
MDT - STATE TRANSIT BLOCK GRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 475 0 0 0 00 0 475
Section A1 - Page 77 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4289754
District:
County:
COMMUTER TRANS. ASSISTANCE
MDT - STATE TRANSIT BLOCK GRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 475 0 0 0 00 0 475
950 0 0 0 0 00 950TotalOPERATIONS
$950Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $82,484428975Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4289821
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5307 FEDERAL FORMULA FUNDING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 055,000 0 55,000
0 0 0 0 013,750 0 13,750
0 0 0 0 0 068,750 68,750TotalCAPITAL
Section A1 - Page 78 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
$68,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $137,500428982Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4289822
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5307 FEDERAL FORMULA FUNDING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 55,000 0 0 0 00 0 55,000
LF 13,750 0 0 0 00 0 13,750
68,750 0 0 0 0 00 68,750TotalCAPITAL
$68,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $137,500428982Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4309521
District:
County:
PTO STUDIES
MIAMI-DADE CO MPO FTA SECTION 5303 METRO PLANNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 213 0 0 0 00 0 213
DU 1,706 0 0 0 00 0 1,706
Section A1 - Page 79 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4309521
District:
County:
PTO STUDIES
MIAMI-DADE CO MPO FTA SECTION 5303 METRO PLANNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 213 0 0 0 00 0 213
2,132 0 0 0 0 00 2,132TotalPLANNING
$2,132Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,132430952Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 80 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4309531
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - FLAGLER MAX (RTE51)OPERATING ASSISTNC
FROM W MIA DADE TO DTWN
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 1,110 1,016 2,117 570 00 0 4,813
1,110 1,016 2,117 570 0 00 4,813TotalOPERATIONS
$4,813Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,813430953Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204625
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - 95 EXPRESS DADE BROWARD EXPRESS (MIAMI CBD)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 0 0 800 1,305 01,247 0 3,352
0 0 800 1,305 0 01,247 3,352TotalOPERATIONS
$3,352Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,723431077Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 81 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4310773
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - SR 836 EXPRESS ENHANCED BUS SERVICE (BUS PURCHASE)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
CIGP 0 0 0 0 00 0 0
0 0 0 0 0 00 0TotalCAPITAL
$0Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,723431077Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4310774
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - SR 836 EXPRESS PANTHER STATION @ FIU
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
CM 1,570 1,550 0 0 01,571 0 4,691
FTAT 1,570 1,550 0 0 01,571 0 4,691
LF 393 393 0 0 0407 0 1,193
3,533 3,493 0 0 0 03,549 10,575TotalCAPITAL
$10,575Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,723431077Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 82 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329361
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 8,762 0 0 00 0 8,762
DPTO 0 11,890 0 0 00 0 11,890
LF 0 20,652 0 0 00 0 20,652
0 41,304 0 0 0 00 41,304TotalOPERATIONS
$41,304Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $85,950432936Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329362
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 487 0 0 00 0 487
Section A1 - Page 83 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329362
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 487 0 0 00 0 487
0 974 0 0 0 00 974TotalOPERATIONS
$974Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $85,950432936Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329363
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 244 0 00 0 244
DPTO 0 0 259 0 00 0 259
Section A1 - Page 84 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329363
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 503 0 00 0 503
0 0 1,006 0 0 00 1,006TotalOPERATIONS
$1,006Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $85,950432936Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329365
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 11,758 0 00 0 11,758
DPTO 0 0 9,575 0 00 0 9,575
LF 0 0 21,333 0 00 0 21,333
Section A1 - Page 85 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329365
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 42,666 0 0 00 42,666TotalOPERATIONS
$42,666Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $85,950432936Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329391
District:
County:
PTO STUDIES
MIAMI-DADE CO MPO FTA SECTION 5303 METRO PLANNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 158 0 0 00 0 158
DU 0 1,265 0 0 00 0 1,265
LF 0 1,423 0 0 00 0 1,423
0 2,846 0 0 0 00 2,846TotalPLANNING
$2,846Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,846432939Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 86 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4329651
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5307 FEDERAL FORMULA FUNDING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 0 55,000 0 0 00 0 55,000
LF 0 13,750 0 0 00 0 13,750
0 68,750 0 0 0 00 68,750TotalCAPITAL
$68,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $68,750432965Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4335251
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FLAGLER ENHANCED BUS SERVICE (BUS PURCHASE)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
CIGP 4,567 452 0 0 00 0 5,019
LF 4,567 452 0 0 00 0 5,019
9,134 904 0 0 0 00 10,038TotalCAPITAL
$10,038Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,038433525Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 87 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4348971
District:
County:
PTO STUDIES
MIAMI-DADE CO - MPO FTA SECTION 5305(D) METRO PLANNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 158 0 00 0 158
DU 0 0 1,265 0 00 0 1,265
LF 0 0 158 0 00 0 158
0 0 1,581 0 0 00 1,581TotalPLANNING
$1,581Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,581434897Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4349751
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5307 FEDERAL FORMULA FUNDING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 0 0 55,000 0 00 0 55,000
Section A1 - Page 88 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4349751
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5307 FEDERAL FORMULA FUNDING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 13,750 0 00 0 13,750
0 0 68,750 0 0 00 68,750TotalCAPITAL
$68,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $68,750434975Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4349791
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 24,000 0 0 0 00 0 24,000
Section A1 - Page 89 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4349791
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 6,000 0 0 0 00 0 6,000
30,000 0 0 0 0 00 30,000TotalCAPITAL
$30,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $30,000434979Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4349801
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 0 24,000 0 0 00 0 24,000
Section A1 - Page 90 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4349801
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 6,000 0 0 00 0 6,000
0 30,000 0 0 0 00 30,000TotalCAPITAL
$30,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $30,000434980Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4349811
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 0 0 24,000 0 00 0 24,000
Section A1 - Page 91 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4349811
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 6,000 0 00 0 6,000
0 0 30,000 0 0 00 30,000TotalCAPITAL
$30,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $30,000434981Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 92 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4366951
District:
County:
PURCHASE VEHICLES/EQUIPMENT
CITY OF MIAMI - TROLLEY TRANSIT CORRIDOR PROGRAM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 294 00 0 294
0 0 0 294 0 00 294TotalCAPITAL
$294Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $294436695Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4368821
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5339 BUS AND BUS FACILITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 12,000 6,000 6,000 6,000 06,000 0 36,000
LF 3,000 1,500 1,500 1,500 01,500 0 9,000
15,000 7,500 7,500 7,500 0 07,500 45,000TotalCAPITAL
$45,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $45,000436882Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 93 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4368891
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 0 0 0 25,000 00 0 25,000
LF 0 0 0 6,250 00 0 6,250
0 0 0 31,250 0 00 31,250TotalCAPITAL
$31,250Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $31,250436889Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4368911
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5307 TRANSIT OPERATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 0 0 0 55,000 00 0 55,000
LF 0 0 0 13,750 00 0 13,750
0 0 0 68,750 0 00 68,750TotalCAPITAL
$68,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $68,750436891Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 94 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4379451
District:
County:
PTO STUDIES
DORAL FREIGHT IMPROVEMENT PLAN STUDY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 20 0 0 0 00 0 20
DS 300 0 0 0 00 0 300
320 0 0 0 0 00 320TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$320Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $320437945Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4379461
District:
County:
PTO STUDIES
MIAMI RIVER FREIGHT IMPROVEMENT PLAN
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 20 0 0 0 00 0 20
DS 300 0 0 0 00 0 300
320 0 0 0 0 00 320TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$320Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $320437946Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 95 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4379471
District:
County:
PTO STUDIES
FREIGHT VILLAGE ANALYSIS STUDY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 20 0 0 00 0 20
DS 0 300 0 0 00 0 300
0 320 0 0 0 00 320TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$320Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $320437947Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4379491
District:
County:
PTO STUDIES
HIALEAH IMPROVEMENT PLAN STUDY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 20 0 0 00 0 20
DS 0 300 0 0 00 0 300
0 320 0 0 0 00 320TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$320Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $320437949Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 96 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4379991
District:
County:
PTO STUDIES
HOMESTEAD FREIGHT IMPROVEMENT PLAN STUDY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 20 00 0 20
DS 0 0 0 300 00 0 300
0 0 0 320 0 00 320TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$320Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $320437999Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4387311
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 12,5860 0 12,586
DPTO 0 0 0 0 10,9730 0 10,973
Section A1 - Page 97 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4387311
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 23,5590 0 23,559
0 0 0 0 47,118 00 47,118TotalOPERATIONS
$47,118Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $47,118438731Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4387321
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 5280 0 528
Section A1 - Page 98 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4387321
District:
County:
OPERATING FOR FIXED ROUTE
MDT - STATE TRANSIT BLOCK GRRANT FOR SOUTH FLORIDA VANPOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 5280 0 528
0 0 0 0 1,056 00 1,056TotalOPERATIONS
$1,056Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,056438732Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4387361
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 25,000 0 0 0 00 0 25,000
Section A1 - Page 99 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4387361
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5337 FEDERAL FORMULA FUNDING STATE OF GOOD REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 6,250 0 0 0 00 0 6,250
31,250 0 0 0 0 00 31,250TotalCAPITAL
$31,250Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $31,250438736Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4387371
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5339 BUS AND BUS FACILITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
FTA 6,000 0 0 0 00 0 6,000
Section A1 - Page 100 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4387371
District:
County:
CAPITAL FOR FIXED ROUTE
MDT - FTA SECTION 5339 BUS AND BUS FACILITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 1,500 0 0 0 00 0 1,500
7,500 0 0 0 0 00 7,500TotalCAPITAL
$7,500Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,500438737Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 101 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4388401
District:
County:
COMMUTER TRANS. ASSISTANCE
SOUTH FLA VANPOOL MIAMI-DADE COUNTY MDT MARKETING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 75 75 75 75 750 0 375
75 75 75 75 75 00 375TotalOPERATIONS
$375Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $375438840Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389321
District:
County:
TRANSIT SERVICE DEMONSTRATION
UNIVERSITY CITY TRANSPORTATION MGMT ASSOCIATION (TMA) OF SWEETWATER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 200 0 0 0 00 0 200
LF 200 0 0 0 00 0 200
400 0 0 0 0 00 400TotalOPERATIONS
$400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $400438932Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 102 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389331
District:
County:
TRANSIT SERVICE DEMONSTRATION
CITY OF MIAMI - LITTLE HAVANA TROLLEY ROUTE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 145 0 0 0 00 0 145
LF 145 0 0 0 00 0 145
290 0 0 0 0 00 290TotalOPERATIONS
$290Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $290438933Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389341
District:
County:
TRANSIT SERVICE DEMONSTRATION
CITY OF MIAMI TROLLEY - WYNWOOD TROLLEY ROUTE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 75 0 0 0 00 0 75
LF 75 0 0 0 00 0 75
150 0 0 0 0 00 150TotalOPERATIONS
$150Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $150438934Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 103 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389351
District:
County:
PURCHASE VEHICLES/EQUIPMENT
CITY OF MIAMI - TROLLEY VEHICLES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 3540 0 354
LF 0 0 0 0 3540 0 354
0 0 0 0 708 00 708TotalCAPITAL
$708Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $708438935Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389361
District:
County:
PTO STUDIES
MIAMI-DADE CO - MPO FTA SECTION 5305(D) METRO PLANNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 1680 0 168
DU 0 0 0 0 1,3420 0 1,342
Section A1 - Page 104 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389361
District:
County:
PTO STUDIES
MIAMI-DADE CO - MPO FTA SECTION 5305(D) METRO PLANNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 1680 0 168
0 0 0 0 1,678 00 1,678TotalPLANNING
$1,678Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,678438936Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204602
District:
County:
PARK AND RIDE LOTS
MDT-PARK & RIDE LOT AT S MIAMI-DADE BUSWAY/QUAIL ROOST & EUREKA DR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 014 0 14
DPTO 200 0 0 0 0595 0 795
DS 0 0 0 0 0638 0 638
Section A1 - Page 105 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4204602
District:
County:
PARK AND RIDE LOTS
MDT-PARK & RIDE LOT AT S MIAMI-DADE BUSWAY/QUAIL ROOST & EUREKA DR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 200 0 0 0 01,247 0 1,447
400 0 0 0 0 02,494 2,894TotalCAPITAL
$2,894Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,566438943Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 106 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389431
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - 95 EXPRESS DADE/BROWARD EXPRESS MIAMI CBD
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 0 0 0 0 8003,872 0 4,672
0 0 0 0 800 03,872 4,672TotalOPERATIONS
$4,672Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,566438943Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389461
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - 95 EXPRESS DADE/BROWARD CIVIC CENTER
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 0 0 0 0 4000 0 400
0 0 0 0 400 00 400TotalOPERATIONS
$400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $400438946Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Section A1 - Page 107 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389481
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - FLAGLER MAX (ROUTE 51)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 5100 0 510
0 0 0 0 510 00 510TotalOPERATIONS
$510Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $510438948Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389491
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - KENDALL CRUISER (ROUTE 288)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
DPTO 0 0 0 0 1650 0 165
Section A1 - Page 108 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
TA4389491
District:
County:
URBAN CORRIDOR IMPROVEMENTS
MDT - KENDALL CRUISER (ROUTE 288)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 1650 0 165
0 0 0 0 330 00 330TotalOPERATIONS
$330Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $330438949Item Number:
RESPONSIBLE AGENCY: FDOT
$223,230 $167,768 $160,263 $129,847 $55,476$225,328 $0 $961,912Yearly Totals
5 Year TIP Total $736,584FLP: TRANSIT
Section A1 - Page 109 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
FLP: TRANSIT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT1043
District:
County:
TOLL PLAZA
TOLL OPERATIONS MIAMI DADE XWAY - DOLPHIN
Roadway ID:
Project Length: 13.048
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87200000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
PKYO 0 0 0 0 02 0 2
TO04 4,748 4,758 4,768 4,795 4,79566,811 23,977 114,652
4,748 4,758 4,768 4,795 4,795 23,97766,813 114,654TotalOPERATIONS
$114,654Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $114,654104Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2485941
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE ROW MAP PREPARATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 60 60 60 60 01,189 0 1,429
DS 0 0 0 0 05 0 5
60 60 60 60 0 01,194 1,434TotalPLANNING AND DESIGN
$1,434Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,434248594Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 110 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2491121
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM 2000FT S OF NW 25 ST TO 2000FT N OF NW 25 ST
Roadway ID:
Project Length: 0.858
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0397 0 397
0 0 0 0 0 0397 397TotalPLANNING AND DESIGN
0 0 0 0 01 0 1
0 0 0 0 0 01 1TotalRIGHT OF WAY
0 0 0 0 048 0 48
0 0 0 0 018,469 0 18,469
0 0 0 0 0 018,517 18,517TotalCONSTRUCTION
0 0 0 0 01,200 0 1,200
0 0 0 0 0 01,200 1,200TotalALTERNATIVE CONTRACTING INCENTIVES
$20,115Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,480249112Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 111 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2491122
District:
County:
LANDSCAPING
SR 826/PALMETTO EXPY FROM NW 14 STREET TO NW 31 STREET
Roadway ID:
Project Length: 0.769
Lanes Exist:Lanes Improved:Lanes Added:
10
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 096 0 96
0 0 0 0 0 0116 116TotalPLANNING AND DESIGN
DI 1,045 0 0 0 00 0 1,045
DIH 69 0 0 0 00 0 69
DS 135 0 0 0 00 0 135
1,249 0 0 0 0 00 1,249TotalCONSTRUCTION
$1,365Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,480249112Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2495811
District:
County:
INTERCHANGE - ADD LANES
SR 826/SR 836 FROM N OF SW 8 ST TO S OF NW 25 ST & FM NW 87 TO 57 AVE'
Roadway ID:
Project Length: 4.831
Lanes Exist:Lanes Improved:Lanes Added:
7
7
2
MIAMI-DADE
LRTP Ref:
87200000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 08,576 0 8,576
Section A1 - Page 112 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2495811
District:
County:
INTERCHANGE - ADD LANES
SR 826/SR 836 FROM N OF SW 8 ST TO S OF NW 25 ST & FM NW 87 TO 57 AVE'
Roadway ID:
Project Length: 4.831
Lanes Exist:Lanes Improved:Lanes Added:
7
7
2
MIAMI-DADE
LRTP Ref:
87200000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 0 04,646 0 4,646
DIH 0 0 0 0 0984 0 984
DS 0 0 0 0 02,737 0 2,737
GMR 0 0 0 0 0250 0 250
LF 0 0 0 0 015,890 0 15,890
NHPP 0 0 0 0 0800 0 800
0 0 0 0 0 033,883 33,883TotalPLANNING AND DESIGN
BNCA 0 0 0 0 03,024 0 3,024
BNDS 0 0 0 0 09,188 0 9,188
BNIR 0 0 0 0 0632 0 632
BNIR 0 0 0 0 07,364 0 7,364
DDR 0 0 0 0 01,868 0 1,868
DDR 0 0 0 0 010,404 0 10,404
DI 0 0 0 0 09,443 0 9,443
DIH 0 0 0 0 03,070 0 3,070
DIRS 0 0 0 0 0584 0 584
DS 0 0 0 0 021 0 21
DS 0 0 0 0 02,637 0 2,637
Section A1 - Page 113 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2495811
District:
County:
INTERCHANGE - ADD LANES
SR 826/SR 836 FROM N OF SW 8 ST TO S OF NW 25 ST & FM NW 87 TO 57 AVE'
Roadway ID:
Project Length: 4.831
Lanes Exist:Lanes Improved:Lanes Added:
7
7
2
MIAMI-DADE
LRTP Ref:
87200000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 038,842 0 38,842
LF 0 0 0 0 08,804 0 8,804
LFR 0 0 0 0 027,398 0 27,398
NHAC 0 0 0 0 0774 0 774
NHAC 0 0 0 0 07,333 0 7,333
NHPP 0 0 0 0 01,526 0 1,526
NHPP 0 0 0 0 054,729 0 54,729
SA 0 0 0 0 04,063 0 4,063
0 0 0 0 0 0191,704 191,704TotalRIGHT OF WAY
ACNH 0 0 0 0 01,163 0 1,163
ACNP 0 0 0 0 02,831 0 2,831
DC 0 0 0 0 01 0 1
DDR 0 0 0 0 0685 0 685
DDR 0 0 0 0 01,200 0 1,200
DI 0 0 0 0 049 0 49
DIS 0 0 0 0 030 0 30
DPTO 0 0 0 0 093 0 93
DS 0 0 0 0 0255 0 255
Section A1 - Page 114 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2495811
District:
County:
INTERCHANGE - ADD LANES
SR 826/SR 836 FROM N OF SW 8 ST TO S OF NW 25 ST & FM NW 87 TO 57 AVE'
Roadway ID:
Project Length: 4.831
Lanes Exist:Lanes Improved:Lanes Added:
7
7
2
MIAMI-DADE
LRTP Ref:
87200000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 0150 0 150
EBNH 0 0 0 0 098,402 0 98,402
FSF1 0 0 0 0 089,176 0 89,176
GMR 0 0 0 0 01,010 0 1,010
GMR 0 0 0 0 0280 0 280
LF 46,500 0 0 0 0150,684 0 197,184
NH 0 0 0 0 06 0 6
NHAC 0 0 0 0 05,604 0 5,604
NHPP 0 0 0 0 0199,228 0 199,228
TRIP 0 0 0 0 0525 0 525
TRIP 0 0 0 0 0471 0 471
46,500 0 0 0 0 0551,843 598,343TotalDESIGN/BUILD
BNIR 0 0 0 0 027,405 0 27,405
0 0 0 0 0 027,405 27,405TotalLOCAL ADVANCE REIMBURSEMENT
$851,335Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $852,257249581Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 115 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2495812
District:
County:
LANDSCAPING
SR 826/PALMETTO EXPY FROM S OF SW 2 STREET TO NW 14 STREET
Roadway ID:
Project Length: 1.656
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 09 0 9
DS 0 0 0 0 079 0 79
0 0 0 0 0 088 88TotalPLANNING AND DESIGN
DDR 0 600 0 0 00 0 600
DIH 0 32 0 0 00 0 32
DS 0 147 0 0 00 0 147
0 779 0 0 0 00 779TotalCONSTRUCTION
$867Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $852,257249581Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 116 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2495813
District:
County:
DRAINAGE IMPROVEMENTS
SR 826/PALMETTO EXPY RELOCATION OF CANAL SE OF INTERCHANGE WITH SR 836
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 055 0 55
0 0 0 0 0 055 55TotalCONSTRUCTION
$55Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $852,257249581Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496141
District:
County:
TRANSPORTATION PLANNING
SR 997/KROME AVENUE FROM US-1 (FLORIDA CITY) TO SR 90/TAMIAMI TRAIL
Roadway ID:
Project Length: 22.298
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0200 0 200
0 0 0 0 0851 0 851
0 0 0 0 0 01,051 1,051TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,051Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $156,588249614Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 117 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496142
District:
County:
ADD TURN LANE(S)
SR 997/KROME AVENUE AT SW 272,SW 256, SW 192, SW 168, SW 136 INTERSCTN
Roadway ID:
Project Length: 9.055
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0243 0 243
0 0 0 0 0 0243 243TotalPLANNING AND DESIGN
0 0 0 0 02,346 0 2,346
0 0 0 0 0 02,346 2,346TotalRIGHT OF WAY
0 0 0 0 06 0 6
0 0 0 0 0 06 6TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
0 0 0 0 06,173 0 6,173
0 0 0 0 0 06,173 6,173TotalDESIGN/BUILD
$8,768Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $156,588249614Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 118 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496143
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM SR 94/KENDALL DR TO 1 MI N OF SW 8TH ST
Roadway ID:
Project Length: 6.567
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0791 0 791
DIH 0 0 0 0 0301 0 301
DS 0 0 0 0 02,754 0 2,754
0 0 0 0 0 03,846 3,846TotalPLANNING AND DESIGN
BNIR 0 0 0 0 08,409 0 8,409
DDR 0 0 0 0 0624 0 624
DIH 0 0 0 0 0657 0 657
DS 0 0 0 0 0149 0 149
SU 0 0 0 0 01,154 0 1,154
TRIP 0 0 0 0 01,154 0 1,154
TRIP 0 0 0 0 0147 0 147
0 0 0 0 0 012,294 12,294TotalRIGHT OF WAY
ACNP 0 0 0 0 043,738 0 43,738
ACSA 0 0 0 0 0121 0 121
ACSN 0 0 0 0 0167 0 167
ACSU 0 0 0 0 0104 0 104
DDR 0 0 0 0 0190 0 190
DIH 0 0 0 0 010 0 10
Section A1 - Page 119 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496143
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM SR 94/KENDALL DR TO 1 MI N OF SW 8TH ST
Roadway ID:
Project Length: 6.567
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 037 0 37
SU 0 0 0 0 011,689 0 11,689
TRIP 0 0 0 0 08,686 0 8,686
TRIP 0 0 0 0 0116 0 116
0 0 0 0 0 064,858 64,858TotalCONSTRUCTION
DDR 0 1,475 0 0 00 0 1,475
0 1,475 0 0 0 00 1,475TotalALTERNATIVE CONTRACTING INCENTIVES
$82,473Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $156,588249614Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 120 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496144
District:
County:
PD&E/EMO STUDY
SR 997/KROME AVENUE FROM SW 296 STREET TO SW 136 STREET
Roadway ID:
Project Length: 10.068
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 012 0 12
0 0 0 0 0 012 12TotalPLANNING AND DESIGN
0 0 0 0 02,398 0 2,398
0 0 0 0 0 02,398 2,398TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,410Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $156,588249614Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496145
District:
County:
ADD TURN LANE(S)
SR 997/KROME AVENUE AT SW 288,SW 216, SW 200, SW 184 INTERSECTIONS
Roadway ID:
Project Length: 13.449
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0114 0 114
0 0 0 0 0 0114 114TotalPLANNING AND DESIGN
0 0 0 0 09 0 9
0 0 0 0 0169 0 169
Section A1 - Page 121 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496145
District:
County:
ADD TURN LANE(S)
SR 997/KROME AVENUE AT SW 288,SW 216, SW 200, SW 184 INTERSECTIONS
Roadway ID:
Project Length: 13.449
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 056 0 56
0 0 0 0 0876 0 876
0 0 0 0 0 01,110 1,110TotalRIGHT OF WAY
0 0 0 0 05,719 0 5,719
0 0 0 0 00 0 0
0 0 0 0 0 05,719 5,719TotalCONSTRUCTION
0 0 0 0 0250 0 250
0 0 0 0 0 0250 250TotalALTERNATIVE CONTRACTING INCENTIVES
$7,193Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $156,588249614Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 122 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496146
District:
County:
INTERSECTION (MINOR)
SR 997/KROME AVENUE AT SR 94/KENDALL DRIVE
Roadway ID:
Project Length: 0.080
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 038 0 38
0 0 0 0 0 038 38TotalPLANNING AND DESIGN
0 0 0 0 019 0 19
0 0 0 0 0 019 19TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
0 0 0 0 0499 0 499
0 0 0 0 0 0499 499TotalCONSTRUCTION
0 0 0 0 020 0 20
0 0 0 0 0 020 20TotalALTERNATIVE CONTRACTING INCENTIVES
$576Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $156,588249614Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 123 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496147
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM S OF SW 136TH ST TO S OF SR 94/KENDALL DR
Roadway ID:
Project Length: 3.544
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0173 0 173
DIH 0 0 0 0 0771 0 771
DS 0 0 0 0 0473 0 473
0 0 0 0 0 01,417 1,417TotalPLANNING AND DESIGN
ACNP 0 0 0 0 0100 0 100
ACNP 0 0 0 0 01,700 0 1,700
BNDS 0 0 0 0 0112 0 112
BNIR 0 0 0 0 04,534 0 4,534
DIH 0 0 0 0 0420 0 420
DS 0 0 0 0 054 0 54
DS 0 0 0 0 039 0 39
0 0 0 0 0 06,959 6,959TotalRIGHT OF WAY
ACNP 0 0 0 0 039,959 0 39,959
DIS 0 0 0 0 0257 0 257
SN 0 0 0 0 02,059 0 2,059
0 0 0 0 0 042,275 42,275TotalCONSTRUCTION
SA 0 0 1,000 0 00 0 1,000
0 0 1,000 0 0 00 1,000TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 124 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$51,651Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $156,588249614Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496148
District:
County:
RESURFACING
SR 997/KROME AVENUE FROM S OF SW 122 STREET TO S OF SR 94/KENDALL DR
Roadway ID:
Project Length: 2.941
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 062 0 62
0 0 0 0 0273 0 273
0 0 0 0 0 0335 335TotalPLANNING AND DESIGN
0 0 0 0 046 0 46
0 0 0 0 0 046 46TotalRAILROAD & UTILITIES
0 0 0 0 031 0 31
0 0 0 0 02,054 0 2,054
0 0 0 0 0 02,085 2,085TotalCONSTRUCTION
$2,466Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $156,588249614Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 125 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496152
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM NORTH OF SW 8 ST TO MP 2.754
Roadway ID:
Project Length: 2.097
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87070000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0575 0 575
DS 0 0 0 0 043 0 43
0 0 0 0 0 0618 618TotalPLANNING AND DESIGN
ACNP 0 0 0 0 081 0 81
DIS 0 0 0 0 0107 0 107
0 0 0 0 0 0188 188TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 014,500 0 14,500
DIS 0 0 0 0 075 0 75
DS 0 0 0 0 013 0 13
0 0 0 0 0 014,588 14,588TotalCONSTRUCTION
DSBD 600 0 0 0 00 0 600
600 0 0 0 0 00 600TotalALTERNATIVE CONTRACTING INCENTIVES
$15,994Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,415249615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 126 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496153
District:
County:
PD&E/EMO STUDY
SR 997/KROME AVENUE FROM SW 136TH STREET TO US-27/OKEECHOBEE ROAD
Roadway ID:
Project Length: 22.810
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87070000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,626 0 1,626
0 0 0 0 0 01,626 1,626TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,626Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,415249615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496154
District:
County:
WETLAND MITIGATION/RESTORATION
SR 997/KROME AVENUE FROM SR 90/SW 8 STREET TO US-27/OKEECHOBEE ROAD
Roadway ID:
Project Length: 14.275
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87070000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0187 0 187
0 0 0 0 0 0187 187TotalPLANNING AND DESIGN
0 0 0 0 09,586 0 9,586
0 0 0 0 0 09,586 9,586TotalENVIRONMENTAL
$9,773Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,415249615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 127 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496155
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM MP 10.935 TO 14.032/SOUTH OF OKEECHOBEE ROAD
Roadway ID:
Project Length: 3.097
Lanes Exist:Lanes Improved:Lanes Added:
1
2
2
MIAMI-DADE
LRTP Ref:
87070000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 025 0 25
DIH 0 0 0 0 0306 0 306
DS 0 0 0 0 022 0 22
0 0 0 0 0 0353 353TotalPLANNING AND DESIGN
ACNP 0 0 0 0 022,067 0 22,067
DIS 0 0 0 0 0153 0 153
0 0 0 0 0 022,220 22,220TotalCONSTRUCTION
DI 1,120 0 0 0 00 0 1,120
1,120 0 0 0 0 00 1,120TotalALTERNATIVE CONTRACTING INCENTIVES
$23,693Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,415249615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 128 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496156
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM MP 2.754 TO MP 5.122
Roadway ID:
Project Length: 2.368
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87070000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 025 0 25
DIH 0 0 0 0 0188 0 188
DS 0 0 0 0 06 0 6
0 0 0 0 0 0219 219TotalPLANNING AND DESIGN
ACNP 0 0 0 0 093 0 93
DIS 0 0 0 0 0137 0 137
0 0 0 0 0 0230 230TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 014,977 0 14,977
DIS 0 0 0 0 075 0 75
DS 0 0 0 0 05 0 5
0 0 0 0 0 015,057 15,057TotalCONSTRUCTION
DSBD 530 0 0 0 00 0 530
530 0 0 0 0 00 530TotalALTERNATIVE CONTRACTING INCENTIVES
$16,036Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,415249615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 129 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496157
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM MP 5.122 TO MP 8.151
Roadway ID:
Project Length: 3.029
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87070000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 083 0 83
DS 0 0 0 0 05 0 5
0 0 0 0 0 088 88TotalPLANNING AND DESIGN
ACNP 0 0 0 0 042 0 42
DIS 0 0 0 0 092 0 92
0 0 0 0 0 0134 134TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 016,946 0 16,946
DIS 0 0 0 0 0150 0 150
DS 0 0 0 0 05 0 5
NHPP 0 0 0 0 03,766 0 3,766
0 0 0 0 0 020,867 20,867TotalCONSTRUCTION
DSBD 740 0 0 0 00 0 740
740 0 0 0 0 00 740TotalALTERNATIVE CONTRACTING INCENTIVES
$21,829Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,415249615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 130 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496158
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM MP 8.151 TO MP 10.935
Roadway ID:
Project Length: 2.784
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87070000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 099 0 99
DS 0 0 0 0 05 0 5
0 0 0 0 0 0104 104TotalPLANNING AND DESIGN
ACNP 0 0 0 0 013,599 0 13,599
DIS 0 0 0 0 0153 0 153
DS 0 0 0 0 09 0 9
NHPP 0 0 0 0 06,518 0 6,518
0 0 0 0 0 020,279 20,279TotalCONSTRUCTION
DSBD 670 0 0 0 00 0 670
670 0 0 0 0 00 670TotalALTERNATIVE CONTRACTING INCENTIVES
$21,053Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,415249615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 131 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2496159
District:
County:
MAINTENANCE RESURFACING (FLEX)
SR 997/KROME AVENUE FROM 1 MILE N OF SW 8 ST TO S OF OKEECHOBEE RD
Roadway ID:
Project Length: 13.009
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 047 0 47
0 0 0 0 0 047 47TotalPLANNING AND DESIGN
0 0 0 0 03,364 0 3,364
0 0 0 0 0 03,364 3,364TotalCONSTRUCTION
$3,411Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,415249615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 132 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497262
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0723 0 723
0 0 0 0 0 0723 723TotalPLANNING AND DESIGN
$723Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,504249726Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497263
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE MISC STUDIES & RCI DATA COLLECTION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0559 0 559
0 0 0 0 0 0559 559TotalPLANNING AND DESIGN
$559Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,504249726Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 133 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497264
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 3 3 3 0 046 0 55
DS 360 0 0 0 0442 0 802
363 3 3 0 0 0488 857TotalPLANNING AND DESIGN
$857Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,504249726Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497265
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE MISC STUDIES & RCI DATA COLLECTION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 3 0 0 0 019 0 22
DS 150 0 0 0 01,006 0 1,156
153 0 0 0 0 01,025 1,178TotalPLANNING AND DESIGN
$1,178Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,504249726Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 134 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497266
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE MISC STUDIES & RCI DATA COLLECTION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 1 3 3 0 00 0 7
DS 380 0 150 150 1500 0 830
381 3 153 150 150 00 837TotalPLANNING AND DESIGN
$837Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,504249726Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497267
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 50 300 00 0 350
0 0 50 300 0 00 350TotalPLANNING AND DESIGN
$350Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,504249726Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 135 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497962
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04,572 0 4,572
0 0 0 0 0278 0 278
0 0 0 0 01,282 0 1,282
0 0 0 0 0 06,132 6,132TotalPLANNING AND DESIGN
$6,132Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,338249796Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497963
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,643 0 1,643
0 0 0 0 0 01,643 1,643TotalPLANNING AND DESIGN
$1,643Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,338249796Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 136 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497964
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,562 0 1,562
0 0 0 0 0 01,562 1,562TotalPLANNING AND DESIGN
$1,562Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,338249796Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497965
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 6 6 3 0 047 0 62
DS 0 0 0 0 0760 0 760
6 6 3 0 0 0807 822TotalPLANNING AND DESIGN
$822Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,338249796Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 137 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497966
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 8 8 0 0 032 0 48
DS 300 0 0 0 01,050 0 1,350
308 8 0 0 0 01,082 1,398TotalPLANNING AND DESIGN
$1,398Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,338249796Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497967
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 5 0 0 0 013 0 18
DS 300 400 0 0 0800 0 1,500
305 400 0 0 0 0813 1,518TotalPLANNING AND DESIGN
$1,518Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,338249796Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 138 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497968
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 5 5 0 00 0 10
DS 0 0 300 300 3000 0 900
0 5 305 300 300 00 910TotalPLANNING AND DESIGN
$910Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,338249796Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2497969
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 3 0 00 0 3
DS 0 0 350 0 00 0 350
0 0 353 0 0 00 353TotalPLANNING AND DESIGN
$353Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,338249796Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 139 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499411
District:
County:
ADD LANES & RECONSTRUCT
SR 823/NW 57 AVENUE FROM W 46TH STREET TO W 53RD STREET
Roadway ID:
Project Length: 0.549
Lanes Exist:Lanes Improved:Lanes Added:
4
2
4
MIAMI-DADE
LRTP Ref:
87002000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0209 0 209
0 0 0 0 0914 0 914
0 0 0 0 01,995 0 1,995
0 0 0 0 0 03,118 3,118TotalPLANNING AND DESIGN
0 0 0 0 01,115 0 1,115
0 0 0 0 03,039 0 3,039
0 0 0 0 01,329 0 1,329
0 0 0 0 0 05,483 5,483TotalRIGHT OF WAY
0 0 0 0 064 0 64
0 0 0 0 0 064 64TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
0 0 0 0 0312 0 312
0 0 0 0 014,164 0 14,164
0 0 0 0 027 0 27
0 0 0 0 0494 0 494
0 0 0 0 0 014,997 14,997TotalCONSTRUCTION
$23,662Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $130,462249941Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 140 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499412
District:
County:
ADD LANES & RECONSTRUCT
SR 823/NW 57 AVENUE FROM WEST 19 STREET TO WEST 23 STREET
Roadway ID:
Project Length: 0.261
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 066 0 66
0 0 0 0 02,542 0 2,542
0 0 0 0 0 02,608 2,608TotalPLANNING AND DESIGN
0 0 0 0 0541 0 541
0 0 0 0 02,401 0 2,401
0 0 0 0 02 0 2
0 0 0 0 01,322 0 1,322
0 0 0 0 0 04,266 4,266TotalRIGHT OF WAY
0 0 0 0 09,201 0 9,201
0 0 0 0 0 09,201 9,201TotalCONSTRUCTION
$16,075Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $130,462249941Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 141 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499413
District:
County:
ADD LANES & RECONSTRUCT
SR 823/NW 57 AVENUE FROM OKEECHOBEE ROAD TO WEST 19TH ST
Roadway ID:
Project Length: 0.628
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0116 0 116
0 0 0 0 01,713 0 1,713
0 0 0 0 0 01,829 1,829TotalPLANNING AND DESIGN
0 0 0 0 00 0 0
0 0 0 0 0 00 0TotalRIGHT OF WAY
0 0 0 0 08,408 0 8,408
0 0 0 0 0 08,408 8,408TotalCONSTRUCTION
$10,237Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $130,462249941Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499414
District:
County:
ADD LANES & RECONSTRUCT
SR 823/NW 57 AVENUE FROM W 65 STREET TO W 84TH STREET
Roadway ID:
Project Length: 1.193
Lanes Exist:Lanes Improved:Lanes Added:
3
4
2
MIAMI-DADE
LRTP Ref:
87002000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0704 0 704
Section A1 - Page 142 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499414
District:
County:
ADD LANES & RECONSTRUCT
SR 823/NW 57 AVENUE FROM W 65 STREET TO W 84TH STREET
Roadway ID:
Project Length: 1.193
Lanes Exist:Lanes Improved:Lanes Added:
3
4
2
MIAMI-DADE
LRTP Ref:
87002000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0155 0 155
DS 0 0 0 0 022 0 22
LF 0 0 0 0 0315 0 315
0 0 0 0 0 01,196 1,196TotalPLANNING AND DESIGN
LF 0 0 0 0 05,182 0 5,182
0 0 0 0 0 05,182 5,182TotalRAILROAD & UTILITIES
DDR 0 0 0 0 069 0 69
DDR 0 0 0 0 0141 0 141
DS 0 0 0 0 0135 0 135
LF 0 0 0 0 0352 0 352
SU 0 0 0 0 016,575 0 16,575
0 0 0 0 0 017,272 17,272TotalCONSTRUCTION
SA 840 0 0 0 00 0 840
840 0 0 0 0 00 840TotalALTERNATIVE CONTRACTING INCENTIVES
$24,490Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $130,462249941Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 143 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499415
District:
County:
ADD LANES & RECONSTRUCT
SR 823/NW 57 AVENUE FROM WEST 23 STREET TO WEST 46 STREET
Roadway ID:
Project Length: 1.465
Lanes Exist:Lanes Improved:Lanes Added:
4
2
4
MIAMI-DADE
LRTP Ref:
87002000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 075 0 75
0 0 0 0 0754 0 754
0 0 0 0 0 0829 829TotalPLANNING AND DESIGN
0 0 0 0 0816 0 816
0 0 0 0 030 0 30
0 0 0 0 0 0846 846TotalRAILROAD & UTILITIES
0 0 0 0 014 0 14
0 0 0 0 0522 0 522
0 0 0 0 025,340 0 25,340
0 0 0 0 01,698 0 1,698
0 0 0 0 0 027,574 27,574TotalCONSTRUCTION
$29,249Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $130,462249941Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 144 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499416
District:
County:
ADD LANES & RECONSTRUCT
SR 823/NW 57 AVENUE FROM W 53 STREET TO W 65 STREET
Roadway ID:
Project Length: 0.711
Lanes Exist:Lanes Improved:Lanes Added:
4
4
2
MIAMI-DADE
LRTP Ref:
87002000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0580 0 580
DIH 0 0 0 0 0169 0 169
DS 0 0 0 0 0239 0 239
LF 0 0 0 0 0259 0 259
0 0 0 0 0 01,247 1,247TotalPLANNING AND DESIGN
LF 0 0 0 0 05,545 0 5,545
0 0 0 0 0 05,545 5,545TotalRAILROAD & UTILITIES
DDR 0 0 0 0 069 0 69
DS 0 0 0 0 0208 0 208
DS 0 0 0 0 0155 0 155
LF 0 0 0 0 0589 0 589
SU 0 0 0 0 016,538 0 16,538
0 0 0 0 0 017,559 17,559TotalCONSTRUCTION
SA 800 0 0 0 00 0 800
800 0 0 0 0 00 800TotalALTERNATIVE CONTRACTING INCENTIVES
$25,151Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $130,462249941Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 145 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499417
District:
County:
SIDEWALK
SR 823/NW 57 AVE-N/B FROM NW 202 ST/HONEY HILL TO TPK EXIT NSIDE OF HE
Roadway ID:
Project Length: 1.148
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
86190500
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0324 0 324
0 0 0 0 0 0324 324TotalPLANNING AND DESIGN
0 0 0 0 01,274 0 1,274
0 0 0 0 0 01,274 1,274TotalCONSTRUCTION
$1,598Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $130,462249941Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499431
District:
County:
ENVIRONMENTAL TEST/MITIGATE
MIAMI-DADE COUNTYWDE CONTAMINATION ASSESSMENT & REMEDIATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,077 0 3,077
0 0 0 0 0 03,077 3,077TotalPLANNING AND DESIGN
0 0 0 0 0865 0 865
Section A1 - Page 146 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499431
District:
County:
ENVIRONMENTAL TEST/MITIGATE
MIAMI-DADE COUNTYWDE CONTAMINATION ASSESSMENT & REMEDIATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0124 0 124
0 0 0 0 0 0989 989TotalENVIRONMENTAL
0 0 0 0 0363 0 363
0 0 0 0 0 0363 363TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$4,429Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,461249943Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499433
District:
County:
ENVIRONMENTAL TEST/MITIGATE
MIAMI-DADE COUNTYWDE CONTAMINATION ASSESSMENT & REMEDIATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 760 760 760 760 7601,749 0 5,549
DS 0 0 0 0 0850 0 850
760 760 760 760 760 02,599 6,399TotalPLANNING AND DESIGN
Section A1 - Page 147 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499433
District:
County:
ENVIRONMENTAL TEST/MITIGATE
MIAMI-DADE COUNTYWDE CONTAMINATION ASSESSMENT & REMEDIATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 0167 0 167
0 0 0 0 0 0167 167TotalENVIRONMENTAL
DIH 50 50 50 50 50112 0 362
50 50 50 50 50 0112 362TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$6,928Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,461249943Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 148 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2500842
District:
County:
CORRIDOR/SUBAREA PLANNING
TRANSPORTATION SYSTEMS MANAGEMENT AND OPERATIONS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,255 0 2,255
0 0 0 0 0 02,255 2,255TotalPLANNING AND DESIGN
$2,255Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,620250084Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2500843
District:
County:
CORRIDOR/SUBAREA PLANNING
TRANSPORTATION SYSTEMS MANAGEMENT AND OPERATIONS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 5 5 5 0 05 0 20
DS 900 900 900 1,000 0595 0 4,295
905 905 905 1,000 0 0600 4,315TotalPLANNING AND DESIGN
$4,315Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,620250084Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 149 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2500844
District:
County:
CORRIDOR/SUBAREA PLANNING
TRANSPORTATION SYSTEMS MANAGEMENT AND OPERATIONS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 50 1,0000 0 1,050
0 0 0 50 1,000 00 1,050TotalPLANNING AND DESIGN
$1,050Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,620250084Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2500932
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0635 0 635
0 0 0 0 0 0635 635TotalPLANNING AND DESIGN
$635Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,957250093Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 150 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2500933
District:
County:
CORRIDOR/SUBAREA PLANNING
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 3 3 3 0 028 0 37
DS 360 0 0 0 0575 0 935
363 3 3 0 0 0603 972TotalPLANNING AND DESIGN
$972Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,957250093Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2500934
District:
County:
CORRIDOR/SUBAREA PLANNING
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 50 300 00 0 350
0 0 50 300 0 00 350TotalPLANNING AND DESIGN
$350Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,957250093Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 151 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501022
District:
County:
PERIODIC MAINTENANCE
DISTRICTWIDE ITS OPERATIONS & MAINTENANCE OF FIELD DEVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 039 0 39
0 0 0 0 0 039 39TotalPLANNING AND DESIGN
0 0 0 0 02,288 0 2,288
0 0 0 0 0 02,288 2,288TotalCONSTRUCTION
$2,327Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $40,838250102Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501023
District:
County:
PERIODIC MAINTENANCE
DISTRICTWIDE ITS OPERATIONS & MAINTENANCE OF FIELD DEVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0519 0 519
0 0 0 0 0 0519 519TotalPLANNING AND DESIGN
Section A1 - Page 152 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501023
District:
County:
PERIODIC MAINTENANCE
DISTRICTWIDE ITS OPERATIONS & MAINTENANCE OF FIELD DEVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 08,945 0 8,945
0 0 0 0 0 08,945 8,945TotalCONSTRUCTION
$9,464Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $40,838250102Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501025
District:
County:
PERIODIC MAINTENANCE
DISTRICTWIDE ITS OPERATIONS & MAINTENANCE OF FIELD DEVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0148 0 148
0 0 0 0 0 0148 148TotalPLANNING AND DESIGN
DIH 0 0 0 0 068 0 68
Section A1 - Page 153 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501025
District:
County:
PERIODIC MAINTENANCE
DISTRICTWIDE ITS OPERATIONS & MAINTENANCE OF FIELD DEVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 3,000 0 0 0 012,356 0 15,356
3,000 0 0 0 0 012,424 15,424TotalCONSTRUCTION
D 500 0 0 0 00 0 500
500 0 0 0 0 00 500TotalMAINTENANCE
$16,072Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $40,838250102Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501026
District:
County:
PERIODIC MAINTENANCE
DISTRICTWIDE ITS OPERATIONS & MAINTENANCE OF FIELD DEVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 30 30 0 015 0 75
DS 0 3,100 3,100 3,100 3,1000 0 12,400
0 3,130 3,130 3,100 3,100 015 12,475TotalCONSTRUCTION
Section A1 - Page 154 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501026
District:
County:
PERIODIC MAINTENANCE
DISTRICTWIDE ITS OPERATIONS & MAINTENANCE OF FIELD DEVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 500 0 0 00 0 500
0 500 0 0 0 00 500TotalMAINTENANCE
$12,975Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $40,838250102Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501051
District:
County:
ADD LANES & RECONSTRUCT
SR 25/OKEECHOBEE RD FROM EAST OF W 12TH AVE TO WEST 19TH STREET
Roadway ID:
Project Length: 0.329
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,110 0 2,110
0 0 0 0 0120 0 120
0 0 0 0 037 0 37
0 0 0 0 0 02,267 2,267TotalPLANNING AND DESIGN
0 0 0 0 0916 0 916
Section A1 - Page 155 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501051
District:
County:
ADD LANES & RECONSTRUCT
SR 25/OKEECHOBEE RD FROM EAST OF W 12TH AVE TO WEST 19TH STREET
Roadway ID:
Project Length: 0.329
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0324 0 324
0 0 0 0 05,579 0 5,579
0 0 0 0 0722 0 722
0 0 0 0 0 07,541 7,541TotalRIGHT OF WAY
0 0 0 0 083 0 83
0 0 0 0 036,639 0 36,639
0 0 0 0 08 0 8
0 0 0 0 0 036,730 36,730TotalDESIGN/BUILD
0 0 0 0 01,300 0 1,300
0 0 0 0 0 01,300 1,300TotalALTERNATIVE CONTRACTING INCENTIVES
$47,838Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $66,231250105Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 156 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501052
District:
County:
ADD LANES & RECONSTRUCT
SR 25/OKEECHOBEE RD FROM SR 826/PALMETTO XWAY
TO EAST OF WEST 12 AVE
Roadway ID:
Project Length: 1.199
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 016 0 16
0 0 0 0 0 016 16TotalRAILROAD & UTILITIES
0 0 0 0 048 0 48
0 0 0 0 012,821 0 12,821
0 0 0 0 0 012,869 12,869TotalCONSTRUCTION
0 0 0 0 0735 0 735
0 0 0 0 0 0735 735TotalALTERNATIVE CONTRACTING INCENTIVES
$13,620Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $66,231250105Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 157 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501053
District:
County:
FIXED GUIDEWAY IMPROVEMENTS
SR 25/OKEECHOBEE RD AT METRORAIL CROSSING
Roadway ID:
Project Length: 0.002
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,979 0 3,979
0 0 0 0 0 03,979 3,979TotalCONSTRUCTION
0 0 0 0 0200 0 200
0 0 0 0 0332 0 332
0 0 0 0 0 0532 532TotalALTERNATIVE CONTRACTING INCENTIVES
$4,511Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $66,231250105Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 158 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501054
District:
County:
LANDSCAPING
SR 25/OKEECHOBEE RD FROM EAST OF W 12 AVENUE TO WEST 19TH STREET
Roadway ID:
Project Length: 0.329
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0262 0 262
0 0 0 0 0 0262 262TotalCONSTRUCTION
$262Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $66,231250105Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501131
District:
County:
SERVICE PATROL/FHP
SERVICE PATROLS SR 826/PALMETTO XWAY
Roadway ID:
Project Length: 24.708
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0834 0 834
0 0 0 0 0 0834 834TotalPLANNING AND DESIGN
0 0 0 0 0142 0 142
0 0 0 0 0 0142 142TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
0 0 0 0 0600 0 600
0 0 0 0 0 0600 600TotalOPERATIONS
Section A1 - Page 159 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501131
District:
County:
SERVICE PATROL/FHP
SERVICE PATROLS SR 826/PALMETTO XWAY
Roadway ID:
Project Length: 24.708
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 018,306 0 18,306
0 0 0 0 0 018,306 18,306TotalMAINTENANCE
$19,882Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,839250113Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501132
District:
County:
ITS FREEWAY MANAGEMENT
SERVICE PATROLS SR 93/I-75
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 019 0 19
0 0 0 0 0 019 19TotalPLANNING AND DESIGN
Section A1 - Page 160 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501132
District:
County:
