rf commissioning

21
RF Commissioning D. Jacquet and M. Gruwé

Upload: arsenio-hood

Post on 02-Jan-2016

30 views

Category:

Documents


0 download

DESCRIPTION

RF Commissioning. D. Jacquet and M. Gruw é. RF systems in a few words (I). A transverse dampers system ACCELERATING SYSTEM 4 HV bunkers containing : the klystron modulators the fast protection systems (crowbars) the high voltage switches and the klystron heater power supplies. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: RF Commissioning

RF Commissioning

D. Jacquet and M. Gruwé

Page 2: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 2

RF systems in a few words (I)

• A transverse dampers systemACCELERATING SYSTEM• 4 HV bunkers containing:

– the klystron modulators– the fast protection systems (crowbars)– the high voltage switches – and the klystron heater power supplies.

• 16 high power lines : – HV cables, klystron, circulators, RF load, wave guides and the high

power couplers

• 16 superconducting cavities:– 8 per beam on each side of point 4, powered independently by the high

power lines.

• Low level RF system…

Page 3: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 3

RF systems in a few words (II)

• A sophisticated low level RF system (called cavity controller)– For each RF line:

• RF Feedback• a Tuner Loop• a Klystron Ripple Loop • and a Conditioning system

=> RF control for each cavity is independent.• A beam Control system (generates the 400MHz signal for the cavity

controllers)– For each ring:

• Frequency Program• Phase Loop• Radial Loop • and Synchronization Loop

• An RF synchronization system implements the bunch into bucket transfer from the SPS into each LHC ring.

Page 4: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 4

RF cryo• 4 superconducting cavity modules made of four cavities.

=>The temperature of all four cavities in a module is not controlled independently. Each superconducting cavity module is connected to the QRL (4.5K).

Page 5: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 5

Tests

• Power systems commissioning• Superconducting cavities commissioning• Klystrons & cavities feedback loops• RF synchro & beam control• Transverse Dampers

Page 6: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 6

POWER SYSTEMS COMMISSIONING

• The individual high power RF systems have to be set to full power (short circuited).– The klystron power converters switch ON, and HV settings :

done.– HV fast protection system, HV switch to individual klystron and

klystron modulators : ongoing (one out of 4 is done).– Low level equipment set-up for open loop operation : done– Commissioning and calibration of high RF power equipment

(modulator, RF drivers, klystrons, circulators, loads, directional couplers, …) : on going for 8 cavities, for the other 8 their collectors have to be replaced before the commissioning can start.

Page 7: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 7

CAVITIES COMMISSIONING (I)

• Can start only when Power Commissioning has been completed

• Additional Services needed– Access system operational in “RF test mode” permitting RF in

cavities – Cryogenic system commissioning completed (4.5 K): Cavities

cooled down and pressure in the QRL headers stabilized, process control and procedures for cavity operation verified

– Radiation monitors operational (RAMSES system commissioned)

Page 8: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 8

CAVITIES COMMISSIONING (II)

• Low power verification and measurements:– Couplers and antennas.

• Controls:– Check the interlock, signal acquisition, analog multiplexers – Check the cavity tuning system and main couplers positioning system– Set up the control for coupler and cavity conditioning: feedback loops on

cavity and main coupler vacuums, He pressure

• Tune the RF power with cold cavities.• Pre-calibration measurements:

– Antenna/Couplers/Klystrons/Tuners

• Conditioning of– the high power couplers up to full power – and the cavities up to full field

• Setting up of the tuning loop for each individual cavity

Page 9: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 9

CAVITIES COMMISSIONING (III)

• Conditioning of the cavities (cleaning of the cavity surface): – A software (Labview) has been developed to automate the

conditioning process: The cavity field is raised by small steps for different position of the couplers, until there is full power and full field in the cavities.

– At this stage, operation team may be involved as the cavities can be conditioned in parallel and the procedure is automatic.

– The conditioning of the cavities in sector 4-5 will start as soon as the cryo is ready.

– The duration off the test is heavily linked to the cryo stability. Without cryo problem, it should take 1 week to prepare the cavities and one week/cavity for the conditioning.

Page 10: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 10

KLYSTRONS & CAVITIES FEEDBACK LOOPS

Page 11: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 11

KLYSTRONS & CAVITIES FEEDBACK LOOPS

• The remaining Low-Level RF activity can be carried-out only after the cavities and the main couplers in a module have been conditioned.

• For each of the 16 RF lines, the following tests have to be performed– Fine setting up of the tuner loop– Setting up the klystron polar loop (reduces klystron phase ripples)– Setting up the gain, notch and time constants of the RF feedback loop– Setting up the one turn feedback loop– Fine tuning of the "Switch/Protection module" threshold so that we do

not trip the klystron on drive transients – A full set of measurements: loop responses etc.

• All the above depend on the actual loop delay, klystron response, cable/antenna attenuation so that they have to be customized for each line.

Page 12: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 12

KLYSTRONS & CAVITIES FEEDBACK LOOPS

This tests require a very specific expertise: it is not likely that OP could provide any help. The needed software will be provided by the RF team, probably using Labview.

2 weeks per cavity are needed Once all lines are commissioned, a global low-level

adjustment will be performed(1 week).

Page 13: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 13

• RF synchro : – Generation of kicker pulses, beam dump signals, Frev, clocks to the

experiments and the SPS– All hardware modules are ready. They have to be tested as far as

possible without beam. – The tests will start mid-January. Expected to last 8 weeks. They have to

be completed 3 months before beam.

