reserve analysis sample hoa...2013/08/19 · p.o. box 1762 • castle rock, co 80104 • phone...
TRANSCRIPT
P.O. Box 1762 • Castle Rock, CO 80104 • Phone (303) 790-7572 • Fax (303) 688-3083 www.aspenrs.com
Treehouse Condominiums
Ryan Gulch Road Silverthorne, CO 80498
Level 1 Reserve Analysis
Report Period – 01/01/13 – 12/31/13
Client Reference Number - 8508 Property Type – Condominiums Number of Units – 249 Fiscal Year End – December 31
Date of Property Observation - November and December 2012, January 2013 Project Manager - G. Michael Kelsen, RS, PRA Main Contact Person - Ms. Barb Walter, Community Manager Report was prepared on - Monday, August 19, 2013
FINAL REPORT
Table of Contents SECTION 1:
Introduction to Reserve Analysis--------------------------------------------------------------page 1
General Information and Answers to FAQ’s------------------------------------------pages 2 - 3
Summary of Reserve Analysis------------------------------------------------------------------page 4
SECTION 2:
Physical Analysis (Photographic) Common Area Grounds---------------------------------------------------------------------pages 1 – 16 Buildings A – I----------------------------------------------------------------------------------pages 1 – 30 Buildings J – K---------------------------------------------------------------------------------pages 1 – 13 Guest Clubhouse------------------------------------------------------------------------------pages 1 – 46 Owner’s Clubhouse---------------------------------------------------------------------------pages 1 – 31
SECTION 3:
Financial Analysis
a) Funding Summary-------------------------------------------------------------------------------------page 1 b) Percent Funded – Graph----------------------------------------------------------------------------page 2 c) Asset Inventory List
Common Area Grounds------------------------------------------------------------------------------page 3 Buildings A – I-----------------------------------------------------------------------------------------pages 4 Buildings J – K----------------------------------------------------------------------------------------pages 5 Guest Clubhouse-------------------------------------------------------------------------------------pages 6 Owner’s Clubhouse----------------------------------------------------------------------------------pages 7
d) Significant Components Table---------------------------------------------------------------pages 8 – 9 e) Significant Components – Graph----------------------------------------------------------------page 10 f) Yearly Summary Table-----------------------------------------------------------------------------page 11 g) Yearly Contributions – Graph---------------------------------------------------------------------page 12 h) Component Funding Information--------------------------------------------------------pages 13 – 15 i) Yearly Cash Flow Table----------------------------------------------------------------------------page 16 j) Projected Expenditures Year by Year – Graph ----------------------------------------------page 17k) Projected Expenditures Year by Year --------------------------------------------------pages 18 – 23
SECTION 4: Glossary of Terms and Definitions------------------------------------------------------pages 1 - 2
1
Introduction to the Reserve Analysis – The elected officials of this association made a wise decision to invest in a Reserve Analysis to get a better understanding of the status of the Reserve funds. This Analysis will be a valuable tool to assist the Board of Directors in making the decision to which the dues are derived. Typically, the Reserve contribution makes up 15% - 40% of the association’s total budget. Therefore, Reserves is considered to be a significant part of the overall monthly association payment. Every association conducts its business within a budget. There are typically two main parts to this budget, Operating and Reserves. The Operating budget includes all expenses that are fixed on an annual basis. These would include management fees, maintenance fees, utilities, etc. The Reserves is primarily made up of Capital Replacement items such as asphalt, roofing, fencing, mechanical equipment, etc., that do not normally occur on an annual basis. The Reserve Analysis is also broken down into two different parts, the Physical Analysis and the Financial Analysis. The Physical Analysis is information regarding the physical status and replacement cost of major common area components that the association is responsible to maintain. It is important to understand that while the Component Inventory will remain relatively “stable” from year to year, the Condition Assessment and Life/Valuation Estimates will most likely vary from year to year. You can find this information in the Asset Inventory Section (Section 2) of this Reserve Analysis. The Financial Analysis Section is the evaluation of the association’s Reserve balance, income, and expenses. This is made up of a finding of the clients current Reserve Fund Status (measured as Percent Funded) and a recommendation for an appropriate Reserve Allocation rate (also known as the Funding Plan). You can find this information in Section 3 (pages 1 – 13) of this Reserve Analysis. The purpose of this Reserve Analysis is to provide an educated estimate as to what the Reserve Allocation needs to be. The detailed schedules will serve as an advanced warning that major projects will need to be addressed in the future. This will allow the Board of Directors to have ample timing to obtain competitive estimates and bids that will result in cost savings to the individual homeowners. This will also ensure the physical well being of the property and ultimately enhance each owner’s investment, while limiting the possibility of unexpected major projects that may lead to Special Assessments. It is important for the client, homeowners, and potential future homeowners to understand that the information contained in this analysis is based on estimates and assumptions gathered from various sources. Estimated life expectancies and cycles are based upon conditions that were readily visible and accessible at time of the observation. No destructive or intrusive methods (such as entering the walls to inspect the condition of electrical wiring, plumbing lines, and telephone wires) were performed. In addition, environmental hazards (such as lead paint, asbestos, radon, etc.), construction defects, and acts of nature have not been investigated in the preparation of this report. If problem areas were revealed, a reasonable effort has been made to include these items within the report. While every effort has been made to ensure accurate results, this report reflects the judgement of Aspen Reserve Specialties and should not be construed as a guarantee or assurance of predicting future events.
2
General Information and Answers to Frequently Asked Questions – Why is it important to perform a Reserve Study? As previously mentioned, the Reserve allocation makes up a significant portion of the total monthly dues. This report provides the essential information that is needed to guide the Board of Directors in establishing the budget in order to run the daily operations of your association. It is suggested that a third party professionally prepare a Reserve Study since there is no vested interest in the property. Also, a professional knows what to look for and how to properly develop an accurate and reliable component list. Now that we have “it”, what do we do with “it”? Hopefully, you will not look at this report and think it is too cumbersome to understand. Our intention is to make this Reserve Analysis very easy to read and understand. Please take the time to review it carefully and make sure the “main ingredients” (asset information) are complete and accurate. If there are any inaccuracies, please inform us immediately so we may revise the report. Once you feel the report is an accurate tool to work from, use it to help establish your budget for the upcoming fiscal year. The Reserve allocation makes up a significant portion of the total monthly dues and this report should help you determine the correct amount of money to go into the Reserve fund. Additionally, the Reserve Study should act as a guide to obtain proposals in advance of pending normal maintenance and replacement projects. This will give you an opportunity to shop around for the best price available. The Reserve Study should be readily available for Real Estate agents, brokerage firms, and lending institutions for potential future homeowners. As the importance of Reserves becomes more of a household term, people are requesting homeowners associations to reveal the strength of the Reserve fund prior to purchasing a condominium or townhome. How often do we update or review “it”? Unfortunately, there is a misconception that these reports are good for an extended period of time since the report has projections for the next 30 years. Just like any major line item in the budget, the Reserve Analysis should be reviewed each year before the budget is established. Invariably, some assumptions have to be made during the compilation of this analysis. Anticipated events may not materialize and unpredictable circumstances could occur. Aging rates and repair/replacement costs will vary from causes that are unforeseen. Earned interest rates may vary from year to year. These variations could alter the content of the Reserve Analysis. Therefore, this analysis should be reviewed annually, and a property observation should be conducted at least once every three years. Is it the law to have a Reserve Study conducted? The Government requires reserve analyses in approximately 20 states. The State of Colorado currently requires all associations to adopt a Reserve policy, but does not currently enforce a Reserve Study is completed. Despite enacting this current law, the chances are also very good the documents of the association require the association to have a Reserve fund established. This may not mean a Reserve Analysis is required, but how are you going to know there are enough funds in the account if you don’t have the proper information? Hypothetically, some associations look at the Reserve fund and think $50,000 is a lot of money and they are in good shape. What they don’t know is the roof will need to be replaced within 5 years, and the cost of the roof is going to exceed $75,000. So while $50,000 sounds like a lot of money, in reality it won’t even cover the cost of a roof, let alone all the other amenities the association is responsible to maintain.
3
What makes an asset a “Reserve” item versus an “Operating” item? A “Reserve” asset is an item that is the responsibility of the association to maintain, has a limited Useful Life, predictable Remaining Useful Life expectancies, typically occurs on a cyclical basis that exceeds 1 year, and costs above a minimum threshold cost. An “operating” expense is typically a fixed expense that occurs on an annual basis. For instance, minor repairs to a roof for damage caused by high winds or other weather elements would be considered an “operating” expense. However, if the entire roof needs to be replaced because it has reached the end of its life expectancy, then the replacement would be considered a Reserve expense. The GREY area of “maintenance” items that are often seen in a Reserve Study – One of the most popular questions revolves around major “maintenance” items, such as painting the buildings or seal coating the asphalt. You may hear from your accountant that since painting or seal coating is not replacing a “capital” item, then it cannot be considered a Reserve issue. However, it is the opinion of several major Reserve Study providers that these items are considered to be major expenses that occur on a cyclical basis. Therefore, it makes it very difficult to ignore a major expense that meets the criteria to be considered a Reserve component. Once explained in this context, many accountants tend to agree and will include any expenses, such as these examples, as a Reserve component. The Property Observation – The Property Observation was conducted following a review of the documents that were established by the developer identifying all common area assets. In some cases, the Board of Directors at some point may have revised the documents. In either case, the most current set of documents was reviewed prior to inspecting the property. In addition, common area assets may have been reported to Aspen Reserve Specialties by the client, or by other parties. Estimated life expectancies and life cycles are based upon conditions that were readily accessible and visible at the time of the observation. We did not destroy any landscape work, building walls, or perform any methods of intrusive investigation during the observation. In these cases, information may have been obtained by contacting the contractor or vendor that has worked on the property. The Reserve Fund Analysis – We projected the starting balance from taking the most recent balance statement, adding expected Reserve contributions for the rest of the year, and subtracting any pending projects for the rest of the year. We compared this number to the ideal Reserve Balance and arrived at the Percent funded level. Measures of strength are as follows: 0% - 30% Funded – Is considered to be a “weak” financial position. Associations that fall into this category are subject to Special Assessments and deferred maintenance, which could lead to lower property values. If the association is in this position, actions should be taken to improve the financial strength of the Reserve Fund. 31% - 69% Funded – The majority of associations are considered to be in this “fair” financial position. While this doesn’t represent financial strength and stability, the likelihood of Special Assessments and deferred maintenance is diminished. Effort should be taken to continue strengthening the financial position of the Reserve fund. 70% - 99% Funded – This indicates financial strength of a Reserve fund and every attempt to maintain this level should be a goal of the association. 100% Funded – This is the ideal amount of Reserve funding. This means that the association has the exact amount of funds in the Reserve account that should be at any given time.
4
Summary of Treehouse Condominiums- Association ID # - 08508 Reported Starting Balance as of March 1, 2013 - $1,041,157 Ideal Reserve Balance as of January 1, 2013 - $1,947,613 Percent Funded as of January 1, 2013 - 53% Recommended Reserve Allocation (per month) - $17,575 (for rest of 2013) Recommended Reserve Allocation (per month) - $28,800 (starting 2014) Minimum Reserve Allocation (per month) - $24,500 (starting 2014) Recommended Special Assessment - $0 Information to complete this Reserve Analysis was gathered during several property observations of the common area elements in November and December 2012, as well as a follow up site visit in January 2013. In addition, we obtained information by contacting local vendors and contractors, as well as communicating with the property representatives (Community Manager). To the best of our knowledge, the conclusions and suggestions of this report are considered reliable and accurate insofar as the information obtained from these sources. This property contains 249 condominium style units among 9 similar buildings that were originally constructed approximately 40 years ago in the mid 1970's. Two additional townhome styled buildings were constructed about 5 years ago in 2008. Common area amenities the association is responsible to maintain include building exterior surfaces, the interior surfaces and mechanical systems associated with the condominium buildings, two separate clubhouses with pools and spas, private driveways and parking lots, a tennis court, and a playground area. The on-site maintenance staff performs various tasks around the community that extends or eliminates the need for Reserve funding of various components. Please refer to the Projected Reserve Expenditure section of the Financial Analysis for a list of when components are scheduled to be addressed. In comparing the projected balance of $1,041,157 versus the ideal Reserve Balance of $1,947,613, we find the association Reserve fund to be in an average financial position at this point in time (approximately 53% funded of ideal). Based on the information contained in this report, we suggest keeping the Reserve contribution at the budgeted amount of $17,575 for the rest of 2013. However, in order to strengthen the Reserve account for future project consideration, a substantial increase will be necessary starting in 2014. If you refer to page 1 of the Financial Analysis section, you will see we are recommending an increase of the Reserve contribution to $28,800 (representing an increase of $45.08 per unit) per month starting January 2014. This should be followed by nominal annual increases of 4.50% thereafter to help offset the effects of inflation. By following the recommendation, the plan will increase the Reserve account to a fully funded position within the thirty-year period. In the percent Funded graph, you will see we have also provided a “minimum Reserve contribution” of $24,500 per month. If the Reserve contribution falls below this rate, then the Reserve fund will fall into a situation where additional Special Assessments, deferred maintenance, and lower property values are possible at some point in the future. The minimum Reserve allocation follows the “threshold” theory of Reserve funding where the ”percent funded” status is not allowed to dip below 30% funded at any point during the thirty-year period. This was provided for one purpose only, to show the association how small the difference is between the two scenarios and how it would not make financial sense to contribute less money (approximately $17.30 on average per unit per month in this case) to the Reserve fund to only stay above a certain threshold. As you can see, the difference between the two scenarios is considered to be minimal, and based on the risk involved, we strongly suggest the recommended Reserve Allocation is followed.
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 401
Source of Information: Cost Database
Best Cost: $138,100$138,100$138,100$138,100
Worst Cost: $159,000$159,000$159,000$159,000
Location: Communit drives/parkingCommunit drives/parkingCommunit drives/parkingCommunit drives/parking
Quantity: 50% of 167,380 GSF50% of 167,380 GSF50% of 167,380 GSF50% of 167,380 GSF
Observations:
Majority of parking lots exhibit some moderate to substantial cracking. These cracks have been sealed, but continue to require maintenance on an annual basis to prevent them from worsening. In our observation, we determined about half of the parking lots to be in fair condition, and the other half to be in fair to poor condition. As a result, we split all asphalt surfaces into two different line items to resurface in two separate phases. This line item is for the first phase that should be done within the next 5 years.
Life Expectancy: 24242424 Remaining Life: 5555
$1.65/GSF; Est. to rotomill and 2" overlay
$1.90/GSF; Higher estimate for more repairs
Asphalt - Overlay (A)
General Notes:
Sunday, April 28, 2013Page 1 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 401
Source of Information: Cost Database
Best Cost: $138,100$138,100$138,100$138,100
Worst Cost: $159,000$159,000$159,000$159,000
Location: Communit drives/parkingCommunit drives/parkingCommunit drives/parkingCommunit drives/parking
Quantity: 50% of 167,380 GSF50% of 167,380 GSF50% of 167,380 GSF50% of 167,380 GSF
Observations:
Majority of parking lots exhibit some moderate to substantial cracking. These cracks have been sealed, but continue to require maintenance on an annual basis to prevent them from worsening. In our observation, we determined about half of the parking lots to be in fair condition, and the other half to be in fair to poor condition. As a result, we split all asphalt surfaces into two different line items to resurface in two separate phases. This line item is for the first phase that should be done within the next 5 - 10 years.
Life Expectancy: 24242424 Remaining Life: 9999
$1.65/GSF; Est. to rotomill and 2" overlay
$1.90/GSF; Higher estimate for more repairs
Asphalt - Overlay (B)
General Notes:
Sunday, April 28, 2013Page 2 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 402
Source of Information: Cost Database
Best Cost: $26,800$26,800$26,800$26,800
Worst Cost: $33,500$33,500$33,500$33,500
Location: Communit drives/parkingCommunit drives/parkingCommunit drives/parkingCommunit drives/parking
Quantity: Approx. 167,380 GSFApprox. 167,380 GSFApprox. 167,380 GSFApprox. 167,380 GSF
Observations:
Asphalt seal coat is generally in fair to poor condition and should be sealed this fiscal year. Noted significant cracking throughout asphalt surface. No pot holes or structural problems noted. Typically asphalt surfaces should be sealed every 3 to 4 years depending on traffic to protect asphalt surface.
Life Expectancy: 4444 Remaining Life: 0000
$.16/GSF; Estimate for seal coat only
$.20/GSF; Higher est. includes repairs/crack fill
Asphalt - Seal Coat/crack fill
General Notes:
Sunday, April 28, 2013Page 3 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 607
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Throughout communityThroughout communityThroughout communityThroughout community
Quantity: See General NotesSee General NotesSee General NotesSee General Notes
Observations:
It was reported these are repaired on an as needed basis by the on site maintenance staff with general operating funds. Therefore, separate Reserve funding is not required for this component at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Wood Paths - Replace
General Notes:
wood paths - 19,855 GSFwood paths - 19,855 GSFwood paths - 19,855 GSFwood paths - 19,855 GSFrailing - 3,885 GSFrailing - 3,885 GSFrailing - 3,885 GSFrailing - 3,885 GSF
tie steps - 96tie steps - 96tie steps - 96tie steps - 96
Sunday, April 28, 2013Page 4 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 610
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Throughout communityThroughout communityThroughout communityThroughout community
Quantity: Approx. 328 GSFApprox. 328 GSFApprox. 328 GSFApprox. 328 GSF
Observations:
These stair treads have an indefinite life expectancy under normal conditions. As a result, there is no expectancy to replace all of these at the same time. Therefore, we suggest replacing on an as needed basis with general operating funds and repairing the handrails by on-site maintenance staff.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Steel Stairs/Landings - Replace
General Notes:
Bldg. I - Bldg. I - Bldg. I - Bldg. I - treads - (10) 8' wide, landing - 65 GSF, rail - 46 LF treads - (10) 8' wide, landing - 65 GSF, rail - 46 LF treads - (10) 8' wide, landing - 65 GSF, rail - 46 LF treads - (10) 8' wide, landing - 65 GSF, rail - 46 LFBldg. H - Bldg. H - Bldg. H - Bldg. H - treads - (8) 8' wide, rail - 20 LF treads - (8) 8' wide, rail - 20 LF treads - (8) 8' wide, rail - 20 LF treads - (8) 8' wide, rail - 20 LFBldg. G - Bldg. G - Bldg. G - Bldg. G - treads - (6) 8' wide, rail - 20 LF treads - (6) 8' wide, rail - 20 LF treads - (6) 8' wide, rail - 20 LF treads - (6) 8' wide, rail - 20 LFBldg. F - Bldg. F - Bldg. F - Bldg. F - treads - (11) 8' wide (stringers rotting) treads - (11) 8' wide (stringers rotting) treads - (11) 8' wide (stringers rotting) treads - (11) 8' wide (stringers rotting)Bldg. E - Bldg. E - Bldg. E - Bldg. E - treads - (7) 8' wide treads - (7) 8' wide treads - (7) 8' wide treads - (7) 8' wide
Sunday, April 28, 2013Page 5 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 611
Source of Information: Research on website
Best Cost: $4,250$4,250$4,250$4,250
Worst Cost: $5,000$5,000$5,000$5,000
Location: Throughout communityThroughout communityThroughout communityThroughout community
Quantity: Approx. (194) matsApprox. (194) matsApprox. (194) matsApprox. (194) mats
Observations:
The cost of these mats (about $70 each + tax and delivery) is too small if replacement occurred on an individual basis. Due to the overall quantity of the mats, we recommend establishing a Reserve allowance to replace 25% of the mats (about 50) every 4 years. By replacing multiple mats at the same time, the association will save money by purchasing bulk amounts of mats. The conditions vary throughout the community and as a result, it is unlikely every mat would be replaced at the same time.
Life Expectancy: 4444 Remaining Life: 1111
Estimate to replace 50 mats every 4 years
Higher estimate for better quality mat
Slip Resistant Mats - Replace
General Notes:
Common areas - (74) 5x3 matsCommon areas - (74) 5x3 matsCommon areas - (74) 5x3 matsCommon areas - (74) 5x3 matsaround clubhouse - (18) 5x3 matsaround clubhouse - (18) 5x3 matsaround clubhouse - (18) 5x3 matsaround clubhouse - (18) 5x3 mats
bldg. A - (24) 5x3 matsbldg. A - (24) 5x3 matsbldg. A - (24) 5x3 matsbldg. A - (24) 5x3 matsbldg. B - (23) 5x3 matsbldg. B - (23) 5x3 matsbldg. B - (23) 5x3 matsbldg. B - (23) 5x3 matsbldg. C - (29) 5x3 matsbldg. C - (29) 5x3 matsbldg. C - (29) 5x3 matsbldg. C - (29) 5x3 matsbldg. D - (10) 5x3 matsbldg. D - (10) 5x3 matsbldg. D - (10) 5x3 matsbldg. D - (10) 5x3 matsbldg. H - (11) 5x3 matsbldg. H - (11) 5x3 matsbldg. H - (11) 5x3 matsbldg. H - (11) 5x3 matsbldg. E - (5) 5x3 matsbldg. E - (5) 5x3 matsbldg. E - (5) 5x3 matsbldg. E - (5) 5x3 mats
Sunday, April 28, 2013Page 6 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 622
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Near bldg INear bldg INear bldg INear bldg I
Quantity: See general notesSee general notesSee general notesSee general notes
Observations:
No need for separate Reserve funding for this component. Replace and maintain at the same time as other building components.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Covered Stairway - Replace
General Notes:
roof - approx. 125 GSFroof - approx. 125 GSFroof - approx. 125 GSFroof - approx. 125 GSFsiding - approx. 440 GSFsiding - approx. 440 GSFsiding - approx. 440 GSFsiding - approx. 440 GSFmetal stairs - (8) treads (4' wide)metal stairs - (8) treads (4' wide)metal stairs - (8) treads (4' wide)metal stairs - (8) treads (4' wide)
Sunday, April 28, 2013Page 7 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 801
Source of Information: Cost Database
Best Cost: $4,500$4,500$4,500$4,500
Worst Cost: $5,750$5,750$5,750$5,750
Location: Adjacent to main clubhouseAdjacent to main clubhouseAdjacent to main clubhouseAdjacent to main clubhouse
Quantity: See General NotesSee General NotesSee General NotesSee General Notes
Observations:
Wood is starting to show signs of age and minor deterioration. Some minor prep work and a new coat of paint will extend the life of the sign. Therefore, we are recommending the on site maintenance staff repaints the sign to protect the wood against any deterioration to the materials. In order to maintain an appropriate appearance for the community, most associations are upgrading monuments to establish a modern appearance. We realize this may be a discretionary expense decided by the Board, but we strongly recommend some funds are set aside for eventual upgrades to the signage.
Life Expectancy: 20202020 Remaining Life: 8888
Estimate to replace sign
Higher estimate for major repairs to stone work
Identification Sign - Replace
General Notes:
wood sign - 9x3, 2 sided (peeling paint)wood sign - 9x3, 2 sided (peeling paint)wood sign - 9x3, 2 sided (peeling paint)wood sign - 9x3, 2 sided (peeling paint)stone wall - approx. 75 GSFstone wall - approx. 75 GSFstone wall - approx. 75 GSFstone wall - approx. 75 GSF(2) kim lights(2) kim lights(2) kim lights(2) kim lights
Sunday, April 28, 2013Page 8 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 1003
Source of Information: Cost Database
Best Cost: $12,600$12,600$12,600$12,600
Worst Cost: $14,400$14,400$14,400$14,400
Location: Tennis CourtsTennis CourtsTennis CourtsTennis Courts
Quantity: Approx. 360 LFApprox. 360 LFApprox. 360 LFApprox. 360 LF
Observations:
The tennis court fence is generally in fair to poor condition with bent and leaning sections observed. Local repairs should be completed as part of the tennis court refurbishment project. Reserve funding has been established to replace the chain link only every 30 years. If the need exists to include post repairs/replacement, the total fence replacement would cost about $60 - $75 per post.
Life Expectancy: 35353535 Remaining Life: 5555
$35/LF; Estimate to replace
$40/LF: Higher estimate
Chain Link Fencing - Replace
General Notes:
Fence is 10' tall chain link, no windscreen at time of Fence is 10' tall chain link, no windscreen at time of Fence is 10' tall chain link, no windscreen at time of Fence is 10' tall chain link, no windscreen at time of observation.observation.observation.observation.
Sunday, April 28, 2013Page 9 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 1201
Source of Information: Cost Database
Best Cost: $57,500$57,500$57,500$57,500
Worst Cost: $65,000$65,000$65,000$65,000
Location: Tennis courtTennis courtTennis courtTennis court
Quantity: (1) court(1) court(1) court(1) court
Observations:
The court is considered to be unplayable at this time with severe cracking and loss of surface noted. Most tennis courts are being replaced with a post tension court that are expected to last 40+ years, even in this climate. As long as this asset remains in the community, we are obligated to Reserve for general maintenance and renovation of this component. Based on observed conditions, we recommend the association address this component in the near future to restore the court back to functional conditions.
Life Expectancy: 35353535 Remaining Life: 0000
Estimate to replace with post tension
Higher estimate for more labor
Tennis Court Asphalt - Replace
General Notes:
Sunday, April 28, 2013Page 10 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 1202
Source of Information: Cost Database
Best Cost: $6,000$6,000$6,000$6,000
Worst Cost: $6,750$6,750$6,750$6,750
Location: Tennis courtTennis courtTennis courtTennis court
Quantity: (1) court(1) court(1) court(1) court
Observations:
Tennis court is generally in poor condition with significant cracking and loss of coating noted throughout. Based on observed condition, we recommend resurfacing or replacing the court this year to restore court back to functional conditions. Depending on the level of use, expect to recoat every 6 - 8 years assuming normal use and wear.
Life Expectancy: 7777 Remaining Life: 0000
Estimate to crack fill, repaint/coat
Higher estimate for some minor repairs
Tennis Court - Recoat/Paint
General Notes:
Sunday, April 28, 2013Page 11 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 1301
Source of Information: Research on website
Best Cost: $39,000$39,000$39,000$39,000
Worst Cost: $46,000$46,000$46,000$46,000
Location: Common areasCommon areasCommon areasCommon areas
Quantity: (1) play structure(1) play structure(1) play structure(1) play structure
Observations:
Structures were new and stable and in good condition at time of site observation with no major signs of abuse, mistreatment, or vandalism at time of field work. Depending on overall level of use, quality, and care, the average life expectancy for play equipment ranges from 12 - 18 years. The remaining life is based on the age of the system and the observed conditions.
Life Expectancy: 17171717 Remaining Life: 15151515
Estimate to replace and install with similar type
Higher estimate for larger structure
Play Equipment - Replace
General Notes:
NOTE: playground installed in 2011NOTE: playground installed in 2011NOTE: playground installed in 2011NOTE: playground installed in 2011
Play structure components - Play structure components - Play structure components - Play structure components - monkey bars, side-by-side slide, 10' wavy slide, monkey bars, side-by-side slide, 10' wavy slide, monkey bars, side-by-side slide, 10' wavy slide, monkey bars, side-by-side slide, 10' wavy slide, geodesic climber, 2 sets of stairs, 2 platforms, geodesic climber, 2 sets of stairs, 2 platforms, geodesic climber, 2 sets of stairs, 2 platforms, geodesic climber, 2 sets of stairs, 2 platforms, fire pole, shade canopy fire pole, shade canopy fire pole, shade canopy fire pole, shade canopySwingset - Swingset - Swingset - Swingset - trees used for posts, wood cross-beam. trees used for posts, wood cross-beam. trees used for posts, wood cross-beam. trees used for posts, wood cross-beam. (2) saddle swings (2) saddle swings (2) saddle swings (2) saddle swings
Sunday, April 28, 2013Page 12 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 1306
Source of Information: Cost Database
Best Cost: $2,500$2,500$2,500$2,500
Worst Cost: $3,000$3,000$3,000$3,000
Location: Common areasCommon areasCommon areasCommon areas
Quantity: (14) Assorted pieces(14) Assorted pieces(14) Assorted pieces(14) Assorted pieces
Observations:
Conditions and ages range throughout the community. The benches at the park area are new, while there are older picnic tables where the wood is beginning to splinter. This line item is set up to establish an allowance to periodically replace the needed furnishings every 5 years. The remaining life is based on the new equipment and the fact there is no need for immediate replacement at this time.
Life Expectancy: 5555 Remaining Life: 2222
Allowance to replace the needed furnishings
Higher estimate for more pieces
Park Furnishings - Replace
General Notes:
Tables:Tables:Tables:Tables:playground area - (1) picnic tableplayground area - (1) picnic tableplayground area - (1) picnic tableplayground area - (1) picnic tablepicnic area btwn G & H - (2) picnic tablespicnic area btwn G & H - (2) picnic tablespicnic area btwn G & H - (2) picnic tablespicnic area btwn G & H - (2) picnic tables
Benches:Benches:Benches:Benches:playground area - (2) 8' benches (2012)playground area - (2) 8' benches (2012)playground area - (2) 8' benches (2012)playground area - (2) 8' benches (2012)picnic area btwn G & H - (1) bench (log)picnic area btwn G & H - (1) bench (log)picnic area btwn G & H - (1) bench (log)picnic area btwn G & H - (1) bench (log)
Trash:Trash:Trash:Trash:common area - (2) receptacles (pebbled)common area - (2) receptacles (pebbled)common area - (2) receptacles (pebbled)common area - (2) receptacles (pebbled)playground area - (3) receptacles (1 new)playground area - (3) receptacles (1 new)playground area - (3) receptacles (1 new)playground area - (3) receptacles (1 new)picnic are btwn G & H - (3) receptaclespicnic are btwn G & H - (3) receptaclespicnic are btwn G & H - (3) receptaclespicnic are btwn G & H - (3) receptacles
Sunday, April 28, 2013Page 13 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 1311
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Throughout common areasThroughout common areasThroughout common areasThroughout common areas
Quantity: Approx. (12) stationsApprox. (12) stationsApprox. (12) stationsApprox. (12) stations
Observations:
No unusual conditions observed during field observation. The individual replacement cost of these stations (less than $550 each) is too small for Reserve consideration. Therefore, we recommend replacing these on an as needed basis with general operating funds.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Pet Waste Stations - Replace
General Notes:
near bldg A - (1) stationnear bldg A - (1) stationnear bldg A - (1) stationnear bldg A - (1) stationnear bldg C - (1) stationnear bldg C - (1) stationnear bldg C - (1) stationnear bldg C - (1) stationnear bldg H - (1) stationnear bldg H - (1) stationnear bldg H - (1) stationnear bldg H - (1) stationnear bldg G - (1) stationnear bldg G - (1) stationnear bldg G - (1) stationnear bldg G - (1) stationnear bldg F - (1) stationnear bldg F - (1) stationnear bldg F - (1) stationnear bldg F - (1) stationcommon areas - (7) stationscommon areas - (7) stationscommon areas - (7) stationscommon areas - (7) stations
Sunday, April 28, 2013Page 14 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 1423
Source of Information: Cost Database
Best Cost: $5,500$5,500$5,500$5,500
Worst Cost: $6,250$6,250$6,250$6,250
Location: ClubhousesClubhousesClubhousesClubhouses
Quantity: (2) units(2) units(2) units(2) units
Observations:
Direct access to the managers unit was not available at time of our field work. We have established this line item for periodic upgrades and replacement to the necessary items in the managers unit every 4 years. The cycle and amount were determined by the on-site manager and ourselves at the time of our initial meeting.
