rfp for mpls, p2p & ill connectivity and procurement of ... · fast ethernet switches are now...
TRANSCRIPT
Sr. No. RFP Page
No
RFP Rule No Rule Details Query/ Suggestion/ Clarification Change in RFP
1 80 2.2 Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink
portspopulated with 1G
single mode transceivers.
For higher scalability, we request you to consider switch with 41G/10G SFP+ slots and for higher avaliability, we highly
recommend to consider switch with internal redundant power supplies
Minimum 16 RJ-45 autosensing 10/100/1000 ports & 4*1/10Gbps Uplink with Min. 2 no's of Fiber based SFP and
internal RPS equipped with 370w PoE budget redundancy
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers2 81 3.4 The Switch should support stacking of switches Please clarify, do we need to consider stacking with virtual chassis technology with which multiple switches in stack
shall operate as one logical Layer 3 Switch for higher avalaibility ?
The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements. 3 81 5.4 The switch should have to support OSPFv2 and OSPFv3 protocols for
routing from day 1
Please clarify, do we need to consider BGP support, it will be required for summurising the routes in different
autonomous networks
As per Draft RFP
4 83 7 Request for Addition:
Switch should support openflow v1.3
Openflow v1.3 is an open standrad for ease of managament and brings higher avalibiltiy in networks. Its being adopted
by all leading OEM's. So, would request you to consider switch with SDN openflow v1.3
As per Draft RFP
5 84 8 Ethernet 10/100 ports and 2 dual-purpose uplinks (each dual-purpose uplink port has 1 10/100/1000 Ethernet port
and 1 SFP-based Gigabit Ethernet port with single mode transceiver, 1 port active)
Fast ethernet switches are now lecgacy and no more in production, so we request you to consider gigabit switches,
please change clause as
8 Ethernet 10/100/1000 ports and 2 dual-purpose uplinks (each dual-purpose uplink port has 1 10/100/1000 Ethernet
port and 1 SFP-based Gigabit Ethernet port with single mode transceiver, 1 port active)
8 Ethernet 10/100/1000 ports and 2 SFP-based
Gigabit Ethernet uplink port with populated single
mode transceiver
6 85 IPv6 protocol support Please clarify, do we need to consider switch with IPv6 QoS, IPv6 hardware ACL for prioritising the IPv6 traffic? As per Draft RFP
7 86 OEM should be in " Leaders Quadrant of latest Gartner's magic
Quadrant for the Wired and wireless LAN access infrastructure
2019"
The Leaders quadrant has Cisco, HPE and Extreme OEM's, which is restricting open competition, so request you to
consider all OEM's featured in Gartners magic quadrant report as being considered for L3 Switches. Please change
clause as
OEM should be in " latest Gartner's magic Quadrant for the Wired and wireless LAN access infrastructure 2019" And
all switches shall be from same OEM for ease of integration
As per Draft RFP
8 86 1.4 128 MB flash, 256 MB DRAM Flash memeory varies with OEM harware design, please consider minimum 64MB flash memory As per Draft RFP
9 86 5 Request for Addition:
Switch should support openflow v1.3
Openflow v1.3 is an open standrad for ease of managament and brings higher avalibiltiy in networks. Its being adopted
by all leading OEM's. So, would request you to consider switch with SDN openflow v1.3
As per Draft RFP
10 67 SLA for Network Equipment: For higher avaliability and network security, we recommend to consider Zero touch recovery of failed switches, auto-
backup of switch configurations, blocking of switch ports upon detection of threats like viruses, malwares on Security
appliance Firewall WAN port
As per Draft RFP
11 14 4. PRE-QUALIFICATION /
ELIGIBILITY CRITERIA, Sr.
No. 6
Certifications: The bidder must possess, at the time of bidding, a valid ISO 9001 / ISO 20000 / ISO 27001/ CMMi
Level V.
BSNL, being a Central Govt. PSU, should be exempted from this condition As per Draft RFP
12 16 5.1. Detailsof Scope of
Work (SoW) A (1) Pre-
implementation (a)
RISL shall provide the list of sites to be connected to bidder/SPs. Bidder/SPs shall perform Site-survey of all the
ordered locations for feasibility. The Bidder/SPs shall intimate feasible links within specified timelines. If no
intimation is provided by bidder/SPs within specified days, it shall be deemed that the site(s)are feasibleto the
bidder/SP.
(A) If some location is found not-feasible on existing media and bidder/SP intimate RISL within specified time, whether
RISL will pay the additional one-time charges to make the location feasible?
(B) After commissioning of circuit, if the office is shifted to some not-feasible location, can bidder/SP then declare the
new location as Non-feasible and deny to shift the circuit?
As per Draft RFP
13 17 5.1. Detailsof Scope of
Work (SoW) A (2)
Implementation (b)
The Equipment to be installed by the Bidder/SP shall extend an electrical Ethernet interface to the end CPE
equipment (Router/Layer3 Switch) installed at each location. The required Router/Switch, UPS, Rack and earthing
shall be provided by the RISL.
Should be clarified further. As per Draft RFP
14 28 5.2 Project Milestones,
Deliverables& Timelines
Agreement Signing Time Frame: Within 15 days
of issue of LOI
Should be increased to at least 21 days As per Draft RFP
15 29 5.2 Project Milestones,
Deliverables& Timelines
(a)
Lot Size and Commissioning timelines Whether Link Commissioning timeline, begins from the date of work order or after expiry of Link Feasibility timeline? As per Draft RFP
16 52 7. GENERAL TERMS AND
CONDITIONS OF TENDER
& CONTRACT (17)
Sub-contracting BSNL gets various activities executed through its empannelled System Integrators whether this clause will apply on
such type of work execution?
As per Draft RFP
17 91 Item No.30 Point 5 Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals (ETL report for zero bit should be submitted)
Please put slash is cross member/fluted member as both are different types of separators .Also request to remove Zero
Bit Error verified by ETL as this test is outdated and no OEM get this ETL verification program done and same can be
cjecked from Intertek website under ETL verification program directory ( https://www.intertek.com/cabling-products/)
Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
18 91 Item No.30 Point 7 Box of 305 meters Packing, 45ns MAX. Delay Skew, 100 Ohms + /- 15 ohms for 1 to 250 MHz Allow Box packing of 500 meters also as mostly european companies provide 500 meter cable box Box of 305/500 meters Packing, 45ns MAX. Delay
Skew, 100 Ohms + /- 15 ohms for 1 to 250 MHz
19 92 Item No.31 Point 5 Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals (ETL report for zero bit should be submitted)
Please put slash is cross member/fluted member as both are different types of separators .Also request to remove Zero
Bit Error verified by ETL as this test is outdated and no OEM get this ETL verification program done and same can be
cjecked from Intertek website under ETL verification program directory ( https://www.intertek.com/cabling-products/)
Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
20 92 Item No.31 Point 7 Box of 305 meters Packing, 45ns MAX. Delay Skew, 100 Ohms + /- 15 ohms for 1 to 250 MHz Allow Box packing of 500 meters also as mostly european companies provide 500 meter cable box Box of 305/500 meters Packing, 45ns MAX. Delay
Skew, 100 Ohms + /- 15 ohms for 1 to 250 MHz
21 93 Item No.32 Point 5 Accessories Strain relief and bendlimiting
boot for cable , Approval UL or ETL or 3P
Plesae make it Approval UL and ETL verified or 3P verified (ETL alone done not mean any thing as ETL verified is the
conformance mark )Also UL is for fire and ETL and 3P are for performance so option between ETL verified or 3P can be
given but UL being a different certificate can not be included in option
As per Draft RFP
22 93 Item No.32 Point 9 ROHS Compliant , 3rd party from bodies like ETL verified (ETL report should be submitted) Pleae make it 3rd party from bodies like ETL verified/3P (ETL/3P certificate to be available on respective
website).These verification certificates are on only valid if they are present on testing lab website .
As per Draft RFP
23 93 Item No.32 Point 11 1-port with shutter , High ImpactPlastic Body ABS material Please allow hinged dust cover also As per Draft RFP
24 93 Item No.32 Point 13 Screw hole covers – to be suppliedwith plate Please remove as it differs on OEM to OEM design As per Draft RFP
25 93 Item No.32 Point 14 Plug in Icons – Icon tree – to be supplied with plate This is OEM specific only one OEM complies please remove As per Draft RFP
26 94 Item No.33 Point 14 Jack Panel should be RoHS Complaint Please add certification for information outlet in panel also like IO is Jack panel should be ETL verified/3P verified
(ETL/3P certificate to be available on respective website)
As per Draft RFP
27 95 Item No.34 Point 14 Jack Panel should be RoHS Complaint Please add certification for information outlet in panel also like IO is Jack panel should be ETL verified/3P verified
(ETL/3P certificate to be available on respective website)
As per Draft RFP
28 95 Item No.35 Point 4 4 Pair 24 AWG Copper Cable with integral cross member pair, transparent slim line clear anti-snag
slip on boots and factory moulded RJ-45 plugs at both end LSZH sheath.
Please 26 AWG also as in patch cord it is easier to do rack dressing and increase flexibility . As per Draft RFP
29 95 Item No.35 Point 8 Load bar polycarbonate, Jacket
FRPVC
Plesae remove this line as Jacket asked in point no 4 is LSZH and here PVC request to remove this line to avoid
confussion
As per Draft RFP
30 96 Item No.36 Point 4 4 Pair 24 AWG Copper Cable with integral cross member pair, transparent slim line clear anti-snag
slip on boots and factory moulded RJ-45 plugs at both end LSZH sheath.
Please 26 AWG also as in patch cord it is easier to do rack dressing and increase flexibility . As per Draft RFP
31 96 Item No.36 Point 8 Load bar polycarbonate, Jacket
FRPVC
Plesae remove this line as Jacket asked in point no 4 is LSZH and here PVC request to remove this line to avoid
confussion
As per Draft RFP
RFP for MPLS, P2P & ILL connectivity and Procurement of Network hardware & LAN Infra under RajNET Project through Rate Contract
NIB Ref No: F3.3(292)/RISL/Pur/2020/8086
RESPONSES TO PREBID QUERIES/SUGGESTIONS/CLARIFICATIONS
32 97 Item No.37 Point 4 4 Pair 24 AWG Copper Cable with integral cross member pair, transparent slim line clear anti-snag
slip on boots and factory moulded RJ-45 plugs at both end LSZH sheath.
Please 26 AWG also as in patch cord it is easier to do rack dressing and increase flexibility . As per Draft RFP
33 97 Item No.37 Point 8 Load bar polycarbonate, Jacket
FRPVC
Plesae remove this line as Jacket asked in point no 4 is LSZH and here PVC request to remove this line to avoid
confussion
As per Draft RFP
34 98 Item No.38 Point 4 4 Pair 24 AWG Copper Cable with integral cross member pair, transparent slim line clear anti-snag
slip on boots and factory moulded RJ-45 plugs at both end LSZH sheath.
Please 26 AWG also as in patch cord it is easier to do rack dressing and increase flexibility . As per Draft RFP
35 98 Item No.38 Point 8 Load bar polycarbonate, Jacket
FRPVC
Plesae remove this line as Jacket asked in point no 4 is LSZH and here PVC request to remove this line to avoid
confussion
As per Draft RFP
36 14 4 B a) A valid UASL/USL/CMTS/2G/3G And NLD License for Rajasthan Telecom Circle duly issued by DoT same is not required for providing ILL/MPLS & NLD services. IBW services are provided through Unified License &
MPLS/P2P services comes under NLD License same may be considered. The above condition disqualifies POWER GRID
Corporation of India Limited ( A Maharatna PSU under ministry of POWER from participating & a partner of National
Knowledge Network) to come as NBSP & restricts competition.
A valid UL-Internet Service-Category-A and NLD
Licenses for Rajasthan Telecom Circle duly issued by
DoT.
37 80 2.2 Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink
portspopulated with 1G
single mode transceivers.
Please clarify, do we need to consider internal redundant power supplies for higher avaliability? Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers38 81 3.4 The Switch should support stacking of switches Please clarify, with stacking do we consider switches with Virtual chassis/IRF/VSS/equivalent technology? The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements. 39 81 5.4 The switch should have to support OSPFv2 and OSPFv3 protocols for
routing from day 1
Please clarify, do we need to consider BGP for IPv4 and IPv6 from day-1? As per Draft RFP
40 84 8 Ethernet 10/100 ports and 2 dual-purpose uplinks (each dual-purpose uplink port has 1 10/100/1000 Ethernet port
and 1 SFP-based Gigabit Ethernet port with single mode transceiver, 1 port active)
We don’t have fast ethernet switches, as technology is outdated, so please consider 8x1G Base-T PoE+ switch with
2x1G SFP+ slots
8 Ethernet 10/100/1000 ports and 2 SFP-based
Gigabit Ethernet uplink port with populated single
mode transceiver
41 85 IPv6 protocol support Please clarify, with IPv6, do we need to prioritise the IPv6 traffic and IPv6 ACL for security? As per Draft RFP
42 86 OEM should be in " Leaders Quadrant of latest Gartner's magic
Quadrant for the Wired and wireless LAN access infrastructure
2019"
The Leaders quadrant has Cisco, HPE and Extreme OEM's, which is restricting open competition, so request you to
consider all OEM's featured in Gartners magic quadrant report as being considered for L3 Switches. Please change
clause as
OEM should be in " latest Gartner's magic Quadrant for the Wired and wireless LAN access infrastructure 2019" And
all switches shall be from same OEM for ease of integration
As per Draft RFP
43 Page 81 Item No. 25: - L3 Switch
1.1
1.1OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change this clause to
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
44 Page 81 Item No. 25: - L3 Switch
2.2
2.2 Should have Minimum 16 RJ-45
autosensing 10/100/1000 ports
and separate 2*1Gbps Fiber based
SFP Uplink portspopulated with 1G
single mode transceivers.
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 4*1Gbps Fiber based SFP
Uplink ports populated with 1G single mode transceivers.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers
45 Page 82 Item No. 25: - L3 Switch
8.15
3.4The Switch should support stacking of switches The switch should support dedicated stacking port separate from uplink ports with 48 Gbps of stacking bandwidth.
Justification : with 48Gbps stacking bandwidth, can support higher data transfer between stacked switches of 2 or
more.
The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements.
46 Page 82 Item No. 25: - L3 Switch
5.2
5.2The switch should support minimum 256 static IP routing Request to change this clause to
"The switch should support minimum 256 static IP routing / 1000 IPv4 routes"
Justification: For layer 3 switch, having routing protocol running will have better results in terms of
redundancy and resiliency. Request to allow 1000 Routes as alternative.
The switch should support minimum 256 static IP
routing / 1000 IPv4 routes"
47 Page 84 Item No. 25: - L3 Switch
8.15
8.15 The switch should support IPv6 Guard, Source-Guard features Request to change this clause to
Switch should support IPv6 Source Guard,IPv6 DHCP Guard, IPv6 RA Guard, IPv6 Neighbour Discovery Inspection,
Neighbour Discovery (ND) protocol snooping, IPv6 Prefix Guard, IPv6 Destination Guard
Justification: Above are bare minimum IPv6 feature required for basic IPv6 security.
As per Draft RFP
48 Page 81 Item No. 25: - L3 Switch New Clause Request to add clause
Switch should support External/Internal Redundant Power Supply.
Justification : Being Layer 3 switch will be installed at important locations, This switch should have provision to
support redundant power supply to continue operations.
As per Draft RFP
49 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Must have SDCard/memory card for easier switch Replacement , to ensure that field switch does not require
reconfiguration and storage cards can be swapped.
As per Draft RFP
50 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Switch must support IPv6 management and troubleshooting features like IPv6 Ping, IPv6 traceroute, IPv6 Telnet, IPv6
SSH, HTTP over IPv6, SNMP over IPv6 and Dual Stack
Justification : These are basic IPv6 features needed for both layer 2 or Layer 3 switch and must for Network basic
operations/troubleshooting.
As per Draft RFP
51 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Shall support IEEE 802.3az Energy- efficient Ethernet (EEE) to reduce power consumption
Justification: This feature helps in reducing power consumption
As per Draft RFP
52 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Switch should support UDLD, MLD v1 and v2 snooping, IP Source Guard features.
Justification : This are basic features for layer 2 switch and help for better traffic management and security
As per Draft RFP
53 Page 79 Item No. 21: - SFP -1G-LR
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, "SFP -1G-LR" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
54 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
55 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
56 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
57 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, " GLC-EX-SMD" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
58 Page 79 3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible with SFP MSA Request to change as below
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible
Type Gigabit Ethernet, Single Mode Fiber
Transceiver Compatible
59 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
60 Page 79 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
61 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
62 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
63 Page 80 Item No. 23: - SFP -10G-
LR for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
64 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
65 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
66 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
67 Page 80 Item No. 24: - SFP -10G-
ER for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
68 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
69 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
70 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
71 13 4. Pre-Bid Qualification
Criteria
S.No. 2 - Financial
Turnover
Annual Average Turnover of the bidder from IT/ ITeS/ Networking(Active/Passive Network Component/ Data Center
Equipments) during the last three financial years, i.e., 2016-2017 to 2018-19 (as per the last published audited
balance sheets), should be at least Rs. 250 crores
We request you to please amend the clause as:
"Annual Average Turnover of the bidder during the last three financial years, i.e., 2016-2017 to 2018-19 (as per the
last published audited balance sheets), should be at least Rs. 250 crores
AND
Annual Turnover of the bidder from IT/ ITeS/ Networking(Active/Passive Network Component/ Data Center
Equipments) during the last financial year, i.e., 2018-19 should be at least Rs. 40 crores"
As per Draft RFP
72 91 Item No.30 Point 5 Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals (ETL report for zero bit should be submitted)
Please put slash is cross member/fluted member as both are different types of separators .Also request to remove Zero
Bit Error verified by ETL as this test is outdated and no OEM get this ETL verification program done and same can be
cjecked from Intertek website under ETL verification program directory ( https://www.intertek.com/cabling-products/)
Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
73 91 Item No.30 Point 7 Box of 305 meters Packing, 45ns MAX. Delay Skew, 100 Ohms + /- 15 ohms for 1 to 250 MHz Allow Box packing of 500 meters also as mostly european companies provide 500 meter cable box Box of 305/500 meters Packing, 45ns MAX. Delay
Skew, 100 Ohms + /- 15 ohms for 1 to 250 MHz
74 92 Item No.31 Point 5 Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals (ETL report for zero bit should be submitted)
Please put slash is cross member/fluted member as both are different types of separators .Also request to remove Zero
Bit Error verified by ETL as this test is outdated and no OEM get this ETL verification program done and same can be
cjecked from Intertek website under ETL verification program directory ( https://www.intertek.com/cabling-products/)
Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
75 92 Item No.31 Point 7 Box of 305 meters Packing, 45ns MAX. Delay Skew, 100 Ohms + /- 15 ohms for 1 to 250 MHz Allow Box packing of 500 meters also as mostly european companies provide 500 meter cable box Box of 305/500 meters Packing, 45ns MAX. Delay
Skew, 100 Ohms + /- 15 ohms for 1 to 250 MHz
76 93 Item No.32 Point 5 Accessories Strain relief and bendlimiting
boot for cable , Approval UL or ETL or 3P
Plesae make it Approval UL and ETL verified or 3P verified (ETL alone done not mean any thing as ETL verified is the
conformance mark )Also UL is for fire and ETL and 3P are for performance so option between ETL verified or 3P can be
given but UL being a different certificate can not be included in option
As per Draft RFP
77 93 Item No.32 Point 9 ROHS Compliant , 3rd party from bodies like ETL verified (ETL report should be submitted) Pleae make it 3rd party from bodies like ETL verified/3P (ETL/3P certificate to be available on respective
website).These verification certificates are on only valid if they are present on testing lab website .
As per Draft RFP
78 93 Item No.32 Point 11 1-port with shutter , High ImpactPlastic Body ABS material Please allow hinged dust cover also As per Draft RFP
79 93 Item No.32 Point 13 Screw hole covers – to be suppliedwith plate Please remove as it differs on OEM to OEM design As per Draft RFP
80 93 Item No.32 Point 14 Plug in Icons – Icon tree – to be supplied with plate This is OEM specific only one OEM complies please remove As per Draft RFP
81 94 Item No.33 Point 14 Jack Panel should be RoHS Complaint Please add certification for information outlet in panel also like IO is Jack panel should be ETL verified/3P verified
(ETL/3P certificate to be available on respective website)
As per Draft RFP
82 95 Item No.34 Point 14 Jack Panel should be RoHS Complaint Please add certification for information outlet in panel also like IO is Jack panel should be ETL verified/3P verified
(ETL/3P certificate to be available on respective website)
As per Draft RFP
83 95 Item No.35 Point 4 4 Pair 24 AWG Copper Cable with integral cross member pair, transparent slim line clear anti-snag
slip on boots and factory moulded RJ-45 plugs at both end LSZH sheath.
Please 26 AWG also as in patch cord it is easier to do rack dressing and increase flexibility . As per Draft RFP
84 95 Item No.35 Point 8 Load bar polycarbonate, Jacket
FRPVC
Plesae remove this line as Jacket asked in point no 4 is LSZH and here PVC request to remove this line to avoid
confussion
As per Draft RFP
85 96 Item No.36 Point 4 4 Pair 24 AWG Copper Cable with integral cross member pair, transparent slim line clear anti-snag
slip on boots and factory moulded RJ-45 plugs at both end LSZH sheath.
Please 26 AWG also as in patch cord it is easier to do rack dressing and increase flexibility . As per Draft RFP
86 96 Item No.36 Point 8 Load bar polycarbonate, Jacket
FRPVC
Plesae remove this line as Jacket asked in point no 4 is LSZH and here PVC request to remove this line to avoid
confussion
As per Draft RFP
87 97 Item No.37 Point 4 4 Pair 24 AWG Copper Cable with integral cross member pair, transparent slim line clear anti-snag
slip on boots and factory moulded RJ-45 plugs at both end LSZH sheath.
Please 26 AWG also as in patch cord it is easier to do rack dressing and increase flexibility . As per Draft RFP
88 97 Item No.37 Point 8 Load bar polycarbonate, Jacket
FRPVC
Plesae remove this line as Jacket asked in point no 4 is LSZH and here PVC request to remove this line to avoid
confussion
As per Draft RFP
89 98 Item No.38 Point 4 4 Pair 24 AWG Copper Cable with integral cross member pair, transparent slim line clear anti-snag
slip on boots and factory moulded RJ-45 plugs at both end LSZH sheath.
Please 26 AWG also as in patch cord it is easier to do rack dressing and increase flexibility . As per Draft RFP
90 98 Item No.38 Point 8 Load bar polycarbonate, Jacket
FRPVC
Plesae remove this line as Jacket asked in point no 4 is LSZH and here PVC request to remove this line to avoid
confussion
As per Draft RFP
91 Page 81 Item No. 25: - L3 Switch
1.1
1.1OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change this clause to
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
92 Page 81 Item No. 25: - L3 Switch
2.2
2.2 Should have Minimum 16 RJ-45
autosensing 10/100/1000 ports
and separate 2*1Gbps Fiber based
SFP Uplink portspopulated with 1G
single mode transceivers.
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 4*1Gbps Fiber based SFP
Uplink portspopulated with 1G single mode transceivers.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers
93 Page 82 Item No. 25: - L3 Switch
8.15
3.4The Switch should support stacking of switches The switch should support dedicated stacking port separate from uplink ports with 48 Gbps of stacking bandwidth.
Justificaton : with 48Gbps stacking bandwidth, can support higher data transfer between stacked switches of 2 or
more.
The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements.
94 Page 82 Item No. 25: - L3 Switch
5.2
5.2The switch should support minimum 256 static IP routing Request to change this clause to
"The switch should support minimum 256 static IP routing / 1000 IPv4 routes"
Justification: For layer 3 switch, having routing protocol running will have better results in terms of
redundancy and resiliency. Request to allow 1000 Routes as alternative.
The switch should support minimum 256 static IP
routing / 1000 IPv4 routes"
95 Page 84 Item No. 25: - L3 Switch
8.15
8.15 The switch should support IPv6 Guard, Source-Guard features Request to change this clause to
Switch should support IPv6 Source Guard,IPv6 DHCP Guard, IPv6 RA Guard, IPv6 Neighbor Discovery Inspection,
Neighbor Discovery (ND) protocol snooping, IPv6 Prefix Guard, IPv6 Destination Guard
Justification: Above are bare minimum IPv6 feature required for basic IPv6 security.
As per Draft RFP
96 Page 81 Item No. 25: - L3 Switch New Clause Request to add clause
Switch should support External/Internal Redundant Power Supply.
Justification : Being Layer 3 switch will be installed at important locations, This switch should have provision to
support redundant power supply to continue operations.
As per Draft RFP
97 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Must have SDCard/memory card for easier switch Replacement , to ensure that field switch does not require
reconfiguration and storage cards can be swapped.
As per Draft RFP
98 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Switch must support IPv6 management and troublshooting features like IPv6 Ping, IPv6 traceroute, IPv6 Telnet, IPv6
SSH, HTTP over IPv6, SNMP over IPv6 and Dual Stack
Justification : These are basic IPv6 features needed for both layer 2 or Layer 3 switch and must for Network basic
operations/troubleshooting.
As per Draft RFP
99 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Shall support IEEE 802.3az Energy- efficient Ethernet (EEE) to reduce power consumption
Justificaiton : This feature helps in reducing power consumption
As per Draft RFP
100 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Switch should support UDLD, MLD v1 and v2 snooping, IP Source Guard features.
Justificaiton : This are basic features for layer 2 switch and help for better traffic management and security
As per Draft RFP
101 Page 79 Item No. 21: - SFP -1G-LR
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, "SFP -1G-LR" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
102 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
103 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
104 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
105 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, " GLC-EX-SMD" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
106 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible with SFP MSA Request to change as below
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible
Type Gigabit Ethernet, Single Mode Fiber
Transceiver Compatible
107 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
108 Page 79 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
109 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
110 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
111 Page 80 Item No. 23: - SFP -10G-
LR for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
112 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
113 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
114 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
115 Page 80 Item No. 24: - SFP -10G-
ER for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
116 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
117 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
118 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
119 74/141 Item No. 17: - 6U Wall
Mount indoor Network
Rack
12 > Certifications > UL Listed. Only one or two rack OEM has UL certificate which is for their safety standard, not for the construction of rack, please
remove this condition as already you have asked IS014001:2004, which is meant for Quality Standard, please remove
" UL listed"
As per Draft RFP
120 84/141 Item No. 26: - L3 Outdoor Switch We are considering this as L2 Switch, as you have given permission on Topology Selection "Bidder has to decide switch
model type, be it L2 or L3 as per their design principle"
Bidder has to make sure that spanning tree related
loops are prevented at each and every layer.
