report%28september004
DESCRIPTION
Svinesund BridgeTRANSCRIPT
-
Brobyggnad
KTH Brinellvgen 34, SE-100 44 Stockholm
Tel: 08-790 9084, Fax: 08-21 69 49
www.byv.kth.se/avd/bro
Monitoring of the New Svinesund Bridge
Presentation of some measured data including the lifting of the mid-section of the bridge deck on 25 July
Raid Karoumi & Gerard James
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
2 (18)
Contents
1 General information & some important events .................................................................. 3
2 Presentation of statistical results ........................................................................................ 4
2.1 Wind and outside air temperature data................................................................... 4 2.2 Strain in the arch .................................................................................................... 6 2.3 Temperature in concrete....................................................................................... 11
3 Presentation of raw data results........................................................................................ 13
3.1 Arch frequencies .................................................................................................. 13 4 Summary and conclusions................................................................................................ 18
Copyright Dept. of Civil and Architectural Engineering KTH Stockholm September 2004
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
3 (18)
1 General information & some important events
As the amount of triggered raw data files have increased after erecting the deck of the main span, the trigger criteria for standard deviation for accelerations was increased on the 10th of September from 2 to 10 mm/s2.
25th -27th of July the main span was erected.
During the period June to August 2004, several long stops occurred of the SMHI:s windsensor most certainly due to main 230 V power problems at site. SMHI is informed and will try to solve the problem by installing a battery backup to their system.
Klaus at NGI has investigated the ADSL alternatives and promised to present them during September.
On the 4th of June NGI modified/reconnected the power supply on the Swedish side in Bilfingers 230V supply box for datasystem and SMHI windsensor.
Starting on the 20th of May, wind direction is evaluated correctly in NGI's system. Wind direction data from SMHI agree now with data on BridgeMon..
Starting on the 8th of April, wind direction is evaluated correctly in SMHI's system.
Equipment for power failure alarm have been installed in week 12 for the data systems both on N- and S-side in order to minimize repair time and data logging down-time.
More important details and dates can be found in the diary on the monitoring projects homepage http://www.byv.kth.se/svinesund/diary.htm
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
4 (18)
2 Presentation of statistical results
2.1 Wind and outside air temperature data
Figure 2.1 Outside air temperature.
Figure 2.2 Wind direction - wind rose.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
5 (18)
Figure 2.3 Wind speed and direction from SMHI:s system.
0
1
2
3
4
5
6
7
8
9
10
11
12
Feb Mar Apr May Jun Jul Aug
284 WindH.Mean
Figure 2.4 Wind speed from NGI/KTH:s system.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
6 (18)
2.2 Strain in the arch
-400
-300
-200
-100
0
100
200
300
400
Apr2004
May Jun Jul Aug Sep
Channel 74 (StatData 010404-260804.bin)
48 VWS1-T.Mean 290 RSS1-T.Mean (-560.62)
291 VWS1-B.Mean (+100)
Figure 2.5 Comparison of strain readings at segment S1. The above figure show clearly that the two strain signals from vibrating-wire and resistance strain sensors agree well with each other. VWS1-T show signal disturbance in August.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
7 (18)
-250
-200
-150
-100
-50
0
50
100
150
200
250
300
350
Oct2003
Jan 2004 Apr Jul
Channel 74
48 VWS1-T.Mean 292 VWN1-T.Mean (-25)
Figure 2.6 Comparison of strain readings from the top of segment S1 and N1.