ITS FREEWAY MANAGEMENT
SERVICE PATROLS SR 93/I-75
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,152 0 2,152
0 0 0 0 0 02,152 2,152TotalMAINTENANCE
$2,171Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,839250113Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501134
District:
County:
SERVICE PATROL/FHP
SERVICE PATROLS
Roadway ID:
Project Length: 24.708
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87260000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 079 0 79
0 0 0 0 0 079 79TotalPLANNING AND DESIGN
D 509 523 0 0 01,449 0 2,481
Section A1 - Page 161 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501134
District:
County:
SERVICE PATROL/FHP
SERVICE PATROLS
Roadway ID:
Project Length: 24.708
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87260000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 2,054 1,532 0 0 05,018 0 8,604
2,563 2,055 0 0 0 06,467 11,085TotalMAINTENANCE
$11,164Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,839250113Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506041
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE VALUE ENGINEERING CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 50 50 50 50 50523 0 773
DS 150 150 150 150 1501,783 0 2,533
200 200 200 200 200 02,306 3,306TotalPLANNING AND DESIGN
$3,306Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,306250604Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 162 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506051
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE MISCELLANEOUS PE DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,364 0 2,364
0 0 0 0 0 02,364 2,364TotalPLANNING AND DESIGN
0 0 0 0 052 0 52
0 0 0 0 0 052 52TotalCONSTRUCTION
$2,416Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,641250605Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506081
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE AERIAL PHOTOGRAPHY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 200 0 0 0 05,960 0 6,160
Section A1 - Page 163 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506081
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE AERIAL PHOTOGRAPHY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 02,169 0 2,169
200 0 0 0 0 08,129 8,329TotalPLANNING AND DESIGN
$8,329Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,979250608Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 164 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506082
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE AERIAL PHOTOGRAPHY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 200 200 300 400 200350 0 1,650
200 200 300 400 200 0350 1,650TotalPLANNING AND DESIGN
$1,650Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,979250608Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506101
District:
County:
LANDSCAPING
DISTRICTWIDE LANDSCAPE DESIGN CONSULTANT & JPA
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 078 0 78
DS 0 0 0 0 01,099 0 1,099
0 0 0 0 0 01,177 1,177TotalPLANNING AND DESIGN
DIH 0 0 0 0 097 0 97
DS 0 0 0 0 01,600 0 1,600
0 0 0 0 0 01,697 1,697TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
Section A1 - Page 165 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506101
District:
County:
LANDSCAPING
DISTRICTWIDE LANDSCAPE DESIGN CONSULTANT & JPA
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 018 0 18
DIH 0 0 0 0 02 0 2
DS 0 0 0 0 045 0 45
DS 500 0 0 0 04,829 0 5,329
500 0 0 0 0 04,894 5,394TotalCONSTRUCTION
$8,268Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,764250610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 166 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506104
District:
County:
LANDSCAPING
DISTRICTWIDE LANDSCAPE DESIGN CONSULTANT & JPA
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 500 500 500 2500 0 1,750
0 500 500 500 250 00 1,750TotalCONSTRUCTION
$1,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,764250610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506211
District:
County:
RIGHT OF WAY ACTIVITIES
D/W PROPERTY MGT BY DIST R/W ADMIN
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BNCA 0 0 0 0 03 0 3
BNDS 0 0 0 0 08 0 8
BNIR 0 0 0 0 033 0 33
DDR 0 0 0 0 0134 0 134
DIH 350 350 350 350 3502,894 0 4,644
DS 100 100 100 100 1003,079 0 3,579
Section A1 - Page 167 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506211
District:
County:
RIGHT OF WAY ACTIVITIES
D/W PROPERTY MGT BY DIST R/W ADMIN
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
450 450 450 450 450 06,151 8,401TotalRIGHT OF WAY
$8,401Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,996250621Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506221
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE PD&E AND TRAFFIC CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04,421 0 4,421
0 0 0 0 0 04,421 4,421TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$4,421Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,404250622Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 168 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506222
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE PD&E AND TRAFFIC CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,560 0 2,560
0 0 0 0 0 02,560 2,560TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,560Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,404250622Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506224
District:
County:
PD&E/EMO STUDY
D/W PD&E CONSULTANT SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 60 50 50 50 5093 0 353
DS 350 300 300 300 3501,204 0 2,804
410 350 350 350 400 01,297 3,157TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,157Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,404250622Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 169 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506225
District:
County:
PD&E/EMO STUDY
D/W PD&E CONSULTANT SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 60 50 50 50 6051 0 321
DS 350 300 300 300 4001,229 0 2,879
410 350 350 350 460 01,280 3,200TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,200Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,404250622Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506261
District:
County:
TRAFFIC OPS IMPROVEMENT
DISTRICTWIDE TRAFFIC OPERATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 1,200 1,200 1,200 1,200 021,059 0 25,859
1,200 1,200 1,200 1,200 0 021,059 25,859TotalPLANNING AND DESIGN
$25,859Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $25,859250626Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 170 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506291
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PUSH BUTTON DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,706 0 1,706
0 0 0 0 0 01,706 1,706TotalPLANNING AND DESIGN
$1,706Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,672250629Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506292
District:
County:
TRAFFIC OPS IMPROVEMENT
D/W TRAFFIC OPS DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,781 0 1,781
0 0 0 0 0 01,781 1,781TotalPLANNING AND DESIGN
0 0 0 0 02 0 2
0 0 0 0 0 02 2TotalRIGHT OF WAY
$1,783Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,672250629Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 171 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506293
District:
County:
TRAFFIC OPS IMPROVEMENT
D/W TRAFFIC OPS DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 18 7 0 0 092 0 117
DS 222 0 0 0 01,299 0 1,521
240 7 0 0 0 01,391 1,638TotalPLANNING AND DESIGN
$1,638Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,672250629Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506294
District:
County:
TRAFFIC OPS IMPROVEMENT
D/W TRAFFIC OPS DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 9 18 18 00 0 45
DS 0 500 500 500 00 0 1,500
0 509 518 518 0 00 1,545TotalPLANNING AND DESIGN
$1,545Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,672250629Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 172 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506295
District:
County:
TRAFFIC OPS IMPROVEMENT
D/W TRAFFIC OPS PUSHBUTTON DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 500 5000 0 1,000
0 0 0 500 500 00 1,000TotalPLANNING AND DESIGN
$1,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,672250629Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506331
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE CONSTRUCTABILITY REVIEW CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05,014 0 5,014
0 0 0 0 0 05,014 5,014TotalPLANNING AND DESIGN
$5,014Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,896250633Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 173 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506332
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE CONSTRUCTABILITY REVIEW CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 300 300 300 0 0600 0 1,500
300 300 300 0 0 0600 1,500TotalPLANNING AND DESIGN
$1,500Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,896250633Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506333
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE CONSTRUCTABILITY REVIEW CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 150 100 150 150 50182 0 782
150 100 150 150 50 0182 782TotalPLANNING AND DESIGN
$782Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,896250633Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 174 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506334
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE CONSTRUCTABILITY REVIEW CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 300 3000 0 600
0 0 0 300 300 00 600TotalPLANNING AND DESIGN
$600Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,896250633Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506351
District:
County:
ENVIRONMENTAL TEST/MITIGATE
DISTRICTWIDE CULTURAL RESOURCE ASSESSMENT CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,587 0 3,587
0 0 0 0 0 03,587 3,587TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,587Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,602250635Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 175 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506352
District:
County:
ENVIRONMENTAL TEST/MITIGATE
D/W CULTURAL RESOURCE MANAGEMENT PLAN
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0107 0 107
0 0 0 0 0 0107 107TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$107Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,602250635Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506353
District:
County:
ENVIRONMENTAL TEST/MITIGATE
D/W CULTURAL RESOURCE ASSESSMENT CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 20 20 20 20 2020 0 120
DS 300 300 300 350 300238 0 1,788
320 320 320 370 320 0258 1,908TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,908Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,602250635Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 176 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506471
District:
County:
BRIDGE-REPAIR/REHABILITATION
DISTRICTWIDE REPAIR/REHAB PLANS PREPARATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0543 0 543
0 0 0 0 0 0543 543TotalPLANNING AND DESIGN
$543Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,102250647Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506472
District:
County:
BRIDGE-REPAIR/REHABILITATION
DISTRICTWIDE REPAIR/REHAB PLANS PREPARATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 300 0 0 0 300780 0 1,380
DS 0 0 0 0 0100 0 100
300 0 0 0 300 0880 1,480TotalPLANNING AND DESIGN
Section A1 - Page 177 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506472
District:
County:
BRIDGE-REPAIR/REHABILITATION
DISTRICTWIDE REPAIR/REHAB PLANS PREPARATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 079 0 79
0 0 0 0 0 079 79TotalCONSTRUCTION
$1,559Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,102250647Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506491
District:
County:
ENVIRONMENTAL PERMITS ACQ
DISTRICTWIDE PERMITS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 016 0 16
0 0 0 0 0 016 16TotalENVIRONMENTAL
DIH 0 0 0 0 0297 0 297
Section A1 - Page 178 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506491
District:
County:
ENVIRONMENTAL PERMITS ACQ
DISTRICTWIDE PERMITS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 200 0 0 0 03,792 0 3,992
200 0 0 0 0 04,089 4,289TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$4,305Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,880250649Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506492
District:
County:
ENVIRONMENTAL PERMITS ACQ
DISTRICTWIDE PERMITS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 100 0 50
DS 250 400 400 450 400200 0 2,100
260 410 410 460 410 0200 2,150TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,150Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,880250649Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 179 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506501
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS - OPERATIONAL STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,295 0 2,295
0 0 0 0 0 02,295 2,295TotalPLANNING AND DESIGN
$2,295Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,208250650Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506502
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS - OPERATIONAL STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0315 0 315
0 0 0 0 0 0315 315TotalPLANNING AND DESIGN
$315Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,208250650Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 180 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506503
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 3 3 0 0 080 0 86
DS 0 0 0 0 0500 0 500
3 3 0 0 0 0580 586TotalPLANNING AND DESIGN
$586Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,208250650Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506504
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS - SAFETY STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 3 3 3 0 03 0 12
DS 200 200 200 200 2000 0 1,000
203 203 203 200 200 03 1,012TotalPLANNING AND DESIGN
$1,012Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,208250650Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 181 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506541
District:
County:
SAFETY PROJECT
DISTRICTWIDE COMMUNITY SAFETY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 071 0 71
NHTS 50 50 50 50 50530 0 780
SS 0 0 0 0 064 0 64
50 50 50 50 50 0665 915TotalPLANNING AND DESIGN
$915Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $915250654Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506621
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY CONSULTANT STUDIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 051 0 51
0 0 0 0 0325 0 325
Section A1 - Page 182 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506621
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY CONSULTANT STUDIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0276 0 276
0 0 0 0 0 0652 652TotalPLANNING AND DESIGN
$652Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,511250662Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 183 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506622
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY CONSULTANT STUDIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,771 0 1,771
0 0 0 0 0 01,771 1,771TotalPLANNING AND DESIGN
$1,771Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,511250662Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506623
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 1 0 0 0 019 0 20
DS 0 0 0 0 01,500 0 1,500
1 0 0 0 0 01,519 1,520TotalPLANNING AND DESIGN
$1,520Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,511250662Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 184 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506624
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 6 6 6 0 00 0 18
DS 350 300 300 300 3000 0 1,550
356 306 306 300 300 00 1,568TotalPLANNING AND DESIGN
$1,568Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,511250662Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506681
District:
County:
ENVIRONMENTAL TEST/MITIGATE
DISTRICTWIDE MITIGATION SITE MAINTENANCE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05,261 0 5,261
0 0 0 0 0 05,261 5,261TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$5,261Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,335250668Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 185 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506682
District:
County:
ENVIRONMENTAL TEST/MITIGATE
DISTRICTWIDE MITIGATION SITE MAINTENANCE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 25 50 25 50 2599 0 274
DS 200 250 200 250 200700 0 1,800
225 300 225 300 225 0799 2,074TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,074Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,335250668Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506731
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PUBLIC INVOLVEMENT CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05,079 0 5,079
0 0 0 0 0 05,079 5,079TotalPLANNING AND DESIGN
$5,079Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,049250673Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 186 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506732
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PUBLIC INVOLVEMENT WEB SITE MANAGEMENT CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 00 0 0
0 0 0 0 0 00 0TotalPLANNING AND DESIGN
$0Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,049250673Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506761
District:
County:
SPECIAL SURVEYS
DISTRICTWIDE CONSTR ENGINEERING INSPECTION CONSULTANT SURVEYS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,937 0 1,937
0 0 0 0 0 01,937 1,937TotalCONSTRUCTION
$1,937Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,364250676Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 187 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506762
District:
County:
SPECIAL SURVEYS
DISTRICTWIDE CONSTR ENGINEERING INSPECTION CONSULTANT SURVEYS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 50 50 0 0 0127 0 227
50 50 0 0 0 0127 227TotalCONSTRUCTION
$227Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,364250676Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506763
District:
County:
SPECIAL SURVEYS
DISTRICTWIDE CONSTRUCTION ENGINEERING INSPECTION CONSULTANT SURVEYS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 100 50 500 0 200
0 0 100 50 50 00 200TotalCONSTRUCTION
$200Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,364250676Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 188 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506801
District:
County:
ENVIRONMENTAL PERMITS ACQ
DISTRICTWIDE ENVIRONMENTAL COMPLIANCE CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,821 0 3,821
0 0 0 0 0 03,821 3,821TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,821Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,156250680Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506802
District:
County:
ENVIRONMENTAL PERMITS ACQ
DISTRICTWIDE ENVIRONMENTAL COMPLIANCE CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 5 5 5 5 510 0 35
DS 300 400 300 300 400600 0 2,300
305 405 305 305 405 0610 2,335TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,335Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,156250680Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 189 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506841
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE MINOR PE DESIGN BY CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 15 0 0 0 048 0 63
DS 0 0 0 0 06,277 0 6,277
15 0 0 0 0 06,325 6,340TotalPLANNING AND DESIGN
DS 0 0 0 0 0239 0 239
0 0 0 0 0 0239 239TotalCONSTRUCTION
$6,579Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,579250684Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 190 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506861
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE ROW LOCATION SURVEY CONSULTNT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 010,548 0 10,548
0 0 0 0 0 010,548 10,548TotalPLANNING AND DESIGN
$10,548Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,389250686Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506862
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE MISC LOCATION SURVEY CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 600 600 600 600 6001,852 0 4,852
600 600 600 600 600 01,852 4,852TotalPLANNING AND DESIGN
$4,852Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,389250686Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 191 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506863
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE MISC LOCATION SURVEY CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 200 200 200 200 0189 0 989
200 200 200 200 0 0189 989TotalPLANNING AND DESIGN
$989Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,389250686Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506931
District:
County:
RESEARCH
DISTRICTWIDE ENVIRONMENTAL DATA & REPORT CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05,202 0 5,202
0 0 0 0 0 05,202 5,202TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$5,202Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,362250693Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 192 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506932
District:
County:
RESEARCH
D/W ENVIRONMENTAL DATA & REPORT CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 20 20 20 20 2033 0 133
DS 600 700 600 700 600827 0 4,027
620 720 620 720 620 0860 4,160TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$4,160Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,362250693Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506961
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE LOCATION SURVEY CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 011,201 0 11,201
0 0 0 0 0 011,201 11,201TotalPLANNING AND DESIGN
$11,201Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,227250696Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 193 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506962
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE ROW MAPPING AND SURVEY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,632 0 3,632
0 0 0 0 0 03,632 3,632TotalPLANNING AND DESIGN
$3,632Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,227250696Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506971
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE TITLE SEARCH
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0110 0 110
DS 120 120 0 0 01,816 0 2,056
120 120 0 0 0 01,926 2,166TotalPLANNING AND DESIGN
$2,166Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,266250697Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 194 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506972
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE TITLE SEARCH
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0100 0 100
0 0 0 0 0 0100 100TotalPLANNING AND DESIGN
$100Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,266250697Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507111
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE MISC CONSTRUCTION ENGINEERING INSPECTION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 012,097 0 12,097
0 0 0 0 0 012,097 12,097TotalCONSTRUCTION
$12,097Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,282250711Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 195 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507112
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE RESIDENCY CEI CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 09,761 0 9,761
0 0 0 0 01,355 0 1,355
0 0 0 0 0 011,116 11,116TotalCONSTRUCTION
$11,116Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,282250711Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507115
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE MISC CONSTRUCTION ENGINEERING INSPECTION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 900 900 900 0 02,771 0 5,471
900 900 900 0 0 02,771 5,471TotalCONSTRUCTION
$5,471Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,282250711Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 196 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507116
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE MISC CONSTRUCTION ENGINEERING INSPECTION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 450 450 0 0 0548 0 1,448
450 450 0 0 0 0548 1,448TotalCONSTRUCTION
$1,448Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,282250711Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507117
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE MISC CONSTRUCTION ENGINEERING INSPECTION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 450 1,350 1,3500 0 3,150
0 0 450 1,350 1,350 00 3,150TotalCONSTRUCTION
$3,150Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,282250711Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 197 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507231
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE UTILITY COORDINATION/LOCATING SERVICES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 014,603 0 14,603
0 0 0 0 0 014,603 14,603TotalPLANNING AND DESIGN
$14,603Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $24,188250723Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507232
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE UTILITY LOCATING SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 1,400 1,000 1,000 1,000 1,0001,185 0 6,585
1,400 1,000 1,000 1,000 1,000 01,185 6,585TotalPLANNING AND DESIGN
$6,585Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $24,188250723Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 198 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507233
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE UTILITY COORDINATION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 600 600 600 600 6000 0 3,000
600 600 600 600 600 00 3,000TotalPLANNING AND DESIGN
$3,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $24,188250723Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507241
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE MISC STRUCTURAL PROJECTS MINOR DESIGN
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,864 0 2,864
0 0 0 0 0 02,864 2,864TotalPLANNING AND DESIGN
0 0 0 0 039 0 39
0 0 0 0 0 039 39TotalCONSTRUCTION
$2,903Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,831250724Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 199 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507242
District:
County:
PRELIMINARY ENGINEERING
D/W STRUCTURAL PROJECTS MINOR DESIGN CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 1020 0 70
DS 450 600 450 450 600308 0 2,858
460 610 460 460 610 0328 2,928TotalPLANNING AND DESIGN
$2,928Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,831250724Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507301
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE MATERIALS TESTING/ GEOTECHNICAL SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04,744 0 4,744
0 0 0 0 0 04,744 4,744TotalPLANNING AND DESIGN
$4,744Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,830250730Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 200 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507302
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE MATERIALS TESTING/ GEOTECHNICAL SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 600 600 850 600 600836 0 4,086
600 600 850 600 600 0836 4,086TotalPLANNING AND DESIGN
$4,086Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,830250730Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507411
District:
County:
PRELIMINARY ENGINEERING
D/W IN HOUSE CONSULTANT MANAGEMENT SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 600 500 500 0 02,551 0 4,151
600 500 500 0 0 02,551 4,151TotalPLANNING AND DESIGN
$4,151Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,151250741Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 201 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507421
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PD&E PROJECT MGT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 500 500 500 500 5008,802 0 11,302
500 500 500 500 500 08,802 11,302TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$11,302Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,302250742Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507431
District:
County:
PRELIMINARY ENGINEERING
D/W IN HOUSE ROADWAY DESIGN SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 100 100 100 0 02,628 0 2,928
100 100 100 0 0 02,628 2,928TotalPLANNING AND DESIGN
$2,928Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,928250743Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 202 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507471
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE ENGINEERING SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 1,500 1,400 1,500 1,500 1,50017,504 0 24,904
DS 0 0 0 0 01,052 0 1,052
1,500 1,400 1,500 1,500 1,500 018,556 25,956TotalPLANNING AND DESIGN
$25,956Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $28,850250747Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507591
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE PROJECT MANAGEMENT PD&E SCOPING UNIT & SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 300 300 300 300 3001,496 0 2,996
300 300 300 300 300 01,496 2,996TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,996Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,869250759Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 203 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2511561
District:
County:
MISCELLANEOUS STRUCTURE
PORT OF MIAMI TUNNEL FROM PORT OF MIAMI TO SR 836/I-395
Roadway ID:
Project Length: 1.800
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-30
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0341 0 341
0 0 0 0 018 0 18
0 0 0 0 0 0359 359TotalPLANNING AND DESIGN
$359Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,691,898251156Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2511562
District:
County:
NEW ROAD CONSTRUCTION
PORT OF MIAMI TUNNEL FROM PORT OF MIAMI TO SR836/I-395
Roadway ID:
Project Length: 0.496
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87059000
6
6-30
SIS or Non-SIS: No
PHASE :
Extra Description:
DIS 0 0 0 0 01,218 0 1,218
DIS 0 0 0 0 04,135 0 4,135
DS 0 0 0 0 00 0 0
FD21 0 0 0 0 06,405 0 6,405
GMR 250 250 250 250 2504,517 1,250 7,017
Section A1 - Page 204 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2511562
District:
County:
NEW ROAD CONSTRUCTION
PORT OF MIAMI TUNNEL FROM PORT OF MIAMI TO SR836/I-395
Roadway ID:
Project Length: 0.496
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87059000
6
6-30
SIS or Non-SIS: No
PHASE :
Extra Description:
GMR 0 0 0 0 01,658 0 1,658
LF 0 0 0 0 0609 0 609
PKYI 0 0 0 0 096 0 96
250 250 250 250 250 1,25018,638 21,138TotalPLANNING AND DESIGN
$21,138Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,691,898251156Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2511563
District:
County:
NEW ROAD CONSTRUCTION
PORT OF MIAMI TUNNEL FROM PORT OF MIAMI TO SR 836/I-395
Roadway ID:
Project Length: 0.496
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87059000
6
6-30
SIS or Non-SIS: No
PHASE :
Extra Description:
Transportation Infrastructure Finance and Innovation Act of 1998 (TIFIA). Following is a
DI 0 0 0 0 0727 0 727
DIH 0 0 0 0 01,148 0 1,148
DIS 125 0 0 0 04,811 0 4,936
DS 0 0 0 0 020 0 20
Section A1 - Page 205 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2511563
District:
County:
NEW ROAD CONSTRUCTION
PORT OF MIAMI TUNNEL FROM PORT OF MIAMI TO SR 836/I-395
Roadway ID:
Project Length: 0.496
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87059000
6
6-30
SIS or Non-SIS: No
PHASE :
Extra Description:
Transportation Infrastructure Finance and Innovation Act of 1998 (TIFIA). Following is a
FD21 0 0 0 0 0250 0 250
GMR 0 0 0 0 0372 0 372
GMR 0 125 125 125 12513,253 2,625 16,378
LF 0 0 0 0 016,702 0 16,702
NHAC 0 0 0 0 0158 0 158
NHPP 0 0 0 0 01,843 0 1,843
125 125 125 125 125 2,62539,284 42,534TotalPLANNING AND DESIGN
DIH 0 0 0 0 011 0 11
DS 0 0 0 0 012 0 12
LF 0 0 0 0 050,000 0 50,000
0 0 0 0 0 050,023 50,023TotalRIGHT OF WAY
DC 0 0 0 0 03 0 3
DIH 0 0 0 0 0689 0 689
DIS 0 0 0 0 0192 0 192
DS 0 0 0 0 020 0 20
GMR 22,168 23,008 22,152 22,990 24,33852,582 786,887 954,125
GMR 0 0 0 0 023,258 0 23,258
HPP 0 0 0 0 01,260 0 1,260
Section A1 - Page 206 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2511563
District:
County:
NEW ROAD CONSTRUCTION
PORT OF MIAMI TUNNEL FROM PORT OF MIAMI TO SR 836/I-395
Roadway ID:
Project Length: 0.496
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87059000
6
6-30
SIS or Non-SIS: No
PHASE :
Extra Description:
Transportation Infrastructure Finance and Innovation Act of 1998 (TIFIA). Following is a
LF 2,607 2,686 2,766 2,849 2,9353,471 101,383 118,697
LF 0 0 0 0 0292,462 0 292,462
NHAC 0 0 0 0 0151 0 151
NHPP 0 0 0 0 0211,339 0 211,339
24,775 25,694 24,918 25,839 27,273 888,270585,427 1,602,196TotalDESIGN/BUILD
DI 16,723 17,050 19,107 19,507 19,43534,312 700,130 826,264
16,723 17,050 19,107 19,507 19,435 700,13034,312 826,264TotalOPERATIONS
$2,521,017Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,691,898251156Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 207 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2511564
District:
County:
FUNDING ACTION
PORT OF MIAMI TUNNEL MIAMI-DADE COUNTY MPO PRIORITY
Roadway ID:
Project Length: 0.496
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87059000
6
6-30
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 8,000 17,000 17,000 17,0000 85,000 144,000
0 8,000 17,000 17,000 17,000 85,0000 144,000TotalADMINISTRATION
$144,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,691,898251156Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2511565
District:
County:
INSPECT CONSTRUCTION PROJS.
PORT OF MIAMI TUNNEL OVERSIGHT CONSULTANT
Roadway ID:
Project Length: 0.496
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87059000
6
6-20
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 0 0134 0 134
0 0 0 0 0 0134 134TotalPLANNING AND DESIGN
D 400 300 0 0 00 0 700
DI 300 300 300 300 3001,250 1,500 4,250
DIS 0 0 0 0 0300 0 300
700 600 300 300 300 1,5001,550 5,250TotalMAINTENANCE
Section A1 - Page 208 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$5,384Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,691,898251156Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512651
District:
County:
BIKE PATH/TRAIL
SOUTH DADE GREENWAYS NETWORK
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0375 0 375
0 0 0 0 0 0375 375TotalPLANNING AND DESIGN
0 0 0 0 0289 0 289
0 0 0 0 0 0289 289TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$664Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,949251265Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512652
District:
County:
BIKE PATH/TRAIL
BISCAYNE TRAIL/SW 87 AVE FROM OLD CUTLER RD TO BLACK POINT PARK & MARI
Roadway ID:
Project Length: 2.657
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0150 0 150
0 0 0 0 0 0150 150TotalPLANNING AND DESIGN
Section A1 - Page 209 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512652
District:
County:
BIKE PATH/TRAIL
BISCAYNE TRAIL/SW 87 AVE FROM OLD CUTLER RD TO BLACK POINT PARK & MARI
Roadway ID:
Project Length: 2.657
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0552 0 552
0 0 0 0 0 0552 552TotalCONSTRUCTION
$702Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,949251265Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512653
District:
County:
BIKE PATH/TRAIL
BLACK CREEK TRAIL(A) FROM BLACK POINT PARK TO MARY/PENNY THOMPSON PARK
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04 0 4
Section A1 - Page 210 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512653
District:
County:
BIKE PATH/TRAIL
BLACK CREEK TRAIL(A) FROM BLACK POINT PARK TO MARY/PENNY THOMPSON PARK
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,780 0 2,780
0 0 0 0 0 02,784 2,784TotalCONSTRUCTION
$2,784Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,949251265Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 211 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512654
District:
County:
BIKE PATH/TRAIL
BISCAYNE S DADE(C&D) FROM BLACK POINT PARK TO SW 138 ST & SW 137 AVE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0625 0 625
0 0 0 0 0 0625 625TotalPLANNING AND DESIGN
$625Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,949251265Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512656
District:
County:
BIKE PATH/TRAIL
OLD CUTLER TRAIL FROM SW 136 ST/SW 63 AVE TO CARTAGENA PLAZA
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05 0 5
0 0 0 0 01,319 0 1,319
0 0 0 0 0 01,324 1,324TotalCONSTRUCTION
$1,324Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,949251265Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 212 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512657
District:
County:
BIKE PATH/TRAIL
BISCAYNE TRAIL SEG D, SW 328 ST/SW 137 AVE TO HOMESTEAD BAYFRONT PARK
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 5 0 0 00 0 5
TALT 0 1,126 0 0 00 0 1,126
TALU 0 719 0 0 00 0 719
0 1,850 0 0 0 00 1,850TotalCONSTRUCTION
$1,850Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,949251265Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512713
District:
County:
BIKE PATH/TRAIL
NBEACH REC CORRIDOR FROM 21ST STREET TO 64TH STTEET
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0704 0 704
0 0 0 0 0 0704 704TotalCONSTRUCTION
$704Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,970251271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 213 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512715
District:
County:
BIKE PATH/TRAIL
MIDDLE BEACH REC-PH1 FROM 47 ST TO 53 ST INCLG BEACH VIEW PARK AT 53 S
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
TALU 1,000 0 0 0 00 0 1,000
1,005 0 0 0 0 00 1,005TotalCONSTRUCTION
$1,005Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,970251271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512716
District:
County:
BIKE PATH/TRAIL
NORTH BEACH CORRIDOR -VARIOUS BIKE PATH LINKS, ADA ACCESS, SIDEWALK +
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 31 0 0 00 0 31
TALU 0 292 0 0 00 0 292
0 323 0 0 0 00 323TotalCONSTRUCTION
$323Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,970251271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 214 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2516701
District:
County:
PD&E/EMO STUDY
SR 836/I-395/I-95 FROM NW 17TH AVENUE TO MACARTHUR CSWY BR
Roadway ID:
Project Length: 2.748
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87200000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,828 0 1,828
0 0 0 0 03,309 0 3,309
0 0 0 0 01,729 0 1,729
0 0 0 0 0718 0 718
0 0 0 0 0154 0 154
0 0 0 0 0 07,738 7,738TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$7,738Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,738251670Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2516841
District:
County:
INTERMODAL HUB CAPACITY
SR 9A/I-95 GOLDEN GLADES MULTIMODAL TERMINAL
Roadway ID:
Project Length: 0.727
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0158 0 158
0 0 0 0 05 0 5
Section A1 - Page 215 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2516841
District:
County:
INTERMODAL HUB CAPACITY
SR 9A/I-95 GOLDEN GLADES MULTIMODAL TERMINAL
Roadway ID:
Project Length: 0.727
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0163 163TotalPLANNING AND DESIGN
0 0 0 0 0572 0 572
0 0 0 0 013 0 13
0 0 0 0 0 0585 585TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$748Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $51,951251684Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2516842
District:
County:
PARK AND RIDE LOTS
SR 9A/I-95 LEGAL CONSULTANT FOR GOLDEN GLADES MULTIMODAL TERMINL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0269 0 269
0 0 0 0 0 0269 269TotalPLANNING AND DESIGN
$269Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $51,951251684Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 216 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2516844
District:
County:
PARK AND RIDE LOTS
SR 9A/I-95 GOLDEN GLADES INTERCHANGE PARK & RIDE (EAST LOT)
Roadway ID:
Project Length: 0.198
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0922 0 922
0 0 0 0 050 0 50
0 0 0 0 0 0972 972TotalCONSTRUCTION
$972Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $51,951251684Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2516881
District:
County:
BRIDGE-REPLACE AND ADD LANES
SR 836/I-395 FROM WEST OF I-95 TO MACARTHUR CSWY BRIDGE
Roadway ID:
Project Length: 1.693
Lanes Exist:Lanes Improved:Lanes Added:
1
3
2
MIAMI-DADE
LRTP Ref:
87200000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 03,732 0 3,732
DDR 0 0 0 0 025 0 25
DI 0 0 0 0 05,896 0 5,896
DIH 50 0 0 0 0875 0 925
DIS 0 0 0 0 0200 0 200
Section A1 - Page 217 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2516881
District:
County:
BRIDGE-REPLACE AND ADD LANES
SR 836/I-395 FROM WEST OF I-95 TO MACARTHUR CSWY BRIDGE
Roadway ID:
Project Length: 1.693
Lanes Exist:Lanes Improved:Lanes Added:
1
3
2
MIAMI-DADE
LRTP Ref:
87200000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 0136 0 136
NHPP 0 0 0 0 07,187 0 7,187
50 0 0 0 0 018,051 18,101TotalPLANNING AND DESIGN
BNCA 0 0 0 0 024 0 24
BNDS 0 0 0 0 01,193 0 1,193
BNIR 0 0 0 0 0130,806 0 130,806
DDR 0 0 0 0 0300 0 300
DI 0 0 0 0 09,579 0 9,579
DI 1,300 0 0 0 0620 0 1,920
DIH 0 0 0 0 02,268 0 2,268
DIS 0 0 0 0 02,074 0 2,074
DS 0 0 0 0 014,385 0 14,385
DS 0 0 0 0 011 0 11
GMR 0 0 0 0 010,644 0 10,644
LF 606 0 0 0 00 0 606
1,906 0 0 0 0 0171,904 173,810TotalRIGHT OF WAY
ACNP 60,000 111,178 0 0 00 0 171,178
BRRP 0 0 0 0 051 0 51
Section A1 - Page 218 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2516881
District:
County:
BRIDGE-REPLACE AND ADD LANES
SR 836/I-395 FROM WEST OF I-95 TO MACARTHUR CSWY BRIDGE
Roadway ID:
Project Length: 1.693
Lanes Exist:Lanes Improved:Lanes Added:
1
3
2
MIAMI-DADE
LRTP Ref:
87200000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 340 0 00 0 340
DI 5,153 21,467 15,673 555 5690 0 43,417
DI 177,405 104,927 3,326 0 00 0 285,658
LF 94 0 0 0 00 0 94
STED 0 1,106 100,000 0 00 0 101,106
242,652 238,678 119,339 555 569 051 601,844TotalDESIGN/BUILD
ACSU 0 0 0 0 00 7,000 7,000
0 0 0 0 0 7,0000 7,000TotalALTERNATIVE CONTRACTING INCENTIVES
$800,755Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $800,755251688Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 219 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055741
District:
County:
TRAFFIC SIGNALS
MIAMI-DADE COUNTYWDE AGREEMENT-TRAFFIC SIGNALS MAINTENANCE & OPERATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 00 0 0
0 0 0 0 0 00 0TotalPLANNING AND DESIGN
DDR 2,669 2,776 2,887 3,000 3,10525,208 0 39,645
DITS 4,338 4,446 4,555 4,668 4,7833,747 0 26,537
7,007 7,222 7,442 7,668 7,888 028,955 66,182TotalOPERATIONS
$66,182Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $66,182405574Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055751
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 997/KROME AVENUE FROM SR 5/US-1 TO SW 296TH STREET
Roadway ID:
Project Length: 3.827
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05 0 5
0 0 0 0 01,212 0 1,212
0 0 0 0 0 01,217 1,217TotalPLANNING AND DESIGN
Section A1 - Page 220 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055751
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 997/KROME AVENUE FROM SR 5/US-1 TO SW 296TH STREET
Roadway ID:
Project Length: 3.827
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 013 0 13
0 0 0 0 0 013 13TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
0 0 0 0 04 0 4
0 0 0 0 0 04 4TotalCONSTRUCTION
$1,234Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $59,677405575Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055752
District:
County:
PD&E/EMO STUDY
SR 997/KROME AVENUE FROM SO OF FLAGLER AVE TO SW 296TH ST (BY-PASS)
Roadway ID:
Project Length: 1.933
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 012 0 12
0 0 0 0 0 012 12TotalPLANNING AND DESIGN
0 0 0 0 0214 0 214
Section A1 - Page 221 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055752
District:
County:
PD&E/EMO STUDY
SR 997/KROME AVENUE FROM SO OF FLAGLER AVE TO SW 296TH ST (BY-PASS)
Roadway ID:
Project Length: 1.933
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,610 0 1,610
0 0 0 0 0 01,824 1,824TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,836Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $59,677405575Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055753
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM SR 5/US-1 TO LUCY STREET
Roadway ID:
Project Length: 1.810
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,118 0 2,118
0 0 0 0 02,446 0 2,446
0 0 0 0 0 04,564 4,564TotalRIGHT OF WAY
Section A1 - Page 222 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$4,564Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $59,677405575Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055755
District:
County:
RESURFACING
SR 997/KROME AVENUE FROM SR 5/US-1 TO SW 296TH ST W/EXCEPTIONS
Roadway ID:
Project Length: 3.827
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 057 0 57
0 0 0 0 0300 0 300
0 0 0 0 0 0357 357TotalPLANNING AND DESIGN
0 0 0 0 05,187 0 5,187
0 0 0 0 0 05,187 5,187TotalCONSTRUCTION
$5,544Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $59,677405575Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055756
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SW 312 ST/CAMPBELL DR FROM SR 997/KROME AVE TO SR 5/US 1 (TRUCKBYPASS)
Roadway ID:
Project Length: 0.753
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87000043
6
6-14
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 01,257 0 1,257
Section A1 - Page 223 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055756
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SW 312 ST/CAMPBELL DR FROM SR 997/KROME AVE TO SR 5/US 1 (TRUCKBYPASS)
Roadway ID:
Project Length: 0.753
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87000043
6
6-14
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSA 0 0 0 0 080 0 80
0 0 0 0 0 01,337 1,337TotalPLANNING AND DESIGN
ACNP 4,757 0 0 0 00 0 4,757
ACNP 21 0 0 0 00 0 21
SA 1,543 8,600 5,380 0 00 0 15,523
6,321 8,600 5,380 0 0 00 20,301TotalRIGHT OF WAY
SA 0 0 54 0 00 0 54
SU 0 0 13,876 1,776 00 0 15,652
0 0 13,930 1,776 0 00 15,706TotalCONSTRUCTION
SU 0 0 0 0 4800 0 480
0 0 0 0 480 00 480TotalALTERNATIVE CONTRACTING INCENTIVES
$37,824Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $59,677405575Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 224 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055757
District:
County:
WIDEN/RESURFACE EXIST LANES
SW 336 ST/DAVIS PKWY FROM SR 997/KROME AVENUE TO US 1 (TRUCK BYPASS)
Roadway ID:
Project Length: 0.127
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87000031
6
6-14
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSA 0 0 0 0 0375 0 375
0 0 0 0 0 0375 375TotalPLANNING AND DESIGN
SA 0 81 0 0 00 0 81
0 81 0 0 0 00 81TotalRIGHT OF WAY
SA 0 0 2,020 278 00 0 2,298
0 0 2,020 278 0 00 2,298TotalCONSTRUCTION
SA 0 0 0 0 600 0 60
0 0 0 0 60 00 60TotalALTERNATIVE CONTRACTING INCENTIVES
$2,814Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $59,677405575Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 225 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055758
District:
County:
WIDEN/RESURFACE EXIST LANES
SR 9336/PALM DRIVE FROM SR 997/KROME AVE TO SR 5/US 1 (TRUCK BYPASS)
Roadway ID:
Project Length: 0.127
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87160000
6
6-14
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 0 0200 0 200
DIH 0 0 0 0 020 0 20
0 0 0 0 0 0220 220TotalPLANNING AND DESIGN
DDR 0 0 1,044 145 00 0 1,189
DIH 0 0 27 0 00 0 27
0 0 1,071 145 0 00 1,216TotalCONSTRUCTION
DDR 0 0 0 0 400 0 40
0 0 0 0 40 00 40TotalALTERNATIVE CONTRACTING INCENTIVES
$1,476Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $59,677405575Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 226 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4055759
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 997/KROME AVENUE FROM SW 312ST/CAMPBELL DR
TO SW 296 ST (TRUCKBYPS)
Roadway ID:
Project Length: 1.036
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 0 0523 0 523
DIH 0 0 0 0 075 0 75
DS 0 0 0 0 00 0 0
0 0 0 0 0 0598 598TotalPLANNING AND DESIGN
DDR 0 210 103 0 00 0 313
DIH 42 25 15 0 00 0 82
DS 296 0 0 0 00 0 296
338 235 118 0 0 00 691TotalRIGHT OF WAY
DDR 0 0 2,532 423 00 0 2,955
DIH 0 0 81 0 00 0 81
0 0 2,613 423 0 00 3,036TotalCONSTRUCTION
DDR 0 0 0 0 600 0 60
0 0 0 0 60 00 60TotalALTERNATIVE CONTRACTING INCENTIVES
$4,385Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $59,677405575Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 227 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056101
District:
County:
LANDSCAPING
DISTRICTWIDE LANDSCAPING CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,880 0 2,880
0 0 0 0 0 02,880 2,880TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,880Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,032405610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056102
District:
County:
LANDSCAPING
DISTRICTWIDE LANDSCAPING PUSHBUTTON CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01 0 1
0 0 0 0 0 01 1TotalPLANNING AND DESIGN
0 0 0 0 0872 0 872
0 0 0 0 0 0872 872TotalCONSTRUCTION
$873Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,032405610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 228 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056103
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 047 0 47
0 0 0 0 0 047 47TotalCONSTRUCTION
$47Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,032405610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056104
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02 0 2
0 0 0 0 0 02 2TotalPLANNING AND DESIGN
0 0 0 0 0848 0 848
0 0 0 0 0 0848 848TotalCONSTRUCTION
$850Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,032405610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 229 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056105
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02 0 2
0 0 0 0 0 02 2TotalPLANNING AND DESIGN
0 0 0 0 02,638 0 2,638
0 0 0 0 0 02,638 2,638TotalCONSTRUCTION
$2,640Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,032405610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056106
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 06 0 6
0 0 0 0 0 06 6TotalPLANNING AND DESIGN
Section A1 - Page 230 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056106
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0834 0 834
0 0 0 0 0 0834 834TotalCONSTRUCTION
$840Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,032405610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056107
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 88 0 0 00 0 88
Section A1 - Page 231 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056107
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 715 0 0 00 0 715
0 803 0 0 0 00 803TotalCONSTRUCTION
$803Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,032405610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056108
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 17 00 0 17
Section A1 - Page 232 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056108
District:
County:
LANDSCAPING
DISTRICTWIDE PUSHBUTTON LANDSCAPING CONTRACTOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 1,082 00 0 1,082
0 0 0 1,099 0 00 1,099TotalCONSTRUCTION
$1,099Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,032405610Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056151
District:
County:
PD&E/EMO STUDY
NW 87TH AVENUE FROM NW 58TH STREET TO OKEECHOBEE ROAD
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,149 0 1,149
Section A1 - Page 233 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056151
District:
County:
PD&E/EMO STUDY
NW 87TH AVENUE FROM NW 58TH STREET TO OKEECHOBEE ROAD
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 00 0 0
0 0 0 0 0 01,149 1,149TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,149Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $53,279405615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056152
District:
County:
NEW ROAD CONSTRUCTION
NW 87TH AVENUE FROM NW 58TH STREET TO NW 74TH STREET
Roadway ID:
Project Length: 1.002
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 077 0 77
0 0 0 0 0966 0 966
0 0 0 0 0 01,043 1,043TotalPLANNING AND DESIGN
Section A1 - Page 234 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056152
District:
County:
NEW ROAD CONSTRUCTION
NW 87TH AVENUE FROM NW 58TH STREET TO NW 74TH STREET
Roadway ID:
Project Length: 1.002
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0536 0 536
0 0 0 0 0 0536 536TotalRAILROAD & UTILITIES
0 0 0 0 07,902 0 7,902
0 0 0 0 011 0 11
0 0 0 0 086 0 86
0 0 0 0 0 07,999 7,999TotalCONSTRUCTION
$9,578Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $53,279405615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056153
District:
County:
NEW ROAD CONSTRUCTION
NW 87TH AVENUE FROM NW 74TH STREET TO NW 103RD STREET
Roadway ID:
Project Length: 1.959
Lanes Exist:Lanes Improved:Lanes Added: 4
MIAMI-DADE
LRTP Ref:
87674507
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
EB 0 0 0 0 01,591 0 1,591
Section A1 - Page 235 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056153
District:
County:
NEW ROAD CONSTRUCTION
NW 87TH AVENUE FROM NW 74TH STREET TO NW 103RD STREET
Roadway ID:
Project Length: 1.959
Lanes Exist:Lanes Improved:Lanes Added: 4
MIAMI-DADE
LRTP Ref:
87674507
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 0718 0 718
RED 0 0 0 0 01,335 0 1,335
SA 0 0 0 0 065 0 65
SU 0 0 0 0 033 0 33
0 0 0 0 0 03,742 3,742TotalPLANNING AND DESIGN
LF 6,667 0 0 0 00 0 6,667
SA 0 0 0 0 094 0 94
SU 1,200 0 0 0 00 0 1,200
SU 0 0 0 0 010 0 10
SU 0 0 0 0 079 0 79
7,867 0 0 0 0 0183 8,050TotalRIGHT OF WAY
DS 128 0 0 0 00 0 128
LF 956 0 0 0 00 0 956
SU 22,777 0 0 0 00 0 22,777
23,861 0 0 0 0 00 23,861TotalCONSTRUCTION
SU 0 0 1,000 0 00 0 1,000
0 0 1,000 0 0 00 1,000TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 236 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$36,653Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $53,279405615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056154
District:
County:
ADD TURN LANE(S)
SR 25/OKEECHOBEE ROAD AND SR 932/NW 103 STREET
AT NW 87 AVENUE
Roadway ID:
Project Length: 0.560
Lanes Exist:Lanes Improved:Lanes Added:
4
6
1
MIAMI-DADE
LRTP Ref:
87090000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
Okeechobee Rd as is, is off system and needs to use state funds.