121 86/141 Item No. 27: - L 2 Switch OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
Kindly change the requirement as "OEM should be in "Gartner Magic Quadrant for wired and wireless LAN 2019" as
you have asked in L3 Switch, for not restricting OEM to participate
As per Draft RFP
122 86/141 Item No. 27: - L 2 Switch 1.4 > 128 MB flash, 256 MB DRAM the size of Flash is OEM specific as it is used to store the IOS , which can be compact , kindly don't restrict on this, as
size of DRAM is usually considered for full functionality
Please change the size to " 32 MB Flash "
As per Draft RFP
123 87/141 Item No. 27: - L 2 Switch 4.3 > DiffServ Differentiated services (DiffServ) is sub set of Quality of Service (QoS) policies. Which is already complied ,
Kindly remove separate support of " DiffServ"
As per Draft RFP
124 90/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Unshielded Twisted Pair, Category 6, TIA / EIA 568-C.2: (UL certificate should be submitted for CMR rating) 23 AWG
solid bare copper conductor
Usually CM rated cable is widely available, suitable for in-wall installation of Ethernet cables, while CMR cable is
suitable for use in Riser installation between floors , CM type is inexpensive 23 AWG solid bare copper conductor,
asking for CMR is only increasing the cost of cable and favouring some specific OEM. so Please change to "
(UL certificate should be submitted for CM/CMR rating"
Unshielded Twisted Pair, Category6, TIA / EIA 568-
C.2: (UL certificate should be submitted for CM/CMR
rating) 23 AWG solid bare copper conductor
125 91/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Polyethylene insulation/LSZH, CMR rated jacket as per UL 1666 or IEC 60332-3 When we are requesting to change the requirement to CM/CMR , please change to " FRPVC CM/CMR rated jacket as
per UL 1666 or IEC 60332-3 "
Polyethylene insulation/LSZH, CM/CMR rated jacket
as per UL 1666 or IEC 60332-3
126 91/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals {ETL report for zero bit should be submitted)
Certificate to be submitted accordingly for CM/CMR type cable Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
127 92/141 Item No.31: - Cat 6
Ethernet Cable
Unshielded Twisted Pair, Category 6, TIA / EIA 568-C.2: (UL certificate should be submitted for CMR rating) 23 AWG
solid bare copper conductor
Usually CM rated cable is widely available, suitable for in-wall installation of Ethernet cables, while CMR cable is
suitable for use in Riser installation between floors , CM type is inexpensive 23 AWG solid bare copper conductor,
asking for CMR is only increasing the cost of cable and favouring some specific OEM. so Please change to "
(UL certificate should be submitted for CM/CMR rating"
Unshielded Twisted Pair, Category6, TIA / EIA 568-
C.2: (UL certificate should be submitted for CM/CMR
rating) 23 AWG solid bare copper conductor
128 92/141 Item No.31: - Cat 6
Ethernet Cable
Polyethylene insulation/LSZH, CMR rated jacket as per UL 1666 or IEC 60332-3 When we are requesting to change the requirement to CM/CMR , please change to " FRPVC CM/CMR rated jacket as
per UL 1666 or IEC 60332-3 "
Polyethylene insulation/LSZH, CM/CMR rated jacket
as per UL 1666 or IEC 60332-3
129 92/141 Item No.31: - Cat 6
Ethernet Cable
Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals (ETL report for zero bit should be submitted)
Certificate to be submitted accordingly for CM/CMR type cable Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
130 92/141 Item No.31: - Cat 6
Ethernet Cable
Attenuation(dB/100m) 32.8MAX. At 250MHz, 43.2MAX. At 400MHz, 54.8MAX. at 250 MHz Please check as different Attenuation(dB/100m) value is asked for 250 MHz, Please ask to submit the channel
performance chart in datasheet
Attenuation(dB/100m) - 32.8MAX. At
250MHz
131 93/141 Item No. 32: -
Information Outlets
Jack contacts : Beryllium copper Please add the option of " The Jack contact can be phosphor bronze with gold plated " which is widely accepted Jack contacts: Beryllium copper/ phosphor bronze
with thick gold and minimum thick nickel under
plate, Performance
Characteristics Attenuation, NEXT,
PS NEXT, FEXT and Return Loss, IDC
Contact: Phosphor bronze
50micron" gold plated contact
Surface
132 98/141 Item No. 39: - 6 core
ADSS OFC
Compliance to TEC/GR/TX/OAF-001/03 MAR 2017 and GR No. GR/OAF-01/02. JUL 2005 and subsequent
amendments, if any.
TEC/GR is very rare available and very few 1 or 2 OEM are complied to this, being ADSS construction, it should be
allowed on the performance basis and should have approval EIA/TIA in place of TEC GR,
As per Draft RFP
133 Page 81 Item No. 25: - L3 Switch
1.1
1.1OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change this clause to
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
134 Page 81 Item No. 25: - L3 Switch
2.2
2.2 Should have Minimum 16 RJ-45
autosensing 10/100/1000 ports
and separate 2*1Gbps Fiber based
SFP Uplink portspopulated with 1G
single mode transceivers.
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 4*1Gbps Fiber based SFP
Uplink portspopulated with 1G single mode transceivers.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers
135 Page 82 Item No. 25: - L3 Switch
8.15
3.4The Switch should support stacking of switches The switch should support dedicated stacking port separate from uplink ports with 48 Gbps of stacking bandwidth.
Justificaton : with 48Gbps stacking bandwidth, can support higher data transfer between stacked switches of 2 or
more.
The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements
136 Page 82 Item No. 25: - L3 Switch
5.2
5.2The switch should support minimum 256 static IP routing Request to change this clause to
"The switch should support minimum 256 static IP routing / 1000 IPv4 routes"
Justification: For layer 3 switch, having routing protocol running will have better results in terms of
redundancy and resiliency. Request to allow 1000 Routes as alternative.
The switch should support minimum 256 static IP
routing/1000 IPv4 routes
137 Page 84 Item No. 25: - L3 Switch
8.15
8.15 The switch should support IPv6 Guard, Source-Guard features Request to change this clause to
Switch should support IPv6 Source Guard,IPv6 DHCP Guard, IPv6 RA Guard, IPv6 Neighbor Discovery Inspection,
Neighbor Discovery (ND) protocol snooping, IPv6 Prefix Guard, IPv6 Destination Guard
Justification: Above are bare minimum IPv6 feature required for basic IPv6 security.
As per Draft RFP
138 Page 81 Item No. 25: - L3 Switch New Clause Request to add clause
Switch should support External/Internal Redundant Power Supply.
Justification : Being Layer 3 switch will be installed at important locations, This switch should have provision to
support redundant power supply to continue operations.
As per Draft RFP
139 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Must have SDCard/memory card for easier switch Replacement , to ensure that field switch does not require
reconfiguration and storage cards can be swapped.
As per Draft RFP
140 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Switch must support IPv6 management and troublshooting features like IPv6 Ping, IPv6 traceroute, IPv6 Telnet, IPv6
SSH, HTTP over IPv6, SNMP over IPv6 and Dual Stack
Justification : These are basic IPv6 features needed for both layer 2 or Layer 3 switch and must for Network basic
operations/troubleshooting.
As per Draft RFP
141 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Shall support IEEE 802.3az Energy- efficient Ethernet (EEE) to reduce power consumption
Justificaiton : This feature helps in reducing power consumption
As per Draft RFP
142 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Switch should support UDLD, MLD v1 and v2 snooping, IP Source Guard features.
Justificaiton : This are basic features for layer 2 switch and help for better traffic management and security
As per Draft RFP
143 Page 79 Item No. 21: - SFP -1G-LR
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, "SFP -1G-LR" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
144 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
145 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
146 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
147 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, " GLC-EX-SMD" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
148 Page 79 3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible with SFP MSA Request to change as below
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible
Type Gigabit Ethernet, Single Mode Fiber
Transceiver Compatible
149 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
150 Page 79 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
151 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
152 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
153 Page 80 Item No. 23: - SFP -10G-
LR for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
154 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
155 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
156 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
157 Page 80 Item No. 24: - SFP -10G-
ER for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
158 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
159 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
160 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
161 13 ELIGIBILITY CRITERIA:
Point 4.2
Annual Average Turnover of the bidder from IT/ITeS/ Networking(Active/Passive Network Component/Data Center
Equipments) during the last three financial years, i.e., 2016-2017 to 2018-19 (as per the last published audited
balance sheets), should be at least Rs. 250 crores
We request you to kindly amend the point as under:
Annual Average Turnover of the bidder from IT/ITeS during
the last three financial years, i.e., 2016-2017 to 2018-19 (as per the last published audited balance sheets), should be
at least Rs. 120 crores
As per Draft RFP
162 13 ELIGIBILITY CRITERIA:
Point 4.2
A. The bidder must have successfully completed One project of Supply and Installation of active Networking devices
(Router/ Switches and other active network equipment) value not less than the amount of Rs. 30.00CR during the
period from 01/04/2015 to 31/03/2020. or
two project of Supply and Installation of active Networking devices (Router/Switches and other active network
equipment) value not less than the amount of Rs. 40 CR during the period from 01/04/2015 to 31/03/2019. (Bidder
to submit the documents as per Annexure - 15)
AND
B.The bidder must have agreement with minimum Three NBSP (Network Bandwidth Service Provider) within 15 days
of LOI. At the time of Tripartite agreement,The NBSP should have:
a) Avalid UASL/USL/CMTS/2G/3G And NLD License for Rajasthan Telecom Circle duly issued by DoT.
b) Network management center with DR facility, at different locations in India.
We request you to kindly amend the point as under:
A. The bidder or its consortium Partner must have successfully completed One project of Supply and Installation of
large IT Infrastructure set up or active Networking devices (Router/ Switches and other active network equipment)
value not less than the amount of Rs. 30.00CR during the period from 01/04/2015 to 31/03/2020. or
two projects of Supply and Installation of large IT Infrastructure set up or active Networking devices (Router/Switches
and other active network equipment) value not less than the amount of Rs. 40 CR during the period from 01/04/2015
to 31/03/2019. (Bidder to submit the documents as per Annexure - 15)
AND
B.The bidder must have agreement with minimum Two NBSP (Network Bandwidth Service Provider) within 15 days of
LOI. At the time of Tripartite agreement,The NBSP should have:
a) Avalid UASL/USL/CMTS/2G/3G And NLD License for Rajasthan Telecom Circle duly issued by DoT.
b) Network management center with DR facility, at different locations in India.
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 20.00CR
during the period from 01/04/2015 to
31/03/2020.
or
three project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 40 CR during the
period from 01/04/2015 to
31/03/2020.
(Bidder to submit the documents as per
Annexure - 15)
163 49 Joint Venture, Consortium or Association We request you to kindly allow consortium of at least two parties. As per Draft RFP
164 74/141 Item No. 17: - 6U Wall
Mount indoor Network
Rack
12 > Certifications > UL Listed. Only one or two rack OEM has UL certificate which is for their safety standard, not for the construction of rack, please
remove this condition as already you have asked IS014001:2004, which is meant for Quality Standard, please remove
" UL listed"
As per Draft RFP
165 84/141 Item No. 26: - L3 Outdoor Switch We are considering this as L2 Switch, as you have given permission on Topology Selection "Bidder has to decide switch
model type, be it L2 or L3 as per their design principle"
Bidder has to make sure that spanning tree related
loops are prevented at each and every layer.
166 86/141 Item No. 27: - L 2 Switch OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
Kindly change the requirement as "OEM should be in "Gartner Magic Quadrant for wired and wireless LAN 2019" as
you have asked in L3 Switch, for not restricting OEM to participate
As per Draft RFP
167 86/141 Item No. 27: - L 2 Switch 1.4 > 128 MB flash, 256 MB DRAM the size of Flash is OEM specific as it is used to store the IOS , which can be compact , kindly don't restrict on this, as
size of DRAM is usually considered for full functionality
Please change the size to " 32 MB Flash "
As per Draft RFP
168 87/141 Item No. 27: - L 2 Switch 4.3 > DiffServ Differentiated services (DiffServ) is sub set of Quality of Service (QoS) policies. Which is already complied ,
Kindly remove separate support of " DiffServ"
As per Draft RFP
169 90/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Unshielded Twisted Pair, Category 6, TIA / EIA 568-C.2: (UL certificate should be submitted for CMR rating) 23 AWG
solid bare copper conductor
Usually CM rated cable is widely available, suitable for in-wall installation of Ethernet cables, while CMR cable is
suitable for use in Riser installation between floors , CM type is inexpensive 23 AWG solid bare copper conductor,
asking for CMR is only increasing the cost of cable and favouring some specific OEM. so Please change to "
(UL certificate should be submitted for CM/CMR rating"
Unshielded Twisted Pair, Category6, TIA / EIA 568-
C.2: (UL certificate should be submitted for CM/CMR
rating) 23 AWG solid bare copper conductor
170 91/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Polyethylene insulation/LSZH, CMR rated jacket as per UL 1666 or IEC 60332-3 When we are requesting to change the requirement to CM/CMR , please change to " FRPVC CM/CMR rated jacket as
per UL 1666 or IEC 60332-3 "
Polyethylene insulation/LSZH, CM/CMR rated jacket
as per UL 1666 or IEC 60332-3
171 91/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals {ETL report for zero bit should be submitted)
Certificate to be submitted accordingly for CM/CMR type cable Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
172 92/141 Item No.31: - Cat 6
Ethernet Cable
Unshielded Twisted Pair, Category 6, TIA / EIA 568-C.2: (UL certificate should be submitted for CMR rating) 23 AWG
solid bare copper conductor
Usually CM rated cable is widely available, suitable for in-wall installation of Ethernet cables, while CMR cable is
suitable for use in Riser installation between floors , CM type is inexpensive 23 AWG solid bare copper conductor,
asking for CMR is only increasing the cost of cable and favouring some specific OEM. so Please change to "
(UL certificate should be submitted for CM/CMR rating"
Unshielded Twisted Pair, Category6, TIA / EIA 568-
C.2: (UL certificate should be submitted for CM/CMR
rating) 23 AWG solid bare copper conductor
173 92/141 Item No.31: - Cat 6
Ethernet Cable
Polyethylene insulation/LSZH, CMR rated jacket as per UL 1666 or IEC 60332-3 When we are requesting to change the requirement to CM/CMR , please change to " FRPVC CM/CMR rated jacket as
per UL 1666 or IEC 60332-3 "
Polyethylene insulation/LSZH, CM/CMR rated jacket
as per UL 1666 or IEC 60332-3
174 92/141 Item No.31: - Cat 6
Ethernet Cable
Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals (ETL report for zero bit should be submitted)
Certificate to be submitted accordingly for CM/CMR type cable Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
175 92/141 Item No.31: - Cat 6
Ethernet Cable
Attenuation(dB/100m) 32.8MAX. At 250MHz, 43.2MAX. At 400MHz, 54.8MAX. at 250 MHz Please check as different Attenuation(dB/100m) value is asked for 250 MHz, Please ask to submit the channel
performance chart in datasheet
Attenuation(dB/100m) - 32.8MAX. At
250MHz
176 93/141 Item No. 32: -
Information Outlets
Jack contacts : Beryllium copper Please add the option of " The Jack contact can be phosphor bronze with gold plated " which is widely accepted Jack contacts: Beryllium copper/ phosphor bronze
with thick gold and minimum thick nickel under
plate, Performance
Characteristics Attenuation, NEXT,
PS NEXT, FEXT and Return Loss, IDC
Contact: Phosphor bronze
50micron" gold plated contact
Surface
177 98/141 Item No. 39: - 6 core
ADSS OFC
Compliance to TEC/GR/TX/OAF-001/03 MAR 2017 and GR No. GR/OAF-01/02. JUL 2005 and subsequent
amendments, if any.
TEC/GR is very rare available and very few 1 or 2 OEM are complied to this, being ADSS construction, it should be
allowed on the performance basis and should have approval EIA/TIA in place of TEC GR,
As per Draft RFP
178 18 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES
5.1. Detailsof Scope of
Work (SoW)
A. Rate Contract of
MPLS, P2P and Internet
Lease Line connectivity.
2. Implementation:
g) The bandwidth provided shall be discovered in the NMS provided by the RISL/
DoIT&C. This NMS shall be used to monitor the SLA. UAT request shall be
accepted only when a link has been detected in NMS.
Kindly share NMS detail provided by RISL for better understanding. As per Draft RFP
179 21 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES
5.1. Detailsof Scope of
Work (SoW)
B. Rate Contract for
Network Infrastructure
a. Rate Contract for
Network Equipments
The SFP (Small Form-factor pluggable) required as per Annexure - 1 should be compatible with below mentioned
existing network switches and routers:
Sr.NO Make / Model
1 CISCO ASR 9010
2 CISCO ASR 903 & 7206VXRG2/VSAVPNK9
3 CISCO Catalyst 3560 Switch (CISCO WS-C3560G-24PS-E)
4 CISCO ASR 903 / C2911-VSEC/K9
5 Cisco SRW2024P-K9-NA (Model Name: SG300-28P)
6 Cisco SRW224G4P-K9 V02 (Model Name: SF300-24P)
7 Brocade VDX 6740
8 Brocade ICX 7450
9 HP Aruba 2530
We can procure supporting SFP, but support require from Cisco/Broacade/Aruba from RISL end for require
license/Software upgradation to integrate in existing equipment at RISL
As per Draft RFP
180 Uplink for ILL/MPLS is from single point or distributed points? Request for Network Architecture of existing network
with line diagram for better network design
As per Draft RFP
181 73 ANNEXURE-1: BILL OF
MATERIAL (BOM)
PART – B: Network Equipments, LAN Work& Site Shifting (Rate Contract): Kindly provide the timeline for delivery of Whole quantity mentioned in RFP.Also kindly elobarate the criteria of
Payment released against delivered equipments/materials.
As per Draft RFP
182 72 ANNEXURE-1: BILL OF
MATERIAL (BOM)
PART – A: MPLS,P2P and ILL Connectivity (Rate Contract): For MPLS 4 Mbps to 32 Mbps line items -Kindly share the distance from HUB location BW wise. As per Draft RFP
183 29 5.2 Project Milestones,
Deliverables& Timelines
a. For MPLS and P2P & ILL Connectivity Request for payment to be released LOT wise after successful Go Live of the links of respective LOT. As per Draft RFP
184 80 ANNEXURE-1: BILL OF
MATERIAL (BOM)
Item No. 25: - L 3 Switch Kindly allow PMA compliance-Make in India switch for Item No. 25: - L 3 Switch As per Draft RFP
185 30 5.2 Project Milestones,
Deliverables& Timelines
Note:-
a) RISL is working as a Pure Agent and executing the projects on behalf of Government of Rajsthan. All the invoices
should be raised in the name of department for which goods and services will be taken. The name for which billing
will be done, shall be intimated by RISL
Kindly clarify the procedure for bill submission and payment released from RISL(single window) As per Draft RFP
186 29 5.2 Project Milestones,
Deliverables& Timelines
a. For MPLS and P2P &
ILL Connectivity
Note:
The payment process for the work order shall be start after issuing of Go-live date of last lot. However, payable
amount of links shall be effective from Go-live date of Links.
Kindly clarify the allotment of last lot is towards the partial allotment or the last of whole project As per Draft RFP
187 81,87 1.1 OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019". For Switches following has to be adhered : The offered product shall be a domestically manufactured product
complying with the Indian government regulations/ notifications regarding domestically manufactured/ produced
products including requirements of Ministry of Electronics and Information technology (MEITY) notification reference
File No. 1(10)/2017-CLES dated 02/07/2018. The product shall be accepted only on submission of Proof of compliance
to the abovereferred notification. OR
The offered product shall be in the latest Leaders quadrant in the Gartner magic quadrant for relevant items for Year
2019. In case a new Gartner magic quadrant for relevant items is released before the technical bid opening date,
products present in the Leaders quadrant in the new report shall also be accepted.
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
188 82 4.6 IPv6 host and Dual stack (IPv4/IPv6) support to provide transition mechanism from IPv4 to IPv6 This is a L3 feature and in RFP same is mentioned under L2 feature with repeat of same clause in L3 features as well.
our understanding is this is a typo error and same has be to deleted kindly confirm.
As per Draft RFP
189 83 5.6 The switch should support Dual stack (IPV4 and IPV6) to transition from IPv4 to IPv6, supporting connectivity for
both protocols
Dual stack and IPv4 to IPv6 transition both are different set of features and in fact for transition major role is of DNS
server not on switch. We request you to modify the clause as " The switch should support Dual stack (IPV4 and IPV6)".
Kindly confirm.
As per Draft RFP
190 88 3.6 IPv6 host and Dual stack (IPv4/IPv6) support to provide transition mechanism from IPv4 to IPv6 Our understanding is this is a L3 feature and same is not required in L2 switch. We request you to kindly delete the
same from L2 switch specification. Kindly confirm
As per Draft RFP
191 None L3 & L2 switches None There hasn’t been any mention of type of Power Supply for both L3 & L2 switch . We understand that AC Power
supply would be available at these locations and hence both L3 & L2 switches should have AC Power Supply modules.
Please confirm if our understanding is correct.
As per Draft RFP
192 None L3 Outdoor switch None There hasn’t been any mention of type of Power Supply for L2 outdoor switch . as per standard industrial practices
industrial grade switches always haves DC input. we understand DC power module required for outdoor L3 switch and
shall be supply with AC-DC convertor based on the availability of power supply at site . Please confirm if our
understanding is correct.
As per Draft RFP
193 None L3 & L2 switches None Telecom Providers generally deploy routers with flexibility to use AC Power supply module or DC Power Supply
Module as per the requirement. Please confirm if such flexibility is required for these routers also.
As per Draft RFP
194 None NMS None There hasn’t been any features mentioned for NMS functionality for management of switches from a centralized
location. Network with such qty of switches should be deploy with FCAPS model to their respective NMS to enable
ease in management of devices. kindly confirm
As per Draft RFP
195 None NMS None We request to accommodate FCAPS model NMS functionality in RFP along with Qty of NMS in BoQ as well As per Draft RFP
196 12 3 Project Profile Project Profile - The connectivity (MPLS/P2P/ILL) shall be provided to Government offices and shall be integrated
with RajSWAN network. Also the active and passive component of networking shall be deployed in Government
premises.
The connectivity should be integrated to RAJNET or RAJSWAN network , please clarify as both are having different
architecture. Also, the tender subject says RAJNET network and not RAJSWAN. Please amend
As per Draft RFP
197 12 4 PRE-QUALIFICATION /
ELIGIBILITY CRITERIA -
Legal Entity Note: Consortium of firms is not allowed Please clarify why the consortium is not allowed ? In such a large scale project Consortium should be allowed to have
better chances of higher participation
As per Draft RFP
198 13 4 PRE-QUALIFICATION /
ELIGIBILITY CRITERIA -
Technical Capability Please clarify why there is no technical capability requirement mentioned for NBSP. Why is completion certificate not
asked from the NBSP for atleast one major project of similar magnitude.
As per Draft RFP
199 13 4 PRE-QUALIFICATION /
ELIGIBILITY CRITERIA -
Technical Capability Please clarify Why there is no class of NBSP is mentioned ? There is a list of NBSP approved by DOT available on DOT
website. You should ideally allow only CLASS A NBSPs having own network in Rajasthan.
A valid UL-Internet Service-Category-A and NLD
Licenses for Rajasthan Telecom Circle duly issued by
DoT.
200 13 4 PRE-QUALIFICATION /
ELIGIBILITY CRITERIA -
Technical Capability Certifications The bidder must possess, at the time of bidding, a valid ISO 9001 / ISO 20000 / ISO
27001/ CMMi Level V.
Please clarify - Will any one of these documents suffice or all of them required. As per Draft RFP
201 13 4 PRE-QUALIFICATION /
ELIGIBILITY CRITERIA -
PRE-QUALIFICATION / ELIGIBILITY CRITERIA - Financial: Net
Worth The net worth of the bidder as on 31-03- 2019 should be ‘Positive’.
Please clarify - Is there any specific formula for evalutaing the net worth ? Omitted
202 16 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity.
Connectivity termination at end-office and SHQ should be on Ethernet only. Any requirement of converter shall be
provided by bidder only without any cost to purchaser. The cost of earthing for equipment/RF Pole/mast, if any, shall
be included in the Bandwidth charges by the Bidder/SP. The last mile connectivity can be extended by the SP on
radio/OFC, however, required throughput should be ensured by the SP. Network Rack, Router/Layer 3 switch, Rack
and UPS shall be provided by RISL.
i) Connectivity will be terminated on Fast ethernet? Pls confirm
ii) Pls mention what all converters are requried?
Iii) Requisite Space, Power, permission and space will be arranged by RISL, Pls confirm
As per Draft RFP
203 16 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity.
The bidder shall be required to extend FE connectivity to RISL router using LAN cable. Pls confirm avg. distance between POE & Router for cable length As per Draft RFP
204 16 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity.
The orders may be placed in a phased manner i.e. RRC mode Pls provide clarity phased manner As per Draft RFP
205 16 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity.
The bidder has to provide MPLS connectivity from Government premise to RSDC, Jaipur By MPLS it is understood as L3 MPLS, Please confirm. L3 MPLS confiuration at PE, protocol & other details
WAN IP & LAN IP details to be provided by RISL. Pls confirm
As per Draft RFP
206 16 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 1. Pre-
implementation (a)
RISL shall provide the list of sites to be connected to bidder/SPs. Bidder/SPs shallperform Site-survey of all the
ordered location for feasibility. The Bidder/SPs shall intimate feasible links within specified timelines. If no
intimation is provided bybidder/SPs within specified days, it shall be deemed that the site(s)are feasibleto
the bidder/SP.
Claritification will be require on number of Days . Also RISL should provide access letter to the site location to the
Bidder/SP team along with the list of sites for feasibilities. If Bidder/SP are unable to submit the feasibility due to
access issues at the location and if these sites got deemed feasible, Bidder /SP will not pay penalties due to non
feasibilities of such sites later on - RISL needs to first provide the access letter and concerned SPOC to contact in
department and then start considering the timelines for feasibilities in that case.