Life Expectancy: 4444 Remaining Life: 0000
Allowance to replace needed components
Higher allowance for more repalcement
Manager's Units - Remodel
General Notes:
Sunday, April 28, 2013Page 15 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area GroundsComponent Inventory for Common Area Grounds
Comp #: 1604
Source of Information: Research on website
Best Cost: $5,950$5,950$5,950$5,950
Worst Cost: $7,000$7,000$7,000$7,000
Location: Throughout common areasThroughout common areasThroughout common areasThroughout common areas
Quantity: Approx. (14) fixturesApprox. (14) fixturesApprox. (14) fixturesApprox. (14) fixtures
Observations:
No structural problems noted with lights at the time of inspection. One of the fixtures was still on during daylight hours. We recommend painting the poles regularly to protect the wood materials from deterioration (this should be done at the same time as the building exteriors for best cost estimate and to match the same color as the buildings). Expect to replace the fixtures (not posts) every 25 - 30 years to maintain appearance and function.
Life Expectancy: 28282828 Remaining Life: 5555
$425/fixture; Estimate to replace
Higher estimate for better quality fixture
Pole Lights - Replace
General Notes:
near bldg A - (1) fixturenear bldg A - (1) fixturenear bldg A - (1) fixturenear bldg A - (1) fixturenear bldg C - (2) fixturesnear bldg C - (2) fixturesnear bldg C - (2) fixturesnear bldg C - (2) fixturescommon areas - (11) fixturescommon areas - (11) fixturescommon areas - (11) fixturescommon areas - (11) fixtures
Sunday, April 28, 2013Page 16 of 16
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 105
Source of Information: Research with contractor
Best Cost: $220,500$220,500$220,500$220,500
Worst Cost: $249,900$249,900$249,900$249,900
Location: Three of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofs
Quantity: Approx. 294 squaresApprox. 294 squaresApprox. 294 squaresApprox. 294 squares
Observations:
Direct access to the roofs were not available at time of field work due to time constraints and follow up observations took place during winter months. It was reported the roofs vary in age from 7 - 14 years old. The average life expectancy for these types of roofs range between 17 - 20 years, depending on the level of maintenance and the quality of the roof. We have phased out the replacement based on average age of the roofs, replacing 3 building roofs in each phase. This line item is for the first phase of 3 buildings to be replaced.
Life Expectancy: 20202020 Remaining Life: 6666
$750/square; Estimate to remove and replace
$850/square; Higher estimate for more labor costs
Modified Bitumen - Replace (1)
General Notes:
Approx. 98 sqs per building x 3 bldgs = 294 sqsApprox. 98 sqs per building x 3 bldgs = 294 sqsApprox. 98 sqs per building x 3 bldgs = 294 sqsApprox. 98 sqs per building x 3 bldgs = 294 sqs
Sunday, August 11, 2013Page 1 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 105
Source of Information: Cost Database
Best Cost: $220,500$220,500$220,500$220,500
Worst Cost: $249,900$249,900$249,900$249,900
Location: Three of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofs
Quantity: Approx. 294 squaresApprox. 294 squaresApprox. 294 squaresApprox. 294 squares
Observations:
Direct access to the roofs were not available at time of field work due to time constraints and follow up observations took place during winter months. It was reported the roofs vary in age from 7 - 14 years old. The average life expectancy for these types of roofs range between 17 - 20 years, depending on the level of maintenance and the quality of the roof. We have phased out the replacement based on average age of the roofs, replacing 3 building roofs in each phase. This line item is for the final phase of 3 buildings to be replaced.
Life Expectancy: 20202020 Remaining Life: 13131313
$750/square; Estimate to remove and replace
$850/square; Higher estimate for more labor costs
Modified Bitumen - Replace (3)
General Notes:
Approx. 98 sqs per buildings x 3 bldgs = 294 sqsApprox. 98 sqs per buildings x 3 bldgs = 294 sqsApprox. 98 sqs per buildings x 3 bldgs = 294 sqsApprox. 98 sqs per buildings x 3 bldgs = 294 sqs
Sunday, August 11, 2013Page 2 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 105
Source of Information: Cost Database
Best Cost: $220,500$220,500$220,500$220,500
Worst Cost: $249,900$249,900$249,900$249,900
Location: Three of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofs
Quantity: Approx. 294 squaresApprox. 294 squaresApprox. 294 squaresApprox. 294 squares
Observations:
Direct access to the roofs were not available at time of field work due to time constraints and follow up observations took place during winter months. It was reported the roofs vary in age from 7 - 14 years old. The average life expectancy for these types of roofs range between 17 - 20 years, depending on the level of maintenance and the quality of the roof. We have phased out the replacement based on average age of the roofs, replacing 3 building roofs in each phase. This line item is for the second phase of 3 buildings to be replaced.
Life Expectancy: 20202020 Remaining Life: 10101010
$750/square; Estimate to remove and replace
$850/square; Higher estimate for more labor costs
Modified Bitumen - Replace (2)
General Notes:
Approx. 98 sqs per buildings x 3 bldgs = 294 sqsApprox. 98 sqs per buildings x 3 bldgs = 294 sqsApprox. 98 sqs per buildings x 3 bldgs = 294 sqsApprox. 98 sqs per buildings x 3 bldgs = 294 sqs
Sunday, August 11, 2013Page 3 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 123
Source of Information: Cost Database
Best Cost: $12,000$12,000$12,000$12,000
Worst Cost: $15,000$15,000$15,000$15,000
Location: Three of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofs
Quantity: (12) 6x6 lights(12) 6x6 lights(12) 6x6 lights(12) 6x6 lights
Observations:
No unusual conditions reported with the skylights at the time of preparing this report. Typically, skylights are replaced or major repairs are performed at the same time as roof replacement. It has been advised by industry professionals that we include funding to address skylights at this time.
Life Expectancy: 20202020 Remaining Life: 6666
$1000/skylight; Estimate to replace
$1250/skylight; Higher estimate for more labor
Skylights - Replace (1)
General Notes:
Sunday, August 11, 2013Page 4 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 123
Source of Information: Cost Database
Best Cost: $12,000$12,000$12,000$12,000
Worst Cost: $15,000$15,000$15,000$15,000
Location: Three of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofs
Quantity: (12) 6x6 lights(12) 6x6 lights(12) 6x6 lights(12) 6x6 lights
Observations:
No unusual conditions reported with the skylights at the time of preparing this report. Typically, skylights are replaced or major repairs are performed at the same time as roof replacement. It has been advised by industry professionals that we include funding to address skylights at this time.
Life Expectancy: 20202020 Remaining Life: 13131313
$1000/skylight; Estimate to replace
$1250/skylight; Higher estimate for more labor
Skylights - Replace (3)
General Notes:
Sunday, August 11, 2013Page 5 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 123
Source of Information: Cost Database
Best Cost: $12,000$12,000$12,000$12,000
Worst Cost: $15,000$15,000$15,000$15,000
Location: Three of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofsThree of the 9-unit building roofs
Quantity: (12) 6x6 lights(12) 6x6 lights(12) 6x6 lights(12) 6x6 lights
Observations:
No unusual conditions reported with the skylights at the time of preparing this report. Typically, skylights are replaced or major repairs are performed at the same time as roof replacement. It has been advised by industry professionals that we include funding to address skylights at this time.
Life Expectancy: 20202020 Remaining Life: 10101010
$1000/skylight; Estimate to replace
$1250/skylight; Higher estimate for more labor
Skylights - Replace (2)
General Notes:
Sunday, August 11, 2013Page 6 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 204
Source of Information: Research with contractors
Best Cost: $130,500$130,500$130,500$130,500
Worst Cost: $153,000$153,000$153,000$153,000
Location: Siding, trim, railings, etc.Siding, trim, railings, etc.Siding, trim, railings, etc.Siding, trim, railings, etc.
Quantity: (9) Condo Buildings(9) Condo Buildings(9) Condo Buildings(9) Condo Buildings
Observations:
Paint exhibited some signs of fading and minor peeling in various locations at the time of our field observations. It was reported these were last painted in 2011. In this climate, we recommend painting every 4 - 5 years to protect the wood from premature deterioration and damage. The remaining life is based on the age of the painted surfaces and the overall conditions.
Life Expectancy: 5555 Remaining Life: 3333
$14500/building; Estimate to repaint
$17000/building; Higher estimate for more prep work
Building Ext Surfaces - Repaint
General Notes:
Sunday, August 11, 2013Page 7 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 301
Source of Information: Cost Database
Best Cost: $45,000$45,000$45,000$45,000
Worst Cost: $54,000$54,000$54,000$54,000
Location: Unit building exterior claddingUnit building exterior claddingUnit building exterior claddingUnit building exterior cladding
Quantity: Approx. 200,340 GSFApprox. 200,340 GSFApprox. 200,340 GSFApprox. 200,340 GSF
Observations:
At time of field work, we observed some loose and warped boards that will need to be repaired prior to painting. There were also some split boards and loose railing pickets noted as well. Based on observed conditions and the age of the buildings, we recommend including an allowance for periodic repairs prior to each painting cycle.
Life Expectancy: 5555 Remaining Life: 3333
$5000/bldg; Allowance for major repairs
Higher allowance for more repairs
Wood Siding - Major Repairs
General Notes:
Approx. 22,260 GSF per buildingApprox. 22,260 GSF per buildingApprox. 22,260 GSF per buildingApprox. 22,260 GSF per building
Sunday, August 11, 2013Page 8 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 501
Source of Information: Cost Database
Best Cost: $20,250$20,250$20,250$20,250
Worst Cost: $22,300$22,300$22,300$22,300
Location: Unit buildings A - IUnit buildings A - IUnit buildings A - IUnit buildings A - I
Quantity: (81) Common doors(81) Common doors(81) Common doors(81) Common doors
Observations:
Conditions of doors varied from building to building. Most are functional, but have a poor appearance with dings and dents noted throughout. The declarations do not clearly state who is responsible for the unit doors, but in most associations, the windows and doors are owner responsibility. So, funding for unit doors is not included as part of this Reserve plan. Due to varying conditions and levels of use, Reserve to replace 1/3rd of the doors every 8 years.
Life Expectancy: 8888 Remaining Life: 2222
Allowance to replace 27 doors every 8 years
Higher estimate for more
Doors - Partial Replacement
General Notes:
Unit buildings A - I common area doors - Unit buildings A - I common area doors - Unit buildings A - I common area doors - Unit buildings A - I common area doors - (9) 3x7 per building x 9 buildings = (81) doors (9) 3x7 per building x 9 buildings = (81) doors (9) 3x7 per building x 9 buildings = (81) doors (9) 3x7 per building x 9 buildings = (81) doors
(245) unit doors(245) unit doors(245) unit doors(245) unit doors
Sunday, August 11, 2013Page 9 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 506
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Unit buildings A - IUnit buildings A - IUnit buildings A - IUnit buildings A - I
Quantity: Approx. (490) openingsApprox. (490) openingsApprox. (490) openingsApprox. (490) openings
Observations:
Declarations are not clear as to who is responsible for the unit windows. Typically, windows are the responsibility of each individual owner. Therefore, separate Reserve funding is not required for this component at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Unit Windows - Replace
General Notes:
(245) - windows (245) - windows (245) - windows (245) - windows (245) - 6x7 sliders(245) - 6x7 sliders(245) - 6x7 sliders(245) - 6x7 sliders
Sunday, August 11, 2013Page 10 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 606
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Unit buildings A - IUnit buildings A - IUnit buildings A - IUnit buildings A - I
Quantity: Approx. 8,775 LFApprox. 8,775 LFApprox. 8,775 LFApprox. 8,775 LF
Observations:
Funding for repairs is included with building siding repairs. Therefore, separate funding requirements are not needed for this component.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Deck Railings - Replace
General Notes:
Approx. 975 LF per building x 9 buildings = 8,775 LFApprox. 975 LF per building x 9 buildings = 8,775 LFApprox. 975 LF per building x 9 buildings = 8,775 LFApprox. 975 LF per building x 9 buildings = 8,775 LF
Sunday, August 11, 2013Page 11 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 607
Source of Information: Cost database
Best Cost: $12,000$12,000$12,000$12,000
Worst Cost: $15,000$15,000$15,000$15,000
Location: Unit deckingUnit deckingUnit deckingUnit decking
Quantity: Approx. 10,080 GSFApprox. 10,080 GSFApprox. 10,080 GSFApprox. 10,080 GSF
Observations:
Direct access to decks was not available due to privacy reasons. Overall life expectancy will depend on the level of use and care on each unit. We have established Reserve funding for periodic repairs every other painting and building repair cycle in order to maintain appropriate conditions and safety for all unit decks.
Life Expectancy: 10101010 Remaining Life: 3333
Allowance for general repairs every 10 years
Higher allowance for more repairs
Wood Deck - Major Repairs
General Notes:
Approx. 1,120 GSF per building x 9 buildings = Approx. 1,120 GSF per building x 9 buildings = Approx. 1,120 GSF per building x 9 buildings = Approx. 1,120 GSF per building x 9 buildings = 10,080 GSF 10,080 GSF 10,080 GSF 10,080 GSF
Sunday, August 11, 2013Page 12 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 701
Source of Information: Cost Database
Best Cost: $8,000$8,000$8,000$8,000
Worst Cost: $10,000$10,000$10,000$10,000
Location: Building CBuilding CBuilding CBuilding C
Quantity: (2) boilers(2) boilers(2) boilers(2) boilers
Observations:
Due to the expected level of use these systems will receive, major renovations will need to occur every 4 - 5 years. According to manufacturer, these units typically do not require complete replacement. However, it is possible that parts will eventually become obsolete and with advances in technology, replacement may become necessary at some point in the next 20+ years. Following a good preventative maintenance program will extend the life of the boilers another 10 - 15 years. This line item is for major rebuilding of boiler components every 5 years. See item #702 for replacement.
Life Expectancy: 5555 Remaining Life: 1111
Allowance for major repairs and some rebuilding
Higher allowance for more parts
Boilers - Major Repairs (Bldg C)
General Notes:
building C - (2) Multi-Temp Hydrotherm boilersbuilding C - (2) Multi-Temp Hydrotherm boilersbuilding C - (2) Multi-Temp Hydrotherm boilersbuilding C - (2) Multi-Temp Hydrotherm boilers (no visible labels) (no visible labels) (no visible labels) (no visible labels)
Sunday, August 11, 2013Page 13 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 701
Source of Information: Cost Database
Best Cost: $36,000$36,000$36,000$36,000
Worst Cost: $42,000$42,000$42,000$42,000
Location: Building HBuilding HBuilding HBuilding H
Quantity: (2) boilers(2) boilers(2) boilers(2) boilers
Observations:
Boilers were replaced about 5 years ago and still appear to be in good condition. According to current service contractor, they did not perform any major repairs on these boilers this past winter. Therefore, we assume there are no problems with these units. In our experience, we typically see these types of boilers last 17 - 20 years, depending on the level of maintenance and the quality of the water running through the system. Remaining life is based on age of units.
Life Expectancy: 20202020 Remaining Life: 15151515
$18000/boiler; Estimate to replace
$21000/boiler; Higher estimate for more labor
Boilers - Replace (Bldg H)
General Notes:
building H - (2) Raypak boilersbuilding H - (2) Raypak boilersbuilding H - (2) Raypak boilersbuilding H - (2) Raypak boilers m/n: H3-0824, m/n: H3-0824, m/n: H3-0824, m/n: H3-0824, s/n: (a) 0811289693 (b) 0808286814 s/n: (a) 0811289693 (b) 0808286814 s/n: (a) 0811289693 (b) 0808286814 s/n: (a) 0811289693 (b) 0808286814 825,000 BTU in 825,000 BTU in 825,000 BTU in 825,000 BTU in
Sunday, August 11, 2013Page 14 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 701
Source of Information: Research with contractor
Best Cost: $140,000$140,000$140,000$140,000
Worst Cost: $160,000$160,000$160,000$160,000
Location: Unit buildings A, B, D, E, F, G, IUnit buildings A, B, D, E, F, G, IUnit buildings A, B, D, E, F, G, IUnit buildings A, B, D, E, F, G, I
Quantity: (28) boilers(28) boilers(28) boilers(28) boilers
Observations:
Due to the expected level of use these systems will receive, major renovations will need to occur every 5 - 7 years. According to manufacturer, these units typically do not require complete replacement. However, it is possible that parts will eventually become obsolete (currently there are Burnham and generic parts available) and with advances in technology, replacement may become necessary at some point in the next 20+ years. Following a good preventative maintenance program will extend the life of the boilers another 10 - 15 years. This line item is for major rebuilding of boiler components every 7 years. See item #702 for replacement.
Life Expectancy: 7777 Remaining Life: 3333
Allowance for major rebuilding every 7 years
Higher allowance for more parts
Boilers - Major Repairs
General Notes:
Building A - (4) Burnham boilersBuilding A - (4) Burnham boilersBuilding A - (4) Burnham boilersBuilding A - (4) Burnham boilers m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU inBuilding B - (4) Burnham boilersBuilding B - (4) Burnham boilersBuilding B - (4) Burnham boilersBuilding B - (4) Burnham boilers m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU inBuilding D - (4) Burnham boilersBuilding D - (4) Burnham boilersBuilding D - (4) Burnham boilersBuilding D - (4) Burnham boilers m/n: #809, 528,000 BTU in m/n: #809, 528,000 BTU in m/n: #809, 528,000 BTU in m/n: #809, 528,000 BTU inBuilding E - (4) Burnham boilersBuilding E - (4) Burnham boilersBuilding E - (4) Burnham boilersBuilding E - (4) Burnham boilers m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU inBuilding F - (4) Burnham boilersBuilding F - (4) Burnham boilersBuilding F - (4) Burnham boilersBuilding F - (4) Burnham boilers m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU inBuilding G - (4) Burnham boilersBuilding G - (4) Burnham boilersBuilding G - (4) Burnham boilersBuilding G - (4) Burnham boilers m/n: 8096-WI, 528,000 BTU in m/n: 8096-WI, 528,000 BTU in m/n: 8096-WI, 528,000 BTU in m/n: 8096-WI, 528,000 BTU inBuilding I - (4) Burnham boilersBuilding I - (4) Burnham boilersBuilding I - (4) Burnham boilersBuilding I - (4) Burnham boilers m/n:809B-W, 528,000 BTU in m/n:809B-W, 528,000 BTU in m/n:809B-W, 528,000 BTU in m/n:809B-W, 528,000 BTU in
Sunday, August 11, 2013Page 15 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 701
Source of Information: Research with contractor
Best Cost: $164,400$164,400$164,400$164,400
Worst Cost: $178,800$178,800$178,800$178,800
Location: Unit buildings G, IUnit buildings G, IUnit buildings G, IUnit buildings G, I
Quantity: (8) boilers(8) boilers(8) boilers(8) boilers
Observations:
Due to the expected level of use these systems will receive, major renovations will need to occur every 4 - 5 years. According to manufacturer, these units typically do not require complete replacement. However, parts eventually become obsolete after numerous years and with advances in technology, replacement may become necessary at some point in the next 30+ years. This line item is for major complete replacement of boiler every 35 years. Cost of rebuilding should be added to this line item for complete replacement cost. Per the request of the client, we split the replacement to occur over a three year period to spread out the expense of this project.
Life Expectancy: 35353535 Remaining Life: 19191919
Estimate to replace boilers
Higher estimate for more labor
Boilers - Replace (G,I)
General Notes:
Building G - (4) Burnham boilersBuilding G - (4) Burnham boilersBuilding G - (4) Burnham boilersBuilding G - (4) Burnham boilers m/n: 8096-WI, 528,000 BTU in m/n: 8096-WI, 528,000 BTU in m/n: 8096-WI, 528,000 BTU in m/n: 8096-WI, 528,000 BTU inBuilding I - (4) Burnham boilersBuilding I - (4) Burnham boilersBuilding I - (4) Burnham boilersBuilding I - (4) Burnham boilers m/n:809B-W, 528,000 BTU in m/n:809B-W, 528,000 BTU in m/n:809B-W, 528,000 BTU in m/n:809B-W, 528,000 BTU in
Sunday, August 11, 2013Page 16 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 701
Source of Information: Research with contractor
Best Cost: $246,600$246,600$246,600$246,600
Worst Cost: $268,200$268,200$268,200$268,200
Location: Unit buildings A, B, DUnit buildings A, B, DUnit buildings A, B, DUnit buildings A, B, D
Quantity: (12) boilers(12) boilers(12) boilers(12) boilers
Observations:
Due to the expected level of use these systems will receive, major renovations will need to occur every 4 - 5 years. According to manufacturer, these units typically do not require complete replacement. However, parts eventually become obsolete after numerous years and with advances in technology, replacement may become necessary at some point in the next 30+ years. This line item is for major complete replacement of boiler every 35 years. Cost of rebuilding should be added to this line item for complete replacement cost. Per the request of the client, we split the replacement to occur over a three year period to spread out the expense of this project.
Life Expectancy: 35353535 Remaining Life: 17171717
Estimate to replace boilers
Higher estimate for more labor
Boilers - Replace (A,B,D)
General Notes:
Building A - (4) Burnham boilersBuilding A - (4) Burnham boilersBuilding A - (4) Burnham boilersBuilding A - (4) Burnham boilers m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU inBuilding B - (4) Burnham boilersBuilding B - (4) Burnham boilersBuilding B - (4) Burnham boilersBuilding B - (4) Burnham boilers m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU inBuilding D - (4) Burnham boilersBuilding D - (4) Burnham boilersBuilding D - (4) Burnham boilersBuilding D - (4) Burnham boilers m/n: #809, 528,000 BTU in m/n: #809, 528,000 BTU in m/n: #809, 528,000 BTU in m/n: #809, 528,000 BTU in
Sunday, August 11, 2013Page 17 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 701
Source of Information: Research with contractor
Best Cost: $164,400$164,400$164,400$164,400
Worst Cost: $178,800$178,800$178,800$178,800
Location: Unit buildings E, FUnit buildings E, FUnit buildings E, FUnit buildings E, F
Quantity: (8) boilers(8) boilers(8) boilers(8) boilers
Observations:
Due to the expected level of use these systems will receive, major renovations will need to occur every 4 - 5 years. According to manufacturer, these units typically do not require complete replacement. However, parts eventually become obsolete after numerous years and with advances in technology, replacement may become necessary at some point in the next 30+ years. This line item is for major complete replacement of boiler every 35 years. Cost of rebuilding should be added to this line item for complete replacement cost. Per the request of the client, we split the replacement to occur over a three year period to spread out the expense of this project.
Life Expectancy: 35353535 Remaining Life: 18181818
Estimate to replace boilers
Higher estimate for more labor
Boilers - Replace (E,F)
General Notes:
Building E - (4) Burnham boilersBuilding E - (4) Burnham boilersBuilding E - (4) Burnham boilersBuilding E - (4) Burnham boilers m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU inBuilding F - (4) Burnham boilersBuilding F - (4) Burnham boilersBuilding F - (4) Burnham boilersBuilding F - (4) Burnham boilers m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in m/n: 809B-WI, 528,000 BTU in
Sunday, August 11, 2013Page 18 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 702
Source of Information: Research with contractor
Best Cost: $85,000$85,000$85,000$85,000
Worst Cost: $100,000$100,000$100,000$100,000
Location: Building CBuilding CBuilding CBuilding C
Quantity: (2) boilers(2) boilers(2) boilers(2) boilers
Observations:
Due to the expected level of use these systems will receive, major renovations will need to occur every 4 - 5 years. According to manufacturer, these units typically do not require complete replacement. However, parts eventually become obsolete after numerous years and with advances in technology, replacement may become necessary at some point in the next 30+ years. This line item is for major complete replacement of boiler every 35 years. Cost of rebuilding should be added to this line item for complete replacement cost.
Life Expectancy: 35353535 Remaining Life: 16161616
Estimate to replace
Higher estimate for more labor
Boilers - Replace (Bldg C)
General Notes:
building C - (2) Multi-Temp Hydrotherm boilersbuilding C - (2) Multi-Temp Hydrotherm boilersbuilding C - (2) Multi-Temp Hydrotherm boilersbuilding C - (2) Multi-Temp Hydrotherm boilers (no visible labels) (no visible labels) (no visible labels) (no visible labels)
Sunday, August 11, 2013Page 19 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 703
Source of Information: Research with contractor
Best Cost: $32,000$32,000$32,000$32,000
Worst Cost: $36,000$36,000$36,000$36,000
Location: Buildings C & D mechanical roomsBuildings C & D mechanical roomsBuildings C & D mechanical roomsBuildings C & D mechanical rooms
Quantity: (4) Assorted tanks(4) Assorted tanks(4) Assorted tanks(4) Assorted tanks
Observations:
No unusual conditions noted on storage tanks at time of site visit. Dates vary from building to building. These tanks were purchased and installed in 2006. We have separated out the storage tanks based on the date they were installed. In our experience, we have seen the need to replace storage tanks on the average of 10 - 15 years, depending on the quality of the tank, the liner, and the quality of the water running through the system. It was reported the water in this area is "hard", which impacts the life expectancy of the tank. Also, these tanks need to be ASME approved, therefore, the reason for the higher cost. The remaining life is based on the age of the units.
Life Expectancy: 12121212 Remaining Life: 5555
$8000/tank; Estimate to replace
$9000/heater; Higher estimate for more labor
Hot Water Storage Tank - Replace (06)
General Notes:
building C - (2) Bradford Whitebuilding C - (2) Bradford Whitebuilding C - (2) Bradford Whitebuilding C - (2) Bradford White m/n: M38ST120R5, date: 2006 m/n: M38ST120R5, date: 2006 m/n: M38ST120R5, date: 2006 m/n: M38ST120R5, date: 2006
building D - (2) Bradford Whitebuilding D - (2) Bradford Whitebuilding D - (2) Bradford Whitebuilding D - (2) Bradford White m/n: M3ST120RS, date: 2006 m/n: M3ST120RS, date: 2006 m/n: M3ST120RS, date: 2006 m/n: M3ST120RS, date: 2006
Sunday, August 11, 2013Page 20 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 703
Source of Information: Research with contractor
Best Cost: $24,000$24,000$24,000$24,000
Worst Cost: $27,000$27,000$27,000$27,000
Location: Buildings B & I mechanical roomsBuildings B & I mechanical roomsBuildings B & I mechanical roomsBuildings B & I mechanical rooms
Quantity: (3) Assorted tanks(3) Assorted tanks(3) Assorted tanks(3) Assorted tanks
Observations:
No unusual conditions noted on storage tanks at time of site visit. Dates vary from building to building. We have separated out the storage tanks based on the date they were installed. These tanks were purchased and installed from 2009 through 2011. In our experience, we have seen the need to replace storage tanks on the average of 10 - 15 years, depending on the quality of the tank, the liner, and the quality of the water running through the system. It was reported the water in this area is "hard", which impacts the life expectancy of the tank. Also, these tanks need to be ASME approved, therefore, the reason for the higher cost. The remaining life is based on the average age of these units.
Life Expectancy: 12121212 Remaining Life: 9999
$8000/tank; Estimate to replace
$9000/heater; Higher estimate for more labor
Hot Water Storage Tank - Replace (09, 10, 11)
General Notes:
building B - (1) Statebuilding B - (1) Statebuilding B - (1) Statebuilding B - (1) State m/n: PVG01200OVT, date: 2009 m/n: PVG01200OVT, date: 2009 m/n: PVG01200OVT, date: 2009 m/n: PVG01200OVT, date: 2009 (1) Bradford White, m/n: M3ST120R5A (1) Bradford White, m/n: M3ST120R5A (1) Bradford White, m/n: M3ST120R5A (1) Bradford White, m/n: M3ST120R5A
building I - (2) State building I - (2) State building I - (2) State building I - (2) State m/n: PVG01200OVT, 2010 and 2011 m/n: PVG01200OVT, 2010 and 2011 m/n: PVG01200OVT, 2010 and 2011 m/n: PVG01200OVT, 2010 and 2011
Sunday, August 11, 2013Page 21 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 703
Source of Information: Research with contractor
Best Cost: $32,000$32,000$32,000$32,000
Worst Cost: $36,000$36,000$36,000$36,000
Location: Buildings G & H mechanical roomsBuildings G & H mechanical roomsBuildings G & H mechanical roomsBuildings G & H mechanical rooms
Quantity: (4) Assorted tanks(4) Assorted tanks(4) Assorted tanks(4) Assorted tanks
Observations:
No unusual conditions noted on storage tanks at time of site visit. Dates vary from building to building. We have separated out the storage tanks based on the date they were installed. These tanks were purchased and installed in 2005. In our experience, we have seen the need to replace storage tanks on the average of 10 - 15 years, depending on the quality of the tank, the liner, and the quality of the water running through the system. It was reported the water in this area is "hard", which impacts the life expectancy of the tank. Also, these tanks need to be ASME approved, therefore, the reason for the higher cost. The remaining life is based on the age of these units.