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 050 0 50
0 0 0 0 0 060 60TotalPLANNING AND DESIGN
DIH 53 0 0 0 00 0 53
DS 36 0 0 0 00 0 36
SU 5,750 0 0 0 00 0 5,750
5,839 0 0 0 0 00 5,839TotalCONSTRUCTION
$5,899Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $53,279405615Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 237 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056361
District:
County:
RESURFACING
SR 90/SW 8TH STREET FROM 5.7 MI E OF MICCOS E TO 1.3 MI W OF KROME AV
Roadway ID:
Project Length: 10.750
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87110000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0104 0 104
0 0 0 0 0 0104 104TotalPLANNING AND DESIGN
0 0 0 0 03,867 0 3,867
0 0 0 0 0 03,867 3,867TotalCONSTRUCTION
$3,971Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,887405636Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056362
District:
County:
RESURFACING
SR 90/TAMIAMI TRAIL FM 13.1MI E OF COLLIER CL TO 11.8M W OF KROME AVE
Roadway ID:
Project Length: 0.737
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87110000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0143 0 143
DIH 0 0 0 0 028 0 28
DS 0 0 0 0 019 0 19
Section A1 - Page 238 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4056362
District:
County:
RESURFACING
SR 90/TAMIAMI TRAIL FM 13.1MI E OF COLLIER CL TO 11.8M W OF KROME AVE
Roadway ID:
Project Length: 0.737
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87110000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0190 190TotalPLANNING AND DESIGN
DDR 0 0 0 0 0581 0 581
DIH 0 0 0 0 033 0 33
DS 92 0 0 0 00 0 92
92 0 0 0 0 0614 706TotalCONSTRUCTION
DDR 20 0 0 0 00 0 20
20 0 0 0 0 00 20TotalALTERNATIVE CONTRACTING INCENTIVES
$916Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,887405636Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 239 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4062301
District:
County:
PRELIMINARY ENGINEERING
SR 90/SW 8TH STREET FROM 11 MI W OF KROME AVE TO 1 MI W OF KROME AVE
Roadway ID:
Project Length: 10.750
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87110000
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 1035 0 85
10 10 10 10 10 035 85TotalPLANNING AND DESIGN
DIH 25 25 25 25 25636 0 761
25 25 25 25 25 0636 761TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
DIH 10 10 10 10 1040 0 90
DS 0 0 0 0 0165 0 165
10 10 10 10 10 0205 255TotalCONSTRUCTION
$1,101Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,101406230Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 240 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4064861
District:
County:
RIGHT OF WAY ACTIVITIES
D/W RIGHT-OF-WAY DONATIONS AND DEDICATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 50 50 50 50 5080 0 330
50 50 50 50 50 080 330TotalPLANNING AND DESIGN
DIH 10 10 10 10 10374 0 424
10 10 10 10 10 0374 424TotalRIGHT OF WAY
$754Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $754406486Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4068003
District:
County:
NEW ROAD CONSTRUCTION
MIAMI INTERMODAL CTR (MIC) TRI-RAIL ACCESS RD
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 06 0 6
0 0 0 0 0 06 6TotalPLANNING AND DESIGN
0 0 0 0 01,775 0 1,775
Section A1 - Page 241 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4068003
District:
County:
NEW ROAD CONSTRUCTION
MIAMI INTERMODAL CTR (MIC) TRI-RAIL ACCESS RD
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 019 0 19
0 0 0 0 0 01,794 1,794TotalCONSTRUCTION
$1,800Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $415,651406800Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 242 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4068008
District:
County:
NEW ROAD CONSTRUCTION
MIAMI INTERMODAL CTR (MIC) FROM BUS PLAZA ROAD WAY TO NW 25 STREET
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,758 0 3,758
0 0 0 0 0 03,758 3,758TotalCONSTRUCTION
$3,758Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $415,651406800Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4068009
District:
County:
PUBLIC TRANSPORTATION STATION
MIAMI INTERMODAL CTR (MIC) TRI-RAIL RELOCATION /TEMPORARY STATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 00 0 0
0 0 0 0 0 00 0TotalDESIGN/BUILD
$0Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $415,651406800Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 243 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4073471
District:
County:
TRANSPORTATION PLANNING
DISTRICTWIDE INTERGOVERNMENTAL AFFAIRS & COMMUNITY LIAISON SVCS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 5 5 5 5 0115 0 135
DS 0 0 0 0 03,811 0 3,811
5 5 5 5 0 03,926 3,946TotalPLANNING AND DESIGN
$3,946Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,496407347Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4073472
District:
County:
TRANSPORTATION PLANNING
DISTRICTWIDE COMMUNICATION PROGRAMS & SPECIAL PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 700 650 650 625 625300 0 3,550
700 650 650 625 625 0300 3,550TotalPLANNING AND DESIGN
$3,550Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,496407347Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 244 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4083231
District:
County:
FUNDING ACTION
MIAMI INTERMODAL CTR (MIC) FDOT/TIFIA LOAN REPAYMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 017,107 0 17,107
0 0 0 0 0 017,107 17,107TotalADMINISTRATION
$17,107Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $276,171408323Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4095211
District:
County:
TRAFFIC OPS IMPROVEMENT
DISTRICTWIDE TRAFFIC OPERATIONS CONSULTANT STUDIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,697 0 1,697
0 0 0 0 0 01,697 1,697TotalPLANNING AND DESIGN
$1,697Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,373409521Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 245 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4095212
District:
County:
TRAFFIC OPS IMPROVEMENT
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,263 0 1,263
0 0 0 0 0 01,263 1,263TotalPLANNING AND DESIGN
$1,263Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,373409521Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4095213
District:
County:
TRAFFIC OPS IMPROVEMENT
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 5 0 0 072 0 87
DS 50 0 0 0 0700 0 750
60 5 0 0 0 0772 837TotalPLANNING AND DESIGN
$837Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,373409521Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 246 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4095214
District:
County:
TRAFFIC OPS IMPROVEMENT
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,055 0 1,055
0 0 0 0 0 01,055 1,055TotalPLANNING AND DESIGN
$1,055Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,373409521Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4095215
District:
County:
TRAFFIC OPS IMPROVEMENT
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 4 4 4 0 04 0 16
DS 300 300 300 300 0300 0 1,500
304 304 304 300 0 0304 1,516TotalPLANNING AND DESIGN
$1,516Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,373409521Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 247 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4095216
District:
County:
TRAFFIC OPS IMPROVEMENT
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 2 3 0 00 0 5
DS 0 350 0 350 00 0 700
0 352 3 350 0 00 705TotalPLANNING AND DESIGN
$705Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,373409521Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4095217
District:
County:
TRAFFIC OPS IMPROVEMENT
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 3000 0 300
0 0 0 0 300 00 300TotalPLANNING AND DESIGN
$300Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,373409521Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 248 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4102651
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE LEAD ABATEMENT INSPECTIONS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,830 0 2,830
0 0 0 0 0 02,830 2,830TotalCONSTRUCTION
$2,830Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,003410265Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4102652
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE ASBESTOS & LEAD ABATEMENT SUPERVISION & INSPECTNS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 300 300 300 300 300673 0 2,173
300 300 300 300 300 0673 2,173TotalCONSTRUCTION
$2,173Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,003410265Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 249 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4106461
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 934/NE 79 & 82 ST FROM SR 5/BISCAYNE BLVD TO BAY DRIVE
Roadway ID:
Project Length: 3.441
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03 0 3
0 0 0 0 0 03 3TotalPLANNING AND DESIGN
$3Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,941410646Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4106462
District:
County:
PD&E/EMO STUDY
SR 934/NE 79 STREET FROM WEST OF I-95(13 CT) TO END OF SR 934/1 WAY P
Roadway ID:
Project Length: 5.985
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,234 0 1,234
0 0 0 0 0 01,234 1,234TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,234Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,941410646Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 250 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4106463
District:
County:
RESURFACING
SR 934/NE 82 STREET FRON SR 5/BISCAYNE BLVD TO NE BAYSHORE COURT
Roadway ID:
Project Length: 0.763
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0300 0 300
0 0 0 0 0 0300 300TotalPLANNING AND DESIGN
0 0 0 0 018 0 18
0 0 0 0 09 0 9
0 0 0 0 00 0 0
0 0 0 0 0 027 27TotalRIGHT OF WAY
0 0 0 0 088 0 88
0 0 0 0 0160 0 160
0 0 0 0 0641 0 641
0 0 0 0 08 0 8
0 0 0 0 0 0897 897TotalCONSTRUCTION
$1,224Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,941410646Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 251 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4106464
District:
County:
PD&E/EMO STUDY
SR 934/NE/NW 79 ST FROM WEST OF I-95(13 CT) TO END OF SR 934/1 WAY PT
Roadway ID:
Project Length: 5.948
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87080001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 1,400 0 0 0 00 0 1,400
DIH 40 0 0 0 040 0 80
1,440 0 0 0 0 040 1,480TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,480Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,941410646Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4109931
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE STRUCTURES DESIGN AND REVIEW CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 1060 0 110
DS 300 300 300 300 3004,375 0 5,875
310 310 310 310 310 04,435 5,985TotalPLANNING AND DESIGN
$5,985Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,985410993Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 252 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4114331
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE DRAINAGE DESIGN AND PLANS REVIEW CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04,127 0 4,127
0 0 0 0 0 04,127 4,127TotalPLANNING AND DESIGN
$4,127Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,771411433Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4114332
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE DRAINAGE DESIGN AND PLAN REVIEW CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 40 40 40 0 024 0 144
DS 400 400 400 400 400500 0 2,500
440 440 440 400 400 0524 2,644TotalPLANNING AND DESIGN
$2,644Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,771411433Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 253 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4116691
District:
County:
PD&E/EMO STUDY
EVERGLADES COMPREHENSIVE RESTORATION PLAN (CERP)
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 1076 0 126
10 10 10 10 10 076 126TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$126Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $126411669Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124731
District:
County:
RIGID PAVEMENT REHABILITATION
SR 5/BRICKELL AVENUE FROM S OF SE 25TH ROAD TO SE 4TH STREET
Roadway ID:
Project Length: 1.689
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0114 0 114
0 0 0 0 01,084 0 1,084
0 0 0 0 0 01,198 1,198TotalPLANNING AND DESIGN
0 0 0 0 05 0 5
0 0 0 0 01,357 0 1,357
0 0 0 0 0 01,362 1,362TotalRIGHT OF WAY
Section A1 - Page 254 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124731
District:
County:
RIGID PAVEMENT REHABILITATION
SR 5/BRICKELL AVENUE FROM S OF SE 25TH ROAD TO SE 4TH STREET
Roadway ID:
Project Length: 1.689
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0459 0 459
0 0 0 0 0 0459 459TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
0 0 0 0 0263 0 263
0 0 0 0 0322 0 322
0 0 0 0 07,735 0 7,735
0 0 0 0 01,819 0 1,819
0 0 0 0 0 010,139 10,139TotalCONSTRUCTION
$13,158Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,394412473Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 255 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124732
District:
County:
LIGHTING
SR 5/BRICKELL AVENUE FROM S OF SE 25TH ROAD TO SE 15TH ROAD
Roadway ID:
Project Length: 0.830
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,013 0 1,013
0 0 0 0 0 01,013 1,013TotalCONSTRUCTION
0 0 0 0 01,013 0 1,013
0 0 0 0 0 01,013 1,013TotalLOCAL ADVANCE REIMBURSEMENT
$2,026Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,394412473Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124733
District:
County:
ADV TRAVELER INFORMATION SYSTM
SR 5/BRICKELL AVENUE FROM S OF SE 25 ROAD TO BRICKELL BR(N OF SE 5 ST)
Roadway ID:
Project Length: 1.721
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 06 0 6
0 0 0 0 0 06 6TotalPLANNING AND DESIGN
0 0 0 0 0358 0 358
0 0 0 0 0 0358 358TotalDESIGN/BUILD
Section A1 - Page 256 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$364Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,394412473Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124735
District:
County:
INTERSECTION IMPROVEMENT
SR 5/BRICKELL AVE FROM SE 5 STREET TO SE 8 STREET
Roadway ID:
Project Length: 0.249
Lanes Exist:Lanes Improved:Lanes Added:
5
5
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 038 0 38
0 0 0 0 0 038 38TotalPLANNING AND DESIGN
0 0 0 0 04 0 4
0 0 0 0 0 04 4TotalRAILROAD & UTILITIES
0 0 0 0 0159 0 159
0 0 0 0 0156 0 156
0 0 0 0 0721 0 721
0 0 0 0 083 0 83
0 0 0 0 0 01,119 1,119TotalCONSTRUCTION
$1,161Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,394412473Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 257 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124736
District:
County:
DRAINAGE IMPROVEMENTS
SR 5/BRICKELL AVE FROM NE OF SE 5TH STREET TO S OF BRICKELL AVE BRDG
Roadway ID:
Project Length: 0.037
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02 0 2
0 0 0 0 0 02 2TotalPLANNING AND DESIGN
0 0 0 0 076 0 76
0 0 0 0 0 076 76TotalCONSTRUCTION
$78Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,394412473Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124737
District:
County:
RESURFACING
SR 5/SE 2ND AVENUE FROM SE 2ND STREET TO SE 4TH STREET
Roadway ID:
Project Length: 0.317
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87030001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 069 0 69
DIH 0 0 0 0 043 0 43
DS 0 0 0 0 0100 0 100
Section A1 - Page 258 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124737
District:
County:
RESURFACING
SR 5/SE 2ND AVENUE FROM SE 2ND STREET TO SE 4TH STREET
Roadway ID:
Project Length: 0.317
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87030001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HSP 0 0 0 0 0200 0 200
0 0 0 0 0 0412 412TotalPLANNING AND DESIGN
DIH 0 0 0 0 07 0 7
DS 0 0 0 0 0341 0 341
LF 8 0 0 0 00 0 8
8 0 0 0 0 0348 356TotalRIGHT OF WAY
DS 31 0 0 0 00 0 31
HSP 896 0 0 0 00 0 896
SA 623 0 0 0 00 0 623
1,550 0 0 0 0 00 1,550TotalCONSTRUCTION
$2,318Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,394412473Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 259 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124738
District:
County:
RESURFACING
SR 90/US-41/SR 5/US-1/BRICKELL FROM N OF SE 5 STREET TO SE 3 AVENUE
Roadway ID:
Project Length: 0.248
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0272 0 272
0 0 0 0 0 0272 272TotalPLANNING AND DESIGN
0 0 0 0 03 0 3
0 0 0 0 00 0 0
0 0 0 0 0 03 3TotalRAILROAD & UTILITIES
0 0 0 0 01,033 0 1,033
0 0 0 0 0 01,033 1,033TotalCONSTRUCTION
$1,308Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,394412473Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124739
District:
County:
RESURFACING
SR 5/BISCAYNE BLVD FROM SE 3RD AVENUE TO SE 2ND STREET
Roadway ID:
Project Length: 0.243
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0206 0 206
Section A1 - Page 260 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124739
District:
County:
RESURFACING
SR 5/BISCAYNE BLVD FROM SE 3RD AVENUE TO SE 2ND STREET
Roadway ID:
Project Length: 0.243
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 032 0 32
DS 0 0 0 0 0122 0 122
0 0 0 0 0 0360 360TotalPLANNING AND DESIGN
DIH 0 0 0 0 05 0 5
DS 0 0 0 0 0393 0 393
LF 9 0 0 0 00 0 9
9 0 0 0 0 0398 407TotalRIGHT OF WAY
DDR 41 0 0 0 00 0 41
NHRE 150 0 0 0 00 0 150
SA 1,023 0 0 0 00 0 1,023
1,214 0 0 0 0 00 1,214TotalCONSTRUCTION
$1,981Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,394412473Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 261 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124791
District:
County:
RESURFACING
SR 985/SW 107 AVENUE FROM SR 90/SW 8 STREET TO SR 968/FLAGLER STREET
Roadway ID:
Project Length: 0.505
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0275 0 275
0 0 0 0 0 0275 275TotalPLANNING AND DESIGN
0 0 0 0 0461 0 461
0 0 0 0 0 0461 461TotalCONSTRUCTION
$736Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $49,535412479Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124792
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 985/SW 107 AVENUE FROM SW 3 STREET TO N OF WEST FLAGLER ST
Roadway ID:
Project Length: 0.359
Lanes Exist:Lanes Improved:Lanes Added:
2
3
1
MIAMI-DADE
LRTP Ref:
87072000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DC 0 0 0 0 00 0 0
DDR 0 0 0 0 086 0 86
DIH 0 0 0 0 0530 0 530
DS 0 0 0 0 0172 0 172
Section A1 - Page 262 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124792
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 985/SW 107 AVENUE FROM SW 3 STREET TO N OF WEST FLAGLER ST
Roadway ID:
Project Length: 0.359
Lanes Exist:Lanes Improved:Lanes Added:
2
3
1
MIAMI-DADE
LRTP Ref:
87072000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 033 0 33
0 0 0 0 0 0821 821TotalPLANNING AND DESIGN
DDR 0 0 0 0 03,608 0 3,608
DIH 0 0 0 0 0261 0 261
DS 75 0 0 0 02,073 0 2,148
LF 0 0 0 0 0365 0 365
75 0 0 0 0 06,307 6,382TotalRAILROAD & UTILITIES
DDR 0 0 0 0 0249 0 249
DIH 0 0 0 0 037 0 37
0 0 0 0 0 0286 286TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
ACSU 0 0 0 0 04,416 0 4,416
DDR 0 0 0 0 068 0 68
DIH 0 0 0 0 067 0 67
LF 0 0 0 0 0116 0 116
SU 0 0 0 0 050 0 50
0 0 0 0 0 04,717 4,717TotalCONSTRUCTION
DDR 0 200 0 0 00 0 200
Section A1 - Page 263 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124792
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 985/SW 107 AVENUE FROM SW 3 STREET TO N OF WEST FLAGLER ST
Roadway ID:
Project Length: 0.359
Lanes Exist:Lanes Improved:Lanes Added:
2
3
1
MIAMI-DADE
LRTP Ref:
87072000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 200 0 0 0 00 200TotalALTERNATIVE CONTRACTING INCENTIVES
$12,406Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $49,535412479Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124793
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 985/SW 107 AVENUE FROM THE SW 1100 BLOCK TO SW 3 STREET
Roadway ID:
Project Length: 0.561
Lanes Exist:Lanes Improved:Lanes Added:
4
6
2
MIAMI-DADE
LRTP Ref:
87072000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DC 0 0 0 0 00 0 0
DIH 0 0 0 0 0888 0 888
DS 0 0 0 0 0511 0 511
LF 0 0 0 0 0125 0 125
0 0 0 0 0 01,524 1,524TotalPLANNING AND DESIGN
BNCA 0 0 0 0 084 0 84
BNDS 0 0 0 0 02,121 0 2,121
Section A1 - Page 264 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124793
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 985/SW 107 AVENUE FROM THE SW 1100 BLOCK TO SW 3 STREET
Roadway ID:
Project Length: 0.561
Lanes Exist:Lanes Improved:Lanes Added:
4
6
2
MIAMI-DADE
LRTP Ref:
87072000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 04,519 0 4,519
DIH 0 0 0 0 0835 0 835
DS 50 0 0 0 09,762 0 9,812
DS 0 0 0 0 08 0 8
LF 0 0 0 0 01,363 0 1,363
50 0 0 0 0 018,692 18,742TotalRIGHT OF WAY
ACSU 0 0 0 0 07,692 0 7,692
DDR 0 0 0 0 046 0 46
DDR 0 0 0 0 0173 0 173
DIH 0 0 0 0 076 0 76
DS 0 0 0 0 01,668 0 1,668
DS 0 0 0 0 027 0 27
HSP 0 0 0 0 03,056 0 3,056
LF 0 0 0 0 0328 0 328
S117 0 0 0 0 02 0 2
SU 0 0 0 0 01,694 0 1,694
0 0 0 0 0 014,762 14,762TotalCONSTRUCTION
DDR 0 600 0 0 00 0 600
Section A1 - Page 265 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124793
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 985/SW 107 AVENUE FROM THE SW 1100 BLOCK TO SW 3 STREET
Roadway ID:
Project Length: 0.561
Lanes Exist:Lanes Improved:Lanes Added:
4
6
2
MIAMI-DADE
LRTP Ref:
87072000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 600 0 0 0 00 600TotalALTERNATIVE CONTRACTING INCENTIVES
$35,628Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $49,535412479Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4124794
District:
County:
LANDSCAPING
SR 985/SW 107 AVE FROM SW 1100 BLOCK TO NORTH OF SR 968/FLAGLER STREET
Roadway ID:
Project Length: 0.920
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 8 0 0 0 00 0 8
DS 60 0 0 0 00 0 60
68 0 0 0 0 00 68TotalPLANNING AND DESIGN
DIH 0 0 13 0 00 0 13
DS 0 0 684 0 00 0 684
0 0 697 0 0 00 697TotalCONSTRUCTION
Section A1 - Page 266 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$765Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $49,535412479Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4140521
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS STUDIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,919 0 1,919
0 0 0 0 0 01,919 1,919TotalPLANNING AND DESIGN
$1,919Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,737414052Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4140522
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 0 0 042 0 62
Section A1 - Page 267 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4140522
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 50 50 0 0 0600 0 700
60 60 0 0 0 0642 762TotalPLANNING AND DESIGN
$762Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,737414052Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4140523
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 3 3 0 00 0 6
Section A1 - Page 268 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4140523
District:
County:
TRANSPORTATION STATISTICS
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 250 200 200 200 2000 0 1,050
250 203 203 200 200 00 1,056TotalPLANNING AND DESIGN
$1,056Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,737414052Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146243
District:
County:
RESURFACING
SR 5/BISCAYNE BLVD FROM N OF NE 196TH STREET TO N OF NE 213TH STREET
Roadway ID:
Project Length: 1.618
Lanes Exist:Lanes Improved:Lanes Added:
1
1
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0261 0 261
DIH 0 0 0 0 025 0 25
DS 0 0 0 0 053 0 53
Section A1 - Page 269 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146243
District:
County:
RESURFACING
SR 5/BISCAYNE BLVD FROM N OF NE 196TH STREET TO N OF NE 213TH STREET
Roadway ID:
Project Length: 1.618
Lanes Exist:Lanes Improved:Lanes Added:
1
1
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0339 339TotalPLANNING AND DESIGN
DDR 0 0 0 0 010 0 10
LF 0 0 0 0 06 0 6
0 0 0 0 0 016 16TotalRAILROAD & UTILITIES
ACSA 0 0 0 0 0960 0 960
DDR 0 0 0 0 044 0 44
DDR 0 0 0 0 020 0 20
DS 0 0 0 0 0118 0 118
SA 0 0 0 0 0462 0 462
0 0 0 0 0 01,604 1,604TotalCONSTRUCTION
DS 60 0 0 0 00 0 60
60 0 0 0 0 00 60TotalALTERNATIVE CONTRACTING INCENTIVES
$2,019Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,019414624Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 270 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146331
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 968/W FLAGLER ST FROM WEST 14TH AVENUE TO WEST 2ND AVENUE
Roadway ID:
Project Length: 1.285
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0523 0 523
DIH 0 0 0 0 0144 0 144
DS 0 0 0 0 0857 0 857
LF 0 0 0 0 0110 0 110
0 0 0 0 0 01,634 1,634TotalPLANNING AND DESIGN
DDR 0 0 0 0 0119 0 119
DIH 0 0 0 0 0115 0 115
DS 0 0 0 0 043 0 43
LF 0 0 0 0 01,652 0 1,652
0 0 0 0 0 01,929 1,929TotalRIGHT OF WAY
ACSA 0 0 0 0 06,183 0 6,183
DS 0 0 0 0 0209 0 209
DS 0 0 0 0 04,207 0 4,207
LF 0 0 0 0 0255 0 255
0 0 0 0 0 010,854 10,854TotalCONSTRUCTION
DS 0 400 0 0 00 0 400
0 400 0 0 0 00 400TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 271 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$14,817Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,646414633Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146332
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 968/SW 1ST STREET FROM W FLAGLER STREET TO EAST OF 17TH AVENUE
Roadway ID:
Project Length: 0.760
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87053001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 030 0 30
DIH 0 0 0 0 0124 0 124
DS 0 0 0 0 023 0 23
DS 0 0 0 0 047 0 47
EB 0 0 0 0 0156 0 156
LF 0 0 0 0 0132 0 132
SA 0 0 0 0 099 0 99
SU 0 0 0 0 0956 0 956
0 0 0 0 0 01,567 1,567TotalPLANNING AND DESIGN
DDR 0 0 0 0 069 0 69
DIH 0 0 0 0 069 0 69
LF 0 0 0 0 01,451 0 1,451
0 0 0 0 0 01,589 1,589TotalRIGHT OF WAY
ACSA 0 0 0 0 04,319 0 4,319
DDR 0 0 0 0 068 0 68
DS 0 0 0 0 03,727 0 3,727
Section A1 - Page 272 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146332
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 968/SW 1ST STREET FROM W FLAGLER STREET TO EAST OF 17TH AVENUE
Roadway ID:
Project Length: 0.760
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87053001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 085 0 85
LF 0 0 0 0 0224 0 224
0 0 0 0 0 08,423 8,423TotalCONSTRUCTION
SA 0 250 0 0 00 0 250
0 250 0 0 0 00 250TotalALTERNATIVE CONTRACTING INCENTIVES
$11,829Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,646414633Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146431
District:
County:
RESURFACING
SR 933/SW/NW 12 AVE FROM SW 13TH STREET TO NW 7TH STREET
Roadway ID:
Project Length: 1.343
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0306 0 306
0 0 0 0 0 0306 306TotalPLANNING AND DESIGN
0 0 0 0 04,596 0 4,596
Section A1 - Page 273 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146431
District:
County:
RESURFACING
SR 933/SW/NW 12 AVE FROM SW 13TH STREET TO NW 7TH STREET
Roadway ID:
Project Length: 1.343
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 038 0 38
0 0 0 0 0134 0 134
0 0 0 0 0 04,768 4,768TotalCONSTRUCTION
0 0 0 0 0110 0 110
0 0 0 0 0 0110 110TotalALTERNATIVE CONTRACTING INCENTIVES
$5,184Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,326414643Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146432
District:
County:
LANDSCAPING
SR 933/NW 12 AVENUE FROM SW 22 STREET TO NW 8 TERRACE
Roadway ID:
Project Length: 2.085
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87085000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 013 0 13
DS 0 0 0 0 0101 0 101
0 0 0 0 0 0114 114TotalPLANNING AND DESIGN
Section A1 - Page 274 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4146432
District:
County:
LANDSCAPING
SR 933/NW 12 AVENUE FROM SW 22 STREET TO NW 8 TERRACE
Roadway ID:
Project Length: 2.085
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87085000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 26 0 0 0 00 0 26
DS 1,002 0 0 0 00 0 1,002
1,028 0 0 0 0 00 1,028TotalCONSTRUCTION
$1,142Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,326414643Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4147661
District:
County:
BUILDING REPAIR/REHABILITATION
CURTIS MANSION RESTORATION & TRAILHEAD (COF MIAMI SPRINGS)LAP
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,000 0 1,000
0 0 0 0 0 01,000 1,000TotalCONSTRUCTION
$1,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,150414766Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 275 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4149641
District:
County:
PD&E/EMO STUDY
SR 9A/I-95 FROM S OF SR 836/I-395 TO BROWARD COUNTY LINE
Roadway ID:
Project Length: 14.179
Lanes Exist:Lanes Improved:Lanes Added:
12
2
2
MIAMI-DADE
LRTP Ref:
87270000
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 13,035 0 00 0 13,035
0 0 13,035 0 0 00 13,035TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$13,035Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,123414964Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4149646
District:
County:
CORRIDOR/SUBAREA PLANNING
SR 9A/I-95 FROM US 1 TO DADE/BROWARD LINE
Roadway ID:
Project Length: 17.260
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,688 0 2,688
0 0 0 0 0 02,688 2,688TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,688Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,123414964Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 276 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4149647
District:
County:
PD&E/EMO STUDY
SR 9A/I-95 FROM US-1/SOUTH DIXIE HIGHWAY
TO SOUTH OF SR 90/SW 8 STREET
Roadway ID:
Project Length: 1.645
Lanes Exist:Lanes Improved:Lanes Added:
2
4
MIAMI-DADE
LRTP Ref:
87270000
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 2,500 4,000 0 00 0 6,500
DIH 0 200 0 0 00 0 200
0 2,700 4,000 0 0 00 6,700TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$6,700Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,123414964Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4149648
District:
County:
PD&E/EMO STUDY
SR 9A/I-95 FROM NORTH OF SR 90/SW 8 STREET
TO SOUTH OF SR 836/I-395
Roadway ID:
Project Length: 1.000
Lanes Exist:Lanes Improved:Lanes Added:
3
4
MIAMI-DADE
LRTP Ref:
87270000
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 1,500 2,000 0 00 0 3,500
DIH 0 200 0 0 00 0 200
0 1,700 2,000 0 0 00 3,700TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,700Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,123414964Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 277 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4152391
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PLANS REVIEW CONSULTANT AND SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,506 0 2,506
0 0 0 0 0 02,506 2,506TotalPLANNING AND DESIGN
0 0 0 0 04 0 4
0 0 0 0 0 04 4TotalRIGHT OF WAY
$2,510Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,659415239Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4152392
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PLANS REVIEW CONSULTANT AND SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 18 18 18 0 072 0 126
Section A1 - Page 278 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4152392
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PLANS REVIEW CONSULTANT AND SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 100 100 100 0 0323 0 623
118 118 118 0 0 0395 749TotalPLANNING AND DESIGN
$749Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,659415239Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 279 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4152393
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PLANS REVIEW CONSULTANT AND SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 200 300 300 300 3000 0 1,400
200 300 300 300 300 00 1,400TotalPLANNING AND DESIGN
$1,400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,659415239Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4154561
District:
County:
ADD SPECIAL USE LANE
SR 9A/I-95 EXPRESS FROM N OF SR 836/I-395 TO GOLDEN GLADES INTERCHANGE
Roadway ID:
Project Length: 9.640
Lanes Exist:Lanes Improved:Lanes Added:
10
2
10
MIAMI-DADE
LRTP Ref:
87270000
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,865 0 3,865
0 0 0 0 0238 0 238
0 0 0 0 059 0 59
0 0 0 0 0900 0 900
0 0 0 0 0648 0 648
0 0 0 0 0895 0 895
Section A1 - Page 280 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4154561
District:
County:
ADD SPECIAL USE LANE
SR 9A/I-95 EXPRESS FROM N OF SR 836/I-395 TO GOLDEN GLADES INTERCHANGE
Roadway ID:
Project Length: 9.640
Lanes Exist:Lanes Improved:Lanes Added:
10
2
10
MIAMI-DADE
LRTP Ref:
87270000
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 08,895 0 8,895
0 0 0 0 0 015,500 15,500TotalPLANNING AND DESIGN
0 0 0 0 015 0 15
0 0 0 0 0341 0 341
0 0 0 0 0 0356 356TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
0 0 0 0 0813 0 813
0 0 0 0 0316 0 316
0 0 0 0 0103,277 0 103,277
0 0 0 0 01,181 0 1,181
0 0 0 0 034,038 0 34,038
0 0 0 0 0 0139,625 139,625TotalDESIGN/BUILD
0 0 0 0 03,000 0 3,000
0 0 0 0 03,350 0 3,350
0 0 0 0 0 06,350 6,350TotalALTERNATIVE CONTRACTING INCENTIVES
$161,831Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $243,233415456Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 281 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4154563
District:
County:
OTHER ITS
SR 9A/I-95 EXPRESS OPERATIONS & MAINTENANCE
Roadway ID:
Project Length: 9.640
Lanes Exist:Lanes Improved:Lanes Added:
5
1
5
MIAMI-DADE
LRTP Ref:
87270000
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0173 0 173
TOBD 5 5 0 0 0583 0 593
5 5 0 0 0 0756 766TotalPLANNING AND DESIGN
DDR 0 0 0 0 0654 0 654
DDR 0 0 0 0 0670 0 670
DS 0 0 0 0 01,060 0 1,060
TOBD 0 0 100 100 100638 0 938
TOBD 1,437 682 0 0 026,046 0 28,165
1,437 682 100 100 100 029,068 31,487TotalOPERATIONS
TMBD 0 0 0 0 03,164 0 3,164
0 0 0 0 0 03,164 3,164TotalMAINTENANCE
$35,417Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $243,233415456Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 282 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4154564
District:
County:
WIDEN/RESURFACE EXIST LANES
SR 9A/I-95 FROM NB I-95 EXIT TO NB SR 91(INCLUDES AUX LANE)
Roadway ID:
Project Length: 0.739
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0442 0 442
0 0 0 0 051 0 51
0 0 0 0 0 0493 493TotalPLANNING AND DESIGN
0 0 0 0 098 0 98
0 0 0 0 0 098 98TotalRAILROAD & UTILITIES
0 0 0 0 0525 0 525
0 0 0 0 015 0 15
0 0 0 0 08,992 0 8,992
0 0 0 0 0138 0 138
0 0 0 0 0 09,670 9,670TotalDESIGN/BUILD
$10,261Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $243,233415456Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 283 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4154567
District:
County:
TECHNICAL ASSISTANCE
SR 9A/I-95 EXPRESS LANES ITS OPERATIONS CONSULTANT CONTRACT
Roadway ID:
Project Length: 17.260
Lanes Exist:Lanes Improved:Lanes Added:
9
9
MIAMI-DADE
LRTP Ref:
87270000
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 10 10 10 0 00 0 30
10 10 10 0 0 00 30TotalPLANNING AND DESIGN
TOBD 3,380 3,364 3,350 3,350 3,3500 0 16,794
3,380 3,364 3,350 3,350 3,350 00 16,794TotalOPERATIONS
$16,824Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $243,233415456Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 284 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4154568
District:
County:
OTHER ITS
SR 9A/I-95 EXPRESS OPERATIONS & MAINTENANCE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 4,004 4,004 0 0 09,072 0 17,080
4,004 4,004 0 0 0 09,072 17,080TotalOPERATIONS
$17,080Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $243,233415456Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4154569
District:
County:
OTHER ITS
SR 9A/I-95 EXPRESS FHP ENHANCED ENFORCEMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 5 5 0 0 010 0 20
5 5 0 0 0 010 20TotalCONSTRUCTION
TOBD 0 0 600 600 6000 0 1,800
0 0 600 600 600 00 1,800TotalOPERATIONS
$1,820Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $243,233415456Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 285 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4164871
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE ETDM CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 10163 0 213
DS 150 250 200 200 2002,761 0 3,761
160 260 210 210 210 02,924 3,974TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,974Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,974416487Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4170261
District:
County:
RIGHT OF WAY ACTIVITIES
DISTRICTWIDE R/W ADVANCED ACQ SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BNCA 0 0 0 0 0137 0 137
DIH 10 10 10 10 10120 0 170
Section A1 - Page 286 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4170261
District:
County:
RIGHT OF WAY ACTIVITIES
DISTRICTWIDE R/W ADVANCED ACQ SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 049 0 49
10 10 10 10 10 0306 356TotalRIGHT OF WAY
$356Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $356417026Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177402
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length: 17.260
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0273 0 273
0 0 0 0 0 0273 273TotalDESIGN/BUILD
0 0 0 0 02,149 0 2,149
Section A1 - Page 287 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177402
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length: 17.260
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0199 0 199
0 0 0 0 0 02,348 2,348TotalCAPITAL
$2,621Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177403
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS OPERATIONS HARDWARE/SOFTWARE AND REPLACEMENT EQUIPMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0823 0 823
0 0 0 0 0414 0 414
0 0 0 0 0 01,237 1,237TotalCAPITAL
Section A1 - Page 288 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$1,237Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177404
District:
County:
OTHER ITS
DISTRICTWIDE ITS EQUIPMENT REPLACEMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 07 0 7
0 0 0 0 0424 0 424
0 0 0 0 0 0431 431TotalDESIGN/BUILD
0 0 0 0 01,478 0 1,478
0 0 0 0 010 0 10
0 0 0 0 0 01,488 1,488TotalCAPITAL
$1,919Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 289 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177405
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 079 0 79
0 0 0 0 0 079 79TotalCONSTRUCTION
0 0 0 0 0748 0 748
0 0 0 0 0 0748 748TotalCAPITAL
$827Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177406
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 00 0 0
0 0 0 0 0 00 0TotalPLANNING AND DESIGN
0 0 0 0 0114 0 114
Section A1 - Page 290 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177406
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0114 114TotalDESIGN/BUILD
0 0 0 0 0971 0 971
0 0 0 0 013 0 13
0 0 0 0 0 0984 984TotalCAPITAL
$1,098Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177407
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02 0 2
0 0 0 0 0 02 2TotalPLANNING AND DESIGN
0 0 0 0 07 0 7
Section A1 - Page 291 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177407
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0130 0 130
0 0 0 0 0 0137 137TotalDESIGN/BUILD
0 0 0 0 0453 0 453
0 0 0 0 050 0 50
0 0 0 0 0 0503 503TotalCAPITAL
$642Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177408
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 060 0 60
DS 37 0 0 0 080 0 117
Section A1 - Page 292 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177408
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
37 0 0 0 0 0140 177TotalDESIGN/BUILD
ACNP 0 0 0 0 0591 0 591
DITS 0 0 0 0 031 0 31
DSBD 0 0 0 0 0377 0 377
0 0 0 0 0 0999 999TotalCAPITAL
$1,176Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177409
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 3 0 0 0 03 0 6
DS 0 0 0 0 00 0 0
3 0 0 0 0 03 6TotalPLANNING AND DESIGN
Section A1 - Page 293 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177409
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 02 0 2
DS 40 0 0 0 084 0 124
DSBD 165 0 0 0 0131 0 296
205 0 0 0 0 0217 422TotalDESIGN/BUILD
DITS 0 0 0 0 0673 0 673
DSBD 0 0 0 0 01,345 0 1,345
0 0 0 0 0 02,018 2,018TotalCAPITAL
$2,446Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 294 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4180641
District:
County:
SIDEWALK
DISTRICTWIDE (ADA) COMPLIANCE CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 300 150 150 300 1503,279 0 4,329
300 150 150 300 150 03,279 4,329TotalPLANNING AND DESIGN
$4,329Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,329418064Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4180911
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 968/W FLAGLER ST FROM W OF SR 9/27 AVE TO W 14 AVENUE
Roadway ID:
Project Length: 1.340
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0749 0 749
DIH 0 0 0 0 0167 0 167
DS 0 0 0 0 01,496 0 1,496
LF 0 0 0 0 0186 0 186
0 0 0 0 0 02,598 2,598TotalPLANNING AND DESIGN
DDR 0 0 0 0 0284 0 284
Section A1 - Page 295 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4180911
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 968/W FLAGLER ST FROM W OF SR 9/27 AVE TO W 14 AVENUE
Roadway ID:
Project Length: 1.340
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0164 0 164
DS 0 0 0 0 0396 0 396
LF 0 0 0 0 02,129 0 2,129
0 0 0 0 0 02,973 2,973TotalRIGHT OF WAY
DDR 0 0 0 0 01,882 0 1,882
DIH 0 0 0 0 036 0 36
DS 0 0 0 0 0157 0 157
LF 0 0 0 0 039 0 39
LF 0 0 0 0 0290 0 290
SA 0 0 0 0 09,621 0 9,621
0 0 0 0 0 012,025 12,025TotalCONSTRUCTION
SA 0 400 0 0 00 0 400
0 400 0 0 0 00 400TotalALTERNATIVE CONTRACTING INCENTIVES
$17,996Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $17,996418091Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 296 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4183122
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 968/SW 1ST STREET FROM SW 17TH AVENUE TO E OF SW 6TH AVENUE
Roadway ID:
Project Length: 1.163
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87053001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 025 0 25
DIH 0 0 0 0 0127 0 127
DS 0 0 0 0 027 0 27
DS 0 0 0 0 0167 0 167
EB 0 0 0 0 0377 0 377
SA 0 0 0 0 065 0 65
SU 0 0 0 0 0690 0 690
0 0 0 0 0 01,478 1,478TotalPLANNING AND DESIGN
DIH 0 0 0 0 080 0 80
DS 0 0 0 0 052 0 52
LF 66 0 0 0 00 0 66
66 0 0 0 0 0132 198TotalRIGHT OF WAY
DDR 77 0 0 0 00 0 77
DDR 10,043 0 0 0 00 0 10,043
DIH 71 0 0 0 00 0 71
DS 0 0 0 0 04 0 4
10,191 0 0 0 0 04 10,195TotalCONSTRUCTION
DS 0 400 0 0 00 0 400
Section A1 - Page 297 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4183122
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 968/SW 1ST STREET FROM SW 17TH AVENUE TO E OF SW 6TH AVENUE
Roadway ID:
Project Length: 1.163
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87053001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 400 0 0 0 00 400TotalALTERNATIVE CONTRACTING INCENTIVES
$12,271Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $12,271418312Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4184231
District:
County:
PD&E/EMO STUDY
SR 826/PALMETTO EXPY FROM SR 93/I-75 TO GOLDEN GLADES INTRCHNG
Roadway ID:
Project Length: 9.591
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0562 0 562
0 0 0 0 05,318 0 5,318
0 0 0 0 01,314 0 1,314
0 0 0 0 0 07,194 7,194TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$7,194Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $47,593418423Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 298 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4184232
District:
County:
ADD AUXILIARY LANE(S)
SR 826/PALMETTO EXPY FROM NW 67 AVENUE TO NW 47 AVENUE
Roadway ID:
Project Length: 1.652
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0370 0 370
0 0 0 0 0 0370 370TotalPLANNING AND DESIGN
0 0 0 0 01 0 1
0 0 0 0 0 01 1TotalRAILROAD & UTILITIES
0 0 0 0 0218 0 218
0 0 0 0 02,200 0 2,200
0 0 0 0 039 0 39
0 0 0 0 0 02,457 2,457TotalCONSTRUCTION
$2,828Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $47,593418423Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 299 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4184233
District:
County:
PD&E/EMO STUDY
SR 826/PALMETTO EXPY FROM SR 836 TO SR 93/I-75
Roadway ID:
Project Length: 7.316
Lanes Exist:Lanes Improved:Lanes Added:
3
1
3
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05,334 0 5,334
0 0 0 0 0 05,334 5,334TotalPLANNING AND DESIGN
0 0 0 0 01 0 1
0 0 0 0 09 0 9
0 0 0 0 0 010 10TotalRIGHT OF WAY
0 0 0 0 01,066 0 1,066
0 0 0 0 0 01,066 1,066TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$6,410Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $47,593418423Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 300 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4184235
District:
County:
ADD SPECIAL USE LANE
SR 826/PALMETTO EXPY FROM NW 154 STREET TO NW 17 AVENUE
Roadway ID:
Project Length: 7.143
Lanes Exist:Lanes Improved:Lanes Added:
6
8
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 1,099 0 0 00 0 1,099
DI 0 0 67 0 00 0 67
DI 1,517 1,637 9,563 0 01,000 0 13,717
DIH 40 100 51 0 00 0 191
DIS 0 100 0 0 00 0 100
DIS 0 5,038 0 0 00 0 5,038
DS 0 500 0 0 00 0 500
DSBD 169 0 0 0 00 0 169
DSBD 5,025 0 0 0 00 0 5,025
SIWR 0 3,175 0 0 00 0 3,175
6,751 11,649 9,681 0 0 01,000 29,081TotalRIGHT OF WAY
$29,081Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $47,593418423Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 301 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4184236
District:
County:
PD&E/EMO STUDY
SR 826/PALMETTO EXPY FROM SR 968/W FLAGLER ST TO NW 154 STREET
Roadway ID:
Project Length: 6.517
Lanes Exist:Lanes Improved:Lanes Added:
3
5
2
MIAMI-DADE
LRTP Ref:
87260000
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 800 0 80
DS 0 0 0 0 2,0000 0 2,000
0 0 0 0 2,080 00 2,080TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,080Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $47,593418423Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4188281
District:
County:
BRIDGE-ROUTINE MAINTENANCE
D/W MOVABLE BR AM ASSET MANAGEMENT
Roadway ID:
Project Length: 2.925
Lanes Exist:Lanes Improved:Lanes Added:
4
DIST/ST-WIDE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 0199 0 199
DIH 0 0 0 0 012 0 12
DS 0 0 0 0 0295 0 295
0 0 0 0 0 0506 506TotalCONSTRUCTION
Section A1 - Page 302 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4188281
District:
County:
BRIDGE-ROUTINE MAINTENANCE
D/W MOVABLE BR AM ASSET MANAGEMENT
Roadway ID:
Project Length: 2.925
Lanes Exist:Lanes Improved:Lanes Added:
4
DIST/ST-WIDE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 3,274 3,274 3,274 3,274 3,27433,118 0 49,488
3,274 3,274 3,274 3,274 3,274 033,118 49,488TotalMAINTENANCE
$49,994Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $49,994418828Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4209101
District:
County:
NEW BRIDGE CONSTRUCTION
WEST AVE CONNECTOR BRDG FRM N OF LINCOLN RD TO SOUTH OF 18 STREET
Roadway ID:
Project Length: 0.105
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87000148
6
6-14
SIS or Non-SIS: No
PHASE :
Extra Description:
HPP 0 0 0 0 0561 0 561
SA 0 0 0 0 00 0 0
Section A1 - Page 303 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4209101
District:
County:
NEW BRIDGE CONSTRUCTION
WEST AVE CONNECTOR BRDG FRM N OF LINCOLN RD TO SOUTH OF 18 STREET
Roadway ID:
Project Length: 0.105
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87000148
6
6-14
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 05 0 5
0 0 0 0 0 0566 566TotalPLANNING AND DESIGN
LF 0 0 0 0 01,635 0 1,635
0 0 0 0 0 01,635 1,635TotalRIGHT OF WAY
HPP 0 0 0 0 0689 0 689
0 0 0 0 0 0689 689TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
LF 0 2,552 0 0 00 0 2,552
0 2,552 0 0 0 00 2,552TotalCONSTRUCTION
$5,442Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,442420910Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 304 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4209171
District:
County:
BIKE PATH/TRAIL
OVERTOWN GREENWAY BETWEEN NW 3RD AVE AND NW 7TH AVENUE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01 0 1
0 0 0 0 04 0 4
0 0 0 0 01,080 0 1,080
0 0 0 0 01,057 0 1,057
0 0 0 0 0 02,142 2,142TotalCONSTRUCTION
$2,142Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,095420917Item Number:
RESPONSIBLE AGENCY: CITY OF MIAMI
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4209172
District:
County:
BIKE PATH/TRAIL
OVERTOWN GREENWAY ALONG NW 11 ST
FROM NW 7 AVE TO E OF NW 12 AVE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-56
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 0115 0 115
0 0 0 0 0 0115 115TotalPLANNING AND DESIGN
LF 0 135 0 0 00 0 135
Section A1 - Page 305 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4209172
District:
County:
BIKE PATH/TRAIL
OVERTOWN GREENWAY ALONG NW 11 ST
FROM NW 7 AVE TO E OF NW 12 AVE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-56
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 2 0 0 00 0 2
TALU 0 701 0 0 00 0 701
0 838 0 0 0 00 838TotalCONSTRUCTION
$953Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,095420917Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4213571
District:
County:
ADD TURN LANE(S)
SW 320 STREET FROM SW 187 AVENUE TO FLAGLER AVENUE
Roadway ID:
Project Length: 1.101
Lanes Exist:Lanes Improved:Lanes Added:
2
2
1
MIAMI-DADE
LRTP Ref:
87000044
6
6-14
SIS or Non-SIS: No
PHASE :
Extra Description:
HPP 0 1,795 0 0 00 0 1,795
SA 0 5 0 0 00 0 5
0 1,800 0 0 0 00 1,800TotalCONSTRUCTION
$1,800Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,800421357Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 306 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4217072
District:
County:
ADD SPECIAL USE LANE
SR 93/I-75 ML SYSTEM FROM NW 170 STREET TO S OF HEFT INTERCHANGE
Roadway ID:
Project Length: 1.349
Lanes Exist:Lanes Improved:Lanes Added:
8
8
2
MIAMI-DADE
LRTP Ref:
87075000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 0 067 0 67
DIH 0 0 0 0 039 0 39
DS 0 0 0 0 014 0 14
STED 0 0 0 0 067 0 67
0 0 0 0 0 0187 187TotalPLANNING AND DESIGN
DDR 0 0 0 0 01,549 0 1,549
DDR 0 0 0 0 064 0 64
LF 0 0 0 0 02,821 0 2,821
0 0 0 0 0 04,434 4,434TotalRIGHT OF WAY
ACNP 0 0 0 0 03,582 0 3,582
DDR 31 0 0 0 051 0 82
DI 20 20 0 0 060 0 100
DI 0 0 0 0 0178 0 178
DIH 0 0 0 0 070 0 70
DS 0 0 0 0 0150 0 150
NHPP 0 0 0 0 0806 0 806
PKYI 0 0 0 0 02 0 2
SIWR 1,800 0 20 0 00 0 1,820
Section A1 - Page 307 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4217072
District:
County:
ADD SPECIAL USE LANE
SR 93/I-75 ML SYSTEM FROM NW 170 STREET TO S OF HEFT INTERCHANGE
Roadway ID:
Project Length: 1.349
Lanes Exist:Lanes Improved:Lanes Added:
8
8
2
MIAMI-DADE
LRTP Ref:
87075000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
STED 0 0 0 0 030,969 0 30,969
1,851 20 20 0 0 035,868 37,759TotalDESIGN/BUILD
DDR 0 700 0 0 00 0 700
0 700 0 0 0 00 700TotalALTERNATIVE CONTRACTING INCENTIVES
$43,080Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $207,592421707Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4217078
District:
County:
ADD SPECIAL USE LANE
SR 93/I-75 ML SYSTEM FR S OF HEFT INTCH TO MIAMI/DADE COUNTYLINE
Roadway ID:
Project Length: 0.608
Lanes Exist:Lanes Improved:Lanes Added:
8
4
2
MIAMI-DADE
LRTP Ref:
87075000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 0 0264 0 264
DIH 0 0 0 0 024 0 24
PKYI 0 0 0 0 073 0 73
Section A1 - Page 308 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4217078
District:
County:
ADD SPECIAL USE LANE
SR 93/I-75 ML SYSTEM FR S OF HEFT INTCH TO MIAMI/DADE COUNTYLINE
Roadway ID:
Project Length: 0.608
Lanes Exist:Lanes Improved:Lanes Added:
8
4
2
MIAMI-DADE
LRTP Ref:
87075000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0361 361TotalPLANNING AND DESIGN
ACNP 0 0 0 0 032,130 0 32,130
DDR 21 0 0 0 0101 0 122
DIH 0 0 0 0 033 0 33
DIS 0 0 0 0 01,609 0 1,609
NHPP 0 0 0 0 0541 0 541
PKYI 0 0 0 0 090 0 90
PKYI 0 0 0 0 046,423 0 46,423
STED 0 0 0 0 080,181 0 80,181
21 0 0 0 0 0161,108 161,129TotalDESIGN/BUILD
DDR 0 2,125 0 0 00 0 2,125
0 2,125 0 0 0 00 2,125TotalALTERNATIVE CONTRACTING INCENTIVES
$163,615Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $207,592421707Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 309 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4217079
District:
County:
ITS COMMUNICATION SYSTEM
SR 93/I-75 ML SYSTEM FROM NW 170 STREET TO MIAMI-DADE/BROWARD CL
Roadway ID:
Project Length: 1.957
Lanes Exist:Lanes Improved:Lanes Added:
8
8
MIAMI-DADE
LRTP Ref:
87075000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 01 0 1
PKYI 0 0 0 0 023 0 23
STED 0 0 0 0 015 0 15
0 0 0 0 0 039 39TotalPLANNING AND DESIGN
ACNP 0 0 0 0 0703 0 703
DS 0 0 0 0 05 0 5
PKYI 0 0 0 0 00 0 0
0 0 0 0 0 0708 708TotalDESIGN/BUILD
ACNP 150 0 0 0 00 0 150
150 0 0 0 0 00 150TotalALTERNATIVE CONTRACTING INCENTIVES
$897Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $207,592421707Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 310 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4231261
District:
County:
INTERCHANGE IMPROVEMENT
SR 836/I-95 INTERCHANGE RAMPS FROM NW 17 AVE TO I-95 (MDX)
Roadway ID:
Project Length: 1.953
Lanes Exist:Lanes Improved:Lanes Added:
8
8
MIAMI-DADE
LRTP Ref:
87200000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 02,293 0 2,293
0 0 0 0 0 02,293 2,293TotalPLANNING AND DESIGN
LF 191,900 16,000 0 0 00 0 207,900
191,900 16,000 0 0 0 00 207,900TotalDESIGN/BUILD
$210,193Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $252,098423126Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4231262
District:
County:
INTERCHANGE IMPROVEMENT
SR 9A/I-95 SOUTHBOUND RAMP TO WESTBOUND SR 836
Roadway ID:
Project Length: 0.227
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87270224
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 5,939 00 0 5,939
DIH 0 0 0 966 00 0 966
Section A1 - Page 311 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4231262
District:
County:
INTERCHANGE IMPROVEMENT
SR 9A/I-95 SOUTHBOUND RAMP TO WESTBOUND SR 836
Roadway ID:
Project Length: 0.227
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87270224
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
STED 0 0 0 35,000 00 0 35,000
0 0 0 41,905 0 00 41,905TotalDESIGN/BUILD
$41,905Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $252,098423126Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232511
District:
County:
PD&E/EMO STUDY
