request for tender no. 1819
TRANSCRIPT
Request for Tender No. 1819
2016 Sidewalk and Traffic Circle Project
Issue date: September 29, 2016
Closing Location Purchasing Department
2020 Labieux Road Nanaimo, BC V9T 6J9
City Contact Mike Strain
Construction Project Manager Telephone: (250)756-5328
Email: [email protected]
Closing date and time Responses must be received at the Purchasing Department before
3:00 PM Pacific Time on October 13, 2016
Site Visit
No formal site visit will be conducted. It is the bidder’s responsibility to view the site to determine the existing conditions, layouts and limitations and ask
any questions prior to submitting their bid.
Questions Cut Off Question cut off is the end of the business day on October 11, 2016
Tenders will not be opened in Public. Unverified tender results will be sent to all vendors that submit a bid
TABLE OF CONTENTS Instructions to Bidders Minimum Rate of Pay Bid Form Schedule of Quantities General Terms & Conditions Section 2, 3, 4, 5, 7, 8, 9, and 12 Measurement and Payment APPENDICES Appendix A - Prime Contractor Form Appendix B - Prime Contractor Preconstruction Meeting Form Appendix C - Receipt Confirmation Form
TENDER DRAWINGS 1819 JINGLE POT, SECOND, AND WENTWORTH – IFT DRAWINGS
SHEET DRAWING TITLE DATE 1 21521 COVER SHEET
KEY PLOAN, LOCATION PLAN 22-Sep-16
2 21522 ROADWORKS PLAN
JINGLEPOT STA. 0+090 TO 0+450 22-Sep-16
4 21524 ROADWORKS PLAN
JINGLEPOT STA. 0+810 TO 1+180 22-Sep-16
5 21525 ROADWORKS PLAN
SECOND STA. 1+180 TO 1+540 22-Sep-16
7 21527 ROADWORKS PLAN
WENTWORTH STA. 0+090 TO 1+470 22-Sep-16
8 21528 ROADWORKS PLAN
WENTWORTH STA. 1+470 TO 1+820 22-Sep-16
1819 VANCOUVER AND TOWNSITE – IFT DRAWINGS
SHEET DRAWING TITLE DATE
1 21566 COVER SHEET KEYPLAN, LOCATION PLAN
26-Sep-16
4 21569 CURB EXTENSION, TRAFFIC SIGNS AND STREET MARKINGS
TOWNSITE ROAD TERMINAL TO STEWART
26-Sep-16
5 21570 DETAILS 26-Sep-16
INSTRUCTIONS TO TENDERERS ARTICLE 1. TENDER Tenders clearly marked "Tender No. 1819 2016 Sidewalk and Traffic Circle Project” will be received by the Purchasing Agent up to 3:00 p.m. local time, October 13, 2016 at the Purchasing office, City of Nanaimo, 2020 Labieux Rd, Nanaimo, BC, V9T 6J9. Tenders will not be opened in public. The wall clock in the Purchasing Department is the official time piece. ARTICLE 2. SCOPE OF WORK The work consists of the installation of approximately 300m² of asphalt sidewalk, 190m² of concrete sidewalk, 200m of concrete curb, 2 catch basins with leads, approximately 350 tons of slope fill, and all other work incidental thereto as shown on the drawings specification and contract documents. Excluded items include:
1) All landscaping will be by others. 2) Other than the relocation of 2 signs on Jingle Pot Road and removal of the 4 signs
included in the roundabout, all other signage removal, supply, and installation will be by others.
3) All line painting and street markings will be by others. 4) Pole relocation will be by others. City is in the process of relocating the pole.
The successful Contractor is responsible to provide own power, water, and portable toilet. Materials and Installation: In accordance with Sections 3, 4, 5, 7, 8, 9, 12 of the 2013 City of Nanaimo Manual of Engineering Standards and Specifications Edition No. 10 at the following link: http://www.nanaimo.ca/EN/main/departments/Engineering-Public-Works/4491/engineering-standards-manual.html ARTICLE 3. SITE VISIT No formal site visit will be conducted. It is the responsibility of the potential contractors to be familiar with the site to determine the existing conditions, layouts and limitations and ask any questions. In submitting a tender, the contractor confirms that he/she has viewed the site and the tender includes any equipment, materials and labour necessary for this project. The contractor will rely entirely upon his/her own judgment in submitting a tender and include a sum sufficient to cover all items required for the contract. ARTICLE 4. RECEIPT CONFIRMATION FORM Tenderers are encouraged to complete and return the ‘Receipt Confirmation Form” in order to have any addenda sent directly to your firm. Regardless, it is the Tenderer’s sole responsibility to
check the City’s Purchasing Department for any addenda prior to submitting their Tender and include any changes in their Tender. ARTICLE 5. EXAMINE The Tenderer must carefully examine the Contract Documents and the site of the proposed works, judging for and satisfying himself as to the probable conditions to be encountered. Should a Tenderer find discrepancies in, or omissions from the drawings or other documents, or should he be in doubt as to their meaning, he should, prior to submitting his tender, notify the City in writing. The Tenderer may not claim, after the submission of a tender, that there was any misunderstanding with respect to the conditions imposed by the documents. The Tenderer's attention is drawn to any addenda which may be issued prior to the time of tender closure. No verbal agreement or conversation made or had at any time with any officer, agency or employee of the Owner shall affect or modify any of the terms or obligations herein stated, nor deemed to be any representation of warranty. ARTICLE 6. SUBMISSION METHODS Submission methods (use one of the methods below to submit your tender):
a) Via email at the only acceptable email address: [email protected] All email submissions must be less than 8MB b) Via hard copy: One (1) hard copy in a sealed envelope delivered to the Purchasing
Department, 2020 Labieux Road, Nanaimo, B.C., V9T 6J9 c) Via facsimile at the only acceptable facsimile number: (250)756-5327
It is the Bidder’s sole responsibility to ensure their Tender is received prior to the posted closing date and time. Bidders are strongly encouraged to call the Purchasing Department to ensure receipt prior to the posted closing date and time. ARTICLE 7. PROPOSED ALTERNATE MATERIALS No alternates will be considered. Please bid as specified. ARTICLE 8. FEDERAL AND PROVINCIAL SALES TAXES Lump sum prices shall include provincial sales tax payable on all applicable materials and equipment incorporated in the work. GST is not to be included in the lump sum price. GST shall be shown separately on the Tender Form based on the total contract value.
ARTICLE 9. TENDER PRICE Unit prices shall be filled in where indicated on the Tender Form. In the event of a price extension discrepancy when calculating the total contract value, the City reserves the right to correct the totals. ARTICLE 10. BONDING No bonding or bid security is required for this project. ARTICLE 11. REVISIONS TO TENDER Any revision to the tender by the Tenderer must be in writing and received by the Purchasing Agent at the closing location before the closing time. Faxcom revisions must be faxed to the only acceptable fax number of 250.756.5327. The Tenderer assumes all responsibility for the timely and effective delivery of any revisions. Where a Tenderer submits multiple revisions to the original tender price, each revision should be numbered sequentially by the Tenderer. Unless the Tenderer clearly stipulates to the contrary on the face of the revision, each successive revision will nullify and replace any previous revision to the identified item or tender price. If in the opinion of the City, any revision is unclear, ambiguous as to meaning or intent, that revision will be disregarded and the original tender price, or the tender price determined by consideration of any other revisions will prevail. The City, its employees and agents will not assume any responsibility for timely receipt of any revisions. ARTICLE 12. TENDER SIGNING The tender must be executed by an authorized signatory in a position to legally bind their Company to the information contained in the Tender Form. ARTICLE 13. TENDER WITHDRAWAL A Tenderer may, without prejudice to himself, withdraw his tender on written request received by the Purchasing Agent any time prior to the time set for the closing of tenders. ARTICLE 14. TENDER REJECTION .1 The City of Nanaimo reserves the right to reject any or all tenders, or accept other than the
lowest tender and to accept the tender which it deems most advantageous to the City of Nanaimo.
.2 To determine whether a Tenderer is qualified to do the work, the following criteria will be
used: a) The Tenderer’s ability and agreement to complete the work within the Construction Schedule; b) The Tenderer’s references;
.3 The City of Nanaimo may reject a tender if:
a) After investigation and consideration, the City concludes that the Tenderer is not qualified to do the work and/or cannot do the work and perform the Contract in a manner satisfactory to the City of Nanaimo. b) A tender contains qualifying conditions or otherwise fails to conform to these Instructions to Tenderers. c) A tender is incomplete, is considered incomplete in the Instructions to Tenderers, is obscure or irregular, which has erasures or corrections in the Tender Form, in which prices are omitted or are unbalanced, or which has an insufficient or irregular surety. d) The City of Nanaimo may, in its absolute discretion, reject a Tender submitted by Tenderer if the Tenderer, or any officer or director of the Tenderer is or has been engaged either directly or indirectly through another corporation in a legal action against the City of Nanaimo, its elected or appointed officers and employees in relation to: e) any other contract for works or services; or f) any matter arising from the City of Nanaimo’s exercise of its powers, duties, or functions under the Local Government Act or another enactment.
.4 In determining whether to reject a tender under this clause, the City of Nanaimo will consider whether the litigation is likely to affect the Tenderer’s ability to work with the City of Nanaimo, its consultants and representatives and whether the City of Nanaimo’s experience with the Tenderer indicates that the City of Nanaimo is likely to incur increased staff and legal costs in the administration of this contract if it is awarded to the Tenderer.
.5 The City of Nanaimo, however, may at its sole discretion elect to retain for consideration a tender which is non-conforming because it does not contain the content or form required by these Instructions to Tenderers or because a Tenderer has not complied with the procedures set out in the Instructions to Tenderers provided that the Tenderer complies substantially with the Instructions to Tenderers. .5 The City may reject all tenders if for any reason the City considers to be in its best interest to
do so, including without limitation for any of the following reasons; a) the lowest tender that the City considers otherwise acceptable is higher than the funds budgeted or otherwise available for the project; b) the City decides not to proceed with the project or to defer the project; c) if only one bid is received, then the tender will be reissued unless a financial analysis indicates that the sole bid represents a good value for the taxpayers ; or d) the City is delayed in obtaining, or is unable to obtain, all approvals or consents it considers necessary, whether required by law or otherwise.
.6 The City of Nanaimo reserves the right to consider and to reject any tender or all tenders
without notice to a Tenderer or Tenderers and without permitting a Tenderer to provide additional information.
.7 In no event will the City of Nanaimo be responsible for a Tenderer’s costs of preparing or
submitting a tender.
ARTICLE 15. AWARD Awards shall be made on tenders that will give the greatest value based on quality, service and price. The Owner will, following receipt of an acceptable tender, issue in writing a Notice of Award to the successful Tenderer. This notice will be given as soon as possible following the closing of tenders and unless otherwise agreed to by the Tenderer, not later than sixty (60) days following the closing of tenders. ARTICLE 16. FORM OF AGREEMENT The form of agreement will be the City’s tender documents, successful Bidder’s Tender Form, Insurance Certificate, Prime Contractor Forms, Worksafe BC Letter of Clearance, Business Licence and other documents the City deems appropriate to be included, all encapsulated with a City of Nanaimo Purchase Order. ARTICLE 17. NO CLAIM FOR COMPENSATION Except as expressly and specifically permitted in these Instructions to Tenderers, no Tenderer shall have any claim for any compensation of any kind whatsoever, as a result of participating in the tender, and by submitting a bid each Tenderer shall be deemed to have agreed that it has no claim. ARTICLE 18. SOLICITATION OF COUNCIL MEMBERS “If a member of Council, or a person who was a member of Council in the previous six months has a direct or indirect interest in the contract, then the Tenderer shall report this to Council in accordance with Section 107 of the Community Charter upon being notified of the award of the contract. The Tenderer warrants and represents that it has not received any information or a record from any Council member or former Council member contrary to Section 108 of the Community Charter.” The successful Tenderer will be required to direct all communications related to their contract through the appropriate staff members. ARTICLE 19. CONSTRUCTION SCHEDULE City of Nanaimo requires that this contract be completed: December 16, 2016. If the asphalt paving is not complete by this time, it will be the Contractor’s responsibility to temporarily restore and maintain surfaces within the roadway with 50mm coldmix asphalt flush with existing surfaces at no additional cost to the City of Nanaimo. ARTICLE 20. WORKSAFE BC PRIME CONTRACTOR 1. The Tenderer is advised the workplace may have the following known operations and/or site
conditions that could present a potential hazard to workers and other persons at the workplace. Other hazards may exist.
- Energized Equipment - Electrical Systems - Overhead and Underground Utilities - Traffic
The successful Tenderer is designated as the Prime Contractor and shall fulfill the Prime Contractor responsibilities as defined in:
a) WorkSafeBC Occupational Health and Safety Regulation, Notice of project, Section 20.2, and Coordination of multiple employer workplaces, Section 20.3; b) Workers Compensation Act (BC), Coordination at multiple-employer workplaces, Section 118, Subsections (1) & (2); and c) General Requirements, Section 3.10 WorkSafe BC.
The Prime Contractor will be required to coordinate the safety of all workers on the work site, including their employees, their subcontractors, City work crews and their contractors, and private utilities, (BC Hydro, Telus, Shaw and FortisBC). Prior to commencing work, the successful Tenderer will be required to provide the City with a WorkSafeBC Notice of Project if required, latest WorkSafeBC Clearance Letter and completed City issued Prime Contractor Forms. ARTICLE 21. LOCAL PREFERENCE Preference shall be given to suppliers located within the Regional District of Nanaimo where quality, service, and price are equivalent. ARTICLE 23. FREEDOM OF INFORMATION AND PROTECTION OF PRIVACY ACT All documents submitted to the City will be held in confidence by the City, subject to the provisions of the Province of British Columbia’s Freedom of Information and Protection of Privacy Act. ARTICLE 24. HOURS OF WORK Tenderer is advised that no work will be permitted outside the hours defined by NOISE CONTROL BYLAW 1994 NO. 4750 which reads: “Erecting, demolishing, constructing, reconstructing, altering or repairing of any building or other structure within the Municipality or the excavating of any street, highway, lane or other land before 7:00 a.m. or after 9:00 p.m., Monday to Saturday and before 9:00 a.m or after 9:00 p.m., on Sundays and Statutory Holidays.”
CITY OF NANAIMO and CANADIAN UNION OF PUBLIC EMPLOYEES, LOCAL 41 COLLECTIVE AGREEMENT ARTICLE 31 MINIMUM RATE OF PAY
Minimum Rate of Pay The Collective Agreement between the City of Nanaimo and Canadian Union of Public Employees, Local 401 says that:
Article 31- Contract or Sub-Contracts Every contract made by the Employer for construction, remodeling, repair, or, demolition of any municipal works or for providing any municipal service or function shall be subject to the following condition:
"Minimum rate of pay for work performed under this Contract or under Sub-contract shall be as classified in the current Agreement between the City of Nanaimo and Canadian Union of Public Employees, Local 401."
Please find below the rates that will apply to this contract. 95% rate is applicable for the first 60 calendar days from the commencement of the work. Full rate from day 61 onwards.
Position Title 95% first 60
days Full Rate
Labourer II $24.19 $25.46 Roads Service Person $29.20 $30.74 Equipment Operator, Asphalt $30.19 $31.78 Traffic Control (Flagger) $16.56
LETTER OF UNDERSTANDING #12 BETWEEN:
CITY OF NANAIMO AND
CANADIAN UNION OF PUBLIC EPLOYEES, LOCAL 401
Re: Contracting Out Issues The City of Nanaimo and CUPE Local 401 agree to the following conditions in order to:
a) provide an interpretation of Article 31, Contracts or Sub Contracts.
1. Where the Union can provide documented evidence to prove to the City's satisfaction that a contractor hired by the City of Nanaimo is not paying wage rates pursuant to Article 31, the City will follow the process outlined in Appendix I.
2. The Parties agree that for the purposes of complying with Article 31, the rate for flagging shall be set at $14.20 {2009 rate) per hour.
3. The City agrees to provide available cost information on contracts to the Union upon request
4. This Agreement will be effective on new contracts awarded after date of signing and on current contracts on which the Union provides evidence of breach of Article 31.
5. This Letter of Agreement forms part of the Collective Agreement and remains in effect in the same manner and to the same extent as any other provision in the Collective Agreement.
6. All issues arising under the grievance and/or issues relating to contracts in effect up to the signing of this Letter shall be deemed to be resolved and, no grievance will be filed in respect of any such issues with the exception of current contracts where either Party discovers that a contractor is contravening Article 31.
7. In the event a dispute occurs between the Parties regarding the implementation of this Agreement, either Party may refer the matter to or a-mutually agreed arbitrator on an expedited basis for resolution.
Appendix I DEFINITIONS "Work performed" refers to the current classifications contained in the Parties' Collective Agreement and not directly connected to the job which is contracted. PROCESS 1. Each contract assigned to a contractor by the City of Nanaimo will contain terms:
(a) Requiring that the contractor adhere to the provisions of Article 31 of the
Collective Agreement. Current classified rates will be included. (b) Specifying that failure to adhere to the provisions is a breach of the
contract and may give rise to termination of the contract. (c) Entitling the City to copies of information showing the wage rates paid to its
employees. (The City will provide copies to the Union if requested.) 2. In the event the City has concerns that a contractor is in violation of Article 31,
the following shall apply: (a) The City shall immediately inform the contractor of its concerns and require
the contractor to comply. (b) The City shall follow up contact and if violation still exists within thirty (30)
days provide written request for compliance. (c) If violation continues, the City shall provide second request within a further thirty
(30) days and demand compliance or contract forfeiture may occur. (d) If violation continues, the City shall provide final request within a further
thirty (30) days and may give two weeks notice for failure to comply with provision of contract.
(e) The City may terminate the contract and/or withhold funds and/or require the contractor to submit appropriate monies to rectify the breach of contract.
(f) If the City does not require forfeiture, such decision must be for bona fide operational or legal reasons.
(g) Notwithstanding the above, the City may proceed to (d) or (e) directly.
TENDER FORM No. 1819 2016 Sidewalk and Traffic Circle Project
Page 1 of 2 Date: ________________________________________________________________________ Submitted by: _________________________________________________________________ Address: Telephone:__________________________________ Email: ____________________________ To: City of Nanaimo C/o Purchasing Department 2020 Labieux Road Nanaimo, BC V9RT 6J9 Having examined the Project site, and having carefully examined all of the tender documents including Addenda to issued as supplements thereto, and having examined and complied with Instructions to Bidders, we hereby offer to perform the Work set forth in the aforesaid documents for the Stipulated Contract Price, which includes any applicable taxes in force at this date. Unit Pricing – As per the attached Tender Form Schedule of Quantities.
NOTES: .1 Lump Sum Prices include the Contractor’s Labour, material, equipment, material costs,
overhead and profit, all taxes and duties, and shall represent the cost to the Owner of such charges (does not include GST).
.2 We have reviewed the work schedule requirements and can accomplish all of the work by
December 16, 2016 and understand that time is of the essence. .3 We understand the City reserves the right to adjust the quantity of work to match the
budget available. This may mean increasing, decreasing or deleting items from the scope of the work prior to awarding the contract.
