request for tender - shire of perenjori...this is a request for tender. your tender will be...
TRANSCRIPT
REQUEST FOR TENDER
Request for Tender PERENJORI BUSINESS CENTRE RE-
DEVELOPMENT
Deadline: 4PM ON TUESDAY 6TH AUGUST 2013
Address for Delivery:
PO BOX 22, PERENJORI WA 6620
OR
40 FOWLER STREET, PERENJORI.
OR
EMAILTO:
EMAILED OR FACSIMILIE TENDERS WILL
BE ACCEPTED
RFT Number: 02/2013
TABLE OF CONTENTS
1 CONDITIONS OF TENDERING
DEFINITIONS
TENDER DOCUMENTS
HOW TO PREPARE YOUR TENDER
CONTACT PERSONS
TENDER BRIEFING / SITE INSPECTION
LOGEMENT OF TENDERS AND DELIVERY METHOD
REJECTION OF TENDERS
LATE TENDERS
ACCEPTANCE OF TENDERS
DISCLOSURE OF CONTRACT INFORMATION
TENDER VALIDITY PERIOD
PRECEDENCE OF DOCUMENTS
REGISTRATION OR LICENSING OF CONTRACTORS
ALTERNATIVE TENDERS
TENDERERS TO INFORM THEMSELVES
ALTERATIONS
RISK ASSESSMENT
EVALUATION PROCESS
SELECTION CRITERIA
PRICE CONSIDERATIONS
PRICE BASIS
OWNERSHIP OF TENDERS
CANVASSING OF OFFICIALS
IDENTITY OF THE TENDERER
COSTS OF TENDERING
TENDER OPENING
IN-HOUSE TENDERS
2 SPECIFICATION
CONTRACT REQUIREMENTS IN BRIEF
DEFINITIONS
INTRODUCTION
BACKGROUND INFORMATION
SCOPE OF WORK
SPECIFIC REQUIREMENTS OF THE CONTRACT
IMPLEMENTATION TIMETABLE
3 GENERAL CONDITIONS OF CONTRACT
INSURANCES
PERIOD OF CONTRACT AND TERMINATION
4 SPECIAL CONDITIONS OF CONTRACT
WARRANTIES
SUPPLEMENTARY CONDITIONS OF CONTRACT
5 TENDERER’S OFFER
OFFER FORM
SELECTION CRITERIA
PRICE INFORMATION
PRICE SCHEDULE
APPENDIX A ELECTRICAL
APPENDIX B ARCHITECT SPECIFICATION PHOTOGRAPHS
PART 1 READ AND KEEP THIS PART
CONDITIONS OF TENDERING
DEFINITIONS
Below is a summary of some of the important defined terms used in this Request:
Attachments: The documents you attach as part of your Tender;
Contractor: Means the person or persons, corporation or corporations whose Tender is accepted by the Principal, and includes the executors or administrators, successors and assigns of such person or persons, corporation or corporations;
Deadline: The deadline for lodgement of theTender as detailed on the front of this Request;
General
Conditions of
Contract:
Means the General Conditions of Contract for the Construction of the Perenjori
Business Incubator Proposed Workshop Conversion as per the specifications
provided or nominated in Part 2.
Offer: Your offer to be selected to supply the Requirements;
Principal: Shire of Perenjori
Request OR RFT
OR Request for
Tender:
This document;
Requirements: The services requested by the Principal;
Selection Criteria: The criteria used by the Principal in evaluating your Tender;
Special Conditions: The additional contractual terms;
Specification: The statement of Requirements that the Principal requests you to provide if
selected;
Tender: Completed Offer form, response to the Selection Criteria and Attachments;
Tenderer: Someone who has or intends to submit an Offer to the Principal.
TENDER DOCUMENTS
This Request for Tender is comprised of the following parts:
(a) Part 1 - Conditions of Tendering (read and keep this part).
(b) Part 2 – Specification and/or plans/drawings (read and keep this part);
(c) Part 3 – Tenderer’s Offer (complete and return this part);
(d) Part 4 – General Conditions of Contract (read and keep this part).
(e) Part 5 – Special Conditions of Contract (read and keep this part); and
PART 1 READ AND KEEP THIS PART
Separate Documents:
(a) Addenda and any other special correspondence issued to Tenderers by the Principal;
HOW TO PREPARE YOUR TENDER
(a) Carefully read all parts of this document.
(b) Ensure you understand the Requirements.
(c) Complete and return the Offer (Part 3) in all respects and include all Attachments.
(d) Make sure you have signed the Offer Form and responded to all of the Selection Criteria.
(e) Lodge your Tender before the Deadline.
CONTACT PERSONS
Tenderers should not rely on any information provided by any person other than the person listed below:
RFT Enquiries
Name: Alison Mills
Telephone: 08 9973 1002
Email: [email protected]
PART 1 READ AND KEEP THIS PART
TENDER BRIEFING/SITE INSPECTION
Attendance at this meeting is not mandatory.
Tenderers are requested to attend a site inspection on [Friday 12th July 2013] at [1000 hours].
The location of the meeting is 40 Fowler Street, Perenjori.
The site inspection will provide Tenderers with the opportunity to clarify any uncertainties with the contact
person prior to the closing of the tender.
Please confirm with the contact person Alison Mills on 08 9973 1002 or via email to
[email protected] your attendance at this meeting no later than Wednesday 10th July 2013.
LODGEMENT OF TENDERS AND DELIVERY METHOD
The Tender must be lodged by the Deadline. The Deadline for this Request is by 4.00 pm on Tuesday 6th
August 2013 at 4pm.
The Tender is to be:
(a) placed in a sealed envelope clearly endorsed with the tender number and title as shown on the front
cover of this Request; and
(b) delivered by hand and placed in the Tender Box at 40 Fowler Street, Perenjori (by the Tenderer or
the Tenderer’s private agent) or sent through the mail to the Chief Executive Officer, PO Box 22,
PERENJORI, WA, 6620.
Electronic mail Tenders and Tenders submitted by facsimile will be accepted.
Tenderers must ensure that they have provided Tender Number 02 /2013 signed copies of their Tender
(one to be marked “ORIGINAL” and bound, the other(s) to be marked “COPY”. Any brochures or pamphlets
must be attached to both the original and the copies.
All copies must be bound, and the original must be unbound and clipped (not stapled). All pages must be
numbered consecutively and the Tender must include an index.
PART 1 READ AND KEEP THIS PART
REJECTION OF TENDERS
A Tender will be rejected without consideration of its merits in the event that:
(a) it is not submitted before the Deadline; or
(b) it is not submitted at the place specified in the Request; or
(c) it may be rejected if it fails to comply with any other requirements of the Request.
LATE TENDERS
Tenders received:
(a) after the Deadline; or
(b) in a place other than that stipulated in this Request;
will not be accepted for evaluation.
ACCEPTANCE OF TENDERS
Unless otherwise stated in this Request, Tenders may be for all or part of the Requirements and may be
accepted by the Principal either wholly or in part. The Principal is not bound to accept the lowest Tender
and may reject any or all Tenders submitted.
DISCLOSURE OF CONTRACT INFORMATION
Documents and other information relevant to the contract may be disclosed when required by law under
the Freedom of Information Act 1992 or under a Court order.
All Tenderers will be given particulars of the successful Tenderer(s) or advising that no Tender was
accepted.
TENDER VALIDITY PERIOD
All Tenders will remain valid and open for acceptance for a minimum period of ninety (90) days from the
Deadline or forty-five (45) days from the Council’s resolution for determining the Tender, whichever is the
later unless extended on mutual agreement between the Principal and the Tenderer in writing.
PRECEDENCE OF DOCUMENTS
In the event of there being any conflict or inconsistency between the terms and conditions in this Request
and those in the General Conditions of Contract, the terms and conditions appearing in this Request will
have precedence.
PART 1 READ AND KEEP THIS PART
REGISTRATION OR LICENSING OF CONTRACTORS
Where an act or ordinance of the state of Western Australia requires that a Contractor (as defined by the
act or ordinance) be registered or licensed to carry out the work described in the Request documents, the
Tenderer shall state on the Tender Form in the space provided, its registration or license number.
The Tender may not be considered if the Tenderer fails to provide such registration or license number.
ALTERNATIVE TENDERS
All Alternative Tenders may be accompanied by a conforming Tender.
Tenders submitted as Alternative Tenders or made subject to conditions other than the General and Special
Conditions of Contract must in all cases arising be clearly marked “ALTERNATIVE TENDER”.
The Principal may in its absolute discretion reject any Alternative Tender as invalid.
Any printed “General Conditions of Contract” shown on the reverse of a Tenderer’s letter or quotation
form will not be binding on the Principal in the event of a Contract being awarded unless the Tender is
marked as an Alternative Tender.
TENDERERS TO INFORM THEMSELVES
Tenderers will be deemed to have:
(a) examined the Request and any other information available in writing to Tenderers for the purpose of tendering;
(b) examined all further information relevant to the risks, contingencies, and other circumstances having an effect on their Tender which is obtainable by the making of reasonable enquires;
(c) satisfied themselves as to the correctness and sufficiency of their Tenders including tendered prices which will be deemed to cover the cost of complying with all the Conditions of Tendering and of all matters and things necessary for the due and proper performance and completion of the work described therein;
(d) acknowledged that the Principal may enter into negotiations with a chosen Tenderer and that negotiations are to be carried out in good faith; and
(e) satisfied themselves they have a full set of the Request documents and all relevant attachments.
ALTERATIONS
The Tenderer must not alter or add to the Request documents unless required by these Conditions of
Tendering.
The Principal will issue an addendum to all registered Tenderers where matters of significance make it
necessary to amend or supplement the issued Request documents before the Deadline.
PART 1 READ AND KEEP THIS PART
RISK ASSESSMENT
The Principal may have access to and give consideration to:
(a) any risk assessment undertaken by any credit rating agency;
(b) any financial analytical assessment undertaken by any agency; and
(c) any information produced by the Bank, financial institution, or accountant of a Tenderer;
so as to assess that Tender and may consider such materials as tools in the Tender assessment process.
Tenderers may be required to undertake to provide to the Principal (or its nominated agent) upon request
all such information as the Principal reasonably requires to satisfy itself that Tenderers are financially viable
and have the financial capability to provide the Services for which they are submitting and to otherwise
meet their obligations under any proposed Contract. The Principal reserves the right to engage (at its own
cost) an independent financial assessor as a nominated agent to conduct financial assessments under
conditions of strict confidentiality. For this assessment to be completed, a representative from the
nominated agent may contact you concerning the financial information that you are required to provide.
The financial assessment is specifically for use by the Principal for the purpose of assessing Tenderers and
will be treated as strictly confidential.
EVALUATION PROCESS
This is a Request for Tender.
Your Tender will be evaluated using information provided in your Tender.
The following evaluation methodology will be used in respect of this Request:
(a) Tenders are checked for completeness and compliance. Tenders that do not contain all information
requested (eg. completed Offer form and Attachments) may be excluded from evaluation.
(b) Tenders are assessed against the Selection Criteria. Contract costs are evaluated, eg tendered prices
and other relevant whole of life costs are considered.
(c) The most suitable Tenderers may be short listed and may also be required to clarify their Tender,
make a presentation, demonstrate the product/solution offered and/or open premises for
inspection. Referees may also be contacted prior to the selection of the successful Tenderer.
A Contract may then be awarded to the Tenderer whose Tender is considered the most advantageous
Tender to the Principal.
PART 1 READ AND KEEP THIS PART
SELECTION CRITERIA
The Contract may be awarded to either a sole or group of Tenderer(s) who best demonstrates the ability to
provide quality products and/or services at a competitive price. The tendered prices will be assessed
together with qualitative and compliance criteria to determine the most advantageous outcome to the
Principal.
The Principal has adopted a best value for money approach to this Request.
This means that, although price is considered, the Tender containing the lowest price will not necessarily be
accepted, nor will the Tender ranked the highest on the qualitative criteria.
A scoring system will be used as part of the assessment of the qualitative criteria. Unless otherwise stated,
a Tender that provides all the information requested will be assessed as satisfactory. The extent to which a
Tender demonstrates greater satisfaction of each of these criteria will result in a greater score. The
aggregate score of each Tender will be used as one of the factors in the final assessment of the qualitative
criteria and in the overall assessment of value for money.
COMPLIANCE CRITERIA
These criteria are detailed within Part 5 of this document and will not be point scored. Each Tender will be
assessed on a Yes/No basis as to whether the criterion is satisfactorily met. An assessment of “No” against
any criterion may eliminate the Tender from consideration.
QUALITATIVE CRITERIA
In determining the most advantageous Tender, the Evaluation Panel will score each Tenderer against the
qualitative criteria as detailed within Part 5 of this document. Each criterion will be weighted to indicate
the relative degree of importance that the Principal places on the technical aspects of the goods or services
being purchased.
It is essential that Tenderers address each qualitative criterion. Information that you provide addressing
each qualitative criterion will be point scored by the Evaluation Panel. Failure to provide the specified
information may result in elimination from the tender evaluation process or a low score.
PRICE CONSIDERATIONS
The non-weighted cost method is used where functional considerations such as capacity, quality,
transitional and adaptability are seen to be crucial to the outcome of the contract. The evaluation panel will
make a series of value judgements based on the capability of the Tenderers to complete the Requirements
and a number of factors will be considered including:
(a) the qualitative ranking of each Tenderer; and
(b) the pricing submitted by each Tenderer.
PART 1 READ AND KEEP THIS PART
Once the tenders have been ranked, the evaluation panel will make a value judgement as to the cost
affordability, qualitative ranking and risk of each Tender, in order to determine the Tender which is most
advantageous to the Principal.
The tendered price will be considered along with related factors affecting the total cost to the Principal. eg
the lifetime operating costs of goods or the Principal’s contract management costs may also be considered
in assessing the best value for money outcome.
REGIONAL PRICE PREFERENCE
Tenderers for these works may be afforded a preference in accordance with Regulation 24A-G of the Local
Government (Functions and General) Regulations and Perenjori Shire Policy Number 4008 – “Buy Local
Policy”, adopted 18th June 2009.
The Policy stipulates that local preference may be afforded:
To contribute to regional sustainability by supporting local businesses; and
To provide the best value for money for the Shire of Perenjori.
PRICE BASIS
All prices for goods/services offered under this Request are to be fixed for the term of the Contract.
Tendered prices must include Goods and Services Tax (GST).
Unless otherwise indicated prices tendered must include delivery, unloading, and all applicable levies,
duties, taxes and charges. Any charge not stated in the Tender, as being additional will not be allowed as a
charge for any transaction under any resultant Contract.
OWNERSHIP OF TENDERS
All documents, materials, articles and information submitted by the Tenderer as part of or in support of a
Tender will become upon submission the absolute property of the Principal and will not be returned to the
Tenderer at the conclusion of the Tender process PROVIDED that the Tenderer be entitled to retain
copyright and other intellectual property rights therein, unless otherwise provided by the Contract.
CANVASSING OF OFFICIALS
If a Tenderer, whether personally or by an agent, canvasses any of the Principal’s Commissioners or
Councillors (as the case may be) Officers with a view to influencing the acceptance of any Tender made by
it or any other Tenderer, then regardless of such canvassing having any influence on the acceptance of such
Tender, the Principal may at its absolute discretion omit the Tenderer from consideration.
IDENTITY OF THE TENDERER
The identity of the Tenderer and the Contractor is fundamental to the Principal. The Tenderer will be the
person, persons, corporation or corporations named as the Tenderer in Part 5 and whose execution
appears on the Offer Form in Part 5 of this Request. Upon acceptance of the Tender, the Tenderer will
become the Contractor.
PART 1 READ AND KEEP THIS PART
COSTS OF TENDERING
The Principal will not be liable for payment to the Tenderer for any costs, losses or expenses incurred by
the Tenderer in preparing their Offer.
TENDER OPENING
Tenders will be opened in the Principal’s offices, following the advertised Deadline. All Tenderers and
members of the public may attend or be represented at the opening of Tenders.
The names of the persons who submitted a Tender by the due Deadline will be read out at the tender
opening. No discussions will be entered into between Tenderers and the Principal’s officers present or
otherwise, concerning the Tenders submitted.
The Tender opening will be held on as soon as practicable after the Deadline at Perenjori Shire Office, 40
Fowler Street, Perenjori.
IN-HOUSE TENDERS
The Principal does not intend to submit an in-house Tender.
PART 2 READ AND KEEP THIS PART
SPECIFICATION
CONTRACT REQUIREMENTS IN BRIEF
The requirement for this project is the conversion of an existing up-fronted steel shed structure into
enclosed workshop premises.
A full statement of the goods and/or services required under the proposed contract appears in the
Specification.
DEFINITIONS
Below is a summary of some of the important defined terms used in this Part:
Contractors
Representative:
Means any Officer or person duly authorised by the Contractor, in writing, to
act on its behalf for the purpose of the Contract;
Principals Representative: Means any Officer or person duly authorised by the Principal, in writing, to act
on its behalf for the purpose of the Contract;
Works or Services: Means the Services, which the Contractor is required to provide to the Principal
and the Contractor under the Contract;
INTRODUCTION
The conversion of the existing up-fronted steel shed is for the purpose of developing business tenancy units
to provide an opportunity for small businesses that are either newly created or new to the region to be
able to set up a facility from which to operate that can then be configured to meet their business needs.
BACKGROUND INFORMATION
The Perenjori Business incubator centre is aligned with the Perenjori Shire’s strategic development object Area 2
– Industry and Business Development – Our Economy goal “Fostering and maximizing growth across the
economy, embracing opportunities for diversifying and strengthening our economic base.”
In May 2010, a workgroup was formed with the title of “Leaving a Legacy” was held in Perenjori to discuss the
future opportunities being presented by the investments being made by the mining industry in the Midwest and
actions were developed by key regional, state organization’s and private enterprise to ensure that the Midwest
regional councils were supported in strategic decisions to ensure that the appropriate funding and investments
were being made to support the potential growth within the area.
