rethinking economic regulation of infrastructure …...+ other costs (r&d, idm, sqi) +/- annual...

29
www.gsb.uct.ac.za/mir Prof Anton Eberhard Management Program in Infrastructure Reform and Regulation University of Cape Town [email protected] www.gsb.uct.ac.za/mir Rethinking Economic Regulation of Infrastructure Industries South African economic regulators conference 21 & 22 August 2012, Johannesburg

Upload: others

Post on 26-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Prof Anton Eberhard Management Program in Infrastructure Reform and Regulation

University of Cape Town

[email protected]

www.gsb.uct.ac.za/mir

Rethinking Economic Regulation

of Infrastructure Industries

South African economic regulators conference

21 & 22 August 2012, Johannesburg

Page 2: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Outline

• Performance of infrastructure regulators

• The case of electricity: the issues that

consumers really care about….

– Prices

– Reliability of supply

• Regulatory reform proposals

Page 3: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Evaluating regulatory systems

Legal design and institutional

arrangements of regulatory system and

processes of regulatory decision-making

Content of regulation

licences, tariffs

supply & service standards

Credibility, legitimacy,

and transparency of

regulatory decisions

Quality & robustness

of regulatory decisions

Impact on sector

Adapted from Brown, Stern, Tenenbaum & Gencer, 2006

Competitively priced, reliable infrastructure services

Financial viability, new investment

Regulatory substance Regulatory governance

Page 4: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Impact of infrastructure regulation in South Africa?

Electricity [see later slides]

• Power outages between 2006-2008

• Supply security still threatened by

– Insufficient availability of generation capacity

– Poorly maintained networks

• Prices have risen steeply to unprecedented levels

ICT [Research ICT Africa]

• South Africa slipping down international & African rankings

in prices for landline and mobile telephony and in

broadband access, quality and prices

Ports [Port regulator benchmark study]

• Rates are higher than international benchmarks

Page 5: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

SA Electricity Prices (1970-2012)

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012

Nominal

Page 6: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

SA Electricity Prices (1970-2012)

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012

Nominal

Real (2008 values)

Page 7: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

SA Electricity Prices (1970-2012)

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012

Nominal

Average

Real (2008 values)

Why are prices now more than double (and soon treble)

historical average (in real terms)

Page 8: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

SA electricity regulatory periods (1990-2012)

0

10

20

30

40

50

60

70

1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012

c/k

Wh

Avg nominal prices Avg real prices (2008)

1st price compact: 1991

reduction of 20% over 5 years

(real terms)

2nd price compact: 1994,

decrease of 15% (real terms) by 2000

ACTUAL

REAL 2008

Page 9: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

SA electricity regulatory periods (1990-2012)

0

10

20

30

40

50

60

70

1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012

c/k

Wh

Avg nominal prices Avg real prices (2008)

1st price compact: 1991

reduction of 20% over 5 years

(real terms)

2nd price compact: 1994,

decrease of 15% (real terms) by 2000

Rate of return regulation

applied from 2000/1

ACTUAL

REAL 2008

Page 10: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

SA electricity regulatory periods (1990-2012)

0

10

20

30

40

50

60

70

1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012

c/k

Wh

Avg nominal prices Avg real prices (2008)

1st price compact: 1991

reduction of 20% over 5 years

(real terms)

2nd price compact: 1994,

decrease of 15% (real terms) by 2000

Rate of return regulation

applied from 2000/1

MYPD1 modified revenue cap

methodology from 2006-8

5% 27%, 31%

MYPD2 2009-2011

25% 25% 16%)

ACTUAL

REAL 2008

Price increases driven in part by increased coal costs and mainly by

increases in financing costs for new generation assets (but still high!!)

