richard fisher 1 the university of texas at dallas project management richard fisher the university...
TRANSCRIPT
Richard Fisher1
The University of Texas at Dallas
Project Management
Richard Fisher
The University of Texas at Dallas
Richard Fisher2
The University of Texas at Dallas
Project Management
A PROJECT is a set of tasks (activities) with a definite
beginning and ending point.
Phases– Project Planning
– Project Scheduling
– Project Tracking
Richard Fisher3
The University of Texas at Dallas
Tasks
Task (Activity) --A work component needed to be accomplished; a task within the overall project that has a definite beginning and ending point. The activity consumes time.
Richard Fisher4
The University of Texas at Dallas
Work Breakdown Structure(pp 88-89)
Developed before the dependencies are identified
and activity durations are estimated.
List of tasks and duration (work) required for
project
WBS is foundation for project schedule
Richard Fisher5
The University of Texas at Dallas
Decomposition
Breaking a Task into smaller Tasks or Sub-Tasks
The lowest level tasks are independent, manageable units and can be performed in a reasonable (measurable) amount of time
The project manager is typically responsible for defining all top level tasks
Richard Fisher6
The University of Texas at Dallas
Decomposition Example
Using Microsoft Word as a decomposition tool
WBS Example
Student setting up their first web page on the UTD
server assignment
Fence Assignment (Individual Assignment 1)
MS Project Assignment (Individual Assignment 2)
Richard Fisher7
The University of Texas at Dallas
Steps in Project ManagementNetwork Analysis
Task Definition and Decomposition Define Relationships Estimate Task Times Construct Diagram Network Evaluation Project Tracking and Revision
Richard Fisher8
The University of Texas at Dallas
PM Networks
ACTIVITY (TASK) --A work component needed to be accomplished; a task within the overall project that has a definite beginning and ending point. The activity consumes time.
EVENTS -- Designates the beginning and / or ending of activities. A point in time. Also shows the precedence relationships of the activities.
NETWORK -- A combination of Activities and Events that describe the logic of the project. There is one definite starting and ending point.
Richard Fisher9
The University of Texas at Dallas
Relationships
Relationships determine task sequencing Finish-to-Start
– Task B cannot start until Task A is finished
– Most common type
Start-to-Start
– Task B cannot start until Task A is started
– A delay is often used in this relationship
A B
A
B
Richard Fisher10
The University of Texas at Dallas
Relationships
Finish-to-Finish– Task B cannot finish until
Task A is finished
Start-to-Finish– Task B cannot finish
until Task A is started
A
B
A
B
Richard Fisher11
The University of Texas at Dallas
Precedence Relationships
Task C may not begin until both A and B have been completed.
A and B may occur concurrently and are parallel tasks.B
AC D
BA
CF
D
E
Task D may begin after B is completed. Task E may begin after C is completed.
A-B-D-F and A-C-E-F are parallel paths.
Richard Fisher12
The University of Texas at Dallas
CPM- Critical Path Method
CRITICAL PATH -- The path through the network consisting of several activities whose total activity times are the longest of any path through the network.
The most pressing, dangerous, risky path through the network. Usually denoted by heavy lines through the activities on the Critical Path.
CRITICAL PATH TIME -- Total time of all activities on the critical path.
Richard Fisher13
The University of Texas at Dallas
CPM Terminology
EXPECTED TIME of a task (activity)
EARLIEST START -- Earliest time expected to complete all previous tasks.
EARLIEST FINISH = ES + T for a task.
LATEST FINISH -- Latest time a task can finish and still allow the project to finish on time.
LATEST START = LF - T for a task.
SLACK TIME = LS - ES or LF - EF(there is NO slack on the CP)
TES
EFLF
LS
S
Richard Fisher14
The University of Texas at Dallas
Network Evaluation Steps
1. Construct network diagram showing tasks, relationships and task times using standard format
2. Define the various paths through the network
3. Moving from left-to-right calculate the ES (Earliest Start) and EF (Earliest Finish) time for each task
4. Define Critical Path
5. Moving from right-to-left calculate the LF(Latest Finish) and LS (Latest Start) for each task
6. Note Slack Times
Richard Fisher15
The University of Texas at Dallas
Sample Laboratory Example
TASK AFTER TASK TIME1 Begin Project 02 Build laboratory - 123 Inspect laboratory 2 34 Install test equipment 2 65 Recruit lab staff - 36 Train lab staff 5 57 Perform pilot sample evaluation 3,4,6 68 End Project 0
Richard Fisher16
The University of Texas at Dallas
Task (Activity) Diagramming
On the critical path: ES = LS & EF = LF
T
ES EF
LFLS
(Expected Task time)
1. Description of
Task goes here
Richard Fisher17
The University of Texas at Dallas
Sample Laboratory CMP
1. Beginproject
3.Inspect lab
2. Build lab
4.Install equip
6. Train Staff
5.Recruit staff
7. Pilot
eval
8. End project
Richard Fisher18
The University of Texas at Dallas
3 3e= 12 15
2 12 l= 15 18 7 6 8. Finish
e= 0 12 e= 18 24 e= 24
l= 0 12 4 6 l= 18 24 l=
e= 12 18
l= 12 18 Paths:
1-2-3-7-8= 21
5 3 6 5 1-2-4-7-8= 24
e= 0 3 e= 3 8 1-5-6-7-8= 14
l= 10 13 l= 13 18
Sample Laboratory CMP
Richard Fisher19
The University of Texas at Dallas
Gantt Charts
Use Horizontal Bars to represent Tasks on a Horizontal Time Line
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 242 Build 123 Inspect 34 Install 65 Recruit 36 Train 57 Pilot 6
Richard Fisher20
The University of Texas at Dallas
Gantt Charts
Richard Fisher21
The University of Texas at Dallas
PERT/CPM Charts
The Program Evaluation Review Technique (PERT)
Critical Path Method (CPM) The distinctions between the two methods
have disappeared over time, and today the technique is called either PERT, CPM, or PERT/CPM
Richard Fisher22
The University of Texas at Dallas
PERT/CPM Charts
Overview of PERT/CPM– PERT/CPM is called a bottom-up technique
– Project tasks
– Once you know the tasks, their duration, and the order in which they must be performed, you can calculate the time that it will take to complete the project
Richard Fisher23
The University of Texas at Dallas
PERT/CPM Charts
PERT/CPM Tasks– Task box
– Task ID
– Task name
– Task Duration
– Start Day/Date
– Finish Day/Date
Richard Fisher24
The University of Texas at Dallas
PERT/CPM Charts
A PERT/CPM Example with Five Tasks
Richard Fisher25
The University of Texas at Dallas
Web Page Example
TASK AFTER TASK TIMEA Get UNIX Account - 1.1B Set up web directory A 0.7C Learn HTML - 1.1D Design Page - 0.9E Code Page C , D 1.2F FTP Page to Server B , E 0.5
Richard Fisher26
The University of Texas at Dallas
Project Tracking Tips
Update Project as needed Make sure tasks are broken down enough to
see progress (or lack of progress) Poor “task status” communication often
means poor progress Watch for changes in Critical Path Make sure that there are no “resource
conflicts”