redesign of the international timetabling process (ttr) · 2019. 10. 31. · 12 ttr pilots: lessons...

26
1 REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR) supported by TTR Plenary Day Vienna, 25 September 2019

Upload: others

Post on 26-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • 1

    REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS

    (TTR)

    supported byTTR Plenary Day

    Vienna, 25 September 2019

  • 2

    TTR pilots

  • 3

    TTR Pilots: Topics

    − Aim of the pilots, organisational set-up

    − Phase 1 of pilots and first achievements

    − Phase 2 of pilots and first findings

    − Q&A

  • 4

    Introduction to TTR Pilots

    In order to test the new approach to capacitymanagement developed in TTR, several pilotshave been launched:

    - Test the innovative components in real life

    - To improve the process

    - Definition and specification of data referencemodel for capacity

    - To detect pressure points

    - To use lessons learned for full TTR rollout

    The focus when selecting the pilots was on RFC lines: Possibility of own rules thanks to FCA (Framework for Cap. Allocation, 913/2010/EU).

  • 5

    Introduction to TTR Pilots

    The pilot itself will be conducted in three phases:

    - Phase 1: Capacity partitioning andcapacity planning

    - Phase 2: Capacity publication and capacity requests for TT 2020

    - Phase 3: Running timetable 2020

  • 6

    Introduction to TTR Pilots

    TTR overall structure:

  • 7

    TTR Pilots: Achievements (I)

    − Development of functioning organisations for the respective pilots

    − Good cooperation thanks to highly motivated IMs

    − Broad-based willingness ofstakeholders (Ministries, ports/terminals, Regulatory Bodies,applicants) to participate in thepilots

    Ex.: Organisation of Pilot Antwerp - Rotterdam

  • 8

    TTR Pilots: Achievements (II)

    − Creation of Cap. Models with the support of applicants for TT 2020

    − Publication of available capa-city for TT 2020 in Jan. 19

    − Availability of a tool (PCS) forplacing the first RollingPlanning requests in Aug. 19

    − First requests for RollingPlanning Cap. for TT 2020received

  • 9

    TTR Pilots: Achievements (III)

    − Publication of a “Pilot Information Document”

    Pilot Information Document focusses on thedescription of the new TTR concepts that aretested in the pilot.

  • 10

    TTR Pilots: Achievements (IV)

    − Development of a ECMT (tool for visualising Cap. Model)

  • 11

    TTR Pilots: Lessons Learned (I)

    − Management attention is crucial for the success of the pilots

    − Planning and coordination of TCRs respecting 2012/34 Annex VII is still difficult

    − Benefits for passenger RUs must be tested as well

    − Ministries of Transport and Regulatory Bodies are required to implement strategic thinking (not only based on existing laws) and allow tests

    − Need for increased resources for IT implementation (nat. and internat. level)

    − Commercial Conditions required to influence applicants’ path requesting behaviour and IMs’ allocation processes (incentive to respect agreed processes)

    − Multi-annual validity of a Rolling Planning request require legal backing

  • 12

    TTR Pilots: Lessons Learned (II)

    Path requests for TT 2020:

    − Capacity Model was built based on announcements from applicants with their needs for Annual TT and Rolling Planning traffic

    − Pilots published PaPs (as required by 913/2010) and Rolling Planning Cap. in January 2019, based on these announcements

    − Experiences:

    o Applicants requested PaPs for pre-announced Rolling Planning Cap.

    o Applicants requested Internat. Rolling Planning Cap. as Annual TT traffic by using national tools (Pilot Antwerp-Rotterdam)

    o Paths were requested in time windows where no capacity was published in the Cap. Model

    − TTR pilot message has not clearly beeing understood by applicants even they were deeply involved as member of the Pilot Advisory Board

  • 13

    Findings in the TTR Pilots− Absence of (harmonised) rules on capacity partitioning phase constitutes a

    risk − Example: Some IMs are concerned that RBs may e.g. challenge their capacity

    model/split.

    − Different interpretation of Directive 2012/34 leads to heterogenous national legal frameworks and/or (uncoordinated) RB action that may hamper a harmonised implementation of TTR.

    − Example 1: diverging opinions regarding the possibility to set aside capacity for rolling planning requests lead to legal uncertainty e.g. in case of an annual TT request conflicting with safeguarded RP capacity

    − Example 2: national capacity allocation frameworks are in some MS enshrined in law and much more detailed than EU law, limiting the IM’s ability to implement TTR

    − Example 3: diverging national law and RB decisions on commercial conditions (FR vs DE vs IT etc.) make it difficult, if not impossible, for IMs to agree on a common set of CCs

  • 14

    TTR Pilot Antwerp – Rotterdam

    − Creation of Capacity Model

    • Applicants had difficulties to make a traffic forecast, proposed to take IMs own historical data.

    • Inclusion of TCRs:

    − Asset/construction departments of ProRail and Infrabel exchanged information/data for the first time for the mid-term planning.

