rf commissioning
DESCRIPTION
RF Commissioning. D. Jacquet and M. Gruw é. RF systems in a few words (I). A transverse dampers system ACCELERATING SYSTEM 4 HV bunkers containing : the klystron modulators the fast protection systems (crowbars) the high voltage switches and the klystron heater power supplies. - PowerPoint PPT PresentationTRANSCRIPT
RF Commissioning
D. Jacquet and M. Gruwé
November 8th 2007 D. Jacquet and M. Gruwé 2
RF systems in a few words (I)
• A transverse dampers systemACCELERATING SYSTEM• 4 HV bunkers containing:
– the klystron modulators– the fast protection systems (crowbars)– the high voltage switches – and the klystron heater power supplies.
• 16 high power lines : – HV cables, klystron, circulators, RF load, wave guides and the high
power couplers
• 16 superconducting cavities:– 8 per beam on each side of point 4, powered independently by the high
power lines.
• Low level RF system…
November 8th 2007 D. Jacquet and M. Gruwé 3
RF systems in a few words (II)
• A sophisticated low level RF system (called cavity controller)– For each RF line:
• RF Feedback• a Tuner Loop• a Klystron Ripple Loop • and a Conditioning system
=> RF control for each cavity is independent.• A beam Control system (generates the 400MHz signal for the cavity
controllers)– For each ring:
• Frequency Program• Phase Loop• Radial Loop • and Synchronization Loop
• An RF synchronization system implements the bunch into bucket transfer from the SPS into each LHC ring.
November 8th 2007 D. Jacquet and M. Gruwé 4
RF cryo• 4 superconducting cavity modules made of four cavities.
=>The temperature of all four cavities in a module is not controlled independently. Each superconducting cavity module is connected to the QRL (4.5K).
November 8th 2007 D. Jacquet and M. Gruwé 5
Tests
• Power systems commissioning• Superconducting cavities commissioning• Klystrons & cavities feedback loops• RF synchro & beam control• Transverse Dampers
November 8th 2007 D. Jacquet and M. Gruwé 6
POWER SYSTEMS COMMISSIONING
• The individual high power RF systems have to be set to full power (short circuited).– The klystron power converters switch ON, and HV settings :
done.– HV fast protection system, HV switch to individual klystron and
klystron modulators : ongoing (one out of 4 is done).– Low level equipment set-up for open loop operation : done– Commissioning and calibration of high RF power equipment
(modulator, RF drivers, klystrons, circulators, loads, directional couplers, …) : on going for 8 cavities, for the other 8 their collectors have to be replaced before the commissioning can start.
November 8th 2007 D. Jacquet and M. Gruwé 7
CAVITIES COMMISSIONING (I)
• Can start only when Power Commissioning has been completed
• Additional Services needed– Access system operational in “RF test mode” permitting RF in
cavities – Cryogenic system commissioning completed (4.5 K): Cavities
cooled down and pressure in the QRL headers stabilized, process control and procedures for cavity operation verified
– Radiation monitors operational (RAMSES system commissioned)
November 8th 2007 D. Jacquet and M. Gruwé 8
CAVITIES COMMISSIONING (II)
• Low power verification and measurements:– Couplers and antennas.
• Controls:– Check the interlock, signal acquisition, analog multiplexers – Check the cavity tuning system and main couplers positioning system– Set up the control for coupler and cavity conditioning: feedback loops on
cavity and main coupler vacuums, He pressure
• Tune the RF power with cold cavities.• Pre-calibration measurements:
– Antenna/Couplers/Klystrons/Tuners
• Conditioning of– the high power couplers up to full power – and the cavities up to full field
• Setting up of the tuning loop for each individual cavity
November 8th 2007 D. Jacquet and M. Gruwé 9
CAVITIES COMMISSIONING (III)
• Conditioning of the cavities (cleaning of the cavity surface): – A software (Labview) has been developed to automate the
conditioning process: The cavity field is raised by small steps for different position of the couplers, until there is full power and full field in the cavities.