1.0 ACCEPTANCE .1 This Bid is open to acceptance for a period of sixty (60) days from the date of bid
closing.
.2 Submission of this Bid implies acceptance of the existing conditions at the site. .3 We understand that the lowest or any Bid will not necessarily be accepted. The
Owner may also elect not to proceed with the Project. .4 The Owner reserves the right to waive minor defects or irregularities in the bid. .5 We agree to adhere to the Minimum Rate of Pay provisions. .6 We agree to be designated as the Prime Contractor for this project per WorkSafe
BC OH&S Regulations and have the necessary qualifications and are willing to accept the responsibilities as Prime Contractor for the project.
Company: __________________________________________________________________ Signature: __________________________________________________________________ (Authorized Officer) Printed: __________________________________________________________________ (Authorized Officer)
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORM
VANCOUVER AND TOWNSITE
SCHEDULE OF QUANTITIES AND PRICES
Item Description Est.Qty. Units Unit Price Total
Section 2 General Conditions
2.1 Location of Works - Project Layout (2.1) (not to exceed 5% of the total contract price) 1 lump sum
Total Section 2
Section 3 General Requirements
3.1 Locate Existing Structures (Section 3.70)
a) Catch Basin Lead Tie-In Location 2 ea.
3.2 Control of Traffic (Section of 3.73) 1 lump sum
3.3 Removal of Existing Structures (Section 3.75)
a) Existing Catch Basin 2 ea.
b) Existing Catch Basin Lead 5 m
Total Section 3
Section 4 Trench Excavation, Bedding and Backfill
4.1 Import Granular Fill (trench backfill) (Section 4.73) 25 t
4.2 Surface Restoration (Section 4.76)a) 75mm Asphalt 5 m
2
Total Section 4
Section 7 Storm Sewer System
7.1 Piping 200mm PVC SDR-35 (Section 7.70) 10 m
7.2 Connect to Existing Piping (Section 7.72)
a) 200mm PVC x 200mm Conc 1 ea.
b) 200mm PVC & 150mm Conc 1 ea.
7.3 Catch Basins (Section 7.74)
a) ST-1 Type 1 2 ea.
7.4 Service Connection Inspection Assembly (Section 7.81)
a) 150mm Storm 1 ea.
b) 150mm Sanitary 1 ea.
Total Section 7
Page 1 of 7 Tenderer's Initials _________
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORM
VANCOUVER AND TOWNSITE
SCHEDULE OF QUANTITIES AND PRICES
Item Description Est.Qty. Units Unit Price Total
Section 8 Curbs, Sidewalks and Walkways
8.1 Curbs (Section 8.70)
a) CS-2 60 m
8.2 Sidewalk (Section 8.71)
a) 100mm Thick Concrete 65 m2
b) Bus Ramp Sidewalk c/w welded wire mesh as per detailon DWG #21570 35 m
2
8.3 Cutting and Removal of Existing Sidewalk (Section 8.72)
a) Cutting - concrete 5 m
b) Removal - concrete 45 m2
Total Section 8
Section 9 Streets, Traffic Signs and Markings
9.1 Stripping and Common Excavation (assume 0.3m depth) (Section 9.70) 30 m
3
9.2 Subgrade Preparation (Section 9.75) 100 m2
9.3 Base Course (Section 9.77) 70 t
Total Section 9
Section 12 Asphaltic Concrete Paving
12.1 Cutting of Existing Asphalt (Section 12.70) 74 m
12.2 Removal of Existing Asphal(Section 12.71) 110 m2
Total Section 12
Page 2 of 7 Tenderer's Initials _________
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORM
VANCOUVER AND TOWNSITE
SCHEDULE OF QUANTITIES AND PRICES
Item Description Est.Qty. Units Unit Price Total
TOTAL SECTION 2 $
TOTAL SECTION 3 $
TOTAL SECTION 4 $
TOTAL SECTION 7 $
TOTAL SECTION 8 $
TOTAL SECTION 9 $
TOTAL SECTION 12 $
SUB-TOTAL $
GST $
TOTAL - VANCOUVER AND TOWNSITE $
Name of Company
Signature of Signing Officer
Date
SUMMARY - Vancouver Ave. and Townsite Road
Page 3 of 7 Tenderer's Initials _________
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORM
JINGLE POT, SECOND, AND WENTWORTH
SCHEDULE OF QUANTITIES AND PRICES
Item Description Est.Qty. Units Unit Price Total
Section 2 General Conditions
2.1 Location of Works - Project Layout (Section 2.1)
(not to exceed 5% of the total contract price) 1 lump sum
Total Section 2
Section 3 General Requirements
3.1 Location of Existing Structures (Section 3.70)
a) City Fiber Optic 2 ea
3.2 Clearing and Grubbing 0+930 to 0+970 (Section 3.71) 1 lump sum
3.3 Control of Public Traffic
(Section 3.73) 1 lump sum
3.4 Removal of Existing Structures (Section 3.75)
a) Stop Signs 4 ea.
3.5 Relocate Existing Sign per City Standard Dwg. R-S1 2 ea
Total Section 3
Section 5 Water Distribution System
5.1 Relocate Existing Hydrant and Extend Lead (Section 5.75) 1 ea
Total Section 5
Section 8 Curbs, Sidewalks and Walkways
8.1 Curbs (Section 8.70)
a) CS-4A 150 m
8.2 Sidewalk (Section 8.71)
a) 100mm Thick Concrete 70 m2
b) 50mm Asphalt 300 m2
c) 150mm Thick Concrete 20 m2
d) Concrete Apron as per detail
on DWG # 21527 48 m2
Page 4 of 7 Tenderer's Initials _________
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORM
JINGLE POT, SECOND, AND WENTWORTH
SCHEDULE OF QUANTITIES AND PRICES
Item Description Est.Qty. Units Unit Price Total
8.3 Cutting and Removal of Existing Asphalt and Concrete
(Section 8.72)
a) Cutting Asphalt 90 m
b) Cutting Conrete 10 m
c) Remove Asphalt 185 m2
d) Remove Concrete 15 m2
8.4 Cutting and Removal of Existing Curb and Gutter
(Section 8.73)
a) Concrete 110 m
8.5 Handrails (Section 8.75)
a) ST-12 Black Powder Coated
Without Chainlink 37 m
8.6 Catch Basins and Manholes (Section 8.58)
a) Raise Manholes 2 ea.
b) Raise Monument Casting 1 ea.
Total Section 8
Section 9 Streets, Traffic Signs and Markings
9.1 Stripping and Common Excavation (Section 9.70) 175 m3
9.2 Imported Granular Fill (Section 9.74)
a) MOTI Bridge End Fill 400 t
9.3 Subgrade Preparation (Section 9.75) 430 m2
9.4 Base Course (Section 9.77) 375 t
Total Section 9
Section 12 Asphaltic Concrete Paving
12.1 Asphalt (Section 12.74)
a) 50mm 30 m2
b) 75mm 20 m2
Total Section 12
Page 5 of 7 Tenderer's Initials _________
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORM
JINGLE POT, SECOND, AND WENTWORTH
SCHEDULE OF QUANTITIES AND PRICES
Item Description Est.Qty. Units Unit Price Total
TOTAL SECTION 2 $
TOTAL SECTION 3 $
TOTAL SECTION 5 $
TOTAL SECTION 8 $
TOTAL SECTION 9 $
TOTAL SECTION 12 $
SUB-TOTAL $
GST $
TOTAL - JINGLE POT, SECOND, AND WENTWORTH $
Name of Company
Signature of Signing Officer
Date
SUMMARY - Jingle Pot Road, Second Street, and Wentworth Street
Page 6 of 7 Tenderer's Initials _________
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORM
SCHEDULE OF QUANTITIES AND PRICES
TOTAL - VANCOUVER AND TOWNSITE $
TOTAL - JINGLE POT, SECOND, AND WENTWORTH $
TOTAL CONTRACT $
Name of Company
Signature of Signing Officer
Date
SUMMARY - TENDER 1819
Page 7 of 7 Tenderer's Initials _________
GENERAL TERMS AND CONDITIONS Insurance & Indemnity The Contractor will indemnify and save harmless the Owner, its employees and agents, from and against any and all losses, claims, damages, actions, causes of action, costs and expenses that the Owner may sustain, incur, suffer or be put to at any time either before or after the expiration or termination of this Contract, where the same or any of them are based upon, arise out of or occur, directly or indirectly, by reason of any act or omission of the Contractor or of any agent, employee, officer, director or subcontractor of the Contractor pursuant to this Contract, excepting always liability arising out of the independent negligent acts of the owner.
1. The Contractor shall, without limiting its obligations or liabilities herein and at its own expense, provide and maintain the following insurances with insurers licensed in British Columbia and in forms and amounts acceptable to the Owner:
a. Comprehensive General Liability in an amount not less than Two Million Dollars ($2,000,000.00) inclusive per occurrence against bodily injury and property damage. The Owner is to be added as an additional insured under this policy. Such insurance shall include, but not be limited to:
.01 Products or Completed Operations Liability;
.02 Owner’s and Contractor’s Protective Liability;
.03 Blanket Written Contractual Liability;
.04 Contingent employer’s Liability;
.05 Personal Injury Liability;
.06 Non-Owned Automobile Liability;
.07 Cross Liability;
.08 Employees as additional Insureds;
.09 Broad Form Property Damage;
.10 Broad Form Completed Operations; and where such further risk exists: .11 Shoring Blasting, Excavating, Underpinning, Demolition, Piledriving and
Caisson Work, Work Below Ground Surface, Tunneling and Grading, as applicable;
.12 Elevator and Hoist Liability; and
.13 Operation of Attached Machinery.
b. Automobile Liability on all owned or leased vehicles in an amount not less than Two Million Dollars ($2,000,000.00)
c. Aircraft and/or Watercraft Liability, where applicable, for all owned or non-owned craft operating or used in the performance of the Work by the Contractor, in an amount not less than Two Million Dollars ($2,000,000.00) per occurrence and including aircraft passenger hazard liability, where applicable.
d. Property insurance which shall cover all property, of every description, to be used in the construction of the Work, against “All Risks” of physical loss or damage, while such property
is being transported to the site, and thereafter throughout erection, installation and testing and such insurance shall be maintained until Substantial Performance of the Work. Such policy of insurance shall extend to protect the interest of the Owner, and shall contain a waiver of subrogation against the Owner.
2. All the foregoing insurance shall be primary and not require the sharing of any loss by any insurer of the Owner.
3. The Contractor shall provide the Owner with evidence of all required insurance prior to the commencement of the Work or services. Such evidence shall be in a form acceptable to the Owner. When requested by the Owner, the Contractor shall provide certified copies of required insurance policies.
4. All required insurance shall be endorsed to provide the Owner with thirty days (30) advance written notice of cancellation or material change.
5. The Contractor hereby waives all rights of recourse against the Owner with regard to damage to the Contractor’s property.
6. The Contractor shall require and ensure that each subcontractor maintain liability insurance comparable to that required above.
7. Unless specified otherwise, the duration of each insurance policy shall be from the date of commencement of the Work until the date of the final certificate for payment.
Business License The successful Contractor must have a current City of Nanaimo Business License or Inter-Community License prior to the commencement of any work. WorkSafe BC The successful Contractor shall provide WorkSafeBC coverage for all workers on their payroll and provide the City with a satisfactory Letter of Clearance prior to the commencement of any work. Competency and Qualifications The successful contractor must have the necessary competence, experience, qualified personnel and equipment to carry out all aspects of the work of the Contract. The successful Contractor will employ properly licensed, trained and unimpaired workers throughout the duration of the contract. Failure to do so could result in termination. Copies of certifications may be requested by the City. Smoking is permitted in designated areas. Alcohol and Drug consumption is not permitted on City property Cancellation The entire process is subject to final award approval by the City of Nanaimo whom retains the ability to cancel the process for any reason whatsoever without any compensation to anyone.
Governing Law This agreement shall be governed by the laws of the Province of British Columbia.
Correspondence Both parties shall designate one person from their respective organizations to be primarily responsible for coordinating contractual and financial matters.
Invoicing The Contractor will be solely responsible for invoicing the City ensuring to include the City’s Purchase Order number on all invoices to assure timely payment. All invoices are subject to prior review and approval by the City and approved invoices will be paid on a net 30 day basis unless otherwise negotiated and agreed to in writing. If the City does not approve of the services or part of them which are the subject of the invoice, the City shall advise the Contractor in writing of the reasons for non-approval and the Contractor shall remedy at no additional cost to the City before the City shall be obliged to pay the invoice or any part of it, as the case may be.
Force Majeure (Act of God) Neither party shall be responsible for any delay or failure to perform its obligations under this Agreement where such delay or failure is due to fire, flood, explosion, war, embargo, governmental action, Act of Public Authority, Act of God or to any other cause beyond its control, except labour disruption. In the event Force Majeure occurs, the party who is delayed or fails to perform shall give prompt notice to the other party and shall take all reasonable steps to eliminate the cause. Should the Force Majeure event last longer than 30 calendar days, the City may terminate this Agreement immediately by written notice to the Contractor without further liability, expense, or cost of any kind. Dispute Resolution Where any dispute arises out of or in connection with this agreement, either party may request the other party to appoint senior representatives to meet and attempt to resolve the dispute either by direct negotiations or mediation. Unresolved disputes may be submitted for final resolution by arbitration administered by the British Columbia International Commervial Arbitration Centre under its “Shorter Rules for Domestic Commercial Arbitration” in Vancouver, British Columbia, Canada. Alternatively, the Parties may agree, within 30 days of request by a party for final resolution, to submit the dispute for final resolution by arbitration in another manner. Conflict of Interest The contractor declares that it has no financial interest, directly or indirectly in the business of any third party that would be or be seen to be a conflict of interest in carrying out the services. It warrants that neither it nor any of its officers or directors, or any employee with authority to bind the Bidder, has any financial or personal relationship or affiliation with any elected official or employee of the City or their immediate families which might in any way be seen by the City to create a conflict.
Independent Contractor The Contractor shall be, and in all respects be deemed to be, an independent contractor and nothing in this Agreement shall be construed to mean that the Contractor is an employee of the City or that any agency, joint venture or partnership exists between the Contractor and the City. The Contractor shall be responsible for providing own employment insurance, WorkSafe BC coverage, business licence, income tax remittance and complying with any other applicable laws and regulations applicable to an independent contractor. Irrevocability
Submissions will be irrevocable and remain open for acceptance by the City for a period of sixty (60) calendar days, after the closing time.
Permits, Regulations and Building Codes If applicable, the successful Contractor shall at his own expense, obtain all applicable permits, certificates and licences required by law for the conduct of the work and shall comply with all Federal, Provincial and City Laws, Regulations, Building Codes and Ordinances affecting the execution of the work unless indicated otherwise. The Contractor will be responsible for the coordination of all inspections required under the permits. Site Maintenance and Clean up The working area shall be maintained in an orderly manner and shall not be encumbered with equipment, materials or debris. Bankruptcy The Owner reserves the right to stop the work, or, terminate the contract if the contractor commits an act of bankruptcy, threatens to commit an act of bankruptcy. Collusion The bidder shall not engage in collusion of any sort and shall ensure that no person or other legal entity, other than the bidder has an interest in the bidder’s submission and prepare the submission without any knowledge of, comparison of figures with, or arrangement with any other person or firm preparing a Submission for the same work.
SECTION 2 - GENERAL CONDITIONS
MEASUREMENT AND PAYMENT
________________________ Section 2 - Measurement & Payment
Page 1 of 2 DATED: 2016
MEASUREMENT AND PAYMENT
Location or Works – Project Layout 2.1
SECTION 2 - GENERAL CONDITIONS
MEASUREMENT AND PAYMENT
________________________ Section 2 - Measurement & Payment
Page 2 of 2 DATED: 2016
2.1 LOCATION OF WORKS – PROJECT LAYOUT
.1 Where location dimensions for the proposed works are not shown on the drawings or digital
file, the locations are intended to be approximate. .2 Unless otherwise specified, the Engineer will provide the contractor with a copy of the digital
drawing file for the Contractor and/or his surveyor to create a point file to be used for layout to perform the construction works.
.3 The Contractor shall perform all layout as required from the digital drawing file and shall be
responsible for all dimensions and elevations determined from the digital information. .4 The Contractor shall satisfy himself, before commencing any work, as to the meaning, intent,
and accuracy of the information in the digital drawing file as it relates to control points, control lines, benchmarks, and the construction drawings.
.5 Should the Contractor discover or suspect any errors in the digital drawing file provided by the
Engineer, he shall at once discontinue the affected work until such errors are investigated by the Engineer and, if necessary, rectified.
.6 The Contractor shall carefully preserve bench marks, reference points and stakes. In case of
willful or careless destruction or disturbance of such markers, he shall be charged with the expense of replacing them and shall be responsible for any mistakes that may be caused by their destruction, loss or disturbance.
.7 In any dispute between the Contractor and the Engineer on the correctness of grades,
locations, elevations of the installations or constructed works, the Contractor shall be responsible for proving by means of cut sheets and undisturbed stakes, that he has made the installation or construction in accordance with the layout provided.
.8 The contractor shall be required to maintain an "as-constructed" drawing set for the project,
with all changes and notes marked in red ink and an “as-constructed” digital survey file. This information shall be available to the Engineer for review on request, and shall be submitted to the Engineer prior to issuing the Notice of Acceptance.
.9 Legal survey markers, disturbed or removed by the construction operation that existed at a horizontal distance of 1.0 m or more from the maximum allowable trench width as shown on the standard drawings, shall be replaced at the Contractor’s expense. If it is necessary to remove or disturb existing legal survey markers that are within the above limits, the Engineer shall be so notified a minimum of three working days before such removal or disturbance and replacement will be at the Owner’s expense.
SECTION 3 - GENERAL REQUIREMENTS
MEASUREMENT AND PAYMENT
________________________ Section 3 - Measurement & Payment
Page 1 of 3 DATED: 2013
MEASUREMENT AND PAYMENT
Existing Structures and Utility Works 3.70
Clearing and Grubbing 3.71
Salvaged Materials 3.72
Control of Public Traffic 3.73
Removal of Existing Culverts 3.74
Removal of Existing Structures 3.75
SECTION 3 - GENERAL REQUIREMENTS
MEASUREMENT AND PAYMENT
________________________ Section 3 - Measurement & Payment
Page 2 of 3 DATED: 2013
3.70 EXISTING STRUCTURES AND UTILITY WORKS
Extra payment will not be made to the Contractor for expense incurred as a result of the presence of
existing structures except as follows:
(a) Location of Existing Structures: Section 3.22.3
Where he is specifically instructed by the Engineer to locate, by excavating, underground
structures for the purpose of establishing line or grade, the Contractor will be paid on the
basis of the payment items shown on the Tender Form.
(b) Relocation of Existing Piping: Section 3.35
Where an existing pipe parallels the centreline of the trench and lies within the allowable
trench width as shown on standard drawing T-1 or T-2, or crosses the trench and intersects
the pipe to be installed and must, in either case, be relocated, the Contractor will, unless
otherwise specified elsewhere herein, be paid on the basis of the payment items shown in
the Tender Form. No payment will be made for delays, standby, or any claims of the
Contractor other than for the actual cost of relocating the existing pipe, and no payment will
be made for tunnelling under or protecting the existing pipe.
