Port of New Orleans Deepening Feasibility Study Appendix A: Engineering Revised Annex 6 Cost Engineering: TSP March 2020

Upload: others

Post on 26-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Port of New Orleans Deepening Feasibility Study

Appendix A: Engineering

Revised Annex 6

Cost Engineering: TSP

March 2020

Page 2: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

M-CACES

Page 3: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Print Date Thu 20 February 2020 U.S. Army Corps of Engineers Time 07:37:01Eff. Date 1/29/2020 Project PONO: PORT OF NEW ORLEANS DEEPENING NAVIGATIONAL FEASIBILITY STUDY - TSP- 50-FT DEPTH

TSP-Port of New Orleans Deepening - FEB 2020 Title Page

Labor ID: NOL2017 EQ ID: EP18R03 Currency in US dollars TRACES MII Version 4.4

This report is not copyrighted, but the information contained herein is For Official Use Only.

Estimated Construction Time 100 DaysEffective Date of Pricing 1/29/2020

Preparation Date 1/29/2020

Prepared by Benjamin Salamone

Estimated by Benjamin SalamoneDesigned by US Army Corps of Engineers

PORT OF NEW ORLEANS DEEPENING NAVIGATIONAL FEASIBILITY STUDY - TSP- 50-FT DEPTH5.0 Study Scope

The scope of the feasibility study includes evaluation of alternatives, including the no-action alternative, to provide deep draft access along the PONO at incremental depths between 40 feet and 50 feet for the next phase of construction. Per authority, the evaluation of alternatives was limited to a depth of the existing MRSC (which is currently justified to 50 feet).

Implementation is driven by the need to safely dock New Panamax deep draft ships (ships with a draft deeper than 49 feet). The feasibility study will identify the depth that creates the greatest net benefits, up to a depth of 50 feet. At initiation, the study recognized there was a need to evaluate phasing/sequencing of the PONO deepening because of existing conditions

and constraints.

The feasibility study will investigate an array of alternatives that deepen the PONO from 35 feet to 50 feet from RM 98.3 to 100.6. The focused array of alternatives are as follows:� No Action (35 ft)

� Alternative 2: Dredge the entire study area to 40 ft.� Alternative 3: Dredge the entire study area to 45 ft.

� Alternative 4: Dredge the entire study area to 50 ft. - TSP

FCCM Adjustment: The equipment FCCM adjustment percentage is adjusted using the following: We assume that the dredge assistant equipment shall work 6 hours per day, 7 days per week. Using EP 1110-1-8, Vol 3, paragraph 3.8 an adjustment factor of -4.762% was determined. -4.762% = (40/42)-1*100.

Orleans Parish. LA

Page 4: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Print Date Thu 20 February 2020 U.S. Army Corps of Engineers Time 07:37:01Eff. Date 1/29/2020 Project PONO: PORT OF NEW ORLEANS DEEPENING NAVIGATIONAL FEASIBILITY STUDY - TSP- 50-FT DEPTH

TSP-Port of New Orleans Deepening - FEB 2020 ProjectTop Level Cost Summary Page 1

Description ContractCost ProjectCost

ProjectTop Level Cost Summary 8,105,362.30 8,105,362.30

12 NAVIGATION, PORTS & HARBORS 8,105,362.30 8,105,362.30

12 Dredging - Construction and Maintenance 8,105,362.30 8,105,362.30

12 01 04 Alternative 4 - TSP 6,514,982.95 6,514,982.95

12 01 04 01 Port of New Orleans - CONSTRUCTION PHASE I 4,646,267.17 4,646,267.17

12 01 04 01 01 BID ITEM 0001 - Mobilization and Demobilization 768,312.35 768,312.35

12 01 04 16 02 BID ITEM 0002 - DREDGING 3,877,954.82 3,877,954.82

12 01 04 02 Port of New Orleans - MAINTENANCE PHASE I & II 1,868,715.78 1,868,715.78

12 01 04 02 01 BID ITEM 0001 - Mobilization and Demobilization 764,132.90 764,132.90

12 01 04 02 16 02 BID ITEM 0002 - DREDGING 1,104,582.88 1,104,582.88

12 01 00 FEDERAL STANDARD 1,590,379.35 1,590,379.35

12 01 00 02 Port of New Orleans - MAINTENANCE FEDERAL STANDARD 1,590,379.35 1,590,379.35

12 01 00 02 01 BID ITEM 0001 - Mobilization and Demobilization 764,132.90 764,132.90

12 01 00 02 16 02 BID ITEM 0002 - DREDGING 826,246.45 826,246.45

Labor ID: NOL2017 EQ ID: EP18R03 Currency in US dollars TRACES MII Version 4.4

Page 5: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Print Date Thu 20 February 2020 U.S. Army Corps of Engineers Time 07:37:01Eff. Date 1/29/2020 Project PONO: PORT OF NEW ORLEANS DEEPENING NAVIGATIONAL FEASIBILITY STUDY - TSP- 50-FT DEPTH

TSP-Port of New Orleans Deepening - FEB 2020 Project Cost Summary Page 2

Description DirectLabor DirectEQ DirectMatl DirectSubBid DirectCost ContractCost CostToPrime

Project Cost Summary 348,742.93 1,400,590.98 0.00 4,607,813.00 6,357,146.91 8,105,362.30 6,357,146.91

12 NAVIGATION, PORTS & HARBORS 348,742.93 1,400,590.98 0.00 4,607,813.00 6,357,146.91 8,105,362.30 6,357,146.91

12 Dredging - Construction and Maintenance 348,742.93 1,400,590.98 0.00 4,607,813.00 6,357,146.91 8,105,362.30 6,357,146.91

12 01 04 Alternative 4 - TSP 283,169.52 1,131,981.03 0.00 3,694,640.00 5,109,790.55 6,514,982.95 5,109,790.55

12 01 00 FEDERAL STANDARD 65,573.41 268,609.95 0.00 913,173.00 1,247,356.35 1,590,379.35 1,247,356.35

Labor ID: NOL2017 EQ ID: EP18R03 Currency in US dollars TRACES MII Version 4.4

Page 6: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Print Date Thu 20 February 2020 U.S. Army Corps of Engineers Time 07:37:01Eff. Date 1/29/2020 Project PONO: PORT OF NEW ORLEANS DEEPENING NAVIGATIONAL FEASIBILITY STUDY - TSP- 50-FT DEPTH

TSP-Port of New Orleans Deepening - FEB 2020 Table of Contents

Description Page

ProjectTop Level Cost Summary 112 NAVIGATION, PORTS & HARBORS 112 Dredging - Construction and Maintenance 112 01 04 Alternative 4 - TSP 112 01 04 01 Port of New Orleans - CONSTRUCTION PHASE I 112 01 04 01 01 BID ITEM 0001 - Mobilization and Demobilization 112 01 04 16 02 BID ITEM 0002 - DREDGING 1

12 01 04 02 Port of New Orleans - MAINTENANCE PHASE I & II 112 01 04 02 01 BID ITEM 0001 - Mobilization and Demobilization 112 01 04 02 16 02 BID ITEM 0002 - DREDGING 1

12 01 00 FEDERAL STANDARD 112 01 00 02 Port of New Orleans - MAINTENANCE FEDERAL STANDARD 112 01 00 02 01 BID ITEM 0001 - Mobilization and Demobilization 112 01 00 02 16 02 BID ITEM 0002 - DREDGING 1

Project Cost Summary 212 NAVIGATION, PORTS & HARBORS 212 Dredging - Construction and Maintenance 212 01 04 Alternative 4 - TSP 212 01 00 FEDERAL STANDARD 2

Labor ID: NOL2017 EQ ID: EP18R03 Currency in US dollars TRACES MII Version 4.4

Page 7: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

TOTAL PROJECT COST SUMMARY

CONSTRUCTION

Page 8: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:3/20/2020 Page 1 of 2

PROJECT: DISTRICT: New Orleans District PREPARED: 2/7/2020PROJECT NO: P2471889 POC: CHIEF, COST ENGINEERING, John PetitbonLOCATION: New Orleans , Louisiana

This Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

Program Year (Budget EC): 2025Effective Price Level Date: 1 OCT 24

Spent Thru:WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL 1-Oct-19 INFLATED COST CNTG FULL

NUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) ($K) ($K) (%) ($K) ($K) ($K) A B C D E F G H I J K L M N O

12 NAVIGATION PORTS & HARBORS $4,649 $1,545 33.24% $6,194 16.0% $5,393 $1,793 $7,186 $302 $7,488 2.3% $5,516 $1,833 $7,651-------

__________ __________ ____________ _________ _________ __________ ____________ _________ _________ ________________CONSTRUCTION ESTIMATE TOTALS: $4,649 $1,545 $6,194 16.0% $5,393 $1,793 $7,186 $302 $7,488 2.3% $5,516 $1,833 $7,651

01 LANDS AND DAMAGES $0 $0 - $0 - $0 $0 $0 $0 $0 - $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN $350 $52 15.0% $402 20.7% $422 $63 $485 $0 $485 0.9% $426 $64 $490