Page 11: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

SA electricity regulatory periods (1990-2012)

0

10

20

30

40

50

60

70

1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012

c/k

Wh

Avg nominal prices Avg real prices (2008) infalted prices

1st price compact: 1991

reduction of 20% over 5 years

(real terms)

2nd price compact: 1994,

decrease of 15% (real terms) by 2000

Rate of return regulation

applied from 2000/1

MYPD1 modified revenue cap

methodology from 2006-8

5% 27%, 31%

MYPD2 2009-2011

25% 25% 16%)

ACTUAL

IF INCREASED

BY INFALTION

FROM 1990

REAL 2008

Price increases driven in part by increased coal costs and mainly by

increases in financing costs for new generation assets (but still high!!)

Page 12: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Pick a number, any number: the MYPD1 record

2007/8 Eskom electricity price increase

• Feb 2006 Original Nersa MYPD decision 5.9%

• April 2007 Eskom applies for revision 18.7%

• Dec 2007 Nersa approves 14.2%

• March 2008 Eskom applies for 2nd revision 60.0%

• June 2008 Nersa approves 27.5%

ACTUAL PRICE INCREASE FOR 2007/8 8.5%

2008/9 Eskom electricity price increase

• Feb 2006 Original Nersa MYPD1 decision 6.2%

• May 2009 Eskom applies for revision 34.0%

• June 2009 Nersa approves 31.1%

ACTUAL PRICE INCREASE FOR 2008/9 27.5%

In 2007/8 Eskom changes its request for price increases

from 5.9% to 18.7% to 60% !!

Page 13: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

MYPD2 (2010/11/12/13) also radically revised

• Sept 2009 Eskom gives notice that it intends to

apply for an increase of 45% in each year

• Nov 2009 Eskom reduces request to 35%

after consultation with NT and SALGA

• April 2010 Nersa approves average of 25% for each year

• Feb 2012 Eskom applies for a reduction to 16%

• March 2012 Nersa approves reduction to 16%

• May 2012 Eskom reports “profit” of R18.4 billion

Neither Eskom nor Nersa

appear to be able to predict or assess costs accurately

The MYPD was meant to create certainty

It has achieved the exact opposite

Page 14: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Medupi and Kusile cost & time overruns

• Approved project costs- excluding capitalised interest Medupi: R 98 900 million US$ 2770 / kW

Kusile: R121 000 million US$ 3360 / kW

• Commissioning dates slip by 2-3 years

Medupi (work starts May 2007)

– Estimated in Nov 2007 1st unit Apr-11; last unit Jan-15

– Estimated in July 2012 1st unit Aug-13; last unit May-17

Kusile (Work starts April 2008)

– Estimated May-07 1st unit Mar-12; last unit Dec-15

– Estimated Jul-12 1st unit Dec-14; last unit Aug-18

Sources: Eskom Annual reports; System adequacy Reports What are final costs, including contract revisions?

Amongst most expensive coal-fired power stations in world?

Interest during construction grows with delays

Page 15: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

How does Nersa determine electricity tariffs?

Simplifying

Allowed revenue = O&M

+ depreciation

+ rate of return (WACC) on reg. assets

+ taxes

+ pass through of power purchase cost

+ other costs (R&D, IDM, SQI)

+/- annual reconciliation

Allowed average tariff = allowed revenue / predicted kWh

Nothing wrong in principle with this cost of service methodology

Eskom needs to recover prudently and efficiently incurred

operating and maintenance costs plus consumption of assets

(depreciation) plus its cost of capital in financing capital expansion

Page 16: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

But methodology not appropriately applied

This may not be an entirely fair criticism – but

Nersa appears to change its assumptions in order to get the tariff

increase it judges to be acceptable

Examples

Phasing in revaluation of assets, different assumptions in the WACC

calculation, different depreciation assumptions

Another example

When Nersa accepted Eskom’s extraordinary request to lower the

increase for 2012/13 from 25.9% to 16% after the president had said

something had to be done about high electricity increases, it said this

was possible through “accepting a change in the regulatory clearing

account and the re-phasing of returns”.

Page 17: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Security of electricity supply also unsatisfactory

– Western Cape blackouts in late 2005 / early 2006 after generator failures at Cape Town’s Koeberg nuclear power plant, coupled with transmission line failures

– First national load shedding on18 January 2007 when unprecedented number of coal generation units fail

(boiler tube ruptures, etc)

– 9 major load shedding events Oct - Dec 2007

– Major load shedding from 10 Jan 2008

– Mines shut down on 24 January 2008 to prevent

system collapse

insufficient capacity as generator units fail

coupled with coal supplies running out!