As per Draft RFP
207 16 5 The broad scope of work for the BIDDER/SP during the period of contract/ engagement includes commissioning &
maintenance of connectivity(MPLS, P2P and Internet Lease Line) provided at various government premises located
anywhere in the State of Rajasthan. The bidder has to provide MPLS connectivity from Government premise to RSDC,
Jaipur. The MPLS topology will be HUB and SPOKE where HUB is RSDC Jaipur and SPOKE locations are various
Government offices across the state.
Please provide the addresses of Government premises as the higher bandwidth requirements would require fibre
laying and the cost varies to lay the fibre varies from city to city.
As per Draft RFP
208 16 5.1 A SCOPE OF WORK, DELIVERABLES AND TIMELINES - It is proposed to enter into Rate Contract with selected SIs at L-1
rates discovered through this tender, as defined in the RFP. Selected Bidder/SI shall be required to sign a tripartite
agreement with RISL and with minimum two NBSP.
Please clarify whether two or three NBSP are required as in the Technical capability it is mentioned as minimum three .
Please correct either of them.
Selected Bidder/SI shall be required to sign a
tripartite agreement with RISL and with minimum
three NBSP
209 16 5.1 A SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.1. Detailsof Scope of Work (SoW) - 1. Pre-implementation c) If
the bidder fails to provide the connectivity after submitting feasibility, a penalty,
as per the provisions contained in the RFP, shall be imposed on per site basis.
The reason for non delivery should not be attributed to NBSP if the Government body changes the location of the
office, denies the pole/mast permission or proper Space and Power is not available. No penalty should be applicable if
the reason are attributed to Government office. Pls confirm on this
As per Draft RFP
210 16 5.1 A SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.1. Detailsof Scope of Work (SoW) - 1. Pre-implementation d)
The requisite space & 5A AC power for installing the equipment at the designated locations shall be provided by
respective state government office/RISL.
The UPS power should be available 24X7 for the MPLS Connectivity with atleast 2 Hrs Power Backup. If power fails and
the links goes down , it should not be attributed to NBSP.
As per Draft RFP
211 17 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 1. Pre-
implementation ( e )
Bidder/SP, in consultation with the nodal officer of the respective location, shall ensure proper positioning and
electric earthing at each designated project location wherever required, before setting up tower/Mast/network CPE
equipments, if any. However, the existing earth at respective location can also be utilized for the indoor equipment
ONLY with proper permission from department/RISL.
Can You please share List of Location where Eathing is currently Present and where it is not As per Draft RFP
212 17 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 1. Pre-
implementation (d)
The requisite space & 5A AC power for installing the equipment at the designated locations shall be provided by
respective state government office/RISL.
UPS power will be required, Pls confirm As per Draft RFP
213 17 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 2. -
implementation (a)
Implementation: Establishment of Network Connectivity
a) Bidder/SP shall establish an end-to-end secure MPLS connectivity (Wired/ Wireless) with requisite bandwidth
without any compression from respective office to SHQ.
What do we mean by secure MPLS, pls clarify. As per Draft RFP
214 17 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 1. Pre -
implementation (e)
Bidder/SP, in consultation with the nodal officer of the respective location, shall
ensure proper positioning and electric earthing at each designated project location
wherever required, before setting up tower/Mast/network CPE equipments, if any.
However, the existing earth at respective location can also be utilized for the indoor
equipment ONLY with proper permission from department/RISL.
We understand this clause is related to earthing for RF mast, pls confirm.
In building earthing for equipments from power source will be arranged by RISL. Pls confirm
As per Draft RFP
215 17 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 2. -
implementation (c)
The last mile connectivity at SHQ shall be provided only on fiber and the last mile connectivity end-office location
may be provided either on Wired / Wireless media. No charges shall be paid for aggregated bandwidth at SHQ.
Pls elaborate aggregated bandwidth at SHQ ? Why is it asked Free of Cost. The NBSP needs to invest a lot for the
Backhaul , please make the Aggregated Bandwidth also chargeable.
As per Draft RFP
216 17 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 2. -
implementation (e)
In case of order for Bandwidth upgradation, the upgradation should be provided in the same link at end office, i.e. if
4 Mbps link is ordered to be upgraded to 6 Mbps then Bandwidth should be increased on the same port. No
additional/separate link/port shall be permitted for upgradation.
Please help to clarify the timelines if any for BW upgradation.
Also, please confirm the higher side BW can go upto.
Upgradation is subject to BW availability & existing Hardware compatibility. Please amend accordingly
As per Draft RFP
217 18 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 2.
Implementation: ( g )
he bandwidth provided shall be discovered in the NMS provided by the RISL/
DoIT&C. This NMS shall be used to monitor the SLA. UAT request shall be
accepted only when a link has been detected in NMS.
Please Clarify which NMS is used by RISL/DoIT&C to Mointor the links As per Draft RFP
218 18 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 2. -
implementation (l)
The Bandwidth provided should be transparent to Video, Audio, Data and IP address i.e. it should be possible for
RISL/DoITC to implement QoS and utilize allocated IP Range.
QOS has to be configure on the SP devices as well, pls share the break up for QOS like bw reserved for voice, video,
data and same will be configured at the SP end
As per Draft RFP
219 18 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 2. -
implementation (n)
The SP/Bidder must obtain the required permission for laying OFC, wherever required, and deposit the charges
prescribed by concerned authority. DoIT&C/RISL shall extend help in obtaining such permission expeditiously.
Customer needs to provide the In-building permission, request to please change accordingly. IBD permission to be
provided by RISL
As per Draft RFP
220 18 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 2. -
implementation (o)
Any other activity to keep the solution/ set-up functional to its full capacity shall be the responsibility of the
bidder/SP.
Other Activity is a broad term, Pls elaborate on other acitivity ? As per Draft RFP
221 18 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 2. -
implementation (g)
The bandwidth provided shall be discovered in the NMS provided by the RISL/ DoIT&C. This NMS shall be used to
monitor the SLA. UAT request shall be accepted only when a link has been detected in NMS.
The router provided by the customer should support the feature. Request to please add that in case of any issue with
NMS the delay will not be attributed to SP.
As per Draft RFP
222 19 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 3. Testing &
Commissioning ( c )
RISL shall carry out the UAT of established links in the previous month subject to a lot size
of minimum 80% links i.e. Go-Live shall be given in a lot. Since there may be possibility of
some links failing in UAT, the bidder is advised to offer more number of links for UAT. No
more than three lots shall be accepted for UAT for each PO
As minimum 80% Link need to be submitted and the max lots can be 3 . So Bidder can share any Mix of % in these
three Lots which total combined to 80% of Links as per PO , Is our understanding correct
As per Draft RFP
223 19 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 3. Testing &
Commissioning ( d )
Bidder shall be required to acquire an acknowledgement letter of establishment of
connectivity from the end-office location.The established connectivity must be detected in
RISL NOC.
Need Clarity on established connectivity must be detected in
RISL NOC. , What all paramter require to Detected a link in RISL NOC and what would be the format of the letter.
As per Draft RFP
224 19 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 3. Testing &
Commissioning ( e ) A , B
For MPLS Links
i. Latency (Round-trip): The average round trip delay for 1000 diagnostic packets of 100 bytes each between
respective end offices should be less than 60 milliseconds.
ii. Packet Loss: Packet loss for 1000 diagnostic packets of 100 bytes each to transit from end office to DHQ/SHQ
equipment should be < 3%. Three such consecutive tests shall be performed with a time interval of 5 min each to
verify the packet loss/ drop percentage in each link.
iii. Load Test: A file transfer test between respective end offices using FTP may be done to verify the effective
bandwidth/ throughput, if felt necessaryby RISL B. For P2P Links
i. Latency (Round-trip): The average round trip delay for 1000 diagnostic packets of 1500 bytes each between
respective end offices should be less than 40 milliseconds.
ii. Packet Loss: Packet loss for 1000 diagnostic packets of 1500 bytes each to transit from DHQ PoP Equipment to
respective Div.HQ PoP and SHQ equipment should be <1%. Three such consecutive tests shall be
performed with a time interval of 5 min each to verify the packet loss/ drop percentage in each link.
iii. Load Test: A file transfer test between respective end offices using FTP
may be done to verify the effective bandwidth/ throughput, if felt necessary
by RISL
Need Clarification on Latency , as this can only be committed bases the location details shared , However at this point
Bidder is not known to the location address … Need clarity on this . Also as per Industry Standard parameter Packet
loss is 5% . Load Test : AN FTP mode of testing is not very reliable to get the link tested , as it involve many parameter
ie Bandwidth at FTP Server , Capacity of FTPServer , Application used for this FTP Transfer . We would like to
recommend BERT testing for bandwidth/ throughput
As per Draft RFP
225 19 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 3. Testing &
Commissioning ( e ) A , B
Packet
drop <=0.05
Industry Standard is 1% , So request to get it change to 1% As per Draft RFP
226 20 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 3. Testing &
Commissioning:
On successful AT by DoIT&C/RISL of the link, the event shall be marked as the “Date of
Commissioning” of the lot.
Please consider the date of delivery as the date of link commissioning. Also, please allow to start billing of each link
from the date of delivery . The acceptance date should be Bidder/SP system policy means if UAT is not carried by RISL
in specific period and link get auto accepted then the same date should be eligible for billing date or there should be
mutual acceptance on UAT days requirement.
As per Draft RFP
227 20 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 3. Testing &
Commissioning:
Latency (Round-trip): The average round trip delay for 1000 diagnostic packets of 100 bytes each should be less than
50 milliseconds.
Request to change the latency required from less than 50ms to 80ms. As per Draft RFP
228 20 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity. 3. Testing &
Commissioning:
A period of one week shall be taken for conduct of UAT for each lot. Any delay, due to reasons assignable to the
purchaser, beyond this period shall not be counted on part of SP/bidder.
Please confirm the lot size if the numbe rof locations for which the PO is issued is greater than 10 As per Draft RFP
229 21 Post-implementation:
Network Management
Services and FM( b)
Bidder/SP shall proactively monitor and maintain all the commissioned links for desired
uptime and performance as per agreed SLA.
RISL/ DoIT&C SHOULD PROVIDE Read Only Access and String of the router to mointor these links As per Draft RFP
230 21 Post-implementation:
Network Management
Services and FM( C)
RISL may request for discontinuation of a particular link before expiry of Project period
by giving One month notice. The payment to the SP/Bidder for such discontinued link(s)
shall be made on pro-rata basis upto the notified termination date or actual date of
removal of the connectivity whichever is earlier.
Need More clarity on this as there should be some Minimum Timeframe for disconnect as bidder will already got their
Invesment done to get this link delivered . Why disconnection is required, bidder/SP would be incurring capex to
connect the location. It is requested to run the link as per the contract period of 3 years.
As per Draft RFP
231 21 5.1 A SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.1. Detailsof Scope of Work (SoW) - 4. Post-implementation:
Network Management Services and FMS - a) Since the tickets shall be generated using the existing HP EMS installed
under RajNET, the BIDDER/SP shall ensure with the respective operator that the tickets are closed on restoration of
fault. The BIDDER/SP’s support should coordinate for ticket management and monitoring of Faulty/Down circuits.
Any communication like phone call, email, fax etc. shall be treated as logging of fault and duration shall be counted
till the link is up
and operational.
Please clarify the clause. The HP EMS belongs to RISL and the NOC Management team book the ticket on respective
NBSP Helpline. The IRT should start once the complaint is logged by the respective department on NBSP Helpline No or
email id. The NBSP shall not book any complaint on behalf of RISL and the respective department.
As per Draft RFP
232 21 5.1 A SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.1. Detailsof Scope of Work (SoW) - 4. Post-implementation:
Network Management Services and FMS - a) Some Links may be required to be shifted to new location during O&M
period. The Bidder/SP shall be required to uninstall, pack, shift, unpack, re-install and configure at new site location
during contract period without any additional cost to the Purchaser, RISL will provide the required time to lay OFC to
concern bidder/SP in such shifting cases.Such links will not be more than 1% of order given during contract period
The NSBP should be allowed to do the feasibility of the new location . If the site is found not feasible , no penalty
should be imposed on NBSP.
As per Draft RFP
233 21 5.1 A SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.1. Details of Scope of Work (SoW) - 4. Post-implementation:
Network Management Services and FMS -b) Bidder/SP shall proactively monitor and maintain all the commissioned
links for desired uptime and performance as per agreed SLA.
Proactive monitoring is not possible as the NMS belongs to RISL and we will work on open tickets. Please remove the
clause .
As per Draft RFP
234 21 5.1 A SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.1. Details of Scope of Work (SoW) - 4. Post-implementation:
Network Management Services and FMS - c) RISL may request for discontinuation of a particular link before expiry of
Project period by giving One month notice. The payment to the SP/Bidder for such discontinued link(s) shall be made
on pro-rata basis upto the notified termination date or actual date of removal of the connectivity whichever is
earlier.
One month notice is too short as we have made investements in delivering the link. Please make the lock in period
atleast one year.
As per Draft RFP
235 26 D. Technical Resources
for Dedicated Single
Point of Contact (SPOC)
Bidder/SP Shall designate and deploy, a dedicated Single Point of Contact
(SPOC), equipped with all the required tools/ resources, for handling day-to-day
issues/ problems/Hardware/monitoring of the links and to co-ordinate with the
RajSWAN/RajNET Operator Team and nodal officers of designated SHQ/Div.
HQ/DHQ PoP locationswithout any additional cost to purchaser/RISL.
Need clarity on the scope of co-ordination required from SP as Router/CPE configuration is in RISL scope and also NMS
is owned by RISL.
As per Draft RFP
236 29 Project Milestones,
Deliverables& Timelines
Lot Size & Commmisioning Timelines Table:- Request RISL/ DoIT&C to Consider 8 Weeks as deilvery timeline for all the links rather than separate time frames. Can
we have delivery timelines of 8 - 10 weeks for all order sizes.
As per Draft RFP
237 29 Payment Terms ii. The payment for each lot shall be released after completion of one quarter from commissioning & Go-Live of the
lot/link.
Please confirm the lot size and request to treat the commissioning/Go-live link wise instead of lot wise As per Draft RFP
238 29 5.2 SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.2 Project Milestones, Deliverables& Timelines - e) Payment
Terms: iii. The payment for each lot shall be released Bi-annually from commissioning & Go-Live of
the lot/link.
The industry practice for payment is Quarterly arrear. Please amend the clause. The payment for each lot shall be released Quarterly
from commissioning & Go-Live of the lot/link
239 29 5.2 SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.2 Project Milestones, Deliverables& Timelines - e) Payment
Terms: Note:-
a) RISL is working as a Pure Agent and executing the projects on behalf of Government of Rajasthan. All the invoices
should be raised in the name of department for which goods and services will be taken. The name for which billing
will be done, shall be intimated by RISL
Who will place the WO to NBSP . If it is RISL /DOITC, the invoices would be in the name of RISL/DOITC and the payment
responsibility lies with RISL / DOITC. Please amend the clause.
As per Draft RFP
240 29 5.2 SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.2 Project Milestones, Deliverables& Timelines -c) The supplier’s/
selected bidder’s request for payment shall be made to the purchaser in writing,
accompanied by invoices describing, as appropriate, the goods delivered and related services performed, and by the
required documents submitted pursuant to general conditions of the contract and upon fulfilment of all the
obligations stipulated in the Contract.
Please clarify what all documents are required to be submitted for payment processing. As per Draft RFP
241 29 5.2 SCOPE OF WORK, DELIVERABLES AND TIMELINES - 5.2 Project Milestones, Deliverables& Timelines -d) Due payments
shall be made promptly by the purchaser, generally within sixty (60) days after submission of an invoice or request
for payment by the supplier/ selected bidder.
Please add a late payment penalty clause like we have LD clause for delivery. If the department fails to pay within 60
days , penalty would be payable to the NBSP.
As per Draft RFP
242 41 25) Right to Vary
Quantities
If the procuring entity does not procure any subject matter of procurement or procures less than
the quantity specified in the bidding documents due to change in circumstances, the
bidder shall not be entitled for any claim or compensation.
b) The rates quoted by the bidder shall be valid for two years from the date of agreement and
purchaser may place purchase orders during this period.
c) Repeat orders for extra items or additional quantities may be placed on the rates and
conditions given in the contract. Delivery or completion period may also be proportionately
increased. The limits of repeat order shall be as under: -
i. 50% of the quantity of the individual items and 50% of the value of original contract in
case of works; and
ii. 50% of the value of goods or services of the original contract.
iii. Such orders shall not be given for a period exceeding one month from the date of
expiry of last supply* (delivery) made and also subject to the condition that price have
since not reduced and purchase were not made on urgent basis.
*Last supply mean supply made under clause (b) above.
It is suggested that any alterations made by RISL in the Scope of Work shall be deemed acceptable to the extent such
alteration does not invoke unreasonable costs that render Bidder/SP to fulfil the obligations to a nullity or is beyond
the capacity of Bidder/SP where such capacity is due to Licenses and permissions granted to Bidder/SP restricted and
regulated by Governmental Agencies. It needs to be informed to RISL that in case of such unreasonable alterations,
Bidder/SP shall not indemnify the RISL or be liable for any deficiency in Services.
It is also suggested that any modification in the contract document shall be in writing with mutual consent of both
parties and RISL alone cannot have this right alone by itself. Such amendment shall be after due negotiation between
the parties to be recorded in writing and made part of the contract.
Repeat Orders shall be subject to negotiations and parties shall arrive at mutually decided rates and ot at the arbitary
rates provided herein.
As per Draft RFP
243 41 6 6. Instructions to Bidders 26. Performance Security - Performance security shall be furnished in any one of the
following forms: -
i. Bank Draft or Banker’s Cheque of a scheduled bank;
ii. National Savings Certificates and any other script/ instrument under National Savings Schemes for promotion of
small savings issued by a Post Office in Rajasthan, if the same can be pledged under the relevant rules. They shall be
accepted at their surrender value at the time of bid and formally transferred in the name of procuring
entity with the approval of Head Post Master;
iii. Bank guarantee/s of a scheduled bank. It shall be got verified from the issuing bank. Other conditions regarding
bank guarantee shall be same as mentioned in the bidding document for bid security;
iv. Fixed Deposit Receipt (FDR) of a scheduled bank. It shall be in the name of procuring entity on account of bidder
and discharged by the bidder in advance. The procuring entity shall ensure before accepting the FDR that the bidder
furnishes an undertaking from the bank to make payment/ premature payment of the FDR on demand to the
procuring entity without requirement of consent of the bidder concerned. In the event of forfeiture of the
performance security, the Fixed Deposit shall be forfeited along with interest earned on such Fixed Deposit.
Please allow NEFT or RTGS and share the details. In view of lockdown facilitating a DD might be difficult As per Draft RFP
244 41 6 6. Instructions to Bidders 26. Performance Security - Performance security furnished in the form specified in clause
[b.] to [e.] of (C) above shall
remain valid for a period of 60 days beyond the date of completion of all contractual obligations
of the bidder, including warranty obligations and maintenance and defect liability period
Please allow PBG for 1 year with renewal on expiry. The amount of PBG depends upon the order value which will keep
on adding till the completion of duration of tender.
As per Draft RFP
245 42 28) Confidentiality d) The obligation of a party under sub-clauses above, however, shall not apply to information that:-
i. the Purchaser or Supplier/ Selected Bidder need to share with RISL or other institutions participating in the
Contract;
Unable to understand on why is the obligation of Confidentiality is not applicable for Information's shared herein with
RISL or other institutions participating in the contract
As per Draft RFP
246 43 Section 30 Code of Integrity We suggest that as a company we have strong Anti-Bribery and Ethical Code of Conduct and all our employees strongly
abide by them. We do not indulge in the instances enumerated that may cause any conflict
As per Draft RFP
247 50
General Terms and
Conditions Section 7 -
Governing Law
Governing Law
The Contract shall be governed by and interpreted in accordance with the laws of the
Rajasthan State/ the Country (India), unless otherwise Bidder/SPecified in the contract.
The Contract shall be governed by and construed in accordance with the laws of India, without regard to any choice of
law or conflict of law provisions that would require the application of the laws of any other jurisdiction. Each Party
irrevocably shall submit to the exclusive jurisdiction of the courts that we recommend should be neutral venue for
both parties over any dispute, controversy or claim (including any question regarding its existence, validity or
termination) arising under or in connection with the Agreement Contract.
As per Draft RFP
248 51 12. Contract Price Prices charged by the Supplier/ Selected Bidder for the Goods delivered and the Related
Services performed under the Contract shall not vary from the prices quoted by the
Supplier/ Selected Bidder in its bid, with the exception of any price adjustments authorized
in the special conditions of the contract.
Does this means that the price quoted in this tender will be applicable for all other existing contracts of SP , Please
clarify. These rates should be for any further contract and not applicable for existing contracts. Pls clarify
As per Draft RFP
249 51 Copyright The copyright in all drawings, design documents, source code and other materials containing data and information
furnished to the Purchaser by the Supplier/ Selected Bidder herein shall remain vested in the Purchaser, or, if they
are furnished to the Purchaser directly or through the Supplier/ Selected Bidder by any third party, including
suppliers of materials, the copyright in such materials shall remain vested in such third party.
Would want to understand from Business team on whether the technical diagram and other submissions made therein
have certain elements of our Intellectual property or concepts that are purely VIL driven in this project, as in case yes
then the same would need to be protected. Therefore it cannot just be passed on to the Purchaser
As per Draft RFP
250 52 Section 17 Sub-
Contracting,
a) The bidder shall not assign or sub-let his contract or any substantial part thereof to any other agency without the
permission of Purchaser/ Tendering Authority.
Can we include the line 'which consent shall not be unreasonably withheld by Purchaser'; since we do not want to be
liable for delay in performing our obligation under the tender due to delay in permission from Purchaser.There are
various vendor involovment as a party of delivery of link and this has to be agreed by department.
As per Draft RFP
251 54 Section 22 Inspection The Purchase Officer or his duly authorized representative shall at all reasonable time have
access to the supplier’s/ selected bidder’s premises and shall have the power at all
reasonable time to inspect and examine the materials and workmanship of the goods/
equipment/ machineries during manufacturing process or afterwards as may be decided.
b) The supplier/ selected bidder shall furnish complete address of the premises of his factory,
office, go-down and workshop where inspection can be made together with name and
address of the person who is to be contacted for the purpose.
c) After successful inspection, it will be suppliers/ selected bidder’s responsibility to dispatch
and install the equipment at respective locations without any financial liability to the
Purchaser. However, supplies when received at respective locations shall be subject to
inspection to ensure whether they conform to the specification
It is suggested that such inspection and audit shall be conducted only during normal business hours upon notice
Specifying the day/date. Such audit or inspection shall be conducted to the extent of permissibility and non-violation
of Service Provider’s applicable laws and regulations. Also, it shall be incumbent to share the details of such
independent auditors before allowing the latter to enter into the service locations under the License where the
network architecture setup is established by the Service Provider. It is also recommended to have this provision
validated with the regulatory team, since there are certain restriction in our license condition on regarding audit being
conducted on the premises.
As per Draft RFP
253 56 Section 31 Patent
Indemnity
The supplier/ selected Bidder/SP shall, subject to the RISL’s compliance with sub-clause
(b) below, indemnify and hold harmless the RISL and its employees and officers from and against any and all suits,
actions or administrative proceedings, claims, demands, losses, damages, costs, and expenses of any nature,
including attorney’s fees and expenses, which the RISL may suffer as a result of any infringement or alleged
infringement of any patent, utility model, registered design, trademark, copyright, or other intellectual property
right registered or otherwise existing at the date of the Contract.
Can we have a mutual clause, wherein RISL would need to indemnify the bidder from the third party claim on
Intellectual Property Rights matter that may be related to compliance by RISL.
As per Draft RFP
254 57 Section 32 Limitation of
Liability
The aggregate liability of the supplier/ selected Bidder/SP to the RISL, whether under the Contract, in tort, or
otherwise, shall not exceed the amount specified in the Contract, provided that this limitation shall not apply to the
cost of repairing or replacing defective equipment, or to any obligation of the supplier/ selected Bidder/SP to
indemnify the RISL with reBidder/SPect to patent infringement.
It is suggested to have the maximum limit of Liability of the Service Provided limited to a sum equal to 100% of the
aggregate value of all charges payable under the Contract during a period of preceding 12 months of the Contract. The
Service Provider shall not be liable for any indirect or consequential damage or loss.
As per Draft RFP
255 57 Section 33 Force Majeure d) If the performance in whole or part or any obligation under the contract is prevented or delayed by any reason of
Force Majeure for a period exceeding 60 days, either party at its option may terminate the contract without any
financial repercussion on either side.
Due to a Force Majeure event, the right to terminate the contract should be on the party non-affected by the Force
Majeure Event and shouldn't be made either party. Requesting relook into the said clause
As per Draft RFP
256 58 35. Termination a)
Termination for Default
ii.
If RISL terminates the contract in whole or in part, amount of PSD may be forfeited. Kindly clarify the meaning of this As per Draft RFP
257 58 35 Termination The tender sanctioning authority of RISL may, without prejudice to any other remedy for breach of contract, by a
written notice of default of at least 30 days sent to the supplier/ selected bidder, terminate the contract in whole or
in par
We need to enforce strict contract lock in unless due to performance issues As per Draft RFP
258 58 35 Termination ii. Depending on merits of the case the supplier/ selected bidder may be appropriately compensated on mutually
agreed terms for the loss incurred by the contract if any due to such termination.
The compensation would need to be as per actual and cannot be based on merits of case depending on Purchaser. All
cost and expenses incurred by bidder needs to be paid forth by Purchaser / Tendering Authority
As per Draft RFP
259 58 7
7. GENERAL TERMS AND CONDITIONS OF TENDER & CONTRACT 34. Change Orders and Contract Amendments If any
such change causes an increase or decrease in the cost of, or the time required for,
the supplier’s/ selected bidder’s performance of any provisions under the Contract, an equitable adjustment shall be
made in the Contract Price or in the Delivery and Completion Schedule, or both, and the Contract shall accordingly
should be amended. Any claims by the supplier/ selected bidder for adjustment under this clause must be asserted
within thirty
(30) days from the date of the supplier’s/ selected bidder’s receipt of the Purchaser’s change order.
