risk analysis process training - florida department of... tea… · risk analysis process training...

76
RISK ANALYSIS PROCESS TRAINING TRAINING D i T i i E Design T raining Expo Disney’s Coronado Springs Resort Lake Buena Vista FL Lake Buena Vista, FL

Upload: hakhanh

Post on 07-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

RISK ANALYSIS PROCESSTRAININGTRAINING

D i T i i EDesign Training ExpoDisney’s Coronado Springs Resort

Lake Buena Vista FLLake Buena Vista, FL

Presentation Format

Risk Analysis Process Overview

Presentation Format

Risk Analysis Process OverviewGreg Davis, PEState Estimates Engineer

Risk Analysis WorkshopKurt Lieblong, PE, CVSgState Project Review Administrator

Project Manager Roles Project Manager RolesRob Quigley, PEState Project Management Engineer

2

What is Risk?

• Project Management Institute (PMI) Says: oject a age e t st tute ( ) Says:“An uncertain event or condition that, if it occurs, has a positive or negative effect on the project’s b ”objectives.”

S Scope

$

S Schedule

Cost

What is Risk Management?g

• The systematic process of identifying,The systematic process of identifying, assessing, and responding to risks in order to manage or reduce potential adverse effects on the achievement of program and project goals.

• Goal: To increase the likelihood ofGoal: To  increase the likelihood of meeting on‐time and on‐budget  project mandates.

Why Risk Analysis?y y

Traditional Risk-BasedTraditional Contingency is intended to

include all risk (known & unknown)

Risk Based Risk are clearly identified and

quantified Reasonable control of cost andunknown)

Little control of cost and schedule

Reactive

Reasonable control of cost and schedule

ProactiveThreatThreatThreatThreat Reactive

1, 2,3,etc1, 2,3,etcThreatThreat

1, 2,3,etc1, 2,3,etc

OpportunityOpportunity1, 2, 3, etc1, 2, 3, etc

ContingencyContingency

Why Risk Analysis?

St bili & S t W k P ith b tt

y y

Stabilize & Support Work Program with bettercost estimates and scheduleso Validate cost & schedule for accurate project deliveryo Validate cost & schedule for accurate project delivery o Replace general project contingency with risk-based costo Quantify District Work Program Contingency.

Enhance Risk Assessment/Mitigation activities in Enhance Risk Assessment/Mitigation activities inProject Management

Support FHWA requirement for financial plans onmajor projects by providing risk-based cost estimates

6

Why Risk Management?y g

• Encouraging pro-activity and early planningEncouraging pro activity and early planning • Building confidence and credibility in project’s plans and

estimates• Developing targeted mitigation strategies for all anticipated

threats• Better allocation of risks and identification of project delivery• Better allocation of risks and identification of project delivery

methods• Ensuring transparency, integrity, and accountability

throughout the life-cycle of the project

Maximizing the Likelihood of MeetingTime & Budget Goals

Typical Project Scenario without Risk Management

Construction

without Risk ManagementConstruction

et

Design

Ove

r B

udge

ost

PD&E

O

Co

Late

PD&EDesign

Construction

Time

(nationwide trend)

Typical Project Scenariowith Risk Managementwith Risk Management

ost

Co

Design Construction

actualWithin Budget

Design ConstructionOn-time

Time

(nationwide trend)

When to Use Ri k M tRisk Management

• Early planning and budgeting• Early planning and budgeting

• Evaluation of project delivery alternatives

• Financial Planning Support

• Establishing Risk Allocation between partiesEstablishing Risk Allocation between parties

• Preparation of project contract documents

• Throughout Project Delivery Lifecycle

Risk Management Objectivesg j

• “ to increase the probability and impact of positive• …to increase the probability and impact of positive events, and decrease the probability and impact of negative events in the project.”*

• Make better decisions

• Allocate risks to those who can best control them

• Increase agency credibility

• Foster good relationships with project stakeholdersFoster good relationships with project stakeholders

* Source: PMI

Risk ManagementO tOutcomes

Validation of Project Cost and Schedule Validation of Project Cost and Schedule

Managed Risk Response Plan Managed Risk Response Plano Identification of high cost and schedule risk drivers

Managed District Contingency Boxo Reduced Contingency as project evolves

Understand and Communicate Cash Flow Requirements and Financial PlansRequirements and Financial Plans