31 CONSTRUCTION MANAGEMENT $225 $56 25.0% $282 20.7% $272 $68 $340 $0 $340 0.9% $275 $69 $344

PROJECT COST TOTALS: $5,224 $1,654 31.7% $6,878 $6,087 $1,924 $8,012 $302 $8,314 2.1% $6,217 $1,966 $8,485

CHIEF, COST ENGINEERING, John PetitbonESTIMATED TOTAL PROJECT COST: $8,485

PROJECT MANAGER, Marti Lucore

CHIEF, REAL ESTATE, Judy Guitierrez

CHIEF, PLANNING, Troy Constance

CHIEF, ENGINEERING, Jean Vossen

CHIEF, OPERATIONS, Micheal Park

CHIEF, CONSTRUCTION, Stuart Waits

CHIEF, CONTRACTING, Deborah Logan

CHIEF, PM-PB, Brad Inman

CHIEF, DPM, Durand Elzey

TSP-Port of New Orleans Deepening-CONSTRUCTION-50-ft

Civil Works Work Breakdown Structure ESTIMATED COST

TOTAL PROJECT COST (FULLY FUNDED)

TOTAL FIRST COST

PROJECT FIRST COST (Constant Dollar Basis)

Filename: TPCS-PONO-CONST-TSP-29JAN2020.xlsxTPCS

Page 9: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:3/20/2020 Page 2 of 2

**** CONTRACT COST SUMMARY ****

PROJECT: DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 2025 1-Oct-19 1 OCT 24

RISK BASED WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULL

NUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K) A B C D E F G H I J P L M N O

PHASE 1 or CONTRACT 112 NAVIGATION PORTS & HARBORS $4,649 $1,545 33.24% $6,194 16.0% $5,393 $1,793 $7,186 2025Q4 2.3% $5,516 $1,833 $7,349

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________CONSTRUCTION ESTIMATE TOTALS: $4,649 $1,545 33.2% $6,194 $5,393 $1,793 $7,186 $5,516 $1,833 $7,349

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN1.5% Project Management $70 $10 15.0% $80 20.7% $84 $13 $97 2025Q2 0.9% $85 $13 $980.5% Planning & Environmental Compliance $23 $3 15.0% $27 20.7% $28 $4 $32 2025Q2 0.9% $28 $4 $332.3% Engineering & Design $106 $16 15.0% $121 20.7% $127 $19 $147 2025Q2 0.9% $129 $19 $1480.5% Reviews, ATRs, IEPRs, VE $21 $3 15.0% $24 20.7% $25 $4 $29 2025Q2 0.9% $25 $4 $290.5% Life Cycle Updates (cost, schedule, risks) $23 $3 15.0% $27 20.7% $28 $4 $32 2025Q2 0.9% $28 $4 $330.5% Contracting & Reprographics $23 $3 15.0% $27 20.7% $28 $4 $32 2025Q2 0.9% $28 $4 $330.5% Engineering During Construction $23 $3 15.0% $27 20.7% $28 $4 $32 2025Q2 0.9% $28 $4 $330.3% Planning During Construction $14 $2 15.0% $16 20.7% $17 $3 $19 2025Q2 0.9% $17 $3 $200.5% Adaptive Management & Monitoring $23 $3 15.0% $27 20.7% $28 $4 $32 2025Q2 0.9% $28 $4 $330.5% Project Operations $23 $3 15.0% $27 20.7% $28 $4 $32 2025Q2 0.9% $28 $4 $33

31 CONSTRUCTION MANAGEMENT2.9% Construction Management $132 $33 25.0% $166 20.7% $160 $40 $200 2025Q2 0.9% $161 $40 $2021.0% Project Operation: $46 $12 25.0% $58 20.7% $56 $14 $70 2025Q2 0.9% $57 $14 $711.0% Project Management $46 $12 25.0% $58 20.7% $56 $14 $70 2025Q2 0.9% $57 $14 $71

CONTRACT COST TOTALS: $5,224 $1,654 $6,878 $6,087 $1,924 $8,012 $6,217 $1,966 $8,183

ESTIMATED COST

TSP-Port of New Orleans Deepening-CONSTRUCTION-50-ft

TOTAL PROJECT COST (FULLY FUNDED)

Estimate Prepared:Effective Price Level:

Program Year (Budget EC):Effective Price Level Date:

Civil Works Work Breakdown Structure PROJECT FIRST COST(Constant Dollar Basis)

Filename: TPCS-PONO-CONST-TSP-29JAN2020.xlsxTPCS

Page 10: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

TOTAL PROJECT COST SUMMARY

MAINTENANCE

Page 11: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 1 of 11

PROJECT: DISTRICT: New Orleans District PREPARED: 2/7/2020PROJECT NO: P2471889 POC: CHIEF, COST ENGINEERING, John PetitbonLOCATION: New Orleans , Louisiana

This Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

Program Year (Budget EC): 2025Effective Price Level Date: 1 OCT 24

Spent Thru:WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL 1-Oct-19 INFLATED COST CNTG FULL

NUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) ($K) ($K) (%) ($K) ($K) ($K) A B C D E F G H I J K L M N O

12 NAVIGATION PORTS & HARBORS $74,350 $24,536 33.0% $98,886 16.0% $86,251 $28,463 $114,714 $0 $114,714 137.6% $204,975 $67,642 $272,616-------

__________ __________ ____________ _________ _________ __________ ____________ _________ _________ ________________CONSTRUCTION ESTIMATE TOTALS: $74,350 $24,536 $98,886 16.0% $86,251 $28,463 $114,714 $0 $114,714 137.6% $204,975 $67,642 $272,616

01 LANDS AND DAMAGES $0 $0 - $0 - $0 $0 $0 $0 $0 - $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN $12,491 $4,122 33.0% $16,613 20.7% $15,080 $4,977 $20,057 $0 $20,057 185.6% $43,072 $14,214 $57,285

31 CONSTRUCTION MANAGEMENT $11,264 $3,717 33.0% $14,981 20.7% $13,599 $4,488 $18,087 $0 $18,087 205.8% $41,582 $13,722 $55,304

PROJECT COST TOTALS: $98,105 $32,375 33.0% $130,479 $114,931 $37,927 $152,858 $0 $152,858 152.0% $289,628 $95,577 $385,206

CHIEF, COST ENGINEERING, John PetitbonESTIMATED TOTAL PROJECT COST: $385,206

PROJECT MANAGER, Marti Lucore

CHIEF, REAL ESTATE, Judy Guitierrez

CHIEF, PLANNING, Troy Constance

CHIEF, ENGINEERING, Jean Vossen

CHIEF, OPERATIONS, Micheal Park

CHIEF, CONSTRUCTION, Stuart Waits

CHIEF, CONTRACTING, Deborah Logan

CHIEF, PM-PB, Brad Inman

CHIEF, DPM, Durand Elzey

TOTAL PROJECT COST (FULLY FUNDED)

TOTAL FIRST COST

PROJECT FIRST COST (Constant Dollar Basis)

TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft

Civil Works Work Breakdown Structure ESTIMATED COST

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 12: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 2 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 2025 1-Oct-19 1 OCT 24

RISK BASED WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULL

NUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K) A B C D E F G H I J P L M N O

Maintenance Year 112 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2026Q4 5.3% $1,817 $600 $2,417

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% $1,978 $1,725 $569 $2,294 $1,817 $600 $2,417

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2026Q1 3.8% $37 $12 $500.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2026Q1 3.8% $9 $3 $121.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2026Q1 3.8% $19 $6 $251.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2026Q1 3.8% $19 $6 $250.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2026Q1 3.8% $9 $3 $121.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2026Q1 3.8% $19 $6 $251.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2026Q4 6.8% $29 $9 $380.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2026Q4 6.8% $10 $3 $131.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2026Q1 3.8% $19 $6 $257.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2026Q1 3.8% $145 $48 $193

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% $181 20.7% $164 $54 $218 2026Q4 6.8% $175 $58 $2333.0% Project Operation: $45 $15 33.0% $59 20.7% $54 $18 $72 2026Q4 6.8% $58 $19 $763.0% Project Management $45 $15 33.0% $59 20.7% $54 $18 $72 2026Q4 6.8% $58 $19 $76

CONTRACT COST TOTALS: $1,962 $647 $2,610 $2,299 $759 $3,057 $2,422 $799 $3,221

TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft

TOTAL PROJECT COST (FULLY FUNDED)

Estimate Prepared:Effective Price Level:

Program Year (Budget EC):Effective Price Level Date:

Civil Works Work Breakdown Structure ESTIMATED COST PROJECT FIRST COST(Constant Dollar Basis)

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 13: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 3 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 2025 1-Oct-19 1 OCT 24

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 2

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2027Q4 8.5% $1,872 $618 $2,489

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________

CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% $1,978 $1,725 $569 $2,294 $1,872 $618 $2,489