This should be subject to feasibility submitted by the NBSP and cost to be beared by department as one time cost. As per Draft RFP
260 58 7
7. GENERAL TERMS AND CONDITIONS OF TENDER & CONTRACT b) If any such change causes an increase or decrease
in the cost of, or the time required for, the supplier’s/ selected bidder’s performance of any provisions under the
Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery and Completion Schedule, or
both, and the Contract shall accordingly should be amended. Any claims by the supplier/ selected bidder for
adjustment under this clause must be asserted within thirty
(30) days from the date of the supplier’s/ selected bidder’s receipt of the Purchaser’s change order.
This should be mutually agreed as there is high risk of PSD forfeiture. Please amend this rule. As per Draft RFP
261 58 7
7. GENERAL TERMS AND CONDITIONS OF TENDER & CONTRACT 35. Termination The tender sanctioning authority of
RISL may, without prejudice to any other remedy for breach of contract, by a written notice of default of at least 30
days sent to the supplier/ selected bidder, terminate the contract in whole or in par
Please amend this. A lot of investment to be made by NBSP for delivering the link. We need to enforce strict contract
lock in unless due to performance issues.
As per Draft RFP
262 59 Section 36 Exit
Management
Entire Clause. It is suggested that the additional services provided by the Service Provider post termination and during the transition
period shall come with a cost borne by the RISL and any penalty or liquidated damages sought shall not be in addition
to termination rights and shall be negotiated with Service Credits proposed by the Service Provider.
Also, the penalty induced from the breach of the obligations by the Service Provider shall not be set off or adjusted
against the payment of invoices rather such dispute claim be referred to the dispute resolution process and the award
of the same shall be final and binding upon the both the parties.
It is suggested that the provision of termination for convenience be allowed only with a provision of a lock-in period
and exit charges. Termination for convenience within the lock-in period shall levy exit charges payable by the RISL to
Service Provider in order to compensate for the loss made by the Service Provider on account of investment under the
Contract.
Transition Plan- Bidder/SP Business Teams to confirm the commercials involved in the transition plan and their
feasibility[ Transfer of Configuration Management Database, Transfer of Assets, Transfer of Software Licenses, Transfer
of Software; Transfer of Documentation, Transfer of Service Management Process, Transfer of Knowledge Base,
Transfer of Service Structure, Transfer of Data, Training Services on Transfer, Transfer Support Activities] within 6 (six)
months prior to expiry or within 2 (two) week of notice of termination of Agreement.
Our suggestions involve with regard to the notice period being short. The Service Provider should be given reasonable
time and this should be calculated basis mutual discussions between both the RISL and Service Provider to enable
optimum results out oif the transition plan. Any Additonal costs and other numeric expenses should be sorted out
before completion of transition period with proper handover mechanisms ogverning the ebtire tranition plan. Hence it
is suggested that ebough room for negotiabiltiy should be prsesent between the RISL and Service Provider for any
transiton Services.
As per Draft RFP
252 55 28 ) Liquidated Damages Liquidated Damages (LD)
a) In case of extension in the delivery period with liquidated damages the recovery shall be
made on the basis of following percentages of value of which the bidder has failed to
supply/commence services:-
b) Fraction of a day in reckoning period of delay in supplies shall be eliminated if it is less than
half a day.
c) The maximum amount of liquidated damages shall be 10% of the contract value.
d) If the supplier requires an extension of time in completion of contractual supply on account
of occurrence of any hindrance, he shall apply in writing to the authority, which has placed
the supply order, for the same immediately on occurrence of the hindrance but not after the
stipulated date of completion of supply.
e) Delivery period may be extended with or without liquidated damages if the delay in the
supply of goods is on account of hindrances beyond the control of the bidder.
f) Bidders must make their own arrangements to obtain import license, if necessary. If a
bidder imposes conditions which are in addition to or in conflict with the conditions
mentioned herein, his bid is liable to summary rejection. In any case none of such
conditions will be deemed to have been accepted unless specifically mentioned in the letter
of acceptance of bid issued by the Purchase Officer.
It is suggested that the additional services provided by the Service Provider post termination and during the transition
period shall come with a cost borne by the RISL and any penalty or liquidated damages sought shall not be in addition
to termination rights and shall be negotiated with Service Credits proposed by the Service Provider.
Also, the liquidated damages induced from the breach of the obligations by the Service Provider shall not be set off or
adjusted against the payment of invoices rather such dispute claim be referred to the dispute resolution process and
the award of the same shall be final and binding upon the both the parties.
It is suggested that the provision of termination for convenience be allowed only with a provision of a lock-in period
and exit charges. Termination for convenience within the lock-in period shall levy exit charges payable by the RISL to
Service Provider in order to compensate for the loss made by the Service Provider on account of investment under the
Contract.
It is suggested that failure or defect for non-readiness of the bandwidth links or to meet SLA Compliance or delay in
Delivery of Services and delay beyond the delivery schedule, a proper mechanism should be in place mutually agreed
between the parties to detect the causation of such defect and its attribution. Under it, the Bidder/SP should be first
notified of such defect and then given reasonable time to remedy such failure/ delay post prior notice for such
delay/failure by RISL to the Bidder/SP.
Also, the clause fails to address the concern when the delay is due to force majeure event or for the reasons
attributable to RISL. The Service Provider cannot be held liable for penalty in case the delay is due to force majeure
event or reasons attributable to RISL.
The Penalty for non-readiness of the bandwidth links or to meet SLA Compliance or delay in Delivery of Services and
delay beyond the delivery schedule.
RISL having the right to terminate the contract with no payment of rental amount is unfair and arbitrary. The period
for equipment replacement should be reasonable and should suffice the replacement of defected equipment in proper
time.
It is suggested that RISL shall pre-inform the Service Provider or mutually agree to a pre-decided day/date for
conducting the test during the peak hours in a given month. The Service Provider shall only agree to the penalty if such
failure to the expected operating requirements is attributable to the Service Provider.
No Cumulative penalty shall be levied or adjusted against the payment to Service Provider. We do not agree to it since
it shall be a cost burden to us in addition to the other penalties. We suggest no such set off should be made.
As per Draft RFP
263 61 Section 37 Settlement of
disputes
Arbitration
Any disputes which may arise out of this Agreement, and which cannot be settled in discussions or negotiations
between the Parties, shall be referred to the appropriate management or higher authorities of the reBidder/SPective
parties to resolve such dispute in good faith. In case no settlement is reached the parties shall refer it to a sole
arbitrator appointed and selected by parties. Arbitration shall be conducted in accordance with the provisions of the
Arbitration and Conciliation (Amendment) Act, 2015 or any other subsequent modifications or enactments thereof.
The venue for Arbitration proceedings shall be Jaipur or any suitable place agreed by all parties. The Arbitration shall
be conducted in English Language and the award shall be binding upon all Parties.
It is suggested that the parties should resolve their disputes by courts directly rather than going for arbitration
proceeding in the second stage of any commercial contracts dispute, on the reasoning that after pronouncement of
arbitration award also there is scope of Appeal to court in the Indian Arbitration Act and it makes the whole process
more time consuming since, then the Lis gets resolved finally by Court order.
As per Draft RFP
264 63 - 64 8 8. SPECIAL TERMS AND CONDITIONS OF TENDER & CONTRACT - SLA for MPLS Connectivity: 2. SLA Matrix: Initial
Response Time (IRT) to rectify and restore the services will be calculated from the time of detection of non-
availability of services either through HDMS/ NMS/ or registration of complaints at Help Desk/Service Window or
any other mechanism adopted under the project (by DoITC/RISL), whichever is earlier.
Please clarify the clause. The IRT should start once the complaint is logged by the respective department on NBSP
Helpline No or email id. The NBSP shall not book any complaint on behalf of the respective department.
As per Draft RFP
265 64 SPECIAL TERMS AND
CONDITIONS OF TENDER
& CONTRACT (Service
Level Requirement for
each link)Point 3
Service Level Requirement for each link:The BIDDER/SP has to maintain the
network uptime at each of the locations as per the table given below:
Request RISL/ DoIT&C to Consider 98% Uptime for P2P & ILL in the same line as of MPLS As per Draft RFP
266 64 Special terms and
Conditions
3. Service Level
Requirement for each
link:
Service Level Requirement for each link: The BIDDER/SP has to maintain the network uptime at each of the locations
as per the table given below:
Location Desired Network Uptime Prime Hours Non-Prime Hours
HUB Sites at SHQ
99%
98%
End Office at SHQ/DHQ level
98%
95%
End Office at BHQ/GP level
96%
92%
Need to amend the clause
Can be applicable for locations with Local contact available 24 hours & access availability.
Most of the locations gets closed after working hours and access is an issue to resolve the trouble ticket in non-prime
hours
As per Draft RFP
267 64 Special terms and
Conditions
3. Service Level
Requirement for each
link:
In addition to IRT, following shall be excluded from fault duration (SLA Exclusion time):
i. Unavailability of circuit due to power failure at purchaser end.
In case of power outage, SP will not have any visibility and control to prove that site was down due to power outage.
Please clarify, how same is going to be attributed in NMS.
SP will not be able to provide any report or sign-off pertaining to power outage at remote location.
As per Draft RFP
268 64 Special terms and
Conditions
3. Service Level
Requirement for each
link:
b) SLA Matrix: Initial Response Time (IRT) to rectify and restore the services will be calculated from the time of
detection of non-availability of services either through HDMS/ NMS/ or registration of complaints at Help
Desk/Service Window or any other mechanism adopted under the project (by DoITC/RISL), whichever is earlier.
IRT to rectify will start once the ticket is logged at the SP helpdesk only as SP will not have any visibility of
HDMS/NMS/CPE installed and controlled by RISL. Request to please amend accordingly.
As per Draft RFP
269 64 8 8. SPECIAL TERMS AND CONDITIONS OF TENDER & CONTRACT - SLA for MPLS Connectivity: 4. Uptime and SLA
exclusion time calculation shall be done as below: 2) In addition to IRT, following shall be excluded from fault
duration (SLA Exclusion time): i. Unavailability of circuit due to power failure at purchaser end.
Please clarify how will RISL / DOITC establish the fact that the power failure is at purchaser end. As per Draft RFP
270 65 Special terms and
Conditions
Point 6. Penalty for non-
achivement of Service
Levels
End Office -Equal % of deduction from payable amount for each link for uptime upto 80%. No payment shall be
made for links having uptime less than 80%.
SHQ- Equal % of deduction from payable amount for all links.
E.g-An end-office at BHQ has uptime of, say, 93% during Prime Hours and 87% during Non-Prime hours for a quarter.
So the breach is (96-93=3%) and (92-87=5%), i.e. total 8%. Therefore, a deduction of 8% shall be made from the
payable amount for the quarter for that particular link.
*Penalty calculation on quaterly basis to be calculated separately for Prime and Non-Prime Hours.
**A penalty of 10% of the link rental of a year of the link, shall be deducted from the payable amount to SP/bidder
for commissioned links.
We understand that time is of the essence and it shall verily be vital for the completion of work by Bidder.
Penalty at the given rate shall not be acceptable since there has to be preventive mechanism to determine the loss of
time between the parties towards delivery and any such loss should be documented with a prior notice to be given by
RISL to the successful bidder and a reasonable opportunity be granted to rectify such delay and catch up with the lost
time. Any such attributable delay in delivery on account of successful bidder shall also be met with service credits to
RISL post any non-fulfilment of rectification of delay.
It is suggested that upon such default, the service provider should be given reasonable time to remedy such failure/
delay post prior notice for such delay/failure by the RISL to the vedor. The penalty should be imposed only after vendor
fails to rectify the default after to failing to remedy such default.
Also the clause fails to address the concern when the default is due to force majeure event or for the reasons
attributable to The RISL. The Selected Bidder cannot be held liable for penalty in case the default is due to force
majeure event or reasons attributable to RISL
As per Draft RFP
271 66 SPECIAL TERMS AND
CONDITIONS OF TENDER
& CONTRACT (Service
Level Requirement for
each link)
Penalty for non-achievement of Latency for P2P connectivity shall be deducted as
below:
As P2P is L1 Links Provided By NBSP and NBSP cannot mointor L1 Circuit Latency , So request you to keep this Clause to
a Inudstry Standard pratice of Min 80ms without Penalty
As per Draft RFP
272 67 8 8. SPECIAL TERMS AND CONDITIONS OF TENDER & CONTRACT - 7. Penalty for non-commissioning of links:
If a SP/Bidder fails to commission the link after declaring the site feasibility within the stipulated time period
provided in the work-order issued by RISL, a penalty of 100% of the link rental of a year of the link, shall be deducted
from the payable amount to SP/bidder for commissioned links.Such links shall be offered to other SP/Bidder for
commissioning.
The cause of failure of delivering should not be attributed to RISL or the concered department. Also, a penalty of 100%
of the link rental of a year of the link is very high and not an industry practise. Please make it as one Qtr rental.
As per Draft RFP
273 106 Annexure - 7 Manufacturer's Authorisation Form (MAF) We request that the title of the Annexure be changed to Services Provider's Authorisation Form, since the bidder is a
service provider and not a Manufacturer.
As per Draft RFP
274 128 ANNEXURE-18:
CERTIFICATE OF
CONFORMITY/ NO
DEVIATION BY OEM {To
be filled by the OEM)
Since the department have not given the list of location for delivering links. The link acceptance should be as per actual
feasibility of the location during delivery
As per Draft RFP
275 14 Clause 4, Pre
qualification/Eligibility
Criteria
B.The bidder must have agreement with minimum Three NBSP (Network Bandwidth Service Provider) within 15 days
of LOI. At the time of Tripartite agreement,The NBSP should have:
a) Avalid UASL/USL/CMTS/2G/3G And NLD
License for Rajasthan Telecom Circle duly
issued by DoT.
b) Network management center with DR
facility, at different locations in India.
Please clarify whether to do the agreement with minimum two NBSP or minimum three NBSP as somewhere it is
written that agreement should be done with minimum two and somewhere written with minimum three NBSP in RFP.
Selected Bidder/SI shall be required to sign a
tripartite agreement with RISL and with minimum
three NBSP
276 14 Clause 4, Pre
qualification/Eligibility
Criteria
B.The bidder must have agreement with minimum Three NBSP (Network Bandwidth Service Provider) within 15 days
of LOI. At the time of Tripartite agreement,The NBSP should have:
a) Avalid UASL/USL/CMTS/2G/3G And NLD
License for Rajasthan Telecom Circle duly
issued by DoT.
b) Network management center with DR
facility, at different locations in India.
Please confirm NBSP can be NLD operator for MPLS and Point to point and allow/consider ILL for ISP. A valid UL-Internet Service-Category-A and NLD
Licenses for Rajasthan Telecom Circle duly issued by
DoT.
277 98 Item No. 39: - 6 core
ADSS OFC
Valid TEC GR Certificate Request to remove the condition of valid TEC GR Certificate as the quantity mentioned in the RFP is very less and such
cable is not in demand in telecom as now a days they take higher count OFC so OFC OEM's are not renewing the TEC
GR certificate, but agrees to keep the clause OEM need to supply the product complying the TEC/GR/TX/OAF-
001/03 MAR 2017 and GR No.
GR/OAF-01/02. JUL 2005 and
subsequent amendments, if any. as same was in Rajnet Bids.
Omitted
278 16 Clause 5, Scope of work
(SoW), Pre
Implementation
RISL shall provide the list of sites to be connected to bidder/SPs. We request to share us the list of probable sites with address where connectivity to be provided or planned so that link
feasibillity and last mile connectivity can be identified by bidder.
As per Draft RFP
279 21 Clause 5, Scope of work,
4. Post-implementation:
Network Management
Services and FMS
c. RISL may request for discontinuation of a particular link before expiry of Project period by giving One month
notice. The payment to the SP/Bidder for such discontinued link(s) shall be made on pro-rata basis upto the notified
termination date or actual date of removal of the connectivity whichever is earlier.
We request to change it that there should be atleast one year lockin period post handover of link as SI/Bidder has
incurred the investment in link feasibilty with last mile connectivity. One month notice should be also be changed to 3
month notice.
As per Draft RFP
280 28 Clause 5.2 Project
Milestones,
Deliverables& Timelines,
Amount Payable For
MPLS and P2P & ILL
Connectivity
Bi-annually at the approved rates over a period of three years from the “Date of Commissioning & Go-
Live” for each lot.
We request to change it to monthly at the approved rates over a period of three years from the “Date of
Commissioning & Go- Live” for each lot.
The payment for each lot shall be released Quarterly
from commissioning & Go-Live of the lot/link
281 30 e) Payment terms, Note Due payments shall be made promptly by the purchaser, generally within sixty (60) days after
submission of an invoice or request for payment by the supplier/ selected bidder.
Due payments shall be made promptly by the purchaser, within fifteen (15) days after submission of an invoice or
request for payment by the supplier/ selected bidder.
As per Draft RFP
282 73 Annexure 1, BoM, PART
– B: Network
Equipments, LAN Work&
Site Shifting (Rate
Contract):
S.No.21, 22, 23,24: SFP -1G-LR/ SFP -1G-ER/SFP -1OG-LR/SFP -10G-ER for CISCO Routers of same OEM SFP -1G-LR/ SFP -1G-ER/SFP -1OG-LR/SFP -10G-ER compatible to CISCO Routers. As warranty and support liability lies
with SI
Query not clear
283 29 5.2 Project Milestones,
Deliverables& Timelines
b.For Network
Equipment
Payment terms
90% of total work order value and remaining 10% in
equated installment yearly i.e 2% at the end of each year OR this remaining 10% may be released against Bank
Guarantee of equal amount.
Please change the payment terms to 7 days for 50% of materials delivery at HO and 40% within 15 days of installation
and link shown on NMS and remaining 10% in equated installment yearly i.e 2% at the end of each year OR this
remaining 10% may be released against Bank Guarantee of equal amount.
As per Draft RFP
284 10 INVITATION FOR BIDS
(IFB)& NOTICE INVITING
BID (NIB)
Security and mode of
Payment
Amount (INR): 216 Lakh We request to change the EMD to 20 lakh as this is rate contract and doesn't give any certainty of the award of whole
of contract in one go, therefore T&C w.r.t EMD be revised accordingly.
As per Draft RFP
285 41 26) Performance Security b) The amount of performance security shall be 5%, of the amount of supply order in case of procurement of goods
and services.
5% of PBG be calculated on the basis of total award of work order instead of LOI value/award of the contract as this is
a rate contarct and doesn't guarantee for whole order. PBG may be obtained on the basis of multiple work order
issued from the department from time to time.
As per Draft RFP
286 Page 81 Item No. 25: - L3 Switch
1.1
1.1OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change this clause to
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
287 Page 81 Item No. 25: - L3 Switch
2.2
2.2 Should have Minimum 16 RJ-45
autosensing 10/100/1000 ports
and separate 2*1Gbps Fiber based
SFP Uplink portspopulated with 1G
single mode transceivers.
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 4*1Gbps Fiber based SFP Uplink
portspopulated with 1G single mode transceivers.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers
288 Page 82 Item No. 25: - L3 Switch
8.15
3.4The Switch should support stacking of switches The switch should support dedicated stacking port separate from uplink ports with 48 Gbps of stacking bandwidth.
Justificaton : with 48Gbps stacking bandwidth, can support higher data transfer between stacked switches of 2 or
more.
The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements.
289 Page 82 Item No. 25: - L3 Switch
5.2
5.2The switch should support minimum 256 static IP routing Request to change this clause to
"The switch should support minimum 256 static IP routing / 1000 IPv4 routes"
Justification: For layer 3 switch, having routing protocol running will have better results in terms of redundancy and
resiliency. Request to allow 1000 Routes as alternative.
The switch should support minimum 256 static IP
routing/1000 IPv4 routes
290 Page 84 Item No. 25: - L3 Switch
8.15
8.15 The switch should support IPv6 Guard, Source-Guard features Request to change this clause to
Switch should support IPv6 Source Guard,IPv6 DHCP Guard, IPv6 RA Guard, IPv6 Neighbor Discovery Inspection,
Neighbor Discovery (ND) protocol snooping, IPv6 Prefix Guard, IPv6 Destination Guard
Justification: Above are bare minimum IPv6 feature required for basic IPv6 security.
As per Draft RFP
291 Page 81 Item No. 25: - L3 Switch New Clause Request to add clause
Switch should support External/Internal Redundant Power Supply.
Justification : Being Layer 3 switch will be installed at important locations, This switch should have provision to
support redundant power supply to continue operations.
As per Draft RFP
292 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Must have SDCard/memory card for easier switch Replacement , to ensure that field switch does not require
reconfiguration and storage cards can be swapped.
As per Draft RFP
293 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Switch must support IPv6 management and troublshooting features like IPv6 Ping, IPv6 traceroute, IPv6 Telnet, IPv6
SSH, HTTP over IPv6, SNMP over IPv6 and Dual Stack
Justification : These are basic IPv6 features needed for both layer 2 or Layer 3 switch and must for Network basic
operations/troubleshooting.
As per Draft RFP
294 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Shall support IEEE 802.3az Energy- efficient Ethernet (EEE) to reduce power consumption
Justificaiton : This feature helps in reducing power consumption
As per Draft RFP
295 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Switch should support UDLD, MLD v1 and v2 snooping, IP Source Guard features.
Justificaiton : This are basic features for layer 2 switch and help for better traffic management and security
As per Draft RFP
296 Page 79 Item No. 21: - SFP -1G-LR
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, "SFP -1G-LR" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
297 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
298 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
299 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
300 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, " GLC-EX-SMD" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
301 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible with SFP MSA Request to change as below
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible
Type Gigabit Ethernet, Single Mode Fiber
Transceiver Compatible
302 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
303 Page 79 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
304 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
305 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
306 Page 80 Item No. 23: - SFP -10G-
LR for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
307 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
308 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
309 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
310 Page 80 Item No. 24: - SFP -10G-
ER for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
311 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
312 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
313 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
314 85 Item no. 26 EN/IEC Standard Ratings :EN/IEC 60068-2-27,ESD EN/IEC 61000-4-2, EN/IEC 61000-4-3, EN/IEC 61000-4-4, EN/IEC
61000-4-6, EN/IEC 61000-4-8, EN/IEC 60068-2-6,RoHS
and EMC as FCC Part 15, Class A
Request to change "EN/IEC 60068-2-27" to "EN/IEC 60068-2-27/IEC 60255-21-2/IEC 60255-21-1
Justification :
EN/IEC 60068-2-27 is intended for equipment or products that could be subjected to infrequent or repetitive shocks
during storage, use or transportation. Equivalent to this we have IEC 60255-21-2 (mechanical shock) & IEC 60255-21-1
(vibration) which is equivalent to the mention standard.
EN/IEC 60068-2-27/IEC 60255-21-2/IEC 60255-21-
1,ESD EN/IEC 61000-4-2, EN/IEC
61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6,
EN/IEC 61000-4-8, EN/IEC 60068-2-6,RoHS and EMC
as FCC Part 15, Class A
315 85 Item no. 26 8 Ethernet 10/100 ports and 2 dual-purpose
uplinks (each dual-purpose uplink port has 1
10/100/1000 Ethernet port and 1 SFP-based Gigabit Ethernet
port with single mode transceiver, 1 port active)
8 Ethernet 10/100/1000 ports and 4 Gigabit SFP uplinks
Justification :
Since 8 Ethernet ports are allready provided , we don't think there is need of any dual pupose uplinks. Since gigabit
ports are requested in uplinks , we would request to kindly make 8 ethernet ports gigabit and keep 4 gigabit SFP
uplinks . Earlier design is CISCO specific.
8 Ethernet 10/100/1000 ports and 2 SFP-based
Gigabit Ethernet uplink port with populated single
mode transceiver
316 85 Item no. 26 IEEE 802.3at on minimum 4 10/100 ports or
better POE Budget : min. 120w
IEEE 802.3at/ 802.3bt on minimum 4 10/100/1000 ports or
better POE Budget : min. 120w
Justification :
To support high end POE requirement we would recommend 802.3bt standard and gigabit ports as mentioned above.
As per Draft RFP
317 10 INVITATION FOR BIDS
(IFB)& NOTICE INVITING
BID (NIB)
Bid Security Request you to kindly avail exemption in EMD of Rs 216.00 lacs to the company registered under MSME/NSIC on
submission of requisite proof in the form of valid certification.
As per Draft RFP
318 13 PRE-QUALIFICATION /
ELIGIBILITY CRITERIA
clause 4.4
The bidder must have successfully completed One project of Supply and Installation of active Networking devices
(Router/Switches and other active network equipment) value not less than the amount of Rs. 30.00CR during the
period from 01/04/2015 to 31/03/2020. or
Two project of Supply and Installation of active Networking devices (Router/Switches and other active network
equipment) value not less than the amount of Rs. 40 CR during the period from 01/04/2015 to 31/03/2019.
Kindly amend the clause as -
"The bidder must have successfully completed One project of Supply and Installation of active Networking devices
(Router/Switches and other active network equipment) value not less than the amount of Rs. 22.00CR during the
period from 01/04/2015 to 31/03/2020. or
Two project of Supply and Installation of active Networking devices (Router/Switches and other active network
equipment) value not less than the amount of Rs. 20 CR during the period from 01/04/2015 to 31/03/2019."
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 20.00CR
during the period from 01/04/2015 to
31/03/2020.
or
three project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 40 CR during the
period from 01/04/2015 to
31/03/2020.
(Bidder to submit the documents as per
Annexure - 15)
319 13 PRE-QUALIFICATION /
ELIGIBILITY CRITERIA
clause 4.2
Financial: Turnover
Annual Average Turnover of the bidder from IT/ITeS/Networking(Active/Passive Network Component/Data Center
Equipments) during the last three financial years, i.e., 2016-2017
to 2018-19 (as per the last published audited balance sheets), should be at least Rs. 250 crores)
Request you to kindly reduce the average annual turnover of the bidder to atleast 200 crores. As per Draft RFP
320 21 Rate Contract for
Network Equipments
The SFP (Small Form-factor pluggable) required as per Annexure - 1 should be compatible with existing network
switches and routers:
We request to kindly ask for the original oem product to avoid any operability issues. As per Draft RFP
321 Additional Since this is very critical project it is requested that bidders who have minimum 200 on roll technical resources should
be allowed to bid.
As per Draft RFP
322 Additional It is requested to kindly consider mobilization advance of atleast 10% at the start of the project. As per Draft RFP
323 80 2.2 Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink
portspopulated with 1G single mode transceivers.