The results of the “Economic Development Strategy” report completed by Pracsys in 2006 demonstrated that
given the number of mining development projects within the Shire of Perenjori which outlined a modeling plan
for the development of housing, infrastructure and businesses to meet the needs and estimated growth as a
result of the investment being made by the mining & exploration companies. (Pracsys, July, 2006)
The Perenjori Shire Council during this time were going through the decision making process of identifying how
they could provide support to the upcoming projects to ensure that key activities were able to progress in relation
to the construction activities whilst also considering what other activities the Perenjori shire could undertake to
provide further economic support to their community and regional business partners.
PART 2 READ AND KEEP THIS PART
At this stage the development of industrial land was proposed and the major mining construction project for
Karara Mining commenced with a commitment to supporting local businesses which has resulted in more than
fifteen (15) local (Perenjori based) business’s and community services having benefited from the opportunities
that have arisen from this one project.
The results of the ABS (Australian Bureau of Statistics) national census conducted in 2011showed that the
population growth in Perenjori from 2006 until 2011 had developed at a rate of 4.2%, this exceeds all of our
neighbouring shires. Additionally, research conducted by Pracsys in 2006 demonstrated that the average
expenditure for households within the Shire of Perenjori is set to increase by more than 20% each year, which is
4% higher than the national average. (Summary of Results – Household Expenditure, ABS, 2011)
Further research was conducted in 2012with results showing the following;
Improved / Increased number of retail options
Opportunities for new enterprises
Business Support / Training
Workforce development / training
Industrial area with office space provided
Even though the local businesses have experienced growth resulting in the need for an increased number of
personnel, the actual number of businesses located within the town of Perenjori has seen almost no change since
2006.
A business incubator centre provides an opportunity for suppliers / vendors to be closer to their clients to be able
to service their needs more effectively, as well as the development of new industry in our region which can
support the community and the mining and agricultural industries. Business Incubator centre’s have been proven
to provide an increase 20 times more jobs than community infrastructure projects (US Department of Commerce
Economic Development Administration, 2009)
The development of opportunities for new businesses to be located within the Perenjori business district can
provide the following benefits;
Improved response times to reduce the impact on business and the community groups
Improved social well-being through confidence in service levels meeting demands
SCOPE OF WORK
Site Preparation
1. Locate and isolate services through site;
2. Remove existing transportable ablution building;
3. Liaise with plumber regarding isolation of hydraulic services to transportable;
4. Remove vegetation to works area;
5. Remove sections of fencing as required;
6. Break up and remove bitumen as required;
PART 2 READ AND KEEP THIS PART
7. Break up and remove or lift concrete paving;
8. Cut back concrete paving to crossover;
9. Cut back to neat lines paving to remain;
10. Remove asbestos cement fencing as drawn;
11. Liaise with electrician regarding isolation and removal of electrical items;
12. Remove framed room structures from within existing building.
13. Remove RAC air-conditioners from walls;
Hydraulics
1. Locate existing water service to existing ablution building and tee off and extend service to individual
tenancies and to new ablution block;
2. Locate existing sewer service to existing ablution building and extend to new tenancy facilities and to new
ablution;
3. Supply and install spoon drains to downpipes;
4. Supply and install new soak-wells;
5. Supply and install 100mm PVC stormwater pipe secured to rear of shed to collect and Dis-charge
stormwater from the roof downpipes;
6. Supply and install trough and tap-ware to each tenancy;
7. Supply and install standpipe to each tenancy;
8. Supply and install new fixtures and fittings to ablution block;
9. Supply and install new drainage channel ad grate at thresholds;
10. Supply and install new drains to ablution block;
11. Supply and install materials and equipment required to connect new buildings to existing septics;
12. Supply and install materials and equipment required to connect new buildings to watersupply;
13. Supply and install approved RPZ valve onto main water service to site;
14. Supply and install road grates and soak-wells;
Bituminous Concrete Paving
1. Prepare sub base for areas to be bitumen paved;
2. Supply and lay compacted road base;
3. Construct non-mountable concrete kerbs as drawn;
4. Supply and lay bituminous concrete paving;
5. Provide line marking as drawn;
PART 2 READ AND KEEP THIS PART
Masonry Unit Paving
1. Supply and lay masonry unit pavers as drawn;
Concrete and Concrete paving
1. Supply and lay in-situ concrete building slab and footings as drawn;
2. Construct concrete plinth to new MSSB;
3. Provide concrete footings to fences and gates as required;
Structural Steel
1. Fabricate and install steel columns to building front elevation;
2. Fabricate and install miscellaneous steel brackets and cleats as required;
Metalwork
1. Supply and install roller shutters to tenancies;
2. Supply and install fixtures and fittings to toilets;
3. Supply and install palisade fencing where drawn;
4. Supply and install Colorbond sheet fencing where drawn;
Carpenter and Joiner
1. Supply and install wall framing to front elevations as drawn;
2. Supply and install exterior cladding as drawn;
3. Supply and retro-fit insulation to existing shed walls and roof;
4. Supply and install insulation to new walls;
5. Construct wall and roof framing to new ablution block;
6. Supply and install exterior and interior linings to new ablutions;
7. Supply and install new doors and frames to tenancies and ablutions;
8. Supply and install wall framing between tenancies;
9. Supply and install fibre-cement lining over plasterboard to dividing walls;
Roofer
1. Supply and install new full wall sheets to replace those with holes from removed services;
2. Supply and install new exterior metal cladding to building as drawn;
Glazier
1. Supply and install aluminium door frames;
2. Supply and install new windows to ablution block;
Plasterboard
1. Supply and install new fire rated wall sheets to dividing walls;
PART 2 READ AND KEEP THIS PART
Painter
1. Prepare and paint existing steelwork to shed (excluding purlins and girts);
2. Prepare and paint new steelwork to shed;
3. Prepare and exterior fibre-cement cladding (allow for 4 colours);
4. Prepare and paint interior lining;
5. Prepare and paint doors and frames;
Electrical (refer Appendix A)
1. Remove electrical services to existing building;
2. Supply and install new MSSB;
3. Liaise with Western Power regarding upgrade of site power supply and new dome;
4. Supply and install new load centres to tenancies;
5. Supply and install new power circuits as drawn;
6. Supply and install new lighting circuits and fittings as drawn;
7. Extend communications service from existing MDF system as drawn;
PART 2 READ AND KEEP THIS PART
SPECIFIC REQUIREMENTS OF THE CONTRACT
2.1 - EXCAVATION
PART I - SITE PREPARATION
Scope
The work of this section comprises but is not limited to excavation, disposal of surplus excavated material both on
and off the site, supply of compaction and filling material and the preparation necessary to bring the areas to
correct shape and level prior to building construction, and as per Scope.
Supply and installation of waterproofing membrane.
Sleeves under paving
Liaison with Hydraulics regarding excavation and installation of soakwells and plumbing beneath Paving
Related Work
Co-ordinate and co-operate with the following trades:
Transportable Building Contractor
Hydraulics
Electrical
Concretor
Provide a rate per cubic metre for rock excavation and removal.
Quality Assurance
Provide data indicating that the tradesmen engaged for this project have a minimum of three years' experience in
such work required by this Specification. Supply names of contacts, with telephone numbers, who can verify
performance quality.
References
AS 1289.0 2000 Methods of testing soils for engineering purposes.
There are many parts to this Standard, 1995 - 2007; each refers to a specific application.
AS1289.5.1.1 2003 Soil compaction and density tests.
AS 2187 Explosives - Storage, transport and use. (2187.0 2187 .2 1998-2006).
AS 3798 2007 Guidelines on earthworks for commercial and residential developments.
AS/NZS 4200 1994 Pliable building membranes and underlays. There are 2 parts to this Standard.
AS 4678 2002 Earth-retaining structures.
Comply with particular specifications in Building Regulations and/or Local Council publications.
PART 2 READ AND KEEP THIS PART
Definitions:
Rock: natural or artificial material encountered in the excavation which cannot be removed until broken up by
mechanical means such as rippers, jack-hammers or percussion drills.
Rippable Rock: Means rock which can be removed by a single tine, “D9” ripper.
Non-Rippable Rock: Means all other rock. Other than Rock: other material encountered in excavation.
Sub-Grade: The natural ground below the excavations. Filling: A general term for material spread and compacted
over the sub-grade to make up levels to the underside of the base.
Sub Base: Selected filling spread and completed over sub-grade to compacted over sub-grade to make up levels
to the underside of the base. Base: A selected filling layer spread and compacted to form an acceptable working
surface directly under the building.
Comply throughout with the current edition of the Building Code.
Approval for Variations
Before starting excavation work which may involve a variation (whether addition or deduction) because of the
nature of the material to be excavated, obtain a determination as to the nature from the Architect. The variation
is derived from the determination. If no prior determination has been obtained, the variation, if any, is to be
made only at the Architect's discretion.
Use of Explosives
Do not use Explosives.
Provisional Depths
The footing or strip depths shown on the Drawings are provisional.
Approval of the relevant Building Surveyor and Architect is required for actual depths on the site. If there have
been variations to the Contract levels or dimensions of excavations, do not commence back-filling or place
permanent work in excavations until the Architect has made measurements and approved them.
Site Management
Inspection:
Give the Architect at least one working day's notice that the following are ready for inspection:
1. Rock encountered in the excavations
2. Excavation completed to Contract levels
3. Filling completed to Contract levels
4. Completed placement of waterproof membrane
Excess Excavation
Excessive excavation and consequent backfilling and compacting may not be claimed as a reason for extra
payment.
PART 2 READ AND KEEP THIS PART
PART II - MATERIALS
Termite Control
Supply approved mechanical termite shields or natural ethical substances in accordance with supplier's
recommendations. Comply with AS 3660 in selecting appropriate material.
Filling
Bring filling on to the site unless it can be provided from spoil recovered from the site. Filling is to be sound
material, free of perishable material, or material that will form stable fill, but subject always to Architect's
approval.
Fill generally as required or as shown on the Drawings, and as follows:
Under concrete floor slabs cast on ground:
First 50mm below slab: sand blinding.
Remainder: approved excavated material for non-suspended slab.
Back-fill: approved excavated material unless otherwise specified.
To retaining walls or walls below grade: free draining granular material.
Sand Pit – Approved coarse washed white sand.
The filling types are as follows:
Approved Excavated Material: The best of the clean inorganic excavated material, approved by the Architect.
1. Hardcore: Clean hard filling such as broken brick or stone rubble, consolidated in position.
2. Porous Filling: Hard core graded from 40mm to 15mm.
Sand: Salt free, loam free, packing quality
Fine Crushed Rock: 15 to 5mm clean crushed rock.
3. Refer Clause 307.
Water-proof Membrane
Approved flexible poly-metric film 0.2mm thick. Deliver underlays to the site in suitable protective packaging,
bearing the name of the manufacturer. Handle and store the underlay so that it is not punctured, torn or
otherwise damaged. Comply with AS/NZS 4200.
PART III – EXECUTION
Examine Conditions
Start of work means total acceptance of conditions.
Excavations Generally
A. Suspend ground works during inclement weather which would result in unsatisfactory work.
B. Excavate accurately to shape and profile and keep free from loose earth and stones.
PART 2 READ AND KEEP THIS PART
C. Excavate generally as required or as shown on the Drawings, including but not necessarily limited to the
following :
Removal of footings and unnatural items to 900mm below grade.
Preparation of sub-grade as necessary. Refer Clause 107.
D. Trim the sub-grade surface evenly to the profiles shown on the Drawings.
E. Make allowance for settlement and compaction.
F. Allow for falls in slabs on grade to streets, lanes and outlets.
G. Prepare for underground services, referred to in other Sections of the Specification.
H. Prepare for strip footings, footing beams, pad footings, ducts and pits, to depths shown.
I. Carry out additional excavation where necessary to permit full use of suitable mechanical equipment (eg.
rippers) and back-fill with appropriate material as specified in this Section.
J. Where excavation exceeds the required depth, fill back to correct depth with material as follows :
below slabs on ground: Hardcore.
below footings, beams and other structural elements : Concrete of strength equal to the
structural element, minimum 15MPa.
Bad Ground
Should unsuitable material be encountered at the prescribed depths of excavation, or soft, wet and unstable areas develop during excavation, obtain instructions from the Architect before carrying out additional excavations. Back-fill and compact to the correct levels as directed. If the Builder has not caused or contributed to the above conditions and if the occurrence could not have been anticipated at the date of the Builder's tender, the Builder may claim for a variation.
Existing Services
Locate existing services.
Shoring
Provide shoring, planking and strutting necessary to retain the sides of the excavations and to ensure safe working. Provide safety covers over holes. Provide necessary needling, shoring and strutting to adjacent buildings. If in the opinion of the Architect support provided is insufficient he may order the provision of additional support. No instruction relieves the Builder of sole responsibility for the sufficient support of the excavation. Guard against the formation of voids outside sheeting or sheet piling if used and should voids form, fill and consolidate them to approval.
Filling Schedule
Fill generally as required or as shown on the drawings, and as follows:
Under concrete floor slabs cast on ground:
First 50mm below slab: sand blinding.
PART 2 READ AND KEEP THIS PART
Remainder: 100mm compacted sand for non-suspended slab.
To retaining walls or walls below grade: free draining granular material.
Bearing Surfaces in Rock
Where structural loads bear on rock, unless otherwise specified, scabble the rock face to give even plane bearing surfaces, level unless required to be sloping or stepped. Bored pier holes are to be taken a minimum of 150mm below the rock surface and the bottoms cleaned of loose matter.
Compaction
Place filling in layers not exceeding 150mm deep when measured loose.
Bring filling to optimum water content by watering, and compact each layer thoroughly and uniformly with a
vibrating roller where practicable.
Hand tamp against ground or perimeter beams or walls.
Compact each layer of filling to obtain a uniform density of not less than 95% of the maximum density at
optimum moisture content as determined by the Dry Density/Moisture Content tests set out in AS 1289.
Finish the base to the following tolerances:
Variation from designed level : 5mm
Variation from 3000mm straight edge : 5mm
Waterproof Membrane
Lay on approved sand blinding - Refer Clause 307. Where necessary, cut sheets to maximum practical width, to
suit the layout, and arrange laps to face away from the direction of the pour.
Provide laps as recommended by the manufacturer, but not less than 200mm. Seal laps with pressure adhesives
or tapes as recommended by the manufacturer of the underlay and ensure that the adhered surface of the
underlay is dry and clean.
Take the underlay up walls to level of top of future concrete slab or as otherwise instructed. Seal service pipes
and similar elements when they penetrate the underlay. Allow ample slack to avoid pulling at tape junctions.
Cover vertical or inclined surfaces in an unbroken sheet where possible. Otherwise arrange laps vertically to avoid
pulling at joints. Fix at the top with tape or other recommended fixing.
Inspect membrane after laying and before concrete is poured. Patch and seal punctures.
Maintain the membrane or underlays in their best possible condition throughout the construction period.
Repair immediately, to the approval of the Architect, damage which does occur.
Clean Up
On completion of work specified above, remove surplus materials imported to the site, level off surplus excavated
material, or pile such material on the site as directed by the Architect.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
Architect.
PART 2 READ AND KEEP THIS PART
2.2 - HYDRAULICS
PART I GENERAL - HYDRAULICS
Scope
Supply labour and materials, services and equipment necessary for the preparation, application and finishing of
items as indicated on Drawings, schedules and as specified herein and as listed within the Scope.:
Locate existing water service to existing ablution building and tee off and extend service to individual tenancies
and to new ablution block;
Locate existing sewer service to existing ablution building and extend to new tenancy facilities and to new
ablution;
Supply and install spoon drains to downpipes;
Supply and install new soakwells;
Supply and install 100mm PVC stormwater pipe secured to rear of shed to collect and discharge stormwater from
the roof downpipes;
Supply and install trough and tapware to each tenancy;
Supply and install standpipe to each tenancy;
Supply and install new fixtures and fittings to ablution block;
Supply and install new drainage channel and grate at thresholds;
Supply and install new drains to ablution block
Supply and install materials and equipment required to connect new buildings to existing septics
Supply and install materials and equipment required to connect new buildings to water supply
Supply and install approved RPZ valve onto main water service to site.
Supply and install road grates and soakwells
Related Work
Co-ordinate and co-operate between the following trades:
A. Demolition
B. Carpenter
C. Cabinetmaker
D. Painter
Quality Assurance
Tradesmen are required to be experienced in and knowledgeable about the work to be performed and the
various standards to which the work is to comply. The Architect will make random inspections during the
execution of the work.
PART 2 READ AND KEEP THIS PART
References
Comply with applicable portions of the following Australian Standards:
AS 1273 1991 Unplasticised PVC (UPVC) downpipe and fittings for rainwater
AS/NZS 3500 National Plumbing and Drainage Code
AS 3566 1988 Screws self-drilling for the building and construction industries
The whole of the Sanitary Plumbing, Water Supply and Drainage work shall be carried out by or under the direct
supervision of a Water Corporation licensed Plumbing Contractor in direct accordance with the Water
Corporation By-Laws, AS3500 Parts 1,2,3 & 4, the requirements of the Location Authority and the requirements of
any other Authority having jurisdiction and to the entire satisfaction of the Superintendent.
Permits and Certificates
Unless otherwise specified, the Contractor shall give all necessary notices and obtain all necessary permits so that
the work hereinafter specified may be carried out and he shall furnish any certificates necessary as evidence that
the work installed conforms to the laws and regulations of all Authorities having jurisdiction before the certificate
of final payment is issued.
Delivery, Handling and Storage
Deliver to site, unload and stack in a location away from potential damage, preferably directly on to installed roof
framing. Inspect on arrival and reject bent or damaged material.
Warranty
Provide a warranty covering aspects of the installation performed by this trade, against defective materials and
workmanship for a period of five (5) years from the date of Practical Completion.
The warranty includes a statement that the whole of the work has been carried out in accordance with Australian
Standards and the instructions of the manufacturers of components in effect at the time of installation.
PART II MATERIALS
General
Materials shall be the best of their respective kind, manufactured in accordance with the relevant Australian
Standard Specification or in its absence, the relevant British Standard Specification.
All installed materials are to be tested and stamped by the Water Corporation and are to bare such stamps of
approval. All materials and products shall be as specified or similar product equivalent in function quality etc to
the approval of the Superintendents representative.