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2027Q1 7.8% $39 $13 $510.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2027Q1 7.8% $10 $3 $131.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2027Q1 7.8% $19 $6 $261.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2027Q1 7.8% $19 $6 $260.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2027Q1 7.8% $10 $3 $131.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2027Q1 7.8% $19 $6 $261.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2027Q4 10.9% $30 $10 $400.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2027Q4 10.9% $10 $3 $131.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2027Q1 7.8% $19 $6 $267.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2027Q1 7.8% $151 $50 $201

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% $181 20.7% $164 $54 $218 2027Q4 10.9% $182 $60 $2423.0% Project Operation: $45 $15 33.0% $59 20.7% $54 $18 $72 2027Q4 10.9% $60 $20 $793.0% Project Management $45 $15 33.0% $59 20.7% $54 $18 $72 2027Q4 10.9% $60 $20 $79

CONTRACT COST TOTALS: $1,962 $647 $2,610 $2,299 $759 $3,057 $2,499 $825 $3,324

Estimate Prepared: Program Year (Budget EC):Effective Price Level: Effective Price Level Date:

TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft

ESTIMATED COST PROJECT FIRST COST(Constant Dollar Basis) TOTAL PROJECT COST (FULLY FUNDED)Civil Works Work Breakdown Structure

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 14: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 4 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 2025 1-Oct-19 1 OCT 24

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 3

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2028Q4 11.8% $1,928 $636 $2,564

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________

CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% $1,978 $1,725 $569 $2,294 $1,928 $636 $2,564

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2028Q1 11.9% $40 $13 $530.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2028Q1 11.9% $10 $3 $131.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2028Q1 11.9% $20 $7 $271.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2028Q1 11.9% $20 $7 $270.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2028Q1 11.9% $10 $3 $131.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2028Q1 11.9% $20 $7 $271.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2028Q4 15.2% $31 $10 $410.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2028Q4 15.2% $10 $3 $141.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2028Q1 11.9% $20 $7 $277.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2028Q1 11.9% $157 $52 $208

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% $181 20.7% $164 $54 $218 2028Q4 15.2% $189 $62 $2523.0% Project Operation: $45 $15 33.0% $59 20.7% $54 $18 $72 2028Q4 15.2% $62 $20 $833.0% Project Management $45 $15 33.0% $59 20.7% $54 $18 $72 2028Q4 15.2% $62 $20 $83

CONTRACT COST TOTALS: $1,962 $647 $2,610 $2,299 $759 $3,057 $2,580 $851 $3,431

Effective Price Level: Effective Price Level Date:

TOTAL PROJECT COST (FULLY FUNDED)ESTIMATED COST PROJECT FIRST COST(Constant Dollar Basis)

Estimate Prepared: Program Year (Budget EC):

TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft

Civil Works Work Breakdown Structure

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 15: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 5 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 Program Year (Budget EC): 2025 1-Oct-19 Effective Price Level Date: 1 OCT 24 FULLY FUNDED PROJECT ESTIMATE

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 4

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2029Q4 15.1% $1,986 $655 $2,641

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________

CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% $1,978 $1,725 $569 $2,294 $1,986 $655 $2,641

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2029Q1 16.3% $42 $14 $560.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2029Q1 16.3% $10 $3 $141.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2029Q1 16.3% $21 $7 $281.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2029Q1 16.3% $21 $7 $280.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2029Q1 16.3% $10 $3 $141.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2029Q1 16.3% $21 $7 $281.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2029Q4 19.8% $32 $11 $430.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2029Q4 19.8% $11 $4 $141.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2029Q1 16.3% $21 $7 $287.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2029Q1 16.3% $163 $54 $217

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% $181 20.7% $164 $54 $218 2029Q4 19.8% $197 $65 $2623.0% Project Operation: $45 $15 33.0% $59 20.7% $54 $18 $72 2029Q4 19.8% $65 $21 $863.0% Project Management $45 $15 33.0% $59 20.7% $54 $18 $72 2029Q4 19.8% $65 $21 $86

CONTRACT COST TOTALS: $1,962 $647 $2,610 $2,299 $759 $3,057 $2,663 $879 $3,542

Effective Price Level:

Civil Works Work Breakdown Structure ESTIMATED COST PROJECT FIRST COST(Constant Dollar Basis) TOTAL PROJECT COST (FULLY FUNDED)

Estimate Prepared:

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 16: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 6 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 Program Year (Budget EC): 2025 1-Oct-19 Effective Price Level Date: 1 OCT 24 FULLY FUNDED PROJECT ESTIMATE

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 5

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2030Q4 18.6% $2,045 $675 $2,720

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________

CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% $1,978 $1,725 $569 $2,294 $2,045 $675 $2,720

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2030Q1 20.9% $43 $14 $580.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2030Q1 20.9% $11 $4 $141.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2030Q1 20.9% $22 $7 $291.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2030Q1 20.9% $22 $7 $290.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2030Q1 20.9% $11 $4 $141.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2030Q1 20.9% $22 $7 $291.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2030Q4 24.6% $34 $11 $450.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2030Q4 24.6% $11 $4 $151.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2030Q1 20.9% $22 $7 $297.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2030Q1 20.9% $169 $56 $225

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% $181 20.7% $164 $54 $218 2030Q4 24.6% $205 $68 $2723.0% Project Operation: $45 $15 33.0% $59 20.7% $54 $18 $72 2030Q4 24.6% $67 $22 $893.0% Project Management $45 $15 33.0% $59 20.7% $54 $18 $72 2030Q4 24.6% $67 $22 $89

CONTRACT COST TOTALS: $1,962 $647 $2,610 $2,299 $759 $3,057 $2,750 $908 $3,658

Estimate Prepared:Effective Price Level:

PROJECT FIRST COST(Constant Dollar Basis)Civil Works Work Breakdown Structure ESTIMATED COST TOTAL PROJECT COST (FULLY FUNDED)

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 17: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 7 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 Program Year (Budget EC): 2025 1-Oct-19 Effective Price Level Date: 1 OCT 24 FULLY FUNDED PROJECT ESTIMATE

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 6

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2031Q4 22.1% $2,107 $695 $2,802

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________

CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% $1,978 $1,725 $569 $2,294 $2,107 $695 $2,802

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2031Q1 25.8% $45 $15 $600.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2031Q1 25.8% $11 $4 $151.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2031Q1 25.8% $23 $7 $301.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2031Q1 25.8% $23 $7 $300.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2031Q1 25.8% $11 $4 $151.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2031Q1 25.8% $23 $7 $301.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2031Q4 29.5% $35 $12 $460.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2031Q4 29.5% $12 $4 $151.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2031Q1 25.8% $23 $7 $307.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2031Q1 25.8% $176 $58 $234

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% $181 20.7% $164 $54 $218 2031Q4 29.5% $213 $70 $2833.0% Project Operation: $45 $15 33.0% $59 20.7% $54 $18 $72 2031Q4 29.5% $70 $23 $933.0% Project Management $45 $15 33.0% $59 20.7% $54 $18 $72 2031Q4 29.5% $70 $23 $93

CONTRACT COST TOTALS: $1,962 $647 $2,610 $2,299 $759 $3,057 $2,840 $937 $3,777

Civil Works Work Breakdown Structure ESTIMATED COST PROJECT FIRST COST(Constant Dollar Basis)

Effective Price Level:

TOTAL PROJECT COST (FULLY FUNDED)

Estimate Prepared:

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 18: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 8 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 Program Year (Budget EC): 2025 1-Oct-19 Effective Price Level Date: 1 OCT 24 FULLY FUNDED PROJECT ESTIMATE

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 7

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2032Q4 25.8% $2,170 $716 $2,886

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________

CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% $1,978 $1,725 $569 $2,294 $2,170 $716 $2,886

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2032Q1 30.8% $47 $15 $620.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2032Q1 30.8% $12 $4 $161.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2032Q1 30.8% $23 $8 $311.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2032Q1 30.8% $23 $8 $310.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2032Q1 30.8% $12 $4 $161.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2032Q1 30.8% $23 $8 $311.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2032Q4 34.7% $36 $12 $480.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2032Q4 34.7% $12 $4 $161.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2032Q1 30.8% $23 $8 $317.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2032Q1 30.8% $183 $60 $244

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% $181 20.7% $164 $54 $218 2032Q4 34.7% $221 $73 $2943.0% Project Operation: $45 $15 33.0% $59 20.7% $54 $18 $72 2032Q4 34.7% $73 $24 $973.0% Project Management $45 $15 33.0% $59 20.7% $54 $18 $72 2032Q4 34.7% $73 $24 $97

CONTRACT COST TOTALS: $1,962 $647 $2,610 $2,299 $759 $3,057 $2,932 $968 $3,900

Effective Price Level:Estimate Prepared:

Civil Works Work Breakdown Structure ESTIMATED COST PROJECT FIRST COST(Constant Dollar Basis) TOTAL PROJECT COST (FULLY FUNDED)

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 19: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 9 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 Program Year (Budget EC): 2025 1-Oct-19 Effective Price Level Date: 1 OCT 24 FULLY FUNDED PROJECT ESTIMATE

