8/8/2019 Reach a Utility Shifting
http://slidepdf.com/reader/full/reach-a-utility-shifting 1/4
Contractor
Page 1 BMRCL
BANGALORE METRO RAIL CORPORATION LIMITED
(A Joint Venture of Govt. of India and Govt. of Karnataka)BMTC Complex, 3rd floor, Shanthinagar,
K.H. Road, Bangalore-560027.Ph: 080-22969300, 22969301 Fax: 22969222E-mail: [email protected] Web:www.bmrc.co.in
No.: BMRCL/Tender/E-155/US/2009-10/6160 Date: 06/02/2010
SHORT TERM TENDER NOTIFICATION
Bangalore Metro Rail Corporation Ltd. (BMRCL) a Joint Venture of Government of Karnataka and Government of India invites sealed tenders from eligible agencies for ‘Shifting of BESCOM High Tension / Low Tension, Under Ground / Overhead electricalutilities in the phase – 1 alignment of Bangalore Metro Rail Project from RajalaxmiKalyan Mantap to Sarakki Junction in Reach-4A.
Details of the Tender are as under:
Completion Period: 1. For Stretch.1 -90 Days.
2. For Stretch.2 -180 Days
Financial/Technical Eligibility Criteria for Bidders:
1. The Bidder should have a valid class-1 electrical license issued by the
Electrical Inspectorate, Govt. of Karnataka. Notarized copy of the License
shall be furnished. Original Document of the license will have to be produced
for verification by BMRCL after opening of the Technical bid as requested.
2. The bidder should have experience in creation of Transmission &
distribution networks of EHT, HT/ LT both Underground and Overhead andshould have completed similar works and fulfill the following to establish the
same:
a. The bidder should have executed at least one similar completed work
during the last five years ending 31.03.2009 of value not less than
Rs.3,04,00,000/- (Rupees Three Crores and Four Lakhs only). The Bidder
shall furnish clients’ certificates in support of the same.
or
Sl.No Name of the Work Stretch
Approximateamount putto Tender
in Rs.
Cost of theTender
Documentsin Rs.
EMDin Rs.
1.Shifting of BESCOMLT/HT UG/Overheadelectrical utilities in thealignment of Bangalore Metro RailProject Phase-1 fromRajalaxmi KalyanMantap to SarakkiJunction in Reach-4A
1. Rajlaxmi KalyanMantap toShastri Bakery,Banashankari(EP 1 to EP 27)
2. Shastri Bakery toSarakki Junction(EP 27 to EP 63)KanakapuraRoad.
3.8 Crores
Rs.25,000/-(RupeesTwenty
FiveThousand
only )
3.8Lakhs
![Page 2: Reach a Utility Shifting](https://reader030.vdocument.in/reader030/viewer/2022021119/577d36081a28ab3a6b91fd74/html5/thumbnails/2.jpg)
8/8/2019 Reach a Utility Shifting
http://slidepdf.com/reader/full/reach-a-utility-shifting 2/4
Contractor
Page 2 BMRCL
b. The bidder should have executed at least two similar completed
works during the last five years ending 31.03.2009, each of value not
less than Rs.1,90,00,000/-(Rupees One Crore Ninety Lakhs only). The
Bidder shall furnish clients’ certificates in support of the same.
or
c. The bidder should have executed at least three similar completed works
during the last five years ending 31.03.2009 each of value not less thanRs.1,52,00,000/-(Rupees One Crore Fifty Two lakhs only). The Bidder
shall furnish client’s certificates in support of the same.
3. The bidder should have an average annual turnover during the last three
years ending 31.03.2009, of at least Rs.2,28,00,000/- (Rupees Two Crores
Twenty Eight lakhs only).
4. The Bidder shall furnish copies of audited and certified financial reports in
support of the same, for the financial years 2006-07, 2007-08 and 2008-09.
5. The Bidder should not have been black listed by any government department.The Bidder should furnish a declaration to that effect.
6. i) For Fresh Bidders.
The details of deployment of the following personnel should be furnished in
format I.
1. Project Manager.2. Project Engineer.3. Site Engineer.
Format I.
Sl.No.