Life Expectancy: 12121212 Remaining Life: 4444
$8000/tank; Estimate to replace
$9000/heater; Higher estimate for more labor
Hot Water Storage Tank - Replace (05)
General Notes:
building G - (2) Bradford Whitebuilding G - (2) Bradford Whitebuilding G - (2) Bradford Whitebuilding G - (2) Bradford White m/n: M3ST120R5A, date: 2005 m/n: M3ST120R5A, date: 2005 m/n: M3ST120R5A, date: 2005 m/n: M3ST120R5A, date: 2005
building H - (2) Bradford Whitebuilding H - (2) Bradford Whitebuilding H - (2) Bradford Whitebuilding H - (2) Bradford White m/n: M3ST120R5A, date: 2005 m/n: M3ST120R5A, date: 2005 m/n: M3ST120R5A, date: 2005 m/n: M3ST120R5A, date: 2005
Sunday, August 11, 2013Page 22 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 703
Source of Information: Research with contractor
Best Cost: $48,000$48,000$48,000$48,000
Worst Cost: $54,000$54,000$54,000$54,000
Location: Buildings A, E, & F mechanical roomsBuildings A, E, & F mechanical roomsBuildings A, E, & F mechanical roomsBuildings A, E, & F mechanical rooms
Quantity: (6) Assorted tanks(6) Assorted tanks(6) Assorted tanks(6) Assorted tanks
Observations:
No unusual conditions noted on storage tanks at time of site visit. Dates vary from building to building. These tanks were purchased and installed in 2007. We have separated out the storage tanks based on the date they were installed. In our experience, we have seen the need to replace storage tanks on the average of 10 - 15 years, depending on the quality of the tank, the liner, and the quality of the water running through the system. It was reported the water in this area is "hard", which impacts the life expectancy of the tank. Also, these tanks need to be ASME approved, therefore, the reason for the higher cost. The remaining life is based on the age of the units.
Life Expectancy: 12121212 Remaining Life: 6666
$8000/tank; Estimate to replace
$9000/heater; Higher estimate for more labor
Hot Water Storage Tank - Replace (07)
General Notes:
building A - (2) Bradford Whitebuilding A - (2) Bradford Whitebuilding A - (2) Bradford Whitebuilding A - (2) Bradford White m/n: M38ST120R5, date: 2007 m/n: M38ST120R5, date: 2007 m/n: M38ST120R5, date: 2007 m/n: M38ST120R5, date: 2007
building E - (1) Statebuilding E - (1) Statebuilding E - (1) Statebuilding E - (1) State m/n: PVG012000VT, date: 2007 m/n: PVG012000VT, date: 2007 m/n: PVG012000VT, date: 2007 m/n: PVG012000VT, date: 2007 (1) Bradford White (1) Bradford White (1) Bradford White (1) Bradford White m/n: M3ST120R5, date: 2007 m/n: M3ST120R5, date: 2007 m/n: M3ST120R5, date: 2007 m/n: M3ST120R5, date: 2007
building F - (2) Bradford Whitebuilding F - (2) Bradford Whitebuilding F - (2) Bradford Whitebuilding F - (2) Bradford White m/n: M3ST120R5A, date: 2007 m/n: M3ST120R5A, date: 2007 m/n: M3ST120R5A, date: 2007 m/n: M3ST120R5A, date: 2007
Sunday, August 11, 2013Page 23 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 706
Source of Information: Cost Database
Best Cost: $49,500$49,500$49,500$49,500
Worst Cost: $56,250$56,250$56,250$56,250
Location: Buildings A - I mechanical roomsBuildings A - I mechanical roomsBuildings A - I mechanical roomsBuildings A - I mechanical rooms
Quantity: (9) heaters(9) heaters(9) heaters(9) heaters
Observations:
These sidearm heaters appear to be original and assumed to be functional and in working condition. There were no reports of problems from the current service contractor. In our experience, we have seen the average life expectancy of these units range between 22 - 28 years. Even those these have exceeded the typical life, we have extended the useful life, as well as the remaining life. Even though these are still functional, the association needs to prepare for eventual replacement.
Life Expectancy: 30303030 Remaining Life: 6666
$5500/heater; Estimate to replace
$6250/heater; Higher estimate for more labor
Tankless Water Heaters - Replace
General Notes:
building A - building A - building A - building A - (1) Therma-flow tankless water heater(1) Therma-flow tankless water heater(1) Therma-flow tankless water heater(1) Therma-flow tankless water heater m/n: TF-30, s/n: 053188-1 m/n: TF-30, s/n: 053188-1 m/n: TF-30, s/n: 053188-1 m/n: TF-30, s/n: 053188-1building B - building B - building B - building B - (1) Everhot tankless water heater(1) Everhot tankless water heater(1) Everhot tankless water heater(1) Everhot tankless water heater m/n: 30-Wide, s/n: 010907-25 m/n: 30-Wide, s/n: 010907-25 m/n: 30-Wide, s/n: 010907-25 m/n: 30-Wide, s/n: 010907-25building C - building C - building C - building C - (1) Everhot tankless water heaters(1) Everhot tankless water heaters(1) Everhot tankless water heaters(1) Everhot tankless water heaters m/n: 25-long, s/n: 030411-06 m/n: 25-long, s/n: 030411-06 m/n: 25-long, s/n: 030411-06 m/n: 25-long, s/n: 030411-06building D - building D - building D - building D - (1) Everhot tankless water heater(1) Everhot tankless water heater(1) Everhot tankless water heater(1) Everhot tankless water heater m/n: 25-long, s/n: 072110-12 m/n: 25-long, s/n: 072110-12 m/n: 25-long, s/n: 072110-12 m/n: 25-long, s/n: 072110-12building E - building E - building E - building E - (1) Everhot tankless water heater (no visible badge)(1) Everhot tankless water heater (no visible badge)(1) Everhot tankless water heater (no visible badge)(1) Everhot tankless water heater (no visible badge)building F - building F - building F - building F - (1) Everhot tankless water heater(1) Everhot tankless water heater(1) Everhot tankless water heater(1) Everhot tankless water heater m/n: 25-long, s/n: 04012-13 m/n: 25-long, s/n: 04012-13 m/n: 25-long, s/n: 04012-13 m/n: 25-long, s/n: 04012-13building G - building G - building G - building G - (1) Everhot tankless water heater (badge illegible)(1) Everhot tankless water heater (badge illegible)(1) Everhot tankless water heater (badge illegible)(1) Everhot tankless water heater (badge illegible)building H - building H - building H - building H - (1) Everhot tankless water heater(1) Everhot tankless water heater(1) Everhot tankless water heater(1) Everhot tankless water heater m/n: 25-long, s/n: 101508-20 m/n: 25-long, s/n: 101508-20 m/n: 25-long, s/n: 101508-20 m/n: 25-long, s/n: 101508-20building I - building I - building I - building I - (1) Everhot tankless water heater (no label)(1) Everhot tankless water heater (no label)(1) Everhot tankless water heater (no label)(1) Everhot tankless water heater (no label)
Sunday, August 11, 2013Page 24 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 715
Source of Information: Cost Database
Best Cost: $20,000$20,000$20,000$20,000
Worst Cost: $25,000$25,000$25,000$25,000
Location: Building mechanical roomsBuilding mechanical roomsBuilding mechanical roomsBuilding mechanical rooms
Quantity: Approx. (35) pumpsApprox. (35) pumpsApprox. (35) pumpsApprox. (35) pumps
Observations:
Ages and conditions vary from mechanical room to mechanical room. It was reported that several pumps have been replaced recently. Due to the varying ages, we recommend establishing Reserve funds for periodic replacement of the needed pumps every 3 years.
Life Expectancy: 3333 Remaining Life: 1111
Allowance for partial replacement
Higher allowance for more replacement
Pumps - Replace
General Notes:
building A - (2) Grundsfos circ pumpsbuilding A - (2) Grundsfos circ pumpsbuilding A - (2) Grundsfos circ pumpsbuilding A - (2) Grundsfos circ pumpsbuilding B - (2) Grundsfos circ pumps, (3) ass't small circ building B - (2) Grundsfos circ pumps, (3) ass't small circ building B - (2) Grundsfos circ pumps, (3) ass't small circ building B - (2) Grundsfos circ pumps, (3) ass't small circ pumpspumpspumpspumpsbuilding C - (1) Grundsfos circ pumps, (3) ass't small circ building C - (1) Grundsfos circ pumps, (3) ass't small circ building C - (1) Grundsfos circ pumps, (3) ass't small circ building C - (1) Grundsfos circ pumps, (3) ass't small circ pumpspumpspumpspumpsbuilding D - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding D - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding D - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding D - (1) Grundsfos circ pump, (3) ass't small circ pumpsBuilding E - (1) Grundsfos circ pump, (3) ass't small circ pumpsBuilding E - (1) Grundsfos circ pump, (3) ass't small circ pumpsBuilding E - (1) Grundsfos circ pump, (3) ass't small circ pumpsBuilding E - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding F - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding F - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding F - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding F - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding G - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding G - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding G - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding G - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding H - (1) Grundsfos circ pumpbuilding H - (1) Grundsfos circ pumpbuilding H - (1) Grundsfos circ pumpbuilding H - (1) Grundsfos circ pumpbuilding I - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding I - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding I - (1) Grundsfos circ pump, (3) ass't small circ pumpsbuilding I - (1) Grundsfos circ pump, (3) ass't small circ pumps
Sunday, August 11, 2013Page 25 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 721
Source of Information: Cost Database
Best Cost: $15,000$15,000$15,000$15,000
Worst Cost: $18,000$18,000$18,000$18,000
Location: Unit buildings A - I mechanical roomsUnit buildings A - I mechanical roomsUnit buildings A - I mechanical roomsUnit buildings A - I mechanical rooms
Quantity: Approx. (23) tanksApprox. (23) tanksApprox. (23) tanksApprox. (23) tanks
Observations:
Ages and conditions vary from mechanical room to mechanical room. Based on dates on the tanks, it appears that several tanks have been replaced recently. Due to the varying ages, we recommend establishing Reserve funds for periodic replacement of the needed tanks every 5 years.
Life Expectancy: 5555 Remaining Life: 3333
Allowance for partial replacement
Higher allowance for more replacement
Expansion Tanks - Replace
General Notes:
building A - (2) tanks building A - (2) tanks building A - (2) tanks building A - (2) tanks Wessels - 1995, Amtrol - 2011 Wessels - 1995, Amtrol - 2011 Wessels - 1995, Amtrol - 2011 Wessels - 1995, Amtrol - 2011building B - (2) tanksbuilding B - (2) tanksbuilding B - (2) tanksbuilding B - (2) tanks AX200V - 1998, Amtrol - 2002 AX200V - 1998, Amtrol - 2002 AX200V - 1998, Amtrol - 2002 AX200V - 1998, Amtrol - 2002building C - (2) tanksbuilding C - (2) tanksbuilding C - (2) tanksbuilding C - (2) tanks Amtrol - 2008, Amtrol - 2010 Amtrol - 2008, Amtrol - 2010 Amtrol - 2008, Amtrol - 2010 Amtrol - 2008, Amtrol - 2010building D - (2) tanksbuilding D - (2) tanksbuilding D - (2) tanksbuilding D - (2) tanks Extol - 2009, Therm X Trol - 2005 Extol - 2009, Therm X Trol - 2005 Extol - 2009, Therm X Trol - 2005 Extol - 2009, Therm X Trol - 2005building E - (1) tankbuilding E - (1) tankbuilding E - (1) tankbuilding E - (1) tank Therm X Trol - 2010 Therm X Trol - 2010 Therm X Trol - 2010 Therm X Trol - 2010building F - (1) tankbuilding F - (1) tankbuilding F - (1) tankbuilding F - (1) tank Therm X Trol - 2010 Therm X Trol - 2010 Therm X Trol - 2010 Therm X Trol - 2010building G - (2) tanksbuilding G - (2) tanksbuilding G - (2) tanksbuilding G - (2) tanks Amtrol - 2010, Extrol - 2011 Amtrol - 2010, Extrol - 2011 Amtrol - 2010, Extrol - 2011 Amtrol - 2010, Extrol - 2011building H - (3) tanksbuilding H - (3) tanksbuilding H - (3) tanksbuilding H - (3) tanks Extrol - 2008, Therm X Trol - 2008, Extrol - 2008 Extrol - 2008, Therm X Trol - 2008, Extrol - 2008 Extrol - 2008, Therm X Trol - 2008, Extrol - 2008 Extrol - 2008, Therm X Trol - 2008, Extrol - 2008building I - (2) tanksbuilding I - (2) tanksbuilding I - (2) tanksbuilding I - (2) tanks Extrol - no date, Therm X Trol - 2009 Extrol - no date, Therm X Trol - 2009 Extrol - no date, Therm X Trol - 2009 Extrol - no date, Therm X Trol - 2009
Sunday, August 11, 2013Page 26 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 901
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Throughout community buildingsThroughout community buildingsThroughout community buildingsThroughout community buildings
Quantity: (9) Silent Knight panels(9) Silent Knight panels(9) Silent Knight panels(9) Silent Knight panels
Observations:
System was not tested during inspection. It was reported the panels are a conventional panel, meaning it reports problem areas on a particular floor, as opposed to an exact location. Upgrades to an addressable system are not required unless the entire building had to be replaced for an unknown reason. These conventional panels cost less than $1500 each to replace and the ages of these panels range from 5 - 10 years old. Due to the small cost and varying ages, we recommend replacing the panels on an as needed basis with general operating funds. Therefore, as long as replacement can occur with conventional panels, then separate Reserve funding is not required for this component.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Fire Protection System - Replace
General Notes:
Bldg. A - Silent Knight - m/n: SK-5208Bldg. A - Silent Knight - m/n: SK-5208Bldg. A - Silent Knight - m/n: SK-5208Bldg. A - Silent Knight - m/n: SK-5208Bldg. B - Silent Knight - m/n: SK-5208Bldg. B - Silent Knight - m/n: SK-5208Bldg. B - Silent Knight - m/n: SK-5208Bldg. B - Silent Knight - m/n: SK-5208Bldg. C - Silent Knight - m/n: SK-5208Bldg. C - Silent Knight - m/n: SK-5208Bldg. C - Silent Knight - m/n: SK-5208Bldg. C - Silent Knight - m/n: SK-5208Bldg. D - Silent Knight - m/n: SK-5208Bldg. D - Silent Knight - m/n: SK-5208Bldg. D - Silent Knight - m/n: SK-5208Bldg. D - Silent Knight - m/n: SK-5208Bldg. E - Silent Knight - m/n: SK-5207Bldg. E - Silent Knight - m/n: SK-5207Bldg. E - Silent Knight - m/n: SK-5207Bldg. E - Silent Knight - m/n: SK-5207Bldg. F - Silent Knight - m/n: SK-5207Bldg. F - Silent Knight - m/n: SK-5207Bldg. F - Silent Knight - m/n: SK-5207Bldg. F - Silent Knight - m/n: SK-5207Bldg. G - Silent Knight - m/n: SK-5207Bldg. G - Silent Knight - m/n: SK-5207Bldg. G - Silent Knight - m/n: SK-5207Bldg. G - Silent Knight - m/n: SK-5207Bldg. H - Silent Knight - m/n: SK-5208Bldg. H - Silent Knight - m/n: SK-5208Bldg. H - Silent Knight - m/n: SK-5208Bldg. H - Silent Knight - m/n: SK-5208Bldg. I - Silent Knight - m/n: SK-5208Bldg. I - Silent Knight - m/n: SK-5208Bldg. I - Silent Knight - m/n: SK-5208Bldg. I - Silent Knight - m/n: SK-5208
Sunday, August 11, 2013Page 27 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 1424
Source of Information: Cost Database
Best Cost: $30,000$30,000$30,000$30,000
Worst Cost: $36,000$36,000$36,000$36,000
Location: Unit buildings A - IUnit buildings A - IUnit buildings A - IUnit buildings A - I
Quantity: See General NotesSee General NotesSee General NotesSee General Notes
Observations:
Interior décor and conditions vary from building to building. Level of use and care will also dictate the frequency of addressing certain needs in the hallways. Due to the varying conditions of the hallways, we have established a Reserve allowance to refurbish 3 interiors every 5 years. Included in the refurbishment costs are painting/sealing the wall surfaces and replacing flooring products. Major upgrades, such as completely remodeling the interiors is not included in this report. If the association has a desire for major upgrades and complete renovation of the interiors, we would be able to add funding for that project in future Reserve Study updates.
Life Expectancy: 5555 Remaining Life: 1111
Allowance to refurbish interior hallways
Higher allowance for minor upgrades
Unit Building Interiors - Refurbish
General Notes:
Buildings A, B, C, - Buildings A, B, C, - Buildings A, B, C, - Buildings A, B, C, - carpet - 185 GSY, slate tile - 40 GSFcarpet - 185 GSY, slate tile - 40 GSFcarpet - 185 GSY, slate tile - 40 GSFcarpet - 185 GSY, slate tile - 40 GSFhandrail - 130 LF, interior siding - 1,880 GSFhandrail - 130 LF, interior siding - 1,880 GSFhandrail - 130 LF, interior siding - 1,880 GSFhandrail - 130 LF, interior siding - 1,880 GSFpainted areas - 2,865 GSF, unit doors - (23) 3x7painted areas - 2,865 GSF, unit doors - (23) 3x7painted areas - 2,865 GSF, unit doors - (23) 3x7painted areas - 2,865 GSF, unit doors - (23) 3x7utility doors - (3) 3x7 doorsutility doors - (3) 3x7 doorsutility doors - (3) 3x7 doorsutility doors - (3) 3x7 doors Building D - Building D - Building D - Building D - sub interior siding - 3,765 GSF sub interior siding - 3,765 GSF sub interior siding - 3,765 GSF sub interior siding - 3,765 GSF sub paint - 800 GSF sub paint - 800 GSF sub paint - 800 GSF sub paint - 800 GSF Building E - Building E - Building E - Building E - add slate tile - 65 GSF add slate tile - 65 GSF add slate tile - 65 GSF add slate tile - 65 GSF Building F - Building F - Building F - Building F - add carpet - 65 GSY add carpet - 65 GSY add carpet - 65 GSY add carpet - 65 GSY add paint - 1,345 GSF add paint - 1,345 GSF add paint - 1,345 GSF add paint - 1,345 GSF Building H - Building H - Building H - Building H - sub carpet - 225 GSY sub carpet - 225 GSY sub carpet - 225 GSY sub carpet - 225 GSY sub paint - 2,930 GSF sub paint - 2,930 GSF sub paint - 2,930 GSF sub paint - 2,930 GSF Building G & I - Building G & I - Building G & I - Building G & I - add carpet - 25 GSY add carpet - 25 GSY add carpet - 25 GSY add carpet - 25 GSY add slate tile - 65 GSF add slate tile - 65 GSF add slate tile - 65 GSF add slate tile - 65 GSF add paint - 1,345 GSF add paint - 1,345 GSF add paint - 1,345 GSF add paint - 1,345 GSF sub unit doors - (20) 3x7 doors sub unit doors - (20) 3x7 doors sub unit doors - (20) 3x7 doors sub unit doors - (20) 3x7 doors add vinyl flooring - 105 GSF add vinyl flooring - 105 GSF add vinyl flooring - 105 GSF add vinyl flooring - 105 GSF
Sunday, August 11, 2013Page 28 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 1506
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Unit buildings A - IUnit buildings A - IUnit buildings A - IUnit buildings A - I
Quantity: Approx. 560 GSYApprox. 560 GSYApprox. 560 GSYApprox. 560 GSY
Observations:
Conditions vary from building to building. Due to the small area per building, we recommend replacing this carpeting on an as needed basis with general operating funds.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Outdoor Carpet - Replace
General Notes:
Approx. 62 yards, (48) stairs average per building x 9 bldgs = Approx. 62 yards, (48) stairs average per building x 9 bldgs = Approx. 62 yards, (48) stairs average per building x 9 bldgs = Approx. 62 yards, (48) stairs average per building x 9 bldgs = 560 GSY560 GSY560 GSY560 GSY
Sunday, August 11, 2013Page 29 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - IComponent Inventory for Buildings A - I
Comp #: 1602
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Exterior and interior lightingExterior and interior lightingExterior and interior lightingExterior and interior lighting
Quantity: Numerous fixturesNumerous fixturesNumerous fixturesNumerous fixtures
Observations:
Lights are in good condition. Due to the minimal cost to replace these lights, Reserve funding is not appropriate. Repair and replace as necessary as an operating expense.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Wall Mounted Lights - Replace
General Notes:
Sunday, August 11, 2013Page 30 of 30
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 105
Source of Information: Cost Database
Best Cost: $42,000$42,000$42,000$42,000
Worst Cost: $49,000$49,000$49,000$49,000
Location: Building J & K roofsBuilding J & K roofsBuilding J & K roofsBuilding J & K roofs
Quantity: Approx. 70 SquaresApprox. 70 SquaresApprox. 70 SquaresApprox. 70 Squares
Observations:
It was reported these buildings were constructed in 2008. Even though this roof may be rated as a 30 year roof, a life expectancy of 18 - 22 years is expected in this environment due to extreme weather elements. The remaining life is based on the reported age of the roofs and the observed conditions at the time of our field work.
Life Expectancy: 22222222 Remaining Life: 17171717
$600/square; Estimate to remove and replace
$700/square; Higher estimate for more labor costs
Comp Shingle Roof - Replace
General Notes:
(2) buildings @ 35 squares each = 70 squares(2) buildings @ 35 squares each = 70 squares(2) buildings @ 35 squares each = 70 squares(2) buildings @ 35 squares each = 70 squares
Sunday, April 28, 2013Page 1 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 120
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Bldg J & K roof perimeterBldg J & K roof perimeterBldg J & K roof perimeterBldg J & K roof perimeter
Quantity: Approx. 130 LFApprox. 130 LFApprox. 130 LFApprox. 130 LF
Observations:
Quantity is too small for separate Reserve designation. Repair on an as needed basis with general operating funds. Replace at the same time as roof replacement to ensure proper size is installed and to achieve the best cost possible.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Gutters/Downspouts - Replace
General Notes:
(2) buildings @ 65 LF each = 130 LF(2) buildings @ 65 LF each = 130 LF(2) buildings @ 65 LF each = 130 LF(2) buildings @ 65 LF each = 130 LF
Sunday, April 28, 2013Page 2 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 121
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: North side of roofsNorth side of roofsNorth side of roofsNorth side of roofs
Quantity: Approx. 130 GSFApprox. 130 GSFApprox. 130 GSFApprox. 130 GSF
Observations:
Heat tape has been installed along edges of roof to prevent frost damage to roof shingle during winter months. No problems noted or reported during time of inspection. Linear foot measurement refers to the amount of roof surfaces to which the heat tape is applied and is not the actual measurement of the heat tape used. Due to small area, repairs should be conducted on an as needed basis with general operating funds. Separate Reserve funding is not required for this component at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Heat Tape - Replace
General Notes:
NOTE: Heat tape quantities are not actual, we use the linear NOTE: Heat tape quantities are not actual, we use the linear NOTE: Heat tape quantities are not actual, we use the linear NOTE: Heat tape quantities are not actual, we use the linear foot measurement of the roof line/s in which it is installed.foot measurement of the roof line/s in which it is installed.foot measurement of the roof line/s in which it is installed.foot measurement of the roof line/s in which it is installed.
Sunday, April 28, 2013Page 3 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 204
Source of Information: Cost Database
Best Cost: $8,000$8,000$8,000$8,000
Worst Cost: $10,000$10,000$10,000$10,000
Location: Siding, trim, railings, etc.Siding, trim, railings, etc.Siding, trim, railings, etc.Siding, trim, railings, etc.
Quantity: (4) Units(4) Units(4) Units(4) Units
Observations:
At the time of construction, it appears that a transparent stain was applied to the surfaces. If a solid stain was applied the next time around, then the restaining cycle could range from 4 - 5 years. If the association sticks with a transparent stain, expect to reseal the buildings every 3 - 4 years. Current conditions are poor and in need of a sealant this year.
Life Expectancy: 5555 Remaining Life: 0000
$2000/unit; estimate to reseal
Higher estimate for more prep work
Building Ext Surfaces - Reseal
General Notes:
Sunday, April 28, 2013Page 4 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 305
Source of Information: Cost Database
Best Cost: $8,000$8,000$8,000$8,000
Worst Cost: $10,000$10,000$10,000$10,000
Location: Buildings J & KBuildings J & KBuildings J & KBuildings J & K
Quantity: Approx. 10,650 GSFApprox. 10,650 GSFApprox. 10,650 GSFApprox. 10,650 GSF
Observations:
Majority of siding materials were in good condition at time of field work. There was one small board (looks like a patch) on the back side of the building that was split and had a small piece missing. This can be repaired prior to sealing this year. Due to the type of material and the probability of periodic repairs, we recommend establishing a Reserve allowance for major repairs every other sealing cycle. As the buildings age and a history of repairs is established, we can adjust the cost accordingly in future Reserve Study updates.
Life Expectancy: 10101010 Remaining Life: 5555
Allowance for major repairs every other seal cycle
Higher allowance for more repairs
Wood Siding - Replace/Major Repairs
General Notes:
(2) buildings @ 5,325 GSF each = 10,650 GSF(2) buildings @ 5,325 GSF each = 10,650 GSF(2) buildings @ 5,325 GSF each = 10,650 GSF(2) buildings @ 5,325 GSF each = 10,650 GSF
Sunday, April 28, 2013Page 5 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 309
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Buildings J & KBuildings J & KBuildings J & KBuildings J & K
Quantity: Approx. 1,070 GSFApprox. 1,070 GSFApprox. 1,070 GSFApprox. 1,070 GSF
Observations:
Stones appeared to be adhered to the sides well with no loose or missing stone noted. These are stones with a flat backing to ensure proper attachment to the buildings. Typically, these stones have an extended life expectancy and complete replacement is unlikely. There are times where some stones will loosen and fall off, but this is unpredictable when and how much would occur. Repairs should be handled as a maintenance issue on an as needed basis. No reserve funding is required for this component at this time. If it later turns out that frequent repairs are necessary, then funding could be added in future Reserve Study updates.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Stone/Rock Siding - Major Repairs
General Notes:
(2) buildings @ 535 GSF each = 1,070 GSF(2) buildings @ 535 GSF each = 1,070 GSF(2) buildings @ 535 GSF each = 1,070 GSF(2) buildings @ 535 GSF each = 1,070 GSF
Sunday, April 28, 2013Page 6 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 501
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Building J & KBuilding J & KBuilding J & KBuilding J & K
Quantity: (8) 3x7 doors(8) 3x7 doors(8) 3x7 doors(8) 3x7 doors
Observations:
No unusual conditions noted at time of property observation. Declarations are unclear as to who is responsible for the doors, but it is assumed the doors are the responsibility of the unit owner. Therefore, separate Reserve funding is not required for this component.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Unit Doors - Replace
General Notes:
front doors - (2) 3x7 doors, (2) 3x7 doors w/litefront doors - (2) 3x7 doors, (2) 3x7 doors w/litefront doors - (2) 3x7 doors, (2) 3x7 doors w/litefront doors - (2) 3x7 doors, (2) 3x7 doors w/lite (per building) (per building) (per building) (per building)
Sunday, April 28, 2013Page 7 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 502
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Buildings J & KBuildings J & KBuildings J & KBuildings J & K
Quantity: (4) 8x16 OH doors(4) 8x16 OH doors(4) 8x16 OH doors(4) 8x16 OH doors
Observations:
No major problems observed with the garage doors at the time of inspection. According to the declarations, the garage doors are not the responsibility of the association. Therefore, at this time, Reserve funding is not required for this component. Some associations decide to take on the responsibility as an HOA expense in order to maintain a consistent appearance and to obtain the best replacement cost possible. If this occurs, we can add Reserve funding in future Reserve Study updates.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Garage Doors - Replace
General Notes:
Sunday, April 28, 2013Page 8 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 601
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Buildings J & KBuildings J & KBuildings J & KBuildings J & K
Quantity: Approx. 240 GSFApprox. 240 GSFApprox. 240 GSFApprox. 240 GSF
Observations:
All of the concrete surfaces are new and in good condition with only minor areas of cracking noted. Due to small area, we recommend treating repairs on an as needed basis. Therefore, separate Reserve funding is not required for this component.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Concrete Patios - Repair
General Notes:
patio/porch - 140 GSFpatio/porch - 140 GSFpatio/porch - 140 GSFpatio/porch - 140 GSFsite concrete - 100 GSFsite concrete - 100 GSFsite concrete - 100 GSFsite concrete - 100 GSF
Sunday, April 28, 2013Page 9 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 606
Source of Information: Cost Database
Best Cost: $15,300$15,300$15,300$15,300
Worst Cost: $19,125$19,125$19,125$19,125
Location: Buildings J & KBuildings J & KBuildings J & KBuildings J & K
Quantity: Approx. 765 GSFApprox. 765 GSFApprox. 765 GSFApprox. 765 GSF
Observations:
Minor splitting of a few boards were noted on the upper level entry walkway deck. Unable to visually observe the condition of the private decks due to accessibility and privacy issues. In this climate, the average life expectancy for wood decks ranges between 10 - 15 years, depending on the quality of the materials and the level of care.
