Revolutionize Material and Production Planning

with

Advanced Planner

Deborah Vermillion, CPIM, CIRM

CISTECH Inc.www.cistech.net

Page 2: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

What is Advanced Planner?• Advanced Planner is an alternative to XA MPSP, MRP and CRP• Windows based fast MRP that helps you to do interactive planning• Allows you to visualize load on the facilities (work centers). AVP

uses color coded graphs and charts that makes it easier to manage the master schedule process. This includes material and capacity testing

• Helps you to take appropriate decisions such as offloading, outsourcing, level loading etc to meet the on time delivery of your customer orders

• You can also estimate the labor requirements to support your plant schedules

• Generates suggested supplies( both MOs and POs), supply exceptions, detailed operation start times and shipment delivery dates

Page 3: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

How does AVP do this?

• Planning information is downloaded from the AS400 creating an Access database on the PC

• Planning run is done on the PC eliminating job conflicts on the 400 and decreasing processing time. This allows for “more” planning runs. Quicker response time!!!

Page 4: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Product Structures•part attributes•Standard and workorder bills•Standard and workorder routings

AV

P E

ngi

ne

Demand•Forecasts•customer orders •Replenishment policy

Supply•inventory on hand•shop orders and allocations•Outside operations•purchase orders

Plant Structures•Workcenters•Labor

Procurement Plan•purchase order releases•expedite; defer; cancel

Production Plan•manufacturing order releases•load vs. capacity•workcenter schedules

Shipping Plan•customer promise dates

AVP- Input Output

Page 5: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP/MRP Similarities

• Both use all the planning modifiers in the Item Balance/Plan record• Both use the MRP Execution Options for re-scheduling, auto-release, etc.• Both use the MRP Horizon Dates• Both have direct or indirect interface to Mapics Forecast module• Both use the Manufactured due date from the customer orders for planning

Page 6: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP vs. MRP

• An MRP generation is performed by a BOM explosion and netting routine usually overnight

• With Advanced Planner NO AS400 MRP generation is ever necessary

• MRP has multi-planning warehouse capabilities• 6.1 Provides multi-warehouse planning

Page 7: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

• MRP/CRP uses Mapics calendars • AVP has its own calendar within the database.

This calendar holds hours of operation per day.

• MRP has no easy “what if” capability short of a new MRP generation

• AVP has powerful “what if” capability directly with the AVP access database on the PC

AVP vs. MRP

Page 8: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP vs. MRP cont’d

• MRP interfaces with MPSP• AVP has its own Master Schedule Routine

• MRP uses Lead Time to calculate start date• AVP uses backward scheduling and the times in

the routing to calculate start date

Page 9: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

• MPSP uses the greater of Customer Order or Forecast

• AVP nets the CO’s against the Forecast and plans with the CO’s and Net Forecast

• MRP assumes infinite capacity• AVP plans the work load in each work center for

capacity review prior to accepting the plan

AVP vs. MRP cont’d

Page 10: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

• MRP provides a warning if a planned order quantity exceeds the Maximum

• AVP uses the Maximum to create multiple orders due on the same day for the Max quantity (or less)

• MRP plans an order to be due the same day as the requirement

• AVP plans an order to be due the day before the requirement

AVP vs. MRP cont’d

Page 11: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Forecast can be consumed in four ways:

– Individual Item: The sales of each item consume the item forecast– An item and its parents: If many possible finished product

configurations exist, made from a small number of components, you can forecast at the component level rather than the finished product level. The sales of the item and any parent consume the item forecast

– Planning bill Family: Identify an item as a planning bill item and enter shippable forecasts for the item (% based on qty per in Planning Bill. Forecast is consumed by end item and matching configurations in the Bill of Material

– Product Family: Does not use a Planning Bill. The ‘Base’ Item is forecasted. Customer Order Demand for items within the Product Family consume the ‘Base’ Item’s forecast. (introduced at AVP 6.1)

AVP extras: Forecast Consumption

Page 12: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Forecast Consumption

This is the forecast consumption chart

within AVP

Page 13: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP Extras

Config.ini settings to:– Calculate run time by flow or batch method– Uses RM Quantity (at the time of the RM

transaction) or Operation Quantity Completed (from Labor Reporting) to calculate balance due

– Can define horizon length values 1-999 days

Page 14: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP Extras

You can optionally update either or both

– The promise date on the customer order– The manufacturing due date on the customer

order

Page 15: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Questions?