Risk Management Processg

Risk Management Processg

Identifyy

AssessPlan &OrganizeOrganize

AnalyzeMonitor

MitigateAllocate

& Control

Risk Management Processg

• Review purpose & need

Plan & Organize

• Review purpose & need

• Gather project information & data

Risk Management ProcessgIdentify

•Where to Start?-Start-up Risk ListStart up Risk List-Lessons Learned -Project KnowledgeProject Knowledge-Project History-Brainstorming inBrainstorming inTeam Setting

Risk Management ProcessgAssess

Probability Impact to Schedule Impact to Cost

40% 60 Daysx $100,000and/or

40% 60 D 0.1M

10% 90% 10% 90% 10% 90%

0.1M

Risk Management ProcessgQualitative Analysis

Risk Management ProcessgQuantitative Analysis - Monte Carlo Simulation

140

160

85% 06/07/17

90% 07/02/17

95% 08/02/17

100% 11/24/17

Multiple ProjectsEntire Plan : Finish Date

200

85% $234,026,824

90% $238,713,928

95% $246,352,157

100% $272,345,809

Multiple ProjectsEntire Plan : Cost

100

120

s

55% 03/17/17

60% 03/30/17

65% 04/13/17

70% 04/25/17

75% 05/07/17

80% 05/23/17

Freq

uenc

y

150

s

55% $213,691,092

60% $216,886,236

65% $219,269,142

70% $222,216,311

75% $226,114,881

80% $229,852,196

Freq

uenc

y

40

60

80Hits

20% 12/31/16

25% 01/11/17

30% 01/20/17

35% 01/31/17

40% 02/12/17

45% 02/22/17

50% 03/05/17

Cum

ulat

ive

F

50

100Hits

20% $193 286 839

25% $196,953,091

30% $200,371,341

35% $202,663,343

40% $205,495,351

45% $208,265,868

50% $210,532,804

Cum

ulat

ive

F

11/10/16 07/18/17

Distribution (start of interval)

0

20

0% 08/27/16

5% 11/01/16

10% 11/27/16

15% 12/14/16

20% 12/31/16

$150,000,000 $200,000,000 $250,000,000

Distribution (start of interval)

0 0% $146,848,167

5% $178,021,244

10% $185,034,183

15% $188,797,647

20% $193,286,839

Distribution (start of interval)Distribution (start of interval)

Source: Primavera Risk Analyst

Risk Management ProcessgRisk Response Strategies

Risk Management ProcessgRisk Response Strategies

“Hope is not a Strategy”

Risk Management ProcessgAllocation

Assign Risk to those in best position to control it

Risk Management ProcessgMonitor & Control

The Big Pictureg

• Better Management of Program Contingencies• Better Management of Program Contingencies• Opportunity to Reallocate Funds• Enables Cash Flow Financial Management• Enables Cash-Flow Financial Management

Risk AnalysisRisk Analysis Workshop

Kurt LieblongKurt Lieblong

Risk Management Process Overview

Qualitative vs Quantitative Analysis?

• Risk Based Graded Approach Worksheet (total

Qualitative vs Quantitative Analysis?

• Risk Based Graded Approach Worksheet (total project cost $20 million or less)

• Risk Analysis Self Modeling Tool (total project cost• Risk Analysis Self Modeling Tool (total project cost $20 ‐ $50 million)

• Risk Analysis Workshop and Commercial RiskRisk Analysis Workshop and Commercial Risk Modeling Program (total project cost greater than $50 million)

• Consultant‐led Workshop (complex or total projects greater than $500 million)

27

Baseline Risk AssessmentBaseline Risk Assessment

• Review base cost and schedule estimate and scope• Review base cost and schedule estimate and scope• Validate base cost estimate• Develop project flowchart• Develop project flowchart• Conduct Risk Assessment Workshop to identify and quantify risk factorsquantify risk factors

• Identify or Develop Cost Escalation Factors• Develop Risk Analysis Model• Develop Risk Analysis Model• Produce Cost and Schedule Risk‐Adjusted ResultsR ki f k i k f t• Ranking of key risk factors

Cost Risk Analysis WorkshopCost Risk Analysis Workshop 

• Preparation Session with the project team to• Preparation Session with the project team to Educate, Plan, Set the stage, and Build expectation with the project team.with the project team.

• Workshop to elicit project characteristics and develop understanding, solicit inputs, develop p g, p , pranges, identify and quantify risk factors, identify opportunities, and develop mitigation strategies.