DetailsPertaining to:
Name of the
person
EducationalQualification
ExperiencePosition
heldRemarks
1.Personnel for the Tenderedworks.
ii) For BMRCL Working Contractors
Contractors already working with BMRCL, who intend to participate in the
tender, shall possess the following additional requirements for qualifying in
the Bid.
a) Annual average turnover mentioned in clause (3) above, should be
equivalent to the sum of the turnover required for the works they are
already carrying out in BMRCL and the turnover required for tendered
works.
b) Separate team of personnel is required to be deployed for each works,
particularly the Project Engineers and the Site Engineers. The curriculum
Vitae of the personnel deployed / to be deployed shall be furnished as
detailed in Clause (c) below.
![Page 3: Reach a Utility Shifting](https://reader030.vdocument.in/reader030/viewer/2022021119/577d36081a28ab3a6b91fd74/html5/thumbnails/3.jpg)
8/8/2019 Reach a Utility Shifting
http://slidepdf.com/reader/full/reach-a-utility-shifting 3/4
Contractor
Page 3 BMRCL
c) The details of deployment of the following personnel should be furnished
in format II.
1) Project Manager.
2) Project Engineer.
3) Site Engineer.
Format II
Sl.No.
DetailsPertaining to:
Name of the
person
EducationalQualification
ExperiencePosition
heldRemarks
1.Personnel for the ongoingworks.
2Personnel for the newtendered work
7. Joint venture or a consortium is not allowed.
Notwithstanding anything stated above or elsewhere in the tender specification,
BMRCL reserves the right to relax the qualifying requirements and assess the
capability/suitability of the Bidder to perform the overall contract should the
circumstances warrant such assessment in the overall interest of BMRCL.
Bidder shall have adequate erection facilities and capabilities. The Bidder shall
have quality assurance plan for procuring of materials, erection and
commissioning. The Bidder shall furnish documentary evidence in support of the
qualifying requirements stipulated as above.
Bid documents will be issued to Bidders on the strength of their claim in goodfaith. However such issue of Bid document will not automatically mean that
Bidders are considered qualified. Such qualification will be reviewed again at the
time of the evaluation of the bids. Intending parties who fulfill the qualifying
requirements are advised to visit the sites to familiarize themselves with the
nature and quantum of works & site conditions.
COMPLETION PERIOD:
A) Time is the essence of this contract. Period of completion from the date of
letter of award (LOA) for the entire work is 90 Days for Stretch1 and 180 Days
for Stretch2.
B) If an existing cable is damaged and to be provided with one/two numbers of
straight through joint/s without any additional cable/with small cable piece up to a
length of 10m, the same shall be completed within 2 to 3 days from the day the
cable is identified for jointing.
C) The contractor shall complete any specific work of cable shifting(less than
50m length) within 15 days from the date cable is identified and notice to start the
work is intimated orally/in writing by Engineer-in-Charge.
![Page 4: Reach a Utility Shifting](https://reader030.vdocument.in/reader030/viewer/2022021119/577d36081a28ab3a6b91fd74/html5/thumbnails/4.jpg)
8/8/2019 Reach a Utility Shifting
http://slidepdf.com/reader/full/reach-a-utility-shifting 4/4
Contractor
Page 4 BMRCL
D) The contractor shall complete any specific work of cable shifting(more than 50
m length) within 30 days from the date cable is identified and notice to start the
work is intimated orally/in writing by Engineer-in-Charge.
E) The contractor shall complete pole mounted transformer shifting works/
providing new spun pole with structure materials within 30 days from the date
location is identified and notice to start the work is intimated orally/in writing byEngineer-in-Charge.
Tender documents can be obtained from 08.02.2010 to 22.02.2010 during the office
working days and hours on payment of the above mentioned tender document cost in
form of DD drawn in favor of Bangalore Metro Rail Corporation Limited payable at
Bangalore along with a requisition letter.
Date of submission of sealed tender documents is up to 24.02.2010 during office hours
between 11.00 hours and 15.00 hours (IST).
Tenders will be opened on the same day (i.e. on 24.02.2010) at 15.30 hours (IST) in
the presence of the available bidders/representatives of the bidders.
The tender opening shall be in two parts. The Technical Bid shall be opened on the
tender opening day as mentioned above. The Financial Bid of the technically qualified
bidders shall be opened on the notified day.
BMRCL reserves the right to reject or accept any or all offers without assigning any
reason whatsoever.
for Bangalore Metro Rail Corporation Ltd.
-sd-
Dy. Chief Engineer Electrical (Traction)