Materials
Item: WC Manufacturer Caroma Model Concorde disabled pan with Concorde dual flush cistern, Deluxe double flap seat and extended flushpipe; 15 cp mini-stop Item: Handbasin Manufacturer Caroma Model Concorde wall basin with one tap hole Item: Basin Tapware
PART 2 READ AND KEEP THIS PART
Manufacturer RAM Model Myuna single lever mixer with extended Disabled lever Item: Standpipes Model Tapware 15cp brass hose cock with removable spindle key Item: Road Grate Manufacturer Reln Model Storm Masta; 200x200; Class B grate Item: Soakwell Manufacturer Cooper Concrete or equal Model 1800dia x 1200 deep with trafficable lid or traffic lid with grate as required; provide relief vent.
PVC Pipe
P.V.C. pipes are to be rigid P.V.C. manufactured in accordance with Australian Standard Specification A.S. 1415 for soil waste and vent application and A.S. 1260 for sewer application all with compatible fittings and/or of a class required by the Water Corporation.
Fabrication
Form and fabricate components in accordance with AS 1562, AS 2179 and AS 2180, and other relevant standards. Self-drilling screws are to conform to Class 3 as described in AS 3566. All roof screws to be complete with neoprene washer/seals.
Access and Inspection/Clean Out Points
Provide all necessary cleaning access to all pipework concealed in a cavity, in ducts, etc. to the requirements of the Water Corporation whether shown on the drawings or not. Allow to inform Contractor of location of access panels in walls and access slabs in pre-cast concrete paths etc. Provide inspection points brought up to ground or floor level and terminating in cast iron box for pedestrian traffic areas, pre-cast concrete box for garden areas, solid screwed brass finish flush with floor level inside buildings, where indicated on the drawings.
PART III EXECUTION
Examination
Inspect site conditions before installation. Ensure framing is entirely satisfactory. Ensure that delivery and installation will not be impeded by on-site condition at time of delivery. Start of work means total acceptance of conditions.
Fees and Charges
Make application and pay all fees to the relevant Authority as required to obtain a CDC and Building Permit. Make application for and pay Water Corporation Headworks charges applicable to this project.
Setting Out
The pipe runs shall be set out before the pouring of concrete including providing and setting any sleeves which may be necessary to avoid cutting holes in the finished work. All prefabricated sections must be fixed in position in ample time to avoid cutting holes in the finished work. All prefabricated sections must be fixed in position in ample time to avoid delay to any other trades. The Contractor shall set out all pipe runs, sumps, outlets, etc. and check same against reinforcing steel.
PART 2 READ AND KEEP THIS PART
Should there be a need for relocating any item due to interference the builder shall obtain Superintendent approval.
Excavation
Provide all excavation and backfilling necessary for the installation of the work of this section. Bottoms of trenches shall be excavated so that piping will be supported on a solid bed of undisturbed earth and/or made up compacted earth compacted to eight blows per 300 on a penetrometer with additional excavation under the joints to permit the joint to be properly made up. All backfilling outside the buildings, except as noted, shall be done with selected excavated sands, containing no large stones to a depth of 300 above crown of pipe and with unselected sands for the balance of the depth. Backfilling shall be done in 300 layers, thoroughly watered and compacted to six blows per 300 on a penetrometer. The first 600 of all backfill over drains shall be hand compacted. Large boulder, rubbish etc. shall not be used for backfilling and shall be removed from the site and approved earth shall be brought in for use in this event. Backfilling around manholes and catch basins shall be in all cases done with the same materials to the same depth as connecting piping.
Preparation and Execution
Refer drawings for locations of services under new buildings. Locate and identity existing services. Co-ordination with all other trades to ensure that problems arising from possible collision of work are solved before the work is installed. Shut off existing services to connect new services at times agreed to in writing by the Architect and two working days written prior notification of shut downs shall be given to the Architect. Shut down times shall be kept to a minimum and notification shall include length of time required for services to be shut. Locate existing services as necessary. Services to all existing fixtures and outlets and connections which are required shall be maintained throughout construction period. Provide temporary services as necessary. Where required cut and seal existing services and remove redundant pipework as directed and make good to building and existing work and match adjacent finishes. Any existing services shown on the drawings are indicative only and are not complete. Make allowance to locate services on site and excavate by hand where necessary to avoid causing damage to services. The Plumbing Contractor shall suitably allow for locating the existing services, which under this contract require diversion, connection to and upgrading, within a six (6) metre radius and or 600mm depth from that indicated on the drawings and as the case may be.
Property Sewer
All new property sewers are to be U.P.V.C. to AS1260 as previously specified and/or to type of material where indicated on the drawings. Property sewer installed at depths greater than 4.0 metres shall be constructed of S.E.H. UPVC. Provide and install all necessary inspection openings, clean outs, manholes etc. to Water Corporation regulations. Extend new property sewer as required and connect to existing property sewer in location as indicated on the
PART 2 READ AND KEEP THIS PART
drawings. Exact size, depth, location and material type of existing property sewer shall be determined and physically confirmed on site prior to the commencement of any work to ensure connection can be achieved.
Waste Pipes and Tundishes
Provide and install waste pipes of sizes and located in positions as indicated on the drawings. Connect waste pipes to fixture outlet traps and extend to combine with floor waste gullies, vented graded pipes or dis-connector gullies.
Waste pipes shall be constructed of the following :
A. Exposed externally - UPVC B. Concealed externally - UPVC/HDPE
Vent Pipes
All vent pipes shall be of U.P.V.C., SWV class unless otherwise specified on drawings. Provide and install all vents of sizes shown on drawings, complete with all bends, junctions and reducers. Provide vent offsets where necessary. Vent pipes shall terminate 3 metres from extract fans or openings into the building and 5 metres from intake fans. Provide expansion joints and appropriate anchors to all continuous vent risers, in accordance with requirements of the Water Corporation. Vent pipes shall be extended to 150mm above metal deck roofs and be fitted with ‘Dektite’ formed rubber flashing secured and sealed to roof. Terminate vent risers at Water Corporation approved proximity to windows/parapets/all intakes etc. and at correct height, fitted with mosquito proof cowl.
Cold Water Service
Provide and install copper water service and connect to all fixtures requiring water. All cold water service branches shall be a minimum diameter of 15 for one outlet and 20 for two outlets or more. All cold water pipes concealed in cavities, chased into brickwork, cast into concrete or laid below ground shall be installed as previously specified under ‘Concealment of Pipework’. Water Service pipework shall be as follows :-
IN-GROUND 15 and 20 diameter inclusive Copper Type ‘B’ to AS 1432 25 to 80 diameter inclusive - Poly PN12 Blueline All sizes below slab - Copper Type ‘B’ to AS 1432.
EXPOSED AND ABOVE GROUND 15 diameter and over - Copper Type ‘B’ to AS 1432 Isolating valves are to be fitted by screwing to a tube bush brazed to the pipe on the inlet and a flare type boiler union on the outlet side. Stop valves must not be brazed to a pipe except in the case of concealed assemblies. Where pipes terminate in walls, e.g. at taps or outlets, a suitable anchor is to be brazed to the pipe and securely cemented into the wall.
PART 2 READ AND KEEP THIS PART
Isolating valves in the ground are to be fitted with a GALVINS cast iron valve box with hinged lid and set on brickwork built up from the pipe and with lid finishing flush with ground or paving level. The entire cold water installation shall be subject to a hydrostatic pressure test of 2000 Kpa as set out by the Water Corporation. Locate existing cold water service and connect new branch lines complete with isolating valves in locations indicated drawings. Exact size, depth, location and material type of existing cold water service shall be determined and physically confirmed on site prior to the commencement of any work to ensure connection can be achieved. Any discrepancy shall be reported immediately to the Superintendent for further action. Extend new main in size and location indicated to isolating valves. Extend pipework from isolating valves and connect to all fixtures and outlets as noted and as required. Provide and install backflow prevention valves in locations indicated.
Storm Water
100 diameter - sewer class UPVC with solvent weld joints.
Provide and install stormwater drainage as indicated on drawings and connect to all downpipes,
sumps, manholes, sand traps, soakwells etc.
External downpipes shall discharge over a drains as specified.
Provide and install soakwells in locations and as detailed on the drawings.
Adjustments, Cleaning, Finishing and Protection
A. Finish the work specified in this Section and remedy anything not finished prior to completion. Adjust to achieve a uniform appearance. Remove handling marks from visible surfaces.
B. Protection: Do everything needed to ensure that work is without damage or deterioration at Practical Completion.
Testing
All pipework is to be tested at regular intervals or as required during the progress of the work. Carry out all testing required by the Water Corporation Local Authority and other Authorities having jurisdiction over the work. Sections of work not covered by Authorities shall be tested to the satisfaction of the Superintendent as specified hereafter. Provide all equipment necessary to satisfactorily perform each testing operation and provide all personnel requested by the Authority or the Superintendent to assist in executing tests.
As Constructed Documentation
Provide “As Constructed” drawings as computer data in AutoCAD Version 2008 (or later) format on CD in addition to bond copies of A3 sized reductions for inclusion in each Hydraulics Operating Manuals. The “As Constructed” drawings shall be documented in accordance with the BMW CAD Documentation Procedures Manual. Mark up plans as pipe work is installed, clearly indicating dimensions of all pipework and valves with their respective alignments, depths and invert levels from fixed reference points prior to backfilling trenches.
PART 2 READ AND KEEP THIS PART
These marked up drawings are to be kept on site for regular inspection by the superintendent and/or consultant.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the Architect.
2.3 BITUMINOUS CONCRETE PAVING
PART I GENERAL
Scope
Supply and install a complete installation of bituminous concrete paving including but not limited to:
A. Excavation B. Preparation of sub-grade C. Base courses, laying and compaction D. Kerbing E. Bituminous concrete surfacing F. Lane marking
Related Work
Co-ordinate and co-operate with the following trades:
A. Site Preparation - Excavation B. Sanitary Sewerage C. Storm Drainage D. Concrete Pavement
Quality Assurance
Provide data indicating that the tradesmen engaged for this project have a minimum of five years of experience in such work as required by this specification. Supply names of contacts, with telephone numbers, who can verify performance quality.
References
AS 2150 2005 Hot mix asphalt – A guide to good practice. AS 2758 Aggregates and rock for engineering purposes. AS 2876 2000 Concrete kerbs and channels (gutters) - Manually or machine placed. AS 4049 Paints and related materials - Pavement marking materials. AUSTROADS Supplies a range of technical bulletins. Where relevant, comply with Standards of pavement construction as available from State Road Construction authority. Comply throughout with the current edition of the Building Code.
PART II MATERIALS
Pavement Construction Materials
Comply with the material specification of the appropriate State Road Construction authority. Such specifications define materials required for various classes of load capacity.
PART 2 READ AND KEEP THIS PART
The appropriate specification is :
Sub-base: Sub-base material: clean, clay free gravel or crushed rock (may be limestone) – 150mm minimum compacted thickness to car parking and 200mm compacted thickness to main driveway, rear apron and access to rear apron. Prime coat: Bitumen Emulsion, minimum 60% bitumen content Hot Mix Asphalt: to comply with AS 2150
a) nominal mix size 5mm b) binder: Bitumen c) binder content – 6% d) minimum thickness 20mm to car parking and front access drive. 25mm thickness to main drive,
rear apron and access to rear apron, and street crossover.
Lane Marking
Approved roadwork line marking paint.
Kerbing
25 mpa concrete manufactured in accordance with AS 3600 with 10mm aggregate and with 50mm slump. Kerb to line with and match existing where applicable at existing road kerb.
Equipment
Provide and employ equipment required for satisfactory completion of the work.
PART III EXECUTION
Examination
Inspect the site. Determine conditions and ensure that suitable conditions exist at the time of start of work. Prevent delay in job schedule. Start of work means total acceptance of conditions.
Preparation
Remove surface material to required depth. Test compaction capacity of natural material. Fill soft spots with crushed rock to required compaction. Shape to specified falls. Allow for installation by other trades of drainage and other items.
Installation of Base Course
Comply with state road construction authority, Spec No. [ ] See clause 201 above or spread base course material in layers between 100 and 150mm thick. Compact to 100% of standard maximum dry density with minimum 10 tonne roller. Employ a vibrating roller as necessary. Maintain damp condition of material until seal is applied. Employ 15 tonne roller for final compaction.
Testing
Allow for three separate compaction density tests to be conducted in random locations by a NATA approved testing organisation. Should tests prove unsatisfactory, repair the work and repeat tests to a satisfactory result without cost to the Proprietor.
Pavement Courses
Finish pavement courses consisting of layers of wet-mix crushed rock to smooth and uniform surfaces and conform to the lines, grades and cross sections shown on the drawings, within the following limits:
A. Level: the top of each pavement course: within 10 mm of level shown on drawing. B. Thickness: of the top course of the wet mix pavement: within the tolerance of +5, -10mm.
PART 2 READ AND KEEP THIS PART
C. Shape: finished surface of the pavement course: within 10mm either way from a 3 metre straight-edge
laid parallel to the centre line of the pavement or from a template placed at right angles to the centre-line.
Prime Coat
Prime with cut back bitumen suitable for the surface of base material and prevailing weather conditions. Apply in compliance with state authority specification.
Tack Coat
If required, apply tack coat to clean dry surface. Consulting engineer will determine necessity for this item. Apply in compliance with state authority specification.
Bituminous Concrete
Prepare adjacent surfaces such as longitudinal joints, kerbs, channels, headers, manholes, etc. with a thin uniform tack coat. Install bituminous concrete with approved equipment in suitable climatic conditions. Form straight and waterproof joints with even texture and density. Compact without delay, and finish smooth and true to established grades. Thoroughly compact areas around kerbs, channels, manholes to the same density as other surfaces. Thickness of bituminous concrete is not to vary more than 7mm from that indicated on drawings. Replace low or defective areas immediately by cutting out and replacing with fresh hot mix and compacting to conform to surrounding areas. Entire area is to be free draining on completion. The finished work is not to be less than 97% of laboratory tested specified density.
Concrete Extruded Kerbing
General
Kerbs to road shall be constructed of extruded kerbing. Kerbing to smaller radii than can be placed with the extrusion machine used shall be cast insitu to the same cross section as that of the extruded kerbing, except that the cast insitu shall be 100mm deeper than the appearance of the extruded and cast insitu shall be identical.
Kerb Construction
All kerbing shall be constructed from 25 mpa, 28 day cylinder test compressive strength, concrete manufactured in accordance with AS 3600 for 10mm aggregate with 50mm slump. The final shape and dimensions of the extruded kerb shall be as detailed on the Drawings. The top surface of the kerb shall always be parallel to the ruling grade of the pavement, with gentle transitions at changes in grade. The kerb shall be placed in straight lines and in a circular curve as shown on the Drawings. The width of the road shall be the distance between the kerbs along straight sections of the road measured at right angles to the kerbs from toe to toe and shall be as detailed on the drawings. The kerbs shall be equidistant from the road centre line. At road junctions and intersections the radius or kerbing shall be measured from the roadside toe of the kerb. The kerb shall be placed using an appropriate extrusion machine, approved by the Architect and the work shall be carried out by an experienced and competent crew. The first 150mm of any new pour shall be cut away and removed. The gap between the old and new work shall be filled by hand placing, rounding and shaping of the concrete until a satisfactory shape and finish has been obtained. Extruded kerb shall be joined to existing kerbing by using the same method.
PART 2 READ AND KEEP THIS PART
Expansion Joints
Not less than 24 hours after placing of the kerb, expansion joints shall be constructed at every third contraction joint. The expansion joints shall be formed by sawing of a 10mm gap that completely severs the adjoining sections of the kerb. The gap shall be filled with approved joint filler after the Architect has inspected and approved the cut joints
Curing
Within two hours of surface finishing, all exposed faced of the completed kerb shall be protected against loss of moisture for a period of not less than 96 hours after placing by shrouding with plastic sheeting or by spraying with an approved curing compound. Calcure “D” is an approved curing compound.
Protection
Kerbs shall be protected from bitumen overspray at all times by adequately covering the kerbs with polythene sheeting or similar approved material. Any kerbing marked by bitumen spray shall be made good by the Contractor at his own expense.
Backfilling
The backfilling to kerbing shall be placed after the curing and acceptance of the kerbing. The backfill material is to be similar material to the locally occurring topsoil, free from debris and compacted adequately to accommodate the driving of rubber tyred domestic vehicles to a level to suit the required finished surfaces and level.
Cleaning Up
The Contractor shall remove any excess mortar and concrete from the road verges prior to backfilling. Dispose of offsite. Cut back bitumen, behind kerbs if required. During completion of the pavement, the contractor shall take every care to avoid damage and bitumen spillage onto the kerbs. Where damage or spillage has occurred, the Contractor shall make good this damage and remove bitumen spillages at his own expense.
Lane Marking
Comply with local authority requirements regarding sizes of parking bays and traffic control.
Mark pavement surface as instructed. Comply with AS 4049.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the architect.
2.4 FENCES & GATES
PART 1 GENERAL
Scope
Supply and install wooden fences and gates including but not limited to:
Palisade/Garrison Type Fencing
Gate construction
Metal screen Fencing
Related Work
Coordinate and co-operate with the following trades:
Bituminous Concrete Paving
Site Preparation
PART 2 READ AND KEEP THIS PART
Concrete
Quality Assurance
Submit evidence of experience appropriate to the class of work requires. Install under the direct supervision of a capable foreman with a proven background in the trade.
References
AS 1379 2007 Specification and supply of concrete. AS 1725 2003 Chain-link fabric security fencing and gates. Comply throughout with the current edition of the Building Code. Manufacturer’s printed instructions
Delivery, Handling and Storage
Deliver, handle and store products so that damage, deterioration and loss will be prevented.
Control delivery schedules to minimise long-term storage at site.
PART II MATERIALS
Material Suppliers
1. Lysaght 2. Stratco 3. IWF Fencing
Material
Item: Garrison Type Fencing – 1800mm high Concrete for post bases: 20 mpa concrete; 300dia x 800mm deep for fence posts; 400dia x 1000mm deep for vehicle gates; Posts: 65x65mm SHS (fence) Posts: 100x100mm SHS (gate) Rails: 40x40mm SHS Vertical bars: 25x25mm SHS welded to the outside of the rails to avoid rust forming on the inside of the rails Material: Hot dip Galvanised steel
Item. Metal Sheet fencing – 1800mm high Lysaght Neetascreen or equal Item. Gates Frame: Fully welded steel; hot dip galvanised finish Vertical bars: 25x25mm SHS Hinges: Heavy Duty security gate hinges Latch (bolt): Security gate slide bar with padlock rings; drop bolt and ground sleeve; provide Lockwood 334S45/538 to both new gates; provide 12 keys. Maison key with roller shutters and tenancy doors
PART III EXECUTION
Examination
Visit the site and inspect conditions. Check dimensions and compare aspects with the drawings and specification. Resolve differences before ordering materials or starting work. Start of work means total acceptance of conditions.