(c) Support of Existing Asbestos Cement or Cast Iron Piping Section 3.27
Standard Drawing T-11
Payment for work to support or replace existing asbestos cement or cast iron piping under
which excavation for works crosses shall be made at the price quoted in the Tender Form.
This price shall include supply of materials, excavation, backfilling and all work incidental
thereto.
3.71 CLEARING AND GRUBBING Section 3.52
Payment for clearing and grubbing will be made at the lump sum price shown in the Tender Form.
This price shall include materials, and all work incidental thereto.
3.72 SALVAGED MATERIALS Section 3.23
This item covers the cost of salvage and delivery of salvaged items to the City of Nanaimo Works
Yard on Labieux Road. This work shall be paid for on a per unit basis as shown in the Tender Form.
No payment will be made for items damaged due to the act of removal or delivery.
SECTION 3 - GENERAL REQUIREMENTS
MEASUREMENT AND PAYMENT
________________________ Section 3 - Measurement & Payment
Page 3 of 3 DATED: 2013
3.73 CONTROL OF PUBLIC TRAFFIC Section 3.60, 3.61 and 3.62
Payment will be made as a lump sum as shown in the Tender Form.
3.74 REMOVAL OF EXISTING CULVERTS
Payment for culvert removal will be made at the unit price per linear metre shown in the Tender Form for the various sizes of culverts. Measurement will be made horizontally along the centre line of the existing culverts.
This item covers the removal and disposal of all existing culverts and headwalls designated on the
drawings for removal including backfill of the trench with suitable native material. Where imported
granular fill is required, it shall be paid for at the unit price quoted in the tender form.
3.75 REMOVAL OF EXISTING STRUCTURES Section 3.23
Payment for the removal and disposal of structures, as designated on the drawings, will be made at the unit price shown in the Tender Form.
a) Valve Boxes – This price shall include the removal and disposal of the valve box, filling the valve
stand pipe with pea gravel or non-shrink grout, abandoning valves in place unless otherwise shown on the drawings, and all work incidental thereto.
b) Air Valve – This price shall include the removal and disposal of the air valve, air valve chamber,
casting and lid, all associated piping and fittings, backfill and compaction with suitable native material, and all work incidental thereto..
For these pay items, import granular backfill where required, and surface restoration will be paid separately under the applicable unit rate in the Tender Form.
SECTION 4 - TRENCH EXCAVATION, BEDDING AND BACKFILL
MEASUREMENT AND PAYMENT
____________________________ Section 4 - Trench Excav, Bedding & Backfill
Page 1 of 4 DATED: 2013
MEASUREMENT AND PAYMENTS
Authorized Hand Excavation 4.70
Trench Rock Excavation 4.71
Over excavation and Placement of Base Gravel Material 4.72
Imported Granular Fill 4.73
Concrete and Controlled Density Fill 4.74
Trench Dams 4.75
Surface Restoration 4.76 Asbestos Cement Pipe Removal 4.77
SECTION 4 - TRENCH EXCAVATION, BEDDING AND BACKFILL
MEASUREMENT AND PAYMENT
____________________________ Section 4 - Trench Excav, Bedding & Backfill
Page 2 of 4 DATED: 2013
4.70 AUTHORIZED HAND EXCAVATION Section 4.09
Payment for authorized hand excavation will be made at the unit price per linear metre if shown in the
Tender Form and will be based on the trench depth. This price shall include supply of materials,
hand excavation, hand backfilling, and all work incidental thereto.
4.71 TRENCH ROCK EXCAVATION Section 4.03.3
Payment for trench rock excavation will be made as shown in the Tender Form:
(a) By Volume Measurement:
Payment will be made for excavation of single boulders, pieces of concrete, or masonry
having individual volumes exceeding one cubic metre in volume.
Measurement for trench rock excavation will be calculated based on:
1. The depth from the top of the rock surface to 150 mm below the bottom of the pipe
barrel.
2. The maximum allowable trench dimensions as per T-1, or for common trenches, as
per T-2.
3. The length measured horizontally along the centre line of the trench.
4. Cross sectional measurements will be made at 3 m intervals or as required.
5. In the event that the average rock width is less than 600 mm in any 3 m interval,
payment will be based on a 600 mm minimum rock width.
This price shall include excavation, disposal of rock, and all work incidental thereto.
(b) By Linear Metre:
The City will provide a rock profile along the trench centreline showing rock elevations at 10
m intervals.
Payment will be made per linear metre of trench where rock is excavated irrespective of
depth. This price shall include excavation, disposal of rock, and all work incidental thereto.
(c) By hourly rates:
Rates for personnel and equipment shall be in accordance to Section 2 – Article 40 Force
Account Work. The contractor shall schedule his workforce in such a manner that the Trench
Rock Excavation will not interfere substantially with progress of other work. Only personnel
and equipment required for the excavation and disposal of the rock will be paid under force
account rates. No payment will be made for delays or standby time.
SECTION 4 - TRENCH EXCAVATION, BEDDING AND BACKFILL
MEASUREMENT AND PAYMENT
____________________________ Section 4 - Trench Excav, Bedding & Backfill
Page 3 of 4 DATED: 2013
4.72 OVEREXCAVATION AND PLACEMENT OF BASE GRAVEL MATERIAL Section 4.03.3 (d) (e) and 4.14
Payment for authorized overexcavation and placement of base gravel material or other material
specified will be made at the unit price per tonne of material placed as shown in the Tender Form.
This price shall include supply of materials, overexcavation and disposal of the unsuitable material,
placement and compaction of the specified base gravel material, special bracing and sheeting as may
be required, and all work incidental thereto. Payment for this work will only be made when, in the
opinion of the Engineer, it is necessitated by the natural existence of unsatisfactory soil conditions.
No payment will be made for unauthorized over excavation which has resulted from acts, neglects, or
delays of the Contractor.
4.73 IMPORTED GRANULAR FILL Section 4.20
Payment for imported granular fill will be made at the price per cubic metre or tonne as shown in the
tender form (conversion of tonnes to cubic metres compacted will be 2.43 tonnes/cubic meter). This
price shall include supplying, loading, hauling, placing, compacting imported granular material,
disposal of excavated material and all work incidental thereto. Payment by weight will be based on
weigh certificates for material actually incorporated into the work unless otherwise approved by the
Engineer.
Tender quantities are based on the allowable trench width limits as shown on Standard Drawings T-1
or T-2, with allowances for site soil conditions. Placement of import granular fill beyond these limits
will be at the Contractor’s expense where the Contractor employs methods that excavate beyond
these limits without prior authorization from the Engineer.
4.74 CONCRETE AND CONTROLLED DENSITY FILL
(a) Concrete Fill Section 4.21 - Standard Drawing T-5 and T-6
(b) Controlled Density Fill - Section 4.24 - Standard Drawing T-3
Payment for concrete or controlled density fill for pipe base, encasement, or backfill in the trench will
be made at the unit price per cubic metre shown in the Tender Form. Measurement will be based on
the design dimensions of the concrete placed. This price shall include supply of materials, concrete
work, form work, curing and protection and all work incidental thereto.
4.75 TRENCH DAMS Section 4.18 Standard Drawing T-8
Payment for trench dams will be made at the unit price per trench dam shown in the Tender Form.
This price shall include supply of materials, installation and all work incidental thereto.
SECTION 4 - TRENCH EXCAVATION, BEDDING AND BACKFILL
MEASUREMENT AND PAYMENT
____________________________ Section 4 - Trench Excav, Bedding & Backfill
Page 4 of 4 DATED: 2013
4.76 SURFACE RESTORATION Section 4.27, 4.28 & 4.29
Payment for surface restoration will be made at the price per square metre as shown on the
Tender Form for the various types of surface restoration.
a) For surface restoration of untraveled areas, (boulevards, rights-of-way and private
property), price shall include all labour, equipment and materials necessary to restore
untraveled areas, to a condition equal to or better than existed prior to construction and in
accordance with the specifications and drawings.
b) For surface restoration of traveled areas, (roads, shoulders, driveways, sidewalks, curbs
and walkways), price shall include all labour, equipment and materials necessary to
restore the traveled areas, to a condition equal to or better than existed prior to
construction and in accordance with the specifications and drawings. This price shall
include surface cutting and removal, supply and installation of gravel materials,
and restoration of the travelled surface.
c) For temporary surface restoration of traveled areas, (roads, driveways, sidewalks, curbs
and walkways), price shall include all labour, equipment and materials necessary to
restore and maintain the traveled surface, as directed by the Engineer, using the
materials as shown on the Tender Form.
Tender quantities are based on the allowable trench width limits as shown on Standard Drawings
T-1 or T-2. Surface restoration beyond these limits will be at the Contractor’s expense where the
Contractor employs methods that damage areas beyond these limits without prior authorization
from the Engineer.
4.77 ASBESTOS CEMENT PIPE REMOVAL
Payment for the handling, cutting and removal of asbestos cement pipe will be made at the unit price per linear metre of pipe removed as shown in the Tender Form. This price shall include all labour, equipment and materials required for the proper removal and disposal of asbestos cement pipe as required by the WorkSafeBC Regulations.
SECTION 5 - WATER DISTRIBUTION SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 5 - Water Distribution System
Page 1 of 5 DATED: 2013
MEASUREMENT AND PAYMENT
Water Main Pipe 5.70
Water Main Fittings 5.71
Flange Adaptors and Joint Restraints 5.72
Water Main Gate Valves 5.73
Water Main Valve Markers 5.74
Hydrants Assemblies 5.75
Hydrant Access Crossing 5.76
Flushouts 5.77
Air Valves and Fittings 5.78
Floor Drain Assemblies 5.79
Connection to Existing Main Piping 5.80
Connections to Existing Services 5.80A
Service Connection Pipe 5.81
Corporation Stops and Saddles 5.82
Curb Stops 5.83
Meter Service Boxes, Box Extensions, and Lids 5.84
Touch Read Meters 5.85
Meter Chambers (Section 5.58) Booster Pump Stations (Section 5.59)
and Pressure Reducing Stations (Section 5.60) 5.86
SECTION 5 - WATER DISTRIBUTION SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 5 - Water Distribution System
Page 2 of 5 DATED: 2013
The contractor will note that the tendered price for all items specified in this section will include but not be
limited to the following: Please refer to Section 4 – Trench Excavation, Bedding and Backfill for further
clarification of these items.
(a) materials
(b) excavation
(c) dewatering
(d) bracing & sheeting
(e) bedding
(f) pipe installation
(g) backfill with native material
(h) maintenance
The Contractor will note that payment for surface restoration and asphalt removal is paid in accordance
with Section 4.76.
5.70 PIPE Section 5.43
Payment for water main pipe will be made at the unit price per linear metre shown in the Tender
Form for the various sizes and class of pipe. Measurement will be made horizontally along the
centreline of the installed pipe including fittings. This price shall include materials, excavation,
dewatering, bracing & sheeting, bedding, pipe installation, backfill with native material, and
maintenance, test points and testing as specified, and all work incidental thereto except those
items for which payment is specified additional to that for piping.
5.71 FITTINGS Section 5.48
Payment for fittings will be made at the unit price per fitting shown in the Tender Form. This price
shall include supply of materials, installation of the fitting, thrust blocking, and all work incidental
thereto. Payment will be in addition to that of 5.70.
5.72 FLANGE ADAPTORS AND JOINT RESTRAINTS Section 5.47
Where noted on the drawings or specifically requested by the Engineer, payment for flange
adaptors and joint restraints shall be made at the unit prices shown in the Tender Form. This
price shall include supply of materials, bolts, installation, and all work incidental thereto. Payment
will be in addition to that of 5.70.
5.73 GATE VALVES Section 5.50 Standard Drawing W-16
Payment for valves will be made at the unit prices shown in the Tender Form for gate valves.
This price shall include supply of materials, installation of the valve and valve box, valve hood,
riser pipe, asphalt apron and thrust blocking if required, and all work incidental thereto. Payment
will be in addition to that of 5.70.
SECTION 5 - WATER DISTRIBUTION SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 5 - Water Distribution System
Page 3 of 5 DATED: 2013
5.74 VALVE MARKERS Section 5.51 Standard Drawing W-9
Payment for water main valve markers will be made at the unit price shown in the Tender Form.
This price shall include supply of materials, excavation, fabrication, painting, installation,
backfilling, and all work incidental thereto. Payment will be in addition to that of 5.70.
5.75 HYDRANT ASSEMBLIES Section 5.52.1, 5.52.2 Standard Drawings W-5
Payment for hydrant assemblies will be made at the unit price shown in the Tender Form as
follows:
a) Hydrant Assemblies
This price shall include supply of materials, installation of the hydrant, hydrant lead,
valve, valve box riser pipe, tie rods, drain rock, and all work incidental thereto. Payment
will be in addition to that of 5.70.
b) Relocating Existing Hydrants
Payment for relocating existing hydrants will be made as per 5.75 a) except work
includes relocating an existing hydrant to the new location as specified on the drawings.
c) Connect to Existing Hydrants
Payment for connecting to existing hydrants will be made as per 5.75 a) except work
includes connecting to an existing hydrant as specified on the drawings.
5.76 HYDRANT ACCESS CROSSING Section 5.52.3 Standard Drawing W-7
Payment for hydrant access crossings will be made at the unit price shown in the Tender Form.
This price shall include all supply of materials, excavation, dewatering, backfill and compaction
and all work incidental thereto. Payment will be in addition to that of 5.70.
5.77 FLUSHOUTS Section 5.53 Standard Drawing W2A - W2B
Flushouts will be paid at the unit price shown in the Tender Form for the specified type of
flushout.
a) For above ground flushouts, this price shall include supply and installation of flushouts in
accordance with the specifications and drawings including all pipes, fittings, valves, valve
boxes, thrust blocking, drain rock, bedding, backfill, cedar post, painting and all work
incidental thereto. Payment for the iron cap or plug will be paid separately under Section
5.71. Payment will be in addition to Section 5.70.
b) For below grade flushouts, this price shall include supply and installation of flushouts in
accordance with the specifications and drawings including all pipes, fittings, valves, valve
boxes, thrust blocking, drain rock, bedding, backfill, concrete barrel, brickwork, frame and
cover, grouting, adjustment to grade, asphalt apron and all work incidental thereto.
Payment for the iron cap or plug will be paid separately under Section 5.71. Payment will
be in addition to Section 5.70.
SECTION 5 - WATER DISTRIBUTION SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 5 - Water Distribution System
Page 4 of 5 DATED: 2013
5.78 AIR VALVES AND FITTINGS Section 5.54 Standard Drawing W4
Air valves and fittings will be paid for at the unit price shown in the Tender Form. This price shall
include excavation, supply of materials, piping, pipe saddle, vent piping, gate valve, air valve,
manhole, manhole frame and cover, adjustment to final grade, asphalt apron and all work
incidental thereto. Payment will be in addition to that of 5.70.
5.79 FLOOR DRAIN ASSEMBLIES Section 5.55
Floor drains will be paid at the unit price shown in the Tender Form for the various types of floor
drain assemblies. Payment for the storm service connection will be paid separately under
Section 7 - Storm Sewers.
a) For perimeter drains, price shall include supply and installation of materials including
pipe, fittings, drain rock, filter cloth and all work incidental thereto.
b) For sump pumps, price shall include supply and installation of materials including sump
drainer assembly, piping, fittings, piping to surface discharge, and all work incidental
thereto.
5.80 CONNECTION TO EXISTING MAIN PIPING Section 5.49
Payment for connections to existing piping will be made at the unit price per connection shown in
the Tender Form. This price shall include supply of couplings, materials, and all work incidental
thereto. Payment will be made in addition to that of 5.70.
5.80A CONNECTIONS TO EXISTING SERVICES Section 5.49
Payment for connections to existing services will be made at the unit price per connection shown
in the Tender Form regardless of existing service depth. This price shall include supply of
materials, and all work incidental thereto.
5.81 SERVICE CONNECTION PIPE Section 5.56
Payment for water service connection pipe will be made at the unit price per linear metre shown
in the Tender Form. Measurement will be made horizontally along the centreline of the installed
pipe from the centre of the main pipe to the curb stop. This price shall include supply of
materials, pipe installation, testing, flushing, chlorination, and all work incidental thereto, except
those items for which payment is specified additional to that for water connection pipe.
5.82 CORPORATION STOPS AND SADDLES Section 5.30.7 and 5.56.2 (e)
Payment for corporation stops and saddles will be made at the unit price shown the Tender Form.
This price shall include supply of materials, drilling and tapping the main pipe, installation, and all
work incidental thereto. Payment will be in addition to that of 5.81.
SECTION 5 - WATER DISTRIBUTION SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 5 - Water Distribution System
Page 5 of 5 DATED: 2013
5.83 CURB STOPS Section 5.56.3
Payment for curb stops will be made at the unit price shown in the Tender Form. This price shall
include supply of materials, installation of curb stop, and all work incidental thereto. No additional
payments will be made for supply and installation of test points. Payment will be in addition to
that of 5.81.
5.84 METER SERVICE BOXES, BOX EXTENSIONS, AND LIDS Section 5.56.4 (b)
Standard Drawings W-10A and W-10B
Payment for meter service boxes, box extension, and touch read lids will be made at the unit
price shown in the Tender Form. This price shall include supply of materials, installation of
service boxes and all work incidental thereto. Payment will be in addition to that of 5.81.
5.85 TOUCH READ METERS Section 5.57.2
Payment for touch read meters will be made at the unit price shown in the Tender Form. This
price shall include completion of meter cards, supply of materials, installation of meter, touch read
sensor and all work incidental thereto. This pay item includes installing new meters in both
existing and new meter boxes. Payment will be made in addition to that of 5.81.
5.86 METER CHAMBERS (Section 5.58) BOOSTER PUMP STATIONS (Section 5.59) and
PRESSURE REDUCING STATIONS (Section 5.60)
Payment for meter chambers, booster pump stations and pressure reducing stations will be made
at the lump sum price in the Tender Form and shall include supply and installation of valves,
chamber, piping and asphalt apron all as detailed on the drawings and all work and materials
incidental to construction of the station.
SECTION 7 - STORM SEWER SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 7 - Storm Sewer System
Eng. Specifications and Standards Page 1 of 5
DATED 2013
MEASUREMENT AND PAYMENT
Pipings and Fittings 7.70
Service Junctions 7.71
Connections to Existing Piping and Appurtenances 7.72
Precast Manholes Sections 7.73
Catchbasins 7.74
Concrete Bases, Frames and Covers 7.75
Drop Structures 7.76
Stubs 7.77
Cleanouts 7.78
Additional Excavation and Backfill 7.79
Storm Sewer Service Connection Piping 7.80
Service Connection Inspection Assembly 7.81
Special Fittings 7.82
Perforated Drains 7.83
Inlet and Outlet Structures 7.84
Rip-Rap 7.85
Drainage Ditch Construction 7.86
Culvert Installation 7.87
Culvert Headwalls 7.88
Manhole and Cleanout Lid Markers 7.89
SECTION 7 - STORM SEWER SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 7 - Storm Sewer System
Eng. Specifications and Standards Page 2 of 5
DATED 2013
The Contractor will note that the Tendered Price for all items specified in this section will include but not be
limited to the following: Please refer to Section 4 - Trench Excavation, Bedding and Backfill for further
clarification of these items.