• Modeling and reporting to summarize all the project aspects in terms of risk as applied to: budget, h d l d lschedule, and management plan. 

Preparation SessionPreparation Session

• Risk Assessment Process overview• Risk Assessment Process overview

• Presentation of the project overview

• Building a flowchart diagram to serve as the backbone for the analysis

• Discuss base cost estimates

• Develop initial list of risks• Develop initial list of risks

• Assign tasks to the project team

• Set the agenda for the workshop

Risk Analysis FlowchartRisk Analysis Flowchart

Activity B

Activity A

StartEnd

Activity C

Activity D$ }

For Each Task

Flowchart – An Illustration

2008 2009 2010 2011 2012 2013 2014 2015 2016

Jan-Mar Oct-DecApr-Jun Jul-Sep Jan-Mar Oct-DecApr-Jun Jul-Sep Jan-Mar Oct-DecApr-Jun Jul-Sep Jan-Mar Oct-DecApr-Jun Jul-Sep Jan-Mar Oct-DecApr-Jun Jul-Sep Jan-Mar Oct-DecApr-Jun Jul-Sep Jan-Mar Oct-DecApr-Jun Jul-Sep Jan-Mar Oct-DecApr-Jun Jul-Sep Jan-Mar Oct-DecApr-Jun Jul-Sep

1. Publish DEIS

10. Record of Decision

15. Begin Construction

men

t Per

iod

nths

16a. Construct Columbia River Structure35 months

17b. Hayden Island Interchange

10a.

Rev

iew

to

get R

ecor

d of

D

ecis

ion

4 m

onth

s16b. Construct Columbia River

Structure 7 months

17a. Hayden Island Interchange 16 months

FF

2. D

EIS

Com

m2

mon

cal A

genc

y A

dopt

ion

2 m

onth

s

11. PS&E River Crossing18 months

12. PS&E Transit18 months

13. R/W Highway18 months

14. R/W Transit18 months

32 months

18b. SR-14 Interchange 18 months

19b. Marine Drive

Interchange

18a. SR-14 Interchange28 months

19a. Marine Drive Interchange19 months

Project Complete

4. LPA

3. L

oc

5. Prepare and Publish FEIS12 months

6 months

20. Mill Plain Interchange40 months

21. Fourth Plain Interchange43 months

22. SR-500 Interchange46 months

23 Demo Existing Interstate

SS + 43 months

28. PS&E Hayden Island18 months

29. PS&E SR-1418 months

30. PS&E Marine Drive18 months

31. PS&E Mill Plain18 months

32. PS&E Fourth Plain18 months

7. FTA New Starts Submital

6. PE – 30% Design Highway12 months

8. PE – 30% Design Transit

8 months

23. Demo Existing Interstate Bridge

10 months

24. LRT South25 months

25. LRT North22 months

FS + 2 months

Columbia River Crossing Project

26. LRT Across the River14 months

33. PS&E SR-50018 months

FS + 2 months27. LRT Burn

6 months

8 months

9. Environmental Permitting28 months

Columbia River Crossing ProjectLight Rail Transit Mill District Alignment

--Not to Scale--

Decision Point

Environmental, Permitting, Review, and Agency Adoption

Highway Activities

Transit Activities

River Crossing

Principles of the Risk Assessment k h hWorkshop Approach

ll b h• Collaborative, team approach• Look at all project costs, including design, right‐of‐way, and construction

• Define threats and opportunities individually pp y(to the extent possible)

• Provide broad flexibility to representProvide broad flexibility to represent uncertainty and correlation

• Identify risk management strategies• Identify risk management strategies

Objectives of the WorkshopsObjectives of the Workshops

• Assess the project risk to account for uncertainty ssess t e p oject s to accou t o u ce ta tysurrounding scope, cost and schedule;  

• Elicit information on the cost and schedule risks associated with the project; and 

• Full re‐baseline of cost estimates, identification of risk factors, and development of mitigation strategies.

