revised draft ammendment to irs t29 mar13
TRANSCRIPT
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
1/11
Proposed changes in IRS-T-29-2000
6.1.1 On receipt of permission for casting of prototypes, the manufacturer shall
then give 15 days notice to inspecting authority for witnessing of melting
and pouring for casting of prototypes. The witnessing of melting and
pouring shall be mandatory for casting of prototypes. However, for regularproduction, if inspecting official is not present during melting and pouring,
the manufacturer may go ahead with the casting keeping records and
samples as indicated in Clause 9.
6.2.2. Solidity Tests:
10%of the prototype castings subject to a minimum of one casting of each
type shall be selected for sectioning at seven locations preferably by
abrasive cutter as mentioned in Clause 5.2 above. Each sectioned face on
examination, shall not show a total defective area of more than 2% of the
cross-sectional area. The defect shall not be clustered at any particular
location and shall be uniformly distributed throughout. Defect within
10mm from the surface and defects connected with the outside and presence
of cracks/hot tears shall be cause for rejection. Hardness of the sectioned
faces shall be taken at the center of the thick section. Dye-penetrant test
shall be carried out on sectioned faces for detection of shrinkage and
chequered cracks.
This test shall be carried out once in two years from the clearance ofprototype or completion of 1000 CMS Crossings satisfactorily whichever is
earlier. After clearance of prototype, this test shall be carried out for each
design along with reassessment or on completion of every 1000 CMS
crossings satisfactorily whichever is earlier.
6.2.4
After solidity test and radiographic examination have been certified as
satisfactory, the firm will prepare a document mentioning parameters
(methoding size, shape and location of runners, risers and ingates, moulding
practice, source and properties of prepared sand and metal tapping and
pouring parameters) which gave satisfactory results. This document will be
countersigned by representative of RDSO. Inspectors will be free to verify
the parameters which were used during solidity test and which had been
countersigned by RDSO representative, so as to ensure the consistency of
foundry practice. The solidity test shall be carried out physically in the
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
2/11
presence of RDSO representative at least once in a year as a regular
measure.
7.6.7 The CMS Crossings are prone to damage due to improper handling and
stacking prior to Heat treatment process. The crossings therefore must be
handled with due care avoiding jerks, impacts, hitting with metal surface
and improper support during lifting and placement. While placement of
crossings care must be taken to avoid metal to metal contact by using
wooden separators of adequate size.
7.7.1 All crossings along with relevant test bars carrying metal tag shall suitably
be heat-treated to render them tough. It shall be ensured that impression
insignia on the metal tag given by inspecting official is not defaced even
after heat treatment and shot blasting to facilitate inspecting officials in
identifying the test bar.
Heat treatment shall consist of uniform heating of the crossing to a suitable
temperature holding it at that temperature till uniformly heated throughout
and quenching in water, within 60 seconds from a minimum temperature of
10500C . The crossing should be kept in the quenching tank in head down
manner. The initial temperature of water in the quenching tank shall be less
than or equal to 300C and should not rise by more than 100C during and
immediately after quenching of crossing. Water in quenching tank shall be
agitated and circulated properly and a continuous temperature measuringsystem should be installed to record before and after quenching temperature
of tank for each heat treated batches of crossings. The recording of
temperature should be kept preserved for checking of inspecting officials.
7.7.2 The identification mark from the metal tag along with insignia of inspecting
official shall be transferred on the test bar in the presence of the inspecting
official.
9. INSPECTION
9.1 The CMS crossing is related to the public safety in the railway transit. The
process of manufacture is most intricate both from the foundry and
metallurgical point of view. Considering the basic characteristic of the steel
i.e. the thermal sensitivity, low diathermic character, mould metal reactivity of
the steel, the work hardening and high shrinkage characteristics of the steel,
rigorous inspection (both metallurgical and dimensional) at different stages of
manufacture shall be carried out to ensure the quality of product as detailed
herein.
