renovation of saline embankment of narvel, benavale
TRANSCRIPT
Renovation of Saline Embankment of
Narvel, Benavale villages in
Pen Taluka, Raigad District, Maharashtra
(IN -RRD-2628 – CW – RFB)
Environmental Impact Assessment Report
EIA Consultant:
EQMS INDIA PVT. LTD. INDIA
304-305, 3rd Floor, Plot No. 16, Rishabh Corporate Tower,
Community Centre, Karkardooma, Delhi – 110092
Phone: 011-43062757; 42270087
Website: www.eqmsindia.com ; E-mail – [email protected]
STATE PROJECT IMPLEMENTATION UNIT, NCRMP II,
RELIEF AND RENOVATION DEPARTMENT, GOVERNMENT OF
MAHARASHTRA
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 2
Table of Contents
Executive summary ........................................................................................................... 8
Chapter 1. Introduction and Project Background ........................................................... 20
1.1. Project Background ............................................................................................. 20
1.2. Project Overview ................................................................................................. 22
1.3. Need of the Sub-Project ...................................................................................... 23
1.4. Benefits of the Project ......................................................................................... 23
1.5. Need of Environment Impact Assessment Study ................................................ 24
1.6. Objective of EIA study ......................................................................................... 25
1.7. Scope of the EIA Study ....................................................................................... 25
1.8. Approach and Methodology ................................................................................ 26
1.9. Limitation of EIA Study ........................................................................................ 27
1.10. Structure of the EIA Report ................................................................................. 27
Chapter 2. Regulatory Clearances/Permission requirement .......................................... 29
2.1. Introduction ......................................................................................................... 29
2.2. Environmental Standards .................................................................................... 38
2.3. Key safeguard documents ................................................................................... 38
Chapter 3. Project Description ....................................................................................... 39
3.1. Introduction ......................................................................................................... 39
3.2. Project Location and Its Connectivity .................................................................. 39
3.3. Condition of existing embankment ...................................................................... 40
3.4. Existing facilities on and around embankment .................................................... 41
3.5. Natural Hazards of the Project Area .................................................................... 41
3.6. Description of The Project ................................................................................... 41
3.7. Right of Way Detail & Land Details ..................................................................... 43
3.8. Existing Drainage Conditions .............................................................................. 43
3.9. Design Criteria ..................................................................................................... 44
3.10. Proposed Project Components and Construction Methodology .......................... 44
3.11. Slope Stabilization ............................................................................................... 45
3.12. Waste Generation and Management ................................................................... 45
3.13. Construction Material Requirement ..................................................................... 46
3.14. Time and Implementation .................................................................................... 46
3.15. Project Cost ......................................................................................................... 47
Chapter 4. Description of the Environment .................................................................... 48
4.1. Introduction ......................................................................................................... 48
4.2. Site Description and Its Environmental Salient Features ..................................... 48
4.2. Climate ................................................................................................................ 55
4.3. Seismicity and Associated Hazards all along the waterways .............................. 56
4.4. Soil ...................................................................................................................... 56
4.5. Water Environment .............................................................................................. 56
4.6. Biological Environment (Project Site and Zone of 1 km radius) ........................... 57
4.7. Socioeconomic Environment ............................................................................... 63
4.8. Archaeological Sites: ........................................................................................... 66
Chapter 5. Environmental Impacts and Mitigation Measures ......................................... 67
5.1. Introduction ......................................................................................................... 67
5.2. Project Influence or Environmental Impact Area ................................................. 67
5.3. Identification of Project Activities and Associated Impacts .................................. 67
5.4. Impact Assessment and Evaluation .................................................................... 70
5.5. Impacts during pre-construction and construction Phase .................................... 70
5.5.1 Impact Due to Shifting of Utilities ......................................................................... 70
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 3
5.5.2 Impact Due to Shifting of Community/Religious Resources/Properties and Access to Properties ................................................................................................................... 71
5.5.3 Impact on Private land and Property ................................................................... 72
5.5.4 Impact Due to Clearing of Vegetation and Cutting of Trees and Impact on Mangroves ..................................................................................................................... 73
5.5.5 Impact Due to setting up of Construction Camp, material storage and debris disposal areas ................................................................................................................ 74
5.5.6 Impact Due to Setting up of Labour camps ......................................................... 76
5.5.7 Impact Due to Waste Generation and Setting up Debris Disposal Site ............... 78
5.5.8 Impact Due to Construction Material Sourcing and Establishment of Borrow Areas… .......................................................................................................................... 78
5.5.9 Impact Due to Transportation of Construction Material and Debris ..................... 82
5.5.10 Impacts Due to Hiring of Labour .......................................................................... 82
5.5.11 Impact due to Operation and Management of the construction vehicle and machinery ....................................................................................................................... 83
5.5.12 Impact on Drainage due to Siltation during Renovation of Embankment and Reconstruction of Cross Drainage works ....................................................................... 83
5.5.13 Impact on Slope Due to Embankment Renovation Works ................................... 85
5.5.14 Impact on Water Resources ................................................................................ 85
5.5.15 Impact on Water Quality ...................................................................................... 86
5.5.16 Impact on Top Layer of Soil and Soil Quality ...................................................... 87
5.5.17 Impact on Air Quality ........................................................................................... 88
5.5.18 Impact on Noise Level ......................................................................................... 89
5.5.19 Impact on Occupational Health & Safety of workers due to project activities ...... 90
5.5.20 Impact due to Contractor Demobilization ............................................................ 93
5.6. Impacts during Operation phase ......................................................................... 94
5.7. Summary Outcome ............................................................................................. 94
Chapter 6. Alternative Analysis ...................................................................................... 95
6.1. Introduction ......................................................................................................... 95
6.2. Location (Alignment), Planning and Design Alternatives ..................................... 95
6.3. With and Without Project Criteria ........................................................................ 96
6.4. Summary Outcome ............................................................................................. 99
Chapter 7. Public Consultation .................................................................................... 100
7.1. Introduction ....................................................................................................... 100
7.2. Objective of Public Consultation ........................................................................ 100
7.3. Methodology and Outcome of Consultations ..................................................... 101
7.4. Disclosure ......................................................................................................... 103
7.5. Summary Outcome ........................................................................................... 103
Chapter 8. Environmnetal Management Plan .............................................................. 104
8.1. Introduction ....................................................................................................... 104
8.2. Objective of Environmental Management Plan ................................................. 104
8.3. Environmental Management Plan ..................................................................... 104
8.4. Consolidated Environmental Management Plan................................................ 151
8.5. Environmental Monitoring Plan.......................................................................... 171
8.6. Institutional Framework for Implementation of EMP .......................................... 173
8.7. Trainings and Capacity Building ........................................................................ 179
8.8. Reporting ........................................................................................................... 179
8.9. Documentation, Updating and Record Keeping ................................................ 181
8.10. Mechanism for Feedback and Adjustments ...................................................... 181
8.11. Regulatory Clearances /Permission Required ................................................... 182
8.12. Grievance Readdress System ........................................................................... 182
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 4
8.13. Environmental Management Budget ................................................................. 183
List of Tables
TABLE 1.1 : BENEFITS OF PROPOSED EMBANKMENT ........................................................................................................ 24 TABLE 2.1 : SUMMARY OF ENVIRONMENTAL AND OTHER LEGISLATION WITH APPLICABILITY SCREENING .................... 30 TABLE 2.2 : WORLD BANKS OPERATIONAL POLICIES - ENVIRONMENTAL & SOCIAL SAFEGUARD .................................... 37 TABLE 3.1 : EXISTING ELEVATION LEVELS OF THE SALINE EMBANKMENT ........................................................................ 40 TABLE 3.2 : EXISTING ELEVATION LEVELS OF THE SALINE EMBANKMENT ........................................................................ 41 TABLE 3.3 : SALINE FEATURES OF PROPOSED EMBANKMENT ........................................................................................... 42 TABLE 3.4 : SHOWING EXISTING AND PROPOSED RIGHT OF WAY (ROW)/BOTTOM WIDTH DETAILS .............................. 43 TABLE 3.5 : VILLAGE WISE DETAIL OF LAND REQUIREMENT ............................................................................................. 43 TABLE 3.6 : ESTIMATION OF QUANTITY OF WASTE ........................................................................................................... 45 TABLE 3.7 : LIST OF MATERIAL AND THEIR SOURCES WITH DISTANCES ............................................................................ 46 TABLE 3.8 : COST ESTIMATION OF THE RENOVATION OF EMBANKMENT......................................................................... 47 TABLE 4.1 : SALIENT ENVIRONMENTAL FEATURES OF NARVEL BENAVALE EMBANKMENT SITE ...................................... 49 TABLE 4.2 : LAND USE OF THE STUDY AREA ...................................................................................................................... 53 TABLE 4.3 : METEOROLOGICAL DATA OF ALIBAG (PERIOD: 1981-2010) ........................................................................... 55 TABLE 4.4 : SENSITIVE ENVIRONMENTAL FEATURE WITHIN 10 KM RADIUS OF THE NARVEL BENAVALE EMBANKMENT
SITE ........................................................................................................................................................................... 57 TABLE 4.5 : DETAIL OF TREES PRESENT ON EMBANKMENT .............................................................................................. 60 TABLE 4.6 : DETAIL OF A FEW PATCHES OBSERVED ON LAND SIDE DURING SURVEY ....................................................... 61 TABLE 4.7 : LIST OF CRUSTACEANS AND FISH IN STUDY AREA .......................................................................................... 62 TABLE 4.8 : POPULATION OF PROJECT AREA ..................................................................................................................... 65 TABLE 4.9 : SOCIO ECONOMIC PROFILE OF PROJECT AREA ............................................................................................... 65 TABLE 5.1 : IMPACT IDENTIFICATION MATRIX ................................................................................................................... 68 TABLE 5.2 : NOISE LEVELS DURING VARIOUS CONSTRUCTION PHASE AND FROM CONSTRUCTION MACHINERY ........... 89 TABLE 6.1 : ANALYSIS OF ALTERNATIVES ON THE VIEW OF “WITH AND WITHOUT” PROJECT SCENARIO ........................ 96 TABLE 7.1 : DETAILS OF PUBLIC CONSULTATION ............................................................................................................. 101 TABLE 8.1 : ENVIRONMENTAL MANAGEMENT PLAN FOR SALINE EMBANKMENT-NARVEL- BANAVALE ........................ 105 TABLE 8.2 : CONSOLIDATED ENVIRONMENTAL MANAGEMENT PLAN FOR SALINE EMBANKMENT-NARVEL- BANAVALE
................................................................................................................................................................................ 152 TABLE 8.3 : ENVIRONMENT MONITORING PLAN ............................................................................................................. 171 TABLE 8.4 : REPORTING SCHEDULE .................................................................................................................................. 179 TABLE 8.5 : ENVIRONMENT MANAGEMENT BUDGET ..................................................................................................... 184
List of Figures
FIGURE 1.1 : COASTAL AREA MAP OF STATES COVERED UNDER NCRMP ......................................................................... 21 FIGURE 1.2 : LOCATION MAP OF NARVEL BENAVALE EMBANKMENT SITE ....................................................................... 23 FIGURE 3.1 : CONNECTIVITY MAP OF NARVEL BENAVALE EMBANKMENT SITE ................................................................ 39 FIGURE 3.2 : PHOTOGRAPHS OF THE EXISTING EMBANKMENT ........................................................................................ 40 FIGURE 4.1 : LOCATION MAP AND SURROUNDINGS WITHIN 1 KM RADIUS ..................................................................... 51 FIGURE 4.2 : LOCATION MAP AND SURROUNDINGS WITHIN 10 KM RADIUS ................................................................... 52 FIGURE 4.3 : GRAPHICAL PRESENTATION OF THE LAND USE WITHIN 1 KM RADIUS OF THE NARVEL EMBANKMENT SITE
.................................................................................................................................................................................. 53 FIGURE 4.4 : LAND USE MAP.............................................................................................................................................. 54 FIGURE 4.5 : SEISMIC ZONES OF INDIA .............................................................................................................................. 56 FIGURE 8.1 : INSTITUTIONAL MECHANISM FOR EMP IMPLEMENTATION-CONSTRUCTION PHASE ................................ 174 FIGURE 8.2 GRIEVANCE READDRESS MECHANISM-CONSTRUCTION PHASE ................................................................... 183
List of Annexure
ANNEXURE 1.1: LIST OF EIA REPORT PREPARERS ............................................................................................................ 192 ANNEXURE 2.1: NATIONAL AMBIENT AIR QUALITY STANDARDS, 2009 .......................................................................... 193 ANNEXURE 2.2: NOISE STANDARDS, CPCB ...................................................................................................................... 194 ANNEXURE 2.3: OSHA’S NOISE EXPOSURE LIMITS FOR THE WORK ZONE ....................................................................... 195 ANNEXURE 2.4: DRINKING WATER QUALITY STANDARDS-IS: 10500:2012 ..................................................................... 196
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 5
ANNEXURE 3.1: DETAIL OF THE EXISTING EMBANKMENT .............................................................................................. 197 ANNEXURE 3.2: DETAIL OF THE LOCATION OF TREES AND FACILITIES LOCATED WITHIN THE PROPOSED ROW ........... 209 ANNEXURE 3.5: DETAILS OF PROPOSED EMBANKMENT ................................................................................................. 236 ANNEXURE 3.6: LOCATION FOR PROPOSED PROTECTION/GABION WALL ...................................................................... 257 ANNEXURE 3.7: CROSS SECTIONS OF CD WORKS ............................................................................................................ 260 ANNEXURE 4.1: STRIP MAPS OF THE DIRECT IMPACT ZONE ........................................................................................... 269 ANNEXURE 5.1: PERMISSION LETTER FROM MANGROVES CELL OF FOREST DEPARTMENT ........................................... 275 ANNEXURE 6.1 : HIGH COURT NOTIFICATION FOR MANGROVE PROTECTION ............................................................... 280 ANNEXURE 7.1: INVENTORY OF HOT SPOTS, CRITICAL AND SENSITIVE LOCATIONS ....................................................... 292 ANNEXURE 7.2 : FORMAT FOR CONDUCTING CENSUS.................................................................................................... 295 ANNEXURE 7.3: LIST OF PAP ............................................................................................................................................ 296 ANNEXURE 7.4: LIST OF PAPS (PEOPLE WHOSE STRUCTURES ARE GETTING AFFECTED ................................................. 373 ANNEXURE 8.2: FORMATS FOR AMBIENT AIR AND NOISE MONITORING ....................................................................... 386
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 6
ABBREVIATIONS
ABBREVIATION FULL FORM BOCWA Building and Other Construction Workers (regulation of employment
and conditions of services) Act, 1996 BOCWR Building & Other Construction Workers Rules
°C Degree celcius CD Works Cross Drainage Works
CGWB Central Ground Water Board Ch Chainage
CPCB Central Pollution Control Board CR Critically Endangered
CRZ Coastal Regulation Zone CTE Consent to Establish CTO Consent to Operate Cum Cubic meter dB Decibles
DDMO District Disaster Management Officer DEIAA District Environment Impact Assessment Authority
DG Diesel Generator Dist District DPR Detailed Project Report EA Environment Assessment EC Environment Clearance EE Executive Enghineer
EEC European Economic Community EHS Environment Health & Safety EIA Environment Impact Assessment
ELCB Earth Leakage Circuit Breakers EMP Environment Management Plan EN Endangered
EPA Environment (Protection) Act ESMF Environment Social Management Framework FGD Focus Group Discussions FRP Fibre-Reinforced Plastic GIS Geographic Information System GoI Government of India Govt Government GRM Grievance Redress Mechanism GTS Great Trignometrical Survey Ha Hectare
HCFL Highest Creek Flood Level HDPE High Density Poly Ethylene
HEC RAS Hydrologic Engineering Center- River Analysis System HFL Highest Flood Level HH Household HTL High Tide Line IFC International Finance Corpofration ILO International Labour Organization IMD Indian Meteorological Department INR Indian rupees IRC Indian Road Congress IS Indian Standards
IUCN International Union for Conservation of Nature
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 7
Kg Kilogram KLD Kilo liters Per Day
KLDC Kharland Development Corporation Km Kilometer
Kmph Kilometre per hour LED Light Emitting Diode MCM Million Cubic Meter
MCZMA Maharashtra Coastal Zone Management Authority Mm Milimeter
MoEF&CC Ministry of Environment, Forest and Climate Change MPCB Maharashtra Pollution Control Board
MSEDCL Maharashtra State Electricity Development Distribution Company Limited Board
MSK Scale Medvedev–Sponheuer–Karnik Scale NAAQS National Ambient Air Quality Standards
NBSS&LUP National Bureau of Soil Survey and Land Use Planning NCRMP National Coastal Risk Mitigation Project NDMA National Disaster Management Authority
NE North East NGOs Non-Governmental organizations NGT National Green Tribunal NOC No Objection Certificate NW North-west OP Operational Policy
OSHA’S Occupational Safety and Health Administration PM Particulate Matter
PMC Project Management Consultant PPEs Personal Protective Equipment PPGL Pre-painted galvalume steel, Pre-painted Hot-Dip Galvalume Steel
PRA/ RRA Participatory Rural Appraisal / Rrapid Rrural Aappraisal PUC Pollution Under Control Pvt Private
PWD Public Works Department R.C.C Reinforced Cement Concretre cement RDC Resident District Collector RET Rare/Endangered/Threatened RL Reduced Level
RMC Ready Mixed MixedConcreteement SC Schedule Caste
SCZMA State Coastal Zone Management Authority SE Saline Embankment SE South East
SEIAA State Environment Impact Assessment Authority SIA Social Impact Assessment
SMP Social Management Plan SPIU State Project Implementation Unit ST Schedule Tribe SW South West
TPQA Third Party Quality Assurance USEPA United States Environmental Protection Agency of United States
UTs Union Territories WB World Bank
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 8
EXECUTIVE SUMMARY
1.0 INTRODUCTION
The National Cyclone Risk Mitigation Project (NCRMP) is initiated by Ministry of Home
Affairs, Government of India with the purpose of creating suitable infrastructure to mitigate
the effects of cyclones in the coastal states of India in a sustainable way. The NCRMP is a
flagship program, World Bank exclusively focusing on ex-ante disaster risk mitigation in
cyclone prone coastal states and union territories. It is being implemented by the National
Disaster Management Authority (NDMA) with support from the Ministry of Home Affairs
Government of India, with financial aid from International Development Association – World
Bank.
The main objective of the NCRMP project are:
• minimize risk and vulnerabilities of coastal to cyclones
• to strengthen the structural and non-structural cyclone mitigation efforts through creation of appropriate infrastructure which can help to mitigate the adverse impacts of cyclones, while preserving the ecological balance of a coastal region and
• Strengthening of cyclone warning systems enabling quick and effective dissemination of warning and advisories from source/district/sub-district level to the relevant communities.
• to build capabilities and capacities of people for cyclone risk mitigation in harmony with the conservation of coastal ecosystems
The project has identified 13 cyclone prone States and Union Territories (UTs), with varying
levels of vulnerability. These States/UTs are divided into two following categories, based on
the frequency of occurrence of cyclones, size of population and the existing institutional
mechanism for disaster management.
i. Category I- Higher Vulnerability States: Andhra Pradesh, Gujarat, Orissa, and West
Bengal
ii. Category II-Lower Vulnerability States: Maharashtra, Goa, Karnataka, Kerala,
Daman & Diu, Pondicherry, Tamil Nadu, Lakshadweep and Andaman & Nicobar
Island
NCRMP Maharashtra Project Components:
The project components in Maharashtra includes conversion of overhead electrical cable
network to underground system in Alibag, Ratnagiri, and Satpathi town, multi-purpose
cyclone shelters and Renovation of select Saline embankments. This EIA reports relates to
“Renovation of Saline Embankment in Narvel & Benavale villages in Pen Taluka, Raigad
District. Separate EIA reports are prepared for other saline embankments.
An SPIU has been formed under the Relief and Rehabilitation Department, Government of
Maharashtra for implementing the NCRMP-II project in Maharashtra state which will
implement the project in coordination with various government agencies like Kharland
Development Circle(KLDC), Harbour Division of Public Works Department(PWD),
Maharashtra State Electricity Distribution Company Limited(MSEDCL), through State
Disaster Management Authority. Project for renovation of saline embankments will be
implemented by Kharland Development Circle.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 9
2.0 BRIEF DESCRIPTION OF THE PROJECT
Project Components
The proposed project is renovation of Narvel Benavale saline embankment scheme through
raising and strengthening under NCRMP-II project. Geographically, the proposed project
lies between latitudes of “18°46'41.50"N to 18°39'7.91"N”and longitudes from “73°2'12.85"E” to 73° 2'24.96"E. The embankment is situated near villages Bhal, Narvel & Benavale in
Taluka Pen, District Raigad. The embankment is located at a distance of 20 Kms from
Taluka place at Pen. Site is connected through Narvel Benavale, Washi-Vadhav, Vadhav-
Kaleshree rand other small roads to NH-66 (Alibag-Khopoli road). Map showing location on
Google map and connectivity of the site is given in Figure 1.
Figure 1. : Google Map for location and connectivity of the embankment site
Study area drains into the Bhogwati and Amba River/creek. Arabian sea is approx. 8 km
from the embankment in East direction. Maximum water level near the embankment is 3.88
m with respect to G.T.S. The topography of the study area is almost flat sloping towards
Arabian Sea. The general elevation of land at the proposed project area varies from 0 m to
2 m amsl and is thus prone to inundation during flood and cyclones. Thus, embankment is
essential to protect inland area from inundation.
Condition of Existing Embankment and its linked facilities
The existing embankment was constructed in 1952. At present it has become dialapidated
and under section in various sections. Total length of the embankment proposed is 16.44
km. Top level (RL) of existing bund varies from 1.69 m to 4.05 m. Available bottom width of
existing embankment varies between 0.0 m to 15.31 m. Top width of the existing bund
varies 0.88 m to 5.99 m. Facilities existing within the alignment includes 10 electric poles,
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 10
19 pukka house, 8 jetty, 24 fish ponds, 1 service line, 11 kachha house, 7 toilets, 5 toilets, 5
ottas, 3 sheds, 4 crematorium, 1 school, 2 temple, 1 well and 1 road.
The facilities mentioned above will either be completely or partially affected due to
embankment construction and budget is considered for either rehabilitation or
reconstruction of these facilities. As a measure to mitigate the impact on school and other
structures it is proposed to realign the existing embankment by straightening between
chainage 13230 to 13380. Structure falling between these chainages includes 3 houses, 1
jetty, 1 tree, 1 temple (Bahari) and 1 pond. These structures may also be saved along with
the school due to straightening of the embankment.
In addition to the above facilities, 42 nos. of trees exists on the embankment which will also
may get affected. Mangroves are also present in close vicinity to the embankment and they
are all along the embankment towards creek side whereas in patches towards land side.
NOC from Mangroves Cell of Forest Department is obtained for working in the area while
minimizing the impact on mangroves. Budget for relocation of facilities is considered under
the project cost.
Details of the Proposed Project
Under the project, existing embankment will be compacted, strengthened and height will
also be increased. Since the height of the embankment will increase, approach roads will
also be developed to connect the existing roads and the embankment. Facilities which will
be affected due to the project will also be shifted or reconstructed. Road which will be
affected at chainage 2910-2970 will be reconstructed. There are 7 existing CD works which
is in dilapidated condition and needs to be reconstructed. It is proposed to construct new
CD work. Ring bund will be provided at location of CD work during reconstruction to prevent
ingress of sea water. Total land requirement for the renovated embankment is 243960 sq. m
out of which 115958 sq. m is existing and additional 128002 sq. m of land is required1.
However, people have given their consent to KLDC to use their land for construction of
embankment.
The stone pitching is provided at Field Side up to H.F.L & at Creek Side up to Top of Bund
Level of the saline embankments. Beyond the stone pitching, turfing will be provided on land
side. The thickness of stone pitching is 20 cms. Pitching is provided from the ground level
right up to the top of embankment on creek side. Headers are provided for the pitching on
the creek side so as to sustain the wave action and tidal effects. 30 cm thick murum
bedding is provided below stone pitching for better strength and stability.
Highest tide levels published by the Maharashtra Maritime Board over a period of 25 years
up to the year 2014 are considered for design of the Saline Embankment. The design of the
Cross-Drainage works is adopted in the form of R.C.C Structures founded on Raft footings
& supported by counter-fort retaining walls on sides to save in the quantity of concrete as
per the finalized design. Salient features of the project are given in Table 1.
Table 1 : Salient features of the Existing Embankment project
S.No. Parameter Description Embankment
1. Type of embankment (Homogeneous / zoned/ rockfill): -
Zoned2
2. Length of embankment (m) : 16440
1 As per the PAP List Prepared by KLDC
2 Zoned embankments are the one which comprises of zones of selected materials having different degree of porosity, permeability and
density
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 11
3. Top width (m) :- 3.00 4. Top Bund level TBL (m) 5.18 5. Maximum Bottom Width (m) 23.76 6. Seismicity of the project area (IS:1893):
- Zone – IV
7. Slope of embankment. 1) U/S (Field side.) 2) D/S (Creek side.)
1.50 : 1 1.50 : 1
8. Sill level. 0.83 9. High tide level. 2.6 10. High flood level. 3.88 11. Free board. 1.5 m.
Sluice Gate/Ugadi 12. No. of C.D. Works. 8 13. Location. Of CD works Existing: Ch. 388m, 1786m, 2507m,
6732m, 7228m, 8787m & 9547m Proposed: 16405 m
14. Opening Rectangular 15. Catchment area. 20.37 Sq. Kms. 16. Flood discharge as per DICKNS
FORMULA 174.22 cum/sec
17. Area of water way provided. 149.89 Sqm. 18. Dimensions of opening (mm) Existing: 7 nos
Proposed: 1 additional Total: 7 reconstructed +1 new Existing
1) Ch.393m 3 x 1.50 x 2.43 2) Ch.1786m 3 x 1.50 x 2.43 3) Ch.2507m 3 x 1.50 x 2.43 4) Ch.6732m 3 x 1.50 x 2.43 5) Ch.7228m 3 x 1.50 x 2.43 6) Ch.8787m 3 x 1.50 x 2.43 7) Ch.9547m 3 x 1.50 x 2.43
Proposed 8) Ch.16405m 7 x 1.5 x 2.43
19. Types of Gates FRP / PPGL Gates, with horizontal hinges on top, acting one way restricting thereby saline water to enter in the benefited area.
3.0 NEED AND BENEFITS OF THE PROJECT
The coastal area of Raigad district is prone to frequent cyclonic storms and concurrent flood
hazards causing considerable loss of livelihood and livestock. Pen has experienced
devastating cyclones in the past including ARB02 in 1994 & Phyan in 2009, which has
caused substantial loss of life, and property in the area. Further the area also gets flooded
and the highest flood level were observed in 1979 and 2009 which is 3.31 m w.r.t GTS.
Hence, there is a need to protect disaster prone areas by renovating the existing
embankments which would certainly give security and safety to community living in the
area.
Considering the above, NCRMP-II includes the renovation of existing damaged
embankments in select vulnerable coastal areas. These embankments not only protect the
area from cyclones but also prevents ingress of sea water during high tide and cyclones to
the agriculture fields thus making the cultivation feasible in the area.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 12
Benefits of the proposed embankment are as follows:
• Proposed renovation of the embankment will secure life of 12544 people, 815 households and assets worth 1222.50 lacs
• The water ponds and ground water recharge will be free from salination making ground water potable. Villagers are dependent either on wells, bore wells, or local natural resources.
• The saline embankment will act as a barrier between the creek & the coastal lands, thereby protecting the coastal lands from getting washed away during floods & daily tidal fluctuations. During the construction earthen embankment provides opportunities to the poor people residing in villages as well as its maintenance work in the future.
4.0 NEED FOR ENVIRONMENTAL IMPACT ASSESSMENT STUDY
Most of the impacts due to the project are anticipated on the environmental and social
sensitive receptors located in the direct impact zone (Proposed RoW) of the project and spill
over effects may be felt in immediate surroundings (15 m on either side of the
embankment). In addition, majority of impacts are short-term, temporary and mitigable with
measures except tree cutting. Thus, the impacts of the project anticipated are for the limited
time over the limited area. Since the impacts of the project are short term, temporary and
spread over the direct impact zone majorly, a limited EIA study is undertaken for the project.
EIA study has focused mainly on the environmental and social sensitive receptors falling
within the direct impact zone. All the environmental and social sensitive features falling in
the direct impact zone are mapped and strip maps are prepared. Mitigation and
management plan are designed so as to minimize impact of renovation of the saline
embankment on these environment and social sensitive receptors. Alternative analysis
study is also carried out for location, design and with & without project scenario as per WB
guidelines. CRZ clearance for renovation of the 8 nos of the saline embankment including
Narvel has been exempted by MCZMA vide letter no CRZ2013/CR-77/TC-4 dated 6th
February, 2015.
5.0 APPLICABILITY OF LEGAL AND REGULATORY FRAMEWORK ON PROJECT
The project has been evaluated for applicability of all National and State Laws, Rules and
Regulations as well as Operational policies and guidelines of World Bank. The Acts, rules
and guidelines applicable for the project are critically analysed to list out the statutory and
regulatory requirements including permits/NOC to be obtained by KLDC/ SPIU during
Planning phase and by Contractor during implementation phase. The detailed requirements
under each rule/regulation are mentioned in main report. Some of the key important
legislations and requirements applicable for the project are listed below.
i. Environment Protection Act-1986
ii. The Forest (Conservation) Act, 1980 and amendment 1988 and Maharashtra Felling of Tree (Regulation) Act 1964 No forest land involved but Mangroves are declared as protected forests as per High Court Notification thus permission is required from mangrove cell of Forest Department which is also obtained. Also, there is requirement to cut 42 trees for strengthening of the embankment. There is no reserve trees listed under Maharashtra Tree Felling Act, 1964. Permission should be obtained from District collector for cutting other non-reserve trees as per NGT order dated 8th Jan 2016 – case no 11/2015 (WZ). Also, compensatory plantation should be carried out in ratio of 1:10 for every tree cut
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 13
iii. Coastal Zone Management Act 2011 as amended
MCZMA has already granted exemption for CRZ clearance for the Narvel Saline embankment.
iv. Air (Prevention and Control of Pollution) Act, 1981, 1987 Consent to Establish (before installing) and Operate (after installing) of construction
camp is required if any plants like RMC Plant/DG sets are installed for the project.
Activity falls under orange category as per CPCB classification for industries dated
March 07, 2016 directions)
v. Water (Prevention and Control of Pollution) Act, 1974, 1988
Consent to Establish (CTE) for installation and operate (CTO) after installation of
construction camp is required if any plants like RMC Plant/DG sets are installed for
the project.
vi. Noise Pollution (Regulation and Control Act) 2000 and amendment till date (Noise
Rules 2010)
No Permit required but need to comply with prescribed noise levels.
vii. Hazardous and other waste (Management and Transboundary Movement) Rules, 2016
Authorization is required to be obtained if there is generation and disposal of waste oil
during construction phase from concerned state pollution control board)
viii. Manufacture Storage, & Imports of Hazardous Chemicals (Amendment) Rules, 2000
Permit for storage of hazardous material if the quantity exceeds the threshold limits
defined in the Rules
ix. Construction and Demolition Waste Management Rules, 2016
Waste will be generated from dismantling of the CD works and stripping of the soil from
existing embankment & proposed alignment area, authorization for handling and
management is required, So permission from local bodies of the area for disposal in
landfill areas
x. Solid Waste Management Rules, 2016
Contractor should follow the rules for disposal of the waste to be generated from labour
hutments
xi. Central Motor Vehicle Act 1988 and amendment, Central Motor Vehicle Rules, 1989 and
amendments till date Applicable, The Maharashtra Motor Vehicle Rules 1989
Rule to be followed for all the vehicles at site during construction & operation phase.
PUC is required for all vehicles at site.
xii. Maharashtra Minor, Mineral Extraction (Development and Regulation) Rules 2013
Appropriate permissions will be required from DEIAA / SEIAAA if contractor undertake
extraction himself or use sources already approved by the authorities.
xiii. The Gas Cylinder Rules 2016
Applicable if contractor store more than the exempted quantity of gas cylinder. Gas
cylinders will be required for the welding activity. Permission required from Chief
Controller of explosives.
xiv. Ancient Monuments and Archaeological Sites and Remains Act, 1958
No archaeological site falls within 300 m of proposed embankment But permission or
NOC from ASI should be taken prior start construction work.
xv. Building and Other Construction Workers (Regulation Of Employment And Conditions
Of Service) Act, 1996
Mandatory for contractors to provide safety health and welfare measures for all
construction labour as per the Act and Rules
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 14
The details of administrative authority for each above applicable legislation is given in
chapter 2 of the EIA Report.
Assessment is made wrt to the applicability of the World Bank Operational Policies on
Project. It is found that OP 4.01, OP 4.04, and OP 4.36 are triggered for the project.
Environmental standards to be maintained during project implementation and operation
stage includes the following
1. National Ambient Air Quality Standards, 2009 2. Noise Standards, CPCB 3. OSHAS Noise Exposure Limits for the Work Zone 4. Drinking water Quality Standards-IS:10500:2012
6.0 ANALYSIS OF ALTERNATIVE
Analysis of alternatives is carried out for analytical comparison of the operational
effectiveness, costs and environmental and social risks of the proposed developmental
options. It has been carried out for following two aspects:
1. Location/Alignment, Planning and Design of the Embankment
2. “With” and “Without Project” scenario
Considering the alternatives has saved mangroves and various structures existing along the
alignment. KLDC has modified the design of the embankment to reduce the land
requirement also and minimize impact on the farmers giving the land. In one section, i.e.
chainage between 13230 and 13380 is straightened to save the school and other structures
on the land side. However, some of the structures exists on the embankment will be
impacted due to the project as they cannot be avoided. Facilities/utilities which will be
impacted includes 42 trees, 10 electricity poles, 16 pakka houses, 8 jetties, 24 fish ponds, 1
electricity service line, 11 kachha houses, 7 nos of toilets (community and private toilets), 5
solar lights, 5 fish drying platforms, 3 shed, 4 crematorium, 1 shed, 2 temples, 1 well and
road. Budget for shifting of utilities is considered under the EMP budget to minimize the
impacts. None of the tree to cut falls in Maharashtra Tree Felling Act, 1964. Permission for
tree cutting will be required from District Collector as per NGT Order dated 8th Jan 2016 –
case no 11/2015 (WZ).
As per the old DPR, land requirement on land side was huge which has been reduced to by
modifying the initially proposed design and reducing the bottom & top width requirement. In
the design top width is reduced from 4 m to 3 m w which has also reduced the bottom width
or land requirement. Total additional land required is 128002 sq m.
Analysis was also carried out for With and Without Project Scenario. Proposed project will
secure 12544 lives, 815 households and property of worth 1222.50 lakhs, and also will
increase agricultural land to 1388 ha from 1010 ha which may lead to improved socio-
economic conditions of the people living in these villages. Air, water and noise quality will be
affected during construction phase but it will be short term and impact will be minimized with
mitigation measures as detailed out in the environment management plan.
7.0 PROJECT IMPACT AREA
The entire study area is classified under two categories i.e. Direct Impact zone and Project
Influence area. Proposed RoW of the embankment is considered as the direct impact zone
as all the project activities will be restricted to the proposed RoW. However, spill over
effects of construction will also occur in immediate surroundings like blockage of access to
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 15
houses and agriculture field, impact on mangroves and vegetation along the embankment,
dust generation and high noise level. Strip mapping is thus done for the proposed RoW and
additional 15 m width on each side of the proposed alignment.
Impacts of project are disturbance in air quality, increase in noise levels, impact on access
to village and the agriculture fields, shifting of utilities and disturbance of aesthetics. These
types of impacts are not anticipated to be significant beyond 1 km area. Thus the project
influence area is considered as direct impact zone (proposed RoW) and area within 1 km
radius of the saline embankment. However, notified eco-sensitive zones are studied within
the 10 km radius are of the proposed alignment.
ENVIRONMENTAL SCREENING OF PROJECT AREA
Environmental sensitivities associated with the site are listed below
• Existence of Mangrove all along embankment which needs protection while carrying
out repair works of embankment
• Requirement of the additional land in addition to the land under existing
embankment (this additional land can be private land or Government land)
• Facilities/utilities which will be impacted includes 10 electricity poles, 16 pakka
houses, 8 jetties, 24 fish ponds, 1 electricity service line, 11 kachha houses, 7 nos of
toilets (community and private toilets), 5 solar lights, 5 fish drying platforms, 3 shed,
4 crematorium, 1 shed, 2 temples, 1 well and road. Compensation will be provided in
form of shifting/relocation/reconstruction etc as feasible
• Cutting of 42 nos of non-reserved trees on the embankment, requiring compensatory
plantation in the area
Benefited area and the embankment are not falling in any notified eco-sensitive zone or
forest areas. However, mangroves are present all along the embankment on the creek side
and mangroves are considered as protected forest as per High Court Notification dated
06.10.2005. In addition, no archaeological site is present within 300 m radius of the
proposed embankment. Mangroves exist all along the embankment towards the creek side,
hence, the existing toe line on the creek side avoiding mangroves has been considered as
the starting point of the proposed embankment. There are no other notified areas like
National Park, Elephant / Tiger Reserve, migratory routes of avifauna or terrestrial fauna
within 10 km radius of the site.
8.0 ENVIRONMENTAL IMPACT ASSESSMENT
The impacts anticipated vary from low to high significance but most of the impacts are
associated with construction phase and are of short term, site specific and temporary in
nature. Major impacts are anticipated due to tree cutting, working in close vicinity to
mangroves, shifting of utilities, need of private land for embankment renovation, aesthetics
and occupational health & safety of workers. The impacts envisaged are manageable and
mitigable, if the suggested mitigation measures and environment management plan are
implemented. No impacts are anticipated during the operation phase of the project.
9.0 PUBLIC CONSULTATION AND DISCLOSURE
Informal consultations were carried out with the project implementation agency, i.e.
Kharland Development Circle, SPIU, local people and other stakeholders like Gram
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 16
panchayat. A large-scale consultation was also carried out by Kharland Development Circle
with local people and Patwari to inform people about the project and to obtain their consent
for using their land for construction of embankment. People have agreed to give off their
land voluntarily for construction of embankment and have signed the consent letters.
Design of the embankment has been improved in terms of reducing the land requirement for
embankment. Bottom width is reduced to minimize the land requirement and height of the
embankment is also increased. Other things considered in design after the survey and
consultation are provision of stone pitching on the land side also and mangroves line should
be kept as the creek side boundary of the proposed embankment to minimize the impact on
mangroves. Public consultation and site surveys has helped significantly to improve the
project design and social acceptability of the project. Environment impact assessment report
will be disclosed at the SPIU (NCRMP) website. Executive summary will also be disclosed
in local language as well at SPIU and NCRMP website and made available to local people
at the KLDC office.
10.0 ENVIRONMENT MANAGEMENT PLAN AND BUDGET
The Environmental Management Plan (EMP) is a synthesis of all proposed mitigation and
monitoring actions, set to a time frame with a specific responsibility assigned and follow-up
actions defined. Prepared EMP is a plan of actions for avoidance, mitigation and
management of the negative impacts assessed due to project activities. A detailed set of
mitigation measures have been compiled in view of the likely impacts associated with the
proposed project. EMP provides a management schedule of time and sequence of
implementation of the proposed mitigation measures. It also includes plans for pollution
prevention, environmental guidelines & standards, emergency management plan,
institutional framework, grievance readdress mechanism, capacity building, environment
monitoring plan and environment management budget.
Institutional Framework for EMP Implementation
Environmental and social management plan will be implemented by EHS officer of the
Contractor under direct reporting to Executive Engineer of Kharland Development Circle.
EHS cell of SPIU will supervise the KLDC and the contractor for EMP / SMP
implementation. Third Party Quality Assurance (TPQA) agency will be assigned the task of
effective monitoring and advisory for implementation after appointment.
Environment Monitoring Plan
Key monitoring indicators are defined as the environmental parameters which may get
impacted during different project stages and environment monitoring plan is prepared for
these key indicators for e.g. air quality, creek water quality, drinking water quality, noise
level, occupational health & safety, community issues, solid waste disposal, sanitation,
construction waste, sanitation, labour camps and construction camp during construction
stage and community issues & compensatory plantation survival during operation phase of
the project
Environmental Management Budget
Budget for environmental management both during construction and operation phase is
estimated and provisions for the same are provided.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 17
11.0 GRIEVANCE READRESS MECHANISM
The Grievance Redress Mechanism (GRM) will have two tier structures. First tier will be at
Kharland Development Circle – at its Sub-division office and Divisional Office at Pen level
and second tier at SPIU level. The Executive Engineer of KLDC will be responsible to
address the concerns of the aggrieved person at first stage. Kharland Development Circle
will designate a dedicated email, phone number for receipt of grievances. A drop box will
also be installed at Kharland Office and at construction work site with lock and key. Drop
box shall be opened in presence of Contractor, KLDC and TPQA and the grievances will be
lodged in the grievance register and a specific number will be allotted to each grievance on
its receipt. The Sub-Division Engineer, Pen and Executive Engineer, Pen Division will
analyze the grievance received through interaction with contractor EHS officer and the
contractor will also visit the site to verify the complaint. District Collector or his deputed
representative shall be member of GRM Cell and any complaint / grievance is to be heard in
his presence who shall facilitate the redressal of such heard grievances, if any. The
response to the complaint with resolution will be communicated back to the aggrieved
person within 15 days. In case, grievance cannot be resolved at Kharland Department level,
then it will be escalated to SPIU level for further resolution. SPIU will put up this to
Grievance redress committee comprising District Collector or his deputed representative,
Sub Division Officer Kharland Pen, Executive Engineer Kharland Pen, Superintending
Engineer, Chief Engineer Water Resources Department, Representative of District
Administration and EHS Officer SPIU who will evolve the action plan to resolve the
complaint.
Grievance Readress Mechanism-Construction Phase
Grievance Readdress Committee (Sub Division Officer and Executive engineer Kharland Pen, Superintending engineer, Chief Engineer Water Resources Department, EHS Officer SPIU and District Collector/Representative
Kharland Pen Office or Construction Camp Site
Aggrieved Person
Written Response within 15 days
Mode of communication: Letter
and Drop box Joint Site Visit With Contractor and TPQA
Action Plan Implementation By
Contractor
Action Plan Supervision and
Reporting by SPIU with support of PMC
Closure Update
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 18
12.0 TRAINING AND CAPACITY BUILDING
The staff and workers at the site shall be given environmental trainings to enhance their
understanding of EMP requirements and ensure effective implementation of EMP. In case
change in any labour or other staff who will be engaged on the construction site also need
to be oriented about the project and EMP requirement. Both Contractor /Kharland
Department shall organize such training for staff & workers. These trainings shall be
organized by contractor through TPQA shall organizing the trainings.
• Training for usage of personal protective equipment
• Training for usage of fire-fighting equipment
• First aid training including protection from Snake bites
• Training for implementation of EMP
• Training for protection of working near water body
13.0 Reporting
Following reporting schedule is recommended.
• The contractor shall submit the monthly EMP compliance report including various
aspects such as material sourcing, waste disposal, compliance to statutory
conditions, incident and accident public grievances, work progress, to Executive
Engines Kharland Department, and Kharland shall forward the reports to SPIU and
SPIU with the support of PMC/TPQA shall review the reports
• TPQA shall undertake periodical Audits and provide orientation including status of
EMP and SMP implementation and submit periodical reports to SPIU and PMC shall
verity its reports and submit a quarterly report to SPIU on EMP compliance status.
• SPIU environment and social expert supported by PMC/TPQA will submit progress
reports to SPIU Project Director, PIU and World Bank. Reporting frequencies shall
be as per ESMF.
14.0 Documentation, Updation and Record Keeping
The following reference documents shall be maintained and available with contractor and
SPIU for implementation at construction site
1. Environmental Management Plan (EMP), Environment and Social Management
Framework (ESMF)
2. Environmental Standards
3. SoPs (Standard Operating Procedures) and Method Statements for each project
activity (to be prepared by contractor and submitted to Kharland Department)
The EMP should be updated regularly based on change in regulatory requirements, WB
/IFC EHS guideline and finding of annual independent audit findings.
The following records shall be maintained at the site
1. Records on health check-ups
2. Records of accidents
3. Records of entry/exit of the vehicle at the site and material transportation by each
vehicle
4. Record of debris disposal with date, quantity and location
5. Records of training & mock drills
6. Records of equipment and vehicle inspection and maintenance
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 19
7. Records of number of PPE and rejection of PPE
8. Records of grievances (received & closed)
9. Environmental monitoring reports
15.0 Mechanism for Feedback And Adjustments
As part of the feedback mechanism, Kharland Department, Pen Division and TPQA shall
monitor project compliance based on monitoring reports, audit and inspection reports with
respect EMP, EMoP and applicable laws, rules and regulations. Kharland Department will
report to SPIU/PMC on a quarterly basis. In case, any deviation from the contract
requirements with respect to proposed EMP is observed, the same shall be corrected within
a fortnight through contractor and TPQA and records maintained for the same. Kharland
Department will also verify the facts reports through periodic site visits. If required
SPIU/PMC shall verify the facts through site verification.
Public involvement shall be encouraged and ensured throughout the lifecycle of the project.
The Kharland Development Circle, Pen Division shall gather and maintain information on
any damage or public concern that may be raised by the local people, NGOs and local
authorities. While immediate solutions are to be worked out with the help of contractor, a
detailed report will be submitted to the SPIU for information or detailed consideration. The
KLDC, Pen Division and TPQA shall be responsible to bring it to the notice of the
SPIU/PMC. Resulting decisions shall be communicated back to KLDC and TPQA and
contractor for correction and future implementation.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 20
CHAPTER 1. INTRODUCTION AND PROJECT BACKGROUND
1.1. Project Background
The National Cyclone Risk Mitigation Project (NCRMP) is initiated by Ministry of Home
Affairs, Government of India with the purpose of creating suitable infrastructure to mitigate
the effects of cyclones in the coastal states of India in a sustainable way. The NCRMP is a
flagship program, World Bank exclusively focusing on ex-ante disaster risk mitigation in
cyclone prone coastal states and union territories. It is being implemented by the National
Disaster Management Authority (NDMA) with support from the Ministry of Home Affairs
Government of India, with financial aid from International Development Association – World
Bank.
Project Objectives and States Covered under NCRMP: Main objectives of the NCRMP
project are:
• minimize risk and vulnerabilities of coasts to cyclones
• to strengthen the structural and non-structural cyclone mitigation efforts through
creation of appropriate infrastructure which can help to mitigate the adverse impacts
of cyclones, while preserving the ecological balance of a coastal region and
strengthening of cyclone warning systems enabling quick and effective
dissemination of warning and advisories from source/district/sub-district level to the
relevant communities.
• to build capabilities and capacities of people for cyclone risk mitigation in harmony
with the conservation of coastal ecosystems
The project has identified 13 cyclone prone States and Union Territories (‘UTs’), with varying levels of vulnerability. These States/UTs are divided into two following categories,
based on the frequency of occurrence of cyclones, size of population and the existing
institutional mechanism for disaster management.
iii. Category I- Higher Vulnerability States: Andhra Pradesh, Gujarat, Orissa, and West
Bengal
iv. Category II-Lower Vulnerability States: Maharashtra, Goa, Karnataka, Kerala,
Daman & Diu, Pondicherry, Tamil Nadu, Lakshadweep and Andaman & Nicobar
Island
NCRMP project is being implemented in Phases. The Costal states with phase bifurcation
are shown at Figure 1.1.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 21
Figure 1.1 : Coastal Area Map of States Covered Under NCRMP
NCRMP Project Components: NCRMP has the following four major components:
• Early Warning Dissemination Systems
• Cyclone Risk Mitigation Infrastructure
• Technical Assistance for Multi-Hazard Risk Management
• Project Management and Implementation Support
Project Components in Maharashtra: The project components in Maharashtra includes
conversion of overhead electrical cable network to underground system in Alibag, Ratnagiri,
and Satpati towns, construction of few Multi-Purpose Cyclone Shelters and renovation of
select existing saline embankments. This EIA reports relates to “Renovation of Narvel
Benavale Saline Embankment located in Pen Tehsil of Raigad District. Separate EIA reports
are prepared for other saline embankments.
An SPIU has been formed under the Relief and Rehabilitation Department, Government of
Maharashtra for implementing the NCRMP- II project in Maharashtra state which will
implement the project in coordination with various government agencies like MSEDCL,
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 22
Harbour Division of PWD, Kharland Development Circle (KLDC), through State Disaster
Management Authority.
1.2. Project Overview
The Narvel Benavale Kharland (embankment) Scheme measures about 16.44 km and
protects village Kaleshrivadi, Tukaramwadi, Mothe Bhal, Vitthalwadi, Lakhola, Borze,
Narvel, Benavale, Sarebhag and Vashi with total benefited area of 1388 ha. The
embankment is situated near villages Bhal, Narvel & Benavale in Taluka Pen, District
Raigad. The Kharland Development Board constructed Narvel Benavale Kharland Scheme
in 1952 to protect the settlements and agriculture fields of above-mentioned villages.
Embankment abuts Bhogwati and Amba River/creek. The Scheme is located at a distance
of 20 Kms from Taluka Place at Pen. Site is connected through Narvel Benavale, Washi-
Vadhav, Vadhav-Kaleshree rand other small roads to NH-66 (Alibag-Khopoli road). At
present embankment is in dilapidated or became under section largely due to continuous
erosive action of tides, meandering action of the creek and heavy rainfall. Further workers
and animals have been using the earthen embankment as a road, which has aggravated
the damage of the embankment.
This kharland scheme is selected under the NCRMP-II project for Renovation. Kharland
Development Circle has obtained the clearance from Coastal Zone Management Authority
for repair and strengthening of embankment for its Renovation. There are no notified eco-
sensitive zones within 10 km radius of the embankment. No reserve forest area is present
within 1 km radius of the embankment. In addition, no archaeological site is present within
300 m radius of the proposed embankment. Mangroves exist all along the embankment
towards the creek side and on land side in some patches. Mangroves are classified as
protect forest areas as per High Court Order of 2005. Mangroves exist all along the
embankment on the creek side hence, the existing toe line on the creek side avoiding
mangroves has been considered as the starting point of the proposed embankment. Map
showing location of the embankment site is shown at Figure 1.2.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 23
Figure 1.2 : Location Map of Narvel Benavale Embankment Site
1.3. Need of the Sub-Project
Maharashtra has a coastal belt of over 720 km between Gujarat to Goa. Raigad is coastal
district of Maharashtra. The coastal area of Raigad district is prone to frequent cyclonic
storms and concurrent flood hazards causing considerable loss of livelihood and livestock.
Pen has experienced devastating cyclones in the past including ARB02 in 1994 & Phyan in
2009, which has caused substantial loss of life, and property in the area. Further the area
also gets flooded and the highest flood level were observed in 1979 and 2009 which is 3.31
m w.r.t GTS. Hence, there is a need to protect disaster prone areas by renovating the
existing embankments, which would certainly give security and safety to coastal locality.
Considering the above, NCRMP-II includes the renovation of existing damaged
embankments in select vulnerable coastal areas. These embankments not only protect the
area from cyclones but also prevents ingress of sea water during high tide and cyclones to
the agriculture fields thus making the cultivation feasible in the area.
1.4. Benefits of the Project
Embankments are very useful as they help in protecting the area from the surge water
entering the area due to high tides. Embankments can improve soil fertility by controlling
saline water ingress; protect sources of drinking water & irrigation sources from salination;
reduce acute scarcity of water resources; improve crop productivity; increases fishing
opportunities there by increasing economic benefits and overall fishermen development;
enhances biodiversity by protecting flora and fauna of the area; land use improvement by
bringing large area which is presently wastelands under productive use; increases
availability of fodder & fuel; safeguards different and valuable assets of vulnerable people
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 24
from cyclone; and increases economic security & reduces migration. Specific benefits of the
proposed embankment are as follows:
Table 1.1 : Benefits of Proposed Embankment
1. Area of land to be saved from saline water ingress
There will be an improvement in the microclimate and soil productivity and thus, agriculture production can also be enhanced significantly, with the available livestock. Agricultural fields will be protected from saline water inundation and the sustainable agricultural production could be ensured. The project envisages protection of 1388 Ha. This component will help in stopping of the salinity ingress in the agricultural lands, improving sweet water recharge in the agricultural lands and controlling run off water.
2. Saving life and assets of people
Embankment will save life of 12544 people, 815 households and assets worth 1222.50 lacs). Also, embankment can be used as approach road for rescuing the life of people during cyclone and will also help to maintain supply continuity during emergency
3. Area of land irrigated with construction of canals / creek irrigation.
The water ponds and ground water recharge will be free from salination making ground water potable.
4. Availability of potable drinking water
The water ponds and ground water recharge will be free from salination making ground water potable. Water for drinking is one very critical problem. Villagers are dependent either on wells, bore wells, or local natural resources. The cost of fetching water from outside to the villagers is 36 lacs for six month.
5. To protect areas from erosion of soil.
The saline embankment will act as a barrier between the creek & the coastal lands, thereby protecting the coastal lands from getting washed away during floods & daily tidal fluctuations.
6. Employment opportunities during construction
During the construction earthen embankment provides opportunities to the poor people residing in villages as well as its maintenance work in future.
7. Reduction in migration of people
Due to shortage of the natural resources & opportunities for development, people migrate towards the urban areas, like Mumbai, Thane, Pune and Kolhapur. By renovation of existing saline embankment there will be an improvement in the microclimate and soil productivity and thus, agriculture production will also be enhanced significantly. Agricultural fields will be protected from saline water inundation and the sustainable agricultural production could be ensured. The project envisages protection of 1388 Ha. of kharland from saline water, thereby making the coastal farmers fetch agricultural income to the tune of Rs. 565.27 Lacs in the next 20 Year’s Span of the embankment.
1.5. Need of Environment Impact Assessment Study
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 25
Screening exercise has been undertaken for the project, and screening exercise indicated
the limited impacts of the project. Most of the impacts are anticipated on the environmental
and social sensitive receptors located within the proposed RoW and spill over effect will also
be observed in immediate surrounding areas. In addition, majority of impacts are short-term,
temporary and mitigable with measures except tree cutting. Thus, the impacts of the project
anticipated are for the limited time over the limited area. As per the section 6.4 and item nos
of the ESMF Volume I, “A detailed or limited environmental impact assessment study
(as the case may be depending on findings from the screening exercise) will be
undertaken for investments pertaining to saline embankment/bund strengthening
works and underground electric cabling (or in exceptional cases for roads with major
re-alignments). These sub-projects will undergo an analysis of alternatives,
especially in terms of their proposed location and/or design as required under
standard EA practice. For sub-projects requiring regulatory clearances (including the
Coastal Regulation Zone (CRZ) clearance), alternative site/s will be explored, and for
those with no viable alternatives, permissions will be sought in line with regulatory
requirements”
Since the impacts of the project are short term, temporary and spread over the direct impact
zone (proposed RoW) majorly and spill over effects may be felt in immediate surroundings
(15 m on either side of the embankment), a limited EIA study is undertaken for the project.
The EIA study has focused mainly on the environmental and social sensitive receptors
falling within the direct impact zone. All the environmental and social sensitive features
falling in the direct impact zone are mapped and strip maps are prepared. Mitigation and
management plan are designed so as to minimize impact of renovation of the saline
embankment on these environment and social sensitive receptors. Alternative analysis
study is also carried out for location, design and with & without project scenario as per WB
guidelines. CRZ clearance for renovation of the 8 nos of the saline embankment including
Narvel Benavale has been exempted by MCZMA vide letter no CRZ2013/CR-77/TC-4 dated
6th February, 2015 (Annexure 8.1).
1.6. Objective of EIA study
The EIA study is aimed to achieve the following:
• To conduct environmental impact assessment study for each saline embankment
site by establishing the environmental baseline in the study area through primary
and secondary data collection, Identification of impacts associated with project
activities during pre-construction, construction and operation stages of project and
Preparation of appropriate impact mitigation measures for identified impacts.
• Preparation of environment management and monitoring plan along with
environmental budget, institutional arrangement and grievance readdress
mechanism.
• Measures to address identified environmental issues through appropriate planning
and design interventions as feasible and integration of EHS requirements into the
bidding documents
1.7. Scope of the EIA Study
As per the terms of references of the project issued by SPIU, Relief and Renovation Department, Government of Maharashtra, scope of this study is to update the existing EIA
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 26
report of the Narvel Benavale Embankment. Tasks undertaken for updation of the EIA report includes the following
• Review of existing EIA study, old DPR reports
• Suggestions on the basis of the study of existing EIA study and DPRs for improvising of the DPRs
• Preparation of inception and screening report
• Site survey and identification of all the environment and social assets falling within the proposed alignment/RoW
• Analysis and tabulation of the collected data
• Preparation of strip maps on the GIS platform using the data collected from the site
• Collection of the baseline data through the site survey and authentic secondary sources
• Impact identification, assessment and evaluation
• Designing the mitigation measures
• Preparation of environment management plan
• Updation of the environment impact assessment report
1.8. Approach and Methodology
NCRMP II, appointed M/s EQMS India Pvt. Ltd., for undertaking the study for updating the EIA reports the Renovation of the existing saline embankment-Narvel Benavale located in Pen Taluka of Ragiad District. The study was undertaken under Mr S K Jain (Environment Specialist) and Mr T G Ekande (Social Specialist) supported by other team members, following preparation of inception report, screening report and joint visits to the site along with DPR consultants and field surveys (Refer Annexure 1.1). This EIA study is undertaken in line with the requirements defined under ESMF, Operational Policies of World Bank, EHS Guidelines for General Industry by IFC. Methodology followed includes the following actions:
• Interaction with the client and collection of all project related studies and documents
• Review of the project alignment, old DPRs, Existing EIA study of the embankments
and ESMF of the project to understand the project
• Reconnaissance site visits to understand the project site, analyse the environmental
settings of the project area, identify the pollution sources in the area, know about the
perception & knowledge of people about the project and identification of the
stakeholders of the project
• Suggestions for improvising the DPRs on basis of the findings during the visit &
review of the documents
• Defining the study area for EIA study which is defined as corridor of impact
(proposed RoW/alignment) and project influence area (1 km radius area). Study is
extended to 10 km of project alignment for identification of notified protected areas
e.g. National parks, or wild life sanctuaries.
• Preparation of inception report and environmental screening report
• Site visits for collection of environmental and social parameters to be affected due to
the project development. Since this project is linear in nature and has site specific
impacts, the mapping of environmental and social features along the alignment has
larger importance for impact assessment and decision making, therefore larger
emphasis was given to collection of environmental and social features and strip
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 27
mapping of the environmental & social sensitive receptors. For other parameters,
secondary data has been used while providing the references.
• Consultation with the public during the study. Inputs obtained during the
consultations and considering the inputs provided for designing the EMP
• Formal and informal consultation was held during the study and stakeholders ‘input
was considered for defining the mitigation measures.
• Based on the understanding of the project & associated activities and the data
collected during baseline study, impacts of the project on environment was
identified, assessed and evaluated and accordingly appropriate cost-effective
mitigation measures are proposed
• Analysis of alternative to assess the ‘with’ and; without’ project scenario and identify
best feasible option for alignment route
• Preparation of environment management plan including the pollution prevention
plan, environment monitoring plan, capacity building, audits, reporting,
documentation, institutional framework, grievance readdress mechanism and
environment management budget
1.9. Limitation of EIA Study
The Environmental Assessment is carried out in tandem with the preparation of detailed project report. Strip mapping is carried out on the basis of the current situation and proposed alignment but if there is any change in the alignment in later stage/at the time of implementation, sensitivity analysis of that particular stretch would need to be undertaken prior implementation of project in that stage.
1.10. Structure of the EIA Report
The EIA report is presented in 8 chapters following this introduction chapter.
Chapter 1: Introduction: This chapter describes project background, need of the project,
objective and background including the need of the project.
Chapter 2: Policy, Legal and Administrative Framework: This chapter deals with the
identification & listing of applicable legislations and applicable administrative framework. It
also provides screening of applicable operational policies of World Bank and other
international practices and guidelines.
Chapter 3: Description of Project and Analysis of Alternatives: This chapter describes
the various project components incorporated in the overall project framework.
Chapter 4: Description of Environment (Environmental profile and baseline of the
project and study area): This provides background information based on primary and
secondary information for physical, biological, social and cultural resources of project and
study areas.
Chapter 5: Anticipated Environmental Impacts and Mitigation Measures: Here This
chapters provides details of identified impacts and suggested mitigation measures to
eliminate or minimise the identified impacts for preconstruction, construction and operation
stages of the project.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 28
Chapter 6: Analysis of Alternatives: It also provides details the alternatives analyses for
with and without project scenarios.
Chapter 7: Public Consultation and Disclosure: The report provides details on the
stakeholder consultations carried out for the project, outcomes and methodology followed
for conducting stakeholder consultation
Chapter 8: Environmental Management Plan and Grievances Redress Mechanism:
This chapter provide the details on the management plans, along with institutional
mechanism, capacity building requirements and resources required for effective
implementation of the proposed mitigation measures and the monitoring framework
essential during construction as well as operation stages of the project.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 29
CHAPTER 2. REGULATORY CLEARANCES/PERMISSION REQUIREMENT
2.1. Introduction
India has well defined institutional and legislative framework. The legislation covers all
components of environment viz. air, water, soil, terrestrial and aquatic flora and fauna,
natural resources, and sensitive habitats. India is also signatory to various international
conventions and protocols. The environmental legislations in India are framed to protect the
valued environmental components and comply with its commitment to international
community under various conventions and protocols. World Bank has also defined its
Environmental and Social Safeguard Operational Policies. This assessment is about the
applicability of above laws and regulations, conventions, protocols, and safeguard policies
to the proposed project.
2.1.1 Overview of Indian Environmental Legislation and Administrative Framework
The Government of India has framed various laws and regulations for protection and
conservation of natural environment. The legislations are broadly divided under following
categories.
• Environmental Protection
• Forests Conservation
• Wildlife Protection
There are no notified wildlife sanctuaries or national parks within 10 Km radius of the project
area. The highlights of umbrella legislations for Environment Protection and Forests
Conservation are given below:
The Environment (Protection) Act, 1986 was enacted with the objective of providing for
the protection and improvement of the environment. It empowers the Central Government to
establish authorities charged with the mandate of preventing environmental pollution in all
its forms and to tackle specific environmental problems that are peculiar to different parts of
the country. Various rules are framed under this Act for grant of environmental clearance for
any developmental project, resources conservation and waste management.
The Forest (Conservation) Act, 1980, amended 1988 was enacted to help conserve the
country's forests. It strictly restricts and regulates the de-reservation of forests or use of
forest land for non-forest purposes without the prior approval of Central Government. To this
end the act lays down the pre-requisites for the diversion of forest land for non-forest
purposes.
The Ministry of Environment, Forests & Climate Change (MOEF&CC) and Central Pollution
Control Board (CPCB) at Central levels and Maharashtra State Pollution Control Board at
state level are responsible for grant of environmental clearances/ consents/permits and
ensuring compliances to various environmental laws and regulations. MOEF&CC at
National Level, State Forests Departments at State level are responsible for matters related
to Forests. Maharashtra Coastal Zone Management Authority is responsible for matter
related to coastal zone for this project.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 30
2.1.2 Applicable Environmental Legislation
As per the nature of the project, screening has been done to identify the legislations
applicable to the project. The summary of applicable legislation for the proposed project are
summarised at Table 2.1.
2.1.1 Operational Policies of World Bank
The project is being developed with the financial aid from World Bank. World Bank has its
operational policies, which safeguards the different environment and social components.
World Bank operational policies triggered for this project are summarised at Table 2.2.
Table 2.1 : Summary of Environmental and Other Legislation with Applicability Screening
S. No.
Legislation
Purpose Applicability
Reason Type of permit and
stage of applicabilit
y
Administrative
Authority
Responsibilit
y-Procuri
ng & Followi
ng
Responsibili
ty-Supervision
Applicable Legislations 1. Environ
ment Protection Act/Rules-1986
To protect and improve overall environment
Yes Project have potential to generate the pollutants and pollute the environment
No specific permission is required under this
law. However, follow the applicable guidelines
as applicable
under different
rules prescribed under this
law.
MoEF&CC Contractor
Kharland
Developmen
t Circle (KLDC
) & SPIU
2. The Forest (Conservation) Act, 1980 and amendments The Forest (conservation) Rules 1981 and amendments
To help conserve the country's forests. It strictly restricts and regulates the de-reservation of forests or use of forest land for non-forest purposes without the prior approval of the Government. To this end the Act lays down the pre-requisites for the diversion of forest land for
Yes No forest land involved but mangroves lies in close vicinity to the embankment and Mangroves are declared as protected forests as per High Court Notification thus permission is required from mangrove
Permission for working in close vicinity to mangroves Permission for tree cutting
State Forest
Department
Contractor &
Kharland
Development Circle
(KLDC)
SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 31
S. No.
Legislation
Purpose Applicability
Reason Type of permit and
stage of applicabilit
y
Administrative
Authority
Responsibilit
y-Procuri
ng & Followi
ng
Responsibili
ty-Supervision
till date Maharashtra Felling of Tree (Regulation) Act 1964
non-forest purposes
cell of Forest Department Also, there is requirement to cut 42 trees for strengthening of embankment. Permission should be obtained from District collector for cutting these trees as per NGT order dated 8th Jan 2016 – case no 11/2015 (WZ). Also, compensatory plantation should be carried out in ratio of 1:10 for every tree cut
3. Coastal Regulation Zone (CRZ) notification 2011 and amendment till date
To regulate development activities within the 500 m of high tide line in coastal zone and 100 m3 of tidal influence rivers.
Yes Project falls in the CRZ area
CRZ Clearance
(MCZMA has already granted exemption for CRZ clearance which is attached as Annexure 8.1).
MCZ MA, Kharland
Development Circle
(KLDC)
SPIU
4. Air (Prevention and Control of
An act to prevent and control Air pollution
Yes Involves air pollution generation and management
Consent to Establish (before installing) and
MPCB Contractor
Kharland
Developmen
t
3 This distance is reduced to 50 m as per CRZ Notification dated 18.01.2019 but this is subject to revision & final approval of CZMPs,
CZMA has submitted the MCZMP for reviision
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 32
S. No.
Legislation
Purpose Applicability
Reason Type of permit and
stage of applicabilit
y
Administrative
Authority
Responsibilit
y-Procuri
ng & Followi
ng
Responsibili
ty-Supervision
Pollution) Act, 1981, 1987
for installation and operation of construction camp involving RMC and DG Set
Operate (after installing) of construction camp involving RMC Plant/DG sets. Activity falls under orange category as per CPCB classification for industries dated March 07, 2016 directions)
Circle (KLDC
) & SPIU
5. Water Prevention and Control of Pollution) Act, 1974, 1988
An act to prevent and control water pollution.
Yes Domestic sewage may generate from labour camps and also run-off from construction camp which may pollute the surface water bodies
Consent to Establish for installation and operate after installation of construction and labour camps involving RMC Plant/DG sets) as applicable
MPCB Contractor
Kharland
Developmen
t Circle (KLDC
) & SPIU
6. Noise Pollution (Regulation and Control Act) 2000 and amendm
Ambient Noise Standards for different areas and zones
Yes Construction activities & vehicle may generate high noise levels than the prescribed levels under
No Permit required but need to comply with prescribed noise levels.
CPCB & MPCB
Contractor
Kharland
Developmen
t Circle (KLDC
) & SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 33
S. No.
Legislation
Purpose Applicability
Reason Type of permit and
stage of applicabilit
y
Administrative
Authority
Responsibilit
y-Procuri
ng & Followi
ng
Responsibili
ty-Supervision
ent till date
Noise Rules, 2010
7. Hazardous & Other Waste (Management and Transboundary Movement) Rules, 2016 as amended
Protection to general public against improper handling storage and disposal of hazardous waste. The rules prescribe the management requirement of hazardous wastes from its generation to final disposal.
Yes Used oil/lubricants from DG sets & machinery.
Authorization is required to be obtained for generation and disposal of waste oil during construction phase from concerned state pollution control board)
MPCB Contractor
Kharland
Developmen
t Circle (KLDC
) & SPIU
8. Manufacture Storage, & Imports of Hazardous Chemicals (Amendment) Rules, 2000
Usage and storage of hazardous substances
Yes Construction work may require storage of the hazardous substance or explosives like fuel
Permit for storage of hazardous material if the quantity exceeds the threshold limits defined in the Rules
Chief Controller
of Explosives
Contractor
Kharland
Developmen
t Circle (KLDC
) & SPIU
9. Construction and Demolition Waste Management Rules, 2016
To manage the demolition and construction waste and prevent environmental degradation
Yes Waste will be generated from dismantling of the CD works and stripping of the soil from existing embankment & proposed alignment area
Authorization
Permission from local
bodies of the area
for disposal in
landfill areas
Contractor
Kharland
Developmen
t Circle (KLDC
) & SPIU
10. Solid To manage solid Yes There could No specific Local Contrac Kharla
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 34
S. No.
Legislation
Purpose Applicability
Reason Type of permit and
stage of applicabilit
y
Administrative
Authority
Responsibilit
y-Procuri
ng & Followi
ng
Responsibili
ty-Supervision
Waste Management Rules, 2016
waste or semi-solid domestic waste, sanitary waste,
be generation of waste from labour camps and construction camps
permit is required. Just comply with the handling and disposal requirements of the rules
bodies of the area
tor nd Developmen
t Circle (KLDC
) & SPIU
11. Motor Vehicle Act 1988 and amendment till date Central and Motor Vehicle Rules, 1989 and amendments till date and The Maharashtra Motor Vehicle Rules 1989
To minimize the road accidents, penalizing the guilty, provision of compensation to victim and family and check vehicular air and noise pollution.
Yes Applicable, for all the vehicles at site during construction & operation phase
PUC Certificates, Use of licenced drivers, and vehicle insurances and permits
Motor Vehicle
Department
(Licensing authority, registration authority
&State Transport Authorities
)
Contractor
Kharland
Developmen
t Circle (KLDC
) & SPIU
12. The Gas Cylinder Rules 2016
To regulate the storage of gas / possession of gas cylinder more than the exempted quantity. (As per this rule, the emption quantity very depending on
Yes Applicable if contractor store more than the exempted quantity of gas cylinder. Criteria for exempt category is different for
License to store gas cylinder more than the regulated quantity
Chief Controller
of explosives
Contractor
Kharland
Developmen
t Circle (KLDC
) & SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 35
S. No.
Legislation
Purpose Applicability
Reason Type of permit and
stage of applicabilit
y
Administrative
Authority
Responsibilit
y-Procuri
ng & Followi
ng
Responsibili
ty-Supervision
nature of gas) different category4 of gases
13. Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996
To regulate the employment and conditions of service of buildings and other construction workers and to provide for their safety, health and welfare measures and for other matters connected therewith or incidental thereto.