    − Stability of TCR planning, but not all TCRs need to be planned in Annual Timetable

    − TCRs on other lines with an impact on the pilot line

    • Splitting of available capacity was a challenge. What are the shares for Pre-arranged Paths/PaPs (legally still required), Annual Timetable and Rolling Planning Cap.?

  • 15

    TTR Pilot Antwerp – Rotterdam

    − Capacity publication and requests for TT 2020

    • On-time publication in an Excel-file (https://cms.rne.eu/ttr-communication-platform/rotterdam-antwerp-library)

    • TCR: up to 75% of published TCRs needed to be changed

    • Participating key applicants have a different approach/vision on Rolling Planning

    • Despite Rolling Planning Offer, 1/3 more requests for Annual Timetable 2020 than real usage in TT 2019 (… and based on last years’ experiences will be cancelled…)

    • First intentions of applicants for placing Rolling Planning requests failed due to missing PCS experience.

  • 16

    TTR Pilot Antwerp – Rotterdam

    − Capacity Model for TT 2021

    • First known TCRs already discussed between BE, NL and DE (rerouting)

    • A two step approach is foreseen:

    − X-11: Publication of Annual TT Cap., Rolling Planning volume for a standard day and known TCRs

    − X-6: Rolling Planning Cap. for 365 days, update of TCRs (incl. inclusion of minor TCRs)

    • Elaboration of Cap. Model with the support of ECMT

    • Analysis of extension of pilot line from Antwerp via Brussels to Paris (inclusion of high-speed passenger trains)

  • 17

    TTR Pilot RFC Atlantic

    − Creation of Capacity Model• Inclusion of

    − traffic data section by section fora normal day

    − Regular-interval timetable

    − Freight traffic matrix includingcapacity bandwidths

    − 24-hour view of the model(bandwidths and TCRs)

    • Aim to offer 8 paths for AnnualTimetable and 2 for RollingPlanning Traffic

  • 18

    TTR Pilot RFC Atlantic

    − Creation of Capacity Model for TT 2020 had to be stopped

    • Due to high amount of TCRs with a negative impact on the foreseen capacity

    • Low level of TT colleagues’ availability to study an axis view

    • TT colleagues were not convinced that TTR will help them and tried to stick to former process which led to delays, lack of coordination and improper use of the capacity model

  • 19

    TTR Pilot RFC Atlantic

    − Capacity Model for TT 2021 & 2022

    • Creation of models are still in progress. Nevertheless, process are still to be written and shared by all entities involved.

    • Cap. Model TT 2021 for Atlantic pilot considers a single band with 5 long-distance paths each way (4 for Annual TT, 1 for Rolling Planning without any multiannual consideration)

    • For now, risk still exists to have no commercial capacity for TT2021 due to too confiscatory TCRs.

  • 20

    TTR Pilot Munich – Verona

    − Creation of Capacity Model

    • Inputs (cap. needs) of applicants: early announcements change massively from the first request at X-16 till the second request at X-9

    • TTR-Pilot Brenner observed avery high variance ofannouncements from thedifferent applicants

    • TCRs: IM planning process notstable. Hence, input for Cap.Model is too volatile

  • 21

    TTR Pilot Munich – Verona

    − Capacity publication and requests for TT 2020

    • On-time publication in an Excel-file of pre-constructed system pathsfor Annual TT and capacity bands with Rolling Planning paths for everyweekday (https://cms.rne.eu/ttr-pilots-communication-platform/brenner-library)

    • Customers indicate demandfor Rolling Planning also atAnnual TT deadline toensure the reservation forRolling Planning capacity

    • Several requests for RollingPlanning capacity werealready placed

  • 22

    TTR Pilot Munich – Verona

    − Capacity Model for TT 2021

    • Start of discussions on different ways to shift dynamic traffic from the Annual TT to Rolling Planning (incl. exchange of view for Rolling Planning capacity with applicants)

    • Validation of Cap. Model based on early announcements as a base for Rolling Planning capacity is regarded as critical

    − Other issue

    • Discussion with German Regulatory Body regarding the treatment of the TTR pilot in the Network Statement

  • 23

    TTR Pilot ÖBB Network

    Capacity Model including system paths for Timetable 2021 is currently being developed and the possibility of technical implementation in path planning/scheduling is being examined.

  • 24

    Experiences from TTR Pilots

    o Common commercial conditions

    o IT

    o Legal framework (national)

    The TTR Pilots showed: Several preconditions need to be provided!

    Planning capacity needs to be predictable and reliable.

  • 25

    How to Support the Pilots?

    − Implement /experiment with TTR process elements in your network− Capacity model is the key element and can be tested “outside” normal process

    (applicable for lines/countries that are not yet involved in a pilot)

    − Reduce national particularities by increasing the willingness to change national processes and adapt them with neighbours

    − Start discussions between Regulators/Ministries, IMs and RBs about the adaptations that are needed for TTR on national level

    The TTR team gladly shares its knowledge and helps in implementing tests of TTR items!

  • 26