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
3/11
9.1.1. For suppliers who have not completed mandatory quantity of 100 nos of
crossing of each design ( 1in 8.5 52kg & 60 kg,1 in 12 52 kg &60 kg),
subject to total of 500 Nos covering all designs, the inspection of the firm will
be considered as Developmental and shall be carried out as per offer memo
mentioned in Appendix II. The cases of special layouts will be considered
separately.9.1.2 For suppliers who have completed mandatory quantity of minimum 100 nos
of crossing of each design ( 1in 8.5 52kg & 60 kg,1 in 12 52 kg &60 kg),
subject to total of at least of 500 Nos, and have achieved annual (financial
year) rejection rate less than or equal to 5% the inspection of the inspecting
official will be considered as Normal production and shall be carried out as
per offer memo mentioned in Appendix IIA. In case cumulative rejection rate
compiled once a year i.e. in April, of a suppliers becomes more than 5% ,the
inspection will be reverted to as per offer memo given in Appendix-II. Railway
shall be free to revert the inspection of any design or all the designs of CMS
crossing to as per offer memo given in Appendix-II based on the rejection rate
and/or field performance even prior to the above scheduled compilation in
April every year.
9.2. CHEMICAL COMPOSITION
9.2.1 For Developmental Inspection:
a. The manufacturers shall intimate the inspecting authority well in advanceso as to enable him to witness sampling of molten steel at different stages
for chemical analysis and shall furnish details of charge, pouringtemperature etc. The witnessing of melting and pouring shall be mandatory
for the casting of prototypes (Para 6.1.1). For regular production (i.e.
production after clearance of prototypes) under development inspection
category (Para 9.1.1), the inspecting official will advise the firm ,if he
desires to witness pouring, if required. In case, pouring is not witnessed
then the chemical composition will be verified by testing of lug sample in
presence of by the inspecting official as provided for in offer memo at
Annexure II & IIA
b. Portions of different bath samples (BT, BP & EP) should be preserved in
two sealed envelopes. These envelopes will be jointly sealed if RDSO
official decides to witness to pouring of heat. One of the sealed envelopes
containing above samples shall be handed over to the inspecting authority
on demand during the stage inspection of casting. These samples shall be
preserved till three months after issue of IC (Inspection Certificate).
c. Integral test bars are to be cast along with the casting as per Cl.No:12.1.1.
The parting of the integral test bars should be witnessed by the inspecting
official.
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
4/11
9.2.2 For Normal production Inspection
The manufacturers shall carryout sampling of molten steel at different
stages for chemical analysis and shall furnish details of charge, pouring
temperature etc. while offering for inspection at Stage I. Separation of
Integral test bar shall be done only after heat treatment in presence of
inspecting official. Chemical analysis on lug/test bar shall be done in
presence of inspecting official only. If inspecting official desires to witnessthe pouring of casting, facility as per Para 9.2.1(b) should be extended by
the manufacturer. Integral test bars are to be cast along with the casting as
per Cl.No:12.1.1.
.
9.2.3 The test results shall be presented to the Inspecting Officials for cross check
before Stage-I inspection as per Clause 9.4.2.
9.3 IDENTIFICATION OF CAST AND CORRELATION OF HEAT NUMBERS
9.3.1 The castings shall bear manufacturers identification marks, drawingnumber, serial number and month and year of cast and date of cast. A
register shall be maintained by the manufacturer correlating the casting
serial number and heat number and register shall be produced to the
Inspecting Authority for their verification on demand.
9.4 STAGES OF INSPECTION
9.4.1 Inspection plan shall be targeted to cover the following four stages. The
firm shall keep all the internal inspection records for all the stages as
mentioned below and submit it to the inspecting official. Inspection by the
inspecting official shall be planned as per corresponding offer memo ( as
mentioned in Appendix II & IIA) so that verification/inspection of quality
parameters involving all the following stages are covered completely.
Stage I: After knockout, oxy-cutting, fettling cleaning, shot blasting etc.
Stage- II: After heat-treatment and shot blasting etc.
Stage III: After removal / rectification of defects and straightening
Stage IV: After final finishing prior to final acceptance
9.4.2.: For developmental Inspection:
Inspection of Prototypes and inspection of further quantity manufactured
against furtherpurchase orders is to be carried out as per the Format of
seven offer memos (Offer Memo No: 1 to 7) given in Appendix-II.