Yes As the project involve construction activities and handling of heavy machinery
No permit is required-Construction Phase, Mandatory for contractors to provide Safety Health and Welfare measures for workers
Labour Commissi
oner
Contractor
Kharland Development Circle (KLDC) & SPIU
14.
Maharashtra minor, Mineral Extraction (Development and Regulation) Rules 2013
Control of extraction, collection and removal of minor minerals
Yes
Project need minor minerals (like sand, aggregate, murram, etc)
Appropriate permissions will be required if contract undertake extraction himself or use sources already approved
Mines Department/ DEIAA/SEIAA
Contractor
Kharland Development Circle (KLDC) & SPIU
15.
Other applicable Social Laws
Contractor to Comply with the provisions of these laws as applicable.
• The Child Labour (Prohibition and Regulation) Act, 1986
• The Bonded Labour System (Abolition) Act 1976
• Minimum Wages Act, 1948
• The Payment of Wages Act, 1936, amended in 2005
• Equal Remuneration Act, 1976
• Workmen's Compensation Act, 1923
• Maternity Benefit Act, 1961
• Inter-State Migrant Workmen’s (Regulation of Employment
Contractor
KHARLAND DEVELOPMENT CIRCLE (KLDC)& SPIU
4 LPG : <100kg at a time, Flamable but non toxic: <200 kg at a time, Non flammable- Non Toxic : <200 kg at a time, Any toxic Gas :< 5 cylinders at a time, Acetylene Gas contained in cylinders in dissolved state: , 25 at a time.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 36
S. No.
Legislation
Purpose Applicability
Reason Type of permit and
stage of applicabilit
y
Administrative
Authority
Responsibilit
y-Procuri
ng & Followi
ng
Responsibili
ty-Supervision
& Condition of Service) Act, 1979
• Petroleum Rules, 2002
• The Employees Provident Fund and Miscellaneous Provisions Act, 1952
• Payment of Bonus Act, 1965 and Amendment Act No.43 of 1977 and No.48 of 1978 and amendments
• Payment of Gratuity Act, 1972
• Public Provident Fund Act, 1968
• Employee State Insurance Act, 1948
• The Contract Labour (Regulation & Abolition) Act, 1970 and Rules
• Employer's Liability Act, 1938 (as amended)
• Labour (Regulation and Abolition) Act 1970
• Sexual Harassment of Women at the Workplace (Prevention, Prohibition and Redressal) Act 2013
• The Personal Injuries (Compensation Insurance) Act, 1963 (as amended)
• The Electricity Act 2003. Legislations Not Applicable to Project
• The Batteries (Management and Handling) Rules 2001
• Plastic waste management Rules, 2016/
• Maharashtra Plastic and Thermocol Products (Manufacture, Usages, Sale, Transport Handling and Storage) Notification 2018
• E-Waste Management Rules, 2016
• Biological Diversity Act, 2002
• EIA Notification, 2006 (This is not applicable at this stage but if the borrow areas or new quarries are required to be established then environmental clearance will be required from DEIAA/SEIAA)
• Wildlife (Protection) Act 1972 amended 2003
• Chemical Accidents (Emergency Planning, Preparedness and Response) Rules, 1996
• Bio-Medical Waste (Management and Handling rules) 2016 (Provision is made only for first aid box at camps and construction site with tie up with nearby hospitals. No bio medical waste is likely to be generated at these camps and work site)
• Public Liability Insurance Act 1991
• Explosive Act 1884 & Explosive Rules, 2008
• Ozone Depleting Substances (Regulation) Rules, 2000 as amended in 2005
• The Maharashtra Groundwater (Development and Management) Act 2009
• Guidelines for evaluation of proposals/requests for ground water abstraction for drinking and domestic purposes in Notified areas and Industry/Infrastructure project proposals in Non-notified areas, 2012
• The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 & Rules, 2007
• Ancient Monuments and Archaeological Sites and Remains Act, 1958 (May be applicable for chance findings of archaeological artifact/objects)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 37
Table 2.2 : World Banks Operational Policies - Environmental & Social Safeguard
Name Key Requirement Applicability Remarks
OP 4.01 Environmental Assessment
Ensures sustainability and environmental feasibility of the project. Projects are classified into A, B & C category depending on the nature and extent of the impact.
Triggered Project will have environmental and social impacts All potential impacts are to be identified and appropriate mitigation measures to developed and implemented.
OP 4.04 Natural habitats
Ensures conservation of natural habitats and discourages disturbance of any natural habitat due to project development by recommending adoption of alternative method/route/approach or adopting management measures
Triggered Alignment of saline embankment falls in CRZ area and work shall be undertaken in close vicinity to the mangroves. Also 42 nos of trees are anticipated to be affected due to the project
OP 4.36 Forests
Ensures that project activities do not disturbs/interfere with the forest, forest dwellers activities, fauna and flora of the forest. Prevents and discourages deforestation and impacts on rights of forest dependent people.
Triggered Mangroves are protected forests as per the High Court Notification. Mangroves are in close vicinity to the proposed site which may affect the mangroves. No forest land will be acquired
OP 4.12 Involuntary Resettlement
Ensures minimal involuntary resettlement by considering feasible alternatives project design, assisting displaced people to improve their former living standard.
Not Triggered Not applicable. People are voluntarily donating the land for development of embankment. Consents from land owner is obtained from Kharland Development Circle (KLDC). The project is for welfare of people and protecting the inner land area from sea water ingress
OP 4.10 Indigenous people
Ensures protection of the dignity, right and cultural uniqueness of indigenous people and ensures they receive social and economic benefits
Not Triggered Not applicable, no indigenous people are present in the project area.
OP 4.11 Physical Cultural Resources
Ensures preservation of property of cultural and religious importance, heritage and property of natural importance and enhancement of cultural properties
Not Triggered No archaeological site exists within 300 m of proposed alignment
World Bank’s operational policy 4.01 (OP 4.01) categorize the project into Category A, B &
C on the basis of nature and extent of the impacts anticipated from the project. Scope of
Environmental assessment studies depends on the category in which the project falls and is
defined below.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 38
Category A - Projects with significant environmental impacts and requiring a full
Environmental Assessment (EA),
Category B - Projects with moderate environmental impacts and requiring a lesser level of
environmental assessment,
Category C - Projects which require no environmental assessment, but screening required
The proposed project is sub-component of the NCRMP, is classified as “Category A” as per ESMF guidelines. The project categorization or extent of EIA is undertaken as per approved ESMF. As per the
section 6.4 and item no. d of the ESMF Volume I, “A detailed or limited environmental impact assessment study (as the case may be depending on findings from the
screening exercise) will be undertaken for investments pertaining to saline
embankment/bund strengthening works and underground electric cabling (or in
exceptional cases for roads with major re-alignments). These sub-projects will
undergo an analysis of alternatives, especially in terms of their proposed location
and/or design as required under standard EA practice. For sub-projects requiring
regulatory clearances (including the Coastal Regulation Zone (CRZ) clearance),
alternative site/s will be explored, and for those with no viable alternatives,
permissions will be sought in line with regulatory requirements”
Since the impacts of the project are short term, temporary and spread over the direct impact
zone (proposed RoW) majorly and spill over effects may be felt in immediate surroundings
(15 m on either side of the embankment), a limited EIA study is undertaken for the project.
The EIA study has focused mainly on the environmental and social sensitive receptors
falling within the direct impact zone. All the environmental and social sensitive features
falling in the direct impact zone are mapped and strip maps are prepared. Mitigation and
management plan are designed so as to minimize impact of renovation of the saline
embankment on these environment and social sensitive receptors. Alternative analysis
study is also carried out for location, design and with & without project scenario as per WB
guidelines. CRZ clearance for renovation of the 8 nos of the saline embankment including
Narvel Benavale has been exempted by MCZMA vide letter no CRZ2013/CR-77/TC-4 dated
6th February, 2015 (Annexure 8.1).
2.2. Environmental Standards
Environmental standards are being framed under above mentioned legislations, acts and rules. Standards to be followed during the development and operation phase of the project are listed below.
1. National Ambient Air Quality Standards, 2009 (Annexure 2.1) 2. Noise Standards, CPCB (Annexure 2.2) 3. OSHA’S Noise Exposure Limits for the Work Zone (Annexure 2.3) 4. Drinking water Quality Standards-IS: 10500:2012 (Annexure 2.4)
2.3. Key safeguard documents
Other than this EIA report, existing Environment Social Management Framework for NCRMP – II is referred and other supplementary documents prepared under this project are Strip Maps, Social Impact Assessment Report and Screening Report.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 39
CHAPTER 3. Project Description
3.1. Introduction
The Kharland Development board constructed Narvel Benavale Kharland Scheme in 1952.
The Alignment of Saline Embankment abuts Bhogwati and Amba River/creek. The
embankment has become under section over the period and thus requires renovation by
repairing and strengthening. The Narvel Benavale embankment measures about 16.44 km
and protects village Kaleshrivadi, Tukaramwadi, Mothe Bhal, Vitthalwadi, Lakhola, Borze,
Narvel, Benavale, Sarebhag and Vashi with total benefited area of 1388 ha. Vulnerable
population of 12544 people and their property to the tune of Rs. 1222.50 Lakhs can be
protected from Cyclone and tsunami by rehabilitating this embankment. In addition, people
will be able to carry out agriculture on the land which gets affected due to saline water
ingress in the under-section portions of embankment.
3.2. Project Location and Its Connectivity
The proposed project is renovation of Narvel Benavale saline embankment scheme through
raising and strengthening under NCRMP-II project. Geographically, the proposed project
lies between latitudes of “18°46'41.50"N to 18°39'7.91"N”and longitudes from “73°2'12.85"E” to 73° 2'24.96"E. The embankment is situated near villages Bhal, Narvel & Benavale in
Taluka Pen, District Raigad. The embankment is located at a distance of 20 Kms from
Taluka place at Pen. Site is connected through Narvel Benavale, Washi-Vadhav, Vadhav-
Kaleshree rand other small roads to NH-66 (Alibag-Khopoli road). Location and connectivity
map of the embankment is given in Figure 3.1.
Figure 3.1 : Connectivity Map of Narvel Benavale Embankment Site
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 40
Study area drains into the Bhogwati and Amba River/creek. Arabian sea is approx. 8 km
from the embankment in East direction. Maximum water level near the embankment is 3.88
m with respect to G.T.S. The topography of the study area is almost flat sloping towards
Arabian Sea. The general elevation of land at the proposed project area varies from 0 m to
2 m amsl and is thus prone to inundation during flood and cyclones. Thus, embankment is
essential to protect inland area from inundation. The minimum, maximum and average
ground and top levels of the bund is detailed below in Table 3.1:
Table 3.1 : Existing Elevation Levels of the Saline Embankment
Description Maximum (Meters) Minimum (Meters) Average (Meters)
Ground Level-RL 2.77 -0.74 1.76
Bund Top Level-RL 4.05 1.69 3.11
Source: DPR
3.3. Condition of existing embankment
The existing embankment was constructed in 1952. At present it has become dialapidated
and under section in various sections. Details of the ground level, top width and bottom
width of the existing embankment are attached as Annexure 3.1. Photographs of the
existing embankment are given in Figure 3.3. Top level (RL) of existing bund varies from
1.69 m to 4.05 m. Available bottom width of existing embankment varies between 0.0 m to
15.31 m. Top width of the existing bund varies 0.88 m to 5.99 m
Condition of Embankment Captured at Various Chainages
Figure 3.2 : Photographs of the Existing Embankment
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 41
3.4. Existing facilities on and around embankment
Existing embankment has become undersection and requires repair and strengthening to
continue to protect the benefited area for which is constructed. Over the time various
facilities have come over and in close vicinity to the embankment. Facilities existing on the
embankment is given in Table 3.2.
Table 3.2 : Existing Elevation Levels of the Saline Embankment
Fa
cilit
y
Ele
ctr
ic P
ole
Pu
kka H
ou
se
Jett
y
Fis
h
Po
nd
/Po
nd
s
Serv
ice lin
e
Kach
ha
ho
us
e/jh
op
di
To
ilet
So
lar
Lig
ht
Ott
a/F
ish
dry
ing
pla
tfo
rm
Sh
ed
Cre
mato
riu
m
Sch
oo
l
Te
mp
le
Well
Ro
ad
Nos 10 19 8 24 1 11 7 5 5 3 4 1 2 1 1
Source: Survey
The facilities mentioned above will either be completely or partially affected due to
embankment construction and budget is considered for either rehabilitation or
reconstruction of these facilities. As a measure to mitigate the impact on school and other
structures it is proposed to realign the existing embankment by straightening between
chainage 13230 to 13380. Structure falling between these chainages includes 3 houses, 1
jetty, 1 tree, 1 temple (Bahari) and 1 pond. These structures may also be saved along with
the school due to straightening of the embankment.
In addition to the above facilities, 42 nos of trees exists on the embankment which will also
may get affected. Mangroves are also present in close vicinity to the embankment and they
are all along the embankment towards creek side whereas in patches towards land side.
NOC from Mangroves Cell of Forest Department is obtained for working in the area while
minimizing the impact on mangroves. Budget for relocation of facilities is considered under
the project cost. Details of location of the facilities, which will get impacted due to the
proposed project, are given in Annexure 3.2.
3.5. Natural Hazards of the Project Area
Project area falls under the coastal zone of the Raigad District and is prone to threats of
cyclones and inundation during storm. Area in past have experienced two devastating
cyclones, i.e. ARB02 in 1994 & Phyan in 2009, which has caused substantial loss of life,
and property in the area. In addition, seawater enters inland from the locations where the
saline embankment has become undersection during high tide in monsoon season. Such
chainages are not defined in the DPR but has been communicated by the public during the
consultation. HFL/HCL level at the site is 3.68 m. Thus, to prevent the impact of cyclone on
these embankments, it is proposed to increase the height of the embankment. Top level of
the designed embankment considered is 5.18, thus there is free board of 1.5 m available
beyond the HFL/HCL. Seismic hazard is high in the area as the area falls under the seismic
zone IV. Structure of embankment is designed as per the seismic zone IV.
3.6. Description of The Project
Project involves Renovation of the saline embankment by strengthening and repairing the
embankment. Under the project, existing embankment will be compacted, strengthened and
height will also be increased. Since the height of the embankment will increase, approach
roads will also be developed to connect the existing roads and the embankment. Facilities
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 42
which will be affected due to the project will also be shifted or reconstructed. Road which
will be affected at chainage 2910-2970 will be reconstructed. There are 7 existing CD works
which is in dilapidated condition and needs to be reconstructed. It is proposed to construct
new CD work. Ring bund will be provided at location of CD work during reconstruction to
prevent ingress of sea water. Salient features of the project are given in Table 3.3 below.
Layout map of the proposed embankment is attached as Annexure 3.3. Typical cross
sections of the embankment are attached as Annexure 3.4.
Table 3.3 : Saline Features of Proposed Embankment
S.No. Parameter Description Embankment
20. Type of embankment (Homogeneous / zoned/ rockfill): -
Zoned5
21. Length of embankment (m) : 16440 22. Top width (m) :- 3.00 23. Top Bund level TBL (m) 5.18 24. Maximum Bottom Width (m) 23.76 25. Seismicity of the project area (IS:1893): - Zone – IV 26. Slope of embankment.
1) U/S (Field side.) 2) D/S (Creek side.)
1.50 : 1 1.50 : 1
27. Sill level. 0.83 28. High tide level. 2.6 29. High flood level. 3.88 30. Free board. 1.5 m.
Sluice Gate/Ugadi 31. No. of C.D. Works. 8 32. Location. Of CD works Existing: Ch. 388m, 1786m, 2507m,
6732m, 7228m, 8787m & 9547m Proposed: 16405 m
33. Opening Rectangular 34. Catchment area. 20.37 Sq. Kms. 35. Flood discharge as per DICKNS
FORMULA 174.22 cum/sec
36. Area of water way provided. 149.89 Sqm. 37. Dimensions of opening (mm) Existing: 7 nos
Proposed: 1 additional Total: 7 reconstructed +1 new Existing
9) Ch.393m 3 x 1.50 x 2.43 10) Ch.1786m 3 x 1.50 x 2.43 11) Ch.2507m 3 x 1.50 x 2.43 12) Ch.6732m 3 x 1.50 x 2.43 13) Ch.7228m 3 x 1.50 x 2.43 14) Ch.8787m 3 x 1.50 x 2.43 15) Ch.9547m 3 x 1.50 x 2.43
Proposed 16) Ch.16405m 7 x 1.5 x 2.43
38. Types of Gates FRP / PPGL Gates, with horizontal hinges on top, acting one way restricting thereby saline water to
5 Zoned embankments are the one which comprises of zones of selected materials having different degree of porosity, permeability and
density
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 43
enter in the benefited area.
3.7. Right of Way Detail & Land Details
Existing Narvel Benavale saline embankment was constructed using private and
government lands earlier, however as per the proposed renovation and strengthening the
design requires additional land. Width of the embankment as per the existing design and
proposed design requirements is shown in the Table 3.4 below and the existing and
proposed width and height are detailed in Annexure 3.1 and 3.5. Total land requirement for
the renovated embankment is 243960 sq. m out of which 115958 sq. m is existing and
additional 128002 sq. m of land is required6. However, people have given their consent to
KLDC to use their land for construction of embankment. Village wise detail of the land
requirement is given below in Table 3.5.
Table 3.4 : Showing Existing and Proposed Right of Way (RoW)/Bottom Width Details
Sl. No Name of the Saline Embankment
Existing bottom width in meters
Designed Bottom width meters
1 Narvel Benavale 0.0 m to 15.31 m 10.33-23.76 Source: DPR
Table 3.5 : Village Wise Detail of Land Requirement
Village Private Government land/creek side land/other land
Total Land
Existing Land-ha
Additional Land-ha
Total Existing Land-ha
Additional Land-ha
Total
Kaleshrivadi 0.2399 0.4317 0.6716 0.7761 0.9799 1.756 2.4276 Tukaramvadi 0.1002 0.1747 0.2749 0.4735 0.3388 0.8123 1.0872 Mothe Bhal 0.0722 0.0593 0.1315 0.3001 0.4192 0.7193 0.8508 Vithalwadi 0.4169 0.2921 0.709 2.681 3.0605 5.7415 6.4505 Lakhola 0.7365 0.9155 1.652 0.0806 0.089 0.1696 1.8216 Borze 0.6495 0.766 1.4155 0 0 0 1.4155 Narvel 0.9709 0.781 1.7519 0.0924 0.1645 0.2569 2.0088
Benavale 1.8255 1.476 3.3015 0.1022 0.1559 0.2581 3.5596 Sarebagh 0 0 0 2.0397 2.6477 4.6874 4.6874
Vashi 0 0 0 0.0386 0.0484 0.087 0.087 Total 5.0116 4.8963 9.9079 6.5842 7.9039 14.4881 24.396
Source: KLDC
3.8. Existing Drainage Conditions
Benefited area protected by existing embankment is well drained through the seven nos of
CD works. Same CD works shall be maintained after the renovation works also to ensure
the drainage. One more CD work is proposed to be constructed at chainage 16405 m. After
renovation there will be 8 CD works through which embankment will drain the storm water.
Additionally, longitudinal drains will be provided on the slope of embankment and along the
toe of the embankment to drain on creek side so as the water falling on the embankment
can easily be drained off to prevent the erosion. Drainage system is designed so as the
entire water will be channelized to the creek.
6 As per the PAP List Prepared by KLDC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 44
3.9. Design Criteria
European Economic Community (EEC) has carried out the study and provided the designs
to the Kharland Development Circle (KLDC) for construction of the embankments. European
Economic Community (EEC) in their study has considered the designs approved by
Government of Maharashtra with certain modifications7. Top level of the embankment is
finalized considering the results of HEC RAS computer program. Highest tide levels
published by the Maharashtra Maritime Board over a period of 25 years up to the year 2014
are considered for design of the Saline Embankment. The design of the Cross-Drainage
works is adopted in the form of R.C.C Structures founded on Raft footings & supported by
counter-fort retaining walls on sides to save in the quantity of concrete as per the finalized
design
3.10. Proposed Project Components and Construction Methodology
Embankment
ROW of embankment will be cleared off the vegetation. Earth will be stripped up to the
depth of 15 cm from the RoW. Existing embankment will then be compacted using
compactors and rollers. Thereafter the earth (hearting (earth) followed by casing (murrum)
material) & other material will be laid in layers as per approved design. Geo-textile will be
provided on the slopes followed by murrum. Thereafter stone pitching will be carried out on
the embankments using stone rubble or stone chips. Rock toe of the embankment will be
constructed for retaining the embankment. Gabion wall/protection wall is proposed to be
constructed in various sections which are weak and where enough land is not available to
strengthened the embankment and minimize the social issues. Details of chainages where it
is proposed to provide gabion wall is given in Annexure 3.6. The embankment will be
constructed with suitable material as determine by Engineer & compaction to 95 % of
standard proctor density with vibratory roller.
Groynes
Groynes are the vertical stone structures which are engineer at the sharp curves or edges
of the embankment so as to divert the water/waves to prevent direct hitting to the
embankment. These structures will prevent the washing away/scouring and erosion of the
embankment. These groynes will be constructed at curvature points in this embankment.
Provision for Groyne construction is kept in the DPR. It is proposed to provide groynes at
chainage 13500, 13595, 13550, 14570, 14600, 14640, 14790, 15100 and 15150.
CD Works
There are total seven nos of CD work existing in embankment. CD works are existing at
Chainage 388 m, 1786 m, 2507 m, 6732 m, 7228 m, 8787 m, 9547 m. One more CD work
will be constructed at chainage 16405 m. Ring bund will be provided at location of the CD
works construction to prevent flow of water from creek to land during high tide. Raft
foundation will be provided for the proposed CD work. Material approved by engineer and
as per BOQ will only be used for construction of the CD works. Rock toe will be provided in
starting and end chainages of the CD work to prevent scouring of the CD works due to
water action. Cross section drawings of CD works are attached as Annexure 3.7.
7 Modification in the Murum bedding below the stone pitching from 10 cm to 30 cm thick
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 45
Approach Road
Approach road of total length 500 m (250 m on each side) will be constructed to connect the
embankment with the existing roads.
3.11. Slope Stabilization
The stone pitching is provided at Field Side up to H.F.L & at Creek Side up to Top of Bund
Level of the saline embankments. Beyond the stone pitching, turfing will be provided on land
side. The thickness of stone pitching is 20 cms. Pitching is provided from the ground level
right up to the top of embankment on creek side. Headers are provided for the pitching on
the creek side so as to sustain the wave action and tidal effects. 30 cm thick murum
bedding is provided below stone pitching for better strength and stability.
Jute/coco fibers are more economic and environment friendly options but as per KLDC
experience for stone pitching option is more suitable, as the life of stone pitching is much
more than jute/coco fibers and consider stone pitching more economical and suitable for the
location. Stone pitching of the existing embankment is also intact in many places and
reference can be taken from Koleti embankment which was constructed 5 years ago and is
still intact8. Further there are no issues of theft with the stone pitching unlike jute/coco fibers
pitching. It was discussed with villagers also and they have agreed to protect the
embankment and the pitching.
3.12. Waste Generation and Management
Waste which may generate from the project will include the demolition waste, stripped earth,
vegetation waste, municipal waste from labour, Dry concrete/empty cement bags/broken
bricks and stones, broken wooden supports etc. Estimation is done for the quantity of
demolition waste and stripped earth and is given in Table 3.6.
Table 3.6 : Estimation of Quantity of Waste
S. No. Type of Waste & Source Quantity Management and Disposal
1 Demolition of Waste: Dismantling of 7 nos of CD works
365.9 cum for all the CD works
Segregation into recyclable and non-recyclable waste. Recyclable waste to be sold to the authorized vendors and non-recyclable to be disposed at debris disposal site to be identified by contractor
2 Earth: Stripping of existing 40105.69 cum for the To be heaped along
8 Pictures of Stone pitching of Koleti saline
embankment
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 46
embankment and proposed embankment alignment
entire project the alignment on landward side under covered condition. To be disposed in regular intervals at debris disposal site to be identified by contractor
3 Municipal Waste: generated from labour camps
Approx. 20-25 kg/day (@ approx. 50 labours in the labour camp)
Disposed-off through the local agency in area or pit composted or disposal at the debris disposal site to be identified by contractor
4 Construction Waste: Generated from construction of embankment and CD works
Approx. 10-20 kg/day Segregation into recyclable and non-recyclable waste. Recyclable waste to be sold to the authorized vendors and non-recyclable to be disposed at debris disposal site to be identified by contractor
Source: DPR & EQMS Experts 3.13. Construction Material Requirement
Detail of the construction material requirement, quantity and sources are provided in the
Table 3.7. All material will be purchased from local vendors only within distance of 35 km
from embankment. Earth and quarry materials will be purchased from the authorized
suppliers having valid environmental clearance for minor minerals as per EIA Notification,
2006. Map showing location of the material sources is attached as Annexure 3.8.
Table 3.7 : List of material and their sources with distances
Sr. No. Material Available at Distance (km.) Quantity
1 Soil (cum) Pen 20.00 312654.56 2 Murum (cum) Mapgaon 35.00 73460.46 3 Rubble (cum) Mapgaon 35.00 46312.35 4 Sand (cum) Dharmtar 25.00 11885.89 5 Cement (cum) Pen 20.00 3224.93
6 Steel (MT) for sheet pile
Pen 20.00 108
7 Stone Pitching-sq. m
Mapgaon 35.00 42224.25
8 Metal-cum Mapgaon 35.00 4195.68
3.14. Time and Implementation
The project will be implemented within the period of 180 days. The contractor shall start
work in different packages wherever approach is available in order to complete the work in
the designated time period. Work should be undertaken only after offset of monsoon
season.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 47
3.15. Project Cost
The total estimated project cost for the renovation of embankment, CD work and the
approach road will be Rs. 53,03,93,768.66. Description of the project cost is shown in Table
3.8. This cost does not include the cost of environmental management and restoration of
the facilities/utilities getting disturbed which can be referred from the EMP chapter
Table 3.8 : Cost Estimation of the Renovation of Embankment
Sr.No. Description of Item Amount
1 'Earthen Embankment.'' 266908652
2 'C. D. Works''. 71382895.82
3 Approach Road 1013136.50
Total INR 33,93,04,685.31
Final Cost with Quality Control, price variation, GST (12%), Royalty charges, 10% additional charges,
53,03,93,768.66
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 48
CHAPTER 4. Description of the Environment
4.1. Introduction
Generation of environmental baseline of a project area is an important phase of any
Environmental Assessment process. Baseline data provide vital information on the existing
environmental quality in which a development is planned. In order to assess impacts due to
the project, baseline environmental conditions have been studied and discussed in this
chapter.
The entire study area is classified under two categories i.e. Direct Impact zone and Project
Influence area.
Direct Impact Zone: Proposed RoW of the embankment is considered as the direct impact
zone as all the project activities will be restricted to the proposed RoW. No project activity
like clearance, staging of machinery, stocking of material etc will be done outside the
designed RoW of embankment. Thus, the proposed/design alignment is considered as
operational area for this project. However, spill over effects of construction will also occur in
immediate surroundings like blockage of access to houses and agriculture field, impact on
mangroves and vegetation along the embankment, dust generation and high noise level.
Strip mapping is thus done for the proposed RoW and additional 15 m width on each side of
the proposed alignment. Strip maps are attached as Annexure 4.1.
Project Influence Area: It is the area, which will be impacted due to the project
development. It includes both direct and indirect impact zones. For this study purpose,
impacts anticipated are majorly during construction phase and short term only. The impacts
which may occur up to 1 km will include disturbance in air quality, increase in noise level,
impact on access to village and the agriculture field, shifting of utilities and disturbance of
aesthetics. Considering the type of impact, it is anticipated that the impact will not extend
beyond the 1 km radius of the proposed project. Thus, project influence area is considered
as proposed RoW/alignment and area within 1 km radius of the proposed alignment.
However, notified eco-sensitive zones are studied within the 10 km radius are of the
proposed alignment
4.2. Site Description and Its Environmental Salient Features
The embankment is situated near villages Bhal, Narvel & Benavale in Taluka Pen, District
Raigad. The embankment is located at a distance of 20 Kms from Taluka place at Pen. Site
is connected through Narvel Benavale, Washi-Vadhav, Vadhav-Kaleshree rand other small
roads to NH-66 (Alibag-Khopoli road). Study area drains into the Bhogwati and Amba
River/creek. Arabian sea is approx. 8 km from the embankment in East direction. Maximum
water level near the embankment is 3.88 m with respect to G.T.S. The topography of the
study area is almost flat sloping towards Arabian Sea. The general elevation of land at the
proposed project area varies from 0 m to 2 m amsl and is thus prone to inundation during
flood and cyclones. Thus, embankment is essential to protect inland area from inundation.
There are no environmentally sensitive components such as National Park, Wildlife
Sanctuary, Elephant / Tiger Reserve, migratory routes of avi fauna or terrestrial fauna is
present within 1 Km as well as within 10 km radius of the site. The Salient Environmental
Features of Narvel-Benavale embankment site is summarised in Table 4.1. Map showing
the location of site and surroundings within 1 km and 10 km radius are given in Figure 4.1
and 4.2.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 49
Table 4.1 : Salient Environmental Features of Narvel Benavale embankment Site
Sl.
No.
Environmental Features
Yes
No
Details
1 Biosphere Reserve √ No notified area within 10 km
distance from embankment 2 National Park √ No notified area within 10 km
distance 3 Wildlife/Bird Sanctuary √ No notified area within 10 km
4 Tiger Reserve/Elephant Reserve √ No notified area within 10 km
distance 5 Turtle nesting grounds √ No notified area within 10 km
distance 6 Wetland √ No notified area within 10 km
distance 7 Mangrove area √ All along the embankment in
creek side and in patches on
land side. Mangroves exists
along the water channel
existing on the land side
8 Estuary with mangrove √ Bhogwati and Amba
Creek/River
9 Natural lake √ None within 1 km distance
10 Swamp/mudflat √ Present within 1 km area
11 Habitat of migratory birds (outside
protected area)
√ None
12 Migratory route of wild animals/birds √ None
13 Area with threatened/rare/endangered √ None
14 Reserve / protected forest √ Mangroves are declared
protected forest as per High
Courts Notification and they
exist along the embankment in
creek side and in patches on
land side. Mangroves exists
along the water channel
existing on the land side.
Mangrove cell has given NOC
for renovation of the
embankment while protecting
the mangroves
15 Zoological park/Botanical Garden √ None
16 Rivers, streams, estuaries or deltaic
mouth? Within 500 M
√ Bhogwati and Amba
Creek/River
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 50
17 CRZ Area Yes, falls under CRZ area.
Permission obtained from
MCZMA for renovation of
embankment
18 World heritage site √ None
19 Archeological monument/site (under ASI-
Central or state list)
√ None
20 Historical places (not listed under ASI-
central or state list but regionally/locally
important)
√ None
21 Reservoir/Dam √ None
22 Public Water Supply Areas from
Rivers/Surface Water Bodies/ Ground
Water Sources
√ None
Source: EQMS Experts
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 51
Figure 4.1 : Location Map and Surroundings Within 1 km Radius
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 52
Figure 4.2 : Location Map and Surroundings within 10 km Radius
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 53
4.1. Physiography and Land Use
The district Raigad has three physiographic divisions i.e. (i) Coastal zone in west covers
about 20% percent of the district (ii) Central zone covers about 1/3rd of the district,
consisting of fertile land in low lying area (iii) Hilly zone in the eastern part highly uneven in
altitude and covered with forest. This hill range is characterized by ruggedness and uneven
topography, with crestline of peaks and saddles forming the eastern horizon. The drainage
of the study area is controlled by Amba and Bhogwati river. Amba river is flowing west of the
Narvel Benavale embankment and Bhogwati river is flowing along the northern boundary of
the embankment.
The study area lies in Coastal zone in west and form an extensive flat alluvial tract. The
topography of the study area is almost plain sloping towards Arabian sea. Elevation of the
benefited area varies from 0-4 m amsl.
The land use of the core embankment site is with spars shrubby plantation. As per the land
use analysis of 1 km area around the proposed embankment site, about 53.58% of the land
is under cultivation, about 19.89% land is under water bodies, about 16.06% of the land is
under vegetation, 10.07% land is marshy land and rest of the land is under other uses
(Refer Figure 4.3 and Table 4.3). Land Use map of the project influence area is given in
Figure 4.4.
Table 4.2 : Land use of the Study Area
Sl. No. Class Area (Sq. km) Percentage
1 Agricultural Land 17.35 53.58 2 Settlement 0.13 0.40 3 Water body 6.44 19.89 4 Vegetation 5.20 16.06 5 Marshy Land 3.26 10.07 Total 32.38 100
(Source: Satellite image analysis by EQMS)
(Source: Satellite image analysis by EQMS)
Figure 4.3 : Graphical presentation of the Land use within 1 km radius of the Narvel Embankment site
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 54
(Source: Satellite image analysis by EQMS)
Figure 4.4 : Land Use Map
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 55
4.2. Climate
The study area falls in Raigad district of Maharashtra state. The climate of the study area is
typical as of the west coast of India, with plentiful, regular and seasonal rainfall during the
monsoon season. Being a coastal district, the diurnal (daily) and seasonal variations in
temperature is not much. The year may be divided into four seasons; the summer from
March to May, the rainy season from June to September, the post-monsoon season in
October and November, and the winter season from December to February. The average
annual rainfall for the district as a whole is 2164 mm. The air is humid throughout the year.
Humidity is 98% in rainy season & in winter is 60%. Average daily temperature in the district
is 22°C to 30°C and minimum temperature is 17°C to 27 °C. Climate of the town is also
moderate. The wind speed was observed mostly between 6.9 and 27.3 km/hour for all the
months. The predominant wind direction during summer and winter is from North-West
direction. During monsoon season the wind flows from South-West direction.
Severe tropical storms with wind speed of over 150 km/hr occur in the Arabian Sea,
generally during May /June and October /November. However, the frequency of such
cyclonic storms passing over Mumbai and surrounding areas is low when compared to East
coast of India. Two major cyclones which affected Maharashtra and project area are ARB
02 in 1994 and Phyan in 2009. Wind speed during ARB02 cyclone was between 118-165
kmph (32-45 mps)9 and during Phyan was between 85-95 kmph (24-26 mps). These types
of cyclones are classified as very severe and severe category cyclones.10 The
meteorological parameters play a vital role in transport and dispersion of pollutants in the
atmosphere. The long term historical meteorological data was obtained from nearest IMD
station located at Alibag which is approx. 20 km from site in SW direction. Details provided
in Table 4.3.
Table 4.3 : Meteorological Data of Alibag (Period: 1981-2010)
Month
Temperature (oC) daily
Relative Humidity (%)
Rainfall (mm)
Predominant Wind Direction
(From)
Cloud Amounts
Oktas
Wind Speed Km/hr
Max Min 08:30 17:30 08:30 17:30 08:30 17:30
January 29.1 17.5 75 62 0.6 E, NE NW, N 0.5 0.4 7.6
February 29.3 18.3 75 63 0.1 NE, E NW, N 0.3 0.2 8.5
March 30.8 21.0 78 65 0.2 NE, E NW, N 0.6 0.4 10.2
April 32.0 23.9 79 70 0.2 NE, E NW, W 1.0 0.6 11.0
May 33.4 26.6 76 72 16.4 SE, NW
NW, SW 2.8 1.9 13.8
June 31.9 26.2 84 80 584.7 SW, SE
SW, NW 5.3 5.3 19.5
July 30.2 25.5 88 84 730.7 SW, W
SW, W 6.5 6.5 24.7
August 29.7 25.1 88 83 555.9 SW, W
SW, NW 6.6 6.4 22.1
September 30.4 24.4 89 79 345.4 SE, E NW, SW 4.6 4.7 11.7
October 32.6 23.5 83 70 76.2 E, NE NW, N 2.0 1.9 7.9
November 33.0 21.1 75 63 7.2 E, NE NW, N 0.8 0.7 6.9
9Source: Report on cyclonic disturbances over North Indian Ocean During 1994 10Source: Cyclone hazard proneness of districts of India by M Mohapatra, Cyclone Warning Division, India Meteorological Department
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 56
December 31.0 18.8 74 63 3.1 E, NE NW, N 0.7 0.7 6.8
Annual Total or Mean
31.1 22.7 80 71 2320.7 E, NE NW, SW 2.7 2.5 12.6
(Source-IMD Alibag)
4.3. Seismicity and Associated Hazards all along the waterways
According Seismic map of India 2002 the entire Raigad districts lie in Zone IV, where the
maximum expected intensity is VIII (MSK). Project area also falls under Seismic Zone-IV. It
means that the area is covered under “High Seismicity-hazard zone. The seismic zoning
map of India showing project site is shown in Figure 4.5.
(Source: Seismic Zone Map of India 2002)
Figure 4.5 : Seismic Zones of India
4.4. Soil
Soil types of Pen are loamy, mixed, isohypethermic and Lithi Ustorthents as per soil maps
of Maharashtra, NBSS&LUP (National Bureau of Soil Survey and Land Use Planning),
Nagpur. Soil types of direct impact zone are khar/saline.
4.5. Water Environment
Ground Water: Project site is located in the coastal area and along the creek. In coastal
areas, ground water level is high and the quality is not fit for drinking due to saline water
ingress. As per the CGWB11 estimation the net annual ground water availability for Pen
Taluka is 1.69 MCM. Gross draft of ground water in Pen Taluka for irrigation is 6.17 MCM,
for domestic and industrial water supply is 4.34 MCM making total gross draft to be 10.51
MCM. In the project area, as per CGWB report, stage of ground water development in Pen
Taluka is 8.22% and is categorized as safe zone.
11 Ground water information, Raigad district Maharashtra, CGWB, 2013
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 57
Hydrogeology: Deccan Trap Basalt of upper Cretaceous to lower Eocene is the major rock
formation in the study area. The western part of the district consisting Basalt flows are
altered to Laterite. Recent deposits comprising Beach Sand and Alluvium occur along the
coast and in the river mouth.
Coastal Saline Area and Effect on Ground Water: Being a coastal alluvial tract the whole
study area is saline. Both fresh and saline aquifers are present in the area but most of the
study area is along the coast and ground water and have been rendered saline due to
breach in age old bunds.
4.6. Biological Environment (Project Site and Zone of 1 km radius)
Biological environment is the environment where life forms can exist. The sum of
environments where life forms exist is called the biosphere, these includes a portion of land,
water, and air. Generally, biological environment of an area is good indicators of climatic
and edaphic factors. Studies on biological aspects of ecosystems are important in
Environmental Impact Assessment for safety of natural flora and fauna. The biological
environment includes terrestrial and aquatic ecosystems. The animal and plant communities
co-exist in a well-organized manner. Their natural settings can get disturbed by any
externally induced anthropological activities or by naturally occurring calamities or disaster.
So, once this setting is disturbed, it sometimes is either practically impossible or may take a
longer time to come back to its original state. Hence, changes in the status of flora and
fauna are an elementary requirement of Environmental Impact Assessment studies, in view
of the need for conservation of environmental quality and biodiversity.
4.6.2 Ecological Profile of Project Area
Ecological study is carried out for the project influence area which is proposed RoW and 1
km radius around the embankment site. The ecology of project influence area includes tree
plantation, mangroves, agrarian ecosystem as well as aquatic ecosystem Bhogawati and
Amba river/creek. Eco-sensitive features area studied in 10 km radius of the embankment
and the summary of analysis is presented in Table 4.4.
Table 4.4 : Sensitive Environmental Feature within 10 km radius of the Narvel Benavale Embankment Site
Sl.
No.
Environmental Features
Yes
No
Details
1 Biosphere Reserve √ No notified area within 10 km
distance from embankment 2 National Park √ No notified area within 10 km
distance 3 Wildlife/Bird Sanctuary √ No notified area within 10 km
4 Tiger Reserve/Elephant Reserve √ No notified area within 10 km
distance 5 Turtle nesting grounds √ No notified area within 10 km
distance 6 Wetland √ No notified area within 10 km
distance
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 58
7 Mangrove area √ All along the embankment in
creek side and in patches on
land side. Mangroves exists
along the water channel
existing on the land side
8 Estuary with mangrove √ Bhogwati and Amba
Creek/River
9 Natural lake √ None within 1 km distance
10 Swamp/mudflat √ Present within 1 km area
11 Habitat of migratory birds (outside
protected area)
√ None
12 Migratory route of wild animals/birds √ None
13 Area with threatened/rare/endangered
flora
√ None
14 Reserve / protected forest √ Mangroves are declared
protected forest as per High
Courts Notification and they
exist along the embankment in
creek side and in patches on
land side. Mangroves exists
along the water channel
existing on the land side.
Mangrove cell has given NOC
for renovation of the
embankment while protecting
the mangroves
15 Zoological park/Botanical Garden √ None
16 Rivers, streams, estuaries or deltaic
mouth? Within 500 M
√ Bhogwati and Amba
Creek/River
17 CRZ Area Yes, falls under CRZ area.
Permission obtained from
MCZMA for renovation of
embankment
18 World heritage site √ None
19 Archeological monument/site (under ASI-
Central or state list)
√ None
20 Historical places (not listed under ASI-
central or state list but regionally/locally
important)
√ None
21 Reservoir/Dam √ None
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 59
22 Public Water Supply Areas from
Rivers/Surface Water Bodies/ Ground
Water Sources
√ None
Source: Primary and Desktop Survey
4.6.3 Terrestrial Ecology in Project Influence Area
The terrestrial ecology within the whole impact zone is discussed as under:
Direct Impact Zone: There are approx. 42 trees on the saline embankment apart from the
shrubs and herbs. Details of the trees existing on the embankment are given in Table 4.5.
These trees will be cut for the renovation
of embankment. None of these trees are
listed in the Maharashtra Tree Felling
Act, 1964, thus permission for tree cutting
should be obtained from District Collector
as per NGT Order order dated 8th Jan
2016 – case no 11/2015 (WZ). There are
mangroves and shrubs all along the
embankment on the creek side whereas
there are cultivated and non-cultivated
agricultural fields on the land side of the
embankment. Mangroves are also
observed in patches in land side and
along the channels running inside the
benefited area. List of some of the
patches where mangroves were found on land ward side are given below in Table 4.6.
These patches are marked on the strip maps also. Major mangrove species observed close
to the embankment are Tivar (Avicenia marina), and Maraudi (Acanthus ilicifolius). Other
mangrove species present in area includes White Mangroves (Avicennia officinalis),
Kamodumbi (Rhizophora apiculate or Rhizophora mucronata), Salvadora persica and
Sonneratia species. Some of the mangrove associates found in the area are Acanthus
illicifolius, Clerodendron inerme, Cressa cretica, Derris trifoliata, Derris uliginosa and
Fimbristylis ferruginea. Permission has been obtained
fom Mangrove cell of forest Department for
renovation of the embankment. There will be minimal
disturbance to mangroves while carrying out
renovation works. Mangrove line (creek side toe line
of existing embankment) is considered as the creek
side starting boundary of the embankment. Kharland
Department Circle has planned the project in a way to
have minimal impact on the mangroves. Mangroves
on land side will continue to get brackish water supply
through the existing water channels on the land ward side. None of the channel will be
blocked or diverted.
Vegetation on the Bund
Mangroves on Landward Side
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 60
Table 4.5 : Detail of Trees Present on Embankment
S.No. Trees Coordinates Distance from creek side end
of embankment(
m)
Chainage/Chainage Range
No of Trees
1. Neem 18°46'42.83"N 73° 2'11.95"E
6.5 70 1
2. Trees Bhend Suvabal Nariyal
18°46'46.03"N 73°
2'10.50"E
6.0 180 5 3 1 1
3. Anwala Tree
18°46'46.40"N
73° 2'10.40"E
7.4 210-260 1
4. Bhendi 18°46'58.77"N
73° 2'3.83"E
9.0 540-570 2
5. Bhendi 18°47'13.03"N
73° 1'5.08"E
7.5 2550 3
6. Bhendi 18°47'14.13"N
73° 1'4.67"E
9.5 2590 1
7. Trees Bhendi Segva Nariyal Neem
18°47'21.89"N
73° 0'58.06"E
8.8 2910-2930 9 4 2 1 2
8. Trees Bhendi Sitaphal Kaju
18°47'23.45"N 73°
0'57.40"E
9.5 2970 3 1 1 1
9. Bhendi 18°47'21.89"N
73° 0'58.06"E
10 3360 1
10. Bhendi 18°47'17.94"N 72°59'59.16"E
4 7235 1
11. Trees Bhendi
18°46'23.93"N73° 0'2.13"E
7.4 9000 5 4
Mangroves Patches on Landward Side
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 61
Siras 1
12. Bhendi 18°45'20.49"N 73° 0'27.98"E
6.5 13290 6
13. Bhendi 18°45'13.44"N 73°
0'37.52"E
7.2 13800 1
14. Bhendi 18°44'57.95"N
73° 1'24.52"E
6.8 15780 2
15. Bhendi 18°45'1.08"N 73° 1'54.30"E
9.0 16440 1
16. Total 42
Source: Site Survey
Table 4.6 : Detail of A Few patches Observed on Land Side During Survey
S.No. Structure Trees Coordinates Distance from creek side end
of embankment(
m)
Chainage/Chainage Range
1. - Mangroves patches creek and landward
side
18°47'13.83"N 73°
1'35.51"E To
18°47'11.65"N 73°
1'31.82"E
00 1650-1740
2. - Mangroves patches creek and landward
side
18°48'0.11"N 73° 0'7.21"E
To 18°47'54.53"
N 72°59'43.00"E
00 5010-5820
3. - Mangroves patches creek and landward
side
18°47'40.01"N
72°59'41.43"E To
18°47'8.20"N 72°59'59.88"E
00 6270 -7590
4. - Mangrove patches creek and landward
side
18°46'46.06"N 73° 0'10.70"E To 18°46'24.38"N 73° 0'2.67"E
00 8340 -9090
5. - Mangrove patches creek and landward
side
18°46'21.78"N 73° 0'1.40"E To 18°46'19.42"N 73°
00 9150-9240
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 62
0'0.16"E
6. - Mangrove patches creek and landward
side
18°46'10.45"N 72°59'55.10"E To 18°45'58.70"N 72°59'50.78"E
00 9720-10350
7. - Mangrove Patches creek and landward
side
18°45'0.76"N 73° 1'46.06"E To 18°45'3.01"N 73° 1'53.13"E
00 16110-16380
Source: Site Survey
4.6.4 Fauna
No significant wildlife is observed in the study area as there are no national parks, birds’ sanctuaries, wildlife sanctuaries, Elephant / Tiger Reserve (existing or proposed), migratory
routes/ wildlife corridor within 1 km area of the embankment site. Few patches of mangrove
forests exist within 1 km area of the embankment. Mangroves are present along the
alignment of the proposed embankment. These mangrove patches serve as a habitat for the
wild fauna.
Mammals: No significant carnivorous and herbivorous wild animals are found in the area.
Fox, Mongoose, Porcupine, monkeys and Jungle Cat (Felis chaus) are the common
mammals found in the project influence area
Amphibian & Reptiles: Frog, Indian bull frog, snake like Indian cobra (Naja naja); Dhaman
(Lycodon aulicus), Chitti (Bungarus spp.) and lizard are found in the project influence area
Avifauna
The area is inhibited by resident’s forms of a large numbers of avifauna like the weaver bird,
common myna, house sparrow, Weaver bird house crow, Common Crow, Blue Rock Pigeon
and many water birds. All the birds are found near water bodies and wet irrigated fields
feeding actively on insects.
Details of Fisheries
Fishes are at the apex in aquatic food chain. Fishing is the prime occupation of people in
the study area. Being a coastal area people is engaged in fishing activity, so fishermen have
their own assets of fishing. List of fish observed/reported in the study area is given in Table
4.7.
Table 4.7 : List of Crustaceans and fish in Study area
Sl.No. Scientific name Family Local Name
1. Uca sp. Ocypodidae Fiddler crab
2. Scylla serrata Portunidae Mud crab
3. Penaeus monodon Penaeidae Tiger prawn
4. Penaeus indicus Penaeidae White shrimp
5. Squilla mantis Squillidae Squilla
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 63
6. Scylla serrata Portunidae Mud crab
7. Charybdis annulata Portunidae Swimming crab
8. Charybdis cruciata Portunidae Cross crab
9. Metapenaeus affinis. Penaeidae Jinga shrimp
10. Palaemon semlenkii Penaeidae Prawn
11. Scylla serrata (Mud crab) Ariidae Cat fish (Shingala)
12. Rastrelliger kanagurta Scombridae Mackerel (Bangda)
13. Pampus chinensis Stromateidae Chinese silver pomfret (Halwa / kalet)
14. Chirocentrus dorab Chirocentridae Silver bar fish (Karli)
15. Boleophthalmus dussumieri Gobiidae Mud skipper
16 Scatophagus argus Scatophagidae Spotted scat (Wada)
17 Coilia dussumieri
Engraulidae (Anchovies)
Goldspotted grenadier anchovy (Mandeli)
18. Lates calcarifer Latidae Barramundi / Asian Seabass (Jitada / Khajura)
19. Mugil cephalus Mugilidae Mullet (Boi/Pit)
20. Eleutheronema tetradactylum
Polynemidae Rawas (Sallmon Indian )
21. Polynemus plebeius Polynemidae Rawas
22. Acanthacaris spp
Nephropidae Shevand (Lobster)
23. Ariosoma anago Murai-nesocidae Vam, Bale (Eel) Source: Consultation with people
Endangered Species
Endangered (EN) species is a species which has been categorized by the International
Union for Conservation of Nature (IUCN). "Endangered" is the second most severe category
for wild populations in the IUCN list after Critically Endangered (CR). No species were found
in study area which is listed as endangered species in IUCN category.
4.7. Socioeconomic Environment
Raigad is one of the 36 districts in the state of Maharashtra. The district is bounded
by Mumbai Harbor to the northwest, Thane District to the north, Pune District to the
east, Ratnagiri district to the south, and the Arabian Sea to the west. For administrative
purposes the district is divided into 4 sub-divisions viz., Alibag, Panvel, Mapgaon and
Mahad. Pen is town and taluka in Raigad District. Pen is famous and known for its world
class Ganesh Idols. Narvel Benavale embankment is located in Pen taluka and protects the
villages Kaleshrivadi, Tukaramwadi, Mothe Bhal, Vitthalwadi, Lakhola, Borze, Narvel,
Benavale, Sarebhag and Vashi with length of 16.44 km and total benefited area of 1388 ha.
Population of 12544 people will be protected with the renovation of embankment. Major
occupation of people within the benefited area is agriculture, fishing and jobs. Total area
under the existing embankment is 243960 sq. m out of which 115958 sq. m is existing and
additional 128002 sq. m of land is required12. As per the survey there are total 627 project
affected people (private and Government) and 27 people whose properties (houses, ponds
& toilets) are getting affected. Other than this community property (community toilet, sheds,
jetties, road, solar lights, electricity poles, electricity line, crematorium etc) are also getting
affected. Measures are also taken to minimize impact on the community properties.
Alignment is straightened in the section between chainage 13230 and 3380 to protect a
12
As per the PAP List Prepared by KLDC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 64
school. Various structures and utilities are getting affected due to renovation of
embankment which will be shifted or reconstructed. Details of the land and facilities getting
affected is given in detail in section 3.7 and Annexure 3.2. Detail SIA is carried out for the
project to assess the impact of project on socio-economy. Detailed Socio-economy and
details of the land owner and land area affected due to the project area can be referred from
the SIA report. Brief of socio-economy of the district, tehsil and project area is given in
sections below.
4.7.1 Demography of District and Tehsil
For administrative purposes, The Raigad district is divided into 15 Talukas (Tahsils) namely
Alibag, Panvel, Karja, Pen, Roha, Mangaon, Mahad, Shrivardhan, Tala, Murud, Poladpur,
Khalapur, Sudhagad, Mhasala, Urant.
As per 2011 official census report, the population of the district is 26, 34,200 with sex ratio
of 959, which is higher than the state ratio of 929. The geographical area of Raigad district
is 7,152 sq km. The average literacy is 82.34% comprising male literacy of 89.13% and
female literacy of 76.92%. The schedule Caste (SC) and Schedule Tribe (ST) community
are considered as socially weak, hence the state and central governments have several
welfare schemes for their economic and social development. SC population of Raigad
District is 134952 out of which male are 67980 and female are 66972. ST population of
Raigad District is 305125 out of which male are 153657 and female are 151468.
Proposed embankment is located in the Pen Taluka of Raigad District. As per the Census
India 2011, Pen Taluka has 45,142 households, population of 1,95,454 of which 99,570 are
males and 95,884 are females. The population of children between age 0-6 is 21,884 which
is 11.2% of total population. The sex-ratio of Pen Taluka is around 963 compared to 929
which is average of Maharashtra state. The literacy rate of Pen Taluka is 69.18% out of
which 75.8% males are literate and 62.3% females are literate. The total area of Pen is
527.68 sq.km with population density of 370 per sq.km. Out of total population, 76.14% of
population lives in Urban area and 23.86% lives in Rural area. There are 2.28% Scheduled
Caste (SC) and 16.58% Scheduled Tribe (ST) of total population in Pen Taluka. Urban area
of the Pen Taluka is Pen Municipal Corporation.
The Pen Municipal Council has population of 37,852 of which 19,257 are males while
18,595 are females as per report released by Census India 2011. Population of Children
with age of 0-6 is 3910 which is 10.33% of total population of Pen (M Cl). In Pen Municipal
Council, Female Sex Ratio is of 966 against state average of 929. Moreover, Child Sex
Ratio in Pen is around 911 compared to Maharashtra state average of 894. Literacy rate of
Pen city is 91.40% higher than state average of 82.34%. In Pen, Male literacy is around
93.91% while female literacy rate is 88.82%.
Traditionally, Pen city was populated by Agri, Brahmins and merchant's community as it was
centre of culture, education and trade. But now, city of Pen has become a beautiful
amalgam of diverse castes and religions, co-existing peacefully, side by side. Project site
falls in rural area of the Pen Taluka. Details of socio-economy of project area is given in
section below
4.7.2 Demography of Project Area
Population of the project area is given below in Table 4.8 and Table 4.9. Entire project area
is urban area with total population of 1225 out of which male are 587 and female are 638
with sex ratio of.1086.8 which is higher than state ratio of 929.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 65
Table 4.8 : Population of Project Area
Village No. of Household
Population Total Male Female SC ST
Mothe Bhal 218 923 462 461 0 0 Vitthalwadi 228 1085 561 524 0 0 Kanhoba 149 493 222 271 0 6 Kaleshriwadi 231 939 465 474 0 4 Lakhola 100 453 225 228 3 0 Benavale 120 494 243 251 0 0 Bahiramwatak 88 368 184 184 0 4 Narvel 166 664 322 342 0 0 Wadhav 382 1660 846 814 4 6 Div 303 1294 655 639 6 0 Borze 321 1377 699 678 0 0 Washi 661 2671 1333 1338 17 31 Total 2967 12421 6217 6204 30 51
Source: Census Data dated 2011
Table 4.9 : Socio Economic Profile of Project Area
Sr No
Particular Numbers Remark
1 Demography of the Project Area.
1388 ha All 14 village
2 SC/ ST population
81 Wahi – 41
3 Literacy Village HH
Total Population
Literate Male
Literate Female
Mothe Bhal 218 923 371 261
Vitthalwadi 228 1085 478 342
Kanhoba 149 493 160 154
Kaleshriwadi 231 939 367 270
Lakhola 100 453 199 163
Benavale 120 494 216 184
Bahiramwatak 88 368 143 114
Narvel 166 664 272 247
Wadhav 382 1660 688 541
Div 303 1294 545 458
Borze 321 1377 586 513
Washi 661 2671 1119 916
Total 2967 12421 5144 4163
4 Occupation/ Livelihood Pattern
Farming & Fisheries
5 Infrastructure Facilities
Village Facility at a Distance in Km from village
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 66
Pri
mary
S
ch
oo
l M
idd
le
Sc
ho
ol
Se
co
nd
ary
S
ch
oo
l H
igh
er
Se
co
nd
ary
Co
lle
ge
Ho
sp
ita
l
Dis
pe
ns
ary
PH
C
PH
SC
Po
st
Off
ice
Tele
ph
on
e
Co
nn
ec
t
Ba
nk
Cre
dit
S
ocie
ty
So
urc
e
of
Wate
r
Re
tail
Ma
rke
t
Wh
ole
sa
le
Dis
tric
t a
dm
inis
tT
ak
uk
a /
Blo
ck
Kaleshri, ,
0 3 3 3 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Mothe Bhal,
0 4 4 4 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Vithalwadi
0 3 3 3 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Narvel, 0 4 4 4 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Benavale, 0 4 4 4 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Bahiram Kotak,
0 5 5 5 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Vadhav, 0 4 4 4 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Div 0 2 2 2 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Vashi, 0 0 0 0 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Lakhole, -Kanhoba,
0 4 4 4 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Borje 0 4 4 4 10 10 8 8 8 4 4 4 4 3 10 10 45 10
Source: Census Data dated 2011
4.8. Archaeological Sites:
There no historical monument, archaeological site is present within the 1 km proximity of the
Narvel Benavale embankment.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 67
Chapter 5. Environmental Impacts and Mitigation Measures
5.1. Introduction
Environmental Impact Assessment helps in identifying the likely impacts due to the project
activities for all stages of the project viz, design, construction and operation stage. Impacts
are quantified using established practices, tools and mathematical models followed by
identification of mitigation measures to mitigate the impacts to acceptable levels.
The project “Renovation of Existing Narvel-Benavale Embankment” involves various activities, which may have impact on the environment. Impact analysis is carried out for all
the activities under project for physical, biological and socio-economic environment. Key
issues identified requiring greater attention are related to impact on mangroves, trees,
structures affected, land required, traffic management, land use, drainage (siltation of
drains), community and aesthetics, water, noise, and air quality. Impacts are identified and
evaluated for all the project activities during project implementation (construction) phase
and operation phase. Detailed impact assessment is given in sections below
5.2. Project Influence or Environmental Impact Area
Area, which will be impacted due to the project activities, is defined as project influence
area. Project influence area includes the area of direct impact zone, i.e. proposed RoW and
area within 1 km radius around the proposed embankment site.
For this study purpose, impacts anticipated are majorly during construction phase and
environmental parameters to be impacted are mangroves, trees, air quality, noise levels,
water quality, soil quality, hydrology and occupational health & safety. Apart from this there
are various structures and utilities located on the embankment which are getting affected.
Considering these parameters and type of impact, it is anticipated that the impact will are
locational and will not extend beyond the 1 km radius of the proposed project. Thus, project
influence area is considered as Proposed RoW area and area within 1 km radius of the
proposed alignment.
5.3. Identification of Project Activities and Associated Impacts
Project activities primarily involves clearing of grass and removal of rubbish, shifting of
utilities/structures (electrical poles, solar lights, houses, shed and huts, jetty, water bodies,
ottas, community toilets, crematorium, road, temple etc), cutting of trees, establishment of
construction & labour camp, stripping of embankment, material storage and transportation,
strengthening and raising height of the embankment, slope stabilisation, debris disposal,
reconstruction of CD works, construction of new CD work, construction of retaining structure
and dismantling of construction & labour camp. All these activities may have direct and
indirect impact on the physical, biological and social environmental components in the
project influence area. However, the impacts are majorly anticipated during the construction
phase. Impacts are identified for each of the project activity and the impact identification
table is given in the Table 5.1.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 68
Table 5.1 : Impact Identification Matrix
Physical Components Biological Components
Social Components
AQ NL SWQ GWQ SQ WR Drainage LU EB A&SE OHS TP&A Existing
Utilities
AM CP
Pre-Construction and Construction Stage
Clearing and Removal of Vegetation and Cutting of Trees from existing and proposed alignment route
√ √ √ × √ × √ √ √ √ √ √ × × ×
Shifting of the utilities (electrical poles, service electricity line, solar lights, houses, shed and huts, jetty, water bodies, ottas, community toilets and road)
√ √ × × × × × × × √ √ √ √ × ×
Shifting of the Community Property Resources, (crematorium and temple)
√ √ × × × × × × × √ √ √ × × √
Setting up construction camp and material storage areas
√ √ √ √ √ √ × √ √ √ √ √ × × ×
Sourcing, Transportation and Storage of earth for raw materials for the proposed project
√ √ √ × √ × × × √ √ √ √ × × ×
Project
Activity
Impacted
Environmental
Components
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 69
Sourcing Water for Construction and Labour
√ √ √ √ × × × × × × × √ × × ×
Renovation of embankment
√ √ √ √ √ √ √ √ √ √ √ √ √ × √
Demolition of old CD works and Construction of new CD works
√ √ √ √ √ √ √ √ √ √ √ √ √ × √
Debris disposal (management)
√ √ √ √ √ × √ √ √ √ √ √ × × ×
Dismantling of construction and labour camp
√ √ × × √ × × √ √ √ √ √ × × ×
Operation and Maintenance
Monitoring and Maintenance
× × × × × × × × √ × × √ × × ×
Remarks Increase in concentration of air pollutants like PM10, PM2.5, CO, SO2, NO2 due to emission from vehicle, machinery, equipment and DG sets
Increased noise level due to operation of vehicle, machinery, equipment and DG sets
Entering of
contaminated run-off from site
to Bhogwati river and
Amba River Water bodies such as ponds,
fish pond, wells, etc
are required
to be shifted
Need of Dewate
ring may be there during
embankment
construction
Contamination of soil
due to accidental spillage of
solid/hazardous
material, construction
material ,disposal of waste water
Water requirement for
construction
purpose and
drinking
Siltation of the
drainage
network
Some agriculture
area may be taken for
embankment construction
and temporary impact due to establishment
of labour & construction
camps
Cutting of 42 nos of trees and working in
close vicinity to
mangroves
Loss of visual
amenity due to constru
ction works being
carried out.
Aesthetics will
significantly
improve after
project implementation
Handling of
heavy machin
ery, working along the
roads etc are all risk activitie
s
Traffic congestion and traffic
diversion due to
material transport
ation and
construction
works
Shifting of the utilities (electric
al poles, solar lights,
houses, shed and huts, jetty, water
bodies, ottas,
community
toilets, road)
No impact found
Access to houses,
Crematorium and temples
(Bahari Dev at chain age 13230 and Bap Dev
Temple at chain age 13770 to 13800)
present on embankment
will be affected
AQ-Air quality, NL-Noise Level, SWQ-Surface water quality, GWQ-Ground water quality, SQ-Soil quality, WR-Water Resources, OHS Occupational health& safety, LU-Land use, EB-Ecology & Bio-doversity,TP&A-Traffic Pattern and Accessibility, AM-Archaeological monuments, CP-Cultural Properties, A&SE-Aesthetics and Socio-economy
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 70
5.4. Impact Assessment and Evaluation
Identification of project activities (project implementation and operation phase) and environmental components, which may be impacted due to project activities, is carried out and is given in Table 5.2. Significance of impact on each of the identified environmental component for all the activities is assessed and is given in the sections below. Thereafter, cost-effective but appropriate mitigation measures are proposed to eliminate or minimise the identified impacts. An EMP has been designed to ensure the effective implementation of proposed mitigation measures (refer chapter 8). Impact assessment and evaluation along with the mitigation measures is given in sections below.
5.5. Impacts during pre-construction and construction Phase
5.5.1 Impact Due to Shifting of Utilities
Utilities to be shifted include
• 10 nos of electricity poles and service line which should be relocated at
appropriate location without affecting the final alignment and adjoining farms
along with their ROWs,
• Five no’s Solar lights should be relocated prior renovation of embankment to the suitable location without affecting the final alignment and adjoining farms along with their ROWs.
Disruption of these facilities will affect the community if dismantling is done prior
providing the alternative. Thus, measures should be taken to prevent the impact of
shifting the utilities on community. Measures proposed are listed below.
Mitigation Measures
• Ten electricity poles and service electricity line will be required to be shifted for
embankment strengthening and renovation. Location of electricity poles to be
shifted is attached as Annexure 3.2. Shifting of the poles should be carried out
through MSEDCL prior to start of work. Permission should be obtained from
MSEDCL and all conditions mentioned in permission letter should be followed.
• Permission shall be taken from the gram panchayat for shifting of 5 nos of solar
lights located on embankment.
• Shifting of the solar lights, service line and electricity poles should be done prior
to dismantling to avoid the disturbance to the community
• Costing for relocation/shifting is considered in the DPR for the service electricity
line, electricity poles and solar lights
• Necessary safety and protection work shall be undertaken by the contractor for shifting the electricity poles, electricity line and solar lights.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 71
5.5.2 Impact Due to Shifting of Community/Religious Resources/Properties and Access to Properties
Community Property Resources exists on the embankment which includes 4 nos of
crematorium, 8 nos of jetties, 4 no of community toilets, 5 nos of Ottas/fish drying
platforms, 3 nos of sheds, 2 nos of temples, 1 no of well and 1 no road. Detail of the
chainages of these properties/resources is given in Annexure 3.2.
Disruption of these facilities will affect the community if dismantling is done prior
providing the alternative. Thus, measures should be taken to prevent the impact of
shifting the utilities on community. Measures proposed are listed below.
Mitigation Measures
• A school is located at chainage 13230 m which is now proposed to be saved by straightening the embankment between chainage 13230 and 13380. 6 structures (3 houses, 1 jetty, 1 temple (Bahari) and 1 pond) will also be saved due to straightening of the embankment.
• Community and gram panchayat concurrence shall be obtained prior to demolition of the crematorium, jetties, community toilet, Otta/fish drying platforms, well, sheds, temple, well and road.
• Concurrence shall be taken from maritime board for shifting the jetties and all conditions prescribed in the letter shall be followed
• Location for crematorium, well, community toilet, temples, road and sheds construction shall be decided in consultation with the local people and gram panchayat
• Crematorium shall be constructed at the decided location prior dismantling
• Crematorium to be constructed should have proper and safe access and covered shed
• Alternatives should be provided for jetties, ottas, road (access to Vithalwadi village), access to school to the community in consultation with them during construction phase to minimize the social impact
• Cost of the reconstruction/shifting of the structures to be impacted is considered and is included in the DPR
• Cost for provision of alternate access and steel barricading in front of school shall be considered and included in DPR
• Necessary safety and protection work shall be undertaken by the contractor
• Additional safety measure like steel barricading shall be provided near the school to ensure safety of children
• Contractor shall ensure adequate signage and safety measure including installation of display, signage and diversion boards
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 72
5.5.3 Impact on Private land and Property
Additional private land will be required for renovation and strengthening of the
embankment. Land owners are willing to give off their land for the project and have also
signed the consent forms for giving off their land for free for the project construction as
development of embankment will protect their remaining land from saline water ingress
and infertility due to salinity. Kharland Department has carried out meeting with Patwari,
Sarpanch, land owners and other villagers and has discussed the issue in length. Land
owners have signed the paper of consent for voluntary contribution of land for proposed
project. Consents letter through voluntary donations are obtained by the Revenue Officer
(District administration) facilitated by Kharland Department. Thus, there are no impacts
due to land acquisition as people are willingly giving their land for the project.
There are 19 pakka houses on the embankment out of which 3 nos may be saved due to
straightening of the embankment between 13230 and 13380, thus 16 nos of pakka
house will be impacted. 24 nos of fish ponds, 11 kachha houses and 3 private toilets will
be affected due to renovation of embankment. It is thus required to consider these
impacts during project design and implementation and prepare mitigation plan to
minimize the social impacts of the project. Proposed mitigation measures are given
below
• Private land to be taken for the project shall be as per the consent given by the land owners. Contractor shall stop the work in case of any conflict with land owners and shall contact to Kharland Development Circle. Work shall be resumed only after resolution of the conflict
• Community is consulted and concurrence is obtained from community to demolish these private structures and pay off the cost for these structures
• List and location of these structures is given in Annexure 3.2 and no other structure mentioned in the list should be impacted
• Compensation should be provided to the private property owners as per the concurrence of the property owners and as defined in the SIA report (in line with R & R Act, 2013 and WB policy). Compensation should be given prior to demolishing the structures
• Alignment is proposed to be straighten between 13230 to 13380 so all the structures within this section should be protected
• Budget of compensation shall be included in the cost of the project as mentioned in the DPR
• No other structure shall be affected due to the proposed project.
• In case access to any of the private property/house/structure gets impacted then alternate access should be provided during construction phase. Alternate access arrangement shall be provided for Vithhal vadi village as the road to vithavadi will get impacted.
• Grievance readdress mechanism shall be provided at Kharland office so as community can lodge the complaint if any.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 73
• Information shall be given to the people about this grievance readdress mechanism through consultation and appropriate media.
5.5.4 Impact Due to Clearing of Vegetation and Cutting of Trees and Impact on Mangroves
Vegetation on the proposed alignment includes bushes, shrubs, herbs and trees. There
are 42 trees existing on the embankment which are required to be cut. These trees are
not listed in Maharashtra Tree Felling Act, 1964 but permission shall be taken from
District Collector as per NGT Order dated 8th Jan, 2016 – case no 11/2015 (WZ).
Mangroves exists all along the embankment on creek side and in patches on land side.
Details of the location of trees and mangroves is given in Table 4.5 & Table 4.6 and
Annexure 3.2. These mangroves and the trees other than the 42 nos which are in close
vicinity of proposed embankment alignment may get impacted due to renovation works.
Measures should be taken to minimize the impacts on the trees and mangroves and are
given below:
Mitigation Measures
• Contractor shall take approval of the concerned Engineer before site clearance
• Efforts shall be made to save these trees through design changes. It is proposed to straighten the embankment between 13230 and 13380 m which can save one tree from cutting located at chainage 13290 m on embankment
• A joint visit shall be conducted by the Kharland Development Circle (KLDC)
along with the environment expert of contractor to ascertain the tree saving and
requirement of tree cutting. If any change in design measure is suggested for
saving the tree then that should be updated in the EMP document by contractor
• If any trees need to be removed from proposed right way (42 no’s as estimated)
before commencement of work it shall be done by obtaining Permission from the
District Collector for cutting the trees as per NGT order
• Identified trees (as per joint visit of KLDC & contractor and tree cutting
permission) for cutting should be cut. Cut logs should be managed as per the
condition given in tree cutting permission
• No other flora should be harmed other than identified and marked vegetation and
trees
• Vegetation (bushes, weeds etc) at the site shall be removed in presence of
Environmental Expert of Contractor and Kharland Development Circle (KLDC)
• Scraped vegetation waste should be collected and should be disposed-off at the
debris disposal site
• Compensatory afforestation for every tree cut shall be panned in the ratio of 1:10.