SR 25/OKEECHOBEE RD FROM SR 997/KROME AVENUE TO NW 79TH AVENUE
Roadway ID:
Project Length: 9.626
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 06 0 6
0 0 0 0 0 06 6TotalPLANNING AND DESIGN
0 0 0 0 0159 0 159
Section A1 - Page 312 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232511
District:
County:
PD&E/EMO STUDY
SR 25/OKEECHOBEE RD FROM SR 997/KROME AVENUE TO NW 79TH AVENUE
Roadway ID:
Project Length: 9.626
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,590 0 3,590
0 0 0 0 093 0 93
0 0 0 0 0 03,842 3,842TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,848Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $407,093423251Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232512
District:
County:
ADD LANES & RECONSTRUCT
SR 25/OKEECHOBEE RD FROM WEST OF KROME AVENUE
TO EAST OF NW 117 AVENUE
Roadway ID:
Project Length: 4.490
Lanes Exist:Lanes Improved:Lanes Added:
4
4
2
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 3,000 0 0 0 00 0 3,000
DIH 150 0 0 0 00 0 150
3,150 0 0 0 0 00 3,150TotalPLANNING AND DESIGN
DDR 0 1,573 1,550 530 00 0 3,653
DIH 0 65 50 50 00 0 165
Section A1 - Page 313 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232512
District:
County:
ADD LANES & RECONSTRUCT
SR 25/OKEECHOBEE RD FROM WEST OF KROME AVENUE
TO EAST OF NW 117 AVENUE
Roadway ID:
Project Length: 4.490
Lanes Exist:Lanes Improved:Lanes Added:
4
4
2
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 1,638 1,600 580 0 00 3,818TotalRIGHT OF WAY
DI 0 0 0 0 00 17,400 17,400
DIH 0 0 0 0 00 189 189
DS 0 0 0 0 00 2,236 2,236
0 0 0 0 0 19,8250 19,825TotalCONSTRUCTION
$26,793Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $407,093423251Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232513
District:
County:
ADD LANES & RECONSTRUCT
SR 25/OKEECHOBEE RD FROM EAST OF NW 87 AVE TO NW 79 AVE (CONCRETE)
Roadway ID:
Project Length: 0.710
Lanes Exist:Lanes Improved:Lanes Added:
6
6
2
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 3,500 0 0 0 00 0 3,500
DIH 100 0 0 0 00 0 100
3,600 0 0 0 0 00 3,600TotalPLANNING AND DESIGN
Section A1 - Page 314 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232513
District:
County:
ADD LANES & RECONSTRUCT
SR 25/OKEECHOBEE RD FROM EAST OF NW 87 AVE TO NW 79 AVE (CONCRETE)
Roadway ID:
Project Length: 0.710
Lanes Exist:Lanes Improved:Lanes Added:
6
6
2
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 00 124 124
DI 0 0 0 0 00 7,652 7,652
DIH 0 0 0 0 1100 70 180
DS 0 0 0 0 00 4,444 4,444
DSBD 0 0 0 0 6,5560 0 6,556
0 0 0 0 6,666 12,2900 18,956TotalRIGHT OF WAY
ACNP 0 0 0 0 00 23,100 23,100
DI 0 0 0 0 00 2,000 2,000
DIH 0 0 0 0 00 260 260
DS 0 0 0 0 00 2,996 2,996
0 0 0 0 0 28,3560 28,356TotalCONSTRUCTION
$50,912Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $407,093423251Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 315 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232514
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 25/OKEECHOBEE RD FROM E OF NW 116 WAY TO E OF NW 87 AVE(CONCRETE)
Roadway ID:
Project Length: 1.194
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 013,000 0 13,000
0 0 0 0 0100 0 100
0 0 0 0 0 013,100 13,100TotalPLANNING AND DESIGN
0 0 0 0 07,250 0 7,250
0 0 0 0 01,610 34,814 36,424
0 0 0 0 0 34,8148,860 43,674TotalRIGHT OF WAY
0 0 0 0 00 170,700 170,700
0 0 0 0 00 23,844 23,844
0 0 0 0 0 194,5440 194,544TotalCONSTRUCTION
$251,318Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $407,093423251Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 316 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232515
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 25/OKEECHOBEE RD FROM E OF NW 107 AVE TO E OF NW 116 WAY(CNCRETE)
Roadway ID:
Project Length: 1.836
Lanes Exist:Lanes Improved:Lanes Added:
6
6
2
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 05,200 0 5,200
DIH 0 0 0 0 0150 0 150
0 0 0 0 0 05,350 5,350TotalPLANNING AND DESIGN
DDR 0 0 0 999 3480 450 1,797
DIH 0 0 0 100 1000 259 459
DSBD 0 0 0 0 6,8660 0 6,866
SU 0 0 0 6,244 00 4,276 10,520
0 0 0 7,343 7,314 4,9850 19,642TotalRIGHT OF WAY
$24,992Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $407,093423251Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 317 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4232516
District:
County:
ADD LANES & REHABILITATE PVMNT
SR 25/OKEECHOBEE RD FROM E OF NW 117 AVE TO E OF NW 107 AVE(CNCRETE)
Roadway ID:
Project Length: 2.507
Lanes Exist:Lanes Improved:Lanes Added:
4
6
2
MIAMI-DADE
LRTP Ref:
87090000
6
6-32
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 03,500 0 3,500
DIH 0 0 0 0 0100 0 100
0 0 0 0 0 03,600 3,600TotalPLANNING AND DESIGN
DDR 0 1,621 860 240 00 0 2,721
DIH 0 32 30 20 00 0 82
0 1,653 890 260 0 00 2,803TotalRIGHT OF WAY
ACNP 0 0 0 0 00 36,301 36,301
DI 0 0 0 0 00 3,000 3,000
DIH 0 0 0 0 00 297 297
DS 0 0 0 0 00 3,229 3,229
0 0 0 0 0 42,8270 42,827TotalCONSTRUCTION
$49,230Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $407,093423251Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 318 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4234481
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE ROW MONUMENTATION CONSULTANT CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 0 0 0 039 0 49
DS 0 0 0 0 01,494 0 1,494
10 0 0 0 0 01,533 1,543TotalPLANNING AND DESIGN
$1,543Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,543423448Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4234521
District:
County:
LANDSCAPING
SR 9A/I-95 FROM NW 8TH STREET TO NW 17TH STREET
Roadway ID:
Project Length: 0.750
Lanes Exist:Lanes Improved:Lanes Added:
10
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0210 0 210
0 0 0 0 0 0210 210TotalPLANNING AND DESIGN
0 0 0 0 055 0 55
0 0 0 0 01,368 0 1,368
Section A1 - Page 319 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4234521
District:
County:
LANDSCAPING
SR 9A/I-95 FROM NW 8TH STREET TO NW 17TH STREET
Roadway ID:
Project Length: 0.750
Lanes Exist:Lanes Improved:Lanes Added:
10
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 065 0 65
0 0 0 0 0 01,488 1,488TotalCONSTRUCTION
$1,698Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,781423452Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4234522
District:
County:
LANDSCAPING
SR 9A/I-95 FROM NW 32ND STREET TO NW 47TH TERRACE
Roadway ID:
Project Length: 0.855
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0168 0 168
0 0 0 0 0 0168 168TotalPLANNING AND DESIGN
0 0 0 0 0370 0 370
Section A1 - Page 320 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4234522
District:
County:
LANDSCAPING
SR 9A/I-95 FROM NW 32ND STREET TO NW 47TH TERRACE
Roadway ID:
Project Length: 0.855
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,749 0 1,749
0 0 0 0 03 0 3
0 0 0 0 0 02,122 2,122TotalCONSTRUCTION
$2,290Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,781423452Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4234523
District:
County:
LANDSCAPING
SR 9A/I-95 FROM NW 155TH STREET TO NW 170TH STREET
Roadway ID:
Project Length: 1.060
Lanes Exist:Lanes Improved:Lanes Added:
10
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 225 028 0 253
DIH 0 0 0 30 06 0 36
DS 0 0 0 0 0187 0 187
Section A1 - Page 321 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4234523
District:
County:
LANDSCAPING
SR 9A/I-95 FROM NW 155TH STREET TO NW 170TH STREET
Roadway ID:
Project Length: 1.060
Lanes Exist:Lanes Improved:Lanes Added:
10
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 255 0 0221 476TotalPLANNING AND DESIGN
DDR 0 0 0 0 00 123 123
DIH 0 0 0 0 00 70 70
SA 0 0 0 0 00 5,124 5,124
0 0 0 0 0 5,3170 5,317TotalCONSTRUCTION
$5,793Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,781423452Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4244071
District:
County:
BRIDGE REPLACEMENT
SR 968/SW 1ST STREET AT MIAMI RIVER (BRIDGE #870660)
Roadway ID:
Project Length: 0.418
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87053001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSB 0 0 0 0 03,325 0 3,325
DDR 0 0 0 0 019 0 19
DIH 0 0 0 0 0141 0 141
Section A1 - Page 322 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4244071
District:
County:
BRIDGE REPLACEMENT
SR 968/SW 1ST STREET AT MIAMI RIVER (BRIDGE #870660)
Roadway ID:
Project Length: 0.418
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87053001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 05 0 5
SABR 0 0 0 0 0789 0 789
0 0 0 0 0 04,279 4,279TotalPLANNING AND DESIGN
ACBR 4,460 3,000 0 0 00 0 7,460
ACSA 898 0 0 0 00 0 898
ACSB 1,200 0 0 0 0840 0 2,040
DIH 50 40 0 0 060 0 150
DS 600 200 0 0 0443 0 1,243
DS 0 5 0 0 00 0 5
EBBP 0 0 0 0 015,000 0 15,000
LF 0 1,000 0 0 00 0 1,000
SA 540 0 0 0 00 0 540
7,748 4,245 0 0 0 016,343 28,336TotalRIGHT OF WAY
BRT 0 0 0 0 01,179 0 1,179
DIH 0 0 0 0 0145 0 145
DS 0 0 0 0 07 0 7
0 0 0 0 0 01,331 1,331TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
ACBR 0 74,226 5,635 0 00 0 79,861
Section A1 - Page 323 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4244071
District:
County:
BRIDGE REPLACEMENT
SR 968/SW 1ST STREET AT MIAMI RIVER (BRIDGE #870660)
Roadway ID:
Project Length: 0.418
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87053001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRP 0 0 110 0 00 0 110
BRRP 0 0 0 0 07 0 7
0 74,226 5,745 0 0 07 79,978TotalCONSTRUCTION
$113,924Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $113,924424407Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4249331
District:
County:
TOLL COLLECTION
I-95 EXPRESS TOLL OPERATIONS DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DSBD 0 0 0 0 0678 0 678
TOBD 1,325 1,325 1,325 1,325 1,3258,910 0 15,535
1,325 1,325 1,325 1,325 1,325 09,588 16,213TotalOPERATIONS
$16,213Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,213424933Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 324 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4251441
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE GENERAL CONSULTANT FOR PLANS REVIEW & DESIGN SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 06,432 0 6,432
0 0 0 0 0 06,432 6,432TotalPLANNING AND DESIGN
$6,432Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,426425144Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4252161
District:
County:
INTERSECTION IMPROVEMENT
SR 9A/I-95 AT SR 860/MIA GDNS DRIVE (INSTALL RAMP SHOULDER)
Roadway ID:
Project Length: 0.232
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0109 0 109
0 0 0 0 0 0109 109TotalPLANNING AND DESIGN
0 0 0 0 09 0 9
0 0 0 0 0333 0 333
Section A1 - Page 325 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4252161
District:
County:
INTERSECTION IMPROVEMENT
SR 9A/I-95 AT SR 860/MIA GDNS DRIVE (INSTALL RAMP SHOULDER)
Roadway ID:
Project Length: 0.232
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01 0 1
0 0 0 0 0 0343 343TotalCONSTRUCTION
$452Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,429425216Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4252162
District:
County:
RESURFACING
SR 9A/I-95 RAMPS AT SR 860 MIAMI GARDENS DRIVE
Roadway ID:
Project Length: 0.743
Lanes Exist:Lanes Improved:Lanes Added:
1
1
MIAMI-DADE
LRTP Ref:
87270215
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 031 0 31
DS 0 0 0 0 0220 0 220
0 0 0 0 0 0251 251TotalPLANNING AND DESIGN
Section A1 - Page 326 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4252162
District:
County:
RESURFACING
SR 9A/I-95 RAMPS AT SR 860 MIAMI GARDENS DRIVE
Roadway ID:
Project Length: 0.743
Lanes Exist:Lanes Improved:Lanes Added:
1
1
MIAMI-DADE
LRTP Ref:
87270215
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 1,542 0 0 0 00 0 1,542
DIH 51 0 0 0 00 0 51
DS 133 0 0 0 00 0 133
1,726 0 0 0 0 00 1,726TotalCONSTRUCTION
$1,977Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,429425216Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4252711
District:
County:
SAFETY PROJECT
SR 968/FLAGLER ST FROM SW 72 AVENUE TO SW 42 AVENUE
Roadway ID:
Project Length: 3.048
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0363 0 363
0 0 0 0 0 0363 363TotalPLANNING AND DESIGN
Section A1 - Page 327 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4252711
District:
County:
SAFETY PROJECT
SR 968/FLAGLER ST FROM SW 72 AVENUE TO SW 42 AVENUE
Roadway ID:
Project Length: 3.048
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01 0 1
0 0 0 0 04 0 4
0 0 0 0 0 05 5TotalRIGHT OF WAY
0 0 0 0 0135 0 135
0 0 0 0 01,107 0 1,107
0 0 0 0 01 0 1
0 0 0 0 0 01,243 1,243TotalCONSTRUCTION
$1,611Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,247425271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 328 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4252712
District:
County:
SAFETY PROJECT
SR 968/FLAGLER ST FROM SW 42 AVENUE TO SW 27 AVENUE
Roadway ID:
Project Length: 1.539
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0181 0 181
0 0 0 0 0 0181 181TotalPLANNING AND DESIGN
0 0 0 0 02 0 2
0 0 0 0 0 02 2TotalRAILROAD & UTILITIES
0 0 0 0 016 0 16
0 0 0 0 0728 0 728
0 0 0 0 046 0 46
0 0 0 0 0 0790 790TotalCONSTRUCTION
$973Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,247425271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 329 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4252713
District:
County:
RESURFACING
SR 968/FLAGLER ST FROM W OF 69 AVENUE TO W OF SR 9/NW 27TH AVE
Roadway ID:
Project Length: 4.267
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0814 0 814
DIH 0 0 0 0 038 0 38
DS 25 0 0 0 0327 0 352
25 0 0 0 0 01,179 1,204TotalPLANNING AND DESIGN
DDR 10 0 0 0 00 0 10
LF 69 0 0 0 00 0 69
79 0 0 0 0 00 79TotalRAILROAD & UTILITIES
DDR 2,957 0 0 0 00 0 2,957
DIH 119 0 0 0 00 0 119
DS 785 369 0 0 00 0 1,154
3,861 369 0 0 0 00 4,230TotalCONSTRUCTION
DDR 0 150 0 0 00 0 150
0 150 0 0 0 00 150TotalALTERNATIVE CONTRACTING INCENTIVES
$5,663Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,247425271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 330 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4254021
District:
County:
LANDSCAPING
DISTRICTWIDE LANDSCAPE DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 20 20 20 20 20100 0 200
DS 400 300 600 400 5001,986 0 4,186
420 320 620 420 520 02,086 4,386TotalPLANNING AND DESIGN
$4,386Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,386425402Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4255981
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 7/NW 7 AVENUE FROM NW 8 STREET TO NW 36 STREET
Roadway ID:
Project Length: 2.040
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87140000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0320 0 320
DIH 0 0 0 0 0733 0 733
DS 0 0 0 0 0243 0 243
0 0 0 0 0 01,296 1,296TotalPLANNING AND DESIGN
DDR 0 0 0 0 01 0 1
Section A1 - Page 331 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4255981
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 7/NW 7 AVENUE FROM NW 8 STREET TO NW 36 STREET
Roadway ID:
Project Length: 2.040
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87140000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 026 0 26
DS 0 0 0 0 046 0 46
LF 0 0 0 0 07,106 0 7,106
0 0 0 0 0 07,179 7,179TotalRIGHT OF WAY
ACSA 0 0 0 0 0473 0 473
DDR 0 0 0 0 0155 0 155
DDR 0 0 0 0 0182 0 182
DS 0 0 0 0 06 0 6
EB 0 0 0 0 02,116 0 2,116
LF 0 0 0 0 0927 0 927
SA 0 0 0 0 015,676 0 15,676
0 0 0 0 0 019,535 19,535TotalCONSTRUCTION
SA 0 1,200 0 0 00 0 1,200
0 1,200 0 0 0 00 1,200TotalALTERNATIVE CONTRACTING INCENTIVES
$29,210Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $29,361425598Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 332 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4255982
District:
County:
INTERSECTION IMPROVEMENT
SR 7/NW 7TH AVE FROM NW 6TH STREET TO NW 32ND STREET
Roadway ID:
Project Length: 1.882
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 077 0 77
0 0 0 0 0 077 77TotalPLANNING AND DESIGN
0 0 0 0 026 0 26
0 0 0 0 045 0 45
0 0 0 0 03 0 3
0 0 0 0 0 074 74TotalCONSTRUCTION
$151Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $29,361425598Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4256371
District:
County:
RESURFACING
SR 7/SR 826/ SR-9A GOLDEN GLADES INTERCHANGE VARIOUS RAMPS
Roadway ID:
Project Length: 1.613
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87140001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0710 0 710
Section A1 - Page 333 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4256371
District:
County:
RESURFACING
SR 7/SR 826/ SR-9A GOLDEN GLADES INTERCHANGE VARIOUS RAMPS
Roadway ID:
Project Length: 1.613
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87140001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0304 0 304
0 0 0 0 0 01,014 1,014TotalPLANNING AND DESIGN
0 0 0 0 039 0 39
0 0 0 0 02,836 0 2,836
0 0 0 0 02 0 2
0 0 0 0 0 02,877 2,877TotalCONSTRUCTION
$3,891Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,148425637Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4256372
District:
County:
RESURFACING
SR 7/US 441 SB FROM NW 2ND AVE TO BRIDGE # 870045 (TURNPIKE CONNECTOR)
Roadway ID:
Project Length: 0.591
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 20 0 0 0 00 0 20
Section A1 - Page 334 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4256372
District:
County:
RESURFACING
SR 7/US 441 SB FROM NW 2ND AVE TO BRIDGE # 870045 (TURNPIKE CONNECTOR)
Roadway ID:
Project Length: 0.591
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 150 0 0 0 00 0 150
170 0 0 0 0 00 170TotalPLANNING AND DESIGN
DDR 0 0 146 0 00 0 146
DIH 0 0 11 0 00 0 11
NHRE 0 0 550 0 00 0 550
0 0 707 0 0 00 707TotalCONSTRUCTION
$877Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,148425637Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4256373
District:
County:
RESURFACING - RIDE ONLY
SR 7/US 441 SB FROM NORTH OF NW 15900 BLOCK
TO NORTH OF NW 16000 BLOCK
Roadway ID:
Project Length: 0.150
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 040 0 40
Section A1 - Page 335 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4256373
District:
County:
RESURFACING - RIDE ONLY
SR 7/US 441 SB FROM NORTH OF NW 15900 BLOCK
TO NORTH OF NW 16000 BLOCK
Roadway ID:
Project Length: 0.150
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 06 0 6
0 0 0 0 0 046 46TotalPLANNING AND DESIGN
LF 6 0 0 0 00 0 6
6 0 0 0 0 00 6TotalRAILROAD & UTILITIES
DIH 5 0 0 0 00 0 5
DS 323 0 0 0 00 0 323
328 0 0 0 0 00 328TotalCONSTRUCTION
$380Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,148425637Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258572
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL MIAMI LAKES ELEM SCHOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 03 0 3
Section A1 - Page 336 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258572
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL MIAMI LAKES ELEM SCHOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 0 0 0 0 030 0 30
0 0 0 0 0 033 33TotalPLANNING AND DESIGN
SA 28 0 0 0 00 0 28
TALU 170 0 0 0 00 0 170
198 0 0 0 0 00 198TotalCONSTRUCTION
$231Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,074425857Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258653
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI-DADE COUNTYWDE DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 029 0 29
0 0 0 0 0 029 29TotalPLANNING AND DESIGN
0 0 0 0 01 0 1
Section A1 - Page 337 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258653
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI-DADE COUNTYWDE DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 01 1TotalRIGHT OF WAY
0 0 0 0 0267 0 267
0 0 0 0 0 0267 267TotalCONSTRUCTION
$297Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,888425865Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258655
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI-DADE COUNTYWDE DRAINAGE PUSH BUTTON CONTRACTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 011 0 11
0 0 0 0 0 011 11TotalPLANNING AND DESIGN
0 0 0 0 01,093 0 1,093
0 0 0 0 0 01,093 1,093TotalCONSTRUCTION
Section A1 - Page 338 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$1,104Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,888425865Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258657
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI-DADE COUNTYWDE DRAINAGE PUSH BUTTON CONTRACTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
0 0 0 0 0 010 10TotalPLANNING AND DESIGN
DDR 152 0 0 0 0849 0 1,001
DIH 0 0 0 0 0101 0 101
152 0 0 0 0 0950 1,102TotalCONSTRUCTION
$1,112Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,888425865Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 339 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258659
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI-DADE COUNTYWD DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03 0 3
0 0 0 0 0 03 3TotalPLANNING AND DESIGN
0 0 0 0 0441 0 441
0 0 0 0 0 0441 441TotalCONSTRUCTION
$444Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,888425865Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4259791
District:
County:
RESURFACING
SR 948/NW 36TH ST FROM W OF LEE DRIVE TO E OF OKEECHOBEE ROAD
Roadway ID:
Project Length: 0.718
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0136 0 136
0 0 0 0 0 0136 136TotalPLANNING AND DESIGN
0 0 0 0 013 0 13
Section A1 - Page 340 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4259791
District:
County:
RESURFACING
SR 948/NW 36TH ST FROM W OF LEE DRIVE TO E OF OKEECHOBEE ROAD
Roadway ID:
Project Length: 0.718
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03 0 3
0 0 0 0 02 0 2
0 0 0 0 0 018 18TotalRIGHT OF WAY
0 0 0 0 01,431 0 1,431
0 0 0 0 0 01,431 1,431TotalDESIGN/BUILD
$1,585Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,965425979Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4259792
District:
County:
RESURFACING
SR 25/OKEECHOBEE RD FROM W OF SE 7 AVENUE TO N OF NW 36 STREET
Roadway ID:
Project Length: 1.506
Lanes Exist:Lanes Improved:Lanes Added:
1
1
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSA 0 0 0 0 0525 0 525
DIH 0 0 0 0 035 0 35
Section A1 - Page 341 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4259792
District:
County:
RESURFACING
SR 25/OKEECHOBEE RD FROM W OF SE 7 AVENUE TO N OF NW 36 STREET
Roadway ID:
Project Length: 1.506
Lanes Exist:Lanes Improved:Lanes Added:
1
1
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 032 0 32
0 0 0 0 0 0592 592TotalPLANNING AND DESIGN
DDR 0 2,048 0 0 00 0 2,048
HSP 0 1,675 0 0 00 0 1,675
SA 0 65 0 0 00 0 65
0 3,788 0 0 0 00 3,788TotalCONSTRUCTION
$4,380Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,965425979Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 342 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4261131
District:
County:
BRIDGE REPLACEMENT
NW 34 AVENUE OVER COMFORT CANAL (CITY OF MIAMI)
Roadway ID:
Project Length: 0.006
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87000443
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSB 0 0 0 0 0544 0 544
0 0 0 0 0 0544 544TotalPLANNING AND DESIGN
ACBR 0 0 100 0 00 0 100
SA 191 0 0 0 00 0 191
191 0 100 0 0 00 291TotalRIGHT OF WAY
ACBR 0 0 1,211 0 00 0 1,211
SA 0 0 353 0 00 0 353
0 0 1,564 0 0 00 1,564TotalCONSTRUCTION
$2,399Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,399426113Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 343 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273691
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM SW 296 STREET TO S OF SW 232 STREET
Roadway ID:
Project Length: 3.674
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0381 0 381
DIH 0 0 0 0 0101 0 101
DS 0 0 0 0 0209 0 209
GMR 0 0 0 0 03,095 0 3,095
0 0 0 0 0 03,786 3,786TotalPLANNING AND DESIGN
DDR 0 11,710 6,498 0 00 0 18,208
DDR 0 42 0 0 00 0 42
DI 5,906 0 0 0 00 0 5,906
DIH 260 500 400 0 00 0 1,160
DS 0 1,000 554 0 00 0 1,554
DSBD 19,627 0 0 0 00 0 19,627
DSBD 500 0 0 0 00 0 500
26,293 13,252 7,452 0 0 00 46,997TotalRIGHT OF WAY
ACNP 0 0 36,766 0 00 0 36,766
DDR 0 0 3,030 0 00 0 3,030
0 0 39,796 0 0 00 39,796TotalCONSTRUCTION
ACNP 0 0 0 0 00 820 820
0 0 0 0 0 8200 820TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 344 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$91,399Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $203,382427369Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273692
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM SW 232 STREET TO S OF SW 184TH ST/EUREKA DR
Roadway ID:
Project Length: 3.251
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0174 0 174
DIH 0 0 0 0 084 0 84
DS 0 0 0 0 0142 0 142
GMR 0 0 0 0 02,349 0 2,349
0 0 0 0 0 02,749 2,749TotalPLANNING AND DESIGN
ACNP 0 5,000 0 0 00 0 5,000
ACNP 0 800 0 0 00 0 800
BNIR 4,000 0 0 0 01,942 0 5,942
DDR 200 0 0 0 0100 0 300
DDR 0 980 0 0 030 0 1,010
DI 0 0 0 0 0250 0 250
DIH 50 150 0 0 020 0 220
DS 0 500 0 0 0735 0 1,235
DSBD 15,767 0 0 0 00 0 15,767
DSBD 400 0 0 0 00 0 400
20,417 7,430 0 0 0 03,077 30,924TotalRIGHT OF WAY
Section A1 - Page 345 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273692
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM SW 232 STREET TO S OF SW 184TH ST/EUREKA DR
Roadway ID:
Project Length: 3.251
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 27,238 3,442 0 00 0 30,680
DI 0 0 216 0 00 0 216
DS 0 2 0 0 00 0 2
HSP 0 450 65 0 00 0 515
0 27,690 3,723 0 0 00 31,413TotalCONSTRUCTION
DSBD 0 0 0 0 6800 0 680
0 0 0 0 680 00 680TotalALTERNATIVE CONTRACTING INCENTIVES
$65,766Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $203,382427369Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273693
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM SW 184 STREET TO SOUTH OF SW 136 STREET
Roadway ID:
Project Length: 3.039
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 01,765 0 1,765
Section A1 - Page 346 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273693
District:
County:
ADD LANES & RECONSTRUCT
SR 997/KROME AVENUE FROM SW 184 STREET TO SOUTH OF SW 136 STREET
Roadway ID:
Project Length: 3.039
Lanes Exist:Lanes Improved:Lanes Added:
2
2
2
MIAMI-DADE
LRTP Ref:
87150000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 087 0 87
DS 0 0 0 0 0164 0 164
0 0 0 0 0 02,016 2,016TotalPLANNING AND DESIGN
BNIR 3,919 0 0 0 01,697 0 5,616
DDR 0 252 0 0 00 0 252
DI 0 0 0 0 020 0 20
DIH 50 150 0 0 0100 0 300
DS 0 2,888 0 0 01,065 0 3,953
DS 0 50 0 0 0275 0 325
DSBD 3,791 0 0 0 00 0 3,791
DSBD 250 0 0 0 00 0 250
8,010 3,340 0 0 0 03,157 14,507TotalRIGHT OF WAY
ACNP 0 21,352 2,901 0 00 0 24,253
DDR 0 0 162 0 00 0 162
DIS 0 2,235 0 0 00 0 2,235
0 23,587 3,063 0 0 00 26,650TotalCONSTRUCTION
DSBD 0 0 0 0 6800 0 680
0 0 0 0 680 00 680TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 347 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$43,853Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $203,382427369Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273694
District:
County:
DRAINAGE IMPROVEMENTS
SR 997/KROME AVENUE RELOCATE & RECONSTRUCT CONTROL STRUCTURE
AT C-102
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 26 0 0 0 00 0 26
DSBD 2,338 0 0 0 00 0 2,338
2,364 0 0 0 0 00 2,364TotalCONSTRUCTION
$2,364Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $203,382427369Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4274521
District:
County:
RESURFACING
SR 934/NW/NE 79 ST FROM NW 14 AVENUE TO NORTH BAYSHORE DRIVE
Roadway ID:
Project Length: 2.956
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87080000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0203 0 203
0 0 0 0 01,236 0 1,236
0 0 0 0 0 01,439 1,439TotalPLANNING AND DESIGN
Section A1 - Page 348 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4274521
District:
County:
RESURFACING
SR 934/NW/NE 79 ST FROM NW 14 AVENUE TO NORTH BAYSHORE DRIVE
Roadway ID:
Project Length: 2.956
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87080000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 076 0 76
0 0 0 0 020 0 20
0 0 0 0 0 096 96TotalRAILROAD & UTILITIES
0 0 0 0 068 0 68
0 0 0 0 09,401 0 9,401
0 0 0 0 091 0 91
0 0 0 0 0 09,560 9,560TotalCONSTRUCTION
0 0 0 0 0300 0 300
0 0 0 0 0 0300 300TotalALTERNATIVE CONTRACTING INCENTIVES
$11,395Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,957427452Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 349 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4274522
District:
County:
LANDSCAPING
SR 934/NW/NE 79 ST FROM NW 14 AVENUE TO NORTH BAYSHORE DRIVE
Roadway ID:
Project Length: 2.977
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87080000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 071 0 71
DIH 0 0 0 0 015 0 15
DS 0 0 0 0 02 0 2
0 0 0 0 0 088 88TotalPLANNING AND DESIGN
DS 0 0 0 0 05 0 5
0 0 0 0 0 05 5TotalRAILROAD & UTILITIES
DDR 92 0 0 0 0343 0 435
DIH 0 0 0 0 034 0 34
92 0 0 0 0 0377 469TotalCONSTRUCTION
$562Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,957427452Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 350 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276471
District:
County:
PD&E/EMO STUDY
SR 90/SW 7 STREET FROM SW 2ND AVENUE TO SW 5 AVENUE
Roadway ID:
Project Length: 0.628
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04 0 4
0 0 0 0 0 04 4TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$4Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4427647Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276511
District:
County:
RESURFACING
SR 986/SUNSET DR FROM SW 109 PLACE TO SW 87 AVENUE
Roadway ID:
Project Length: 2.321
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87055000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0370 0 370
0 0 0 0 0 0370 370TotalPLANNING AND DESIGN
0 0 0 0 01 0 1
0 0 0 0 026 0 26
0 0 0 0 020 0 20
0 0 0 0 0 047 47TotalRIGHT OF WAY
Section A1 - Page 351 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276511
District:
County:
RESURFACING
SR 986/SUNSET DR FROM SW 109 PLACE TO SW 87 AVENUE
Roadway ID:
Project Length: 2.321
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87055000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 022 0 22
0 0 0 0 02,979 0 2,979
0 0 0 0 0518 0 518
0 0 0 0 0 03,519 3,519TotalCONSTRUCTION
$3,936Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,542427651Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276512
District:
County:
RESURFACING
SR 986/SW 72 ST FROM W OF SW 87 CT TO E OF SW 84 PL & AT SR 973/SW 87 AVE
Roadway ID:
Project Length: 0.374
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87047000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 035 0 35
DS 0 0 0 0 0318 0 318
0 0 0 0 0 0353 353TotalPLANNING AND DESIGN
DIH 0 0 0 0 09 0 9
Section A1 - Page 352 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276512
District:
County:
RESURFACING
SR 986/SW 72 ST FROM W OF SW 87 CT TO E OF SW 84 PL & AT SR 973/SW 87 AVE
Roadway ID:
Project Length: 0.374
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87047000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 025 0 25
0 0 0 0 0 034 34TotalRIGHT OF WAY
DDR 0 157 0 0 00 0 157
DIH 0 59 0 0 00 0 59
SA 0 1,003 0 0 00 0 1,003
0 1,219 0 0 0 00 1,219TotalCONSTRUCTION
$1,606Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,542427651Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4278491
District:
County:
RIGHT OF WAY ACTIVITIES
D/W PROPERTY MGMT ASBESTOS CONSULT ABATEMNT AND DEMOLITION SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 5 5 5 5 5199 0 224
Section A1 - Page 353 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4278491
District:
County:
RIGHT OF WAY ACTIVITIES
D/W PROPERTY MGMT ASBESTOS CONSULT ABATEMNT AND DEMOLITION SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 25 25 25 25 25106 0 231
30 30 30 30 30 0305 455TotalRIGHT OF WAY
$455Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $455427849Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282781
District:
County:
INTERSECTION IMPROVEMENT
SR 944/NW 54 STREET FROM SR 7/NW 7 AVENUE TO NW 6TH COURT
Roadway ID:
Project Length: 0.057
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87250000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 051 0 51
0 0 0 0 0105 0 105
0 0 0 0 0 0156 156TotalPLANNING AND DESIGN
0 0 0 0 04 0 4
0 0 0 0 0321 0 321
0 0 0 0 05 0 5
Section A1 - Page 354 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282781
District:
County:
INTERSECTION IMPROVEMENT
SR 944/NW 54 STREET FROM SR 7/NW 7 AVENUE TO NW 6TH COURT
Roadway ID:
Project Length: 0.057
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87250000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0330 330TotalCONSTRUCTION
$486Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,523428278Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282782
District:
County:
RESURFACING
SR 944/NW/NE 54TH ST FROM E OF NW 7 AVENUE TO BISCAYNE BOULEVARD
Roadway ID:
Project Length: 1.325
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87250000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSA 0 0 0 0 0405 0 405
DIH 0 0 0 0 025 0 25
DS 0 0 0 0 011 0 11
0 0 0 0 0 0441 441TotalPLANNING AND DESIGN
DDR 0 10 0 0 00 0 10
DIH 0 0 0 0 012 0 12
DS 100 0 0 0 0104 0 204
Section A1 - Page 355 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282782
District:
County:
RESURFACING
SR 944/NW/NE 54TH ST FROM E OF NW 7 AVENUE TO BISCAYNE BOULEVARD
Roadway ID:
Project Length: 1.325
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87250000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 05 0 5
100 10 0 0 0 0121 231TotalRIGHT OF WAY
DIH 0 104 0 0 00 0 104
DS 0 1,177 0 0 00 0 1,177
SA 0 1,457 0 0 00 0 1,457
0 2,738 0 0 0 00 2,738TotalCONSTRUCTION
$3,410Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,523428278Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282783
District:
County:
INTERSECTION IMPROVEMENT
SR 944/NW/NE 54 STREET FROM NW 6TH COURT TO NE 1ST AVENUE
Roadway ID:
Project Length: 0.818
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87250000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
Section A1 - Page 356 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282783
District:
County:
INTERSECTION IMPROVEMENT
SR 944/NW/NE 54 STREET FROM NW 6TH COURT TO NE 1ST AVENUE
Roadway ID:
Project Length: 0.818
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87250000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 07 0 7
HSP 0 0 0 0 0109 0 109
0 0 0 0 0 0126 126TotalPLANNING AND DESIGN
DIH 0 0 0 0 06 0 6
DS 0 0 0 0 039 0 39
0 0 0 0 0 045 45TotalRIGHT OF WAY
DIH 0 21 0 0 00 0 21
DS 0 16 0 0 00 0 16
HSP 0 370 49 0 00 0 419
0 407 49 0 0 00 456TotalCONSTRUCTION
$627Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,523428278Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 357 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283581
District:
County:
INTERCHANGE RAMP (NEW)
SR 826/PALMETTO EXPY - SR 826 EASTBOUND RAMP TO SR 9A/I-95 NORTHBOUND
Roadway ID:
Project Length: 4.114
Lanes Exist:Lanes Improved:Lanes Added:
4
8
MIAMI-DADE
LRTP Ref:
87260000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 0632 0 632
DI 0 0 0 0 04,321 0 4,321
DIH 0 0 0 0 01 0 1
DIS 2,630 0 0 0 00 0 2,630
DS 0 0 0 0 091 0 91
PKYI 0 0 0 0 0616 0 616
PKYI 0 0 0 0 035 0 35
2,630 0 0 0 0 05,696 8,326TotalPLANNING AND DESIGN
BNIR 0 0 0 0 05,879 0 5,879
DDR 0 0 0 0 026 0 26
DI 0 0 570 0 07,195 0 7,765
DI 0 0 0 0 0500 0 500
DIH 0 0 0 0 082 0 82
DIS 0 4,550 0 0 00 0 4,550
DS 0 0 0 0 0110 0 110
DSBD 6,075 0 0 0 00 0 6,075
PKYI 0 0 0 0 01 0 1
6,075 4,550 570 0 0 013,793 24,988TotalRIGHT OF WAY
Section A1 - Page 358 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283581
District:
County:
INTERCHANGE RAMP (NEW)
SR 826/PALMETTO EXPY - SR 826 EASTBOUND RAMP TO SR 9A/I-95 NORTHBOUND
Roadway ID:
Project Length: 4.114
Lanes Exist:Lanes Improved:Lanes Added:
4
8
MIAMI-DADE
LRTP Ref:
87260000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 050 0 50
DIH 0 0 0 0 0171 0 171
EBNH 0 0 0 0 02,462 0 2,462
NHPP 0 0 0 0 01,039 0 1,039
PKYI 0 0 0 0 0236 0 236
0 0 0 0 0 03,958 3,958TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
DDR 0 0 0 13,362 00 0 13,362
DIH 0 0 930 0 00 0 930
DS 0 0 0 1,909 00 0 1,909
DSBD 0 0 105,610 0 00 0 105,610
0 0 106,540 15,271 0 00 121,811TotalCONSTRUCTION
$159,083Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670,512428358Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 359 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283582
District:
County:
INTERCHANGE IMPROVEMENT
SR 826/PALMETTO XWAY FROM NW 17 AVENUE TO GOLDEN GLADES INTERCHG
Roadway ID:
Project Length: 1.405
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 00 1,564 1,564
0 0 0 0 0 1,5640 1,564TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 00 83,927 83,927
DI 0 0 0 0 00 6,066 6,066
DIH 0 0 0 0 00 685 685
SU 0 0 0 0 00 6,317 6,317
0 0 0 0 0 96,9950 96,995TotalCONSTRUCTION
$98,559Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670,512428358Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283583
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO XWAY FROM W OF NW 17TH AVENUE TO I-95
Roadway ID:
Project Length: 4.768
Lanes Exist:Lanes Improved:Lanes Added:
2
8
1
MIAMI-DADE
LRTP Ref:
87260000
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 4,854 00 0 4,854
Section A1 - Page 360 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283583
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO XWAY FROM W OF NW 17TH AVENUE TO I-95
Roadway ID:
Project Length: 4.768
Lanes Exist:Lanes Improved:Lanes Added:
2
8
1
MIAMI-DADE
LRTP Ref:
87260000
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 200 00 0 200
STED 0 0 0 12,146 00 0 12,146
0 0 0 17,200 0 00 17,200TotalPLANNING AND DESIGN
DI 0 0 0 0 00 2,877 2,877
0 0 0 0 0 2,8770 2,877TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 00 101,873 101,873
DI 0 0 0 0 00 84,744 84,744
DIH 0 0 0 0 00 1,360 1,360
SU 0 0 0 0 00 7,820 7,820
0 0 0 0 0 195,7970 195,797TotalCONSTRUCTION
$215,874Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670,512428358Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 361 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283584
District:
County:
INTERCHANGE RAMP (NEW)
GGI INTERCHANGE VARIOUS RAMP RECONSTRUCTION
Roadway ID:
Project Length: 0.789
Lanes Exist:Lanes Improved:Lanes Added:
1
2
1
MIAMI-DADE
LRTP Ref:
87270210
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 150 00 0 150
SU 0 0 0 4,174 00 0 4,174
0 0 0 4,324 0 00 4,324TotalPLANNING AND DESIGN
SA 0 0 0 5 00 0 5
0 0 0 5 0 00 5TotalRAILROAD & UTILITIES
$4,329Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670,512428358Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283585
District:
County:
WIDEN/RESURFACE EXIST LANES
SR 9A/I-95 FROM BISCAYNE RIVER CANAL
TO SR 860/MIAMI GARDEN DR
Roadway ID:
Project Length: 2.235
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87270000
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 100 00 0 100
SU 0 0 0 2,691 00 0 2,691
0 0 0 2,791 0 00 2,791TotalPLANNING AND DESIGN
Section A1 - Page 362 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283585
District:
County:
WIDEN/RESURFACE EXIST LANES
SR 9A/I-95 FROM BISCAYNE RIVER CANAL
TO SR 860/MIAMI GARDEN DR
Roadway ID:
Project Length: 2.235
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87270000
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 00 1,402 1,402
0 0 0 0 0 1,4020 1,402TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 00 30,309 30,309
0 0 0 0 0 30,3090 30,309TotalCONSTRUCTION
$34,502Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670,512428358Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283586
District:
County:
INTERCHANGE RAMP (NEW)
SR 91/FL TURNPIKE SB TO SR 9A/I-95 SB EXPRESS LN FLYOVER(TPK CONECTOR)
Roadway ID:
Project Length: 0.833
Lanes Exist:Lanes Improved:Lanes Added: 1
MIAMI-DADE
LRTP Ref:
87270903
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 150 00 0 150
SU 0 0 0 3,263 00 0 3,263
0 0 0 3,413 0 00 3,413TotalPLANNING AND DESIGN
Section A1 - Page 363 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283586
District:
County:
INTERCHANGE RAMP (NEW)
SR 91/FL TURNPIKE SB TO SR 9A/I-95 SB EXPRESS LN FLYOVER(TPK CONECTOR)
Roadway ID:
Project Length: 0.833
Lanes Exist:Lanes Improved:Lanes Added: 1
MIAMI-DADE
LRTP Ref:
87270903
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 5 00 15 20
DI 0 0 0 0 00 800 800
0 0 0 5 0 8150 820TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 00 35,937 35,937
DIH 0 0 0 0 00 360 360
STED 0 0 0 0 00 17,347 17,347
SU 0 0 0 0 00 1,922 1,922
0 0 0 0 0 55,5660 55,566TotalCONSTRUCTION
$59,799Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670,512428358Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 364 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283587
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 9/I-95 FROM SR 916/OPALOCKA BLVD
TO GOLDEN GLADES INTCHG
Roadway ID:
Project Length: 1.708
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87270000
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 799 00 0 799
DI 0 0 0 2,723 00 0 2,723
DIH 0 0 0 150 00 0 150
0 0 0 3,672 0 00 3,672TotalPLANNING AND DESIGN
DI 0 0 0 0 00 800 800
0 0 0 0 0 8000 800TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 00 18,582 18,582
DIH 0 0 0 0 00 420 420
STED 0 0 0 0 00 42,053 42,053
0 0 0 0 0 61,0550 61,055TotalCONSTRUCTION
$65,527Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670,512428358Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 365 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283588
District:
County:
Add Lanes and Reconstruct
SR 826 CONNECTOR AT GOLDEN GLADES INTERCHG AND VARIOUS RAMPS
Roadway ID:
Project Length: 1.029
Lanes Exist:Lanes Improved:Lanes Added:
4
6
1
MIAMI-DADE
LRTP Ref:
87170000
6
6-18
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 01,720 0 1,720
DIH 0 0 0 0 020 0 20
DIS 1,000 0 0 0 0350 0 1,350
1,000 0 0 0 0 02,090 3,090TotalPLANNING AND DESIGN
DIH 10 0 0 0 00 0 10
DS 856 82 0 0 00 0 938
DSBD 1,718 0 0 0 00 0 1,718
2,584 82 0 0 0 00 2,666TotalRIGHT OF WAY
DIH 0 0 162 0 00 0 162
DS 0 0 5,766 2,439 00 0 8,205
DSBD 0 0 4,390 0 00 0 4,390
SU 0 0 14,326 0 00 0 14,326
0 0 24,644 2,439 0 00 27,083TotalCONSTRUCTION
$32,839Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670,512428358Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 366 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4284791
District:
County:
RESURFACING - RIDE ONLY
SR 976/SW 40 STREET FROM W OF SW 38 AVE TO SR 5/US-1
Roadway ID:
Project Length: 0.350
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 021 0 21
0 0 0 0 0 021 21TotalPLANNING AND DESIGN
0 0 0 0 03 0 3
0 0 0 0 0 03 3TotalRAILROAD & UTILITIES
0 0 0 0 0217 0 217
0 0 0 0 0 0217 217TotalCONSTRUCTION
$241Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $795428479Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4284792
District:
County:
RESURFACING - RIDE ONLY
SR 976/SW 40 STREET FROM EAST OF SW 38 COURT TO US-1/S DIXIE HIGHWAY
Roadway ID:
Project Length: 0.366
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87044000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 020 0 20
Section A1 - Page 367 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4284792
District:
County:
RESURFACING - RIDE ONLY
SR 976/SW 40 STREET FROM EAST OF SW 38 COURT TO US-1/S DIXIE HIGHWAY
Roadway ID:
Project Length: 0.366
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87044000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 0157 0 157
0 0 0 0 0 0177 177TotalPLANNING AND DESIGN
DIH 0 15 0 0 00 0 15
DS 0 56 0 0 00 0 56
NHRE 0 306 0 0 00 0 306
0 377 0 0 0 00 377TotalCONSTRUCTION
$554Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $795428479Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 368 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4284871
District:
County:
RESURFACING
SR 5/US-1/S DIXIE FROM N OF SW 168 STREET TO SW 183 STREET/SB ONLY
Roadway ID:
Project Length: 1.080
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0240 0 240
0 0 0 0 0 0240 240TotalPLANNING AND DESIGN
0 0 0 0 07 0 7
0 0 0 0 0 07 7TotalRAILROAD & UTILITIES
0 0 0 0 0814 0 814
0 0 0 0 0 0814 814TotalCONSTRUCTION
$1,061Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,841428487Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4284872
District:
County:
RESURFACING
SR 5/US-1/S DIXIE FROM N OF SW 184 STREET TO S OF SW 168 STREET
Roadway ID:
Project Length: 1.028
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87020000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 028 0 28
DS 0 0 0 0 0351 0 351
Section A1 - Page 369 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4284872
District:
County:
RESURFACING
SR 5/US-1/S DIXIE FROM N OF SW 184 STREET TO S OF SW 168 STREET
Roadway ID:
Project Length: 1.028
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87020000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0379 379TotalPLANNING AND DESIGN
DDR 0 677 0 0 00 0 677
DIH 0 53 0 0 00 0 53
DS 0 671 0 0 00 0 671
0 1,401 0 0 0 00 1,401TotalCONSTRUCTION
$1,780Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,841428487Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290141
District:
County:
INTERSECTION IMPROVEMENT
SR 823/NW 57 AVENUE AT NW 138 STREET INTERSECTION IMPROVEMENT
Roadway ID:
Project Length: 0.295
Lanes Exist:Lanes Improved:Lanes Added:
7
7
MIAMI-DADE
LRTP Ref:
87002000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 09 0 9
DIH 0 0 0 0 063 0 63
DS 0 0 0 0 04 0 4
Section A1 - Page 370 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290141
District:
County:
INTERSECTION IMPROVEMENT
SR 823/NW 57 AVENUE AT NW 138 STREET INTERSECTION IMPROVEMENT
Roadway ID:
Project Length: 0.295
Lanes Exist:Lanes Improved:Lanes Added:
7
7
MIAMI-DADE
LRTP Ref:
87002000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HSP 0 0 0 0 0165 0 165
0 0 0 0 0 0241 241TotalPLANNING AND DESIGN
DIH 0 0 0 0 02 0 2
LF 0 0 0 0 02,979 0 2,979
0 0 0 0 0 02,981 2,981TotalRIGHT OF WAY
ACSA 0 0 0 0 089 0 89
DIH 0 0 0 0 07 0 7
DS 0 0 0 0 019 0 19
HSP 0 0 0 0 0858 0 858
LF 0 0 0 0 0353 0 353
LF 0 0 0 0 040 0 40
SA 0 0 0 0 0263 0 263
0 0 0 0 0 01,629 1,629TotalCONSTRUCTION
SA 40 0 0 0 00 0 40
40 0 0 0 0 00 40TotalALTERNATIVE CONTRACTING INCENTIVES
$4,891Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,891429014Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 371 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290221
District:
County:
INTERSECTION IMPROVEMENT
SR 922/NW 125 STREET FROM NW 6 AVENUE TO NE MIAMI COURT
Roadway ID:
Project Length: 0.689
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87066000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 050 0 50
DIH 0 0 0 0 0137 0 137
DS 0 0 0 0 0332 0 332
0 0 0 0 0 0519 519TotalPLANNING AND DESIGN
DIH 50 150 0 0 0129 0 329
DS 510 600 0 0 0644 0 1,754
HSP 917 0 0 0 0500 0 1,417
1,477 750 0 0 0 01,273 3,500TotalRIGHT OF WAY
BRRP 0 0 0 0 04 0 4
DDR 0 53 0 0 00 0 53
DIH 0 5 0 0 00 0 5
HSP 0 1,514 158 0 00 0 1,672
SA 0 1,196 0 0 00 0 1,196
0 2,768 158 0 0 04 2,930TotalCONSTRUCTION
$6,949Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,299429022Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 372 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290222
District:
County:
INTERSECTION IMPROVEMENT
SR 922/NW 125 STREET FROM NW 6 COURT TO NW 6 AVENUE
Roadway ID:
Project Length: 0.100
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87066000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 034 0 34
DS 0 0 0 0 014 0 14
0 0 0 0 0 048 48TotalPLANNING AND DESIGN
DIH 0 21 0 0 00 0 21
DS 0 11 0 0 00 0 11
HSP 0 745 108 0 00 0 853
SA 0 417 0 0 00 0 417
0 1,194 108 0 0 00 1,302TotalCONSTRUCTION
$1,350Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,299429022Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 373 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290371
District:
County:
INTERSECTION IMPROVEMENT
SR 90/SW 8 & SW 7 ST AT SW 4 AVENUE AND AT SW 3 AVENUE
Roadway ID:
Project Length: 0.417
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87120000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 18 0 00 0 18
HSP 0 0 175 0 00 0 175
0 0 193 0 0 00 193TotalPLANNING AND DESIGN
DIH 0 0 0 11 00 0 11
DS 0 0 0 557 1,0100 0 1,567
0 0 0 568 1,010 00 1,578TotalRIGHT OF WAY
$1,771Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,771429037Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290471
District:
County:
LANDSCAPING
SR 93/I-75 FROM NW 178 STREET TO NW 202 STREET
Roadway ID:
Project Length: 1.463
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87075000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 15 0 0 02 0 17
DS 0 155 0 0 09 0 164
Section A1 - Page 374 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290471
District:
County:
LANDSCAPING
SR 93/I-75 FROM NW 178 STREET TO NW 202 STREET
Roadway ID:
Project Length: 1.463
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87075000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 170 0 0 0 011 181TotalPLANNING AND DESIGN
DDR 0 0 0 0 2,0450 0 2,045
DIH 0 0 0 0 310 0 31
DS 0 0 0 0 3520 0 352
0 0 0 0 2,428 00 2,428TotalCONSTRUCTION
$2,609Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,650429047Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290472
District:
County:
LANDSCAPING
SR 93/I-75 FROM NW 162 STREET TO NW 178 STREET
Roadway ID:
Project Length: 0.979
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87075000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 15 0 0 00 0 15
DS 0 125 0 0 00 0 125
0 140 0 0 0 00 140TotalPLANNING AND DESIGN
Section A1 - Page 375 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290472
District:
County:
LANDSCAPING
SR 93/I-75 FROM NW 162 STREET TO NW 178 STREET
Roadway ID:
Project Length: 0.979
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87075000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 1,0010 0 1,001
DIH 0 0 0 0 170 0 17
DS 0 0 0 0 1900 0 190
0 0 0 0 1,208 00 1,208TotalCONSTRUCTION
$1,348Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,650429047Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290473
District:
County:
LANDSCAPING
SR 93/I-75 FROM NW 148 STREET TO NW 162 STREET
Roadway ID:
Project Length: 0.923
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87075000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 015 0 15
DS 0 0 0 0 0129 0 129
Section A1 - Page 376 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4290473
District:
County:
LANDSCAPING
SR 93/I-75 FROM NW 148 STREET TO NW 162 STREET
Roadway ID:
Project Length: 0.923
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87075000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0144 144TotalPLANNING AND DESIGN
DIH 0 68 0 0 00 0 68
DS 0 481 0 0 00 0 481
0 549 0 0 0 00 549TotalCONSTRUCTION
$693Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,650429047Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291461
District:
County:
RESURFACING
SR 916/NW 135 STREET FROM SR 9/NW 27 AVENUE TO NW 8 AVENUE
Roadway ID:
Project Length: 1.935
Lanes Exist:Lanes Improved:Lanes Added:
5
3
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0141 0 141
0 0 0 0 0 0141 141TotalPLANNING AND DESIGN
0 0 0 0 06 0 6
0 0 0 0 03 0 3
Section A1 - Page 377 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291461
District:
County:
RESURFACING
SR 916/NW 135 STREET FROM SR 9/NW 27 AVENUE TO NW 8 AVENUE
Roadway ID:
Project Length: 1.935
Lanes Exist:Lanes Improved:Lanes Added:
5
3
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 09 9TotalRIGHT OF WAY
0 0 0 0 028 0 28
0 0 0 0 01,697 0 1,697
0 0 0 0 04 0 4
0 0 0 0 0 01,729 1,729TotalCONSTRUCTION
$1,879Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,181429146Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291462
District:
County:
INTERSECTION IMPROVEMENT
SR 916/NW 135 STREET AT NW 17 AVENUE
Roadway ID:
Project Length: 0.019
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 09 0 9
0 0 0 0 0 09 9TotalPLANNING AND DESIGN
0 0 0 0 072 0 72
Section A1 - Page 378 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291462
District:
County:
INTERSECTION IMPROVEMENT
SR 916/NW 135 STREET AT NW 17 AVENUE
Roadway ID:
Project Length: 0.019
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02 0 2
0 0 0 0 0 074 74TotalCONSTRUCTION
$83Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,181429146Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291463
District:
County:
INTERSECTION IMPROVEMENT
SR 916/NW 135 ST AT NW 17 AVENUE
Roadway ID:
Project Length: 0.050
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 031 0 31
DS 0 0 0 0 010 0 10
0 0 0 0 0 041 41TotalPLANNING AND DESIGN
DDR 155 0 0 0 00 0 155
DIH 22 0 0 0 00 0 22
Section A1 - Page 379 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291463
District:
County:
INTERSECTION IMPROVEMENT
SR 916/NW 135 ST AT NW 17 AVENUE
Roadway ID:
Project Length: 0.050
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 01 0 1
177 0 0 0 0 01 178TotalCONSTRUCTION
$219Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,181429146Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291591
District:
County:
RESURFACING
SR 25/NW 36 STREET FROM EAST OF NW 17 AVENUE
TO WEST OF NW 7 AVENUE
Roadway ID:
Project Length: 0.933
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0319 0 319
0 0 0 0 0 0319 319TotalPLANNING AND DESIGN
0 0 0 0 07 0 7
0 0 0 0 038 0 38
0 0 0 0 0 045 45TotalRIGHT OF WAY
Section A1 - Page 380 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291591
District:
County:
RESURFACING
SR 25/NW 36 STREET FROM EAST OF NW 17 AVENUE
TO WEST OF NW 7 AVENUE
Roadway ID:
Project Length: 0.933
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 032 0 32
0 0 0 0 02,566 0 2,566
0 0 0 0 057 0 57
0 0 0 0 0 02,655 2,655TotalCONSTRUCTION
$3,019Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,072429159Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291592
District:
County:
RESURFACING - RIDE ONLY
SR 25/US-27/NE 36 ST FROM N MIAMI AVENUE TO E OF NE 5 AVENUE
Roadway ID:
Project Length: 0.442
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 0166 0 166
0 0 0 0 0 0186 186TotalPLANNING AND DESIGN
DIH 0 0 0 0 011 0 11
Section A1 - Page 381 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291592
District:
County:
RESURFACING - RIDE ONLY
SR 25/US-27/NE 36 ST FROM N MIAMI AVENUE TO E OF NE 5 AVENUE
Roadway ID:
Project Length: 0.442
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 053 0 53
DS 20 0 0 0 00 0 20
LF 16 0 0 0 00 0 16
36 0 0 0 0 064 100TotalRIGHT OF WAY
DIH 22 0 0 0 00 0 22
DS 745 0 0 0 00 0 745
767 0 0 0 0 00 767TotalCONSTRUCTION
