renewable rfp process update september 26, 2007 renewable rfp process update september 26, 2007
TRANSCRIPT
![Page 1: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/1.jpg)
Renewable RFP Process Update
September 26, 2007
Renewable RFP Process Update
September 26, 2007
![Page 2: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/2.jpg)
2
BackgroundBackground
Renewable RFP issued – February 2007
Responses received – April 2007
Responses reduced to short-list – July 2007
Due diligence – July/August
Contract negotiations – August/September
Renewable RFP issued – February 2007
Responses received – April 2007
Responses reduced to short-list – July 2007
Due diligence – July/August
Contract negotiations – August/September
![Page 3: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/3.jpg)
3
Responses to RFPResponses to RFP
23 Projects proposed by 17 developers Two projects from outside Kansas
All responses were wind energy projects
Per MWh prices ranged from ~$35 - $70
Proposals were for both ownership and PPA’s
23 Projects proposed by 17 developers Two projects from outside Kansas
All responses were wind energy projects
Per MWh prices ranged from ~$35 - $70
Proposals were for both ownership and PPA’s
![Page 4: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/4.jpg)
4
Review TeamReview Team
Greg Greenwood, Team Leader
Westar Energy employees from the following areas: Generation resource planning Environmental Finance Transmission Legal Regulatory
HDR Engineering
Black & Veatch
Les Evans, KEPCO, VP Power Supply
Alan Pollom, The Nature Conservancy
Greg Greenwood, Team Leader
Westar Energy employees from the following areas: Generation resource planning Environmental Finance Transmission Legal Regulatory
HDR Engineering
Black & Veatch
Les Evans, KEPCO, VP Power Supply
Alan Pollom, The Nature Conservancy
![Page 5: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/5.jpg)
5
Evaluation Criteria to Make Short-ListEvaluation Criteria to Make Short-List
Public/Community Acceptance
Environmental Compatibility/Acceptance
Credit Risk
Levelized Cost -Revenue Requirements (PPA or Ownership)
Transmission Upgrade Costs
Wind Turbine Equipment Evaluation
Developer Experience
Public/Community Acceptance
Environmental Compatibility/Acceptance
Credit Risk
Levelized Cost -Revenue Requirements (PPA or Ownership)
Transmission Upgrade Costs
Wind Turbine Equipment Evaluation
Developer Experience
![Page 6: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/6.jpg)
6
Short-list ProcessShort-list Process
Seven projects remained after initial screening process
Short-list project developers invited to half-day due diligence sessions in Topeka
Refined selection criteria used to reduce short-list to 500 MW’s to begin negotiations
Seven projects remained after initial screening process
Short-list project developers invited to half-day due diligence sessions in Topeka
Refined selection criteria used to reduce short-list to 500 MW’s to begin negotiations
![Page 7: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/7.jpg)
7
Evaluation Criteria - Short-List to NegotiationsEvaluation Criteria - Short-List to Negotiations
Environmental Analysis/ Public Acceptance 5%
Production Tax Credit Certainty 5%
Credit Risk 5%
Levelized Cost -Revenue Requirements (PPA or Ownership) 35%
Transmission Costs 15%
Developer Construction Experience 10%
Wind Turbine Equipment Evaluation 15%
Developer Interview 10%
Environmental Analysis/ Public Acceptance 5%
Production Tax Credit Certainty 5%
Credit Risk 5%
Levelized Cost -Revenue Requirements (PPA or Ownership) 35%
Transmission Costs 15%
Developer Construction Experience 10%
Wind Turbine Equipment Evaluation 15%
Developer Interview 10%
![Page 8: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/8.jpg)
8
Selection ProcessSelection Process
Absolute project score did not always determine projects selected due to:
Transmission constraints
Wind diversity goals
Excess turbine diversity
Other
Absolute project score did not always determine projects selected due to:
Transmission constraints
Wind diversity goals
Excess turbine diversity
Other
![Page 9: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/9.jpg)
9
Ownership vs. PPAOwnership vs. PPA
Our analysis showed little cost difference to customers
Ultimate answer to economics question can’t be known today
Our conclusion - - Diversity of ownership reduces risk for Westar and its customers
Targeting ~50% ownership, 50% PPA’s in 500 MW portfolio
Our analysis showed little cost difference to customers
Ultimate answer to economics question can’t be known today
Our conclusion - - Diversity of ownership reduces risk for Westar and its customers
Targeting ~50% ownership, 50% PPA’s in 500 MW portfolio
![Page 10: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/10.jpg)
10
Contract NegotiationsContract Negotiations
Negotiating with four developers currently for 500MW of Wind
Contracts near completion - - But not complete
Filing for predetermination of rate treatment planned no later than October 1st
KCC decision requested by yearend
Negotiating with four developers currently for 500MW of Wind
Contracts near completion - - But not complete
Filing for predetermination of rate treatment planned no later than October 1st
KCC decision requested by yearend
![Page 11: Renewable RFP Process Update September 26, 2007 Renewable RFP Process Update September 26, 2007](https://reader036.vdocument.in/reader036/viewer/2022072016/56649efa5503460f94c0b845/html5/thumbnails/11.jpg)
11
Wind RFP HighlightsWind RFP Highlights
Cost per MWh (levelized) ranged from $35 - $70 Selected 500 MW portfolio – low $40’s/MWh Costs exclude dispatch inefficiency and assumes
PTC’s are extended
300MW’s of wind energy currently scheduled to be online in 2008
Public announcement of specific projects expected soon
Cost per MWh (levelized) ranged from $35 - $70 Selected 500 MW portfolio – low $40’s/MWh Costs exclude dispatch inefficiency and assumes
PTC’s are extended
300MW’s of wind energy currently scheduled to be online in 2008
Public announcement of specific projects expected soon