Area for plantation shall be identified with the help of Forest Department and
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 74
Kharland Development Circle (KLDC) and SPIU shall be requested to transfer
the fund to Forest Department, based on the estimate from Forest Department.
• Stacking, transport and storage of wood shall be done as per prevailing norms of
the state forest department
• Mangroves are present all along the creek side of embankment and in patches
on the land side of the embankment. During the strengthening and repair
process, mangrove should not be disturbed. All mangroves shall be preserved.
• The existing boundary of the bund away from the mangrove area on the creek
side is considered as the edge of the proposed alignment. The proposed bund
will extend to the field side to accommodate for its increased width.
• Any additional land if required for strengthening of the embankment shall be
taken on creek side only if mangroves are not present else land on agriculture
field side should be considered with consent of land owners.
• No mangrove shall be disturbed or removed during dismantling & reconstruction
of CD works and Ring bund construction & dismantling. There are mangroves
existing on the land side of the embankment and along the channels within the
benefited area. These mangroves shall not be cut or removed. Flow of water to
these channels shall not be blocked
• No waste shall be dumped into the mangroves area, inside the creek and in the channels flowing in the benefited area
• Since embankment in buffer zone (50 m) of mangroves, No Objection Certificate
(NOC) from the Forest Department (Mangroves Cell) is obtained and contractor
should follow all the conditions of the NOC. NOC is attached Annexure 5.1.
• Contractor should study the strip map for mangroves presence. (Strip mapping is
prepared in August 2018 to show the presence of mangroves). This strip maps
shall be followed strictly for available bottom width and additional private land
required for embankment strengthening
• All caution shall be exercised to prevent any harm to mangroves
5.5.5 Impact Due to setting up of Construction Camp, material storage and debris disposal areas
Construction camp sites are established for development of storage yards, site office, staging of machinery and equipment and other activities. Impacts are anticipated due to location of the project. Establishment and operation at construction camps may lead to noise pollution, dust generation and generation of solid waste and may have impact if located close to residential area or environmental and social sensitive areas. Construction camp involves operation of various machinery and equipment, which may pose occupational health risks to construction workers. Storage and spillages of oils can contaminate the soil. Inadequate space for parking may also lead for vehicle idling and dust generation. There will be generation of sewage and run-off from site which should be managed to prevent generation of unhygienic conditions and sanitation issues.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 75
Uncontrolled disposal of debris and wastes may lead to dust generation, change in land use and impact the surrounding aesthetics. These issues are short term in nature and are restricted to construction period and construction camp site but may be significant if not managed. All the anticipated impacts are manageable with the proposed mitigation measures, which are given below:
Mitigation Measures
• Contractor shall identify the sites for setting up material storage area, construction camp, and if any plant established shall notify the Executive Engineer for their approval for the site.
• Any plant or construction camp site & construction material storage site shall be sited at a min. distance of 150 m from water body and 500 m from residential area or any sensitive location like school or hospital. Mobile units can be placed within 250 m distance of residential area also. These plants shall be located in downwind direction of any residential area.
• Available Government waste land (on land side only) along the embankment shall preferably be used for the establishment of these plant sites with the permission of concerned authority.
• If usage of this land is not possible then the private land which is currently not being cultivated within the benefited area can be used for the establishment of the plant site with the consent of the land owner.
• Site shall be marked on the map and the layout of such sites along with the photographs shall be submitted to KLDC prior to setting up any such facility to obtain prior approval
• These sites shall be fenced preferably with the sheets so as to minimize the exposure of the public to the dust
• Establishment and operation of these plants shall be initiated only after obtaining consent to establish and consent to operate from MPCB by contractor
• Contractor shall ensure all measures for dust control (like sprinkling of water) and prevention of water, soil (preventing flow of contaminated water from camp) and noise pollution shall be taken up.
• Speed limits at site shall be maintained between 15-20 km/hr
• Contractor shall ensure parking of vehicles or installation of machineries shall not block the access or block public utilities in the project area.
• 2 Bio-toilets (one for male and one for female) shall be provided at construction camp, storage areas and operational areas.
• The bio toilet must have provision of at least 1000 litres overhead water storage. It shall be well maintained and in usable condition at all the times. It shall be regularly cleaned, and overhead tank replenished as per requirement. Work force shall be oriented to use mobile toilets. No open urination/defecation shall be allowed.
• Drinking water facility shall be available for workers at site
• Loose construction material and waste storage area shall be paved and covered
• Oil shall be stored on concreted floor with spillages and leak collection pits
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 76
• Oil interceptor shall be provided in vehicle cleaning areas
• Contractor shall ensure all construction vehicle shall comply with traffic rules and carry PUC certificate.
• Contractor shall ensure First Aid Kits at the camp in case of any emergency.
• Contractor shall ensure provision of Fire extinguishers in the storage/ yard area
• Location of storage of each material shall be pre-identified and signage shall be provided for the same
• Provision of sprinklers for dust suppression shall be made
• Contractor shall ensure weekly inspection by Environment and Safety experts of the contractor to confirm fitness of these plants and following points shall be verified during their visit
o All plants are working in good working condition
o Dust pollution control measures are being taken up as per the consent orders
o Noise monitoring shall be taken up to ensure prevention of noise pollution
o Contractor shall ensure Workers safety by providing and encouraging use of PPEs
o Contractor shall ensure the maintenance of record including Log book of operation of the plants
• Contractor shall ensure after completion of the construction works these plant sites shall be restored back to the original condition.
• Contractor shall ensure all waste and machinery shall be removed from the site. Site shall be made clean and free from any temporary structure.
• Contractor shall ensure Renovation of the site as per the provision of the contract and by providing of a vegetation cover in form of grass and small herbs.
5.5.6 Impact Due to Setting up of Labour camps
Setting up of labour camp could have impact on air quality of area due to site clearance, establishment, burning of bio-mass and movement. In addition, there will be generation of sewage and waste from kitchen area, which can pollute the water quality and soil quality of area and may create unhygienic conditions. There will also be generation of municipal waste from the labour camps, which again requires proper management to prevent environmental pollution. There could also be impact on workers’ health if proper waste and sewage management facility and other basic facilities are not available for the workers. All these anticipated impacts are short term and localized, i.e. restricted to construction phase and labour camp site. These impacts may be significant if not managed properly. The propose mitigation measures are as follows:
Mitigation Measures
• Labour camp shall be established only if local labour is not available
• No workforce camps shall be set up at any of the operational areas. Each workforce is to be provided with suitable type of rented accommodation or in the labour camp established for the project. Transportation facility shall be provided to workers for commuting between construction camp and work place. Pooled
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 77
transportation facility shall be provided to workers who opt to stay at their residence.
• Labour camps shall not be established on agriculture land, vegetated and planted land area and shall be set up at least at a minimum distance of 250 m from water body. Approval shall be obtained from gram panchayat prior setting up such camp.
• The location, layout and basic facility provisions of the labour camp and photographs of the location will be submitted to KLDC for prior approval before establishing it. Contractor will comply with the relevant provisions of Building and other Construction Workers (Regulation of Employment and Conditions of Services) Act 1996.
• The contractor will provide and maintain well ventilated living accommodation and ancillary facilities for workers in functional and hygiene manner.
• Minimum Basic facility like fans, first aid, rest area, sanitation facility & dustbins, fire-safety measures, cooking area, bathing area and washing area shall be provided in the camps. Open urination/defecation shall be strictly prohibited. Two Mobile toilet with anaerobic digestion facility shall be provided by contractor. Contractor shall make arrangement with local municipal extractor for disposal of night soil.
• Provision of supplying clean and cool drinking water shall be made at labour camp, construction camp and work sits for workers. A mobile drinking water counter/kiosk with minimum 300 litter capacity and two taps with bottom tank to collect waste water will be made close to worksite (say within 100 m of site)
• Provision of LPG shall be made for cooking. Use of wood as fuel shall be fully prohibited. No open burning of bio-mass shall be allowed. Separate cooking area shall be designated if common mess is not provided.
• Once labour camp is discontinued then site shall be restored to original condition
• The domestic waste shall be segregated at site into recyclable and non-recyclable materials. Recyclable material shall be sold to recyclers and non-recyclable material shall be send for disposal through the local bodies
• The contractor shall take necessary HIV/AIDs prevention awareness measures will be taken at labour camps by the contractor including provision of contraceptives. Every quarter, HIV/AIDs awareness programme shall be organised by EHS officer of the contractor. Contractor will prohibit contractor for use of any explosive, destruction of trees or disposing of waste to any water bodies or nearby open lands. Contractor will be responsible for the action of his employees.
• Inspection shall be carried out by the environmental expert of the contractor and executive engineer KLDC once a quarter to ensure availability of minimum facilities at the camp and sanitation level at the camp. Status report shall form part of quarterly report from KLDC to SPIU.
• Daily attendance shall be taken at worker camp by contractor.
• A crèche facility shall be provided for the children of worker if the female and male contracted labour are more than 50.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 78
5.5.7 Impact Due to Waste Generation and Setting up Debris Disposal Site
Waste to be generated due to the project includes demolition waste, construction debris, municipal waste from labour camp, used oil from machinery & equipment and excavated muck from stripping. It is estimated that 365.9 cum of waste will be generated due to dismantling of CD works and 40105.69 cum of muck will be generated from stripping. This waste if not treated may have significant impact on the environment thus it is required to be manged. A site is to be identified and established for disposal of these debris and wastes. Setting up of this site shall also have impact on the land use and soil quality of the area. Following measures are proposed for management of the waste.
Mitigation Measures
• Construction and demolition waste shall be managed as per C&D Waste Rules, 2016, municipal waste should be managed as per the Solid Waste Management Rules, 2016 and hazardous waste should be managed as per the Hazardous and Other Waste Management Rules, 2016
• A site must be identified by the contractor prior start of construction for disposal of the above-mentioned waste material. This site should be located minimum 50 m distance from water body and 250 m from a residential area. This site should be selected only at land side of embankment
• Muck generated from stripping shall be used for construction of the ring bunds
after obtaining consent from the KLDC engineer. Thus, clearance of vegetation
followed by stripping of the soil should be the first activity to be carried out for the
proposed project
• The site should be approved by the executive engineer of KLDC
• Contractor should submit the location, area and photographs of the proposed site to the KLDC at least 15 days in advance for their acceptance of the site.
• Record of debris generated and transported should be maintained by contractor
• All the waste shall be segregated into recyclable and non-recyclable waste. Recyclable waste should be sold to authorized vendors and non-recyclable waste should be disposed off through local agencies in the area
• Compostable fraction of the municipal waste to be generated from the labour camps should be pit composted if possible
• Hazardous waste should be stored in isolated location in HDPE container only and should be disposed off through authorized vendors. NOC should be obtained for disposal of hazardous waste from MPCB.
5.5.8 Impact Due to Construction Material Sourcing and Establishment of Borrow Areas
All the materials will be sourced from local area, i.e. within 35 km radius from the project site. Sourcing of materials from local areas will ensure minimal emissions during transportation. No new borrow area or quarry will be established. Material will be sourced from the licensed quarries/borrow areas and authorized suppliers. Construction material if sourced from unauthorised sourced may lead to illegal mining or other activities.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 79
Storage area for material is expected to be located close to project area. The location of store preferably is recommended not to be more than 2 km distance from embankment site. Material if stored in open may generate the dust which may add to the dust concentration in the air so measures are required to prevent the impact on air quality. Impacts due to sourcing and storage of material are short term but significant if proper measures are not taken up during the pre-construction and construction stage. Measures are proposed to mitigate the impacts and they are listed below.
Mitigation Measures
Measures for Sourcing of Earth
• Existing earth from the embankment shall be used to maximum and only
additional earth required should be sourced from external source.
• The project requires approx. (406558.8 cum for hearting + 91829.48 cum for casing) for embankment. Earth shall be obtained from the approved quarries of KLDC
• KLDC shall ensure the proposed borrow areas (if any) have permission from the appropriate authority including Environmental Clearance (DEIAA/ SEIAA).
• KLDC had identified a tentative borrow areas at a distance of 20 km i.e. in village Pen, Gram Panchayat, Pen Taluk and District Raigad which shall be used
• Contractor shall get approval of KLDC prior to opening and closure of every borrow area. KLDC and TPQA shall approve the borrow pits in accordance to the IRC recommended practice for borrow pits (IRC 10: 1961)
• Contractor shall develop borrow area plan indicating the location and area of the identified borrow area along with the consent order of land owner, photographs of the area and geographical coordinates of the corners of the borrow areas
• Finalization of borrow areas for earth and all logistic arrangements as well as compliance to environmental requirements, as applicable shall be the sole responsibility of the Contractor.
Selection Criteria of Borrow areas is as follows:
• Contractor shall identify the potential borrow areas and take permission from Executive Engineer before operating any borrow areas.
• The Contractor shall not start borrowing earth from selected borrow area until the mutual agreement is signed between landowner and Contractor. Copy of the document shall be submitted to Executive Engineer.
• The Contractor in addition to the established practices, rules and regulation will also consider following criteria before finalizing the locations.
o The borrow area should not be located in agriculture field unless
unavoidable i.e. barren land is not available.
o The borrow pits should not be located along the roads.
o The loss of productive and agricultural land should be minimum.
o The loss of vegetation is almost nil or minimum.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 80
o Sufficient quality of soil is available.
o The Contractor will ensure the availability of suitable earth. The Contractor
shall obtain representative samples from each of the identified borrow
areas and have these tested at the site laboratory following a testing
programme as approved by the concerned Engineer. It shall be ensured
that the fill material compacted to the required density.
o Planning of haulage roads for accessing borrows areas shall be
undertaken during this stage. The haulage roads shall be routed to avoid
agricultural areas as well as forest areas as far as possible and shall use
the existing village roads wherever possible.
• Contractor shall not be permitted to borrow areas in forest areas
• Contractor shall identify location of borrow areas and get approval from E.E staff.
• Earth material should be taken from barren land or selected borrow area during lean period as per IS Code 1498 after taking approval from Executive Engineer.
• Borrow areas should be dug as per IS code: 4701 and prior approval from the competent authorities must be taken before execution and mutual agreement with the land owners should be taken by the contractor and ensure the borrow areas should not have any environmental issues like water logging etc.
• Borrow pits should be drained to avoid stagnation of water and the bottom should be levelled properly / bottom level of borrow pits should be fixed with reference to the prevailing ground slope towards the nearest natural drainage course.
• Borrow areas should be avoided in agricultural areas
• Required permission should be obtained from the authorized person as stipulated in the Maharashtra State minor minerals act and if operating in private lands mutual agreement and no objection certificate need to be produced to E.E by the contractor.
• No borrow pits shall be dug within 5m of the toe of the embankment, if the depth of the borrow pit is less than 0.5m it shall be after 5m of the toe of the embankment and if the pit depth shall be more than 0.5m it shall be 10m of the toe of the embankment or within such a distance from the toe of the bank where a 4:1 hydraulic gradient line cuts the ground surface, which ever more.
• Borrow pits shall be drained to avoid stagnation of water and the bottom should be levelled properly / bottom level of borrow pits should be fixed with reference to the prevailing ground slope towards the nearest natural drain based on the site conditions
• Borrow areas shall be preferably outside CRZ areas
• Precautions to be taken up if Private Lands are used:
• If waste land is not available then soil from the agriculture fields can be taken with the consent of the land owners.
• An agreement shall be formed with land owner indicating the area to be borrowed, the quantity of earth to be excavated, time for borrowing, restoration
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 81
works and the cost to be paid to land owner in local language. Borrow areas shall not be constructed near the road side.
• Along with the consents, the Contractor shall apply to appropriate authority including obtaining Environmental Clearance from DEIAA/ SEIAA through KLDC
• Contractor shall ensure that borrow area shall be planned so as to minimize the vegetation loss, no tree cutting is required and shall not be located close to roads (up to 50 m).
General Conditions to be followed
• Haulage of material to the areas of fill shall proceed only when sufficient spreading and compaction plants are operating at the place of deposition
• Top soil from the borrow area shall be removed up to depth of 15 cm and shall be preserved under covered condition. This soil shall be spread on the borrow area during closure. A 15 cm topsoil will be stripped off from the borrow pit and this will be stored in stockpiles in a designated area for height not exceeding 2m and side slopes not steeper than 1:2 (Vertical: Horizontal).
• Restoration of the Borrow pits shall be done as per the EC conditions and in case of private lands it shall be as per willing of the land owner i.e. conversion to aquaculture farms/ farm ponds etc as per the site conditions.
• Contractor shall keep records of all the borrow earth and TPQA shall check and verify all the sources and approvals time to time and if any issues arises it shall be brought to the notice of SPIU
• The Contractor will keep record of photographs of various stages i.e. before using materials form the location (pre-project), for the period borrowing activities (Construction Phase) and after Renovation (post development), to ascertain the pre and post borrowing status of the area.
Measures for Sourcing of Other Construction Material
• Other material required are aggregates, cement, sand, steel and geotextile.
(Rubble: 46312.35 cum; Cement: 3224.93 cum, Steel: 108 MT and Sand:
11885.89 cum)
• Contractor shall ensure all materials used in construction of embankment shall
be purchased from approved quarry suggested by KLDC. No other sources are
permitted. Quarries/suppliers identified by KLDC are Mapgaon at 35 km for
rubble, cement & steel from Pen at 20 km and sand from Dharmtar at approx 25
km
• A joint visit may be made by environmental expert of the contractor, Executive Engineer KLDC to verify the quality and suitability of material, environmental approvals and environment management measures at the quarry site
• The Contractor shall finalize the quarry for procurement of construction materials after assessment of the availability of sufficient materials, quality and other logistic arrangements.
• A preliminary survey has been carried out by the Executive Engineer and identified the quarry and is provided in DPR
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 82
• If extraction shall be done, prioritize sites already permitted by the Mining or concerned department,
• Contractor shall purchase materials and finalize vendors who have valid permissions.
• If other sites are necessary and the contractor want to use, let the contractor obtain necessary permission from the concerned regulatory authority and inform Executive Engineer.
• Contractor shall ensure use of potable water for every construction activity. Contractor shall provide necessary approval regarding water supplying agency.
5.5.9 Impact Due to Transportation of Construction Material and Debris
Transportation of material may generate dust and other vehicular emissions (SO2, NO2 and CO) leading to air pollution. There will be increased vehicular movement on roads due to transportation of material which may lead to traffic congestion and increased risk of accidents. However, all the materials will be sourced from local area, i.e. within 35 km radius from the project site. Sourcing of materials from local areas will ensure minimal emissions during transportation. Impacts due to transportation and storage of material mare short term but are manageable if suitable mitigation measures are taken up. Construction material if sourced from unauthorised sourced may lead to illegal mining or other activities. Mitigation Measures
• Material transportation shall be carried out in covered vehicles only
• Transportation vehicles shall have valid PUC certificate
• Transportation vehicle shall strictly follow the speed limits designated for the roads and speed shall be limited to 10 kmph at the site
• Transportation vehicle shall be properly serviced and maintained
• Transportation vehicle shall no way block the villager’s access.
• Contractor will ensure that all construction vehicle use only the designate haulage road and no shall drift to agriculture field and affect the standing crops.
• Bamboo shall be used for haulage road boundary marking.
• Haulage road shall be restored to original condition and returned to farmer after construction work is over.
5.5.10 Impacts Due to Hiring of Labour
Labour will be required to hire for construction phase. This will render positive impact on community, as jobs will be generated for local people. This will improve the quality of life of people. Further, if labour is hired from outside then there is influx of people in the area though temporarily, but this additional population have its impact on the community. Thus, following measures shall be taken to prevent impact and the measures are given below Mitigation Measures
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 83
• Contractor shall employ local people preferably for carrying out the construction works of embankment
• If the local labour is not available then contractor shall obtain a letter from the panchayat officials in this regard and then only can hire labour from outside
• No child labour shall be allowed at the site
5.5.11 Impact due to Operation and Management of the construction vehicle and machinery
During operation and management of machinery and equipment used during construction phase generate gaseous emissions, increase of noise level, leakage of oil and grease, generation of waste water from cleaning which may have impact on surface water body located nearby, air, soil and noise quality, impact on aesthetics, construction workers and the residents located nearby. These measures are short term but may be significant if proper mitigation measures are not taken up. These impacts can be managed with the mitigation measures, which are proposed below. Mitigation Measures
• All the construction vehicles and machinery shall meet the prescribed exhaust standards (Bharat stage emission standards)
• Machinery to be installed close to the creek/nallah, i.e. for construction of CD works shall be checked for oil and grease leakage
• Weekly inspection shall be carried out by Environment and Safety expert of contractor to confirm fitness of these vehicle and machinery and following points shall be verified during the visit
o PUC certificates of wheel or chain mounted machinery/vehicle
o All vehicle and machinery are clean and properly serviced and maintained. Cleaning water shall flow over to waste water collection tank after passing through oil interceptor.
• A log book will be maintained documenting all fuelling and maintenance events (date, time, location, condition of site, weather conditions, amount of fuel on maintenance event, issues
5.5.12 Impact on Drainage due to Siltation during Renovation of Embankment and Reconstruction of Cross Drainage works
There are likely chances of falling of sand/earth from slope and embankment to the creek which are flowing along the embankment leading to siltation of the drains and the creek. Also, during construction, banks of the embankment may get eroded due to wave action which will increase siltation of the creek and loss of the soil from the embankment. There are existing 7 CD works which will be reconstructed and one additional CD work is proposed to be constructed for draining the benefited area. During dismantling and construction of CD works there are likely chances of flowing of the saline water from creek to land side which will make the soil and the drains inside the benefited area saline. Thus, measures should be taken to prevent the flow of saline water to landward
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 84
side. The impacts anticipated are short term, temporary but significant if proper mitigation measures are not adopted. Proposed mitigation measures are given below. Mitigation Measures:
• Existing 7 nos of CD work shall be reconstructed and additional 1 no of CD work will be constructed to ensure proper drainage across the embankment
• Arrangement shall be made for prevention of flow of creek water to agriculture field during construction of CD works (8 no’s). A ring bund is proposed to be constructed to prevent the flow of saline water to the field side
• CD work construction shall not be undertaken during monsoon. Ring bund in any
case should be dismantled prior onset of monsoon even if construction of CD
work is not completed. New ring bund shall be constructed after offset of
monsoon prior resuming construction of CD works
• A silt fence (geo textile sheets with bamboos13) shall be provided along the active construction area or say 1 km, at the base of the embankment on creek side and around the stockpiles prior to start of construction works. The fencing shall be retained till the embankment up-gradation for activity area is completed and slopes are stabilized
• Contractor shall not dispose or allow disposal/spillage of earth or any other construction material or debris into the creek/nallah
• All loose construction material shall be stored on the paved surface and in covered condition
• Longitudinal drains shall be provided for flowing the water from top of embankment to the bottom to prevent the erosion of embankment
• Gabion wall is proposed to be provided at sections which are weak and are likely
to get impacted due to heavy/sharp water flow
• Provision for drain shall be made at the toe end of embankment to drain out the accumulated water to nearest cross drainage structure.
13
Steps of installation of silt fence (Indicative Method): A: Dig the trench line (6 inch deep and 4 inch wide approx) along the starting line of proposed embankment B.Install bamboo supports at space of 1-1.5 m and bury these bamboos to teh depth of 15 cm into the ground. Height of the silt fence should atleast be equal to height of existing embankment C. Geo-textile fabric then should be placed on the bamboo supports with the help of staple guns with heavy duty staples. Put minimum 3 staples D. Back-fill the trenches back with the excavated soil. Put all the surplus soil on the filled trench as the filled spoil in trench will further subside with time. Compact the filled soil properly.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 85
• The Contractor will ensure that construction debris, waste and construction material shall not be disposed or allowed to get spilled to creek or drainage channel so as not to block the flow of water of any watercourse/cross drainage channels.
5.5.13 Impact on Slope Due to Embankment Renovation Works
Height of the embankment will be increased and also the existing embankment will be
compacted. Free board of 1.5 m is kept above the HFL. There may be disturbance to the
slope or slope destabilization during renovation works. Due to this embankment may
slide. Also, if proper pitching is not provided then there are chances that embankment
may get eroded by wave action. Thus, the slope of the embankment shall properly be
stabilized. Measures are required to be taken for stabilizing the slope and are given
below
Mitigation Measures
• The embankment slope shall be stabilized and protected using appropriate
stabilization methods. Stone pitching is proposed to be provided for slope
stabilization on both creek side and land side. Stone pitching is preferred over other
like bamboo splits on creek side due to exposure to saline water. Stone pitching
should be provided as this is the most suitable option and have long life as compared
to other available options
• Embankment shall properly be compacted using the machinery as specified in DPR
• Grass turfing shall be provided on landward side only above the stone pitching area
as per DPR.
• Embankment shall properly be compacted using the machinery as specified in DPR
• Protection wall (stone gabion wall) is proposed to be provided in the areas where
water flow is heavy to prevent impact on embankment and breaching of embankment
• Rock toe will be provided at start and end of CD works to provide stability
• Groynes shall be provided at curve points of the embankment to prevent scouring of
embankment due to the wave action
• Geo-textile is also proposed to be laid on the slopes prior murrum and pitching to
prevent the breach of embankment due to heavy rain and water ingress into the
embankment due to heavy waves
5.5.14 Impact on Water Resources
Water will be required for construction activities like excavation works, reconstruction of
cross drainage works, construction of approach roads, RCC work, water sprinkling and
meeting domestic water requirement of workers. App. 50 labour will be required for
implementation of project. Thus, water requirement for domestic purpose can be app. 6
KLD. This water will be sourced from authorized private water tanker suppliers.
However, the water resources will be impacted only during project implementation
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 86
phase. Water requirement can be minimized by taking water conservation measures to
some extent. Mitigation measures are suggested and are given below.
Mitigation Measures
• Contractor shall ensure use of potable water for every construction activity.
Contractor shall provide necessary approval regarding water-supplying agency.
• Water shall be purchased from authorized private water tanker suppliers
• Contractor shall obtain and submit copy of approval of tanker water supplier to KLDC before start of supply.
• Water tanks and pipelines shall be checked for leakage on daily basis and any leakage if detected shall be repaired immediately
• Idle flow of water and taps shall not be allowed and supervisors at site shall do random inspection for the same on daily basis
• Workers shall be educated about importance of water conservation and things they have to follow for conserving water. Posters shall be displayed at each water source for water conservation and preventing wastage
• Run-off from the site collected in sedimentation tanks shall be used at the site for water sprinkling. Run-off from curing area also shall be collected and shall be used for sprinkling, wheel washing etc.
• Flow of water sprinklers shall be maintained so as the water is sprinkled as small dots so as consumption is less, and water pounding will be prevented
• Curing shall be done by spraying only to minimize water requirement. Curing shall be done in early morning and late evening hours to minimize evaporation loses. Cured structures can be covered with gunny bags so as to minimize the evaporation
5.5.15 Impact on Water Quality
During strengthening and renovation work of Embankment, CD works and approach
road, and dismantling of few structures leads to destabilization of embankment slope,
soil erosion and generation of debris which may contaminate the creek flowing along the
embankment. In addition, surface water may get contaminated due to generation of
construction waste and wastewater, mixing of sewage from labour camps and toilets and
spillage of lubricants and fuel at plant/construction site. This waste should be collected,
stored & disposed off properly on daily basis to prevent contamination of the surface run-
off with this waste.
However, all the above impacts are anticipated to be short term and temporary and of
low significance which can be managed by proper mitigation measures.
Mitigation Measures:
• Construction debris shall be collected from the site and shall be stored on the paved
surface under covered condition
• No construction debris shall be disposed or allowed to be spilled in the water body
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 87
• Construction debris shall be transported to the debris disposal site on regular basis
• All loose construction material shall be stored on the paved surface and in covered
condition
• Wastewater from the batching plant if established shall be collected in the tank.
Supernatant water shall be re-used in batching plant or can be used for dust
suppression. Slurry settled below can be reused in batching plant
• Vehicle service and washing shall be avoided at the construction site. If vehicle
washing if required than washing effluent at construction camps shall pass through
grease tap to collection tank. This water shall be used for dust separation.
• Monitoring of the creek water shall be carried out every Quarterly from accredited
laboratory
• Wastewater generated from toilets, washing area and kitchen area in labour camp
and toilets at construction site shall not be discharged into the creek/nallahs
• Bio-toilets shall be installed at the labour camp site and construction site area.
Sewage generated will be treated within the bio-toilets
• Water from bathing and kitchen area shall be passed through the oil and grease
chamber and shall be stored in the septic tank (soak pit is not feasible at this site due
to high water table level). This septic tank shall be a concrete tank and shall be
evacuated when filled.
• Oil and lubricants shall be stored on paved surface in covered containers with oil
collection pit on one end.
• Oils shall not be stored close to creek or any drainage channel.
5.5.16 Impact on Top Layer of Soil and Soil Quality
Areas will be required temporarily for setting up labour camp, construction camp, storage
areas, debris disposal site and setting up of borrow areas and permanently for
construction of embankment as per proposed alignment (proposed additional land of
9.9079 ha). Top layer of the soil in these areas if not preserved will get wasted and will
lead to loss of important resource. Thus, measures shall be taken to prevent loss of top
soil.
Soil quality will get impacted due to contamination of soil with the construction materials,
debris and oil. Soil from the slopes of the embankment may also get washed away due
to wave action during the construction & operation phase. Thus, measures shall be
taken to prevent impact on the soil quality and soil erosion.
Mitigation Measures:
• Embankment is constructed by layering various grades of soil so top layer of existing
embankment soil may not be fertile and may also be bit saline so may not be used
for plantation later so this shall be disposed off to the debris disposal site
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 88
• Top soil to be preserved will include top soil from the sites to eb used as construction
camps, labour camps, debris disposal site & borrow areas (if any)
• Before beginning the construction of embankments, the surface area of ground
additionally to be occupied (on field side) shall be cleared of all roots and vegetable
matter and stripped to a suitable depth as per IS: 4701 - 1982
• (i)Depth of stripping 5.0 to 7.5 cm for soil containing light grass cover
• (ii) Depth up to bottom of ploughed zone usually 15.0 to 22.5 cm in agricultural land.
• Top soil shall be preserved and reused in turfing activities if possible, in borrow areas
(if any), bunds or if excess shall be distributed to farmers for using in the agricultural
lands
• Project activities shall be carried out during lean period and non- monsoon period for
minimizing loss.
• Top soil shall be stockpiled at the site and shall be kept covered with tarpaulin cover.
Stockpile will be designed such that the slope does not exceed 1:2 (vertical to
horizontal), and height of the pile is restricted to 2m. All loose construction material
shall be stored and transported in covered condition on paved surface
• Oil shall be stored on paved surface only and a storage area shall have containment
for collection of spilled oil. Oil spill kits shall be available to manage the oil spill.
• All transportation vehicle shall be provided with the drip pans to prevent soil
contamination with the oil
• Silt fencing shall be provided to prevent washing away of the embankment and
entering of soil from embankment to creek during construction phase
• Stone pitching shall be provided on both the sides of embankment to prevent erosion
of the embankment
• Longitudinal drains and drains near the toe shall be provided to drain the water from
embankment and prevent washing off of the embankment.
5.5.17 Impact on Air Quality
Construction works, operation of machinery, material storage and transportation, waste
handling, demolition of CD works etc are the activities which may lead to generation of
dust and other emissions like SO2, NO2 and CO. This may impact the air quality of the
area. Impact on air quality will be short term but significant, if not managed properly.
Thus, mitigation measures are proposed to manage the impact and the measures are
given below.
Mitigation Measures:
• Water shall be sprinkled on embankment site, construction camp site and on haulage roads for dust suppression
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 89
• All the construction vehicle and machinery shall be compliant to the emission standards as per Bharat Stage Emission Standards
• All construction vehicle/machinery shall have valid PUC certificate
• All construction vehicle/machinery shall be regularly serviced and maintained and the records of the same shall be maintained at the site by contractor
• Low Sulphur fuel shall be used for DG sets
• Stacks based as per the formula (height of the stake 2 √kVA above DG set if kept in open otherwise above the building height if kept inside a room) shall be provided with DG sets
• Ambient air quality shall be carried out during construction phase every quarter from accredited laboratory.
5.5.18 Impact on Noise Level
Noise generation source during project implementation will be movement & operation of
machinery & equipment, movement of vehicles, site clearance, excavation activity,
construction activities etc. Machinery which may be involved for project implementation
are bull dozer, dumpers, back hoes, loaders, excavators, crane, transit concrete mixers,
batching plant etc.
Noise levels generated due to construction machinery during construction phase is given
in Table 5.2.
Table 5.2 : Noise Levels During Various Construction Phase and from
Construction Machinery
Construction Equipment for Different Activities
Noise Level in dB(A)
Bulldozer 80 Excavators 80-90 Front end loader 72-84 Dump Truck 83-90 Crane with ball 75-87 Scraper 80-90 Grader 80-90 Roller 73-75 Crane 75-77 Welding generator 71-82 Concrete mixer 74-88 Concrete pump 81-84 Concrete vibrator 76 Air compressor 74-87 Paver 86-88 Truck 83-90 Tamper 74-77 Backhoe 72-93
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 90
Source: Bolt, Beranek and Newman, Inc, “Noise from construction equipment and operations building equipment, and home appliances, “USEPA, Washington, DC, 1971
It is evident from the above table that operation of construction machinery & equipment will generate high noise levels due to which it may affect the health of labour and nearby residents/working population if the adequate mitigation measures are not taken. Highest noise level during construction phase may reach up to 90 dB(A). Impact due to noise level will be significant especially during night-time if no measures are taken to reduce the noise levels. Measures are proposed to minimize the impacts and are given below. Mitigation Measures:
• All machinery, equipment and machinery shall comply with the noise standards as specified by CPCB
• All the machinery equipment shall have inbuilt noise controlling mechanism such as silencers and mufflers
• All the machinery, equipment and vehicles shall be regularly serviced and maintained
• Construction activities shall only be carried out during the day time (6:00 AM to 10:00 PM)
• Honking shall be prohibited at site
• Noise monitoring shall be carried out during construction phase near residential
areas every month and quarterly through accredited firm and periodical checking of
equipment and machines shall be undertaken by the contractor on a day to day basis
5.5.19 Impact on Occupational Health & Safety of workers due to project activities
Construction activities involve risks to health & safety of construction workers as it involves handling of heavy construction machinery/vehicle/components & lifting equipment and working on heights. Dismantling of existing structures will also be manual thus will involve risks of operating machinery and lifting of heavy materials. Occupational risks involved during implementation phase are fall, slip, accidents, failure of crane, fire, electric shock etc. Safety measures are required to be taken up to prevent any injury or accident during the construction phase. Impacts anticipated during project implementation phase on occupational health and safety and community health, safety & security is short term and is restricted to construction period but may be significant if proper safety measures are not taken up. Impacts on these aspects are anticipated moderate and manageable with the adoption of safety measures. Measures are proposed to ensure occupational, health & safety of the workers and staff during project implementation phase and are listed below. Mitigation Measures:
a) Personal safety measures for labour and other staff at site
• All personal protective equipment shall be provided for construction worker which
includes safety shoes, safety jacket, helmet, earplugs, masks and goggles
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 91
• Barricading shall be provided for the embankment with LED lighting on top. All such
barricading and signage shall comply with IRS SP: 55 (2014) specifications.
• Steel barricading shall be provided on land side along the habitations abutting the
embankment, i.e. Vithalwadi village and near the school. Barricading may not be
required on land side other than this location. Bamboos fitted with geotextile which
are proposed to be provided as stilt fence will work as barricading on creek side in
active area
• The contractor will make sure that during the construction work all relevant
provisions of the Building and Other Construction Workers (regulation of employment
and conditions of services) Act, 1996 are adhered to. The Contractor will comply with
all the precautions as required for ensuring the safety of the workmen as per the
country' labour regulations and International Labour Organization (ILO) Convention
No-62 as far as those are applicable to this contract.
• All work force shall be subjected to an orientation program to familiarize them with
work requirements, safety practices at work, safe distances to keep from earth
moving equipment, emergency response etc. to be adopted to ensure their own
safety and that of other workers and public around operational areas.
• Visitors/officials to worksite are to be provided with PPEs (such as hard hats and
safety boots & safety jackets) and shall be briefed ongoing operations on that
specific time and related safety requirement at work site including safe distances to
keep, while at site visit.
• Contractor will ensure that each worker use the safety vests when on construction
site. He will also ensure availability and use of PPE and other measures specific to a
task as below:
• Hard hat or helmets for all workers, supervising staff and inspecting official/s entering
work site, plant area, and engaged in loading/unloading operations.
• Safety shoes and goggles for all workers employed for handling of cement, mortar,
concrete, asphalt or for those engaged in crusher operations.
• Protective eye gear, helmets, gum boots, hand gloves for all labour/workers at the
construction site.
• Welder’s protective eye-shields to workers who are engaged in welding works.
• Earplugs to all workers exposed to high noise levels.
• No smoking and other high-risk areas are to be provided with warning signage.
• Staff will be given induction training about the processes and risks involved during
the construction phase and the response plan to be followed during the case of
emergency.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 92
• Work force shall be subjected only to standard work shifts/hours. Overtime
allowances shall be paid with ceiling limits. Working beyond such ceiling limits shall
be discouraged, even if, so desired workforce or sub-contractor.
• Safety instruction/guidelines shall be displayed at all the sites in English and local
language
• Provision of Lifeguard and rescue boat shall be kept at site as the creek runs parallel
to the embankment and there may be accident of falling in the creek and drowning
• Construction work shall not be carried out during monsoon period
• Construction work shall be carried out during day time only
• Emergency assembly area shall be designated at the site and same shall be
informed to all the workers
• Workers shall be given training for safe operation of the construction vehicle and
equipment
• Defensive driving training shall be provided to drivers of construction vehicle
• Rest areas shall be provided for workers at the construction site. No worker shall be
allowed to rest in activity area.
• Construction machinery & equipment shall be in good conditions and shall comply
with all safety conditions
• All the lifting equipment/heavy machinery shall be properly examined and tested prior
usage. All relevant information shall be known by safety officer about the load,
method of slinging and attachment points. Heavy lifting machinery shall be managed
as per heavy lifting machinery management plan
• Gas cylinder if used for the welding works at the site then cylinders shall be kept
upright and shall be provided with flash back arrestor. Domestic LPG cylinders shall
not be used at site for welding and other works. Person operating the gas cylinder
shall be provided with PPE including gloves, goggles and helmet with the face
shields
• Fire safety measures including buckets filled with sand and fire extinguishers shall be
provided at the construction camp site, labour camp site and active construction work
area
b) Risk from electrical equipment
• No open or damaged electrical wires shall be present at the site. Electrical cables
shall be run in extra plastic conduits
• Install Earth Leakage Circuit Breakers (ELCB) in all circuits to protect the operators
from electrical hazards
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 93
• Keep the main switch box in good condition, protected from the weather. Install an
appropriately sized ELCB
• Provide good earth or ground connection for all installations
• Adequate lighting shall be provided for illumination at site
c) First aid
• First aid-trained personnel shall be available at site. Tie up with the nearby hospital
shall be made so as emergency can be handled. First aid facilities shall be
developed as per the Schedule V of BOCWR (Building & Other Construction
Workers Rules)
• A first aid kit shall be provided at the construction and labour camp site
• A motorized four-wheeler shall be available at the site to take the injured or sick
person to the nearby hospital
• Hospitals near to the site shall be identified and tie-ups shall be made with hospitals
• Presence of snakes is confirmed by local people in the area. First aid kit also shall
carry the bandages and tourniquet for managing the snake bite. First aider shall be
trained in using the tourniquet. Anti-venoms can be purchased and kept with the
hospitals identified so as they can be used in case of emergency.
d) Signages and hoardings
• Effective Safety caution and signage boards shall be placed at active site in English
and local language
• An information board detailing the name of project, length of embankment, duration
of work, risks involved and contact persons and Grievance Redress Mechanism
(GRM) shall be provided at both the ends of the embankment and in KLDC office.
5.5.20 Impact due to Contractor Demobilization
Demobilization of contractors involves activities such as clean up and restoration works;
disposal of waste generation from camp site, plant site and construction site; removal of
machinery, equipment and vehicles; dismantling of labour hutments and construction
material storage site and septic tanks if any; restoration and Renovation at site. These
activities may generate air emission, noise pollution, contamination of soil and surface
water body. These impacts are low and are confined to the project area and activity
period only. Thus, the impacts can be classified as the short term, temporary and of low
significance.
Mitigation Measures:
• At the time of completion of construction, contractor shall submit demobilization plan
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 94
• Clean up and restoration works shall be taken up by the contractor immediately after
completion of construction
• All the machinery, equipment and vehicle shall be removed from the site
• All the waste from the camp site, plant site and construction site shall be removed
and disposed as per the debris management plan given in this table
• All the temporary structures like the labour hutment, material storage sheds, rest
areas, fencing etc shall be dismantled and the material shall be removed from the
site
• Sites shall be restored back to the original condition and shall be handed over to the
land owner
• A satisfactory statement shall be obtained from the land owner by contractor and
shall be submitted to KLDC
• Septic tanks if any developed shall be dismantled and the pits shall be refilled
• Approval shall be obtained from KLDC for effective restoration of the site and
completion of demobilization activities.
5.6. Impacts during Operation phase
Project is not likely to cause any impact on environment during operation phase.
However, integrity of the Embankment, stability of slope and pitching, condition of CD
works and the drains and proposed compensatory afforestation need to be monitored
and maintained at the site. Mitigation measures proposed are:
Mitigation Measures:
• KLDC should monitor and maintain the integrity of embankment, stability of slope
and pitching, condition of the CD works and condition of the drains
• KLDC should also monitor the compensatory afforestation carried out in lieu of the
tree cut and ensure survivability rate of at least 70%.
5.7. Summary Outcome
Major impacts anticipated are due to tree cutting, working in close vicinity to mangrove,
soil erosion, high noise level generation, generation of air emissions, operation of heavy
machinery, impact on private land and property, impact on community property etc. The
impacts are of low to high significance but are majorly short term, temporary and
mitigable with appropriate mitigation measures
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 95
CHAPTER 6. Alternative Analysis
6.1. Introduction
Analysis of alternatives is carried out for the proposed Renovation of saline embankment
near Narvel and Benavale villages. Analysis of alternatives are studied in terms of
existing and proposed alignment of the embankment and in “With” and “Without” Project scenario. Alternatives are discussed in sections below
6.2. Location (Alignment), Planning and Design Alternatives
Location (Alignment) and Planning:
Existing embankment was constructed in 1952 by KLDC. Existing embankment has now
become undersection at various location and mangroves are grown in certain sections of
embankment (in slope area of embankment in creek side and in patches in land side and
along the channels in the benefited area). In these sections, construction is not possible
as mangroves are not allowed to be removed for any purpose as per High Court
Notification dated 06.10.2005 (Annexure 6.1).
Also, people have constructed some structures on the existing saline embankment and
some of those are of cultural importance also. If these structures are impacted, it will
lead to social issues. Thus, the embankment alignment is modified to avoid the social
and environmental issues. The entire alignment has been shifted to the land side and no
mangrove is to be removed for proposed embankment. Shifting of embankment has
saved mangrove vegetation substantially. Only agriculture fields exist on the land side of
the embankment and people are voluntarily willing to give off their land for the project but
not more than 1-2 m as per consultation. However, KLDC has modified the design of the
embankment to reduce the land requirement also and minimize impact on the farmers
giving the land. In one section, i.e. chainage between 13230 and 13380 is straightened
to save the school and other structures on the land side. Thus, alignment has been
modified to minimize the social and environmental impacts of the project.
However, some of the structures exists on the embankment will be impacted due to the
project as they cannot be avoided. Facilities/utilities which will be impacted includes 42
trees, 10 electricity poles, 16 pakka houses, 8 jetties, 24 fish ponds, 1 electricity service
line, 11 kachha houses, 7 nos of toilets (community and private toilets), 5 solar lights, 5
fish drying platforms, 3 shed, 4 crematorium, 1 shed, 2 temples, 1 well and road. Details
of the structures to be impacted as Annexure 3.2. None of the tree to cut falls in
Maharashtra Tree Felling Act, 1964. Permission for tree cutting will be required from
District Collector as per NGT Order dated 8th Jan 2016 – case no 11/2015 (WZ).
Kharland Development Circle (KLDC) has conveyed to all the concerned departments
for requirement of shifting of utilities and have requested the relocation plan to minimize
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 96
impact on people due to relocation of these facilities. KLDC has kept cost provision in
BOQ for shifting and reconstruction of these facilities.
Design Alternatives
As per the old DPR, land requirement on land side was huge which has been reduced to
by modifying the initially proposed design and reducing the bottom & top width
requirement. In the design top width is reduced from 4 m to 3 m w which has also
reduced the bottom width or land requirement. Total additional land required is 128002
sq m.
KLDC has proposed to provide the various design features in embankment to prevent
breach of the embankment due to wave action. It is proposed to provide protection walls
in weak portions, groynes in the high wave action points and rock toe at starting end
chainages of the CD works.
Construction raw material are selected on the basis of availability in the local area.
Sulphate resistant cement will be used for marine construction to prevent impact on the
structures due to marine water. Demolition waste or residual material may also be used
as filler material for CD works
Various alternatives for slope pitching was considered which includes stone pitching and
ECBs like coconut coir, bamboos, grass turfing etc. However, KLDC suggested that
stone pitching is more practical and long-term solution as per their experience in other
and past schemes. The scheme is for benefit of people and during public consultation
issues of breach of embankment and harm to pitching were explained to the villagers.
Villagers have agreed to take care of the pitching and consent forms signed by them
also include this clause. Reference from other scheme was also taken and it is found
that the stone pitching is found intact even after so many years. So, in all options KLDC
has suggested to use for pitching for creek side and up to HFL on land side
6.3. With and Without Project Criteria
Analysis is carried out for the impacts on physical, social and biological environment in both “with” and “without” project scenario. Comparative analysis is given on Table 6.1 below. From the analysis, it is found that the proposed project has great social significance. It will overall improve the quality of life of people. Environmentally, proposed project has certain impacts but all are limited to construction phase and are mitigable.
Table 6.1 : Analysis of Alternatives on the view of “With and Without” Project Scenario S. No. Parameters Without Project
Scenario With Project Scenario
Social Environment 1. Protection of
Land, people and property
At present, the embankment has become undersection and the
Height of the embankment will be increased and the embankment will be
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 97
resources bund is slide at various sections. Thus, the agriculture land will continue to get impacted due to saline water ingress at these sections. Only 1010 ha of land is under kharif crop cultivation with the existing embankment. Also, the height of the embankment is less, and the water gets inside during cyclonic storms affecting life and property of people leading to huge losses. approx 12544 lives and property costing 1222.50 lacs
renovated so as to prevent saline water ingress. Proposed Renovation project will secure 12544 lives, 815 households and property of worth 1222.50 lacs. Also, it will increase agricultural land to 1388 ha from 1010 ha.
2. Improved communication and village road network
Communication gets disturbed due to inundation during cyclonic storms with the existing embankment
Height of embankment will increase which will prevent inundation during cyclonic storms and communication facility will remain secured
3. Economy Economy will continue to get impacted due to loss of agricultural land and loss of life and property
Income of people in area will improve with increase in agricultural area, crop yield and employment for local people. Also, employment will be generated for local people during embankment construction
Physical Environment 4. Land Use Land use will remain
unaffected with existing project
Additional agricultural land is to be diverted for the construction of the embankment. However due to proposed embankment construction cultivable area will increase from 1010 ha to 1388 ha
5. Air Quality Air quality will remain unaffected due to the existing embankment
Air quality will affect during construction of embankment, but the impact is short term temporary and reversible. Impact can be minimized with mitigation measures
6. Water Quality Water quality will remain unaffected due to the existing embankment
Water quality will affect during construction of embankment, but the impact
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 98
is short term temporary and reversible. Impact can be minimized with mitigation measures
7. Noise Level Noise levels will remain unaffected due to the existing embankment
Noise levels will affect during construction of embankment, but the impact is short term temporary and reversible. Impact can be minimized with mitigation measures
8. Soil quality Soil from the embankment will continue to erode by wave action with the existing embankment
Stone pitching will be provided which will prevent erosion of soil from the embankment
Biological Environment 9. Trees No impacts are
anticipated to tree with the existing embankment project
Total of 42 trees (anwala-1; bhend-30; sevga-2; Nariyal-2; Neem-3; Suvabal-1; Sitaphal-1; Kaju-1; Siras-1) of different girth and height are located on the top and slope of existing embankment. None of these trees are listed under the Maharashtra Tree Felling Act, 1964. Permission is required to be taken from the District Collector for cutting these trees as per NGT order dated 8th Jan 2016 – case no 11/2015 (WZ). Also, compensatory plantation will be carried out in ratio of 1:10.
10. Mangroves Mangroves are gown all along the embankment and on the damaged slopes of the embankment on the creek side. Mangroves exists in the patches on land side and along the channels in the benefited area. If embankment is not rehabilitated, mangroves will spread in the agriculture land also impacting the soil quality and livelihood of people
Mangroves will not be impacted but their growth will be restricted to the existing location only
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 99
6.4. Summary Outcome
As per the analysis carried out it is found that the selected embankment will have
minimal impact on the environment and socio-economy. Proposed project is highly
beneficial for socio-economy. There is minor impact on environmental parameters like
ecology, air quality, water quality and noise levels but these impacts are manageable if
appropriate mitigation measures are adopted.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 100
CHAPTER 7. Public Consultation
7.1. Introduction
Public consultation is one of the key components of the environmental assessment. The
environmental and social impact assessment team conducted public consultations in
project site and study areas. The approach involved a mix of conventional as well as
participatory/ rapid rural appraisal (PRA/ RRA), focus group discussions (FGD) and one-
to-one discussion. Consultation with all the stakeholders has been carried out and the
inputs from the stakeholder were incorporated in the environment management plan in
discussion with the DPR consultant, SPIU and KLDC
This chapter provides details of the public consultations and participation activities
undertaken during the environmental impact assessment studies for the project
“Renovation of Saline Embankment of Narvel Benavale Village at Pen Taluka, Raigad
District, Maharashtra. During public consultation, emphasis was placed on a fully-
inclusive, open and transparent public participation process in the transfer of information
regarding the project and likely impacts from the project on each component of
environment. A number of stakeholders are involved in this project ranging from the
project implementation and monitoring agency, project design agency, kharland
department and general public.
7.2. Objective of Public Consultation
The public consultations were conducted with the following objectives:
• To create awareness and generate understanding about the project among
stakeholders, and to collect their opinion, suggestions for planning and designing
of the project
• To assess positive as well as adverse socio economic and environmental
impacts in the area through participatory methods such as one to one discussion
and focus group discussions.
• To identify the need and concern of the public
• To assess cultural patterns and behaviour of local communities towards the
project
• To understand the environmental and social issues associated with the project
through discussions
• To understand suggestions and opinions of the community and Government
officials on mitigation measures to counter and check the adverse and negative
impact that threaten the socio-economic environment in the area.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 101
• To disclose the environmental sensitive issues and form a consensus for such
issue’s purposes. For example, cutting of trees on the embankment, GAIL
pipeline, etc.
• To understand the satisfaction level of people with proposed mitigation and
management measures proposed for the project
7.3. Methodology and Outcome of Consultations
Informal consultations were carried out with the project implementation agency, i.e.
Kharland Development Circle (KLDC), SPIU, local people and other stakeholders like
gram panchayat. Discussion was also carried out with RDC and DDMO to clarify the
status of the ownership of land where the project is to come up. Team used checklists
for carrying out consultations and the checklists are attached as Annexure 7.1 and 7.2.
Before beginning of consultation, the team inquired with stakeholders whether they were
aware about the project. With support of KLDC/SPIU representative, the Consultant
team elaborated purpose, work plans and methods to be used in execution of the saline
embankment works in the project area. Details on the number of consultations
conducted are given in Table 7.1 below.
Table 7.1 : Details of Public Consultation
Sl. No.
Name of Stakeholders Period of Consultation
Outcome of Discussion
1. Kharland Development Circle (KLDC)
28 Aug, 2016 Preliminary meeting was carried out with the KLDC and visit was made to the site and general discussion were carried out with people of Narvel Benavale during the visit. All people were found aware about the project and are in favour of the project
2. People of Kaleshri and Vithalwadi
Cooperative Society of Bhal Vithawadi (Fisherman) People of Kaleshri (Ramesh Shankar Patil, Mrs Jyoti Narendra Patil, Nikhil A Thakur, Jayesh Pandurang Mhatre and Sharad Vasant Patil and Vilas Mhatre: 9922966249) and Bahiram Kotak People of Narvel and Benavale (Shri Ganesh Shivram Mokal, Atmaram
01/09/2016 18/09/2016 19/09/2016 24/09/2016
Detailed survey and discussion were carried out with the different group of people of villages regarding the project and the additional land requirement. People asked for the proposed alignment, timeline of start and completion of the project, insisted to move towards creek side for expansion. Importance of mangroves were explained to people and they understood and were agreeing to allow construction of embankment to some extent in their land. The embankment provides accessibility to them People of Vithalwadi complained that due to breach of embankment, water enter their houses during floods. Embankment is getting
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 102
Ganu Mokal, Yashwant Narayan Mhatre, Lakshman Bandu Mokal, Janardan Javarya Mokal, Narayan Padam Thakur, Narayan Padam Thakur, Bhal Vithalwadi, Ambaji Maya Mhatre, Anant Laxman Mhatre, Vilas Shantaram Mhatre, Nandkumar Narayan Mhatre, Parashuram Shantaram Mhatre, Amarchand Kamalakar Mhate, Bahiram Kotak, Chandra Joma Patil, Sanchin Lakshman Patil, Mahadev Joma Langi, Kashinath Krishna Patil, Ganapat Nagu Mali, Lakshman Ramdas Mali) People of Mothebhal
26/09/2016
impacted/damaged due to crabs and rodents. Approx. 100 ha of land in Vithhalvadi is affected due to saline water ingression. People repair the embankment on their own to prevent entry of saline water inside. In Kaleshri also approx. 10 ha of the land is damaged due to entry of saline water As per KLDC, land is Government land and no private land is required and as per survey and discussion with people, it was found that the land of embankment and additional land required both are private properties. People also suggested to construct walls in the weak section to prevent breach of embankment due to wave action. Also, people insisted on providing stone pitching on the both sides to prevent damage by crabs and rodents. Also, people suggested that height of the embankment should be increased as sometime water during high tide enters inside the fields landward side which affect the soil quality of their fields. This is also considered in design. Overall height of embankment is increased and it is kept as 1.5 m higher than the highest creek level.
3. Kharland Development Circle (KLDC) and SPIU
Sep-Oct, 2016 SPIU was informed about the land issue and SPIU directed Kharland to verify the issue with revenue department.
4. RDC, DDMO, Kharland Development Circle (KLDC)
03/12/2016 It was clarified with RDC and DDMO that the land under the saline embankment is private land
5. People of Vithhalvadi and Mothe Bhal
22/04/2017 Visit was made to the site to discuss about the project and their will to donate the land for the proposed embankment construction and people agreed to donate the land but they said they cannot donate large area as people have small land holdings. If embankment is to be moved by 1-2 m inside their land then they can donate the land. Thus, the embankment design is modified so as the bottom width requirement has been reduced which will minimize the land
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 103
requirement on the field side. Also land owners agreed for donating the land but demanded for compensation of the structures built by them which may get affected due to renovation of embankment. Also, they demanded that all the utilities which will be affected due to the project should be shifted or reconstructed for them prior dismantling
6. People of Kaleshri, Kanoba, Waskand, Bahiram Kotak, Ghoda Bhander
June-Oct, 2018 A survey was made at the site to assess the structures which will be impacted and for the additional land required. Details of the people losing the land and details of the PAPs whose structures will be affected is provided in Annexure 7.3 and 7.4.
A large-scale consultation was also carried out by Kharland Development Circle (KLDC)
with local people and Patwari (Talathi as called locally) to inform people about the
project and to obtain their consent for using their land for strengthening of embankment.
People have agreed to give off their land voluntarily for such construction of
embankment and have signed the consent letters.
7.4. Disclosure
Environment impact assessment report will be disclosed at the SPIU (NCRMP) website.
Executive summary will also be disclosed in local language as well at SPIU and NCRMP
website
7.5. Summary Outcome
The EQMS team had discussion with all the above-mentioned stakeholders using one to
one interview and focus group discussion. These discussions helped to convey the
project elements, activities and likely impact on the ground to all concerned. The
suggestions made during these interactions were noted and included in the design and
environment management plan.
Design of the embankment has been improved in terms of the land requirement for
embankment. Bottom width is reduced to minimize the land requirement. Height of the
embankment is also increased. Other things considered in design after the survey and
consultation are provision of stone pitching on the land side also and mangroves line
should be kept as the creek side boundary of the proposed embankment to minimize the
impact on mangroves. Public consultation and site surveys has helped significantly to
improve the project design and social acceptability of the project.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 104
CHAPTER 8. Environmnetal Management Plan
8.1. Introduction
The Environmental Management Plan (EMP) is synthesis of all proposed mitigation and
monitoring actions, set to a time frame with specific responsibility assigned and follow-up
actions defined. EMP is a plan of actions for avoidance, mitigation and management of
the impacts associated with construction and operation stages of the project. A detailed
set of mitigation measures have been compiled in view of the likely impacts associated
with the proposed project “Renovation of saline embankment of Narvel and Benavale
village at Pen Taluka, Raigad district”.
8.2. Objective of Environmental Management Plan
The EMP consists of a set of mitigation, monitoring and institutional measures to be
taken up during the design, construction and operation (post-construction) stages of the
project. The EMP has been designed keeping in view of the regulatory and other
requirements to ensure the following:
• Minimum disturbance to the environment and social components
• Compliance with the environmental acts, rules and guidelines of the GoI &
maintaining the quality of air, water, soil and noise as per the prescribed norms by
regulatory bodies.
• Compliance to the Operational Policies and Guidelines of the Funding Agency
• Conservation of natural resources to the extent possible
• Enhancement of Project benefits for Society & Environment
• Sustainable development and operation of project
8.3. Environmental Management Plan
Major activities associated with the proposed project involves clearing of the site,
stripping of soil, vegetation removal & tree cutting, utility shifting, material transportation
& storage, shifting of utilities & structures, strengthening and raising height of the
embankment, slope stabilisation, debris storage, transportation & disposal, construction
of CD works and construction of new CD works.
A detailed environmental management plan for each activity of Pre-construction,
construction and operation phases is prepared. EMP lists the activities involved along
with environmental impacts associated with each activity, suggestive impact mitigation
measures and implementation plan covering monitoring and supervisory responsibilities.
The environmental management plan is included as Table 8.1.
Environment Budget and It Implementation: Adequate resources are allocated under
the project for environmental management which will be part of construction and
operation costs. The environmental budget is estimated at INR 37789597.44. In addition
to this other environment management measures are considered as part of project cost.
The Pre-Construction and construction stage EMP requirements should form part of
Bidding document. Contractor will have to quote for each of the mitigative measures as
applicable. Details of Environmental Management Budget are given at section 8.12.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 105
Table 8.1 : Environmental Management Plan for Saline Embankment-Narvel- Banavale
S. No. Environmental Issues Management Measures Responsibility Planning and
Execution Supervision
Pre-Construction Stage (Planning- Impacts based on Location) 1. Embankment located in
CRZ area • Saline embankment falls under Coastal
Regulation Zone (CRZ) area and Kharland
Authority has already obtained CRZ clearance
for restoration, repair and strengthening of the
embankment. Contractor will follow the
conditions specified in CRZ letter which is
attached as Annexure 8.1
KLDC SPIU
2. Requirement of additional land for
strengthening
• No land acquisition is anticipated, as additional
land is through a voluntary contribution of land by
the landowners.
• As per KLDC additional land (12.8 ha) is required
for strengthening of the bund which is private
land (4.8963 ha) and Government/other land
(7.9039 ha)
• Consents letter through voluntary donations are
obtained from landowners by the Revenue
Officer facilitated by KLDC. Farmers have given
willingness to give their land in writing for
construction of bund in order to protect their
farms and village in total.
• District administration and KLDC have jointly
organized Public consultation meetings to create
awareness about the proposed embankment and
also on requisite voluntary contribution for the
same on their behalf.
• Embankment is straightened between the
KLDC SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 106
chainage 13230 and 13380 m
• Consultation shall be carried out with the
community again prior start of construction
• Grievance readdress mechanism shall be
provided at Kharland office so as community can
lodge the complaint if any. Information shall be
given to the people about this grievance
readdress mechanism through consultation and
appropriate media
• Land shall be taken on land side as per the
proposed design and consent letters only
• The saline embankment shall be renovated
within the proposed right of way
3. Presence of Mangroves in the area
• The proposed alignment is in the vicinity / buffer
zone of mangroves (on both creek & land side)
• Mangroves are present all along the creek side
of embankment and in patches on the land side
from 1650-1740, 5010-5820, 6270-7590, 8340-
9090, 9150-9240, 9720-10350 and 16110-
16380 chainages.
• The existing boundary of the bund away from the
mangrove area on the creek side is considered
as the edge of the proposed alignment. The
proposed bund will extend to the field side to
accommodate for its increased width.
• Mangroves are present along the creek side of
embankment and in patches on the land side and
along the canals in the benefited area. During the
strengthening and repair process, mangrove on
both creek and land side should not be disturbed.
All mangroves shall be preserved. Any additional
KLDC SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 107
land if required for strengthening of the
embankment shall be taken on creek side, only if
mangroves are not present on creek side else
land on agriculture field side should be
considered as per the consent of land owners
• No mangrove shall be disturbed or removed
during dismantling & reconstruction of CD works
and Ring bund construction & dismantling.
• Since embankment is in buffer zone (50 m) of
mangroves. No Objection Certificate (NOC) from
the Forest Department (Mangroves Cell) is
obtained and is given in Annexure 5.1 and
contractor should follow all the conditions of the
NOC
• Contractor shall study the strip map for
mangroves presence. Strip maps are attached as
Annexure 4.1. This strip maps shall be followed
strictly for available bottom width and additional
private land required for embankment
strengthening
• All caution shall be exercised to prevent any
harm to mangroves
4. Impact on Trees • Total of 42 trees (anwala-1; bhend-30; sevga-2;
Nariyal-2; Neem-3; Suvabal-1; Sitaphal-1; Kaju-
1; Siras-1) of different girth and height are
present all along the stretch of the embankment.
All the trees are present on the embankment and
are anticipated to be cut for embankment
construction. However, one tree exists between
chainage 13230 to 13380 and efforts can be
made to save the tree as the alignment is
KLDC/ District Collector/Forest
Department
SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 108
proposed to be straightened in this section
• Efforts shall be made to save these trees through
design changes. However, during embankment
construction measures shall be taken to retain
the trees as much as possible. All efforts shall be
made to preserve the trees including any minor
adjustment in the design to save the trees
• A joint visit shall be conducted by the KLDC
along with the environment expert of Contractor
to ascertain the tree saving and requirement of
tree cutting
• Permission shall be taken from the District
Collector for cutting the trees as per NGT order
• If any trees need to be removed from proposed
right way before commencement of work it shall
be done by obtaining Permission from the District
Collector for cutting the trees as per NGT order
• Identified trees (as per joint visit of KLDC &
contractor and tree cutting permission) for cutting
should be cut. Cut logs should be managed as
per the condition given in tree cutting permission
• No other flora should be harmed other than
identified and marked vegetation and trees
• Stacking, transport and storage of wood shall be
done as per prevailing norms of the state forest
department
• Vegetation (bushes, weeds etc) at the site shall
be removed in presence of Environmental Expert
of Contractor and KLDC
• Scraped vegetation waste shall be collected and
shall be disposed of at the debris disposal site
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 109
• Compensatory afforestation for every tree cuts
shall be panned in the ratio of 1:10. Area for
plantation shall be identified with the help of
Forest Department and Kharland Development
Circle (KLDC) and SPIU shall be requested to
transfer the fund to Forest Department, based on
the estimate from Forest Department.
5. Shifting of the utilities - electricity poles and
service electricity line
• Ten electricity poles and service electricity line
need to be shifted for embankment strengthening
and renovation. Shifting of the poles and the line
should be carried out through MSEDCL prior to
start of work. Concurrence should be obtained
from MSEDCL and all the conditions mentioned
in the concurrence shall be followed by KLDC
• HT electricity line Pole is present at
18.749467oN, 73.0174580E, as it comes in the
outer right end of the embankment so it not to be
shifted from the existing location.
• KLDC in consultation with MSEDCL shall identify
the exact number of poles and length of the line
for shifting and the cost required for the same i.e.
shifting shall be included in the DPR.
• Proposed shifting locations shall be confirmed by
MSEDCL with the concerned stakeholders and
MSEDCL shall undertake the responsibility of
shifting
• The necessary costing for shifting of of
poles/service line shall be included in the DPR
cost
• Necessary safety and protection work shall be
undertaken by the contractor for shifting the
KLDC/MSEDCL SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 110
electricity poles, electricity line and solar lights.
6. Shifting of utilities- Solar lights
• Five Solar lights are available at the
embankment zone and all are required to be
shifted temporarily as per survey for renovation
of the embankment
• Proposed shifting locations shall be confirmed by
gram panchayat with the concerned stakeholders
and gram panchayat shall undertake the
responsibility of shifting.
• Alternative should be provided after dismantling
the solar light till the time solar lights are shifted.
• The necessary costing for shifting of these
utilities shall be included in the DPR cost.
• Necessary safety and protection work shall be undertaken by the contractor for shifting the electricity poles, electricity line and solar lights.
KLDC/Gram panchayat
SPIU
7. Shifting of CPR: Crematorium-4 nos
• Four crematorium exists at the chainage 2280,
2550-2580, 9555, and 13030 m which will be
affected and required to be shifted during
embankment construction. These crematoriums
are CC structure covered with the shed.
Dimension of this crematorium are 7 m X 6 m,
6.8m X 6m, 23m X 20m, 12X 4 m respectively.
The crematorium is accessible through the 2-3
no stairs and is at same level of existing
embankment.
• Community and gram panchayat concurrence
shall be obtained prior to demolition and
reconstruction of crematoriums. Location for
crematorium shall be decided in consultation with
the local people and gram panchayat
KLDC SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 111
• Crematorium shall be constructed at the decided
location prior dismantling
• Crematorium to be constructed should have
proper and safe access and covered shed
• Cost for construction of the crematorium shall eb
included in the DPR
• Necessary safety and protection work shall be
undertaken by the contractor
• Contractor shall ensure adequate signage and
safety measure including installation of display,
signage and diversion boards
8. Shifting of CPR: Jetties-8 nos
• Alternate access to the jetties from the village
shall be provided during the construction phase
• Concurrence shall be taken from Maritime Board
and gram panchayat prior dismantling and
reconstructing the jetties. All conditions as
prescribed in the concurrence letter shall be
followed
• Cost for construction of the jetties shall be
included in the DPR as per discussion with the
Maritime Board
• Necessary safety and protection work shall be
undertaken by the contractor
• Contractor shall ensure adequate signage and
safety measure including installation of display,
signage and diversion boards
KLDC/Maritime Board
SPIU
9. Shifting of CPR: Shed-3 nos
• 3 nos of passenger shed are located on the
embankment at chainages 2990, 3280 and
between 1980 to 2040 chainage. Shed between
1980 to 2040 chainage is RCC shed and have
dimension of 15 m X 10 m
KLDC SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 112
• These sheds will be affected and thus shall be
relocated at alternate location in consultation with
the gram panchayat and local people
• Concurrence will have to be obtained from gram
Panchayat and the villagers prior to shifting of
sheds. All conditions given in the concurrence
letter shall be followed
• Necessary safety and protection work shall be
undertaken by the contractor
• Contractor shall ensure adequate signage and
safety measure including installation of display,
signage and diversion boards
10. Shifting of CPR: Temples-2 nos
• Two Temples i.e. Bahari Dev located at 13230
and Bap dev located at 13770 to 13800 m chain
age are present on the landward side of the
embankment and will be affected.
• Bahari Dev temple located at chainage 13230
can be saved as embankment between chainage
13230 and 13380 m is proposed to be
straightened
• Concurrence should be obtained from gram
Panchayat and the villagers prior to shifting of
temples
• Locations for shifting of the temples shall be
decided in consultation with the gram panchayat
and villagers
• Necessary safety and protection work shall be
undertaken by the contractor
• Contractor shall ensure adequate signage and
safety measure including installation of display,
signage and diversion boards
KLDC/Gram panchayat
SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 113
11. Shifting of CPR: School (1 no)
• One school is present at chain age 13230 along
the creek side of the embankment which will be
affected.
• This school will not be affected as in this section
embankment is proposed to be straightened
• However, access to this school may get
disturbed so temporary access should be
provided for the school
• Cost for provision of alternate access and steel
barricading in front of school shall be considered
and included in DPR
• Necessary safety and protection work shall be
undertaken by the contractor
• Additional safety measure like steel barricading
shall be provided near the school to ensure
safety of children
• Contractor shall ensure adequate signage and
safety measure including installation of display,
signage and diversion boards
KLDC/Gram panchayat
SPIU
12. Shifting of Well (1 no), Ottas (5 nos),
community toilet (4 no) and road
• Five Ottas are present on creek side of the
embankment site.
• A road exists near village Vithalwadi and this will
also be impacted due to proposed renovation
works
• Temporary arrangement shall be made for fish
drying till the Ottas are reconstructed in
consultation with the community. Arrangement
shall also be made for access to Vithalwadi
village during construction phase till the road is
constructed again
• One well of RCC (15*10) is located at chainage
KLDC/Gram panchayat
SPIU
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 114
1910 m on the embankment and 4 community
toilets exists at 3 different chainages (1980-2040,
2910-2940 and 2970)
• Locations for shifting of the well shall be decided
in consultation with the gram panchayat and
villagers
• Cost provision for shifting of the well &
community toilets and reconstruction of Ottas
and road shall be considered and included in the
DPR
• Necessary safety and protection work shall be
undertaken by the contractor
• Contractor shall ensure adequate signage and
safety measure including installation of display,
signage and diversion boards
13. Impact on the Private land and private
Properties (19 no pakka houses, 11 no kachha
houses, 3 toilets and 24 fish ponds)
• Private land to be taken for the project shall be
as per the consent given by the land owners.