(a) materials
(b) excavation
(c) dewatering
(d) bracing & sheeting
(e) bedding
(f) pipe installation
(g) backfill with native material
(h) video inspection
(i) maintenance
The Contractor will note that payment for surface restoration and asphalt removal is paid in accordance with
Section 4.76.
7.70 PIPING AND FITTINGS Section 7.42 - 7.46
Payment for piping and fittings will be made at the unit price per linear metre shown in the Tender
Form for the various sizes and class of pipe. Measurement will be made horizontally along the
centreline of the installed pipe, including fittings, from centre-to-centre of manholes or to the end of
the pipe, whichever is applicable. This price shall include materials, excavation, dewatering,
bracing and sheeting, bedding, pipe installation, backfill with native material, video inspection and
maintenance, testing as specified, and all work incidental thereto except those items for which
payment is specified additional to that for gravity sewer pipe.
7.71 SERVICE JUNCTIONS Section 7.48
Payment for service junctions installed in the gravity sewers will be made at the unit price shown in
the Tender Form. This price shall include materials, and placement of the wye and plug or cap as
required.
7.72 CONNECTIONS TO EXISTING PIPING AND APPURTENANCES Section 7.47
(a) Payment for connections to existing main piping will be made at the unit price per proposed
pipe size per connection shown in the Tender Form. This price shall include materials and
all work incidental thereto.
(b) Payment for connections to existing service connections will be made at the unit price per
pipe size per connection shown in the Tender Form. This price shall include materials and
all work incidental thereto.
SECTION 7 - STORM SEWER SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 7 - Storm Sewer System
Eng. Specifications and Standards Page 3 of 5
DATED 2013
7.73 PRECAST MANHOLE SECTIONS Section 7.51 and 7.55
Payment for manholes will be made at the unit price per vertical metre per diameter of manhole
barrel shown in the Tender Form.
Measurement will be made from the lowest channel invert in the manhole to the bottom of the
manhole cover slab. This price shall include materials, installation, grouting, and all work incidental
thereto except those items for which payment is specified additional to that for manholes.
7.74 CATCHBASINS Section 7.60
Payment for catchbasins will be made at the unit price as shown in the Tender Form for the specified
type of catchbasin. This price shall include materials, installation, brickwork, concrete, grouting,
adjustment to grade, asphalt apron and all work incidental thereto.
7.75 CONCRETE BASES, FRAMES AND COVERS Sections 7.49, 7.50, 7.52, 7.53 and 7.54
Payment for concrete bases or tee manholes, cover slabs, and frames and covers will be made at
the unit price shown in the Tender Form. This price shall include materials, installation, brickwork,
concrete channeling and grouting, adjustment to grade, asphalt apron and all work incidental thereto.
Payment will be in addition to that of 7.73 above.
7.76 DROP STRUCTURES Section 7.56
Payment for drop structures on manholes will be made at the unit price per vertical metre of drop
shown in the Tender Form. Measurement will be made between pipe inverts at the top and bottom
of the drop section. This price shall include materials, installation, concrete and all work incidental
thereto. Payment will be in addition to that of 7.73 above.
7.77 STUBS Section 7.57
Payment for stubs in manholes will be made at the unit price per linear metre for the various sizes of
pipe shown in the Tender Form. This price shall include materials, grouting, installation, cap and all
work incidental thereto. Payment will be in addition to that of 7.73 above.
7.78 CLEANOUTS Section 7.58 Standard Drawing S12 - S13
Payment for cleanouts will be made at the unit price shown in the Tender Form for the specified type
of cleanout. This price shall include excavation, materials, installation, concrete base, concrete
barrel, grouting, brickwork, frame and cover, pipe, fittings, adjustment to grade and all work
incidental thereto.
SECTION 7 - STORM SEWER SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 7 - Storm Sewer System
Eng. Specifications and Standards Page 4 of 5
DATED 2013
7.79 ADDITIONAL EXCAVATION AND BACKFILL
Payment will not be made as a separate item for excavation, backfill and work applicable thereto
required at any structure specified in this section. The cost of such work shall be included in the
applicable prices for the various structures shown in the Tender Form.
7.80 STORM SEWER SERVICE CONNECTION PIPING Section 7.61.3
Payment for sewer service connection pipe will be made at the unit price per linear metre shown in
the Tender Form for the various sizes of pipe. Measurement will be made horizontally along the
centreline of the installed pipe from the centre of the gravity sewer main to the terminus of the
service pipe or from the bend fitting in the case of riser service connections.
This price shall include materials, excavation, dewatering, bracing & sheeting, bedding, pipe
installation, backfill with native material, and maintenance, testing as specified, bends, caps and
other fittings, and all work incidental thereto except those items for which payment is specified
additional to that for sewer service connection pipe.
7.81 SERVICE CONNECTION INSPECTION ASSEMBLY Section 7.61.3 (j) Standard Drawing S5
Payment for service connection inspection assemblies will be made at the unit price shown in the
Tender Form. This price shall include installation of pipe, fittings, marker posts, concrete service
box, other materials and all work incidental thereto.
7.82 SPECIAL FITTINGS
Payment for special fittings will be made at the unit price per fitting shown in the Tender Form. This
price shall include materials and placing of the fitting as required. No deduction will be made under
Item 7.70 for the length of fitting.
7.83 PERFORATED DRAINS Section 7.67
Payment for perforated drains will be made at the unit price per linear metre shown in the Tender
Form for various sizes and classes of pipe. Measurement will be made horizontally along the
centreline of the installed pipe. This price shall include materials, excavation, dewatering, bracing &
sheeting, bedding, pipe installation, backfill with drain rock, surround with specified filter fabric, video
inspection and maintenance, and all work incidental thereto.
7.84 INLET AND OUTLET STRUCTURES Section 7.68
Payment for inlet and outlet structures and energy dissipator structures will be made at the unit price
shown in the Tender Form for the various individual structures. This price shall include all concrete,
guard rails, trash racks, grating, other materials, installation and all work incidental thereto.
SECTION 7 - STORM SEWER SYSTEM
MEASUREMENT AND PAYMENT
___________________________ Section 7 - Storm Sewer System
Eng. Specifications and Standards Page 5 of 5
DATED 2013
7.85 RIP-RAP Section 7.69
Payment for rip-rap will be made at the unit price per class per cubic metre as shown in the Tender
Form. This price shall include materials, installation and all work incidental thereto.
7.86 DRAINAGE DITCH CONSTRUCTION Section 7.64
Except in rock, payment for excavation of drainage ditches will be made at the unit price per linear
metre shown in the Tender Form. This price shall include excavating material, placing and
compacting as earth fill or rock fill, disposal of surplus material and all work incidental thereto.
Payment for rock excavation will be made by the method shown in the Tender Form - Sec. 4.71.
7.87 CULVERT INSTALLATION Section 7.65
Payment for culverts will be made at the unit price per linear metre shown in the Tender Form for the
various sizes of culverts. Measurement will be made horizontally along the centreline of the installed
pipe. This price shall include materials, excavation, bedding, pipe installation, backfilling and all work
incidental thereto.
7.88 CULVERT HEADWALLS Section 7.66
Payment for culvert headwalls will be made at the unit price per headwall as shown in the Tender
Form. This price shall include materials, preparation and placing of the headwall and all work
incidental thereto.
7.89 MANHOLE AND CLEANOUT LID MARKERS Section 7.37 Standard Drawing S14
Payment for manhole and cleanout lid markers will be made at the unit price shown in the Tender
Form. This price shall include supply of materials, excavation, fabrication, painting, installation,
backfilling and all work incidental thereto. Payment will be in addition to that of 7.73 and 7.78 above.
SECTION 8 - CURBS AND SIDEWALKS
MEASUREMENT AND PAYMENT
_________________________ Section 8 - Curbs & Sidewalks
Eng. Specifications and Standards Page 1 of 3
DATED: 2013
MEASUREMENT AND PAYMENT
Curbs 8.70
Sidewalks, Miscellaneous Sidewalks and Crossings 8.71
Cutting and Removal of Existing Asphaltic and Concrete Sidewalk Pavement 8.72
Cutting and Removal of Existing Concrete Curb or Curb and Gutter 8.73
Catch Basins and Manholes 8.74
Handrails, Bollards and Barriers 8.75
Stairways 8.76
SECTION 8 - CURBS AND SIDEWALKS
MEASUREMENT AND PAYMENT
_________________________ Section 8 - Curbs & Sidewalks
Eng. Specifications and Standards Page 2 of 3
DATED: 2013
8.70 CURBS Section 8.20 (a)
Payment for curbs will be made at the unit price per linear metre per curb type shown in the
Tender Form. Linear measurement will be made along the centreline of the curbs. This price
shall include materials, base preparation, forming, jointing, reinforcing, finishing, curing, curb
and all work incidental to the completed installation. Payment for granular base materials will
be made at the unit price per material type shown in the Tender Form.
8.71 SIDEWALKS, MISCELLANEOUS SIDEWALKS AND CROSSINGS Section 8.20 (b), 8.56
Payment for sidewalks and crossings will be made at the unit price per square metre shown in
the Tender Form. The price shall include materials, base preparation and all work incidental to
the completed installation. Payment for import fill, excavation, subgrade preparation, granular
sub-base and granular base materials will be made at the unit price for material type shown in
Section 9 of the Tender Form.
8.72 CUTTING AND REMOVAL OF EXISTING ASPHALTIC AND CONCRETE SIDEWALK
PAVEMENT Section 8.42
(a) Payment for cutting of existing asphaltic and concrete sidewalk pavement will be made
at the unit price per linear metre of sidewalk cut, regardless of thickness, shown in the
Tender Form.
(b) Payment for removal of existing asphaltic and concrete sidewalk pavement will be
made at the unit price per square metre of pavement and sidewalk removed, regardless
of thickness, shown in the Tender Form. This price shall include loading, hauling, and
disposal of all unwanted material.
8.73 CUTTING AND REMOVAL OF EXISTING CONCRETE CURB OR CURB AND GUTTER
Section 8.42
Payment for cutting and removal of existing concrete curb or curb and gutter will be made at the
unit price per lineal metre of curb or curb and gutter removed, regardless of thickness,
measured along the curb face as shown in the Tender Form.
This price shall include cutting, loading, hauling and disposal of all unwanted material.
8.74 CATCH BASINS AND MANHOLES Section 8.58
Payment for adjusting frames on existing catch basins, manholes, and other structures will be
made at the unit price per item shown in the Tender Form. No additional payment will be made
for adjusting catchbasins, manholes, and other structures installed in this contract.
SECTION 8 - CURBS AND SIDEWALKS
MEASUREMENT AND PAYMENT
_________________________ Section 8 - Curbs & Sidewalks
Eng. Specifications and Standards Page 3 of 3
DATED: 2013
8.75 HANDRAILS, BOLLARDS AND BARRIERS Section 8.62 Drawing Nos. CS-11, CS-12, CS-14, CS-15, CS-17, CS-18, CS-19
Payment for handrails, bollards and barriers will be made at the unit price shown in the Tender Form. This price shall include all labour, equipment, materials, for the supply, installation and all work incidental thereto.
8.76 STAIRWAYS Section 8.12 Drawing CS-16
Payment for stairways will be made at the unit price shown in the Tender Form. The price shall include materials, base preparation and all work incidental to the completed installation. Payment for import fill, excavation, subgrade preparation, and granular base materials will be made at the unit price for material type shown in Section 9 of the Tender Form.
SECTION 9 - STREETS
MEASUREMENT AND PAYMENT
__________________________ Section 9 - Street
Eng. Specification and Standards Page 1 of 4
DATED: 2013
MEASUREMENT AND PAYMENT
Stripping and Common Excavation 9.70
Rock Excavation 9.71
Authorized Overexcavation 9.72
Imported Earth Fill 9.73
Imported Granular Fill 9.74
Sub-Grade Preparation 9.75
Sub-Base 9.76
Base Course 9.77
Borrow Pits, Crushing and Stockpiling 9.78
Ditches (N/A) 9.79
Street Name and Traffic Signs 9.80 Street Markings 9.81
SECTION 9 - STREETS
MEASUREMENT AND PAYMENT
__________________________ Section 9 - Street
Eng. Specification and Standards Page 2 of 4
DATED: 2013
9.70 STRIPPING AND COMMON EXCAVATION Section 9.44 and 9.45
Payment for stripping and common excavation will be made at the unit price per cubic metre shown
in the Tender Form. Excavated volume will be computed as the difference between the original
cross sections and the subgrade cross section using the average end area method. Cross sections
will be taken every 20 m along the centreline, or at such lesser interval as the Engineer may deem
necessary. This price shall include excavating material, placing and compacting as earth fill or rock
fill, disposal of surplus material and all work incidental thereto.
9.71 ROCK EXCAVATION Section 9.46
Payment for rock excavation will be made as shown in the Tender Form.
a) By Volume Measurement: Payment will be made for excavation of single boulders exceeding one metre in volume. Where solid rock is excavated, the volume of rock for payment will be calculated on the basis of the average end area method measured at 5 metre intervals along the grade to the design subgrade. This price shall include excavation, disposal of unsuitable material and grading of subgrade. No additional payment will be made for backfill material required to achieve subgrade elevations due to overbreak.
b) By Hourly Rates: Rates for personnel and equipment will be as listed in the Tender Form
for force account work. The Contractor shall schedule the work in such a manner that it will not interfere substantially with progress of other work. No allowance will be made for standby time.
9.72 AUTHORIZED OVEREXCAVATION Section 9.47
Payment for authorized over-excavation and placement of import material will be made:
(a) At the applicable unit rates for common excavation and import materials, as shown on the
Tender Form, when the authorized over-excavation occurs in conjunction with the
Contractor’s common excavation operation.
(b) At the unit price per tonne of import material placed, as shown in the Tender Form for
authorized over-excavation, when the authorized over-excavation occurs independent of the
Contractor’s common excavation operation. This price shall include over-excavation,
disposal of unsuitable material, supply and placement and compaction of specified imported
material, and all work incidental thereto.
Payment for this work will only be made when, in the opinion of the Engineer, it is necessitated by
the natural existence of unsatisfactory soil conditions. No payment will be made for unauthorized
over-excavation which has resulted from acts, neglects or delays of the Contractor.
SECTION 9 - STREETS
MEASUREMENT AND PAYMENT
__________________________ Section 9 - Street
Eng. Specification and Standards Page 3 of 4
DATED: 2013
9.73 IMPORTED EARTH FILL Section 9.27A
Payment for imported earth fill will be made at the unit price per cubic metre or tonne shown in the
Tender Form. This price shall include borrow pit development and restoration, materials,
excavation, hauling, placing and compacting as earth fill, disposal of surplus or unsuitable material
from the borrow pit and all work incidental thereto. Payment by cubic metre will be based on the
volume used on the construction between the existing ground after stripping of topsoil and
unsuitable material and the final cross sections of the fill area. Cross sections of the fill area will be
taken every 15 metres or at such lesser interval as the Engineer may deem necessary.
9.74 IMPORTED GRANULAR FILL See Section 9.28A
Payment for import granular fill will be made at the unit price per tonne as shown in the Tender
Form. This price shall include supply, placement and compaction, and all work incidental thereto.
Payment by weight will be based on weigh certificates for material actually incorporated into the
work unless otherwise approved by Engineer.
9.75 SUBGRADE PREPARATION Section 9.50
Payment for the subgrade preparation will be made at the unit price per square metre shown in the
Tender Form. The area will be computed using the nominal design width of the finished subgrade
and the length measured horizontally along the centreline of the finished roadway, with due
allowance made for increased areas at intersections. This price shall include scarifying, windrowing,
watering and dewatering, shaping, compacting, proof rolling and all work incidental thereto.
Payment will not be made in areas where an earth or rock fill in excess of 150 mm has been placed.
No additional payment will be made for reworking the subgrade because of damage from weather
conditions.
9.76 SUBBASE Section 9.54
Payment for subbase will be made at the unit price per tonne shown in the Tender Form. This price
shall include materials, materials handling, placing, watering, shaping, compacting, and all work
incidental thereto. Payment by weight will be based on weigh certificates for material actually
incorporated into the work unless otherwise approved by Engineer
9.77 BASE COURSE Section 9.54
Payment for base course will be made at the unit price per tonne shown in the Tender Form. This
price shall include materials, materials handling, placing, watering, shaping, compacting, and all
work incidental thereto. Payment by weight will be based on weigh certificates for material actually
incorporated into the work unless otherwise approved by Engineer.
SECTION 9 - STREETS
MEASUREMENT AND PAYMENT
__________________________ Section 9 - Street
Eng. Specification and Standards Page 4 of 4
DATED: 2013
9.78 BORROW PITS, CRUSHING AND STOCKPILING Section 9.40 and 9.41
No payment will be made for acquisition, royalties, clearing and grubbing, stripping, access, crushing
or any other costs incurred in developing or operating borrow pits. Related costs for acquisition,
handling and stockpiling of borrow material shall be included in the applicable tendered prices.
9.79 DITCHES N/A
No separate payment will be made for excavation of drainage ditches unless otherwise shown in the
Tender Form. Material excavated will be classified as common excavation, except in rock, and
payment made in accordance with 9.70 except rock payment shall be made in accordance with 9.71.
9.80 STREET NAME AND TRAFFIC SIGNS Section 9.61
Payment for street name and traffic signs will be made at the unit price per sign shown in the Tender
Form for the various signs. This price shall include all materials, erection of the sign post and sign
and all work incidental thereto.
9.81 STREET MARKINGS Section 9.62
Payment for street markings will be made as a lump sum as shown in the Tender Form. These
prices will include all materials, premarking, preparation, application and all work incidental thereto.
SECTION 12 - ASPHALTIC CONCRETE PAVING
MEASUREMENT AND PAYMENT
__________________________ Section 12 - Asphaltic Concrete Paving
Eng. Specification and Standards Page 1 of 2
DATED: 2013
MEASUREMENT AND PAYMENT
Cutting of Existing Asphaltic Concrete Pavement 12.70
Removal of Existing Pavement 12.71
Adjustment of Services 12.72
Tack Coat 12.73
Asphaltic Concrete 12.74
SECTION 12 - ASPHALTIC CONCRETE PAVING
MEASUREMENT AND PAYMENT
__________________________ Section 12 - Asphaltic Concrete Paving
Eng. Specification and Standards Page 2 of 2
DATED: 2013
12.70 CUTTING OF EXISTING ASPHALTIC CONCRETE PAVEMENT Section 12.42
Payment for cutting of existing asphaltic concrete pavement will be made at the unit price per
linear metre of cut shown in the Tender Form, regardless of pavement thickness. This price
shall include cutting and all work incidental thereto.
No payment will be made for cutting of existing pavement except where a neat vertical edge is
required for paving operations. No payment will be made where cutting has been necessitated
by the Contractor's operations.