Page 16: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Advanced Planner Process

• Downloading Data to the Engine– Pulls BOM, Route,

Item, Item process, Item plan, Forecast, CO’s and/or Manual Requirements

– Creates flat files that are pulled in to create access database

Page 17: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

• Generating the Plan– Forecast Consumption– Nets the Requirements

against on hand & on order (Load Project) using Access Database

• Builds product structure network using the BOM and Routing

• Plans Orders (PO, MO & Schedules)

Advanced Planner Process

Page 18: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

• Manipulate the Plan– View Load to Capacity Chart

– View items on Load

– Level Load both Material and Capacity

– Time phased view

– Drill down/up

– Perform “what-if” planning

Advanced Planner Process

Page 19: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Load To Capacity and Time phased load : Identify overload problem

Orders that can be Orders that can be offloaded-Yellowoffloaded-Yellow

Planned Orders- Planned Orders- GreenGreen

New Colors at AVP New Colors at AVP 6.1:6.1:

Firm Planned- PinkFirm Planned- Pink

Released- Light Released- Light OrangeOrange

Page 20: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Load To Capacity Chart

Red – W/C is overloadedYellow – W/C has past due backlogBlue – Overload within one time period that can be corrected by re-scheduling, offloading, etc.Green – Plan is within capacity constraints

Routing Facilities

Process Hours; Setup hours;

Capacity hours

Page 21: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

As decisions are taken you get instant feedback

Page 22: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Order waterfall view:Identify what is needed when and the Critical chain

Page 23: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Advanced Planner Process

• Upload to Mapics Files– Loads info into the MRP planning work files:

• Requirements-unconsumed forecast and generated demand

• Planned Orders-all supply orders, including open, firm planned and planned

• Demand Ref-Demand information• Reschedule Activity-rescheduling actions

Page 24: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Advanced Planner Process

• What happens?– Reschedules open MO’s/PO’s/Rep

schedules according to set up– Updates the CO dates if specified in the

upload options– Updates work center file in the MO/REP

operations as specified during offloading– Loads the MRP planning files– Creates the Order Review file– Prints MRP reports as specified

Page 25: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Planning Execution

Once plan is saved

– Execute plan using OBPM

OR– Green Screen Order review and release

OR– Repetitive

Page 26: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Execute Plan using OBPM

Page 27: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Green Screen Execution

Page 28: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

MRP Requirements inquiry

Page 29: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Questions?

Page 30: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP 6.1 New Functionality

• Planning Multiple warehouses in one planning run• Saving the Schedules to database on the client machine• Support for SQL server and Oracle databases• Time phased Labor loads• Job-step information in the waterfall• Automatic offload from one facility to other by batch size• Which customer orders to be pushed out• Adjusting the operation start times of intermediate

operations thru Modifying the delay times• Demand Prioritization• Ability to handle negative on hand balances.

Page 31: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Waterfall with Job step information

Page 32: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Estimating the Labor Requirement

Page 33: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Which Orders to push out

New Commands show New Commands show the potential order list the potential order list that will be delayed that will be delayed based upon the current based upon the current schedule.schedule.

Global Records not limited to within the Global Records not limited to within the Facility. “Which Customer Orders..” lists only Facility. “Which Customer Orders..” lists only Customer Orders where Demand Suggested Customer Orders where Demand Suggested Date > Demand Due Date. Customer Orders Date > Demand Due Date. Customer Orders pushed out will be displayed from the “List of pushed out will be displayed from the “List of Customer Orders..” Customer Orders..”

Generated from within the Generated from within the Facility. Lists supply orders Facility. Lists supply orders where Supply Due Date > where Supply Due Date > Supply Suggested DatedSupply Suggested Dated

Page 34: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP Benefits

• Improves capacity usage—maximize factory productivity

• Increases revenue—the ability to consistently provide more accurate dates and deliver on time will attract more business

• Streamlines purchasing an item that has an m-plan or s-plan order (outsourcing)

Page 35: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP Benefits

• Expediting costs are lowered due to improved planning

• Improves internal processing coordination—running your planning process quickly and more frequently will

• Catch changes and allow you to alert the shop floor and suppliers quicker

Page 36: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

AVP Summary

• Alternative to traditional MPSP/MRP/CRP• Tight integration for quick implementation• Quick ROI from improved capacity planning• Improved Capacity usage• Decreased Lead time and inventory• Decreased costs

Page 37: Revolutionize Material and Production Planning with Advanced Planner Deborah Vermillion, CPIM, CIRM CISTECH Inc

Thank you!!Thank you!!