responding to and planning for lift station failures
TRANSCRIPT
Denton Wastewater Utility Background
• 100+ square mile service area
• 540+ miles of collection and force mains
• 2 WWTPs
• 31+ lift stations (and more on the way)
• 2 full time 6-man construction crews
2020 WEAT SEMINAR 2
Hickory Creek Lift Station
• 40 Square mile basin
• Constructed in 1984
• Wet well – Dry pit construction
• Firm Capacity = 3,500 gpm (5 MGD)
• 3 pumps (2 functional)
• 12,200 LF 24-inch Forcemain
• Average Daily Flow 3 MGD
2020 WEAT SEMINAR 4
Hickory Creek System Failures
A pump casing failed after ingesting concrete. Pump replaced. Pump 3 valves damaged and not repaired for cost savings. SSO – 720,750 gallons
Feb. 2018
Electrical anomaly believed to have caused transient surge. SSO – 300,000 gallons
Dec. 2018
Electrical anomaly believed to have caused transient surge. SSO – 490,000 gallons
Nov. 2019
2020 WEAT SEMINAR 5
December 2018 Event
• 1:56 PM – Plant receives VFD Failure Alarm on Pump 1
• 2:20 PM – Staff determines VFD 1 fuses have blown
• 2:30 PM – Staff start Pump 2
• 2:43 PM – Dispatch receives call of sewer coming out of the ground
• 3:00 PM – Staff identify forcemain leak
• 4:28 PM – Lift station is shut down
• 11:00PM the following day – FM Repairs completed
2020 WEAT SEMINAR 6
Thanksgiving 2019 Event
• Sunday, November 24th
• Received a call of an issue at the HCLS
• 10:00 am City staff rapidly mobilized to the site
• Immediate notification was sent to UTRWD, TCEQ and CMO/PA
• Contacted Sunbelt to provide bypass equipment
• Staff set up pumps and piping we had on hand to begin bypass
• 3:59 pm begin bypass to UTRWD with small pipe and pumps COD had
• 10:30 pm Sunbelt piping, drive over, and pumps set up and sent flow to UTRWD
2020 WEAT SEMINAR 11
Thanksgiving 2019 Event
• Monday, November 25th and Tuesday, November 26th
• Contractor onsite to deploy sand bag and plug piping
• Declaration of Emergency issued
• Press Releases sent
• Pumping continued to evaluate the situation
• Water Quality Sampling began
• Walked project with TCEQ
• Damage discovered
• Sand plug failed
2020 WEAT SEMINAR 12
Thanksgiving 2019 Event
• Wednesday, November 27th and Thursday, November 28th
• Pumping and Water Quality Sampling continued• Pump 2 part received from Chicago • Pump 2 repairs were made and regular lift station operation restored• Bypass pumping to UTRWD still deployed• Overflow stopped
• Tuesday, December 3rd – Monday, December 9th
• Press release sent• Rangeline installed stopple on force main• Boil water notice lifted for citizens with water well within one half-mile of lift station• Pump 1 repairs were made using parts from Pump 3 • Pump 1 was operational and redundancy was restored
2020 WEAT SEMINAR 13
Total Spend on Two Events
December 2018 Event – $115,500 + Equipment time
Bypass Pumping Equipment – $205,000 to date (not all costs accounted for)
November 2019 Event – $165,000 + Equipment time to date (not all costs accounted for)
2020 WEAT SEMINAR 18
Recurring Questions
• What did we do last time?
• Why reinvent the response?
• Why not own everything we need?
• What do we need to purchase?
• Why can’t we use what we purchased?
• Where is that old public notice document?
• Who do we call at TCEQ?
• Leadership Transitions led to knowledge loss.
2020 WEAT SEMINAR 19
Lift Station Emergency Response Plan
• What does it need to say?
• What data is necessary?
• Maps
• System curves
• Pump curves
• Equipment lists
• Bypass capability
• Site photos
• Incident Commander
2020 WEAT SEMINAR 20
Lessons Learned
Establish an ERP
Establish a Scribe and central POC
Public Notices and Press Releases
Departmental Coordination
Establish working parameters
Establish Documentation process
Bypass equipment and materials need to be ready
2020 WEAT SEMINAR 24
Materials List for Emergency Response•10” Lay-Flat Hose
•10”, 8”, 6” and 4” Centrifugal Pumps
•Trailer(s)
•Road Ramp
•Road Ramp Adapters
•10” Adapters
•10” O-Ring
•2” Air Vent
•10” Check Valve
•10” 45 degree and 90 degree Bends
2020 WEAT SEMINAR 25