PART 2 READ AND KEEP THIS PART
Preparation
Consult with architect or proprietor before clearing site of the work. Obtain instructions regarding removing or retaining plants or trees existing near the new work. Construct adequate protection for plants to be retained. Prevent damage to plants. Remove from the site material not required. Consult with neighbours and reach agreement on methods of construction and access to work areas.
Installation
Establish exact location of fences and gates to be installed. Excavate for posts to required depths and in correct locations. Prepare post bases for installation with either sole plates and struts, or for setting in concrete. Set posts vertical and backfill around base. Check out posts for rails use galvanised fasteners throughout. Complete the installation as detailed.
Hardware
Install scheduled hardware for gates. Ensure correct location for latches, keepers etc and test satisfactory operation on completion.
Finishing and Cleaning
Prepare each surface scheduled to be stained or painted. Remove matter which could prevent satisfactory painting.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the architect.
2.4 CONCRETE SMALL WORKS
PART I GENERAL
Scope
Supply and install concrete and reinforcing steel for:
Footings
Floor Slab
Including but not limited to edge trim, vibrating, float screeding and curing
Related Work
Co-ordinate and co-operate with the following trades:
Site Preparation
Sewerage and Drainage
References
Comply with applicable portions of the following Australian Standards: AS 1304 1991 Welded wire reinforcing fabric for concrete AS 1379 1991 The specification and manufacture of concrete AS 2870 Residential slabs and footings 2870.1 1988 Construction (Amended 1993) 2870.1 1989 Supplement 1 1989 Construction 2870.2 1990 Guide to design by engineering principles AS 3610 1990 Formwork for concrete with Supplements 1, 2 and 3 Comply with the requirements of: Any Building Regulations applicable to the project.
PART 2 READ AND KEEP THIS PART
Delivery and Handling
Deliver concrete materials to the site in ready-mix trucks in accordance with AS 1379. Arrange and provide for concrete pumping equipment as needed. Except as otherwise directed, deliver fabrications in the same sequence as they are installed. Avoid double handling at the site, to minimise chance of damage to finishes. Co-ordinate delivery and fixing schedules to reduce use of cranes.
Warranty
Forward to the Architect a statement guaranteeing that the concrete complies with the approved mix design and that concrete has attained required strength at 28 days.
PART II MATERIALS
Formwork
Provide formwork required to meet the requirements of both Drawings and this Specification. Comply with AS 3610. Formwork for concrete.
Steel Reinforcement
A. Provide required steel reinforcement for concrete in accordance with Drawings and details thereon. Comply with relevant Australian Standards.
B. Ensure reinforcing is free from loose mill scale, rust, mud, oil, grease or other non-metallic coatings which would reduce the bond between the concrete and steel and is free from kinks or other defects, at the time of placing concrete. When there is a delay between placing the reinforcement and pouring the concrete, the Engineer may require the reinforcement to be restored to a condition satisfactory to receive concrete.
Concrete
Comply with AS 3600 Concrete Strength: 20 MPa (unless otherwise shown on Concrete Drawings) at 28 days.
PART III EXECUTION
Examination
Inspect the site and relevant conditions before installing work. Ensure conditions are satisfactory for installation. Start of work means total acceptance of conditions.
Preparation
Ensure that preparatory work of other trades is complete, including site preparation, sub-base placement, plumbing and other fittings are in place and secured, membrane and other materials are secure and complete.
Fixing Reinforcement
Place and secure in correct location, reinforcement in accordance Standards.
Build In
Install and build in items required including:
Construction joints
Conduits and piping and other items so required.
Pouring Concrete
A. Arrange for, with sufficient notice, inspection of preparatory work by Architect, Engineer and Local Authority. No concrete may be poured until authority is received.
B. Ensure that surfaces, trenches and formwork is both free of water and building debris and material which may adversely affect concrete.
PART 2 READ AND KEEP THIS PART
C. Transport concrete from the mixer to the place of final position without delay and by means that will
prevent segregation and loss of materials. Where necessary, transport concrete on substantial gangways or barrow runs supported on stools clear of reinforcement. Remove hardened concrete and foreign materials from the inner surfaces of the conveying equipment.
D. Place concrete in accordance with AS 3600.
Compaction of Concrete
A. Compact concrete by mechanical vibration to the maximum practicable density, free of air or stone pockets. Concrete not vibrated will be rejected.
Floor Finishes
Finish floor slabs monolithically with steel trowel, or as detailed on Drawings, or Schedule of Finishes.
Curing Concrete
Comply throughout with the requirements of AS 3600.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the Architect.
2.5 METALWORK
PART I GENERAL
Scope
Supply, engineer and install required general and architectural metalwork items including but not limited to 1. Handrails 2. Paper towel dispensers 3. Shelf
Related Work
Co-ordinate and co-operate with the following Trade Sections: Carpenter /Joiner
Quality Assurance
Work of this Section will be performed by experienced craftsmen familiar with the quality required in this class of work. Comply throughout with manufacturer's instructions.
References
AS 1627 Metal finishing – Preparation and pre-treatment of surfaces. There are 7 parts to this Standard, 1997-2005.
AS/NZS 1664 1997 Aluminium structures, There are 2 parts to this Standard. AS/NZS 4680 2006 Hot-dip galvanised (zinc) coatings on fabricated ferrous articles. Comply throughout with the current edition of the Building Code.
Shop Drawings
Comply with Section 4. Provide Shop Drawings for major items supplied hereunder (other than off the shelf items).
PART II MATERIALS
Materials
Item: Shelf (2No.)
PART 2 READ AND KEEP THIS PART
Manufacturer: JD Macdonald Model 0692 Surface mounted shelf flat top series – 120x400mm. Item: Paper towel Dispenser (2No.) Manufacturer: JD Macdonald Model 1020 Surface Mounted Paper towel dispenser; s/steel. Item: Soap Dispenser (2No.) Manufacturer: JD Macdonald Model 0347 Surface mounted vertical soap dispenser; s/steel. Item: Grab Rails – Toilet (2 sets) Manufacturer: JD Macdonald Model: GRE05 + PBR35A + GRE1400 (check handing)
Material: Stainless steel Finish
Materials exposed to weather maybe either: Mild steel - hot dipped galvanised after fabrication or chromate pre-treated followed by polyester powder coating. Finish internal steel after fabrication with zinc rich organic primer, or with inorganic zinc silicate paint. Comply with relevant codes of practice or Manufacturers' recommendations.
Welding Steel
General: Details of joints, the techniques of welding employed, the appearance and quality of welds made and the methods used to correct defective work; conform to requirements of AS/NZS1554, Part 1. Welds exposed to view: grind smooth to Architect's approval. Concealed welds: grind smooth before galvanising. Tack or skip welding: at regular intervals, very neat; not permitted if material is to be hot dip galvanised. Remove weld spatter. Certification: Only welders who have previously been qualified by tests may weld. Tack welding or skip welding will NOT be permitted where items are to be galvanised. Weld continuously form joints and connections to exclude water and to permit draining during galvanising.
Connection Design
General: Design fabricated items so that possible work is done before delivery. Fully protect for shipment. Take possible care to prevent damage.
A. Welding External Items: conform to the recommendations of AS/NZS 1554, noting particularly the design criteria.
B. Flanges: Concealed where possible. Sleeve connecting railings inside railing sections and secure with flush or set screws. Except where access is impossible, connection screws and bolts will be on the underside of joints.
C. Fasteners on the top of railing sections will not be permitted. D. Weld shop connections for steel fabrications, and bolt field connections. E. Provide smooth finishes to exposed surfaces with sharp well-defined lines and arrises. Mill to a close fit
machined joints. Design necessary lugs, brackets and similar items so that work can be assembled and installed in a neat, substantial manner.
F. Provide ample strength and stiffness by using appropriate metal thickness of assembly and supports. G. Provide holes and connections as required to accommodate the work of other trades and for site
assembly of Metalwork. Drill or punch and ream in the shop.
PART 2 READ AND KEEP THIS PART
Miscellaneous
Fasteners: Provide required bolts, screws, inserts, fasteners, templates and other accessories required for a complete installation. Co-ordinate with other trades as to the proper fastening systems suitable for the substrates to which the item is to be secured. Refer to Architect if in doubt. Fasten galvanised items with galvanised fasteners.
PART III EXECUTION
Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure conditions are satisfactory for installation. Arrange for rectification required. Start of work means total acceptance of relevant conditions.
Preparation
A. Field measurements: Do not delay job progress. Allow for adjustments and fitting of the work in the field where taking of measurements might cause delay.
B. Co-ordination with work of others: Furnish to each relevant trade foreman anchorages and setting Drawings, diagrams, templates and instructions for installation of items having integral anchors which are to be embedded in concrete or masonry construction. Coordinate delivery of such items to the project site.
Inspection and Reinstatement
A. Check fabrications as they are unloaded at the project site for evidence of physical damage. Treat damaged fabrications as follows:
1. Damage through galvanising: Perform immediate inorganic zinc silicate paint or cold-galvanising repair. Do not install until reinstated.
2. Architectural metalwork: Returned to shop for repair or replacement. a. Verify anchors, bolts and other required anchorage items for proper size and accurate location
prior to erection.
Installation
A. Anchorage: Except for anchorages furnished herein but placed by other trades, set and secure necessary anchorages, including concrete and masonry inserts, bolts, wood screws and other connectors as needed. Perform cutting, drilling and fitting as needed, locating anchorages and holes to ensure proper positioning of completed work.
B. Fit: During installation and assembly, form tight joints with exposed connections accurately fitted, and reveals uniform. Finish work accurately, plumb, level, square and true in reference to adjacent construction. Make tolerances conform to Australian Standards.
C. Finish: Do not cut or abrade shop finishes which cannot be completely restored in the field. D. The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted under
conditions. Fabrications may be cut shorter with power hacksaws on site.
Isolate dissimilar metals likely to be subject to moisture with inert materials, not visible on completion of installation.
Field Quality Control
Where considered necessary by the Architect, arrange for the manufacturer of products to instruct installers regarding correct installation.
PART 2 READ AND KEEP THIS PART
Protection
Cover Work: Immediately following installation, wrap or cover architectural metalwork to avoid wear and tear of finish during subsequent construction.
Cleaning
Clean materials installed to the satisfaction of the Architect.
Remove temporary protective coatings.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the Architect.
2.6 CARPENTRY AND JOINERY
PART I GENERAL
Scope
Provide materials and labour, equipment and services and perform operations necessary to complete the carpentry and joinery as indicated and specified. Work shall include:
Wall framing
Dividing wall framing.
Doors
Door furniture and seals
Roof framing
Verandah framing
Related Work
Co-operative and co-ordinate with the following trades:
Metalwork
Plasterboard
Mechanical
Quality Assurance
Manufacturers and installers are required to be widely experienced in the relevant aspects and class of work required for this section.
References
AS 1684 Residential timber-framed construction. AS 1720 Timber structures. There are 3 parts to this Standard, 1997-2006. AS/NZS 1859 Reconstituted wood-based panels – Specifications Comply throughout with the current edition of the Building Code.
Submissions
Submit the following prior to ordering materials:
Product literature on hardware items proposed
Technical data on melamine laminates proposed for use
Technical data and samples of substrate materials (particleboard etc.) Thickness of materials at typical locations and functions.
Delivery, Handling and Storage
Deliver, handle and store products so that damage, deterioration and loss will be prevented. Control delivery schedules to minimise long-term storage at site.
PART 2 READ AND KEEP THIS PART
Store timber on site indoors, or above ground and cover with secure impervious material.
PART II MATERIALS
Materials
Item: Wall Framing Material: 90x45 CCA pine. Studs @ 450c/c Item: Wall Lining – Shed Front Material: 9mm Scyon Matrix – cut to size; expressed joint; exposed wafer head fixing. Item: Verandah Posts Material: 90x90mm; CCA pine. Item: Roof Framing Material: Sizes as drawn; CCA pine. Item: Wall Lining – Ablutions Material: 6mm Hardies “Villaboard”; flush jointed. Item: Wall Lining – Ablutions Exterior Material: 9mm Scyon Matrix – 600 wide; expressed joint; exposed wafer head fixing. Item: Doors Material: 920x2040x40mm; solid HMR MDF core with WP plywood timber face and timber edging all around; Item: Door Frame Material: DDSD hardwood timber; Item: Door Furniture – Tenancies Material: Lockwood KL50 Exterior Deadlatch; satin s/steel; provide 5 keys with tags per lockset; Maisson key with gates and roller shutters Item: Door Furniture - Ablutions Material: Lockwood KL50 Classroom Set; satin s/steel; provide 3 keys with tags per lockset; Lockwood Toilet Bolt with Indicator 801SCP – 1 per door; Maisson key with gates and roller shutters Item: Door Seals Material: Raven RP4 Door Bottom Seals;
All timber used within the structure of the building shall be treated to a minimum H3 standard.
Fastening Schedule
All fastenings to be stainless steel.
Fabrication
Construct by screwing and gluing or other approved method. A dry stapled assembly will not be approved. Fabricate bench tops as indicated in a manner recommended by the material's manufacturer. Fabricate units without joints unless counter length exceeds maximum available length of materials.
PART 2 READ AND KEEP THIS PART
Seal joints between counter and splash back with matching colour silicone. Wherever possible, per-cut openings to receive hardware, appliances, plumbing fixtures, electrical work and similar items. Locate openings accurately using templates or roughing-in diagrams for proper size and shape. Smooth edges of cut-outs and, where located in bench tops and similar exposures, seal edges of cut-outs with a water resistant coating. Back prime all concealed solid timber surfaces prior to installation. Install fasteners, hinges etc in accordance with manufacturer’s instructions. When in doubt about suitability, consult with manufacturer of the items specified or selected.
PART III EXECUTION
Examination
Visit site and inspect conditions, comparing conditions to Drawings before delivery of materials to site. Start of work means total acceptance of conditions.
Installation General
Comply with: AS 1684 SAA Timber Framing Code, and other relevant standards.
Installation Particulars
Perform operations including grooving, rebating, framing, housing, beading, mitring, scribing, nailing, screwing and gluing as necessary to carry out the works. Use timber in single lengths whenever possible. If joins are necessary, make them over supports unless otherwise shown or specified. Arris visible edges in sawn work and in dressed work arris with sandpaper to 1.5mm radius unless otherwise shown or specified. Back plough boards liable to warping (for example, if exposed on one face). Make the width, depth number and distribution of ploughs appropriate to the dimensions of the board and the degree of its exposure. Provide necessary templates, linings, blocks, stops, ironwork and hardware, screws, bolts, plugs and fixings generally. Trim framing where necessary for openings, including those required by other trades. Unless otherwise noted, construct framing so that floors are horizontal, i.e. no more than 3mm slope in 3000mm. Construct wall framing vertical, so that no more than 3mm out of vertical in 3000mm of wall height.
Preparation for Installation
Prior to installing, condition joinery to the average humidity conditions prevailing in the installation areas. Delivery anchoring devices and similar inserts required to be built into substrates well in advance of the fixing of fittings and provide full details when they are to be fixed by others. Prior to installation, examine shop-fabricated work for completeness and remedy and deficiencies. Include back priming. Remove packing where not required. Thoroughly clean all floors and walls that will be permanently concealed by joinery.
Hardware
Install all door and joinery hardware as scheduled, listed and required in full compliance with the manufacturer's recommendations.
PART 2 READ AND KEEP THIS PART
Adjust as needed to centre doors in openings.
Adjustments, Cleaning, Finishing and Protection
A. Finish the work specified in this Section and remedy anything not finished at the shop or any other stage prior to completion.
B. Adjust joinery to achieve a uniform appearance. C. Lubricate and clean hardware making any final adjustments needed for proper operation. Remove all
handling marks from visible joinery surfaces. D. Protection: Do everything needed to ensure that all work is without damage or deterioration at
completion.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the Architect.
2.7 INSULATION
PART I GENERAL
Scope
The scope of work includes but is not limited to, the supply and installation of thermal insulation. It also includes the supply and installation of acoustic insulation.
Related Work
Co-ordinate and co-operate with the following trades:
Carpentry
Wall and roof framing
Metal Roofing
Fibrecement
Plasterboard
Quality Assurance
Installers are required to be widely experienced in relevant aspects of the work and with the requirements of Australian Standards appropriate to the work.
References
Comply with the applicable portions of these Australian Standards: AS/NZS 2107 2000 Acoustics - Recommended design sound levels and reverberation times for building
interiors. AS 2627 Thermal insulation of dwellings.
2627.1 1993 Thermal insulation of roof/ceilings and walls in dwellings. AS/NZS 4200 Pliable building membranes and underlays.
4200.1 1994 Materials. 4200.2 1994 Installation requirements.
AS/NZS 4859 Materials for the thermal insulation of buildings. 4859.1 2002 General criteria and technical provisions.
Comply with the requirements of the Building Code of Australia.
Submission
Provide to the architect before ordering, samples, literature and technical data of each specified material.
Delivery, Handling and Storage
Deliver, handle and store products so that damage, deterioration and loss will be prevented.
PART 2 READ AND KEEP THIS PART
Control delivery schedules to minimise long-term storage at the site. Store above ground with secure impervious material.
PART II MATERIALS
Approved Material Suppliers
Fletcher Insulation Green Insulation
Materials
Item: Roof Insulation (Retrofit) Material: Aircell Retroshield Item: Roof Insulation (New) Material: Green Insulation Reflecta Cell Item: Wall Insulation (Retrofit) Material: Aircell Retroshield Item: Wall Insulation (Ablutions) Material: Green Insulation Reflecta Guard Item: Wall Insulation (Dividing Wall - Acoustic) Material: 90mm Fletcher Insulation Sonobatts Silencer+ Item: Ceiling Insulation (Ablutions) Material: R3.0 Insulation batts
Comply with manufacturer’s recommendations and the relevant Australian Standards.