WorkshopWorkshop

• Structured Workshops to Build Consensus AmongStructured Workshops to Build Consensus Among Various Stakeholders 

• Engagement of Internal and External Subject‐Matter g g jExperts

• Sessions by Functional Assignment to:y g– Identify Risks– Quantify Risks– Discuss Risk Response and Mitigation Strategies

Who Should Attend WorkshopWho Should Attend Workshop

• Project Manager • Disciplines j g• External Subject Matter Experts

p– Construction– Bridge & Structures

• Internal and External Stakeholders

– Environmental– Right of Way– GeotechnicalGeotechnical– Construction– Utilities– Local agencies– Others depending on project scopeproject scope

Project Team RolesProject Team Roles

• Provide Project Information:j– Project location maps, overheads, etc.– Project cost estimate and backupD i d t ti h d l fl h t– Design and construction schedule or flow chart

– Develop comprehensive list of risks, typically using starter risk list

• Workshop Support:– Provide input on risk identifying, quantification and mitigatemitigate

– Provide information on project history and key decisions as these items come up in discussion

Type of RisksType of Risks

B d t Ri k (b t t i t ) Budget Risks (base cost uncertainty) Risk that budget elements will deviate from the estimate. Examples: deviations in unit prices, deviations in quantitiesquantities.

Event Risks Risk of internal or external events that force the project team to work beyond the estimate just to meet the Projectteam to work beyond the estimate just to meet the Project Scope and SOW.

Examples: Extreme weather, contractor non‐performance.

Scope Risks Scope Risks Risk of significant changes to project scope due to external pressures.

Examples: community pressures for changes in alignment.

Quantifying Individual Risks

Risk Factor Probability of Potential Impacts

Quantifying Individual Risks

Risk Factor Probability of Occurrence

Potential Impacts

Delay of NEPAProcess 33%

CostIncrease$2M

ScheduleDelay by 12monthsProcess $

I t l IncrementalIncrementalIncrease Cost

IncrementalScheduleDelay

Overall Effect on the

Project Cost

Risk Register: Risk IdentificationRisk Register: Risk Identification

Risk Register: Risk QuantificationRisk Register: Risk Quantification

Modeling and PresentationModeling and Presentation

• Within or following the workshop preliminaryWithin or following the workshop, preliminary results are generated

• Results are presented to the project team forResults are presented to the project team for feedback and review

• Results are finalized and include risk based cost• Results are finalized and include risk based cost and schedule estimates, ranking of key drivers of risks and detailed information on each risk factorrisks and detailed information on each risk factor

• Results are used by the project team to develop a risk management planrisk management plan

Baseline Risk Assessment ResultsBaseline Risk Assessment Results

100%

$674.4

$360.7

$452.1

80%

90%$650.0

60%

70%

ot Exceeding Contingency

$650.0 ‐ $605.3 = $44.7

$605.3

30%

40%

50%

Prob

ability of N

Alternative 1 ‐ Risk‐Based Total Cost (Pre‐Response)

$533.210%

20%

30%P

Alternative 1 ‐ Base Cost Estimate (mean value, 2010 $)

Alternative 1 ‐ Base Cost Estimate (mean value escalated)

0%

$250.0 $350.0 $450.0 $550.0 $650.0 $750.0

Project Cost, Millions of Dollars

(mean value, escalated)

Baseline Risk Assessment ResultsBaseline Risk Assessment Results

$51.0ENV 20.03a1 ‐ Determination of direct impacts  to wetlands ‐ Alt 1

$3.8

$25.5

$

CNS 30.01 ‐ Excavation  impacts during construction due to weather

ENV 20.04a1 ‐ Determination  of indirect impacts  to wetlands  ‐ Alt 1

$2.3

$2.3

$3.8

ENV 60.06a1 ‐ Development of mitigation  plan to offset  impacts to bli l d Alt 1

STG 10.01 ‐ Design Changes on Bridge or Overpass

ENV 10.01a1 ‐ Determination  of Significance Requiring EIS ‐ Alt 1

$1.7

$1.9

$

RR 20 .01 ‐ Cost for Railroad Flaggers

ENV 80.01 ‐ New Storm water Rule ‐Water quantity and quality issues

public lands ‐ Alt 1

$1.4

$1.5

$0.00 $10.00 $20.00 $30.00 $40.00 $50.00 $60.00

MGT 900.03 ‐ Loss of Toll Revenue due to complex MOT

ENV 30.01a12 ‐ Expected Controversy on Environmental Grounds ‐ Alt 1/2

$0.00 $10.00 $20.00 $30.00 $40.00 $50.00 $60.00

Expected Value Cost Impact ($ millions)

Based on Risks that Impact Alternative 1 ActivitiesAlternative 1 ‐ Cost EV ($M) (Pre‐Response)