Life Expectancy: 12121212 Remaining Life: 7777
$20.00/GSF; Estimate to replace
Higher estimate for upgraded materials
Wood Deck - Replace
General Notes:
upper decks - 460 GSFupper decks - 460 GSFupper decks - 460 GSFupper decks - 460 GSFupper entry decks - 305 GSFupper entry decks - 305 GSFupper entry decks - 305 GSFupper entry decks - 305 GSF
Sunday, April 28, 2013Page 10 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 1001
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Buildings J & KBuildings J & KBuildings J & KBuildings J & K
Quantity: Approx. 160 LFApprox. 160 LFApprox. 160 LFApprox. 160 LF
Observations:
Cost for major repairs or replacement is included with the decking estimate. Therefore, separate Reserve funding is not required for this component.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Wood/Iron Rails - Replace
General Notes:
Upper decks - 130 LFUpper decks - 130 LFUpper decks - 130 LFUpper decks - 130 LFlower/front porch - 30 LFlower/front porch - 30 LFlower/front porch - 30 LFlower/front porch - 30 LFupper/entry decks - 105 LFupper/entry decks - 105 LFupper/entry decks - 105 LFupper/entry decks - 105 LF
Sunday, April 28, 2013Page 11 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 1011
Source of Information: Cost Database
Best Cost: $14,500$14,500$14,500$14,500
Worst Cost: $17,500$17,500$17,500$17,500
Location: Buildings J & KBuildings J & KBuildings J & KBuildings J & K
Quantity: Approx. 290 GSFApprox. 290 GSFApprox. 290 GSFApprox. 290 GSF
Observations:
Wall was structurally stable and intact at time of field work. No unusual conditions were present at that time. Generally, in most conditions, these walls have an overall life expectancy of 20 - 25 years. However, with periodic repairs, the life of the wall can be extended. The top timber tends to become the first piece to deteriorate and need to be replaced. This type of wall also tends to be susceptible to movement and leaning. When replacement is necessary, most associations are converting to block wall for longer life expectancy and less maintenance.
Life Expectancy: 30303030 Remaining Life: 25252525
Estimate to replace
Higher estimate for more labor
Retaining Wall - Replace
General Notes:
Sunday, April 28, 2013Page 12 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - KComponent Inventory for Buildings J - K
Comp #: 1602
Source of Information: Cost Database
Best Cost: $3,000$3,000$3,000$3,000
Worst Cost: $3,600$3,600$3,600$3,600
Location: Buildings J & K exteriorBuildings J & K exteriorBuildings J & K exteriorBuildings J & K exterior
Quantity: Approx. (20) fixturesApprox. (20) fixturesApprox. (20) fixturesApprox. (20) fixtures
Observations:
No unusual conditions were observed or reported at time of observation. While replacement can occur on an as needed basis, it is our opinion and recommendation to replace all lights at the same time every 12 - 15 years to maintain a consistent appearance throughout the property. In addition, by replacing multiple fixtures, the association will be able to obtain a quantity discount for the fixtures. Estimated replacement cost includes labor for installation. Remaining life based on observed conditions and age.
Life Expectancy: 15151515 Remaining Life: 10101010
$150/light; Estimate to replace
$180/light; Higher estimate for better quality
Exterior Wall Mount - Replace
General Notes:
Sunday, April 28, 2013Page 13 of 13
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 104
Source of Information: Cost database
Best Cost: $12,000$12,000$12,000$12,000
Worst Cost: $13,125$13,125$13,125$13,125
Location: Building roofBuilding roofBuilding roofBuilding roof
Quantity: Approx. 15 squaresApprox. 15 squaresApprox. 15 squaresApprox. 15 squares
Observations:
Direct access was not available to all areas at time of initial field observation, and follow up field work took place during winter months. No reports of problems with the roof were noted. The average life expectancy for this type of roof ranges between 12 - 18 years in this climate. Remaining life is based on the age of this building.
Life Expectancy: 17171717 Remaining Life: 7777
$800/square; Estimate to replace
$875/square; Higher estimate for more labor
Flat Roof - Replace
General Notes:
Sunday, August 11, 2013Page 1 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 105
Source of Information: Cost Database
Best Cost: $47,500$47,500$47,500$47,500
Worst Cost: $53,200$53,200$53,200$53,200
Location: Building roofBuilding roofBuilding roofBuilding roof
Quantity: Approx. 76 sqsApprox. 76 sqsApprox. 76 sqsApprox. 76 sqs
Observations:
This building was constructed about 5 years ago after the original building burned down. Even though this roof may be rated as a 30 year roof, a life expectancy of 18 - 22 years is expected in this environment. Due to the potentially harsh environment, we typically see associations replacing roofs sooner than the manufacturer's suggested useful life.
Life Expectancy: 22222222 Remaining Life: 12121212
$625/square; estimate to replace
$700/square; Higher estimate for more labor costs
Comp Shingle Roof - Replace
General Notes:
Sunday, August 11, 2013Page 2 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 120
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Building roof perimeterBuilding roof perimeterBuilding roof perimeterBuilding roof perimeter
Quantity: Approx. 50 LFApprox. 50 LFApprox. 50 LFApprox. 50 LF
Observations:
Area is too small for separate Reserve designation. Replace as needed with general operating funds.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Gutters/Downspouts/Heat Tape - Replace
General Notes:
Sunday, August 11, 2013Page 3 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 204
Source of Information: Cost Database
Best Cost: $4,000$4,000$4,000$4,000
Worst Cost: $4,750$4,750$4,750$4,750
Location: Siding, trim, handrails, etc.Siding, trim, handrails, etc.Siding, trim, handrails, etc.Siding, trim, handrails, etc.
Quantity: Moderate GSFModerate GSFModerate GSFModerate GSF
Observations:
Painted surfaces are thin and in need of repainting soon. In this climate, we recommend painting every 4 - 5 years to protect the wood from pre-mature deterioration and splitting. Based on observed conditions and age of building, we recommend painting this building as soon as possible.
Life Expectancy: 5555 Remaining Life: 0000
Estimate to repaint exterior surfaces
Higher estimate for more prep work
Building Ext Surfaces - Repaint
General Notes:
Sunday, August 11, 2013Page 4 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 216
Source of Information: Cost Database
Best Cost: $9,530$9,530$9,530$9,530
Worst Cost: $10,960$10,960$10,960$10,960
Location: Interior surfacesInterior surfacesInterior surfacesInterior surfaces
Quantity: Approx. 9,530 GSFApprox. 9,530 GSFApprox. 9,530 GSFApprox. 9,530 GSF
Observations:
Majority of painted surfaces appeared in fair condition at time of observation with local marking noted in many areas. The manager's office showed signs of drywall damage which should be repaired as an operating expense prior to repainting. Expect to repaint interior surfaces in high traffic areas such as the clubhouse every 9 - 10 years.
Life Expectancy: 10101010 Remaining Life: 0000
$1.00/GSF; Estimate to repaint
$1.15/GSF; Higher estimate
Interior Surfaces - Repaint
General Notes:
manager's office - 645 GSFmanager's office - 645 GSFmanager's office - 645 GSFmanager's office - 645 GSFupper level - 1,775 GSFupper level - 1,775 GSFupper level - 1,775 GSFupper level - 1,775 GSFwomen's restroom - 475 GSFwomen's restroom - 475 GSFwomen's restroom - 475 GSFwomen's restroom - 475 GSFmen's restroom - 560 GSFmen's restroom - 560 GSFmen's restroom - 560 GSFmen's restroom - 560 GSFpool area - 3,675 GSFpool area - 3,675 GSFpool area - 3,675 GSFpool area - 3,675 GSFfitness room - 725 GSFfitness room - 725 GSFfitness room - 725 GSFfitness room - 725 GSFlaundry room - 1,675 GSF (incl restroom)laundry room - 1,675 GSF (incl restroom)laundry room - 1,675 GSF (incl restroom)laundry room - 1,675 GSF (incl restroom)
Sunday, August 11, 2013Page 5 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 301
Source of Information: Cost Database
Best Cost: $12,000$12,000$12,000$12,000
Worst Cost: $15,000$15,000$15,000$15,000
Location: Exterior claddingExterior claddingExterior claddingExterior cladding
Quantity: Approx. 9,240 GSFApprox. 9,240 GSFApprox. 9,240 GSFApprox. 9,240 GSF
Observations:
Siding was in good condition with no signs of warped or delaminating pieces of material noted. This type of siding has a life expectancy of 20 - 30 years, depending on the level of maintenance and exposure to elements. As long as the building is painted and the joints are caulked every 4 - 5 years, the overall life could be extended. At this time, we recommend establishing Reserve funding for periodic repairs every 15 years. If siding ages better than expected, then we can adjust this line item in future Reserve Study updates.
Life Expectancy: 15151515 Remaining Life: 5555
Allowance for major repairs
Higher allowance for more repairs
Wood Siding - Major Repairs
General Notes:
Sunday, August 11, 2013Page 6 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 309
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Exterior claddingExterior claddingExterior claddingExterior cladding
Quantity: Approx. 2,025 GSFApprox. 2,025 GSFApprox. 2,025 GSFApprox. 2,025 GSF
Observations:
Due to the very long life expectancy of cultured stone, we do not recommend reserving to completely replace. Due to the low quantity of stonework on site, we do not recommend reserving for major repairs. Frequently inspect and repair the stone work as needed using operating funds.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Stone/Rock Siding - Major Repairs
General Notes:
Interior - Interior - Interior - Interior - lower level - 250 GSF lower level - 250 GSF lower level - 250 GSF lower level - 250 GSF upper level - 510 GSF upper level - 510 GSF upper level - 510 GSF upper level - 510 GSFExterior - 1,265 GSFExterior - 1,265 GSFExterior - 1,265 GSFExterior - 1,265 GSF
Sunday, August 11, 2013Page 7 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 503
Source of Information: Cost Database
Best Cost: $16,250$16,250$16,250$16,250
Worst Cost: $18,750$18,750$18,750$18,750
Location: Common areasCommon areasCommon areasCommon areas
Quantity: Approx. (25) doorsApprox. (25) doorsApprox. (25) doorsApprox. (25) doors
Observations:
No problems noted or reported with clubhouse doors. Expect to replace these doors every 20 - 25 years depending on levels of use and abuse. Make minor repairs or replace individual doors as needed using operating funds between replacement cycles.
Life Expectancy: 25252525 Remaining Life: 15151515
$650/door; Estimate to replace
$750/door; Higher estimate for better quality
Common Area Doors - Replace
General Notes:
Large Clubhouse - Large Clubhouse - Large Clubhouse - Large Clubhouse - manager's office - (1) 3x7 door manager's office - (1) 3x7 door manager's office - (1) 3x7 door manager's office - (1) 3x7 door large clubhouse lower level - (3) 3x7 doors (glass) large clubhouse lower level - (3) 3x7 doors (glass) large clubhouse lower level - (3) 3x7 doors (glass) large clubhouse lower level - (3) 3x7 doors (glass) upper level - (1) 3x7 door upper level - (1) 3x7 door upper level - (1) 3x7 door upper level - (1) 3x7 door stairs/corridor to pool - (3) 3x7 doors stairs/corridor to pool - (3) 3x7 doors stairs/corridor to pool - (3) 3x7 doors stairs/corridor to pool - (3) 3x7 doors women's restroom - (1) 3x7 doors women's restroom - (1) 3x7 doors women's restroom - (1) 3x7 doors women's restroom - (1) 3x7 doors pool area - (5) 3x7 doors pool area - (5) 3x7 doors pool area - (5) 3x7 doors pool area - (5) 3x7 doors laundry room - (6) 3x7 doors laundry room - (6) 3x7 doors laundry room - (6) 3x7 doors laundry room - (6) 3x7 doors exterior metal doors - (3) 3x7 doors exterior metal doors - (3) 3x7 doors exterior metal doors - (3) 3x7 doors exterior metal doors - (3) 3x7 doorsUnit doors - (2) 3x7 doorsUnit doors - (2) 3x7 doorsUnit doors - (2) 3x7 doorsUnit doors - (2) 3x7 doors
Sunday, August 11, 2013Page 8 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 506
Source of Information: Cost Database
Best Cost: $75,600$75,600$75,600$75,600
Worst Cost: $89,600$89,600$89,600$89,600
Location: Large clubhouseLarge clubhouseLarge clubhouseLarge clubhouse
Quantity: Approx. (112) windowsApprox. (112) windowsApprox. (112) windowsApprox. (112) windows
Observations:
Windows appeared in good condition at time of observation with no reported or noted problems. Expect to replace windows every 25 - 30 years. Individual windows can be replaced as an operating expense between replacement cycles.
Life Expectancy: 30303030 Remaining Life: 20202020
$675/opening; Average estimate to replace
$800/window; Higher estimate for better quality
Windows - Replace
General Notes:
manager's office - (1) windowmanager's office - (1) windowmanager's office - (1) windowmanager's office - (1) windowlarge clubhouse lower level - (36) windowslarge clubhouse lower level - (36) windowslarge clubhouse lower level - (36) windowslarge clubhouse lower level - (36) windowsupper level - (46) windowsupper level - (46) windowsupper level - (46) windowsupper level - (46) windowspool area - (26) windowspool area - (26) windowspool area - (26) windowspool area - (26) windowsracquet ball court - (3) windowsracquet ball court - (3) windowsracquet ball court - (3) windowsracquet ball court - (3) windows
Sunday, August 11, 2013Page 9 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 607
Source of Information: Cost Database
Best Cost: $8,000$8,000$8,000$8,000
Worst Cost: $10,000$10,000$10,000$10,000
Location: Building EgressBuilding EgressBuilding EgressBuilding Egress
Quantity: See General NotesSee General NotesSee General NotesSee General Notes
Observations:
Stairways and decks were stable at time of property observation. The average life expectancy for wood stair systems ranges between 17 - 20 years, depending on level of use and maintenance.
Life Expectancy: 20202020 Remaining Life: 10101010
estimate to rebuild deck and stairs
Higher estimate for upgraded materials
Wood Stairs/Deck - Replace
General Notes:
stairs - (39) treadsstairs - (39) treadsstairs - (39) treadsstairs - (39) treadsstringers - 95 LFstringers - 95 LFstringers - 95 LFstringers - 95 LFwood rail - 115 LFwood rail - 115 LFwood rail - 115 LFwood rail - 115 LFdecking - 250 GSFdecking - 250 GSFdecking - 250 GSFdecking - 250 GSF
Sunday, August 11, 2013Page 10 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 608
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Pool areaPool areaPool areaPool area
Quantity: Approx. 1,555 GSFApprox. 1,555 GSFApprox. 1,555 GSFApprox. 1,555 GSF
Observations:
Concrete appeared in good condition at time of observation with no problems noted. Due to this concrete being indoors, it is unlikely that advanced deterioration will occur at any time in the foreseeable future. At some point, reserve funding may need to be added to future updates of this report. Make repairs and seal or caulk any cracks as needed using operating funds.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Pool Deck - Replace
General Notes:
Sunday, August 11, 2013Page 11 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 702
Source of Information: Cost Database
Best Cost: $16,000$16,000$16,000$16,000
Worst Cost: $19,000$19,000$19,000$19,000
Location: Mechanical roomMechanical roomMechanical roomMechanical room
Quantity: (1) boiler(1) boiler(1) boiler(1) boiler
Observations:
Boiler is approximately 10 years old at time of observation with no apparent or reported problems with boiler function. Noted some scaling and rust in the air intake pan of this boiler. Expect to replace this heater every 20 - 25 years depending on levels of maintenance and the quality of the water running through the system.
Life Expectancy: 25252525 Remaining Life: 15151515
Estimate to replace
Higher estimate
Boiler - Replace
General Notes:
Heating boiler - Heating boiler - Heating boiler - Heating boiler - Laars Laars Laars Laars m/n: HH 0715 IN 09 K1AC CQ m/n: HH 0715 IN 09 K1AC CQ m/n: HH 0715 IN 09 K1AC CQ m/n: HH 0715 IN 09 K1AC CQ s/n: C03 A00715 s/n: C03 A00715 s/n: C03 A00715 s/n: C03 A00715715,000 BTU in715,000 BTU in715,000 BTU in715,000 BTU in
Sunday, August 11, 2013Page 12 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 703
Source of Information: Cost Database
Best Cost: $4,500$4,500$4,500$4,500
Worst Cost: $5,500$5,500$5,500$5,500
Location: Mechanical roomMechanical roomMechanical roomMechanical room
Quantity: (1) heater(1) heater(1) heater(1) heater
Observations:
Water heater appeared in working condition at time of observation with no noted or reported problems. Depending on levels of use, expect to replace this water heater every 12 - 15 years. Higher levels of maintenance will lead to a longer useful life.
Life Expectancy: 15151515 Remaining Life: 5555
$4,500/heater; Est for 120 Gallon storage tank
Higher estimate for emergency call
Water Heater - Replace
General Notes:
Water heater - Water heater - Water heater - Water heater - Rheem Ruud Commercial Rheem Ruud Commercial Rheem Ruud Commercial Rheem Ruud Commercial s/n: URNG 0603G02909 s/n: URNG 0603G02909 s/n: URNG 0603G02909 s/n: URNG 0603G02909 m/n: G100-200 m/n: G100-200 m/n: G100-200 m/n: G100-200 100 gal. 100 gal. 100 gal. 100 gal.199,000 BTUin199,000 BTUin199,000 BTUin199,000 BTUindate: 6/2003date: 6/2003date: 6/2003date: 6/2003
Sunday, August 11, 2013Page 13 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 707
Source of Information: Cost Database
Best Cost: $50,000$50,000$50,000$50,000
Worst Cost: $60,000$60,000$60,000$60,000
Location: Elevator control roomElevator control roomElevator control roomElevator control room
Quantity: (1) elevator(1) elevator(1) elevator(1) elevator
Observations:
The elevator was operating smoothly with no problems noted. The inspection and maintenance records on site did not report any unusual problems. This elevator is relatively new and in good condition. Elevator should be inspected annually by a professional to ensure proper operation and to detect any safety concerns. The equipment that will eventually fail and need to be replaced include the control system (brain of the unit), door operator and tracks, and the pump unit. Eventually, parts of the system become obsolete and replacement will be necessary. Due to a moderate use facility, Reserve to replace this equipment every 25 years.
Life Expectancy: 25252525 Remaining Life: 15151515
$50000/elevator; Estimate to rebuild
$60000/elevator; Higher estimate
Elevator - Rebuild/Upgrade
General Notes:
Elevator - Elevator - Elevator - Elevator - OTIS Elevator - OTIS Elevator - OTIS Elevator - OTIS Elevator - 3-phase, 15 hp, 208 Volts 3-phase, 15 hp, 208 Volts 3-phase, 15 hp, 208 Volts 3-phase, 15 hp, 208 Voltscontract #: 469281contract #: 469281contract #: 469281contract #: 469281 s/n: 12340312 s/n: 12340312 s/n: 12340312 s/n: 12340312 m/n: AAA21241U m/n: AAA21241U m/n: AAA21241U m/n: AAA21241U date: 3/19/2003 date: 3/19/2003 date: 3/19/2003 date: 3/19/2003
Sunday, August 11, 2013Page 14 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 709
Source of Information: Cost Database
Best Cost: $12,000$12,000$12,000$12,000
Worst Cost: $15,000$15,000$15,000$15,000
Location: Elevator control roomElevator control roomElevator control roomElevator control room
Quantity: (1) elevator(1) elevator(1) elevator(1) elevator
Observations:
No unusual wear or deterioration noted on cab interiors. Timing of remodels and décor choices depend on the association ownership and desires to improve appearance. Per new Colorado conveyance regulations, it is required that a licensed elevator contractor oversee all cab renovations unless you are replacing like-for-like (e.g. replacing old tile with new tile). New interiors also have to be permitted with the state so that they meet code standards such as flame spread ratings, retain proper ventilation, etc. This new regulation has caused the cost of remodeling to increase by more than double over the past couple years.
Life Expectancy: 15151515 Remaining Life: 5555
$12000/cab; Estimate for a basic remodel
$15000/cab; Higher estimate
Elevator Cab - Remodel
General Notes:
OTIS Elevator - OTIS Elevator - OTIS Elevator - OTIS Elevator - 3 stop, 2,100 lbs 3 stop, 2,100 lbs 3 stop, 2,100 lbs 3 stop, 2,100 lbs
Formica (or similar) walls - 65 GSFFormica (or similar) walls - 65 GSFFormica (or similar) walls - 65 GSFFormica (or similar) walls - 65 GSFcarpet - 20 GSFcarpet - 20 GSFcarpet - 20 GSFcarpet - 20 GSFlighted ceiling panel - 20 GSFlighted ceiling panel - 20 GSFlighted ceiling panel - 20 GSFlighted ceiling panel - 20 GSF
Sunday, August 11, 2013Page 15 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 715
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Mechanical RoomMechanical RoomMechanical RoomMechanical Room
Quantity: Approx. (2) circ pumpsApprox. (2) circ pumpsApprox. (2) circ pumpsApprox. (2) circ pumps
Observations:
Due to low quantity and low cost of replacement, we do not recommend reserving to replace these pumps at this time. Replace as needed using operating funds.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Pumps - Replace
General Notes:
Sunday, August 11, 2013Page 16 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 721
Source of Information: Cost database
Best Cost: $3,500$3,500$3,500$3,500
Worst Cost: $4,500$4,500$4,500$4,500
Location: Mechanical roomMechanical roomMechanical roomMechanical room
Quantity: (4) expansion tanks(4) expansion tanks(4) expansion tanks(4) expansion tanks
Observations:
The cause of failure for expansion tanks is deterioration of the rubber bladder over time or the sudden pressurization within the system. Both of these causes are unpredictable, and therefore cannot be classified as a reserve item. However, due to the large quantity of expansion tanks on site, we recommend reserving an allowance to replace tanks as needed every 8 - 10 years.
Life Expectancy: 10101010 Remaining Life: 2222
Allowance to replace needed tanks
Higher allowance for more labor
Expansion Tanks - Replace
General Notes:
(3) small expansion tanks(3) small expansion tanks(3) small expansion tanks(3) small expansion tanks(1) medium expansion tank.(1) medium expansion tank.(1) medium expansion tank.(1) medium expansion tank.
Sunday, August 11, 2013Page 17 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 901
Source of Information: Cost Database
Best Cost: $3,500$3,500$3,500$3,500
Worst Cost: $3,850$3,850$3,850$3,850
Location: Lower level main roomLower level main roomLower level main roomLower level main room
Quantity: (1) Fire panel(1) Fire panel(1) Fire panel(1) Fire panel
Observations:
No problems noted or reported with panel at time of observation. Perform regular, professional inspections and testing to panel and system and expect to completely replace panels approximately every 20 to 25 years.
Life Expectancy: 25252525 Remaining Life: 15151515
$3500/Panel; Estimate to replace
Higher estimate for additional parts
Fire Protection System - Replace
General Notes:
Fire panel - EST-2Fire panel - EST-2Fire panel - EST-2Fire panel - EST-2
Sunday, August 11, 2013Page 18 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 903
Source of Information: Cost Database
Best Cost: $8,500$8,500$8,500$8,500
Worst Cost: $10,000$10,000$10,000$10,000
Location: Manager's officeManager's officeManager's officeManager's office
Quantity: (1) DVR, (5) cameras(1) DVR, (5) cameras(1) DVR, (5) cameras(1) DVR, (5) cameras
Observations:
DVR was working properly and no reports of problems with cameras at time of observation. Expect to replace video surveillance system every 10 - 12 years.
Life Expectancy: 12121212 Remaining Life: 2222
Estimate to replace
Higher estimate for more functionality
Video Surveillance System - Replace
General Notes:
Sunday, August 11, 2013Page 19 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1101
Source of Information: Cost Database
Best Cost: $10,500$10,500$10,500$10,500
Worst Cost: $11,600$11,600$11,600$11,600
Location: Pool areaPool areaPool areaPool area
Quantity: (1) 12x30 pool (1) 6x7 spa(1) 12x30 pool (1) 6x7 spa(1) 12x30 pool (1) 6x7 spa(1) 12x30 pool (1) 6x7 spa
Observations:
At time of observation, there were no problems noted or reported with the pool. This pool is a fiberglass shell that should be resurfaced approximately every 8 - 9 years to ensure a comfortable and safe environment.
Life Expectancy: 9999 Remaining Life: 4444
Estimate to recoat pool
Higher estimate for more labor
Pool w/Spa - Resurface
General Notes:
Sunday, August 11, 2013Page 20 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1102
Source of Information: Cost Database
Best Cost: $5,000$5,000$5,000$5,000
Worst Cost: $6,000$6,000$6,000$6,000
Location: Pool areaPool areaPool areaPool area
Quantity: (2) spas(2) spas(2) spas(2) spas
Observations:
Similar to the pool, these spas are fiberglass shells that need to be resurfaced on a cyclical basis. Due to the increased level of chemicals and the heat of the water, we recommend resurfacing the spas more often than the pool. Plan on resurfacing projects taking place every 5 - 6 years.
Life Expectancy: 6666 Remaining Life: 1111
$2,500/Spa; Estimate to resurface spa
$3,000/Spa; Higher estimate for more prep work
Spa - Resurface
General Notes:
Sunday, August 11, 2013Page 21 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1105
Source of Information: Cost Database
Best Cost: $3,000$3,000$3,000$3,000
Worst Cost: $3,500$3,500$3,500$3,500
Location: Pool mechanical roomPool mechanical roomPool mechanical roomPool mechanical room
Quantity: (1) heater(1) heater(1) heater(1) heater
Observations:
Pool heater appeared in fair condition with no scaling or rusting noted. However, due to year round use of this pool and the fact that the heater is never taken off line, we expect this heater will have a slightly shorter useful life than seasonal pool setups. Therefore, expect to replace every 10 - 12 years.
Life Expectancy: 12121212 Remaining Life: 2222
$3000/heater; Estimate to replace
$3500/heater; Higher estimate
Pool Heater - Replace
General Notes:
Laars Lite 2Laars Lite 2Laars Lite 2Laars Lite 2 m/n: LG175M m/n: LG175M m/n: LG175M m/n: LG175M s/n: J08PE0859 s/n: J08PE0859 s/n: J08PE0859 s/n: J08PE0859 date: 5/08 date: 5/08 date: 5/08 date: 5/08
175,000 BTU in175,000 BTU in175,000 BTU in175,000 BTU in
Sunday, August 11, 2013Page 22 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1106
Source of Information: Cost Database
Best Cost: $7,500$7,500$7,500$7,500
Worst Cost: $8,400$8,400$8,400$8,400
Location: Pool mechanical roomPool mechanical roomPool mechanical roomPool mechanical room
Quantity: (3) heaters(3) heaters(3) heaters(3) heaters
Observations:
The spa heater showed signs of minor scaling and rust. The typical life of this heater ranges between 10 - 12 years with proper maintenance. The shorter replacement cycle is due to how hard it works to keep the water at a hot temperature, and the level of chemicals that run through the system. The remaining life is based on current age and condition.
Life Expectancy: 12121212 Remaining Life: 2222
$2500/heater; Estimate to replace
$2800/heater; Higher estimate for more labor
Spa Heaters - Replace
General Notes:
Spa #1 - Laars Lite 2Spa #1 - Laars Lite 2Spa #1 - Laars Lite 2Spa #1 - Laars Lite 2 m/n: LD125N-H, s/n: C02PH0182 m/n: LD125N-H, s/n: C02PH0182 m/n: LD125N-H, s/n: C02PH0182 m/n: LD125N-H, s/n: C02PH0182Spa #2 - Laars Lite 2Spa #2 - Laars Lite 2Spa #2 - Laars Lite 2Spa #2 - Laars Lite 2 m/n: LJ125N-H, s/n: D03PI1573 m/n: LJ125N-H, s/n: D03PI1573 m/n: LJ125N-H, s/n: D03PI1573 m/n: LJ125N-H, s/n: D03PI1573Spa #3 - Laars Lite 2Spa #3 - Laars Lite 2Spa #3 - Laars Lite 2Spa #3 - Laars Lite 2 m/n: LJ125NXH, s/n: C03PF1383 m/n: LJ125NXH, s/n: C03PF1383 m/n: LJ125NXH, s/n: C03PF1383 m/n: LJ125NXH, s/n: C03PF1383
All boilers - 125,000 BTU inAll boilers - 125,000 BTU inAll boilers - 125,000 BTU inAll boilers - 125,000 BTU in
Sunday, August 11, 2013Page 23 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1108
Source of Information: Cost Database
Best Cost: $3,600$3,600$3,600$3,600
Worst Cost: $4,500$4,500$4,500$4,500
Location: Pool mechanical roomPool mechanical roomPool mechanical roomPool mechanical room
Quantity: (4) filters(4) filters(4) filters(4) filters
Observations:
These filters will have an extended useful life due to the type of construction and the ability to replace gaskets and seals separate from the shell itself. Expect to replace the sand media every 5 - 7 years depending on levels of use as an operating expense.
Life Expectancy: 20202020 Remaining Life: 10101010
$1200/filter; Estimate to replace
$1500/filter; Higher estimate
Pool Filter - Replace
General Notes:
(3) Triton, Sand Dollar Filters(3) Triton, Sand Dollar Filters(3) Triton, Sand Dollar Filters(3) Triton, Sand Dollar Filters(1) Triton, Tagelus Filter(1) Triton, Tagelus Filter(1) Triton, Tagelus Filter(1) Triton, Tagelus Filter
Sunday, August 11, 2013Page 24 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1121
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Pool areaPool areaPool areaPool area
Quantity: Approx. (15) piecesApprox. (15) piecesApprox. (15) piecesApprox. (15) pieces
Observations:
All pool furniture is plastic and easily replaced with matching pieces in the future. Due to the type of furnishings in the pool area, we recommend replacing as needed using operating funds. No reserve funding necessary at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Pool Furniture - Replace
General Notes:
Large Clubhouse - Large Clubhouse - Large Clubhouse - Large Clubhouse - All furniture is plastic (Rubbermaid or similar) - All furniture is plastic (Rubbermaid or similar) - All furniture is plastic (Rubbermaid or similar) - All furniture is plastic (Rubbermaid or similar) - (5) lounge chairs, (8) chairs, (2) tables (5) lounge chairs, (8) chairs, (2) tables (5) lounge chairs, (8) chairs, (2) tables (5) lounge chairs, (8) chairs, (2) tables
Sunday, August 11, 2013Page 25 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1126
Source of Information: Cost Database
Best Cost: $8,500$8,500$8,500$8,500
Worst Cost: $10,000$10,000$10,000$10,000
Location: Pool mechanical roomPool mechanical roomPool mechanical roomPool mechanical room
Quantity: ExtensiveExtensiveExtensiveExtensive
Observations:
At time of observation all equipment was functioning as expected with no reported or noted problems. Expect to replace various pieces of equipment every 5 - 10 years to stay current in terms of jurisdictional code, efficiency and "green" technology.