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 8

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2033Q4 29.6% $2,235 $738 $2,972

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________

CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% 1,978 $1,725 $569 $2,294 $2,235 $738 $2,972

01 LANDS AND DAMAGES $0 $0 0.0% -$ 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2033Q1 36.0% $49 $16 $650.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2033Q1 36.0% $12 $4 $161.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2033Q1 36.0% $24 $8 $321.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2033Q1 36.0% $24 $8 $320.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2033Q1 36.0% $12 $4 $161.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2033Q1 36.0% $24 $8 $321.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2033Q4 40.2% $38 $12 $500.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2033Q4 40.2% $13 $4 $171.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2033Q1 36.0% $24 $8 $327.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2033Q1 36.0% $190 $63 $253

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% 181 20.7% $164 $54 $218 2033Q4 40.2% $230 $76 $3063.0% Project Operation: $45 $15 33.0% 59 20.7% $54 $18 $72 2033Q4 40.2% $75 $25 $1003.0% Project Management $45 $15 33.0% 59 20.7% $54 $18 $72 2033Q4 40.2% $75 $25 $100

CONTRACT COST TOTALS: $1,962 $647 2,610 $2,299 $759 $3,057 $3,028 $999 $4,027

PROJECT FIRST COST(Constant Dollar Basis) TOTAL PROJECT COST (FULLY FUNDED)

Estimate Prepared:

Civil Works Work Breakdown Structure ESTIMATED COST

Effective Price Level:

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 20: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 10 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 Program Year (Budget EC): 2025 1-Oct-19 Effective Price Level Date: 1 OCT 24 FULLY FUNDED PROJECT ESTIMATE

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 9

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2034Q4 33.4% $2,302 $760 $3,062

__________ __________ _________ ____________ _________ _________ __________ _________ _________ ________________

CONSTRUCTION ESTIMATE TOTALS: $1,487 $491 33.0% $1,978 $1,725 $569 $2,294 $2,302 $760 $3,062

01 LANDS AND DAMAGES $0 $0 0.0% $0 0.0% $0 $0 $0 0 0.0% $0 $0 $0

30 PLANNING, ENGINEERING & DESIGN2.0% Project Management $30 $10 33.0% $40 20.7% $36 $12 $48 2034Q1 41.6% $51 $17 $680.5% Planning & Environmental Compliance $7 $2 33.0% $10 20.7% $9 $3 $12 2034Q1 41.6% $13 $4 $171.0% Engineering & Design $15 $5 33.0% $20 20.7% $18 $6 $24 2034Q1 41.6% $25 $8 $341.0% Reviews, ATRs, IEPRs, VE $15 $5 33.0% $20 20.7% $18 $6 $24 2034Q1 41.6% $25 $8 $340.5% Life Cycle Updates (cost, schedule, risks) $7 $2 33.0% $10 20.7% $9 $3 $12 2034Q1 41.6% $13 $4 $171.0% Contracting & Reprographics $15 $5 33.0% $20 20.7% $18 $6 $24 2034Q1 41.6% $25 $8 $341.5% Engineering During Construction $22 $7 33.0% $30 20.7% $27 $9 $36 2034Q4 45.9% $39 $13 $520.5% Planning During Construction $7 $2 33.0% $10 20.7% $9 $3 $12 2034Q4 45.9% $13 $4 $171.0% Adaptive Management & Monitoring $15 $5 33.0% $20 20.7% $18 $6 $24 2034Q1 41.6% $25 $8 $347.8% Project Operations $116 $38 33.0% $154 20.7% $140 $46 $186 2034Q1 41.6% $198 $65 $264

31 CONSTRUCTION MANAGEMENT9.2% Construction Management $136 $45 33.0% $181 20.7% $164 $54 $218 2034Q4 45.9% $240 $79 $3193.0% Project Operation: $45 $15 33.0% $59 20.7% $54 $18 $72 2034Q4 45.9% $79 $26 $1053.0% Project Management $45 $15 33.0% $59 20.7% $54 $18 $72 2034Q4 45.9% $79 $26 $105

CONTRACT COST TOTALS: $1,962 $647 $2,610 $2,299 $759 $3,057 $3,127 $1,032 $4,159

PROJECT FIRST COST(Constant Dollar Basis) TOTAL PROJECT COST (FULLY FUNDED)Civil Works Work Breakdown Structure ESTIMATED COST

Estimate Prepared:Effective Price Level:

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 21: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

**** TOTAL PROJECT COST SUMMARY **** Printed:2/20/2020 Page 11 of 11

**** CONTRACT COST SUMMARY ****

PROJECT: TSP-Port of New Orleans Deepening-MAINTENANCE-50-ft DISTRICT: New Orleans District PREPARED: 2/7/2020LOCATION: New Orleans , Louisiana POC: CHIEF, COST ENGINEERING, John PetitbonThis Estimate reflects the scope and schedule in report; WRDA 2016, SECTION1202(d) 13 September 2017

29-Jan-19 Program Year (Budget EC): 2025 1-Oct-19 Effective Price Level Date: 1 OCT 24 FULLY FUNDED PROJECT ESTIMATE

WBS Civil Works COST CNTG CNTG TOTAL ESC COST CNTG TOTAL Mid-Point INFLATED COST CNTG FULLNUMBER Feature & Sub-Feature Description ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) Date (%) ($K) ($K) ($K)

A B C D E F G H I J P L M N OMaintenance Year 10 to 50

12 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2035Q4 37.4% $2,371 $782 $3,15312 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2036Q4 41.6% $2,442 $806 $3,24812 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2037Q4 45.8% $2,515 $830 $3,34612 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2038Q4 50.2% $2,591 $855 $3,44612 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2039Q4 54.7% $2,669 $881 $3,54912 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2040Q4 59.3% $2,749 $907 $3,65612 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2041Q4 64.1% $2,831 $934 $3,76512 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2042Q4 69.0% $2,916 $962 $3,87812 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2043Q4 74.1% $3,004 $991 $3,99512 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2044Q4 79.3% $3,094 $1,021 $4,11512 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2045Q4 84.7% $3,186 $1,052 $4,23812 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2046Q4 90.3% $3,282 $1,083 $4,36512 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2047Q4 96.0% $3,381 $1,116 $4,49612 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2048Q4 101.8% $3,482 $1,149 $4,63112 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2049Q4 107.9% $3,586 $1,184 $4,77012 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2050Q4 114.1% $3,694 $1,219 $4,91312 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2051Q4 120.6% $3,805 $1,256 $5,06012 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2052Q4 127.2% $3,919 $1,293 $5,21212 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2053Q4 134.0% $4,037 $1,332 $5,36912 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2054Q4 141.0% $4,158 $1,372 $5,53012 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2055Q4 148.2% $4,282 $1,413 $5,69612 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2056Q4 155.7% $4,411 $1,456 $5,86612 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2057Q4 163.4% $4,543 $1,499 $6,04212 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2058Q4 171.3% $4,679 $1,544 $6,22412 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2059Q4 179.4% $4,820 $1,591 $6,41012 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2060Q4 187.8% $4,964 $1,638 $6,60312 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2061Q4 196.4% $5,113 $1,687 $6,80112 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2062Q4 205.3% $5,267 $1,738 $7,00512 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2063Q4 214.5% $5,425 $1,790 $7,21512 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2064Q4 223.9% $5,588 $1,844 $7,43112 NAVIGATION PORTS & HARBORS $1,487 $491 33.0% $1,978 16.0% $1,725 $569 $2,294 2065Q4 233.6% $5,755 $1,899 $7,654

CONTRACT COST TOTALS: $46,097 $15,212 $61,309 $53,476 $17,647 $71,123 $118,558 $39,124 $157,682

Civil Works Work Breakdown Structure ESTIMATED COST

Estimate Prepared:Effective Price Level:

PROJECT FIRST COST(Constant Dollar Basis) TOTAL PROJECT COST (FULLY FUNDED)

Filename: TPCS-PONO-MAINT-TSP-29JAN2020.xlsxTPCS

Page 22: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

ABBREVIATED RISK ANALYSIS

CONSTRUCTION

Page 23: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Project (less than $40M):Project Development Stage/Alternative:

Risk Category: Meeting Date: 1/31/2020

Total Estimated Construction Contract Cost = 4,649,000$                  

CWWBS Feature of Work Estimated Cost % Contingency $ Contingency Total

01 LANDS AND DAMAGES Real Estate -$ 0% -$ -$

1 12 01 PORTS Mob/Demob 769,000$ 23% 179,823$ 948,823$

2 12 01 PORTS Dredging 3,880,000$ 35% 1,365,510$ 5,245,510$

3 -$ 0% -$ -$

4 -$ 0% -$ -$

5 -$ 0% -$ -$

6 -$ 0% -$ -$

7 -$ 0% -$ -$

8 -$ 0% -$ -$

9 -$ 0% -$ -$

10 -$ 0% -$ -$

11 -$ 0% -$ -$

12 All Other Remaining Construction Items -$ 0.0% 0% -$ -$

13 30 PLANNING, ENGINEERING, AND DESIGN Planning, Engineering, & Design 350,000$ 15% 52,500$ 402,500$

14 31 CONSTRUCTION MANAGEMENT Construction Management 225,000$ 25% 56,132$ 281,132$

XX FIXED DOLLAR RISK ADD (EQUALLY DISPERSED TO ALL, MUST INCLUDE JUSTIFICATION SEE BELOW) -$ KEEPKEEP TotalsKEEP Real Estate -$ 0% -$ -$ KEEP Total Construction Estimate 4,649,000$ 33% 1,545,333$ 6,194,333$ KEEP Total Planning, Engineering & Design 350,000$ 15% 52,500$ 402,500$ KEEP Total Construction Management 225,000$ 25% 56,132$ 281,132$ KEEPKEEP Total Excluding Real Estate 5,224,000$ 32% 1,653,965$ 6,877,965$ RANGE Base 50% 80%RANGE Confidence Level Range Estimate ($000's) $5,224k $6,216k $6,878kKEEP * 50% based on base is at 5% CL.