Request you to amend the Clause " Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate
2*1/10Gbps Fiber based SFP Uplink ports populated with 1G single mode transceivers. "
Justification:
It is indusrty Trend that Uplink Port Bandwidth should be minumum 60% of downlinking Port.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers324 81 1.11 The switch should have PoE/PoE+ output and should have minimum 120 watt power Request You to Amend the clause " The switch should have PoE/PoE+ output and should have minimum 240 watt
power "
Justification:
Minimum 15 watt PoE Budget should be available on all the Port which Basic Standard for PoE.
As per Draft RFP
325 83 7.4 TFTP and Secure FTP support Request you to amend the Clause "TFTP and Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification:
Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches OS size in in
Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly accept the
change
TFTP, FTP /Secure FTP/ Secure Copy support
326 83 8.9 TFTP, FTP or Secure FTP support Request you to amend the Clause "TFTP, FTP /Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification:
Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches OS size in in
Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly accept the
change
TFTP, FTP /Secure FTP/ Secure Copy support
327 86 1.1 Layer2 :
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
Request you to amend the Clause to OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019"
Justification:
1. L3 switch has also been asked from the complete gartner magic quadarant. 2. There are only 2 OEMS
qualified by the clause which restricts the participation of the other leading OEMs for this prestigious project.
As per Draft RFP
328 86 1.2 Layer2 :
16 RJ-45 autosensing 10/100/1000 ports with 2 open SFP slots populated with 1G single mode transceivers.
Request you to amend the Clause " Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate
2*1/10Gbps Fiber based SFP Uplink portspopulated with 1G single mode transceivers. "
Justification:
It is indusrty Trend that Uplink Port Bandwidth should be minumum 60% of downlinking Port.
As per Draft RFP
329 88 5.4 Layer2 :
TFTP and Secure FTP support
Request you to amend the Clause "TFTP and Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification:
Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches OS size in in
Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly accept the
change
TFTP, FTP /Secure FTP/ Secure Copy support
330 Request you to please add the clause in L2 switches and L3 switches "switch should be common criteria certified for
NDPP/NDcPP (Network Device Protection Profile)
Justification:
This is a security certifications which state that the hardware and the software of the switches has undergone the
global guidelines of security. The Security Requirements for Network Devices Protection Profile (NDPP) defines the
baseline Security Functional Requirements (SFRs) and Security Assurance Requirements (SARs) for network
infrastructure devices in general which is a must. All the leading OEMs support this.
As per Draft RFP
331 Request you to divide this tender into 2 separate tenders as below:
a) MPLS, P2P & ILL connectivity
b) Network hardware & LAN Infraunder
Justification:
MPLS, P2P comes and ILL comes under service where as Network HW is one time purchase, so requesting you to
seperate out both the requirements
As per Draft RFP
332 Project Related Querry A. Rate Contract of MPLS, P2P and Internet Lease Line connectivity.
B. Rate Contract for Network Infrastructure
Requesting to seprate both the Rate Contract since its will be difficult for SI to manage both the part. Also if seprate
MPLS, P2P and Internet Lease Line connectivity RC tender get called commercilas will be more competitive. Where ISP
will get direct change in bid participation.
As per Draft RFP
333 14 Certifications The bidder must possess, at the time of
bidding, a valid ISO 9001 / ISO 20000 / ISO
27001/ CMMi Level V.
The bidder must possess, at the time of
bidding, a valid ISO 9001, ISO 20000,ISO
27001,CMMi Level V.
Justification:
Seems its typo error needs to be separed by commas. All Certifications having its own value & they are not equivalent
to each other.
As per Draft RFP
334 21 The SFP (Small Form-factor pluggable) required as per Annexure - 1 should be
compatible with below mentioned existing network switches and routers:
BOM having Only CISCO SFP details not having SFP details/line item for HP Aruba & Brocade. As per Draft RFP
335 24 Installation, Integration and Commissioning of the Local Area Network BOM not having line item for LAN Work eg. Per meter cost for Laying of cable/conduit, OFC laying, crimping, fixing of
I/O. Digging of Hard/Soft Soil, wall cutting & repairing if required etc. It is difficult for bidder to assume these cost
since each site having its own requirement and may vary.
As per Draft RFP
336 85 Item no. 26 EN/IEC Standard Ratings :EN/IEC 60068-2-27,ESD EN/IEC 61000-4-2, EN/IEC 61000-4-3, EN/IEC 61000-4-4, EN/IEC
61000-4-6, EN/IEC 61000-4-8, EN/IEC 60068-2-6,RoHS
and EMC as FCC Part 15, Class A
Request to change "EN/IEC 60068-2-27" to "EN/IEC 60068-2-27/IEC 60255-21-2/IEC 60255-21-1
Justification:
EN/IEC 60068-2-27 is intended for equipment or products that could be subjected to infrequent or repetitive shocks
during storage, use or transportation. Equivalent to this we have IEC 60255-21-2 (mechanical shock) & IEC 60255-21-1
(vibration) which is equivalent to the mention standard.
EN/IEC 60068-2-27/IEC 60255-21-2/IEC 60255-21-
1,ESD EN/IEC 61000-4-2, EN/IEC
61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6,
EN/IEC 61000-4-8, EN/IEC 60068-2-6,RoHS and EMC
as FCC Part 15, Class A
337 85 Item no. 26 8 Ethernet 10/100 ports and 2 dual-purpose
uplinks (each dual-purpose uplink port has 1
10/100/1000 Ethernet port and 1 SFP-based Gigabit Ethernet
port with single mode transceiver, 1 port active)
8 Ethernet 10/100/1000 ports and 4 Gigabit SFP uplinks
Justification:
Since 8 Ethernet ports are allready provided , we don't think there is need of any dual pupose uplinks. Since gigabit
ports are requested in uplinks , we would request to kindly make 8 ethernet ports gigabit and keep 4 gigabit SFP
uplinks . Earlier design is specific to one OEM Only.
8 Ethernet 10/100/1000 ports and 2 SFP-based
Gigabit Ethernet uplink port with populated single
mode transceiver
338 85 Item no. 26 IEEE 802.3at on minimum 4 10/100 ports or
better POE Budget : min. 120w
IEEE 802.3at/ 802.3bt on minimum 4 10/100/1000 ports or
better POE Budget : min. 120w
Justification:
Minimum 15 watt PoE Budget should be available on all the Port which Basic Standard for PoE.
As per Draft RFP
339 80 2.2 Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink
portspopulated with 1G single mode transceivers.
Request you to amend the Clause " Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate
2*1/10Gbps Fiber based SFP Uplink ports populated with 1G single mode transceivers. "
Justification:
It is indusrty Trend that Uplink Port Bandwidth should be minumum 60% of downlinking Port.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers340 81 1.11 The switch should have PoE/PoE+ output and should have minimum 120 watt power Request You to Amend the clause " The switch should have PoE/PoE+ output and should have minimum 240 watt
power "
Justification:
Minimum 15 watt PoE Budget should be available on all the Port which Basic Standard for PoE.
As per Draft RFP
341 83 7.4 TFTP and Secure FTP support Request you to amend the Clause "TFTP and Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification:
Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches OS size in in
Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly accept the
change
TFTP, FTP /Secure FTP/ Secure Copy support
342 83 8.9 TFTP, FTP or Secure FTP support Request you to amend the Clause "TFTP, FTP /Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification:
Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches OS size in in
Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly accept the
change
TFTP, FTP /Secure FTP/ Secure Copy support
343 86 1.1 OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
Request you to amend the Clause to OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019"
Justification:
1. L3 switch has also been asked from the complete gartner magic quadarant. 2. There are only 2 OEMS
qualified by the clause which restricts the participation of the other leading OEMs for this prestigious project.
As per Draft RFP
344 86 1.2 16 RJ-45 autosensing 10/100/1000 ports with 2 open SFP slots populated with 1G single mode transceivers. Request you to amend the Clause " Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate
2*1/10Gbps Fiber based SFP Uplink portspopulated with 1G single mode transceivers. "
Justification:
It is indusrty Trend that Uplink Port Bandwidth should be minumum 60% of downlinking Port.
As per Draft RFP
345 88 5.4 TFTP and Secure FTP support Request you to amend the Clause "TFTP and Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification:
Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches OS size in in
Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly accept the
change
TFTP, FTP /Secure FTP/ Secure Copy support
346 General Querry Request you to please add the clause in L2 switches and L3 switches "switch should be common criteria certified for
NDPP/NDcPP (Network Device Protection Profile)
Justification:
This is a security certifications which state that the hardware and the software of the switches has undergone the
global guidelines of security. The Security Requirements for Network Devices Protection Profile (NDPP) defines the
baseline Security Functional Requirements (SFRs) and Security Assurance Requirements (SARs) for network
infrastructure devices in general which is a must. All the leading OEMs support this.
As per Draft RFP
347 PRE-
QUALIFICA
TION /
ELIGIBILITY
CRITERIA
13 A. The bidder must have successfully completed One project of Supply and Installation of active Networking devices
(Router/Switches and other active network equipment) value not less than the amount of Rs. 30.00 CR during the
period from 01/04/2015 to 31/03/2020
OR
two project of Supply and Installation of active Networking devices (Router/Switches and other active network
equipment) value not less than the amount of Rs. 40 CR during the period from 01/04/2015 to
31/03/2019. (Bidder to submit the documents as per
Annexure - 15)
Request RISL to consider that bidder have successfully completed one work order (which includes combining MPLS &
CPE) with value of INR 30 cr (incl. taxes) during last 5 years till 30th April 2020.
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 20.00CR
during the period from 01/04/2015 to
31/03/2020.
or
three project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 40 CR during the
period from 01/04/2015 to
31/03/2020.
(Bidder to submit the documents as per
Annexure - 15)
348 PRE-
QUALIFICA
TION /
ELIGIBILITY
CRITERIA
13 A. The bidder must have successfully completed One project of Supply and Installation of active Networking devices
(Router/Switches and other active network equipment) value not less than the amount of Rs. 30.00 CR during the
period from 01/04/2015 to 31/03/2020
OR
two project of Supply and Installation of active Networking devices (Router/Switches and other active network
equipment) value not less than the amount of Rs. 40 CR during the period from 01/04/2015 to
31/03/2019. (Bidder to submit the documents as per
Annexure - 15)
Request RISL to remove the Hardware Eligibility criteria, as this clause is for System Integrator & not for Telecom
services.
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 20.00CR
during the period from 01/04/2015 to
31/03/2020.
or
three project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 40 CR during the
period from 01/04/2015 to
31/03/2020.
(Bidder to submit the documents as per
Annexure - 15)
349 Pre-
Implement
ation
17 The work order to bidder/SP shall be placed for providing connectivity as per provisions of the RFP.
If the bidder fails to provide the connectivity after submitting feasibility, a penalty, as per the provisions contained in
the RFP, shall be imposed on per site basis.
Request RISL department to share us the complete site address details with pin code, lat long for all the sites with
breakup of required bandwidth against each site
As per Draft RFP
350 Implement
ation
17 Bidder/SP shall establish an end-to-end secure dedicated MPLS connectivity (Wired/ Wireless)/Point to Point (P2P)
with requisite bandwidth without any
compression from respective office to SHQ/DHQ/BHQ (As per directions of RISL).The links offered should be through
un-contention media i.e. bandwidth
should be uncompressed and not shared
Request RISL to allow L2 VPN against Point to Point link. Technical performance of L2 VPN solution will be same as of
Point to Point link.
As per Draft RFP
351 Implement
ation
17 The last mile connectivity at SHQ shall be provided only on fiber and the last mile connectivity end-office location
may be provided either on Wired / Wireless media. No charges shall be paid for aggregated bandwidth at SHQ
Request RISL to share us the complete site address details of SHQ with required bandwidth. As per Draft RFP
352 Implement
ation
17 The last mile connectivity at SHQ shall be provided only on fiber and the last mile connectivity end-office location
may be provided either on Wired / Wireless media. No charges shall be paid for aggregated bandwidth at SHQ
Request RISL to share us the complete site address details of end office/ Government office locations with breakup of
required bandwidth against each site.
As per Draft RFP
353 Implement
ation
17 The Equipment to be installed by the Bidder/SP shall extend an electrical Ethernet interface to the end CPE
equipment (Router/Layer3 Switch) installed at each
location. The required Router/Switch, UPS, Rack and earthing shall be provided by the RISL.
As per RFP, RISL has also mentioned that bidder to provide the UPS , earthing & rack. However this clause mentions
that it will be provided by RISL.
Request RISL to check and confirm the same.
As per Draft RFP
354 Implement
ation
18 During installation/ uninstall of any equipment, BIDDER/SP shall not cause any damage to government buildings/
premises/ property. However, if any damage
occurs, the BIDDER/SP shall restore it to the original state at their own cost upto the satisfaction of the GoR.
Trenches, path/road-cutting etc. should be back-filled
and restored to the original condition immediately after laying of the conduit/cable at no extra cost to the purchaser
Request RISL to take care of extension of link in case of any false ceiling, as Bidder will not be able to lay the cable.
Also request RISL to take care of extension of link from Telco Demark to router rack at all the sites.
As per Draft RFP
355 Implement
ation
18 During installation/ uninstall of any equipment, BIDDER/SP shall not cause any damage to government buildings/
premises/ property. However, if any damage
occurs, the BIDDER/SP shall restore it to the original state at their own cost upto the satisfaction of the GoR.
Trenches, path/road-cutting etc. should be back-filled
and restored to the original condition immediately after laying of the conduit/cable at no extra cost to the purchaser
Request RISL to provide the In building permission for laying the fiber cable at SHQ location. Respective TSP will back-
filled & restore to original condition.
As per Draft RFP
356 Implement
ation
18 OFC/ RF Equipment and End office equipment for OFC/Wireless connectivity (like Mux, Tower, Radio equipment,
CPE, Optical to electrical convertor etc.) are to be supplied based on mode of connectivity proposed by SP/Bidder
without additional cost/rent to purchaser. These equipment’s shall be recovered by the SP/ bidder at the end of
project period.Any other activity to keep the solution/ set-up functional to its full capacity shall be the responsibility
of the bidder/SP
Request RISL to provide the site readiness requirement as below:
Online UPS Power of 220 volts to 230 Volts, E-N Voltage < 2 volts, Air Conditioning inside server room/computer room,
permission on roof top for installation of RF Pole or tower, Permission inside building for laying OFC cable, 24* 7
permission inside server room for maintenance of link etc
As per Draft RFP
357 Implement
ation
18 The termination of P2P connectivity shall be on fiber/Ethernet (as per requirement of RISL)at both end with
accessories to terminate the same at respective locations.
Request RISL to allow L2 VPN against Point to Point link. Technical performance of L2 VPN solution will be same as of
Point to Point link.
As per Draft RFP
358 Testing &
commissio
ning
19 UAT request for a particular PO can be raised by the SP/Bidder in parts on monthly basis Request RISL to consider the UAT/ Acceptance testing to be site wise. As per Draft RFP
359 Testing &
commissio
ning
19 ILL Link: Load Test: A file transfer test between respective end offices using FTP may be done to verify the effective
bandwidth/ throughput, if felt necessary
by RISL
Load test activity may not be applicable for Internet Leased line links As per Draft RFP
360 Testing &
commissio
ning
19 ILL - Round Trip Delay between ISP Gateway Router and ISP upstream peering point. --> <= 50 msec Request RISL to consider the Latency as PE to CPE Ping response. As per Draft RFP
361 Testing &
commissio
ning
19 ILL link. Packet Drop < = 0.05% Request RISL to consider the Packet drop of <= 1% As per Draft RFP
362 Testing &
commissio
ning
20 As the Links will be declared GO-LIVE in phased manner, there shall be time-gap between
initially commissioned Links/Sites and last commissioned links/ sites. The period of O&M of
links/sites commissioned before last phase may get completed before that of the last
commissioned links/sites. A letter of Go-live of all the circuits/links shall be issued by RISL.The
payment shall be effective from the date of commissioning & Go-Live of each lot
Request RISL to consider the UAT/ Acceptance testing to be site wise also the payment to be site wise. As per Draft RFP
363 Post-
implement
ation:
Network
Managem
ent
Services
and FMS
21 Some Links may be required to be shifted to new location during O&M period. The Bidder/SP shall be required to
uninstall, pack, shift, unpack, re-install and configure at new site location during contract period without any
additional cost to the Purchaser,
RISL will provide the required time to lay OFC to concern bidder/SP in such shifting cases.Such links will not be more
than 1% of order given during contract period
Request RISL to consider the shifting as one time charges & this shifting of link will be subject to feasibility. As per Draft RFP
364 Post-
implement
ation:
Network
Managem
ent
Services
and FMS
21 RISL may request for discontinuation of a particular link before expiry of Project period
by giving One month notice. The payment to the SP/Bidder for such discontinued link(s)
shall be made on pro-rata basis upto the notified termination date or actual date of
removal of the connectivity whichever is earlier.
Request RISL to delete this clause, as early termination will attract some penalty charges for early exit. Hence request
RISL to keep this link till contract period.
As per Draft RFP
365 Rate
Contract
for
Network
Infrastruct
ure
21 Rate Contract for Network Infrastructure
a. Rate Contract for Network Equipments
Request RISL to remove the Hardware from this RFP & to have separate RFP. As per Draft RFP
366 Rate
Contract
for
Network
Infrastruct
ure
23 Rate Contract for network LAN work Request RISL to remove the Hardware & Network LAN from this RFP & to have separate RFP. As per Draft RFP
367 Project
Milestones
,
Deliverabl
es&
Timelines
28 Bandwidth Upgradation -- T+15 days Request RISL to consider the time lines for up gradation of link to be 3 to 4 weeks from date of PO As per Draft RFP
368 Project
Milestones
,
Deliverabl
es&
Timelines
29 O&M Phase for Bandwidth recurring charges: Bi-annually at the approved rates over a
period of three years from the “Date of
Commissioning & Go- Live” for each lot.
Request RISL to consider the Bandwidth charges to to be paid Quarterly in arrears & acceptance & payment to be site
wise.
The payment for each lot shall be released Quarterly
from commissioning & Go-Live of the lot/link
369 Lot Size
and
Commissio
ning
timelines
29 Feasibility time frame:
Upto 50 Links -- 1 week
Upto 50 Links with end equipments -- 1 week
More than 50 Links -- 2 weeks
Request RISL to provide more time for doing the feasibility study.
Upto 50 Links -- 2 weeks
Upto 50 Links with end equipments -- 2 weeks
More than 50 Links -- 3 weeks
As per Draft RFP
370 Lot Size
and
Commissio
ning
timelines
29 Link Commissioning timeline
(Excluding UAT period)
Upto 50 Links -- 4 weeks
Upto 50 Links with end equipments -- 6 weeks
More than 50 Links -- 8 weeks.
Request RISL to provide more time for implementation of links.
Upto 50 Links -- 8 weeks from date of PO
Upto 50 Links with end equipments -- 10 weeks from date of PO
More than 50 Links but < 100 links -- 16 weeks from date of PO
More than 100 links till 500 links --- 24 weeks from date of PO
As per Draft RFP
371 For
Network
Equipment
29 Supply, Installation and Maintenance of equipment as
per the BoM (Annexure-1) --- T+ 60 days
Request RISL to share us the Qty of PO for required number of Networking hardware? As per Draft RFP
372 For
Network
Equipment
29 Supply, Installation and Maintenance of equipment as
per the BoM (Annexure-1). Payment terms -- 90% of total work order value and remaining 10% in equated
installment yearly i.e 2% at the end of each year
OR this remaining 10% may be released against Bank Guarantee of equal amount
Request RISL to consider the Payment terms as below:
90% on delivery of hardware
10 % post installation of CPE router at respective site.
This payment to be done for individual CPE/ Hardware.
As per Draft RFP
373 Terminatio
n for
Convenien
ce
59 Termination for Convenience: RISL, by a written notice of at least 30 days sent to the supplier/ selected bidder, may
terminate the Contract, in whole or in part, at any time for its convenience. The Notice of
termination shall specify that termination is for the Purchaser’s convenience, the extent to
which performance of the supplier/ selected bidder under the Contract is terminated, and
the date upon which such termination becomes effective.
ii. Depending on merits of the case the supplier/ selected bidder may be appropriately
compensated on mutually agreed terms for the loss incurred by the contract if any due to
such termination.
Request RISL to delete this clause, as Telecom service provider will be investing huge CAPEX. As per Draft RFP
374 Penalty for
not
meeting
Latency
66 Penalty for non-achievement of Latency for P2P connectivity shall be deducted as
below:
Request RISL to delete the penalty for not meeting Latency. As per Draft RFP
375 Penalty for
not
meeting
Latency
66 Penalty for non-commissioning of links:
If a SP/Bidder fails to commission the link after declaring the site feasibility within the
stipulated time period provided in the work-order issued by RISL, a penalty of 100% of
the link rental of a year of the link, shall be deducted from the payable amount to
SP/bidder for commissioned links.Such links shall be offered to other SP/Bidder for
commissioning.
Request RISL to delete this penalty, as bidder has not received the complete site address details. As per Draft RFP
376 Annexure -
1
72 ANNEXURE-1: BILL OF MATERIAL (BOM)
PART – A: MPLS,P2P and ILL Connectivity (Rate Contract):
Request RISL to share us the complete site address details with pin code, lat long & bandwidth requirement against
each site for MPLS, ILL & P2P link.
As per Draft RFP
377 Additional
Query
Exclusion from LD Penalty Request RISL to exclude the LD Penalty on below scenario.
1. Delay in Sharing the complete site address & site contact details for all sites.
2. Delay in getting the Buidling permission for laying the fibre cable
3. Site is not ready (i.e. Site readiness is not available as per checklist shared).
4. CPE is not available for termination of link.
5. Permission not available on rooftop for installation of link.
6. Force Majeure
7. Political Instability
8. Flood/Riots
9. Pandemic situation
As per Draft RFP
378 Additional
Query
Exclusion from SLA up time Penalty Request RISL to exclude the Penalty for not meeting the SLA up time in below scenario.
1. Power failure.
2. Force Majeure
3. Trouble ticket not booked with ISP.
4. Permission not available for maintenance & restoration of link.
5. Earthing issue or Online UPS relatedd issue.
6. Political Instability
7. Flood/Riots
8. Epidemic or Pandemic situation
9. Theft of CPE
10. Damage of CPE due to power fluctuation
As per Draft RFP
379 Additional
Query
Acceptance of the link to be site wise Request RISL to consider in providing the Acceptance of link to be site wise after installing the link at DC & DR. As per Draft RFP
380 Additional
Query
UAT Criteria Request RISL to consider the UAT Criteria as WAN to WAN Ping test from DC to Spoke site. As per Draft RFP
381 Additional
Query
Site Readiness requirement at all the sites Request RISL to have the site readiness requirement at each site as below:
Online UPS Power of 220 volts to 230 volts, E-N Voltage < 2 volts, Air Conditioning inside server room, Permission
inside Data center for installation of link, Permission on roof top for installation of RF Pole/Tower, 24*7 permission
inside server room fro Maintenance of link, Rack space of 9U in existing rack at all sites. etc
As per Draft RFP
382 Extension of Submission Due to ongoing COVID 19 situation we are unable to conduct the feasibility study & site survey.
We request you to extend the bid submission till 20th July 20.
As per Draft RFP
383 Page 13 Eligibility Criteria
Financial: Turnover
Annual Average Turnover of the bidder from IT/ITeS/Networking(Active/Passive Network Component/Data Center
Equipments) during the last three financial years, i.e., 2016-2017 to 2018-19 (as per the last published audited
balance sheets), should be at least Rs. 250 crores
Annual Average Turnover of the bidder from during the last three financial years, i.e., 2016-2017 to 2018-19 (as per
the last published audited balance sheets), should be at least Rs. 75 crores
As per Draft RFP
384 Page 13 Technical Capability
Point A
A. The bidder must have successfully completed One project of Supply and Installation of active Networking devices
(Router/Switches and other active network equipment) value not less than the amount of Rs. 30.00CR during the
period from 01/04/2015 to 31/03/2020 OR
B. The bidder must have successfully completed two project of Supply and Installation of active Networking devices
(Router/Switches and other active network equipment) value not less than the amount of Rs. 40.00CR during the
period from 01/04/2015 to 31/03/2020
A. The bidder must have successfully completed One project of Supply and Installation of active Networking devices
(Router/Switches/Firewall/Server and other active network equipment) value not less than the amount of Rs. 15 .00CR
during the period from 01/04/2015 to 31/03/2020 OR
B. The bidder must have successfully completed Two project of Supply and Installation of active Networking devices
(Router/Switches/Firewall/Server and other active network equipment) value not less than the amount of Rs. 10.00CR
during the period from 01/04/2015 to 31/03/2020
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 20.00CR
during the period from 01/04/2015 to
31/03/2020.
or
three project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 40 CR during the
period from 01/04/2015 to
31/03/2020.
(Bidder to submit the documents as per
Annexure - 15)
385 Page 29 Payment Term: For
Network Equipment
90% of total Order value & ramining 10% in equated installment yearly i.e. 2% at the end of each year OR this
remaining 10% may be released against Bank Guarantee of equal amount.
90% of total Order value against delivery & ramining 10% in equated installment yearly i.e. 2% at the end of each year
OR this remaining 10% may be released against Bank Guarantee of equal amount.
As per Draft RFP
386 Page 81 Item No. 25: - L3 Switch
1.1
1.1OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change this clause to
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
387 Page 81 Item No. 25: - L3 Switch
2.2
2.2 Should have Minimum 16 RJ-45
autosensing 10/100/1000 ports
and separate 2*1Gbps Fiber based
SFP Uplink portspopulated with 1G
single mode transceivers.
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 4*1Gbps Fiber based SFP Uplink
portspopulated with 1G single mode transceivers.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers
388 Page 82 Item No. 25: - L3 Switch
8.15
3.4The Switch should support stacking of switches The switch should support dedicated stacking port separate from uplink ports with 48 Gbps of stacking bandwidth.
Justificaton : with 48Gbps stacking bandwidth, can support higher data transfer between stacked switches of 2 or
more.
The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements.
389 Page 82 Item No. 25: - L3 Switch
5.2
5.2The switch should support minimum 256 static IP routing Request to change this clause to
"The switch should support minimum 256 static IP routing / 1000 IPv4 routes"
Justification: For layer 3 switch, having routing protocol running will have better results in terms of redundancy and
resiliency. Request to allow 1000 Routes as alternative.