This figure show that the top of N1 is in compression compared to S1. The two curves follow each other rather closely until the release of the back-stay cables in March. Possible reasons for the different behaviour of S1 and N1:
different tension in the back-stay cables on the S- and N-side the erection of side span deck sections started earlier on the Norwegian side different support stiffness
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
8 (18)
-450
-400
-350
-300
-250
-200
-150
-100
-50
0
50
100
Oct2003
Jan 2004 Apr Jul
Channel 74
293 VWS1-B.Mean (+100) 294 VWN1-B.Mean (+155)
Figure 2.7 Comparison of strains at the bottom of segments N1 and S1. Signal disturbance in VWN1-B.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
9 (18)
-400
-300
-200
-100
0
100
200
300
400
Oct2003
Jan 2004 Apr Jul
Channel 74
48 VWS1-T.Mean 290 VWS6-T.Mean (+140)
293 VWS1-B.Mean (+100) 298 VWS6-B.Mean (+190)
Figure 2.8 Comparison of strains at S1 and S6. At the final stag, approximately zero tension at VWS6-T and VWS1-T is obtained closing the earlier developed cracks.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
10 (18)
-1500
-1000
-500
0
500
1000
Mar2004
Apr May Jun Jul Aug
Channel 74
295 RSS25-B.Mean (-1940) 296 RSS25-T.Mean (-2100)
297 RSS25-W.Mean (+980)
Figure 2.9 Strain readings from RSS25-T, RSS25-B and RSS25-W. As seen from the strain curves, the lifting of the main deck started on the 25th of July. The reinforcement at the top of segment S25 has approximately zero strain at this final stage. Developed cracks on the top of the segment are now closed. The east and west walls of segment S25 are still in tension, possibly due to the two installed steel pressure bars.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
11 (18)
2.3 Temperature in concrete
15
20
25
30
35
40
45
50
100
200
300
400
500
600
700
800
900
1000
Thu 1Jul 2004
Thu 8 Thu 15 Thu 22 Sun 1 Sun 8 Sun 15 Sun 22Channel 74
176 TS25-WO.Mean 184 TS25-WM.Mean
297 RSS25-W.Mean (+980)
25
30
35
40
45
50
400
500
600
700
800
900
Mon 9Aug 2004
Tue 10 Wed 11 Thu 12 Fri 13Channel 74
20
25
30
35
40
45
300
400
500
600
700
800
900
Sat 7Aug 2004
3:00 6:00 9:00 12:00 15:00 18:00 21:00 Sun 8Channel 74
( )
Figure 2.10 This figure illustrates the temperature effect on the strain in section S25. The right Y-axis gives the strain (microstrain) and the left Y-axis the temperature (degrees
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
12 (18)
Celsius). As seen a temperature difference of about 9 degrees corresponds to a strain difference of about 260 microstrain.
-10
-5
0
5
10
15
20
25
30
Jan 2004 Feb Mar Apr May Jun Jul Aug Sep
Channel 74
84 TS6-B.Mean 88 TS6-E.Mean 92 TS6-W.Mean 96 TS6-T.Mean
Figure 2.11 This figure illustrates the temperature difference between top, bottom, east and west walls of segment S6.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
13 (18)
3 Presentation of raw data results
3.1 Arch frequencies
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 20
500
1000
1500PS
D v
ert
Power Spectrum ACCS14(D20040709141040.bin)
1.17
0.77
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 20
1000
2000
3000
4000
PSD
hor
is
Frequency/Hz
0.43
0.87
1.37
Figure 3.1 The power spectral density from the accelerometers at approximately the quarter point of the arch, S14. The measurements were made on the 9th July 2004.
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 20
500
1000
1500
PSD
ver
t
Power Spectrum ACCN26(D20040709141040.bin)
1.17
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 20
0.5
1
1.5
2
x 104
PSD
hor
is
Frequency/Hz
0.43
Figure 3.2 The power spectral density from the accelerometers at the mid-point of the arch, N26. The measurements were made on the 9th July 2004.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
14 (18)
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 20
10
20
30
40
PSD
ver
t
Power Spectrum ACCS14(D20040721154631.bin)
0.76
1.16
1.72
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 20
50
100
PSD
hor
is
Frequency/Hz
1.37
0.85
0.43
Figure 3.3 The power spectral density from the accelerometers at approximately the quarter point of the arch, S14. The measurements were made on the 21st July 2004.
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 20
100
200
300
PSD
ver
t
Power Spectrum ACCN26(D20040721154631.bin)
1.16
1.72
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 20
10
20
30
40
50
PSD
hor
is
Frequency/Hz
0.42
1.32 1.37
Figure 3.4 The power spectral density from the accelerometers at the mid-point of the arch, N26. The measurements were made on the 21st July 2004.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
15 (18)
0 0.5 1 1.5 2 2.5 3 3.5 40
2000
4000
6000
PSD
ver
t
Power Spectrum ACCS14(D20040825151438.bin)
0.75
1.5
2.47
0 0.5 1 1.5 2 2.5 3 3.5 40
1000
2000
3000
4000
PSD
hor
is
Frequency/Hz
0.99
0.46
Figure 3.5 The power spectral density from the accelerometers at approximately the quarter point of the arch, S14. The measurements were made on the 25th Aug 2004.