Contractor shall stop the work in case of any
conflict with land owners and shall contact to
Kharland Development Circle. Work shall be
resumed only after resolution of the conflict
• There are total 19 pakka houses on the
embankment however only 16 may be affected
due to straightening of embankment between
13230 and 13380. Other than this 11 kachha
houses/jhopdi, 3 private toilets and 24 fish ponds
will be affected due to renovation works.
• Alignment is proposed to be straighten between
13230 to 13380 so all the structures within this
section should be protected
• Community is consulted and concurrence is
Contractor SPIU/Kharland Department/Third Party Supervision
and monitoring Agency (if appointed)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 115
obtained from community to demolish these
private structures and pay off the cost for these
structures
• Compensation shall be given to people whose
private property (houses, huts and ponds) will get
affected as per the valuation estimation (in line
with SIA, R & R Act, 2013 and WB policy) and
agreement with the owners
• Budget for compensation for structures/private
property shall be included in the project cost.
• No other structure shall be affected due to the
proposed project.
• Grievance readdress mechanism shall be
provided at Kharland office so as community can
lodge the complaint if any.
• Information shall be given to the people about
this grievance readdress mechanism through
consultation and appropriate media.
14. Impact on Access to – Private Properties
(School/Vithhalvadi village and other private
properties) and Provision of Improved
Access to Private Properties
• Road access to the Vithalwadi village will get
affected at the chain age 2910 to 2970 m.
Alternate access arrangement shall be provided
for Vithhal vadi village as the road to vithavadi
will get impacted.
• Access to the school located at chainage 13230
will also get affected and alternate access shall
be provided for school
• In case access to any of the private
property/house/structure gets impacted then
alternate access should be provided during
construction phase.
Contractor SPIU/Kharland Department/Third Party Supervision
and monitoring Agency (if appointed)
Pre-Construction Stage (Design Based)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 116
15. Finalization of drawings and alignment
• A re-survey shall be conducted at the time of
implementation for verifying encroachment of the
mangroves on the proposed alignment
• Care has been taken while designing the
proposed alignment is after the mangrove line /
area as agreed by Forest Dept/ Mangrove cell
• While Transferring the alignment on the ground
care shall be taken by the KLDC and Contractor
that the alignment is as per the drawing and no
additional private or mangrove land is involved.
Contractor/KLDC SPIU
16. Contractor’s Mobilization Designation of Environment and Safety Officer and Orientation Training
• Contractor shall designate and mobilize the
qualified Environment, Health and Safety officer
for effective implementation of EMP and ensuring
safe operations during construction stage.
Contractor
Kharland Development Circle (KLDC), Third Party
Supervision and monitoring Agency (after appointment)
and SPIU/ PMC 17. Joint Verification by
KLDC and Contractor • A joint visit shall be carried out by KLDC and
contractor for demarcating the final alignment in
the field.
• Identification & marking of utilities that are to be
impacted like Electric Poles, solar lights, service
electricity line etc., trees to cut, and other utilities
(crematorium, sheds etc) to be shifted or re-built
as per the DPR
• Contractor shall submit a request to Kharland
Development Circle (KLDC) for a joint visit
• Contractor shall record proceedings and
decisions made during site visit and take
approval of the Engineer.
Contractor and Kharland
Development Circle (KLDC)
Kharland Development Circle (KLDC), Third Party
Supervision and monitoring Agency (after appointment)
and SPIU/ PMC
18. Regulatory Permits and Compliances to
• Contractors and their EHS officer should inform
himself of requirements of local laws, regulations,
Contractor
SPIU/Kharland Department/Third
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 117
Clearance conditions Obtaining all regulatory permissions and clearances prior to start of work as applicable
and rules in force in State of Maharashtra, with
regard to labour laws, electrical safety, and
applicable environmental laws and regulations
• Contractor will obtain Consent to Establish and
Consent to Operate will be obtained by
contractor for setting up of DG sets, batching
plant, as required from Maharashtra State
Pollution Control Board (MSPCB)
• Contractor should obtain environmental
clearance from State or District Environmental
Impact Assessment Authority (SEIAA/DEIAA) as
the case be for establishment of the borrow
areas if new borrow areas are identified. (current
proposal is to source material from operational
mines)
• Saline embankment falls under Coastal
Regulation Zone (CRZ) area and CRZ clearance
for restoration, repair and strengthening of the
embankment has already been obtained by
Kharland Authority. Contractor will follow the
conditions specified in CRZ letter which is
attached as Annexure 8.1
• Permission is obtained from mangroves cell,
Forest Department for working in close vicinity to
Mangroves. Contractor shall follow all the
conditions mentioned in the permission
• Permissions to be obtained by Kharland
Department includes Permission from DC office
for tree cutting, permission from maritime Board
for jetties dismantling and construction,
Permission from MSEDCL for dismantling and
Party Supervision and monitoring
Agency (if appointed)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 118
reinstalling electricity poles and service line and
permission from Gram panchayat for
shifting/reconstruction of solar lights,
crematorium, road, ottas, well, temples, ponds,
toilets and sheds
19. Preservation of Mangroves
• Contractor shall not disturb or cut any Mangroves
either in the creek side or in land ward side
during construction. All mangroves shall be
preserved and Contractor shall abide by the
NOC of the Forest Department.
• Mangroves shall not be disturbed during
construction especially in the chainages (1650-
1740, 5010-5820, 6270-7590, 8340-9090, 9150-
9240, 9720-10350 and 16110- 16380) where
mangroves are present on land side also
• Contractor shall undertake the work as per the
strip maps prepared for the embankment.
• This strip maps shall be followed strictly for
available bottom width and additional private land
required for embankment strengthening
Contractor Kharland Department, Third Party Supervision
and monitoring Agency (after
appointment) and SPIU/ PMC
20. Preservation of trees and vegetation
• Contractor shall take approval of the concerned
Engineer before site clearance
• Contractor shall take care all precautions needed
to preserve the trees
• Contractor shall identify the number of trees that
need to be cut through a joint verification by the
KLDC. Trees present on embankment are listed
in Annexure 3.2.
• Contractor shall undertake tree cutting as per the
written instructions of the Engineer after
obtaining permission from Contractor shall
Contractor Kharland Development Circle (KLDC), Third Party
Supervision and monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 119
undertake tree cutting as per the written
instructions of the Engineer after obtaining
permission from Forest Department or
Appropriate authority
21. Construction plan and communication with
community
• Contractor shall visit the entire project stretches
and develop time bound construction schedule
and submit it to Executive Engineer KLDC at
least 15 days prior to start of construction work
• Contractor and KLDC shall install a project
information board showing name of work, project
costs, duration, date of commencement,
proposed date of completion, full details of
grievance redressal mechanism along with all
related contact details at the site and kharland
office respectively
• Share the project information to public using
appropriate mode (display, pamphlet distribution)
at least 15 days in advance.
Contractor
KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
22. Setting up construction camp and material
storage areas: Selection of
land/Location for setting up construction camp, or
material storage area, Batching Plants etc., operational safety, sanitation, drinking
water supply,
• Contractor shall identify the sites for setting up
material storage area, construction camp, and if
any plant established shall notify the Executive
Engineer for their approval for the site.
• Any plant or construction camp site &
construction material storage site shall be sited
at a min. distance of 150 m from water body and
500 m from residential area or any sensitive
location like school or hospital. Mobile units can
be placed within 250 m distance of residential
area also. These plants shall be located in
downwind direction of any residential area.
• Available Government waste land along the
Contractor SPIU/Kharland Development Circle (KLDC)/Third Party
Supervision and monitoring Agency
(if appointed)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 120
embankment shall preferably be used for the
establishment of these plant sites with the
permission of concerned authority.
• If usage of this land is not possible then the
private land which is currently not being
cultivated within the benefited area can be used
for the establishment of the plant site with the
consent of the land owner.
• Site shall be marked on the map and the layout
of such sites along with the photographs shall be
submitted to Kharland Development Circle
(KLDC) prior to setting up any such facility to
obtain prior approval
• These sites shall be fenced preferably with the
sheets so as to minimize the exposure of the
public to the dust
• Establishment and operation of these plants shall
be initiated only after obtaining consent to
establish and consent to operate from MPCB by
contractor
• Contractor shall ensure all measures for dust
control (like sprinkling of water) and prevention of
water, soil (preventing flow of contaminated
water from camp) and noise pollution shall be
taken up.
• Speed limits at site shall be maintained between
15-20 km/hr
• Contractor shall ensure parking of vehicles or
installation of machineries shall not block the
access or block public utilities in the project area.
• 2 Bio-toilets (one for male and one for female)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 121
shall be provided at construction camp, storage
areas and operational areas.
• The bio toilet must have provision of at least
1000 litres overhead water storage. It shall be
well maintained and in usable condition at all the
times. It shall be regularly cleaned, and overhead
tank replenished as per requirement. Work force
shall be oriented to use mobile toilets. No open
urination/defecation shall be allowed.
• Drinking water facility shall be available for
workers at site
• Loose construction material and waste storage
area shall be paved and covered
• Oil shall be stored on concreted floor with
spillages and leak collection pits
• Oil interceptor shall be provided in vehicle
cleaning areas
• Contractor shall ensure all construction vehicle
shall comply with traffic rules and carry PUC
certificate.
• Contractor shall ensure First Aid Kits at the camp
in case of any emergency.
• Contractor shall ensure provision of Fire
extinguishers in the storage/ yard area
• Location of storage of each material shall be pre-
identified and signage shall be provided for the
same
• Provision of sprinklers for dust suppression shall
be made
• Contractor shall ensure weekly inspection by
Environment and Safety experts of the contractor
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 122
to confirm fitness of these plants and following
points shall be verified during their visit
o All plants are working in good working
condition
o Dust pollution control measures are being
taken up as per the consent orders
o Noise monitoring shall be taken up to ensure
prevention of noise pollution
o Contractor shall ensure Workers safety by
providing and encouraging use of PPEs
o Contractor shall ensure the maintenance of
record including Log book of operation of the
plants
• Contractor shall ensure after completion of the
construction works these plant sites shall be
restored back to the original condition.
• Contractor shall ensure all waste and machinery
shall be removed from the site. Site shall be
made clean and free from any temporary
structure.
• Contractor shall ensure renovation of the site as
per the provision of the contract and by providing
of a vegetation cover in form of grass and small
herbs.
23. Sourcing of earth and Borrow area management
• The project requires approx. (406558.8 cum for
hearting + 91829.48 cum for casing) for
embankment. Earth shall be obtained from the
approved quarries of KLDC
• KLDC shall ensure the proposed borrow areas (if
any) have permission from the appropriate
authority including Environmental Clearance
Contractor Kharland Development Circle (KLDC), Third Party
Supervision and monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 123
(DEIAA/ SEIAA).
• KLDC had identified a tentative borrow areas at a
distance of 20 km i.e. in village Pen, Gram
Panchayat, Pen Taluk and District Raigad which
shall be used
• Contractor shall get approval of Kharland
department prior to opening and closure of every
borrow area. Kharland and TPQA shall approve
the borrow pits in accordance to the IRC
recommended practice for borrow pits (IRC 10:
1961)
• Contractor shall develop borrow area plan
indicating the location and area of the identified
borrow area along with the consent order of land
owner, photographs of the area and geographical
coordinates of the corners of the borrow areas
• Finalization of borrow areas for earth and all
logistic arrangements as well as compliance to
environmental requirements, as applicable shall
be the sole responsibility of the Contractor.
Selection Criteria of Borrow areas is as follows:
• Contractor shall identify the potential borrow
areas and take permission from Executive
Engineer before operating any borrow areas.
• The Contractor shall not start borrowing earth
from selected borrow area until the mutual
agreement is signed between landowner and
Contractor. Copy of the document shall be
submitted to Executive Engineer.
• The Contractor in addition to the established
practices, rules and regulation will also consider
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 124
following criteria before finalizing the locations.
o The borrow area should not be located in
agriculture field unless unavoidable i.e. barren
land is not available.
o The borrow pits should not be located along
the roads.
o The loss of productive and agricultural land
should be minimum.
o The loss of vegetation is almost nil or
minimum.
o Sufficient quality of soil is available.
o The Contractor will ensure the availability of
suitable earth. The Contractor shall obtain
representative samples from each of the
identified borrow areas and have these tested
at the site laboratory following a testing
programme as approved by the concerned
Engineer. It shall be ensured that the fill
material compacted to the required density.
o Planning of haulage roads for accessing
borrows areas shall be undertaken during this
stage. The haulage roads shall be routed to
avoid agricultural areas as well as forest areas
as far as possible and shall use the existing
village roads wherever possible.
• Contractor shall not be permitted to borrow areas
in forest areas
• Contractor shall identify location of borrow areas
and get approval from E.E staff.
• Earth material should be taken from barren land
or selected borrow area during lean period as per
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 125
IS Code 1498 after taking approval from
Executive Engineer.
• Borrow areas should be dug as per IS code:
4701 and prior approval from the competent
authorities must be taken before execution and
mutual agreement with the land owners should
be taken by the contractor and ensure the borrow
areas should not have any environmental issues
like water logging etc.
• Borrow pits should be drained to avoid
stagnation of water and the bottom should be
levelled properly / bottom level of borrow pits
should be fixed with reference to the prevailing
ground slope towards the nearest natural
drainage course.
• Borrow areas should be avoided in agricultural
areas
• Required permission should be obtained from the
authorized person as stipulated in the
Maharashtra State minor minerals act and if
operating in private lands mutual agreement and
no objection certificate need to be produced to
E.E by the contractor.
• No borrow pits shall be dug within 5m of the toe
of the embankment, if the depth of the borrow pit
is less than 0.5m it shall be after 5m of the toe of
the embankment and if the pit depth shall be
more than 0.5m it shall be 10m of the toe of the
embankment or within such a distance from the
toe of the bank where a 4:1 hydraulic gradient
line cuts the ground surface, which ever more.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 126
• Borrow pits shall be drained to avoid stagnation
of water and the bottom should be levelled
properly / bottom level of borrow pits should be
fixed with reference to the prevailing ground
slope towards the nearest natural drain based on
the site conditions
• Borrow areas shall be preferably outside CRZ
areas
• Precautions to be taken up if Private Lands are
used:
• If waste land is not available then soil from the
agriculture fields can be taken with the consent
of the land owners.
• An agreement shall be formed with land owner
indicating the area to be borrowed, the quantity
of earth to be excavated, time for borrowing,
restoration works and the cost to be paid to land
owner in local language. Borrow areas shall not
be constructed near the road side.
• Along with the consents, the Contractor shall
apply to appropriate authority including obtaining
Environmental Clearance from DEIAA/ SEIAA
through KLDC.
• Contractor shall ensure that borrow area shall be
planned so as to minimize the vegetation loss, no
tree cutting is required and shall not be located
close to roads (up to 50 m).
General Conditions to be followed
• Haulage of material to the areas of fill shall
proceed only when sufficient spreading and
compaction plants are operating at the place of
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 127
deposition
• Top soil from the borrow area shall be removed
up to depth of 15 cm and shall be preserved
under covered condition. This soil shall be
spread on the borrow area during closure. A 15
cm topsoil will be stripped off from the borrow pit
and this will be stored in stockpiles in a
designated area for height not exceeding 2m and
side slopes not steeper than 1:2 (Vertical:
Horizontal).
• Restoration of the Borrow pits shall be done as
per the EC conditions and in case of private
lands it shall be as per willing of the land owner
i.e. conversion to aquaculture farms/ farm ponds
etc as per the site conditions.
• Contractor shall keep records of all the borrow
earth and TPQA shall check and verify all the
sources and approvals time to time and if any
issues arises it shall be brought to the notice of
SPIU
• The Contractor will keep record of photographs
of various stages i.e. before using materials form
the location (pre-project), for the period
borrowing activities (Construction Phase) and
after Renovation (post development), to
ascertain the pre and post borrowing status of
the area.
24. Sourcing of Other
construction material • Other material required are aggregates, cement,
sand, steel and geotextile. (Rubble: 46312.35
cum; Cement: 3224.93 cum, Steel: 108 MT and
Contractor
KLDC, Third Party Supervision and
monitoring Agency (after appointment)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 128
Sand: 11885.89 cum)
• Contractor shall ensure all materials used in
construction of embankment shall be purchased
from approved quarry suggested by KLDC. No
other sources are permitted. Quarries/suppliers
identified by KLDC are Mapgaon at 35 km for
Rubble cement & steel from Pen at 20 km and
sand from Dharmtar at approx 25 km
• A joint visit may be made by environmental
expert of the contractor, Executive Engineer
KLDC to verify the quality and suitability of
material, environmental approvals and
environment management measures at the
quarry site
• The Contractor shall finalize the quarry for
procurement of construction materials after
assessment of the availability of sufficient
materials, quality and other logistic
arrangements.
• A preliminary survey has been carried out by the
Executive Engineer and identified the quarry and
is provided in DPR
• If extraction shall be done, prioritize sites already
permitted by the Mining or concerned
department,
• Contractor shall purchase materials and finalize
vendors who have valid permissions.
• If other sites are necessary and the contractor
want to use, let the contractor obtain necessary
permission from the concerned regulatory
authority and inform Executive Engineer.
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 129
25. Arrangement for construction water
• Contractor shall ensure use of potable water for
every construction activity. Contractor shall
provide necessary approval regarding water
supplying agency.
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC 26. Debris disposal
management and setting up debris disposal site
• Waste expected to be generated due to
construction includes the following
✓ Dismantling of CD works: 365.9 cum ✓ Stripping of the embankment up to 15
cm: 40105.69 cum ✓ Existing vegetation on bund and the
sites for the labour camps/debris disposal site/construction camp/storage yards
✓ Municipal waste from labour camp-20-25 kg/day
✓ Dry concrete/empty cement bags/broken bricks and stones, broken wooden supports etc-10-20 kg/day
• Construction and Demolition waste needs to be
disposed in accordance to construction and
demolition rules, 2016, municipal waste should
be managed as per the Solid Waste
Management Rules, 2016 and hazardous waste
should be managed as per the Hazardous and
Other Waste Management Rules, 2016
• A site must be identified by the contractor prior
start of construction for disposal of the above-
mentioned waste material. This site should be
located minimum 50 m distance from water body
and 250 m from a residential area. This site
should be selected only at land side of
embankment
• Muck generated from stripping shall be used for
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 130
construction of the ring bunds after obtaining
consent from the KLDC engineer. Thus,
clearance of vegetation followed stripping of the
soil should be the first activity to be carried out
for the proposed project.
• The site shall be approved by the executive
engineer of KLDC
• Contractor shall submit the location, area and
photographs of the proposed site to the KLDC at
least 15 days in advance for their acceptance of
the site.
• Contractor will ensure that the debris are
collected and transported to the pre-designated
and approved debris disposal site. Record of
debris generated and transported should be
maintained by contractor
• All the waste shall be segregated into recyclable
and non-recyclable waste. Recyclable waste
should be sold to authorized vendors and non-
recyclable waste should be disposed off through
local agencies in the area
• Compostable fraction of the municipal waste to
be generated from the labour camps should be
pit composted if possible
• Hazardous waste should be stored in isolated
location in HDPE container only and should be
disposed off through authorized vendors. NOC
should be obtained for disposal of hazardous
waste from MPCB.
27. Hiring of the Construction Labour
• Contractor shall employ local people preferably
for carrying out the construction works of
Contractor KLDC, Third Party Supervision and
monitoring Agency
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 131
embankment
• If the local labour is not available then contractor
shall obtain a letter from the panchayat officials
in this regard and then only can hire labour from
outside
• No child labour shall be allowed at the site
(after appointment) and SPIU/ PMC
28. Setting up of Labour Camp Site
• Labour camp shall be established only if local
labour is not available
• No workforce camps shall be set up at any of
the operational areas. Each workforce is to be
provided with suitable type of rented
accommodation or in the labour camp
established for the project. Transportation facility
shall be provided to workers for commuting
between construction camp and work place.
Pooled transportation facility shall be provided to
workers who opt to stay at their residence.
• Labour camps shall not be established on
agriculture land, vegetated and planted land
area and shall be set up at least at a minimum
distance of 250 m from water body. Approval
shall be obtained from gram panchayat prior
setting up such camp.
• The location, layout and basic facility provisions
of the labour camp and photographs of the
location will be submitted to KLDC for prior
approval before establishing it. Contractor will
comply with the relevant provisions of Building
and other Construction Workers (Regulation of
Employment and Conditions of Services) Act
1996.
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 132
• The contractor will provide and maintain well
ventilated living accommodation and ancillary
facilities for workers in functional and hygiene
manner.
• Minimum Basic facility like fans, first aid, rest
area, sanitation facility & dustbins, fire-safety
measures, cooking area, bathing area and
washing area shall be provided in the camps.
Open urination/defecation shall be strictly
prohibited. Two Mobile toilet with anaerobic
digestion facility shall be provided by contractor.
Contractor shall make arrangement with local
municipal extractor for disposal of night soil.
• Provision of supplying clean and cool drinking
water shall be made at labour camp,
construction camp and work sits for workers. A
mobile drinking water counter/kiosk with
minimum 300 litter capacity and two taps with
bottom tank to collect waste water will be made
close to worksite (say within 100 m of site)
• Provision of LPG shall be made for cooking. Use
of wood as fuel shall be fully prohibited. No open
burning of bio-mass shall be allowed. Separate
cooking area shall be designated if common
mess is not provided.
• Once labour camp is discontinued then site shall
be restored to original condition
• The domestic waste shall be segregated at site
into recyclable and non-recyclable materials.
Recyclable material shall be sold to recyclers
and non-recyclable material shall be send for
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 133
disposal through the local bodies
• The contractor shall take necessary HIV/AIDs
prevention awareness measures will be taken at
labour camps by the contractor including
provision of contraceptives. Every quarter,
HIV/AIDs awareness programme shall be
organised by EHS officer of the contractor.
Contractor will prohibit contractor for use of any
explosive, destruction of trees or disposing of
waste to any water bodies or nearby open lands.
Contractor will be responsible for the action of
his employees.
• Inspection shall be carried out by the
environmental expert of the contractor and
executive engineer of KLDC once a quarter to
ensure availability of minimum facilities at the
camp and sanitation level at the camp. Status
report shall form part of quarterly report from
KLDC to SPIU.
• Daily attendance shall be taken at worker camp
by contractor.
• A crèche facility shall be provided for the
children of worker if the female and male
contracted labour are more than 50.
29. Scheduling Construction Works
• Construction works must not be taken up during
monsoon
• Construction activity shall not be undertaken
during night time
• A schedule of construction (activity wise) along
with time line shall be submitted by the
contractor prior to start of work to the KLDC and
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 134
shall carry out work according to the schedule
submitted
• In case of any deviation a report on the same
shall be submitted to the Kharland and third-
party monitoring agency.
Construction Stage 30. Site Clearance works Contractor KLDC, Third Party
Supervision and monitoring Agency (after appointment)
and SPIU/ PMC
Site Clearance & Grubbing
• Vegetation (bushes, weeds etc) at the site shall
be removed in presence of Environmental
Expert of Contractor and KLDC
• Identified trees (as per joint visit of KLDC
&Contractor and tree cutting permission) for
cutting shall be cut. Cut logs shall be managed
as per the condition given in tree cutting
permission
• No other flora shall be harmed other than
identified and marked vegetation and trees
• No mangrove shall be removed during the
clearing and grubbing process
• Vegetation waste shall be collected and shall be
disposed off at the debris disposal site
• Top material of the embankment shall be
stripped off to the suitable depth as per the
requirement given in DPR prior carrying out
strengthening works
31. Generation of debris from dismantling structures
• Quantity and source of debris to be generated
due to dismantling can be referred from point no
26 of this table.
• Record of debris generated and transported
shall be maintained by contractor
• Electricity poles and service cable to be
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 135
replaced should be handled by MSEDCL for
disposal
• Solar lights to be shifted can be reused and shall
be handed over to Gram Panchayat if cannot be
reused at alternate location
32. Stripping, Stocking and Damage to Top soil and Preservation of top soil
• Embankment is constructed by layering various
grades of soil so top layer of existing
embankment soil may not be fertile and may
also be bit saline so may not be used for
plantation later so this shall be disposed off to
the debris disposal site
• Top soil to be preserved will include top soil from
the sites to eb used as construction camps,
labour camps, debris disposal site & borrow
areas (if any)
• Before beginning the construction of
embankments, the surface area of ground
additionally to be occupied (on field side) shall
be cleared of all roots and vegetable matter and
stripped to a suitable depth as per IS: 4701 -
1982
• (i)Depth of stripping 5.0 to 7.5 cm for soil
containing light grass cover
• (ii) Depth up to bottom of ploughed zone usually
15.0 to 22.5 cm in agricultural land.
• Top soil shall be preserved and reused in turfing
activities if possible, in borrow areas (if any),
bunds or if excess shall be distributed to farmers
for using in the agricultural lands
• Project activities shall be carried out during lean
period and non- monsoon period for minimizing
Contractor Kharland Development Circle (KLDC), Third Party
Supervision and monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 136
loss.
• Top soil shall be stockpiled at the site and shall
be kept covered with tarpaulin cover. Stockpile
will be designed such that the slope does not
exceed 1:2 (vertical to horizontal), and height of
the pile is restricted to 2m. All loose construction
material shall be stored and transported in
covered condition on paved surface
33. Soil Quality • Oil shall be stored on paved surface only and a
storage area shall have containment for
collection of spilled oil. Oil spill kits shall be
available to manage the oil spill.
• All transportation vehicle shall be provided with
the drip pans to prevent soil contamination with
the oil
• Silt fencing shall be provided to prevent washing
away of the embankment and entering of soil
from embankment to creek during construction
phase
• Stone pitching shall be provided on both the
sides of embankment to prevent erosion of the
embankment
• Longitudinal drains and drains near the toe shall
be provided to drain the water from embankment
and prevent washing off of the embankment.
Contractor Kharland Department, Third Party Supervision
and monitoring Agency (after
appointment) and SPIU/ PMC
34. Haulage Road • Contractor will ensure that all construction
vehicle use only the designate haulage road and
no should drift to agriculture field and affect the
standing crops.
• Route markers shall be used for marking the
haulage route.
Contractor SPIU/KLDC/Third Party Supervision
and monitoring Agency (if appointed)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 137
• Haulage road should be restored to original
condition and returned to farmer after
construction work is over.
35. Operation and Management of the construction vehicle and machinery
• All the construction vehicles and machinery shall
meet the prescribed exhaust standards (Bharat
stage emission standards)
• Machinery to be installed close to the
creek/nallah, i.e. for construction of CD works
shall be checked for oil and grease leakage
• Weekly inspection shall be carried out by
Environment and Safety expert of contractor to
confirm fitness of these vehicle and machinery
and following points shall be verified during the
visit
o PUC certificates of wheel or chain mounted machinery/vehicle
o All vehicle and machinery are clean and properly serviced and maintained. Cleaning water shall flow over to waste water collection tank after passing through oil interceptor.
• A log book will be maintained documenting all
fuelling and maintenance events (date, time,
location, condition of site, weather conditions,
amount of fuel on maintenance event, issues
Contractor SPIU/KLDC/Third Party Supervision
and monitoring Agency (if appointed)
36. Transportation of construction material from suppliers/quarry to the site
• Material transportation shall be carried out in
covered vehicles only
• Transportation vehicles shall have valid PUC
certificate
• Transportation vehicle shall strictly follow the
Contractor SPIU/KLDC/Third Party Supervision
and monitoring Agency (if appointed)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 138
speed limits designated for the roads and speed
shall be limited to 10 kmph at the site
• Transportation vehicle shall be properly serviced
and maintained
• Transportation vehicle shall no way block the
villager’s access. • Contractor will ensure that all construction
vehicle use only the designate haulage road and
no shall drift to agriculture field and affect the
standing crops.
• Bamboo shall be used for haulage road
boundary marking.
• Haulage road shall be restored to original
condition and returned to farmer after
construction work is over.
37. Impact on Drainage due to Renovation of Embankment and Reconstruction of Cross Drainage works
• Existing 7 nos of CD work shall be reconstructed
and additional 1 no of CD work will be
constructed to ensure proper drainage across
the embankment
• Arrangement shall be made for prevention of
flow of creek water to agriculture field during
construction of CD works (8 no’s). A ring bund is
proposed to be constructed to prevent the flow
of saline water to the field side
• CD work construction shall not be undertaken
during monsoon. Ring bund in any case should
be dismantled prior onset of monsoon even if
construction of CD work is not completed. New
ring bund shall be constructed after offset of
monsoon prior resuming construction of CD
works
Contractor SPIU/KLDC/Third Party Supervision
and monitoring Agency (if appointed)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 139
• Longitudinal drains shall be provided for flowing
the water from top of embankment to the bottom
to prevent the erosion of embankment
• Gabion wall is proposed to be provided at
sections which are weak and are likely to get
impacted due to heavy/sharp water flow
• Provision for drain shall be made at the toe end
of embankment to drain out the accumulated
water to nearest cross drainage structure.
• The Contractor will ensure that construction
debris, waste and construction material shall not
be disposed or allowed to get spilled to creek or
drainage channel so as not to block the flow of
water of any watercourse/cross drainage
channels.
38. Siltation of Water Bodies • A silt fence (geo textile sheets with bamboos)
shall be provided along the active construction
area or say 1 km, at the base of the
embankment on creek side and around the
stockpiles prior to start of construction works.
The fencing shall be retained till the
embankment up-gradation for activity area is
completed and slopes are stabilized
• Contractor shall not dispose or allow
disposal/spillage of earth or any other
construction material or debris into the
creek/nallah
• All loose construction material shall be stored on
the paved surface and in covered condition
Contractor SPIU/KLDC/Third Party Supervision
and monitoring Agency (if appointed)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 140
39. Slope Protection and Control of Soil Erosion
• The embankment slope shall be stabilized and
protected using appropriate stabilization
methods. Stone pitching is proposed to be
provided for slope stabilization on both creek
side and land side. Stone pitching is preferred
over other like bamboo splits on creek side due
to exposure to saline water and wave action.
• Embankment shall properly be compacted using
the machinery as specified in DPR
• Grass turfing of slopes on land-side shall be
done above HFL/HCL as specified in DPR
• Gabion wall is proposed to be provided in the
weak sections of embankment. These walls will
provide strength to the embankment and will
stabilize the embankment
• Rock toe will be provided in starting and end of
CD works to provide additional strength and
stability
• Geo-textile is also proposed to be laid on the
slopes prior murrum and pitching to prevent to
provide additional strength and stability
• Groynes shall be provided at curve points of the
embankment to prevent scouring of
embankment due to the wave action
Contractor SPIU/KLDC/Third Party Supervision
and monitoring Agency (if appointed)
40. Water Resources, Water Pollution Prevention and Control
Water Resources • Contractor shall ensure use of potable water for
every construction activity. Contractor shall
provide necessary approval regarding water-
supplying agency.
• Water shall be purchased from authorized
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 141
private water tanker suppliers
• Contractor shall obtain and submit copy of
approval of tanker water supplier to KLDC
before start of supply.
• Water tanks and pipelines shall be checked for
leakage on daily basis and any leakage if
detected shall be repaired immediately
• Idle flow of water and taps shall not be allowed
and supervisors at site shall do random
inspection for the same on daily basis
• Workers shall be educated about importance of
water conservation and things they have to
follow for conserving water. Posters shall be
displayed at each water source for water
conservation and preventing wastage
• Run-off from the site collected in sedimentation
tanks shall be used at the site for water
sprinkling. Run-off from curing area also shall be
collected and shall be used for sprinkling, wheel
washing etc.
• Flow of water sprinklers shall be maintained so
as the water is sprinkled as small dots so as
consumption is less, and water pounding will be
prevented
• Curing shall be done by spraying only to
minimize water requirement. Curing shall be
done in early morning and late evening hours to
minimize evaporation loses. Cured structures
can be covered with gunny bags so as to
minimize the evaporation
41. Water pollution from • Construction debris shall be collected from the Contractor KLDC, Third Party
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 142
construction waste and wastewater from the plant site
site and shall be stored on the paved surface
under covered condition
• No construction debris shall be disposed or
allowed to be spilled in the water body
• Construction debris shall be transported to the
debris disposal site on regular basis
• All loose construction material shall be stored on
the paved surface and in covered condition
• Wastewater from the batching plant if
established shall be collected in the tank.
Supernatant water shall be re-used in batching
plant or can be used for dust suppression. Slurry
settled below can be reused in batching plant
• Vehicle service and washing shall be avoided at
the construction site. If vehicle washing if
required than washing effluent at construction
camps shall pass through grease tap to
collection tank. This water shall be used for dust
separation.
• Monitoring of the creek water shall be carried
out every Quarterly from accredited laboratory
Supervision and monitoring Agency (after appointment)
and SPIU/ PMC
42. Water pollution due to mixing of sewage from the labour camps and toilets at plant/construction site
• Wastewater generated from toilets, washing
area and kitchen area in labour camp and toilets
at construction site shall not be discharged into
the creek/nallahs
• Bio-toilets shall be installed at the labour camp
site and construction site area. Sewage
generated will be treated within the bio-toilets
• Water from bathing and kitchen area shall be
passed through the oil and grease chamber and
shall be stored in the septic tank (soak pit is not
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 143
feasible at this site due to high water table level).
This septic tank shall be a concrete tank and
shall be evacuated when filled.
43. Water pollution due to spillage of lubricants and fuel
• Oil and lubricants shall be stored on paved
surface in covered containers with oil collection
pit on one end.
• Oils shall not be stored close to creek or any
drainage channel.
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
44. Air Pollution prevention and Control Dust pollution Emission from construction vehicles, equipment and machineries Emission from running DG sets
• Water shall be sprinkled on embankment site,
construction camp site and on haulage roads for
dust suppression
• All the construction vehicle and machinery shall
be compliant to the emission standards as per
Bharat Stage Emission Standards
• All construction vehicle/machinery shall have
valid PUC certificate
• All construction vehicle/machinery shall be
regularly serviced and maintained and the
records of the same shall be maintained at the
site by contractor
• Low Sulphur fuel shall be used for DG sets
• Stacks based as per the formula (height of the
stake 2 √kVA above DG set if kept in open otherwise above the building height if kept inside
a room) shall be provided with DG sets
• Ambient air quality shall be carried out during
construction phase every quarter from
accredited laboratory.
Contractor
KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 144
45. Noise Level: Noise from the vehicles, equipment and machineries
• All machinery, equipment and machinery shall
comply with the noise standards as specified by
CPCB
• All the machinery equipment shall have inbuilt
noise controlling mechanism such as silencers
and mufflers
• All the machinery, equipment and vehicles shall
be regularly serviced and maintained
• Construction activities shall only be carried out
during the day time (6:00 AM to 10:00 PM)
• Honking shall be prohibited at site
• Noise monitoring shall be carried out during
construction phase near residential areas every
month and quarterly through accredited firm
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
46. Safety
Personal safety measures for labour and other staff at site
• All personal protective equipment shall be
provided for construction worker which includes
safety shoes, safety jacket, helmet, earplugs,
masks and goggles
• Barricading shall be provided for the
embankment with LED lighting on top. All such
barricading and signage shall comply with IRS
SP: 55 (2014) specifications.
• Steel barricading shall be provided on land side
along the habitations abutting the embankment,
i.e. Vithalwadi village and near the school.
Barricading may not be required on land side
other than this location. Bamboos fitted with
geotextile which are proposed to be provided as
stilt fence will work as barricading on creek side
in active area
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 145
• The contractor will make sure that during the
construction work all relevant provisions of the
Building and Other Construction Workers
(regulation of employment and conditions of
services) Act, 1996 are adhered to. The
Contractor will comply with all the precautions as
required for ensuring the safety of the workmen
as per the country' labour regulations and
International Labour Organization (ILO)
Convention No-62 as far as those are applicable
to this contract.
• All work force shall be subjected to an
orientation program to familiarize them with work
requirements, safety practices at work, safe
distances to keep from earth moving equipment,
emergency response etc. to be adopted to
ensure their own safety and that of other
workers and public around operational areas.
• Visitors/officials to worksite are to be provided
with PPEs (such as hard hats and safety boots
& safety jackets) and shall be briefed ongoing
operations on that specific time and related
safety requirement at work site including safe
distances to keep, while at site visit.
• Contractor will ensure that each worker use the
safety vests when on construction site. He will
also ensure availability and use of PPE and
other measures specific to a task as below:
• Hard hat or helmets for all workers, supervising
staff and inspecting official/s entering work site,
plant area, and engaged in loading/unloading
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 146
operations.
• Safety shoes and goggles for all workers
employed for handling of cement, mortar,
concrete, asphalt or for those engaged in
crusher operations.
• Protective eye gear, helmets, gum boots, hand
gloves for all labour/workers at the construction
site.
• Welder’s protective eye-shields to workers who
are engaged in welding works.
• Earplugs to all workers exposed to high noise
levels.
• No smoking and other high-risk areas are to be
provided with warning signage.
• Staff will be given induction training about the
processes and risks involved during the
construction phase and the response plan to be
followed during the case of emergency.
• Work force shall be subjected only to standard
work shifts/hours. Overtime allowances shall be
paid with ceiling limits. Working beyond such
ceiling limits shall be discouraged, even if, so
desired workforce or sub-contractor.
• Safety instruction/guidelines shall be displayed
at all the sites in English and local language
• Provision of Lifeguard and rescue boat shall be
kept at site as the creek runs parallel to the
embankment and there may be accident of
falling in the creek and drowning
• Construction work shall not be carried out during
monsoon period
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 147
• Construction work shall be carried out during
day time only
• Emergency assembly area shall be designated
at the site and same shall be informed to all the
workers
• Workers shall be given training for safe
operation of the construction vehicle and
equipment
• Defensive driving training shall be provided to
drivers of construction vehicle
• Rest areas shall be provided for workers at the
construction site. No worker shall be allowed to
rest in activity area.
• Construction machinery & equipment shall be in
good conditions and shall comply with all safety
conditions
• All the lifting equipment/heavy machinery shall
be properly examined and tested prior usage. All
relevant information shall be known by safety
officer about the load, method of slinging and
attachment points. Heavy lifting machinery shall
be managed as per heavy lifting machinery
management plan
• Gas cylinder if used for the welding works at the
site then cylinders shall be kept upright and shall
be provided with flash back arrestor. Domestic
LPG cylinders shall not be used at site for
welding and other works. Person operating the
gas cylinder shall be provided with PPE
including gloves, goggles and helmet with the
face shields
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 148
• Fire safety measures including buckets filled
with sand and fire extinguishers shall be
provided at the construction camp site, labour
camp site and active construction work area
Risk from electrical equipment
• No open or damaged electrical wires shall be
present at the site. Electrical cables shall be run
in extra plastic conduits
• Install Earth Leakage Circuit Breakers (ELCB) in
all circuits to protect the operators from electrical
hazards
• Keep the main switch box in good condition,
protected from the weather. Install an
appropriately sized ELCB
• Provide good earth or ground connection for all
installations
• Adequate lighting shall be provided for
illumination at site
First aid • First aid-trained personnel shall be available at
site. Tie up with the nearby hospital shall be
made so as emergency can be handled. First
aid facilities shall be developed as per the
Schedule V of BOCWR (Building & Other
Construction Workers Rules)
• A first aid kit shall be provided at the
construction and labour camp site
• A motorized four-wheeler shall be available at
the site to take the injured or sick person to the
nearby hospital
• Hospitals near to the site shall be identified and
tie-ups shall be made with hospitals
• Presence of snakes is confirmed by local people
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 149
in the area. First aid kit also shall carry the
bandages and tourniquet for managing the
snake bite. First aider shall be trained in using
the tourniquet. Anti-venoms can be purchased
and kept with the hospitals identified so as they
can be used in case of emergency.
Signages and hoardings • Effective Safety caution and signage boards
shall be placed at active site in English and local
language
• An information board detailing the name of
project, length of embankment, duration of work,
risks involved and contact persons and
Grievance Redress Mechanism (GRM) shall be
provided at both the ends of the embankment.
47. Contractors Demobilization: Clean-up operations, restoration and Renovation
• At the time of completion of construction,
contractor shall submit demobilization plan
• Clean up and restoration works shall be taken
up by the contractor immediately after
completion of construction
• All the machinery, equipment and vehicle shall
be removed from the site
• All the waste from the camp site, plant site and
construction site shall be removed and disposed
as per the debris management plan given in this
table
• All the temporary structures like the labour
hutment, material storage sheds, rest areas,
fencing etc shall be dismantled and the material
shall be removed from the site
• Sites shall be restored back to the original
condition and shall be handed over to the land
Contractor KLDC, Third Party Supervision and
monitoring Agency (after appointment)
and SPIU/ PMC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 150
owner
• A satisfactory statement shall be obtained from
the land owner by contractor and shall be
submitted to KLDC
• Septic tanks if any developed shall be
dismantled and the pits shall be refilled
• Approval shall be obtained from KLDC for
effective restoration of the site and completion of
demobilization activities.
Operation and Maintenance 48. Monitoring and
Maintenance • KLDC should monitor and maintain the integrity
of embankment, stability of slope and pitching,
condition of the CD works and condition of the
drains
• KLDC should also monitor the compensatory
afforestation carried out in lieu of the tree cut
and ensure survivability rate of at least 70%.
KLDC KLDC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 151
8.4. Consolidated Environmental Management Plan
"Based on the EIA studies conducted and the EMP recommended in this report,
following consolidated EMP has been approved by World Bank for the timely compliance
and monitoring of the project during its construction phase. The consolidated
Envirionmental Management Plan is given in Table 8.2.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 152
Table 8.2 : Consolidated Environmental Management Plan for Saline Embankment-Narvel- Banavale
S.No. Activity/Aspect Measures to be implemented by the Contractor
1. Work Program and Planning
The Contractor’s Project Manager shall be responsible for implementation of EMP and will coordinate the over -all implementation of the said plan. As part of the revised Work Program, within 14 days of delivery of the Letter of Acceptance, the Contractor shall submit an EHSM plan, including method statement and timeline about specific actions that will be taken by Contractor to implement the provisions laid out in the EMP.
2. Appointment of
Environment and Safety Officer
The Contractor shall designate and mobilize the qualified Environment and Safety officer for effective implementation of EMP and ensuring safe operations during construction stage within 30 days from signing the Letter of Acceptance.
3. Joint Verification a. Videography (not using a phone) shall be carried out clearly showing the site conditions and the state of mangroves/ other vegetation within 15 days from signing of the Contract. SPIU and KLDC staff will remain present during this exercise.
b. The Contractor will also submit geo-referenced and digitally date stamped still photographs taken at every 50 meters to SPIU, KLDC and Forest Department clearly showing the chainage and site conditions, including the state of mangroves and other vegetation within 15 days from signing of the Contract.
c. A joint survey with KLDC shall be carried out to demarcate the toe lines on the either side of the embankment with suitable markers to delineate the proposed outer limits of construction.
d. Identification and marking of utilities that are likely to be impacted such as electric poles, trees to be cut, access, Common Property Resources and other utilities to be shifted or re-built shall be done.
e. Once this is done, the Contractor shall submit a request to Kharland Development Circle (KLDC) for a detailed joint site wherein KLDC, SPIU and Mangrove Cell, Forest Department will participate.
f. Based on the regulatory conditions, land availability and any suggestions/recommendations made during the joint visit/s, the proposed alignment/design will be adjusted to minimize adverse impacts on environment and people.
g. The Contractor shall record all findings/proceedings and decisions made. A
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 153
comprehensive report incorporating all aspects (including land and mangroves) will be jointly signed by the Contractor, KLDC and SPIU. A copy of the same shall be submitted to the Forest Department, Govt. of Maharashtra.
4. Obtaining requisite regulatory
permissions and
clearances prior to
start of work as applicable
a. The Contractor, including the Environment and Social Officer and all other key staff should be well informed about requirements of local laws, regulations, and rules in force in State of Maharashtra. This includes applicable environmental laws and regulations, labour laws and safety requirements.
b. Contractor shall obtain permission for cutting of trees, in line with state government rules and norms.
c. Contractor will obtain Consent to Establish and Consent to Operate for setting up of DG sets, Batching Plant (RMC), etc. as required from Maharashtra State Pollution Control Board (MPCB).
d. Contractor should obtain environmental clearance from State or District Environmental Impact Assessment Authority (SEIAA/DEIAA) as the case new borrow areas are identified and opened.
5. Shifting of Utilities a. Contractor based on the joint verification exercise will ensure that the necessary permissions are obtained from concerned departments, including for electrical poles that require shifting for the works under this contract.
b. Contractor shall continue to coordinate with respective departments, as needed during the utility shifting process to avoid unwarranted delays and issue during execution of works.
6. Access to public and private properties
Contractor shall ensure that temporary access to public and private properties are provided during the construction of the embankment and that these are permanently restored after the work in that section is over.
7.
Protection of Mangroves
a. Contractor shall take approval of the concerned Engineer before site clearance to start the construction work.
b. Contractor shall not disturb or cut any mangroves during construction. All mangroves shall be preserved, and the Contractor shall abide by the NOC and conditions of the Forest Department.
c. As required, the Contractor shall propose modifications in design to suit site conditions to the Engineer.
8. Protection of trees and a. Contractor shall take all precautions needed to preserve the trees. All efforts shall be
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 154
vegetation made to prevent damage to trees other than those identified for cutting.
b. Contractor shall identify the number of trees that need to be cut through a joint verification with the KLDC. If any tree needs to be cut, necessary prior permission shall be obtained.
c. Contractor shall undertake tree cutting as per the written instructions of the Engineer and only after obtaining permission from Forest Department or appropriate authority.
9. Construction plan and communication with
community
a. Contractor shall develop time bound construction schedule and submit it to Executive Engineer Kharland Development Circle (KLDC) at least 15 days prior to start of construction work
b. Contractor and Kharland Development Circle (KLDC) shall install a project information board at the start and end of the project site showing name of work, project cost, duration, date of commencement, proposed date of completion, details of grievance redressal mechanism along with contact details of key officials/personnel.
c. Information campaigns shall be planned/designed and implemented in line with provisions made in the price schedule.
10. Setting up construction camp construction camp, or material
storage area,
Batching Plants etc., operational safety,
sanitation, drinking water supply,
a. Contractor shall identify the site/s for setting up material storage area, construction camp, plant and shall notify the Engineer for required approval.
b. Any plant or construction camp site and/or construction material storage site shall be sited at a min. distance of 150 m from water body and 500 m from residential area or any sensitive location like school or hospital. The plant/s shall be located in downwind direction of any residential area.
c. Available barren land shall preferably be used for the establishment of camp/plant site.
d. If usage of this land is not possible then the private land which is currently not being cultivated can be used for the establishment of the plant site with the consent of the land owner.
e. Site shall be marked on the map and the layout of such sites along with the photographs shall be submitted to Kharland Development Circle (KLDC) prior to setting up any such facility to obtain prior written approval.
f. These sites shall be fenced preferably with the sheets so as to minimize the exposure of the public to the dust
g. Establishment and operation of these plants shall be initiated only after obtaining consent to establish and consent to operate from MPCB by the Contractor.
h. Contractor shall ensure all measures for dust control (like sprinkling of water) and
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 155
prevention of water, soil (preventing flow of contaminated water from camp) and noise pollution shall be taken up.
i. Speed limits at site shall be maintained between 15-20 km/hr.
j. Contractor shall ensure parking of vehicles or installation of machineries shall not block the access or public utilities in the project area.
k. Adequate Bio-toilets (for male and for female) shall be provided at construction camp, storage areas and operational areas.
l. The bio toilet must have provision of at least 1000 litres overhead water storage. It shall be well maintained and in usable condition at all the times. It shall be regularly cleaned, and overhead tank replenished as per requirement. Work force shall be oriented to use mobile toilets. No open urination/defecation shall be allowed.
m. Clean and cool drinking water facility shall be available for workers at site.
n. Loose construction materials and waste storage area shall be covered properly.
o. Fuel/Lube Oil shall be stored on concreted floor with spillages and leak collection pits.
p. Oil interceptor shall be provided in vehicle cleaning areas
q. Contractor shall ensure all construction vehicle shall comply with traffic rules and carry PUC certificate.
r. Contractor shall ensure First Aid Kits at the camp in case of any emergency.
s. Contractor shall ensure provision of Fire extinguishers in the fuel storage/ camps.
t. Provision of sprinklers for dust suppression shall be made.
u. Contractor shall ensure regular inspection to confirm fitness of these plants and following points shall be verified during the visit:
o All plants are working in good working condition o Dust pollution control measures are being taken up as per the consent orders
o Noise monitoring shall be taken up to ensure prevention of noise pollution
o Contractor shall ensure Workers safety by providing and use of necessary PPEs
o Contractor shall ensure the maintenance of record including Log book of operation of the plants
o Implementation of all provisions of EMP.
v. Contractor shall ensure that these plant sites are restored back to the original condition after completion of the construction works.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 156
w. Contractor shall ensure all wastes and machinery shall be removed from the site after completion of works. Site shall be made clean and free from any temporary structure.
x. Contractor shall ensure renovation of the site as per the provision of the contract and by providing of a vegetation cover in form of grass and small herbs or as per owner satisfaction.
11. Sourcing of earth and
Borrow Area
Management
a. KLDC shall ensure the proposed borrow areas identified for project works have
permission from the appropriate authority including Environmental Clearance (DEIAA/ SEIAA).
b. KLDC had identified tentative borrow areas at a distance of 18 km i.e. in village Bandhan
and Village Tudal, Mapgaon Gram Panchayat, Alibag Taluk and District Raigad which shall be considered for used.
c. Contractor shall get approval of Kharland Development Circle (KLDC) prior to opening
and closure of every borrow area. Kharland and TPQA shall approve the borrow areas in accordance to the IRC recommended practice for borrow pits (IRC 10: 1961)
d. Contractor shall develop borrow area plan indicating the location and area of the
identified borrow area along with the consent order of land owner, photographs of the area and geographical coordinates of the corners of the borrow areas
e. Finalization of borrow areas for earth and all logistic arrangements as well as compliance
to environmental requirements, as applicable shall be the sole responsibility of the Contractor.
Selection Criteria of Borrow areas is as follows:
a. Contractor shall identify the potential borrow areas and take permission from Executive Engineer before operating any borrow areas.
b. The Contractor shall not start borrowing earth from selected borrow area until the mutual agreement is signed between landowner and Contractor. Copy of the document shall be submitted to Executive Engineer.
c. The Contractor in addition to the established practices, rules and regulation will also consider following criteria before finalizing the locations.
o The borrow area should not be located in agriculture field unless unavoidable i.e.
barren land is not available.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 157
o The borrow pits should not be located along the roads.
o The loss of productive and agricultural land should be minimum.
o The loss of vegetation is almost nil or minimum. o The Contractor will ensure the
availability of suitable earth. The Contractor shall obtain representative samples from
each of the identified borrow areas and have these tested at the site laboratory
following a testing program as approved by the concerned Engineer. It shall be ensured
that the fill material compacted to the required density.
o Planning of haul roads for accessing borrows areas shall be undertaken during this
stage. The haul roads shall be routed to avoid agricultural areas as well as forest areas
as far as possible and shall use the existing village roads wherever possible.
d. Contractor shall not be permitted to borrow areas in forest areas
e. Earth material should be taken from barren land or selected borrow area during lean
period as per IS Code 1498 after taking approval from Executive Engineer.
f. Borrow areas should be dug as per IS code: 4701 and prior approval from the competent authorities must be taken before execution and mutual agreement with the land owners
should be taken by the contractor and ensure the borrow areas should not have any environmental issues like water logging etc.
g. Borrow pits should be drained to avoid stagnation of water and the bottom should be levelled properly / bottom level of borrow pits should be fixed with reference to the
prevailing ground slope towards the nearest natural drainage course.
h. No borrow pits shall be dug within 5m of the toe of the embankment, if the depth of the borrow pit is less than 0.5m it shall be after 5m of the toe of the embankment and if the pit
depth shall be more than 0.5m it shall be 10m of the toe of the embankment or within such a distance from the toe of the bank where a 4:1 hydraulic gradient line cuts the ground surface, which ever more.
i. Borrow pits shall be drained to avoid stagnation of water and the bottom should be
levelled properly / bottom level of borrow pits should be fixed with reference to the prevailing ground slope towards the nearest natural drain based on the site conditions
j. Borrow areas shall be strictly outside CRZ areas
k. Precautions to be taken up if Private Lands are used:
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 158
l. If waste land is not available, then soil from the agriculture fields can be taken with the
consent of the land owners.
m. An agreement shall be formed with land owner indicating the area to be borrowed, the quantity of earth to be excavated, time for borrowing, restoration works and the cost to be
paid to land owner in local language. Borrow areas shall not be constructed near the road side.
n. Contractor shall ensure that borrow area shall be planned so as to minimize the
vegetation loss, no tree cutting is required and shall not be located close to roads (up to 50 m).
General Conditions to be followed
o. Top soil from the borrow area shall be removed up to depth of 15 cm and shall be preserved under covered condition. This soil shall be spread on the borrow area during closure. A 15cm topsoil will be stripped off from the borrow pit and this will be stored in
stockpiles in a designated area for height not exceeding 2m and side slopes not steeper than 1:2 (Vertical: Horizontal).
p. Restoration of the Borrow pits shall be done as per the EC conditions and in case of
private lands it shall be as per willing of the land owner i.e. conversion to aquaculture farms/ farm ponds etc. as per the site conditions.
q. Contractor shall keep records of all the borrow earth and TPQA shall check and verify all
the sources and approvals time to time and if any issues arises it shall be brought to the notice of SPIU
r. The Contractor will keep record of photographs of various stages i.e. before using
materials form the location (preproject), for the period borrowing activities (Construction Phase) and after renovation (post development), to ascertain the pre and post borrowing status of the area.
12. Sourcing of Other
Construction Material
a. Contractor shall ensure all materials used in construction of embankment shall be
purchased from approved quarry suggested by Kharland Development Circle (KLDC).
b. A joint visit may be made by environmental expert of the contractor, Executive Engineer
Kharland Development Circle (KLDC) to verify the quality and suitability of material, environmental approvals and environment management measures at the quarry site.
c. A preliminary survey has been carried out by the Executive
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 159
d. Engineer and identified the quarry and is provided in DPR
e. If extraction shall be done, prioritize sites already permitted by the Mining or concerned department,
f. Contractor shall purchase materials and finalize vendors who have valid permissions.
g. If other sites are necessary and the contractor want to use, let the contractor obtain necessary permission from the concerned regulatory authority and inform Executive
Engineer.
13. Arrangement for construction water
Contractor shall ensure use of potable water for every construction activity. Contractor shall obtained necessary approval regarding water supplying agency.
14. Debris disposal management and setting up debris
disposal site
a. Construction and Demolition wastes need to be disposed in accordance to Construction and Demolition Waste Management Rules, 2016, municipal waste should be managed as per the Solid Waste Management Rules, 2016 and hazardous waste shall be managed
as per the Hazardous and Other Waste Management Rules, 2016
b. A site must be identified by the contractor prior start of construction for disposal of the above-mentioned waste material. This site shall be located minimum 150 m distance from
water body and 500 m from a residential area. This site should be selected only at landward side of embankment.
c. Muck generated from stripping shall be used for construction of the ring bunds after
obtaining consent from the KLDC engineer. Thus, clearance of vegetation followed stripping of the soil should be the first activity to be carried out for the proposed project.
d. The site for waste disposal shall be approved by the Executive Engineer of Kharland Development Circle (KLDC)
e. Contractor shall submit the location, area and photographs of the proposed site to the Kharland Development Circle (KLDC) at least 15 days in advance for their acceptance of the site.
f. Contractor will ensure that the debris are collected and transported to the pre-designated and approved debris disposal site. Records of debris generated and transported should be maintained by contractor.
g. All the waste shall be segregated into recyclable and nonrecyclable waste. Recyclable waste should be sold to authorized vendors and non-recyclable waste should be
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 160
disposed off through local agencies in the area
h. Compostable fraction of the municipal waste to be generated from the labour camps
should be pit composted.
i. Hazardous waste should be stored in isolated location in HDPE container only and
should be disposed off through authorized vendors.
15. Hiring of the Construction Labour
a. Contractor shall employ local people preferably for carrying out the construction works of embankment
b. If the local labour is not available, then contractor shall obtain a letter from the panchayat officials in this regard and then only can hire labour from outside
c. No child labour shall be allowed at the site.
16. Setting up of Labour Camp Site
a. Labour camps shall not be established on agriculture land, vegetated and planted land
area and shall be set up at least at a minimum distance of 250 m from water body. Approval shall be obtained from Gram Panchayat prior setting up such camp.
b. The location, layout and basic facility provisions of the labour camp and photographs of the location will be submitted to Kharland Development Circle (KLDC) for prior approval
before establishing it. Contractor will comply with the relevant provisions of Building and other Construction Workers (Regulation of Employment and Conditions of Services) Act 1996.
c. The contractor will provide and maintain well ventilated living accommodation and
ancillary facilities for workers in functional and hygiene manner.
d. Minimum Basic facility like fans, first aid, rest area, sanitation facility & dustbins, fire-
safety measures, cooking area, bathing area and washing area shall be provided in the camps. Open urination/defecation shall be strictly prohibited. Mobile toilets as per requirement with anaerobic digestion facility shall be provided by contractor. Contractor shall make arrangement with local municipal extractor for disposal of night soil.
e. Provision of supplying clean and cool drinking water shall be made at labour camp, construction camp and work sits for workers. A mobile drinking water counter/kiosk with minimum 300 litter capacity and two taps with bottom tank to collect waste water will be
made close to worksite.
f. Provision of LPG shall be made for cooking. Use of wood as fuel shall be prohibited.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 161
g. Once labour camp is demobilized then site shall be restored to original condition
h. The domestic waste shall be segregated at site into recyclable and non-recyclable materials. Recyclable material shall be sold to recyclers and non-recyclable material shall be send for disposal through the local bodies
i. The contractor shall take necessary HIV/AIDs prevention awareness measures will be taken at labour camps by the contractor including provision of contraceptives. Every quarter, HIV/AIDs awareness program shall be organized by EHS officer of the
contractor. Contractor will prohibit contractor for use of any explosive, destruction of trees or disposing of waste to any water bodies or nearby open lands. Contractor will be responsible for the action of his employees.
j. Regular Inspection shall be carried out by the EHS Officer of the contractor and executive
engineer of Kharland Development Circle (KLDC) to ensure availability of minimum facilities at the camp and sanitation level at the camp. Status report shall form part of quarterly report from Kharland Development Circle (KLDC) to SPIU.
k. Daily attendance shall be taken at worker camp by contractor.
l. A crèche facility shall be provided for the children of worker if the female and male contracted labour are more than 50.
m. Mosquito net shall be provided to workers.
n. First Aid Facilities and periodic health checkup facilities for workers shall be provided.
o. Daily cleaning and sweeping of camp and worker accommodation will be ensured.
p. Labour insurance and labour permit shall be obtained by the contractor and readily
available.
q. Fire extinguisher shall be made available at the camp site.
r. Electrical safety at the camp site will be maintained as per applicable regulations
17. Scheduling
Construction Works
a. Construction works must not be taken up on rainy days.
b. Construction activity shall not be undertaken during night time.
c. A schedule of construction (activity wise) along with time line shall be submitted by the contractor prior to start of work to the Kharland Development Circle (KLDC) and shall
carry out work according to the schedule submitted.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 162
18 Site Clearance Works
Site Clearance and
Grubbing a. Vegetation (bushes, weeds etc.) at the site shall be removed in presence of EHS Officer
of Contractor and Kharland Development Circle (KLDC)
b. No other flora shall be harmed other than identified and marked vegetation and trees
c. No mangrove shall be removed during the clearing and grubbing process.
d. Debris shall be collected and shall be disposed off at the debris disposal site
e. Top material of the embankment shall be stripped off to the suitable depth as per the
requirement given in DPR prior carrying out strengthening works
Generation of debris
from dismantling
structures
a. Quantity and source of debris to be generated due to dismantling shall be documented.
b. Record of debris generated and transported shall be maintained by contractor.
19. Stripping, Stocking and Preservation of Top Soil
a. Embankment is constructed by layering various grades of soil so top layer of existing embankment soil may not be fertile and may also be bit saline so may not be used for plantation later so this should be disposed off to the debris disposal site
b. Top soil to be preserved will include top soil from the sites to be used as construction
camps, labour camps, debris disposal site & borrow areas
c. Before beginning the construction of embankments, the surface area of ground
additionally to be occupied (on field side) shall be cleared of all roots and vegetable matter and stripped to a suitable depth as per IS: 4701 - 1982
(i)Depth of stripping 5.0 to 7.5 cm for soil containing light grass cover
(ii) Depth upto to bottom of ploughed zone usually 15.0 to 22.5 cm in agricultural land.
d. Top soil may be preserved and reused in turfing activities if possible, in borrow areas (if any), bunds or if excess shall be distributed to farmers for using in the agricultural lands
e. Project activities shall be carried out during lean period and non- monsoon period for
minimizing loss.
f. Top soil should be stockpiled at the site and should be kept covered with tarpaulin cover.
Stockpile will be designed such that the slope does not exceed 1:2 (vertical to horizontal), and height of the pile is restricted to 2 m.
20. Soil Quality a. Fuel and Lube Oil shall be stored on paved surface only and the storage area shall have
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 163
containment for collection of spilled oil. Oil spill kits shall be available to manage the oil spill.
b. Well maintained vehicles shall be used for transportation of construction material.
c. Silt fencing shall be provided to prevent washing away of the embankment and entering
of soil from embankment to creek during construction phase
d. Municipal solid waste and debris shall be collected and disposed in environmental sound manner.
e. Stone pitching shall be provided on both the sides of embankment to prevent erosion of the embankment
f. Longitudinal drains and drains near the toe shall be provided to drain the water from
embankment and prevent washing off of the embankment.
21. Haulage Road a. Contractor will ensure that all construction vehicle use only the designate haulage road
and no other route should be followed.
b. Route markers shall be used for marking the haulage route.
c. Haulage road shall be restored to original condition if any damage has happened.
d. Water sprinkling shall be done to suppress the dust emission from the haulage roads.
22. Operation and
Management of the
Construction Vehicle and Machinery
a. All the construction vehicles and machinery shall meet the prescribed exhaust standards
(Bharat stage emission standards)
b. Well maintained vehicles shall be used for transportation of construction material.
c. Weekly inspection shall be carried out by EHS Officer of contractor to confirm fitness of these vehicle and machinery and following points shall be verified during the visit
o PUC certificates vehicle.
o All vehicle and machinery are clean and properly serviced and maintained. Cleaning water shall flow over to waste water collection tank after passing through oil interceptor.
o A log book will be maintained documenting all fuelling and maintenance events
(date, time, location, condition of site, weather conditions, amount of fuel on maintenance event, issues.
23. Transportation of a. Loose/fine materials shall be properly covered with tarpaulin sheet during transportation.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 164
construction material to
the site b. Transportation vehicles shall have valid PUC certificate
c. Transportation vehicle shall strictly follow the speed limits prescribed by respective authority.
d. Transportation vehicle shall be properly serviced and maintained
e. Transportation vehicle shall no way block the villager’s access.
24. Cross Drainage works a. Adequacy of cross drainage shall be ensured during construction phase.
b. Arrangement shall be made for prevention of flow of creek water to agriculture field during cross drainage construction works. Ring bunds are proposed to be constructed for
preventing the flow of sea water to the landward side
c. CD work construction shall not be undertaken during rainy days. Ring bund in any case should be dismantled prior onset of monsoon even if construction of CD work is not
completed. New ring bund shall be constructed avoiding rainy days during monsoon prior to resuming construction of CD works, if any is left.
d. The Contractor will ensure that construction debris, waste and construction material shall
not be disposed or allowed to get spilled to creek or drainage channel so as not to block the flow of water of any watercourse/cross drainage channels.
25. Siltation of Water
Bodies a. A silt fence shall be provided at the base of the embankment, continuously along the
creek side, as needed on the landward side and around the stockpiles prior to start of construction work. The coco log silt fencing shall be generally retained even after the works are over except in small lengths if so directed by the Engineer-in-charge.
b. Contractor shall not dispose or allow disposal/spillage of earth or any other construction
material or debris into the creek/nallah.
26.
Slope Protection and
Control of Soil Erosion
a. The embankment slope shall be stabilized and protected using appropriate stabilization
methods. Stone pitching is proposed to be provided for slope stabilization on both creek side and land side.
b. Embankment shall properly be compacted using the machinery as specified in DPR
c. Gabion wall is proposed to be provided at sections having mangroves presence close to the embankment or where bund is eroded as indicated in the strip maps.
d. Geo-textile is also proposed to be laid on the slopes prior murrum and pitching to prevent
to provide additional strength and stability.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 165
27. Water Resources, Water Pollution Prevention and Control
Water Resources a. Water shall be purchased from authorized private water tanker suppliers
b. Contractor shall obtain and submit copy of approval of tanker water supplier to Kharland
Development Circle (KLDC) before start of water supply.
c. Water tanks and pipelines shall be checked for leakage on daily basis and any leakage if leakage detected should be repaired immediately
d. Idle flow of water and taps shall not be allowed and supervisors at site should do random
inspection for the same on daily basis
e. Posters shall be displayed at each water source for water conservation and preventing
wastage
f. Flow of water sprinklers shall be maintained so as the water is sprinkled as small dots so as consumption is less, and water pounding will be prevented
g. Curing shall be done by spraying only to minimize water requirement. Curing shall be done in early morning and late evening hours to minimize evaporation loses. Cured structures can be covered with gunny bags so as to minimize the evaporation
Water pollution from
construction waste
and wastewater from
the plant site
a. Construction debris shall be collected from the site and shall be temporarily stored and disposed of all pre-approved waste disposal plan.
b. No construction debris shall be disposed or allowed to be spilled in the water body
c. Vehicle service and washing shall be avoided at the construction site. If vehicle washing if required than washing effluent at construction camps shall pass through grease tap to
collection tank and disposed in environmentally sound manner.
Water pollution due to
mixing of sewage from
the labour
camps and toilets at
plant/construction
site
a. Wastewater management plan shall be prepared by the contractor. Wastewater generated from toilets, washing area and kitchen area in labour camp and toilets at
construction site shall not be discharged into the creek/nallahs.
b. Bio-toilets shall be installed at the labour camp site and construction site area. Water from bathing and kitchen area shall be passed through the oil and grease chamber and
disposed as per norms.
Water pollution due to
spillage of lubricants a. Oil and lubricants shall be stored on paved surface in covered containers with oil
collection pit.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 166
and fuel b. Fuel/Lube Oils shall not be stored close to creek or any drainage channel.
28 Air Pollution prevention
and Control a. Water shall be sprinkled on embankment site, construction camp site and on haulage
roads for dust suppression.
b. All the construction vehicle and machinery shall be compliant to the emission standards.
c. All construction vehicle/machinery shall have valid PUC certificate
d. All construction vehicle/machinery shall be regularly serviced and maintained and the
records of the same shall be maintained by contractor.
e. Stacks based as per the formula (height of the stake 0.2 √kVA above DG set if kept in open otherwise above the building height if kept inside a room) shall be provided with DG sets
f. Ambient air quality monitoring shall be carried out as per Environmental Monitoring Plan
during construction phase through accredited laboratory.
29. Noise from vehicles, equipment and
machineries
a. All equipment and machinery shall comply with the noise standards as specified by CPCB.
b. All the machinery and equipment shall have inbuilt noise controlling mechanism such as acoustic enclosure/silencers/mufflers, etc
c. All the machinery, equipment and vehicles shall be regularly serviced and maintained
d. Construction activities shall only be carried out during the daytime.
e. Honking shall be prohibited at site
f. Ambient noise monitoring shall be carried out as per Environmental Monitoring Plan during construction phase through accredited laboratory.
30 Safety
Personal safety measures for labour and other staff at site
a. All personal protective equipment shall be provided for construction workers which
includes safety shoes, safety jacket, helmet, earplugs, masks and goggles
b. Embankment construction site shall be properly barricaded. Steel barricading shall be provided on land side for length of 250 from 0 chainage near the habitat. After this
barricading may not be required on land side. Bamboos fitted with geotextile may be provided as barricading on creek side in active area.
c. The contractor will make sure that during the construction work all relevant provisions of
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 167
the Building and Other Construction Workers (regulation of employment and conditions of services) Act, 1996 are adhered to. The Contractor will comply with all the precautions as
required for ensuring the safety of the workmen as per the country' labour regulations.
d. All work force shall be subjected to an orientation program to familiarize them with work requirements, safety practices at work, safe distances to keep from earth moving
equipment, emergency response etc. to be adopted to ensure their own safety and that of other workers and public around operational areas.
e. Visitors/officials to worksite are to be provided with Personal Protective Equipment
(PPEs) (such as hard hats and safety boots & safety jackets) and shall be briefed ongoing operations on that specific time and related safety requirement at work site including safe distances to keep, while at site visit.
f. Contractor will ensure that each worker use the safety vests when on construction site.
Contractor will also ensure availability and use of PPE and other measures specific to a task as below:
g. Hard hat or helmets for all workers, supervising staff and inspecting official/s entering
work site, plant area, and engaged in loading/unloading operations.
h. Safety shoes and goggles for all workers employed for handling of cement, concrete, etc..
i. Protective eye gear, helmets, gum boots, hand gloves as applicable for all labour/workers
at the construction site.
j. Welder’s protective eye-shields to workers who are engaged in welding works (if any).
k. Earplugs to all workers exposed to high noise levels.
l. No smoking and other high-risk areas are to be provided with warning signage.
m. Staff will be given induction training and tool box talk about the processes and risks involved during the construction phase and the response plan to be followed during the case of emergency.
n. Work force shall be subjected only to standard work shifts/hours. Overtime allowances
shall be paid with ceiling limits. Working beyond such ceiling limits shall be discouraged, even if, so desired workforce or subcontractor.
o. Safety instruction/guidelines shall be displayed at all the sites in English and local
language
p. Provision of Lifeguard and rescue boat shall be kept at site as the creek runs parallel to
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 168
the embankment and there may be accident of falling in the creek and drowning
q. Emergency assembly area shall be designated at the site and same shall be informed to
all the workers
r. Workers shall be given regular training for safe operation of the construction vehicle and
equipment
s. Defensive driving training shall be provided to drivers of construction vehicle
t. Rest areas shall be provided for workers at the construction site. All the lifting
equipment/heavy machinery shall be properly examined and tested prior usage. All relevant information shall be known by safety officer about the load, method of slinging and attachment points.
u. Gas cylinder if used for the welding works at the site then cylinders shall be kept upright
and shall be provided with flash back arrestor. Domestic LPG cylinders shall not be used at site for welding and other works. Person operating the gas cylinder shall be provided with PPE including gloves, goggles and helmet with the face shields
v. Fire safety measures including buckets filled with sand and fire extinguishers shall be provided at the construction camp site, labour camp site and active construction work area.
