CHALLENGES IN CONSTRUCTION OF URBAN

ROAD TUNNELS, THE CASE HISTORY OF TOHID

EXPRESSWAY TUNNELS IN CENTRAL TEHRAN Jamal Rostami Mohsen Kashi

Penn State University, SRS Engineering,

University Park, PA Tehran, Iran

Page 2: RETC2011 Rostami Kashi

OUTLINE

Introduction

Tunnel Alignment and Profile

Site Development

Portals and Construction Shafts

Tunneling Operation

Crossing an active Subway Station

Conclusions

Page 3: RETC2011 Rostami Kashi

South Portal

Page 4: RETC2011 Rostami Kashi

BACKGROUND

Tehran & Suburbs is the home for over 10 million people

City is spread over an area of around 50 km in the E-W and 30 km in

N-S direction

Tehran has experienced a rapid growth in past 3 decades,

The original fabric is old and does not have sufficient ratio of traffic

space to residential space to accommodate the flow

Streets are congested, slow traffic

2 subway lines are operational, 5 under construction

A network of highways has been constructed around the town

A series of road tunnels are planned to connect the highways

First highway tunnel (Resalat) was completed in 2004 (6 lanes)

2nd one is Towheed, Inaugurated in Feb 2010, 3rd is under

construction for 9 km + a 2000 car capacity underground parking

Page 5: RETC2011 Rostami Kashi

پروژه تونل توحيد

Page 6: RETC2011 Rostami Kashi

Project Map

Page 7: RETC2011 Rostami Kashi

Tunnel

The Least Neighborhood Interference

Fuel Cost

Traffic Congestion

Travel Time

Page 8: RETC2011 Rostami Kashi

ALIGNMENT & PORTALS

Page 9: RETC2011 Rostami Kashi

VERTICAL ALIGNMENT

Page 10: RETC2011 Rostami Kashi

Project North

End Point

Toeheed Shaft North

Portal Jomhoury Shaft

Azadi Shaft South

Portal Project

South End

Point

557-m 310-m 2136-m

Metro Line No. 4

Metro Line No.2

557-m 677-m 496-m 406-m

Work Sites Site Name

1 The North Portal

2 Toeheed Shaft

3 Azadi Shaft

4 Jomhouri Shaft

5 The South Portal

Longitudinal Profile North Ramp Slope 6%

Tunnel Overall Slope 4%

South Ramp Slope 4.29%

Page 11: RETC2011 Rostami Kashi

TUNNEL PROFILE

Page 12: RETC2011 Rostami Kashi

GENERAL INFORMATION

Tunnel Height : 8.5-m

Tunnel Width: 13.5-m Each

Overall Project length: 3003-m

The Tunnel Length: 2136-m

Tunnel Cross Section Area: 305-m2

Approach Half-Tunnels North 577-m

South 310-m

Start Date: June 10, 2007

Page 13: RETC2011 Rostami Kashi

Quantity Unit Activity

750000

m3

Open Excavation

660000 m3 Tunnel Excavation

26000 m Pile Construction

56000 m2 Formwork

25000 Ton Steel Reinforcement

200000 m3 Concrete Placement

450000 m2 Shotcrete Application

250000 m2 Wire Mesh

50000 m2 Precast Concrete Elements

Bill of Quantities

Project Budget ~$400M

Page 14: RETC2011 Rostami Kashi

INTERFACES WITH OTHER UNDERGROUND STRUCTURES

Subway Line No. 2 (Existing). The longitudinal profile of the tunnel is designed to go under the Subway Station Line No. 2 located around station 2+392 of this tunnel.

Subway Line No. 4 (under construction). The Toeheed tunnel passes beneath the Subway Line No. 4 currently under construction.

Subway Line No. 7 (future construction). The tunnel will essentially run parallel to the No. 7 Subway Line and provisions shall be made in the design and construction of this subway line to assure constructability and other operational issues involved.

Urban Utilities. Several underground utilities including water, gas, electric and telephone lines did interfere with the tunnel and other auxiliary structures such as the shafts, galleries, and the access ramps.

Page 15: RETC2011 Rostami Kashi

GROUND CONDITION

Mainly course grained soils, gravel/sand

Primarily dry except for certain sections

Intersecting old water works (qanats) Table 1. Borehole/Test Pit Soil Classifications

Borehole Station

(km)