Life Expectancy: 7777 Remaining Life: 2222
Allowance for needed replacement equipment
Higher allowance for more needed replacements
Misc. Pool Equipment - Replace
General Notes:
Large Clubhouse - Large Clubhouse - Large Clubhouse - Large Clubhouse - (4) Tab feeders (4) Tab feeders (4) Tab feeders (4) Tab feeders (2) Eclipse, Ozone generators (2) Eclipse, Ozone generators (2) Eclipse, Ozone generators (2) Eclipse, Ozone generators (2) O3 zone by Balboa (2) O3 zone by Balboa (2) O3 zone by Balboa (2) O3 zone by BalboaPumps - Pumps - Pumps - Pumps - (2) A.O. Smith pumps (spa) (2) A.O. Smith pumps (spa) (2) A.O. Smith pumps (spa) (2) A.O. Smith pumps (spa) (1) Extreme E pump (spa) (1) Extreme E pump (spa) (1) Extreme E pump (spa) (1) Extreme E pump (spa) (1) Whisper-Flo pump (pool) (1) Whisper-Flo pump (pool) (1) Whisper-Flo pump (pool) (1) Whisper-Flo pump (pool)
Sunday, August 11, 2013Page 26 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1309
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Lower level main roomLower level main roomLower level main roomLower level main room
Quantity: (1) ping pong table(1) ping pong table(1) ping pong table(1) ping pong table
Observations:
Due to the ability to replace this table with similar equipment from local retailers, we recommend doing so as needed using operating funds. If more game equipment is purchase in the coming years, we can add funding in future updates of this report.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Ping Pong Table - Replace
General Notes:
NOTE: heavily scratched and damagedNOTE: heavily scratched and damagedNOTE: heavily scratched and damagedNOTE: heavily scratched and damaged
Sunday, August 11, 2013Page 27 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1401
Source of Information: Cost Database
Best Cost: $15,000$15,000$15,000$15,000
Worst Cost: $18,000$18,000$18,000$18,000
Location: Large ClubhouseLarge ClubhouseLarge ClubhouseLarge Clubhouse
Quantity: (1) laundry room(1) laundry room(1) laundry room(1) laundry room
Observations:
Laundry room was clean and appeared in good condition at time of observation. It was reported that the laundry machines are leased and therefore funding is not included in this line item or this report. Expect to remodel the laundry room every 18 - 20 years to keep the space appealing to residents and visitors.
Life Expectancy: 20202020 Remaining Life: 10101010
Allowance for general remodel
Higher allowance for better quality materials
Laundry Room - Remodel
General Notes:
Main Room - Main Room - Main Room - Main Room - Formica (or similar) - 100 GSF Formica (or similar) - 100 GSF Formica (or similar) - 100 GSF Formica (or similar) - 100 GSFRestroom - Restroom - Restroom - Restroom - (1) toilet, (1) sink (1) toilet, (1) sink (1) toilet, (1) sink (1) toilet, (1) sink
Sunday, August 11, 2013Page 28 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1403
Source of Information: Cost Database
Best Cost: $12,000$12,000$12,000$12,000
Worst Cost: $15,000$15,000$15,000$15,000
Location: Upper levelUpper levelUpper levelUpper level
Quantity: (1) kitchen(1) kitchen(1) kitchen(1) kitchen
Observations:
At time of observation the kitchen appeared clean but some minor damage was noted. Signs of abuse were noted during observation. Expect to remodel the kitchen area every 12 - 15 years in order to maintain an attractive appearance.
Life Expectancy: 15151515 Remaining Life: 5555
Allowance to remodel kitchen
Higher allowance for better quality materials
Kitchen - Remodel
General Notes:
Upper level kitchen - Upper level kitchen - Upper level kitchen - Upper level kitchen - countertop (Formica or similar) - 115 GSF countertop (Formica or similar) - 115 GSF countertop (Formica or similar) - 115 GSF countertop (Formica or similar) - 115 GSF cabinetry - (15) lower, (10) upper cabinetry - (15) lower, (10) upper cabinetry - (15) lower, (10) upper cabinetry - (15) lower, (10) upperAppliances - Appliances - Appliances - Appliances - (1) range/oven, (1) refrigerator, (1) dishwasher (1) range/oven, (1) refrigerator, (1) dishwasher (1) range/oven, (1) refrigerator, (1) dishwasher (1) range/oven, (1) refrigerator, (1) dishwasher
Sunday, August 11, 2013Page 29 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1405
Source of Information: Cost Database
Best Cost: $18,000$18,000$18,000$18,000
Worst Cost: $20,000$20,000$20,000$20,000
Location: Throughout clubhouseThroughout clubhouseThroughout clubhouseThroughout clubhouse
Quantity: Approx. (63) piecesApprox. (63) piecesApprox. (63) piecesApprox. (63) pieces
Observations:
Furnishings appeared aged and in need of replacement at time of observation. Similar to other areas in the clubhouse, the furniture has been heavily used or abused detracting from the overall appearance of the space. Expect to replace furniture, in a high use facility, every 5 - 6 years to maintain an attractive appearance.
Life Expectancy: 6666 Remaining Life: 0000
Allowance to replace furnishings
Higher allowance for more needed furniture
Furnishings - Replace
General Notes:
Large Clubhouse -Large Clubhouse -Large Clubhouse -Large Clubhouse - manager's office - (1) sofa, (3) desk chairs, manager's office - (1) sofa, (3) desk chairs, manager's office - (1) sofa, (3) desk chairs, manager's office - (1) sofa, (3) desk chairs, (2) desks (2) desks (2) desks (2) desks lower level - (1) sofa, (1) loveseat lower level - (1) sofa, (1) loveseat lower level - (1) sofa, (1) loveseat lower level - (1) sofa, (1) loveseat upper level - (3) loveseats, (3) armchairs, upper level - (3) loveseats, (3) armchairs, upper level - (3) loveseats, (3) armchairs, upper level - (3) loveseats, (3) armchairs, (3) sofas, (1) entertainment center, (3) sofas, (1) entertainment center, (3) sofas, (1) entertainment center, (3) sofas, (1) entertainment center, (30) wood dining chairs, (2) coffee tables, (30) wood dining chairs, (2) coffee tables, (30) wood dining chairs, (2) coffee tables, (30) wood dining chairs, (2) coffee tables, (3) end tables, (5) dining tables, (2) chess tables (3) end tables, (5) dining tables, (2) chess tables (3) end tables, (5) dining tables, (2) chess tables (3) end tables, (5) dining tables, (2) chess tables (1) sofa table, (2) barstools (1) sofa table, (2) barstools (1) sofa table, (2) barstools (1) sofa table, (2) barstools
Sunday, August 11, 2013Page 30 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1406
Source of Information: Cost Database
Best Cost: $7,200$7,200$7,200$7,200
Worst Cost: $9,000$9,000$9,000$9,000
Location: Fitness roomFitness roomFitness roomFitness room
Quantity: See General NotesSee General NotesSee General NotesSee General Notes
Observations:
All equipment appears in good to fair condition at time of observation. Due to changes in fitness trends, we recommend reserving to replace strength equipment every 12 - 15 years to maintain a current and effective fitness center.
Life Expectancy: 15151515 Remaining Life: 8888
Estimate to replace all equipment
Higher estimate for more pieces
Strength Equipment - Replace
General Notes:
(1) Vision Fitness Multi-Station(1) Vision Fitness Multi-Station(1) Vision Fitness Multi-Station(1) Vision Fitness Multi-Station(1) Weider 200 dip/ab stand(1) Weider 200 dip/ab stand(1) Weider 200 dip/ab stand(1) Weider 200 dip/ab stand
Sunday, August 11, 2013Page 31 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1406
Source of Information: Cost Database
Best Cost: $15,500$15,500$15,500$15,500
Worst Cost: $20,500$20,500$20,500$20,500
Location: Fitness roomFitness roomFitness roomFitness room
Quantity: See General NotesSee General NotesSee General NotesSee General Notes
Observations:
Schedules for replacing cardio equipment depends heavily upon level of use. Due to the observed condition of the equipment we recommend replacing this equipment every 8 - 10 years. No signs of abuse or mistreatment were noted at time of observation.
Life Expectancy: 10101010 Remaining Life: 3333
Estimate to replace all equipment
Higher estimate for more pieces
Cardio Equipment - Replace
General Notes:
(1) Landice L7 treadmill - $6,000 - $7,000(1) Landice L7 treadmill - $6,000 - $7,000(1) Landice L7 treadmill - $6,000 - $7,000(1) Landice L7 treadmill - $6,000 - $7,000(1) Vision Fitness E3600 bike - $2,500 - $3,500(1) Vision Fitness E3600 bike - $2,500 - $3,500(1) Vision Fitness E3600 bike - $2,500 - $3,500(1) Vision Fitness E3600 bike - $2,500 - $3,500(1) Vision Fitness X6600 Elliptical $4,000 - $6,000(1) Vision Fitness X6600 Elliptical $4,000 - $6,000(1) Vision Fitness X6600 Elliptical $4,000 - $6,000(1) Vision Fitness X6600 Elliptical $4,000 - $6,000(1) Vision Fitness R2600 recumbent bike - (1) Vision Fitness R2600 recumbent bike - (1) Vision Fitness R2600 recumbent bike - (1) Vision Fitness R2600 recumbent bike - $3,000 - $4,000 $3,000 - $4,000 $3,000 - $4,000 $3,000 - $4,000
Sunday, August 11, 2013Page 32 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1407
Source of Information: Cost Database
Best Cost: $18,935$18,935$18,935$18,935
Worst Cost: $22,375$22,375$22,375$22,375
Location: Interior finishInterior finishInterior finishInterior finish
Quantity: Approx. 6,885 GSFApprox. 6,885 GSFApprox. 6,885 GSFApprox. 6,885 GSF
Observations:
Wallpaper was aged in appearance and many areas of damaged surface area were noted. Based on current condition, we recommend replacing wallpaper every 10 years to maintain appearance.
Life Expectancy: 10101010 Remaining Life: 0000
$2.75/GSF; Estimate to replace
$3.25/GSF; Higher estimate for better quality
Wallpaper - Replace
General Notes:
lower level - 1,170 GSFlower level - 1,170 GSFlower level - 1,170 GSFlower level - 1,170 GSFupper level - 2,755 GSFupper level - 2,755 GSFupper level - 2,755 GSFupper level - 2,755 GSFstairs/corridor to pool - 680 GSFstairs/corridor to pool - 680 GSFstairs/corridor to pool - 680 GSFstairs/corridor to pool - 680 GSFfitness room - 2,280 GSFfitness room - 2,280 GSFfitness room - 2,280 GSFfitness room - 2,280 GSF
Sunday, August 11, 2013Page 33 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1409
Source of Information: Cost Database
Best Cost: $3,000$3,000$3,000$3,000
Worst Cost: $4,500$4,500$4,500$4,500
Location: Pool areaPool areaPool areaPool area
Quantity: (1) sauna(1) sauna(1) sauna(1) sauna
Observations:
Sauna room appeared in good condition at time of observation with no noted or reported problems. In order to keep this room sanitary and appearing in good condition, we recommend reserving to refurbish every 12 - 15 years.
Life Expectancy: 15151515 Remaining Life: 5555
Allowance for major refurbishment of room
Higher allowance for more labor
Sauna Room - Refurbish
General Notes:
Sauna - Sauna - Sauna - Sauna - concrete - 90 GSF concrete - 90 GSF concrete - 90 GSF concrete - 90 GSF cedar - 330 GSF cedar - 330 GSF cedar - 330 GSF cedar - 330 GSF
Sunday, August 11, 2013Page 34 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1410
Source of Information: Cost Database
Best Cost: $2,400$2,400$2,400$2,400
Worst Cost: $2,800$2,800$2,800$2,800
Location: Pool areaPool areaPool areaPool area
Quantity: (1) heater(1) heater(1) heater(1) heater
Observations:
Sauna heater appeared in fair condition with signs of deterioration noted at time of observation. Expect a useful life of approximately 12 years assuming normal use and wear.
Life Expectancy: 12121212 Remaining Life: 2222
Estimate to replace heater
Higher estimate for better quality heater
Sauna Heater - Replace
General Notes:
Heater type - 1105-120Heater type - 1105-120Heater type - 1105-120Heater type - 1105-120 s/n: C 83/0011 s/n: C 83/0011 s/n: C 83/0011 s/n: C 83/0011
Sunday, August 11, 2013Page 35 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1413
Source of Information: Cost Database
Best Cost: $24,000$24,000$24,000$24,000
Worst Cost: $30,000$30,000$30,000$30,000
Location: Lower levelLower levelLower levelLower level
Quantity: (2) restrooms(2) restrooms(2) restrooms(2) restrooms
Observations:
Restrooms appeared in good to fair condition at time of observation with no overt signs of deterioration or abuse. Funding for painting and flooring are included with other line items in this report. This is for replacing fixtures and partitions only. Expect to update fixtures every 15 - 20 years depending on levels of maintenance and use.
Life Expectancy: 20202020 Remaining Life: 10101010
$12,000/restroom; Estimate to remodel
$15,000/restroom; Estimate for better quality
Restrooms - Remodel
General Notes:
Women's Restroom - Women's Restroom - Women's Restroom - Women's Restroom - (3) toilets, (1) fiberglass shower unit, (3) sinks, (3) toilets, (1) fiberglass shower unit, (3) sinks, (3) toilets, (1) fiberglass shower unit, (3) sinks, (3) toilets, (1) fiberglass shower unit, (3) sinks, (3) toilet partitions (3) toilet partitions (3) toilet partitions (3) toilet partitions
Men's restroom - Men's restroom - Men's restroom - Men's restroom - (2) toilets, (1) urinal, (1) fiberglass shower unit, (2) toilets, (1) urinal, (1) fiberglass shower unit, (2) toilets, (1) urinal, (1) fiberglass shower unit, (2) toilets, (1) urinal, (1) fiberglass shower unit, (3) sinks, (2) toilet partitions (3) sinks, (2) toilet partitions (3) sinks, (2) toilet partitions (3) sinks, (2) toilet partitions
Sunday, August 11, 2013Page 36 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1421
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Fitness roomFitness roomFitness roomFitness room
Quantity: (1) 36" TV(1) 36" TV(1) 36" TV(1) 36" TV
Observations:
This type of TV is available at local retailers for less than $1,000 and does not require any special installation or mounting beyond what is already installed in the fitness room. Replace this TV as needed using operating funds, no reserve funding necessary at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Televisions - Replace
General Notes:
36" VIZIO HDTV36" VIZIO HDTV36" VIZIO HDTV36" VIZIO HDTV
Sunday, August 11, 2013Page 37 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1429
Source of Information: Cost Database
Best Cost: $4,400$4,400$4,400$4,400
Worst Cost: $4,800$4,800$4,800$4,800
Location: Throughout clubhouse lower levelThroughout clubhouse lower levelThroughout clubhouse lower levelThroughout clubhouse lower level
Quantity: Approx. 1,600 GSFApprox. 1,600 GSFApprox. 1,600 GSFApprox. 1,600 GSF
Observations:
Overall, ceiling tiles appeared in good condition. It is typical for ceiling tiles to show signs of staining and discoloration after 6 - 8 years. There were only a few discolored tiles at time of observation. Although the association can replace individual tiles as an operating issue, we recommend reserving to completely replace every 10 - 15 years because manufacturers will "retire" styles of ceiling tiles and individual replacement will not match existing.
Life Expectancy: 15151515 Remaining Life: 5555
$2.75/GSF; Estimate to replace
$3.00/GSF; Higher estimate
Ceiling Tiles - Replace
General Notes:
lower level - 1,445 GSFlower level - 1,445 GSFlower level - 1,445 GSFlower level - 1,445 GSFstairs/corridor to pool - 155 GSFstairs/corridor to pool - 155 GSFstairs/corridor to pool - 155 GSFstairs/corridor to pool - 155 GSF
Sunday, August 11, 2013Page 38 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1430
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: ClubhouseClubhouseClubhouseClubhouse
Quantity: Approx. 95 LFApprox. 95 LFApprox. 95 LFApprox. 95 LF
Observations:
Due to the location of this rail being inside and the low quantity of wood rail, we do not recommend reserving to replace at this time. Include staining or painting of the rail with component #216. Any repairs that are needed as the railing ages can be performed as an operating issue.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Wood Handrail - Replace
General Notes:
stairs to upper level - 95 LFstairs to upper level - 95 LFstairs to upper level - 95 LFstairs to upper level - 95 LF
Sunday, August 11, 2013Page 39 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1430
Source of Information: Cost Database
Best Cost: $8,500$8,500$8,500$8,500
Worst Cost: $9,000$9,000$9,000$9,000
Location: Large ClubhouseLarge ClubhouseLarge ClubhouseLarge Clubhouse
Quantity: (1) court(1) court(1) court(1) court
Observations:
Court appears well worn, leading us to believe that racquetball is played often in this community. Therefore, we recommend reserving to refurbish the court every 6 - 8 years in order to maintain a proper playing surface in terms of the hardwood floors as well as the wall panels. It appeared, at time of observation, that there was an issue with an expansion joint in the floor where a 1/4" crack had developed.
Life Expectancy: 8888 Remaining Life: 0000
Allowance to refurbish racquetball court
Higher allowance for more refurb costs
Racquet Ball Court - Refurbish
General Notes:
court components - court components - court components - court components - hardwood flooring - 725 GSF hardwood flooring - 725 GSF hardwood flooring - 725 GSF hardwood flooring - 725 GSF walls/ceiling Formica (or similar) - 3,005 GSF walls/ceiling Formica (or similar) - 3,005 GSF walls/ceiling Formica (or similar) - 3,005 GSF walls/ceiling Formica (or similar) - 3,005 GSF
Sunday, August 11, 2013Page 40 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1501
Source of Information: Cost Database
Best Cost: $15,060$15,060$15,060$15,060
Worst Cost: $17,570$17,570$17,570$17,570
Location: Large ClubhouseLarge ClubhouseLarge ClubhouseLarge Clubhouse
Quantity: Approx. 502 GSYApprox. 502 GSYApprox. 502 GSYApprox. 502 GSY
Observations:
Carpet showed signs of traffic patterns, cuts, separating seams, and an overall poor appearance. The main issues were in the lower level game room where the carpet receives most of the traffic in the building. Expect to replace this carpet every 5 - 6 years depending on levels of use and quality of carpet used.
Life Expectancy: 6666 Remaining Life: 0000
$30/GSY; Estimate for average quality
$35/GSY; Higher estimate for better quality
Carpeting - Replace
General Notes:
manager's office - 24 GSYmanager's office - 24 GSYmanager's office - 24 GSYmanager's office - 24 GSYlower level - 170 GSYlower level - 170 GSYlower level - 170 GSYlower level - 170 GSYstairs to upper level - 17 GSYstairs to upper level - 17 GSYstairs to upper level - 17 GSYstairs to upper level - 17 GSYupper level - 184 GSYupper level - 184 GSYupper level - 184 GSYupper level - 184 GSYstairs/corridor to pool - 19 GSYstairs/corridor to pool - 19 GSYstairs/corridor to pool - 19 GSYstairs/corridor to pool - 19 GSYfitness room - 88 GSYfitness room - 88 GSYfitness room - 88 GSYfitness room - 88 GSY
Sunday, August 11, 2013Page 41 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1502
Source of Information: Cost Database
Best Cost: $10,950$10,950$10,950$10,950
Worst Cost: $13,150$13,150$13,150$13,150
Location: Upper level, Laundry roomUpper level, Laundry roomUpper level, Laundry roomUpper level, Laundry room
Quantity: Approx. 730 GSFApprox. 730 GSFApprox. 730 GSFApprox. 730 GSF
Observations:
At time of observation, cuts, discoloration and other problems were noted in the vinyl flooring. The typical useful life of vinyl flooring is between 8 - 10 years. The laundry room floor appeared in slightly better condition than the kitchen area of the clubhouse but due to the seams beginning to separate, we recommend replacing as a safety concern.
Life Expectancy: 10101010 Remaining Life: 0000
$15/GSF; Estimate to replace
$18/GSF; Higher estimate for better quality
Vinyl Flooring - Replace
General Notes:
Clubhouse upper level - 130 GSFClubhouse upper level - 130 GSFClubhouse upper level - 130 GSFClubhouse upper level - 130 GSFLaundry room - 600 GSFLaundry room - 600 GSFLaundry room - 600 GSFLaundry room - 600 GSF
Sunday, August 11, 2013Page 42 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1503
Source of Information: Cost Database
Best Cost: $33,400$33,400$33,400$33,400
Worst Cost: $39,000$39,000$39,000$39,000
Location: Throughout clubhouseThroughout clubhouseThroughout clubhouseThroughout clubhouse
Quantity: Approx. 1,855 GSFApprox. 1,855 GSFApprox. 1,855 GSFApprox. 1,855 GSF
Observations:
Tile appeared in good to fair condition at time of observation with no missing or broken tile noted. Although the life of the tile may outlast our recommended useful life, it is typical for communities to replace the tile based on decorative appearance every 12 - 15 years. Therefore, we recommend replacing tile every 15 years in order to maintain a current appearance.
Life Expectancy: 15151515 Remaining Life: 5555
$18/GSF: Estimate to replace
$21/GSF: Higher estimate for more labor
Ceramic Tile - Replace
General Notes:
women's restroom - 475 GSF (wall and floor)women's restroom - 475 GSF (wall and floor)women's restroom - 475 GSF (wall and floor)women's restroom - 475 GSF (wall and floor)men's restroom - 560 GSF (wall and floor)men's restroom - 560 GSF (wall and floor)men's restroom - 560 GSF (wall and floor)men's restroom - 560 GSF (wall and floor)pool area - 820 GSF (wall tile)pool area - 820 GSF (wall tile)pool area - 820 GSF (wall tile)pool area - 820 GSF (wall tile)
Sunday, August 11, 2013Page 43 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1601
Source of Information: Cost Database
Best Cost: $16,400$16,400$16,400$16,400
Worst Cost: $20,500$20,500$20,500$20,500
Location: Common areasCommon areasCommon areasCommon areas
Quantity: Approx. (82) fixturesApprox. (82) fixturesApprox. (82) fixturesApprox. (82) fixtures
Observations:
Light fixtures appeared in good condition at time of observation with no apparent damage noted. While it is possible to replace individual light fixtures as needed, we recommend replacing all fixtures at once for significant cost savings and in order to ensure a consistent appearance throughout the clubhouse.
Life Expectancy: 20202020 Remaining Life: 10101010
$200/fixture; Estimate to replace and install new
$250/fixture; Higher estimate
Interior - Replace
General Notes:
lower level - (4) ceilinglower level - (4) ceilinglower level - (4) ceilinglower level - (4) ceilingupper level - (7) pendant, (27) ceiling, (3) sconce,upper level - (7) pendant, (27) ceiling, (3) sconce,upper level - (7) pendant, (27) ceiling, (3) sconce,upper level - (7) pendant, (27) ceiling, (3) sconce, (4) ceiling fans (4) ceiling fans (4) ceiling fans (4) ceiling fansstairs/corridor to pool - (4) sconcestairs/corridor to pool - (4) sconcestairs/corridor to pool - (4) sconcestairs/corridor to pool - (4) sconcepool area - (14) sconce, (19) ceilingpool area - (14) sconce, (19) ceilingpool area - (14) sconce, (19) ceilingpool area - (14) sconce, (19) ceiling
Sunday, August 11, 2013Page 44 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1602
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Clubhouse exterior lightingClubhouse exterior lightingClubhouse exterior lightingClubhouse exterior lighting
Quantity: Approx. (11) fixturesApprox. (11) fixturesApprox. (11) fixturesApprox. (11) fixtures
Observations:
Lights are in good condition. Due to the minimal cost to replace these lights, Reserve funding is not appropriate. Repair and replace as necessary as an operating expense.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Exterior Wall Mount - Replace
General Notes:
Sunday, August 11, 2013Page 45 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest ClubhouseComponent Inventory for Guest Clubhouse
Comp #: 1608
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: ClubhousesClubhousesClubhousesClubhouses
Quantity: Approx.. (70) fixturesApprox.. (70) fixturesApprox.. (70) fixturesApprox.. (70) fixtures
Observations:
Due to these fixtures being standard equipment and the fact that they are kept in stock at local retailers, we recommend replacing as needed using operating funds. Frequently inspect the exit and emergency fixtures for proper function as a life safety issue. No reserve funding necessary at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Multi-Purpose Lighting - Replace
General Notes:
Large Clubhouse -Large Clubhouse -Large Clubhouse -Large Clubhouse - manager's office - (2) fluorescent manager's office - (2) fluorescent manager's office - (2) fluorescent manager's office - (2) fluorescent lower level - (22) cans, (2) exit, (2) emerg lower level - (22) cans, (2) exit, (2) emerg lower level - (22) cans, (2) exit, (2) emerg lower level - (22) cans, (2) exit, (2) emerg upper level - (1) exit, (3) emerg upper level - (1) exit, (3) emerg upper level - (1) exit, (3) emerg upper level - (1) exit, (3) emerg stairs/corridor to pool - (1) exit, (1) emerg stairs/corridor to pool - (1) exit, (1) emerg stairs/corridor to pool - (1) exit, (1) emerg stairs/corridor to pool - (1) exit, (1) emerg women's restroom - (3) fluorescent, (5) cans women's restroom - (3) fluorescent, (5) cans women's restroom - (3) fluorescent, (5) cans women's restroom - (3) fluorescent, (5) cans men's restroom - (7) cans men's restroom - (7) cans men's restroom - (7) cans men's restroom - (7) cans pool area - (3) exit, (3) emerg pool area - (3) exit, (3) emerg pool area - (3) exit, (3) emerg pool area - (3) exit, (3) emerg racquet ball court - (6) fluorescent racquet ball court - (6) fluorescent racquet ball court - (6) fluorescent racquet ball court - (6) fluorescent laundry room - (7) fluorescent, (1) emerg, (1) exit laundry room - (7) fluorescent, (1) emerg, (1) exit laundry room - (7) fluorescent, (1) emerg, (1) exit laundry room - (7) fluorescent, (1) emerg, (1) exit
Sunday, August 11, 2013Page 46 of 46
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 102
Source of Information: Cost Database
Best Cost: $4,000$4,000$4,000$4,000
Worst Cost: $4,500$4,500$4,500$4,500
Location: Clubhouse roofClubhouse roofClubhouse roofClubhouse roof
Quantity: Approx. 5 squaresApprox. 5 squaresApprox. 5 squaresApprox. 5 squares
Observations:
Direct access was not available to all areas at time of initial field observation, and follow up field work took place during winter months. No reports of problems with the roof were noted. The average life expectancy for this type of roof ranges between 12 - 15 years in this climate. Remaining life is based on the age of this building.
Life Expectancy: 18181818 Remaining Life: 6666
$800/square; Estimate to replace
Higher estimate for more labor
Mod. Bitumen Flat Roof - Replace
General Notes:
Sunday, April 28, 2013Page 1 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 105
Source of Information: Cost Database
Best Cost: $22,425$22,425$22,425$22,425
Worst Cost: $25,350$25,350$25,350$25,350
Location: Clubhouse roofClubhouse roofClubhouse roofClubhouse roof
Quantity: Approx.. 39 squaresApprox.. 39 squaresApprox.. 39 squaresApprox.. 39 squares
Observations:
Observed chips and loss of granule material noted at time of field work. Even though this roof may be rated as a 30 year roof, a life expectancy of 18 - 22 years is expected in this environment. Due to the potentially harsh environment, we typically see associations replacing roofs sooner than the manufacturer's suggested useful life.
Life Expectancy: 22222222 Remaining Life: 4444
$575/square; Estimate to remove and replace
$650/square; Higher estimate for more labor costs
Comp Shingle Roof - Replace
General Notes:
Sunday, April 28, 2013Page 2 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 120
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Clubhouse roof perimeterClubhouse roof perimeterClubhouse roof perimeterClubhouse roof perimeter
Quantity: Approx. 165 LFApprox. 165 LFApprox. 165 LFApprox. 165 LF
Observations:
Area is too small for separate Reserve designation. Replace as needed with general operating funds.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Gutters/Downspouts/Heat Tape - Replace
General Notes:
Sunday, April 28, 2013Page 3 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 204
Source of Information: Cost Database
Best Cost: $3,000$3,000$3,000$3,000
Worst Cost: $3,600$3,600$3,600$3,600
Location: Siding, trim, etc.Siding, trim, etc.Siding, trim, etc.Siding, trim, etc.
Quantity: Approx. 4,260 GSFApprox. 4,260 GSFApprox. 4,260 GSFApprox. 4,260 GSF
Observations:
Painted surfaces are thin and in need of repainting soon. In this climate, we recommend painting every 4 - 5 years to protect the wood from pre-mature deterioration and splitting. Based on observed conditions and age of building, we recommend painting this building as soon as possible.
Life Expectancy: 5555 Remaining Life: 0000
Estimate to repaint
Higher estimate for more prep work
Building Ext Surfaces - Repaint
General Notes:
Sunday, April 28, 2013Page 4 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 216
Source of Information: Cost Database
Best Cost: $4,825$4,825$4,825$4,825
Worst Cost: $5,550$5,550$5,550$5,550
Location: Throughout clubhouseThroughout clubhouseThroughout clubhouseThroughout clubhouse
Quantity: Approx. 4,815 GSFApprox. 4,815 GSFApprox. 4,815 GSFApprox. 4,815 GSF
Observations:
Owner's clubhouse was very dated in appearance at time of observation partly due to type of finish, but also because the paint appeared dull, discolored and faded. We recommend reserving to repaint this year in order to restore appearance. Expect to repaint every 8 - 10 years in order to maintain an appropriate appearance in the clubhouse.