Risk from electrical equipment
a. No open or damaged electrical wires shall be present at the site. Electrical cables shall be laid into the ground in shockproof material or taken over head. Cables shall be run in
extra plastic conduits
b. Install Earth Leakage Circuit Breakers (ELCB) in all circuits to protect the operators from electrical hazards
c. Keep the main switch box in good condition, protected from the weather. Install an
appropriately sized ELCB
d. Provide good earth or ground connection for all installations
e. Adequate lighting shall be provided for illumination at site
f. All three phase Electrical Panels and electrical motors, DG set, etc shall be double
earthed and provided danger signage with bone and skull.
First aid a. First aid trained personnel shall be available at site plant and camp site. Tie up with the nearby hospital shall be made so as emergency can be handled. First aid facilities shall
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 169
be developed as per the Schedule V of BOCWR (Building & Other Construction Workers Rules)
b. A first aid facility with snake bite kit with tourniquet shall be provided at the construction and labour camp sites.
c. A motorized four-wheeler shall be available at the site to take the injured or sick person to
the nearby hospital.
d. Hospitals near to the site shall be identified and tie-ups shall be made to deal with an
emergency.
e. Sensor based electronic snake repellents shall be installed at the labour accommodation and camp site. Snake repellent (non-toxic) may be sprayed around active works sites.
Signage and hoardings
a. Adequate in numbers and Effective Safety caution and signage boards shall be placed at active site in English and local language.
b. An information board detailing the name of project, length of embankment, duration of
work, risks involved and contact persons and Grievance Redress Mechanism (GRM) shall be provided at both the ends of the embankment
31 Clean-up operations, restoration and
renovation
a. Contractor shall submit demobilization and restoration plan to be implemented after
completion of construction works.
b. All work sites and areas under temporary use (including construction and labour camps,
plant sites, haul roads and borrow areas) shall be restored/ rehabilitated to a better condition (if not at least to its original condition) and to the satisfaction of the Engineer and land owner upon completion of construction work by the Contractor.
c. Clean up and restoration works shall be taken up by the contractor immediately after
completion of construction.
d. All the machinery, equipment and vehicle shall be removed from the site.
e. All the waste from the camp site, plant site and construction site shall be removed and disposed as per the debris management plan given in this table
f. All the temporary structures like the labour hutment, material storage sheds, rest areas,
ring bund, fencing etc. shall be dismantled and the materials shall be removed from the site
g. Borrow areas shall be rehabilitated and shall be handed over to the land owner.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 170
h. A NOC shall be obtained from the land owner by contractor and shall be submitted to
Kharland Development Circle (KLDC)
i. Septic tanks if any developed shall be dismantled and the pits shall be refilled
j. Approval shall be obtained from Kharland Development Circle (KLDC) for effective
restoration of the site and completion of demobilization activities.
32 Chance finds and
Archaeological/ Heritage Value
No ASI sites are near to the proposed project site, however for chance finds during construction, the following shall apply:
a. Any fossils, coins, articles of value of antiquity, structures and other remains or archaeological interest discovered on the site shall be the property of the Government and shall be dealt with as per provisions of the Ancient Monuments, Archaeological Sites
and Remains Act, 1958 and other applicable rules/regulations.
b. The Contractor will take reasonable precautions to prevent his workmen or any other persons from removing and damaging any such article or thing. The contractor will,
immediately upon discovery thereof and before removal inform the Employer and the Environmental Specialist of PMU of such discovery and carry out the Engineer’s instructions for dealing with the same, waiting which all work shall be stopped. The Employer/Engineer will seek direction from the State Archaeological Survey of India (ASI)
Circle before instructing the Contractor to recommence the work in the site.
33 Reporting The required documentation related guidance and aspects for monthly reporting are described in EMP. The Contractor needs to ensure that these reports are submitted within five days of each calendar month, starting right after the Contract has been signed.
34 Liabilities Any liability arising out of Contractor’s agreement with landowners/local people/gram panchayat (including those related to temporary use of land, water extraction and disposal of debris) shall be the sole responsibility of the Contractor. Any such claim shall be settled by the
Contractor.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 171
8.5. Environmental Monitoring Plan
Environmental monitoring should be conducted for the key indicators which are likely to
be affected during construction & operation stage of the project and is given in Table
8.2. Formats for the air and noise monitoring are attached as Annexure 8.2.
Table 8.3 : Environment Monitoring Plan
S. No.
Key Indicator
s
Location of
Monitoring
Frequency of
Monitoring/
Observations
Parameters to be
monitored/Observed
Responsibility
Unit Rate
Tentative
Cost
Construction Phase 1. Air Quality Construct
ion sites Once in a Quarter
from accredited
Lab-2 samples
PM10, PM2.5, SO2, NO2, CO
EHS officer of Contractor
5000/sample
40,000
2. Noise levels
Construction sites
Once in Quarter
from accredited
Lab-1 sample
Day time & Night time levels
EHS officer of Contractor
2500/sample
10,000
3. Creek Water Quality
Creek along the Embankment
once in Quarter
from accredited
Lab-1 sample
pH, Salinity, BOD, COD, TSS
EHS officer of Contractor
5000/sample
20,000
4. Drinking Water
Drinking Water for labour
once in Quarter
from accredited
Lab-1 sample
As per IS:10500
EHS officer of Contractor
5000/sample
20,000
5. Occupational health & Safety
Construction sites, material storage sites
Daily Availability and use of Barricades, Use of PPE by workers, Availability of firefighting equipment, analysis of incidents/accidents if any
EHS officer of Contractor
Lumpsum
10,000
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 172
6. Community Issues
Project area
Monthly Analysis and action taken for issues raised by community time to time.
EHS officer of Contractor
7. Solid Waste Disposal
Construction sites, labour camps, site office & Storage Yards
Monthly Compliance to EMP requirements with regard to storage, transportation & disposal of Debris, excess earth and other waste.
EHS officer of Contractor
8. Construction vehicles
Construction sites and material storage sites
Monthly Availability of Safety kit, first aid kit, maintenance &service records, DL (driving license), PUC, drivers training records, driver awareness
EHS officer of Contractor
9. Sanitation Construction sites, labour camps, site office & Storage Yards
Monthly Condition of toilets, availability of water in toilets, provision of septic tank, availability of clean drinking water
EHS officer of Contractor
10. Labour camp
Labour camp-Conditions of facilities- Hygiene and sanitation
Monthly Compliance to EMP requirements regarding Hygiene and Sanitation at labour camps (clean fuel, toilets, septic tanks, ventilation, illumination, storm water drainage)
EHS officer of Contractor
11. Constructi Construct Monthly Availability of EHS officer of
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 173
on Camps -Fuel storage area
ion sites/Camps
fire-fighting equipment, spill oil collection pits/interceptors
Contractor
Operation Stage 1 Communit
y Issues Project Area
Six Monthly
Grievance readdress box and interaction with community to identify their issues, if any being faced due to project development
Concerned Executive Engineer – Kharland Development Circle (KLDC)
-- Under KLDC scope
2 Compensatory Plantation
Plantation location
Quarterly 70% survival rate
Concerned Executive Engineer – Kharland Development Circle (KLDC) / Forest Department/District Collector
-- Under KLDC scope
8.6. Institutional Framework for Implementation of EMP
Environmental and social management plan will be implemented by EHS officer of the
Contractor under direct reporting to Executive Engineer of KLDC. EHS cell of SPIU will
supervise the KLDC and contractor for EMP / SMP and RAP effective implementation
Third Party Quality Assurance (TPQA) agency will be assigned the task of effective
monitoring and advisory for implementation after appointment. Roles and Responsibility
of the Key Staff is defined in following sections below.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 174
Figure 8.1 : Institutional Mechanism for EMP Implementation-Construction Phase
Project Director &
Superintending Engineer,
Kharland Department, Circle
Thane
Executive Engineer, Kharland
S& I Division, Pen, Dist Raigad
Secretary Water Resources
Department
Chief Engineer Water
Resources Department, Konkan
Region
Environment and
Social Expert-
Contractor
Sub Division Engineer, KLDC
sub division, Pen
SPIU (Environment
and Social Experts)
World Bank
State Project
Steering
Committee
National Steering
Committee PIU/NDMA
PMC
Experts/TPQA
Project Director-
Contractor
Safety Officer-
Contractor
Through KLDC
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 175
A. Roles & Responsibilities of the Executive Engineer l-KLDC
Roles and responsibilities of Executive Engineer KLDC Pen includes the following
1. To incorporate the EMP in the contractors’ bid document and to specify the condition that enclosed EMP shall be mandatorily followed by contractor while undertaking the specified scope of work
2. To ensure that the suggested EMP are being implemented by contractor during project implementation and ensure day to day monitoring of the EMP
3. To obtain the updated EMP from contractor in case of any diversion, change in proposed mitigation measure etc
4. To ensure suggested safety practices are being followed at the site
5. To ensure all regulatory approvals required for the projects are taken and being renewed time to time
6. To ensure compliance is being done to the conditions specified in consents issued, World Bank guidelines and other rules & regulation of GoI
7. To ensure effective grievance readdress system is implemented by contractor at the site during construction & operation stage
8. To attend the SHE meetings organized by the contractor every month and to review their records
9. To review the SHE reports sent and submitted by contractor
10. • To review the accidents records and to the accidental reports submitted by contractor and to analyse the root cause of each of the accident
11. To ensure that contractor maintains safe working environment at the site and gives safety the priority
12. To train the staff to handle emergency conditions, giving first aid treatments and handling the firefighting equipment
B. Roles & Responsibilities of the Contractor
Roles and responsibilities of EHS personnel of Contractor includes the following
1. Implementation of EMP provisions and will coordinate its over-all implementation. Immediately after mobilization and as part of the Work Program, the Contractor shall submit a plan including method statement and timeline about specific actions that will be taken by him to implement the provisions laid out in the EMP
2. Contractor shall update the EMP document if any proposed condition or measure is changed and updated document shall be submitted to monitoring agency as well as the implementation agency (KLDC)
3. To mobilize qualified and experienced Environment and Safety Officers, who shall support the Project Manager in the day-to-day implementation of activities stated in the EMP
4. To fully inform himself of the requirements of the local Laws, regulations and rules in-force in the State of Maharashtra, especially with respect to local employment laws, licensing requirements and environmental regulations
5. The contractor shall obtain all requisite statutory clearances for setting-up construction camp including labour camp; plants and equipment; water extraction and opening/use of material sources. The contractor shall abide by all conditions laid out in the said clearances. This includes:
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 176
a. Consents for establishment and operation of camps/plants from the MPCB.
b. Submit plan for water sourcing.
c. PUC certification for all vehicles/equipment used for/during construction.
6. The Contractor shall consult and obtain written consents of landowners (individual/ panchayat/local urban authority/govt. agency) for temporary use of land for all construction related activities including:
a. Setting-up and operation of construction and labour camps.
b. Disposal of debris and other waste material in line with EMP conditions.
c. Haulage road
7. The Contractor shall implement all precautionary measures for prevention of pollution from the entire project site as per the requirements/standards of latest/applicable environmental laws and regulations issued by the Ministry of Environment and Forest and Climate Change (MoEF&CC), Govt. of India; Central Pollution Control Board and Maharashtra State Pollution Control Board apart from those stated in this Environmental Management Plan. All apparatus and material supplied, and all work carried out shall comply in all respects with the requirements of all Regulations and Acts in force in the country and state in particular of the Employer as are applicable to the Contract Works.
8. The Contractor shall be responsible for applying for all necessary licenses; including Workmen’s’ Permits and Certificates of Competency for Supervisors and for the payment of all necessary fees associated with such licenses and approvals
9. Contractor shall be responsible for carrying out environmental monitoring at the site as per environmental monitoring plan given in the EMP. Contractor shall environmental monitoring report to the KLDC/implementation agency every month and TPQA shall verify and submit to SPIU/ PMC
10. Contractor shall comply with all the measures and provision given in EMP and prepare a compliance report for the same and shall submit it to the implementation agency (KLDC) Quarter monthly.
11. All work sites and areas under temporary use (including construction and labour camps, plant sites, etc) shall be restored/rehabilitated to a better condition (if not at least to its original condition) and to the satisfaction of the Engineer and the land owner/s upon completion of construction work by the Contractor
12. All liabilities as per the Contractor’s agreement with the landowners/gram panchayat (including those related to temporary use of land and disposal of debris) shall be settled and certified before closure of the work by the Contractor
13. Project Information Board/s showing the name of work, project cost, duration, date of commencement, date of completion, executing agency and contract telephone numbers for filing a grievance etc. shall be displayed prominently in both English and in vernacular.
14. Before commencing construction, the Contractor in consultation with Executive Engineer KLDC-Pen, would share information with local people about the type of activities; proposed work schedule; planned diversions and/or partial closures; utility shifting/demolition and reconstruction of crematorium.
15. The time bound construction schedule shall be prepared prior to initiation of works. It shall be submitted for Engineer’s approval at least 15 days prior to initiation of works on the ground.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 177
16. Before initiating works, site clean-up and removal of all waste materials/debris lying within operation shall be ensured. This will be repeated before each work segment is opened-up for construction.
17. No tree cutting is to be carried out without the written instruction from the Employer, who in turn will ensure that relevant regulatory permission/s (including those from Forest Department or District Administration, as required) are obtained prior to cutting of such trees.
B. Roles & Responsibilities of the Environmental Specialist of SPIU as per ESMF
Roles and responsibilities of Environmental specialist of SPIU includes the following
• Coordinate the preparation of environmental screening report of project sites assessments, Preparation of site-specific environment management plans (EMP)for selected subprojects;
• Capacity building of staff, contractors, stakeholders and consultants (wherever detailed Environmental Impact Assessments (EIAs) are taken up) on environmental safeguard issues, practices and procedures to be followed;
• Organizing training for line departments (Kharlanad) on ESMF / EMP implementation
• Ensuring appropriate application of the ESMF to all components and sub-projects.
• Identifying and providing oversight to other consultants who may be deployed to carry out sub-project specific EAs and EMPs of sub-projects (wherever required);
• Prepare information, communication, and education strategy to enable proper conduct of stakeholder consultations and documenting the implementation of EMPs;
• Detailing all the environmental laws and regulations of the state and national government which will apply to specific sub project activities;
• Liaising with various State line departments & other implementing agencies to provide necessary advice on environmental matters;
• Coordinating with MoEF& C.C, State-level regulatory authorities for obtaining environment clearances in a timely manner as per the site conditions;
• Periodic site visits to ensure that environmental requirements in the ESMF are being followed during implementation of projects activities by the Line departments and contractors, identify shortcomings and advise on the remedial measures.
• Preparing and / or providing necessary inputs to project quarterly progress reports on environmental matters pertaining to ESMF implementation;
• Supporting hiring of external environmental auditors where appointed by the PIU’s and coordinating the conduct of these audits as per the ESMF requirements. Oversee the working of the third-party auditors for social and environment compliance, including review of:
• the audit plan,
• the results and the exceptions of the audits and recommended corrective action
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 178
C. Roles & Responsibilities of the Social Specialist of SPIU as per ESMF
Roles and responsibilities of Social specialist of SPIU includes the following
• The consultant will assist the state level PIUs, their line departments, Implementing Agencies (IAs) and non-governmental organizations (NGOs) engaged in the project in community mobilization, preparation, and implementation of resettlement plans in accordance with the agreed ESMF;
• Assist the above stakeholders in the preparation and implementation of RAP for sub-projects which trigger adverse social concerns for the Project Affected People (PAPs);
• Carry out wherever required an initial poverty and social assessment, sample socio-economic survey, and detailed inventory of affected assets and losses and disclosure of the sub-project Resettlement Plan to the affected persons;
• Provide guidance to line departments/implementing NGOs in preparation of information materials related to resettlement, consultation with PAPs on resettlement/relocation options and finalization of individual entitlements, verification, and delivery of compensation and allowances, house reconstruction (if required) prior to dispossession or displacement;
• Wherever land acquisition issues are involved, liaise with District Collectors and relevant authorities to expedite land acquisition process and assist in finalizing estimates of compensation, extend assistance to PIU and line departments in effectively addressing the grievances of the PAPs in consultation with Grievance Redressal mechanisms;
• Monitor all land acquisition and resettlement related activities;
• Prepare monthly progress reports highlighting implementation progress, issues/constraints that require decisions by the PIUs and other agencies involved.
D. Roles & Responsibilities of the PMC
Roles and responsibilities of PMC are given below
• Support the SPIU in preparing the audit plan
• Prepare compliance report for sub-project activities with ESMF guidelines and other statutory requirements as applicable through scheduled or unscheduled audits
• Conducting random field visits especially at the environmentally or socially sensitive areas
• Review the performance of the project through an assessment of periodical monitoring reports submitted by the line department (MSEDCL), TPQA on request of SPIUs.
• Share audit findings with the SPIU to aid in timely decision making and adopting appropriate mitigation action if necessary.
E. Third Part Quality Control Audit (TPQA) Roles and Responsibilities –
Roles and Responsibility of TPQA are defined below
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 179
• to assist the State Project Implementation Unit (SPIU) in maintaining the quality standards of the works by independent assessment/audit of quality of works at various stages of construction of Saline Embankment
• Providing Orientation training to the SPIU and Line Agency staff in improving their Engineering/ Technical/ Managerial skills.
• Assess and report on the compliance with the requirements of environmental and social safeguards in the form of Environmental Management Plans and Resettlement Action Plan.
8.7. Trainings and Capacity Building
The staff and workers at the site shall be given environmental trainings to enhance
their understanding of EMP requirements and ensure effective implementation of
EMP. Both Contractor /KLDC shall organize such training for staff & workers. These
trainings shall be organized by contractor through TPQA shall organizing the
trainings.
• Training for usage of personal protective equipment
• Training for usage of fire-fighting equipment
• First aid training including protection from Snake bites
• Training for implementation of EMP
• Training for protection of working near water body
8.8. Reporting
Following reporting schedule is recommended.
• The contractor shall submit the monthly EMP compliance report including
various aspects such as material sourcing, waste disposal, compliance to
statutory conditions, incident and accident public grievances, work progress,
to Executive Engines KLDC, and KLDC shall forward the reports to SPIU and
SPIU with the support of PMC shall review the reports
• TPQA shall undertake periodical Audits and provide orientation including
status of EMP and SMP and RAP implementation and submit periodical
reports to SPIU and PMC shall verity its reports and submit a quarterly report
to SPIU on EMP compliance status.
• SPIU environment and social expert supported by PMC/TPQA will submit
progress reports to SPIU Project Director and PIU, World Bank. Reporting
frequencies shall be as per ESMF as defined below in Table 8.3.
Table 8.4 : Reporting Schedule
S.No.
Particulars Frequenc
y
Reporting Responsibilit
y
Monitoring
responsibility
Applicability to this sub-project during project
implementation
1
ESMF Compliance/Status Report, including screening results,
Monthly/ Quarterly
SPIU, Environmental
and Social Experts
SPIU, Project Director
and PMU,
Yes
(Screening stage is completed)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 180
S.No.
Particulars Frequenc
y
Reporting Responsibilit
y
Monitoring
responsibility
Applicability to this sub-project during project
implementation
status of conduct of EIA/SIA and actions taken for compliance
Environmental and
Social Specialist
s
2 Environment and social site visit report
Quarterly
SPIU, Environmental
and Social Experts
SPIU, Project Director
and PMU,
Environmental and
Social Specialist
s
Yes
3 Regulatory clearances
Quarterly
SPIU, Environmental
and Social Experts
SPIU, Project Director
and PMU,
Environment
Specialist
Yes
4
Verification of land to be acquired and status of land acquisition
Monthly SPIU, Social
Expert
SPIU, Project Director and PIU,
Social Expert
Yes, for compensation to be
given to the land owners for the structures to be affected. Also
status of voluntary donation of land
should be reported
5 Distribution of entitlements and assistances
Monthly SPIU, Social
Expert
SPIU, Social Expert
Not applicable
6 Community consultations
Quarterly
SPIU, Environmental
and Social Experts
SPIU, Project Director
and PMU,
Environmental and
Social Specialist
Yes
Also status of shifting the community
properties shall be submitted
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 181
S.No.
Particulars Frequenc
y
Reporting Responsibilit
y
Monitoring
responsibility
Applicability to this sub-project during project
implementation
s
7 Grievance redressal
Monthly/ Quarterly
SPIU, Social Expert
SPIU, Project Director
and PMU,
Environmental and
Social Specialist
s
Yes
Source: ESMF
8.9. Documentation, Updating and Record Keeping
The following reference documents shall be maintained and available with contractor
and SPIU for implementation at construction site
4. Environmental Management Plan (EMP), Environment and Social
Management Framework (ESMF)
5. Environmental Standards
6. SoPs (Standard Operating Procedures) and Method Statements for each
project activity (to be prepared by contractor and submitted to KLDC)
The EMP should be updated regularly based on change in regulatory requirements,
WB /IFC EHS guideline and finding of annual independent audit findings.
The following records shall be maintained at the site
10. Records on health check-ups
11. Records of accidents
12. Records of entry/exit of the vehicle at the site and material transportation by
each vehicle
13. Record of debris disposal with date, quantity and location
14. Records of training & mock drills
15. Records of equipment and vehicle inspection and maintenance
16. Records of number of PPE and rejection of PPE
17. Records of grievances (received & closed)
18. Environmental monitoring reports
8.10. Mechanism for Feedback and Adjustments
As part of the feedback mechanism, KLDC, Pen Division and TPQA shall monitor
project compliance based on monitoring reports, audit and inspection reports with
respect EMP, EMoP and applicable laws, rules and regulations. KLDC will report to
SPIU/PMC on a quarterly basis. In case, any deviation from the contract
requirements with respect to proposed EMP is observed, the same shall be corrected
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 182
within a fortnight through contractor and TPQA and records maintained for the same.
KLDC will also verify the facts reports through periodic site visits. If required
SPIU/PMC shall verify the facts through site verification.
Public involvement shall be encouraged and ensured throughout the lifecycle of the
project. The KLDC Pen Division shall gather and maintain information on any
damage or public concern that may be raised by the local people, NGOs and local
authorities. While immediate solutions are to be worked out with the help of
contractor, a detailed report will be submitted to the SPIU for information or detailed
consideration. The KLDC, Pen Division and TPQA shall be responsible to bring it to
the notice of the SPIU/PMC. Resulting decisions shall be communicated back to
KLDC and TPQA and contractor for correction and future implementation.
8.11. Regulatory Clearances /Permission Required
Statutory clearances will be obtained for any project activity/component wherever
found applicable. A regulatory framework has also been prepared detailing about the
NOC/permits to be obtained. Certain permits required are consent to
establish/operate from State Pollution Control Board for setting up any plant,
appropriate permission for opening borrow areas and quarry materials, tree cutting
permission from forest department, etc. All such permits are supposed to be obtained
by the contractor who shall obtain it before setting up of any facility attracting these
permission
8.12. Grievance Readdress System
The Grievance Redress Mechanism (GRM) will have two tier structure. First tier will
be at KLDC – at its Divisional office at Pen level and second tier at SPIU level. The
Executive Engineer of KLDC will be responsible to address the concerns of the
aggrieved person at first stage. KLDC will designate a dedicated email, phone
number for receipt of grievances. A drop box will also be installed at Kharland Office
and at construction work site with lock and key. Drop box shall be opened in
presence of Contractor, KLDC and TPQA and the grievances will be lodged in the
grievance register and a specific number will be allotted to each grievance on its
receipt. The Sub-Division Engineer and Executive Engineer, Pen Division will
analyse the grievance received through interaction with contractor EHS officer and
the contractor will also visit the site to verify the complaint. District Collector or his
deputed representative shall be member of GRM Cell and any complaint / grievance
is to be heard in his presence who shall facilitate the redressal of such heard
grievances, if any. He/she will also initiate corrective preventive action as may be
required. The corrective preventive action and supervision responsibility will be well
defined for a time bound action by contractor and closer report by executive
engineer. The response to the complaint with resolution will be communicated back
to the aggrieved person within 15 days. In case, grievance cannot be resolved at
KLDC level, then it will be escalated to SPIU level for further resolution. SPIU will put
up this to Grievance redress committee comprising District Collector or his deputed
representative, Sub Division Officer Kharland & Executive Engineer Kharland Pen,
Superintending Engineer, Chief Engineer Water Resources Department and EHS
Officer SPIU who will evolve the action plan to resolve the complaint. They may invite
the complainant for discussion and consultation if required.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 183
Any aggrieved person can send written communication to KLDC through email or
using other modes of communication like phone call or drop his/her complain to drop
box (to be installed at Kharland Office and Work site). The GRM will be displayed at
active site along with name of Executive Engineer Kharland_ Pen, dedicated email
and phone number.
Figure 8.2 Grievance Readdress Mechanism-Construction Phase
8.13. Environmental Management Budget
Budget for environmental management both during construction and operation phase
is given below in Table 8.4.
Grievance Readdress Committee (Sub Division Officer and Executive engineer Kharland Pen, Superintending engineer, Chief Engineer Water Resources Department, EHS Officer SPIU and District Collector/Representative
Kharland Pen Office or Construction Camp Site
Aggrieved Person
Written Response within 15 days
Mode of communication: Letter
and Drop box Joint Site Visit With Contractor and TPQA
Action Plan Implementation By
Contractor
Action Plan Supervision and
Reporting by SPIU with support of PMC
Closure Update
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 184
Table 8.5 : Environment Management Budget
1
Worksite Safety Measures Unit Qty.
Basic
Unit
Rate in
INR.
Total Amount
Without Taxes in
INR
Applicable
percentage
Amount in INR. TOTAL
AMOUNT with
taxes & duties in
INR
1a
Provision, fabrication and erection of MS barricades
of 1.0 m height, meeting specifications prescribed in
IRC SP-55:2014. MS barricades should be made of
mild steel material with two legs. MS barricade
should be applied with anticorrosive zinc primer / red
oxide and applied with synthetic enamel paint of
standard colour on it. Radium reflective strips would
be provided on the barricades. Letter writing should
done on both the sides barricades, as per the
requirement of Client, in radium strip.
MS barricades shall installed on the landward side of
the saline embankment in worksites near houses,
common property resources and sluice gates /
drainage structures, including cost of materials and
fabrication charges, all materials/equipment required
for fabrication, transportation to site, shifting of
barricades from one place to another with all
incidental charges, leads, lifts and all taxes and duties
as applicable from time to time as specified by
Engineer-in-charge.
Meter
300
11000.00
3300000.00
12%
396000.00 3696000.00
1b
Provision and installation of retro-reflective
cautionary/warning signage as per specifications in
IRC SP:55-2014 at starting & end point of the project
site and at/near work zones, having standard design,
using 2 mm aluminum / MS sheet, and having
square, round, rectangular shapes including cost of
Numbe
r 15
15000.00
225000.00
12%
27000.00 252000.00
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 185
boards and other materials required for fixing,
shifting charges from one place to another with all
incidental charges, leads, lifts and all taxes and
duties, as applicable from time to time and as
specified by Engineer-in-charge.
1c
Provision of temporary access / cross over for
properties adjacent to work zones using portable
planks (with length 1 to 2 mts. or as required in line
with site conditions, with at least 1.2 mts. width)
Meter 40 1000.00 40000.00
12% 4800.00 44800.00
1d
Provision of first aid and emergency response
arrangements in the camp, plant/s and worksites,
including fire and electrical safety provisions
including unbreakable box, category – recreation first
aid boxes, travelling first aid boxes, industrial first
aid boxes, having standard dimensions.
camp 2 500000.0
0 1000000.00
12%
120000.00 1120000.00
2
Issuing public notice, printing and putting banners
and information dissemination through appropriate
means regarding type and schedule of civil works,
planned diversions and/or partial closures, utility
shifting/damage/emergency repairs, complaint
handling and all such issues that affect public/road
users/residents close to work zones works, at least
once in a month for the entire project duration.
Numbe
r 54 1000.00 54000.00
12%
6480.00 60480.00
3
Installation of Project Information Board in MS sheet
and all supports, including fixing and maintenance
during the entire project. Minimum board size should
be 2 meters x 1 meters, with necessary information in
English and Marathi written in black paint with white
background. The board details and the required
information will be furnished by the Engineer. The
design and information shall be approved by the
Engineer-in-charge.
Numbe
r 2 15000.00 30000.00
12%
3600.00 33600.00
4
Restoration of crematorium in masonry & providing
access to crematorium during construction activity,
as per the site condition
Square
Meter 50 2400.00 120000.00
14400.00 134400.00
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 186
Specification - Proper cleaning before the masonry
work, construction of burnt brick or un-coursed
rubble masonry in 1:6 mortar proportion. Stone shall
be hard, sound, free from decay and weathering.
Work must be true to horizontal lines and perfect
plumb. Vertical joints are required to be truly vertical
and align vertically with those of alternate courses.
Joint thickness should be within the range of 6mm to
10mm depending upon the size of bricks or boulders.
12%
5
Provision and restoration of all access / approaches to
the embankment, including provision of a hume pipe
(NP II) to ensure continuous/uninterrupted
longitudinal drainage on the landward side of the
embankment. The diameter of hume pipes would be
as per the site conditions (300 mm / 600 mm / 900
mm). Hume pipes of necessary shapes - such as plain
type , spigot & socket end Type, Tung type , Groove
end type , collar joint and flush jointed (external &
internal), to be provided as per site conditions.
Specifications – Non expansive soil / Sand obtained
from excavation shall be used for Embankment
construction which require the compaction.
Compaction shall be done to standard density of the
maximum dry density (MDD – 96%) corresponding
to equivalent Optimum Moisture Content (OMC).
Per
meter
length
3000 1500.00 4500000.00
12%
540000.00 5040000.00
6
Identification and verification of trees along the route
of the saline embankment, marking, preparing the list
as per the norms and obtaining clearance for cutting
of trees (only in case it is unavoidable), paying
compensation and cutting of trees as per the norms,
transportation of cut material to the identified
site/depot as per direction of KLDC and the
concerned authority.
Numbe
r 42 3846.00 161532.00
12%
19383.84 180915.80
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 187
Plantation of equivalent trees or plantation of trees as
per the norms of Govt of Maharashtra
7
Tree Plantation as per strategy (species, distance etc.)
suggested in the Environment Management Plan,
including use of tall saplings (at least 5 feet),
preparation and of pits, watering, protection using
bamboo tree guards, manuring, replacement of
saplings, etc. till closure of contract. At least 90%
should survive at the end of contract period.
Numbe
r 420 1539.00 646380.00
12%
77565.60 723945.60
8
Suitable facilities for Workers at Worksites such as
Toilets, Washing Facilities, Drinking Water,
Changing Room and Lockers, facilities for rest
8a
Provision of mobile toilet fitted with anaerobic
digestion system separately for male and female
workers, Indian type of pot with other facilities such
as tap, lighting and ventilation; stationed at a suitable
place in or within 100 metres from active work front.
Includes cost of water, shifting cost of mobile toilet
from one operational area to another, attendant cost
for looking after cleaning and operation of the toilets.
All materials and labour charges, incidental charges,
leads, lifts and all taxes as applicable from time to
time and as specified by Engineer-in-charge.
Numbe
r 2
150000.0
0 300000.00
12%
36000.00 336000.00
8b
Providing of mobile drinking water counter/kiosk,
fabricated from stainless steel with 300 liters
capacity, with two taps and with bottom tank (300
liter holding capacity) to collect waste water and
stationed at a suitable place within 100 meters from
operational area, with one common attendant for both
mobile toilet and drinking water kiosk. Cost includes
charges for emptying bottom tank through suction
machine, shifting cost of the kiosk from one
Numbe
r 3
350000.0
0 1050000.00
126000.00 1176000.00
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 188
operational area to another area, attendant cost for
looking after cleaning and operation, all materials,
labour charges, incidental charges, leads, lifts and all
taxes as applicable from time to time and as specified
by Engineer-in-charge.
12%
8c
Temporary rest area for workers
Temporary shed for workers area constructed by MS
corrugated Sheet with the support of Bamboos and
MS windows, one number of door to be provided for
good ventilation. Flooring to be constructed using
burnt brick bat coba.
Numbe
r 3 15000.00 45000.00
12% 5400.00 50400.00
9
Periodic health check-up once in a quarter for all
construction workers
Arrange of visit of BHMS or BAMS doctor for
regular health checkup of labors.
camp 6 50000.00 300000.00
12% 36000.00 336000.00
10
Provision of standard coconut fiber logs or coir bags
as silt fencing on both sides of embankment - to be
installed before the construction is initiated in the
stretch and to be left on the site after construction is
complete
Specifications - Provision of standard coconut fiber
logs / mesh or coir bags having approximate size 30
cm dia to be provided for both side of embankments,
as per the site condition / slope including all
necessary items for installation and fixing the
coconut fiber logs / mesh for soil / embankment
stabilization. Plantation of necessary vegetation /
shrubs to protect and hold the coconut fiber logs /
mesh, as per the site condition. It should be installed
before the construction is initiated in the stretch and
to be left on the site after construction is complete.
All materials, labour charges, incidental charges,
leads, lifts and all taxes as applicable from time to
time and as specified by Engineer-in-charge.
R.MT 16000 400.00 6400000.00
12%
768000.00 7168000.00
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 189
11
Disposal of extra earth / debris / similar
unserviceable waste material by mechanical means,
including loading, transporting, unloading to pre-
approved disposal ground in line with EMP
stipulations, including rehabilitation of disposal site
within a lead distance of 10 km and as approved by
Engineer-in-Charge
Cumec 9000 200.00 1800000.00
12%
216000.00 2016000.00
12
Temporary storm water drainage arrangements, oil
interceptors and sedimentation tanks at the
construction camp and plant site/s
Specification – Half round RCC gutter having size
100 mm to 1000 mm to be provided necessary area
near camp/plant site and same is connected to
sedimentation tank constructed in burnt brick
masonry.
camp 3 200000.0
0 600000.00
12% 72000.00 672000.00
13
Cost of water and air quality monitoring once in a
quarter
We shall check water and air quality and submit the
report once in every quarterly.
Numbe
r 6 50000.00 300000.00
12% 36000.00 336000.00
14 Utility shifting and restoration
14.1
Electric Poles (Shifting, dismantling & Restoration of
Electric Poles)
Electrical poles and material shifting by mechanical
means, including loading, transporting, unloading
and restoring it pre-approved location. Vendor to
submit all the necessary drawing for restoration, as
per the site condition
Numbe
rs 10 50000.00 500000.00
12%
60000.00 560000.00
14.2
Restoration of Temple (Dismantling old temple &
constructing new with Brick & shed)
Proper dismantling of old temples and construction
of new temple with burnt brick in 1:6 mortar
proportion. Vendor to submit all the necessary
drawing for restoration, as per the site condition.
Disposal of extra earth / debris / similar
Square
Meter
150 20000.00 3000000
360000.00 3360000.00
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 190
unserviceable waste material by mechanical means,
including loading, transporting, unloading to pre-
approved disposal ground in line with EMP
stipulations, including rehabilitation of disposal site
within a lead distance of 10 km and as approved by
Engineer-in-Charge
Vendor to submit all the necessary drawing, as per
the site condition
12%
14.3
Restoration of crematorium in masonry & providing
access to crematorium during construction activity, ,
as per the site condition
Specification - Proper cleaning before the masonry
work, construction of burnt brick or un-coursed
rubble masonry in 1:6 mortar. Stone shall be hard,
sound, free from decay and weathering.
Work must be true to horizontal lines and perfect
plumb. Vertical joints are required to be truly vertical
and align vertically with those of alternate courses.
Joint thickness should be within the range of 6mm to
10mm depending upon the size of bricks or boulders.
Vendor to submit all the necessary drawing, as per
the site condition
Square
Meter
275.94 20000.00 5518800
12%
662256.00 6181056.00
14.4 Restoration of Jetties at 8 sites. (soiling, bedding &
concrete work)
Specifications – Soil to be compacted to MDD of
96%. Soling should be laid with 100 mm thickness.
After packing the stones properly in position, the
interstices between them should be carefully filled
with quarry spoils or stone chips of larger size
possible to obtain a smooth, compact surface.
PCC / Bedding – M-15, 100 mm concrete bedding to
be provided.
Concrete – M-20 concrete with 12mm 200 c/c both
way surface steel, to be provided, with expansion
joints, of 150 mm thickness, for restoration of jetties.
Rmt
10 250000.0
0 2500000
12%
300000.00 2800000.00
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 191
Open Foundation / Pile foundation to be provided, as
per site conditions to support the jetty.
Vendor to submit all the necessary drawing, as per
the site condition
14.5
Fish drying concrete platform (using M15) (5 Nos)
Specifications - Soil to be compacted by watering
and vibratory roller. Soling should be laid with 100
mm thickness. After packing the stones properly in
position, the interstices between them should be
carefully filled with quarry spoils or stone chips of
larger size possible to obtain a smooth, compact
surface.
PCC / Bedding – M-15, 100 mm concrete bedding to
be provided.
Concrete – M-20 concrete with 12mm 200 c/c both
way surface steel to be provided, with expansion
joints, of 150 mm thickness.
Foundation to be provided, as per site conditions to
support the structure.
Vendor to submit all the necessary drawing, as per
the site condition
Cubic
Meter
300 4500.00 1350000
12%
162000.00 1512000.00
Sub-Total Cost of Environment Management Plan
33740712.00 4048885.44 37789597.44
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 192
Annexure 1.1: List of EIA Report Preparers
S. No. Name of Expert Designation
1. Sanjay Kumar Jain Team Leader and Senior Environment Expert
2. T.G. Ekande Social Team Leader and Sr. Social Expert
3. Anil Kumar GIS Expert
4. Ratnesh Kotiyal Ecologist
5. Nisha Rani Hydrogeologist and Water Pollution Management Expert, Support environment expert
6. Eknath Mapare Support Social Expert and Consultation Specialist
7. Koushik Mukhopadhya Support Social Expert
Since project has run for the longer period, some of the experts worked in initial period of the project till their allotted time got exhausted. In addition to the monitoring staff, name of the experts involved in the initial period of report are not named. I S.K.Jain, Director EQMS and Team Leader of the Project Undertakes that the above team members were involved in the project:
S.K. Jain
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 193
Annexure 2.1: National Ambient Air Quality Standards, 2009
Ambient Air Quality Standards The MoEF&CC has the overall responsibility to set policy and Standards for the protection of environment along with Central Pollution Control Board (CPCB). Ambient Air Quality Standard given below:
Revised National Ambient Air Quality Standards (16th November 2009) Pollutants Time
Weighted Average
Concentration in Ambient Air Industrial,
Residential, Rural, other
areas
Ecologically Sensitive Area
(Notified by Central
Government) Sulphur Dioxide (SO2), μg/m3 Annual *
24 Hours ** 50 80
20 80
Nitrogen Dioxide (NO2), μg/m3 Annual * 24 Hours **
40 80
30 80
PM10, μg/m3 Annual * 24 Hours **
60 100
60 100
PM2.5, μg/m3 Annual * 24 Hours **
40 60
40 60
Ozone (O3) μg/m3 8 Hours * 1 Hour **
100 180
100 180
Lead (Pb) μg/m3
in particulate matter Annual *
24 Hours ** 0.50 1.0
0.50 1.0
Carbon Monoxide (CO), mg/m3 8 Hours ** 1 Hour **
02 04
02 04
Ammonia (NH3), μg/m3 Annual * 24 Hours **
100 400
100 400
Benzene (C6H6), μg/m3 Annual * 05 05
Benzo(a)Pyrene (BaP) ng/m3
in particulate matter Annual * 01 01
Arsenic (As), ng/m3
in particulate matter Annual * 06 06
Nickel (Ni), ng/m3
in particulate matter Annual * 20 20
* Annual Arithmetic mean of minimum 104 measurements in a year at a particular site taken twice a week 24 hourly at uniform intervals. ** 24 hourly or 8 hourly or 1 hourly monitored values, as applicable, shall be complied with 98% of the time in a year. 2% of the time, they may exceed the limits but not on two consecutive days of monitoring.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 194
Annexure 2.2: Noise Standards, CPCB
Ambient Noise Standards Ambient standard with respect to noise have been notified by the Ministry of Environment and forest vide gazette notification dated 26th December 1989 (amended in February 2000). It is based on ‘A’ weighted equivalent noise level (Leq). The ambient noise standards are presented in table below:
Ambient Noise Level Standards
Area code Category of Area Limits in dB(A) Leq
Day Time Night Time
A Industrial Area 75 70
B Commercial Area 65 55
C Residential Area 55 45
D Sensitive Area 50 40
Note: *Day time is from 6 am to 10 pm, Night time is 10 pm to 6.00 am; ** Silence zone is defined as area up to 100 meters around premises of hospitals, educational institutions and courts. Use of vehicle horns, loud speakers and bursting of crackers are banned in these zones
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 195
Annexure 2.3: OSHA’S NOISE EXPOSURE LIMITS FOR THE WORK ZONE
OSHA’S Noise Exposure Limits for The Work Environment Noise Levels in dB(A) Permissible Exposure (hours &
minutes) 85 16 hrs 90 8 hrs 96 3 hrs 30 minutes
102 1 hr 30 minutes 108 40 min 115 15 min 121 6 min 127 3 min 130 1 min
Source: Marsh, 1991, p.322
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 196
Annexure 2.4: Drinking Water Quality Standards-Is: 10500:2012
Standards For Drinking Water (IS:10500)
Parameters Unit Acceptable Limit IS:10500
Permissible Limit IS:10500
1 Colour Hazen units 5 15 2 Odour - Agreeable Agreeable 3 Taste - Agreeable Agreeable 4 Turbidity NTU 1 5 5 Total Dissolved Solids mg/l 500 2000 6 pH - 6.5 to 8.5 No Relaxation 7 Total Hardness as CaCO3 mg/l 200 600 8 Iron as Fe mg/l 0.3 No Relaxation 9 Aluminium mg/l 0.03 0.2 10 Copper as Cu mg/l 0.05 1.5 11 Manganese as Mn mg/l 0.1 0.3 12 Zinc as Zn mg/l 5 15 13 Magnesium as Mg mg/l 30 No Relaxation 14 Barium mg/l 0.7 No Relaxation 15 Calcium as Ca mg/l 75 200 16 Silver mg/l 0.1 No Relaxation 17 Selenium as Se mg/l 0.01 No Relaxation 18 Molybdenum mg/l 0.07 No Relaxation 19 Boron mg/l 0.5 1.0 20 Nitrates as NO3 mg/l 45 No Relaxation 21 Sulphate mg/l 200 400 22 Sulphide
0.01 No Relaxation
23 Fluoride as F mg/l 1.0 1.5 24 Chlorides as Cl mg/l 250 1000 25 Ammonia mg/l 0.5 No Relaxation 26 Chloramines mg/l 0.2 No Relaxation 27 Residual, Free chlorine mg/l 0.2 1.0 28 Total Alkalinity as calcium
carbonate mg/l 200 600
29 Phenolic compounds (as C6H5OH)
mg/l 0.001 0.002
30 Mineral Oil mg/l 0.03 No Relaxation 31 Anionic detergents
(as MBAS) mg/l 0.2 1.0