Depths at Tunnel

Section(m) USCS Soil Symbols

BH-1 0+360 5-15 SC/GC-GM/GC

BH-2 0+850 9-18 SC-SM/GC-GM

BH-3 1+070 12-21 GM/GC-GM/SC-SM

BH-7 1+810 20-30 SC

BH-8 1+920 21-30 GC-GM/GM/SC-SM

BH-9 2+150 22-31 SC-SM

Test Pits

TP-1 0+270 0-5 GW/SW/GP

TP-2 0+400 0-10 GP/GP-GM/GW/GP

TP-3 0+520 4-13 GW-GM/GM/GP/GM

TP-4 1+200 15-22 GW/GC/GW

Page 16: RETC2011 Rostami Kashi

Embedded U-Turn Lane

UNIQUE PORTAL ENTRY DESIGN

Page 17: RETC2011 Rostami Kashi

HALF ARCH U-TURN LANE

Provides additional traffic lane for U-turn

Allows for easier transition to daylight

Page 18: RETC2011 Rostami Kashi

MOBILIZATION, SITE PREPARATION

Page 19: RETC2011 Rostami Kashi

Power House, bar Bending & Batching

Plant

Page 20: RETC2011 Rostami Kashi

Power House

Page 21: RETC2011 Rostami Kashi

Equipment

Page 22: RETC2011 Rostami Kashi

10,000 Ton Cement Silos

Page 23: RETC2011 Rostami Kashi

Staging Area, Equipment Shops

Page 24: RETC2011 Rostami Kashi

NORTH RAMP

SITE PREPARATION

Page 25: RETC2011 Rostami Kashi

Traffic Diversion & Preparatory Work Relocating 600-mm Water main Pipe Traffic Diversion Barriers Road Widening

Supporting 1000-mm Water main Pipe Relocating the military base walls

Page 26: RETC2011 Rostami Kashi

REDIRECTING

TRAFFIC

Page 27: RETC2011 Rostami Kashi
Page 28: RETC2011 Rostami Kashi
Page 29: RETC2011 Rostami Kashi

CONTINUED HEAVY TRAFFIC

Page 30: RETC2011 Rostami Kashi

TOEHEED SHAFT SITE

Page 31: RETC2011 Rostami Kashi

Toeheed Shaft

Chain Bucket

Vertical Conveyor

Page 32: RETC2011 Rostami Kashi
Page 33: RETC2011 Rostami Kashi

Lowering the Road Header

Inside the shaft

Page 34: RETC2011 Rostami Kashi

Towheed Shaft

Side Gallery

Page 35: RETC2011 Rostami Kashi

Middle Gallery

Inside Towheed Shaft

Page 36: RETC2011 Rostami Kashi

AZADI SHAFT SITE

Page 37: RETC2011 Rostami Kashi

AZADI

SHAFT

METRO

Station

Azadi

Shaft Site

Page 38: RETC2011 Rostami Kashi

AZADI SHAFT 677-M TO TOEHEED SHAFT

496-M TO JOMHOORI SHAFT

Page 39: RETC2011 Rostami Kashi

AZADI

SHAFT

METRO

LINE

كارگاه شفت

آزادي

Galleries Excavated in the Access Tunnel

from Azadi Shaft

Page 40: RETC2011 Rostami Kashi

JOMHOORI SHAFT SITE

Page 41: RETC2011 Rostami Kashi

JOMHOORI

SHAFT

METRO

LINE

Jomhoori

Shaft Site

Page 42: RETC2011 Rostami Kashi
Page 43: RETC2011 Rostami Kashi

JOMHOORI SHAFT

496-M TO AZADI SHAFT 406-M TO THE SOUTHERN

PORTAL

Page 44: RETC2011 Rostami Kashi

Middle Galleries inside the Jomhoori Shaft

Page 45: RETC2011 Rostami Kashi

گالری های کناری شفت گالری میانی شفت جمهوری

Installing the Pre-cast Lining and Concreting جمهوری

Page 46: RETC2011 Rostami Kashi

SITE PREPARATION FOR

SOUTHERN RAMP / PORTAL

Page 47: RETC2011 Rostami Kashi

U Turn

South Portal

Face

km 2.600

South Ramp

28(m)

Page 48: RETC2011 Rostami Kashi

28(m)

Page 49: RETC2011 Rostami Kashi

South Ramp Portal Access

Page 50: RETC2011 Rostami Kashi

گالری میانی فوقانی و تونلهای دسترسی شرقی و غربی

Page 51: RETC2011 Rostami Kashi

A view of South Ramp at Night

Page 52: RETC2011 Rostami Kashi

TUNNEL EXCAVATION METHOD

Sequential Excavation Method (SEM)

Page 53: RETC2011 Rostami Kashi

Excavation of the upper part of the middle gallery

1

Page 54: RETC2011 Rostami Kashi

Excavation of the Bench, or lower part of the middle gallery

1

2

Page 55: RETC2011 Rostami Kashi

Excavation of the side galleries

2

1

3 3

Page 56: RETC2011 Rostami Kashi

Construction of cast in placement of concrete piles Installation of a portion of final lining in the side galleries