$1,053Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,072429159Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 382 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291621
District:
County:
RESURFACING
SR 90/TAMIAMI TRAIL FROM L-N41 CANAL BRIDGE TO 1/2 MI W OF KROME AVE
Roadway ID:
Project Length: 0.545
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87110000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0105 0 105
0 0 0 0 0 0105 105TotalPLANNING AND DESIGN
0 0 0 0 0898 0 898
0 0 0 0 0 0898 898TotalCONSTRUCTION
$1,003Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,079429162Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291622
District:
County:
RESURFACING
SR 90/TAMIAMI TRAIL FROM W OF LOOP ROAD TO W OF EVERGLADES PRESV
Roadway ID:
Project Length: 9.205
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87110000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 061 0 61
DS 0 0 0 0 02 0 2
EB 0 0 0 0 0510 0 510
0 0 0 0 0 0573 573TotalPLANNING AND DESIGN
Section A1 - Page 383 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291622
District:
County:
RESURFACING
SR 90/TAMIAMI TRAIL FROM W OF LOOP ROAD TO W OF EVERGLADES PRESV
Roadway ID:
Project Length: 9.205
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87110000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 078 0 78
DIH 0 0 0 0 0200 0 200
NHRE 0 0 0 0 02,468 0 2,468
SA 384 0 0 0 02,132 0 2,516
384 0 0 0 0 04,878 5,262TotalCONSTRUCTION
DDR 40 0 0 0 00 0 40
DS 100 0 0 0 00 0 100
140 0 0 0 0 00 140TotalALTERNATIVE CONTRACTING INCENTIVES
$5,975Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,079429162Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 384 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291623
District:
County:
RESURFACING
SR 90/TAMIAMI TRAIL FROM E OF SW 127TH AVENUE TO TURNPIKE EXT ON-RAMP
Roadway ID:
Project Length: 0.771
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87120000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0140 0 140
0 0 0 0 0 0140 140TotalPLANNING AND DESIGN
0 0 0 0 01 0 1
0 0 0 0 05 0 5
0 0 0 0 01 0 1
0 0 0 0 0 07 7TotalRIGHT OF WAY
0 0 0 0 0954 0 954
0 0 0 0 0 0954 954TotalCONSTRUCTION
$1,101Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,079429162Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 385 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291861
District:
County:
RESURFACING
SR 817/NW 27 AVENUE FROM SOUTH OF NW 187 ST TO NORTH OF NW 202 TERR
Roadway ID:
Project Length: 1.030
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87019000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 047 0 47
0 0 0 0 0256 0 256
0 0 0 0 0 0303 303TotalPLANNING AND DESIGN
0 0 0 0 03 0 3
0 0 0 0 0 03 3TotalRIGHT OF WAY
0 0 0 0 090 0 90
0 0 0 0 01,418 0 1,418
0 0 0 0 0 01,508 1,508TotalCONSTRUCTION
$1,814Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,524429186Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 386 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291862
District:
County:
INTERSECTION IMPROVEMENT
SR 817/NW 27 AVENUE AT MIAMI GARDENS DRIVE
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87019000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 077 0 77
0 0 0 0 0 077 77TotalPLANNING AND DESIGN
0 0 0 0 013 0 13
0 0 0 0 0229 0 229
0 0 0 0 08 0 8
0 0 0 0 0 0250 250TotalCONSTRUCTION
$327Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,524429186Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 387 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291863
District:
County:
RESURFACING
SR 817/NW 27 AVENUE FROM SOUTH OF NW 203 ST TO NW 215 ST/COUNTY LINE
Roadway ID:
Project Length: 0.859
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 324 0 0 00 0 324
DIH 0 59 0 0 00 0 59
0 383 0 0 0 00 383TotalPLANNING AND DESIGN
$383Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,524429186Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291931
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 907/ALTON ROAD FROM MICHIGAN AVENUE TO S OF ED SULLIVAN DR/43 ST
Roadway ID:
Project Length: 1.281
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87037000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSA 0 0 0 0 060 0 60
DIH 0 0 0 0 042 0 42
DS 0 0 0 0 0675 0 675
DS 0 0 0 0 045 0 45
SA 0 0 0 0 050 0 50
Section A1 - Page 388 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291931
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 907/ALTON ROAD FROM MICHIGAN AVENUE TO S OF ED SULLIVAN DR/43 ST
Roadway ID:
Project Length: 1.281
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87037000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SU 0 0 0 0 0225 0 225
0 0 0 0 0 01,097 1,097TotalPLANNING AND DESIGN
DIH 0 0 0 0 05 0 5
DS 148 0 0 0 00 0 148
DS 0 0 0 0 250 0 25
LF 0 0 0 0 3,0000 0 3,000
148 0 0 0 3,025 05 3,178TotalRIGHT OF WAY
DDR 0 0 0 0 21,8340 0 21,834
DIH 0 0 0 0 340 0 34
0 0 0 0 21,868 00 21,868TotalCONSTRUCTION
$26,143Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $27,456429193Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 389 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291932
District:
County:
INTERSECTION IMPROVEMENT
SR 907/ALTON ROAD AT MICHIGAN AVENUE
Roadway ID:
Project Length: 0.208
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87037000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 053 0 53
DS 0 0 0 0 0189 0 189
0 0 0 0 0 0242 242TotalPLANNING AND DESIGN
LF 3 0 0 0 00 0 3
3 0 0 0 0 00 3TotalRAILROAD & UTILITIES
DDR 51 0 0 0 0140 0 191
DIH 66 0 0 0 00 0 66
DS 5 0 0 0 00 0 5
HSP 776 0 0 0 00 0 776
898 0 0 0 0 0140 1,038TotalCONSTRUCTION
SA 0 30 0 0 00 0 30
0 30 0 0 0 00 30TotalALTERNATIVE CONTRACTING INCENTIVES
$1,313Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $27,456429193Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 390 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4291941
District:
County:
RESURFACING
SR 968/W FLAGLER ST FROM WEST 75 AVENUE TO E OF TAMIAMI CANAL RD
Roadway ID:
Project Length: 0.389
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 20 0 0 0 0148 0 168
DIH 0 0 0 0 047 0 47
DS 0 0 0 0 012 0 12
20 0 0 0 0 0207 227TotalPLANNING AND DESIGN
LF 14 0 0 0 00 0 14
14 0 0 0 0 00 14TotalRAILROAD & UTILITIES
DDR 0 105 0 0 00 0 105
DIH 54 0 0 0 00 0 54
DS 922 0 0 0 00 0 922
976 105 0 0 0 00 1,081TotalCONSTRUCTION
DS 0 30 0 0 00 0 30
0 30 0 0 0 00 30TotalALTERNATIVE CONTRACTING INCENTIVES
$1,352Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,352429194Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 391 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4292712
District:
County:
PD&E/EMO STUDY
PERIMETER ROAD FROM NW 57 AVENUE TO NW 18 STREET
Roadway ID:
Project Length: 1.200
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01 0 1
0 0 0 0 0 01 1TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $22,673429271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4292851
District:
County:
PRELIMINARY ENGINEERING
TRAFFIC ENGINEERING STUDIES & ENGINEERING REVIEWS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 8 0 0 0 0225 0 233
DS 0 0 0 0 01,200 0 1,200
8 0 0 0 0 01,425 1,433TotalPLANNING AND DESIGN
$1,433Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,014429285Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 392 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4292852
District:
County:
PRELIMINARY ENGINEERING
TRAFFIC ENGINEERING STUDIES & ENGINEERING REVIEWS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 12 12 12 0 00 0 36
DS 225 225 225 300 0270 0 1,245
237 237 237 300 0 0270 1,281TotalPLANNING AND DESIGN
$1,281Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,014429285Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4292853
District:
County:
PRELIMINARY ENGINEERING
TRAFFIC ENGINEERING STUDIES & ENGINEERING REVIEWS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 3000 0 300
0 0 0 0 300 00 300TotalPLANNING AND DESIGN
$300Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,014429285Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 393 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4292861
District:
County:
PRELIMINARY ENGINEERING
TRAFFIC ENGINEERING RDWAY DESIGN & STRUCTURAL ANALYSIS CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 4 0 0 0 0105 0 109
DS 0 0 0 0 0500 0 500
4 0 0 0 0 0605 609TotalPLANNING AND DESIGN
$609Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,598429286Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4292862
District:
County:
PRELIMINARY ENGINEERING
TRAFFIC ENGINEERING SUPPORT SERVICES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 35 10 2 0 0104 0 151
DS 100 0 0 0 0600 0 700
135 10 2 0 0 0704 851TotalPLANNING AND DESIGN
$851Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,598429286Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 394 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4292863
District:
County:
PRELIMINARY ENGINEERING
TRAFFIC ENGINEERING SUPPORT SERVICES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 5 0 033 0 38
DS 300 300 400 0 0500 0 1,500
300 300 405 0 0 0533 1,538TotalPLANNING AND DESIGN
$1,538Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,598429286Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4292864
District:
County:
PRELIMINARY ENGINEERING
TRAFFIC ENGINEERING SUPPORT SERVICES CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 300 3000 0 600
0 0 0 300 300 00 600TotalPLANNING AND DESIGN
$600Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,598429286Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 395 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293001
District:
County:
RIGID PAVEMENT REHABILITATION
SR 9A/I-95 FROM NW 79TH STREET TO NW 103RD STREET
Roadway ID:
Project Length: 1.529
Lanes Exist:Lanes Improved:Lanes Added:
12
12
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 046 0 46
0 0 0 0 01,139 0 1,139
0 0 0 0 0 01,185 1,185TotalPLANNING AND DESIGN
0 0 0 0 03 0 3
0 0 0 0 011,197 0 11,197
0 0 0 0 01,615 0 1,615
0 0 0 0 0 012,815 12,815TotalCONSTRUCTION
0 0 0 0 0160 0 160
0 0 0 0 0 0160 160TotalALTERNATIVE CONTRACTING INCENTIVES
$14,160Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $126,009429300Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 396 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293002
District:
County:
RIGID PAVEMENT RECONSTRUCTION
SR 9A/I-95 FROM NW 8 STREET TO NW 29 STREET
Roadway ID:
Project Length: 4.013
Lanes Exist:Lanes Improved:Lanes Added:
1
1
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 0453 0 453
DI 0 0 0 0 02,399 0 2,399
DIH 0 0 0 0 072 0 72
DIS 0 0 0 0 0450 0 450
DS 0 0 0 0 0372 0 372
0 0 0 0 0 03,746 3,746TotalPLANNING AND DESIGN
ACNP 250 0 0 0 00 0 250
250 0 0 0 0 00 250TotalRAILROAD & UTILITIES
ACNP 25,780 2,050 0 0 00 0 27,830
BRRP 0 0 0 0 013 0 13
DS 1,050 0 0 0 00 0 1,050
26,830 2,050 0 0 0 013 28,893TotalDESIGN/BUILD
ACNP 0 0 0 0 00 700 700
0 0 0 0 0 7000 700TotalALTERNATIVE CONTRACTING INCENTIVES
$33,589Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $126,009429300Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 397 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293003
District:
County:
RIGID PAVEMENT RECONSTRUCTION
SR 9A/I-95 FROM NW 29 STREET TO NW 79 STREET
Roadway ID:
Project Length: 7.094
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 727 0 0 0 00 0 727
727 0 0 0 0 00 727TotalPLANNING AND DESIGN
ACNP 66 0 0 0 00 0 66
66 0 0 0 0 00 66TotalRAILROAD & UTILITIES
ACNP 57,663 6,613 0 0 00 0 64,276
57,663 6,613 0 0 0 00 64,276TotalDESIGN/BUILD
ACNP 0 0 0 1,320 00 0 1,320
0 0 0 1,320 0 00 1,320TotalALTERNATIVE CONTRACTING INCENTIVES
$66,389Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $126,009429300Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 398 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293004
District:
County:
RESURFACING
SR 925/NW 3RD COURT & NW 3RD AVENUE
FROM NW 1ST STREET TO NW 8TH ST
Roadway ID:
Project Length: 1.203
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 864 0 0 0 00 0 864
DIH 156 0 0 0 00 0 156
1,020 0 0 0 0 00 1,020TotalPLANNING AND DESIGN
DDR 0 0 0 3,546 00 0 3,546
DIH 0 0 0 155 00 0 155
DS 0 0 0 1,582 00 0 1,582
SA 0 0 0 5,568 00 0 5,568
0 0 0 10,851 0 00 10,851TotalCONSTRUCTION
$11,871Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $126,009429300Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 399 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293451
District:
County:
RESURFACING
SR 969/NW 72 AVE FROM NW 25 ST TO NW 74 STREET
Roadway ID:
Project Length: 2.889
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87027000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSA 0 0 0 0 0703 0 703
DDR 0 0 0 0 025 0 25
DIH 0 0 0 0 052 0 52
DS 0 0 0 0 024 0 24
0 0 0 0 0 0804 804TotalPLANNING AND DESIGN
DDR 0 0 0 0 00 0 0
DIH 0 0 0 0 06 0 6
DS 0 0 0 0 05 0 5
LF 0 0 0 0 056 0 56
0 0 0 0 0 067 67TotalRIGHT OF WAY
ACSA 0 0 0 0 02,706 0 2,706
BRRP 0 0 0 0 07 0 7
DDR 0 0 0 0 0800 0 800
DIH 0 0 0 0 0173 0 173
SA 515 0 0 0 00 0 515
515 0 0 0 0 03,686 4,201TotalCONSTRUCTION
SA 150 0 0 0 00 0 150
150 0 0 0 0 00 150TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 400 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$5,222Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,488429345Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293452
District:
County:
INTERSECTION IMPROVEMENT
SR 969/NW 72 AVE AT SR 934/NW 74 STREET
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87027000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01 0 1
0 0 0 0 093 0 93
0 0 0 0 0 094 94TotalPLANNING AND DESIGN
0 0 0 0 02 0 2
0 0 0 0 0164 0 164
0 0 0 0 06 0 6
0 0 0 0 0 0172 172TotalCONSTRUCTION
$266Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,488429345Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 401 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293461
District:
County:
RESURFACING
SR 916/NW/NE 135 ST FROM NW 6 AVENUE TO SR 5/BISCAYNE BLVD
Roadway ID:
Project Length: 3.008
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 041 0 41
DDR 0 0 0 0 068 0 68
DIH 0 0 0 0 054 0 54
DS 0 0 0 0 061 0 61
DS 0 0 0 0 099 0 99
SA 0 0 0 0 01,074 0 1,074
0 0 0 0 0 01,397 1,397TotalPLANNING AND DESIGN
LF 0 0 3 0 00 0 3
SA 0 0 15 0 00 0 15
0 0 18 0 0 00 18TotalRAILROAD & UTILITIES
BRRP 0 0 0 0 05 0 5
DDR 0 0 2,074 0 00 0 2,074
DIH 0 0 198 0 00 0 198
DS 0 0 805 0 00 0 805
SA 0 0 2,320 0 00 0 2,320
0 0 5,397 0 0 05 5,402TotalCONSTRUCTION
DS 0 0 0 100 00 0 100
0 0 0 100 0 00 100TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 402 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$6,917Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,596429346Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293462
District:
County:
INTERSECTION IMPROVEMENT
SR 916/NE 135 STREET AT SR 915/NE 6 AVENUE AND AT SR 909/W DIXIE HWY
Roadway ID:
Project Length: 0.114
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87034000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 014 0 14
0 0 0 0 0133 0 133
0 0 0 0 05 0 5
0 0 0 0 0 0152 152TotalPLANNING AND DESIGN
0 0 0 0 07 0 7
0 0 0 0 0 07 7TotalRIGHT OF WAY
0 0 0 0 09 0 9
0 0 0 0 0667 0 667
0 0 0 0 069 0 69
0 0 0 0 0 0745 745TotalCONSTRUCTION
$904Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,596429346Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 403 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4293463
District:
County:
ROAD/SLOPE PROTECTION
SR 916/NE 135TH STREET FROM E OF NE 2ND CT TO W OF NE 4TH AVENUE
Roadway ID:
Project Length: 0.151
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 21 0 0 0 00 0 21
DS 754 0 0 0 00 0 754
775 0 0 0 0 00 775TotalCONSTRUCTION
$775Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,596429346Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4295362
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
DISTRICTWIDE (ADA) PUSHBUTTON CONSTRUCTION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 022 0 22
0 0 0 0 0 022 22TotalPLANNING AND DESIGN
Section A1 - Page 404 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4295362
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
DISTRICTWIDE (ADA) PUSHBUTTON CONSTRUCTION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0743 0 743
0 0 0 0 0 0743 743TotalCONSTRUCTION
$765Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,465429536Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4295363
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
DISTRICTWIDE (ADA) PUSHBUTTON CONSTRUCTION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 91 0 0 0 00 0 91
Section A1 - Page 405 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4295363
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
DISTRICTWIDE (ADA) PUSHBUTTON CONSTRUCTION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 726 0 0 0 00 0 726
817 0 0 0 0 00 817TotalCONSTRUCTION
$817Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,465429536Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4295364
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
DISTRICTWIDE (ADA) PUSHBUTTON CONSTRUCTION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 147 0 00 0 147
Section A1 - Page 406 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4295364
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
DISTRICTWIDE (ADA) PUSHBUTTON CONSTRUCTION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 736 0 00 0 736
0 0 883 0 0 00 883TotalCONSTRUCTION
$883Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,465429536Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4299961
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 93/I-75 RAMP SB TO SR 826 AT NW 138 STREET REPAIR BRIDGE # 870604
Roadway ID:
Project Length: 0.102
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87075600
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 25 0 0 0 054 0 79
DIH 0 0 0 0 016 0 16
25 0 0 0 0 070 95TotalPLANNING AND DESIGN
Section A1 - Page 407 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4299961
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 93/I-75 RAMP SB TO SR 826 AT NW 138 STREET REPAIR BRIDGE # 870604
Roadway ID:
Project Length: 0.102
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87075600
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 1,842 0 0 00 0 1,842
DIH 0 16 0 0 00 0 16
0 1,858 0 0 0 00 1,858TotalCONSTRUCTION
$1,953Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,953429996Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4300291
District:
County:
BRIDGE-REPAIR/REHABILITATION
ATLANTIC ISLE AT WEST OF SR A1A (BRIDGE# 874218)
Roadway ID:
Project Length: 0.009
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87674513
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACBZ 47 45 0 0 00 0 92
47 45 0 0 0 00 92TotalPLANNING AND DESIGN
ACBZ 0 0 445 0 00 0 445
0 0 445 0 0 00 445TotalCONSTRUCTION
Section A1 - Page 408 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$537Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $537430029Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4301612
District:
County:
INSPECT CONSTRUCTION PROJS.
DISTRICTWIDE RESIDENCY CEI CONSULTANT FOR LAP OVERSIGHT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 2800 0 280
SA 400 380 380 460 01,256 0 2,876
400 380 380 460 280 01,256 3,156TotalCONSTRUCTION
$3,156Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,156430161Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302911
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 41 0 0 0 00 0 41
DSBD 205 613 0 0 00 0 818
246 613 0 0 0 00 859TotalDESIGN/BUILD
Section A1 - Page 409 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302911
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DITS 724 0 0 0 00 0 724
DS 598 0 0 0 00 0 598
DSBD 4,600 0 0 0 00 0 4,600
5,922 0 0 0 0 00 5,922TotalCAPITAL
$6,781Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,529430291Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302912
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 44 0 0 00 0 44
DS 0 0 256 0 00 0 256
DSBD 0 0 754 0 00 0 754
0 44 1,010 0 0 00 1,054TotalDESIGN/BUILD
Section A1 - Page 410 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302912
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DITS 0 1,392 0 0 00 0 1,392
DSBD 0 4,100 0 0 00 0 4,100
0 5,492 0 0 0 00 5,492TotalCAPITAL
$6,546Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,529430291Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302913
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 22 0 00 0 22
DS 0 0 0 178 00 0 178
DSBD 0 0 0 264 00 0 264
Section A1 - Page 411 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302913
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 22 442 0 00 464TotalDESIGN/BUILD
DITS 0 0 945 0 00 0 945
DSBD 0 0 1,400 0 00 0 1,400
0 0 2,345 0 0 00 2,345TotalCAPITAL
$2,809Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,529430291Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302914
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 27 00 0 27
DS 0 0 0 0 1920 0 192
DSBD 0 0 0 0 4180 0 418
0 0 0 27 610 00 637TotalDESIGN/BUILD
Section A1 - Page 412 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302914
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DITS 0 0 0 873 00 0 873
DSBD 0 0 0 1,900 00 0 1,900
0 0 0 2,773 0 00 2,773TotalCAPITAL
$3,410Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,529430291Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4302915
District:
County:
ITS COMMUNICATION SYSTEM
ITS EQUIPMENT REPLACEMENT - CONSULTANTS /GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DITS 0 0 0 0 11,5830 0 11,583
DSBD 0 0 0 0 2,4000 0 2,400
0 0 0 0 13,983 00 13,983TotalCAPITAL
$13,983Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $33,529430291Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 413 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4304441
District:
County:
FLEXIBLE PAVEMENT RECONSTRUCT.
SR 907/ALTON ROAD FROM S OF 43RD STREET TO E OF ALLISON ROAD
Roadway ID:
Project Length: 2.567
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87037000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACCM 0 0 0 0 0699 0 699
ACSA 0 0 0 0 01,859 0 1,859
DIH 0 0 0 0 056 0 56
DS 0 0 0 0 012 0 12
SA 0 0 0 0 0557 0 557
0 0 0 0 0 03,183 3,183TotalPLANNING AND DESIGN
DIH 0 0 0 0 025 0 25
DS 0 0 0 0 0158 0 158
DS 0 0 0 0 250 0 25
LF 0 0 0 0 2,0000 0 2,000
0 0 0 0 2,025 0183 2,208TotalRIGHT OF WAY
DDR 0 0 0 0 9,2180 0 9,218
DIH 0 0 0 0 2210 0 221
DS 0 0 0 0 3,0930 0 3,093
SA 0 0 0 0 9,9970 0 9,997
0 0 0 0 22,529 00 22,529TotalCONSTRUCTION
$27,920Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $27,920430444Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 414 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4305881
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 5/BISCAYNE BLVD FROM NE 5OTH TERRACE TO NE 87 STREET
Roadway ID:
Project Length: 2.331
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0120 0 120
0 0 0 0 0 0120 120TotalCONSTRUCTION
$120Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,319430588Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4305882
District:
County:
RESURFACING - RIDE ONLY
SR 5/BISCAYNE BLVD FROM S OF NE 76 STREET TO S OF NE 87 STREET
Roadway ID:
Project Length: 0.688
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 0129 0 129
0 0 0 0 0 0139 139TotalPLANNING AND DESIGN
LF 19 0 0 0 00 0 19
19 0 0 0 0 00 19TotalRAILROAD & UTILITIES
DDR 40 0 0 0 00 0 40
Section A1 - Page 415 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4305882
District:
County:
RESURFACING - RIDE ONLY
SR 5/BISCAYNE BLVD FROM S OF NE 76 STREET TO S OF NE 87 STREET
Roadway ID:
Project Length: 0.688
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 23 0 0 0 00 0 23
DS 409 0 0 0 00 0 409
472 0 0 0 0 00 472TotalCONSTRUCTION
$630Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,319430588Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4305883
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 5/US-1/BISCAYNE BLVD FROM NE 61 ST TO NE 78 ST
Roadway ID:
Project Length: 0.991
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 030 0 30
DS 0 0 0 0 0149 0 149
0 0 0 0 0 0179 179TotalPLANNING AND DESIGN
DIH 31 0 0 0 00 0 31
Section A1 - Page 416 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4305883
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 5/US-1/BISCAYNE BLVD FROM NE 61 ST TO NE 78 ST
Roadway ID:
Project Length: 0.991
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 359 0 0 0 00 0 359
390 0 0 0 0 00 390TotalCONSTRUCTION
$569Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,319430588Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4306371
District:
County:
ADD LANES & RECONSTRUCT
SR 847/NW 47 AVENUE FROM SR 860/NW 183 STREET TO PREMIER PKY (BROWARD)
Roadway ID:
Project Length: 2.364
Lanes Exist:Lanes Improved:Lanes Added:
2
4
2
MIAMI-DADE
LRTP Ref:
87012000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0103 0 103
DIH 0 0 0 0 0334 0 334
DS 0 0 0 0 0587 0 587
Section A1 - Page 417 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4306371
District:
County:
ADD LANES & RECONSTRUCT
SR 847/NW 47 AVENUE FROM SR 860/NW 183 STREET TO PREMIER PKY (BROWARD)
Roadway ID:
Project Length: 2.364
Lanes Exist:Lanes Improved:Lanes Added:
2
4
2
MIAMI-DADE
LRTP Ref:
87012000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 01,024 1,024TotalPLANNING AND DESIGN
DIH 25 0 0 0 0255 0 280
DS 2,000 0 0 0 05,865 0 7,865
DS 300 0 0 0 035 0 335
DSBD 8,200 0 0 0 00 0 8,200
LF 0 7,000 0 0 00 0 7,000
SU 1,000 0 0 0 00 0 1,000
11,525 7,000 0 0 0 06,155 24,680TotalRIGHT OF WAY
DIH 0 0 0 0 092 0 92
DS 0 0 0 0 063 0 63
SU 0 0 0 0 01,405 0 1,405
0 0 0 0 0 01,560 1,560TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
BRRP 0 0 0 0 012 0 12
DDR 0 158 0 0 00 0 158
DIH 0 147 0 0 00 0 147
DS 0 3,937 0 0 00 0 3,937
SU 0 24,474 0 0 00 0 24,474
0 28,716 0 0 0 012 28,728TotalCONSTRUCTION
Section A1 - Page 418 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4306371
District:
County:
ADD LANES & RECONSTRUCT
SR 847/NW 47 AVENUE FROM SR 860/NW 183 STREET TO PREMIER PKY (BROWARD)
Roadway ID:
Project Length: 2.364
Lanes Exist:Lanes Improved:Lanes Added:
2
4
2
MIAMI-DADE
LRTP Ref:
87012000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
SU 0 0 0 1,000 00 0 1,000
0 0 0 1,000 0 00 1,000TotalALTERNATIVE CONTRACTING INCENTIVES
$56,992Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $57,637430637Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4306372
District:
County:
LANDSCAPING
SR 847/NW 47 AVE FROM SR 860/MIAMI GARDENS TO MIAMI DADE/BRWD CO LINE
Roadway ID:
Project Length: 2.144
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87012000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 10 0 0 00 0 10
DS 0 80 0 0 00 0 80
0 90 0 0 0 00 90TotalPLANNING AND DESIGN
DIH 0 0 0 17 00 0 17
DS 0 0 0 538 00 0 538
Section A1 - Page 419 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4306372
District:
County:
LANDSCAPING
SR 847/NW 47 AVE FROM SR 860/MIAMI GARDENS TO MIAMI DADE/BRWD CO LINE
Roadway ID:
Project Length: 2.144
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87012000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 555 0 00 555TotalCONSTRUCTION
$645Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $57,637430637Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4307633
District:
County:
ADD SPECIAL USE LANE
SR 93/I-75 FROM S OF NW 170 STREET TO MIAMI-DADE COUNTY LINE
Roadway ID:
Project Length: 1.957
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87075000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 0 038 0 38
DIH 0 0 0 0 036 0 36
DIS 0 0 0 0 0185 0 185
GMR 0 0 0 0 01,400 0 1,400
NHPP 0 0 0 0 01,890 0 1,890
STED 0 0 0 0 01,343 0 1,343
0 0 0 0 0 04,892 4,892TotalPLANNING AND DESIGN
Section A1 - Page 420 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4307633
District:
County:
ADD SPECIAL USE LANE
SR 93/I-75 FROM S OF NW 170 STREET TO MIAMI-DADE COUNTY LINE
Roadway ID:
Project Length: 1.957
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87075000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 540 500 500 0 01,119 0 2,659
DI 0 0 0 0 0698 0 698
DIS 0 0 0 0 0244 0 244
STED 0 0 0 0 0238 0 238
540 500 500 0 0 02,299 3,839TotalCONSTRUCTION
$8,731Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,347430763Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4307636
District:
County:
PRELIM ENG FOR FUTURE CAPACITY
SR-93/I-75 FROM NW 103 STREET TO MIAMI-DADE/BROWARD CL
Roadway ID:
Project Length: 5.442
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,170 0 2,170
0 0 0 0 0709 0 709
0 0 0 0 0 02,879 2,879TotalENVIRONMENTAL
Section A1 - Page 421 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$2,879Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,347430763Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4307638
District:
County:
INSPECT CONSTRUCTION PROJS.
SR-93/I-75 FROM NW 170 STREET TO MIAMI-DADE/BROWARD CL
Roadway ID:
Project Length: 5.442
Lanes Exist:Lanes Improved:Lanes Added:
8
8
MIAMI-DADE
LRTP Ref:
87075000
6
6-10
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 095 0 95
0 0 0 0 0 095 95TotalPLANNING AND DESIGN
0 0 0 0 0836 0 836
0 0 0 0 0806 0 806
0 0 0 0 0 01,642 1,642TotalCONSTRUCTION
$1,737Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,347430763Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4307681
District:
County:
INTERSECTION IMPROVEMENT
SR 5/BISCAYNE BLVD AT NE 199, 203, 205, 209 & 213 STREETS
Roadway ID:
Project Length: 0.958
Lanes Exist:Lanes Improved:Lanes Added:
7
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 01 0 1
Section A1 - Page 422 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4307681
District:
County:
INTERSECTION IMPROVEMENT
SR 5/BISCAYNE BLVD AT NE 199, 203, 205, 209 & 213 STREETS
Roadway ID:
Project Length: 0.958
Lanes Exist:Lanes Improved:Lanes Added:
7
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 028 0 28
HSP 0 0 0 0 0384 0 384
0 0 0 0 0 0413 413TotalPLANNING AND DESIGN
DDR 0 0 0 0 031 0 31
DIH 0 0 0 0 062 0 62
HSP 0 0 0 0 010 0 10
HSP 0 0 0 0 02,313 0 2,313
0 0 0 0 0 02,416 2,416TotalCONSTRUCTION
SA 40 0 0 0 00 0 40
40 0 0 0 0 00 40TotalALTERNATIVE CONTRACTING INCENTIVES
$2,869Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,869430768Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 423 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308031
District:
County:
RESURFACING
SR 823/NW 57 AVENUE FROM S OF NW 142 ST TO S OF NW 186 STREET
Roadway ID:
Project Length: 2.808
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87002000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 069 0 69
DS 0 0 0 0 0798 0 798
LF 0 0 0 0 0178 0 178
0 0 0 0 0 01,045 1,045TotalPLANNING AND DESIGN
DIH 0 0 0 0 03 0 3
LF 0 0 0 0 031 0 31
0 0 0 0 0 034 34TotalRIGHT OF WAY
DDR 0 0 0 0 01,000 0 1,000
DIH 0 0 0 0 021 0 21
DS 77 0 0 0 00 0 77
DS 489 0 0 0 01,241 0 1,730
HSP 33 0 0 0 0168 0 201
SA 0 0 0 0 01,800 0 1,800
599 0 0 0 0 04,230 4,829TotalCONSTRUCTION
$5,908Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,908430803Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 424 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308081
District:
County:
RESURFACING
SR 5/BISCAYNE BLVD FROM NE 151 STREET TO NE 196 STREET
Roadway ID:
Project Length: 3.053
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0213 0 213
DS 0 0 0 0 0759 0 759
HSP 0 0 0 0 0150 0 150
0 0 0 0 0 01,122 1,122TotalPLANNING AND DESIGN
DDR 0 0 0 0 05 0 5
DIH 0 0 0 0 021 0 21
DS 0 0 0 0 012 0 12
LF 0 0 0 0 09 0 9
0 0 0 0 0 047 47TotalRIGHT OF WAY
DDR 0 0 0 0 01,839 0 1,839
DIH 69 0 0 0 0155 0 224
DS 87 0 0 0 03,503 0 3,590
HSP 0 0 0 0 0961 0 961
HSP 63 0 0 0 00 0 63
SA 428 0 0 0 00 0 428
647 0 0 0 0 06,458 7,105TotalCONSTRUCTION
DS 0 220 0 0 00 0 220
0 220 0 0 0 00 220TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 425 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$8,494Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,331430808Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308082
District:
County:
INTERSECTION IMPROVEMENT
SR 860/MIAMI GARDENS DRIVE AT BISCAYNE BLVD AND AT WEST DIXIE HIGHWAY
Roadway ID:
Project Length: 0.097
Lanes Exist:Lanes Improved:Lanes Added:
5
MIAMI-DADE
LRTP Ref:
87026000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0222 0 222
DIH 0 0 0 0 056 0 56
DS 0 0 0 0 081 0 81
0 0 0 0 0 0359 359TotalPLANNING AND DESIGN
DIH 0 0 0 0 012 0 12
DS 0 0 0 0 070 0 70
0 0 0 0 0 082 82TotalRIGHT OF WAY
DDR 21 0 0 0 00 0 21
DDR 0 0 0 0 010 0 10
DIH 0 0 0 0 044 0 44
HSP 18 0 0 0 0229 0 247
39 0 0 0 0 0283 322TotalCONSTRUCTION
SA 0 20 0 0 00 0 20
0 20 0 0 0 00 20TotalALTERNATIVE CONTRACTING INCENTIVES
$783Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,331430808Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 426 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308083
District:
County:
INTERSECTION IMPROVEMENT
SR 860/MIAMI GARDENS DRIVE AT BISCAYNE BLVD
Roadway ID:
Project Length: 0.097
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 05 0 5
DS 0 0 0 0 049 0 49
0 0 0 0 0 054 54TotalPLANNING AND DESIGN
$54Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,331430808Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308131
District:
County:
RESURFACING - RIDE ONLY
SR A1A/INDIAN CRK DR FROM SR 907/WEST 63 STREET
TO ABBOTT AVENUE
Roadway ID:
Project Length: 0.516
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87060001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0149 0 149
DIH 0 0 0 0 021 0 21
DS 0 0 0 0 07 0 7
0 0 0 0 0 0177 177TotalPLANNING AND DESIGN
DDR 0 802 0 0 00 0 802
Section A1 - Page 427 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308131
District:
County:
RESURFACING - RIDE ONLY
SR A1A/INDIAN CRK DR FROM SR 907/WEST 63 STREET
TO ABBOTT AVENUE
Roadway ID:
Project Length: 0.516
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87060001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 30 0 0 00 0 30
DS 0 239 0 0 00 0 239
0 1,071 0 0 0 00 1,071TotalCONSTRUCTION
$1,248Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,248430813Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308171
District:
County:
RESURFACING
SR 7/NW 7 AVENUE FROM NW 36 STREET TO N OF NW 78 STREET
Roadway ID:
Project Length: 2.558
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87140000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0514 0 514
0 0 0 0 0 0514 514TotalPLANNING AND DESIGN
0 0 0 0 00 0 0
0 0 0 0 062 0 62
Section A1 - Page 428 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308171
District:
County:
RESURFACING
SR 7/NW 7 AVENUE FROM NW 36 STREET TO N OF NW 78 STREET
Roadway ID:
Project Length: 2.558
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87140000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 020 0 20
0 0 0 0 0 082 82TotalRIGHT OF WAY
0 0 0 0 012 0 12
0 0 0 0 07,532 0 7,532
0 0 0 0 0134 0 134
0 0 0 0 0 07,678 7,678TotalCONSTRUCTION
0 0 0 0 0470 0 470
0 0 0 0 0 0470 470TotalALTERNATIVE CONTRACTING INCENTIVES
$8,744Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,643430817Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 429 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308172
District:
County:
RESURFACING
SR 7/NW 7 AVENUE FROM N OF NW 79 STREET TO LITTLE RIVER DRIVE
Roadway ID:
Project Length: 0.590
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87140000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 021 0 21
DS 0 0 0 0 0583 0 583
0 0 0 0 0 0604 604TotalPLANNING AND DESIGN
DDR 0 926 0 0 00 0 926
DIH 0 35 0 0 00 0 35
DS 0 0 87 0 00 0 87
0 961 87 0 0 00 1,048TotalCONSTRUCTION
$1,652Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,643430817Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 430 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308173
District:
County:
RESURFACING
SR 7/US 441/NW 7 AVE FROM LITTLE RIVER DR TO SOUTH OF NW 117 STREET
Roadway ID:
Project Length: 1.861
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 100 0 0 0 00 0 100
100 0 0 0 0 00 100TotalPLANNING AND DESIGN
DDR 0 0 0 5,267 00 0 5,267
DIH 0 0 0 78 00 0 78
0 0 0 5,345 0 00 5,345TotalCONSTRUCTION
$5,445Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,643430817Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308174
District:
County:
RESURFACING
SR 7/US 441/NW 7 AVE FROM NW 119 STREET TO SOUTH OF BISCAYNE CANAL
Roadway ID:
Project Length: 2.227
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 100 0 0 0 00 0 100
100 0 0 0 0 00 100TotalPLANNING AND DESIGN
Section A1 - Page 431 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4308174
District:
County:
RESURFACING
SR 7/US 441/NW 7 AVE FROM NW 119 STREET TO SOUTH OF BISCAYNE CANAL
Roadway ID:
Project Length: 2.227
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 5,621 0 00 0 5,621
DIH 0 0 81 0 00 0 81
0 0 5,702 0 0 00 5,702TotalCONSTRUCTION
$5,802Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,643430817Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4309491
District:
County:
RESURFACING
SR A1A/COLLINS AVE FROM BAYVIEW DRIVE TO SR 856/192 STREET
Roadway ID:
Project Length: 2.241
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87060000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0697 0 697
DIH 0 0 0 0 045 0 45
Section A1 - Page 432 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4309491
District:
County:
RESURFACING
SR A1A/COLLINS AVE FROM BAYVIEW DRIVE TO SR 856/192 STREET
Roadway ID:
Project Length: 2.241
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87060000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 095 0 95
0 0 0 0 0 0837 837TotalPLANNING AND DESIGN
LF 23 0 0 0 00 0 23
23 0 0 0 0 00 23TotalRAILROAD & UTILITIES
DS 147 0 0 0 00 0 147
SA 5,135 0 0 0 00 0 5,135
5,282 0 0 0 0 00 5,282TotalCONSTRUCTION
DS 0 200 0 0 00 0 200
0 200 0 0 0 00 200TotalALTERNATIVE CONTRACTING INCENTIVES
$6,342Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,342430949Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 433 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4309571
District:
County:
NEW ROAD CONSTRUCTION
SR 860/MIAMI GARDENS DRIVE INTERCHANGE (SYSTEM-TO-SYSTEM INTCH)
Roadway ID:
Project Length: 2.007
Lanes Exist:Lanes Improved:Lanes Added: 2
MIAMI-DADE
LRTP Ref:
87026112
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 250 0 00 0 250
DS 0 0 300 0 00 0 300
0 0 550 0 0 00 550TotalPLANNING AND DESIGN
DDR 0 0 5 0 00 0 5
0 0 5 0 0 00 5TotalRAILROAD & UTILITIES
$555Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $565430957Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 434 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4309572
District:
County:
PARK AND RIDE LOTS
SR 860/MIAMI GARDNS DR FROM E OF NW 97 AVE TO I-75 AND PARK & RIDE LOT
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
0 0 0 0 0 010 10TotalPLANNING AND DESIGN
$10Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $565430957Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4311701
District:
County:
RESURFACING
SR 94/KENDALL DRIVE FROM SW 97 AVENUE TO SW 79 AVENUE
Roadway ID:
Project Length: 1.716
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 030 0 30
DS 0 0 0 0 0352 0 352
0 0 0 0 0 0382 382TotalPLANNING AND DESIGN
DDR 0 53 0 0 00 0 53
DIH 0 128 0 0 00 0 128
DS 0 233 0 0 00 0 233
Section A1 - Page 435 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4311701
District:
County:
RESURFACING
SR 94/KENDALL DRIVE FROM SW 97 AVENUE TO SW 79 AVENUE
Roadway ID:
Project Length: 1.716
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
NHRE 0 291 0 0 00 0 291
SA 0 1,806 0 0 00 0 1,806
0 2,511 0 0 0 00 2,511TotalCONSTRUCTION
DDR 0 0 90 0 00 0 90
0 0 90 0 0 00 90TotalALTERNATIVE CONTRACTING INCENTIVES
$2,983Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,836431170Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4311702
District:
County:
RESURFACING
SR 94/KENDALL DRIVE
Roadway ID:
Project Length: 0.559
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 0164 0 164
0 0 0 0 0 0174 174TotalPLANNING AND DESIGN
Section A1 - Page 436 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4311702
District:
County:
RESURFACING
SR 94/KENDALL DRIVE
Roadway ID:
Project Length: 0.559
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 25 0 0 00 0 25
DS 0 0 0 0 05 0 5
0 25 0 0 0 05 30TotalRAILROAD & UTILITIES
DIH 0 77 0 0 00 0 77
DS 0 69 0 0 00 0 69
NHRE 0 1,237 0 0 00 0 1,237
SA 0 126 0 0 00 0 126
0 1,509 0 0 0 00 1,509TotalCONSTRUCTION
DS 0 0 50 0 00 0 50
0 0 50 0 0 00 50TotalALTERNATIVE CONTRACTING INCENTIVES
$1,763Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,836431170Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 437 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4311703
District:
County:
RESURFACING
SR 94/KENDALL DRIVE FROM SW 7500 BLOCK/SW 73 PLACE
TO US 1/S DIXIE HWY
Roadway ID:
Project Length: 0.451
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0215 0 215
DIH 0 0 0 0 030 0 30
DS 0 0 0 0 017 0 17
0 0 0 0 0 0262 262TotalPLANNING AND DESIGN
DDR 0 16 0 0 00 0 16
DIH 0 61 0 0 00 0 61
DS 0 53 0 0 00 0 53
SA 0 1,063 0 0 00 0 1,063
0 1,193 0 0 0 00 1,193TotalCONSTRUCTION
DS 0 0 40 0 00 0 40
0 0 40 0 0 00 40TotalALTERNATIVE CONTRACTING INCENTIVES
$1,495Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,836431170Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 438 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4311704
District:
County:
INTERSECTION IMPROVEMENT
SR 94/KENDALL DRIVE FROM SW 77 AVE TO US 1
Roadway ID:
Project Length: 0.718
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 030 0 30
HSP 0 0 0 0 0414 0 414
0 0 0 0 0 0444 444TotalPLANNING AND DESIGN
DDR 0 0 150 0 00 0 150
DIH 0 0 109 0 00 0 109
DS 0 32 0 0 00 0 32
HSP 0 179 1,681 0 00 0 1,860
0 211 1,940 0 0 00 2,151TotalCONSTRUCTION
$2,595Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,836431170Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 439 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314331
District:
County:
MISCELLANEOUS CONSTRUCTION
PEDESTRIAN & BICYCLE SAFETY PUSHBUTTON CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,047 0 1,047
0 0 0 0 0 01,047 1,047TotalCONSTRUCTION
$1,047Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,285431433Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314332
District:
County:
MISCELLANEOUS CONSTRUCTION
TRAFFIC OPERATIONS PUSH BUTTON - ROADS MIAMI-DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 106 0 00 0 106
DS 0 0 1,042 0 00 0 1,042
0 0 1,148 0 0 00 1,148TotalCONSTRUCTION
$1,148Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,285431433Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 440 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314333
District:
County:
MISCELLANEOUS CONSTRUCTION
TRAFFIC OPERATIONS PUSH BUTTON - ROADS MIAMI-DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 114 1170 0 231
DS 0 0 0 122 1,0320 0 1,154
0 0 0 236 1,149 00 1,385TotalCONSTRUCTION
$1,385Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,285431433Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314334
District:
County:
MISCELLANEOUS CONSTRUCTION
PEDESTRIAN & BICYCLE SAFETY PUSHBUTTON CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 120 0 0 00 0 120
DS 0 1,053 0 0 00 0 1,053
0 1,173 0 0 0 00 1,173TotalCONSTRUCTION
$1,173Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,285431433Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 441 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314335
District:
County:
MISCELLANEOUS CONSTRUCTION
PEDESTRIAN & BICYCLE SAFETY PUSHBUTTON CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 126 00 0 126
DS 0 0 0 1,110 00 0 1,110
0 0 0 1,236 0 00 1,236TotalCONSTRUCTION
$1,236Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,285431433Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314336
District:
County:
MISCELLANEOUS CONSTRUCTION
TRAFFIC OPERATIONS PUSH BUTTON - ROADS MIAMI-DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 111 114 0 0 00 0 225
DS 1,071 0 0 0 00 0 1,071
1,182 114 0 0 0 00 1,296TotalCONSTRUCTION
$1,296Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,285431433Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 442 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314341
District:
County:
MISCELLANEOUS CONSTRUCTION
PEDESTRIAN & BICYCLE SAFETY PUSHBUTTON CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,047 0 1,047
0 0 0 0 0 01,047 1,047TotalCONSTRUCTION
$1,047Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,871431434Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314342
District:
County:
MISCELLANEOUS CONSTRUCTION
TRAFFIC OPERATIONS PUSH BUTTON - SIGNALS MIAMI-DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 103 106 0 00 0 209
DS 0 0 1,042 0 00 0 1,042
0 103 1,148 0 0 00 1,251TotalCONSTRUCTION
$1,251Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,871431434Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 443 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314343
District:
County:
MISCELLANEOUS CONSTRUCTION
TRAFFIC OPERATIONS PUSH BUTTON - SIGNALS MIAMI-DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 114 1170 0 231
DS 0 0 0 111 1,0320 0 1,143
0 0 0 225 1,149 00 1,374TotalCONSTRUCTION
$1,374Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,871431434Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314344
District:
County:
MISCELLANEOUS CONSTRUCTION
TRAFFIC OPERATIONS PUSH BUTTON - SIGNALS MIAMI-DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 128 0 0 0 00 0 128
DS 1,071 0 0 0 00 0 1,071
1,199 0 0 0 0 00 1,199TotalCONSTRUCTION
$1,199Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,871431434Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 444 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4314991
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL INFRASTRUCTURE PROJECT - BISCAYNE SCHOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 00 0 0
SA 0 0 0 0 02 0 2
TALU 0 0 0 0 030 0 30
0 0 0 0 0 032 32TotalPLANNING AND DESIGN
SA 2 0 0 0 00 0 2
TALU 232 0 0 0 00 0 232
234 0 0 0 0 00 234TotalCONSTRUCTION
$266Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $266431499Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4315031
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL INFRASTRUCTURE PROJECT PERRINE ELEMENTARY SCHOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 02 0 2
Section A1 - Page 445 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4315031
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL INFRASTRUCTURE PROJECT PERRINE ELEMENTARY SCHOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 00 0 0
TALU 0 0 0 0 054 0 54
0 0 0 0 0 056 56TotalPLANNING AND DESIGN
SA 2 0 0 0 00 0 2
TALU 417 0 0 0 00 0 417
419 0 0 0 0 00 419TotalCONSTRUCTION
$475Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $475431503Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4315071
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL INFRASTRUCTURE PRIORITY 2 CORAL REEF ELEMENTARY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 03 0 3
SA 0 0 0 0 00 0 0
Section A1 - Page 446 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4315071
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL INFRASTRUCTURE PRIORITY 2 CORAL REEF ELEMENTARY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 0 0 0 0 018 0 18
0 0 0 0 0 021 21TotalPLANNING AND DESIGN
SA 3 0 0 0 00 0 3
TALU 139 0 0 0 00 0 139
142 0 0 0 0 00 142TotalCONSTRUCTION
$163Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $163431507Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4316351
District:
County:
SAFETY PROJECT
DISTRICTWIDE SAFETY PUSHBUTTON PROJECTS PILOT PROGRAM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 013 0 13
0 0 0 0 0859 0 859
Section A1 - Page 447 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4316351
District:
County:
SAFETY PROJECT
DISTRICTWIDE SAFETY PUSHBUTTON PROJECTS PILOT PROGRAM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0193 0 193
0 0 0 0 0 01,065 1,065TotalPLANNING AND DESIGN
0 0 0 0 0543 0 543
0 0 0 0 03,282 0 3,282
0 0 0 0 0134 0 134
0 0 0 0 0 03,959 3,959TotalCONSTRUCTION
$5,024Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,514431635Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4316352
District:
County:
SAFETY PROJECT
DISTRICTWIDE SAFETY PUSHBUTTON CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 3 3 3 0 06 0 15
DS 0 0 0 0 0100 0 100
Section A1 - Page 448 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4316352
District:
County:
SAFETY PROJECT
DISTRICTWIDE SAFETY PUSHBUTTON CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HSP 300 300 300 0 00 0 900
303 303 303 0 0 0106 1,015TotalPLANNING AND DESIGN
DIH 106 109 100 0 00 0 315
HSP 1,025 1,053 1,082 0 00 0 3,160
1,131 1,162 1,182 0 0 00 3,475TotalCONSTRUCTION
$4,490Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,514431635Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4324091
District:
County:
BIKE PATH/TRAIL
NE 183RD STREET FROM NE 11 AVENUE TO NE 19 AVENUE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 00 0 0
SA 0 0 0 0 05 0 5
SE 0 0 0 0 0137 0 137
Section A1 - Page 449 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4324091
District:
County:
BIKE PATH/TRAIL
NE 183RD STREET FROM NE 11 AVENUE TO NE 19 AVENUE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 0 0 0 0 045 0 45
0 0 0 0 0 0187 187TotalPLANNING AND DESIGN
SA 0 5 0 0 00 0 5
TALU 0 318 0 0 00 0 318
0 323 0 0 0 00 323TotalCONSTRUCTION
$510Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $510432409Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 450 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4324131
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE SCOPING UNIT TRAFFIC SAFETY REVIEWS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 200 200 200 200 0660 0 1,460
200 200 200 200 0 0660 1,460TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,460Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,460432413Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326391
District:
County:
TRANSPORTATION PLANNING
SR 826/PALMETTO EXPY FROM US-1/S DIXIE HWY TO SR 836/DOLPHIN XWAY
Roadway ID:
Project Length: 7.224
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 5,063 0 0 0 00 0 5,063
DIH 10 10 10 0 019 0 49
DIS 1,637 0 0 0 00 0 1,637
DS 0 0 0 0 0619 0 619
6,710 10 10 0 0 0638 7,368TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
Section A1 - Page 451 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$7,368Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,029432639Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326396
District:
County:
PD&E/EMO STUDY
SR 90/SW 7 ST/SW 8 ST FROM BRICKELL AVENUE TO SR 9/SW 27 AVENUE
Roadway ID:
Project Length: 2.970
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87120000
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,000 0 2,000
0 0 0 0 040 0 40
0 0 0 0 0 02,040 2,040TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,040Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,029432639Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326871
District:
County:
ADD SPECIAL USE LANE
SR 826 FROM FLAGLER ST TO NW 154 ST & I-75 FROM SR 826 TO NW 170 ST
Roadway ID:
Project Length: 13.518
Lanes Exist:Lanes Improved:Lanes Added:
3
5
1
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 01,677 0 1,677
DIH 0 0 0 0 0192 0 192
DS 0 0 0 0 0178 0 178
Section A1 - Page 452 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326871
District:
County:
ADD SPECIAL USE LANE
SR 826 FROM FLAGLER ST TO NW 154 ST & I-75 FROM SR 826 TO NW 170 ST
Roadway ID:
Project Length: 13.518
Lanes Exist:Lanes Improved:Lanes Added:
3
5
1
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
PKYI 0 0 0 0 0194 0 194
STED 0 0 0 0 0309 0 309
0 0 0 0 0 02,550 2,550TotalPLANNING AND DESIGN
ACNP 0 0 0 0 01,766 0 1,766
DDR 0 0 0 0 0363 0 363
NHPP 0 0 0 0 01,000 0 1,000
PKED 0 0 0 0 015 0 15
0 0 0 0 0 03,144 3,144TotalRAILROAD & UTILITIES
ACNP 0 0 0 0 0112,502 0 112,502
DDR 62 42 0 0 0227 0 331
DI 0 0 0 0 0516 0 516
DIH 63 32 0 0 0729 0 824
DIS 0 0 0 0 0150 0 150
DIS 0 0 0 0 0500 0 500
DS 513 527 0 0 038 0 1,078
DSBD 0 0 0 0 019,999 0 19,999
DSBD 0 0 0 0 02,470 0 2,470
GMR 2,000 0 0 0 00 0 2,000
Section A1 - Page 453 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326871
District:
County:
ADD SPECIAL USE LANE
SR 826 FROM FLAGLER ST TO NW 154 ST & I-75 FROM SR 826 TO NW 170 ST
Roadway ID:
Project Length: 13.518
Lanes Exist:Lanes Improved:Lanes Added:
3
5
1
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
NHPP 0 0 0 0 082,297 0 82,297
PKED 0 0 0 0 026,220 0 26,220
PKED 0 0 0 0 08,264 0 8,264
PKYI 0 0 0 0 05 0 5
SA 0 0 0 0 01 0 1
STED 0 0 0 0 015,309 0 15,309
2,638 601 0 0 0 0269,227 272,466TotalDESIGN/BUILD
GMR 2,363 0 0 0 00 0 2,363
STED 7,887 0 0 0 00 0 7,887
10,250 0 0 0 0 00 10,250TotalALTERNATIVE CONTRACTING INCENTIVES
$288,410Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $290,695432687Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 454 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326872
District:
County:
RESURFACING
SR 826/PALMETTO EXPY FROM SR 93/I-75 TO NW 154 STREET
Roadway ID:
Project Length: 1.054
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05 0 5
0 0 0 0 0 05 5TotalPLANNING AND DESIGN
0 0 0 0 0315 0 315
0 0 0 0 0 0315 315TotalDESIGN/BUILD
$320Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $290,695432687Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326873
District:
County:
LANDSCAPING
SR 826/PALMETTO EXPY FROM NW 31 STREET TO FEC RAILROAD
Roadway ID:
Project Length: 3.118
Lanes Exist:Lanes Improved:Lanes Added:
10
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 025 0 25
DS 0 0 0 0 0176 0 176
0 0 0 0 0 0201 201TotalPLANNING AND DESIGN
DS 0 5 0 0 00 0 5
Section A1 - Page 455 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326873
District:
County:
LANDSCAPING
SR 826/PALMETTO EXPY FROM NW 31 STREET TO FEC RAILROAD
Roadway ID:
Project Length: 3.118
Lanes Exist:Lanes Improved:Lanes Added:
10
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
0 5 0 0 0 00 5TotalRAILROAD & UTILITIES
DIH 0 58 0 0 00 0 58
DS 0 466 0 0 00 0 466
0 524 0 0 0 00 524TotalCONSTRUCTION
$730Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $290,695432687Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326874
District:
County:
LANDSCAPING
SR 826/PALMETTO EXPY FROM FEC RAILROAD TO NW 154 STREET
Roadway ID:
Project Length: 4.549
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 015 0 15
DS 0 0 0 0 0135 0 135
0 0 0 0 0 0150 150TotalPLANNING AND DESIGN
Section A1 - Page 456 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326874