– At this stage, operation team may be involved as the cavities can be conditioned in parallel and the procedure is automatic.
– The conditioning of the cavities in sector 4-5 will start as soon as the cryo is ready.
– The duration off the test is heavily linked to the cryo stability. Without cryo problem, it should take 1 week to prepare the cavities and one week/cavity for the conditioning.
November 8th 2007 D. Jacquet and M. Gruwé 10
KLYSTRONS & CAVITIES FEEDBACK LOOPS
November 8th 2007 D. Jacquet and M. Gruwé 11
KLYSTRONS & CAVITIES FEEDBACK LOOPS
• The remaining Low-Level RF activity can be carried-out only after the cavities and the main couplers in a module have been conditioned.
• For each of the 16 RF lines, the following tests have to be performed– Fine setting up of the tuner loop– Setting up the klystron polar loop (reduces klystron phase ripples)– Setting up the gain, notch and time constants of the RF feedback loop– Setting up the one turn feedback loop– Fine tuning of the "Switch/Protection module" threshold so that we do
not trip the klystron on drive transients – A full set of measurements: loop responses etc.
• All the above depend on the actual loop delay, klystron response, cable/antenna attenuation so that they have to be customized for each line.
November 8th 2007 D. Jacquet and M. Gruwé 12
KLYSTRONS & CAVITIES FEEDBACK LOOPS
This tests require a very specific expertise: it is not likely that OP could provide any help. The needed software will be provided by the RF team, probably using Labview.
2 weeks per cavity are needed Once all lines are commissioned, a global low-level
adjustment will be performed(1 week).
November 8th 2007 D. Jacquet and M. Gruwé 13
• RF synchro : – Generation of kicker pulses, beam dump signals, Frev, clocks to the
experiments and the SPS– All hardware modules are ready. They have to be tested as far as
possible without beam. – The tests will start mid-January. Expected to last 8 weeks. They have to
be completed 3 months before beam.
• Beam control : – Set up the 400 MHz reference generation in the Beam Control crate to
drive the Cavity Controllers– Commission frequency Prgm, synchro loop, radial loop and phase loop
without beam– 2 modules are still under design. – Tests done from March 2008 till beam start up.
RF SYNCHRO & BEAM CONTROL I
November 8th 2007 D. Jacquet and M. Gruwé 14
RF SYNCHRO & BEAM CONTROL II
These systems are located in SR4, so accessible even during beam. Most of the commissioning will be done with beam.
The commissioning has to be done by the expert who designed the systems.
November 8th 2007 D. Jacquet and M. Gruwé 15
DDS1 DDS2F RF Prog 1 F RF Prog 2
WB
sw
itch
WB
sw
itch
Inj. F rev
F injRing 1
Ring 2
Ring 1
Ring 2
Pha
se s
hifte
r
1/(7 h) divider
1/h Divider
RF IN
OUT
1/h DividerRF IN
OUT
SyncOUT
RF IN
Sync
Bucket nbr.
Shi
fted
F in
j to
SP
S
Del
aye
d F
c to
SP
S
SP
S e
xtr.
war
ning
Inj. Pulse generator
RF IN
OUT
Inje
ctio
n pu
lse
Injection VETO
Sync
Ring 1
Ring 2
Ring 2
Ring 1
Next
Shut
Open
Inj. Phase
WB Demux
Inj.
Rin
g 1
Inj.
Rin
g 2
Fiber optic links to AB/BT
Fiber optic links to/from SPS FC
Ring 2
Ring 1
F rev prog1
F rev prog2
Fiber optic links to UX45
VTU
DUAL FREQ PRGM
BUCKET SELECTOR
INJ PULSE GENE
VTUVTU
This divider will adjust the relative position of ring 2 vs ring 1
This is the Dual Freq Program represented on the previous block diagram
By changing the programmable delay in the bucket selector one chooses the LHC bucket for transfer
This module generates the pulses sent to the injection kickers
LHC LLRF RF Synchronization( from P. Baudrenghien )
November 8th 2007 D. Jacquet and M. Gruwé 16
R1
Low-levelLoops
Processor
Radial PUFront-end
VCXO
Phase Discri
F RF Prog 1
Radial loop
Phase loop
Synchro loop
DDS1 DDS2
Sync
F1,P
1
F2,P
2
F1 F2
1/h divider
Master F rev
To Ring 1 Cavity Controllers (fibers)
Dual Frequency Program and
Rephasor FPGA
Function Gen. Function Gen.