Life Expectancy: 10101010 Remaining Life: 0000
$1.00/GSF; Estimate to repaint
$1.15/GSF; Higher estimate
Interior Surfaces - Repaint
General Notes:
clubhouse interior - clubhouse interior - clubhouse interior - clubhouse interior - main room - 1,385 GSF main room - 1,385 GSF main room - 1,385 GSF main room - 1,385 GSF pool/spa area - 2,670 GSF pool/spa area - 2,670 GSF pool/spa area - 2,670 GSF pool/spa area - 2,670 GSF restrooms - 760 GSF restrooms - 760 GSF restrooms - 760 GSF restrooms - 760 GSF
Sunday, April 28, 2013Page 5 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 301
Source of Information: Cost Database
Best Cost: $5,500$5,500$5,500$5,500
Worst Cost: $6,250$6,250$6,250$6,250
Location: Clubhouse exterior claddingClubhouse exterior claddingClubhouse exterior claddingClubhouse exterior cladding
Quantity: Approx. 4,260 GSFApprox. 4,260 GSFApprox. 4,260 GSFApprox. 4,260 GSF
Observations:
Siding was in fair to poor condition with several signs of warped and split pieces of material noted. This type of siding has a life expectancy of 20 - 30 years, depending on the level of maintenance and exposure to elements. Based on observed conditions, we recommend performing some repairs prior to painting the surfaces as soon as possible.
Life Expectancy: 10101010 Remaining Life: 0000
Allowance for periodic repairs
Higher allowance for more repairs
Wood Siding - Replace
General Notes:
Sunday, April 28, 2013Page 6 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 503
Source of Information: Cost Database
Best Cost: $2,600$2,600$2,600$2,600
Worst Cost: $3,000$3,000$3,000$3,000
Location: Clubhouse exteriorClubhouse exteriorClubhouse exteriorClubhouse exterior
Quantity: Approx. (4) doorsApprox. (4) doorsApprox. (4) doorsApprox. (4) doors
Observations:
Doors appeared in very poor condition at time of observation. We recommend replacing all doors at the same time in order to maintain a proper and consistent appearance within the clubhouse. Under normal conditions and with proper maintenance, we expect these doors to have a useful life of approximately 25 years.
Life Expectancy: 25252525 Remaining Life: 0000
$650/door; Estimate to replace doors
$750/door; Higher estimate
Doors - Replace
General Notes:
Sunday, April 28, 2013Page 7 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 506
Source of Information: Cost Database
Best Cost: $10,400$10,400$10,400$10,400
Worst Cost: $12,000$12,000$12,000$12,000
Location: Throughout clubhouseThroughout clubhouseThroughout clubhouseThroughout clubhouse
Quantity: Approx. (16) openingsApprox. (16) openingsApprox. (16) openingsApprox. (16) openings
Observations:
Windows appear to be in good condition at time of observation with no apparent problems noted or reported. Due to these windows being vinyl, we expect that they have been replaced at some point within the last 10 years. Expect a useful life of approximately 25 years under normal conditions.
Life Expectancy: 25252525 Remaining Life: 15151515
$650/opening; Average estimate to replace
$750/window; Higher estimate for better quality
Windows - Replace
General Notes:
main room - (4) windowsmain room - (4) windowsmain room - (4) windowsmain room - (4) windowspool area - (12) windowspool area - (12) windowspool area - (12) windowspool area - (12) windows
Sunday, April 28, 2013Page 8 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 607
Source of Information: Cost Database
Best Cost: $10,000$10,000$10,000$10,000
Worst Cost: $12,500$12,500$12,500$12,500
Location: Spa deck, exterior deckingSpa deck, exterior deckingSpa deck, exterior deckingSpa deck, exterior decking
Quantity: See General NotesSee General NotesSee General NotesSee General Notes
Observations:
In general, decks are in fair condition with typical signs of weathering and deterioration. We recommend replacing all decks at the same time for best cost estimate. Based on observed conditions, we anticipate replacement will need to occur within the next 7 - 10 years.
Life Expectancy: 25252525 Remaining Life: 10101010
Estimate to replace all decks
Higher estimate for upgraded material
Wood Deck - Replace
General Notes:
Interior - Interior - Interior - Interior - spa deck - 110 GSF spa deck - 110 GSF spa deck - 110 GSF spa deck - 110 GSF lattice work - 120 GSF lattice work - 120 GSF lattice work - 120 GSF lattice work - 120 GSFExterior - Exterior - Exterior - Exterior - Entry area - deck - 310 GSF, rail - 40 LF Entry area - deck - 310 GSF, rail - 40 LF Entry area - deck - 310 GSF, rail - 40 LF Entry area - deck - 310 GSF, rail - 40 LF
Sunday, April 28, 2013Page 9 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 608
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Pool areaPool areaPool areaPool area
Quantity: Approx. 605 GSFApprox. 605 GSFApprox. 605 GSFApprox. 605 GSF
Observations:
We recommend sealing the tile and grout as needed using operating funds in order to protect the material from the harsh chemicals in the pool. There were no signs of cracking or other issues at time of observation. The tile should have an indefinite useful life and therefore, reserve funding is not appropriate at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Pool Deck - Replace
General Notes:
Sunday, April 28, 2013Page 10 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 702
Source of Information: Cost Database
Best Cost: $18,000$18,000$18,000$18,000
Worst Cost: $22,000$22,000$22,000$22,000
Location: Mechanical roomMechanical roomMechanical roomMechanical room
Quantity: (1) boiler(1) boiler(1) boiler(1) boiler
Observations:
Boiler was working as expected during observation with no apparent problems noted or reported. Expect a useful life of approximately 20 years assuming proper maintenance is performed and based on the quality of the water running through the system.
Life Expectancy: 20202020 Remaining Life: 7777
Estimate to replace boiler
Higher estimate for more efficient unit
Boilers - Replace
General Notes:
Boiler - Boiler - Boiler - Boiler - Teledyne Laars Teledyne Laars Teledyne Laars Teledyne Laars m/n: HH0500IN09K1ACE m/n: HH0500IN09K1ACE m/n: HH0500IN09K1ACE m/n: HH0500IN09K1ACE s/n: C97A00389 s/n: C97A00389 s/n: C97A00389 s/n: C97A00389500,000 BTU in500,000 BTU in500,000 BTU in500,000 BTU in
Sunday, April 28, 2013Page 11 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 703
Source of Information: Cost Database
Best Cost: $3,200$3,200$3,200$3,200
Worst Cost: $3,500$3,500$3,500$3,500
Location: Mechanical roomMechanical roomMechanical roomMechanical room
Quantity: (1) tank(1) tank(1) tank(1) tank
Observations:
This storage tank appears to have been recently installed with on problems noted or reported. We recommend reserving to replace the storage tank every 15 - 16 years in order to maintain function and to ensure the best possible efficiency within the water heating system.
Life Expectancy: 16161616 Remaining Life: 12121212
$3200/tank; Est for 120 Gallon storage tank
$3500/tank; Higher estimate for better quality
Hot Water Storage Tank - Replace
General Notes:
NOTE: Hot water storage tank did not have a legible NOTE: Hot water storage tank did not have a legible NOTE: Hot water storage tank did not have a legible NOTE: Hot water storage tank did not have a legible badge/label.badge/label.badge/label.badge/label.
Sunday, April 28, 2013Page 12 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 717
Source of Information: Cost Database
Best Cost: $1,200$1,200$1,200$1,200
Worst Cost: $1,500$1,500$1,500$1,500
Location: Pool areaPool areaPool areaPool area
Quantity: (1) nat gas heater(1) nat gas heater(1) nat gas heater(1) nat gas heater
Observations:
The heater was not functioning at time of observation due to favorable weather conditions, however the unit appears very old and in need to updating in order to add efficiency to the system which will result in a net savings for heating the pool area. After replacing the current heater, do not expect a similar useful life for the new heater as they are not meant to last as long as they once did. Replace heater approximately every 15 years.
Life Expectancy: 15151515 Remaining Life: 0000
$1200/heater; Estimate to replace
$1500/heater; Higher estimate
Suspended Heaters - Replace
General Notes:
Sunday, April 28, 2013Page 13 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 721
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Mechanical roomMechanical roomMechanical roomMechanical room
Quantity: (2) expansion tanks(2) expansion tanks(2) expansion tanks(2) expansion tanks
Observations:
Due to the unpredictable nature of these tanks, it is very difficult to assign a useful life. Therefore, we recommend planning to replace these expansion tanks as needed using operating funds.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Expansion Tanks - Replace
General Notes:
Sunday, April 28, 2013Page 14 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 901
Source of Information: Cost Database
Best Cost: $2,000$2,000$2,000$2,000
Worst Cost: $2,500$2,500$2,500$2,500
Location: Main room wall cabinetMain room wall cabinetMain room wall cabinetMain room wall cabinet
Quantity: (2) fire panels(2) fire panels(2) fire panels(2) fire panels
Observations:
No problems noted or reported with panel at the time of observation. Perform regular, professional inspections and testing to panel and system and expect to completely replace panels approximately every 20 to 25 years.
Life Expectancy: 25252525 Remaining Life: 8888
Estimate to replace
Higher estimate for additional parts
Fire Protection System - Replace
General Notes:
(1) Silent Knight - m/n: 5107(1) Silent Knight - m/n: 5107(1) Silent Knight - m/n: 5107(1) Silent Knight - m/n: 5107(1) Thorn Fire Quest 100(1) Thorn Fire Quest 100(1) Thorn Fire Quest 100(1) Thorn Fire Quest 100
Sunday, April 28, 2013Page 15 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1001
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Manager's unitManager's unitManager's unitManager's unit
Quantity: Approx. 55 LFApprox. 55 LFApprox. 55 LFApprox. 55 LF
Observations:
No unusual conditions observed at time of site visit. It appears that repairs are conducted on an as needed basis by on site maintenance staff. Therefore, at this time, separate Reserve funding is not required for this component.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Wood Fencing - Replace
General Notes:
Sunday, April 28, 2013Page 16 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1101
Source of Information: Cost Database
Best Cost: $9,500$9,500$9,500$9,500
Worst Cost: $10,500$10,500$10,500$10,500
Location: PoolPoolPoolPool
Quantity: (1) 14x34 pool(1) 14x34 pool(1) 14x34 pool(1) 14x34 pool
Observations:
Pool was covered and the cover reel was broken at time of observation so we were unable to observe the entire pool surface. However, the areas we were able to observe appeared in fair to poor condition with discoloration and missing "finish" noted. It is recommended by professionals that fiberglass pools be resurfaced every 8 - 9 years in this type of setting.
Life Expectancy: 9999 Remaining Life: 1111
Estimate to resurface pool
Higher estimate for more labor
Pool - Resurface
General Notes:
Sunday, April 28, 2013Page 17 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1102
Source of Information: Cost Database
Best Cost: $15,000$15,000$15,000$15,000
Worst Cost: $18,000$18,000$18,000$18,000
Location: Pool areaPool areaPool areaPool area
Quantity: (1) 11x8 spa(1) 11x8 spa(1) 11x8 spa(1) 11x8 spa
Observations:
Spa appeared in fair condition at time of observation. This spa is used year-round and therefore receives heavy amounts of use and the high temperatures and increased concentration of chemicals will likely shorten the life of the surface. Therefore, expect to replace this spa every 12 - 15 years.
Life Expectancy: 15151515 Remaining Life: 4444
Estimate to replace spa shell
Higher estimate for better quality
Spa - Replace
General Notes:
Sunday, April 28, 2013Page 18 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1108
Source of Information: Cost Database
Best Cost: $1,800$1,800$1,800$1,800
Worst Cost: $2,200$2,200$2,200$2,200
Location: Mechanical roomMechanical roomMechanical roomMechanical room
Quantity: (1) filter(1) filter(1) filter(1) filter
Observations:
Pool filter showed no signs of leaks or other problems at time of observation. Due to the ability to replace gaskets and seals without replacing the entire unit, we expect this filter to have a very long useful life if properly maintained. Expect to replace every 20 - 25 years.
Life Expectancy: 25252525 Remaining Life: 10101010
$1800/filter; Estimate to replace
$2200/filter; Higher estimate
Pool Filter - Replace
General Notes:
(1) STA Rite System 3 filter(1) STA Rite System 3 filter(1) STA Rite System 3 filter(1) STA Rite System 3 filter
Sunday, April 28, 2013Page 19 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1109
Source of Information: Cost Database
Best Cost: $1,200$1,200$1,200$1,200
Worst Cost: $1,500$1,500$1,500$1,500
Location: Mechanical roomMechanical roomMechanical roomMechanical room
Quantity: (1) filter(1) filter(1) filter(1) filter
Observations:
Pool filter showed no signs of leaks or other problems at time of observation. Due to the ability to replace gaskets and seals without replacing the entire unit, we expect this filter to have a very long useful life if properly maintained. Expect to replace every 20 - 25 years.
Life Expectancy: 25252525 Remaining Life: 5555
$1200/filter; Estimate to replace
$1500/filter; Higher estimate
Spa Filter - Replace
General Notes:
(1) sand media filter(1) sand media filter(1) sand media filter(1) sand media filter
Sunday, April 28, 2013Page 20 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1121
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Pool areaPool areaPool areaPool area
Quantity: Approx. (3) piecesApprox. (3) piecesApprox. (3) piecesApprox. (3) pieces
Observations:
Due to low quantity of furniture and the limited space around the pool area we recommend replacing furniture as needed using operating funds. No reserve funding necessary at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Pool Furniture - Replace
General Notes:
Pool area - Pool area - Pool area - Pool area - (3) arm chairs (3) arm chairs (3) arm chairs (3) arm chairs
Sunday, April 28, 2013Page 21 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1126
Source of Information: Cost Database
Best Cost: $4,500$4,500$4,500$4,500
Worst Cost: $6,000$6,000$6,000$6,000
Location: Pool mechanical roomPool mechanical roomPool mechanical roomPool mechanical room
Quantity: ExtensiveExtensiveExtensiveExtensive
Observations:
At time of observation all equipment was functioning as expected with no reported or noted problems. Expect to replace various pieces of equipment every 5 - 10 years to stay current in terms of jurisdictional code, efficiency and "green" technology.
Life Expectancy: 7777 Remaining Life: 4444
Allowance to replace needed equipment
Higher allowance for more needed equipment
Misc. Pool Equipment - Replace
General Notes:
Misc. pool equipment - Misc. pool equipment - Misc. pool equipment - Misc. pool equipment - (2) tab feeders (2) tab feeders (2) tab feeders (2) tab feedersPumps - Pumps - Pumps - Pumps - pool - pool - pool - pool - (1) Whisper-Flo (1) Whisper-Flo (1) Whisper-Flo (1) Whisper-Flo spa - spa - spa - spa - (2) Waterway pumps (2) Waterway pumps (2) Waterway pumps (2) Waterway pumps (1) Whisper-Flo pump (1) Whisper-Flo pump (1) Whisper-Flo pump (1) Whisper-Flo pump
Sunday, April 28, 2013Page 22 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1405
Source of Information: Cost Database
Best Cost: $8,000$8,000$8,000$8,000
Worst Cost: $10,000$10,000$10,000$10,000
Location: Main roomMain roomMain roomMain room
Quantity: Approx. (15) piecesApprox. (15) piecesApprox. (15) piecesApprox. (15) pieces
Observations:
Furniture was very dated and in need of replacement as soon as possible in order to restore appearance and to solicit higher levels of use. The more the clubhouse is used by residents, the more potential for increased property values in the community. Therefore, we recommend replacing furnishings every 5 - 6 years in order to ensure a proper appearance and a sanitary and comfortable environment.
Life Expectancy: 6666 Remaining Life: 0000
Estimate to replace furniture
Higher estimate for better quality
Furnishings - Replace
General Notes:
Furnishings - Furnishings - Furnishings - Furnishings - (2) arm chairs, (2) loveseats, (1) coffee tables, (2) arm chairs, (2) loveseats, (1) coffee tables, (2) arm chairs, (2) loveseats, (1) coffee tables, (2) arm chairs, (2) loveseats, (1) coffee tables, (2) end tables, (1) dining table, (4) dining chairs, (2) end tables, (1) dining table, (4) dining chairs, (2) end tables, (1) dining table, (4) dining chairs, (2) end tables, (1) dining table, (4) dining chairs, (1) sofa table, (2) chairs (1) sofa table, (2) chairs (1) sofa table, (2) chairs (1) sofa table, (2) chairs
Sunday, April 28, 2013Page 23 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1409
Source of Information: Cost Database
Best Cost: $4,000$4,000$4,000$4,000
Worst Cost: $4,500$4,500$4,500$4,500
Location: Pool areaPool areaPool areaPool area
Quantity: (1) sauna(1) sauna(1) sauna(1) sauna
Observations:
Sauna in this clubhouse has a wood floor as well as wood walls and ceiling. Therefore, expect a higher cost to refurbish than the sauna in the large clubhouse. The wood appeared in fair condition at time of observation with no overt problems, but the room had a damp odor even with the heater turned off. Therefore, we recommend reserving to refurbish within the next 1 - 2 years to restore comfort and a sanitary atmosphere.
Life Expectancy: 15151515 Remaining Life: 2222
Estimate to refurbish sauna room
Higher estimate for more labor
Sauna Room - Refurbish
General Notes:
Sauna - Sauna - Sauna - Sauna - cedar - 265 GSF cedar - 265 GSF cedar - 265 GSF cedar - 265 GSF
Sunday, April 28, 2013Page 24 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1410
Source of Information: Cost Database
Best Cost: $2,400$2,400$2,400$2,400
Worst Cost: $2,800$2,800$2,800$2,800
Location: Pool areaPool areaPool areaPool area
Quantity: (1) heater(1) heater(1) heater(1) heater
Observations:
Sauna heater appeared in fair condition with signs of deterioration noted at time of observation. Expect a useful life of approximately 12 years assuming normal use and wear.
Life Expectancy: 12121212 Remaining Life: 0000
Estimate to replace heater
Higher estimate for better quality heater
Sauna Heater - Replace
General Notes:
NOTE: Owner's sauna heater did not have an identification NOTE: Owner's sauna heater did not have an identification NOTE: Owner's sauna heater did not have an identification NOTE: Owner's sauna heater did not have an identification label/badge.label/badge.label/badge.label/badge.
Sunday, April 28, 2013Page 25 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1413
Source of Information: Cost Database
Best Cost: $18,000$18,000$18,000$18,000
Worst Cost: $20,000$20,000$20,000$20,000
Location: Owner's ClubhouseOwner's ClubhouseOwner's ClubhouseOwner's Clubhouse
Quantity: (2) restrooms(2) restrooms(2) restrooms(2) restrooms
Observations:
Restrooms were finished in a way that present a rustic appearance, however, due to the appearance of the cabinetry and the toilet partitions, we recommend a complete remodel of the space within the next 3 - 5 years to restore appearance. The decision of when to remodel and how much to spend is ultimately up to the board of directors because this is considered an aesthetic issue.
Life Expectancy: 20202020 Remaining Life: 5555
$9,000/restroom; Estimate to remodel
$10,000/restroom: Higher estimate for better qual.
Restroom - Remodel
General Notes:
Restrooms (mirrored) - Restrooms (mirrored) - Restrooms (mirrored) - Restrooms (mirrored) - Men's - Men's - Men's - Men's - (1) sink, (1) toilet, (1) shower, fiberglass (1) sink, (1) toilet, (1) shower, fiberglass (1) sink, (1) toilet, (1) shower, fiberglass (1) sink, (1) toilet, (1) shower, fiberglass Women's - Women's - Women's - Women's - (1) sink, (1) toilet, (1) shower, fiberglass (1) sink, (1) toilet, (1) shower, fiberglass (1) sink, (1) toilet, (1) shower, fiberglass (1) sink, (1) toilet, (1) shower, fiberglass
Sunday, April 28, 2013Page 26 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1501
Source of Information: Cost Database
Best Cost: $1,500$1,500$1,500$1,500
Worst Cost: $1,700$1,700$1,700$1,700
Location: Main roomMain roomMain roomMain room
Quantity: Approx. 48 GSYApprox. 48 GSYApprox. 48 GSYApprox. 48 GSY
Observations:
At time of observation, carpet appeared in good to fair condition. Carpet style appeared dated, but the overall condition was good. Expect to replace the carpet in this clubhouse on a slightly longer cycle than the large clubhouse due to the lower amount of foot traffic. We recommend planning for replacement every 8 - 10 years.
Life Expectancy: 10101010 Remaining Life: 3333
Estimate to replace carpet
Higher estimate for more labor/better quality
Carpeting - Replace
General Notes:
Sunday, April 28, 2013Page 27 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1503
Source of Information: Cost Database
Best Cost: $4,680$4,680$4,680$4,680
Worst Cost: $5,850$5,850$5,850$5,850
Location: Main entranceMain entranceMain entranceMain entrance
Quantity: Approx. 390 GSFApprox. 390 GSFApprox. 390 GSFApprox. 390 GSF
Observations:
Tile was aged in appearance at the main entrance, but in good condition with no broken tiles or apparent grout issues. The tile in the restrooms and pool area was slightly newer but more prone to damage due to the larger tile. Therefore, we believe the association should plan on replacing all tile at the same time in order to present a consistent appearance and to ensure proper function and safe walking surface. Expect to replace tile every 18 - 20 years.
Life Expectancy: 20202020 Remaining Life: 10101010
$12/GSF: Estimate to replace
$15/GSF: Higher estimate for more labor
Tile - Replace
General Notes:
Main entrance - 180 GSFMain entrance - 180 GSFMain entrance - 180 GSFMain entrance - 180 GSFRestrooms - 210 GSFRestrooms - 210 GSFRestrooms - 210 GSFRestrooms - 210 GSF
Sunday, April 28, 2013Page 28 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1601
Source of Information: Cost Database
Best Cost: $2,600$2,600$2,600$2,600
Worst Cost: $3,250$3,250$3,250$3,250
Location: Owner's clubhouseOwner's clubhouseOwner's clubhouseOwner's clubhouse
Quantity: Approx. (13) FixturesApprox. (13) FixturesApprox. (13) FixturesApprox. (13) Fixtures
Observations:
Decorative fixtures in this clubhouse were very dated in appearance and should be replaced as soon as possible to update the décor. Expect to replace interior fixtures every 20 years to maintain current decorative trends and to ensure proper function and "green" technology.
Life Expectancy: 20202020 Remaining Life: 0000
$200; Estimate to replace and install new
$250/fixture; Higher estimate
Interior - Replace
General Notes:
Main Room - Main Room - Main Room - Main Room - (8) track lights (8) track lights (8) track lights (8) track lights (1) wall light (1) wall light (1) wall light (1) wall lightRestrooms - Restrooms - Restrooms - Restrooms - (4) ceiling lights (4) ceiling lights (4) ceiling lights (4) ceiling lights
Sunday, April 28, 2013Page 29 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1602
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: Exterior lightingExterior lightingExterior lightingExterior lighting
Quantity: Approx. (4) fixturesApprox. (4) fixturesApprox. (4) fixturesApprox. (4) fixtures
Observations:
Due to the low quantity of fixtures, we recommend replacing as needed using operating funds. No reserve funding necessary at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Exterior Wall Mount - Replace
General Notes:
Sunday, April 28, 2013Page 30 of 31
Client Reference #Client Reference #Client Reference #Client Reference # 8508850885088508Component Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's ClubhouseComponent Inventory for Owner's Clubhouse
Comp #: 1608
Source of Information:
Best Cost: $0$0$0$0
Worst Cost: $0$0$0$0
Location: ClubhousesClubhousesClubhousesClubhouses
Quantity: Appox. (9) fixturesAppox. (9) fixturesAppox. (9) fixturesAppox. (9) fixtures
Observations:
Due to these fixtures being standard equipment and the fact that they are kept in stock at local retailers, we recommend replacing as needed using operating funds. Frequently inspect the exit and emergency fixtures for proper function as a life safety issue. No reserve funding necessary at this time.