12.71 REMOVAL OF EXISTING PAVEMENT Section 12.42
Payment for removal of existing pavement as specified in the Tender Form will be made at the
unit price per square metre shown in the Tender Form for pavement removed, regardless of
thickness. Payment will be based on the measured area of the pavement designated for
removal. (This price shall include ripping, grinding, loading, hauling, disposal and all work
incidental to the removal of asphaltic concrete pavement.)
No payment will be made where removal of existing asphaltic concrete pavement is included in
common excavation or has been necessitated by the Contractor's operations.
12.72 ADJUSTMENT OF SERVICES Section 12.43
Payment for the adjustment of existing manholes, catchbasins, valve boxes and other structures
within the area to be paved will be made at the unit prices shown in the Tender Form. These
prices shall include materials and all work incidental thereto.
12.73 TACK COAT Section 12.45
Payment for tack coat will be made at the unit price per square metre shown in the Tender Form.
Payment will be based on the measured area of the tack coated surface. This price shall include
material, spraying, and all work incidental thereto.
12.74 ASPHALTIC CONCRETE Section 12.46 - 12.50
Payment for asphaltic concrete pavement will be at the unit price per tonne or square metre
shown in the Tender Form. Payment by weight will be based on weighing certificates for mix
actually incorporated into the work. Payment by square metre will be based on the actual area
of asphaltic concrete pavement laid. The price by weight or square metre shall include final
base preparation, supply of aggregate and asphaltic cement, mixing, weighing, transporting,
placing, compacting and all other work incidental thereto.
Prime Contractor
Preconstruction Meeting Form APPENDIX “B”
Date: Meeting Location: Firm Name: Contract #: Prime Contractor: Prime Contractor’s Superintendent: City’s Contract Representative: AGREEMENT The Prime Contractor:
Acknowledges appointment as Prime Contractor defined by WorkSafe BC OH&S Regulations Sections 20.2 and 20.3, and in the Workers’ Compensation Act, Sections 118 Clauses 1 and 2.
Understands the Owners duties as defined in the Workers’ Compensation Act, Section 119. Understands for any discrepancy establishing health and safety protocol, WorkSafe BC OH&S
Regulation and/or the Workers’ Compensation Act (Part 3) shall prevail. Acknowledges being informed of any known workplace hazards by the owner or owner’s
delegate, by signing attached “Existing Known Hazard Assessment” form. Shall communicate known hazards to any persons who may be affected and ensure
appropriate measures are taken to effectively control or eliminate the hazards. Shall ensure all workers are suitably trained and qualified to perform the duties for which they
have been assigned. Shall ensure or coordinate first aid equipment and services as required by WorkSafe BC OH&S
Regulation. Shall coordinate the occupational health and safety activities for the project. Assumes responsibility for the health and safety of all workers and for ensuring compliance by
all workers with the Workers Compensation Act (Part 3) and WorkSafe BC OH&S Regulation. Understands any WorkSafe BC violation by the Prime Contractor may be considered a breach
of contract resulting in possible termination or suspension of the contract and/or any other actions deemed appropriate at the discretion of the City.
Understands any penalties, sanctions or additional costs levied against the Prime Contractor will be the responsibility of the Prime Contractor.
Confirms the Prime contractor’s safework procedures and risk assessments were prepared by, or approved by a Qualified Person as defined by WorkSafe BC OH&S Regulations.
Accepts the following required documents shall be maintained and made available upon request from the City and/or WorkSafe BC Prevention officer at the workplace.
The documents required to be maintained and available by the Prime Contractor will include, but not be limited to:
All notices which the Prime Contractor is required to provide to WorkSafe BC as per
WorkSafe BC OH&S Regulation. Any written summaries of remedial action taken to reduce occupational health and safety
hazards within the area of responsibility. All directives and inspection reports issued by WorkSafe BC. Records of any incidents and accidents occurring within the Prime Contractor’s area of
responsibility. Completed accident investigations for any incidents and accidents occurring within the
Prime Contractor’s area of responsibility.
On a construction workplace, these additional documents are required to be maintained and available by the Prime Contractor: • Records of all orientation and regular safety meetings held between contractors and their
workers, including topics discussed, worker names and companies in attendance. • Written evidence of regular inspections within the workplace. • Occupational first aid records. • Worker training records. • Current list of the name of a qualified person designated to be responsible for each
subcontractor (employer’s) site health and safety activities. • Diagram of the emergency route to the hospital.
The following information must be provided to the City Contract Representative:
WorkSafe BC Notice of Project WorkSafe BC Clearance Letter Prime Contractor’s OH&S Safety Program Prime Contractor’s OH&S Safety Program Document
First Aid Attendants:
Safety Supervisor:
Location of First Aid Station:
Signature of Prime Contractor: Signature of City Contract
Representative:
EXISTING KNOWN HAZARD ASSESSMENT Discussion between the Prime Contractor and the City Contract Representative Date: Meeting Location: Prime Contractor: Prime Contractor Representative: • City Contract Representative to make the Prime Contractor aware of any known extraordinary
pre-existing hazards peculiar to the contract. • It is recognized the known pre-existing hazards identified may not be a comprehensive list and
due caution is always required. • Use additional pages if necessary.
Identified Extraordinary Hazards Action required to eliminate or control hazards and ensure worker safety
Comment:
Comment:
Comment:
Prime Contractor Representative (signature) City Contract Representative (signature) Prime Contractor Representative (printed) City Contract Representative (printed)
-1-
Prime Contractor General Information Form
APPENDIX “A”
This document does not replace the Workers Compensation Act or OH&S Regulations
Sections 118 of the Workers Compensation Act: “multiple employer workplace” means a workplace where workers of 2 or more employers are working at the same time. Note:
• Workers of one employer do not necessarily have to come in contact with workers of the other • They do not have to be in the same place at the same time • Workers’ activities could affect the health and safety of another employer’s workers. This is true
even if the workers at the workplace are workers of the owner or contractor. “prime contractor” means, in relation to a multiple-employer workplace,
(a) the directing contractor, employer or other person who enters into a written agreement with the owner of that workplace to be the prime contractor for the purposes of this Part, or
(b) if there is no agreement referred to in paragraph (a), the owner of the workplace. The prime contractor of a multiple employer workplace must
• Ensure that the activities of all employers, workers (including the owners), and other persons at the workplace relating to occupational health and safety are coordinated and
• Do everything that is reasonably practicable to establish and maintain a system or process that will ensure compliance with the WC Act and the Regulation in respect of the workplace
Each employer of workers at a multiple employer workplace must give to the prime contractor the name of the person the employer has designated to supervise the employer’s workers at that workplace. For the sake of clarity, the following apply in determining whether there is a “multiple-employer” workplace:
• Two or more adjacent workplaces do not constitute a “multiple-employer workplace”, even though the activities at one place might affect the health and safety of workers at an adjacent workplace.
• In contrast, the workplace will generally be a “multiple-employer” workplace in the following situations:
-Workers of different employers are present at the same time working on the different projects; or -Workers of different employers are present at the same time working on the same project.
In either case the workplace would be considered a “multiple-employer” worksite.
-2-
Prime Contractor General Information Form
Page 2 of 3
• In determining whether “workers of 2 or more employers are working at the same time”, the phrase “at the same time” will be given such fair, large and liberal construction as may best attain the objectives of section 118. “At the same time” does not mean that, at any precise point in time, there are workers of 2 or more employers present in the workplace. Rather, it means that, over an appropriate interval, there are workers of 2 or more employers present in the workplace, whether or not the 2 or more groups of workers are actually present together in the workplace at any precise point in time at all. The duration of the interval of time to be considered will depend upon the circumstances of the individual workplace.
• Whether the workers of the one employer come into actual contact with the workers of the other employer does not generally affect the determination of whether the workplace is a “multiple-employer workplace”. An employer, the employer’s workers and their activities could well affect the health and safety of another employer’s workers who come into the workplace later in the day or on another day, even though there may be no actual contact between the two groups of workers. However, the degree to which the activities of the first employer and its workers affect the health and safety of the second employer’s workers will generally affect the determination of the responsibilities of the prime contractor and of the two employers under Part 3 and the regulations
• Virtually all workplaces will be visited by workers of other employers. For
example, workers may deliver or pick up mail, goods or materials or enter to inspect the premises. Short term visits of this type, even if regular, do not make the workplace a “multiple-employer workplace” for purposes of section 118(1).
The written agreement referred to in section 118(1) of the Act must be made available within a reasonable time if requested by a Board officer. There can be only one "prime contractor" at a workplace at any point in time. If an owner enters into more than one agreement purporting to create a "prime contractor" for the same period of time, the owner is considered to be the prime contractor.
-3-
Prime Contractor General Information Form
Page 3 of 3 Section 119 of the Workers Compensation Act: Every owner of a workplace must
(a) provide and maintain the owner's land and premises that are being used
as a workplace in a manner that ensures the health and safety of persons at
or near the workplace,
(b) give to the employer or prime contractor at the workplace the information
known to the owner that is necessary to identify and eliminate or control
hazards to the health or safety of persons at the workplace, and
(c) comply with this Part, the regulations and any applicable orders. Prime Contractor Qualified Coordinator OH&S Regulations 20.3: If a work location has overlapping or adjoining work activities of 2 or more employers that create a hazard to workers, and the combined workforce at the workplace is more than 5,
(a) the owner, or if the owner engages another person to be the prime contractor, then that person must
(i) appoint a qualified coordinator for the purpose of ensuring the coordination of health and safety activities for the location, and
(ii) provide up-to-date information as specified in subsection (4), readily available on site, and
(b) each employer must give the coordinator appointed under paragraph (a)(i) the name of a qualified person designated to be responsible for that employer's site health and safety activities.
(3) The duties of the qualified coordinator appointed under paragraph (2)(a)(i) include
(a) informing employers and workers of the hazards created, and
(b) ensuring that the hazards are addressed throughout the duration of the work activities.
(4) The information required by subsection (2)(a)(ii) includes
(a) the name of the qualified coordinator appointed under subsection (2)(a)(i),
(b) a site drawing, which must be posted, showing project layout, first aid location, emergency transportation provisions, and the evacuation marshalling station, and
(c) a set of construction procedures designed to protect the health and safety of workers at the workplace, developed in accordance with the requirements of this Regulation.
APPENDIX C
RECEIPT CONFIRMATION FORM
Request for Tender No. 1819
2016 Sidewalk and Traffic Circle Project
Closing date and time: 3:00 PM, Pacific Time, October 13, 2016
As receipt of this document, and to receive any addendums regarding this Request for Tender
please return this form to:
PURCHASING DEPARTMENT City of Nanaimo
2020 Labieux Road, Nanaimo, BC, V2T 4M7 Fax: 250.756.5327
Email: [email protected]
COMPANY NAME: ________________________________________________
STREET ADDRESS: _______________________________________________
CITY/PROVINCE: _________________________________________________
POSTAL CODE: __________________________________________________
PHONE NUMBER: ________________________________________________
FAX NUMBER: ___________________________________________________
CONTACT PERSON: ______________________________________________
EMAIL ADDRESS: ________________________________________________
SIGNATURE: ___________________________________________________________
APPENDIX C
RECEIPT CONFIRMATION FORM
Request for Tender No. 1819
2016 Sidewalk and Traffic Circle Project
Closing date and time: 3:00 PM, Pacific Time, October 13, 2016
As receipt of this document, and to receive any addendums regarding this Request for Tender
please return this form to:
PURCHASING DEPARTMENT City of Nanaimo
2020 Labieux Road, Nanaimo, BC, V2T 4M7 Fax: 250.756.5327
Email: [email protected]
COMPANY NAME: ________________________________________________
STREET ADDRESS: _______________________________________________
CITY/PROVINCE: _________________________________________________
POSTAL CODE: __________________________________________________
PHONE NUMBER: ________________________________________________
FAX NUMBER: ___________________________________________________
CONTACT PERSON: ______________________________________________
EMAIL ADDRESS: ________________________________________________
SIGNATURE: ___________________________________________________________
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORMVANCOUVER AND TOWNSITE
SCHEDULE OF QUANTITIES AND PRICES
Page 1 of 7 Tenderer's Initials _________
Item Description Est.Qty. Units Unit Price Total
Section 2 General Conditions
2.1 Location of Works - Project Layout (2.1) (not to exceed 5% of the total contract price) 1 lump sum
Total Section 2
Section 3 General Requirements
3.1 Locate Existing Structures (Section 3.70)a) Catch Basin Lead Tie-In Location 2 ea.
3.2 Control of Traffic (Section of 3.73) 1 lump sum
3.3 Removal of Existing Structures (Section 3.75)a) Existing Catch Basin 2 ea.b) Existing Catch Basin Lead 5 m
Total Section 3
Section 4 Trench Excavation, Bedding and Backfill
4.1 Import Granular Fill (trench backfill) (Section 4.73) 25 t
4.2 Surface Restoration (Section 4.76)a) 75mm Asphalt 5 m2
Total Section 4
Section 7 Storm Sewer System
7.1 Piping 200mm PVC SDR-35 (Section 7.70) 10 m
7.2 Connect to Existing Piping (Section 7.72)a) 200mm PVC x 200mm Conc 1 ea.b) 200mm PVC & 150mm Conc 1 ea.
7.3 Catch Basins (Section 7.74)a) ST-1 Type 1 2 ea.
7.4 Service Connection Inspection Assembly (Section 7.81)a) 150mm Storm 1 ea.b) 150mm Sanitary 1 ea.
Total Section 7
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORMVANCOUVER AND TOWNSITE
SCHEDULE OF QUANTITIES AND PRICES
Page 2 of 7 Tenderer's Initials _________
Item Description Est.Qty. Units Unit Price Total
Section 8 Curbs, Sidewalks and Walkways
8.1 Curbs (Section 8.70)a) CS-2 60 m
8.2 Sidewalk (Section 8.71)a) 100mm Thick Concrete 65 m2
b) Bus Ramp Sidewalk c/w welded wire mesh as per detailon DWG #21570 35 m2
8.3 Cutting and Removal of Existing Sidewalk (Section 8.72)a) Cutting - concrete 5 mb) Removal - concrete 45 m2
Total Section 8
Section 9 Streets, Traffic Signs and Markings
9.1 Stripping and Common Excavation (assume 0.3m depth) (Section 9.70) 30 m3
9.2 Subgrade Preparation (Section 9.75) 100 m2
9.3 Base Course (Section 9.77) 70 t
Total Section 9
Section 12 Asphaltic Concrete Paving
12.1 Cutting of Existing Asphalt (Section 12.70) 74 m
12.2 Removal of Existing Asphal(Section 12.71) 110 m2
Total Section 12
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORMVANCOUVER AND TOWNSITE
SCHEDULE OF QUANTITIES AND PRICES
Page 3 of 7 Tenderer's Initials _________
Item Description Est.Qty. Units Unit Price Total
TOTAL SECTION 2 $
TOTAL SECTION 3 $
TOTAL SECTION 4 $
TOTAL SECTION 7 $
TOTAL SECTION 8 $
TOTAL SECTION 9 $
TOTAL SECTION 12 $
SUB-TOTAL $
GST $
TOTAL - VANCOUVER AND TOWNSITE $
Name of Company
Signature of Signing Officer
Date
SUMMARY - Vancouver Ave. and Townsite Road
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORMJINGLE POT, SECOND, AND WENTWORTH SCHEDULE OF QUANTITIES AND PRICES
Page 4 of 7 Tenderer's Initials _________
Item Description Est.Qty. Units Unit Price Total
Section 2 General Conditions
2.1 Location of Works - Project Layout (Section 2.1)(not to exceed 5% of the total contract price) 1 lump sum
Total Section 2
Section 3 General Requirements
3.1 Location of Existing Structures (Section 3.70)a) City Fiber Optic 2 ea
3.2 Clearing and Grubbing 0+930 to 0+970 (Section 3.71) 1 lump sum
3.3 Control of Public Traffic(Section 3.73) 1 lump sum
3.4 Removal of Existing Structures (Section 3.75)a) Stop Signs 4 ea.
3.5 Relocate Existing Sign per City Standard Dwg. R-S1 2 ea
Total Section 3
Section 5 Water Distribution System
5.1 Relocate Existing Hydrant and Extend Lead (Section 5.75) 1 ea
Total Section 5
Section 8 Curbs, Sidewalks and Walkways
8.1 Curbs (Section 8.70)a) CS-4A 150 m
8.2 Sidewalk (Section 8.71)a) 100mm Thick Concrete 70 m2
b) 50mm Asphalt 300 m2
c) 150mm Thick Concrete 20 m2
d) Concrete Apron as per detailon DWG # 21527 48 m2
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORMJINGLE POT, SECOND, AND WENTWORTH SCHEDULE OF QUANTITIES AND PRICES
Page 5 of 7 Tenderer's Initials _________
Item Description Est.Qty. Units Unit Price Total
8.3 Cutting and Removal of Existing Asphalt and Concrete(Section 8.72)
a) Cutting Asphalt 90 mb) Cutting Conrete 10 mc) Remove Asphalt 185 m2
d) Remove Concrete 15 m2
8.4 Cutting and Removal of Existing Curb and Gutter(Section 8.73)
a) Concrete 110 m
8.5 Handrails (Section 8.75)a) ST-12 Black Powder Coated
Without Chainlink 37 m
8.6 Catch Basins and Manholes (Section 8.58)a) Raise Manholes 2 ea.b) Raise Monument Casting 1 ea.
Total Section 8
Section 9 Streets, Traffic Signs and Markings
9.1 Stripping and Common Excavation (Section 9.70) 175 m3
9.2 Imported Granular Fill (Section 9.74)a) MOTI Bridge End Fill 400 t
9.3 Subgrade Preparation (Section 9.75) 430 m2
9.4 Base Course (Section 9.77) 375 t
Total Section 9
Section 12 Asphaltic Concrete Paving
12.1 Asphalt (Section 12.74)a) 50mm 30 m2
b) 75mm 20 m2
Total Section 12
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORMJINGLE POT, SECOND, AND WENTWORTH SCHEDULE OF QUANTITIES AND PRICES
Page 6 of 7 Tenderer's Initials _________
Item Description Est.Qty. Units Unit Price Total
TOTAL SECTION 2 $
TOTAL SECTION 3 $
TOTAL SECTION 5 $
TOTAL SECTION 8 $
TOTAL SECTION 9 $
TOTAL SECTION 12 $
SUB-TOTAL $
GST $
TOTAL - JINGLE POT, SECOND, AND WENTWORTH $
Name of Company
Signature of Signing Officer
Date
SUMMARY - Jingle Pot Road, Second Street, and Wentworth Street
TENDER 1819 - 2016 SIDEWALK AND TRAFFIC CIRCLE TENDER FORM
SCHEDULE OF QUANTITIES AND PRICES
Page 7 of 7 Tenderer's Initials _________
TOTAL - VANCOUVER AND TOWNSITE $
TOTAL - JINGLE POT, SECOND, AND WENTWORTH $
TOTAL CONTRACT $
Name of Company
Signature of Signing Officer
Date
SUMMARY - TENDER 1819
NTS
LOCATION PLAN
KEY PLAN
1:1250
GENERAL NOTES:
1. ALL CONSTRUCTION TO BE IN ACCORDANCE WITH CITY OF NANAIMO ENGINEERING
STANDARDS AND SPECIFICATIONS.