32 Chromium mg/l 0.05 No Relaxation 33 Arsenic as As mg/l 0.01 0.05 34 Mercury as Hg mg/l 0.001 No Relaxation 35 Cadmium as Cd mg/l 0.003 No Relaxation 36 Lead as Pb mg/l 0.01 No Relaxation 37 Nickel as Ni mg/l 0.02 No Relaxation 38 Cyanide as CN mg/l 0.05 No Relaxation 39 Polynuclear Aromatic
Hydrocarbons (as PAH) mg/l 0.0001 No Relaxation
40 Polychlorinated biphenyls mg/l 0.0005 No Relaxation 41 Total Coliform MPN/100ml Nil No Relaxation
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 197
Annexure 3.1: Detail of The Existing Embankment
Chainage Ground Level Existing Top R.
L.
Height Width Area Mean Area Creek
side field side
Average T. W. B. W.
0 2.99 3.06 3.03 3.35 0.32 1.45 4.33 0.93 0.47
30 2.49 2.95 2.72 3.30 0.58 1.18 4.15 1.54 1.24
60 2.44 2.73 2.59 2.85 0.26 1.20 6.16 0.94 1.24
90 2.56 1.92 2.24 3.15 0.91 2.98 6.99 4.55 2.75
120 2.40 1.93 2.16 3.28 1.12 2.06 6.63 4.87 4.71
150 2.35 2.66 2.51 3.26 0.75 1.88 6.62 3.19 4.03
180 2.45 1.30 1.88 3.08 1.20 2.69 5.66 4.99 4.09
210 2.33 1.85 2.09 3.18 1.09 2.85 7.11 5.43 5.21
240 2.43 1.77 2.10 3.27 1.17 2.69 8.01 6.26 5.85
270 2.35 1.79 2.07 3.21 1.14 3.05 8.70 6.72 6.49
300 2.41 1.78 2.09 3.20 1.11 2.56 7.94 5.83 6.28
330 2.28 1.76 2.02 3.23 1.21 3.37 9.69 7.87 6.85
360 2.28 1.80 2.04 3.31 1.27 2.51 7.67 6.47 7.17
390 2.18 1.30 1.74 3.31 1.57 1.47 5.70 5.61 6.04
393 0.42 0.42 0.42 3.69 3.27 2.28 0.00 3.72 4.67
420 2.16 1.17 1.66 3.25 1.59 2.46 6.22 6.91 5.32
450 2.21 1.31 1.76 3.40 1.64 2.47 7.46 8.12 7.52
480 2.25 1.21 1.73 3.30 1.57 4.64 8.79 10.54 9.33
510 2.25 1.75 2.00 3.30 1.30 2.25 8.78 7.14 8.84
540 2.30 1.64 1.97 3.02 1.05 4.39 8.31 6.65 6.90
570 2.14 1.69 1.92 3.29 1.37 2.96 9.44 8.46 7.56
600 2.28 1.59 1.93 3.36 1.43 2.64 10.58 9.43 8.95
630 2.21 1.53 1.87 3.35 1.48 1.83 11.94 10.20 9.82
660 2.18 0.91 1.54 3.27 1.73 2.58 10.81 11.60 10.90
690 2.26 0.95 1.60 3.14 1.54 2.72 9.74 9.62 10.61
720 2.26 0.91 1.59 3.31 1.72 2.66 9.30 10.28 9.95
750 2.33 0.93 1.63 3.13 1.50 3.89 11.24 11.37 10.83
780 2.35 1.78 2.06 3.24 1.18 2.56 9.60 7.15 9.26
810 2.21 1.84 2.03 3.29 1.26 2.26 8.39 6.73 6.94
840 2.20 1.89 2.05 3.21 1.16 2.67 7.10 5.66 6.20
870 2.23 1.85 2.04 3.20 1.16 2.36 5.95 4.83 5.25
900 2.25 1.73 1.99 3.28 1.29 2.83 7.54 6.68 5.76
930 2.25 1.70 1.97 3.27 1.30 1.92 8.72 6.91 6.80
960 2.03 1.76 1.89 3.31 1.42 2.35 10.81 9.36 8.14
990 2.23 1.80 2.02 3.20 1.18 1.92 5.58 4.41 6.89
1020 2.05 1.76 1.90 3.02 1.12 2.37 8.46 6.07 5.24
1050 2.05 1.77 1.91 3.10 1.19 2.40 8.53 6.52 6.30
1080 1.99 1.79 1.89 3.12 1.23 1.69 7.60 5.70 6.11
1110 2.04 1.74 1.89 3.05 1.16 3.15 8.63 6.86 6.28
1140 2.01 1.77 1.89 3.06 1.17 2.52 10.73 7.75 7.31
1170 2.05 1.83 1.94 3.08 1.14 2.71 8.83 6.59 7.17
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 198
1200 2.03 1.76 1.90 3.05 1.15 2.58 9.02 6.66 6.63
1230 2.08 1.73 1.91 3.06 1.15 2.58 9.22 6.77 6.72
1260 2.11 1.88 2.00 3.01 1.01 2.61 6.86 4.80 5.79
1290 2.11 1.82 1.97 3.05 1.08 2.37 6.52 4.80 4.80
1320 2.08 1.74 1.91 2.99 1.08 3.30 7.83 5.99 5.40
1350 2.00 1.82 1.91 3.04 1.13 3.29 7.45 6.07 6.03
1380 1.98 1.75 1.87 3.09 1.22 2.90 7.55 6.36 6.22
1410 1.92 1.62 1.77 3.17 1.40 2.22 7.45 6.77 6.57
1440 1.93 1.86 1.89 2.99 1.10 1.84 6.82 4.75 5.76
1470 1.91 1.93 1.92 2.99 1.07 2.06 5.67 4.12 4.44
1500 1.88 1.66 1.77 2.95 1.18 2.21 5.69 4.66 4.39
1530 1.95 1.66 1.81 2.95 1.14 2.36 5.71 4.60 4.63
1560 1.80 1.67 1.73 2.94 1.21 2.97 6.13 5.52 5.06
1590 1.83 1.65 1.74 2.92 1.18 3.52 6.97 6.17 5.85
1620 1.83 1.71 1.77 2.91 1.14 2.76 5.66 4.78 5.48
1650 1.94 1.67 1.80 2.90 1.10 2.19 4.24 3.52 4.15
1680 1.84 1.30 1.57 2.97 1.40 2.98 6.43 6.61 5.07
1710 1.65 1.29 1.47 2.87 1.40 3.70 10.23 9.77 8.19
1740 1.73 1.43 1.58 2.72 1.14 2.94 7.45 5.89 7.83
1770 1.73 1.33 1.53 2.89 1.36 2.28 9.11 7.76 6.83
1786 0.00 0.33 0.16 1.70 1.54 1.87 0.00 1.44 4.60
1800 1.78 1.08 1.43 2.97 1.54 1.31 7.30 6.64 4.04
1830 1.76 1.97 1.87 3.01 1.14 1.23 6.28 4.29 5.47
1860 1.75 1.93 1.84 2.98 1.14 1.88 7.63 5.43 4.86
1890 1.85 1.93 1.89 2.95 1.06 2.51 8.41 5.78 5.61
1920 1.83 2.02 1.92 2.86 0.94 1.91 4.14 2.84 4.31
1950 1.93 1.94 1.93 2.86 0.93 2.57 6.58 4.24 3.54
1980 0.83 1.55 1.19 2.85 1.66 3.23 8.57 9.82 7.03
2010 1.81 1.57 1.69 2.81 1.12 3.00 8.49 6.46 8.14
2040 1.79 1.64 1.72 2.86 1.14 2.54 6.71 5.27 5.87
2070 1.82 1.50 1.66 2.83 1.17 3.65 6.60 6.02 5.65
2100 2.12 1.59 1.85 2.84 0.99 2.49 5.74 4.07 5.05
2130 2.11 1.71 1.91 2.87 0.96 3.43 7.07 5.03 4.55
2160 1.94 1.70 1.82 2.86 1.04 2.99 7.47 5.43 5.23
2190 2.26 1.70 1.98 2.81 0.83 2.99 5.73 3.61 4.52
2220 1.78 1.66 1.72 2.85 1.13 2.40 5.70 4.57 4.09
2250 1.78 1.74 1.76 2.91 1.15 2.08 5.47 4.33 4.45
2280 1.75 1.74 1.75 2.88 1.13 1.81 6.82 4.87 4.60
2310 1.66 1.68 1.67 2.85 1.18 2.35 8.92 6.62 5.75
2340 1.86 1.57 1.72 2.87 1.15 2.85 7.06 5.71 6.17
2370 1.83 1.73 1.78 3.02 1.24 2.75 8.46 6.96 6.34
2400 1.85 0.72 1.29 3.17 1.88 2.52 9.74 11.50 9.23
2430 1.96 0.88 1.42 3.29 1.87 3.31 9.14 11.66 11.58
2460 2.00 0.65 1.32 3.03 1.71 3.54 8.55 10.34 11.00
2490 1.97 0.72 1.34 2.98 1.64 2.65 6.52 7.53 8.94
2507 0.00 0.08 0.04 1.69 1.65 2.17 0.00 1.78 4.66
2520 0.94 1.30 1.12 2.99 1.87 2.95 7.43 9.69 5.74
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 199
2550 1.91 1.30 1.60 2.86 1.26 2.17 6.92 5.72 7.71
2580 1.95 1.34 1.64 3.08 1.44 2.79 9.22 8.63 7.18
2610 1.69 1.59 1.64 2.92 1.28 2.22 8.84 7.10 7.87
2640 1.89 1.26 1.57 2.91 1.34 3.10 9.10 8.18 7.64
2670 1.80 1.17 1.49 2.81 1.32 2.13 8.59 7.07 7.63
2700 1.84 0.66 1.25 2.84 1.59 2.28 7.00 7.38 7.23
2730 1.84 1.23 1.53 2.90 1.37 2.16 7.99 6.97 7.18
2760 1.87 1.28 1.57 2.87 1.30 2.67 8.35 7.17 7.07
2790 1.93 0.81 1.37 2.86 1.49 2.87 7.02 7.35 7.26
2820 1.86 1.12 1.49 2.88 1.39 2.05 6.08 5.63 6.49
2850 1.31 0.71 1.01 2.96 1.95 2.32 8.02 10.11 7.87
2880 1.35 0.62 0.98 3.08 2.10 2.58 8.61 11.72 10.92
2910 1.68 0.62 1.15 3.06 1.91 3.13 8.43 11.04 11.38
2940 1.31 0.47 0.89 3.08 2.19 4.38 7.92 13.44 12.24
2970 1.58 1.11 1.35 3.08 1.73 4.04 9.08 11.32 12.38
3000 1.64 0.92 1.28 3.22 1.94 3.03 9.71 12.39 11.86
3030 1.69 1.34 1.51 3.56 2.05 2.46 8.92 11.69 12.04
3060 1.46 0.79 1.12 3.45 2.33 2.92 10.11 15.20 13.45
3090 1.62 1.29 1.45 3.38 1.93 2.48 8.03 10.12 12.66
3120 1.49 1.21 1.35 3.12 1.77 2.51 7.69 9.02 9.57
3150 1.52 1.24 1.38 3.00 1.62 2.51 6.92 7.61 8.32
3180 1.82 1.00 1.41 3.15 1.74 2.35 7.55 8.59 8.10
3210 1.78 1.02 1.40 3.14 1.74 2.72 7.91 9.22 8.91
3240 1.79 1.11 1.45 3.19 1.74 2.52 7.94 9.11 9.17
3270 1.54 1.02 1.28 3.12 1.84 2.82 8.76 10.63 9.87
3300 1.40 1.07 1.24 3.32 2.08 2.69 8.98 12.12 11.38
3330 1.45 1.12 1.28 3.32 2.04 2.39 8.67 11.25 11.69
3360 1.54 1.08 1.31 3.37 2.06 3.05 9.11 12.52 11.89
3390 1.45 0.96 1.20 3.34 2.14 3.15 9.71 13.73 13.13
3420 1.51 0.73 1.12 3.13 2.01 2.56 9.31 11.96 12.85
3450 1.41 0.66 1.03 3.04 2.01 2.53 9.06 11.66 11.81
3480 1.56 0.80 1.18 3.00 1.82 2.92 9.10 10.96 11.31
3510 1.44 0.78 1.11 2.98 1.87 2.73 10.24 12.09 11.53
3540 1.44 1.83 1.64 2.98 1.34 2.30 8.93 7.53 9.81
3570 1.55 0.91 1.23 2.92 1.69 2.76 7.73 8.83 8.18
3600 1.53 0.92 1.22 2.93 1.71 2.66 8.38 9.44 9.14
3630 1.47 0.94 1.21 3.00 1.79 3.14 9.72 11.48 10.46
3660 1.46 0.90 1.18 3.08 1.90 2.60 9.48 11.45 11.47
3690 1.50 0.94 1.22 3.08 1.86 3.07 9.72 11.88 11.67
3720 1.45 0.85 1.15 2.99 1.84 3.03 8.97 11.05 11.47
3750 1.52 1.11 1.32 2.86 1.54 3.29 8.78 9.27 10.16
3780 1.49 1.06 1.27 2.91 1.64 3.46 8.33 9.64 9.46
3810 1.02 1.06 1.04 2.91 1.87 3.57 8.86 11.59 10.62
3840 1.04 0.63 0.84 2.93 2.09 3.31 8.62 12.48 12.04
3870 1.10 0.63 0.87 3.03 2.16 3.00 9.57 13.59 13.04
3900 1.10 0.58 0.84 3.02 2.18 2.68 9.22 12.96 13.28
3930 1.07 0.69 0.88 2.96 2.08 2.21 7.35 9.92 11.44
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 200
3960 1.12 1.18 1.15 2.85 1.70 2.59 6.85 8.03 8.98
3990 1.13 1.24 1.18 2.98 1.80 2.50 7.10 8.64 8.34
4020 1.13 1.06 1.09 2.92 1.83 2.47 7.32 8.95 8.80
4050 1.52 1.24 1.38 2.93 1.55 2.08 8.55 8.22 8.59
4080 1.52 1.84 1.68 2.89 1.21 2.21 7.10 5.61 6.92
4110 1.63 1.79 1.71 2.94 1.23 2.39 7.38 6.02 5.82
4140 1.68 2.24 1.96 2.92 0.96 2.89 7.25 4.87 5.45
4170 1.72 1.36 1.54 3.20 1.66 2.38 8.55 9.04 6.96
4200 1.78 1.37 1.57 2.98 1.41 2.53 8.50 7.79 8.42
4230 1.79 1.58 1.69 2.92 1.23 1.97 7.03 5.51 6.65
4260 1.79 1.23 1.51 2.91 1.40 2.09 6.32 5.87 5.69
4290 1.83 1.28 1.56 2.90 1.34 1.99 6.17 5.49 5.68
4320 1.77 1.15 1.46 2.96 1.50 2.47 6.68 6.88 6.19
4350 1.82 1.27 1.54 3.03 1.49 2.49 6.52 6.73 6.81
4380 1.79 1.58 1.68 3.11 1.43 2.07 6.54 6.16 6.45
4410 1.72 1.19 1.45 3.11 1.66 2.23 7.45 8.06 7.11
4440 1.72 1.20 1.46 2.94 1.48 2.55 8.17 7.94 8.00
4470 1.65 1.14 1.40 2.92 1.52 2.04 7.99 7.63 7.79
4500 1.63 1.11 1.37 2.95 1.58 1.79 7.46 7.29 7.46
4530 1.52 1.05 1.29 2.96 1.67 1.81 6.04 6.57 6.93
4560 1.56 1.10 1.33 2.94 1.61 1.20 6.25 6.00 6.29
4590 1.66 1.17 1.41 2.99 1.58 1.52 6.17 6.05 6.03
4620 1.60 0.97 1.29 2.97 1.68 1.49 6.36 6.58 6.32
4650 1.60 1.03 1.31 2.86 1.55 1.36 4.73 4.70 5.64
4681 1.57 1.28 1.43 2.87 1.44 1.22 6.12 5.28 4.99
4710 1.57 1.29 1.43 2.86 1.43 1.12 6.28 5.30 5.29
4740 1.57 1.29 1.43 2.86 1.43 1.77 4.61 4.55 4.93
4770 1.58 1.30 1.44 2.85 1.41 2.22 4.49 4.74 4.65
4800 1.58 1.31 1.44 2.85 1.41 2.42 4.70 5.00 4.87
4830 1.79 2.07 1.93 2.99 1.06 2.50 4.86 3.90 4.45
4860 1.79 2.03 1.91 2.99 1.08 2.58 5.34 4.27 4.09
4890 1.54 1.16 1.35 2.92 1.57 3.15 6.28 7.38 5.83
4920 1.42 1.21 1.32 2.96 1.64 3.93 6.75 8.74 8.06
4950 1.51 1.22 1.36 2.93 1.57 3.82 7.39 8.81 8.78
4980 1.52 1.41 1.47 2.95 1.48 3.55 7.01 7.79 8.30
5010 1.58 1.42 1.50 2.94 1.44 3.69 7.38 7.95 7.87
5040 1.51 1.38 1.44 2.96 1.52 3.42 8.09 8.74 8.35
5070 1.68 1.55 1.61 2.97 1.36 3.29 7.30 7.18 7.96
5100 1.65 1.60 1.62 2.97 1.35 3.24 6.73 6.72 6.95
5130 1.74 1.52 1.63 2.99 1.36 3.68 7.09 7.33 7.03
5160 1.74 1.56 1.65 3.12 1.47 3.48 6.97 7.66 7.50
5190 1.60 1.63 1.61 2.89 1.28 3.06 7.15 6.53 7.10
5220 1.59 1.55 1.57 2.98 1.41 3.59 6.97 7.44 6.99
5250 1.61 1.58 1.60 2.94 1.34 2.72 5.94 5.79 6.62
5280 1.58 1.46 1.52 2.91 1.39 2.53 6.54 6.30 6.05
5310 1.88 1.37 1.63 2.93 1.30 2.64 5.98 5.61 5.96
5340 1.93 1.51 1.72 2.97 1.25 3.71 6.55 6.39 6.00
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 201
5370 1.81 1.54 1.67 2.96 1.29 3.35 6.07 6.07 6.23
5400 1.76 1.51 1.64 2.93 1.29 3.96 6.64 6.83 6.45
5430 1.95 1.31 1.63 2.90 1.27 4.23 7.01 7.15 6.99
5460 1.80 1.31 1.56 3.03 1.47 3.79 7.14 8.01 7.58
5490 1.74 1.54 1.64 3.04 1.40 4.16 7.18 7.92 7.97
5520 1.67 1.54 1.60 3.04 1.44 3.74 7.30 7.93 7.93
5550 1.66 1.49 1.58 2.96 1.38 3.67 7.15 7.47 7.70
5580 1.63 1.41 1.52 2.97 1.45 3.97 7.02 7.94 7.71
5610 1.65 1.44 1.55 2.97 1.42 3.86 6.58 7.44 7.69
5640 1.58 1.50 1.54 2.94 1.40 3.67 6.66 7.25 7.35
5670 1.68 1.44 1.56 2.98 1.42 3.85 7.01 7.70 7.48
5700 1.56 1.44 1.50 2.95 1.45 4.48 7.44 8.66 8.18
5730 1.69 2.26 1.97 3.08 1.11 3.55 7.12 5.93 7.30
5760 1.81 1.36 1.58 3.04 1.46 3.50 8.50 8.76 7.35
5790 1.83 1.39 1.61 3.05 1.44 4.01 9.06 9.38 9.07
5820 1.80 1.44 1.62 2.99 1.37 4.03 7.70 8.01 8.70
5850 1.81 1.39 1.60 2.94 1.34 3.78 6.86 7.10 7.56
5880 1.69 1.40 1.54 2.93 1.39 4.01 7.56 8.06 7.58
5910 1.68 2.23 1.95 2.99 1.04 4.01 8.42 6.43 7.25
5940 1.84 1.50 1.67 2.95 1.28 3.90 8.29 7.81 7.12
5970 1.85 1.19 1.52 2.94 1.42 3.92 8.17 8.61 8.21
6000 2.01 1.23 1.62 3.05 1.43 3.59 8.81 8.86 8.74
6030 2.00 1.16 1.58 2.93 1.35 3.43 8.42 7.98 8.42
6060 2.17 1.07 1.62 3.09 1.47 3.57 7.95 8.46 8.22
6090 2.07 1.19 1.63 2.96 1.33 3.40 8.35 7.84 8.15
6120 2.14 1.14 1.64 3.02 1.38 3.61 8.48 8.36 8.10
6150 1.96 1.17 1.57 3.17 1.60 3.76 8.86 10.09 9.23
6180 1.94 1.17 1.55 3.15 1.60 3.78 9.21 10.36 10.23
6210 1.96 1.05 1.50 3.20 1.70 3.77 9.35 11.17 10.77
6240 2.03 1.18 1.60 3.24 1.64 3.90 9.39 10.92 11.05
6270 1.97 1.16 1.57 3.49 1.92 3.62 9.38 12.46 11.69
6300 1.99 1.26 1.63 3.21 1.58 3.57 10.47 11.09 11.78
6330 1.93 1.37 1.65 3.37 1.72 3.75 9.73 11.56 11.33
6360 1.94 1.47 1.70 3.29 1.59 3.37 8.50 9.42 10.49
6390 2.09 1.31 1.70 3.27 1.57 3.29 7.65 8.57 9.00
6420 1.93 1.19 1.56 3.33 1.77 3.40 8.71 10.75 9.66
6450 1.90 1.22 1.56 3.17 1.61 3.96 9.49 10.80 10.78
6480 1.92 1.19 1.55 3.30 1.75 3.79 9.56 11.65 11.23
6510 1.97 1.16 1.57 3.08 1.51 3.17 9.45 9.54 10.60
6540 1.92 1.16 1.54 3.10 1.56 3.03 8.58 9.07 9.31
6570 1.61 1.21 1.41 3.24 1.83 2.53 7.30 9.00 9.04
6600 1.61 1.16 1.38 3.19 1.81 0.88 4.07 4.47 6.74
6630 1.06 1.54 1.30 3.06 1.76 1.25 4.14 4.73 4.60
6660 0.94 1.30 1.12 3.02 1.90 2.67 6.32 8.56 6.65
6690 0.95 1.28 1.11 3.00 1.89 2.89 5.96 8.36 8.46
6720 -0.07 -0.07 -0.07 3.11 3.18 2.41 3.70 9.73 9.05
6732 0.00 -0.06 -0.03 3.16 3.19 2.54 0.00 4.06 6.90
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 202
6750 -0.07 -0.07 -0.07 2.90 2.97 2.40 5.45 11.65 7.86
6780 1.10 1.54 1.32 3.10 1.78 2.46 5.25 6.86 9.26
6810 2.22 1.62 1.92 3.13 1.21 2.51 5.43 4.79 5.83
6840 2.20 1.66 1.93 3.27 1.34 2.72 5.28 5.38 5.09
6870 2.11 1.69 1.90 3.29 1.39 2.67 5.39 5.62 5.50
6900 2.13 1.77 1.95 3.33 1.38 2.63 5.49 5.61 5.62
6930 2.20 1.93 2.06 3.58 1.52 2.84 6.53 7.14 6.38
6960 2.21 1.97 2.09 3.31 1.22 2.88 6.12 5.47 6.31
6990 2.21 1.95 2.08 3.31 1.23 2.92 5.55 5.19 5.33
7020 2.41 1.99 2.20 3.37 1.17 2.81 5.79 5.03 5.11
7050 2.25 2.25 2.25 3.33 1.08 2.67 5.83 4.61 4.82
7080 2.28 1.99 2.14 3.33 1.19 2.65 5.50 4.84 4.73
7110 2.28 2.02 2.15 3.31 1.16 2.67 5.57 4.77 4.81
7140 2.14 1.96 2.05 3.24 1.19 2.94 6.07 5.36 5.07
7170 2.25 1.80 2.03 3.24 1.21 2.75 5.54 5.00 5.18
7200 1.79 1.79 1.79 2.81 1.02 3.02 5.66 4.41 4.71
7228 0.00 -0.44 -0.22 3.01 3.23 2.33 0.00 3.76 4.09
7260 1.91 1.68 1.79 3.31 1.52 2.34 6.37 6.63 5.20
7290 2.40 1.82 2.11 3.33 1.22 2.21 4.00 3.77 5.20
7320 2.35 2.19 2.27 3.37 1.10 2.47 3.72 3.41 3.59
7350 2.34 2.01 2.18 3.23 1.05 2.80 4.38 3.76 3.59
7380 2.34 2.00 2.17 3.23 1.06 2.95 4.72 4.06 3.91
7410 2.34 2.04 2.19 3.37 1.18 2.86 4.72 4.47 4.27
7440 2.30 2.01 2.15 3.37 1.22 2.98 4.85 4.77 4.62
7470 2.30 2.03 2.17 3.42 1.25 3.18 5.06 5.14 4.96
7500 2.22 1.80 2.01 3.43 1.42 3.29 7.38 7.56 6.35
7530 2.23 2.07 2.15 3.47 1.32 2.66 5.82 5.60 6.58
7560 2.35 2.11 2.23 2.93 0.70 2.45 5.59 2.80 4.20
7590 2.34 2.07 2.21 3.52 1.31 2.65 5.37 5.25 4.03
7620 2.28 2.06 2.17 3.60 1.43 2.81 5.48 5.91 5.58
7650 2.23 2.08 2.16 3.61 1.45 2.82 6.06 6.42 6.17
7680 2.23 2.15 2.19 3.61 1.42 2.92 6.95 6.99 6.71
7710 2.19 1.88 2.04 3.56 1.52 3.38 8.11 8.74 7.87
7740 2.17 1.78 1.97 3.54 1.57 3.25 7.56 8.50 8.62
7770 2.09 1.80 1.94 3.39 1.45 3.10 7.26 7.50 8.00
7800 2.21 1.91 2.06 3.51 1.45 3.63 7.30 7.90 7.70
7830 2.09 1.98 2.04 3.60 1.56 3.91 6.13 7.83 7.87
7860 2.02 1.90 1.96 3.48 1.52 4.05 6.84 8.26 8.05
7890 1.90 1.99 1.94 3.51 1.57 4.08 7.15 8.83 8.55
7920 1.91 1.94 1.92 3.43 1.51 3.93 7.34 8.50 8.67
7950 1.99 2.09 2.04 3.53 1.49 3.32 6.71 7.48 7.99
7980 2.41 1.98 2.19 3.53 1.34 4.13 7.03 7.46 7.47
8010 2.38 1.99 2.18 3.53 1.35 2.44 5.19 5.16 6.31
8040 2.32 1.99 2.15 3.53 1.38 2.54 5.27 5.39 5.28
8070 2.33 1.98 2.16 3.56 1.40 2.77 5.71 5.92 5.66
8100 2.36 1.89 2.12 3.57 1.45 2.94 6.75 7.01 6.47
8130 2.29 1.99 2.14 3.54 1.40 3.01 6.47 6.65 6.83
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 203
8160 2.38 2.08 2.23 3.75 1.52 2.99 7.36 7.84 7.25
8190 2.72 1.96 2.34 3.65 1.31 2.93 6.74 6.34 7.09
8220 2.45 2.06 2.26 3.68 1.42 3.07 6.73 6.96 6.65
8250 2.50 2.00 2.25 3.60 1.35 3.16 6.55 6.55 6.76
8280 2.49 1.93 2.21 3.63 1.42 3.12 6.97 7.18 6.87
8310 2.36 1.85 2.10 3.61 1.51 3.18 6.77 7.49 7.34
8340 2.49 1.86 2.17 3.63 1.46 3.22 6.21 6.87 7.18
8370 2.55 1.85 2.20 3.14 0.94 3.55 6.69 4.81 5.84
8400 2.45 1.87 2.16 3.10 0.94 2.78 7.15 4.67 4.74
8430 3.02 1.84 2.43 3.19 0.76 2.65 6.71 3.54 4.11
8460 2.49 1.87 2.18 3.23 1.05 2.85 6.88 5.11 4.33
8490 2.52 1.79 2.15 3.36 1.21 2.66 6.67 5.63 5.37
8520 2.52 1.83 2.18 3.27 1.09 2.67 7.87 5.74 5.69
8550 2.65 1.78 2.21 3.13 0.92 2.81 6.12 4.11 4.93
8580 2.32 1.93 2.13 3.32 1.19 2.68 6.10 5.22 4.67
8610 2.39 1.72 2.05 3.18 1.13 2.58 5.59 4.61 4.92
8640 2.32 1.64 1.98 3.33 1.35 2.58 6.35 6.00 5.31
8670 2.24 1.52 1.88 2.97 1.09 2.93 6.77 5.30 5.65
8700 2.25 1.60 1.93 3.20 1.27 2.55 5.63 5.21 5.26
8730 2.46 1.56 2.01 3.13 1.12 3.28 6.89 5.69 5.45
8760 2.18 1.58 1.88 3.15 1.27 2.85 7.55 6.59 6.14
8787 -0.16 -0.01 -0.08 3.11 3.19 2.84 0.00 4.52 5.56
8820 1.61 1.66 1.63 3.10 1.47 3.45 8.32 8.62 6.57
8850 2.10 1.56 1.83 3.10 1.27 2.52 7.00 6.02 7.32
8880 2.13 1.70 1.91 2.95 1.04 2.38 6.41 4.55 5.29
8910 2.17 1.52 1.84 3.06 1.22 2.01 6.05 4.90 4.73
8940 2.15 1.59 1.87 3.11 1.24 2.39 5.93 5.16 5.03
8970 2.28 1.72 2.00 3.07 1.07 2.22 6.83 4.83 5.00
9000 2.28 1.54 1.91 3.04 1.13 2.25 6.98 5.23 5.03
9030 2.30 1.90 2.10 3.16 1.06 2.51 5.73 4.37 4.80
9060 2.38 1.79 2.09 3.22 1.13 2.07 5.08 4.02 4.20
9090 2.39 1.48 1.93 3.16 1.23 2.77 6.53 5.69 4.86
9120 2.06 1.87 1.96 3.16 1.20 2.96 5.56 5.09 5.39
9150 2.06 1.68 1.87 3.19 1.32 1.85 7.40 6.11 5.60
9180 2.10 1.61 1.85 3.01 1.16 2.04 6.42 4.90 5.51
9210 2.11 1.63 1.87 3.20 1.33 1.92 7.66 6.34 5.62
9240 2.09 1.46 1.78 3.24 1.46 1.48 7.75 6.76 6.55
9270 2.09 1.53 1.81 2.98 1.17 1.70 5.93 4.46 5.61
9300 1.93 1.66 1.80 2.91 1.11 3.18 10.00 7.28 5.87
9330 1.93 1.93 1.93 3.80 1.87 5.99 12.26 17.08 12.18
9360 1.93 1.65 1.79 3.14 1.35 2.33 6.55 6.01 11.55
9390 1.96 1.69 1.83 3.10 1.27 2.21 7.44 6.11 6.06
9420 1.92 1.69 1.81 3.16 1.35 1.96 6.06 5.42 5.77
9450 1.97 2.05 2.01 3.13 1.12 1.50 4.70 3.46 4.44
9480 1.97 2.95 2.46 3.05 0.59 1.15 4.40 1.65 2.56
9510 1.97 1.75 1.86 3.05 1.19 1.15 4.31 3.26 2.46
9540 1.96 1.76 1.86 3.53 1.67 2.11 10.46 10.49 6.88
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 204
9547 -0.06 0.00 -0.03 3.54 3.57 1.37 0.00 2.45 6.47
9570 1.97 1.65 1.81 3.38 1.57 2.12 9.14 8.83 5.64
9600 2.03 1.54 1.79 3.22 1.43 2.70 7.97 7.64 8.24
9630 2.04 1.44 1.74 3.22 1.48 2.71 7.75 7.75 7.70
9660 2.02 1.43 1.73 3.26 1.53 2.62 7.75 7.91 7.83
9690 2.01 1.54 1.78 3.26 1.48 2.51 8.00 7.75 7.83
9720 2.12 1.40 1.76 3.57 1.81 2.57 8.57 10.07 8.91
9750 2.31 2.08 2.19 3.57 1.38 2.62 7.94 7.28 8.68
9780 2.14 1.40 1.77 3.58 1.81 2.67 8.23 9.83 8.56
9810 2.03 1.45 1.74 3.38 1.64 2.81 7.63 8.55 9.19
9840 2.11 1.57 1.84 3.44 1.60 3.07 9.25 9.84 9.20
9870 2.21 1.45 1.83 3.44 1.61 3.02 8.77 9.50 9.67
9900 2.12 1.39 1.76 3.37 1.61 3.01 8.42 9.21 9.36
9930 2.09 1.56 1.82 3.28 1.46 3.02 8.43 8.39 8.80
9960 2.14 1.55 1.85 3.13 1.28 3.92 7.67 7.43 7.91
9990 1.92 1.56 1.74 3.12 1.38 3.24 7.27 7.26 7.35
10020 1.92 1.57 1.75 3.04 1.29 2.36 7.55 6.38 6.82
10050 1.94 1.49 1.72 3.16 1.44 2.59 7.66 7.40 6.89
10080 1.90 1.62 1.76 3.24 1.48 2.61 7.82 7.74 7.57
10110 1.91 1.50 1.71 2.96 1.25 2.74 7.63 6.48 7.11
10140 2.00 1.46 1.73 2.79 1.06 2.67 6.87 5.04 5.76
10170 1.95 1.16 1.56 2.71 1.15 2.96 6.78 5.61 5.33
10200 2.01 1.53 1.77 3.16 1.39 3.46 6.85 7.18 6.40
10230 1.93 1.73 1.83 3.21 1.38 3.01 7.48 7.24 7.21
10260 1.99 1.83 1.91 3.07 1.16 3.05 7.37 6.04 6.64
10290 2.08 1.78 1.93 3.19 1.26 2.85 7.30 6.37 6.21
10320 1.98 1.76 1.87 3.10 1.23 2.86 7.33 6.26 6.32
10350 2.04 1.80 1.92 2.85 0.93 4.28 8.33 5.87 6.07
10380 1.83 1.64 1.74 3.12 1.38 2.79 7.10 6.81 6.34
10410 1.86 1.57 1.71 3.11 1.40 3.01 8.16 7.83 7.32
10440 1.78 1.64 1.71 3.26 1.55 2.71 8.62 8.76 8.30
10470 1.84 1.62 1.73 3.21 1.48 2.81 8.44 8.32 8.54
10500 1.98 1.56 1.77 3.32 1.55 3.03 8.44 8.90 8.61
10530 1.91 1.53 1.72 3.33 1.61 2.96 8.92 9.58 9.24
10560 1.95 1.43 1.69 3.33 1.64 2.62 8.84 9.41 9.50
10590 1.96 1.45 1.70 3.50 1.80 2.66 9.17 10.62 10.02
10620 2.09 1.57 1.83 3.37 1.54 2.62 6.72 7.19 8.91
10650 2.08 1.62 1.85 3.26 1.41 3.22 7.52 7.60 7.40
10680 2.15 1.42 1.78 3.65 1.87 3.21 7.53 10.06 8.83
10710 2.08 1.55 1.81 3.51 1.70 3.26 7.15 8.82 9.44
10740 2.03 1.58 1.80 3.45 1.65 3.36 7.44 8.92 8.87
10770 2.08 1.53 1.81 3.27 1.46 3.30 8.16 8.38 8.65
10800 2.06 1.61 1.83 3.20 1.37 3.04 8.51 7.90 8.14
10830 2.19 1.69 1.94 3.36 1.42 2.50 6.21 6.17 7.04
10860 2.32 1.65 1.99 3.35 1.36 3.15 7.31 7.12 6.65
10890 2.22 2.27 2.25 3.47 1.22 2.68 6.14 5.38 6.25
10920 2.37 1.65 2.01 3.36 1.35 3.72 7.13 7.30 6.34
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 205
10950 2.37 1.94 2.16 3.34 1.18 3.29 6.30 5.64 6.47
10980 2.00 1.36 1.68 2.97 1.29 3.13 11.00 9.09 7.37
11010 1.62 1.44 1.53 2.80 1.27 3.13 10.09 8.37 8.73
11040 1.63 1.46 1.54 2.80 1.26 3.59 15.31 11.87 10.12
11070 1.60 1.43 1.51 2.85 1.34 3.35 10.23 9.10 10.49
11100 1.57 1.49 1.53 2.70 1.17 3.50 9.96 7.91 8.51
11130 1.63 1.45 1.54 2.77 1.23 3.69 9.58 8.15 8.03
11160 1.65 1.49 1.57 2.84 1.27 3.79 9.06 8.17 8.16
11190 1.62 1.48 1.55 2.90 1.35 3.65 9.20 8.66 8.42
11220 1.63 1.43 1.53 2.90 1.37 3.46 9.47 8.85 8.76
11250 1.67 1.51 1.59 2.82 1.23 3.26 9.46 7.82 8.34
11280 1.67 1.50 1.58 2.82 1.24 3.07 9.52 7.80 7.81
11310 1.67 1.49 1.58 3.01 1.43 2.94 9.16 8.63 8.22
11340 1.67 1.51 1.59 3.01 1.42 2.85 8.67 8.16 8.40
11370 1.61 1.52 1.57 2.88 1.31 2.54 8.33 7.12 7.64
11400 1.50 1.53 1.52 2.88 1.36 2.30 7.78 6.85 6.99
11430 1.58 1.46 1.52 3.04 1.52 2.47 7.90 7.85 7.35
11460 1.62 1.47 1.54 3.12 1.58 2.80 6.89 7.64 7.75
11490 1.69 1.48 1.58 3.18 1.60 2.69 6.73 7.54 7.59
11520 1.65 1.45 1.55 3.18 1.63 2.70 6.82 7.77 7.66
11550 1.58 1.40 1.49 3.12 1.63 3.00 8.19 9.10 8.44
11580 1.65 1.36 1.51 3.11 1.60 2.72 9.10 9.46 9.28
11610 1.57 1.44 1.50 3.03 1.53 2.73 9.17 9.09 9.28
11640 1.59 1.43 1.51 3.03 1.52 2.69 8.42 8.42 8.76
11670 1.60 1.59 1.59 2.91 1.32 2.61 7.76 6.82 7.62
11700 1.60 1.52 1.56 2.94 1.38 2.80 8.57 7.83 7.33
11730 1.60 1.54 1.57 2.94 1.37 2.90 9.18 8.29 8.06
11760 1.51 1.44 1.47 2.86 1.39 3.07 9.57 8.79 8.54
11790 1.51 1.45 1.48 2.86 1.38 3.24 7.83 7.64 8.22
11820 1.61 1.49 1.55 3.05 1.50 2.71 5.41 6.10 6.87
11850 1.60 1.37 1.49 3.05 1.56 2.43 7.52 7.78 6.94
11880 1.54 1.63 1.59 3.16 1.57 2.23 6.86 7.14 7.46
11910 1.67 1.57 1.62 2.91 1.29 2.46 6.63 5.87 6.51
11940 1.63 1.55 1.59 2.89 1.30 2.56 7.78 6.70 6.29
11970 1.62 1.52 1.57 2.96 1.39 2.54 7.45 6.93 6.82
12000 1.62 1.53 1.57 2.96 1.39 2.27 7.50 6.78 6.86
12030 1.59 1.70 1.64 2.88 1.24 2.30 6.83 5.64 6.21
12060 1.59 1.69 1.64 2.88 1.24 2.38 6.00 5.18 5.41
12090 1.59 1.57 1.58 2.94 1.36 2.54 6.41 6.09 5.64
12120 1.42 1.61 1.52 2.94 1.42 2.65 6.95 6.82 6.46
12150 1.61 1.63 1.62 2.94 1.32 2.41 7.22 6.38 6.60
12180 1.61 1.62 1.62 2.94 1.32 2.33 7.56 6.55 6.47
12210 1.65 1.57 1.61 2.97 1.36 2.72 8.11 7.38 6.97
12240 1.64 1.57 1.61 3.14 1.53 2.25 7.85 7.71 7.55
12270 1.70 1.57 1.63 3.02 1.39 2.05 7.42 6.59 7.15
12300 1.88 1.42 1.65 3.02 1.37 2.33 7.23 6.56 6.58
12330 1.85 1.34 1.60 3.04 1.44 2.70 8.21 7.83 7.20
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 206
12360 1.77 1.36 1.57 3.02 1.45 2.47 8.10 7.67 7.75
12390 1.71 1.41 1.56 2.93 1.37 2.49 8.02 7.17 7.42
12420 1.74 1.42 1.58 2.86 1.28 2.51 8.26 6.88 7.03
12450 1.80 2.00 1.90 2.94 1.04 2.95 7.87 5.60 6.24
12480 1.62 1.99 1.81 3.11 1.30 3.06 7.11 6.60 6.10
12510 1.79 0.70 1.25 3.08 1.83 2.46 7.98 9.54 8.07
12540 1.75 1.35 1.55 3.08 1.53 2.93 7.93 8.32 8.93
12570 2.00 1.42 1.71 2.89 1.18 2.67 6.51 5.42 6.87
12600 1.72 1.45 1.59 2.90 1.31 2.19 6.71 5.82 5.62
12630 1.71 1.45 1.58 2.94 1.36 2.37 8.35 7.32 6.57
12660 1.78 1.43 1.61 3.08 1.47 2.47 7.93 7.66 7.49
12690 1.99 1.46 1.72 3.00 1.28 2.67 7.65 6.62 7.14
12720 1.95 1.48 1.72 2.99 1.27 2.71 7.78 6.67 6.65
12750 2.05 1.45 1.75 3.09 1.34 2.76 6.76 6.37 6.52
12780 2.22 1.48 1.85 3.18 1.33 3.04 7.38 6.94 6.66
12810 2.04 1.46 1.75 2.97 1.22 3.14 9.00 7.41 7.18
12840 1.82 1.45 1.64 2.94 1.30 3.70 10.55 9.26 8.34
12870 2.17 1.39 1.78 3.08 1.30 3.86 9.65 8.76 9.01
12900 1.78 1.44 1.61 3.09 1.48 3.13 7.87 8.14 8.45
12930 1.73 1.60 1.67 3.12 1.45 2.71 9.50 8.84 8.49
12960 1.73 1.42 1.57 2.94 1.37 3.22 8.35 7.95 8.40
12990 1.73 1.25 1.49 2.84 1.35 3.47 8.00 7.74 7.85
13020 1.65 1.44 1.55 2.89 1.34 3.22 7.34 7.09 7.42
13050 1.54 1.25 1.40 3.01 1.61 2.75 6.72 7.62 7.36
13080 1.28 1.72 1.50 3.01 1.51 2.86 7.00 7.45 7.54
13110 1.48 1.65 1.57 3.01 1.44 3.17 7.80 7.89 7.67
13140 1.41 1.59 1.50 2.88 1.38 3.14 8.20 7.83 7.86
13170 1.51 0.96 1.24 2.84 1.60 3.31 8.06 9.12 8.48
13200 1.65 1.52 1.58 2.91 1.33 3.37 7.10 6.95 8.04
13230 2.85 1.44 2.15 2.80 0.65 4.12 7.31 3.71 5.33
13260 1.70 1.42 1.56 2.88 1.32 3.76 6.93 7.04 5.38
13290 1.69 2.06 1.88 2.88 1.00 2.65 6.06 4.37 5.71
13320 1.71 1.80 1.75 2.89 1.14 2.81 6.22 5.14 4.76
13350 1.69 1.73 1.71 3.14 1.43 3.69 7.09 7.68 6.41
13380 2.07 1.64 1.85 3.07 1.22 3.76 7.96 7.14 7.41
13410 2.10 1.64 1.87 3.05 1.18 4.34 8.88 7.79 7.47
13440 1.98 0.80 1.39 3.09 1.70 3.44 7.67 9.44 8.62
13470 1.97 1.50 1.74 3.27 1.53 2.54 7.56 7.70 8.57
13500 1.62 1.47 1.54 3.25 1.71 2.33 7.51 8.42 8.06
13530 1.82 1.53 1.67 3.26 1.59 2.25 8.24 8.32 8.37
13560 1.83 1.49 1.66 3.21 1.55 2.21 7.30 7.34 7.83
13590 1.85 1.58 1.72 3.24 1.52 2.44 7.71 7.70 7.52
13620 2.30 1.58 1.94 3.05 1.11 2.69 7.90 5.87 6.79
13650 1.99 1.51 1.75 3.08 1.33 3.56 8.33 7.91 6.89
13680 1.93 1.33 1.63 3.03 1.40 3.17 8.74 8.32 8.12
13710 1.90 0.52 1.21 3.00 1.79 3.53 8.06 10.37 9.35
13740 2.00 0.53 1.26 3.16 1.90 2.89 6.75 9.17 9.77
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 207
13770 1.55 0.52 1.03 3.16 2.13 2.89 6.87 10.42 9.80
13800 1.80 0.67 1.24 3.15 1.91 3.37 6.75 9.66 10.04
13830 1.87 0.81 1.34 3.07 1.73 3.66 7.17 9.38 9.52
13860 1.93 0.88 1.40 3.17 1.77 3.78 7.30 9.78 9.58
13890 2.06 2.17 2.11 3.05 0.94 3.42 8.87 5.77 7.78
13920 2.02 1.68 1.85 3.20 1.35 3.14 8.64 7.94 6.86
13950 1.94 1.83 1.89 3.16 1.27 2.52 8.38 6.91 7.43
13980 1.94 1.84 1.89 2.96 1.07 3.26 8.09 6.05 6.48
14010 1.92 1.85 1.88 2.97 1.09 3.92 7.53 6.22 6.14
14040 1.96 1.85 1.91 3.04 1.13 4.51 8.39 7.29 6.76
14070 1.87 1.07 1.47 3.02 1.55 3.40 7.45 8.41 7.85
14100 1.90 0.85 1.38 2.91 1.53 3.10 6.79 7.59 8.00
14130 2.01 1.59 1.80 2.97 1.17 3.44 7.13 6.21 6.90
14160 2.14 1.58 1.86 2.95 1.09 3.96 7.80 6.39 6.30
14190 2.03 1.23 1.63 3.02 1.39 2.75 6.78 6.64 6.52
14220 1.89 1.24 1.57 3.00 1.43 2.97 7.48 7.49 7.07
14250 1.64 1.51 1.57 3.04 1.47 2.85 7.96 7.96 7.73
14280 1.42 1.45 1.43 2.95 1.52 2.81 8.43 8.54 8.25
14310 1.51 1.43 1.47 2.95 1.48 2.10 6.26 6.20 7.37
14340 1.60 1.57 1.58 2.96 1.38 2.04 6.75 6.06 6.13
14370 1.80 1.61 1.71 2.96 1.25 2.06 7.42 5.93 6.00
14400 1.81 1.03 1.42 3.01 1.59 3.10 6.32 7.50 6.72
14430 1.80 1.03 1.42 2.96 1.54 2.95 6.55 7.29 7.40
14460 1.97 1.64 1.81 3.06 1.25 4.14 7.81 7.47 7.38
14490 2.03 1.77 1.90 3.12 1.22 3.83 7.02 6.63 7.05
14520 2.11 1.62 1.87 3.22 1.35 3.56 6.59 6.83 6.73
14550 2.11 1.58 1.85 3.23 1.38 3.23 6.61 6.78 6.81
14580 2.03 1.62 1.83 3.06 1.23 3.71 8.77 7.67 7.23
14610 2.03 1.65 1.84 3.40 1.56 3.43 8.48 9.29 8.48
14640 2.05 1.72 1.89 3.39 1.50 2.57 7.19 7.32 8.31
14670 1.94 1.66 1.80 3.23 1.43 2.64 6.69 6.65 6.99
14700 2.44 1.74 2.09 3.27 1.18 2.98 8.48 6.77 6.71
14730 2.30 1.94 2.12 2.96 0.84 3.29 7.98 4.75 5.76
14760 2.30 1.94 2.12 3.03 0.91 3.28 6.40 4.41 4.58
14790 2.27 1.94 2.11 3.32 1.21 2.88 6.26 5.54 4.98
14820 2.14 1.93 2.04 3.15 1.11 2.53 6.43 4.99 5.27
14850 2.18 1.89 2.03 3.15 1.12 3.48 7.07 5.93 5.46
14880 2.12 1.93 2.03 3.13 1.10 3.25 8.42 6.39 6.16
14910 2.04 1.98 2.01 2.99 0.98 1.98 6.38 4.11 5.25
14940 2.15 2.14 2.14 3.02 0.88 1.88 6.25 3.58 3.85
14970 1.97 1.99 1.98 3.04 1.06 1.38 5.27 3.53 3.56
15000 1.86 1.94 1.90 3.04 1.14 1.55 5.68 4.12 3.83
15030 1.88 1.94 1.91 3.12 1.21 1.23 6.50 4.68 4.40
15060 2.07 1.98 2.03 3.22 1.19 1.12 5.81 4.13 4.41
15090 2.07 2.01 2.04 3.21 1.17 1.41 4.39 3.40 3.77
15120 2.13 2.01 2.07 3.26 1.19 1.93 5.14 4.21 3.81
15150 2.10 2.00 2.05 3.37 1.32 1.74 5.22 4.58 4.40
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 208
15180 2.07 1.99 2.03 3.34 1.31 2.02 5.18 4.71 4.65
15210 2.08 2.03 2.05 3.19 1.14 2.37 5.10 4.27 4.49
15240 2.24 2.12 2.18 3.36 1.18 1.62 6.08 4.54 4.41
15270 2.06 2.11 2.09 3.27 1.18 1.99 5.06 4.17 4.36
15300 2.07 2.09 2.08 3.24 1.16 1.99 4.59 3.81 3.99
15330 2.05 2.10 2.08 3.15 1.07 1.41 4.86 3.35 3.58
15360 2.13 2.15 2.14 3.03 0.89 1.82 4.60 2.85 3.10
15390 1.99 2.23 2.11 3.20 1.09 2.16 4.83 3.79 3.32
15420 2.17 2.28 2.22 3.07 0.85 1.27 4.70 2.54 3.17
15450 1.92 2.08 2.00 3.06 1.06 1.18 3.91 2.71 2.63
15480 2.29 2.00 2.15 3.06 0.91 1.31 4.56 2.68 2.70
15510 2.12 2.30 2.21 3.13 0.92 1.77 3.74 2.53 2.61
15540 2.23 2.17 2.20 3.22 1.02 2.93 7.17 5.16 3.85
15570 2.18 2.14 2.16 3.19 1.03 3.16 5.90 4.65 4.91
15600 2.19 2.16 2.17 3.05 0.88 3.32 7.44 4.75 4.70
15630 1.98 2.08 2.03 3.00 0.97 3.08 6.14 4.46 4.61
15660 1.98 1.59 1.78 3.01 1.23 2.79 5.35 5.02 4.74
15690 2.18 1.69 1.94 3.02 1.08 2.11 5.61 4.16 4.59
15720 1.96 1.94 1.95 3.00 1.05 2.39 5.12 3.93 4.05
15750 1.97 2.04 2.00 3.05 1.05 2.73 5.85 4.48 4.21
15780 1.86 2.00 1.93 3.01 1.08 3.36 6.31 5.24 4.86
15810 2.15 1.92 2.04 3.02 0.98 3.57 6.64 5.01 5.13
15840 2.18 2.45 2.31 3.10 0.79 3.40 5.38 3.48 4.25
15870 2.25 1.94 2.09 3.11 1.02 3.28 5.93 4.68 4.08
15900 2.29 2.10 2.19 3.16 0.97 3.12 5.83 4.32 4.50
15930 2.33 2.16 2.24 3.10 0.86 2.51 5.40 3.41 3.87
15960 2.26 2.05 2.16 3.06 0.90 2.94 5.73 3.89 3.65
15990 2.30 2.17 2.23 3.13 0.90 3.10 5.83 4.03 3.96
16020 2.00 2.01 2.00 3.03 1.03 3.04 5.96 4.64 4.34
16050 2.01 2.07 2.04 3.03 0.99 3.46 7.38 5.39 5.02
16080 2.15 1.91 2.03 2.94 0.91 2.47 5.74 3.72 4.56
16110 1.94 1.75 1.85 3.10 1.25 2.86 5.89 5.46 4.59
16140 2.30 2.06 2.18 3.19 1.01 2.77 6.78 4.81 5.14
16170 2.46 2.14 2.30 3.29 0.99 2.56 5.25 3.85 4.33
16200 2.45 2.25 2.35 3.27 0.92 2.71 4.85 3.47 3.66
16230 2.41 2.47 2.44 3.47 1.03 2.81 4.60 3.82 3.65
16260 2.52 2.02 2.27 3.54 1.27 2.84 4.58 4.70 4.26
16290 2.45 2.47 2.46 3.27 0.81 2.79 5.35 3.29 4.00
16320 2.38 2.04 2.21 2.99 0.78 3.87 6.69 4.13 3.71
16350 2.28 1.62 1.95 3.29 1.34 2.49 6.31 5.91 5.02
16380 2.36 1.62 1.99 3.29 1.30 2.59 7.60 6.64 6.28
16405 -0.49 -0.49 -0.49 4.05 4.54 3.11 0.00 7.06 6.85
16440 1.49 1.66 1.57 3.27 1.70 3.77 6.77 8.95 8.01
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 209
Annexure 3.2: Detail of The Location of Trees and Facilities Located Within the Proposed RoW
S.No. Structure Trees Coordinates Distance from creek
side end of
embankment(m)
Chainage/Chainage Range
Trees 1. - 1 tree Neem 18°46'42.83"N 73°
2'11.95"E 6.5
70
2. - Trees -5 (Bhend-3, Suvabal-1, Nariyal-1)
18°46'46.03"N 73° 2'10.50"E
6 180
3. - 1 Anwala Tree 18°46'46.40"N 73° 2'10.40"E
7.4 210-260
4. - 2 Trees Bhend
18°46'58.77"N 73° 2'3.83"E
9.0 540-570
5. - 3 trees Bhend 18°47'13.03"N 73° 1'5.08"E
7.5 2550
6. - 1 Tree Bhend 18°47'14.13"N 73° 1'4.67"E
9.5 2590
7. - 9 Tree, (Bhend-4, sevga-2, Nariyal-1 neem-2)
18°47'21.89"N 73° 0'58.06"E
8.8 2910-2930
8. - 3 Trees (Bhend-1, Sitaphal-1,Kaju-1)
18°47'23.45"N 73° 0'57.40"E
9.5 2970
9. - 1 Tree Bhend 18°47'21.89"N 73° 0'58.06"E
10 3360
10. - 1 Tree
18°47'17.94"N 72°59'59.16"E
4 7235
11. - 5 Trees (Bhendi-4,
siras-1)
18°46'23.93"N73° 0'2.13"E
7.4 9000
12. - 6 Trees (Bhendi
18°45'20.49"N 73° 0'27.98"E
6.5 13290
13. - 1 Tree Bhend 18°45'13.44"N 73° 0'37.52"E
7.2 13800
14. - 2 Tree Bhend 18°44'57.95"N 73° 1'24.52"E
6.8 15780
15. - 1 Tree Bhend 18°45'1.08"N 73° 1'54.30"E
9.0 16440
Mangrooves
16. - Mangroves patches creek and landward
18°47'13.83"N 73° 1'35.51"E
To
00 1650-1740
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 210
side 18°47'11.65"N 73° 1'31.82"E
17. - Mangroves patches creek and landward
side
18°48'0.11"N 73° 0'7.21"E
To 18°47'54.53"N 72°59'43.00"E
00 5010-5820
18. - Mangroves patches creek and landward
side
18°47'40.01"N 72°59'41.43"E
To 18°47'8.20"N 72°59'59.88"E
00 6270 -7590
19. - Mangrove patches creek and landward
side
18°46'46.06"N 73° 0'10.70"E To 18°46'24.38"N 73° 0'2.67"E
00 8340 -9090
20. - Mangrove patches creek and landward
side
18°46'21.78"N 73° 0'1.40"E To 18°46'19.42"N 73° 0'0.16"E
00 9150-9210
21. - Mangrove patches creek and landward
side
18°46'10.45"N 72°59'55.10"E To 18°45'58.70"N 72°59'50.78"E
00 9720-10350
22. - Mangrove Patches creek and landward
side
18°45'0.76"N 73° 1'46.06"E To 18°45'3.01"N 73° 1'53.13"E
00 16110-16380
Houses/Jhopadi 23. 1 House Pakka - 18°46'41.45"N, 73°
2'13.17"E 5 5
24. 1 House Pakka - 18°46'41.93"N 73° 2'12.53"E
10 10
25. 1 House Pakka
-- 18°46'42.83"N 73° 2'11.95"E
14
70
26. 1 House Pakka
-- 18°46'46.03"N 73° 2'10.50"E
9
180
27. 1 House Pakka - 18°47'10.98"N 73° 1'30.47"E
9 1800
28. 1 House kacha - 18°47'10.97"N 73° 1'30.07"E
10 1800 to 1850
29. 1 House kacha - 18°47'10.82"N 73° 1'29.33"E
9 1800 to 1850
30. 1 House Pakka - 18°47'10.52"N ,73° 1'27.80"E
15 1800 to 1890
31. 1 House Pakka - 18°47'10.94"N 73° 1'27.92"E
4 1800 to 1890
32. 1 House Pakka and jhopdi
- 18°47'10.38"N 73° 1'27.20"E
18 1800 to 1890
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 211
33. 1 House Pakka - 18°47'10.28"N 73° 1'26.96"E
20 1800 to 1890
34. 1 House Pakka and jhopdi
- 18°47'10.32"N 73° 1'26.70"E
12 1800 to 1890
35. 1 Jhopadi - 18°47'10.69"N 73° 1'26.63"E
8 1800 to 1890
36. 1 House Pakka - 18°47'10.38"N ,73° 1'26.86"E
20 1800 to 1890
37. 1 House Pakka - 18°47'10.59"N 73° 1'26.69"E
12 1800 to 1890
38. 1 Jhopadi - 18°47'10.59"N 73° 1'26.69"E
11 1800 to 1890
39. 1 Jhopdi - 18°47'10.38"N 73° 1'26.20"E
10 1800 to 1890
40. 1 Jhopdi - 18°47'10.58"N 73° 1'26.10"E
5 1800 to 1890
41. 1 House Pakka - 18°47'10.44"N 73° 1'26.08"E
7 1800 to 1890
42. 1 House Pakka - 18°47'10.37"N 73° 1'25.75"E
8 1800 to 1890
43. 1 House Pakka - 18°47'10.38"N 73° 1'25.54"E
10 1800 to 1890
44. Kaccha Jhopdi - 18°47'10.44"N 73° 1'24.66"E
2 1930
45. 1 Jhopdi kaccha
- 18°47'11.17"N 73° 1'9.08"E
13 2460
46. 1 Jhopdi - 18°47'11.83"N73° 1'7.29"E
11 2480 to 2500
47. House Pakka -- 18°46'23.93"N73° 0'2.13"E
9
9000
48. 3 Houses Pakka
- 18°45'22.27"N 73° 0'26.13"E
12 13260
Fish Pond/Pond 49. 1 Fish Pond -- 18°46'42.83"N 73°
2'11.95"E 14
70
50. 2 Fish Pond -- 18°46'46.03"N 73° 2'10.50"E
9
180
51. Pond - 18°46'53.29"N 73° 2'7.18"E
13 420
52. Pond - 18°46'54.10"N 73° 2'6.89"E
17 450
53. Pond - 18°46'54.66"N 73° 2'6.53"E
18 480
54. 1 Fish Pond - 18°47'18.72"N 73° 1'0.05"E
8 2850
55. 1 Pond - 18°47'11.31"N 73° 1'10.09"E
7 2340
56. 1 Pond - 18°47'11.57"N 73° 1'8.27"E
8 2470
57. 1 Pond - 18°47'21.89"N 73° 0'58.06"E
12 2940
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 212
58. 1 Pond - 18°47'22.69"N 73° 0'57.43"E
13 2945
59. 2 Pond - 18°47'35.29"N 73° 0'52.05"E
7 3280
60. 2 Pond - 18°47'51.55"N 73° 0'44.01"E
8 3780
61. 2 Pond - 18°45'51.78"N 72°59'48.35"E
17 10500
62. 1 Fish Pond - 18°45'12.97"N 73° 0'0.91"E
11 12420
63. 1 Fish Pond - 18°45'21.45"N 73° 0'17.99"E
5 13020
64. 1 Fish Pond - 18°45'20.43"N 73° 0'27.95"E
11 13320
65. 1 Fish Pond - 18°45'16.78"N 73° 0'36.19"E
10 13680
66. 2 Fish Pond
- 18°45'13.44"N 73° 0'37.52"E
13 13770 to 13800
67. `1 Pond (Prabhakar Sankar Thoi)
- 18°45'8.73"N 73° 0'44.69"E
15 14040
Electricity Poles and Electricity Line 68. 1 Electric Pole - 18°46'41.13"N ,73°
2'13.37"E 8.7 0
69. Service Electric Line
- 18°46'42.83"N 73° 2'11.95"E
13.7 75
70. 5 Electrical Pole
- 18°47'11.10"N 73° 1'30.05"E To 18°47'10.42"N 73° 1'25.11"E
5 1800 to 1890
71. 1 Electrical pole
- 18°47'12.16"N 73° 1'7.00"E
4 2480 to 2500
72. 1 electrical Pole
- 18°47'12.43"N 73° 1'6.38"E
4 2520
73. 1 Electrical Pole
- 18°47'13.25"N 73° 1'5.27"E
10 2550 -2580
74. 1 Electrical Pole
- 18°45'4.73"N 73° 1'51.94"E
10 16320-16350
Jetties 75. 1 Jetty - 18°46'42.44"N 73°
2'12.52"E 00 45
76. 1 Jetty - 18°47'10.38"N, 73° 1'24.49"E
00 1980 to 2040
77. 1 Jetty - 18°47'24.23"N 73° 0'57.12"E
6 2990
78. 1 Jetty - 18°46'31.06"N 73° 0'7.01"E
00 8790
79. 1 Jetty - 18°46'10.10"N 72°59'55.22"E
00 9585
80. 1 Jetty - 18°45'21.29"N 73° 0'23.47"E
00 13230
81. 1 jetty - 18°44'57.85"N 73° 1'25.29"E
12 15420
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 213
82. 1 Jetty - 18°45'1.02"N 73° 1'54.19"E
00 16440
Toilets 83. 3 Toilet-private - 18°47'10.62"N ,73°
1'26.49"E 8 1800 to 1890
84. Community Toilet
- 18°47'10.18"N 73° 1'23.26"E
5 1980 to 2040
85. 2 Toilet-community
- 18°47'21.36"N 73° 0'58.55"E
3 2910-2940
86. 1 Toilet-community
18°47'23.45"N 73° 0'57.40"E
5
2970
RCC Well 87. 1 Well RCC- - 18°47'10.10"N 73°
1'25.17"E 8 1910
Sheds 88. Shed 15*10
RCC - 18°47'10.46"N ,73°
1'24.36"E 8 1980 to 2040
89. 1 Passenger Shed
- 18°47'24.33"N 73° 0'57.02"E
7 2990
90. 1 Shed - 18°47'35.29"N 73° 0'52.05"E
7 3280
Ottas
91. 3 Otta - 18°47'10.18"N 73° 1'23.47"E
12 1980 to 2040
92. 1 Otta - 18°47'22.87"N 73° 0'57.38"E
10 2950-2970
93. 1 Otta - 18°47'24.08"N 73° 0'57.27"E
6 2985
Crematoria
94. 1 crematorium: 7 m X 6 m
- 18°47'10.14"N 73° 1'16.35"E
7 2280
95. 1crematorium: 6.8m X 6m
- 18°47'13.32"N 73° 1'5.50"E
3 2550 -2580
96. 1 Crematorium: 23m X 20m
- 18°46'11.41"N 72°59'56.02"E
10 9555
97. 1 crematorium: 12X 4 m
- 18°45'21.68"N 73° 0'18.57"E
6 13030
Road 98. Road - 18.789266°N-
73.016265° E to 18.790084°N-73.015875 E
- 2910-2970
Solar Lights 99. 1 Solar Light - 18°47'13.03"N 73°
1'5.08"E 8 2550 -2580
100. 1 Solar light - 18°45'4.73"N 73° 1'51.94"E
10 16320-16350
101. 1 Solar light - 18°45'4.10"N 73° 1'52.17"E
7 16350
102. 2 Solar light - 18°45'1.02"N 73° 1'54.19"E
10 16410 to 16440
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 214
Temples 103. 1 Temple
(Bahari dev) - 18°45'21.64"N 73°
0'23.44"E 12 13230
104. 1 Temple- Bap dev bhagwan
- 18°45'13.44"N 73° 0'37.52"E
12 13770 to 13800
School 105. 1 School -not
affected 18°45'21.64"N 73°
0'23.44"E 12 13230
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 215
Annexure 3.3: Layout Map of Proposed RoW of Embankment
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 216
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 217
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 218
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 219
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 220
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 221
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 222
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 223
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 224
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 225
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 226
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 227
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 228
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 229
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 230
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 231
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 232
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 233
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 234
Annexure 3.4: Typical Cross Sections of Embankment
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 235
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 236
Annexure 3.5: Details of Proposed Embankment
Ch. Ground Level Stripped R. L. Design
bund top
R. L.
Height of desig
n bund
Design
bund Top
Width
Existing
bund botto
m width
Design
bund botto
m width
Creek
Side
Field
Side
Average
Creek
Side
Field
Side
Average
0 2.99 3.0
6 3.03 2.84 2.9
1 2.88 5.995
3 3.12 4.00 4.33
13.35
30 2.49 2.9
5 2.72 2.34 2.8
0 2.57 5.995
3 3.43 4.00 4.15
14.28
60 2.44 2.7
3 2.59 2.29 2.5
8 2.44 5.995
3 3.56 4.00 6.16
14.67
90 2.56 1.9
2 2.24 2.41 1.7
7 2.09 5.995
3 3.91 4.00 6.99
15.72
120 2.40 1.9
3 2.16 2.25 1.7
8 2.01 5.995
3 3.99 4.00 6.63
15.96
150 2.35 2.6
6 2.51 2.20 2.5
1 2.36 5.995
3 3.64 4.00 6.62
14.91
180 2.45 1.3
0 1.88 2.30 1.1
5 1.73 5.995
3 4.27 4.00 5.66
16.80
210 2.33 1.8
5 2.09 2.18 1.7
0 1.94 5.995
3 4.06 4.00 7.11
16.17
240 2.43 1.7
7 2.10 2.28 1.6
2 1.95 5.995
3 4.05 4.00 8.01
16.14
270 2.35 1.7
9 2.07 2.20 1.6
4 1.92 5.995
3 4.08 4.00 8.70
16.23
300 2.41 1.7
8 2.09 2.26 1.6
3 1.94 5.995
3 4.06 4.00 7.94
16.17
330 2.28 1.7
6 2.02 2.13 1.6
1 1.87 5.995
3 4.13 4.00 9.69
16.38
360 2.28 1.8
0 2.04 2.13 1.6
5 1.89 5.995
3 4.11 4.00 7.67
16.32
390 2.18 1.3
0 1.74 2.03 1.1
5 1.59 5.995
3 4.41 4.00 5.70
17.22
393 0.42 0.4
2 0.42 0.27 0.2
7 0.27 5.995
3 5.73 4.00 0.00
21.18
420 2.16 1.1
7 1.66 2.01 1.0
2 1.51 5.995
3 4.49 4.00 6.22
17.46
450 2.21 1.3
1 1.76 2.06 1.1
6 1.61 5.995
3 4.39 4.00 7.46
17.16
480 2.25 1.2
1 1.73 2.10 1.0
6 1.58 5.995
3 4.42 4.00 8.79
17.25
510 2.25 1.7
5 2.00 2.10 1.6
0 1.85 5.995
3 4.15 4.00 8.78
16.44
540 2.30 1.6
4 1.97 2.15 1.4
9 1.82 5.995
3 4.18 4.00 8.31
16.53
570 2.14 1.6
9 1.92 1.99 1.5
4 1.77 5.995
3 4.23 4.00 9.44
16.68
600 2.28 1.5
9 1.93 2.13 1.4
4 1.78 5.995
3 4.22 4.00 10.58
16.65
630 2.21 1.5
3 1.87 2.06 1.3
8 1.72 5.995
3 4.28 4.00 11.94
16.83
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 237
660 2.18 0.9
1 1.54 2.03 0.7
6 1.39 5.995
3 4.61 4.00 10.81
17.82
690 2.26 0.9
5 1.60 2.11 0.8
0 1.45 5.995
3 4.55 4.00 9.74
17.64
720 2.26 0.9
1 1.59 2.11 0.7
6 1.44 5.995
3 4.56 4.00 9.30
17.67
750 2.33 0.9
3 1.63 2.18 0.7
8 1.48 5.995
3 4.52 4.00 11.24
17.55
780 2.35 1.7
8 2.06 2.20 1.6
3 1.91 5.995
3 4.09 4.00 9.60
16.26
810 2.21 1.8
4 2.03 2.06 1.6
9 1.88 5.995
3 4.12 4.00 8.39
16.35
840 2.20 1.8
9 2.05 2.05 1.7
4 1.90 5.995
3 4.10 4.00 7.10
16.29
870 2.23 1.8
5 2.04 2.08 1.7
0 1.89 5.995
3 4.11 4.00 5.95
16.32
900 2.25 1.7
3 1.99 2.10 1.5
8 1.84 5.995
3 4.16 4.00 7.54
16.47
930 2.25 1.7
0 1.97 2.10 1.5
5 1.82 5.995
3 4.18 4.00 8.72
16.53
960 2.03 1.7
6 1.89 1.88 1.6
1 1.74 5.995
3 4.26 4.00 10.81
16.77
990 2.23 1.8
0 2.02 2.08 1.6
5 1.87 5.995
3 4.13 4.00 5.58
16.38
1020 2.05 1.7
6 1.90 1.90 1.6
1 1.75 5.995
3 4.25 4.00 8.46
16.74
1050 2.05 1.7
7 1.91 1.90 1.6
2 1.76 5.995
3 4.24 6.00 8.53
18.71
1080 1.99 1.7
9 1.89 1.84 1.6
4 1.74 5.995
3 4.26 6.00 7.60
18.77
1110 2.04 1.7
4 1.89 1.89 1.5
9 1.74 5.995
3 4.26 4.00 8.63
16.77
1140 2.01 1.7
7 1.89 1.86 1.6
2 1.74 5.995
3 4.26 4.00 10.73
16.77
1170 2.05 1.8
3 1.94 1.90 1.6
8 1.79 5.995
3 4.21 4.00 8.83
16.62
1200 2.03 1.7
6 1.90 1.88 1.6
1 1.75 5.995
3 4.25 4.00 9.02
16.74
1230 2.08 1.7
3 1.91 1.93 1.5
8 1.76 5.995
3 4.24 4.00 9.22
16.71
1260 2.11 1.8
8 2.00 1.96 1.7
3 1.85 5.995
3 4.15 4.00 6.86
16.44
1290 2.11 1.8
2 1.97 1.96 1.6
7 1.82 5.995
3 4.18 4.00 6.52
16.53
1320 2.08 1.7
4 1.91 1.93 1.5
9 1.76 5.995
3 4.24 4.00 7.83
16.71
1350 2.00 1.8
2 1.91 1.85 1.6
7 1.76 5.995
3 4.24 4.00 7.45
16.71
1380 1.98 1.7
5 1.87 1.83 1.6
0 1.72 5.995
3 4.28 4.00 7.55
16.83
1410 1.92 1.6
2 1.77 1.77 1.4
7 1.62 5.995
3 4.38 4.00 7.45
17.13
1440 1.93 1.8
6 1.89 1.78 1.7
1 1.74 5.995
3 4.26 4.00 6.82
16.77
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 238
1470 1.91 1.9
3 1.92 1.76 1.7
8 1.77 5.995
3 4.23 4.00 5.67
16.68
1500 1.88 1.6
6 1.77 1.73 1.5
1 1.62 5.995
3 4.38 4.00 5.69
17.13
1530 1.95 1.6
6 1.81 1.80 1.5
1 1.66 5.995
3 4.34 6.00 5.71
19.01
1560 1.80 1.6
7 1.73 1.65 1.5
2 1.58 5.995
3 4.42 6.00 6.13
19.25
1590 1.83 1.6
5 1.74 1.68 1.5
0 1.59 5.995
3 4.41 4.00 6.97
17.22
1620 1.83 1.7
1 1.77 1.68 1.5
6 1.62 5.995
3 4.38 4.00 5.66
17.13
1650 1.94 1.6
7 1.80 1.79 1.5
2 1.65 5.995
3 4.35 4.00 4.24
17.04
1680 1.84 1.3
0 1.57 1.69 1.1
5 1.42 5.995
3 4.58 4.00 6.43
17.73
1710 1.65 1.2
9 1.47 1.50 1.1
4 1.32 5.995
3 4.68 4.00 10.23
18.03
1740 1.73 1.4
3 1.58 1.58 1.2
8 1.43 5.995
3 4.57 4.00 7.45
17.70
1770 1.73 1.3
3 1.53 1.58 1.1
8 1.38 5.995
3 4.62 4.00 9.11
17.85
1786 0.00 0.3
3 0.16 -
0.15 0.1
8 0.01 5.995
3 5.99 4.00 0.00
21.96
1800 1.78 1.0
8 1.43 1.63 0.9
3 1.28 5.995
3 4.72 4.00 7.30
18.15
1830 1.76 1.9
7 1.87 1.61 1.8
2 1.72 5.995
3 4.28 4.00 6.28
16.83
1860 1.75 1.9
3 1.84 1.60 1.7
8 1.69 5.995
3 4.31 4.00 7.63
16.92
1890 1.85 1.9
3 1.89 1.70 1.7
8 1.74 5.995
3 4.26 4.00 8.41
16.77
1920 1.83 2.0
2 1.92 1.68 1.8
7 1.77 5.995
3 4.23 4.00 4.14
16.68
1950 1.93 1.9
4 1.93 1.78 1.7
9 1.78 5.995
3 4.22 4.00 6.58
16.65
1980 0.83 1.5
5 1.19 0.68 1.4
0 1.04 5.995
3 4.96 4.00 8.57
18.87
2010 1.81 1.5
7 1.69 1.66 1.4
2 1.54 5.995
3 4.46 4.00 8.49
17.37
2040 1.79 1.6
4 1.72 1.64 1.4
9 1.57 5.995
3 4.43 4.00 6.71
17.28
2070 1.82 1.5
0 1.66 1.67 1.3
5 1.51 5.995
3 4.49 4.00 6.60
17.46
2100 2.12 1.5
9 1.85 1.97 1.4
4 1.70 5.995
3 4.30 4.00 5.74
16.89
2130 2.11 1.7
1 1.91 1.96 1.5
6 1.76 5.995
3 4.24 4.00 7.07
16.71
2160 1.94 1.7
0 1.82 1.79 1.5
5 1.67 5.995
3 4.33 4.00 7.47
16.98
2190 2.26 1.7
0 1.98 2.11 1.5
5 1.83 5.995
3 4.17 4.00 5.73
16.50
2220 1.78 1.6
6 1.72 1.63 1.5
1 1.57 5.995
3 4.43 4.00 5.70
17.28
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 239
2250 1.78 1.7
4 1.76 1.63 1.5
9 1.61 5.995
3 4.39 4.00 5.47
17.16
2280 1.75 1.7
4 1.75 1.60 1.5
9 1.60 5.995
3 4.40 4.00 6.82
17.19
2310 1.66 1.6
8 1.67 1.51 1.5
3 1.52 5.995
3 4.48 4.00 8.92
17.43
2340 1.86 1.5
7 1.72 1.71 1.4
2 1.57 5.995
3 4.43 4.00 7.06
17.28
2370 1.83 1.7
3 1.78 1.68 1.5
8 1.63 5.995
3 4.37 4.00 8.46
17.10
2400 1.85 0.7
2 1.29 1.70 0.5
7 1.14 5.995
3 4.86 4.00 9.74
18.57
2430 1.96 0.8
8 1.42 1.81 0.7
3 1.27 5.995
3 4.73 4.00 9.14
18.18
2460 2.00 0.6
5 1.32 1.85 0.5
0 1.17 5.995
3 4.83 4.00 8.55
18.48
2490 1.97 0.7
2 1.34 1.82 0.5
7 1.19 5.995
3 4.81 4.00 6.52
18.42
2507
0.00 0.08
0.04
-0.15
-0.0
7 -0.11
5.9953
6.11
4.00 0.00
22.32
2520 0.94 1.3
0 1.12 0.79 1.1
5 0.97 5.995
3 5.03 4.00 7.43
19.08
2550 1.91 1.3
0 1.60 1.76 1.1
5 1.45 5.995
3 4.55 4.00 6.92
17.64
2580 1.95 1.3
4 1.64 1.80 1.1
9 1.49 5.995
3 4.51 4.00 9.22
17.52
2610 1.69 1.5
9 1.64 1.54 1.4
4 1.49 5.995
3 4.51 4.00 8.84
17.52
2640 1.89 1.2
6 1.57 1.74 1.1
1 1.42 5.995
3 4.58 4.00 9.10
17.73
2670 1.80 1.1
7 1.49 1.65 1.0
2 1.34 5.995
3 4.66 4.00 8.59
17.97
2700 1.84 0.6
6 1.25 1.69 0.5
1 1.10 5.995
3 4.90 4.00 7.00
18.69
2730 1.84 1.2
3 1.53 1.69 1.0
8 1.38 5.995
3 4.62 4.00 7.99
17.85
2760 1.87 1.2
8 1.57 1.72 1.1
3 1.42 5.995
3 4.58 4.00 8.35
17.73
2790 1.93 0.8
1 1.37 1.78 0.6
6 1.22 5.995
3 4.78 4.00 7.02
18.33
2820 1.86 1.1
2 1.49 1.71 0.9
7 1.34 5.995
3 4.66 4.00 6.08
17.97
2850 1.31 0.7
1 1.01 1.16 0.5
6 0.86 5.995
3 5.14 4.00 8.02
19.41
2880 1.35 0.6
2 0.98 1.20 0.4
7 0.83 5.995
3 5.17 4.00 8.61
19.50
2910 1.68 0.6
2 1.15 1.53 0.4
7 1.00 5.995
3 5.00 4.00 8.43
18.99
2940 1.31 0.4
7 0.89 1.16 0.3
2 0.74 5.995
3 5.26 4.00 7.92
19.77
2970 1.58 1.1
1 1.35 1.43 0.9
6 1.20 5.995
3 4.80 6.00 9.08
20.39
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 240
3000 1.64 0.9
2 1.28 1.49 0.7
7 1.13 5.995
3 4.87 6.00 9.71
20.60
3030 1.69 1.3
4 1.51 1.54 1.1
9 1.36 5.995
3 4.64 4.00 8.92
17.91
3060 1.46 0.7
9 1.12 1.31 0.6
4 0.97 5.995
3 5.03 4.00 10.11
19.08
3090 1.62 1.2
9 1.45 1.47 1.1
4 1.30 5.995
3 4.70 4.00 8.03
18.09
3120 1.49 1.2
1 1.35 1.34 1.0
6 1.20 5.995
3 4.80 4.00 7.69
18.39
3150 1.52 1.2
4 1.38 1.37 1.0
9 1.23 5.995
3 4.77 4.00 6.92
18.30
3180 1.82 1.0
0 1.41 1.67 0.8
5 1.26 5.995
3 4.74 4.00 7.55
18.21
3210 1.78 1.0
2 1.40 1.63 0.8
7 1.25 5.995
3 4.75 4.00 7.91
18.24
3240 1.79 1.1
1 1.45 1.64 0.9
6 1.30 5.995
3 4.70 4.00 7.94
18.09
3270 1.54 1.0
2 1.28 1.39 0.8
7 1.13 5.995
3 4.87 4.00 8.76
18.60
3300 1.40 1.0
7 1.24 1.25 0.9
2 1.09 5.995
3 4.91 4.00 8.98
18.72
3330 1.45 1.1
2 1.28 1.30 0.9
7 1.13 5.995
3 4.87 4.00 8.67
18.60
3360 1.54 1.0
8 1.31 1.39 0.9
3 1.16 5.995
3 4.84 4.00 9.11
18.51
3390 1.45 0.9
6 1.20 1.30 0.8
1 1.05 5.995
3 4.95 4.00 9.71
18.84
3420 1.51 0.7
3 1.12 1.36 0.5
8 0.97 5.995
3 5.03 4.00 9.31
19.08
3450 1.41 0.6
6 1.03 1.26 0.5
1 0.88 5.995
3 5.12 4.00 9.06
19.35
3480 1.56 0.8
0 1.18 1.41 0.6
5 1.03 5.995
3 4.97 4.00 9.10
18.90
3510 1.44 0.7
8 1.11 1.29 0.6
3 0.96 5.995
3 5.04 6.00 10.24
21.11
3540 1.44 1.8
3 1.64 1.29 1.6
8 1.49 5.995
3 4.51 6.00 8.93
19.52
3570 1.55 0.9
1 1.23 1.40 0.7
6 1.08 5.995
3 4.92 4.00 7.73
18.75
3600 1.53 0.9
2 1.22 1.38 0.7
7 1.07 5.995
3 4.93 4.00 8.38
18.78
3630 1.47 0.9
4 1.21 1.32 0.7
9 1.06 5.995
3 4.94 4.00 9.72
18.81
3660 1.46 0.9
0 1.18 1.31 0.7
5 1.03 5.995
3 4.97 4.00 9.48
18.90
3690 1.50 0.9
4 1.22 1.35 0.7
9 1.07 5.995
3 4.93 4.00 9.72
18.78
3720 1.45 0.8
5 1.15 1.30 0.7
0 1.00 5.995
3 5.00 4.00 8.97
18.99
3750 1.52 1.1
1 1.32 1.37 0.9
6 1.17 5.995
3 4.83 4.00 8.78
18.48
3780 1.49 1.0
6 1.27 1.34 0.9
1 1.12 5.995
3 4.88 4.00 8.33
18.63
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 241
3810 1.02 1.0
6 1.04 0.87 0.9
1 0.89 5.995
3 5.11 4.00 8.86
19.32
3840 1.04 0.6
3 0.84 0.89 0.4
8 0.69 5.995
3 5.31 4.00 8.62
19.92
3870 1.10 0.6
3 0.87 0.95 0.4
8 0.72 5.995
3 5.28 4.00 9.57
19.83
3900 1.10 0.5
8 0.84 0.95 0.4
3 0.69 5.995
3 5.31 4.00 9.22
19.92
3930 1.07 0.6
9 0.88 0.92 0.5
4 0.73 5.995
3 5.27 4.00 7.35
19.80
3960 1.12 1.1
8 1.15 0.97 1.0
3 1.00 5.995
3 5.00 4.00 6.85
18.99
3990 1.13 1.2
4 1.18 0.98 1.0
9 1.03 5.995
3 4.97 4.00 7.10
18.90
4020 1.13 1.0
6 1.09 0.98 0.9
1 0.94 5.995
3 5.06 4.00 7.32
19.17
4050 1.52 1.2
4 1.38 1.37 1.0
9 1.23 5.995
3 4.77 4.00 8.55
18.30
4080 1.52 1.8
4 1.68 1.37 1.6
9 1.53 5.995
3 4.47 4.00 7.10
17.40
4110 1.63 1.7
9 1.71 1.48 1.6
4 1.56 5.995
3 4.44 4.00 7.38
17.31
4140 1.68 2.2
4 1.96 1.53 2.0
9 1.81 5.995
3 4.19 6.00 7.25
18.56
4170 1.72 1.3
6 1.54 1.57 1.2
1 1.39 5.995
3 4.61 6.00 8.55
19.82
4200 1.78 1.3
7 1.57 1.63 1.2
2 1.42 5.995
3 4.58 4.00 8.50
17.73
4230 1.79 1.5
8 1.69 1.64 1.4
3 1.54 5.995
3 4.46 4.00 7.03
17.37
4260 1.79 1.2
3 1.51 1.64 1.0
8 1.36 5.995
3 4.64 4.00 6.32
17.91
4290 1.83 1.2
8 1.56 1.68 1.1
3 1.41 5.995
3 4.59 4.00 6.17
17.76
4320 1.77 1.1
5 1.46 1.62 1.0
0 1.31 5.995
3 4.69 4.00 6.68
18.06
4350 1.82 1.2
7 1.54 1.67 1.1
2 1.39 5.995
3 4.61 4.00 6.52
17.82
4380 1.79 1.5
8 1.68 1.64 1.4
3 1.53 5.995
3 4.47 4.00 6.54
17.40
4410 1.72 1.1
9 1.45 1.57 1.0
4 1.30 5.995
3 4.70 4.00 7.45
18.09
4440 1.72 1.2
0 1.46 1.57 1.0
5 1.31 5.995
3 4.69 4.00 8.17
18.06
4470 1.65 1.1
4 1.40 1.50 0.9
9 1.25 5.995
3 4.75 4.00 7.99
18.24
4500 1.63 1.1
1 1.37 1.48 0.9
6 1.22 5.995
3 4.78 4.00 7.46
18.33
4530 1.52 1.0
5 1.29 1.37 0.9
0 1.14 5.995
3 4.86 4.00 6.04
18.57
4560 1.56 1.1
0 1.33 1.41 0.9
5 1.18 5.995
3 4.82 4.00 6.25
18.45
4590 1.66 1.1
7 1.41 1.51 1.0
2 1.26 5.995
3 4.74 4.00 6.17
18.21
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 242
4620 1.60 0.9
7 1.29 1.45 0.8
2 1.14 5.995
3 4.86 6.00 6.36
20.57
4650 1.60 1.0
3 1.31 1.45 0.8
8 1.16 5.995
3 4.84 6.00 4.73
20.51
4681 1.57 1.2
8 1.43 1.42 1.1
3 1.28 5.995
3 4.72 4.00 6.12
18.15
4710 1.57 1.2
9 1.43 1.42 1.1
4 1.28 5.995
3 4.72 4.00 6.28
18.15
4740 1.57 1.2
9 1.43 1.42 1.1
4 1.28 5.995
3 4.72 4.00 4.61
18.15
4770 1.58 1.3
0 1.44 1.43 1.1
5 1.29 5.995
3 4.71 4.00 4.49
18.12
4800 1.58 1.3
1 1.44 1.43 1.1
6 1.29 5.995
3 4.71 4.00 4.70
18.12
4830 1.79 2.0
7 1.93 1.64 1.9
2 1.78 5.995
3 4.22 4.00 4.86
16.65
4860 1.79 2.0
3 1.91 1.64 1.8
8 1.76 5.995
3 4.24 4.00 5.34
16.71
4890 1.54 1.1
6 1.35 1.39 1.0
1 1.20 5.995
3 4.80 4.00 6.28
18.39
4920 1.42 1.2
1 1.32 1.27 1.0
6 1.17 5.995
3 4.83 4.00 6.75
18.48
4950 1.51 1.2
2 1.36 1.36 1.0
7 1.21 5.995
3 4.79 4.00 7.39
18.36
4980 1.52 1.4
1 1.47 1.37 1.2
6 1.32 5.995
3 4.68 4.00 7.01
18.03
5010 1.58 1.4
2 1.50 1.43 1.2
7 1.35 5.995
3 4.65 4.00 7.38
17.94
5040 1.51 1.3
8 1.44 1.36 1.2
3 1.29 5.995
3 4.71 4.00 8.09
18.12
5070 1.68 1.5
5 1.61 1.53 1.4
0 1.46 5.995
3 4.54 4.00 7.30
17.61
5100 1.65 1.6
0 1.62 1.50 1.4
5 1.47 5.995
3 4.53 4.00 6.73
17.58
5130 1.74 1.5
2 1.63 1.59 1.3
7 1.48 5.995
3 4.52 6.00 7.09
19.55
5160 1.74 1.5
6 1.65 1.59 1.4
1 1.50 5.995
3 4.50 6.00 6.97
19.49
5190 1.60 1.6
3 1.61 1.45 1.4
8 1.46 5.995
3 4.54 4.00 7.15
17.61
5220 1.59 1.5
5 1.57 1.44 1.4
0 1.42 5.995
3 4.58 4.00 6.97
17.73
5250 1.61 1.5
8 1.60 1.46 1.4
3 1.45 5.995
3 4.55 4.00 5.94
17.64
5280 1.58 1.4
6 1.52 1.43 1.3
1 1.37 5.995
3 4.63 4.00 6.54
17.88
5310 1.88 1.3
7 1.63 1.73 1.2
2 1.48 5.995
3 4.52 4.00 5.98