– Between January and July 2008: 1000 GWh electricity demand interrupted; approximately 5 – 6 % less electricity consumed than predicted in 2008.

Electricity supply/ demand still very tight and risk of further

blackouts is high

Page 18: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Actual system reserve margin 2012

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

12

-Jan

19

-Jan

26

-Jan

02

-Fe

b

09

-Fe

b

16

-Fe

b

23

-Fe

b

01

-Mar

08

-Mar

15

-Mar

22

-Mar

29

-Mar

05

-Apr

12

-Apr

19

-Apr

26

-Apr

03

-May

10

-May

17

-May

24

-May

31

-May

07

-Jun

14

-Jun

21

-Jun

28

-Jun

05

-Jul

12

-Jul

19

-Jul

26

-Jul

02

-Aug

peak demand Available capacity

MW

Source: Eskom System Status Bulletins

Page 19: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Power generation capacity not in service

0

2000

4000

6000

8000

10000

12000

12-Jan 26-Jan 09-Feb 23-Feb 08-Mar 22-Mar 05-Apr 19-Apr 03-May 17-May 31-May 14-Jun 28-Jun 12-Jul 26-Jul

Planned maintenance Unplanned outages

MW

Source: Eskom System Status Bulletins

Page 20: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Electricity consumption has stagnated for 5 years

4000

4400

4800

5200

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52

GW

h

Week

2007 2012

Source: Eskom Medium Term Generation Adequacy Reports

Page 21: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Eskom could not have supplied normal growth

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

12

-Jan

19

-Jan

26

-Jan

02

-Fe

b

09

-Fe

b

16

-Fe

b

23

-Fe

b

01

-Mar

08

-Mar

15

-Mar

22

-Mar

29

-Mar

05

-Apr

12

-Apr

19

-Apr

26

-Apr

03

-May

10

-May

17

-May

24

-May

31

-May

07

-Jun

14

-Jun

21

-Jun

28

-Jun

05

-Jul

12

-Jul

19

-Jul

26

-Jul

02

-Aug

peak demand Available capacity

MW

Total demand in

2012 if it had

grown at 3% p.a.

since 2007

Page 22: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Electricity Distribution Industry in trouble

• REDs are dead (2010 Cabinet decision) – The Constitution specifies that electricity distribution is a local government

function and even though many municipalities entered into voluntary

agreements to proceed with restructuring, they demurred when faced with

the prospect of giving up their most valuable assets and revenue streams.

Constitutional amendment won’t pass

• EDI Holding spent R1.2 billion between 2006 and 2010 – No restructuring but valuable work done on ring-fencing, asset registers

and maintenance plans (ADAM)

– EDI Holding dissolved and experience staff now in a “technical Diaspora”

• Maintenance backlog now R35 billion and growing at a

minimum of R2.5 Billion per annum. Average age of network

approaching 50 years

• Increasing evidence of grid failures

• But no evidence of urgency in tackling problem

Page 23: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Cost of power crisis is higher than generally acknowledged

• Lost output, investment constraints, reduced economic growth, less employment and income, reduced exports, increased fuel imports, increased pressure on balance of payments & current account deficit, cycles of currency depreciation, imported inflation, higher interest rates, reduced economic growth………

• Cost of unserved energy (value of lost load) is MUCH higher than marginal cost of new generation

• And steep rises in electricity prices reduce competitiveness of South African mines and industry

Page 24: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Regulatory reform clearly needed in power sector

• Rate-of-return regulation based on depreciated historical asset

valuation in the context of large, lumpy, intermittent capital

investments and high inflation will lead to peaks and troughs in

electricity prices, but the transition to replacement cost accounting

is resulting in unacceptably sharp price increases

• Greater price certainty needed and price spikes and dips need to

be smoothed

• Insufficient controls over large capital expenditure is at the heart of

problem (biggest cost driver)

