reference project · reference project . year of implementation: 2018- 2020 . project: natural poem...

6
REFERENCE PROJECT Year of Implementation: 2018-2020 Project: NATURAL POEM APARTMENT – Block 1. Work items: MEP SYSTEM Address: 629 Kinh Duong Vuong, An Lac Ward, Binh Tan District, HCM City, Viet Nam. Summary Project: - Total Floor: 20 Floor Hight & 01 Basement. - Construction acreage: 18.100 m2. Year of Implementation: 2018-2020 Project: NATURAL POEM APARTMENT – Block 2 Work items: Hthống Điện (M&E) Address: 629 Kinh Duong Vuong, An Lac Ward, Binh Tan District, HCM City, Viet Nam. Summary Project: - Total Floor: 20 Floor Hight & 01 Basement. - Construction acreage: 18.100 m2. Year of Implementation: 2018-2019 Project: Factory For Rent 6Ha Work items: MEP SYSTEM Address: 7C Street, Nhơn Trạch II Industrial Zone - Đong Nai. Summary Project: - Total: 5 Factory. - Construction acreage: 34.000 m2

Upload: others

Post on 06-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • REFERENCE PROJECT

    Year of Implementation: 2018-2020 Project: NATURAL POEM APARTMENT – Block 1. Work items: MEP SYSTEM

    Address: 629 Kinh Duong Vuong, An Lac Ward, Binh Tan District, HCM City, Viet Nam.

    Summary Project: - Total Floor: 20 Floor Hight & 01 Basement. - Construction acreage: 18.100 m2.

    Year of Implementation: 2018-2020

    Project: NATURAL POEM APARTMENT – Block 2 Work items: Hệ thống Điện (M&E)

    Address: 629 Kinh Duong Vuong, An Lac Ward, Binh Tan District, HCM City, Viet Nam.

    Summary Project: - Total Floor: 20 Floor Hight & 01 Basement. - Construction acreage: 18.100 m2.

    Year of Implementation: 2018-2019

    Project: Factory For Rent 6Ha Work items: MEP SYSTEM

    Address: 7C Street, Nhơn Trạch II Industrial Zone - Đong Nai.

    Summary Project: - Total: 5 Factory. - Construction acreage: 34.000 m2

  • Year of Implementation: 2016-2018 Project: Khang Viet Apartment (Block 3)

    Address: Phu Huu Ward, District 9, HCM City Viet Nam.

    Work items: MEP System Summary Project: - Total Floor: 19 Floor Hight & 01 Basement. - Construction acreage: 7500 m2.

    Year of Implementation: 2017-2018 Project: Casta Long Khanh-Dong Nai Factory. Work items: MEP SYSTEM

    Address: Lot M, Long Khanh Industrial, Binh Loc Ward, Long Khanh Town, Dong Nai Province

    Summary Project: Supply and installation MEP System.

    Construction acreage 80.000 m2

    Year of Implementation: 2016-2017 Project: Vina Kraft Factory Binh Duong (ETP2) Work items: E&I system

    Address: D-6A-CN, My Phuoc III Industrial, Ben Cat Town, Binh Duong Province

    Summary Project: - Supply & Installation Cable ladder & cable tray

    system. - Supply & Installation Electrical & Instrument

    system

  • Year of Implementation: 2016-2017

    Project: Khang Viet Apartment (Block 1) Work items: MEP System

    Address: Phu Huu Ward, District 9, HCM City Viet nam.

    Summary Project: - Total Floor : 18 Floor Hight & 01 Basement. - Construction acreage: 8000 m2

    Year of Implementation: 2015-2016 Project: First Home Thu Duc(Saigon Metro Park) Work items: MEP System

    Address: Road No 01, Truong Tho Ward, Thu Duc District, HCM City, Việt Nam.

    Summary Project: - Total Floor : 15 Floor Hight & 01 Basement. - Construction acreage: 5500 m2

    Year of Implementation: 2014-2015 Project: Vinakyoei Steel Water treament Work items: E&I System

    Address: Phu My I Industrial, Tan Thanh Ward, Ba Ria – Vung Tau Province.

    Summary Project: - Supply & Installation Cable ladder & cable tray

    system. - Supply & Installation Electrical & Instrument

    system

  • Year of Implementation: 2015-2016 Project: First Home Binh Duong Work items: MEP System Address: Hung Dinh Ward,Thuan An Town , Binh Dương Province.

    Summary Project: - Total Floor : 18 Floor Hight & 01 Basement. - Construction acreage: 9740 m2

    Year of Implementation: 2014-2015

    Project: First home Thanh Loc - Dist.12. Work items: MEP System

    Address: Thanh Loc Ward, Dist.12 , HCM City Summary Project:

    - Total Floor : 14 Floor Hight & 01 Basement. - Construction acreage: 5000m2

    Year of Implementation: 2013-2014 Project: Center for training women's knowledge in Ho Chi Minh City.

    Work items: MEP System Address: 20 Nguyen Van Giai Street, Dist.2, HCM City.

    Summary Project: - Total Floor : 14 Floor Hight & 01 Basement - Construction acreage: 7000m2

  • Year of Implementation: 2012 Project: Canadian International Primary School Work items: MEP system

    Address: Phu My Hung Ward, Dist.7, HCM City Summary Project: - Total : 4 Floor - Construction acreage: 13.000m2 - Total room: 60 room

    Year of Implementation: 2009 - 2011

    Project: Blue Saphire Binh Phu Work items: MEP System Address: 29 Binh Phu Street, Dist.6, HCM City Summary Project: - Total Floor : 15 Floor Hight & 01 Basement. - Construction acreage : 18. 799 m2

    Year of Implementation: 2008-2009 Project: Building Kim Khi Company HCM Work items: MEP System Address: 189 Nguyen Thi Minh Khai Street ,HCM City Summary Project:

    - Total Floor 10 Floor. - 02 Basement.

  • Year of Implementation: 2007-2008 Project: Factory Pharmacy Nanogen Work items: MEP System Address: High – Tech Zone Didt.9, HCM City Summary Project:

    - Clean room GMP-WHO standard. - RO clean water system

    Year of Implementation: 2007-2008 Project: Factory Kingjim File Work items: MEP System Address: My Phuoc III Industrial, Binh Duong. Summary Project: Construction : 6 ha

    • We are committed to the above Projects that we have done are absolutely true.

    GENERAL DIRECTOR

    GIANG THANH TRUONG

    Address: Lot M, Long Khanh Industrial, Binh Loc Ward, Long Khanh Town, Dong Nai ProvinceSummary Project:Address: D-6A-CN, My Phuoc III Industrial, Ben Cat Town, Binh Duong Province