District:
County:
LANDSCAPING
SR 826/PALMETTO EXPY FROM FEC RAILROAD TO NW 154 STREET
Roadway ID:
Project Length: 4.549
Lanes Exist:Lanes Improved:Lanes Added:
8
MIAMI-DADE
LRTP Ref:
87260000
6
6-12
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 5 0 0 00 0 5
0 5 0 0 0 00 5TotalRAILROAD & UTILITIES
DDR 0 984 0 0 00 0 984
DIH 0 96 0 0 00 0 96
0 1,080 0 0 0 00 1,080TotalCONSTRUCTION
$1,235Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $290,695432687Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326951
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI-DADE COUNTYWDE DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 45 0 0 0 00 0 45
45 0 0 0 0 00 45TotalPLANNING AND DESIGN
Section A1 - Page 457 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326951
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI-DADE COUNTYWDE DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 1,118 0 0 00 0 1,118
DIH 0 110 0 0 00 0 110
0 1,228 0 0 0 00 1,228TotalCONSTRUCTION
$1,273Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,697432695Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326953
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI-DADE COUNTYWIDE DRAINAGE PUSHBUTTON PROJECT FOR FY 19-20
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 45 0 00 0 45
0 0 45 0 0 00 45TotalPLANNING AND DESIGN
DDR 0 0 0 1,323 00 0 1,323
DIH 0 0 0 56 00 0 56
0 0 0 1,379 0 00 1,379TotalCONSTRUCTION
Section A1 - Page 458 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$1,424Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,697432695Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327431
District:
County:
RESURFACING
SR 826/PALMETTO EXPY FROM SR 5/US-1 TO N OF SR 878/SNAPPER CREEK EXPY
Roadway ID:
Project Length: 3.288
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87260000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0374 0 374
0 0 0 0 0 0374 374TotalPLANNING AND DESIGN
0 0 0 0 02,383 0 2,383
0 0 0 0 0 02,383 2,383TotalCONSTRUCTION
0 0 0 0 032 0 32
0 0 0 0 0 032 32TotalALTERNATIVE CONTRACTING INCENTIVES
$2,789Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,769432743Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 459 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327432
District:
County:
RESURFACING
SR 826/PALMETTO EXPY FROM EAST OF NW 57 AVE TO WEST OF NW 27 AVE
Roadway ID:
Project Length: 8.309
Lanes Exist:Lanes Improved:Lanes Added:
1
1
MIAMI-DADE
LRTP Ref:
87260000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 01,035 0 1,035
DIH 0 0 0 0 041 0 41
DS 0 0 0 0 084 0 84
0 0 0 0 0 01,160 1,160TotalPLANNING AND DESIGN
DDR 0 0 0 0 01 0 1
LF 0 0 0 0 010 0 10
0 0 0 0 0 011 11TotalRAILROAD & UTILITIES
BRRP 0 0 0 0 08 0 8
DDR 0 0 0 0 01,777 0 1,777
DIH 0 0 0 0 021 0 21
DS 0 0 0 0 0315 0 315
SA 0 0 0 0 03,481 0 3,481
0 0 0 0 0 05,602 5,602TotalCONSTRUCTION
DS 235 0 0 0 00 0 235
235 0 0 0 0 00 235TotalALTERNATIVE CONTRACTING INCENTIVES
$7,008Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,769432743Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 460 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327433
District:
County:
RESURFACING
SR 826/PALMETTO EXPY FROM WEST OF NW 27 AVE TO WEST OF NW 17 AVE
Roadway ID:
Project Length: 4.710
Lanes Exist:Lanes Improved:Lanes Added:
1
MIAMI-DADE
LRTP Ref:
87260000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0534 0 534
DIH 0 0 0 0 037 0 37
DS 0 0 0 0 048 0 48
0 0 0 0 0 0619 619TotalPLANNING AND DESIGN
BRRP 0 0 0 0 09 0 9
DDR 0 0 0 0 040 0 40
DIH 0 0 0 0 041 0 41
DS 0 0 0 0 0233 0 233
NHRE 0 0 0 0 03,251 0 3,251
0 0 0 0 0 03,574 3,574TotalCONSTRUCTION
DS 210 0 0 0 00 0 210
210 0 0 0 0 00 210TotalALTERNATIVE CONTRACTING INCENTIVES
$4,403Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,769432743Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 461 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327434
District:
County:
RESURFACING
SR 826/PALMETTO EXPY FROM W OF NW 67 AVENUE TO W OF NW 57 AVENUE
Roadway ID:
Project Length: 1.231
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 015 0 15
DS 0 0 0 0 0283 0 283
0 0 0 0 0 0298 298TotalPLANNING AND DESIGN
DDR 0 1,308 0 0 00 0 1,308
DIH 0 11 0 0 00 0 11
0 1,319 0 0 0 00 1,319TotalCONSTRUCTION
$1,617Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,769432743Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327435
District:
County:
INTERSECTION IMPROVEMENT
SR 817/NW 27 AVENUE FROM NW 165 STREET TO NW 171 STREET
Roadway ID:
Project Length: 0.485
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87019000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 097 0 97
0 0 0 0 0217 0 217
Section A1 - Page 462 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327435
District:
County:
INTERSECTION IMPROVEMENT
SR 817/NW 27 AVENUE FROM NW 165 STREET TO NW 171 STREET
Roadway ID:
Project Length: 0.485
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87019000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0314 314TotalPLANNING AND DESIGN
0 0 0 0 021 0 21
0 0 0 0 0 021 21TotalRIGHT OF WAY
0 0 0 0 015 0 15
0 0 0 0 0579 0 579
0 0 0 0 023 0 23
0 0 0 0 0 0617 617TotalCONSTRUCTION
$952Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,769432743Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327481
District:
County:
RESURFACING - RIDE ONLY
SR 933/NW 12 AVENUE FROM NW 1500 BLOCK TO NW 20TH STREET
Roadway ID:
Project Length: 0.341
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87085000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 027 0 27
Section A1 - Page 463 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327481
District:
County:
RESURFACING - RIDE ONLY
SR 933/NW 12 AVENUE FROM NW 1500 BLOCK TO NW 20TH STREET
Roadway ID:
Project Length: 0.341
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87085000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 0261 0 261
0 0 0 0 0 0288 288TotalPLANNING AND DESIGN
LF 9 0 0 0 00 0 9
9 0 0 0 0 00 9TotalRAILROAD & UTILITIES
DDR 26 0 0 0 00 0 26
DIH 12 0 0 0 00 0 12
DS 0 0 0 0 02 0 2
SA 703 0 0 0 00 0 703
741 0 0 0 0 02 743TotalCONSTRUCTION
$1,040Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,492432748Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 464 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327482
District:
County:
RESURFACING - RIDE ONLY
SR 933/SW-NW 12 AVENUE FROM NORTH OF SW 13 STREET
TO NW 1500 BLOCK
Roadway ID:
Project Length: 1.993
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87085000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0197 0 197
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 046 0 46
0 0 0 0 0 0263 263TotalPLANNING AND DESIGN
LF 41 0 0 0 00 0 41
41 0 0 0 0 00 41TotalRAILROAD & UTILITIES
DDR 62 0 0 0 00 0 62
DIH 37 0 0 0 00 0 37
SA 1,009 0 0 0 00 0 1,009
1,108 0 0 0 0 00 1,108TotalCONSTRUCTION
$1,412Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,492432748Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 465 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327483
District:
County:
INTERSECTION IMPROVEMENT
SR 933/SW/NW 12 AVENUE FROM SW 3 STREET TO NW 12 STREET
Roadway ID:
Project Length: 1.044
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 0239 0 239
0 0 0 0 0 0249 249TotalPLANNING AND DESIGN
DDR 10 0 0 0 00 0 10
DIH 10 0 0 0 00 0 10
HSP 771 0 0 0 00 0 771
791 0 0 0 0 00 791TotalCONSTRUCTION
$1,040Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,492432748Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 466 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4329501
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PROGRAM MANAGEMENT CONTRACT ADMIN SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 600 600 600 600 6002,240 0 5,240
600 600 600 600 600 02,240 5,240TotalPLANNING AND DESIGN
$5,240Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,240432950Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4330591
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 5/BISCAYNE BLVD FROM NE 13 STREET TO NE 78 STREET
Roadway ID:
Project Length: 3.208
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0202 0 202
0 0 0 0 0 0202 202TotalPLANNING AND DESIGN
0 0 0 0 01 0 1
0 0 0 0 04 0 4
0 0 0 0 0 05 5TotalRIGHT OF WAY
Section A1 - Page 467 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4330591
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 5/BISCAYNE BLVD FROM NE 13 STREET TO NE 78 STREET
Roadway ID:
Project Length: 3.208
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0920 0 920
0 0 0 0 0 0920 920TotalCONSTRUCTION
$1,127Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,963433059Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4330592
District:
County:
INTERSECTION IMPROVEMENT
SR 5/BISCAYNE BLVD FROM NE 32ND STREET TO NE 38TH STREET
Roadway ID:
Project Length: 0.316
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 036 0 36
DS 0 0 0 0 013 0 13
Section A1 - Page 468 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4330592
District:
County:
INTERSECTION IMPROVEMENT
SR 5/BISCAYNE BLVD FROM NE 32ND STREET TO NE 38TH STREET
Roadway ID:
Project Length: 0.316
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HSP 0 0 0 0 0448 0 448
0 0 0 0 0 0497 497TotalPLANNING AND DESIGN
LF 29 0 0 0 00 0 29
29 0 0 0 0 00 29TotalRAILROAD & UTILITIES
DIH 56 0 0 0 00 0 56
DS 51 0 0 0 00 0 51
HSP 1,203 0 0 0 00 0 1,203
1,310 0 0 0 0 00 1,310TotalCONSTRUCTION
$1,836Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,963433059Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 469 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4332641
District:
County:
INTERSECTION IMPROVEMENT
SR 94/KENDALL DRIVE FROM W OF SW 127 AVENUE TO W OF SW 122 AVENUE
Roadway ID:
Project Length: 0.592
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 088 0 88
0 0 0 0 0221 0 221
0 0 0 0 0 0309 309TotalPLANNING AND DESIGN
0 0 0 0 02 0 2
0 0 0 0 01 0 1
0 0 0 0 026 0 26
0 0 0 0 0 029 29TotalRIGHT OF WAY
0 0 0 0 045 0 45
0 0 0 0 01,264 0 1,264
0 0 0 0 054 0 54
0 0 0 0 0 01,363 1,363TotalCONSTRUCTION
$1,701Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,164433264Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 470 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4332642
District:
County:
RESURFACING
SR 94/KENDALL DR/SW 88 ST FROM E OF SW 132 AVE TO E OF SW 122 AVE
Roadway ID:
Project Length: 0.697
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 54 0 0 00 0 54
DS 0 300 0 0 00 0 300
0 354 0 0 0 00 354TotalPLANNING AND DESIGN
DIH 0 0 0 40 00 0 40
DS 0 0 0 2,774 00 0 2,774
0 0 0 2,814 0 00 2,814TotalCONSTRUCTION
$3,168Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,164433264Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4332643
District:
County:
RESURFACING
SR 94/KENDALL DR/SW 88 ST FROM E OF SW 150 AVE TO E OF SW 132 AVE
Roadway ID:
Project Length: 2.095
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 130 0 0 00 0 130
DS 0 720 0 0 00 0 720
Section A1 - Page 471 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4332643
District:
County:
RESURFACING
SR 94/KENDALL DR/SW 88 ST FROM E OF SW 150 AVE TO E OF SW 132 AVE
Roadway ID:
Project Length: 2.095
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 850 0 0 0 00 850TotalPLANNING AND DESIGN
DIH 0 0 0 0 910 0 91
DS 0 0 0 0 5,3540 0 5,354
0 0 0 0 5,445 00 5,445TotalCONSTRUCTION
$6,295Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,164433264Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4332831
District:
County:
INTERSECTION IMPROVEMENT
SR 9/NW/SW/27 AVENUE FROM SW 10TH STREET TO NW 1ST STREET
Roadway ID:
Project Length: 0.713
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87240000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0164 0 164
DS 0 0 0 0 045 0 45
0 0 0 0 0 0209 209TotalPLANNING AND DESIGN
DIH 0 0 0 0 06 0 6
Section A1 - Page 472 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4332831
District:
County:
INTERSECTION IMPROVEMENT
SR 9/NW/SW/27 AVENUE FROM SW 10TH STREET TO NW 1ST STREET
Roadway ID:
Project Length: 0.713
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87240000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 06 0 6
DS 0 0 0 0 01 0 1
LF 0 0 0 0 012 0 12
0 0 0 0 0 025 25TotalRIGHT OF WAY
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 014 0 14
HSP 0 0 0 0 01,245 0 1,245
0 0 0 0 0 01,269 1,269TotalCONSTRUCTION
SA 0 100 0 0 00 0 100
0 100 0 0 0 00 100TotalALTERNATIVE CONTRACTING INCENTIVES
$1,603Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,603433283Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 473 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4332861
District:
County:
INTERSECTION IMPROVEMENT
SR 992/SW 152 STREET FROM SW 93 AVENUE TO SR 5/US-1
Roadway ID:
Project Length: 0.158
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87039000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0105 0 105
DIH 0 0 0 0 015 0 15
DS 0 0 0 0 010 0 10
HSP 0 0 0 0 0135 0 135
0 0 0 0 0 0265 265TotalPLANNING AND DESIGN
LF 7 0 0 0 00 0 7
7 0 0 0 0 00 7TotalRAILROAD & UTILITIES
DDR 329 0 0 0 00 0 329
DIH 38 0 0 0 00 0 38
HSP 726 0 0 0 00 0 726
SA 410 0 0 0 00 0 410
1,503 0 0 0 0 00 1,503TotalCONSTRUCTION
$1,775Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,554433286Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 474 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4332862
District:
County:
RESURFACING
SR 992/SW 152 STREET FROM SR 821 HEFT NB RAMP TO SW 93RD AVENUE
Roadway ID:
Project Length: 2.208
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87039000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSA 0 0 0 0 0477 0 477
DDR 0 0 0 0 0128 0 128
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 010 0 10
0 0 0 0 0 0625 625TotalPLANNING AND DESIGN
LF 5 0 0 0 00 0 5
5 0 0 0 0 00 5TotalRAILROAD & UTILITIES
DDR 51 0 0 0 00 0 51
DIH 137 0 0 0 00 0 137
DS 21 0 0 0 00 0 21
SA 1,940 0 0 0 00 0 1,940
2,149 0 0 0 0 00 2,149TotalCONSTRUCTION
$2,779Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,554433286Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 475 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4333781
District:
County:
BRIDGE - PAINTING
SR A1A/COLLINS AVE AT BAKER HAULOVER CUT CHANNEL-BAKER HAULOVER BR
Roadway ID:
Project Length: 0.240
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87060000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 0355 0 355
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 039 0 39
0 0 0 0 0 0404 404TotalPLANNING AND DESIGN
BRRP 0 0 0 0 050 0 50
DIH 0 0 0 0 021 0 21
DS 0 0 0 0 0110 0 110
0 0 0 0 0 0181 181TotalRIGHT OF WAY
BRRP 923 0 0 0 04,470 0 5,393
DDR 0 0 0 0 02,087 0 2,087
DIH 0 0 0 0 0208 0 208
923 0 0 0 0 06,765 7,688TotalCONSTRUCTION
$8,273Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,273433378Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 476 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334251
District:
County:
LANDSCAPING
SR 823/NW 57 AVENUE FROM NW 183 ST/MIAMI GDNS TO MIAMI-DADE/BROWRD LIN
Roadway ID:
Project Length: 2.130
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87002000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 015 0 15
DS 0 0 0 0 062 0 62
0 0 0 0 0 077 77TotalPLANNING AND DESIGN
DIH 33 0 0 0 012 0 45
DS 0 0 0 0 0802 0 802
33 0 0 0 0 0814 847TotalCONSTRUCTION
$924Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $924433425Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334551
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 FROM SW 37 AVENUE TO PONCE DE LEON
Roadway ID:
Project Length: 0.363
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 057 0 57
DDR 0 0 0 0 0227 0 227
Section A1 - Page 477 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334551
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 FROM SW 37 AVENUE TO PONCE DE LEON
Roadway ID:
Project Length: 0.363
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 071 0 71
DS 0 0 0 0 0119 0 119
HSP 0 0 0 0 0986 0 986
0 0 0 0 0 01,460 1,460TotalPLANNING AND DESIGN
DDR 0 0 0 0 0829 0 829
DIH 0 0 0 0 025 0 25
DS 700 0 0 0 0128 0 828
LF 0 6 0 0 00 0 6
700 6 0 0 0 0982 1,688TotalRIGHT OF WAY
DDR 0 21 0 0 00 0 21
DIH 0 171 0 0 00 0 171
HSP 0 4,217 0 0 00 0 4,217
SA 0 317 0 0 00 0 317
0 4,726 0 0 0 00 4,726TotalCONSTRUCTION
HSP 0 0 120 0 00 0 120
0 0 120 0 0 00 120TotalALTERNATIVE CONTRACTING INCENTIVES
$7,994Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,965433455Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 478 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334552
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 AT RIVIERA DRIVE
Roadway ID:
Project Length: 0.200
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 023 0 23
DIH 0 0 0 0 025 0 25
DS 0 0 0 0 062 0 62
HSP 0 0 0 0 0405 0 405
0 0 0 0 0 0515 515TotalPLANNING AND DESIGN
DDR 184 0 0 0 00 0 184
DIH 0 0 0 0 012 0 12
DS 30 0 0 0 033 0 63
HSP 0 0 0 0 0170 0 170
214 0 0 0 0 0215 429TotalRIGHT OF WAY
DIH 0 71 0 0 00 0 71
DS 0 113 0 0 00 0 113
HSP 0 769 0 0 00 0 769
SA 0 361 0 0 00 0 361
0 1,314 0 0 0 00 1,314TotalCONSTRUCTION
HSP 0 0 30 0 00 0 30
0 0 30 0 0 00 30TotalALTERNATIVE CONTRACTING INCENTIVES
Section A1 - Page 479 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$2,288Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,965433455Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334553
District:
County:
RESURFACING
SR 5/US-1/S DIXIE HWY FROM RIVIERA DR TO SW 27 AVE (WITH EXCEPTION)
Roadway ID:
Project Length: 1.966
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 50 0 0 0 00 0 50
SA 550 0 0 0 00 0 550
600 0 0 0 0 00 600TotalPLANNING AND DESIGN
DDR 0 0 655 0 00 0 655
DIH 0 0 63 0 00 0 63
DS 0 0 1,540 0 00 0 1,540
NHRE 0 0 157 0 00 0 157
SA 0 0 2,010 0 00 0 2,010
0 0 4,425 0 0 00 4,425TotalCONSTRUCTION
$5,025Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,965433455Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 480 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334554
District:
County:
RESURFACING
SR 5/US-1/S DIXIE HWY FROM EAST OF SR 9/SW 26 AVENUE
TO SR 9A/I-95
Roadway ID:
Project Length: 1.839
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 50 0 0 0 00 0 50
SA 530 0 0 0 00 0 530
580 0 0 0 0 00 580TotalPLANNING AND DESIGN
DDR 0 0 0 599 00 0 599
DIH 0 0 0 56 00 0 56
DS 0 0 0 3,423 00 0 3,423
0 0 0 4,078 0 00 4,078TotalCONSTRUCTION
$4,658Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $19,965433455Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334851
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 AT GRAND AVENUE
Roadway ID:
Project Length: 0.089
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 025 0 25
Section A1 - Page 481 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334851
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 AT GRAND AVENUE
Roadway ID:
Project Length: 0.089
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 06 0 6
HSP 0 0 0 0 067 0 67
0 0 0 0 0 098 98TotalPLANNING AND DESIGN
DIH 0 0 0 0 04 0 4
DS 0 0 0 0 018 0 18
HSP 18 0 0 0 088 0 106
18 0 0 0 0 0110 128TotalCONSTRUCTION
$226Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $226433485Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334891
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 AT SW 104 STREET
Roadway ID:
Project Length: 0.587
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87020000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 040 0 40
Section A1 - Page 482 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334891
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 AT SW 104 STREET
Roadway ID:
Project Length: 0.587
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87020000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 087 0 87
HSP 0 0 0 0 0253 0 253
0 0 0 0 0 0380 380TotalPLANNING AND DESIGN
DIH 0 0 0 0 09 0 9
0 0 0 0 0 09 9TotalRIGHT OF WAY
DS 51 0 0 0 00 0 51
HSP 0 53 0 0 00 0 53
HSP 1,561 152 0 0 00 0 1,713
SA 93 0 0 0 00 0 93
SA 781 0 0 0 00 0 781
2,486 205 0 0 0 00 2,691TotalCONSTRUCTION
$3,080Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,080433489Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 483 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4334901
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 FROM SANTONA STREET TO EAST OF GRANADA BLVD
Roadway ID:
Project Length: 1.004
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 039 0 39
DS 0 0 0 0 034 0 34
HSP 0 0 0 0 0211 0 211
0 0 0 0 0 0284 284TotalPLANNING AND DESIGN
DIH 0 0 0 0 013 0 13
0 0 0 0 0 013 13TotalRIGHT OF WAY
DIH 0 0 0 0 035 0 35
DS 0 0 0 0 040 0 40
DS 0 0 0 0 01 0 1
HSP 113 0 0 0 0722 0 835
113 0 0 0 0 0798 911TotalCONSTRUCTION
$1,208Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,208433490Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 484 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4335341
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS OPERATIONS HARDWARE/SOFTWARE AND REPLACEMENT EQUIPMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 0194 0 194
DITS 0 125 125 125 125227 375 1,102
DS 125 0 0 0 0127 0 252
DSBD 0 0 0 0 054 0 54
125 125 125 125 125 375602 1,602TotalCAPITAL
$1,602Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,602433534Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4344431
District:
County:
SIDEWALK
SR 9336/SW 344 ST FROM W OF SW 187 AVENUE TO E OF SW 182 AVENUE
Roadway ID:
Project Length: 0.631
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87160000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 025 0 25
DIH 0 0 0 0 074 0 74
DS 0 0 0 0 07 0 7
Section A1 - Page 485 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4344431
District:
County:
SIDEWALK
SR 9336/SW 344 ST FROM W OF SW 187 AVENUE TO E OF SW 182 AVENUE
Roadway ID:
Project Length: 0.631
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87160000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0106 106TotalPLANNING AND DESIGN
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 0100 0 100
0 0 0 0 0 0110 110TotalRIGHT OF WAY
DIH 13 0 0 0 00 0 13
DS 255 0 0 0 00 0 255
268 0 0 0 0 00 268TotalCONSTRUCTION
$484Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $484434443Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 486 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4346051
District:
County:
PD&E/EMO STUDY
91 ST/SURFSIDE ST INDIAN CREEK BRIDGE BRIDGE# 876100
Roadway ID:
Project Length: 0.068
Lanes Exist:Lanes Improved:Lanes Added:
4
2
MIAMI-DADE
LRTP Ref:
87000202
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SU 0 1,515 0 0 00 0 1,515
0 1,515 0 0 0 00 1,515TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,515Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,515434605Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4346641
District:
County:
SAFETY PROJECT
DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIES CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 8 0 00 0 8
DS 0 300 400 300 2000 0 1,200
0 300 408 300 200 00 1,208TotalPLANNING AND DESIGN
$1,208Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,208434664Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 487 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4346761
District:
County:
OTHER ITS
SR 9A/I-95 EXPRESS OPERATIONS & MAINTENANCE INCIDENT MGMT/RD RANGERS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 0 0 5 0 00 0 5
0 0 5 0 0 00 5TotalCONSTRUCTION
TOBD 0 0 3,900 3,900 3,9000 0 11,700
0 0 3,900 3,900 3,900 00 11,700TotalOPERATIONS
$11,705Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,705434676Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4346921
District:
County:
BIKE LANE/SIDEWALK
SOUTH MIAMI AVENUE FROM SW 10 STREET TO SW 9 STREET
Roadway ID:
Project Length: 0.065
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87067510
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 075 0 75
0 0 0 0 0 075 75TotalPLANNING AND DESIGN
LF 0 0 25 0 00 0 25
Section A1 - Page 488 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4346921
District:
County:
BIKE LANE/SIDEWALK
SOUTH MIAMI AVENUE FROM SW 10 STREET TO SW 9 STREET
Roadway ID:
Project Length: 0.065
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87067510
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 5 0 00 0 5
TALU 0 0 400 0 00 0 400
0 0 430 0 0 00 430TotalCONSTRUCTION
$505Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $505434692Item Number:
RESPONSIBLE AGENCY: CITY OF MIAMI
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347661
District:
County:
INTERSECTION IMPROVEMENT
SR 953/LEJEUNE ROAD AT BIRD ROAD
Roadway ID:
Project Length: 0.091
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87281000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 050 0 50
DIH 0 0 0 0 037 0 37
DS 0 0 0 0 077 0 77
Section A1 - Page 489 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347661
District:
County:
INTERSECTION IMPROVEMENT
SR 953/LEJEUNE ROAD AT BIRD ROAD
Roadway ID:
Project Length: 0.091
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87281000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HSP 0 0 0 0 0200 0 200
0 0 0 0 0 0364 364TotalPLANNING AND DESIGN
DIH 0 0 0 0 010 0 10
DS 20 0 0 0 063 0 83
HSP 0 0 0 0 02,164 0 2,164
20 0 0 0 0 02,237 2,257TotalRIGHT OF WAY
DIH 0 32 0 0 00 0 32
DS 0 11 0 0 00 0 11
HSP 0 732 0 0 00 0 732
0 775 0 0 0 00 775TotalCONSTRUCTION
$3,396Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,396434766Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 490 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347681
District:
County:
INTERSECTION IMPROVEMENT
SR 932/NW 103 STREET FROM SR 826 TO WEST 12TH AVENUE
Roadway ID:
Project Length: 1.078
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87038000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 043 0 43
DS 0 0 0 0 0194 0 194
HSP 0 0 0 0 0294 0 294
0 0 0 0 0 0531 531TotalPLANNING AND DESIGN
DIH 0 0 0 0 040 0 40
DS 0 0 0 0 0234 0 234
0 0 0 0 0 0274 274TotalRIGHT OF WAY
DIH 26 0 0 0 00 0 26
DS 21 21 0 0 00 0 42
HSP 506 53 0 0 00 0 559
553 74 0 0 0 00 627TotalCONSTRUCTION
$1,432Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,383434768Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 491 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347682
District:
County:
INTERSECTION IMPROVEMENT
SR 932/NW 103 STREET FROM E OF WEST 12 AVENUE TO EAST 5 AVENUE
Roadway ID:
Project Length: 2.243
Lanes Exist:Lanes Improved:Lanes Added:
5
5
MIAMI-DADE
LRTP Ref:
87038000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 015 0 15
DS 0 0 0 0 0256 0 256
0 0 0 0 0 0271 271TotalPLANNING AND DESIGN
DDR 591 63 0 0 00 0 654
DIH 26 0 0 0 00 0 26
617 63 0 0 0 00 680TotalCONSTRUCTION
$951Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,383434768Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347691
District:
County:
INTERSECTION IMPROVEMENT
SR 953/LEJEUNE ROAD FROM SW 2 STREET TO NW 11 STREET
Roadway ID:
Project Length: 0.863
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87281000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 026 0 26
DS 0 0 0 0 014 0 14
Section A1 - Page 492 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347691
District:
County:
INTERSECTION IMPROVEMENT
SR 953/LEJEUNE ROAD FROM SW 2 STREET TO NW 11 STREET
Roadway ID:
Project Length: 0.863
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87281000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HSP 0 0 0 0 0262 0 262
0 0 0 0 0 0302 302TotalPLANNING AND DESIGN
DIH 0 0 0 0 036 0 36
DS 0 200 0 0 088 0 288
DSBD 2,301 0 0 0 00 0 2,301
2,301 200 0 0 0 0124 2,625TotalRIGHT OF WAY
DIH 0 39 0 0 00 0 39
DS 0 73 0 0 00 0 73
HSP 0 707 0 0 00 0 707
0 819 0 0 0 00 819TotalCONSTRUCTION
$3,746Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,746434769Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 493 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347711
District:
County:
INTERSECTION IMPROVEMENT
SR 976/BIRD ROAD FROM SW 57TH AVENUE TO ALHAMBRA CIRCLE
Roadway ID:
Project Length: 0.300
Lanes Exist:Lanes Improved:Lanes Added:
5
5
MIAMI-DADE
LRTP Ref:
87044000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 033 0 33
DIH 0 0 0 0 011 0 11
DS 0 0 0 0 013 0 13
HSP 0 0 0 0 0227 0 227
0 0 0 0 0 0284 284TotalPLANNING AND DESIGN
DIH 0 0 0 0 01 0 1
DS 95 0 0 0 017 0 112
95 0 0 0 0 018 113TotalRIGHT OF WAY
DIH 0 42 0 0 00 0 42
DS 0 58 0 0 00 0 58
HSP 0 981 0 0 00 0 981
SA 0 216 0 0 00 0 216
0 1,297 0 0 0 00 1,297TotalCONSTRUCTION
$1,694Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,694434771Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 494 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347721
District:
County:
INTERSECTION IMPROVEMENT
SR 90/SW 8TH STREET AT SW 67TH AVENUE
Roadway ID:
Project Length: 0.108
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87120000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0183 0 183
DIH 0 0 0 0 039 0 39
DS 0 0 0 0 011 0 11
0 0 0 0 0 0233 233TotalPLANNING AND DESIGN
LF 4 0 0 0 00 0 4
4 0 0 0 0 00 4TotalRAILROAD & UTILITIES
DIH 22 0 0 0 00 0 22
DS 15 0 0 0 00 0 15
HSP 426 0 0 0 00 0 426
463 0 0 0 0 00 463TotalCONSTRUCTION
$700Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $700434772Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 495 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347731
District:
County:
INTERSECTION IMPROVEMENT
SR A1A/COLLINS AVE FROM 4700 BLOCK TO 5800 BLOCK
Roadway ID:
Project Length: 1.279
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
87060000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 0141 0 141
HSP 0 0 0 0 0738 0 738
0 0 0 0 0 0899 899TotalPLANNING AND DESIGN
DIH 25 0 0 0 00 0 25
DS 184 0 0 0 00 0 184
209 0 0 0 0 00 209TotalRIGHT OF WAY
DIH 0 104 0 0 00 0 104
DS 0 148 0 0 00 0 148
HSP 0 2,391 0 0 00 0 2,391
0 2,643 0 0 0 00 2,643TotalCONSTRUCTION
$3,751Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,751434773Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 496 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347761
District:
County:
INTERSECTION IMPROVEMENT
SR 94/KENDALL DRIVE AND SR 985/SW 107 AVENUE
Roadway ID:
Project Length: 0.788
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 044 0 44
DIH 0 0 0 0 047 0 47
DS 0 0 0 0 036 0 36
HSP 0 0 0 0 0302 0 302
0 0 0 0 0 0429 429TotalPLANNING AND DESIGN
LF 13 0 0 0 00 0 13
13 0 0 0 0 00 13TotalRAILROAD & UTILITIES
DIH 43 0 0 0 00 0 43
DS 268 0 0 0 00 0 268
HSP 1,312 116 0 0 00 0 1,428
1,623 116 0 0 0 00 1,739TotalCONSTRUCTION
$2,181Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,181434776Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 497 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4347781
District:
County:
INTERSECTION IMPROVEMENT
SR 112/ARTHUR GODFREY FROM ALTON ROAD TO WEST OF PINE TREE
Roadway ID:
Project Length: 0.585
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87016000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 031 0 31
DIH 0 0 0 0 016 0 16
DS 0 0 0 0 03 0 3
HSP 0 0 0 0 0323 0 323
SA 0 0 0 0 031 0 31
0 0 0 0 0 0404 404TotalPLANNING AND DESIGN
DS 21 0 0 0 00 0 21
HSP 1,396 332 0 0 00 0 1,728
SA 758 0 0 0 00 0 758
2,175 332 0 0 0 00 2,507TotalCONSTRUCTION
$2,911Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,911434778Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 498 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4348454
District:
County:
TRANSPORTATION PLANNING
SR 976/BIRD ROAD FROM SR 821/HEFT TO US 1/SOUTH DIXIE HWY
Roadway ID:
Project Length: 8.466
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87044000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 670 0 0 0 00 0 670
670 0 0 0 0 00 670TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$670Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $670434845Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4349221
District:
County:
NEW BRIDGE - NO ADDED CAPACITY
SR 90/TAMIAMI TRAIL FROM MP 14.038 TO MP 17.230
Roadway ID:
Project Length: 3.192
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87110000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0149 0 149
DS 0 0 0 0 03,722 0 3,722
0 0 0 0 0 03,871 3,871TotalPLANNING AND DESIGN
DIH 0 0 0 0 032 0 32
DS 0 0 0 0 0114 0 114
0 0 0 0 0 0146 146TotalRIGHT OF WAY
Section A1 - Page 499 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4349221
District:
County:
NEW BRIDGE - NO ADDED CAPACITY
SR 90/TAMIAMI TRAIL FROM MP 14.038 TO MP 17.230
Roadway ID:
Project Length: 3.192
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87110000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACEM 0 0 0 0 042,000 0 42,000
DI 7,175 0 0 0 0150 0 7,325
DI 0 0 0 0 053,246 0 53,246
DIH 154 158 108 0 049 0 469
DS 4,231 105 0 0 00 0 4,336
PLH 0 0 0 0 010,000 0 10,000
TIGR 0 0 0 0 020,000 0 20,000
11,560 263 108 0 0 0125,445 137,376TotalDESIGN/BUILD
DS 0 0 0 2,500 00 0 2,500
0 0 0 2,500 0 00 2,500TotalALTERNATIVE CONTRACTING INCENTIVES
$143,893Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $143,893434922Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 500 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4351731
District:
County:
LANDSCAPING
SR 825/SW 137 AVENUE FROM SR 90/SW 8 STREET TO NW 12 STREET
Roadway ID:
Project Length: 1.470
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87134000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 10 0 0 00 0 10
DS 0 80 0 0 00 0 80
0 90 0 0 0 00 90TotalPLANNING AND DESIGN
DIH 0 0 0 17 00 0 17
DS 0 0 0 605 00 0 605
0 0 0 622 0 00 622TotalCONSTRUCTION
$712Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $712435173Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 501 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4352011
District:
County:
TRAFFIC CONTROL DEVICES/SYSTEM
DISTRICT 6 DISTRICTWIDE TRAFFIC SIGNAL SYSTEMS RETIMING PROJECT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,056 0 1,056
0 0 0 0 0 01,056 1,056TotalPLANNING AND DESIGN
$1,056Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,729435201Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4352012
District:
County:
TRAFFIC CONTROL DEVICES/SYSTEM
DISTRICT 6 SIGNAL RETIMING SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 013 0 13
DITS 1,232 1,232 0 0 01,232 0 3,696
1,232 1,232 0 0 0 01,245 3,709TotalPLANNING AND DESIGN
$3,709Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,729435201Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 502 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4352013
District:
County:
TRAFFIC CONTROL DEVICES/SYSTEM
TRAFFIC ENGINEERING DATA COLLECTION - CONTINUING SERVICES CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 500 500 500 500 5000 0 2,500
500 500 500 500 500 00 2,500TotalPLANNING AND DESIGN
$2,500Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,729435201Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4352014
District:
County:
TRAFFIC CONTROL DEVICES/SYSTEM
DISTRICT 6 SIGNAL RETIMING SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DITS 0 0 1,232 1,232 00 0 2,464
0 0 1,232 1,232 0 00 2,464TotalPLANNING AND DESIGN
$2,464Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,729435201Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 503 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4354121
District:
County:
TOLL COLLECTION
I-75 EXPRESS TOLL OPERATIONS MIAMI-DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBG 2,215 2,315 2,350 2,404 2,4152,115 0 13,814
2,215 2,315 2,350 2,404 2,415 02,115 13,814TotalOPERATIONS
$13,814Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,814435412Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4354781
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL N BEACH ELEMENTARY & NAUTILUS MIDDLE SCHOOL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 2 0 0 0 00 0 2
TALU 89 0 0 0 00 0 89
91 0 0 0 0 00 91TotalCONSTRUCTION
$91Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $91435478Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 504 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4354791
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL FEINBERG-FISHER K-8 CENTR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 05 0 5
SE 0 0 0 0 015 0 15
0 0 0 0 0 020 20TotalPLANNING AND DESIGN
SA 2 0 0 0 00 0 2
TALU 161 0 0 0 00 0 161
163 0 0 0 0 00 163TotalCONSTRUCTION
$183Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $183435479Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4354801
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL HIALEAH GARDNS ELEMENTARY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 03 0 3
TALU 0 0 0 0 019 0 19
Section A1 - Page 505 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4354801
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL HIALEAH GARDNS ELEMENTARY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 022 22TotalPLANNING AND DESIGN
SA 2 0 0 0 00 0 2
TALU 147 0 0 0 00 0 147
149 0 0 0 0 00 149TotalCONSTRUCTION
$171Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $171435480Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4354811
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL KINLOCH PARK ELEMENTARY & MIDDLE SCHOOLS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 03 0 3
TALU 0 0 0 0 020 0 20
0 0 0 0 0 023 23TotalPLANNING AND DESIGN
SA 2 0 0 0 00 0 2
Section A1 - Page 506 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4354811
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL KINLOCH PARK ELEMENTARY & MIDDLE SCHOOLS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 155 0 0 0 00 0 155
157 0 0 0 0 00 157TotalCONSTRUCTION
$180Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $180435481Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355051
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI GARDENS NW 191 ST/BETTY FERGUSON RECREATION COMPLEX
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-4
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 0111 0 111
0 0 0 0 0 0111 111TotalPLANNING AND DESIGN
LF 0 219 0 0 00 0 219
Section A1 - Page 507 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355051
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI GARDENS NW 191 ST/BETTY FERGUSON RECREATION COMPLEX
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-4
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 3 0 0 00 0 3
TALT 0 624 0 0 00 0 624
TALU 0 376 0 0 00 0 376
0 1,222 0 0 0 00 1,222TotalCONSTRUCTION
$1,333Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,333435505Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355061
District:
County:
TRAFFIC SIGNAL UPDATE
SR 90/SW 8 STREET TRAFFIC SIGNAL UPDATE PILOT PROJECT
Roadway ID:
Project Length: 7.550
Lanes Exist:Lanes Improved:Lanes Added:
7
MIAMI-DADE
LRTP Ref:
87120000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 035 0 35
0 0 0 0 0 035 35TotalPLANNING AND DESIGN
0 0 0 0 0431 0 431
0 0 0 0 0 0431 431TotalDESIGN/BUILD
Section A1 - Page 508 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355061
District:
County:
TRAFFIC SIGNAL UPDATE
SR 90/SW 8 STREET TRAFFIC SIGNAL UPDATE PILOT PROJECT
Roadway ID:
Project Length: 7.550
Lanes Exist:Lanes Improved:Lanes Added:
7
MIAMI-DADE
LRTP Ref:
87120000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 03,828 0 3,828
0 0 0 0 0 03,828 3,828TotalCAPITAL
$4,294Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,294435506Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355063
District:
County:
TRAFFIC SIGNAL UPDATE
SR 90 ASCT PILOT PROJECT OPERATION OF M-D COUNTY TRAF SIGNAL FACILITY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 600 600 600 600 6000 0 3,000
600 600 600 600 600 00 3,000TotalOPERATIONS
$3,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,294435506Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 509 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355071
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI ALONG NW 17 ST BETWEEN NW 7 AVE AND NW 9 AVE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 25 0 0 0 00 0 25
25 0 0 0 0 00 25TotalPLANNING AND DESIGN
LF 75 0 0 0 00 0 75
SA 3 0 0 0 00 0 3
TALU 123 0 0 0 00 0 123
201 0 0 0 0 00 201TotalCONSTRUCTION
$226Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $226435507Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 510 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355081
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI MIAMI WOMAN'S CLUB BAYWALK
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 198 0 0 00 0 198
SA 0 2 0 0 00 0 2
TALU 0 66 0 0 00 0 66
0 266 0 0 0 00 266TotalCONSTRUCTION
$266Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $266435508Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355091
District:
County:
BIKE PATH/TRAIL
TOWN OF MIAMI LAKES CITYWIDE BICYCLE/ PEDESTRIAN IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 200 0 0 00 0 200
0 200 0 0 0 00 200TotalPLANNING AND DESIGN
LF 0 200 0 0 00 0 200
SA 0 2 0 0 00 0 2
Section A1 - Page 511 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355091
District:
County:
BIKE PATH/TRAIL
TOWN OF MIAMI LAKES CITYWIDE BICYCLE/ PEDESTRIAN IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TALT 0 801 0 0 00 0 801
TALU 0 199 0 0 00 0 199
0 1,202 0 0 0 00 1,202TotalCONSTRUCTION
$1,402Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,402435509Item Number:
RESPONSIBLE AGENCY: Town of Miami Lakes
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355731
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC ENGINEERING SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
DS 350 350 350 350 3501,354 0 3,104
350 350 350 350 350 01,364 3,114TotalPLANNING AND DESIGN
$3,114Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,864435573Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 512 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355732
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE PEDESTRIAN & BICYCLE SAFETY PROGRAM CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 350 350 350 350 3500 0 1,750
350 350 350 350 350 00 1,750TotalPLANNING AND DESIGN
$1,750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,864435573Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4356011
District:
County:
DRAINAGE IMPROVEMENTS
SR 916/NE 135 STREET FROM MP 10.12 TO MP 10.14 (OVER ARCH CREEK)
Roadway ID:
Project Length: 0.020
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 056 0 56
0 0 0 0 0 076 76TotalPLANNING AND DESIGN
DIH 0 0 0 0 021 0 21
0 0 0 0 0 021 21TotalRIGHT OF WAY
DIH 21 0 0 0 070 0 91
Section A1 - Page 513 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4356011
District:
County:
DRAINAGE IMPROVEMENTS
SR 916/NE 135 STREET FROM MP 10.12 TO MP 10.14 (OVER ARCH CREEK)
Roadway ID:
Project Length: 0.020
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87008000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 189 0 0 0 01,587 0 1,776
LF 283 0 0 0 01,983 0 2,266
493 0 0 0 0 03,640 4,133TotalCONSTRUCTION
$4,230Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,230435601Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4357601
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM I-75 TO N OF CANAL C-8 BRDG(APPROX NW 162ST)
Roadway ID:
Project Length: 1.882
Lanes Exist:Lanes Improved:Lanes Added:
3
4
1
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 05,900 0 5,900
DIH 0 0 0 0 0150 0 150
0 0 0 0 0 06,050 6,050TotalPLANNING AND DESIGN
DDR 0 0 0 441 00 300 741
DIH 0 0 0 50 500 53 153
Section A1 - Page 514 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4357601
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM I-75 TO N OF CANAL C-8 BRDG(APPROX NW 162ST)
Roadway ID:
Project Length: 1.882
Lanes Exist:Lanes Improved:Lanes Added:
3
4
1
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
DSBD 0 0 0 0 4,6000 0 4,600
SU 0 0 0 10,050 5,7000 5,000 20,750
0 0 0 10,541 10,350 5,3530 26,244TotalRIGHT OF WAY
$32,294Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $297,445435760Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4357602
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM N OF CANAL C-8 BRDG(162ST)
TO E OF NW 67 AVE
Roadway ID:
Project Length: 1.263
Lanes Exist:Lanes Improved:Lanes Added:
6
6
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 200 0 0 0 00 0 200
DSBD 6,300 0 0 0 00 0 6,300
6,500 0 0 0 0 00 6,500TotalPLANNING AND DESIGN
Section A1 - Page 515 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4357602
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM N OF CANAL C-8 BRDG(162ST)
TO E OF NW 67 AVE
Roadway ID:
Project Length: 1.263
Lanes Exist:Lanes Improved:Lanes Added:
6
6
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
DI 0 0 0 0 00 5,200 5,200
DIH 0 0 0 0 550 50 105
DSBD 0 0 0 0 4,1130 0 4,113
0 0 0 0 4,168 5,2500 9,418TotalRIGHT OF WAY
ACNP 0 0 0 0 00 94,235 94,235
DDR 0 0 0 0 00 7,864 7,864
DI 0 0 0 0 00 3,500 3,500
DIH 0 0 0 0 00 657 657
0 0 0 0 0 106,2560 106,256TotalCONSTRUCTION
$122,174Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $297,445435760Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 516 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4357603
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM E OF NW 67 AVE TO E OF NW 57 AVE
Roadway ID:
Project Length: 0.963
Lanes Exist:Lanes Improved:Lanes Added:
6
6
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 5,300 0 0 0 00 0 5,300
DIH 200 0 0 0 00 0 200
5,500 0 0 0 0 00 5,500TotalPLANNING AND DESIGN
DI 0 0 0 0 00 11,400 11,400
DIH 0 0 0 0 1000 197 297
DSBD 0 0 0 0 7,9640 0 7,964
0 0 0 0 8,064 11,5970 19,661TotalRIGHT OF WAY
$25,161Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $297,445435760Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 517 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4357604
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM E OF NW 57 AVE TO E OF NW 42 AVE
Roadway ID:
Project Length: 1.400
Lanes Exist:Lanes Improved:Lanes Added:
6
6
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 6,500 0 0 0 00 0 6,500
SA 200 400 0 0 00 0 600
6,700 400 0 0 0 00 7,100TotalPLANNING AND DESIGN
$7,100Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $297,445435760Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4357605
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM E OF NW 42 AVE TO E OF NW 32 AVE
Roadway ID:
Project Length: 0.900
Lanes Exist:Lanes Improved:Lanes Added:
6
6
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-24
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 4,400 0 0 0 00 0 4,400
DIH 200 100 0 0 00 0 300
4,600 100 0 0 0 00 4,700TotalPLANNING AND DESIGN
$4,700Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $297,445435760Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 518 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4357606
District:
County:
ADD LANES & RECONSTRUCT
SR 826/PALMETTO EXPY FROM E OF NW 32 AVE TO W OF NW 17 AVE
Roadway ID:
Project Length: 1.240
Lanes Exist:Lanes Improved:Lanes Added:
6
8
4
MIAMI-DADE
LRTP Ref:
87260000
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 6,700 0 0 0 00 0 6,700
DIH 200 0 0 0 00 0 200
6,900 0 0 0 0 00 6,900TotalPLANNING AND DESIGN
DI 0 0 0 0 00 4,488 4,488
DIH 0 0 0 0 950 100 195
DSBD 0 0 0 0 3,5410 0 3,541
0 0 0 0 3,636 4,5880 8,224TotalRIGHT OF WAY
ACNP 0 0 0 0 00 73,777 73,777
DDR 0 0 0 0 00 7,033 7,033
DI 0 0 0 0 00 5,288 5,288
STED 0 0 0 0 00 4,794 4,794
0 0 0 0 0 90,8920 90,892TotalCONSTRUCTION
$106,016Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $297,445435760Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 519 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4358431
District:
County:
NEW ROAD CONSTRUCTION
SR 112/I-195 FRONTAGE RD/RAMP EXTENSN (MIAMI DESIGN DISTRICT)
Roadway ID:
Project Length: 0.510
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87004000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 0237 0 237
DS 0 0 0 0 0146 0 146
0 0 0 0 0 0383 383TotalPLANNING AND DESIGN
LF 0 4 0 0 00 0 4
0 4 0 0 0 00 4TotalRAILROAD & UTILITIES
ACNP 0 4,280 0 0 00 0 4,280
DDR 410 0 0 0 00 0 410
DIH 154 15 0 0 00 0 169
564 4,295 0 0 0 00 4,859TotalCONSTRUCTION
DS 0 180 0 0 00 0 180
0 180 0 0 0 00 180TotalALTERNATIVE CONTRACTING INCENTIVES
$5,426Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,426435843Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 520 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4361991
District:
County:
TECHNICAL ASSISTANCE
SR 93/I-75 EXPRESS LANES TOLLING AND OPERATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBG 100 500 600 600 6000 0 2,400
100 500 600 600 600 00 2,400TotalOPERATIONS
$2,400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,400436199Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362001
District:
County:
TECHNICAL ASSISTANCE
SR 826/PALMETTO EXPY EXPRESS LANES TOLLING & RAMP SIGNALING OPERATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBI 800 1,500 1,700 1,700 1,7000 0 7,400
800 1,500 1,700 1,700 1,700 00 7,400TotalOPERATIONS
$7,400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,400436200Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 521 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362021
District:
County:
OTHER ITS
SR 9A/I-95 EXPRESS OPERATIONS & MAINTENANCE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBD 0 637 656 675 6960 0 2,664
0 637 656 675 696 00 2,664TotalOPERATIONS
$2,664Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,664436202Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362031
District:
County:
OTHER ITS
SR 826/PALMETTO EXPY ITS CONTRACT FOR MAINTENANE OF TOLLING EQUIPMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBI 0 200 400 412 4240 0 1,436
0 200 400 412 424 00 1,436TotalOPERATIONS
$1,436Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,436436203Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 522 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362041
District:
County:
OTHER ITS
SR 93/I-75 EXPRESS LANES ITS MAINTENANCE OF TOLLING EQUIPMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBG 0 100 200 206 2120 0 718
0 100 200 206 212 00 718TotalOPERATIONS
$718Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $718436204Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362071
District:
County:
OTHER ITS
SR 826/PALMETTO EXPRESSWAY INCIDENT MGMT/ROAD RANGER SERVICE PATROLS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBI 0 1,641 0 0 00 0 1,641
0 1,641 0 0 0 00 1,641TotalOPERATIONS
$1,641Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,641436207Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 523 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362081
District:
County:
OTHER ITS
SR 93/I-75 EXPR LANES INCIDENT MANAGEMENT/ROAD RANGER SERVICE PATROLS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBG 0 837 0 0 00 0 837
0 837 0 0 0 00 837TotalOPERATIONS
$837Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $837436208Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362091
District:
County:
OTHER ITS
SR 826/PALMETTO EXPY INCIDENT MANAGEMENT ROAD RANGER SERVICE PATROLS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBI 0 0 2,282 2,282 2,2820 0 6,846
0 0 2,282 2,282 2,282 00 6,846TotalOPERATIONS
$6,846Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,846436209Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 524 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362101
District:
County:
OTHER ITS
SR 93/I-75 EXPRESS LANES INCIDENT MANAGMNT/ROAD RANGER SERVICE PATROLS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBG 0 0 1,673 1,673 1,6730 0 5,019
0 0 1,673 1,673 1,673 00 5,019TotalOPERATIONS
$5,019Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,019436210Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362121
District:
County:
OTHER ITS
SR 826/PALMETTO EXPRESSWAY FHP ENHANCED ENFORCEMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBI 0 200 400 400 4000 0 1,400
0 200 400 400 400 00 1,400TotalOPERATIONS
$1,400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,400436212Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 525 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4362131
District:
County:
OTHER ITS
SR 93/I-75 EXPRESS LANES FHP ENHANCED ENFORCEMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TOBG 0 100 200 200 2000 0 700
0 100 200 200 200 00 700TotalOPERATIONS
$700Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $700436213Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363101
District:
County:
INTERSECTION IMPROVEMENT
SR 973/SW 87 AVENUE FROM SW 14 STREET TO N OF SW 4 STREET
Roadway ID:
Project Length: 0.690
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87047000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 015 0 15
HSP 0 0 0 0 0198 0 198
0 0 0 0 0 0213 213TotalPLANNING AND DESIGN
DDR 0 31 0 0 00 0 31
DIH 0 26 0 0 00 0 26
Section A1 - Page 526 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363101
District:
County:
INTERSECTION IMPROVEMENT
SR 973/SW 87 AVENUE FROM SW 14 STREET TO N OF SW 4 STREET
Roadway ID:
Project Length: 0.690
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87047000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HSP 0 399 0 0 00 0 399
0 456 0 0 0 00 456TotalCONSTRUCTION
$669Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $669436310Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363111
District:
County:
INTERSECTION IMPROVEMENT
SR 90/SW 8 STREET FROM EAST OF SW 90 AVENUE TO EAST OF SW 86 COURT
Roadway ID:
Project Length: 0.610
Lanes Exist:Lanes Improved:Lanes Added:
8
8
MIAMI-DADE
LRTP Ref:
87120000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 030 0 30
HSP 0 0 0 0 0194 0 194
0 0 0 0 0 0224 224TotalPLANNING AND DESIGN
Section A1 - Page 527 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363111
District:
County:
INTERSECTION IMPROVEMENT
SR 90/SW 8 STREET FROM EAST OF SW 90 AVENUE TO EAST OF SW 86 COURT
Roadway ID:
Project Length: 0.610
Lanes Exist:Lanes Improved:Lanes Added:
8
8
MIAMI-DADE
LRTP Ref:
87120000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 16 0 0 00 0 16
HSP 0 1,075 0 0 00 0 1,075
0 1,091 0 0 0 00 1,091TotalCONSTRUCTION
$1,315Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,315436311Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363121
District:
County:
INTERSECTION IMPROVEMENT
SR 7/NW 2 AVENUE AT NW 199 STREET
Roadway ID:
Project Length: 0.166
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87140000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 047 0 47
DS 0 0 0 0 018 0 18
0 0 0 0 0 065 65TotalPLANNING AND DESIGN
Section A1 - Page 528 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363121
District:
County:
INTERSECTION IMPROVEMENT
SR 7/NW 2 AVENUE AT NW 199 STREET
Roadway ID:
Project Length: 0.166