PART III EXECUTION
Examination
Visit the site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Start of work means total acceptance of conditions.
Preparation
Prepare surfaces and or framing material and ensure that no obstructions will prevent rapid and effective installation.
Installation General
Comply with manufacturer’s current written recommendations and the relevant Australian Standards.
Installation – Roof Retro-fit
Retrofit insulation to walls and roof in accordance with manufacturer’s instructions.
Roll out insulation perpendicular to the purlins.
Fix to the purlins using 12 g x 25 mm Tek screws or similar.
Use 4 screws across the width of the roll at each purlin, with one 25 mm from each edge and the other two at approx. 430 mm centers. For neatest finish, butt joins rolls and tape joins with 72 mm reinforced aluminium tape.
PART 2 READ AND KEEP THIS PART
Alternatively, rolls can be overlapped by 50 mm and taped as above. At connections between purlin and frame cut a slot in the insulation to allow it to pass over or behind the frame. Neatly cut insulation around penetrations and tape if necessary. Reveal skylights by lining beneath, as for roof, and then cut down the centre and diagonally to the corners forming flaps. Curl these flaps back under the roof to reveal the skylight and fix in position by taping or otherwise.
Cleaning
Remove surplus material on completion and arrange for inspection(s) by manufacturer’s representative.
Completion
Complete contracted work in accordance with the contract document and written variation orders issued by the architect.
2.8 METAL ROOFING AND CLADDING
PART I GENERAL
Scope
Supply and install a complete roofing and fascia installation as shown on the Drawings including but not limited to the following :
A. Metal deck of Colorbond steel including accessories, flashings, apron flashings, gutters, overflow pipes, downpipes.
B. Skylight sheets to existing roofs. C. Roof penetrations and sealing thereof. D. Metal fascias including cappings and flashings E. Repairs to wall sheeting
Related Work
Co-ordinate and co-operate with the following trades:
Carpenter
Quality Assurance
Tradesmen are required to be experienced in and knowledgeable about the work to be performed and the various standards to which the work is to comply. The Architect will make random inspections during the execution of the work.
References
Comply with applicable portions of the following Australian Standards: AS 1170 Minimum design loads on structures (known as the SAA loading code)
There are 5 parts and 2 supplements to this code, 1989 - 1993 AS/NZS 1562 Design and installation of sheet roof and wall cladding
There are 3 parts to this standard, 1992 - 1999 1562.1 1992 Metal
AS 1904 1976 Code of practice for installation of reflective foil laminate in buildings AS/NZS 2179 Specifications for rain water goods, accessories and fasteners
2179.1 : 1994 Metal shape or sheet rainwater goods and metal accessories and fasteners
AS 2180 1986 Metal rainwater goods - Selection and installation AS 3566 1988 Screws self-drilling for the building and construction industries
PART 2 READ AND KEEP THIS PART
AS/NZS 4256 Plastic roof and wall cladding materials.
There are 5 parts to this standard, 1994 - 1996 SAA HB 39 - 1997 Installation code for metal roof and wall cladding SAA HB 63 1994 Home insulation in Australia
Submissions
Submit prior to ordering materials:
A. Samples and product data of specified products.
Delivery, Handling and Storage
Deliver to site, unload and stack in a location away from potential damage, preferably directly on to installed roof framing. Inspect on arrival and reject bent or damaged material.
Warranty
Provide to the Proprietor a written warranty on the whole of the roof and roof plumbing including penetrations for pipes, flues, upstands etc. which states that work will remain waterproof and weather-tight for the period of seven years from the date of Practical Completion.
PART II MATERIALS
Acceptable Manufacturers
Materials
Item: Metal Roof sheeting - Ablution Profile: Spanform or equal Base Metal Thickness: 0.42mm Material: Colorbond Steel Colour: TBA Item: Metal Wall Sheeting – North Wall Profile: To match existing cladding Base Metal Thickness: 0.42mm Material: Zincalume Steel Item: Flashings/Cappings Profile: As drawn Base Metal Thickness: 0.6mm Material: Colorbond steel Item: Eaves Gutters - Ablutions Profile: Quarter Round Base Metal Thickness: 0.55mm Material: Colorbond steel Item: Wall Cladding Profile: To match existing Thickness: 0.42mm Material: Zincalume Item: Skylight Sheeting Profile: To match existing Manufacturer: Ampelite Material: Cool-Lite GC – 3050 Series Weight: 3.05kg/m²
PART 2 READ AND KEEP THIS PART
Material: Premium grade gel coated fibreglass Item: Downpipes Material: Colorbond steel Description: 75mm dia.; finish at shoe Item: Sealing of penetrations (Up to 200mm diameter) Material: EPDM collars of approved manufacture.
Fabrication
Form and fabricate components in accordance with AS 1562, AS 2179 and AS 2180, and other relevant standards. Self-drilling screws are to conform to Class 3 as described in AS 3566.
PART III EXECUTION
Examination
Inspect site conditions before installation. Ensure framing is entirely satisfactory. Ensure that delivery and installation will not be impeded by on-site condition at time of delivery. Start of work means total acceptance of conditions.
Terrain Category
The site is zoned as Terrain Category: 3. Refer AS 1170.
Preparation – Roof Framing
Prepare framing and surfaces for installation.
Installation
Install work in accordance with manufacturer's instruction and Australian Standards. Refer Clause 104.
Flashing
Lap flashing at least 150mm at junctions, and over flashings neatly dressed and finished. Where necessary to follow a roof slope, step flashings in even overlapping widths. Finish top corners to a line parallel to the roof slope.
Fabricated flashings in materials which are compatible with, and same finish as gutter and roofing materials. Complete work and leave an entirely watertight installation.
Penetrations
For penetrations under 200mm in diameter use use EPDM collars.
Where the width of a penetration is wider than a roofing trough or extends across several troughs, allow to extend flashing back to roof ridge using specified material well lapped under the ridge, double riveted and sealed with silicone sealant. Close and seal ends of cut ribs. Form over-flashings of penetration collars neatly in material matching the roofing material but not less than 0.6mm thick, securely clipped and sealed to the penetrating items and dressed well down over the collars to finish at a straight line level with the tops of the ribs. Do not use lead or copper for over-flashings.
Downpipes
Install in accordance with AS 1273 for PVC. Comply also with manufacturer's instructions.
PART 2 READ AND KEEP THIS PART
Secure to building at recommended centres, minimum 1800mm with galvanised steel straps
Cleaning
To prevent contamination and corrosion, keep clean metal roofing and rainwater goods at times during the progress of the works. At the end of work each day, and immediately before each occurrence of rain, sweep the metal surfaces thoroughly to remove metal filing, swarf, off-cuts, dust, and other materials which could cause corrosion or blockages. Prevent waste materials from entering downpipes, rainwater heads, or drains. Remove unsecured nails, rivets, screws, bolts and similar fixing devices, guttering, etc., at the end of work each day and at the completion of roofing installation.
Testing
On completion, test the entire installation in the presence of and to the satisfaction of the Architect.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the Architect.
2.9 ROLLER SHUTTER DOORS
PART I GENERAL
Scope
Supply, engineer and install roller shutter door(s) including but not limited to:
Drum support
Door guides
Manual control devices
Locking devices
Wind locks
Weatherstrips
Related Work
Co-ordinate and co-operative with the following trades:
Structural Steel
Carpenter
Electrical
Painting
Quality Assurance
Craftsmen are required to be experienced and familiar with the quality required in this class of work. Comply throughout with manufacturer's instructions.
References
AS/NZS 1905.2 2005 Fire-resistant roller shutters. Comply throughout with the current edition of the Building Code.
Shop drawings
Provide manufacturer’s drawings for items supplied hereunder.
PART 2 READ AND KEEP THIS PART
A. Contract drawings and details provided are indicative as to general and minimum requirements, and do not show conditions.
B. Develop details not shown and in conformity with the indicative details shown. C. Take and confirm dimensions on site, before preparing shop drawings where possible.
Warranty
Provide to the proprietor a warranty, counter-signed by the installer, on the whole of the installation, which states that work will remain intact, waterproof and fully operational for the period of not less than five years after date of Practical Completion.
PART II MATERIALS
Acceptable Manufacturers
Gliderol Austral Monsoon Mirage.
Materials
Item: Roller Shutters Manufacturer: Gliderol Model: Broadline Commercial Roller Door Material: Colorbond Features: Chain hoist (direct drive); Windlock; internal shoot bolt locks x 2 per door; weatherseals; Locking: 2 x Lockwood 334S45/538 to each door; provide 2 keys; key to match tenancy doors.
Maisson key with gates.
Miscellaneous Items
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required for a complete installation.
Co-ordinate with other trades as to the proper fastening systems suitable for the substrates to which the item is to be secured. Refer to architect if in doubt. Fasten galvanised items with galvanised fasteners.
PART III EXECUTION
Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure conditions are satisfactory for installation. Arrange for rectification required. Start of work means total acceptance of relevant conditions.
Preparation
A. Field measurements: do not delay job progress. Allow for adjustments and fitting of the work in the field where taking of measurements might cause delay.
B. Co-ordination with work of others.
Inspection and Reinstatement
A. Check fabrications as they are unloaded at the project site for evidence of physical damage.
Treat damaged fabrications as follows:
1. Misshaped items: return to shop for repair or replacement.
PART 2 READ AND KEEP THIS PART
2. Damaged surface treatment: repair as recommended by application of the finish.
B. Verify anchors, bolts and other required anchorage items for proper size and accurate location prior to
erection.
Installation
A. Anchorage: except for anchorages furnished herein but placed by other trades, set and secure necessary anchorages, including concrete and masonry inserts, bolts, wood screws and other connectors as needed. Perform cutting, drilling and fitting as needed, locating anchorages and holes to ensure proper positioning of completed work.
B. Fit: during installation and assembly, form tight joints with exposed connections accurately fitted, and reveals uniform. Finish work accurately, plumb, level, square and true in reference to adjacent construction.
C. Finish: do not cut or abrade shop finishes which cannot be completely restored in the field. The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted. Fabrications may be cut shorter with power hacksaws on site. Isolate dissimilar metals likely to be subject to moisture with inert materials, not visible on completion of installation.
D. Comply with manufacturers' installation instructions throughout.
Protection
Protect the completed installation from damage by appropriate means until completion of the project.
Cleaning
Clean materials installed to the satisfaction of the architect. Apply necessary lubrication. Remove temporary protective coating.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the architect.
2.9 METAL WINDOWS & GLAZING
PART I GENERAL
Scope
Design, engineer, supply and install a complete glazed system of windows, doors and screens, including but not limited to:
Mirrors
Aluminium Windows
Aluminium Door Frames
Related Work
Co-ordinate and co-operate with the tradesmen preparing walls and frames to accept windows, including casting in of anchors.
PART 2 READ AND KEEP THIS PART
Quality Assurance
A. Manufacturer qualifications: not less than ten (10) years continuous experience in the manufacture of the product types specified.
B. Installer qualifications: installer is to have not less than five (5) years continuous experience in the erection of specified material.
References
AS/NZS 1170 STRUCTURAL DESIGN ACTIONS. THERE ARE 5 PARTS TO THIS STANDARD, 1993-2003. AS 1288 2006 Glass in buildings – Selection and installation. AS 2047 1999 Windows in buildings – Selection and installation. AS 3715 2002 Metal finishing - Thermoset powder coatings for architectural applications… SAA HB 125 2007 The glass and glazing Handbook Comply throughout with the current edition of the Building Code.
Delivery, Handling and Storage
Handle materials with care. Do not store on site. Install directly in place. Store sealants as instructed by manufacturer.
Warranty
Provide to the proprietor a warranty, counter-signed by the installer, on the whole of the installation, which states that work will remain intact, waterproof and fully operational for the period of not less than five years after date of Practical Completion.
PART II MATERIALS
Acceptable Manufacturers
The following manufacturers of window frames are acceptable:
Alspec
Materials
Window Frames: extruded aluminium components manufactured from aluminium alloy 6063, temper T5 or T6. Item: Windows Model Powdercoat Aluminium frame; short glazed with insect screen Item: Door Frames Manufacturer Alspec Model Aluminium Specialties Alspec Centre Pocket Glazing Suite with door stop inserts; Item: Mirrors Description Powdercoat aluminium frame with safety mirror glass;
Structural Criteria
A. Adopt terrain category: 3. Refer AS/NZS 1170.
B. Wind loading: Design:
1. Glazing and frame assemblies to suit the static and dynamic wind forces as indicated on the tables in
the AS/NZS 1170. 2. Structural members of glazed units of such strength that when tested at the specified design wind
values they do not deflect by an amount greater than span/240 and do not cause permanent deflection.
PART 2 READ AND KEEP THIS PART
3. Fix members so that the above loading is generated in the members without stress causing failure or
movement becoming evident at any joint. C. Contact with other materials: coat metal surfaces in contact with mortar, concrete, plaster, masonry, wet-
application of fire-proofing and absorbent materials with an antigalvanic, moisture barrier material. Isolate, with inert material, dissimilar metals for the prevention of electrolytic action and corrosion.
D. Distortion: design the glazed assembly to minimise visual distortion of reflected images.
Finish
A. Polyester powder coat: Polyester powdercoated, to colour approved by the architect and by the manufacturer of the powder material, to metal of windows, doors and shop fronts. Perform pre-treatment and application of powder coating by applicators approved by the architect and by the manufacturer of the powder material. Minimum coating thickness of 50 microns subjected to random testing after installation. Non-conforming material will be removed and made good by the Builder. Comply with requirements of AS 3715.
Glass
A. Glass materials for external use: Obscure
Sealants and Accessory Materials
A. Provide non-structural external weatherproofing sealants of low modulus neutral curing silicone rubber compounds by approved manufacture.
B. Generally comply with AS 1288, Part 2, Section 6 or 8. Supply spacer gaskets, glazing tapes and setting blocks compatible with sealants, which do not contribute to sealant colour change or affect the sealants adhesion to substrates when exposed to ultraviolet light.
C. Prior to application, samples of materials receiving the silicone, including elastomeric Silicone sealants generally will be clear in colour.
D. Exposed screws: countersunk type, anodised aluminium or non-magnetic stainless steel evenly and neatly located in an approved manner. Exposed fasteners: finished to match aluminium.
Fabrication
Comply with AS 2047.
PART III EXECUTION
Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are satisfactory for installation. Perform rectification required before delivery of materials. Start of work means total acceptance of conditions.
Preparation
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.
Frame Anchorage
Fabricator is required to supply the anchorage devices to the builder for building in by others and check that devices are located as required to suit the requirements of window frame fabrication for positive and permanent fixing.
PART 2 READ AND KEEP THIS PART
Insulation: isolate dissimilar metals at interfaces with bitumen based or nylon shim materials to prevent galvanic action.
Frame Installation
Comply with AS 2047.2.
Glazing
Secure glass in accordance with glass manufacturer's recommendations and AS 1288. Allow for thermal expansion of glass, the metal framing and spandrels.
Installation of Sealants
A. Install sealant to depths as recommended by sealant manufacturer. B. Cure sealants and caulking compounds in compliance with manufacturer's instructions and
recommendations, to obtain high early bond strength internal cohesive strength and surface durability. C. Remove excess caulking compound and sealant and leave surfaces neat, smooth and clean, without
smears on surrounding work. Tool joints where recommended by manufacturer or where required. Remove cartons and debris from site as the work progresses.
Protection
A. Framing system: protect metal surfaces as necessary during erection. Finish surfaces free from mechanical imperfections such as scratches, scrapes, dents, spots, stains and streaks.
B. Glass: protect glass from breakage immediately upon installation and until Practical Completion. Remove and replace glass and metal panels which are broken, cracked, abraded, chipped or damaged in other ways, before, during or after installation, at no additional cost to proprietor.
C. Be responsible for breakage and damage to installation until Practical Completion.
Cleaning
A. Remove labels, excess glazing compounds, stains, spots and other foreign matter from glass, frames, hardware and other finished surfaces immediately upon installation of glazing for each light.
B. Debris: remove rubbish and debris resulting from glazing operations, each day.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the architect.
2.10 PLASTERBOARD
PART I GENERAL
Scope
Supply and install a complete installation of plasterboard including but not limited to:
Plasterboard
Fire-rated plasterboard walls
Related Work
Co-ordinate and co-operate with the following trades:
Electrical
Stud walls
Insulation
References
AS/NZS 2589 2007 Gypsum linings in residential and light commercial construction –
PART 2 READ AND KEEP THIS PART
Application and finishing – Gypsum plasterboard. There are 2 parts to this Standard, 1997.
Comply throughout with the current edition of the Building Code. Comply with manufacturer’s technical bulletins.
Delivery, Handling and Storage
Deliver manufactured materials in bundles and packages bearing the name of the manufacturer, and the brand. Handle with care. Remove damaged materials from the site. Protect stored materials from damage and damp, or materials which may cause deterioration.
Warranty
Provide warranty covering the work against defective materials and workmanship for a period of five (5) years from the date of Practical Completion. The warranty includes a statement that the whole of the work has been carried out in accordance with relevant Australian Standards and Codes and manufacturer's instructions in effect at the time of installation.
PART II MATERIALS
Acceptable Manufacturers
CSR Boral
Materials
Supply materials in accordance with material supplier's recommendations for each application.
Item: Fire Wall Cladding Manufacturer CSR Model 16mm Fyrchek
PART III EXECUTION
Examination
Acceptance: visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Rectify any discrepancy or unsuitability of substrate. Start of work means total acceptance of conditions.
Preparation
A. Co-ordinate with and ensure preparatory work by other trades is done prior to commencement of work; failure to do so will involve removal of plasterboard and immediate rectification.
B. Arrange for provision of additional stud, nogging, trimmed openings, boxed studs, fixing grounds, etc.,
required for satisfactory execution of the work of this trade including penetrations through plasterboard for services. co-operate in installation of frames, duct openings, etc.
C. Space Enclosure: do not install materials until space is enclosed and weatherproof, and until wet-work in
space is completed and nominally dry.