The switch should support minimum 256 static IP
routing/1000 IPv4 routes
390 Page 84 Item No. 25: - L3 Switch
8.15
8.15 The switch should support IPv6 Guard, Source-Guard features Request to change this clause to
Switch should support IPv6 Source Guard,IPv6 DHCP Guard, IPv6 RA Guard, IPv6 Neighbor Discovery Inspection,
Neighbor Discovery (ND) protocol snooping, IPv6 Prefix Guard, IPv6 Destination Guard
Justification: Above are bare minimum IPv6 feature required for basic IPv6 security.
As per Draft RFP
391 Page 81 Item No. 25: - L3 Switch New Clause Request to add clause
Switch should support External/Internal Redundant Power Supply.
Justification : Being Layer 3 switch will be installed at important locations, This switch should have provision to
support redundant power supply to continue operations.
As per Draft RFP
392 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Must have SDCard/memory card for easier switch Replacement , to ensure that field switch does not require
reconfiguration and storage cards can be swapped.
As per Draft RFP
393 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Switch must support IPv6 management and troublshooting features like IPv6 Ping, IPv6 traceroute, IPv6 Telnet, IPv6
SSH, HTTP over IPv6, SNMP over IPv6 and Dual Stack
Justification : These are basic IPv6 features needed for both layer 2 or Layer 3 switch and must for Network basic
operations/troubleshooting.
As per Draft RFP
394 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Shall support IEEE 802.3az Energy- efficient Ethernet (EEE) to reduce power consumption
Justificaiton : This feature helps in reducing power consumption
As per Draft RFP
395 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Switch should support UDLD, MLD v1 and v2 snooping, IP Source Guard features.
Justificaiton : This are basic features for layer 2 switch and help for better traffic management and security
As per Draft RFP
396 Page 79 Item No. 21: - SFP -1G-LR
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, "SFP -1G-LR" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
397 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
398 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
399 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
400 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, " GLC-EX-SMD" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
401 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible with SFP MSA Request to change as below
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible
Type Gigabit Ethernet, Single Mode Fiber
Transceiver Compatible
402 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
403 Page 79 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
404 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
405 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
406 Page 80 Item No. 23: - SFP -10G-
LR for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
407 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
408 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
409 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
410 Page 80 Item No. 24: - SFP -10G-
ER for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
411 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
412 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
413 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
414 Page 29 Timelines For Network
Equipment
T+60 Days Due to COVID19, the deliveries of almost all OEMs have been hampered. Hence request you to make it as T+120days As per Draft RFP
415 Page 81 Item No. 25: - L3 Switch
1.1
1.1OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change this clause to
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
416 Page 81 Item No. 25: - L3 Switch
2.2
2.2 Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink
portspopulated with 1G single mode transceivers.
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 4*1Gbps Fiber based SFP
Uplink portspopulated with 1G single mode transceivers.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers417 Page 82 Item No. 25: - L3 Switch
8.15
3.4The Switch should support stacking of switches The switch should support dedicated stacking port separate from uplink ports with 48 Gbps of stacking bandwidth.
Justificaton : with 48Gbps stacking bandwidth, can support higher data transfer between stacked switches of 2 or
more.
The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements.
418 Page 82 Item No. 25: - L3 Switch
5.2
5.2The switch should support minimum 256 static IP routing Request to change this clause to
"The switch should support minimum 256 static IP routing / 1000 IPv4 routes"
Justification: For layer 3 switch, having routing protocol running will have better results in terms of
redundancy and resiliency. Request to allow 1000 Routes as alternative.
The switch should support minimum 256 static IP
routing/1000 IPv4 routes
419 Page 84 Item No. 25: - L3 Switch
8.15
8.15 The switch should support IPv6 Guard, Source-Guard features Request to change this clause to
Switch should support IPv6 Source Guard,IPv6 DHCP Guard, IPv6 RA Guard, IPv6 Neighbor Discovery Inspection,
Neighbor Discovery (ND) protocol snooping, IPv6 Prefix Guard, IPv6 Destination Guard
Justification: Above are bare minimum IPv6 feature required for basic IPv6 security.
As per Draft RFP
420 Page 81 Item No. 25: - L3 Switch New Clause Request to add clause
Switch should support External/Internal Redundant Power Supply.
Justification : Being Layer 3 switch will be installed at important locations, This switch should have provision to
support redundant power supply to continue operations.
As per Draft RFP
421 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Must have SDCard/memory card for easier switch Replacement , to ensure that field switch does not require
reconfiguration and storage cards can be swapped.
As per Draft RFP
422 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Switch must support IPv6 management and troublshooting features like IPv6 Ping, IPv6 traceroute, IPv6 Telnet, IPv6
SSH, HTTP over IPv6, SNMP over IPv6 and Dual Stack
Justification : These are basic IPv6 features needed for both layer 2 or Layer 3 switch and must for Network basic
operations/troubleshooting.
As per Draft RFP
423 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Shall support IEEE 802.3az Energy- efficient Ethernet (EEE) to reduce power consumption
Justificaiton : This feature helps in reducing power consumption
As per Draft RFP
424 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Switch should support UDLD, MLD v1 and v2 snooping, IP Source Guard features.
Justificaiton : This are basic features for layer 2 switch and help for better traffic management and security
As per Draft RFP
425 Page 79 Item No. 21: - SFP -1G-LR
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, "SFP -1G-LR" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
426 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
427 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
428 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
429 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, " GLC-EX-SMD" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
430 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible with SFP MSA Request to change as below
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible
Type Gigabit Ethernet, Single Mode Fiber
Transceiver Compatible
431 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
432 Page 79 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
433 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
434 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
435 Page 80 Item No. 23: - SFP -10G-
LR for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
436 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
437 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
438 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
439 Page 80 Item No. 24: - SFP -10G-
ER for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
440 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
441 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
442 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
443 Page 77 ANNEXURE-2:
TECHNICAL
SPECIFICATIONS
Item No. 20: - Universal SFP Request you to provide more details for Devices where these transceivers will be used As per Draft RFP
444 13 As per Draft RFP
445 14 4. PRE-QUALIFICATION /
ELIGIBILITY CRITERIA
4. Techinical Capability
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 30.00CR
during the period from 01/04/2015 to
31/03/2020.
or
two project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 40 CR during the period from 01/04/2015 to
31/03/2019.
(Bidder to submit the documents as per
Annexure - 15)
Request RISL to revise the clause as below :
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 20.00CR
during the period from 01/04/2015 to
31/03/2020.
or
three project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 40 CR during the period from 01/04/2015 to
31/03/2020.
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 20.00CR
during the period from 01/04/2015 to
31/03/2020.
or
three project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 40 CR during the
period from 01/04/2015 to
31/03/2020.
(Bidder to submit the documents as per
Annexure - 15)
446 15 4. PRE-QUALIFICATION /
ELIGIBILITY CRITERIA
3. Financial Net worth : The net worth of the bidder as on 31-03-2019 should be ‘Positive’. Request RISL to kindly remove this clause. Omitted
447 15 4. PRE-QUALIFICATION /
ELIGIBILITY CRITERIA
B.The bidder must have agreement with
minimum Three NBSP (Network Bandwidth
Service Provider) within 15 days of LOI. At
the time of Tripartite agreement,The NBSP
should have:
a) Avalid UASL/USL/CMTS/2G/3G And NLD
License for Rajasthan Telecom Circle duly
issued by DoT.
b) Network management center with DR
facility, at different locations in India.
Request RISL to please confirm , how many Tripartite agreement need to be done by the bidder with NBSP , as its
contradicting with Clause no 4. PRE-QUALIFICATION / ELIGIBILITY CRITERIA page no 14 , at one place its ask 3 and at
one place 2 .
Request RISL to allow bidder to provide the connectivity by their own without the tripartite agreement , as Telecom
provider might not agree to take payment from RISL
Selected Bidder/SI shall be required to sign a
tripartite agreement with RISL and with minimum
three NBSP
448 21 4 ( c ) RISL may request for discontinuation of a particular link before expiry of Project period
by giving One month notice. The payment to the SP/Bidder for such discontinued link(s)
shall be made on pro-rata basis upto the notified termination date or actual date of
removal of the connectivity whichever is earlier.
Customer should pay for the remaining period as per the contract or relevant SOW as Early termination charges As per Draft RFP
449 28 5.2 Project Milestones,
Deliverables& Timelines
a. For MPLS and P2P & ILL Connectivity On page 28, under a) For MPLS and P2P & ILL Connectivity - It is written O&M phase as 2 years whereas in BOQ it is 2
years. Request customer to please clarify.
As per Draft RFP
450 28 5.2 Project Milestones,
Deliverables& Timelines
a. For MPLS and P2P & ILL Connectivity On page 28, under a) For MPLS and P2P & ILL Connectivity - Request to please amend the payment terms as -
Quarterly in arrears from te date of commissioning & Go live of each lot
The payment for each lot shall be released Quarterly
from commissioning & Go-Live of the lot/link
451 28 5.2 Project Milestones,
Deliverables& Timelines
The payment process for the work order shall be start after issuing of Go-live date of last lot.
However, payable amount of links shall be effective from Go-live date of Links.
Request customer to please amend the clause as: The payment process for the work order shall be start after issuing of
Go-live date of each lot.
And payable amount of links shall be effective from Go-live date of Links.
As per Draft RFP
452 29 b. For Network
Equipment
Query not clear
453 30 Note d) D) Due payments shall be made promptly by the purchaser, generally within sixty (60) days after
submission of an invoice or request for payment by the supplier/ selected bidder.
Request customer to please amend the clause as Due payments shall be made promptly by the purchaser, generally
within Thirty (30) days after
submission of an invoice or request for payment by the supplier/ selected bidder.
As per Draft RFP
454 55 28. Liquidated Damages
(LD)
a) In case of extension in the delivery period with liquidated damages the recovery shall be
made on the basis of following percentages of value of which the bidder has failed to
supply/commence services:-
b) Fraction of a day in reckoning period of delay in supplies shall be eliminated if it is less than
half a day.
c) The maximum amount of liquidated damages shall be 10% of the contract value.
Request customer to please amend the ppenal caluse: a) In case of extension in the delivery period with liquidated
damages the recovery shall be
made on the basis of following percentages of value of which the bidder has failed to
supply/commence services:-
b) Fraction of a day in reckoning period of delay in supplies shall be eliminated if it is less than
half a day.
c) The maximum amount of liquidated damages shall be 5% of the contract value.
As per Draft RFP
455 59 c) Termination for
Convenience
c) Termination for Convenience In case of “Termination by Convenience” Customer should pay for the remaining period as per the contract or relevant
PO/WO as Early termination charges
As per Draft RFP
456 65 6. Penalty for non-
achievement of Service
Level Requirements:
As per Draft RFP
457 67 7. Penalty for non-
commissioning of links:
If a SP/Bidder fails to commission the link after declaring the site feasibility within the
stipulated time period provided in the work-order issued by RISL, a penalty of 100% of
the link rental of a year of the link, shall be deducted from the payable amount to
SP/bidder for commissioned links.Such links shall be offered to other SP/Bidder for
commissioning.
Note: The penalty shall be calculated separately for Prime Hours and Non-Prime
Hours and for each parameter defined above, on quarterly basis. Penalty imposed
shall be sum of both (i.e. Prime Hours and Non-Prime Hours). However, for any given
link, penalty shall not exceed 100% of Half yearly equated instalments (i.e. rental) for
that link.
Request customer to please relax the pemal terms:
And also due consideration to be given, if the bidder is not able to commission the link due to unaviodable factors.
If a SP/Bidder fails to commission the link after declaring the site feasibility within the
stipulated time period provided in the work-order issued by RISL, a penalty of 5% of
the link rental of a quarter of the link, shall be deducted from the payable amount to
SP/bidder for commissioned links.Such links shall be offered to other SP/Bidder for
commissioning.
Note: The penalty shall be calculated separately for Prime Hours and Non-Prime
Hours and for each parameter defined above, on quarterly basis. Penalty imposed
shall be sum of both (i.e. Prime Hours and Non-Prime Hours). However, for any given
link, penalty shall not exceed 10% of Half yearly equated instalments (i.e. rental) for
that link.
As per Draft RFP
458 16 5.1. Detailsof Scope of
Work (SoW) A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity
required throughput should be ensured by the SP. we assume that this is as per IEEE standards As per Draft RFP
459 16 5.1. Detailsof Scope of
Work (SoW) A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity
The bidder shall be required to extend FE
connectivity to RISL router using LAN cable.
Bidder assumes that at most of the locations bidder will only provide router & switches to terminate the WAN
connectivity which is a part of BOQ. If bidder is not providing any routers & switches for link delivery then it will be the
responsibility of the RISL/RISL's router partner to provide & connect the required cables.
As per Draft RFP
460 17 5.1. Detailsof Scope of
Work (SoW) A. Rate
Contract of MPLS, P2P
and Internet Lease Line
connectivity 1. Pre-
implementation
RISL shall provide the list of sites to be connected to bidder/SPs. Bidder/SPs shall perform Site-survey of all the
ordered locations for feasibility. The Bidder/SPs shall intimate feasible links within specified timelines. If no
intimation is provided by bidder/SPs within specified days, it shall be deemed that the site(s)are feasible to the
bidder/SP.
Request customer to please remove the,
If no intimation is provided by bidder/SPs within specified days, it shall be deemed that the site(s)are feasible to the
bidder/SP.
As per Draft RFP
461 17 1. Pre-implementation d) The requisite space & 5A AC power for installing the equipment at the designated
locations shall be provided by respective state government office/RISL.
Bidder assumes that power socket will be provided near to Rack and if any delay due to power socket same will be
excluded from the LD calculation.
As per Draft RFP
462 17 2. Implementation: f) Bidder/SP shall coordinate with the RajSWAN/RajNET Operator and nodal officer for detection of the circuit/link in
NMS.
Bidder assumes that if there is any delay in providing router and router configuration by the RISL will be exclude from
the LD calculation . And link delivery date will be consider for the commissioning.
As per Draft RFP
463 17 2. Implementation: p) OFC/ RF Equipment and End office equipment for OFC/Wireless connectivity (like Mux, Tower, Radio equipment,
CPE, Optical to electrical convertor etc.) are to be supplied based on mode of connectivity proposed by SP/Bidder
without additional cost/rent to purchaser. These equipment’s shall be recovered by the SP/ bidder at
the end of project period.Any other activity to keep the solution/ set-up functional to its full capacity shall be the
responsibility of the bidder/SP.
Request RISL to please remove (These equipment’s shall be recovered by the SP/ bidder at
the end of project period) as bidder is providing the services and hardware belong to bidder only
As per Draft RFP
464 18 2. Implementation: q) The termination of P2P connectivity shall be on fiber/Ethernet (as per requirement
of RISL)at both end with accessories to terminate the same at respective locations.
Request Customer to please change the clause as below
The termination of P2P connectivity shall be on fiber/RF with Ethernet hand-off(as per requirement
of RISL)at both end with accessories to terminate the same at respective locations.
As per Draft RFP
465 19 3. Testing &
Commissioning:
a) UAT request for a particular PO can be raised by the SP/Bidder in parts on monthly basis. We request RISL to please change twice in month from monthly basis. As per Draft RFP
466 19 3. Testing &
Commissioning:
b) After successful establishment of links at all the designated locations, BIDDER/SP shall
inform DoIT&C/RISL designated agency about the same and submit a request for
Acceptance Testing (AT) of each link by DoIT&C/RISL designated agency, at the end of
the month OR on completion of the work order.BIDDER/SP shall assist DoIT&C/RISL in
conducting Acceptance Testing.
We assume Bidder need to assist at central location only for the UAT . As per Draft RFP
467 19 3. Testing &
Commissioning:
c) RISL shall carry out the UAT of established links in the previous month subject to a lot size
of minimum 80% links i.e. Go-Live shall be given in a lot. Since there may be possibility of
some links failing in UAT, the bidder is advised to offer more number of links for UAT. No
more than three lots shall be accepted for UAT for each PO.
Request RISL to change the clause as below .
RISL shall carry out the UAT of established links in the previous month subject to a lot size
of minimum 30% links i.e. Go-Live shall be given in a lot. Since there may be possibility of
some links failing in UAT, the bidder is advised to offer more number of links for UAT.
As per Draft RFP
468 19 3. Testing &
Commissioning:
d) Bidder shall be required to acquire an acknowledgement letter of establishment of
connectivity from the end-office location.The established connectivity must be detected in
RISL NOC.
RISL should appoint a central SPOC for all operational challenges & he should be the authorized signatory in case
bidder is not having information about nodal officer or the nodal office is not available at the site during installation
As per Draft RFP
469 19 A. For MPLS Links i. Latency (Round-trip): The average round trip delay for 1000 diagnostic packets of 100 bytes each between
respective end offices should be less than 60 milliseconds.
Request RISL to please allow Latency till 80 millisecond. As per Draft RFP
470 19 A. For MPLS Links iii. Load Test: A file transfer test between respective end offices using FTP may be done to verify the effective
bandwidth/ throughput, if felt necessary by RISL
We assume that these test will be performed by the RISL/Agency assigned by the RISL , and no manpower is require at
delivery location from bidder
As per Draft RFP
471 19 B. For P2P Links i. Latency (Round-trip): The average round trip delay for 1000 diagnostic
packets of 1500 bytes each between respective end offices should be less
than 40 milliseconds.
Request RISL to please allow Latency till 60 millisecond. As per Draft RFP
472 19 B. For P2P Links iii. Load Test: A file transfer test between respective end offices using FTP
may be done to verify the effective bandwidth/ throughput, if felt necessary
by RISL.
We assume that these test will be performed by the RISL/Agency assigned by the RISL , and no manpower is require at
delivery location from bidder
As per Draft RFP
473 20 C. For ILL i. Latency (Round-trip): ISP’s Latency will be determined by round trip delay from ISP’s any edge router in INDIA &
terminating point with upstream service provider. It will be measured by standard 1000 packets of 64-byte ping.
Latency,
Packet drop will be under SLA as per the below mentioned table:
We assume that RISL require the latency between ISP edge router to global DNS server - please confirm and also share
how RISL will monitor this
As per Draft RFP
474 20 C. For ILL Packet drop Request RISL to please allow the 1 % packet drop As per Draft RFP
475 20 C. For ILL ii. Load Test: A file transfer test between respective end offices using FTP
may be done to verify the effective bandwidth/ throughput, if felt necessary
by RISL.
We assume that these test will be performed by the RISL/Agency assigned by the RISL , and no manpower is require at
delivery location from bidder
As per Draft RFP
476 20 3. Testing &
Commissioning:
g) On successful AT by DoIT&C/RISL of the link, the event shall be marked as the “Date of
Commissioning” of the lot
We request RISL to consider the link delivery date on which bidder has delivered the link and taken the
acknowledgement letter from Local person for the LD calculation as we can submit the request only one time in a
month .
As per Draft RFP
477 21 4. Post-implementation:
Network Management
Services and FMS
a) Since the tickets shall be generated using the existing HP EMS installed under RajNET,
the BIDDER/SP shall ensure with the respective operator that the tickets are closed on
restoration of fault. The BIDDER/SP’s support should coordinate for ticket management
and monitoring of Faulty/Down circuits. Any communication like phone call, email, fax
etc. shall be treated as logging of fault and duration shall be counted till the link is up
and operational.
We Assume that duration shall be counted from the time of intimation to bidder Helpdesk to restoration of the link ,
not the ticket closed in HP EMS
As per Draft RFP
478 21 4. Post-implementation:
Network Management
Services and FMS
b) Bidder/SP shall proactively monitor and maintain all the commissioned links for desired
uptime and performance as per agreed SLA.
Bidder Can only monitor proactively MPLS and Internet link not the P2P links , and also request RISL to please put the
NMS string for bidder in RISL provided router also
As per Draft RFP
479 21 Rate Contract for
Network Infrastructure
a. Rate Contract for Network Equipments The bidder has to do Earthing (as per order) strictly according to the
specifications.The Earthing shall be provided to power socket where PDU would have been connected. If there is no
power socket available at site, a 3 pin 15 Amp power socket shall be installed by bidder with no extra cost to
purchaser and earthing shall be terminated at the socket thereafter. The bidder has to repair/replace PDU in
warranty
duration.
Request RISL to please confirm whether PDU will be supplied by the bidder and also request to please share the
average fault rate of PDU in last 3 years
As per Draft RFP
480 22 Rate Contract for
Network Infrastructure
The SPOC provided by bidder shall be responsible for handling support tickets for the equipment mentioned in the
RFP and getting support issues rectified as per the
defined SLA. In case of faults in any of supplied End Office Equipment, tickets shall be raised to SPOC and SPOC shall
get the fault rectified or equipment replaced as required, by coordinating with respective OEM’s. RISL will arrange
the pickup of faulty devices at the nearest Block level of the location, OEM’s need to deliver devices to the nearest
Block level location for any replacement. However, bidder can arrange its own to meet SLA timelines, SPOC shall also
be responsible for the re-configuration of replaced devices.The devices supplied shall be compatible with existing
NMS system and shall be discoverable through NMS System. Bidder is responsible to do configuration in supplied
switches and will coordinate with team for discovery in
existing HP NMS
Request RISL to own the pick & drop till block level from the sites & exclude any delay due to this from SLA calculation. As per Draft RFP
481 21 Rate Contract for
Network Infrastructure
The SFP (Small Form-factor pluggable) required as per Annexure - 1 should be compatible with below mentioned
existing network switches and routers:
Request RISL to please provide the SFP requirement as per the router and switch ,so bidder can provide the SFP from
the same OEM
As per Draft RFP
482 22 Configuration and
reconfiguration of
equipment/network/serv
ices
The Successful bidder shall maintain a record of hardware and software configurations of all equipment including
the details of different policies implemented on the devices such as VLAN configurations, access control lists, routing
filters, clustering details etc. Successful bidder shall keep regular backups of soft copies of the configurations of each
of the devices mentioned
We assume to keep record of soft configuration RISL will provide the required Space in server/PC . As per Draft RFP
483 23 3. User Acceptance Test The bidder shall co-ordinate and carry any other required test as desired by purchaser for demonstrating the asked
functionality.
Request RISL to please specify the required test which need to be performed for Hardware As per Draft RFP
484 23 3. User Acceptance Test The RISL/GoR may engage third party auditor (TPA) at its own costs to carry out UAT. The bidder shall be required to
extend required cooperation including carrying at pit holes, Testing of Material/Links etc. for successful UAT by TPA.
Request RISL to please confirm whether bidder need to realign the engineer at site for the UAT or it will be done by
the TPA only , as its have cost impact for re visit
As per Draft RFP
485 23 b. Rate Contract for
network LAN work
Extend electrical cable & install electrical switches/sockets. Request RISL to please provide the specification of switches/sockets and require cables . As per Draft RFP
486 23 b. Rate Contract for
network LAN work
f. Conduiting/Wiring/Fixing of Modular accessories for electrical wiring to supply
electric power to LAN points.
Request RISL to please provide the specification of these accessories. As per Draft RFP
487 25 h. UAT(User Acceptance
Test)
Test Report for OFC/LAN cabling signed by the respective nodal /designated
officer.
Request RISL to please mention the required test which bidder need to perform for the UAT As per Draft RFP
488 26 Shifting of site
equipments and
connectivity under
RajNET/
RajSWAN:
If there is no change in the type of connectivity, the same
equipment shall be used for the connectivity and the bidder shall do the
necessary cabling & Earthing at new locations.
We assume that For new cabling and Earthing bidder can invoice to RISL . As per Draft RFP
489 28 5.2 Project Milestones,
Deliverables& Timelines
d) Payments to the SP, after successful commissioning of links of the work order shall be made on
Half yearly basis i.e. Half yearly equated instalments as per the agreed rates from the “Date of
Commissioning & Go-Live” of links (As per As per RFP Clause: “A. Scope of Work” (Chapter 5))
on receipt of following deliverables:
We Request RISL to please allow bidder to raise quarterly invoice, as RISL know from some time the industry health is
not good and to maintain the eco system liquidity requires.
The payment for each lot shall be released Quarterly
from commissioning & Go-Live of the lot/link
490 28 5.2 Project Milestones,
Deliverables& Timelines
Deployment Technical Resource for Dedicated Single
Point of Contact (SPOC) as defined in Annexure -3 Within 21 days from issuing of first work/ feasibility order
We request RISL to please allow mim 45 days for Deployment of Technical Resource As per Draft RFP
491 29 Lot Size and
Commissioning timelines
For Feasibilty
Upto 50 Links - 1 week
Upto 50 Links with end equipments - 1 week
More than 50 Links - 2 weeks
We request RISL to please provide the feasibility timelines as below as bidder team need to physically visit all the sites
for the feasibility which is not possible in given time lines .
Require min timelines
Up to 50 Links - 3 week
Up to 50 Links with end equipment's - 3 week
More than 50 Links - 5 weeks
As per Draft RFP
492 29 Lot Size and
Commissioning timelines
Link Commissioning timeline (Excluding UAT period)
Upto 50 Links - 4 week
Upto 50 Links with end equipments - 6 week
More than 50 Links - 8 weeks
We request RISL to please provide the feasibility timelines as below as bidder team need to physically visit all the sites
for the feasibility which is not possible in given time lines .
Require min timelines
Up to 50 Links - 6 week
Up to 50 Links with end equipment's - 10 week
More than 50 Links - 12 to 14 weeks
As per Draft RFP
493 29 Lot Size and
Commissioning timelines
Note:The payment process for the work order shall be start after issuing of Go-live date of last lot.
However, payable amount of links shall be effective from Go-live date of Links.
Request RISL to release payment of each go-live not on the complete lot. Installation & delivery depends on site
readiness & customer permission for which bidder will not be completely responsible.