Life Expectancy: N/AN/AN/AN/A Remaining Life:
Multi-Purpose Lighting - Replace
General Notes:
main room - (3) exit, (1) emergmain room - (3) exit, (1) emergmain room - (3) exit, (1) emergmain room - (3) exit, (1) emergpool area - (3) spot, (2) exitpool area - (3) spot, (2) exitpool area - (3) spot, (2) exitpool area - (3) spot, (2) exit
Sunday, April 28, 2013Page 31 of 31
Funding Summary For Treehouse Condominiums
Beginning Assumptions (from 2012 budget)Financial Information Source Research With Client# of units 249Fiscal Year End December 31, 2013Budgeted Monthly Dues $100,312Budgeted Monthly Reserve Allocation $17,575Projected Starting Reserve Balance $1,041,157Ideal Starting Reserve Balance $1,947,613
Economic Factors (For 2013)Past 20 year Average Inflation Rate 4.50%Past 20 year Average Interest Rate 1.00%
Current Reserve StatusCurrent Balance as a % of Ideal Balance 53%
RecommendationsMonthly Reserve Allocation (rest of 2013) $17,575
Average Per Unit $70.58Monthly Reserve Allocation (starting 2014) $28,800
Average Per Unit $115 66
1
Average Per Unit $115.66Minimum Monthly Reserve Allocation (starting 2014) $24,500
Average Per Unit $98.39Nominal Annual Increases 4.50%Special Assessment $0
Average Per Unit $0
Changes From Prior 2013 to 2014Increase/Decrease to Reserve Allocation $11,225
as Percentage 64%Average per unit $45.08
1
Percent Funded Graph For Treehouse Condominiums
80%
100%
120%
ndin
g
Percent FundedRecommended
Current
Minimum
2
0%
20%
40%
60%
80%
100%
120%
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
2041
2043
% L
evel
of F
undi
ng
Year
Percent FundedRecommended
Current
Minimum
2
Component Inventory for Common Area Grounds
Category Asset # Asset Name UL RUL Best Cost Worst Cost
Drive Materials 401 Asphalt - Overlay (A) 24 5 $138,100 $159,000
401 Asphalt - Overlay (B) 24 9 $138,100 $159,000
402 Asphalt - Seal Coat/crack fill 4 0 $26,800 $33,500
Decking 607 Wood Paths - Replace N/A $0 $0
610 Steel Stairs/Landings - Replace N/A $0 $0
611 Slip Resistant Mats - Replace 4 1 $4,250 $5,000
622 Covered Stairway - Replace N/A $0 $0
Prop. Identification 801 Identification Sign - Replace 20 8 $4,500 $5,750
Fencing/Walls 1003 Chain Link Fencing - Replace 35 5 $12,600 $14,400
Courts 1201 Tennis Court Asphalt - Replace 35 0 $57,500 $65,000
1202 Tennis Court - Recoat/Paint 7 0 $6,000 $6,750
Recreation Equip. 1301 Play Equipment - Replace 17 15 $39,000 $46,000
1306 Park Furnishings - Replace 5 2 $2,500 $3,000
1311 Pet Waste Stations - Replace N/A $0 $0
Interiors 1423 Manager's Units - Remodel 4 0 $5,500 $6,250
Light Fixtures 1604 Pole Lights - Replace 28 5 $5,950 $7,000
3
Component Inventory for Buildings A - I
Category Asset # Asset Name UL RUL Best Cost Worst Cost
Roofing 105 Modified Bitumen - Replace (1) 20 6 $220,500 $249,900
105 Modified Bitumen - Replace (3) 20 13 $220,500 $249,900
105 Modified Bitumen - Replace (2) 20 10 $220,500 $249,900
123 Skylights - Replace (1) 20 6 $12,000 $15,000
123 Skylights - Replace (3) 20 13 $12,000 $15,000
123 Skylights - Replace (2) 20 10 $12,000 $15,000
Painted Surfaces 204 Building Ext Surfaces - Repaint 5 3 $130,500 $153,000
Siding Materials 301 Wood Siding - Major Repairs 5 3 $45,000 $54,000
Property Access 501 Doors - Partial Replacement 8 2 $20,250 $22,300
506 Unit Windows - Replace N/A $0 $0
Decking 606 Deck Railings - Replace N/A $0 $0
607 Wood Deck - Major Repairs 10 3 $12,000 $15,000
Mechanical Equip. 701 Boilers - Major Repairs (Bldg C) 5 1 $8,000 $10,000
701 Boilers - Replace (Bldg H) 20 15 $36,000 $42,000
701 Boilers - Major Repairs 7 3 $140,000 $160,000
701 Boilers - Replace (G,I) 35 19 $164,400 $178,800
701 Boilers - Replace (A,B,D) 35 17 $246,600 $268,200
701 Boilers - Replace (E,F) 35 18 $164,400 $178,800
702 Boilers - Replace (Bldg C) 35 16 $85,000 $100,000
703 Hot Water Storage Tank - Replace (06) 12 5 $32,000 $36,000
703 Hot Water Storage Tank - Replace (09, 1 12 9 $24,000 $27,000
703 Hot Water Storage Tank - Replace (05) 12 4 $32,000 $36,000
703 Hot Water Storage Tank - Replace (07) 12 6 $48,000 $54,000
706 Tankless Water Heaters - Replace 30 6 $49,500 $56,250
715 Pumps - Replace 3 1 $20,000 $25,000
721 Expansion Tanks - Replace 5 3 $15,000 $18,000
Security 901 Fire Protection System - Replace N/A $0 $0
Interiors 1424 Unit Building Interiors - Refurbish 5 1 $30,000 $36,000
Flooring 1506 Outdoor Carpet - Replace N/A $0 $0
Light Fixtures 1602 Wall Mounted Lights - Replace N/A $0 $0
4
Component Inventory for Buildings J - K
Category Asset # Asset Name UL RUL Best Cost Worst Cost
Roofing 105 Comp Shingle Roof - Replace 22 17 $42,000 $49,000
120 Gutters/Downspouts - Replace N/A $0 $0
121 Heat Tape - Replace N/A $0 $0
Painted Surfaces 204 Building Ext Surfaces - Reseal 5 0 $8,000 $10,000
Siding Materials 305 Wood Siding - Replace/Major Repairs 10 5 $8,000 $10,000
309 Stone/Rock Siding - Major Repairs N/A $0 $0
Property Access 501 Unit Doors - Replace N/A $0 $0
502 Garage Doors - Replace N/A $0 $0
Decking 601 Concrete Patios - Repair N/A $0 $0
606 Wood Deck - Replace 12 7 $15,300 $19,125
Fencing/Walls 1001 Wood/Iron Rails - Replace N/A $0 $0
1011 Retaining Wall - Replace 30 25 $14,500 $17,500
Light Fixtures 1602 Exterior Wall Mount - Replace 15 10 $3,000 $3,600
5
Component Inventory for Guest Clubhouse
Category Asset # Asset Name UL RUL Best Cost Worst Cost
Roofing 104 Flat Roof - Replace 17 7 $12,000 $13,125
105 Comp Shingle Roof - Replace 22 12 $47,500 $53,200
120 Gutters/Downspouts/Heat Tape - Replac N/A $0 $0
Painted Surfaces 204 Building Ext Surfaces - Repaint 5 0 $4,000 $4,750
216 Interior Surfaces - Repaint 10 0 $9,530 $10,960
Siding Materials 301 Wood Siding - Major Repairs 15 5 $12,000 $15,000
309 Stone/Rock Siding - Major Repairs N/A $0 $0
Property Access 503 Common Area Doors - Replace 25 15 $16,250 $18,750
506 Windows - Replace 30 20 $75,600 $89,600
Decking 607 Wood Stairs/Deck - Replace 20 10 $8,000 $10,000
608 Pool Deck - Replace N/A $0 $0
Mechanical Equip. 702 Boiler - Replace 25 15 $16,000 $19,000
703 Water Heater - Replace 15 5 $4,500 $5,500
707 Elevator - Rebuild/Upgrade 25 15 $50,000 $60,000
709 Elevator Cab - Remodel 15 5 $12,000 $15,000
715 Pumps - Replace N/A $0 $0
721 Expansion Tanks - Replace 10 2 $3,500 $4,500
Security 901 Fire Protection System - Replace 25 15 $3,500 $3,850
903 Video Surveillance System - Replace 12 2 $8,500 $10,000
Pool/Spa 1101 Pool w/Spa - Resurface 9 4 $10,500 $11,600
1102 Spa - Resurface 6 1 $5,000 $6,000
1105 Pool Heater - Replace 12 2 $3,000 $3,500
1106 Spa Heaters - Replace 12 2 $7,500 $8,400
1108 Pool Filter - Replace 20 10 $3,600 $4,500
1121 Pool Furniture - Replace N/A $0 $0
1126 Misc. Pool Equipment - Replace 7 2 $8,500 $10,000
Recreation Equip. 1309 Ping Pong Table - Replace N/A $0 $0
Interiors 1401 Laundry Room - Remodel 20 10 $15,000 $18,000
1403 Kitchen - Remodel 15 5 $12,000 $15,000
1405 Furnishings - Replace 6 0 $18,000 $20,000
1406 Strength Equipment - Replace 15 8 $7,200 $9,000
1406 Cardio Equipment - Replace 10 3 $15,500 $20,500
1407 Wallpaper - Replace 10 0 $18,935 $22,375
1409 Sauna Room - Refurbish 15 5 $3,000 $4,500
1410 Sauna Heater - Replace 12 2 $2,400 $2,800
1413 Restrooms - Remodel 20 10 $24,000 $30,000
1421 Televisions - Replace N/A $0 $0
1429 Ceiling Tiles - Replace 15 5 $4,400 $4,800
1430 Wood Handrail - Replace N/A $0 $0
1430 Racquet Ball Court - Refurbish 8 0 $8,500 $9,000
Flooring 1501 Carpeting - Replace 6 0 $15,060 $17,570
1502 Vinyl Flooring - Replace 10 0 $10,950 $13,150
1503 Ceramic Tile - Replace 15 5 $33,400 $39,000
Light Fixtures 1601 Interior - Replace 20 10 $16,400 $20,500
1602 Exterior Wall Mount - Replace N/A $0 $0
1608 Multi-Purpose Lighting - Replace N/A $0 $0
6
Component Inventory for Owner's Clubhouse
Category Asset # Asset Name UL RUL Best Cost Worst Cost
Roofing 102 Mod. Bitumen Flat Roof - Replace 18 6 $4,000 $4,500
105 Comp Shingle Roof - Replace 22 4 $22,425 $25,350
120 Gutters/Downspouts/Heat Tape - Replac N/A $0 $0
Painted Surfaces 204 Building Ext Surfaces - Repaint 5 0 $3,000 $3,600
216 Interior Surfaces - Repaint 10 0 $4,825 $5,550
Siding Materials 301 Wood Siding - Replace 10 0 $5,500 $6,250
Property Access 503 Doors - Replace 25 0 $2,600 $3,000
506 Windows - Replace 25 15 $10,400 $12,000
Decking 607 Wood Deck - Replace 25 10 $10,000 $12,500
608 Pool Deck - Replace N/A $0 $0
Mechanical Equip. 702 Boilers - Replace 20 7 $18,000 $22,000
703 Hot Water Storage Tank - Replace 16 12 $3,200 $3,500
717 Suspended Heaters - Replace 15 0 $1,200 $1,500
721 Expansion Tanks - Replace N/A $0 $0
Security 901 Fire Protection System - Replace 25 8 $2,000 $2,500
Fencing/Walls 1001 Wood Fencing - Replace N/A $0 $0
Pool/Spa 1101 Pool - Resurface 9 1 $9,500 $10,500
1102 Spa - Replace 15 4 $15,000 $18,000
1108 Pool Filter - Replace 25 10 $1,800 $2,200
1109 Spa Filter - Replace 25 5 $1,200 $1,500
1121 Pool Furniture - Replace N/A $0 $0
1126 Misc. Pool Equipment - Replace 7 4 $4,500 $6,000
Interiors 1405 Furnishings - Replace 6 0 $8,000 $10,000
1409 Sauna Room - Refurbish 15 2 $4,000 $4,500
1410 Sauna Heater - Replace 12 0 $2,400 $2,800
1413 Restroom - Remodel 20 5 $18,000 $20,000
Flooring 1501 Carpeting - Replace 10 3 $1,500 $1,700
1503 Tile - Replace 20 10 $4,680 $5,850
Light Fixtures 1601 Interior - Replace 20 0 $2,600 $3,250
1602 Exterior Wall Mount - Replace N/A $0 $0
1608 Multi-Purpose Lighting - Replace N/A $0 $0
7
Significant Components For Treehouse CondominiumsSignificance:(Curr Cost/UL)
Asset ID Asset Name UL RUL As $ As %COMMON AREA GROUNDS
401 Asphalt - Overlay (A) 24 5 $148,550 $6,190 2.5420%401 Asphalt - Overlay (B) 24 9 $148,550 $6,190 2.5420%402 Asphalt - Seal Coat/crack fill 4 0 $30,150 $7,538 3.0956%611 Slip Resistant Mats - Replace 4 1 $4,625 $1,156 0.4749%801 Identification Sign - Replace 20 8 $5,125 $256 0.1052%1003 Chain Link Fencing - Replace 35 5 $13,500 $386 0.1584%1201 Tennis Court Asphalt - Replace 35 0 $61,250 $1,750 0.7187%1202 Tennis Court - Recoat/Paint 7 0 $6,375 $911 0.3740%1301 Play Equipment - Replace 17 15 $42,500 $2,500 1.0267%1306 Park Furnishings - Replace 5 2 $2,750 $550 0.2259%1423 Manager's Units - Remodel 4 0 $5,875 $1,469 0.6032%1604 Pole Lights - Replace 28 5 $6,475 $231 0.0950%
BUILDINGS A-I105 Modified Bitumen - Replace (1) 20 6 $235,200 $11,760 4.8297%105 Modified Bitumen - Replace (2) 20 10 $235,200 $11,760 4.8297%105 Modified Bitumen - Replace (3) 20 13 $235,200 $11,760 4.8297%123 Skylights - Replace (1) 20 6 $13,500 $675 0.2772%123 Skylights - Replace (2) 20 10 $13,500 $675 0.2772%123 Skylights - Replace (3) 20 13 $13,500 $675 0.2772%204 Building Ext Surfaces - Repaint 5 3 $141,750 $28,350 11.6431%301 Wood Siding - Major Repairs 5 3 $49,500 $9,900 4.0659%501 Doors - Partial Replacement 8 2 $21,275 $2,659 1.0922%607 Wood Deck - Major Repairs 10 3 $13,500 $1,350 0.5544%701 Boilers - Major Repairs 7 3 $150,000 $21,429 8.8006%701 Boilers - Major Repairs (Bldg C) 5 1 $9,000 $1,800 0.7392%701 Boilers - Replace (A,B,D) 35 17 $257,400 $7,354 3.0204%701 Boilers - Replace (Bldg H) 20 15 $39,000 $1,950 0.8009%701 Boilers - Replace (E,F) 35 18 $171,600 $4,903 2.0136%701 Boilers - Replace (G,I) 35 19 $171,600 $4,903 2.0136%702 Boilers - Replace (Bldg C) 35 16 $92,500 $2,643 1.0854%703 Hot Water Storage Tank - Replace (05) 12 4 $34,000 $2,833 1.1636%703 Hot Water Storage Tank - Replace (06) 12 5 $34,000 $2,833 1.1636%703 Hot Water Storage Tank - Replace (07) 12 6 $51,000 $4,250 1.7454%703 Hot Water Storage Tank - Replace (09, 10, 11) 12 9 $25,500 $2,125 0.8727%706 Tankless Water Heaters - Replace 30 6 $52,875 $1,763 0.7238%715 Pumps - Replace 3 1 $22,500 $7,500 3.0802%721 Expansion Tanks - Replace 5 3 $16,500 $3,300 1.3553%1424 Unit Building Interiors - Refurbish 5 1 $33,000 $6,600 2.7106%
BUILDINGS J & K105 Comp Shingle Roof - Replace 22 17 $45,500 $2,068 0.8494%204 Building Ext Surfaces - Reseal 5 0 $9,000 $1,800 0.7392%305 Wood Siding - Replace/Major Repairs 10 5 $9,000 $900 0.3696%606 Wood Deck - Replace 12 7 $17,213 $1,434 0.5891%1011 Retaining Wall - Replace 30 25 $16,000 $533 0.2190%1602 Exterior Wall Mount - Replace 15 10 $3,300 $220 0.0904%
GUEST CLUBHOUSE104 Flat Roof - Replace 17 7 $12,563 $739 0.3035%105 Comp Shingle Roof - Replace 22 12 $50,350 $2,289 0.9399%204 Building Ext Surfaces - Repaint 5 0 $4,375 $875 0.3594%216 Interior Surfaces - Repaint 10 0 $10,245 $1,025 0.4208%301 Wood Siding - Major Repairs 15 5 $13,500 $900 0.3696%503 Common Area Doors - Replace 25 15 $17,500 $700 0.2875%506 Windows - Replace 30 20 $82,600 $2,753 1.1308%607 Wood Stairs/Deck - Replace 20 10 $9,000 $450 0.1848%702 Boiler - Replace 25 15 $17,500 $700 0.2875%
Ave Curr Cost
8
Significant Components For Treehouse CondominiumsSignificance:(UL/Curr Cost)
Asset ID Asset Name UL RUL As $ As %703 Water Heater - Replace 15 5 $5,000 $333 0.1369%707 Elevator - Rebuild/Upgrade 25 15 $55,000 $2,200 0.9035%709 Elevator Cab - Remodel 15 5 $13,500 $900 0.3696%721 Expansion Tanks - Replace 10 2 $4,000 $400 0.1643%901 Fire Protection System - Replace 25 15 $3,675 $147 0.0604%903 Video Surveillance System - Replace 12 2 $9,250 $771 0.3166%1101 Pool w/Spa - Resurface 9 4 $11,050 $1,228 0.5042%1102 Spa - Resurface 6 1 $5,500 $917 0.3765%1105 Pool Heater - Replace 12 2 $3,250 $271 0.1112%1106 Spa Heaters - Replace 12 2 $7,950 $663 0.2721%1108 Pool Filter - Replace 20 10 $4,050 $203 0.0832%1126 Misc. Pool Equipment - Replace 7 2 $9,250 $1,321 0.5427%1401 Laundry Room - Remodel 20 10 $16,500 $825 0.3388%1403 Kitchen - Remodel 15 5 $13,500 $900 0.3696%1405 Furnishings - Replace 6 0 $19,000 $3,167 1.3005%1406 Cardio Equipment - Replace 10 3 $18,000 $1,800 0.7392%1406 Strength Equipment - Replace 15 8 $8,100 $540 0.2218%1407 Wallpaper - Replace 10 0 $20,655 $2,066 0.8483%1409 Sauna Room - Refurbish 15 5 $3,750 $250 0.1027%1410 Sauna Heater - Replace 12 2 $2,600 $217 0.0890%1413 Restrooms - Remodel 20 10 $27,000 $1,350 0.5544%1429 Ceiling Tiles - Replace 15 5 $4,600 $307 0.1259%1430 Racquet Ball Court - Refurbish 8 0 $8,750 $1,094 0.4492%1501 Carpeting - Replace 6 0 $16,315 $2,719 1.1167%1502 Vinyl Flooring - Replace 10 0 $12,050 $1,205 0.4949%1503 Ceramic Tile - Replace 15 5 $36,200 $2,413 0.9911%1601 Interior - Replace 20 10 $18,450 $923 0.3789%
OWNERS CLUBHOUSE102 Mod. Bitumen Flat Roof - Replace 18 6 $4,250 $236 0.0970%105 Comp Shingle Roof - Replace 22 4 $23,888 $1,086 0.4459%204 Building Ext Surfaces - Repaint 5 0 $3,300 $660 0.2711%216 Interior Surfaces - Repaint 10 0 $5,188 $519 0.2130%301 Wood Siding - Replace 10 0 $5,875 $588 0.2413%503 Doors - Replace 25 0 $2,800 $112 0.0460%506 Windows - Replace 25 15 $11,200 $448 0.1840%607 Wood Deck - Replace 25 10 $11,250 $450 0.1848%702 Boilers - Replace 20 7 $20,000 $1,000 0.4107%703 Hot Water Storage Tank - Replace 16 12 $3,350 $209 0.0860%717 Suspended Heaters - Replace 15 0 $1,350 $90 0.0370%901 Fire Protection System - Replace 25 8 $2,250 $90 0.0370%1101 Pool - Resurface 9 1 $10,000 $1,111 0.4563%1102 Spa - Replace 15 4 $16,500 $1,100 0.4518%1108 Pool Filter - Replace 25 10 $2,000 $80 0.0329%1109 Spa Filter - Replace 25 5 $1,350 $54 0.0222%1126 Misc. Pool Equipment - Replace 7 4 $5,250 $750 0.3080%1405 Furnishings - Replace 6 0 $9,000 $1,500 0.6160%1409 Sauna Room - Refurbish 15 2 $4,250 $283 0.1164%1410 Sauna Heater - Replace 12 0 $2,600 $217 0.0890%1413 Restroom - Remodel 20 5 $19,000 $950 0.3902%1501 Carpeting - Replace 10 3 $1,600 $160 0.0657%1503 Tile - Replace 20 10 $5,265 $263 0.1081%1601 Interior - Replace 20 0 $2,925 $146 0.0601%
Ave Curr Cost
9
Significant Components Graph For Treehouse Condominiums
11% 9%5%
70%
Significant Components
204 Building Ext Surfaces - Repaint
701 Boilers - Major Repairs
105 Modified Bitumen - Replace (1)
105 Modified Bitumen - Replace (1)
All Other
Asset ID Asset name UL RUL As %204 Building Ext Surfaces - Repaint 5 3 $141,750 $28,350 12%701 Boilers - Major Repairs 7 3 $150,000 $21,429 9%105 Modified Bitumen - Replace (1) 20 6 $235,200 $11,760 5%105 Modified Bitumen - Replace (1) 20 6 $235,200 $11,760 5%
All Other See Expanded Table For Breakdown $170,193 70%
Ave Curr. Cost
Significance: (Curr Cost /UL)
11% 9%5%
5%70%
Significant Components
204 Building Ext Surfaces - Repaint
701 Boilers - Major Repairs
105 Modified Bitumen - Replace (1)
105 Modified Bitumen - Replace (1)
All Other
10
Yearly Summary For Treehouse Condominiums
Year2013 $1,947,613 $1,041,157 53% $175,750 $10,151 $237,0782014 $2,041,958 $989,981 48% $345,600 $11,237 $88,4332015 $2,307,332 $1,258,385 55% $361,152 $14,102 $70,5182016 $2,615,335 $1,563,121 60% $377,404 $15,358 $446,0252017 $2,557,297 $1,509,858 59% $394,387 $16,255 $177,9392018 $2,789,864 $1,742,562 62% $412,134 $17,427 $427,7212019 $2,785,528 $1,744,403 63% $430,680 $16,789 $577,0842020 $2,639,182 $1,614,789 61% $450,061 $17,889 $118,2592021 $2,980,634 $1,964,480 66% $470,314 $20,183 $381,1232022 $3,078,340 $2,073,853 67% $491,478 $21,900 $279,2742023 $3,303,158 $2,307,957 70% $513,594 $20,929 $962,8062024 $2,840,818 $1,879,674 66% $536,706 $21,194 $76,6802025 $3,301,457 $2,360,895 72% $560,858 $25,313 $243,1722026 $3,627,421 $2,703,893 75% $586,097 $25,361 $944,9792027 $3,254,084 $2,370,371 73% $612,471 $26,615 $54,4932028 $3,814,796 $2,954,964 77% $640,032 $30,826 $412,9892029 $4,047,318 $3,212,833 79% $668,834 $33,146 $495,5312030 $4,226,205 $3,419,282 81% $698,931 $32,569 $1,053,5712031 $3,853,148 $3,097,210 80% $730,383 $29,223 $1,106,8672032 $3,431,806 $2,749,949 80% $763,250 $28,639 $561,5312033 $3,586,669 $2,980,307 83% $797,597 $30,527 $680,7972034 $3,650,293 $3,127,634 86% $833,488 $34,613 $197,8392035 $4,249,085 $3,797,896 89% $870,995 $22,165 $106,1362036 $4,999,510 $4,604,751 92% $910,190 $25,896 $710,6092037 $5 182 185 $4 851 593 94% $951 149 $26 806 $743 457
Interest Income
Reserve Expenses
Starting Reserve Balance
Percent Funded
Annual Reserve Contribs
Fully Funded Balance
11
2037 $5,182,185 $4,851,593 94% $951,149 $26,806 $743,4572038 $5,370,268 $5,109,067 95% $993,950 $30,073 $314,5192039 $6,047,985 $5,843,237 97% $1,038,678 $31,818 $1,127,2292040 $5,941,330 $5,812,943 98% $1,085,419 $35,177 $74,6662041 $6,965,766 $6,887,169 99% $1,134,263 $39,039 $1,115,0812042 $6,986,647 $6,975,635 100% $1,185,304 $40,372 $670,842
11
Yearly Contributions Graph For Treehouse Condominiums
$60 000
$80,000
$100,000
$120,000
ontr
ibut
ion
Reserve Contributions
Recommended Current
Minimum
12
$-
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
20
13
20
15
20
17
20
19
20
21
20
23
20
25
20
27
20
29
20
31
20
33
20
35
20
37
20
39
20
41
20
43
Mon
thly
Con
trib
utio
n
Year
Reserve Contributions
Recommended Current
Minimum
12
Component Funding Information For Treehouse Condominiums
Asset Name MonthlyCOMMON AREA GROUNDS
401 Asphalt - Overlay (A) $148,550 $185,120 $117,602 $117,602 $446.76401 Asphalt - Overlay (B) $148,550 $220,759 $92,844 $0 $446.76402 Asphalt - Seal Coat/crack fill $30,150 $35,954 $30,150 $30,150 $544.05611 Slip Resistant Mats - Replace $4,625 $4,833 $3,469 $3,469 $83.46801 Identification Sign - Replace $5,125 $7,288 $3,075 $0 $18.501003 Chain Link Fencing - Replace $13,500 $16,823 $11,571 $11,571 $27.841201 Tennis Court Asphalt - Replace $61,250 $285,875 $61,250 $61,250 $126.311202 Tennis Court - Recoat/Paint $6,375 $8,675 $6,375 $6,375 $65.731301 Play Equipment - Replace $42,500 $82,250 $5,000 $0 $180.451306 Park Furnishings - Replace $2,750 $3,003 $1,650 $1,650 $39.701423 Manager's Units - Remodel $5,875 $7,006 $5,875 $5,875 $106.011604 Pole Lights - Replace $6,475 $8,069 $5,319 $5,319 $16.69
BUILDINGS A-I105 Modified Bitumen - Replace (1) $235,200 $306,292 $164,640 $164,640 $848.83105 Modified Bitumen - Replace (2) $235,200 $365,258 $117,600 $0 $848.83105 Modified Bitumen - Replace (3) $235,200 $416,821 $82,320 $0 $848.83123 Skylights - Replace (1) $13,500 $17,581 $9,450 $9,450 $48.72123 Skylights - Replace (2) $13,500 $20,965 $6,750 $0 $48.72123 Skylights - Replace (3) $13,500 $23,925 $4,725 $0 $48.72204 Building Ext Surfaces - Repaint $141,750 $161,760 $56,700 $56,700 $2,046.28301 Wood Siding - Major Repairs $49,500 $56,488 $19,800 $19,800 $714.57501 Doors - Partial Replacement $21,275 $23,233 $15,956 $15,956 $191.95607 Wood Deck - Major Repairs $13,500 $15,406 $9,450 $9,450 $97.44701 Boilers - Major Repairs $150,000 $171,175 $85,714 $85,714 $1,546.70701 Boilers - Major Repairs (Bldg C) $9,000 $9,405 $7,200 $7,200 $129.92701 Boilers - Replace (A,B,D) $257,400 $543,983 $132,377 $0 $530.83701 Boilers - Replace (Bldg H) $39,000 $75,476 $9,750 $0 $140.75701 Boilers - Replace (E,F) $171,600 $378,975 $83,349 $0 $353.88701 Boilers - Replace (G,I) $171,600 $396,029 $78,446 $0 $353.88702 Boilers - Replace (Bldg C) $92,500 $187,069 $50,214 $0 $190.76703 Hot Water Storage Tank - Replace (05) $34,000 $40,546 $22,667 $22,667 $204.51703 Hot Water Storage Tank - Replace (06) $34,000 $42,370 $19,833 $19,833 $204.51703 Hot Water Storage Tank - Replace (07) $51,000 $66,415 $25,500 $25,270 $306.76703 Hot Water Storage Tank - Replace (09, 10$25,500 $37,895 $6,375 $0 $153.38706 Tankless Water Heaters - Replace $52,875 $68,857 $42,300 $0 $127.22715 Pumps - Replace $22,500 $23,513 $15,000 $15,000 $541.34721 Expansion Tanks - Replace $16,500 $18,829 $6,600 $6,600 $238.191424 Unit Building Interiors - Refurbish $33,000 $34,485 $26,400 $26,400 $476.38
BUILDINGS J & K105 Comp Shingle Roof - Replace $45,500 $96,159 $10,341 $0 $149.28204 Building Ext Surfaces - Reseal $9,000 $11,216 $9,000 $9,000 $129.92305 Wood Siding - Replace/Major Repairs $9,000 $11,216 $4,500 $4,500 $64.96606 Wood Deck - Replace $17,213 $23,424 $7,172 $0 $103.531011 Retaining Wall - Replace $16,000 $48,087 $2,667 $0 $38.501602 Exterior Wall Mount - Replace $3,300 $5,125 $1,100 $0 $15.88
GUEST CLUBHOUSE104 Flat Roof - Replace $12,563 $17,096 $7,390 $0 $53.34105 Comp Shingle Roof - Replace $50,350 $85,388 $22,886 $0 $165.19204 Building Ext Surfaces - Repaint $4,375 $5,452 $4,375 $4,375 $63.16216 Interior Surfaces - Repaint $10,245 $15,910 $10,245 $10,245 $73.95301 Wood Siding - Major Repairs $13,500 $16,823 $9,000 $9,000 $64.96503 Common Area Doors - Replace $17,500 $33,867 $7,000 $0 $50.53
Current Fund BalanceID
Ave Current Cost Future Cost
Ideal Balance
13
Component Funding Information For Treehouse Condominiums
Asset Name Monthly506 Windows - Replace $82,600 $199,208 $27,533 $0 $198.73607 Wood Stairs/Deck - Replace $9,000 $13,977 $4,500 $0 $32.48702 Boiler - Replace $17,500 $33,867 $7,000 $0 $50.53703 Water Heater - Replace $5,000 $6,231 $3,333 $3,333 $24.06707 Elevator - Rebuild/Upgrade $55,000 $106,441 $22,000 $0 $158.79709 Elevator Cab - Remodel $13,500 $16,823 $9,000 $9,000 $64.96721 Expansion Tanks - Replace $4,000 $4,368 $3,200 $3,200 $28.87901 Fire Protection System - Replace $3,675 $7,112 $1,470 $0 $10.61903 Video Surveillance System - Replace $9,250 $10,101 $7,708 $7,708 $55.641101 Pool w/Spa - Resurface $11,050 $13,177 $6,139 $6,139 $88.621102 Spa - Resurface $5,500 $5,748 $4,583 $4,583 $66.161105 Pool Heater - Replace $3,250 $3,549 $2,708 $2,708 $19.551106 Spa Heaters - Replace $7,950 $8,682 $6,625 $6,625 $47.821108 Pool Filter - Replace $4,050 $6,290 $2,025 $0 $14.621126 Misc. Pool Equipment - Replace $9,250 $10,101 $6,607 $6,607 $95.381401 Laundry Room - Remodel $16,500 $25,624 $8,250 $0 $59.551403 Kitchen - Remodel $13,500 $16,823 $9,000 $9,000 $64.961405 Furnishings - Replace $19,000 $24,743 $19,000 $19,000 $228.571406 Cardio Equipment - Replace $18,000 $20,541 $12,600 $12,600 $129.921406 Strength Equipment - Replace $8,100 $11,519 $3,780 $0 $38.981407 Wallpaper - Replace $20,655 $32,077 $20,655 $20,655 $149.091409 Sauna Room - Refurbish $3,750 $4,673 $2,500 $2,500 $18.041410 Sauna Heater - Replace $2,600 $2,839 $2,167 $2,167 $15.641413 Restrooms - Remodel $27,000 $41,930 $13,500 $0 $97.441429 Ceiling Tiles - Replace $4,600 $5,732 $3,067 $3,067 $22.131430 Racquet Ball Court - Refurbish $8,750 $12,443 $8,750 $8,750 $78.951501 Carpeting - Replace $16,315 $21,246 $16,315 $16,315 $196.271502 Vinyl Flooring - Replace $12,050 $18,713 $12,050 $12,050 $86.981503 Ceramic Tile - Replace $36,200 $45,112 $24,133 $24,133 $174.191601 Interior - Replace $18,450 $28,652 $9,225 $0 $66.59
OWNERS CLUBHOUSE102 Mod. Bitumen Flat Roof - Replace $4,250 $5,535 $2,833 $0 $17.04105 Comp Shingle Roof - Replace $23,888 $28,486 $19,544 $19,544 $78.37204 Building Ext Surfaces - Repaint $3,300 $4,112 $3,300 $3,300 $47.64216 Interior Surfaces - Repaint $5,188 $8,056 $5,188 $5,188 $37.44301 Wood Siding - Replace $5,875 $9,124 $5,875 $5,875 $42.41503 Doors - Replace $2,800 $8,415 $2,800 $2,800 $8.08506 Windows - Replace $11,200 $21,675 $4,480 $0 $32.34607 Wood Deck - Replace $11,250 $17,471 $6,750 $0 $32.48702 Boilers - Replace $20,000 $27,217 $13,000 $0 $72.18703 Hot Water Storage Tank - Replace $3,350 $5,681 $838 $0 $15.11717 Suspended Heaters - Replace $1,350 $2,613 $1,350 $1,350 $6.50901 Fire Protection System - Replace $2,250 $3,200 $1,530 $0 $6.501101 Pool - Resurface $10,000 $10,450 $8,889 $8,889 $80.201102 Spa - Replace $16,500 $19,677 $12,100 $12,100 $79.401108 Pool Filter - Replace $2,000 $3,106 $1,200 $0 $5.771109 Spa Filter - Replace $1,350 $1,682 $1,080 $1,080 $3.901126 Misc. Pool Equipment - Replace $5,250 $6,261 $2,250 $2,250 $54.131405 Furnishings - Replace $9,000 $11,720 $9,000 $9,000 $108.271409 Sauna Room - Refurbish $4,250 $4,641 $3,683 $3,683 $20.45
IDAve Current Cost Future Cost
Ideal Balance
Current Fund Balance
14
Component Funding Information For Treehouse Condominiums
Asset Name Monthly1410 Sauna Heater - Replace $2,600 $4,409 $2,600 $2,600 $15.641413 Restroom - Remodel $19,000 $23,677 $14,250 $14,250 $68.571501 Carpeting - Replace $1,600 $1,826 $1,120 $1,120 $11.551503 Tile - Replace $5,265 $8,176 $2,633 $0 $19.001601 Interior - Replace $2,925 $7,054 $2,925 $2,925 $10.56
IDAve Current Cost Future Cost
Ideal Balance
Current Fund Balance
15
Yearly Cash Flow For Treehouse Condominiums
Year 2013 2014 2015 2016 2017Starting Balance $1,041,157 $989,981 $1,258,385 $1,563,121 $1,509,858 Reserve Income $175,750 $345,600 $361,152 $377,404 $394,387 Interest Earnings $10,151 $11,237 $14,102 $15,358 $16,255 Loan Payback $0 $0 $0 $0 $0Funds Available $1,227,058 $1,346,818 $1,633,638 $1,955,883 $1,920,500Reserve Expenditures $237,078 $88,433 $70,518 $446,025 $177,939Ending Balance $989,981 $1,258,385 $1,563,121 $1,509,858 $1,742,562