Layout and Tolerances
A. Check dimensions of areas and surfaces to which material is applied before installation begins.
B. Measure each area and establish layout pattern.
C. All finished work is to be within + 2mm of the sizes shown on the relevant drawings.
PART 2 READ AND KEEP THIS PART
Installation - General
A. Comply with manufacturer's installation instructions. Anchor and fasten materials and components to comply with ratings and performance requirements, and to comply with governing local regulations. Comply with appropriate Australian Standard.
B. Take care of and protect surrounding work, including other finishes, equipment and components, during installation. Provide protective covering where necessary.
Finishing Details
General: apply treatment at board joints (both directions), flanges of trim accessories, penetration, fasteners, heads, surface defects and elsewhere as required to prepare work for decoration. Pre-fill open joints and rounded or bevelled edges, using type of compound recommended by manufacturer.
A. Apply fibreglass joint tape at joints between boards, where a trim accessory is indicated, or where extra strength is required.
Protection
Protect finished work. Make good damage in every respect at no additional cost to the proprietor, and without delay to job progress.
Cleaning
A. Adjust and Clean: clean exposed surfaces including trim, edge moldings, and comply with manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and replace work which cannot be successfully cleaned and repaired to permanently eliminate damage.
B. Remove spatterings and droppings resulting from work. Remove daily surplus materials and rubbish from the work area.
C. Leave floors broom clean at completion.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the architect.
2.11 CERAMIC TILES
PART I GENERAL
Scope
Supply and install Ceramic Tile work including but not limited to: A. Wall tile B. Floor tile C. Cleaning of finished tiled surfaces.
Related Work
Co-ordinate and co-operate with the following trades: Wall construction Floor construction
Quality Assurance
A. Qualifications: Tiling subcontractor to submit to architect evidence of reliability in quality of work and performance.
References
AS 2358 1990 Adhesives - For fixing ceramic tiles. AS/NZS 3661.2 1994 Slip resistance of pedestrian surface – Guide to the reduction of slip hazards. AS 3740 2004 Water proofing of wet areas within residential buildings. AS 3958 Ceramic Tiles. There are 2 parts to this Standard, 1992-2007.
PART 2 READ AND KEEP THIS PART
AS/NZS 4586 2004 Slip resistance classification of new pedestrian surface materials. AS/NZS 4663 2004 Slip resistance classification of existing pedestrian surfaces. Comply throughout with the current edition of the Building Code. Comply with material manufacturer’s current written instructions.
Submissions
Submissions Required Prior to Installation: product specifications for: adhesives, primers, prepared grouts, moisture resisting admixtures.
Delivery, Handling and Storage
Deliver to the site in original, unopened containers with grade, type and quality indicated on the labels. Provide secure and dry storage.
Warranty
Provide a warranty covering defects in materials and installation for a period of five years from the date of Practical Completion.
PART II MATERIALS
Adhesives
A. Exterior/Wet area adhesives: cement-based ceramic tile adhesive, complying with AS 2358.
B. Interior/Dry area adhesives: organic based adhesive, complying with AS 2358:
Waterproofing
Morgans Single Pack Waterproofing with approved reinforcing scrim.
Tile
Item: Wall Tiles Materials: TCM 200x200 gloss white Item: Floor Tiles Materials: Cerdissa R11 Fully vitrified 200x200 floor tiles with 200x110 coved skirting tiles
Grout
Prepared Grout: inorganic Portland cement integrated, ready-to-use, dry-curing grout. Colours to architect’s selection. Supply waterproof grout for wet area tiling.
Expansion Joints
Silicone rubber, as recommended by manufacturer. Colour to architects selection.
PART III EXECUTION
Examination
Visit site and inspect conditions, comparing conditions to drawings, before delivery of materials to site. Rectify any discrepancy or unsuitability of substrate. Start of work means total acceptance of conditions.
Conditions of Installation
A. Rectify substrate so that when checked with a 2m straightedge, gap under the straightedge does not exceed 6mm.
PART 2 READ AND KEEP THIS PART
B. Allow new concrete to dry out for at least 4 weeks before rendering or direct fixing of tiles.
Setting Out
A. As far as possible, set out work so that no tile less than half size occurs. Align joints in floor tile at right angles to each other and straight with walls to conform to patterns selected. Verify locations of equipment before installing tile. Co-ordinate with plumbing and other trades. Fully tile surfaces under surface-mounted items.
B. Expansion Joints Set out panels of tiling so that tiles may expand or contract to and from corners of tiled walls and floors. Allow for expansion in each corner of 5mm minimum. Fill expansion joints with silicone rubber.
C. Control Joints Provide control joint
1. At junctions of dissimilar wall construction. 2. In walls, no more than 2.5 apart. 3. At junctions of wall and floor in multi-storey buildings.
Installation - General
A. Wall tiling: comply with the recommendations of AS 3958.1 and AS 3740.
B. Floor tiling: comply with the recommendations of AS 3958.1 and AS/NZS 3661.2.
C. Adhesives: comply with AS 2358 and recommendations of adhesive manufacturer.
D. Sealing: where tiles are cut around penetrations for taps and outlets, seal thoroughly with silicone rubber to prevent water entry behind tiles.
E. Membrane: install to manufacturer’s instructions, with a 100% waterproof result.
Tolerances and Cleaning
A. General: install tiles in true planes so that when checked with a 2m straightedge, gap under the straightedge does not exceed 3mm. In sloped floor tiling this tolerance does not apply across intersections of fall planes. Adjust tiles within 10 minutes of fixing.
B. Cleaning: cleaned down using a damp cloth before cement smears and surplus mortar begin to harden on the surface or in the joint spaces, care being taken to avoid disturbance of the tiles during the setting of the bedding.
C. Lighting: whenever possible the lighting at the time of applying the bedded finish is not to be appreciably different from the ultimate permanent lighting.
Grouting
A. Except as otherwise required, do not commence grouting for at least 24 hours after placing of tile. Follow specific instructions of materials manufacturer.
B. Grout Mix: 1. General use, except as noted below: Apply an approved pigmented prepared grout mix, one (1)
part Portland cement to one (1) part fine dry sand by volume mixed to a paste consistency with the minimum of water; too wet a mix may result in the joint filling cracking or drying out.
2. Floors: Prepared grout, acid resistive. 3. Walls: Epoxy-based mortar grout, mildew resistant. 4. Colours: as selected by the architect.
C. Grouting and Curing: 1. Apply the grouting mix to as large an area as can be worked before hardening commences. Apply
with a squeegee working back and forth over the area until the joints are completely filled. Remove surplus grout from the tiles with the aid of a damp, not wet, cloth and the joints then tooled. After the grouting has dried, final polish using a clean, dry cloth.
PART 2 READ AND KEEP THIS PART
2. Remove surplus grout from the floor surface; on no account use sawdust for this purpose, as there is a danger that sawdust entering moist joint surfaces may break down their strength, and cause them to become porous.
3. In dry weather, grout joints after maintaining damp condition for three days by sponging down,
fog-spraying or other methods. Allow floors to set 48 hours before permitting ordinary foot traffic.
Protection
Prevent walking on or contact with floor or wall tiles for a minimum of seven days. During that period, cover floor tiles
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the architect.
2.12 PAINTING
PART I GENERAL
Scope
Supply labour and materials, services and equipment necessary for the preparation, application and finishing of painting and staining as indicated on Drawings, schedules and as specified herein, to internal and external surfaces of building, as follows:
Internal Firewall; Plasterboard walls Fibrecement walls and ceilings Doors Steelwork External Fibrecement cladding Scyon cladding (four colours); Timberwork Concealed steelwork prior to enclosure (sealer only) Exposed Steelwork
Consult with the Architect with regard to requirements of other Sections of the Specification which require painting, and include as part of the work of this Section the appropriate preparation, painting, and finish required to complete the installation. Do not paint powder-coated, anodised, Colorbond or other pre-finished items.
Related Work
Co-ordinate and co-operate with the following trades: A. Substrates to be painted. B. Cleaning and finishing.
Quality Assurance
A. Compatibility of Shop and Field Paints:
PART 2 READ AND KEEP THIS PART
Determine that the materials specified in the Schedule of Finishes are compatible with shop coats. Failure to do so will be construed as accepting the paints specified. Contractor is to correct, at his own expense, defects in his work resulting from the use of such materials.
References
AS/NZS 2311 2000 Guide to the painting of buildings. AS/NZS 2312 2002 Guide to the protection of structural steel against atmospheric corrosion by the use of protective coatings.
Comply throughout with the current edition of the Building Code.
Comply with manufacturer’s printed instructions.
Submissions
Submit product literature on proposed painting systems if different to that specified.
Delivery, Handling and Storage
A. Store materials in designated spaces in a manner which meets the requirements of applicable codes and fire regulations. When not in use, keep such spaces locked and inaccessible to those not employed under this Section. Provide each space with a fire extinguisher of carbon dioxide or dry chemical type bearing a tag of recent inspection.
B. Bring materials to the building and store in manufacturer's original sealed containers, bearing the manufacturer's standard label, indicating type and colour. Deliver materials in sufficient quantities in advance of the time needed in order that work will not be delayed in any way.
Project Conditions
Temperature: Comply with the requirements of Clause 6.3 of "AS 2311 The painting of buildings" and of paint manufacturers with regard to both ambient temperature and relative humidity.
Warranty
Provide a written warranty stating that preparation of surfaces, materials and material application installed under this contract will show no deterioration and remain in good condition for a period of seven years from date of Practical Completion.
PART II MATERIALS
Materials
General: Where manufacturer makes more than one grade of any material specified, use the highest grade of each type, whether or not the material is mentioned by trade name in these Specifications. Use Paints and finishes used for the project may be manufactured by one or more of the following manufacturers:
Taubmans Dulux Wattyl International Coatings Haymes
Other products may be approved by Architect. Apply to Architect for approval of alternatives prior to closing of tenders. Only alternatives approved prior to close of tenders will be accepted. Provide materials necessary for preparation of surfaces, and for application of paint finishes.
Schedules
External Timber Painted 2 coats Taubmans Endure Exterior Acrylic Low Sheen
PART 2 READ AND KEEP THIS PART
Fibrecement 2 coats Taubmans Endure Exterior Acrylic Low Sheen Steelwork 1 coat International Coatings “Interplus 356”
2 coats International Coatings “Interfine 878” Internal Plasterboard 1 coat Taubmans 3 in 1
2 coats Taubmans Endure Interior Acrylic Satin Fibrecement 2 coats Taubmans Endure Interior Acrylic Satin Timber (Painted) 1 coat Taubmans 3 in 1
2 coats Taubmans Ultra Enamel Gloss Doors 1 coat Taubmans 3 in 1
2 coats Taubmans Ultra Enamel Satin
Colours
Allow to paint Scyon and doors in Accent based colours.
Allow to black line shadow line joints to Scyon.
Priming Materials
Colours of priming coats (and body coats where specified) are to be lighter than those of finish coat.
PART III EXECUTION
Examination
Inspect surfaces and determine that they are in proper condition to receive the work to be performed under this Section. Refer 302 A, below. The starting of work under this Section will be taken to mean acceptance of such surfaces as being satisfactory and defects in work resulting from accepting poor surfaces are to be corrected at no cost to the Proprietor. Refer AS 2311 Appendix C.
Preparation
A. General : Prepared to a standard not less than that described under AS 2311, Section 3: Preparation of Un-Painted Surfaces, pages 17 - 22 inclusive, and other Clauses of Australian Standards referenced therein.
B. Broom clean floor surfaces before painting. Remove dust, dirt, plaster, grease and other extraneous matter affecting the finish work.
C. Putty-stop or plug nail holes and cracks on both exterior and interior work, as required. Natural or stained wood finishes are to have putty coloured to match. Putty wood after prime coat or sealer coat has been applied.
D. Clean bare metal surfaces of mill scale, rust, grease, oil, dirt, or other foreign matter, then properly washed with spirit or other approved cleaning agents. After cleaning, etch, pickle, prime, or otherwise prepare, as recommended by the paint manufacturer.
E. Remove blisters or other imperfections in previous coats caused by foreign substances or paint skins from painted surfaces before the subsequent coat is applied.
F. Rub down wood and metal surfaces before finishing and between coats with No. 00 and finer sandpaper or steel wool, leaving a perfectly clean surface. Sand smooth-finished surfaces before finishing and between coats as required to smooth out rough areas and to assure a smooth, even finish. Surfaces to receive paint are to be smooth and free of sandpaper scratches, mill-marks, and other imperfections.
G. Remove hardware, accessories, plates, lighting fixtures and similar items in place prior to painting and re-position upon completion of each space, or protect as otherwise directed by the Architect.
H. Thoroughly stir materials in containers before application, unless otherwise directed by the manufacturer of the paint used, to ensure uniformity of colour and mass. Strain out paint skins or other materials which would cause lumps or roughness. Thin only as recommended by the manufacturer.
PART 2 READ AND KEEP THIS PART
Protection
Furnish and lay suitable drop cloths in areas where painting is being done to protect floors and other surfaces from damage during the work.
Application
A. General: Execute work of this Section in strict compliance with paint manufacturer's recommendations, and with the provisions of AS 2311, Section 6: Paint Application, pages 36 - 40 inclusive. This Standard is incorporated by reference as part of this Specification and applies to the work below to the same extent as if written herein. In the event of conflict between manufacturer's recommendations and the provisions of AS 2311, manufacturer's recommendations govern.
Cleaning
At completion of work in each area, remove paint spots, oil and stain from adjacent surfaces, including finish hardware. Replace hardware previously removed.
Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the Architect.
2.14 ELECTRICAL
Refer to Appendix A.
IMPLEMENTATION TIMETABLE
Proposed implementation schedule as per Scope of Works provided;
MILESTONE KEY DELIVERABLES COMMENCEMENT DATE
COMPLETION DATE
Site preparation 1. Removal of old fuel bowsers (Not included in SOW)
Week -6 Week -5
2. Removal of items currently in storage (Not included in SOW)
Week -12 Week - 8
3. Clear vegetation, bitumen, concrete and fencing as required
4. Removal of old ablution building
5. Locate and Isolate services through the site
Week 1 Week 3
PART 2 READ AND KEEP THIS PART
MILESTONE KEY DELIVERABLES COMMENCEMENT DATE
COMPLETION DATE
Re-development of tenancy units
1. Hydraulics 2. Concrete and
Concrete Paving 3. Structural Steel 4. Metalwork 5. Carpentry and Joinery 6. Plasterboard 7. Masonry Unit Paving 8. Roofer 9. Glazier 10. Painter 11. Electrical
Week 1 Week 16
Re-instate services 1. Re-instate all hydraulic and electrical services
Week 4 Week 16
Car park area development
1. Bituminous Concrete Paving
Week 15 Week 18
Sign off and acceptance 1. Notice of Practical Completion to be submitted to the Shire of Perenjori.
April 2014
PART 3 READ AND KEEP THIS PART
GENERAL CONDITIONS OF CONTRACT
INSURANCES
The following certificates of currency must be provided when submitting your tender;
1. Public Liability (Required) – All companies are required to have this insurance to protect them
against claims arising from personal injury or property damage caused by the actions and
operations of the insured.
2. Workers Compensation or Personal Accident Insurance Cover (Required) – All employees in
Australia must be insured by their employer for workers’ compensation. Or in the case of a sole
business owner or operator then Personal Accident Insurance Cover is required. The company or
person appointed will be required to have the appropriate insurance in effect.
PERIOD OF CONTRACT AND TERMINATION
SUPPLY CONTRACT
The Contract is to be completed on supply of the Requirements.
PART 3 READ AND KEEP THIS PART
GENERAL CONDITIONS OF CONTRACT
1 Security provided by the contractor (clause C1) Cash or Bank Guarantee
2 Percentage of *contract price for cash retention (clause C2)
5%
3 Percentage of *contract price for each unconditional guarantee (clause C3)
2.5%
4 Period for payment of Certificates, and release of security (clauses C6, C7, N6, N13, Q10 and Q18)
7 calendar days
5 Public liability insurance (clause E1)
Is the owner or the contractor to take out and maintain this insurance?
Contractor
6 Contract works (clause E2)
Is the owner or the contractor to take our and maintain this insurance?
Contractor
7 Amount to cover fees of the Architect and other Consultants (clause E4.1)
10%
8 Amount to cover cost of demolition and removal of debris (clause E4.1)
10%
9 Amount of insurance for injury, illness, disease or death (clause E4.2)
$10,000,000.00
10 Insurance excess (clause E16)
Amount of excess for public liability insurance (clause E1)
$1,000.00
Amount of excess for contract works insurance
(clause E2)
$1,000.00
11 Percentage for the contractor’s overheads and profit (clause H2)
10%
PART 3 READ AND KEEP THIS PART
GENERAL CONDITIONS OF CONTRACT (CONTINUED) 12 Adjustment of time costs (clause H5)
Stage of completion of the *works (description) Sum per *working day (incl GST)
Nil
13 Percentage of difference to be added to the *contract price (clause K4.2)
5%
14 Allowance for delay due to disruptive weather conditions (clauses L2 and L4)
10 *working days
15 Other allowances for delay having regard to the nature of the contract and the *works which do not entitle *adjustment of time costs (clauses L2 and L4)
Clause (description)
Allowance *working days
Nil
16 Date for Practical Completion (clause M1)
17 Commissioning tests for *practical completion Electrical
17 Rate for liquidated damages (clause M9) $500.00/week
18 Defects liability period for the *works (clause M13) 12 months
19 Date for submitting progress claims (clause N3) 20 of the month
20 Information to be included in a claim for progress payment (clause N3)
Percentage of trade works completed against a trade and preliminaries Break-up of the Contract Price.
21 Interest on overdue amounts (clause N15) 10%
22 Governing law (clauses P4, P5, P6 and R8) Law of the State of Western Australia
23 Official Documents required to begin the works but to be obtained by the contractor
Building Permit
Certificate of Construction Compliance (CCC)
PART 3 READ AND KEEP THIS PART
24 Official documents required to complete the works but
to be obtained by the owner Development Approval
Certificate of Design Compliance (CDC)
Occupancy Permit
PART 4 READ AND KEEP THIS PART
SPECIAL CONDITIONS OF CONTRACT
WARRANTIES
Warranty Requirements
1. The Builder or other approved Warrantors shall provide written warranties where so specified elsewhere in this specification.