3 3 2

1

4

Page 57: RETC2011 Rostami Kashi

Excavation of the crown region of the tunnels

2

1

3 3

4

5 5

Page 58: RETC2011 Rostami Kashi

Removing the temporary supports, benching, and completion of crown lining

2

1

3 3

4

5 5

6 6

Page 59: RETC2011 Rostami Kashi

Excavation of the lower portion of the tunnels

2

1

3 3

4

5 5

6 6

7 7

Page 60: RETC2011 Rostami Kashi

Completing excavation of the lower parts of the tunnels

2

1

3 3

4

5 5

6 6

7 7 8 8

Page 61: RETC2011 Rostami Kashi

Installation of Permanent Concrete Forms

and concreting

2

1

3 3

4

5 5

6 6

7 7 8 8 9 9

Page 62: RETC2011 Rostami Kashi

Drainage Ditch and Base Slab Construction

2

1

3 3

4

5 5

6 6

7 7 8 8 9 9

10 10

Page 63: RETC2011 Rostami Kashi

Completed Tunnel Profile

Page 64: RETC2011 Rostami Kashi

Using Conveyor Belt for Soil Removal

Page 65: RETC2011 Rostami Kashi

Excavation using Roadheader

Page 66: RETC2011 Rostami Kashi
Page 67: RETC2011 Rostami Kashi

Excavation using Roadheader

Page 68: RETC2011 Rostami Kashi
Page 69: RETC2011 Rostami Kashi

Shotcrete Application

Page 70: RETC2011 Rostami Kashi

Reinforcing Cages For the Piles

Page 71: RETC2011 Rostami Kashi

عملیات الینینگ دیواره های کناری عملیات بتن پاشی برای تثبیت دیواره گالری

Installation of Precast Elements

Page 72: RETC2011 Rostami Kashi

Permanent Linings عملیات بتن پاشی برای تثبیت دیواره گالری

Page 73: RETC2011 Rostami Kashi
Page 74: RETC2011 Rostami Kashi

CHALLANGES

Page 75: RETC2011 Rostami Kashi

CHALLENGES

Crossing the active subway line, under the station

Small footprint for work

Redirecting of traffic

Restriction in access, muck haulage

Fast -Track project, accelerated schedule

Maintaining existing utilities, (i.e. a1.8 m water main)

Dealing with historical waterworks (qanats)

Causing water leakage into the tunnel

Subsidence - sinkhole

Page 76: RETC2011 Rostami Kashi

CROSSING OF THE ACTIVE SUBWAY

STATION

Page 77: RETC2011 Rostami Kashi

PROFILE

Page 78: RETC2011 Rostami Kashi

CROSSING OF SUBWAY STATION

Intersecting Station in

North

Middle

South

Page 79: RETC2011 Rostami Kashi

ADDITIONAL PROVISIONS FOR STATION

CROSSING

Installation of Invert

beam in the middle

gallery

Heavy grouting of the

lining under the station

Page 80: RETC2011 Rostami Kashi

MODELING AND ANALYSIS

Numerical Modeling of Sequential Excavation

under the station

Page 81: RETC2011 Rostami Kashi

GROUND REACTION MODELING

Page 82: RETC2011 Rostami Kashi

RESULTS

Max measured settlement at the station was:

Page 83: RETC2011 Rostami Kashi

COMPLETION OF THE WORK

Page 84: RETC2011 Rostami Kashi

CONSTRUCTION PROGRESS

Page 85: RETC2011 Rostami Kashi

FINISHING TOUCHES

Page 86: RETC2011 Rostami Kashi

VENTILATION AND CONTROL STRUCTURE

Page 87: RETC2011 Rostami Kashi

UTILITIES & FIT OUTS

Ventilation

Fire protection

Lighting

Communication

Traffic Control

CCTV

Art Works!

Page 88: RETC2011 Rostami Kashi

UTILITIES & FIT OUTS

70 jet fans, each powered at 30 KW.

North fan combined ventilation equipment: 3 axial fans, powered at 600 KW.

Niyayesh fan combined ventilation equipment: 2 axial fans (to let in fresh air into Tunnel) powered at 410 KW. 4 axial fans (to let out exhaust air from Tunnel) powered at 500 KW.

South portal fan combined ventilation equipment: 3 axial fans powered at 990 KW.

Air purification system at the air entering Niyayesh fans.

Lghts in the Tunnel: 1,064 lights powered at 550 KW.

Length of cables for the utilities: 220 km.

Special and standby power generators

Air pollution monitoring sensors

Smart firefighting system.

Traffic alarms.

Intercom telephones.

Closed-Circuit TV.

Vehicles counter.

Road closure system.

Traffic signs.

Thermal sensors.

Page 89: RETC2011 Rostami Kashi

FINISHED TUNNEL

Page 90: RETC2011 Rostami Kashi

FINISHED TUNNEL

Page 91: RETC2011 Rostami Kashi

INAUGURATION CEREMONEY, FEB 2010

Opening of the project by Citizens / Veterans

Page 92: RETC2011 Rostami Kashi

Questions ?????