Fixed Dollar Risk Add: (Allows for additional risk to be added to the risk analsyis. Must include

justification. Does not allocate to Real Estate.

Abbreviated Risk AnalysisPort of New Orleans Deepening Study 50-ft DepthAlternative FormulationModerate Risk: Typical Project Construction Type

TSP-50-ft-ConstructionAlternative:

Page 24: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Port of New Orleans Deepening Study 50-ft Depth TSP-50-ft-ConstructionAlternative Formulation Risk RegisterAbbreviated Risk Analysis

Meeting Date: 31‐Jan‐20

Risk Element Feature of Work ConcernsPDT Discussions & Conclusions(Include logic & justification for choice of Likelihood & Impact)

Impact Likelihood Risk Level

ProjectManagement&ScopeGrowth Maximum Project Growth 75%

PS-1 Mob/Demob

• Potential for scope growth, added features? • Project accomplishes intent? • Funding Difficulties? • Sufficent Staffing/Support?

The quantity for mobilizations is set. The Contractor would mobilize one time to deliver all equipment and resources required to complete work. Project is normally occurring work for MVN. There is no project without funding, no risk.

Negligible Unlikely 0

PS-2 Dredging

• Potential for scope growth, added features? • Project accomplishes intent? • Funding Difficulties? • Sufficent Staffing/Support?

Dredging scope is agreed upon by the PDT and the nonfederal sponsor. The dredging scope is maximum with this alternative since the navigaiton channel is authorized to 50-ft. Funding stream shall be addressed in External Project Risk. Staffing is not an issue. Project is normally occurring work for MVN.

Marginal Unlikely 0

PS-3 0 Negligible Unlikely 0

PS-4 0 Negligible Unlikely 0

PS-5 0 Negligible Unlikely 0

PS-6 0 Negligible Unlikely 0

PS-7 0 Negligible Unlikely 0

PS-8 0 Negligible Unlikely 0

PS-9 0 Negligible Unlikely 0

PS-10 0 Negligible Unlikely 0

PS-11 0 Negligible Unlikely 0

PS-12 Remaining Construction Items Negligible Unlikely 0

Page 25: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

PS-13 Planning, Engineering, & Design

• Potential for scope growth, added features? • Project accomplishes intent? • Funding Difficulties? • Sufficent Staffing/Support?

No concerns. Project is normally occurring work for MVN Negligible Unlikely 0

PS-14 Construction Management

• Potential for scope growth, added features? • Project accomplishes intent? • Funding Difficulties? • Sufficent Staffing/Support?

If a scope change occurrs is would be minor time increase to the project. Project is normally occurring work for MVN. Since this depth is the maximum attainable no further change could occur.

Negligible Possible 0

AcquisitionStrategy Maximum Project Growth 30%

AS-1 Mob/Demob

• Contracting plan firmly established?• 8a or small business likely?• Requirement for subcontracting?• Accelerated schedule or harsh weather schedule?• High-risk acquisition limits competition, design/build?• Limited bid competition anticipated?• Bid schedule developed to reduce quantity risks?

Large business competitive solicitation. There is a very small chance of this being small business but is not likely to happen.

Marginal Possible 1

AS-2 Dredging

• Contracting plan firmly established?• 8a or small business likely?• Requirement for subcontracting?• Accelerated schedule or harsh weather schedule?• High-risk acquisition limits competition, design/build?• Limited bid competition anticipated?• Bid schedule developed to reduce quantity risks?

Contracting plan will be to lowest bidder open competition. There is an oppurtunity for a small business to bid and construct the project as a open competition project. The scarcity of equipment dictates that this contract be advertised as open cometition.

Moderate Possible 2

AS-3 0 Negligible Unlikely 0

AS-4 0 Negligible Unlikely 0

AS-5 0 Negligible Unlikely 0

AS-6 0 Negligible Unlikely 0

AS-7 0Negligible Unlikely 0

AS-8 0Negligible Unlikely 0

AS-9 0Negligible Unlikely 0

AS-10 0Negligible Unlikely 0

AS-11 0Negligible Unlikely 0

AS-12 Remaining Construction Items Negligible Unlikely 0

AS-13 Planning, Engineering, & Design

• Contracting plan firmly established?• 8a or small business likely?• Requirement for subcontracting?• Accelerated schedule or harsh weather schedule?• High-risk acquisition limits competition, design/build?• Limited bid competition anticipated?• Bid schedule developed to reduce quantity risks?

No concerns Negligible Unlikely 0

Page 26: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

AS-14 Construction Management

• Contracting plan firmly established?• 8a or small business likely?• Requirement for subcontracting?• Accelerated schedule or harsh weather schedule?• High-risk acquisition limits competition, design/build?• Limited bid competition anticipated?• Bid schedule developed to reduce quantity risks?

No concerns Negligible Unlikely 0

ConstructionElements Maximum Project Growth 25%

CON-1 Mob/Demob

• Accelerated schedule or harsh weather schedule? • High risk or complex construction elements, site access, in-water? • Water care and diversion plan? • Unique construction methods?• Special mobilization?• Special equipment or subcontractors needed?• Potential for construction modification and claims? Work is common to the MVN area.

Negligible Unlikely 0

CE-2 Dredging

• Accelerated schedule or harsh weather schedule? • High risk or complex construction elements, site access, in-water? • Water care and diversion plan? • Unique construction methods?• Special mobilization?• Special equipment or subcontractors needed?• Potential for construction modification and claims?

There is always a potentential for claims The work is within the Mississippi River New Orleans Port area. Rental equipment is used for surveying, crew boats, and towing vessels. All construction methods are common to MVN. The Port of New Orleans opinion is that there is a marginal chance of encountering an obstruction.

Marginal Possible 1

CE-3 0 Negligible Unlikely 0

CE-4 0 Negligible Unlikely 0

CE-5 0 Negligible Unlikely 0

CE-6 0 Negligible Unlikely 0

CE-7 0Negligible Unlikely 0

CE-8 0Negligible Unlikely 0

CE-9 0Negligible Unlikely 0

CE-10 0Negligible Unlikely 0

CE-11 0Negligible Unlikely 0

CE-12 Remaining Construction Items Negligible Unlikely 0

Page 27: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

CE-13 Planning, Engineering, & Design

• Accelerated schedule or harsh weather schedule? • High risk or complex construction elements, site access, in-water? • Water care and diversion plan? • Unique construction methods?• Special mobilization?• Special equipment or subcontractors needed?• Potential for construction modification and claims?

No concerns Negligible Unlikely 0

CE-14 Construction Management

• Accelerated schedule or harsh weather schedule? • High risk or complex construction elements, site access, in-water? • Water care and diversion plan? • Unique construction methods?• Special mobilization?• Special equipment or subcontractors needed?• Potential for construction modification and claims?

No concerns. Project is normally occurring work for MVN Marginal Possible 1

SpecialtyConstructionorFabrication Maximum Project Growth 65%

SC-1 Mob/Demob

• Atypical construction elements, unusual material or equipment manufactured or installed? • Confidence in constructibility or methodology? • One of a kind and confidence in fabrication and installation? • Ability to reasonably transport?• Risk of specialty equipment functioning first time? Testing?

Entire project is marine accesed and highway accessed for some of the disposal areas and BUDMAT. Nomrally occuring work for MVN.

Negligible Unlikely 0

SC-2

Dredging

• Atypical construction elements, unusual material or equipment manufactured or installed? • Confidence in constructibility or methodology? • One of a kind and confidence in fabrication and installation? • Ability to reasonably transport?• Risk of specialty equipment functioning first time? Testing?