17.55
5340 1.93 1.5
1 1.72 1.78 1.3
6 1.57 5.995
3 4.43 4.00 6.55
17.28
5370 1.81 1.5
4 1.67 1.66 1.3
9 1.52 5.995
3 4.48 4.00 6.07
17.43
5400 1.76 1.5
1 1.64 1.61 1.3
6 1.49 5.995
3 4.51 4.00 6.64
17.52
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 243
5430 1.95 1.3
1 1.63 1.80 1.1
6 1.48 5.995
3 4.52 4.00 7.01
17.55
5460 1.80 1.3
1 1.56 1.65 1.1
6 1.41 5.995
3 4.59 4.00 7.14
17.76
5490 1.74 1.5
4 1.64 1.59 1.3
9 1.49 5.995
3 4.51 4.00 7.18
17.52
5520 1.67 1.5
4 1.60 1.52 1.3
9 1.45 5.995
3 4.55 4.00 7.30
17.64
5550 1.66 1.4
9 1.58 1.51 1.3
4 1.43 5.995
3 4.57 4.00 7.15
17.70
5580 1.63 1.4
1 1.52 1.48 1.2
6 1.37 5.995
3 4.63 4.00 7.02
17.88
5610 1.65 1.4
4 1.55 1.50 1.2
9 1.40 5.995
3 4.60 4.00 6.58
17.79
5640 1.58 1.5
0 1.54 1.43 1.3
5 1.39 5.995
3 4.61 6.00 6.66
19.82
5670 1.68 1.4
4 1.56 1.53 1.2
9 1.41 5.995
3 4.59 6.00 7.01
19.76
5700 1.56 1.4
4 1.50 1.41 1.2
9 1.35 5.995
3 4.65 4.00 7.44
17.94
5730 1.69 2.2
6 1.97 1.54 2.1
1 1.82 5.995
3 4.18 4.00 7.12
16.53
5760 1.81 1.3
6 1.58 1.66 1.2
1 1.43 5.995
3 4.57 4.00 8.50
17.70
5790 1.83 1.3
9 1.61 1.68 1.2
4 1.46 5.995
3 4.54 4.00 9.06
17.61
5820 1.80 1.4
4 1.62 1.65 1.2
9 1.47 5.995
3 4.53 4.00 7.70
17.58
5850 1.81 1.3
9 1.60 1.66 1.2
4 1.45 5.995
3 4.55 4.00 6.86
17.64
5880 1.69 1.4
0 1.54 1.54 1.2
5 1.39 5.995
3 4.61 4.00 7.56
17.82
5910 1.68 2.2
3 1.95 1.53 2.0
8 1.80 5.995
3 4.20 4.00 8.42
16.59
5940 1.84 1.5
0 1.67 1.69 1.3
5 1.52 5.995
3 4.48 4.00 8.29
17.43
5970 1.85 1.1
9 1.52 1.70 1.0
4 1.37 5.995
3 4.63 4.00 8.17
17.88
6000 2.01 1.2
3 1.62 1.86 1.0
8 1.47 5.995
3 4.53 4.00 8.81
17.58
6030 2.00 1.1
6 1.58 1.85 1.0
1 1.43 5.995
3 4.57 4.00 8.42
17.70
6060 2.17 1.0
7 1.62 2.02 0.9
2 1.47 5.995
3 4.53 4.00 7.95
17.58
6090 2.07 1.1
9 1.63 1.92 1.0
4 1.48 5.995
3 4.52 4.00 8.35
17.55
6120 2.14 1.1
4 1.64 1.99 0.9
9 1.49 5.995
3 4.51 6.00 8.48
19.52
6150 1.96 1.1
7 1.57 1.81 1.0
2 1.42 5.995
3 4.58 6.00 8.86
19.73
6180 1.94 1.1
7 1.55 1.79 1.0
2 1.40 5.995
3 4.60 4.00 9.21
17.79
6210 1.96 1.0
5 1.50 1.81 0.9
0 1.35 5.995
3 4.65 4.00 9.35
17.94
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 244
6240 2.03 1.1
8 1.60 1.88 1.0
3 1.45 5.995
3 4.55 4.00 9.39
17.64
6270 1.97 1.1
6 1.57 1.82 1.0
1 1.42 5.995
3 4.58 4.00 9.38
17.73
6300 1.99 1.2
6 1.63 1.84 1.1
1 1.48 5.995
3 4.52 4.00 10.47
17.55
6330 1.93 1.3
7 1.65 1.78 1.2
2 1.50 5.995
3 4.50 4.00 9.73
17.49
6360 1.94 1.4
7 1.70 1.79 1.3
2 1.55 5.995
3 4.45 4.00 8.50
17.34
6390 2.09 1.3
1 1.70 1.94 1.1
6 1.55 5.995
3 4.45 4.00 7.65
17.34
6420 1.93 1.1
9 1.56 1.78 1.0
4 1.41 5.995
3 4.59 4.00 8.71
17.76
6450 1.90 1.2
2 1.56 1.75 1.0
7 1.41 5.995
3 4.59 4.00 9.49
17.76
6480 1.92 1.1
9 1.55 1.77 1.0
4 1.40 5.995
3 4.60 4.00 9.56
17.79
6510 1.97 1.1
6 1.57 1.82 1.0
1 1.42 5.995
3 4.58 4.00 9.45
17.73
6540 1.92 1.1
6 1.54 1.77 1.0
1 1.39 5.995
3 4.61 4.00 8.58
17.82
6570 1.61 1.2
1 1.41 1.46 1.0
6 1.26 5.995
3 4.74 4.00 7.30
18.21
6600 1.61 1.1
6 1.38 1.46 1.0
1 1.23 5.995
3 4.77 4.00 4.07
18.30
6630 1.06 1.5
4 1.30 0.91 1.3
9 1.15 5.995
3 4.85 4.00 4.14
18.54
6660 0.94 1.3
0 1.12 0.79 1.1
5 0.97 5.995
3 5.03 4.00 6.32
19.08
6690 0.95 1.2
8 1.11 0.80 1.1
3 0.96 5.995
3 5.04 4.00 5.96
19.11
6720
-0.07
-0.0
7 -0.07
-0.22
-0.2
2 -0.22
5.9953
6.22
4.00 3.70
22.65
6732
0.00 -0.0
6 -0.03
-0.15
-0.2
1 -0.18
5.9953
6.18
4.00 0.00
22.53
6750
-0.07
-0.0
7 -0.07
-0.22
-0.2
2 -0.22
5.9953
6.22
4.00 5.45
22.65
6780 1.10 1.5
4 1.32 0.95 1.3
9 1.17 5.995
3 4.83 4.00 5.25
18.48
6810 2.22 1.6
2 1.92 2.07 1.4
7 1.77 5.995
3 4.23 4.00 5.43
16.68
6840 2.20 1.6
6 1.93 2.05 1.5
1 1.78 5.995
3 4.22 4.00 5.28
16.65
6870 2.11 1.6
9 1.90 1.96 1.5
4 1.75 5.995
3 4.25 4.00 5.39
16.74
6900 2.13 1.7
7 1.95 1.98 1.6
2 1.80 5.995
3 4.20 4.00 5.49
16.59
6930 2.20 1.9
3 2.06 2.05 1.7
8 1.91 5.995
3 4.09 4.00 6.53
16.26
6960 2.21 1.9 2.09 2.06 1.8 1.94 5.995 4.06 4.00 6.12 16.17
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 245
7 2 3
6990 2.21 1.9
5 2.08 2.06 1.8
0 1.93 5.995
3 4.07 4.00 5.55
16.20
7020 2.41 1.9
9 2.20 2.26 1.8
4 2.05 5.995
3 3.95 4.00 5.79
15.84
7050 2.25 2.2
5 2.25 2.10 2.1
0 2.10 5.995
3 3.90 4.00 5.83
15.69
7080 2.28 1.9
9 2.14 2.13 1.8
4 1.99 5.995
3 4.01 4.00 5.50
16.02
7110 2.28 2.0
2 2.15 2.13 1.8
7 2.00 5.995
3 4.00 4.00 5.57
15.99
7140 2.14 1.9
6 2.05 1.99 1.8
1 1.90 5.995
3 4.10 4.00 6.07
16.29
7170 2.25 1.8
0 2.03 2.10 1.6
5 1.88 5.995
3 4.12 4.00 5.54
16.35
7200 1.79 1.7
9 1.79 1.64 1.6
4 1.64 5.995
3 4.36 4.00 5.66
17.07
7228
0.00 -0.4
4 -0.22
-0.15
-0.5
9 -0.37
5.9953
6.37
4.00 0.00
23.10
7260 1.91 1.6
8 1.79 1.76 1.5
3 1.64 5.995
3 4.36 4.00 6.37
17.07
7290 2.40 1.8
2 2.11 2.25 1.6
7 1.96 5.995
3 4.04 4.00 4.00
16.11
7320 2.35 2.1
9 2.27 2.20 2.0
4 2.12 5.995
3 3.88 4.00 3.72
15.63
7350 2.34 2.0
1 2.18 2.19 1.8
6 2.03 5.995
3 3.97 4.00 4.38
15.90
7380 2.34 2.0
0 2.17 2.19 1.8
5 2.02 5.995
3 3.98 4.00 4.72
15.93
7410 2.34 2.0
4 2.19 2.19 1.8
9 2.04 5.995
3 3.96 4.00 4.72
15.87
7440 2.30 2.0
1 2.15 2.15 1.8
6 2.00 5.995
3 4.00 4.00 4.85
15.99
7470 2.30 2.0
3 2.17 2.15 1.8
8 2.02 5.995
3 3.98 4.00 5.06
15.93
7500 2.22 1.8
0 2.01 2.07 1.6
5 1.86 5.995
3 4.14 4.00 7.38
16.41
7530 2.23 2.0
7 2.15 2.08 1.9
2 2.00 5.995
3 4.00 4.00 5.82
15.99
7560 2.35 2.1
1 2.23 2.20 1.9
6 2.08 5.995
3 3.92 4.00 5.59
15.75
7590 2.34 2.0
7 2.21 2.19 1.9
2 2.06 5.995
3 3.94 4.00 5.37
15.81
7620 2.28 2.0
6 2.17 2.13 1.9
1 2.02 5.995
3 3.98 4.00 5.48
15.93
7650 2.23 2.0
8 2.16 2.08 1.9
3 2.01 5.995
3 3.99 4.00 6.06
15.96
7680 2.23 2.1
5 2.19 2.08 2.0
0 2.04 5.995
3 3.96 4.00 6.95
15.87
7710 2.19 1.8
8 2.04 2.04 1.7
3 1.89 5.995
3 4.11 4.00 8.11
16.32
7740 2.17 1.7 1.97 2.02 1.6 1.82 5.995 4.18 4.00 7.56 16.53
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 246
8 3 3
7770 2.09 1.8
0 1.94 1.94 1.6
5 1.79 5.995
3 4.21 4.00 7.26
16.62
7800 2.21 1.9
1 2.06 2.06 1.7
6 1.91 5.995
3 4.09 4.00 7.30
16.26
7830 2.09 1.9
8 2.04 1.94 1.8
3 1.89 5.995
3 4.11 6.00 6.13
18.32
7860 2.02 1.9
0 1.96 1.87 1.7
5 1.81 5.995
3 4.19 6.00 6.84
18.56
7890 1.90 1.9
9 1.94 1.75 1.8
4 1.79 5.995
3 4.21 4.00 7.15
16.62
7920 1.91 1.9
4 1.92 1.76 1.7
9 1.77 5.995
3 4.23 4.00 7.34
16.68
7950 1.99 2.0
9 2.04 1.84 1.9
4 1.89 5.995
3 4.11 4.00 6.71
16.32
7980 2.41 1.9
8 2.19 2.26 1.8
3 2.04 5.995
3 3.96 4.00 7.03
15.87
8010 2.38 1.9
9 2.18 2.23 1.8
4 2.03 5.995
3 3.97 4.00 5.19
15.90
8040 2.32 1.9
9 2.15 2.17 1.8
4 2.00 5.995
3 4.00 4.00 5.27
15.99
8070 2.33 1.9
8 2.16 2.18 1.8
3 2.01 5.995
3 3.99 4.00 5.71
15.96
8100 2.36 1.8
9 2.12 2.21 1.7
4 1.97 5.995
3 4.03 4.00 6.75
16.08
8130 2.29 1.9
9 2.14 2.14 1.8
4 1.99 5.995
3 4.01 4.00 6.47
16.02
8160 2.38 2.0
8 2.23 2.23 1.9
3 2.08 5.995
3 3.92 4.00 7.36
15.75
8190 2.72 1.9
6 2.34 2.57 1.8
1 2.19 5.995
3 3.81 4.00 6.74
15.42
8220 2.45 2.0
6 2.26 2.30 1.9
1 2.11 5.995
3 3.89 4.00 6.73
15.66
8250 2.50 2.0
0 2.25 2.35 1.8
5 2.10 5.995
3 3.90 4.00 6.55
15.69
8280 2.49 1.9
3 2.21 2.34 1.7
8 2.06 5.995
3 3.94 4.00 6.97
15.81
8310 2.36 1.8
5 2.10 2.21 1.7
0 1.95 5.995
3 4.05 4.00 6.77
16.14
8340 2.49 1.8
6 2.17 2.34 1.7
1 2.02 5.995
3 3.98 4.00 6.21
15.93
8370 2.55 1.8
5 2.20 2.40 1.7
0 2.05 5.995
3 3.95 6.00 6.69
17.84
8400 2.45 1.8
7 2.16 2.30 1.7
2 2.01 5.995
3 3.99 6.00 7.15
17.96
8430 3.02 1.8
4 2.43 2.87 1.6
9 2.28 5.995
3 3.72 4.00 6.71
15.15
8460 2.49 1.8
7 2.18 2.34 1.7
2 2.03 5.995
3 3.97 4.00 6.88
15.90
8490 2.52 1.7
9 2.15 2.37 1.6
4 2.00 5.995
3 4.00 4.00 6.67
15.99
8520 2.52 1.8
3 2.18 2.37 1.6
8 2.03 5.995
3 3.97 4.00 7.87
15.90
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 247
8550 2.65 1.7
8 2.21 2.50 1.6
3 2.06 5.995
3 3.94 4.00 6.12
15.81
8580 2.32 1.9
3 2.13 2.17 1.7
8 1.98 5.995
3 4.02 4.00 6.10
16.05
8610 2.39 1.7
2 2.05 2.24 1.5
7 1.90 5.995
3 4.10 4.00 5.59
16.29
8640 2.32 1.6
4 1.98 2.17 1.4
9 1.83 5.995
3 4.17 4.00 6.35
16.50
8670 2.24 1.5
2 1.88 2.09 1.3
7 1.73 5.995
3 4.27 4.00 6.77
16.80
8700 2.25 1.6
0 1.93 2.10 1.4
5 1.78 5.995
3 4.22 4.00 5.63
16.65
8730 2.46 1.5
6 2.01 2.31 1.4
1 1.86 5.995
3 4.14 4.00 6.89
16.41
8760 2.18 1.5
8 1.88 2.03 1.4
3 1.73 5.995
3 4.27 4.00 7.55
16.80
8787
-0.16
-0.0
1 -0.08
-0.31
-0.1
6 -0.23
5.9953
6.23
4.00 0.00
22.68
8820 1.61 1.6
6 1.63 1.46 1.5
1 1.48 5.995
3 4.52 4.00 8.32
17.55
8850 2.10 1.5
6 1.83 1.95 1.4
1 1.68 5.995
3 4.32 4.00 7.00
16.95
8880 2.13 1.7
0 1.91 1.98 1.5
5 1.76 5.995
3 4.24 4.00 6.41
16.71
8910 2.17 1.5
2 1.84 2.02 1.3
7 1.69 5.995
3 4.31 4.00 6.05
16.92
8940 2.15 1.5
9 1.87 2.00 1.4
4 1.72 5.995
3 4.28 4.00 5.93
16.83
8970 2.28 1.7
2 2.00 2.13 1.5
7 1.85 5.995
3 4.15 4.00 6.83
16.44
9000 2.28 1.5
4 1.91 2.13 1.3
9 1.76 5.995
3 4.24 4.00 6.98
16.71
9030 2.30 1.9
0 2.10 2.15 1.7
5 1.95 5.995
3 4.05 4.00 5.73
16.14
9060 2.38 1.7
9 2.09 2.23 1.6
4 1.94 5.995
3 4.06 4.00 5.08
16.17
9090 2.39 1.4
8 1.93 2.24 1.3
3 1.78 5.995
3 4.22 4.00 6.53
16.65
9120 2.06 1.8
7 1.96 1.91 1.7
2 1.81 5.995
3 4.19 4.00 5.56
16.56
9150 2.06 1.6
8 1.87 1.91 1.5
3 1.72 5.995
3 4.28 4.00 7.40
16.83
9180 2.10 1.6
1 1.85 1.95 1.4
6 1.70 5.995
3 4.30 4.00 6.42
16.89
9210 2.11 1.6
3 1.87 1.96 1.4
8 1.72 5.995
3 4.28 4.00 7.66
16.83
9240 2.09 1.4
6 1.78 1.94 1.3
1 1.63 5.995
3 4.37 4.00 7.75
17.10
9270 2.09 1.5
3 1.81 1.94 1.3
8 1.66 5.995
3 4.34 4.00 5.93
17.01
9300 1.93 1.6
6 1.80 1.78 1.5
1 1.65 5.995
3 4.35 4.00 10.00
17.04
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 248
9330 1.93 1.9
3 1.93 1.78 1.7
8 1.78 5.995
3 4.22 4.00 12.26
16.65
9360 1.93 1.6
5 1.79 1.78 1.5
0 1.64 5.995
3 4.36 4.00 6.55
17.07
9390 1.96 1.6
9 1.83 1.81 1.5
4 1.68 5.995
3 4.32 4.00 7.44
16.95
9420 1.92 1.6
9 1.81 1.77 1.5
4 1.66 5.995
3 4.34 4.00 6.06
17.01
9450 1.97 2.0
5 2.01 1.82 1.9
0 1.86 5.995
3 4.14 4.00 4.70
16.41
9480 1.97 2.9
5 2.46 1.82 2.8
0 2.31 5.995
3 3.69 4.00 4.40
15.06
9510 1.97 1.7
5 1.86 1.82 1.6
0 1.71 5.995
3 4.29 4.00 4.31
16.86
9540 1.96 1.7
6 1.86 1.81 1.6
1 1.71 5.995
3 4.29 4.00 10.46
16.86
9547
-0.06
0.00
-0.03
-0.21
-0.1
5 -0.18
5.9953
6.18
4.00 0.00
22.53
9570 1.97 1.6
5 1.81 1.82 1.5
0 1.66 5.995
3 4.34 4.00 9.14
17.01
9600 2.03 1.5
4 1.79 1.88 1.3
9 1.64 5.995
3 4.36 4.00 7.97
17.07
9630 2.04 1.4
4 1.74 1.89 1.2
9 1.59 5.995
3 4.41 4.00 7.75
17.22
9660 2.02 1.4
3 1.73 1.87 1.2
8 1.58 5.995
3 4.42 4.00 7.75
17.25
9690 2.01 1.5
4 1.78 1.86 1.3
9 1.63 5.995
3 4.37 4.00 8.00
17.10
9720 2.12 1.4
0 1.76 1.97 1.2
5 1.61 5.995
3 4.39 4.00 8.57
17.16
9750 2.31 2.0
8 2.19 2.16 1.9
3 2.04 5.995
3 3.96 4.00 7.94
15.87
9780 2.14 1.4
0 1.77 1.99 1.2
5 1.62 5.995
3 4.38 4.00 8.23
17.13
9810 2.03 1.4
5 1.74 1.88 1.3
0 1.59 5.995
3 4.41 4.00 7.63
17.22
9840 2.11 1.5
7 1.84 1.96 1.4
2 1.69 5.995
3 4.31 4.00 9.25
16.92
9870 2.21 1.4
5 1.83 2.06 1.3
0 1.68 5.995
3 4.32 4.00 8.77
16.95
9900 2.12 1.3
9 1.76 1.97 1.2
4 1.61 5.995
3 4.39 4.00 8.42
17.16
9930 2.09 1.5
6 1.82 1.94 1.4
1 1.67 5.995
3 4.33 4.00 8.43
16.98
9960 2.14 1.5
5 1.85 1.99 1.4
0 1.70 5.995
3 4.30 4.00 7.67
16.89
9990 1.92 1.5
6 1.74 1.77 1.4
1 1.59 5.995
3 4.41 4.00 7.27
17.22 1002
0 1.92 1.5
7 1.75 1.77 1.4
2 1.60 5.995
3 4.40 4.00 7.55
17.19 1005
0 1.94 1.4
9 1.72 1.79 1.3
4 1.57 5.995
3 4.43 4.00 7.66
17.28
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 249
10080
1.90 1.62 1.76
1.75 1.47 1.61
5.9953 4.39
4.00 7.82 17.16
10110
1.91 1.50 1.71
1.76 1.35 1.56
5.9953 4.44
4.00 7.63 17.31
10140
2.00 1.46 1.73
1.85 1.31 1.58
5.9953 4.42
4.00 6.87 17.25
10170
1.95 1.16 1.56
1.80 1.01 1.41
5.9953 4.59
4.00 6.78 17.76
10200
2.01 1.53 1.77
1.86 1.38 1.62
5.9953 4.38
4.00 6.85 17.13
10230
1.93 1.73 1.83
1.78 1.58 1.68
5.9953 4.32
4.00 7.48 16.95
10260
1.99 1.83 1.91
1.84 1.68 1.76
5.9953 4.24
4.00 7.37 16.71
10290
2.08 1.78 1.93
1.93 1.63 1.78
5.9953 4.22
4.00 7.30 16.65
10320
1.98 1.76 1.87
1.83 1.61 1.72
5.9953 4.28
4.00 7.33 16.83
10350
2.04 1.80 1.92
1.89 1.65 1.77
5.9953 4.23
4.00 8.33 16.68
10380
1.83 1.64 1.74
1.68 1.49 1.59
5.9953 4.41
4.00 7.10 17.22
10410
1.86 1.57 1.71
1.71 1.42 1.56
5.9953 4.44
6.00 8.16 19.31
10440
1.78 1.64 1.71
1.63 1.49 1.56
5.9953 4.44
6.00 8.62 19.31
10470
1.84 1.62 1.73
1.69 1.47 1.58
5.9953 4.42
4.00 8.44 17.25
10500
1.98 1.56 1.77
1.83 1.41 1.62
5.9953 4.38
4.00 8.44 17.13
10530
1.91 1.53 1.72
1.76 1.38 1.57
5.9953 4.43
4.00 8.92 17.28
10560
1.95 1.43 1.69
1.80 1.28 1.54
5.9953 4.46
4.00 8.84 17.37
10590
1.96 1.45 1.70
1.81 1.30 1.55
5.9953 4.45
4.00 9.17 17.34
10620
2.09 1.57 1.83
1.94 1.42 1.68
5.9953 4.32
4.00 6.72 16.95
10650
2.08 1.62 1.85
1.93 1.47 1.70
5.9953 4.30
4.00 7.52 16.89
10680
2.15 1.42 1.78
2.00 1.27 1.63
5.9953 4.37
4.00 7.53 17.10
10710
2.08 1.55 1.81
1.93 1.40 1.66
5.9953 4.34
4.00 7.15 17.01
10740
2.03 1.58 1.80
1.88 1.43 1.65
5.9953 4.35
4.00 7.44 17.04
10770
2.08 1.53 1.81
1.93 1.38 1.66
5.9953 4.34
4.00 8.16 17.01
10800
2.06 1.61 1.83
1.91 1.46 1.68
5.9953 4.32
4.00 8.51 16.95
10830
2.19 1.69 1.94
2.04 1.54 1.79
5.9953 4.21
4.00 6.21 16.62
10860
2.32 1.65 1.99
2.17 1.50 1.84
5.9953 4.16
4.00 7.31 16.47
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 250
10890
2.22 2.27 2.25
2.07 2.12 2.10
5.9953 3.90
4.00 6.14 15.69
10920
2.37 1.65 2.01
2.22 1.50 1.86
5.9953 4.14
4.00 7.13 16.41
10950
2.37 1.94 2.16
2.22 1.79 2.01
5.9953 3.99
6.00 6.30 17.96
10980
2.00 1.36 1.68
1.85 1.21 1.53
5.9953 4.47
6.00 11.00 19.40
11010
1.62 1.44 1.53
1.47 1.29 1.38
5.9953 4.62
4.00 10.09 17.85
11040
1.63 1.46 1.54
1.48 1.31 1.39
5.9953 4.61
4.00 15.31 17.82
11070
1.60 1.43 1.51
1.45 1.28 1.36
5.9953 4.64
4.00 10.23 17.91
11100
1.57 1.49 1.53
1.42 1.34 1.38
5.9953 4.62
4.00 9.96 17.85
11130
1.63 1.45 1.54
1.48 1.30 1.39
5.9953 4.61
4.00 9.58 17.82
11160
1.65 1.49 1.57
1.50 1.34 1.42
5.9953 4.58
4.00 9.06 17.73
11190
1.62 1.48 1.55
1.47 1.33 1.40
5.9953 4.60
4.00 9.20 17.79
11220
1.63 1.43 1.53
1.48 1.28 1.38
5.9953 4.62
4.00 9.47 17.85
11250
1.67 1.51 1.59
1.52 1.36 1.44
5.9953 4.56
4.00 9.46 17.67
11280
1.67 1.50 1.58
1.52 1.35 1.43
5.9953 4.57
4.00 9.52 17.70
11310
1.67 1.49 1.58
1.52 1.34 1.43
5.9953 4.57
4.00 9.16 17.70
11340
1.67 1.51 1.59
1.52 1.36 1.44
5.9953 4.56
4.00 8.67 17.67
11370
1.61 1.52 1.57
1.46 1.37 1.42
5.9953 4.58
4.00 8.33 17.73
11400
1.50 1.53 1.52
1.35 1.38 1.37
5.9953 4.63
4.00 7.78 17.88
11430
1.58 1.46 1.52
1.43 1.31 1.37
5.9953 4.63
4.00 7.90 17.88
11460
1.62 1.47 1.54
1.47 1.32 1.39
5.9953 4.61
6.00 6.89 19.82
11490
1.69 1.48 1.58
1.54 1.33 1.43
5.9953 4.57
6.00 6.73 19.70
11520
1.65 1.45 1.55
1.50 1.30 1.40
5.9953 4.60
4.00 6.82 17.79
11550
1.58 1.40 1.49
1.43 1.25 1.34
5.9953 4.66
4.00 8.19 17.97
11580
1.65 1.36 1.51
1.50 1.21 1.36
5.9953 4.64
4.00 9.10 17.91
11610
1.57 1.44 1.50
1.42 1.29 1.35
5.9953 4.65
4.00 9.17 17.94
11640
1.59 1.43 1.51
1.44 1.28 1.36
5.9953 4.64
4.00 8.42 17.91
11670
1.60 1.59 1.59
1.45 1.44 1.44
5.9953 4.56
4.00 7.76 17.67
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 251
11700
1.60 1.52 1.56
1.45 1.37 1.41
5.9953 4.59
4.00 8.57 17.76
11730
1.60 1.54 1.57
1.45 1.39 1.42
5.9953 4.58
4.00 9.18 17.73
11760
1.51 1.44 1.47
1.36 1.29 1.32
5.9953 4.68
4.00 9.57 18.03
11790
1.51 1.45 1.48
1.36 1.30 1.33
5.9953 4.67
4.00 7.83 18.00
11820
1.61 1.49 1.55
1.46 1.34 1.40
5.9953 4.60
4.00 5.41 17.79
11850
1.60 1.37 1.49
1.45 1.22 1.34
5.9953 4.66
4.00 7.52 17.97
11880
1.54 1.63 1.59
1.39 1.48 1.44
5.9953 4.56
4.00 6.86 17.67
11910
1.67 1.57 1.62
1.52 1.42 1.47
5.9953 4.53
4.00 6.63 17.58
11940
1.63 1.55 1.59
1.48 1.40 1.44
5.9953 4.56
6.00 7.78 19.67
11970
1.62 1.52 1.57
1.47 1.37 1.42
5.9953 4.58
6.00 7.45 19.73
12000
1.62 1.53 1.57
1.47 1.38 1.42
5.9953 4.58
4.00 7.50 17.73
12030
1.59 1.70 1.64
1.44 1.55 1.49
5.9953 4.51
4.00 6.83 17.52
12060
1.59 1.69 1.64
1.44 1.54 1.49
5.9953 4.51
4.00 6.00 17.52
12090
1.59 1.57 1.58
1.44 1.42 1.43
5.9953 4.57
4.00 6.41 17.70
12120
1.42 1.61 1.52
1.27 1.46 1.37
5.9953 4.63
4.00 6.95 17.88
12150
1.61 1.63 1.62
1.46 1.48 1.47
5.9953 4.53
4.00 7.22 17.58
12180
1.61 1.62 1.62
1.46 1.47 1.47
5.9953 4.53
4.00 7.56 17.58
12210
1.65 1.57 1.61
1.50 1.42 1.46
5.9953 4.54
4.00 8.11 17.61
12240
1.64 1.57 1.61
1.49 1.42 1.46
5.9953 4.54
4.00 7.85 17.61
12270
1.70 1.57 1.63
1.55 1.42 1.48
5.9953 4.52
4.00 7.42 17.55
12300
1.88 1.42 1.65
1.73 1.27 1.50
5.9953 4.50
4.00 7.23 17.49
12330
1.85 1.34 1.60
1.70 1.19 1.45
5.9953 4.55
4.00 8.21 17.64
12360
1.77 1.36 1.57
1.62 1.21 1.42
5.9953 4.58
4.00 8.10 17.73
12390
1.71 1.41 1.56
1.56 1.26 1.41
5.9953 4.59
6.00 8.02 19.76
12420
1.74 1.42 1.58
1.59 1.27 1.43
5.9953 4.57
6.00 8.26 19.70
12450
1.80 2.00 1.90
1.65 1.85 1.75
5.9953 4.25
4.00 7.87 16.74
12480
1.62 1.99 1.81
1.47 1.84 1.66
5.9953 4.34
4.00 7.11 17.01
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 252
12510
1.79 0.70 1.25
1.64 0.55 1.10
5.9953 4.90
4.00 7.98 18.69
12540
1.75 1.35 1.55
1.60 1.20 1.40
5.9953 4.60
4.00 7.93 17.79
12570
2.00 1.42 1.71
1.85 1.27 1.56
5.9953 4.44
4.00 6.51 17.31
12600
1.72 1.45 1.59
1.57 1.30 1.44
5.9953 4.56
4.00 6.71 17.67
12630
1.71 1.45 1.58
1.56 1.30 1.43
5.9953 4.57
4.00 8.35 17.70
12660
1.78 1.43 1.61
1.63 1.28 1.46
5.9953 4.54
4.00 7.93 17.61
12690
1.99 1.46 1.72
1.84 1.31 1.57
5.9953 4.43
4.00 7.65 17.28
12720
1.95 1.48 1.72
1.80 1.33 1.57
5.9953 4.43
4.00 7.78 17.28
12750
2.05 1.45 1.75
1.90 1.30 1.60
5.9953 4.40
4.00 6.76 17.19
12780
2.22 1.48 1.85
2.07 1.33 1.70
5.9953 4.30
4.00 7.38 16.89
12810
2.04 1.46 1.75
1.89 1.31 1.60
5.9953 4.40
4.00 9.00 17.19
12840
1.82 1.45 1.64
1.67 1.30 1.49
5.9953 4.51
4.00 10.55 17.52
12870
2.17 1.39 1.78
2.02 1.24 1.63
5.9953 4.37
4.00 9.65 17.10
12900
1.78 1.44 1.61
1.63 1.29 1.46
5.9953 4.54
6.00 7.87 19.61
12930
1.73 1.60 1.67
1.58 1.45 1.52
5.9953 4.48
6.00 9.50 19.43
12960
1.73 1.42 1.57
1.58 1.27 1.42
5.9953 4.58
4.00 8.35 17.73
12990
1.73 1.25 1.49
1.58 1.10 1.34
5.9953 4.66
4.00 8.00 17.97
13020
1.65 1.44 1.55
1.50 1.29 1.40
5.9953 4.60
4.00 7.34 17.79
13050
1.54 1.25 1.40
1.39 1.10 1.25
5.9953 4.75
4.00 6.72 18.24
13080
1.28 1.72 1.50
1.13 1.57 1.35
5.9953 4.65
4.00 7.00 17.94
13110
1.48 1.65 1.57
1.33 1.50 1.42
5.9953 4.58
4.00 7.80 17.73
13140
1.41 1.59 1.50
1.26 1.44 1.35
5.9953 4.65
4.00 8.20 17.94
13170
1.51 0.96 1.24
1.36 0.81 1.09
5.9953 4.91
4.00 8.06 18.72
13200
1.65 1.52 1.58
1.50 1.37 1.43
5.9953 4.57
4.00 7.10 17.70
13230
2.85 1.44 2.15
2.70 1.29 2.00
5.9953 4.00
4.00 7.31 15.99
13260
1.70 1.42 1.56
1.55 1.27 1.41
5.9953 4.59
4.00 6.93 17.76
13290
1.69 2.06 1.88
1.54 1.91 1.73
5.9953 4.27
4.00 6.06 16.80
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 253
13320
1.71 1.80 1.75
1.56 1.65 1.60
5.9953 4.40
4.00 6.22 17.19
13350
1.69 1.73 1.71
1.54 1.58 1.56
5.9953 4.44
4.00 7.09 17.31
13380
2.07 1.64 1.85
1.92 1.49 1.70
5.9953 4.30
4.00 7.96 16.89
13410
2.10 1.64 1.87
1.95 1.49 1.72
5.9953 4.28
6.00 8.88 18.83
13440
1.98 0.80 1.39
1.83 0.65 1.24
5.9953 4.76
6.00 7.67 20.27
13470
1.97 1.50 1.74
1.82 1.35 1.59
5.9953 4.41
4.00 7.56 17.22
13500
1.62 1.47 1.54
1.47 1.32 1.39
5.9953 4.61
4.00 7.51 17.82
13530
1.82 1.53 1.67
1.67 1.38 1.52
5.9953 4.48
4.00 8.24 17.43
13560
1.83 1.49 1.66
1.68 1.34 1.51
5.9953 4.49
4.00 7.30 17.46
13590
1.85 1.58 1.72
1.70 1.43 1.57
5.9953 4.43
4.00 7.71 17.28
13620
2.30 1.58 1.94
2.15 1.43 1.79
5.9953 4.21
4.00 7.90 16.62
13650
1.99 1.51 1.75
1.84 1.36 1.60
5.9953 4.40
4.00 8.33 17.19
13680
1.93 1.33 1.63
1.78 1.18 1.48
5.9953 4.52
4.00 8.74 17.55
13710
1.90 0.52 1.21
1.75 0.37 1.06
5.9953 4.94
4.00 8.06 18.81
13740
2.00 0.53 1.26
1.85 0.38 1.11
5.9953 4.89
4.00 6.75 18.66
13770
1.55 0.52 1.03
1.40 0.37 0.88
5.9953 5.12
4.00 6.87 19.35
13800
1.80 0.67 1.24
1.65 0.52 1.09
5.9953 4.91
4.00 6.75 18.72
13830
1.87 0.81 1.34
1.72 0.66 1.19
5.9953 4.81
4.00 7.17 18.42
13860
1.93 0.88 1.40
1.78 0.73 1.25
5.9953 4.75
4.00 7.30 18.24
13890
2.06 2.17 2.11
1.91 2.02 1.96
5.9953 4.04
6.00 8.87 18.11
13920
2.02 1.68 1.85
1.87 1.53 1.70
5.9953 4.30
6.00 8.64 18.89
13950
1.94 1.83 1.89
1.79 1.68 1.74
5.9953 4.26
4.00 8.38 16.77
13980
1.94 1.84 1.89
1.79 1.69 1.74
5.9953 4.26
4.00 8.09 16.77
14010
1.92 1.85 1.88
1.77 1.70 1.73
5.9953 4.27
4.00 7.53 16.80
14040
1.96 1.85 1.91
1.81 1.70 1.76
5.9953 4.24
4.00 8.39 16.71
14070
1.87 1.07 1.47
1.72 0.92 1.32
5.9953 4.68
4.00 7.45 18.03
14100
1.90 0.85 1.38
1.75 0.70 1.23
5.9953 4.77
4.00 6.79 18.30
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 254
14130
2.01 1.59 1.80
1.86 1.44 1.65
5.9953 4.35
4.00 7.13 17.04
14160
2.14 1.58 1.86
1.99 1.43 1.71
5.9953 4.29
4.00 7.80 16.86
14190
2.03 1.23 1.63
1.88 1.08 1.48
5.9953 4.52
4.00 6.78 17.55
14220
1.89 1.24 1.57
1.74 1.09 1.42
5.9953 4.58
4.00 7.48 17.73
14250
1.64 1.51 1.57
1.49 1.36 1.42
5.9953 4.58
4.00 7.96 17.73
14280
1.42 1.45 1.43
1.27 1.30 1.28
5.9953 4.72
4.00 8.43 18.15
14310
1.51 1.43 1.47
1.36 1.28 1.32
5.9953 4.68
4.00 6.26 18.03
14340
1.60 1.57 1.58
1.45 1.42 1.43
5.9953 4.57
4.00 6.75 17.70
14370
1.80 1.61 1.71
1.65 1.46 1.56
5.9953 4.44
4.00 7.42 17.31
14400
1.81 1.03 1.42
1.66 0.88 1.27
5.9953 4.73
6.00 6.32 20.18
14430
1.80 1.03 1.42
1.65 0.88 1.27
5.9953 4.73
6.00 6.55 20.18
14460
1.97 1.64 1.81
1.82 1.49 1.66
5.9953 4.34
4.00 7.81 17.01
14490
2.03 1.77 1.90
1.88 1.62 1.75
5.9953 4.25
4.00 7.02 16.74
14520
2.11 1.62 1.87
1.96 1.47 1.72
5.9953 4.28
4.00 6.59 16.83
14550
2.11 1.58 1.85
1.96 1.43 1.70
5.9953 4.30
4.00 6.61 16.89
14580
2.03 1.62 1.83
1.88 1.47 1.68
5.9953 4.32
4.00 8.77 16.95
14610
2.03 1.65 1.84
1.88 1.50 1.69
5.9953 4.31
4.00 8.48 16.92
14640
2.05 1.72 1.89
1.90 1.57 1.74
5.9953 4.26
4.00 7.19 16.77
14670
1.94 1.66 1.80
1.79 1.51 1.65
5.9953 4.35
4.00 6.69 17.04
14700
2.44 1.74 2.09
2.29 1.59 1.94
5.9953 4.06
4.00 8.48 16.17
14730
2.30 1.94 2.12
2.15 1.79 1.97
5.9953 4.03
4.00 7.98 16.08
14760
2.30 1.94 2.12
2.15 1.79 1.97
5.9953 4.03
4.00 6.40 16.08
14790
2.27 1.94 2.11
2.12 1.79 1.96
5.9953 4.04
4.00 6.26 16.11
14820
2.14 1.93 2.04
1.99 1.78 1.89
5.9953 4.11
4.00 6.43 16.32
14850
2.18 1.89 2.03
2.03 1.74 1.88
5.9953 4.12
4.00 7.07 16.35
14880
2.12 1.93 2.03
1.97 1.78 1.88
5.9953 4.12
4.00 8.42 16.35
14910
2.04 1.98 2.01
1.89 1.83 1.86
5.9953 4.14
6.00 6.38 18.41
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 255
14940
2.15 2.14 2.14
2.00 1.99 1.99
5.9953 4.01
6.00 6.25 18.02
14970
1.97 1.99 1.98
1.82 1.84 1.83
5.9953 4.17
4.00 5.27 16.50
15000
1.86 1.94 1.90
1.71 1.79 1.75
5.9953 4.25
4.00 5.68 16.74
15030
1.88 1.94 1.91
1.73 1.79 1.76
5.9953 4.24
4.00 6.50 16.71
15060
2.07 1.98 2.03
1.92 1.83 1.88
5.9953 4.12
4.00 5.81 16.35
15090
2.07 2.01 2.04
1.92 1.86 1.89
5.9953 4.11
4.00 4.39 16.32
15120
2.13 2.01 2.07
1.98 1.86 1.92
5.9953 4.08
4.00 5.14 16.23
15150
2.10 2.00 2.05
1.95 1.85 1.90
5.9953 4.10
4.00 5.22 16.29
15180
2.07 1.99 2.03
1.92 1.84 1.88
5.9953 4.12
4.00 5.18 16.35
15210
2.08 2.03 2.05
1.93 1.88 1.90
5.9953 4.10
4.00 5.10 16.29
15240
2.24 2.12 2.18
2.09 1.97 2.03
5.9953 3.97
4.00 6.08 15.90
15270
2.06 2.11 2.09
1.91 1.96 1.94
5.9953 4.06
4.00 5.06 16.17
15300
2.07 2.09 2.08
1.92 1.94 1.93
5.9953 4.07
4.00 4.59 16.20
15330
2.05 2.10 2.08
1.90 1.95 1.93
5.9953 4.07
4.00 4.86 16.20
15360
2.13 2.15 2.14
1.98 2.00 1.99
5.9953 4.01
4.00 4.60 16.02
15390
1.99 2.23 2.11
1.84 2.08 1.96
5.9953 4.04
6.00 4.83 18.11
15420
2.17 2.28 2.22
2.02 2.13 2.07
5.9953 3.93
6.00 4.70 17.78
15450
1.92 2.08 2.00
1.77 1.93 1.85
5.9953 4.15
4.00 3.91 16.44
15480
2.29 2.00 2.15
2.14 1.85 2.00
5.9953 4.00
4.00 4.56 15.99
15510
2.12 2.30 2.21
1.97 2.15 2.06
5.9953 3.94
4.00 3.74 15.81
15540
2.23 2.17 2.20
2.08 2.02 2.05
5.9953 3.95
4.00 7.17 15.84
15570
2.18 2.14 2.16
2.03 1.99 2.01
5.9953 3.99
4.00 5.90 15.96
15600
2.19 2.16 2.17
2.04 2.01 2.02
5.9953 3.98
4.00 7.44 15.93
15630
1.98 2.08 2.03
1.83 1.93 1.88
5.9953 4.12
4.00 6.14 16.35
15660
1.98 1.59 1.78
1.83 1.44 1.63
5.9953 4.37
4.00 5.35 17.10
15690
2.18 1.69 1.94
2.03 1.54 1.79
5.9953 4.21
4.00 5.61 16.62
15720
1.96 1.94 1.95
1.81 1.79 1.80
5.9953 4.20
4.00 5.12 16.59
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 256
15750
1.97 2.04 2.00
1.82 1.89 1.85
5.9953 4.15
4.00 5.85 16.44
15780
1.86 2.00 1.93
1.71 1.85 1.78
5.9953 4.22
4.00 6.31 16.65
15810
2.15 1.92 2.04
2.00 1.77 1.89
5.9953 4.11
4.00 6.64 16.32
15840
2.18 2.45 2.31
2.03 2.30 2.16
5.9953 3.84
4.00 5.38 15.51
15870
2.25 1.94 2.09
2.10 1.79 1.94
5.9953 4.06
4.00 5.93 16.17
15900
2.29 2.10 2.19
2.14 1.95 2.04
5.9953 3.96
6.00 5.83 17.87
15930
2.33 2.16 2.24
2.18 2.01 2.09
5.9953 3.91
6.00 5.40 17.72
15960
2.26 2.05 2.16
2.11 1.90 2.01
5.9953 3.99
4.00 5.73 15.96
15990
2.30 2.17 2.23
2.15 2.02 2.08
5.9953 3.92
4.00 5.83 15.75
16020
2.00 2.01 2.00
1.85 1.86 1.85
5.9953 4.15
4.00 5.96 16.44
16050
2.01 2.07 2.04
1.86 1.92 1.89
5.9953 4.11
4.00 7.38 16.32
16080
2.15 1.91 2.03
2.00 1.76 1.88
5.9953 4.12
4.00 5.74 16.35
16110
1.94 1.75 1.85
1.79 1.60 1.70
5.9953 4.30
4.00 5.89 16.89
16140
2.30 2.06 2.18
2.15 1.91 2.03
5.9953 3.97
4.00 6.78 15.90
16170
2.46 2.14 2.30
2.31 1.99 2.15
5.9953 3.85
4.00 5.25 15.54
16200
2.45 2.25 2.35
2.30 2.10 2.20
5.9953 3.80
4.00 4.85 15.39
16230
2.41 2.47 2.44
2.26 2.32 2.29
5.9953 3.71
4.00 4.60 15.12
16260
2.52 2.02 2.27
2.37 1.87 2.12
5.9953 3.88
4.00 4.58 15.63
16290
2.45 2.47 2.46
2.30 2.32 2.31
5.9953 3.69
4.00 5.35 15.06
16320
2.38 2.04 2.21
2.23 1.89 2.06
5.9953 3.94
4.00 6.69 15.81
16350
2.28 1.62 1.95
2.13 1.47 1.80
5.9953 4.20
4.00 6.31 16.59
16380
2.36 1.62 1.99
2.21 1.47 1.84
5.9953 4.16
4.00 7.60 16.47
16405
-0.49
-0.4
9 -0.49
-0.64
-0.6
4 -0.64
5.9953
6.64
6.00 0.00
25.91 1644
0 1.49 1.6
6 1.57 1.34 1.5
1 1.42 5.995
3 4.58 6.00 6.77
19.73
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 257
Annexure 3.6: Location for Proposed Protection/Gabion Wall
Chainage
Bottom
R.L. Top R.L.
Height
Top Widt
h
Bottom
width TW+BW/2 Area
M.Area
Length
Quantity
Protection Wall @ Ratan Kotha
7360 96.18 100.
50 4.3
2 1.00 9.64 5.32
22.98
7390 96.20 100.
50 4.3
0 1.00 9.60 5.30
22.79
22.89 30
686.59
7420 96.00 100.
50 4.5
0 1.00 10.00 5.50
24.75
23.77 30
713.10
7450 96.70 100.
50 3.8
0 1.00 8.60 4.80
18.24
21.50 30
644.85
7480 96.65 100.
50 3.8
5 1.00 8.70 4.85
18.67
18.46 30
553.69
7510 96.60 100.
50 3.9
0 1.00 8.80 4.90
19.11
18.89 30
566.74
7540 96.75 100.
50 3.7
5 1.00 8.50 4.75
17.81
18.46 30
553.84
7570 96.70 100.
50 3.8
0 1.00 8.60 4.80
18.24
18.03 30
540.79
7600 96.65 100.
50 3.8
5 1.00 8.70 4.85
18.67
18.46 30
553.69
7630 96.80 100.
50 3.7
0 1.00 8.40 4.70
17.39
18.03 30
540.94
7660 96.85 100.
50 3.6
5 1.00 8.30 4.65
16.97
17.18 30
515.44
7690 96.65 100.
50 3.8
5 1.00 8.70 4.85
18.67
17.82 30
534.68
7720 96.70 100.
50 3.8
0 1.00 8.60 4.80
18.24
18.46 30
553.69
7750 96.72 100.
50 3.7
8 1.00 8.56 4.78
18.07
18.15 30
544.63
7780 96.78 100.
50 3.7
2 1.00 8.44 4.72
17.56
17.81 30
534.40
7810 96.68 100.
50 3.8
2 1.00 8.64 4.82 18.4
17.99 30
539.56
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 258
1
7840 96.82 100.
50 3.6
8 1.00 8.36 4.68
17.22
17.82 30
534.52
7870 96.79 100.
50 3.7
1 1.00 8.42 4.71
17.47
17.35 30
520.45
7900 96.85 100.
50 3.6
5 1.00 8.30 4.65
16.97
17.22 30
516.70
7930 96.76 100.
50 3.7
4 1.00 8.48 4.74
17.73
17.35 30
520.50
7960 96.80 100.
50 3.7
0 1.00 8.40 4.70
17.39
17.56 30
526.76
7990 96.67 100.
50 3.8
3 1.00 8.66 4.83
18.50
17.94 30
538.33
8020 96.69 100.
50 3.8
1 1.00 8.62 4.81
18.33
18.41 30
552.38
8050 96.71 100.
50 3.7
9 1.00 8.58 4.79
18.15
18.24 30
547.20
8080 96.74 100.
50 3.7
6 1.00 8.52 4.76
17.90
18.03 30
540.78
8110 96.75 100.
50 3.7
5 1.00 8.50 4.75
17.81
17.86 30
535.65
8140 96.70 100.
50 3.8
0 1.00 8.60 4.80
18.24
18.03 30
540.79
8170 96.64 100.
50 3.8
6 1.00 8.72 4.86
18.76
18.50 30
554.99
8200 96.80 100.
50 3.7
0 1.00 8.40 4.70
17.39
18.07 30
542.24
8230 96.86 100.
50 3.6
4 1.00 8.28 4.64
16.89
17.14 30
514.19
8260 96.85 100.
50 3.6
5 1.00 8.30 4.65
16.97
16.93 30
507.93
8290 96.83 100.
50 3.6
7 1.00 8.34 4.67
17.14
17.06 30
511.67
8320 96.79 100.
50 3.7
1 1.00 8.42 4.71
17.47
17.31 30
519.19
8350 96.80 100.
50 3.7
0 1.00 8.40 4.70 17.3
17.43 30
522.96
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 259
9
8380 96.78 100.
50 3.7
2 1.00 8.44 4.72
17.56
17.47 30
524.23
8410 96.76 100.
50 3.7
4 1.00 8.48 4.74
17.73
17.64 30
529.29
8440 96.78 100.
50 3.7
2 1.00 8.44 4.72
17.56
17.64 30
529.29
8470 96.80 100.
50 3.7
0 1.00 8.40 4.70
17.39
17.47 30
524.23
8500 96.75 100.
50 3.7
5 1.00 8.50 4.75
17.81
17.60 30
528.04
8530 96.82 100.
50 3.6
8 1.00 8.36 4.68
17.22
17.52 30
525.52
8560 96.73 100.
50 3.7
7 1.00 8.54 4.77
17.98
17.60 30
528.08
8590 96.75 100.
50 3.7
5 1.00 8.50 4.75
17.81
17.90 30
536.93
8620 96.80 100.
50 3.7
0 1.00 8.40 4.70
17.39
17.60 30
528.04
8650 96.85 100.
50 3.6
5 1.00 8.30 4.65
16.97
17.18 30
515.44
8680 96.90 100.
50 3.6
0 1.00 8.20 4.60
16.56
16.77 30
502.99
8710 96.89 100.
50 3.6
1 1.00 8.22 4.61
16.64
16.60 30
498.03
Total Length in M.
1350
TOTAL QUANTITY IN M3
24393.9
5
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 260
Annexure 3.7: Cross sections of CD Works
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 261
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 262
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 263
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 264
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 265
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 266
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 267
Annexure 3.8: Quarry Map
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 268
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 269
Annexure 4.1: Strip Maps of The Direct Impact Zone
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 270
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 271
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 272
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 273
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 274
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 275
Annexure 5.1: Permission Letter from Mangroves Cell of Forest Department
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 276
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 277
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 278
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 279
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 280
ANNEXURE 6.1 : HIGH COURT NOTIFICATION FOR MANGROVE PROTECTION
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 281
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 282
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 283
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 284
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 285
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 286
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 287
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 288
’
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 289
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 290
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 291
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 292
Annexure 7.1: Inventory of Hot Spots, Critical and Sensitive Locations
Saline Embankment Narvel Benavale Project Area
Package: _____________________________________________________________ Data Sheet No. Date Time: Name of Enumerator: ……………………………………………………………………………
1. Location
Section (Km) Name of Village/ Urban Ward
Chainage in m City / urban area Taluka District Block Landmark Location GPS Coordinates Left side Right Side Lat Lon Informant details
Name Address
Contact No Occupation
2. Inventory of anticipated impacts 2.1 Traffic Congestion observed / projected
Location details Present During Construction After construction
2.2 Inventory of physical assets located in the corridor likely to be affected
Location details - Private Assets- Utility Public Assets– Utility Community Property Resources - Utility
2.3 Probable impact on assets
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 293
Who will be affected most
Temporary – shifting Permanent – Displacement
Inaccessibility (to shop etc.)
Private Assets Public Assets CPR
2.4 Likely inconvenience to public due to project (frequent visitors to the location)
Description of inconvenience
Temporary
Permanent Who will be affected most
2.5 Likely uncomfortable conditions for people (Inhabitants aside the locations)
Description of uncomfortable conditions
Temporary Permanent Who will be affected most
2.6 Likely impacts on accessibility to Livelihood resources– shops, business, individuals, households and others
Description of livelihood accessibility to resources
Temporary Permanent Who will be affected most
2.7 Impact on archaeological and cultural /tourist spots
2.8 Loss of Trees
Location and ownership – public, private
Species Density Area
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 294
2.9 Likely impact on movement / Transit corridors of cattle, wildlife
Location, Type of cattle Likely impact permanent
Likely impact – temporary
2.10 Likely impact on Air / Noise pollution
Location Air Noise Cumulative Impact
2.11 Land Acquisition requirements if any
Location Area in ha No of Project Affected Households
LA amounts to displacement of households
2.12 Any other Specify -
Name Signature
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 295
Annexure 7.2 : Format for Conducting Census
Name of Village / Ward No. Household : Date Name Sex Age Relation to Household Head (HH) Primary Occupation Secondary Occupation Number of HH Members Disaggregated by Sex Property Ownership with Estimated Value
• Structures
• Land and Type
• Other: Wells, Trees, Livestock Highest Level of Education Income
• Farm-based
• Off-farm labor
• Informal Sector Activities
• Other: Remittances Name and Signature of Surveyor Name and Signature of Informant
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 296
Annexure 7.3: List of PAP
S
r
.
N
o
.
F
r
o
m
R
e
d
u
c
i
n
g
D
i
s
t
a
n
c
e
(
R
D
)/
C
h
a
i
n
a
g
e
T
o
R
e
d
u
c
i
n
g
D
i
s
t
a
n
c
e
(
R
D
)/
C
h
a
i
n
a
g
e
Name
of the
Land
Owner
/s
Sur
vey
Nu
mb
er/
Gut
No
T
y
p
e
of
L
a
n
d
/
C
la
ss
ifi
ca
ti
o
n
of
L
a
n
d
Tot
al
Are
a in
the
Sur
vey
No.
Exis
ting
land
unde
r
emb
ank
men
t
Add
ition
al
land
area
requ
ired
for
emb
ank
men
t
O
n
t
h
e
S
e
a
/
C
r
e
e
k
S
i
d
e
(
1
)
o
r
L
a
n
d
w
o
r
d
/
C
o
n
t
r
y
s
i
d
e
Na
me
of
the
Titl
e
hol
der
/
lan
d
ow
ner
Lan
d
Own
ershi
p
{Go
vt.
(1) /
Pvt
(2)}
Remarks
Structures on the Exsting
Embankment Structures on the Proposed Embankment
(
Are
a in
Ha.
)
(
Area
in
Ha.)
(Are
a in
Ha.)
Houses
Area
(sqmtrs)
Catt
lesh
ed
T
r
e
e
s
(
S
p
e
c
i
e
s
a
n
d
N
u
m
b
e
r
s
)
Commun
Utilities
(Cremitorium
/Temple/Wat
er Tanks
/Electric
Polls/Hand
Pumps etc)
An
y
Ot
her
Houses
Area
(sqmtrs)
C
a
t
t
l
e
s
h
e
d
Fis
h
Po
nd
Trees
(Speci
es and
Numb
ers)
C
o
m
m
u
n
U
t
i
l
i
t
i
e
s
(
C
r
e
m
i
t
o
r
i
u
m
/
T
e
m
p
l
e
/
Any Other
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 297
(
2
)
W
a
t
e
r
T
a
n
k
s
/
E
l
e
c
t
r
i
c
P
o
l
l
s
/
H
a
n
d
P
u
m
p
s
e
t
c
)
1 2 3 4
5 6 7 8 9 1
0 11 12 13 14 15
1
6 17 18 19
2
0 21 22
2
3 24
Kales
hriva
di
1 0 5
1
Shri.
Ganap
ati
Dev
Vahiva
210
P
V
T.
0.9
4.3
0.00
9
0.00
58 2
PV
T. PVT.
Permane
nt/Reside
ntial
Hou
ses
(f/s)
6
2
s
q
m
- -
Electrical
pole @
ch.5m
- - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 298
tdar t
2
Ravika
nt
Naray
an
Thaku
r
3
Arun
Naray
an
Thaku
r
4
Jayshr
ee
Naray
an
Thaku
r
5
Shaku
ntala
Naray
an
Thaku
r
6
Rajash
ri
Naray
an
Thaku
r
7
Kishor
Naray
an
Thaku
r
8
Niraba
i
Naray
an
Thaku
r
9 1
2
3
6
Ravika
nt
Naray
an
Thaku
211
P
V
T.
0.0
2.2
0.00
54
0.00
46 2
PV
T. PVT. - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 299
r
1
0
Arun
Naray
an
Thaku
r
1
1
Jayshr
ee
Naray
an
Thaku
r
1
2
Shaku
ntala
Naray
an
Thaku
r
1
3
Rajash
ri
Naray
an
Thaku
r
1
4
Kishor
Naray
an
Thaku
r
1
5
Niraba
i
Naray
an
Thaku
r
1
6
5
1
1
5
6
Mada
n
Shank
ar
Patil
190
P
V
T.
0.5
7.9
0.08
37
0.07
59 2
PV
T. PVT. - - - - - - - - - - - - - -
1
7 &
Rama
n
Shank
ar
Patil
1 3 1 Anjani
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 300
8 8 8
3
Babur
ao
Patil
1
9
Rajani
Shashi
kant
mokal
2
0
Rohini
Shank
ar
Patil
2
1
Mukta
bai
Shank
ar
Patil
2
2
1
5
6
1
9
7
Tai
Murali
dhar
Mhatr
e
192
P
V
T
0.5
4.4
0.01
3
0.01
75 1 -
W.C
BLO
CK
(f/s)
2
s
q
m
t
- - - - - - - - - - -
2
3
Shank
ar
Murali
dhar
Mhatr
e
2
4
Geeta
Govar
dhan
Patil
2
5
Pramil
a
Rohid
as
Patil
2
6
1
9
1
2
4
0
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
189
P
V
T.
0.1
5.4
0.03
1
0.03
21 2
PV
T. PVT. - - - - - - - - - - - - - -
2
7
2
3
2
6
Shri.
Marut188
P
V
0.0
9.4
0.00
32
0.01
56 2
PV
T. PVT. - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 301
4 0 i Dev
Vastav
ya
Kalesh
ri
T.
2
8
Pandu
rang
Hasu
Patil
2
9
Shara
d
Vasan
t Patil
3
0
2
4
0
3
1
6
Sunil
Prabh
akar
Thaku
r 187
P
V
T.
0.5
6.2
0.03
68
0.04
85 2
PV
T. PVT. - - - - - - - - - - - - - -
3
1
Suhas
Prabh
akar
Thaku
r
3
2
3
0
5
3
2
5
Hasu
Shank
ar
Mhatr
e
177
P
V
T.
0.2
9.0
0.00
01
0.00
31 2
PV
T. PVT.
3
3
Motir
am
Shank
ar
Mhatr
e
3
4
Hashi
Hiru
Mhatr
e
3
5
Vishn
u
Raghu
nath
Mhatr
e
3
6
Vasan
t
Raghu
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 302
nath
Mhatr
e
3
7
Kamla
kar
Raghu
nath
Mhatr
e
3
8
Sitabai
Vitthal
Mhatr
e
3
9
Taram
ati
Harish
chand
ra
Mhatr
e
4
0
3
8
8
7
0
2
Comp
any
S.E.Z
168
/1
P
V
T.
0.8
3.7
0.04
39
0.18
58 2
PV
T. PVT.
- - - - - - - - - - - - - -
4
1
Comp
any
S.E.Z
168
/2
P
V
T.
0.4
5.0
PV
T. PVT.
4
2
Comp
any
S.E.Z
168
/3
P
V
T.
0.4
5.0
PV
T. PVT.
4
3
Arvind
Nilkan
th
Thaku
r
168
/4A
P
V
T.
0.6
5.0
PV
T. PVT.
4
4
Kumar
Nilkan
th
Thaku
r
168
/4B
P
V
T.
0.6
0.0
PV
T. PVT.
4
5
Comp
any
S.E.Z
168
/5
P
V
T.
0.8
0.0
PV
T. PVT.
4
6
Comp
any
S.E.Z
168
/6
P
V
T.
0.3
7.8
PV
T. PVT.
4
7
1
2
1
3
Shri.
Marut
158
/1
P
V
0.3
8.4 0
0.00
33 2
PV
T. PVT. - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 303
9
0
1
0
i Dev
Vastav
ya
Kalesh
ri
T.
4
8
Pandu
rang
Hasu
Patil
4
9
Shara
d
Vasan
t Patil
5
0
Shri.
Marut
i Dev
Vastav
ya
Kalesh
ri 158
/2
P
V
T.
0.3
6.9
PV
T. PVT.
5
1
Pandu
rang
Hasu
Patil
5
2
Shara
d
Vasan
t Patil
5
3
Shri.
Marut
i Dev
Vastav
ya
Kalesh
ri 158
/3
P
V
T.
0.2
9.8
PV
T. PVT.
5
4
Pandu
rang
Hasu
Patil
5
5
Shara
d
Vasan
t Patil
5
6
Shri.
Marut
i Dev
Vastav
158
/4
P
V
T.
1.4
2.4
PV
T. PVT.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 304
ya
Kalesh
ri
5
7
Pandu
rang
Hasu
Patil
5
8
Shara
d
Vasan
t Patil
5
9
Gover
nment
land 154
G
o
vt
.
13.
55.
0
0.77
61
0.97
99
1
&
2
Go
vt.
Govt
. - - - - - - - - - - - - - -
6
0
1
7
7
0
1
8
2
6
Sitabai
Jayra
m
Thaku
r
153
P
V
T.
0.0
3.0
0.01
35
0.03
88 1
PV
T. PVT. - - - - -
Electrical
pole @
ch.1833m
- - - - - - - -
6
1
Mahar
udra
Jayra
m
Thaku
r
6
2
Pralha
d
Jayra
m
Thaku
r
6
3
Rampr
asad
Jayra
m
Thaku
r
6
4
Bhagy
ashri
Dhar
mendr
a
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 305
6
5
Ganpa
t
Laksh
man
Thaku
r
6
6
Parsh
uram
Laksh
man
Thaku
r
6
7
Hausa
bai
Laksh
man
Thaku
r
6
8
Sunita
Laksh
man
Thaku
r
6
9
Yasho
dha
Yashw
ant
Thaku
r
7
0
Hanu
mant
Yashw
ant
Thaku
r
7
1
Pandh
arinat
h
Yashw
ant
Thaku
r
7
2
Hiraba
i
Yashw
ant
Thaku
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 306
r
7
3
Bharat
i
Yashw
ant
Thaku
r
7
4
Sudha
Yashw
ant
Thaku
r
7
5
Shant
abai
Yashw
ant
Thaku
r
7
6
Gauta
m
Yashw
ant
Thaku
r
7
7
Devta
Yashw
ant
Thaku
r
7
8
Ravika
nt
Babur
ao
Thaku
r
7
9
1
8
2
6
1
8
1
8
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
152
P
V
T.
0.2
6.3
0.00
03
0.00
07 2
PV
T. PVT. - - - - - - - - - - - - - -
- - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 307
Tukar
amwa
di
(Kano
ba)
- - - - - - - - - - - - - -
8
0
1
8
2
5
1
9
5
0
Gover
nment
of
mahar
ashtra
62
G
O
V
T.
3.1
1
0.08
21
0.08
95 1
GO
VT.
GOV
T.
Temporar
y/Reside
ntial
(Govt.
land)
- - - -
Electrical
pole @
ch.1892m
Electrical
pole @
ch.2445m
-
H
o
u
s
e
(
c
/
s
)
42
sqmt
- - - - Farm Pond at
ch.2438m
H
o
u
s
e
(
c
/
s
)
40
sqmt
H
o
u
s
e
(
c
/
s
)
42
sqmt
H
o
u
s
e
(
c
/
s
)
20
sqmt
H
o
34
sqmt
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 308
u
s
e
(f
/
s
)
8
1
1
9
1
0
1
9
2
9
Rama
bai
Ramc
handra
Thaku
r
100
P
V
T
1.8
8.6
0.00
36
0.00
41 2
PV
T PVT - - - - - - - - - - - - - -
8
2
Shridh
ar
Ramc
handra
Thaku
r
8
3
Janard
an
Ramc
handra
Thaku
r
8
4
Gajan
an
Ramc
handra
Thaku
r
8
5
Pravin
Ramc
handra
Thaku
r
8
6
Jayva
nti
Murali
dhar
Patil
8
7
Sunan
da
Pandu
rang
Muka
dam
8
8
Kaush
alya
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 309
Rames
h Patil
8
9
Sunita
Gajan
an
Mhatr
e
9
0
Gunva
nti
Chang
dev
Mhatr
e
9
1
1
8
9
6
1
9
1
8
Vittha
l
Naray
an
Koli
103
P
V
T
0.0
1.0
0.00
82 0 1
PV
T PVT - - - - - - - - - - - - - -
9
2
1
9
1
8
1
9
4
0
Ganpa
t
Rama
Koli
102
P
V
T
0.0
1.0
0.00
35 0 1
PV
T PVT - - - - - - - - - - - - - -
9
3
Nagib
ai
Ganpa
t Koli
9
4
Parshu
ram
Ganpa
t Koli
9
5
Kamla
kar
Ganpa
t Koli
9
6
Prabh
akar
Ganpa
t Koli
9
7
Tai
Ganpa
t Koli
Tukar
amwa
di
(Kano
ba)
- - - - - - - - - - - - - -
1 1
9
2
5
Gover
nment 62
GO
VT.
3.1
1
0.3
332
0.1
925 1
GO
VT.
GO
VT.
Tempora
ry/Resid- - - -
Electric
al pole -
House
(c/s)
42
sqm- - - -
Farm Pond at
ch.2438m
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 310
5
0
3
8
of
mahar
ashtra
ential
(Govt.
land)
@
ch.1892
m
Electric
al pole
@
ch.2445
m
t
House
(c/s)
40
sqm
t
House
(c/s)
42
sqm
t
House
(c/s)
20
sqm
t
House
(f/s)
34
sqm
t
2
1
9
6
6
1
9
8
4
Devaji
Krush
na
Mhatr
e
74 PV
T
0.2
6.3 0
0.0
045 2
PV
T
PV
T - - - - - - - - - - - - - -
3
1
9
8
4
2
0
2
7
Vasan
t
Tukar
am
Mhatr
e
73 PV
T
0.2
3.5 0
0.0
147 2
PV
T
PV
T - - - - - - - - - - - - - -
4
2
0
2
7
2
0
6
1
Balira
m
Namd
ev
Mhatr
e
72 PV
T
0.1
8.2 0
0.0
07 2
PV
T
PV
T - - - - - - - - - - - - - -
5
2
0
6
4
2
0
8
7
Balaji
Ragha
Mhatr
e
71 PV
T
0.1
9.2 0
0.0
038
2.0.
0
PV
T
PV
T - - - - - - - - - - - - - -
6
Hiriba
i
Kamal
Mhatr
e
7
Ramd
as
Kamal
Mhatr
e
8
Raghu
pati
Kamal
Mhatr
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 311
e
9
Krush
na
Kamal
Mhatr
e
1
0
2
0
8
7
2
1
1
5
Shrav
ani
Joma
Mokal
70 PV
T
0.1
7.2 0
0.0
087
2.0.
0
PV
T
PV
T - - - - - - - - - - - - - -
1
1
Dattar
am
Dhava
ji
Mokal
1
2
Atmar
am
Dhava
ji
Mokal
1
3
Parash
uram
Dhava
ji
Mokal
1
4
Balira
m
Dhava
ji
Mokal
1
5
Vijay
Dhava
ji
Mokal
1
6
Sumat
i
Madh
ukar
Mhatr
e
1
7
Devku
bai
Dhava
ji
Mokal
1
8
Chhay
a
Devic
handra
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 312
Patil
1
9
2
1
1
5
2
1
7
2
Janard
an
Budhy
a
Mhatr
e
69 PV
T
0.2
8.4 0
0.0
353 2
PV
T
PV
T - - - - - - - - - - - - - -
2
0
2
1
7
2
2
1
9
1
Shri
Maruti
Devaj
Sthan
Vahiv
at
68 PV
T
0.0
5.6 0
0.0
118 2
PV
T
PV
T - - - - - - - - - - - - - -
2
1
Gana
Maha
du
Mhatr
e
2
2
Balaji
Nama
Mhatr
e
2
3
2
1
9
1
2
2
7
4
Naray
n
Ramaj
i
Mhatr
e
67 PV
T
0.3
2.4
0.0
254
0.0
463 2
PV
T
PV
T
Permane
nt/Resid
ential
House
(f/s)
79
sq
mt
- - - - - - - - - - -
2
4
2
2
7
4
2
3
7
3
Janard
an &
Balaji
Budhy
a
Mhatr
e
64 PV
T
0.2
8.3
0.0
595
0.0
385 2
PV
T
PV
T - - - - - - - - - - - - - -
2
5
2
1
7
1
2
4
1
9
Gover
nment
of
mahar
ashtra
63 GO
VT.
0.1
0.4
0.0
582
0.0
568 1
GO
VT.
GO
VT. - - - - - - - - - - - - -
Farm Pond at
ch. 2378m
Moth
e bhal
2
6
2
5
5
7
2
6
4
0
Anant
Pandu
rang
Mhatr
e
38 PV
T
0.1
9.3
0.0
719
0.0
541
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 313
2
7
2
5
4
3
2
5
5
7
Rama
Joma
Mhatr
e
39 PV
T
0.0
8.2 0
0.0
043 2
PV
T
PV
T - - - - - - - - - - - - - -
Creek
side
0.0
176
0.0
182 1
- - - - - - - - - - - - - -
Vittha
lwadi - - - - - - - - - - - - - -
2
8
2
6
3
5
2
6
7
2
Natha
Vama
n
Mhatr
e
43
7
PV
T
0.4
3.5
0.0
089
0.0
224 2
PV
T
PV
T - - - - - - - - - - - - - -
2
9
Balkru
shna
Vama
n
Mhatr
e
3
0
Ramd
as
Vama
n
Mhatr
e
3
1
Bayob
ai
Janard
an
Patil
3
2
Bhagu
bai
Balira
m
Patil
3
3
Gangu
bai
Aabaji
Patil
3
4
Annap
urna
Kesha
v
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 314
3
5
Mathu
ra
Bhask
ar
Patil
3
6
2
6
7
2
2
6
9
0
Pandu
rang
Shivar
am
Mhatr
e 43
6
PV
T
0.1
6.9
0.0
049
0.0
131 2
PV
T
PV
T - - - - - - - - - - - - -
Farm Pond at
ch. 2675m
(combine
436,435 &
434) 3
7
Shank
untala
Shivar
am
Mhatr
e
3
8
2
6
9
0
2
7
1
1
Kashin
ath
Chang
a
Mhatr
e
43
5
PV
T
0.2
6.7
0.0
041
0.0
184 2
PV
T
PV
T - - - - - - - - - - - - - -
3
9
2
7
1
1
2
7
3
1
Pandu
rang
Shivar
am
Mhatr
e
43
4
PV
T
0.3
0.6
0.0
021
0.0
175 2
PV
T
PV
T - - - - - - - - - - - - - -
4
0
2
7
3
1
2
7
6
8
Nagib
ai
Rama
Mhatr
e
43
2
PV
T
0.2
63
0.0
082
0.0
261 2
PV
T
PV
T - - - - - - - - - - - - - -
4
1
Narha
ri
Rama
Mhatr
e
4
2
Vasud
ev
Rama
Mhatr
e
4
3
Vatsal
a
Vasan
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 315
t
Mhatr
e
4
4
Vinaya
k
Vasan
t
Mhatr
e
4
5
Minak
shi
Vasan
t
Mhatr
e
4
6
Vanita
Pramo
d
Mhatr
e
4
7
Shank
untala
Anant
Mhatr
e
4
8
Sandip
Anant
Mhatr
e
4
9
Nitin
Anant
Mhatr
e
5
0
Sanjiv
ani
Anant
Mhatr
e
5
1
Indum
ati
Anant
Mhatr
e
5
2
Sindh
u
Shant
aram
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 316
Patil
5
3
2
7
6
8
2
7
9
5
Shanti
bai
Joma
Katho
d
Mhatr
e
42
8
PV
T
0.1
3.2
0.0
083
0.0
233 2
PV
T
PV
T - - - - - - - - - - - - -
Farm Pond at
ch.2784m
(combine 428
& 427)
5
4
2
7
9
5
2
8
0
7
Naga
Chang
a
Mhatr
e
42
7
PV
T
0.0
8.6
0.0
031
0.0
1 2
PV
T
PV
T - - - - - - - - - - - - - -
5
5
Ramac
handr
a
Chang
a
Mhatr
e
5
6
Budhi
bai
Joma
Mhatr
e
5
7
Barku
bai
Tukar
am
Patil
5
8
2
8
0
7
2
8
2
8
Parvat
i
Marut
i
Mhatr
e
42
6
PV
T
0.0
9.1
0.0
015
0.0
188 2
PV
T
PV
T - - - - - - - - - - - - - - 5
9
Sunan
da
Parsh
uram
Patil
6
0
Chand
ralekh
a
Marut
i
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 317
Mhatr
e
6
1
Laksh
mi
Bhau
Patil
6
2
Usha
Marut
i
Mhatr
e
6
3
Gulab
Ambaj
i Patil
6
4
2
8
2
8
2
8
5
8
Vama
n
Naga
Mhatr
e
41
9
PV
T
0.3
2.4 0
0.0
252 2
PV
T
PV
T - - - - - - - - - - - - -
Farm Pond at
ch. 2829m
6
5
Babib
ai
Bacch
u Patil
6
6
Tai
Balkru
shna
Mhatr
e
6
7
2
8
5
8
2
8
9
0
Balu
Ambu
Mhatr
e
41
8
PV
T
0.3
5.1 0
0.0
277 2
PV
T
PV
T - - - - - - - - - - - - -
Farm Pond at
ch.2847m
(combine 418
& 419)
6
8
Pandu
rang
Balu
Mhatr
e
6
9
Surek
ha
Subha
sh
Patil
7
0
2
8
9
0
2
9
2
4
Ratna
kar
Krush
na
Mhatr
41
7
PV
T
0.3
5.1 0
0.0
236 2
PV
T
PV
T - - - - - - - - - - - - -
Farm Pond at
ch. 2893m
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 318
e
7
1
2
9
2
4
2
9
5
0
Ramc
handr
a
Nagaji
Mhatr
e
41
6
PV
T
0.3
5.2 0
0.0
161 2
PV
T
PV
T - - - - - - - - - - - - -
Farm Pond at
ch. 2925m
7
2
Namd
ev
Nagaji
Mhatr
e
7
3
Manju
la
Chand
rakant
Mhatr
e
7
4
2
9
5
0
2
9
6
5
Vijaya
Dhar
maji
Mhatr
e
41
5
PV
T
0.2
2.0 0
0.0
005 2
PV
T
PV
T - - - - - - - - - - - - - -
7
5
2
9
6
5
3
0
2
5
Arjun
Pandu
rang
Mhatr
e
41
3/
2
PV
T
0.9
5.1 0
0.0
221 2
PV
T
PV
T - - - - - - -
House(f
/s)
29
sqm
t
- - - - -
7
6
3
1
8
8
3
2
4
7
Lahu
Shank
ar
Mhatr
e
40
5
PV
T
0.6
9.4
0.0
161 0 2
PV
T
PV
T - - - - - - - - - - - - - -
7
7
3
2
8
4
3
4
2
5
Raghu
pati
Tanhu
Mhatr
e
40
2
PV
T
1.3
48
0.0
67 0 2
PV
T
PV
T -
7
8
Murali
dhar
Tanhu
Mhatr
e
7
9
Randh
ir
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 319
Tanhu
Mhatr
e
8
0
Subha
sh
Tanhu
Mhatr
e
8
1
Girija
Dhar
maji
Patil
8
2
3
4
2
5
3
4
5
3
Nagub
ai
Tanhu
Mhatr
e
8
3
Gauri
Ganpa
t
Mhatr
e
40
0
PV
T
0.0
0.7
0.0
129 0 2
PV
T
PV
T - - - - - - - - - - - - - -
8
4
Dhar
maji
Ganpa
t
Mhatr
e
8
5
Nama
Ganpa
t
Mhatr
e
8
6
Chand
rabha
ga
Ramc
handr
a Patil
8
7
Tai
Balaji
Mhatr
e
8
8
Nita
Natha
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 320
8
9
Prasha
nt
Natha
Mhatr
e
9
0
Ashish
Natha
Mhatr
e
9
1
Vanda
na
Shashi
kant
Patil
9
2
Ranja
na
Shank
ar
Patil
9
3
Nayan
a
Parag
Sharm
a
9
4
Sima
Natha
Mhatr
e
9
5
3
4
5
3
3
5
0
6
Laksh
man
Hiru
Mhatr
e
39
9
PV
T
0.1
9.8
0.0
226 0 2
PV
T
PV
T - - - - - - - - - - - - - -
9
6
Janard
an
Laksh
man
Mhatr
e
9
7
Vishva
nath
Laksh
man
Mhatr
e
9
8
Rajara
m
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 321
Laksh
man
Mhatr
e
9
9
3
5
0
6
3
5
4
3
Ganga
ram
Chang
a
Mhatr
e 39
3
PV
T
0.2
0.5
0.0
105 0 2
PV
T
PV
T - - - - - - - - - - - - - -
1
0
0
Dhar
maji
Ganpa
t
Mhatr
e
1
0
1
3
5
4
3
3
6
0
4
Gauri
Ganpa
t
Mhatr
e
39
2
PV
T
0.3
9.0
0.0
043
0.0
025 2
PV
T
PV
T - - - - - - - - - - - - - -
1
0
2
Dhar
maji
Ganpa
t
Mhatr
e
1
0
3
Natha
Ganpa
t
Mhatr
e
1
0
4
Vasan
t
Ganpa
t
Mhatr
e
1
0
5
Chand
rabha
ga
Ramc
handr
a Patil
1
0
6
Tai
Balaji
Mhatr
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 322
e
1
0
7
Lina
Nasha
Mhatr
e
1
0
8
Prasha
nt
Natha
Mhatr
e
1
0
9
Aatish
Natha
Mhatr
e
1
1
0
Vanda
na
Shashi
kant
Patil
1
1
1
Ranja
na
Shank
ar
Patil
1
1
2
Nayan
a
Parag
Sharm
a
1
1
3
Sima
Natha
Mhatr
e
A 0.0
011 0 1
A1 0 0.0
391 1
1
1
4
3
6
0
5
3
6
1
7
Tulshi
das
Rama
Mhatr
e
39
1
PV
T
0.6
7.0
0.0
029 0 2
PV
T
PV
T - - - - - - - - - - - - - -
1
1
5
3
6
1
7
3
6
3
7
Barku
bai
Gana
Mhatr
39
0
PV
T
0.0
6.3
0.0
017
0.0
001 2
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 323
e
1
1
6
Jaywa
nt
Gana
Mhatr
e
1
1
7
Balkru
shna
Gana
Mhatr
e
1
1
8
Shrira
m
Gana
Mhatr
e
1
1
9
Anant
Gana
Mhatr
e
1
2
0
3
6
3
7
3
6
8
0
Eknat
h
Maha
du
Mhatr
e
38
9
PV
T
0.2
3.0
0.0
005
0.0
007 2
PV
T
PV
T - - - - - - - - - - - - - -
1
2
1
3
8
2
5
3
8
7
5
Parvat
i
Marut
i
Mhatr
e
37
8
PV
T
0.1
9.2
0.0
013
0.0
002 2
PV
T
PV
T - - - - - - - - - - - - - -
1
2
2
Sunan
da
Parsh
uram
Patil
1
2
3
Chand
ralekh
a
Marut
i
Mhatr
e
1
2
Laksh
mi
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 324
4 Bhau
Patil
1
2
5
Usha
Marut
i
Mhatr
e
1
2
6
Gulab
Ambaj
i Patil
1
2
7
Vijaya
Namd
ev
Mhatr
e
1
2
8
Rajash
ri
Marut
i
Mhatr
e
1
2
9
Vanda
na
Marut
i
Mhatr
e
1
3
0
Santos
h
Marut
i
Mhatr
e
1
3
1
Mruna
li
Bhau
Patil
1
3
2
Sonali
Bhau
Patil
1
3
3
3
8
7
5
3
9
6
7
Tarab
ai
Krush
na
Mhatr
e
37
7
PV
T
0.5
2.9
0.0
093
0.0
009 2
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 325
1
3
4
Sudhir
Krush
na
Mhatr
e
1
3
5
Prasha
nt
Krush
na
Mhatr
e
1
3
6
Milind
Krush
na
Mhatr
e
1
3
7 3
9
6
7
4
0
6
1
Maha
dev
Lahu
Mhatr
e 36
5
PV
T
0.5
6.9
0.0
025 0 2
PV
T
PV
T - - - - - - - - - - - - - -
1
3
8
Namd
ev
Lahu
Mhatr
e
1
3
9
4
1
3
5
4
1
7
8
Janard
an
Ambo
Mhatr
e
36
2
PV
T
0.3
6.9
0.0
089 0 2
PV
T
PV
T - - - - - - - - - - - - - -
1
4
0
Sadas
hiv
Ambo
Mhatr
e
1
4
1
Raghu
nath
Ambo
Mhatr
e
1
4
2
Ambib
ai
Ambo
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 326
1
4
3
4
1
7
8
4
2
3
4
Rukmi
ni
Balu
Mhatr
e
36
1
PV
T
0.3
8.4
0.0
155 0 2
PV
T
PV
T - - - - - - - - - - - - - -
1
4
4
Balu
Ambu
Mhatr
e
1
4
5
Surek
ha
Subha
sh
Patil
1
4
6
4
2
6
6
4
3
2
2
Shant
aram
Vithu
Mhatr
e
35
9
PV
T
0.2
1.0
0.0
249
0.0
047 2
PV
T
PV
T - - - - - - - - - - - - - -
1
4
7 4
3
2
2
4
3
5
6
Chand
rabha
ga
Jayra
m
Mhatr
e 35
8
PV
T
0.1
3.1
0.0
209
0.0
083 2
PV
T
PV
T - - - - - - - - - - - - - -
1
4
8
Mang
esh
Jayra
m
Mhatr
e
1
4
9
4
3
5
6
4
3
9
5
Gopal
Shivar
am
Mhatr
e
35
7
PV
T
0.1
3.7
0.0
234
0.0
011 2
PV
T
PV
T - - - - - - - - - - - - - -
1
5
0
4
3
9
5
4
4
8
9
Anant
Pandu
rang
Mhatr
e
35
6
PV
T
0.4
6.8
0.0
492 0 2
PV
T
PV
T - - - - - - - - - - - - - -
1
5
1
4
4
8
9
4
5
3
2
Hari
Aalu
Mhatr
e
35
5
PV
T
0.2
1.5
0.0
239 0 2
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 327
1
5
2
4
5
3
2
4
7
1
7
Joma
Kayor
Patil
35
3
PV
T
0.5
3.3
0.0
395
0.0
006 2
PV
T
PV
T - - - - - - - - - - - - - -
1
5
3
4
7
6
2
4
7
7
7
Nitin
Shant
aram
Mhatr
e
34
8
PV
T
0.1
2.1
0.0
024
0.0
003 2
PV
T
PV
T - - - - - - - - - - - - - -
B 0.0
312 0
B1 0 0.2
229
C 0.0
14
0.0
079
1
5
4
4
8
0
7
4
8
4
5
Radhi
bai
Br.Bal
aji
Mhatr
e
34
1
PV
T
0.2
3.7
0.0
125
0.0
064 2
PV
T
PV
T - - - - - - - - - - - - - -
1
5
5
Vilas
Shant
aram
Mhatr
e
1
5
6
Lata
Murali
dhar
Mhatr
e
D 0.0
371 0 1
1
5
7
2
6
4
0
3
5
1
8
Gover
nment
of
Mahar
ashtra
35
4
P
Go
vt.