Comparison of Risk Based Costs

100%

Comparison of Risk Based Costs

$5,747$3,520$3,379

$2,291

$2,932

80%

90%

100%

g 1

$4,443

$4,641

$3,041

$3,129

$2,902

$2,992

50%

60%

70%

of Not Exceeding

Risk‐Based Total Project Cost, 2010 Analysis

2

20%

30%

40%

Prob

ability o

Risk‐Based Total Project Cost, 2011 Update

Risk‐Based Total Project Cost, 2011 Update (With Opportunities)

Non‐Escalated Total Project Base Cost Estimate,

$3,626$2,563$2,419

0%

10%

20%

$1,800 $2,800 $3,800 $4,800 $5,800 $6,800 $7,800

Non Escalated Total Project Base Cost Estimate, 2011 Update

Escalated Total Project Base Cost Estimate, 2011 Update

Project Cost, Millions of Dollars

Workshop DeliverablesWorkshop Deliverables

• Final report detailing the results of theFinal report detailing the results of the workshop

• Final Risk Register for Project Manager to use• Final Risk Register for Project Manager to use managing the identified risks

References

• Project Management Handbook Chapter 19

References

• Project Management Handbook  Chapter 19http://www.dot.state.fl.us/projectmanagementoffice/PMHandbook/pmhandbookindex.shtm

• Washington State Department of Transportationhttp://www.wsdot.wa.gov/Projects/ProjectMgmt/RiskAssessment/

• FHWA Risk Assessmenthttp://international.fhwa.dot.gov/riskassess/index.cfmhttp://international.fhwa.dot.gov/riskassess/index.cfmhttp://www.fhwa.dot.gov/ipd/project_delivery/resources/risk_management/

Risk AnalysisProject Manager Roles

Rob QuigleyRob Quigley

ObjectivesObjectives

• Understand how the Risk Management Plan fits ginto the overall Project Management Plan

• Describe Project Manager’s Roles in Risk Analysis and Management for the life of project

Ri k R S i– Risk Response Strategies– Risk Tracking

• Integrate Risk Management into regular project delivery activities…consistently applied ondelivery activities…consistently applied on every project ‐ CPR

Risk Management within the O ll P j t M t PlOverall Project Management Plan

ProjectSchedule

CostProject

Project

CostControlScope

ProjectManagement

Plan

ProjectProcurement

ProjectQA‐QC

ProjectProject

Staffing (HR)Risk

ManagementCommuni‐cations

Management

Risk ManagementRisk Management

INPUTS TOOLS & TECHNIQUES OUTPUTS

1. Project Scope2. Cost Management 

Plan3. Schedule 

M t Pl

1. Planning Meetings2. Risk Workshop3. Risk Analysis

1. Risk Analysis Results2. Risk Management Plan

Management Plan4. Communications Plan5. Enterprise 

Environmental Factors6. Organizational 

Process Assets

Risk Management Plan – Detailed Fl DiFlow Diagram

Perform Risk Analysis

Pl

IdentifyRisks

PlanRisk 

ResponsesProjectRisk

ManagementPlan

Allocate RisksMonitor &ControlRisksRisks

Goal of Risk Managementg

• Risk Assessment’s aim is to assess potential impact of various scope, event, and budget risks on the project’s

ImpactInitial Risk

budget risks on the project s cost and schedule.

• Risk Management’s aim is to identify opportunities and mitigation strategies to

Managed Riskmitigation strategies to reduce both the likelihood of an event occurrence and 

Probability of Occurrence

the potential effect if it occurs. 

Managing Potential OutcomesManaging Potential Outcomes

Highest possibleTotal Project Cost Estimate

SignificantRisks Realized

Cost

Few RisksRealized

CostRange

Lowest possibleTotal Project Cost Estimate

Project Delivery Lifecycle

Planning Scoping Design Letting

Needs & Management FundamentalsNeeds & Management Fundamentals

What People Need To Know Triple Constraints

1. What are we getting?

2. How long will it take?

1. Prioritize

2. Optimize3. What’s it going to

cost?

2. Optimize

3. Accept

WHAT ?

Risk ConstraintsRisk Constraints 

SCOPEWhen one side changes, 

the other two are inevitably affected

SCOPE

SCOPE are inevitably affected

SCOPE SCOPE

Risk Management Process O iOverview

Addressing Cost and Schedule CConcerns

• How much will it cost?• How much will it cost?• How long will it take?• Why does it cost that much?