Typical dredge work and disposal methods for the MVN area. Negligible Unlikely 0

SC-30 Negligible Unlikely 0

SC-40 Negligible Unlikely 0

SC-50 Negligible Unlikely 0

SC-60 Negligible Unlikely 0

SC-7 0Negligible Unlikely 0

SC-8 0Negligible Unlikely 0

SC-9 0Negligible Unlikely 0

SC-10 0Negligible Unlikely 0

SC-11 0Negligible Unlikely 0

SC-12Remaining Construction Items Negligible Unlikely 0

Page 28: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

SC-13

Planning, Engineering, & Design

• Atypical construction elements, unusual material or equipment manufactured or installed? • Confidence in constructibility or methodology? • One of a kind and confidence in fabrication and installation? • Ability to reasonably transport?• Risk of specialty equipment functioning first time? Testing?

No concerns. Project is normally occurring work for MVN Negligible Unlikely 0

SC-14

Construction Management

• Atypical construction elements, unusual material or equipment manufactured or installed? • Confidence in constructibility or methodology? • One of a kind and confidence in fabrication and installation? • Ability to reasonably transport?• Risk of specialty equipment functioning first time? Testing?

No concerns. Project is normally occurring work for MVN Negligible Unlikely 0

TechnicalDesign&Quantities Maximum Project Growth 30%

T-1 Mob/Demob

• Level of confidence based on design and assumptions? • Possibility for increased quantities due to loss, waste, or subsidence?• Appropriate methods applied to calculate quantities?• Sufficient investigations to develop quantities?• Quality control check applied? Mobilization will occur once. No risk for additional mobilizations.

Negligible Unlikely 0

T-2

Dredging

• Level of confidence based on design and assumptions? • Possibility for increased quantities due to loss, waste, or subsidence?• Appropriate methods applied to calculate quantities?• Sufficient investigations to develop quantities?• Quality control check applied?

Quantities were develooped from surveys of August 2019. No quantity is included above elevation -37.4 NAVD88 which is the maximum depth of maintenance dredging. Maintenance dredging is assumed to occur first. Due to the dynamics of the Mississippi River and dredging depths the current project could change the dredge quantities.

Moderate Possible 2

T-30 Negligible Unlikely 0

T-40 Negligible Unlikely 0

T-50 Negligible Unlikely 0

T-60 Negligible Unlikely 0

T-7 0Negligible Unlikely 0

T-8 0Negligible Unlikely 0

T-9 0Negligible Unlikely 0

T-10 0Negligible Unlikely 0

T-11 0Negligible Unlikely 0

T-12Remaining Construction Items Negligible Unlikely 0

Page 29: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

T-13

Planning, Engineering, & Design

• Level of confidence based on design and assumptions? • Possibility for increased quantities due to loss, waste, or subsidence?• Appropriate methods applied to calculate quantities?• Sufficient investigations to develop quantities?• Quality control check applied?

No concerns. Project is normally occurring work for MVN Negligible Unlikely 0

T-14

Construction Management

• Level of confidence based on design and assumptions? • Possibility for increased quantities due to loss, waste, or subsidence?• Appropriate methods applied to calculate quantities?• Sufficient investigations to develop quantities?• Quality control check applied?

If there is a quantity fluctuation then a revision to duration is possible. Project is normally occurring work for MVN Moderate Possible 2

CostEstimateAssumptions Maximum Project Growth 35%

EST-1 Mob/Demob

• Reliability and number of key quotes? • Assumptions related to prime and subcontractor markups/assignments?• Assumptions regarding crew, productivity, overtime?• Site accessibility, transport delays, congestion?• Overuse of Cost Book, lump sum, allowances?• Lack confidence on critical cost items?

Job site is in New Orleans area. Contact tugs are used in the MII estimate to facilitate hauling of equipment. Overtime is based upond avergaes for dredge companies. Typical work for MVN. The CEDEP for mobilization has been revised to reflect all crew and dredge plant movement in a more realistic fashion.

Moderate Unlikely 1

EST-2

Dredging

• Reliability and number of key quotes? • Assumptions related to prime and subcontractor markups/assignments?• Assumptions regarding crew, productivity, overtime?• Site accessibility, transport delays, congestion?• Overuse of Cost Book, lump sum, allowances?• Lack confidence on critical cost items?

A robust crew is described in the cost estimate working at conservative rates for this dredge area. This is based on historical data. Dredge running time is conservative but the risk for this will be addressed in EX-2 EXTERNAL RISK. Dredging is done as the prime contractor in this estimate. Mobilization tugs, crew boats and survey boats are rental equipment. The CEDEP developed by New Orleans Districts features 3 separate size tenders, anchor barges, skidder barges and fuel water barges in addition to previous inputs. The New Orleans District CEDEP also has insurance as a separate input and features full field office overhead. If dredge material is stiffer than anticipated a lower production rate may be needed. A stiff clay is currently assumed however somthing stiffer is possible but not likely. Borings have not been obtained however with our experience dredging in south louisiana a drastic change is not anticipated. Due to the depth greater than 40-ft and the lack of ladder pump some ineffecieny in production adds risk.

Moderate Possible 2

EST-30 Negligible Unlikely 0

EST-40 Negligible Unlikely 0

EST-50 Negligible Unlikely 0

EST-60 Negligible Unlikely 0

EST-7 0Negligible Unlikely 0

EST-8 0Negligible Unlikely 0

Page 30: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

EST-9 0Negligible Unlikely 0

EST-10 0Negligible Unlikely 0

EST-11 0Negligible Unlikely 0

EST-12Remaining Construction Items Negligible Unlikely 0

EST-13

Planning, Engineering, & Design

• Reliability and number of key quotes? • Assumptions related to prime and subcontractor markups/assignments?• Assumptions regarding crew, productivity, overtime?• Site accessibility, transport delays, congestion?• Overuse of Cost Book, lump sum, allowances?• Lack confidence on critical cost items?

No concerns with design. Negligible Unlikely 0

EST-14

Construction Management

• Reliability and number of key quotes? • Assumptions related to prime and subcontractor markups/assignments?• Assumptions regarding crew, productivity, overtime?• Site accessibility, transport delays, congestion?• Overuse of Cost Book, lump sum, allowances?• Lack confidence on critical cost items?

Time could be increased some due to stiffer materials or differing dredge sizes to accomplish the work Moderate Possible 2

ExternalProjectRisks Maximum Project Growth 40%

EX-1 Mob/Demob

• Potential for severe adverse weather? • Political influences, lack of support, obstacles?• Unanticipated inflations in fuel, key materials?• Potential for market volatility impacting competition, pricing?• Funding Constraints

To the PDT's knowledge there are no environmental windows affecting the project. Fuel is a volatile commodity and swings in prices occur annually. The river must be in a dropping mode before construction/maintenance can begin. It is logical to wait for the river to drop to accomplish minimal maintenance dredging first before construction.

Moderate Possible 2

EX-2 Dredging

• Potential for severe adverse weather? • Political influences, lack of support, obstacles?• Unanticipated inflations in fuel, key materials?• Potential for market volatility impacting competition, pricing?• Funding Constraints

Conservative running times are used for the dredging cost. Minimal impact. There is an opportunity for inflations in fuel or a disaster somewhere else impacting availability. Adverse weather is a possibility however the work location is in safe harbor. Funding constraints affect when the project occurs however not a major driver with cost risk. Funding stream is not a constraint, uncertainty or unpredictability of appropriation. This affects the schedule. The river must be in a dropping mode before construction/maintenance can begin. It is logical to wait for the river to drop to accomplish minimal maintenance dredging first before construction. Since the New Orleans Harbor is a vital resource to the nation funding is usually forethcoming. The dollar amount for the construction is small therefore assisting the projects approval.

Moderate Possible 2

EX-3 0 Negligible Unlikely 0

EX-4 0 Negligible Unlikely 0

EX-5 0 Negligible Unlikely 0

Page 31: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

EX-6 0 Negligible Unlikely 0

EX-7 0Negligible Unlikely 0

EX-8 0Negligible Unlikely 0

EX-9 0Negligible Unlikely 0

EX-10 0Negligible Unlikely 0

EX-11 0Negligible Unlikely 0

EX-12 Remaining Construction Items Negligible Unlikely 0

EX-13 Planning, Engineering, & Design

• Potential for severe adverse weather? • Political influences, lack of support, obstacles?• Unanticipated inflations in fuel, key materials?• Potential for market volatility impacting competition, pricing?• Funding Constraints

No conerns. Negligible Unlikely 0

EX-14 Construction Management

• Potential for severe adverse weather? • Political influences, lack of support, obstacles?• Unanticipated inflations in fuel, key materials?• Potential for market volatility impacting competition, pricing?• Funding Constraints

No concers. Negligible Unlikely 0

Page 32: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

ABBREVIATED RISK ANALYSIS

MAINTENANCE

Page 33: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Project (less than $40M):Project Development Stage/Alternative:

Risk Category: Meeting Date: 1/31/2020

Total Estimated Construction Contract Cost = 1,487,196$                  

CWWBS Feature of Work Estimated Cost % Contingency $ Contingency Total

01 LANDS AND DAMAGES Real Estate -$ 0% -$ -$

1 12 01 PORTS Mob/Demob 382,500$ 23% 89,444$ 471,944$

2 12 01 PORTS Dredging 1,104,696$ 41% 449,486$ 1,554,182$

3 -$ 0% -$ -$

4 -$ 0% -$ -$

5 -$ 0% -$ -$

6 -$ 0% -$ -$

7 -$ 0% -$ -$

8 -$ 0% -$ -$

9 -$ 0% -$ -$

10 -$ 0% -$ -$

11 -$ 0% -$ -$

12 All Other Remaining Construction Items -$ 0.0% 0% -$ -$

13 30 PLANNING, ENGINEERING, AND DESIGN Planning, Engineering, & Design 250,000$ 15% 37,500$ 287,500$

14 31 CONSTRUCTION MANAGEMENT Construction Management 225,000$ 27% 61,515$ 286,515$

XX FIXED DOLLAR RISK ADD (EQUALLY DISPERSED TO ALL, MUST INCLUDE JUSTIFICATION SEE BELOW) -$ KEEPKEEP TotalsKEEP Real Estate -$ 0% -$ -$ KEEP Total Construction Estimate 1,487,196$ 36% 538,930$ 2,026,126$ KEEP Total Planning, Engineering & Design 250,000$ 15% 37,500$ 287,500$ KEEP Total Construction Management 225,000$ 27% 61,515$ 286,515$ KEEPKEEP Total Excluding Real Estate 1,962,196$ 33% 637,944$ 2,600,140$ RANGE Base 50% 80%RANGE Confidence Level Range Estimate ($000's) $1,962k $2,345k $2,600kKEEP * 50% based on base is at 5% CL.

Fixed Dollar Risk Add: (Allows for additional risk to be added to the risk analsyis. Must include

justification. Does not allocate to Real Estate.

Abbreviated Risk AnalysisPort of New Orleans Deepening Study 50-ft DepthAlternative FormulationModerate Risk: Typical Project Construction Type

TSP-50-FT-MaintenanceAlternative:

Page 34: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

Port of New Orleans Deepening Study 50-ft Depth TSP-50-FT-MaintenanceAlternative Formulation Risk RegisterAbbreviated Risk Analysis

Meeting Date: 31‐Jan‐20

Risk Element Feature of Work ConcernsPDT Discussions & Conclusions(Include logic & justification for choice of Likelihood & Impact)

Impact Likelihood Risk Level

ProjectManagement&ScopeGrowth Maximum Project Growth 75%

PS-1 Mob/Demob

• Potential for scope growth, added features? • Project accomplishes intent? • Funding Difficulties? • Sufficent Staffing/Support?

The quantity for mobilizations is set. The Contractor would mobilize one time to deliver all equipment and resources required to complete work. Project is normally occurring work for MVN. There is no project without funding, no risk. The cost for this mobilization shall be shared with outher dredging areas in the harbor, therefore mobilization cost is cut in half, this is a conservative approach.

Negligible Unlikely 0

PS-2 Dredging

• Potential for scope growth, added features? • Project accomplishes intent? • Funding Difficulties? • Sufficent Staffing/Support?

Dredging scope is agreed upon by the PDT and the nonfederal sponsor. The dredging scope is maximum with this alternative since the navigaiton channel is authorized to 50-ft. Funding stream shall be addressed in External Project Risk. Staffing is not an issue. Project is normally occurring work for MVN.

Marginal Unlikely 0

PS-3 0 Negligible Unlikely 0

PS-4 0 Negligible Unlikely 0

PS-5 0 Negligible Unlikely 0

PS-6 0 Negligible Unlikely 0

PS-7 0 Negligible Unlikely 0

PS-8 0 Negligible Unlikely 0

PS-9 0 Negligible Unlikely 0

PS-10 0 Negligible Unlikely 0

PS-11 0 Negligible Unlikely 0

PS-12 Remaining Construction Items Negligible Unlikely 0

Page 35: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

PS-13 Planning, Engineering, & Design

• Potential for scope growth, added features? • Project accomplishes intent? • Funding Difficulties? • Sufficent Staffing/Support?

No concerns. Project is normally occurring work for MVN Negligible Unlikely 0

PS-14 Construction Management

• Potential for scope growth, added features? • Project accomplishes intent? • Funding Difficulties? • Sufficent Staffing/Support?

If a scope change occurrs is would be minor time increase to the project. Project is normally occurring work for MVN. Since this depth is the maximum attainable no further change could occur.

Negligible Possible 0

AcquisitionStrategy Maximum Project Growth 30%

AS-1 Mob/Demob

• Contracting plan firmly established?• 8a or small business likely?• Requirement for subcontracting?• Accelerated schedule or harsh weather schedule?• High-risk acquisition limits competition, design/build?• Limited bid competition anticipated?• Bid schedule developed to reduce quantity risks?

Large business competitive solicitation. There is a very small chance of this being small business but is not likely to happen.

Marginal Possible 1

AS-2 Dredging

• Contracting plan firmly established?• 8a or small business likely?• Requirement for subcontracting?• Accelerated schedule or harsh weather schedule?• High-risk acquisition limits competition, design/build?• Limited bid competition anticipated?• Bid schedule developed to reduce quantity risks?

Contracting plan will be to lowest bidder open competition. There is an oppurtunity for a small business to bid and construct the project as a open competition project. A small buisiness adds 10% to the large buisness bidders. The New Orleans Harbor is fairly difficult for a small buisness to maintain however not impossible. The scarcity of equipment dictates that this contract be advertised as open cometition.

Marginal Possible 1

AS-3 0 Negligible Unlikely 0

AS-4 0 Negligible Unlikely 0

AS-5 0 Negligible Unlikely 0

AS-6 0 Negligible Unlikely 0

AS-7 0Negligible Unlikely 0

AS-8 0Negligible Unlikely 0

AS-9 0Negligible Unlikely 0

AS-10 0Negligible Unlikely 0

AS-11 0Negligible Unlikely 0

AS-12 Remaining Construction Items Negligible Unlikely 0

Page 36: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

AS-13 Planning, Engineering, & Design

• Contracting plan firmly established?• 8a or small business likely?• Requirement for subcontracting?• Accelerated schedule or harsh weather schedule?• High-risk acquisition limits competition, design/build?• Limited bid competition anticipated?• Bid schedule developed to reduce quantity risks?

No concerns Negligible Unlikely 0

AS-14 Construction Management

• Contracting plan firmly established?• 8a or small business likely?• Requirement for subcontracting?• Accelerated schedule or harsh weather schedule?• High-risk acquisition limits competition, design/build?• Limited bid competition anticipated?• Bid schedule developed to reduce quantity risks?

No concerns Negligible Unlikely 0

ConstructionElements Maximum Project Growth 25%

CON-1 Mob/Demob

• Accelerated schedule or harsh weather schedule? • High risk or complex construction elements, site access, in-water? • Water care and diversion plan? • Unique construction methods?• Special mobilization?• Special equipment or subcontractors needed?• Potential for construction modification and claims? Work is common to the MVN area.

Negligible Unlikely 0

CE-2 Dredging

• Accelerated schedule or harsh weather schedule? • High risk or complex construction elements, site access, in-water? • Water care and diversion plan? • Unique construction methods?• Special mobilization?• Special equipment or subcontractors needed?• Potential for construction modification and claims?

There is always a potentential for claims The work is within the Mississippi River New Orleans Port area. Rental equipment is used for surveying, crew boats, and towing vessels. All construction methods are common to MVN. Modifications are very non existant in the harbor because of the contract base and option hours structure.

Marginal Unlikely 0

CE-3 0 Negligible Unlikely 0

CE-4 0 Negligible Unlikely 0

CE-5 0 Negligible Unlikely 0

CE-6 0 Negligible Unlikely 0

CE-7 0Negligible Unlikely 0

CE-8 0Negligible Unlikely 0

CE-9 0Negligible Unlikely 0

CE-10 0Negligible Unlikely 0

CE-11 0Negligible Unlikely 0

CE-12 Remaining Construction Items Negligible Unlikely 0

Page 37: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

CE-13 Planning, Engineering, & Design

• Accelerated schedule or harsh weather schedule? • High risk or complex construction elements, site access, in-water? • Water care and diversion plan? • Unique construction methods?• Special mobilization?• Special equipment or subcontractors needed?• Potential for construction modification and claims?

No concerns Negligible Unlikely 0

CE-14 Construction Management

• Accelerated schedule or harsh weather schedule? • High risk or complex construction elements, site access, in-water? • Water care and diversion plan? • Unique construction methods?• Special mobilization?• Special equipment or subcontractors needed?• Potential for construction modification and claims?

No concerns. Project is normally occurring work for MVN Marginal Unlikely 0

SpecialtyConstructionorFabrication Maximum Project Growth 65%

SC-1 Mob/Demob

• Atypical construction elements, unusual material or equipment manufactured or installed? • Confidence in constructibility or methodology? • One of a kind and confidence in fabrication and installation? • Ability to reasonably transport?• Risk of specialty equipment functioning first time? Testing?

Entire project is marine accesed and highway accessed for some of the disposal areas and BUDMAT. Nomrally occuring work for MVN.