However, on achieving the desired level of consistency in quality
measured in terms of rejection rate after manufacturing of minimum
mandatory quantity as mentioned in para 9.1.2 i.e. less than 5% of
cumulative rejection rate during manufacture and supply of at least 500
CMS including minimum 100 CMS Crossing of each design, the reduction
in stages of inspection can be permitted as mentioned for normal inspection
in Para 9.4.3
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
5/11
Sr.no Stage of
Inspectio
n
Offer memo no
of Annexure II
to be presented
by firms
Quality In
charge to RDSOinspecting
official by the
firm
Condition for signing the offer memo
by RDSO inspecting official.
1 Stage-I Offer Memo 1 After witnessing pouring and
confirming satisfactory chemistry by
witnessing molten steel sample testing
and observation of temperature during
various stage of casting
Offer Memo 2 After demoulding, and stamping of
integral test bars and verification of
chemical composition of integral test
bar, in case witnessing of pouring not
done earlier
Offer Memo 3 After fettling, shot blasting and
cleaning and observing satisfactory
dimension and surface quality.
2 Stage-II Offer Memo 4 After satisfactory heat treatment and
shot blasting, satisfactory surface and
gross dimension checking .3 Stage-III Offer Memo 5 Identifying surface defects and
permitting them for repairs, if
admissible, Testing of integral test bars
for impact bend test, Hardness test,
Grain size microstructure test.
Permitting for machining.
Offer Memo 6 After satisfactory removal of defects
after welding on permitted location,
No unauthorized welding, satisfactorymachining, Straightening, Dye
penetration test. Magnetic test,
Satisfactory Radiography test results
and Gross dimensional check.
4 Stage
-IV
Offer Memo 7 1. Checking satisfactory
Straightening including DPT.
2. Detailed Dimension checking
using approved gauges.
3. Satisfactory Quality (dimension,
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
6/11
metallurgical)of
components/fittings being
supplied with CMS Crossing.
4. Satisfactory checking of all
records pertaining to previous
inspections.
9.4.3 For Normal Production Inspection:
Inspection of above stages are to be carried out as per the Format of three
offer memos (Offer Memo No: I, IA & II, 1, 2, 2A & 3) given in Appendix-
II A. The consistency of the Quality of product of a firm shall be reviewed
over a period of calendar year and if cumulative rejection rate is found
beyond 5 % then the firm may be considered for resorting to inspection as
per seven offer memos as mentioned in 9.4.2.
Sr.no
Stage ofInspectio
n
Offer memo noof Annexure
IIA to be
presented by
firms Quality In
charge to RDSO
inspecting
official by the
firm
Condition for signing the offer memoby RDSO inspecting official.
1 Stage-I Offer Memo 1 1. After verifying chemistry bywitnessing testing of lug sample.
2. After demoulding and stamping
of integral test bars.
3. After fettling, shot blasting and
cleaning and observing
satisfactory dimension and surface
Quality.
2 Stage-II Offer memo 2 1. After satisfactory heat treatment
and shot blasting, satisfactory
surface and gross dimensionchecking . After satisfactory heat
treatment and stamping of integral
test bars.
2. Testing of integral test bars for
impact bend test, Hardness test,
Grain size microstructure test.
Permitting for machining
Checking satisfactory
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
7/11
Straightening including DPT.
3. Satisfactory
Quality(dimension,
metallurgical)of
components/fittings being supplied
with CMS Crossing.
4. Observing satisfactorydimension and surface Quality and
gross dimension checking .
5. Identifying surface defects and
permitting them for repairs if
admissible.
6. Identifying surface defects and
permitting them for repairs if
admissible, Testing of integral test
bars for impact bend test, Hardness
test, Grain size microstructure test.
Permitting for machining.
3 Stage-III Offer memo 2A After satisfactory removal of defects
after welding on permitted location,
No unauthorized welding, satisfactory
machining, Straightening, Dye
penetration test. Magnetic test,
Satisfactory Radiography test results
and Gross dimensional check.
4 Stage -IV Offer memo 3 1. No unauthorized welding hasbeen done.
2. After satisfactory Straightening,
maching Dye penetration test.