– Better monitoring and scrutiny of large capital projects with SOE Boards and

managers held to account for cost and time overruns

– Commission of enquiry into Medupi and Kusile cost overruns

– Different approach to power planning and investment

– More diversity, more innovation, incremental rather mega projects, turnkey IPP

investments and more competition in power generation needed

Page 25: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Pricing reform

• Review 2008 Pricing Policy

– Regulated electricity prices should move in a narrower band around

long term sustainable average

– Implies that the state should take out greater profits in the form of

dividends during periods of low investment and would need to inject

equity in periods of high investment

– Core regulatory accounting principles should not be abandoned:

for utility to provide an adequate service it needs to be financially

viable and prices have (on average) to be cost-reflective. Hard to

justify National Treasury subsidizing electricity (and telecom)

sectors over long term (except targeted support mechanisms for

vulnerable households)

Page 26: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Regulators role in security of supply

• Electricity consumers value security of supply above all else

• Current system of non-dynamic IRPs, Ministerial determinations

and ad-hoc procurement via Doe & NT PPP not robust

• The Electricity Regulation Act says that Nersa should facilitate

investment in the sector

– Adequacy of supply requires timely planning, procurement and contracting

of generation capacity

– Functions of generation expansion planning, allocation of new build

opportunities (between Eskom and IPPs), procurement and contracting

need to be clearly allocated and institutional capacity built

– ISMO and Electricity Regulation Amendment Bills will hopefully accomplish

this, although there is danger that too rigid a system of “approved” plans

and procurement and licensing dependant on Ministerial determinations

could be cumbersome and could inhibit innovation

– Nersa ISMO licence could contain requirements to report on adequacy of

supply and Nersa can act as early warning system if insufficient investment

Page 27: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Also need to fix the EDI (Nersa can assist)

• Adopt 80:20 principle. Focus on top 12 munics that provide nearly

80% of municipal electricity distribution

– Ring-fencing, asset registers, maintenance plans, ADAM, RoR regulation

– Transfer bits of Eskom grid in their boundaries to these muncis

• Service deliver agreements between small ailing municipal

distributors and Eskom or larger towns/cities

– E.g. Centlec around Manguang; requests to Eskom

• Ensure maintenance backlog doesn’t grow

– Nersa has powers to establish national norms and standards, including ring-

fencing of municipal electricity businesses and minimum maintenance levels.

– Nersa also approves annual electricity tariff increases based on costs

including maintenance. Municipalities that fail to spend allocated budgets

could in subsequent years face revenue claw-backs and lower tariff

increases.

• Special 10 year programme to eliminate maintenance backlog

– Conditional fiscal grants via DoE INEP with close monitoring & auditing

Page 28: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

In conclusion…………..

• The fact that regulation of electricity prices and security of

supply have been less than perfect does not mean that

independent regulatory agencies should be abolished

• No guarantee that government departments would do a

better job

• Experience across Africa (and other regions) has shown

that independent regulators enable a more transparent

debate around infrastructure pricing and service quality

– Better understanding by stakeholders of how cost-reflective tariffs

should be determined

– Arbitrary administrative action less likely

– Regulators can be held to account

Market reforms needed for more competition, transparency and accountability

in large infrastructure investments

Regulatory reforms needed for steadier prices and ensuring adequacy of supply

Page 29: Rethinking Economic Regulation of Infrastructure …...+ other costs (R&D, IDM, SQI) +/- annual reconciliation Allowed average tariff = allowed revenue / predicted kWh Nothing wrong

www.gsb.uct.ac.za/mir

Prof Anton Eberhard Research, training courses, consultancy

University of Cape Town

The Management Programme in Infrastructure

Reform & Regulation (MIR) is an emerging centre

of excellence and expertise in Africa. It is

committed to enhancing knowledge and capacity to

manage the reform and regulation of the electricity,

gas, telecommunications, water and transport

industries in support of sustainable development.

www.gsb.uct.ac.za/mir