18.
08.
0
1.2
16
1.2
99 1
Go
vt.
Go
vt.
- House
(c/s)
15
sq
mt
- - - - - - - - - - -
3
6
0
0
3
6
5
5
- House
(c/s)
15
sq
mt
- - - - - - - - - - -
4
7
6
2
4
8
4
0
- House
(c/s)
16
sq
mt
- - - - - - - - - - -
1
5
4
8
6
6- - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 328
8 5
9
8
9
1
5
9
4
9
1
4
4
9
3
1
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
48
8
PV
T
0.3
9.9
0.0
017 0 2 - - - - - - - - - - - - - -
1
6
0
5
0
0
0
5
0
4
4
Sadas
hiv
Shivra
m
Mhatr
e
48
7
PV
T
0.4
1.4
0.0
014
0.0
015 2 - - - - - - - - - - - - - -
A 1.2
157
0.6
786
B 0.0
106 0
C 0.1
037 0
D 0.0
516 0
K 0 0.0
132
L 0 0
M 0 0.7
998
Moth
e bhal
A 0.2
012
0.3
596
B 0.0
49
0.0
062
1
6
1
7
1
8
7
7
2
6
0
Poi
Vahal
39
7
2.7
4.0
0.0
323
0.0
352 2
PV
T
PV
T - - - - - - - - - - - - - -
1
6
2
7
2
5
8
7
2
6
6
Mumb
ai
Vishes
h
Arthik
39
4
PV
T
0.4
1.4
0.0
003
0.0
009 2
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 329
kshetr
a
comp
any
Lakh
ola
1
6
3
7
2
5
3
7
3
2
5
Gajan
an
Ganpa
t
Mhatr
e
48
7
PV
T
0.5
1.7
0.0
3
0.0
625
1 PV
T
PV
T - - - - - - - - - - - - - -
1
6
4
7
3
2
5
7
3
5
8
Ramkr
ushan
a
Naga
Mhatr
48
8
PV
T
0.4
6.7
0.0
138
0.0
308 1
PV
T
PV
T - - - - - - - - - - - - - -
1
6
5
7
3
5
8
7
3
9
5
Savita
Vidya
dhar
Patil
48
9
PV
T
0.4
3.0
0.0
172
0.0
33 1
PV
T
PV
T - - - - - - - - - - - - - -
1
6
6
7
3
9
5
7
4
3
7
Madh
ukar
Marya
Patil
49
1
PV
T
0.4
5.0
0.0
203
0.0
378 1
PV
T
PV
T - - - - - - - - - - - - - -
1
6
7
7
4
3
7
7
4
6
4
Sadas
hhiv
Vama
n
Mhatr
e
49
2
PV
T
0.3
8.7
0.0
131
0.0
231 1
PV
T
PV
T - - - - - - - - - - - - - -
1
6
8 7
4
6
4
7
6
5
7
Laksh
man
Krush
na
Mhatr
e 50
6
PV
T
0.9
5.5
0.1
271
0.1
734
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
1
6
9
Balira
m
Laksh
man
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 330
1
7
0
Ashok
Laksh
man
Mhatr
e
1
7
1
Dnyan
eshwa
r
Laksh
man
Mhatr
e
1
7
2
Gopin
ath
Laksh
man
Mhatr
e
1
7
3
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
1
7
4
7
6
5
8
7
6
8
4
Arjun
Kavlya
Mhatr
e
52
0
PV
T
0.3
1
0.0
001
0.0
1 2
PV
T
PV
T - - - - - - - - - - - - - -
1
7
5
HIram
an
Kavlya
Mhatr
e
1
7
6
Sanjay
Krush
na
Mhatr
e
1
7
7
Sande
sh
Krush
na
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 331
1
7
8
Sangit
a
Krush
na
Mhatr
e
1
7
9
Sarita
Krush
na
Mhatr
e
1
8
0
Jayshr
ee
Krush
na
Mhatr
e
1
8
1
Bhau
Kavlya
Mhatr
e
1
8
2
Yamu
na
Krush
na
Mhatr
e
1
8
3
Vithab
ai
Ganpa
t Patil
1
8
4
Savitri
Gajan
an
Patil
1
8
5
Shivpr
asad
Shank
ar
Thaku
r
1
8
6
Ujjwal
a
Shank
ar
Thaku
r
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 332
1
8
7
7
6
7
7
7
8
1
5
Baghw
an
Ragho
Mhatr
e
52
1
PV
T
0.9
0.5
0.0
501
0.0
001 1
PV
T
PV
T - - - - - - - - - - - - - -
1
8
8
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
1
8
9
7
6
8
4
7
7
5
8
Dilip
Rama
Mhatr
e
52
2
PV
T
0.3
4.5
0.0
183
0.0
475 2
PV
T
PV
T - - - - - - - - - - - - - -
1
9
0
7
7
5
8
7
8
2
2
Vasan
t
Sukaji
Mhatr
e
52
4
PV
T
0.3
2.7
0.0
342
0.0
457 2
PV
T
PV
T - - - - - - - - - - - - - -
1
9
1
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
1
9
2
7
8
2
2
7
9
0
6
Marut
i Naga
Mhatr
e
53
4
PV
T
0.3
3.2
0.0
553
0.0
645 2
PV
T
PV
T - - - - - - - - - - - - - -
1
9
3
7
8
9
7
7
9
9
4
T.M
.State
co-op
branc
h, Pen 54
1
PV
T
0.5
6.0
0.0
681
0.0
678 2
PV
T
PV
T - - - - - - - - - - - - - -
1
9
4
Naray
an
Joma
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 333
1
9
5
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
1
9
6
7
9
9
6
8
0
0
4
Rama
Balya
Mhatr
e
54
0
PV
T
0.4
1.2 0
0.0
018 2
PV
T
PV
T - - - - - - - - - - - - - -
1
9
7
Suryak
ant
Rama
Mhatr
e
1
9
8
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
1
9
9
7
9
9
4
8
0
7
5
Sitabai
Sitara
m
Mhatr
e
54
2
PV
T
0.4
3.0
0.0
385
0.0
574 2
PV
T
PV
T - - - - - - - - - - - - - -
2
0
0
Dinan
ath
Sitara
m
Mhatr
e
2
0
1
Lalita
Kashin
ath
Thaku
r
2
0
2
Mumb
ai
Vishes
h
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 334
Arthik
kshetr
a
comp
any
2
0
3
8
0
4
5
8
0
8
8
Ramu
bai
Padm
a Patil
54
3
PV
T
0.4
0.0
0.0
081
0.0
207 2
PV
T
PV
T - - - - - - - - - - - - - -
2
0
4
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
2
0
5
8
0
7
5
8
1
0
4
Shakar
Chahy
a
Mhatr
e
55
1
PV
T
0.4
0.2
0.0
089
0.0
055
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
2
0
6
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
2
0
7
8
0
8
8
8
1
9
9
Ashok
Shank
ar
Mhatr
e
55
0
PV
T
0.3
7.2
0.0
712
0.0
739
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
2
0
8
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
2 8 8 Kashin 54 PV 0.3 0.0 0.0 1 PV PV - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 335
0
9
1
9
9
2
3
7
ath
Hiru
Mhatr
e
9 T 9.0 265 26 T T
2
1
0
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
2
1
1
8
2
3
7
8
2
9
0
Balara
m
Shank
ar
Mhatr
e
54
8
PV
T
0.3
8.0
0.0
35
0.0
347 1
PV
T
PV
T - - - - - - - - - - - - - -
2
1
2
8
2
9
0
8
3
2
8
Joma
Gaury
a
Mhatr
e
54
7
PV
T
0.4
6.0
0.0
256
0.0
21 1
PV
T
PV
T - - - - - - - - - - - - - -
2
1
3
Devku
bai
Joma
Mhatr
e
2
1
4
Suresh
Joma
Mhatr
e
2
1
5
Amrut
Joma
Mhatr
e
2
1
6
Resh
ma
Pandu
rang
Bhoir
2
1
7
Mumb
ai
Vishes
h
Arthik
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 336
kshetr
a
comp
any
2
1
8
8
3
2
8
8
4
4
2
Shank
ar
Dhau
Mhatr
e
55
5
PV
T
0.4
3.7
0.0
751
0.0
783 1
PV
T
PV
T - - - - - - - - - - - - - -
2
1
9
Ankus
h
Shank
ar
Mhatr
e
2
2
0
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
2
2
1
8
4
4
2
8
5
5
7
Gover
nment
of
Mahar
ashtra
16
4
GO
VT.
1.5
2.0
0.0
806 0.0
89
1 GO
VT.
GO
VT. - - - - - - - - - - - - - -
Borze
2
2
2
8
5
7
0
8
6
0
8
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
69
3
PV
T
0.1
7.5
0.0
212
0.0
257
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
2
2
3
8
6
0
8
8
6
2
5
Mumb
ai
Vishes
h
Arthik
kshetr
69
2
PV
T
0.1
4.4
0.0
093
0.0
136 1
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 337
a
comp
any
2
2
4
8
6
2
5
8
6
4
2
Naga
Kasha
Thaku
r
69
1
PV
T
0.1
2.4
0.0
092
0.0
128 1
PV
T
PV
T - - - - - - - - - - - - - -
2
2
5
Indira
Shank
ar
Mhatr
e
2
2
6
Chand
ra
Hiram
an
Mhatr
e
2
2
7
Babur
ao
Maha
dev
Thaku
r
2
2
8
Chand
rakant
Maha
dev
Thaku
r
2
2
9
Suryak
ant
Maha
dev
Thaku
r
2
3
0
Anuba
i Lahu
Patil
2
3
1
8
6
4
2
8
6
6
2
Madh
ukar
Laksh
man
Thaku
r
69
0
PV
T
0.1
2.4
0.0
126
0.0
147 1
PV
T
PV
T - - - - - - - - - - - - - -
2
3
8
6
8
6
Bamu
bai
68
9
PV
T
0.1
5.2
0.0
115
0.0
133 1
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 338
2 6
2
7
8
Ganpa
t
Mhatr
e
2
3
3
Parsh
uram
Posha
Patil
2
3
4
Shant
a
Ambaj
i
Mhatr
e
2
3
5
Jomub
ai
Babur
ao
Patil
2
3
6
Ramu
bai
Naray
an
Mhatr
e
2
3
7
Naray
an
Babur
ao
Patil
2
3
8
Bhima
bai
Motir
am
Mhatr
e
2
3
9
Sakhu
bai
Shant
abai
Patil
2
4
0
Taibai
Dhana
ji Patil
2
4
1
Shant
abai
Babur
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 339
ao
Patil
2
4
2
Yasho
da
Ramb
hau
Patil
2
4
3 8
6
7
8
8
6
9
6
Marut
i
Kunda
lik
Thaku
r 68
8
PV
T
0.1
2.4
0.0
119
0.0
142 1
PV
T
PV
T - - - - - - - - - - - - - -
2
4
4
Sita
Ganpa
t
Mhatr
e
2
4
5
8
6
9
6
8
7
0
9
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
68
7
PV
T
0.1
3.1
0.0
07
0.0
109 1
PV
T
PV
T - - - - - - - - - - - - - -
2
4
6
8
7
0
9
8
7
2
2
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
68
6
PV
T
0.1
4.4
0.0
073
0.0
102 1
PV
T
PV
T - - - - - - - - - - - - - -
2
4
7
8
7
2
2
8
7
3
5
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
68
5
PV
T
0.1
3.9
0.0
099
0.0
114 1
PV
T
PV
T - - - - - - - - - - - - - -
2
4
8
7
8
7
Naga
Kasha
68
4
PV
T
0.1
6.0
0.0
087
0.0
079 1
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 340
8 3
5
4
7
Thaku
r
2
4
9
Indira
Shank
ar
Mhatr
e
2
5
0
Chand
ra
Hiram
an
Mhatr
e
2
5
1
Babur
ao
Maha
dev
Thaku
r
2
5
2
Chand
rakant
Maha
dev
Thaku
r
2
5
3
Suryak
ant
Maha
dev
Thaku
r
2
5
4
Anuba
i Lahu
Patil
2
5
5
8
7
4
7
8
7
5
9
Ramkr
ushna
Shank
ar
Patil
68
3
PV
T
0.1
0.6
0.0
097
0.0
086 1
PV
T
PV
T - - - - - - - - - - - - - -
2
5
6
8
7
5
9
8
7
9
9
Gover
nment
of
Mahar
ashtra
68
2
PV
T
8.1
6.0
0.2
411
0.3
421
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
2
5
7
8
7
9
8
8
1
Naga
Kasha
Thaku
79
6
PV
T
0.1
4.9
0.0
115
0.0
119 1
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 341
9 3 r
2
5
8
Indira
Shank
ar
Mhatr
e
2
5
9
Chand
ra
Hiram
an
Mhatr
e
2
6
0
Babur
ao
Maha
dev
Thaku
r
2
6
1
Chand
rakant
Maha
dev
Thaku
r
2
6
2
Suryak
ant
Maha
dev
Thaku
r
2
6
3
Anuba
i Lahu
Patil
2
6
4
8
8
1
3
8
8
2
4
Suma
n
Hiram
an
Mhatr
e
78
0
PV
T
0.1
1.4
0.0
096
0.0
08 1
PV
T
PV
T - - - - - - - - - - - - - -
2
6
5
8
8
2
4
8
8
3
9
Krush
naji
Vitthal
Vadha
vkar
76
8
PV
T
0.1
2.9
0.0
112
0.0
109 1
PV
T
PV
T - - - - - - - - - - - - - -
2
6
8
8
8
8
Mumb
ai
76
6
PV
T
0.1
1.9
0.0
087
0.0
095 1
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 342
6 3
9
5
1
Vishes
h
Arthik
kshetr
a
comp
any
2
6
7
8
8
5
1
8
8
6
6
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
89
7
PV
T
0.1
1.9
0.0
102
0.0
12 1
PV
T
PV
T - - - - - - - - - - - - - -
2
6
8
8
8
6
6
8
8
9
0
Gangu
bai
Namd
ev
Thaku
r
89
6
PV
T
0.1
4.4
0.0
15
0.0
183 1
PV
T
PV
T - - - - - - - - - - - - - -
2
6
9
Vishvn
ath
Namd
ev
Thaku
r
2
7
0
Janard
an
Namd
ev
Thaku
r
2
7
1
Ramc
handr
a
Namd
ev
Thaku
r
2
7
2
8
8
9
0
8
9
1
1
Janard
an
Vishw
nath
Patil
89
5
PV
T
0.1
2.9
0.0
133
0.0
188 1
PV
T
PV
T - - - - - - - - - - - - - -
2 Krush
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 343
7
3
naji
Naray
an
Mhatr
e
2
7
4
8
9
1
1
8
9
2
9
Dhar
ma
Dhau
Thaku
r
89
4
PV
T
0.1
1.9
0.0
11
0.0
161 1
PV
T
PV
T - - - - - - - - - - - - - -
2
7
5
8
9
2
9
8
9
6
1
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
89
3
PV
T
0.1
5.4
0.0
197
0.0
26 1
PV
T
PV
T - - - - - - - - - - - - - -
2
7
6 8
9
6
1
8
9
7
4
Shri.
Maha
dev
Vastvy
a
Janava
li
Vahiva
t
89
2
PV
T
0.1
8.0
0.0
348
0.0
502 1
PV
T
PV
T - - - - - - - - - - - - - -
2
7
7
Kalu
Rama
Mhatr
e
2
7
8
8
9
7
4
9
0
9
7
Sakhu
bai
Balaji
Patil
89
1
PV
T
0.3
4.2
0.0
465
0.0
574 1
PV
T
PV
T - - - - - - - - - - - - - -
2
7
9
Kamal
akar
Balaji
Patil
2
8
0
Poshib
ai
Hasu
Mhatr
e
2
8
Bhagu
bai
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 344
1 Bamy
a
Mhatr
e
2
8
2
Deoba
i
Damaj
i
Mhatr
e
2
8
3
Vachal
a
Marut
i
Mhatr
e
2
8
4
9
0
9
7
9
1
3
6
Gajan
an
Maha
du
Patil
89
0
PV
T
0.1
6.6
0.0
229
0.0
181 1
PV
T
PV
T - - - - - - - - - - - - - -
2
8
5
Tulshi
das
Maha
du
Patil
2
8
6
Dilip
Maha
du
Patil
2
8
7
Subha
sh
Maha
du
Patil
2
8
8
Radha
bai
Suda
m
Patil
2
8
9
Ajit
Suda
m
Patil
2
9
0
Nilesh
Suda
m
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 345
Patil
2
9
1
Pramil
a
Sandip
Patil
2
9
2
Jyoti
Gajan
an
Patil
2
9
3
Sadha
na
Rames
h Patil
2
9
4
9
1
3
6
9
1
7
4
Narda
s
Krush
na
Patil
88
9
PV
T
0.1
7.1
0.0
275
0.0
115 2
PV
T
PV
T - - - - - - - - - - - - - -
2
9
5
9
1
7
4
9
2
1
3
Shant
aram
Nagu
Patil
88
8
PV
T
0.3
4.2
0.0
264
0.0
119 2
PV
T
PV
T - - - - - - - - - - - - - -
2
9
6
Tukar
am
Nagu
Patil
2
9
7
Balira
m
Nagu
Patil
2
9
8
Rukh
mini
Nagu
Patil
2
9
9
Sande
ep
Haribh
au
Patil
3
0
0
Jakhu
Pada
m
Patil
3
0
1
Chand
rakant
Pada
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 346
m
Patil
3
0
2
Savitri
Damaj
i Patil
3
0
3
Jana
Arun
Thaku
r
3
0
4
9
2
1
3
9
2
4
9
Janard
an
Balaji
Patil
88
7
PV
T
0.2
4.4
0.0
218
0.0
05 2
PV
T
PV
T - - - - - - - - - - - - - -
Narvel
3
0
5
9
5
3
5
9
5
6
0
Sakhar
am
Naray
an
Thaku
r
16
9
PV
T
0.0
8.9
0.0
245
0.0
025 2
PV
T
PV
T - - - - - - - - - - - - - -
3
0
6 9
5
6
0
9
5
9
7
Gajan
an
Budha
ji Patil 16
8
PV
T
0.1
5.7
0.0
247
0.0
014
2
PV
T
PV
T - - - - - - - - - - - - - -
3
0
7
Pada
m
Budhy
a Patil
2
3
0
8
9
5
9
7
9
6
2
9
Gajan
an
Hiru
Patil
16
7
PV
T
0.1
2.6
0.0
086 0 2
PV
T
PV
T - - - - - - - - - - - - - -
3
0
9
9
6
2
9
9
6
4
5
Dhar
ma
Ganu
Patil
16
6
PV
T
0.1
5.7
0.0
005 0 2
PV
T
PV
T - - - - - - - - - - - - - -
3
1
0
9
6
7
3
9
6
8
3
Shank
ar
Arjun
Mhatr
e
34
8/
1
PV
T
0.1
57
0.0
027
0.0
101 1
PV
T
PV
T - - - - - - - - - - - - - -
3
1
1
Gajan
an
Shank
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 347
ar
Mhatr
e
3
1
2
Shara
d
Shank
ar
Mhatr
e
3
1
3
Subha
sh
Shank
ar
Mhatr
e
3
1
4
Shivaji
Shank
ar
Mhatr
e
3
1
5
Dattat
ray
Shank
ar
Mhatr
e
3
1
6
Harish
chand
ra
Shank
ar
Mhatr
e
3
1
7
Krush
naji
Shank
ar
Mhatr
e
3
1
8
Ratna
mala
Lalu
Mhatr
e
3
1
9
Sunan
da
Hanu
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 348
mant
Patil
3
2
0
Rekha
Hanu
mant
Patil
3
2
1
Nathu
ram
Naray
an
Mhatr
e
34
8/
2
PV
T
0.1
5.7
PV
T
PV
T - - - - - - - - - - - - - -
3
2
2
Dnyan
deo
Rama
Mhatr
e
34
8/
3
PV
T
0.1
5.7
PV
T
PV
T - - - - - - - - - - - - - -
3
2
3
Janard
han
Rama
Mhatr
e
34
8/
4
PV
T
0.1
5.7
PV
T
PV
T - - - - - - - - - - - - - -
3
2
4
Shridh
ar
Govin
d
Mhatr
e
34
8/
5
PV
T
0.1
5.7
PV
T
PV
T - - - - - - - - - - - - - -
3
2
5
Jayra
m
Kashin
ath
Mhatr
e
34
8/
6
PV
T
0.1
5.7
PV
T
PV
T - - - - - - - - - - - - - -
3
2
6
Damo
dar
Bhoru
Mhatr
e
34
8/
7
PV
T
0.1
5.7
PV
T
PV
T - - - - - - - - - - - - - -
3
2
7
Gopin
ath
Damo
dar
Mhatr
e
3
2
Pandu
rang
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 349
8 Damo
dar
Mhatr
e
3
2
9
Hiram
an
Damo
dar
Mhatr
e
3
3
0
Moha
n
Damo
dar
Mhatr
e
3
3
1
Kusu
m
Janard
han
Patil
3
3
2
Vimal
Rames
h
Mhatr
e
3
3
3
Alka
Ravin
dra
Mhatr
e
3
3
4
Lata
Gajajn
an
Patil
3
3
5
Raghu
nath
Shank
ar
Mhatr
e 34
8/
8
PV
T
0.1
5.7
PV
T
PV
T - - - - - - - - - - - - - -
3
3
6
Tulshi
das
Shank
ar
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 350
3
3
7
Krush
na
Naray
an
Mhatr
e
34
8/
9
PV
T
0.1
5.6
PV
T
PV
T - - - - - - - - - - - - - -
3
3
8
Sitara
m
Naray
an
Mhatr
e
34
8/
10
PV
T
0.1
56
PV
T
PV
T - - - - - - - - - - - - - -
3
3
9
Ambaj
i
Sitara
m
Mhatr
e
3
4
0
Marut
i
Sitara
m
Mhatr
e
3
4
1
Rajara
m
Sitara
m
Mhatr
e
3
4
2
Madh
ukar
Sitara
m
Mhatr
e
3
4
3 9
9
9
5
1
0
0
4
7
Vanda
na
Parsh
uram
Patil
15
4/
1
PV
T
0.5
9.7 0.0
412
0.0
185 2
PV
T
PV
T - - - - - - - - - - - - - -
3
4
4
Sanjay
Parsh
uram
Patil
3
4
Anant
Pandu
15
4/
PV
T
0.6
0.0
PV
T
PV
T
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 351
5 rang
Patil
2
3
4
6
1
0
0
4
7
1
0
1
2
3
Nathu
ram
Naray
an
Mhatr
e
15
3
PV
T
0.6
3.5
0.0
592
0.0
32 2
PV
T
PV
T - - - - - - - - - - - - - -
3
4
7
1
0
1
2
3
1
0
1
5
5
Eknat
h
Ravya
Mhatr
e
15
1
PV
T
0.7
6.9
0.0
204
0.0
079 2
PV
T
PV
T - - - - - - - - - - - - - -
3
4
8
1
0
1
6
2
1
0
3
1
6
46
7
PV
T
0.0
515
0.0
842 1
PV
T
PV
T - - - - - - - - - - - - - -
3
4
9
1
0
2
3
6
1
0
2
9
6
Bala
Ganap
at
patil
46
6
PV
T
0.4
4.6
0.0
546
0.0
353 2
PV
T
PV
T - - - - - - - - - - - - - -
3
5
0 1
0
3
1
6
1
0
4
0
0
Vithob
a
Bama
Bhoir
46
5/
1
PV
T
0.5
5.0
0.0
526
0.0
213 2
PV
T
PV
T - - - - - - - - - - - - - -
3
5
1
Parvat
i
Ramc
handr
a Patil
46
5/
2
PV
T
0.1
6.9
PV
T
PV
T - - - - - - - - - - - - - -
3
5
2
1
0
4
0
0
1
0
4
4
0
Dhar
ma
Pandu
Patil
46
4
PV
T
0.6
87
0.0
189 0 2
PV
T
PV
T - - - - - - - - - - - - - -
3
5
3
Kamal
Balu
Mhatr
e
3
5
4
Bhaur
ao
Kamal
Mhatr
e
3
5
Narda
s
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 352
5 Kamal
Mhatr
e
3
5
6
Rames
h
Kamal
Mhatr
e
3
5
7
Budhi
bai
Babur
ao
Patil
3
5
8
Sitabai
Ramc
handr
a Patil
3
5
9
Vithab
ai
kamal
Patil
3
6
0
Dhar
mubai
Dhar
maji
Patil
3
6
1
Sandip
Dhar
maji
Patil
3
6
2
Shashi
kant
Dhar
maji
Patil
3
6
3
Jayvan
ti
Sadas
hiv
Mhatr
e
3
6
4
Shaila
Haribh
au
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 353
3
6
5
Sangit
a
Dhar
maji
Mhatr
e
3
6
6
1
0
4
4
0
1
0
4
8
3
Ishvar
Punda
lik
Mhatr
e
46
3/
1
PV
T
0.1
5.2
0.0
133 0 2
PV
T
PV
T
- - - - - - - - - - - - - -
3
6
7
Dnyan
eshwa
r
Punda
lik
Mhatr
e
46
3/
2
PV
T
0.1
5.2
PV
T
PV
T
3
6
8
Vishw
as
Punda
lik
Mhatr
e
46
3/
3
PV
T
0.1
5.2
PV
T
PV
T
3
6
9
Anil
Punda
lik
Mhatr
e
46
3/
4
PV
T
0.1
5.1
PV
T
PV
T
3
7
0
Sanat
an
Punda
lik
Mhatr
e
46
3/
5
PV
T
0.1
5.1
PV
T
PV
T
3
7
1 1
0
4
8
3
1
0
5
2
5
Krush
nibai
Pruthv
iraj
Patil
46
2/
1
PV
T
0.1
5.0
0.0
053 0 2
PV
T
PV
T
- - - - - - - - - - - - - - 3
7
2
Namd
eo
Kalu
patil
46
2/
2
PV
T
0.3
76
PV
T
PV
T 3
7
3
Arjun
Namd
eo
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 354
Patil
3
7
4
Janard
han
Namd
eo
Patil
3
7
5
Samad
han
Namd
eo
Patil
3
7
6
Vinod
Namd
eo
Patil
3
7
7
Parvat
i
Vishva
nath
Patil
3
7
8
Savitri
Ramkr
ushna
Mali
3
7
9
Gover
nment
of
Mahar
ashtra
(Parig
h)
44
7
PV
T
8.5
4.0
0.5
928
0.5
676 1
PV
T
PV
T - - - - - - - - - - - - - -
A 0.0
179
0.0
832
3
8
0
1
0
8
9
4
1
0
8
9
9
Marut
i
Vetya
Patil
44
9
PV
T
0.0
7.1
0.0
001
0.0
002 2
PV
T
PV
T - - - - - - - - - - - - - -
B 0.0
745
0.0
813
Benav
ale (2)
3
8
1
0
1
1
Janard
an
48
1
PV
T
0.3
7.7
0.4
658
0.2
811 1
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 355
1 8
9
7
4
1
1
Javrya
Mokal
A
0.0
047
0.0
504
1
1
4
1
1
1
1
5
0
3
B
0.0
616
0.0
812
3
8
2 1
1
4
9
2
1
1
7
5
5
Prakas
h
Pandu
rang
Mhatr
e
44
6/
A
PV
T
0.2
5.3
0.2
088
0.1
715
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
3
8
3
Prakas
h
Pandu
rang
Mhatr
e
44
6/
B,
C
PV
T
0.3
7.7
1
2
1
5
0
1
2
1
8
1
D
0.0
05 0
3
8
4
1
2
1
8
1
1
2
2
3
6
Ramd
as
Chang
a
Mhatr
e
41
4
PV
T
0.3
1.0
0.0
355 0 2
PV
T
PV
T - - - - - - - - - - - - - -
3
8
5 1
2
2
3
6
1
2
2
7
7
Ramc
handr
a
Kashin
ath
Mhatr
e 41
3
PV
T
0.1
8.0
0.0
254
0.0
002 2
PV
T
PV
T - - - - - - - - - - - - - -
3
8
6
Narda
s
Kashin
ath
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 356
3
8
7
Anand
i
Gajan
an
Mhatr
e
3
8
8
1
2
2
7
7
1
2
3
1
9
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
41
2
PV
T
0.1
5.5
0.0
082
0.0
055 2
PV
T
PV
T - - - - - - - - - - - - - -
3
8
9
1
2
3
1
9
1
2
3
6
1
Sadas
hiv
Pavsh
a Patil 41
1
PV
T
0.3
6.6
0.0
043 0 2
PV
T
PV
T - - - - - - - - - - - - - -
3
9
0
1
2
8
1
2
1
2
9
0
4
Ramd
as
Lakhu
Thavai
37
3/
A
PV
T
0.2
5.2
0.0
631
0.0
359
1 &
2
PV
T
PV
T
- - - - - - - - - - - - - -
3
9
1
Ramd
as
Lakhu
Thavai
37
3/
B
PV
T
0.2
4.5
PV
T
PV
T
3
9
2
1
0
9
0
4
1
2
9
3
0
Devich
and
Gajan
an
Patil
37
2
PV
T
0.9
8.0
0.0
215
0.0
176
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
3
9
3
Jaywa
nt
Gajan
an
Patil
3
9
4
Subha
sh
Gajan
an
Patil
3
9
5
Ganes
h
Gajan
an
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 357
Patil
3
9
6
Laksh
mibai
Gajan
an
Patil
3
9
7
Vimal
Rama
kant
Mhatr
e
3
9
8
Minak
shi
Chand
rakant
Mhatr
e
3
9
9
Shara
da
Kishor
Madh
avi
4
0
0
1
2
9
3
0
1
2
9
7
2
Naray
an
Maya
Patil
37
1
PV
T
0.3
8.8
0.0
437
0.0
274
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
4
0
1
Maha
dibai
Maya
Patil
4
0
2
Anand
ibai
Raghu
nath
Patil
1
2
9
7
2
1
2
9
8
6
F
0.0
109
0.0
104 - - - - - - - - - - - - - -
4
0
3
1
2
9
8
6
1
3
0
5
5
Gauru
bai
Balira
m
Mhatr
e
35
1/
1
PV
T
0.1
6.7
0
0.0
475
0.0
678
1 &
2
PV
T
PV
T - - - - - - - - - - - - -
Farm Pond at
ch.12986
(combine of
350 & 351)
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 358
4
0
4
Kiran
Balira
m
Mhatr
e
4
0
5
Kumar
Balira
m
Mhatr
e
4
0
6
Kailas
Balira
m
Mhatr
e
4
0
7
Ramc
handr
a
Nathu
ram
Mhatr
e
35
1/
2 0.1
6.7
0
4
0
8
1
3
0
5
5
1
3
0
8
8
Mumb
ai
Vishes
h
Arthik
kshetr
a
comp
any
35
0
PV
T
0.1
6.2
0.0
238
0.0
317
1 &
2
PV
T
PV
T - - - - - - -
House
(f/s)
42
sqm
t
- - - - Farm Pond at
ch.13057
4
0
9
1
3
0
8
8
1
3
1
3
9
Devid
as
Rama
Vartak
34
9
PV
T
0.1
7.4
0.0
412
0.0
409
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
4
1
0
Bayob
ai
Kamal
akar
Thaku
r
4
1
1
Shank
untala
Jakhu
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 359
4
1
2
Chand
rabha
ga
Raghu
nath
Mhatr
e
4
1
3
1
3
1
3
9
1
3
2
2
4
Sadas
hiv
Pavsh
a Patil
34
7
PV
T
0.2
0.7
0.0
656
0.0
665
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
4
1
4
Kashin
ath
Pavsh
a Patil
4
1
5
Minal
Madh
ukar
Patil
4
1
6
Gajan
an
Naray
an
Patil
4
1
7
Shank
untala
Naray
an
Patil
4
1
8
Ratna
prabh
a Sunil
Redka
r
4
1
9
Gopin
ath
Kashin
ath
Patil
4
2
0
Dayar
am
Kashin
ath
Patil
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 360
Sareb
hag
4
2
1
1
1
7
3
0
1
2
8
5
7
Gover
nment
of
Mahar
ashtra
16
7A
GO
VT.
10.
21.
0
0.7
374
0.8
909 1
GO
VT.
GO
VT. - - - - - - - - - - - - - -
Z 0.0
632
0.0
794 2
Benav
ale (1)
1
1
3
3
1
1
1
3
3
2
9
Suda
m
Pitkur
Mokal
32
2
PV
T
0.2
2.5
0.0
079
0.0
081 2
PV
T
PV
T - - - - - - -
House(f
/s)
10
sqm
t
- - - - -
2
1
3
3
2
9
1
3
5
1
7
Harib
hau
Dhar
maji
Mokal
32
1
PV
T
0.7
4.2
0.1
193
0.0
981
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
3
Prasad
Harib
hau
Mokal
4
Dipak
Gajan
an
Mokal
5
Sande
ep
Gajan
an
Mokal
6
Pradee
p
Gajan
an
Mokal
7
Sanjay
Gajan
an
Mokal
8
Subha
sh
Pandu
rang
Mokal
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 361
9
Nares
h
Pandu
rang
Mokal
1
0
Satish
Sadas
hiv
Mokal
1
1
Ninad
Prasad
Mokal
1
2
Rutuja
Prasad
Mokal
1
3
1
3
4
2
3
1
3
4
6
5
Shivra
m
Kamal
Patil
32
0
PV
T
0.7
5.1
0.0
263
0.0
251 2
PV
T
PV
T - - - - - - - - - - - - - -
1
4
Hirub
ai
Shivra
m
Patil
1
5
Shank
ar
Shivra
m
Patil
1
6
Vilas
Shivra
m
Patil
1
7
Anand
i
Vasan
t
Vartak
1
8
1
3
5
1
7
1
3
5
6
0
Naray
an
Padam
Thaku
r
31
5/
1
PV
T
0.1
9.8
0.0
343
0.0
372
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
1
9
Balaji
Santur
am
Patil
31
5/
2
PV
T
0.2
0.7 PV
T
PV
T
2
0 Naren
dra 31
5/
PV
T
0.4
0.6 PV
T
PV
T
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 362
Janard
an
Patil
3
2
1
1
3
5
6
0
1
3
6
3
7
Maha
dev
Vittha
l
Mhatr
e
31
4
PV
T
0.3
4.4
0.0
583
0.0
538
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
2
2
Ravin
dra
Krush
naji
Mhatr
e
2
3
1
3
6
3
7
1
3
7
0
5
Gajan
an
Phakir
Mhatr
e
31
3
PV
T
0.7
6.9
0.0
566
0.0
463
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
1
3
7
0
5
1
3
7
1
2
A 0.0
064
0.0
063
2
4
1
3
7
1
2
1
3
7
9
0
Lilaba
i
Shivra
m
Mhatr
e
18
0
PV
T
0.1
2.6
0.0
561
0.0
773
1
&2
PV
T
PV
T - - - - - - - - - - - - - -
2
5
Ratna
kar
Shivra
m
Mhatr
e
2
6
Kesari
nath
Shivra
m
Mhatr
e
2
7
Ganes
h
Shivra
m
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 363
2
8
Jayshr
ee
Krush
na
Thaku
r
2
9
Sunan
da
Vasan
t Patil
3
0
Nilam
Anil
Mhatr
e
3
1
Pratib
ha
Rames
h
Mhatr
e
3
2
1
3
7
9
0
1
3
9
3
6
Jayra
m
Ganu
Mhatr
e
17
9
PV
T
0.5
1.0
0.0
352
0.0
264 2
PV
T
PV
T - - - - - - - - - - - - - -
3
3
Nandk
ishor
Jayra
m
Mhatr
e
3
4
Nandk
ishor
Jayra
m
Mhatr
e
3
5
Pradip
chandr
a
Jayra
m
Mhatr
e
3
6
Ashok
Jayra
m
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 364
3
7
Vikas
Jayra
m
Mhatr
e
3
8
1
4
1
3
9
1
4
2
3
9
Samb
haji
Harib
hau
Mhatr
e
17
2/
1
PV
T
0.2
6.9
0.0
172
0.0
145 2
PV
T
PV
T - - - - - - - - - - - - - -
3
9
Jagga
nath
Hariba
hu
Mhatr
e
17
2/
2
PV
T
0.2
6.0 PV
T
PV
T
4
0
Rajen
dra
Jagga
nath
Mhatr
e
4
1
Shrika
nt
Jagga
nath
Mhatr
e
4
2
Indum
ati
Jagga
nath
Mhatr
e
4
3
Surek
ha
Jagdis
h Patil
4
4
Kiran
Hares
hwar
Patil
4
5
Purus
hotta
m
Hariba
hu
Mhatr
e
17
2/
3
PV
T
0.2
7.0 PV
T
PV
T
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 365
4
6
1
4
2
3
9
1
4
2
8
0
Harib
hau
Dhar
maji
Mokal
16
5
PV
T
1.3
8.5
0.0
087
0.0
215 1
PV
T
PV
T - - - - - - - - - - - - - -
4
7
Dhar
maji
Joma
Mokal
4
8
Laksh
man
Joma
Patil
4
9
Shanta
ram
Joma
Patil
5
0
Sanjay
Shank
ar
Patil
5
1
Sunil
Shank
ar
Patil
5
2
Janaki
Laksh
man
Patil
5
3
Sachin
Laksh
man
Patil
5
4
Satish
Laksh
man
Patil
5
5
Sima
Laksh
man
Patil
5
6
Suvar
na
Vasan
t
Thaku
r
5
7
1
4
2
1
4
3
Radhi
bai
Lakhu
16
4
PV
T
0.8
4.0
0.0
577
0.0
738
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 366
8
0
7
0
Patil
5
8
Parshu
ram
Lakhu
Patil
5
9
Shanta
ram
Lakhu
Patil
6
0
Pandu
rang
Lakhu
Patil
6
1
Jaywa
nt
Lakhu
Patil
6
2
Shara
da
Vishw
anath
Thaku
r
6
3
Gulab
Raghu
nath
Mhatr
e
6
4
1
4
3
7
0
1
4
4
3
0
Mada
n
Maha
dev
Mokal
15
6
PV
T
0.4
7.0
0.0
395
0.0
588
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
6
5
1
4
4
3
0
1
4
4
3
5
Gover
nment
of
Mahar
ashtra
15
5
G
O
V
T
0.2
1.5
0.0
136
0.0
076
G
O
V
T
GO
VT - - - - - - - - - - - - - -
6
6
1
4
4
4
0
1
4
6
0
5
Janard
an
Javrya
Mokal
15
3
PV
T
0.8
6.8
0.0
54
0.0
41 2
PV
T
PV
T - - - - - - - - - - - - - -
6
7
1
4
6
0
5
1
4
6
5
7
Vithab
ai
Naga
Bapu
Mokal
15
1
PV
T
0.6
0.0
0.0
151
0.0
01 2
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 367
6
8
1
4
6
5
7
1
4
7
7
3
Rukmi
ni
Shivar
am
Mokal
15
0
PV
T
0.7
9.6
0.0
29
0.0
022 2
PV
T
PV
T - - - - - - - - - - - - - -
6
9
1
5
0
0
3
1
5
0
2
2
Harish
chandr
a
Kashi
nath
Patil
10
0
PV
T
0.4
5.7
0.0
015
0.0
004 2
PV
T
PV
T - - - - - - - - - - - - - -
7
0
Vama
n
Kashi
nath
Patil
7
1
Vishn
u
Kashi
nath
Patil
7
2
Dattat
ray
Kashi
nath
Patil
7
3
1
5
0
2
2
1
5
0
9
1
Parshu
ram
Shank
ar
Mhatr
e
99 PV
T
0.5
8.4
0.0
172
0.0
003 2
PV
T
PV
T - - - - - - - - - - - - - -
7
4
1
5
0
9
1
1
5
1
9
5
Krush
na
Shank
ar
Mhatr
e
98 PV
T
0.7
0.9
0.0
49
0.0
01 2
PV
T
PV
T - - - - - - - - - - - - - -
7
5
Jaywa
nt
Anant
Mhatr
e
7
6
Ravik
ant
Anant
Mhatr
e
7
7 Anubh
av
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 368
Anant
Mhatr
e
7
8
Pushpl
ata
Ramc
handra
Mhatr
e
7
9
Rajash
ri
Kamla
kar
Bhoir
8
0
Sange
eta
Anant
Mhatr
e
8
1
Pushp
Anant
Mhatr
e
8
2
Anju
Anant
Mhatr
e
8
3
Kashi
bai
Anant
Mhatr
e
8
4
1
5
1
9
5
1
5
2
5
3
Gauru
bai
Balira
m
Mhatr
e
97
/1
PV
T
0.1
6.7
0.0
274
0.0
003 2
PV
T
PV
T - - - - - - - - - - - - - -
8
5
Kiran
Balira
m
Mhatr
e
8
6
Kuma
r
Balira
m
Mhatr
e
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 369
8
7
Kailas
Balira
m
Mhatr
e
8
8
Ramc
handra
Nathu
ram
Mhatr
e
97
/2
PV
T
0.1
6.7 PV
T
PV
T
8
9
1
5
2
5
3
1
5
3
7
6
Namd
ev
Posu
Mhatr
e
81 PV
T
0.4
7.1
0.0
069
0.0
003 2
PV
T
PV
T - - - - - - - - - - - - - -
9
0
Anant
Posu
Mhatr
e
9
1
Atmar
am
Posu
Mhatr
e
9
2
Balara
m
Posu
Mhatr
e
9
3
Kasub
ai
Janard
an
Mhatr
e
9
4
Namu
bai
Parshu
ram
Kothe
kar
9
5
1
5
3
7
6
1
5
5
1
1
Krush
na
Marya
Thaku
r
80
/1
PV
T
0.3
6.0
0.0
001
0.0
661 2
PV
T
PV
T - - - - - - - - - - - - - -
9
6
Nagib
ai
Padam
80
/2
PV
T
0.3
6.0 PV
T
PV
T
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 370
Thaku
r
9
7
Hasur
am
Padam
Thaku
r
9
8
Naray
an
Padam
Thaku
r
9
9
Babur
ao
Padam
Thaku
r
1
0
0
Ramkr
ushna
Padam
Thaku
r
1
0
1
Vimal
Ganes
h
Thaku
r
1
0
2
Santos
h
Ganes
h
Thaku
r
1
0
3
Sandi
p
Ganes
h
Thaku
r
1
0
4
Sange
eta
Mahes
h
Mhatr
e
1
0
5
Janki
Laksh
man
Patil
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 371
1
0
6
Jayshr
ee
Devar
am
Mhatr
e
1
0
7
Kalpa
na
Kamla
kar
Mhatr
e
1
0
8
Maha
dev
Marya
Thaku
r
80
/3
PV
T
0.3
1.2 PV
T
PV
T
1
0
9
Ayatu
bai
Maruti
Patil
1
1
0
Ashok
Maha
dev
Thaku
r
1
1
1
Kamal
abai
Maha
dev
Thaku
r
1
1
2
Vanda
na
Mahes
h
Marat
he
1
1
3
Vijay
Maha
dev
Thaku
r
1
1
4
Dhanv
anti
Jagga
nath
Patil
1
1
1
5
1
5
Maha
dev 60
PV
T
0.3
4.4 0
0.0
113 2
PV
T
PV
T - - - - - - - - - - - - - -
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 372
5 5
1
1
6
3
1
Vittha
l
Mhatr
e
1
1
6
Ravin
dra
Krush
naji
Mhatr
e
1
1
7
1
5
6
3
1
1
5
6
9
4
Gajan
an
Phakir
Mhatr
e
59 PV
T
0.7
6.9
0.0
338
0.0
512
1 &
2
PV
T
PV
T - - - - - - - - - - - - - -
Sareb
hag
1
1
8
1
4
4
5
2
1
6
3
9
9
Gover
nment
of
Mahar
ashtra
(Parig
h)
16
5
G
O
V
T.
24.
89.
0
1.2
391
1.6
774 1
G
O
V
T.
GO
VT
.
- - - - - - - House(
c/s)
490
sqm
t
- - - - -
House(
c/s)
18
sqm
t
House
(f/s)
6
sqm
t
Vashi
1
1
9
1
6
3
0
6
1
6
3
4
4
Gover
nment
of
Mahar
ashtra
(Parig
h)
20
4
G
O
V
T
1.1
6.0
0
0.0
105
0.0
184 2
G
O
V
T
GO
VT - - - - - - - - - - - - - -
F 0.0
281
0.0
3 1
T
O
T
A
L
16
3.2
33
11.
576
12.
791
Hec
t.
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 373
Annexure 7.4: List of PAPs (People whose structures are getting Affected
Sl.No Description of Affected Structure
Type of Structure (Temporary/ Permanent)
Area/ Road Name
Land Mark Chainage
Lat/Long Property Owner
Agree/ Disagree to sell the plot
Remarks (if any)
1. 1 Electric Pole Permanent In Kalshri 5 18°46'41.13"N ,73° 2'13.37"E
2. 1 House Pakka Ravikant Narayan Thakur( 33*20 Feet) Room-3 Hall-1 Kitchen-1 Toiltet-1, Roof Lakdi
Permanent In Kalshri 10 18°46'41.45"N, 73° 2'13.17"E
Ravikant Narayan Thakur
No 1 House Pakka
3. 1 House Pakka Mira Bai Narayan Thakur ( 31*14 Feet) Room-2 Hall-1 Kitchen-1 Toiltet-1, Roof Cement Patra
Permanent In Kalshri 45 18°46'41.93"N 73° 2'12.53"E
Mira Bai Narayan Thakur
yes 1 House Pakka
4. Jetty, 17 Mtr.+5 Mtr* 2.5 Mtr.) after 17 mtr. Mengru and 5 mtr. Extra jeeti
Permanent In Kalshri 70 18°46'42.44"N 73° 2'12.52"E
Martian Board Yes Martian Board
5. 1 House Pakka Madan Sankar Patil ( 29*23 Feet) Room-1 Hall-1 Kitchen-1 Toiltet-1, Roof Cement Patra and Iron Pipe (water Tank 11*8*5 RCC) 1 Fish Pond 33*33 Feet
Permanent In Kalshri 75 18°46'42.83"N 73° 2'11.95"E
Madan Sankar Patil
yes
1 House Pakka
6. Service Electric Line Permanent In Kalshri 180 18°46'42.83" House Pakka yes Service Electric
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 374
- Madan sankar patil house to Sakar Murlidhar House
N 73° 2'11.95"E
Sankar Murlidhar Mathre
Line
7. 1 House Pakka Sankar Murlidhar Mathre( 24*18 Feet) Room-2 Hall-1 Kichan-1 Toiltet-1, Roof Lakdi, 2 Fish Pond (10*10 and 15*10 mtr.)
Permanent In Kalshri 390 18°46'46.03"N 73° 2'10.50"E
Sankar Murlidhar Mathre
yes 1 House Pakka
8. Sidi work, Ughadi (RCC 3.8*2.5) 1 Gate
Permanent In Kalshri 420 18°46'52.41"N 73° 2'7.91"E
Kharland yes Kharland
9. Pond Permanent In Kalshri 450 18°46'53.29"N 73° 2'7.18"E
Padam Nilkhant Thakur
yes Near saline Imbickment
10. Pond Permanent In Kalshri 480 18°46'54.10"N 73° 2'6.89"E
Padam Nilkhant Thakur
yes Near saline Imbickment
11. Pond Permanent In Kalshri 1770 18°46'54.66"N 73° 2'6.53"E
Padam Nilkhant Thakur
yes Near saline Imbickment
12. Sidi work at Band, Ughadi (RCC 3*2 Mtr.) 1 Gate
Permanent In Konoba 1800 18°47'11.21"N 73° 1'30.95"E
Kharland yes Imbickment
13. 1 House Pakka Tai Chandrakant Thakur ( 33*23 Feet) Room-2 Hall-1, Kichan-1 Toiltet-1,
Permanent In Konoba 1800 to 1850
18°47'10.98"N 73° 1'30.47"E
Chandrakant Thakur
Yes 1 House Pakka
14. 1 House Ravikant Baburao Thakur ( 23*21 Feet) Room-1 Kitchen-1, Baramda-1, Toiltet-1,
permenent In Konoba 1800 to 1850
18°47'10.97"N 73° 1'30.07"E
Ravikant Baburao Thakur
yes Pakka House
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 375
15. 1 House kacha Ravikant Baburao Thakur ( 20*15 Feet)
Permanent In Konoba 1800 to 1890
18°47'10.82"N 73° 1'29.33"E
Ravikant Baburao Thakur
Yes 1 House kacha
16. 1 House 20*12 Kalpana Akash Mhatre (Room-1, Kitchen-1)
Permanent In Konoba 1800 to 1890
18°47'10.52"N ,73° 1'27.80"E
Kalpana Akash Mhatre
Yes Pakka House
17. 1 House Pakka Tai Kamlakar Ganpat Bhoir( 34*18 Feet) Room-2 Hall-1, Kitchen-1 Toiltet-1,
Permanent In Konoba 1800 to 1890
18°47'10.94"N 73° 1'27.92"E
Tai Kamlakar Ganpat Bhoir
yes 1 House Pakka
18. 1 House Kisna Bitthal Bhoir 20*15, Room-1, Kitchen-1, Hall-1 and 10*10 jhopdi
Permanent In Konoba 1800 to 1890
18°47'10.38"N 73° 1'27.20"E
Kisna Bitthal Bhoir
Yes 1 House
19. 1 House Datta BitthalBhoir 20*15, Room-1, Kitchen-1, Hall-1
Permanent In Konoba 1800 to 1890
18°47'10.28"N 73° 1'26.96"E
Datta BitthalBhoir
Yes 1 House
20. 1 House Mayaram Bhoir 40*15, Room-1, Kitchen-1, Hall-1 and 10*10 jhopdi
Permanent In Konoba 1800 to 1890
18°47'10.32"N 73° 1'26.70"E
Mayaram Bhoir Yes Affected Structure of Mayaram Bhoir
21. 1 Jhopad Vijay Maya Bhoir 15*10 Feet
Permanent In Konoba 1800 to 1890
18°47'10.69"N 73° 1'26.63"E
Vijay Maya Bhoir
Yes
22. 1 House Anantram Bhoir 40*15, Room-1, Kitchen-1, Hall-1
Permanent In Konoba 1800 to 1890
18°47'10.38"N ,73° 1'26.86"E
Anantram Bhoir Yes
23. 3 Toilet (Anantrama,Mayarama and Pandurang)
Permanent In Konoba 1800 to 1890
18°47'10.62"N ,73° 1'26.49"E
Anantrama,Mayarama and Pandurang
Yes
24. 1 House Pandurang Dama 40*15, Room-
Permanent In Konoba 1800 to 1890
18°47'10.59"N 73°
Pandurang Dama
Yes
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 376
1,Kitchen-1, Hall-1 1'26.69"E 25. 1 Jhopadi Vinayak
Pandura Bhoir 15*10 Feet
Permanent In Konoba 1800 to 1890
18°47'10.59"N 73° 1'26.69"E
Vinayak Pandura Bhoir
Yes
26. 1 Jhopdi Nani Bai Ganpat Bhir 15*15, Room-1, Kitchen-1, Hall-1
Permanent In Konoba 1800 to 1890
18°47'10.38"N 73° 1'26.20"E
Nani Bai Ganpat Bhir
Yes
27. 1 Jhopdi, Ranjna parasuram Bhoir 20*20 Kachha, chat patra
Permanent In Konoba 1800 to 1890
18°47'10.58"N 73° 1'26.10"E
Ranjna parasuram Bhoir
Yes
28. 1 House Parasuram 34*20
Permanent In Konoba 1800 to 1890
18°47'10.44"N 73° 1'26.08"E
Parasuram Bhior
29. 5 Electrical Pole Permanent In Konoba 1800 to 1890
18°47'11.10"N 73° 1'30.05"E To 18°47'10.42"N 73° 1'25.11"E
MSEDCL Affected Structure of MSEDCL
30. 1 House Padmakar narayan Bhoir, Room-1, Kitchen-1
Permanent In Konoba 1800 to 1890
18°47'10.37"N 73° 1'25.75"E
Padmakar narayan Bhoir
31. 1 House Dasarath Padmakar, Room-2, Kitchen-1, Hall-1
Permanent In Konoba 18°47'10.38"N 73° 1'25.54"E
Dasarath Padmakar Bhior
32. 1 Well RCC Permanent In Konoba 1910 18°47'10.10"N 73° 1'25.17"E
G P Affected Structure of Grampanchayat
33. KacchaJhopdi 10*10 sankar Bhiva mhatre
Temporary In Konoba 1930 18°47'10.44"N 73° 1'24.66"E
sankar Bhiva mhatre
Kaccha Zopadi
34. Jetty, RCC 40*3 Permanent In Konoba 1980 to 2040
18°47'10.38"N, 73° 1'24.49"E
Maharashtra Maritain Board
Affected Structure of Maharashtra
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 377
Maritain Board 35. Shed 15*10 RCC Permanent In Konoba 1980 to
2040 18°47'10.46"N ,73° 1'24.36"E
Maharashtra Maritain Board
Affected Structure of Maharashtra Maritain Board
36. 3 Ota, 40*40 feet-1 and 2 small
Permanent In Konoba 1980 to 2040
18°47'10.18"N 73° 1'23.47"E
Affected Structure of Harder Department
37. Community Toilet -2 (3 Seat + 4 seat)
Permanent 1980 to 2040
18°47'10.18"N 73° 1'23.26"E
G P Affected Structure of Grampanchayat
38. 1 crematorium 23*20
Permanent 2280 18°47'10.14"N 73° 1'16.35"E
G P Affected Structure of Grampanchayat
39. 1 Pond (Santosh Maruti Mhatre Gat No.-59)
Permanent Vitthal Wadi 2340 18°47'11.31"N 73° 1'10.09"E
Santosh Maruti Mhatre
40. 1 Jhopdi kaccha 10*10
Permanent Vitthal Wadi 2460 18°47'11.17"N 73° 1'9.08"E
Santosh Maruti Mhatre
41. 1 Pond (in Govt land Gat No.-63)
Permanent Vitthal Wadi 2470 18°47'11.57"N 73° 1'8.27"E
42. 1 Jhopdi 20*15 Pakka
Permanent Vitthal Wadi 2480 to 2500
18°47'11.83"N73° 1'7.29"E
43. 1 Electrical pole Permanent Vitthal Wadi 2480 to 2500
18°47'12.16"N 73° 1'7.00"E
MSEDCL Affected Structure of MSEDCL
44. 1 Sidi work 3.7*2.3 mtr. RCC 1 Gate
Permanent Vitthal Wadi 2490 18°47'12.22"N 73° 1'6.70"E
45. 1 electrical Pole Permanent Vitthal Wadi 2520 18°47'12.43"N 73° 1'6.38"E
MSEDCL Affected Structure of MSEDCL
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 378
46. 1 Solar Light Permanent Vitthal Wadi 2550 -2580
18°47'13.03"N 73° 1'5.08"E
Grampanchyet Grampanchyet
47. 1 Electrical Pole Permanent Vitthal Wadi 2550 -2580
18°47'13.25"N 73° 1'5.27"E
MSEDCL Affected Structure of MSEDCL
48. 1crematorium, Siting Sed 12*4 mtr. RCC+ Chhat Tin, + 8.5*6.5 ShamsanGhat Tin, + 8.5*6.5 6 gatar
Permanent Vitthal Wadi 2550 -2580
18°47'13.32"N 73° 1'5.50"E
G P Affected Structure of Grampanchayat
49. 1 Fish Pond (Kiran Patil)
Permanent Vitthal Wadi 2850 18°47'18.72"N 73° 1'0.05"E
Kiran Patil
50. Road Effected Permanent Vitthal Wadi 2910-2970
18.789266°-73.016265° to 18.790084°-73.015875
Grampanchyet Affected Structure of Grampanchyet
51. 1 Toilet 4 Seat (Community)
Permanent Vitthal Wadi 2910-2940
18°47'21.36"N 73° 0'58.55"E
Grampanchyet Affected Structure of Grampanchyet
52. 1 Toilet 4 Seat (Community)
Permanent Vitthal Wadi 2910-2940
18°47'21.37"N 73° 0'58.53"E
G P Affected Structure of Grampanchyet
53. 1 Pond (Ratnakar Krushna Mhatre gat No.-417)
Permanent Vitthal Wadi 2940 18°47'21.89"N 73° 0'58.06"E
Ratnakar Krushna Mhatre
54. 1 Pond (RamchnadraNagaji Mhatre gat No.-416)
Permanent Vitthal Wadi 2945 18°47'22.69"N 73° 0'57.43"E
RamchnadraNagaji Mhatre
55. 1 Ota (16*8 Mtr) Permanent Vitthal Wadi 2950-2970
18°47'22.87"N 73° 0'57.38"E
Harber Department
Affected Structure of Harber Department
56. 1 Toilet 4 Seat Permanent Vitthal Wadi 2970 18°47'23.45" Grampanchyet Affected
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 379
(Community) N 73° 0'57.40"E
Structure of Grampanchyet
57. 1 Ota (8*6 Mtr) Permanent Vitthal Wadi 2985 18°47'24.08"N 73° 0'57.27"E
Harber Department
Affected Structure of Harber Department
58. 1 Passenger Sed 6.5*4 Mtr. RCC
Permanent Vitthal Wadi 2990 18°47'24.33"N 73° 0'57.02"E
Maharashtra Maritain Board
Affected Structure of Maharashtra Maritain Board
59. 1 Jetty (4*8.8+17+10)
Permanent Vitthal Wadi 2990 18°47'24.23"N 73° 0'57.12"E
Maharashtra Maritain Board
Affected Structure of Maharashtra Maritain Board
60. 2 Pond (0.8 htr.+0.2 htr.) Sibhas tanaji mhatre and Rancho rTanaji mhatre (in rent)+ 1 Shed 11*4 mtr.tin Gat No-402
Permanent Vitthal Wadi 3280 18°47'35.29"N 73° 0'52.05"E
Sibhas tanaji mhatre and Rancho rTanaji mhatr
61. 2 Pond Yasbant Ambaji Mahatre, Amarchand Ganpat Mhatre, santosh Maruti Mhatre, toSashankThakre (Rent) Gat no. 387, 379, 378
Permanent Vitthal Wadi 3780 18°47'51.55"N 73° 0'44.01"E
Ambaji Mahatre, Amarchand Ganpat Mhatre, santosh Maruti Mhatre, toSashankThakre
62. Sluice Gate (RCC, 4.5*3 Mtr., Gate-2), 50*3 mtr. RCC
Permanent Vitthal Wadi 6750 18°47'30.27"N 72°59'49.32"E
Kharland Dep Affected Structure of Kharland Dep
63. Sluice Gate (RCC, 6*2.3 Mtr., Gate-2)
Permanent Vitthal Wadi 7230 18°47'17.94"N 72°59'59.16"E
Kharland Dep Affected Structure of Kharland Dep
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 380
64. Sluice Gate, 1+1, 4.5*28, 4*2 Mr. RCC
Permanent Janavali 8760 18°46'32.42"N 73° 0'7.72"E
Kharland Dep Affected Structure of Kharland Dep
65. Jetty-2.5 Breadth Permanent Janavali 8790 18°46'31.06"N 73° 0'7.01"E
Maharashtra Maritain Board
Affected Structure of Maharashtra Maritain Board
66. Balaram house, 21*14 feet, pakka,
Permanent Janavali 9000 18°46'23.93"N73° 0'2.13"E
Balaram
67. 1 sluice Gate 4*1.3, RCC , gate-1
Permanent Ghoda Bander
9555 18°46'11.24"N 72°59'55.97"E
Kharland Dep Affected Structure of Kharland Dep
68. 1 Crematorium, 6.8*6 mtr. RCC, 6 Gatar
Permanent Ghoda Bander
9555 18°46'11.41"N 72°59'56.02"E
Affected Structure of Grampanchayat
69. 1 Jetty, 2.7*145 mtr. Permanent Ghoda Bander
9585 18°46'10.10"N 72°59'55.22"E
Maritain Board Yes Affected Structure of Maharashtra Maritain Board
70. 2 Pond Amarchnd baliram mhatre Gat-290/1
Permanent Bahiram Kotak
10500 18°45'51.78"N 72°59'48.35"E
Amarchnd baliram mhatre
71. 1 Fish Pond Jaiprakash kashinath Patil Gat No.-154
Permanent Bahiram Kotak
12420 18°45'12.97"N 73° 0'0.91"E
Jaiprakash kashinath Patil
72. 1 Fish Pond Kishor Ananat Mhatre
Permanent Bahiram Kotak
13020 18°45'21.45"N 73° 0'17.99"E
Kishor Ananat Mhatre
73. 1 crematorium, 7*6 mtr. RCC, Chat Iron Pipe Support and tin
Permanent Bahiram Kotak
13030 18°45'21.68"N 73° 0'18.57"E
Grampanchayat Affected Structure of Grampanchayat
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 381
6 Ghatar 74. 1 Temple (Bahari
dev) Permanent Bahiram
Kotak 13230 18°45'21.64"
N 73° 0'23.44"E
People of Bahiram Kotak
75. 1 Jeety, 3* 8+11+6 mtr.
Permanent Bahiram Kotak
13230 18°45'21.29"N 73° 0'23.47"E
Maritain Board Affected Structure of Maharashtra Maritain Board
76. 3 Houses Dharma Narayan Mali 9*6.5 Mtr. Room-1, Kichan-1, Hall-1, Vaishali Sankar mali 7.5*6.5 Mtr.Room-1, Kitchen-1, Hall-1 1 House Prakash Naryanmali 6.5*5 mtr.Room-1, Kitchen-1, Hall-1
Permanent Bahiram Kotak
13260 18°45'22.27"N 73° 0'26.13"E
Dharma Narayan Mali Vaishali Sankar mali Prakash Naryan mali
Yes Seprat House
77. 1 Fish Pond Chandra Kant Ganpat patil
Permanent Bahiram Kotak
13320 18°45'20.43"N 73° 0'27.95"E
Chandra Kant Ganpat patil
78. 2 Fish Pond Jankai Laxman patil &Sandesh Laxman Patil
Permanent Benvale 13680 18°45'16.78"N 73° 0'36.19"E
Jankai Laxman patil & Sandesh Laxman Patil
2 Ponds
79. 2 Fish Pond PanduramKrusna Patil (Gat No.12),
Permanent Benvale 13770 to 13800
18°45'13.44"N 73° 0'37.52"E
PanduramKrusna Patil
Yes
80. 1 Temple- Bap dev bhagwan
Permanent Benvale 13770 to 13800
18°45'13.44"N 73° 0'37.52"E
prabhakar sankar thoi
Yes Personal Temple
81. 1 Pond (prabhakar Permanent Benvale 14040 18°45'8.73"N prabhakar Yes
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 382
sankar thoi) 73° 0'44.69"E
sankar thoi
82. 1 jetty 3.5*17+13+5 Permanent Waskand, Washi
15420 18°44'57.85"N 73° 1'25.29"E
Maritain Board Yes Affected Structure of Maharashtra Maritain Board
83. 1 Electrical Pole Permanent Waskand, Washi
16320-16350
18°45'4.73"N 73° 1'51.94"E
MSEDCL Yes Affected Structure of MSEDCL
84. 1 Solar light Permanent Waskand, Washi
16320-16350
18°45'4.73"N 73° 1'51.94"E
Maritain Board Yes Affected Structure of Maharashtra Maritain Board
85. Sluice Gate, 2.5*4 Permanent Waskand, Washi
16320-16350
18°45'4.73"N 73° 1'51.94"E
Kharland Yes Affected Structure of Kharland
86. 1 Solar light Permanent Waskand, Washi
16350 18°45'4.10"N 73° 1'52.17"E
Maritain Board Yes Affected Structure of Maritain Board
87. Sluice Gate, 2.8*15 mtr. 5 Gate lakdi RCC
Permanent Waskand, Washi
16380 18°45'2.13"N 73° 1'53.71"E
Kharland Yas Affected Structure of Kharland
88. 2 Solar light Permanent Waskand, Washi
16410 to 16440
18°45'1.02"N 73° 1'54.19"E
Maritain Board Affected Structure of Maharashtra Maritain Board
89. Jetty RCC. 3.3* Permanent Waskand, Washi
16440 18°45'1.02"N 73° 1'54.19"E
Maritain Board Affected Structure of Maritain Board
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 383
Annexure 8.1: CRZ Clearance Letter
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 384
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 385
Draft Final EIA for Project “Renovation of Saline Embankment of Narvel Benavale, Taluka Pen, District Raigad, Maharashtra under NCRMP-II Project
EQMS Document No: EQMS-NCRMP-SE-EIA/Narvel/01 Issue 01 R 00 386
Annexure 8.2: Formats for Ambient Air and Noise Monitoring
Format for Ambient Air Quality and Noise Monitoring Format for Air quality Monitoring Date of Analysis Testing Period Report NO.: - Report DATE: - Name of CLIENT: ADDRESS: - Type of WORK: - Ambient Air monitoring Sample Ref. No. :- Sample Drawn BY: Representative Duration of sampling 24 Hrs. Date of ANALYSIS: - Testing Period 01 Day Location/Site S. NO
Sampling Stations
Date of Sampling
PM10µg /m3
PM2.5µg /m3
SO2 µg /m3
NOX µg /m3
CO mg /m3
Method: - IS:5182 (Part-23)
IS:5182 (Part-23)
IS:5182 (Part-II)
IS:5182 (Part-VI)
IS:5182 (Part-X)
CPCB Standards 100
(24 hrs) 60 (24 hrs)
80 (24 hrs)
80 (24 hrs)
2.0 (8 hrs)
For, M/s ………………………………….. Chemist /Authorized Signatory Format for Noise Monitoring Location/Site:
S. No Location Date of Sampling
Time of Sampling
Noise Level dB(A)
Day Night For, M/s ………………………………….. Chemist /Authorized Signatory