2. Each Warranty shall be in approved from and shall specifically include the provisions required in writing.
3. Warranty periods shall commence from the date of the Notice of Practical Completion .
SECTION NAME NO.OF YEARS
Exterior Cladding 5 Years
Metal Roofing 7 Years
Metal Windows and Doors 5 Years
Painting 7 Years
Electr ical 5 Years
SUPPLEMENTARY CONDITIONS OF CONTRACT
1. Information to Subcontractors, Suppliers and Installers
Advise Sub-contractors and suppliers and installers of material of the requirements of these Supplementary
Conditions of Contract.
2. Amount of Security (Bank Guarantee)
Refer to Schedule 1 items 1, 2 and 3.
3. Interpretation of Drawings
The drawings, specification and all other documents represent generally the forms, dimensions and
descriptions of the works. The several documents, which constitute the Contract, shall be taken as mutually
explanatory. Should there be any discrepancy between the Drawings and the Specification, such discrepancy
is to be brought to the attention of the Architect at the time of Tender. Otherwise the Builder shall be
deemed to cover the alternative, which involved the greatest cost.
No ambiguity, conflict or discrepancy shall exist where a provision or requirement, which appears in one
document, is omitted from another. The Builder shall so far as is possible perform the work necessary to
complete all things in all the documents forming the Contract.
Check dimensions on site before proceeding with the work of the Contract.
It is the Builder’s responsibility to ensure sub-contractors received all documents for the purpose of
tendering. Sub- trade information may be contained on some drawings and not others and may be contained
within Specification clauses where it may appear to be not directly associated with a particular sub trade.
PART 4 READ AND KEEP THIS PART
4. Construction Progress Bar Graph
Within fourteen (14) calendar days after the date of Letter of Acceptance of tender, submit to the Architect a
detailed chart of the plan of progress, in Bar Graph form. For each item of work provided graph showing
planned progress with planned monthly quantities and with space or other provision for entering actual
progress. The Architect may require the Builder to provide an amended bar graph within seven(7) days of
being requested to do so.
Submit bar graph at monthly intervals showing actual progress.
5. Sub-Contractors and Suppliers
Within seven days of receipt of the Letter of Acceptance, supply to the Architect a complete list of Sub-
Contractors and Suppliers proposed for the Works. The Proprietor, through the Architect, reserves the right
to reject any so listed.
6. Indemnity of Proprietor
A. Indemnify, and keep indemnified the Proprietor against claim, demand, action, suit or proceeding that
may be brought or made against the Proprietor by any other person who has entered into a contract with
the Proprietor to execute work associated with the project.
B. Submit evidence of such insurance in respect of loss, damage or expense incurred by that other person by
reason of an act, default or neglect of the Builder in the performance of his obligations under the contract
or arising out of or as a consequence of delay by the Builder in executing or failing to complete work
under the contract and also from costs and expenses that may be incurred by that other person in
connection with such claim, demand, action, suit or proceeding.
C. Provide Homeowners Indemnity Insurance as required by law.
D. Do not proceed with work under the contract until evidence of indemnities and insurances required
herein, is submitted in writing to the Architect.
7. Approvals, Services, Fees and Tax
The following documents have been obtained by the proprietor, via the architect and fees paid for;
A. Planning permit and / or D.A.
B. Certificate of Design Compliance (CDC)
Be responsible for the connection or upgrade of services – water, sewerage, drainage, electricity and gas etc.
C. Pay for an submit an Application for Building Permit – Certified” and pay BCITF, Building Services Levy and
Permit Application;
D. Apply for such permits, pay for fees and charges levied by relevant bodies for such connections. Issue
necessary notices to such bodies. Obtain and pay for scaffolding permit.
E. In later trade sections where permits are required to be issued by local authorities a note to this effect is
provided for the subcontractor: Apply for permits and pay required fees and charges to responsible
authorities. Provide permits and approval certificates to builder”.
F. Pay Tax on items where such tax is applicable. If Tax is not applicable, request from the proprietor, via
the architect, a Tax exemption certificate for use when ordering specified materials.
PART 4 READ AND KEEP THIS PART
G. Pay fees, where applicable, relating to “Workplace Health and Safety” Acts and other state or local
government acts.
H. Pay for and submit an Application for a “Certificae of Construction Compliance (CCC).
I. Pay for an submit an Application for an Occupancy Permit.
8. Building and Construction Industry Training Fund and Levy
The Contractor is deemed to be the project owner under the Building and Construction Industry Training Fund
and Levy Collection Act 1990 (WA) and shall pay all levies required to be paid under this Act to the Building
and Construction Industry Training Fund. The Contractor must not commence work on the Site until it has
paid the levy.
The Building Act 2011 (WA) requires a permit issuing authority to be satisfied that the Building and
Construction Industry Training Fund and Levy has been paid prior to the issuance of a building permit. Within
14 days of the Date of Acceptance of Tender, the Contractor must provide evidence in writing that the
Building and Construction Industry Training Fund and Levy has been paid. A failure to provide such evidence
has the potential to delay the issuance of a building permit by the permit issuing authority.
Prior to Superintendent’s Representative issuing a Certificate of Practical Completion, where the costs of the
Works increase by an amount greater than $25,000, then:
a. Notwithstanding clause 42.1 of the General Conditions, the Contractor shall not become entitled to
receive any outstanding progress payments until it provides evidence to the Superintendent’s
Representative that it has paid any additional levy required to be paid into the Fund under the
Building and Construction Industry Training Fund and Levy Collection Act 1990 (WA), Building and
Construction Industry Training Levy Act 1990 (WA) and the Building Act 2011 (WA),; and
b. Notwithstanding any provision of the Contract to the contrary, the Contractor shall not become
entitled to the release of any remaining security or retention until it provides evidence to the
Superintendent’s Representative that it has paid any additional levy required to be paid into the
Fund under the Building and Construction Industry Training Fund and Levy Collection Act 1990 (WA),
Building and Construction Industry Training Levy Act 1990 (WA) and the Building Act 2011 (WA). The
payment of any additional levy under this clause shall constitute a variation in favour of the
Contractor, however the Contractor shall not be entitled to an Extension of Time as a result of such a
variation.
9. Site Control
A. Be responsible for activities on the site including providing access for authorised persons and restricting
access by unauthorised persons. Take necessary precautions to secure the assets of the Proprietor.
B. Except as otherwise provided in the contract, delivery of materials for the works, space for storage of
same and for building sheds, office and workshops will be allowed only as directed by the Builder.
PART 4 READ AND KEEP THIS PART
C. Do not store waste building materials and flammable liquids in the building.
D. Take proper precautions to keep poisons and other injurious substances in places secured against access
by unauthorised persons.
10. Compliance with Ordinances, etc.
Whenever work or type of plant or machinery, etc. is required either by the specification or by the relevant
statutory authority, provide full details of such work, plant, etc. to the relevant statutory authority and make
such applications, etc. as may be required within two weeks of receipt of Letter of Acceptance.
In such cases, approval given by the Architect to data submitted by the Builder will not necessarily imply that
such data meet the requirements of the relevant statutory authority.
11. Site Amenities and Meetings
A. Provide statutory and necessary amenities and sanitary facilities for site workers where such are not
already available in suitable locations. Maintain in working condition and clean daily. Comply with
Union requirements.
B. Provide accommodation on the site of sufficient size to hold regular site meetings of Building
Foreman, Architect and Consultants.
C. Arrange for site meetings to occur at regular intervals throughout the contract period. Advise
Architect and Consultants of meeting times, keep accurate records of each meeting, and issue to
each Attendee a copy of the record within three days of each meeting.
12. Temporary Fire Extinguishers
Maintain fully charged, and accessible fire extinguishers as are necessary for the care and safety of the
Works, as required by local Fire Authority.
13. Telephone and Fax
Provide either a mobile telephone or a telephone service and pay costs of installation, rental, calls and
removal.
14. Light and Power
Provide temporary electric light and power supply during construction and pay charges connected therewith.
Provide sufficient of each as required for execution of work specified.
15. Water
Provide and maintain a temporary water supply sufficient for executing the work under the contract.
Disconnect and clear away same on completion and pay costs and charges in connection therewith. Provide
tapping of main supply if required.
16. Project Identification Sign
Provide and erect a project identification sign in accordance with the Drawing supplied by the Architect
(located in Appendix B) and amendment thereto and erect same on the site as directed and maintain same in
good condition throughout the currency of the contract. The sign shall remain the property of the Builder.
Remove same from the site on completion of the Works.
17. Commencement of Work
Notwithstanding that possession of the site has been given to the Builder, the Builder shall not be permitted
to commence work on the site until he has provided:
PART 4 READ AND KEEP THIS PART
A. Security required by the Conditions of Contract, as stated in the Annexure to the Conditions of
Contract.
B. Insurances: refer Clause 6 above.
18. Adjacent Premises
Ensure that the work is carried out without damage to and with a minimum of nuisance or annoyance to
the occupants of adjacent premises.
Provide a thorough photographic record of surfaces of existing buildings adjacent to the site.
19. General Attendance on Sub-Contractors
General attendance shall include taking delivery, assisting to unload, storing and protecting Sub- Contractor's
materials and for allowing Sub-Contractors ample working space, free use of water, electricity (unless
otherwise described), scaffolding, hoists and ordinary plant, etc., and messing and sanitary accommodation
and for cutting away, building in and protecting finished work and making good.
20. Precautions in Carrying Out Work Under the Contract Unless otherwise specified in the contract, observe, in the absence of statutory requirement to the contrary,
the relevant current Australian Standard published by Standards Australia relating to storage, transport, use
of materials, explosives, fire precautions in arc or flame cutting flame heating and arc or gas welding
operations, plant and equipment, work processes and safety precautions.
21. Joining Up Existing Buildings Where the method of joining up of old and new work is not otherwise specified the cut away and join up in a
manner approved by the architect and made good by relevant trades to match existing adjacent work.
22. Interference with Existing Services Notify the Architect of connection, disconnection or interference with existing services.
Repair, to the satisfaction of the Architect, damage which occurs to services during currency of the contract.
23. Damaged Services Where existing services at or adjacent to the site are in non-optimum condition, arrange for an inspection by
the Architect and the Officer-in-charge of the area responsible for such service. At such meeting, record the
condition and follow instructions when issued in writing by the Architect.
24. Solid, Liquid and Gaseous Contaminants A. Be responsible for the proper disposal of solids, liquid and gaseous contaminants.
B. Discharge gaseous contaminants in such a manner that they will be sufficiently diluted with fresh air
that the toxicity will be reduced to an acceptable level.
C. Subject to statutory and local requirements, liquid contaminant may be diluted with water to a level
of quality acceptable in the sewer system or contained in approved vessels for disposal at sites
approved by the relevant Authority.
D. Dispose of solid contaminants by removal from the site to locations approved by the relevant
Authority.
25. Disposal of Refuse Refuse from construction operation (including food scraps and the like) shall be removed from the site at
frequent intervals.
PART 4 READ AND KEEP THIS PART
26. Explosive Devices
Powder powered fixing tools may be used.
27. Dimensioning Do not scale from drawings.
28. Shop drawings Shop drawings mean complete drawings showing details of fabrication, assembly, installation, fixing and
waterproofing methods of specific items or components, and shall include necessary explanatory notes and
specifications.
When preparing shop drawings, do the following:
A. Include provision in construction programme for the production and distribution of shop drawings.
B. Refer discrepancies discovered in the contract documents to the Architect for direction.
C. Verify relevant dimensions. Dimension drawings so that the items or components fit accurately into the required positions.
D. Ensure that shop drawings conform with the requirements of the contract.
E. Drawings shall be of consistent standard size and presentation.
F. Submit 4 initial copies, one of each of the following: Specialist Subcontractor, Builder, Architect, relevant Consultant. Subcontractor submits 4 and gets 1 back. Builder submits 4 and gets 2 back. All parties retain one copy. If amendments are required, one copy will be marked and returned to the Builder for amendments to the original shop drawings. (This process may be repeated until the Architect considers that the shop drawings are satisfactory.) Do not fax shop drawings as they are often illegible on receipt.
G. When the shop drawings are satisfactory, one copy will be stamped by the Architect. Supply two additional copies of the satisfactory shop drawings to the Architect. Provide also as required for the Builder's site office, manufacturers or Sub-Contractors.
H. Acceptance of shop drawings shall imply only that the Builder's interpretations of the relevant requirements of the contract are generally correct, but shall in no way relieve the Builder of his obligations under the contract to construct and complete the Works correctly and accurately.
I. Do not order, manufacture, assemble or supply any item or component needed according to requirements of shop drawings until the Architect returns the applicable stamped drawings.
29. Care of the Works
A. Delivery, Handling and Storage: Deliver, handle and store products in accordance with manufacturer's recommendations and by methods and means which will prevent damage, deterioration, and loss including theft. Control delivery schedules to minimise long-term storage of products at site and over-crowding of construction spaces. In particular, co- ordinate delivery and/or installation to ensure minimum holding or storage times for products recognised to be flammable, hazardous, easily damaged, or sensitive to deterioration, theft and other sources of loss.
B. Limiting Exposure of Work: To the extent possible, through control and protection methods, supervise performance of work in a manner which will ensure that none of the work, whether completed or in progress, will be subjected to harmful, dangerous, or damaging exposures during construction period.
C. Cleaning and Protection of Finished Work: General: during handling and installation of work as project proceeds, clean site and protect work in progress and adjoining work on a basis of perpetual maintenance. Apply suitable protective covering on newly installed work where required to ensure freedom from damage or deterioration at a time of Practical Completion; otherwise, clean and perform maintenance on newly installed work as frequently as necessary throughout remainder of construction period. Adjust and lubricate operable components to ensure equipment operates as intended.
PART 4 READ AND KEEP THIS PART
30. General Product Compliance
A. Provide products which comply with requirements, and which are undamaged and unused at time of installation, and which are complete with accessories, trim, finish, features required by regulation, and other devices and details needed for a complete installation and for intended use and effect.
B. Standard Products: where available, provide standard products of types which have been produced and used previously and successfully on other projects and in similar applications.
C. Continued Availability: where additional amounts of a product, by its application, are likely to be needed by Proprietor at a later date for maintenance and repair or replacement work, provide a standard, domestically produced product which is likely to be available to Proprietor at such later date.
D. Manufacturer's recommendations: where installations include manufactured products, comply with manufacturer's current and applicable recommendations for installation, to whatever extent these are more explicit or more stringent than applicable requirements indicated in contract Documents.
E. At completion of project, provide to the Architect a copy of each set of Manufacturer's recommendations which have been used in the work of each trade.
F. Manufacturer's Data Sheets: where this specification requires, obtain two copies of the current data sheets issued by the manufacturer of specified component. Retain one copy for use on site and submit the other to the Architect as a record of instructions followed on the site.
31. Builder's Quality Control
A. Inspect each item of materials or equipment immediately prior to installation and reject damaged or defective items.
B. Provide attachment and connection devices and methods for securing materials properly as they are installed, true to line and level, and within recognised industry tolerances unless otherwise indicated. Allow for expansion and building movements. Provide uniform joint widths in exposed Work, organised for best possible visual effect. Refer questionable visual effect choices to the Architect.
C. Re-check measurements and dimensions of the Work as an integral step before starting each installation.
D. Install work during conditions of temperature, humidity, exposure and weather which will ensure the best possible results for each part of the work, or component or treatment as necessary to prevent damage and deterioration.
E. Co-ordinate enclosure and closing-in of work with required inspections and tests, so as to avoid necessity of uncovering work for that purpose.
32. Quality Assurance A. Provision of a formal quality assurance system is not required.
33. Material/Colour Selections
A. The Architect will prepare a master Colour Schedule indicating the required colour, finish, pattern, material, texture and other pertinent information in connection with interior and exterior finishes.
B. Submit colour chips for items having colour unless otherwise directed or approved by Architect.
C. To facilitate the preparation of such a schedule, submit within fifteen days following date of award of contract, unless otherwise extended by the Architect, the names and products of those manufacturers whose products are proposed for use within the framework of the specifications wherever colour, finish, pattern, texture and other related information is a consideration.
PART 4 READ AND KEEP THIS PART
34. Miscellaneous Completion Procedures
A. Removal of Protection: except as otherwise indicated or requested by Architect, remove temporary protection devices and facilities installed during course of the work to protect previously-completed work. Where secured to exposed-to-view new work or existing to remain, remove evidence of protection devices. Remove protection within 5 days before Practical Completion.
B. Trade Cleaning: as each trade completes its work in each area of the building, the Sub- Contractor is required to be responsible for "broom clean" standard of cleaning in that area.
35. Final Cleaning
Final Cleaning: provide final cleaning of the work of this specification, at time indicated, consisting of cleaning each surface of unit of work to normal 'clean' condition expected for a first class building cleaning and maintenance programme.
Examples of required cleaning are:
A. Remove labels which are not required as permanent labels.
B. Clean transparent materials, including mirrors and window/door glass, to a polished condition, removing substances which are noticeable as vision-obscuring materials. Replace broken glass and damaged transparent materials.
C. Clean exposed exterior and interior hard surfaces finished, to a dirt free condition, free of dust, stains, finger marks, films and similar noticeable distracting substances. Except as otherwise indicated, avoid disturbance of natural weathering of exterior surfaces.
D. Restore reflective surfaces to original reflective condition.
E. Wipe clean surface of mechanical and electrical equipment, including lift and similar equipment; remove excess lubrication and other substances.
F. Remove debris and surface dust from limited access spaces.
G. Clean concrete floors broom clean.
H. Vacuum clean carpet and similar soft surfaces.
I. Clean plumbing fixtures to a sanitary and polished condition, free of stains including those resulting from water exposure.
J. Clean light fixtures and lamps so as to function with full efficiency.
K. If permanent lighting fixtures have been used for construction purposes replace globes with new.
L. Clean project site, including planted sections and footpaths, of litter and foreign substances. Sweep paved areas to a broom clean condition; remove stains, petro-chemical spills and other foreign deposits. Label keys for locks accurately and provide in duplicate to the Architect at the completion of the project.
36. Clean Site and Access Roads
A. Be responsible for maintaining clean roads and access. Remove and clean away mud, building debris from footpaths, gutters, drains, walls etc. when such occurs.
37. Warranties
Provide written warranties as set out in this document.
38. Authority Approvals and Certificates
A. Prior to the issue of a Practical Completion Notice for the whole or section of the work, lodge with the Permit Authority an application for an Occupancy Permit.