0 0.5 1 1.5 2 2.5 3 3.5 40
500
1000
1500
2000
2500
PSD
ver
t
Power Spectrum ACCN26(D20040825151438.bin)
2.471.5
0 0.5 1 1.5 2 2.5 3 3.5 40
0.5
1
1.5
2
x 104
PSD
hor
is
Frequency/Hz
0.46
1.05
Figure 3.6 The power spectral density from the accelerometers at the mid-point of the arch, N26. The measurements were made on the 25th Aug 2004.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
16 (18)
0 0.5 1 1.5 2 2.5 3 3.5 40
0.05
0.1
0.15
PSD
ver
t
Power Spectrum ACCS14(D20040904000144.bin)
1.50
2.35
3.42
0 0.5 1 1.5 2 2.5 3 3.5 40
0.05
0.1
0.15
PSD
hor
is
Frequency/Hz
0.43
0.94
1.40
Figure 3.7 The power spectral density from the accelerometers at approximately the quarter point of the arch, S14. The measurements were made on the 4th Sept 2004.
0 0.5 1 1.5 2 2.5 3 3.5 40
0.05
0.1
0.15
0.2
0.25
PSD
ver
t
Power Spectrum ACCN26(D20040904000144.bin)
1.49
0 0.5 1 1.5 2 2.5 3 3.5 40
0.1
0.2
0.3
0.4
PSD
hor
is
Frequency/Hz
0.43
1.04
Figure 3.8 The power spectral density from the accelerometers at the mid-point of the arch, N26. The measurements were made on the 4th Sept 2004.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
17 (18)
Table 3.1. A comparison of the measured natural bending frequencies during the construction phase. The 6th of February was before the arch stone was in place. On the 9th and the 21st of July the middle section of the bridge deck was not in place. On the 25th of August and for the September measurements, the bridge deck was complete.
Horizontal Frequency Hz Vertical Frequency Hz Date 1st 2nd 3rd 1st 2nd 3rd 6th Feb 2004 0.34 1.25 0.47 0.98
9th July 2004 0.43 0.87 1.37 0.77 1.17 -
21st July 2004 0.42 0.85 1.37 0.76 1.16 1.72
25th Aug 2004 0.46 1.00 - 0.75 1.5 2.47
4th Sept 2004 0.43 0.94-1.04 1.40 (0.77) 1.49
6th Sept 2004 0.44 0.95 (0.77) 1.49 2.35-2.41 Table 3.1 shows the natural frequencies of the arch during different stages of the construction phase. For the measurement on the 6th of February, the arch stone was not in place and therefore the measurement was for the two halves for the arch acting separately. The mid-section of the bridge deck was lifted into place between the 25th to the 27th of July 2004. At the time of writing this report we lack information regarding the construction methods at different stages such as the manner in which the bridge deck is attached to the arch during these dates and when the mid-section of the bridge deck had been welded to the earlier constructed bridge deck.
-
Monitoring of the New Svinesund Bridge KTH/Brobyggnad
18 (18)
4 Summary and conclusions
This short report presents some measured data including the lifting of the mid-section of the bridge deck on the 25-27 of July. The presented figures show very interesting results, especially those for temperature and concrete strain. Earlier developed cracks at the top wall of the arch are now closed as this part of the arch have no tension at this final stage. The east and west walls of segment S25 are still in tension, possibly due to the two installed steel pressure bars. The strain curves for the part of the Swedish arch do not agree with those of the Norwegian part. This illustrates the influence of the order in which the work on site is done, as it is believed that the construction sequence of the side span decking sections have affected the strains in the arch. Valuable wind data has been lost during the summer period due to main power failures. It was interesting to note that the first horizontal and vertical natural frequencies of the arch do not appear to have changed appreciably after the lifting of the mid-section of the steel bridge deck. Compare a change in the first natural frequencies of 0.42 to 0.46 Hz for the horizontal and unchanged at approximately 0.75 Hz for the first vertical. However, the higher natural frequencies have increased notably.
A great deal of additional information and reports on The New Svinesund Bridge are available on theWorld Wide Web at the following address: www.byv.kth.se/svinesund