Usual Questions

• Why does it take that long?

• Risk Identification• Qualitative and Quantitative

Risk Analysis• Mitigation Strategy• Risk Monitoring & Control

Analysis Needs g

Risk RegisterRisk Register

• IdentifyIdentify• Quantify

i i• Mitigate• Tracking, Monitoring, and Control 

– Adequate & Continuous Reporting

Risk Management Process O iOverview

Step 2: Develop Risk Response Strategies

Other 7%

Strategies• Avoidance is a change to the project

Utilities 3%

Geotechnical 3%

Avoidance is a change to the project scope to eliminate the impact of a risk.

• Transference of a risk to another Construction 26%

Traffic 7%

Market Conditions 5%

$277.0 M Expected

party who is more capable at handling the risk (such as the contractor or insurance company). Mitigation is seeking to lessen the

Design 19% Right of Way 22%

Hazardous Waste 8%

Expected Value Risk• Mitigation is seeking to lessen the

impact of a specific risk items, which may involve the consumption of additional time pand/or money.

• Acceptance is recognition by the project team of a specific risk and d i i t t t k ti t d l decision to not take action to deal with the risk.

Risk Strategies ‐ AvoidRisk Strategies  Avoid

• Some threats can be avoided entirely. This can be      So e t eats ca be a o ded e t e y. s ca bedone by changing the way the project is performed or by de‐scoping the portion of the 

h h k lproject that contains the risk element. • This will often have a cost. Completing the job d i i k f i t i lik l t tdone in a risk free environment is likely to cost more. 

• Eliminating the risky scope might disappoint a• Eliminating the risky scope might disappoint a critical stakeholder or degrade the business reason for performing the project.p g p j

Risk Strategies ‐ TransferRisk Strategies  Transfer

• This involves moving the responsibility for a risk g p yto another party usually by payment of a fee (outsourcing  to a skilled expert or fixed price construction contracts) or a premiumconstruction contracts) or a premium (insurance).

• Transferring risk will almost always have an g yadded cost. Some risk, such as schedule risk, cannot be transferred.  Even though the owner can contract (transfer) the schedulecan contract (transfer) the schedule responsibility to third parties, if they are late, the project is still late.

Risk Strategies ‐MitigateRisk Strategies  Mitigate

• This involves taking positive actions to reduce s o es ta g pos t e act o s to educeeither the impact of a threat or the probability of it occurring. 

• Mitigation usually requires positive action and has a cost. These actions should be reflected in 

j t k k d t ll d likproject work packages and controlled like any other part of the project. They will affect your budget and schedule.budget and schedule. 

• Mitigation can be a very effective strategy. It’s often better than a ‘do nothing’ approach.g pp

Risk Strategies ‐ AcceptRisk Strategies  Accept

• After trying to avoid, transfer, or mitigate the y g , , gthreats to the project, residual risk may remain ‐threats that can’t be reduced further

In active acceptance the project cost is revised to take– In active acceptance, the project cost is revised to take the residual expected value of the remaining risk

– Passive acceptance involves acknowledging the risk d i f d th j t ith tand moving forward on the project without reserves, 

which may make sense for risks with small expected values

f f– The third form of risk acceptance is called denial and professional risk management seeks to reduce the use of denial as a strategy

Response PlanningResponse Planning

• Risk Response Plan – A plan of action designed to           p p greduce the impact once a risk event has occurred

– Planning – Prior to the risk event occurring as though it g g gwill occur 

– Trigger – Identifies that the risk event has occurred and tifi th t t i l t th i k lnotifies the team to implement the risk response plan

– Implementation – Actions to take after the risk event has occurredoccu ed

Risk Management Process Overview

Step 3: Risk Analysis on Risk ResponseStep 3: Risk Analysis on Risk Response

$45 90$51.00ENV 20.03a1 ‐ Determination of direct impacts  to wetlands  ‐ Alt 1

$2.34

$3.80

$3.83

$22.95

$45.90

$2.34

$3.80

$3.83

$25.50

STG 10.01 ‐ Design Changes on Bridge or Overpass

ENV 10.01a1 ‐ Determination of Significance Requiring EIS  ‐ Alt 1

CNS 30.01 ‐ Excavation  impacts during construction due to weather

ENV 20.04a1 ‐ Determination  of indirect impacts  to wetlands  ‐ Alt 1

p

100%

$0.90

$2.00

$1.88

$2.25

$1.50

$1.70

$1.88

$2.25

ENV 30.01a12 ‐ Expected Controversy on Environmental Grounds  ‐ Alt 1/2

RR 20 .01 ‐ Cost for Railroad Flaggers

ENV 80.01 ‐ New Storm water Rule ‐Water quantity and quality issues

ENV 60.06a1 ‐ Development of mitigation plan to offset  impacts to public lands ‐ Alt 1 $674$662