2. ALL LOCATIONS AND ELEVATIONS OF EXISTING UTILITIES SHOWN ARE APPROXIMATE ONLY
AND SHOULD BE CONFIRMED BY USE OF A PIPE LOCATOR AND MANUAL DIGGING. ALL OR ANY
STRUCTURES NOT NECESSARILY SHOWN.
3. COORDINATES ARE GROUND LEVEL (UTM NAD 83 WITH COMBINED SCALE FACTOR OF
1/0.99965) AND ALL ELEVATIONS ARE TO GEODETIC DATUM.
4. LOCATION OF SERVICE CONNECTIONS TO BE DETERMINED ON SITE UNLESS SHOWN
OTHERWISE.
5. ANY ALTERNATIVES TO SPECIFIED MATERIALS OR APPURTENANCES TO BE APPROVED BY
THE CITY ENGINEER PRIOR TO CONSTRUCTION.
6. THE LOCATIONS OF EXISTING SERVICES ARE APPROXIMATE AND SHALL BE CONFIRMED IN
THE FIELD BY THE CONTRACTOR PRIOR TO CONSTRUCTION. EXISTING AND PROPOSED
SERVICES MAY REQUIRE ADJUSTMENT WHERE A CONFLICT OCCURS. THE ENGINEER SHALL
BE NOTIFIED OF ANY CONFLICT.
7. TRENCHING DETAIL TO CON STANDARD DWG T-1. TRAVELED AREA BACKFILL TO BE IMPORTED
GRANULAR MATERIAL COMPACTED TO MINIMUM 95% MODIFIED PROCTOR.
8. ASPHALT RESTORATION TO CON STD DWG T-4 PERMANENT RESTORATION.
9. ALL SURFACES TO BE RESTORED TO EXISTING CONDITION OR BETTER.
CON. DWG. No. 21566
Eng File No. 5220.01.C1431
SHEET No. DRAWING No. PROJECT TITLE
01 21566 PEDESTRIAN AND BICYCLE IMPROVEMENTS COVER SHEET
HOLLY AVENUE AND TOWNSITE ROAD - E&N TO STEWART KEYPLAN, LOCATION PLAN
02 21567 PEDESTRIAN AND BICYCLE IMPROVEMENTS CURB EXTENSION, TRAFFIC SIGNS AND STREET MARKINGS
HOLLY AVENUE AND TOWNSITE ROAD - E&N TO STEWART HOLLY AVENUE
ROSEHILL TO TOWNSITE
03 21568 PEDESTRIAN AND BICYCLE IMPROVEMENTS CURB EXTENSION, TRAFFIC SIGNS AND STREET MARKINGS
HOLLY AVENUE AND TOWNSITE ROAD - E&N TO STEWART TOWNSITE ROAD
E&N TO TERMINAL
04 21569 PEDESTRIAN AND BICYCLE IMPROVEMENTS CURB EXTENSION, TRAFFIC SIGNS AND STREET MARKINGS
HOLLY AVENUE AND TOWNSITE ROAD - E&N TO STEWART TOWNSITE ROAD
TERMINAL TO STEWART
05 21570 PEDESTRIAN AND BICYCLE IMPROVEMENTS DETAILS
HOLLY AVENUE AND TOWNSITE ROAD - E&N TO STEWART
Millstone A
ve
Rosehill St
Holly A
ve
E&
N R
ailw
ay
Caledonia A
ve
R
o
s
e
h
ill S
t
V
a
n
c
o
u
v
e
r
A
v
e
S
te
w
a
r
t A
v
e
N
e
w
c
a
s
tle
A
v
e
Bradley St
Pythian St
Pythian Ln
Wall S
t
Park St
M
t B
e
n
s
o
n
S
t
B
r
y
d
e
n
S
t
Thistle St
B
a
r
s
b
y
A
v
e
M
i
l
l
S
t
T
e
r
m
i
n
a
l
A
v
e
N
o
r
t
h
D
a
w
e
s
S
t
T
r
a
n
s
C
a
n
a
d
a
H
ig
h
w
a
y
Millstone A
ve
Harding A
ve
Cypress St
T
e
r
m
in
a
l A
v
e
N
o
r
th
S
te
w
a
r
t A
v
e
B
lu
e
G
ir
l W
a
y
Northum
berland A
ve
Churchill A
ve
Arbutus A
ve
Eberts St
Aldorann A
ve
Townsite Rd
T
o
w
n
s
ite
R
d
PEDESTRIAN AND BICYCLE IMPROVEMENTSHOLLY AVENUE AND TOWNSITE ROAD - E&N TO STEWART
PROJECT
LOCATION
HO
LLY
A
VE
TOWNSITE RD
E&
N R
AILW
AY
ROSEHILL ST
LANE
AR
BU
TU
S A
VE
ALD
OR
AN
N A
VE
LA
NE
T
E
R
M
IN
A
L
A
V
E
T
O
W
N
S
IT
E
R
D
V
A
N
C
O
U
V
E
R
A
V
E
S
T
E
W
A
R
T
A
V
E
SH
T 02
S
H
T
0
4
I S S U E D F O R
T E N D E R
S
H
T
0
3
SHEET 02 AND 03
NOT IN CONTRACT
Date
Reference data
No. By Revisions Eng.
Drawn by
Approved by
Checked by
Design by
Consult.Dwg
Dwg No.
Eng File No.
Scale
Horiz.
Sheet of
Vert.
Title
Project
T H E H A R B O U R C I T Y
Z:\P
RO
JE
CT
_01431\2 D
ES
IG
N\D
RA
WIN
GS
\~
CU
RR
EN
T\1431 H
OLLY
-T
OW
NS
IT
E9.27.2016
Date
Seal
PEDESTRIAN AND BICYCLE IMPROVEMENTS
HOLLY AVENUE TOWNSITE ROAD - E&N TO STEWART
CURB EXTENSION, TRAFFIC SIGNS AND STREET MARKINGS
TOWNSITE ROAD
TERMINAL TO STEWART
1:250 N/A
0405
5220.01.C1431
21569
MJY
MJY
PS
PS
2014-11-04
2014-11-04
2016-03-30
2016-03-30
I S S U E D F O R
T E N D E R
0
1:250
15m5
VA
NC
OU
VE
R A
VE
ST
EW
AR
T A
VE
TOWNSITE RD
TE
RM
IN
AL A
VE
FO
R C
ON
TIN
UA
TIO
N, S
EE
S
HT
0
3
EXTEND EXISTING
STOP BAR
REMOVE EXISTING DETECTOR LOOPS
TO EXISTING JUNCTION BOX, AND
SEAL SLOTS WITH ELSRO HOT POUR
CRACK FILLER No. 1190 OR EQUAL
INSTALL NEW DETECTOR LOOPS AS
PER SECTION 10 OF THE MANUAL OF
ENGINEERING STANDARDS AS
SPECIFICATIONS, LATEST EDITION.
SEE NORTHWEST CURB
EXTENSION DETAIL, THIS DWG
SEE SOUTHWEST CURB
EXTENSION DETAIL, THIS DWG
NORTHWEST CURB
EXTENSION DETAIL
1:100
SOUTHWEST CURB
EXTENSION DETAIL
1:100
VA
NC
OU
VE
R A
VE
TOWNSITE RD
TOWNSITE RD
VA
NC
OU
VE
R A
VE
R
3
.
0
m
R
3
.
0
m
R
5
.
0
m
R
5
.0
m
R
3
.
0
m
R
5
.
0
m
R
7
.
5
m
R
5
.
0
m
R
3
.
0
m
R
7
.
5
m
2.0
2.0
2.0
TIE-INTO
EXIST CURB
CS-2 CURB
GRADE TO MATCH
EXIST ASPHALT
INSTALL SIDEWALK LETDOWN
(2 PLACES), SEE DETAIL, THIS DWG
INSTALL TYPE 1 CB AS
PER CoN STD ST-1
200Ø PVC CB LEAD.
CONNECT TO EXIST CB LEAD
LOCATE PRIOR TO CONSTRUCTION
REMOVE EXIST CB
TIE-INTO
EXIST CURB
0.5
0.5
0.5
0.5
INSTALL TYPE 1 CB AS
PER CoN STD ST-1
REMOVE EXIST CB
200Ø PVC CB LEAD.
CONNECT TO EXIST CB LEAD
LOCATE PRIOR TO CONSTRUCTION
CS-2 CURB
GRADE TO MATCH
EXIST ASPHALT
INSTALL SIDEWALK LETDOWN
(2 PLACES), SEE DETAIL, THIS DWG
SAW-CUT EXIST CONC SIDEWALK
AT PANEL JOINT,
(±5.8m FROM NEW CURB)
REMOVE AND DISPOSE OFF SITE
INSTALL NEW CONCRETE
SIDEWALK. 100mm THICK ON
100mm COMPACTED CRUSH
GRAVEL (20mm MINUS)
INSTALL NEW CONCRETE
SIDEWALK. 100mm THICK ON
100mm COMPACTED CRUSH
GRAVEL (20mm MINUS)
SAW-CUT EXIST CONC SIDEWALK
AT PANEL JOINT,
(±13.2 FROM NEW CURB) .
REMOVE AND DISPOSE OFF SITE
SAW-CUT EXIST CONC SIDEWALK
AT PANEL JOINT,
(±15.0m FROM NEW CURB)
REMOVE AND DISPOSE OFF SITE
250Ø CONC
2
0
0
Ø
C
O
N
C
-R
200Ø VC 200Ø VC-R
TIE-INTO
EXIST CURB
TIE-INTO
EXIST CURB
2.0 MIN
0
.
5
0
.
5
1.5
100mm THICK CONC
SIDEWALK ON 100mm
COMPACTED CRUSH
GRAVEL (20mm MINUS)
SCORE LINES AT 200mm SPACING,
10mm WIDE x 15mm DEEP,
PARALLEL WITH CROSSWALK IN THE
DIRECTION OF THE RECEIVING LETDOWN
CENTRE OF SIDEWALK
TRANSITION FROM
RAMP TO CURB
TO BE FLUSH
RAMP SLOPE MAX 8.3%
EXTEND IF REQ'D
CURB DROP
CURB DROP
SIDEWALK LETDOWN DETAIL
1:50
NOTES:
1. FOR GENERAL NOTES, SEE SHT 01
2. SIDEWALKS TO BE CONSTRUCTED TO SECTION 8 OF THE MANUAL OF
ENGINEERING STANDARDS AND SPECIFICATIONS, LATEST EDITION.
3. TRAFFIC SIGNS AND STREET MARKINGS TO BE CONSTRUCTED TO
SECTION 9 OF THE MANUAL OF ENGINEERING STANDARDS AND
SPECIFICATIONS, LATEST EDITION.
CS-2 CURBSEE LANDSCAPING NOTES
SEE LANDSCAPING NOTES
LANDSCAPING NOTES:
LANDSCAPE RESTORATION TO BE COMPLETED BY OTHERS.CONTRACTOR TO LEAVE ALL PROPOSED OR DISTURBEDLANDSCAPING AREAS100mm BELOW FINISHED GRADE
1 2015-02-20 MJY 50% DESIGN SUBMISSION PS
PARKING
TRAVEL
& BIKE
TRAVEL
BIKE
TRAVEL
BIKE
PARKING
PARKING
TRAVEL
& BIKE
TRAVEL
BIKE
PARKING
TRAVEL
TRAVEL
77H5303 HOLLY & BRADLEY
EL: 37.281
77H5308 HOLLY & TOWNSITE
EL: 42.908
77H5346 TOWNSITE &
VANCOUVER
EL: 25.482
INSTALL CURBSIDE PEDESTRIAN
PUSHBUTTON POST,
SEE SHT 03 FOR DETAILS
INSTALL WC-19
SHARE THE ROAD SIGN
c/w WC-19S TAB
R=260.4m
R=146.7m
R=150m
R=150m
R=
150m
R=150m
BUS RAMP,
SEE DETAIL ON SHT 05
INSTALL WA-36R
OBJECT MARKER
SIGN
INSTALL RB-91
RESERVED BICYCLE
LANE SIGN
R
7
.
5
R
3
.
0
R
5
.
0
100mm WHITE PAINTED MEDIAN,
c/w 600mm WHITE
THERMOPLASTIC GORING
WHITE THERMOPLASTIC
SHARED BICYCLE LANE, TYP
100mm YELLOW
PAINTED SOLID LINE
100mm WHITE
PAINTED SOLID LINE
WHITE THERMOPLASTIC
BICYCLE RESERVED LANE,
TYP
15.0
100mm WHITE DASHED
THERMOPLASTIC LINE
1.0m x 1.0m
100mm YELLOW
PAINTED SOLID LINE
100mm WHITE
PAINTED SOLID LINE100mm WHITE DASHED
THERMOPLASTIC LINE
1.0m x 1.0m
100mm WHITE DASHED
THERMOPLASTIC LINE
1.0m x 1.0m
RELOCATE EXIST RA-1
STOP SIGN
INSTALL WA-36R
OBJECT MARKER
SIGN
SAW CUT EXISTING ASPHALT
AT FACE OF NEW CURB.
REMOVE ASPHALT UNDER THE
SIDEWALK EXTENSION AND
DISPOSE OFF SITE
SAW CUT EXISTING ASPHALT
AT FACE OF NEW CURB.
REMOVE ASPHALT UNDER THE
SIDEWALK EXTENSION AND
DISPOSE OFF SITE
INSTALL RB-51L
NO PARKING SIGN
INSTALL WA-36R
OBJECT MARKER
SIGN
INSTALL WA-36R
OBJECT MARKER
SIGN
PAINT CURB
YELLOW
INSTALL POST FOR BUS
STOP SIGN, CoN STD R-S1
SIGN SCHEDULE
SIGN QTY LOCATION
RB-91
1 NW CORNER TOWNSITE/STEWART
RB-51L
1 AT 220 TOWNSITE
2 2015-06-26 MJY 95% DESIGN SUBMISSION PS
WA-36R
WC-19 & WC-19S
1 - NW CORNER
VANCOUVER/TOWNSITE
2 - SW CORNER
TOWNSITE/VANCOUVER
1 - SOUTHEND OF BUST RAMP
1 - NW CORNER
TOWNSITE/VANCOUVER
1
SE CORNER OF
TOWNSITE/TERMINAL
5
INSTALL WA-36R
OBJECT MARKER
SIGN
INSTALL NEW SERVICES
BOXES FLUSH WITH
NEW SIDEWALK
1.5
1.5
1.5
1.5
SECTION C
1:25
150
R12mm
SAWCUT
R25mm
15
0
40
0
EXIST
ASPHALT
EXIST ROAD
STRUCTURE
100mm OF TOPSOIL
(BY OTHERS)
PROVIDE COMPACTED BASE
UNDER NEW CURB
MIN 100mm OF COMPACTED
20mm MINUS CRUSH
CONC
CURB
APPROVED NATIVE
BACKFILL TO 125mm
BELOW TOP OF CURB
200
MIN
IMPORTED GRANULAR
BACKFILL, COMPACTED TO
95% SPD.
25
C
-
C
-
MIN
3 2016-01-11 MJY 100% DESIGN SUBMISSION PS
4 2016-03-30 MJY RE-ISSUED FOR 100% DESIGN PS
1.0
3.4
TYP
TY
P, U
NO
12.0
NOTE:
PAINT LINES AND SIGNS
NOT IN CONTRACT
5 2016-09-26 MJY ISSUED FOR TENDER - CURBS AND SIDEWALKS ONLY PS
Date
Reference data
No. By Revisions Eng.
Drawn by
Approved by
Checked by
Design by
Consult.Dwg
Dwg No.
Eng File No.
Scale
Horiz.
Sheet of
Vert.
Title
Project
T H E H A R B O U R C I T Y
Z:\P
RO
JE
CT
_01431\2 D
ES
IG
N\D
RA
WIN
GS
\~
CU
RR
EN
T\1431 H
OLLY
-T
OW
NS
IT
E9.27.2016
Date
Seal
PEDESTRIAN AND BICYCLE IMPROVEMENTS
HOLLY AVENUE TOWNSITE ROAD - E&N TO STEWART
DETAILS
1:250 N/A
0505
5220.01.C1431
21570
MJY
MJY
PS
PS
2014-11-04
2014-11-04
2016-03-30
2016-03-30
I S S U E D F O R
T E N D E R
NOTES:
1. FOR GENERAL NOTES, SEE SHT 01
2. SIDEWALKS TO BE CONSTRUCTED TO SECTION 8 OF THE MANUAL OF
ENGINEERING STANDARDS AND SPECIFICATIONS, LATEST EDITION.
1 2015-02-20 MJY 50% DESIGN SUBMISSION PS
BUS RAMP DETAIL
1:50
VANCOUVER AVE
TO
WN
SIT
E R
D
B
-
TRIM EXISTING HEDGE
AS REQ'D TO INSTALL
NEW CONCRETE CURB
EXIST. CONC WALK TO
REMAIN ACCESSIBLE
RAISED CONCRETE BUS STOP
FINISH SIMLAR TO CONCRETE
SIDEWALK, C/W BROOM FINISH &
CONTRACTION JOINTS
SECTION B
1:10
EXIST
ASP CURB
2%
12
5m
m
2.0m
TOOLED JOINT
TO SIMULATE
CURB, TYP
EXIST
ASPHALT
CONCRETE
WELDED WIRE MESH
102x102 MW13.3/MW13.3
PLACE IN CENTRE OF SLAB
±6.4%
EX
S
LO
PE
±260mmC
-
GRIND OR REMOVE
EXIST ASPHALT TO KEY
IN CONCRETE RAMP, TYP
SECTION C
1:10
EXIST ASPHALT
PAINT CURB
YELLOW
2 2015-06-26 MJY 95% DESIGN SUBMISSION PS
RAMP
1.8m ASPHALT GRINDING OR REMOVAL
10
0m
m
MIN
10
0m
m
MIN
SAWCUT OR GRIND EXIST
ASPHALT TO ENSURE THAT
CONCRETE IS MIN 100mm THICK
3.7% NOMIN
AL SLOPE
150mm
PROVIDE TOOLED LINES
ON RAMPS, 15mm DEEP
AT 200mm O/C
3 2016-01-11 MJY 100% DESIGN SUBMISSION PS
4 2016-03-30 MJY RE-ISSUED FOR 100% DESIGN PS
ENSURE EXISTING
ASPHALT IS CLEAN OF DIRT
AND OIL PRIOR TO
POURING CONCRETE
EX
C
O
N
C
W
ALK
EX ASPHALT STORM
WATER CONTROL CURB
EX
S
TO
P B
AR
ASP CURB
ASP CURB
16.0
±3.4%
EX
S
LO
PE
±3.6%
EX SLOPE
±4.2%
EX SLOPE
2.0
15
0m
m M
IN
TO
E
XIS
T C
UR
B
3.5 RAMP 2.5 RAMP
EXTENT OF MODIFIED EXISTING ASPHALT CURB (15.2m)
5.0 RAMP
EXISTING GROUND
AT EXISTING GUTTERLINE
EXISTING GROUND AT
WEST (STREET) SIDE
TOP OF NEW CONCRETE AT
WEST (STREET) SIDE
TOP OF NEW CONCRETE
AT EAST (CURB) SIDE
BUS RAMP ELEVATION
1:50
MIN
50
mm
M
IN
REMOVE TOP
OF EXISTING
ASPHALT CURB
5 2016-09-26 MJY ISSUED FOR TENDER - CURBS AND SIDEWALKS ONLY PS
±14.7% RAMP
±6.7% RAMP ±2.8% RAMP
±10.5 RAMP
CON. DWG. No. 21521
1:5000
SHEET 002
JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREETBIKE LANE IMPROVEMENTS
LOCATION PLAN
KEY PLAN
1:1000
SHEET No. DWG No. PROJECT TITLE
1 21521 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET COVER SHEET
BIKE LANE IMPROVEMENTS KEY PLAN, LOCATION PLAN
2 21522 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET ROADWORKS PLAN
BIKE LANE IMPROVEMENTS JINGLEPOT STA. 0+090 TO 0+450
3* 21523 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET ROADWORKS PLAN
BIKE LANE IMPROVEMENTS JINGLEPOT STA. 0+450 TO 0+810
4 21524 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET ROADWORKS PLAN
BIKE LANE IMPROVEMENTS JINGLEPOT STA. 0+810 TO 1+180
5 21525 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET ROADWORKS PLAN
BIKE LANE IMPROVEMENTS SECOND STA. 1+180 TO 1+540
6* 21526 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET ROADWORKS PLAN
BIKE LANE IMPROVEMENTS SECOND STA. 1+540 TO 1+727 & PINE ST
7 21527 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET ROADWORKS PLAN
BIKE LANE IMPROVEMENTS WENTWORTH STA. 0+090 TO 1+470
8 21528 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET ROADWORKS PLAN
BIKE LANE IMPROVEMENTS WENTWORTH STA. 1+470 TO 1+820
9 009 JINGLEPOT ROAD, SECOND STREET, & WENTWORTH STREET LANDSCAPING PLAN
BIKE LANE IMPROVEMENTS WENTWORTH STA. 1+470 TO 1+820
GENERAL NOTES:
1. ALL CONSTRUCTION TO BE IN ACCORDANCE WITH CITY OF NANAIMO
ENGINEERING STANDARDS AND SPECIFICATIONS.