Negligible Unlikely 0

SC-2

Dredging

• Atypical construction elements, unusual material or equipment manufactured or installed? • Confidence in constructibility or methodology? • One of a kind and confidence in fabrication and installation? • Ability to reasonably transport?• Risk of specialty equipment functioning first time? Testing?

Typical dredge work and disposal methods for the MVN area. Negligible Unlikely 0

SC-30 Negligible Unlikely 0

SC-40 Negligible Unlikely 0

SC-50 Negligible Unlikely 0

SC-60 Negligible Unlikely 0

SC-7 0Negligible Unlikely 0

SC-8 0Negligible Unlikely 0

SC-9 0Negligible Unlikely 0

SC-10 0Negligible Unlikely 0

SC-11 0Negligible Unlikely 0

SC-12Remaining Construction Items Negligible Unlikely 0

Page 38: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

SC-13

Planning, Engineering, & Design

• Atypical construction elements, unusual material or equipment manufactured or installed? • Confidence in constructibility or methodology? • One of a kind and confidence in fabrication and installation? • Ability to reasonably transport?• Risk of specialty equipment functioning first time? Testing?

No concerns. Project is normally occurring work for MVN Negligible Unlikely 0

SC-14

Construction Management

• Atypical construction elements, unusual material or equipment manufactured or installed? • Confidence in constructibility or methodology? • One of a kind and confidence in fabrication and installation? • Ability to reasonably transport?• Risk of specialty equipment functioning first time? Testing?

No concerns. Project is normally occurring work for MVN Negligible Unlikely 0

TechnicalDesign&Quantities Maximum Project Growth 30%

T-1 Mob/Demob

• Level of confidence based on design and assumptions? • Possibility for increased quantities due to loss, waste, or subsidence?• Appropriate methods applied to calculate quantities?• Sufficient investigations to develop quantities?• Quality control check applied? Mobilization will occur once. No risk for additional mobilizations.

Negligible Unlikely 0

T-2

Dredging

• Level of confidence based on design and assumptions? • Possibility for increased quantities due to loss, waste, or subsidence?• Appropriate methods applied to calculate quantities?• Sufficient investigations to develop quantities?• Quality control check applied?

Due to the dynamics of the Mississippi River depths deeper than the current project could change the maintenace dredge quantities slightly more than what is currently assumed. The dredge quantity for maintenance dredging in the harbor can vary 60%.

Significant Likely 4

T-30 Negligible Unlikely 0

T-40 Negligible Unlikely 0

T-50 Negligible Unlikely 0

T-60 Negligible Unlikely 0

T-7 0Negligible Unlikely 0

T-8 0Negligible Unlikely 0

T-9 0Negligible Unlikely 0

T-10 0Negligible Unlikely 0

T-11 0Negligible Unlikely 0

T-12Remaining Construction Items Negligible Unlikely 0

Page 39: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

T-13

Planning, Engineering, & Design

• Level of confidence based on design and assumptions? • Possibility for increased quantities due to loss, waste, or subsidence?• Appropriate methods applied to calculate quantities?• Sufficient investigations to develop quantities?• Quality control check applied?

No concerns. Project is normally occurring work for MVN Negligible Unlikely 0

T-14

Construction Management

• Level of confidence based on design and assumptions? • Possibility for increased quantities due to loss, waste, or subsidence?• Appropriate methods applied to calculate quantities?• Sufficient investigations to develop quantities?• Quality control check applied?

If there is a quantity fluctuation then a revision to duration is possible. Project is normally occurring work for MVN but is not a large impact to schedule.

Moderate Possible 2

CostEstimateAssumptions Maximum Project Growth 35%

EST-1 Mob/Demob

• Reliability and number of key quotes? • Assumptions related to prime and subcontractor markups/assignments?• Assumptions regarding crew, productivity, overtime?• Site accessibility, transport delays, congestion?• Overuse of Cost Book, lump sum, allowances?• Lack confidence on critical cost items?

Job site is in New Orleans area. Contact tugs are used in the MII estimate to facilitate hauling of equipment. Overtime is based upond avergaes for dredge companies. Typical work for MVN. The CEDEP for mobilization has been revised to reflect all crew and dredge plant movement in a more realistic fashion.

Moderate Unlikely 1

EST-2

Dredging

• Reliability and number of key quotes? • Assumptions related to prime and subcontractor markups/assignments?• Assumptions regarding crew, productivity, overtime?• Site accessibility, transport delays, congestion?• Overuse of Cost Book, lump sum, allowances?• Lack confidence on critical cost items?

A robust crew is described in the cost estimate working at conservative rates for this dredge area. This is based on historical data. Dredge running time is conservative but the risk for this will be addressed in EX-2 EXTERNAL RISK. Dredging is done as the prime contractor in this estimate. Mobilization tugs, crew boats and survey boats are rental equipment. The CEDEP developed by New Orleans Districts features 3 separate size tenders, anchor barges, skidder barges and fuel water barges in addition to previous inputs. The New Orleans District CEDEP also has insurance as a separate input and features full field office overhead. Because of the deeper depth fine tuning the pay efficiency may occur increasing cost initially.

Moderate Possible 2

EST-30 Negligible Unlikely 0

EST-40 Negligible Unlikely 0

EST-50 Negligible Unlikely 0

EST-60 Negligible Unlikely 0

EST-7 0Negligible Unlikely 0

EST-8 0Negligible Unlikely 0

EST-9 0Negligible Unlikely 0

EST-10 0Negligible Unlikely 0

Page 40: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

EST-11 0Negligible Unlikely 0

EST-12Remaining Construction Items Negligible Unlikely 0

EST-13

Planning, Engineering, & Design

• Reliability and number of key quotes? • Assumptions related to prime and subcontractor markups/assignments?• Assumptions regarding crew, productivity, overtime?• Site accessibility, transport delays, congestion?• Overuse of Cost Book, lump sum, allowances?• Lack confidence on critical cost items?

No concerns with design. Negligible Unlikely 0

EST-14

Construction Management

• Reliability and number of key quotes? • Assumptions related to prime and subcontractor markups/assignments?• Assumptions regarding crew, productivity, overtime?• Site accessibility, transport delays, congestion?• Overuse of Cost Book, lump sum, allowances?• Lack confidence on critical cost items?

Verying dredge sizes with different capabilities can accomplish this maintenance dredging. A fluctuation in schedule will occur Moderate Likely 3

ExternalProjectRisks Maximum Project Growth 40%

EX-1 Mob/Demob

• Potential for severe adverse weather? • Political influences, lack of support, obstacles?• Unanticipated inflations in fuel, key materials?• Potential for market volatility impacting competition, pricing?• Funding Constraints

To the PDT's knowledge there are no environmental windows affecting the project. Fuel is a volatile commodity and swings in prices occur annually. The river must be in a dropping mode before maintenance can begin. It is logical to wait for the river to drop to accomplish minimal maintenance dredging first before construction.

Moderate Possible 2

EX-2 Dredging

• Potential for severe adverse weather? • Political influences, lack of support, obstacles?• Unanticipated inflations in fuel, key materials?• Potential for market volatility impacting competition, pricing?• Funding Constraints

Conservative running times are used for the dredging cost. Minimal impact. There is an opportunity for inflations in fuel or a disaster somewhere else impacting availability. Adverse weather is a possibility however the work location is in safe harbor. Funding constraints affect when the project occurs however not a major driver with cost risk. Funding stream is not a constraint, uncertainty or unpredictability of appropriation. This affects the schedule. The river must be in a dropping mode before construction/maintenance can begin. It is logical to wait for the river to drop to accomplish minimal maintenance dredging first before construction. Since the New Orleans Harbor is a vital resource to the nation funding is usually forethcoming. The dollar amount for the construction is small therefore assisting the projects approval.

Moderate Possible 2

EX-3 0 Negligible Unlikely 0

EX-4 0 Negligible Unlikely 0

EX-5 0 Negligible Unlikely 0

EX-6 0 Negligible Unlikely 0

EX-7 0Negligible Unlikely 0

Page 41: Revised Annex 6 Cost Engineering: TSP March 2020 6_Cost Engineerin… · Revised Annex 6 Cost Engineering: TSP March 2020 . M-CACES . Print Date Thu 20 February 2020 U.S. Army Corps

EX-8 0Negligible Unlikely 0

EX-9 0Negligible Unlikely 0

EX-10 0Negligible Unlikely 0

EX-11 0Negligible Unlikely 0

EX-12 Remaining Construction Items Negligible Unlikely 0

EX-13 Planning, Engineering, & Design

• Potential for severe adverse weather? • Political influences, lack of support, obstacles?• Unanticipated inflations in fuel, key materials?• Potential for market volatility impacting competition, pricing?• Funding Constraints

No conerns. Negligible Unlikely 0

EX-14 Construction Management

• Potential for severe adverse weather? • Political influences, lack of support, obstacles?• Unanticipated inflations in fuel, key materials?• Potential for market volatility impacting competition, pricing?• Funding Constraints

No concers. Negligible Unlikely 0