B. Produce to the Architect a certificate of clearance of reinstatement of damage to footpaths and road, etc. from the appropriate Road Authority or Shire Engineer before issue of Practical Completion Notice.
39. Contract Stamp Duty
If contract is liable to stamp duty, the Builder shall provide to the Architect at time of signing the contract, duty stamps to the value required by the state in which the project is being constructed, together with one new copy of the printed Conditions of Contract being used in this project.
PART 4 READ AND KEEP THIS PART
40. Asbestos
No asbestos products or asbestos based materials shall be used in any part or parts of this building or its services and the Builder shall ensure that Sub-Contractors, Nominated Sub-Contractors, suppliers and others are advised of this restriction.
No compensation will be paid if asbestos is brought on to the site and subsequently discovered and if discovered such removal and consequential making good or costs will be totally at the expense of the Builder.
41. Patent Rights
Ensure that no patent is infringed and that unless otherwise specified, amounts payable and conditions imposed in respect of the manufacture, use or exercise of patented invention are paid and complied with and shall indemnify the Proprietor against claims, damages, costs, charges and expenses in any way whatsoever arising out of the manufacture, use or exercise by the Builder of patented invention.
42. Allowances
The proprietor shall not be liable for any Union dues, Building Union Superannuation fee or loading. The Contract shall not be subject to any adjustments for any site, dust, clothing, structural or any monetary or other allowances or lading granted, awarded or requested of the Builder or any of his employees, sub-contractors or sub-contractor’s employees after the closing time and date of tenders. Tenders received, which clarify or exclude the above as a condition of the tender may be considered invalid.
43. Record of Services
In order to enable issuing of a Certificate of Construction Compliance (CCC) the Contractor will be required to produce an as constructed record of the project in both soft and hard copies.
Obtain from the Architect and consultants the DWG files for the project and update to reflect construction on site and return to the Architect 2 weeks prior to Practical Completion to enable checking.
Contractor shall liaise with sub consultants for the provision of ‘As Constructed Services” documentation of Electrical, Hydraulic and Mechanical Services.
Approved Completed ‘As Constructed’ documentation and manuals shall be submitted to the Architect prior to Practical Completion.
Contractor shall ensure all drawings are prepared on Auto Cad Version 2008 or better. Copies shall be provided on CD in addition to bound A3 copy. All ‘As Constructed’ drawings shall be documented in accordance with the BMW CAD documentation procedures manual.
Provide two (2) copies of drawings and manuals of professional quality comprising of heavy duty foolscap 4 ring files with printed identification lettering.
Copies shall also be provided to the building surveyor as part of the CCC process.
Occupation of the building is not possible until the Occupancy Permit is provided, and therefore Practical Completion will not be awarded until the Occupancy Permit is provided to the Superintendent.
44. Payment of workers and subcontractors
(a) Before the Principal makes each payment to the Contractor, the Architect may, not less than 5 days before a payment certificate is due, in writing request the Contractor:
i. to give the Architect a statutory declaration by the Contractor or, where the Contractor is a corporation, by a representative of the Contractor who is in a position to know the facts declared,
that all workers who have at any time been employed by the Contractor on work under the contract have at the date of the request been paid all moneys due and payable to them in respect of their employment on the work under the contract; and
ii. to provide documentary evidence to the Architect that at the date of the request all workers who have been employed by a subcontractor of the Contractor have been paid all moneys due and payable to them in respect of their employment on the work under the contract.
(b) Not earlier than 14 days after the Contractor has made each claim for payment, and before the Principal makes that payment to the Contractor, the Contractor shall give to the Architect a statutory declaration by the Contractor or, where the Contractor is a corporation, by a
PART 4 READ AND KEEP THIS PART
representative of the Contractor who is in a position to know the facts declared, that all subcontractors have been paid all moneys due and payable to them in respect of work under the contract.
(c) If the Contractor fails-
i. within five days after a request by the Architect to provide the statutory declaration, or the documentary evidence (as the case may be) required, or fails :
ii. to comply with these requirements, payment of moneys to the Contractor may be withheld by the Principal until the statutory declaration or the documentary evidence (as the case may be) is received by the Architect.
If the Contractor provides to the Architect satisfactory proof of the maximum amount due and payable to workers and subcontractors by the Contractor, the Principal shall not be entitled to withhold any amount in excess of the maximum amount. At the written request of the Contractor, from and out of, moneys payable to the Contractor, the Principal may on behalf of the Contractor make payments directly to any worker or subcontractor. If any worker or subcontractor obtains a court order in respect of moneys referred to in clause b or c above and produces to the Principal the court order and a statutory declaration that it remains unpaid, the Principal may pay the amount of the order, and costs included in the order, to the worker or subcontractor and the amount paid shall be a debt due from the Contractor to the Principal. After the making of a sequestration order or a winding up order in respect of the Contractor, the Principal shall not make any payment to a worker or subcontractor without the concurrence of the official receiver or trustee of the bankrupt or the liquidator as the case may be.
45. Building Act (2011)
COMPLIANCE
Under this new legislative regime, the Principal is required to apply to a permit authority for building permits, demolition permits, occupancy permits and/or building approval certificates as the case may be in relation to specified types of building work and demolition work as defined by the Building Act 2011 (WA). The Contractor will be responsible for submitting permit applications to the permit issuing authority.
Consistent with this new legislative regime, the Contractor must:
(a) undertake to do all things and take all steps reasonably necessary to enable the Principal to obtain or vary building, demolition or occupancy permits (as the case may be) for the works under the Contract;
(b) ensure that any building or demolition work is carried out pursuant to all requirements of the building or demolition permits (as the case may be) and any conditions that may be imposed on such permits;
(c) ensure that any building or demolition work is undertaken in accordance with the design documentation or any variations directed under the Contract;
(d) ensure that any building or demolition work carried out complies with any building orders issued by the permit authority;
(e) ensure that where any variations affect compliance with any relevant code or standard, the Contractor assists the Principal and its agents to do all things necessary to facilitate the recertification of the work under the Contract;
(f) ensure that all inspections and tests required under the building, demolition or occupancy permit, or otherwise required by the building certifier or building surveyor at any time when certifying the works, are carried out on Site during construction and provide documentation of results in a timely manner to the building certifier or building surveyor and the Principal so as to not prejudice or delay the issuance of a construction compliance certificate;
(g) duly obtain a certificate of construction compliance to permit the timely application for an occupancy permit or building approval certificate as the case may be from the permit authority to enable lawful occupancy of the building(s) or any part(s) thereof within the program timeframes required by the Principal and the Contract;
PART 4 READ AND KEEP THIS PART
(h) take into account the time periods and limits prescribed under the Building Act 2011 (WA) in its
construction program;
i. provide such further information or materials that the permit authority may reasonably require to support an application or impose conditions on the permit or certificate;
(i) otherwise comply with the following Acts and any subsidiary legislation made under them:
i. Building Act 2011 (WA);
ii. Building Services (Complaint Resolution and Administration) Act 2011 (WA);
iii. Building Services (Registration) Act 2011 (WA);
iv. Building Services Levy Act 2011 (WA); and
v. Building and Construction Industry Training Levy Act 2011 (WA), without limiting the Contractor’s general obligations under the Contract.
PERMIT AUTHORITY
The Permit Authority in this instance is the Shire of Perenjori.
46. Occupancy Permit
Occupation of the building is not possible until the Occupancy Permit is issued and provided, and therefore Practical Completion will not be awarded until the Occupancy Permit is provided.
This in turn will be dependent on the provision of:
1. Certificate of Compliance for electrical installation in accordance with Health Regulations for Public Buildings.
2. As-Constructed Drawings and manuals.
3. Such other information as requested by the Building Surveyor.
PART 5 COMPLETE AND RETURN THIS PART
TENDERER’S OFFER
OFFER FORM
The Chief Executive Officer SHIRE OF PERENJORI PO BOX 22 OR 40 FOWLER STREET, PERENJORI WA 6620 I/We (Registered Entity Name) (BLOCK LETTERS) of (REGISTERED STREET ADDRESS) ABN ________________________________ACN (if any)
Telephone No: __________________________________Facsimile No:
E-mail (if any): In response to RFT 02/2013 – PERENJORI BUSINESS CENTRE RE-DEVELOPMENT: 1/We agree that I am/We are bound by, and will comply with this Request and its associated schedules, attachments, all in accordance with the Conditions of Tendering contained in this Request signed and completed. The tendered price is valid up to ninety (90) calendar days from the date of the tender closing or forty-five (45) days from the Council’s resolution for determining the Tender, whichever is the later unless extended on mutual agreement between the Principal and the Tenderer in writing. I/We agree that there will be no cost payable by the Principal towards the preparation or submission of this Tender irrespective of its outcome. The tendered consideration is as provided under the schedule of rates of prices in the prescribed format and submitted with this Tender.
Dated this __________ day of ______________________20___
Signature of authorised signatory of Tenderer:
Name of authorised signatory (BLOCK LETTERS):
Position:
Telephone Number:
Authorised signatory Postal address:
Email Address:
PART 5 COMPLETE AND RETURN THIS PART
SELECTION CRITERIA
COMPLIANCE CRITERIA
Description of Compliance Criteria
(a) Tenderers are to provide acknowledgment that your organisation has submitted in accordance with the Conditions of Tender including completion of the Offer Form and provision of your pricing submitted in the format required by the Principal.
Yes / No
(b) Tenderers are to provide their
Certificates of Currency
Certified copies of business registration
Yes / No
(c) Compliance with the Specification contained in the Request. Yes / No
(d) Compliance with the Quality Assurance requirement for this Request. Yes / No
(e) Compliance with the Delivery Date. Yes / No
(f) Compliance with Environmental and OSH management plans Yes / No
QUALITATIVE CRITERIA
Before responding to the following qualitative criteria, Tenderers must note the following:
All information relevant to your answers to each criterion are to be contained within your Tender;
Tenderers are to assume that the Evaluation Panel has no previous knowledge of your organisation, its activities or experience;
Tenderers are to provide full details for any claims, statements or examples used to address the qualitative criteria; and
Tenderers are to address each issue outlined within a qualitative criterion.
A) Relevant Experience
Tenderers must address the following information in an attachment and
label it “Relevant Experience”:
(a) Provide details of similar work;
(b) Provide scope of the Tenderer’s involvement including details of outcomes;
(c) Provide details of issues that arose during the project and how these were managed;
(d) Demonstrate competency and proven track record of achieving outcomes.
(e) Demonstrate competency of achieving milestones as per project timelines
Weighting
<25%>
“Relevant
Experience”
Tick if
attached
PART 5 COMPLETE AND RETURN THIS PART
B) Key Personnel skills and experience
Tenderers must address the following information in an attachment and
label it “Key Personnel Skills and Experience”:
(a) Their role in the performance of the Contract;
(b) Curriculum vitae inclusive of, Membership to any professional or business association; Qualifications;
Supply details in an attachment and label it “Key Personnel”.
Weighting
<25%>
“Key Personnel”
Tick if
attached
C) Tenderer’s Resources
Tenderers must address the following information in an attachment and
label it “Tenderers Resources”:
(a) Plant, equipment and materials; and
(b) Any contingency measures or back up of resources including personnel (where applicable).
As a minimum, Tenderers should provide a current commitment schedule
and plant/equipment schedule in an attachment and label it “Tenderer’s
Resources”.
Weighting
<10%>
“Tenderer’s
Resources”
Tick if
attached
D) Demonstrated Understanding
Tenderers must address the following information in an attachment and
label it “Demonstrated Understanding”:
(a) A project schedule/timeline (where applicable);
(b) The process for the delivery of the goods/services;
Supply details and provide an outline of your proposed methodology in an
attachment labelled “Demonstrated Understanding”.
Weighting
<25%>
“Demonstrated
Understanding”
Tick if
attached
E) Risk Assessment
Tenderers must address the following information in an attachment and
label it “Risk Assessment”:
(a) An outline of your organisational structure inclusive of any branches and number of personnel.
(b) If companies are involved, attach their current ASC company extracts search including latest annual return.
(c) Provide the organisations directors/company owners and any other positions held with other organisations.
(d) Provide a summary of the number of years your organisation has been in business.
(e) Attach details of your referees. You should give examples of work provided for your referees where possible.
(f) Are you acting as an agent for another party? If Yes, attach details (including name and address) of your principal
(g) Are you acting as a trustee of a trust? If Yes, give the name of the trust and include a copy of the trust deed (and any related documents);and if there is no trust deed, provide the names and addresses of beneficiaries.
(h) Do you intend to subcontract any of the Requirements?
If Yes provide details of the subcontractor(s) including; the name, address and the number of people employed; and the Requirements that will be subcontracted.
(i) Will any actual or potential conflict of interest in the performance of your obligations under the Contract exist if you are awarded the Contract, or are any such conflicts of interest likely to arise during the Contract?
If Yes, please supply in an attachment details of any actual or potential conflict of interest and the way in which any conflict will be dealt with
(j) Are you presently able to pay all your debts in full as and when they fall due?
(k) Are you currently engaged in litigation as a result of which you may be liable for $50,000 or more?
If Yes please provide details.
(l) In order to demonstrate your financial ability to undertake this contract, include a profit and loss statement and the latest financial return for you and each of the other proposed contracting entities, together with a list of financial referees from your bank and/or accountant.
(m) The insurance requirements for this Request are stipulated in Part 3 of this Request. Tenderers are to supply evidence of their insurance coverage including, insurer, expiry date, value and type of insurance. If Tenderer hold “umbrella Insurance” please ensure a breakdown of the required insurances are provided. A copy of the Certificate of Currency is to be provided to the Principal within 30 days of acceptance.
Weighting
<15%>
“Risk
Assessment”
Tick if
attached
PRICE INFORMATION
Tenderers must complete the following “Price Schedule”. Before completing the Price Schedule,
Tenderers should ensure they have read this entire Request.
PRICE BASIS
Are you prepared to offer a fixed price? Yes / No
PRICE SCHEDULE
LUMP SUM SERVICES
No Service Description Price Tendered
(ex GST) GST
Price Tendered
(inc GST)
1. Locate & Isolate Services through site
2. Remove Existing transportable
ablution building
3. Liaise with plumber regarding
isolation of hydraulic services to
transportable
4. Remove vegetation to works area
5. Remove sections of fencing as
required
6. Break up and remove bitumen as
required
7. Break up and remove or lift
concrete paving
8. Cut back concrete paving to
crossover
9. Cut back to near lines paving to
remain
10. Remove asbestos cement fencing as
drawn
11. Liaise with electrician regarding
isolation and removal of electrical
items
12. Remove framed room structures
from within existing building
13. Remove RAC air-conditioners from
walls
14. Locate existing water service to
existing ablution building
15. Locate existing sewer service to
existing ablution building and
extend to new tenancy facilities and
to new ablution
16. Supply and install spoon drains to
No Service Description Price Tendered
(ex GST) GST
Price Tendered
(inc GST)
downpipes
17. Supply and install new soak wells
18. Supply and install 100mm PVC
stormwater pipe secured to rear of
shed to collect and dis-charge
stormwater from the roof
downpipes
19. Supply and install trough and tap-
ware to each tenancy
20. Supply and install standpipe to each
tenancy
21. Supply and install new fixtures and
fittings to ablution block
22. Supply and install new drainage
channel and grate at thresholds
23. Supply and install new drains to
ablution block
24. Supply and install materials and
equipment required to connect new
buildings to existing septics
25. Supply and install materials and
equipment required to connect new
buildings to water supply
26. Supply and install approved RPZ
valve onto
27. Supply and install road grates and
soak-wells
28. Prepare sub-base for areas to be
bitumen paved
29. Supply and lay compacted road base
30. Construct non-mountable concrete
kerbs as drawn
31. Supply and lay bituminous concrete
paving
32. Provide line marking as drawn
33. Supply and lay masonry unit pavers
as drawn
34. Supply and lay in-situ concrete
building slab and footings as drawn
35. Construct concrete plinth to new
MSSB
36. Provide concrete footings to fences
and gates as required
No Service Description Price Tendered
(ex GST) GST
Price Tendered
(inc GST)
37. Fabricate and install steel columns
to building front elevations
38. Fabricate and install miscellaneouse
steel brackets and cleats as required
39. Supply and install roller shutters to
tenancies
40. Supply and install fixtures and
fittings to toilets
41. Supply and install palisade fencing
where drawn
42. Supply and install Colorbond sheet
fencing where drawn
43. Supply and install wall framing to
front elevations as drawn
44. Supply and install exterior cladding
as drawn.
45. Supply and retro-fit insulation to
existing shed walls and roof
46. Supply and install insulation to new
walls
47. Construct wall and roof framing to
new ablution block
48. Supply and install exterior and
interior linings to new ablutions
49. Supply and install new doors and
frames to tenancies and ablutions
50. Supply and install wall framing
between tenancies
51. Supply and install fibre-cement
lining over plasterboard to dividing
walls
52. Supply and install new full wall
sheets to replace those with holes
from removed services
53. Supply and install new exterior
metal cladding to building as drawn
54. Supply and install aluminium door
frames
55. Supply and install new windows to
ablution block
56. Supply and install new fire rated
wall sheets to dividing walls
57. Prepare and paint existing steelwork
to shed (excluding purlins and girts)
58. Prepare and paint new steelwork to
shed
No Service Description Price Tendered
(ex GST) GST
Price Tendered
(inc GST)
59. Prepare and exterior fibre-cement
cladding (allow for 4 colours)
60. Prepare and paint interior lining
61. Prepare and paint doors and frames
62. Remove electrical services to
existing building
63. Supply and install new MSSB
64. Liaise with Western Power
regarding upgrade of site power
supply and new dome
65. Supply and install new load centres
to tenancies
66. Supply and install new power
circuits as drawn
67. Supply and install new lighting
circuits and fittings as drawn
68. Extend communications service
from existing MDF system as drawn.
APPENDIX A – ELECTRICAL
APPENDIX B – ARCHITECT TENDER SPECIFICATION
TENDERING, PRE-CONTRACT INFORMATION
TABLE OF CONTENTS
DOCUMENT 00860 Drawings 17
APPENDICES
APPENDIX B Photographs
APPENDIX B
PHOTOGRAPHS