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87140000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0214 0 214
DIH 0 0 0 0 018 0 18
0 0 0 0 0 0232 232TotalRIGHT OF WAY
DDR 484 73 0 0 00 0 557
DIH 31 0 0 0 00 0 31
DS 268 0 0 0 00 0 268
783 73 0 0 0 00 856TotalCONSTRUCTION
$1,153Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,153436312Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363131
District:
County:
INTERSECTION IMPROVEMENT
SR 25/OKEECHOBEE RD FROM N OF NW 186 STREET TO S OF NW 170 STREET
Roadway ID:
Project Length: 0.568
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 024 0 24
Section A1 - Page 529 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363131
District:
County:
INTERSECTION IMPROVEMENT
SR 25/OKEECHOBEE RD FROM N OF NW 186 STREET TO S OF NW 170 STREET
Roadway ID:
Project Length: 0.568
Lanes Exist:Lanes Improved:Lanes Added:
4
4
MIAMI-DADE
LRTP Ref:
87090000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 025 0 25
DS 0 0 0 0 067 0 67
0 0 0 0 0 0116 116TotalPLANNING AND DESIGN
DIH 0 0 0 0 010 0 10
DS 10 0 0 0 00 0 10
DS 0 0 0 0 052 0 52
HSP 25 0 0 0 0288 0 313
35 0 0 0 0 0350 385TotalCONSTRUCTION
$501Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $501436313Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 530 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363421
District:
County:
RESURFACING
SR 990/SW 112 STREET FROM SW 97 AVENUE TO US 1/S DIXIE HIGHWAY
Roadway ID:
Project Length: 1.712
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87046000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0288 0 288
DIH 0 0 0 0 077 0 77
DS 0 0 0 0 01 0 1
0 0 0 0 0 0366 366TotalPLANNING AND DESIGN
DDR 0 870 0 0 00 0 870
SA 0 1,511 0 0 00 0 1,511
0 2,381 0 0 0 00 2,381TotalCONSTRUCTION
$2,747Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,747436342Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363431
District:
County:
RESURFACING
SR 990/KILLIAN PARKWAY FROM WEST OF KENDALE BLVD
TO SW 97 AVENUE
Roadway ID:
Project Length: 0.813
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87046000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0410 0 410
Section A1 - Page 531 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363431
District:
County:
RESURFACING
SR 990/KILLIAN PARKWAY FROM WEST OF KENDALE BLVD
TO SW 97 AVENUE
Roadway ID:
Project Length: 0.813
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87046000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 052 0 52
DS 0 0 0 0 01 0 1
0 0 0 0 0 0463 463TotalPLANNING AND DESIGN
DDR 0 1,515 0 0 00 0 1,515
DIH 0 87 0 0 00 0 87
DS 0 142 0 0 00 0 142
0 1,744 0 0 0 00 1,744TotalCONSTRUCTION
$2,207Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,207436343Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363551
District:
County:
RESURFACING
SR 976/SW 40 ST FROM E OF SW 102 AVE TO E OF SW 87 AVE/GALLOWAY RD
Roadway ID:
Project Length: 1.596
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 030 0 30
Section A1 - Page 532 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363551
District:
County:
RESURFACING
SR 976/SW 40 ST FROM E OF SW 102 AVE TO E OF SW 87 AVE/GALLOWAY RD
Roadway ID:
Project Length: 1.596
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 0253 0 253
0 0 0 0 0 0283 283TotalPLANNING AND DESIGN
DIH 0 74 0 0 00 0 74
DS 0 4,290 774 0 00 0 5,064
0 4,364 774 0 0 00 5,138TotalCONSTRUCTION
$5,421Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,904436355Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363552
District:
County:
RESURFACING
SR 976/SW 40 ST FROM EAST OF SW 117 AVENUE
TO EAST OF SW 102 AVENUE
Roadway ID:
Project Length: 1.504
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 324 0 0 0 00 0 324
DIH 59 0 0 0 00 0 59
Section A1 - Page 533 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363552
District:
County:
RESURFACING
SR 976/SW 40 ST FROM EAST OF SW 117 AVENUE
TO EAST OF SW 102 AVENUE
Roadway ID:
Project Length: 1.504
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
383 0 0 0 0 00 383TotalPLANNING AND DESIGN
DIH 0 0 0 44 00 0 44
DS 0 0 0 3,056 00 0 3,056
0 0 0 3,100 0 00 3,100TotalCONSTRUCTION
$3,483Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,904436355Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363851
District:
County:
INTERSECTION IMPROVEMENT
SR 9/NW 27 AVENUE AT NW 17TH STREET
Roadway ID:
Project Length: 0.147
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87240000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
HSP 0 0 0 0 0215 0 215
0 0 0 0 0 0225 225TotalPLANNING AND DESIGN
DDR 0 0 0 0 047 0 47
Section A1 - Page 534 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363851
District:
County:
INTERSECTION IMPROVEMENT
SR 9/NW 27 AVENUE AT NW 17TH STREET
Roadway ID:
Project Length: 0.147
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87240000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 06 0 6
0 0 0 0 0 053 53TotalRIGHT OF WAY
DIH 0 11 0 0 00 0 11
DS 0 0 16 0 00 0 16
HSP 0 379 38 0 00 0 417
0 390 54 0 0 00 444TotalCONSTRUCTION
$722Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $722436385Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363861
District:
County:
INTERSECTION IMPROVEMENT
SR 976/BIRD ROAD AT SW 97 AVENUE
Roadway ID:
Project Length: 0.144
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87044000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 015 0 15
Section A1 - Page 535 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4363861
District:
County:
INTERSECTION IMPROVEMENT
SR 976/BIRD ROAD AT SW 97 AVENUE
Roadway ID:
Project Length: 0.144
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87044000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 0139 0 139
0 0 0 0 0 0154 154TotalPLANNING AND DESIGN
DDR 0 0 0 0 023 0 23
DIH 0 0 0 0 024 0 24
DS 0 0 0 0 05 0 5
0 0 0 0 0 052 52TotalRIGHT OF WAY
DIH 0 11 0 0 00 0 11
DS 0 26 16 0 00 0 42
HSP 0 320 49 0 00 0 369
SA 0 223 0 0 00 0 223
0 580 65 0 0 00 645TotalCONSTRUCTION
$851Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $851436386Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 536 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4364041
District:
County:
INTERSECTION IMPROVEMENT
SR 934/E 25 ST/NW 79 ST FROM E 4 AVE/NW 47 AVE TO E 12 AVE/NW 37 AVE
Roadway ID:
Project Length: 0.995
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87080900
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 030 0 30
DS 0 0 0 0 02 0 2
HSP 0 0 0 0 0372 0 372
0 0 0 0 0 0404 404TotalPLANNING AND DESIGN
DDR 165 0 0 0 00 0 165
DDR 0 0 15 0 00 0 15
DIH 31 0 0 0 00 0 31
DS 0 0 0 0 05 0 5
196 0 15 0 0 05 216TotalRIGHT OF WAY
DIH 0 0 22 0 00 0 22
DS 0 0 32 0 00 0 32
HSP 0 0 1,063 0 00 0 1,063
0 0 1,117 0 0 00 1,117TotalCONSTRUCTION
$1,737Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,737436404Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 537 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4364261
District:
County:
TRANSPORTATION PLANNING
SR 948/NW 36 ST FROM SR 826/PALMETTO EXPY
TO SR 953/NW 42 AVE/LEJEUNE
Roadway ID:
Project Length: 3.705
Lanes Exist:Lanes Improved:Lanes Added:
6
6
MIAMI-DADE
LRTP Ref:
87220000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 500 0 0 00 0 500
DIH 0 5 0 0 00 0 5
0 505 0 0 0 00 505TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$505Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $825436426Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4364262
District:
County:
PTO STUDIES
SR 25/NW 36 STREET FROM NW 36 AVENUE TO SR 5/US-1
Roadway ID:
Project Length: 4.070
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 20 0 00 0 20
DS 0 0 300 0 00 0 300
0 0 320 0 0 00 320TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$320Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $825436426Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 538 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4364321
District:
County:
LANDSCAPING
SR 5/US-1/S DIXIE HIGHWAY FROM SW 80 STREET TO SW 57 AVENUE
Roadway ID:
Project Length: 1.222
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 012 0 12
DS 0 0 0 0 0169 0 169
0 0 0 0 0 0181 181TotalPLANNING AND DESIGN
DIH 0 0 0 0 047 0 47
DS 108 0 0 0 0529 0 637
108 0 0 0 0 0576 684TotalCONSTRUCTION
$865Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $865436432Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4364791
District:
County:
INTERSECTION IMPROVEMENT
SR 934/NW 74 STREET FROM SR 826/PALMETTO EXPWY
TO SR 25/OKEECHOBEE RD
Roadway ID:
Project Length: 1.468
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87000234
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 0 0 0 0 0550 0 550
DIH 0 0 0 0 010 0 10
Section A1 - Page 539 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4364791
District:
County:
INTERSECTION IMPROVEMENT
SR 934/NW 74 STREET FROM SR 826/PALMETTO EXPWY
TO SR 25/OKEECHOBEE RD
Roadway ID:
Project Length: 1.468
Lanes Exist:Lanes Improved:Lanes Added:
2
2
MIAMI-DADE
LRTP Ref:
87000234
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 066 0 66
0 0 0 0 0 0626 626TotalPLANNING AND DESIGN
ACNP 0 250 0 0 00 0 250
DIH 0 6 4 0 00 0 10
DS 0 80 12 0 00 0 92
SA 0 785 500 0 00 0 1,285
0 1,121 516 0 0 00 1,637TotalRIGHT OF WAY
ACNP 0 0 0 3,729 00 0 3,729
DIH 0 0 0 333 00 0 333
DS 0 0 0 67 00 0 67
0 0 0 4,129 0 00 4,129TotalCONSTRUCTION
$6,392Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,392436479Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 540 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365221
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR A1A/MACARTHUR CAUSEWAY EAST BRIDGE # 870077
Roadway ID:
Project Length: 0.399
Lanes Exist:Lanes Improved:Lanes Added:
5
MIAMI-DADE
LRTP Ref:
87060000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 0549 0 549
DIH 0 0 0 0 030 0 30
0 0 0 0 0 0579 579TotalPLANNING AND DESIGN
DS 0 100 0 0 00 0 100
0 100 0 0 0 00 100TotalENVIRONMENTAL
BRRP 0 7,204 1,481 0 00 0 8,685
DIH 0 137 0 0 00 0 137
0 7,341 1,481 0 0 00 8,822TotalCONSTRUCTION
$9,501Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,501436522Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 541 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365251
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 826/PALMETTO EXPWY OVER INTRACOASTAL CANAL BRIDGES 870592, 870593
Roadway ID:
Project Length: 0.532
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87170000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 0408 0 408
DIH 0 0 0 0 035 0 35
0 0 0 0 0 0443 443TotalPLANNING AND DESIGN
BRRP 0 0 0 50 00 0 50
0 0 0 50 0 00 50TotalENVIRONMENTAL
BRRP 0 0 0 5,106 00 0 5,106
DIH 0 0 0 78 00 0 78
0 0 0 5,184 0 00 5,184TotalCONSTRUCTION
$5,677Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,677436525Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 542 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365261
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 934/NE 79 ST OVER INTRACOASTAL CANAL 4 BRDGS: 870082;-554;-085;551
Roadway ID:
Project Length: 1.900
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87080000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 0641 0 641
DIH 0 0 0 0 035 0 35
0 0 0 0 0 0676 676TotalPLANNING AND DESIGN
BRRP 0 0 0 0 4,8740 0 4,874
DIH 0 0 0 0 800 0 80
0 0 0 0 4,954 00 4,954TotalCONSTRUCTION
$5,630Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,630436526Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365271
District:
County:
BRIDGE - PAINTING
SR 90/US-41/BRICKELL AVENUE OVER MIAMI RIVER BRIDGE # 870759
Roadway ID:
Project Length: 0.058
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 0428 0 428
DIH 0 0 0 0 040 0 40
Section A1 - Page 543 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365271
District:
County:
BRIDGE - PAINTING
SR 90/US-41/BRICKELL AVENUE OVER MIAMI RIVER BRIDGE # 870759
Roadway ID:
Project Length: 0.058
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0468 468TotalPLANNING AND DESIGN
BRRP 0 4,499 926 0 00 0 5,425
DIH 0 74 0 0 00 0 74
0 4,573 926 0 0 00 5,499TotalCONSTRUCTION
$5,967Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,967436527Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365281
District:
County:
BRIDGE - PAINTING
SR 970/DOWNTOWN DISTRIBUTOR AT I-95 NB TO SR 970 EB BRIDGE # 870472
Roadway ID:
Project Length: 0.492
Lanes Exist:Lanes Improved:Lanes Added:
1
MIAMI-DADE
LRTP Ref:
87006000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 0107 0 107
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 010 0 10
0 0 0 0 0 0137 137TotalPLANNING AND DESIGN
Section A1 - Page 544 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365281
District:
County:
BRIDGE - PAINTING
SR 970/DOWNTOWN DISTRIBUTOR AT I-95 NB TO SR 970 EB BRIDGE # 870472
Roadway ID:
Project Length: 0.492
Lanes Exist:Lanes Improved:Lanes Added:
1
MIAMI-DADE
LRTP Ref:
87006000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 171 0 0 0 0866 0 1,037
DDR 0 0 0 0 0107 0 107
DIH 0 0 0 0 035 0 35
171 0 0 0 0 01,008 1,179TotalCONSTRUCTION
$1,316Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,316436528Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365291
District:
County:
BRIDGE - PAINTING
SR 9A/I-95 NW 65 STREET PEDESTRIAN BRIDGE BRIDGE# 879007
Roadway ID:
Project Length: 0.003
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 080 0 80
DIH 0 0 0 0 06 0 6
Section A1 - Page 545 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365291
District:
County:
BRIDGE - PAINTING
SR 9A/I-95 NW 65 STREET PEDESTRIAN BRIDGE BRIDGE# 879007
Roadway ID:
Project Length: 0.003
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87270000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 06 0 6
0 0 0 0 0 092 92TotalPLANNING AND DESIGN
BRRP 122 0 0 0 0569 0 691
DDR 0 0 0 0 071 0 71
DIH 0 0 0 0 010 0 10
122 0 0 0 0 0650 772TotalCONSTRUCTION
$864Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $864436529Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365331
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 112/JULIA TUTTLE CAUSEWAY/I-195 OVER BISCAYNE BAY BRIDGE # 870302
Roadway ID:
Project Length: 0.216
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87004000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 0121 0 121
DIH 0 0 0 0 07 0 7
Section A1 - Page 546 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365331
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 112/JULIA TUTTLE CAUSEWAY/I-195 OVER BISCAYNE BAY BRIDGE # 870302
Roadway ID:
Project Length: 0.216
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87004000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 0128 128TotalPLANNING AND DESIGN
BRRP 0 0 945 0 00 0 945
DIH 0 0 22 0 00 0 22
0 0 967 0 0 00 967TotalCONSTRUCTION
$1,095Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,095436533Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365351
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 907/ALTON ROAD AT DADE BLVD BRIDGE # 870665 OVER COLLINS CANAL
Roadway ID:
Project Length: 0.007
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87037000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 049 0 49
DIH 0 0 0 0 015 0 15
0 0 0 0 0 064 64TotalPLANNING AND DESIGN
BRRP 0 0 655 0 00 0 655
Section A1 - Page 547 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365351
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 907/ALTON ROAD AT DADE BLVD BRIDGE # 870665 OVER COLLINS CANAL
Roadway ID:
Project Length: 0.007
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87037000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 27 0 00 0 27
0 0 682 0 0 00 682TotalCONSTRUCTION
$746Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $746436535Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365361
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 933/NW 12 AVENUE OVER MIAMI RIVER BRIDGE # 871005
Roadway ID:
Project Length: 0.118
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87085000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 095 0 95
DIH 0 0 0 0 020 0 20
0 0 0 0 0 0115 115TotalPLANNING AND DESIGN
BRRP 0 0 560 0 00 0 560
DIH 0 0 38 0 00 0 38
Section A1 - Page 548 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365361
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 933/NW 12 AVENUE OVER MIAMI RIVER BRIDGE # 871005
Roadway ID:
Project Length: 0.118
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87085000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 598 0 0 00 598TotalCONSTRUCTION
$713Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $713436536Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365371
District:
County:
BRIDGE-REPAIR/REHABILITATION
SR 9/NW 27 AVENUE OVER MIAMI RIVER BRIDGES 870731 & 870763
Roadway ID:
Project Length: 0.072
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87240000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 300 0 0 0 00 0 300
DIH 20 0 0 0 00 0 20
320 0 0 0 0 00 320TotalPLANNING AND DESIGN
BRRP 0 0 0 0 4,0850 0 4,085
DIH 0 0 0 0 800 0 80
0 0 0 0 4,165 00 4,165TotalCONSTRUCTION
Section A1 - Page 549 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$4,485Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,485436537Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365381
District:
County:
BRIDGE - PAINTING
SR 860/MIAMI GARDENS DRIVE OVER SNAKE CREEK CANAL BRIDGE # 870624
Roadway ID:
Project Length: 0.161
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87026000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 040 0 40
DIH 0 0 0 0 05 0 5
0 0 0 0 0 045 45TotalPLANNING AND DESIGN
BRRP 0 0 279 0 00 0 279
DIH 0 0 11 0 00 0 11
0 0 290 0 0 00 290TotalCONSTRUCTION
$335Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $335436538Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 550 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365391
District:
County:
BRIDGE - PAINTING
SR 856/WM LEHMAN CSWAY OVER INTRACOASTAL CANAL BRIDGES 870606 & 870607
Roadway ID:
Project Length: 0.028
Lanes Exist:Lanes Improved:Lanes Added:
3
MIAMI-DADE
LRTP Ref:
87210000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 205 0 0 0 00 0 205
DIH 10 0 0 0 00 0 10
215 0 0 0 0 00 215TotalPLANNING AND DESIGN
BRRP 0 0 0 2,725 00 0 2,725
DIH 0 0 0 33 00 0 33
0 0 0 2,758 0 00 2,758TotalCONSTRUCTION
$2,973Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,973436539Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365401
District:
County:
BRIDGE - PAINTING
SR 5/US-1 OVER CORAL GABLES CANAL BRIDGE # 870019
Roadway ID:
Project Length: 0.017
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRRP 0 0 0 0 040 0 40
DIH 0 0 0 0 07 0 7
Section A1 - Page 551 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4365401
District:
County:
BRIDGE - PAINTING
SR 5/US-1 OVER CORAL GABLES CANAL BRIDGE # 870019
Roadway ID:
Project Length: 0.017
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87030000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 047 47TotalPLANNING AND DESIGN
BRRP 0 0 390 0 00 0 390
DIH 0 0 11 0 00 0 11
0 0 401 0 0 00 401TotalCONSTRUCTION
$448Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $448436540Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366031
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL WALK SAFE EDUCATIONAL COMPONENT & DISSEMINATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACSA 0 0 0 0 05 0 5
LF 0 0 0 0 075 0 75
Section A1 - Page 552 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366031
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL WALK SAFE EDUCATIONAL COMPONENT & DISSEMINATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 427 0 0 0 0213 0 640
427 0 0 0 0 0293 720TotalPLANNING
$720Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $720436603Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366091
District:
County:
SIDEWALK
CITY OF MIAMI - METROMOVER STATION ACCESS IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 075 0 75
0 0 0 0 0 075 75TotalPLANNING AND DESIGN
LF 0 25 0 0 00 0 25
Section A1 - Page 553 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366091
District:
County:
SIDEWALK
CITY OF MIAMI - METROMOVER STATION ACCESS IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 5 0 0 00 0 5
TALU 0 362 0 0 00 0 362
0 392 0 0 0 00 392TotalCONSTRUCTION
$467Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $467436609Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366181
District:
County:
BIKE LANE/SIDEWALK
TOWN OF MIAMI LAKES - SIDEWALK IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 182 0 00 0 182
SA 0 0 5 0 00 0 5
TALU 0 0 600 0 00 0 600
0 0 787 0 0 00 787TotalCONSTRUCTION
Section A1 - Page 554 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$787Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $787436618Item Number:
RESPONSIBLE AGENCY: Town of Miami Lakes
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366241
District:
County:
SIDEWALK
SR 922/NE 125 STREET - DOWNTOWN NORTH MIAMI PEDESTRIAN ENHANCEMENT
Roadway ID:
Project Length: 0.505
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87066000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 25 0 0 0 00 0 25
25 0 0 0 0 00 25TotalPLANNING AND DESIGN
LF 0 0 0 113 00 0 113
SA 0 0 0 5 00 0 5
TALT 0 0 0 80 00 0 80
TALU 0 0 0 691 00 0 691
0 0 0 889 0 00 889TotalCONSTRUCTION
$914Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $914436624Item Number:
RESPONSIBLE AGENCY: City of North Miami
Section A1 - Page 555 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366251
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
CITY OF AVENTURA - COUNTRY CLUB DRIVE PEDESTRIAN SAFETY IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
TALU 490 0 0 0 00 0 490
495 0 0 0 0 00 495TotalCONSTRUCTION
$495Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $495436625Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4367361
District:
County:
BIKE LANE/SIDEWALK
CITY OF HIALEAH - WEST 4TH AVE SIDEWALK & GUARDRAIL IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 05 0 5
TALU 0 0 0 0 082 0 82
0 0 0 0 0 087 87TotalPLANNING AND DESIGN
SA 0 0 5 0 00 0 5
TALT 0 0 455 0 00 0 455
Section A1 - Page 556 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4367361
District:
County:
BIKE LANE/SIDEWALK
CITY OF HIALEAH - WEST 4TH AVE SIDEWALK & GUARDRAIL IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 0 0 451 0 00 0 451
0 0 911 0 0 00 911TotalCONSTRUCTION
$998Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $998436736Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4367481
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI BEACH - PEDESTRIAN AND BICYCLE PATHWAY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-4
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 12,000 0 00 0 12,000
SA 0 0 5 0 00 0 5
TALT 0 0 297 0 00 0 297
Section A1 - Page 557 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4367481
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI BEACH - PEDESTRIAN AND BICYCLE PATHWAY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-4
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 0 0 703 0 00 0 703
0 0 13,005 0 0 00 13,005TotalCONSTRUCTION
$13,005Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,005436748Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4367541
District:
County:
PEDESTRIAN/WILDLIFE UNDERPASS
SNAKE CREEK TRAIL UNDERPASS PRELIMINARY ENGINEERING STUDY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 5 00 0 5
TALU 0 0 0 300 00 0 300
0 0 0 305 0 00 305TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
Section A1 - Page 558 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$305Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $305436754Item Number:
RESPONSIBLE AGENCY: Miami-Dade County Parks & Recreation
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4368771
District:
County:
TRAFFIC OPS IMPROVEMENT
SR 997/KROME AVENUE FROM SR 5/US-1 TO SR 25/OKEECHOBEE ROAD (FHP)
Roadway ID:
Project Length: 36.705
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 02 0 2
DIH 0 0 0 0 019 0 19
DS 670 670 462 254 2541,120 0 3,430
670 670 462 254 254 01,141 3,451TotalCONSTRUCTION
$3,451Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,451436877Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4369331
District:
County:
LANDSCAPING
SR 934/NW 82 STREET FROM NW 13 COURT TO MIAMI AVENUE
Roadway ID:
Project Length: 1.549
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87080001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
DS 0 0 0 0 046 0 46
Section A1 - Page 559 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4369331
District:
County:
LANDSCAPING
SR 934/NW 82 STREET FROM NW 13 COURT TO MIAMI AVENUE
Roadway ID:
Project Length: 1.549
Lanes Exist:Lanes Improved:Lanes Added:
2
MIAMI-DADE
LRTP Ref:
87080001
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 056 56TotalPLANNING AND DESIGN
DDR 36 0 0 0 0138 0 174
DIH 0 0 0 0 015 0 15
36 0 0 0 0 0153 189TotalCONSTRUCTION
$245Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $245436933Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4369391
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CUTLER BAY ACADEMY OF ADVANCE STUDIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 05 0 5
TALU 0 0 0 0 055 0 55
0 0 0 0 0 060 60TotalPLANNING AND DESIGN
SA 5 0 0 0 00 0 5
Section A1 - Page 560 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4369391
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CUTLER BAY ACADEMY OF ADVANCE STUDIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 353 0 0 0 00 0 353
358 0 0 0 0 00 358TotalCONSTRUCTION
$418Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $418436939Item Number:
RESPONSIBLE AGENCY: Town of Cutler Bay
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4369401
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CITRUS GROVE;FAIRLAWN;SHENANDOAH;SILVER BLUFF ELEM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
TALU 76 0 0 0 00 0 76
81 0 0 0 0 00 81TotalPLANNING AND DESIGN
Section A1 - Page 561 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4369401
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CITRUS GROVE;FAIRLAWN;SHENANDOAH;SILVER BLUFF ELEM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 5 0 0 00 0 5
TALU 0 514 0 0 00 0 514
0 519 0 0 0 00 519TotalCONSTRUCTION
$600Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $600436940Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4369411
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL JMS BRIGHT/JW JHNSN;MORNINGSDE;NATHN YNG;SUNY ISLE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
TALU 55 0 0 0 00 0 55
60 0 0 0 0 00 60TotalPLANNING AND DESIGN
SA 0 44 0 0 00 0 44
TALU 0 336 0 0 00 0 336
Section A1 - Page 562 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4369411
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL JMS BRIGHT/JW JHNSN;MORNINGSDE;NATHN YNG;SUNY ISLE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
0 380 0 0 0 00 380TotalCONSTRUCTION
$440Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $440436941Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4374751
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 90/US-41/SW 8 STREET FROM SR 9/SW 27 AVENUE TO SW 1ST AVENUE
Roadway ID:
Project Length: 2.706
Lanes Exist:Lanes Improved:Lanes Added:
3
3
MIAMI-DADE
LRTP Ref:
87120000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 050 0 50
0 0 0 0 0 050 50TotalPLANNING AND DESIGN
LF 15 0 0 0 00 0 15
15 0 0 0 0 00 15TotalRAILROAD & UTILITIES
DIH 21 0 0 0 00 0 21
DS 2,237 211 0 0 00 0 2,448
2,258 211 0 0 0 00 2,469TotalCONSTRUCTION
Section A1 - Page 563 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$2,534Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,534437475Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4377061
District:
County:
TRAFFIC SIGNALS
SR 25/US 27/OKEECHOBEE ROAD AT NW 138TH STREET
Roadway ID:
Project Length: 0.100
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 0177 0 177
0 0 0 0 0 0197 197TotalPLANNING AND DESIGN
LF 3 0 0 0 00 0 3
3 0 0 0 0 00 3TotalRAILROAD & UTILITIES
DDR 0 174 0 0 00 0 174
DI 1,151 0 0 0 00 0 1,151
DIH 21 0 0 0 00 0 21
1,172 174 0 0 0 00 1,346TotalCONSTRUCTION
$1,546Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,546437706Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 564 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4377111
District:
County:
TOLL COLLECTION
SR 9A/I-95 EXPRESS LANES SAFETY GATE CLOSURE SYSTEM PILOT PROJECT
Roadway ID:
Project Length: 11.583
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DSBD 85 0 0 0 00 0 85
85 0 0 0 0 00 85TotalDESIGN/BUILD
DSBD 500 0 0 0 00 0 500
500 0 0 0 0 00 500TotalCAPITAL
$585Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $585437711Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4377221
District:
County:
BRIDGE REPLACEMENT
NORTH MIAMI AVE BRIDGE 874127 OVER LITTLE RIVER CANAL REPLACEMENT
Roadway ID:
Project Length: 0.017
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACBR 0 0 14 0 00 0 14
LF 0 0 147 0 00 0 147
0 0 161 0 0 00 161TotalPLANNING AND DESIGN
Section A1 - Page 565 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4377221
District:
County:
BRIDGE REPLACEMENT
NORTH MIAMI AVE BRIDGE 874127 OVER LITTLE RIVER CANAL REPLACEMENT
Roadway ID:
Project Length: 0.017
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACBR 0 0 0 0 2,2070 0 2,207
LF 0 0 0 0 7110 0 711
0 0 0 0 2,918 00 2,918TotalCONSTRUCTION
$3,079Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,079437722Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4377821
District:
County:
PD&E/EMO STUDY
SR 968/FLAGLER ST FROM SR 821/HEFT TO SR 5/BISCAYNE BLVD (BRT STUDY)
Roadway ID:
Project Length: 15.357
Lanes Exist:Lanes Improved:Lanes Added:
1
3
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 1,900 400 0 0 01,000 0 3,300
Section A1 - Page 566 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4377821
District:
County:
PD&E/EMO STUDY
SR 968/FLAGLER ST FROM SR 821/HEFT TO SR 5/BISCAYNE BLVD (BRT STUDY)
Roadway ID:
Project Length: 15.357
Lanes Exist:Lanes Improved:Lanes Added:
1
3
MIAMI-DADE
LRTP Ref:
87053000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 100 50 0 0 035 0 185
2,000 450 0 0 0 01,035 3,485TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,485Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,485437782Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4377841
District:
County:
PD&E/EMO STUDY
SR 94/KENDALL DR FROM SR 997/KROME AVE TO SR 5/S DIXIE HWY (BRT STUDY)
Roadway ID:
Project Length: 10.700
Lanes Exist:Lanes Improved:Lanes Added:
2
6
MIAMI-DADE
LRTP Ref:
87001000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 1,900 400 0 0 01,000 0 3,300
DIH 100 50 0 0 035 0 185
2,000 450 0 0 0 01,035 3,485TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
Section A1 - Page 567 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$3,485Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,485437784Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4377921
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 90/SW 7 STREET FROM SR 9/SW 27 AVENUE TO SR 5/BRICKELL AVENUE
Roadway ID:
Project Length: 2.998
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0187 0 187
DIH 0 0 0 0 010 0 10
0 0 0 0 0 0197 197TotalPLANNING AND DESIGN
DIH 0 11 0 0 00 0 11
DS 0 791 0 0 00 0 791
0 802 0 0 0 00 802TotalCONSTRUCTION
$999Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $999437792Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 568 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4378731
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 5/US-1/SOUTH DIXIE HIGHWAY AT SW 200TH STREET
Roadway ID:
Project Length: 0.247
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0130 0 130
DIH 0 0 0 0 010 0 10
0 0 0 0 0 0140 140TotalPLANNING AND DESIGN
DIH 0 11 0 0 00 0 11
DS 0 14 0 0 00 0 14
HSP 0 483 0 0 00 0 483
0 508 0 0 0 00 508TotalCONSTRUCTION
$648Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $648437873Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 569 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379111
District:
County:
TRAFFIC SIGNAL UPDATE
NHS INTERMODAL DATA COLLECTION FOR SIGNAL RETIMING
Roadway ID:
Project Length: 11.709
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACNP 1,005 0 0 0 00 0 1,005
1,005 0 0 0 0 00 1,005TotalPLANNING AND DESIGN
$1,005Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,005437911Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379151
District:
County:
INTERSECTION IMPROVEMENT
SR 5/BISCAYNE BLVD FROM SE 2ND STREET TO NE 11TH TERRACE
Roadway ID:
Project Length: 0.932
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 0146 0 146
0 0 0 0 0 0166 166TotalPLANNING AND DESIGN
DIH 0 0 11 0 00 0 11
DS 0 0 13 0 00 0 13
Section A1 - Page 570 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379151
District:
County:
INTERSECTION IMPROVEMENT
SR 5/BISCAYNE BLVD FROM SE 2ND STREET TO NE 11TH TERRACE
Roadway ID:
Project Length: 0.932
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HSP 0 0 736 0 00 0 736
0 0 760 0 0 00 760TotalCONSTRUCTION
$926Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $926437915Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379161
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 934/NORMANDY DRIVE AT RUE GRANVILLE
Roadway ID:
Project Length: 0.105
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 0 0 0 04 0 14
HSP 130 0 0 0 00 0 130
140 0 0 0 0 04 144TotalPLANNING AND DESIGN
Section A1 - Page 571 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379161
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 934/NORMANDY DRIVE AT RUE GRANVILLE
Roadway ID:
Project Length: 0.105
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 5 0 00 0 5
DS 0 0 11 0 00 0 11
HSP 0 0 280 0 00 0 280
0 0 296 0 0 00 296TotalCONSTRUCTION
$440Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $440437916Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379171
District:
County:
INTERSECTION IMPROVEMENT
SR 25/OKEECHOBEE ROAD AT WEST 16TH AVENUE
Roadway ID:
Project Length: 0.247
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 0 0 0 00 0 10
HSP 150 0 0 0 00 0 150
Section A1 - Page 572 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379171
District:
County:
INTERSECTION IMPROVEMENT
SR 25/OKEECHOBEE ROAD AT WEST 16TH AVENUE
Roadway ID:
Project Length: 0.247
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
160 0 0 0 0 00 160TotalPLANNING AND DESIGN
DIH 0 5 0 0 00 0 5
DS 0 7 0 0 00 0 7
HSP 0 80 0 0 00 0 80
0 92 0 0 0 00 92TotalRIGHT OF WAY
DIH 0 0 11 0 00 0 11
DS 0 0 5 6 00 0 11
HSP 0 0 410 84 00 0 494
0 0 426 90 0 00 516TotalCONSTRUCTION
$768Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $768437917Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 573 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379181
District:
County:
INTERSECTION IMPROVEMENT
SR 5/US-1 AT SW 22 AVENUE
Roadway ID:
Project Length: 0.169
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 020 0 20
DS 0 0 0 0 0147 0 147
0 0 0 0 0 0167 167TotalPLANNING AND DESIGN
DIH 0 10 0 0 00 0 10
DS 0 82 0 0 00 0 82
0 92 0 0 0 00 92TotalRIGHT OF WAY
DIH 0 0 11 0 00 0 11
DS 0 0 18 0 00 0 18
HSP 0 0 896 0 00 0 896
0 0 925 0 0 00 925TotalCONSTRUCTION
$1,184Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,184437918Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 574 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379201
District:
County:
INTERSECTION IMPROVEMENT
SR 973/NW 87 AVENUE FROM SOUTH OF NW 7 ST TO NW 800 BLOCK
Roadway ID:
Project Length: 0.264
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 015 0 15
DS 0 0 0 0 0177 0 177
0 0 0 0 0 0192 192TotalPLANNING AND DESIGN
DIH 0 0 16 0 00 0 16
DS 0 0 14 0 00 0 14
HSP 0 0 784 0 00 0 784
0 0 814 0 0 00 814TotalCONSTRUCTION
$1,006Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,006437920Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379211
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 817/NW 27 AVENUE FROM NW 171 STREET TO NW 177 STREET
Roadway ID:
Project Length: 0.379
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 088 0 88
Section A1 - Page 575 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379211
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 817/NW 27 AVENUE FROM NW 171 STREET TO NW 177 STREET
Roadway ID:
Project Length: 0.379
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
0 0 0 0 0 098 98TotalPLANNING AND DESIGN
DIH 10 0 0 0 00 0 10
DS 2 0 0 0 00 0 2
HSP 85 0 0 0 00 0 85
97 0 0 0 0 00 97TotalRIGHT OF WAY
DDR 0 0 11 0 00 0 11
DIH 0 11 0 0 00 0 11
HSP 0 316 69 0 00 0 385
0 327 80 0 0 00 407TotalCONSTRUCTION
$602Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $602437921Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 576 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379221
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SR 9/NW 27 AVENUE FROM NW 23 STREET TO NW 26 STREET
Roadway ID:
Project Length: 0.153
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 0 0 0 00 0 10
HSP 130 0 0 0 00 0 130
140 0 0 0 0 00 140TotalPLANNING AND DESIGN
DIH 0 21 0 0 00 0 21
DS 0 6 0 0 00 0 6
HSP 0 84 0 0 00 0 84
SA 0 63 0 0 00 0 63
0 174 0 0 0 00 174TotalRIGHT OF WAY
DDR 0 0 0 11 00 0 11
DIH 0 0 0 11 00 0 11
DS 0 0 0 6 00 0 6
HSP 0 0 0 476 00 0 476
0 0 0 504 0 00 504TotalCONSTRUCTION
$818Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $818437922Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 577 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4379231
District:
County:
INTERSECTION IMPROVEMENT
SR 976/SW 40 STREET FROM SW 11500 BLOCK TO SW 107 AVENUE
Roadway ID:
Project Length: 1.042
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 20 0 0 0 00 0 20
HSP 210 0 0 0 00 0 210
230 0 0 0 0 00 230TotalPLANNING AND DESIGN
DDR 0 39 0 0 00 0 39
DIH 0 15 0 0 00 0 15
HSP 0 150 0 0 00 0 150
0 204 0 0 0 00 204TotalRIGHT OF WAY
DDR 0 0 0 22 00 0 22
DIH 0 0 0 17 00 0 17
DS 0 0 0 6 00 0 6
HSP 0 0 0 918 00 0 918
0 0 0 963 0 00 963TotalCONSTRUCTION
$1,397Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,397437923Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 578 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380281
District:
County:
TRANSPORTATION PLANNING
SR 25/US 27/OKEECHOBEE RD FROM NW 72 AVE/W 12 AVE TO SE 4 AVE/E DR
Roadway ID:
Project Length: 3.335
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 45 0 00 0 45
DS 0 0 500 0 00 0 500
0 0 545 0 0 00 545TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$545Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $545438028Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380341
District:
County:
LANDSCAPING
SR 997/KROME AVENUE FROM SW 296 STREET TO SW 232 STREET
Roadway ID:
Project Length: 3.672
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 10 00 0 10
DS 0 0 0 140 00 0 140
0 0 0 150 0 00 150TotalPLANNING AND DESIGN
DDR 0 0 0 0 00 1,128 1,128
DIH 0 0 0 0 00 14 14
Section A1 - Page 579 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380341
District:
County:
LANDSCAPING
SR 997/KROME AVENUE FROM SW 296 STREET TO SW 232 STREET
Roadway ID:
Project Length: 3.672
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 0 0 0 00 199 199
0 0 0 0 0 1,3410 1,341TotalCONSTRUCTION
$1,491Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,363438034Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380342
District:
County:
LANDSCAPING
SR 997/KROME AVENUE FROM SW 232 STREET TO SW 184TH STREET
Roadway ID:
Project Length: 3.251
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 10 0 00 0 10
DS 0 0 145 0 00 0 145
0 0 155 0 0 00 155TotalPLANNING AND DESIGN
Section A1 - Page 580 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380342
District:
County:
LANDSCAPING
SR 997/KROME AVENUE FROM SW 232 STREET TO SW 184TH STREET
Roadway ID:
Project Length: 3.251
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 140 0 14
DS 0 0 0 0 1,0010 140 1,141
0 0 0 0 1,015 1400 1,155TotalCONSTRUCTION
$1,310Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,363438034Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380343
District:
County:
LANDSCAPING
SR 997/KROME AVENUE FROM SW 184 STREET TO SW 136 STREET
Roadway ID:
Project Length: 3.039
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 135 0 00 0 135
DIH 0 0 10 0 00 0 10
0 0 145 0 0 00 145TotalPLANNING AND DESIGN
Section A1 - Page 581 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380343
District:
County:
LANDSCAPING
SR 997/KROME AVENUE FROM SW 184 STREET TO SW 136 STREET
Roadway ID:
Project Length: 3.039
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 1,0580 0 1,058
DIH 0 0 0 0 140 0 14
0 0 0 0 1,072 00 1,072TotalCONSTRUCTION
$1,217Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,363438034Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380344
District:
County:
LANDSCAPING
SR 997/KROME AVENUE FROM SW 136 STREET TO SW 88 STREET
Roadway ID:
Project Length: 3.544
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 0 0 0 00 0 10
DS 140 0 0 0 00 0 140
150 0 0 0 0 00 150TotalPLANNING AND DESIGN
DIH 0 0 0 13 00 0 13
DS 0 0 0 1,182 00 0 1,182
Section A1 - Page 582 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380344
District:
County:
LANDSCAPING
SR 997/KROME AVENUE FROM SW 136 STREET TO SW 88 STREET
Roadway ID:
Project Length: 3.544
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 1,195 0 00 1,195TotalCONSTRUCTION
$1,345Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,363438034Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380561
District:
County:
LANDSCAPING
SR 968/WEST FLAGLER STREET FROM SW 27 AVENUE TO SW 14 AVENUE
Roadway ID:
Project Length: 1.297
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 0 0 0 00 0 10
DS 20 0 0 0 00 0 20
30 0 0 0 0 00 30TotalPLANNING AND DESIGN
DIH 0 13 0 0 00 0 13
DS 0 153 0 0 00 0 153
0 166 0 0 0 00 166TotalCONSTRUCTION
Section A1 - Page 583 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
$196Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $750438056Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380562
District:
County:
LANDSCAPING
SR 968/WEST FLAGLER STREET FROM SW 14 AVENUE TO SW 2 AVENUE
Roadway ID:
Project Length: 1.285
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 5 0 0 0 00 0 5
DS 20 0 0 0 00 0 20
25 0 0 0 0 00 25TotalPLANNING AND DESIGN
DDR 0 100 0 0 00 0 100
DIH 0 11 0 0 00 0 11
DS 0 35 0 0 00 0 35
0 146 0 0 0 00 146TotalCONSTRUCTION
$171Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $750438056Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 584 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380563
District:
County:
LANDSCAPING
SR 986/SW 1 STREET FROM FLAGLER TO SW 17 AVENUE
Roadway ID:
Project Length: 0.767
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 5 0 0 0 00 0 5
DS 20 0 0 0 00 0 20
25 0 0 0 0 00 25TotalPLANNING AND DESIGN
DDR 0 122 0 0 00 0 122
DIH 0 11 0 0 00 0 11
DS 0 21 0 0 00 0 21
0 154 0 0 0 00 154TotalCONSTRUCTION
$179Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $750438056Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380564
District:
County:
LANDSCAPING
SR 968/SW 1 STREET FROM SW 17 AVENUE TO SW 6 AVENUE
Roadway ID:
Project Length: 1.129
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 5 0 0 00 0 5
Section A1 - Page 585 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380564
District:
County:
LANDSCAPING
SR 968/SW 1 STREET FROM SW 17 AVENUE TO SW 6 AVENUE
Roadway ID:
Project Length: 1.129
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 20 0 0 00 0 20
0 25 0 0 0 00 25TotalPLANNING AND DESIGN
DDR 0 0 168 0 00 0 168
DIH 0 0 11 0 00 0 11
0 0 179 0 0 00 179TotalCONSTRUCTION
$204Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $750438056Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 586 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4380761
District:
County:
PD&E/EMO STUDY
SR 9/NW 27 AVE FROM MIAMI INTERMODAL CENTER
TO NW 215 ST / UNITY STATION (PTC STUDY)
Roadway ID:
Project Length: 14.147
Lanes Exist:Lanes Improved:Lanes Added:
2
3
MIAMI-DADE
LRTP Ref:
87240000
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 1,900 400 0 0 01,000 0 3,300
DIH 100 50 0 0 035 0 185
2,000 450 0 0 0 01,035 3,485TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,485Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,485438076Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4382631
District:
County:
BIKE LANE/SIDEWALK
SR 924/NW 119 STREET FROM I-95 TO WEST DIXIE HIGHWAY
Roadway ID:
Project Length: 1.017
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
0 0 0 0 0 010 10TotalPLANNING AND DESIGN
DIH 62 0 0 0 00 0 62
DS 587 0 0 0 00 0 587
649 0 0 0 0 00 649TotalRIGHT OF WAY
Section A1 - Page 587 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4382631
District:
County:
BIKE LANE/SIDEWALK
SR 924/NW 119 STREET FROM I-95 TO WEST DIXIE HIGHWAY
Roadway ID:
Project Length: 1.017
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 11 0 0 00 0 11
DS 0 642 0 0 00 0 642
0 653 0 0 0 00 653TotalCONSTRUCTION
$1,312Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,312438263Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4383141
District:
County:
DYNAMIC MESSAGE SIGN
ITS FIELD EQUIPMENT COMMUNICATIONS SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 137 0 0 0 00 0 137
137 0 0 0 0 00 137TotalOPERATIONS
$137Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $307438314Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 588 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4383142
District:
County:
DYNAMIC MESSAGE SIGN
ITS FIELD EQUIPMENT ELECTRIC SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 170 0 0 0 00 0 170
170 0 0 0 0 00 170TotalOPERATIONS
$170Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $307438314Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4385211
District:
County:
TRANSPORTATION PLANNING
SR 953/NW 42 AVENUE WITH SR 948/NW 36 STREET AND SR 25/OKEECHOBEE ROAD
Roadway ID:
Project Length: 3.583
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 750 0 0 0 00 0 750
750 0 0 0 0 00 750TotalPLANNING
$750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $750438521Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 589 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4385401
District:
County:
TRAFFIC SIGNAL UPDATE
SR 9A/ I-95 INTERCHANGES ASCT PHASE II PILOT PROJECT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 21 0 0 0 00 0 21
DITS 800 0 0 0 00 0 800
DS 0 152 0 0 00 0 152
821 152 0 0 0 00 973TotalDESIGN/BUILD
$973Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $973438540Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386111
District:
County:
TRANSPORTATION PLANNING
SR 5/US 1 FROM SW 344 STREET/PALM DRIVE
TO SR 992/SW 152 STREET
Roadway ID:
Project Length: 16.484
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 1,500 0 0 00 0 1,500
0 1,500 0 0 0 00 1,500TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,500Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,500438611Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 590 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386381
District:
County:
RAIL SAFETY PROJECT
NW 121ST WAY RAILROAD AT RAILROAD XING# 272768V
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
RHP 330 0 0 0 00 0 330
330 0 0 0 0 00 330TotalRAILROAD & UTILITIES
$330Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $330438638Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386401
District:
County:
RAIL SAFETY PROJECT
NW 22ND AVENUE AT RAILROAD XING# 628320N
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
RHP 137 0 0 0 00 0 137
137 0 0 0 0 00 137TotalRAILROAD & UTILITIES
$137Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $137438640Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 591 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386421
District:
County:
RAIL SAFETY PROJECT
SR 817/NW 27 AVENUE AT RAILROAD XING# 628321V
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
RHP 129 0 0 0 00 0 129
129 0 0 0 0 00 129TotalRAILROAD & UTILITIES
$129Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $129438642Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386431
District:
County:
RAIL SAFETY PROJECT
SR 916/NW 135TH STREET AT RAILROAD XING# 628334W
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
RHP 99 0 0 0 00 0 99
99 0 0 0 0 00 99TotalRAILROAD & UTILITIES
$99Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $99438643Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 592 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386441
District:
County:
RAIL SAFETY PROJECT
SR 944/NW 54 STREET AT RAILROAD XING# 628355P
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
RHP 145 0 0 0 00 0 145
145 0 0 0 0 00 145TotalRAILROAD & UTILITIES
$145Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $145438644Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386451
District:
County:
RAIL SAFETY PROJECT
NW 46TH STREET/SE 8TH STREET AT RAILROAD XING# 628360L
Roadway ID:
Project Length: 0.001
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
RHP 119 0 0 0 00 0 119
119 0 0 0 0 00 119TotalRAILROAD & UTILITIES
$119Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $119438645Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 593 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386461
District:
County:
RAIL SAFETY PROJECT
NW NORTH RIVER DRIVE AT RAILROAD XING# 628378W
Roadway ID:
Project Length: 0.010
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
RHP 124 0 0 0 00 0 124
124 0 0 0 0 00 124TotalRAILROAD & UTILITIES
$124Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $124438646Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4392181
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE GENERAL ENGINEERING CONSULTANT FOR MODAL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 010 0 10
DS 30 0 0 0 00 0 30
30 0 0 0 0 010 40TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$40Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $40439218Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 594 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4392281
District:
County:
DRAINAGE IMPROVEMENTS
SR A1A/INDIAN CREEK DRIVE DRAINAGE MITIGATION PROJECT
Roadway ID:
Project Length: 1.161
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0152 0 152
0 0 0 0 0 0152 152TotalPLANNING AND DESIGN
$152Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $25,152439228Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4392282
District:
County:
DRAINAGE IMPROVEMENTS
SR A1A/INDIAN CREEK DRIVE DRAINAGE MITIGATION PROJECT
Roadway ID:
Project Length: 1.161
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 17,568 0 0 0 00 0 17,568
Section A1 - Page 595 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4392282
District:
County:
DRAINAGE IMPROVEMENTS
SR A1A/INDIAN CREEK DRIVE DRAINAGE MITIGATION PROJECT
Roadway ID:
Project Length: 1.161
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 7,432 0 0 0 00 0 7,432
25,000 0 0 0 0 00 25,000TotalCONSTRUCTION
$25,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $25,152439228Item Number:
RESPONSIBLE AGENCY: FDOT
$1,011,148 $716,757 $555,430 $298,552 $261,056$4,127,055 $2,727,202 $9,697,200Yearly Totals
5 Year TIP Total $2,842,943HIGHWAYS
Section A1 - Page 596 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
HIGHWAYS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501133
District:
County:
ITS FREEWAY MANAGEMENT
AUTOMATIC VEHICLE LOCATOR SERVICE PATROLS ALL STATE ROADS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 013 0 13
0 0 0 0 0 013 13TotalMAINTENANCE
$13Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,839250113Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501135
District:
County:
SERVICE PATROL/FHP
SERVICE PATROLS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 0 537 551 5650 0 1,653
DDR 0 0 1,665 1,652 1,6390 0 4,956
0 0 2,202 2,203 2,204 00 6,609TotalMAINTENANCE
$6,609Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $39,839250113Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 597 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506102
District:
County:
LANDSCAPING
COUNTYWIDE NW COUNTYWIDE ROAD BEAUTIFICATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0746 0 746
0 0 0 0 0 0746 746TotalMAINTENANCE
$746Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $10,764250610Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507822
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE/LOAD RT COMPLEX STRUCTURE LOAD RATING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACBR 200 0 200 200 2000 0 800
ACBR 0 0 0 0 0200 0 200
BRAC 0 0 0 0 0444 0 444
BRAC 0 0 0 0 0625 0 625
BRT 0 0 0 0 0202 0 202
BRT 0 0 0 0 0599 0 599
Section A1 - Page 598 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507822
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE/LOAD RT COMPLEX STRUCTURE LOAD RATING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SABR 0 0 0 0 0400 0 400
200 0 200 200 200 02,470 3,270TotalMAINTENANCE
$3,270Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,270250782Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 599 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4105681
District:
County:
BRIDGE OPERATIONS
SIGN INSPECTIONS DISTRICTWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 310 0 0 02,366 0 2,676
0 310 0 0 0 02,366 2,676TotalMAINTENANCE
$2,676Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,806410568Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4105682
District:
County:
BRIDGE OPERATIONS
MAST ARM INSPECTIONS DISTRICTWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,474 0 1,474
0 0 0 0 0 01,474 1,474TotalMAINTENANCE
$1,474Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,806410568Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 600 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4105683
District:
County:
BRIDGE OPERATIONS
BRIDGE & MAINTENANCE CONSULTANT SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 47 47 47 47 47256 0 491
47 47 47 47 47 0256 491TotalMAINTENANCE
$491Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,806410568Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4105684
District:
County:
BRIDGE OPERATIONS
TRAFFIC SIGNAL MAST ARMS AND HIGH MAST LIGHT POLES INSPECTIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 340 340 376 0 01,109 0 2,165
340 340 376 0 0 01,109 2,165TotalMAINTENANCE
$2,165Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,806410568Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 601 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4105731
District:
County:
INSPECT CONSTRUCTION PROJS.