As per Draft RFP
494 29 For Network Equipment Delivery Challan
•Invoice Copy
•Installation Report & UAT
•Warranty certificate issued
by respective OEMs for
each hardware/Software
We assume that bidder need to provide the warranty from the delivery date of hardware , please confirm As per Draft RFP
495 29 For Network Equipment Timelines - 60 days We request RISL to please provide the 75 days for the delivery As per Draft RFP
496 29 For Network Equipment Payment Terms 90% of total work order value
and remaining 10% in equated installment yearly i.e
2% at the end of each year OR this remaining 10% may
be released against Bank Guarantee of equal amount
Request RISL to please confirm whether bidder can raise the 100 % amount invoice or need to raise in 90%+ 10% As per Draft RFP
497 29 For LAN Work Timelines - Final Survey report/Design/document - 2 weeks We request RISL to please provide mim 4 weeks for the site survey as bidder need to do the physical visit for each
location
As per Draft RFP
498 29 For LAN Work Timelines- Installation andCommissioning of IT
infrastructure & cabling as detailed in SoW - 6 weeks
we request RISL to please provide the minimum 8 weeks for the installation as its depend on hardware delivery also As per Draft RFP
499 30 Note:- a) RISL is working as a Pure Agent and executing the projects on behalf of Government of Rajsthan. All the invoices
should be raised in the name of department for which goods and services will be taken. The name for which billing
will be done, shall be intimated by RISL
we request RISL to please remove this clause as bidder is getting PO from RISL then bidder should invoice to RISL only. As per Draft RFP
500 56 30. Warranty a) The bidder must supply all items of BoM (Annexure-1) with comprehensive on-site valid warranty for the period
of as mentioned in Technical Specification (Annexure –2). And
all other items (including passive components) where warranty period not mentioned,are to be supplied with 3 years
on site warranty/ maintenance
we assume that warranty start date is delivery date of hardware at respective location - please confirm As per Draft RFP
501 64 SLA for MPLS
Connectivity:
SLA Matrix: Initial Response Time (IRT) to rectify and restore the services will be calculated from the time of
detection of non-availability of services either through HDMS/ NMS/ or registration of complaints at Help
Desk/Service Window or any other mechanism adopted under the project (by DoITC/RISL), whichever is earlier. IRT
asbelow shall be permitted and excluded from SLA breach:
We request RISL to start the IRT from the time call logged with bidder helpdesk. As per Draft RFP
502 64 SLA for MPLS
Connectivity:
Location Prime Hours Non-Prime Hours
HUB Sites at SHQ 15 Minutes 30 Minutes
End Office at SHQ/DHQ level 30 Minutes 60 Minutes
End Office at BHQ/GP level 60 Minutes 90 Minutes
We request RISL to please amend the clause as below .
Location Prime Hours Non-Prime Hours
HUB Sites at SHQ 30 Minutes 60 Minutes
End Office at SHQ/DHQ level 60 Minutes 90 Minutes
End Office at BHQ/GP level 90 Minutes 120 Minutes
As per Draft RFP
503 64 SLA for MPLS
Connectivity:
Service Level Requirement for each link:The BIDDER/SP has to maintain the network uptime at each of the locations
as per the table given below:
We request RISL to please provide some relaxation in ILL and P2P SLA as below
End Office at SHQ/DHQ level - 98% and 96%
End Office at BHQ/GP level -98% and 96%
As per Draft RFP
504 64 4. Uptime and SLA
exclusion time
calculation shall be done
as below:
2) In addition to IRT, following shall be excluded from fault duration (SLA Exclusion
time):
In addition given point we request RISL to please add below mention points also in SLA Exclusion
NO SLA penalty will be applicable on bidder incase the location is down due to
1) Power issue at customer end.
2) Improper earthing at site where earthing is not provided by bidder.
3) Equipment damaged due to water seepage, gone faulty due to power/fire.
4) Access not available at site for the bidder engineer to check the issue.
5) Local contact person not available at site.
6) Any condition which is beyond the control of bidder.
7) Theft of hardware.
8) Any delay in pick & drop from respective sites to block level which is RISL's responsibility.
As per Draft RFP
505 65 5. Measurement of
Service Level Parameter:
i.
2) The uptime shall be calculated on quarterly basis during the entire project period by DoIT&C/RISL/ designated
agency using EMS/ NMS tool and penalty if any would be
charged per Quarter. Downtime of any one of the services (Voice, Video and Data) would result in deduction of that
downtime from the total time in the Quarter
We request RISL to please calculate the SLA from the time of complaint logged with the bidder helpdesk, as bidder will
get the restoration work start after the intimation only
As per Draft RFP
506 65 5. Measurement of
Service Level Parameter:
i.
4)Committed Interface Rate (CIR): The Committed Interface Rate (CIR) is a QoS type arrangement. It is basically an
agreement that the Bandwidth Service Provider/Bidder
ensures that the purchaser has a guaranteed minimum data rate across the network. Failure to provide this rate
could result in a breach of contract. The bandwidth to be
provided shall be non-shared bandwidth. CIR shall be measured at all times. The link shall be treated as down if the
CIR for that particular link is below 95% of ordered
bandwidth. Penalties would be calculated accordingly.
We request RISL to please keep CIR as per the IEEE standards As per Draft RFP
507 68 SLA for the Hardware
component
Replacement due to repeated failure
If, during the warranty period, any equipment
has any failure on two or more occasions
Request customer to please amend the clause as below
Replacement due to repeated failure
If, during the 3 months period, any equipment
has any failure on two or more occasions
As per Draft RFP
508 68 7. Penalty for non-
achievement of Service
Level Requirements
More than Next Business Day - 2% of Device Cost Per Day, Up to
maximum of device cost.
We request RISL to please relax the penalty as below
More than Next Business Day - 0.2% of Device Cost Per Day, Up to 20% of device cost.
And also request RISL to exclude any delay in pick & drop from respective sites to block level which is RISL's
responsibility. Any fault or ticket log after 2PM if any hardware replacement is required will be done by bidder (NBD
+1 business day).
As per Draft RFP
509 69 7. Penalty for non-
achievement of Service
Level Requirements
The Downtime would be calculated for each item from the time ticket through NMS or
by raising ticket on OEM / SI portal
We request RISL to calculate the downtime from the time ticket has been logged with bidder helpdesk As per Draft RFP
510 69 A. Delay in Time for LAN
Connectivity work:-
Delay in time for providing Final Survey report to DoIT&C/RISL Beyond T+2 weeks from the issue of survey work
order Rs.2500 per day
We request RISL to please change from 2500 Rs to 500 RS and also provide the extension in delivery time lines as
request earlier
As per Draft RFP
511 69 A. Delay in Time for LAN
Connectivity work:-
Delay in time for installation of required IT Infrastructure at
government office/premises/GPs Beyond T+6 weeks from
the issue of work order Rs.2500 per day
We request RISL to please change from 2500 Rs to 500 RS and also provide the extension in delivery time lines as
request earlier
As per Draft RFP
512 69 A. Delay in Time for LAN
Connectivity work:-
3. The maximum total penalty in any event shall not be more than 25% of the total amount due for the event.
Imposition of maximum penalty for continuous 2 events
shall be treated as non-performance and beyond which the tendering authority may terminate the contract and
forfeit the PSD.
Request RISL to please reduce the penalty from 25% to Max 10 % As per Draft RFP
513 71 2. Personnel
Deployment:
The selected bidder has to deploy the minimum number of dedicated skilled personnel as mentioned in Annexure-3 Request RISL to ask for Senior Program Manager to govern the overall ecosystem. Program manager should be capable
of working closely with senior government officials. The Program Manager should have an experience of 12-15 years.
And also request RISL to ask 3 service engineers to maintain the ask SLA & complete project
As per Draft RFP
514 89 Item No. 29: - Earthing The voltage between Neutral &
Earth should not exceed more than
2 volts.
We request RILS to please allow mim 4 Volt as its is very difficult to achieve 2 V in Rajasthan due to soil and also please
confirm whether bidder need to maintain the earthing for complete contract or its one time activity OR ask two
earthpit for each location to acheive 2 volts between earth & neutral.
As per Draft RFP
Genral Central spoke Central spoke required from RISL for smooth operations As per Draft RFP
-> address and resolve all customer end issues. As per Draft RFP
-> provide link delivery acceptance As per Draft RFP
-> weekly/monthly project review As per Draft RFP
-> Invoice submission and clearance As per Draft RFP
23 3. Testing &
Commissioning
In case of delay/ non-completion of work by BIDDER/SP at any designated location(s) due to reasons not attributable
to the BIDDER/SP, the delay shall not be counted on part of
If any delay which in not attributable to bidder than links will be deemed acceptable for invoicing after 7 days of UAT
request submission from bidder .
As per Draft RFP
bidder/SP and no LD shall be imposed for such links. As per Draft RFP
24 Rate Contract for
network LAN work
The Successful bidder has to ensure that the installed network equipment like Bidder will be responsible only for those active hardware which is the part of BOQ and will able to under stand the
SNMP string
As per Draft RFP
Switches/End points (access point) etc. which are to be connected in LAN are As per Draft RFP
reflected in the network monitoring system deployed by DoIT&C/RISL. As per Draft RFP
518 72 ANNEXURE-1: BILL OF
MATERIAL (BOM)
PART – A: MPLS,P2P and ILL Connectivity (Rate Contract): Request RISL to please share the complete location address with required media(Fiber/RF),so bidder can do the
feasibility
As per Draft RFP
ANNEXURE-2:
TECHNICAL
SPECIFICATIONS
Bidder/SI/SP should ensure that all the software, hardware, peripherals, accessories, sub-components Since this is rate contract bidder will do the site survey and share the requirement with RISL to get the approval , if any
hardware /Soft ware/ Passive component which is not the part of BOQ then RISL need to procure same and will
provide to bidder
As per Draft RFP
required for the functionality and completeness of the solution, including devices, equipment, As per Draft RFP
accessories, patch cords (copper / fiber), cables, software, licenses, development / testing kits, tools, As per Draft RFP
etc. should also be provisioned according to the requirements of the solution. Also, any additional As per Draft RFP
components, sub-components, assemblies, sub-assemblies that may be required to meet the desired As per Draft RFP
performance requirements will have to be provisioned by the SI at no additional cost. As per Draft RFP
520 85 Item no. 26 EN/IEC Standard Ratings :EN/IEC 60068-2-27,ESD EN/IEC 61000-4-2, EN/IEC 61000-4-3, EN/IEC 61000-4-4, EN/IEC
61000-4-6, EN/IEC 61000-4-8, EN/IEC 60068-2-6,RoHS
and EMC as FCC Part 15, Class A
Request to change "EN/IEC 60068-2-27" to "EN/IEC 60068-2-27/IEC 60255-21-2/IEC 60255-21-1.
Justification:
EN/IEC 60068-2-27 is intended for equipment or products that could be subjected to infrequent or repetitive shocks
during storage, use or transportation. Equivalent to this we have IEC 60255-21-2 (mechanical shock) & IEC 60255-21-1
(vibration) which is equivalent to the mention standard.
EN/IEC 60068-2-27/IEC 60255-21-2/IEC 60255-21-
1,ESD EN/IEC 61000-4-2, EN/IEC
61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6,
EN/IEC 61000-4-8, EN/IEC 60068-2-6,RoHS and EMC
as FCC Part 15, Class A
521 85 Item no. 26 8 Ethernet 10/100 ports and 2 dual-purpose
uplinks (each dual-purpose uplink port has 1
10/100/1000 Ethernet port and 1 SFP-based Gigabit Ethernet
port with single mode transceiver, 1 port active)
8 Ethernet 10/100/1000 ports and 4 Gigabit SFP uplinks
Justification:
Since 8 Ethernet ports are allready provided , we don't think there is need of any dual pupose uplinks. Since gigabit
ports are requested in uplinks , we would request to kindly make 8 ethernet ports gigabit and keep 4 gigabit SFP
uplinks . Earlier design is specific to one OEM Only.
8 Ethernet 10/100/1000 ports and 2 SFP-based
Gigabit Ethernet uplink port with populated single
mode transceiver
522 85 Item no. 26 IEEE 802.3at on minimum 4 10/100 ports or
better POE Budget : min. 120w
IEEE 802.3at/ 802.3bt on minimum 4 10/100/1000 ports or
better POE Budget : min. 120w
Justification
As per Draft RFP
523 80 2.2 Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink
portspopulated with 1G single mode transceivers.
Request you to amend the Clause " Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate
2*1/10Gbps Fiber based SFP Uplink ports populated with 1G single mode transceivers. "
Justification
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers524 81 1.11 The switch should have PoE/PoE+ output and should have minimum 120 watt power Request You to Amend the clause " The switch should have PoE/PoE+ output and should have minimum 240 watt
power "
Justification
As per Draft RFP
525 83 7.4 TFTP and Secure FTP support Request you to amend the Clause "TFTP and Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification
TFTP, FTP /Secure FTP/ Secure Copy support
526 83 8.9 TFTP, FTP or Secure FTP support Request you to amend the Clause "TFTP, FTP /Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification:
Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches OS size in in
Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly accept the
change
TFTP, FTP /Secure FTP/ Secure Copy support
527 86 1.1 OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
Request you to amend the Clause to OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019"
Justification:
1. L3 switch has also been asked from the complete gartner magic quadarant. 2. There are only 2 OEMS
qualified by the clause which restricts the participation of the other leading OEMs for this prestigious project.
As per Draft RFP
528 86 1.2 16 RJ-45 autosensing 10/100/1000 ports with 2 open SFP slots populated with 1G single mode transceivers. Request you to amend the Clause " Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate
2*1/10Gbps Fiber based SFP Uplink portspopulated with 1G single mode transceivers. "
Justification:
It is indusrty Trend that Uplink Port Bandwidth should be minumum 60% of downlinking Port.
As per Draft RFP
529 88 5.4 TFTP and Secure FTP support Request you to amend the Clause "TFTP and Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification
Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches OS size in in
Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly accept the
change
TFTP, FTP /Secure FTP/ Secure Copy support
530 49 4 Joint Venture, Consortium or Association Request you to allow for Joint Venture, Consortium or Association
Justification
Joint Venture or Consortium partner will make help to execute the project in given project dead line.
As per Draft RFP
531 Suggestion Request you to please add the clause in L2 switches and L3 switches "switch should be common criteria certified for
NDPP/NDcPP (Network Device Protection Profile)
Justification:
This is a security certifications which state that the hardware and the software of the switches has undergone the
global guidelines of security. The Security Requirements for Network Devices Protection Profile (NDPP) defines the
baseline Security Functional Requirements (SFRs) and Security Assurance Requirements (SARs) for network
infrastructure devices in general which is a must. All the leading OEMs support this.
As per Draft RFP
532 Pg No. 77 Item No. 20: Universal
SFP; 3 Type
Gigabit Ethernet, Single Mode Fiber Trans receiver Compatible with SFP MSA Please change the Clause to:
Gigabit Ethernet, Single Mode Fiber Transreceiver Compatible with the L2/L3 switches offered, from the same OEM
Reason:
Non-OEM SFP can impact the functioning of the switch and can generate hardware/software issues. Request to modify
the Universal SFP to Switch OEM SFP to ensure compatibility, quality testing and Warranty support.
As per Draft RFP
519
516
517
515
533 Page No.
77,78,79
Item No. 21,22,23,24 SFP -1G-LR for CISCO Routers of same OEM SFP -1G-ER for CISCO Routers of same OEM SFP -10G-LR for CISCO
Routers of same OEM SFP -10G-ER for CISCO Routers of same OEM
Please change the Clause- We request RISL to review these line
Items since these are Proprietary Items specific to one OEM , This Clause can effect/ Impact the overall participation of
other OEM/Partners Hence we request Department to remove these line items from this RFP & Department can plan
to buy these items /products separately so that multiple OEM can participate in this RFP...
As per Draft RFP
534 Pg No. 80 Item No. 25: L3 Switch:
1.1
OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change the clause:
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"..Same clause as been asked in L2 Switch( Item No27 )..Hence it looks a typo Error..So request you
to modify the clause so that all the competent OEMs can qualify.
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
535 Pg No. 80 Item No. 25: L3 Switch:
2.2
Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports
and separate 2*1Gbps Fiber based SFP Uplink ports populated with 1G
single mode transceivers
Request to change the clause:
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink ports
populated with 1G single mode transceivers.
Reason:
All the OEMs follow 24 port configurations.16-port switches are not standard configuration prevalent in the
networking industry. .Only one or two OEMs have such kind of configuration that too in a particular series switch.
Considering 16 port configuration will favour a particular OEM and hence will lead to a costly solution to the
Department. Equivalent 24 port switches will allow all OEMs to participate resulting in a much better competitive bid
to the department.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers
536 Pg No. 80 Item No. 25: L3 Switch:
2.2
Should have minimum 128 MB flash, 512 MB DRAM Request to change the clause:
Should have minimum 128 MB flash, 512 MB DRAM and packet buffer memory of minimum 8MB.
Reason: Packet Buffer is one of the most important feature of any electronic devie to avoid any information lost during
transmission. This will keep packets in the buffer in case of increased transmission traffic. Hence
this will improve the overall traffic forwarding and QoS capability of the switch. So Kindly modify the clause as
requested
As per Draft RFP
537 Pg No. 81 Item No. 25: L3 Switch:
2.11
The switch should have PoE/PoE+ output and should have minimum
120 watt power.
Please change the Clause to:
The switch should have PoE/PoE+ output and should have minimum 250 watt power.
Reason:
Current value of 120Watt is not justified by any calculation of Power Budget/port even if we consider 16 Port switch.
Considering the industry standard 24 Port we request you to modify the POE budget to support POE (15.4 Watts) on
all 16-ports and POE+ on other 8 ports. This will help the department to use High Wattage equipment's on the switch.
This will provide more flexibility and scalability to the department and with better commercials than 16 port switch
since more OEMs will be able to quote industry standard else department will end up in purchasing a 16 port switch at
a much higher prices.
As per Draft RFP
538 Pg No. 84 Item No. 26: - L 3
Outdoor Switch; Type
Managed Outdoor Industrial grade switch Request to change the clause:
Managed Outdoor Industrial grade switch/solution with industrial grade enclosures (with IP30/NEMA certification) .
As per Draft RFP
539 Pg No. 84 Item No. 26: - L 3
Outdoor Switch; Ring
Support
Switch Should support the Ring connectivity in uplink port (IEEE802.17/Equivalent), Request to change the clause:
Switch Should support the Ring connectivity in uplink port (IEEE802.17/Equivalent) or feature to provide link
redundancy of active and standby links without Spanning Tree.
Reason:
Request to accept other active/standby unlinking technology for fast failover without the use of Spanning Tree
As per Draft RFP
540 Pg No. 85 Item No. 26: - L 3
Outdoor Switch;
Industrial Rating
IP 30 and NEMA TS-2 Request to change the clause:
L 3 Outdoor Switch/Solution; Industrial Rating
As per Draft RFP
541 Pg No. 85 Item No. 26: - L 3
Outdoor Switch; EN/IEC
Standard
Ratings
EN/IEC 60068-2-27,ESD EN/IEC 61000-4-2, EN/IEC 61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6, EN/IEC 61000-4-
8, EN/IEC 60068-2-6, RoHS and EMC as FCC Part 15, Class A
Request to change the clause:
ESD EN/IEC 61000-4-2, EN/IEC 61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6, EN/IEC 61000-4-8, RoHS and EMC as
FCC Part 15, Class A
Reason:
Request to accept Enterprise grade switch with industrial grade enclosure (IP30/NEMA/Weatherproof),
vibration/shock being addressed through the enclosure
EN/IEC 60068-2-27/IEC 60255-21-2/IEC 60255-21-
1,ESD EN/IEC 61000-4-2, EN/IEC
61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6,
EN/IEC 61000-4-8, EN/IEC 60068-2-6,RoHS and EMC
as FCC Part 15, Class A
542 Pg No. 85 Item No. 26: - L 3
Outdoor Switch;
Operating Temperature
(-)10 to 70 degrees C or better Request to change the clause:
(-)10 to 70 degrees C or better on switch/solution
As per Draft RFP
543 Pg No. 86 Item No. 27: - L 2 Switch;
1.2
16 RJ-45 autosensing 10/100/1000 ports with 2 open SFP slots populated with 1G single mode transceivers. Request to change the clause:
24 RJ-45 autosensing 10/100/1000 ports with 2 open SFP slots populated with 1G single mode transceivers.
Reason:
All the OEMs follow 24 port configurations.16-port switches are not standard configuration prevalent in the
networking industry. .Only one or two OEMs have such kind of configuration that too in a particular series switch.
Considering 16 port configuration will favour a particular OEM and hence will lead to a costly solution to the
Department. Equivalent 24 port switches will allow all OEMs to participate resulting in a much better competitive bid
to the department.
As per Draft RFP
544 Pg No. 86 Item No. 27: - L 2 Switch;
1.4
128 MB flash, 256 MB DRAM Request to change the clause:
128 MB flash, 256 MB DRAM and packet buffer memory of minimum 1.5MB
Reason:
Packet Buffer is one of the most important feature of any electronic devie to avoid any information lost during
transmission. This will keep buckets in the buffer in case of increased transmission traffic. Hence
this will improve the overall traffic forwarding and QoS capability of the switch
As per Draft RFP
545 Pg No. 86 Item No. 27: - L 2 Switch;
Additional Point
PoE capability The switch should have PoE/PoE+ output and should have minimum 180 watt power.
Reason: Request to add POE support to L2 access switches for powering end devices like IP Phones, Access Points etc.
The switch should have PoE/PoE+ output and should
have minimum 120 watt power.
546 15 Pre-Qualification Criteria
# 8
The Bidder should have Manufacturers’ authorization and a direct back-to-back support agreement with the OEM for
the equipment’s included in the existing solution as per Annexure -1 (Part – B).
AND
The bidder must be an authorized system integrator for sale, support and services of the OEM who meets the criteria
under Eligible Goods and Services of the products being quoted in this bid.
OR
The bidder must be a manufacturer, distributor or bona-fide dealer in the goods and furnish necessary proof for the
same in the specified format.
Annx -1 (Part-B) is the list of the compnents/equipemnts to be supplied as a part of bid. It does not have list of any
existung solution.
Also, we kindly reqest you to relex this clause "The Bidder should have Manufacturers’ authorization and a direct back-
to-back support agreement with the OEM for the equipment’s included in the existing solution as per Annexure -1
(Part – B)." as scope of work as mentioned on Page No. 21/Clause -a is for new devices/ components/ equipments -
"The selected bidder shall be responsible for the supply, installation and commissioning of the required
Hardware/Accessories as per the BoM (Bill of Material Annexure-1) & Technical specifications (Annexure-2) of this
RFP, at various Government Office location across the Rajasthan State"
As per Draft RFP
547 Pg No. 77 Item No. 20: Universal
SFP; 3 Type
Gigabit Ethernet, Single Mode Fiber Trans receiver Compatible with SFP MSA Please change the Clause to:
Gigabit Ethernet, Single Mode Fiber Transreceiver Compatible with the L2/L3 switches offered, from the same OEM
Reason:
Non-OEM SFP can impact the functioning of the switch and can generate hardware/software issues. Request to modify
the Universal SFP to Switch OEM SFP to ensure compatibility, quality testing and Warranty support.
As per Draft RFP
548 Page No.
77,78,79
Item No. 21,22,23,24 SFP -1G-LR for CISCO Routers of same OEM SFP -1G-ER for CISCO Routers of same OEM SFP -10G-LR for CISCO
Routers of same OEM SFP -10G-ER for CISCO Routers of same OEM
Please change the Clause- We request RISL to review these line
Items since these are Proprietary Items specific to one OEM , This Clause can effect/ Impact the overall participation of
other OEM/Partners Hence we request Department to remove these line items from this RFP & Department can plan
to buy these items /products separately so that multiple OEM can participate in this RFP...
As per Draft RFP
549 Pg No. 80 Item No. 25: L3 Switch:
1.1
OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change the clause:
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"..Same clause as been asked in L2 Switch( Item No27 )..Hence it looks a typo Error..So request you
to modify the clause so that all the competent OEMs can qualify.
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
550 Pg No. 80 Item No. 25: L3 Switch:
2.2
Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports
and separate 2*1Gbps Fiber based SFP Uplink ports populated with 1G
single mode transceivers
Request to change the clause:
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink ports
populated with 1G single mode transceivers.
Reason:
All the OEMs follow 24 port configurations.16-port switches are not standard configuration prevalent in the
networking industry. .Only one or two OEMs have such kind of configuration that too in a particular series switch.
Considering 16 port configuration will favour a particular OEM and hence will lead to a costly solution to the
Department. Equivalent 24 port switches will allow all OEMs to participate resulting in a much better competitive bid
to the department.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers
551 Pg No. 80 Item No. 25: L3 Switch:
2.2
Should have minimum 128 MB flash, 512 MB DRAM Request to change the clause:
Should have minimum 128 MB flash, 512 MB DRAM and packet buffer memory of minimum 8MB.
Reason: Packet Buffer is one of the most important feature of any electronic devie to avoid any information lost during
transmission. This will keep packets in the buffer in case of increased transmission traffic. Hence
this will improve the overall traffic forwarding and QoS capability of the switch. So Kindly modify the clause as
requested
As per Draft RFP
552 Pg No. 81 Item No. 25: L3 Switch:
2.11
The switch should have PoE/PoE+ output and should have minimum
120 watt power.
Please change the Clause to:
The switch should have PoE/PoE+ output and should have minimum 250 watt power.
Reason:
Current value of 120Watt is not justified by any calculation of Power Budget/port even if we consider 16 Port switch.
Considering the industry standard 24 Port we request you to modify the POE budget to support POE (15.4 Watts) on
all 16-ports and POE+ on other 8 ports. This will help the department to use High Wattage equipment's on the switch.
This will provide more flexibility and scalability to the department and with better commercials than 16 port switch
since more OEMs will be able to quote industry standard else department will end up in purchasing a 16 port switch at
a much higher prices.
As per Draft RFP
553 Pg No. 84 Item No. 26: - L 3
Outdoor Switch; Type
Managed Outdoor Industrial grade switch Request to change the clause:
Managed Outdoor Industrial grade switch/solution with industrial grade enclosures (with IP30/NEMA certification) .
As per Draft RFP
554 Pg No. 84 Item No. 26: - L 3
Outdoor Switch; Ring
Support
Switch Should support the Ring connectivity in uplink port (IEEE802.17/Equivalent), Request to change the clause:
Switch Should support the Ring connectivity in uplink port (IEEE802.17/Equivalent) or feature to provide link
redundancy of active and standby links without Spanning Tree.