Year 2018 2019 2020 2021 2022Starting Balance $1,742,562 $1,744,403 $1,614,789 $1,964,480 $2,073,853 Reserve Income $412,134 $430,680 $450,061 $470,314 $491,478 Interest Earnings $17,427 $16,789 $17,889 $20,183 $21,900 Special Assessments $0 $0 $0 $0 $0Funds Available $2,172,124 $2,191,872 $2,082,738 $2,454,976 $2,587,231Reserve Expenditures $427,721 $577,084 $118,259 $381,123 $279,274Ending Balance $1,744,403 $1,614,789 $1,964,480 $2,073,853 $2,307,957
Year 2023 2024 2025 2026 2027Starting Balance $2,307,957 $1,879,674 $2,360,895 $2,703,893 $2,370,371 Reserve Income $513,594 $536,706 $560,858 $586,097 $612,471 Interest Earnings $20,929 $21,194 $25,313 $25,361 $26,615 Special Assessments $0 $0 $0 $0 $0Funds Available $2,842,481 $2,437,574 $2,947,066 $3,315,351 $3,009,458Reserve Expenditures $962,806 $76,680 $243,172 $944,979 $54,493Ending Balance $1,879,674 $2,360,895 $2,703,893 $2,370,371 $2,954,964
Year 2028 2029 2030 2031 2032
16
Year 2028 2029 2030 2031 2032Starting Balance $2,954,964 $3,212,833 $3,419,282 $3,097,210 $2,749,949 Reserve Income $640,032 $668,834 $698,931 $730,383 $763,250 Interest Earnings $30,826 $33,146 $32,569 $29,223 $28,639 Special Assessments $0 $0 $0 $0 $0Funds Available $3,625,822 $3,914,813 $4,150,782 $3,856,817 $3,541,839Reserve Expenditures $412,989 $495,531 $1,053,571 $1,106,867 $561,531Ending Balance $3,212,833 $3,419,282 $3,097,210 $2,749,949 $2,980,307
Year 2033 2034 2035 2036 2037Starting Balance $2,980,307 $3,127,634 $3,797,896 $4,604,751 $4,851,593 Reserve Income $797,597 $833,488 $870,995 $910,190 $951,149 Interest Earnings $30,527 $34,613 $41,995 $47,262 $49,782 Special Assessments $0 $0 $0 $0 $0Funds Available $3,808,431 $3,995,735 $4,710,887 $5,562,203 $5,852,524Reserve Expenditures $680,797 $197,839 $106,136 $710,609 $743,457Ending Balance $3,127,634 $3,797,896 $4,604,751 $4,851,593 $5,109,067
Year 2038 2039 2040 2041 2042Starting Balance $5,109,067 $5,843,237 $5,812,943 $6,887,169 $6,975,635 Reserve Income $993,950 $1,038,678 $1,085,419 $1,134,263 $1,185,304 Interest Earnings $54,738 $58,256 $63,474 $69,285 $72,661 Special Assessments $0 $0 $0 $0 $0Funds Available $6,157,756 $6,940,172 $6,961,835 $8,090,716 $8,233,601Reserve Expenditures $314,519 $1,127,229 $74,666 $1,115,081 $670,842Ending Balance $5,843,237 $5,812,943 $6,887,169 $6,975,635 $7,562,758
16
Yearly Expenditures Graph For Treehouse Condominiums
$1,000,000
$1,200,000
$1,400,000
$1,600,000
$1,800,000
$2,000,000
al T
otal
s
Reserve Expenditures
$-
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
$1,400,000
$1,600,000
$1,800,000
$2,000,000 2
01
3
20
15
20
17
20
19
20
21
20
23
20
25
20
27
20
29
20
31
20
33
20
35
20
37
20
39
20
41
20
43
Annu
al T
otal
s
Year
Reserve Expenditures
17
Projected Reserve Expenditures For Treehouse CondominiumsProjected
Year Sub Group Asset ID Asset Name Cost2013 Common Area Grounds 402 Asphalt - Seal Coat/crack fill $30,150
Common Area Grounds 1201 Tennis Court Asphalt - Replace $61,250Common Area Grounds 1202 Tennis Court - Recoat/Paint $6,375Common Area Grounds 1423 Manager's Units - Remodel $5,875Buildings J & K 204 Building Ext Surfaces - Reseal $9,000Guest Clubhouse 204 Building Ext Surfaces - Repaint $4,375Guest Clubhouse 216 Interior Surfaces - Repaint $10,245Guest Clubhouse 1405 Furnishings - Replace $19,000Guest Clubhouse 1407 Wallpaper - Replace $20,655Guest Clubhouse 1430 Racquet Ball Court - Refurbish $8,750Guest Clubhouse 1501 Carpeting - Replace $16,315Guest Clubhouse 1502 Vinyl Flooring - Replace $12,050Owners Clubhouse 204 Building Ext Surfaces - Repaint $3,300Owners Clubhouse 216 Interior Surfaces - Repaint $5,188Owners Clubhouse 301 Wood Siding - Replace $5,875Owners Clubhouse 503 Doors - Replace $2,800Owners Clubhouse 717 Suspended Heaters - Replace $1,350Owners Clubhouse 1405 Furnishings - Replace $9,000Owners Clubhouse 1410 Sauna Heater - Replace $2,600Owners Clubhouse 1601 Interior - Replace $2,925 $237,078
2014 Common Area Grounds 611 Slip Resistant Mats - Replace $4,833Buildings A-I 701 Boilers - Major Repairs (Bldg C) $9,405Buildings A-I 715 Pumps - Replace $23,513Buildings A-I 1424 Unit Building Interiors - Refurbish $34,485Guest Clubhouse 1102 Spa - Resurface $5,748Owners Clubhouse 1101 Pool - Resurface $10,450 $88,433
2015 Common Area Grounds 1306 Park Furnishings - Replace $3,003Buildings A-I 501 Doors - Partial Replacement $23,233Guest Clubhouse 721 Expansion Tanks - Replace $4,368Guest Clubhouse 903 Video Surveillance System - Replace $10,101Guest Clubhouse 1105 Pool Heater - Replace $3,549Guest Clubhouse 1106 Spa Heaters - Replace $8,682Guest Clubhouse 1126 Misc. Pool Equipment - Replace $10,101Guest Clubhouse 1410 Sauna Heater - Replace $2,839Owners Clubhouse 1409 Sauna Room - Refurbish $4,641 $70,518
2016 Buildings A-I 204 Building Ext Surfaces - Repaint $161,760Buildings A-I 301 Wood Siding - Major Repairs $56,488Buildings A-I 607 Wood Deck - Major Repairs $15,406Buildings A-I 701 Boilers - Major Repairs $171,175Buildings A-I 721 Expansion Tanks - Replace $18,829Guest Clubhouse 1406 Cardio Equipment - Replace $20,541Owners Clubhouse 1501 Carpeting - Replace $1,826 $446,025
2017 Common Area Grounds 402 Asphalt - Seal Coat/crack fill $35,954Common Area Grounds 1423 Manager's Units - Remodel $7,006Buildings A-I 703 Hot Water Storage Tank - Replace (05) $40,546Buildings A-I 715 Pumps - Replace $26,832Guest Clubhouse 1101 Pool w/Spa - Resurface $13,177Owners Clubhouse 105 Comp Shingle Roof - Replace $28,486Owners Clubhouse 1102 Spa - Replace $19,677Owners Clubhouse 1126 Misc. Pool Equipment - Replace $6,261 $177,939
2018 Common Area Grounds 401 Asphalt - Overlay (A) $185,120Common Area Grounds 611 Slip Resistant Mats - Replace $5,764
Total Per Annum
18
Projected Reserve Expenditures For Treehouse Condominiums
Year Sub Group Asset ID Asset Name Projected CostCommon Area Grounds 1003 Chain Link Fencing - Replace $16,823Common Area Grounds 1604 Pole Lights - Replace $8,069Buildings A-I 703 Hot Water Storage Tank - Replace (06) $42,370Buildings J & K 204 Building Ext Surfaces - Reseal $11,216Buildings J & K 305 Wood Siding - Replace/Major Repairs $11,216Guest Clubhouse 204 Building Ext Surfaces - Repaint $5,452Guest Clubhouse 301 Wood Siding - Major Repairs $16,823Guest Clubhouse 703 Water Heater - Replace $6,231Guest Clubhouse 709 Elevator Cab - Remodel $16,823Guest Clubhouse 1403 Kitchen - Remodel $16,823Guest Clubhouse 1409 Sauna Room - Refurbish $4,673Guest Clubhouse 1429 Ceiling Tiles - Replace $5,732Guest Clubhouse 1503 Ceramic Tile - Replace $45,112Owners Clubhouse 204 Building Ext Surfaces - Repaint $4,112Owners Clubhouse 1109 Spa Filter - Replace $1,682Owners Clubhouse 1413 Restroom - Remodel $23,677 $427,721
2019 Buildings A-I 105 Modified Bitumen - Replace (1) $306,292Buildings A-I 123 Skylights - Replace (1) $17,581Buildings A-I 701 Boilers - Major Repairs (Bldg C) $11,720Buildings A-I 703 Hot Water Storage Tank - Replace (07) $66,415Buildings A-I 706 Tankless Water Heaters - Replace $68,857Buildings A-I 1424 Unit Building Interiors - Refurbish $42,975Guest Clubhouse 1405 Furnishings - Replace $24,743Guest Clubhouse 1501 Carpeting - Replace $21,246Owners Clubhouse 102 Mod. Bitumen Flat Roof - Replace $5,535Owners Clubhouse 1405 Furnishings - Replace $11,720 $577,084
2020 Common Area Grounds 1202 Tennis Court - Recoat/Paint $8,675Common Area Grounds 1306 Park Furnishings - Replace $3,742Buildings A-I 715 Pumps - Replace $30,619Buildings J & K 606 Wood Deck - Replace $23,424Guest Clubhouse 104 Flat Roof - Replace $17,096Guest Clubhouse 1102 Spa - Resurface $7,485Owners Clubhouse 702 Boilers - Replace $27,217 $118,259
2021 Common Area Grounds 402 Asphalt - Seal Coat/crack fill $42,876Common Area Grounds 801 Identification Sign - Replace $7,288Common Area Grounds 1423 Manager's Units - Remodel $8,355Buildings A-I 204 Building Ext Surfaces - Repaint $201,583Buildings A-I 301 Wood Siding - Major Repairs $70,394Buildings A-I 721 Expansion Tanks - Replace $23,465Guest Clubhouse 1406 Strength Equipment - Replace $11,519Guest Clubhouse 1430 Racquet Ball Court - Refurbish $12,443Owners Clubhouse 901 Fire Protection System - Replace $3,200 $381,123
2022 Common Area Grounds 401 Asphalt - Overlay (B) $220,759Common Area Grounds 611 Slip Resistant Mats - Replace $6,873Buildings A-I 703 Hot Water Storage Tank - Replace (09, 10, 11 $37,895Guest Clubhouse 1126 Misc. Pool Equipment - Replace $13,746 $279,274
2023 Buildings A-I 105 Modified Bitumen - Replace (2) $365,258Buildings A-I 123 Skylights - Replace (2) $20,965Buildings A-I 501 Doors - Partial Replacement $33,039Buildings A-I 701 Boilers - Major Repairs $232,945Buildings A-I 715 Pumps - Replace $34,942Buildings J & K 204 Building Ext Surfaces - Reseal $13,977
Total Per Annum
19
Projected Reserve Expenditures For Treehouse Condominiums
Year Sub Group Asset ID Asset Name Projected CostBuildings J & K 1602 Exterior Wall Mount - Replace $5,125Guest Clubhouse 204 Building Ext Surfaces - Repaint $6,794Guest Clubhouse 216 Interior Surfaces - Repaint $15,910Guest Clubhouse 607 Wood Stairs/Deck - Replace $13,977Guest Clubhouse 1108 Pool Filter - Replace $6,290Guest Clubhouse 1401 Laundry Room - Remodel $25,624Guest Clubhouse 1407 Wallpaper - Replace $32,077Guest Clubhouse 1413 Restrooms - Remodel $41,930Guest Clubhouse 1502 Vinyl Flooring - Replace $18,713Guest Clubhouse 1601 Interior - Replace $28,652Owners Clubhouse 204 Building Ext Surfaces - Repaint $5,125Owners Clubhouse 216 Interior Surfaces - Repaint $8,056Owners Clubhouse 301 Wood Siding - Replace $9,124Owners Clubhouse 607 Wood Deck - Replace $17,471Owners Clubhouse 1101 Pool - Resurface $15,530Owners Clubhouse 1108 Pool Filter - Replace $3,106Owners Clubhouse 1503 Tile - Replace $8,176 $962,806
2024 Buildings A-I 701 Boilers - Major Repairs (Bldg C) $14,606Buildings A-I 1424 Unit Building Interiors - Refurbish $53,554Owners Clubhouse 1126 Misc. Pool Equipment - Replace $8,520 $76,680
2025 Common Area Grounds 402 Asphalt - Seal Coat/crack fill $51,131Common Area Grounds 1306 Park Furnishings - Replace $4,664Common Area Grounds 1423 Manager's Units - Remodel $9,963Guest Clubhouse 105 Comp Shingle Roof - Replace $85,388Guest Clubhouse 721 Expansion Tanks - Replace $6,784Guest Clubhouse 1405 Furnishings - Replace $32,222Guest Clubhouse 1501 Carpeting - Replace $27,668Owners Clubhouse 703 Hot Water Storage Tank - Replace $5,681Owners Clubhouse 1405 Furnishings - Replace $15,263Owners Clubhouse 1410 Sauna Heater - Replace $4,409 $243,172
2026 Common Area Grounds 611 Slip Resistant Mats - Replace $8,196Buildings A-I 105 Modified Bitumen - Replace (3) $416,821Buildings A-I 123 Skylights - Replace (3) $23,925Buildings A-I 204 Building Ext Surfaces - Repaint $251,209Buildings A-I 301 Wood Siding - Major Repairs $87,724Buildings A-I 607 Wood Deck - Major Repairs $23,925Buildings A-I 715 Pumps - Replace $39,874Buildings A-I 721 Expansion Tanks - Replace $29,241Guest Clubhouse 1101 Pool w/Spa - Resurface $19,583Guest Clubhouse 1102 Spa - Resurface $9,747Guest Clubhouse 1406 Cardio Equipment - Replace $31,900Owners Clubhouse 1501 Carpeting - Replace $2,836 $944,979
2027 Common Area Grounds 1202 Tennis Court - Recoat/Paint $11,806Guest Clubhouse 903 Video Surveillance System - Replace $17,130Guest Clubhouse 1105 Pool Heater - Replace $6,019Guest Clubhouse 1106 Spa Heaters - Replace $14,723Guest Clubhouse 1410 Sauna Heater - Replace $4,815 $54,493
2028 Common Area Grounds 1301 Play Equipment - Replace $82,250Buildings A-I 701 Boilers - Replace (Bldg H) $75,476Buildings J & K 204 Building Ext Surfaces - Reseal $17,418Buildings J & K 305 Wood Siding - Replace/Major Repairs $17,418Guest Clubhouse 204 Building Ext Surfaces - Repaint $8,467
Total Per Annum
20
Projected Reserve Expenditures For Treehouse Condominiums
Year Sub Group Asset ID Asset Name Projected CostGuest Clubhouse 503 Common Area Doors - Replace $33,867Guest Clubhouse 702 Boiler - Replace $33,867Guest Clubhouse 707 Elevator - Rebuild/Upgrade $106,441Guest Clubhouse 901 Fire Protection System - Replace $7,112Owners Clubhouse 204 Building Ext Surfaces - Repaint $6,386Owners Clubhouse 506 Windows - Replace $21,675Owners Clubhouse 717 Suspended Heaters - Replace $2,613 $412,989
2029 Common Area Grounds 402 Asphalt - Seal Coat/crack fill $60,974Common Area Grounds 1423 Manager's Units - Remodel $11,881Buildings A-I 701 Boilers - Major Repairs (Bldg C) $18,201Buildings A-I 702 Boilers - Replace (Bldg C) $187,069Buildings A-I 703 Hot Water Storage Tank - Replace (05) $68,761Buildings A-I 715 Pumps - Replace $45,503Buildings A-I 1424 Unit Building Interiors - Refurbish $66,738Guest Clubhouse 1126 Misc. Pool Equipment - Replace $18,707Guest Clubhouse 1430 Racquet Ball Court - Refurbish $17,696 $495,531
2030 Common Area Grounds 611 Slip Resistant Mats - Replace $9,774Common Area Grounds 1306 Park Furnishings - Replace $5,812Buildings A-I 701 Boilers - Major Repairs $317,007Buildings A-I 701 Boilers - Replace (A,B,D) $543,983Buildings A-I 703 Hot Water Storage Tank - Replace (06) $71,855Buildings J & K 105 Comp Shingle Roof - Replace $96,159Owners Clubhouse 1409 Sauna Room - Refurbish $8,982 $1,053,571
2031 Buildings A-I 204 Building Ext Surfaces - Repaint $313,052Buildings A-I 301 Wood Siding - Major Repairs $109,320Buildings A-I 501 Doors - Partial Replacement $46,985Buildings A-I 701 Boilers - Replace (E,F) $378,975Buildings A-I 703 Hot Water Storage Tank - Replace (07) $112,632Buildings A-I 721 Expansion Tanks - Replace $36,440Guest Clubhouse 1405 Furnishings - Replace $41,961Guest Clubhouse 1501 Carpeting - Replace $36,031Owners Clubhouse 1126 Misc. Pool Equipment - Replace $11,595Owners Clubhouse 1405 Furnishings - Replace $19,876 $1,106,867
2032 Buildings A-I 701 Boilers - Replace (G,I) $396,029Buildings A-I 715 Pumps - Replace $51,927Buildings J & K 606 Wood Deck - Replace $39,724Guest Clubhouse 1102 Spa - Resurface $12,693Owners Clubhouse 1101 Pool - Resurface $23,079Owners Clubhouse 1102 Spa - Replace $38,080 $561,531
2033 Common Area Grounds 402 Asphalt - Seal Coat/crack fill $72,713Common Area Grounds 1423 Manager's Units - Remodel $14,169Buildings J & K 204 Building Ext Surfaces - Reseal $21,705Guest Clubhouse 204 Building Ext Surfaces - Repaint $10,551Guest Clubhouse 216 Interior Surfaces - Repaint $24,708Guest Clubhouse 301 Wood Siding - Major Repairs $32,558Guest Clubhouse 506 Windows - Replace $199,208Guest Clubhouse 703 Water Heater - Replace $12,059Guest Clubhouse 709 Elevator Cab - Remodel $32,558Guest Clubhouse 1403 Kitchen - Remodel $32,558Guest Clubhouse 1407 Wallpaper - Replace $49,814Guest Clubhouse 1409 Sauna Room - Refurbish $9,044Guest Clubhouse 1429 Ceiling Tiles - Replace $11,094
Total Per Annum
21
Projected Reserve Expenditures For Treehouse Condominiums
Year Sub Group Asset ID Asset Name Projected CostGuest Clubhouse 1502 Vinyl Flooring - Replace $29,061Guest Clubhouse 1503 Ceramic Tile - Replace $87,304Owners Clubhouse 204 Building Ext Surfaces - Repaint $7,959Owners Clubhouse 216 Interior Surfaces - Repaint $12,511Owners Clubhouse 301 Wood Siding - Replace $14,169Owners Clubhouse 1601 Interior - Replace $7,054 $680,797
2033 Common Area Grounds 611 Slip Resistant Mats - Replace $11,656Common Area Grounds 1202 Tennis Court - Recoat/Paint $16,067Buildings A-I 701 Boilers - Major Repairs (Bldg C) $22,682Buildings A-I 703 Hot Water Storage Tank - Replace (09, 10, 11 $64,266Buildings A-I 1424 Unit Building Interiors - Refurbish $83,168 $197,839
2035 Common Area Grounds 1306 Park Furnishings - Replace $7,243Buildings A-I 715 Pumps - Replace $59,257Guest Clubhouse 721 Expansion Tanks - Replace $10,535Guest Clubhouse 1101 Pool w/Spa - Resurface $29,102 $106,136
2036 Buildings A-I 204 Building Ext Surfaces - Repaint $390,120Buildings A-I 301 Wood Siding - Major Repairs $136,232Buildings A-I 607 Wood Deck - Major Repairs $37,154Buildings A-I 721 Expansion Tanks - Replace $45,411Guest Clubhouse 1126 Misc. Pool Equipment - Replace $25,458Guest Clubhouse 1406 Cardio Equipment - Replace $49,539Guest Clubhouse 1406 Strength Equipment - Replace $22,293Owners Clubhouse 1501 Carpeting - Replace $4,403 $710,609
2037 Common Area Grounds 402 Asphalt - Seal Coat/crack fill $86,712Common Area Grounds 1423 Manager's Units - Remodel $16,897Buildings A-I 701 Boilers - Major Repairs $431,402Guest Clubhouse 104 Flat Roof - Replace $36,130Guest Clubhouse 1405 Furnishings - Replace $54,644Guest Clubhouse 1430 Racquet Ball Court - Refurbish $25,165Guest Clubhouse 1501 Carpeting - Replace $46,922Owners Clubhouse 102 Mod. Bitumen Flat Roof - Replace $12,223Owners Clubhouse 1405 Furnishings - Replace $25,884Owners Clubhouse 1410 Sauna Heater - Replace $7,478 $743,457
2038 Common Area Grounds 611 Slip Resistant Mats - Replace $13,900Buildings A-I 715 Pumps - Replace $67,622Buildings J & K 204 Building Ext Surfaces - Reseal $27,049Buildings J & K 305 Wood Siding - Replace/Major Repairs $27,049Buildings J & K 1011 Retaining Wall - Replace $48,087Buildings J & K 1602 Exterior Wall Mount - Replace $9,918Guest Clubhouse 204 Building Ext Surfaces - Repaint $13,149Guest Clubhouse 1102 Spa - Resurface $16,530Owners Clubhouse 204 Building Ext Surfaces - Repaint $9,918Owners Clubhouse 503 Doors - Replace $8,415Owners Clubhouse 1126 Misc. Pool Equipment - Replace $15,779Owners Clubhouse 1413 Restroom - Remodel $57,103 $314,519
2039 Buildings A-I 105 Modified Bitumen - Replace (1) $738,688Buildings A-I 123 Skylights - Replace (1) $42,399Buildings A-I 501 Doors - Partial Replacement $66,818Buildings A-I 701 Boilers - Major Repairs (Bldg C) $28,266Buildings A-I 1424 Unit Building Interiors - Refurbish $103,642Guest Clubhouse 903 Video Surveillance System - Replace $29,051Guest Clubhouse 1105 Pool Heater - Replace $10,207
Total Per Annum
22
Projected Reserve Expenditures For Treehouse Condominiums
Year Sub Group Asset ID Asset Name Projected CostGuest Clubhouse 1106 Spa Heaters - Replace $24,968Guest Clubhouse 1410 Sauna Heater - Replace $8,166Owners Clubhouse 105 Comp Shingle Roof - Replace $75,023 $1,127,229
2040 Common Area Grounds 1306 Park Furnishings - Replace $9,026Owners Clubhouse 702 Boilers - Replace $65,640 $74,666
2041 Common Area Grounds 402 Asphalt - Seal Coat/crack fill $103,405Common Area Grounds 801 Identification Sign - Replace $17,577Common Area Grounds 1202 Tennis Court - Recoat/Paint $21,864Common Area Grounds 1423 Manager's Units - Remodel $20,149Buildings A-I 204 Building Ext Surfaces - Repaint $486,160Buildings A-I 301 Wood Siding - Major Repairs $169,770Buildings A-I 703 Hot Water Storage Tank - Replace (05) $116,610Buildings A-I 715 Pumps - Replace $77,168Buildings A-I 721 Expansion Tanks - Replace $56,590Owners Clubhouse 703 Hot Water Storage Tank - Replace $11,489Owners Clubhouse 1101 Pool - Resurface $34,297 $1,115,081
2042 Common Area Grounds 401 Asphalt - Overlay (A) $532,409Common Area Grounds 611 Slip Resistant Mats - Replace $16,576Buildings A-I 703 Hot Water Storage Tank - Replace (06) $121,857 $670,842
2043 Buildings A-I 105 Modified Bitumen - Replace (2) $880,899Buildings A-I 123 Skylights - Replace (2) $50,562Buildings A-I 703 Hot Water Storage Tank - Replace (07) $191,011Buildings J & K 204 Building Ext Surfaces - Reseal $33,708Guest Clubhouse 204 Building Ext Surfaces - Repaint $16,386Guest Clubhouse 216 Interior Surfaces - Repaint $38,371Guest Clubhouse 607 Wood Stairs/Deck - Replace $33,708Guest Clubhouse 1108 Pool Filter - Replace $15,169Guest Clubhouse 1126 Misc. Pool Equipment - Replace $34,644Guest Clubhouse 1401 Laundry Room - Remodel $61,798Guest Clubhouse 1405 Furnishings - Replace $71,161Guest Clubhouse 1407 Wallpaper - Replace $77,360Guest Clubhouse 1413 Restrooms - Remodel $101,124Guest Clubhouse 1501 Carpeting - Replace $61,105Guest Clubhouse 1502 Vinyl Flooring - Replace $45,131Guest Clubhouse 1601 Interior - Replace $69,101Owners Clubhouse 204 Building Ext Surfaces - Repaint $12,360Owners Clubhouse 216 Interior Surfaces - Repaint $19,429Owners Clubhouse 301 Wood Siding - Replace $22,004Owners Clubhouse 717 Suspended Heaters - Replace $5,056Owners Clubhouse 1109 Spa Filter - Replace $5,056Owners Clubhouse 1405 Furnishings - Replace $33,708Owners Clubhouse 1503 Tile - Replace $19,719 $1,898,567
Total Per Annum
23
1
Glossary of Commonly used Words and Phrases (provided by the National Reserve Study Standards of the Community Associations Institute) Asset or Component – Individual line items in the Reserve Study, developed or updated in the Physical Analysis. These elements form the building blocks for the Reserve Study. Components typically are: 1) Association Responsibility, 2) with limited Useful Life expectancies, 3) have predictable Remaining Life expectancies, 4) above a minimum threshold cost, and 5) required b y local codes. Cash Flow Method – A method of developing a Reserve Funding Plan where contributions to the Reserve fund are designed to offset the variable annual expenditures from the Reserve fund. Different Reserve Funding Plans are tested against the anticipated schedule of Reserve expenses until the desired Funding Goal is achieved. Component Inventory – The task of selecting and quantifying Reserve Components. This task can be accomplished through on-site visual observations, review of association de sign and organizational documents, a review of established association precedents, and discussion with appropriate association representatives. Deficit – An actual (or projected) Reserve Balance, which is less than the Fully Funded Balance. Effective Age – The difference between Useful Life and Remaining Useful Life. Not always equivalent to chronological age, since some components age irregularly. Used primarily in computations. Financial Analysis – The portion of the Reserve Study where current status of the Reserves (Measured as cash or Percent Funded) and a recommended Reserve contribution rate (Reserve Funding Plan) are derived, and the projected Reserve income and expense over time is presented. The Financial Analysis is one of the two parts of the Reserve Study. Component Full Funding – When the actual (or projected) cumulative Reserve balance for all components is equal to the Fully Funded Balance. Fully Fund Balance (aka – Ideal Balance) – An indicator against which Actual (or projected) Reserve Balance can be compared. The Reserve balance that is in direct proportion to the fraction of life “used up” of the current Repair or Replacement cost. This number is calculated for each component, and then summed together for an association total. FFB = Replacement Cost X Effective Age / Useful Life Fund Status – The status of the Reserve Fund as compared to an established benchmark, such as percent funding. Funding Goals – Independent of methodology utilized, the following represent the basic categories of Funding Plan Goals.
• Baseline Funding: Establishing a Reserve funding goal of keeping the Reserve Balance above zero.
• Component Full Funding: Setting a Reserve funding goal of attaining and maintaining cumulative Reserves at or near 100% funded.
• Threshold Funding: Establishing a Reserve funding goal of keeping the Reserve balance above a specified dollar or Percent Funded amount. Depending on the threshold, this may be more or less conservative than the “Component Fully Funding” method.
2
Funding Plan – An associations plan to provide income to a Reserve fund to offset anticipated expenditures from that fund. Funding Principles –
• Sufficient Funds When Required • Stable Contribution Rate over the Years • Evenly Distributed Contributions over the Years • Fiscally Responsible
Life and Valuation Estimates – The task of estimating Useful Life, Remaining Useful Life, and Repair or Replacement Costs for the Reserve components. Percent Funded – The ratio, at a particular point of time (typically the beginning of the Fisc al Year), of the actual (or projected) Reserve Balance to the accrued Fund Balance, expressed as a percentage. Physical Analysis – The portion of the Reserve Study where the Component Inventory, Condition Assessment, and Life and Valuation Estimate tasks are performed. This represents one of the two parts of the Reserve Study. Remaining Useful Life (RUL) – Also referred to as “Remaining Life” (RL). The estimated time, in years, that a reserve component can be expected to continue to serve its intended function. Projects anticipated to occur in the initial year have “0” Remaining Useful Life. Replacement Cost – The cost of replacing, repairing, or restoring a Reserve Component to its original functional condition. The Current Replacement Cost would be the cost to replace, repair, or restore the component during that particular year. Reserve Balance – Actual or projected funds as of a particular point in time (typically the beginning of the fiscal year) that the association has identified for use t o defray the future repair or replacement of those major components in which the association is obligated to maintain. Also known as Reserves, Reserve Accounts, Cash Reserves. This is based upon information provided and is not audited. Reserve Provider – An individual that prepares Reserve Studies. Also known as Aspen Reserve Specialties. Reserve Study – A budget-planning tool that identifies the current status of the Reserve fund and a stable and equitable Funding Plan to offset the anticipated future major common area expenditures. The Reserve Study consists of two parts: The Physical Analysis and the Financial Analysis. Special Assessment – An assessment levied on the members of an association in addition to regular assessments. Special Assessments are often regulated by governing documents or local statutes. Surplus – An actual (or projected) Reserve Balance that is greater that the Fully Funded Balance. Useful Life (UL) – Also known as “Life Expectancy”, or “Depreciable Life”. The estimated time, in years, that a Reserve component can be expected to serve its intended function if properly constructed and maintained in its present application or installation.