• Beam control : – Set up the 400 MHz reference generation in the Beam Control crate to

drive the Cavity Controllers– Commission frequency Prgm, synchro loop, radial loop and phase loop

without beam– 2 modules are still under design. – Tests done from March 2008 till beam start up.

RF SYNCHRO & BEAM CONTROL I

Page 14: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 14

RF SYNCHRO & BEAM CONTROL II

These systems are located in SR4, so accessible even during beam. Most of the commissioning will be done with beam.

The commissioning has to be done by the expert who designed the systems.

Page 15: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 15

DDS1 DDS2F RF Prog 1 F RF Prog 2

WB

sw

itch

WB

sw

itch

Inj. F rev

F injRing 1

Ring 2

Ring 1

Ring 2

Pha

se s

hifte

r

1/(7 h) divider

1/h Divider

RF IN

OUT

1/h DividerRF IN

OUT

SyncOUT

RF IN

Sync

Bucket nbr.

Shi

fted

F in

j to

SP

S

Del

aye

d F

c to

SP

S

SP

S e

xtr.

war

ning

Inj. Pulse generator

RF IN

OUT

Inje

ctio

n pu

lse

Injection VETO

Sync

Ring 1

Ring 2

Ring 2

Ring 1

Next

Shut

Open

Inj. Phase

WB Demux

Inj.

Rin

g 1

Inj.

Rin

g 2

Fiber optic links to AB/BT

Fiber optic links to/from SPS FC

Ring 2

Ring 1

F rev prog1

F rev prog2

Fiber optic links to UX45

VTU

DUAL FREQ PRGM

BUCKET SELECTOR

INJ PULSE GENE

VTUVTU

This divider will adjust the relative position of ring 2 vs ring 1

This is the Dual Freq Program represented on the previous block diagram

By changing the programmable delay in the bucket selector one chooses the LHC bucket for transfer

This module generates the pulses sent to the injection kickers

LHC LLRF RF Synchronization( from P. Baudrenghien )

Page 16: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 16

R1

Low-levelLoops

Processor

Radial PUFront-end

VCXO

Phase Discri

F RF Prog 1

Radial loop

Phase loop

Synchro loop

DDS1 DDS2

Sync

F1,P

1

F2,P

2

F1 F2

1/h divider

Master F rev

To Ring 1 Cavity Controllers (fibers)

Dual Frequency Program and

Rephasor FPGA

Function Gen. Function Gen.

F RF Prog 2

DUAL FREQUENCY

PRGM

Master F RF

Beam 1Rad. PU

Beam/Vt phase

RF/Fprog phase

F out

Rad

Pos

.Fiber Optic

TX

BEAM CONTROL

LOOPS MODULE

Radial steering with radial loop

Coarse F1

LF switch

Phase Discri

7 TeV synthesizer

Phase shifter

180 deg hybrid

a b

BEAM POS

MODULE

FPGA

AD

C

SYNCHROMODULE

Ib RF Summing Network

Vt

Phase PU

AD

C

CORDIC (+ AGC?)

Bunch/RF phase

CORDIC (+ AGC?)

Vt/RF phase

Phase Difference

and Averaging

BEAM PHASE

MODULE

AD

C

Cavities

Analog I/Q demod

Analog I/Q demod

Master FrfMaster Frf

AD

C

AD

C

Delay adjust

Function Gen.

fsync

fphase

A function sets the RF frequency on the injection plateau and through the ramp

Injection frequency, injection phase and stable phase will be adjusted by observing these two signals

The VCXO generates the RF sent to the Cavity Controllers

This synthesizer replaces the frequency program during physics

LHC LLRF Beam Control

( from P. Baudrenghien )

Page 17: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 17

TRANSVERSE DAMPERS (ADT)

• Principle:– Designed to damp the transverse oscillations of the beam at injection to

preserve beam size– The system measures the transverse position of the beam (both

horizontal and vertical) and applies a correction

• System consists of 4 independent damper systems (2 per beam) with– 4 kickers per beam and plane– Dedicated pickups (2 per plane and per beam)– Electronics on surface (driver amplifiers, PLC controls, fast interlocks)

Page 18: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 18

Overview of one ADT system

Commissioned

Page 19: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 19

ADT (high power part)

20 electrostatic kickers 40 wideband amplifiers, i.e. 40 tetrodes

(RS2048 CJC, 30 kW) 20 amplifier cases

Damper system

Beam 1

IP4

“Electrostatic”kicker

Beam 2

WidebandamplifierUnit

H H V VSpare units+

H H H HV VV V

H H H H V V V V

Module

Page 20: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 20

ADT Commissioning

• Commissioning:– Controls: Interlocks, power supply controls, application software. Done.– Power converter tests: interlocks, switch ON. Done.– Damper power: Done.

• Damper tetrodes power amplifiers• Kickers• Drive amplifiers

– Damper Low Level system: feedback loops and the pickups. Ongoing.• One of the card is not completed yet. • Calibration will be finished as soon as card is ready (one month before beam

start up)• 10 systems of pick-up have to be calibrated. This requires an access, 2 days

per system is needed.• Some work can be done with simulated beam, but most of the setting up

requires beam.

Page 21: RF Commissioning

November 8th 2007 D. Jacquet and M. Gruwé 21

Conclusions

• RF systems commissioning– The RF power commissioning is ongoing– Once the lines are ready, the cryo in sector 4-5, then in sector 3-

4, have to be ready to start the cavities conditioning.– OP can be involved in the cavity conditioning, but the other

systems require too much expertise.– The software needed for the hardware commissioning will be

provided by the RF group itself.– An operational application has still to be developed, this one

should be used for the cold check-out.