Reason:
Request to accept other active/standby unlinking technology for fast failover without the use of Spanning Tree
As per Draft RFP
555 Pg No. 85 Item No. 26: - L 3
Outdoor Switch;
Industrial Rating
IP 30 and NEMA TS-2 Request to change the clause:
L 3 Outdoor Switch/Solution; Industrial Rating
As per Draft RFP
556 Pg No. 85 Item No. 26: - L 3
Outdoor Switch; EN/IEC
Standard
Ratings
EN/IEC 60068-2-27,ESD EN/IEC 61000-4-2, EN/IEC 61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6, EN/IEC 61000-4-
8, EN/IEC 60068-2-6, RoHS and EMC as FCC Part 15, Class A
Request to change the clause:
ESD EN/IEC 61000-4-2, EN/IEC 61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6, EN/IEC 61000-4-8, RoHS and EMC as
FCC Part 15, Class A
Reason:
Request to accept Enterprise grade switch with industrial grade enclosure (IP30/NEMA/Weatherproof),
vibration/shock being addressed through the enclosure
EN/IEC 60068-2-27/IEC 60255-21-2/IEC 60255-21-
1,ESD EN/IEC 61000-4-2, EN/IEC
61000-4-3, EN/IEC 61000-4-4, EN/IEC 61000-4-6,
EN/IEC 61000-4-8, EN/IEC 60068-2-6,RoHS and EMC
as FCC Part 15, Class A
557 Pg No. 85 Item No. 26: - L 3
Outdoor Switch;
Operating Temperature
(-)10 to 70 degrees C or better Request to change the clause:
(-)10 to 70 degrees C or better on switch/solution
As per Draft RFP
558 Pg No. 86 Item No. 27: - L 2 Switch;
1.2
16 RJ-45 autosensing 10/100/1000 ports with 2 open SFP slots populated with 1G single mode transceivers. Request to change the clause:
24 RJ-45 autosensing 10/100/1000 ports with 2 open SFP slots populated with 1G single mode transceivers.
Reason:
All the OEMs follow 24 port configurations.16-port switches are not standard configuration prevalent in the
networking industry. .Only one or two OEMs have such kind of configuration that too in a particular series switch.
Considering 16 port configuration will favour a particular OEM and hence will lead to a costly solution to the
Department. Equivalent 24 port switches will allow all OEMs to participate resulting in a much better competitive bid
to the department.
As per Draft RFP
559 Pg No. 86 Item No. 27: - L 2 Switch;
1.4
128 MB flash, 256 MB DRAM Request to change the clause:
128 MB flash, 256 MB DRAM and packet buffer memory of minimum 1.5MB
Reason:
Packet Buffer is one of the most important feature of any electronic devie to avoid any information lost during
transmission. This will keep buckets in the buffer in case of increased transmission traffic. Hence
this will improve the overall traffic forwarding and QoS capability of the switch
As per Draft RFP
560 Pg No. 86 Item No. 27: - L 2 Switch;
Additional Point
PoE capability The switch should have PoE/PoE+ output and should have minimum 180 watt power.
Reason: Request to add POE support to L2 access switches for powering end devices like IP Phones, Access Points etc.
The switch should have PoE/PoE+ output and should
have minimum 120 watt power.
561 74/141 Item No. 17: - 6U Wall
Mount indoor Network
Rack
12 > Certifications > UL Listed. Only one or two rack OEM has UL certificate which is for their safety standard, not for the construction of rack, please
remove this condition as already you have asked IS014001:2004, which is meant for Quality Standard, please remove
" UL listed"
As per Draft RFP
562 76 Item No. 19- 1 KVA UPS
with Battery
15> Battery type No stand required as Batteries will be inside the UPS As per Draft RFP
563 76 Item No. 19- 1 KVA UPS
with Battery
16> Battery Make Kindly add Or Equivalent As per Draft RFP
564 76 Item No. 19- 1 KVA UPS
with Battery
17> VAH Required in each battery set maximum 168/216 VAH can be provided i.e 2x 7Ah or 2 x 9 Ah batteries which will provide 45 mints to 60 mints back
up. Please share Max load and backup timing required.
As per Draft RFP
565 77 Item No. 19- 1 KVA UPS
with Battery
23> Generator compatibility To provide Clean uninterrupted power when Generator is used. Query not clear
566 90/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Unshielded Twisted Pair, Category 6, TIA / EIA 568-C.2: (UL certificate should be submitted for CMR rating) 23 AWG
solid bare copper conductor
Usually CM rated cable is widely available, suitable for in-wall installation of Ethernet cables, while CMR cable is
suitable for use in Riser installation between floors , CM type is inexpensive 23 AWG solid bare copper conductor,
asking for CMR is only increasing the cost of cable and favouring some specific OEM. so Please change to "
(UL certificate should be submitted for CM/CMR rating"
Unshielded Twisted Pair, Category6, TIA / EIA 568-
C.2: (UL certificate should be submitted for CM/CMR
rating) 23 AWG solid bare copper conductor
567 91/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Polyethylene insulation/LSZH, CMR rated jacket as per UL 1666 or IEC 60332-3 When we are requesting to change the requirement to CM/CMR , please change to " FRPVC CM/CMR rated jacket as
per UL 1666 or IEC 60332-3 "
Polyethylene insulation/LSZH, CM/CMR rated jacket
as per UL 1666 or IEC 60332-3
568 91/141 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals {ETL report for zero bit should be submitted)
Certificate to be submitted accordingly for CM/CMR type cable Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
569 92/141 Item No.31: - Cat 6
Ethernet Cable
Unshielded Twisted Pair, Category 6, TIA / EIA 568-C.2: (UL certificate should be submitted for CMR rating) 23 AWG
solid bare copper conductor
Usually CM rated cable is widely available, suitable for in-wall installation of Ethernet cables, while CMR cable is
suitable for use in Riser installation between floors , CM type is inexpensive 23 AWG solid bare copper conductor,
asking for CMR is only increasing the cost of cable and favouring some specific OEM. so Please change to "
(UL certificate should be submitted for CM/CMR rating"
Unshielded Twisted Pair, Category6, TIA / EIA 568-
C.2: (UL certificate should be submitted for CM/CMR
rating) 23 AWG solid bare copper conductor
570 92/141 Item No.31: - Cat 6
Ethernet Cable
Polyethylene insulation/LSZH, CMR rated jacket as per UL 1666 or IEC 60332-3 When we are requesting to change the requirement to CM/CMR , please change to " FRPVC CM/CMR rated jacket as
per UL 1666 or IEC 60332-3 "
Polyethylene insulation/LSZH, CM/CMR rated jacket
as per UL 1666 or IEC 60332-3
571 92/141 Item No.31: - Cat 6
Ethernet Cable
Cross- member fluted member pair separator, ETL or 3P tested for TIA/EIA-568C.2, 3P, also verified to Cat 6 for Zero
Bit Error verified by ETL Approvals (ETL report for zero bit should be submitted)
Certificate to be submitted accordingly for CM/CMR type cable Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
572 92/141 Item No.31: - Cat 6
Ethernet Cable
Attenuation(dB/100m) 32.8MAX. At 250MHz, 43.2MAX. At 400MHz, 54.8MAX. at 250 MHz Please check as different Attenuation(dB/100m) value is asked for 250 MHz, Please ask to submit the channel
performance chart in datasheet
Attenuation(dB/100m) - 32.8MAX. At
250MHz
573 93/141 Item No. 32: -
Information Outlets
Jack contacts : Beryllium copper Please add the option of " The Jack contact can be phosphor bronze with gold plated " which is widely accepted Jack contacts: Beryllium copper/ phosphor bronze
with thick gold and minimum thick nickel under
plate, Performance
Characteristics Attenuation, NEXT,
PS NEXT, FEXT and Return Loss, IDC
Contact: Phosphor bronze
50micron" gold plated contact
Surface
574 98/141 Item No. 39: - 6 core
ADSS OFC
Compliance to TEC/GR/TX/OAF-001/03 MAR 2017 and GR No. GR/OAF-01/02. JUL 2005 and subsequent
amendments, if any.
TEC/GR is very rare available and very few 1 or 2 OEM are complied to this, being ADSS construction, it should be
allowed on the performance basis and should have approval EIA/TIA in place of TEC GR,
As per Draft RFP
575 Page
No.13
4.4.A The bidder must have successfully
completed:
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 30.00CR
during the period from 01/04/2015 to
31/03/2020.
This condition should be relaxed for Central PSU/State PSU.
OR
the period of project should be from 01.12.2014 to 31.03.2020.
The bidder must have successfully
completed
One project of Supply and Installation of
active Networking devices (Router/Switches
and other active network equipment) value
not less than the amount of Rs. 20.00CR
during the period from 01/04/2015 to
31/03/2020.
576 Page
No.13
4.4.A Annexure-15
and
Work Order + Work
For Completion
Certificates from the
client;
OR
Work Order + Phase
Completion
Only the work order/purchase order should be considered as the works are in progress and not completed due to
Lockdown/COVID-19 situation.
As per Draft RFP
577 Page
No.14
4.4.B B.The bidder must have agreement with
minimum Three NBSP (Network Bandwidth
Service Provider) within 15 days of LOI. At
the time of Tripartite agreement,The NBSP
should have:
a) Avalid UASL/USL/CMTS/2G/3G And NLD
License for Rajasthan Telecom Circle duly
issued by DoT.
b) Network management center with DR
facility, at different locations in India.
1. The NBSP should have UL and NLD license as IBW services can be provided through UL license and MPLS/P2P sevice
comes under NLD license.
2. There should be only one NBSP, as it is difficult to match the rates for all three NBSP for SI.
A valid UL-Internet Service-Category-A and NLD
Licenses for Rajasthan Telecom Circle duly issued by
DoT.
578 Page
No.14
4.6 The bidder must possess, at the time of
bidding, a valid ISO 9001 / ISO 20000 / ISO
27001/ CMMi Level V.
The certification required should be CMMI Maturity Level-3, as it fulfills the criteria. As per Draft RFP
579 Page
No.17
5.1.A.2.c The last mile connectivity at SHQ shall be provided only on fiber and the last mile
connectivity end-office location may be provided either on Wired / Wireless media.
No charges shall be paid for aggregated bandwidth at SHQ.
The Right of Way (ROW) charges for last mile connectivity shall be paid by RISL Please clarify. As per Draft RFP
580 Page No.
28
5.2.a.2 Link Commissioning: As per timelines
defined in below
table
The time taken in procuring ROW should be waived off and should not be counted in Link Commissioning time., ROW
charges should be waived off or paid by RISL because links are used for office use of Rajasthan Government.
As per Draft RFP
581 Page No.
28
5.2.a.4 O&M Phase The costing of O&M for 3 year duration is to be included in the financial Bid or is extra. Please clarify. As per Draft RFP
582 Page No.
16
5.1.A.1 RISL shall provide the list of sites to be connected to bidder/SPs. Bidder/SPs shall
perform Site-survey of all the ordered locations for feasibility. The Bidder/SPs shall
intimate feasible links within specified timelines. If no intimation is provided by
bidder/SPs within specified days, it shall be deemed that the site(s)are feasibleto
the bidder/SP.
If all the NBSP are not feasible at some locations, the Bidder/NBSP should not be responsible for commissioning of
same.
As per Draft RFP
583 Page No.
72
ANNEXURE-1: BILL OF
MATERIAL (BOM)
PART – A: MPLS,P2P and ILL Connectivity (Rate Contract Address of the links are not mentioned, only quantities are given. It is difficult to calculate the costing of link in the
absence of same. It is requested to kindly provide the address of Source/End offices or indicate the last mile distance.
OR
Last Mile Charges should be applicable seperately for individual links.
As per Draft RFP
584 Page 81 Item No. 25: - L3 Switch
1.1
1.1OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019" Request to change this clause to
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
OEM should be in " Leaders Quadrant of latest
Gartner's magic Quadrant for the Wired and wireless
LAN access infrastructure 2019"
585 Page 81 Item No. 25: - L3 Switch
2.2
2.2 Should have Minimum 16 RJ-45
autosensing 10/100/1000 ports
and separate 2*1Gbps Fiber based
SFP Uplink portspopulated with 1G
single mode transceivers.
Should have Minimum 24 RJ-45 autosensing 10/100/1000 ports and separate 4*1Gbps Fiber based SFP
Uplink portspopulated with 1G single mode transceivers.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers
586 Page 82 Item No. 25: - L3 Switch
8.15
3.4The Switch should support stacking of switches The switch should support dedicated stacking port separate from uplink ports with 48 Gbps of stacking bandwidth.
Justificaton : with 48Gbps stacking bandwidth, can support higher data transfer between stacked switches of 2 or
more.
The Switch should support stacking or virtual
switching fabric creation with stacking cable or
standard optical fiber connectivity as per the
requirements.
587 Page 82 Item No. 25: - L3 Switch
5.2
5.2The switch should support minimum 256 static IP routing Request to change this clause to
"The switch should support minimum 256 static IP routing / 1000 IPv4 routes"
Justification: For layer 3 switch, having routing protocol running will have better results in terms of
redundancy and resiliency. Request to allow 1000 Routes as alternative.
The switch should support minimum 256 static IP
routing/1000 IPv4 routes
588 Page 84 Item No. 25: - L3 Switch
8.15
8.15 The switch should support IPv6 Guard, Source-Guard features Request to change this clause to
Switch should support IPv6 Source Guard,IPv6 DHCP Guard, IPv6 RA Guard, IPv6 Neighbor Discovery Inspection,
Neighbor Discovery (ND) protocol snooping, IPv6 Prefix Guard, IPv6 Destination Guard
Justification: Above are bare minimum IPv6 feature required for basic IPv6 security.
As per Draft RFP
589 Page 81 Item No. 25: - L3 Switch New Clause Request to add clause
Switch should support External/Internal Redundant Power Supply.
Justification : Being Layer 3 switch will be installed at important locations, This switch should have provision to
support redundant power supply to continue operations.
As per Draft RFP
590 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Must have SDCard/memory card for easier switch Replacement , to ensure that field switch does not require
reconfiguration and storage cards can be swapped.
As per Draft RFP
591 Page 85 Item No. 26: - L 3
Outdoor Switch
New Clause Request to add clause
Switch must support IPv6 management and troublshooting features like IPv6 Ping, IPv6 traceroute, IPv6 Telnet, IPv6
SSH, HTTP over IPv6, SNMP over IPv6 and Dual Stack
Justification : These are basic IPv6 features needed for both layer 2 or Layer 3 switch and must for Network basic
operations/troubleshooting.
As per Draft RFP
592 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Shall support IEEE 802.3az Energy- efficient Ethernet (EEE) to reduce power consumption
Justificaiton : This feature helps in reducing power consumption
As per Draft RFP
593 Page 87 Item No. 27: - L2 Switch New Clause Request to add
Switch should support UDLD, MLD v1 and v2 snooping, IP Source Guard features.
Justificaiton : This are basic features for layer 2 switch and help for better traffic management and security
As per Draft RFP
594 Page 79 Item No. 21: - SFP -1G-LR
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, "SFP -1G-LR" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
595 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
596 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
597 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
598 Page 79 Item No. 22: - SFP -1G-ER
for CISCO Routers of
same OEM
Query Request to reconfirm partcode, " GLC-EX-SMD" Ideally should be "GLC-LH-SMD" which is supported on most of ASR903
platform. For ASR9010 Partcode will be different as per linecard. Compatibility matrix at https://tmgmatrix.cisco.com/
As per Draft RFP
599 Page 79 3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible with SFP MSA Request to change as below
3TypeGigabit Ethernet, Single Mode Fiber Transceiver Compatible
Type Gigabit Ethernet, Single Mode Fiber
Transceiver Compatible
600 Page 79 7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
601 Page 79 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
602 Page 79 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
603 Page 79 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
604 Page 80 Item No. 23: - SFP -10G-
LR for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
605 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
606 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
607 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
608 Page 80 Item No. 24: - SFP -10G-
ER for CISCO Routers of
same OEM
7Operating Temperature-10 ̊C to + 60 ̊C 7Operating Temperature -0˚ C to + 60˚ C Operating Temperature -0˚ C to + 60˚ C
609 Page 80 8Standard ComplianceIEEE 802.3, ITU-T G.652, SFF-8472, EN 60825-1 8Standard ComplianceIEEE 802.3, ITU-T G.652, EN 60825-1 Standard ComplianceIEEE 802.3, ITU-T G.652, EN
60825-1
610 Page 80 9WarrantyThe product should have 5 year OEM comprehensive warranty. Request to Remove this clause, Support is clubbed to Product where SFP is installed and not covered for
spare(consumables)
The product should have 5 year Bidder comprehensive
warranty.
611 Page 80 10Hardware SupportShould support CISCO ASR 9010/903 Routers Please confirm linecard details, for ASR9010 optics model may differ for different line cards. As per Draft RFP
612 95 Item No.30: - Cat 6
Ethernet Cable in casing
and conduiting (with
laying)
Cross- member fluted member pair
separator, ETL or 3P tested
for TIA/EIA-568C.2, 3P, also
verified to Cat 6 for Zero Bit Error
verified by ETL Approvals (ETL
report for zero bit should be
submitted)
Please remove the ETL certificate as you already as UL Certification. ETL is a performance standard from third Party. Cross- member/ fluted member pair separator, ETL
or 3P tested for TIA/EIA-568C.2, 3P, (ETL
report should be submitted)
613 98 Item No. 39: - 6 core
ADSS OFC (with laying
including splice and
making termination at
ends in casing
and counduit)
Compliance to TEC/GR/TX/OAF-
001/03 MAR 2017 and GR No.
GR/OAF-01/02. JUL 2005 and
subsequent amendments, if any.
As TEC is a specific standard for telecommunication. Request you to kindly consider other common industry standards
as well like TIA/EIA,ANSI,IEEE, ISO/IEC
As per Draft RFP
614 73 PART – B: Network
Equipments, LAN Work&
Site Shifting (Rate
Contract):
SFP -1G-LR for CISCO Routers of same OEM Request you please remove MAF for the following Item. hence it is indicationg from a Particular OEM OEM MAF not required
615 73 PART – B: Network
Equipments, LAN Work&
Site Shifting (Rate
Contract):
SFP -1G-ER for CISCO Routers of same OEM Request you please remove MAF for the following Item. hence it is indicationg from a Particular OEM OEM MAF not required
616 73 PART – B: Network
Equipments, LAN Work&
Site Shifting (Rate
Contract):
SFP -10G-LR for CISCO Routers of same OEM Request you please remove MAF for the following Item. hence it is indicationg from a Particular OEM OEM MAF not required
617 73 PART – B: Network
Equipments, LAN Work&
Site Shifting (Rate
Contract):
SFP -10G-ER for CISCO Routers of same OEM Request you please remove MAF for the following Item. hence it is indicationg from a Particular OEM OEM MAF not required
618 25 2. Installation,
Integration and
Commissioning of the
Local Area Network
Laying of Flexible Unarmored indoor OFC through Conduits for in-campus work For Laying OFC underground / Wall, HDEP Pipe is mandatory request you to add HDEP Pipe in the BOM and the
quantity
As per Draft RFP
619 25 2. Installation,
Integration and
Commissioning of the
Local Area Network
The bidder would be required to lay the OFC cable in casing & fixing of ISI marked PVC conduit pipes having diameter
of minimum 20mm where OFC is to be laid within a Campus/building to connect different offices/Switches
OFC cable laying may required digging at different location . Request you please mention if there any digging requied
to connect different building , If yes , Please mention the meter and deep of digging.
As per Draft RFP
620 16 5. SCOPE OF WORK,
DELIVERABLES AND
TIMELINES
5.1. Detailsof Scope of Work (SoW) request you to share a overall Network diagram along with the details of all the location and the deliverables items
per location where work has to be done for better undestating the project interms of commercial.
As per Draft RFP
621 56 30. Warranty The bidder must supply all items of BoM (Annexure-1) with comprehensive on-site valid warranty for the period of
as mentioned in Technical Specification (Annexure –2). And
all other items (including passive components) where warranty period not mentioned, are to be supplied with 3
years on site warranty/ maintenance
Bidder can provide warranty if there any manufacturing defect of the product. Physical damage warranty shall not be
cover if any happends (like short circuit, physical damage caused by animals ) so please change it for Passive items.
As per Draft RFP
622 29 Lot Size and
Commissioning timelines
Link Feasibility timeline Request you please increase the time line by 3 weeks on the given times lines. As per Draft RFP
623 29 Lot Size and
Commissioning timelines
Link Commissioning timeline (Excluding UAT period) Request you please increase the time line by 3 weeks on the given times lines. As per Draft RFP
624 14 Specific Requirements The bidder must have agreement with minimum Three NBSP (Network Bandwidth Service Provider) within 15 days
of LOI. At
the time of Tripartite agreement,The NBSP should have:
Request you to remove this clause. As per Draft RFP
625 29 b. For Network
Equipment
Timelines We request you to release a corrigendum 90 days for delivery. As per Draft RFP
626 29 c.For LAN Work Timelines Request you please change the timeline 4 weeks Final Survey report/Design document As per Draft RFP
627 29 c.For LAN Work Timelines Request you please change the timeline 10 weeks For Inventory Details/Delivery Challan, Installation Report, User
Acceptance Report, Network Design Report
As per Draft RFP
628 80 2.2 Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate 2*1Gbps Fiber based SFP Uplink
portspopulated with 1G single mode transceivers.
Request you to amend the Clause " Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate
2*1/10Gbps Fiber based SFP Uplink ports populated with 1G single mode transceivers. " Justification It is
indusrty Trend that Uplink Port Bandwidth should be minumum 60% of downlinking Port.
Should have 24 RJ-45 autosensing 10/100/1000
ports and separate minimum 2*1Gbps Fiber based
SFP Uplink ports populated with 1G single mode
transceivers629 81 1.11 The switch should have PoE/PoE+ output and should have minimum 120 watt power Request You to Amend the clause " The switch should have PoE/PoE+ output and should have minimum 240 watt
power " Justification Minimum 15 watt PoE Budget should be available on all the Port which Basic Standard for
PoE.
As per Draft RFP
630 83 7.4 TFTP and Secure FTP support Request you to amend the Clause "TFTP and Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification Secure FTP is generally required in data center Switches where file Size is very high but Campus
Switches OS size in in Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them,
kindly accept the change
TFTP, FTP /Secure FTP/ Secure Copy support
631 83 8.9 TFTP, FTP or Secure FTP support Request you to amend the Clause "TFTP, FTP /Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification Secure FTP is generally required in data center Switches where file Size is very high but Campus
Switches OS size in in Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them,
kindly accept the change
TFTP, FTP /Secure FTP/ Secure Copy support
632 86 1.1 OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
Request you to amend the Clause to OEM should be in “Gartner Magic Quadrant for wired and wireless LAN 2019"
Justification 1. L3 switch has also been asked from the complete gartner magic quadarant. 2. There are
only 2 OEMS qualified by the clause which restricts the participation of the other leading OEMs for this prestigious
project.
As per Draft RFP
633 86 1.2 16 RJ-45 autosensing 10/100/1000 ports with 2 open SFP slots populated with 1G single mode transceivers. Request you to amend the Clause " Should have Minimum 16 RJ-45 autosensing 10/100/1000 ports and separate
2*1/10Gbps Fiber based SFP Uplink portspopulated with 1G single mode transceivers. " Justification It is
indusrty Trend that Uplink Port Bandwidth should be minumum 60% of downlinking Port.
As per Draft RFP
634 88 5.4 TFTP and Secure FTP support Request you to amend the Clause "TFTP and Secure FTP/ Secure Copy support" which will enable us for bidding.
Justification Secure FTP is generally required in data center Switches where file Size is very high but Campus Switches
OS size in in Mbs. For Secure Transfer of OS image or File there are Multiple ways and these are one of them, kindly
accept the change
TFTP, FTP /Secure FTP/ Secure Copy support
635 Request you to please add the clause in L2 switches and L3 switches "switch should be common criteria certified for
NDPP/NDcPP (Network Device Protection Profile) Justification This is a security certifications
which state that the hardware and the software of the switches has undergone the global guidelines of security. The
Security Requirements for Network Devices Protection Profile (NDPP) defines the baseline Security Functional
Requirements (SFRs) and Security Assurance Requirements (SARs) for network infrastructure devices in general which
is a must. All the leading OEMs support this.
As per Draft RFP
636 Industrial Rating : IP 30 and NEMA TS-2 NEMA TS-2 is an American standard for enclosure which shall not be made a compulsory requirement. These switches
are going to be installed inside an IP66 grade outdoor enclosure. Therefore to make the bid open and competitive,
kindly remove or make the NEMA-TS 2 Certification as optional requirement.
As per Draft RFP
637 Certification to be
provided by bidder:
UL,CE and NEMA TS-2 As per Draft RFP
638 Item No. 27: - L 2 Switch
General
OEM should be in " Leaders Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access
infrastructure 2019"
This Clause is restricting other OEMs to participate in the bid.
- Gartner Magic Quadrants doesn't certify/ confirms that Leader quadrant is the best followed by Challengers
quadrant and being in Visionary quadrant is a weakness as compared to being in Challengers Quadrant. - A vendor in the Challengers quadrant will have demonstrated sustained execution in the marketplace, and will have clear and long-term viability in the market, but may not have a complete access layer product portfolio for either products or network applications. - A vendor in the Visionaries quadrant demonstrates an ability to increase features in its offering to provide a unique and differentiated approach to the market. Visionaries will have innovated in one or more of the key areas of access layer technologies within the enterprise (for example, convergence, security, management or operational efficiency).Therefore it is clear that OEMs are positioned in different Quadrant based on their product fortfolio/ execution capabilities/ unique & innovation approach etc. We request you to kindly modify this as " OEM should be in " Leaders or Challengers Quadrant of latest Gartner's magic Quadrant for the Wired and wireless LAN access infrastructure 2019 or Data Center Magic Quadrant Report 2019"
As per Draft RFP
639 74 Item No. 17 6U Wall
Mount Network Rack
Department Requirement : Height: 6 U Height: 6U Usable space for 19" equipment’s
640 91-98 ITEM 31,34,35,37,38
CAT-6 , patch panel,
patch cord(1m,5m,10m)
Department Requirement : MAF requirement: Yes MAF requirement: Yes
641 86 Item 27 : L2 Switch Department Requirement : New Clause: The switch should have PoE/PoE+
output and should have minimum 120 watt power.
642 74 Item No. 19 1 KVA UPS
with Battery
Approvals : CE/ EN 50091-1/ EN 50091-2 compliant UPS Approvals : CE/ EN 50091-1/ EN 50091-2 compliant
UPS/BIS Certificate
643 Item No.
17,18,19,28,30,31,32,33,3
4,35,36,37,38,39,40,41,42,
43
New Clause : Product should be make in India