2. ALL LOCATIONS AND ELEVATIONS OF EXISTING UTILITIES SHOWN ARE
APPROXIMATE ONLY AND SHOULD BE CONFIRMED BY USE OF A PIPE LOCATOR
AND MANUAL DIGGING. ALL OR ANY STRUCTURES NOT NECESSARILY SHOWN.
3. COORDINATES ARE GROUND LEVEL (UTM NAD 83 WITH COMBINED SCALE
FACTOR OF 1/0.99965) AND ALL ELEVATIONS ARE TO GEODETIC DATUM.
4. LOCATION OF SERVICE CONNECTIONS TO BE DETERMINED ON SITE UNLESS
SHOWN OTHERWISE.
5. ANY ALTERNATIVES TO SPECIFIED MATERIALS OR APPURTENANCES TO BE
APPROVED BY THE CITY ENGINEER PRIOR TO CONSTRUCTION.
6. THE LOCATIONS OF EXISTING SERVICES ARE APPROXIMATE AND SHALL BE
CONFIRMED IN THE FIELD BY THE CONTRACTOR PRIOR TO CONSTRUCTION.
EXISTING AND PROPOSED SERVICES MAY REQUIRE ADJUSTMENT WHERE A
CONFLICT OCCURS. THE ENGINEER SHALL BE NOTIFIED OF ANY CONFLICT.
7. TRENCHING DETAIL TO CON STANDARD DWG T-1. TRAVELED AREA BACKFILL
TO BE IMPORTED GRANULAR MATERIAL COMPACTED TO MINIMUM 95%
MODIFIED PROCTOR.
8. ASPHALT RESTORATION TO CON STD DWG T-4 PERMANENT RESTORATION.
9. ALL SURFACES TO BE RESTORED TO EXISTING CONDITION OR BETTER.
BIKE LANE NOTES:
1. BICYCLE LANE LINES ARE SOLID, WHITE IN COLOUR WITH A WIDTH OF 100mm
2. WHERE MOTOR VEHICLES ARE PERMITTED TO MOVE INTO OR CROSS THE BICYCLE
LANE TO PERFORM A TURNING MOVEMENT, DASHED LINE SEGMENTS SHALL BE
USED. IN SUCH SITUATIONS, A MINIMUM 15m DASHED LINE IS TO BE USED.
3. BICYCLE LANES SHOULD INCLUDE BICYCLE AND DIAMOND SYMBOLS SPACED AT
75m OR AS CONDITIONS DICTATE, AND APPROXIMATELY 10m DOWNSTREAM FROM
AN INTERSECTION OR CROSSWALK.
Lubbock S
q
S
e
l
b
y
S
t
F
it
z
w
illia
m
S
t
W
e
s
l
e
y
S
t
R
o
b
s
o
n
S
t
B
a
s
tio
n
S
t
W
a
l
l
a
c
e
S
t
C
om
m
ercial S
t
W
h
a
r
f
S
t
P
ine S
t
M
achleary S
t
K
ennedy S
t
Com
ox Rd
M
ilton S
t
P
rideaux S
t
W
allace S
t
T
erm
inal A
ve
Com
ox Rd
Cliff S
t
C
h
a
p
e
l
S
t
F
r
o
n
t
S
t
O'Hara Pl
Ka
mp
P
l
T
h
o
r
a
P
l
Kerr St
S
elby S
t
C
am
pbell S
t
Fraser S
t
B
e
n
s
o
n
S
t
S
k
in
n
e
r
S
t
O'Brien Pl
Lam
bert A
ve
F
it
z
w
illia
m
S
t
M
a
c
h
l
e
a
r
y
S
t
W
e
s
l
e
y
S
t
D
u
n
s
m
u
i
r
S
t
C
h
i
n
a
S
t
e
p
s
McBride Pl
Ta
ylo
r P
l
Montague Rd
Craig S
t
Elizabeth St
W
entw
orth S
t
Johnston P
l
Beaconsfield Rd
Gail Pl
K
e
n
n
e
d
y
S
t
M
i
l
t
o
n
S
t
P
r
i
d
e
a
u
x
S
t
F
r
a
n
k
l
y
n
S
t
R
o
c
k
la
n
d
R
d
Wordsworth Gate Way
Wakesiah A
ve
J
in
g
le
P
o
t
R
d
V
a
lle
y
O
a
k
D
r
B
e
c
c
a
-
M
a
y
L
n
B
e
r
i
n
g
e
r
B
l
v
d
Sarum Rise Way
Poets Trail Dr
C
r
o
w
s
N
e
s
t
P
l
Addison R
d
Jingle Pot Rd
Derby P
l
Second St
Manning S
t
Second St
Harvey S
t
P
rideaux S
t
S
elby S
t
W
entw
orth S
t
R
ichards S
t
T
e
r
m
i
n
a
l
A
v
e
C
h
u
r
c
h
S
t
N
a
n
a
i
m
o
P
a
r
k
w
a
y
Coal Tyee Trail
C
h
a
m
b
e
r P
l
Peat Pl
Wessex Ln
T
h
ird
S
t
Valley O
ak D
r
Noorzan S
t
V
a
l
l
e
y
O
a
k
D
r
Bird
S
an
ctu
ary D
r
Wild
life
P
l
Kerr St
Kerr St
Skin
ne
r S
t
C
h
a
p
e
l
S
t
JINGLEPOT ROAD
JINGLEPOT ROAD
JINGLEPOT ROAD
JINGLEPOT ROAD
J
I
N
G
L
E
P
O
T
R
O
A
D
SECOND STREET
SECOND STREET
SECOND STREET
SECOND STREET
PINE STREET
WENTWORTH STREET
WENTWORTH STREET
WENTWORTH STREET WENTWORTH STREET
SIGNAGE & LINEPAINTING NOTES:
1. THE DESIGN, INSTALLATION AND DESIGNATION OF TRAFFIC SIGNS (REGULATORY
AND WARNING) TO BE IN ACCORDANCE WITH THE MOST CURRENT STANDARDS
CONTAINED IN THE "MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES FOR
CANADA" DISTRIBUTED BY THE TRANSPORTATION ASSOCIATION OF CANADA (TAC).
2. ALL ROAD MARKING TO BE THERMOPLASTIC.
SHEET 003
SHEET 004
SHEET 005
SHEET 006
SHEET 007
SHEET 008
Bird
S
an
ctu
ary D
r
B
eringer B
lvd
Derby P
l
Wakesiah A
ve
Ka
mp
P
l
Manning S
t
P
ine S
t
Harvey S
t
Craig S
t
How
ard A
ve
Do
ric A
ve
Sarum
rise W
ay
Wentw
orth S
t
S
e
c
o
n
d
S
t
Pin
e S
t
Machleary S
t
Ke
nn
ed
y S
t
Milto
n S
t
Prid
ea
ux S
t
Selby S
t
Richards S
t
W
a
lla
c
e
S
t
* SHEETS 3 AND 6 ARE NOT IN CONTRACT
Date
Reference data
No. By Revisions Eng.
Drawn by
Approved by
Checked by
Design by
Consult.Dwg
Dwg No.
Eng File No.
Scale
Horiz.
Sheet of
Vert.
Title
Project
T H E H A R B O U R C I T Y
Z:\P
RO
JE
CT
_01803\2_D
ES
IG
N\D
RA
WIN
GS
\~
CU
RR
EN
T\R
OA
DW
OR
KS
9.27.2016
Date
Seal
SECOND STREET BIKEWAY
JINGLE POT ROAD
STA 0+090 to 0+450
1:250 1:50
18
5220.01.C1803
21522
AF
AF
PS
PR
AUG 2014
1DEC 17, 2014
AF 50% SUBMISSION PS
I S S U E D F O R
T E N D E R
90H6366 Jingle Pot & Bird Sanctuary
EL: 58.014
77H5240 2nd & Wakesiaha Ave
EL: 65.854
77H5216 2nd & Doric Ave
EL: 58.117
REPLACE EXISTING "BIKE LANE
ENDS" SIGN WITH TAC "BIKE
LANE ENDS" SIGN (RB-92)
1
5
.0
7
EXTEND 100mm WHITE
DELINEATION LINE TO THE
EXISTING CROSSWALK
REPLACE EXISTING "BIKE
LANE BEGINS" SIGN WITH
TAC "BIKE LANE" SIGN (RB-91)
F
O
R
C
O
N
T
I
N
U
A
T
I
O
N
,
S
E
E
B
E
L
O
W
FO
R C
ON
TIN
UA
TIO
N, S
EE
D
WG
0
03
PROPOSED JINGLE POT TYPICAL SECTION A - STA 0+140 to 0+383
SCALE 1:100
INSTALL ADDITIONAL
CROSSWALK BAR TO SUIT
INSTALL BIKE LANE SYMBOL AT
APPROX 10m PAST CROSSWALKS
AND INTERSECTIONS. (TYP)
ERADICATE EXISTING FOG
LINE AND REPLACE WITH
100mm WIDE WHITE LINE
35m - DASHED 1.0 x 1.0
112m - SOLID
35.0
FO
R C
ON
TIN
UA
TIO
N, S
EE
A
BO
VE
EXISTING
YELLOW LINE
EXISTING
WHITE LINE
EXISTING
YELLOW LINE
EXISTING
WHITE LINE
EXISTING "CAMPING / RV"
DIRECTION SIGN TO REMAIN
INSTALL WAYFINDING SIGN
CON 2016 S-WB1.1D1
EXISTING PARK
INFORMATION
SIGN TO REMAIN
EXISTING "CHEVRON
ALIGNMENT" SIGNS
TO REMAIN (WA-6)
WA-9
EXISTING "PEDESTRIAN
CROSSWALK" SIGNS TO
REMAIN (RA-4L & 4R)
RA-4L & R
EXISTING BUS STOP
SIGN TO BE REMOVED.
RELOCATE AS SHOWN
BY OTHERS.
EXISTING "PEDESTRIAN
CROSSWALK" SIGNS
TO REMAIN (RA-4L & R)
RA-4L & R
EXISTING "CURVE" SIGN
TO REMAIN (WA-3L)
EXISTING "PEDESTRIAN
CROSSING AHEAD" SIGN
TO REMAIN (WC-2)
CON 2016 S-EB1.1D3
CON 2016 S-EB5.2D1
ERADICATE 15m OF EXISTING FOG
LINE AND REPLACE WITH 100mm
WIDE WHITE DASHED 1.0 x 1.0
INSTALL BIKE LANE SYMBOL AT
APPROX 100m SPACING (TYP)
MAX. 150m WHERE APPROPRIATE
7.50
5.00
25.00
7.00
INSTALL 1m WIDE x 7.0m LONG
ASPHALT PAD FOR BUS PASSENGER
LOADING/UNLOADING AREA.
1
1
2.0m
2%
REMOVE EX. CONCRETE
CURB AS REQUIRED
INSTALL 8.5m OF NEW CURB
TO CoN DWG CS-4A C/W
PEDESTRIAN CROSSING
INSTALL NEW 2m WIDE ASPHALT
SIDEWALK FROM START OF BUS
DELINEATION ZONE TO THE NEW LETDOWN
EXISTING "PEDESTRIAN
CROSSWALK" SIGNS
TO REMAIN (RA-4L & R)
RA-4L & R
EXISTING YEILD
SIGNS TO REMAIN
WA-36
EXISTING 'OBJECT
MARKER' SIGN TO
REMAIN (WA-36)
EXISTING STOP
SIGN TO REMAIN
EXISTING "CHEVRON
ALIGNMENT" SIGN
TO REMAIN (WA-6)
WA-9
EXISTING "PEDESTRIAN
CROSSWALK" SIGNS
(RA-4L & R) AND
'OBJECT MARKER' SIGN
(WA-36R) TO REMAINWA-36R RA-4L
& R
15.00
DAYLIGHT LINE
AT 2:1 FILL SLOPE
ERADICATE 30m OF EXISTING FOG
LINE AND REPLACE WITH 25m OF
100mm WIDE WHITE DASHED 1.0 x 1.0
10.00
INSTALL BIKE LANE SYMBOL AT
APPROX 100m SPACING (TYP)
MAX. 150m WHERE APPROPRIATE
10.00
2FEB 11, 2014
AF 95% SUBMISSION PS
PROPOSED JINGLE POT SECTION B - STA 0+383 to 0+417
SCALE 1:100
DAYLIGHT LINE
AT 2:1 FILL SLOPE
3JUL 30, 2015
AF 100% SUBMISSION PS
50mm - ASPHALT
150mm - BASE ON
APPROVED SUBGRADE
Section A
Section BSection A
Section CSection B
REMOVE BUS STOP WRAP FROM HYDRO
POLE AND INSTALL BUS STOP AT EAST
SIDE OF BIRD SANCTUARY RD AS SHOWN.
2%
7.00
1.8m
INSTALL 1m WIDE x 7.0m
LONG ASPHALT PAD FOR
BUS PASSENGER
LOADING/UNLOADING AREA.
INSTALL NEW 1.8m WIDE
ASPHALT SIDEWALK C/W 32m
OF CURB PER DWG CS-4A
R
8
.
0
0
PROPOSED JINGLE POT TYPICAL SECTION C - STA 0+417 to 0+465
SCALE 1:100
1.5
3.6
15.00
ERADICATE 15m OF EXISTING FOG
LINE AND REPLACE WITH 100mm
WIDE WHITE DASHED 1.0 x 1.0
100mm SOLID LINE
4APR 25, 2016
AF ISSUED FOR SIGNS & LINES CONSTRUCTION PS
INSTALL WAYFINDING SIGN
CON 2016 S-EB1.1D3
ON EX LAMP POST BELOW
AQUATIC CENTER SIGN
INSTALL WAYFINDING
SIGN CON 2016 S-EB1.2D1
ON EX POST BELOW
CROSSING SIGN
5JUN 22, 2016
AF UPDATED WAYFINDING SIGN INFORMATION PS
6SEP 22, 2016
AF ISSUED FOR TENDER PS
50mm - ASPHALT
150mm - BASE ON
APPROVED SUBGRADE
NOTE: HATCHED AREAS
NOT IN CONTRACT
Date
Reference data
No. By Revisions Eng.
Drawn by
Approved by
Checked by
Design by
Consult.Dwg
Dwg No.
Eng File No.
Scale
Horiz.
Sheet of
Vert.
Title
Project
T H E H A R B O U R C I T Y
Z:\P
RO
JE
CT
_01803\2_D
ES
IG
N\D
RA
WIN
GS
\~
CU
RR
EN
T\R
OA
DW
OR
KS
9.27.2016
Date
Seal
SECOND STREET BIKELANE
JINGLE POT ROAD
STA - 0+810 to 1+180
1:250 1:50
48
5220.01.C1803
21524
AF
AF
PS
PR
AUG 2014
I S S U E D F O R
T E N D E R
FO
R C
ON
TIN
UA
TIO
N, S
EE
B
EL
OW
90H6366 Jingle Pot & Bird Sanctuary
EL: 58.014
77H5240 2nd & Wakesiaha Ave
EL: 65.854
77H5216 2nd & Doric Ave
EL: 58.117
3.30
2.90
3.30
1.5m
1.5m
ERADICATE EXISTING ROAD
LINES AND MARKINGS AND
REPLACE AS SHOWN (TYP).
10.0m
IB-23RB-91
IB-23
EXISTING BIKE ROUTE SIGN (IB-23) AND
DIRECTIONAL TAB. INSTALL "BIKE LANE"
SIGN (RB-91) ON EXISTING SIGN POST.
REMOVE EX BIKE SIGN (IB-23). RELOCATE
POLE BEHIND PROP SDWK AND INSTALL
WAYFINDING SIGN CON 2016 S-EB3.1D3
INSTALL NEW LEFT
TURN ARROW IN
CENTER OF LANE (TYP).
INSTALL BIKE LANE STENCIL LOCATED
AT APPROX 10m PAST INTERSECTION
OR CROSSWALKS. (TYP)
15.00
1.50
3.60
3.40
3.70
1.50
10.0m
15.0m
IB-23RB-91
EXISTING BIKE ROUTE SIGN (IB-23) AND
DIRECTIONAL TAB. INSTALL "BIKE LANE"
SIGN (RB-91) AT 15m PAST CURB RETURN.
CUT NEW TRAFFIC SIGNAL DETECTOR LOOPS ON JINGLE
POT RD EBL. INSTALL NEW LEFT TURN ARROW AND BIKE
DETECTOR STENCILS ON FRONT LOOPS (TYP.).
INSTALL BIKE LANE STENCIL LOCATED
AT APPROX 10m PAST INTERSECTION
OR CROSSWALKS. (TYP)
INSTALL BIKE LANE SYMBOL AT
APPROX 10m PAST CROSSWALKS
AND INTERSECTIONS. (TYP)
10.0
EXISTING
YELLOW LINE
ERADICATE
WHITE LINE
15m OF 100mm WIDE WHITE DASHED
1.0 x 1.0 LINE WHERE VEHICLES
TURNING RIGHT ARE EXPECTED TO
CROSS THE BIKE LANE. (TYP)
2
.