Magnetic test, Satisfactory
Radiography test results.
3. Detailed Dimension checking
using approved gauges.
4. Satisfactory Quality (dimension &
,metallurgical) of
components/fittings being
supplied with CMS Crossing
5. Satisfactory checking of all
records pertaining to previous
inspections.
6. Detailed Dimension checking
using approved gauges.
7. Satisfactory Quality (dimension,
metallurgical) of
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
8/11
components/fittings being
supplied with CMS Crossing.
8. Satisfactory checking of all
records pertaining to previous
inspections.
9.5 Initial Surface as well as Dimensional Inspection (Stage-I)
9.5.1 For developmental inspection, the inspection will be carried out as per Para
9.4.2 whereas for Normal production, inspection procedure as laid down in
Para 9.4.3 will be followed.
9.5.2 After fettling and shot blasting as per clause 7.6 ,the defective areas of the
surface of crossing if any shall be marked with the dimension of defects
(i.e. length, width and depth) and shown in isometric view as shown inAppendix-V and their locations indicated from a datum line. The details
are also to be tabulated and certified by the manufacturer in a proforma
prescribed by the inspecting official and shall be submitted to the inspecting
official for the verification / inspection. The inspection should be aimed at
detecting foundry defects like cracks, sand holes, cold shuts, pin holes,
porosity, extra metal, sand fusion etc. Crossing having cracks, unauthorized
welding, grinding, buffing markshall be straight away rejected.
9.5.3 The crossing shall be checked for gross dimensions and discrepancies shallbe tabulated with the remark in a sketch with isometric view classifying the
castings.
9.5.4 At this stage, gross dimensions such as overall length, distance between
actual nose and heel, actual nose and toe end, height at different locations
flange thickness at different locations, web thickness, roof thickness, flange
way clearance, throat clearance, flange well depth wheel tread at toe end
and opposite to actual nose, nose thickness, nose depression and offsets
bottom, bottom width, tie thickness, extent of vertical bend etc, shall be
checked and recorded.
9.5.5 After satisfactory inspection if crossing is considered fit for further
processing, Offer Memo No. 1, 2 & 3 as per Appendix-II for
Developmental Inspection and Offer Memo No. 1 as per Appendix-II A for
Normal Production Inspection shall be signed as mentioned in Clause 9.4.2
& 9.4.3 above.
9.6 Metallurgical & Dimensional Inspection (Stage-II)
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
9/11
9.6.1 Metallurgical inspection shall be carried out as after heat treatment as per
clause 7.7 & shot blasting for both Developmental as well as Normal
Production inspection.
9.6.2 The heat treatment of castings in a batch shall cover all castings of one heat.
The castings belonging to one melting heat and heat treatment batch shall
be referred as casting of one heat. Micro structure shall be checked by
inspecting official per heat as per clause No; 7.7.7 as amended as percorrigendum no 2 of August 2001. Two micro test pieces are to be cut each
from first and last casting, poured from same melting heat and both the
pieces are required to be passed in micro-structure test. Solidity test shall be
conducted as per clause 6.2.2.
9.6.3 At this stage, gross dimensions as mentioned in clause 9.5.4.3 shall be
checked.
9.6.4 Crossings having cracks as well as unauthorized welding/repairs shall be
rejected.
9.6.5 Integral Test bars shall be detached from the casting in presence of
inspection authority at the time of inspection. At least two test bars per
casting should be made available to the inspecting officer. The test bars are
to be stamped by inspecting official with proper identification. The firm
shall also keep their internal metallurgical test results readily available and
those shall be presented to the Inspecting Officials for cross check during
inspection
9.6.6 Impact Bend test on stamped test bars shall be conducted in presence of the
inspecting official as per Clause 12.1 and record of test shall be maintained.
Suitable hardness test shall be conducted at this stage both on thick and thin
section of each casting as per Clause 12.2 and also on test bars representing
a patch in presence of inspecting official and record shall be maintained.