F RF Prog 2
DUAL FREQUENCY
PRGM
Master F RF
Beam 1Rad. PU
Beam/Vt phase
RF/Fprog phase
F out
Rad
Pos
.Fiber Optic
TX
BEAM CONTROL
LOOPS MODULE
Radial steering with radial loop
Coarse F1
LF switch
Phase Discri
7 TeV synthesizer
Phase shifter
180 deg hybrid
a b
BEAM POS
MODULE
FPGA
AD
C
SYNCHROMODULE
Ib RF Summing Network
Vt
Phase PU
AD
C
CORDIC (+ AGC?)
Bunch/RF phase
CORDIC (+ AGC?)
Vt/RF phase
Phase Difference
and Averaging
BEAM PHASE
MODULE
AD
C
Cavities
Analog I/Q demod
Analog I/Q demod
Master FrfMaster Frf
AD
C
AD
C
Delay adjust
Function Gen.
fsync
fphase
A function sets the RF frequency on the injection plateau and through the ramp
Injection frequency, injection phase and stable phase will be adjusted by observing these two signals
The VCXO generates the RF sent to the Cavity Controllers
This synthesizer replaces the frequency program during physics
LHC LLRF Beam Control
( from P. Baudrenghien )
November 8th 2007 D. Jacquet and M. Gruwé 17
TRANSVERSE DAMPERS (ADT)
• Principle:– Designed to damp the transverse oscillations of the beam at injection to
preserve beam size– The system measures the transverse position of the beam (both
horizontal and vertical) and applies a correction
• System consists of 4 independent damper systems (2 per beam) with– 4 kickers per beam and plane– Dedicated pickups (2 per plane and per beam)– Electronics on surface (driver amplifiers, PLC controls, fast interlocks)
November 8th 2007 D. Jacquet and M. Gruwé 18
Overview of one ADT system
Commissioned
November 8th 2007 D. Jacquet and M. Gruwé 19
ADT (high power part)
20 electrostatic kickers 40 wideband amplifiers, i.e. 40 tetrodes
(RS2048 CJC, 30 kW) 20 amplifier cases
Damper system
Beam 1
IP4
“Electrostatic”kicker
Beam 2
WidebandamplifierUnit
H H V VSpare units+
H H H HV VV V
H H H H V V V V
Module
November 8th 2007 D. Jacquet and M. Gruwé 20
ADT Commissioning
• Commissioning:– Controls: Interlocks, power supply controls, application software. Done.– Power converter tests: interlocks, switch ON. Done.– Damper power: Done.
• Damper tetrodes power amplifiers• Kickers• Drive amplifiers
– Damper Low Level system: feedback loops and the pickups. Ongoing.• One of the card is not completed yet. • Calibration will be finished as soon as card is ready (one month before beam
start up)• 10 systems of pick-up have to be calibrated. This requires an access, 2 days
per system is needed.• Some work can be done with simulated beam, but most of the setting up
requires beam.
November 8th 2007 D. Jacquet and M. Gruwé 21
Conclusions
• RF systems commissioning– The RF power commissioning is ongoing– Once the lines are ready, the cryo in sector 4-5, then in sector 3-
4, have to be ready to start the cavities conditioning.– OP can be involved in the cavity conditioning, but the other
systems require too much expertise.– The software needed for the hardware commissioning will be
provided by the RF group itself.– An operational application has still to be developed, this one
should be used for the cold check-out.