MEI MAINT/PERMIT INSPECTIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 1,500 890 1,510 1,600 1,92012,471 0 19,891
DDR 0 0 0 0 0372 0 372
1,500 890 1,510 1,600 1,920 012,843 20,263TotalMAINTENANCE
$20,263Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $20,263410573Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4142221
District:
County:
ROUTINE MAINTENANCE
MIAMI-DADE COUNTYWDE LIGHTING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 2,969 3,034 3,125 3,218 3,34227,429 0 43,117
2,969 3,034 3,125 3,218 3,342 027,429 43,117TotalMAINTENANCE
$43,117Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $43,117414222Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 602 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4142931
District:
County:
SIGNING/PAVEMENT MARKINGS
MIAMI-DADE COUNTYWDE FROM MONROE COUNTY LINE TO BROWARD COUNTY LINE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,357 0 2,357
0 0 0 0 0 02,357 2,357TotalMAINTENANCE
$2,357Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,035414293Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4142932
District:
County:
SIGNING/PAVEMENT MARKINGS
MIAMI-DADE COUNTYWDE FROM MONROE COUNTY LINE TO BROWARD COUNTY LINE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0594 0 594
0 0 0 0 0 0594 594TotalMAINTENANCE
$594Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,035414293Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 603 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4142933
District:
County:
SIGNING/PAVEMENT MARKINGS
MIAMI-DADE COUNTYWDE PAVEMENT MARKINGS
FROM BROWARD TO MONROE LINES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0376 0 376
0 0 0 0 0 0376 376TotalMAINTENANCE
$376Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,035414293Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4142935
District:
County:
SIGNING/PAVEMENT MARKINGS
MIAMI-DADE COUNTY STRIPING PHASE 1
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0658 0 658
0 0 0 0 0 0658 658TotalMAINTENANCE
$658Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,035414293Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 604 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4142936
District:
County:
SIGNING/PAVEMENT MARKINGS
RPM INSTALLATION MIAMI-DADE COUNTYWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 100 100 0 0 0550 0 750
100 100 0 0 0 0550 750TotalMAINTENANCE
$750Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,035414293Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4142937
District:
County:
SIGNING/PAVEMENT MARKINGS
RPM INSTALLATION MIAMI-DADE COUNTYWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 0 150 150 00 0 300
0 0 150 150 0 00 300TotalMAINTENANCE
$300Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,035414293Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 605 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4229321
District:
County:
ROUTINE MAINTENANCE
SR A1A CITY OF MIAMI BEACH ROADWAY LIGHTING MAINTENANCE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 173 178 183 189 1941,208 0 2,125
173 178 183 189 194 01,208 2,125TotalMAINTENANCE
$2,125Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,125422932Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273381
District:
County:
BRIDGE OPERATIONS
LOCAL ON - UNKNOWN BRIDGE FOUNDATION EVALUATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACBR 5 0 0 0 00 0 5
ACSB 0 0 0 0 0598 0 598
BRAC 0 0 0 0 0729 0 729
Section A1 - Page 606 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273381
District:
County:
BRIDGE OPERATIONS
LOCAL ON - UNKNOWN BRIDGE FOUNDATION EVALUATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
NHBR 0 0 0 0 0365 0 365
5 0 0 0 0 01,692 1,697TotalMAINTENANCE
$1,697Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,697427338Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273391
District:
County:
BRIDGE OPERATIONS
LOCAL OFF - UNKNOWN BRIDGE FOUNDATION EVALUATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACBR 0 0 0 0 011 0 11
ACBZ 2 0 0 0 04 0 6
Section A1 - Page 607 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4273391
District:
County:
BRIDGE OPERATIONS
LOCAL OFF - UNKNOWN BRIDGE FOUNDATION EVALUATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
BRTZ 0 0 0 0 0899 0 899
2 0 0 0 0 0914 916TotalMAINTENANCE
$916Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $916427339Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 608 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282801
District:
County:
BRIDGE-ROUTINE MAINTENANCE
BRIDGE REPAIR MIAMI DADE COUNTYWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0861 0 861
0 0 0 0 0 0861 861TotalMAINTENANCE
$861Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,056428280Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282802
District:
County:
BRIDGE-ROUTINE MAINTENANCE
BRIDGE REPAIR MIAMI-DADE COUNTYWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0597 0 597
0 0 0 0 0 0597 597TotalMAINTENANCE
$597Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,056428280Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 609 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282803
District:
County:
BRIDGE-ROUTINE MAINTENANCE
BRIDGE REPAIR DISTRICTWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0698 0 698
0 0 0 0 0 0698 698TotalMAINTENANCE
$698Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,056428280Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282804
District:
County:
BRIDGE-ROUTINE MAINTENANCE
BRIDGE REPAIR DISTRICTWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 500 500 0 0 0500 0 1,500
500 500 0 0 0 0500 1,500TotalMAINTENANCE
$1,500Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,056428280Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 610 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282805
District:
County:
BRIDGE-ROUTINE MAINTENANCE
BRIDGE REPAIR DISTRICTWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0400 0 400
0 0 0 0 0 0400 400TotalMAINTENANCE
$400Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,056428280Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282806
District:
County:
BRIDGE-ROUTINE MAINTENANCE
BRIDGE REPAIR MIAMI DADE COUNTY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 700 700 700 700 01,200 0 4,000
700 700 700 700 0 01,200 4,000TotalMAINTENANCE
$4,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,056428280Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 611 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283251
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI DADE COUNTY DERM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0252 0 252
0 0 0 0 0 0252 252TotalMAINTENANCE
$252Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $316428325Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283252
District:
County:
DRAINAGE IMPROVEMENTS
MIAMI DADE COUNTY DERM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 64 0 0 0 00 0 64
64 0 0 0 0 00 64TotalMAINTENANCE
$64Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $316428325Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 612 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283271
District:
County:
DRAINAGE IMPROVEMENTS
SPECIALIZED CONSULTANT SERVICES NPDES PROGRAM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0673 0 673
0 0 0 0 0 0673 673TotalMAINTENANCE
$673Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,164428327Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283272
District:
County:
DRAINAGE IMPROVEMENTS
SPECIALIZED CONSULTANT SERVICES NPDES PROGRAM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 270 260 0 0 0961 0 1,491
270 260 0 0 0 0961 1,491TotalMAINTENANCE
$1,491Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,164428327Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 613 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283451
District:
County:
DRAINAGE IMPROVEMENTS
D/W NPDES PUSH BUTTON DRAINAGE & TECH CONSULT SERVICE & GIS SUP
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,167 0 1,167
0 0 0 0 0 01,167 1,167TotalMAINTENANCE
$1,167Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,980428345Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283452
District:
County:
DRAINAGE IMPROVEMENTS
D/W NPDES PUSH BUTTON DRAINAGE & TECH CONSULT SERVICE & GIS SUP
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,423 0 1,423
0 0 0 0 0 01,423 1,423TotalMAINTENANCE
$1,423Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,980428345Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 614 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283453
District:
County:
DRAINAGE IMPROVEMENTS
D/W NPDES PUSH BUTTON DRAINAGE & TECH CONSULT SERVICE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 300 300 300 110 0590 0 1,600
300 300 300 110 0 0590 1,600TotalMAINTENANCE
$1,600Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,980428345Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4283454
District:
County:
DRAINAGE IMPROVEMENTS
D/W NPDES PUSH BUTTON DRAINAGE & TECH CONSULT SERVICE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 0 0 490 3000 0 790
0 0 0 490 300 00 790TotalMAINTENANCE
$790Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,980428345Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 615 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4318711
District:
County:
DRAINAGE IMPROVEMENTS
COUNTYWIDE DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0450 0 450
0 0 0 0 0 0450 450TotalMAINTENANCE
$450Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $900431871Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4318712
District:
County:
DRAINAGE IMPROVEMENTS
COUNTYWIDE DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 450 0 0 0 00 0 450
450 0 0 0 0 00 450TotalMAINTENANCE
$450Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $900431871Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 616 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4329071
District:
County:
BRIDGE OPERATIONS
DISTRICTWIDE LOCAL GOVERNMENT IN-DEPTH BRIDGE INSPECTION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACBZ 34 739 79 784 84596 0 2,316
34 739 79 784 84 0596 2,316TotalMAINTENANCE
$2,316Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,316432907Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4329081
District:
County:
BRIDGE OPERATIONS
DISTRICTWIDE LOCAL GOVERNMENT IN-DEPTH BRIDGE INSPECTION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
ACBR 66 1,913 108 1,659 940 0 3,840
ACSB 0 0 0 0 01,167 0 1,167
66 1,913 108 1,659 94 01,167 5,007TotalMAINTENANCE
$5,007Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,007432908Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 617 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4383301
District:
County:
LIGHTING
DISTRICT 6 STATE HIGHWAY LIGHTING ELECTRICITY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 1,500 1,500 923 950 9790 0 5,852
1,500 1,500 923 950 979 00 5,852TotalMAINTENANCE
$5,852Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,852438330Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4388721
District:
County:
FIXED CAPITAL OUTLAY
D6 NORTH DADE YARD BUILDINGS & GROUNDS - MAINTENANCE & REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 87 0 0 0 00 0 87
87 0 0 0 0 00 87TotalMAINTENANCE
$87Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $87438872Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 618 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4388731
District:
County:
FIXED CAPITAL OUTLAY
D6 SOUTH DADE YARD BUILDINGS & GROUNDS - MAINTENANCE & REPAIR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 100 0 0 0 00 0 100
100 0 0 0 0 00 100TotalMAINTENANCE
$100Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $100438873Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4390081
District:
County:
LANDSCAPING
LANDSCAPE MAINTENANCE MIAMI-DADE COUNTYWIDE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 400 400 0 0 00 0 800
400 400 0 0 0 00 800TotalMAINTENANCE
$800Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $800439008Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 619 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4390211
District:
County:
BRIDGE-ROUTINE MAINTENANCE
BRIDGE REPAIR, BRIDGE # ....?
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 2,781 0 0 00 0 2,781
0 2,781 0 0 0 00 2,781TotalMAINTENANCE
$2,781Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,781439021Item Number:
RESPONSIBLE AGENCY: FDOT
$9,807 $13,992 $9,903 $12,300 $9,364$68,590 $0 $123,956Yearly Totals
5 Year TIP Total $55,366MAINTENANCE
Section A1 - Page 620 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MAINTENANCE
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2499432
District:
County:
ENVIRONMENTAL TEST/MITIGATE
DISTRICTWIDE CONTAMINATION ASSESSMENT & REMEDIATION CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0104 0 104
0 0 0 0 0 0104 104TotalPLANNING AND DESIGN
$104Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,461249943Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501151
District:
County:
TECHNICAL ASSISTANCE
ITS TECHNICAL CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 05,106 0 5,106
0 0 0 0 0 05,106 5,106TotalPLANNING AND DESIGN
$5,106Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $43,371250115Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 621 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501152
District:
County:
TECHNICAL ASSISTANCE
ITS DISTRICTWIDE TECHNICAL SUPPORT & PUBLIC INVOLVEMENT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,649 0 1,649
0 0 0 0 0 01,649 1,649TotalPLANNING AND DESIGN
$1,649Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $43,371250115Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501153
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS PROGRAM OPERATIONS CONSULTANT CONTRACTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 022,506 0 22,506
0 0 0 0 0 022,506 22,506TotalPLANNING AND DESIGN
$22,506Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $43,371250115Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 622 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501154
District:
County:
TECHNICAL ASSISTANCE
ITS TECHNICAL CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 0 0 0 0 0100 0 100
DIH 30 30 0 0 085 0 145
DS 300 100 0 0 01,000 0 1,400
330 130 0 0 0 01,185 1,645TotalPLANNING AND DESIGN
$1,645Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $43,371250115Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501155
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS OPERATIONS CONSULTANT CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 50 50 50 0 00 0 150
DS 0 0 0 0 050 0 50
Section A1 - Page 623 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501155
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS OPERATIONS CONSULTANT CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 2,218 2,202 2,234 2,200 2,1660 0 11,020
2,268 2,252 2,284 2,200 2,166 050 11,220TotalPLANNING AND DESIGN
$11,220Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $43,371250115Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501156
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS TECHNICAL CONSULTANT CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 15 30 0 00 0 45
Section A1 - Page 624 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2501156
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS TECHNICAL CONSULTANT CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 0 300 300 300 3000 0 1,200
0 315 330 300 300 00 1,245TotalPLANNING AND DESIGN
$1,245Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $43,371250115Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506052
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE MISCELLANEOUS PE DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 1 1 1 1 01 0 5
Section A1 - Page 625 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506052
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE MISCELLANEOUS PE DESIGN CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 60 0 0 60 0100 0 220
61 1 1 61 0 0101 225TotalPLANNING AND DESIGN
$225Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,641250605Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 626 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506212
District:
County:
RIGHT OF WAY ACTIVITIES
D/W PROPERTY MGT BY DIST R/W ADMIN
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 620 620 620 620 6203,495 0 6,595
620 620 620 620 620 03,495 6,595TotalRIGHT OF WAY
$6,595Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $14,996250621Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506223
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE PD&E AND TRAFFIC CONSULTANT SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 066 0 66
0 0 0 0 0 066 66TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$66Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,404250622Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 627 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506493
District:
County:
ENVIRONMENTAL PERMITS ACQ
DISTRICTWIDE ENVIRONMENTAL PERMITS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 50 50 50 50 50175 0 425
50 50 50 50 50 0175 425TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$425Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,880250649Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506733
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE PUBLIC INVOLVEMENT CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 20 20 20 20 2020 0 120
DS 500 400 400 500 300750 0 2,850
520 420 420 520 320 0770 2,970TotalPLANNING AND DESIGN
$2,970Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,049250673Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 628 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506963
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE ROW PUBLIC RECORDS SEARCH
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 6 6 6 6 640 0 70
6 6 6 6 6 040 70TotalRIGHT OF WAY
$70Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,227250696Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506964
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE ROW ENGINEERING SUPPORT FOR R/W ADMINISTRATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 1032 0 82
DS 0 0 0 0 043 0 43
10 10 10 10 10 075 125TotalPLANNING AND DESIGN
$125Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,227250696Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 629 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506965
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE MISC LOCATION SURVEY CONSULTANT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 600 800 800 600 6002,473 0 5,873
600 800 800 600 600 02,473 5,873TotalPLANNING AND DESIGN
$5,873Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,227250696Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2506966
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE ROW MAPPING & SURVEY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 750 750 750 950 1,250876 0 5,326
750 750 750 950 1,250 0876 5,326TotalPLANNING AND DESIGN
$5,326Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $26,227250696Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 630 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507472
District:
County:
PRELIMINARY ENGINEERING
D/W DESIGN OFFICE ENGINEERING SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 303 241 241 241 2411,627 0 2,894
303 241 241 241 241 01,627 2,894TotalPLANNING AND DESIGN
$2,894Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $28,850250747Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507532
District:
County:
FUNDING ACTION
DISTRICTWIDE OPERATIONS DIVISION SUPPORT/OPER BUDGET
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 47 47 47 47 47192 0 427
DS 0 0 0 0 0227 0 227
47 47 47 47 47 0419 654TotalCONSTRUCTION
$654Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $654250753Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 631 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507592
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE RESURFACING SCOPING REPORTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 220 0 0 0 01,250 0 1,470
220 0 0 0 0 01,250 1,470TotalPLANNING
DS 0 0 0 0 0110 0 110
0 0 0 0 0 0110 110TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,580Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,869250759Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507593
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE RESURFACING SCOPING REPORTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 50 50 50 50 5060 0 310
Section A1 - Page 632 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2507593
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE RESURFACING SCOPING REPORTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 350 500 500 500 500633 0 2,983
400 550 550 550 550 0693 3,293TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$3,293Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,869250759Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512711
District:
County:
BIKE PATH/TRAIL
NORTH BEACH FROM 63RD STREET TO 75TH STREET LAP
Roadway ID:
Project Length: 1.116
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0841 0 841
0 0 0 0 0360 0 360
0 0 0 0 0 01,201 1,201TotalCONSTRUCTION
Section A1 - Page 633 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
$1,201Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,970251271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512712
District:
County:
BIKE PATH/TRAIL
N BEACH REC CORRIDR FROM 64TH STREET TO 79TH STREET (PH IV)
Roadway ID:
Project Length: 1.006
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,708 0 1,708
0 0 0 0 04,490 0 4,490
0 0 0 0 0 06,198 6,198TotalCONSTRUCTION
$6,198Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,970251271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512714
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI BEACH FROM 23 STREET TO 64TH STREET
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 00 0 0
0 0 0 0 05 0 5
Section A1 - Page 634 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2512714
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI BEACH FROM 23 STREET TO 64TH STREET
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0534 0 534
0 0 0 0 0 0539 539TotalPLANNING AND DESIGN
$539Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,970251271Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 635 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4132212
District:
County:
GEOGRAPHIC INFO. SYSTEMS
TRANSPORTATION SYSTEMS GIS SUPPORT FOR DESIGN
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 231 231 231 231 231550 0 1,705
231 231 231 231 231 0550 1,705TotalPLANNING AND DESIGN
$1,705Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,215413221Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4147531
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC STUDIES - FIU
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,214 0 1,214
0 0 0 0 0 01,214 1,214TotalPLANNING AND DESIGN
$1,214Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,283414753Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 636 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4147532
District:
County:
TRAFFIC ENGINEERING STUDY
FIU SUNGUIDE TMC OPS SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 024 0 24
0 0 0 0 0 024 24TotalPLANNING AND DESIGN
$24Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,283414753Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4147533
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC STUDIES - FIU
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 0 0 0 0 031 0 31
DS 50 50 50 50 50875 0 1,125
50 50 50 50 50 0906 1,156TotalPLANNING AND DESIGN
$1,156Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,283414753Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 637 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4147534
District:
County:
TRAFFIC ENGINEERING STUDY
DISTRICTWIDE TRAFFIC STUDIES - FIU
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 0 040 0 70
DS 250 250 250 250 250519 0 1,769
TOBD 0 0 0 0 050 0 50
260 260 260 250 250 0609 1,889TotalPLANNING AND DESIGN
$1,889Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,283414753Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4147662
District:
County:
BIKE LANE/SIDEWALK
CITY OF MIAMI SPRINGS AT CURTISS MANSION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
Section A1 - Page 638 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4147662
District:
County:
BIKE LANE/SIDEWALK
CITY OF MIAMI SPRINGS AT CURTISS MANSION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 145 0 0 0 00 0 145
150 0 0 0 0 00 150TotalCONSTRUCTION
$150Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,150414766Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4166602
District:
County:
BIKE PATH/TRAIL
MIAMI DADE COUNTY - LUDLAM TRAIL CORRIDOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
***
SIS or Non-SIS: No
PHASE :
Extra Description:
GR17 2,000 0 0 0 00 0 2,000
Section A1 - Page 639 of 685FY 2017-2021 Approved May 19, 2016
***Project will require an LRTP amendment.
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4166602
District:
County:
BIKE PATH/TRAIL
MIAMI DADE COUNTY - LUDLAM TRAIL CORRIDOR
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
***
SIS or Non-SIS: No
PHASE :
Extra Description:
SED 1,000 0 0 0 00 0 1,000
3,000 0 0 0 0 00 3,000TotalCONSTRUCTION
$3,000Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,000416660Item Number:
RESPONSIBLE AGENCY: MIAMI-DADE COUNTY
***Project will require an LRTP amendment.
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177401
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS OPERATIONS CONSULTANTS/GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 01,543 0 1,543
0 0 0 0 0806 0 806
0 0 0 0 07,546 0 7,546
Section A1 - Page 640 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4177401
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS OPERATIONS CONSULTANTS/GRANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0 09,895 9,895TotalOPERATIONS
$9,895Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $21,861417740Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4251442
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE GENERAL CONSULTANT ENGINEERING SERVICES CONTRACT #1
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 1010 0 60
DS 550 550 550 800 5501,630 0 4,630
560 560 560 810 560 01,640 4,690TotalPLANNING AND DESIGN
$4,690Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,426425144Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 641 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4251443
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE GENERAL CONSULTANT ENGINEERING SERVICES CONTRACT #2
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 1010 0 60
DS 550 550 550 800 5501,103 0 4,103
560 560 560 810 560 01,113 4,163TotalPLANNING AND DESIGN
DS 0 0 0 0 0141 0 141
0 0 0 0 0 0141 141TotalCONSTRUCTION
$4,304Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $15,426425144Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258571
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CARIBBEAN, S POINTE, S MIAMI HEIGHTS ELEMENTARY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0101 0 101
0 0 0 0 0 0101 101TotalPLANNING AND DESIGN
0 0 0 0 05 0 5
Section A1 - Page 642 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258571
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CARIBBEAN, S POINTE, S MIAMI HEIGHTS ELEMENTARY
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0737 0 737
0 0 0 0 0 0742 742TotalCONSTRUCTION
$843Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,074425857Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258651
District:
County:
DRAINAGE IMPROVEMENTS
COUNTYWIDE DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 055 0 55
0 0 0 0 0 055 55TotalPLANNING AND DESIGN
Section A1 - Page 643 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4258651
District:
County:
DRAINAGE IMPROVEMENTS
COUNTYWIDE DRAINAGE PUSHBUTTON PROJECTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0676 0 676
0 0 0 0 0 0676 676TotalCONSTRUCTION
0 0 0 0 01,200 0 1,200
0 0 0 0 0 01,200 1,200TotalMAINTENANCE
$1,931Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,888425865Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282101
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL (GRADES K-8) VARIOUS SCHOOLS/LOCATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 02 0 2
SR2S 0 0 0 0 088 0 88
0 0 0 0 0 090 90TotalPLANNING AND DESIGN
Section A1 - Page 644 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282101
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL (GRADES K-8) VARIOUS SCHOOLS/LOCATIONS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-52
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
TALU 673 0 0 0 00 0 673
678 0 0 0 0 00 678TotalCONSTRUCTION
$768Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $768428210Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282111
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CORAL WY, DEVONAIRE K-8; MAYA ANGELOU,MELROSE ELEM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-48
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 0 0 0 0 02 0 2
SR2S 0 0 0 0 084 0 84
0 0 0 0 0 086 86TotalPLANNING AND DESIGN
SA 5 0 0 0 00 0 5
TALU 605 0 0 0 00 0 605
Section A1 - Page 645 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4282111
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CORAL WY, DEVONAIRE K-8; MAYA ANGELOU,MELROSE ELEM
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-48
SIS or Non-SIS: No
PHASE :
Extra Description:
610 0 0 0 0 00 610TotalCONSTRUCTION
$696Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $696428211Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4318681
District:
County:
PUBLIC INFORMATION/EDUCATION
DISTRICTWIDE PUBLIC INFORMATION SERVICES ON DIST 6 CONSTRUCTION PROJS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 400 300 350 300 3001,000 0 2,650
400 300 350 300 300 01,000 2,650TotalCONSTRUCTION
$2,650Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,400431868Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 646 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4318682
District:
County:
PUBLIC INFORMATION/EDUCATION
DISTRICTWIDE PUBLIC INFORMATION SERVICES ON DIST 6 CONSTRUCTION PROJS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 400 300 350 300 300900 0 2,550
400 300 350 300 300 0900 2,550TotalCONSTRUCTION
$2,550Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,400431868Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4318683
District:
County:
PUBLIC INFORMATION/EDUCATION
DISTRICTWIDE PUBLIC COMMUNICATION SERVICES FOR MISC CONSTRUCTION PROJS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 300 500 300 300 350450 0 2,200
300 500 300 300 350 0450 2,200TotalCONSTRUCTION
$2,200Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,400431868Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 647 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4324001
District:
County:
TRANSPORTATION STATISTICS
MIAMI-DADE COUNTYWDE MDX DOCUMENTS REVIEW
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 50 50 50 50 50127 0 377
DS 0 0 0 0 0800 0 800
50 50 50 50 50 0927 1,177TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,177Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,177432400Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4325901
District:
County:
TRANSPORTATION PLANNING
MIAMI-DADE CO WIDE PLANNING CONSULTANT SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DDR 300 300 300 300 300750 0 2,250
DS 0 0 0 0 0300 0 300
300 300 300 300 300 01,050 2,550TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$2,550Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,550432590Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 648 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326392
District:
County:
TRANSPORTATION PLANNING
SR 7/SR 933/US 441 FROM SW 8 ST/TAMIAMI TRL TO GGI PARK AND RIDE LOT
Roadway ID:
Project Length: 10.812
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0759 0 759
0 0 0 0 0 0759 759TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$759Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,029432639Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326394
District:
County:
TRANSPORTATION PLANNING
NW 74 STREET FROM SR 826/PALMETTO XWAY
TO SR 27/OKEECHOBEE ROAD
Roadway ID:
Project Length: 1.128
Lanes Exist:Lanes Improved:Lanes Added:
4
MIAMI-DADE
LRTP Ref:
87000635
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0402 0 402
0 0 0 0 0 0402 402TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$402Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,029432639Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 649 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4326395
District:
County:
TRANSPORTATION PLANNING
SW 7/SW 8 STREET FROM US-1/BRICKELL AVENUE TO SR 9/SW 27 AVENUE
Roadway ID:
Project Length: 2.970
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-36
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0460 0 460
0 0 0 0 0 0460 460TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$460Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,029432639Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4327931
District:
County:
PRELIMINARY ENGINEERING
DISTRICTWIDE LOCATION SURVEY SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 300 300 300 300 3001,398 0 2,898
DS 0 0 0 0 034 0 34
300 300 300 300 300 01,432 2,932TotalPLANNING AND DESIGN
$2,932Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,932432793Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 650 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4330561
District:
County:
PTO STUDIES
DISTRICTWIDE FREIGHT LOGISTICS & PAX CONSULTANT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 350 250 312 0 0775 0 1,687
DS 0 0 0 0 0183 0 183
350 250 312 0 0 0958 1,870TotalPLANNING
$1,870Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,870433056Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4330571
District:
County:
PTO STUDIES
DISTRICTWIDE PUBLIC TRANSPORTATION CONSULTANT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 400 450 500 500 5000 0 2,350
DS 100 100 0 0 00 0 200
500 550 500 500 500 00 2,550TotalPLANNING
$2,550Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,050433057Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 651 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4346651
District:
County:
TRAFFIC MANAGEMENT CENTERS
ITS OPERATIONS CONSULTANTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DITS 1,052 1,084 1,116 1,150 1,1840 0 5,586
1,052 1,084 1,116 1,150 1,184 00 5,586TotalOPERATIONS
$5,586Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,586434665Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4346731
District:
County:
PD&E/EMO STUDY
DISTRICTWIDE NOISE AND AIR QUALITY ASSESSMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DIH 10 10 10 10 1016 0 66
DS 150 150 300 150 150350 0 1,250
160 160 310 160 160 0366 1,316TotalPROJECT DEVELOPMENT AND ENVIRONMENTAL
$1,316Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,316434673Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 652 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4346871
District:
County:
BIKE PATH/TRAIL
VILLAGE OF PINECREST CITYWIDE BICYCLING IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 050 0 50
0 0 0 0 0 050 50TotalPLANNING AND DESIGN
LF 0 250 0 0 00 0 250
TALT 0 340 0 0 00 0 340
TALU 0 660 0 0 00 0 660
0 1,250 0 0 0 00 1,250TotalCONSTRUCTION
$1,300Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,300434687Item Number:
RESPONSIBLE AGENCY: Village of Pinecrest
Section A1 - Page 653 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4351401
District:
County:
PTO STUDIES
DISTRICTWIDE FREIGHT LOGISTICS & PAX CONSULTANT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 300 400 288 500 500324 0 2,312
DS 0 0 0 0 0200 0 200
300 400 288 500 500 0524 2,512TotalPLANNING AND DESIGN
$2,512Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $2,512435140Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355011
District:
County:
BIKE PATH/TRAIL
THE UNDERLINE- MPATH/ BRICKELL BACKYARD PROJECT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
***
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 320 0 0 0 00 0 320
320 0 0 0 0 00 320TotalPLANNING AND DESIGN
LF 1,243 0 0 0 00 0 1,243
SA 5 0 0 0 00 0 5
SU 2,000 0 0 0 00 0 2,000
Section A1 - Page 654 of 685FY 2017-2021 Approved May 19, 2016
***Project will require an LRTP amendment.
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4355011
District:
County:
BIKE PATH/TRAIL
THE UNDERLINE- MPATH/ BRICKELL BACKYARD PROJECT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
***
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 1,000 0 0 0 00 0 1,000
4,248 0 0 0 0 00 4,248TotalCONSTRUCTION
$4,568Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,568435501Item Number:
RESPONSIBLE AGENCY: Miami-Dade County Parks & Recreation
***Project will require an LRTP amendment.
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366101
District:
County:
ROAD/SLOPE PROTECTION
HOBIE ISLAND, NORTH SIDE, SHORELINE AND ROADWAY PROTECTION
Roadway ID:
Project Length: 0.692
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87000094
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 2,543 0 00 0 2,543
SA 0 0 5 0 00 0 5
Section A1 - Page 655 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366101
District:
County:
ROAD/SLOPE PROTECTION
HOBIE ISLAND, NORTH SIDE, SHORELINE AND ROADWAY PROTECTION
Roadway ID:
Project Length: 0.692
Lanes Exist:Lanes Improved:Lanes Added:
6
MIAMI-DADE
LRTP Ref:
87000094
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 0 0 1,000 0 00 0 1,000
0 0 3,548 0 0 00 3,548TotalCONSTRUCTION
$3,548Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,096436610Item Number:
RESPONSIBLE AGENCY: Miami-Dade Dept. of Transportation and Public Works
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366102
District:
County:
ROAD/SLOPE PROTECTION
HOBIE ISLAND, NORTH SIDE, SHORELINE AND ROADWAY PROTECTION PHASE II
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 2,5430 0 2,543
SA 0 0 0 0 50 0 5
TALT 0 0 0 0 1,0000 0 1,000
Section A1 - Page 656 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4366102
District:
County:
ROAD/SLOPE PROTECTION
HOBIE ISLAND, NORTH SIDE, SHORELINE AND ROADWAY PROTECTION PHASE II
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 3,548 00 3,548TotalCONSTRUCTION
$3,548Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $7,096436610Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4370481
District:
County:
ENVIRONMENTAL TEST/MITIGATE
PILOT PROJECT FOR WETLAND MITIGATION
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 10 0 0 0 00 0 10
DEM 200 0 0 0 00 0 200
210 0 0 0 0 00 210TotalPLANNING AND DESIGN
$210Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $210437048Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 657 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381471
District:
County:
BIKE LANE/SIDEWALK
SAFE RTS TO SCHOOL ARCH CRK,E.M. HARTNR,LAKEVW ES;N MIAMI,J DIEGO MIDDLE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
TALT 77 0 0 0 00 0 77
82 0 0 0 0 00 82TotalPLANNING AND DESIGN
SA 0 0 0 5 00 0 5
TALT 0 0 0 77 00 0 77
TALU 0 0 0 514 00 0 514
0 0 0 596 0 00 596TotalCONSTRUCTION
$678Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $678438147Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381601
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CORAL REEF, HOWARD DRIVE AND PERRINE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
Section A1 - Page 658 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381601
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL CORAL REEF, HOWARD DRIVE AND PERRINE
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
TALT 65 0 0 0 00 0 65
70 0 0 0 0 00 70TotalPLANNING AND DESIGN
SA 0 0 5 0 00 0 5
TALT 0 0 848 0 00 0 848
0 0 853 0 0 00 853TotalCONSTRUCTION
$923Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $923438160Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381621
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL KEY BISCAYNE K8
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
Section A1 - Page 659 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381621
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL KEY BISCAYNE K8
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
TALT 84 0 0 0 00 0 84
89 0 0 0 0 00 89TotalPLANNING AND DESIGN
SA 0 0 0 5 00 0 5
TALT 0 0 0 197 00 0 197
TALU 0 0 0 557 00 0 557
0 0 0 759 0 00 759TotalCONSTRUCTION
$848Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $848438162Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381631
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL COMSTOCK ES, GRATGNY ES, AND HIBISCUS ES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
Section A1 - Page 660 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381631
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHOOL COMSTOCK ES, GRATGNY ES, AND HIBISCUS ES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
TALT 73 0 0 0 00 0 73
78 0 0 0 0 00 78TotalPLANNING AND DESIGN
SA 0 0 0 5 00 0 5
TALT 0 0 0 73 00 0 73
TALU 0 0 0 484 00 0 484
0 0 0 562 0 00 562TotalCONSTRUCTION
$640Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $640438163Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381651
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHL CRESTVW ES; EDISON PK K8 CTR; LORAH PK ES,SWEETWTR ES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
SA 5 0 0 0 00 0 5
SA 0 0 0 5 00 0 5
Section A1 - Page 661 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4381651
District:
County:
PEDESTRIAN SAFETY IMPROVEMENT
SAFE RTS TO SCHL CRESTVW ES; EDISON PK K8 CTR; LORAH PK ES,SWEETWTR ES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-50
SIS or Non-SIS: No
PHASE :
Extra Description:
TALT 91 0 0 0 00 0 91
TALT 0 0 0 91 00 0 91
TALU 0 0 0 603 00 0 603
96 0 0 699 0 00 795TotalPLANNING AND DESIGN
$795Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $795438165Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386611
District:
County:
BIKE PATH/TRAIL
CITY OF MIAMI BEACH BEACHWALK II
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 3,8800 0 3,880
SA 0 0 0 0 50 0 5
TALU 0 0 0 0 8500 0 850
0 0 0 0 4,735 00 4,735TotalPLANNING AND DESIGN
Section A1 - Page 662 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
$4,735Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,735438661Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386621
District:
County:
BIKE LANE/SIDEWALK
CITY OF CORAL GABLES - ALHAMBRA CIRCLE BIKE LANES
Blue Road SW 40th Street
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 90 00 0 90
LF 0 0 0 0 900 0 90
TALU 0 0 0 0 5980 0 598
0 0 0 90 688 00 778TotalPLANNING AND DESIGN
$778Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $778438662Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 663 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386631
District:
County:
BIKE PATH/TRAIL
TOWN OF MIAMI LAKES G.R.E.E.N.
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 85 0 0 0 00 0 85
LF 0 0 150 0 00 0 150
TALT 0 0 200 0 00 0 200
85 0 350 0 0 00 435TotalPLANNING AND DESIGN
$435Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $435438663Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386651
District:
County:
BIKE PATH/TRAIL
MIAMI SHORES MULTIMODAL MOBILITY IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 70 0 0 0 00 0 70
LF 0 0 0 77 00 0 77
SA 5 0 0 0 00 0 5
Section A1 - Page 664 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386651
District:
County:
BIKE PATH/TRAIL
MIAMI SHORES MULTIMODAL MOBILITY IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
TALT 0 0 0 454 00 0 454
75 0 0 531 0 00 606TotalPLANNING AND DESIGN
$606Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $606438665Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386671
District:
County:
BIKE PATH/TRAIL
BLACK CREEK TRAIL SEGMENT B PHASE I
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 1830 0 183
SA 5 0 0 0 00 0 5
SA 0 0 0 0 50 0 5
Section A1 - Page 665 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386671
District:
County:
BIKE PATH/TRAIL
BLACK CREEK TRAIL SEGMENT B PHASE I
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
6-54
SIS or Non-SIS: No
PHASE :
Extra Description:
TALT 372 0 0 0 00 0 372
TALU 0 0 0 0 6280 0 628
377 0 0 0 816 00 1,193TotalPLANNING AND DESIGN
$1,193Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,193438667Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386681
District:
County:
BIKE PATH/TRAIL
CITY OF NORTH MIAMI - NE 8TH AVENUE GREEN TRAIL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 110 0 00 0 110
LF 0 0 0 0 2980 0 298
SA 0 0 0 0 50 0 5
Section A1 - Page 666 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386681
District:
County:
BIKE PATH/TRAIL
CITY OF NORTH MIAMI - NE 8TH AVENUE GREEN TRAIL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
TALU 0 0 0 0 9960 0 996
0 0 110 0 1,299 00 1,409TotalPLANNING AND DESIGN
$1,409Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,409438668Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386691
District:
County:
BIKE PATH/TRAIL
TOWN OF CUTLER BAY BIKE/PED FACILITY IMPROVEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 100 0 0 00 0 100
LF 0 0 0 58 00 0 58
SA 0 0 0 5 00 0 5
TALT 0 0 0 361 00 0 361
0 100 0 424 0 00 524TotalPLANNING AND DESIGN
Section A1 - Page 667 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
$524Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $524438669Item Number:
RESPONSIBLE AGENCY: FDOT
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4386731
District:
County:
BIKE PATH/TRAIL
CITY OF SOUTH MIAMI SW 62 AVENUE PED AND BIKE MOBILITY ENHANCEMENTS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
NA
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 100 0 0 00 0 100
LF 0 0 0 19 00 0 19
SA 0 0 0 5 00 0 5
TALT 0 0 0 480 00 0 480
0 100 0 504 0 00 604TotalPLANNING AND DESIGN
$604Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $604438673Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 668 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4390311
District:
County:
FUNDING ACTION
TRAFFIC OPERATIONS CONSULTANT SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 0145 0 145
0 0 0 0 0 0145 145TotalPLANNING AND DESIGN
$145Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $642439031Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 669 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4390312
District:
County:
FUNDING ACTION
TRAFFIC OPERATIONS CONSULTANT SUPPORT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
DS 497 0 0 0 00 0 497
497 0 0 0 0 00 497TotalOPERATIONS
$497Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $642439031Item Number:
RESPONSIBLE AGENCY: FDOT
$22,623 $13,497 $16,807 $16,331 $22,841$79,173 $0 $171,272Yearly Totals
5 Year TIP Total $92,099MISCELLANEOUS
Section A1 - Page 670 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
MISCELLANEOUS
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2520711
District:
County:
TRANSPORTATION STATISTICS
TRANSPORTATION STATISTICS SUPPORT #1
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 550 500 500 500 50010,777 0 13,327
HP 0 0 0 0 060 0 60
550 500 500 500 500 010,837 13,387TotalPLANNING
$13,387Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,421252071Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2520712
District:
County:
TRANSPORTATION STATISTICS
TRANSPORTATION STATISTICS SUPPORT #1
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 034 0 34
0 0 0 0 0 034 34TotalPLANNING
$34Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $13,421252071Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 671 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2520941
District:
County:
MODAL SYSTEMS PLANNING
METROPOLITAN PLANNING ORGANIZATION (MPO) SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 200 200 200 200 2003,542 0 4,542
D 0 0 0 0 0331 0 331
D 0 0 0 0 01,019 0 1,019
HP 0 0 0 0 046 0 46
SU 0 0 0 0 0100 0 100
200 200 200 200 200 05,038 6,038TotalPLANNING
$6,038Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $6,038252094Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2521801
District:
County:
TRANSPORTATION STATISTICS
TRANSPORTATION STATISTICS SUPPORT #2
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 500 500 500 500 5005,875 0 8,375
D 0 0 0 0 0229 0 229
Section A1 - Page 672 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT2521801
District:
County:
TRANSPORTATION STATISTICS
TRANSPORTATION STATISTICS SUPPORT #2
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
SU 0 0 0 0 0500 0 500
SU 0 0 0 0 01,800 0 1,800
SU 0 0 0 0 0750 0 750
SU 0 0 0 0 0893 0 893
500 500 500 500 500 010,047 12,547TotalPLANNING
$12,547Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $12,547252180Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4034871
District:
County:
TRANSPORTATION PLANNING
HPR PROGRAM TRANSPORTATION PLANNING ACTIVITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 0 0 0 015 0 15
D 0 0 0 0 04 0 4
D 44 49 55 61 67524 0 800
Section A1 - Page 673 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4034871
District:
County:
TRANSPORTATION PLANNING
HPR PROGRAM TRANSPORTATION PLANNING ACTIVITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 0 0 0 00 0 0
D 0 0 0 0 01 0 1
D 0 0 0 0 01 0 1
D 0 0 0 0 02 0 2
HP 0 0 0 0 0849 0 849
HP 0 0 0 0 015 0 15
HP 0 0 0 0 01,346 0 1,346
HP 0 0 0 0 0940 0 940
HP 755 779 803 828 8225,297 0 9,284
HP 0 0 0 0 0816 0 816
HP 0 0 0 0 01,057 0 1,057
HP 0 0 0 0 01,160 0 1,160
HPAC 0 0 0 0 0887 0 887
HPAC 0 0 0 0 0626 0 626
799 828 858 889 889 013,540 17,803TotalPLANNING
$17,803Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $17,835403487Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 674 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4034872
District:
County:
TRANSPORTATION PLANNING
HPF PROGRAM TRANSPORTATION PLANNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 032 0 32
0 0 0 0 0 032 32TotalPLANNING
$32Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $17,835403487Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4034881
District:
County:
TRANSPORTATION STATISTICS
HPR PROGRAM DATA COLLECTION ACTIVITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 0 0 0 02 0 2
D 0 0 0 0 01 0 1
D 0 0 0 0 00 0 0
D 20 20 20 20 2021 0 121
HP 0 0 0 0 0192 0 192
HP 0 0 0 0 0173 0 173
Section A1 - Page 675 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4034881
District:
County:
TRANSPORTATION STATISTICS
HPR PROGRAM DATA COLLECTION ACTIVITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
HP 0 0 0 0 0208 0 208
HP 0 0 0 0 0131 0 131
HP 0 0 0 0 087 0 87
HP 0 0 0 0 074 0 74
HP 224 225 225 226 2521,578 0 2,730
HPAC 0 0 0 0 068 0 68
HPAC 0 0 0 0 061 0 61
244 245 245 246 272 02,596 3,848TotalPLANNING
$3,848Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $3,848403488Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 676 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4034891
District:
County:
TRANSPORTATION PLANNING
HPR PROGRAM SYSTEMS PLANNING ACTIVITIES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 0 0 0 0 00 0 0
D 30 30 30 30 30120 0 270
HP 0 0 0 0 044 0 44
HP 0 0 0 0 046 0 46
HP 0 0 0 0 059 0 59
HP 0 0 0 0 024 0 24
HP 0 0 0 0 032 0 32
HP 0 0 0 0 022 0 22
HP 300 300 300 300 3002,056 0 3,556
HPAC 0 0 0 0 012 0 12
HPAC 0 0 0 0 07 0 7
330 330 330 330 330 02,422 4,072TotalPLANNING
$4,072Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,072403489Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 677 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4081991
District:
County:
URBAN CORRIDOR IMPROVEMENTS
TRANSPORTATION STATISTICS SUPPORT #3
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
C-6
SIS or Non-SIS: No
PHASE :
Extra Description:
D 500 700 500 500 5006,677 0 9,377
500 700 500 500 500 06,677 9,377TotalPLANNING
$9,377Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $9,377408199Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4132211
District:
County:
TRANSPORTATION STATISTICS
TRANSPORTATION SYSTEMS GIS DATA DEVELOPMENT AND MAPPING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 170 250 250 250 2505,340 0 6,510
170 250 250 250 250 05,340 6,510TotalPLANNING
$6,510Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $8,215413221Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 678 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4210531
District:
County:
TRANSPORTATION PLANNING
DISTRICTWIDE PLANNING AND PD&E SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 02,366 0 2,366
0 0 0 0 0 02,366 2,366TotalPLANNING
$2,366Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,091421053Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4210532
District:
County:
GEOGRAPHIC INFO. SYSTEMS
DISTRICTWIDE PLANNING AND PD&E SUPPORT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 034 0 34
0 0 0 0 0 034 34TotalPLANNING
$34Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,091421053Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 679 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4210533
District:
County:
TRANSPORTATION PLANNING
DISTRICTWIDE INTERMODAL SYSTEMS PLANNING
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 450 550 500 500 5003,225 0 5,725
450 550 500 500 500 03,225 5,725TotalPLANNING
$5,725Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,091421053Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4210534
District:
County:
TRANSPORTATION PLANNING
DISTRICTWIDE COMPLETE STREETS CONTRACT
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 450 550 500 500 500466 0 2,966
450 550 500 500 500 0466 2,966TotalPLANNING
$2,966Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $11,091421053Item Number:
RESPONSIBLE AGENCY: FDOT
Section A1 - Page 680 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276051
District:
County:
TRANSPORTATION PLANNING
MIAMI-DADE MPO UPWP FY 2014/2015 & 2015/16 PL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
0 0 0 0 04,740 0 4,740
0 0 0 0 0869 0 869
0 0 0 0 0 05,609 5,609TotalPLANNING
$5,609Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,734427605Item Number:
RESPONSIBLE AGENCY: MIAMI DADE MPO
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276052
District:
County:
TRANSPORTATION PLANNING
MIAMI-DADE MPO UPWP FY 2016/2017 & 2017/2018 PL
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 434 434 0 0 00 0 868
PL 1,791 1,791 0 0 00 0 3,582
2,225 2,225 0 0 0 00 4,450TotalPLANNING
$4,450Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,734427605Item Number:
RESPONSIBLE AGENCY: MIAMI DADE MPO
Section A1 - Page 681 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276053
District:
County:
TRANSPORTATION PLANNING
MIAMI-DADE MPO UPWP FY 2018/2019 & 2019/2020
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 434 434 00 0 868
PL 0 0 1,791 1,791 00 0 3,582
0 0 2,225 2,225 0 00 4,450TotalPLANNING
$4,450Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,734427605Item Number:
RESPONSIBLE AGENCY: MIAMI DADE MPO
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4276054
District:
County:
TRANSPORTATION PLANNING
MIAMI-DADE MPO UPWP FY 2020/2021 & 2021/2022
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
LF 0 0 0 0 4340 0 434
PL 0 0 0 0 1,7910 0 1,791
0 0 0 0 2,225 00 2,225TotalPLANNING
$2,225Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $16,734427605Item Number:
RESPONSIBLE AGENCY: Miami-Dade Aviation Department
Section A1 - Page 682 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4280441
District:
County:
TRANSPORTATION PLANNING
PLEMO OPERATING FUND NON-PROJECT SPECIFIC CONSULTANT TASKS
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
MIAMI-DADE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 183 183 183 183 183734 0 1,649
183 183 183 183 183 0734 1,649TotalPLANNING
$1,649Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $1,649428044Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4324511
District:
County:
PTO STUDIES
DISTRICTWIDE PUBLIC TRANSPORTATION CONSULTANT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 300 300 300 300 5000 0 1,700
300 300 300 300 500 00 1,700TotalPLANNING
$1,700Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,022432451Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 683 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4324512
District:
County:
PTO STUDIES
DISTRICTWIDE FREIGHT LOGISTICS & PASSENGER OPS CONSULTANT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 272 0 300 400 2001,150 0 2,322
272 0 300 400 200 01,150 2,322TotalPLANNING
$2,322Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $4,022432451Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
Section A1 - Page 684 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING
$12,493,061$5,398,387 $2,839,163$1,402,776 $1,086,066 $857,948 $498,155 $410,566
Proposed Funding (in $000s)
2016 - 2017
2017 - 2018
2018 - 2019
2019 - 2020
2020 - 2021 >2021<2017 All Years
Funding Source
MPO Project No:
Type of Work:
Project Description:
DT4330572
District:
County:
PTO STUDIES
DISTRICTWIDE PUBLIC TRANSPORTATION CONSULTANT SERVICES
Roadway ID:
Project Length:
Lanes Exist:Lanes Improved:Lanes Added:
DIST/ST-WIDE
LRTP Ref:
6
5-5
SIS or Non-SIS: No
PHASE :
Extra Description:
D 500 500 500 500 5000 0 2,500
500 500 500 500 500 00 2,500TotalPLANNING
$2,500Item Segment TOTAL ALL Years ALL Phases:
Item TOTAL ALL Years ALL Phases ALL Segments: $5,050433057Item Number:
RESPONSIBLE AGENCY: Florida Department of Transportation District 6
$7,673 $7,861 $7,891 $8,023 $8,049$70,147 $0 $109,644Yearly Totals
5 Year TIP Total $39,497TRANSPORTATION PLANNING
Yearly Totals
5 Year TIP Total $4,255,511
TOTAL COSTS - ALL PROJECTS
Florida Department of Transportation
Section A1 - Page 685 of 685FY 2017-2021 Approved May 19, 2016
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION
TRANSPORTATION IMPROVEMENT PROGRAM
PRIMARY STATE HIGHWAYS AND INTERMODAL
TRANSPORTATION PLANNING