report bi-weekly construction progress · 2020-07-23 · period: 7/07/20 - 7/20/20 community high...
TRANSCRIPT
Period: 7/07/20 - 7/20/20
Community High School District 99
Master Facility Plan Implementation
Wight Construction Services2500 North Frontage RoadDarien, IL 60561
Bi-Weekly Construction ProgressReport
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase B - Fine Arts Addition
360° Pictures: Demo Kitchen Ceramics Studio 2D Studio Art Gallery - East
• Prepped and started flooring in 2nd floor corridor. Installed sheet vinyl in science lab
• Started stone grading for patios and excavations for Dunham drop off
• Continued hanging lights and installing door hardware where accessible
• Finished installing new window frame east of bridge and started painting them
• Started installations of display cases and speakers
• Started metal panels installation at west wall
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase B - Bleachers & Squad Rooms
• Installed water piping and started sprinkler piping. Installed gas line
• Continued plastic and insulation in second squad room
• Cleaned up outside in preparation for exterior grading and concrete
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase C - Auditorium
• Finished all foundations, SOG and wall bracing needed to erect precast panels
• Assembled crane and started precast panel erection, finishing 80% of auditorium box
• Installed East columns and corresponding beam before erecting west panels of auditorium box
• Steel will follow with an expected pouring date for the auditorium box roof on August 1st
• Started installing wrestling room steel joists
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase C - Learning Commons
• Built scaffold at north tower and started laying CMU walls
• Installed column wraps for 1st floor columns and poured interior piers
• Continued installing VAVs and wrapping duct/piping on 2nd floor. AHUs were delivered and arebeing installed
• Assembled crane in south parking lot and started steel erection
• Continued taping at electric room & commons offices
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase B - Gym, Kitchen, Alley, Multipurpose,and Gymnastics Loft Addition
360° Pictures: Main Gym Kitchen Multi-Purpose Room Gymnastics Room
• Floor tile has been fully set in the servery area, with the kitchen following shortly behind
• Elevator install started. Lula Lift fully installed, with few punchlist items pending
• Gym accent color bands have been painted, doors installed, and ceiling grid set
• Multipurpose room has been fully painted, lights and overhead equipment has been hung
• Gymnastics room has been fully rocked, taped and will be ready for paint next week
• Alley windows have been installed. Skylight glass install is currently underway
Servery
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase B - Bleachers & Squad Rooms
• All CMU perimeter walls have been erected, interior CMU bathroom walls to proceed this week
• Bleacher crew has completed their install of the backside panels and will begin installing theexterior enclosure this week
• MEP trades continue performing their rough in-s, which will be followed by final grading forflatwork, expected to be poured the first week of August
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase C - Cafeteria, Culinary Arts, Commons,and Southeast Addition
• Dining area has been rocked/taped, prepped for floor tile, and columns have been tiled. Flooringcurrently underway
• Culinary area has been rocked and landings for the incoming millwork has been laid out
• Elevator shaft from basement to 2nd floor has been fully erected, 1st deck floor tie-in poured,basement ramp set to be poured this week
• All floor decks along the SE Addition (1st, 2nd, 3rd Floors) including miscellaneous buildinginfills have been poured out and are ready to receive rough MEP connections and exterior framing
• Courtyard demo of piers complete – additional structural work to start in the coming weeks
• Roof survey and layout for incoming steel along courtyard perimeter is currently underway
360° Pictures: Commons