70%

80%

90%

eeding

$1.43$1.43

$0.00 $10.00 $20.00 $30.00 $40.00 $50.00 $60.00

MGT 900.03 ‐ Loss of Toll Revenue due to complex MOT

Expected Value Cost Impact ($ millions)

Alternative 1 ‐ Cost EV ($M) (Pre‐Response) Alternative 1 ‐ Cost EV ($M) Post‐Response)

$605$594

30%

40%

50%

60%Prob

ability of N

ot Exce

Alternative 1 ‐ Risk‐Based Total Cost 

$533$522

0%

10%

20%

30%P (Pre‐Response)

Alternative 1 ‐ Risk‐Based Total Cost (Post‐Response)

$420.0 $470.0 $520.0 $570.0 $620.0 $670.0 $720.0 $770.0

Project Cost, Millions of Dollars

Risk Management Process O iOverview

Step 4: Tracking, Monitoring and Control

• Development of Risk Management Plan involves:Development of Risk Management Plan involves:– Identifying Risk Owners to take responsibility for key risk factors and associated risk response strategiesrisk factors and associated risk response strategies

– Identifying the Monitoring Frequency for risk updates and feedback on the effectiveness of risk response pstrategies

– Updates to the risk assessment model and results at pkey milestones and when baseline cost and schedules are updated

– Continuous updates to Risk Management Plan that document and report progress 

Monitoring and Controlg

• Identify the action to be taken Risk Response Plan Monitoring and Control

(Response Plan) and review frequency

• Identify the owner of the riskegy Action To Be Taken

( ti i l di d t d

wne

r

Risk R i

Date, Status and Review Comments (t h th hi t f i k’ it i

y– Who is responsible for 

monitoring?– The Task Manager assigned to

Stra

te (response actions including advantages and disadvantages. Specify the time frame)

Ris

k O Review

Dates (to show the history of risk’s monitoring

do not delete previous comments)

The Task Manager, assigned to the risk, reports periodically to the Project Manager on the effectiveness of the plan,  o.

mgr

-Jan

-2

p ,unintended consequences, and makes suggestions on mid‐course corrections to 

Miti

gatio

n Finalize design to identify all wetlands that are impacted. Early coordination with the outside agencies to determine mitigation

ratio eade

r/Env

iro

-2

2

008-

As of Nov. 15, 2008 there are only two potential areas where there could be

additional wetland impacts. As of Dec. 2, 2008 agency has initially determined that

further mitigate the riskM ratio.

Des

ign

Le

2008

-Dec

- mitigation ration would be 4:1.

Risk Management Plan D t il d Fl DiDetailed Flow Diagram

Perform Risk Analysis

Pl

IdentifyRisks

PlanRisk 

ResponsesProjectRisk

ManagementPlan

Allocate RisksMonitor &ControlRisksRisks

Risk Management

What’s the Ret rn?

Risk Management

What’s the Return?

•Helps manage expectations for budget and scheduleHelps manage expectations for budget and schedule

•Improved Communication between stakeholders

•Risk management shown to 

–decrease 90% of project problems (1) anddecrease 90% of project problems  and 

–generate 5% cost savings (2)

Source: FHWA Risk Management Workshop course materials, Golder Associates Inc. & Dr. Keith Molenaar, October 9, 2007; attributed to (1) Project Management Institute, and (2) Construction Management Institute

Summaryy

• Risk Analysis Process– Terms– Process– Big Picture

• Risk Analysis Workshop– Assessment– Workshops

• Project Manager Roles– Risk Management Plan– Risk response strategies– Assessment– Risk Tracking– Risk Tracking

Questions?Q

Risk Analysis Process OverviewGreg Davis, PEState Estimates [email protected] 414 4170850-414-4170

Risk Analysis WorkshopKurt Lieblong, PE, CVSState Project Review [email protected]

Project Manager ResponsibilitiesRob Quigley, PEState Project Management [email protected]