9.6.5 After satisfactory inspection as per provisions of Clause 9.6 above, if
crossing is considered fit for further processing, Offer Memo No. 4 as per
Appendix -II for Developmental Inspection and Offer Memo No. 2 as per
Appendix-IIA for Normal Production Inspection shall be signed as
mentioned in Clause 9.4.2 & 9.4.3 respectively.
9.7 Surface & Dimensional Inspection (Stage III) (After Removal /
Rectification of casting defects only)
9.7.1. Before putting up to the inspecting official, the castings shall be suitably
prepared for the removal/rectification of defects as per Clause 7.8 and
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
10/11
straightened as per Clause 7.9. No crack shall develop on locations repaired
by welding, due to straightening operation.
9.7.2 Repair welding shall be done strictly as per the procedure for
repair/rectification of CMS Crossings at Appendix-III. The manufacturer
will produce a certificate to this effect.
9.7.3 The castings shall be offered to the inspecting official in the manner as in
Stage-I and Stage II for metallurgical and dimensional inspection, if
necessary.
9.7.4 The machining operation as per the product drawing shall be carried out at
this stage. No gross dimension except flange thickness,tie thickness,height
at different locations shall be checked.
9.7.5 The crossings which are considered process able shall be permitted for final
finishing and Offer Memo No. 5&6 shall be signed as per Appendix -II for
Developmental Inspection and Offer Memo No. 2A as per Appendix -IIA
for Normal Production Inspection.
9.8 Final Dimensional check up & Magnetic Test (Stage-IV /Final Stage)
9.8.1 After final internal inspection and certification by the Works Inspector of
the firm as per clause 15.3 the crossing shall be offered for dimensional
check up (as per sequence shown in Appendix-IV) on the inspection
table/marking table with the approved gauges/templates/equipment as
mentioned in clause 8.2.
9.8.2 Theeach casting shall be visually inspected for surface defects employing
dye-penetrant tests. Each casting shall also be tested for its non-magnetic
characteristics either by portable permanent magnet or by suitable electro-
magnet. The check will be done on head surface preferably after heat
treatment.
9.8.3 Dimensions of crossings shall be checked with the help of approved
gauges/templates, fishing cord, straight edge, filler gauge etc.
9.8.4 Crossing should be checked for alignment after straightening operation (if
straightened). Dye Penetration Test shall be carried out after straightening
operation to detect development of any crack.
9.8.5 Radiography shall be conducted as per Para 6.2.3
9.8.6 After the inspecting officials are satisfied that the crossing conforms to
relevant drawing and specifications, the crossing shall be accepted finally
-
7/28/2019 Revised Draft Ammendment to IRS T29 MAR13
11/11
and offer Memo No. 7 as per Appendix II for Developmental Inspection
and Offer Memo No 3 as per Appendix-IIA for Normal Production
Inspection shall be signed.
9.8.7 The inspected crossings should be handled properly avoiding impact and
stacked properly to avoid metal to metal contact among CMS Crossings by
keeping wooden spacer below the crossings.
14.1 Rejection;
Any batch of crossings produced from the same melt and heat treated
together under the same conditions which fails to comply with the
requirements of the specifications shall be rejected. Rejected crossings shall
be made unusable by gas cutting or by any other means in to at least two
pieces preferably near middle of crossing in order to avoid mixing up with
the crossings under processing/finishing/inspection and kept stacked
separately till verified by inspecting official. A certificate to this effect shall
be enclosed with next inspection call.
14.2 Any crossing which fails to comply with the requirements of the
specifications shall be rejected. Rejected crossings shall be made unusable
by gas cutting or by any other means in to at least two pieces preferably
near middle of crossing in order to avoid mixing up with the crossings
under processing/finishing/inspection and kept stacked separately till
verified by inspecting official. A certificate to this effect shall be enclosed
with next inspection call.
15.1 All the inspections offer memos shown in Appendix-II and IIA shall be gotprinted by the manufacturer in sufficient numbers. They will be bound in
separate booklet with all pages duly machine numbered in duplicate for
Appendix II and Appendix IIA respectively. One set of offer memo of
Appendix II (in duplicate) or Appendix IIA in respective
developmental/regular production shall be used for recording details of
only one crossing during its different stages of manufacture/inspection.