5
1
.
0
20:1
0.57
REMOVE EXISTING CURB
AND INSTALL 37m OF NEW
CURB TO CoN DET CS-4A.
SEE SECTION LEFT. FILL
VOLUME = ± 69m³
JINGLE POT TYPICAL SECTION E - STA 0+853.62 to 0+965
SCALE 1:100
1
1.5
IB-23
ERADICATE 15m OF EXISTING FOG
LINE AND REPLACE WITH 100mm WIDE
WHITE DASHED 1.0 x 1.0 LINE (TYP)
10.0m
INSTALL BIKE LANE STENCIL LOCATED
AT APPROX 10m PAST INTERSECTION
OR CROSSWALKS. (TYP)
1.5m
INSTALL 1.5m WIDE
ASPHALT SIDEWALK
DAYLIGHT LINE AT 1.5:1
FILL SLOPE. HYDRO SEED
POST CONSTRUCTION.
RELOCATE EXISTING BUS STOP
SIGN TO BACK ON NEW SIDEWALK
EXISTING BUS STOP
ON STREETLIGHT
POLE TO REMAIN
35.0m
ERADICATE 40m OF EXISTING FOG LINE
AND REPLACE WITH 35m OF 100mm
WIDE WHITE DASHED 1.0 x 1.0 LINE
ERADICATE EXISTING MEDIAN BARS
ABOVE NEW CENTERLINE AND
RETAIN EXISTING MEDIAN BARS
BELOW CENTERLINE AS SHOWN.
2%
25.00
25m OF 100mm WIDE
WHITE DASHED 1.0 x 1.0
LINE FOR BUS STOP
INSTALL BIKE LANE SYMBOL AT
APPROX 100m SPACING (TYP)
MAX. 150m WHERE APPROPRIATE
1DEC 17, 2014
AF 50% SUBMISSION PS
2FEB 11, 2014
AF 95% SUBMISSION PS
3JUL 30, 2015
AF 100% SUBMISSION PS
PAINT DIAMOND 2m FROM
EXISTING BIKE SYMBOL
Section ESection D
Section DSection E
INSTALL HANDRAIL TO
CoN DWG ST-13 POWDER
COATED BLACK. NO
CHAIN LINK FENCING.
EX HEDGE ON
PL TO REMAIN
INSTALL 0.5m WIDE GRAVEL
BLVD C/W HANDRAIL
0.5m
7.00
INSTALL 1m WIDE x 7.0m LONG
ASPHALT PAD FOR BUS PASSENGER
LOADING/UNLOADING AREA.
2%
INSTALL 27m OF 1.8m WIDE
ASPHALT SIDEWALK FROM EXISTING
LETDOWN. EX CURB TO REMAIN.
27.14
JINGLE POT TYPICAL SECTION D - STA 0+826.47 to 0+853.62
SCALE 1:100
4APR 25, 2016
AF PS
REMOVE EX BIKE SIGN (IB-23)
AND INSTALL WAYFINDING SIGN
CON 2016 S-WB3.1D3
REMOVE EXISTING BIKE ROUTE SIGN
(IB-23) AND DIRECTIONAL TABS. INSTALL
WAYFINDING SIGN CON 2016 S-SB3.1D2
REMOVE EXISTING BIKE ROUTE SIGN
(IB-23) AND DIRECTIONAL TABS. INSTALL
WAYFINDING SIGN CON 2016 S-NB3.1D3
5JUN 22, 2016
AF UPDATED WAYFINDING SIGN INFORMATION PS
CLEAR AND GRUB
AS NECESSARY.
ISSUED FOR SIGNS & LINES CONSTRUCTION
6SEP 22, 2016
AF ISSUED FOR TENDER PS
FO
R C
ON
TIN
UA
TIO
N, S
EE
D
WG
0
03
FO
R C
ON
TIN
UA
TIO
N, S
EE
D
WG
0
05
FO
R C
ON
TIN
UA
TIO
N, S
EE
A
BO
VE
50mm - ASPHALT
150mm - BASE ON
APPROVED SUBGRADE
50mm - ASPHALT
150mm - BASE ON
APPROVED SUBGRADE
NOTE: HATCHED AREAS
NOT IN CONTRACT
INSTALL COCO
NETTING ON
FILL SLOPE
Date
Reference data
No. By Revisions Eng.
Drawn by
Approved by
Checked by
Design by
Consult.Dwg
Dwg No.
Eng File No.
Scale
Horiz.
Sheet of
Vert.
Title
Project
T H E H A R B O U R C I T Y
Z:\P
RO
JE
CT
_01803\2_D
ES
IG
N\D
RA
WIN
GS
\~
CU
RR
EN
T\R
OA
DW
OR
KS
9.27.2016
Date
Seal
SECOND STREET BIKEWAY
SECOND STREET
STA - 1+180 to 1+540
1:250 1:50
58
5220.01.C1803
21525
AF
AF
PS
PR
AUG 2014
I S S U E D F O R
T E N D E R
FO
R C
ON
TIN
UA
TIO
N, S
EE
B
EL
OW
90H6366 Jingle Pot & Bird Sanctuary
EL: 58.014
77H5240 2nd & Wakesiaha Ave
EL: 65.854
77H5216 2nd & Doric Ave
EL: 58.117
EXISTING SCHOOL
AREA ZONE SIGN (WC-1)
WITH 30KM/H TAB (RB-1)
INSTALL 100mm SOLID
WHITE DELINEATION LINE
STA: 1+235 to STA: 1+275
ERADICATE 15m OF EXISTING FOG
LINE AND REPLACE WITH 100mm WIDE
WHITE DASHED 1.0 x 1.0 LINE (TYP)
15.00
FO
R C
ON
TIN
UA
TIO
N, S
EE
D
WG
0
04
WC-1RB-1
15.00
FO
R C
ON
TIN
UA
TIO
N, S
EE
D
WG
0
06
10.0m
2.4
1.5
4.00
3.69
1.5
1.5
4.2
43.73
1.5
PROPOSED JINGLE POT TYPICAL SECTION F - STA 0+965 to 1+710
SCALE 1:100
IB-23
EXISTING SCHOOL AREA
ZONE SIGN (WC-3) WITH
30KM/H TAB (RB-1) AND
BIKE ROUTE SIGN (IB-23)
WC-1
EXTEND STOP
BAR TO SUIT
INSTALL "BIKE LANE" SIGN
(RB-91) APPROX 15m FROM
END OF CURB RETURN
INSTALL "BIKE LANE" SIGN
(RB-91) IMMEDIATELY EAST OF
STREET PARKING AS SHOWN
15.0m (TYP)
FO
R C
ON
TIN
UA
TIO
N, S
EE
A
BO
VE
PROPOSED
WHITE LINE
15m OF 100mm WIDE WHITE
DASHED 1.0 x 1.0 LINE (TYP)
15m OF 100mm WIDE WHITE
DASHED 1.0 x 1.0 (TYP)
PROPOSED
WHITE LINE
INSTALL BIKE LANE SYMBOL AT
APPROX 10m PAST CROSSWALKS
AND INTERSECTIONS. (TYP)
2.1
1.5
EXISTING "PEDESTRIAN
CROSSWALK" SIGNS
TO REMAIN (RA-4L)
RA-4L
EXISTING "NO PARKING
ANYTIME" SIGNS TO
REMAIN (RB 51-1)
RB 51-1
EXISTING BUS STOP SIGN TO APPROX
40m FROM INTERSECTION ON
SOUTHBOUND HOWARD AVE ACROSS
FROM EXISTING NORTHBOUND BUS STOP.
EXISTING STOP
SIGN TO REMAIN
ERADICATE 15m OF EXISTING FOG
LINE AND REPLACE WITH 100mm
WIDE WHITE DASHED 1.0 x 1.0
15.0m (TYP)
15.0m (TYP)
15.0m (TYP)
ERADICATE EXISTING PARKING
LINE AND REPLACE WITH
100mm WIDE LINE AT 2.4m
FROM BIKE LANE AS SHOWN
REMOVE 4m OF CURB & INSTALL 1.7m
WIDE ASPHALT LETDOWN FOR
CROSSWALK. GRADES TO MATCH
NEIGHBORING DRIVEWAY LETDOWN.
INSTALL 0.6m W x 3.0m L CROSSWALK
LINES SPACED AT 0.6m AS SHOWN
REMOVE 2.8m OF CURB & INSTALL 1.7m
WIDE ASPHALT LETDOWN FOR CROSSWALK.
GRADES TO MATCH EXISTING LETDOWN.
10.00
1DEC 17, 2014
AF 50% SUBMISSION PS
2FEB 11, 2014
AF 95% SUBMISSION PS
3JUL 30, 2015
AF 100% SUBMISSION PS
Section FSection F
Section FSection F
PAINT CURB
EXTENSION WITH
GORING AS SHOWN.
R
3
.
0
0
40
m
INSTALL "PEDESTRIAN
CROSSWALK" SIGNS
(RA-4L & 4R)
RA-4L & R
R
5
.
0
0
INSTALL "PEDESTRIAN
CROSSWALK" SIGNS
(RA-4L & 4R)
RA-4L & R
4APR 25, 2016
AF PS
5JUN 22, 2016
AF UPDATED WAYFINDING SIGN INFORMATION PS
ISSUED FOR SIGNS & LINES CONSTRUCTION
6SEP 22, 2016
AF ISSUED FOR TENDER PS
NOTE: HATCHED AREAS
NOT IN CONTRACT
Date
Reference data
No. By Revisions Eng.
Drawn by
Approved by
Checked by
Design by
Consult.Dwg
Dwg No.
Eng File No.
Scale
Horiz.
Sheet of
Vert.
Title
Project
T H E H A R B O U R C I T Y
Z:\P
RO
JE
CT
_01803\2_D
ES
IG
N\D
RA
WIN
GS
\~
CU
RR
EN
T\R
OA
DW
OR
KS
9.27.2016
Date
Seal
SECOND STREET BIKEWAY
WENTWORTH STREET
STA - 0+090 to 0+470
1:250 1:50
78
5220.01.C1803
21527
AF
AF
PS
PR
AUG 2014
I S S U E D F O R
T E N D E R
FO
R C
ON
TIN
UA
TIO
N, S
EE
B
EL
OW
FOR CONTINUATION, SEE DWG 006
90H6366 Jingle Pot & Bird Sanctuary
EL: 58.014
77H5240 2nd & Wakesiaha Ave
EL: 65.854
77H5216 2nd & Doric Ave
EL: 58.117
WC-20
INSTALL "SHARED USE LANE
SINGLE FILE" SIGN (WC-20)
TAC STANDARD BICYCLE SHARROW
ROADWAY MARKING (WHITE
THEROPLASTIC HOT TAPE) (TYP.)
(T
YP
)
15.0m (TYP)
2.6
FO
R C
ON
TIN
UA
TIO
N, S
EE
D
WG
0
08
PROPOSED WENTWORTH TYPICAL SECTION
SCALE 1:100
TAC STANDARD BICYCLE SHARROW
ROADWAY MARKING (WHITE
THERMOPLASTIC HOT TAPE) (TYP.)
(T
YP
)
15.0m (TYP)
2.6
FO
R C
ON
TIN
UA
TIO
N, S
EE
A
BO
VE
EXISTING STOP
SIGN TO REMAIN
EXISTING STOP
SIGN TO REMAIN
EXISTING "NO PARKING
ANYTIME" SIGN TO
REMAIN (RB-55L)
RB-55L
EXISTING
"PLAYGROUND AHEAD"
SIGN TO REMAIN (WC-3)
WC-3
EXISTING STOP
SIGN TO REMAIN
EXISTING "NO PARKING
ANYTIME" SIGN TO
REMAIN (RB 51-1)
RB 51-1
EXISTING "NO PARKING
ANYTIME" SIGN TO
REMAIN (RB-55R)
RB-55R
EXISTING "PLAYGROUND
AHEAD" SIGN TO REMAIN
(WC-3). INSTALL WC-20
ON EXISTING POLE
EXISTING "TRUCKS
PROHIBITED" SIGN
TO REMAIN (RB 62)
RB 62
EXISTING STOP
SIGN TO REMAIN
EXISTING STOP
SIGN TO REMAIN
WC-20
INSTALL "SHARED USE LANE
SINGLE FILE" SIGNS (WC-20)
IB-23
EXISTING BIKE ROUTE SIGN (IB-23)
WITH DIRECTIONAL TAB AND 2HR
PARKING SIGN TO REMAIN.
EXISTING 2HR PARKING
SIGN TO REMAIN
WC-3
1DEC 17, 2014
AF 50% SUBMISSION PS
2FEB 11, 2014
AF 95% SUBMISSION PS
A
A
CROSS SECTION OF TRAFFIC CIRCLE (A-A)
SCALE 1:50
3JUL 30, 2015
AF 100% SUBMISSION PS
REMOVE ASPHALT
LETDOWN ON ALL CORNERS
AND REPLACE WITH 150mm
TOPSOIL & SEED (TYP)
3.7m
INSTALL LETDOWNS 3.7m FROM
CIRCLE EDGE IN ALL CROSSING
DIRECTIONS PER DWG CS-7A
R
4
.
0
0
REMOVE ASPHALT AND REPLACE
WITH 150mm OF TOPSOIL & SEED
REMOVE EX CURB TO EXTENT SHOWN ON ALL
CORNERS AND INSTALL NEW CS-4A CURB.
MATCH EX CURB HEIGHT AT ALL ENDS (TYP)
4.8
m
3.7m
3.7
m
R
4
.
0
0
R
4
.
0
0
R
3
.
0
0
WC-20
INSTALL "SHARED USE LANE
SINGLE FILE" SIGN (WC-20)
ER
AD
IC
AT
E C
L 1
5.0
m (T
YP
)
WC-20
WC-20
INSTALL "SHARED USE LANE
SINGLE FILE" SIGN (WC-20)
R
3
.
0
0
R
5
.0
0
EXISTING HYDRO
POLE TO REMAIN
R
5
.
0
0
R
3
.
0
0
4APR 25, 2016
AF PS
5JUN 22, 2016
AF UPDATED WAYFINDING SIGN INFORMATION PS
PROTECT AND MAINTAIN ACCESS TO EX. MONUMENT.
REMOVE EXISTING RISER AND INSTALL 200mm PVC
TO RAISE CASTING TO BEDDING SURFACE.
RAISE STM MH
COVER ±0.12m
RAISE SAN MH
COVER ±0.20m
SAWCUT ALONG EXTENDED
PARKING AREA AND INSTALL
75mm ASPHALT TO DWG T-4A.
ISSUED FOR SIGNS & LINES CONSTRUCTION
6SEP 22, 2016
AF ISSUED FOR TENDER PS
HYDRO POLE TO BE
RELOCATED BY OTHERS
0.6
RELOCATE HYDRANT
BEHIND SIDEWALK TO
C.O.N. STD. DWG W-5
CAUTION: FIBER OPTIC LINES
WITH SHALLOW 95mm COVER
ACROSS ROAD AND SIDEWALK
NOTE: HATCHED AREAS
NOT IN CONTRACT
Date
Reference data
No. By Revisions Eng.
Drawn by
Approved by
Checked by
Design by
Consult.Dwg
Dwg No.
Eng File No.
Scale
Horiz.
Sheet of
Vert.
Title
Project
T H E H A R B O U R C I T Y
Z:\P
RO
JE
CT
_01803\2_D
ES
IG
N\D
RA
WIN
GS
\~
CU
RR
EN
T\R
OA
DW
OR
KS
9.27.2016
Date
Seal
SECOND STREET BIKEWAY
WENTWORTH STREET
STA - 0+470 to 0+820
1:250 1:50
88
5220.01.C1803
21528
AF
AF
PS
PR
AUG 2014
I S S U E D F O R
T E N D E R
FO
R C
ON
TIN
UA
TIO
N, S
EE
B
EL
OW
90H6366 Jingle Pot & Bird Sanctuary
EL: 58.014
77H5240 2nd & Wakesiaha Ave
EL: 65.854
77H5216 2nd & Doric Ave
EL: 58.117
TAC STANDARD BICYCLE SHARROW
ROADWAY MARKING (WHITE
THEROPLASTIC HOT TAPE) (TYP.)
(T
YP
)
15.0m (TYP)
2.6
FO
R C
ON
TIN
UA
TIO
N, S
EE
D
WG
0
07
WC-20
INSTALL "SHARED USE LANE
SINGLE FILE" SIGN (WC-20)
TAC STANDARD BICYCLE SHARROW
ROADWAY MARKING (WHITE
THEROPLASTIC HOT TAPE) (TYP.)
(T
YP
)
15.0m (TYP)
2.6
FO
R C
ON
TIN
UA
TIO
N, S
EE
A
BO
VE
EN
D O
F P
RO
JE
CT
EXISTING 2HR PARKING
SIGNS TO REMAIN
EXISTING 2HR PARKING
SIGNS TO REMAIN
EXISTING 2HR PARKING
SIGNS TO REMAIN
EXISTING 2HR PARKING
SIGNS TO REMAIN
IB-23
EXISTING BIKE ROUTE SIGN (IB-23)
WITH DIRECTIONAL TAB AND 2HR
PARKING SIGN TO REMAIN.
EXISTING STOP
SIGN TO REMAIN
EXISTING BUS STOP SIGN
TO REMAIN. INSTALL
RB-58 SIGN ON POLE.
EXISTING 2HR PARKING
SIGNS TO REMAIN
EXISTING 2HR HANDICAP
PARKING SIGNS TO REMAIN
EXISTING 2HR PARKING
SIGNS TO REMAIN
EXISTING 2HR PARKING
SIGNS TO REMAIN
EXISTING 2HR PARKING
SIGNS TO REMAIN
IB-23
REMOVE EXISTING BIKE ROUTE SIGN (IB-23) WITH
DIRECTIONAL TAB. 2HR PARKING SIGN TO REMAIN.
INSTALL WAYFINDING SIGN CON 2016 S-EB5.1D1.
1DEC 17, 2014
AF 50% SUBMISSION PS
2FEB 11, 2014
AF 95% SUBMISSION PS
3JUL 30, 2015
AF 100% SUBMISSION PS
INSTALL CONCRETE LANDING PAD
-150mm CONCRETE
-150mm BASE ON APPROVED
SUBGRADE
9.00
0.50
RB-58
4APR 25, 2016
AF ISSUED FOR CONSTRUCTION PS
REMOVE EX BIKE ROUTE SIGN (IB-23)
AND INSTALL WAYFINDING SIGN
CON 2016 D-SB5.1D1
IB-23
REMOVE EX BIKE ROUTE SIGN (IB-23)
AND INSTALL WAYFINDING SIGN
CON 2016 D-NB5.1D1
IB-23
5JUN 22, 2016
AF UPDATED WAYFINDING SIGN INFORMATION PS
ISSUED FOR SIGNS & LINES CONSTRUCTION
6SEP 22, 2016
AF ISSUED FOR TENDER PS
NOTE: HATCHED AREAS
NOT IN CONTRACT